Upload
buidiep
View
216
Download
1
Embed Size (px)
Citation preview
Order on
Approval of Business Plan and Multi
Year Tariff Petition
For
Uttarakhand Power Corporation Ltd. for
Second Control Period
(FY 2016-17 to FY 2018-19)
April 5, 2016
UTTARAKHAND ELECTRICITY REGULATORY COMMISSION Vidyut Niyamak Bhawan,
Near I.S.B.T., P.O. Majra, Dehradun – 248171
i
Table of Contents
1. Background and Procedural History ............................................................................................. 5
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and
Commission’s Views ....................................................................................................................... 9
2.1 General ...................................................................................................................................... 9
2.1.1 Compliance to Regulations/Directions of Commission ......................................................... 9
2.2 Overall Tariff Increase ........................................................................................................... 10
2.3 Domestic Tariff ....................................................................................................................... 12
2.3.1 Tariff Hike ................................................................................................................................ 12
2.3.2 Fixed Charges based on Load ................................................................................................. 13
2.4 Non-Domestic Tariff .............................................................................................................. 14
2.4.1 Tariff Hike ................................................................................................................................ 14
2.4.2 Tariff for Dharamshala/Trust/Ashram ................................................................................. 15
2.4.3 Tariff for Telecom Tower......................................................................................................... 16
2.5 Independent Advertising Hoardings ..................................................................................... 17
2.6 Agricultural Tariff .................................................................................................................. 17
2.6.1 Tariff Increase .......................................................................................................................... 17
2.6.2 Floriculture ............................................................................................................................... 18
2.7 Mixed Load (RTS-8) Tariff ..................................................................................................... 19
2.8 Industrial Tariff ...................................................................................................................... 20
2.8.1 Tariff Hike ................................................................................................................................ 20
2.8.2 Rebate in Demand Charges for non-supply of power........................................................... 21
2.8.3 Textile Industry ........................................................................................................................ 21
2.8.4 Fixed/Demand Charge and Energy Charge .......................................................................... 22
2.8.5 Time of Day Tariff.................................................................................................................... 24
2.8.6 Rostering and Load Shedding ................................................................................................ 26
2.8.7 Load Factor based Tariff.......................................................................................................... 28
2.9 Railway Traction ................................................................................................................... 31
2.10 Fixed Charges .......................................................................................................................... 34
2.11 Minimum Consumption Guarantee (MCG) .......................................................................... 35
2.12 Delayed Payment Surcharge (DPS) ....................................................................................... 37
2.13 Rebate and Incentives ............................................................................................................ 38
ii
2.14 Energy Sale Forecast ...............................................................................................................42
2.15 Cost of Supply and Cross Subsidy.........................................................................................43
2.16 Continuous Supply .................................................................................................................45
2.17 Components on ARR and Revenue ........................................................................................46
2.17.1 Power Purchase Cost ................................................................................................................ 46
2.17.2 PGCIL Charges ......................................................................................................................... 48
2.17.3 Return on Equity ...................................................................................................................... 49
2.17.4 Operation & Maintenance Expenses ....................................................................................... 50
2.17.5 Depreciation .............................................................................................................................. 51
2.17.6 Provision for Bad and Doubtful Debts .................................................................................... 52
2.17.7 Other Costs ............................................................................................................................... 53
2.17.8 Consumer Security Deposit ..................................................................................................... 54
2.18 Capital Expenditure ................................................................................................................56
2.19 Truing-up for Past Years ........................................................................................................58
2.20 Departmental Employees .......................................................................................................59
2.21 Collection Efficiency ...............................................................................................................60
2.22 Fuel Charge Adjustment .........................................................................................................61
2.23 Metering and Billing ...............................................................................................................62
2.24 Load Reduction .......................................................................................................................65
2.25 Distribution Line/ Line Losses...............................................................................................65
2.26 Distribution Infrastructure ....................................................................................................69
2.27 KCC Data ................................................................................................................................70
2.28 Quality of Power ....................................................................................................................71
2.29 Open Access .............................................................................................................................71
2.30 Green Cess and Electricity Duty for Open Access Consumers ............................................74
2.31 Renewable Energy Promotion ...............................................................................................75
2.32 Miscellaneous Comments .......................................................................................................76
2.32.1 LED Lamps ............................................................................................................................... 76
2.32.2 Payment of Public Lamp connections ..................................................................................... 76
2.32.3 Temporary Connections ........................................................................................................... 77
2.32.4 Location of Installation of meters ............................................................................................ 77
2.32.5 Load Shedding .......................................................................................................................... 78
2.32.6 Transfer of Petitioner’s personnel............................................................................................ 78
iii
2.32.7 Departmental employees ........................................................................................................ 79
2.32.8 Safety Requirements ................................................................................................................ 79
2.33 Views of Advisory Committee Meeting ................................................................................ 80
3. Petitioners’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business
Plan for the second Control Period ............................................................................................. 82
3.1 Statutory Requirement ........................................................................................................... 82
3.2 Multi Year Tariff Framework ................................................................................................ 82
3.3 Business Plan for the second Control Period ....................................................................... 83
3.4 Sales Forecast ......................................................................................................................... 90
3.4.1 Domestic (RTS-1) ..................................................................................................................... 97
3.4.2 Non-Domestic (RTS-2) ............................................................................................................. 97
3.4.3 Public Lamps (RTS-3) .............................................................................................................. 97
3.4.4 Private Tube-Wells (RTS-4) ..................................................................................................... 98
3.4.5 Government Irrigation Systems (RTS-5) ................................................................................ 98
3.4.6 Public Water Works (RTS-6) ................................................................................................... 98
3.4.7 Industry (RTS-7)....................................................................................................................... 99
3.4.8 Mixed Load (RTS-8) ................................................................................................................. 99
3.4.9 Railway Traction (RTS-9) ....................................................................................................... 100
3.5 Efficiency Parameters........................................................................................................... 101
3.5.1 Distribution Losses ................................................................................................................. 101
3.5.2 Collection Efficiency ............................................................................................................... 107
3.6 Power Procurement Plan ..................................................................................................... 109
3.6.1 Power Purchase from UJVN Ltd. ........................................................................................... 112
3.6.2 Power Purchase from NHPC Ltd. ......................................................................................... 114
3.6.3 Power Purchase from THDC India Ltd. ................................................................................ 115
3.6.4 Power Purchase from NTPC Ltd. .......................................................................................... 115
3.6.5 Power Purchase from SJVN Ltd............................................................................................. 117
3.6.6 Power Purchase from existing Renewable Energy Sources ................................................. 117
3.6.7 Power Purchase from Vishnu Prayag HEP (State Royalty Power) ..................................... 118
3.6.8 Power Purchase from Sasan UMPP ....................................................................................... 118
3.6.9 Power purchase from Kashipur CCPP .................................................................................. 118
3.6.10 Power purchase from Greenko Budhil Hyrdo ...................................................................... 119
3.6.11 Power purchase from upcoming generating stations........................................................... 119
3.6.12 Energy available from Firm Sources...................................................................................... 120
iv
3.6.13 Power Purchase for fulfilling RPO ........................................................................................ 120
3.6.14 Return of banked power during FY 2016-17 ......................................................................... 121
3.6.15 Deficit/ (Surplus) energy ....................................................................................................... 121
3.7 Capital Expenditure Plan and Capitalisation Plan .......................................................... 122
3.8 Financing Plan ...................................................................................................................... 126
3.9 Human Resources Plan......................................................................................................... 127
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up
for FY 2014-15 ............................................................................................................................... 130
4.1 Truing-up for FY 2014-15 ...................................................................................................... 130
4.1.1 Sales ......................................................................................................................................... 131
4.1.2 Distribution Losses ................................................................................................................. 140
4.1.3 Power Purchase Expenses (Including Transmission Charges) ............................................ 142
4.1.4 Operation and Maintenance (O&M) Expenses ..................................................................... 147
4.2 Cost of Assets & Financing .................................................................................................. 152
4.2.1 Capital cost of Original Assets ............................................................................................... 152
4.2.2 Depreciation ............................................................................................................................ 159
4.2.3 Provision for Bad & Doubtful Debts ..................................................................................... 160
4.2.4 Interest on Working Capital (IoWC) ..................................................................................... 164
4.2.5 Return on Equity .................................................................................................................... 164
4.2.6 Non-Tariff Income .................................................................................................................. 166
4.3 Tariff Revenue ....................................................................................................................... 167
4.4 Sharing of gains and losses .................................................................................................. 171
4.5 ARR & Revenue for FY 2014-15 ........................................................................................... 173
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT
Period for second Control Period............................................................................................... 175
5.1 Background ............................................................................................................................ 175
5.2 Sales ....................................................................................................................................... 175
5.3 Distribution Loss Trajectory ............................................................................................... 176
5.4 Aggregate Revenue Requirement ......................................................................................... 177
5.5 Power Purchase Cost ............................................................................................................ 178
5.5.1 Merit Order ............................................................................................................................. 179
5.5.2 Cost of power purchase.......................................................................................................... 179
5.6 Transmission Charges .......................................................................................................... 185
v
5.6.1 Inter-State Transmission Charges payable to PGCIL ........................................................... 185
5.6.2 Intra-State Transmission Charges payable to PTCUL .......................................................... 186
5.6.3 Transmission Charges ............................................................................................................ 186
5.7 SLDC Charges ....................................................................................................................... 186
5.8 Water Tax .............................................................................................................................. 186
5.9 GFA and Additional Capitalisation ................................................................................... 187
5.9.1 GFA base for FY 2015-16 ........................................................................................................ 187
5.9.2 Capitalisation during the second Control Period ................................................................. 188
5.10 Means of Finance .................................................................................................................. 188
5.11 Interest and Finance Charges ............................................................................................... 189
5.11.1 Depreciation ............................................................................................................................ 191
5.11.2 Operation and Maintenance expenses................................................................................... 193
5.11.3 Employee expenses ................................................................................................................. 195
5.11.4 R&M expenses ........................................................................................................................ 197
5.11.5 A&G expenses ......................................................................................................................... 198
5.11.6 O&M expenses ........................................................................................................................ 200
5.11.7 Interest on Working Capital ................................................................................................... 200
5.11.8 One Month O&M Expenses ................................................................................................... 201
5.11.9 Maintenance Spares ................................................................................................................ 201
5.11.10 Receivables .............................................................................................................................. 201
5.11.11 Capital required to finance shortfall in collection of current dues ...................................... 201
5.11.12 Adjustment for security deposits and credit by power suppliers ....................................... 202
5.11.13 Return on Equity ..................................................................................................................... 203
5.11.14 Income Tax .............................................................................................................................. 204
5.11.15 Provision for Bad and doubtful debts ................................................................................... 205
5.11.16 Non-Tariff Income .................................................................................................................. 206
5.11.17 Past year adjustments ............................................................................................................. 206
5.11.18 Treatment of past year adjustments ...................................................................................... 209
5.11.19 Revenue Requirement for FY 2016-17 ................................................................................... 210
5.11.20 Revenue at Existing Tariff ...................................................................................................... 211
5.11.21 Revenue Gap for FY 2016-17 at existing Tariff...................................................................... 211
6. Tariff Rationalisation, Tariff Design and Related Issues....................................................... 213
6.1 Discontinuation of Additional Surcharge on account of Re-Determination of Tariff for
FY 2010-11 from FY 2016-17 onwards .......................................................................................... 213
vi
6.2 Tariff Rationalisation and Tariff Design for FY 2016-17 .................................................. 214
6.2.1 General .................................................................................................................................... 214
6.2.2 Petitioner’s Proposals ............................................................................................................. 214
6.2.3 Commission’s Views on Tariff Rationalisation Measures ................................................... 218
6.2.4 kVAh Tariffs ........................................................................................................................... 236
6.2.5 Treatment of Revenue Gap .................................................................................................... 237
6.2.6 Cross Subsidy ......................................................................................................................... 238
6.2.7 Category-wise Tariff Design .................................................................................................. 238
6.2.8 RTS-2: Non-Domestic Tariff ................................................................................................... 240
6.2.9 RTS-3: Public Lamps............................................................................................................... 242
6.2.10 RTS-4: Private Tube Wells/Pump Sets and Agriculture Allied Activities.......................... 242
6.2.11 RTS-5: Government Irrigation System .................................................................................. 243
6.2.12 RTS-6: Public Water Works .................................................................................................... 243
6.2.13 RTS-7: Industry ....................................................................................................................... 243
6.2.14 RTS-8: Mixed Load ................................................................................................................. 245
6.2.15 RTS-9: Railway Traction ......................................................................................................... 245
6.3 Revenue for FY 2016-17 ......................................................................................................... 246
6.4 Cross Subsidy ........................................................................................................................ 247
6.5 Open Access Charges ............................................................................................................ 249
7. Review of Commercial Performance of UPCL ......................................................................... 251
7.1 General ................................................................................................................................... 251
7.1.1 Consumer Mix during FY 2013-14 & FY 2014-15 .................................................................. 252
7.1.2 Consumption Pattern during FY 2013-14 & FY 2014-15....................................................... 254
7.1.3 Revenue Pattern during FY 2013-14 & FY 2014-15 ............................................................... 255
7.2 Commission’s Analysis and Directions on Commercial Performance ............................. 256
7.2.1 Metering .................................................................................................................................. 258
7.2.2 Billing ...................................................................................................................................... 265
7.2.3 Billing and Bill Collection System ......................................................................................... 270
7.3 Energy Audit .......................................................................................................................... 273
7.4 AT&C Losses ......................................................................................................................... 273
7.5 Conclusion ............................................................................................................................. 277
8. Commission’s Directives ............................................................................................................ 279
8.1 Compliance to the Directives Issued in Tariff Order for FY 2015-16 dated April 11, 2015279
8.1.1 Performance Report ................................................................................................................ 279
vii
8.1.2 Sales ......................................................................................................................................... 280
8.1.3 Load Shedding ........................................................................................................................ 282
8.1.4 AT&C Losses ........................................................................................................................... 283
8.1.5 Power Purchase Quantum and Cost ..................................................................................... 284
8.1.6 Fixed Assets Register .............................................................................................................. 285
8.1.7 Depreciation ............................................................................................................................ 285
8.1.8 Return on Equity ..................................................................................................................... 286
8.1.9 Employee Expenses ................................................................................................................ 286
8.1.10 Bad & Doubtful Debts ............................................................................................................ 287
8.1.11 Reliability Indices ................................................................................................................... 288
8.1.12 Voltage wise Cost of Supply .................................................................................................. 288
8.1.13 Demand Side Management Measures ................................................................................... 289
8.1.14 Electrical Accidents ................................................................................................................. 290
8.1.15 Issues raised by the Petitioner again despite Commission’s ruling in previous Tariff
Orders ...................................................................................................................................... 290
8.1.16 Additional Surcharge on account of Re-determination of Tariff for FY 2009-10 and FY
2010-11 ..................................................................................................................................... 291
8.1.17 Load Shedding ........................................................................................................................ 291
8.1.18 Metering of unmetered connections ...................................................................................... 291
8.1.19 Interest on GPF Trust.............................................................................................................. 292
8.1.20 Treatment of Assets sent for repairs ...................................................................................... 292
8.1.21 Billing of Departmental Employees ....................................................................................... 293
8.1.22 Subsidy from GoU for disaster affected areas ...................................................................... 294
8.1.23 Capitalization of Assets .......................................................................................................... 294
8.1.24 Installation of Meter ............................................................................................................... 294
8.1.25 MCG Charges .......................................................................................................................... 295
8.1.26 Issue of Voltage wise Loss ...................................................................................................... 295
8.1.27 Power Purchase Expenses (Including Transmission Charges) ............................................ 296
8.1.28 Cost of Deficit Power .............................................................................................................. 296
8.1.29 RTS-4 (Private Tubewells) ...................................................................................................... 297
8.1.30 Status of NA/NR, IDF/ADF/RDF ........................................................................................ 298
8.1.31 Replacement of Improper, Non-Functional, Stop/Stuck up defective or IDF Meters ....... 298
8.1.32 Replacement of Mechanical Meters ....................................................................................... 299
8.1.33 Ghost/Fictitious Consumers .................................................................................................. 299
8.1.34 NB & SB Cases ........................................................................................................................ 300
viii
8.1.35 Outstanding Arrears............................................................................................................... 300
8.1.36 Status of KCC Consumers ...................................................................................................... 301
8.1.37 Status of Revenue realisation per unit sold .......................................................................... 302
8.1.38 Billing and Collection System ................................................................................................ 302
8.1.39 Energy Audit .......................................................................................................................... 303
8.1.40 Abnormal Sales in Public Lamps Category .......................................................................... 304
8.1.41 Abnormal Sales in Private Tubewell Category ..................................................................... 304
8.1.42 Abnormal Sales in Public Water Works Category................................................................ 304
8.1.43 Abnormal Sales in LT Industries ........................................................................................... 305
8.1.44 Abnormal Sales in HT industries (Upto 1000 kVA) ............................................................. 305
8.1.45 Abnormal Sales in Mixed Load Category ............................................................................. 306
8.1.46 Transfer of Distribution Business from UJVN Ltd. to UPCL (Reference Para 7.2.22 of Tariff
Order dated 10.04.2014) ......................................................................................................... 306
8.2 Fresh Directives..................................................................................................................... 307
8.2.1 Departmental Employees ....................................................................................................... 307
8.2.2 Metering & Billing .................................................................................................................. 307
8.2.3 Distribution Infrastructure ..................................................................................................... 307
8.2.4 Quality of Power ..................................................................................................................... 308
8.2.5 Temporary Connections ......................................................................................................... 308
8.2.6 Location of Installation of meters .......................................................................................... 308
8.2.7 Load Shedding ........................................................................................................................ 308
8.2.8 Transfer of Petitioner’s personnel.......................................................................................... 308
8.2.9 Water Tax ................................................................................................................................ 309
8.2.10 Prepaid Metering .................................................................................................................... 309
8.2.11 kVAh Tariffs ........................................................................................................................... 309
8.2.12 Open Access Charges ............................................................................................................. 309
8.2.13 Power procurement plan ....................................................................................................... 309
8.3 Conclusion ............................................................................................................................. 310
9. Annexures ..................................................................................................................................... 311
9.1 Annexure 1: Rate Schedule Effective from 01.04.2016......................................................... 311
9.2 Annexure 2: Schedule of Miscellaneous Charges ................................................................ 337
9.3 Annexure 3: Public Notice .................................................................................................... 338
Annexure 4: List of Respondents .................................................................................................. 341
9.4 Annexure 5: List of Participants in Public Hearings ......................................................... 343
ix
List of Tables
Table 1.1: Publication of Notice ................................................................................................................. 6
Table 1.2: Schedule of Hearing .................................................................................................................. 6
Table 2.1: Summary of Total Gap as submitted by the Petitioner ........................................................ 11
Table 2.2: Cost of Power as submitted by the Petitioner ....................................................................... 11
Table 2.3: Load Shedding Priority decided by UPCL ............................................................................ 27
Table 2.4: Delayed Payment Surcharge applicable in Other States ...................................................... 38
Table 2.5: Existing and Proposed Levels of Cross-subsidy submitted by UPCL ................................. 44
Table 3.1: Actual consumer category wise sales for FY 2010-11 to FY 2014-15 (MU) .......................... 90
Table 3.2: Projected sales as per 18th EPS forecast (MU) ........................................................................ 90
Table 3.3: Computed CAGR of sales as submitted by the Petitioner.................................................... 91
Table 3.4: Consumer Category wise sales projected by the Petitioner for FY 2016-17 to FY 2018-19
(MU) ................................................................................................................................................... 92
Table 3.5: Month wise and Consumer Category wise sales projected by the Petitioner for FY 2016-17
(MU) ................................................................................................................................................... 93
Table 3.6: Month wise and Consumer Category wise sales projected by the Petitioner for FY 2017-18
(MU) ................................................................................................................................................... 94
Table 3.7: Month wise and Consumer Category wise sales projected by the Petitioner for FY 2018-19
(MU) ................................................................................................................................................... 94
Table 3.8: Consumer Category wise connected load projected by the Petitioner for FY 2016-17 to FY
2018-19 (kW) ...................................................................................................................................... 95
Table 3.9: Consumer Category wise number of consumers projected by the Petitioner for FY 2016-17
to FY 2018-19 (No.)............................................................................................................................ 96
Table 3.10: Category Wise Sales Projections for second Control Period (MU) .................................. 100
Table 3.11: Year wise distribution losses as submitted by the Petitioner ........................................... 101
Table 3.12: Distribution Loss trajectory proposed by the Petitioner for FY 2016-17 to FY 2018-19 .. 102
Table 3.13: Distribution Losses for FY 2013-14 to FY 2015-16 ............................................................. 102
Table 3.14: Distribution Losses for FY 2016-17 to FY 2018-19 ............................................................. 106
Table 3.15: Energy Input requirement approved by the Commission for the second Control Period
from FY 2016-17 to FY 2018-19 ....................................................................................................... 107
x
Table 3.16: Collection efficiency trajectory proposed by the Petitioner for FY 2016-17 to FY 2018-19
.......................................................................................................................................................... 108
Table 3.17: Collection efficiency for FY 2013-14 to FY 2015-16 ........................................................... 108
Table 3.18: Collection efficiency for FY 2016-17 to FY 2018-19 ........................................................... 108
Table 3.19: Power Purchase from UJVN Ltd......................................................................................... 113
Table 3.20: Energy Availability from UJVN Ltd. For FY 2016-17 to FY 2018-19(MU) ....................... 113
Table 3.21: Power Purchase from NHPC Ltd. ...................................................................................... 114
Table 3.22: Energy Availability from NHPC Ltd. for FY 2016-17 to FY 2018-19 (MU) ...................... 114
Table 3.23: Power Purchase from THDC India Ltd. ............................................................................. 115
Table 3.24: Energy Availability at State periphery from THDC Ltd. for FY 2016-17 to FY 2018-19
(MU) ................................................................................................................................................. 115
Table 3.25: Power Purchase from NTPC Ltd. ....................................................................................... 116
Table 3.26: Energy Availability from NTPC Ltd. at State periphery for FY 2016-17 to FY 2018-19
(MU) ................................................................................................................................................. 116
Table 3.27: Power Purchase from SJVN Ltd.......................................................................................... 117
Table 3.28: Energy Availability from SJVN Ltd. at State periphery for FY 2016-17 to FY 2018-19
(MU) ................................................................................................................................................. 117
Table 3.29: Energy Availability from existing Renewable Energy Sources for FY 2016-17 to FY 2018-
19 (MU) ............................................................................................................................................ 117
Table 3.30: Energy Availability from Vishnu Prayag HEP at State Periphery (State Royalty Power)
for FY 2016-17 to FY 2018-19 (MU) ................................................................................................ 118
Table 3.31: Energy Availability from Sasan UMPP at State periphery for FY 2016-17 to FY 2018-
19(MU) ............................................................................................................................................. 118
Table 3.32: Energy Availability from Kashipur CCPP at State periphery for FY 2016-17 to FY 2018-19
(MU) ................................................................................................................................................. 119
Table 3.33: Energy Availability from Greenko Budhil Hydro at State periphery for FY 2016-17 to FY
2018-19 (MU) ................................................................................................................................... 119
Table 3.34: Energy Availability from upcoming generating stations at State periphery for FY 2016-17
to FY 2018-19(MU) .......................................................................................................................... 120
Table 3.35: Energy available from Long Term Sources (MU) .............................................................. 120
Table 3.36: Additional Purchase for fulfilling RPO .............................................................................. 121
xi
Table 3.37: Energy deficit/surplus Scenario for FY 2016-17 to FY 2018-19 (MU) .............................. 122
Table 3.38: Capital Expenditure Plan for FY 2016-17 to FY 2018-19 as submitted by the Petitioner
(Rs. Crore) ........................................................................................................................................ 122
Table 3.39: Capitalisation Plan for FY 2016-17 to FY 2018-19 as submitted by the Petitioner (Rs.
Crore) ............................................................................................................................................... 124
Table 3.40: Actual GFA addition of UPCL (Rs. Crore) ........................................................................ 124
Table 3.41: Capitalisation as % of sum of opening CWIP and Capital Expenditure ......................... 125
Table 3.42: Capital expenditure and Capitalisation approved by the Commission (Rs. Crore) ....... 126
Table 3.43: Financing Plan proposed by the Petitioner (Rs. Crore) .................................................... 127
Table 3.44: Actual funding of capitalisation for FY 2012-13, FY 2013-14 and FY 2014-15 ................. 127
Table 3.45: Financing Plan approved by the Commission (Rs. Crore) ............................................... 127
Table 3.46: Additional man power requirement as submitted by the Petitioner............................... 128
Table 3.47: HR Plan approved by the Commission ............................................................................. 129
Table 4.1: Break up of Sales submitted by the Petitioner for FY 2014-15 (MU) ................................. 131
Table 4.2: Division wise anomalies in Consumption and Average Revenue per unit of Mixed Load
as per Commercial Statements for FY 2014-15 ............................................................................. 132
Table 4.3: Division wise anomalies in Average Revenue per unit of LT Industries as per Commercial
Statements for FY 2014-15 .............................................................................................................. 133
Table 4.4: Division wise anomalies in Average Revenue per unit of HT Industries as per
Commercial Statements for FY 2014-15......................................................................................... 133
Table 4.5: Division wise anomalies in Average Revenue per unit of PTW consumers as per
Commercial Statements for FY 2014-15......................................................................................... 134
Table 4.6: Division wise anomalies in Consumption and Average Revenue per Unit of Public Lamps
as per Commercial Statements for FY 2014-15 ............................................................................. 134
Table 4.7: Division wise anomalies in Consumption and Average Revenue per unit of Public Water
Works as per Commercial Statements for FY 2014-15 ................................................................. 135
Table 4.8: Division wise anomalies in Consumption and Average Revenue per unit of Government
Irrigation System as per Commercial Statements for FY 2014-15 ............................................... 136
Table 4.9: Re-casted Sales for Domestic Category for FY 2014-15 (MU) ............................................ 138
Table 4.10: Re-casted sales for PTW Category for FY 2014-15 (MU) .................................................. 139
Table 4.11: Re-casted sales for Other Categories for FY 2014-15 (MU) ............................................... 140
xii
Table 4.12: Category-wise Sales for FY 2014-15 (MU) .......................................................................... 140
Table 4.13: Assessed Distribution losses for FY 2014-15 (MU) ............................................................ 141
Table 4.14: Power Purchase Cost approved in the Tariff Order Vs Actual Power Purchase Cost for
FY 2014-15 (Rs. Crore)..................................................................................................................... 142
Table 4.15: Power Purchase Cost claimed by UPCL and approved by the Commission for FY 2014-
15 (Rs. Crore) ................................................................................................................................... 147
Table 4.16: Revised Employee Expenses Trajectory for MYT Control Period as submitted by the
Petitioner (Rs. Crore) ...................................................................................................................... 150
Table 4.17: Approved Employee Expenses for FY 2014-15 (Rs. Crore)............................................... 151
Table 4.18: Approved R&M Expenses for FY 2014-15 (Rs. Crore) ...................................................... 151
Table 4.19: Approved A&G expenses for FY 2014-15 (Rs. Crore) ....................................................... 152
Table 4.20: Approved O&M expenses for FY 2014-15 (Rs. Crore) ...................................................... 152
Table 4.21: Year wise GFA addition as submitted by UPCL (Rs. Crore) ............................................ 154
Table 4.22: Net Fixed Assets addition approved by the Commission (Rs. Crore) ............................. 155
Table 4.23: Assets base approved by the Commission (Rs. Crore) ..................................................... 155
Table 4.24: Means of Finance approved by the Commission (Rs. Crore) ........................................... 155
Table 4.25: Impact of final true up of capital related expenses for FY 2007-08 to FY 2012-13 approved
by the Commission (Rs. Crore) ...................................................................................................... 156
Table 4.26: Approved Means of Finance for FY 2013-14 (Rs. Crore)................................................... 156
Table 4.27: Means of Finance for FY 2014-15 as submitted by the Petitioner (Rs. Crore).................. 157
Table 4.28: GFA & Means of Finance approved by the Commission (Rs. Crore) .............................. 157
Table 4.29: Interest and Finance Charges for FY 2014-15 (Rs. Crore)................................................. 159
Table 4.30: Depreciation approved for FY 2014-15 (Rs. Crore) ........................................................... 160
Table 4.31: Provision for Bad and Doubtful Debts and Actual Write off ........................................... 162
Table 4.32: Interest on Working Capital for FY 2014-15 (Rs. Crore) ................................................... 164
Table 4.33: Return on Equity approved by the Commission for FY 2014-15 (Rs. Crore) .................. 166
Table 4.34: Non-tariff Income approved by the Commission for FY 2014-15 (Rs. Crore) ................. 167
Table 4.35: Revenue loss due to higher distribution loss for FY 2014-15 claimed by the Petitioner 168
Table 4.36: Revenue for FY 2014-15 Corresponding to Assessed Sales .............................................. 169
Table 4.37: Revenue from Sale of Power for FY 2014-15 (Rs. Crore) ................................................... 170
Table 4.38: Additional Revenue from Sale due to inefficiency for FY 2014-15 (Rs. Crore) ............... 170
xiii
Table 4.39: Sharing of Gains and Losses for FY 2014-15 claimed by the Petitioner (Rs. Crore)........ 171
Table 4.40: Sharing of gains on account of controllable factors approved by the Commission for FY
2014-15 (Rs. Crore) .......................................................................................................................... 173
Table 4.41: Summary of true up for FY 2014-15 approved by the Commission (Rs. Crore) ............. 174
Table 5.1: Consumer Category wise sales approved by the Commission for the second Control
Period from FY 2016-17 to FY 2018-19 (MU)................................................................................. 176
Table 5.2: Distribution Loss Trajectory approved by the Commission for the second Control Period
from FY 2016-17 to FY 2018-19 ....................................................................................................... 176
Table 5.3: Energy Input requirement approved by the Commission for the second Control Period
from FY 2016-17 to FY 2018-19 ....................................................................................................... 177
Table 5.4: Approach of the Commission in estimating the Cost of Power Purchase ........................ 180
Table 5.5: Summary of power purchase cost for FY 2016-17 ............................................................... 182
Table 5.6: Quarterly Power Purchase approved by the Commission for FY 2016-17 ........................ 183
Table 5.7: Energy Charges of thermal generating stations for FY 2016-17 ......................................... 185
Table 5.8: Transmission Charges for FY 2016-17 (Rs. Crore) ............................................................... 186
Table 5.9: GFA base approved by the Commission for FY 2015-16 (Rs. Crore) ................................. 188
Table 5.10: GFA base approved by the Commission for the second Control Period from FY 2016-17
to FY 2018-19 (Rs. Crore) ................................................................................................................ 188
Table 5.11: Details of financing for capitalisation for FY 2015-16 (Rs. Crore) .................................... 188
Table 5.12: Details of financing for capitalisation for FY 2016-17 (Rs. Crore) .................................... 189
Table 5.13: Details of financing for capitalisation for FY 2017-18 (Rs. Crore) .................................... 189
Table 5.14: Details of financing for capitalisation for FY 2018-19 (Rs. Crore) .................................... 189
Table 5.15: Interest on Loan approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 (Rs. Crore) .................................................................................................. 191
Table 5.16: Depreciation approved by the Commission for the second Control Period from FY 2016-
17 to FY 2018-19 (Rs. Crore) ........................................................................................................... 193
Table 5.17: Gn approved by the Commission ...................................................................................... 196
Table 5.18: Employee expenses approved by the Commission for the second Control Period from
FY 2016-17 to FY 2018-19 (Rs. Crore) ............................................................................................. 197
Table 5.19: R&M expenses approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 (Rs. Crore) .................................................................................................. 198
xiv
Table 5.20: A&G expenses approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 (Rs. Crore) ................................................................................................... 199
Table 5.21: O&M expenses approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 (Rs. Crore) ................................................................................................... 200
Table 5.22: Capital required to finance the shortfall in collection of current dues as claimed by the
Petitioner .......................................................................................................................................... 201
Table 5.23: Capital required to finance the shortfall in collection of current dues approved by the
Commission ..................................................................................................................................... 202
Table 5.24: Interest on working capital approved by the Commission for FY 2016-17 (Rs. Crore) .. 203
Table 5.25: Return on Equity approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 (Rs. Crore) ................................................................................................... 204
Table 5.26: Material Cost Variance considered as Non-Tariff Income (Rs. Crore) ............................ 207
Table 5.27: Prior Period Income (Rs. Crore) .......................................................................................... 209
Table 5.28: Past year adjustments approved by the Commission (Rs. Crore) .................................... 209
Table 5.29: Treatment of past year adjustments approved by the Commission (Rs. Crore) ............. 210
Table 5.30: Revenue Requirement approved by the Commission for FY 2016-17 (Rs. Crore) .......... 210
Table 5.31: Revenue for FY 2016-17 at existing Tariff (Rs. Crore) ....................................................... 211
Table 5.32: Revenue Gap for FY 2016-17 (Rs. Crore) ............................................................................ 212
Table 6.1 : Tariff for Domestic Consumers............................................................................................ 240
Table 6.2 : Concessional Tariff for Snowbound Areas ......................................................................... 240
Table 6.3: Tariff for Non-domestic consumers ..................................................................................... 241
Table 6.4: Tariff for Public Lamps.......................................................................................................... 242
Table 6.5: Tariff for Private tube Wells/ Pump Sets............................................................................. 242
Table 6.6: Tariff for Government Irrigation System ............................................................................. 243
Table 6.7 : Tariff for Public Water Works .............................................................................................. 243
Table 6.8: Tariff for LT Industries .......................................................................................................... 244
Table 6.9: Existing and Proposed Tariff for HT Industries .................................................................. 244
Table 6.10: Approved Tariff for HT Industry ....................................................................................... 245
Table 6.11: Tariff for Mixed Load .......................................................................................................... 245
Table 6.12: Tariff for Railway Traction .................................................................................................. 245
Table 6.13: Revenue at approved Tariffs for FY 2016-17 ...................................................................... 246
xv
Table 6.14 : Cross Subsidy at Average Cost of Supply ........................................................................ 247
Table 6.15 : Cross Subsidy at Approved Tariffs in FY 2015-16 and FY 2016-17 ................................. 247
Table 6.16 : Wheeling Charges approved for FY 2016-17 .................................................................... 250
Table 7.1: Detail of Sub-stations (S/s) maintained by UPCL as on 31.12.2015 .................................. 251
Table 7.2: Detail of Lines maintained by UPCL as on 31.12.2015....................................................... 252
Table 7.3: Quantum of Power Traded through Open Access............................................................. 255
Table 7.4: Revised Formats prescribed by the Commission vide letter dated 27.11.2014 ................ 257
Table 7.5: Status of Provisional Billing Viz. NA/NR/IDF/ADF/RDF ............................................. 259
Table 7.6: Status of Defective Meters.................................................................................................... 261
Table 7.7: Status of Mechanical Meters ................................................................................................ 262
Table 7.8: Status of Ghost/Fictitious Consumers ................................................................................ 263
Table 7.9: Status of Unmetered Consumers ......................................................................................... 264
Table 7.10: Status of NB & SB Cases ..................................................................................................... 265
Table 7.11: Status of Outstanding Arrears. .......................................................................................... 266
Table 7.12: Comparison of Outstanding Arrears. ............................................................................... 267
Table 7.13: Status of KCC Consumers .................................................................................................. 268
Table 7.14: Status of Revenue realisation per unit sold ...................................................................... 269
Table 8.1: Rostering Policy as submitted by the Petitioner ................................................................. 282
Table 8.2: Summary of Direct Recruitment........................................................................................... 287
Table 8.3: Details of collection of Revenue Arrears during FY 2014-15 as submitted by the Petitioner
(Rs. Crore) ........................................................................................................................................ 300
Table 8.4: Details of collection as submitted by the Petitioner ............................................................ 303
Uttarakhand Electricity Regulatory Commission 1
Before
UTTARAKHAND ELECTRICITY REGULATORY COMMISSION
Petition No. 48 of 2015 And
Petition No. 49 of 2015
In the Matter of: Petition filed by Uttarakhand Power Corporation Limited for approval of Business Plan for second
Control Period from FY 2016-17 to 2018-19.
AND
In the Matter of: Petition filed by Uttarakhand Power Corporation Limited for determination of ARR of second
Control Period from FY 2016-17 to 2018-19 and Tariff for FY 2016-17.
AND
In the Matter of:
Uttarakhand Power Corporation Limited ……… Petitioner
Urja Bhawan, Kanwali Road, Dehradun
Coram
Shri Subhash Kumar Chairman Shri K. P. Singh Member
Date of Order: April 5, 2016
Section 64(1) read with Section 61 and 62 of the Electricity Act, 2003 (hereinafter referred to
as “the Act”) requires the Generating Companies and the Licensees to file an application for
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
2 Uttarakhand Electricity Regulatory Commission
determination of tariff before the Appropriate Commission in such manner and along with such fee
as may be specified by the Appropriate Commission through Regulations.
In accordance with the relevant provisions of the Act, the Commission had notified
Uttarakhand Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff)
Regulations, 2011 hereinafter referred as UERC Tariff Regulations, 2011 for the first Control Period
from FY 2013-14 to FY 2015-16 specifying therein terms, conditions and norms of operation for
licensees, generating companies and SLDC. The Commission had issued the Multi Year Tariff
(MYT) Order dated May 6, 2013 for the Control Period from FY 2013-14 to FY 2015-16. In
accordance with the provisions of the UERC Tariff Regulations, 2011, the Commission had carried
out the Annual Performance Review for FY 2013-14 and FY 2014-15 vide its Orders dated April 10,
2014 and April 11, 2015 respectively.
Further, in accordance with the relevant provisions of the Act, the Commission had notified
Uttarakhand Electricity Regulatory Commission (Terms and Conditions for Determination of Multi
Year Tariff) Regulations, 2015 hereinafter referred as UERC Tariff Regulations, 2015 for the second
Control Period from FY 2016-17 to FY 2018-19 specifying therein terms, conditions and norms of
operation for licensees, generating companies and SLDC. In compliance with the provisions of the
Act and Regulation 8(1) and Regulation 10(1) of UERC Tariff Regulations, 2015, Uttarakhand Power
Corporation Limited (hereinafter referred to as “UPCL” or “Licensee” or “Petitioner”) filed separate
Petitions for approval of its Business Plan for the second Control Period from FY 2016-17 to FY
2018-19 (Petition No. 48 of 2015, hereinafter referred to as the “Business Plan Petition”) and Multi
Year Tariff Petition (Petition No. 49 of 2015, hereinafter referred to as the “MYT Petition”) on
November 30, 2015. UPCL, in its Business Plan Petition, has submitted the Capital Investment Plan,
Financing Plan, Human Resources Plan and trajectory of performance parameters for the second
Control Period. Further, through the MYT Petition, UPCL has submitted the detailed calculations of
its projected Aggregate Revenue Requirement for the second Control Period from FY 2016-17 to FY
2018-19 in accordance with teh UERC Tariff Regulations, 2015. Through the MYT Petition, the
Petitioner also requested for true up of FY 2014-15 based on the audited accounts in accordance
with UERC Tariff Regulations, 2011 (UERC Tariff Regulations, 2011).
The Business Plan Petition filed by UPCL had certain infirmities/deficiencies which were
informed to UPCL vide Commission’s letter no. UERC/6/TF-284/15-16/2015/1359 dated
Uttarakhand Electricity Regulatory Commission 3
December 8, 2015 and UPCL was directed to rectify the said infirmities in the Petition and submit
certain additional information necessary for admission of the Business Plan Petition. UPCL vide its
letter no. 5327/UPCL/RM/B-17 dated December 16, 2015 submitted most of the information sought
by the Commission. Based on the submission dated December 16, 2015 made by UPCL, the
Commission vide its Order dated December 22, 2015 provisionally admitted the Petition for further
processing subject to the condition that UPCL shall furnish any further information/clarifications as
deemed necessary by the Commission during the processing of the Petition within the time frame,
as may be stipulated by the Commission, failing which the Commission may proceed to dispose of
the matter as deemed fit by it based on the information available with it.
Further, the MYT Petition filed by UPCL also had certain infirmities/deficiencies. The
Commission, accordingly, vide its letter no. UERC/6/TF-284/15-16/2015/1357 dated December 8,
2015 directed UPCL to rectify these infirmities/deficiencies and to submit certain additional
information necessary for admission of the MYT Petition. UPCL vide its letter no.
5326/UPCL/RM/B-17 dated December 16, 2015 submitted most of the information sought by the
Commission. Based on the submission dated December 16, 2015 by UPCL, the Commission vide its
Order dated December 22, 2015 provisionally admitted the MYT Petition, with the condition that
UPCL shall furnish any further information/clarifications as deemed necessary by the Commission
during the processing of the Petition within the time frame, as may be stipulated by the
Commission, failing which the Commission may proceed to dispose of the matter as deemed fit by
it based on the information available with it.
This Order, accordingly, relates to the Business Plan Petition and the MYT Petition filed by
UPCL for approval of the Business Plan and determination of Aggregate Revenue Requirement
(ARR) for the second Control Period from FY 2016-17 to FY 2018-19 and Tariff for FY 2016-17 as well
as true up for FY 2014-15 and Annual Performance Review for FY 2015-16, and is based on the
original as well as subsequent submissions made by UPCL during the course of the proceedings.
Tariff determination being the most vital function of the Commission, it has been the
practice of the Commission to elaborate in detail the procedure and to explain the underlying
principles in determination of tariffs. Accordingly, in the present Order also, in line with past
practices, the Commission has tried to elaborate the procedure and principles followed by it in
determining the ARR of the licensee. Accordingly, in the present Order also, in line with the past
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
4 Uttarakhand Electricity Regulatory Commission
practices, the Commission has tried to detail the procedure and principles followed in determining
the ARR of the licensee. For the sake of convenience and clarity, this Order has further been divided
into following Chapters:
Chapter 1 - Background and Procedural History
Chapter 2 - Summary of Stakeholders’ Objections/Suggestions, Petitioner’s Responses and
Commission’s Views
Chapter 3 - Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on
Business Plan for second Control Period
Chapter 4 - Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on
Truing up for FY 2014-15
Chapter 5 - Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on
MYT Period for second Control Period
Chapter 6 - Tariff Rationalisation, Tariff Design and Related Issues
Chapter 7 - Review of Commercial Performance of UPCL
Chapter 8 - Commission’s Directives
Uttarakhand Electricity Regulatory Commission 5
1. Background and Procedural History
In accordance with the provisions of the Uttar Pradesh Reorganization Act, 2000 (Act 29 of
2000), enacted by the Parliament of India on August 25, 2000, the State of Uttaranchal came into
existence on November 9, 2000. Section 63(4) of the above Reorganization Act allowed the
Government of Uttaranchal (hereinafter referred to as “GoU” or “State Government”) to constitute
a State Power Corporation at any time after the creation of the State. GoU, accordingly, established
the Uttaranchal Power Corporation Limited (UPCL) under the Companies Act, 1956, on February
12, 2001 and entrusted it with the business of transmission and distribution in the State.
Subsequently, from April 1, 2001, all works pertaining to the transmission, distribution and retail
supply of electricity in the area of Uttaranchal were transferred from UPPCL to UPCL, in
accordance with the Memorandum of Understanding dated March 13, 2001, signed between the
Governments of Uttaranchal and Uttar Pradesh. On May 31, 2004, GoU first vested all the interests,
rights and liabilities related to Power Transmission and Load Despatch of “Uttaranchal Power
Corporation Limited” into itself and, thereafter, re-vested them into a new company, i.e. “Power
Transmission Corporation of Uttaranchal Limited”, now renamed as “Power Transmission
Corporation of Uttarakhand Limited” after change of name of the State. Since then Uttarakhand
Power Corporation Ltd. (UPCL) a company wholly owned by the Government of Uttarakhand
bacame the sole distribution licensee engaged in the business of distribution and retail supply of
power in the State of Uttarakhand.
The Commission vide its Order dated May 6, 2013 issued the Order on approval of Business
Plan for UPCL for the first Control Period FY 2013-14 to FY 2015-16 and Tariff for FY 2013-14.
Further the Commission had issued the Tariff Orders for FY 2014-15 and FY 2015-16 vide its Orders
dated April 10, 2014 and April 11, 2015 respectively.
As mentioned earlier also, in accordance with the provisions of the Electricity Act, 2003 and
Regulation 8(1) and Regulation 10(1) of the UERC Tariff Regulations, 2015, UPCL is required to
submit Business Plan Petition and MYT Petition for determination of its ARR by November 30,
2015. UPCL in compliance to the Regulations submitted the Business Plan Petition and MYT
Petition for determination of ARR for the second Control Period from FY 2016-17 to FY 2018-19 and
Tariff for FY 2016-17 along with the True up for FY 2014-15 on November 30, 2015.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
6 Uttarakhand Electricity Regulatory Commission
The Business Plan Petition and MYT Petition were provisionally admitted by the
Commission vide two separate Orders dated December 22, 2015. The Commission, through its
above Admittance Orders dated December 22, 2015, to provide transparency in the process of tariff
determination and give all the stakeholders an opportunity to submit their objections/suggestions
/comments on the proposals of the Distribution Licensee, also directed UPCL to publish the salient
points of its Petitions in the leading newspapers. The salient points of the Petitions were published
by the Petitioner in the following newspapers:
Table 1.1: Publication of Notice S.No. Newspaper Name Date Of Publication
1 Amar Ujala 25.12.2015 2 Dainik Jagran 25.12.2015 3 Hindustan 25.12.2015 4 Rashtriya Sahara 25.12.2015 5 Times of India 25.12.2015 6 Hindustan Times 25.12.2015
Through above notice, the stakeholders were requested to submit their
objections/suggestions/comments latest by February 10, 2016 (copy of the notice is enclosed as
Annexure 3). The Commission received in all thirty eight objections/suggestions/comments in
writing on the Petitions filed by UPCL. The list of stakeholders who have submitted their
objections/suggestions/comments in writing is enclosed as Annexure-4.
Further, for direct interaction with all the stakeholders and public at large, the Commission
also held public hearings on the Petitions filed by the Petitioner at the following places in the State
of Uttarakhand.
Table 1.2: Schedule of Hearing S. No Place Date
1 Pithoragarh February 16, 2016 2 Sitarganj February 18, 2016 3 Pauri Garhwal February 23, 2016 4 Dehradun March 1, 2016
The list of participants who attended the Public Hearing is enclosed at Annexure-5.
The Commission also sent the copies of the salient features of the tariff Petitions to Members
of the State Advisory Committee and the State Government. The salient features of the tariff
Petitions submitted by UPCL were also made available on the website of the Commission, i.e.
www.uerc.gov.in. The Commission also held a meeting with the Members of the Advisory
1. Background and Procedural History
Uttarakhand Electricity Regulatory Commission 7
Committee on March 4, 2016, wherein, detailed deliberations were held with the Members of the
Advisory Committee on the various issues linked with the Petitions filed by UPCL.
The objections/suggestions/comments, as received from the stakeholders through
mail/post as well as during the course of public hearings were sent to the Petitioner for its
response. All the issues raised by the stakeholders, Petitioner’s responses and Commission’s views
thereon are detailed in Chapter 2 of this Order. In this context, it is also to underline that while
finalizing this Order, the Commission has, as far as possible, tried to address the issues raised by the
stakeholders.
Meanwhile, based on the scrutiny of the Petitions submitted by UPCL, the Commission vide
its letter no. UERC/6/TF-284/15-16/2015/1360 dated December 8, 2015, letter no. UERC/6/TF-
285/15-16/2016/1568 dated January 15, 2016, letter no. UERC/6/TF-284/15-16/2015/1358 dated
December 8, 2015 and letter no. UERC/6/TF-284/15-16/2016/1467 dated January 5, 2016 pointed
out certain data gaps in the Petitions and sought following additional information/clarifications
from the Petitioner:
Business Plan Petition
• Actual category wise sales for April, 2015 to December, 2015.
• Actual source wise monthly generation for each source of power purchase for FY
2012-13 to FY 2014-15 considered for projecting the power purchase for the second
Control Period.
• Actual Inter-State transmission losses for past 52 weeks (1 year).
• Basis of the escalation rate considered for projecting the fixed cost of power purchase
for FY 2016-17.
• Details of expected COD considered for each of the upcoming stations.
• Basis for considering power purchase cost from new generating stations (thermal
andlarge hydro) developed by the Central Sector at Rs. 5/kWh for the Control
period.
• Preparedness to execute the capital works proposed during the second Control
Period.
MYT Petition
• Submission of duly filled in excel formats.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
8 Uttarakhand Electricity Regulatory Commission
• Electrical Inspector’s Clearance Certificates for the assets capitalised in FY 2014-15.
• Actual number of employees recruited in FY 2014-15.
• Existing and proposed consumer category wise cross subsidy.
• Details of month wise energy banked during FY 2014-15.
• Source wise power purchase quantum, cost in Rs. Crore and rate in Rs./kWh for FY
2014-15.
• Actual interest on consumer security deposit paid to consumers/adjusted in
consumers’ bills in FY 2014-15.
• Progress made in writing off bad debts.
• Justification for higher consumption per kW and lower revenue per unit than that
approved by the Commission as observed in the Commercial Statement submitted
for FY 2014-15.
So as to have better clarity on the data filed by the Petitioner and to remove inconsistency in
the data, a Technical Validation Session (TVS) was also held with the Petitioner’s officers on January
13, 2016, for further deliberations on certain issues related to the Petition filed by UPCL. Minutes of
the above Technical Validation Session were sent to the Petitioner vide Commission’s letter no.
UERC/6/TF-284/15-16/2016/1567 dated January 15, 2016, letter no. UERC/6/TF-285/15-
16/2016/1568 dated January 15, 2016 for its response.
The Petitioner submitted the replies to the data gaps vide its letter no. 5327/UPCL/RM/B-
17 dated December 16, 2015, letter no. 5421/UPCL/RM/B-17 dated December29, 2015, letter no.
5422/UPCL/RM/B-17 dated December 29, 2015, letter no. 116/UPCL/RM/B-17 dated January 11,
2016 and replies to Minutes of TVS vide letter no. 206/UPCL/RM/B-17 dated January 24, 2016 and
letter no. 205/UPCL/RM/B-17 dated January 25, 2016. Further data gaps were forwarded by the
Commission vide letter no. UERC/6/TF-284/15-16/2016/1676 dated February 8, 2016 and the
Petitioner submitted its replies vide letter no. 394/UPC/RM/B-17 dated February 11, 2016. The
submissions made by UPCL in the Petitions as well as additional submissions have been discussed
by the Commission at appropriate places in the Order along with the Commission’s views on the
same.
Uttarakhand Electricity Regulatory Commission 9
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
The Commission has received suggestions and objections on UPCL’s Petition for True-up of
Expenses & Revenues for FY 2014-15, Business Plan and Multi Year Tariff Petiton for the second
Control Period from FY 2016-17 to FY 2018-19. The Commission also obtained responses from
UPCL on the comments received from the stakeholders.
Since, several issues are common and have been raised by more than one respondent all
comments have been clubbed issue-wise and summarized below.
2.1 General
2.1.1 Compliance to Regulations/Directions of Commission
2.1.1.1 Stakeholder’s Comments
Shri Pankaj Gupta, President, Industries Association of Uttarakhand & Shri Ashok Bansal,
KGCCI submitted that Tariff/ARR fixation exercise is not only about approving the expenses and
revenues, but also an exercise of taking stock of the past work done and setting a road map for
future performance. In this respect the Commission gave various directions to UPCL. The variance
in projections of the Commission and that of UPCL is on account of non-compliance by UPCL on
the directives of the Commission in letter and spirit. It is requested to take up seriously with UPCL
for the proper follow up on these directives.
Some other stakeholders suggested that UPCL should provide the compliance of the
directions issued by the Commission in Tariff Order for FY 2015-16.
2.1.1.2 Petitioner’s Reply
The Petitioner submitted that the compliance status of the directions issued by the
Commission has been submitted. The progress reports in respect of various works are submitted by
UPCL as and when required by the Commission.
2.1.1.3 Commission’s Views
The Commission is regularly monitoring the compliances of the directives issued to UPCL
on regular basis. Further, the Commission obtained the detailed report of the compliance on the
directions from UPCL during the Technical Validation Session held during theTariff proceedings.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
10 Uttarakhand Electricity Regulatory Commission
The submissions of the Petitioner on the action taken by it with regard to various directives and the
Commission’s views on the same are discussed in Chapter 8 (Commission’s Directives) of the
Order.
2.2 Overall Tariff Increase
2.2.1.1 Stakeholder’s Comments
Shree Karuna Jan Kalyan Samiti and some other stakeholders submitted that the tariff
should not be increased and if required the same should be limited to 5%.
Uttarakhand Steel Manufacturers Association (USMA) requested the Commission to not
increase the tariff as at this juncture any tariff increase would put the industry into further hardship.
They suggested that the tariffs should be reduced due to reduction in coal prices which might have
reduced the power purchase costs from NTPC and other thermal power plants.
Shri R.K. Singh from Tata Motors Ltd., M/s Asahi India Glass Ltd., M/s East West Products
Ltd., M/s Vista Alps Industries Ltd. and Shri G S Bedi, Indian Drugs & Pharmaceuticals submitted
that an increase proposed by UPCL in categories like PWW, LT & HT Industry and Mixed load
along with the hikes proposed by UJVN Ltd. and PTCUL are exorbitant unjustified and will break
the backbone of industry and other consumers.
2.2.1.2 Petitioner’s Reply
The Petitioner submitted that it is a commercial organization and is required to meet its
Annual Revenue Requirement out of the revenue realized from the consumers through electricity
tariffs.
The revenue deficit for FY 2016-17 including the deficit of FY 2014-15 has been estimated at
Rs. 1220.26 Crore, which necessitates a tariff hike of 24.96%. Summary of gap to be recovered in FY
2016-17 is as follows:-
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 11
Table 2.1: Summary of Total Gap as submitted by the Petitioner S. No. Particulars Rs. Crore Rs./Unit %
1. Cost of Power [from Table 2.2] 4688.45 4.32 84.24% 2. Cost of Service 876.99 0.81 15.76% 3. ARR (1+2) 5565.44 5.12 100.00% 4. Gap for FY 15 544.39 0.50 9.78% 5. Net ARR (3+4) 6109.83 5.62 109.78% 6. Existing Tariff 4889.57 4.50 87.86% 7. Increase in Tariff Required (5-6) 1220.26 1.12 24.96%
The Petitioner further submitted the details of the above referred Cost of Power as follows:
Table 2.2: Cost of Power as submitted by the Petitioner S. No. Particulars Rs./Unit %%
1. Power Purchase 2.99 69.24% 2. Transmission Charges 0.52 12.00% 3. Transmission Loss 0.06 1.47% 4. Cost of Power at Distribution Periphery (1+2+3) 3.57 82.71% 5. Distribution Loss 0.75 17.29% 6. Cost of Power (4+5) 4.32 100.00%
The Petitioner submitted that on the basis of estimates of expenses and revenue, tariff hike
of 24.96% is required in the existing tariff.
2.2.1.3 Commission’s Views
The Commission is of the view that the overall tariff increase is a function of projected
Annual Revenue Requirement for the ensuing year (including impact of truing up of expenses and
revenue for previous year) and projected revenue at existing tariffs. The Commission has carried
out the detailed scrutiny of ARR for FY 2016-17 and truing up for FY 2014-15 in accordance with the
provisions of relevant Regulations as discussed in Chapter 4 and 5 of the Order. Based on the
approved ARR for FY 2016-17 including impact of truing up for FY 2014-15, the Commission has
marginally increased the tariff to meet the projected revenue gap as discussed in detail in Chapter 6
of the Order.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
12 Uttarakhand Electricity Regulatory Commission
2.3 Domestic Tariff
2.3.1 Tariff Hike
2.3.1.1 Stakeholder’s Comments
Shree Karuna Jan Kalyan Samiti and some other stakeholders submitted that the tariff
increase proposed for domestic category is very high and the tariff increase should be limited to 5%.
They further suggested for not increasing the tariff for first two slabs of domestic category (upto 100
unit per month and 101-200 units per month).
Shri Mukesh Chandra Joshi, Village Joshiyana, PO Parsundakhal Patti Paidulsyun, Distt.
Pauri Garhwal, Uttarakhand submitted that the consumers residing in the hilly areas of
Uttarakhand and those who are consuming less than 50 units should be given full rebate on
electricity charges or minimum of 80 % rebate and consumers whose consumption is less than 100
units should be provided with a rebate of minimum of 50%.
Shri Vijay Singh Verma of Bhartiya Kisan Club submitted that the rates of energy consumed
for all BPL connections should be increased. Further, if the BPL consumer is consuming more than
30 units than what should be the rate of energy charge for those consumer should be decided.
2.3.1.2 Petitioner’s Reply
As regards the contention raised by several stakeholders regarding tariff hike, the Petitioner
submitted that UPCL is a commercial organization and is required to meet its Annual Revenue
Requirement out of the revenue realized from the consumers through electricity tariffs. The revenue
deficit for FY 2016-17 including the deficit of FY 2014-15 has been estimated at Rs. 1220.26 Crore,
which necessitates a tariff hike of 24.96%.
Thus, on the basis of estimates of expenses and revenue, tariff hike of 24.96% is required in
the existing tariff.
The Petitioner further submitted that the tariff of electricity is determined in accordance
with the provisions of Electricity Act, 2003. The tariff of BPL consumers has been proposed close to
50% of the Average Cost of Supply. The tariff for other domestic consumers has been proposed at
about 67% of Average Cost of Supply. The rates of electricity cannot be kept below these rates
keeping in view the cost estimates of UPCL and the provisions of law.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 13
The Petitioner further clarified that in case any BPL Consumer consumes more than 30 units
in a month, the tariff applicable to other domestic consumers is also applicable to such consumer.
2.3.1.3 Commission’s Views
The Commission appreciates the views expressed by some of stakeholders that the tariff
increase should be reasonable in the range of around 5%. As discussed earlier, based on approved
ARR for FY 2016-17 including impact of truing up for FY 2014-15, the Commission has marginally
increased the tariff to meet the projected revenue gap as discussed in detail in Chapter 6 of the
Order.
Further, continuing with the approach adopted in the previous years, the Commission has
attempted to reduce the cross-subsidy while desiging the tariffs for various categories as elaborated
in Chapter 6 of the Order. As regards the special tariff to be provided for consumers in hilly areas
and consumers having lower consumption, the Commission would like to clarify that as per the
existing tariff structure also, the tariff structure for domestic category includes BPL customers with
consumption upto 30 units/month as a sub-category with a much lower tariff and also within
domestic category, the consumers having consumption upto 100 units per month fall in the 1st slab
with lowest tariff and hence, there arises no need to provide any separate rebate. For better
understanding, the Rate Schedule (RTS-1) annexed to the Tariff Order can be referred.
On the issue of consumption of BPL consumers exceeding 30 units per month, the
Commission would like to clarify that in case consumption of any BPL Consumer exceeds more
than 30 units in a month, the tariff applicable to other domestic consumers becomes applicable to
such BPL consumers on the entire monthly consumption.
2.3.2 Fixed Charges based on Load
2.3.2.1 Stakeholder’s Comments
Bhartiya Kisan Club and some other stakeholders suggested that the fixed charges should be
specified on the basis of load and not the consumption.
2.3.2.2 Petitioner’s Reply
The Petitioner submitted that the existing tariff of the Domestic Category has been
determined at about 67% of Cost of Supply. The Domestic Consumers who have higher
consumption are affluent consumers and should not be subsidized and they should pay the cost of
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
14 Uttarakhand Electricity Regulatory Commission
supply of electricity. With a view to reduce cross subsidy in this category, the tariff (Energy Charge
as well as Fixed Charge) for higher consumption should be high and, therefore, it is logical that the
fixed charge for higher consumption should be more and this is possible only when fixed charges
are based on consumption.
2.3.2.3 Commission’s Views
The Commission appreciates the views expressed by some of the stakeholders. The
Commission during the last tariff proceedings floated a concept paper on this issue and after due
consultation with the stakeholders specified the fixed charges based on consumption as
consumption data is the most authentic data available.
2.4 Non-Domestic Tariff
2.4.1 Tariff Hike
2.4.1.1 Stakeholder’s Comments
Shri Karuna Jan Kalyan Samiti, M/s Devbhoomi Dharamshall Prabhandhak Sabha & some
of the non-domestic consumers opposed the tariff increase proposed by UPCL, while some
stakeholders submitted that the tariff increase should be reasonable.
2.4.1.2 Petitioner’s Reply
The Petitioner submitted that on the basis of estimates of expenses and revenues, tariff hike
of 24.96% is required in the existing tariff.
2.4.1.3 Commission’s Views
The Commission appreciates the views expressed by some of the stakeholders that the tariff
increase should be reasonable. As discussed earlier, based on the approved ARR for FY 2016-17
including impact of truing up for FY 2014-15, the Commission has marginally increased the tariff to
meet the projected revenue gap as discussed in detail in Chapter 6 of the Order.
Further, continuing with the approach adopted in the previous years, the Commission has
attempted to reduce the cross-subsidy while desiging the tariffs for various categories as
eleaborated in Chapter 6 of the Order.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 15
2.4.2 Tariff for Dharamshala/Trust/Ashram
2.4.2.1 Stakeholder’s Comments
M/s Dev Bhoomi Dharamshala Prabhandhak Sabha, Haridwar submitted that all types of
Dharamshalas, Trusts should be kept under Institutional/Domestic category as earlier. These
Dharamshalas/trusts/Ashrams are not involved in any kind of business and only the arrangement
fees is charged to the people going for pilgrimage. They further submitted that the fixed charges per
kW levied in the electricity bill should be abolished as there is no relevant justification for the same.
They also submitted there should not be any increase in the tariff rates for these organizations in FY
2016-17, 2017-18, 2018-19, as these organizations are engaged in works of public interest.
2.4.2.2 Petitioner’s Reply
The Petitioner submitted that as per the existing categorization of consumers,
Dharamshalas/Trusts/Ashrams fall under the category of RTS-2 (Non-domestic). The domestic
category applies only on the residential premises for light, fan & power and other domestic
purposes including single point bulk supply above 50 kW for residential colonies, residential
multistoried buildings where energy is exclusively used for such purpose. Non-domestic category is
a subsidizing category whereas the domestic category is a subsidized category. In accordance with
the provisions of Electricity Act, 2003 and National Tariff Policy, the cross subsidy is to be
maintained at a level of ±20% of the average cost of supply.
In view of the facts mentioned hereinabove, consumers covered under the subsidising
category cannot be transferred into the subsidized category. Thus, the Dharamshalas
/Trusts/Ashrams are rightly categorized under Rate Schedule RTS-2 (Non-domestic).
As regards levy of Fixed Charges, the Petitioner submitted that Section-45(3) of the
Electricity Act, 2003, stipulates for levy of fixed charges as follows:
“The charges for electricity supplied by a distribution licensee may include:
(a) a fixed charge in addition to the charge for the actual electricity supplied ;
(b) a rent or other charges in respect of any electric meter or electrical plant provided by the distribution
licensee.”
About 50% of the UPCL’s total costs are fixed in nature including the capacity / fixed charge
of power purchase, which should be recovered to a certain extent through fixed charges to ensure
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
16 Uttarakhand Electricity Regulatory Commission
revenue stability. Hence, levy of fix charge is necessary and in accordance with the provisions of
law.
2.4.2.3 Commission’s Views
The Commission agrees with the views of the Petitioner that as per the existing
categorization of consumers, Dharamshalas/Trusts/Ashrams fall under the category of RTS-2
(Non-domestic). The domestic category applies only on the residential premises for light, fan &
power and other domestic purposes including single point bulk supply above 50 kW for residential
colonies, residential multistoried buildings where energy is exclusively used for domestic purpose.
Hence it will not be appropriate to categorise Dharamshalas/Trusts/Ashrams under RTS-1
(Domestic) category. Moreover, the Commission has deliberated in detail on the issue of levy of
Fixed Charges in Chapter 6 of the Order.
2.4.3 Tariff for Telecom Tower
2.4.3.1 Stakeholder’s Comments
M/s Indus Tower Ltd. submitted that the tariff for consumers with flat load profile and high
power factor requiring electricity on continuous basis should be considered separately while
determining the tariff for the current year. They further submitted that the Hon’ble APTEL
judgement (MERC vs. Mumbai Airport and Tata Steel vs. OERC) should be considered for the tariff
rationalization and should be taken as a guiding factor in tariff determination process and tariff for
the commercial category be considered to reduce with immediate effect.
They also submitted that the Commission should consider classifying telecom towers under
a separate sub-category within the existing commercial category under Section 62(3) of the
Electricity Act 2003, with a suitable relaxation in the applicable tariff.
2.4.3.2 Petitioner’s Reply
The Petitioner submitted that the telecom towers are for commercial purposes and,
therefore, these are rightly categorized under Rate Schedule RTS – 2 (Non-Domestic). In Rate
Schedule RTS – 2, tariff for consumers having load above 25 KW is kVAh based wherein a
consumer is automatically benefited by having healthy/high power factor. For consumers having
load upto 25 kW, there is kWh based tariff and consumer having low power factor are liable to pay
low power factor surcharge.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 17
2.4.3.3 Commission’s Views
The Commission is of the view that creation of separate sub-category for telecom towers will
be against the overall principle of tariff rationalization. However, tariffs categorization of
consumers has been done in accordance with the provisions of the Act/Regulations while keeping
the cross-subsidy levels within the norms laid down in the National Tariff Policy.
2.5 Independent Advertising Hoardings
2.5.1.1 Stakeholder’s Comments
Shri Karuna Jan Kalyan Samiti requested the Commission that the tariff for category
Independent Advertising Hoardings should not be increased.
2.5.1.2 Petitioner’s Reply
The Petitioner submitted that as per the provisions of the Electricity Act, 2003 and the Tariff
Policy, the tariff of each category should be designed in a manner that the level of cross subsidy
should be within ± 20% of the average cost of supply. In case the tariff of this category is not
increased, this subsidizing category may convert into subsidized category. Thus, the proposed
increase in tariff for this category is justified and required.
2.5.1.3 Commission’s Views
As discussed earlier, based on the approved ARR for FY 2016-17 including the impact of
truing up for FY 2014-15, the Commission has marginally increased the tariff to meet the projected
revenue gap as discussed in detail in Chapter 6 of the Order.
Further, continuing with the approach adopted in the previous years, the Commission has
attempted to reduce the cross-subsidy while desiging the tariffs for various categories as elaborated
in Chapter 6 of the Order.
2.6 Agricultural Tariff
2.6.1 Tariff Increase
2.6.1.1 Stakeholder’s Comments
Bhartiya Kisan Union submitted that the suggestion of Uttarakhand Power Corporation
Limited to increase the charge on Energy charge should not be accepted as the farmers are already
debt trapped and in poor financial condition. Therefore, if the tariff is further increased it would
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
18 Uttarakhand Electricity Regulatory Commission
impose extra financial burden on the farmers. They requested the Commission not to increase PTW
Tariffs.
Shri Mukesh Chandra Joshi, Village Joshiyana, PO Parsundakhal Patti Paidulsyun, Distt.
Pauri Garhwal, Uttarakhand submitted that the electricity tariff for irrigation and PTW connections
should not be increased. The consumers residing in the hilly areas can be released pump connection
of 1 kW or 2 kW and the same should be considered under domestic category.
2.6.1.2 Petitioner’s Reply
As regards the tariff increase, the Petitioner submitted that it is a commercial organization
and is required to meet its Annual Revenue Requirement out of the revenue realized from the
consumers through electricity tariffs. The Petitioner further submitted that on the basis of estimates
of expenses and revenues, tariff increase of 24.96% is required in the existing tariff.
2.6.1.3 Commission’s Views
As discussed earlier, based on approved ARR for FY 2016-17 including impact of truing up
for FY 2014-15, the Commission has marginally increased the tariff to meet the projected revenue
gap as discussed in detail in Chapter 6 of the Order. Further, continuing with the approach adopted
in previous years, the Commission has attempted to reduce the cross-subsidy while desiging the
tariffs for various categories as elaborated in Chapter 6 of the Order. Further, the tariff categories
have been designed based on the usage & hence, the suggestion to consider pump connections
under domestic category is not proper. Besides the tariffs of PTW is lowest in the State.
2.6.2 Floriculture
2.6.2.1 Stakeholder’s Comments
Smt. Poonam Uniyal, 236, Nehru Gram Road, Ring Road, Dehradun suggested that the
commercial tariff should not be charged for floriculture.
2.6.2.2 Petitioner’s Reply
The Petitioner submitted that as per the provisions of Tariff Orders issued by the
Commission from time to time electricity consumption for floriculture purpose is required to be
charged under Rate Schedule RTS-7 (Industry) for the period upto 31-03-2015 and under Rate
Schedule RTS – 4A (Agriculture Allied Activity) for the period from 01-04-2015.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 19
2.6.2.3 Commission’s Views
The Commission in its Tariff Order dated April 10, 2015 for FY 2015-16 had created a
separate category Agriculture Allied Activities after due consultation processs and hence, the tariff
applicable for floriculture is not a commercial tariff. However, in this Tariff Order, the tariff of
Agriculture Allied Activities which does not have further processing plant have been kept same as
that of PTW category.
2.7 Mixed Load (RTS-8) Tariff
2.7.1.1 Stakeholder’s Comments
Shri G.S. Bedi of Indian Drugs and Pharmacueticals Ltd. (IDPL, Rishikesh), requested that
the rate for RTS-8 (Mixed load) be brought at par with the single point bulk supply connections
under RTS-1(Domestic) because such consumers like IDPL colony connection has no commercial
activity except for some shops/khokhas to cater to the urgent needs of the residents of the IDPL
Colony. It also pointed out that domestic consumers having contracted load up to 2 kW &
consumption up to 200 kWh per month are allowed to use some portion of the premises for
business/other purposes without any additional charges at the domestic rates. These two cases are
quite similar. Alternatively RTS-8 be merged with RTS-1 (Domestic-Single point bulk supply).
2.7.1.2 Petitioner’s Reply
The Petitioner submitted that Single Point Bulk Supply under Domestic (RTS -1) category is
allowed where the consumption of electricity is only for domestic residential purposes. Whereas,
Single Point Bulk Supply under Mixed Load (RTS – 8) category is applicable where there is at least
60% domestic load and rest load is used for other non–domestic purposes. In case some portion of
the supply is used for non-domestic purpose, the supply of electricity cannot be given under rate
schedule RTS -1. Further, single point bulk supply under Mixed Load category cannot be compared
with the consumers covered under domestic category having load upto 2 kW and consumption
upto 200 kWh per month using some portion of their premises for non-domestic purposes.
2.7.1.3 Commission’s Views
The Commission agrees with the reply given by the Petitioner that the Single Point Bulk
Supply under Domestic (RTS -1) category is allowed where the consumption of electricity is for
domestic residential purposes whereas Single Point Bulk Supply under Mixed Load (RTS – 8)
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
20 Uttarakhand Electricity Regulatory Commission
category is applicable where there is a mixed load with minimum 60% of domestic load while the
balance load is used for other non–domestic purposes. As in Mixed load category, part of the load is
utilised for other than domestic purposes, it will not be appropriate to merge the Mixed Load
category with the domestic category.
2.8 Industrial Tariff
2.8.1 Tariff Hike
2.8.1.1 Stakeholder’s Comments
Shri Pramod Singh Tomar of M/s Galwalia Ispat Udyog Pvt. Ltd. and Shri Shakeel A.
Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted that the proposed tariff revision
and hike proposed in case of HT consumer category of 24.87% is not linked to input cost of UPCL
which is not in consonance with the letter and spirit of the Electricity Act, 2003 and Tariff Policy,
2006. The power purchase cost per unit has increased only by 8% from FY 2015-16 to FY 2016-17
while the increase in tariff proposed for HT consumers is 24.87%. This establishes that the proposed
increase in tariff has no direct correlation with the input cost.
M/s KVS Infratech LLP submitted that the current tariffs for LT Industrial category are
sufficient and there is no need to increase the tariff further.
M/s Kashi Vishwanath Steels Pvt. Ltd. submitted that the proposed tariff hike is not
justified as growth in industries is merely 2-3%, however, tariff hike sought is 24.96%.
2.8.1.2 Petitioner’s Reply
The Petitioner submitted the basis of tariff increase as follows:
(i) Increase in total cost in FY 17 over revenue of FY 16 (4.24/3.70) – 14.59%
(ii) Gap of FY 2014-15 to be recovered in FY 17 - 11.13%
(iii) Total increase required - 25.72%
The Petitioner submitted that it is clear that out of required increase of 25.72%, UPCL has
proposed a tariff increase of 24.96% and balance recovery is through performance improvement.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 21
2.8.1.3 Commission’s Views
As discussed earlier, based on the approved ARR for FY 2016-17 including impact of truing
up for FY 2014-15, the Commission has marginally increased the tariff in order to meet the projected
revenue gap as discussed in detail in Chapter 6 of the Order. Further, continuing with the approach
adopted in previous years, the Commission has attempted to reduce the cross-subsidy while
desiging the tariffs for various categories as elaborated in Chapter 6 of the Order.
2.8.2 Rebate in Demand Charges for non-supply of power
2.8.2.1 Stakeholder’s Comments
M/s USMA suggested that the current level of 20% rebate in demand charges for minimum
average supply to HT Industrial Consumers of 18 hours per day during the month should be
changed to minimum average supply of 22 hours per day during the month.
2.8.2.2 Petitioner’s Reply
The Petitioner submitted that as per the provisions of Tariff Order, if the minimum average
supply to HT Industry Consumer is less than 18 hours per day during the month, demand charges
for such industry is reduced by 20%. The supply hours of 18 per day should not be increased for
this purpose.
2.8.2.3 Commission’s Views
The Commission is of the view that the current provision that if the minimum average
supply to HT Industrial Consumer is less than 18 hours per day during the month, demand charges
for such industry is reduced by 20% is appropriate.
2.8.3 Textile Industry
2.8.3.1 Stakeholder’s Comments
Shri Shakeel A. Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd., M/s Vista Alps
Industries Ltd. and some other stakeholders submitted that the textile policy for the State of
Uttarakhand was released on December 11, 2014 providing attractive subsidies and relaxations to
promote textile industry in the State comprising power bill rebate of Rs. 1 per unit and 100% relief
on electricity duty. Accordingly, textile industries in the State should be allowed power rebate of Rs.
1 per unit and waiver in electricity duty.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
22 Uttarakhand Electricity Regulatory Commission
2.8.3.2 Petitioner’s Reply
The Petitioner submitted that as per section 65 of the Electricity Act, 2003, if the State
Government requires the grant of any subsidy to any consumer or class of consumer in the tariff
determined by the State Commission, the State Government shall pay in advance the amount of
subsidy to the DISCOM. Thus, the subsidy to any industry may be given as per this provision.
As per section 3 of Uttar Pradesh Electricity (Duty) Act (Uttarakhand Adaptation and
Modification) Order, 2001, State Government is empowered to fix the rates of Electricity Duty to be
charged from various categories of consumers. Government of Uttarakhand vide its notification no.
79/I/2016-01(3)/01/2003, dated 25-01-2016 has fixed these rates applicable w.e.f. 1-01-2016. UPCL
is charging electricity duty as per the Government Orders. The Electricity duty charged from
consumers is payable by UPCL to GoU and hence, this matter may be taken up with GoU.
2.8.3.3 Commission’s Views The issue of Government subsidies/concessions and Electricity Duty does not fall under the
purview of the Commission and while fixing tariff, the Commissin is bound by the provisions of the
Act & Regulations framed thereunder.
2.8.4 Fixed/Demand Charge and Energy Charge
2.8.4.1 Stakeholder’s Comments
M/s Kashi Vishwanath Steels Pvt. Ltd. submitted that the proposed hike in demand charges
for HT Industry is on a higher side and the demand charges should be abolished.
M/s Kashi Vishwanath Steels Pvt. Ltd., M/s Kashi Enterprises and other industrial
consumers submitted that in the past, the Commission has increased energy charges by around 10-
15 paise/kVAh in each financial year. UPCL has proposed an increase of 95 paise/kVAh which is
very high and cannot be considered in present market scenario.
They also submitted that in the past, the Commission has increased demand charges by
around Rs. 10-20 /kVA in each financial year. UPCL has proposed an increase of Rs. 75/kVA. They
submitted that most the industries under this category is using more than 80% power load of their
contracted load and hence, there is no need to increase demand charges and rather the demand
charges should be abolished.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 23
SIDCUL Manufacturers Association Uttarakhand submitted that fixed charges on new
connection to industrial consumer should be reduced as the rates charged are three times of the cost
incurred.
2.8.4.2 Petitioner’s Reply
The Petitioner submitted that the justification to the proposed tariff increase has clearly been
brought out in the Petition which is to meet the revenue gap.
The Petitioner further submitted that the Electricity Act, 2003 mandates for a two part tariff
and the relevant clause is reiterated below:
“The charges for electricity supplied by a distribution licensee may include:
(a) a fixed charge in addition to the charge for the actual electricity supplied ;
(b) a rent or other charges in respect of any electric meter or electrical plant provided by the
distribution licensee.”
About 50% of the UPCL’s total costs are fixed in nature including the capacity / fixed charge
of power purchase, which should be recovered to a certain extent through fixed charges to ensure
revenue stability. Presently only 14% of revenue at existing tariff is recovered from fixed charges.
Also two part tariff exercise involves determination of fixed and energy charges to meet the
cost of supply, any reduction in fixed charges would thus, call for increase in energy charges to
match the tariff with COS.
2.8.4.3 Commission’s Views
It is a well-accepted economic principle that the fixed costs of the Utility should be
recovered to a certain extent through fixed charges to ensure revenue stability. At the same time, the
Commission recognises that if the entire fixed cost is recovered through fixed charges, then the
Utility shall have no incentive to bother about sales and, hence, quality of supply may suffer.
Historically, the fixed recovery has been done through a mix of minimum charges and fixed
charges. Levy of Minimum Consumption Guarantee Charges (MCG) is a way of ensuring minimum
revenue to the Utility from the consumers, however, if the consumption exceeds the specified units,
then no MCG charges are levied on the consumers and, entire charges recovered by the Utility are
through energy/fixed charges.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
24 Uttarakhand Electricity Regulatory Commission
The fixed charge component reflecting the fixed cost of providing the service to the
consumer and the energy charge component reflecting the cost of energy actually consumed should
ideally be taken in the two-part tariff structure.
Section 45(3) of the Electricity Act, 2003 also provides for levy of fixed charges. The relevant
Section is reproduced below:
“The charges for electricity supplied by a distribution licensee may include:
(a) a fixed charge in addition to the charge for the actual electricity supplied;
...”
Further, the licensee is incurring fixed cost directly attributable to individual consumers
such as meter reading, bill preparation, bill distribution and collection, which should ideally be
allocated to and recovered from each consumer. One of the guiding factors mentioned in Section 61
of the Electricity Act, 2003 for specifying terms and conditions of tariffs is that the tariff has to be
gradually cost reflective. Accordingly, as discussed in detail in Section 6 of the Order, the
Commission has marginally increased the Fixed/Demand Charges for various categories of
consumers.
2.8.5 Time of Day Tariff
2.8.5.1 Stakeholder’s Comments
M/s Kashi Vishwanath Steels Pvt. Ltd., Shri Ashok Bansal and some other stakeholders,
submitted that the morning peak hours should be abolished or shifted to the period between 7-9.30
AM, retain the evening peak hour charges and increase the rebate during off peak hours from 10%
to 25%. Uttarakhand Steel Manufactures Association (USMA) suggested that the peak hour rates
should be in about 15-20% higher than the normal rates in line with Other States and the rebate for
off peak hours should be increased to 20%.
Shri G.S. Bedi of Indian Drug and Pharmacueticals Ltd., USMA & M/s BST Textile Mills
suggested that the differential tariff for morning peak hours should be abolished as in other States
including Himachal Pradesh differential tariff for morning peak hours does not exist and with
morning hours continuing till 9.30 AM, it is not leaving a space for 8 hours general shift working at
normal rates in the industry.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 25
Shri Rakesh Bhatia, Uttarakhand Industrial Welfare Association & M/s BST Textile Mills
Pvt. Ltd. submitted that the night shift breakdown should be attended in the night itself which is
not happening and the morning peak hours in winter season should be abolished immediately.
Bhartiya Kisan Club submitted that Time of Day Tariff should be applicable for every
consumer category.
2.8.5.2 Petitioner’s Reply
The Petitioner submitted that the objective of introduction of ToD Tariff is to minimize the
gap between maximum (peak) demand and minimum demand and to bring the peak demand as
closer to the average demand as possible. On every reduction of this gap, the generation cost,
transmission cost and distribution cost and power cuts will be reduced and the higher demand can
be catered from the available capacity. In other words, ToD Tariff is very effective tool of demand
side management which makes possible the optimum utilization of the available capacity of
Generation, Transmission and Distribution, resulting in reduction of costs. The benefit of such
reduction in cost is passed on to the consumers. With a view to effectively implement the ToD
Tariff, substantial increase in tariff is required for consumption during peak hours.
The Petitioner further submitted that the morning peak hours have been kept only in the
winter season, i.e. from October to March of the financial year. The timings of morning peak hours
are from 06:00 hours to 09:30 hours. Morning peak hours have been provided due to heating load
and reduced generation in winter season, whereas the Air Conditioning load during summer
season in the State of Uttarakhand from 06:00 hours to 09:30 hours is negligible. Therefore, morning
peak hours in winter are required to be continued. Further, it is also worthwhile to mention here
that the own generation of Himachal Pradesh is much higher than Uttarakhand and, therefore,
imposition of peak hours in both the States should not be compared. It is submitted that Peak hour
extra charges have been kept at a rate more than the rate of rebate during off peak hours so that the
load during peak hours may be shifted to the off peak hours and normal hours. Further, the gap of
demand between normal hours and off peak hours is not too high and, therefore, keeping in view
the level of this gap, this rebate should not be increased.
The Petitioner also submitted that there is a deficit situation of electricity throughout the
day, but the quantum of deficit during peak hours is much more than the quantum of deficit during
normal hours and off-peak hours. Further, the quantum of deficit during normal hours is more than
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
26 Uttarakhand Electricity Regulatory Commission
quantum of deficit during off peak hours. In this situation, the Petitioner submitted that its priority
is to shift the demand during peak hours first to off-peak hours and, thereafter, to normal hours
thereby flattening the load curve and making the diversity factor closer to unity. Therefore, higher
tariff is needed for peak hours in order to shift the demand to off peak and normal hours. Further,
the determination of peak hour tariff is the Commissions prerogative which gives sufficient
incentive during the off peak period.
The Petitioner further submitted that as per the ToD tariff, during off-peak hours, a rebate of
10% is already allowed by the Commission for industrial category as per existing tariff, and UPCL
has followed the same approach, while proposing the ToD tariffs for the said category in its MYT
Petition. Further, any increase in the rebate during the off peak hours would require proportionate
increase in energy charges during peak/normal hours.
As regards applicability of Time of Day for all the categories, the Petitioner submitted that
presently, time of day tariff is applicable only in Industrial Category. The nature of requirement of
consumption of other categories like domestic and non-domestic category is that they cannot shift
their consumption during peak hours to any other timeslot and, therefore, ToD Tariff has not been
proposed for other categories.
2.8.5.3 Commission’s Views
The Commission has analysed the actual daily hourly load curves in the State of
Uttarakhand and has found apparent morning peak demand in the State. The Commission has
further deliberated on this issue in Chapter 6 of the Order.
2.8.6 Rostering and Load Shedding
2.8.6.1 Stakeholder’s Comments
M/s Kashi Vishwanath Steels Pvt. Ltd., Shree Karuna Jan Kalyan Samiti and Shri Harindra
Kr. Garg, Chairman, SIDCUL Manufactures Association submitted that in the State of Uttarakhand,
there is a big and old problem of un-scheduled power rostering resulting in huge hidden losses
which needs special attention. M/s Tata Motors Limited submitted that UPCL should either
arrange power from open market or declare a schedule for load shedding in advance so that
interested consumers may avail power under Open Access during peak hours. USMA submitted
that in the current year, there has been load shedding of around 6 hours and considering the overall
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 27
power supply situation in the country, there should not be any load shedding. M/s Hindustan
Glass & Industries Ltd submitted that continuous process industries that are paying additional
charge should be provided power supply without any interruption/with utilities taking planned
shutdown with advance intimation. Shri Vijay Singh Verma of Bhartiya Kisan Club submitted that
the UPCL should be made accountable for the load shedding under the tariff norms and proper
action should be taken against UPCL in case of unauthorized load shedding.
Some of the stakeholders submitted that for continuous process industries power should be
supplied without interruption and the shutdown should be planned by utilities with proper prior
intimation well in advance to the consumers.
During the hearing in Dehradun, Shri Virat Seth also mentioned that existing infrastructure
of the utilities are inadequate to meet the demand and as a result, the overloaded sub-stations are
also resulting in load shedding.
2.8.6.2 Petitioner’s Reply
The Petitioner submitted that in FY 2014-15 it has met 97% of the demand of electricity. 3%
unmet demand was due to gap in demand and availability of energy/transmission network/
distribution network. This level is also being maintained in the current year.
The Petitioner further submitted that it has prepared its power cut policy, which is as
follows:-
• Commonly, there is no powercut in the state of Uttarakhand.
• In case the demand exceeds the availability, due to Non-availability of
Transmission/Distribution system within or outside the State, etc. in such type of
emergency conditions the Power cut in the State will be according to the following
priority as shown below:
Table 2.3: Load Shedding Priority decided by UPCL Sr.No. Industrial Area Other Areas
1 Steel business/Furnace Business Rural Plain Region 2 Industries not opting for continuous supply Small Urban Plain Region 3 Industries Opting continuous Supply Large Urban Plain Region 4. -- Hilly region 5. -- Capital
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
28 Uttarakhand Electricity Regulatory Commission
• For other categories the time and day of Power cut for operation will be decided by
Director (Operation) based on the demand of electricity for respective categories.
• No load shedding will be applicable for all tourist/Pilgrimage places & hospitals
supplied electricity from independent feeders and Public Water Works.
• The power cut in any region will not exceed 14 days continuously in that region.
• It will be ensured that all the industries get a minimum of 18 hours of electricity per
day in a month.
The Petitioner furtehr submitted that there are times when there occurs certain technical &
environmental complication not in control of the Petitioner due to which there might be
unscheduled power outages. It has always been the first priority of UPCL to provide quick &
reliable services to its customers, therefore, it has taken major steps to minimize these problems &
provide continuous supply to the consumers by using new & improved state of the art technology.
2.8.6.3 Commission’s Views
In this regard, the Commission in its MYT Order dated May 6, 2013 observed that any
outage continuously been affected by the Petitioner for certain number of hours in a day for 15 or
more days shall not be considered as unscheduled/emergency outage. The Commission has also
given directions in its MYT Order dated May 6, 2013 vide which the Petitioner has to obtain prior
approval of the Commission for load shedding to be carried out continuously for certain number of
hours in a day for 15 or more days. Further, in case, during any month if the average supply hours
are less than 18 hours per day for HT Industry, then in that case HT Industrial consumers shall
charged only 80% of the applicable demand charges as per rate schedule.
2.8.7 Load Factor based Tariff
2.8.7.1 Stakeholder’s Comments
Shri R. S. Yadav of M/s India Glycols Limited & M/S BST Textile Mills Pvt. Ltd., submitted
that the load factor based tariff should be abolished or reviewed/modified and charged in
proportionate to consumption in each slab. Shri Kumar Gupta, Shri Achal Sharma, Shri
Rudramurthy N and Shri Ashok Bansal submitted that load factor based tariff to HT industries is
penalizing them with consumption within their contracted demand being charged in the higher slab
of energy charges on whole of their consumption. This approach is most unscientific and illogical.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 29
Further, the Commission has devised the following formula for the calculation of the load factor as
follows:
In this regard, they suggested that the above formula does not allow consumer for the
consumption for load factor based on the contracted load if the consumer is running load less than
its contracted load and paying demand charges for 80% of contracted load and thus, is consuming
less power than at the contracted load. On this account, a consumer using less maximum demand
than the contracted demand but paying demand charges for minimum 80% of contracted load is
subjected to higher energy charges for the high load factor based on his actual low maximum
demand even without consuming power for the minimum billable demand. A consumer is legally
entitled to consume power upto the contracted demand or at least for billable demand if it is less
than the contracted demand in lowest load factor slab. In the present tariff structure there are cases
when consumers being billed for MCG units in a month are made to pay higher energy charges
based on their load factor above 33% or 50%. This anomaly can be rectified by revising the formula
for calculation of load factor as follows:
M/s Kashi Enterprises Limited submitted that if the consumer draws maximum power with
the same Contract demand, licensee's average power purchase cost which can be passed on to the
consumer average tariff will automatically get reduced and, therefore, the gain on account of
reduction of average power purchase cost can be passed on to the consumer through load factor
incentive. Higher load factors also result in maximum utilization of transmission and distribution
assets, thus, resulting in average lower costs for the licensee.
Shri Ashok Bansal, Kumaon Garhwal Chamber of Commerce and Industry made the
following submissions on the issue of load factor based tariff:
a) The Load Factor Tariff is increasing cross subsidy.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
30 Uttarakhand Electricity Regulatory Commission
b) The existing load factor based tariff penalizes the industries with incremental
consumption within its contracted demand upto 100% load factor by way of higher
energy rates on whole of the consumption for load factor above 40% and further for
load factor above 50%. Such an approach is clearly one sided and completely ignores
the interest of the consumers who are supposed to consume power for the load, they
have contracted with the licensee. Increase of rate of energy charge for higher load
factor is without any basis.
c) The load factor based tariff to HT industries is penalizing them with incremental
consumption within their contracted demand being charged in the higher slab of
energy charges on whole of their consumption. This approach is most unscientific
and illogical. Even if load factor based tariff is imposed, it should provide telescopic
basis for charging incremental consumption beyond specified load factor limit on
higher rates instead the existing provision and the practice of charging the whole
consumption at higher rate of energy charge for the particular load factor slab.
d) The existing formula for calculation of load factor should be replaced by the
following:
Load factor =
M/s Khatema Fibres Ltd. & M/s East West Products Limited submitted that Calculation of
Load Factor should be based on billable demand and not on contracted demand.
2.8.7.2 Petitioner’s Reply
The Petitioner submitted that as per Section 62(3) of the Electricity Act, 2003, tariff may be
differentiated on the basis of consumer’s load factor. Further, it is submitted that higher energy
charges are levied for higher consumption due to the fact that the State is power deficit and deficit
power is procured at a rate higher than the average rate of firm power. Secondly, at higher load
factor demand charges per unit is reduced which is the incentive to the consumer for having higher
load factor.
The Petitioner further submitted that the Load Factor formula is based on the actual
requirement of load of the consumer. In case maximum demand is lower than the contracted load,
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 31
maximum demand (actual requirement) is considered. In case maximum demand is higher than the
contracted load, contracted load is considered because the consumer has contracted this capacity.
The Petitioner also submitted that as per the provisions of Tariff Policy, the tariff of
subsidizing categories may be kept at cost plus 20%. The Tariff of HT Industry Category has been
proposed at cost plus 14.58%. Thus, the proposed Tariff is as per the provisions of law. Moreover,
the cross subsidy for this category has not been increased in the proposal. Hence, it is not correct to
say load factor based tariff is increasing cross subsidy.
The Petitioner further submitted that Load Factor formula is based on the actual
requirement of load of the consumer. In case maximum demand is lower than the contracted load,
maximum demand (actual requirement) is considered. In case maximum demand is higher than the
contracted load, contracted load is considered because the consumer has contracted this capacity.
2.8.7.3 Commission’s Views
The Commission has deliberated on this issue in Chapter 6 of the Order.
2.9 Railway Traction
2.9.1.1 Stakeholder’s Comments
Shri Pramod Kumar of Northern Railways submitted that the tariff increase proposed by
UPCL is the steepest and will give tariff shock to the consumer like railways. He further submitted
that Railways have been making timely payment, drawing uninterrupted uniform supply day and
night, contributing negligible technical and commercial losses, etc. and hence, the tariff for Railways
should not be increased and should be commensurate with the average cost of supply. He further
submitted that the overall revenue gap estimated by UPCL to be recovered for FY 2016-17 is Rs.
1220.26 Crore. An average tariff hike of 24.96% has been proposed to cover this revenue gap. This
revenue gap should be supported by Government subsidy and tariff of railways should not be
increased.
He further submitted that Tariff Order, 2005 issued by Hon’ble Rajasthan State Electricity
Regulatory Commission, provides for rebate of 5% on railway traction tariff and the same should be
made applicable.
He also submitted that in case of incoming supply failures, Railway have to extend the feed
of Roorkee/TSS being fed by UPCL in the feeding zone of failed TSS being fed by HVPN/UPPCL
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
32 Uttarakhand Electricity Regulatory Commission
and have to pay load violation charges for exceeding the sanctioned contract demand for the
circumstances, whenever there is supply failure from HVPN/UPPCL till such time the supply
failure persists. Further, it submitted that railways takes supply from UPCL for traction purpose at
220 kV at Roorkee/TSS. Railway have to pay load violation charges on exceeding the sanctioned
contracted demand.
As regards metering, he submitted that as per Regulation 7(b)-I of the Central Electricity
Authority (Installation and Operation of Meters) Regulation 2006, the consumer meter shall be
installed by the licensee either at consumer premises or outside the consumer premises. In case of
railway traction consumer premises is Railway traction sub station. Therefore, meters should be
installed on the railway traction substation instead of grid sub-station of UPCL. He also requested
to consider the provision of simultaneous maximum demand of all adjacent metering points and
also of making single agreement for all adjacent supply points for future Railway Traction sub-
stations in Uttarakhand.
He suggested that for Demand Charges, the Billing Demand should be 65% of the contract
demand or recorded demand during the month, whichever is higher for traction load as in
Haryana.
He suggested that Railways must be exempted from payment of ACD/security deposit and
if not then Railways may be allowed the payment in form of Letter of assurance from RBI.
2.9.1.2 Petitioner’s Reply
The Petitioner submitted that as per the provisions of Electricity Act, 2003 and Tariff Policy,
the tariff of all the categories should be determined at Average Cost of Supply keeping the cross
subsidy of subsidizing category at 20%. Accordingly, Tariff of all the categories has been proposed
and Tariff for Traction Category cannot be kept equivalent to Average Cost of Supply. Presently,
voltage wise / category wise losses are not available and Category wise Tariff has been calculated
on the basis of average cost of supply and permissible level of cross subsidy. This is as per
Regulation 91 of the UERC Tariff Regulations, 2015. The issue of subsidy may be taken up with the
State Government. There is no provision in the Electricity Act to provide any rebate to a new
consumer. However, all the consumers in Uttarakhand are automatically being compensated by
way of cheaper electricity as compared to other States.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 33
On the issue of load violation charges, the Petitioner submitted that as per the existing rate
schedule, in case of consumers where electronic meters with MDI have been installed, if the
maximum demand recorded in any month exceeds the contracted load/demand, such excess
load/demand shall be levied twice the normal rate of fixed/demand charge as applicable. The
submission of consumer cannot be considered, since the power failure at TSS not falling in the area
of distribution licensee is not the responsibility of the licensee. The consumer should take up this
matter with the concerned licensees.
Regarding installation of meters, the Petitioner submitted that Regulation 2(2)(a) of the
Central Electricity Authority (Installation and Operation of Meters) Amendment Regulations, 2010
provides that the consumer meter shall be installed by the distribution licensee either at the
consumer premises or outside the consumer premises. Hence, it is the discretion of distribution
licensee to provide the meter either at consumer premises or outside the consumer premises. UPCL
has installed the consumer meter at Grid substation, i.e. outside the consumer premises. This is as
per the provisions of law. As per the provisions of existing Tariff Order, single point supply is
allowed to any consumer and, therefore, sum of maximum demand recorded at two or more meters
should not be considered.
As regards the billing demand to be kept at 65%, the Petitioner submitted that about 50% of
UPCL’s cost is fixed in nature while recovery from fixed charges is about 15% and, therefore,
reduction in billable demand from 80% to 65% would further reduce the recovery of fixed charges
which should be avoided in a mandate of two part tariff. Further, in case demand charges are
reduced, the energy charges will have to be increased in order to have the composite tariff
equivalent to the cost of supply and the desired level of cross subsidy.
On the issue of Security Deposit, the Petitioner submitted that the Security deposit is
received from the consumers to securitize the credit sales made by the DISCOM. In case a consumer
defaults in making the payment of his electricity bills, the recovery of such electricity dues may be
made by adjusting the security deposit of the consumer. As per Section 47(4) of the Electricity Act,
2003, the Distribution Licensee is required to pay interest on the security deposit. As interest cannot
be paid on the money held with UPCL as Bank Guarantee/Letter of Credit, the security deposits
should only be in the form of cash/bank draft.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
34 Uttarakhand Electricity Regulatory Commission
2.9.1.3 Commission’s Views
The reply of the Petitioner on subsidy, security deposit etc. is in accordance with the
provisions of the Act, CEA Regulations, and Orders of the Commission. However, w.r.t. tariff hike
as discussed earlier, based on the approved ARR for FY 2016-17 including impact of truing up for
FY 2014-15, the Commission has marginally increased the tariff to meet the projected revenue gap
as discussed in detail in Chapter 6 of the Order. Further, continuing with the approach adopted in
previous years, the Commission has attempted to reduce the cross-subsidy while desiging the
tariffs for various categories as elaborated in Chapter 6 of the Order.
The Commission does not find UPCL’s response in the matter of installation of consumer
meter at the grid sub-station satisfactory and in continuation of the directions issued by the
Commission in its previous Tariff Orders, UPCL is directed to submit a compliance report in this
regard within one month of the date of Order.
2.10 Fixed Charges
2.10.1.1 Stakeholder’s Comments
Shree Karuna Jan Kalyan Samiti and other stakeholders requested the Commission to
abolish the fixed charges. M/s Shiv Shakti Electricals submitted that the Fixed Charges should only
be applicable for consumers whose premises are locked for certain period of time and not on all the
consumers.
Shri Rakesh Bhatia, Uttarakhand Industrial Welfare Association submitted that Fixed
charges should not be increased as infrastructure is already available with UPCL and there is no
increase in cost and whatever they are increasing they are claiming depreciation on it which is also
a profit of UPCL.
2.10.1.2 Petitioner’s Reply
As regards levy of Fixed Charges, the Petitioner submitted that Section 45(3) of the
Electricity Act, 2003, stipulates for levy of fixed charges as follows:
“The charges for electricity supplied by a distribution licensee may include:
(a) a fixed charge in addition to the charge for the actual electricity supplied ;
(b) a rent or other charges in respect of any electric meter or electrical plant provided by the distribution
licensee.”
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 35
About 50% of the UPCL’s total costs are fixed in nature including the capacity / fixed charge
of power purchase, which should be recovered to a certain extent through fixed charges to ensure
revenue stability. Hence, levy of fix charge is necessary and as per the provisions of law.
The Petitioner further submitted that the Fixed Charges are based on the cost of the
Company other than variable power purchase cost. On the basis of projected such cost, increase in
fixed charges have been proposed. Further, depreciation is not a profit of the Company rather it is
the recovery of fixed cost already incurred by the Company.
2.10.1.3 Commission’s Views
The Commission has already expressed its views on the levy of fixed charges in para 2.8.4.3
above & in Chapter 6 and is not reiterating the same again.
The Commission does not agree with the views of the stakeholder that the Fixed Charges
should only be charged when the premises is locked as in two part tariff structure Fixed Charge is
also one component of tariff which is required to be recovered from all consumers to meet the total
revenue requirement of the Utility and the category-wise tariffs are designed accordingly as
discussed in detail in Chapter 6 of the Order. The Commission also does not agree with the view of
the Stakeholder that fixed cost of the Petitioner is not increasing. All types of fixed costs are linked
to inflation/index and they are bound to increase.
2.11 Minimum Consumption Guarantee (MCG)
2.11.1.1 Stakeholder’s Comments
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that UPCL
has not projected revenue receipt on account of MCG. As per the past data, this amount is very low
and it causes heavy burden on the consumers paying MCG. In respect of Cross Subsidy to be within
the range of target latest by the end of year 2010-11, tariffs are within ± 20% of the average cost of
supply. In case of LT, the Tariff is as high as 100% in some cases being subjected to MCG. MCG
would result in wastage of power as the consumer is left with no incentive to save power. As most
of the LT industries are paying MCG, this is resulting in unnecessary extra burden on them. It
requested that the MCG be removed in the current Tariff fixation.
Shri Mahesh Sharma of Uttarakhand Industrial Welfare Association submitted that the
minimum Consumption Guarantee should be abolished.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
36 Uttarakhand Electricity Regulatory Commission
Shri Ashok Bansal submitted that the Commission had abolished MCG from Consumers in
the Tariff Order for FY 2005-06. Thereafter, in the Tariff Order dated 18.03.2008 the Commission had
again introduced monthly minimum consumption charges over and above the fixed
charges/demand charges on the industrial consumers which has been retained upto the last Tariff
Order for FY 2014-15. The rationale given by the Commission for introducing MCG charges was
deficiency in billing data of the licensee. This clearly indicate that the industrial consumers are
being burdened with an additional charge to compensate the inefficiency of UPCL in ensuring
proper meter reading and billing of its consumers. Ideally, the Commission should have directed
the distribution utility to improve its internal mechanisms to ensure prompt meter reading, billing
and diligent recovery of the bills.
2.11.1.2 Petitioner’s Reply
The Petitioner submitted that the levy of Minimum consumption guarantee is not on the
account of poor billing but for the recovery of minimum fixed charges. In this regard, Section 45(3)
of the Electricity Act, 2003, stipulates for levy of fixed charges as follows:
“The charges for electricity supplied by a distribution licensee may include:
a fixed charge in addition to the charge for the actual electricity supplied ;
a rent or other charges in respect of any electric meter or electrical plant provided by the
distribution licensee.”
About 50% of the UPCL’s total costs are fixed in nature including the capacity/ fixed charge
of power purchase, which should be recovered to a certain extent through fixed charges to ensure
revenue stability. Levy of minimum consumption guarantee charge is a way of ensuring minimum
revenue to the licensee from the consumers.
The Petitioner further submitted that the MCG has been proposed at very low level of
consumption i.e. at 6.85% load factor in respect of non-domestic category and LT industry category
and at 13.70% in respect of HT industry category. In case during certain month, actual consumption
is less than MCG, MCG is charged in those months. Any excess of billed consumption (actual
consumption or minimum consumption, whichever is higher) is adjusted at the end of the financial
year.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 37
The Petitioner further submitted that while computing the Revenue for FY 2016-17, it has
also considered revenue from MCG as follows:-
• RTS - 2 - Rs. 8.35 Crore
• RTS - 7 - Rs. 34.86 Crore
2.11.1.3 Commission’s Views
Historically, the fixed cost recovery has been done through a mix of minimum charges and
fixed charges. Levy of Minimum Consumption Guarantee Charges (MCG) is a way of ensuring
minimum revenue to the Utility from the consumers, however, if the consumption exceeds specified
units, then no MCG charges are levied on the consumers and, entire charges recovered by the
Utility are through energy/fixed charges. The Commission has, further, deliberated on this issue in
Chapter 6 of the Order.
2.12 Delayed Payment Surcharge (DPS)
2.12.1.1 Stakeholder’s Comments
M/s Kashi Vishwanath Steels Pvt. Ltd., submitted that the current rate of DPS @ 1.25% per
month even for one day delay is very high in current economic scenario. They proposed the DPS
should be charged on pro-rata basis @ 0.75% if the payment is made within 15 days after the due
date and @ 1% if the payment is made after 15 days from the due date.
During the hearing in Dehradun, Shri V.S. Bhatnagar & Shri Vishwamitra pointed out that
the Scheme of Waiver of DPS introduced by UPCL is unjust for honest consumers who pay their bill
in time.
2.12.1.2 Petitioners Reply
The Petitioner submitted that the Delayed Payment Surcharge is the cost of money not
received by UPCL in time. This surcharge is also levied with a view to discourage the consumers
who do not pay their bills within due date.
The Petitioner further submitted that the Delayed Payment Surcharge in Uttarakhand is
lower than that charged by other utilities in across states and provided the DPS applicable in few
other Staes as follows:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
38 Uttarakhand Electricity Regulatory Commission
Table 2.4: Delayed Payment Surcharge applicable in Other States State DPS
Haryana 1.5 % on unpaid amount of the bill for each 30 days successive period or part thereof until the amount is paid in full.
Uttar Pradesh 1.5% per month on unpaid amount Delhi 1.5% per month on unpaid amount
2.12.1.3 Commission’s Views
The Commission is of the view that the objective of Delayed Payment Surcharge is to recover
the cost of funds for delayed payment by the consumers, and the main objective of DPS is to act as
deterrent so that the consumers pay their bill on time. The Commission agress to the submission
made by the stakeholders that the Scheme for Waiver of DPS gives a wrong message to the honest
consumers. UPCL is advised to refrain itself from allowing such schemes & infact should be
cautious to recover its dues from the consumers in time.
2.13 Rebate and Incentives
2.13.1.1 Stakeholder’s Comments
Shri Pramod Singh Tomar of M/s Galwalia Ispat Udyog Pvt. Ltd. and Shri Shakeel A.
Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted that the voltage rebate proposed
for 33 kV feeder supply is 1.5% as against existing 2.50% and for 132 kV feeder supply is 5% against
existing 7.5%. UPCL has proposed lower voltage rebates in comparison to the existing voltage
rebates comparing the voltage rebates in other States. Voltage rebate is a technical issue which is to
compensate for lower transmission losses. The difference between input energy and billed energy is
primarily on account of transmission losses. The loss of 17.29% for FY 2016-17 is average across all
the consumer categories. For 33 kV and 132 kV feeder supply, losses shall be minimal. The voltage
rebates for 33 kV and 132 kV feeder supply should be 5% and 12.5% respectively.
M/s Kashi Vishwanath Steels Pvt. Ltd., and M/s Kashi Enterprises submitted that the
industrial consumers at independent feeders, are making huge investments in construction of
33/132/220 kV substation, which later on becomes the property of the Discom. These independent
feeders gives huge benefit to distribution licensee as losses on these feeders are around 1% as
against 18-19% in case of industries which are not connected on independent feeder. They requested
the Commission to approve a rebate of 10% on energy charges for industries connected on an
independent feeder at 33 kV/132 kV/220 kV.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 39
M/s Tata Motors suggested to increase the voltage rebate from existing level of 7.5% to
12.5% for 220 kV consumers.
M/s India Glycols Limited submitted that the high voltage rebate for 132 kV and above
should not be reduced, rather it should be increased from 7.5% to 10% as the line losses in 132 kV
and above as proposed by PTCUL is only 1.80% and combined loss of UPCL should not be
burdened on the consumers who are not a part of the distribution system. They further submitted
that the details of voltage wise loss have not been given by UPCL, inspite of repeated directions by
the Commission and hence, the Commission should direct UPCL to give the same to arrive at
higher rebate and to determine voltage wise Tariff.
M/s BST Textile Mills Pvt. Ltd., submitted that the voltage rebate proposed for 33 kV
customers should be increased to 5% from the current rebate of 2.5%.
M/s Khatima Fibres Ltd, M/s East West Products Ltd. and Shri Ashok Bansal, President,
Kumaun Garhwal Chamber of Commerce Industry submitted that the Commission in its Tariff
Order dated 25.04.2005 had provided the high voltage rebates to the consumers on rate of charge
(demand and energy charge) as follows:
(a) LT Consumers - 5% for supply voltage at 11 kV.
(b) HT Consumers - 2.5% for supply voltage at 33 kV, 5% for supply voltage above 33
kV, i.e. for 132 kV and 220 kV.
In the next Tariff Order, the Commission linked the H.V. rebate mechanism to systems
technical requirement ignoring the fact that the tariff therein was not reflecting cost of supply at
different voltages but was being computed on average cost of supply. Based on the
comments/objections on subsequent Tariff Proposals, the Commission restored the HV rebates
partially on rate of charge in its Tariff Order dated 06.05.2013 as under:
(a) LT Consumers - 5% for supply voltage above 400 Volts and upto 11 kV.
(b) HT Consumers – 1.5% for supply voltage of 33 kV, 5% for supply voltage of 132 kV
and 220 kV.
Thus, the Commission while restoring previously admissible rebates of other supply
voltages, the rebate for 33 kV voltage was reduced to 1.5% without any justification for such a
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
40 Uttarakhand Electricity Regulatory Commission
change. On being pursued further, the Commission in the last Tariff Order provided for H.V.
rebates on energy charge instead of rate of charge (demand and energy charge) as follows:
(a) LT consumer - 5.0% for supply voltage above 400 Volts and upto 11 kV.
(b) For HT consumer - In case of supply at 33 kV voltage rebate of 2.5% on energy
charge and for supply at 132 kV and above voltages, 7.5% on the energy charge.
Thus, the Commission increased the rebate of HT consumers of 33 kV and above, but made
it admissible only on energy charge while previously it was admissible on rate of charge. Therefore,
the Commission is requested to review the matter and allow HV rebates on rate of charge, i.e.
demand and energy charge instead of energy charge only.
Shree Karuna Jan Kalyan Samiti, Shri Mukesh Chandra and some of the stakeholders
suggested that special rebate should be given to consumers using CFLs, LEDs and other non-
conventional sources of energy.
Shri G.S. Bedi of Indian Drugs and Pharmacueticals Ltd. suggested considering a
rebate/incentive for consumers directly connected to PTCUL substations on account of reduced line
losses. Supply switch gear located in PTCUL for IDPL is separated only by a boundary wall from
IDPL substation receiving supply. He further submitted that Rebate/incentive for reactive power
management by keeping very high PF in case of RTS-8 based on kW/kWh billing be considered to
encourage consumers as it offloads UPCL system from reactive power.
Shri Vishwamita and some of the stakeholders suggested that incentive should be applicable
on timely payment of bills.
2.13.1.2 Petitioner’s Reply
The Petitioner submitted that rebate for taking supply at higher voltage was revised by the
Commission in its Tariff Order dated April 10, 2014 from 1.5% and 5% to 2.5% and 7.5% for taking
supply at 33 kV and 132 kV and above respectively. The Petitioner believes that voltage rebate
approved by the Commission is very high and was done without hearing the Petitioner’s view
point and hence, it has proposed to keep the rates of rebate which were applicable in FY 2013-14.
The Petitioner also submitted that the proposed rates of rebates are higher than the rebates
applicable in neighbouring States like Madhya Pradesh, Haryana, Delhi and Punjab.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 41
The Petitioner submitted that the consumers using CFLs/LEDs are automatically awarded
in terms of reduced bills, on account of reduced consumption due to CFLs/LEDs. Further, it is to
inform that a scheme for distribution of LED Bulbs has been started in the State. Under the scheme
all domestic consumers and non – domestic consumers (upto 10 kW load) are being provided three
LED Bulbs at a very low cost of Rs. 110 / bulb. This cost also is being subsidized by State
Government by 75% in respect of BPL consumers and 25% in respect of domestic consumers having
consumption upto 100 units/ month.
As regards rebate for consumers directly connected to PTCUL substations, the Petitioner
submitted that the rebate for supply at 132 kV or above voltage has been proposed @ 5% of energy
charges.
On the issue of rebate/incentive for reactive power management, the Petitioner submitted
that the tariff is determined keeping in view the fact that the consumer will maintain a healthy
power factor.
2.13.1.3 Commission’s Views
The Commission in its Order dated April 10, 2014 considering the requests made by various
stakeholders & UPCL’s response on the same, modified the provisions of voltage rebate and the
Commission feels that the provisions of the prevalent voltage rebate are appropriate.
As regards incentive for reactive power management, the Commission has been providing
for kVAh based tariff for industries in its Tariff Orders which covers the benefit of incentive as
suggested by the respondents.
As regards the suggestion for incentive for timely payment, the Commission has already
dealt with the matter in its Tariff Order for FY 2003-04 which is being reproduced as under:
“The Commission finds that consumers already enjoy sufficiently long credit for the supplies made to
them. Petitioner has intimated the Commission that even for consumers being billed on monthly basis
the time lag between the first day of supply and actual payment is about two months, resulting in
interest free credit for an average period of 45 days for the entire billed amount. For consumers being
billed once in two months the interest free credit period works out to around two months. This
existing arrangement itself is quite generous and no further concessions seem called for. Allowing
consumers rebate for timely payment and booking the cost of it on tariff through expenses incurred,
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
42 Uttarakhand Electricity Regulatory Commission
gives no real advantage to consumers and is only an exercise of smart packaging. The Commission has
therefore decided to do away with the system of rebate for timely payment of the bills by consumers.”
The above views of the Commission are relevant even in today’s context.
2.14 Energy Sale Forecast
2.14.1.1 Stakeholder’s Comments
M/s Kashi Enterprises submitted that UPCL has presented CAGR of 3.64% from FY 2011-12
to FY 2015-16 for HT Industrial category and 4.39% for all category of consumer. They submitted as
no new concessional scheme is running in the State, it would be appropriate to consider a growth of
1-2% for HT category and 2-3% increase in overall consumption as against overall 6-7% increase
proposed by UPCL.
Shri Ashok Bansal, (President, Kumaon Garhwal Chamber of Commerce Industry), Shri L.S.
Chamyal , Shri Achal Sharma and M/s Khatema Fibres Ltd. submitted that as per the actual energy
consumption, the licensee has reported the State’s energy consumption CAGR of 9.09% over the last
few years and has assumed it to grow in future at the same trend. However, the energy sales for LT
and HT consumer are over projected at the growth rate of 4.15% for LT industry and 5% for HT
industry. He further submitted that the growth rate of energy sales may not be more than 30% of
growth in past for industries and 5% for other categories.
Shri Ashok Bansal (President, Kumaun Garhwal Chamber of Commerce Industry), Shri L.S.
Chamyal, Shri Achal Sharma submitted that the growth rate of 3% for various categories as per the
current trend appears reasonable as compared to 4.75% and 5.47% assumed by the Petitioner for LT
and HT industries respectively.
They also submitted that there is also an over estimation in the growth of number of
industrial consumers which must be corrected to 2.5% as per existing trend. For other categories
annual growth rate may be reasonably considered as 5% as against projection from 5.55% to 8.23%
for other categories by the licensee.
2.14.1.2 Petitioner’s Reply
The Petitioner submitted that the sales for HT category have been projected at the rate of
5.00% each year which is a decent rate as compared to the trends observed in previous years. The 4
& 5 year CAGR is observed to be 7% and 10% respectively. The Petitioner while taking on
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 43
assumption has tried to be as conservative as possible, and thus, a rate of 5% has been assumed for
increase in HT sales. Similarly for other categories, the Petitioner while taking assumptions has
tried to be as realistic and astute as possible.
The Petitioner further submitted that accurate sales estimation is very important while
estimating the annual revenue requirement. For the same, the Petitioner has tried to estimate the
energy sales utilizing three methods
• Estimation of Sales as per draft 18th EPS;
• Estimation of Sales based on Econometric Model;
• Estimation of Sales based on Adjusted trend Analysis (CAGR)
The sales figures arrived at from each of these models were discussed in detail and based on
the existing scenarios, the authenticity of estimation of base variables and the informed judgments
as already explained in MYT petition, it was decided that the best method shall be the estimation of
sales based on adjusted trend Analysis.
2.14.1.3 Commission’s Views
The Commission has duly scrutinised and analysed the sales projected by the Petitioner for
the second Control Period and has approved the category-wise sales based on past trends including
recent trends and considering the other factors submitted by the Petitioner and other stakeholders
as elaborated in Chapter 3 of the Order. Further, the Petitioner in its Petition has projected restricted
sales (i.e. presuming load shedding in the State), but the Commission is of the view that for
planning purposes, the sales projections should be unrestricted sales and, accordingly, the
Commission has projected the unrestricted sales for the next Control Period.
2.15 Cost of Supply and Cross Subsidy
2.15.1.1 Stakeholder’s Comments
Shri Ashok Bansal, KGCCI submitted that UPCL has not submitted the voltage wise cost of
supply. Shri Pramod Singh Tomar of M/s Galwalia Ispat Udyog Pvt. Ltd. and Shri Shakeel A.
Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted that Section 61 of the Electricity
Act, 2003 stipulates that tariff should progressively reflect cost of supply of electricity. The study
conducted by UPCL to determine cost of supply based on which the tariff proposal has been made,
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
44 Uttarakhand Electricity Regulatory Commission
should be shared with public. UPCL should also submit how the proposed tariff shall reduce cross
subsidy. Some of the stakholders suggested linking the category-wise tariffs to averge cost of
supply. Shri R.S. Yadav of M/s IGL submitted that cross-subsidy should be reduced.
They also asked as to how the tariff proposed is helping in reducing cross subsidy.
2.15.1.2 Petitioner’s Reply
The Petitioner submitted that presently, voltage wise / category wise losses are not available
and Category wise Tariff has been calculated on the basis of average cost of supply and permissible
level of cross subsidy. This is as per Regulation 91 of the UERC Tariff Regulations, 2015. The
Petitioner further submitted it is in the process to calculate the voltage wise cost of supply and will
be able to file the next ARR on the basis of the same. The Petitioner further submitted that the
existing and proposed cross subsidy levels have been maintained for each category as follows:-
Table 2.5: Existing and Proposed Levels of Cross-subsidy submitted by UPCL S. No. Category Existing Proposed
1. Domestic -32.74% -32.59% 2. Non Domestic 15.19% 15.15% 3. Public Lamps -0.89% -0.68% 4. Private Tube Wells -68.86% -68.89% 5. Govt. Irrigation System 1.85% 1.97% 6. Public Water Works 2.07% 1.80% 7. Industry LT Industry 14.66% 14.70% HT Industry 14.80% 14.58%
8. Mixed Load -3.64% -4.22% 9. Railway Traction 10.55% 20.87%
The Petitioner, further, submitted that as per the provisions of Tariff Policy, the tariff of
subsidising categories may be kept at cost plus 20%. The tariff of HT Industry Category has been
proposed at cost plus 14.58%. Thus, the proposed Tariff is as per the provisions of law. Moreover,
the cross subsidy for HT Industries has not been increased in the proposal.
2.15.1.3 Commission’s Views
The issue of level of cross-subsidy across various categories of consumers and increase in
tariffs has been deliberated by the Commission in Chapter 6 of the Order.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 45
2.16 Continuous Supply
2.16.1.1 Stakeholder’s Comments
Shri Shakeel A. Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. & M/s Galwalia
Ispat Udyog (P) Ltd. submitted that continuous process industry (as well as non-continuous process
industrial consumers) provides demand visibility to UPCL and thus, it is easier for UPCL to have a
back to back long term power purchase agreements. A generalized commercial principle is that
consumers which guarantee a certain amount of off take are provided concessional rate. In contrary,
additional charge is being imposed on continuous process industry. The additional charge should
be removed or subsidized for continuous process industry as well as non-continuous process
industrial consumers connected on either independent feeders or industrial feeders enjoying
continuous supply as it is contrary to commercial principles.
Shri R.S. Yadav of IGL, M/s Hindustan Glass & Industries Ltd. & Shri V.K. Agarwal
submitted that the Continuous Supply Surcharge (CSS) should be reduced to 10% from the existing
level of 15% and further reduce it to nil in next 3 to 5 years.
Shri Ashok Bansal, Kumaon Garhwal Chamber of Commerce and Industry submitted that
the Electricity Act, 2003 does not allow the Commission to differentiate consumers by the hours of
supply or consumers subjected to load shedding and CSS should be reduced to 10%. He, further,
submitted that the compensation should be provided in case of interruptions in continuous supply.
M/s Khatema Fibres Ltd. & M/s East West Products Ltd. Submitted that compensation
should be provided in case of interruptions in continuous supply of power. Shri Mahesh Sharma of
Uttarakhand Industrial Welfare Association submitted that option of continuous supply should be
discontinued and if provided should be given with a surcharge of 15%.
2.16.1.2 Petitioner’s Reply
The Petitioner submitted that following are the provisions, which proves that levy of higher
energy charges is absolutely necessary in accordance with the provisions of the law:
Para-5.5.1 of National Electricity Policy – “There is an urgent need for ensuring recovery of cost of
service from consumers to make the power sector sustainable.”
Para-8.2.1(1) of Tariff Policy – “……Consumers, particularly those who are ready to pay a tariff
which reflects efficient costs have the right to get uninterrupted 24 hours supply of quality power…”
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
46 Uttarakhand Electricity Regulatory Commission
The Petitioner, further, submits that extra energy charge for continuous supply is charged
from the consumers who have opted for continuous supply. These consumers are exempted from
load shedding during scheduled/unscheduled power cuts and during restricted hours of the period
of restriction of usages approved by the Commission from time to time. However, load shedding
required due to emergency break-down / shut-down is imposed on these consumers as and when
the situations arise.
The Petitioner further submitted that the purchase of power over and above the availability
from firm sources is, inter-alia, required to give continuous supply to the desired industries and,
therefore, keeping in view the rates of electricity in the open market and increase in rates of UI
overdrawl, continuous supply surcharge is required for giving continuous supply and it cannot be
kept below 15% of Energy Charges throughout the year.
As regards compensation for interruptions in continuous supply, the Petitioner submitted
that Industries who have been opted continuous supply are being given continuous supply and no
rostering/power cuts are imposed on them except load shedding required due to emergency
breakdown/ shutdown. Thus, there is no need for compensation to the consumers.
2.16.1.3 Commission’s Views
The issue of continuous power supply and surcharge thereof alongwith other terms and
conditions w.r.t. continuous supply has been deliberated by the Commission in Chapter 6 of the
Order.
2.17 Components on ARR and Revenue
2.17.1 Power Purchase Cost
2.17.1.1 Stakeholder’s Comments
M/s Tata Motors and Uttarakhand Steel Manufacturers Association (USMA) suggested that
the power purchase cost for Central Generating Stations is decreasing due to decrease in coal prices
and, therefore, the tariffs should not be increased.
USMA suggested that the cess for UJVN Ltd. stations should be discontinued.
Shri Ashok Bansal of KGCCI suggested that projected availability of power from various
sources may be checked by the Commission.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 47
M/s Asahi India Glass Ltd. submitted that the power purchase cost from outside the State
source is very high and explanations are not given for certain power purchase figures. They
submitted that there must be separate energy audit to ascertain the facts.
M/s KVS Infratech LLP submitted that UPCL has projected power consumption of 10863
MU for FY 2016-17 and availability of 10184 MU from all the sources. As the availability of power is
adequate to meet the requirement for FY 2016-17, there is no need to purchase power from other
sources at a higher rate.
M/s Kashi Vishwanath Steels Pvt. Ltd. and M/s Kashi Enterprises submitted that UPCL is
purchasing very small quantity of power through open market purchase and suggested that UPCL
should purchase maximum power in peak hours from open market at a cheaper cost to reduce the
overall deficit. M/s Kashi Vishwanath Steels Pvt. Ltd. submitted that UPCL has projected the power
purchase from new generating stations of Central Sector @ Rs. 5/kWh, which is very high.
Shri Rakesh Bhatia, Uttarakhand Industrial Welfare Association submitted that the average
power purchase rates from THDC appears higher.
2.17.1.2 Petitioner’s Reply
The Petitioner submitted that it is not correct to say that the cost of NTPC Power is being
reduced. The average power purchase price of NTPC Power is around Rs. 3.25/unit this year which
is similar with the rate of previous year. Further, the availability of power from firm sources is not
being increased in the proportion of increase in demand. The deficit of power is increasing every
year and the rate of deficit power to be procured from open market is high as compared to the rate
of firm power. Therefore, weighted average rate of power for the coming years is going to be high
and, accordingly, the power purchase cost has been proposed.
As regards applicability of cess for UJVN Ltd. stations, the Petitioner suggested that this
matter may be taken up with Government of Uttarakhand.
The Petitioner further submitted that the power purchase cost has been projected for each
source individually. The power purchase cost for CSGS stations has been projected based on the
rates approved by the CERC and in case the cost has not been approved by CERC suitable
assumptions has been taken in order to project the cost. Similarly, the cost from other stations, i.e
state generation and IPP’s has been projected after considering suitable assumptions.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
48 Uttarakhand Electricity Regulatory Commission
On the issue of power availability, the Petitioner submitted that the sales projected for FY
2015-16 are 10227 MU and not 9654 MU. 9654 MU are the actual sales for FY 2014-15. Thus, the sales
for FY 2016-17 are only 6.21% higher which is nominal in regard to the increasing demand and the
trend observed in previous years. Also, since the demand for FY 2016-17 is higher than the
availability, the Petitioner is compelled to procure power from short term market.
As regards the procurement of power through open market, the Petitioner submitted that it
is very important for a distribution utility to have a right mix of short and long term power. It is
submitted that there may be a period when the rate of power from short term market is higher than
firm sources. There is no guarantee that the rate will always remain lower as compared to firm
sources. Furthermore, there may be instances when short term power may not be available during
certain period, at that time firm sources are the best option. Thus, it is always advisable for a
Discom to keep more and more power available from firm sources in order to keep the power
purchase cost minimal and also for the purpose of energy security.
As regards high cost of power purchase from THDC, the Petitioner submitted that the
power purchase amount submitted in the Petition for THDC in FY 2014-15 contains major amount
of arrears and hence, the average power purchase cost is coming to be on a higher side. However
upon excluding the amount pertaining to the arrears, the average cost works out to be Rs.
5.90/kwh.
2.17.1.3 Commission’s Views
The issue of the power purchase cost has been deliberated by the Commission in Chapter 3,
4 & 5 of the Order.
2.17.2 PGCIL Charges
2.17.2.1 Stakeholder’s Comments
Shri V. K. Garg, Munirka, New Delhi submitted that the PGCIL charges for FY 2015-16
claimed by UPCL are Rs. 349 Crore as against the approved charges of Rs. 228 Crore. This increase
needs to be clarified as to whether there had been huge capital expenditure on new lines in the State
or it is merely because of PoC/ pricing of transmission charges.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 49
2.17.2.2 Petitioner’s Reply
The Petitioner submitted that the during the first six months of FY 2015-16, it has received
bills of Rs. 174.72 Crore on account of revised POC Charges starting from May 2015 as per various
CERC amendments notified during Jan to July 2015. Due to these amendments, the Petitioner has
incurred an additional expenditure of Rs. 42 Crore approx. on account of adjustments for FY 2015-
16 in the first six months. Subsequently, for estimating PGCIL transmission charges for FY 2015-16,
the Petitioner has assumed the same amount for remaining six months. The per MU PGCIL Charge
for FY 2015-16 has been calculated using the estimated charges and energy coming from outside
Uttarakhand during FY 2015-16. The per MU rate thus, calculated is escalated by 4% per annum and
then multiplied by the projected power purchase quantum for each year of the Control Period to
arrive at the total estimated PGCIL charges.
2.17.2.3 Commission’s Views
The issue of PGCIL charges has been deliberated by the Commission in Chapter 5 of the
Order.
2.17.3 Return on Equity
2.17.3.1 Stakeholder’s Comments
Shri V. K. Garg, Munirka, New Delhi submitted that the Return on Equity for FY 2015-16
claimed by UPCL is Rs. 93 Crore as against the approved Return on Equity of Rs. 48 Crore. UPCL
should clarify if this increase is on account of increase in equity and should submit the copy of GO
regarding the equity contribution for FY 2016-17.
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that no
Return on Equity should be allowed on the assets created out of grant in line with the earlier
approach of the Commission.
M/s Asahi India Glass Ltd. submitted that RoE is increasing every year as addition in equity
in each year is based on funding pattern projected for investing in the capital expenditure plan.
2.17.3.2 Petitioner’s Reply
The Petitioner submitted that in the MYT Petition, RoE has been computed @ 16% on the
average equity. Year wise addition of equity has been considered at maximum of 30% of the
capitalization excluding grants for each year. In the year when the equity deployed was less than
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
50 Uttarakhand Electricity Regulatory Commission
30%, actual equity has been considered. The equity in excess of 30% has been considered as
normative loan.
The Petitioner, further, submitted that it has not claimed any return (depreciation/interest)
on the assets created out of grant.
2.17.3.3 Commission’s Views
The issue of Return on Equity has been deliberated by the Commission in Chapter 4 & 5 of
the Order.
2.17.4 Operation & Maintenance Expenses
2.17.4.1 Stakeholder’s Comments
M/s Asahi India Glass Ltd. submitted that the O&M expenses proposed with an overall
increase of 10% with respect to preceding years is very high as compared to the inflation index and
current market scenario.
Shri Ashok Bansal of Kumaon Garhwal Chamber of Commerce and Industry submitted that
all regular cadres should find place on UPCL’s rolls and contract system of employees should be
abolished as early as possible.
M/s Khatema Fibres Limited submitted that as per the details provided by UPCL only the
officer and supervisory staff are being recruited and no office staff is being recruited.
Shri Katar Singh submitted that under-staffing in UPCL should be taken care of and vacant
posts should be filled immediately.
2.17.4.2 Petitioners Reply
The Petitioner submitted that O&M Expenses are calculated as per UERC MYT Regulations,
2015 and methodology prescribed by the Commission. The growth factor considered for projecting
employee expenses are as per the recruitment plan to be carried out in the Control Period. It is,
hereby, assured that UPCL has tried to keep the estimates as conservative as possible considering
inflation rate as the average of past three years.
The Petitioner submitted that outsourcing of employees is required for core and non-core
activities. It is submitted that there are instances when UPCL is not able to recruit employees for
core activities due to factors beyond the control of the Petitioner, for instance Court Order and
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 51
various legal roadblocks. During that time outsourcing on contractual basis is the best option
available to the Petitioner as it provides instant manpower to carry out the day to day activities
which otherwise would have been stopped due to deficit manpower which would ultimately have
an adverse effect on the consumers. The Petitioner, further, submitted that the outsourcing not only
brings inefficiency in the system but also helps in reducing the costs incurred by the Petitioner.
On the issue of recruitment, the Petitioner submitted that as per the recruitment plan
provided in the Business Plan and MYT Petition (Page 111 of the MYT Petition) the recruitment is
envisaged at each and every level of service during the three year period specifically for core
activities concerning the Petitioner.
2.17.4.3 Commission’s Views
The issue of the Operation & Maintenance Expenses has been deliberated by the
Commission in Chapter 3, 4 & 5 of the Order.
2.17.5 Depreciation
2.17.5.1 Stakeholder’s Comments
Shri V. K. Garg, Munirka, New Delhi submitted that the depreciation for FY 2015-16
claimed by UPCL is Rs. 122 Crore as against the approved depreciation of Rs. 94 Crore. Further, the
depreciation proposed for FY 2016-17 is Rs. 145 Crore which has increased to Rs. 209 Crore in FY
2018-19. UPCL should clarify whether such increase in depreciation is on account of carry forward
of Kedarnath tragedy damages or its write off process or incremental capital expenditure. UPCL
should specify the rates of depreciation considered.
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that the
Depreciation should be allowed considering the opening value of GFA as on 08.11.2001 as Rs. 508
Crore and additional capitalisation as approved by the Commission. He also submitted that in line
with the earlier approach of the Commission, depreciation should not be allowed on the assets
created out of grants.
2.17.5.2 Petitioner’s Reply
The Petitioner submitted that the Commission in its Tariff Order for FY 2015-16 approved
depreciation @ 4.57% on the depreciable opening GFA (net of grant) of Rs. 2068.62 Crore and the
rate of depreciation was assumed as was computed for FY 2013-14. UPCL in the MYT Petition
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
52 Uttarakhand Electricity Regulatory Commission
computed depreciation @ 5.20% on the depreciable average GFA (net of grant). UPCL further
confirmed that no Kedarnath Tragedy damages or write offs have been considered in the
computation of depreciation in the MYT Petition.
The Petitioner submitted that for computation of depreciation, the value of GFA and its
financing from FY 2001-02 to FY 2012-13 has been considered the same which has been considered
by the Commission in its earlier Tariff Orders and, accordingly, GFA as on 08-11-2001 is considered
as Rs. 508 Crore.
2.17.5.3 Commission’s Views
The issue of depreciation has been deliberated by the Commission in Chapter 4 & 5 of the
Order.
2.17.6 Provision for Bad and Doubtful Debts
2.17.6.1 Stakeholder’s Comments
Shri V. K. Garg, Munirka, New Delhi submitted that the provision for bad and doubtful
debts proposed by UPCL is Rs. 46 Crore for FY 2015-16, Rs. 55 Crore for FY 2016-17, Rs. 61 Crore for
FY 2017-18 and Rs. 89 Crore for FY 2018-19. UPCL should clarify as to how the bad debts are
decided and proposed in advance to be increasing every year. One time provision for bad and
doubtful debts for Kedarnath tragedy may be acceptable but not an increased write off every year.
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted the
following:
a. The Commission has not fixed any norm for bad and doubtful debts.
b. UPCL has not identified and actually written off bad debts according to a transparent
policy approved by the Commission.
c. UPCL is trying to move in its own direction without taking into consideration the
observations of the Commission on bad and doubtful debts.
d. The earlier stand taken by the Commission for bad and doubtful debts should hold
good for this year also.
Shri Ashok Bansal of KGCCI, M/s Khatema Fibres Ltd., M/s East West Products Ltd., M/s
Asahi India Glass Ltd. and other stakeholders submitted that the provisions for bad & doubtful
debts are on a higher side and are unjustified.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 53
2.17.6.2 Petitioner’s Reply
The Petitioner submitted that Regulation 31 of the UERC Tariff Regulations, 2015 provides
that the Commission may allow a provision for Bad and Doubtful Debts @ 1% of the estimated
Annual Revenue subject to (i) actual writing off of Bad Debts in previous years, (ii) the total amount
of such provisioning allowed in the previous years should not exceed 5% of the receivables at the
beginning of the year. UPCL at the time of transfer of Assets and Liabilities got a provision for Bad
and Doubtful Debts amounting to Rs. 230.01 Crore. UPCL started its functioning w.e.f. 09-11-2001
and the Commission so far allowed a provision for Bad and Doubtful Debts of Rs. 103.74 Crore.
UPCL for the period upto FY 2014-15 has written off the bad debts amounting to Rs. 139.15 Crore.
Accordingly, the entire provision allowed by the Commission has been exhausted by UPCL. Thus,
the claim of provision of 1% of Annual Revenue for each year is in line with the provisions of the
Regulations.
2.17.6.3 Commission’s Views
The issue of provision for bad & doubtful debts has been deliberated by the Commission in
Chapter 4 & 5 of the Order.
2.17.7 Other Costs
2.17.7.1 Stakeholder’s Comments
Shri Pramod Singh Tomar of M/s Galwalia Ispat Udyog Pvt. Ltd. and Shri Shakeel A.
Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted that the contribution of power
purchase cost in the total ARR was 89.65% in FY 2014-15 which is proposed to be 84.24% in FY 2016-
17 and 82.04% in FY 2018-19 while the contribution of other costs in the total ARR has increased
from 10.35% in FY 2014-15 to 17.96% in FY 2018-19. In absolute terms, other costs have increased
from Rs. 451.46 Crore in FY 2014-15 to Rs. 1252.69 Crore in FY 2018-19 which is an increase of 177%
in 5 years. The increase in other costs (primarily fixed in nature) is not being met by commensurate
increase in volumes as billed energy has increased only by 27.08% over the 5 years period.
Shri Rajiv Gupta submitted that the provision of cost towards the RPO should not be
allowed.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
54 Uttarakhand Electricity Regulatory Commission
2.17.7.2 Petitioner’s Reply
The Petitioner submitted that in its MYT Petition, it has proposed various improvements
and other works for providing continuous and quality supply and other services to the consumers.
Impact of these works is reflecting in the increased level of other costs. Further, increase in power
purchase cost has been kept at minimum which is major part of cost of supply and increased level
of such cost may lead to abnormal hike in consumer tariffs. The Petitioner, further, submitted that
the projections of all the expenses have been made as per the provisions of UERC Tariff
Regulations, 2015.
2.17.7.3 Commission’s Views
The issue of other costs has been deliberated by the Commission in Chapter 4 & 5 of the
Order.
2.17.8 Consumer Security Deposit
2.17.8.1 Stakeholder’s Comments
Shri Shakeel A. Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. & M/s Galwalia
Ispat Udyog (P) Ltd. submitted that the rate of interest on consumer security deposit should be
increased from 9% as credit facilities available to the industries is around 12% to 14%. Also, UPCL
has proposed the rate of interest on working capital as 14.05% and rate of interest on loans as
10.17%.
M/s BST Textile Mills Pvt. Ltd submitted that the security deposit rule of 2 months should
be reduced to 1.5 months.
M/s East West Products Ltd., M/s Khatema Fibres Ltd., Shri Ashok Bansal of KGCCI & M/s
Ganesha Ecosphere Ltd. requested to facilitate the process of depositing the security and additional
security deposit by way of bank guarantee/ letter of credit.
Shri Mahesh Sharma, Uttarakhand Industrial Welfare Association submitted that interest on
cosumer security deposit is not being paid yearly.
Shri Arvind Jain & Shri Vishwamitra submitted that the amount of security deposit is not
mentioned in the bills.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 55
2.17.8.2 Petitioner’s Reply
The Petitioner in its response has submitted as follows:
• Interest on Security Deposit is being paid as per the provision of section 47(4) of the
Electricity Act, 2003. The rate of Interest for FY 2015-16 is 8.50 % p.a.
• While computing the working capital consumer security deposit is reduced and
UPCL is allowed interest on such value of working capital.
• Security deposit is received from the consumers to securitize the credit sales made by
the DISCOM. In case a consumer defaults in making the payment of his electricity
bills, the recovery of such electricity dues may be made by adjusting the security
deposit of the consumer. Thus, the rate of interest on loans and working capital can
not be compared with interest on security deposits.
As regards reduction in security deposit from 2 months to 1.5 months, the Petitioner
submitted that once the supply is drawn by a consumer the bill is generated after a period of 1
month. In 15 days, the bill is received by the consumer and a 15 days time period is given for
payment. Thus, a 2 month period is justifiable and is also in accordance with the UERC Supply
Code.
As regards depositing the security and additional security deposit by way of Bank
Guarantee/Letter of Credit, the Petitioner submitted that as per Section 47(4) of the Electricity Act,
2003, the Distribution Licensee is required to pay interest on the security deposit. As interest cannot
be paid on the money held with UPCL as Bank Guarantee/Letter of Credit, the Bank Guarantee
should only be in the form of cash/bank draft.
On the contention of non-payment of interest on security deposit, the Petitioner submitted
that there are clear orders of UPCL to pay interest on security deposits to the consumers on yearly
basis. This interest is first adjusted towards shortage of security deposits, if any, and the balance
amount of interest is adjusted in the electricity bills of the consumers.
2.17.8.3 Commission’s Views
The Commission agrees with the replies made by the Petitioner in this regard. However,
UPCL is directed to make full payment/adjustment of the interest on security deposit & also to
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
56 Uttarakhand Electricity Regulatory Commission
show the amount of interest so due alongwith the amount of security deposit in the bills of the
consumers.
2.18 Capital Expenditure
2.18.1.1 Stakeholder’s Comments
M/s Khatema Fibres Ltd. & M/s Asahi India Glass Ltd. submitted that the capital
expenditure plan proposed for the Business Plan period of FY 2016-17 to FY 2018-19 is very high.
Shri Pramod Singh Tomar of M/s Galwalia Ispat Udyog Pvt. Ltd. and Shri Shakeel A.
Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted that UPCL had been proposing
capital expenditure on various measures for controlling losses like replacement of mechanical
meters with electronic meters, installation of electronic meters in unmetered connections,
installation of additional distribution transformers, installation of capacitor bank, installation of
double metering of high voltage consumers, augmentation of existing 33/11 kV S/s etc. The capital
expenditure of UPCL directly affects the consumers in the form of interest on loans. But, UPCL has
not submitted the target and actual works executed. Further, non-execution of the proposed capital
expenditure results in power theft, losses etc.
They requested that the details of capital expenditure works undertaken and accomplished
with pendency thereon should be shared with consumers.
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that in line
with the earlier approach of the Commission, capitalisation of assets should be allowed only if the
Electrical Inspector Certificates have been submitted.
Shri Ashok Bansal, Kumaon Garhwal Chamber of Commerce and Industry submitted that
the Capital expenditure plan proposed by UPCL may be considered by the Commission in terms of
revenue generated by these schemes and all other schemes that are not deemed to be productive
should be scrapped.
2.18.1.2 Petitioner’s Reply
The Petitioner submitted that the year wise and work wise details of capital expenditure is
mentioned in the MYT Petition and Business Plan. The Petitioner further submitted that with a view
to provide better power supply, consumer services and providing electricity to all the households/
consumers of the State, UPCL has proposed many works to be executed for this purpose and,
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 57
accordingly, the capex plan has been prepared. In this capex plan, there are two central sponsored
schemes (IPDS, DDUGGY) in which major part of funding is grant which will be passed on to the
consumers and there will be no impact of such expenditure on the tariffs of the consumer.
The Petitioner, further, submitted that the need for capital expenditure in UPCL is for two
primary reasons:
• The rising electricity demand makes it essential for the Petitioner to make investments in
procuring power to meet the demand and also prepare its distribution infrastructure for
evacuating the increasing power that shall be procured and subsequently distributed to
its growing consumers.
• Making investments to facilitate loss reduction, increase operational efficiency through
IT and automation to improve the quality and reliability of supply.
Thus, the Petitioner has proposed the capital investments in purview of the above
mentioned objectives which will in turn help in more revenue generation for the Petitioner.
As regards the capitalisation after clearances are received from the Electrical Inspector, the
Petitioner submitted that out of total HT/EHT works amounting to Rs. 1630.45 Crore capitalized for
the period from FY 2007-08 to FY 2013-14, UPCL has submitted the Electrical Inspector Certificates
in respect of assets amounting to Rs. 1330.52 Crore and there is a balance of Rs. 299.93 Crore only
and the certification work in respect of these assets is in progress and the certificates shall be
provided to the Commission shortly. Further, as against the HT/EHT works capitalized during FY
2014-15 amounting to Rs. 209.77 Crore, certificates in respect of HT works amounting to Rs. 107.15
Crore have already been submitted to the Commission. The Petitioner submitted that thus, it is clear
that it is very near to the target of submission of Electrical Inspector Certificate and hence, the
Petitioner should be allowed return for the same.
2.18.1.3 Commission’s Views
The Commission has duly scrutinised each and every element of ARR for the second Control
Period from FY 2016-17 to FY 2018-19 in accordance with the provisons of UERC Tariff Regulations,
2015 and the same has been discussed in Chapter 3, 4 & 5 of the Order.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
58 Uttarakhand Electricity Regulatory Commission
2.19 Truing-up for Past Years
2.19.1.1 Stakeholder’s Comment
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that the
shortfall in revenue as against the revenue projected by the Commission during FY 2014-15 is
mainly due to load shedding on industrial consumers. Industrial consumers pay the highest tariff
and they are subject to maximum rostering resulting in shortfall in revenue for UPCL. In other
States, rostering of industrial consumers is done as the last measure to maintain grid balance.
M/s Kashi Vishwanath Steels Pvt. Ltd. and M/s KVS Infratech LLP submitted that UPCL
has proposed to recover the Revenue Gap of Rs 1220.26 Crore from FY 2014-15 to FY 2016-17 which
is very huge and equivalent to one fourth of total revenue. They requested the Commission to
examine the huge gap and publish the reason in Tariff Order whether it is due to wrong estimation
or it is due to inefficiency of the licensee.
Shri Mahesh Sharma of Uttarakhand Industrial Welfare Association submitted that during
FY 2014-15, UPCL was having a revenue surplus.
2.19.1.2 Petitioner’s Reply
The Petitioner submitted that the gap of revenue and expenditure for FY 2014-15 is mainly
due to lesser rate of power purchase approved by the Commission. The actual power purchase cost
was Rs. 3.29 /unit whereas the Commission had approved Rs. 3.13/ unit. This increased the gap by
Rs. 190 Crore. The second main reason was low level of distribution losses approved by the
Commission as compared to actual. Actual distribution losses for FY 2014-15 are 18.79% whereas
the Commission approved only 15.50%. This loss is equivalent to the revenue of Rs. 160 Crore.
The Petitioner further submitted that during FY 2014-15, 97% of demand was met and 3%
unmet demand was due to gap of demand and availability of energy/transmission network/
distribution network. The Petitioner, further, submitted that it has also prepared its rostering policy.
2.19.1.3 Commission’s Views
The Commission has duly scrutinised each and every element of Truing up for FY 2014-15 in
accordance with the provisons of UERC (Terms and Conditions for Determination of Tariff)
Regulations, 2011 and the same has been discussed in Chapter 4 of the Order.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 59
2.20 Departmental Employees
2.20.1.1 Stakeholder’s Comments
Shri Ashok Bansal, Kumaon Garhwal Chamber of Commerce and Industry submitted that
there has been a nominal hike of tariff for departmental employees and pensioners, however, tariff
for other consumers has increased by about 40% in past 12 years.
Shri Amar S Dhunta, RTI Club, Uttarakhand submitted that most of the departmental
employees are not being billed and charged for their consumption of electricity and the tariff they
are charged with is subsidised. The meter placed in the employees premises are damaged,
electricity is being misused by the employees as they use it for commercial purposes.
Shri Viru Bisht submitted that UPCL’s offices and sub-stations do not have meters.
2.20.1.2 Petitioner’s Reply
The Petitioner submitted that the employees of UPCL are being given the facility of
departmental electricity connection since U.P. State Electricity Board was in existence. Under this
facility, a fix lump-sum amount is charged from the employees according to their designation
towards electricity charges for electricity supplied to them. Erstwhile UPSEB was unbundled under
the provisions of Uttar Pradesh Electricity Reforms Act, 1999 and Section 23(7) of the said Act
provides “terms and conditions of service of the personnel shall not be less favorable to the terms
and condition which were applicable to them before the transfer”. The same spirit has been echoed
under the first proviso of Section 133(2) of the Electricity Act, 2003. The benefits for employees /
pensioners as provided in Section 12(b)(ii) of the Uttar Pradesh Reform Transfer Scheme, 2000
include “concessional rate of electricity”, which means concession in the rate of electricity to the
extent it is not inferior to what was existing before 14th January, 2000. The rates and charges
indicated above for this category are strictly in adherence of the above statutory provisions. As
UPCL is the successor entity of UPPCL (formed as a result of unbundling of UPSEB), the above
legal provisions are also applicable on it (UPCL).
The Petitioner, further, submitted that the meters have been installed on the connections of
the Departmental Employees/Pensioners and any employee/pensioner found indulging in
unauthorized use of electricity through departmental electricity connection is liable to penal action
as per departmental rules/provisions of Law.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
60 Uttarakhand Electricity Regulatory Commission
2.20.1.3 Commission’s Views
Regarding the issue of misuse of electricity by the employee of the Petitioner, the
Commission in its previous Tariff Orders had directed the Petitioner to take appropriate steps on
the issues raised by the respondents to avoid the misuse of electricity by UPCL’s employees.
Further, the Commission clarifies that while approving the cost of electricity consumed by
employees, average consumption of metered domestic category for the whole State at normal
domestic tariff has been considered. Based on the above, the cost of energy consumed to the extent
not recovered from the employees is to be borne by the Petitioner, i.e. it is not being passed on to
other consumers of the State.
Further, the Commission also directs the Petitioner to install meters at all its offices and
sub-stations, if not installed, within one month of the date of the Order and submit report to the
Commission by May 15, 2016.
2.21 Collection Efficiency
2.21.1.1 Stakeholder’s Comments
M/s Kashi Vishwanath Steels Pvt. Ltd. and M/s KVS Infratech LLP submitted that UPCL
has failed to collect target percentage of revenue from the consumers and requested for analysis of
the reason behind the same.
M/s Shiv Shakti Electricals and other stakeholders submitted that unpaid billed amounts
from Govt. as well as non-Govt. organisations should be recovered regularly to improve the
collection efficiency.
2.21.1.2 Petitioner’s Reply
The Petitioner submitted that during the last 5 years it has reduced its AT&C Losses by
10.77% at a yearly average of 2.154 %, increased collection efficiency by 6.34% at an yearly average
of 1.268%. The level of AT&C Losses and Collection Efficiency in FY 2014-15 is 18.64% and 99.87%
respectively. This may be treated a good performance of UPCL.
The Petitioner submitted that it is a constant endeavour of the Petitioner to improve upon its
collection efficiency each year so that the burden of lesser revenue realisation is not put on to the
other consumers. Continuous efforts are made to realise revenue specifically from the Government
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 61
organisations as is evident from the increasing collection efficiency for this category through the
years.
2.21.1.3 Commission’s Views
The Commission has approved the collection efficiency trajectory for the second Control
Period while approving the Business Plan as discussed in Chapter 3 of the Order.
The Commission agrees with the concerns raised by the stakeholders/objectors regarding
electricity dues on various Government departments and private consumers. Various stakeholders
suggested that these dues should be recovered. The Commission has been consistently directing the
Petitioner to make concerted efforts for recovering its dues and improve its financial position by
identifying such consumers and writing off dubious/non-existent or ghost consumers from its
records through a policy of writing off the bad debts and initiating recovery of its dues from other
consumers. Further, as elaborated in Chapter 4 and 5 of the Order, the Commission in this Tariff
Order is not allowing any provision for bad and doubtful debts as proposed by the Petitioner. With
regard to the issue of collection efficiency and receivable management, the Commission has
discussed the same in Chapters 3, 4 & 5 of the Order.
2.22 Fuel Charge Adjustment
2.22.1.1 Stakeholder’s Comments
M/s Shiv Shakti Electricals & M/s Dev Bhoomi Dharamshala Prabhandhak Sabha
submitted that the fuel Charges should not be charged to the consumers and should be pre-
included in the tariff.
2.22.1.2 Petitioner’s Reply
The Petitioner submitted that the Fuel Charge Adjustment is levied on account of
incremental fuel charges of the generating stations not envisaged at the time of determination of
Tariff. In case a normative incremental fuel cost is added in the power purchase cost at the time of
determination of tariff, this will unduly increase the tariff of the consumers. Therefore, on the basis
of actual incremental fuel cost, fuel charge adjustment is revised quarterly. During FY 2015-16 the
FCA was zero in the second and last quarter.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
62 Uttarakhand Electricity Regulatory Commission
2.22.1.3 Commission’s Views
With regard to FCA recovery mechanism, the Commission has already specified the
mechanism in its UERC Tariff Regulations, 2015.
2.23 Metering and Billing
2.23.1.1 Stakeholder’s Comments
Shree Karuna Jan Kalyan Samiti made certain suggestions that the bill distribution system
should be improved and meters should be shifted from open areas to closed areas to avoid
tampering and theft of meters.
M/s KVS Infratech LLP & Shri P.C. Agarwal submitted that the Commission has approved
15 days grace period for depositing electricity bill from the date of billing but for last so many
months, bills are prepared/delivered/published on internet just before last date and hence, the
benefit of grace period is not available.
M/s Shiv Shakti Electricals submitted that the domestic supply is being utilised for the non-
domestic purposes. They further submitted that the replacement of defective meters should be done
within 7 days.
Bhartiya Kisan Union submitted that the Meters for Private Tube Well connections should
be placed on HT line (11 kV), further PTW connection should be disconnected after six months if the
payments for the bills are not made in time.
Bhartiya Kisan Union submitted that if meter shows the reading of NR for PTW connections
then the concerned customer should be given notice for that and should be asked for the
replacement of meter and if the customer does not act, accordingly, then proper penalty should be
levied on the customer.
a. In case of meter showing the NR for (PTW) connections unless meter is replaced, the
reading should be charged according to the fix rate within 2 months.
b. If the meter is showing RDF/NA, NR/IDF to the PTW electricity connection the
concerned authority (Meter reader, AE, JEE, EED, SE) should be made accountable
and should be punished according to the degree of offence.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 63
Bhartiya Kisan Club submitted that separate connections should be given to cane crushers
other than the private tube well connections. They also submitted that those consumers who can
lease their land for one year should be given temporary connections for six months.
Bhartiya Kisan Club submitted that the load capacity of the connection is not clearly
mentioned in FY 2015-2016 tariff, while in earlier tariffs it was clearly mentioned for the meter
connections upto 4 kW load.
M/s Indus Tower Ltd., requested the Commission to provide directions to the utilities for
supporting the proposal of installation of AMR meters and roll out of consolidated billing for large
consumers with multiple connections. Such a measure would drive the efficiency of the DISCOM by
way of savings in meter reading and billing cost while also ensuring accuracy.
SIDCUL Manufacturers Association Uttarakhand submitted as part of check meter
assessment, consumers should not be charged more than 3 months of average consumption. They
further submitted that 100% online billing shall be implemented for industrial consumers.
Shree Karuna Jan Kalyan Samiti submitted that Prepaid metering should be extensively
publicised and the tariff for the same should be reduced by 15-20% across all categories.
Shri Sunil Kapri suggested that consumers should be allowed the facility of payment of bills
through cheque to person who distributes the bills.
2.23.1.2 Petitioner’s Reply
The Petitioner submitted that the meter reading of the consumers is being taken by the
meter readers and the bill is being provided to the consumers at the time of meter reading. The
following consumer services have also been started by UPCL.
• Online billing of all the consumers
• Online bill payment facility for all the consumers
• Bill payment facility in the branches of Punjab National Bank
• An agreement has been signed with M/s CSC to collect the payment of bills in
various locations of the State. Presently, 1,119 centers are operative.
As regards the grace period, the Petitioner submitted that the grace period was allowed by
the Commission on the premise that 15 clear days are not given to the consumers for making the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
64 Uttarakhand Electricity Regulatory Commission
payment of the bill. UPCL starts billing from fifth of every month but in some cases due date for
payment of bill is not kept giving clear 15 days. However, bill is always delivered before the due
date and thus, the consumer avails a grace period of 15 days for making the payment.
As regards the domestic supply being utilised for the non-domestic purposes, the Petitioner
submitted that tariff for non-domestic category is specified by the Commission and the same is
applicable to consumers falling under that category. For particular cases as mentioned here the
stakeholder is requested to report the case to the respective division office.
As regards the replacement of meters, the Petitioner submitted Defective Meters are being
replaced as per the provisions of Tariff Order/Regulations. During FY 2015-16 UPCL has replaced
1,05,076 meters till 31-01-2016.
Regarding, AMR, the Petitioner submitted that AMR of all the Commercial and Industrial
Consumers having load above 5 kW is under consideration and shall be finalized in due course of
time.
Regarding Check Meter Assessment, the Petitioner submitted that it is done as per the
provisions of UERC (The Electricity Supply Code), Regulations, 2007.
On the suggestion of online billing, the Petitioner submitted the the facility of online
payment of electricity bills has already been provided to all its consumers.
Regarding publicity of pre-paid metering, the Petitioner submitted that notice showing the
category wise details of postpaid tariff and prepaid tariff were published in the following news
papers:
• Amar Ujala, Uttarakhand dated 31-01-2016
• Hindustan (Hindi), Uttarakhand 31-01-2016
• Rastriya Sahara, Uttarakhand 31-01-2016
• The Times of India, New Delhi dated 01- 02-2016
2.23.1.3 Commission’s Views
The Commission has taken note of various suggestions received from the stakeholders
regarding improvement in metering and billing and the Commission directs the UPCL to consider
the suggestions given by the stakeholders to improve its metering and billing system. The
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 65
Commission directs UPCL to provide services to the Consumers namely restoration of power,
voltage fluctuation, metering & billing related etc. as per Orders/Supply Code/SOP Regulations
of the Commission. The Commission has deliberated on technical & commercial performance of
the Petitioner in Chapter 7 of the Order.
With regard to the request of the consumers of payment of bill through cheque to the person
who distributes the bill, the Commission is of the view that it is a policy matter to be decided by the
Petitioner with the approval of GoU & its Board of Directors. Hence, UPCL is directed to submit
the comments on the suggestions of payment of bills by cheque to the person who come to
distribute the bills within one month of the date of Order.
2.24 Load Reduction
2.24.1.1 Stakeholder’s Comments
SIDCUL Manufacturers Association Uttarakhand submitted that load reduction should be
allowed more than once in a financial year.
2.24.1.2 Petitioner’s Reply
The Petitioner submitted that on the basis of contracted load of the consumers, UPCL plans
its power purchases and frequent reduction in contracted load will make the planning difficult.
Thus, load should not be reduced more than once in a Financial Year.
2.24.1.3 Commission’s Views
The Commission agrees with the views of the Petitioner that if frequent reduction in load is
allowed, then it will affect the planning of power procurement and the same may affect the quality
of supply. Further, this is also in accordance with relevant Regulations of the Commission.
2.25 Distribution Line/ Line Losses
2.25.1.1 Stakeholder’s Comments
Shri Virat Seth, Shri Pramod Singh Tomar of M/s Galwalia Ispat Udyog Pvt. Ltd. and Shri
Shakeel A. Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted that the emphasis of
UPCL should be on reducing the line losses, pilferage by theft, collection inefficiency, strong
mechanism of recovering bad debts instead of directly increasing the tariff.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
66 Uttarakhand Electricity Regulatory Commission
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted the
following:
a. UPCL had been claiming in its Petitions that the Distribution Loss trajectory
specified by the Commission is unachievable and unrealistic. The whole focus of the
Electricity Act, 2003 was to be on efficient use of resources and reduction of
Distribution Losses is the most important goal to this act.
b. In Uttarakhand, the sale of energy to industrial consumers has increased from 28% in
FY 2004-05 to 56% in FY 2014-15. Therefore, the loss level should be much lower. It is
generally accepted that the losses incurred in the distribution to these industrial
consumers cannot be more than 3%-4%. With such lower loss levels of industrial
consumers, the overall losses should be much lower than the target level. If the losses
at all levels other than industrial consumers is seen, then these losses are actually
increasing.
c. The Commission had fixed the loss reduction target and directed UPCL to carry out
Energy Audit to which UPCL has not complied. UPCL should be directed to carry
out Energy Audit at S/s level and also at different voltage levels separately so that
the actual reason for losses can be ascertained and action be taken to bring down the
losses to target level.
d. The Commission should appoint an agency for carrying out the investigation of
losses and energy audit. If the HT consumers are consuming more than 50%, whose
losses should not be more than 5%-6%, the losses in other categories are more than
45%. This is enough reason for proper investigation under Section 128 of the
Electricity Act, 2003.
e. UPCL should convert their S/s into cost centres and any S/s found to be losing
money should be subjected to penalties.
M/s Kashi Vishwanath Steels Pvt. Ltd., M/s KVS Infratech LLP, M/s Asahi India Glass Ltd.
and some other consumers submitted that there is a gap of around 2-3% in distribution losses
approved by the Commission and actual distribution losses. They submitted that it is not feasible to
pass on the inefficiencies of UPCL on the consumers.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 67
M/s Tata Motors submitted that UPCL is not achieving the loss targets and consequently
consumers are facing tariff increase. They requested the Commission to fix the stringent targets for
distribution losses and not to pass the impact of non-achievement of targets to the consumers.
Shri R.S. Yadav of India Glycols Ltd. submitted that the determination of voltage-wise losses
should be carried out.
Shri Ashok Bansal submitted that the tariff of HT industries in the last Tariff order was fixed
on the basis of assumption of 15% losses in the UPCL’s System. Realistically the losses at HT level
may not be more than 5% and these can be fairly accurate extent with a little exercise and effort by
licensee.
Shri Vijay Singh Verma of Bhartiya Kisan Club submitted that losses in the domestic lines
and PTW lines should be shown separately.
Shri Rakesh Bhatia, President, Uttarakhand Industrial Welfare Association submitted that
UPCL should submit area wise distribution losses and collection efficiency to the Commission in
order to substantiate their claim decrease in losses in FY 2014-15.
Shri Mahesh Sharma and Shri Mukesh Chandra also suggested that the trajectory for
reduction of losses should be specified.
2.25.1.2 Petitioner’s Reply
The Petitioner submitted that during the last 5 years it has reduced its AT&C Losses by
10.77% at an yearly average of 2.154%, increased collection efficiency by 6.34% at an yearly average
of 1.268%. The level of AT&C Losses and Collection Efficiency in FY 2014-15 is 18.64% and 99.87%
respectively.
The Petitioner further submitted that the Commission had estimated the distribution losses
of UPCL for FY 2002-03 as 44.32%. These losses for FY 2014-15 are 18.79%. Thus, UPCL reduced
these losses by 25.53% within a period of 12 years at an yearly average of 2.1275 % and this may be
treated as a good achievement of UPCL.
The Petitioner also submitted that even after such significant reduction in distribution losses,
UPCL has suffered a loss of Rs. 1023 Crore from FY 2003-04 to FY 2013-14 due to stringent loss
trajectory fixed by the Commission, which is adversely impacting the financial position of the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
68 Uttarakhand Electricity Regulatory Commission
Company. The Petitioner also submitted that electricity tariff in Uttarakhand is lowest and the
distribution loss trajectory claimed by UPCL is realistic and should be allowed.
The Petitioner also submitted that in order to curb theft of energy, the following measures
have been taken up by it:
• Vigilance Raids are being conducted and cases are being registered under Section 126
and 135 of the Electricity Act, 2003. Legal proceedings are being initiated against the
person(s) who is found indulging in theft of electricity.
• Mechanical meters are being replaced by electronic meters. 25,042 meters have been
replaced so far in this year.
• All defective meters are being replaced. 93,691 meters have been replaced so far in
this year.
• AB cable is being laid in theft prone areas. 1706 Km. cable has been laid so far in this
year.
• New connections are being released by installing meters outside the premises of the
consumers.
• Meters installed on the connections of existing consumers are being shifted outside
the premises of the consumers.
The Petitioner further submitted that the following consumer services have also been started
by UPCL.
• Online billing of all the consumers
• Online bill payment facility for all the consumers
• Bill payment facility in the branches of Punjab National Bank
• An agreement has been signed with M/s CSC to collect the payment of bills in
various locations of the State. Presently, 1,119 centers are operative.
The Petitioner, further, submitted that it is in process of working out the voltage
wise/category wise losses and cost of supply, and will be able to file the next ARR on the basis of
the same.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 69
As regards, area wise distribution losses and collection efficiency, the Petitioner submitted
that circle wise/division wise information including collection efficiency is submitted to the
Commission during the process of tariff determination each year. However, as per prevailing
Regulations area wise separate tariff cannot be determined.
2.25.1.3 Commission’s Views
The Commission has taken note of the concerns raised by the stakeholder and the initiatives
taken by UPCL for reducing the losses. The Commission would like to clarify that though the actual
distribution losses are higher, the Commission for the tariff purposes have been considering the
distribution loss target approved by the Commsision and the same approach has been continued
while approving the true-up for FY 2014-15 as discussed in Chapter 4 of the Order. Further, the
Commission has specified the loss reduction target for second Control Period as elaborated in
Chapter 3 of the Order while approving the Business Plan.
2.26 Distribution Infrastructure
2.26.1.1 Stakeholder’s Comment
M/s Tata Motors submitted that the existing infrastructure in U S Nagar and TML vendor
park is not sufficient to meet the demand for the areas as load has increased by more than 40% and
hence, should be augmented.
Shri Rakesh Bhatia submitted that the Commission should not allow the licensee to increase
the fixed cost as there is enough infrastructure available with the Petitioner so there is no increase in
the cost. Further, he submitted that whatever the corporation is increasing they are claiming
depreciation on it which is also a profit to UPCL.
2.26.1.2 Petitioner’s Reply
The Petitioner submitted that its constant endeavors is trying to provide the best quality
supply to its consumers. Accordingly, the Petitioner has proposed the capital expenditure in
respective Discom areas. The Petitioner has proposed capital expenditure in US Nagar in purview
of substation augmentation of 66/33/11 kV, increase in network line, meter replacement, electronic
metering, new substations etc. as can be observed in the Business Plan submitted to the
Commission.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
70 Uttarakhand Electricity Regulatory Commission
Further, the Petitioner in response to Shri Rakesh Bhatia submitted that Fixed Charges are
based on the cost of the Company other than variable power purchase cost. On the basis of the
projected costs, increase in fixed charges have been proposed. Further, depreciation is not a profit of
the Company rather it is the recovery of fixed cost already incurred by the Company.
2.26.1.3 Commission’s Views
The Commission has taken note of concern raised by the stakeholder about inadequate
distribution infrastructure and directs the Petitioner to strengthen its distribution network. The
Commission based on analysis of past performance of UPCL in executing capital works has
approved the Capital Expenditure for the next Control Period as discussed in Chapter 3 of the
Order while approving the Business Plan.
2.27 KCC Data
2.27.1.1 Stakeholder’s Comment
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that
although UPCL has done good job in compiling data in KCC cell, enough benefit is not being
derived from scrutiny of this data. He suggested that the Commission may set up one cell either in
its office or in UPCL for scrutiny of this data. This cell should be independent and should not be
reporting to UPCL. The formation of this cell would help in proper diagnostics of UPCL at division
level.
2.27.1.2 Petitioner’s Reply
The Petitioner submitted that it has covered all the industrial consumers having load above
5 kW and non-domestic consumers having load above 10 kW under KCC billing. The MRI report
and billing of the HT consumers are being checked at Corporate Office on regular basis. Corrective
actions are being taken on the irregularities found in the checking of the metering system and
billing of these consumers.
2.27.1.3 Commission’s Views
As regards the suggestion for scrutiny of KCC data, the Commission would like to clarify
that the commercial performance monitoring including KCC data of the Petitioner is being done at
Commission’s office on regular basis based on the monthly report submitted by the Petitioner on
regular basis on the prescribed format.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 71
2.28 Quality of Power
2.28.1.1 Stakeholder’s Comment
Shri Pankaj Gupta, President, Industries Association of Uttarakhand submitted that the
issues like voltage variations amongst different phases, low voltage, high voltage, frequent
breakdowns etc. have become a common practice. The Commission should give clear directions to
UPCL for improvement in quality of supply.
M/s Hindustran Glass & Industries Limited submitted that alternate source of supply
should be provided to HT and LT Consumers in case of a breakdown.
2.28.1.2 Petitioner’s Reply
The Petitioner submitted that efforts are regularly made by UPCL for improvement in
quality of power. The demand of electricity has become about four times from the date of creation
of State and UPCL is meeting the demand of electricity to the satisfaction of the consumers. It is
worthwhile to mention here that in the whole State average supply of electricity in a day is between
22-24 hours.
The Petitioner submitted that it tries to provide best quality supply to all its consumer but
there occurs instance when a breakdown occurs which is beyond the control of the Petitioner and
when such situation arises, it tries its level best to keep the response time as minimal as possible.
2.28.1.3 Commission’s Views
The Commission has taken note of concerns raised by the stakeholders and directs UPCL to
take adequate steps to improve the quality of supply. In this regard, the Commission would like
to clarify that UPCL’s complaint handling procedures have been approved by the Commission
and are available in the website of the Commission. If the complaints are not resolved by UPCL
internally, the consumers can also lodge their complaints with the “Consumer Grievance
Redressal Forum” functional in the respective Garhwal and Kumaon Zones of Uttarakhand.
2.29 Open Access
2.29.1.1 Stakeholder’s Comment
Shri Shakeel A. Siddiqui of M/s Kashi Vishwanath Textile Mill (P) Ltd. submitted the
following:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
72 Uttarakhand Electricity Regulatory Commission
a. In Uttarakhand, the demand exceeds supply till the open access power purchase is
not supported in the State.
b. There is no system of adjustments of open access unit at the time of billing and too
much follow up for rectification of the same is required. There are no guidelines for
adjustment and this is leading to confusion.
c. The compensation allowed by the Commission in case of open access is not being
paid to the consumers in spite of repetitive reminders.
d. The NOC to procure open access power is given by SLDC normally in the last days
of the month. A schedule needs to be provided by which NOC is given latest by 15th
of every month.
M/s Kashi Enterprises M/s Kashi Vishwanath Steels Pvt. Ltd. and M/s Galwalia Ispat
Udyog (P) Ltd. submitted that the Commission may take interest and encourage open access to
purchase power through open access to reduce the burden on UPCL and this can happen when
different losses and charges are reasonably reduced. This will increase power in the State resulting
in availability of power to industries. Further, all departmental defaults should be minimised.
M/s Tata Motors suggested to reduce the losses from 15% to 8.33% for computing Open
Access Charges.
M/s Hindustan Glass & Industries Ltd submitted that there is no fool proof system for
adjustment of energy availed under open access through IEX. They proposed that the entire system
of open access adjustments should be made online and copies be provided to the consumers.
M/s Hindustan Glass & Industries Ltd. further suggested that the renewal of open access
should be on annual basis instead of monthly basis.
M/s BST Textile Mills Pvt. Ltd. submitted that no wheeling charges should be levied on
open access power as demand charges are already being paid.
2.29.1.2 Petitioner’s Reply
The Petitioner submitted that it already allows open access to the consumers to the extent
technically possible. This is also evident from the fact from its large number of registered open
access consumers.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 73
The Petitioner, further, submitted that the extra energy charges for continuous supply are
charged from the consumer who has opted for continuous supply. This charge is premium to get
continuous and quality supply. These consumers are exempted from load shedding during
scheduled/unscheduled power cuts and during restricted hours of the period of restriction of
usages approved by the Commission from time to time. With a view to recovery of cost, continuous
supply surcharge @ 15% is justified. In this connection, the following provisions of Law are
relevant:-
Para-5.5.1 of National Electricity Policy – “There is an urgent need for ensuring recovery of cost of
service from consumers to make the power sector sustainable.”
Para-8.2.1(1) of Tariff Policy – “…onsumers, particularly those who are ready to pay a tariff which
reflects efficient costs have the right to get uninterrupted 24 hours supply of quality power…”
The Petitioner submitted that there is no centralized mechanism for monthly adjustment of
Open Access Power Purchases by consumers. However, this adjustment of Open Access Energy is
being done by division offices in the next billing cycle. Further, in order to make adjustment of
Open Access Energy in the current billing cycle, a centralized system is being studied at head
quarter level.
As regards the distribution losses for open access, the Petitioner submitted that as per
Regulation 29(2) of the UERC (Terms and Conditions of Intra-State Open Access) Regulations, 2010,
Distribution Loss on Open Access Energy are required to be calculated by applying the following
formula:-
“Average Distribution Loss – Average Recovery Rate from HT Industry Category / Average Power
Purchase Rate x Applicable Voltage Rebate. Accordingly, distribution losses at 33 Kv and 132 Kv
were computed 13.88% and 8.92% respectively for FY 2014-15.”
UERC (Terms and Conditions of Intra-State Open Access) Regulations, 2015 were issued on
13-01-2015 and as per Regulation 29(2), system distribution losses shall be as determined by the
Commission in the Tariff Order for the open access customers. At the time of issuance of Tariff
Order for FY 2015-16, Regulations, 2015 was applicable and the Commission in the said order
approved the pooled average system distribution losses for FY 2015-16 @ 15%. Thus, the request of
the consumer cannot be accepted in view of the provisions of Regulations.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
74 Uttarakhand Electricity Regulatory Commission
As regards the wheeling charges for Open Access, the Petitioner submitted that the
Wheeling Charges is the sum of all expenses of UPCL other than power purchase expenses and
Transmission charges. As the demand charges has been kept less than the required wheeling
charges, the differential of required wheeling charges and demand charges is also payable as
wheeling charges by the embedded open access consumers.
2.29.1.3 Commission’s Views
Some of the stakeholders have raised the issues related to Open Access such as renewal of
open access, etc, which are governed by Uttarakhand Electricity Regulatory Commission (Terms
and Conditions of Intra State Open Access) Regulations, 2015 and are not relevant to ARR and
Tariff determination process. On the issues raised that no wheeling charge should be levied on open
access consumers as demand charges are already being paid by them, the Commission clarifies that
wheeling charges recovered by embedded open access consumers is net off demand charges
applicable to such consumers in accordance with the provisions of the Regulations.
2.30 Green Cess and Electricity Duty for Open Access Consumers
2.30.1.1 Stakeholder’s Comments
M/s BST Textile Mills (P) Ltd. and M/s Tata Motors submitted that Green Cess @ Rs.
0.10/kWh is levied on open access consumers to create “Green Energy Fund”. As Open Access
consumers are purchasing Renewable Energy Certificates to meet RPO, this will result in duplicity
of charges. They further submitted that the electricity duty shall also be waived for Open Access
consumers.
2.30.1.2 Petitioner’s Response
The Petitioner submitted that as per Section 4 of the Uttarakhand Green Energy Cess Act,
2014, Government of Uttarakhand has levied this cess w.e.f. 01-07-2015 @ Rs. 0.10/unit on the
electricity consumption by Commercial and Industrial Consumers. UPCL is charging this cess as
per Government orders. This cess charged from consumers is payable by UPCL to GoU. Therefore,
the matter may be taken up with GoU.
Further, the Petitioner submitted that as per Section 3 of Uttar Pradesh Electricity (Duty) Act
(Uttarakhand Adaptation and Modification) Order 2001, State Government is empowered to fix the
rates of Electricity Duty to be charged from various categories of consumers. Government of
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 75
Uttarakhand vide its notification no. 79/I/2016-01(3)/01/2003, dated 25-01-2016 has fixed these
rates applicable w.e.f. 1-01-2016. UPCL is charging electricity duty as per Government Orders. The
electricity duty charged from consumers is payable by UPCL to GoU. Therefore, the matter may be
taken up with GoU.
2.30.1.3 Commission’s Views
These issues do not fall under the purview of the Commission.
2.31 Renewable Energy Promotion
2.31.1.1 Stakeholder’s Comment
M/s Bhilangana Hydro Power Ltd. submitted that the Small Hydro Electric Plants
(hereinafter referred as “SHEP”) within the state of Uttrakhand are already under financial stress
due to non-functioning of the REC markets under recovery of cost/poor selling price. Now this
additional cost due to levy of water tax may lead to defaults in meeting the obligations by SHEPs. It
further submitted that UPCL preferably procures Renewable Energy power through competitive
bidding on short term basis and the levy of water tax would mean that SHEP within the State of
Uttarakhand would be at disadvantage from other generators outside the State. The imposition of
water tax affects the competitive leverage of the SHEPs in comparison to the generators from
outside the State. However, the other SHEPs who have entered into a long term PPA with UPCL are
at an advantageous position. The SHEP willing to sell Renewable energy to UPCL on short term
basis are at clear disadvantage to that of SHEP who are under long term PPA with UPCL as they
have no such obligation.
M/s Bhilangana Hydro Power Ltd. submitted that the impact of water tax should be
considered in this tariff as a special provision for only those who are willing to sell RE to UPCL on
short term basis. M/s Bhilangana Hydro Power Ltd. submitted that the Commission should
consider the above submission in order to not only motivate the renewable energy generators in the
State of Uttarakhand to sell renewable energy within the State but also be a big step in promotion of
Renewable Energy in the State of Uttarakhand.
2.31.1.2 Petitioners Reply
The Petitioner submitted that the Commission may take a view in the matter.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
76 Uttarakhand Electricity Regulatory Commission
2.31.1.3 Commission’s Views
This issue is not related to approval of Business Plan, true-up for FY 2014-15, ARR for
second Control Period and Tariff for FY 2016-17.
2.32 Miscellaneous Comments
2.32.1 LED Lamps
2.32.1.1 Stakeholder’s Comment
Shri Mukesh Joshi, Village Joshiyada, Pauri Garhwal and other stakeholders submitted that
there should be a VAT exemption and rebate on the purchase and use LED bulbs.
2.32.1.2 Commission’s View
The issue of taxation including VAT is not under the purview of the Commission and,
therefore, the consumer may take up the matter with the Government. The issue of rebate on
purchase of LEDs has already been dealt in the reply of the Petitioner in Para 2.13.1.2 above and the
Commission agrees with the same.
2.32.2 Payment of Public Lamp connections
2.32.2.1 Stakeholder’s Comment
Shri Ghanshyam Singh Rana, Village Thali, Pauri Garhwal submitted that the bills for street
lighting and public lamps in the hilly areas should be paid by the State Government.
2.32.2.2 Commission’s View
The Commission is of the view that street lighting/public lamps system is the responsibility
of the local bodies namely Municipal Corporations, Panchayats etc. and these local bodies have
elected public representatives as their heads and the staffs in these bodies are primarily
Government employees. In case local bodies decided to handover operation & maintenance of the
above system to UPCL, it conducts the operation and maintenance of street light/public lamp
system as an agency to these local bodies and material cost incurred is borne by these local bodies
while UPCL is entitled for labour charges to be recovered by these local bodies. It is for these bodies
and the Government to decide amongst themselves as to who would be making payments for
electricity consumed by them.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 77
2.32.3 Temporary Connections
2.32.3.1 Stakeholder’s Comment
Shri Viru Bisht submitted that the temporary connection issued for marriages, ceremonies
and other similar purposes are not issued properly and are sometimes irregular connections which
results in burning of transformers due to overloading.
2.32.3.2 Commission’s View
The Commission is of the view that this is a complete menace, wherein due to the
unplanned release of temporary connections in a locality for marriages/
ceremonies/functions/Melas etc. by UPCL’s field officers without even assessing the overall load of
such new temporary connections in the locality vis-à-vis the capacity of the existing transformer in
the locality which would be feeding this enhanced load. This results into failure of the transformer
and consumers of the locality bear the burnt and get adversely affected by the non-supply of power.
Therefore, the Commission directs the Petitioner to issue instructions to its field/
distribution division officers to properly plan and take caution while releasing such temporary
connections and submit a compliance report within one month of the issuance of this Order.
2.32.4 Location of Installation of meters
2.32.4.1 Stakeholder’s Comment
Shri Manoj Chauhan, Shri Pawan Kumar Joshi, Shri Pankaj Kathayat, Shri Mahendra Waldia
present during the hearing at Pithoragarh and some other stakeholders also submitted that the
meters are installed on the electricity poles outside the premises which are residential/shops in
congested markets are getting damaged. Therefore, they requested the Commission for shifting of
the meters to the premises. Further, the consumers also submitted about the existence of old poles
which are not firmly erected causing accidents. Further, the conductors between the span are very
loose and hence, the lines are found to be hanging very low causing accidents and becoming a
major issue of safety.
2.32.4.2 Commission’s View
The Commission enquired from the field officers of the Petitioner about the issues raised by
the consumers. The Executive Engineer, EDD Pithoragarh, UPCL agreed to resolve the problems of
the consumers and shift the meters in a secure place on the consumer premises. Taking a serious
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
78 Uttarakhand Electricity Regulatory Commission
view on the same, the Commission directed Executive Engineer, EDD Pithoragarh to submit a
detailed compliance report of action taken for shifting of the meters to a safer location in or around
the premises within two months. Accordingly, Executive Engineer, EDD Pithoragarh, UPCL is
directed to submit a detailed compliance report on action taken for shifting of the meters to a
safer location in or around the premises within one month of the date of Order.
The Commission also expressed serious concern on the safety aspect. Hence, the
Commission directs the Chief Engineer, Rudrapur Zone, UPCL and Executive Engineer, EDD
Pithoragarh, UPCL to take necessary action and submit the compliance report within one month
of the date of the Order.
2.32.5 Load Shedding
2.32.5.1 Stakeholder’s comments
During the public hearing in Pithoragarh, the consumers also raised the issue of power cut
and load sheddings between 7:00 am to 10:00 a.m. every morning. They requested that the same
should be done away with since in the morning people require electricity for their daily needs.
2.32.5.2 Commission’s View
The Commission enquired the same from the field officers of Pithoragarh division and they
informed the Commission that they carry out the load shedding on the Orders of the District
Administration and local authorities since a large number of people in Pithoragarh have installed
electric pumps on the water supply lines which prevent water from flowing into the premises of
those persons where such pumps are not installed.
The Commission directs the concerned Chief Engineer and Executive Engineer, EDD
Pithoragarh, UPCL to coordinate with the District Administration/Local authorities and resolve
this issue and submit the compliance report within one month of the date of the Order.
2.32.6 Transfer of Petitioner’s personnel
2.32.6.1 Stakeholder’s Comment
Some of the consumers during the hearing submitted that the Petitioner’s personnel posted
in the field like lineman etc. should be transferred on regular intervals and there should be a proper
mechanism laid down by the Petitioner for transfer of lineman from one part of the State to another
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 79
in a definite time frame. Moreover, the Petitioner’s field personnel/staff should be imparted proper
technical training of the job assigned to them.
2.32.6.2 Commission’s View
The Commission has taken note of the above suggestion with regard to the personnel
including lineman of the Petitioner and directs the Petitioner to lay down a policy in this regard
and submit a compliance report within two month of the issuance of this Order.
2.32.7 Departmental employees
2.32.7.1 Stakeholder’s Comment
Some stakeholders/consumers submitted before the Commission that departmental
employees of the Petitioner are not metered and even if they are metered then meter readings are
not being taken.
2.32.7.2 Commission’s View
The Commission takes note of the above and directs the Petitioner to carry out 100%
metering of its departmental employees, to take regular meter readings and to maintain separate
energy account of all its employees on a monthly basis. The Commission directs the Petitioner to
submit a compliance report of the same within one month of the issuance of this Order.
2.32.8 Safety Requirements
2.32.8.1 Stakeholder’s Comment
Shri K.L. Sundriyal representing licensed electrical contractor/wiremen submitted before
the Commission that electrical works inside the buildings are not being carried out by skilled
licenced persons and, hence, these works are not compliant with IE/safety rules and requested the
Commission to make Work Completion Certificates/(B&L form), a compulsory requirement before
the release of new Connection by the Petitioner.
2.32.8.2 Commission’s View
The Commission is of the view that provision for release of new connections are covered in
the relevant Regulations and, therefore, this matter cannot be dealt in the Tariff proceedings as
these are the subject matter of the Regulations.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
80 Uttarakhand Electricity Regulatory Commission
2.33 Views of Advisory Committee Meeting
During the Advisory Committee meeting held on March 4, 2016, the Members made the
following suggestions on the Petition for True of FY 2014-15, Business Plan and MYT for the second
Control Period of FY 2016-17 to FY 2018-19.
• Linking Fixed Charge for domestic consumer category to consumption is detrimental
to the Utility. The Fixed Charge for domestic consumer category should be linked to
the Connected Load/contract Damand.
• Payment of electricity bills should be linked to Direct Benefit Transfer mechanism of
GoI.
• For pre-paid metering, the validity of recharge amount in prepaid metering should
not be restricted to three months and should be carried forward at the time of
recharge. Also recharge/top up should be without any interface with UPCL office.
• Measures need to be taken to procure power by UPCL through long term contracts
rather than short term contracts.
• Voltage rebates may be retained at the present levels or increased further.
• Modes of payment of security deposit by the consumers should not be restricted to
cash payment or Demand Draft and other modes of payment should be allowed.
• Minimum Consumption Guarantee (MCG) encourages wasteful consumption of
electricity and need to be abolished atleast for LT industries. Also MCG should not
be applicable during the period of temporary disconnection.
• Peak hours need to be revisited as the existing definition of peak hours of 8 hours
during winter months in a day of 24 hours is very high.
• Distribution loss for each year may be approved by the Commission in line with the
earlier approved trajectory.
• Payments of bills should be accepted at UPCL collection centres till 4 P.M. in the day
and not only upto 1.30 PM currently in practice at UPCL’s collection centres.
2. Summary of Stakeholders’Objections/Suggestions, Petitioner’s Responses and Commission’s Views
Uttarakhand Electricity Regulatory Commission 81
• Income from the hoardings on the electric poles should be to the account of UPCL
and not to the municipal bodies.
• Return on Equity on government contribution from PDF is not allowable as the PDF
was funded by the public for the specific purpose of utilisation in the power sector of
the State.
• For pre-paid meters, the recharge should be allowed to be made online and wide
publicity publicity should given by UPCL regarding the new initiatives by hosting
them on the website or developing a departmental application.
• Representative of Railways mentioned that electrification and doubling of railway
traction has been sanctioned for some of the routes in the State and some new routes
have been proposed. As some of the State Electricity Regulators have incentivised the
tariff of railway traction, the tariff of railway traction in the State may also be
incentivised for the promotion of projects in the State.
2.33.1.1 Commission’s Views
The issues related to fixed charge, prepaid metering system, power procurement, voltage
rebates, security deposit, MCG, duration of peak hours, distribution losses/trajectory, RoE & tariff
rationalisation have been discussed in detail in this Order. However, issues related to standard of
services offered by the Petitioner have been particularly discussed in this Chapter and how the
Commission is regularly monitoring technical & commercial performance of the Petitioner keeping
in view the consumer services, specific/centric Regulations of the Commission. The Commission
has compiled a Charter of Services which is a collection of the provisions of aforesaid Regulations.
Also, the Commission has approved a Complaint Handling Procedure for the Petitioner which is IT
driven mechanism with minimal manual intervention. All the abovesaid Regulations, Codes,
Charter of Services & Complaint Handling Procedures are available in the website of Commission
www.uerc.gov.in.
Uttarakhand Electricity Regulatory Commission 82
3. Petitioners’s Submissions, Commission’s Analysis, Scrutiny
and Conclusion on Business Plan for the second Control Period
3.1 Statutory Requirement
The Commission had notified the UERC Tariff Regulations, 2011on December 19, 2011 in
accordance with the provisions of the Act. The above Regulations were applicable for determination
of Tariff for the first Control Period from FY 2013-14 to FY 2015-16. The Commission had further
notified the UERC Tariff Regulations, 2015 on September 10, 2015 applicable for determination of
Tariff for the second Control Period from FY 2016-17 to FY 2018-19.
3.2 Multi Year Tariff Framework
As regards the Multi Year Tariff Framework, UERC Tariff Regulations, 2015 specifies as
follows:
“4. Multi-year Framework
The Multiyear tariff framework shall be based on the following: -
a) Business plan submitted by the applicant for the entire control period for the approval
of the Commission prior to the beginning of the control period;
b) Applicant’s forecast of expected ARR for each year of the control period, based on
reasonable assumptions and financial & operational principles/parameters laid down
under these Regulations submitted alongwith the MYT petition for determination of
Aggregate Revenue Requirement and Tariffs for first year of the control period;
c) Trajectory for specific parameters as may be stipulated by the Commission based on
submissions made by the Licensee, actual performance data of the Applicants and
performance achieved by similarly placed utilities;
d) Annual review of performance shall be conducted vis-à-vis the approved forecast and
categorization of variations in performance into controllable factors and uncontrollable
factors;
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 83
e) Sharing of excess profit or loss due to controllable and uncontrollable factors as per
provisions of these Regulations.
…
7. Determination of Baseline
The baseline values (operating and cost parameters) for the base year of the control period
shall be determined by the Commission based on the approved values by the Commission, the
latest audited accounts, estimates for the relevant year, prudence check and other factors
considered by the Commission.
The Commission may re-determine the baseline values for the base year based on the actual
audited accounts of the base year.”
3.3 Business Plan for the second Control Period
Regulation 8 of the UERC Tariff Regulations, 2015 specifies as follows:
“8. Business Plan
(1) An Applicant shall submit, under affidavit and as per the UERC (Conduct of Business)
Regulations, 2014, a Business Plan by November 30th, 2015, for the Control Period of three (3)
financial years from April 1, 2016 to March 31, 2019,
...
c) The Business Plan for the Distribution Licenses shall be for the entire control period and shall,
interalia, contain-
(i) Sales/demand forecast for each consumer category and sub-categories for each year of
the control period;
(ii) Distribution loss reduction trajectory for each year of the control period, including
details of the measures proposed to be taken for achieving the target loss;
(iii) Power procurement plan in case of long term, medium term and short term based on
the sales forecast and distribution loss trajectory for each year of the business plan period;
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
84 Uttarakhand Electricity Regulatory Commission
the power procurement plan may also include energy efficiency and demand side
management measures;
(iv) Collection efficiency improvement trajectory for each year of the control period;
(v) Capital investment plan considering the sales/demand forecast, power procurement
plan, distribution loss trajectory, targets for quality of supply, etc. The capital investment
plan shall be consistent with the perspective plan drawn by the State Transmission Utility
(STU), and the investment plan should also include yearly phasing of capital expenditure
alongwith the source of funding, financing plan and corresponding capitalisation schedule;
(vi)The appropriate capital structure of each scheme proposed and cost of financing
(interest on debt and return on equity), terms of the existing loan agreements, etc;
(vii) Details related to availability of power from renewable energy sources and actions
proposed for complying with the RPO specified by the Commission.
...
(2) The Applicant shall also submit the details in respect of its manpower planning for the
Control Period as part of Business Plan.
(3) The Commission shall scrutinize and approve the business plan after following the due
consultation process.”
With regard to Sales Forecast, Regulation 77 of the UERC Tariff Regulations, 2015 specifies
as follows:
“77. Sales Forecast
(1) Considering the importance of capturing seasonal variation, Monthly Sales Forecast for
the Control Period shall be done in respect of each consumer category/sub-category and to
each tariff slab within such consumer category/sub-category, based on the past trends, as far
as possible and shall be submitted to the Commission for approval along with the Business
Plan. Suitable adjustments shall be made to reflect the effect of known and measurable
changes with respect to number of consumers, the connected load and the energy
consumption, thereby removing any abnormality in the past data.
Provided that where the Commission has stipulated a methodology for forecasting sales to any
particular tariff category, the Distribution Licensee shall incorporate such methodology in
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 85
developing the sales forecast for such tariff category.
(2) The sales forecast shall be consistent with the load forecast prepared as part of the long-
term power procurement plan submitted as a part of Business Plan under these Regulations
and shall be based on past data and reasonable assumptions regarding the future.
(3) The Commission shall examine the forecasts for reasonableness based on growth in
number of consumers, the connected load and the energy consumption in previous years and
anticipated growth in the next year and any other factor, which the Commission may consider
relevant and approve the projected sale of electricity to consumers with such modifications as
deemed fit.”
Regarding Distribution Losses, Regulation 79 of the UERC Tariff Regulations, 2015 specifies
as follows:
“79. Distribution Losses
(1) Energy loss in the distribution system shall be called Distribution Loss.
(2) Distribution Loss above and up to a particular voltage level shall be calculated as the
difference between the energy initially injected into the distribution system and the sum of
energy sold up to that level and energy delivered to next voltage level.
% Distribution Loss above and up to a particular voltage level shall be expressed in
terms of Distribution Loss up to that level as a percentage of the energy initially injected into
the distribution system.
(3) The Commission may require information on Circle-wise/Division-wise and/or month-
wise Distribution loss calculation.
(4) To substantiate the Distribution Loss calculations, the Commission may require the
Distribution Licensee to conduct proper and reliable energy audit.
(5) The Distribution Licensee shall also propose voltage-wise losses for remaining years of the
control period from FY 2017-18 onwards for the determination of voltage-wise cost of supply.
The Commission shall examine the filings made by the licensee for the distribution loss
trajectory for each year of the control period and approve the same with modification as it may
consider necessary.
(6) The Commission may ask Distribution Licensee to submit detailed information on
voltage-wise Distribution Losses segregating them into Technical loss (i.e. Ohmic/Core loss
in the lines, substations and equipment) and Commercial Loss (i.e. unaccounted energy due
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
86 Uttarakhand Electricity Regulatory Commission
to metering inaccuracies/inadequacies, pilferage of energy, etc.). The Commission shall
examine the filings made by the Distribution Licensee in respect of distribution loss
(segregated into technical loss and commercial loss) and approve the same with modification,
as it may consider necessary.
(7) The Commission may fix targets, both long term and short term, for each year of control
period for loss reduction to bring down the Distribution loss levels (both technical and
commercial) gradually to acceptable norms of efficiency.”
Regarding Power Procurement Plan, Regulation 73 of the UERC Tariff Regulations, 2015
specifies as follows:
“73. Power Procurement Plan
(1) The Distribution Licensee shall prepare a plan for procurement of power to serve the
demand for electricity in its area of supply and submit such plan to the Commission for
approval:
Provided that such power procurement plan shall be submitted for the second Control Period
commencing on April 1, 2016:
Provided further that the power procurement plan, approved as a part of the Business Plan,
shall be submitted along with the application for determination of tariff.
Provided that the power procurement plan submitted by the Distribution Licensee may
include long-term, medium-term and short-term power procurement sources of power, in
accordance with these Regulations. However, the distribution licensee should as far as
possible, not plan for short-term purchases except for conditions specified in Regulations 75
and should endeavor to meet its requirement from long term and medium term power
procurement and make a plan accordingly.
(2) The power procurement plan of the Distribution Licensee shall comprise of the following:
a) A quantitative forecast of the unrestricted demand for electricity for each tariff
category, within its area of supply over the Control Period;
b) An estimate of the quantities of electricity supply from the identified sources of
generation and power purchase;
c) An estimate of availability of power to meet the base load and Peak load
requirement.
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 87
Provided that estimate should be monthly estimation of demand and supply expressed
both in Mega-Watt (MW) as well as in Million Units (MUs).
d) Standards to be maintained with regard to quality and reliability of supply, in
accordance with the UERC (Standards of Performance) Regulations, 2007, as
amended from time to time;
e) Measures proposed to be implemented as regards energy conservation and energy
efficiency;
f) The requirement for new sources of power generation and/or procurement,
including augmentation of generation capacity and identified new sources of supply,
based on (a) to (d) above;
g) The plan for procurement of power including quantities and cost estimates for such
procurement:
Provided that the forecast/estimate contained in the long-term procurement plan shall
be separately stated for peak and off-peak periods, in terms of quantities of power to be
procured (in millions of units of electricity) and maximum demand (in MW / MVA):
Provided further that the forecasts/estimates shall be prepared for each month of the
Control Period:
Provided also that the long-term procurement plan shall be a cost-effective plan based
on available information regarding costs of various sources of supply.
h) Short-term power procurement proposed shall be in accordance with Regulation 75
of these Regulations.
(3) The forecasts/estimates shall be prepared using forecasting techniques based on past data
and reasonable assumptions regarding the future:
Provided that the forecasts/estimates shall take into account factors such as overall economic
growth, consumption growth of electricity-intensive sectors, advent of competition in the
electricity industry, trends in captive power, impact of loss reduction initiatives,
improvement in Generating Station Plant Load Factors and other relevant factors.
(4) Where the Commission has stipulated a percentage of the total consumption of electricity
in the area of a Distribution Licensee to be purchased from co-generation and renewable
sources of energy, the power procurement plan of such Distribution Licensee shall include the
plan for procurement from such sources at least upto the stipulated level.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
88 Uttarakhand Electricity Regulatory Commission
(5) The Distribution Licensee shall be required to forward a copy of the power procurement
plan to the State Transmission Utility for verification of its consistency with the transmission
system plan for the intra-State transmission system;
Provided that the Distribution Licensee may also consult the State Transmission Utility at
the time of preparation of the power procurement plan to ensure consistency of such plan with
the transmission system plan.
(6) The Distribution Licensee may, as a result of additional information not previously known
or available to him at the time of submission of the procurement plan under sub-Regulation
(1) above, apply for a modification in the power procurement plan, for the remainder of the
Control Period, as part of the application for Annual Performance Review:
(7) The Commission may, as a result of additional information not previously known or
available to the Commission at the time of submission of the procurement plan under sub-
Regulation (1) above, if it so deems, either on suo motu basis or on an application made by
any interested or affected party, modify the procurement plan of the Distribution Licensee, for
the remainder of the Control Period, as part of the Annual Performance Review.
(8) The Commission shall review the power procurement plan of the Distribution Licensee, or
any proposed modification thereto, and upon such review being completed, the Commission
shall either-
a) Issue an order approving the power procurement plan, or modifications thereto,
subject to such modifications and conditions as it may deem appropriate; or
b) Reject the power procurement plan or application for modification thereto, for
reasons recorded in writing, if such plan is not in accordance with the guidelines
contained in this Part, and direct the Distribution Licensee to submit a revised plan
based on such considerations as it may specify:
Provided that the Distribution Licensee shall be given reasonable opportunity of being heard
before rejecting its power procurement plan.”
Regarding Capital Investment Plan, Regulation 71 of the UERC Tariff Regulations, 2015
stipulates as follows:
“71. Capital Investment Plan
(1) The Distribution Licensee shall file a detailed capital investment plan, financing plan and
physical targets for each year of the Control Period, for meeting the requirement of load
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 89
growth, reduction in distribution losses, improvement in quality of supply, reliability,
metering, reduction in congestion, etc. to the Commission for approval as a part of Business
Plan. The capital investment plan should be filed at the beginning of the Control Period.
(2) The investment plan shall be a least cost plan for undertaking investments on
strengthening and augmentation of the distribution system for meeting the requirement of
load growth, reduction in distribution losses, improvement in quality of supply, reliability,
metering, etc.
(3) The investment plan shall cover all capital expenditure projects to be undertaken by the
Transmission Licensee in the Control Period and shall be in such form as may be stipulated
by the Commission from time to time.
(4) The prior approval of the Commission shall be required for all capital expenditure
schemes of the value exceeding the ceiling specified by the Commission in the distribution
license.
(5) The investment plan shall be accompanied by such information, particulars and
documents as may be required showing the need for the proposed investments, alternatives
considered, cost/benefit analysis and other aspects that may have a bearing on the wheeling
tariff and retail tariffs. The investment plan shall also include the capitalisation schedule and
financing plan.
…”
In accordance with Regulation 8, Regulation 71, Regulation 73, Regulation 77 & Regulation
79 of UERC Tariff Regulations, 2015, the Petitioner submitted the Business Plan for the second
Control Period from FY 2016-17 to FY 2018-19. The Petitioner in its Business Plan Petition and
subsequent submissions has submitted the Sales Forecast, distribution loss reduction trajectory,
power procurement plan, collection efficiency improvement trajectory, capital expenditure plan,
capitalisation plan, and human resources plan for the second Control Period from FY 2016-17 to FY
2018-19. The Petitioner’s submissions and the Commission’s analysis on the approval of the
Business Plan for UPCL for the second Control Period from FY 2016-17 to FY 2018-19 are detailed
below.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
90 Uttarakhand Electricity Regulatory Commission
3.4 Sales Forecast
The Petitioner submitted that in the State of Uttarakhand one of the reasons for the State
witnessing gap between electricity demand and supply is the increase in per capita power
consumption. According to the Power for All document of Ministry of Power, the per capita
electricity consumption in Uttarakhand was 1012 kWh in FY 2011-12 which increased to 1154 kWh
in FY 2014-15 in a span of three years. Based on actual energy sales data, Uttarakhand had energy
consumption CAGR (Compound Annual Growth Rate) of 9.09% over the past five years from FY
2010-11 to FY 2014-15. The actual consumer category wise sales for the past 5 years are as shown in
the Table below:
Table 3.1: Actual consumer category wise sales for FY 2010-11 to FY 2014-15 (MU)
Consumer Category FY 2010-11
FY 2011-12
FY 2012-13
FY 2013-14
FY 2014-15
RTS-1: Domestic 1485.57 1676.70 1795.06 2105.05 2272.98 RTS-2:Non-Domestic 812.52 885.42 953.94 995.76 1069.93 RTS-3: Public Lamps 53.86 66.89 87.20 44.06 46.84 RTS-4: Private Tube-wells / Pumping sets 183.02 188.46 244.80 222.76 268.89 RTS-5: Government Irrigation System 112.97 136.56 130.20 104.23 107.64 RTS-6: Public Water Works 276.37 324.52 302.68 293.37 316.64 RTS-7: LT & HT Industry 4197.72 4805.52 4884.88 5092.57 5371.28 Total LT 234.96 269.78 289.42 287.66 304.79 Total HT 3962.76 4535.74 4595.46 4804.91 5066.49 RTS-8: Mixed Load 120.86 160.26 167.55 177.60 185.68 RTS-9: Railway Traction 7.80 8.39 7.83 11.49 14.70
Total 7250.68 8252.72 8574.15 9046.89 9654.58
The Petitioner further submitted the projected annual sales as per the draft 18th Electric Power
Survey forecast as shown in the Table below:
Table 3.2: Projected sales as per 18th EPS forecast (MU)
Total Annual Sales FY 2012-13
FY 2013-14
FY 2014-15
FY 2015-16
FY 2016-17
FY 2017-18
FY 2018-19
A. Projected Sales (MU) 8216 8832 9387 9974 10600 11265 11974 B. Actual Sales (MU) 8574 9047 9655 - - - - Difference (A-B) -358 -215 -268 - - - -
The Petitioner submitted that for projecting the consumer category-wise sales for each year
of the Control Period, the Adjusted Trend Analysis Method has been adopted. This method
assumes that the underlying factors which drive the demand for electricity are expected to follow
the same trend as in the past. This approach also discounts any outlier (relative to the trend)
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 91
observed in the growth rates over the period of 5 years and excludes the same while making
projections for FY 2016-17 to FY 2018-19. As per this method, Compound Annual Growth Rate
(CAGR) for each consumer category has been computed from the actual sales for the past 5 years
from FY 2010-11 to FY 2014-15. The CAGR calculated for different lengths of time from FY 2010-11
to FY 2014-15 is as shown in the Table below:
Table 3.3: Computed CAGR of sales as submitted by the Petitioner Consumer Category 5 year 4 year 3 year 2 year 1 year
RTS-1: Domestic 10.38% 11.23% 10.69% 12.59% 7.98% RTS-2:Non-Domestic 7.81% 7.12% 6.51% 5.91% 7.65% RTS-3: Public Lamps -1.85% -3.43% -11.20% -18.10% 6.29% RTS-4: Private Tube-wells / Pumping sets 8.22% 10.10% 12.58% 4.81% 20.71% RTS-5: Government Irrigation System -1.65% -1.20% -7.63% -9.08% 3.27% RTS-6: Public Water Works 5.07% 3.46% -0.82% 2.28% 7.93% RTS-7: LT & HT Industry 9.58% 6.36% 3.78% 4.86% 5.47% Total LT 8.59% 6.72% 4.15% 2.62% 5.96% Total HT 9.64% 6.34% 3.76% 5.00% 5.44% RTS-8: Mixed Load 8.62% 11.33% 5.03% 5.27% 4.55% RTS-9: Railway Traction 14.89% 17.15% 20.55% 36.99% 27.98% Total 9.09% 7.42% 5.37% 6.22% 6.72%
The Petitioner submitted that for projecting the sales for the second Control Period from FY
2016-17 to FY 2018-19, first of all sales for FY 2015-16 has been estimated based on the category wise
actual sales in FY 2015-16 in Apr- June, comparing the same with category wise actual sales for Apr-
June for FY 2012-13, FY 2013-14 and FY 2014-15 and total sales for respective years. For forecasting
the expected sales for each year of the Control Period, projected sales for FY 2015-16 have been
considered as the base, i.e. the chosen growth rate is applied over the sales for FY 2015-16.
Subsequently to project the sales for each year, the chosen rates are applied upon the sales of the
preceding year to finally arrive upon the sales for FY 2018-19. Energy sales to un-metered
consumers under Domestic and Private Tube Wells in FY 2014-15 have been re-casted as per the
methodology (based on the connected load for the un-metered consumers vis-à-vis that for metered
consumers in the same consumer category) specified by the Commission before considering them
for projections.
The Petitioner submitted that the sales for various categories of consumers have been
projected in the following manner:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
92 Uttarakhand Electricity Regulatory Commission
• The RTS-1: Domestic and RTS-9: Railway Traction category sales have been
projected based on the year on year average increase in the sales for last five
years excluding the outliers.
• Sales for RTS-2: Non- Domestic, Private Tube-wells and Public Water Works have
been projected based upon the 5 year CAGR of the respective categories.
• Sales for RTS-3: Public Lamps and RTS-5 Government Irrigation System have
been projected to increase at a subjective Rate of 5%.
• Sales for LT and HT categories have been projected based upon 3 year and 2 year
CAGR and for Mixed Load Consumers Y-o-Y increase for FY 2013-14 to FY 2014-
15 has been chosen as per the best possible trends observed.
The projections of consumer category wise sales for the second Control Period from FY 2016-
17 to FY 2018-19 submitted by the Petitioner is shown in the Table below:
Table 3.4: Consumer Category wise sales projected by the Petitioner for FY 2016-17 to FY 2018-19 (MU)
Consumer Category FY 2015-16 (Revised)
Growth Rate
FY 2016-17
FY 2017-18
FY 2018-19
RTS-1: Domestic 2360 8.72% 2566 2790 3033 RTS-2:Non-Domestic 1099 7.81% 1185 1278 1378 RTS-3: Public Lamps 50 5.00% 52 55 58 RTS-4: Private Tube-wells / Pumping sets 313 8.22% 338 366 396
RTS-5: Government Irrigation System 118 5.00% 124 131 137
RTS-6: Public Water Works 333 5.07% 349 367 386 RTS-7: LT & HT Industry 5736 6020 6318 6631 Total LT 313 4.15% 326 339 353 Total HT 5423 5.00% 5694 5979 6278 RTS-8: Mixed Load 203 4.55% 213 222 232 RTS-9: Railway Traction 15 6.90% 16 17 18 Total 10227 10864 11544 12269
The Petitioner submitted that the annual projected sales as shown in the Table above have
been further projected month-wise and category wise. For projection of sale for sub-categories of
any consumer category on a monthly basis over the Control Period, UPCL has used the seasonality
in energy consumption and the ratio of actual sales in the sub-category to total sales of the category
as observed in the actual sales data of FY 2014-15.
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 93
The month wise and consumer category-wise sales projected by the Petitioner for FY 2016-17
to FY 2018-19 is as shown in the Table below:
Table 3.5: Month wise and Consumer Category wise sales projected by the Petitioner for FY 2016-17 (MU)
Consumer Category
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
Jan-17
Feb-17
Mar-17 Total
RTS-1: Domestic 181 199 220 224 243 237 217 219 213 209 202 201 2566
RTS-2: Non-Domestic 83 93 104 109 109 109 101 95 89 99 95 99 1185
RTS-3: Public Lamps 4 4 4 4 4 4 5 5 3 4 4 5 52
RTS-4: Private Tube-wells / Pumping sets
14 17 33 39 18 18 22 18 44 60 27 28 338
RTS-5: Government Irrigation System
8 11 12 12 9 8 8 11 10 13 10 11 124
RTS-6: Public Water Works 25 31 32 26 29 24 32 33 28 31 31 28 349
RTS-7: LT & HT Industry 487 499 501 498 513 519 492 495 495 513 502 506 6020
Total LT 24 27 26 28 33 27 26 29 26 29 26 25 326 Total HT 463 472 475 470 480 492 466 466 469 484 476 481 5694 RTS-8: Mixed Load 16 15 16 17 17 18 15 14 15 22 29 20 213
RTS-9: Railway Traction
1 1 1 1 1 1 1 1 1 1 1 2 16
Total 819 871 925 931 944 937 893 893 901 953 902 898 10864
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
94 Uttarakhand Electricity Regulatory Commission
Table 3.6: Month wise and Consumer Category wise sales projected by the Petitioner for FY 2017-18 (MU)
Consumer Category
Apr-17
May-17
Jun-17
Jul-17
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18 Total
RTS-1: Domestic 197 216 240 244 265 258 236 238 231 228 220 218 2790 RTS-2: Non-Domestic 90 100 112 118 118 117 109 103 96 107 102 106 1278
RTS-3: Public Lamps 5 5 5 5 5 4 5 5 4 5 5 5 55
RTS-4: Private Tube-wells / Pumping sets
15 19 36 42 19 19 24 19 48 65 29 31 366
RTS-5: Government Irrigation System
8 12 13 13 9 9 8 12 11 14 11 12 131
RTS-6: Public Water Works 26 33 33 27 30 25 34 35 30 33 32 29 367
RTS-7: LT & HT Industry 511 523 526 522 539 544 517 520 520 538 527 531 6318
Total LT 25 28 27 29 35 28 27 30 27 30 27 26 339 Total HT 486 495 499 493 504 516 490 490 493 508 500 505 5979 RTS-8: Mixed Load 16 15 16 18 18 18 16 15 16 23 30 21 222
RTS-9: Railway Traction 1 1 1 1 1 2 1 2 1 1 1 2 17
Total 869 925 983 990 1004 996 949 948 957 1012 957 953 11544
Table 3.7: Month wise and Consumer Category wise sales projected by the Petitioner for FY 2018-19 (MU)
Consumer Category Apr-18
May-18
Jun-18
Jul-18
Aug-18
Sep-18
Oct-18
Nov-18
Dec-18
Jan-19
Feb-19
Mar-19 Total
RTS-1: Domestic 214 235 261 265 288 281 256 259 252 247 239 237 3033 RTS-2: Non-Domestic 97 108 121 127 127 126 117 111 104 115 110 115 1378 RTS-3: Public Lamps 5 5 5 5 5 4 5 6 4 5 5 5 58 RTS-4: Private Tube-wells / Pumping sets 16 20 39 46 21 21 26 21 52 70 31 33 396
RTS-5: Government Irrigation System 8 12 13 14 10 9 9 12 11 14 11 12 137
RTS-6: Public Water Works 27 34 35 28 32 26 36 37 31 34 34 31 386
RTS-7: LT & HT Industry 536 549 552 548 565 571 542 545 545 565 553 557 6631
Total LT 26 29 28 30 36 29 28 31 28 32 28 27 353 Total HT 510 520 524 518 529 542 514 514 517 533 525 530 6278 RTS-8: Mixed Load 17 16 17 18 19 19 16 16 17 24 31 21 232 RTS-9: Railway Traction 1 1 2 1 2 2 2 2 2 1 1 2 18
Total 923 982 1045 1053 1068 1059 1009 1008 1018 1076 1017 1013 12269
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 95
The Petitioner submitted that for making projections of connected load and number of
consumers, the actual connected load/number of consumers for FY 2015-16 for each consumer
category is taken as the base, i.e. the chosen growth rate is applied over the actual connected
load/number of consumers for FY 2015-16 to make the projections for each category for FY 2016-17,
and for projections for FY 2017-18, the growth rate is applied on the projected connected
load/number of consumers of FY 2016-17, while for FY 2018-19, the growth rate is applied on
projected connected load/number of consumers for FY 2017-18. The projected connected load for
FY 2016-17 to FY 2018-19 for each consumer category is as shown in the Table below:
Table 3.8: Consumer Category wise connected load projected by the Petitioner for FY 2016-17 to FY 2018-19 (kW)
Consumer Category FY 2015-16 (Revised Estimate)
Growth Rate FY 2016-17 FY 2017-18 FY 2018-19
RTS-1: Domestic 2481002 8.33% 2687601 2911404 3153844 RTS-2:Non-Domestic 835244 7.73% 899794 969333 1044245 RTS-3: Public Lamps 12999 6.93% 13900 14864 15894 RTS-4: Private Tube-wells / Pumping sets 144618 12.79% 163111 183968 207492
RTS-5: Government Irrigation System 55871 7.78% 60215 64897 69943
RTS-6: Public Water Works 74885 13.67% 85122 96760 109989
RTS-7: LT & HT Industry 1778773 1874702 1975814 2082389
Total LT 195252 4.75% 204521 214231 224402 Total HT 1583521 5.47% 1670181 1761583 1857987 RTS-8: Mixed Load 64445 5.00% 67670 71055 74610 RTS-9: Railway Traction 6800 0.00% 6800 6800 6800
Total 5454637 7.41% 5858916 6294895 6765206
The projected number of consumers for FY 2016-17 to FY 2018-19 for each consumer
category is as shown in the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
96 Uttarakhand Electricity Regulatory Commission
Table 3.9: Consumer Category wise number of consumers projected by the Petitioner for FY 2016-17 to FY 2018-19 (No.)
Consumer Category FY 2015-16 (Revised Estimate)
Growth Rate FY 2016-17 FY 2017-18 FY 2018-19
RTS-1: Domestic 1740928 5.55% 1837465 1939355 2046896 RTS-2:Non-Domestic 205349 5.81% 217284 229912 243275 RTS-3: Public Lamps 764 8.23% 827 895 969 RTS-4: Private Tube-wells / Pumping sets 28307 5.22% 29785 31339 32975
RTS-5: Government Irrigation System 1533 6.23% 1629 1730 1838
RTS-6: Public Water Works 1293 4.89% 1356 1422 1492 RTS-7: LT & HT Industry 11465 11558 11653 11751 Total LT 9593 0.36% 9627 9661 9696 Total HT 1872 3.16% 1931 1992 2055 RTS-8: Mixed Load 79 7.03% 85 91 97 RTS-9: Railway Traction 1 0.00% 1 1 1 Total 1989719 5.54% 2099990 2216400 2339294
The Commission observed that the sales projections made by the Petitioner for the second
Control Period are the restricted sales projections as the Petitioner has computed the growth rates
based on actual restricted sales and then applied the growth rates on the actual restricted sales. It
would be important to note that the actual load shedding in FY 2013-14 and FY 2014-15 was to the
extent of 458 MU and 370 MU respectively.
The Commission is of the view that for the purpose of planning, it would be more
appropriate to project the unrestricted sales for the second Control Period from FY 2016-17 to FY
2018-19 as UPCL can arrange to procure additional power from the market due to improvement in
demand supply situation across the country as well as in the Northern Region. Accordingly, the
Commission has projected the unrestricted sales for the second Control Period.
For projecting the category-wise sales for the second Control Period from FY 2016-17 to FY
2018-19, the Commission analysed the growth rates derived based on re-casted unrestricted sales
data for the previous 6 years. The Commission has normalized the growth rate, wherever,
considered appropriate based on the ground reality, to realistically estimate the sales figures for a
particular category of consumers for each year of the Control Period. The Commission has first
applied the growth rates so derived on the actual re-casted sales figures for FY 2014-15 to estimate
the category wise sales for FY 2015-16 and, thereafter, applying the same growth rates on the
estimated sales figures for FY 2015-16, category wise sales figures has been projected from FY 2016-
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 97
17 onwards for the second Control Period.
The category-wise growth rates considered by the Commission for different categories of
consumers and sales projections for the Control Period are discussed in the following paras.
3.4.1 Domestic (RTS-1)
The Petitioner has considered a growth rate of 8.72% based on average growth less outliers
in respect of sales of domestic consumers and applied the same over the restricted sales.
Accordingly, the Petitioner has projected energy sales to domestic consumers for FY 2016-17 as
2565.79MU.
The 5 years, 4 years, 3 years, 2 years and 1 year CAGR of unrestricted sales for domestic
category works out to 9.58%, 11.50%, 12.92%, 12.69% and 10.83% respectively. Considering the
CAGR of previous years and year on year variation, the Commission for projecting the sales for the
second Control Period has considered five year CAGR of 9.58%. Hence, the sales for domestic
Category projected by the Commission for FY 2016-17, FY 2017-18 and FY 2018-19 works out to
2800.54 MU, 3068.92 MU and 3363.03 MU respectively.
3.4.2 Non-Domestic (RTS-2)
The Petitioner has considered a growth rate of 7.81% based on 5 years CAGR in respect of
sales of non-domestic consumers and applied the same over the restricted sales. Accordingly, the
Petitioner has projected energy sales to non-domestic consumers for FY 2016-17 as 1185 MU.
The 5 years, 4 years, 3 years, 2 years and 1 year CAGR of unrestricted sales for non-domestic
category works out to 7.02%, 6.84%, 6.73%, 4.74% and 6.16% respectively. Considering the CAGR of
previous years and year on year variation in sales, the Commission for projecting the sales for the
second Control Period has considered four years CAGR of 6.84%. Hence, the sales for non-domestic
Category projected by the Commission for FY 2016-17, FY 2017-18 and FY 2018-19 works out to
1256.82 MU, 1338.24 MU and 1424.93 MU respectively.
3.4.3 Public Lamps (RTS-3)
The Petitioner has estimated sales to Public Lamps on the basis of growth rate of 5% applied
over the restricted sales. Accordingly, the Petitioner has projected a total sale of 52 MU for FY 2016-
17 for this category.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
98 Uttarakhand Electricity Regulatory Commission
Based on the analysis of sales of previous years, it is observed that the 5 years, 4 years, 3
years and 2 years CAGR of unrestricted sales works out to be negative, while for FY 2014-15, the
growth rate with respect to previous year is 8.32%. As no clear trend is observed in the sales of
previous years, the Commission has considered a growth rate of 5% for projecting the sales for the
second Control Period for this category. With these assumptions, the total consumption of public
lamps as projected by the Commission for FY 2016-17, FY 2017-18 and FY 2018-19 works out to 49.22
MU, 51.69 MU and 54.27 MU respectively.
3.4.4 Private Tube-Wells (RTS-4)
The Petitioner has considered a growth rate of 8.22% based on 5 years CAGR applied over
the restricted sales and projected the consumption for Private Tube-Wells as 338 MU for FY 2016-17.
The 5 years CAGR of unrestricted sales for PTW category works out to 9.64%, while the 4
years CAGR, 3 years CAGR and 2 years CAGR works out to be very high. Considering year on year
variation in sales, the Commission for projecting the sales for the second Control Period has
considered a growth rate of 7%. Hence, the sales for PTW Category projected by the Commission
for FY 2016-17, FY 2017-18 and FY 2018-19 works out to 318.57 MU, 340.87 MU and 364.73 MU
respectively.
3.4.5 Government Irrigation Systems (RTS-5)
The Petitioner has estimated the sales to Government Irrigation System on the basis of the
growth rate of 5% applied over the restricted sales. Accordingly, the Petitioner has projected a total
sale of 124 MU for FY 2016-17 in this category.
As no clear trend is observed in the sales of previous years for this category, the Commission
has considered a growth rate of 5% for projecting the sales for the second Control Period for this
category. With these assumptions, the total consumption of GIS as projected by the Commission for
FY 2016-17, FY 2017-18 and FY 2018-19 works out to 123.18 MU, 129.34 MU and 135.81 MU
respectively.
3.4.6 Public Water Works (RTS-6)
The Petitioner has considered a growth rate of 5.07% based on 5 years CAGR applied over
the restricted sales and projected the consumption for PWW as 349 MU for FY 2016-17.
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 99
As no clear trend is observed in the sales of previous years for this category, the Commission
has considered a growth rate of 5% for projecting the sales for the second Control Period for this
category. With these assumptions, the total consumption of PWW as projected by the Commission
for FY 2016-17, FY 2017-18 and FY 2018-19 works out to 361.63 MU, 379.71 MU and 398.70 MU
respectively.
3.4.7 Industry (RTS-7)
The Petitioner has considered a growth rate of 4.15% based on 3 years CAGR applied over
the restricted sales for projecting the sales of LT Industry. The Petitioner projected the consumption
for LT Industry as 326 MU for FY 2016-17.
The 5 years, 4 years, 3 years, 2 years and 1 year CAGR of unrestricted sales for LT Industry
works out to 7.88%, 6.13%, 4.43%, 1.59% and 4.70% respectively. Considering the CAGR of previous
years and year on year variation in sales, the Commission for projecting the sales for LT Industry
for the second Control Period has considered three year CAGR of 4.43%. Hence, the sales for LT
Industry projected by the Commission for FY 2016-17, FY 2017-18 and FY 2018-19 works out to
345.05 MU, 360.34 MU and 376.30 MU respectively.
The Petitioner has considered a growth rate of 5% based on a 2 years CAGR applied over the
restricted sales for projecting the sales of HT Industry. The Petitioner projected the consumption for
HT Industry as 5694.15 MU for FY 2016-17.
The 5 years, 4 years, 3 years, 2 years and 1 year CAGR of unrestricted sales for HT Industry
category works out to 8.92%, 5.75%, 4.11%, 5.10% and 4.21% respectively. Considering the CAGR of
previous years, year on year variation in sales and views expressed by the industrial consumers, the
Commission for projecting the sales for HT Industry for the second Control Period has considered
three year CAGR of 4.11%. Hence, the sales for HT Industry projected by the Commission for FY
2016-17, FY 2017-18 and FY 2018-19 works out to 5701.46 MU, 5936.01 MU and 6180.22 MU
respectively.
3.4.8 Mixed Load (RTS-8)
The Petitioner has considered a growth rate of 4.45% based on the growth in one year which
is applied over the restricted sales for projecting the sales of Mixed Load. Accordingly, the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
100 Uttarakhand Electricity Regulatory Commission
Petitioner projected the consumption for Mixed Load as 213 MU for FY 2016-17.
The 5 years, 4 years, 3 years, 2 years and 1 year CAGR of unrestricted sales for Mixed Load
category works out to 7.90%, 10.72%, 5.32%, 4.22% and 3.32% respectively. Considering the CAGR
of previous years and year on year variation in sales the Commission for projecting the sales for
Mixed Load for the second Control Period has considered three year CAGR of 5.32%. Hence, the
sales for this Category projected by the Commission for FY 2016-17, FY 2017-18 and FY 2018-19
works out to 213.80 MU, 225.16 MU and 237.13 MU respectively.
3.4.9 Railway Traction (RTS-9)
The Petitioner has considered a growth rate of 6.90% over the restricted sales for projecting
the sales of Railway Traction. Accordingly, the Petitioner projected the consumption for Railway
Traction as 16 MU for FY 2016-17.
As the 5 years, 4 years, 3 years, 2 years and 1 year CAGR of unrestricted sales for this
category works out to be on higher side, the Commission for projecting the sales for Railway
Traction for the second Control Period has considered the growth rate of 7%. Hence, the sales for
this Category projected by the Commission for FY 2016-17, FY 2017-18 and FY 2018-19 works out to
17.47 MU, 18.69 MU and 20 MU respectively.
The summary of the category-wise sales projected by the Petitioner and as approved by the
Commission for the second Control Period is given in the Table below:
Table 3.10: Category Wise Sales Projections for second Control Period (MU)
S.No Category Petitioner’s Projections Approved
FY 2016-17
FY 2017-18
FY 2018-19
FY 2016-17
FY 2017-18
FY 2018-19
A. Domestic 2,566 2,790 3,033 2,801 3,069 3,363 B. Non Domestic 1,185 1,278 1,378 1,257 1,338 1,425 C. Public Lamps 52 55 58 49 52 54 D. Private Tube Wells (PTW) 338 366 396 319 341 365 E. Government Irrigation System (GIS) 124 131 137 123 129 136 F Public Water Works (PWW) 349 367 386 362 380 399 G Industrial Consumers
LT Industries 326 339 353 345 360 376
HT Industries 5,694 5,979 6,278 5,701 5,936 6,180
Total 6,020 6,318 6,631 6,047 6,296 6,557 H Mixed Load 213 222 232 214 225 237 I Railway Traction 16 17 18 17 19 20
GRAND TOTAL 10,864 11,544 12,269 11,188 11,849 12,555
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 101
3.5 Efficiency Parameters
3.5.1 Distribution Losses
The Petitioner submitted the year-wise status of distribution losses which is as shown in the
Table below:
Table 3.11: Year wise distribution losses as submitted by the Petitioner
Year Approved by the Commission
Actual Estimated by the
Commission
Actual as per UPCL record
FY 2003-04 40.32% 35.55% 29.52% FY 2004-05 36.32% 36.63% 26.66% FY 2005-06 32.32% 33.38% 28.37% FY 2006-07 28.32% 32.84% 29.73% FY 2007-08 24.32% 30.98% 29.65% FY 2008-09 22.32% 31.02% 28.01% FY 2009-10 20.32% 25.09% 24.53% FY 2010-11 19.00% 22.72% 21.61% FY 2011-12 18.00% 21.27% 19.96% FY 2012-13 17.00% 21.70% 20.50% FY 2013-14 16.00% 20.66% 19.18% FY 2014-15 15.50% - 18.53% FY 2015-16 15.00% - -
The Petitioner submitted that the Commission in the past had considered the deemed
revenue due to non-achievement of target distribution losses. Out of the accumulated losses of Rs.
1695 Crore as on March 31, 2014 for the Petitioner, Rs. 1022.51 Crore are towards the deemed
revenue considered by the Commission on account of non-achievement of target distribution losses
from FY 2003-04 to FY 2013-14.
The Petitioner further submitted that it has taken the following initiatives for loss reduction:
• Installation of Capacitor Bank at 33/11 kV substations;
• Implementation of R-APDRP Part A Scheme;
• Implementation of R-APDRP Part B Scheme;
• Implementation of Double metering in selected 11 kV and 33 kV consumers;
• Implementation of AMR;
• Replacement of mechanical meters with electronic meters and installation of
electronic meters in un-metered connection;
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
102 Uttarakhand Electricity Regulatory Commission
• Laying of LT ABC;
• DT metering;
• Replacement of defective meters;
• Procurement of high value consumer management system (HVCMS).
The Petitioner submitted that at a distribution loss level below 20%, reduction of distribution
losses is extremely difficult and the reduction in losses reduces considerably. The Petitioner
proposed to reduce the distribution losses by 1% during FY 2015-16 and further 0.5% per annum
during every year of the second Control Period from FY 2016-17 to FY 2018-19. The proposed
distribution loss trajectory for the second Control Period from FY 2016-17 to FY 2018-19 is as shown
in the Table below:
Table 3.12: Distribution Loss trajectory proposed by the Petitioner for FY 2016-17 to FY 2018-19
Particulars FY 2014-15 (Restated)
FY 2015-16 (Projected)
FY 2016-17 (Projected)
FY 2017-18 (Projected)
FY 2018-19 (Projected)
Distribution Losses 18.79% 17.79% 17.29% 16.79% 16.29%
The distribution loss target approved by the Commission and the actual distribution loss
achieved for the first Control Period from FY 2013-14 to FY 2015-16 is as shown in the Table below:
Table 3.13: Distribution Losses for FY 2013-14 to FY 2015-16
Particulars FY 2013-14 FY 2014-15 FY 2015-16 Approved Actual Approved Actual Approved Proposed
Distribution Losses 16.00% 19.18% 15.50% 18.79% 15.00% 17.79%
As regards the distribution loss trajectory of UPCL, the Commission would like to refer to
the MoU signed between the Ministry of Power, Government of India and the Government of
Uttarakhand on March 30, 2001. The purpose of the MoU was to affirm the commitment of
Uttarakhand towards upgrading the services in the power sector with a view to providing
commercial viability and quality 24-hour supply at affordable rates to all its residents. It was,
further, agreed that Uttarakhand will undertake Energy Audit at all levels in order to reduce system
losses to bring them progressively to the level of 20% by March, 2004. This was required to be done
in a time bound manner, and in the following steps:
a) Joint verification and sealing of interface points with power suppliers.
b) To meter all 11 kV feeders by 31.03.2001 & in no case later than 30.09.2001.
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 103
c) 100% metering of all consumers to be done by 31.12.2001.
d) Number of billing and collection centers including computerized billing centers to be
increased by 31.12.2001.
e) Identify and develop distribution circles as profit centers. Separate commercial
accounts/shadow Balance Sheets for such centers to be prepared from 31.03.2001.
f) In case commercial viability in distribution is not attained by 31.03.2003,
corporatization/co-operatization/privatization of distribution, to be considered.
g) To consider innovations such as the creation of user groups/peoples‘ cooperatives to
oversee LT distribution in composite clusters and to take over the responsibility of
billing, collection, theft detection, etc.
Clearly the idea was to reduce the distribution losses and bring them down to the level of
20% by March, 2004. In this connection, it is also to be underlined that while fixing the loss
reduction trajectory, the Commission, did not consider the losses as given under the FRP for FY
2002-03, i.e. 38%, instead considering the ground realities, it fixed the opening losses for FY 2002-03
at 44.32%, i.e. 6.32% higher than the losses of 38.00% considered under the FRP. The Commission,
therefore, allowed the utility an extra cushion and comfort to reduce distribution losses in a gradual
manner. Further, the trajectory for reduction of losses by 4% every year, specified by the
Commission was applicable for an initial period of 5 years only, i.e. upto FY 2007-08. Thereafter,
while determining the UPCL’s ARR and Retail Supply Tariff for FY 2007-08 and FY 2008-09, the
Commission directed UPCL to submit a loss reduction trajectory from FY 2008-09 onwards.
However, in the absence of any study conducted by UPCL for realistic assessment of losses in line
with past trend, the Commission in its Tariff Order for FY 2007-08 and FY 2008-09 specified a
distribution loss target of 22.32% for FY 2008-09. Further, the Commission in its Tariff Order for FY
2009-10 directed the Petitioner to reduce the distribution losses of 22.32% fixed for FY 2008-09, by a
modest 2% to achieve the distribution loss target of 20.32% for FY 2009-10. This reduction target was
also in accordance with the recommendations of the Task Force set up by Ministry of Power,
Government of India on APDRP Programme (Abraham Committee), which recommended that
licensee with distribution losses in the range of 20 to 30% should be given a loss reduction target of
2% per annum. However, the Commission in its subsequent Tariff Order for FY 2010-11 took a
lenient view and considering the difficulties faced by the Petitioner in reducing the losses, set a loss
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
104 Uttarakhand Electricity Regulatory Commission
reduction target of only 1.32% for FY 2010-11 for UPCL and approved the target losses of 19% for
FY 2010-11. Subsequently, the Commission in its Tariff Orders for FY 2011-12 and FY 2012-13
approved the loss reduction target of only 1% and the detailed reasons for the same are elaborated
in respective Tariff Orders.
The Commission, so as to review and revise the loss reduction trajectory, has been
repeatedly directing the Petitioner, in its previous Tariff Orders, to carry out the energy audit study.
However, the Petitioner has so far not made any substantial progress in this regard. The Petitioner
has consistently failed to address the issues of replacement of defective meters and meter reading in
each billing cycle. The sum of defective meters and meter not read continue to be above 20% of the
total consumers for more than 5 years in each billing cycle. Further, it would also not be out of place
to mention that the Petitioner had itself been making unmetered supply to some of the consumer
categories including the departmental employees despite categorical directions and being subject to
a recurring daily penalty imposed on it by the Commission. Apparently the provisional billing on
assumed consumption basis for aforesaid consumers is used for booking of losses by the Petitioner
in order to camouflage its distribution losses. Besides, the status of Feeder metering as well as DT
metering of the Petitioner has not been satisfactory despite repeated directions of the Commission.
Further, as pointed out by the Commission in its previous Orders large number of ghost consumers
exists in the Petitioner’s billing database. Considering all these facts, it would not be improper to
say that the Petitioner’s actual losses can be still higher than that submitted by it and this being so
despite huge investments of about Rs. 3000 Crore made by the Petitioner over a period of 15 years.
As discussed in the Tariff Order dated April 11, 2015 for FY 2015-16, the Commission observed that
for the past 5 years there had been no reduction in losses of consumers in LT categories, since the
Petitioner had not put in serious efforts in reducing the losses and ensuring compliance with the
directions issued by the Commission from time to time. The loss reduction that occurred in the
distribution system was due to the fact that proportion of sales to HT consumers which was about
25% in FY 2002-03 increased to about 60% in FY 2013-14. Thus, the under-achievement of losses by
UPCL was not due to the stringent targets fixed by the Commission but due to its own inefficiency
and callous approach which in no way can be passed on to the consumers.
Infact Hon’ble ATE in its Judgment dated May 18, 2015 in Appeal no. 180 of 2013 has also
held as under:
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 105
“We find that during the period 2006-07 to 2011-12, the State Commission had given a target of
28.32% to 18% i.e. 10% in a period of 5 years. However, UPCL was able to reduce it to only upto
19.96% at the end of 2011-12. For the year 2012-13 and 2013-14 Commission has fixed target of 17
and 16% respectively i.e. reduction of 1% over the previous year’s target. Thereafter for 2014-15 and
2015-16, the reduction in loss level has been reduced to 0.5% per annum. It is clear from the
submissions made by State Commission that the Appellant has not been taking action on the
directions given by the State Commission on defective meter and meter not read which remained
above 20% of total consumers more than five years in each billing cycle. The State Commission UPCL
has not taken action for energy audit. We do not find any infirmity in fixing up of loss reduction
targets by the State Commission. The Appellant has not given any instances where funds for capital
works for strengthening of distribution system have been denied by the State Commission in ARR.
Wesco’s case will not be applicable to the present case as in Wesco, the Discom was not allowed
adequate amount in Annual Revenue Requirement for capital works. On the other hand the Appellant
is also a beneficiary of RAPDRP. This issue is decided against the Appellant. “
In this context, the Commission would also like to highlight the issues emerging out of the
R-APDRP programme of the Central Government. The focus of the R-APDRP programme is to
develop the distribution infrastructure in such a manner so as to improve the commercial viability
of the sector. The programme, accordingly, focuses on actual, demonstrable performance in terms of
sustained loss reduction. Under this Scheme, the projects are being taken up by the utilities in two
parts. Part-A includes the projects for establishment of base line data and IT applications for energy
accounting/auditing & IT based consumer service centres. Part-B includes regular distribution
system strengthening projects. The Central Government is providing 100% funds for the Part-A
project as loan. Whereas under Part-B of the project, the Central Government shall provide up to
90% funds for the projects to special category States like Uttarakhand, through loan from GoI. The
MoU further stipulates conditions for conversion of loans into grants for each of the projects. In case
of Part-A, the loan along with the interest thereon shall be converted into grant in case projects are
completed within 3 years from the date of sanctioning of the projects. In case of Part-B, the loan
shall be converted into grant in five equal tranches on achieving 15% AT&C loss in the project area
on a sustainable basis for a period of five years. Further, if the utility fails to achieve or sustain the
15% AT&C loss target in a particular year, conversion of that year‘s tranche of loan to grant will be
reduced in proportion to the shortfall in achieving 15% AT&C loss target from the starting AT&C
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
106 Uttarakhand Electricity Regulatory Commission
loss figure. Thus, this would have a financial implication for both the Petitioner as well as the
consumers. In case, the Petitioner is not able to achieve or sustain the 15% AT&C loss target, it
would result in an increased burden of loan on the Petitioner, which if allowed as pass through in
tariffs, would put extra burden on the consumers. In case, the loss targets are revised as proposed
by the Petitioner, the Petitioner will not be able to reach the AT&C loss target of 15%, which the
Petitioner has itself committed to achieve while seeking funding under R-APDRP from the Central
Government. Further, the Central Government has also sanctioned “Integrated Power Development
Scheme” (IPDS) on December 03, 2014 under which new initiatives have been planned by the
Petitioner for strengthening of distribution system, metering of feeders/distribution transformers/
consumers in urban areas and IT enablement of its operations.
Based on the above discussions and more so in the absence of any energy audit study and
considering the ground realities, the Commission decides not to modify the opening loss for FY
2016-17. UPCL’s inaction and continuous high level of inefficiency does not allow it to claim that
every time a new Regulation is made, loss level should be refixed at a level higher than prevailing
in the previous Regulations. Accordingly, the Commission decides to retain the distribution loss for
FY 2016-17 at 15%, i.e. at the same target level as applicable for FY 2015-16. The Commission has set
the target of marginal loss reduction to the extent of 0.25% for second and third year of the second
Control Period. The distribution loss trajectory proposed by the Petitioner and approved by the
Commission for the second Control Period from FY 2016-17 to FY 2018-19 is shown in the Table
below:
Table 3.14: Distribution Losses for FY 2016-17 to FY 2018-19
Particulars FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 Approved Proposed Approved Proposed Approved Proposed Approved
Distribution Losses 15.00% 17.29% 15.00% 16.79% 14.75% 16.29% 14.50%
In line with the approach adopted by the Commission in its previous Tariff Orders, the
Commission has considered the entire distribution loss reduction target for each year of the Control
Period as reduction in commercial losses of the Petitioner and has, therefore, considered the impact
of distribution loss reduction in terms of increase in sales due to efficiency improvement.
Accordingly, the estimated energy requirement at distribution periphery, State periphery
and approved loss level for the second Control Period from FY 2016-17 to FY 2018-19 are given in
the Table below:
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 107
Table 3.15: Energy Input requirement approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 Particulars FY 2016-17 FY 2017-18 FY 2018-19
Distribution Sales (MU) 11,188 11,849 12,555 Loss level for Energy Input (MU) 15.00% 15.00% 14.75% Energy Input required at T-D interface (MU) 13,162 13,940 14,771 Commercial Loss reduction (%) - 0.25% 0.25% Commercial Loss reduction (Additional sales due to efficiency improvement) (MU) - 34.85 36.93
Total sales with efficiency improvement (MU) 11,188 11,884 12,592 Overall Distribution Loss (%) 15.00% 14.75% 14.50% PTCUL Loss (%) 1.78% 1.78% 1.78% Energy Input at State periphery (MU) 13,401 14,193 14,994
3.5.2 Collection Efficiency
The Petitioner submitted that in FY 2014-15, the actual collection efficiency was recorded to
the tune 100.61% (including arrears) and 95.9% (without arrears). The recorded collection efficiency
for FY 2013-14 is 98.43%. The collection efficiency approved for FY 2014-15 is 98.00%. The slight
improvement in collection efficiency in FY 2013-14 and FY 2014-15 is the result of continuous and
dedicated measures undertaken by the Petitioner such as introduction of surcharge waiver scheme,
which is one time in nature, implementation of systems under RAPDRP schemes, due to which
billing process has been streamlined, accuracy in the system which has led to proper recording of
the information, timely collection of bills during the FY 2014-15. The Petitioner submitted that the
following initiatives have been implemented for commercial loss reduction and improvement in
collection efficiency:
• Implementation of R-APDRP, Part-A & Part-B in 31 towns having population above
10,000, SCADA/DMS in towns having population greater than 4 lacs and energy input
greater than 350 MU/annum.
• Convenient bill payment options like cash collection counters, online bill payment
through credit card, debit card, internet banking, etc.
• More teams to be sent to rural areas for increasing collection.
• Recovery of past arrears
These efforts put in by the Petitioner needs to be continued in the future as well.
The collection efficiency trajectory proposed by the Petitioner is as shown in the Table
below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
108 Uttarakhand Electricity Regulatory Commission
Table 3.16: Collection efficiency trajectory proposed by the Petitioner for FY 2016-17 to FY 2018-19
Particulars FY 2014-15 (Actual)
FY 2015-16 (Projected)
FY 2016-17 (Projected)
FY 2017-18 (Projected)
FY 2018-19 (Projected)
Collection efficiency 95.9% 96.65% 97.40% 98.25% 99.0%
The collection efficiency (without arrears) achieved by the Petitioner against the approved
levels for the first Control Period from FY 2013-14 to FY 2015-16 is as shown in the Table below:
Table 3.17: Collection efficiency for FY 2013-14 to FY 2015-16
Particulars FY 2013-14 FY 2014-15 FY 2015-16 Approved Actual Approved Actual Approved Proposed
Collection efficiency 97.50% 98.43% 98.00% 95.90% 98.50% 96.65%
The actual collection efficiency (current dues) for FY 2014-15 is 95.9%. The Petitioner has
proposed improvement of 0.75% each year from FY 2015-16 to FY 2018-19. It is disheartening to
observe that against the collection efficiency of 98.43% achieved by the Petitioner in FY 2013-14, the
collection efficiency has gone down to 95.90% in FY 2014-15. The Petitioner should strive to improve
upon its performance rather than have a laid-back approach. The Commission is of the opinion that
the target of collection efficiency of 98.50% so approved for FY 2015-16 is not a stringent target and
can be easily achieved if proper focus on billing and realisation of its dues. The same has already
been achieved by the Petitioner once in FY 2013-14. Hence, in line with the approach adopted by the
Commission in the approval of Distribution Loss, the Commission has approved the collection
efficiency of 98.50% for FY 2016-17 which is also the approved collection efficiency for FY 2015-16.
For FY 2017-18 and FY 2018-19, the Commission has considered an improvement of 0.25% in
collection efficiency. The collection efficiency trajectory approved by the Commission for the second
Control Period from FY 2016-17 to FY 2018-19 is as shown in the Table below:
Table 3.18: Collection efficiency for FY 2016-17 to FY 2018-19
Particulars FY 2016-17 FY 2017-18 FY 2018-19 Proposed Approved Proposed Approved Proposed Approved
Collection efficiency 97.40% 98.50% 98.25% 98.75% 99.0% 99.0%
However, the Commission would like to point out that it does not determine the ARR and
Tariffs of UPCL based on the AT&C loss levels but based on the distribution loss levels. The
shortfall in collections is covered through an allowance in working capital for the distribution
licensee to the extent of collection inefficiency. The licensee should strive for maximum collections
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 109
so as to improve its financial health and prevent any receivables turning bad. Further, the scheme of
surcharge waiver should not be encouraged as it gives a wrong signal to the honest consumers who
pay their dues in time. The Petitioner is required and expected to improve its bill collection system
further, and also to monitor its receivables so as to prevent them from turning into bad and
unrealizable.
3.6 Power Procurement Plan
The Petitioner submitted that the total consumer sales for each year have been grossed up by
the distribution loss level for the respective year, to arrive at the required quantum of power
purchase for that year at the Discom periphery. The power requirement of UPCL is met from
various sources which includes the generating stations of:
• State Generating Stations of UJVN Ltd.
• NTPC Ltd.
• NHPC Ltd.
• NPCIL
• SJVN Ltd.
• THDC India Ltd.
• Independent Power Producers (IPPs)
• Solar Rooftop generators
• Short term power arrangements: Banking, open market purchases etc.
For projecting the availability of power for FY 2016-17, the Petitioner considered the average
of the actual monthly energy generation during the past 3 years. For the stations which have not
been operational for complete 3 years, the average of the actual monthly generation during the
years in which such stations have been fully operational has been considered. The energy
availability from various sources has been projected based on the following:
• UJVN Ltd. – For 10 LHPs, the average of actual monthly energy generation during the
past 3 years from FY 2012-13 to FY 2014-15 has been considered. For SHPs, the average
of actual monthly energy generation in FY 2012-13 and FY 2014-15 has been considered.
• NTPC – For Singrauli STPS, Unchahar I, II, III, Dadri (NCT) II and Rihand STPS I, II, the
average of actual monthly energy generation during the past 3 years from FY 2012-13 to
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
110 Uttarakhand Electricity Regulatory Commission
FY 2014-15 has been considered. For Rihand STPS III, Aravali (Jhajjar), gas power plants
Anta, Auraiya, Dadri (Gas), the actual monthly energy generation for FY 2014-15 has
been considered. For Kahalgaon II, the average of actual monthly energy generation of
FY 2013-14 and FY 2014-15 has been considered. For Koldam HPS, the energy
availability has been projected based on the Design Energy of the Station and share
allocation to UPCL.
• NHPC – For Salal, Tanakpur, Chamera I, II, Dulhasti and Sewa II, the average of actual
monthly energy generation during the past 3 years from FY 2012-13 to FY 2014-15 has
been considered. For Chamera III, the average of actual monthly energy generation for
FY 2013-14 and FY 2014-15 has been considered. For Dhauliganga and Uri I, the average
of actual monthly energy generation for FY 2012-13 and FY 2014-15 has been considered.
For Uri II and Parbati III, the energy availability has been projected based on the Design
Energy of the respective station and share allocation to UPCL.
• NPCIL – For NAPP and RAPP, the average of actual monthly generation during the past
3 years from FY 2012-13 to FY 2014-15 has been considered.
• SJVNL – For Nathpa Jhakri, the average of actual monthly generation during the past 3
years from FY 2012-13 to FY 2014-15 has been considered. For Rampur HPS, the energy
availability has been projected based on the Design Energy of the station and the share
allocation to UPCL.
• THDC – For Tehri I and Koteshwar, the average of actual monthly energy generation
during the past 3 years from FY 2012-13 to FY 2014-15 has been considered.
• Vishnu Prayag HEP – For Vishnu Prayag HEP, the average of actual monthly energy
generation of FY 2012-13 and FY 2014-15 has been considered.
• UREDA stations and IPPs – For SHPs of UREDA, the average of actual monthly energy
generation during the past 3 years from FY 2012-13 to FY 2014-15 has been considered
and for IPPs based on the information furnished by the developers. For Sasan UMPP, the
energy availability has been projected considering the PLF of 75% for FY 2016-17, and
85% for FY 2017-18 and FY 2018-19. The energy availability from solar rooftop generators
has been considered based on the capacity being added during each of the Control
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 111
Period and normative PLF.
• Upcoming stations – The energy availability from hydro stations expected to be
commissioned during the Control Period has been projected considering the likely COD
of such generating stations, normative performance parameters and share allocation to
UPCL.
• Forward banking of power – The Petitioner has proposed a forward banking of 300 MU
in FY 2016-17, FY 2017-18 and FY 2018-19 which shall be returned under reverse banking
in FY 2017-18 and FY 2018-19. During FY 2017-18 and FY 2018-19, the forward banking
and reverse banking would nullify each other.
• Transmission Losses – The Petitioner has considered the ISTS losses of 4% and intra-
State transmission losses of 1.78%.
• Short term purchases – Based on the energy balance at UPCL periphery, after
considering the energy availability from firm sources, the Petitioner has projected
shortfall of 3246 MU in FY 2016-17, 2790 MU in FY 2017-18, and 3106 MU in FY 2018-19.
• The Petitioner has proposed the total power purchase of 13673.41 MU in FY 2016-17,
14124.55 MU in FY 2017-18 and 14922.25 MU in FY 2018-19.
The Commission has gone through the submissions of the Petitioner. The
Commission for projection purposes has considered the energy availability from various generating
stations on the basis of month-wise energy availability from all the generating stations. On the basis
of monthly energy availability and estimated energy requirement, the Commission has computed
the deficit quantum of power which the Petitioner would be required to purchase from open
market, energy exchange, medium/short term basis depending on its requirement. The
Commission for projecting power purchase has considered both existing generating stations and
upcoming stations to be commissioned during the Control Period, in which UPCL has share
allocation. The Commission, however, has projected the power purchase cost only for FY 2016-17 in
Chapter 5 of the Order while analysing the ARR for FY 2016-17 as projecting power purchase cost at
this point of time for FY 2017-18 and FY 2018-19 will be of no relevance as the fuel costs varies
significantly over a period of time and further CERC is also yet to issue the Orders for most of the
NTPC, THDC and NHPC stations for the tariff period FY 2014-15 to FY 2018-19 . Further, as per
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
112 Uttarakhand Electricity Regulatory Commission
UERC Tariff Regulations, 2015, the Petitioner shall be filing Petitions for tariff determination for FY
2017-18 and FY 2018-19 alongwith the Annual Performance Review for FY 2016-17 and FY 2017-18
and power purchase cost will require detailed scrutiny while processing those Petitions. The
detailed approach for approving the power purchase quantum has been discussed below and the
detailed approach for projecting power purchase cost for FY 2016-17 is discussed in Chapter 5 of the
Order.
For projecting the energy availability quantum from various sources, the Commission
sought the following information from the Petitioner:
• Copies of agreements executed with upcoming generating stations.
• Likely COD of the upcoming generating stations.
• Economics of forward banking and reverse banking projected during the Control Period.
• Actual ISTS losses for the past 52 weeks (1 year) based on bills received from Central
Sector Generating Stations (CSGS).
In reply, UPCL submitted the following:
• Copies of PPAs for the upcoming generating stations.
• Likely COD of the upcoming generating stations.
• Regarding banking of power, the Petitioner submitted that banking is an instrument for
safeguarding the distribution utility from the fluctuations in the short term power
market.
• UPCL submitted the actual ISTS losses for the period of December 2014 to November
2015.
The Commission while projecting the quantum of energy available from various sources for
FY 2016-17 to FY 2018-19 has made the assumptions as detailed below.
3.6.1 Power Purchase from UJVN Ltd.
The Commission has considered the availability from generating stations of UJVN Ltd. as
under:
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 113
Table 3.19: Power Purchase from UJVN Ltd. Stations of UJVN
Ltd. Basis Rationale
UJVN Ltd. (9 LHPs)
Average of actual month wise gross generation in FY 2012-13, FY 2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months); The impact of loss in generation during the relevant months due to approved RMU works and DRIP closure for the respective stations in the 9 LHPs has been considered in FY 2016-17 FY 2013-14 has not been
considered as the hydro generation in the State was adversely affected due to natural calamity.
Maneri Bhali-II
Average of actual month wise gross generation in FY 2012-13, FY 2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months) The Commission has considered the shutdown of the generating station during the months of November 2016 to January 2017 for carrying out works related to increase in dam height and, accordingly, energy generation during these months has not been considered in FY 2016-17
SHPs, viz. Pathri, Mohammadpur & Galogi
Average of actual month wise gross generation in FY 2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months)
FY 2013-14 has not been considered as the hydro generation in the State was adversely impacted due to natural calamity; FY 2012-13 has not been considered as RMU works were carried out during FY 2012-13 and enhanced generation on account of the same has been observed in FY 2014-15.
The Commission has estimated the energy availability from these generating stations to
UPCL at State Periphery after considering the normative auxiliary consumption and also excluding
the share allocation to Himachal Pradesh. The summary of energy availability from UJVN Ltd. for
FY 2016-17 to FY 2018-19 as estimated by the Petitioner and the Commission is shown in the Table
below:
Table 3.20: Energy Availability from UJVN Ltd. For FY 2016-17 to FY 2018-19(MU)
Station FY 2016-17 FY 2017-18 FY 2018-19
Estimated by UPCL
Estimated by Commission
Estimated by UPCL
Estimated by Commission
Estimated by UPCL
Estimated by Commission
UJVN Ltd. (9 LHPs) 2955.02 2972.04 2955.02 3004.38 2955.02 3004.38 Maneri Bali II 950.66 971.05 950.66 1088.40 950.66 1088.40 Small Hydro
Pathri 134.69
111.80 134.69
111.80 134.69
111.80 Mohammadpur 52.52 52.52 52.52 Galogi 5.73 5.73 5.73
Total 4040.37 4113.15 4040.37 4262.84 4040.37 4262.84
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
114 Uttarakhand Electricity Regulatory Commission
3.6.2 Power Purchase from NHPC Ltd.
The Commission has considered the availability from generating stations of NHPC Ltd. as
under:
Table 3.21: Power Purchase from NHPC Ltd. Stations of
NHPC Basis Rationale
Salal
Average of actual month wise gross generation in FY 2012-13, FY 2014-15 & FY 2015-16 (actual for 9
months, projections for 3 months)
FY 2013-14 has not been considered as the hydro generation had been
adversely affected
Tanakpur Chamera I Chamera II Chamera III Uri Dhauliganga Dulhasti Sewa II Uri II Average of actual month wise gross generation in FY
2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months)
Considered the full years of operation Parbati III
The Commission has estimated the energy availability from these generating stations to
UPCL at State Periphery after considering the normative auxiliary consumption, actual ISTS losses
for the respective generating station for the period from December 2014 to November 2015 and
considering share allocation to Uttarakhand. The summary of energy availability from NHPC Ltd.
for FY 2016-17 to FY 2018-19 as estimated by the Petitioner and the Commission is shown in the
Table below:
Table 3.22: Energy Availability from NHPC Ltd. for FY 2016-17 to FY 2018-19 (MU) Station Estimated by UPCL Estimated by Commission
Salal 38.37 40.04 Tanakpur 12.30 16.17 Chamera I 80.05 86.37 Chamera II 18.61 17.75 Chamera III 49.54 50.05 Uri 99.78 101.18 Dhauliganga 43.39 48.51 Dulhasti 105.06 105.46 Sewa II 26.19 28.80 Uri II 55.10 56.27 Parbati III 34.82 32.38 Free Power-Tanakpur 39.94 53.48 Free Power-Dhauliganga 106.76 114.03 Total 709.91 750.51
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 115
3.6.3 Power Purchase from THDC India Ltd.
The Commission has considered the availability from generating stations of THDC Ltd. as
under:
Table 3.23: Power Purchase from THDC India Ltd. Stations of THDCIL Basis Rationale
Tehri HEP Average of actual month wise gross generation in FY 2012-13, FY 2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months)
FY 2013-14 has not been considered as the hydro generation in the State had been adversely affected Koteshwar HEP
The Commission has estimated the energy availability from these generating stations to
UPCL at State Periphery after considering the normative auxiliary consumption, actual ISTS losses
for the respective generating station for the period from December 2014 to November 2015 and
considering the share allocation to Uttarakhand. The summary of energy availability from THDC
Ltd. for FY 2016-17 to FY 2018-19 at State periphery as estimated by the Petitioner and the
Commission is shown in the Table below:
Table 3.24: Energy Availability at State periphery from THDC Ltd. for FY 2016-17 to FY 2018-19 (MU)
State Estimated by UPCL Estimated by Commission
Tehri HEP 110.84 101.25 Free Power-Tehri HEP 388.62 358.93 Koteshwar HEP 50.55 62.91 Free Power-Koteshwar HEP 147.96 139.03 Total 697.97 662.11
3.6.4 Power Purchase from NTPC Ltd.
The Commission has considered the availability from generating stations of NTPC Ltd. as
under:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
116 Uttarakhand Electricity Regulatory Commission
Table 3.25: Power Purchase from NTPC Ltd. Stations of
NTPC Basis Rationale
Singrauli STPS
Average of actual month wise gross generation in FY 2013-14, FY 2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months)
Actual monthly generation of past 3 years
Rihand STPS Rihand I Rihand II Rihand III Unchahar TPS Unchahar I Unchahar II Unchahar III Anta CCPP Auraiya CCPP Dadri CCPP Dadri (NCTPP) Jhajjar Kahalgaon TPS Koldam Monthly ex-bus generation as projected by UPCL -
The Commission has estimated the energy availability from these generating stations to
UPCL at State Periphery after considering the normative auxiliary consumption, actual ISTS losses
for the respective generating station for the period from December 2014 to November 2015 and
considering the share allocation to Uttarakhand. The summary of energy availability from NTPC
Ltd. for FY 2016-17 to FY 2018-19 at State periphery as estimated by the Petitioner and the
Commission is shown in the Table below:
Table 3.26: Energy Availability from NTPC Ltd. at State periphery for FY 2016-17 to FY 2018-19 (MU)
Station Estimated by UPCL Estimated by Commission Singrauli STPS 782.02 720.76 Rihand STPS Rihand I 304.60 256.73 Rihand II 294.38 232.47 Rihand III 275.98 267.23 Unchahar TPS Unchahar I 266.52 230.18 Unchahar II 133.86 107.91 Unchahar III 105.31 87.86 Anta CCPP 76.56 73.95 Auraiya CCPP 72.37 71.66 Dadri CCPP 99.62 109.24 Dadri (NCTPP) 38.20 47.02 Jhajjar 5.63 28.56 Kahalgaon TPS 184.48 170.17 Koldam 197.66 198.94
Total 2837.19 2602.69
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 117
3.6.5 Power Purchase from SJVN Ltd.
The Commission has considered the availability from generating stations of SJVN Ltd. as
under:
Table 3.27: Power Purchase from SJVN Ltd. Stations of
SJVNL Basis Rationale
Nathpa Jhakri HEP
Average of actual month wise gross generation in FY 2012-13, FY 2014-15 & FY 2015-16 (actual for 9 months, projections for 3 months)
FY 2013-14 has not been considered as the hydro generation had been adversely affected
Rampur HPS
Average of actual month wise gross generation in FY 2014-15 and FY 2015-16 (actual for 9 months, projections for 3 months)
Full years of operation have been considered
The Commission has estimated the energy availability from these generating stations to
UPCL at State Periphery after considering the normative auxiliary consumption, actual ISTS losses
for the respective generating station for the period from December 2014 to November 2015 and
considering the share allocation to Uttarakhand. The summary of energy availability from SJVN
Ltd. for FY 2016-17 to FY 2018-19 as estimated by the Commission is shown in the Table below:
Table 3.28: Energy Availability from SJVN Ltd. at State periphery for FY 2016-17 to FY 2018-19 (MU)
Station Estimated by UPCL Estimated by Commission Nathpa Jhakri HEP 49.30 45.66 Rampur HPS 185.25 175.89 Total 234.55 221.55
3.6.6 Power Purchase from existing Renewable Energy Sources
The existing renewable energy sources include the hydro power stations of UREDA, IPPs,
co-generation plants, and solar power plants within the State. For these generating stations, the
Commission has considered the energy availability at State periphery as projected by UPCL.
The summary of energy availability from existing renewable energy sources for FY 2016-17
to FY 2018-19 as estimated by the Petitioner and the Commission is shown in the Table below:
Table 3.29: Energy Availability from existing Renewable Energy Sources for FY 2016-17 to FY 2018-19 (MU)
Station Estimated by UPCL Estimated by Commission
Existing renewable energy sources 511.76 511.76
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
118 Uttarakhand Electricity Regulatory Commission
3.6.7 Power Purchase from Vishnu Prayag HEP (State Royalty Power)
For estimating the State Royalty power from Vishnu Prayag HEP, the Commission has
considered the average of actual monthly generation for the years FY 2012-13, FY 2014-15 and FY
2015-16 (actual for 9 months, projections for 3 months). The summary of energy availability from
Vishnu Prayag HEP as estimated by the Petitioner and the Commission is shown in the Table
below:
Table 3.30: Energy Availability from Vishnu Prayag HEP at State Periphery (State Royalty Power) for FY 2016-17 to FY 2018-19 (MU)
Station Estimated by UPCL
Estimated by Commission
Vishnu Prayag HEP (State Royalty Power) 196.27 195.93
3.6.8 Power Purchase from Sasan UMPP
For estimating the energy availability from Sasan UMPP, the Commission has considered
the actual monthly generation of FY 2015-16 (actual for 9 months, projections for 3 months) as the
entire capacity of the generating station come into operation from April, 2015. The Commission has
estimated the energy available from Sasan UMPP to UPCL at State Periphery after considering the
normative auxiliary consumption, actual ISTS losses for the period from December 2014 to
November 2015 and considering share allocation to Uttarakhand. The summary of energy
availability from Sasan UMPP for FY 2016-17 as estimated by the Petitioner and the Commission is
shown in the Table below:
Table 3.31: Energy Availability from Sasan UMPP at State periphery for FY 2016-17 to FY 2018-19(MU)
Station Estimated by UPCL Estimated by Commission
FY 2016-17 FY 2017-18 FY 2018-19 FY 2016-17, FY 2017-18 & FY 2018-19
Sasan UMPP 552.02 625.62 625.62 685.39
3.6.9 Power purchase from Kashipur CCPP
The Commission vide its Order dated February 8, 2016 approved the PPA between UPCL
and Gama Infrapop (P) Ltd. (Kashipur CCPP) for sale of power corresponding to 107 MW (gross
capacity) to UPCL. The Commission, accordingly, has considered the energy availability from
Kashipur CCPP considering the normative performance parameters. The summary of energy
availability from Kashipur CCPP for FY 2016-17 to FY 2018-19 as estimated by the Commission is
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 119
shown in the Table below:
Table 3.32: Energy Availability from Kashipur CCPP at State periphery for FY 2016-17 to FY 2018-19 (MU)
Station Estimated by UPCL Estimated by Commission
Kashipur CCPP 0.00 776.80
3.6.10 Power purchase from Greenko Budhil Hyrdo
The Commission vide its Order dated October 15, 2015 ruled that approval of PPA between
UPCL and Greenko Budhil Hydro for sale of power corresponding to 70 MW (gross capacity) to
UPCL shall be taken up subsequenty after the Tariff for the generating station has been determined
by the Commission under Section 62 of the Electricity Act, 2003. The Petition for approval of
generation tariff in this matter has been filed before the Commission. In light of the above, the
Commission, accordingly, has considered the energy availability from the generating station based
on the month wise Design Energy. The Commission has estimated the energy available from the
generating station to UPCL at State Periphery after considering the normative auxiliary
consumption, ISTS losses of 4% and also excluding the free share of Himachal Pradesh. The
summary of energy availability from Greenko Budhil Hydro for FY 2016-17 to FY 2018-19 as
estimated by the Commission is shown in the Table below:
Table 3.33: Energy Availability from Greenko Budhil Hydro at State periphery for FY 2016-17 to FY 2018-19 (MU)
Station Estimated by UPCL Estimated by Commission
Greenko Budhil Hydro 0.00 232.98
3.6.11 Power purchase from upcoming generating stations
The upcoming generating stations include the IPPs within the State, hydro power plants of
UREDA, solar power plants within the State and Central Sector Generating Stations (CSGS)
expected to be commissioned during the second Control Period. For estimating the energy
availability from IPPs within the State and hydro power plants of UREDA, the Commission has
considered the actual progress of those generating stations and likely commissioning dates. The
Commission has also considered the energy availability from solar generation capacity amounting
to 30 MW from April, 2016 and another 180 MW from November, 2016 based on the normative
performance parameters. Regarding upcoming CSGS, UPCL had projected the energy availability
from Meja STPP and Unchahar IV in FY 2016-17. As per the monthly report on status of thermal
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
120 Uttarakhand Electricity Regulatory Commission
power projects issued by CEA for the month of December, 2015, the likely COD of Meja STPP and
Unchahar IV is in FY 2017-18. Hence, the Commission has not considered the energy availability
from these CSGS in FY 2016-17.
The summary of energy availability from upcoming generating stations expected to achieve
COD during the second Control Period as estimated by the Petitioner and the Commission is shown
in the Table below:
Table 3.34: Energy Availability from upcoming generating stations at State periphery for FY 2016-17 to FY 2018-19(MU)
Station FY 2016-17 FY 2017-18 FY 2018-19
Estimated by UPCL
Estimated by Commission
Estimated by UPCL
Estimated by Commission
Estimated by UPCL
Estimated by Commission
Upcoming generating stations 332.10 202.33 1176.51 722.10 1709.65 1256.39
3.6.12 Energy available from Firm Sources
The total energy available from firm sources estimated by the Petitioner and the
Commission is as shown in the Table given below:
Table 3.35: Energy available from Long Term Sources (MU)
Station FY 2016-17 FY 2017-18 FY 2018-19
Estimated by UPCL
Estimated by Commission
Estimated by UPCL
Estimated by Commission
Estimated by UPCL
Estimated by Commission
UJVN Ltd. 4040.37 4113.15 4040.37 4262.84 4040.37 4262.84 NHPC Ltd. 709.91 750.51 709.91 750.51 709.91 750.51 THDCIL 697.97 662.11 697.97 662.11 697.97 662.11 NTPC Ltd. 2837.19 2602.69 2837.19 2602.69 2837.19 2602.69 NPCIL 255.99 265.95 255.99 265.95 255.99 265.95 SJVN Ltd. 234.55 221.55 234.55 221.55 234.55 221.55 Existing Renewable sources 511.76 511.76 511.76 511.76 511.76 511.76 Free Power-Vishnu Prayag 196.27 195.93 196.27 195.93 196.27 195.93 Sasan UMPP 552.02 685.39 625.62 685.39 625.62 685.39 Kashipur CCPP 0.00 776.80 0.00 776.80 0.00 776.80 Greenko Budhil Hydro 0.00 232.98 0.00 232.98 0.00 232.98 Upcoming Stations 332.10 202.33 1176.51 722.10 1709.65 1256.39 Total 10368.13 11221.16 11286.14 11890.61 11819.28 12424.90
3.6.13 Power Purchase for fulfilling RPO
UPCL had proposed to fulfill the RPO over and above the estimated power purchase from
renewable energy sources by purchase of RECs.
The Commission had specified the RPO for FY 2016-17 as 1.50% for Solar and 8.00% for
Non-Solar and for FY 2017-18 as 2.50% for Solar & 8.00% for Non-Solar. Based on the estimated
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 121
power purchase from renewable energy sources, the status of fulfillment of RPO and additional
purchase required is as shown in the Table below.
Table 3.36: Additional Purchase for fulfilling RPO Particulars Units FY 2016-17 FY 2017-18
Total Power Purchase at State Periphery MU 13400.60 14193.00 RPO
Solar % 1.50% 2.50% Non-Solar % 8.00% 8.00%
RPO Solar MU 201.01 354.83 Non-Solar MU 1072.05 1135.44 Total MU 1273.06 1490.27
Purchase from Renewable Sources Solar MU 214.48 416.95 Non-Solar MU 655.81 738.42 Total MU 870.29 1155.37
Additional Energy to be purchased for fulfilment of RPO Solar MU 0.00 0.00 Non-Solar MU 416.24 397.02 Total MU 416.24 397.02
Hence, the additional energy to be purchased from Non-Solar renewable energy sources,
over and above the energy sources listed above, for fulfilling the RPO targets for FY 2016-17 is
416.24 MU and 397.02 MU for FY 2017-18.
3.6.14 Return of banked power during FY 2016-17
The Petitioner, in its replies to data gaps submitted that it had executed an agreement for
inward banking of 200 MW RTC power from October, 2015 to March, 2016 which would be
returned with 5% extra power during the period July, 2016 to September, 2016. The Petitioner had
not considered the same in its projections of power purchase for FY 2016-17 submitted in the
Petition. The Commission, accordingly, has considered 907.52 MU to be returned by UPCL during
the period of July 2016 to September, 2016.
3.6.15 Deficit/ (Surplus) energy
As against the energy requirement of 14308.12 MU (13400.60+907.52), the total estimated
energy available from firm sources is 11637.39 MU leaving a deficit of 2670.72 MU.
Further, the energy deficit/surplus scenario estimated by the Commission for FY 2016-17 to
FY 2018-19 is as shown in the Table given below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
122 Uttarakhand Electricity Regulatory Commission
Table 3.37: Energy deficit/surplus Scenario for FY 2016-17 to FY 2018-19 (MU) Particulars FY 2016-17 FY 2017-18 FY 2018-19
Energy requirement at State periphery 14308 14193 14994 Total Energy available from firm sources 11637 12216 12425 Deficit/(Surplus) 2671 1977 2569
In view of persistent deficit scenario, the Petitioner should put its sincere efforts to
procure the deficit energy through a mix of long term arrangements, medium term arrangements
and short term purchases optimizing the cost of power purchase and reliable power. Further, the
procurement should be through transparent process of bidding and not on mutual agreements as
has been the practice of UPCL. UPCL is directed to submit a comprehensive plan as to how it
intends to meet the deficit within one month of the date of Order.
3.7 Capital Expenditure Plan and Capitalisation Plan
The Petitioner submitted that in order to achieve the anticipated load growth and targeted
loss reduction, it has carried out a detailed analysis of capital investment required for next three
years based on various technical and physical requirements. The capital expenditure plan proposed
for the second Control Period from FY 2016-17 to FY 2018-19 is as shown in the Table below:
Table 3.38: Capital Expenditure Plan for FY 2016-17 to FY 2018-19 as submitted by the Petitioner (Rs. Crore)
S. No. Particulars FY
2016-17 FY
2017-18 FY
2018-19 Total
1 Load Growth 1.1 Construction of 33/11 kV Substation 129.58 98.6 61.9 290.08 1.2 Increasing Capacity of 33/11 kV substations 12.88 10.50 10.50 33.88 1.3 Release of New PTW Connections 2.46 2.72 2.98 8.16
1.4 Installation of meters for giving new connections 25.15 29.65 34.82 89.63
1.5 Deen Dayal Upadhyay Grameen Jyoti Yojana 168.40 421.00 235.76 825.16 Sub-total for Load Growth 338.47 562.47 345.96 1246.90
2 Loss Reduction 2.1 Installation of Capacitor Bank at 33/11 kV
substations 45.16 25.97 10.34 81.47
2.2 Implementation of R-APDRP Part A scheme 20.78 11.01 0 31.79 2.3 Implementation of R-APDRP Part B scheme 223.9 0 0 223.9
2.4 Installation of Double metering in selected 11 kV & 33 kV consumers 2.15 1.65 1.81 5.61
2.5 Implementation of AMR 8.53 3.56 3.56 15.65 2.6 IPDS 57.21 95.34 38.14 190.68
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 123
Table 3.38: Capital Expenditure Plan for FY 2016-17 to FY 2018-19 as submitted by the Petitioner (Rs. Crore)
2.7 Replacement of Mechanical Meters with Electronic Meters and Installation of Electronic meters in un-metered connections
4.88 5.37 5.91 16.18
2.8 11 kV Cable for forest 10.42 11.47 12.61 34.52 2.9 Laying of LT ABC 143.38 157.72 173.50 474.60 2.10 Replacement of defective meters 23.35 25.69 28.26 77.32
2.11 Procurement of High value consumer management system (HVCMS) 2.37 2.37 2.37 7.11
2.12 33 kV Underground Cable 19.55 21.51 23.66 64.72 Subtotal for Loss Reduction 569.71 361.67 300.17 1223.55
3 System reliability and safety improvement 3.1 Additional Transformers installation with
associated 11 kV 70.84 77.93 85.72 234.49
3.2 Installation of 11 kV underground cables 22.16 24.38 26.81 73.35 3.3 Smart Grid projects for industrial areas 11.85 11.85 11.85 35.55 3.4 LT Protection System for safety Improvement 15.51 17.06 18.77 51.34 3.5 Safety Measures 7.77 8.54 9.40 25.71
Subtotal for System reliability and safety improvement 128.13 139.76 152.55 420.44
4 Creation of infrastructure facilities & other misc.
4.1 Video conferencing services and integrating it with all the divisions/sub-divisions 0.12 0.12 0.12 0.36
4.2 Procurement of Sub-station and consumer meter testing equipment 1.19 1.19 1.19 3.57
4.3 Consumer care centres, E-payment of bills and Cash collection centres 1.19 1.19 1.19 3.57
4.4 New and emerging technologies and miscellaneous works like, new vehicles, office infrastructure, IT infrastructure, etc.
4.74 12.74 4.74 22.22
Subtotal for Creation of infrastructure facilities & other misc. 7.24 7.24 7.24 29.72
Total Capital Expenditure 1043.54 1071.12 805.91 2920.58
The Petitioner has estimated that the expenditure incurred towards Central Schemes will be
capitalized within two years from the year in which the expenditure has been incurred. The balance
capital expenditure is split into 35%, 35% and 20% over three years based on the historical trend.
The opening CWIP at the end of FY 2014-15 has been estimated to be capitalised equally during FY
2015-16 and FY 2016-17. The capitalisation plan proposed by the Petitioner during the second
Control Period from FY 2016-17 to FY 2018-19 is as shown in the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
124 Uttarakhand Electricity Regulatory Commission
Table 3.39: Capitalisation Plan for FY 2016-17 to FY 2018-19 as submitted by the Petitioner (Rs. Crore)
Particulars Capital expenditure Capitalisation FY 2016-17 1043.54 903.60 FY 2017-18 1071.12 1023.61 FY 2018-19 805.91 949.13 Total 2920.58 2876.34
Regarding the proposed capital expenditure and capitalisation during the second Control
Period from FY 2016-17 to FY 2018-19 the Commission sought the following information:
• Preparedness to execute the proposed capital works in terms of status of Commission’s
approval for the proposed schemes, orders placed and funds tie-up.
• Action plan with PERT Chart for each scheme.
• Current status of DPR for each scheme.
• Status of tendering process for each scheme.
• Status of funds tie-up for each scheme.
In reply, UPCL submitted the following:
• RAPDRP Part A and Part B had been approved by the Commission. The capital works
under the schemes like IPDS and DDUGY have been approved by the Central
Government. For the remaining works, the funds would be arranged after obtaining
approvals from the Commission.
• The orders for equipment worth Rs. 295.99 Crore have been placed to be utilized for the
proposed schemes. The tendering process and activities for later years of the Control
Period can only be initiated as per the requirements.
The actual GFA addition by UPCL during the last 3 years is as shown in the Table below:
Table 3.40: Actual GFA addition of UPCL (Rs. Crore) Year Amount
FY 2012-13 369.76 FY 2013-14 265.17 FY 2014-15 595.03
In comparison to the actual capitalisation during the last 3 years, the year wise capitalisation
proposed during the second Control Period from FY 2016-17 to FY 2018-19 is substantially higher.
Further, the Distribution Licensee is required to seek prior approval of the Commission for all the
capital expenditure schemes of the value exceeding the ceiling specified by the Commission in the
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 125
distribution licence.
In view of the actual performance of the Petitioner in the past, the Commission finds the
proposed year wise capital expenditure and capitalisation proposed by the Petitioner on a much
higher side. As many of the schemes are also yet to be accorded investment approval by the
Commission, the Commission does not find it prudent to approve scheme wise capitalisation
during the second Control Period from FY 2016-17 to FY 2018-19 based on the estimated cost
submitted by the Petitioner. Hence, the Commission for the purpose of approval of Business Plan
has considered the capitalisation for each year of the Control Period based on the approved total
Capital Expenditure and Capital Works in Progress (CWIP). However, during the Annual
Performance Review/Truing-up exercise, the Commission shall consider the Capitalisation on
actual basis subject to capitalisation of only those Schemes which fulfill the conditions as stipulated
by the Commission. The approach adopted by the Commission in approval of year wise capital
expenditure and capitalisation for the second Control Period is detailed below.
The Commission analyzed the trends of amount capitalised by the Petitioner as percentage
of the sum of opening CWIP) and Capital Expenditure for the past 3 years from FY 2012-13 to FY
2014-15 based on the audited accounts submitted by the Petitioner. The same is shown in the Table
below:
Table 3.41: Capitalisation as % of sum of opening CWIP and Capital Expenditure (Rs. Crore)
Particulars Legend FY 2012-13 FY 2013-14 FY 2014-15 Opening CWIP A 248.08 296.08 411.68 Addition to CWIP (Capital Expenditure) B 345.54 386.84 568.37 Deduction from CWIP (Tfd. To GFA) C 297.54 271.24 597.43 Closing CWIP A+B-C 296.08 411.68 382.62 Capitalisation as % of opening CWIP plus capital expenditure C÷(A+B) 50% 40% 61%
Average of 3 years 50%
As discussed earlier, the capital expenditure proposed by the Petitioner during each year of
the second Control Period is substantially higher than the actual capital expenditure incurred
during the last three years. The average actual capital expenditure incurred during the last three
years is Rs. 433.58 Crore and the maximum actual capital expenditure of Rs. 568.37 Crore was
incurred in FY 2014-15. Considering the past performance of the Petitioner and the status of capital
investment approval of the schemes, the capital expenditure plan submitted by the Petitioner for
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
126 Uttarakhand Electricity Regulatory Commission
the second Control Period appears to be over ambitious and unlikely to materialize. The
Commission for the purpose of approval of Business Plan is approving the capital expenditure of
Rs. 568.37 Crore (equivalent to maximum actual capital expenditure in any year during the last
three years) for each year of the second Control Period from FY 2016-17 to FY 2018-19.
The Commission observed that the amount capitalised by the Petitioner during the past 3
years is in the range of 40% to 61% of the sum of opening CWIP and Capital Expenditure during the
year. For approving the capitalisation for each year of the second Control Period from FY 2016-17 to
FY 2018-19, the Commission has considered the average capitalisation as % of the amount
transferred from CWIP over the sum of opening CWIP and capital expenditure for the past 3 years,
i.e. 50%.
Further, based on the submissions of the Petitioner regarding the revised capitalisation for
FY 2015-16, the Commission has worked out the allowable capitalisation for FY 2015-16.
The year wise capital expenditure and capitalisation approved by the Commission for FY
2015-16 and for the second Control Period from FY 2016-17 to FY 2018-19 is shown in the Table
below:
Table 3.42: Capital expenditure and Capitalisation approved by the Commission (Rs. Crore) Particulars FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Claimed Approved Claimed Approved Claimed Approved Claimed Approved Opening CWIP 382.64 382.62 601.65 472.96 741.59 517.89 789.10 540.24 Capital Expenditure 686.83 568.37 1043.54 568.37 1071.12 568.37 805.91 568.37 Capitalisation 467.82 478.03 903.60 523.44 1023.61 546.02 949.13 557.26 Closing CWIP 601.65 472.96 741.59 517.89 789.10 540.24 645.88 551.35 Capitalisation as % of opening CWIP plus capital expenditure
44% 50% 55% 50% 56% 50% 60% 50%
The Commission will consider the actual capital expenditure/capitalization as a part of
Annual Performance Review/Truing-up exercise subject to prudence check in accordance with the
conditions stipulated by the Commission.
3.8 Financing Plan
The financing plan for the proposed capitalisation for the second Control Period as
submitted by the Petitioner is shown in the Table below.
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 127
Table 3.43: Financing Plan proposed by the Petitioner (Rs. Crore)
Particulars Capitalisation Grant Debt Internal Resource/ State Govt. Equity
FY 2016-17 903.60 342.23 392.96 168.41 FY 2017-18 1023.61 430.39 415.25 177.97 FY 2018-19 949.13 224.40 507.31 217.42
The Commission has approved the funding of the approved capitalisation for the second
Control Period by considering the average of the actual funding pattern of capitalisation during FY
2012-13 to FY 2014-15 as shown in the Table below:
Table 3.44: Actual funding of capitalisation for FY 2012-13, FY 2013-14 and FY 2014-15 (Rs. Crore)
Particulars FY 2012-13 FY 2013-14 FY 2014-15 Average Approved Approved Approved Capitalisation 230.50 185.01 472.76 Financing Debt 93.61 41% 134.01 72% 268.47 57% 57% Equity-State Government 17.20 7% 19.05 10% 22.45 5% 8% Grant-Central Government 119.70 52% 31.95 17% 181.84 38% 36% Total 230.51 100% 185.01 100% 472.76 100% 100%
Accordingly, the financing plan approved by the Commission for the second Control Period
from FY 2016-17 to FY 2018-19 is shown in the Table below:
Table 3.45: Financing Plan approved by the Commission (Rs. Crore) Particulars FY 2016-17 FY 2017-18 FY 2018-19
Capitalisation 523.44 546.02 557.26 Financing Debt 296.32 309.11 315.47 Equity-State Government 39.27 40.96 41.81 Grant-Central Government 187.85 195.95 199.98 Total 523.44 546.02 557.26
3.9 Human Resources Plan
The Petitioner submitted that as against the total sanctioned posts of 6158, the actual
employee strength as on March 31, 2015 is 3509. The report on man power assessment, which
includes the analysis on the current man power requirement of UPCL has been sent to the
Government of Uttarakhand (GoU) for approval. Once the report is approved by GoU, it will be
submitted to the Commission. The additional sanctioned posts will be filled within six months after
approval from the Government of Uttarakhand. The Table below details the additional man power
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
128 Uttarakhand Electricity Regulatory Commission
requirement of UPCL designation-wise against which recruitment will be considered:
Table 3.46: Additional man power requirement as submitted by the Petitioner Designation FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Accounts Officer 11 02 02 02 Law Officer 02 01 01 01 Assistant Engineer (E&M) 47 11 11 11 Assistant Engineer (Civil) 07 02 02 02 Junior Engineer (E&M) 13 23 23 23 Junior Engineer (Civil) 20 35 35 35 Office Assistant-III 77 121 121 121 Technician Grade-2 496 116 116 117 Assistant Accountant 57 13 13 13 Assistant Store Keeper 20 - - - Stenographer Grade 3 - 14 14 14 Total 750 338 338 339
Regarding the proposed HR plan for the second Control Period from FY 2016-17 to FY 2018-
19, the Commission sought the following information:
• Actual recruitment in FY 2013-14 and FY 2014-15.
• Actual number of employees recruited in FY 2015-16 till December, 2015.
• Actual number of employees joined in FY 2015-16 till December, 2015.
• Employees likely to be recruited and likely to join in FY 2015-16 during January to
March, 2016.
• Actual number of employees retired in FY 2015-16 till December, 2015.
• Number of employees likely to retire during January to March, 2016.
• Revised recruitment plan for each year from FY 2016-17 to FY 2018-19 along with current
status giving the preparedness and expected time for each recruitment.
• Number of employees retiring during each year from FY 2016-17 to FY 2018-19.
In reply, UPCL submitted the following:
• The actual recruitment is 2 number of employees in FY 2013-14 and 5 number of
employees in FY 2014-15.
• The number of employees recruited is 89 and number of employees joined is 43 in FY
2015-16 till January 20, 2016.
• The number of employees likely to be recruited during the remaining period in FY
3. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Business Plan for the second Control Period
Uttarakhand Electricity Regulatory Commission 129
2015-16 is 661 and all the employees are likely to join before March, 2016.
• There is no revision in the recruitment plan submitted in the Petition for the second
Control Period.
• The number of employees retiring in FY 2016-17 are 233, in FY 2017-18 are 214 and in
FY 2018-19 are 208.
The Commission had approved the recruitment of 444 employees for FY 2013-14 and 444
employees for FY 2014-15. As against the same, the actual recruitment is 2 in FY 2013-14 and 5 in FY
2014-15. The number of employees retired during the respective years outpaced the recruitment
and, hence, in actuality, the number of employees of UPCL has decreased over the two years. The
Commission also does not find the submissions of the Petitioner regarding the recruitment of 661
employees during the period of January to March 2016 achievable given the past performance.
Hence, the Commission has considered the recruitment in FY 2015-16 as 89.
As the adequate human resources are crucial for maintaining reliability in operations and
also the quality of supply, the Commission has considered the recruitment plan proposed by the
Petitioner. The Commission has considered the recruitment of 661 employees, which the Petitioner
has proposed during the period Feb-Mar, 2016 in next financial year, i.e. FY 2016-17. The
Commission has shifted the proposed recruitment for FY 2016-17 and FY 2017-18 to the following
years, i.e. FY 2017-18 and FY 2018-19. If the actual addition to the number of employees is lower
than the recruitments considered in this Order, the impact of same shall be adjusted while carrying
out the Truing Up.
The HR Plan approved by the Commission is shown in the Table below:
Table 3.47: HR Plan approved by the Commission Particulars FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Claimed Approved Claimed Approved Claimed Approved Claimed Approved Opening no. of employees 3456 3456 4076 3415 4181 3843 4305 3967 Recruitment 750 89 338 661 338 338 339 338 Retirement 130 130 233 233 214 214 208 208 Closing no. of employees 4076 3415 4181 3843 4305 3967 4436 4097
Uttarakhand Electricity Regulatory Commission 130
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny
and Conclusion on Truing Up for FY 2014-15
4.1 Truing-up for FY 2014-15
Regulation 13(3) of the UERC (Terms and Conditions for Determination of Tariff) Regulations,
2011 specifies as under:
“The scope of Annual Performance Review shall be a comparison of the performance of the Applicant
with the approved forecast of Aggregate Revenue Requirement and expected revenue from tariff and
charges and shall comprise the following:-
a) A comparison of the audited performance of the applicant for the previous financial year with
the approved forecast for such previous financial year and truing up of expenses and revenue
subject to prudence check including pass through of impact of uncontrollable factors;
b) Categorisation of variations in performance with reference to approved forecast into factors
within the control of the applicant (controllable factor) and those caused by factors beyond the
control of the applicant (un-controllable factors);
c) Revision of estimates for the ensuing financial year, if required, based on audited financial
results for the previous financial year;
d) Computation of sharing of gains and losses on account of controllable factors for the previous
year.”
The Petitioner submitted that the Commission vide its MYT Order dated May 06, 2013
determined the expenses and revenue of the Petitioner for FY 2014-15 based on the UERC Tariff
Regulations, 2011 and also on the basis of historical trends. Further, the Commission, vide its Order
dated April 10, 2014 determined the expenses and revenue for FY 2014-15 based on the revised
projections of the Petitioner.
The Commission has analysed the head-wise elements of ARR and revenue for FY 2014-15 in
the succeeding paragraphs. The head-wise details of variations in expenses and revenues are
enumerated below.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 131
4.1.1 Sales
The Commission had approved the energy sales for FY 2014-15 in the Tariff Order dated
April 10, 2014 as 9915 MU. The Petitioner in the current Petition has submitted the actual restated
sales for FY 2014-15 as 9655 MU.
The Commission continuing with its approach adopted in its Tariff Order for FY 2014-15
directed the Petitioner to submit the breakup of sales for all the consumer categories into three
parts, i.e. sales based on actual meter reading, unmetered sales and sales billed on
provisional/assessment basis for FY 2014-15 during the current proceedings. In reply to the
Commission’s direction, the Petitioner submitted the following:
Table 4.1: Break up of Sales submitted by the Petitioner for FY 2014-15 (MU)
S. N
o
Sub-
Cat
egor
y Based on Actual Meter
Reading Based on Assessment Un-metered Total
Num
ber o
f C
onsu
mer
s (N
o)
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Num
ber o
f C
onsu
mer
s (N
o)
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Num
ber o
f C
onsu
mer
s (N
o)
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Num
ber o
f C
onsu
mer
s (N
o)
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
1 Domestic (i) BPL and Kutir
Jyoti 297044 286979 179.60 22427 22066 13.96 319471 309045 193.56
(ii) Other Domestic Consumers 1189261 1783396 1798.97 131512 178450 183.37 7626 9981 10.77 1328399 1971827 1993.10
(iii) UPCL Employees and Pensioners
- - - 8051 25254 47.80 - - - 8051 25254 47.80
(iv) UJVNL Employees and Pensioners
- - - 661 1625 3.57 - - - 661 1625 3.57
(v) PTCUL Employees and Pensioners
- - - 355 1166 1.36 - - - 355 1166 1.36
(vi) Single Point Bulk Supply 93 21357 34.62 - - - - - - 93 21357 34.62
Total Domestic 1486399 2091732 2013.20 163005 228561 250.06 7626 9981 10.77 1657030 2330274 2274.02 2 Non-domestic 178876 764004 1043.81 13010 17506 24.14 191886 781510 1067.95 3 PTW 23965 140545 233.85 1894 11067 20.32 1389 8776 44.27 27248 160388 298.44 4 LT Industry 8759 184660 299.82 544 3041 4.97 9303 187701 304.79 5 Public Lamps 629 11332 36.83 28 402 1.50 40 1454 8.51 697 13188 46.84
6 Govt. Irrigation System 1345 50832 104.93 59 1303 2.71 - - - 1404 52135 107.64
7 Public Water Works 1165 69700 309.58 49 1430 7.06 - - - 1214 71130 316.64
8 HT Industry 1827 1458303 5066.49 - - - - - - 1827 1458303 5066.49 9 Mixed Load 76 61409 185.68 - - - - - - 76 61409 185.68 10 Railway Traction 1 6800 14.70 - 1 6800 14.70
11 Other State Supply 6 985 1.97 - - - - - - 6 985 1.97
Total 1703048 4840302 9310.85 178589 263310 310.76 9055 20211 63.54 1890692 5123823 9685.16
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
132 Uttarakhand Electricity Regulatory Commission
The Petitioner had also submitted the division wise commercial statement for FY 2014-15.
From the division wise commercial statement submitted by UPCL for FY 2014-15, certain anomalies
like higher consumption per kilowatt or lower revenue per unit than that approved by the
Commission for FY 2014-15 has been observed in some of the distribution divisions of UPCL for
some of the categories of consumers which are discussed hereunder.
In the Mixed Load category under RTS-8 anamolies were observed in the following
distribution divisions given in the Table below:
Table 4.2: Division wise anomalies in Consumption and Average Revenue per unit of Mixed Load as per Commercial Statements for FY 2014-15
Sl. No. Category Division Consumption/ kW Revenue/unit
(Rs. per unit) 1.
Mixed Load- RTS 8
EDD, Gopeshwar 546.10 2.60 2. EDD (U), Roorkee 300.00 3.40 3. EDD (R), Haridwar 733.33 4.00 4. EDD Pithoragarh 184.04 3.73
Here it would be relevant to point out that the average billing rate approved for FY 2014-15
for the Mixed Load category was Rs. 3.94 per unit with Energy Charges of Rs. 3.80 per unit. Hence,
the average billing rate for this category can in no way be less than the energy charges approved for
FY 2014-15. Similarly the sales reported by EDD, Gopeshwar, EDD (U), Roorkee and EDD (R),
Haridwar implies a load factor of 75.85%, 41.67% and 101.85% respectively which in turn signifies
the utilisation of all the electrical fittings and appliances for 18.20 hours, 10 hours and 24.44 hours
per day respectively which is highly unimaginable.
Similarly, for LT Industries under RTS-7, the revenue reported by the following distribution
divisions given in the Table below are even less than the average cost of supply approved for FY
2014-15 and in EDD Kotdwar even less than the Energy Charges approved of Rs. 3.75 per unit. The
average billing rate of LT industry approved for FY 2014-15 was Rs. 4.54 per unit and they were
cross-subsidising category of consumers. However, the actual average billing rate even being lower
than the cost of supply is not possible. The highest load factor amongst the Distribution division
listed below is 28% in EDD Rudrapur and 15.38% in EDD Gopeshwar and the average billing rate at
the approved tariffs at these load factor works out to Rs. 4.25 per unit and Rs. 4.65 per unit
respectively against the actual billing rate reported of Rs. 3.94 per unit and Rs. 3.93 per unit.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 133
Table 4.3: Division wise anomalies in Average Revenue per unit of LT Industries as per Commercial Statements for FY 2014-15
S. No. Division Consumption/ kW Revenue/unit (Rs. per unit)
1. EDD, Gopeshwar 110.74 3.93 2. EDD, Kotdwar 138.75 2.90 3. EDD (U), Roorkee 157.80 3.77 4. EDD, Ramnagar 112.91 3.96 5. EDD (R), Haldwani 127.12 3.98 6. EDD, Rudrapur 201.62 3.94 7. EDD, Sitarganj 120.26 3.91
For HT Industries under RTS-7, the revenue reported by the following distribution divisions
given in the Table below are even less than the average cost of supply approved for FY 2014-15. The
average billing rate of HT industry approved for FY 2014-15 was Rs. 4.57 per unit and they were
cross-subsidising category of consumers. However, the actual average billing rate even being lower
than the cost of supply is not possible. The highest load factor amongst the Distribution division
listed below is 69.78% in EDD Sitarganj and 16.79% in EDD Tehri and the average billing rate at the
approved tariffs at these load factor works should work out to Rs. 4.79 per unit and Rs. 4.14 per unit
respectively at base rate (ignoring the ToD charges and the continuous supply surcharge) against
the billing rate reported of Rs. 3.63 per unit and Rs. 3.72 per unit.
Table 4.4: Division wise anomalies in Average Revenue per unit of HT Industries as per Commercial Statements for FY 2014-15
Sl. No. Category Division Consumption/ kW Revenue/unit
(Rs. per unit) 1. HT Industry
(upto 1000 KVA)
EDD, Tehri 120.91 3.63 2. EDD (R), Haldwani 222.41 3.74 3. EDD, Sitarganj 250.66 3.83 4. HT Industry (Above
1000 KVA) EDD (R), Haldwani 213.33 3.62
5. EDD, Sitarganj 502.39 3.72
Similarly, for PTW consumers under RTS-4, the revenue reported by the following
distribution divisions given in the Table below are even less than the energy charges approved by
the Commission for these consumers for FY 2014-15. The energy charges approved by the
Commission for RTS-4 consumers is Rs. 1.10 per unit, however, the average billing rate reported by
UPCL for FY 2014-15 is as low as Rs. 0.83/unit in EDD, Kotdwar.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
134 Uttarakhand Electricity Regulatory Commission
Table 4.5: Division wise anomalies in Average Revenue per unit of PTW consumers as per Commercial Statements for FY 2014-15
Sl. No. Division Consumption/ kW Revenue/unit (Rs. per unit)
1. EDD (R), Dehradun 89.04 1.02 2. EDD, Vikasnagar 17.98 0.88 3. EDD, Kotdwar 59.52 0.83 4. EDD (U), Roorkee 238.49 1.07 5. EDD (R), Roorkee 121.36 0.97 6. EDD (U), Hardwar 107.66 1.01 7. EDD, Laksar 41.70 0.99 8. EDD, Rudrapur 135.51 1.08 9. EDD, Champawat 94.66 1.05
In the Public Lamps category under RTS 3, EDD (R), Roorkee, EDD Kashipur and EDD
Bajpur reported a sale of 1152.78 units/kW/month, 1035.29 units/kW/month and 737.24
units/kW/month respectively which implies a daily running of about 38, 35 and 24 hours a day
which is abnoxious. Even the consumption in EDD Srinagar implies a daily running of almost 18
hours a day which is again unreasonable. On an average, the daily consumption of this category
should not exceed 10-13 hours a day. This signifies wastage of electricity or a refuge to book excess
losses as it is understood that most of the connections in this category are still unmetered. The
Commission has been time and again directing UPCL to devise means to prevent the wasteful
consumption of electricity in this category but the data reported by UPCL reveals that UPCL has
paid no heed to the directions of the Commission. Further, the average billing rate of Rs. 2.14 per
unit reported by EDD (R) Roorkee and Rs. 3.79 per unit reported by EDD (R) Haridwar is
unacceptable as the energy charges approved for FY 2014-15 was itself Rs. 4.10 per unit and, hence,
the average billing rate can in no way be less than the energy charges.
Table 4.6: Division wise anomalies in Consumption and Average Revenue per Unit of Public Lamps as per Commercial Statements for FY 2014-15
Sl. No. Division Consumption/ kW Revenue/unit (Rs. per unit)
1. EDD, Srinagar 531.81 4.04 2. EDD (R), Roorkee 1152.78 2.14 3. EDD (R), Hardwar 197.99 3.79 4. EDD, Kashipur 1035.29 4.12 5. EDD, Bajpur 737.24 4.17 6. EDD, Pithoragarh 367.44 4.05
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 135
In the Public Water Works category under RTS 6, as given in the Table below, Jal Sansthan
connections in EDD (C), Dehradun, EDD Kashipur, EDD Bajpur are having a very high sales
signifying the running hours as 24.81 hours/day, 71.61 hours/day and 23.55 hours/day
respectively. Even EDD (R) Haridwar is having a very high consumption/kW signifying a running
hour of 16.80 hours/day. The running hours in these connections for more than 24 hours a day is
totally unrealistic. In case of EDD Kashipur the running hours are equivalent to almost 72
hours/day. UPCL’s field divisions are making a mockery by submitting such data. Further, the
energy charges approved for FY 2014-15 for this category was Rs. 4.00/kVAh, however, the actual
average billing rate reported by EDD (R) Haridwar and EDD Rudrapur is even lower than the
energy charges.
Further, in respect of Other Water Works/Plastic Recycling Plant under RTS-6, as given in
the Table below, EDD (R), Dehradun, EDD Vikasnagar and EDD, Ranikhet are having a very high
sales signifying the running hours as 23.00 hours/day, 38.89 hours/day and 19.71 hours/day
respectively. The running hours in these connections are totally unrealistic. Moreover, the average
billing rate in EDD (U), Roorkee is infact even lower than the energy charges approved for this
category. The average billing rate in EDD, Bageshwar of Rs. 0.42/unit is infact even lower than the
lowest tariffs approved by the Commission for PTW connections.
Table 4.7: Division wise anomalies in Consumption and Average Revenue per unit of Public Water Works as per Commercial Statements for FY 2014-15
Sl. No. Category Division Consumption/ kW Revenue/unit
(Rs. per unit) 1.
Jal Sansthan
EDD (C), Dehradun 744.32 4.74 2. EDD (R), Hardwar 504.14 3.93 3. EDD, Kashipur 2148.19 4.15 4. EDD, Bajpur 706.61 4.15 5. EDD, Rudrapur 358.79 3.76 6.
Other Water Works/Plastic Recycling Plant
EDD (R), Dehradun 690.73 4.26 7. EDD, Vikasnagar 1166.67 4.73 8. EDD (U), Roorkee 243.83 3.79 9. EDD, Bageshwar 52.63 0.42
10. EDD, Ranikhet 591.23 4.07
In the Government Irrigation System under RTS-5, as given in the Table below, State
Tubewell Connections in EDD, Rishikesh and EDD (R), Haridwar are having a very high sales
signifying the running hours as 29.56 hours/day and 29.49 hours/day respectively. The running
hours in these connections for more than 24 hours a day is totally unrealistic. Further, the energy
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
136 Uttarakhand Electricity Regulatory Commission
charges approved for FY 2014-15 for this category was Rs. 4.10/kWh, however, the actual average
billing rate reported by EDD (R) Haridwar and EDD Rudrapur is even lower than the energy
charges approved by the Commission.
Further, in respect of Pump Canals under RTS-5, as given in the Table below, EDD
Vikasnagar is having a very high sales signifying the running hours of almost 18.00 hours/day.
Moreover, the average billing rate in EDD, Srinagar, EDD, Gopeshwar, EDD, Kotdwar and EDD,
Ramnagar are even lower than the energy charges approved for this category.
Table 4.8: Division wise anomalies in Consumption and Average Revenue per unit of Government Irrigation System as per Commercial Statements for FY 2014-15
Sl. No. Category Division Consumption/ kW Revenue/unit
(Rs. per unit) 1.
State Tubewell EDD, Rishikesh 886.92 4.89
2. EDD (R), Hardwar 884.55 1.17 3. EDD, Rudrapur 385.78 3.01 4.
Pump Canal
EDD, Vikasnagar 538.33 4.35 5. EDD, Srinagar 42.86 2.38 6. EDD, Gopeshwar 8.10 3.11 7. EDD, Kotdwar 0.93 - 8. EDD, Ramnagar 34.23 3.96
This signifies that either proper load monitoring is not being carried out and the connections
are released on lower contracted load or fictitious sales are booked to camouflage the losses because
of which the consumption/kW is coming very high and average revenue/unit is working out to be
even lower than the energy charges. In either case, UPCL’s revenue is being suppressed and is
being loaded on to other consumer categories. This also reflects towards the inadequate monitoring
of sales and revenues at the distribution/circle/zonal/head office level of UPCL. Infact during the
current proceedings UPCL was asked to submit the reasons and basis for the anamolies discussed
above. UPCL in its reply merely submitted that it has taken strict measures for curbing the same
and the Field officers have been directed to avoid such kind of careless mistakes and be accountable
for such kind of errors. UPCL further submitted that in order to avoid such errors in the future and
to simplify the monitoring system, the corporate office has revised the formats and, accordingly,
circulated them to the field offices.
In its reply dated January 25, 2016 filed under affidavit, UPCL further submitted that the
matter was examined at the Corporate Office and it was found that the bills are being generated
through a billing software. The billing logics were checked and found to be correct and hence, the
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 137
billing was being done correctly and accordingly, it requested the Commission to treat the pointed
out deficiencies in such a manner that no financial loss is caused to it.
The reply of UPCL again exemplifies its callous and casual approach. In its reply, UPCL
made reference to the billing logic, however, it easily chose to ignore the fact that the Commerical
Statements are being prepared manually and there are every possible chance of human error be it
deliberate or inadvertent. If everything was correct then, UPCL should have furnished the reason
for consumption equivalent to almost 72 hours in a day in case of Jal Sansthan connection in EDD
Kashipur or the Average Revenue in case of Industries being lower than even Rs. 4.00 per unit.
The Commission has been pointing out to such abnormalities in the sales of UPCL in its
previous Orders also, however, still no corrective action has been taken by UPCL in this regard. The
Commission in these proceedings is not making any adjustment on the above accounts. However,
the Commission would examine the matter and if required necessary corrections to this extent
would be made in the subsequent years. In this regard, the Zonal Chiefs, the Circle Chief and the
concerned Executive Engineers are hereby directed to examine the data pointed out above with
reference to their Divisions for FY 2014-15 and submit the justification to the Commission within
45 days of the date of Order on the above discrepancies failing which action may be initiated
against them individually by the Commission under Section 142 of the Electricity Act, 2003.
The category wise sales of UPCL for FY 2014-15 are being discussed hereunder:
a) Domestic Consumers:-
Based on the detailed analysis of the breakup of sales data submitted for FY 2014-15, it is
observed that for domestic consumers, the load factor (sales/kW of connected load) for unmetered
consumers and consumers whose consumption was recorded on assessment basis was substantially
higher than the load factor for consumers whose consumption was recorded on the basis of actual
meter reading. The distribution licensee has not substantiated the basis of recording assessed sales
and unmetered sales. It has also been observed that there are large numbers of defective meters as
in previous years and substantial number of these meters have not been replaced for years. The
Commission in its previous Tariff Orders has been recasting the unmetered sales and assessed sales
based on the load factor of metered consumers.
For carrying out the Truing Up of sales for FY 2014-15, the Commission considering the
abnormalities observed while carrying out the sales analysis for FY 2014-15 has continued with the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
138 Uttarakhand Electricity Regulatory Commission
approach adopted by it in the previous Orders and has recasted the sales for FY 2014-15 of
unmetered consumers and consumers billed on assessment basis. For recasting sales of domestic
category, the Commission has considered the load factor of metered consumers as the basis for
deriving the sales of unmetered consumers and consumers billed on assessment basis.
The Commission has also recasted the sales of departmental employees on the basis of the
load factor of the metered domestic consumers considering the Petitioner’s admission that although
the Departmental employees had been metered, however, the consumption of Departmental
employees was not being recorded and, hence, the same has been considered as unmetered sales by
the Commission.
Accordingly, based on the above, the total recasted sales for Domestic Category for FY 2014-
15 works out to 2245.37 MU against 2274.02 MU submitted by UPCL and the same is summarised
in the Table below:
Table 4.9: Re-casted Sales for Domestic Category for FY 2014-15 (MU)
S. N
o
Sub-
Cat
egor
y Based on Actual Meter Reading Based on Assessment Un-metered Total Total
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Sale
s/kW
/M
onth
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Rec
aste
d Sa
les
(MU
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Rec
aste
d Sa
les
(MU
)
Re-
cast
ed
Sale
s (M
U)
1. BPL and Kutir Jyoti 297044 286979 179.60 625.83 22427 22066 13.96 13.81 - - - - 193.41
2. Other Domestic Consumers 1189261 1783396 1798.97 1008.70 131512 178450 183.37 180.01 7626 9981 10.77 10.07 1989.05
3. UPCL Employees and Pensioners - - - - 8051 25254 47.80 25.47 - - - - 25.47
4. UJVNL Employees and Pensioners - - - - 661 1625 3.57 1.64 - - - - 1.64
5. PTCUL Employees and Pensioners - - - - 355 1166 1.36 1.18 - - - - 1.18
6. Single Point Bulk Supply 93 21357 34.62 1621.10 - - - - - - - - 34.62
Total Domestic 1486399 2091732 2013.20 - 163005 228561 250.06 222.11 7626 9981 10.77 10.07 2245.37
b) PTW Consumers
Based on the detailed analysis of the breakup of sales data submitted for FY 2014-15, it is
observed that for PTW consumers also, the load factor of unmetered consumers and consumers
whose consumption was recorded on assessment basis was substantially higher than the load factor
of the consumers whose consumption was recorded on the basis of actual meter reading. The
distribution licensee has not substantiated the basis of recording assessed sales and unmetered
sales. The Commission in its previous Tariff Orders has been recasting the unmetered sales and
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 139
assessed sales based on the load factor of metered consumers.
For carrying out the Truing Up of sales for FY 2014-15, the Commission has continued with
the approach adopted by it in the previous Orders and has recasted the sales for FY 2014-15 of the
unmetered consumers and consumers billed on assessment basis. For recasting the sales of PTW
category, the Commission has considered the load factor of metered consumers as the basis for
deriving the sales of unmetered consumers and consumers billed on assessment basis.
Accordingly, based on the above, the total re-casted sales for PTW Category for FY 2014-15
works out to 266.86 MU against 298.44 MU submitted by UPCL and the same is summarised in the
Table below:
Table 4.10: Re-casted sales for PTW Category for FY 2014-15 (MU)
Sub-
Cat
egor
y Based on Actual Meter Reading Based on Assessment Un-metered Total Total
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Sale
s/kW
/M
onth
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Rec
aste
d Sa
les
(MU
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Rec
aste
d Sa
les
(MU
)
Re-
cast
ed
Sale
s (M
U)
PTW 23965 140545 233.85 1663.8 1894 11067 20.32 18.41 1389 8776 44.27 14.60 266.86
c) Other Categories
For some other categories, i.e. Non-Domestic, PWW, GIS, Public Lamps and LT Industrial
based on the analysis of the breakup of sales data submitted for FY 2014-15, it is observed that for
these categories, the load factor of unmetered consumers and consumers whose consumption was
recorded on assessment basis was marginally higher than the load factor of those consumers whose
consumption was recorded on the basis of actual meter reading. The Commission in its previous
Tariff Orders has been recasting the unmetered sales and assessed sales based on the load factor of
the metered consumers. For recasting sales for these categories, the Commission has considered the
load factor of the metered consumers as the basis for deriving the sales of unmetered consumers
and consumers billed on assessment basis.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
140 Uttarakhand Electricity Regulatory Commission
Table 4.11: Re-casted sales for Other Categories for FY 2014-15 (MU) S.
No
Cat
egor
y
Based on Actual Meter Reading Based on Assessment Un-metered Total Total
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Sale
s/kW
/M
onth
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Rec
aste
d Sa
les
(MU
Num
ber o
f C
onsu
mer
s
Con
nect
ed
Load
(KW
)
Sale
s (M
U)
Rec
aste
d Sa
les
(MU
)
Re-
cast
ed
Sale
s (M
U)
1. Non Domestic 178876 764004 1043.81 1366.2 13010 17506 24.14 23.92 - - - - 1067.73 2. PWW 1165 69700 309.58 4441.6 49 1430 7.06 6.35 - - - - 315.93 3. GIS 1345 50832 104.93 2064.2 59 1303 2.71 2.69 - - - - 107.62 4. Public Lamps 629 11332 36.83 3249.8 28 402 1.50 1.31 40 1454 8.51 4.73 42.86 5. LT Industry 8759 184660 299.82 1623.6 544 3041 4.97 4.94 - - - - 304.76
d) HT Industries
The Petitioner submitted the sales to HT Industry of 5066.49 MU for FY 2014-15. The
Commission in this regard sought clarification from UPCL whether the sales made to HT Industrial
category has been adjusted for power consumed by HT Industrial consumers through open access.
The Petitioner in its reply submitted that the energy availed through open access energy by HT
Industrial consumers has been adjusted from the consumption units recorded in respect of HT
Industries. As the Petitioner has correctly submitted the sales for this category by excluding the
energy consumed by HT Industries through open access, the Commission has approved the sales
for HT Industries as submitted by the Petitioner.
Based on the above analysis, the category wise sale for FY 2014-15 as re-worked by the
Commission is as shown in the Table below:
Table 4.12: Category-wise Sales for FY 2014-15 (MU)
Categories Approved in the
Tariff Order dated 10.04.2014
Claimed in the Petition
Approved after Truing Up
Domestic (RTS - 1) 2039.38 2272.98 2245.37 Non-domestic, incl Commercial (RTS - 2) 1173.72 1069.93 1067.73 Public Lamps (RTS - 3) 89.70 46.84 42.86 Private Tubewell/Pump Sets (RTS - 4) 210.16 268.89 266.86 Government Irrigation System (RTS - 5) 179.62 107.64 107.62 Public Water Works (RTS - 6) 438.26 316.64 315.93 Industrial Consumers (RTS - 7) 5554.22 5371.28 5371.25 Mixed Load (RTS - 8) 219.23 185.68 185.68 Railway Traction (RTS - 9) 10.26 14.70 14.70 Total 9914.54 9654.58 9618.00
4.1.2 Distribution Losses
The Petitioner in its Petition has submitted its distribution losses for FY 2014-15 at 18.79%.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 141
The Commission for FY 2014-15 had approved distribution losses of 15.50% based on the loss
reduction trajectory approved in the MYT Order for the Control Period from FY 2013-14 to FY 2015-
16. However, as per the actual data submitted by the Petitioner and the sales approved by the
Commission, the actual distribution losses for FY 2014-15 works out to 19.06%.
The Commission, in accordance with the approach adopted in its previous Orders, has
allowed the actual power purchase made by the Petitioner. Considering the actual energy input of
11,882.20 MU at distribution periphery (T&D interface) for FY 2014-15 and applying the approved
loss level of 15.50% for the year, the Commission has re-estimated the sales of 10040.46 MU for FY
2014-15. As against this sale of 10040.46 MU, the actual sales recasted by the Commission for FY
2014-15 is 9618.00 MU. Therefore, there is a loss of sales to the tune of 422.46 MU on account of
commercial inefficiencies of the Petitioner resulting from its failure to achieve target distribution
losses approved by the Commission. The Petitioner has submitted the average billing rate of Rs.
4.09/kWh worked out on the claimed sales of 9654.58 MU. However, on the recasted sale of 9618
MU, the average billing rate works out to Rs. 4.11/kWh and, accordingly, the Commission has
worked out additional revenue of Rs. 173.63 Crore at an average billing rate of Rs. 4.11/kWh for the
sales lost during FY 2014-15. The following Table shows actual distribution loss and approved
distribution loss along with efficiency loss for FY 2014-15 as explained above.
Table 4.13: Assessed Distribution losses for FY 2014-15 (MU)
Particulars Approved in the
Tariff Order dated 10.04.2014
Revised Claim
Approved after Truing
Up Actual Energy Input at T-D Interface / Power Purchase Requirement (MU) 11,803.03 11,882.20 11,882.20
Actual/ Recasted Sales (MU) 9,914.54 9,654.58 9,618.00 Actual Distribution Loss (MU) 1,888.49 2,227.62 2,264.20 Distribution Loss Level (%) 16.00% 18.79% 19.06% Commercial Loss Reduction (%) 0.50% - 0.50% (Loss)/Gain of sales due to inefficiency/efficiency (MU) (Normative Sales-Actual Re-casted Sales)
59.02 390.97 422.46
Approved Distribution Loss (%) 15.50% 15.50% 15.50% Total Normative Sales (MU) 9,973.56 10,045.55 10,040.46 PTCUL Losses (%) 1.82% 1.78% 1.78% Energy Input at State Periphery 12,021.83 12,097.54 12,097.54
Further, as distribution loss is a controllable parameter, the Commission has carried out the
sharing of the impact of excess distribution loss in accordance with the provisions of UERC Tariff
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
142 Uttarakhand Electricity Regulatory Commission
Regulations, 2011.
4.1.3 Power Purchase Expenses (Including Transmission Charges)
The comparison of source wise power purchase quantum and cost as approved by the
Commission in the Tariff Order for FY 2014-15 and actual as claimed by UPCL for FY 2014-15 is as
shown in the Table below:
Table 4.14: Power Purchase Cost approved in the Tariff Order Vs Actual Power Purchase Cost for FY 2014-15 (Rs. Crore)
Source Approved in the Tariff Order Claimed by UPCL
Quantum (MU)
Total cost (Rs. Crore)
Rate (Rs./kWh)
Quantum (MU)
Total cost (Rs. Crore)
Rate (Rs./kWh)
UJVN Ltd. 4463.51 737.73 1.65 3828.31 643.86 1.68 NHPC 637.78 210.09 3.29 562.07 215.00 3.83 THDC 183.15 85.66 4.68 143.99 111.81 7.77 NTPC 3147.85 953.00 3.03 2481.45 803.39 3.24 NPCIL 222.36 68.45 3.08 231.49 72.43 3.13 Free Power 866.43 148.09 1.71 799.89 154.92 1.94 SJVNL 107.46 42.67 3.97 174.35 72.67 4.17 Other IPPs 1162.95 383.93 3.30 709.47 211.22 2.98 Open Market Purchases 1345.54 547.63 4.07 2275.08 844.03 3.71
Banking 115.19 - - 776.76 299.38 3.85 PTCUL - 238.70 - - 236.78 - PGCIL - 254.92 - - 246.50 - Water charges - 20.00 - - - -
Total 12021.85 3690.87 3.07 11982.86 3911.99 3.26
Based on the above comparative statement, the Commission sought the following
clarifications from UPCL:
• Basis of arriving at the banking cost of Rs. 299.38 Crore.
• Reasons for claiming lower PTCUL charges than that approved by the Commission.
In reply, the Petitioner submitted the following:
• The total quantum of 809.125 MU was received by UPCL under banking arrangement
during FY 2014-15 which has to be returned with additional energy of 5% in FY 2015-16.
In the power deficit scenario in the State, the inability of firm sources to meet the existing
demand and absence of any new source in the State, the per unit rate of banking has
been considered as the average per unit rate incurred for purchase from open market
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 143
with 5% escalation to balance out the 5% additional energy to be returned. Accordingly,
the cost of Rs. 299.38 Crore has been booked in the accounts considering the average rate
of Rs. 3.70/kWh.
• The Petitioner submitted that an amount of Rs. 1.91 Crore pertaining to wheeling
charges of open access has been adjusted against the PTCUL charges and submitted the
copies of supporting invoices for the same.
Further, the Commission sought the following information from the Petitioner:
• Month wise energy banking details for FY 2014-15.
• Detailed reasons for making the provision of cost towards banked energy in FY 2014-15
as the energy is to be returned in FY 2015-16.
• How provisioning of cost towards banking made in FY 2014-15 would be dealt in FY
2015-16.
• Source wise actual power purchase cost showing past arrears separately.
In reply, the Petitioner submitted the following information:
• Month wise banking details of forward banking and reverse banking in FY 2014-15.
• Under the banking arrangement, either the energy is received first from other utility and
is returned with some additional energy in the next year of the receipt or energy is given
first to the other utility and is received back alongwith the additional energy. Generally,
no cash transaction is involved in such Banking arrangement of Energy. However, in
case at the end of the year there is any balance of such Banking, the cost has to be
reflected in the books of Accounts and in the cost of electricity supplied. The Petitioner
also placed reliance on Accounting Standard – 1 issued by ICAI which specifies the
fundamental Accounting Assumptions. One of such assumption is “Accrual”, which has
been defined to mean that Financial Statement is prepared on mercantile system only.
Mercantile System of Accounting is known where all the transactions (expenses/
revenues) are recorded on occurrence of such transactions and not when the cash is paid
/received. The Petitioner also submitted that any balance of energy received under
banking arrangement is the part of cost of supply of energy of the year in which such
energy is received and revenue is also booked in the year of receipt of energy and,
therefore, the cost of energy should be booked on the estimated basis in the year of
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
144 Uttarakhand Electricity Regulatory Commission
receipt of such energy which is in line with the matching principle. However, in case at
the end of the year, there is any balance of such banking, the cost has to be reflected in
the books of accounts towards cost of electricity supplied.
• The Petitioner received 809 MU of energy under banking arrangement during FY 2014-
15 and booked the cost of such energy in FY 2014-15. This energy has been returned in
FY 2015-16 out of the power purchase made for FY 2015-16. Thus, the payment of energy
received under banking system in FY 2014-15 has been made in FY 2015-16. The
provision made by UPCL towards the cost of energy banked in FY 2014-15 shall be
reduced in FY 2015-16 and shall not form the part of the power purchase cost in FY 2015-
16. In the previous years, since the net balance of banking energy remained nominal, the
cost of the same was being considered in the year in which it was returned (where it was
first received) and in the year in which it was given (where it was first given).
• The Petitioner submitted that the power purchase cost claimed for true up of FY 2014-15
is as per the audited accounts. The information of actual arrear amount pertaining to the
power purchase cost booked in the accounts for each of the sources of power for FY
2014-15 is not maintained. The Petitioner submitted that the arrear amount as reflected in
the comdata for FY 2014-15 may be considered. The Petitioner further submitted that
during the start of a financial year, billing adjustments are done of bills pertaining to the
previous financial years in the accounts, therefore, certain variations occur on this
account between the cost reflected in the comdata and in the accounts. The Petitioner
also submitted that the average power purchase cost of THDC Ltd. for FY 2014-15 was
substantially high due to arrears.
After scrutiny of the submissions of the Petitioner, the Commission does not find the
methodology adopted by the Petitioner regarding the provisioning of cost towards banked energy
in FY 2014-15 as appropriate since the energy is due to be returned in FY 2015-16. This methodology
leads to serious financial implications as observed in the past practices of the Petitioner when the
excess provisioning towards power purchase cost was made by the Petitioner in previous years and
those provisions were written back in FY 2013-14. The Commission is of the view that the energy
received under banking in FY 2014-15 is to be returned in FY 2015-16 and this is a regular
phenomenon every year. The Petitioner itself in replies to queries raised has also mentioned that the
cost of energy purchased towards return of energy banked in FY 2014-15 has been incurred in FY
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 145
2015-16. Further, it is important to note that the Commission in its Order dated April 11, 2015 while
approving the quantum of power purchase observed as follows:
“As shown above, the total energy availability from the above firm sources works out to 11075.48
MU. The Commission has worked out the monthwise energy requirement and energy availability
from various sources. Considering the month wise requirement and availability, it is observed that
surplus power of 290.08 MU is projected to be available during the months of June to September
2015.
The Commission in its Tariff Order for 2014-15 dated April 10, 2014 has considered the availability
of 1345.54 MU from Medium Term PPA during FY 2014-15. However, as the medium term PPA
during FY 2014-15 is not materialised, UPCL has procured the power through short term sources as
well as received the banking energy during 2014-15. The actual banking energy received by UPCL for
the period April 2014 to January 2015 is around 504 MU, which UPCL will have to return in FY
2015-16. The Commission in line with its approach adopted in its MYT Order dated May 06, 2013
directs the Petitioner to utilise the surplus power for returning the energy received through banking
or bank the same for utilisation in next financial year.”
Thus, the Commission while approving the power purchase quantum and cost for FY 2015-
16 in its Order dated April 11, 2015 had allowed surplus energy of around 290.08 MU to be utilised
for returning the energy received through banking. Further, the Commission is of the opinion that
reliance made by the Petitioner on AS-1 regarding the accrual system of accounting is not relevant
in this issue. In this regard, AS-1 stipulates as under:
“...Revenues and costs are accrued, that is, recognised as they are earned or incurred (and not as
money is received or paid) and recorded in the financial statements of the periods to which they
relate...”
(Emphasis added)
Here, the relevant issue would be the period to which the cost resulting from the banking
arrangement would relate. In accordance with the Banking arrangement entered into by the
Petitioner, it is bound to ensure return of 105% of the banked power during the surplus months, i.e.
summer/rainy season of the financial year, i.e. between 01.07.2015 – 30.09.2015. Hence, the cost
does not accrue to the Petitioner during FY 2014-15 as the Petitioner would either have to return the
banked power during FY 2015-16 or in case of its failure to return such power, it would be liable to
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
146 Uttarakhand Electricity Regulatory Commission
pay the penalty @ average IEX rate of that particular day +Rs. 2.04/kWh. Thus, the Commission
does not confirm to the views of the Petitioner in this regard and is, therefore, of the view that it
would be a more prudent approach to consider the return of energy banked in the year in which it
is being returned instead of making the provisioning of power purchase cost in the year in which
energy has been received under the banking arrangement.
It would also be relevant to mention that the Petitioner has made excess provisioning in this
regard. The Petitioner has made a provision of the cost of Rs. 299.38 Crore considering the average
rate of Rs. 3.70/kWh. However, the Commission had vide its Order dated July 03, 2015 allowed the
Petitioner purchase of about 849.58 MU of energy from M/s. Manikaran Power Limited at a Landed
Price of Rs. 3.37/kWh at the State Periphery which was to be returned to M/s. Haryana Power
Purchase Centre. Thus, the Petitioner has already made an excess provision of Rs. 27 Crore.
In view of the above, the Commission has not considered the provisioning of Rs. 299.37
Crore in approving the power purchase cost for FY 2014-15. The Commission would duly consider
the energy requirement and its cost for FY 2015-16 including return of banked energy received in FY
2014-15 while carrying out the truing up for FY 2015-16. The Petitioner in this regard is directed to
separately claim the cost of the energy returned under banking during truing up exercise of FY
2015-16 and not show the same as adjustment from the provisions.
Further, the Petitioner has also shown Rs. 160.48 Crore paid to UJVN Ltd. towards its past
dues against the gap allowed to UJVN Ltd. for previous years. The Petitioner was asked to clarify
the same. In response the Petitioner submitted that the total past dues of UJVN Ltd. amounting to
Rs. 160.48 Crore were paid during FY 2014-15 and the same were part of the cost of UPCL in FY
2014-15. Since, the Commission has been allowing power purchase cost on the basis of audited
accounts, accordingly, the Commission has considered Rs. 160.48 Crore paid to UJVN Ltd. towards
its past dues for FY 2014-15 on the basis of the audited accounts. Further, with regard to the arrears
paid during FY 2014-15, as the Petitioner has not submitted the break-up for the same, the
Commission has approved the sources wise power purchase cost as reflected in the audited
accounts. Henceforth, the Commission directs the Petitioner to put in place a mechanism for
recording the arrears paid in the year for submission along with its claim of truing up for the
respective year in the absence of which the Commission shall take an appropriate view
regarding the allowable power purchase cost while carrying out the truing up exercise.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 147
Further, the Commission sought the details of deemed generation charges paid by UPCL for
FY 2014-15. In reply the Petitioner submitted that the amount of Rs. 0.17 Crore has been paid on
account of deemed generation charges in FY 2014-15. In this regard, Regulation 47(5) of the UERC
(Tariff and Other Terms of Supply of Electricity from Renewable Energy Sources and non-fossil fuel
based Co-generating Stations) Regulations, 2013 specifies as follows:
“(5) Any charges paid by the distribution licensee towards deemed generation shall not be allowed as
an expense to be pass through in tariffs. The distribution licensee will have to bear such charges.”
In accordance with RE Tariff Regulations, the charges paid by the distribution licensee
towards deemed generation are not allowable in the ARR of the distribution licensee. Hence, the
Commission has not considered the charges of Rs. 0.17 Crore in power purchase cost of FY 2014-15
paid towards deemed generation.
The Commission has considered the rate of free power equivalent to the average power
purchase rate from all major hydro generating stations except free power in accordance with the
methodology laid down by the Commission in its Order dated April 10, 2014 for FY 2014-15. Based
on the above approach, the rate of free power works out to Rs. 1.94/kWh which is equal to the rate
claimed by the Petitioner.
Accordingly, the power purchase cost approved by the Commission on truing up for FY
2014-15 is as shown in the Table below:
Table 4.15: Power Purchase Cost claimed by UPCL and approved by the Commission for FY 2014-15 (Rs. Crore)
Particulars Claimed by UPCL
Approved by the Commission
Power Purchase Expenses 3267.69 2968.15 UJVN Ltd. Arrear 160.48 160.48 Transmission Charges-PGCIL 246.54 246.54 Transmission Charges- PTCUL 236.78 236.78 Total Power Purchase Cost 3911.49 3611.95
4.1.4 Operation and Maintenance (O&M) Expenses
O&M expenses comprises of Employee Expenses, A&G Expenses and R&M Expenses, i.e.
expenditure on staff, administration and repairs and maintenance etc. For estimating the O&M
expenses for the first Control Period, Regulation 84 of UERC Tariff Regulations, 2011 specifies as
below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
148 Uttarakhand Electricity Regulatory Commission
“...
(2) The O&M expenses for the first year of the Control Period will be approved by the Commission
taking into account the actual O&M expenses for last five years till Base Year subject to prudence
check and any other factors considered appropriate by the Commission.
(3) The O&M expenses for the nth year and also for the year immediately preceding the Control
Period, i.e. 2012-13, shall be approved based on the formula given below:-
O&Mn = R&Mn + EMPn + A&Gn
Where –
• O&Mn – Operation and Maintenance expense for the nth year;
• EMPn – Employee Costs for the nth year;
• R&Mn – Repair and Maintenance Costs for the nth year;
• A&Gn – Administrative and General Costs for the nth year;
(4) The above components shall be computed in the manner specified below:
EMPn = (EMPn-1) x (1+Gn) x (CPIinflation)
R&Mn = K x (GFAn-1) x (WPIinflation) and
A&Gn = (A&Gn-1) x (WPIinflation) + Provision
Where –
• EMPn-1 – Employee Costs for the (n-1)th year;
• A&Gn-1 – Administrative and General Costs for the (n-1)th year;
• Provision: Cost for initiatives or other one-time expenses as proposed by the Distribution
Licensee and approved by the Commission after prudence check.
• “K” is a constant specified by the Commission in %. Value of K for each year of the
control period shall be determined by the Commission in the MYT Tariff order based on
licensee’s filing, benchmarking of repair and maintenance expenses, approved repair and
maintenance expenses vis-à-vis GFA approved by the Commission in past and any other
factor considered appropriate by the Commission;
• CPIinflation – is the average increase in the Consumer Price Index (CPI) for
immediately preceding three years;
• WPIinflation – is the average increase in the Wholesale Price Index (CPI) for immediately
preceding three years;
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 149
• GFAn-1 - Gross Fixed Asset of the Transmission Licensee for the n-1th year;
• Gn is a growth factor for the nth year. Value of Gn shall be determined by the
Commission in the MYT tariff order for meeting the additional manpower requirement
based on licensee’s filings, benchmarking and any other factor that the Commission feels
appropriate:
Provided that repair and maintenance expenses determined shall be utilised towards repair and
maintenance works only.”
4.1.4.1 Employee Expenses
The Petitioner submitted that the normative employee expenses for FY 2014-15 have been
arrived at as per the UERC Tariff Regulations, 2011 by considering the employee expenses for FY
2011-12 as the base year expense.
The Petitioner submitted that it had to bear the responsibility of paying enhanced pension
which was on account of pay revision in third time scale with effect from 01.01.1996 due to which
pension and family pension was revised for the employees who retired between 01.01.1996 and
20.07.2010. The treasury department of Uttarakhand refused to disburse pension on enhanced pay
as they did not get contribution on this account. GoU vide GO No. 85 dated 07.07.2011 stated that
the pension/family pension is not allowed on presumptive pay. On February 5, 2013, Additional
Secy (Energy) vide letter no. 173 directed UPCL to release enhanced pension from their own fund.
In accordance with the directions of GoU, UPCL has started paying enhanced pension to the
employees who retired during 01.01.1996 to 20.07.2010.
The Petitioner submitted that the actual impact of enhanced pension for FY 2014-15 was Rs.
11.23 Crore. Since enhanced pension was not part of the base employee expenses, this has been
considered additionally in FY 2014-15. The Petitioner has claimed the normative gross employee
expenses for FY 2014-15 of Rs. 352.99 Crore as shown in the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
150 Uttarakhand Electricity Regulatory Commission
Table 4.16: Revised Employee Expenses Trajectory for MYT Control Period as submitted by the Petitioner (Rs. Crore)
Particulars FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 Inflation Factor 10.40% 9.76% 9.50% 8.80% Growth Factor 0.00% 0.00% 0.00% 5.91% Gross Employee Expenses 284.35 312.10 341.76 393.82 Impact of enhanced pension 17.23 11.23 12.22
Gross Employee Expenses 284.35 329.33 352.99 406.03
The Petitioner submitted that the normative gross employee expenses for FY 2014-15 have
been considered as Rs. 352.99 Crore. The actual capitalisation of employee expenses for FY 2014-15
is Rs. 50.34 Crore. Hence, the normative net employee expenses for FY 2014-15 is Rs. 302.65 Crore as
against the actual net employee expenses of Rs. 263.72 Crore.
The Commission has re-worked the normative employee expenses for FY 2014-15 in
accordance with UERC Tariff Regulations, 2011. The Commission has approved the trued up
normative gross employee expenses of Rs. 261.99 Crore for FY 2013-14. Considering the same, in
accordance with the Regulations, the Commission has computed the normative employee expenses
for FY 2014-15. Regarding the growth factor, the Commission observed that the number of
employees of UPCL has reduced from FY 2013-14 to FY 2014-15 as the retirement of employees
outpaced the recruitment of employees during these years. Hence, the Commission has considered
the Gn factor as zero. The Commission has considered the inflation factor of 9.50% which is the
average of CPI inflation for the preceding three years of FY 2014-15 as against the inflation factor of
8.75% approved by the Commission in the MYT Order based on the CPI inflation for FY 2010-11 to
FY 2012-13. The Commission has considered the capitalisation of expenses in the same proportion
of actual capitalisation of expenses to the actual gross expenses. Further, in line with the approach
adopted by the Commission in the true up for FY 2013-14, the Commission has considered the
impact of enhanced pension as claimed by UPCL considering the statutory liability of the Petitioner.
However, the Commission would again like to caution the Petitioner that any further allowance or
incentives or benefits granted to its employees will have to be borne by UPCL from its own
resources or through increased efficiency. The normative employee expense approved by the
Commission for FY 2014-15 is as shown in the Table below:
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 151
Table 4.17: Approved Employee Expenses for FY 2014-15 (Rs. Crore)
Particulars Approved in
the Tariff Order
Actual as per Audited
Accounts
Normative Claimed by
UPCL Approved
Employee expenses 259.89 263.72 302.65 255.86
4.1.4.2 Repair and Maintenance
The Commission has approved the R&M expenses of Rs. 119.56 Crore for FY 2014-15. As
against the same, the actual R&M expenses for FY 2014-15 as per the audited accounts is Rs. 86.99
Crore. The Petitioner has claimed the normative R&M expenses of Rs. 119.56 Crore.
The Commission has re-worked the normative R&M expenses for FY 2014-15 in accordance
with UERC Tariff Regulations, 2011. The Commission in its Order dated April 11, 2015 had
approved the K factor of 2.84% based on the revised GFA approved for FY 2007-08 to FY 2012-13.
The Commission has considered the inflation factor of 7.42% which is the average of WPI inflation
for the preceding three years of FY 2014-15. The normative R&M expenses approved by the
Commission for FY 2014-15 is as shown in the Table below:
Table 4.18: Approved R&M Expenses for FY 2014-15 (Rs. Crore)
Particulars Approved in
the Tariff Order
Actual as per Audited
Accounts
Normative Claimed by
UPCL Approved
R&M Expenses 119.56 86.99 119.56 114.02
4.1.4.3 A&G Expenses
The Commission has approved the A&G expenses of Rs. 24.79 Crore for FY 2014-15. As
against the same, the actual A&G expenses as per the audited accounts is Rs. 20.99 Crore. The
Petitioner has claimed the normative A&G expenses of Rs. 24.79 Crore for FY 2014-15.
The Commission has re-worked the normative A&G expenses for FY 2014-15 in accordance
with UERC Tariff Regulations, 2011. The Commission has considered the inflation factor of 7.42%
which is average of WPI inflation for the preceding three years of FY 2014-15. The Commission had
further allowed additional A&G expenses for Rs. 3.48 Crore towards the data centre cost and call
centres. The Commission in its additional queries sought actual expenses incurred under these
heads from the Petitioner. The Petitioner in response submitted that the actual cost incurred
towards the same was Rs. 0.75 Crore. The Commission has, therefore, allowed Rs. 0.75 Crore
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
152 Uttarakhand Electricity Regulatory Commission
towards such expenses as against Rs. 3.48 Crore approved by the Commission in its MYT Order.
With regards to capitalisation of A&G Expenses, the Commission has considered the
capitalisation amount of Rs. 8.14 Crore as submitted by the Petitioner. The A&G expenses approved
by the Commission for FY 2014-15 is as shown in the Table below:
Table 4.19: Approved A&G expenses for FY 2014-15 (Rs. Crore)
Particulars Approved in
the Tariff Order
Actual as per Audited
Accounts
Normative Claimed by
UPCL Approved
A&G expenses 24.79 20.99 24.79 21.03
Accordingly, the Commission has allowed net O&M expenses as shown in the Table below:
Table 4.20: Approved O&M expenses for FY 2014-15 (Rs. Crore)
S. No. Particulars
Approved in the Tariff
Order
Actual as per Audited
Accounts
Normative Claimed by
UPCL Approved
1. Employee expenses 259.89 263.72 302.65 255.86 2. R&M expenses 119.56 86.99 119.56 114.02 3. A&G expenses 24.79 20.99 24.79 21.03 Total 404.23 371.70 447.00* 390.90
*submitted as 440.47 in the Petition
4.2 Cost of Assets & Financing
4.2.1 Capital cost of Original Assets
As regards the capital cost of original assets, the Commission vide its Order dated April 11,
2015 held as under:
“3.2.5.1 Capital Cost of Original Assets
The Commission observed that the issue of original value of fixed assets for the Petitioner examined in
detail in Paras 5.3.1 and 5.3.2 of the Order dated April 25, 2005. For reasons provided in the said
Order, the original value of GFA as on November 09, 2001 was fixed at Rs. 508 Crore for the
Petitioner, instead of the value of Rs. 1058.18 Crore assigned in the Provisional Transfer Scheme. The
Commission had already recorded the reasons for the same in its previous Tariff Orders. Since, there
is no change in the factual position and the matter is pending before the Hon’ble ATE, the
Commission decides to maintain Status-quo ante.”
In this regard, Hon’ble ATE in its Judgment dated May 18, 2015 in Appeal No. 180 of 2013
ruled as under:
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 153
“25. We feel that since it is matter of transfer scheme and apportioning of value of assets between two
States after reorganization, the Appellant should take up the matter with State Government for
issuance of notification on transfer of assets to Uttarakhand from UP. Accordingly decided.”
In light of the Judgment of the Hon’ble ATE, the Commission does not find the need to
revise the capital cost of original assets from the earlier approved value of Rs. 508 Crore for the
Petitioner.
As regards the capitalisation of assets, the Commission vide its Order dated April 11, 2015
held as under:
“3.2.5.2 Capitalisation of Assets
……………………….
In view of the above and taking cognisance of the efforts made by the Petitioner so far to get the
clearance of all the HT/EHT works and also the fact that the Petitioner has deposited the requisite fee
& has also given an undertaking to submit EI certificates for all the HT works executed till FY 2013-
14 by July 31, 2015, the Commission has provisionally considered capitalisation of all the assets as per
the audited accounts till FY 2013-14. The capitalisation so allowed is provisional and is subject to
submission of EI certificates. Since the capitalisation of assets is being considered on the provisional
basis, the Commission has not carried out the truing up for FY 2007-08 to FY 2012-13 for capital
related expenses and the same shall be carried out in the next tariff proceedings after the Petitioner
submits before the Commission all the clearance certificate of HT/EHT works capitalised and also
upon submission of additional information/details as directed in the Order…………………
The Commission, therefore, once again reiterates its views in the matter that the delay in obtaining
clearance certificates from the Electrical Inspector and also the segregation of LT and HT/EHT works
was due to the inefficiency of UPCL, hence, no carrying cost will be admissible to UPCL on account
of truing up of the capital works…”
In this regard, the Petitioner submitted that the year wise gross addition in fixed assets
(plant and machinery & lines and cables) as per the Audited Accounts was as follows:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
154 Uttarakhand Electricity Regulatory Commission
Table 4.21: Year wise GFA addition as submitted by UPCL (Rs. Crore)
Year Plant & Machinery Lines & Cables
Sum of Plant and Machinery and Lines &
Cables
HT LT Total HT LT Total HT LT Grand Total
FY 2007-08 49.50 70.01 119.51 184.42 48.26 232.68 233.92 118.27 352.19 FY 2008-09 40.50 45.27 85.77 70.51 34.65 105.16 111.01 79.92 190.93 FY 2009-10 67.81 117.91 185.72 258.35 143.51 401.86 326.16 261.42 587.58 FY 2010-11 24.92 88.87 113.79 276.91 196.37 473.28 301.83 285.24 587.07 FY 2011-12 24.04 129.76 153.80 319.73 119.92 439.65 343.77 249.68 593.45 FY 2012-13 41.69 64.67 106.36 122.50 92.02 214.52 164.19 156.69 320.88 FY 2013-14 84.19 41.30 125.49 65.38 102.99 168.37 149.57 144.29 293.86 FY 2014-15 124.43 126.58 251.01 166.56 156.99 323.55 290.99 283.57 574.56 Total 457.08 684.37 1141.45 1464.36 894.71 2359.07 1921.44 1579.08 3500.52
• It was observed that out the HT/EHT assets amounting to Rs. 1921.44 Crore as per the
Audited Accounts, physically HT/EHT assets amounted to Rs. 1358.13 Crore and
remaining assets were LT. Hence, out of the total assets amounting to Rs. 3500.52 Crore,
the value of HT/EHT assets amounts to Rs. 1358.13 Crore and value of LT assets
amounts to Rs. 2142.39 Crore.
• The Electrical Inspector Certificates for HT works amounting to Rs. 1358.13 Crore has
been submitted to the Commission vide various correspondences.
The Commission vide its Order dated April 11, 2015 had carried out the truing up for FY
2013-14 by provisionally considering the revised net fixed assets addition till FY 2013-14. As there is
no change in the opening fixed assets and net fixed assets addition for FY 2013-14, the provisional
truing up for FY 2013-14 has attained finality and the Commission does not find the need to reopen
the same. However, the Commission in its Order dated April 11, 2015 has not carried out the final
true up of capital related expenses for FY 2007-08 to FY 2012-13 although the revised net fixed assets
addition had been provisionally considered.
Considering the fact that the Petitioner has already submitted the Electrical Inspector
Certificates for the entire HT works amounting to Rs. 1358.13 Crore and since, the balance works are
LT works, accordingly, the Commission has carried out the truing up of capital related expense for
FY 2007-08 to FY 2012-13 based on the revised net fixed assets addition.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 155
4.2.1.1 Impact of truing up of capital related expense for FY 2007-08 to FY 2012-13
4.2.1.1.1 Gross Fixed Assets
The details of capitalisation as approved by the Commission for FY 2007-08 to FY 2012-13 is
as shown in the Table below:
Table 4.22: Net Fixed Assets addition approved by the Commission (Rs. Crore) Particulars FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13
Net Fixed Assets addition 312.69 158.42 320.88 430.11 337.17 230.50
Accordingly, the Assets base of the Petitioner as approved by the Commission for FY 2007-
08 to FY 2012-13 is as shown in the Table below:
Table 4.23: Assets base approved by the Commission (Rs. Crore) Particulars FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13
Opening Balance 1227.76 1540.46 1698.88 2019.76 2449.87 2787.04 Net additions 312.69 158.42 320.88 430.11 337.17 230.50 Closing Balance 1540.46 1698.88 2019.76 2449.87 2787.04 3017.55
4.2.1.1.2 Financing of Capital assets
The following Table shows the means of finance as approved in the Tariff Order dated April
11, 2015 while carrying out the truing up for FY 2013-14 for assets capitalised from FY 2007-08 to FY
2012-13 .
Table 4.24: Means of Finance approved by the Commission (Rs. Crore) Particulars FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13
RGVVY Loan 13.24 9.99 6.05 19.94 - - AREP Loans 0.02 - - - 16.84 - State/District Plan 29.43 12.93 10.76 23.19 84.14 10.90 APDRP Loan - 1.82 0.68 4.17 - - R-APDRP Part A Loan - - - - - - REC Loan - - - - - 42.58 PMGY/MNP - - - 9.92 17.64 - PTW Loan 4.63 - - - - - Deposit works 26.07 43.52 164.82 60.40 47.25 26.50 Grants 152.13 35.85 63.06 186.94 104.34 93.20 Internal Resources 87.18 54.32 75.51 125.56 66.96 57.32 Total 312.69 158.42 320.88 430.11 337.17 230.50
The Commission has, accordingly, re-computed the depreciation, interest on loans, RoE and
interest on working capital for FY 2007-08 to FY 2012-13 on account of revised net fixed asset
addition approved in this Order. The capital cost related expenses approved in the provisional true
up and approved in this Order for FY 2007-08 to FY 2012-13 is as shown in the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
156 Uttarakhand Electricity Regulatory Commission
Table 4.25: Impact of final true up of capital related expenses for FY 2007-08 to FY 2012-13 approved by the Commission (Rs. Crore)
Particulars
FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13
Prov
isio
nal
true
up
Fina
l tru
e up
Prov
isio
nal
true
up
Fina
l tru
e up
Prov
isio
nal
true
up
Fina
l tru
e up
Prov
isio
nal
true
up
Fina
l tru
e up
Prov
isio
nal
true
up
Fina
l tru
e up
Prov
isio
nal
true
up
Fina
l tru
e up
Depreciation 18.89 26.86 18.87 30.61 24.33 41.14 33.18 45.26 35.19 51.76 38.77 58.83 Interest on Loan 20.25 21.57 20.21 26.20 21.33 26.83 26.96 27.28 27.23 33.81 30.20 35.55
RoE 0.70 9.54 1.64 13.21 3.47 15.49 16.20 18.66 19.80 23.93 22.30 26.74 IWC 4.77 5.08 6.00 6.50 6.93 7.63 12.42 12.71 2.85 3.44 8.70 9.43 Total 44.61 63.05 46.72 76.51 56.06 91.09 88.76 103.91 85.07 112.94 99.97 130.56 Impact 18.44 29.79 35.03 15.15 27.87 30.59
Hence, the total impact of the final true up of capital related expenses for FY 2007-08 to FY
2012-13 results in a gap of Rs. 156.87 Crore. As already held by the Commission in its Order dated
April 11, 2015 no carrying cost has been considered on this gap on account of final true up of capital
related expenses from FY 2007-08 to FY 2012-13. The Commission has dealt with this gap of Rs.
156.87 Crore in Chapter 5 of this Order.
4.2.1.2 Truing up of Capital Related Expense for FY 2014-15
The Commission vide its Order dated April 11, 2015 had carried out the true up for FY 2013-
14 and had approved the net GFA addition of Rs. 185.01 Crore for FY 2013-14. The Commission had
also approved the means of finance in the previous Order and the same is shown in the Table
below:
Table 4.26: Approved Means of Finance for FY 2013-14 (Rs. Crore) Particulars FY 2013-14
RGVVY Loan 7.78 AREP Loan - State/District Plan 1.89 APDRP Loan - R-APDRP Part A Loan 2.97* REC Loan 79.90 PMGY/MNP - PTW Loan - Deposit Works 28.98* Grant - Internal resources 63.49# Total 185.01
*considered as grant #30% has been considered as equity & 70% has been treated as mormative loan
The Petitioner has claimed the net GFA addition of Rs. 472.76 Crore for FY 2014-15. The
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 157
Petitioner has submitted the Electrical Inspector Certificates for the HT works capitalised in FY
2014-15. Hence, the Commission has considered the net GFA addition of Rs. 472.76 Crore for FY
2014-15. The means of finance for the capitalisation of Rs. 472.76 Crore as submitted by the
Petitioner is shown in the Table below:
Table 4.27: Means of Finance for FY 2014-15 as submitted by the Petitioner (Rs. Crore)
Particulars FY 2014-15 RGVVY Loan 9.62 R-APDRP Part A Loan 16.59 REC Loan 189.89 Deposit Works 181.84 Grant Internal resources 74.82* Total 472.76
* 30% has been considred as equity and balance 70% considered as normative loan
The means of finance approved by the Commission for FY 2014-15 is as shown in the Table
below:
Table 4.28: GFA & Means of Finance approved by the Commission (Rs. Crore)
Particulars FY 2013-14 FY 2014-15 Grants Loan Equity Total Grants Loan Equity Total
Opening Value 1 ,362.72 1,195.07 459.76 3,017.55 1394.67 1329.08 478.80 3202.56 Total Addition during the year 31.95 134.01 19.05 185.01 181.84 268.47 22.45 472.76
Closing Value of GFA 1,394.67 1,329.08 478.80 3,202.56 1576.51 1597.56 501.25 3675.32
4.2.1.2.1 Interest and Finance Charges
The Petitioner has claimed Interest and Finance Charges of Rs. 135.49 Crore for FY 2014-15
against the amount of Rs. 121.82 Crore approved by the Commission in the Tariff Order dated April
10, 2014.
The Petitioner submitted that it has claimed interest expenses on the following basis:
a) Actual interest accrued during the year has been claimed which is net off
capitalisation.
b) Interest on UPPCL Loans has not been considered.
c) Interest on REC (Old) loans has been taken in accordance with the interest
determined by the Commission in the Tariff Order for FY 2014-15 dated April 10,
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
158 Uttarakhand Electricity Regulatory Commission
2014.
d) Government Guarantee fees is considered on actual basis.
e) Interest on GPF has been considered. The Petitioner requested the Commission to
allow interest on GPF as part of interest expense as this is the statutory liability of the
Petitioner. The Petitioner submitted that the Government of Uttarakhand (GoU) has
in the past refused to provide support on account of Interest on GPF. The Petitioner
added that GoU is already bearing the terminal liability of the old employees unlike
other States. The Petitioner, further, requested the Commission that in case the
interest on GPF has to be borne by the State Government, the Commission should
issue suitable directions to GoU in this regard.
f) No Interest on short-term funding through overdraft facility has been considered.
It is observed that the Petitioner has again claimed interest on AREP loans which has not
been allowed by the Commission in its previous Tariff Orders for reasons given in the respective
Orders. In this regard, the Petitioner submitted that since it is paying interest on AREP loans, the
same should be allowed. However, the Petitioner chose to ignore the fact that the AREP loan were
interest free loan and interest was payable in case of default by the borrower and the costs
associated with any default cannot be allowed to be pass through in tariffs. Hence, the Commission
again disallows the interest claimed on AREP loans. The Commission has also not considered
interest on R-APDRP loans in line with the approach adopted by the Commission in the previous
Tariff Order.
Regulation 28 of the UERC Tariff Regulations, 2011 stipulates the methodology for
computation of interest expenses. The Commission in accordance with the above Regulation has
worked out the Interest and Finance Charges for FY 2014-15 considering the loan amounts
corresponding to assets capitalised in the year based on the approved means of finance, and the
interest rate of 10.41% has been computed on the basis of weighted average interest rate on the
actual loan portfolio at the beginning of each year.
The Petitioner has again requested the Commission to allow interest on GPF as part of
interest expenses as the same is a statutory liability of the Petitioner. The Commission in the past
has not allowed such expenses for reasons given in the respective Orders. Hence, the Commission
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 159
again disallows the interest claimed on GPF.
The Petitioner has claimed interest liability on consumers’ security deposits (CSD) for FY
2014-15 as Rs. 43.95 Crore. In reply to the Commission’s query, the Petitioner submitted that the
actual interest on CSD paid/adjusted in the bills for FY 2014-15 was Rs. 31.86 Crore. The
Commission has approved the interest on CSD for FY 2014-15 as Rs. 31.86 Crore.
Further, the Guarantee Fee and interest on REC Old Loan has been allowed as claimed by
UPCL. Also, the Commission has not reduced the amount of interest capitalised as the Commission
has considered the loans corresponding to the assets capitalised and not the total loans as taken by
the Petitioner.
The Commission has worked out the Interest and Finance Charges for FY 2014-15
considering the loan amounts corresponding to the assets capitalised in the year based on the
approved means of finance, as shown in the Table below:
Table 4.29: Interest and Finance Charges for FY 2014-15 (Rs. Crore)
Particulars Tariff Order
Claimed by UPCL Approved
Govt. of Uttarakhand Loan 50.13 48.55 47.12 REC Old Loan 25.51 25.51 25.51 Interest on other loans 0.00 67.23 0.00 Total Interest on Loan 75.64 141.29 72.63 Guarantee Fee 2.20 3.40 3.40 Interest on Security Deposit 43.99 43.95 31.86 Other finance and bank charges 0.00 0.62 0.62 Total Interest Charges 121.82 189.26 108.51 Capitalisation 0.00 53.78 0.00 Net Interest and Finance Charges 121.82 135.48 108.51
4.2.2 Depreciation
The Petitioner in its Petition has submitted that it has calculated depreciation considering
the opening and closing GFA for FY 2014-15 on an average basis. Further, the rate of depreciation
considered by it was as specified in UERC Tariff Regulations, 2011. The Petitioner has computed
depreciation at the rate of 5.21% for FY 2014-15. The Petitioner has, accordingly, claimed total
depreciation of Rs. 105.86 Crore as against Rs. 69.38 Crore approved by the Commission in the
Tariff Order for FY 2014-15.
The Commission has allowed depreciation at a weighted average rate of 5.21% based on the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
160 Uttarakhand Electricity Regulatory Commission
audited balance sheet for FY 2014-15. Further, the Commission has been allowing depreciation on
the value of opening GFA keeping in line with the practice being followed by the Petitioner of
capitalising the asset in its accounts on the last day of the financial year. The Tariff Regulations of
the Commission provides for depreciation on pro-rata basis, however, the Petitioner in its accounts
calculates depreciation on the opening GFA as is evident from its Notes to Accounts. Therefore, the
Commission finds no justification to depart from the practice adopted in the previous Tariff Orders
of allowing depreciation on the opening balance of GFA.
The Commission in its additional information directed the Petitioner to confirm that it has
not claimed depreciation in excess of 90% for its assets. The Petitioner in its reply confirmed that
depreciation in FY 2014-15 has been less than 90% of GFA for all assets in accordance with the
UERC Tariff Regulations, 2011.
The depreciation approved by the Commission for FY 2014-15 is as shown in the Table
below:
Table 4.30: Depreciation approved for FY 2014-15 (Rs. Crore) Particulars Claimed by UPCL Approved
Opening GFA - 3202.56 Grants - 1394.67 Depreciable opening GFA 1876.19 1807.89 Net addition during the year 311.38 290.92* Closing GFA 2187.57 2098.81 Depreciation rate 5.21% 5.21% Depreciation 105.86 94.19
*Addtions less grants
4.2.3 Provision for Bad & Doubtful Debts
The Petitioner in its Petition has submitted that the Commission in the MYT Order dated
May 06, 2013 did not allow any provisioning of bad debts for earlier years.
The Petitioner submitted that annual provision towards bad & doubtful debts is an accepted
method of accounting and considering the peculiarity of retail supply of electricity business, the
same has also been recognized by other SERCs. The Petitioner added that the amount, if any,
written off towards bad debts is only adjusted against the accumulated provisions in the books,
irrespective of the actual amount of bad debts during any particular financial year.
The Petitioner requested the Commission to allow provision for bad and doubtful debts on
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 161
actual basis after considering the geographical spread of the large consumer base across the State
including a large part of the same prevailing in the difficult terrain and hilly region and the problem
of realizing energy dues from retail consumers.
The Petitioner further submitted that in line with the approach followed by the Commission
in the previous Tariff Orders, the Petitioner has not included any amount on account of
provisioning of bad debts in the ARR but has calculated the same and has requested the
Commission for its approval.
The Petitioner further submitted that as per the directions of the Commission, the process of
writing off bad debts has already been initiated. The Petitioner in its Petition has requested the
Commission to approve Rs. 37.55 Crore which is the actual write off of bad debts in FY 2014-15.
Regulation 32 of the UERC Tariff Regulations, 2011 specifies as follows:
“32. Bad and doubtful debts
The Commission may allow a provision for bad and doubtful debts upto one percent (1%) of
the estimated annual revenue of the distribution licensee, subject to actual writing off of bad
debts by it in the previous years.
Provided that where the amount of such provisioning for bad and doubtful debts exceeds five
(5) per cent of the receivables at the beginning of the year, no such appropriation shall be
allowed which would have the effect of increasing the provisioning beyond the said
maximum.”
As regards the bad and doubtful debts, the Commission sought the following clarification
from UPCL:
• As to whether the provisioning for bad debts allowed by the Commission till FY
2014-15 were sufficient or not.
• Year wise details of provision for bad debts allowed by the Commission and actual
bad debts written off corresponding to the arrears created subsequent to the
formation of UPCL and those bad debts written off which pertained prior to creation
of UPCL.
In reply, UPCL submitted the following:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
162 Uttarakhand Electricity Regulatory Commission
• The provision for bad and doubtful debts as on November 9, 2001 as per the Transfer
Scheme of Assets and Liabilities executed between UPPCL and UPCL was Rs. 230.01
Crore. The details of provision for bad debts allowed by the Commission and actual
written off is as shown in the Table below:
Table 4.31: Provision for Bad and Doubtful Debts and Actual Write off Year Provision allowed by the Commission Actual written off
FY 2001-02 3.86 - FY 2002-03 10.03 - FY 2003-04 10.94 - FY 2004-05 11.03 - FY 2005-06 12.44 - FY 2006-07 13.87 - FY 2007-08 17.59 - FY 2008-09 23.98 - FY 2009-10 - - FY 2010-11 - - FY 2011-12 - 10.96 FY 2012-13 - 44.04 FY 2013-14 - 47.01 FY 2014-15 - 37.14 Total 103.74 139.15
• Hence, no bad debts have been written off out of the provision made in the Transfer
Scheme.
• Out of the provision of Rs. 103.74 Crore allowed by the Commission till FY 2008-09,
the actual bad debt written off till FY 2013-14 is Rs. 102.01 Crore. In the absence of
availability of sufficient provision, bad debts written off during FY 2014-15 have been
claimed in the true up for FY 2014-15.
• UPCL has identified bad and doubtful arrears amounting to Rs. 417.32 Crore against
1,43,579 consumers. UPCL has targeted to settle this bad debt amount during FY
2016-17 taking steps as per the rules for recovery of the debt and by writing off
irrecoverable amount.
UPCL was asked to submit the details of bad debts written off and also to confirm that the
amount shown as bad debts written off does not include any billing adjustments. However, in
response UPCL submitted the category wise details of the bad debts written off and did not clarify
that the amount shown as bad debts written off does not include any billing adjustments. On
perusal of the category wise details of bad debts written off during FY 2014-15, it appears that
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 163
UPCL has written off Rs. 1.65 Crore dues of Public Water Works and Government Irrigation
System, which are connections to Government owned corporations or departments and it is
unimaginable to comprehend as to how the dues to such connections can turn bad. Moreover, with
respect to the amount written off by the Petitioner during FY 2011-12 and FY 2012-13, the Petitioner
in the previous proceedings had submitted that the wrong billing made in the earlier period were
corrected by the distribution divisions and the value of excess billing had been written off in FY
2011-12 and FY 2012-13. Since the write offs were basically the rectification of wrong billing and,
accordingly, the Commission had held that such corrections cannot be treated as writing off of bad
debts. This clearly indicates lack of proper policy framework for identification, recognition and
management of provision for bad and doubtful debt. Further, it is surprising that despite categorical
directions issued by the Commission in its previous Tariff Orders, to frame a transparent policy for
identifying, recognising and writing off the bad debts, the Petitioner in its reply has yet again
submitted that it is in the process to finalise the bad debts write off policy of the company.
The Petitioner is directed to finalise the Policy within three month from the date of Order
and submit the same for approval of the Commission.
It is all the more surprising to note that the Petitioner has chosen to ignore the provisions of
Rs. 230 Crore inherited by it from UPPCL against the opening debtors of Rs. 619 Crore. The Transfer
Scheme agreed by the two Corporation dates back to the year 2001. It cannot be ruled out that out of
Rs. 619 Crore inherited by UPCL, some amount may be bad and doubtful by now which have to be
written off by the Petitioner from the total amount of provisions available with it. Infact, UPCL in its
submissions has also submitted that the arrears amounting to Rs. 273 Crore are pending for more
than 5 years. However, UPCL has not submitted the basis of arriving at the ageing of debtors. UPCL
is directed to submit the basis of arriving at the ageing of debtors within one month of the date
of Order. Hence, the Commission does not see any justification on the part of the Petitioner to
ignore the opening provisions inherited by UPCL.
Hence, the Commission has already allowed the Petitioner a total provision of Rs. 333.74
Crore till FY 2008-09 which also includes the opening balance of the provision inherited from
UPPCL. Even considering the actual write off debt of Rs. 139.15 Crore till FY 2014-15, the Petitioner
is still left with a provision of about Rs. 194 Crore. The closing debtors of UPCL as on 31.03.2015
were to the tune of Rs. 2087.33 Crore. Hence, the provision available with UPCL is to the extent of
9.30% of the existing debtors and any additional provision is not allowable in accordance with the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
164 Uttarakhand Electricity Regulatory Commission
Regulations as referred above.
4.2.4 Interest on Working Capital (IoWC)
The Petitioner has submitted that it has computed interest on working capital as per UERC
Tariff Regulations, 2011. However, as per the computation submitted by the Petitioner the net
working capital is submitted as Rs. -66.78 Crore. The Petitioner has submitted that it has not
claimed any IoWC.
The computation of interest on working capital as submitted by the Petitioner is detailed in
the Table below:
Table 4.32: Interest on Working Capital for FY 2014-15 (Rs. Crore) Particulars Amount
Operation and Maintenance Expenses (one month) 30.98 Maintenance @ 15% of O&M Expenses 55.76 Receivables (2 months) 685.01 Sub-total 771.74 Less: Adjustment for security deposits & Credit available for Power Purchase 838.53 Net working capital -66.78 Interest on working capital 0.00
The Commission has computed the working capital requirement as per UERC Tariff
Regulations, 2011. Similar to the Petitioner’s submission, the net working capital as worked out
based on the approved expenses is negative, therefore, the Commission is not approving any IoWC
for FY 2014-15, and hence, the Commission has not carried out any sharing of gains and losses on
account of working capital requirement.
4.2.5 Return on Equity
The Petitioner submitted that it has computed Return on Equity (RoE) for FY 2014-15 based
on actual equity invested in the business. The Petitioner further submitted that it has calculated RoE
on the basis of the following:
• Revised opening equity has been considered for FY 2001-02 depending upon the
finalisation of transfer scheme.
• Year wise addition of equity has been considered at maximum of 30% of the
capitalisation excluding grants and deposit works for each year. In the year when the
equity deployed was less than 30%, actual equity has been considered. The equity in
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 165
excess of 30% has been considered as normative loan.
• The closing equity for FY 2013-14 has been considered as the opening equity for FY 2014-
15.
• The capitalisation for FY 2014-15 excluding the grants and deposit works has been
considered to be funded in the debt equity ratio of 70:30.
• Return on equity has been computed on the average equity at the rate of return of 16%.
In this regard, Regulation 22 of UERC Tariff Regulations, 2011 specifies as under:
“22. Debt-equity ratio
(1) For a project declared under commercial operation on or after 1.4.2013, debt-equity ratio shall
be 70:30. Where equity employed is more than 30%, the amount of equity for the purpose of
tariff shall be limited to 30% and the balance amount shall be considered as normative loan.
Where actual equity employed is less than 30%, the actual equity would be used for
determination of Return on Equity in tariff computations...”
Further, Regulation 27 of UERC Tariff Regulations, 2011 specifies as under:
“27. Return on Equity
(1) Return on equity shall be computed on the equity base determined in accordance with Regulation
22.
Provided that, Return on Equity shall be allowed on amount of allowed equity capital
for the assets put to use at the commencement of each financial year…”
(Emphasis added)
Thus, it is to be noted that merely having equity in its accounts does not qualify the equity as
eligible for return purposes. For equity to be eligible for return, the same should have been invested
in creation of an asset. Moreover, contrary to UPCL’s practice of considering the year wise addition
of equity at maximum of 30% of the total capitalisation excluding grants and deposit works for each
year, the Commission in accordance with the Regulations has considered project wise financing as
submitted by UPCL and if in any project equity is in excess of 30% of the cost of the project, balance
has been treated as normative loan. Further, as per the Regulations referred above, return on equity
is allowable on opening equity.
Hence, the Commission has considered the closing equity for FY 2013-14 as the opening
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
166 Uttarakhand Electricity Regulatory Commission
equity for FY 2014-15. The Commission has approved the Return on Equity at the rate of 16% on the
opening equity in accordance with the Regulations. The Return on Equity approved by the
Commission for FY 2014-15 is as shown in the Table below:
Table 4.33: Return on Equity approved by the Commission for FY 2014-15 (Rs. Crore)
Particulars Approved in the Tariff Order Claimed by UPCL Approved
Return on Equity 40.42 78.17 36.36
4.2.6 Non-Tariff Income
The Petitioner submitted that the Non-Tariff Income includes income from non-tariff sources
such as income from investments, delayed payment surcharge, etc. The Petitioner, in its Petition,
has claimed non-tariff income as Rs. 162 Crore on the actual basis, including delayed payment
surcharge of Rs. 60.58 Crore. The actual Non-Tariff Income as per the audited accounts is Rs. 515.86
Crore. The Petitioner has not considered the Non-Tariff Income on account of material cost
variance, interest on institutional liabilities for previous years written back and 50% of
rebate/incentive.
The Petitioner submitted that the Non-Tariff Income on account of material cost variance has
not been considered as this is only an accounting entry due to change in accounting policy and
there is no cash involved in the same. The Non-Tariff Income further included the impact of
reversal of provision for obsolete stock material as the provision was written back in FY 2014-15 to
portray true state of affairs of the Corporation since the credit balance was persisting in the audited
accounts from the date of creation of UPCL. The Petitioner submitted that the Non-Tariff income on
account of interest on institutional/liabilities for previous years written back has not been
considered as the same pertains to accounting adjustments of previous years.
Further, the Petitioner in reply to the Commission’s query submitted that the material cost
variance amounting to Rs. 117.71 Crore was pertaining to the previous years from creation of UPCL
till FY 2014-15. The Petitioner requested the Commission to consider the same as Non-Tariff Income
equally in the next 10 years. The Petitioner also requested the Commission to consider the
provisioning of obsolete stock material amounting to Rs. 14.52 Crore as Non-Tariff Income equally
in the next 10 years. The Commission has dealt with this issue and other past period adjustments in
the next Chapter on Approval of ARR and Revenue Gap for FY 2016-17.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 167
The Commission for the purpose of truing up for FY 2014-15 has considered the Non-Tariff
Income as claimed by UPCL. The Non-Tariff Income approved by the Commission for FY 2014-15 is
as shown in the Table below:
Table 4.34: Non-tariff Income approved by the Commission for FY 2014-15 (Rs. Crore)
Particulars Approved in the Tariff Order
Claimed by UPCL Approved
Non–Tariff Income 70.04 162.00 162.00
4.3 Tariff Revenue
The Petitioner submitted the revenue at existing tariff as Rs. 3950.12 Crore as against the
revenue of Rs. 4145.84 Crore approved by the Commission in the Tariff Order for FY 2014-15.
The Petitioner submitted that as per UERC Tariff Regulations, 2011, the baseline values for
the Control Period shall be determined by the Commission based on the historical data, latest
audited accounts, estimates for the relevant year and prudence check as applied by the
Commission. The Petitioner further submitted that in case there is a substantial difference between
the estimates provided earlier or considered for the determination of baseline values and the actual
audited accounts, the Commission may re-determine the baseline values for the base year suo-moto
or on an application filed by the Applicant.
Based on the above, the Petitioner has requested the Commission to re-determine the
distribution loss trajectory keeping in mind the actual distribution loss for FY 2012-13 which is
21.70% against 17% considered by the Commission in the MYT Order based on which the trajectory
for the Control Period was projected.
The Petitioner submitted that the Commission, in previous Tariff Orders, has been
computing additional deemed revenue earned by the Utility for adjusting the approved losses
against the actual, which in reality is not earned by the Petitioner. The Petitioner submitted that it
has always strived to achieve the targets of distribution losses fixed by the Commission and,
thereby, provide the best service to its consumers. The Petitioner further submitted that it has
reduced distribution losses by 5.74% in the last 6 years.
The Petitioner, further, submitted that for the loss target not achieved during a particular
year, the Utility is being penalised every year for its non-achievement. However, in order to comply
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
168 Uttarakhand Electricity Regulatory Commission
with the approach adopted by the Commission in its previous Tariff Orders, the Petitioner has
calculated additional revenue for FY 2014-15 and is as shown in the Table below:
Table 4.35: Revenue loss due to higher distribution loss for FY 2014-15 claimed by the Petitioner
Particulars Formula Amount Actual/recasted sales (MU) A 9654.58 Actual energy input at distribution periphery (MU) B 11882.20 Approved distribution losses (%) C 15.5% Sales at approved distribution loss level (MU) D = B*(1-C) 10045.55 Loss of sale due to inefficiency in distribution loss (MU) E=D-A 390.98 Revenue for FY 2014-15 (Rs. Crore) F 3950.12 ABR (Rs./kWh) G= F/A 4.09 Revenue from additional sale (Rs. Crore) F=E*G 159.97
The Petitioner has submitted that as per UERC Tariff Regulations, 2011 distribution losses is
a controllable parameter and, hence, it has proposed to share losses on account of under-
achievement of distribution losses for FY 2014-15.
The Petitioner has further submitted that as per the UERC Tariff Regulation, 2011, collection
efficiency is a controllable parameter. The Petitioner further submitted that the Commission in the
MYT Order dated May 6, 2013 has fixed the collection efficiency target for the Petitioner for FY
2014-15 as 98%. The Petitioner submitted that the actual collection efficiency achieved by the
Petitioner was 100.61% (including arrears), resulting in gain due to higher collection by Rs. 103.19
Crore. The Petitioner has further proposed to share gains with the consumer @ 20% in accordance
with the UERC Tariff Regulations 2011. The Commission with regard to Petitioner’s claim of
sharing of gains on account of increased collection efficiency is of the view that as per the
Regulations, the Commission has been approving the revenue to meet the ARR on accrual basis and
not on cash basis. Moreover, the licensee should strive for maximum collections so as to improve its
financial health and preventing any receivables turning bad. Hence, sharing of gains on account of
increase in collection efficiency is not correct and, therefore, the Commission has not considered the
same. The Commission, as discussed earlier, has carried out the sharing of losses for under-
achievement in distribution losses.
The Commission has considered distribution loss for FY 2014-15 as approved by it in its
MYT Order and, accordingly, has computed the loss of sales as 422.46 MU due to commercial
inefficiencies of UPCL.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 169
As discussed while approving the category wise sales for FY 2014-15, the Commission has
recasted the sales of domestic, PTW, Non-Domestic, PWW, Public Lamps and LT Industry
consumers from the sales submitted by the Petitioner. Since, the sale has been reduced, the
Commission has, accordingly, reduced the revenue corresponding to the assessed sales from the
total revenue submitted by the Petitioner. The revenue corresponding to the assessed sale is shown
in the Table below:
Table 4.36: Revenue for FY 2014-15 Corresponding to Assessed Sales
Particulars
Assessed Sales to be reduced based
on average metered sale (MU)
Actual ABR (Rs./kWh)
Revenue Corresponding to
Assessed Sales (Rs. Crore)
BPL and Kutir Jyoti 0.15 2.12 0.03 Other Domestic Consumers 4.05 2.96 1.20 Non Domestic 0.22 4.74 0.10 PTW 31.58 1.18 3.74 PWW 0.71 5.44 0.39 GIS 0.02 4.73 0.01 Public Lamps 3.98 5.62 2.24 LT Industries 0.03 4.52 0.01 Total 7.71
With regards the revenue from departmental employees both in service and retired, it is
observed that per unit rate of Rs. 0.39/kWh for this category is very low compared to other
domestic category of consumers. The Petitioner has submitted that departmental employees have
been metered, thus, actual consumption of departmental employees should have been recorded on
metered basis and, accordingly, the rate applicable to domestic category of consumers should have
applied to these consumers also. The consumption of these consumers is on assessed basis and as
mentioned earlier even sales booked under this head has been recasted to align it with the average
metered sale. The tariff prescribed by this Commission does not provide any special dispensation
for serving or retired employees of the licensee. As such, they are like any other domestic
consumers and revenue recognition for them should be based on tariff prescribed for domestic
consumers. Apparently, this is not being done. It is understood that the licensee has prescribed a
fixed sum to be recovered from them for domestic use of electricity. The cost of subsidised supply of
power to its employees will have to be borne by the licensee and cannot be allowed to devolve on
other consumers, therefore, the Commission has added the impact of difference in the ABR of
departmental consumers and the ABR of other domestic consumers in the revenue for FY 2014-15.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
170 Uttarakhand Electricity Regulatory Commission
Considering the re-casted consumption of 28.29 MU and the average billing rate of other
domestic consumers which are metered, i.e. Rs. 2.96/kWh the revenue works out to Rs. 8.37 Crore.
However, as per the submission of the Petitioner the revenue realized from the departmental
employees is only to the extent of Rs. 0.96 Crore. As detailed in the previous Tariff Orders, the
Petitioner shall have to bear the burden of any subsidy it wants to provide to the departmental
employees from its own resources and, therefore, the Commission has added the difference of Rs.
7.42 Crore as additional revenue towards sale to departmental employees.
Based on the above, the revenue from the sale of power, as worked out by the Commission
is shown in the Table below:
Table 4.37: Revenue from Sale of Power for FY 2014-15 (Rs. Crore) Particulars Amount
Actual Revenue 3950.12 Less: Revenue corresponding to reduction in Sales 7.71 Add: Revenue corresponding to departmental employees 7.42 Total Revenue 3949.83
Further, as discussed above there is a loss of 422.46 MU on account of commercial
inefficiencies of the Petitioner failing to achieve target distribution loss approved by the
Commission. The Commission has considered the revenue of Rs. 173.63 Crore at an average billing
rate of Rs. 4.11 kWh for this additional loss of sale on account of higher distribution losses while
truing up the ARR for FY 2014-15 as shown in the Table below:
Table 4.38: Additional Revenue from Sale due to inefficiency for FY 2014-15 (Rs. Crore) Sr. No. Particulars Claimed by UPCL Approved
1. Actual/ Re-casted Sales (MU) 9,654.58 9,618.00 2. Approved Distribution Loss Level (%) 15.50% 15.50% 3. Actual Energy Input at T-D Interface (MU) 11,882.20 11,882.20 4. Sales at Actual Energy Input with 15.50% Loss (MU) 10,045.55 10,040.46 5. Loss of Sales due to Inefficiency (MU) 390.97 422.46 6. Revenue at existing Tariff (Rs. Crore) 3950.12 3949.83 7. ABR (Rs./kWh) 4.09 4.11 8. Additional Revenue due to higher distribution losses (Rs. Crore) 173.63 9. Losses to borne by Petitioner Rs Crore) (75% of (8)) 130.22
Accordingly, the Commission has considered tariff revenue of Rs. 4080.05 Crore including
Rs. 130.22 Crore as deemed revenue on account of excess loss for FY 2014-15 as against total
revenue of Rs. 3950.12 Crore claimed by the Petitioner.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 171
4.4 Sharing of gains and losses
The Petitioner submitted that it has achieved better performance against the targets specified
on the performance parameters, i.e. employee expenses, R&M expenses, A&G expenses and
collection efficiency and it was not able to achieve the performance target w.r.t. the distribution
losses.
The sharing of gains and losses claimed by the Petitioner for FY 2014-15 is as shown in the
Table below:
Table 4.39: Sharing of Gains and Losses for FY 2014-15 claimed by the Petitioner (Rs. Crore)
Particulars Amount Consumer Share UPCL Share
A. Gain 20% 80% Employee Expenses 38.93 7.79 31.14 A&G Expenses 3.80 0.76 3.04 R&M Expenses 32.57 6.51 26.06 Collection Efficiency 103.19 20.64 82.55 Subtotal (A) 171.95 35.70 142.79 B. Loss 25% 75% Revenue from Additional Sales 159.97 39.99 119.97 Subtotal (B) 159.97 39.99 119.97 Grand Total – (Loss)/ profit to be borne (4.30) 22.81
Regulation 13 of the UERC Tariff Regulations, 2011 specifies that:
“13. Annual Performance Review
…
(5) The “uncontrollable factors” shall include the following factors which were beyond the control
of, and could not be mitigated by, the applicant, as determined by the Commission. Some
examples of uncontrollable factors are as follows:-
…
c) Economy wide influences such as unforeseen changes in inflation rate, market interest rates,
taxes and statutory levies;
…
(6) Some illustrative variations or expected variations in the performance of the applicant which
may be attributed by the Commission to controllable factors shall include, but not limited to, the
following:-
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
172 Uttarakhand Electricity Regulatory Commission
…
d) Variations in working capital requirements;
…
h) Variation in operation & maintenance expenses
…
(10) Upon completion of the Annual Performance Review, the Commission shall pass on an order
recording-
a) The approved aggregate gain or loss to the Applicant on account of uncontrollable factors and
the mechanism by which the Applicant shall pass through such gains or losses in accordance with
Regulation 14;
b) The approved aggregate gain or loss to the Applicant on account of controllable factors and the
amount of such gains or such losses that may be shared in accordance with Regulation 15;
c) The approved modifications to the forecast of the Applicant for the ensuing year, if any;
The surplus/deficit determined by the Commission in accordance with these Regulations on
account of truing up of the ARR of the Applicant shall be carried forward to the ensuing financial
year.”
Regulation 14 of the UERC Tariff Regulations, 2011 specifies that:
“14. Sharing of Gains and Losses on account of Uncontrollable factors
(1) The approved aggregate gain or loss to the Applicant on account of uncontrollable factors shall be
passed through as an adjustment in the tariff/charges of the Applicant over such period as may be
specified in the Order of the Commission;
…”
Regulation 15 of the UERC Tariff Regulations, 2011 specifies that:
“15. Sharing of Gains and Losses on account of Controllable factors
(1) The approved aggregate gain to the Applicant on account of controllable factors shall be dealt
with in the following manner:
a) 20% of such gain shall be passed on as a rebate in tariffs over such period as may be
specified in the Order of the Commission;
b) The balance amount of gain may be utilized at the discretion of the Applicant.
4. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on Truing Up for FY 2014-15
Uttarakhand Electricity Regulatory Commission 173
(2) The approved aggregate loss to the Applicant on account of controllable factors shall be dealt
with in the following manner:
a) 25% of the amount of such loss shall be allowed by the Commission to be recovered through
tariffs over such period as may be specified in the Order of the Commission under;
b) The balance amount of loss shall be absorbed by the Applicant.”
Hence, in accordance with UERC Tariff Regulations, 2011, the O&M expenses and
Distribution losses are controllable factors and any gain or loss on account of the controllable factors
is to be dealt in accordance with the provisions of Regulation 15 of the above mentioned
Regulations.
The sharing of gains on account of controllable factors approved by the Commission for FY
2014-15 is as shown in the Table given below:
Table 4.40: Sharing of gains on account of controllable factors approved by the Commission for FY 2014-15 (Rs. Crore)
Particulars Actual Normative as
Trued up Aggregate gain/(loss)
Consumer’s Share
Petitioner’s Share of Gain/(Loss)
A B C=B-A Gain: D=20% x CLoss D=25% x C E=C-D
O&M expenses 371.70 390.90 19.20 3.84 15.36 Distribution Loss 19.06% 15.50% (173.63) (43.41) (130.22) Total (154.43) (39.57) (114.86)
4.5 ARR & Revenue for FY 2014-15
The Commission in its Tariff Order dated April 10, 2014 had approved the Net Revenue
Requirement for FY 2014-15 as Rs. 4124.92 Crore. The Petitioner has now claimed an ARR of Rs.
4340.13 Crore for FY 2014-15. However, based on the various elements of the ARR as discussed
above and approved by the Commission, the summary of final Truing up for FY 2014-15 is given in
the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
174 Uttarakhand Electricity Regulatory Commission
Table 4.41: Summary of true up for FY 2014-15 approved by the Commission (Rs. Crore) S.
No. Particulars Tariff Order Claimed by UPCL Approved
1. Total Power Purchase Cost 3690.88 3911.49 3611.95 2. Interest on Loan 121.82 135.48 108.51 3. Guarantee Fee 4. Depreciation 69.38 105.86 94.19 5. O&M expenses after sharing of gains and losses 404.23 371.70 387.06 6. Interest on Working Capital 6.36 0.00 0.00 7. Return on Equity 40.42 78.17 36.36 8. Provision for Bad and doubtful debts 0.00 37.55 0.00 9. Aggregate Revenue Requirement 4333.09 4640.26 4238.07
10. Less: Non-Tariff Income 70.04 162.00 162.00 11. Gap/(Surplus) of previous year -138.13 -138.13 -138.13 12. Net ARR 4124.92 4340.13 3937.94 13. Revenue
Revenue at Existing Tariff 4145.84 3950.12 3949.83
Revenue from Addl Sales. (after sharing) 130.22 14. Total Revenue 4145.84 3950.12 4080.05 15. Other Adjustment 16. Sharing of Gains and Losses - 22.81 - 17. Adjusted Revenue (Surplus)/Gap -20.92 412.82 -142.11
The Petitioner in its Petition had requested the Commission to approve the gap of Rs. 412.82
Crore. However, the Commission has approved a surplus of Rs. 142.11 Crore for FY 2014-15. The
surplus for FY 2014-15 with carrying cost works out to Rs. 175.10 Crore which has been adjusted by
the Commission in ARR of FY 2016-17.
175 Uttarakhand Electricity Regulatory Commission
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
5.1 Background
This Chapter deals with the determination of the projected ARR of the Petitioner for the
Control Period from FY 2016-17 to FY 2018-19. To determine the ARR of the Petitioner for the
ensuing year FY 2016-17, the Commission has first projected the monthly power purchase
requirement of the Petitioner by estimating the category wise sales based on the past trends and
considering the normative distribution losses. After determining the monthly power purchase
requirement, the Commission has determined the overall power purchase cost by applying monthly
merit order. The Commission has discussed the Sales Projections, Distribution loss trajectory, Power
Purchase Plan and Capital Expenditure in detail in Chapter 3 of this Order while approving the
Business Plan components. The Commission has, thereafter, estimated the other elements of ARR
such as Depreciation, O&M expenses, Interest and Finance Charges, Working Capital requirement
and Return on Equity to project the ARR of the Petitioner for the Control Period from FY 2016-17 to
FY 2018-19. Based on the analysis and scrutiny of Petitioner’s projections in the Petition and
considering the subsequent submissions including actual data for the preceding years, the
Commission has determined the total ARR for first year of the second Control Period, i.e. FY 2016-
17 and ARR excluding Power Purchase Cost for the remaining two years of the Control Period from
FY 2017-18 and FY 2018-19 as detailed in the subsequent Paras of this Chapter.
5.2 Sales
The Commission has already discussed the approach adopted by it for approving the
consumer category wise sales for each year of the second Control Period from FY 2016-17 to FY
2018-19 in detail in Chapter 3 of the Order. The consumer category wise sale approved by the
Commission for the second Control Period from FY 2016-17 to FY 2018-19 is as shown in the Table
below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
176 Uttarakhand Electricity Regulatory Commission
Table 5.1: Consumer Category wise sales approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (MU)
S. No. Category
Petitioner’s Projections Approved FY
2016-17 FY
2017-18 FY
2018-19 FY
2016-17 FY
2017-18 FY
2018-19 1. Domestic 2,566 2,790 3,033 2,801 3,069 3,363 2. Non Domestic 1,185 1,278 1,378 1,257 1,338 1,425 3. Public Lamps 52 55 58 49 52 54 4. Private Tube Wells (PTW) 338 366 396 319 341 365
5. Government Irrigation System (GIS) 124 131 137 123 129 136
6. Public Water Works (PWW) 349 367 386 362 380 399 7. Industrial Consumers
LT Industries 326 339 353 345 360 376
HT Industries 5,694 5,979 6,278 5,701 5,936 6,180
Total 6,020 6,318 6,631 6,047 6,296 6,557 8. Mixed Load 213 223 232 214 225 237 9. Railway Traction 16 17 18 17 19 20 GRAND TOTAL 10,864 11,544 12,269 11,188 11,849 12,555
The Commission would like to once again highlight that the Petitioner has projected the
restricted sales for the second Control Period from FY 2016-17 to FY 2018-19. The Commission as
discussed in Chapter 3 of the Order has projected unrestricted sales for the second Control Period.
5.3 Distribution Loss Trajectory
The Commission has approved the Distribution Loss Trajectory for the second Control
Period from FY 2016-17 to FY 2018-19 as discussed in Chapter 3 of the Order. The distribution loss
trajectory approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-
19 is as shown in the Table given below:
Table 5.2: Distribution Loss Trajectory approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19
Particulars FY 2016-17 FY 2017-18 FY 2018-19 Proposed Approved Proposed Approved Proposed Approved
Distribution Losses 17.29% 15.00% 16.79% 14.75% 16.29% 14.50%
In line with the approach adopted by the Commission in its previous Tariff Orders, the
Commission has considered the entire distribution loss reduction target for each year of the Control
Period as reduction in commercial losses of the Petitioner and has, therefore, considered the impact
of distribution loss reduction in terms of increase in sales due to efficiency improvement.
Accordingly, the estimated energy requirement at distribution periphery, State periphery
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 177
and approved loss level for the second Control Period from FY 2016-17 to FY 2018-19 are given in
the Table below:
Table 5.3: Energy Input requirement approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19
Particulars FY 2016-17 FY 2017-18 FY 2018-19 Distribution Sales (MU) 11,188 11,849 12,555 Loss level for Energy Input (MU) 15.00% 15.00% 14.75% Energy Input required at T-D interface (MU) 13,162 13,940 14,771 Commercial Loss reduction (%) 0.00% 0.25% 0.25% Commercial Loss reduction (Additional sales due to efficiency improvement) (MU) 0.00% 34.85 36.93
Total sales with efficiency improvement (MU) 11,188 11,884 12,592 Overall Distribution Loss (%) 15.00% 14.75% 14.50% PTCUL Loss (%) 1.78% 1.78% 1.78% Energy Input at State periphery (MU)* 13,401 14,193 14,994
* In addition to the energy requirement to meet the demand for FY 2016-17, the Commission has also considered 907.52 MU which UPCL has to return under the Banking Arrangement as discussed Chapter 3.
5.4 Aggregate Revenue Requirement
Regulation 69 of the UERC Tariff Regulations, 2015 specifies as follows:
“69. Aggregate Revenue Requirement for each Financial Year of the Control Period
(1) The total annual expenses and return on equity of the Distribution Licensee for each financial year
of the Control Period shall be worked out on the basis of expenses and return allowed in terms of these
Regulations.
(2) The retail supply tariff of a Distribution Licensee for each financial year of the Control Period shall
provide for recovery of Aggregate Revenue Requirement of the Distribution Licensee for each financial
year of the Control Period, as reduced by the amount of non-tariff income, income from wheeling in
respect of open access customers, income from Other Business and receipts on account of cross-
subsidy surcharge and additional surcharge for the relevant financial year, as approved by the
Commission, and subsidy from the State Government for the financial year, if any, and shall comprise
the following:
(a) Cost of power purchase;
(b) Transmission charges;
(c) System Operation Charges i.e. Fee and Charges paid to NLDC/RLDC/SLDC
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
178 Uttarakhand Electricity Regulatory Commission
(d) Interest and Finance charges on Loan Capital and on consumer security deposit;
(e) Depreciation, including and amortisation of intangible assets;
(f) Lease Charges
(g) Operation and Maintenance expenses;
(h) Interest on working capital; and
(i) Return on equity capital;
(j) Income-tax;
(k) Provision for Bad and doubtful debts
(3) Net Revenue Requirement from sale of electricity = Aggregate Revenue Requirement, as above,
minus:
(a) Non-Tariff Income;
(b) Income from wheeling charges recovered from open access customers;
(c) Income from Other Business, to the extent specified in these Regulations;
(d) Receipts from cross-subsidy surcharge from open access consumers; and
(e) Receipts from additional surcharge on charges of wheeling from open access consumers.
(f) Any revenue subsidy or grant received from the State Government other than the subsidy
under Section 65 of Electricity Act, 2003.”
The Commission in this Order has determined the Net Revenue Requirement for the first
year of the Control Period, i.e. FY 2016-17 and Net Revenue Requirement excluding Power Purchase
Cost for the remaining two years of the Control Period, i.e. FY 2017-18 and FY 2018-19 as detailed in
the subsequent Paras of this Chapter.
5.5 Power Purchase Cost
The power requirement of UPCL is met from various sources which includes the generating
stations of:
• State Generating Stations of UJVN Ltd.
• NTPC Ltd.
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 179
• NHPC Ltd.
• NPCIL
• SJVN Ltd.
• THDC Ltd.
• Independent Power Producers (IPPs)
• Deficit in power purchases met through Banking arrangements, open market
purchases etc.
The Commission has approved the power procurement plan from various sources for each
year of the second Control Period from FY 2016-17 to FY 2018-19 in Chapter 3 of the Order. As
discussed in Chapter 3, the Commission is only projecting the power purchase cost for the first year
of the Control Period, i.e. FY 2016-17 and for reasons mentioned in Chapter 3, the Commission finds
no relevance in approving the power purchase cost for FY 2017-18 and FY 2018-19.
5.5.1 Merit Order
In line with the approach adopted by the Commission in the previous Tariff Orders for the
Petitioner, the Commission has projected the power purchase cost for FY 2016-17 by applying the
monthly merit order principle. The Commission is of the view that this approach would help the
Petitioner to plan its monthly power requirement accurately. However, the energy to be procured
from generating stations which are must run generating stations need to be excluded from the merit
order. The Commission, however, recognizes that the actual off take from a generating station and
associated costs for the Petitioner might be different from that determined in the merit order above.
The Commission would, accordingly, review these differences at the time of carrying out the truing
up for FY 2016-17 in future years, subject to prudence check.
5.5.2 Cost of power purchase
The Petitioner submitted that the cost of power purchase has been projected based on the
following assumptions.
For the procurement of power from 10 LHPs of UJVN Ltd., the Petitioner submitted that the
approved Tariff for FY 2015-16 has been escalated by 5% each year for projecting the cost of power
purchase from UJVN Ltd. for each year of the second Control Period from FY 2016-17 to FY 2018-19.
The Petitioner submitted that the cost of power purchase from NTPC, NHPC, NPCIL, SJVNL and
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
180 Uttarakhand Electricity Regulatory Commission
THDC stations has been projected by escalating the actual power purchase cost for FY 2015-16
(based on the bills raised by the respective generating companies) for each year of the second
Control Period from FY 2016-17 to FY 2018-19. The Petitioner submitted that the cost of power
purchase from IPPs has been considered as per the tariff determined by the Commission. The
Petitioner submitted that the cost of power purchase from Sasan UMPP has been considered as per
the bid tariff.
The Petitioner submitted that the cost of free power has been calculated in line with the
methodology specified by the Commission. It also submitted that for upcoming thermal and large
hydro stations, the tariff of Rs. 5/kWh has been considered. The Petitioner submitted that the cost
of power purchase from short term sources has been considered based on the actual cost of short
term power purchase in FY 2015-16 with annual escalation of 5% for each year of the Control
Period.
The Petitioner has projected the average power purchase cost of Rs. 2.80/kWh, Rs.
3.00/kWh and Rs. 3.18/kWh for FY 2016-17, for FY 2017-18 and FY 2018-19 respectively.
The Commission has estimated the cost of power purchase from various sources as detailed
below:
Table 5.4: Approach of the Commission in estimating the Cost of Power Purchase Source Approach of the Commission in estimating the cost of power purchase
UJVN Ltd.
The Commission has considered the approved Tariff of UJVN Ltd. (10 LHPs) for FY 2016-17. As per the GoU Notification No. 1632/I(2)/2009-04(3)/22/2008 dated October 26, 2009 read with Notification No. 2837/I-2004-05-13/2003 dated June 20, 2005 and Notification No. (6604/03)/567/IX-3-Urja/Power Fund/03, the Cess for the purpose of PDF is leviable if the energy rate (tariff) is less than Rs. 0.80/kWh for more than 10 years old stations at the time of notification. The Commission has not considered the cess imposed by GoU for the purpose of Power Development Fund as the approved Energy rate (tariff) is more than Rs. 0.80/kWh for all the 9 LHPs. Further, as the approved tariff for all the stations is more than Rs. 0.80/kWh, the Commission has also not considered the royalty of 10 paise/kWh towards royalty to the State Govt. based on notification no. 1993/I/2005-01(3)/1/03 dated 25.4.2005. For SHPs, the Commission has considered the applicable Tariff for those generating stations as specified in the Renewable Energy Regulations.
NHPC Ltd., THDC Ltd., SJVN Ltd.
For the generating stations for which the Tariff Order for FY 2016-17 has been issued by the Central Electricity Regulatory Commission, the approved Tariff for FY 2016-17 has been considered.
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 181
Table 5.4: Approach of the Commission in estimating the Cost of Power Purchase Source Approach of the Commission in estimating the cost of power purchase
For other stations, the latest approved Tariff has been considered with annual escalation of 3%.
NTPC Ltd.
As the Tariff Orders for FY 2016-17 are yet to be issued, the latest approved AFC has been considered with annual escalation of 3% till FY 2016-17. For estimating the Energy Charges for FY 2016-17, the weighted average of actual Energy Charges for the months of October 2015 to December 2015 has been considered with an escalation of 3%.
NPCIL The tariff for NPCIL stations has been considered based on the actual billing during FY 2015-16 and escalated by 3% for FY 2016-17.
Renewable energy sources
The applicable tariffs for the respective generating stations within the State have been considered as per the Tariff Orders issued by the Commission in accordance with the Renewable Energy Regulations and the Tariff specified in the Renewable Energy Regulations.
Sasan UMPP The applicable tariff for FY 2016-17 as per the PPA has been considered. Kashipur CCPP
The tariff has been considered as Rs. 4.70/kWh as provisionally approved by the Commission.
Greenko Budhil Hydro
The provisional ex-bus Tariff of Rs. 4/kWh has been considered as approved by the Commission.
Additional purchase for fulfilling RPO
The Tariff for the additional purchase for fulfilling the Non-Solar RPO has been considered as Rs. 4.75/kWh in line with the Commission’s approach in the previous Tariff Orders
Upcoming Stations
For upcoming renewable generating stations within the State, the applicable Tariff as per the Renewable Energy Regulations has been considered. For the solar generating capacity of 30 MW expected to be commissioned by April 2016, the tariff of Rs. 7.50/kWh has been considered and for the solar generating capacity of 180 MW expected to be commissioned by November, 2016, the tariff of Rs. 5.99/kWh has been considered.
Deficit purchase
The tariff for deficit purchase has been considered as Rs. 3.64/kWh as proposed by UPCL.
Cost of free power
The cost of free power has been computed in line with the methodology adopted by the Commission in its previous Tariff Orders as shown below:
Particulars Quantum Total Cost Average Cost
MU Rs. Crore Rs./kWh UJVN Ltd. (9 LHPs) 2972.04 264.78 0.89 Maneri Bhali II 971.05 201.98 2.08 NHPC 582.99 199.65 3.42 Tehri 101.25 62.03 6.13 Koteshwar 62.91 26.39 4.20 Nathpa Jhakri HEP 45.66 14.47 3.17 Average 4735.90 769.31 1.62
The summary of estimated power purchase cost for FY 2016-17 is as shown in the Table
given below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
182 Uttarakhand Electricity Regulatory Commission
Table 5.5: Summary of power purchase cost for FY 2016-17
Station
Claimed Approved PP at State
periphery
Total Cost
Average Rate
PP at State
periphery
Total Cost
Average Rate
MU Rs. Crore Rs./kWh MU Rs. Crore Rs./kWh UJVN Ltd. UJVN Ltd. (9 LHPs) 2955.02 320.64 1.09 2972.04 264.78 0.89 Maneri Bali II 950.66 185.46 1.95 971.05 201.98 2.08 Small Hydro 134.69 22.95 1.70 170.06 18.76 1.10 Total UJVN Ltd. 4040.37 529.05 1.31 4113.15 485.52 1.18 NHPC Salal 38.37 3.83 1.00 40.04 4.77 1.19 Tanakpur 12.30 3.63 2.95 16.17 4.94 3.05 Chamera I 80.05 14.75 1.84 86.37 15.29 1.77 Chamera II 18.61 5.46 2.93 17.75 5.32 3.00 Chamera III 49.54 23.67 4.78 50.05 21.71 4.34 Uri 99.78 16.13 1.62 101.18 17.09 1.69 Dhauliganga 43.39 15.57 3.59 48.51 16.43 3.39 Dulhasti 105.06 66.23 6.30 105.46 60.65 5.75 Sewa II 26.19 12.23 4.67 28.80 12.61 4.38 Uri II 55.10 20.59 3.74 56.27 24.54 4.36 Parbati III 34.82 23.56 6.77 32.38 16.30 5.03 Free Power-Tanakpur 39.94 7.64 1.91 53.48 8.69 1.62 Free Power-Dhauliganga 106.76 20.41 1.91 114.03 18.52 1.62 Total NHPC 709.91 233.70 3.29 750.51 226.86 3.02 THDC Tehri HEP 110.84 71.84 6.48 101.25 62.03 6.13 Free Power-Tehri HEP 388.62 74.30 1.91 358.93 58.30 1.62 Koteshwar HEP 50.55 22.80 4.51 62.91 26.39 4.20 Free Power-Koteshwar HEP 147.96 28.29 1.91 139.03 22.58 1.62 Total THDC 697.97 197.23 2.83 662.11 169.32 2.56 NTPC Singrauli STPS 782.02 165.80 2.12 720.76 145.39 2.02 Rihand STPS Rihand I 304.60 90.25 2.96 256.73 77.08 3.00 Rihand II 294.38 89.17 3.03 232.47 68.37 2.94 Rihand III 275.98 96.92 3.51 267.23 73.90 2.77 Unchahar TPS Unchahar I 266.52 113.85 4.27 230.18 88.59 3.85 Unchahar II 133.86 55.73 4.16 107.91 41.62 3.86 Unchahar III 105.31 49.21 4.67 87.86 39.05 4.44 Anta CCPP 76.56 39.15 5.11 73.95 35.79 4.84 Auraiya CCPP 72.37 44.78 6.19 71.66 41.34 5.77 Dadri CCPP 99.62 56.02 5.62 109.24 52.06 4.77
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 183
Table 5.5: Summary of power purchase cost for FY 2016-17
Station
Claimed Approved PP at State
periphery
Total Cost
Average Rate
PP at State
periphery
Total Cost
Average Rate
MU Rs. Crore Rs./kWh MU Rs. Crore Rs./kWh Dadri (NCTPP) 38.20 21.56 5.64 47.02 25.15 5.35 Jhajjar 5.63 11.81 20.98 28.56 17.63 6.17 Kahalgaon TPS 184.48 71.58 3.88 170.17 72.62 4.27 Koldam 197.66 87.16 4.41 198.94 87.23 4.38 Total NTPC 2837.19 992.99 3.50 2602.69 865.82 3.33 NPCIL Narora APP 109.70 29.12 2.65 120.39 30.47 2.53 Rajasthan APP 146.29 55.99 3.83 145.56 53.18 3.65 Total NPCIL 255.99 85.11 3.32 265.95 83.65 3.15 SJVNL Nathpa Jhakri HEP 49.30 15.08 3.06 45.66 14.47 3.17 Rampur HPS 185.25 63.60 3.43 175.89 70.36 4.00 Total SJVNL 234.55 78.68 3.35 221.55 84.83 3.83 Other Renewable 511.76 244.90 4.79 511.76 254.03 4.96 Free Power-Vishnu Prayag 196.27 37.52 1.91 195.93 31.83 1.62 Sasan UMPP 552.02 72.81 1.32 685.39 94.58 1.38 Kashipur CCPP 0.00 0.00 0.00 776.80 365.10 4.70 Greenko Budhil Hydro 0.00 0.00 0.00 232.98 97.07 4.17 Additional Purchase for fulfilling RPO 161.89 416.24 197.71 4.75 Upcoming Stations 332.10 159.65 4.81 202.33 119.74 5.92 Deficit Purchase 3305.27 1201.79 3.64 2670.72 971.07 3.64 Total 13673.41 3996.08 2.92 14308.12 4047.13 2.83
The Commission, further, directs the Petitioner to seek prior approval of the Commission,
in case the variation in power purchase quantum or total power purchase cost in any quarter
exceeds by more than 5% of the approved power purchase quantum and cost for the respective
quarter worked out on pro-rata basis from the total approved quantum and cost for FY 2016-17 as
indicated in the Table below, failing which, the Commission may disallow power purchases so
made while Truing up the ARR for FY 2016-17.
Table 5.6: Quarterly Power Purchase approved by the Commission for FY 2016-17
Quarter Power Purchase Quantum (MU)
Power Purchase Cost (Rs. Crore)
April – June 3224.26 818.35 July – September 4376.55 1060.41 October – December 3313.05 1067.93 January – March 3394.25 1100.43 Total 14308.12 4047.13
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
184 Uttarakhand Electricity Regulatory Commission
Moreover, it has been observed that the Petitioner has been continuously resorting to short
term power purchase without adopting a transparent process and also does not seek approval of
the Commission. In this regard, Third proviso of Regulation 73(1) of UERC Tariff Regulations, 2015
is reproduced hereunder:
“Provided that the power procurement plan submitted by the Distribution Licensee may include long-
term, medium-term and short-term power procurement sources of power, in accordance with these
Regulations. However, the distribution licensee should as far as possible, not plan for short-
term purchases except for conditions specified in Regulations 75 and should endeavor to
meet its requirement from long term and medium term power procurement and make a plan
accordingly.”
(Emphasis added)
Regulation 75 specifies the circumstances under which short term power procurement may
be made by the distribution licensee without seeking prior approval of the Commission. However,
Regulation 75(5) specifies as under:
“(5) Within fifteen (15) days from the date of entering into an agreement or arrangement for short-
term power procurement for which prior approval is not required, the Distribution Licensee shall
provide the Commission, full details of such agreement or arrangement, including quantum, tariff
calculations, duration, supplier details, method for supplier selection and such other details as the
Commission may require with regard to such agreement/arrangement to assess that the conditions
specified in this Regulation have been complied with:”
While projecting the power purchase requirement of the Petitioner for each year of the
second Control Period, it has been observed that the Petitioner is having deficit in almost every
month. Accordingly, the Petitioner is directed to prepare its power purchase plan for the next
three years and initiate the bidding process to meet the deficit, if any. The Petitioner is directed
to submit an action plan in this regard within 15 days of the date of Order. The Petitioner is also
directed to ensure compliance of the Regulations issued by the Commission from time to time,
failing which any consequent liability would be to the account of the Petitioner.
The base Energy Charges of thermal stations (base fuel cost) for the purpose of computation
of FCA is given in the Table below:
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 185
Table 5.7: Energy Charges of thermal generating stations for FY 2016-17
Generating Station Energy Charges (Rs./kWh)
Singrauli STPS 1.352 Rihand STPS Rihand I 1.856 Rihand II 1.652 Rihand III 1.542 Unchahar TPS Unchahar I 2.667 Unchahar II 2.643 Unchahar III 2.642 Anta CCPP 3.155 Auraiya CCPP 3.810 Dadri CCPP 3.351 Dadri (NCTPP) 3.453 Jhajjar 3.730 Kahalgaon TPS 2.595
5.6 Transmission Charges
5.6.1 Inter-State Transmission Charges payable to PGCIL
The Petitioner submitted that during the first six months of FY 2015-16, it has received bills
of Rs. 174.72 Crore towards Inter-State Transmission Charges. By assuming the same amount for the
remaining six months, the per MU PGCIL charge for FY 2015-16 has been calculated using the
estimated charges and energy coming from outside the State during FY 2015-16. The per MU rate
calculated has been escalated by 4% per annum and then multiplied by the projected power
purchase quantum for each year of the second Control Period from FY 2016-17 to FY 2018-19. The
Petitioner has proposed the Inter-State Transmission Charges of Rs. 385.26 Crore, Rs. 441.27 Crore,
and Rs. 497.57 Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively. The Commisison at
this stage has considered the PGCIL charges for FY 2016-17 as claimed by UPCL which shall be
subject to true up based on actual expenses incurred.
As the Commission has not approved the power purchase cost for FY 2017-18 and FY 2018-
19, the Commission in this Order has not considered the inter-State Transmission Charges for FY
2017-18 and FY 2018-19. The Commission will carry out the Truing up of transmission charges
based on actual transmission charges paid to PGCIL during the year.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
186 Uttarakhand Electricity Regulatory Commission
5.6.2 Intra-State Transmission Charges payable to PTCUL
The Petitioner submitted that the Intra-State Transmission Charges for FY 2016-17 have been
projected by escalating the approved Annual Transmission Charges for PTCUL for FY 2015-16 by
applying an annual escalation of 4% for each year of the second Control Period from FY 2016-17 to
FY 2018-19.
The Commission has approved the Annual Transmission Charges for PTCUL of Rs. 261.04
Crore for FY 2016-17 vide its Order dated April 5, 2016. Hence, the Commission has considered the
same in the approval of ARR for FY 2016-17 for the Petitioner.
5.6.3 Transmission Charges
The Transmission Charges claimed by the Petitioner and approved by the Commission for
FY 2016-17 is as shown in the Table given below:
Table 5.8: Transmission Charges for FY 2016-17 (Rs. Crore) Particulars Claimed by UPCL Approved
Inter-State Transmission Charges 385.26 385.26 Intra-State Transmission Charges 307.11 261.04 Total 692.37 646.30
5.7 SLDC Charges
The Petitioner has not claimed any SLDC charges.
The Commission has approved the SLDC Charges of Rs. 10.08 Crore for FY 2016-17 vide its
Order dated April 5, 2016. Hence, the Commission has included the same in the ARR for FY 2016-17
for the Petitioner.
5.8 Water Tax
The Petitioner in the submissions made subsequent to the filing of the MYT Petition
submitted that the Uttarakhand Water Tax on Electricity Generation Act, 2012 came into force w.e.f.
August 15, 2015. As per the provisions of the stated Act, Water Tax is payable on the electricity
generated in Uttarakhand. The tax is applicable on the electricity generation from the generating
stations of UJVN Ltd., NHPC Ltd. and THDC located in the State. The Petitioner requested the
Commission to consider the impact of Water Tax in determination of ARR for the Petitioner.
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 187
Section 17 of The Uttarakhand Water Tax on Electricity Generation Act, 2012 specifies as
follows:
“17. (1) The user shall be liable to pay the Water Tax under the Act at such rates as the Government
may by notification fix in this behalf.
(2) The State Government may review, increase, decrease or vary the rates of the Water Tax fixed
under this section from time to time in the manner it deems fit.”
The State Government vide the notification dated November 7, 2015 notified the applicable
rates of Water Tax.
The Commission has computed the likely impact of Water Tax for the Petitioner for FY 2016-
17 as Rs. 153.82 Crore. The Commission has considered the same in the approval of ARR for FY
2016-17 for the Petitioner. The same shall be trued up based on the actual amount paid by the
Petitioner for FY 2016-17 without considering the variation of the same as efficiency gain or loss.
The Commission directs the Petitioner to submit all the relevant information along with the
supporting documents for substantiating the actual expenses incurred on account of Water Tax,
for FY 2016-17 along with its proposals for True up for FY 2016-17.
5.9 GFA and Additional Capitalisation
5.9.1 GFA base for FY 2015-16
The Commission vide its Order dated April 11, 2015 on approval of ARR for the Petitioner
had approved the capitalisation of Rs. 355.77 Crore for FY 2015-16. As against the same, the
Petitioner has proposed the capitalisation of Rs. 467.82 Crore for FY 2015-16. Further, in reply to the
Commission’s query on the likely achievement of capitalisation considering the actual progress, the
Petitioner has proposed the capitalisation of Rs. 514.44 Crore.
The Commission has considered the scheme wise closing GFA approved for FY 2014-15 as
the opening GFA for FY 2015-16. The Commission, in Chapter 3 of the Order, on approval of
capitalisation plan for the second Control Period from FY 2016-17 to FY 2018-19 has considered the
capitalisation of Rs. 478.03 Crore in FY 2015-16.
Based on the above, the GFA base approved by the Commission for FY 2015-16 is as shown
in the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
188 Uttarakhand Electricity Regulatory Commission
Table 5.9: GFA base approved by the Commission for FY 2015-16 (Rs. Crore)
S. No. Particulars
Approved in the Tariff
Order Claimed by UPCL Approved
1. Opening Value 3553.20 3695.79 3675.32 2. Total addition during the year 355.77 467.82 478.03 3. Less: Deletions during the year 0.00 0.00 0.00 4. Closing value 3908.97 4163.61 4153.35
5.9.2 Capitalisation during the second Control Period
The Commission, in the approval of Business Plan for the second Control Period as
discussed in Chapter 3 of the Order from FY 2016-17 to FY 2018-19 has approved the capitalisation
of Rs. 523.44 Crore in FY 2016-17, Rs. 546.02 Crore in FY 2017-18 and Rs. 557.26 Crore in FY 2018-19.
The Commission has considered the year wise capitalisation for the second Control Period from FY
2016-17 to FY 2018-19 as approved in the Business Plan. The GFA base approved by the
Commission for the second Control Period from FY 2016-17 to FY 2018-19 is as shown in the Table
below:
Table 5.10: GFA base approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2016-17 FY 2017-18 FY 2018-19
Claimed by UPCL Approved Claimed by
UPCL Approved Claimed by UPCL Approved
Opening GFA 4163.61 4153.35 5067.21 4676.79 6090.82 5222.81 GFA addition during the year 903.60 523.44 1023.61 546.02 949.13 557.26
Closing GFA 5067.21 4676.79 6090.82 5222.81 7039.95 5780.07
5.10 Means of Finance
The Commission has approved the funding of the approved capitalisation for FY 2015-16 by
considering the average of the actual funding pattern of the Petitioner’s capitalisation during FY
2012-13 to FY 2014-15 as shown in the Table below:
Table 5.11: Details of financing for capitalisation for FY 2015-16 (Rs. Crore)
Particulars FY 2015-16 Grants etc. Loan Equity Total
Opening Value 1576.51 1597.56 501.25 3675.32 Addition during the year 171.55 270.61 35.86 478.03 Deletions 0.00 0.00 0.00 0.00 Closing Value of GFA 1748.06 1868.17 537.11 4153.35
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 189
The Commission, in the approval of Business Plan for the second Control Period from FY
2016-17 to FY 2018-19 as discussed in Chapter 3 of the Order has approved the Financing Plan of the
approved capitalisation during the second Control Period. The Commission has considered the
Financing Plan for the second Control Period from FY 2016-17 to FY 2018-19 as approved in the
Business Plan. The Financing Plan for FY 2016-17 to FY 2018-19 approved by the Commission is as
shown in the Tables given below:
Table 5.12: Details of financing for capitalisation for FY 2016-17 (Rs. Crore)
Particulars FY 2016-17 Grants etc. Loan Equity Total
Opening Value 1748.06 1868.17 537.11 4153.35 Addition during the year 187.85 296.32 39.27 523.44 Deletions 0.00 0.00 0.00 0.00 Closing Value of GFA 1935.91 2164.49 576.38 4676.79
Table 5.13: Details of financing for capitalisation for FY 2017-18 (Rs. Crore)
Particulars FY 2017-18 Grants etc. Loan Equity Total
Opening Value 1935.91 2164.49 576.38 4676.79 Addition during the year 195.95 309.11 40.96 546.02 Deletions 0.00 0.00 0.00 0.00 Closing Value of GFA 2131.86 2473.60 617.35 5222.81
Table 5.14: Details of financing for capitalisation for FY 2018-19 (Rs. Crore)
Particulars FY 2018-19 Grants etc. Loan Equity Total
Opening Value 2131.86 2473.60 617.35 5222.81 Addition during the year 199.98 315.47 41.81 557.26 Deletions 0.00 0.00 0.00 0.00 Closing Value of GFA 2331.84 2789.07 659.16 5780.07
5.11 Interest and Finance Charges
The Petitioner submitted that the interest expenses have been computed based on the
existing loans and new loans proposed for funding the capital expenditure. For existing loans,
interest has been separately calculated for each loan based on the terms and conditions of such
loans. For new loans, the sources have been considered as PFC and REC. The new loans have been
considered with 3 years moratorium, 10 years repayment period and 11.50% interest rate. The
Petitioner submitted that the interest on GPF loan shall be claimed based on the actual interest
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
190 Uttarakhand Electricity Regulatory Commission
during the truing up for the respective year.
Accordingly, the Petitioner has proposed the interest of Rs. 105.76 Crore, Rs. 133.77 Crore,
and Rs. 164.65 Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively. The Petitioner has
claimed the interest on consumer security deposit of Rs. 52.56 Crore, Rs. 54.14 Crore and Rs. 55.76
Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively. The Petitioner has claimed the
guarantee fee of Rs. 3.40 Crore for each year of the second Control Period from FY 2016-17 to FY
2018-19.
Regulation 27 of the UERC Tariff Regulations, 2015 specifies as follows:
“27. Interest and finance charges on loan capital and on Security Deposit
(1) The loans arrived at in the manner indicated in Regulation 24 shall be considered as gross
normative loan for calculation of interest on loan.
(2) The normative loan outstanding as on 1.4.2016 shall be worked out by deducting the
cumulative repayment as admitted by the Commission up to 31.3.2016 from the gross normative
loan.
(3) The repayment for each year of the Control Period shall be deemed to be equal to the
depreciation allowed for that year…
…
(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the
actual loan portfolio at the beginning of each year applicable to the project:
…
(6) The interest on loan shall be calculated on the normative average loan of the year by applying
the weighted average rate of interest.
…”
The Commission has considered the closing loan balance of Government of Uttarakhand
loans for FY 2014-15 as opening loan balance for FY 2015-16. Thereafter, the Commission has
considered the loan addition during FY 2015-16 as per the approved means of finance for FY 2015-
16. The Commission has considered the depreciation for FY 2015-16 as the normative repayment for
the year. The Commission has considered the closing loan balance for FY 2015-16 as the opening
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 191
loan balance for FY 2016-17. The Commission has considered the loan addition during each year of
the second Control Period from FY 2016-17 to FY 2018-19 as per the approved Financing Plan. The
Commission has considered the normative repayment equivalent to the approved depreciation for
each year of the second Control Period from FY 2016-17 to FY 2018-19. The Commission has
considered the interest rate of 10.41% which is the weighted average rate of interest for FY 2014-15.
The Commission has determined the interest on loan by applying the interest rate of 10.41% on the
amount of average of the opening loan & closing loan excluding the loan additions corresponding
to the assets capitalised during the year for each year of the second Control Period from FY 2016-17
to FY 2018-19. The Commission has not allowed interest on additions during year as the Petitioner
capitalises the assets at the end of the financial year and during the year, whatever interest accrues
on the loan portion corresponding to the capital expenditure, the same is Interest during
construction and is capitalised as CWIP. The interest on loan approved by the Commission for the
second Control Period from FY 2016-17 to FY 2018-19 is as shown in the Table given below:
Table 5.15: Interest on Loan approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2016-17 FY 2017-18 FY 2018-19 Claimed Allowable Claimed Allowable Claimed Allowable
Opening Loan balance 795.98 829.55 1043.35 1000.56 1283.00 1166.86 Drawal during the year 392.96 296.32 415.25 309.11 507.31 315.47 Repayment during the year 145.59 125.32 175.61 142.80 209.88 161.04 Closing Loan balance 1043.35 1000.56 1283.00 1166.86 1580.43 1321.29 Interest Rate 11.50% 10.41% 11.50% 10.41% 11.50% 10.41% Interest 105.76 79.83 133.77 96.73 164.65 113.09
Further, the Commission, for the purpose of approving the ARR for FY 2016-17, has
considered the interest on consumer security deposit and guarantee fee for FY 2016-17 as proposed
by the Petitioner.
5.11.1 Depreciation
The Petitioner submitted that the asset class wise depreciation has been computed
considering the proposed GFA for each year of the second Control Period from FY 2016-17 to FY
2018-19 and the rates of depreciation prescribed in the UERC Tariff Regulations, 2015. Accordingly,
the Petitioner has proposed the depreciation of Rs. 145.59 Crore, Rs. 175.61 Crore, and Rs. 209.88
Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
192 Uttarakhand Electricity Regulatory Commission
Regulation 28 of the UERC Tariff Regulations, 2015 specifies as follows:
“28. Depreciation
(1) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by
the Commission.
Provided that depreciation shall not be allowed on assets funded through Consumer Contribution
and Capital Subsidies/Grants.
(2) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up
to maximum of 90% of the capital cost of the asset.
...
(4) Depreciation shall be calculated annually based on Straight Line Method and at rates specified
in Appendix - II to these Regulations.
…”
The Petitioner has claimed depreciation on the average of opening and closing balances of
the depreciable GFA for the year. However, as observed from the audited accounts till FY 2014-15 of
the Petitioner, the Petitioner follows the practice of capitalising the assets on the last day of the
Financial Year. Nothing has been brought on record by the Petitioner to show that the asset is
capitalised when it is put to use. Hence, the Commission has adopted the similar approach as
adopted by it in the previous Tariff Orders for allowing the depreciation on the opening GFA.
Pro-rata depreciation on assets capitalised during the year would not be admissible in case
the asset is capitalised at the year end. Hence, to validate the same, pre-requisite would be the
capitalisation policy as well as the fixed asset register showing the date of additions made in the
assets during the year. In this regard, the Commission has time and again directed the Petitioner to
take note of the above prerequisite. Further, the Commission in its Order dated April 11, 2015 on
approval of ARR and Retail Tariff for FY 2015-16 directed as under:
“The Commission directs the Petitioner to maintain proper Fixed Asset Register showing
amongst others the date of capitalisation of each asset, their location, alongwith the
accumulated depreciation on the same and submit the same along with the next filing and
also claim depreciation based on the rates as specified in the Regulations for each class of
asset.”
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 193
The Petitioner submitted that it is very difficult to prepare the Fixed Assets Register showing
the date and location of each Asset existing as on November 9, 2001 and created thereafter. The
Petitioner also submitted that the Fixed Assets Register upto FY 2012-13 have been submitted and
that the preparation of Fixed Assets Register for FY 2013-14 and FY 2014-15 is under progress.
In the absence of complete Fixed Asset Register, the Commission at this stage has considered
the weighted average rate of 5.21% computed for FY 2014-15 and has applied the same on the
opening depreciable GFA for each year of the second Control Period from FY 2016-17 to FY 2018-19.
The depreciation approved by the Commission for the second Control Period from FY 2016-
17 to FY 2018-19 is as shown in the Table given below:
Table 5.16: Depreciation approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2016-17 FY 2017-18 FY 2018-19 Claimed Allowable Claimed Allowable Claimed Allowable
Opening GFA - 4153.35 - 4676.79 - 5222.81 Grants - 1748.06 - 1935.91 - 2131.86 Depreciable opening GFA 2439.02 2405.29 2974.02 2740.88 3798.12 3090.95 Net addition during the year 561.37 335.59 593.22 350.07 724.73 357.27 Closing GFA 3080.51 2740.88 3673.73 3090.95 4522.85 3448.22 Depreciation rate 5.21% 5.21% 5.21% 5.21% 5.21% 5.21% Depreciation 145.59 125.32 175.61 142.80 209.88 161.04
5.11.2 Operation and Maintenance expenses
Regarding the Operation and Maintenance expenses, Regulation 84 of the UERC Tariff
Regulations, 2015 specifies as follows:
“84. Operation and Maintenance Expenses
(1) The O&M expenses for the first year of the Control Period will be approved by the Commission
taking into account actual O&M expenses for last five years till Base Year subject to prudence
check and any other factors considered appropriate by the Commission.
(2) The O&M expenses for the nth year and also for the year immediately preceding the Control
Period i.e., FY 2015-16shall be approved based on the formula given below:-
O&Mn = R&Mn + EMPn + A&Gn
Where –
• O&Mn – Operation and Maintenance expense for the nth year;
• EMPn – Employee Costs for the nth year;
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
194 Uttarakhand Electricity Regulatory Commission
• R&Mn – Repair and Maintenance Costs for the nth year;
• A&Gn – Administrative and General Costs for the nth year;
(3) The above components shall be computed in the manner specified below:
EMPn = (EMPn-1) x (1+Gn) x (CPIinflation)
R&Mn = K x (GFAn-1) x (WPIinflation) and
A&Gn = (A&Gn-1) x (WPIinflation) + Provision
Where –
• EMPn-1 – Employee Costs for the (n-1)th year;
• A&Gn-1 – Administrative and General Costs for the (n-1)th year;
Provision: Cost for initiatives or other one-time expenses as proposed by the Distribution
Licensee and approved by the Commission after prudence check.
• “K” is a constant specified by the Commission in %. Value of K for each year of the
control period shall be determined by the Commission in the MYT Tariff order based on
Distribution Licensee’s filing, benchmarking of repair and maintenance expenses,
approved repair and maintenance expenses vis-à-vis GFA approved by the Commission in
past and any other factor considered appropriate by the Commission;
• CPIinflation – is the average increase in the Consumer Price Index (CPI) for
immediately preceding three years;
• WPIinflation – is the average increase in the Wholesale Price Index (CPI) for immediately
preceding three years;
• GFAn-1 - Gross Fixed Asset of the distribution licensee for the n-1th year;
• Gn is a growth factor for the nth year. Value of Gn shall be determined by the
Commission in the MYT tariff order for meeting the additional manpower requirement
based on Distribution Licensee’s filings, benchmarking and any other factor that the
Commission feels appropriate:
Provided that in case of a distribution licensee is governed by Government pay structure, the
Commission may consider allowing a separate provision in Employee expenses towards the
impact of VIIth Pay Commission.
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 195
Provided that repair and maintenance expenses determined shall be utilised towards repair and
maintenance works only.”
The O&M expenses include Employee expenses, R&M expenses and A&G expenses. In
accordance with Regulation 84 of the UERC Tariff Regulations, 2015, the O&M expenses for the
second year of the Control Period shall be determined by the Commission taking into account the
actual O&M expenses of the previous years and any other factors considered appropriate by the
Commission. The submissions of the Petitioner and the Commission’s analysis on the O&M
expenses for the second Control Period from FY 2016-17 to FY 2018-19 is detailed below.
5.11.3 Employee expenses
The Commission had approved the employee expenses of Rs. 329.63 Crore for FY 2015-16 in
its Order dated April 11, 2015 on approval of ARR and Retail Tariff for FY 2015-16. As against the
same, the Petitioner has computed the employee expenses for FY 2015-16 as Rs. 346.39 Crore as per
the UERC Tariff Regulations, 2015 considering the actual employee expenses for FY 2014-15.
The Petitioner submitted that the employee expenses for the second Control Period from FY
2016-17 to FY 2018-19 has been proposed as per the UERC Tariff Regulations, 2015 considering the
actual employee expenses for FY 2014-15. Accordingly, the Petitioner has proposed the employee
expenses of Rs. 386.58 Crore, Rs. 433.08 Crore and Rs. 485.54 Crore for FY 2016-17, FY 2017-18 and
FY 2018-19 respectively.
The Petitioner submitted that employee expenses are likely to increase based on the
recommendations of the Seventh Pay Commission. The Petitioner submitted that the estimated
impact of the recommendations of the Seventh Pay Commission could not be worked out. The
Petitioner requested the Commission to allow increase in employee expenses on account of
recommendations of the Seventh Pay Commission on finalisation of the same and after acceptance
by the State Government.
The Commission has computed the employee expenses in accordance with the UERC Tariff
Regulations, 2015. In accordance with the UERC Tariff Regulations, 2015, the Gn (growth factor) is
to be considered in the computation of employee expenses. The Commission, in the approval of the
Business Plan for the second Control Period from FY 2016-17 to FY 2018-19 as discussed in Chapter
3 of the Order has approved the HR Plan. Based on the approved HR Plan, the Commission has
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
196 Uttarakhand Electricity Regulatory Commission
computed the Gn factor as shown in the Table below:
Table 5.17: Gn approved by the Commission Particulars FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Closing no. of employees 3456 3415 3843 3967 4097 Gn - 0.00% 12.53% 3.23% 3.28%
In accordance with UERC Tariff Regulations, 2015, CPI inflation which is the average
increase in the Consumer Price Index (CPI) for the preceding three years is to be considered. The
Commission has calculated the annual growth in the values of CPI (overall) based on the average of
preceding three full years for FY 2014-15 as 9.50% and for FY 2015-16 and for each year of the
Control Period FY 2016-17 to FY 2018-19 as 8.80%.
The Commission has averaged the actual gross employee expenses for FY 2012-13 to FY
2014-15 to arrive at the gross employee expenses for the median year FY 2013-14. Thereafter, the
gross employee expenses, thus, arrived for FY 2013-14 has been escalated by the CPI inflation of
9.50% to arrive at EMPn-1 for FY 2015-16. Further, the Commission has considered the capitalisation
rate of employee expenses as 14.04% which is the average capitalisation rate of employee expenses
for FY 2012-13 to FY 2014-15.
The Government of India, vide Notification No. 1/1/2013-E.III(A) of 28.02.2014 appointed
the Seventh Central Pay Commission with specified Terms of Reference. The Seventh Central Pay
Commission submitted its report to the Government of India on November 19, 2015. In light of the
recommendations of the Seventh Central Pay Commission and the provisions of the UERC Tariff
Regulations, 2015 UPCL being governed by the Government pay structure, the Commission has
considered the impact of Seventh Pay Commission to the tune of 20% of the approved net employee
expenses. The Commission shall consider the actual impact of Seventh Pay Commission during
each year of the second Control Period in Truing up exercise without considering the efficiency
gain/loss on account of the same. The normative employee expenses approved by the Commission
for FY 2015-16 and for the second Control Period from FY 2016-17 to FY 2018-19 is as shown in the
Table below:
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 197
Table 5.18: Employee expenses approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Approved Claimed by UPCL Approved Claimed
by UPCL Approved Claimed by UPCL Approved
EMPn-1 - 402.98 345.19 449.74 422.64 503.84 474.68 Gn - 2.58% 12.53% 2.97% 3.23% 3.04% 3.28% CPIinflation - 8.80% 8.80% 8.80% 8.80% 8.80% 8.80% EMPn = (EMPn-1) x (1+Gn) x (1+CPIinflation) - 449.74 422.64 503.84 474.68 564.86 533.38
Capitalisation rate - 14.04% 14.04% 14.04% 14.04% 14.04% 14.04% Less: Employee expenses capitalised - 63.16 59.35 70.76 66.66 79.33 74.91
Net Employee expenses - 386.58 363.29 433.08 408.02 485.54 458.48 Impact of Seventh Pay Commission - - 72.66 - 81.60 - 91.70
Total Employee expenses 329.63 386.58 435.95 433.08 489.62 485.54 550.17
The overall employee expenses approved by the Commission for the second Control Period
of FY 2016-17 to FY 2018-19 is higher than as claimed by UPCL mainly due to impact of Seventh Pay
Commission considered by the Commission, which shall be subject to true up based on actuals.
5.11.4 R&M expenses
The Commission had approved the R&M expenses of Rs. 134.39 Crore for FY 2015-16 in its
Tariff Order dated April 11, 2015 on approval of ARR and Retail Tariff for FY 2015-16. The
Petitioner has proposed the R&M expenses for FY 2015-16 as Rs. 134.39 Crore, the same as approved
by the Commission in its Order dated April 11, 2015.
The Petitioner submitted that the R&M expenses for the second Control Period from FY
2016-17 to FY 2018-19 has been proposed as per the UERC Tariff Regulations, 2015. Accordingly, the
Petitioner has proposed the R&M expenses of Rs. 129.25 Crore, Rs. 165.34 Crore and Rs. 208.89
Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively.
The Commission has determined the R&M expenses for the second Control Period from FY
2016-17 to FY 2018-19 in accordance with UERC Tariff Regulations, 2015. The Commission has
computed the percentage of actual R&M expenses upon actual opening GFA for each year of FY
2012-13 to FY 2014-15. Thereafter, the Commission has considered the average of such percentages
as K factor which works out to 2.67% for FY 2015-16 and for each year of the Control Period FY
2016-17 to FY 2018-19. Since Regulation 84(3) reproduced above specifies that “K” is a constant in %,
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
198 Uttarakhand Electricity Regulatory Commission
accordingly, for FY 2016-17, the value of ‘K’ will remain 2.67% against the Petitioner’s claim of
escalating it also by the WPI w.e.f. 2013-14 onwards.
The Commission has considered the WPI inflation based on the average of preceding three
full years for FY 2015-16 and for each year of the Control Period FY 2016-17 to FY 2018-19 as 5.11%.
The Commission has considered the opening GFA for FY 2015-16 and for each year of the second
Control Period from FY 2016-17 to FY 2018-19.
The R&M expenses approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 is as shown in the Table below:
Table 5.19: R&M expenses approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Approved Claimed by UPCL Approved Claimed
by UPCL Approved Claimed by UPCL Approved
K - 2.95% 2.67% 3.10% 2.67% 3.26% 2.67% GFAn-1 - 4163.61 4153.35 5067.22 4676.79 6090.83 5222.81 WPIinflation - 5.11% 5.11% 5.11% 5.11% 5.11% 5.11% R&Mn = K x (GFAn-1) x (1+WPIinflation) 134.39 129.25 116.74 165.34 131.45 208.89 146.80
5.11.5 A&G expenses
The Commission has approved the A&G expenses of Rs. 27.50 Crore for FY 2015-16 in its
Order dated April 11, 2015 on approval of ARR and Retail Tariff for FY 2015-16. The Petitioner has
computed the A&G expenses for FY 2015-16 as Rs. 22.52 Crore as per UERC Tariff Regulations,
2015.
The Petitioner submitted that the A&G expenses for the second Control Period from FY
2016-17 to FY 2018-19 has been proposed as per the UERC Tariff Regulations, 2015. Accordingly, the
Petitioner has proposed the A&G expenses of Rs. 26.67 Crore, Rs. 27.88 Crore and Rs. 29.15 Crore
for FY 2016-17, FY 2017-18 and FY 2018-19 respectively.
The Commission has averaged the actual gross A&G expenses for FY 2012-13 to FY 2014-15
to arrive at the gross A&G expenses for the median year FY 2013-14. Thereafter, the gross A&G
expenses, thus, arrived at for FY 2013-14 has been escalated by the WPI inflation of 7.42% to arrive
at A&Gn-1 for FY 2014-15. For FY 2015-16 and for each year of the second Control Period from FY
2016-17 to FY 2018-19, the WPI inflation has been considered as 5.11%. Further, the Commission has
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 199
considered the capitalisation rate of A&G expenses as 26.68% which is the average capitalisation
rate of A&G expenses for FY 2012-13 to FY 2014-15.
The Regulations provide for Provision in A&G expenses towards cost for initiatives or other
one-time expenses. The Petitioner has proposed Rs. 3.00 Crore against the same, towards data
centre cost. In this regard, the Commission during the first Control Period, i.e. FY 2013-14 to FY
2015-16 had allowed UPCL Rs. 3.48 Crore each for FY 2013-14 and FY 2014-15 and Rs. 4.61 Crore for
FY 2015-16 towards the provision for data centre and call centres costs against which UPCL has
incurred Rs. 0.56 Crore in FY 2013-14 and Rs. 0.75 Crore in FY 2014-15. The expenses incurred in this
regard are significantly lower than the provision allowed to the Petitioner by the Commission.
Moreover, these expenses are already included in the A&G expenses of FY 2013-14 and FY 2014-15.
As already discussed above, the Commission while approving the A&G expenses for the second
Control Period has averaged the gross A&G expenses for FY 2012-13 to FY 2014-15 and escalated for
subsequent years. Accordingly, these expenses have already been factored in the average expenses
considered by the Commission and hence, the Commission finds no reason to allow such provision
again. However, in case the actual expenditure incurred during the second Control Period exceeds
the amount approved by the Commission, the same shall be Trued up based on the actual without
any sharing of gains or losses.
The normative A&G expenses approved by the Commission for the second Control Period
from FY 2016-17 to FY 2018-19 is as shown in the Table below:
Table 5.20: A&G expenses approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19
Approved Claimed by UPCL Approved Claimed
by UPCL Approved Claimed by UPCL Approved
A&Gn-1 - 30.62 28.60 32.18 30.07 33.83 31.60 WPIinflation - 5.11% 5.11% 5.11% 5.11% 5.11% 5.11% Gross A&G expenses - 32.18 30.07 33.83 31.60 35.56 33.22 Capitalisation rate - 26.45% 26.68% 26.45% 26.68% 26.45% 26.68% Less: A&G expenses capitalised - 8.51 8.02 8.95 8.43 9.40 8.86
Net A&G expenses - 23.67 22.05 24.88 23.17 26.15 24.36 Provision - 3.00 0.00 3.00 0.00 3.00 0.00 A&Gn = A&Gn-1 x (1+WPIinflation) + Provision
27.50 26.67 22.05 27.88 23.17 29.15 24.36
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
200 Uttarakhand Electricity Regulatory Commission
5.11.6 O&M expenses
The O&M expenses approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 is as shown in the Table below:
Table 5.21: O&M expenses approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2016-17 FY 2017-18 FY 2018-19
Claimed by UPCL Approved Claimed by
UPCL Approved Claimed by UPCL Approved
Employee expenses 386.58 435.95 433.08 489.62 485.54 550.17 R&M expenses 129.25 116.74 165.34 131.45 208.89 146.80 A&G expenses 26.67 22.05 27.88 23.17 29.15 24.36 Total O&M expenses 542.50 574.73 626.30 644.25 723.59 721.33
5.11.7 Interest on Working Capital
The Petitioner has submitted that the interest on working capital for the second Control
Period from FY 2016-17 to FY 2018-19 has been proposed in accordance with UERC Tariff
Regulations, 2015. Accordingly, the Petitioner has proposed the IWC of Rs. 33.11 Crore, Rs. 36.01
Crore and Rs. 42.78 Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively.
Regulation 33(2) of the UERC Tariff Regulations, 2015 specifies as follows:
“(2) Distribution
a) The Distribution Licensee shall be allowed interest on the estimated level of working capital
for the financial year, computed as follows:
(i) Operation and maintenance expenses for one month;
(ii) Maintenance spares @ 15% of operation and maintenance expenses; plus
(iii) Two months equivalent of the expected revenue from sale of electricity at
prevailing tariffs;
(iv) Capital required to finance such shortfall in collection of current dues as may be
allowed by the Commission; minus
(v) Amount held as security deposits under clause (a) and clause (b) of sub-section
(1) of Section 47 of the Act from consumers and Distribution System Users; minus
(vi) One month equivalent of cost of power purchased, based on the annual power
procurement plan.”
The Commission has determined the interest on working capital for the second Control
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 201
Period in accordance with the UERC Tariff Regulations, 2015.
The Commission has computed the interest on working capital in accordance with UERC
Tariff Regulations, 2015. Since the Commission has not approved the power purchase cost for FY
2017-18 and FY 2018-19, the Commission has determined the interest on working capital for FY
2016-17 only in this Order.
5.11.8 One Month O&M Expenses
The annual O&M expenses approved by the Commission are Rs. 574.73 Crore for FY 2016-
17. Based on the approved O&M expenses, one month’s O&M expenses work out to Rs. 47.89 Crore
for FY 2016-17.
5.11.9 Maintenance Spares
The Commission has considered the maintenance spares as 15% of annual O&M expenses in
accordance with UERC Tariff Regulations, 2015, which works out to Rs. 86.21 Crore for FY 2016-17.
5.11.10Receivables
The Commission has approved the receivables for two months equivalent to the expected
revenue from the sale of electricity at the net revenue requirement of Rs. 5,252.87 Crore for FY 2016-
17, which works out to Rs. 875.48 Crore for FY 2016-17.
5.11.11Capital required to finance shortfall in collection of current dues
The Petitioner has claimed Rs. 144.70 Crore towards the capital required to finance the
shortfall in collection of current dues and the same is as shown in the Table given below:
Table 5.22: Capital required to finance the shortfall in collection of current dues as claimed by the Petitioner
Particulars Legend FY 2016-17 Annual Revenue (Rs. Crore) A 5565.44 Collection efficiency approved for FY 2015-16 B 98.5% Collection efficiency proposed C 97.4% Difference D=100%-C 2.6% Short fall in current dues (Rs. Crore) DxA 144.70
The Working capital specified in the Regulations is on normative basis. Further, as referred
above almost 75% of the revenues is from Industries, Govt. categories and other bulk supply
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
202 Uttarakhand Electricity Regulatory Commission
consumers having load above 25 kW and, hence, in no way the payment from them can be beyond
the period specified in the norms. Further, even UPCL recognizes DPS in its accounts on cash basis,
i.e. when it is collected from the consumers. UPCL is required to devise a system wherein
collections from the consumers are received by it within a period of 2 months. The Commission did
not prevent UPCL from collecting its dues from the consumers or writing off the bad debts.
The Commission has approved the collection efficiency of 98.50% for FY 2016-17 while
approving the Business Plan of UPCL for the second Control Period of FY 2016-17 to FY 2018-19. In
accordance with the provisions of the UERC Tariff Regulations, 2015 the Commission has approved
the capital required to finance shortfall in collection of current dues as shown in the Table given
below:
Table 5.23: Capital required to finance the shortfall in collection of current dues approved by the Commission
Particulars Legend FY 2016-17 Net Revenue Requirement (Rs. Crore) A 5252.87 Collection efficiency approved B 98.5% Difference C=100%-B 1.5% Short fall in current dues (Rs. Crore) CxA 78.79
5.11.12Adjustment for security deposits and credit by power suppliers
The Petitioner has proposed the amount held as security deposit as Rs. 584.02 Crore and one
month of power purchase cost as Rs. 390.70 Crore totalling to Rs. 974.72 Crore for FY 2016-17.
Considering the same amount of security deposit as proposed by the Petitioner and estimating one
month of power purchase cost as Rs. 337.26 Crore, the Commission has approved the total amount
of Rs. 921.28 Crore for FY 2016-17 as the amount held as security deposits and credit by power
suppliers.
Based on the above, the total working capital requirement of the Petitioner for FY 2016-17,
works out to Rs. 167.10 Crore. The Commission has considered the rate of interest on working
capital as 14.05% equal to State Bank Advance Rate (SBAR) of State Bank of India as on the date of
filing of the MYT Petition and, accordingly, the interest on working capital works out to Rs. 23.48
Crore for FY 2016-17. The interest on working capital for FY 2016-17 approved by the Commission
is as shown in the Table below:
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 203
Table 5.24: Interest on working capital approved by the Commission for FY 2016-17 (Rs. Crore)
Particulars Claimed by UPCL Approved O&M expenses for 1 month 45.21 47.89 Maintenance Spares 81.38 86.21 2 months of expected revenue at prevailing tariffs 927.57 875.48 Capital required to finance shortfall in collection of current dues 144.70 78.79
Minus: Amount held as security deposits and credit by power suppliers 974.72 921.28
Net Working Capital 224.14 167.10 Rate of Interest on Working Capital 14.05% 14.05% Interest on Working Capital 33.11 23.48
5.11.13Return on Equity
The Petitioner has considered the opening Equity for FY 2016-17 as Rs. 634.75 Crore. The
Petitioner has considered the equity addition during each year of the second Control Period from
FY 2016-17 to FY 2018-19 as per the proposed financing plan for the respective year. The Petitioner
has proposed the Return on Equity at the rate of 16.50% on the average equity for the year.
Accordingly, the Petitioner has proposed the Return on Equity of Rs. 118.63 Crore, Rs. 147.20 Crore,
and Rs. 179.82 Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively.
Regarding the Return on Equity, Regulation 26 of the UERC Tariff Regulations, 2015
specifies as follows:
“26. Return on Equity
(1) Return on equity shall be computed on the equity base determined in accordance with Regulation
24.
Provided that, Return on Equity shall be allowed on account of allowed equity capital for the assets
put to use at the commencement of each financial year.
(2) Return on equity shall be computed on at the base rate of 15.50% for thermal generating stations,
transmission licensee, SLDC and run of river hydro generating station and at the base rate of 16.50%
for the storage type hydro generating stations and run of river generating station with pondage and
distribution licensee on a post-tax basis.”
In accordance with the UERC Tariff Regulations, 2015, Return on Equity is allowable on the
opening equity for the year. Hence, the Commission has determined the Return on Equity for each
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
204 Uttarakhand Electricity Regulatory Commission
year of the second Control Period from FY 2016-17 to FY 2018-19 considering the eligible opening
equity for return purposes for the respective year.
The Commission has considered the closing eligible equity for return purposes approved for
FY 2014-15 as the opening balance for FY 2015-16. Thereafter, the Commission has considered the
equity addition during FY 2015-16 as per the approved means of finance for FY 2015-16. The
Commission has considered the closing balance for FY 2015-16 as the opening balance for FY 2016-
17.
The Return on Equity approved by the Commission for the second Control Period from FY
2016-17 to FY 2018-19 is as shown in the Table below:
Table 5.25: Return on Equity approved by the Commission for the second Control Period from FY 2016-17 to FY 2018-19 (Rs. Crore)
Particulars FY 2016-17 FY 2017-18 FY 2018-19
Claimed by UPCL Approved Claimed by
UPCL Approved Claimed by UPCL Approved
Opening Equity 634.75 285.58 803.16 324.85 981.12 365.82 Addition during the year 168.41 39.27 177.97 40.96 217.42 41.81
Closing Equity 803.16 324.85 981.12 365.82 1198.54 407.63 Rate of Return 16.50% 16.50% 16.50% 16.50% 16.50% 16.50% Return on Equity 118.63 47.12 147.20 53.60 179.82 60.36
5.11.14Income Tax
The Petitioner has not claimed any Income Tax in its ARR proposals for the second Control
Period from FY 2016-17 to FY 2018-19.
Regulation 34 of the UERC Tariff Regulations, 2015 specifies as follows:
“34. Tax on Income
Income Tax, if any, on the income stream of the regulated business of Generating Companies,
Transmission Licensees, Distribution Licensees and SLDC shall be reimbursed to the Generating
Companies, Transmission Licensees, Distribution Licensees and SLDC shall be reimbursed to the
Generating Companies, Transmission Licensees, Distribution Licensees and SLDC as per actual
income tax paid, based on the documentary evidence submitted at the time of truing up of each year of
the Control Period, subject to prudence check.”
As stated above, Income Tax is admissible at the time of Truing up and hence, the
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 205
Commission has not considered any Income Tax in the approval of ARR for the second Control
Period from FY 2016-17 to FY 2018-19.
5.11.15Provision for Bad and doubtful debts
The Petitioner submitted that the actual collection efficiency for FY 2014-15 is 95.90%
towards the current dues. Although all efforts would be made to achieve 99% collection efficiency,
achievement of the same from the current level of 95.90% in a span of one year is not possible. The
Petitioner submitted that the provision for bad debts has been considered as per the UERC Tariff
Regulations, 2015. The Petitioner further requested the Commission to consider bad debts at the rate
of ‘100% minus collection efficiency’ of the estimated revenue. Accordingly, the Petitioner has
proposed the provision for bad debts as Rs. 55.65 Crore, Rs. 61.90 Crore, and Rs. 69.73 Crore for FY
2016-17, FY 2017-18 and FY 2018-19 respectively.
Regulation 31 of the UERC Tariff Regulations, 2015 specifies as follows:
“31. Bad and doubtful debts
(1) The Commission may allow a provision for bad and doubtful debts upto one percent (1%) of
the estimated annual revenue of the distribution licensee, subject to actual writing off bad debts
by it in the previous years.
Provided further that where the total amount of such provisioning allowed in previous years for
bad and doubtful debts exceeds five (5) per cent of the receivables at the beginning of the year, no
such appropriation shall be allowed which would have the effect of increasing the provisioning
beyond the said maximum.”
The Commission sought justification from the Petitioner for proposing the provision for bad
and doubtful debts when the present provision already exceeds 5% of the amount of receivables. In
its reply, the Petitioner submitted that the provision for bad debts has been proposed as per the
provisions of UERC Tariff Regulations, 2015.
The Petitioner further submitted that as per the directions of the Audit Committee given in
its 28th meeting, the draft Write Off Policy was sent to the Institute of Chartered Accountants of
India on March 27, 2015 for examination by them in view of all the Accounting and Auditing
Standards, Legal Provisions and Practices followed in other companies. In reply, the Institute
informed that the issue raised cannot be considered in view of Rule 3 of the Advisory Service Rules
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
206 Uttarakhand Electricity Regulatory Commission
of the Committee.
As discussed in Chapter 4 of the Order, the Petitioner has chosen to ignore the provisions of
Rs. 230 Crore inherited by it from UPPCL against the opening debtors of Rs. 619 Crore. The Transfer
Scheme agreed by the two Corporation dates back to the year 2001. It cannot be ruled out that out of
Rs. 619 Crore inherited by UPCL, some amount may be bad and doubtful by now which has to be
written off the Petitioner by the total amount of provisions available with it.
The Commission in its Order dated April 10, 2014 on approval of ARR and Retail Tariff for
FY 2014-15 stated as under:
“7.1.23 Bad & Doubtful Debts
...
The Commission has taken note of the reply submitted by the Petitioner in this regard. UPCL
initiated the audit work as late as one and a half year when the direction was first issued and since
then the Petitioner has been extending its timelines for completion and submission of the audit
report...”
The Commission in the previous Tariff Order had directed the Petitioner to carry out an
audit of receivables and also identify and classify the same, however, till date the Petitioner has not
complied with the directions of the Commission. Hence, the Commission has not considered the
provision for bad and doubtful debts in the approval of ARR for FY 2016-17 in accordance with the
UERC Tariff Regulations, 2015.
5.11.16Non-Tariff Income
The Petitioner has proposed non-tariff income of Rs. 178.60 Crore, Rs. 187.54 Crore and Rs.
196.91 Crore for FY 2016-17, FY 2017-18 and FY 2018-19 respectively. In absence of any yardstick for
estimating the non-tariff income of the Petitioner, the Commission provisionally accepts the same
for the second Control Period. The same shall, however, be Trued up based on the actual audited
accounts for the year.
5.11.17Past year adjustments
As discussed in Chapter 4, the Petitioner has not considered the material cost variance for
FY 2014-15 as Non-Tariff Income in its proposal for True up. In reply to the Commission’s query
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 207
regarding the same, the Petitioner submitted that some of it relates to the R&M expenses and some
pertains to capital expenditure. The Petitioner further submitted the year wise details of material
cost variance. The Petitioner submitted that the credit balance as on November 9, 2001 is Rs. 5.67
Crore. With yearly additions till FY 2014-15, the total credit balance as on March 31, 2015 is Rs.
198.86 Crore. The Petitioner submitted that the break-up of material cost variance pertaining to
R&M expenses and capital expenditure is not available. The Petitioner also submitted that the
material cost variance pertains to grants as well. The material cost variance pertaining to grants may
be excluded and the remaining may be treated as Non-Tariff Income. The Petitioner submitted that
the material cost variation pertaining to grants may be considered as Rs. 81.16 Crore. Hence, the
balance material cost variance is Rs. 117.71 Crore (198.86 minus 81.16). The Petitioner requested the
Commission to spread this amount as Non-Tariff Income for 10 years.
The Commission has worked out the material cost variance pertaining to grants portion in
the same proportion of material cost variation pertaining to grants in overall material cost variance
as submitted by the Petitioner. The Commission has considered the net material cost variance after
excluding the grants portion as the Non-Tariff Income for each year from FY 2001-02 to FY 2014-15.
The year wise material cost variance to be treated as Non-Tariff Income considered by the
Commission is as shown below:
Table 5.26: Material Cost Variance considered as Non-Tariff Income (Rs. Crore)
Year Material cost variance considered as Non-Tariff Income
FY 2001-02 5.63 FY 2002-03 3.43 FY 2003-04 11.44 FY 2004-05 6.85 FY 2005-06 3.08 FY 2006-07 1.23 FY 2007-08 19.31 FY 2008-09 1.52 FY 2009-10 1.48 FY 2010-11 1.50 FY 2011-12 1.33 FY 2012-13 31.86 FY 2013-14 17.15 FY 2014-15 11.86 Total 117.70
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
208 Uttarakhand Electricity Regulatory Commission
Further, the Commission in its Order dated April 11, 2015 on approval of True up for FY
2013-14 ruled as under:
“3.2.3 Power Purchase Expenses (Including Transmission Charges)
…
The Commission further observed that the Petitioner in its audited accounts for FY 2013-14 has
written back prior period power purchase liabilities amounting to Rs. 261.45 Crore and has also
booked prior period expenses of Rs. 17.33 Crore. The Commission has asked the Petitioner to submit
the information regarding details of Prior Period Income in the Annual Accounts for carrying out the
true up for the respective year alongwith the reasons which resulted in excess booking for each
financial year separately. The Petitioner in its reply submitted the bifurcation of such expenses,
however, the Petitioner did not submit the year wise excess provisioning done and sought more time
to submit the same. To take correct and proper view on adjustments to be made to power purchase
costs already allowed in earlier year, the complete year wise details of liabilities written back is
essentially required. It is also observed that unpaid liability towards power purchase is shown as Rs.
1097 Crore in the annual accounts of UPCL which relates to power purchase dues of CGS, UJVN
Ltd., etc. This unpaid liability has come down as compared to that in preceding year by the amount
which has been written off. It would, therefore, also be necessary to verify the bonafide of this liability.
As the basic information could not be made available by the Petitioner, the Commission at present is
not taking final view in the matter. The Commission directs the Petitioner to submit the year
wise details of excess liabilities written off under the head of power purchase as also the
complete details and documentary evidence of unpaid liabilities mentioned in the accounts
of FY 2013-14 to the Commission in the format already sent to it within one month from the
date of issue of this Order. The Commission will take appropriate view in the matter in the Tariff
Order for FY 2016-17.”
In its reply, the Petitioner submitted the information sought by the Commission. The
Commission has considered the prior period adjustments on account of power purchase expenses
and other prior period income from FY 2007-08 to FY 2013-14 as shown in the Table given below:
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 209
Table 5.27: Prior Period Income (Rs. Crore)
Year Prior period income on account of Power Purchase
Other prior period income
Total prior period income
FY 2007-08 238.24 - 238.24 FY 2008-09 4.12 1.95 6.07 FY 2009-10 7.89 3.12 11.01 FY 2010-11 72.30 3.34 75.65 FY 2011-12 -53.05 3.10 -49.95 FY 2012-13 -6.61 -28.67 -35.28 FY 2013-14 -1.45 - -1.45 Total 261.45 -17.16 244.29
Considering the year wise material cost variance and prior period income the Commission
has worked out the total amount of Rs. 522.91 Crore till FY 2015-16 to be returned by the Petitioner
to the consumers. While computing the same, the Commission has not considered the carrying cost
on the balance till FY 2007-08, as the Commission had not allowed the carrying cost for the
Petitioner while carrying out the Truing up till FY 2007-08. The past year adjustments worked out
by the Commission is as shown in the Table given below:
Table 5.28: Past year adjustments approved by the Commission (Rs. Crore) Particulars FY
2008-09 FY
2009-10 FY
2010-11 FY
2011-12 FY
2012-13 FY
2013-14 FY
2014-15 FY
2015-16 Opening Balance 289.23 332.72 345.21 422.36 373.74 370.32 386.02 455.70 Addition during the year 7.59 12.49 77.15 -48.61 -3.42 15.70 11.86 - Closing Balance 296.82 345.21 422.36 373.74 370.32 386.02 397.88 455.70 Average Balance 293.03 338.96 383.78 398.05 372.03 378.17 391.95 455.70 Carrying Cost 35.90 41.52 45.09 51.75 54.87 54.65 57.81 67.22 Carry forward to next year 332.72 386.73 467.45 425.49 425.20 440.67 455.70 522.91
5.11.18Treatment of past year adjustments
As discussed in the preceding Para, the Commission has approved the past year adjustments
of Rs. 522.91 Crore to be returned by the Petitioner. The treatment of the past year adjustments is
discussed hereunder.
As discussed in Chapter 4, the Commission has carried out the truing up of capital related
expenses from FY 2007-08 to FY 2012-13 and had approved the amount of Rs. 156.87 Crore as the
amount due to the Petitioner. As the amount due to the Petitioner on account of True up of capital
related expenses also relate to the past years, the Commission has adjusted the same with the
corresponding amount to be returned by the Petitioner from the past year adjustments. The balance
remaining amount of Rs. 366.04 Crore shall be adjusted from the ARR for the Petitioner during the 3
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
210 Uttarakhand Electricity Regulatory Commission
years of the second Control Period from FY 2016-17 to FY 2018-19. The treatment of past year
adjustments approved by the Commission are as shown in the Table given below:
Table 5.29: Treatment of past year adjustments approved by the Commission (Rs. Crore)
Particulars Legend Amount (Rs. Crore)
Past year adjustments A -522.91 Past year adjustments set off against the entitlement of the Petitioner on account of true up of capital related expenses from FY 2007-08 to FY 2012-13
B +156.87
Balance past year adjustments C = A+B -366.04 Total past year adjustments considered in FY 2016-17 E=C÷3 -122.01 Past year adjustments to be considered in the ARR for FY 2017-18 F= C÷3 -122.01 Past year adjustments to be considered in the ARR for FY 2018-19 G= C÷3 -122.01
The remaining amount of Rs. 244.03 Crore would be adjusted by the Commission from the
ARR of subsequent year alongwith the carrying cost.
5.11.19Revenue Requirement for FY 2016-17
Based on the above, the Revenue Requirement approved by the Commission for FY 2016-17
is as shown in the Table below:
Table 5.30: Revenue Requirement approved by the Commission for FY 2016-17 (Rs. Crore)
S. No. Particulars Claimed by UPCL Approved 1. Power Purchase Cost 3996.08 4047.13 2. Impact of True-up of UJVN Ltd. - -35.19 3. Transmission Charges
PGCIL 385.26 385.26
PTCUL 307.11 261.04 4. SLDC Charges 10.08 5. Water Tax - 153.82 6. Interest on Loan 105.76 79.83 7. Interest on Consumer Security Deposit 52.56 52.56 8. Guarantee Fee 3.40 3.40 9. Depreciation 145.59 125.32
10. O&M expenses 542.50 574.73 11. Interest on Working Capital 31.49 23.48 12. Return on Equity 118.63 47.12 13. Provision for Bad and doubtful debts 55.65 0.00 14. Aggregate Revenue Requirement 5744.04 5728.58 15. Less: Non-Tariff Income 178.60 178.60 16. Add: True up impact of FY 2014-15 544.39 -175.10 18. Past year adjustments - -122.01 19. Net Revenue Requirement 6109.83 5252.87
5. Petitioner’s Submissions, Commission’s Analysis, Scrutiny and Conclusion on MYT Period for second Control Period
Uttarakhand Electricity Regulatory Commission 211
5.11.20Revenue at Existing Tariff
The Petitioner has forecasted the revenue of Rs. 4889.57 Crore for FY 2016-17 at the
approved Tariff for FY 2015-16.
By applying the approved Tariff for FY 2015-16 the Commission has estimated the total
consumer category wise revenue for FY 2016-17 as Rs. 5003.31 Crore.
The revenue at existing Tariff as proposed by the Petitioner and estimated by the
Commission is shown in the Table given below:
Table 5.31: Revenue for FY 2016-17 at existing Tariff (Rs. Crore) S.
No. Consumer Category
Proposed by the Petitioner Estimated by the Commission Sales (MU)
Revenue (Rs. Crore)
Average Billing Rate (Rs./kWh)
Sales (MU)
Revenue (Rs. Crore)
Average Billing Rate (Rs./kWh)
1 RTS-1: Domestic 2566.19 776.77 3.03 2800.54 925.32 3.30
2 RTS-2: Non-Domestic 1185.31 614.49 5.18 1256.82 648.96 5.16
3 RTS-3: Public Lamps 52.27 23.32 4.46 49.23 21.99 4.47
4 RTS-4: Private Tube Wells 338.49 47.44 1.40 318.57 44.65 1.40
5
RTS-5: Government Irrigation Systems
124.35 57.00 4.58 123.18 56.50 4.59
6 RTS-6: Public Water Works 349.47 160.54 4.59 361.63 165.54 4.58
7 RTS-7: Industry LT Industry 325.76 168.10 5.16 345.05 167.82 4.86 HT Industry 5693.88 2941.71 5.17 5701.46 2841.59 4.98
8 RTS-8: Mixed Load 212.52 92.16 4.34 213.80 92.94 4.35
9 RTS-9: Railway Traction 16.19 8.05 4.98 17.47 7.99 4.58
Incremental Revenue from MCG
- - - - 30.00 -
Total 10864.42 4889.57 4.50 11187.75 5003.31
5.11.21Revenue Gap for FY 2016-17 at existing Tariff
Based on the net revenue requirement of Rs. 6109.83 Crore (including the proposed True up
amount for FY 2014-15) and revenue at existing Tariff of Rs. 4889.57 Crore, the Petitioner has
proposed the revenue gap of Rs. 1220.26 Crore to be recovered by way of proposed Tariff for FY
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
212 Uttarakhand Electricity Regulatory Commission
2016-17.
Considering the net revenue requirement of Rs. 5252.87 Crore and revenue at existing Tariff
of Rs. 5003.31 Crore, the Commission has approved the revenue gap of Rs. 249.56 Crore for FY 2016-
17. The Commission has approved the Retail Tariff for FY 2016-17 to cover the approved revenue
gap of Rs. 249.56 Crore.
The revenue gap for FY 2016-17 proposed by the Petitioner and approved by the
Commission is as shown in the Table given below:
Table 5.32: Revenue Gap for FY 2016-17 (Rs. Crore) Particulars Proposed by the Petitioner Approved
Net Revenue Requirement 6109.83 5252.87 Revenue at existing Tariff 4889.57 5003.31 Revenue Gap 1220.26 249.56
213 Uttarakhand Electricity Regulatory Commission
6. Tariff Rationalisation, Tariff Design and Related Issues
6.1 Discontinuation of Additional Surcharge on account of Re-Determination of
Tariff for FY 2010-11 from FY 2016-17 onwards
Hon’ble Appellate Tribunal of Electricity in its Judgment dated February 27, 2013 issued in
Appeal No. 152 of 2011 filed by M/s. Kumaon Garhwal Chamber of Commerce and Industry on the
issue of cross subsidy and re-determination of tariff for FY 2010-11 had directed the Commission to
re-determine the tariff for FY 2010-11 while truing up the expenses in accordance with the ratio
decided by the Hon’ble Tribunal in the Judgment dated 31.01.2011. The Commission had re-
determined the Tariff for FY 2010-11, in its Order dated May 06, 2013 alongwith the MYT and Tariff
Petition for FY 2013-14. The Commission in its Order dated May 06, 2013 re-determined the tariffs
for FY 2010-11 for the cross-subsidised categories, namely, Lifeline & Snowbound, Domestic,
Private Tube Wells, Government Irrigation System, Public Lamps and Public Water Works. The
Commission also determined a total amount of Rs. 18.06 Crore recoverable on the account of re-
determined tariffs from the above mentioned cross-subsidised categories for FY 2010-11. As regards
the recovery towards revised tariffs during FY 2010-11 from these consumer categories, the
Commission in its Order dated May 06, 2013 opined that the recovery of entire amount in one single
year would result into significant increase in retail tariffs of some of the category of consumers and
hence, the Commission allowed the deferred recovery of additional surcharge from these consumer
categories in three years in the proportion of 20%, 40% and 40% in year 1, 2 and 3 respectively,
beginning from FY 2013-14 instead of allowing recovery in a single year. Further, as the amount of
rebate to be allowed to subsidizing categories (LT-Industrial and HT-Industrial) as per re-
determined tariffs for FY 2010-11 was to be met out of additional revenue for recovery of additional
surcharge from subsidized categories based on the re-determined tariffs, the Commission allowed
rebate to subsidising categories in three years in the proportion of 20% during FY 2013-14, 40%
during FY 2014-15 and 40% during FY 2015-16. As the entire amount towards re-determined tariff
from subsidized categories has been recovered till FY 2015-16 and corresponding rebate has been
passed on to subsidizing categories, additional surcharge on account of re-determiantion of tariff for
FY 2010-11 shall not be applicable from FY 2016-17 onwards.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
214 Uttarakhand Electricity Regulatory Commission
6.2 Tariff Rationalisation and Tariff Design for FY 2016-17
6.2.1 General
In Chapter 5 of the Order, it has been concluded that the revenue projected to be earned by
UPCL during FY 2016-17 at currently prevailing tariffs will be Rs. 5003.31 Crore. Against this, the
ARR approved by the Commission for FY 2016-17 including gap and surplus on account of truing
up of previous years works out to Rs. 5252.87 Crore, leaving a total gap of Rs. 249.56 Crore. In view
of the objections received and the Petitioner’s submission, the Commission considers it appropriate
to first take a view in this Chapter on the tariff rationalisation measures suggested by the Petitioner
and the concerns voiced by other stakeholders.
6.2.2 Petitioner’s Proposals
The Petitioner submitted that the tariff proposal has been formulated by the Petitioner with
an attempt to keep the impact on the consumers to the minimum possible and at the same time not
defer a large portion of the recovery of the tariff in the coming years. The Petitioner also submitted
that Section 61(g) of the Electricity Act, 2003 states that the Appropriate Commission shall be
guided by the objective that the tariff progressively reflects the efficient and prudent cost of supply
of electricity.
Some of the key alterations proposed by the Petitioner in the retail tariffs for FY 2016-17 are
as follows:
6.2.2.1 Domestic Tariff for consumption on electricity operated water pumps by rural groups under
Uttarakhand Rural Water Supply and Sanitation Project (URWSSP)
The Petitioner submitted that Government of Uttarakhand (GoU) had directed it to submit
tariff proposal for charging domestic tariff for the consumption towards electricity operated water
pumps by rural groups under Uttarakhand Rural Water Supply and Sanitation Project (URWSSP)
Scheme of the GoU which is being charged under RTS-6 (Public water works). The Petitioner
requested the Commission for considering the same.
6.2.2.2 Abolition of MCG from RTS-4(Private Tube Wells)
The Petitioner submitted that it had received several representations from various farmer
groups for abolishing Minimum Consumption Guarantee (MCG) from RTS-4 (Private Tube Well)
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 215
category on the ground that they are not able to consume even the minimum consumption specified
in the Tariff Schedule on account of various reasons like availability of water, higher ground water
level, etc. The Petitioner proposed that MCG may be abolished for RTS-4, if the Government of
Uttarakhand subsidises the same.
6.2.2.3 Revision of Terms and Conditions applicable on Seasonal Industries
The Petitioner proposed to revise the terms and conditions applicable for Seasonal Industries
to bring more clarity and avoid any dispute and has proposed to add the following two new
conditions:
• Any existing consumer, desirous of availing seasonal benefit for any Financial Year,
shall submit his application in the concerned distribution division clearly specifying
the period of operation latest by 15th day of March of previous year.
• Any prospective consumer, desirous of seasonal benefit, shall specifically declare his
seasonal period for the Financial Year at the time of submission of application /
execution of agreement clearly mentioning the period of operation.
6.2.2.4 Rebate for availing supply at higher voltage
The Petitioner submitted that rebate for taking supply at higher voltage was revised by the
Commission in its Tariff Order dated 10th April 2014 from 1.5% and 5% to 2.5% and 7.5% for taking
supply at 33 kV and 132 kV and above respectively. The Petitioner further submitted that voltage
rebate approved by the Commission is very high and was done without hearing the Petitioner’s
view point. The Petitioner further submitted the details of higher voltage rebate applicable in some
other States.
The Petitioner requested the Commission to revise the rebate for availing supply at higher
voltage from the current levels of 2.5% and 7.5% to 1.5% and 5% for availing supply at 33 kV and
132 kV respectively. The Petitioner submitted that the increase of volatage rebate in the Tariff Order
for FY 2014-15 resulted in huge revenue loss.
6.2.2.5 Prepaid metering
The Petitioner submitted the Tariff proposal for prepaid metering. The Petitioner submitted
the key alterations from prepaid guiding principles approved by the Commission in the Tariff
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
216 Uttarakhand Electricity Regulatory Commission
Order for FY 2012-13, relaxations in General Conditions of supply and new provisions proposed in
the prepaid retail tariff for FY 2016-17, and the same are as follows:
a) The Petitioner proposed to limit the prepaid option upto 25 kW under LT category.
b) The Petitioner submitted that as per the guiding principles there shall be a minimum
recharge of Rs. 100 and the maximum limit of recharge shall be Rs. 5000 for single
phase connection and Rs. 15000 for three phase connections. Considering the
operational issues, the maximum limit of recharge is proposed as Rs. 10000
irrespective of single phase or three phase connection. The Petitioner submitted that
it shall generate recharge of any amount in cases of testing of meter, adjustment of
arrear or otherwise and any other reason it deems fit. The time extension recharge for
balance amount after 3 months shall also be allowed.
c) The Petitioner submitted all the future prepaid tariffs shall be made applicable from
at least 30 days ahead of the release of the Tariff Order providing sufficient time for
developing the tariff codes so that no retrospective adjustments would be required.
d) The Petitioner submitted that as per the guiding principles and Section 47(5) of the
Electricity Act, 2003, it shall not charge any security deposit as is required in post
paid connections but price equivalent to the material cost shall be charged as
material security which shall be returned at the time of permanent disconnection.
The proposed material security deposit for FY 2016-17 is Rs. 6000.00 (Rs. 4300.00 for
prepaid meter + Rs. 700 for display unit (keypad) + Rs. 1000 for meter box) and
similarly for three phase prepaid meter is Rs. 12000.00 (Rs. 10300.00 for prepaid
meter + Rs. 700 for display unit (keypad) + Rs. 1000 for meter box).
e) The Petitioner proposed a deviation from the guiding principles and requested the
Commission to restrict the transfer of postpaid connection to prepaid connection in
case consumer has any pending arrear liability.
f) The Petitioner proposed that consumer may be allowed only one transfer from
postpaid to prepaid or otherwise in a financial year.
g) The Petitioner proposed to provide friendly credit hours and days on non-working
hours and on all holidays for which the credit charges shall be adjusted from
subsequent recharge.
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 217
h) The Petitioner proposed a fixed solar rebate of 80% of the rate proposed in postpaid
connections irrespective of the actual bill. The Petitioner proposed that the additional
credit of due solar rebate would be done with the issuance of immediately next
recharge.
i) The Petitioner proposed that no excess load/demand penalty shall be levied on the
consumer.
j) The Petitioner proposed that there shall be no annual adjustment of Minimum
Consumption Guarantee in case of prepaid metering. The Petitioner proposed to
reduce the MCG to 80% of the units proposed in prepaid mechanism.
k) The Petitioner proposed the mandatory prepaid metering for the following:
i. Domestic consumers who have contracted load upto 2 kW and some
premises of Consumer is used for Non Domestic purpose;
ii. Non Domestic consumers who have contracted load upto 4 kW and
consumption upto 50 units per month;
iii. Non Domestic Independent Advertisement Hoarding;
iv. Non Domestic mobile towers.
l) In contrast to the postpaid scheme for Domestic Consumers other than Life Line
Consumers wherein the Contracted load is upto 2 kW and some premises of the
Consumer is used for Non Domestic purpose, with the increase in consumption over
200 units all the previous 200 units are also required to be billed at commercial rates,
the Petitioner proposed that in prepaid scheme the rates of first 200 units shall not be
altered and shall remain same irrespective of consumption over or below 200 units.
m) In contrast to the postpaid scheme for Small Non Domestic Consumers with
connected load upto 4 kW and consumption upto 50 units per month, with the
increase in consumption over 50 units all the previous 50 units are also required to be
billed at higher commercial rates, the Petitioner proposed that in prepaid scheme the
rates of first 50 units shall not be altered and shall remain same irrespective of
consumption over or below 50 units.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
218 Uttarakhand Electricity Regulatory Commission
6.2.3 Commission’s Views on Tariff Rationalisation Measures
The Commission believes that tariff rationalisation is a dynamic and ongoing process and is
essential to accommodate the socio-economic and technological changes taking place in the system
over a period of time.
The following Sections discuss the tariff rationalisation measures suggested by the
Petitioner, Respondents, and the Commission’s view on the same.
6.2.3.1 Domestic Tariff for consumption on electricity operated water pumps by rural groups under
Uttarakhand Rural Water Supply and Sanitation Project (URWSSP)
As discussed earlier, the Petitioner has proposed levying the domestic tariff on electricity
operated water pumps by rural groups under URWSSP. As per the existing Tariff Schedule, Tariff
of RTS-1: Domestic is applicable for residential premises/purposes and places of worship only. The
usage of electricity by these electricity operated water pumps by rural groups under URWSSP by no
means qualify under consumption for residential purposes or places of worship. Hence, the
Commission does not find any appropriate reason to accept the proposal of the Petitioner in this
regard. However, in case the Government of Uttarkhand provides subsidy, then UPCL can charge
the tariff lower than the approved tariff.
6.2.3.2 Fixed Charges, Minimum charges and Minimum Consumption Guarantee
It is a well-accepted economic principle that the fixed costs of the Utility should be
recovered to a certain extent through fixed charges to ensure revenue stability. At the same time, the
Commission recognises that if the entire fixed cost is recovered through fixed charges, then the
utility shall have no incentive to bother about sales and, hence, quality of supply may suffer.
Historically, the fixed recovery has been done through a mix of minimum charges and fixed
charges. Levy of Minimum Consumption Guarantee Charges (MCG) is a way of ensuring minimum
revenue to the utility from the consumers, however, if the consumption exceeds the specified units,
then no MCG charges are levied on the consumers and entire charges recovered by the utility are
through energy/fixed charges.
The fixed charge component reflecting the fixed cost of providing the service to the
consumer and the energy charge component reflecting the cost of energy actually consumed should
ideally be taken in the two-part tariff structure.
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 219
Section 45(3) of the Electricity Act, 2003 also provides for levy of fixed charges. The relevant
Section is reproduced below:
“The charges for electricity supplied by a distribution licensee may include:
(b) a fixed charge in addition to the charge for the actual electricity supplied;
...”
Further, the licensee is incurring fixed cost directly attributable to individual consumers
such as meter reading, bill preparation, bill distribution and collection, which should ideally be
allocated to and recovered from each consumer. One of the guiding factors mentioned in Section 61
of the Electricity Act, 2003 for specifying terms and conditions of tariffs is that the tariff has to be
gradually cost reflective. Considering that levy of higher fixed charges should not impact the
consumers adversely, the Commission, in its Tariff Order dated March 18, 2008, introduced a
nominal fixed charge for all the categories as a progression towards designing a two part tariff
structure linked to cost structure. Further, in its subsequent Tariff Orders for FY 2009-10 to FY 2015-
16, considering the level of proportion of fixed costs, as percentage of total costs of UPCL and level
of revenue recovery from fixed charges, the Commission marginally increased the fixed charges for
most of the categories to increase the revenue recovery from fixed charges and at the same time
avoiding tariff shock to any consumer category.
The Commission in its Tariff Order dated March 18, 2008 had mentioned that ideally, the
fixed charges should be levied on the basis of contracted/sanctioned load for all the categories.
However, for domestic category, considering the data on sanctioned load which had number of
consumers having fractioned contracted load (<1 kW) and also considering the quality of metering
and billing data, the Commission introduced the fixed charges on per connection basis. The
Commission in its Tariff Order dated October 23, 2009, specified different fixed charges on per
connection basis for domestic consumers having contracted/sanctioned load upto 4 kW and
consumers having contracted /sanctioned load above 4 kW. Further, during the tariff proceedings
for FY 2015-16, the Commission floated an in-house paper on the issue of Fixed Charges based on
consumption and the Commission after detailed deliberations in its Order dated April 11, 2015
introduced consumption based fixed charges for domestic consumers.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
220 Uttarakhand Electricity Regulatory Commission
At the approved tariffs, the recovery from Fixed Charges from the consumers for FY 2016-17
is estimated to be around 12.90% against the total fixed cost incidence on the Petitioner of about
48.71% of the licensee’s ARR for FY 2016-17.
The Commission in its Tariff Order dated March 18, 2008 had re-introduced the Minimum
Consumption Guarantee (MCG) Charges for the industrial category and in its Tariff Order dated
October 23, 2009 re-introduced the Minimum Consumption Guarantee (MCG) Charges for the Non-
Domestic Category. The Commission in its Order dated April 11, 2012 had introduced MCG for
metered PTW category also.
Some of the stakeholders submitted that the MCG burdens the consumers with additional
charges and results in wasteful consumption of electricity. They also represented that the MCG on
seasonal industry should be abolished as it encourages unnecessary wastage of electricity by
consumers during off season. Some of the stakeholders also represented that due to demand supply
shortage situation, load shedding is being carried out by UPCL and, hence, MCG should either be
abolished or reduced. Some of the stakeholders also submitted that due to MCG, they are either
forced to consume/waste electricity during off season or are penalized to pay the energy charges
for electricity not consumed by them during off season which is against the principles of energy
efficiency.
The Commission would like to clarify that the MCG is only applicable for the consumers if
their load factor is very low, in the range of 10-15% with 3-4 hours/day usage of electricity. Hence,
MCG charges would actually be recovered from consumers having abnormally low consumption of
electricity with respect to their sanctioned/contracted load. While for other consumers having
reasonable level of consumption with respect to their load, the MCG charges gets subsumed in
energy charges.
The Commission in its Order dated April 11, 2015 taking into cognisance the various
representations received for reduction in MCG and also in line with its plan for gradual elimination
of MCG reduced the MCG to 50 units/kWh/month for all those Non-Domestic sub-categories on
which MCG were earlier specified as 60 units/kWh/month. For HT industries the same was
revised to 100 kVAh/kVA/month from the earlier level of 110 kVAh/kVA/month. For Atta
chakkis, the MCG was revised to 30 units/kW/month from the earlier level of 40 units/kW/month.
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 221
For PTW category the MCG was reduced to 60 units/BHP/month from earlier level of 70
units/BHP/month.
Though the Commission in its Tariff Order dated March 18, 2008 had mentioned that it may
review the continuation of the MCG charges in subsequent Tariff Orders. However, as no
substantial improvement has been achieved by UPCL with respect to metering and billing issues,
the Commission has decided to continue with the levy of MCG charges for entire Industrial
category and for Non-Domestic consumers having contracted load of more than 25 kW and for
PTW Consumers.
Further, the Commission would like to clarify that the minimum consumption guarantee
charges are computed by considering the applicable base energy charges for the relevant category
of consumer alongwith the specified MCG and adjusted only towards the energy charges. Further,
as per the prevalent mechanism, in case cumulative actual consumption, from the beginning of the
financial year, exceeds the units specified for annual minimum consumption guarantee (MCG), no
further billing of monthly MCG is done and in such cases, differential paid, in excess of actual
billing is adjusted in the bill for the month of March. This mechanism has been elaborated through
an illustration in “General Condition of Supply” in the Rate Schedule. In case of HT Industry, the
annual adjustment (refund) of the energy charges for units billed to cover MCG, if any, shall be
given at the energy charge during normal hours for load factor upto 40%.
6.2.3.3 Abolition of MCG from RTS-4(Private Tube Wells)
As discussed earlier, the Petitioner has requested the Commission to abolish the MCG from
RTS-4 with the condition that State Government subsidises the revenue loss on account of the same.
The Commission is of the view that the Petitioner has not given any firm proposal in this
regard and has submitted a conditional proposal that MCG may be abolished for RTS-4 subject to
Government of Uttarakhand subsidising the revenue loss to the Petitioner on account of the same,
which in absence of a concrete proposal from Government of Uttarakhand on which a decision can
be taken, cannot be considered.
The Commission is of the view that the Petitioner cannot submit a conditional proposal to
the Commission and in case the Petitioner wants this proposal to be implemented, the Petitioner
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
222 Uttarakhand Electricity Regulatory Commission
should have beforehand approached the State Government in this regard and submitted a letter
from Government of Uttarakhand towards commitment of subsidy in this regard.
The Commission in its MYT Order dated May 06, 2013 had modified the Minimum
Consumption Guarantee (MCG) mechanism for PTW consumers on the basis of units/month from
Rs. 100/BHP/month. Further, the Commission in its Tariff Order dated April 21, 2015 had reduced
the MCG from 70 units/BHP/month to 60 units/BHP/annum.
Based on the above, since the Commission has not received any communication from
Government of Uttarakhand towards reimbursement of subsidy in this regard, the Commission
does not find any appropriate reason to abolish the MCG for PTW category. However, in case, the
Government of Uttarkhand provides subsidy, then UPCL, based on the quantum of subsidy, can
charge lower tariff than the approved tariff.
6.2.3.4 Continuous Supply Surcharge
The Petitioner has proposed the continuous supply surcharge of 15% for industries opting
for continuous supply.
The Commission, in its Tariff Order dated October 23, 2009, had approved continuous
supply surcharge @ 10% of the Energy Charge for consumers opting for supply during restricted
hours (continuous). Further, all the consumers had this option to opt for continuous supply
irrespective of whether they were on dedicated independent feeder or on mixed feeder. In
accordance with the above provision, even if a single consumer in mixed feeder opted for
continuous supply, its benefit got extended to all the consumers on that mixed feeder. This was a
sort of discrimination amongst the consumers who had opted for continuous supply on mixed
feeder and those who had not opted for continuous supply on mixed feeder as both enjoyed the
benefit of continuous supply irrespective of the fact that they were paying any continuous supply
surcharge or not. On the other hand, if the supply of the mixed feeder was required to be cut during
rostering, the supply of continuous supply consumer was also required to be unintentionally cut.
The Commission in order to rectify this anomaly had taken a view in its Tariff Order dated
April 10, 2010 that the option of continuous supply should be made available only to consumers
who are connected on a dedicated independent feeder or industrial feeder provided that all the
industrial consumers on such feeder opt for continuous supply option. The Commission was also of
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 223
the view that considering the supply shortage position, this option was to be provided only to the
continuous process industries requiring continuous supply due to continuous nature of their
process. In this connection, the Commission would like to refer to Regulation 3(2) of UERC (Release
of new HT & EHT Connections, Enhancement and Reduction of Loads) Regulation, 2008, which
provides that loads for all HT consumers having continuous processes, irrespective of load applied
for, shall be released through independent feeder only. The Commission in its Tariff Order dated
April 10, 2010 had, therefore, decided that with effect from May 1, 2010, the option of continuous
supply shall remain available only to continuous process industries operating twenty four hours a
day and for seven days in a week without any weekly off. Further, this option was only to be
available to continuous process industries connected through an independent feeder or industrial
feeder provided that all the industrial consumers on such feeder opted for continuous supply
option and for availing such an option, they were required to pay 15% extra energy charges at
revised tariff with effect from May 1, 2010 or from the date of connection, whichever is later till 31st
March, 2011 irrespective of actual period of continuous supply option. Further, the Commission in
its Tariff Order dated April 10, 2010 also decided that the load shedding would be applicable for all
the consumer categories except continuous process industries availing continuous supply option
and, hence, the Commission abolished the mechanism of allowing utilisation of power upto 15% of
the contracted load by industrial consumers who did not opt for continuous supply.
In its Tariff Order for FY 2011-12 dated May 24, 2011, Tariff Order for FY 2012-13 dated April
11, 2012, MYT Order dated May 06, 2012 and APR Order dated April 10, 2014 the Commission
decided to continue with the same provisions for Continuous Supply as approved in its Order
dated April 10, 2010.
The Commission in its ARR/Tariff Order dated April 11, 2015 after detailed deliberations on
the issue after floating the in-house paper extended the option of continuous supply to non-
continuous process industries in addition to the continuous process industries.
In these tariff proceedings, the Commission has received mixed responses from various
stakeholders. Some of the industries submitted that the continuous supply surcharge be reduced.
The Commission would like to clarify that it may not be appropriate to reduce the
continuous supply surcharge at this stage as the State of Uttarakhand is still facing power shortage
and UPCL is procuring short term power from market to meet the demand. Even for FY 2016-17,
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
224 Uttarakhand Electricity Regulatory Commission
the Commission has estimated a deficit of about 2670 MUs in the requirement of UPCL which is of
substantial nature. Hence, the Commission does not find any reason to reduce or abolish the
continuous supply surcharge. However, considering the views of stakeholders, the Commission has
decided not to increase the continuous supply surcharge and has retained the same as 15% of
energy charges.
This option will only be available to continuous and non-continuous industries connected on
an independent feeder or industrial feeder provided that all the industrial consumers on such
feeder opt for continuous supply option. The existing non-continuous process industrial consumers
opting for continuous supply shall pay 15% extra energy charges with effect from April 01, 2016 or
in case of new consumers from the date of connection, till March 31, 2017 irrespective of actual
period of continuous supply. However, in case of re-arrangement of supply through independent
feeder, the Continuous Supply Surcharge shall be applicable from the date of energisation of
aforesaid independent feeder till March 31, 2017, irrespective of actual period of continuous supply
option.
In this regard, the Commission would like to clarify certain key issues, pertaining to
applicability conditions for existing and new continuous and non-continuous supply consumers in
order to avoid any misinterpretation of the conditions, and the same are discussed as under:
• Consumers who have opted for Continuous supply shall continue to remain
Continuous Supply Consumers and they need not to apply again for seeking
continuous supply option. Such consumers shall pay 15% extra energy charges,
in addition to the energy charges approved, w.e.f. April 01, 2016 till March 31,
2017. However, in case of any pending dispute with UPCL in the matter of
continuous supply on certain feeders, those consumers will have to apply afresh,
for availing the facility of continuous supply, by April 30, 2016.
• The new applicants for continuous supply of power (including those who are
applying afresh as per above) can apply for seeking the continuous supply option
at any time during the year. However, continuous supply surcharge for such
existing consumers shall be applicable with effect from May 01, 2016 till March
31, 2017. UPCL shall provide the facility of continuous supply within 7 days from
the date of application, subject to fulfilment of Conditions of Supply as
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 225
mentioned in Clause 6 under Tariff Schedule of RTS-7. However, in case of re-
arrangement of supply through independent feeder, UPCL shall provide the
facility of continuous supply from the date of completion of work of independent
feeder subject to fulfilment of Conditions of Supply.
• The existing consumers availing continuous supply option, who wish to
discontinue the continuous supply option granted to them earlier, will have to
communicate, in writing, to UPCL latest by April 30, 2016 and they shall continue
to pay continuous supply surcharge alongwith the tariff approved in this Order
till April 30, 2016. Further, in this regard, if due to withdrawal by one consumer
from availing continuous supply option on a particular feeder, the status of other
continuous supply consumers in that feeder is affected, then UPCL shall inform
all the affected consumers on writing, well in advance.
• UPCL shall not change the status of a continuous supply feeder to a non-
continuous supply feeder.
• UPCL/PTCUL shall take up augmentation, maintenance and overhauling works
on top priority, specially in the sub-stations where circuit breakers, other
equipments, etc. are in dilapidated condition and, thereby, shall ensure
minimisation of interruptions of the continuous supply feeders.
• UPCL/PTCUL shall carry out periodical preventive maintenance of the feeders
supplying to continuous supply consumers. The licensees shall prepare
preventive maintenance schedule, in consultation with continuous supply
consumers, well in advance, so that such consumers can plan their operations,
accordingly.
6.2.3.5 Tariff Categorisation for Horticulture and Floriculture Consumers;
The Commission during the last year tariff proceedings floated an in-house paper on tariff
categorisation for Horticulature and Floriculture Consumers. After detailed deliberations on the in-
house paper, the Commission in its ARR/Tariff Order dated April 11, 2015 created a separate sub-
category “Agriculture Allied Activities” as follows:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
226 Uttarakhand Electricity Regulatory Commission
“Agriculture Allied Activities: All Consumers involved in nurseries growing plants/saplings,
polyhouses growing flowers/vegetables and fruits which doesn’t involve any kind of processing of
product except for storing and preservation.”
The Commission has received the representations that the activities mentioned in the
Agriculture Allied Activites are primarily agricultural activities only and hence, the tariff applicable
for PTW category should also be applicable for these activities. The Commission is of the view that
since, agricultural activity is common for both the activities under RTS-4 & RTS-4A, accordingly, the
Commission has decided to equate the tariff of “Agriculture Allied Activites”with the tariff of RTS-
4: Private Tube Wells/Pumping Sets.
Hence, the tariff applicable for Private Tube Wells/Pumping Sets shall also be applicable to
all consumers involved in nurseries growing plants/saplings, polyhouses growing
flowers/vegetables and fruits which doesn’t involve any kind of processing of product except for
storing and preservation. However, billing cycle will be different for these consumers instead of half
yearly billing cycle provided for PTW consumers.
6.2.3.6 Tariff Categorisation for HT Industries and Load Factor based Tariff
The Commission has considered the stakeholders/industries responses and observed that
some of the consumers have again raised the issue of load factor based tariff for HT Industries.
Some of the stakeholders submitted that the load factor based tariff for HT Industries is
discriminatory as well as against the provisions of the Act, Tariff Policy and the Commission’s
Tariff Regulations.
The Commission would like to highlight Section 62(3) of the Act, which empowers the
Appropriate Commission, while determining the tariff, to differentiate according to the consumer’s
load factor, power factor, voltage, total consumption of electricity etc. Section 62(3) of the Act is
reproduced below:
“The Appropriate Commission shall not, while determining the tariff under this Act, show undue
preference to any consumer of electricity but may differentiate according to the consumer's load
factor, power factor, voltage, total consumption of electricity during any specified period or the time
at which the supply is required or the geographical position of any area, the nature of supply and the
purpose for which the supply is required” (emphasis added).
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 227
Regulation 93(2) of UERC Tariff Regulations, 2011, specifically empowers the Commission
to design load factor based tariffs for any category of consumers and is reproduced below:
“The Commission, shall not, while determining the tariff, show undue preference to any consumer of
electricity but may differentiate according to consumer’s load factor, voltage, total consumption of
electricity during any specified period or time at which the supply is required or the geographical
position of any area, the nature of supply and the purpose for which the supply is required. “
The Commission in its Order dated April 11, 2015 after detailed deliberations in response to
the in-house paper modified the slabs for load factor based tariff from three slabs to two slabs.
Further, as discussed in Chapter 3 of the Order, some of the stakeholders submitted that the
principle applied for the categorisation of the industry on the basis of load factor should be on the
principle of higher the load factor, lower the tariff as prevalent in other States. They further
expressed that the higher load factor implies that the consumer consumes nearly as much as it has
contracted for and has paid the demand charges, accordingly, and the Utility stands to benefit by
higher load factor because the utility is able to sell the electricity which it has arranged for meeting
the demand of the consumer. They further opined that if the load factor is lower, the utility would
find itself having contracted higher power from generating companies than it would be able to sell
to the consumers and in this process may suffer loss.
The Commission does not agree with the views of the stakeholders that higher load factor
implies that the Utility stands to benefit because the Utility is able to sell the electricity which it has
arranged for meeting the demand of the consumer. The Commission would like to clarify that there
is diversity in time of usage of electricity by different consumers and, hence, the actual
simultaneous maximum demand of all the consumers put together shall always be less than the
summation of their contracted loads. Further, nowhere, the Utility makes the power purchase
arrangement equivalent to the contracted demand of its consumers. Further, increase or decrease of
the contracted load, and/or, the load factor, by consumer does not actually influence the
consumption pattern of consumers including diversity factor and, hence, the actual simultaneous
maximum demand, which is the basis for contracting power from different sources by the licensee
rather than the contracted load/load factor of the consumers. Therefore, the argument that if the
load factor increases, the utility is able to sell the electricity which it has arranged is totally incorrect.
As discussed in Chapter 3 and 5 of the Order, currently there is huge demand supply gap and,
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
228 Uttarakhand Electricity Regulatory Commission
hence, UPCL has to purchase additional power to meet the peak demand. Further, the utilisation of
the contracted capacity from firm sources by UPCL is more than 90% and with the increase in load
factor of consumers, the energy requirement of the Utility will further increase, which the Petitioner
will have to purchase at marginal price, i.e. the Petitioner will have to purchase costlier power to
meet the increase in energy requirement at higher load factor.
The Two Part Tariff tends to encourage high consumption as the same reduces the effective
per unit composite rate. Accordingly, to correct this, tariff also needs to increase in a manner so as
to achieve a near uniform composite rate. To do this demand and energy charges would have to
increase with every small increase in contracted demand or load utilization percentage. Although
theoretically possible, such an approach would make the tariffs too complex, incomprehensible and
will pose serious problems in implementation. There is, therefore, a trade of between the simplicity
of the tariff structure and precision in correcting the above distortion. The Commission’s attempt
has been to strike a balance between the two by choosing a uniform rate of demand charge and
different rates of energy charges linked to the consumption levels represented by the Load Factor.
The Commission has avoided sharp increases in energy charges and has infact modified the three
slabs prevalent earlier to only two slabs in its previous Tariff Order dated April 11, 2015.
As had been illustrated by the Commission in its previous Tariff Orders in case of single
energy charge, without any load factor slabs, the effective tariff of an intended cross-subsidising
consumer goes down steeply with increasing load factor, thereby reducing the quantum of cross-
subsidy charged from it. After a threshold level of load factor, this structure leads to an undesirable
anomaly that the effective tariff becomes lower than the Cost of Supply and the consumer instead of
being subsidising consumer becomes subsidised consumer. Thus, this structure apart from leading
to the abovesaid anomaly is highly inequitable amongst the consumers of same category with
consumers having low load factor being loaded with much higher tariff and making up for loss due
to lower tariff even below cost of supply paid by high load factor consumers. Transition from
subsidising consumer to subsidised consumer with increasing load factor is not only incorrect but
also highly undesirable.
This issue has been dealt in detail by the Commission in the the in-house paper issued
during the previous tariff proceedings. Thus, to have cost reflective tariffs, the energy charges
should increase with load factor.
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 229
Hence, in view of the above, the Commission is continuing with the existing load factor
based tariff structure for HT Industry.
6.2.3.7 Time of Day Tariff
Regarding Time of Day Tariff, the stakeholders requested the following:
• Abolishing the morning peak hours.
• Morning peak hours in winter season should be from 7 A.M. to 9:30 A.M. in place of
existing 6 A.M. to 9:30 A.M.
• The ToD charges should be at existing levels.
• The rebate of 10% for consumption during off-peak hours should be increased to
20%/25%.
The Commission in its Tariff Order for FY 2010-11 dated April 10, 2010 approved the peak
hour rate as 50% higher than the normal hour rate for Industrial Category. Further, in case of HT
industries, the Commission has specified the peak hour rate as 50% higher than the normal hour
rate applicable for highest load factor slab, i.e. energy charge for load factor above 50% for all the
HT industrial consumers. The Commission kept the rebate during off peak hours to 10% to
incentivise the shift in consumption from peak hours to off peak hours.
The Commission, in each of its tariff determination exercise, has been analysing the shift
from the peak hours to normal and off-peak as well as the consumption pattern during the peak
and off-peak hours in the State. The Commission has analysed the unrestricted load curves of
summer as well as the winter month to assess the consumption during peak hour period during
these months. The load curves for the days having highest peak load in the months of summer and
winter season have been examined and the same are graphically presented below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
230 Uttarakhand Electricity Regulatory Commission
Chart 1: Load Curve for 29th Jan., 2016 (MW)
Peak Demand – 2034 MW at 8 AM Peak Hours – 7 to 10 AM
Chart 2: Load Curve for 3rd Feb., 2016 (MW)
Peak Demand – 1977 MW at 8 AM Peak Hours – 7 to 10 AM
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 231
Chart 3: Load Curve for 29th May, 2015 (MW)
Peak Demand – 1965 MW at 8 PM Peak Hours – 8 to 10 PM
Chart 4: Load Curve for 10th June, 2015 (MW)
Peak Demand – 1986 MW at 9 PM Peak Hours – 8 to 10 PM
It is observed from the above graphical presentations that during the winter season both
morning as well as evening peak demand exists in the State. Infact, in the months of January and
February, the morning peak demand has been found to be even more pre-dominant than the
evening peak demand. Further, the overall system peak of Uttarkhand State during the year is also
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
232 Uttarakhand Electricity Regulatory Commission
observed in the morning hours. The Commission feels the need for DSM and having ToD tariff as a
measure for ensuring curtailment of morning as well as evening peaks. Considering all these
aspects, the Commission in the present Order is continuing with the same Peak, Normal and Off
Peak hour duration for ToD metering slots including percentage of peak hour surcharge and peak
hour rebate as approved in the earlier Tariff Order dated April 11, 2015
6.2.3.8 Rebate for availing supply at higher voltage
The Petitioner submitted that rebate for taking supply at higher voltage was revised by the
Commission in its Tariff Order dated 10th April 2014 from 1.5% and 5% to 2.5% and 7.5% for taking
supply at 33 kV and 132 kV and above respectively. The Petitioner requested the Commission to
revise the rebate for availing supply at higher voltage from the current levels of 2.5% and 7.5% to
1.5% and 5% for availing supply at 33 kV and 132 kV respectively.
As discussed in Chapter 2 of the Order, some of the stakeholders suggested to retain the
rebates at existing prevalent level in the absence of voltage wise cost of supply.
The Commission after considering the views expressed by several stakeholders revised the
rebate for availing supply at higher voltage in its Order dated April 10, 2014. The Commission is of
the view that supply at higher voltages benefits the Licensee as the losses at higher voltages are on
lower side. As regards the loss incurred by UPCL on account of higher rebate, the Commission
would like to clarify that such losses are not borne by UPCL as the actual revenue billed by UPCL
for industrial consumers is considered while carrying out the truing up of revenue for a particular
year. Further, UPCL has wrongly mentioned that its views were not considered by the Commission
while changing the rebates. The Commission had sought response of UPCL on the suggestions
made by the industries for increasing the rebates and the Commission has dealt with the same in
the said Tariff Order.
In view of above, the Commission has decided to continue with the prevelant rebate levels
for availing supply at higher voltage levels.
6.2.3.9 Revision of Terms and Conditions applicable on Seasonal Industries
As regards addition of new conditions proposed by the Petitioner for seasonal industries, the
Commission is of the view that the existing provisions of Rate Schedule regarding Seasonal
Industries are amply clear and no change is warranted in the same.
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 233
6.2.3.10 Load Factor Computation
Some of the stakeholders submitted that in the formula for computation of Load Factor,
lower of maximum demand and contracted demand is considered and in case the maximum
demand is lower than the contracted demand the billable demand is considered as 80% of
contracted demand for billing purpose. They suggested that the computation of Load Factor based
on contracted demand is appropriate in cases where the monthly billable demand is more than the
contracted demand and hence, the formula may be revised as follows:
The Commission in its ARR/Tariff Order dated April 10, 2014 modified the load factor
computation formula which was further revised by the Commission vide its Order dated November
07, 2014 in Petition No. 24 of 2014 as follows:
“
100period billing in the hours of No. x less is whicheverDemand Contractedor Demand Maximum
period billing theduring Access)Open through receivedenergy the(excludngn Consumptio×
Provided that in cases where maximum demand during the month occurs in period when open access
is being availed by the consumer, then maximum demand for the purpose of computation of load factor
shall be that occurring during the period when no open access is being availed.”
The Commission is of the view that the existing load factor formula is appropriate as UPCL
has to make arrangements of power for the demand contracted by the consumers and not based on
billable demand. The Commission has, therefore, decided to continue with the formula as approved
by the Commission in its Order dated November 07, 2014.
6.2.3.11 Prepaid metering
The Petitioner has proposed some amendments to the Prepaid Metering Scheme approved
by the Commission in its Tariff Order for FY 2012-13. The Commission recognises that Prepaid
Metering is expected to provide better services to the consumers, improve and secure the cash flow
of the Petitioner and also lead to reduction in consumer grievance and dissatisfaction to the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
234 Uttarakhand Electricity Regulatory Commission
consumers. Hence, after detailed deliberations on the proposals of the Petitioner, the Commission
approves the following conditions for Pre-Paid Metering:
a) The option of Pre-paid metering shall be available for all categories of consumers
upto 25 kW load under LT category. Prepaid Metering shall be mandatory for new
Temporary LT connections upto 25 kW and for Advertisements/Hoardings.
The Commission is of the opinion that the same should not be forced upon small
consumers as proposed by UPCL. Hence, proposal of UPCL in this regard is
unacceptable.
b) There shall be a minimum recharge of Rs. 100 and the maximum limit of recharge
shall be Rs. 5000 for single phase connection and Rs. 15000 for three phase
connections.
The Commission does not find any reason for change in this stipulations and, hence,
decides to continue with the same.
c) Any recharge shall be for a maximum period of six months after which time
extension of remaining amount or another top up will be essential.
The apprehension of the licensee in this regard for proposing quarterly recharges
was the levy of FCA charges. Ideally, the meter readers of the licensee visits every
locality atleast once in two months for meter reading and consequent changes for
FCA in the pre-paid meters can be done during those visits of the meter readers
when he goes to take meter readings of post paid consumer in that locality.
Moreover, levy of FCA is an ongoing process as the same changes every quarter so
there may be instances of delay in recovering the FCA charges from the consumers
having pre-paid connections, however, the net impact may not be substantial.
d) As regards the charging for testing of meter, the Petitioner shall recover the amount
as approved by the Commission under Schedule of Miscellaneious Charges directly
from such prepaid consumers as is done for postpaid consumers and shall not be
charged from the recharge amount.
e) The Petitioner shall issue an advertisement in the newspapers within 15 days of the
issue of this Order, briefly mentioning salient features of the Prepaid Metering
Scheme for LT consumers upto 25 kW to provide an option to the consumer to
express their interest to opt for the Prepaid metering scheme latest by June 15, 2016.
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 235
It may be noted that the objective of calling applications for Prepaid metering shall
be primarily for the purpose of estimation of the requirement of such meters based
on the demand of the Scheme. Based on the requests received from the consumers
opting for Prepaid metering, UPCL shall implement the Prepaid metering in a
phased manner. Further, the Petitioner may also allow prepaid metering services to
the consumers who could not submit their request within the stipulated time given
in the advertisement and opt for it subsequently.
f) The Petitioner is also directed to prepare a Salient Features of the Prepaid Metering
Scheme (in 1-2 pages) and circulate the same along with the bills of May, 2016 to all
the eligible consumers, i.e. LT consumers upto 25 kW, to facilitate wide circulation as
well as to provide salient features of the proposed mechanism of the Prepaid
Metering Scheme.
g) In case, the consumer opting for Prepaid Metering have outstanding arrears, the
Petitioner shall adjust 20% of the past arrears or 50% of the recharge amount,
whichever is higher from the recharge voucher, subject to the maximum of the
outstanding arrears. Further, the maximum limit of recharge as mentioned above,
shall not be applicable in case of consumers having outstanding arrears and
accordingly, such consumers having past arrears will have to take minimum
recharge of more than 20% of the outstanding arrears.
The licensee’s proposal of not allowing pre-paid connections to the consumers
having arrears would infact be detrimental to its own interest. After installing the
pre-paid meters atleast some portion of the arrears due would start getting collected
through the mechanism proposed by the Commission.
h) The Petitioner shall make necessary provisions to provide friendly credit hours/limit
to the consumers, in order to ensure uninterrupted supply to the consumer in the
event of expiry of the balance during non working hours, i.e. night time or during
holiday, so as to provide reasonable time to the consumer to procure the recharge
voucher at the next possible working hours or working day. However, the charges
for the electricity consumed between expiry of balance during non-working hours
and subsequent recharge voucher shall be adjusted from the recharge voucher.
i) All the Prepaid meters will be provided with an alarm to indicate low credit.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
236 Uttarakhand Electricity Regulatory Commission
j) As per the guiding principles and Section 47(5) of the Electricity Act, 2003 the
Petitioner shall not charge any security deposit as is required in post paid
connections but price equivalent to the material cost, i.e. cost of meter and associated
equipments shall be charged as material security which shall be returned at the time
of permanent disconnection. The approved material security deposit for FY 2016-17
is Rs. 5000/- for single phase connection and Rs 10,000/- for three phase connection.
The Commission would again review the amount so specified above after availability
of the data relating to meter costs. The licensee is directed to submit the data
related to the cost of the meter and other associated equipments to the
Commission in the Tafiff proceedings for FY 2017-18.
k) The consumer shall be allowed only one transfer from postpaid to prepaid or
otherwise in a financial year.
l) Minimum Consumption Guarantee (MCG) shall not be applicable for prepaid
connections.
m) The Commission approves a rebate of 4% of Energy Charges for Domestic Category
and 3% of Energy Charges for other categories as per the applicable tariff schedule
for the consumers availing this scheme and the rebate shall only be applicable after
installation and operationalisation of Prepaid meters. However, no rebate shall be
applicable on Part (A) of RTS-10, i.e. Temporary Supply for Illumination & Public
Address Needs.
6.2.4 kVAh Tariffs
It has come to the notice of the Commission that the power factor of Government
connections like Public Lamps/Government Irrigation System, etc. is very low and with kWh tariff
still continuing for these categories, the Petitioner (UPCL) is incurring both energy as well as
revenue loss.
In the conventional method of electricity metering, the active energy (kWh) is measured and,
accordingly, the discoms have to meet the loss in the system resulting from the additional current
drawn due to the poor power factor of the load maintained by the consumers. Imposing poor power
factor penalty on all the consumers who create this burden, by identifying them through special
tasks, is not practical. Hence, if kVAh (apparent energy) billing is employed, it automatically
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 237
becomes the responsibility of the consumer to maintain the quality of the load by improving its
power factor. This can be achieved by installation of electrical devices with power factor correctors,
or install capacitors at their premises by such consumers failing which energy losses of the
Petitioner increases and other consumers, even if they are maintaining good power factor,
automatically pay for the additional burden.
In kVAh billing system as the electricity bills conceive this additional burden for the
consumers who create it, no separate penalty need to be imposed or such burden related to one
consumer will not appear as an indirect liability to other consumers. Further, a significant amount
of precious energy will be saved due to reduction of technical loss in the system from the reduction
in reactive currents. Further, UPCL will also save a large amount of money, as the investments in
installation of capacitors in the system would not be required for compensation or voltage
improvement.
Taking this into cognizance, the Commission has been directing UPCL since its Tariff Order
dated 18.03.2008 for FY 2007-08 and FY 2008-09 for releasing all new 3 phase connections above 4
kW with Electronic Tri-vector Meter having MDI. The Commission has already approved kVAh
billing for public water works and GIS connections over 75 kW.
Accordingly, the Commission directs the Petitioner to submit the type of meters installed
at Public Lamps, GIS upto 75 kW, and its action plan for installation of Tri-Vector meters
capable of recording both kWh and kVAh consumption in the above referred categories/sub-
categories where such meters have not been installed within 1 month of the issuance of this
Tariff Order. The Commission also directs the Petitioner to take such measures for installation of
Tri-vector meters in other categories/sub-categories of consumers where power factor is poor and
tariff is on kWh basis.
Based on the compliances submitted by the Petitioner on the above directives and
preparedness thereof, the Commission may take a view of specifying kVAh tariff for those
categories of consumers who are currently billed at kWh Tariffs from next year onwards.
6.2.5 Treatment of Revenue Gap
As concluded in Chapter 5 of the Order, the revenue at existing tariffs leaves a revenue gap
of Rs. 249.56 Crore to meet the Net Revenue Requirement for FY 2016-17, post adjustment of the
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
238 Uttarakhand Electricity Regulatory Commission
revenue surplus and gap determined after truing up of expenses and revenue based on the audited
accounts for FY 2014-15.
The Commission in order to recover the gap has revised the tariffs for FY 2016-17. The
approved tariff will be applicable from April 1, 2016 and will be effective till revised by the
Commission.
6.2.6 Cross Subsidy
As per the provisions of Tariff Policy, the Regulatory Commission has to reduce the cross
subsidies with respect to cost of supply in a gradual manner. The Commission in its APR Order for
FY 2015-16 had computed the cross subsidies for different category of subsidising consumers which
were in accordance with the Tariff Policy.
The Commission has now revised the tariff and ensured that the cross subsidy has broadly
reduced with respect to previous levels with few exceptions as discussed while discussing the cross
subsidy levels at approved tariffs.
6.2.7 Category-wise Tariff Design
The Commission has designed the category-wise tariffs for full recovery of approved Net
Revenue Requirement for FY 2016-17. The category-wise tariffs approved by the Commission are
discussed below and are also shown in the Approved Rate Schedule placed at Annexure-1. These
rates shall be effective from April 1, 2016 and shall continue to be applicable till further revised by
the Commission.
6.2.7.1 RTS-1: Domestic Tariff
The Commission, recognising the fact that lifeline consumers were one of the most
economically weaker sections of the consumers, in its Tariff Order for FY 2003-04 had approved a
tariff of Rs. 1.50/kWh for such consumers when the average cost of supply was Rs. 2.28/kWh.
Considering the fact that the Tariff Policy permits that the tariffs for such lifeline consumers can be
determined at 50% of the average cost of supply, the Commission in order to gradually reduce the
cross subsidy and also to enable the licensee to recover some of its Fixed Cost, in its Tariff Order for
FY 2011-12 dated May 24, 2011 had introduced a Fixed Charges of Rs. 5/connection/month which
was further nominally increased to Rs. 6/connection /month and then to Rs. 7/connection/month
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 239
in the Tariff Order for FY 2012-13 dated April 11, 2012 and MYT Order dated May 06, 2013
respectively.
Since the average cost of supply has increased further, therefore, with a view to reduce the
cross-subsidy, the fixed charges of lifeline consumer have now been increased from Rs.
11/connection /month to Rs. 14/connection/month. However, the energy charges have not been
increased and are kept intact at Rs. 1.50/kWh.
For other domestic consumers, the fixed charges have been marginally increased to enhance
the recovery from fixed charges. The energy charges for lowest slab, i.e. consumption upto 100
units/month have been nominally increased from the existing level of Rs. 2.40/kWh to Rs.
2.45/kWh. The energy charges for the second slab, i.e. for consumption between 101-200
units/month have been fixed as Rs. 3.10/kWh. The energy charges for the third slab, i.e. for
consumption between 201-400 units/month have been fixed as Rs. 4.10/kWh, for consumers having
consumption above 400 units/month, the energy charges have been fixed at Rs. 4.50/kWh.
For single point bulk supply connections, the energy charges have been increased to Rs.
3.70/kWh from Rs. 3.40/kWh and fixed charges has been increased to Rs. 50/kW/month from Rs.
40/kW/month.
A comparison of the tariff, i.e. existing, proposed by the Petitioner and that approved by the
Commission, is given in the Table below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
240 Uttarakhand Electricity Regulatory Commission
Table 6.1 : Tariff for Domestic Consumers
S. No Description
Existing Tariff UPCL Proposed Tariff Approved
Fixed Charge (Per Month)
Energy Charges
Fixed Charge (Per Month)
Energy Charges
Fixed Charge (Per
Month)
Energy Charges
RTS-1: Domestic 1.1 Life Line Consumers Rs. 11/
Connection Rs.
1.50/kWh Rs. 11/
Connection Rs.
1.50/kWh Rs. 14/
Connection Rs.
1.50/kWh 1.2 Other Domestic Consumers
(i) 0-100 Units/Month Rs. 35/ Connection
Rs. 2.40/kWh
Rs. 45/ Connection
Rs. 3.00/kWh
Rs. 40/ Connection
Rs. 2.45/kWh
(ii) 101-200 Units/Month Rs. 50/ Connection
Rs. 2.90/kWh
Rs. 65/ Connection
Rs. 3.80/kWh
Rs. 60/ Connection
Rs. 3.10/kWh
(iii) 201-300 Units/Month Rs. 70/ Connection
Rs. 3.80/kWh
Rs. 90/ Connection
Rs. 4.80/kWh
Rs. 85/ Connection
Rs. 4.10/kWh
(iv) 301-400 Units/Month Rs. 95/ Connection
Rs. 3.80/kWh
Rs. 120/ Connection
Rs. 4.80/kWh
Rs. 110/ Connection
Rs. 4.10/kWh
(v) 401-500 Units/Month Rs. 120/ Connection
Rs. 4.00/kWh
Rs. 145/ Connection
Rs. 5.00/kWh
Rs. 150/ Connection
Rs. 4.50/kWh
(vi) Above 500 Units/Month Rs. 145/ Connection
Rs. 4.00/kWh
Rs. 175/ Connection
Rs. 5.00/kWh
Rs. 175/ Connection
Rs. 4.50/kWh
2 Single point bulk supply Rs. 40/kW Rs. 3.40/kWh Rs. 50/kW Rs.
4.30/kWh Rs. 50/kW Rs. 3.70/kWh
6.2.7.2 RTS 1-A: Concessional Snowbound Area Tariff
A comparison of the tariff, i.e. existing, proposed by the Petitioner and that approved by the
Commission, is given in the Table below:
Table 6.2 : Concessional Tariff for Snowbound Areas
S. No Description
Existing Tariff UPCL Proposed Tariff Approved
Fixed Charge (Per Month) Energy Charges Fixed Charge
(Per Month) Energy
Charges Fixed Charge (Per Month) Energy Charges
RTS-1A: Snowbound
1 Domestic Rs. 11/ Connection Rs. 1.50/kWh Rs. 11/
Connection Rs.
1.50/kWh Rs. 14/
Connection Rs. 1.50/kWh
2 Non-Domestic upto 1 kW
Rs. 11/ Connection Rs. 1.50/kWh Rs. 11/
Connection Rs.
1.50/kWh Rs. 14/
Connection Rs. 1.50/kWh
3 Non-Domestic above 1 kW & upto 4 kW
Rs. 11/ Connection Rs. 2.25/kWh Rs. 11/
Connection Rs.
2.25/kWh Rs. 14/
Connection Rs. 2.25/kWh
4 Non-Domestic above 4 kW
Rs. 20/ Connection Rs. 3.40/kWh Rs. 20/
Connection Rs.
3.40/kWh Rs. 25/
Connection Rs. 3.40/kWh
6.2.8 RTS-2: Non-Domestic Tariff
For Non-domestic consumers, the Commission has increased the energy charges and fixed
charges to enable the licenses to recover its fixed cost and revenue gap. The Commission has
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 241
separately specified the tariff for concessional sub-category of educational institutions, hospitals
and charitable institutions, which shall include:
• Government/Municipal Hospitals;
• Government/Government Aided Educational Institutions; and
• Charitable Institutions registered under the provisions of Income Tax Act, 1961 and
whose income is exempted from tax under this Act.
The existing tariff, tariff proposed by the licensee and that approved by the Commission is
given in Table below:
Table 6.3: Tariff for Non-domestic consumers
Sl. No. Description
Existing Tariff UPCL Proposed Tariff Approved
Fixed / Charges
(Per Month)
Energy Charges MCG
Fixed / Demand Charges
(Per Month)
Energy Charges MCG
Fixed / Demand Charges
(Per Month)
Energy Charges MCG
1 Government, Educational Institutions and Hospitals etc.
1.1 Upto 25 kW Rs. 40/ kW
Rs. 4.05/ kWh Rs. 50/
kW Rs 5.00/
kWh Rs. 45/ kW
Rs. 4.15/ kWh
1.2 Above 25 kW Rs. 45/ kVA
Rs. 3.65/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/annum
Rs. 57/ kVA
Rs. 4.55/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/annum
Rs. 55/ kVA
Rs. 3.85/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/annum 2 Other Non-Domestic Users
2.1
Upto 4 kW and
consumption upto 50 units
per month
Rs. 45 / kW
Rs. 4.20/ kWh Rs. 57 /
kW Rs. 5.20/
kWh Rs. 50 / kW
Rs. 4.30/ kWh
2.2
Others upto 25 kW not
covered in 2.1 above
Rs. 45 / kW
Rs. 4.85/ kWh Rs. 57 /
kW Rs. 6.10/
kWh Rs. 55 / Kw
Rs. 5.10/ kWh
2.3 Above 25 kW Rs. 45 / kVA
Rs. 4.75/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/ annum
Rs. 57 / kVA
Rs. 5.95/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/ annum
Rs. 55 / kVA
Rs. 5.00/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/ annum
3 Single Point Bulk Supply above 75 kW
Rs. 45 / kVA
Rs. 4.65/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/ annum
Rs. 57 / kVA
Rs. 5.80/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/ annum
Rs. 55 / kVA
Rs. 4.90/ kVAh
50 kVAh /kVA
/month & 600 kVAh/
kVA/ annum
4 Independent
Advertisement Hoardings
Rs. 60/ kW
Rs. 4.90/kWh Rs. 75/
kW Rs.
6.10/kWh Rs. 70/ kW
Rs. 5.20/kWh
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
242 Uttarakhand Electricity Regulatory Commission
6.2.9 RTS-3: Public Lamps
The tariff for this category has been approved in such a manner so that the average billing
rate for category is close to average cost of supply. The fixed charges for Pulbic Lamps in rural areas
have been fixed at Rs. 10/kW lower than the fixed charges in urban areas. The existing tariff, tariff
proposed by the licensee and that approved by the Commission is given in the Table below:
Table 6.4: Tariff for Public Lamps
Description
Existing Tariff UPCL Proposed Tariff Approved
Fixed / Demand Charges (Per
Month)
Energy Charges
Fixed / Demand Charges (Per
Month)
Energy Charges
Fixed / Demand Charges (Per
Month)
Energy Charges
RTS-3: Public Lamps 3.1 Urban 1. Metered Rs. 40/kW Rs. 4.35/
kWh Rs. 50/kW Rs. 5.45/ kWh Rs. 50/kW Rs. 4.65/ kWh
3.2 Rural
1. Metered Rs. 35/kW Rs. 4.35/ kWh Rs. 45/kW Rs. 5.45/
kWh Rs. 40/kW Rs. 4.65/ kWh
6.2.10 RTS-4: Private Tube Wells/Pump Sets and Agriculture Allied Activities
The Commission in order to gradually reduce the cross subsidy to this category has
increased the tariff for this category of consumers. Further, as discussed earlier, the Commision has
equated the tariff of “Agriculture Allied Activities” with RTS-4.
The existing tariff, tariff proposed by the licensee and that approved by the Commission are
given in the Table below:
Table 6.5: Tariff for Private tube Wells/ Pump Sets
Category
Existing Tariff UPCL Proposed Tariff Approved Fixed /
Demand Charges
(Per Month)
Energy Charges
Minimum Charges
Fixed / Demand Charges
(Per Month)
Energy Charges
Minimum Charges
Fixed / Demand
Charges (Per Month)
Energy Charges
Minimum Charges
RTS-4: Private Tube-wells / Pumping sets
Metered Nil Rs. 1.40/ kWh
60 units/ BHP/
month & 720 units /BHP/ annum
Nil Rs. 1.75/ kWh
60 units/ BHP/
month &. 720 units /BHP/ annum
Nil Rs. 1.55/ kWh
60 units/ BHP/
month & 720 units /BHP/ annum
RTS-4A: Agriculture Allied Activities
Metered Nil Rs. 2.25/ kWh
60 units/ BHP/
month & 720 units /BHP/ annum
Nil Rs. 2.80/ kWh
60 units/ BHP/
month &. 720 units /BHP/ annum
Nil Rs. 1.55/ kWh
60 units/ BHP/
month & 720 units /BHP/ annum
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 243
6.2.11 RTS-5: Government Irrigation System
The tariff for this category has been approved in such a manner so that the average billing
rate for this category is close to the average cost of supply without any element of cross-subsidy.
The existing tariff, tariff proposed by the licensee and that approved by the Commission is given in
the Table below:
Table 6.6: Tariff for Government Irrigation System
Description
Existing Tariff UPCL Proposed Tariff Approved
Fixed / Demand Charges (Per
Month)
Energy Charges
Fixed / Demand
Charges (Per Month)
Energy Charges
Fixed / Demand Charges (Per
Month)
Energy Charges
RTS-5: Government Irrigation System Upto 75 kW Rs. 40/kW Rs. 4.35/ kWh Rs. 50/kW Rs. 5.45/ kWh Rs. 50/kW Rs. 4.55/ kWh
Above 75 kW Rs. 40/kVA Rs. 4.20/ kVAh Rs. 50/kVA Rs. 5.25/
kVAh Rs. 50/kVA Rs. 4.40/ kVAh
6.2.12 RTS-6: Public Water Works
The tariff for this category has been approved so that the average billing rate for this
category is close to average cost of supply. The fixed charges for Pulbic Water Works in rural areas
have been fixed at Rs. 10/kW lower than the fixed charges in urban areas. The existing tariff, tariff
proposed by the licensee and that approved by the Commission is given in the Table below:
Table 6.7 : Tariff for Public Water Works
Description
Existing Tariff UPCL Proposed Tariff Approved Fixed / Demand
Charges (Per Month)
Energy Charges
Fixed / Demand Charges (Per Month)
Energy Charges
Fixed / Demand Charges (Per
Month)
Energy Charges
Urban Rs. 40/kVA Rs. 4.25/ kVAh Rs. 50/kVA Rs. 5.30/
kVAh Rs. 50/kVA Rs. 4.45/ kVAh
Rural Rs. 35/kVA Rs. 4.25/
kVAh Rs. 45/kVA Rs. 5.30/ kVAh Rs. 40/kVA Rs. 4.45/
kVAh
6.2.13 RTS-7: Industry
The Commission while determining the tariff of HT and LT Industries have taken into
consideration average cost of supply and cross subsidy.
Further, as discussed above, the Commission has decided to retain the peak hour rate as 50%
higher than the normal hour rate applicable for highest slab, i.e. with load factor above 50% for all
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
244 Uttarakhand Electricity Regulatory Commission
the HT industrial consumers. Further, consumers opting for continuous supply as per eligibility
given in this Order shall have to pay 15% additional energy charges as continuous supply
surcharge.
Further, as discussed above in tariff rationalisation measures, the Commission has retained
MCG on monthly basis with adjustment as detailed out in Tariff Schedule. The existing tariff, tariff
proposed by the licensee and that approved by the Commission for LT Industry is given in the
Table below:
Table 6.8: Tariff for LT Industries
Category
Existing Tariff UPCL Proposed Tariff Approved Fixed
Charges (Per
Month)
Energy Charges MCG
Fixed Charges
(Per Month)
Energy Charges MCG
Fixed Charges
(Per Month)
Energy Charges MCG
RTS-7: Industry LT Industry 1. LT Industries (upto 25 kW)
Rs. 105/ kW
Rs. 3.95/ kWh
*50 kWh/ kW/month &
600 kWh /kW/annum
Rs. 132/ kW
Rs. 4.95/ kWh
*50 kWh/ kW/month &
600 kWh /kW/annum
Rs. 130/ kW
Rs. 4.05/ kWh
*50 kWh/ kW/month &
600 kWh /kW/annum
2. LT Industries (above 25kW & upto 75 kW)
Rs. 105/ kVA
Rs. 3.60/ kVAh
50 kVAh/ kVA/month &
600 kVAh /kVA/ annum
Rs. 132/ kVA
Rs. 4.55/ kVAh
50 kVAh/ kVA/month &
600 kVAh /kVA/ annum
Rs. 130/ kVA
Rs. 3.70/ kVAh
50 kVAh/ kVA/month &
600 kVAh /kVA/ annum
*30 kWh/kW/month and 360 kWh/kW/annum for Atta Chakkis.
The existing tariff and tariff proposed by the licensee for HT Industry is given in the Table
below:
Table 6.9: Existing and Proposed Tariff for HT Industries
Sl. No. Category Load Factor
Existing Tariff Proposed Tariff
Energy Charges
(Rs./kVAh)
Fixed /Demand Charges
(Rs./kVA)
MCG Charges
Energy Charges
(Rs./kVAh)
Fixed /Demand Charges
(Rs./kVA)
MCG Charges
1 HT Industry having contracted load above 88kVA/75 kW (100 BHP)
1.1 Contracted Load up to 1000 kVA
Upto 40% 3.40 Rs. 230/kVA of the billable
demand
100 kVAh/kVA/month
& 1200 kVAh
/kVA/annum
4.15 Rs. 285/kVA of the billable
demand
100 kVAh/kVA/month &1200
kVAh /kVA/ annum
Above 40% 3.75 4.70
1.2
Contracted Load More than 1000 kVA
Upto 40% 3.40 Rs. 290/kVA of the billable
demand
4.15 Rs. 365/kVA of the billable
demand Above 40% 3.75 4.70
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 245
The approved tariff for HT Industry is given in Table below:
Table 6.10: Approved Tariff for HT Industry
S. No Category Load Factor
Energy Charges
Fixed Charges MCG
Rs./kVAh Rs./kVA/ month
kVAh/kVA of contracted load
1 HT Industry having contracted load above 88kVA/75 kW (100 BHP)
1.1 Contracted Load up to 1000 kVA
Upto 40% 3.50 Rs. 255/kVA of the billable
demand 100 kVAh/kVA/month
& 1200 kVAh /kVA/annum
Above 40% 3.85
1.2
Contracted Load More than 1000 kVA
Upto 40% 3.50 Rs. 320/kVA of the billable
demand Above 40% 3.85
6.2.14 RTS-8: Mixed Load
The Commission has increased the tariff for this category to reduce the level of cross
subsidy. The existing tariff, tariff proposed by the licensee and that approved by the Commission is
given in the Table below:
Table 6.11: Tariff for Mixed Load
Description
Existing Tariff UPCL Proposed Tariff Tariff Design Fixed /
Demand Charges
Per Month)
Energy Charges
Fixed / Demand Charges
Per Month)
Energy Charges
Fixed / Demand Charges
(Per Month)
Energy Charges
RTS-8: Mixed Load Mixed Load Single Point Bulk Supply above 75 kW including MES as deemed licensee
Rs. 50/kW Rs. 4.15/kWh Rs. 65/kW Rs. 5.15/kWh Rs. 60/kW Rs. 4.50/kWh
6.2.15 RTS-9: Railway Traction
The existing tariff, tariff proposed by the licensee and that approved by the Commission is
given in Table below:
Table 6.12: Tariff for Railway Traction
Description
Existing Tariff UPCL Proposed Tariff Tariff Design Fixed /
Demand Charges (Per
Month)
Energy Charges
Fixed / Demand Charges (Per
Month)
Energy Charges
Fixed / Demand
Charges (Per Month)
Energy Charges
RTS-9: Railway Traction
Rs. 200/kVA Rs. 3.60/ kVAh Rs. 260/kVA Rs. 5.00/
kVAh Rs. 225/kVA Rs. 3.95/ kVAh
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
246 Uttarakhand Electricity Regulatory Commission
6.3 Revenue for FY 2016-17
Considering the revised tariffs, the Commission has computed the projected revenue at the
approved tariffs from each category for FY 2016-17. The summary of category-wise projected
revenue for FY 2016-17 is given in the following Table:
Table 6.13: Revenue at approved Tariffs for FY 2016-17
S. No. Category Sales Revenue
Average Billing Rate
(ABR)
Increase in ABR at Approved Tariffs w.r.t
ABR at existing Tariff
MU Rs. Crore Rs./Unit 1. RTS-1: Domestic 2800.54 997.79 3.56 7.83% 2. RTS-2: Non Domestic 1256.82 683.80 5.44 5.37% 3. RTS-3: Public Lamps 49.23 23.56 4.79 7.14% 4. RTS-4: Private Tube Wells 318.57 49.38 1.55 10.60% 5. RTS-5: Government Irrigation System 123.18 59.67 4.84 5.62% 6. RTS-6: Public Water Works 361.63 173.88 4.81 5.04% 7. RTS-7: Industry LT Industry 345.05 177.87 5.15 5.99% HT Industry 5701.46 2946.28 5.17 3.68%
8. RTS-8: Mixed Load 213.80 101.27 4.74 8.96% 9. RTS-9: Railway Traction 17.47 8.81 5.04 10.20% 10. Sub-Total 11187.75 5222.31 - - 11. Revenue from MCG - 31.50 - - 12. Total 11187.75 5253.82 4.70 -
The estimated revenue for FY 2016-17 at approved tariffs works out to Rs. 5253.82 Crore, as
against the net ARR of Rs. 5252.87 Crore worked out after adjusting trued-up surplus/gaps of
previous years leaving a surplus of Rs. 0.95 Crore with UPCL.
The percentage increase for Railway Traction appears to be on a higher side as load factor of
this category has increased. Even with the percentage increase for Railway Traction as shown
above, the Cross Subsidy from this category has drastically reduced. Further, as observed from
above Table, the percentage tariff increase for most of the subsidized categories, i.e. Domestic, PTW
and Mixed Load is higher than the increase of by 6.58% in Average Cost of Supply approved for FY
2016-17 with respect to approved Average Cost of Supply for FY 2015-16. On the other side, the
percentage tariff increase for most of the subsidizing categories, i.e. Non-Domestic, LT Industries
and HT Industries is lower than the 6.58% increase in Average Cost of Supply approved for FY
2016-17 with respect to the approved Average Cost of Supply for FY 2015-16. Increasing the tariff
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 247
for subsidized categories by higher percentage with respect to percentage increase for subsidising
categories is a step towards reduction in cross subsidy.
6.4 Cross Subsidy
As discussed above, the Commission has designed the tariffs for various categories with an
objective of gradually reducing the cross subsidy with respect to average cost of supply. The extent
of category-wise cross-subsidy at approved tariffs computed at average cost of supply is given in
the Table below:
Table 6.14 : Cross Subsidy at Average Cost of Supply
Category Approved Average Billing Rate (ABR)
Average Cost of Supply (ACoS) ABR / ACoS Cross
Subsidy Rs./kWh Rs./kWh % %
Domestic 3.56 4.70 75.81% -24.19% Non Domestic 5.44 4.70 115.76% 15.76% Public Lamps 4.79 4.70 101.84% 1.84% PTW 1.55 4.70 32.98% -67.02% GIS 4.84 4.70 103.07% 3.07% PWW 4.81 4.70 102.30% 2.30% LT Industrial 5.15 4.70 109.68% 9.68% HT Industrial 5.17 4.70 109.95% 9.95% Mixed Load 4.74 4.70 100.78% 0.78% Railways 5.04 4.70 107.30% 7.30%
The comparison of Cross Subsidy at approved tariffs with respect to the average cost of
supply in Tariff Order for FY 2015-16 and as approved in this Tariff Order for FY 2016-17 is given
below:
Table 6.15 : Cross Subsidy at Approved Tariffs in FY 2015-16 and FY 2016-17
Category Cross Subsidy at Approved Tariff for FY 2015-16
Cross Subsidy at Approved Tariff for FY 2016-17
Domestic -24.84% -24.19% Non Domestic 16.05% 15.76% PTW -63.24% -67.02% GIS 3.37% 3.07% Public Lamps 2.13% 1.84% PWW 1.66% 2.30% LT Industrial 9.92% 9.68% HT Industrial 9.49% (13.30%)* 9.95% Mixed Load -1.66% 7.30% Railways 14.38% 0.78%
* Cross subsidy computed by considering the Revenue from Continuous Supply Surcharge at same level as considered for FY 2016-17.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
248 Uttarakhand Electricity Regulatory Commission
The Commission while designing the tariffs for FY 2016-17 has reduced the cross subsidies
for most of the categories except PTW category with respect to approved tariffs for FY 2015-16 and
has ensured to bring the cross-subsidy levels within the range specified in the National Tariff
Policy.
For PTW category, even with 10.60% tariff increase, the cross-subsidy is marginally
increasing and in order to retain the cross subsidy at same level of FY 2015-16, the tariff increase
required woud be much higher, which will result in tariff shock.
For HT Industry, the Commission while estimating the revenue from approved tariffs in its
Order dated April 10, 2015 had considered the revenue from continuous supply surcharge as Rs. 25
Crore and, accordingly, computed the Revenue and Cross Subsidy. However, during the
proceedings, UPCL submitted that the revenue from continuous supply surcharge from industries
was around Rs. 116 Crore, which has been considered by the Commission for FY 2016-17. If the
cross subsidy at approved tariffs for FY 2015-16 is computed by considering the revenue from
continuous supply surcharge of Rs. 116 Crore, the cross subsidy for HT Industrial category for FY
2015-16 works out to 13.30%.
Further, it can be seen from the Table above, cross-subsidies of all the subsidising consumers
is within the range of 120% as required in the Tariff Policy. The Commission going forward in
future years would attempt to reduce the cross-subsidy for subsidised categories with respect to the
average cost of supply and would reduce the cross subsidies in next 2-3 years to adhere to the
provisions of Tariff Policy.
Further, once the cross-subsidy level has been reduced to be within +20%, there is no
mandate under the Act or Tariff Policy to reduce it further. The criteria of ± 20 % of the average cost
of supply for all the categories including subsidised categories depends upon the consumption mix
of the Licensee. However, in case of the Petitioner, the consumption mix is skewed towards
subsidising categories having almost two third of total sales, while the consumption by subsidised
categories is around one third of the total consumption. Therefore, in case of Petitioner, though the
tariff for all the subsidising categories have been within 120% of the overall average cost of supply
of the Petitioner, the average tariff for some of the subsidised categories is less than 80% of the
overall average cost of supply of the Petitioner.
Hon’ble Appellate Tribunal of Electricity, in its Judgment dated February 28, 2012, in
6. Tariff Rationalsation, Tariff Design and Related Issues
Uttarakhand Electricity Regulatory Commission 249
Appeal No. 159 of 2011 has expressed similar views. The relevant extract given in Para 16 of the
Judgment is reproduced as under:
“... Provision of restricting cross subsidy to +/- 20% in Tariff Policy is applicable to areas where
proportion of both the categories, subsidizing and subsidized, are comparable. The same yard stick
cannot be applied in areas where consumer mix is highly biased in favour on one category.”
6.5 Open Access Charges
Uttarakhand Electricity Regulatory Commission (Terms and Conditions of Intra State Open
Access) Regulations, 2015 inter-alia specify wheeling charges applicable on the customers seeking
open access through distribution system, based on the category/nature of open access these
customers come under in accordance with the Regulations.
In this regard, Regulation 20(2) specifies as under:
“Wheeling charges payable to distribution licensee, by an open access customer for usage of
its system shall be as determined as under:
Wheeling Charges = (ARR–PPC–TC) /(PLSD X365) ( Rs./MW/Day)
Where,
ARR=Annual Revenue Requirement of the distribution licensee for the relevant year
PPC= Total Power Purchase Cost of distribution licensee for the relevant year
TC = Total transmission charges paid by distribution licensee for State and Inter-State
transmission system for the relevant year
PLSD= Total Peak load served by the concerned distribution system for the previous year
Provided Embedded open access consumer shall pay wheeling charges as determined by the
Commission in the following manner:
WC Embedded consumer = WC – [FC*0.85*12*1000/365] (in Rs./MW/day)
Where,
WC Embedded consumer = Net wheeling charges for embedded consumers
WC= Wheeling charges as determined by the Commission in accordance with the
methodology specified in Regulation 20(2) contained in Chapter 5 of these regulations.
FC= Fixed/demand charges in Rs/kVA/month as per rate schedule approved in the Tariff
Order for the relevant year. For the purpose of conversion of kVA into kW power factor of 0.85 has
been taken.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
250 Uttarakhand Electricity Regulatory Commission
Note: In case Wheeling Charges for Embedded consumer worked out as above becomes
negative, such charge shall be zero.”
The PLSD during FY 2015-16 is 2034 MW. Hence, in accordance with the methodology
provided in the aforesaid Regulations, the wheeling charges payable by customers seeking open
access for FY 2016-17 (applicable upto 31st March, 2017) shall be:
Table 6.16 : Wheeling Charges approved for FY 2016-17 Description Rs./MW/day
Wheeling Charges 9804
*“Embedded open access consumers” shall not pay the wheeling charge as above who shall
otherwise pay net wheeling charges calculated in accordance with the methodology specified in the
regulations and the same works out to Rs. 861/MW/day for HT industry consumers and Rs.
8267/MW/day for Non-Domestic consumers. However, where a dedicated distribution system for
open access has been constructed for exclusive use of an open access customer, the wheeling
charges for such dedicated system shall be worked out by the distribution licensee for its respective
system and shall get it approved by the Commission and will be borne entirely by such open access
customer till such time the surplus capacity is allotted and used by other open access customers,
where after, the cost of the above system will be shared on pro-rata basis depending upon open
access capacity allotted to them. Provided that wheeling charges shall not be levied on the open
access customers connected to the transmission system at 132 kV and above voltage levels. The
distribution losses applicable to open access customers for FY 2016-17 shall be the pooled average
system distribution losses, i.e. 15.00% considered in this Order. Cross subsidy surcharge applicable,
in accordance with the regulations, to open access customers for FY 2016-17 have been determined
as Rs. 0.47/kWh for HT industrial consumers and Rs. 0.74/kWh for non-domestic consumers.
The Petitioner is hereby directed that the wheeling charges and cross subsidy surcharge
recovered from open access customers shall be shown separately under the separate head of
income in its ARR/Tariff filings from next year onwards. Further, the Petitioner is directed that
the amount received from PTCUL, in lieu of transmission charges collected by PTCUL from
long/medium term open access customers be shown separately under non-tariff income in the
ARR/Tariff filings from next year onwards and should not be reduced from the Transmission
charges payable to PTCUL.
251 Uttarakhand Electricity Regulatory Commission
7. Review of Commercial Performance of UPCL
7.1 General
Uttarakhand, the 27th State of India was created on 9th November 2000 as the 10th
Himalayan State of the country blessed with abundant natural resources with an approx. 53,483 sq.
km area and presently having a population of approximately 101.17 Lakh. The Electricity
Distribution Network is managed by Uttarakhand Power Corporation Limited (UPCL) the sole
distribution licensee in the State. UPCL, had been entrusted to cater to the Transmission &
Distribution Sectors inherited after the de-merger from UPPCL (erstwhile UPSEB) since 1st April
2001. The Electricity Act, 2003 mandated the separation of Transmission functions under Power
Sector Reforms. Consequently, on 1st June 2004, the Power Transmission Corporation Limited
(PTCUL) was formed to maintain & operate 132 KV & above Transmission Lines & Substations in
the State.
Today UPCL, the sole Power Distribution Utility caters to the Sub –Transmission &
Distribution network which includes Substations & Distribution Lines of 66 KV & below voltages in
13 Districts of Uttarakhand namely Dehradun, Pauri, Tehri, Uttarkashi, Rudraprayag, Chamoli,
Haridwar, Pithoragarh, Bageshwar, Almora, Nainital, Champawat, & Udhamsingh Nagar details of
which are given below in Table 7.1 & 7.2.
Table 7.1: Detail of Sub-stations (S/s) maintained by UPCL as on 31.12.2015
S .No. Name of District 66/11 kV S/s 33/11 kV S/s 11/0.415/11 kV S/s
No. No. of Transformers
Total MVA capacity No. No. of
Transformers Total MVA
capacity No. Total MVA capacity
Kumaon Zone 1 Almora 23 38 122 4046 146.66 2 Bageshwar 8 12 37.5 1706 55.3 3 Nainital 27 47 303 4715 419.07
Total Kumaon Zone 58 97 462.5 10467 621.03 US Nagar Zone
1 US Nagar 47 97 761.5 11386 705.14 2 Pithoragarh 16 25 108.5 3264 107.16 3 Champawat 7 11 45 1278 46.52
Total US Nagar Zone 70 133 915 15928 858.82 Garhwal Zone
1 Chamoli 5 8 58 12 17 65 2013 73.92 2 Dehradun 52 102 691.5 6150 737.97 3 Uttarkashi 10 16 59.05 1716 57.77 4 Pauri 31 50 211 5444 230.33 5 Tehri 14 21 102.5 3482 127.65 6 Rudraprayag 6 7 33 1676 51.07
Total Garhwal Zone 125 213 1162.05 20481 1278.71 Haridwar Zone
1 Haridwar 52 108 863 14701 950.87 Total Haridwar Zone 52 108 863 14701 950.87 Total UPCL 5 8 58 305 551 3402.55 61577 3709.43
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
252 Uttarakhand Electricity Regulatory Commission
Table 7.2: Detail of Lines maintained by UPCL as on 31.12.2015 S .No. Name of District 66 kV line (in km) 33 kV Line
(in km) 11 kV Line
(in km) LT Line (in km)
Kumaon Zone 1. Almora 357.91 3760.23 5580.71 2. Bageshwar 135.8 1578.14 2205.27 3. Nainital 361.9 2691.39 4344.63
Total Kumaon Zone 855.61 8029.76 12130.61 US Nagar Zone
1. US Nagar 526.75 3628.87 4317.68
2. Pithoragarh 69.5 (charged at 33 kV voltage level) 228.72 2803.25 3346.72
3. Champawat 165.87 1647.34 2137.27 Total US Nagar Zone 69.5 921.34 8079.46 9801.67 Garhwal Zone
1. Chamoli 122.26 172 2324.22 3024.32 2. Dehradun 745.93 4437.06 10051.91 3. Uttarkashi 247.6 1485.5 2090.8 4. Pauri 606.44 5099.96 7958.18 5. Tehri 364.38 3796.74 3963.32 6. Rudraprayag 134.44 1240.86 1731.97
Total Garhwal Zone 122.26 2270.79 18384.34 28820.5 Haridwar Zone
1 Haridwar 537 3640.32 4090.71 Total Haridwar Zone 537 3640.32 4090.71 Total UPCL 191.76 4584.74 38133.88 54843.49
The Distribution network of UPCL as on 31st December 2015 contains four Zones namely
Garhwal, Kumaon, Haridwar & Udhamsingh Nagar having total eleven Circles containing 35
Divisions. The State has a distinct advantage over other comparable States as a small number of
consumers consume major share of power for which a Key Consumer Cell (KCC) has been
constituted. Hence a large portion of revenue of the Petitioner comes from these KCC consumers.
There were 17.83 Lakh consumers as on March 2014 and 18.91 Lakh consumers as on March 2015.
This increase of total 1,07,439 consumers during the year was primarily in Domestic category (90%).
The Consumer Mix, Consumption pattern & Revenue pattern for FY 2013-14 & FY 2014-15 are
elaborated below:
7.1.1 Consumer Mix during FY 2013-14 & FY 2014-15
In FY 2013-14, out of the total approximately 17.83 Lakh consumers in the State, there were
87.52%-Domestic consumers, 10.18%-Non-Domestic consumers and only 0.62% consumers of the
Industrial category. It is seen that these industrial (HT+LT Industries) consumers account for
around 56.17% of the total consumption of the State and contribute to about 63% of Petitioner’s
revenue. The following Chart depicts the consumers mix in the State during FY 2013-14.
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 253
CHART 1: Consumer Mix (FY 2013-14)
In FY 2014-15, out of the total approximately 18.91 Lakh consumers in the State, there were
87.64%-Domestic consumers, 10.15%-Non-Domestic consumers and only 0.59% consumers of the
Industrial category. It is seen that these industrial (HT+LT Industries) consumers account for
around 55.46% of the total consumption of the State and contribute to about 62.05% of Petitioner’s
revenue. The following Chart depicts the consumers mix in the State during FY 2014-15.
CHART 2: Consumer Mix (FY 2014-15)
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
254 Uttarakhand Electricity Regulatory Commission
7.1.2 Consumption Pattern during FY 2013-14 & FY 2014-15
In FY 2013-14, it was observed that with respect to the %age of total consumption of the
State, the consumption of Industrial consumers (HT+LT Industries) was 56.17% and for Domestic &
Non-Domestic consumers the consumption was 23.23% & 10.96% respectively. The following Chart
shows the consumption pattern in the State during FY 2013-14.
CHART 3: Consumption Pattern during FY 2013-14
In FY 2014-15, it was observed that with respect to the %age of total consumption of the
State, the consumption of Industrial consumers (HT+LT Industries) was 55.46% and for Domestic &
Non-Domestic consumers the consumption was 23.48% & 11.03% respectively. The following Chart
shows the consumption pattern in the State during FY 2014-15.
CHART 4: Consumption Pattern during FY 2014-15
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 255
Comparison of consumption pattern in FY 2013-14 & FY 2014-15 depicts that %age share of
Industrial consumption has decreased by 0.72%, whereas, %age share of domestic consumption has
increased by 0.25% and the %age share of non-domestic consumption has increased by 0.06%. It has
also been noticed that besides other reasons for decrease in industrial consumption, one of the
primary reasons for this decrease is due to implementation of Open Access Mechanism.
Considering this fact, in case the Petitioner does not improve its performance and ensure the
availability, quality and reliability of power for these consumers, the volume of power being sold by
the Petitioner to this category of consumers may get reduced progressively. Since, Industries are
subsidising consumers, therefore, reduction in revenue from Industries would significantly affect
the commercial viability of the Distribution Business. The following table gives the quantum of
power traded through Exchanges (Open Access) by the Embedded Open Access Consumers.
Table 7.3: Quantum of Power Traded through Open Access Year Quantum of Power Traded through Open Access (MU)
FY 2011-12 10.34 FY 2012-13 100.93 FY 2013-14 281.03 FY 2014-15 181.37
7.1.3 Revenue Pattern during FY 2013-14 & FY 2014-15
With regard to the revenue from sale of energy during FY 2013-14, the contribution of
Industrial consumers was 63.00% [HT Industrial consumers was 59.37%, LT industrial consumers
was 3.63%] and of Domestic consumers were contributing around 15.92%. The following Chart
shows the Revenue Pattern of various consumer categories in the State.
CHART 5: Revenue Mix in FY 2013-14
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
256 Uttarakhand Electricity Regulatory Commission
With regard to the revenue from sale of energy during FY 2014-15, the contribution of
Industrial consumers was 62.05% [HT Industrial consumers was 58.59%, LT industrial consumers
was 3.46%] and of Domestic consumers were contributing around 16.32%. The following Chart
shows the Revenue Pattern of various consumer categories in the State.
CHART 6: Revenue Mix in FY 2014-15
On comparing the revenues of FY 2013-14 and FY 2014-15, it is noticed that the %age
revenue share of Industrial Consumers with respect to the total revenue had decreased by 0.94%
and for domestic & non-domestic consumers had increased by 0.40% & 0.44% respectively.
7.2 Commission’s Analysis and Directions on Commercial Performance
The Commission has been monitoring & reviewing the performance of the Petitioner based
on the information/reports submitted by it. Infact, higher distribution losses in distribution system
are detrimental to financial and commercial viability of the Petitioner. Therefore, analysis of
Petitioner’s performance especially in respect of metering, billing and revenue collection is vital
with focus on reducing the Aggregate Technical and Commercial (AT&C) losses of the Petitioner.
The Commission from its very first Tariff Order has been issuing various directions/Orders in this
regard from time to time. However, the Petitioner has always been non-compliant. The Commission
had, therefore, decided to monitor the commercial performance of the Petitioner in a more
structured way on a monthly basis and, accordingly, various formats were issued to the Petitioner
vide Commission’s letter UERC/7/CL/152/2008-09/284 dated 17.05.2012 with the direction to
submit the above information in these Formats regularly for each month by 15th day of the next
month.
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 257
Despite, the specific directions issued by the Commission in its previous Tariff Orders the
Petitioner had neither been submitting the periodical reports timely nor in accordance with the
prescribed formats.
Going by the past experience of performance monitoring of the Petitioner, the Commission
felt that monitoring should be conducted on Division basis. In order to quantify the improvement
on month on month basis on any of the performance indicators, it is necessary that Division-wise
targets on each parameter be provided by the licensee which would make the whole monitoring
process more meaningful. Hence, the Commission vide its letter no. UERC/5/Tech/112/2014-
15/1622 dated 27.11.2014 issued following revised Commercial Performance Monitoring formats
directing UPCL to submit information on these formats in hard as well as in soft copy (MS-excel file
in CD) on regular basis latest by 25th day of the next month from January, 2015 onwards:
Table 7.4: Revised Formats prescribed by the Commission vide letter dated 27.11.2014
S. No. Description Format 1 No. of Consumers 1 2 Quarterly Targets of NA/NR/IDF/ADF/RDF 2 3 Status of Not Accessible (NA) Consumers (in Percentage) 2(A) 4 Status of Not Read (NR) Consumers (in Percentage) 2(B) 5 Status of Identified Defective Meters (IDF) (in Percentage) 2(C) 6 Status of Appeared Defective Meters (ADF) (in Percentage) 2(D) 7 Status of Reading Defective Meters (RDF) (in Percentage) 2(E)
8 Quarterly Targets of IDF Meters/Mechanical Meters/Un-metered Consumers/Ghost Consumers 3
9 Status of Identified Defective Meters (IDF) 3(A) 10 Status of Un-metered Consumers 3(B) 11 Status of Mechanical Meters 3(C) 12 Status of Ghost Consumers 3(D) 13 Status of NB/SB Cases 4 14 Status of Outstanding Arrears 5 15 MRI Status of KCC Consumers 6 16 Status of Revenue realisation per unit of Energy Sold 7 17 Status of AT&C Losses of UPCL 8
However, the Commission has observed that the Distribution Licensee has again been
inconsistent in furnishing the Commercial Performance Monitoring reports on the aforesaid formats
in hard as well as in soft copy (MS-excel file in CD) on regular basis latest by 25th day of the next
month.
The Commission has also observed that the Petitioner is not co-relating its monthly
Commercial performance Monitoring reports with its submission with regard to compliance status
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
258 Uttarakhand Electricity Regulatory Commission
of the directives issued by the Commission. Numerous anomalies have been observed in past like
the no. of un-metered consumers as on 31.03.2015 were 7031 as per the Petitioner’s submission vide
letter No. 5060/UPCL/RM/B-17 dated 30.11.2015, whereas, the no. of un-metered consumers
indicated in the prescribed Format- 3 (B) as on 31.03.2015 were indicated as 4691. The Commission
has taken a serious view on the same and is of the view that either the Petitioner’s submission in the
Commercial Performance Monitoring reports is incorrect or its submission vide letter No. 5060
dated 30.11.2015 w.r.t. compliance to the Commission’s directions under affidavit is incorrect.
The Commission directs the Petitioner that such wrong reporting/anomalies under
affidavit in its submissions would not be accepted and repetition of such errors may result in
action against the Petitioner under the provisions of Act/Rules/Regulations.
The Commission’s analysis on the information submitted by the Petitioner for the period
April 2015 to December 2015 through its various submissions is being discussed in the following
paragraphs:
7.2.1 Metering
The Commission in its earlier Tariff Orders had been repeatedly giving directions to the
Petitioner to energise new connections as well as unmetered connections, only with the
static/electronic meters and to replace all old mechanical meters with new electronic meters in
accordance with CEA Regulations.
Further, the Commission has observed that the Petitioner has a lackadaisical approach in
furnishing timely and correct report to the Commission in the prescribed formats. The reports
pertaining to various performance parameters on metering and other issues have been analysed and
findings thereof are being discussed below:
7.2.1.1 Status of NA/NR, IDF/ADF/RDF
The Commission vide its Tariff Order dated April 11, 2015, had issued directions to the
Petitioner to take effective steps to reduce the percentage of provisional billing cases namely
NA/NR,IDF/RDF/ADF below 3% and submit an action plan in this regard within two months of
this Order. In this regard, during the meeting held on 22.04.2015 the Commission directed the
Petitioner that Chief Engineer (distribution) of respective Zones should be made responsible for
reduction of the provisional billing cases to achieve the target by March, 2016.
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 259
The Petitioner vide its letter no. 4876/UPCL/RM/M-331 dated 05.11.2015 had submitted
consolidated quarterly targets for NA/NR, IDF/ADF/RDF in the prescribed Format-2.
A meeting was held on 28.10.2015 pertaining to status of Defective meters in the Petitioner’s
network. The Commission had directed Director (Operations) to furnish a detailed monitorable
Action Plan latest by 30.11.2015, failing which appropriate action against Director (Operations)
under the provisions of the electricity Act, 2003 would be taken holding him personally responsible
for non-compliance of the Commission’s Orders/Regulations.
In this regard, the Petitioner vide its letter no. 2942/D(O)/UPCL/C-4 dated 01.12.2015
requested the Commission for allowing it time extension upto 31.03.2016 for achieving defective
meter percentage to 3% in plain areas and 31.03.2017 for hill areas. The Commission vide its letter
no. 1596 dated 22.01.2016 allowed the Petitioner to achieve a target of 3% defective meters upto
31.03.2016 in Plain areas and upto 30.09.2016 in the Hill areas.
The Commission has observed that total provisional billing cases namely NA/NR,
RDF/ADF/IDF cases furnished in prescribed formats 2(A), 2(B), 2(C), 2(D) & 2(E) for FY 2015-16 are
still at alarmingly high percentages vis-a-vis total number of consumers as shown in the Table given
below:
Table 7.5: Status of Provisional Billing Viz. NA/NR/IDF/ADF/RDF
Status As on 31st March 2013
As on 31st March 2014
As on 31st March 2015
As on 31st December 2015
NA (%) 2.5 3.3 4.09 3.35 NR (%) 6.6 5.7 4.79 3.68 IDF (%) 11.9 8.6 7.59 6.66 ADF (%) 0.7 0.5 0.35 0.00 RDF (%) 0.8 1.0 1.62 1.41 Total (%) 22.5 19.2 18.44 15.1 Total Billed Consumers (Nos.) 1647224 1664159 1742507 1802589
From the above table, it is observed that though there is a reduction in total percentage of
NA/NR, IDF/ADF/RDF cases, however, the decrease in trend in FY 2015-16 (upto 31st December
2015) is not adequate as per the requirement of the Regulations and directions. Moreover, it is also
observed that the percentage of provisional billing cases is around 15% as on 31.12.2015 and the
Petitioner in its action plan dated 01.12.2015 has only submitted % target achievement of defective
meters in the State, as discussed above. Since defective meters is one of the constituents of
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
260 Uttarakhand Electricity Regulatory Commission
provisional billing and constitute only a portion of such billing basis therefore, it can be said that the
Petitioner has to put extra efforts to bring the overall provisional billing percentage to 3% in plain as
well as hill areas of the State. The Commission is of the view that despite numerous directives
issued to the Petitioner for reducing and bringing the provisional billing cases within 3%, the
Petitioner has not even reached to a level of 3% for NA/NR cases and still 7.03% NA/NR cases are
there as on 31.12.2015. Therefore, taking a considerate view on the same, the Commission directs
the Petitioner to reduce the percentage NA/NR cases to below 2% in both Hill & Plain area of the
State latest by 31.12.2016.
7.2.1.2 Replacement of Improper, Non-Functional, Stop/Stuck up defective meters (referred to as
Identified defective meters (IDF))
In this regard, the Commission vide its Tariff Order dated 11.04.2015 had directed the
Petitioner, to incorporate logic in its billing software for such bill basis namely NA/NR,
IDF/ADF/RDF in accordance with The Electricity Supply Code & Standard of Performance
Regulations of the Commission. The Commission had also directed the Petitioner to restrict the
percentage of Defective meters (IDF) to 3% in accordance with the Regulations by 30th September,
2015.
In compliance to the same, the Petitioner in its submission for compliance of directives has
submitted that the billing of NA/NR, IDF/ADF/RDF cases are being done as per the provisions of
The Electricity Supply Code and Tariff Order issued by the Commission.
Circle-wise number of defective meters reported by the Petitioner in the prescribed format
3(A) is shown in the table given below:
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 261
Table 7.6: Status of Defective Meters
S. No. Name of Circle
No. of Defective
Meters as on 31.03.2013
No. of Defective
Meters as on 31.03.2014
No. of Defective
Meters as on 31.03.2015
No. of Defective
Meters as on 31.12.2015
1. EDC Dehradun (R) 23166 19278 17263 7458 2. EDC Roorkee 12127 13182 11048 8993 3. EDC Haridwar 16715 9705 7217 6252 4. EDC Srinagar 36515 40586 43236 34202 5. EDC Dehradun 9162 4250 551 556 6. EDC Kashipur 9984 4017 1947 1220 7. EDC Rudrapur 27221 16950 12293 9433 8. EDC Ranikhet 36056 24320 30095 10414 9. EDC Haldwani 25260 10430 8641 6953
10. EDC Tehri - - - 18473 11. EDC Pithoragarh - - - 16144
Total 196206 142718 132291 120098
From the above Table, it can be seen that the Petitioner had managed to reduce 10,427 &
12,193 number of defective meters in FY 2014-15 & FY 2015-16 (upto December, 2015) respectively.
It is an admitted fact that by expeditious replacement of defective meters on the basis of well
laid down defective meter replacement programme, the Petitioner will not only be able to contain
this menace but will also comply with the provisions of SoP Regulations.
As already discussed at para 7.2.1.1, the Commission has directed the Petitioner to achieve a
target of 3% defective meters upto 31.03.2016 in Plain areas and upto 30.09.2016 in the Hill areas.
The Commission has observed that the status as on 31.12.2015 is not encouraging as still 120098
defective meters exists in Petitioner’s network and taking a considerate view the Petitioner is
directed to restrict percentage defective meters (IDF) to 3% in plain areas upto 31.09.2016 and
upto 30.12.2016 in Hill areas of the State, failing which appropriate action under the
Act/Rules/Regulations would be taken against the Petitioner for the continued non-compliance
of the directions of the Commission.
7.2.1.3 Replacement of Mechanical Meters
The Commission vide its Order dated April 11, 2015 had directed Petitioner to consolidate
its complete database for mechanical meters including R-APDRP covered towns and submit correct
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
262 Uttarakhand Electricity Regulatory Commission
reports to the Commission latest by 30th June, 2015 and replace all the existing mechanical meters by
static/electronic meters by 31st December, 2015.
The Petitioner in its submission vide letter no. 206/UPCL/RM/B-17 dated 25.01.2016 with
regard to compliance of directives had stated that for the period from April, 2015 to November,
2015 a total of 23,293 mechanical meters have been replaced with electronic meters and the balance
mechanical meters shall be replaced during the control period from FY 2016-17 to FY 2018-19.
However, as per status of mechanical meters as on December, 2015 given in the below table, still a
staggering figure of 1,28,947 numbers of mechanical meters exist in Petitioner’s network.
The status of mechanical meters furnished by the Petitioner in the prescribed format 3(C) is
given below:-
Table 7.7: Status of Mechanical Meters
Status As on 31st
March 2012
As on 31st March 2013
As on 31st March 2014
As on 31st March 2015
As on 31st December
2015 Balance Mechanical Meters to be replaced by Electronic Meters
214693 199730 183005 152560 128947
From the above Table, it can be seen that the rate of replacement of mechanical meters by
electronic meters is extremely slow. It is an established fact that by replacing the mechanical meters
with static/electronic meters, the Petitioner will not only comply with the prevailing SoP
Regulations but also will have more accurate/precise recording of its billed energy. Therefore, the
Petitioner will have incentive in terms of augmentation of its revenue if it takes all necessary steps
for replacing all remaining mechanical meters including those not covered under R-APDRP/IPDS
funded schemes in a planned time-bound program. The Petitioner during the discussions on this
matter has submitted that priority is given for replacement of defective meters due to which rate of
replacement of Mechanical meters is not encouraging. To this the Commission is of the view that
the Petitioner cannot absolve itself from complying with the provisions of the CEA Regulations on
meters and directives issued by the Commission in this regard from time to time on the pretext that
it is presently focusing more on replacement of defective meters than replacement of mechanical
meters.
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 263
Therefore, the Commission directs Petitioner to replace all the existing mechanical meters
by static/electronic meters by 31st December, 2016 & consolidate its complete database for
mechanical meters including areas not covered under R-APDRP/IPDS Schemes.
7.2.1.4 Ghost/Fictitious Consumers
The Commission in its previous Tariff Orders, had directed the Petitioner for identifying and
writing off ghost/fictitious consumers from its billing database under a transparent policy framed
by it.
The Petitioner vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that
it has targeted to settle these connections during FY 2016-17. Further, it has submitted that they
have prepared a draft policy for Write Off of Bad & Doubtful Debts and have identified Bad &
Doubtful Arrears amounting to Rs. 417.32 Crore which has been targeted to be settled during FY
2016-17.
The status of Ghost/Fictitious consumers furnished by the Petitioner in the prescribed
format 3(D) is given below:
Table 7.8: Status of Ghost/Fictitious Consumers
Status As on
31st March 2013
As on 31st March
2014
As on 31st March
2015
As on 31st December
2015 Nos. of Ghost/Fictitious Consumers 1368 1135 892 733
However, from the above table, it can be seen that the Petitioner has not made any concerted
efforts in identifying and writing off such consumers from its billing database. The Commission is
of the view that there is an urgent need for identifying and writing off such consumers from its
billing database as existence of such consumers in the database prevents proper energy accounting
resulting in erroneous figures of Aggregate Technical & Commercial losses (AT&C losses).
The Commission is of the view that as the Petitioner has drafted a policy for Write Off of
Bad & Doubtful Debts which would also include the arrears on account of ghost/fictitious/non-
existent consumers. Therefore, the Petitioner should expeditiously identify and Write Off
ghost/fictitious/non-existent consumers from its billing database under a transparent policy.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
264 Uttarakhand Electricity Regulatory Commission
The Petitioner is directed to write off ghost/fictitious/non-existent consumers from its
billing database under a transparent policy framed by the Petitioner latest by 30th September,
2016.
7.2.1.5 Un-metered Consumers
The Commission vide its Tariff Order dated April 10, 2014, had directed the Petitioner to
achieve 100% metering by 30th September, 2014 and submit its compliance report to the
Commission by 30th October, 2014. Further, the Commission had categorically stated that no tariffs
has been prescribed for unmetered consumers/connections from FY 2015-16 onwards and
therefore, failure to ensure 100% metering would entail no billing to unmetered consumers.
The Petitioner vide its letters No. 4592/UPCL/RM/C-11 dated 12.10.2015 &
5060/UPCL/RM/B-17 dated 30.11.2015 had submitted that the number of unmetered connections
as on 31.03.2015 were 7031, whereas, from the below table it can be observed that status of un-
metered consumers as on 31.03.2015 were 4691. Further, the Petitioner in its submission vide letter
No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that there are 1085 un-metered
connections as on 27.12.2015, whereas, in prescribed Format- 3 (B) of Commercial performance
Monitoring reports, the Petitioner has submitted that the no. of un-metered connections as on
31.12.2015 were 70 as mentioned in the table given below.
Table 7.9: Status of Unmetered Consumers
Status As on 3/14
As on 3/15
As on 4/15
As on 5/15
As on 6/15
As on 7/15
As on 8/15
As on 9/15
As on 10/15
As on 11/15
As on 12/15
Nos. of Un-metered Consumers
6542 4691 3980 2013 346 240 206 201 199 197 70
From the above Table, it is inferred that though Petitioner has been able to reduce the
number of the un-metered consumers, however, it has still failed to achieve 100% metering as per
the directions of the Commission vide its tariff order dated 11.04.2015.
The Commission is of the view that the Petitioner has adopted a callous approach in
submitting its figures for un-metered consumers which differ from submission to submission and as
the Commission in its Tariff Order dated 10.04.2014 had stated that no tariff for un-metered
connection from FY 2015-16 shall be prescribed and failure to ensure 100% metering would entail no
billing to unmetered consumers. Therefore, the Commission reiterates its views expressed in the
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 265
aforesaid Tariff Order with regard to elimination of un-metered consumers and is of the view that
the presence of the un-metered consumers in the Petitioner’s network are a liability to it and are
add-ons to its Aggregate Technical & Commercial (AT&C) Losses. Moreover, the same is violation
of the provisions of Section 55 of the Electricity Act, 2003.
7.2.2 Billing
The Commission, vide its earlier Tariff Orders, and various directions issued from time to
time in this regard has been directing the Petitioner to improve its billing, bill distribution and
revenue collection system. It is noted that the Petitioner has made a beginning in this direction and
has developed a system for online view/payment of electricity bill for its consumers which has not
only benefitted the consumers of the state but also has improved the billing mechanism of the
Petitioner. However, the Commission is of the view that still a lot of scope for improvement in
billing, bill distribution and bill collection system is required at Petitioner’s end.
7.2.2.1 NB & SB Cases
The Commission, in its Tariff Order dated 11.04.2015, had directed the Petitioner to liquidate
and finalise NB/SB cases and set a target of realisation from at least 25% of these cases within 6
months from the date of issuance of this Order.
The Petitioner vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that
they have prepared a draft policy for Write Off of Bad & Doubtful Debts and they have targeted to
settle these connections during FY 2016-17.
Petitioner’s submission in the prescribed Format- 4 of Commercial Performance Report
pertaining to Not Billed (NB) and Stop Billed (SB) is being presented in the Table given below:
Table 7.10: Status of NB & SB Cases
Status As on 03/13
As on 03/14
As on 03/15
As on 12/15
No. of NB/SB Cases NB 62800 139614 144480 154825 SB 74660
From the above table it is evident that the no. of NB/SB cases increased by 3.49% in FY 2014-
15 and 7.16% in FY 2015-16 (upto December, 2015) which indicates that the Petitioner has shown its
least interest in reducing the no. of NB/SB cases. The Commission had categorically directed it to
realise atleast 25% of such cases whereas, the trend shows that such cases are increasing on year-on-
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
266 Uttarakhand Electricity Regulatory Commission
year basis which clearly indicates that the Petitioner has failed to comply with the directions of the
Commission.
Accordingly, the Petitioner is hereby again directed to liquidate and finalise at least 25%
of the NB/SB cases latest by 30.09.2016, failing which appropriate action under the
Act/Rules/Regulations would be taken against the Petitioner for the continued non-compliance
of the directions of the Commission.
7.2.2.2 Outstanding Arrears
The Commission, through its earlier Tariff Orders and various other Orders issued from
time to time, had given directions to expedite recovery of arrears, considering that this parameter
directly inflicts Petitioner’s financial and commercial viability.
The Commission in its Tariff Order dated 11.04.2015 had directed Petitioner to make sincere
efforts in mobilizing its resources to continuously make efforts throughout the year for collection of
Arrears under a structured programme besides taking corrective actions against the habitual
defaulters.
The Petitioner vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that
Division-wise targets have been fixed for collection of Revenue Arrears during FY 2015-16 and till
November, 2015 arrear collected from Non-Government categories was Rs. 83.99 Crore.
The status of Outstanding Arrears furnished by the Petitioner in the prescribed Format- 5 is
given below:-
Table 7.11: Status of Outstanding Arrears. Description As on 03/13 As on 03/14 As on 03/15 As on 12/15
Arrear No. Amount (Rs. Lac) No. Amount
(Rs. Lac) No. Amount (Rs. Lac) No. Amount
(Rs. Lac) Arrear>=5 Lac 774 19563 714 25794 1141 49782 1477 60275 1=<Arrear<5 Lac 4260 7989 4306 7747 5538 10136 5896 10710 0.5 Lac=<Arrear<1 Lac 13237 8179 15401 10056 15449 10475 14961 10231
0.1 Lac=<Arrear<0.5 Lac 59115 13673 75696 16140 88900 18846 99991 20592
0.05 Lac=<Arrear<0.1 Lac
46703 3318 60664 4308 69730 4951 79982 5587
Total 124089 52722 156781 64044 180758 94190 202307 107395
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 267
From the above Table, it is evident that the Petitioner has not been able to reduce number of
arrear cases and the same are increasing on year-on-year basis and has reached to an all time high of
202307 in FY 2015-16 (upto December 2015).
The Commission is of the view that the Petitioner has been lackadaisical towards collection
of arrears and lacks seriousness in laying down a planned programme/roadmap. This is a grave
concern for the Petitioner and may weed away the Petitioner’s financial viability since 2.02 Lakh
cases of arrears have been pending as on December, 2015 with a staggering amount of Rs. 107395
Lakh pending recovery by the Petitioner.
The comparison of Outstanding Arrears furnished by the Petitioner in the above table vis-a-
vis Outstanding Arrears shown in Commercial Diary report i.e. CS-4 is given below:-
Table 7.12: Comparison of Outstanding Arrears. Description Total Arrear in Rs. Crore
Commercial Performance Monitoring report as on 31.03.2015 (excluding Arrears of amount below Rs. 5,000) 941.90
Commercial Performance Monitoring report as on 31.12.2015 (excluding Arrears of amount below Rs. 5,000) 1073.95
CS-4 report as on 31.03.2015 (including Arrears of amount below Rs. 5,000) 2147.25
CS-4 report as on 31.12.2015 (including Arrears of amount below Rs. 5,000) 2618.42
From the above Table, it has been observed that the Petitioner has not made enough efforts
in claiming its arrears in FY 2015-16 (upto December, 2015) due to which the total arrear to be
recovered as on 31.12.2015 as per CS-4 report is Rs. 2618.42 Crore i.e. almost 50% of its Annual
Revenue requirement. Further, from the above table, it is observed that total amount of arrears
below Rs. 5000 to be recovered by the Petitioner as on 31.03.2015 & 31.12.2015 were Rs. 1205.34
Crore & Rs. 1544.46 Crore respectively, which shows that the Petitioner is not only failing in
collecting its high arrear amount but also failing in collecting the low arrear amount (below Rs.
5000). The Commission is of the view that the Petitioner has to understand the gravity of the
situation otherwise the financial viability of its distribution business would be under serious threat.
This by all standards in any commercial organization is not healthy for its growth and reflects an
indifferent approach in receivable management.
Therefore, the Commission hereby directs Petitioner to make sincere efforts in
mobilizing its resources to continuously make efforts throughout the year for collection of
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
268 Uttarakhand Electricity Regulatory Commission
Arrears under a structured receivable management programme besides taking corrective actions
against the habitual defaulters.The Commission also directs the Petitioner to lay down standard
procedure for receivables management and submit to the Commission within one month of
issuance of this Order.
7.2.2.3 Load Factor of KCC Consumers
The Commission in its Tariff Order dated 11.04.2015 had directed the Petitioner that KCC
consumers having less load factor should be closely monitored and average consumption pattern
and abnormality in consumption pattern should be checked and duly analysed. The Commission
had also directed Petitioner to check KCC consumers who are repeatedly exceeding their
sanctioned/contracted demand and take corrective action in such cases.
The Petitioner vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that
the analysis of load factor are regularly being done at its KCC Billing Centres for load factors less
than 10%, load factor of steel units less than 50%, load factor of ice factories during season less than
70%, load factor of pulp & paper industry less than 50%, load factor of stone crushers less than 40%,
consumption variation analysis (less than 50% from previous month) and access demand for last 3
billing cycles.
The load factor of the KCC consumers, as submitted by the Petitioner in the prescribed
Format-6 of Commercial Performance Monitoring Report has been shown in Table given below:
Table 7.13: Status of KCC Consumers Description As on 03/13 As on 03/14 As on 03/15 As on 12/15 Total KCC Consumers 16939 18668 19997 20736 *Abnormal cases 2257 2554 2709 2948 L.F<10% 6884 7513 8430 8973 L.F>10% 10055 11155 11567 11763
*Abnormal cases- Consumers exceeding sanctioned demand, Consumers having CT, PT by-pass, Tamper Report, unbalanced Tamper Report & any other Tamper Report.
From the above table, it can observed that as on December, 2015, number of consumers
having load factor less that 10% were 8973, which is around 43.27% of the total number of KCC
consumers. To this the Commission is of the view that the consumers having load factor less than
10% are in alarmingly high numbers. Moreover, 2948 consumers which is 14.22% of the total
number of KCC consumers are covered under abnormal cases out of which majorly comprise of
consumers who have exceeded their sanctioned/contracted demand.
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 269
The Commission is of the view that the Petitioner has total billed consumer base of about 18
Lakh consumers in the State, out of which 20736 consumers (Industrial category consumers having
load 5 kW & above and Commercial category consumers having load 10 kW & above) as on
31.12.2015, have been identified as Key Consumers (KCC). These key consumers which are only
about 1% of the total consumer base of the Petitioner contribute nearly 70% of its total annual
revenues.
Therefore, the Commission hereby directs the Petitioner that KCC consumers having less
load factor should be closely monitored and average consumption pattern and abnormality in
consumption pattern should be checked and duly analysed. The Commission also directs
Petitioner to check KCC consumers who are repeatedly exceeding their sanctioned/contracted
demand and take corrective action in such cases.
7.2.2.4 Status of Revenue realisation per unit sold
The Commission in its Tariff Order dated 11.04.2015 had directed the Petitioner to take
immediate steps to frame a time-bound programme along with laying down standard procedure for
realising pending arrears and accordingly a report on the action taken, arrears realised, arrears
remaining outstanding and reasons for the same should be submitted to the Commission.
The Petitioner vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that
Division-wise and month-wise revenue arrear collection targets have been fixed for FY 2015-16.
Moreover, daily revenue collection monitoring at sub division level is being done at Corporate
Office and Field officers of the Petitioner have been instructed to disconnect the supply of
defaulting consumers alongwith disconnection of all high value consumers in case of non-payment
of undisputed dues. In this regard, the information provided by the Petitioner in the prescribed
Format- 7 is given below:
Table 7.14: Status of Revenue realisation per unit sold
Year Sold
Energy (MU)
Collection (Rs. Lac)
Average Realization Rate
(Rs./unit)
Average Power Purchase Cost per
Unit sold (Rs./unit)
Approved /Trued-up Average Cost of Supply (Rs/Unit)
FY 2012-13 8577.01 346873.32 4.04 3.78 4.23 FY 2013-14 9065.02 387651.15 4.28 3.58 4.32 FY 2014-15 9685.16 418388 4.32 3.76 4.08 FY 2015-16 (December 2015) 7754.25 308885 3.98 - -
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
270 Uttarakhand Electricity Regulatory Commission
From the above Table it has been observed that the average realization [collection/unit] is
marginally below the overall average cost of supply of the Petitioner except in FY 2014-15 which
reveals that the Petitioner was not even realizing its average cost of supply in FY 2012-13 & FY 2013-
14. However, in FY 2014-15 the Petitioner was able to comfortably recover its average power
purchase cost & average cost of supply. The Commission feels that the Petitioner should
consistently make efforts for maximizing its revenue realization and minimizing its average cost of
Supply so that financial viability of its business is not threatened.
Therefore, the Commission directs the Petitioner to frame a time-bound programme for
realisation of pending arrears/dues and submit a report on the action taken for realisation of
arrears, amount of arrears realised, arrears remaining outstanding and reasons for non-realisation
of these arrears/dues should be submitted to the Commission within three months of the
issuance of this Order.
7.2.3 Billing and Bill Collection System
Taking cognizance of various complaints received from the consumers to the Commission in
writing and also during public hearing, it has been observed that generally the consumers are either
not getting their bills on time or getting wrong bills. This reflects that Petitioner’s bill generation
and bill distribution system needs to be strengthened with proper checks & balances. The
Commission had earlier specially directed the Petitioner to explore alternative bill collection means
and modes such as Cheque drop boxes at Banks, on-line payment facility including use of
credit/debit cards through IT applications in consumer services. The Commission had nominated
an Expert Committee to check the Bill collection arrangements with respect to the directives issued
by the Commission in its Order dated 01.09.2005. The Expert Committee had submitted in its report
that despite Commission imposing heavy consolidated penalty of Rs. 1,00,000 and recurring
additional penalty of Rs. 2,500 per day on UPCL vide its Order dated 01.09.2005 for non-compliance
of its directions with respect to bill collection system, not much has improved except for new Bill
Collection Centres constructed under R-APDRP schemes which are relatively clean and have all the
basic facilities for the consumer. The Committee also submitted that all other Bill Collection Centres
were lacking in basic conveniences, be it cleanliness, be it proper drinking water facility, proper
sitting arrangement or clean and hygienic toilets. The Petitioner cannot run away from its
responsibility of scientifically establishing adequate number of Bill Collection Centres/outlets so
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 271
that consumers need not to travel more than 1 Km in depositing the bills besides keeping the Bill
Collection Centres consumer friendly and attractive with all basic conveniences so that the
consumers do not avoid them.
The Commission in its Order dated 21.01.2015 had categorically directed MD, UPCL to
submit, within one and a half months, a comprehensive action plan alongwith time lines, for
compliance of the directions of the Commission in the matter of Bill Collection System issued in its
Order dated 01.09.2005 distinctly for Rural and Urban areas across the State. In this regard, UPCL
vide its letter No. 4258/UPCL/RMC-9 dated 16.09.2015 submitted its comprehensive Action Plan.
The Petitioner vide its letter No. 1010/UPCL/Comm/CSC dated 19.03.2015 had submitted
to the Commission details of proposal of Common Service Center E-Governance Services India
Limited [under the National e-Governance Plan (NeGP) formulated by the Department of
Electronics and Information Technology (DEITY), Ministry of Communication and Information
Technology, Government of India] for enabling collection of electricity bills through approximately
2056 numbers Common Service Center (CSCs) as front end points both in rural and urban areas and
requested the Commission to give the post facto approval regarding agreement with Common
Service Center E-Governance Services India Limited for providing online electricity bill payment
collection through CSCs in Uttarakhand so that cost incurred for same, may be incorporated in ARR
by the Petitioner. In this regard the Commission directed the Petitioner to submit a proposal
including the number of consumers estimated by the Petitioner who would avail this facility,
charges which would be payable to CSC on such estimation, for the ensuing FY 2015-16 and
ascertaining the impact of such agreement on A&G expenses of Petitioner by 15.04.2015.
The Commission in its Tariff Order dated 11.04.2015 had observed that the consumer
services viz. online payment, payment through debit/credit card etc. can be easily availed by the
urban consumers and would be very handy, however, for the consumers residing in the rural areas
the Petitioner will have to provide other options like bill collection facilities at rural branches of the
Banks, payment facility at CSCs, sub-post offices in rural areas etc. in addition to the above bill
collection & payment facilities. Therefore, the Petitioner should make concerted efforts to put in
place such systems which are friendly as well as conducive for the consumers residing in rural areas
of the State. Further, the Commission directed the Petitioner to comply with the directions issued in
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
272 Uttarakhand Electricity Regulatory Commission
the Commission’s Order dated 21.01.2015 and furnish an Action Plan in the matter of Bill Collection
System distinctly for Rural and Urban areas across the State.
A meeting was held on 28.10.2015 regarding the Bill Collection System. The Commission
observed that the licensee has summarily failed to comply with the directions/Orders of the
Commission in the matter of Bill Collection System. Thereafter, the Commission vide its Order
dated 07.01.2016 in the matter of waiver and refund of penalty imposed by the Commission vide
Order dated 01.09.2005 had taken a lenient view and directed the Petitioner to submit bi-monthly
report of action taken to augment and upgrade its Bill Collection System, submit monthly reports
on the status of no. of CSCs integrated during the month latest by 15th day of next month and
submit a comprehensive Action Plan latest by 25.01.2016. However, no submission in this regard
has been furnished by the Petitioner till date.
The Commission has observed that the Petitioner has factually failed to comply with the
directions issued in the Commission’s Order dated 01.09.2005 and 07.01.2016. Therefore, as a last
attempt to induce the Petitioner to work in right earnest for meeting the requirement of the
Commission’s Order dated 01.09.2005, the Commission directs the Petitioner to comply with the
directions issued in the Commission’s Order dated 07.01.2016 in the matter of Bill Collection
System, failing which appropriate action under the Act/Rules/Regulations would be taken
against the Petitioner for the continued non-compliance of the directions of the Commission.
The Petitioner vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016 had submitted that
an agreement has been executed between Common Service Centre E-Governance Services India
Ltd., New Delhi and UPCL. Under this agreement CSC will collect payment of electricity bills from
the consumers in various locations mainly in remote and rural areas of the State. At present there
are approx. 1800 functional CSCs in the State, which are expected to go upto 4000 which if
integrated with Petitioner’s billing system shall immensely help the electricity consumers residing
at remote areas of the State. The Commission is of the view that since a large number of CSCs are to
be integrated with UPCL’s billing system for extending the bill collection facility to the consumers
of the State, the Commission directs the Petitioner to expedite integrating CSCs available in State
with its billing system under the agreement executed between UPCL & Common Service Centre
E-Governance Services India Ltd., New Delhi.
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 273
7.3 Energy Audit
The Commission in its earlier Tariff Orders had been reiterating its direction for conducting
the energy audit of 11 kV feeders and submit the audit report before the Commission. Moreover,
the Commission in its Tariff Order dated 11.04.2015 had directed the Petitioner to provide meters at
each feeder, ‘T’ points, DTs & consumers in the entire network for efficient energy auditing of the
whole network or part of the network area and thereafter, start conducting energy audit on
periodical basis and submit action taken report to the Commission on quarterly basis.
A meeting was held on 28.10.2015 with regard to voltage-wise cost of supply. The
Commission had directed the Petitioner to submit the status of metering at various voltage levels,
DTs and at consumer level latest by 15.11.2015. In this regard, the Petitioner submitted vide its letter
No. 2941 dated 01.11.2015 that the metering at 33 kV voltage level shall be completed upto
31.08.2016. However, the Commission has found the Petitioner’s submission as incomplete and had
given further directions to the Petitioner for complying with the directions issued w.r.t. voltage-
wise cost of supply as per meeting held on 28.10.2015.
The Petitioner in its submission vide its letter No. 206/UPCL/RM/B-17 dated 25.01.2016
pertaining to compliance of directives reiterated the points as submitted vide letter No. 2941 dated
01.11.2015. In this regard, the Commission is of the view that the certain vital issues like metering,
voltage-wise cost of supply and energy audit are inter-related and priority should be given to make
a robust metering system which would eventually help in correct energy audit and determining the
voltage-wise cost of supply. Therefore, the Petitioner is directed to provide metering at each
feeder, ‘T’ points, DTs and consumers in its distribution network so that effective energy
auditing can be done and proper energy accounting can throw-up several actionable issues
which, when addressed, will result in marked improvement in distribution losses.
Further, the Commission also directs the Petitioner to submit the quarterly progress
report with regard to metering at each feeder, ‘T’ points, DTs and consumers in its network.
7.4 AT&C Losses From the above comprehensive analysis of metering, billing & collection activities of the
Petitioner, it is evident that these functions of the Petitioner still need lot of improvement. The
AT&C losses of the Petitioner are around 30.06% as on December, 2015. The reason for such high
AT&C loss is primarily high distribution losses and low collection efficiency of the Petitioner till
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
274 Uttarakhand Electricity Regulatory Commission
December, 2015. The Commission, vide its Order dated 19.12.2014, had given investment approval
for the project covering the works covered under Part-‘B’ of Restructured-Accelerated Power
Development & Reform Program of Ministry of Power, Government of India for reduction of AT&C
losses to the extent of 15%. Further, the Commission in its aforesaid Order had categorically
directed the Petitioner to ensure completion of the R-APDRP works within the specified time lines
and also to achieve the specified target for reduction of AT&C losses to the extent of 15% in the
selected towns within the stipulated timeframe for availing the benefits of conversion of loan into
grant. In case the Petitioner fails to do so, the servicing cost/cost of the loan in whole or part may
not be allowed as pass through in the ARR. Similar directions were issued by the Commission in its
Order dated 02.02.2015 in the matter of approval for the investment on the SCADA /DMS Project of
Dehradun town covered under Part-‘A’ of Restructured-Accelerated Power Development & Reform
Program. Therefore, the Commission is of the view that with the above linkage of cost of funding
with the AT&C loss achievement, this program can be construed as a double edged sword, which
might cause adverse financial impact in case the Petitioner fails to obtain required reduction in
AT&C losses of the target area.
The status of AT&C losses of UPCL for the various financial years have been shown in the
Table given below:
Table 7.15: Status of AT&C Losses of UPCL
Year
Inpu
t Ene
rgy
(MU
)
Ener
gy S
old
(MU
)
Ass
essm
ent (
Rs
Lac)
Col
lect
ion
(Rs
Lac)
Dis
trib
utio
n Lo
ss (%
)
App
rove
d D
istr
ibut
ion
Loss
(%)
Col
lect
ion
Effi
cien
cy
(%)
Act
ual A
T&C
Los
s (%
)
Com
pute
d A
T&C
loss
es
(Tar
iff O
rder
) (%
) FY 2011-12 10310.64 8252.72 315899 292757 19.96 18.00 92.67 25.82 20.46 FY 2012-13 10789.11 8577.01 356995.3 346873.3 20.50 17.00 97.16 22.76 19.49 FY 2013-14 11216.31 9065.02 393412.4 387651.2 19.18 16.00 98.54 20.36 18.10 FY 2014-15 11888.23 9685.16 418940 418388 18.53 15.50 99.87 18.64 17.19 FY 2015-16 (upto Dec,15) 9534.91 7754.25 359140 308885 18.68 15.00 86.01 30.06 16.28
It is evident that in the above Table, the Petitioner’s distribution loss levels are higher than
approved levels. Further, the actual AT&C losses for above period are higher than AT&C losses
computed on the basis of approved level of distribution losses & collection efficiency of respective
Tariff Orders. Had the Petitioner achieved the targets as approved by the Commission, it would
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 275
have led the Petitioner towards achieving sound financial position resulting in better quality of
service for the consumers.
It is also apparent that Petitioner, in order to substantially reduce its AT&C losses, needs to
concentrate on the domestic and non-domestic consumers and reduce the distribution losses at LT
level. The Commission would also like to point out that reduction in distribution losses by the
Petitioner, is on account of the share of HT consumption in the State. The trend of HT consumption
in the State is depicted below:
Chart 7: HT Consumer Sales as % of Total Sales
From the above chart, it can be seen that there is a reduction in HT sales in FY 2014-15. This
is primarily due to some power being taken through open access which was around 181.37 MU.
Also this could be due to slow down in economy and load shedding. On long term basis, this might
have an adverse impact on tariff of subsidized consumers viz. PTW, Domestic etc. since the amount
of cross subsidy cannot be increased beyond a limit as per National Tariff Policy.
The trend of losses in other category of consumers (excluding HT consumers) is shown in
the Chart given below:
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
276 Uttarakhand Electricity Regulatory Commission
Chart 8: AT&C Loss in other category of consumers (excluding HT consumers)
It is observed that for past 3 years virtually there has been no reduction in losses of other
category of consumers. It is evident that Petitioner has not put in serious efforts in reducing AT&C
losses for other categories, thereby, failing to bring these losses within acceptable limits. Further, to
reduce the distribution losses at LT level and to achieve loss level in acceptable limits, the Petitioner
should take up the following works at the earliest:
1. The Petitioner must replace all mechanical meters in a time-bound manner in all the
divisions on a war footing. It is a known fact that the cost incurred in purchasing the
electronic meter shall be recovered within no time as there shall be substantial increase in
the revenue of the Petitioner.
2. The Petitioner must remove all ghost/fictitious/non-existent consumers from its billing
database.
3. The Petitioner must conduct planned regular actions for early recovery of outstanding
arrears.
4. The Petitioner must analyse KCC consumers having load factor less than 10% on a regular
basis and lay down mechanism for checking inspection/tamper analysis/condition
monitoring of MRI reports and metering equipments.
5. The Petitioner must ensure that all the meters of the consumers are read and their bills
prepared and distributed within time. The Petitioner shall also ensure that no provisional
7. Review of Commercial Performance of UPCL
Uttarakhand Electricity Regulatory Commission 277
bills namely NA/NR are issued for more than two billing cycles in accordance with the
provision of Electricity Supply Code Regulation, 2007. Divisional head must be held
accountable for not controlling provisional billings. The Petitioner should make efforts to
always issue computerized bills to its consumers requiring no human intervention.
6. The Petitioner should prepare a time bound plan/programme to replace all the bare
overhead conductors with insulated aerial bunched conductors (AB conductor) in theft
prone areas alongwith effective monitoring mechanism for its implementation.
7. The Petitioner should also prepare a time bound plan/programme for segregation of rural
feeders into Agriculture and Non-Agriculture load basis which would be an effective
measure for segregation of theft/pilferage of electricity in Agriculture and Non-Agriculture
usage in villages/rural areas.
8. The Commission has observed that the collection efficiency with respect to realization of
arrears/dues from the Government Departments has been very low and it is showing no
signs of improvement. The Petitioner should make extra efforts to get the arrears realised
from the defaulting Government departments. The Commission is of the view that the
Petitioner should implement the pre-paid metering so that revenue recovery can be
enhanced and problems related to accumulation of arrears is resolved.
9. The Petitioner have to ensure that meters are installed at each point of energy accounting
and are kept in proper working condition.
10. The Petitioner should also develop GIS based consumer indexing database in areas other
then the areas covered under R-APDRP, which shall be helpful in providing prompt services
to consumer and shall be helpful in planning the new connections, transformer
augmentation, phase change, localising fault, supply restoration and other services to
consumers necessarily provided by any distribution utility having consumer services
orientation as its vision & mission.
7.5 Conclusion
After analyzing the data related to the Petitioner’s Commercial Performance, it is concluded
that the Petitioner has to take immediate action in reducing the unmetered/ghost/mechanical
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
278 Uttarakhand Electricity Regulatory Commission
meters/NA/NR/IDF cases which are adversely inflicting upon the Petitioner’s commercial &
financial viability.
The performance improvement can be done by judiciously allocating the responsibilities in
field as well as at Corporate level. Moreover, the Petitioner should understand the significance of
Commercial Performance Monitoring Reporting mechanism and should bring sincerity in its
approach towards it. Further, a sense of belongingness/ownership has to be inculcated in every
employee of the Petitioner’s Organisation.
Further, it is imperative to highlight that the Commercial Performance Reporting
mechanism not only brings transparency in the system but also is an eye-opener for the Petitioner
for taking timely corrective actions. Therefore, authenticity of reports is of paramount importance.
Petitioner is required to strengthen its Commercial Wing so that timely authentic reports are
furnished to the Commission and it shall also help in prompt percolation of information within the
organization which shall be beneficial for the Petitioner as well as for consumers of the State.
Going by the past experience of monitoring performance of the Petitioner, the Commission
is of the view that monitoring should be done Division wise and in order to quantify the
improvement on month on month basis on any of the performance indicators, it is necessary that
Division wise targets on each parameter should be provided by the Petitioner so that the whole
monitoring process is meaningful. Therefore, the Commission vide its letter no.
UERC/5/Tech/112/2014-15/1622 dated 27.11.2014 had issued revised Commercial Performance
Monitoring formats and directed the Petitioner to submit information on the revised formats in
hard as well as soft copy (i.e. MS-excel file in CD) on regular basis, so as to reach to the
Commission latest by 25th day of the following month.
Therefore, the Commission again directs Petitioner to submit monthly Commercial
Performance Monitoring reports strictly in the prescribed formats on regular basis, so as to reach
the Commission latest by 25th day of the following month.
279 Uttarakhand Electricity Regulatory Commission
8. Commission’s Directives
The Commission in its previous Orders had issued a number of specific directions to the
Petitioner with an objective of attaining operational efficiency, efficient manpower deployment and
streamlining the flow of information. These objectives would be beneficial not only for the sector
but also for the Petitioner’s company, both in terms of short and long term perspective. These
directions aim at creating a conducive, competitive and healthy environment for the Petitioner to
provide good quality of electricity supply and service to the consumers of Uttarakhand at optimum
and affordable costs. This Chapter deals with the compliance status and the Commission’s views
thereon on the directives issued vide Tariff Order for FY 2015-16 dated April 11, 2015 as well as the
summary of new directions (given in preceding Chapters of this Order) for compliance and
implementation by the Petitioner.
8.1 Compliance to the Directives Issued in Tariff Order for FY 2015-16 dated
April 11, 2015
8.1.1 Performance Report
The Commission directed the Petitioner to thoroughly check the correctness and validity of
the reports/information being submitted to the Commission and to submit monthly Commercial
Performance Monitoring reports strictly in the prescribed formats on regular basis, so as to reach to
the Commission latest by 25th day of the following month.
Petitioner’s Submissions
The Petitioner submitted that the Commercial Performance Report for the month of July,
2015 and October, 2015 was submitted to the Commission vide its letter no.
4745/UPCL/RM/UERC-10 dated October 23, 2015 and letter no. 5378/UPCL/RM/UERC-10, dated
December 22, 2015 respectively.
The Commission has noted the compliance made by the Petitioner in this regard. The
Commission directs the Petitioner that such wrong reporting/anomalies under affidavit in its
submissions would not be accepted and repetition of such errors may result in action against the
Petitioner under the provisions of Act/Rules/Regulations. (Refer Para 7.2).
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
280 Uttarakhand Electricity Regulatory Commission
The Commission again directs Petitioner to submit monthly Commercial Performance
Monitoring reports strictly in the prescribed formats on regular basis, so as to reach the
Commission latest by 25th day of the following month. (Refer Para 7.5)
8.1.2 Sales
The Commission had directed the Petitioner to analyse the average consumption of the
departmental employees including the reasons for such high consumption based on actual meter
readings and submit the report to the Commission on quarterly basis.
The Petitioner was directed to submit the mechanism for reimbursement of expenses against
electricity consumed by the departmental employees of UPCL within 1 month of the date of the
MYT Order. The Petitioner was also directed to issue instructions to the field offices to record the
sales of the departmental employees based on meter reading and submit compliance of the same
within 1 month of the date of the MYT Order.
The Petitioner was also directed to submit the detailed Action Plan giving timeframe in
which it intends to meter the remaining unmetered consumers within 2 months of the date of the
MYT Order.
Further, the Commission in its Tariff Orders dated April 10, 2014 and April 11, 2015 again
directed the Petitioner to comply with all the above directives and submit the compliance to the
Commission on regular basis.
Petitioner’s Submission
The Petitioner submitted that it had constituted a committee to identify the status of
departmental employees and pensioners of UJVN Ltd., PTCUL and UPCL availing supply of
electricity at the concessional rates specified by the respective department. The findings of the
Committee are that the 7973 no. of employees of UPCL, 753 no. of PTCUL and 3718 no. of
employees of UJVN Ltd. are availing the electricity at departmental tariff. The Petitioner submitted
that in the month of March, 2015, 718 no. of employees/pensioners of UPCL/PTCUL/UJVN Ltd.
were billed through the billing software of UPCL and their average consumption per employee was
320 units. For the period from November, 2001 to March, 2015, the billed amount against the above
employees was assessed as Rs. 135.93 Crore for UPCL employees, Rs. 10.18 Crore for PTCUL
employees and Rs. 62.25 Crore for UJVN Ltd. employees. The Petitioner submitted that in its Board
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 281
Meeting held on September 30, 2015 it was agreed to recover the above amount in monthly
instalments of Rs. 10 Crore and Rs. 2 Crore from UJVN Ltd. and PTCUL respectively and the
recovery is being made.
As regards the mechanism for reimbursement of expenses against electricity consumed by
the departmental employees, the Petitioner submitted that its employees are being given the facility
of departmental electricity connection since the existence of UPSEB. Under this facility, a fixed
lump-sum amount is charged from the employees according to their designation towards electricity
charges for electricity supplied to them. Section 23(7) of the Uttar Pradesh Electricity Reforms Act,
1999 provides that the terms and conditions of service of the personnel shall not be less favourable
to the terms and conditions which were applicable before the transfer. The benefits for employees
/pensioners as provided in Section 12(b)(ii) of the Uttar Pradesh Reform Transfer Scheme, 2000
include concessional rate of electricity to the extent it is not inferior to that existing before January
14, 2000. The rates and charges for this category are in adherence to the statutory provisions. As
UPCL is the successor entity of UPPCL, the above legal provisions are applicable to it also. The
copies of O.M. No. 1714/UPCL/RM/L-99 and No. 1715/UPCL/RM/L-99 dated December 23, 2009
issued in the matter have been submitted to the Commission.
The Petitioner submitted that the number of unmetered connection as on December 27, 2015
is 1085 which are in the Pithoragarah Circle in the area which was maintained and operated earlier
by UREDA/UJVN Ltd. The Petitioner submitted that status of metering of unmetered connections
is 7031 as on March 31, 2015 and 2046 as on August 31, 2015.
The Commission directs the Petitioner to issue instructions to the field offices to record
the sales of the departmental employees based on meter reading and submit compliance of the
same alongwith each APR/Tariff Petition.
The Zonal Chiefs, the Circle Chief and the Executive Engineers are hereby directed to
examine the data pointed out with reference to their Divisions for FY 2014-15 and submit the
justification to the Commission within 45 days of the date of Order on the above discrepancies
failing which action may be initiated against them individually by the Commission under
Section 142 of the Electricity Act, 2003.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
282 Uttarakhand Electricity Regulatory Commission
8.1.3 Load Shedding
The Commission directed the Petitioner to obtain the prior approval of the Commission for
load shedding to be carried out continuously for certain number of hours in a day for 15 or more
days.
Petitioner’s Submission
The Petitioner submitted that the rostering policy was approved in its Board of Directors
meeting held on July 23, 2015.
The Petitioner further submitted that it has prepared its power cut policy, which may be
shown as follows:-
1. Commonly, there is no powercut in the state of Uttarakhand.
2. In case of demand more than available energy, Non availability of
Consigned/Distribution Asset within or outside the state, etc , in such type of
emergency conditions the Power cut in the state will be according to the following
priority as shown below:
Table 8.1: Rostering Policy as submitted by the Petitioner S.No. Industrial Area Other Areas 1. Steel business/Furnace Business Rural Plain Region 2. Industries not opting for continuous supply Small Urban Plain Region 3. Industries Opted for continuous Supply Large Urban Plain Region 4. -- Hilly region 5. -- Capital For other categories the time and day of Power cut for operation will be decided by Director (Operation) considering the demand of electricity for respective categories.
3. No load shedding will be applicable for all tourist/Pilgrimage site.
4. The frequent Power cut in any region will not exceed 14 days constantly in that
region.
5. All industries are ensured to have minimum of 18 hours of electricity per day in a
Month.
The Petitioner further submitted that no load shedding has been carried out in any area
continuously for certain number of hours in a day for 15 or more days.
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 283
The Commission has taken note of the Petitioner’s reply.The Commission, hereby, once
again directs the Petitioner to obtain the prior approval of the Commission for load shedding to
be carried out continuously for certain number of hours in a day for 15 or more days.
8.1.4 AT&C Losses
The Commission directed the Petitioner to regularly incorporate monthly target level
alongside actual level of Distribution losses as directed by the Commission vide its Order dated
04.03.2013 in the Petitioner’s future submissions.
Petitioner’s Submissions
The Petitioner submitted that it has prepared the Efficiency Plan with Division wise targets
in respect of the following activities for reduction of losses:
(i) Replacement of mechanical meters and defective meters
(ii) Metering of unmetered connections
(iii) Bringing three phase meters outside the premises of the consumers
(iv) Double metering on HT connections
(v) Checking of all three phase domestic connections with a view to detect supply used
for commercial purposes
(vi) Collection of non-government arrears
(vii) Checking of connections to detect and prevent unauthorised use of electricity
(viii) Laying of LT cable
The Petitioner submitted that the Corporate Office fixed the Revenue Collection Targets for
each division for FY 2015-16 separately for Non-Government and Government categories with a
view to achieve 15% reduction in AT&C Losses of Non-Government categories.
The Commission has taken note of the compliance made by the Petitioner.The Commission
hereby directs the Petitioner to regularly incorporate monthly target level alongside actual level
of Distribution losses as directed by the Commission vide its Order dated 04.03.2013 in the
Petitioner’s future submissions.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
284 Uttarakhand Electricity Regulatory Commission
8.1.5 Power Purchase Quantum and Cost
The Commission directed the Petitioner to restrict the net drawal from the grid within its
drawal schedules whenever the system frequency is below 49.90 Hz in order to ensure grid
discipline. (Refer Para 4.4.9.7)
The Commission, further, directed the Petitioner to seek prior approval of the Commission,
in case the variation in power purchase quantum or power purchase cost in any quarter exceeds by
more than 5% of the approved power purchase quantum and cost for the respective quarter worked
out on pro-rata basis from the total approved quantity and cost for FY 2015-16 as indicated in the
Table 4.16 of this Order, failing which, the Commission may disallow such additional power
purchase cost while truing up the ARR for FY 2015-16.
Petitioner’s Submissions
The Petitioner submitted that it is restricting its net drawal from the grid within the net
drawal schedules whenever the system frequency is below 49.90 Hz to comply with the directions
of the Commission and in the interest of grid discipline.
The Petitioner submitted that the details of actual power purchases for the quarters ending
June, 2015 and September, 2015 have been submitted to the Commission explaining the reasons for
excess power purchase cost and sought approval for the same. The details of power purchases for
the quarter ending December, 2015 are being compiled and approval shall be sought from the
Commission as per the norms.
The Commission hereby once againdirects the Petitioner to restrict the net drawal from
the grid within its drawal schedules in order to ensure grid discipline.
The Commission, further, directs the Petitioner to seek prior approval of the Commission,
in case the variation in power purchase quantum or power purchase cost in any quarter exceeds
by more than 5% of the approved power purchase quantum and cost for the respective quarter
worked out on pro-rata basis from the total approved quantity and cost for FY 2016-17 as
indicated in the Table 5.6 of this Order, failing which, the Commission may disallow such
additional power purchase cost while truing up the ARR for FY 2016-17.
The Petitioner is directed to prepare its power purchase plan for the next three years and
initiate the bidding process to meet the deficit, if any. The Petitioner is directed to submit an
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 285
action plan in this regard within 15 days of the date of Order. The Petitioner is also directed to
ensure compliance of the Regulations issued by the Commission from time to time, failing
which any consequent liability would be to the account of the Petitioner.
8.1.6 Fixed Assets Register
The Commission directed the Petitioner to expedite the process and submit the updated
Fixed Assets Register within 3 months of the date of the Order.
Petitioner’s Submissions
The Petitioner submitted that Fixed Assets Register for the period upto FY 2012-13have been
submitted to the Commission. Further, the work of preparation of Fixed Assets Register for FY
2013-14 and FY 2014-15 is in progress.
The Commission hereby once again directs the Petitioner to expedite the process and
submit the Fixed Assets Register updated upto 31.3.2015 within 3 months of the date of the Order
and Fixed Assets Register updated upto 31.3.2016 within 6 months of the date of this Order.
8.1.7 Depreciation
The Commission directed the Petitioner to maintain proper Fixed Asset Register showing
amongst others the date of capitalisation of each asset, their location, alongwith the accumulated
depreciation on the same and submit the same along with the next filing and also claim
depreciation based on the rates as specified in the Regulations for each class of asset.
Petitioner’s Submissions
The Petitioner submitted that it is very difficult task now to prepare the Fixed Assets
Register showing the date and location of each Asset existed as on November 9, 2001 and created
thereafter. The Petitioner requested the Commission to exempt from this direction.
The Commission does not find it appropriate to waive off the directive in this regard. The
Commission directs the Petitioner to maintain proper Fixed Asset Register showing amongst
others the date of capitalisation of each asset, their location, alongwith the accumulated
depreciation on the same and submit the same along with the next Tariff filings and also claim
depreciation based on the rates as specified in the Regulations for each class of asset.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
286 Uttarakhand Electricity Regulatory Commission
8.1.8 Return on Equity
The Commission directed the Petitioner to look into the issue of creating long term assets
from current liability and take appropriate remedial action for correcting this practice. Further, the
Petitioner is directed to expedite the matter and submit the details of assets created by mode other
than loan/grants/subsidies/ deposit works/consumer contributions from FY 2001-02 onwards and
submit the source of such finances duly validating the same from their cash flow and fund flow
statements from FY 2001-02 within 3 months of issue of this Order.
Petitioner’s Submissions
The Petitioner submitted that the sought information is being compiled and shall be
submitted to the Commission.
The Commission takes a serious note of the non-compliance of the Petitioner to the
Commission’s directive in this regard.The Commission once again directs the Petitioner to look
into the issue of creating long term assets from current liability and take appropriate remedial
action for correcting this practice. Further, the Petitioner is directed to expedite the matter and
submit the details of assets created by mode other than loan/grants/subsidies/ deposit
works/consumer contributions from FY 2001-02 onwards and submit the source of such finances
duly validating the same from their cash flow and fund flow statements from FY 2001-02 within
3 months of issue of this Order.
8.1.9 Employee Expenses
UPCL was directed to expedite the recruitment process and also submit a quarterly status
report to the Commission detailing the steps taken by it in this regard and also the status of the
recruitments planned.
Further, the Commission cautioned UPCL that any saving in the employee expenses on this
account would not be shared with UPCL. Also, UPCL is advised to exercise caution in incurring the
expenditure as the Commission would allow the expenses during truing up after examining the
prudence of the same.
Petitioner’s Submissions
The Petitioner submitted the status of direct recruitment as shown in the Table given below:
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 287
Table 8.2: Summary of Direct Recruitment Group Position No. Updated Status Remarks
B Accounts Officer 11 Advertisement has been released. Submission of online application shall commence from January 22, 2016
B Law Officer 2
B Assistant Engineer (E&M) 47
B Assistant Engineer (Civil) 7
C Junior Engineer (E&M) 13 Appointment letters issued to 11 no. selected candidates
8 no. selected candidates have joined UPCL
C Junior Engineer (Civil) 20 Appointment letters issued to 16 no. selected candidates
Date of joining has been fixed on January 27, 2016 to January 28, 2016
C Office Assistant-III 77 Written exam held on September 20, 2015 by Uttarakhand Pravidhik Shiksha Parishad
Further course of action under progress
C Technician Grade-2 496
Advertisement has been released on December 8, 2013 by Uttarakhand Pravidhik Shiksha Parishad. Recruitment process withheld as per GoU direction till further Orders
Matter pending before Hon’ble High Court, Nainital
C Assistant Accountant 57 Appointment letters issued to 45 no. selected candidates
35 no. selected candidates have joined UPCL
C Assistance Store Keeper 20 17 no. of candidates were selected
Issue of appointment letters is under process
Sub-total 750 C Junior Engineer (E&M) 11 Adhiyachan has been sent to
Uttarakhand Adhinastha Sewa Chayan Ayog vide letter no. 10585 dated September 10, 2015
C Junior Engineer (Civil) 1
UPCL is directed to expedite the recruitment process and also submit a quarterly status
report to the Commission detailing the steps taken by it in this regard and also the status of the
recruitments planned.
8.1.10 Bad & Doubtful Debts
The Commission directed the Petitioner to finalise the policy and submit the same for
Commission’s perusal within three months from the date of this Order.
Petitioner’s Submissions
The Petitioner submitted that as per the direction of the Audit Committee, the draft write off
policy was sent to the Institute of Chartered Accountants in India for examination in view of all
Accounting and Auditing Standards, Legal Provisions and Practices followed in other companies.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
288 Uttarakhand Electricity Regulatory Commission
In reply, the Institute replied that the issue cannot be considered by the Committee in view of Rule
3 of the Advisory Service Rules of the Committee.
The Petitioner submitted that it has identified bad and doubtful arrears amounting to Rs.
417.32 Crore against 1,43,579 consumers and the list of consumers has been prepared amount wise
and age wise. The Petitioner submitted that it has targeted to settle this debt amount during FY
2016-17 taking steps as per rules for recovery of the debt and by writing off irrecoverable amount.
The Petitioner is directed to finalise the Policy within three month of the date of Order
and submit the same for approval of the Commission.
UPCL is directed to submit the basis of arriving at the ageing of debtors within one
month of the date of Order.
8.1.11 Reliability Indices
The Commission directed the Petitioner to comply with the provision of the Regulations and
submit the target indices along with the next tariff filing. The Commission, also, directed the
Petitioner to submit monthly report on Reliability Indices in the format prescribed by the
Commission vide letter no. 1200/UERC/Tech/9/2010 dated 28.09.2010.
Petitioner’s Submissions
The Petitioner submitted that the reliability indices are being regularly submitted the
Commission. The report on the reliability indices for the month of August, 2015 has been submitted
to the Commission vide letter no. 4715/UPCL/RM/SM dated October 20, 2015.
The Commission has noted the Petitioner’s reply in this regard. The Commission directs the
Petitioner to submit monthly report on Reliability Indices in the format prescribed by the
Commission vide letter no. 1200/UERC/Tech/9/2010 dated 28.09.2010. These reports should also
be submitted in MS-Excel soft form.
8.1.12 Voltage wise Cost of Supply
The Commission had directed the Petitioner to submit status of metering at various voltage
levels, Distribution Transformers and at consumer level within one month from the date of Tariff
Order for FY 2014-15 along with the action plan for completion of the metering at various points
necessary for assessment of voltage wise losses namely sub-station, DTs, and at consumer level
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 289
along with the present status of metering at various voltage levels within one month of the Tariff
Order for FY 2014-15. The Petitioner was also directed to submit the detailed progress report
indicating the status of the work of energy audit and key findings on quarterly basis within 15 days
of the end of each quarter. The Commission further directed the Petitioner to submit the action plan
along with the timelines by which the Petitioner will be completing the work as per the action plan,
within one month of issue of Tariff Order for FY 2015-16.
Petitioner’s Submissions
The Petitioner submitted that 33/11 kV substation and feeders emanating from such
substations are 295 and 1355 respectively and all these substations and feeders are metered. The
Petitioner submitted that 5665 DTs covered under 31 towns of R-APDRP are metered.
The Petitioner submitted that in the first phase, metering at all the input and output points
at 33 kV level will be ensured first. The Petitioner submitted that it has identified all the points
where metering is required at 33 kV voltage level and a detailed action plan has been submitted
vide its letter no. 2941/D(O)/UPCL/C-4 dated November 1, 2015.
The Commission has taken note of the submissions of the Petitioner. The Commission
directs the Petitioner to submit the action plan along with the timelines by which the Petitioner
will be completing the work as per the action plan, within one month of issue of this Order.
8.1.13 Demand Side Management Measures
The Commission directed the Petitioner to submit the report on various Demand Side
Management measures at regular quarterly intervals to the Commission.
Petitioner’s Submissions
The Petitioner submitted that GoUhad approved a scheme on October 31, 2015 for
distribution of LED bulbs in the State under which all domestic consumers and non-domestic
consumers (upto 10 kW) shall be provided three LED bulbs at a price of Rs. 110 per bulb. The
Petitioner submitted the salient features of the Scheme as follows:
(i) 55,65,000 LED bulbs shall be distributed at an estimated cost of Rs. 61.22 Crore.
(ii) 75% cost in respect of BPL consumers and 25% cost in respect of non-domestic
consumers having monthly consumption of 100 units shall be borne by GoU.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
290 Uttarakhand Electricity Regulatory Commission
(iii) The cost to be borne by GoU is Rs. 15.55 Crore.
(iv) The cost of the LED bulbs shall be recovered in 10 monthly or 5 bi-monthly
instalments.
(v) This Scheme was approved by the Commission.
(vi) The Scheme has been launched in the State and the work of distribution of LED bulbs
has been targeted to be completed by March, 2016.
The Commission has taken note of the submissions of the Petitioner.The Commission
directs the Petitioner to submit the report on various Demand Side Management measures at
regular quarterly intervals to the Commission.
8.1.14 Electrical Accidents
The Commission directs the Petitioner to submit the data on year wise fatal accidents for last
4 years, i.e. from FY 2011-12 to FY 2014-15 within 3 months from the date of this Order.
Petitioner’s Submissions
The Petitioner submitted that the number of fatal accidents are 45 for FY 2011-12, 50 for FY
2012-13, 84 for FY 2013-14 and 34 for FY 2014-15.
8.1.15 Issues raised by the Petitioner again despite Commission’s ruling in previous Tariff
Orders
The Commission directed the Petitioner to not raise such issues again in the subsequent
ARR and Tariff Petitions on which the Commission have already taken the decision and given its
ruling in the previous Tariff Orders, failing which, the Commission may reject the Petition upfront.
Petitioner’s Submissions
The Petitioner submitted that the MYT filings have been done keeping in view the directions
issued by the Commission and provisions of Law in the matter.
The Commission has noted the Petitioner’s reply in this regard. The Commission would
like to clarify that the directives issued by the Commission are also in accordance with the
provisions of law. The Commission directs the Petitioner to not raise such issues again in the
subsequent ARR and Tariff Petitions on which the Commission have already taken the decision
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 291
and given its ruling in the previous Tariff Orders, failing which, the Commission may reject the
Petition upfront.
8.1.16 Additional Surcharge on account of Re-determination of Tariff for FY 2009-10 and
FY 2010-11
The Commission directed the Petitioner to submit the total recovery made through
additional surcharge on account of re-determination of tariff of FY 2009-10 in FY 2011-12 to FY 2013-
14 separately along with the APR Petition for FY 2015-16.
The Commission directedthe Petitionerto submit the total recovery made through additional
surcharge on account of re-determination of tariff of FY 2010-11 for FY 2013-14 to FY 2015-16 along
with the APR Petition for FY 2015-16.
Petitioner’s Submissions
The Petitioner submitted the details of additional surcharge
8.1.17 Load Shedding
The Petitioner submitted that UPCL’s 11 kV Bagwara Feeder is about 40 years old and the
length of the same is 35 km. With a view to solve the problem and to provide continuous supply to
the consumers of the area, the Petitioner decided to construct a new 11 kV feeder having length of
2.5 km. The work has been awarded and a line of 27 poles is completed so far and the work is in
progress. The Commission directed the Petitioner to expedite this work and submit the report to
the Commission within 3 months from the date of this Order.
Petitioner’s Submissions
The Petitioner submitted that a new 11 kV Bagwara Industrial Feeder has been energized on
May 11, 2015 and the industrial consumers of Fulsunga and nearby villages shall be benefited
because of this.
8.1.18 Metering of unmetered connections
The Commission directed the Petitioner to meter all the remaining unmetered connections
immediately and submit the compliance to the Commission latest by 31.05.2015.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
292 Uttarakhand Electricity Regulatory Commission
Petitioner’s Submissions
The Petitioner submitted that the number of unmetered connection as on December 27, 2015
is 1085 which are in the Pithoragarah Circle in the area which was maintained and operated earlier
by UREDA/UJVN Ltd and it is expected to convert these to metered connections before the end of
this Financial Year.
The Commission has taken note of the Petitioner’s reply. The Commission directs the
Petitioner to submit the actual status within one month of date of this Order.
8.1.19 Interest on GPF Trust
The Commission directed the Petitioner to expedite the Audit of Accounts of the trust to
ensure that audit is completed by June 30, 2015 and to submit the audit report to the Commission by
July 31, 2015.
Petitioner’s Submissions
The Petitioner submitted that vide its letter no. 1854/UPCL/RM/C-11 dated May 1, 2015,
the copies of Audited Accounts of UPCL Employees GPF Trust for the period from FY 2002-03 to FY
2009-10. The Petitioner submitted that the work of preparation of Accounts and Audit of the same
for the remaining period is under process and shall be submitted to the Commission.
The Commission has taken note of the compliance made by the Petitioner. The Commission
directs the Petitioner toexpedite the matter to ensure that audit is completed by June 30, 2016 and
to submit the audit report to the Commission by July 31, 2016.
8.1.20 Treatment of Assets sent for repairs
UPCL was directed to submit the year wise reconciliation of the financing of the assets
submitted to the Commission within 6 months of the date of the Order.
The Commission also directed the Petitioner to analyse the capitalisation amount from FY
2001-02 onwards and segregate the same under the following heads:
1. Asset class wise actual capitalisation incurred on creation of new assets;
2. Asset class wise capitalisation on account of receipt of repaired assets,
3. Asset class wise actual asset deletion/written off;
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 293
4. Asset class wise asset deletion on account of an asset being sent for repairs.
Further, the Petitioner should also segregate the associated financing with regard to S.No. 1
to 4, i.e. financing of the asset capitalised and financing of the asset written off. Further, the
Petitioner is required to submit the above information within six months from the date of issue of
this Order and the Petitioner should also submit quarterly status report in this regard.
Petitioner’s Submissions
The Petitioner submitted that the desired information is being prepared and shall be
submitted to the Commission.
The Commission takes a serious note of the non-compliance of the Petitioner in this regard.
The Commission directs the Petitioner to submit the information sought within 3 months from
the date of issue of this Order.
8.1.21 Billing of Departmental Employees
The Petitioner was directed to ensure appropriate modification in its billing software so that
revenue for sale to the departmental employees is recognised at the slab wise rate prescribed for
domestic consumers. The difference between revenue so recognised and actual amount recovered
from its employees be shown as subsidy in its annual accounts. The Commission directed the
Petitioner to expedite the process for collection of information and start the billing as per
Commission’s directive in this regard.
Petitioner’s Submissions
As regards the mechanism for reimbursement of expenses against electricity consumed by
the departmental employees, the Petitioner submitted that its employees are being given the facility
of departmental electricity connection since the existence of UPSEB. Under this facility, a fixed
lump-sum amount is charged from the employees according to their designation towards electricity
charges for electricity supplied to them. Section 23(7) of the Uttar Pradesh Electricity Reforms Act,
1999 provides that the terms and conditions of service of the personnel shall not be less favourable
to the terms and conditions which were applicable before the transfer. The benefits for employees
/pensioners as provided in Section 12(b)(ii) of the Uttar Pradesh Reform Transfer Scheme, 2000
include concessional rate of electricity to the extent it is not inferior to that existing before January
14, 2000. The rates and charges for this category are in adherence to the statutory provisions. As
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
294 Uttarakhand Electricity Regulatory Commission
UPCL is the successor entity of UPPCL, the above legal provisions are applicable to it also. The
copies of O.M. No. 1714/UPCL/RM/L-99 and No. 1715/UPCL/RM/L-99 dated December 23, 2009
issued in the matter have been submitted to the Commission.
8.1.22 Subsidy from GoU for disaster affected areas
The Petitioner was required to maintain a separate account for the sales and revenue data
with respect to subsidy applicable for such consumers. The Commission directed the Petitioner to
submit this information alongwith APR Petition for FY 2015-16.
Petitioner’s Submissions
The Petitioner submitted that as the direction of GoU, the energy consumption bills of the
disaster affected areas amounting to Rs. 9.51 Crore were waived off and GoU had reimbursed Rs.
7.84 Crore to UPCL.
8.1.23 Capitalization of Assets
The Commission re-iterated its direction to seek approval of the Commission before starting
any capital works in accordance with the Regulations, failing which the works not approved by the
Commission would not be considered during truing up.
Petitioner’s Submissions
The Petitioner submitted that filing of petition seeking approval of the Commission for
capital works shall be ensured as per the provisions of Regulations.
8.1.24 Installation of Meter
The Petitioner was required to ensure installation of appropriate meters at the consumer’s
premises, i.e. railway traction sub-station within three months from the date of issue of Tariff Order
for FY 2014-15 for billing purpose. The Commission expressed its displeasure on the compliance
made by UPCL in this regard. UPCL wasdirected to ensure proper compliances as directed by the
Commission.
Petitioner’s Submissions
The Petitioner requested the Commission to consider the submissions already made in this
regard as follows:
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 295
The Petitioner submitted that Regulation 2(2)(a) of the Central Electricity Authority
(Installation and Operation of Meters) Amendment Regulations, 2010 provides that the consumer
meter shall be installed by the distribution licensee to provide the meter either at consumer
premises or outside the consumer premises. Hence, it is the discretion of distribution licensee to
provide the meter either at the consumer premises or outside the consumer premises. UPCL has
installed the consumer meter at Grid S/s i.e., outside the consumer premises.
8.1.25 MCG Charges
The Commission directed that the licensee tenders a certificate under affidavit, that
appropriate modification based on the above have been incorporated in its billing software on or
before June 15, 2015.
Petitioner’s Submissions
The Petitioner submitted that necessary modification has been made in the billing software
based on MCG revised vide the Tariff Order dated April 11, 2015as has been apprised to the
Commission vide the letter no. 3284/UPCL/RM/B-16 dated June 15, 2015.
8.1.26 Issue of Voltage wise Loss
The Commission directed the Petitioner to submit the basis for working out voltage wise
losses alongwith approach & methodology adopted by it within two months from the date of this
Order.
Petitioner’s Submissions
The Petitioner submitted that the sought information has been submitted vide its letter no.
1797/UPCL/RM/B-16 dated April 29, 2015 as follows:
i. As per Regulation 29(2) of the UERC (Terms and Conditions of Intra-State Open
Access) Regulations, 2010, Distribution Losses on Open Access Energy are required
to be calculated by applying the formula ‘Average Distribution Loss = Average
Recovery Rate from HT Industry Category ÷ Average Power Purchase Cost x
Applicable Voltage Rebate’.
ii. As per the Tariff Order dated April 10, 2014, average distribution loss on open access
energy for FY 2014-15 is 16%, average recovery rate from HT Industry Category is
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
296 Uttarakhand Electricity Regulatory Commission
Rs. 4.54/kWh, average power purchase cost is Rs. 3.21/kWh and applicable voltage
rebate at 33 kV is 1.5% and at 132 kV & above is 5%. Accordingly, the distribution
loss on open access energy for FY 2014-15 works out to 13.88% for 33 kV voltage level
and 8.92% for 132 kV & above voltage level.
8.1.27 Power Purchase Expenses (Including Transmission Charges)
The Commission directed the Petitioner to submit the year wise details of the excess
liabilities written off under the head of power purchase as also the complete details and
documentary evidence of unpaid liabilities mentioned in the accounts of FY 2013-14 to the
Commission in the format already sent to it within one month from the date of issue of this Order.
Petitioner’s Submissions
The Petitioner submitted that the sought information has been submitted vide its letter no.
545/UPCL/DGM(F) dated September 23, 2015.
The Commission has dealt with the prior period adjustment in detail in Chapter 5 of this
Order.
The Petitioner is directed to separately claim the cost of the energy returned under
banking during truing up exercise of FY 2015-16 and not show the same as adjustment from the
provisions.
The Commission directs the Petitioner to put in place a mechanism for recording the
arrears paid in an year for submission along with its claim of truing up for the respective year in
the absence of which the Commission shall take an appropriate view regarding the allowable
power purchase cost while carrying out the truing up exercise.
8.1.28 Cost of Deficit Power
The Commission directed the Petitioner to expedite the process of medium term
procurement of power through competitive bidding from FY 2015-16 onwards and submit the
details of steps taken towards same within 3 months from the date of this Order.
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 297
Petitioner’s Submissions
The Petitioner submitted that the medium term procurement of power could not be finalised
due to cancellation of coal blocks at the Central Government level. The bidders who have entered
into long term agreements for supply of power are eligible for fuel supply agreement under the new
Design, Build, Finance, Own and Operate (DBFOO) model of Ministry of Power, Government of
India for procurement of power. IPPs which have executed the fuel supply agreements with
different agencies of Government of India are not eligible for participating in medium term power
procurement. The tariff of medium term procurement of power is higher in comparison to short
term and day ahead market. The tariff discovered in medium term power procurement conducted
in Andhra Pradesh is in the range of Rs. 4.290/kWh to Rs. 6.989/kWh. The Petitioner submitted on
account of the above, it discontinued the process of medium term power procurement.
In view of persistent deficit scenario, the Petitioner should put its sincere efforts to
procure the deficit energy through a mix of long term arrangements, medium term arrangements
and short term purchases optimizing the cost of power purchase and reliable power. Further, the
procurement should be through transparent process of bidding and not on mutual agreements as
has been the practice of UPCL. UPCL is directed to submit a comprehensive plan as to how it
intends to meet the deficit within one month of the date of Order.
8.1.29 RTS-4 (Private Tubewells)
The Commission directed the Petitioner to conduct a study to identify and assess the load
and consumption of thrasher, cane crusher and rice huller consumers and submit its report to the
Commission within 6 months from the date of this Order.
Petitioner’s Submissions
The Petitioner submitted that the study shall be undertaken in the next Financial Year.
The Commission takes a serious note of the non-compliance of the Petitioner.The
Commission directs the Petitioner to conduct a study to identify and assess the load and
consumption of thrasher, cane crusher and rice huller consumers and submit its report to the
Commission within 6 months from the date of this Order.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
298 Uttarakhand Electricity Regulatory Commission
8.1.30 Status of NA/NR, IDF/ADF/RDF
The Commission directed the Petitioner to take effective steps to reduce the percentage of
provisional billing cases namely under NA/NR, IDF/RDF/ADF below 3% and submit an Action
Plan in this regard within 2 months of Tariff Order for FY 2015-16.
Petitioner’s Submissions
The Petitioner submitted that it was directed by the Commission to maintain this percentage
of 3% by March 31, 2016. The Petitioner submitted that vide its letter no. 1827/UPCL/RM/N-39
dated April 30, 2015 it had circulated the Efficiency Plan of the Company for FY 2015-16 to its field
officers which inter-alia includes replacement of all meters lying defective (1,38,331) as on March 31,
2015. The Petitioner submitted that 84,818 defective meters have been replaced till November 2015.
The Commission directs the Petitioner to reduce the percentage NA/NR cases to below 2%
in both Hill & Plain area of the State latest by 31.12.2016.
8.1.31 Replacement of Improper, Non-Functional, Stop/Stuck up defective or IDF Meters
The Commission directed the Petitioner to incorporate logic in its billing software for such
bill basis namely NA/NR, IDF /ADF/RDF in accordance with the Electricity Supply Code &
Standard of Performance Regulations of the Commission. The Commission also directs the
Petitioner to restrict percentage defective meters (IDF) to 3% in accordance with the Regulations by
30th September, 2015.
Petitioner’s Submissions
The Petitioner submitted that vide its letter no. 1827/UPCL/RM/N-39 dated April 30, 2015
it had circulated the Efficiency Plan of the Company for FY 2015-16 to its field officers which inter-
alia includes replacement of all meters lying defective (1,38,331) as on March 31, 2015. The
Petitioner submitted that 84,818 defective meters have been replaced till November 2015.
The Petitioner is directed to restrict percentage defective meters (IDF) to 3% in plain areas
upto 31.09.2016 and upto 30.12.2016 in Hill areas of the State, failing which appropriate action
under the Act/Rules/Regulations would be taken against the Petitioner for the continued non-
compliance of the directions of the Commission.
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 299
8.1.32 Replacement of Mechanical Meters
The Commission directed the Petitioner to replace all the existing electro-mechanical meters
by static/electronic meters by December 31, 2015 and consolidate its complete database for electro-
mechanical meters including R-APDRP covered towns and submit correct reports to the
Commission latest by June 30, 2015.
Petitioner’s Submissions
The Petitioner submitted that vide its letter no. 1827/UPCL/RM/N-39 dated April 30, 2015
it had circulated the Efficiency Plan of the Company for FY 2015-16 to its field officers which inter-
alia includes replacement of all mechanical meters (1,38,331) as on March 31, 2015. The Petitioner
submitted that 23293 mechanical meters have been replaced till November 2015 and the remaining
shall be replaced during FY 2016-17 to FY 2018-19.
The Commission has taken note of the compliance status submitted by the Petitioner.
Therefore, the Commission directs Petitioner to replace all the existing mechanical meters by
static/electronic meters by 31st December, 2016 & consolidate its complete database for
mechanical meters including areas not covered under R-APDRP/IPDS Schemes.
8.1.33 Ghost/Fictitious Consumers
The Commission directed the Petitioner to write off ghost/fictitious/non-existent consumers
from its billing database under a transparent policy framed by the Petitioner latest by September 30,
2015.
Petitioner’s Submissions
The Petitioner submitted that the number of ghost consumers as on June 30, 2015 is 808 as
submitted vide its letter no. 3978/UPCL/RM/UERC-10 dated August 24, 2015. The Petitioner
submitted that these connections shall be settled during FY 2016-17.
The Commission has taken note of the compliance status submitted by the Petitioner. The
Petitioner is directed to write off ghost/fictitious/non-existent consumers from its billing
database under a transparent policy framed by the Petitioner latest by 30th September, 2016.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
300 Uttarakhand Electricity Regulatory Commission
8.1.34 NB & SB Cases
The Commission directed the Petitioner to liquidate and finalise NB/SB cases and set a
target of realisation from at least 25% of these cases within 6 months from the date of issuance of
this Order.
Petitioner’s Submissions
The Petitioner submitted that the number of NB & SB cases as on June 30, 2015 is 1,54,134 as
submitted vide its letter no. 3978/UPCL/RM/UERC-10 dated August 24, 2015.The Petitioner
submitted that these connections shall be settled during FY 2016-17.
The Commission has taken note of the compliance status submitted by the Petitioner.
Accordingly, the Petitioner is hereby again directed to liquidate and finalise at least 25% of the
NB/SB cases latest by 30.09.2016, failing which appropriate action under the
Act/Rules/Regulations would be taken against the Petitioner for the continued non-compliance
of the directions of the Commission.
8.1.35 Outstanding Arrears
The Commission directed the Petitioner to make sincere efforts in mobilizing its resources to
continuously make efforts throughout the year for collection of Arrears under a structured
programme besides taking corrective actions against the habitual defaulters.
Petitioner’s Submissions
The Petitioner submitted the details of Revenue Arrears during FY 2014-15 as follows:
Table 8.3: Details of collection of Revenue Arrears during FY 2014-15 as submitted by the Petitioner (Rs. Crore)
Category KCC Non-KCC Total Domestic 0.56 42.17 42.73 Non-Domestic 13.23 8.18 21.41 Industry 55.73 0.11 55.84 PTW 3.08 3.08 Total 69.52 53.54 123.06
The Petitioner submitted that Rs. 282.63 Crore was collected from the Government
categories during FY 2014-15.The Petitioner submitted that Division wise targets have been fixed for
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 301
collection of Revenue Arrears during FY 2015-16 and the arrears collected from Non-Government
categories till November, 2015 was Rs. 83.99 Crore.
The Commission directs Petitioner to make sincere efforts in mobilizing its resources to
continuously make efforts throughout the year for collection of Arrears under a structured
receivable management programme besides taking corrective actions against the habitual
defaulters.The Commission also directs the Petitioner to lay down standard procedure for
receivables management and submit to the Commission within one month of issuance of this
Order.
8.1.36 Status of KCC Consumers
The Commission directed the Petitioner that the KCC consumers having low load factor
should be closely monitored and average consumption pattern and abnormality in consumption
pattern should be checked and duly analysed. The Commission also directed the Petitioner to check
KCC consumers who are repeatedly exceeding their sanctioned/contracted demand and take
corrective action in such cases.
Petitioner’s Submissions
The Petitioner submitted that the analysis of (i) load factor less than 10%, (ii) load factor of
steel units less than 50%, (iii) load factor of ice factories during season less than 70%, (iv) load factor
of pulp & paper industry less than 50%, (v) load factor of stone crushers less than 40%, (vi)
consumption variation analysis (less than 50% from previous month), (vii) Excess demand for last
three billing cycles,is being carried out at KCC Billing Centre. The Petitioner submitted that the list
of above cases are forwarded to filed units with the direction to check such cases and to take
corrective action in case of any anamoly.
The Commission directs the Petitioner that KCC consumers having less load factor
should be closely monitored and average consumption pattern and abnormality in consumption
pattern should be checked and duly analysed. The Commission also directs Petitioner to check
KCC consumers who are repeatedly exceeding their sanctioned/contracted demand and take
corrective action in such cases.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
302 Uttarakhand Electricity Regulatory Commission
8.1.37 Status of Revenue realisation per unit sold
The Commission directed the Petitioner to take immediate steps to frame a time bound
programme along with laying down standard procedure for realising pending arrears and,
accordingly, a report on the action taken, arrears realised, arrears remaining outstanding and
reasons for the same should be submitted to the Commission within three months of the issuance of
this Order.
Petitioner’s Submissions
The Petitioner submitted that the Division wise and month wise revenue arrear collection
targets totalling to amount of Rs. 150 Crore has been fixed for FY 2015-16 out of which Rs. 83.99
Crore has been collected upto November, 2015. The Petitioner submitted that the daily revenue
collection monitoring at sub division level is being done at Corporate Office. The Petitioner
submitted that the field officers have been instructed to disconnect the supply of defaulting
consumers. The Petitioner submitted that disconnection of all high value consumers is being
ensured in case of non-payment of undisputed electricity dues.
Therefore, the Commission directs the Petitioner to frame a time-bound programme for
realisation of pending arrears/dues and submit a report on the action taken for realisation of
arrears, amount of arrears realised, arrears remaining outstanding and reasons for non-realisation
of these arrears/dues should be submitted to the Commission within three months of the
issuance of this Order.
8.1.38 Billing and Collection System
The Commission directed the Petitioner to comply with the directions issued in the
Commission’s Order dated 21.01.2015 and furnish an Action Plan in the matter of Bill Collection
System distinctly for Rural and Urban areas across the State latest by 01.05.2015.
Petitioner’s Submissions
The Petitioner submitted that an agreement has been executed with common service center
E-Governance Services India Ltd. The Petitioner submitted that under this agreement CSC will
collect payment of electricity bills from the consumers in various locations mainly in remote and
rural areas of the State. The Petitioner submitted that presently 1119 collection centres are operative
and the details of collection as follows:
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 303
Table 8.4: Details of collection as submitted by the Petitioner Month No. of Consumers Amount deposited
(Rs. Lakh) June, 2015 1988 13.43 July, 2015 3149 23.59 August, 2015 4468 31.82 September, 2015 3781 28.29 October, 2015 5778 40.47 November, 2015 5179 35.64 December, 2015 7443 50.52
The Commission directs the Petitioner to comply with the directions issued in the
Commission’s Order dated 07.01.2016 in the matter of Bill Collection System, failing which
appropriate action under the Act/Rules/Regulations would be taken against the Petitioner for the
continued non-compliance of the directions of the Commission.
The Commission directs the Petitioner to expedite integrating CSCs available in State
with its billing system under the agreement executed between UPCL & Common Service Centre
E-Governance Services India Ltd., New Delhi.
8.1.39 Energy Audit
The Commission directed the Petitioner to provide meters at each feeder, ‘T’ points, DTs &
consumers in the entire network for efficient energy auditing of the whole network or part of the
network area and thereafter, start conducting energy audit on periodical basis and submit action
taken report to the Commission on quarterly basis.
Petitioner’s Submissions
The Petitioner submitted that it has identified the all the points where metering is required
at 33 kV voltage level and has submitted a detailed action plan vide its letter no.
2941/D(O)/UPCL/C-4 dated November 1, 2015.
The Petitioner is directed to provide metering at each feeder, ‘T’ points, DTs and
consumers in its distribution network so that effective energy auditing can be done and proper
energy accounting can throw-up several actionable issues which, when addressed, will result in
marked improvement in distribution losses.
Further, the Commission also directs the Petitioner to submit the quarterly progress
report with regard to metering at each feeder, ‘T’ points, DTs and consumers in its network.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
304 Uttarakhand Electricity Regulatory Commission
8.1.40 Abnormal Sales in Public Lamps Category
The Commission directed the Petitioner to examine the same and report to the Commission
the reasons for such high consumption in public lamps within 2 months of the date of the Order.
UPCL is directed to examine the same alongwith the status of billing of fixed charges to public
lamps in other divisions and report to the Commission the reasons for such negligence within 2
months of the date of the Order.
Petitioner’s Submissions
The Petitioner submitted that the matter was examined at Corporate Office and found that
the billing logics in the billing software were found to be correct. The Petitioner submitted that the
field officers have been directed not to repeat such errors in the Commercial Information and it is
being ensured at Corporate Office that such errors are not repeated in the Commercial Diary for the
ensuing months.
8.1.41 Abnormal Sales in Private Tubewell Category
The Commission directed the Petitioner to examine the same and report to the Commission
the status of such consumers within 2 months of the date of the Order.
Petitioner’s Submissions
The Petitioner submitted that the matter was examined at Corporate Office and found that
the billing logics in the billing software were found to be correct. The Petitioner submitted that the
field officers have been directed not to repeat such errors in the Commercial Information and it is
being ensured at Corporate Office that such errors are not repeated in the Commercial Diary for the
ensuing months.
8.1.42 Abnormal Sales in Public Water Works Category
The Commission directed the Petitioner to examine the same and report to the Commission
the reasons for such high consumption in public water works and also the action plan for rectifying
the anomaly within 2 months of the date of the Order. UPCL was also directed to give reasons for
such low average billing rate within two months of the date of the Order.
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 305
UPCL was directed to ensure timely compliances of the directions issued in this regard. The
Commission has also decided to review the monthly performance of UPCL in this regard and,
accordingly, UPCL was also directed to submit the monthly commercial report (SG-IV).
Petitioner’s Submissions
The Petitioner submitted that the matter was examined at Corporate Office and found that
the billing logics in the billing software were found to be correct. The Petitioner submitted that the
field officers have been directed not to repeat such errors in the Commercial Information and it is
being ensured at Corporate Office that such errors are not repeated in the Commercial Diary for the
ensuing months.
8.1.43 Abnormal Sales in LT Industries
The Commission directed the Petitioner to examine the same and report the reasons for such
low revenue alongwith the corrective action taken in this regard, within 2 months of the date of the
Order.
Petitioner’s Submissions
The Petitioner submitted that the matter was examined at Corporate Office and found that
the billing logics in the billing software were found to be correct. The Petitioner submitted that the
field officers have been directed not to repeat such errors in the Commercial Information and it is
being ensured at Corporate Office that such errors are not repeated in the Commercial Diary for the
ensuing months.
8.1.44 Abnormal Sales in HT industries (Upto 1000 kVA)
The Commission directed the Petitioner to examine the same and report the reasons for such
low revenue alongwith the corrective action taken in this regard, within 2 months of the date of the
Order.
Petitioner’s Submissions
The Petitioner submitted that the matter was examined at Corporate Office and found that
the billing logics in the billing software were found to be correct. The Petitioner submitted that the
field officers have been directed not to repeat such errors in the Commercial Information and it is
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
306 Uttarakhand Electricity Regulatory Commission
being ensured at Corporate Office that such errors are not repeated in the Commercial Diary for the
ensuing months.
8.1.45 Abnormal Sales in Mixed Load Category
The Commission directed the Petitioner to examine the same and report the reasons for such
low revenue alongwith the corrective action taken in this regard, within 2 months of the date of the
Order.
Petitioner’s Submissions
The Petitioner submitted that the matter was examined at Corporate Office and found that
the billing logics in the billing software were found to be correct. The Petitioner submitted that the
field officers have been directed not to repeat such errors in the Commercial Information and it is
being ensured at Corporate Office that such errors are not repeated in the Commercial Diary for the
ensuing months.
8.1.46 Transfer of Distribution Business from UJVN Ltd. to UPCL (Reference Para 7.2.22 of
Tariff Order dated 10.04.2014)
The Commission at para 7.2.22 of its Tariff Order dated 10.04.2014 had explicitly directed the
Petitioner to take charge of the distribution business carried out by UJVN Ltd., within 6 months of
this Order and submit bi-monthly status of the compliance on this issue.
However, in absence of significant progress in the matter and indifferent attitude shown by
both the utilities in ensuring the compliance, the matter was further taken up during the 6th Co-
ordination Forum Meeting held on 06.01.2015, in which the Commission had directed Managing
Directors of UJVN Ltd. and UPCL to resolve the matter on top priority.
Further, on reviewing the compliance in this matter, the Commission had taken cognizance
of the slow progress and lackadaisical approach of both the utilities and the matter was taken up
during a joint meeting held with the Petitioner and UJVN Ltd. on 28.10.2015, in which the
Commission had directed that:
“... UJVN Ltd. and UPCL to nominate atleast 02 Officers not below the rank of DGM/SE from their
Organization & submit their joint report for ensuring the compliance of the Commission’s directions
latest by 30.11.2015”
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 307
Accordingly, both the utilities nominated its Officers for ensuring the compliance, however,
despite the above steps of the utilities, it has been observed that entire taking over/handing over of
distribution business has not been taken place. The reasons stated by the Petitioner in its submission
that UJVN Ltd. is not providing the documents pertaining to the consumers to be taken over viz.
Application form, Security deposit, verification details etc. while, UJVN Ltd. in its submission has
stated that the Petitioner has never informed for providing such documents. In this regard, the
Commission is of the view that sufficient time has already been given to both the utilities, therefore,
directs the Petitioner and UJVN Ltd. to comply with the directions of the Commission in all
respect by 30.05.2016 and submit compliance report in the matter by 15.06.2016, failing which
appropriate action shall be initiated against both the utilities in accordance with the provisions
of the Act/Regulations.
8.2 Fresh Directives
8.2.1 Departmental Employees
The Commission also directs the Petitioner to install meters at all its offices and sub-
stations, if not installed, within one month of the date of the Order and submit report to the
Commission by May 15, 2016. (Refer Para 2.20.1.3)
The Commission directs the Petitioner to carry out 100% metering of its departmental
employees, to take regular meter readings and to maintain separate energy account of all its
employees on a monthly basis. The Commission directs the Petitioner to submit a compliance
report of the same within one month of the issuance of this Order. (Refer Para 2.32.7.2)
8.2.2 Metering & Billing
The Commission directs the UPCL to consider the suggestions given by the stakeholders
to improve its metering and billing system. The Commission directs UPCL to provide services to
the Consumers namely restoration of power, voltage fluctuation, metering & billing related etc.
as per Orders/Supply Code/SOP Regulations of the Commission. (Refer Para 2.23.1.3)
8.2.3 Distribution Infrastructure
The Commission directs the Petitioner to strengthen its distribution network. (Refer Para
2.26.1.3)
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
308 Uttarakhand Electricity Regulatory Commission
8.2.4 Quality of Power
The Commission directs UPCL to take adequate steps to improve the quality of supply. In
this regard, the Commission would like to clarify that UPCL’s complaint handling procedures
have been approved by the Commission and are available in the website of the Commission. If
the complaints are not resolved by UPCL internally, the consumers can also lodge their
complaints with the “Consumer Grievance Redressal Forum” functional in the respective
Garhwal and Kumaon Zones of Uttarakhand. (Refer Para 2.28.1.3)
8.2.5 Temporary Connections
The Commission directs the Petitioner to issue instructions to its field/ distribution
division officers to properly plan and take caution while releasing such temporary connections
and submit a compliance report within one month of the issuance of this Order. (Refer Para
2.32.3.2)
8.2.6 Location of Installation of meters
The Commission directs Executive Engineer, EDD Pithoragarh, UPCL is directed to
submit a detailed compliance report on action taken for shifting of the meters to a safer location
in or around the premises within one month of the date of Order. Further, the Commission
directs the Chief Engineer, Rudrapur Zone, UPCL and Executive Engineer, EDD Pithoragarh,
UPCL to take necessary action and submit the compliance report within one month of the date of
the Order. (Refer Para 2.32.4.2)
8.2.7 Load Shedding
The Commission directs the concerned Chief Engineer and Executive Engineer, EDD
Pithoragarh, UPCL to coordinate with the District Administration/Local authorities and resolve
this issue and submit the compliance report within one month of the date of the Order. (Refer
Para 2.32.5.2)
8.2.8 Transfer of Petitioner’s personnel
The Commission directs the Petitioner to lay down a policy in this regard and submit a
compliance report within two month of the issuance of this Order. (Refer Para 2.32.6.2)
8. Commission’s Directions
Uttarakhand Electricity Regulatory Commission 309
8.2.9 Water Tax
The Commission directs the Petitioner to submit all the relevant information along with
supporting documents for substantiating the actual expenses incurred on account of Water Tax,
for FY 2016-17 along with its proposals for True up for FY 2016-17. (Refer Para 5.8)
8.2.10 Prepaid Metering
The Petitioner is directed to submit the data related to the cost of the meter and other
associated equipments to the Commission in the Tafiff proceedings for FY 2017-18. (Refer Para
6.2.3.11)
8.2.11 kVAh Tariffs
The Commission directs the Petitioner to submit the type of meters installed at Public
Lamps, GIS upto 75 kW, and its action plan for installation of Tri-Vector meters capable of
recording both kWh and kVAh consumption in the above referred categories/sub-categories
where such meters have not been installed within 1 month of the issuance of this Tariff Order.
The Commission also directs the Petitioner to take such measures for installation of Tri-vector
meters in other categories/sub-categories of consumers where power factor is poor and tariff is
on kWh basis. (Refer Para 6.2.4)
8.2.12 Open Access Charges
The Petitioner is hereby directed that the wheeling charges and cross subsidy surcharge
recovered from open access customers shall be shown separately under the separate head of
income in its ARR/Tariff filings from next year onwards. Further, the Petitioner is directed that
the amount received from PTCUL, in lieu of transmission charges collected by PTCUL from
long/medium term open access customers be shown separately under non-tariff income in the
ARR/Tariff filings from next year onwards and should not be reduced from the Transmission
charges payable to PTCUL. (Refer Para 6.5)
8.2.13 Power procurement plan
The Petitioner is directed to prepare its power purchase plan for the next three years and
initiate the bidding process to meet the deficit, if any. The Petitioner is directed to submit an
action plan in this regard within 15 days of the date of Order. The Petitioner is also directed to
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
310 Uttarakhand Electricity Regulatory Commission
ensure compliance of the Regulations issued by the Commission from time to time, failing
which any consequent liability would be to the account of the Petitioner.
8.3 Conclusion
Having considered the submissions made by the Petitioner, the responses of various
stakeholders and the relevant provisions of the Electricity Act, 2003 and Regulations of the
Commission, the Commission hereby approves that:
(i) Uttarakhand Power Corporation Ltd., the distribution and retail supply licensee
in the State will be entitled to charge the tariffs from consumers in its licensed
area of supply as given in the Rate Schedule for FY 2016-17 annexed hereto as
Annexure-1. These Tariffs will be effective from April 01, 2016.
(ii) Uttarakhand Power Corporation Ltd., the distribution and retail supply licensee
in the State will realize from consumers of Electricity in the State, miscellaneous
charges as listed out in Annexure- 2 of this Order and shall not recover any other
charge, fee, deposit etc., unless approved by the Commission.
(iii) The above tariffs shall continue to be applicable till revised by the Commission.
The Petitioner shall forward a report on compliance of the directions given in this Order
within the time stipulated for compliance.
(K.P. Singh) Member
(Subhash Kumar) Chairman
311 Uttarakhand Electricity Regulatory Commission
9. Annexures
9.1 Annexure 1: Rate Schedule Effective from 01.04.2016
A. General Conditions of Supply
1. Character of Service
i) Alternating Current 50 Hz., single phase, 230 Volts (with permissible variations) up to a
load of 4 kW.
ii) Alternating Current 50 Hz, three phase, 4 wire, 400 Volts or above (with permissible
variations) for loads above 4 kW depending upon the availability of voltage of supply.
2. Conditions for New Connections
i) Supply to new connections of more than 75 kW (88 kVA) and up to 2550 kW (3000 kVA)
shall be released at 11 kV or above, loads above 2550 kW (3000 kVA) and upto 8500 kW
(10000 kVA) shall be released at 33 kV or above and loads above 8500 kW (10000 kVA)
shall be released at 132 kV or above.
ii) All new connections shall be given with meter conforming to CEA Regulations on
Installation and Operation of Meters.
iii) All new 3 phase connections above 4 kW shall be released with Electronic Tri-vector
Meter having Maximum Demand Indicator.
iv) All new Single Point Bulk Connection shall be given only for Load of more than 75 kW.
v) Consumers having motive loads of more than 5 BHP shall install Shunt Capacitor of
appropriate rating and conforming to BIS specification.
vi) All new connections at HT/EHT should be released only with 3 phase 4 wire meters.
3. Point of Supply
Energy will be supplied to a consumer at a single point.
4. Billing in Defective Meter (ADF/IDF), Meter Not Read/Not Accessible (NA/NR)
and Defective Reading (RDF) Cases
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
312 Uttarakhand Electricity Regulatory Commission
In NA/NR cases, the energy consumption shall be assessed and billed as per average
consumption of last one year average consumption (as per the Electricity Supply Code) which shall
be subject to adjustment when actual reading is taken. Such provisional billing shall not continue
for more than two billing cycles at a stretch. Thereafter, the licensee shall not be entitled to raise
any bill on provisional basis. In case of Appear defective meter (ADF) Identified defective meter
(IDF) and Reading defect (RDF) cases, the consumers shall be billed on the basis of the average
consumption of the past three billing cycles immediately preceding the date of the meter being
found or being reported defective (as per the Electricity Supply Code). These charges shall be
leviable for a maximum period of three months or two billing cycle in case of bi-monthly billing
only during which time the licensee is required to replace the defective meter. Thereafter, the
licensee shall not be entitled to raise any bill without correct meters.
The checking and replacement of defective meter cases namely IDF and ADF and defective
reading cases namely RDF shall be done by the licensee in accordance with Regulation 3.1.4 of the
Electricity Supply Code.
5. Billing in case of domestic metered consumers in rural/hilly areas whose meters
are not being read
For cases relating to domestic metered consumers in rural/hilly areas, where meter reading
is either not being taken regularly or taken randomly over delayed interval of time, the provisional
billing under these circumstances for such consumers shall be done at the normative levels of
consumption as given below, which shall be subject to annual adjustment based on actual meter
reading.
Category Normative Consumption Domestic (Rural-Hilly Areas) 30 kWh/kW/month Domestic (Rural-Other Areas) 50 kWh/kW/month
For this purpose, the contracted load shall be rounded off to next whole number. Billing on
this basis is subject to annual adjustment and the licensee is to ensure meter reading of such
consumers at least once a year.
6. Billing in New Connection or conversion from unmetered to metered Cases
For cases such as new connections or conversion of unmetered to metered connection, where
past reading is not available, the provisional billing shall be done at the normative levels of
9. Annexures
Uttarakhand Electricity Regulatory Commission 313
consumption as given below, which shall be subject to adjustment when actual reading is taken.
Category Normative Consumption Domestic (Urban) 100 kWh/kW/month Domestic (Rural-Hilly Areas) 30 kWh/kW/month Domestic (Rural-Other Areas) 50 kWh/kW/month Non-domestic (Urban) 150 kWh/kW/month Non-domestic (Rural) 100 kWh/kW/month Private Tube Wells 60 kWh/BHP/month Industry LT Industry 150 kWh/kW/month HT Industry 150 kVAh /kVA /month
For this purpose, the contracted load shall be rounded off to next whole number. Billing on
this basis shall continue only for a maximum period of 2 billing cycles, during which the licensee
should ensure actual reading. Thereafter, the licensee shall not be entitled to raise any bill without
correct meter reading. In all other categories, 1st bill shall be raised only on actual reading.
7. Delayed Payment Surcharge (DPS) (for all categories except PTW)
In the event of electricity bill rendered by licensee, not being paid in full within 15 days’
grace period after due date, a surcharge of 1.25% on the principal amount of the bill which has not
been paid, shall be levied from the original due date for each successive month or part thereof until
the payment is made in full without prejudice to the right of the licensee to disconnect the supply in
accordance with Section 56 of the Electricity Act, 2003. The licensee shall clearly indicate in the bill
itself the total amount, including DPS, payable for different dates after the due date, after allowing
for the grace period of 15 days, taking month as the unit as shown exemplified below:
EXAMPLE:
Amount payable by Due date Due Date
Rs. 100/-
1st May 2016
Amount Payable
On or Before 16th May 2016
Rs. 100/-
After 16th May 2016
Rs. 101.25
After 1st June 2016
Rs. 102.50
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
314 Uttarakhand Electricity Regulatory Commission
8. Solar Water Heater rebate
If consumer installs and uses solar water heating system, rebate of Rs. 100/- p.m. for each
100 litre capacity of the system or actual bill for that month whichever is lower shall be given
subject to the condition that consumer gives an affidavit to the licensee to the effect that he has
installed such system, which the licensee shall be free to verify from time to time. If any such claim
is found to be false, in addition to punitive legal action that may be taken against such consumer,
the licensee will recover the total rebate allowed to the consumer with 100% penalty and debar him
from availing such rebate for the next 12 months.
9. Prepaid Metering
Prepaid metering scheme approved by the Commission in this Order shall be applicable. A
rebate of 4% of energy charges for Domestic category (RTS-1 and RTS-1A) and 3% of energy charges
for Other LT consumers shall be allowed to the consumers under the Prepaid Metering Scheme
from the date of installation and operationalisation of Prepaid Meters. However, no rebate shall be
applicable on Part (A) of RTS-10, i.e. Temporary Supply for Illumination & Public Address Needs
and for Independent Advertisement Hoardings. Solar water rebate as provided above in the Rate
Schedule shall be applicable on prepaid consumers also subject to fulfillment of conditions
provided therein.
10. Rebate/surcharge for availing supply at voltage higher/lower than base voltage
(i) For consumers having contracted load upto 75 kW/88 kVA - If the supply is given at
voltage above 400 Volts and upto 11 kV, a rebate of 5% would be admissible on the
Energy Charge.
(ii) For consumers having contracted load above 75 kW/88 kVA – In case the supply is
given at 400 Volts, the consumer shall be required to pay an extra charge of 10% on the
bill amount calculated at the Energy Charge.
(iii) For consumers having contracted load above 75kW/88 kVA – In case of supply at 33
kV the consumer shall receive a rebate of 2.5% on the Energy Charge.
(iv) For consumers having contracted load above 75 kW/88 kVA and receiving supply at
132 kV and above, the consumer shall receive a rebate of 7.5% on the Energy Charge.
9. Annexures
Uttarakhand Electricity Regulatory Commission 315
(v) All voltages mentioned above are nominal rated voltages.
(vi) No rebate or surcharges would be applicable on consumers having pre-paid
connections.
11. Low Power Factor Surcharge (not applicable to Domestic, PTW categories and also
to other categories having kVAh based Tariff)
(i) On the consumers without Electronic Tri Vector Meters who have not installed shunt
capacitors of appropriate ratings and specifications, a surcharge of 5% on the current
energy charges shall be levied.
(ii) On consumers with Electronic Tri Vector Meters, a surcharge of 5% on current energy
charges will be levied for having power factor below 0.85 and upto 0.80 & a surcharge
of 10% of current energy charges will be levied for having power factor below 0.80.
(iii) No surcharge would be applicable on consumers having pre-paid connections.
12. Excess Load/Demand Penalty (Not applicable to Domestic, Snow bound and PTW
categories)
In case of consumers where electronic meters with MDI have been installed, if the maximum
demand recorded in any month exceeds the contracted load/demand, charges for such excess
load/demand shall be levied equal to twice the normal rate of fixed/demand charge as applicable.
Such excess load penalty shall be levied only for the month in which maximum demands exceeds
contracted load. However, no excess load penalty would be applicable on consumers having pre-
paid connections.
Example:
(i) For consumers where fixed charges on the basis of contracted load/demand have been
specified:
Contracted load 30 kW, Maximum Demand 43 kW,
Excess Demand 43-30=13 kW, Rate of Fixed Charges= Rs. 50/kW
Fixed Charges for contracted load = 30 x 50=Rs. 1500
Fixed Charges for excess load = 13x (2 x50) =Rs. 1300
Total Fixed Charges = 1500 +1300= Rs. 2800
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
316 Uttarakhand Electricity Regulatory Commission
(ii) For industrial consumers billed on billable demand:
Contracted demand 2500 kVA, Maximum Demand 2800 kVA, Billable Demand =2800 kVA
Excess Demand =2800-2500=300 kVA, Rate of Demand Charges= Rs. 320/kVA
Demand Charges for contracted demand =2500 x 320=Rs. 800000
Demand Charges for excess demand = 300x (2 x 320) =Rs. 192000
Total Demand Charges = 800000+192000= Rs. 992000
13. Minimum Consumption Guarantee (MCG)
The minimum consumption guarantee (MCG) charges shall be applicable to all non-
domestic consumers having load above 25 kW, metered PTW consumers and all industrial
consumers for their consumption in kWh (where kWh tariff is applicable) and kVAh (where kVAh
tariff is applicable). However, no MCG would be applicable on consumers having pre-paid
connections. The Commission has specified the minimum consumption guarantee on monthly basis
as well as on annual basis. The minimum consumption guarantee charges will be levied on monthly
basis when monthly consumption is less than the units specified for monthly minimum
consumption guarantee (MCG). In case Cumulative actual consumption from the beginning of
financial year exceeds the units specified for annual minimum consumption guarantee (MCG) no
further billing of monthly MCG shall be done. In such cases differential paid in excess of actual
billing shall be adjusted in the bill for month of March 2017.
Example:
Illustrative case for LT Industry-Connected load of 10 kW
Month Actual
consumption (kWh)
Cumulative Actual
Consumption (kWh)
Billed Consumption
(kWh)
Cumulative Billed
Consumption (kWh)
Apr 450 450 500 500 May 550 1000 550 1050 Jun 540 1540 540 1590 Jul 600 2140 600 2190 Aug 350 2490 500 2690 Sep 300 2790 500 3190 Oct 400 3190 500 3690 Nov 700 3890 700 4390 Dec 800 4690 800 5190 Jan 550 5240 550 5740 Feb 650 5890 650 6390 Mar 550 6440 50 6440
9. Annexures
Uttarakhand Electricity Regulatory Commission 317
Further in accordance with the Tariff Orders the bills for PTW consumers will be raised
twice in a financial year, i.e. June and December of each year. For the uniform basis of billing, the
following procedure shall be adopted for billing the PTW consumers:
1) For bills to be issued in June 2016:
The MCG per BHP for bills to be issued in June 2016 would be as under:
a) December 2015 to March 2016 – 60 X 4= 240 units
b) April 2016 and May 2016 – 60 X 2= 120 units
c) Total – 360 units (240+120)
2) For bills to be issued in December 2016 the MCG shall be reckoned as 360 units/ BHP (60
units per BHP/ month X 6)
The MCG will be attracted only if the actual recorded consumption is lower than MCG
indicated above.
14. Single Point Bulk Supply for Domestic, Non Domestic and Mixed Load
Categories
(i) Single Point Bulk Supply connection shall only be allowed for Sanctioned/Contracted
Load above 75 kW with single point metering for further distribution to the end users.
However, this shall not restrict the individual owner/occupier from applying for
individual connection.
(ii) The person who has taken the single point supply shall be responsible for all payments
of electricity charges to the Licensee and collection from the end consumer as per tariff
prescribed for such consumer. The Licensee shall ensure that tariff being charged from
end consumer does not exceed the prescribed tariff for the concerned category of the
consumer.
(iii) The person who has taken the single point supply shall also be deemed to be an agent
of Licensee to undertake distribution of electricity for the premises for which single
point supply is given under seventh proviso to section 14 of the Electricity Act, 2003
and distribution licensee shall be responsible for compliance of all provisions of the
Act and Rules & Regulations thereunder within such area.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
318 Uttarakhand Electricity Regulatory Commission
(iv) Single Point Bulk Supply under “Domestic” shall only be applicable for Residential
Colonies/Residential Multistoreyed Buildings including common facilities (such as
Lifts, Common Lighting and Water Pumping system) of such Residential
Colonies/Residential Multistoreyed Buildings. In case these Residential
Colonies/Residential Multistoreyed Buildings also have some shops or other
commercial establishments, the tariff of Mixed Load shall be applicable for such
premises.
(v) Single Point Bulk Supply Under “Non-Domestic” shall only be applicable for Shopping
Complexes/Multiplex/Malls.
15. Rounding off
(i) The contracted load/demand shall be expressed in whole number only and fractional
load/demand shall be rounded up to next whole number.
Example:
Contracted/Sanctioned Load of 0.15 kW shall be reckoned as 1 kW for tariff purposes.
Similarly, contracted/sanctioned load of 15.25 kW/kVA shall be taken as 16 kW/kVA.
(ii) All bills will be rounded off to the nearest rupee.
16. Other Charges
Apart from the charges provided in the Rate of Charge and those included in the Schedule of
Miscellaneous Charges, no other charge shall be recovered from the consumer unless approved by
the Commission.
9. Annexures
Uttarakhand Electricity Regulatory Commission 319
B. Tariffs RTS-1: Domestic
1. Applicability
This schedule shall apply to supply of power to:
(i) Residential premises for light, fan, power and other domestic purposes including common facilities (such as Lifts, Common Lighting and Water Pumping system)
(ii) Single Point Bulk Supply above 75 kW for Residential Colonies, Residential Multi-storeyed buildings where energy is exclusively used for domestic purpose including common facilities (such as Lifts, Common Lighting and Water Pumping system) of such Residential Colonies/Residential Multistoreyed Buildings
(iii) Places of worship, i.e. Mandir, Masjid, Gurudwara, Church, etc. (only for standalone places of worship and not for the places of worship which have other facilities such as Dharamshala, Community Hall, Dormatories, etc. attached with it)
(This rate schedule shall also be applicable to consumers having contracted load upto 2 kW
as also consumption upto 200 kWh/month and who are using some portion of the premises
mentioned above for non-domestic purposes. However, if either contracted load for such premises
is above 2 kW or consumption is more than 200 kWh/month, then the entire energy consumed shall
be charged under the appropriate Rate Schedule unless such load is segregated and separately
metered.)
2. Rate of Charge
Description Fixed Charges* Energy Charges 1) Domestic
1.1) Life line consumers
Below Poverty Line and Kutir Jyoti having load upto 1 kW and consumption upto 30 units per month
Rs. 14/ connection/month Rs. 1.50/kWh
1.2) Other Domestic Consumers
Upto 100 units per month Rs. 40 /month Rs. 2.45/kWh
101-200 units per month Rs. 60 /month Rs. 3.10/kWh
201-300 units per month Rs. 85 /month Rs. 4.10/kWh
301-400 units per month Rs. 110 /month Rs. 4.10/kWh
401-500 units per month Rs. 150 /month Rs. 4.50/kWh
Above 500 units per month Rs. 175 /month Rs. 4.50/kWh
2) Single Point Bulk Supply Rs. 50/kW/month Rs. 3.70/kWh *Fixed Charges in case of other domestic consumers for the month shall be charged at the rates equivalent to the total consumption in
the month.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
320 Uttarakhand Electricity Regulatory Commission
RTS-1A: Snowbound
1. Applicability
This schedule shall apply to supply of power to:
(i) Domestic and non-domestic consumers in snowbound areas.
(ii) This Schedule applies to areas notified as snowbound/snowline areas by the
concerned District Magistrate.
2. Rate of Charge
Description Fixed Charges Energy charges 1) Domestic
Rs.14/connection/month Rs. 1.50/kWh
2) Non-domestic upto 1 kW Rs. 1.50/kWh 3) Non-domestic more than 1kW & upto 4 kW Rs. 2.25/kWh 4) Non-Domestic more than 4 kW Rs. 25/connection/month Rs. 3.40/kWh
3. All other conditions of this Schedule shall be same as those in RTS-1.
9. Annexures
Uttarakhand Electricity Regulatory Commission 321
RTS-2: Non-Domestic 1. Applicability
This schedule should apply to supply of power to:
1.1 (i) Government/Municipal Hospitals (ii) Government/Government Aided Educational Institutions
(iii) Charitable Institutions registered under the Income Tax Act, 1961 and whose income is exempted from tax under this Act
1.2 Small Non Domestic Consumers with connected load upto 4 kW and consumption upto 50
units per month
1.3 Other Non-Domestic Users including single point bulk supply above 75 kW for shopping
complexes/multiplex/malls including common facilities (such as lifts, common lighting and
water pumping system).
1.4 Independent Advertisement Boards/Hoardings - All commercial (road side / roof top or on
the side of the buildings etc.) standalone independent advertisement hoardings such as
private advertising sign posts/ sign boards/ sign glows/flex that are independently
metered through a separate meter.
2. Rate of Charge S.
No. Description Fixed Charges
Energy charges
MCG (kVAh/kW of contracted load)*
1.1
(i) Government/Municipal Hospitals (ii) Government/Government Aided Educational Institutions (iii) Charitable Institutions registered under the Income Tax Act,
1961 and whose income is exempted from tax under this Act
(a) Upto 25 kW Rs. 45/ kW Rs. 4.15/ kWh
(b) Above 25 kW Rs. 55/ kVA Rs. 3.85/ kVAh
50 kVAh /kVA /month & 600 kVAh/
kVA/annum
1.2.
Other Non Domestic Users (a) Small Non Domestic Consumers with connected load upto
4 kW and consumption upto 50 units per month* Rs. 50 /
kW Rs. 4.30/ kWh
(b) Others upto 25 kW not covered in 1.2(a) above Rs. 55 / kW Rs. 5.10/ kWh
(c) Above 25 kW Rs. 55 / kVA
Rs. 5.00/ kVAh
50 kVAh /kVA /month & 600 kVAh/ kVA/
annum
1.3 Single Point Bulk Supply** Rs. 55 / kVA
Rs. 4.90/ kVAh
50 kVAh /kVA /month & 600 kVAh/ kVA/
annum 1.4 Independent Advertisement Hoardings Rs. 70/kW Rs. 5.20/kWh
* If consumption exceeds 50 units/month, then on the entire energy consumed tariff as per sub-category 1.2(b) shall be charged
** For loads above 75 kW for shopping complexes/multiplex/malls
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
322 Uttarakhand Electricity Regulatory Commission
3. Other Conditions 3.1 For consumers having contracted load in kW, the contracted load for MCG purposes
shall be calculated by considering a power factor of 0.85.
3.2 The Minimum Consumption Guarantee Charge shall be in addition to fixed/demand
charge and shall be levied if Consumption during a month is less than MCG and will be
subject to adjustment
3.3 ToD Meters shall be read by Meter Reading Instrument (MRI) only with complete dump
with phasor diagram, Tamper Reports, full load survey reports etc. shall be downloaded
for the purpose of complete analysis.
3.4 All consumers above 25 kW shall necessarily have ToD Meters.
3.5 No meter shall be read at zero load or very low load. Licensee shall carry appropriate
external load and shall apply the same, wherever, necessary to take MRI at load.
3.6 Copy of MRI Summary Report shall be provided alongwith the Bill. Full MRI Report
including load survey report shall be provided on demand and on payment of Rs. 15/
Bill.
9. Annexures
Uttarakhand Electricity Regulatory Commission 323
RTS-3: Public Lamps
1. Applicability
This schedule shall apply to supply of power to public lamps including street lighting
system, traffic control signals, lighting of public parks, etc. The street lighting of Harijan Bastis and
villages are also covered by this Rate Schedule.
2. Rate of Charge
Category Fixed Charges Energy Charge
Urban (Metered) Rs. 50/kW Rs. 4.65/ kWh
Rural (Metered) Rs. 40/kW Rs. 4.65/ kWh
3. Maintenance Charge
In addition to the “Rate of Charge” mentioned above, a sum of Rs. 10/- per light point per
month shall be charged for operation and maintenance of street lights covering only labour charges
where all material required will be supplied by the local bodies. However, the local bodies will have
the option to operate and maintain the public lamps themselves and in such case no maintenance
charge will be charged.
4. Provisions of Street Light Systems
In case, the maintenance charge, as mentioned above, is being charged then the labour
involved in the subsequent replacement or renewals of lamps shall be provided by the licensee but
all the material shall be provided by the local bodies. If licensee provides material at the request of
local body, cost of the same shall be chargeable from the local body.
The cost involved in extension of street light mains (including cost of sub-stations if any) in
areas where distribution mains of the licensee have not been laid, will be paid for by the local
bodies.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
324 Uttarakhand Electricity Regulatory Commission
RTS-4: Private Tube Wells/ Pumping Sets
1. Applicability
This schedule shall apply to supply of power to private tube-wells / pumping sets for
irrigation purposes and for incidental agricultural processes confined to chaff cutter, thrasher, cane
crusher and rice huller only. However, the tariff applicable for RTS-4 shall only be applicable if such
incidental agricultural processes are being carried out for agricultural produce of the connection
sanctioned for irrigation purposes.
2. Rate of charge
Category Fixed Charges Rs./BHP/Month
Energy Charges Rs./kWh
Minimum Consumption Guarantee (MCG)
RTS 4: PTW (Metered) Nil 1.55 60 units /BHP/Month & 720 units /BHP/Annum
3. Payments of bills and Surcharge for Late Payment
The bill shall be raised for this category twice a year only, i.e. by end of December (for
period June to November) and end of June (for period December to May). The bill raised in
December may be paid by the consumer either in lump-sum or in parts (not more than four times)
till 30th April next year for which no DPS shall be levied. Similarly, bill raised in June may be paid
by 31st October without any DPS. In case consumer fails to make payment within the specified
dates, a surcharge @ 1.25% per month for the period (months or part thereof) shall be payable on the
outstanding amount.
9. Annexures
Uttarakhand Electricity Regulatory Commission 325
RTS-4A: Agriculture Allied Activities
1. Applicability
This schedule shall apply to supply of power for use in nurseries growing plants/saplings,
polyhouses growing flowers/vegetables and fruits which doesn’t involve any kind of processing of
product except for storing and preservation.
2. Rate of charge
Category Fixed Charges Rs./BHP/Month
Energy Charges Rs./kWh
Minimum Consumption Guarantee (MCG)
RTS 4(A): Agricultural Allied Services Nil 1.55 60 units /BHP/Month &
720 units /BHP/Annum
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
326 Uttarakhand Electricity Regulatory Commission
RTS-5: Government Irrigation System
1. Applicability
This schedule shall apply to supply of power to:
(i) State Tubewells, World Bank Tubewells, Pumped Canals and Lift irrigation schemes,
Laghu Dal Nahar etc.,
(ii) Irrigation system owned and operated by any Government department.
2. Rate of charge
Description Fixed Charges Energy Charges 1. Upto 75 kW Rs. 50/kW/month Rs. 4.55/kWh
2. More than 75 kW Rs. 50/kVA/month Rs. 4.40/kVAh
9. Annexures
Uttarakhand Electricity Regulatory Commission 327
RTS-6: Public Water Works
1. Applicability
This Schedule shall apply to supply of power to Public Water Works, Sewage Treatment
Plants and Sewage Pumping Stations functioning under Jal Sansthan, Jal Nigam or other local
bodies and Plastic Recycling Plants.
2. Rate of charge
Particulars Fixed Charges Energy Charges
Urban Rs. 50/kVA/month Rs. 4.45/kVAh Rural Rs. 40/kVA/month Rs. 4.45/kVAh
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
328 Uttarakhand Electricity Regulatory Commission
RTS-7: LT and HT Industry
1. Applicability
This schedule shall apply to supply of power to:
(i) Industries and /or processing or agro- industrial purposes, power loom as well as to
Arc/Induction Furnaces, Rolling/Re-rolling Mills, Mini Steel Plants and to other
power consumers not covered under any other Rate Schedule
(ii) The vegetable, fruits, floriculture & Mushroom integrated units engaged in processing,
storing and packaging in addition to farming and those not covered under RTS-4A
shall also be covered under this Rate Schedule.
2. Specific Conditions of Supply
(i) All connections shall be connected with MCB (Miniature Circuit Breaker) or Circuit
Breaker / Switch Gear of appropriate rating and BIS Specification.
(ii) The supply to Induction and Arc Furnaces shall be made available only after ensuring
that the loads sanctioned are corresponding to the load requirements of tonnage of
furnaces. The minimum load of 1 Tonne furnace shall in no case be less than 400 kVA
and all loads will be determined on this basis. No supply will be given for loads below
this norm.
(iii) Supply to Steel Units shall be made available at a voltage of 33 kV or above through a
dedicated individual feeder only with check meter at sub-station end. Difference of
more than 3%, between readings of check meter and consumer meter(s), shall be
immediately investigated by the licensee and corrective action shall be taken.
(iv) Supply to all new connections with load above 1000 kVA should be released on
independent feeders only with provisions as at (iii) above.
9. Annexures
Uttarakhand Electricity Regulatory Commission 329
Description Energy Charge Fixed /Demand
Charge per month
Minimum Consumption
Guarantee (MCG) ** 1. LT Industry having contracted load upto 75kW (100 BHP)
1.1 Contracted load up to 25 kW Rs. 4.05/kWh Rs. 130/ kW of contracted load
$50 kWh/kW of contracted load /
month &
600 kWh/kW of contracted load /
annum
1.2 Contracted load more than 25 kW Rs. 3.70/kVAh Rs. 130/ kVA of contracted load
50 kVAh/kVA *** of contracted load /
month &
600 kVAh/kVA of contracted load /
annum 2. HT Industry having contracted load above 88kVA/75 kW (100 BHP) Load Factor# Rs./ kVAh
2.1 Contracted Load up to 1000 kVA upto 40% 3.50 Rs. 255/kVA of the
billable demand* 100 kVAh/kVA of contracted load /
month &
1200 kVAh/kVA of contracted load /
annum
Above 40% 3.85
2.2 Contracted Load More than 1000 kVA
Upto 40% 3.50 Rs. 320/kVA of the billable demand* Above 40% 3.85
$ 30 kWh/kW/month and 360 kWh/kW/annum for Atta Chakkis. * Billable demand shall be the actual maximum demand or 80 % of the contracted load whichever is higher.
** The Minimum Consumption Guarantee Charge shall be in addition to fixed/demand charge and shall be levied if Consumption during a month is less than MCG and will be subject to adjustment on annual basis. The energy charges for units billed to cover MCG during any month shall be charged at the rates specified for load factor upto 40% during normal hours and the annual adjustment (refund) of such excess energy charges, if any, shall also be given at the rates
specified for load factor upto 40% during normal hours. *** For consumers having contracted load in kW, the contracted load for MCG purposes shall be calculated by
considering a power factor of 0.85.
#For tariff purposes Load Factor (%) would be deemed to be =
100period billing in the hours of No. x less is whicheverDemand Contractedor Demand Maximum
period billing theduring access)open through receivedenergy the(excludingn Consumptio×
Provided that in cases where maximum demand during the month occurs in a period when open access is being availed by the consumer, then maximum demand for the purpose of computation of load factor shall be that occurring during the period when no open access is being availed.
3. Time of Day Tariff
(i) The rates of energy charge given above for LT industry with load more than 25 kW
and HT industry shall be subject to ToD rebate/surcharge.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
330 Uttarakhand Electricity Regulatory Commission
(ii) ToD Meters shall be read by Meter Reading Instrument (MRI) only with complete
dump with phasor diagram, Tamper Reports, full load survey reports etc. shall be
downloaded for the purpose of complete analysis and bills shall be raised as per ToD
rate of charge.
(iii) No meter shall be read at zero load or very low load. Licensee shall carry appropriate
external load and shall apply the same wherever necessary to take MRI at load
(iv) Copy of MRI Summary Report shall be provided along with the Bill. Full MRI Report
including load survey report shall be provided on demand and on payment of Rs. 15/
Bill
(v) ToD Load shall be as under:
Season/Time of day
Morning Peak hours
Normal hours
Evening Peak Hours
Off-peak Hours
Winters 01.10 to 31.03 0600-0930 hrs 0930-1730 hrs 1730-2200 hrs 2200-0600 hrs
Summers 01.04 to 30.09 -- 0700-1800 hrs 1800-2300 hrs 2300-0700 hrs
The, ToD Rate of Energy Charges shall be as under:
For LT Industry Energy Charge during
Normal Hours Peak Hours Off-peak Hours Rs. 3.70/kVAh Rs. 5.55/kVAh Rs. 3.33/kVAh
For HT Industry
Load Factor* Energy Charge during Normal Hours Peak Hours Off-peak Hours
Upto 40% Rs. 3.50/kVAh Rs. 5.78/kVAh Rs. 3.15/kVAh Above 40% Rs. 3.85/kVAh Rs. 5.78/kVAh Rs. 3.47/kVAh
* Load Factor shall be as defined in Clause 2 above
4. Seasonal Industries
Where a consumer having load in excess of 18 kW (25 BHP) and ToD meter and avails
supply of energy for declared Seasonal industries during certain seasons or limited period in the
year, and his plant is regularly closed down during certain months of the financial year, he may be
levied for the months during which the plant is shut down (which period shall be referred to as off-
season period) as follows.
9. Annexures
Uttarakhand Electricity Regulatory Commission 331
(i) The tariff for ‘Season’ period shall be same as “Rate of Charge” as given in this
schedule.
(ii) Where actual demand in ‘Off Season’ Period is not more than 30% of contracted load,
the energy charges for “Off-Season” period shall be same as energy charges for
“Season” period given in Rate of Schedule above. However, the contracted demand in
the “Off Season” period shall be reduced to 30%.
(iii) During ‘Off-season’ period, the maximum allowable demand will be 30% of the
contracted demand and the consumers whose actual demand exceeds 30% of the
contracted demand in any month of the ‘Off Season’ will be denied the above benefit of
reduced contracted demand during that season. In addition, a surcharge at the rate of
10% of the demand charge shall be payable for the entire ‘Off Season’ period.
Terms and Conditions for Seasonal Industries
(i) The period of operation should not be more than 9 months in a financial year.
(ii) Where period of operation is more than 4 months in a financial year, such industry
should operate for at least consecutive 4 months.
(iii) The seasonal period once notified cannot be reduced during the year. The off-season
tariff is not applicable to composite units having seasonal and other categories of
loads.
(iv) Industries in addition to sugar, ice, rice mill, frozen foods and tea shall be notified by
Licensee only after prior approval of the Commission.
5. Factory Lighting
The electrical energy supplied under this schedule shall also be utilised in the factory
premises for lights, fans, coolers, etc. which shall mean and include all energy consumed for factory
lighting in the offices, the main factory building, stores, time keeper’s office, canteen, staff club,
library, creche, dispensary, staff welfare centres, compound lighting, etc.
6. Continuous and Non-continuous supply
(i) Continuous Process Industry as well as non continuous process industrial consumers
connected on either independent feeders or industrial feeder can opt for continuous
supply. For industrial feeder, all connected industries will have to opt for continuous
supply and in case any consumer on industrial feeder does not wish to opt for
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
332 Uttarakhand Electricity Regulatory Commission
continuous supply, all the consumers on such feeder will not be able to avail
continuous supply. Such Industrial consumers who opt for continuous supply shall be
exempted from load shedding during scheduled/unscheduled power cuts and during
restricted hours of the period of restriction in usage approved by the Commission from
time to time, except load shedding required due to emergency breakdown/shutdown.
The existing consumers availing continuous supply option shall pay 15% extra energy
charges, in addition to the energy charges given above, with effect from April 01, 2016
or in case of new consumers, from the date of connection, till 31st March 2017,
irrespective of actual period of continuous supply option. However, in case of re-
arrangement of supply through independent feeder, the Continuous Supply Surcharge
shall be applicable from the date of energisation of aforesaid independent feeder till
31st March 2017, irrespective of actual period of continuous supply option. Demand
charge and other charges remain same as per rate of charge given above.
(ii) Consumers who are existing Continuous Supply Consumers shall continue to remain
Continuous Supply Consumers and they need not apply again for seeking continuous
supply. Such consumers shall pay 15% extra energy charges, in addition to the energy
charges given above, w.e.f. April 01, 2016 till March 31, 2017. However, in case of any
pending dispute with UPCL in the matter of continuous supply on certain feeders,
those consumers will have to apply afresh, for availing the facility of continuous
supply, by April 30, 2016;
(iii) The new applicants for continuous supply of power (including those who are applying
afresh as per above) can apply for seeking the continuous supply option at any time
during the year. However, continuous supply surcharge for such consumers shall be
applicable with effect from May 1, 2016 till March 31, 2017. UPCL shall provide the
facility of continuous supply within 7 days from the date of application, subject to
fulfilment of Conditions of Supply. However, in case of re-arrangement of supply
through independent feeder, UPCL shall provide the facility of continuous supply
from the date of completion of work of independent feeder subject to fulfilment of
Conditions of Supply.
9. Annexures
Uttarakhand Electricity Regulatory Commission 333
(iv) The existing consumers availing continuous supply option, who wish to discontinue
the continuous supply option granted to them earlier, will have to communicate, in
writing, to UPCL latest by April 30, 2016 and they shall continue to pay continuous
supply surcharge alongwith the tariff approved in this Order till April 30, 2016.
Further, in this regard, if due to withdrawal by one consumer from availing
continuous supply option on a particular feeder, supplying to other continuous supply
consumers as well, the status of other continuous supply consumers on that feeder is
affected, then UPCL shall inform all the affected consumers in writing, well in
advance.
(v) UPCL shall not change the status of a continuous supply feeder to a non-continuous
supply feeder.
(vi) UPCL/PTCUL shall take up augmentation, maintenance and overhauling works on
top priority, specially in the sub-stations where circuit breakers, other equipment, etc.
are in dilapidated condition and, thereby, shall ensure minimisation of interruptions of
the continuous supply feeders.
(vii) UPCL/PTCUL shall carry out periodical preventive maintenance of the feeders
supplying to continuous supply consumers. The licensees shall prepare preventive
maintenance schedule, in consultation with continuous supply consumers, well in
advance, so that such consumers can plan their operations accordingly.
(viii) The Licensee should show the energy charges and continuous supply surcharge
thereon separately in the bills.
7. Demand Charges for HT Industry
If the minimum average supply to any HT Industry Consumers is less than 18 hours per day
during the month, the Demand Charges applicable for such HT Industry Consumer shall be 80% of
approved Demand Charges for HT Industry.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
334 Uttarakhand Electricity Regulatory Commission
RTS 8: Mixed Load
1. Applicability
This schedule applies to single point bulk supply connection of more than 75 kW where the
supply is used predominantly for domestic purposes (with more than 60% domestic load) and also
for other non-domestic purposes. This schedule also applies to supply to MES.
2. Rate of Charge
The following rates shall apply to consumers of this category
Fixed Charges Energy Charges Rs. 60/kW/month Rs. 4.50/kWh
3. Other conditions
Apart from the above, other conditions of tariff shall be same as those for RTS-1 consumers.
However, excess load penalty shall be applicable as per clause 12 of General Conditions of Supply.
9. Annexures
Uttarakhand Electricity Regulatory Commission 335
RTS 9: Railway Traction
1. Applicability
This schedule applies to Railways utilizing power for traction purposes.
2. Rate of Charge
The following rates of energy and demand charge shall apply to this category:
Demand Charges Energy Charges Rs./kVA/month Rs./ kVAh
225/- Rs. 3.95
3. Other conditions
Apart from the above, other conditions of tariff shall be same as those for General HT
Industries under RTS-7 consumers except applicability of ToD tariff and surcharge for continuous
supply.
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
336 Uttarakhand Electricity Regulatory Commission
RTS-10: Temporary Supply
(A) Temporary Supply for Illumination & Public Address Needs 1. Applicability
This schedule shall apply to temporary supply of light & fan up to 10 kW, public address
system and illumination loads during functions, ceremonies and festivities, temporary shops not
exceeding three months.
2. Rate of Charge
Description Fixed Charges (1) For Illumination / public address/ ceremonies for load up to 15 kW Rs. 1250 per day (2) Temporary shops set up during festivals / melas and having load upto 2 kW Rs. 85 per day
(3) Other Temporary shops/ Jhuggi /Jhopris for load upto 1 kW 3.1) Rural Rs. 115/month/connection 3.2) Urban Rs. 230/month/connection
The amount of Fixed Service Charge as specified in 2 above shall be taken in advance.
(B) Temporary Supply for Other Purposes
1. Applicability (i) This schedule shall apply to temporary supplies of light, fan and power loads for the
purposes other than mentioned at (A) including illumination/public address/ceremonies
for load above 15 kW.
(ii) This schedule shall also apply for power taken for construction purposes including civil
work by all consumers including Government Departments. Power for construction
purposes for any work / project shall be considered from the date of taking first connection
for the construction work till completion of the work / project.
However, use of electricity through a permanent connection sanctioned for premises
owned by the consumer for construction, repair or renovation of exsisting building, shall
not be considered as unauthorised use of electricity as long as the intended purpose/use of
the building/appurtenants being constructed is same/permissible in the sanctioned
category of the connection.
2. Rate of Charge The rate of charge will be corresponding rate of charge in appropriate Schedule Plus 25%.
The appropriate rate schedule for the temporary supplies for cane crusher upto 15 BHP given for
maximum period of four (4) months will be RTS-7. However, the minimum consumption guarantee
charges shall not be applicable for temporary supply.
9. Annexures
Uttarakhand Electricity Regulatory Commission 337
9.2 Annexure 2: Schedule of Miscellaneous Charges
Sl. No
Nature of Charges Unit Approved
(Rs.)
1
Checking and Testing of Meters a. Single Phase Meters Per Meter 50.00 b. Three Phase Meters Per Meter 75.00 c. Recording Type Watt-hour Meters Per Meter 170.00 d. Maximum Demand Indicator/ LT CT operated Meters Per Meter 350.00 e. Tri-vector Meters/ HT Meters with CT/PT Per Meter 1000.00 f. Ammeters and Volt Meters Per Meter 65.00 g. Special Meters Per Meter 335.00 h. Initial Testing of Meters Per Meter NIL
2 Subsequent testing and installation other than initial testing Per Meter 80.00
3
Disconnection and Reconnection of supply on consumers request or non-payment of bill (for any disconnection or reconnection the charge will be 50%)
a. Consumer having load above 100 BHP/75 kW Per Job 600.00 b. Industrial and Non Domestic consumers upto 100 BHP/75 kW Per Job 400.00 c. All other categories of consumers Per Job 200.00
4
Replacement of Meters a. Installation of Meter and its subsequent removal in case of Temporary Connections
Per Job 75.00
b. Changing of position of Meter Board at the consumer's request
Per Job 100.00
5
Checking of Capacitors (other than initial checking) on consumer's request:
a. At 400 V/ 230 V Per Job 150.00 b. At 11 kV and above Per Job 300.00
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
338 Uttarakhand Electricity Regulatory Commission
9.3 Annexure 3: Public Notice
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
340 Uttarakhand Electricity Regulatory Commission
9. Annexures
Uttarakhand Electricity Regulatory Commission 341
Annexure 4: List of Respondents Sl.No. Name Designation Organization Address
1. Smt. Poonam Uniyal, W/o Sh. B.M. Uniyal - -
236, Nehru Gram Road, Ring Road, Dehradun
2. Dr. V.K. Garg - - A-24/E, DDA Flats, Munirka, New Delhi-110067
3. Sh. Pankaj Gupta President M/s Industries Association of Uttarakhand
Mohabewala Industrial Area, Dehradun-248110
4. Sh. Pramod Singh Tomar
Director (SPNG Steel Division)
M/s Galwalia Ispat Udyog Pvt. Ltd.
Narain Nagar Industrial Estate, Bazpur Road, Kashipur-244713, Distt. Udham
Singh Nagar
5. Sh. Sanjay Kumar Agrawal
Director & General
Secretary
Shree Karuna Jan Kalyan Samiti (Regd.)
Sanjay Bhawan, Malla Joshi Khola, Almora, Uttarakhand-263601
6. Sh. Shakeel A. Siddiqui
General Manager
(Commercial- (SPNG Spinning
Division)
M/s Kashi Vishwanath Textile Mill (P) Ltd.
5th Km. Stone, Ramnagar Road, Kashipur-244713, Distt. Udham Singh Nagar
7. Sh. Pawan Agarwal Vice-President M/s Uttarakhand Steel
Manufacturers Association
C/o Shree Sidhbali Industries Ltd., Kandi Road, Kotdwar, Uttarakhand
8. Sh. Munish Talwar Head-Electrical
and Instrumentation
M/s Asahi India Glass Ltd.
Integrated Glass Plant, Village-Latherdeva Hoon, Manglaur-Jhabrera Road, P.O.
Jhabrera, Tehsil Roorkee, Distt. Haridwar, Uttarakhand
9. Sh. Rajeev Gupta - M/s KVS Infraatech LLP Works: B 20, 29, Industrial Estate, Bazpur
Road, Kashipur-244713, Distt. Udham Singh Nagar
10. Sh. Rajeev Gupta - M/s Kashi Vishwanath Steels Pvt. Ltd.
Narain Nagar Industrial Estate, Bazpur Road, Kashipur-244713, Distt. Udham
Singh Nagar
11. Sh. P.C. Aggarwal - M/s Kashi Enterprises B-25-29, Industrial Estate, Nainital Road,
Kashipur–244713, Distt. Udham Singh Nagar
12. Sh. R.K. Singh Head (CPED & E) M/s Tata Motors Ltd.
Plot No. 1, Sector 11, Integrated Industrial Estate, SIDCUL, Pantnagar-263153, Distt.
Udham Singh Nagar
13. Sh. S.S. Chopra Manager (Electrical)
M/s Hindustan National Glass & Industries Ltd.
Post Off.-Virbhadra, Rishikesh-249202, Uttarakhand
14. Sh. Vijay Kumar Verma - M/s Shiv Shakti
Electricals Sarrafa Bazaar, Kankhal, Distt. Haridwar,
Uttarakhand
15. Sh. R.S. Yadav Vice President (HR & Admin.) M/s India Glycols Ltd.
A-1, Industrial Area, Bazpur Road, Kashipur-244713, Distt. Udham Singh
Nagar
16. - - M/s BST Textile Mills Pvt. Ltd.
Plot 9, Sector 9, IIE, SIDCUL, Pantnagar, Rudrapur-263153
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
342 Uttarakhand Electricity Regulatory Commission
Sl.No. Name Designation Organization Address
17. - - M/s Ganesha Ecosphere Ltd.
Plot No. 6, Sector 2, IIE, Pantnagar, Rudrapur, Distt. Udham Singh Nagar
18. Sh. Ashok Bansal President M/s Kumaon Garhwal
Chamber of Commerce & Industry Uttarakhand
Chamber House, Industrial Estate, Bazpur Road, Kashipur, Distt. Udham Singh
Nagar
19. Sh. Kuldeep Singh - Bhartiya Kisan Union Village-Kaliya Wala, Post Off.-Jaspur, Distt. Udham Singh Nagar
20. Sh. Raj Singh Chairman Devbhoomi Dharmshala
Prabhandak Sabha (Regd.)
Narsingh Bhawan, Upper Road, Haridwar, Uttarakhand
21. Sh. Mukesh Chandra Joshi - - Village-Joshiyana, Post Off.-Parsundakhal,
Patti-Paidalsyun, Distt. Pauri Garhwal
22. Sh. G.S. Bedi General Manager
M/s Indian Drugs & Pharmaceuticals Ltd. Virbhadra, Rishikesh-249202, Uttarakhand
23. Sh. Abhinav Singh - M/s Bhilangana Hydro Power Limited
B-37, 3rd Floor, Sector-1, Noida-201301, Gautam Budh Nagar, Uttar Pradesh
24. Sh. Satvinder - M/s Indus Towers Ltd. H-11, 2nd Floor, Sector-63, Gautam Budh Nagar, Noida-201301, Uttar Pradesh
25. Sh. Vijay Singh Verma - Bhartiya Kisan Club Village-Delna, P.O.-Jhabrera, Haridwar-
247665, Uttarakhand
26. Sh. Manish Garg - M/s Madhu Gupta & Company
510/51, New Hyderebad, Lucknow, Uttar Pradesh
27. Sh. Rakesh Bhatia President M/s Uttarakhand Industrial Welfare
Association
E-8, Govt. Industrial Area, Patel Nagar, Dehradun
28. Sh. Pramod Kumar Chief Electrical
Distribution Engineer
Northern Railway Headquarters Office, Baroda House, New Delhi-110001
29. Sh. Mahesh Sharma State General Secretary
M/s Uttarakhand Industrial Welfare
Association
Off. G-31, UPSIDC, Industrial Area, Selaqui, Dehradun, Uttarakhand
30. Sh. Man Singh General Manager (Engg.) M/s Alps Industries Ltd.
Haridwar Unit-II, Plot No. 1 B, Sector-10, Integrated Industrial Estate, SIDCUL,
Distt. Haridwar, Uttarakhand
31. Sh. Harindra Kumar Garg Chairman
M/s SIDCUL Manufacturers
Association-Uttarakhand
Plot No. 1, Sector-2, SIDCUL, Distt. Haridwar, Uttarakhand
32. Sh. Achal Sharma President M/s East West Products Ltd.
Lohia Head Road, Khatima-262308, Distt. Udham Singh Nagar
33. Sh. L.S. Chamyal Factory Manager M/s Khatema Fibres Ltd. UPSIDC Industrial Area, Khatima-262308, Distt. Udham Singh Nagar
34. Sh. Amar S. Dhunta General Secretary RTI Club-Uttarakhand Off.–827/1, Sirmaur Marg, Kaulagarh
Road, Dehradun
35. Sh. Rajendra Prasad Joshi Secretary
Retired Central Employees Welfare Committee-Almora
Baans Gali, Johri Bazaar, Distt. Almora, Uttarakhand
9. Annexures
Uttarakhand Electricity Regulatory Commission 343
9.4 Annexure 5: List of Participants in Public Hearings
List of Participants in Hearing at Pithoragarh on 16.02.2016
Sl. No. Name Designation Organization Address
1. Sh. Chandra Bhanu Gupta - M/s Gupta Trading
Company Siltham Road, Distt. Pithoragarh
2. Sh. Manoj Chauhan - M/s Chauhan Medical Store Gandhi Chowk, Distt. Pithoragarh
3. Sh. Harish Kapri - Jila Panchayat Office Gandhi Chowk, Distt. Pithoragarh
4. Sh. Manoj Bisht - - Near Mostamanu, Chandak, Tehsil & Distt. Pithoragarh
5. Sh. Pawan Kumar Joshi District President
Udhyog Vyapaar Mandal Simalgair Bazaar, Distt. Pithoragarh
6. Sh. Pawan Joshi - M/s Satkar Sweets Simalgair Bazaar, Distt. Pithoragarh
7. Sh. Pankaj Kadayat - M/s Pankaj Enterprises Siltham, Distt. Pithoragarh
8. Sh. Mahendra Valdiya,
S/o Sh. Ram Singh Valdiya
- - Near Shiv Temple, Chandrabhaga
(Valdiya Bhawan) P.O. Echoli, Distt. Pithoragarh
9. Sh. Tula Singh - - Village-Talli Saar, P.O.-Khati Gaon, Distt. Pithoragarh
10. Sh. Mahesh Ch. Matholiya - - Simlagair Bazaar, Distt. Pithoragarh
11. Sh. Laxman Singh Vaseda - - Vaseda Colony, Near Nagar Palika,
Distt. Pithoragarh
12. Sh. Naveen Chandra Joshi - - G.I.G. Road, Vrindawan Complex,
Distt. Pithoragarh
13. Sh. Raju Mall - M/s Uttaranchal Gifts
Parwati Bazaar, Siltham, Distt. Pithoragarh
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
344 Uttarakhand Electricity Regulatory Commission
List of Participants in Hearing at Sitarganj on 18.02.2016 Sl. No. Name Designation Organization Address
1. Sh. R.S. Yadav - M/s India Glycols Ltd. A-1, Industrial Area, Bazpur Road,
Kashipur, Distt. Udham Singh Nagar-244713
2. Sh. R.K. Mishra - M/s India Glycols Ltd. A-1, Industrial Area, Bazpur Road,
Kashipur, Distt. Udham Singh Nagar-244713
3. Sh. P.K. Gupta - M/s Innovative Textiles Ltd.
B-8, Phase-1, ESIP, Sitarganj, Distt. Udham Singh Nagar
4. Sh. V. K. Aggarwal - M/s Balaji Action
Buildwell
Plot No: C-34 & C-34(a) to (d), ESIP, Sitarganj
Distt. Udham Singh Nagar
5. Sh. Rajiv Gupta - M/s Kashi Vishwanath Steels Pvt. Ltd.
Narain Nagar Industrial Estate, Bajpur Road, Kashipur-244713,
Distt. Udham Singh Nagar
6. Sh. P.C. Aggarwal - M/s Kashi Enterprises
B-25-29, Industrial Estate, Nainital Road, Kashipur–244713,
Distt. Udham Singh Nagar
7. Sh. R.K. Gupta Secretary General (KGCCI)
M/s Gujarat Ambuja Exports Ltd.
C-50, ELDECO SIDCUL, Industrial Park, Sitarganj-262405, Distt.
Udham Singh Nagar
8. Sh. R.K. Saxena - M/s Parle Biscuits Pvt. Ltd.
Plot No. D-10, ESIP, Sitarganj, Distt. Udham Singh Nagar
9. Sh. Durgesh Mohan -
M/s Sitarganj Sidcul Industries Welfare
Association
B-108, ESIP, Sitarganj, Distt. Udham Singh Nagar
10. Sh. S.K. Garg - M/s BST Textile Mills Pvt. Ltd.
Plot. No. 9, Sector-9, SIDCUL, Pantnagar, Distt. Udham Singh
Nagar
11. Sh. J.N. Singh - M/s Ganesha Ecosphere Ltd.
Plot No. 6, Sector-2, IIE, SIDCUL, Pantnagar, Distt. Udham Singh
Nagar
12. Sh. Jeet Singh Cheema - Bhartiya Kisan Union
Dhakiya No.-2, P.O.-Dhakiya No. 1 Kashipur, Distt. Udham Singh
Nagar
13. Sh. Kuldeep Singh Cheema Advisor Member State Council-Uttarakhand
Dhakiya Kalan, P.O.-Dhakiya No.-1, Tehsil Kashipur, Distt. Udham Singh
Nagar
14. Sh. Balkar Singh Fauji - -
Village-Raipur Khurd, P.O. Kashipur, Distt. Udham Singh
Nagar
9. Annexures
Uttarakhand Electricity Regulatory Commission 345
List of Participants in Hearing at Pauri on 23.02.2016 Sl. No. Name Designation Organization Address
1. Sh. Kamal Singh - -
Village-Sarna, P.O.-Chopdiyun, Block - Pabau,
Patti-Ghurdaursyun, Distt. Pauri Garhwal
2. Sh. Mohan Singh Rawat - - Saraswati Sadan,
Near Police Line, Distt. Pauri Garhwal
3. Smt. Vinita Rawat - - M.I.C. Road, Distt. Pauri Garhwal
4. Sh. Mukesh Joshi - -
Village- Joshiyada, P.O.-Parsundakhal,
Patti-Paidalsyun, Distt. Pauri Garhwal
5. Sh. Jagdish Singh - - Village-Rithai, P.O.-Kandara, Patti-Paidalsyun, Distt. Pauri
Garhwal
6. Sh. Ghanshyam Singh Rana - -
Village-Thali, P.O.-Chandola Rai, Patti-Nandalsyun, District Pauri
Garhwal
7. Sh. Ravindra Bhandari - - Village & Post Nisni,
Patti-Paidalsyun, Distt. Pauri Garhwal
8. Sh. Prem Singh Negi - - Village-Daang, P.O.-Toli,
Patti-Kapolsyun, Distt. Pauri Garhwal
9. Sh. Vinod Bisht Sabhasad Nagar Palika Pauri, Distt. Pauri Garhwal
10. Sh. Suraj - -
Village-Chaufanda, P.O.-Chaplodi,
Patti-Balikandarsyun, Distt. Pauri Garhwal
11. Sh. Arvind - - Mamgai Bhawan,
Laxmi Nagar Road, Distt. Pauri Garhwal-246001
12. Sh. Bhagwan Verma - - Kandai Road, Pauri, Distt. Pauri Garhwal
13. Sh. Manoj Singh - - Jhandi Chaur, Uttari Kotdwar, Distt. Pauri Garhwal
14. Sh. Sukhdev Badoni - - Laxmi Narayan Mandir, Pauri, Distt. Pauri Garhwal
15. Sh. Mahaveer Singh Negi - -
Rajkiya Allopathic Chikitsalaya, P.O.-Saankarsain, Patti-
Balikandarsyun, Distt. Pauri Garhwal
16. Sh. Gandhi Singh Negi - - Village-Gandhigram Kadud, Patti-Sitonsyun, Distt. Pauri Garhwal
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
346 Uttarakhand Electricity Regulatory Commission
List of Participants in Hearing at Dehradun on 01.03.2016 Sl. No. Name Designation Organization Address
1 Sh. Virat Seth - M/s Tata Motors Ltd.
Plot No. 1, Sector-1, IIE, SIDCUL, Pantnagar, Distt. Udham Singh
Nagar-263145, Uttarakhand
2 Sh. Devesh Pant - M/s Tata Motors Ltd.
Plot No. 1, Sector-1, IIE, SIDCUL, Pantnagar, Distt. Udham Singh
Nagar-263145, Uttarakhand
3 Sh. Pankaj Gupta President M/s Industries Association of Uttarakhand
C/o Satya Industries, Mohabbewala Industrial Area,
Dehradun
4 Sh. Rajiv Agarwal Sr. Vice-President
M/s Industries Association of Uttarakhand
C/o Satya Industries, Mohabbewala Industrial Area,
Dehradun
5 Sh. K.L. Sundriyal - - 4(4/3), New Road, Near Hotel
Relax, (Amrit Kauri Road), Dehradun
6 Sh. T.S. Bhandari Director M/s Himalayan Resorts Pvt. Ltd. 16-Tagore Villa, Dehradun
7 Sh. Mahesh Sharma General Secretary
M/s Uttarakhand Industrial Welfare
Association
Off. G-31, UPSIDC, Industrial Area, Selaqui, Dehradun,
Uttarakhand
8 Sh. Gulshan Rai Khanduja - Sh. Ganesh Roller
Floor Mills Mohabbewala Industrial Area,
Subhash Nagar, Dehradun-248001
9 Sh. Man Singh General Manager (Engg.)
M/s Alps Industries Ltd.
1-A, Sector-10, Integrated Industrial Area,
SIDCUL, Roshnabad Road, Haridwar-249403, Uttarakhand
10 Sh. Shakeel A. Siddiqui General
Manager (Commercial)
M/s Kashi Vishwanath
Textile Mill Ltd.
Works : 5th Km. Stone, Ramnagar Road, Kashipur-244713,
Distt. Udham Singh Nagar
11 Sh. Manish Garg - Madhu Gupta & Company
51/510, New Hyderabad, Lucknow
12 Sh. Munish Talwar Head-Electrical
& Instrumentation
M/s Asahi India Glass Ltd.
Integrated Glass Plant, Village-Latherdeva Hoon, Manglaur-Jhabrera Road, P.O. Jhabrera,
Tehsil Roorkee, Distt. Haridwar
13 Sh. Vijay Singh Member Bhartiya Kisan Club
Village-Delna, Post-Jhabreda, Roorkee,
Haridwar-247665, Uttarakhand
14 Sh. Arvind Jain Member Tarun Kranti Manch (Regd.) 6-Ramleela Bazaar, Dehradun
15 Sh. Katar Singh President Bhartiya Kisan Club
Village-Sabatwali, P.O.-Jhabreda, Tehsil Roorkee, Haridwar
16 Sh. Gagan Arora - - 89/1/1, Race Course, Near Rose Mount School, Dehradun
17 Sh. Nanda Dutt Madhwal - - 100/25, Ballupur Road, Dehradun
9. Annexures
Uttarakhand Electricity Regulatory Commission 347
18 Sh. Biru Bisht - Mohanpur,
Post Off.-Premnagar, Dehradun-248007
19 Sh. Vishwamitra - - 36-Panchsheel Park,
Chakrata Road, P.O.-New Forest, Dehradun-248006
20 Sh. V.S. Bhatnagar - - 98/3, Bell Road, Near Jr. Hiltons School, Clementown, Dehradun
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
348 Uttarakhand Electricity Regulatory Commission
mÙkjk[k.M ikoj dkWjiksjs'ku fyfeVsM
ds VSfjQ vkns'k ds
v/;k; & 09
nj vuqlwph ¼jsV 'ksM~;wy½
dk fgUnh :ikUrj.k
9. Annexures
Uttarakhand Electricity Regulatory Commission 349
¼uksV%& ;g :ikUrj.k] ek0 vk;ksx }kjk ikfjr VSfjQ vkns'k fnukad 05-04-2016 ds Annexures ¼9-1 ,oa 9-2½ dk
fgUnh :ikUrj.k gS] bl lEcU/k esa fdlh Hkh izdkj ds fuoZpu@O;k[;k ds fy, vaxzsth laLdj.k gh vfUre :i ls
ekU; gksxkA½
9. layXud
9-1 layXud 1% 01-04-2016 ls izHkkoh nj vuqlwph &
,- vkiwfrZ gsrq lkekU; “krsZ&
1- lsok dh izd`fr i) 4 kW ds Hkkj rd vkWYVjusfVax djsaV 50 Hz flaxy Qst 230 oksYV ¼vuqeU; ifjorZuksa ds lkFk½A ii) oksYVst vkiwfrZ dh miyC/krk ij fuHkZj djrs gq, 4 kW ls Åij Hkkjksa ds fy, vYVjusfVax djsaV 50 Hz. 3 Qst] 4 ok;j] 400 oksYV~l ;k blls Åij ¼vuqeU; ifjorZuksa ds lkFk½A
2- u;s la;kstuksa ds fy, “krsZa& i) 75 kW (88 kVA) ls vf/kd rFkk 2550 kW (3000 kVA) rd ds u;s la;kstuksa dks vkiwfrZ 11 kV ;k blls Åij ij fuxZr dh tk;sxh] 2550 kW (3000 kVA) ls Åij 8500 kW (10000 kVA) rd Hkkj
33 kV ;k blls Åij ij fuxZr fd;s tk;saxs rFkk 8500 kW (10000 kVA) ls Åij 132 kV Hkkj ij fuxZr fd;s tk;saxsA ii) lHkh u;s la;kstu] laLFkkiu rFkk ehVjksa ds ifjpkyu ij lh-bZ-,- ds fofu;eksa dh iqf’V djus okys
ehVj ds lkFk fn;s tk;saxsA iii) 4 kW ls Åij ds lHkh u;s 3 Qst la;kstu] vf/kdre ekax ladsrd okys bySDVªkWfud VªkbZ&osDVj
ehVj ds lkFk tkjh fd;s tk;ssaxsA iv) LkHkh u;s flaxy IokbaV cYd la;kstu] 75 kW ls vf/kd Hkkj ij tkjh fd;s tk;saxsA v) 5 BHP ls vf/kd ds eksfVo Hkkj j[kus okys miHkksDrk mi;qDr jsfVax ds rFkk BIS fof”kf’V dh iqf’V
djus okys “kaV dSisflVj laLFkkfir djsaxsA vi) HT/EHT ij lHkh u;s la;kstu dsoy 3 Qst 4 ok;j ehVlZ ds lkFk tkjh fd;s tk;saxsA
3- vkiwfrZ dk fcUnq&
miHkksDrk dks ÅtkZ dh vkiwfrZ ,d ,dy fcUnq ij dh tk;sxhA
4- =qfViw.kZ ehVj ¼ADF/IDF½] ehVj ugha i<+k@igW¡qp ugha ¼NA/NR½ rFkk =qfViw.kZ jhfMax ¼RDF½ ds ekeys
esa fcfyax%& NA/NR ekeyksa esa ÅtkZ miHkksx dk fu/kkZj.k rFkk fcfyax fiNys ,d o’kZ ds vkSlr miHkksx ds
vuqlkj fd;k tk;sxk ¼fo|+qr vkiwfrZ lafgrk ds vuqlkj½ tks fd okLrfod jhfMax fy;s tkus ij lek;kstu ds
v/khu gksxkA ,slh vuafre jhfMax ,d ckj esa nks fcfyax pdzksa ls vf/kd ds fy, tkjh ugha jgsxhA blds
i”pkr~ vuqKkih dks vuafre vk/kkj ij dksbZ fcy tkjh djus dk vf/kdkj ugha gksxkA =qfViw.kZ izrhr voLFkk
¼ADF½] =qfViw.kZ ehVj ¼IDF½ rFkk =qfViw.kZ jhfMax ¼RDF½ ds ekeyksa esa miHkksDrkvksa dh fcfyax] ehVj ds
=qfViw.kZZ ik;s tkus ;k =qfViw.kZ fjiksVZ fd;s tkus dh frfFk ls Bhd igys ds rhu fcfYkax pdzksa ds vkSlr
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
350 Uttarakhand Electricity Regulatory Commission
miHkksx ds vk/kkj ij dh tk;sxh ¼fo|qr vkiwfrZ lafgrk ds vuqlkj½A ;s izHkkj dsoy ml vf/kdre rhu
eghus dh vof/k vFkok f}ekfld fcfyax dh n'kk esa nks fcfyax lkbZfdy gsrq mn~xzg.kh; gksaxs] ftlesa
vuqKkih }kjk =qfViw.kZ ehVj cnyk tkuk vko”;d gksxkA blds i”pkr~ vuqKkih dks lgh fd;s x;s ehVj ds
fcuk fcy tkjh djus dk vf/kdkj ugha gSA
=qfViw.kZ ehVj ds ekeys] ;Fkk IDF/ADF rFkk =qfViw.kZ jhfMax ekeys ;Fkk RDF dh tkap o cnyus dk
dk;Z] fo|qr vkiwfrZ lafgrk ds fofu;e 3-1-4 ds vuqlkj vuqKkih }kjk fd;k tk;sxkA
5- Xkzkeh.k@ioZrh; {ks= ds ?kjsyw ehVMZ miHkksDrkvksa dh fcfyax] ftuds ehVj ugha i<s+ tkrs gSa&
Xkzkeh.k@ioZrh; {ks= ds ?kjsyw miHkksDrkvksa ftudh ehVj jhfMax fu;fer :i ls ugha yh tk jgh gS
vFkok le; esa nsjh vUrjky ls vfu;fer :i ls yh tk jgh gS] ,slh nksuksa fLFkfr;ksa esa miHkksDrkvksa dh
vufUre fcfyax ukWjesfVo miHkksx ds vk/kkj ij fuEuor~ dh tk;sxh] ftldk okLrfod ehVj jhfMax ds
vk/kkj ij okf’kZd lek;kstu fd;k tk;sxk%&
Js.kh ukWjesfVo miHkksx
?kjsyw ¼xzkeh.k&ioZrh; {ks=½ 30 kWh/kW/ ekg ?kjsyw ¼xzkeh.k&vU; {ks=½ 50 kWh/kW/ ekg
bl mn~ns”; gsrq lafonkd`r Hkkj vxys iw.kkZad rd iw.kkZfdar fd;k tk;sxkA vuqKkih }kjk ,sls
miHkksDrkvksa dh ehVj jhfMax o’kZ esa de ls de ,d ckj fy;k tkuk lqfuf”pr fd;k tk;sxk ,oa bl vk/kkj
ij fcfyax okf’kZd lek;ksftr gksxhA
6- Uk;s la;kstuksa esa fcfyax ;k vuehVMZ ds ehVMZ ekeyksa esa laifjoZru
Uk;s la;kstu ;k vuehVMZ ls ehVMZ esa laifjorZu tSls ekeyksa esa tgk¡ fiNyh jhfMax miyC/k ugha gS]
ogka vuafre fcfyax] uhps fn;s vuqlkj miHkksx ds ekudh; Lrjksa ij dh tk;sxh] tks okLrfod jhfMax fy;s
tkus ij lek;kstu ds v/khu gksxhA
Js.kh Ekkudh; miHkksx
?kjsyw&¼”kgjh½ 100 kWh/kW/ ekg ?kjsyw ¼xzkeh.k&ioZrh; {ks=½ 30 kWh/kW/ ekg ?kjsyw ¼xzkeh.k&vU; {ks=½ 50 kWh/kW/ ekg v?kjsyw ¼”kgjh½ 150 kWh/kW/ ekg v?kjsyw ¼xzkeh.k½ 100 kWh/kW/ ekg futh V;wo oSYl 60 kWh/BHP/ ekg m|ksx
,y-Vh- m|ksx 150 kWh/kW/ ekg ,p-Vh- m|ksx 150 kVAh/kVA/ ekg
9. Annexures
Uttarakhand Electricity Regulatory Commission 351
bl mn~ns”; ds fy,] lafonkdr Hkkj vxys iw.kkZad rd iw.kkZafdr fd;k tk;sxkA bl vk/kkj ij dh
xbZ fcfyax dsoy vf/kdre 2 fcfyax pØksa dh vof/k ds fy;s tkjh jgsxh ftl nkSjku vuqKkIkh }kjk
okLrfod jhfMax fy;k tkuk lqfuf'pr djuk gksxkA mlds Ik”pkr~ fcuk lgh ehVj jhfMax fy;s vuqKkIkh dks
fcy tkjh djus dk vf/kdkj ugha gksxkA vU; lHkh oxksZa esa igyk fcy dsoy okLrfod jhfMax ij gh tkjh
fd;k tk;sxkA
7- foyafcr Hkqxrku vf/kHkkj ¼DPS½ ¼PTW dks NksM+dj lHkh oxksZa ds fy;s½
;fn vuqKkih }kjk fn;s x;s fcy dk Hkqxrku fu;r frfFk ds Ik”pkr~ 15 fnu dh fj;k;r vof/k ds
Hkhrj iw.kZ :Ik ls ugha fd;k tkrk gS rks fo|qr vf/kfu;e] 2003 dh /kkjk 56 ds vuqlkj vkiwfrZ vla;ksftr
djus ds vuqKkih ds vf/kdkj ij izfrdwy izHkko Mkys fcuk iwoZ Hkqxrku fd;s tkus rd izR;sd mRrjksÙkj ekg
;k mlds Hkkx ds fy;s ewy ns; frfFk ls] Hkqxrku u fd;s x;s fcy dh ewy jkf”k ij 1-25 izfr”kr vf/kHkkj
yxk;k tk;sxkA vuqKkih] uhps n”kkZ;s vuqlkj] ekg dks ;wfuV ds :Ik esa] 15 fnu fj;k;r vof/k gsrq iznku
dj] fu;r frfFk ds Ik”pkr~ fofHkUu frfFk;ksa ds fy;s ns; Mh-ih-,l- lfgr] fcy esa gh dqy jkf”k Li’V :Ik ls
n”kkZ;sxkA
mnkgj.k
fu;r frfFk rd ns; jkf”k :0 100@&
fu;r frfFk 1 ebZ] 2016
ns; jkf”k
ij ;k iwoZ Ik”pkr~ Ik”pkr~
16 ebZ] 2016 16 ebZ] 2016 1 twu] 2016
:0 100@& :0 101-25 :0 102-50
8- lksyj okWVj ghVj NwV
;fn miHkksDrk lksyj okWVj ghfVax iz.kkyh laLFkkfir djrk gS rFkk mldk mi;ksx djrk gS rks iz.kkyh
dh izR;sd 100 yhVj {kerk ds fy, :0 100@& ;k ml ekg dk fcy] nksuksa esa ls tks de gks] dh NwV
bl “krZ ds v/khu nh tk;sxh fd miHkksDrk vuqKkih dks ;g “kiFki= nsxk fd mlus og iz.kkyh
laLFkkfir dh gS] ftls vuqKkih le;≤ ij lR;kfir djus ds fy;s Lora= gksxkA ;fn ,slk dksbZ
nkok >wBk ik;k tkrk gS rks ,sls miHkksDrk ds fo:) dh tk ldus okyh n.MkRed fof/kd dk;Zokgh ds
vfrfjDr vuqKkih] 100 izfr”kr tqekZus ds lkFk miHkksDrk dks vuqeU; dqy NwV dh olwyh djsxk rFkk
vxys 12 ekg rd ds fy;s ,slh NwV izkfIr fu"ksf/kr djsxkA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
352 Uttarakhand Electricity Regulatory Commission
9- izhisM ehVfjax
vk;ksx ds bl vkns'k ds }kjk izhisM ehVfjax ;kstuk vuqeksfnr dh x;h gS tksfd ykxw jgsxhA izhisM
ehVfjax ;kstuk ds vUrxZr ?kjsyw Js.kh ¼vkjVh,l&1 ,oa vkjVh,l&1,½ gsrq fo|qr izHkkj ij 4% rFkk
vU; ,yVh miHkksDrkvksa dks fo|qr izHkkj ij 3% dh NwV] izhisM ehVj ds laLFkkiu rFkk dk;Z djus dh
frfFk ls iznkfur gksxhA fdUrq vkjVh,l&10 ds Hkkx ¼,½ esa mYysf[kr iznhiu o lkoZtfud lacks/ku
vko”;drkvksa vkSj Lora= foKkiu gksfYMax ds fy, vLFkk;h vkiwfrZ esa NwV vuqeU; ugha gksxhA lksyj
okWVj NwV mijksDr nj vuqlwph ds vuq:i bl gsrq vko';d 'krksaZ dks iw.kZ djus ij izhizsM miHkksDrkvksa
ij Hkh ykxw gksxhA
10- csl oksYVst ls mPp@fuEu oksYVst ij vkiwfrZ dk mi;ksx djus ds fy;s NwV@vf/kHkkjA i) 75 kW@88 kVA rd lafonkd`r Hkkj okys miHkksDrk ;fn vkiwfrZ 400 oksYV~l ds Åij o 11 kV rd nh tkrh gS rks fctyh izHkkj dh nj ij 5% NwV Lohdk;Z gksxhA ii) 75 kW@88 kVA ls Åij lafonkd`r Hkkj okys miHkksDrkvksa ds fy;s & ;fn vkiwfrZ 400 oksYV~l ij
nh tkrh gS rks miHkksDrk dks fctyh izHkkj dh nj ij ifjdfyr fcy jkf”k ij 10% dk vfrfjDr
izHkkj nsuk gksxkA iii) 75 kW@88 kVA ls Åij lafonkd`r Hkkj okys miHkksDrk & 33 kV ij vkiwfrZ ds ekeys esa] fctyh
izHkkj dh nj ij 2-5% dh NwV izkIr djsxsaA iv) 75 kW@88 kVA ls Åij lafonkdr Hkkj okys miHkksDrk tks 132 kV ;k vf/kd ij vkiwfrZ izkIr dj
jgs gksa] fctyh izHkkj dh nj ij 7-5% dh NwV izkIr djsaxsA v) mijksDr lHkh oksYVst ukWfeuy jsVsM oksYVstst gSaA vi) ftu miHkksDrkvksa ds ikl izhisM dusD'ku gS] mu ij NwV ;k vf/kHkkj ykxw ugha gksxhA
11- fuEu ikoj QSDVj vf/kHkkj ¼?kjsyw] PTW rFkk kVAh vk/kkfjr “kqYd okys vU; Jsf.k;ksa ij ykxw ugha½A i) fcuk bySDVªkWfud VªkbZosDVj ehsVlZ okys miHkksDrkvksa] ftUgksaus mi;qDr jsfVaXl rFkk fofunsZ”ku ds “kaV
dSisflVlZ laLFkkfir ugha fd;s gSa a] muls orZeku fo|qr izHkkjksa ij 5% dk vf/kHkkj mn~xzghr fd;k
tk;sxkA ii) bySDVªkWfud VªkbosDVj ehVlZ okys miHkksDrkvksa ds fy, 0-85 ls uhps rFkk 0-80 rd ds ikoj QSDVj
gksus ij orZeku fo|qr izHkkjksa ij 5% dk vf/kHkkj rFkk 0-80 ls fuEu ikoj QSDVj gksus ij orZeku
fo|qr izHkkjksa dk 10% ds vf/kHkkj mn~xzghr gksxkA iii) ftu miHkksDrkvksa ds ikl izhisM dusD'ku gS] mu ij vf/kHkkj ykxw ugha gksxkA
9. Annexures
Uttarakhand Electricity Regulatory Commission 353
12- vf/kHkkj@ekax naM ¼?kjsyw] fgekPNkfnr o PTW Jsf.k;ksa ij ykxw ugha½
,sls miHkksDrkvksa ds ekeys esa tgakW MDI ds lkFk bySDVªkWfud ehVlZ laLFkkfir gS] ;fn fdlh ekg esa
vfHkfyf[kr vf/kdre~ ekax lafonkdr Hkkj@ekax ls vf/kd gks tkrh gS rks ,sls vfrfjDr Hkkj@ekax ij izHkkj
ykxw fLFkj@ekax izHkkj dh lkekU; nj ls nksxquk ds cjkcj &mn~xzghr fd;k tk;sxkA ,slk vf/kd Hkkj naM
dsoy ml ekg ds fy;s yxk;k tk;sxk] ftlesa vf/kdre~ ekax] lafonkdr Hkkj ls vf/kd gksxhA ;|fi] ftu
miHkksDrkvksa ds ikl izhisM dusD'ku gS] mu ij vf/kHkkj vfrfjDr Hkkj tqekZuk ykxw ugha gksxkA
mnkgj.k %& i) mu miHkksDrkvksa ds fy;s] tgk¡ lafonkdr Hkkj@ekax ds vk/kkj ij fLFkj izHkkj fofufnZ’V fd;s x;s gSa% lafonkdr Hkkj 30 kW, vf/kdre~ ekax 43 kW vfr ekax 43&30= 13 kW, fLFkj izHkkjksa dh nj = :0 50@kW
lafonkdr Hkkj ds fy;s fLFkj izHkkj =30x50= :0 1500/- vfrfjDr Hkkj ds fy;s fLFkj izHkkj =13 (2x50) = :0 1300/- dqy fLFkj izHkkj =1500+1300= :0 2800/- ii) fcy ;ksX; ekax ij fcy fy;s tkus okys vkS|kSfxd miHkksDrkvksa ds fy;sss% lafonkdr ekax 2500 kVA] vf/kdre ekax 2800 kVA] fcy ;ksX; ekax=2800 kVA vfrfjDr ekax 2800&2500=300 kVA, ekax izHkkjksa dh nj =:0 320/kVA lafonkdr ekax gssrq ekax izHkkj = 2500 x 320 = :0 800000/- vfrfjDr ekax gsrq ekax izHkkj = 300 x (2x320) = :0 192000/- dqy ekax izHkkj = 800000 + 192000 = :0 992000/-
13- U;wure~ miHkksx xkjaVh ¼MCG½
25 kW ls Åij Hkkj okys lHkh v?kjsyw miHkksDrkvksa] ehVMZ ihVhMCY;w miHkksDrkvksa rFkk lHkh
vkS|kSfxd miHkksDrkvksa dks kWh ¼tgkaW kWh “kqYd ykxw gS½ rFkk kVAh ¼tgkaW kVAh “kqYd ykxw gS½] esa muds
miHkksx gsrq U;wure~ miHkksx xkjaVh izHkkj ykxw gksaxsA ;|fi] izhizsM dusD'ku miHkksDrkvksa ij U;wure~ miHkksx
xkjaVh ¼MCG½ ykxw ugha gksxhA vk;ksx us ekfld vk/kkj ij rFkk okf’kZd vk/kkj ij U;wure~ miHkksx xkjaVh
fofufnZ’V dh gSA U;wure~ miHkksx xkjaVh izHkkj ekfld vk/kkj ij yxk;k tk;sxk] tc ekfld miHkksx ekfld
U;wure~ miHkksx xkajVh ¼MCG½ gsrq fofufnZ’V ;wfuVksa ls de gksxkA ;fn foRrh; o’kZ ds izkjaHk ls lap;h
okLrfod miHkksx okf’kZd U;wure~ miHkksx xkjaVh ¼MCG½ gsrq fofufnZ’V ;wfuVksa ls vf/kd gksrk gS rks ekfld
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
354 Uttarakhand Electricity Regulatory Commission
,e0lh0th0 gsrq vkxs dksbZ fcfyax ugha dh tk;sxhA ,sls ekeyksa esa okLrfod fcfyax ls vf/kd ds fy;s fd;k
x;k Hkqxrku ekpZ] 2017 ds ekg gsrq fcy esa lek;ksftr fd;k tk;sxkA
mnkgj.k %
VSfjQ vkns”k ds vuqlkj foRrh; o’kZ esas nks ckj ih0Vh0MCY;w0 miHkksDrkvksa lss fcy fy;s tk;saxs] tSls
izR;sd o’kZ twu ,oa fnlEcj ekg esaA fcfyax esa ,d:irk yk;s tkus ds mn~ns”; ls ih0Vh0MCY;w0
miHkksDrkvksa gsrq fcfyax ds fy;s fuEu izfØ;k,¡ vey esa yk;h tk;saxh%&
i) twu] 2016 esa fcy tkjh djus ds fy;s ,e0lh0th0 izfr ch-,p-ih- fuEukuqlkj jgsxh% a) fnlEcj] 2015 ls ekpZ] 2016 & 60 X 4 = 240 ;wfuV~l b) vizSy] 2016 ,oa ebZ] 2016 & 60 X 2 = 120 ;wfuV~l c) dqy & 360 ;wfuV~l ¼240+120½
ii) fnlEcj] 2016 esa fcy tkjh djus ds fy;s ,e0lh0th0 dh x.kuk 360 ;wfuV~l@ch-,p-ih- ¼60
;wfuV~l izfr ch-,p-ih-@ekg X 6½ ij dh tk;sxhA OkkLrfod vfHkfyf[kr miHkksx ds mifjfyf[kr ,e0lh0th0 ls de jgus dh fLFkfr esa gh ,e0lh0th0
fy;k tk;sxkA 14- ?kjsyw] v?kjsyw rFkk fefJr Hkkj Jsf.k;ksa ds fy;s ,dy fcanq Fkksd vkiwfrZA i) 75 kW ls Åij dqy Hkkj okys ?kjsyw@v?kjsyw&Hkou@ekWYl@lgdkjh lkewfgd vkokl
lfefr;ka@dkWyksfu;ksa esa vkxs forj.k gsrq ,dy fcanq ehVfjax ds lkFk ,dy fcanq ij la;kstu izkIr
djuh gSaA rFkkfi O;fDrxr la;kstu gsrq vkosnu djus esa oS/kkfud Lokeh@dCtk/kkjh ds fy;s dksbZ
mnkgj.k Lo:Ik ,yVh0 la;kstd ds fy,& lafonkd`r Hkkj 10 kW
Ekkg okLrfod miHkksx
kWh
Lkap;h okLrfod miHkksx
kWh
fcy fd;k miHkksx
kWh
Lkap;h fcy fd;k
miHkksx
kWh
viSzy] 450 450 500 500
ebZ 550 1000 550 1050
Tkwu] 540 1540 540 1590
tqykbZ] 600 2140 600 2190
vxLr] 350 2490 500 2690
flrEcj] 300 2790 500 3190
vDVwcj] 400 3190 500 3690
uoEcj] 700 3890 700 4390
fnlEcj] 800 4690 800 5190
Tkuojh] 550 5240 550 5740
Qjojh] 650 5890 650 6390
ekpZ] 550 6440 50 6440
9. Annexures
Uttarakhand Electricity Regulatory Commission 355
jksd ugha gksxhA ii) ,dy fcUnq vkiwfrZ ysus okyk O;fDr] vuqKkih dks fo|qr izHkkjksa ds lHkh Hkqxrku djus rFkk ,sls
miHkksDrkvksa gsrq fu/kkZfjr VSfjQ ds laxzg djus ds fy, mRrjnk;h gksxkA vuqKkih ;g Hkh lqfuf”pr
djsxk fd miHkksDrk dh lEcfU/kr Js.kh ls fy;k tk jgk VSfjQ fu/kkZfjr VSfjQ ls vf/kd u gksA iii) ,slk O;fDr ftlus ,dy fcanq vkiwfrZ yh gS] og fo|qr vf/kfu;e] 2003 dh /kkjk 14 ds lkrosa
ijUrqd ds v/khu nh xbZ ,dy fcanq vkiwfrZ okys ifjlj ds fy, fo|qr ds forj.k dh ftEesnkjh gsrq
vuqKkih] vfHkdrkZ Hkh le>k tk;sxk rFkk forj.k vuqKkih] ,sls {ks= ds Hkhrj mlds v/khu vf/kfu;e
rFkk fu;eksa o fofu;eksa ds lHkh micU/kksa ds vuqikyu gsrq mRrjnk;h gksxkA iv) ^?kjsyw^ ds vUrxZr ,dy fcanq Fkksd vkiwfrZ dsoy vkoklh; dkWyksfu;ksa@vkoklh; cgqeaftyk bekjrksa
dh vke lqfo/kkvksa ¼tSls fy¶Vksa] lkoZtfud izdk”k vkSj ty ifEiax iz.kkyh ds :Ik esa½ lfgr
vkoklh; dkyksfu;ksa@cgqeaftyk bekjrksa ij ykxw gksxhA ;fn bl izdkj ds vkoklh;
dkyksfu;ksa@vkoklh; cgqeaftyk bekjrksa esa dqN vU; nqdkusa vFkok vU; dksbZ O;kolkf;d izfr’Bku
gksa] ,slh fLFkfr esa mu ij fefJr yksM dk VSfjQ ykxw gksxkA v) v?kjsyw ds vUrxZr ,dy fcanq Fkksd vkiwfrZ dsoy 'kkWfiax dkWEiySDl@eYVhIySDl@ekWYl~ ds fy,
ykxw gksxhA 15- Ikw.kkZadu %
i) Lkafonkd`r Hkkj@ekax dsoy iw.kZ la[;k esa vfHkO;Dr dh tk;sxh rFkk [k.M Hkkj@ekax dh vxyh iw.kZ
la[;k rd iw.kkZafdr fd;k tk;sxkA mnkgj.k%
0-15 kW dk lafonkdr@Lohd`r Hkkj] “kqYd mn~ns”; gsrq 1 kW ekuk tk;sxkA blh izdkj
15-25 kW/kVA dk lafonkdr@Lohd`r Hkkj 16 kW/kVA fy;k tk;sxkA ii) lHkh fcy fudVre~ :Ik;s rd iw.kkZafdr fd;s tk;saxsA
16- vU; izHkkj %
izHkkj dh nj esa fn;s x;s izHkkjksa rFkk fofo/k izHkkjksas dh vuqlwph esa lfEefyr izHkkjksa ds flok; vU;
dksbZ izHkkj vk;ksx dh Lohd`fr ds fcuk miHkksDrkvksa ls olwy ugha fd;s tk;saxsA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
356 Uttarakhand Electricity Regulatory Commission
Ckh- “kqYd njsa
vkj-Vh-,l-&1 % ?kjsyw
1- vuqiz;ksT;rk %
fo|qr dh vkiwfrZ gsrq ;g vuqlwph fuEu ij ykxw gksxh %
i) jks”kuh] ia[kk] ikoj o vU; ?kjsyw mn~ns”;ksa ds fy, vkoklh; ifjlj lkewfgd lqfo/kkvksa lfgr ¼tSls
fy¶V] lkoZtfud izdk”k rFkk okVj ifEiax lsV½A
ii) 75 kW ds Åij ds ,dy fcUnq Fkksd vkiwfrZ ds fy, vkoklh; dkWyksfu;kaW] cgqeaftys Hkou tgk¡ ÅtkZ
dk iz;ksx dsoy ,sls ?kjsyw mn~ns”; ¼tSls fy¶V] lkoZtfud izdk”k rFkk okWVj ifEaix lsV½ ds fy;s
gksrk gks] lfEefyr gSA
iii) /kkfeZd LFkyksa tSls efUnj] efLtn] xq:}kjk] ppZ bR;kfn ¼tgk¡ ek= iwtk@bcknr dh txg vdsys
esa@vyx ls gks] mu iwtk LFkykas@bcknrxkgksa ds fy, tgk¡ /keZ”kkyk] lkeqnkf;d dsUnz] “k;uxg
bR;kfn lEc) gks] ogk¡ ;g vuqlwph ykxw ugha gksxhA½
¼;g nj lwph mu miHkksDrkvksa ij Hkh ykxw gksxh] ftuds ikl 2 kW rd dk lafonkdr Hkkj gS] lkFk
gh 200 kWh@ekg rd dk miHkksx gS rFkk tks mijksDr ifjlj dk dqN Hkkx mijksDr v?kjsyw mn~ns”;ksa ds
fy;s dj jgs gSaA rFkkfi ;fn ,sls ifjljksa ds fy, lafonkdr Hkkj 2 kW ls vf/kd o miHkksx 200 kWh@ekg ls vf/kd gS rks tc rd fd Hkkj dks vyx&vyx ugha fd;k tkrk rFkk iFkd :Ik ls ehVj
ugha fy;k tkrk] nksuksa esa ls dksbZ ,d] miHkksx dh xbZ leLr ÅtkZ mi;qDr nj vuqlwph ds v/khu izHkkfjr
dh tk;sxhA½
2- izHkkj dh nj %
*vU; ?kjsyw miHkksDrkvksa ds ekeys esa fLFkj izHkkj njsa ekg esa dqy [kir ds cjkcj yh tk;sxhA
fooj.k fLFkj izHkkj* fo|qr ewY;
1- ?kjsyw
1-1½ ykbZQ ykbu miHkksDrk
xjhch js[kk ls uhps o dqVhj T;ksfr ftudk 1 kW rd
Hkkj rFkk 30 ;wfuV izfr ekg miHkksx gks
:0 14@la;kstu@ ekg :0 1-50@ kWh 1-2½ vU; ?kjsyw miHkksDrk 100 ;wfuV~l@ekg rd miHkksx gsrq :0 40@ekg :0 2-45@kWh 101&200 ;wfuV~l@ekg miHkksx gsrq :0 60@ekg :0 3-10@kWh 201&300 ;wfuV~l@ekg miHkksx gsrq :0 85@ekg :0 4-10@kWh 301&400 ;wfuV~l@ekg miHkksx gsrq :0 110@ekg :0 4-10@kWh 401&500 ;wfuV~l@ekg miHkksx gsrq :0 150@ekg :0 4-50@kWh 500 ;wfuV~l@ekg ls Åij :0 175@ekg :0 4-50@kWh 2½ ,dy fcUnq Fkksd vkiwfrZ :0 50@kW@ekg :0 3-70@kWh
9. Annexures
Uttarakhand Electricity Regulatory Commission 357
vkj Vh ,l 1 , % fgekPNkfnr
1- Ikz;ksT;rk
fo|qr dh vkiwfrZ gsrq ;g vuqlwph fuEu ij ykxw gksxh % (i) fgekPNkfnr {ks=ksa ds ?kjsyw o v?kjsyw miHkksDrkA (ii) ;g vuqlwph] lacaf/kr ftykf/kdkjh }kjk fgekPNkfnr@fge js[kk ds :Ik esa vf/klwfpr {ks=ksa ij
ykxw gksrh gSA 2- vkiwfrZ izHkkj dh nj
fooj.k fLFkj izHkkj fo|qr ewY;
1½ ?kjsyw
:0 14@la;kstu@ekg
:0 1-50@ kWh 2½ v?kjsyw 1 kW rd :0 1-50@ kWh 3½ v?kjsyw 1 kW ls 4 kW rd :0 2-25@ kWh 4½ v?kjsyw 4 kW ls Åij :0 25@la;kstu@ekg :0 3-40@ kWh
3- bl vuqlwph dh vU; lHkh “krsZ ogh gksaxh tks fd vkjVh,l&1 esa gSA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
358 Uttarakhand Electricity Regulatory Commission
vkj-Vh-,l-&2 % v?kjsyw
1- iz;ksT;rk %
fo|qr dh vkiwfrZ gsrq ;g vuqlwph fuEu ij ykxw gksxh %
1-1 (i) ljdkjh@uxj ikfydk fpfdRlky;A
(ii) ljdkjh@ljdkjh lgk;rk izkIr “kSf{kd laLFkkuA
(iii) vk;dj vf/kfu;e] 1961 ds v/khu iathd`r ,slh /kekZFkZ laLFkk,a ftudh vk; dks bl
vf/kfu;e ds v/khu dj dh NwV izkIr gksA
1-2 NksVs v?kjsyw miHkksDrk ftudk vuqcfU/kr Hkkj 4 kW rd rFkk miHkksx 50 ;wfuV@ekg rd gksA
1-3 75 kW ds Åij ,dy fcanq Fkksd vkiwfrZ ds vU; [email protected];d mi;ksxdrkZ ftlesa “kkWfiax
dkWEiysDl@eYVhIySDl@ekWYl ftlesa lkewfgd lqfo/kkvksa lfgr ¼tSls fy¶V] lkoZtfud izdk”k rFkk
okVj ifEaix lsV½ lfEefyr gks gsrq lfEefyr gSaA
1-4 LorU= foKkiu cksMksZa@gksfMZaXl& lHkh O;olkf;d ¼lM+d fdukjs@Nr ij ;k bekjrksa ds fdukjs
bR;kfn½ ij vdsys [kM+s LorU= foKkiu gksfMZaXl tks fd futh foKkiu lkbZu iksLV@lkbZu
cksMZ~l@lkbZu Xykst~@¶ySDl gS] ftudks iFkd ehVj ls LorU= ehVfjax dh tk jgh gSA
2- izHkkj dh nj
dze la0 fooj.k fLFkj izHkkj fo|qr ewY; MCG ¼lafonkdr Hkkj dk
kVAh/kW½* 1-1 (i) ljdkjh@uxj ikfydk fpfdRlky; (ii) ljdkjh@ljdkj lgk;rk izkIr “kSf{kd
laLFkku (iii) vk;dj vf/kfu;e 1961 ds v/khu
iathdr ,slh /kekFkZ laLFkk,a ftudh vk;
ij bl vf/kfu;e ds v/khu dj dh NwV
izkIr gSA
¼,½ 25 kW rd :0 45@kW :0 4-15@ kWh
¼ch½ 25 kW ls Åij :0 55@kVA :0 3-85@kVAh
50 kVAh/ kVA / ekg o 600 kVAh/ kVA/ okf"kZd
1-2
vU; v?kjsyw miHkksDrkvksa
¼,½ NksVs v?kjsyw miHkksDrk ftudk vuqcfU/kr
Hkkj 4 kW rFkk miHkksx 50 ;wfuV izfr
ekg gksA* :0 50@ kW :0 4-30@kWh
¼ch½ 25 kW rd mijksDr 1-2 ¼,½ esa “kkfey
ugha :0 55@ kW :0 5-10@kWh
¼lh½ 25 kW ls Åij :0 55@ kVA :0 5-00@kVAh 50 kVAh/ kVA / ekg o 600 kVAh/ kVA / okf"kZd
1-3 ,dy fcanq Fkksd vkiwfrZ** :0 55@ kVA :0 4-90@kVAh
50 kVAh/ kVA / ekg o 600 kVAh/ kVA / okf"kZd
1-4 LorU= foKkiu gksfMZaXl~~ :0 70@ kW :0 5-20@kWh
* ;fn [kir 50 ;wfuV@ekg ls vf/kd gS rks iw.kZ [kir ij fo|qr izHkkj mi&Js.kh 1-2 ¼[k½ ds vuqlkj fy;k tk;sxkA
** “kkfiax dkWEIysDl@eYVhIySDl@ekWYl ds fy;s 75 kW ls Åij
9. Annexures
Uttarakhand Electricity Regulatory Commission 359
3- vU; 'krsZa 3.1 kW esa lafonkd`r Hkkj okys miHkksDrkvksa ds fy, ,e lh th mn~~ns';ksa gsrq lafonkd`r Hkkj
0-85 ds ikWoj QSDVj ij fopkj djrs gq, ifjHkkf"kr fd;k tk;sxkA 3.2 U;wure miHkksx xkjaVh izHkkj] fLFkj ekax izHkkj ds vfrfjDr gksxk rFkk rc mn~~xzghr fd;k
tk;sxk tc miHkksx ,d ekg esa MCG ls de gksxk ,oa ;g okf"kZd vk/kkj ij lek;ksftr
fd;k tk;sxkA 3.3 Vh vks Mh ehVlZ] dsoy ehVj jhfMax midj.k ¼MRI½ }kjk i<s tk;saxsA iw.kZ fo”ys’k.k ds
iz;kstu gsrq Qstj Mk;xzke] Vsaij fjiksVZ] iw.kZ Hkkj losZ{k.k fjiksVZ bR;kfn iw.kZ MaIk ds lkFk
Mkmu yksM fd;s tk;saxsA 3.4 25 kW Lks Åij ds lHkh miHkksDrkvksa gsrq vko”;d :Ik ls ToD ehVj gksaxsA 3.5 “kwU; Hkkj ;k vR;Ur de Hkkj ij dksbZ ehVj ugha i<+k tk;sxkA vuqKkih mi;qDr okg~;
Hkkj j[ksxk rFkk mDr Hkkj ij ,e- vkj- vkbZ- ysus ds fy, tgk¡ vko”;d gks mls mi;ksx
djsxkA 3.6 ,e vkj vkbZ lkjka'k fjiksVZ dh izfr fcy ds lkFk miyC/k djkbZ tk;sxhA Hkkj losZ{k.k
fjiksVZ lfgr iw.kZ ,e- vkj- vkbZ- fjiksVZ] ekax djus ij o 15 :0 ds fcy dk Hkqxrku
djus ij iznku dh tk;sxhA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
360 Uttarakhand Electricity Regulatory Commission
vkj Vh ,l&3% ifCyd ySEil
1- vuqiz;ksT;rk
;g vuqlwph fo|qr dh vkiwfrZ gsrq ifCyd ySEil ij ykxw gksxh] ftlesa LVªhV ykbfVax flLVe]
VSªfQd flXuy] lkoZtfud m|kuksa dh ykbZfVax bR;kfn lfEefyr gSA gfjtu cfLr;ksa rFkk xkaoksa dk iFk
izdk”k Hkh bl vuqlwph esa lfEefyr gSA
2- izHkkj dh nj
Js.kh fLFkj izHkkj fo|qr ewY;
'kgjh ¼ehVMZ½ :0 50@kW :0 4-65@ kWh xzkeh.k ¼ehVMZ½ :0 40@kW :0 4-65@ kWh
3- vuqj{k.k izHkkj
mijksDr **izHkkj dh nj** ds vfrfjDr :0 10@&izfr ykbZV IokbaV izfr ekg dsoy etnwjh “kkfey
djrs gq, LVªhV ykbZV ds ifjpkyu ,oa vuqj{k.k gsrq izHkkfjr fd;k tk;sxkA lHkh visf{kr lkexzh dh vkiwfrZ
LFkkuh; fudk;ksa }kjk dh tk;sxhA rFkkfi LFkkuh; fudk;ksa ds ikl ifCyd ySEil dk ifjpkyu o vuqj{k.k
Lo;a djus dk fodYi gksxk rFkk ,slh fLFkfr esa dksbZ vuqj{k.k izHkkj ugha fy;k tk;sxkA
4- iFk izdk'k iz.kkyh ds fy, mica/k
;fn] mijksDrkuqlkj vuqj{k.k izHkkj izHkkfjr fd;k tk jgk gS rks ySEil ds cnyus ;k blds
uohuhdj.k esa yxus okys Jfed vuqKkih }kjk miyC/k djk;s tk;saxs fdarq lHkh lkexzh LFkkuh; fudk;ksa }kjk
miyC/k djk;h tk;sxhA ;fn LFkkuh; fudk; ds vuqjks/k ij vuqKkih lkexzh miyC/k djokrk gS rks bldh
ykxr LFkkuh; fudk; }kjk izHkk;Z gksxhA
,sls {ks=ksa esa tgk¡ vuqKkih ds forj.k esUl ugha fcNk;s x;s gSa ogk¡ LVªhV ykbZV esUl ¼mi LVs”kuksa dh
ykxr] ;fn dksbZ gS] lfgr½ ds foLrkj dh ykxr dk Hkqxrku LFkkuh; fudk; }kjk fd;k tk;sxkA
9. Annexures
Uttarakhand Electricity Regulatory Commission 361
vkj Vh ,l & 4% futh uydwi @ifEiax lsV~l
1- vuqiz;ksT;rk%
;g vuqlwph fo|qr dh vkiwfrZ gsrq mu lHkh miHkksDrkvksa ij ykxw gksrh gS tks flapkbZ ds mn~ns”; ls
rFkk pkjk dkVus dh e”khu] /kku dh Hkwlh fudkyus dh e”khu] xUUkk fijkbZ dh e”khu o vukt ds nkus
vyx djus dh e”khu rd lhfer izklafxd d`f’k dk;ksZ ds fy, futh uy dwiksa@ifEiax lsV~l gsrq vkiwfrZ
izkIr dj jgs gSaA gkykafd izklafxd df’k ds mn~ns”; ds varxZr flapkbZ gsrq fy;s x;s la;kstu ij
vkjVh,l&4 ds vUrxZr VSfjQ ykxw gksxkA
2- izHkkj dh nj%
Js.kh fLFkj izHkkj :0@ch,pih@ekg fo|qr ewY;
:0@kWh U;wure miHkksx xkjUVh
¼,elhth½
vkjVh,l& 4 %
PTW ¼ehVMZ½ “kwU; 1-55
60 ;wfuV~l /BHP/ ekg rFkk 720 ;wfuV~l /BHP/
okf"kZd
3- fcyksa dk Hkqxrku rFkk foyafcr Hkqxrku gsrq vf/kHkkj%
bl Js.kh ds fy;s fcy o’kZ esa nks ckj vFkkZr fnlacj var ¼twu ls uoEcj dh vof/k ds fy;s½ rFkk
twu var ¼fnlEcj ls ebZ dh vof/k ds fy;s½ tkjh fd;s tk;sxsaA fnlEcj esa tkjh fd;s x;s fcyksa dk Hkqxrku
miHkksDrk }kjk ,d lkFk ;k vxys o’kZ 30 viSzy rd ¼vf/kdre pkj Hkkxksa esa fd;k tk;½ fd;k tk ldrk gS
ftlds fy;s dksbZ Mh-ih-,l- mn~xzghr ugha fd;k tk;sxkA blh izdkj twu esa tkjh fd;s x;s fcyksa dk
Hkqxrku fcuk Mh-ih-,l- ds 31 vDVwcj rd fd;k tk ldrk gSA ;fn miHkksDrk fofufnZ’V frfFk;ksa rd
Hkqxrku djus esa vlQy jgrk gS rks cdk;k jkf”k ij ml vof/k ¼ekg ;k mlds Hkkx½ ds fy, 1-25% izfrekg dh nj ls vf/kHkkj yxsxkA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
362 Uttarakhand Electricity Regulatory Commission
vkj Vh ,l & 4 ¼,½ % d`f"k lEc) lsok;sa
1- vuqiz;ksT;rk%
;g vuqlwph fo|qr dh vkiwfrZ gsrq mu ij ykxw gksrh gS tks ikS/kk ulZjh] ikWyhgkÅl esa mxk;s
Qwyksa@lfCt;ksa rFkk Qyksa] tgka Hk.Mkj.k ,oa laj{k.k ds vfrfjDr fdlh izdkj ds mRiknksa dk izlaLdj.k
u dh tkrh gksA
2- izHkkj dh nj
Js.kh fLFkj izHkkj
:0@ch,pih@ekg
fo|qr ewY;
:0@KWh U;wure miHkksx xkjUVh
¼,elhth½
vkjVh,l&4 ¼,½ %
df"k lac) lsok;sa
'kwU; 1-55
60 ;wfuV~l@ch,pih@ekg ,oa
720 ;wfuV~l@ch,pih@okf"kZd
9. Annexures
Uttarakhand Electricity Regulatory Commission 363
vkj Vh ,l & 5% ljdkjh flapkbZ iz.kkyh
1- vuqiz;ksT;rk%
fo|qr dh vkiwfrZ gsrq ;g vuqlwph fuEu ij ykxw gksxh %
(i) jkT; uy dwiksa] fo”o cSad uydwiksa] iai dh xbZ ugjksa] fy¶V flapkbZ ;kstukvksa] y?kq ny ugj
bR;kfnA
(ii) fdlh ljdkjh foHkkx ds LokfeRo o mlds }kjk ifjpkfyr flapkbZ iz.kkyhA
2- izHkkj dh nj%
fooj.k fLFkj izHkkj fo|qr ewY;
1- 75 kW rd :0 50@kW/ekg :0 4-55@kWh 2- 75 kW ls vf/kd :0 50@kVA/ekg :0 4-40@kVAh
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
364 Uttarakhand Electricity Regulatory Commission
vkj Vh ,l & 6% ifCyd okVj oDlZ
1- vuqiz;ksT;rk
;g vuqlwph fo|qr dh vkiwfrZ gsrq lkoZtfud ty dk;ksZa] lhost VªhVesaV IykaV~l rFkk ty laLFkku]
ty fuxe ;k vU; LFkkuh; fudk;ksa ds v/khu dk;Zjr lhost ifEiax LVs”kuksa vkSj IykfLVd fjlkbZfdfyax
la;a=ksa ij ykxw gksxhA
2- izHkkj dh nj
fooj.k fLFkj izHkkj fo|qr ewY;
'kgjh :0 50@ kVA /ekg :0 4-45@kVAh xzkeh.k :0 40@ kVA /ekg :0 4-45@kVAh
9. Annexures
Uttarakhand Electricity Regulatory Commission 365
vkj Vh ,l 7% ,y Vh rFkk ,p Vh m|ksx
1- vuqiz;ksT;rk
fo|qr dh vkiwfrZ gsrq ;g vuqlwph fuEu ij ykxw gksxh %
(i) vkS|kSfxd rFkk@;k izlaLdj.k ;k d`f’k vkS|kSfxd mn~ns”;ksa] fctyh dj?kk o lkFk gh
vkdZ@bUMD”ku QusZlst] jksfyax@fj&jksfyax feYl] y?kq LVhy la;a=ksa ds fy;s rFkk fdlh vU;
nj vuqlwph ds v/khu lfEefyr u fd;s x;s miHkksDrkA
(ii) lCth] Qy] Qwyksa o e”k:e dh [ksrh] izlaLdj.k] HkaMkj.k o iSdsftax ds lkFk d`f"k rFkk tks
vkjVh,l&4 ¼,½ esa vkPNkfnr u gksrs gkas] bl izdkj dh bdkb;k¡ Hkh bl nj vuqlwph esa
lfEefyr gksxhA
2- vkiwfrZ dh fof”k’V “krsZa
(i) lHkh la;kstu] mi;qDr jsfVax rFkk ch-vkbZ-,l- fofunsZ”kuksa ds ,e lh ch ¼fefu;spj lfdZV cszdj½
;k lfdZV cszdj@fLop fx;j ds lkFk la;ksftr fd;s tk;saxsA
(ii) baMD”ku o vkdZ QusZlst dks vkiwfrZ ;g lqfuf”pr dj ysus ds Ik”pkr gh miyC/k djkbZ tk;sxh
fd Lohdr Hkkj QusZlst ds Vust dh Hkkj vko”;drkvksa ds rn~uqlkj gSA 1 Vu dk U;wure~ Hkkj
fdlh Hkh n”kk esa 400 kVA ls de ugha gksxk rFkk lHkh Hkkj blh vk/kkj ij vo/kkfjr fd;s
tk;saxsA bl ekud ls uhps ds fdlh Hkkj ds fy;s dksbZ vkiwfrZ ugha dh tk;sxhA
(iii) LVhy ;wfuV~l dks vkiwfrZ] mi&LVs”ku ds Nksj ij psd ehVj ds lkFk dsoy ,d MsfMdsVsM
bafMfotqoy QhMj ds ek/;e ls 33 kV ;k blls Åij dh oksYVst ij miyC/k djokbZ tk;sxhA
psd ehVj rFkk miHkksDrk ehVj ¼jksa½ dh jhfMaXl ds e/; 3% ls vf/kd ds vaarj dh vuqKkih }kjk
rqjar tk¡p djokbZ tk;sxh rFkk lq/kkjkRed dk;Zokgh dh tk;sxhA
(iv) 1000 kVA ls vf/kd ds Hkkj ds lkFk lHkh u;s la;kstuksa dks vkiwfrZ] mijksDr ds (iii) mica/kksa ds
lkFk dsoy Lora= iks’kdksa ij fuxZr dh tkuh pkfg;sA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
366 Uttarakhand Electricity Regulatory Commission
fooj.k fo|qr izHkkj fLFkj@ekax
izHkkj izfrekg
U;wure miHkksx xkWj.Vh
¼MCG)** 1- 75 kW ¼100 BHP½ rd
lafonkd`r Hkkj okys ,yVh m|ksx
1-1 lafonkd`r Hkkj 25 kW rd :0 4-05@kWh lafonkd`r Hkkj
dk :0 130@ kW
$ Lakfonkdr Hkkj@ekg
dk 50 kWh/ kW rFkk
lafonkdr Hkkj/ okf"kZd
dk 600 kWh/kW
1-2 lafonkd`r Hkkj 25 kW ls
vf/kd
:0 3-70@ kVAh lafonkd`r Hkkj
dk :0 130@ kVA Lakfonkd`r Hkkj@ekg
dk 50 kVAh/ kVA*** rFkk lafonkdr Hkkj/
okf"kZd dk 600 kVAh/kVA 2- 88 kVA /75 kW ¼100 BHP½ ls
Åij lafonkdr Hkkj okys ,pVh
m|ksx
yksM QSDVj#
:0@ kVAh
2-1 lafonkd`r Hkkj 1000 kVA rd 40% rd 3-50
* fcy ;ksX;
ekax dk :0
255@ kVA Lakfonkd`r Hkkj/ ekg dk 100 kVAh/ kVA
rFkk
Lakfonkdr Hkkj/ okf"kZd
dk 1200 kVAh/KVA 40% ls Åij 3-85
2-2 lafonkd`r Hkkj 1000 kVA ls
Åij
40% rd 3-50 * fcy ;ksX;
ekax dk :0
320@ kVA 40% ls Åij 3-85
$vkVk pDdh ds fy, 30 kWh/ kW@ekg rFkk 360 kWh/kW/okf"kZd
*fcy ;ksX; ekax] okLrfod vf/kdre ekax ;k lafonkd`r Hkkj dk 80%] tks vf/kd gks] gksxhA
**U;wure~ miHkksx xkjaVh izHkkj] fLFkj@ekax izHkkj ds vfrfjDr gksxk rFkk rc mn~xzghr fd;k tk;sxk tc ,d ekg dh
vof/k esa miHkksx ,e lh th ls de gks rFkk ;g okf’kZd vk/kkj ij lek;kstu ds v/khu gksxkA ekg esa
U;wure~ miHkksx xkjaVh izHkkj ds vkPNknu gsrq fcYM ;wfuV~l ij fctyh izHkkj dh x.kuk lkekU; vof/k esa 40% rd ds
yksM QSDVj ds fy;s mfYyf[kr izHkkj ij dh tk;sxh rFkk ,sls vfr fctyh izHkkj ds fy;s okf’kZd lek;kstu dh x.kuk]
vxj gksa rks] lkekU; vof/k esa 40% rd ds yksM QSDVj ds fy;s mfYyf[kr izHkkj ij dh tk;sxhA
*** ftu miHkksDrkvksa dk lafonkdr Hkkj kW esa gks] mudk lafonkd`r Hkkj ,elhth ds mn~ns”; gsrq ikoj QSDVj 0-85 ls
x.kuk dh tk,xhA #“kqYd mn~ns”;ksa ds fy;s yksM QSDVj ¼%½ fuEu :Ik esa le>k tk;sxk%&
= fcfyax vof/k esa miHkksx ¼mUeqDr vfHkxeu ls izkIr fo|qr jfgr½ x 100
vf/kdre~ ekax ;k lafonkdr ekax] nksuksa esa ls tks de gks x fcfyax vof/k esa ?kaVksa dh la[;k
;|fi tgk¡ miHkksDrk }kjk mUeqDr vfHkxeu vof/k ds nkSjku fy, tkus ij vf/kdre ekax ml ekg esa c<+ tkus dh
n'kk esa] yksM QSDVj ds vkadyu ds mn~~ns'; gsrq vf/kdre ekax ogh gksxk ftl vof/k esa mUeqDr vfHkxeu u fd;k
x;k gksA
3- le;kuqlkj “kqYd ¼ ToD½ ¼VSfjQ½
(i) 25 kW ls vf/kd Hkkj ds ,y Vh m|ksx rFkk ,p Vh m|ksx ds fy;s Åij fn;s x;s ÅtkZ izHkkj
dh njsa ToD NwV@vf/kHkkj ds v/khu gksaxhA (ii) ToD ehVlZ] dsoy ehVj jhfMax bULVwesaV (MRI) }kjk i<s+ tk;saxsA iw.kZ fo”ys’k.k gsrq Qstj
9. Annexures
Uttarakhand Electricity Regulatory Commission 367
Mk;xzke] Vsaij fjiksZV~lZ] iw.kZ Hkkj losZ fjiksV~lZ bR;kfn ds iw.kZ Mai Mkmu&yksM fd;s tk;saxs rFkk
fcy] izHkkj ToD nj ds vuqlkj tkjh fd;s tk;saxsA (iii) dksbZ Hkh ehVj “kwU; Hkkj ij ;k vR;Ur fuEu Hkkj ij ugha i<+s tk;saxsA vuqKkih mi;qDr okg~;
Hkkj j[ksxk rFkk mDr Hkkj ij MRI ysus ds fy;s tgka vko”;d gks ogk¡ bls ykxw djsxkA (iv) MRI lkjka”k dh izfr] fcy ds lkFk miyC/k djokbZ tk;sxhA Hkkj loZs fjiksVZ lfgr iw.kZ ,e vkj
vkbZ fjiksVZ ekax ij rFkk :0 15@& ds Hkqxrku ij miyC/k djokbZ tk;sxhA (v) ToD Hkkj fuEukuqlkj gksxk %
lhtu@fnu dk
le;
lqcg ihd
vkolZ lkekU; ?k.Vs Lkak; ihd vkolZ
vkWQ ihd
vkolZ
“khrdky
01-10 ls 31-03 0600&0930 cts 0930&1730 cts 1730&2200 cts 2200&0600 cts
Xkzh’edky
01-04 ls 30-09 & 0700&1800 cts 1800&2300 cts 2300&0700 cts
fo|qr ewY; dh ToD nj fuEukuqlkj gksaxh %
,y Vh m|ksx ds fy;s vof/k esa izHkkj dh nj
lkekU; ?k.Vs ihd vkolZ vkWQ ihd vkolZ
:0 3-70@kVAh :0 5-55@kVAh :0 3-33@kVAh
,p Vh m|ksx ds fy;s
yksM QSDVj* vof/k esa izHkkj dh nj
lkekU; ?k.Vs ihd vkolZ vkWQ ihd vkolZ
40% rd :0 3-50@kVAh :0 5-78@kVAh :0 3-15@kVAh 40% ls Åij :0 3-85@kVAh :0 5-78@kVAh :0 3-47@kVAh
*yksM QSDVj Åij [k.M 2 esa ifjHkkf’kr fd;k x;k gSA
4- ekSleh m|ksx
tgk¡ fdlh miHkksDrk ds ikl 18 kW (25 BHP) ls vf/kd dk Hkkj gks rFkk ToD ehVj gks rFkk og o’kZ
esa dqN fuf”pr ekSleksa esa ;k lhfer vof/k ds nkSjku] ?kksf’kr ekSleh m|ksx ds fy;s ÅtkZ dh vkiwfrZ dk
mi;ksx djrk gS rks ftl vof/k esa la;a= can jgrk gS mu eghuksa ¼ftls vkWQ lhtu dgk tk;sxk½ ds fy,
mn~xzg.k fuEukuqlkj fd;k tk;sxk %
(i) *lhtu* vof/k ds fy;s “kqYd ogh gksxk tks bl vuqlwph esa fn;s vuqlkj **izHkkj dh nj** gSaA (ii) tgk¡ **vkWQ lhtu** vof/k esa okLrfod ekax lafonkdr Hkkj ds 30% ls vf/kd ugha gS] ogk¡ **vkWQ
lhtu** vof/k gsrq fo|qr ewY; ogha gksxsa tks Åij vuqlwph dh nj esa nh xbZ **lhtu** vof/k ds
fy;s gSaA rFkkfi **vkWQ lhtu** lafonkdr ekax ?kVkdj 30% dj nh tk;sxhA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
368 Uttarakhand Electricity Regulatory Commission
(iii) vkWQ lhtu vof/k esa vf/kdre vuqKs; ekax] lafonkd`r ekax dk 30% gksxh rFkk ,d miHkksDrk
ftudh okLrfod ekax vkWQ lhtu ds fdlh ekg esa lafonkd`r ekax ds 30% ls vf/kd gksrh gS rks
mUgsa ml lhtu dh vof/k esa ?kVh gqbZ lafonkd`r ekax dk ykHk ugha fn;k tk;sxkA blds vfrfjDr
ekax izHkkj ds 10% dh nj ls iw.kZ **vkWQ lhtu** vof/k gsrq vf/kHkkj ns; gksxkA ekSleh m|ksxksa ds fy;s fuca/ku ,oa “krsZa&
(i) ifjpkyu dh vof/k ,d foRr o’kZ esa 9 ekg ls vf/kd ugha gksuh pkfg;sA (ii) tgk¡ foÙk o’kZ esa ifjpkyu dh vof/k 4 ekg ls vf/kd gS ogk¡ ,sls m|ksx dks de ls de pkj
dzfed ekg rd ifjpkfyr gksuk pkfg;sA (iii) ,d ckj vf/klwfpr lhtuy vof/k dks o’kZ dh vof/k rd ?kVk;k ugha tk ldrkA ekSleh Hkkj ds
lkFk vU; Hkkj /kkfjr dEiksftV bZdkbZ;ksa ij ^vkWQ lhtu^ “kqYd ykxw ugha gksxkA (iv) Pkhuh] cQZ] jkbZl fey] tM+hd`r vkgkj ¼Qzkstu QwM½ rFkk pk; ds vfrfjDr m|ksx vk;ksx ds iwoZ
vuqeksnu ds Ik”pkr~ gh vuqKkih }kjk vf/klwfpr fd;s tk;saxsA 5- QSDVjh ykbZfVax
bl vuqlwph ds v/khu vkiwfrZ dh xbZ fo|qrh; ÅtkZ dk mi;ksx QSDVªh ifjlj esa ykbZV~l] ia[ks] dwylZ]
bR;kfn ds fy;s Hkh fd;k tk;sxk ftlesa dk;kZy;ksa] eq[; QSDVªh Hkou] LVkslZ] VkbZe dhij ds dk;kZy;]
dSUVhu] LVkQ Dyc] iqLrdky;] f”k”kq lnu] vkS’k/kky; LVkQ dY;k.k dsUnzksa] vgkrksa esa QSDVªh ykbfVax ds
fy;s miHkksx dh xbZ lHkh ÅtkZ lfEefyr gksxhA
6- fujarj o vfujarj vkiwfrZ %
(i) fujUrj izfdz;k m|ksx ds lkFk vfujUrj izfØ;k m|ksx ds miHkksDrk tks fd Loa=r QhMj ;k
vkS|kSfxd QhMj ls tqMs+ gkas] fujUrj vkiwfrZ gsrq fodYi pqu ldrs gSA ,d vkS|kSfxd QhMj ls tqMs+
gq, lHkh m|ksxksa ds fujUrj vkiwfrZ fodYi pquus ds mijkUr gh fujUrj vkiwfrZ iznku dh tk;sxh
rFkk ;fn muesa ls dksbZ vkS|kSfxd miHkksDrk fujUrj vkiwfrZ ugha pkgrk gks rks ,sls QhMj ij lHkh
miHkksDrk fujUrj vkiwfrZ dk ykHk mBkus ds fy, vgZ ugha gksaxsA bl rjg dh fujUrj izfdz;k okys
vkS|ksfxd miHkksDrk tks fujUrj vkiwfrZ pqurs gS] mUgsa iwoZ esa lwfpr@vuwlwfpr fctyh dVkSrh ls
rFkk le;≤ ij vk;ksx }kjk vuqeksfnr fctyh miHkksx esa izfrca/k dh vof/k dh lhfer ?kaVs ds
nkSjku ÅtkZ ds vkikrdkyhu :Ik ls BIi gksus ;k can dh fLFkfr dks NksM+dj vU; le; yksM “kSfMax
ls NwV izkIr gksxhA orZeku ds fujUrj vkiwfrZ okys miHkksDrk gsrq Åij mYysf[kr fo|qr izHkkj ds
vykok 15 izfr”kr vfrfjDr fo|qr izHkkj pqdk;saxsA 1 vizSy] 2016 ls vFkok fnuakd 31 ekpZ] 2017
rd ds u;s la;kstu dh n”kk esa] fcuk okLrfod vof/k ds fujUrj vkiwfrZ fodYi gsrq Åij fn;s x;s
izHkkj dh nj ds vuqlkj ekax izHkkj rFkk vU; izHkkj ogha jgsaxsA
9. Annexures
Uttarakhand Electricity Regulatory Commission 369
;|fi Lora= QhMj ds ek/;e ls vkiwfrZ dh iquO;ZoLFkk dh n'kk esa fujUrj vkiwfrZ izHkkj] fujUrj
vkiwfrZ ds fodYi dh okLrfod vof/k ds LFkku ij mDr LorU= QhMj ds Åthdj.k dh frfFk ls
31 ekpZ] 2017 rd ykxw gksxkA ekax izHkkj vkSj vU; izHkkj mijksDr izHkkj dh nj ds vuqlkj leku
jgsxhA (ii) os miHkksDrk tks fd iwoZ esa fujUrj vkiwfrZ fodYi pqus gq, gS] dks fujUrj vkiwfrZ pquus gsrq iqu%
vkosnu djus dh vko”;drk ugha gSA ,sls miHkksDrkvksa dks fnukad 01-04-2016 ls 31-03-2017 rd
Åij mYysf[kr fo|qr izHkkj dk 15 izfr'kr vfrfjDr fo|qr izHkkj ns; gksxkA ;wihlh,y ls ;fn dksbZ
fookn fdlh QhMj esa gks rks ml QhMj ds miHkksDrkvksa dks 30 vizSy] 2016 rd u;s rkSj ls fujUrj
vkiwfrZ gsrq vkosnu djuk gksxkA (iii) fo|qr fujUrj vkiwfrZ ¼tks mijksDrkuqlkj u;s rkSj ij vkosnu dj jgs gksa lfgr½ ds fy, u;s
vkosnd o’kZ esa dHkh Hkh vkosnu ns ldrs gSaA gkykafd] ,sls vkosndksa ds fy;s fujUrj vkiwfrZ ljpktZ
1 ebZ] 2016 ls 31 ekpZ] 2017 rd ds fy;s ykxw jgsxkA ;wihlh,y] vkosnu dh frfFk ls 7 fnuksa ds
nkSjku] fujUrj vkiwfrZ dh “krkZsa dh iwfrZ ds fy, lqfo/kk iznku djsxkA gkykafd] Lora= QhMj ls
vkiwfrZ dk izcU/ku dj fy;s tkus dh fLFkfr esa ;wihlh,y }kjk fujUrj vkiwfrZ dh lqfo/kk] Lora=
QhMj }kjk dk;Z iw.kZ dj fy;s tkus dh frfFk ls] fujUrj vkiwfrZ dh “krkZsa dh iwfrZ ds lkFk] iznku
djsxkA (iv) orZeku esa fujUrj vkiwfrZ dk ykHk mBkus okys miHkksDrk] tks iwoZ esa nh x;h fujUrj vkiwfrZ dks can
djuk pkgrs gks] dks fnuakd 30 vizSy] 2016 ls iwoZ fyf[kr esa lwfpr djuk gksxk vkSj mUgsa fujUrj
vkiwfrZ vf/kHkkj ds lkFk bl vkns”k esa mYysf[kr VSfjQ njksa ds vk/kkj ij 30 vizSy] 2016 rd dh
vof/k dk Hkqxrku djuk gksxkA blds vykok] bl lEcU/k esa ;fn dksbZ miHkksDrk }kjk ,d fo”ks"k
QhMj ij fujUrj vkiwfrZ dk ykHk mBkus ds fodYi NksM+ fn, tkus ij] vU; miHkksDrkvksa dks nh tk
jgh fujUrj vkiwfrZ ds lkFk] mDr QhMj ls tqMs vU; fujUrj vkiwfrZ ds miHkksDrk izHkkfor gksrs gS
rks ;wihlh,y lHkh izHkkfor miHkksDrkvksa dks iwoZ esa fyf[kr :i ls lwfpr djsxkA (v) ;wihlh,y xSj fujUrj vkiwfrZ QhMj ds fy, ,d fujUrj vkiwfrZ QhMj dh fLFkfr dks ifjofrZr ugha
djsxkA (vi) ;wihlh,y@fiVdqy 'kh"kZ izkFkfedrk ds vk/kkj ij ;g lqfuf”pr djsaxs fd o`f)] j[k&j[kko vkSj
ejEer dk;Z fo”ks’kr;k lc&LVs'kuksa esa tgk¡ lfdZV czsdlZ] vU; midj.kksa bR;kfn tksfd th.kZ&”kh.kZ
n'kk esa gS] mulss fujUrj vkiwfrZ QhMj esa :dkoV u gksA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
370 Uttarakhand Electricity Regulatory Commission
(vii) ;wihlh,y@fiVdqy fujUrj vkiwfrZ ds miHkksDrkvksa dks fn;s tk jgs QhMj dh vkof/kd fuokj.k
vuqj{k.k djsxkA ykbZlsalh fujUrj vkiwfrZ ds miHkksDrkvksa dks iwoZ esa vkof/kd fuokj.k vuqj{k.k
dk;Zdze ds ckjs esa lykg mijkUr ;kstuk cukdj lwfpr djsxk] ftlls ,sls miHkksDrk vius dk;Z
dj ldsaA (viii) vuqKkih dks fo|qr ewY; rFkk ml ij fujarj ÅtkZ vf/kHkkj fcy iFkd :Ik ls fn[kkuk pkfg;sA
7- ,pVh m|ksxksa gsrq ekax izHkkj
;fn fdlh ,pVh m|ksx miHkksDrk] tks ekg esa ,d fnu ds 18 ?k.Vs dh U;wure vkSlru vkiwfrZ izkIr
ugha djrs gSa] muds fy, ekax izHkkj Lohd`r ekWax izHkkj dk 80% vuqiz;ksT; gksxkA
9. Annexures
Uttarakhand Electricity Regulatory Commission 371
vkj Vh ,l 8% fefJr Hkkj
1- vuqiz;ksT;rk%
;g vuqlwph 75 kW ls vf/kd ds ,dy fcanq Fkksd vkiwfrZ la;kstu ij ykxw gksrh gS tgk¡ vkiwfrZ
izeq[kr% ?kjsyw mn~ns”;ksa ¼60% ls vf/kd ?kjsyw Hkkj½ ds fy;s rFkk lkFk gh vU; v?kjsyw mn~ns”;ksa ds fy;s
iz/kku :Ik ls mi;ksx esa ykbZ tkrh gSaA ;g vuqlwph MES dks vkiwfrZ ij Hkh ykxw gksrh gSA
2- izHkkj dh nj%
bl Js.kh ds miHkksDrkvksa ij fuEufyf[kr njsa ykxw gksxh %
fLFkj izHkkj fo|qr ewY;
:0 60@kW@ekg :0 4-50@kWh
3- vU; “krsZa %
mijksDr ds vfrfjDr “kqYd dh vU; “krsZ ogh gksaxh] tks vkj-Vh-,l-&1 ds miHkksDrkvksa ds fy;s gSaA
rFkkfi] vf/kHkkj naM] vkiwfrZ dh lkekU; “krksZa ds [k.M 12 ds vuqlkj ykxw gksxkA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
372 Uttarakhand Electricity Regulatory Commission
vkj Vh ,l 9% jsyos VªSD”ku
1- vuqiz;ksT;rk
;g vuqlwph VSªD”ku mn~ns”;ksa ds fy;s ÅtkZ mi;ksx djus okyh jsyos ij ykxw gksrh gSA
2- izHkkj dh nj%
bl Js.kh ds fy;s fuEufyf[kr fo|qr ewY;] ekax izHkkj ykxw gksaxsA
ekax izHkkj fo|qr ewY;
:0@kVA@ekg :0@kVAh 225@& :0 3-95
3- vU; “krsZ %
mijksDr ds vfrfjDr] “kqYd dh vU; “krsZ ogh jgsaxh tks fujarj vkiwfrZ gsrq ToD VSfjQ ,oa vf/kHkkj
dh iz;ksT;rk dks NksM+dj vkjVh,l&7 ds v/khu lkekU; ,p Vh m|ksxksa ds fy;s gSaA
9. Annexures
Uttarakhand Electricity Regulatory Commission 373
vkjVh,l 10 % vLFkk;h vkiwfrZ
¼,½ iznhiu o lkoZtfud lacks/ku vko”;drkvksa gsrq vLFkk;h vkiwfrZ
1- vuqiz;ksT;rk
;g vuqlwph 10 kW rd ds ykbZV vkSj ia[ks] lkoZtfud lacks/ku iz.kkyh] mRloksa] vuq’Bkuksa] eaxy
dk;ksZ ds nkSjku iznhiu Hkkjksa] vf/kdre rhu ekg rd dh vLFkk;h nqdkuksa dh vLFkk;h vkiwfrZ ij ykxw
gksxhA
2- izHkkj dh nj
fooj.k fLFkj izHkkj
¼1½ 15 kW rd ds Hkkj ds iznhiu] lkoZtfud lacks/ku] mRloksa ds fy;s :0 1250 izfrfnu
¼2½ 2 kW rd ds Hkkj okyh] mRloksa ds nkSjku LFkkfir vLFkk;h nqdkusaA :0 85 izfrfnu
¼3½ 1 kW rd ds Hkkj ds fy;s vU; vLFkk;h nqdkuas@>qXxh@>ksiM+h
3-1½ xzkeh.k :0 115@ekg@la;kstu
3-2½ “kgjh :0 230@ekg@la;kstu
mijksDr 2 esa fofufnZ’V fLFkj lsok izHkkj dh jkf”k vfxze :Ik esa yh tk;sxhA
¼ch½ vU; mn~ns”;ksa ds fy;s vLFkk;h vkiwfrZ
1- vuqiz;ksT;rk
(i) ;g vuqlwph 15 kW ls Åij ds Hkkj ds fy;s ¼,½ ij mfYyf[kr ls vU; mn~ns”;ksa ds fy;s
ykbZV] QSu o ÅtkZ Hkkjksa dh vLFkk;h vkiwfrZ ij ykxw gksxh ftlesa iznhiu@lkoZtfud
lacks/ku@mRlo lfEefyr gSaA (ii) ;g vuqlwph] ljdkjh foHkkxksa lfgr lHkh miHkksDrkvksa }kjk flfoy dk;ksZa lfgr fuekZ.k
iz;kstuksa ds fy;s yh xbZ ÅtkZ ds fy;s Hkh ykxw gksxhA fdlh dk;Z@ifj;kstuk ds fy;s
fuekZ.k iz;kstu gsrq ÅtkZ dk;Z@ifj;kstuk ds iw.kZ gksus rd fuekZ.k dk;Z ds fy, izFke
la;kstu ysus dh frfFk ls ekuh tk;sxhA rFkkfi Hkou ds fuekZ.k] ejEer ;k uohuhdj.k ds
fy;s miHkksDrk ds Lo;a ds ifjlj gsrq Lohd`r ,d LFkk;h
la;kstu }kjk fo|qr ds iz;ksx dks fo|qr dk vukf/kdr mi;ksx ugha ekuk tk;sxk] tc rd
fd fuekZ.k fd;s tk jgs orZeku Hkou@vuqyXud dk vk”kf;r iz;kstu@mi;ksx] la;kstd
dh Lohd`r Js.kh esa ogh vuqKs; gSA 2- izHkkj dh nj
izHkkj dh nj] mi;qDr vuqlwph esa izHkkj dh rn~uq:Ik nj ds vfrfjDr 25% gksxhA pkj ¼4½ ekg dh
vf/kdre~ vof/k ds fy;s fn;s x;s 15 BHP rd ds bZ[k nyu ;a= gsrq vLFkk;h vkiwfrZ ds fy;s mi;qDr nj
vuqlwph vkjVh,l&7 gksxhA ;|fi vLFkk;h vkiwfrZ gsrq U;wure miHkksx xkj.Vh izHkkj ykxw ugha gksaxsA
Order on approval of Business Plan and Multi Year Tariff of UPCL for FY 2016-17 to FY 2018-19
374 Uttarakhand Electricity Regulatory Commission
9-2 layXud 2% fofo/k izHkkjksa dh vuqlwph
dz0
la0 izHkkjksa dk LoHkko ;wfuV
nj
¼:0½
1- ehVjksa dh tkWp o ijh{k.k
,- flaxy Qst ehVlZ izfr ehVj 50-00
Ckh- rhu Qst ehVlZ izfr ehVj 75-00
Lkh- fjdkfMZax VkbZi okWV&vkoj ehVlZ izfr ehVj 170-00
Mh- vf/kdre ekax ladsrd@,yVh lhVh lapkfyr eksVlZ izfr ehVj 350-00
bZ- VªkbZ osDVj ehVlZ@,pVh ehVlZ lhVh@ihVh ds lkFk izfr ehVj 1000-00
,Q- ,ehVlZ ,aM oksYV ehVlZ izfr ehVj 65-00
Tkh- Lis”ky ehVlZ izfr ehVj 335-00
,p- ehVjksa dk izkFkfed ijh{k.k izfr ehVj “kwU;
2- izkFkfed ijh{k.k ls vU; ckn dk ijh{k.k rFkk laLFkkiu izfr ehVj 80-00
3- fdlh Hkh dkj.k ls ¼fdlh la;kstu ds dkVus ;k iquZla;kstu ds fy;s½
vkiwfrZ dk la;kstu dkVuk ;k iqula;kstu dk izHkkj 50% gksxkA
,- 100 BHP@75 kW ls Åij Hkkj okys miHkksDrk Ikzfr tkWc 600-00
Ckh- 100 BHP@75 kW rd ds v?kjsyw rFkk vkS|ksfxd miHkksDrk Ikzfr tkWc 400-00
Lkh- miHkksDrkvksa dh vU; lHkh Jsf.k;k¡ Ikzfr tkWc 200-00
4- ehVjksa dk cnyuk
,- ehVj dk laLFkkiu rFkk vLFkk;h la;kstu dh voLFkk esa bldk gVk;k
tkukA Ikzfr tkWc 75-00
ch- miHkksDrk ds fuosnu ij ehVj cksMZ dh fLFkfr esa ifjorZu Ikzfr tkWc 100-00
5- miHkksDRkk ds fuosnu ij dSisflVlZ dh tkWp ¼izkjafHkd tkWp ds vfrfjDr½%
,- 400V@230 V ij Ikzfr tkWc 150-00
ch- 11 kV rFkk blls Åij ij Ikzfr tkWc 300-00