207
FINAL SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT UCSF MEDICAL CENTER AT MISSION BAY— PHASE 1 GARAGE State Clearinghouse Number 2008012075 University of California, San Francisco Certified by the UCSF Chancellor: June 21, 2011 Draft SEIR Publication Date: February 25, 2011 Draft SEIR Public Review Period: February 25, 2011 through April 11, 2011 Draft SEIR Public Hearing Date: March 28, 2011 Final SEIR Date: April 25, 2011 Notice of Determination Date: June 23, 2011 Lead Agency: The University of California Prepared by: UCSF Campus Planning 654 Minnesota Street San Francisco, CA 941430286 Contact: Environmental Coordinator (415) 4762911 University of California San Francisco Campus Planning

Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

FINAL SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT 

 

 

UCSF MEDICAL CENTER AT MISSION BAY— 

PHASE 1 GARAGE 

State Clearinghouse Number 2008012075 

 

University of California, San Francisco 

 

 

 

 

 

Certified by the UCSF Chancellor:  June 21, 2011 

Draft SEIR Publication Date:    February 25, 2011  

Draft SEIR Public Review Period:    February 25, 2011 through April 11, 2011  

Draft SEIR Public Hearing Date:    March 28, 2011  

Final SEIR Date:        April 25, 2011 

Notice of Determination Date:    June 23, 2011 

 

Lead Agency:  The University of California 

 

 

Prepared by:  UCSF Campus Planning 

  654 Minnesota Street 

  San Francisco, CA  94143‐0286 

 

Contact:  Environmental Coordinator 

  (415) 476‐2911 

University of California San Francisco Campus Planning

Page 2: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

 

 

 

 

 

[This page intentionally left blank.]

Page 3: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 i 

 

TABLE OF CONTENTS SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT 

UCSF MEDICAL CENTER AT MISSION BAY –  

PHASE 1 GARAGE Page 

   1.  INTRODUCTION 

1.1  Purpose of this Document .................................................................................................... 1 1.2  Organization of the Document ............................................................................................ 3 

   2.  SUMMARY 

2.1  Background ............................................................................................................................ 4 2.2  Project Description ................................................................................................................ 4 2.3  Summary of Project Impacts ................................................................................................ 5 2.4  Summary of Alternatives Analysis ................................................................................... 12 2.5  Areas of Controversy .......................................................................................................... 14 

   3.  PROJECT DESCRIPTION 

3.1  Background .......................................................................................................................... 15 3.2  Project Description .............................................................................................................. 15 3.3  Project Objectives ................................................................................................................ 21 3.4  Mitigation Monitoring ........................................................................................................ 22 3.5  Required Approvals ............................................................................................................ 22 

 

  4.  ENVIRONMENTAL SETTING, IMPACTS, AND MITIGATION 

4.0  Scope of Analyses  ............................................................................................................... 23 4.1  Greenhouse Gas Emissions ................................................................................................ 24 4.2  Transportation ..................................................................................................................... 56 

   5.  CEQA STATUTORY SECTIONS 

5.1  Significant Unavoidable Environmental Impacts ........................................................... 60 5.2  Cumulative Impacts ............................................................................................................ 60 5.3  Growth‐Inducing Impacts .................................................................................................. 60 5.4  Effects Found Not to Be Significant .................................................................................. 60 5.5  Significant Irreversible Environmental Changes ............................................................ 60   

  6.  ALTERNATIVES 

6.1  Alternatives Analysis .......................................................................................................... 62 

Page 4: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

ii 

7.  REPORT PREPARATION   

7.1  Report Authors .................................................................................................................... 65  

8.  COMMENTS AND RESPONSES   

8.1  Overview .............................................................................................................................. 66 8.2  Public Hearing Transcript .................................................................................................. 66 

  9.  MITIGATION MONITORING AND REPORTING PROGRAM ...................................... 73 

 

 

LIST OF FIGURES 

3‐1  Project Location ................................................................................................................... 16 3‐2  Project Site ............................................................................................................................ 17 3‐3  Project Site Plan ................................................................................................................... 18 3‐4  Project Site Plan/First Floor Plan ....................................................................................... 19 3‐5  Approach from Owens Street ............................................................................................ 20 

 APPENDICES 

A.  Initial Study B.  Air Emissions Estimates C.  Energy Efficiency Projects  

Note:  A solid dot (●) indicates new chapter or section compared to the Draft SEIR. 

Page 5: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 1 of 74 

CHAPTER 1 INTRODUCTION 

1.1  PURPOSE OF THIS DOCUMENT 

This Supplemental Environmental Impact Report (“SEIR”) is an informational document 

prepared in accordance with the California Environmental Quality Act, Public Resources Code 

Sections 21000, et seq. (“CEQA”).  It is intended to provide to decision‐makers and the public 

supplemental environmental information concerning the proposed construction and operation of 

a parking garage at the University of California, San Francisco (UCSF) Medical Center at Mission 

Bay.  The proposed parking garage is part of the phased development of an integrated hospital 

complex to serve children, women and cancer patients at its existing 57‐acre campus site at 

Mission Bay.  

The University of California (University) is the Lead Agency and The Regents of the University 

of California (The Regents), or its delegated committee or administrative official, is the decision‐

making body for the project.  On September 17, 2008, The Regents certified the EIR for the UCSF 

Medical Center at Mission Bay (MCMB) and approved components of Phase I consisting of the 

hospital, energy center, outpatient building, medical helipad, and surface parking.   Approval of 

the cancer outpatient building and Phase I garage was deferred pending funding and design of 

those facilities.  Construction of the approved components of the Medical Center project has now 

commenced, beginning with site development and construction of the hospital and outpatient 

building.   

The proposed Phase I parking garage was fully analyzed in the UCSF Medical Center at Mission 

Bay EIR (UCSF MCMB EIR).  This SEIR has been prepared to update the UCSF MCMB EIR in 

order to analyze three minor changes to the proposed Phase I garage.  In addition, this SEIR 

updates the greenhouse gas (GHG) emissions analysis for the proposed Phase I garage in light of 

new GHG significance criteria recently adopted by the Bay Area Air Quality Management 

District (BAAQMD).  This SEIR focuses on two topics that are affected by the proposed revisions 

to the project:  greenhouse gas emissions and transportation.  All other environmental topics 

were adequately analyzed in the UCSF MCMB EIR and require no further analysis, as 

determined in the Initial Study for this project (see Appendix A).  Pursuant to Section 15163(b), 

this supplement to the EIR contains only the information necessary to make the previous EIR 

adequate for the project as revised.   

Under CEQA Guidelines Section 15162, a subsequent EIR is required only when, among other 

criteria, “substantial changes are proposed in the project which will require major revisions of 

the previous EIR or negative declaration due to the involvement of new significant 

Page 6: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 2 of 74 

 

environmental effects or a substantial increase in the severity of previously identified significant 

effects.”  CEQA Guidelines Section 15163 allows the lead agency to choose to prepare a 

supplement to an EIR rather than a subsequent EIR if “only minor additions or changes would be 

necessary to make the previous EIR adequately apply to the project in the changed situation.” 

The changes proposed to the project consist of the increase in the number of parking spaces 

within the garage by 26 spaces (for a total of about 626 spaces), the increase in height by 15 feet 

(to a total of about 105 feet), and relocation of the Phase I garage to a portion of the hospital site 

north of the originally proposed site.  Only minor additions to the UCSF MCMB EIR are 

necessary for the EIR to adequately address the proposed project.  Because of the modest nature 

of these project changes, a supplement to the UCSF MCMB EIR has been prepared. 

Page 7: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 3 of 74 

 

1.2  ORGANIZATION OF THE DOCUMENT 

This document is organized into the following chapters: 

Chapter 1, Introduction:  Describes the purpose of this SEIR. 

Chapter 2, Summary:  Summarizes the supplemental environmental impact analysis. 

Chapter 3, Project Description:  Provides a description of the modified project, project objectives, project consistency with the LRDP, mitigation monitoring, and required approvals by other agencies. 

Chapter 4, Environmental Settings, Impacts and Mitigation Measures:  Describes the scope of this SEIR, focusing on impact topics of relevance to the modified project. 

Chapter 5, CEQA Statutory Sections:  Discusses various CEQA mandated considerations including unavoidable environmental impacts, cumulative impacts, and growth inducing impacts.   

Chapter 6, Alternatives:  Discusses the alternatives to the project already analyzed in the UCSF MCMB EIR, and includes additional alternatives. 

Chapter 7, Report Preparation:  Lists report authors, in this case UCSF Campus Planning staff, and other consulting staff that assisted with the preparation and review of the SEIR.  Identifies persons, agencies and organizations that were consulted. 

Page 8: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 4 of 74 

CHAPTER 2 SUMMARY  

2.1  BACKGROUND 

On September 17, 2008, The Regents certified the EIR for the UCSF Medical Center at Mission 

Bay (MCMB) (State Clearinghouse No. 2008012075) and approved components of Phase I 

consisting of the 289‐bed hospital, energy center, outpatient building, medical helipad, and 

surface parking.1  Approval of the cancer outpatient building and Phase I garage was deferred 

pending funding and design of those facilities.  Construction of the approved components of the 

Medical Center project has now commenced, beginning with site development and construction 

of the hospital and outpatient building.  The complex is scheduled to open in 2014.  With 

approved funding of the Phase I garage, the University is now prepared to seek approval of its 

design and construction. 

2.2  PROJECT DESCRIPTION 

The Medical Center project site is bordered by 16th Street to the north, 3rd Street to the east, and 

Mariposa Street to the south.  In the future, a new segment of Owens Street will define the western 

boundary of the project site.  The parking structure analyzed in the MCMB EIR consisted of a 600‐

space garage of approximately 90 feet in height, located along the western edge of the site on 

Owens Street between the South Connector Road and the Center Garage Access (now Parking 

Structure Road).  The medical center program envisioned in Phase II the expansion of the garage 

to the north between the Center Garage Access and the North Connector Road.  The garage is 

now proposed to be approximately 626 spaces and an additional story at about 105 feet in height.  

In addition, the Phase I garage is now proposed to the north, between the North Connector Road 

and Parking Structure Road, the originally proposed location of the Phase II garage (see Figure 3‐

3).  Phase II of the garage would expand the structure to the south from Parking Structure Road 

to South Connector Road. 

The number of surface parking spaces proposed on the remainder of Blocks 38 and 39 in Phase I 

has been reduced from 475 spaces to approximately 429 spaces, with an additional 13 spaces east 

of the future extension of 4th Street,  in what  is known as the east lot. The total surface parking 

spaces  would  be  approximately  442  compared  to  the  475  spaces  analyzed  in  the  2008  EIR. 

Therefore,  the  total number of parking  spaces provided  in Phase  I  (626  spaces  in  the parking 

1   The UCSF Medical Center at Mission Bay EIR is available online at 

http://campusplanning.ucsf.edu/physical/RFEIRHospital.php. 

Page 9: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 5 of 74 

 

structure and 442  surface parking  spaces) would decrease by approximately  seven  spaces and 

would total approximately 1,068‐parking spaces from 1,075 spaces (see Figure 3‐4).  

2.3  SUMMARY OF PROJECT IMPACTS 

2.3.1  GREENHOUSE GAS 

Global climate change refers to any significant change in climate measurements, such as 

temperature, precipitation, or wind, lasting for an extended period (i.e., decades or longer) (U.S. 

EPA 2008b). To gauge the potency of GHGs, scientists have established a Global Warming 

Potential (GWP) for each GHG based on its ability to absorb and re‐emit long‐wave radiation 

over a specific period. The GWP of a gas is determined using CO2 as the reference gas, which has 

a GWP of 1 over 100 years (IPCC 1996). The sum of each GHG multiplied by its associated GWP 

is referred to as “carbon dioxide equivalents” (CO2e). 

Significance Criteria  

In accordance with Senate Bill (SB) 97, the Natural Resources Agency adopted amendments to 

the State CEQA Guidelines on December 30, 2009 (effective March 2010), which include criteria for 

evaluating GHG emissions.2  According to the amended Appendix G of the State CEQA 

Guidelines, a project would have a significant effect on the environment if it would:  

Generate greenhouse gas emissions, either directly or indirectly, that may have a 

significant impact on the environment; or  

Conflict with an applicable plan, policy or regulation adopted for the purpose of 

reducing the emissions of greenhouse gases.  

The Bay Area Air Quality Management District (BAAQMD) has established project‐level 

screening criteria and significance thresholds for operational GHG emissions in its CEQA Air 

Quality Guidelines. The BAAQMD’s thresholds of significance for operational‐related GHG 

emissions are as follows:  

For land use development projects, the threshold is compliance with a qualified GHG 

Reduction Strategy; or annual emissions less than 1,100 metric tons CO2e per year 

(MTCO2e/yr); or 4.6 MT CO2e/person/yr (residents plus employees). Land use 

development projects include residential, commercial, industrial, and public land uses 

and facilities.  

For stationary‐source projects, the threshold is 10,000 MTCO2e/yr. Stationary‐source 

projects include land uses that would accommodate processes and equipment that emit 

GHG emissions and would require an Air District permit to operate.  

2 http://ceres.ca.gov/ceqa/guidelines/

Page 10: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 6 of 74 

 

The BAAQMD guidelines do not contain a quantitative threshold of significance for the 

evaluation of GHG emissions resulting from a project’s construction activities.  

Based on the above, the proposed project’s significance with respect to the GHG emissions and 

global climate change will be assessed based on the BAAQMD’s GHG thresholds of significance 

and on the project features and GHG reduction measures that are consistent with the BAAQMD’s 

recommended measures to reduce GHG emissions.  

Impacts and Mitigation Measures 

Impact GHG‐1: Project development would generate greenhouse gas emissions, either directly 

or indirectly, that could have a significant impact on the environment. (Significant; Less than 

significant with mitigation)  

 

Operational Impacts  

Once operational, the proposed project would generate direct operational emissions of GHGs, 

primarily CO2, CH4, and N2O, which would be the result of fuel combustion from the building’s 

lighting and elevator systems, from fuel combustion by the motor vehicles using the garage, and 

from motor vehicle air conditioning.  

 Estimated emissions from mobile sources (transportation) would be 3,168 metric tons of CO2e, 

and emissions from non‐mobile sources would be 627 metric tons of CO2e, resulting in a total of 

about 3,795 metric tons of CO2e. 

These emissions present a worst case scenario.  Transportation emissions will decline in the 

future as new motor vehicles with lower tailpipe emissions required by existing State (Pavley) 

and Federal regulations are adopted into the vehicle fleet.  As shown in Table 4.1‐3, the proposed 

project’s operational emissions would exceed the project level threshold of 1,100 MTCO2e for 

land use development projects. The project’s impact would therefore be significant.  

Phase I Garage Mitigation:  The Regents have committed the University system to reduce its 

GHG emissions from all of its operations to the 1990 level by 2020.  In furtherance of the goal to 

meet these goals, the University is currently implementing the 2010‐12 Statewide Energy 

Partnership Program (through the UC Strategic Energy Plan), an ambitious three year program 

to help meet its goal.  This 3 year program, in its second year of implementation, is expected to 

reduce energy consumption by 11%, natural gas consumption by 8%, and greenhouse gas 

emissions by 9% system‐wide.    

As identified in the UCSF Climate Action Plan, UCSF is undertaking many of these energy 

efficiency projects to retrofit existing facilities in order to assist the campus to meet its 

greenhouse gas goals.  These energy efficiency projects at UCSF provide more than 2,700 

MtCO2e ongoing new reductions per year.  Detail on campus specific reduction projects are 

Page 11: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 7 of 74 

 

described in the UC system wide Strategic Energy Plan.3 

The Regents has approved funding for the 2010 Statewide Energy Partnership Program / UC 

Strategic Energy Plan.  UCSF would mitigate at least 2,700 MtCO2e ongoing reductions per year, 

e.g. the additional significant GHG emissions associated with the proposed garage project, with 

the appropriate number of energy efficiency projects identified on the list in Supplemental EIR 

Appendix C.  Projects identified in Appendix C are those projects that are included in the 

funded, UC Strategic Energy Plan and that are planned to be implemented by 2012, around the 

time garage operations would begin. 

Significance after Mitigation:  Less than Significant   

 

Construction Impacts  

Construction of the proposed project, which would include activities such as grading/excavation, 

trenching, building construction, and architectural coating, would result in one‐time emissions of 

greenhouse gases. Construction of the proposed project is anticipated to commence in Summer 

2011 and continue for approximately 12 months. 

The BAAQMD does not have a quantitative threshold of significance for construction‐related 

GHG emissions. However, the CEQA Air Quality Guidelines requires the Lead Agency to quantify 

and disclose GHG emissions that would occur during construction. Table 4.1‐4, Estimated 

Construction GHG Emissions shows a summary of total estimated GHG emissions from the 

construction of the proposed project, about 500.5 metric tons of CO2e over the course of the two 

year construction period (2011 and 2012).  Given the low numbers, the fact that they are much 

lower than the threshold for operational emissions, and the fact that these would be one‐time 

emissions, the effect on global climate from the proposed project’s construction would not be 

substantial.  

Impact GHG‐2: The proposed project could conflict with an applicable plan, policy or 

regulation adopted for the purpose of reducing the emissions of greenhouse gases. (Less than 

Significant) 

The primary GHG emissions regulation in California is AB 32, which is discussed above. The 

BAAQMD GHG significance threshold was specifically designed to ensure compliance with AB 

32 emissions reductions requirements in the Bay Area. The project would not set back AB 32 

efforts for the Bay Area air basin.  

The BAAQMD 2010 Clean Air Plan contains energy, transportation, and mobile source control 

measures that would reduce operational GHG emissions and that would be potentially 

applicable to the project. The project includes project design features that are generally consistent 

with potentially applicable measures. Furthermore, UCSF has incorporated into the proposed 

3 http://www.universityofcalifornia.edu/sustainability/documents/ucsep_sw.pdf page 14/21

Page 12: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 8 of 74 

 

project substantial sustainability features, including several GHG mitigation measures included 

in the BAAQMD CEQA guidelines.  

With implementation of the reduction projects identified in Impact GHG‐1, emissions would be 

mitigated to less than 1,100 MMTCO2e /year. The proposed project would not conflict with an 

applicable plan, policy or regulation adopted for the purpose of reducing the emissions of 

greenhouse gases. 

The Regents has committed the UC system to meet the State of California’s AB32 goal to reduce 

GHG emissions to 1990 levels by 2020 through the policies identified in the University of 

California Policy on Sustainable Practices.4   UCSF is in compliance with the University of 

California’s Policy on Sustainable Practices by completing all four implementation procedures 

identified in the Policy. 

The proposed project would also be consistent with the UCSF Climate Action Plan (UCSF 2009). 

The Climate Action Plan contains the following transportation‐related measures would reduce 

transportation‐related GHG emissions:  

Transportation Demand Management (TDM) Program – UCSF’s TDM conforms with San 

Francisco’s Transit First Policy to encourage the use of alternative transportation to single‐

occupancy vehicles. UCSF has excellent transit ridership rates according to latest transportation 

survey. About 25.6% of respondents (faculty, staff, and students) reported taking public transit 

(e.g., Muni or other bus system) as their main transportation choice in the latest mobility 

choices survey.  

Bicycling Accommodations ‐Bicycle racks have been expanded from 400 spaces in 2003 

to 680 in 2008. There are now 53 shuttle mounted bike racks. Expenditures on new bike 

racks were $13,445 in 2008. UCSF bicyclists are eligible for a reduced price membership 

in the San Francisco Bicycle Coalition.  

Fuel Efficient Vehicles – The Campus supplies 2 electric vehicle charging stations. Fifteen 

percent (42 of 273) of campus fleet vehicles are powered by alternative fuel or a hybrid 

electric and gas. The Campus offers 103 motorcycle parking stalls.  

Transit Pass sales –To further encourage transit use UCSF offers the Campus community 

5 convenient locations to purchase city and regional transit passes. MUNI Fast Pass and 

Bart Commuter Ticket Monthly sales are 600 passes in 2008.  

Vanpools – The number of vanpools increased from 30 in 2003 to 46 in 2008 and the 

number of car sharing from three to 17 during the same period. These efforts, led by 

UCSF Transportation Services, earned UCSF a place on the inaugural 2006 national list of 

Best Workplaces for Commuters from colleges and universities, awarded by the US 

Environmental Protection Agency (EPA). Vanpools receive preferential parking spaces at 

4 http://www.universityofcalifornia.edu/sustainability/documents/policy_sustain_prac.pdf

Page 13: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 9 of 74 

 

UCSF.  

The UCSF Climate Action Plan contains the following Strategic Energy Plan improvements that 

are pertinent to the proposed project. These measures will be investigated for potential 

implementation by the proposed project and would reduce energy demand and associated GHG 

emissions:  

Lighting Projects UCSF will continue to convert existing T12 and 32 watt T8 fluorescent 

light fixtures to 28 watt T8 lamps. Other possibilities include: broader use of occupancy 

sensor controls, daylight harvesting, and new stairwell fixtures. The replacement of 

lighting in parking structures and interior HID fixtures and with fluorescent will also be 

evaluated. New technologies such as LED lighting, bi‐level fixtures and induction lamps 

are anticipated to become readily available in the near future and these technologies will 

be incorporated into energy efficiency retrofit projects where appropriate.  

The proposed project includes secure bicycle parking, parking fees, and electric vehicle charging 

stations.  In addition, garage attendants would be available to provide information on alternative 

transportation and sell transit passes. The project could also provide preferential parking spaces 

for carpools and vanpools, depending on need, consistent with UCSF guidelines. These measures 

would reduce transportation‐related GHG emissions consistent with the Climate Action Plan 

measures. The project would also be designed to minimize the energy demand by using energy‐

efficient lighting (fluorescent, LED lighting, or similar depending on cost effectiveness). Based on 

the inclusion of these project design features, the project would be consistent with applicable 

plans that have been adopted to reduce GHG emissions. The impact would be less than 

significant.  

Mitigation: No additional mitigation is required.  

 

2.3.2  TRANSPORTATION 

This section evaluates potential changes to the transportation analysis of the MCMB EIR as a 

result of the minor modifications to the proposed Phase I garage project. The MCMB EIR 

concluded that the construction and operation of the Medical Center at Mission Bay, including 

the proposed Phase I garage, would not cause a substantial adverse impact to transit, pedestrian, 

bicycle, or parking conditions, nor result in inadequate emergency access.  The modifications to 

the proposed project would not change the effects anticipated in these topic areas. Therefore, this 

analysis focuses on any potential changes to operational traffic impacts.   

 

Significance Criteria  

The significance criteria and analysis methodology of the MCMB EIR remain unchanged with 

regard to transportation and traffic.  Traffic impacts were analyzed using the concept of Level of 

Page 14: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 10 of 74 

 

Service (LOS), which describes the level of the performance of an intersection based on the 

average delay per vehicle.  Intersection LOS ranges from LOS A, which indicates free‐flow 

conditions with little or no delays, to LOS F, which indicates congested or overloaded conditions 

with extremely long delays.  LOS D, which indicates increasingly unacceptable, yet tolerable, 

delays, is considered to be the minimum acceptable level of service.   

As discussed in the Project Description, although the number of parking spaces within the 

proposed garage has been increased from 600 spaces to 626 spaces with the modified project, the 

number of parking spaces within the surface parking lot, which has been approved, has 

decreased.  The total number of parking spaces in Phase I (626 spaces in the parking structure 

and 442 surface parking spaces) has decreased by approximately seven spaces and would total 

approximately 1,068‐parking spaces, down from the previously analyzed 1,075 spaces.  As 

discussed in the Project Description, the Phase I garage is now proposed to the north, between 

North Connector Road and Parking Structure Road.  Roadways internal to the site and 

connections to surrounding public streets, including Owens Street, would remain unchanged.   

Impacts and Mitigation Measures 

A Transportation Study was prepared for the MCMB EIR.5 The Transportation Study evaluated 

both the Phase I and future buildout of the Phase II development. In addition, the traffic study 

evaluated two potential alternatives for the operation of 4th Street through the Medical Center 

site. Both alternatives would convert the proposed 4th Street right‐of‐way to University of 

California property. 

 

Based on the analysis contained with the Transportation Study, traffic impacts resulting from 

Phase I of the Medical Center at Mission Bay would be less than significant, as all study 

intersections would continue to operate at level‐of‐service D or better.  The impacts analysis 

below updates the impacts analysis of the MCMB EIR. 

 

Construction Impacts  

Impact MCMB.6‐1 of the MCMB EIR (analysis updated with this SEIR):  The MCMB EIR 

concluded that construction of the MCMB Phase I project, including the Phase I garage, 

would not result in significant construction‐period impacts. (Less than Significant) 

 

The MCMB EIR concluded that MCMB Phase I construction activities would temporarily 

increase traffic on area roadways (due to construction employee auto trips and construction 

truck traffic), as well as demand for parking in the area.  In addition, the staging of vehicles and 

construction materials would require temporary closure of on‐street parking near the 

construction site.  The MCMB EIR concluded that the LRDP Amendment #2 – Hospital 

Replacement EIR mitigation measure 4.11‐1, which includes limiting the use of local roads as 

haul routes, and/or limiting truck trips to off‐peak hours, and/or developing a parking plan for 

5 Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation Study, March 2008.  

Page 15: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 11 of 74 

 

construction employees, would ensure transportation‐related construction impacts would be 

reduced to less than significant levels.  In furtherance of this mitigation measure, the proposed 

Phase I garage, once completed, on a temporary basis would provide some construction 

employee parking until construction of the hospital and surface parking lot is complete. 

 

Mitigation:  None required. 

 

Operational Impacts  

 

Impact MCMB.6‐2 of the MCMB EIR (analysis updated with this SEIR):  The MCMB EIR 

concluded that operation of the MCMB project, including the Phase I garage, would not result 

in a significant impact on the adjacent roadway network.  (Less than Significant) 

 

As discussed in the Project Description, while the number of parking spaces in the parking 

structure (from 600 to 626) would increase as a result of the changes to the proposed project,, the 

total number of parking spaces would decrease by about 7 spaces as a result of the proposed 

decrease in surface parking.  Although the location of the Phase I garage is now proposed in the 

location of the proposed Phase II garage, to the north of the previously proposed Phase I garage 

site, effects on traffic would continue to be less than significant in Phase I.  Overall site circulation 

and access to the parking garage would remain substantially the same.  Multiple access points 

to/from the parking facility (including the adjoining surface lot) would continue to be from North 

Connector Road, South Connector Road, West Connector Road, and Parking Structure Road 

(formerly Center Garage Access), all campus streets on the Medical Center site.  Effects on traffic 

at surrounding study intersections would remain largely unchanged.  As a result of the 

relocation of the Phase I garage to north, Parking Structure Road/ Owens Street could experience 

incrementally more traffic in Phase I than previously anticipated, but not to the degree that the 

level of service would deteriorate to unacceptable levels. Multiple roadway access would 

continue to be available to the garage, as previously analyzed, and assumptions regarding the 

distribution of traffic at nearby intersections would not substantially change.   

 

Mitigation:  None required. 

 

Impact MCMB.6‐3 of the MCMB EIR (analysis updated with this SEIR):  Operation of the 

UCSF Medical Center at Mission Bay project would increase traffic at intersections on the 

adjacent roadway network in the Future Phase (Phase II).  (Significant) 

The MCMB EIR traffic analysis of the full project (Phase I and Phase II) would not change 

substantially with the modified project.  With the modified project, the construction of the Phase 

II garage would occur to the south of the Phase I garage, at the original location of the Phase I 

garage.  The significant traffic impact at 16th/Owens in Phase II would continue to be significant 

with the modified project.  The potential impact at Owens/Center Garage Access would remain 

speculative pending project‐level analysis of the traffic and circulation analyses for Phase II. 

Page 16: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 12 of 74 

 

Mitigation:  The mitigation measures identified in the MCMB EIR to address significant traffic 

impacts in Phase II would remain unchanged, as follows: 

16th/Owens:  Mitigation Measure 4.11‐2a from the LRDP Amendment #2 EIR identifies 

modifications to the Owen Street lane configurations (i.e. restriping) to mitigate the 

impact at this intersection:  one southbound shared through‐left turn lane, one 

southbound through lane, and one southbound exclusive right turn lane, would remain 

the same. 

 

Significance after Mitigation: Less than significant. Implementation of the re‐striping at 

this location would improve the operating conditions at this intersection to an acceptable 

LOS D.  The City of San Francisco has found the mitigation measure to be feasible, and 

has committed to working with UCSF to ensure its implementation.6 

 

Owens Street at Center Garage Access:  Mitigation Measure MCMB.6‐3 from the 

Medical Center at Mission Bay EIR would require that UCSF conduct a project‐level 

CEQA review at the time the Phase II development is considered for approval. In 

addition, in order to determine the need for LOS improvements on Owens Street, 

between 16th and Mariposa Streets at Center Garage Access (now Parking Structure 

Road), such as a traffic signal, UCSF would coordinate with the City of San Francisco in 

the periodic update of the Mission Bay traffic triggers survey and would monitor on‐site 

parking access and circulation in order to determine the need for LOS improvements.  

 

Significance after Mitigation:  The need for LOS improvements on Owens Street at the 

Center Garage Access in Phase II remains speculative pending a project‐level design of 

parking requirements and project‐level traffic and circulation evaluation. 

 

2.4  SUMMARY OF ALTERNATIVES ANALYSIS 

2.4.1  NO PROJECT ALTERNATIVE 

CEQA requires that a “No Project” alternative be considered.  Under this alternative, the UCSF 

Medical Center at Mission Bay would be developed as proposed except that the garage would 

not be constructed.  The 442‐parking space surface lots, which have been approved, would be 

constructed as planned.     

This alternative would not meet any of the project objectives. 

Greenhouse Gas Emissions 

With the proposed project, impacts on greenhouse gas emissions would be significant, but would 

be reduced to less than significant levels with mitigation. While the No Project Alternative would 

6 Comment letter dated July 3, 2008 from the San Francisco Municipal Transportation Agency, on the UCSF 

Medical Center at Mission Bay Draft EIR. 

Page 17: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 13 of 74 

 

mean no parking structure would be provided, it is still anticipated that a substantial number of 

patients, visitors, and employees would need to drive to the site.  It is likely that the amount of 

greenhouse gas emissions would be significant, as with the modified project, but those emissions 

could be reduced to less‐than‐significant levels with the implementation of the energy efficiency 

projects identified as mitigation for the modified project. 

Transportation 

The proposed project would result in less than significant impacts on traffic, as would the No 

Project Alternative.  Without a garage on the Medical Center at Mission Bay site, more drivers 

may search for parking in the vicinity, thus more traffic may occur in the surrounding 

neighborhood than with the proposed project.  However, traffic impacts under the No Project 

Alternative would be less than significant. 

2.4.2  REDUCED PROJECT ALTERNATIVE 

Under the Reduced Project Alternative, the number of parking spaces would be reduced to 

approximately one‐half the number of spaces, or about 300 spaces.  The number of parking 

spaces within the surface parking lots, which have been approved, would remain the same at 442 

spaces. 

This alternative would meet the project objectives to (1) ensure that development is compatible 

with and responsive to building scale and character in the surrounding areas; and (2) provide a 

parking structure that incorporates sustainability features to the greatest extent feasible. 

This alternative would only satisfy a portion of the expected parking demand by patients, 

visitors, and staff, and therefore would only partially meet the project objectives to (1) develop a 

patient‐friendly hospital (convenient location, availability of parking, efficient patient/emergency 

access, proximity of related patient service, etc.); (2) develop a staff‐friendly hospital (availability 

of parking, proximity to amenities, loading/delivery access, etc.); (3) support UCSF’s mission of 

patient care by enhancing access to UCSF facilities through convenient, affordable parking for 

those who often cannot utilize alternative forms of transportation; (4) provide parking for those 

essential healthcare providers for whom alternative forms of transportation is infeasible due to 

atypical work hours and responsibilities at multiple campus sites; and (5) avoid pressure on 

neighborhood on‐street parking. 

Greenhouse Gas Emissions 

With the proposed project, impacts on greenhouse gas emissions would be significant, but would 

be reduced to less than significant levels with mitigation. The Reduced Project Alternative would 

likely result in significant greenhouse gas emissions that could be reduced to less than significant 

levels with mitigation, similar to the proposed project.   

Page 18: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 14 of 74 

 

Transportation 

The proposed project would result in less than significant impacts on traffic, as would the 

Reduced Project Alternative.   With fewer parking spaces on the Medical Center at Mission Bay 

site, more drivers may search for parking in the vicinity, thus more traffic may occur in the 

surrounding neighborhood than with the proposed project.  However, traffic impacts under the 

Reduced Project Alternative would be less than significant. 

2.4.3  ENVIRONMENTALLY SUPERIOR ALTERNATIVE 

An EIR is required to identify the environmentally superior alternative—that is, the alternative 

having the fewest significant environmental impacts—from among the alternatives evaluated.  

The environmentally superior alternative among those evaluated within this SEIR is the No 

Project Alternative. Other than the No Project Alternative, the remaining alternative, the 

Reduced Project Alternative, is the environmentally superior alternative.  

2.5  AREAS OF CONTROVERSY 

No concerns have been expressed regarding the proposed garage, and there are no known areas 

of controversy about this project. 

Page 19: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 15 of 74 

CHAPTER 3 PROJECT DESCRIPTION 

3.1  BACKGROUND 

On September 17, 2008, The Regents certified the EIR for the UCSF Medical Center at Mission 

Bay (MCMB) (State Clearinghouse No. 2008012075) and approved components of Phase I 

consisting of the 289‐bed hospital, energy center, outpatient building, medical helipad, and 

surface parking.7  Approval of the cancer outpatient building and Phase I garage was deferred 

pending funding and design of those facilities.  Construction of the approved components of the 

Medical Center project has now commenced, beginning with site development and construction 

of the hospital and outpatient building.  The complex is scheduled to open in 2014.  With 

approved funding of the Phase I garage, the University is now prepared to seek approval of its 

design and construction.   

3.2  PROJECT DESCRIPTION 

The location of the UCSF Medical Center at Mission Bay is as described in the UCSF Medical Center 

at Mission Bay EIR.  The 14.5‐acre site is located in the eastern portion of the City of San Francisco, 

approximately one and one half miles south of downtown, and increases the UCSF Mission Bay 

campus from 43 acres to 57 acres (see Figure 3‐1).8  The site lies within the 303‐acre Mission Bay 

Redevelopment Plan Area, under the jurisdiction of the San Francisco Redevelopment Agency, and 

consists of Mission Bay South Plan Parcels 36, 37, 38, 39, and X3.  

7   The UCSF Medical Center at Mission Bay EIR is available online at 

http://campusplanning.ucsf.edu/physical/RFEIRHospital.php. 8 The 14.5‐acre Medical Center project site was added to the 43‐acre UCSF Mission Bay campus site (a total 

of 57 acres) in September 2008. 

Page 20: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 16 of 74 

 

Source:  Environmental Science Associates, April 2008  Figure 3‐1

Location of UCSF Medical Center at 

Mission Bay

Page 21: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 17 of 74 

 

Source:  UCSF, April 2008 Figure 3‐2

Project Site

Proposed Project

Page 22: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 18 of 74 

Source:  WRNS Studio                              Figure 3‐3 

  Project Site Plan

Page 23: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 19 of 74 

Source:  WRNS Studio Figure 3‐4 

  Project Site Plan/First Floor Plan

Page 24: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 20 of 74 

 

 

Source: Rudolph and Sletten and WRNS Studios LLP                       Figure 3‐5 

  Approach from Owens Street

Page 25: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 21 of 74 

 

The Medical Center project site is bordered by 16th Street to the north, 3rd Street to the east, and 

Mariposa Street to the south.  In the future, a new segment of Owens Street will define the western 

boundary of the project site (see Figure 3‐2). 

Structures that have not yet been approved under Phase I include the garage and the cancer 

outpatient building.  Minor changes to the garage in Phase I are proposed. The parking structure 

analyzed in the MCMB EIR consisted of a 600‐space garage of approximately 90 feet in height, 

located along the western edge of the site on Owens Street between the South Connector Road 

and the Center Garage Access (now Parking Structure Road).  The medical center program 

envisioned in Phase II the expansion of the garage to the north between the Center Garage Access 

and the North Connector Road.  The garage is now proposed to be approximately 626 spaces and 

an additional story at about 105 feet in height.  In addition, the Phase I garage is now proposed to 

the north, between the North Connector Road and Parking Structure Road, the original location 

of the proposed Phase II garage (see Figure 3‐3).  Phase II of the garage would expand the 

structure to the south from Parking Structure Road to South Connector Road. 

The number of surface parking spaces proposed on the remainder of Blocks 38 and 39 in Phase I 

(see  Figure  3‐3)  has  been  reduced  from  475  spaces  to  approximately  429  spaces,  with  an 

additional 13 spaces east of the future extension of 4th Street,  in what  is known as the east  lot. 

The  total  surface  parking  spaces  would  be  approximately  442  compared  to  the  475  spaces 

analyzed in the 2008 EIR. Therefore, the total number of parking spaces provided in Phase I (626 

spaces  in  the  parking  structure  and  442  surface  parking  spaces)  would  decrease  by 

approximately  seven  spaces  and would  total  approximately  1,068‐parking  spaces  from  1,075 

spaces (see Figure 3‐4).  

3.3  PROJECT OBJECTIVES 

3.3.1  OBJECTIVES IN THE UCSF MEDICAL CENTER AT MISSION BAY 

EIR 

The Project Objectives described in the UCSF MCMB EIR remain unchanged.  As a support 

function to the hospital complex, all project objectives are applicable to the proposed garage, and 

in particular the following Project Objectives to:  

Ensure that development is compatible with and responsive to building scale and 

character in the surrounding areas 

Develop a patient‐friendly hospital (convenient location, availability of parking, efficient 

patient/emergency access, proximity of related patient service, etc.) 

Develop a staff‐friendly hospital (availability of parking, proximity to amenities, 

loading/delivery access, etc.) 

Page 26: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 22 of 74 

 

In addition, this SEIR identifies the following Project Objectives for the proposed garage: 

To support UCSF’s mission of patient care by enhancing access to UCSF facilities 

through convenient, affordable parking for those who often cannot utilize alternative 

forms of transportation 

To provide parking for those essential healthcare providers for whom alternative forms 

of transportation is infeasible due to atypical work hours and responsibilities at multiple 

campus sites 

To provide a parking structure that incorporates sustainability features to the greatest 

extent feasible 

To avoid pressure on neighborhood on‐street parking 

3.4  MITIGATION MONITORING 

CEQA requires that when a public agency makes findings of significance based on an EIR, the 

public agency must adopt a reporting or monitoring program to ensure that action is completed 

on those mitigation measures which it has adopted, or made a condition of project approval, in 

order to mitigate or avoid the project’s significant effects on the environment (Public Resources 

Code Section 21081.6).  A mitigation monitoring program for the Medical Center project was 

adopted in September 2008 upon certification of the UCSF MCMB EIR and approval of the 

Medical Center project.  Upon certification of this SEIR and approval of the Phase I garage, the 

revised mitigation monitoring program, updated to include mitigation measures identified in 

this SEIR, would be adopted. 

3.5  REQUIRED APPROVALS 

The University of California is the CEQA lead agency in the review of the project.   The Regents 

of the University of California, or their delegated committee or administrative official, will 

consider certification of this SEIR and approval of the Phase I garage.   

_________________________

Page 27: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 23 of 74 

CHAPTER 4 ENVIRONMENTAL SETTING, IMPACTS, AND MITIGATION 

MEASURES 

4.0  SCOPE OF ANALYSES  

This SEIR updates the UCSF MCMB EIR by analyzing proposed minor changes to the Phase I 

garage project.  There are no changes proposed to the cancer outpatient building, the other 

remaining building in Phase I that has not yet been approved.  In addition, this SEIR updates the 

greenhouse gas (GHG) emissions analysis in light of new GHG significance criteria recently 

adopted by the Bay Area Air Quality Management District (BAAQMD).  As such, this SEIR 

focuses on two topics that are affected by the modified project:  greenhouse gas emissions and 

transportation.  All other environmental topics were adequately analyzed and require no further 

analysis, as determined in the Initial Study for this project (see Appendix A).  

Page 28: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 24 of 74 

 

4.1 GREENHOUSE GAS EMISSIONS  

4.1.1 INTRODUCTION  

This section discusses the existing global, national, and statewide conditions for greenhouse 

gases (GHG) and global climate change and evaluates the potential impacts on global climate 

from the implementation of the proposed Medical Center at Mission Bay Garage project 

(proposed project). The section also provides discussion of the applicable federal, state, regional, 

and local agencies that regulate, monitor, and control GHG emissions. The impacts associated 

with the proposed project are compared with the thresholds of significance adopted by the Bay 

Area Air Quality Management District (BAAQMD). Copies of the modeling runs to estimate 

GHG emissions associated with the proposed project and supporting technical data are found in 

Appendix B.  

The 2008 MCMB FEIR, certified by The Regents September 17, 20089, included an analysis of 

greenhouse gas emissions.  This analysis was done for the entire Medical Center at Mission Bay 

project envelope including of the proposed Medical Center at Mission Bay Garage project.10  The 

analysis was done using the URBEMIS2007 Version 9.2.4 software.  Subsequent to the 

certification of that EIR, additional guidance for the analysis of greenhouse gases has been 

adopted.   

The Natural Resources Agency adopted GHG CEQA Guideline Amendments on December 30, 

2009. They became effective in March 2010.  

The BAAQMD adopted updated CEQA Air Quality Guidelines on June 2, 2010.  These guidelines 

contain greenhouse gas operational emissions significance thresholds and recommended 

methodologies and models to be used for assessing the impacts of project‐specific GHG 

emissions on global climate change.  The updated CEQA Air Quality Guidelines contain project‐

level screening criteria and recommended significance thresholds for evaluation of operational 

GHG emissions from a proposed project. The guidelines also contain recommended 

methodologies to use to estimate these emissions and provide recommended measures for 

reducing GHG emissions from land use development projects and stationary sources.  The 

recommended methodology is the URBEMIS2007 Version 9.2.4 software with an additional Bay 

Area specific spreadsheet module that takes into account Assembly Bill 1493 limitations on motor 

vehicles. 

 

9 State Clearinghouse No. 2008012075 10 http://campusplanning.ucsf.edu/pdf/RFEIR/UCSFMissionBayMedCtrRFEIRAppendices.pdf Table GHG-1

Page 29: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 25 of 74 

 

4.1.2 ENVIRONMENTAL SETTING  

Background  

Global climate change refers to any significant change in climate measurements, such as 

temperature, precipitation, or wind, lasting for an extended period (i.e., decades or longer) (U.S. 

EPA 2008b). Climate change may result from:  

Natural factors, such as changes in the sun’s intensity or slow changes in the Earth’s 

orbit around the sun (Milankovitch cycles);  

Natural processes within the climate system (e.g., changes in ocean circulation, 

changes in planetary albedo from the addition of gases to the atmosphere from 

volcanic eruptions); and  

Human activities that change the atmosphere’s composition (e.g., through burning 

fossil fuels) and the land surface (e.g., deforestation, reforestation, urbanization, 

desertification).  

The natural process through which heat is retained in the troposphere11 is called the “greenhouse 

effect.” The greenhouse effect traps heat in the troposphere through a threefold process as 

follows: (1) short‐wave radiation in the form of visible light emitted by the Sun is absorbed by the 

Earth as heat; (2) long‐wave radiation is re‐emitted by the Earth; and (3) certain gases termed 

greenhouse gases in the upper atmosphere absorb a portion of the long‐wave radiation that 

would otherwise have been emitted into space, warming the earth’s surface. This third process is 

the focus of current climate change actions.  

While water vapor and carbon dioxide (CO2) are the most abundant GHGs, other GHGs found in 

trace amounts have a greater ability to absorb and re‐radiate long‐wave radiation. To gauge the 

potency of GHGs, scientists have established a Global Warming Potential (GWP) for each GHG 

based on its ability to absorb and re‐emit long‐wave radiation over a specific period. The GWP of 

a gas is determined using CO2 as the reference gas, which has a GWP of 1 over 100 years (IPCC 

1996). For example, a gas with a GWP of 10 is 10 times more potent than CO2 over 100 years. The 

use of GWP allows GHG emissions to be reported using CO2 as a baseline. The sum of each GHG 

multiplied by its associated GWP is referred to as “carbon dioxide equivalents” (CO2e). This 

essentially means that 1 metric ton of a GHG with a GWP of 10 has the same climate change 

impacts as 10 metric tons of CO2. The IPCC makes minor adjustments to the GWP values of the 

various GHG’s as the scientific understanding of climate change advances. 

Greenhouse Gases  

11 The troposphere is the bottom layer of the atmosphere, which varies in height from the Earth’s surface to 

10 to 12 kilometers).  

Page 30: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 26 of 74 

 

State law defines GHGs to include the following six compounds:  

Carbon Dioxide (CO2). Carbon dioxide primarily is generated by fossil fuel 

combustion from stationary and mobile sources.  Due to the emergence of industrial 

facilities and mobile sources over the past 250 years, the concentration of carbon dioxide 

in the atmosphere has increased 35 percent.  (U.S. EPA 2008c). Carbon dioxide is the 

most widely emitted GHG and is the reference gas (GWP of 1) for determining the GWP 

of other GHGs. In 2004, 82.8 percent of California’s GHG emissions were carbon dioxide 

(CEC 2007).  

Methane (CH4). Methane is emitted from biogenic sources (i.e., resulting from the 

activity of living organisms), incomplete combustion in forest fires, landfills, manure 

management, and leaks in natural gas pipelines. In the United States, the top three 

sources of methane are landfills, natural gas systems, and enteric fermentation (U.S. 

EPA).  Methane is the primary component of natural gas, which is used for space and 

water heating, steam production, and power generation. The GWP of methane is 21.  

Nitrous Oxide (N2O). Nitrous oxide is produced by natural and human‐related sources.  

Primary human‐related sources include agricultural soil management, animal manure 

management, sewage treatment, mobile and stationary combustion of fossil fuel, adipic 

acid production, and nitric acid production. The GWP of nitrous oxide is 310.  

Hydrofluorocarbons (HFCs). HFCs typically are used as refrigerants in both stationary 

refrigeration and mobile air conditioning. The use of HFCs for cooling and foam‐blowing 

is growing particularly as the continued phase‐out of chlorofluorocarbons (CFCs) and 

hydrochlorofluorocarbons (HCFCs) gains momentum. The GWP of HFCs ranges from 

140 for HFC‐152a to 6,300 for HFC‐236fa.  

Perfluorocarbons (PFCs). Perfluorocarbons are compounds consisting of carbon and 

fluorine. They are primarily created as a byproduct of aluminum production and 

semiconductor manufacturing. Perfluorocarbons are potent GHGs with a GWP several 

thousand times that of carbon dioxide, depending on the specific PFC. Another area of 

concern regarding PFCs is their long atmospheric lifetime (up to 50,000 years) (EIA n.d.). 

The GWPs of PFCs range from 5,700 to 11,900.  

Sulfur Hexafluoride (SF6). Sulfur hexafluoride is a colorless, odorless, nontoxic, 

nonflammable gas. It is mainly used in such purposes as magnesium casting operations, 

semiconductor manufacture, and as an electrical insulator in high voltage equipment 

that transmits and distributes electricity. Minor uses include certain medical and 

laboratory uses.  Sulfur hexafluoride is the most potent GHG that has been evaluated by 

the Intergovernmental Panel (IPCC) on Climate Change with a GWP of 23,900. However, 

its global warming contribution is not as high as the GWP would indicate due to its low 

mixing ratio, as compared to carbon dioxide (4 parts per trillion [ppt] in 1990 versus 365 

parts per million [ppm] of CO2) (U.S. EPA).  

 

The primary GHGs of concern relative to the proposed project are CO2, CH4, and N2O. These 

Page 31: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 27 of 74 

 

three GHGs are generally emitted from combustion activities. The other GHGs listed above are 

related to specific industrial uses and not anticipated to be emitted in measurable or substantial 

quantities by the project.  

 

Contributions to Greenhouse Gas Emissions  

Global  

The World Meteorological Organization (WMO) and United Nations Environmental Program 

(UNEP) established the Intergovernmental Panel on Climate Change (IPCC) in 1988. The goal of 

the IPCC is to evaluate the risk of climate change caused by human activities. The IPCC assesses 

information (i.e., scientific literature) regarding human‐induced climate change, impacts of 

human‐induced climate change, and options for adaptation and mitigation of climate change. 

The IPCC reports its evaluations in special reports called “assessment reports,” the latest of 

which, AR4, was published in 2007.12   

Worldwide anthropogenic (man‐made) GHG emissions are tracked for industrialized nations 

and developing nations. The IPCC estimates worldwide emissions in 1990 were 39,400 million 

metric tons of CO2 equivalent (MMTCO2e).13   The most recent anthropogenic GHG emissions 

from industrialized and developing nations are available through 2007 and 2005, respectively. 

The IPCC estimates sum of these emissions totaled approximately 43,363 MMTCO2e.  This 

translates into approximately 6.8 MTCO2e per capita.  The IPCC projects a significant rise in 

worldwide GHG emissions as world population continues to grow and underdeveloped 

countries industrialize to raise living standards. 

It should be noted that global emissions inventory data are not all from the same year and may 

vary considerably depending on the quality and source of the emissions inventory data. While 

the majority of global CO2 emissions are from the burning of fossil fuels, roughly a quarter of the 

carbon entering the atmosphere is from land‐use changes, which are harder to track.  The IPCC is 

currently working to produce their Fifth Assessment Report with updated emissions estimates 

and analysis. Table 4.1‐1 shows the most recently available comparative GHG emissions for 

various relevant reporting entities. 

United States  

The most recent United States Greenhouse Gas Inventory Report of national GHG emissions was 

prepared by the EPA in 2010.  This inventory covers the period from 1990 to 2008.  The EPA 

estimates that the United States emitted 6,127 MMTCO2e in 1990.   In 2008, total U.S. greenhouse 

12 The IPCC’s Fourth Assessment Report is available online at http://www.ipcc.ch/. 13 The CO2 equivalent emissions commonly are expressed as “million metric tons of carbon dioxide equivalent

(MMTCO2E).” The carbon dioxide equivalent for a gas is derived by multiplying the tons of the gas by the associated GWP, such that MMTCO2E = (million metric tons of a GHG) x (GWP of the GHG). For example, the GWP for methane is 21. This means that the emission of one million metric tons of methane is equivalent to the emission of 21 million metric tons of CO2.

Page 32: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 28 of 74 

 

gas emissions were 6,956 MMTCO2e, or approximately 20 MTCO2e per capita.  Overall, total 

U.S. emissions of GHG’s have risen by approximately 14 percent from 1990 to 2008.  Emissions 

declined from 2007 to 2008, decreasing by 2.9 percent.  This decrease is primarily a result of a 

decrease in demand for transportation fuels associated with the high costs of these fuels that 

occurred in 2008.  Additionally, electricity demand declined in 2008 in part due to a significant 

increase in the cost of fuels used to generate electricity.  Preliminary numbers for 2009 show 

national emissions decreasing by an additional 3.4 percent. 

The primary greenhouse gas emitted by human activities in the United States is CO2, 

representing approximately 85.1 percent of total greenhouse gas emissions.  The largest source of 

CO2, and of overall greenhouse gas emissions, is fossil fuel combustion, primarily for 

transportation and electricity generation.   

Table 4.1‐1   Comparative GHG Emissions 

  GHG Emissions 

(MMTCO2e) 

~ Per Capita 

(MTCO2e) 

World  43,363  6.8 

United States  6,956  20 

California  474  14 

Bay Area Region  97.4  15 

San Francisco  8.5  11 

 

State of California  

The California Air Resources Board (CARB) compiles GHG inventories for the State of California.  

Based upon the 2008 GHG inventory data, the latest year for which data are available, California 

emitted 427 MMTCO2e in 1990 and 474 MMTCO2e in 2008. 14  This translates into approximately 

14 MTCO2e per capita in 2008.   

Between 1990 and 2008, the population of California grew by approximately 8.1 million (from 

29.8 to 37.9 million), or 27.2 percent.15  In addition, the California economy, measured as gross 

state product, grew from $788 billion in 1990 to $1.8 trillion in 2008 representing an increase of 

approximately 128 percent.16  Despite the population and economic growth, California’s net GHG 

emissions grew by only 11 percent.  The California Energy Commission attributes the 

proportionally slower rate of growth in greenhouse gas emissions in part to the success of 

California’s energy efficiency and renewable energy programs. 

14 Including emissions resulting from imported electrical power in 2008 15 California Department of Finance 2010a, U.S. Census Bureau 2010 16 California Department of Finance 2010

Page 33: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 29 of 74 

 

Table 4.1‐2, GHG Emissions in California, provides a summary of GHG emissions reported in 

California in 1990 and 2008 separated by categories defined by the United Nations 

Intergovernmental Panel on Climate Change (IPCC).

Page 34: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 30 of 74 

 

Table 4.1‐2   GHG Emission Detail in California 

Source Category  

1990 

(MMTCO2e) 

Percent 

of Total 

2008 

(MMTCO2e) 

Percent  

of Total 

ENERGY   386.41   89.2%  413.80  86.6%  

Energy Industries   157.33   36.3%  171.23  35.8%  

Manufacturing Industries & Construction   24.24   5.6%  16.67  3.5%  

Transport   150.02   34.6%  173.94  36.4%  

Other (Resident/Commercial/Institutional)   48.19   11.1%  46.59  9.8%  

Non‐Specified   1.38   0.3%  0.00  0.0%  

Fugitive Emissions ‐ Oil & Natural Gas   2.94   0.7%  3.28  0.7%  

Fugitive Emissions Other Energy Prod.  2.31   0.5%  2.09  0.4%  

INDUSTRIAL PROCESS & PRODUCT USE   18.34   4.2%  30.11  6.3%  

Mineral Industry   4.85   1.1%  5.35  1.1%  

Chemical Industry   2.34   0.5%  0.06  0.0%  

Non‐Energy Products Fuels & Solvent Use   2.29   0.5%  1.97  0.4%  

Electronics Industry   0.59   0.1%  0.80  0.2%  

Substitutes ‐ Ozone Depleting Substances   0.04   0.0%  13.89  2.9%  

Other Product Manufacture and Use   3.18   0.7%  1.66  0.3%  

Other   5.05   1.2%  6.39  1.3%  

AGRI., FORESTRY, & OTHER LAND USE   19.11   4.4%  24.42  5.1%  

Livestock   11.67   2.7%  16.28  3.4%  

Land   0.19   0.0%  0.19  0.0%  

Aggr. Sources & Non‐CO2 Sources on Land   7.26   1.7%  7.95  1.7%  

WASTE 

Solid Waste Disposal  

Wastewater Treatment & Discharge  

9.42  

6.26  

3.17  

2.2% 

1.4% 

0.7% 

9.41 

6.71 

2.70 

2.0% 

1.4% 

0.6%  

EMISSIONS SUMMARY         

Gross California Emissions 

Sinks from Forests and Rangelands 

Net California Emissions 

433.29 

‐6.69 

426.60 

  477.74 

‐3.98 

473.76 

 

Source:  

California Air Resources Board. “California Greenhouse Gas 1990‐2004 Inventory by IPCC Category – Summary.”  

http://www.arb.ca.gov/cc/inventory/data/data.htm  2007 

California Air Resources Board. “California Greenhouse Gas 2000‐2008 Inventory by IPCC Category – Summary.”  

http://www.arb.ca.gov/cc/inventory/data/data.htm 2010

Page 35: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 31 of 74 

 

Regional  The Bay Area Air Quality Management (BAAQMD) has compiled several GHG inventories for 

the nine county Bay Area region, the most recent of which was updated in February 2010.17  

Based upon that GHG inventory, the entire region emitted 87.7 MMTCO2e in 1990, and, 97.4 

MMTCO2e, or 11% more, in 2008.18  This translates into approximately 15 MTCO2e per capita.   

Carbon Dioxide accounts for 91.6% of Bay Area emissions.  Carbon dioxide emissions are mainly 

associated with combustion of carbon‐bearing fossil fuels such as gasoline, diesel, and natural 

gas used in mobile sources and energy‐generation‐related activities such as commercial power 

plants. 

 

San Francisco  

The San Francisco Department of the Environment tracks the City’s greenhouse gas emissions.19  

In 2002 the San Francisco Board of Supervisors adopted a resolution that called for the City to 

develop plans to reduce its greenhouse gas emissions to 20% below 1990 levels by the year 2012.  

In 2004 the Department of the Environment and the PUC, issued “The Climate Action Plan for 

San Francisco” which included an accounting of greenhouse gas activities.  In 1990, San 

Francisco’s total greenhouse gas emissions were approximately 9.1 MMTCO2e. 20  San Franciscoʹs 

Climate Action Plan found that 49% of the Cityʹs greenhouse gas emissions came from buildings, 

and 51% from transportation.   

In 2008 the City estimated that its greenhouse gas emissions had decreased to 8.5 MMTCO2e, 

about 7 percent below the 1990 emissions levels.  In May 2008 the Board of Supervisors updated 

the City goals: that by 2017, reduce greenhouse gas emissions by 25% below 1990 levels; by 2025, 

reduce greenhouse gas emissions by 40% below 1990 levels; by 2050, reduce greenhouse gas 

emissions by 80% below 1990 levels. 

Effects of Global Climate Change  

The primary effect of global climate change has been a rise in the average global tropospheric 

temperature of 0.2° Celsius per decade, determined from meteorological measurements 

worldwide between 1990 and 2005 (IPCC 2007). Climate change modeling using 2000 emission 

rates suggests that further warming is likely to occur, which would induce further changes in the 

global climate system during the current century (IPCC 2007). Changes to the global climate 

system and ecosystems, and to the proposed project site, could include:  

Changing weather patterns, including changes to precipitation, ocean salinity, and wind 

patterns, and more energetic aspects of extreme weather including droughts, heavy 

17http://www.baaqmd.gov/~/media/Files/Planning%20and%20Research/Emission%20Inventory/regionalinventory200

7_2_10.ashx 18 http://hank.baaqmd.gov/pln/documents/regionalinventory2007_003_000_000.pdf 19 http://www.livablecity.org/campaigns/documents/SF%20climate%20ordinance%202008.pdf 20 http://www.sfenvironment.org/downloads/library/climateactionplan.pdf

Page 36: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 32 of 74 

 

precipitation, heat waves, extreme cold, and the intensity of tropical cyclones (IPCC 

2007);  

Declining sea ice, thereby increasing sea levels and sea surface evaporation rates with a 

corresponding increase in tropospheric water vapor due to the atmosphere’s ability to 

hold more water vapor at higher temperatures (IPCC 2007);  

Summer warming projections in the first 30 years of the 21st century ranging from about 

0.5 to 2 degrees Celsius (°C) (0.9 to 3.6 °F) and by the last 30 years of the 21st century, 

from about 1.5 to 5.8 °C (2.7 to 10.5 °F) (CalEPA 2006).  

4.1.3 REGULATORY CONSIDERATIONS  

Federal  

In Massachusetts vs. EPA, the Supreme Court held that United States Environmental Protection 

Agency (U.S. EPA) has the statutory authority under Section 202 of the Clean Air Act (CAA) to 

regulate GHGs from new motor vehicles. The court did not hold that the U.S. EPA was required 

to regulate GHG emissions; however, it indicated that the agency must decide whether GHGs 

from motor vehicles cause or contribute to air pollution that is reasonably anticipated to 

endanger public health or welfare. Upon the final decision, the President signed Executive Order 

13432 on May 14, 2007, directing the U.S. EPA, along with the Departments of Transportation, 

Energy, and Agriculture, to initiate a regulatory process that responds to the Supreme Court’s 

decision.  

On July 11, 2008, the U.S. EPA issued an Advanced Notice of Proposed Rulemaking (ANPRM) 

on regulating GHGs under the CAA. The ANPRM reviews the various CAA provisions that may 

be applicable to the regulation of GHGs and presents potential regulatory approaches and 

technologies for reducing GHG emissions. On April 10, 2009, the U.S. EPA published the 

Proposed Mandatory Greenhouse Gas Reporting Rule in the Federal Register (U.S. EPA 2009). The 

rule was adopted on September 22, 2009 and covers approximately 10,000 facilities nationwide, 

accounting for 85 percent of U.S. GHG emissions.  

On September 15, 2009, the U.S. EPA and the Department of Transportation’s (DOT) National 

Highway Traffic Safety Administration (NHTSA) issued a joint proposal to establish a national 

program consisting of new standards for model year 2012 through 2016 light‐duty vehicles that 

will reduce GHG emissions and improve fuel economy. The proposed standards would be 

phased in and would require passenger cars and light‐duty trucks to comply with a declining 

emissions standard. In 2012, passenger cars and light‐duty trucks would have to meet an average 

standard of 295 grams of CO2 per mile and 30.1 miles per gallon. By 2016, the vehicles would 

have to meet an average standard of 250 grams of CO2 per mile and 35.5 miles per gallon.21  

These standards were formally adopted by the U.S. EPA and DOT on April 1, 2010.  

21 The CO2 emission standards and fuel economy standards stated are based on U.S. EPA formulas

Page 37: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 33 of 74 

 

On December 7, 2009, the U.S. EPA Administrator signed two distinct findings regarding GHGs 

under section 202(a) of the Clean Air Act:  

Endangerment Finding: The Administrator finds that the current and projected 

concentrations of the six key well‐mixed GHGs (carbon dioxide, methane, nitrous oxide, 

hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride) in the atmosphere 

threaten the public health and welfare of current and future generations.  

Cause or Contribute Finding: The Administrator finds that the combined emissions of 

these well‐mixed greenhouse gases from new motor vehicles and new motor vehicle 

engines contribute to the greenhouse gas pollution, which threatens public health and 

welfare.  

While these findings do not impose additional requirements on industry or other entities, this 

action was a prerequisite to finalizing the U.S. EPA’s proposed GHG emissions standards for 

light‐duty vehicles, which were jointly proposed by the U.S. EPA and DOT.  

California 

Key state laws and regulations related to GHG emissions are described below.  

Executive Order S‐3‐05 and the Climate Action Team  

In June 2005, Governor Schwarzenegger established California’s GHG emissions reduction 

targets in Executive Order S‐3‐05. The Executive Order established the following goals: GHG 

emissions should be reduced to 2000 levels by 2010, 1990 levels by 2020, and 80 percent below 

1990 levels by 2050. The Secretary of Cal EPA is required to coordinate efforts of various agencies 

in order to collectively and efficiently reduce GHGs. Some of the agency representatives involved 

in the GHG reduction plan include the Secretary of the Business, Transportation and Housing 

Agency, the Secretary of the Department of Food and Agriculture, the Secretary of the Resources 

Agency, the Chairperson of CARB, the Chairperson of the CEC, and the President of the Public 

Utilities Commission.  

Representatives from each of the aforementioned agencies comprise the Climate Action Team. 

The Cal/EPA secretary is required to submit a biannual progress report from the Climate Action 

Team to the governor and state legislature disclosing the progress made toward GHG emission 

reduction targets. In addition, another biannual report must be submitted illustrating the impacts 

of global warming on California’s water supply, public health, agriculture, coastline, and forests, 

and reporting possible mitigation and adaptation plans to combat these impacts. Strategies 

currently being implemented by state agencies include CARB introducing vehicle climate change 

standards and diesel anti‐idling measures, the Energy Commission implementing building and 

appliance efficiency standards, and the Cal/EPA implementing their green building initiative. 

The Climate Action Team also recommends future emission reduction strategies, such as using 

only low‐GWP refrigerants in new vehicles, developing ethanol as an alternative fuel, 

Page 38: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 34 of 74 

 

reforestation, solar power initiatives for homes and businesses, and investor‐owned utility 

energy efficiency programs. According to the report, implementation of current and future 

emission reduction strategies have the potential to achieve the goals set forth in Executive Order 

S‐3‐05. 

Assembly Bill 32  

In furtherance of the goals established in Executive Order S‐3‐05, the legislature enacted 

Assembly Bill 32, the California Global Warming Solutions Act of 2006, which Governor 

Schwarzenegger signed on September 27, 2006.  AB 32 represents the first enforceable statewide 

program to limit GHG emissions from all major industries with penalties for noncompliance.  AB 

32 requires the State to undertake several actions – the major requirements are discussed  

State of California Greenhouse Gas Inventory and 2020 Limit  

As required under AB 32, on December 6, 2007, CARB approved the 1990 greenhouse gas 

emissions inventory, thereby establishing the emissions limit for 2020. The 2020 emissions limit 

was set at 427 MMTCO2e. CARB also projected the state’s 2020 GHG emissions under “business 

as usual” (BAU) conditions—that is, emissions that would occur without any plans, policies, or 

regulations to reduce GHG emissions. CARB used an average of the State’s GHG emissions from 

2002 through 2004 and projected the 2020 levels based on population and economic forecasts. 

The projected net emissions totaled approximately 596 MMTCO2e. Therefore, the state must 

reduce its 2020 BAU emissions by approximately 29 percent in order to meet the 1990 target.  

The inventory revealed that for transportation, the sector with the greatest amount of emissions,  

in 1990 totaled about 150 million metric tons of CO2e (about 35 percent of the stateʹs total 

emissions) (see Table 4.1‐2).  By 2008, transportation‐related emissions rose to about 174 million 

metric tons (about 36 percent of the state’s total emissions).  AB 32 does not require individual 

sectors to meet their individual 1990 GHG emissions inventory; the total statewide emissions are 

required to meet the 1990 threshold by 2020.  

CARB Mandatory Reporting Requirements  

In addition to the 1990 emissions inventory, CARB also adopted regulations requiring the 

mandatory reporting of GHG emissions for large facilities on December 6, 2007. The mandatory 

reporting regulations require annual reporting from the largest facilities in the state, which 

account for approximately 94 percent of point source greenhouse gas emissions from industrial 

and commercial stationary sources in California.  About 800 separate sources fall under the new 

reporting rules and include electricity‐generating facilities, electricity retail providers and power 

marketers, oil refineries, hydrogen plants, cement plants, cogeneration facilities, and industrial 

sources that emit over 25,000 tons of carbon dioxide each year from on‐site stationary 

combustion sources. Transportation sources, which account for 38 percent of California’s total 

greenhouse gas emissions, are not covered by these regulations but will continue to be tracked 

through existing means. Affected facilities will begin tracking their emissions in 2008, to be 

Page 39: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 35 of 74 

 

reported beginning in 2009, with a phase‐in process to allow facilities to develop reporting 

systems and train personnel in data collection. Emissions for 2008 may be based on best available 

emission data. Beginning in 2010, however, emissions reporting requirements will be more 

rigorous and will be subject to third‐party verification. Verification will take place annually or 

every three years, depending on the type of facility.  UCSF’s campus power plant falls under the 

CARB mandatory reporting regulations, and has had its emission levels certified by third‐party 

verification. 

AB 32 Climate Change Scoping Plan  

As indicated above, AB 32 requires CARB to adopt a scoping plan indicating how reductions in 

significant GHG sources will be achieved through regulations, market mechanisms, and other 

actions. After receiving public input on their discussion draft of the Climate Change Proposed 

Scoping Plan released in June 2008, CARB released the Climate Change Proposed Scoping Plan in 

October 2008 that contains an outline of the proposed state strategies to achieve the 2020 

greenhouse gas emission limits. The CARB Governing Board approved the Climate Change 

Scoping Plan on December 11, 2008. Key elements of the Scoping Plan include the following 

recommendations:  

Expanding and strengthening existing energy efficiency programs as well as building 

and appliance standards;  

Achieving a statewide renewable energy mix of 33 percent;  

Developing a California cap‐and‐trade program that links with other Western Climate 

Initiative partner programs to create a regional market system;  

Creating targeted fees, including a public goods charge on water use, fees on high global 

warming potential gases, and a fee to fund the administrative costs of the state’s long‐

term commitment to AB 32 implementation.  

Establishing targets for transportation‐related greenhouse gas emissions for regions 

throughout California and pursuing policies and incentives to achieve those targets; and  Adopting and implementing measures pursuant to existing state laws and policies, 

including California’s clean car standards, goods movement measures, and the Low 

Carbon Fuel Standard.  

Under the Scoping Plan, approximately 85 percent of the state’s stationary emissions are subject 

to a cap‐and‐trade program where covered sectors are placed under a declining emissions cap. 

The emissions cap incorporates a margin of safety whereas the 2020 emissions limit will still be 

achieved even in the event that uncapped sectors do not fully meet their anticipated emission 

reductions.  Emissions reductions will be achieved through regulatory requirements and the 

option to reduce emissions further or purchase allowances to cover compliance obligations. It is 

expected that emission reduction from this cap‐and‐trade program will account for a large 

portion of the reductions required by AB 32.   

 

Page 40: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 36 of 74 

 

On December 16th, 2010 CARB adopted cap‐and‐trade regulations designed to cut greenhouse 

gases in the State 15 percent by 2020.22  These regulations were scheduled to go into effect Jan. 1, 

2012.   

 

On January 21, 2011 in Association of Irritated Residents, et al. v. California Air Resources Board, the 

San Francisco Superior Court partially granted a peremptory writ of mandate to petitioners, e.g. 

environmental justice groups, which had alleged CARB failed to comply with the California 

Environmental Quality Act (CEQA) (Case No. CPF‐09‐509562). 23  Specifically, the petitioners 

alleged that CARB failed to adequately analyze all potential alternatives and prematurely 

adopted the Plan prior to fully responding to public comment.  Under this tentative ruling, 

CARB is ordered to delay implementation of the cap and trade program until CARB is in 

ʺcomplete compliance with its obligations under its certified regulatory program and CEQA.ʺ   

 

The cap‐and‐trade regulations are written to primarily affect stationary sources such as electricity 

generation.  Mobile source GHG emission reductions such as from automobiles are regulated by 

other CARB programs. 

 

Assembly Bill 1493 (Vehicular Emissions) 

 

The Clean Air Act (CAA) gives California special authority to enact stricter air pollution 

standards for motor vehicles than the federal government’s.  The U.S. EPA must approve a 

waiver, however, before California’s rules may go into effect.  The California Air Resources 

Board requested a waiver to the CAA in December 2005.   On June 30, 2009, U.S. EPA granted of 

Clean Air Act preemption to California for its greenhouse gas emission standards for motor 

vehicles beginning with the 2009 model year24.  On September 24, 2009, the ARB adopted 

amendments to the Assembly Bill 1493 (Pavley) (2002) regulations that reduce greenhouse gas 

(GHG) emissions in new passenger vehicles from 2009 through 2016.  It is expected that the 

Pavley regulations will reduce GHG emissions from California passenger vehicles by about 22 

percent in 2012 and about 30 percent in 2016.  These reductions, along with others approved 

actions such as the low carbon fuel standard, are projected to reduce California transportation 

associated emissions 35%, or by 67.8 MMTCO2e, by 2020. 

Senate Bill 97 (CEQA Guidelines)  

In August 2007, the legislature enacted SB 97 (Dutton), which directed the Governor’s Office of 

Planning and Research (OPR) to develop guidelines under CEQA for the mitigation of 

greenhouse gas emissions. A number of actions have taken place under SB 97, which are 

discussed below.  

22 http://www.arb.ca.gov/board/ma/2010/ma121610.htm  23 http://cdn.law.ucla.edu/SiteCollectionDocuments/Environmental%20Law/AIR%20v%20ARB%20Tentative%20Ruli

ng.pdf  24 http://www.epa.gov/otaq/climate/ca-waiver.htm

Page 41: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 37 of 74 

 

OPR Climate Change Technical Advisory  

On June 19, 2008, OPR issued a technical advisory as interim guidance regarding the analysis of 

GHG emissions in CEQA documents (OPR 2008). The advisory indicated that a project’s GHG 

emissions, including those associated with vehicular traffic and construction activities should be 

identified and estimated. The advisory further recommended that the lead agency determine 

significance of the impacts and impose all mitigation measures that are necessary to reduce GHG 

emissions to a less than significant level. The advisory did not recommend a specific threshold of 

significance. Instead, OPR requested that CARB recommend a method for setting thresholds that 

lead agencies may adopt (OPR 2009).  

CEQA Guideline Amendments  

In its work to formulate CEQA Guideline Amendments for GHG emissions, OPR submitted the 

Proposed Draft CEQA Guideline Amendments for Greenhouse Gas Emissions to the Secretary for 

Natural Resources on April 13, 2009. The Natural Resources Agency conducted formal 

rulemaking procedures in 2009 and adopted the CEQA Guideline Amendments on December 30, 

2009. They became effective in March 2010.  

Senate Bill 375  

The California legislature passed SB 375 (Steinberg) on September 1, 2008. SB 375 requires CARB 

to set regional greenhouse gas reduction targets after consultation with local governments. The 

target must then be incorporated within that region’s regional transportation plan (RTP), which 

is used for long‐term transportation planning, in a Sustainable Communities Strategy. SB 375 

also requires each region’s regional housing needs assessment (RHNA) to be adjusted based on 

the Sustainable Communities Strategy in its RTP. Additionally, SB 375 reforms the 

environmental review process to create incentives to implement the strategy, especially transit 

priority projects. The governor signed SB 375 into law on September 30, 2008.  

On January 23, 2009, CARB appointed a Regional Targets Advisory Committee (RTAC) to 

provide recommendations and methodologies to be used in the target setting process.  The RTAC 

provided its recommendations in a report to CARB on September 29, 2009. On August 9, 2010, 

CARB staff issued the Proposed Regional Greenhouse Gas Emission Reduction Targets For Automobiles 

And Light Trucks Pursuant To Senate Bill 375 (CARB 2010b). CARB staff proposed draft reduction 

targets for the four largest MPOs (Bay Area, Sacramento, Southern California, and San Diego) of 

7 to 8 percent for 2020 and reduction targets between 13 to 16 percent for 2035.  For the Bay Area, 

CARB established a draft target of 7 percent for 2020 and 15 percent for 2035.  These targets were 

recommended to CARB by the Metropolitan Transportation Commission, which adopted the 

thresholds for its planning purposes on July 28, 2010.  Of note, the proposed reduction targets 

explicitly exclude emission reductions expected from the AB 1493 and low carbon fuel standard 

regulations.  CARB adopted the final targets on September 23, 2010.  

Title 24 Building Standards Code  

Page 42: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 38 of 74 

 

The California Energy Commission first adopted Energy Efficiency Standards for Residential and 

Nonresidential Buildings (California Code of Regulations, Title 24, Part 6) in 1978 in response to 

a legislative mandate to reduce energy consumption in the state. Although not originally 

intended to reduce GHG emissions, increased energy efficiency, and reduced consumption of 

electricity, natural gas, and other fuels would result in fewer GHG emissions from residential 

and nonresidential buildings subject to the standard.  The standards are updated periodically to 

allow for the consideration and inclusion of new energy efficiency technologies and methods.  

The latest revisions were adopted in 2008 and became effective on January 1, 2010.  

Part 11 of the Title 24 Building Standards Code is referred to as the California Green Building 

Standards Code (CALGreen Code). The purpose of the CALGreen Code is to “improve public 

health, safety and general welfare by enhancing the design and construction of buildings through 

the use of building concepts having a positive environmental impact and encouraging 

sustainable construction practices in the following categories: (1) Planning and design; (2) Energy 

efficiency; (3) Water efficiency and conservation; (4) Material conservation and resource 

efficiency; and (5) Environmental air quality” (California Building Standards Commission 2009). 

Unless otherwise noted in the regulation, all newly constructed buildings in California are 

subject to the requirements of the CALGreen Code.  

Regional  

Bay Area Air Quality Management District  

On June 2, 2010, the BAAQMD adopted updated CEQA Air Quality Guidelines. These guidelines 

contain greenhouse gas operational emissions significance thresholds and recommended 

methodologies and models to be used for assessing the impacts of project‐specific GHG 

emissions on global climate change (BAAQMD 2010a). The updated CEQA Air Quality Guidelines 

contain project‐level screening criteria and recommended significance thresholds for evaluation 

of operational GHG emissions from a proposed project. The guidelines also contain 

recommended methodologies to use to estimate these emissions and provide recommended 

measures for reducing GHG emissions from land use development projects and stationary 

sources.  

Local Plans and Policies  

University of California Policy on Sustainable Practices  

The Regents have delegated authority to the President for promulgating policy promoting 

sustainable new capital projects, existing University facilities, and campus transportation 

resources. The University of California Policy on Sustainable Practices is a system‐wide 

commitment to minimize the University of California’s impact on the environment and reduce 

the University’s dependence on non‐renewable energy sources.25  The University of California 

25 http://www.universityofcalifornia.edu/sustainability/documents/policy_sustain_prac.pdf

Page 43: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 39 of 74 

 

Policy on Sustainable Practices promotes the principles of energy efficiency and sustainability in 

the areas of Green Building Design; Clean Energy Standard; Climate Protection Practices; 

Sustainable Transportation Practices; Sustainable Operations; Recycling and Waste Management; 

Environmentally Preferable Purchasing Practices; and Food, all of which help reduce GHG 

emissions from University operations, and meet the State goals of reducing GHG emissions to 

1990 levels by 2020..  

The Policy guidelines currently recommend that University operations:  

Incorporate the principles of energy efficiency and sustainability in all capital projects, 

renovation projects, operations and maintenance within budgetary constraints and 

programmatic requirements.  

Minimize the use of non‐renewable energy sources on behalf of the University’s built 

environment by creating a portfolio approach to energy use, including the use of local 

renewable energy and purchase of green power from the grid as well as conservation 

measures that reduce energy consumption.  

Incorporate alternative means of transportation to/from and within the campus to 

improve the quality of life on campus and in the surrounding community. The campuses 

will continue their strong commitment to provide affordable on‐campus housing, in 

order to reduce the volume of commutes to and from campus. These housing goals are 

detailed in the campuses’ Long Range Development Plans.  

Track, report and minimize greenhouse gas emissions on behalf of University operations.  

Minimize the amount of University‐generated waste sent to landfill.  

Utilize the University’s purchasing power to meet its sustainability objectives. 

 

UCSF Climate Action Plan  

UCSF published its Climate Action Plan (CAP) in December of 2009 in order to comply with the 

UC Policy on Sustainable Practices as well as meet the requirements of the American Colleges 

and University Presidents Climate Commitment (ACUPCC), of which the UC system is a 

signatory.  The UCSF CAP includes the UCSF 1990 GHG emissions baseline, current (2008) 

emissions, projected 2020 emissions, sustainability efforts to date, and outlines future reduction 

measures UCSF will undertake in order to meet the emissions reduction goal.  UCSF’s 1990 GHG 

emissions levels were estimated to be 81,950 MTCO2e and its 2008 GHG emission levels to be 

162,713 MTCO2e year.  UCSF has committed to reduce its GHG emissions from all of its 

operations to the 1990 level by 2020, with the eventual goal of achieving carbon neutrality for the 

campus.  As part of the system‐wide emissions reduction effort, UCSF regularly reports to The 

Regents its emissions, progress towards reduction goals, and measures used or proposed to meet 

Page 44: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 40 of 74 

 

the Policy on Sustainable Practices goals.  

Page 45: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 41 of 74 

 

4.1.4 SIGNIFICANCE STANDARDS AND ANALYSIS METHODOLOGY  

Significance Criteria  

In accordance with Senate Bill (SB) 97, the Natural Resources Agency adopted amendments to 

the State CEQA Guidelines on December 30, 2009 (effective March 2010), which include criteria for 

evaluating GHG emissions.26  According to the amended Appendix G of the State CEQA 

Guidelines, a project would have a significant effect on the environment if it would:  

Generate greenhouse gas emissions, either directly or indirectly, that may have a 

significant impact on the environment; or  

Conflict with an applicable plan, policy or regulation adopted for the purpose of 

reducing the emissions of greenhouse gases.  

The amended State CEQA Guidelines include a new Section 15064.4, which states that, when 

making a determination of the significance of GHG emissions, a lead agency shall have 

discretion to determine whether to: (1) Use a model or methodology to quantify greenhouse gas 

emissions resulting from a project, and which model or methodology to use; and/or (2) Rely on a 

qualitative analysis or performance based standards.  

Section 15064.4 also states that a lead agency should consider the following factors when 

assessing the significance of GHG emissions on the environment: (1) The extent to which the 

project may increase or reduce greenhouse gas emissions as compared to the existing 

environmental setting; (2) Whether the project emissions exceed a threshold of significance that 

the lead agency determines applies to the project; and (3) The extent to which the project 

complies with regulations or requirements adopted to implement a statewide, regional, or local 

plan for the reduction or mitigation of greenhouse gas emissions.  

The first Appendix G criteria may be evaluated by performing a direct calculation of the GHG 

emissions resulting from the proposed project and comparing the emissions with the available 

significance thresholds. The BAAQMD has established project‐level screening criteria and 

significance thresholds for operational GHG emissions in its CEQA Air Quality Guidelines. The 

BAAQMD’s thresholds of significance for operational‐related GHG emissions are as follows:  

For land use development projects, the threshold is compliance with a qualified GHG 

Reduction Strategy; or annual emissions less than 1,100 metric tons CO2e per year 

(MTCO2e/yr); or 4.6 MT CO2e/person/yr (residents plus employees). Land use 

development projects include residential, commercial, industrial, and public land uses 

and facilities.  

For stationary‐source projects, the threshold is 10,000 MTCO2e/yr. Stationary‐source 

projects include land uses that would accommodate processes and equipment that emit 

26 http://ceres.ca.gov/ceqa/guidelines/

Page 46: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 42 of 74 

 

GHG emissions and would require an Air District permit to operate.  

The BAAQMD guidelines do not contain a quantitative threshold of significance for the 

evaluation of GHG emissions resulting from a project’s construction activities.  

The second Appendix G criteria may be evaluated by demonstrating compliance with plans, 

policies, or regulations adopted by local governments to curb GHG emissions. According to the 

Natural Resources Agency:  

Provided that such plans contain specific requirements with respect to resources that are 

within the agency‘s jurisdiction to avoid or substantially lessen the agency‘s 

contributions to GHG emissions, both from its own projects and from private projects it 

has approved or will approve, such plans may be appropriately relied on in a cumulative 

impacts analysis (Natural Resources Agency 2009).  

Under CEQA, “the determination of whether a project may have a significant effect on the 

environment calls for careful judgment on the part of the public agency involved, based to the 

extent possible on scientific and factual data” (CEQA Section 15064). CEQA grants agencies with 

the general authority to adopt criteria for determining whether a given impact is “significant” 

(California Public Resources Code Section 21082). When no guidance exists under CEQA, the 

agency may look to and assess general compliance with comparable regulatory schemes. The 

BAAQMD’s CEQA Air Quality Guidelines represent a comparable regulatory scheme.  

Based on the above, the proposed project’s significance with respect to the GHG emissions and 

global climate change will be assessed based on the BAAQMD’s GHG thresholds of significance 

and on the project features and GHG reduction measures that are consistent with the BAAQMD’s 

recommended measures to reduce GHG emissions.  

Methodology  

OPR in its Technical Advisory has recommended that GHG emissions from project‐related 

traffic, energy consumption, water usage, and construction activities, should be identified and 

estimated, to the extent that data are available to calculate such emissions. In addition, CARB 

staff has considered extensively the value of indirect emissions in a mandatory reporting 

program. CARB believes that indirect energy usage provides a more complete picture of the 

emissions footprint of a facility: “As facilities consider changes that would affect their emissions 

– addition of a cogeneration unit to boost overall efficiency even as it increases direct emissions, 

for example – the relative impact on total (direct plus indirect) emissions by the facility should be 

monitored. Annually reported indirect energy usage also aids the conservation awareness of the 

facility and provides information” to CARB to be considered for future strategies by the 

industrial sector. For these reasons, CARB has proposed requiring the calculation of direct and 

indirect GHG emissions as part of the AB 32 reporting requirements, and this analysis does so 

(CARB 2007).  

Page 47: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 43 of 74 

 

The California Air Pollution Control Officers Association (CAPCOA) has stated that the 

information needed to characterize GHG emissions from manufacture, transport, and end‐of‐life 

of construction materials (often referred to as lifecycle emissions) would be speculative at the 

CEQA analysis level (CAPCOA 2008). Since accurate and reliable data does not exist for 

estimating lifecycle emissions for the proposed project, the analysis does not assess such lifecycle 

GHG emissions.  

The data sources and tools used to evaluate the GHG impacts associated with construction and 

operation of the proposed project include the URBEMIS2007 Environmental Management 

Software, and information provided in the Software User’s Guide [for] URBEMIS2007 for Windows 

(Rimpo and Associates 2008) and calculation algorithms supported by the sources listed above. 

The URBEMIS2007 model utilizes the EMFAC2007 emissions factor model for on‐road motor 

vehicle sources and the OFFROAD2007 emissions factor model for off‐road equipment. Site‐

specific or project‐specific data were used in the URBEMIS2007 model where available. Where 

information was not available for the project, model default values suggested by the BAAQMD 

were selected. The average daily trip (ADT) generation rate for the proposed project was based 

on the project’s traffic study. The BAAQMD has developed a greenhouse gas emissions modeling 

spreadsheet, called BGM, which uses URBEMIS2007 files in conjunction with emission and 

resource consumption factors specific to the Bay Area to calculate greenhouse gas emissions from 

projects within the BAAQMD’s jurisdiction. The BGM is the BAAQMD’s preferred method for 

estimating operational GHG emissions. The BGM was used in conjunction with URBEMIS2007.  

Additional sources consulted for this analysis include data and guidance from the U.S. EPA, the 

U.S. Energy Information Administration, CARB, the California Energy Commission, the 

California Climate Action Registry’s General Reporting Protocol, and other GHG and global 

climate change data as referenced. Emission calculations conducted for the proposed project are 

contained in Appendix B.  

Page 48: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 44 of 74 

 

 

4.1.5 IMPACTS AND MITIGATION MEASURES  

Impact GHG‐1: Project development would generate greenhouse gas emissions, either directly 

or indirectly, that could have a significant impact on the environment. (Significant; Less than 

significant with mitigation)  

 

Operational Impacts  

Once operational, the proposed project would generate direct operational emissions of GHGs, 

primarily CO2, CH4, and N2O, which would be the result of fuel combustion from the building’s 

lighting and elevator systems, from fuel combustion by the motor vehicles using the garage, and 

from motor vehicle air conditioning. Motor vehicle air conditioning systems may also use HFCs 

(and HCFCs and CFCs to the extent that they have not been completely phased out at later 

dates); however, these emissions are not quantified since they would only occur through 

accidental leaks and it is not possible to estimate the frequency of accidental leaks without some 

level of speculation.  It should be noted that CARB has adopted a mobile air conditioning 

regulation that reduces emissions associated with the use of small containers of automotive 

refrigerants. This regulation requires that refrigerant container be self‐sealing and went into 

effect on January 1, 2010. CARB has also proposed regulations that require the use of lower GWP 

refrigerants in vehicle air conditioners.  

 

Mobile Source Emissions  

Emissions from motor vehicles were calculated using the BAAQMD Greenhouse Gas Model 

(BGM), which uses URBEMIS2007 files in conjunction with emission and consumption factors 

specific to the Bay Area to calculate greenhouse gas emissions from projects within the 

BAAQMD’s jurisdiction. The BGM is the BAAQMD’s preferred method for estimating 

operational GHG emissions and takes into account the California specific emissions reductions 

required for motor vehicles. For the purposes of estimating GHG emissions with BGM, the 

proposed project was assumed to have similar non‐mobile source emissions characteristics to a 

warehouse, as a parking garage is not included as a land use category in BGM.  Mobile emissions 

were based on traffic data provided by the traffic study for the proposed project.  It should be 

noted that parking structures do not generate vehicle trips; rather vehicle trips are generated by 

the land uses that the parking structure serves. The proposed project would serve vehicle trips 

associated with the Medical Center at Mission Bay Phase I buildings, which have commenced 

construction.  Nonetheless, for a conservative GHG analysis of the proposed garage, a portion of 

the vehicle trips that would be generated by the Medical Center uses will be attributed to the 

garage, even though such trips would be generated by already approved Medical Center uses.  

The Medical Center at Mission Bay 2008 FEIR projected 4,465 vehicle trips per day associated 

with Phase I of the MCMB project.  Of these, about 2,616 vehicles per day (58.6%) associated with 

Page 49: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 45 of 74 

 

the Medical Center at Mission Bay buildings could be attributed to the proposed garage.27   This 

portion of the project is what is analyzed for the greenhouse gas emissions of the proposed 

garage. 

Non‐Mobile Source Emissions  

Non‐mobile sources include area sources (landscaping, hearths and fireplaces), natural gas and 

electricity consumption, water use and wastewater generation, and solid waste disposal. 

Emissions from these sources were also calculated using the BGM. Neither the BGM nor the 

URBEMIS2007 model includes a parking garage land‐use type and so the warehouse land‐use 

type is typically used as a surrogate.  Electricity and natural gas consumption, water and 

wastewater generation, and solid waste estimates were based on a warehouse land‐use type. It 

should be noted that emissions estimated from electricity and natural gas consumption, water 

and wastewater generation, and solid waste estimates are highly conservative as a warehouse 

would be expected to use significantly more electricity, natural gas, and water, and generate 

more waste than a parking garage. The solid waste emissions take into account UCSF waste 

diversion rate of 60 percent in 2010. The project would not be a major stationary source.28 

Total Operational Emissions  

Table 4.1‐5, Estimated Operational GHG Emissions, shows a summary of total estimated GHG 

emissions from operation of the proposed project and compares these to the BAAQMD 

significance thresholds. 

These emissions present a worst case scenario.  Transportation emissions will decline in the 

future as new motor vehicles with lower tailpipe emissions required by existing State (Pavley) 

and Federal regulations are adopted into the vehicle fleet. 

The BAAQMD CEQA guideline prescribe a definition for calculating Service Population (SP = 

residents + employees). The proportionate SP for the proposed project would be 786.  

As shown in Table 4.1‐3, the proposed project’s operational emissions would exceed the project 

level threshold of 1,100 MTCO2e for land use development projects. The project’s impact would 

therefore be significant.  

 

27 The total project parking, surface lot + garage, is 1,068 spaces.  The proposed  garage is 626 spaces, or 

58.6% of the total spaces. 

 28 Parking garages are typically open to the air, and do not have large heating or air conditioning systems, 

e.g. ‘permitted or major stationary sources’.  The proposed project does not have a large heating or air 

conditioning system. 

Page 50: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 46 of 74 

 

Table 4.1‐3 Estimated Operational GHG Emissions  

Source  Emissions 

(MTCO2e) 

Transportation  3,167.59 

Electricity  451.16 

Natural Gas  36.81 

Water & Wastewater  6.05 

Solid Waste  133.66 

Total Operational GHG Emissions  3,795.27 MTCO2e /year 

or  

4.8 MTCO2e/SP/year  

BAAQMD Threshold  1,100 MTCO2e /year 

or 

Compliance with a qualified 

GHG Reduction Strategy 

or 

4.6 MTCO2e/SP/year 

Exceeds Threshold  Yes 

 

 Phase I Garage Mitigation:  The Regents have committed the system to reduce its GHG 

emissions from all of its operations to the 1990 level by 2020.  In furtherance of the goal to meet 

these goals, the University is currently implementing the 2010‐12 Statewide Energy Partnership 

Program (through the UC Strategic Energy Plan), an ambitious three year program  to help meet 

its goal.  In March 2009, The Regents approved $247 million of funding for the program.29  In 

September 2010, The Regents approved an augmentation to the 2010‐12 Statewide Energy 

Partnership Program, authorizing $15.7 million for additional projects at two campuses.30 This 3 

year program, in its second year of implementation, is expected to reduce energy consumption 

by 11%, natural gas consumption by 8%, and greenhouse gas emissions by 9% system‐wide.    

As identified in the UCSF Climate Action Plan, UCSF is undertaking many of these energy 

efficiency projects to retrofit existing facilities in order to assist the campus to meet its 

greenhouse gas goals.  These energy efficiency projects at UCSF provide more than 2,700 

29 With external financing providing $178 million and utility incentive payments and other individual 

Campus funds providing the balance. 

Page 51: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 47 of 74 

 

MtCO2e ongoing new reductions per year.  Detail on campus specific reduction projects are 

described in the UC system wide Strategic Energy Plan.31 

As discussed above, The Regents has approved funding for the 2010 Statewide Energy 

Partnership Program / UC Strategic Energy Plan.  UCSF would mitigate at least 2,700 MtCO2e 

ongoing reductions per year, e.g. the additional significant GHG emissions associated with the 

proposed garage project, with the appropriate number of energy efficiency projects identified on 

the list in the Phase I Garage Supplemental EIR Appendix C.  Projects identified in Appendix C 

are those projects that are included in the funded, UC Strategic Energy Plan and that are planned 

to be implemented by 2012, around the time garage operations would begin.  

Significance after Mitigation:  Less than Significant   

 

Construction Impacts  

Construction of the proposed project would result in one‐time emissions of greenhouse gases. 

The primary greenhouse gases during construction are CO2, CH4, and N2O. These emissions are 

the result of fuel combustion by construction equipment and motor vehicles. The other GHGs 

defined by state law (hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride) are 

typically associated with specific industrial sources and processes and would not be emitted 

during construction of the proposed project. The URBEMIS2007 Environmental Management 

Software was used to estimate the construction‐related CO2 emissions. Construction of the 

proposed project is anticipated to commence in Summer 2011 and continue for approximately 12 

months. Construction activities would include grading/excavation, trenching, building 

construction, and architectural coating. UCSF provided a preliminary schedule for construction 

and grading amounts. The default construction equipment and vehicle mixes generated by 

URBEMIS2007 were assumed for grading and building construction. The number of vendor trips 

(e.g., transport of building materials) and worker trips were based on default values in the 

URBEMIS2007 model. URBEMIS2007 only calculates CO2 emissions and does not provide 

estimates of other GHGs associated with combustion (i.e., CH4 and N2O). Therefore, in order to 

account for emissions of these compounds, the following adjustments were made to the 

URBEMIS2007 emission calculations to convert CO2 emissions to a CO2e basis:  

Construction Off‐Road and On‐Road Equipment. The CO2 emissions associated with 

off‐road and on‐road equipment were multiplied by a factor based on the assumption 

that CO2 represents approximately 99.1 and 99.9 percent, respectively, of the CO2e 

emissions. These assumptions were derived from the California Climate Action Registry 

(CCAR 2009) and the California Energy Commission (CEC 2002).  

Motor Vehicles (Workers). The CO2 emissions associated with construction‐related 

worker trips were multiplied by a factor based on the assumption that CO2 represents 95 

30 Including $2.4 million additional for the UCSF campus. 

31 http://www.universityofcalifornia.edu/sustainability/documents/ucsep_sw.pdf  page 14/21 

Page 52: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 48 of 74 

 

percent of the CO2e emissions associated with passenger vehicles, which account for 

most of the project‐related trips (U.S. EPA 2005). The 95 percent factor accounts for CH4, 

N2O and fugitive GHG emissions associated with mobile source air conditioning 

equipment.  

The BAAQMD does not have a quantitative threshold of significance for construction‐related 

GHG emissions. However, the CEQA Air Quality Guidelines requires the Lead Agency to quantify 

and disclose GHG emissions that would occur during construction. Table 4.1‐4, Estimated 

Construction GHG Emissions shows a summary of total estimated GHG emissions from the 

construction of the proposed project. Given the low numbers, the fact that they are much lower 

than the threshold for operational emissions, and the fact that these would be one‐time 

emissions, the effect on global climate from the proposed project’s construction would not be 

substantial.  

Table 4.1‐4 Estimated Construction GHG Emissions  

Construction Year  Emissions 

(MTCO2e) 

2011  250.25 

2012  250.25 

Total  500.5 

BAAQMD Threshold  None 

 

 Impact GHG‐2: The proposed project could conflict with an applicable plan, policy or 

regulation adopted for the purpose of reducing the emissions of greenhouse gases. (Less than 

Significant)  

The primary GHG emissions regulation in California is AB 32, which is discussed above. The 

BAAQMD GHG significance threshold was specifically designed to ensure compliance with AB 

32 emissions reductions requirements in the Bay Area. This was accomplished by the BAAQMD 

by inventorying existing GHG emissions, estimating projected GHG emissions based on 

projected growth in the Bay Area, determining the reductions needed to comply with AB 32 

target for the Bay Area, determining the GHG emissions allowable from new sources associated 

with the growth, and arriving at the 1,100 MTCO2e threshold for a land development project as 

an emission level that would not set back the area from the attainment of AB 32 goals.   The 

project would not set back AB 32 efforts for the Bay Area air basin.  

The BAAQMD 2010 Clean Air Plan contains energy, transportation, and mobile source control 

measures that would reduce operational GHG emissions and that would be potentially 

applicable to the project. The following measures are taken from the 2010 CAP (BAAQMD 

Page 53: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 49 of 74 

 

2010b).  

MSM A‐2: Zero Emission Vehicles and Plug‐In Hybrids. Expand the use of Zero 

Emission (ZEV) and Plug‐in Hybrid (PHEV) passenger vehicles and light‐duty trucks 

within the Bay Area, working in partnership with the Bay Area Electric Vehicle Corridor 

coalition.  

TCM E‐2: Parking Pricing and Management Strategies. Promote policies to implement 

market‐rate pricing of parking facilities, reduce parking requirements for new 

development projects, parking “cash‐out,” unbundling of parking in residential and 

commercial leases, shared parking at mixed‐use  facilities, etc.  

TCM E‐3: Implement Transportation Pricing Reform. Develop a regional transportation 

pricing strategy that includes policy evaluation and implementation. Pricing policies to 

be evaluated include gasoline taxes, bridge tolls, congestion pricing, parking pricing, 

HOT lanes, VMT or carbon fees, pay‐as‐you‐drive insurance, etc.  

The project includes project design features that are generally consistent with the above 

measures. Furthermore, UCSF has incorporated into the proposed project substantial 

sustainability features, including several GHG mitigation measures included in the BAAQMD 

CEQA guidelines. These features include secure bicycle parking, parking fees, and electric 

vehicle charging stations.  In addition, garage attendants would be available to provide 

information on alternative transportation and sell transit passes. Design features to minimize the 

use of energy and water would also be employed. These features would reduce GHG emissions 

from the levels estimated, which assumed no such features would be included, and ensure 

compliance with the BAAQMD GHG control plans.   In terms of pricing policies to discourage 

single‐occupant vehicle commuters, UCSF plans to continue its annual parking fee increase on 

employee parking permits – an annual increase of 7 percent to 8 percent or more for the 

foreseeable future as a component of the campus’ overall sustainability efforts and in support of 

the City’s transit first policy.  

With implementation of the reduction projects identified in Impact GHG‐1, emissions would be 

mitigated to less than 1,100 MMTCO2e /year. The proposed project would not conflict with an 

applicable plan, policy or regulation adopted for the purpose of reducing the emissions of 

greenhouse gases. 

The Regents has committed the UC system to meet the State of California’s AB32 goal to reduce 

GHG emissions to 1990 levels 2020 through the policies identified in the University of California 

Policy on Sustainable Practices.32  The policy spells out four implementation procedures the 

campuses will complete to ensure that the 2020 emission reduction goals are met.   

Each UC campus will pursue individual membership with either the California Climate Action 

Registry (CCAR) or The Climate Registry (TCR). The Senior Vice President, Business and 

32 http://www.universityofcalifornia.edu/sustainability/documents/policy_sustain_prac.pdf 

Page 54: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 50 of 74 

 

Finance, in coordination with campus administration, faculty, students and other stakeholders, 

will form a Climate Change Working Group that will develop a protocol to allow for growth 

adjustment and normalization of data and accurate reporting procedures. The Climate Change 

Working Group will monitor progress toward reaching the stated goals for GHG reduction, 

and will evaluate suggestions for programs to reach these goals. 

 

By September 15, 2008, each UC campus will complete a greenhouse gas emissions inventory. To 

comply with CCAR (or TCR) and ACUPCC requirements, inventories should contain emissions 

from the six Kyoto greenhouse gasses, including: direct and indirect emissions outlined in the 

ACUPCC implementation guide and CCAR or TCR general reporting protocol; air travel paid 

for by or through the institution; and commuting to and from campus on a day to day basis by 

students, faculty, and staff. As ACUPCC member institutions, all UC campuses will report their 

updated emissions inventories through the ACUPCC on‐line reporting tool at least once every 

other year. 

 

By December 2008, the University will develop an action plan for becoming climate neutral 

which will include: a feasibility study for meeting the 2014 and 2020 goals stated in the Policy 

Guidelines, a target date for achieving climate neutrality as soon as possible while maintaining 

the University’s overall mission, and a needs assessment of the resources required to 

successfully achieve these goals. Climate neutrality means that the University will have a net 

zero impact on the Earth’s climate, and will be achieved by minimizing GHG emissions as 

much as possible and using carbon offsets or other measures to mitigate the remaining GHG 

emissions. 

 

By September 15, 2009, each UC campus will implement two of the seven tangible actions to 

reduce greenhouse gas emissions that are outlined in the ACUPCC. 

 

UCSF has completed all four implementation procedures identified above and is in compliance 

with the University of California’s Policy on Sustainable Practices. 

The proposed project would also be consistent with the UCSF Climate Action Plan (UCSF 2009). 

The Climate Action Plan contains the following transportation‐related measures would reduce 

transportation‐related GHG emissions:  

Transportation Demand Management (TDM) Program – UCSF’s TDM conforms with San 

Francisco’s Transit First Policy to encourage the use of alternative transportation to single‐

occupancy vehicles. UCSF has excellent transit ridership rates according to latest transportation 

survey. About 25.6% of respondents (faculty, staff, and students) reported taking public transit 

(e.g., Muni or other bus system) as their main transportation choice in the latest mobility 

choices survey.  

Bicycling Accommodations ‐Bicycle racks have been expanded from 400 spaces in 2003 

to 680 in 2008. There are now 53 shuttle mounted bike racks. Expenditures on new bike 

Page 55: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 51 of 74 

 

racks were $13,445 in 2008. UCSF bicyclists are eligible for a reduced price membership 

in the San Francisco Bicycle Coalition.  

Fuel Efficient Vehicles – The Campus supplies 2 electric vehicle charging stations. Fifteen 

percent (42 of 273) of campus fleet vehicles are powered by alternative fuel or a hybrid 

electric and gas. The Campus offers 103 motorcycle parking stalls.  

Transit Pass sales –To further encourage transit use UCSF offers the Campus community 

5 convenient locations to purchase city and regional transit passes. MUNI Fast Pass and 

Bart Commuter Ticket Monthly sales are 600 passes in 2008.  

Vanpools – The number of vanpools increased from 30 in 2003 to 46 in 2008 and the 

number of car sharing from three to 17 during the same period. These efforts, led by 

UCSF Transportation Services, earned UCSF a place on the inaugural 2006 national list of 

Best Workplaces for Commuters from colleges and universities, awarded by the US 

Environmental Protection Agency (EPA). Vanpools receive preferential parking spaces at 

UCSF.  

The UCSF Climate Action Plan contains the following Strategic Energy Plan improvements that 

are pertinent to the proposed project. These measures will be investigated for potential 

implementation by the proposed project and would reduce energy demand and associated GHG 

emissions:  

Lighting Projects UCSF will continue to convert existing T12 and 32 watt T8 fluorescent 

light fixtures to 28 watt T8 lamps. Other possibilities include: broader use of occupancy 

sensor controls, daylight harvesting, and new stairwell fixtures. The replacement of 

lighting in parking structures and interior HID fixtures and with fluorescent will also be 

evaluated. New technologies such as LED lighting, bi‐level fixtures and induction lamps 

are anticipated to become readily available in the near future and these technologies will 

be incorporated into energy efficiency retrofit projects where appropriate.  

As noted above, the proposed project includes secure bicycle parking, parking fees, and electric 

vehicle charging stations.  In addition, garage attendants would be available to provide 

information on alternative transportation and sell transit passes. The project could also provide 

preferential parking spaces for carpools and vanpools, depending on need, consistent with UCSF 

guidelines. These measures would reduce transportation‐related GHG emissions consistent with 

the Climate Action Plan measures. The project would also be designed to minimize the energy 

demand by using energy‐efficient lighting (fluorescent, LED lighting, or similar depending on 

cost effectiveness). Based on the inclusion of these project design features, the project would be 

consistent with applicable plans that have been adopted to reduce GHG emissions. The impact 

would be less than significant.  

Mitigation: No additional mitigation is required.  

Page 56: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 52 of 74 

 

4.1.5 References  

Bay Area Air Quality Management District. 2010a. “CEQA Air Quality Guidelines.” 

http://www.baaqmd.gov/Divisions/Planning‐and‐Research/CEQA‐

GUIDELINES/UpdatedCEQA‐Guidelines.aspx.  

Bay Area Air Quality Management District. 2010b. “2010 Clean Air Plan.” 

http://www.baaqmd.gov/ Divisions/Planning‐and‐Research/Plans/Clean‐Air‐Plans.aspx.  

Bay Area Air Quality Management District. Source Inventory of Bay Area Greenhouse Gas 

Emissions. 

http://www.baaqmd.gov/~/media/Files/Planning%20and%20Research/Emission%20Inve

ntory/regionalinventory2007_2_10.ashx 

California Air Pollution Control Officers Association. 2008. CEQA & Climate Change: Evaluating 

and Addressing Greenhouse Gas Emissions from Projects Subject to the California 

Environmental Quality Act.  

California Air Resources Board. 2007. Initial Statement of Reasons for Rulemaking, Proposed 

Regulation for Mandatory Reporting of Greenhouse Gas Emissions Pursuant to the California 

Global Warming Solutions Act of 2006 (Assembly Bill 32).  

California Air Resources Board. 2008. Local Government Operations Protocol for the Quantification 

and Reporting of Greenhouse Gas Emissions Inventories Version 1.0.  

California Air Resources Board. 2009. “Stationary Equipment Refrigerant Management 

Program.” http://www.arb.ca.gov/cc/reftrack/reftrack.htm. This regulation is an early 

action measure under AB 32.  

California Air Resources Board. 2010a. “California Greenhouse Gas 2000‐2008 Inventory by 

Scoping Plan Category – Summary.” http://www.arb.ca.gov/cc/inventory/data/data.htm.  

California Air Resources Board. 2010b. Staff Report: Proposed Regional Greenhouse Gas Emission 

Reduction Targets For Automobiles And Light Trucks Pursuant To Senate Bill 375.  

California Building Standards Commission. 2009. 2008 California Green Building Standards Code.  

California Building Standards Commission. 2010. “CALGreen.” 

http://www.bsc.ca.gov/CALGreen/ default.htm.  

California Climate Action Registry. 2009. General Reporting Protocol: Reporting Entity‐Wide 

Greenhouse as Emissions Version 3.1.  

California Climate Action Team. 2007. Updated Macroeconomic Analysis of Climate Strategies 

Presented in the March 2006 Climate Action Team Report.  

California Department of Finance. 2010a. “E‐5 Population and Housing Estimates for Cities, 

Counties, and the State, 2001‐2008, with 2000 Benchmark.” 

Page 57: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 53 of 74 

 

http://www.dof.ca.gov/research/demographic/ reports/estimates/e‐5/2009.  

California Department of Finance. 2010b. “Financial & Economic Data: Gross Domestic Product, 

California.” http://www.dof.ca.gov/HTML/FS_DATA/LatestEconData/FS_Misc.htm.  

California Energy Commission. 2002. Diesel Use in California. Remarks by Commissioner James D. 

Boyd.  

California Energy Commission. 2006a. Inventory of California Greenhouse Gas Emissions and Sinks 

1990 to 2004, Figure 2.  

California Energy Commission. 2006b. Refining Estimates of Water‐Related Energy Use in California, 

PIER Final Project Report (CEC‐500‐2006‐118). Prepared by Navigant Consulting, Inc.  

California Energy Commission. 2007. “Revisions to the 1990‐2004 Greenhouse Gas Emissions 

Inventory Report, Published in December 2006.” 

http://www.energy.ca.gov/2006publications/CEC‐6002006‐013/2007‐01‐

23_GHG_INVENTORY_REVISIONS.PDF.  

California Environmental Protection Agency, Climate Action Team. 2006. Climate Action Team 

Report to Governor Schwarzenegger and the Legislature.  

California Environmental Quality Act Guidelines. California Code of Regulations, Title 14, 

Division 6, Chapter 3, Section 15064(b).  

California Natural Resources Agency, Climate Action Team. 2009. 2009 California Climate 

Adaptation Strategy: A Report to the Governor of the State of California in Response to Executive 

Order S‐13‐2008. California Public Resources. nd. Code Section 21082.  

California Office of the Attorney General. 2008. The California Environmental Quality Act: 

Addressing Global Warming Impacts at the Local Agency Level.  

California Office of the Attorney General. 2010. “Addressing Climate Change at the Project 

Level,” http://ag.ca.gov/globalwarming/pdf/GW_mitigation_measures.pdf  

City and County of San Francisco, Office of the Mayor. 2010. “Press Release: Mayor Newsom 

Announces San Francisco’s Waste Diversion Rate At 77 Percent, Shattering City Goal 

And National Recycling Records.” http://sfmayor.org/press‐room/press‐releases/press‐

release‐mayor‐newsom‐announcessan‐francisco%E2%80%99s‐waste‐diversion‐rate‐at‐

77‐percent‐shattering‐city‐goal‐and‐nationalrecycling‐records/.  

Energy Information Administration. n.d. “Other Gases: Hydrofluorocarbons, Perfluorocarbons, 

and Sulfut Hexafluoride.” http://www.eia.doe.gov/oiaf/1605/gg00rpt/other_gases.html.  

Intergovernmental Panel on Climate Change. 1996. Climate Change 1995: The Science of Climate 

Change – Contribution of Working Group I to the Second Assessment Report of the 

Intergovernmental Panel on Climate Change.  

Intergovernmental Panel on Climate Change. 2007. “Climate Change 2007: The Physical Science 

Page 58: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 54 of 74 

 

Basis, Summary for Policymakers.” 

http://ipccwg1.ucar.edu/wg1/docs/WG1AR4_SPM_Plenary Approved.pdf.  

Letter to Governor Arnold Schwarzenegger from U.S. EPA Administrator Stephen L. Johnson, 

December 19, 2007.  

Natural Resources Agency. 2009. Final Statement of Reasons for Regulatory Action: Amendments to 

the State CEQA Guidelines Addressing Analysis and Mitigation of Greenhouse Gas Emissions 

Pursuant to SB97.  

Office of Planning and Research. 2008a. CEQA and Climate Change: Addressing Climate Change 

Through California Environmental Quality Act (CEQA) Review.  

Office of Planning and Research. 2008b. Technical Advisory – CEQA and Climate Change: Addressing 

Climate Change through California Environmental Quality Act (CEQA) Review.  

Office of Planning and Research. 2009. Preliminary Draft CEQA Guideline Amendments for 

Greenhouse Gas Emissions.  

Rimpo and Associates. 2008. “URBEMIS2007 for Windows.” http://www.urbemis.com.  

United States Census Bureau. 2010. “Data Finders.” http://www.census.gov/.  

United States Environmental Protection Agency. 1998a. Compilation of Air Pollutant Emission 

Factors, AP 

42.  

United States Environmental Protection Agency, Office of Solid Waste and Emergency Response. 

1998b.  

Greenhouse Gas Emission Factors for Management of Selected Materials in Municipal Solid 

Waste (EPA530‐R‐98‐013).  

United States Environmental Protection Agency, Office of Transportation and Air Quality. 2005. 

Greenhouse Gas Emissions from a Typical Passenger Vehicle (EPA420‐F‐05‐004).  

United States Environmental Protection Agency. 2008a. “Advance Notice of Proposed 

Rulemaking:  

Regulating Greenhouse Gas Emissions under the Clean Air Act.” http://www.epa.gov/  

climatechange/anpr.html.  

United States Environmental Protection Agency. 2008b. “Glossary of Climate Change Terms.” 

http://www.epa.gov/climatechange/glossary.html.  

United States Environmental Protection Agency. 2010. “Inventory of US Greenhouse Gas 

Emissions and Sinks 1990‐2008.” 

http://www.epa.gov/climatechange/emissions/usinventoryreport.html.  

United States Environmental Protection Agency. n.d.a. “High GWP Gases and Climate Change.” 

http://www.epa.gov/highgwp/scientific.html#sf6.  

Page 59: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 55 of 74 

 

United States Environmental Protection Agency. n.d.b. “Methane: Sources and Emissions.” 

http://www.epa.gov/methane/sources.html.  

University of California, San Francisco. 2008. Medical Center at Mission Bay FEIR. 

http://campusplanning.ucsf.edu/physical/RFEIRHospital.php 

 University of California, San Francisco. 2009. Climate Action Plan. 

http://www.universityofcalifornia.edu/ sustainability/documents/ucsf_cap_09.pdf  

Page 60: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 56 of 74 

 

4.2  TRANSPORTATION 

4.2.1  INTRODUCTION 

This section evaluates potential changes to the transportation analysis of the MCMB EIR as a 

result of the minor modifications to the proposed Phase I garage project. The MCMB EIR 

concluded that the construction and operation of the Medical Center at Mission Bay, including 

the proposed Phase I garage, would not cause a substantial adverse impact to transit, pedestrian, 

bicycle, or parking conditions, nor result in inadequate emergency access.  The modifications to 

the proposed project would not change the effects anticipated in these topic areas. Therefore, this 

analysis focuses on any potential changes to operational traffic impacts.   

4.2.2  SETTING 

The setting information is substantially the same as discussed in the UCSF Medical Center at 

Mission Bay EIR (pp. 4.5‐1 through 4.5‐8), which is hereby incorporated by reference.  However, 

the current conditions of the project site have changed in that all existing structures and paving 

on the site have been demolished and site work and construction of the hospital complex has 

commenced.       

4.2.3  SIGNIFICANCE CRITERIA AND ANALYSIS METHODOLOGY 

The significance criteria and analysis methodology of the MCMB EIR remain unchanged with 

regard to transportation and traffic.  Traffic impacts were analyzed using the concept of Level of 

Service (LOS), which describes the level of the performance of an intersection based on the 

average delay per vehicle.  Intersection LOS ranges from LOS A, which indicates free‐flow 

conditions with little or no delays, to LOS F, which indicates congested or overloaded conditions 

with extremely long delays.  LOS D, which indicates increasingly unacceptable, yet tolerable, 

delays, is considered to be the minimum acceptable level of service.   

As discussed in the Project Description, although the number of parking spaces within the 

proposed garage has been increased from 600 spaces to 626 spaces with the modified project, the 

number of parking spaces within the surface parking lot, which has been approved, has 

decreased.  The total number of parking spaces in Phase I (626 spaces in the parking structure 

and 442 surface parking spaces) has decreased by approximately seven spaces and would total 

approximately 1,068‐parking spaces, down from the previously analyzed 1,075 spaces.  As 

discussed in the Project Description, the Phase I garage is now proposed to be located to the 

north of its originally proposed site, between North Connector Road and Parking Structure Road.  

Roadways internal to the site and connections to surrounding public streets, including Owens 

Street, would remain unchanged.   

Page 61: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 57 of 74 

 

4.2.4  IMPACTS AND MITIGATION MEASURES  

Medical Center at Mission Bay EIR Analysis  A Transportation Study was prepared for the MCMB EIR.33 The Transportation Study evaluated 

both the Phase I and future buildout of the Phase II development. In addition, the traffic study 

evaluated two potential alternatives for the operation of 4th Street through the Medical Center 

site. Both alternatives would convert the proposed 4th Street right‐of‐way to University of 

California property. 

 

Based on the analysis contained with the Transportation Study, traffic impacts resulting from 

Phase I of the Medical Center at Mission Bay would be less than significant, as all study 

intersections would continue to operate at level‐of‐service D or better.   

 

Effects of Modified Project 

 

The impacts analysis below updates the impacts analysis of the MCMB EIR. 

 

Construction Impacts  

Impact MCMB.6‐1 of the MCMB EIR (analysis updated with this SEIR):  The MCMB EIR 

concluded that construction of the MCMB Phase I project, including the Phase I garage, 

would not result in significant construction‐period impacts. (Less than Significant) 

 

The MCMB EIR concluded that MCMB Phase I construction activities would temporarily 

increase traffic on area roadways (due to construction employee auto trips and construction 

truck traffic), as well as demand for parking in the area.  In addition, the staging of vehicles and 

construction materials would require temporary closure of on‐street parking near the 

construction site.  The MCMB EIR concluded that the LRDP Amendment #2 – Hospital 

Replacement EIR mitigation measure 4.11‐1, which includes limiting the use of local roads as 

haul routes, and/or limiting truck trips to off‐peak hours, and/or developing a parking plan for 

construction employees, would ensure transportation‐related construction impacts would be 

reduced to less than significant levels.  In furtherance of this mitigation measure, the proposed 

Phase I garage, once completed, on a temporary basis would provide some construction 

employee parking until construction of the hospital and surface parking lot is complete. 

 

Mitigation:  None required. 

 

33 Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation Study, March 2008.  

Page 62: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 58 of 74 

 

Operational Impacts  

Impact MCMB.6‐2 of the MCMB EIR (analysis updated with this SEIR):  The MCMB EIR 

concluded that operation of the MCMB Phase I project, including the Phase I garage, would 

not result in a significant impact on the adjacent roadway network.  (Less than Significant) 

 

As discussed in the Project Description, while the number of parking spaces in the parking 

structure (from 600 to 626) would increase as a result of the changes to the proposed project,, the 

total number of parking spaces would decrease by about 7 spaces as a result of the proposed 

decrease in surface parking.  Although the location of the Phase I garage is now proposed in the 

location of the Phase II garage, to the north of the previously proposed Phase I garage site, effects 

on traffic would continue to be less than significant in Phase I.  Overall site circulation and access 

to the parking garage would remain substantially the same.  Multiple access points to/from the 

parking facility (including the adjoining surface lot) would continue to be from North Connector 

Road, South Connector Road, West Connector Road, and Parking Structure Road (formerly 

Center Garage Access), all campus streets on the Medical Center site.  Effects on traffic at 

surrounding study intersections would remain largely unchanged.  As a result of the relocation 

of the Phase I garage to north,  Parking Structure Road/ Owens Street could experience 

incrementally more traffic in Phase I than previously anticipated, but not to the degree that the 

level of service would deteriorate to unacceptable levels. Multiple roadway access would 

continue to be available to the garage, as previously analyzed, and assumptions regarding the 

distribution of traffic at nearby intersections would not substantially change.  

 

Mitigation:  None required. 

 

Impact MCMB.6‐3 of the MCMB EIR (analysis updated with this SEIR):  The MCMB EIR 

concluded that operation of the UCSF Medical Center at Mission Bay project would increase 

traffic at intersections on the adjacent roadway network in the Future Phase (Phase II).  

(Significant) 

The MCMB EIR traffic analysis of the full project (Phase I and Phase II) would not change 

substantially with the modified project.  With the modified project, the construction of the Phase 

II garage would occur to the south of the Phase I garage, at the originally proposed location of 

the Phase I garage.  The significant traffic impact at 16th/Owens in Phase II, which would be 

mitigated to a less‐than‐significant level with the mitigation measure described below, would not 

change with the modified project.  The potential impact at Owens/Center Garage Access would 

remain speculative pending project‐level analysis of the traffic and circulation analyses for Phase 

II. 

Mitigation:  The mitigation measures identified in the MCMB EIR to address significant traffic 

impacts in Phase II would remain unchanged, as follows: 

Page 63: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 59 of 74 

 

16th/Owens:  Mitigation Measure 4.11‐2a from the LRDP Amendment #2 EIR identifies 

modifications to the Owen Street lane configurations (i.e. restriping) to mitigate the 

impact at this intersection:  one southbound shared through‐left turn lane, one 

southbound through lane, and one southbound exclusive right turn lane, would remain 

the same. 

 

Significance after Mitigation: Less than significant. Implementation of the re‐striping at 

this location would improve the operating conditions at this intersection to an acceptable 

LOS D.  The City of San Francisco has found the mitigation measure to be feasible, and 

has committed to working with UCSF to ensure its implementation.34 

 

Owens Street at Center Garage Access:  Mitigation Measure MCMB.6‐3 from the 

Medical Center at Mission Bay EIR would require that UCSF conduct a project‐level 

CEQA review at the time the Phase II development is considered for approval. In 

addition, in order to determine the need for LOS improvements on Owens Street, 

between 16th and Mariposa Streets at Center Garage Access (now Parking Structure 

Road), such as a traffic signal, UCSF would coordinate with the City of San Francisco in 

the periodic update of the Mission Bay traffic triggers survey and would monitor on‐site 

parking access and circulation in order to determine the need for LOS improvements.  

 

Significance after Mitigation:  The need for LOS improvements on Owens Street at the 

Center Garage Access in Phase II remains speculative pending a project‐level design of 

parking requirements and project‐level traffic and circulation evaluation. 

 

 

34 Comment letter dated July 3, 2008 from the San Francisco Municipal Transportation Agency, on the 

UCSF Medical Center at Mission Bay Draft EIR. 

Page 64: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 60 of 74 

CHAPTER 5 CEQA STATUTORY SECTIONS 

5.1  SIGNIFICANT AND UNAVOIDABLE ENVIRONMENTAL 

IMPACTS 

Information regarding significant and unavoidable environmental impacts resulting from the 

project is the same as discussed in the MCMB EIR (p. 5‐1).  That information is hereby 

incorporated by reference. The proposed garage would not affect the conclusions of the MCMB 

EIR with regarding to significant unavoidable impacts.  

5.2  CUMULATIVE IMPACTS 

Information regarding cumulative impacts is the same as discussed in the UCSF Medical Center 

at Mission Bay EIR (p. 5‐2), which is hereby incorporated by reference.  The modified project 

does not affect this analysis.  

5.3  GROWTH‐INDUCING IMPACTS 

Information regarding growth‐inducing impacts is the same as discussed in the UCSF Medical 

Center at Mission Bay EIR (pp. 5‐3 to 5‐4), which is hereby incorporated by reference.  The 

modified project does not affect the analysis. 

5.4    EFFECTS FOUND NOT TO BE SIGNIFICANT 

Much of the information regarding effects found not to be significant is the same as discussed in 

the UCSF Medical Center at Mission Bay EIR (pp. 5‐4 to 5‐5), which is hereby incorporated by 

reference.  The exception is that greenhouse gas emissions were determined in the MCMB EIR to 

be less than significant.  This SEIR found that greenhouse gas emissions of the modified project 

would result in a significant impact, but the impact would be mitigated to a less than significant 

level with the implementation of specified mitigation measures. 

5.5  SIGNIFICANT IRREVERSIBLE ENVIRONMENTAL CHANGES 

THAT WOULD BE CAUSED BY THE PROPOSED PROJECT 

Information regarding significant irreversible environmental changes caused by the Medical 

Center project is the same as discussed in the UCSF Medical Center at Mission Bay EIR (pp. 5‐4 

Page 65: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 61 of 74 

 

to 5‐5), which is hereby incorporated by reference.  The modified project does not affect the 

analysis.

Page 66: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 62 of 74 

CHAPTER 6 ALTERNATIVES 

6.1  ALTERNATIVES TO THE PROJECT 

The California Environmental Quality Act (CEQA) requires an evaluation of the comparative 

effects of a range of reasonable alternatives that would attain most of the basic objectives of the 

proposed project and avoid or substantially lessen one or more of the significant adverse effects 

of the proposed project, including alternatives that are more costly or could otherwise impede to 

some degree the attainment of the project’s objectives. 

The LRDP Amendment #2 – Hospital Replacement EIR, evaluated at an equal level of detail a 

number of hospital replacement scenarios at Mission Bay and Parnassus Heights that, for 

purposes of CEQA, were alternatives to one another.  These project scenarios include a 250‐bed 

and 400‐bed scenario at the Mission Bay campus site (Mission Bay North and South sites); a 650‐

bed scenario at the Mission Bay campus site (Mission Bay South site); and a 250‐bed and 400‐bed 

scenario at the Parnassus Heights campus site (Parnassus East and West sites).  In addition, the 

LRDP Amendment #2 EIR evaluated two No Project alternatives, and an Off‐Site Alternative at 

the Mount Zion South Block. The Medical Center at Mission Bay EIR added an Off‐Site Helipad 

alternative, a No Helipad alternative, and a 4th Street Closed to Through Traffic (No 4th Street) 

alternative.  The modified project would not affect the conclusions of the alternatives analyses, 

including the 4th Street Closed to Through Traffic (No 4th Street) Alternative.  However, in light of 

the new greenhouse gas emissions significance standards and the significant impact of the 

modified project, this SEIR considers two additional alternatives: 

No Project Alternative 

Reduced Project Alternative 

 

6.1.2  NO PROJECT ALTERNATIVE 

CEQA requires that a “No Project” alternative be considered.  Under this alternative, the UCSF 

Medical Center at Mission Bay would be developed as proposed except that the garage would 

not be constructed.  The 442‐parking space surface lots, which have been approved, would be 

constructed as planned.     

This alternative would not meet any of the project objectives. 

Page 67: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 63 of 74 

 

Greenhouse Gas Emissions 

With the proposed project, impacts on greenhouse gas emissions would be significant, but would 

be reduced to less than significant levels with mitigation. While the No Project Alternative would 

mean no parking structure would be provided, it is still anticipated that a substantial number of 

patients, visitors, and employees would need to drive to the site.  These persons would search for 

on‐street parking or off‐street parking in nearby parking facilities, if available.  Because this 

alternative eliminates the proposed garage but not necessarily those who would continue to 

drive, some amount of greenhouse gas emissions would still be expected under this alternative.  

It is likely that the amount of greenhouse gas emissions would be significant, as with the 

modified project, but those emissions could be reduced to less‐than‐significant levels with the 

implementation of the energy efficiency projects identified as mitigation for the modified project. 

Transportation 

The proposed project would result in less than significant impacts on traffic, as would the No 

Project Alternative.  Without a garage on the Medical Center at Mission Bay site, more drivers 

may search for parking in the vicinity, thus more traffic may occur in the surrounding 

neighborhood than with the proposed project.  However, traffic impacts under the No Project 

Alternative would be less than significant. 

Summary 

The No Project alternative would avoid most of the impacts of the proposed project, but would 

not meet any of the project objectives.  Some amount of greenhouse gas emissions would 

continue as some patients, visitors and employees would continue to drive to the site and search 

for parking in the vicinity.  However, greenhouse gas emissions could be mitigated to less than 

significant levels, as with the project.   

6.1.3  REDUCED PROJECT ALTERNATIVE 

Under the Reduced Project Alternative, the number of parking spaces would be reduced to 

approximately one‐half the number of spaces, or about 300 spaces.  The number of parking 

spaces within the surface parking lots, which have been approved, would remain the same at 442 

spaces. 

This alternative would meet the project objectives to (1) ensure that development is compatible 

with and responsive to building scale and character in the surrounding areas; and (2) provide a 

parking structure that incorporates sustainability features to the greatest extent feasible. 

This alternative would only satisfy a portion of the expected parking demand by patients, 

visitors, and staff, and therefore would only partially meet the project objectives to (1) develop a 

patient‐friendly hospital (convenient location, availability of parking, efficient patient/emergency 

access, proximity of related patient service, etc.); (2) develop a staff‐friendly hospital (availability 

of parking, proximity to amenities, loading/delivery access, etc.); (3) support UCSF’s mission of 

Page 68: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 64 of 74 

 

patient care by enhancing access to UCSF facilities through convenient, affordable parking for 

those who often cannot utilize alternative forms of transportation; (4) provide parking for those 

essential healthcare providers for whom alternative forms of transportation is infeasible due to 

atypical work hours and responsibilities at multiple campus sites; and (5) avoid pressure on 

neighborhood on‐street parking. 

Greenhouse Gas Emissions 

With the proposed project, impacts on greenhouse gas emissions would be significant, but would 

be reduced to less than significant levels with mitigation. The Reduced Project Alternative would 

likely result in significant greenhouse gas emissions that could be reduced to less than significant 

levels with mitigation, similar to the proposed project.   

Transportation 

The proposed project would result in less than significant impacts on traffic, as would the 

Reduced Project Alternative.   With fewer parking spaces on the Medical Center at Mission Bay 

site, more drivers may search for parking in the vicinity, thus more traffic may occur in the 

surrounding neighborhood than with the proposed project.  However, traffic impacts under the 

Reduced Project Alternative would be less than significant. 

Summary 

The Reduced Project alternative would avoid most of the impacts of the proposed project, but 

would meet only two of the seven project objectives.  Some amount of greenhouse gas emissions 

would continue as some patients, visitors and employees would continue to drive to the site and 

search for parking in the vicinity.  However, greenhouse gas emissions could be reduced to less 

than significant levels with mitigation, as with the project.   

6.1.4  ENVIRONMENTALLY SUPERIOR ALTERNATIVE 

An EIR is required to identify the environmentally superior alternative—that is, the alternative 

having the fewest significant environmental impacts—from among the alternatives evaluated.  

The environmentally superior alternative among those evaluated within this SEIR is the No 

Project Alternative. Other than the No Project Alternative, the remaining alternative, the 

Reduced Project Alternative, is the environmentally superior alternative.

Page 69: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 65 of 74 

CHAPTER 7 REPORT PREPARATION 

7.1  REPORT AUTHORS 

LEAD AGENCY 

The University of California 

  Susan Desmond‐Hellmann, MD, MPH, Chancellor   Arthur and Toni Rembe Rock Distinguished Professor   University of California, San Francisco  

AUTHORS 

University of California, San Francisco 

  John Plotts, Senior Vice Chancellor, Finance and Administration   Lori Yamauchi, Assistant Vice Chancellor   Kevin Beauchamp, Director, Physical Planning   Diane Wong, Senior Planner   Tammy Chan, Senior Planner   Paul Franke, Assistant Planner  

University of California, Office of the President 

Charlotte Strem, Director, Physical & Environmental Planning 

Mary O’Keefe, Senior Planner 

 

University of California, Office of General Counsel   Elisabeth Gunther, University Counsel  Legal Counsel   Charles Olson, Esq., Sanger & Olson  

CONSULTANTS 

Transportation José Farrán, P.E., Principal Transportation Engineer, Adavant Consulting  

Wind   Charles Bennett, Environmental Science Associates    

Page 70: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 66 of 74 

CHAPTER 8 COMMENTS AND RESPONSES 

8.1  OVERVIEW 

This chapter documents public comments on the Draft Supplemental EIR prepared for the proposed 

project, and the responses to comments.  The public comment period was from February 25, 2011 to 

April 11, 2011.  In addition, a public hearing was held on the UCSF Mission Bay campus site on March 

28, 2011, at which the public was given the opportunity to provide oral testimony.  No public 

comments were submitted by the close of the public comment period, and there was no oral testimony 

at the public hearing.  

8.2  PUBLIC HEARING TRANSCRIPT 

A copy of the transcript of the March 28, 2011 public hearing on the Draft EIR follows. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 71: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417

University of California, San Francisco Mission Bay Campus 600 16th Street

Genentech Hall Auditorium San Francisco, CA

Public Meeting Re:

Draft Supplemental Environmental Impact Report

for the UCSF Medical Center at Mission Bay Phase I Garage

Monday, March 28, 2011

7:00 P.M.

Reported by Tahsha Sanbrailo

Page 72: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417

2

APPEARANCES

Present:

Lori Yamauchi Assistant Vice Chancellor, Campus Planning

1

Page 73: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417

3

P R O C E E D I N G S 1

MARCH 28, 2011 7:05 P.M. 2

Item 1 Welcome and Meeting Purpose. 3

MS. YAMAUCHI: Good evening. My name is Lori 4

Yamauchi, I am the Assistant Vice Chancellor, Campus 5

Planning, for the University of California, San Francisco. 6

I will be the Hearing Officer for tonight’s public hearing 7

on the Draft Supplemental Environmental Impact Report, or 8

Draft SEIR for the UCSF Medical Center Mission Bay Phase 1 9

Garage. 10

The primary purpose of this hearing is to receive 11

public testimony and evidence regarding the adequacy of the 12

Environmental Review for the proposed project. This is not 13

a hearing on the proposed project, itself. We have held 14

several community meetings regarding the project where we 15

received comments about the garage, the design, and about 16

parking, in general. 17

Tonight’s hearing is being conducted pursuant to 18

the University of California’s procedures for implementation 19

of the California Environmental Quality Act, or CEQA. 20

Public Notice regarding this hearing and the availability of 21

the Draft EIR included advertisements in the San Francisco 22

Examiner, postcard mailing to adjacent property owners, two 23

email notifications to a Listserv of about 500 people and 24

organizations, and posting on the Campus Planning Website, 25

Page 74: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417

4

Community Relations Website, and UCSF Events Calendar. 1

This hearing will be transcribed by a Reporter. A 2

complete transcript of this proceeding, as well as all 3

written comments received during the SEIR’s public review 4

period, will be included in and responded to in the Final 5

SEIR. All comments will be presented to the UCSF Chancellor 6

for review before considering the certification of the Final 7

SEIR. 8

If you do not wish to speak tonight, you may 9

submit written comments, which are given equal weight, with 10

oral remarks. Written comment sheets are available on the 11

table if you would like to use them outside in the back. 12

You may also supplement any oral testimony given tonight 13

with additional written material. 14

I would like to note that all comments must be 15

received by the close of the public review period on Monday, 16

April 11th, 2011, at 5:00 p.m. in order to be considered as 17

part of the record. Correspondence should be sent to Diane 18

Wong, Campus Planning, 654 Minnesota Street, San Francisco, 19

California 94143-0286. 20

Regarding the hearing tonight, if you would like 21

to speak and have not already signed up, please fill out a 22

speaker card now and return it to the staff. In order for 23

your testimony to be accurately recorded, and so that we may 24

respond accurately in the Final SEIR, please come forward 25

Page 75: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417

5

when called and use the microphone. As you begin your 1

remarks, please spell your name for the Reporter and 2

indicate the name of any organization you represent. 3

Because the purpose of this hearing is to receive testimony 4

and evidence for the Chancellor to consider, UCSF staff will 5

not attempt to respond to the testimony this evening, nor 6

engage in a dialogue with the public; however, I will be 7

happy to answer any procedural questions about the hearing. 8

Are there any questions that have not been 9

addressed by my comments? If not, is there anyone here who 10

wishes to speak on the SEIR? If not, then I will close the 11

public hearing and thank everyone for coming. 12

-oOo- 13

[Public Hearing Adjourned.] 14

15

16

17

18

19

20

21

22

23

24

25

Page 76: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning
Page 77: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Page 73 of 74 

 

CHAPTER 9 MITIGATION MONITORING and REPORTING PROGRAM 

9.1  OVERVIEW 

The California Environmental Quality Act (CEQA) requires that a Lead Agency establish a 

program to monitor and report on mitigation measures adopted as part of the environmental 

review process to avoid or reduce the severity and magnitude of potentially significant 

environmental impacts associated with project implementation. CEQA (Public Resources Code 

Section 21081.6 (a)(1)) requires that a Mitigation Monitoring and Reporting Program (MMRP) be 

adopted at the time that the agency determines to carry out a project for which an EIR has been 

prepared, to ensure that mitigation measures identified in the EIR are fully implemented. 

The MMRP for the Medical Center at Mission Bay ‐‐ Phase 1 Garage project is presented in the 

following table, which includes the full text of project‐specific mitigation measures identified in 

the Final EIR. The MMRP includes the mitigation measures adopted as part of the UCSF Medical 

Center at Mission Bay project that are included as part of the Phase 1 Garage project, as well as 

the LRDP Amendment #2 mitigation measures that are applicable to the project. The MMRP 

describes implementation and monitoring procedures, responsibilities, and timing for each 

mitigation measure identified in the EIR, including: 

Significant Impact: Identifies the Impact Number and statement from the Final EIR. 

MitigationMeasure: Provides full text of the mitigation measure as provided in the Final EIR. 

Implementation:  Summarizes the steps to be taken to implement the measure. 

Responsible Unit: Designates responsibility for implementation of the mitigation measure. 

Report Mechanism:  Specifies procedures for documenting and reporting mitigation 

implementation. 

Consistent with UC policy, UCSF may modify the means by which a mitigation measure will be 

implemented, as long as the alternative means ensure compliance during project 

implementation. The responsibilities of mitigation implementation, monitoring and reporting 

extend to several UCSF departments and offices. The manager or department lead of the 

identified unit or department will be directly responsible for ensuring the responsible party 

complies with the mitigation. The UCSF Campus Planning Department is responsible for the 

overall administration of the program and for assisting relevant departments and project 

Page 78: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay Supplemental EIR 

Phase 1 Garage

Page 74 of 74 

 

managers in their oversight and reporting responsibilities. The Department is also responsible for 

ensuring the relevant parties understand their charge and complete the required procedures 

accurately and on schedule. 

Page 79: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF Medical Center at Mission Bay – Phase 1 Garage SEIR 1

MITIGATION MONITORING AND REPORTING PROGRAM  

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE  

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

MITIGATION MEASURES NEWLY IDENTIFIED IN THE SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY PHASE 1 GARAGE 

4.1  GREENHOUSE GAS EMISSIONS ‐ OPERATIONS 

GHG‐1: Project development 

would generate greenhouse gas 

emissions, either directly or 

indirectly, that could have a 

significant impact on the 

environment. 

The Regents has approved funding 

for the 2010 Statewide Energy 

Partnership Program / UC Strategic 

Energy Plan.  UCSF would mitigate 

at least 2,700 MtCO2e ongoing 

reductions per year, e.g. the 

additional significant GHG emissions 

associated with the proposed garage 

project, with the appropriate number 

of energy efficiency projects 

identified on the list in Supplemental 

EIR Appendix C.  Projects identified 

in Appendix C are those projects that 

are included in the funded, UC 

Strategic Energy Plan and that are 

planned to be implemented by 2012, 

around the time garage operations 

would begin. 

Complete appropriate number of 

energy efficiency projects included in 

the 2010 Statewide Energy 

Partnership Program / UC Strategic 

Energy Plan to mitigate at least 2,700 

MtCO2e ongoing reductions per 

year. 

 

UCSF Facilities 

Management and/or 

UCSF Medical Center  

UCSF Campus Planning to monitor 

implementation of energy efficiency 

projects and document completion to 

verify mitigation of impact. 

Page 80: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 2

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

MITIGATION MEASURES IDENTIFIED IN THE UCSF MEDICAL CENTER AT MISSION BAY EIR THAT ARE APPLICABLE TO THE PHASE 1 GARAGE 

PROJECT  

4.2  AIR QUALITY 

MCMB.2‐1: Demolition and 

construction activities 

associated with the Medical 

Center at Mission Bay project 

would generate fugitive dust 

and criteria pollutant emissions 

that could adversely affect local 

air quality. 

To further mitigate less‐than‐

significant project‐level impacts, 

additional measures related to the 

2007 CARB off‐road diesel rule on 

equipment exhaust emissions from 

construction equipment shall be 

required in UCSF construction 

contracts to comply with the 

following measures: 

Prohibit the use of conventional cutback asphalt for paving to 

restrict the maximum VOC content 

of asphalt emulsion. Diesel 

portable generators less than 50 

horsepower shall not be allowed at 

the construction site, except for 

those used by welders.  

All diesel‐fueled engines used for on‐ and offsite construction 

activities shall be fueled only with 

ultralow sulfur diesel, which 

contains no more than 15 ppm 

sulfur. 

All construction diesel engines used for on‐ and offsite activities 

that have a rating of 100 hp or 

more shall meet, at a minimum, 

the Tier 2 California Emission 

Standards for Off‐Road 

Compression‐Ignition Engines as 

Issue instructions in each bid 

package of each construction project 

for contractors to incorporate the 

mitigation.  The successful contractor 

will prepare a construction air 

pollution control strategy to report 

on the implementation of the 

mitigation measure. 

Project Manager, 

Medical Center Design 

and Construction Team, 

or Capital Programs 

Facilities Management, 

as appropriate. 

Provide written verification in report 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provision for construction air 

pollution control.  Provide a report on 

construction air pollution control 

strategies and implementation and 

report to Monitor upon request; but 

no less than quarterly after beginning 

each construction phase. 

Page 81: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 3

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

specified in California Code of 

Regulations, Title 13, section 

2423(b)(1) unless it is certified by 

the construction contractor that 

such engine is not available for a 

particular item of equipment. In 

the event a Tier 2 engine is not 

available for any off‐road engine 

larger than 100 hp, that engine 

shall be a Tier 1 engine. In the 

event a Tier 1 or Tier 2 engine is 

not available for any offroad 

engine larger than 100 hp, that 

engine shall be equipped with a 

CARB Level 3‐verified diesel 

emission control device (e.g., 

catalyzed diesel particulate filter), 

unless the engine manufacturer or 

the construction contractor 

certifies that the use of such 

devices is not practical for specific 

engine types. In the event that a 

CARB Level 3 verified diesel 

emission control device is not 

practical for the specific engine 

type, then the engine shall be 

equipped with a CARB Level 1‐ or 

2‐verified control device (e.g., 

diesel oxidation catalyst), unless 

the engine manufacturer or the 

construction contractor certifies 

that such devices are not available 

for the engine in question. For 

purposes of this condition, the use 

of such devices is “not practical” 

if, among other reasons: 

Page 82: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 4

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

1. The construction equipment is 

intended to be onsite for ten 

(10) days or less. 

2. The use of the diesel emission 

control device is excessively 

reducing normal availability of 

the construction equipment 

due to increased downtime for 

maintenance, and/or reduced 

power output due to an 

excessive increase in 

backpressure. 

3. The diesel emission control 

device is causing or is 

reasonably expected to cause 

significant engine damage. 

In the event that the use of a diesel 

emission control device is to be 

terminated, the construction 

contractor shall be required to 

inform the UCSF project manager 

within 10 days prior to such 

termination. 

Construction equipment shall be 

properly tuned and maintained in 

accordance with manufacturers’ 

specifications. 

Best management construction 

practices shall be used to avoid (or 

limit) unnecessary emissions (e.g., 

trucks and vehicles in loading and 

unloading queues would turn their 

engines off when not in use, and to 

Page 83: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 5

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

the extent practical, all diesel 

heavy construction equipment 

shall not remain running at idle for 

more than five minutes) 

Use alternative fueled equipment 

when feasible (such as ULSD, 

CNG, biodiesel, water emulsion 

fuel, and electric). The 

construction contracts shall require 

each contractor and subcontractor 

to consider this measure and adopt 

it for their work unless they can 

demonstrate to UCSF the 

inapplicability or infeasibility of 

the measure to their specific work, 

or can provide mitigation 

measures with equivalent or better 

effectiveness. This information 

shall be reported as part of the 

Mitigation Monitoring Reporting 

and Compliance Program. 

Use on‐site power when feasible to 

reduce reliance on portable 

generators. The construction 

contracts shall require each 

contractor and subcontractor to 

consider this measure and adopt it 

for their work unless they can 

demonstrate to UCSF the 

inapplicability or infeasibility of 

the measure to their specific work, 

or can provide mitigation 

measures with equivalent or better 

effectiveness. This information 

shall be reported as part of the 

Page 84: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 6

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

Mitigation Monitoring Reporting 

and Compliance Program. 

4.5  NOISE         

MCMB.5‐1: Demolition and 

construction activities 

associated with the proposed 

project would elevate noise 

levels in and around the project 

site, and particularly at nearby 

sensitive receptors. 

UCSF shall require construction 

contractors to minimize unavoidable 

construction noise impacts by use of 

proper equipment and work 

scheduling:  

Limit construction hours to the 

following schedule. [Monday 

through Friday, 7 a.m. to 5 p.m. for 

“Not Noisy” work; and Monday 

through Friday 8 a.m. to 5 p.m. for 

Noisy work] Approve extended 

hours [Monday through Friday, 5 

p.m. to 8 p.m.; Saturday 7 a.m. to 8 

p.m.; and Sunday 8 a.m. to 4:30 

p.m.] only with advanced notice 

from the UCSF project manager. 

Prohibit high impact noise on 

Saturdays and Sundays. 

Issue instructions in each bid 

package of each construction project 

for contractors to incorporate the 

mitigation.  The successful contractor 

will prepare a construction noise 

impact abatement plan to report on 

the implementation of the mitigation 

measure. 

Project Manager, 

Medical Center Design 

and Construction Team, 

or Capital Programs 

Facilities Management, 

as appropriate 

Provide written verification in report 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provisions for construction 

noise abatement (including limitations 

on construction hours).  Provide a 

report on construction noise 

abatement to Monitor upon request; 

but no less than quarterly after 

beginning each construction activity. 

  Designate a UCSF Community 

Contact to receive and resolve 

construction complaints. 

Designate a UCSF Community 

Contact to receive and resolve 

construction noise complaints. 

UCSF Community 

Relations 

Provide written verification to the 

Monitor within 10 working days of the 

first contract bid identifying the UCSF 

Community Contact and contact 

information. 

4.6  TRANSPORTATION AND TRAFFIC 

MCMB.6‐3: Operation of the 

Medical Center at Mission Bay 

project would increase traffic at 

intersections on the adjacent 

roadway network in the Future 

Phase. 

Regarding Owens Street at the 

Center Garage Access, UCSF would 

conduct project‐level CEQA review 

at the time the Future Phase 

development is considered for 

approval. In addition, UCSF would 

Conduct project‐level CEQA review 

for Future Phase development.  

Coordinate with the City of San 

Francisco in the periodic update of 

the Mission Bay traffic triggers 

survey.  Monitor on‐site parking 

UCSF Campus Planning  Prepare memo to Monitor within 10 

days of preparation of Project 

Planning Guide (PPG) for Future 

Phase development that project‐level 

CEQA review for Future Phase 

development will be prepared. 

Page 85: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 7

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

coordinate with the City of San 

Francisco in the periodic update of 

the Mission Bay traffic triggers 

survey and would monitor on‐site 

parking access and circulation in 

order to determine the need for LOS 

improvements on Owens Street 

between 16th and Mariposa Streets. 

UCSF would coordinate with the 

Municipal Transportation Agency 

(which includes the Department of 

Parking and Traffic) and the 

Planning Department to confirm the 

feasibility and effectiveness of 

mitigation measures resulting from 

future analysis or consider 

equivalent recommendations made 

by these agencies, and UCSF will pay 

its fair share of the cost of 

implementing the selected 

mitigation. 

access and circulation in order to 

determine the need for LOS 

improvements on Owens Street 

between 16th and Mariposa Streets.  

Coordinate with the Municipal 

Transportation Agency (including 

the Department of Parking and 

Traffic) and the Planning Department 

to confirm the feasibility and 

effectiveness of mitigation measures 

resulting from future analysis or 

consider equivalent 

recommendations made by these 

agencies.  Pay for fair share of the 

cost of implementing selected 

mitigation. 

Following project‐level CEQA review 

for Future Phase development, 

prepare additional memo to Monitor 

describing status of LOS 

improvements on Owens Street 

between 16th and Mariposa, 

coordination efforts with the City to 

confirm the feasibility, acceptability 

and effectiveness of mitigation 

measures, and status of fair share 

payments for cost of implementing 

selected mitigation. 

MITIGATION MEASURES CARRIED FORWARD FROM THE UCSF LRDP AMENDMENT #2 – HOSPITAL REPLACEMENT EIR 

4.1.  AESTHETICS         

4.1‐1:  New hospital 

development at any of the sites 

could increase light and glare 

which could affect nighttime 

views at the selected site and in 

its vicinity. 

Minimize light and glare from new 

hospital development through the 

orientation of buildings, use of 

landscaping materials, and choice of 

primary facade materials.  Design 

standards and guidelines to minimize 

light and glare would be adopted for 

the new hospital development, 

including: 

Reflective metal walls and mirrored 

Issue instruction in each bid package 

of each architectural services contract 

for architects and design 

professionals to incorporate the 

mitigation as design criteria. 

Working with the project and 

construction managers, require 

architects and design professionals to 

document how siting and design 

measures are addressed and 

Medical Center Design 

and Construction Team, 

Project Manager. 

Provide written verification in report 

form to Monitor within 10 working 

days of each contract bid on each 

phase.  Report will certify that selected 

bids utilize design elements which 

maximize compliance with design 

criteria.  

(Status:  facade materials and 

landscaping incorporated into the 

MCMB Phase I Garage project design 

Page 86: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 8

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

glass walls shall not be used as 

primary building materials for 

facades. 

Installation of illuminated building 

signage shall strive to be consistent 

with City Planning Code sign 

requirements and/or Mission Bay 

design guidelines. 

Exterior light fixtures shall be 

configured to emphasize close spacing 

and lower intensity light.  Light 

fixtures shall use luminaries that 

direct the cone of light downward.  

(Modified from LRDP FEIR Mitigation 

Measure 12LI‐3 for the LRDP and 

Future Phases) 

incorporated.  Review design plans 

for each new proposed structure to 

ensure that such features have been 

incorporated in the design to address 

light/glare impacts. 

minimize light and glare impacts.  

Exterior light fixtures have been 

designed to be directed downward.)  

4.1‐2:  Construction of a new 

hospital could result in flood 

lighting at any of the sites 

during nighttime construction 

activities. 

UCSF would require a condition in 

construction contracts that flood or 

area lighting for construction 

activities be placed and directed so 

as to avoid potential disturbances to 

adjacent residences or other uses.  

(Modified from LRDP Mitigation 

Measure 12L1‐4 for the LRDP and 

Future Phases) 

Issue instructions in each bid 

package of each architectural services 

contract for architects and design 

professionals to incorporate the 

mitigation as design criteria. 

Working with the project and 

construction managers, require 

contractors to document how siting 

and construction lighting measures 

are incorporated.  Review 

construction documentation to 

ensure that mitigation is included to 

address lighting effects. 

Medical Center Design 

and Construction Team, 

Project Manager. 

Provide written verification in report 

form to Monitor within 10 working 

days of each contract bid on each 

phase.  Report will certify that selected 

bids utilize design elements which 

maximize compliance with design 

criteria. 

 

Page 87: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 9

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

4.1‐4:  Construction and 

operation of a hospital at the 

Mission Bay South site could 

substantially degrade the visual 

quality of the Mission Bay 

campus site or its 

surroundings. 

Extend to the CMPDG to the Mission 

Bay South site or develop Mission 

Bay South site land use designations 

and design guidelines that apply 

1996 LRDP goals and objectives for 

visual quality, protection of view 

corridors, creation of open space, and 

compatibility with the surrounding 

area.  Implementation of this 

measure would avoid a substantial 

degradation of the visual quality due 

to the Mission Bay South site 

development.  (Identified in the 

LRDP Amendment #2 EIR for the 

LRDP and Future Phases) 

Prior to or as part of project‐specific 

planning and design, develop design 

guidelines for the Mission Bay South 

site and adjacent blocks, as 

applicable.   

UCSF Campus Planning 

and Medical Center 

Design and Construction 

Team 

Issue new design guidelines with 

specific prescriptions for the Mission 

Bay South site and incorporate the site 

as appropriate into the revised 

CMPDG. 

(Status:  The Medical Center at 

Mission Bay, including the Phase 1 

Garage, is consistent with applicable 

guidelines of the CMPDG.  In 

addition, specific design standards for 

the Medical Center at Mission Bay 

were developed and identified in the 

Memorandum of Understanding 

between the University and the San 

Francisco Redevelopment Agency.) 

4.2  AIR QUALITY         

4.2‐1:  Construction and 

operation of replacement 

hospital facilities would 

generate vehicular, stationary 

source, and helicopter‐related 

emissions (depending on 

scenario) that would contribute 

to regional air pollution. 

UCSF shall continue its existing 

Transportation Demand 

Management programs to promote 

shuttle services, ride‐sharing, and 

bicycle programs to reduce the 

number of trips at its campus sites.  

These transit options divert trips 

from single occupancy vehicles and 

would thus reduce impacts of 

vehicular trips generated by the 

project.  (Modified from LRDP FEIR 

Mitigation Measures 12D4‐2 for the 

LRDP and Future Phase) 

Extend UCSF shuttle service to the 

project site; work to promote other 

TDM programs at the project site, 

such as pre‐tax transit passes and 

ride‐sharing; consider in parking 

plans allocations for vanpool, 

motorcycle, and bicycle parking. 

 UCSF Parking & 

Transportation Services 

in conjunction with 

UCSF Medical Center 

and Campus Planning 

 Provide written verification to 

Monitor regarding TDM programs 

considered and implemented. 

4.2‐2:  Demolition and 

construction activities 

associated with the hospital 

construction would generate 

fugitive dust and criteria 

During construction, UCSF shall 

require the construction contractor to 

implement the appropriate level of 

BAAQMD’s dust control procedures 

for all construction sites.  UCSF shall 

Issue instructions in each bid 

package of each construction project 

for contractors to incorporate the 

mitigation.  The successful contractor 

will prepare a construction air 

Project Manager, 

Medical Center Design 

and Construction Team. 

Provide written verification in report 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provisions for construction 

Page 88: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 10

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

pollutant emissions that could 

adversely affect local air 

quality. 

include this requirement in all 

construction contracts. This mitigates 

this impact to less than significant.  

(Modified from LRDP FEIR 

Mitigation Measure 12D1‐1 for the 

LRDP and Future Phase) 

pollution control strategy to report 

on the implementation of the 

mitigation measure. 

air pollution control.  Provide a report 

on construction air pollution control 

strategies and report to Monitor upon 

request; but no less than quarterly 

after beginning each construction 

activity. 

4.2‐5:  Vehicular traffic 

generated by construction and 

operation of a 400‐bed or 650‐

bed hospital and associated 

facilities, in conjunction with 

traffic generated from 

concurrent LRDP projects at 

each campus site, plus non‐

UCSF projects, would result in 

criteria pollutant emissions that 

would have a significant 

cumulative impact on the 

ambient air quality. 

Implement Mitigation Measure 4.2‐1.       

4.3  CULTURAL RESOURCES       

4.3‐1:  Building construction, 

including excavation and 

grading associated with the 

proposed project, could cause 

substantial adverse changes to 

archaeological resources at the 

project sites. 

If the discovery includes human 

remains, CEQA Guidelines 15064.5 

(e)(1) shall be followed: 

In the event of the accidental 

discovery or recognition of any 

human remains in any location other 

than a dedicated cemetery, the 

following steps should be taken: 

(1)  There shall be no further 

excavation or disturbance of the site 

or any nearby area reasonably 

suspected to overlie adjacent human 

remains until: 

Issue instructions in each bid 

package of each construction project 

for contractors to incorporate the 

mitigation.  The successful contractor 

will demonstrate knowledge of 

procedures and requirements when 

cultural resources are discovered 

during construction activities. 

UCSF Capital Projects 

Facilities Management 

Project Manager. 

Provide written verification in report 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provisions for mitigation if 

cultural resources are discovered 

during construction activities.  

Provide construction status report to 

Monitor upon request. 

Page 89: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 11

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

(A)  The coroner of the county in 

which the remains are discovered 

must be contacted to determine that 

no investigation of the cause of death 

is required, and 

(B)  If the coroner determines the 

remains to be Native American: 

(1) The coroner shall contact the 

Native American Heritage 

Commission within 24 hours.  (2) The 

Native American Heritage 

Commission shall identify the person 

or persons it believes to be the most 

likely descended from  the deceased 

Native American. (3) The most likely 

descendent may make 

recommendations to the landowner 

or the person responsible for the 

excavation work, for means of 

treating or disposing of, with 

appropriate dignity, the human 

remains and any associated grave 

goods as provided in Public 

Resources Code Section 5097.98, or  

(2)  Where the following conditions 

occur, the landowner or his 

authorized representative shall 

rebury the Native American human 

remains and associated grave goods 

with appropriate dignity on the 

property in a location not subject to 

further subsurface disturbance. 

(A)  The Native American Heritage 

Commission is unable to identify a 

Page 90: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 12

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

most likely descendent or the most 

likely descendent failed to make a 

recommendation within 24 hours 

after being notified by the 

commission. 

(B)  The descendant identified fails to 

make a recommendation; or  

(C)  The landowner or his authorized 

representative rejects the 

recommendation of the descendant, 

and the mediation by the Native 

American Heritage Commission fails 

to provide measures acceptable to 

the landowner.  (Identified in the 

LRDP Amendment #2 EIR for the 

LRDP and Future Phase) 

4.4  GEOLOGY AND SOILS         

4.4‐4:  In the event of a major 

earthquake in the region, 

seismic ground shaking could 

expose people and property to 

liquefaction and earthquake‐

induced settlement at Mission 

Bay. 

A site‐specific, design‐level 

geotechnical investigation shall be 

completed based on the proposed 

project design and shall provide 

engineering recommendations for 

mitigation of liquefiable soils, in 

accordance with the California 

Geological Survey’s  Geology 

Guidelines for Evaluating and 

Mitigating Seismic Hazards (CGS 

Special Publication 117, 1997).  These 

geotechnical recommendations shall 

be incorporated into the final design 

of the project.  (Identified in the 

LRDP Amendment #2 EIR for the 

LRDP Phase) 

Prepare a geotechnical survey and 

incorporate the results of the 

investigation into the project design 

to address impacts.  

UCSF Campus Planning, 

and Medical Center 

Design and Construction 

Team. 

Provide Medical Center Design and 

Construction Team final geotechnical 

investigation that reports feasible 

measures and incorporates them into 

project design.  

Page 91: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 13

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

4.5  HAZARDS AND HAZARDOUS MATERIALS       

4.5‐4:  Operation of the new 

hospital facilities would 

generate hazardous waste that 

could place an additional load 

on hazardous waste 

management facilities. 

UCSF shall implement hazardous 

waste handling, minimization, and 

disposal procedures at any chosen 

site for hospital replacement 

consistent with safety requirements 

and applicable laws and regulations. 

UCSF shall extend its existing 

hazardous waste minimization plan 

to include any chosen site for 

hospital replacement. 

UCSF shall implement the 

operational controls required to 

comply with laws and regulations, 

including, but not limited to, 

monthly safety and compliance 

audits and training of staff at any 

chosen site for hospital replacement.  

This would 1) allow efficient 

processing of wastes for shipment to 

treatment facilities or disposal, 

reducing the time that hazardous 

wastes are at a chosen hospital 

replacement site, and 2) ensure that 

safety controls such as OSHA 

training, correct practices and safety 

equipment are in place. 

At the new hospital facilities, UCSF 

will extend its program for 

hazardous waste handling, 

minimization and disposal, including 

implementation of all the measures 

identified in the mitigation measure. 

 In addition, in conjunction with bi‐

annual inspections of UCSF by the 

City and County of San Francisco 

Department of Public Health, and the 

Department of Health Services, 

Radiologic Health Branch, initiate a 

review by the Chemical Safety 

Officer and the Radiation Safety 

Officer (in consultation with the 

Chemical Safety Committee and the 

Radiation Safety Committee as 

required) of existing source reduction 

and management plans for 

additional measures that are feasible 

to implement at UCSF to minimize 

hazardous waste and dry long‐lived 

radioactive waste. 

Environmental Health & 

Safety, Chemical Safety 

Officer and Radiation 

Safety Officer. 

Notify Monitor when hazardous 

waste handling, minimization and 

disposal measures are extended to the 

new hospital facilities.  In addition, 

provide hazardous chemical waste 

and radioactive waste source 

reduction and management review to 

Monitor every other year as part of the 

bi‐annual Business Plan inspection 

and RHB inspection.  Report feasible 

measures to be implemented and 

timetable for such additional 

measures. 

UCSF shall implement procedures to 

minimize increases in the long‐lived 

radioactive waste generation.  

According to the California 

Department of Health Services 

Radiologic Health Branch, California, 

radiologic licenses should: 

Page 92: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 14

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

1) minimize the amount of low‐level 

radioactive waste in possession 

and avoid accumulating waste 

that cannot be disposed 

promptly; 

2) segregate for disposing radioactive wastes that are not 

subject to Southwestern Low‐

Level Radioactive Waste Disposal 

Compact regulations; 

3) segregate waste that can be 

disposed of or reduced in volume 

by approved treatment methods; 

4) segregate short‐lived radioactive waste for decay; 

5) consider recycling radioactive materials; 

6) consider extended on‐site storage of any remaining low‐level 

radioactive waste; and 

7) consider non‐radioactive substitutes. (Modified Measure 

from LRDP FEIR Mitigation 

Measure 12F1‐3)

4.5‐6:  Soil and groundwater 

contamination at the Mission 

Bay North and South sites 

could expose construction 

workers, the public, and the 

environment to hazards 

associated with soil and 

groundwater contamination. 

UCSF shall develop a RMP for Parcel 

X‐3 if it is acquired or extend the 

1999 RMP to Parcel X‐3, if feasible. 

The UCSF Office of Environmental 

Health & Safety will coordinate with 

the current land owner to prepare or 

contract for preparation of a 

complete site assessment and 

implementation of the identified 

mitigation measures.  Alternatively, 

UCSF could conduct the assessment 

Environmental Health & 

Safety, Asbestos / 

Hazardous Materials 

Removal Officer 

Provide copies of the assessment and 

remediation plans to Monitor for each 

project and phase.  Provide evidence 

from the Regulatory Agency of 

satisfactory completion of 

remediation. 

Page 93: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 15

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

and remediation itself in accordance 

with federal and state requirements. 

4.6  HYDROLOGY AND WATER QUALITY       

4.6‐3:  Construction of new 

hospital buildings at the 

Mission Bay North or South 

sites by the LRDP Phase or 

Future Phases could result in 

hydrology and water quality 

impacts at Mission Bay. 

UCSF shall adopt Mitigation 

Measures K.2, K.3 and K.4 of the 

Mission Bay Subsequent EIR as 

follows: 

K.2  Participate in the City’s existing 

Water Pollution Prevention Program. 

 Facilitate implementation of the 

City’s Water Pollution Prevention 

Program by providing and installing 

wastewater sampling ports in any 

building anticipated to have a 

potentially significant discharge of 

pollutants to the sanitary sewer, as 

determined by the Water Pollution 

Prevention Program of the San 

Francisco Public Utilities 

Commission’s Bureau of 

Environmental Regulation and 

Management, and in locations as 

determined by the Water Pollution 

Prevention Program. 

This mitigation measure could be 

implemented by including the Water 

Pollution Prevention Program in the 

review process, as each individual 

construction is proposed.  The Water 

Pollution Prevention Program would 

review each project, determine if one 

or more sampling ports should be 

installed in a particular building, and 

specify the location of the sampling 

Issue instructions in each bid 

package of each construction project 

for contractor to incorporate the 

mitigation measures. 

Medical Center Design 

and Construction Team 

Provide written verification in report 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provisions for mitigation 

measures.  Provide construction status 

report to Monitor upon request. 

Page 94: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 16

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

port(s). 

K.3  Design and construct sewer 

improvements such that potential 

flows to the City’s combined sewer 

system from the project do not 

contribute to an increase in the 

annual overflow volume as projected 

by the Bayside Planning Model by 

providing increased storage in 

oversized pipes, centralized storage 

facilities, smaller dispersed storage 

facilities, or detention basins, or 

through other means to reduce or 

delay stormwater discharges to the 

City system. 

K.4  Implement alternative 

technologies or use other means to 

reduce settleable solids and floatable 

materials in stormwater discharges to 

China Basin Channel to levels 

equivalent to, or better than, City‐

treated combined sewer overflows.  

Such alternatives technologies could 

include one or more of the following: 

 biofilter system, vortex sediment 

system, catch basin filters, and/or 

additional source control measures to 

remove particulates from streets and 

parking lots.  (Identified in the LRDP 

Amendment #2 EIR for the LRDP 

and Future Phase) 

 

4.8  NOISE       

4.8‐1:  The proposed Hospital  Mitigation Measure 4.8‐1:  UCSF  Issue instructions in each bid  Capital Projects Facilities  Provide written verification in report 

Page 95: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 17

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

Replacement Program would 

result in noise associated with 

demolition and construction 

activities. 

shall require construction contractors 

to minimize unavoidable 

construction noise impacts by use of 

proper equipment and work 

scheduling: 

Limit construction hours to between 

7:00 a.m. and 8:00 p.m. on weekdays 

and 9:00 a.m. to 5:00 p.m. on 

weekends.  Approve extended hours 

only with advanced notice from 

UCSF project manager. Prohibit high 

impact noise on Sundays. 

[Superceded by Mitigation Measure 

MCMB.5‐1] 

 Require use of construction 

equipment with noise reduction 

devices (i.e., mufflers in good 

working order). 

Erect temporary noise walls to 

protect adjacent noise‐sensitive areas. 

 Use of impact tools would be 

minimized to the extent feasible. 

Implement “quiet” pile‐driving 

technology (such as pre‐drilling of 

piles, and/or the use of more than 

one pile driver to shorten the total 

pile‐driving duration), where 

feasible, in consideration of 

geotechnical and structural 

requirements and conditions. 

Locate stationary noise sources away 

from residential or other sensitive‐

receptor areas, and require use of 

acoustic shielding with such 

package of each construction project 

for contractors to incorporate the 

mitigation.  The successful contractor 

will prepare a construction noise 

impact abatement plan to report on 

the implementation of the mitigation 

measure. 

Management or Medical 

Center Design and 

Construction Team, as 

appropriate 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provisions for construction 

noise abatement.  Provide a report on 

noise abatement to Monitor upon 

request; but no less than quarterly 

after beginning each construction 

activity. 

 

Page 96: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 18

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

equipment when feasible and 

appropriate. 

(Modified measure from LRDP FEIR 

Mitigation Measure 12E1‐1) 

4.8‐2:  Operational activities 

and mechanical equipment 

would increase noise levels at 

sensitive receptors. 

UCSF shall incorporate standard 

industrial noise control measures for 

stationary equipment at any site 

chosen for hospital replacement.  

UCSF shall also adopt noise 

performance standards to ensure that 

operational noise from UCSF sources 

would not exceed noise guidelines 

set forth in local General Plans or 

ordinances for adjacent areas based 

on use standards.  If ambient noise 

levels in areas adjacent to the site(s)’ 

proposed for hospital replacement 

already exceed local noise standards, 

UCSF shall not increase average 

daily noise levels (Ldn) from 

operational noise sources by 3 or 

more dBA at the property line.  USCF 

shall use standard design features 

including installation of relatively 

quiet models, orientation or 

shielding to protect sensitive uses, 

and installation within enclosures 

when necessary to reduce noise.  

(Modified measure from LRDP FEIR 

Mitigation Measure 12E1‐2)  

All contractors and design 

professionals responsible for 

selecting mechanical equipment will 

be required to perform noise 

calculations based on mechanical 

equipment specifications of the 

vendor or measure equipment noise 

levels at the nearest property line to 

ensure the selected equipment meets 

the criteria.  If the projected 

equipment noise levels exceed Noise 

Ordinance specifications, the 

contractor or design professional will 

be required to implement additional 

measures, to ensure that the 

standards are met, and re‐monitor. 

Medical Center Design 

and Construction Team, 

Project Manager. 

Provide written verification to the 

Monitor of the inclusion of the 

performance standards and conduct 

final monitoring as required. 

4.8‐7:  Site‐specific construction 

and demolition activities at 

each campus site would have a 

local, significant cumulative 

impact on the local noise 

Implement Mitigation Measure 4.8‐1.       

Page 97: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 19

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

environment. 

4.11 TRANSPORTATION       

4.11‐1:  Building construction, 

including demolition, 

excavation, and grading 

associated with the proposed 

LRDP Amendment could cause 

substantial adverse impacts to 

traffic flow, circulation and 

access as well as to transit, 

pedestrian, and parking 

conditions. 

Mitigation 4.11‐1:  To assure that 

construction and/or demolition 

activities minimize parking demand 

and circulation obstruction, UCSF 

shall require construction and/or 

demolition contractors to develop 

and implement construction traffic 

and parking management plans 

during demolition and/or 

construction activities at all campus 

sites.  The plans would be expected 

to include measures such as the 

following:   

Develop a traffic management plan 

in consultation with the San 

Francisco DPT and Muni to minimize 

disruption due to lane closures.  The 

plan should be consistent with the 

Regulations for Working in San 

Francisco Streets and Chapter 6 of 

the California Supplement to the 

Manual of Uniform Traffic Control 

Devices. 

Prepare an offsite parking plan for 

construction employees and 

subcontractor employees.  An 

alternative plan would provide 

shuttle service to/from designated 

remote parking lots and/or public 

transportation transfer nodes.  This 

plan would be incorporated into the 

construction contract between UCSF 

Issue instructions in each bid 

package of each construction project 

for contractors to incorporate the 

mitigation.  Require the successful 

contractor to prepare a construction 

traffic and circulation plan for each 

new proposed construction project to 

report on the implementation of the 

mitigation measure. 

Medical Center Design 

and Construction Team, 

Capital Projects Facilities 

Management, as 

appropriate. 

Provide written verification in report 

form to the Monitor within 10 

working days of each contract bid on 

each phase to certify that selected bid 

includes provisions for a construction 

traffic and circulation plan.  Provide a 

construction traffic and circulation 

plan implementation report to 

Monitor upon request; but no less 

than quarterly after beginning each 

construction activity. 

Page 98: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 20

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

and the contractor. 

Schedule heavy‐truck deliveries with 

the construction project manager at 

least one day in advance. 

Whenever possible, make deliveries 

using trucks of 40 feet maximum 

bumper‐to‐bumper length. 

Whenever possible schedule heavy 

trucks deliveries to arrive at off‐peak 

hours, outside of 7:00 a.m. to 9:00 

a.m. and 4:00 p.m. to 6:00 p.m. 

Note any deliveries that cannot 

comply with the above requirements 

for heavy trucks on the schedule, and 

notify the UCSF construction project 

manager at least 48 hours in advance. 

 The contractor may provide flagmen 

to direct traffic in those cases.  

(Identified in the LRDP Amendment 

#2 EIR for the LRDP and Future 

Phases) 

4.11‐2:  Operation of a hospital 

at the Mission Bay North or 

South sites would increase 

traffic at intersections on the 

adjacent roadway network. 

See below.       

4.11‐2a:  Operation of a hospital 

at the Mission Bay South site 

would increase average delay 

per vehicle during the p.m. 

peak hour at the intersection of 

16th Street / Owens Street. 

UCSF shall coordinate with the City 

of San Francisco to provide the 

following lane configuration for the 

southbound approach on Owens 

Street at the intersection of 16th 

Street / Owens Street:  one 

southbound shared through‐left‐turn 

Work with appropriate City 

Departments on lane configuration at 

this intersection to achieve acceptable 

level of service, or develop other 

mitigation measures that are equally 

effective and acceptable to the City. 

Vice Chancellor ‐ 

University Advancement 

& Planning, Campus 

Planning, Government 

Relations. 

 

Report coordination efforts to Monitor 

and provide documentation 

confirming lane configuration has 

been approved by City and 

implemented. 

Page 99: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

MITIGATION MONITORING AND REPORTING PROGRAM (Continued) 

SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE 

UCSF Medical Center at Mission Bay – Phase I Garage SEIR 21

Significant Impact  Mitigation Measure  Implementation  Responsible Unit  Report Mechanism 

lane, one southbound through‐lane, 

and one southbound exclusive right‐

turn lane.  (Identified in the LRDP 

Amendment #2 EIR for the Future 

Phase) 

4.11‐2b:  Operation of a hospital 

at the Mission Bay South site 

would increase average delay 

per vehicle during the p.m. 

peak hour at the intersection of 

Mariposa Street / 3rd Street. 

UCSF shall coordinate with the City 

and County of San Francisco to 

provide an additional southbound 

exclusive right‐turn lane of a 

minimum 50‐foot length on 3rd 

Street at the intersection of Mariposa 

Street / 3rd Street.  (Identified in the 

LRDP Amendment #2 EIR for Future 

Phase) 

Work with appropriate City 

Departments to get Board of 

Supervisor approval for the 

dedication of land that would be 

required for the lane, or develop 

other mitigation measures that are 

equally effective and acceptable to 

the City. 

Vice Chancellor ‐ 

University Advancement 

& Planning, Campus 

Planning, Government 

Relations. 

 

Report coordination efforts to 

Monitor.  If UCSF cannot dedicate to 

City, this measure would remain a 

significant unavoidable impact. 

Page 100: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 

Page 101: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

  

 

 

APPENDIX A INITIAL STUDY 

Page 102: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 

Page 103: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

INITIAL STUDY 

 

 

 

 

University of California San Francisco 

Medical Center at Mission Bay Phase I Garage  

 

 

 

 

 

Lead Agency:  The University of California 

 

Prepared by:  UCSF Campus Planning 

654 Minnesota Street 

San Francisco, CA 94143‐0286 

 

February 25, 2011  

 

University of California 

San Francisco  Campus Planning University Advancement and Planning 

Page 104: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Organization of the Initial Study 

This Initial Study is organized into the following sections: 

 

Section  I  –  Project  Information:  provides  information  about  the  proposed  project,  including  project 

location, lead agency, and contact information.  

 

Section II –Project Description: describes the proposed project, the elements included in the project, and 

the project approvals. 

 

Section III –Environmental Factors Potentially Affected: identifies which environmental factors, if any, 

would  be  affected  by  the  project,  including  those  that  involve  at  least  one  significant  or  potentially 

significant impact that cannot be reduced to a less‐than‐significant level.  

 

Section  IV  –  Determination:  indicates  whether  impacts  associated  with  the  proposed  project  are 

significant, and what, if any, additional environmental documentation is required. 

 

Section V – Evaluation of Environmental Impacts: contains the Environmental Checklist form for each 

resource  area. The  checklist  is used  to  assist  in  evaluating  the potential  environmental  impacts of  the 

proposed project and whether  those  impacts were adequately analyzed  in  the UCSF Medical Center at 

Mission Bay EIR. This section also presents an explanation of all checklist answers. 

 

Section  VI  –  Supporting  Information  Sources:  lists  the  references  used  in  the  preparation  of  this 

document. 

 

Section VII – Initial Study Preparers 

 

Page 105: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

‐ 1‐ 

I.  PROJECT INFORMATION 

 

1.  Project title:  

    UCSF Medical Center at Mission Bay Phase I Garage 

2.    Lead agency name and address: 

  The Regents of the University of California 

  1111 Franklin Street 

Oakland, California 94607 

3.    Contact person and phone number:  

  UCSF Campus Planning 

  Tammy Chan, Senior Planner 

(415) 476‐9627 

4.    Project location:  

  UCSF Medical Center at Mission Bay 

  Portions of Blocks 38 and 39 

San Francisco, California 94143 

5.    Project sponsor’s name and address: 

  Same as above.  

6.    Custodian of the administrative record for this project: 

  Same as above. 

7.    Identification of previous EIRs relied upon for tiering purposes (including all applicable 

LRDP and project EIRs) and address where a copy is available for inspection.) 

   

Document for which this Initial Study and SEIR is prepared: 

 

Final EIR for UCSF Medical Center at Mission Bay, certified by The Regents on September 17, 

2008 (State Clearinghouse No. 2008012075 

 

Related UCSF documents that are referenced: 

 

Final  EIR  on  the  1996  LRDP  certified  by  The  Regents  on  January  17,  1997  (State 

Clearinghouse No. 1995123032) 

 

Final LRDP SEIR on LRDP Amendment #1, Mission Bay Housing Program, certified by The 

Regents on January 17, 2002 (State Clearinghouse No. 1995123032) 

 

Final LRDP FEIR on LRDP Amendment #2, Hospital Replacement Program, certified by The 

Regents on March 17, 2005 (State Clearinghouse Number 2004072067) 

 

UCSF Medical  Center  at Mission  Bay  FSEIR  ‐  Residential  Sound  Reduction  Program  for 

Helicopter  Operations,  certified  by  The  Regents  on  April  20,  2009,  (State  Clearinghouse 

Number No. 2008012075) 

 

Copies of all relevant CEQA documents, including the 1996 LRDP and subsequent LRDP Amendments 

are available at UCSF Campus Planning. 

Page 106: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage 

‐ 2 ‐ 

II.  PROJECT DESCRIPTION 

A. INTRODUCTION 

This initial study evaluates revisions to the proposed parking structure previously analyzed in the 2008 

UCSF Medical Center at Mission Bay EIR to determine whether the minor revisions to the parking garage 

would  cause  new  or  substantially  more  significant  environmental  effects  that  were  not  previously 

examined in the 2008 EIR. If the revisions to the project could cause new or substantially more significant 

environmental effects that were not previously examined in the 2008 EIR, pursuant to Section 15163 of the 

CEQA  Guidelines,  the  lead  agency  may  choose  to  prepare  a  supplement  to  an  EIR  rather  than  a 

subsequent  EIR  if  “only minor  additions  or  changes would  be  necessary  to make  the  previous  EIR 

adequately  apply  to  the  project  in  the  changed  situation.”  This  initial  study  would  support  the 

preparation of  the Supplemental EIR  (SEIR) and Pursuant  to Section 15163(b), “The supplement  to  the 

EIR need contain only  the  information necessary  to make  the previous EIR adequate  for  the project as 

revised.” 

B. BACKGROUND 

Each  campus  of  the University  of California  is  required  to  prepare  a Long Range Development  Plan 

(“LRDP”)  that  sets  forth  concepts, principles,  and plans  to  guide  future growth  of  that  campus.   The 

Board of Regents of the University of California (“The Regents”) adopted the 1996 LRDP, which outlines 

development proposals  for  the University of California, San Francisco  (“UCSF”)  through  the academic 

year  2011/12.    The  LRDP  has  since  been  amended  several  times,  and  an  EIR was  prepared  for  each 

amendment.  The 1996 LRDP FEIR, together with the various EIRs prepared for LRDP amendments, are 

collectively the “LRDP EIR.” 

LRDP Amendment #2, approved in March 2005, described the planning process that considered potential 

hospital  replacement  sites  at  Parnassus Heights, Mount Zion,  and Mission Bay.   A  preferred  plan  to 

develop three integrated specialty hospitals at Mission Bay on the Mission Bay South site located south of 

16th Street was identified, but other sites remained in consideration.  The Hospital Replacement Program 

was  analyzed  at  a program  level  in  the LRDP Amendment  #2‐ Hospital Replacement EIR  (2005 EIR).  

Subsequently, once the Mission Bay South site option was selected, the UCSF Medical Center at Mission 

Bay EIR was prepared in September 2008. The 2008 EIR, which was tiered from the program‐level 2005 

EIR, focused on the project‐level environmental effects of the Medical Center at Mission Bay. 

The project proposed  in  the 2008 UCSF Medical Center at Mission Bay EIR was analyzed  in two major 

phases,  the LRDP Phase  (Phase  I) and Future Phase  (Phase  II). Phase  I  included a 289‐bed hospital, an 

Outpatient building and the Cancer Outpatient building, consisting of 336,500 gross square feet (GSF), a 

36,000 GSF Energy Center, and a 600‐space parking structure with 475‐surface parking spaces,  totaling 

1,075‐parking  spaces.    In  September  2008, The Regents  approved  the hospital,  the Energy Center,  the 

Outpatient building, and the surface parking.  Groundbreaking for the approved components of Phase I 

began  in October  2010, with  the hospital  complex  scheduled  to  open  in  2014.   Approval of  the  other 

components of Phase I, including the parking structure and the Cancer Outpatient building, would occur 

at a future date.  Phase II would include a 261‐bed hospital and approximately 225 to 925 parking spaces. 

Upon  completion  of  both phases,  the UCSF Medical Center  at Mission Bay would provide  a  550‐bed 

hospital, two outpatient facilities, and associated support space and parking. Phase II is assumed to start 

following the completion of the Phase I, and would require subsequent project‐level environment review 

once specific project design is available. 

Page 107: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 3 ‐ 

The UCSF Medical Center at Mission Bay EIR was certified by The Regents on September 17, 2008. The 

purpose of this initial study is to evaluate the proposed revisions to the parking structure in Phase I of the 

UCSF Medical Center at Mission Bay. All other aspects of  the Phase  I project would  remain  the same. 

Therefore, the focus of this initial study is on the revisions to the parking structure, no further discussion 

is required for other components of the Phase I UCSF Medical Center at Mission Bay.  

C. PROJECT LOCATION AND DESCRIPTION 

The Mission Bay  campus  site  is one of  three major UCSF  campus  sites  in San Francisco. As  shown  in 

Figure 1, UCSF Campus Locations, the Mission Bay Campus is located approximately one and one‐half 

miles  south of downtown. The  2008 UCSF Medical Center  at Mission Bay EIR  analyzed  a project  site 

consisting of 14.5 acres  just south of the existing UCSF Mission Bay research campus. The site is within 

the Mission Bay Redevelopment Plan and consists of the Mission Bay South Plan Parcels 36‐39, and X3. 

The project site is bordered by 16th Street to the north, 3rd Street to the east, and Mariposa Street to the 

south.  In  the  future,  a new  segment  of Owens  Street would  extend  south  of  16th  Street  to  create  the 

western boundary of the project site. (See Figure 2, Project Location Map) 

 

As analyzed  in  the 2008 EIR,  the Medical Center at Mission Bay complex would be constructed on  the 

eastern portion of  the  site on Blocks 36, 37 and X3. A 600‐space parking structure at about 90  feet  tall 

would  also  be  constructed  as  part  of  Phase  I.  The  parking  structure  would  be  located  along  the 

southwestern portion of the site. Surface parking for approximately 475 vehicles would be provided on 

the remainder of Blocks 38 and 39. Therefore, at the completion of Phase I, approximately 1,075 parking 

spaces for staff, patients, and visitors would be provided. 

 

As  currently  proposed,  the  Phase  I  parking  structure would  be  105‐feet‐tall  and would  include  626 

spaces.  The location of the proposed garage has also shifted to the north so that it is closer to 16th Street. 

(See Figure 3, Project Site Plan) The location of the proposed parking structure in relation to the Medical 

Center at Mission Bay complex that is currently under construction is illustrated in Figure 4, Aerial Site 

View.  The number of surface parking spaces proposed in Phase I on the remainder of Blocks 38 and 39 

has been reduced to approximately 429 spaces, with an additional 13 spaces east of the future extension 

of 4th Street, in what is known as the east lot. The total surface parking spaces would be approximately 

442 compared to the 475 spaces analyzed in the 2008 EIR. Therefore, the total number of parking spaces 

provided in Phase I (626 spaces in the parking structure and 442 surface parking spaces) would decrease 

by approximately seven spaces and would  total approximately 1,068‐parking spaces  from 1,075 spaces. 

Figure 5, Ground Floor Plan, provides  the  footprint of  the proposed parking structure while Figure 6, 

North‐South Building Section, provides the section of the parking levels. 

 

Subsequent to the publication of the 2008 EIR, the access roads from Owens and 4th Street, leading to the 

proposed parking structure has been renamed from North and South Access Roads to North and South 

Connector Roads, and the Center Garage Access is now referred to as Parking Structure Road. Similar to 

the original proposed project, access and circulation to the site and the associated parking would be from 

Owens or 4th Streets via the North and South Connector Roads, with Owens Street accommodating the 

majority of the vehicular traffic. 

 

A total of 114 bicycle spaces would be constructed, which is in excess of the one bike space per 20 vehicle 

parking  ratio  required  in  the Design  for Development of  the Mission Bay South Plan Area. Of  the 114 

bicycle spaces provided, 72 secured spaces would be provided in a cage inside the garage and 42 spaces 

Page 108: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 4 ‐ 

would be outside the garage. In addition, 66 motorcycle stalls would be provided in the parking garage 

and 16 motorcycle stalls would be provided in the surface parking lot. 

 

Vertical metal louvers with an anodized finish are proposed on the exterior of the parking structure. This 

would provide light and varying views into the garage from different viewpoints, while also allowing for 

proper ventilation. The  louvers would be  finished  in warm earth  tones  in color and would also act as 

shades to reduce the effects of direct headlights from vehicles. Figure 7, Approach from Owens Street, 

shows  the  visual  aesthetics  of  the  structure  along  Owens  Street.  To  reduce  the  potential  for  light 

pollution,  roof  top  light  fixtures are designed with cut off  features  that ensure no direct artificial  light 

spills over the uppermost parking level. 

 

As  noted  above, Phase  II was  also  analyzed  in  the Medical Center  at Mission Bay EIR which would 

include  a  261‐bed  hospital  and  approximately  225  to  925  additional  parking  spaces. No  revisions  are 

being proposed for Phase II. However, subsequent project‐level environment review would be required 

once specific project design is available. All adopted mitigation and improvement measures outlined in 

the 2008 UCSF Medical Center at Mission Bay EIR would continue to be applicable. 

 

D. PROJECT OBJECTIVES 

 

The project objectives outlined in the 2008 UCSF Medical Center at Mission Bay EIR include the goals and 

objectives developed for the 1996 LRDP and subsequent Amendments. The proposed parking structure 

would support the Medical Center Project, analyzed in the 2008 Medical Center at Mission Bay EIR. 

 

E. SURROUNDING LAND USES 

 

The project site borders 16th Street to the north, 3rd Street to the east, and Mariposa Street to the south. 

The western boundary of UCSF’s Mission Bay campus  is along Owens Street, which currently ends at 

16th  Street.  Just  outside UCSF’s  campus  boundary, west  of Owens  and  north  of  16th  Street,  are  the 

Alexandria Life Science and Gladstone Institutes research and lab buildings.  The project site is just south 

of  the existing UCSF Mission Bay  research  campus. The  five  story Genentech Hall and Byers Hall are 

located directly north  across  16th Street. The MUNI KT‐Third Street  light  rail  is  to  the  east,  and  runs 

along  Third  Street. Upon  the  completion  of  Phase  I,  4th  Street would  be  extended  through  the  site 

providing  access  from  16th  Street  to  the  Potrero  Hill  and  Dogpatch  neighborhoods  to  the  south.  

Immediately south of parking proposed in Phase I is the site for a future City park, Mariposa Park. To the 

west of  the proposed parking  structure,  across  from  the  future  extension of Owens  Street  is  a vacant 

parcel, and the elevated I‐280 freeway. 

 

F. DISCRETIONARY APPROVALS 

 

Action  by  The  Regents  (including  any  Regents‐delegated  committee  or  official):  Anticipated  project 

actions and approvals  include, but are not  limited  to approval of  the design by  the Chancellor  for  the 

proposed Phase I Parking Structure at UCSF Medical Center at Mission Bay. 

 

Action by Other Agencies:  There are no responsible or trustee agencies that have approval authority over 

the proposed project.  

 

 

 

Page 109: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 5 ‐ 

G. CONSISTENCY WITH THE LRDP 

 

Current development at UCSF is guided by the 1996 LRDP, as amended, which includes specific policies 

related to future development and space needs at the various UCSF campuses. Amendment #1 amended 

the LRDP to provide for on‐site student housing at Mission Bay. Amendment #2‐ Hospital Replacement 

Program was analyzed at a program level in the LRDP Amendment #2‐ Hospital Replacement EIR (2005 

EIR). Analyzed as part of the 2008 UCSF Medical Center at Mission Bay EIR, Amendment #3 added the 

14.5‐acre UCSF Medical Center project to expand the UCSF Mission Bay campus to 57 acres, incorporated 

the Mission Bay Planning Principles, and updated the functional zone maps at Mission Bay.  

 

The 2008 UCSF Medical Center at Mission Bay EIR analyzed two major phases, LRDP Phase (Phase I) and 

the Future Phase (Phase II). Phase I would include a 289‐bed hospital, two outpatient facilities, an Energy 

Center, and associated parking. The original parking structure associated with Phase I would include 600 

parking spaces with approximately 475‐surface parking spaces.   No changes are currently proposed for 

Phase II. 

 

The  revised project would  include a  626‐space parking  structure with  approximately  442  total  surface 

parking spaces. All over, this would be a reduction of seven parking spaces. The revised project would be 

generally  consistent with  the  original  program. One  of  the Mission  Bay  Planning  Principle  includes 

community consultation during  the  life of a project  regarding exterior design and  landscape elements. 

The  project  team  for  the  proposed  parking  structure  has  been  meeting  with  the  San  Francisco 

Redevelopment Agency,  the Mission Bay Citizens Advisory Committee,  and  a  subgroup of  the UCSF 

Mission Bay Community Advisory Group  ‐‐ the Mission Bay Community Action Team (CAT)  ‐‐ on the 

proposed exterior design. The proposed parking structure and the associated surface parking lot would 

be  consistent  with  the  LRDP  and  the  Mission  Bay  Planning  Principles  adopted  as  part  of  LRDP 

Amendment #3. 

Page 110: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 6 ‐ 

Figure 1:  UCSF Campus Sites 

Project Site is located within the Mission Bay Campus 

Project Site

Page 111: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 7 ‐ 

Figure 2:  Mission Bay Campus Area 

 

 

Proposed Project

Page 112: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 8 ‐ 

Figure 3:  Project Site Plan  

 

Page 113: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage 

‐ 9 ‐ 

Figure 4:  Aerial View of the Proposed Project 

 

Proposed Parking Garage

Page 114: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 10 ‐ 

Figure 5:  Proposed Ground Floor Plan 

 

 UCSF MEDICAL CENTER 

AT MISSION BAY PARKING STRUCTURE        Source:   Rudolph  and  Sletten  and WRNS  Studios  LLP

Page 115: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage 

‐ 11 ‐ 

Figure 6:  Proposed North‐South Building Section 

 

   

UCSF MEDICAL CENTER 

AT MISSION BAY PARKING STRUCTURE Source:  Rudolph and Sletten and WRNS Studios LLP

Page 116: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage 

‐ 12 ‐ 

Figure 7:  Approach from Owens Street 

 

  UCSF MEDICAL CENTER AT MISSION BAY PARKING STRUCTURE Source:  Rudolph and Sletten and WRNS Studios LLP

Page 117: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage 

‐ 13 ‐ 

III.  ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED: 

 

The environmental factors checked below would be potentially affected by this project, involving at least 

one impact that is a “Potentially Significant Impact” as indicated by the checklist on the following pages. 

 

□  Aesthetics  □ Agriculture and Forestry 

Resources  □ Air Quality 

□  Biological Resources  □  Cultural Resources   □ Geology/Soils 

■  Greenhouse Gas Emissions   □ Hazards & Hazardous 

Materials □

Hydrology/Water 

Quality 

□  Land Use/Planning  □  Mineral Resources  □ Noise 

□  Population/Housing  □  Public Services  □  Recreation 

■  Transportation/Traffic  □  Utilities/Service Systems  ■ Mandatory Findings of 

Significance 

 IV.  DETERMINATION: (To be completed by the Lead Agency) 

 

On the basis of the initial evaluation that follows: 

 

■ I  find  that  the  proposed  project  could  have  a  ʺpotentially  significant  impactʺ  or  ʺpotentially  significant 

unless mitigatedʺ impact on the environment, and that these effects have not been adequately analyzed by 

an earlier EIR. A SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT will be prepared. 

□ 

 

I  find  that although  the proposed project could have a significant effect on  the environment, because all 

potentially  significant  effects  (1) have been  addressed  adequately  in  an  earlier  environmental document 

pursuant  to applicable  standards, and  (2)  either no  changes or no  substantial  changes  to  the project  are 

proposed, and no new information of substantial importance has been identified.  An ADDENDUM and/or 

FINDINGS will be prepared. 

 

 

 

 

Diane Wong, Environmental Coordinator 

University of California, San Francisco 

 

   

Date 

 V.  EVALUATION OF ENVIRONMENTAL IMPACTS 

 

The University has defined the column headings in the Initial Study checklist as follows: 

 

A)  “Additional  Project‐level  Impact  Analysis  Required”  applies where  the  project may  result  in  an 

environmental impact that was not considered in an earlier document, or not considered in sufficient 

detail, and/or substantial project changes, changed circumstances, or new information of substantial 

importance triggering CEQA Section 15162 has occurred since certification of the earlier document.  

 

B)  “Project  Impact  Adequately  Addressed  in  Earlier  Environmental  Document”  applies  where  the 

potential  impacts  of  the proposed  project were  adequately  addressed  in  an  earlier  environmental 

document and either no changes or no substantial changes to the project are proposed, and no new 

information of substantial importance has been identified. 

Page 118: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 14 ‐ 

Impact Questions and Responses 

 

The  impact  questions  identified  in  this  Section  are  the  same  as  those  in  Appendix  G  of  the  CEQA 

Guidelines. Additionally,  in several  impact  topics  there are  impact questions  that  relate  to significance 

standards established in UCSF’s LRDP Final EIR, where they are not otherwise covered by Appendix G. 

 

The  impact questions  consist of  two  types:    those  that  require a qualitative  evaluation, and  those  that 

require a quantitative analysis.   In general, the  impact questions themselves constitute the standards of 

significance, and where applicable, additional explanation and/or quantitative  thresholds are provided 

under the appropriate environmental topic. 

 

Issues 

Additional 

Project‐level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

1. AESTHETICS – Would the project:      

a) Have a substantial adverse effect on a scenic vista?  □  ■  

b)  Substantially  damage  scenic  resources,  including, 

but  not  limited  to,  trees,  rock  outcroppings,  and 

historic buildings within a state scenic highway? 

□  ■ 

 

c)  Substantially degrade  the  existing visual  character 

or quality of the site and its surroundings? □  ■ 

 

d)  Create  a  new  source  of  substantial  light  or  glare 

which would adversely affect day or nighttime views 

in the area? 

□  ■ 

 

e)  Exceed  the  LRDP  EIR  significance  standard  by 

substantially  reducing  sunlight  or  significantly 

increasing shadows  in public open space areas, or by 

increasing  pedestrian‐level  wind  speeds  above  the 

hazard  level  set  forth  in  the  San  Francisco  Planning 

Code? 

□  ■ 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

Page 119: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 15 ‐ 

portion  of  the  site  as  part  of Phase  I. The modified  project would  increase  the  height  of  the  parking 

structure to 105 feet tall, reduce the total number of parking spaces in Phase I by seven spaces, and shift 

the  location of  the parking  structure  to  the north,  closer  towards  16th Street,  along  the  future Owens 

Street extension. Due to the shift in the garage location, the intersection at Owens and Parking Structure 

Road that would be constructed as part of Phase II in the original EIR analysis would be constructed as 

part of Phase  I.   Therefore, under  the  revised project,  three access points  from Owens Street would be 

created as part of Phase  I,  the North and South Connector Roads and  the new  intersection at Parking 

Structure Road. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would 

remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The 2008 Medical Center at Mission Bay EIR analyzed a 90‐foot‐tall, 600‐space parking structure located 

on the southwestern portion of Block 38 as part of the Phase I Medical Center at Mission Bay project. The 

general massing of Phase  II of  the parking garage was analyzed at a programmatic  level.  In Phase  II, 

approximately 225 to 925 additional parking spaces would be provided on the western portions of Blocks 

38 and 39.   The  evaluation of visual quality  in  the Medical Center at Mission Bay EIR  considered  the 

potential effects on visual character, views, light and glare, and wind.  

 

1a) and b): As noted in the Notice of Preparation/Initial Study (NOP/IS) for the Medical Center at Mission 

Bay, a scenic vista is defined as a public view from existing parks, plazas, roadways or other public areas, 

and gateway or panoramic views from areas generally available to the general public. Views from private 

residences and non‐public areas are not considered to be scenic views because they are not available to 

the  general  public.  The  NOP/IS  prepared  for  the  Medical  Center  at  Mission  Bay  concluded  that 

implementation of  the project would not  create  impacts not previously  considered  in  the  Initial Study 

prepared  for  the LRDP Amendment  #2‐ Hospital Replacement EIR  and would not have  a  substantial 

adverse effect on a scenic vista.  While the proposed parking structure has increased from 90 to 105 feet in 

height, it would not have a substantial adverse effect on a scenic vista and the conclusion reached in the 

NOP/IS under 1a) and b) would remain valid. 

 

1c):  The Medical  Center  at Mission  Bay  EIR  concluded  that  implementation  of  the  proposed  project 

would result in visual changes at the site with the demolition of the existing structures and development 

and  construction  of  a  medical  center.  The  adopted  Mission  Bay  South  Plan  of  the  San  Francisco 

Redevelopment  Agency  (SFRA)  calls  for  a  densely  built  urban  environment  with  building  heights 

ranging  from 90  to 160  feet. The medical center would be developed  to be visually consistent with  the 

surrounding  development  patterns  in  the  Mission  Bay  mixed‐use  neighborhood.  In  general,  most 

structures for the medical center project would be approximately 105 feet in height, with an additional 20 

feet  to  the  top of  the mechanical  components. The Medical Center at Mission Bay EIR  concluded  that 

Phase I would be consistent with the development standards set forth in the SFRA MOU and compliance 

with  the SFRA MOU, as already  required of UCSF, would ensure  that  the existing visual  character or 

quality of the site and its surroundings are not substantially degraded. 

 

The modified parking garage would continue to be consistent with the development standards set forth 

in  the SFRA MOU, where  the plan  calls  for  a densely built urban  environment with building heights 

ranging from 90 to 160 feet and visual impacts would be less than significant. 

 

The location of the Phase I parking structure has shifted further to the north, where it was previously the 

area planned for the surface parking lot in Phase I. However, it should be noted that under full buildout 

Page 120: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 16 ‐ 

in Phase  II,  the entire site would be planned  for a parking structure. Therefore,  it would be consistent 

with the use designated for this portion of Blocks 38 and 39 and consistent with the prior environmental 

analysis. Access and circulation to the site and the proposed parking structure has been revised due to the 

creation of the intersection at Owens and Parking Structure Road, during Phase I instead of Phase II.  The 

future Owens Street extension  is  still anticipated  to accommodate  the majority of  the vehicular  traffic. 

Potential changes to the traffic analysis as a result of the modified project will be discussed in the SEIR.  

The slight shift  in  the parking structure  location would not substantially degrade or change  the visual 

quality of the site and impacts would be less than significant.  

 

1d): The Medical Center at Mission Bay EIR analyzed the potential for the construction and operation of 

the proposed development to  increase the amount of  light and glare  in the area. The proposed medical 

center  would  include  cladding materials  such  as  glass,  precast  concrete  and metal  panels.  The  EIR 

concluded that any impacts associated with light and glare would be less than significant. 

 

Similar  to what was analyzed  in  the 2008 EIR,  the  revised parking garage would  include metal panels 

(louvers) on the exterior façade and would be generally consistent with the massing, materials, patterns, 

and  colors used  for  the Medical Center design. This would  not  change  the  analysis  on  this  topic. To 

mitigate any potential  light  spillover  from  the garage,  the  roof  top  light  fixtures on  the garage would 

provide a  cut off  feature  to  ensure  that no direct  artificial  light  spillover  from  the uppermost parking 

levels. Second, the metal louvered façade proposed for the parking structure would function as shades, 

allowing  for natural ventilation but  reducing and  refracting  the artificial  light  from within  the parking 

structure. Therefore, the project design would further reduce any impacts associated with light and glare 

and the conclusions reached in the EIR would remain valid and would be less than significant. 

 

1e): A wind  study was  conducted  in  2008  as  part  of  the Medical Center  at Mission  Bay  EIR.  It was 

conducted  in  response  to  the Mission  Bay  South  Redevelopment  Area  requirement  to  identify  and 

mitigate  significant  impacts  of  pedestrian‐level winds,  as  stated  in  the Mission  Bay  Subsequent  EIR1 

Mitigation Measure D.7 (adopted through UCSF’s LRDP EIR Mitigation Measure 4.1‐7), as excerpt is as 

stated as follows:  

 

“D.7  The Redevelopment Agency would  conduct wind  review  of  high‐rise  structures  above  100  feet. 

Wind tunnel testing would also be required unless… it is determined that… impacts, based on a 26‐mile‐

per‐hour hazard  for a single hour of  the year criterion, will not occur. The purpose of  the wind  tunnel 

studies is to determine design‐specific impacts based on the above hazard criterion and to provide a basis 

for design modifications to mitigate these impacts. Projects within Mission Bay, including UCSF, would 

be required to meet this standard or to mitigate exceedances through building design.” 

 

A wind study was conducted  to determine design‐specific  impacts based only on  the Planning Code’s 

Hazard Criterion and to provide a basis for design modifications to mitigate these impacts. Wind‐tunnel 

tests were conducted at 24 test  locations for two scenarios, the Phase I development, and the combined 

Phase I and Phase II development in the Medical Center at Mission Bay EIR. Under the Phase I scenario, 

two  locations,  the  south  side of  16th  Street,  at  the  intersection  at Owens,  and  the  southeast  corner of 

Mariposa  and  3rd  Streets, wind would  exceed  the wind  hazard  criterion  set  forth  in  Planning Code 

Section  148. However,  the  total  duration  of  these  exceedances would  be  similar  to  but  less  than  the 

1 City and County of San Francisco, Final Mission Bay Subsequent EIR, Sept. 17, 1998, and University of California San Francisco LRDP Amendment #2- Hospital Replacement EIR, March 2005.

Page 121: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 17 ‐ 

duration  of  the  existing  wind  hazards  on  the  site,  so  the  project  would  generally  improve  wind 

conditions from those now existing and reduce the overall duration of hazard exceedances. 

 

At the completion and full buildout of Phase II, two wind hazard exceedances that were identified under 

Phase  I would be eliminated. However, a new exceedance would be created at another  location, at 3rd 

and  16th  Streets.  Under  the  combined  Phase  I  and  Phase  II  scenario,  the  medical  center  would 

substantially improve wind conditions by reducing the number of duration of previously occurring wind 

hazard exceedances. The Phase II scenario would result in one remaining wind hazard exceedance at one 

of  the  24 pedestrian  test point  locations. As  a  result,  the EIR  concluded  that  continued  actions under 

UCSF Mitigation Measure  4.1‐7  and City Mitigation Measure D.7  (listed  above) would be  required  to 

eliminate this hazard through building design and no further mitigation measures were necessary. 

 

As noted above, the Phase I parking structure has been modified and the height has increased to 105 feet 

to  the  top‐of‐screen. Under Mitigation Measure D.7,  because  the  structure would  exceed  100  feet  in 

height,  the  revised structure would  require a wind  tunnel  testing or  technical  review  to determine  the 

potential  wind  conditions.  An  updated  technical memorandum2  was  prepared  to  evaluate  potential 

changes to the wind conditions due to the proposed design changes to the Phase I parking structure.  

 

It should be noted that the 2008 wind tunnel test conducted for the UCSF Medical Center EIR included 

the buildout, i.e. Phase II, however, without a defined design for the Phase II garage. The wind testing for 

Phase  II  included  the  total building mass  that would occupy  that portion of  the Campus, but made no 

distinction  between  the  allocations  of  building  uses  in  the  conceptual  building mass  of  the  Phase  II 

development. Therefore, the original proposed 600 space, 90‐foot‐tall parking structure was assumed to 

be part of a larger conceptual building mass that would form the Phase II development.  

 

The  updated  2010  analysis  considered whether  the  proposed modifications  to  the  parking  structure 

would result in a hazardous wind condition. The mechanism in which buildings can adversely affect the 

pedestrian wind  environment  is  that  buildings much  taller  than  surrounding  buildings  intercept  and 

redirect  winds  that  might  otherwise  flow  overhead,  bringing  them  down  the  vertical  faces  of  the 

buildings to the ground level, creating ground‐level wind.  

 

An  increase  from 90  to 105  feet  in height would not  substantially  rise above  the height of  the upwind 

buildings in the Mission Bay South area. Thus, the updated analysis concluded that the resulting change 

would not be substantial. The analysis also considered whether  the screened  (metal  louvers), non‐solid 

surface of the parking structure would gather and redirect winds to the ground level. It was determined 

that  although  the  screened  façade would be  taller, wind would not gather  and be directed down  the 

vertical face of the garage to the ground level. As a result, the current building design would have a lesser 

physical capability  to gather and redirect winds down  to  the ground  level  than  the building mass  that 

was modeled  in  the 2008 wind  tunnel study. Therefore,  the  increase  in height of  the garage  to 105  feet 

would have no greater impact on the wind conditions than the project analyzed in the 2008 EIR and the 

conclusions reached in the EIR would remain valid. 

 

For the reasons noted, sunlight, shadow and wind impacts would be less than significant and will not be 

further analyzed in the SEIR. 

2 ESA, memo to Lori Yamauchi, Assistant Vice Chancellor UCSF Campus Planning, Technical Memorandum Potential Wind Conditions, UCSF Medical Center at Mission Bay, December 3, 2010.

Page 122: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 18 ‐ 

Issues 

Additional 

Project‐level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

2. AGRICULTURE AND FOREST RESOURCES –

Would the project:    

 

a)  Convert  Prime  Farmland,  Unique  Farmland,  or 

Farmland  of  Statewide  Importance  (Farmland),  as 

shown  on  the  maps  prepared  pursuant  to  the 

Farmland Mapping  and Monitoring  Program  of  the 

CA Resources Agency, to non‐agricultural use? 

□  ■ 

 

b) Conflict with existing zoning for agricultural use, or 

a Williamson Act contract? □  ■ 

 

c) Conflict with existing zoning for, or cause rezoning 

of,  forest  land  (as  defined  in  Public Resources Code 

section  12220(g)),  timberland  (as  defined  by  Public 

Resources  Code  section  4526),  or  timberland  zoned 

Timberland  Production  (as  defined  by  Government 

Code section 51104(g))? 

□  ■ 

 

d)  Result  in  the  loss  of  forest  land  or  conversion  of 

forest land to non‐forest use? □  ■ 

 

e) Involve other changes in the existing environment 

which, due to their location or nature, could result in 

conversion of Farmland, to non‐agricultural use or 

conversion of forest land to non‐forest use? 

□  ■ 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic.  There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase  I  and  shift  the  location  of  the  parking  structure  to  the  north.  The modified  project would  not 

include any parking  levels below grade. All other aspects of  the Phase  I and Phase  II project  that was 

analyzed in the Medical Center at Mission Bay EIR would remain the same. 

Page 123: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 19 ‐ 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

2a),  b)  and  e):  The  NOP/IS  prepared  for  the  Medical  Center  at  Mission  Bay  concluded  that 

implementation  of  the  project would  not  create  impacts  or  result  in  a  substantial  adverse  effect  on 

agricultural  uses.  The  proposed  project would  not  be  constructed  on  Farmland  or  land  otherwise  in 

agricultural  use.  The  revisions  to  the  proposed  parking  structure would  not  change  the  analysis  or 

conclusions  reached  in  the NOP/IS prepared  for  the Medical Center at Mission Bay project. However, 

since the publication of the EIR, the CEQA Guidelines was revised to include checklist questions 2c) and 

2d) above.  The site is located in a dense urban area, zoned for urban uses. Therefore, the Medical Center 

at Mission Bay and the minor modifications to the proposed parking garage would not impact forest or 

agricultural  resources  and  no  further  environmental  analysis  for  these  checklist  topics  are  required 

pursuant to Section 15162 of the CEQA Guidelines. 

Page 124: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 20 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

3. AIR QUALITY  – Where  available,  the  significance 

criteria  established  by  the  applicable  air  quality 

management  or  air  pollution  control  district may  be 

relied  upon  to  make  the  following  determinations. 

Would the project:  

 

a)  Conflict  with  or  obstruct  implementation  of  the 

applicable air quality plan? □  ■ 

 

b)  Violate  any  air  quality  standard  or  contribute 

substantially  to  an  existing  or  projected  air  quality 

violation? 

□  ■ 

 

c) Result in a cumulatively considerable net increase of 

any  criteria  pollutant  for which  the  project  region  is 

non‐attainment  under  an  applicable  federal  or  state 

ambient  air  quality  standard  (including  releasing 

emissions  which  exceed  quantitative  thresholds  for 

ozone precursors)? 

□  ■ 

 

d)  Expose  sensitive  receptors  to  substantial  pollutant 

concentrations? □  ■ 

 

e)  Create  objectionable  odors  affecting  a  substantial 

number of people? □  ■ 

 

f)  Exceed  the  applicable  LRDP  EIR  standard  of 

significance  by  exposing  receptors  to  toxic  air 

contaminant  emissions  that  (1)  result  in  a  cancer  risk 

greater  than  10  cancer  cases  per  one  million  people 

exposed in a lifetime; or (2) for acute or chronic effects, 

result  in  concentrations  of  toxic  air  contaminant 

emissions with a Hazard Index of 1.0 or greater 

□  ■ 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic. 

Discussion of Checklist Questions 

Relevant elements of project: 

Page 125: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 21 ‐ 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase  I  and  shift  the  location  of  the  parking  structure  to  the  north.  The modified  project would  not 

include any parking levels below grade. 

 

As  noted  above, Phase  II was  also  analyzed  in  the Medical Center  at Mission Bay EIR which would 

include a 261‐bed hospital and approximately 225 to 925 additional spaces  in a parking structure. With 

the  completion  of  Phase  II,  the  project would  range  from  approximately  1,290  to  1,990  total  parking 

spaces. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would remain 

the  same. No  revisions  are  currently  being  proposed  for  Phase  II. However,  subsequent  project‐level 

environment review would be required once specific Phase II project design is available. 

 

Describe how project was analyzed in earlier environmental document: 

 

3a‐d)  and  f): The potential  construction  and operational  effects of  the proposed medical  center on  air 

quality was  evaluated  in  the Medical Center  at Mission  Bay  EIR. With  the  exception  of  construction 

criteria pollutant and criteria pollutants due  to  the operation of  the Phase  II development, all other air 

quality  impacts were determined  to be  less  than significant. The EIR concluded  that  implementation of 

Mitigation Measure MCMB.2‐1, criteria pollutant construction  impacts would be mitigated to  less‐than‐

significant  levels.  The  mitigation  measure  would  require  certain  emission  standards  for  UCSF 

construction equipment. The EIR also determined that the operation of the medical facilities  in Phase II 

would  generate  criteria  pollutant  emissions  that would  contribute  to  regional  air  pollution  and  this 

impact would be significant and unavoidable. In addition, prior to approval of the Phase II development, 

UCSF  would  conduct  additional  CEQA  review  to  consider  any  new  recommendations  and 

methodologies for mitigating criteria pollutants available at the time of project approvals. 

 

Greenhouse gas (GHG) emissions were also analyzed under  in the Air Quality CEQA checklist topic  in 

the Medical Center at Mission Bay EIR. At the time of the EIR publication, no state or federal regulations 

have  been  set  for  ambient  air  quality  emission  standards  for  greenhouse  gas. The EIR  quantified  the 

project’s emissions and  included a GHG analysis, but used a significance standard  that was consistent 

with strategies to reduce GHG per AB32.3 The EIR concluded that the project would be consistent with 

AB32 and impacts would be less than significant. 

 

3e): The LRDP Amendment #2‐ Hospital Replacement EIR assessed the potential effects of the proposed 

project  to  create objectionable odors. Odorous  substances are  regulated under BAAQMD Regulation 7 

and  is  required  as  part  of  the  hospital  operations.  The  current  medical  center  complies  with  the 

regulations  for  odorous  substances  under  BAAQMD  Regulations  and  the  future  operation  would 

continue to meet the regulations. The LRDP Amendment #2 EIR and the NOP/IS for the Medical Center 

determined  the proposed project would not result  in an adverse effect on odors and  impacts would be 

less than significant. 

 

 

 

 

3 Global Warming Solutions Act of 2006, known as AB32, was passed by the Legislature and signed by Governor Schwarzenegger in 2006, which set the 2020 greenhouse gas emissions reduction goal into law.

Page 126: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 22 ‐ 

Describe how the minor project changes affect the earlier environmental analysis: 

 

3a‐f): The revised parking structure would not result in new or substantially more significant air quality 

impacts that were not previously examined in the Medical Center at Mission Bay EIR.  The 26 additional 

parking spaces in the parking garage would be offset by the decreased number of surface parking spaces. 

The  parking  structure  and  associated  surface  parking  lot  would  support  the medical  center  that  is 

currently under construction and would not generate any additional new trips that was not previously 

analyzed  in  the  Medical  Center  at  Mission  Bay  EIR.  The  parking  structure  would  continue  to  be 

developed  as  part  of  the  Phase  I  project  in  the  same  timeframe  that  was  analyzed  in  the  EIR. 

Implementation of Mitigation Measure MCMB.2‐1  from  the Medical Center at Mission Bay EIR would 

still be required.   Similar  to  the conclusions reached  in  the EIR, Phase  II of  the project would generate 

criteria  pollutant  emissions  that would  contribute  to  regional  air  pollution  and  this  impact would  be 

significant  and  unavoidable.  UCSF  would  implement  all  previously  adopted  measures  and  new 

mitigation measures identified in the Medical Center at Mission Bay EIR, with additional CEQA review 

at the time of project approval for Phase II to consider any new recommendations and methodologies for 

mitigating criteria pollutants.  

 

In  June  2010,  the  BAAQMD  adopted  thresholds  of  significance  for  criteria  air  pollutants, GHGs,  and 

health  risks  from new  sources. The  recently adopted BAAQMD  significance  threshold  for ROG, NOx, 

and PM2.5 is 54lbs/day and 82lbs/day for PM10. An analysis for criteria air pollutants from new sources 

based on the recently adopted BAAQMD thresholds of significance was conducted for Phase I. 

 

With respect to the City of San Francisco’s fine‐particulate exposure standard for development proposals 

located within 500  feet of a major roadway,4  the proposed project would  incorporate  filtration systems 

into the general air supply systems of both the Phase I and Phase II projects. At this time, the proposed 

261‐bed hospital  in Phase II would be  located within 500 feet of the I‐280 freeway, which could be at a 

location where  the potential  for  the PM2.5  concentration  from  local  roadways  to  exceed 0.2  μg/m3. The 

hospital  plans  to  use  high  efficiency  particulate  filtration  (such  as HEPA  or  ULPA) within  systems 

serving  bone  marrow  transfers,  hematology/oncology  treatment,  radiation  therapy,  and  pediatric 

intensive  care. Other  air  handling  systems would  include  these  filters  as‐needed.  Therefore,  ambient 

concentrations of fine particulates would not pose a substantial risk to patients, hospital workers or other 

occupants of the hospital under construction in Phase I (which is beyond 500 feet) or the future hospital 

in  Phase  II.  However,  as  noted  previously,  subsequent  project‐level  environment  review  would  be 

required for the Phase II project once specific project design is available. 

 

It can be assumed that the total criteria air pollutant emissions that were reported in the 2008 EIR would 

remain the same under the current revised project since project revisions would not include any change 

in overall use but slight change of  location  for  the parking structure and a  reduction of seven parking 

spaces in Phase I.  The “Proportional Emissions from the Revised Parking Structure in Phase 1” presented 

below  is  the  subset  of  emissions  previous  analyzed  in  the  2008  EIR.    Based  on  the  new  adopted 

significance criteria,  the Phase  I project would continue  to be  less  than significant and  the proportional 

share of operational daily emissions for the proposed parking garage is listed in the table below: 

4 As established by San Francisco Department of Public Health, the Potential Roadway Exposure Zones are defined as areas within the City and County of San Francisco that may exhibit high ambient PM2.5 concentrations due to their proximity to freeways and major roadways (i.e., “Local Roadway Traffic Sources”).

Page 127: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 23 ‐ 

 

Table 3‐1: Project‐related Criteria Air Pollutant Emissions and CEQA Significance Standards

 

Emission Sources 

Criteria Air Pollutant Emissions (lbs/day)

ROG  NOx  CO  PM10  PM2.5 

Total Phase I Project 

(from 2008 MCMB EIR) 

Mobile Sources 

Area Sources 

Stationary 

Other1 

Total 

28.88 

1.66 

3.98 

1.51 

36.03 

27.26 

5.32 

35.98 

0.60 

69.16 

286.79 

4.45 

52.11 

11.96 

355.31 

60.45 

0.02 

5.34 

0.13 

65.94 

11.43 

0.02 

0.08 

0.13 

11.66 

Proportional Emissions 

from the Revised 

Parking Structure in 

Phase 1 

Mobile Sources 

Area Sources2 

Stationary3 

Other 

Total 

15.18 

1.21 

N/Ap 

N/Ap 

16.39 

21.58 

0.66 

N/Ap 

N/Ap 

22.24 

182.19 

0.55 

N/Ap 

A/Ap 

182.74 

35.4 

N/Ap 

N/Ap 

35.4 

6.68 

N/Ap 

N/Ap 

6.68 

Prior BAAQMD 

Guidelines (1999) 

  80  80  550 

(screening)4 

80  No 

Threshold 

BAAQMD Significance 

Thresholds (June 2010) 

  54  54  See below5  82  54 

Notes:  ROG = reactive organic gases; NOx = oxides of nitrogen; CO = carbon monoxide; PM10 = particulate matter with an 

aerodynamic resistance diameter of 10 micrometers or less; PM2.5 = fine particulate matter with an aerodynamic resistance diameter 

of 2.5 micrometers or less, N/Ap = Not Applicable; ppm = parts per million 

 1 “Other Emissions” applies only to the operation of the hospital and would have no emission values associated with the proposed parking structure. 2 The proportional area emission from the revised parking structure is an amount that is below what is measureable. 3 Operation of the parking structure would not produce stationary source emissions, hence N/Ap. 4 The 1999 guidelines recommend this level as a threshold for conducting additional detailed analysis. 5 9.0 ppm (8-hour average), 20.0 ppm (1-hour average)

 

As shown in Table 3‐1, the proportional emission from the revised parking structure would be below the 

prior 1999 BAAQMD Guidelines and the current 2010 BAAQMD significance thresholds for all criteria air 

pollutants.  It  is  BAAQMD  policy  that  the  adopted  thresholds  apply  to  projects  for which  a NOP  is 

published, or environmental analysis begins, on or after  the applicable effective date.5 Therefore, while 

the  2010  BAAQMD  threshold  for NOx was  reduced  from  80lbs/day  to  54lbs/day,  and  the  total NOx 

emission  for  the  total  Phase  I  Project would  be  69.16,  this  impact would  not  be  significant  and  the 

proportional  emissions  from  the  revised parking  structure would  be  below  the  54lbs/day  significance 

threshold. In regards to CO emissions, BAAQMD recommends analysis of CO emissions at a local, rather 

than  a  regional,  level. BAAQMD has  established preliminary  screening  criteria  to determine with  fair 

certainty  that,  if not violated, project‐generated,  long‐term operational  local mobile‐source emissions of 

CO would not result  in, or substantially contribute  to, emissions concentrations  that exceed  the 1‐hour 

ambient air quality standard of 20 ppm or the 8‐hour standard of 9 ppm, respectively.  

 

Table 3‐2 below presents the thresholds of significance for operational‐related criteria air pollutant and 

precursor emissions. These represent the levels at which a project‘s individual emissions of criteria air 

pollutants or precursors would result in a cumulatively considerable contribution to the San Francisco 

Bay Area Air Basin‘s existing air quality conditions. If daily average or annual emissions of operational‐

5 BAAQMD Adopted Air Quality CEQA Thresholds of Significance - June 2, 2010, available at: http://www.baaqmd.gov/~/media/Files/Planning%20and%20Research/CEQA/Adopted%20Thresholds%20Table_December%202010.ashx Accessed February 2011.

Page 128: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 24 ‐ 

related criteria air pollutants or precursors would exceed any applicable threshold of significance listed in 

the table below, the proposed project would result in a cumulatively significant impact. As shown in 

Table 3‐1, the revised parking structure would not exceed any applicable thresholds and would not have 

a cumulatively considerable contribution to this impact. 

 

Table 3‐2: Thresholds of Significance for Operational‐Related Criteria Air Pollutants and Precursors

Pollutant/Precursor  Maximum Annual Emissions 

(tpy) 

Average Daily Emissions 

(lbs/day) 

ROG  10  54 

NOX  10  54 

PM10  15  82 

PM2.5  10  54 Notes:  tpy = tons per year; lbs/day = pounds per day; ROG = reactive organic gases; NOX = oxides of nitrogen; PM10 = respirable 

particulate matter with an aerodynamic resistance diameter of 10 micrometers or less PM2.5 = fine particulate matter with an 

aerodynamic resistance diameter of 2.5 micrometers or less. 

 

Criteria air pollutants are monitored at several monitoring stations within the San Francisco Bay Area Air 

Basin. The monitoring station nearest the project site is at 10 Arkansas Street in San Francisco. In general, 

the ambient air‐quality measurements from this station are representative of the air quality in the vicinity 

of the project site. During the last three years, the station did not register any days the state CO standards 

were exceeded.6 

 

The modifications to the proposed project would not cause significant air quality impacts and no further 

environmental analysis for these checklist topics are required. Appendix G of the CEQA Guidelines was 

amended and adopted  in December 2009 which  includes updated  significance  standard  for evaluating 

GHG  emissions. Additional GHG discussion  and analysis due  to project  revisions and  changes  to  the 

CEQA Guidelines will be presented in the Greenhouse Gas Emissions chapter in the SEIR.  

6 California Air Resources Board (ARB), 2011, Air Quality Data Statistics, Available at: www.arb.ca.gov/adam/welcome.html, Accessed: January 2011.

Page 129: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 25 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

4. BIOLOGICAL RESOURCES ‐‐ Would the project:    

 

a) Have a  substantial  adverse  effect,  either directly or 

through habitat modifications, on any species identified 

as  a  candidate,  sensitive,  or  special  status  species  in 

local  or  regional  plans,  policies,  or  regulations,  or  by 

the  California Department  of  Fish  and Game  or U.S. 

Fish and Wildlife Service? 

□  ■ 

 

b) Have  a  substantial  adverse  effect  on  any  riparian 

habitat or other sensitive natural community identified 

in local or regional plans, policies, regulations or by the 

California Department  of  Fish  and Game  or US  Fish 

and Wildlife Service? 

□  ■ 

 

c)  Have  a  substantial  adverse  effect  on  federally 

protected  wetlands  as  defined  by  Section  404  of  the 

Clean Water Act  (including, but not  limited  to, marsh, 

vernal  pool,  coastal,  etc.)  through  direct  removal, 

filling, hydrological interruption, or other means? 

□  ■ 

 

d)  Interfere  substantially  with  the  movement  of  any 

native resident or migratory  fish or wildlife species or 

with  established  native  resident  or migratory wildlife 

corridors, or  impede the use of native wildlife nursery 

sites? 

□  ■ 

e)  Conflict  with  any  applicable  policies  protecting 

biological resources?  □  ■  

f) Conflict with  the  provisions  of  an  adopted Habitat 

Conservation  Plan, Natural Community Conservation 

Plan, or other applicable habitat conservation plan? 

□  ■ 

 

g)  Exceed  the  applicable  LRDP  EIR  standard  of 

significance  by  damaging  or  removing  heritage  or 

landmark  trees  or  native  oak  trees  of  a  diameter 

specified in a local ordinance? 

□  ■ 

Standards of Significance  

The  impact  questions  above  constitute  the  significance  standards  for  this  environmental  topic.  In 

Page 130: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 26 ‐ 

addition, the significance standard related to local tree ordinances is used as a basis to evaluate potential 

heritage or landmark trees at UCSF campus sites. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase I and shift the  location of the parking structure to the north. All other aspects of the Phase I and 

Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same. 

 

Describe how project is analyzed under this CEQA checklist topic: 

 

The NOP/IS  prepared  for  the Medical Center  at Mission  Bay  concluded  that  the  development  of  the 

proposed project would not result in a significant impact on riparian habitats, sensitive or special status 

species,  sensitive  natural  communities,  protected wetlands,  or movement  or migration  of  any  fish  or 

wildlife species. The proposed project would also not conflict with any applicable policy or conservation 

plans.  Therefore,  the NOP/IS  concluded  that  the  proposed  project would  not  create  any  substantial 

adverse  effect on biological  resources. The modifications  to  the proposed project would not  affect  the 

prior  impact  analyses  or  conclusions  reached  in  the Medical  Center  at Mission  Bay  EIR  related  to 

biological resources. Thus, impacts to biological resources would be less than significant and will not be 

further analyzed in the SEIR. 

Page 131: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 27 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

5. CULTURAL RESOURCES ‐‐ Would the project:     

a) Cause a substantial adverse change in the significance

of a historical resource as defined in Section 15064.5? □  ■ 

 

b) Cause a substantial adverse change in the significance

of  an  archaeological  resource  pursuant  to  Section

15064.5? 

□  ■ 

 

c) Directly or indirectly destroy a unique paleontological

resource or site or unique geologic feature? □  ■ 

 

d)  Disturb  any  human  remains,  including  those 

interred outside of formal cemeteries? □  ■ 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic.  There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

Four structures were on the project site along the eastern boundary, which have since been demolished to 

accommodate  the  construction  of  the  Phase  I  Medical  Center  at  Mission  Bay,  which  is  currently 

underway. A 600‐space parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in 

the EIR at the southwest portion of the site as part of Phase I. The modified project would reduce a total 

of seven parking spaces in Phase I and shift the location of the parking structure to the north. All other 

aspects of the Phase I and Phase II project that was analyzed in the EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The LRDP Amendment #2‐ Hospital Replacement EIR assessed the proposed Mission Bay South project 

site for potential historical resources and concluded the demolition of the structures would have a  less‐

than‐significant  impact on historic resource. The NOP/IS  for  the Medical Center at Mission Bay project 

concluded that implementation of Mitigation Measure 4.3‐1 from the LRDP Amendment #2 EIR would be 

required. The mitigation measure would require that in the event that archaeological resource or human 

remains was encountered, construction work would halt and a qualified archaeologist or paleontologist 

would be consulted to determine the significance and the appropriate next steps. The modifications to the 

proposed project would not affect  the prior  impact analyses or conclusions  reached  related  to cultural 

resources. Thus, these checklist topics will not be analyzed further in the SEIR. 

Page 132: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 28 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

6. GEOLOGY AND SOILS ‐‐ Would the project:      

a) Expose people or  structures  to potential  substantial 

adverse  effects,  including  the  risk  of  loss,  injury,  or 

death involving: 

   

 

i)  Rupture  of  a  known  earthquake  fault,  as 

delineated  on  the  most  recent  Alquist‐Priolo 

Earthquake Fault Zoning Map  issued by  the State 

Geologist for the area or based on other substantial 

evidence  of  a  known  fault?  Refer  to  Division  of 

Mines and Geology Special Publication 42. 

□  ■ 

 

ii)  Strong seismic ground shaking?  □  ■  

iii)  Seismic‐related  ground  failure,  including 

liquefaction? □  ■ 

 

iv)  Landslides?  □  ■  

b)  Result  in  substantial  soil  erosion  or  the  loss  of 

topsoil? □  ■ 

 

c) Be located on a geologic unit or soil that is unstable, 

or that would become unstable as a result of the project, 

and potentially result in on‐ or off‐site landslide, lateral 

spreading, subsidence, liquefaction or collapse? 

□  ■ 

 

d) Be located on expansive soil, as defined in Table 18‐

1‐B  of  the  Uniform  Building  Code  (1994),  creating 

substantial risks to life or property? 

□  ■ 

 

e) Have  soils  incapable  of  adequately  supporting  the 

use of septic  tanks or alternative waste water disposal 

systems where sewers are not available for the disposal 

of waste water? 

□  ■ 

 

f)  Exceed  the  applicable  LRDP  EIR  standard  of 

significance by exposing people to structural hazards in □  ■ 

Page 133: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 29 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

an existing building rated Poor, or Very Poor, under the 

University’s  seismic  performance  rating  system,  or 

substantial nonstructural hazards? 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase I and shift the location of parking structure to the north. The modified project would not include 

any parking levels below grade. All other aspects of the Phase I and Phase II project that was analyzed in 

the Medical Center at Mission Bay EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

Based  on  information  from  prior  geological  surveys,  the NOP/IS  prepared  for  the Medical Center  at 

Mission Bay concluded the impacts on soil erosion would be less than significant since the project would 

be required  to  follow building code standards  for drainage and earthwork. The LRDP Amendment #2‐ 

Hospital  Replacement  EIR  concluded  that  exposure  of  people  and  property  to  liquefaction  and 

earthquake‐induced settlement at Mission Bay would be significant before mitigation.  

 

The NOP/IS prepared for the Medical Center at Mission Bay concluded that implementation of Mitigation 

Measure  4.4‐4  from  the LRDP Amendment  #2 EIR would be  required. The mitigation measure would 

require  a  site‐specific, design‐level  geotechnical  investigation  be  completed  on  the  project design  and 

these geotechnical recommendations be  incorporated  into  the  final design of  the project. Therefore,  the 

proposed project would not create any new impacts not previously considered or adversely affected by 

geological  seismic  impacts  that  cannot be mitigated  through  implementation of LRDP Amendment  #2 

EIR  Mitigation  Measure  4.4‐4.  The  LRDP  Amendment  #2  EIR  also  concluded  that  the  proposed 

construction of new buildings for the medical center to meet current seismic codes and University policy 

would future reduce potential seismic hazards. 

 

The revisions to the proposed project would not affect the prior impact analyses or conclusions reached 

related to geology and soils that were not previously examined in the Medical Center at Mission Bay EIR 

or  LRDP Amendment  #2‐ Hospital Replacement  EIR.  Therefore,  impacts  regarding  geology  and  soils 

would be less than significant and will not be analyzed further in the SEIR. 

Page 134: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 30 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

7.  GREENHOUSE  GAS  EMISSIONS – Would  the 

project:    

 

a) Generate greenhouse gas emissions, either directly or 

indirectly,  that may  have  a  significant  impact  on  the 

environment? 

■  □ 

 

b) Conflict with an applicable plan, policy or regulation 

adopted  for  the purpose of  reducing  the  emissions of 

greenhouse gases? 

■  □ 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic.  There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase  I  and  shift  the  location  of  the  parking  structure  to  the  north.  The modified  project would  not 

include any parking levels below grade. 

 

As noted previously, Phase II was also analyzed in the Medical Center at Mission Bay EIR which would 

include a 261‐bed hospital and approximately 225 to 925 additional spaces  in a parking structure. With 

the  completion  of  Phase  II,  the  project would  range  from  approximately  1,290  to  1,990  total  parking 

spaces. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would remain 

the  same. No  revisions  are  currently  being  proposed  for  Phase  II. However,  subsequent  project‐level 

environment review would be required once specific Phase II project design is available. 

 

Describe how project was analyzed in earlier environmental document: 

 

Greenhouse Gas was discussed as part of the Air Quality CEQA checklist topic in the Medical Center at 

Mission Bay EIR. At the time of publication, no state or federal regulations had been set for ambient air 

quality emission standards for greenhouse gas. The California Air Resources Board (CARB) approved 44 

greenhouse gas reduction strategies under the California Global Warming Solutions Act of 2006 (AB 32) 

and  adopted mandatory  reporting  regulations  requiring  annual  reporting  from  sources  that  generate 

more than 25,000 metric tons of carbon dioxide each year. However, at the time of the Medical Center at 

Mission Bay EIR, no guidance from CARB, Bay Area Air Quality Management District (BAAQMD), State 

Page 135: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 31 ‐ 

Clearinghouse or other  resource agency on  the  relationship between AB32 and CEQA, and how GHG 

emissions would be evaluated in an EIR had been developed.  

 

At  the  time of  the EIR,  the University of California was developing a  long‐term strategy  to voluntarily 

meet the State of California’s AB 32 goals to reduce GHG emissions to 1990 levels by 2020. Further, the 

University was developing  clean  energy  standards with  the  goal  of  reducing GHG  emissions  to  2000 

levels by 2014 and to provide an action plan to become climate neutral. Each UC campus was to form a 

Climate  Change  Working  Group  to  monitor  progress  towards  reaching  the  stated  goals  for  GHG 

reduction.  Consistent with  the  UC’s  sustainable  policy,  UCSF  prepared  a  GHG  inventory  using  the 

California Climate Action Registry protocol followed by the development of a Climate Action Plan, and 

by that action, UCSF is making reasonable progress on GHG emissions reduction.  

 

The Medical Center at Mission Bay EIR quantified the project’s emissions and included a GHG analysis, 

but used a significance standard that was consistent with strategies to reduce GHG per AB32.   The EIR 

concluded that the proposed project would be consistent with AB32 and would not conflict with the state 

goals; therefore, impacts would be less than significant. 

 

Describe how the minor project changes affect the earlier environmental analysis: 

 

Since the certification of the EIR, the CEQA Guidelines was revised to include checklist questions 7a) and 

b)  above.  In  addition,  in  June  2010,  the BAAQMD  adopted new  significance  standards  for  criteria  air 

pollutants, GHGs, and health risks from new sources and an analysis methodology for the evaluation of 

GHG  emissions  in CEQA  documents.    In  general,  parking  structures  do  not  by  themselves  generate 

vehicle trips, rather they support the trips generated by nearby land use.  As such, the proposed garage 

and the associated surface parking lot would not generate vehicle trips and instead would accommodate 

vehicles generated by the hospital, outpatient building, and other support uses of the Medical Center at 

Mission  Bay. Nonetheless,  for  a  conservative  analysis,  the GHG  emissions  produced  by  vehicles  that 

would travel to the proposed garage will be analyzed in the SEIR. 

Page 136: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 32 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

8.  HAZARDS  AND  HAZARDOUS  MATERIALS –

Would the project:  

 

 

  

a)  Create  a  significant  hazard  to  the  public  or  the 

environment  through  the  routine  transport,  use,  or 

disposal of hazardous materials? 

□  ■ 

 

b)  Create  a  significant  hazard  to  the  public  or  the 

environment through reasonably foreseeable upset and 

accident conditions  involving  the release of hazardous 

materials into the environment? 

□  ■ 

 

c)  Emit  hazardous  emissions  or  handle  hazardous  or 

acutely  hazardous  materials,  substances,  or  waste 

within  one‐quarter  mile  of  an  existing  or  proposed 

school? 

□  ■ 

 

d) Be  located  on  a  site which  is  included  on  a  list  of 

hazardous  materials  sites  compiled  pursuant  to 

Government  Code  Section  65962.5  and,  as  a  result, 

would it create a significant hazard to the public or the 

environment? 

□  ■ 

 

e) For a project located within an airport land use plan 

or, where such a plan has not been adopted, within two 

miles of  a public  airport or public use  airport, would 

the project result in a safety hazard for people residing 

or working in the project area? 

□  ■ 

 

f) For a project within the vicinity of a private airstrip, 

would  the project  result  in a  safety hazard  for people 

residing or working in the project area? 

□  ■ 

 

g)  Impair  implementation  of  or  physically  interfere 

with  an  adopted  emergency  response  plan  or 

emergency evacuation plan? 

□  ■ 

 

h) Expose people or  structures  to  a  significant  risk of 

loss, injury or death involving wildland fires, including 

where  wildlands  are  adjacent  to  urbanized  areas  or 

□  ■ 

Page 137: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 33 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

where residences are intermixed with wildlands? 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic. There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed  in  the Medical Center at 

Mission Bay EIR  at  the  southwest  portion  of  the  site  as  part  of Phase  I. The modified  project would 

reduce a  total of seven parking spaces  in Phase  I and shift  the  location of  the parking structure  to  the 

north. The modified project would not include any parking levels below grade. All other aspects of the 

Phase I and Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain 

the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The LRDP Amendment #2‐ Hospital Replacement EIR assessed the proposed Mission Bay South project 

site  for  potential  impacts  of  hazardous  building material during demolition  or  renovation  of  existing 

structures; use of hazardous materials  in new  construction; hazardous material  transportation,  storage 

and disposal impacts during project operations; and exposure of the public to native contaminated soil or 

groundwater.  The  EIR  concluded  that  these  impacts  were  less  than  significant  and  no  mitigation 

measures were  recommended.   However,  the LRDP Amendment  #2 EIR  found  that  the generation of 

hazardous waste could have a significant impact by contributing to additional loads on hazardous waste 

management facilities outside California. The NOP/IS for the Medical Center at Mission Bay concluded 

that implementation of Mitigation Measure 4.5‐4 from the LRDP Amendment #2 EIR would mitigate this 

impact to less than significant.  

 

The modifications  to  the  proposed  project would  not  affect  the  prior  impact  analyses  or  conclusions 

reached related to hazards and hazardous materials that were previously examined in the Medical Center 

at Mission  Bay  EIR  or  LRDP Amendment  #2‐ Hospital Replacement  EIR.  Impacts  from  hazards  and 

hazardous materials would be less than significant and will not be analyzed further in the SEIR. 

Page 138: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 34 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

9. HYDROLOGY AND WATER QUALITY ‐‐ Would 

the project:    

 

a)  Violate  any  water  quality  standards  or  waste 

discharge requirements? □  ■ 

 

b)  Substantially  deplete  groundwater  supplies  or 

interfere substantially with groundwater recharge such 

that there would be a net deficit in aquifer volume or a 

lowering of  the  local groundwater  table  level (e.g.,  the 

production  rate  of  pre‐existing  nearby  wells  would 

drop to a  level which would not support existing land 

uses  or  planned  uses  for  which  permits  have  been 

granted)? 

□  ■ 

 

c)  Substantially  alter  the  existing  drainage  pattern  of 

the site or area, including through the alteration of the 

course of a stream or  river,  in a manner which would 

result in substantial erosion or siltation on‐ or off‐site? 

□  ■ 

 

d)  Substantially  alter  the  existing  drainage  pattern  of 

the site or area, including through the alteration of the 

course of a stream or river, or substantially increase the 

rate  or  amount  of  surface  runoff  in  a manner which 

would result in flooding on‐ or off‐site? 

□  ■ 

 

e)  Create  or  contribute  runoff  water  which  would 

exceed  the capacity of existing or planned stormwater 

drainage  systems  or  provide  substantial  additional 

sources of polluted runoff? 

□  ■ 

 

f) Otherwise substantially degrade water quality?  □  ■  

g) Place housing within a 100‐year flood hazard area as 

mapped on a federal Flood Hazard Boundary or Flood 

Insurance Rate Map or other  flood hazard delineation 

map? 

□  ■ 

 

h) Place within a 100‐year flood hazard area structures 

which would impede or redirect flood flows? □  ■ 

Page 139: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 35 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

 

i)  Expose  people  or  structures  to  a  significant  risk  of 

loss,  injury  or  death  involving  flooding,  including 

flooding as a result of the failure of a levee or dam? 

□  ■ 

 

j) Inundation by seiche, tsunami, or mudflow?  □  ■ 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic. There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed  in  the Medical Center at 

Mission Bay EIR  at  the  southwest  portion  of  the  site  as  part  of Phase  I. The modified  project would 

reduce a  total of seven parking spaces  in Phase  I and shift  the  location of  the parking structure  to  the 

north. The modified project would not include any parking levels below grade. All other aspects of the 

Phase I and Phase II project that was analyzed in the EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The  project  site  is  located  in  a dense urban  area  in  the  vicinity  of China Basin Channel  and  the  San 

Francisco  Bay. Groundwater  is  not  used  at  the  site  and  the  project would  not  alter  or  interfere with 

groundwater supplies or recharge or alter the course of a stream or river. The site is not located within a 

100‐year flood hazard area, or near a levee or dam. Nor is the site within an area with the potential to be 

inundated by seiche,  tsunami, or mudflow. The modifications  to  the proposed project would not affect 

the prior  impact analyses or conclusions reached related  to hydrology and water quality  that were not 

previously  examined  in  the Medical  Center  at Mission  Bay  EIR  or  LRDP  Amendment  #2‐ Hospital 

Replacement  EIR.  Therefore,  no  further  environmental  analysis  of  hydrology  and  water  quality  is 

required and this topic will not be analyzed in the SEIR. 

Page 140: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 36 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

10.  LAND  USE  AND  PLANNING ‐‐ Would  the 

project:    

 

a) Physically divide an established community?  □  ■  

b) Conflict with any applicable land use plan, policy, or 

regulation  of  an  agency  with  jurisdiction  over  the 

project (including, but not limited to the LRDP, general 

plan,  specific  plan,  local  coastal  program,  or  zoning 

ordinance)  adopted  for  the  purpose  of  avoiding  or 

mitigating an environmental effect? 

□  ■ 

 

c)  Conflict  with  any  applicable  habitat  conservation 

plan or natural community conservation plan? □  ■ 

 

d)  Exceed  an  applicable  LRDP  EIR  standard  of 

significance  by  being  substantially  incompatible with 

existing  land uses,  or  by  substantially  conflicting use, 

density,  height  and  bulk  restrictions  of  local  zoning, 

although UCSF is exempt from such restrictions? 

□  ■ 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic.   

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed  in  the Medical Center at 

Mission Bay EIR  at  the  southwest  portion  of  the  site  as  part  of Phase  I. The modified  project would 

increase the height of the parking structure to 105‐feet‐tall, reduce the number of parking spaces in Phase 

I by seven spaces, and shift the location of the parking structure to the north, closer towards 16th Street, 

along the future Owens Street extension. Due to the shift in the garage location, the intersection at Owens 

and Parking Structure Road would be constructed as part of Phase I  instead of Phase II, as analyzed in 

the  original EIR  analysis. Therefore, under  the  revised project,  three  access points  from Owens  Street 

would be created as part of Phase I, the North and South Connector Roads and the new  intersection at 

Parking Structure Road. 

 

Page 141: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 37 ‐ 

As noted previously, Phase II was also analyzed in the Medical Center at Mission Bay EIR which would 

include a 261‐bed hospital and approximately 225 to 925 additional spaces  in a parking structure. With 

the  completion  of  Phase  II,  the  project would  range  from  approximately  1,290  to  1,990  total  parking 

spaces. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would remain 

the  same. No  revisions  are  currently  being  proposed  for  Phase  II. However,  subsequent  project‐level 

environment review would be required once specific Phase II project design is available. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The  project  site  is  within  an  urban  developed  area  and  no  habitat  conservation  plans  or  natural 

community conservation plans apply  to  the Mission Bay area. The Medical Center at Mission Bay EIR 

concluded that the implementation of the Medical Center at Mission Bay would not result in new impacts 

not previously considered and would not have a substantial adverse effect. Therefore, potential land use 

impacts would be less than significant. 

 

As  noted previously,  the  2008 UCSF Medical Center  at Mission Bay EIR  analyzed  two major phases, 

Phase  I  and Phase  II. Phase  I would  include a  289‐bed hospital,  two outpatient  facilities  consisting of 

336,500 gross square feet (GSF), a 36,000 GSF Energy Center, and a 600‐space parking structure with 475 

surface parking spaces, totaling 1,075 parking spaces. Groundbreaking for Phase I began in October 2010.  

 

The proposed project modifications would not change the uses proposed and analyzed in the 2008 EIR. 

While  the  number  of  parking  spaces  in  the  parking  structure  (from  600  to  626) would  increase,  the 

number of surface spaces would decrease (from 475 to approximately 442). Therefore, the overall number 

of parking  spaces would decrease by about  seven spaces under Phase  I.   A decrease of  seven parking 

spaces would not change the prior impact discussion. The proposed parking facility would support the 

medical center complex  that  is currently under construction and would be consistent with  the existing 

uses around the project site and UCSF’s LRDP, as amended.  

 

The  location of  the Phase  I parking structure has shifted  further  to  the north, where  it was previously 

planned for surface parking in Phase I. However, it should be noted that under buildout of Phase II, the 

entire  site  would  be  planned  for  a  parking  structure  accommodating  approximately  1,290  to  1,990 

parking spaces. Therefore, it would be consistent with the use designated for this portion of Blocks 38 and 

39  and  consistent with  the  prior  environmental  analysis.  Access  and  circulation  to  the  site  and  the 

proposed  parking  structure  would  remain  the  same,  with  the  future  Owen  Street  extension  to 

accommodate the majority of the vehicular traffic. 

 

The project site is within the Mission Bay South Plan area where the allowable base building height is 90 

feet with a provision for some building parcels to reach a maximum height of 160 feet. In addition, the 

SFRA MOU established height limit standards that allowed a base height of 90 feet but may extend up to 

105 feet for up to 75% of the medical center structures. The proposed height increase from 90 to 105 feet 

would  be  consistent with  the  surrounding  height  and  bulk  restrictions  and would  be  consistent with 

SFRA MOU height standards. 

 

Based on  this analysis,  the modified project would not result  in new significant environmental  impacts 

related  to  land  use  that  were  not  previously  examined  in  the Medical  Center  at Mission  Bay  EIR. 

Therefore,  the proposed project would not have a significant  land use  impact and  land use will not be 

analyzed further in the SEIR. 

Page 142: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 38 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

11. MINERAL RESOURCES ‐‐ Would the project:     

a) Result  in the  loss of availability of a known mineral 

resource  that would be of value  to  the  region and  the 

residents of the state? 

□  ■ 

 

b)  Result  in  the  loss  of  availability  of  a  locally‐

important mineral resource recovery site delineated on 

a  local  general  plan,  specific  plan  or  other  land  use 

plan? 

□  ■ 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic.  There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed  in  the Medical Center at 

Mission Bay EIR  at  the  southwest  portion  of  the  site  as  part  of Phase  I. The modified  project would 

reduce a  total of seven parking spaces  in Phase  I and shift  the  location of  the parking structure  to  the 

north. The modified project would not require additional excavation. All other aspects of the Phase I and 

Phase II project that was analyzed in the EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The proposed project site is not in an area of known mineral resources and would not otherwise conflict 

with mineral  resource  recovery.  The NOP/IS  for  the  LRDP  Amendment  #2  and  the NOP/IS  for  the 

Medical  Center  at  Mission  Bay  determined  that  no  further  study  of  mineral  resources  would  be 

necessary. Modifications  to  the proposed project would not  result  in new or substantially more severe 

significant environmental impacts related to mineral resources that were not previously examined in the 

Medical Center at Mission Bay EIR or LRDP Amendment #2‐ Hospital Replacement EIR. Therefore, these 

checklist topics will not be analyzed further in the SEIR. 

Page 143: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 39 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

12. NOISE ‐‐ Would the project:       

a) Exposure of persons to or generation of noise  levels 

in  excess  of  standards  established  in  any  applicable 

plan  or  noise  ordinance,  or  applicable  standards  of 

other agencies? 

□  ■ 

 

b)  Exposure  of  persons  to  or  generation  of  excessive 

groundborne vibration or groundborne noise levels? □  ■ 

 

c) A  substantial  permanent  increase  in  ambient  noise 

levels  in  the  project  vicinity  above  levels  existing 

without the project? 

□  ■ 

 

d)  A  substantial  temporary  or  periodic  increase  in 

ambient noise levels in the project vicinity above levels 

existing without the project (including construction)? 

□  ■ 

 

e) For a project located within an airport land use plan 

or, where such a plan has not been adopted, within two 

miles of  a public  airport or public use  airport, would 

the  project  expose  people  residing  or working  in  the 

project area to excessive noise levels? 

□  ■ 

 

f) For a project within the vicinity of a private airstrip, 

would the project expose people residing or working in 

the project area to excessive noise levels? 

□  ■ 

 

g)  Exceed  an  applicable  LRDP  EIR  standard  of 

significance  by  contributing  to  an  increase  in  average 

daily noise levels (Ldn) of 3 dB(A) or more at property 

lines,  if  ambient  noise  levels  in  areas  adjacent  to 

proposed  development  already  exceed  local  noise 

levels set forth  in  local general plans or ordinances for 

such areas based on their use? 

□  ■ 

Standards of Significance 

The impact questions above constitute the significance standards. Regarding question g), a project could 

have a significant noise impact if it contributes to an increase in already exceeded noise ordinance levels. 

Page 144: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 40 ‐ 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed  in  the Medical Center at 

Mission Bay EIR  at  the  southwest  portion  of  the  site  as  part  of Phase  I. The modified  project would 

reduce a  total of seven parking spaces  in Phase  I and shift  the  location of  the parking structure  to  the 

north. All other aspects of  the Phase  I and Phase  II project  that was analyzed  in  the Medical Center at 

Mission Bay EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

12a‐d)  and  g):  The Medical  Center  at Mission  Bay  EIR  concluded  that  demolition  and  construction 

activities associated with the proposed project would temporarily elevate noise levels to significant levels 

in and around  the project  site, particularly near  sensitive  receptors. The  closest  sensitive  receptors are 

located  in  the Mission Bay  research  campus  site, north of  the project  site, which  includes a  child  care 

center on Block 18 and  the 430 residential units on Block 20.   There  is also  the potential proposal  for a 

child care center on Block 23 and a site for a possible future SFUD public school on Block 14. Additional 

residential uses are located south of the medical center site, along Mariposa and Pennsylvania Streets.  

 

The  revised parking  structure would not  result  in new or  substantially more  significant demolition or 

construction noise impacts that were not previously examined in the Medical Center at Mission Bay EIR 

or  LRDP  Amendment  #2‐  Hospital  Replacement  EIR.  The  parking  structure  would  continue  to  be 

developed as part of the Phase I project in the same timeframe that was analyzed in the EIR.  

 

Implementation of Mitigation Measure MCMB.5‐1  from  the Medical Center at Mission Bay EIR would 

require construction contractors to minimize construction noise impacts by using proper equipment and 

limiting  construction  hours,  however,  because  the  mitigation  measure  would  not  guarantee  that 

construction noise  impacts would be reduced  to  less‐than‐significant  levels,  the EIR concluded  that  the 

project would have a temporary but significant and unavoidable noise impact. Similar to the conclusions 

reached  in  the  EIR,  the  revised  project  would  continue  to  have  a  temporary  but  significant  and 

unavoidable noise impact during project construction and demolition. 

 

12e and f): The project site is more than two miles from an airport or private airstrip. The Medical Center 

at Mission Bay EIR concluded that operation of the helicopter landing site (“helipad”) proposed as part of 

the project would increase noise levels at nearby sensitive receptors. Mitigation Measure MCMB.5‐4 was 

included  in  the EIR, which  requires UCSF  to develop a Residential Sound Reduction Program  (RSRP) 

prior to helicopter operation and to include any additional mitigation measures developed as part of the 

community process  for  the RSRP.   Subsequent  to  the publication of  the Medical Center at Mission Bay 

EIR, a Supplemental EIR was prepared  in April of 2009  to address  the RSRP mitigation measure.   The 

Supplemental EIR determined that  implementation of Mitigation Measure MCMB.5‐4 from the Medical 

Center  at Mission  Bay  EIR,  in  conjunction with  the  RSRP Mitigation Measure MCMB.5‐4a  from  the 

Supplemental  EIR,  would  in  general  mitigate  noise  impacts  on  sensitive  receptors  from  helicopter 

operations to less‐than‐significant levels. However, because it may not be feasible for all property owners 

to participate  in  the RSRP,  this  impact was determined  to be  significant and unavoidable. The  revised 

project would not affect the prior impact analysis. Therefore, noise effects will not be analyzed further in 

the SEIR. 

Page 145: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 41 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

13. POPULATION AND HOUSING ‐‐Would the project:   

a)  Induce  substantial  population  growth  in  an  area, 

either directly  (for example, by proposing new homes 

and  businesses)  or  indirectly  (for  example,  through 

extension of roads or other infrastructure)? 

□  ■ 

 

b)  Displace  substantial  numbers  of  existing  housing, 

necessitating  the  construction  of  replacement  housing 

elsewhere? 

□  ■ 

 

c) Displace substantial numbers of people, necessitating 

the construction of replacement housing elsewhere? □  ■ 

 

d)  Exceed  an  applicable  LRDP  or  Program  EIR 

standard  of  significance  by  creating  a  demand  for 

housing outside the market area where the facilities or 

site are located? 

□  ■ 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic. Population 

and housing changes, in and of themselves, are not normally considered significant impacts (substantial, 

adverse impacts on the physical environment). However, CEQA does allow inclusion of secondary effects 

as indicators and influences on other impacts, such as traffic, public services, and air quality. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase I and shift the  location of the parking structure to the north. All other aspects of the Phase I and 

Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The  proposed  project would  not  displace  existing  housing  or  residents.  The  LRDP  Amendment  #2‐ 

Hospital Replacement EIR  assessed  the proposed Mission Bay South project  site  for potential  impacts 

under  these checklist  topics and determined  that  these  impacts were  less  than  significant. The NOP/IS 

prepared for the Medical Center at Mission Bay concluded that the implementation of the Medical Center 

Page 146: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 42 ‐ 

at  Mission  Bay  would  not  create  a  new  impact  not  previously  considered  and  would  not  have  a 

substantial adverse effect.  

 

The  revised parking  structure would not  result  in new or  substantially more population  and housing 

impacts  that were  not  previously  examined  in  the Medical  Center  at Mission  Bay  EIR  or  the  LRDP 

Amendment #2‐ Hospital Replacement EIR. While the number of parking spaces in the parking structure 

would increase from 600 to 626, the number of surface spaces would decrease from 475 to approximately 

442. Therefore, the overall number of parking spaces would decrease by about seven spaces under Phase 

I.   The proposed Phase  I parking structure and associated surface parking  lot would accommodate  the 

trips  generated  from  the medical  center  complex  that  is  currently  under  construction  and would  not 

create new population or housing demand.  Therefore, impacts associated with population and housing 

would be less than significant and this topic will not be analyzed further in the SEIR  

Page 147: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 43 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

14. PUBLIC SERVICES      

Would the project result in substantial adverse physical 

impacts  associated  with  the  provision  of  new  or 

physically altered governmental facilities, need for new 

or  physically  altered  governmental  facilities,  the 

construction  of  which  could  cause  significant 

environmental impacts, in order to maintain acceptable 

service  ratios,  response  times  or  other  performance 

objectives for any of the public services: 

   

 

a) Fire protection?  □  ■  

b) Police protection?  □  ■  

c) Schools?  □  ■  

d) Parks?  □  ■  

e) Other public facilities?  □  ■ 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic.  There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase I and shift the  location of the parking structure to the north. All other aspects of the Phase I and 

Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The LRDP Amendment #2‐ Hospital Replacement EIR assessed the proposed Mission Bay South project 

site for potential impacts under these checklist topics and concluded that the project’s demand for police 

services,  fire  services,  emergency  medical  service,  and  local  school  enrollments  would  be  less  than 

significant. As noted in CEQA topic 15) Recreation, the impacts of the proposed project on parks would 

Page 148: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 44 ‐ 

also be less than significant. The NOP/IS prepared for the Medical Center at Mission Bay concluded that 

the implementation of the Medical Center at Mission Bay would not result in new impacts not previously 

considered and potential impacts on public services would be less than significant. 

 

The modifications to the proposed project would not result in an increase in public service demand that 

were not previously examined  in  the Medical Center at Mission Bay EIR or  the LRDP Amendment #2‐ 

Hospital Replacement EIR. While the number of parking spaces in the parking structure would increase 

from 600 to 626, the number of surface spaces would decrease from 475 to approximately 442. Therefore, 

the overall Phase I parking supply would reduce by approximately seven spaces.  The proposed parking 

spaces would  continue  to  accommodate  the  visitors  and  employees  generated  by  the medical  center 

complex that is currently under construction and would not create new population that would increase 

demand on public services. Therefore, no further environmental analysis of public service is required and 

this topic will not be analyzed further in the SEIR. 

Page 149: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 45 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

15. RECREATION ‐‐      

a)  Would  the  project  increase  the  use  of  existing 

neighborhood and regional parks or other recreational 

facilities such  that substantial physical deterioration of 

the facility would occur or be accelerated? 

□  ■ 

 

b)  Does  the  project  include  recreational  facilities  or 

require  the  construction  or  expansion  of  recreational 

facilities, which might have an adverse physical effect 

on the environment? 

□  ■ 

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic. There are 

no additionally applicable LRDP significance standards. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase I and shift the  location of the parking structure to the north. All other aspects of the Phase I and 

Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

This  checklist  topic was  focused  out  in  the NOP/IS  that was prepared  for  the LRDP Amendment  #2‐ 

Hospital Replacement EIR. The NOP/IS prepared for the Medical Center at Mission Bay concluded that 

the implementation of the medical complex would not increase the use of existing neighborhood parks or 

other recreational facilities  in the area or result  in the construction or expansion of existing recreational 

facilities. The revisions to the proposed parking structure would not change the analysis or conclusions 

reached  in  the NOP/IS  prepared  for  the Medical  Center  at Mission  Bay  project.  Therefore,  potential 

impacts on recreational resources would be less than significant and no further environmental analysis is 

required in the SEIR. 

Page 150: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 46 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

16.  TRANSPORTATION/TRAFFIC ‐‐

Would the project:    

 

a) Conflict with an applicable plan, ordinance or policy 

establishing  measures  of  effectiveness  for  the 

performance  of  the  circulation  system,  taking  into 

account  all  modes  of  transportation  including  mass 

transit  and  non‐motorized  travel  and  relevant 

components  of  the  circulation  system,  including  but 

not  limited  to  intersections,  streets,  highways  and 

freeways,  pedestrian  and  bicycle  paths,  and  mass 

transit? 

■  □ 

 

b) Conflict with an applicable congestion management 

program, including, but not  limited to  level of service 

standards  and  travel  demand  measures,  or  other 

standards  established  by  the  county  congestion 

management  agency  for  designated  roads  or 

highways? 

■  □ 

 

c) Result  in a  change  in air  traffic patterns,  including 

either  an  increase  in  traffic  levels  or  a  change  in 

location that results in substantial safety risks? 

■  □ 

 

d)  Substantially  increase  hazards  due  to  a  design 

feature  (e.g., sharp curves or dangerous  intersections) 

or incompatible uses (e.g., farm equipment)? 

■  □ 

 

e) Result in inadequate emergency access?  ■  □  

f) Result in inadequate parking capacity?  ■ □  

g) Conflict with adopted policies, plans, or programs 

regarding public transit, bicycle, or pedestrian 

facilities, or otherwise decrease the performance or 

safety of such facilities? 

■  □ 

 

h) Exceed the applicable LRDP or Program EIR 

standard of significance by causing substantial conflict 

among auto, bicyclists, pedestrians, and transit 

■ □

Page 151: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 47 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

vehicles? 

 

i) Exceed the applicable LRDP standard of significance 

by generating transit demand that transit systems or 

projected transit service would not be able to 

accommodate? 

■ □

Standards of Significance  

The impact questions above constitute the significance standards for this environmental topic. 

Discussion of Checklist Questions: 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway.  The  Phase  I 

development includes a 289‐bed hospital and approximately 336,500 gross square feet of outpatient care 

uses. A 600‐space parking structure at 90‐feet‐tall was analyzed in the EIR at the southwest portion of the 

site  as  part  of  Phase  I.  Surface  parking  for  approximately  475  vehicles  would  be  provided  on  the 

remainder  of Blocks  38  and  39. Therefore,  at  the  completion  of Phase  I,  approximately  1,075  parking 

spaces for staff, patients, and visitors would be provided on the Blocks 38 and 39 between 4th Street and 

the proposed Owens Street extension. 

 

Owens Street is designed to handle the majority of vehicular traffic. Therefore, the parking facilities are 

located on the west side of the site. Fourth Street is envisioned as a low‐traffic street, with access to the 

project  site  for drop‐offs and pick‐ups,  access  to  the garage and deliveries, but  limited  through  travel 

between  16th  and Mariposa  Streets.   Access  to  the  Phase  I  parking  structure  and  associated  surface 

parking spaces would be from Owens or 4th Streets via the North and South Connector Roads. The access 

to the Phase I parking structure and associated surface parking would be located at the South Connector 

Road with  another  ingress/egress  along Owens  Street  (now  the  intersection  of Owens  Street  and  the 

Parking  Structure  Road,  located  between  the  North  and  South  Connector  Roads.  A  secondary 

ingress/egress into the parking structure is from the surface parking lot to the east. 

 

Phase II would be located west of 4th Street and would include a 261‐bed hospital and approximately 225 

to 925 parking spaces. Upon project completion and full buildout of Phase II, the onsite parking supply 

for the medical center would range from 1,300 to 2,000 spaces. The 261‐bed hospital in Phase II would be 

L‐shaped, running along 16th and 4th Streets on the eastern portion of Blocks 38 and 39 with the future 

parking structure west of the hospital, along Owens Street.  The Phase II parking structure would occupy 

the western part of the site with three access points.  Under Phase II, ingress/egress into the garage would 

be provided from the new Parking Structure Road at Owens and North and South Connector Roads. 

 

Page 152: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 48 ‐ 

The modified project would  include a 626‐space parking structure at 105  feet tall as part of  the Phase  I 

project.  It would  be  located  further  north,  closer  towards  16th  Street,  along  the  future Owen  Street 

extension.  Compared  to  the  previously  proposed  project,  which  would  include  475  surface  parking 

spaces, the revised project would include approximately 429 surface parking spaces on the remainder of 

Blocks 38 and 39. Thirteen spaces would be provided on  the east  lot, at  the south end of  the proposed 

hospital  across  the  future  4th  Street  extension.    Therefore,  approximately  442  surface  parking  spaces 

would be provided in Phase I.  The total number of parking spaces provided in Phase I would decrease 

by approximately seven spaces and would total approximately 1,068 spaces. With the decrease of seven 

parking spaces in Phase I, at full buildout of Phase II, the onsite parking supply could also decrease by 

approximately seven spaces to approximately 1,290 to 1,990 spaces. 

 

In the revised project, the location of the Phase I parking structure would be located further north, closer 

towards 16th Street, just south of North Connector Road, along the future Owen Street extension. Similar 

to  the original proposed project, access  to  the parking  structure and associated  surface parking  spaces 

would be  from Owens or 4th Streets via  the North and South Connector Roads, and  from  the Owens 

driveway at what  is now proposed  to be Parking Structure Road. However,  there would only be one 

ingress/egress to the revised parking garage from the interior connector road. Aside from this change, no 

other revisions are currently proposed. Subsequent project‐level environment review would be required 

once specific project design is available for Phase II. 

 

Describe how project was analyzed in earlier environmental document: 

 

An  expanded  Transportation  Study was  prepared  for  the Medical  Center  at Mission  Bay  EIR.7  The 

Transportation Study  evaluated both  the Phase  I  and  future buildout of  the Phase  II development.  In 

addition, the traffic study evaluated two potential alternatives for the operation of 4th Street through the 

Medical Center site. Both alternatives would convert the proposed 4th Street right‐of‐way to University of 

California property. 

 

Based on the analysis contained with the Transportation Study, traffic impacts resulting from Phase I of 

the Medical  Center  at Mission  Bay would  be  less  than  significant,  as  all  study  intersections would 

continue to operate at level‐of‐service D or better. 

 

At the completion Phase II, the Medical Center at Mission Bay EIR concluded that that the operation of 

the full buildout, would increase traffic at intersections on adjacent roadways.  The significant impact to 

the  southbound  approach  of Owens  Street  at  16th  Street  identified  in  the  LRDP Amendment  #2  EIR 

would still occur with the proposed project. Mitigation Measure 4.11‐2a from the LRDP Amendment #2 

EIR  identifies modifications  to  the  Owens  Street  lane  configurations  (i.e.  restriping)  to mitigate  this 

impact. Implementation of the re‐striping at this location would improve the operating conditions at this 

intersection to an acceptable LOS D (with an average delay of 50.3 seconds) during the p.m. peak hour.  

 

In addition, a new potential impact could result from the proposed project in Phase II if all parking access 

to the Medical Center  is from a stop‐controlled approach at the garage access at Owens Street, halfway 

between  16th  and Mariposa  Streets.  The  “T”  intersection would  operate  at  an  unacceptable  LOS  F. 

Implementation  of  a  traffic  signal  at  this  location  would  improve  the  operating  conditions  at  this 

intersection to an acceptable LOS B (with an average delay of 15.5 seconds) during the p.m. peak hour.  

 

7 Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation Study, March 2008.  

Page 153: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 49 ‐ 

Mitigation Measure MCMB.6‐3  from  the Medical Center at Mission Bay EIR would  require  that UCSF 

conduct a project‐level CEQA review at the time the Phase II development is considered for approval. In 

addition,  in  order  to  determine  the  need  for  LOS  improvements  on Owens  Street,  between  16th  and 

Mariposa Streets, at Center Garage Access (now Parking Structure Road), such as a traffic signal, UCSF 

would coordinate with the City of San Francisco in the periodic update of the Mission Bay traffic triggers 

survey and would monitor on‐site parking access and circulation in order to determine the need for LOS 

improvements.  

 

Implementation of the restriping of southbound Owens Street at 16th Street would reduce this potential 

Phase II impact to a less‐than‐significant level. The need for LOS improvements on Owens Street at the 

Parking  Structure  Road  in  Phase  II  remains  speculative  pending  a  project‐level  design  of  parking 

requirements and project‐level traffic and circulation evaluation.  

 

The estimated parking demand for Phase I would be approximately 900 spaces (390 spaces for patients 

and visitors and 510 spaces for staff).   As noted previously, the proposed onsite parking supply for the 

medical  center  in  Phase  I  is  approximately  1,075  spaces  (600  spaces  in  the  parking  structure  and 

approximately  475  surface  parking  spaces). Therefore,  the  proposed  parking  supply  in Phase  I  (1,075 

spaces)  could  accommodate  the  anticipated demand  (900  spaces)  and  the proposed project would not 

result in a shortfall of parking capacity under Phase I.  

 

Under Phase II, the estimated parking demand at full buildout would be approximately 1,760 spaces (740 

spaces  for patients  and visitors  and 1,020  for  staff). As noted previously,  the proposed onsite parking 

supply for the medical center in Phase II would range from approximately 1,300 to 2,000 spaces, resulting 

in a potential shortfall in parking supply. As stated in the Medical Center at Mission Bay EIR, as part of 

the proposed project, (as it does at other UCSF campus sites), UCSF would monitor parking demand at 

each  phase  of  development  and  adjust  parking  supply  as  demand warrants.  Should  the  demand  for 

parking exceed onsite supply, priority for onsite parking would be given to patients and visitors, and if 

necessary, UCSF would consider offsite parking  to satisfy  the anticipated staff demand. The additional 

parking  supply  could  be  accommodated  on  the UCSF Mission  Bay  research  campus,  if  available,  or 

elsewhere in the project vicinity. As the Mission Bay Campus develops, UCSF (through its Transportation 

Services Office) will make efforts to educate faculty, staff and students about transit options in order to 

reduce  auto  usage  and  parking  demand.  The Medical Center  at Mission  Bay  EIR  concluded  that  the 

potential parking shortfall under the full project buildout under Phase II would be less than significant.  

 

The Medical Center at Mission Bay EIR  concluded  that  the  construction and operation of  the Medical 

Center  at Mission Bay would not  cause  a  substantial  adverse  impact  to  transit, pedestrian, bicycle, or 

parking conditions, nor result in inadequate emergency access.  

 

Describe how the minor project changes affect the earlier environmental analysis: 

 

While the number of parking spaces in the parking structure would increase from 600 to 626, the number 

of  surface  spaces  would  decrease  from  475  to  approximately  442.  Therefore,  the  overall  number  of 

parking spaces would decrease by about seven spaces. While minor, the potential changes to the traffic 

analysis contained in the Medical Center at Mission Bay EIR will be evaluated and discussed in the SEIR. 

Page 154: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 50 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

17. UTILITIES AND SERVICE SYSTEMS

‐‐ Would the project:    

 

a)  Exceed  wastewater  treatment  requirements  of  the 

applicable Regional Water Quality Control Board? □  ■ 

 

b) Require or result in the construction of new water or 

wastewater treatment facilities or expansion of existing 

facilities,  the  construction  of  which  could  cause 

significant environmental effects? 

□  ■ 

 

c) Require  or  result  in  the  construction  of  new  storm 

water  drainage  facilities  or  expansion  of  existing 

facilities,  the  construction  of  which  could  cause 

significant environmental effects? 

□  ■ 

 

d) Have sufficient water supplies available to serve the 

project from existing entitlements and resources, or are 

new or expanded entitlements needed? 

□  ■ 

 

e)  Result  in  a  determination  by  the  wastewater 

treatment  provider,  which  serves  or  may  serve  the 

project  that  it  has  adequate  capacity  to  serve  the 

project’s  projected  demand  in  addition  to  the 

provider’s existing commitments? 

□  ■ 

 

f)  Be  served  by  a  landfill  with  sufficient  permitted 

capacity  to  accommodate  the  project’s  solid  waste 

disposal needs? 

□  ■ 

 

g)  Comply  with  applicable  federal,  state,  and  local 

statutes and regulations related to solid waste? □  ■ 

 

h) Result  in  the wasteful,  inefficient  and  unnecessary 

consumption  of  energy  (see  CEQA  Statutes  Section 

21100(b)(3))? 

□  ■ 

 

i)  Exceed  the  applicable  LRDP  EIR  standard  of 

significance  by  requiring  or  resulting  in  the 

construction  of new  electrical  or natural  gas  facilities, 

□ ■

Page 155: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 51 ‐ 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

which would cause significant environmental effects? 

Standards of Significance 

The impact questions above constitute the significance standards for this environmental topic. 

Discussion of Checklist Questions 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest 

portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in 

Phase  I  and  shift  the  location  of  the  parking  structure  to  the  north.  The modified  project would  not 

include any parking  levels below grade. All other aspects of  the Phase  I and Phase  II project  that was 

analyzed in the Medical Center at Mission Bay EIR would remain the same. 

 

Describe how the project is analyzed under this CEQA checklist topic: 

 

The LRDP Amendment  #2‐ Hospital Replacement EIR  evaluated  the demand  for utilities, energy, and 

service systems by the hospital replacement program as compared to existing and determined less‐than‐

significant  impact.  The Medical  Center  at Mission  Bay  EIR  provided  an  updated  assessment  of  the 

medical  center project  to evaluate  the potential  impacts  to water  supply  systems, wastewater disposal 

systems, and energy consumption and determined that the project project’s demand on utilities, energy 

and service systems would be less than significant and no mitigation measure would be necessary. . 

 

While the revised parking garage is slightly larger, the proposed project would not change the analysis or 

conclusions  reached  in  in  the Medical  Center  at Mission  Bay  EIR  and  impacts  would  be  less  than 

significant. Therefore, no further environmental analysis is required in the SEIR. 

Page 156: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 52 ‐ 

 

Issues 

Additional 

Project‐

level 

Impact 

Analysis 

Required 

Project Impact 

Adequately 

Addressed in 

Earlier 

Environmental 

Document 

18. MANDATORY FINDINGS OF SIGNIFICANCE – The lead agency shall find that 

a project may have a significant effect on the environment and thereby require an EIR 

to be prepared for the project where there is substantial evidence, in light of the whole 

record, that any of the following conditions may occur.  Where prior to commencement 

of  the  environmental  analysis  a  project  proponent  agrees  to mitigation measures  or 

project modifications  that would  avoid  any  significant  effect  on  the  environment  or 

would mitigate the significant environmental effect, a lead agency need not prepare an 

EIR  solely  because  without mitigation  the  environmental  effects  would  have  been 

significant (per Section 15065 of the State CEQA Guidelines): 

 

a) Does  the  project  have  the  potential  to  degrade  the 

quality  of  the  environment,  substantially  reduce  the 

habitat  of  a  fish  or  wildlife  species,  cause  a  fish  or 

wildlife  population  to  drop  below  self‐sustaining 

levels,  threaten  to  eliminate  a  plant  or  animal 

community, substantially reduce the number or restrict 

the  range  of  a  rare  or  endangered plant  or  animal  or 

eliminate  important  examples  of  the major periods  of 

California history or prehistory? 

□  ■ 

 

b) Does  the project have  impacts  that are  individually 

limited, but cumulatively considerable? (“Cumulatively 

considerable” means  that  the  incremental  effects  of  a 

project are significant when viewed in connection with 

the effects of past projects,  the effects of other current 

projects,  and  the  effects of past, present  and probable 

future projects)? 

■  □ 

 

c) Does  the  project  have  environmental  effects which 

will cause substantial adverse effects on human beings, 

either directly or indirectly? 

■ □ 

 

Relevant elements of project: 

 

The  construction  of  the  Phase  I Medical  Center  at Mission  Bay  is  currently  underway. A  600‐space 

parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed  in  the Medical Center at 

Mission Bay EIR at the southwest portion of the site as part of Phase I. 

 

Discussion of Potential Project Impacts: 

Page 157: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Initial Study for UCSF Medical Center at Mission Bay Phase I Garage 

‐ 53 ‐ 

18a)  The modifications  to  the  proposed  project would  not  affect  fish  or wildlife  habitat,  populations, 

communities, or substantially reduce  the number or restrict  the range of a rare or endangered plant or 

animal or eliminate important examples of the major periods of California history or prehistory.  

 

18 b‐c):   An  evaluation of  the proposed project’s potential  cumulatively  considerable  impacts  and  the 

project’s potential to result in substantial effects on human beings will be included in the SEIR. 

 

VI. SUPPORTING INFORMATION SOURCES  Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation 

Study, March 2008. 

 

ESA, memo to Lori Yamauchi, Assistant Vice Chancellor UCSF Campus Planning, Technical 

Memorandum Potential Wind Conditions, UCSF Medical Center at Mission Bay, December 3, 

2010. 

 

San Francisco Redevelopment Agency, Design for Development of the Mission Bay South Plan Area, 

March 16, 2004. Available at: http://www.sfredevelopment.org/Modules/ShowDocument.aspx?documentid=787 , accessed 

January 20, 2011. 

 

San Francisco Redevelopment Agency, Redevelopment Plan for the Mission Bay South Redevelopment 

Project, November 2, 1998. Available at: 

http://www.sfredevelopment.org/Modules/ShowDocument.aspx?documentid=767, accessed 

January 20, 2011. 

 

VII. INITIAL STUDY PREPARERS 

 

UCSF Campus Planning 

654 Minnesota Street, San Francisco CA 94143‐0286 

Page 158: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 

Page 159: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

  

 

APPENDIX B AIR EMISSIONS ESTIMATES 

Page 160: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 

Page 161: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 1

File Name: C:\Users\pfranke\AppData\Roaming\Urbemis\Version9a\Projects\Medical Center Garage 3.urb924

Project Name: Medical Center Garage 3

Project Location: San Francisco County

On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006

Off-Road Vehicle Emissions Based on: OFFROAD2007

Combined Annual Emissions Reports (Tons/Year)

Urbemis 2007 Version 9.2.4

Percent Reduction 0.00 20.00 16.67 NaN NaN NaN 20.00

TOTALS (tons/year, mitigated) 0.22 0.12 0.10 0.00 0.00 0.00 141.10

TOTALS (tons/year, unmitigated) 0.22 0.15 0.12 0.00 0.00 0.00 176.38

AREA SOURCE EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

2008 TOTALS (tons/year unmitigated) 2.43 2.43 3.06 0.00 0.03 0.12 0.14 0.01 0.11 0.12 448.52

2008 TOTALS (tons/year mitigated) 2.43 2.43 3.06 0.00 0.02 0.12 0.14 0.01 0.11 0.11 448.52

Percent Reduction 0.00 0.00 0.00 0.00 18.23 0.00 3.27 13.14 0.00 0.85 0.00

Percent Reduction 0.00 0.00 0.00 0.00 43.34 0.00 26.02 43.27 0.00 11.02 0.00

2007 TOTALS (tons/year unmitigated) 0.04 0.34 0.18 0.00 0.03 0.02 0.04 0.01 0.02 0.02 27.01

2007 TOTALS (tons/year mitigated) 0.04 0.34 0.18 0.00 0.01 0.02 0.03 0.00 0.02 0.02 27.01

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust

PM2.5 CO2

CONSTRUCTION EMISSION ESTIMATES

Summary Report:

Page 162: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 2

Construction Unmitigated Detail Report:

CONSTRUCTION EMISSION ESTIMATES Annual Tons Per Year, Unmitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2

Percent Reduction 0.00 0.73 0.06 0.00 0.00 0.00 0.98

TOTALS (tons/year, mitigated) 2.99 4.06 33.35 0.03 6.46 1.22 3,566.85

TOTALS (tons/year, unmitigated) 2.99 4.09 33.37 0.03 6.46 1.22 3,602.13

SUM OF AREA SOURCE AND OPERATIONAL EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

Percent Reduction 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTALS (tons/year, mitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75

TOTALS (tons/year, unmitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75

OPERATIONAL (VEHICLE) EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

Page 163: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 3

2007 0.04 0.34 0.18 0.00 0.04 0.02 27.010.03 0.02 0.01 0.02

0.00Asphalt 12/28/2007-01/11/2008 0.00 0.01 0.01 0.00 0.00 1.170.00 0.00 0.00 0.00

Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01

Paving Worker Trips 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18

Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 0.00 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.98

0.04Fine Grading 11/30/2007-01/11/2008

0.04 0.33 0.17 0.00 0.02 25.840.03 0.02 0.01 0.02

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.12

Fine Grading Dust 0.00 0.00 0.00 0.00 0.03 0.00 0.03 0.01 0.00 0.01 0.00

Fine Grading Off Road Diesel 0.04 0.33 0.16 0.00 0.00 0.02 0.02 0.00 0.02 0.02 24.72

Page 164: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 4

20 lbs per acre-day

Fugitive Dust Level of Detail: Default

Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description

Maximum Daily Acreage Disturbed: 0.12

Total Acres Disturbed: 0.5

Phase Assumptions

2008 2.43 2.43 3.06 0.00 0.14 0.12 448.520.03 0.12 0.01 0.11

0.12Building 01/11/2008-08/22/2008 0.26 2.24 2.92 0.00 0.10 430.130.01 0.11 0.01 0.10

Building Worker Trips 0.06 0.10 1.64 0.00 0.01 0.00 0.01 0.00 0.00 0.00 138.02

Building Vendor Trips 0.09 1.30 0.87 0.00 0.01 0.05 0.06 0.00 0.05 0.05 220.19

Building Off Road Diesel 0.11 0.84 0.41 0.00 0.00 0.05 0.05 0.00 0.05 0.05 71.92

0.00Coating 08/08/2008-09/05/2008 2.14 0.00 0.03 0.00 0.00 2.550.00 0.00 0.00 0.00

Coating Worker Trips 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.55

Architectural Coating 2.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.01Asphalt 12/28/2007-01/11/2008 0.01 0.06 0.04 0.00 0.00 5.270.00 0.01 0.00 0.00

Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06

Paving Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80

Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 0.01 0.06 0.03 0.00 0.00 0.01 0.01 0.00 0.00 0.00 4.41

0.02Fine Grading 11/30/2007-01/11/2008

0.02 0.13 0.07 0.00 0.01 10.570.01 0.01 0.00 0.01

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.46

Fine Grading Dust 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.00 0.00

Fine Grading Off Road Diesel 0.01 0.13 0.06 0.00 0.00 0.01 0.01 0.00 0.01 0.01 10.11

Page 165: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 5

Construction Mitigated Detail Report:

1 Cranes (399 hp) operating at a 0.43 load factor for 4 hours per day

2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day

Phase: Building Construction 1/11/2008 - 8/22/2008 - Default Building Construction Description

Off-Road Equipment:

Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Phase: Architectural Coating 8/8/2008 - 9/5/2008 - Default Architectural Coating Description

Rule: Residential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Residential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day

On Road Truck Travel (VMT): 0

Off-Road Equipment:

1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day

4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day

1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day

1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day

Phase: Paving 12/28/2007 - 1/11/2008 - Default Paving Description

Acres to be Paved: 0.12

Off-Road Equipment:

Page 166: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 6

CONSTRUCTION EMISSION ESTIMATES Annual Tons Per Year, Mitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2

2007 0.04 0.34 0.18 0.00 0.03 0.02 27.010.01 0.02 0.00 0.02

0.00Asphalt 12/28/2007-01/11/2008 0.00 0.01 0.01 0.00 0.00 1.170.00 0.00 0.00 0.00

Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01

Paving Worker Trips 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18

Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 0.00 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.98

0.03Fine Grading 11/30/2007-01/11/2008

0.04 0.33 0.17 0.00 0.02 25.840.01 0.02 0.00 0.02

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.12

Fine Grading Dust 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.00 0.00

Fine Grading Off Road Diesel 0.04 0.33 0.16 0.00 0.00 0.02 0.02 0.00 0.02 0.02 24.72

Page 167: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 7

2008 2.43 2.43 3.06 0.00 0.14 0.11 448.520.02 0.12 0.01 0.11

0.12Building 01/11/2008-08/22/2008 0.26 2.24 2.92 0.00 0.10 430.130.01 0.11 0.01 0.10

Building Worker Trips 0.06 0.10 1.64 0.00 0.01 0.00 0.01 0.00 0.00 0.00 138.02

Building Vendor Trips 0.09 1.30 0.87 0.00 0.01 0.05 0.06 0.00 0.05 0.05 220.19

Building Off Road Diesel 0.11 0.84 0.41 0.00 0.00 0.05 0.05 0.00 0.05 0.05 71.92

0.00Coating 08/08/2008-09/05/2008 2.14 0.00 0.03 0.00 0.00 2.550.00 0.00 0.00 0.00

Coating Worker Trips 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.55

Architectural Coating 2.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.01Asphalt 12/28/2007-01/11/2008 0.01 0.06 0.04 0.00 0.00 5.270.00 0.01 0.00 0.00

Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06

Paving Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80

Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 0.01 0.06 0.03 0.00 0.00 0.01 0.01 0.00 0.00 0.00 4.41

0.01Fine Grading 11/30/2007-01/11/2008

0.02 0.13 0.07 0.00 0.01 10.570.01 0.01 0.00 0.01

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.46

Fine Grading Dust 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.00 0.00

Fine Grading Off Road Diesel 0.01 0.13 0.06 0.00 0.00 0.01 0.01 0.00 0.01 0.01 10.11

For Soil Stablizing Measures, the Water exposed surfaces 2x daily watering mitigation reduces emissions by:

PM10: 55% PM25: 55%

The following mitigation measures apply to Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description

Construction Related Mitigation Measures

Page 168: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 8

Architectural Coatings 0.21

Consumer Products 0.00

Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Landscape

Natural Gas 0.01 0.15 0.12 0.00 0.00 0.00 176.38

TOTALS (tons/year, unmitigated) 0.22 0.15 0.12 0.00 0.00 0.00 176.38

Source ROG NOx CO SO2 PM10 PM2.5 CO2

AREA SOURCE EMISSION ESTIMATES Annual Tons Per Year, Unmitigated

Area Source Unmitigated Detail Report:

Area Source Mitigation Measures Selected

Architectural Coatings 0.21

Consumer Products 0.00

Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Landscape

Natural Gas 0.01 0.12 0.10 0.00 0.00 0.00 141.10

TOTALS (tons/year, mitigated) 0.22 0.12 0.10 0.00 0.00 0.00 141.10

Source ROG NOx CO SO2 PM10 PM2.5 CO2

AREA SOURCE EMISSION ESTIMATES Annual Tons Per Year, Mitigated

Industrial Increase Energy Efficiency Beyond Title 24 20.00

Mitigation Description Percent Reduction

Area Source Mitigated Detail Report:

Area Source Changes to Defaults

Page 169: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 9

Residential Mitigation Measures

Operational Mitigation Options Selected

The Presence of Local-Serving Retail checkbox was NOT selected.

Percent Reduction in Trips is 0%

Inputs Selected:

---------------------------------------------------------------

Non-Residential Local-Serving Retail Mitigation

Nonresidential Mitigation Measures

OPERATIONAL EMISSION ESTIMATES Annual Tons Per Year, Mitigated

Warehouse 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75

TOTALS (tons/year, mitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75

Source ROG NOX CO SO2 PM10 PM25 CO2

Operational Mitigated Detail Report:

OPERATIONAL EMISSION ESTIMATES Annual Tons Per Year, Unmitigated

Warehouse 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75

TOTALS (tons/year, unmitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75

Source ROG NOX CO SO2 PM10 PM25 CO2

Operational Unmitigated Detail Report:

Does not include correction for passby trips

Does not include double counting adjustment for internal trips

Operational Settings:

Page 170: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 10

Heavy-Heavy Truck 33,001-60,000 lbs 0.1 0.0 0.0 100.0

Med-Heavy Truck 14,001-33,000 lbs 1.6 0.0 18.8 81.2

Motor Home 0.2 0.0 100.0 0.0

Other Bus 0.1 0.0 100.0 0.0

School Bus 0.1 0.0 0.0 100.0

Motorcycle 3.5 51.4 48.6 0.0

Urban Bus 0.3 0.0 0.0 100.0

Light Truck < 3750 lbs 11.0 0.0 99.1 0.9

Light Auto 61.0 0.3 99.5 0.2

Lite-Heavy Truck 10,001-14,000 lbs 0.5 0.0 60.0 40.0

Lite-Heavy Truck 8501-10,000 lbs 0.5 0.0 80.0 20.0

Med Truck 5751-8500 lbs 4.7 0.0 100.0 0.0

Light Truck 3751-5750 lbs 16.4 0.0 100.0 0.0

Vehicle Fleet Mix

Vehicle Type Percent Type Non-Catalyst Catalyst Diesel

Warehouse 13.08 1000 sq ft 200.00 2,616.00 20,633.70

2,616.00 20,633.70

Summary of Land Uses

Land Use Type Acreage Trip Rate Unit Type No. Units Total Trips Total VMT

Emfac: Version : Emfac2007 V2.3 Nov 1 2006

Analysis Year: 2012 Season: Annual

Page 171: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:15:28 PM

Page: 11

% of Trips - Residential 32.9 18.0 49.1

Trip speeds (mph) 35.0 35.0 35.0 35.0 35.0 35.0

% of Trips - Commercial (by land use)

Warehouse 25.0 12.5 62.5

Rural Trip Length (miles) 16.8 7.1 7.9 14.7 6.6 6.6

Urban Trip Length (miles) 10.8 7.3 7.5 9.5 7.4 7.4

Travel Conditions

Home-Work Home-Shop Home-Other Commute Non-Work Customer

Residential Commercial

Operational Changes to Defaults

Page 172: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 1

File Name: C:\Users\pfranke\AppData\Roaming\Urbemis\Version9a\Projects\Medical Center Garage 3.urb924

Project Name: Medical Center Garage 3

Project Location: San Francisco County

On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006

Off-Road Vehicle Emissions Based on: OFFROAD2007

Combined Summer Emissions Reports (Pounds/Day)

Urbemis 2007 Version 9.2.4

Percent Reduction 0.81 20.99 20.59 NaN NaN NaN 20.00

TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16

TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44

AREA SOURCE EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

2008 TOTALS (lbs/day unmitigated) 207.30 69.39 60.30 0.04 2.60 3.89 6.49 0.57 3.57 4.14 8,863.45

2008 TOTALS (lbs/day mitigated) 207.30 69.39 60.30 0.04 1.55 3.89 5.44 0.35 3.57 3.92 8,863.45

2007 TOTALS (lbs/day mitigated) 6.04 43.98 25.01 0.00 1.37 2.71 4.08 0.29 2.49 2.78 3,520.26

2007 TOTALS (lbs/day unmitigated) 6.04 43.98 25.01 0.00 2.41 2.71 5.12 0.51 2.49 3.00 3,520.26

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust

PM2.5 CO2

CONSTRUCTION EMISSION ESTIMATES

Summary Report:

Page 173: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 2

Construction Unmitigated Detail Report:

CONSTRUCTION EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2

Time Slice 11/30/2007-12/27/2007 Active Days: 20

3.56 29.72 15.47 0.00 3.90 1.87 2,349.392.40 1.49 0.50 1.37

3.90Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

Percent Reduction 0.06 0.87 0.08 0.00 0.00 0.00 0.94

TOTALS (lbs/day, mitigated) 16.04 19.30 179.67 0.20 35.38 6.70 20,438.20

TOTALS (lbs/day, unmitigated) 16.05 19.47 179.81 0.20 35.38 6.70 20,631.48

SUM OF AREA SOURCE AND OPERATIONAL EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

Percent Reduction 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTALS (lbs/day, mitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04

TOTALS (lbs/day, unmitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04

OPERATIONAL (VEHICLE) EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

Page 174: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 3

Time Slice 12/28/2007-12/31/2007 Active Days: 2

6.04 43.98 25.01 0.00 5.12 3.00 3,520.262.41 2.71 0.51 2.49

3.90Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12

Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23

Time Slice 1/1/2008-1/10/2008 Active Days: 8

5.68 41.56 24.07 0.00 4.98 2.87 3,520.212.41 2.57 0.51 2.36

3.82Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Page 175: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 4

Time Slice 1/11/2008-1/11/2008 Active Days: 1

8.88 69.39 60.30 0.04 6.49 4.14 8,863.452.60 3.89 0.57 3.57

3.82Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Time Slice 1/14/2008-8/7/2008 Active Days: 149

3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

Page 176: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 5

20 lbs per acre-day

Fugitive Dust Level of Detail: Default

Off-Road Equipment:

On Road Truck Travel (VMT): 0

Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description

Maximum Daily Acreage Disturbed: 0.12

Total Acres Disturbed: 0.5

1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day

1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day

1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

Phase Assumptions

Time Slice 8/25/2008-9/5/2008 Active Days: 10

204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 8/8/2008-8/22/2008 Active Days: 11

207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

Page 177: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 6

Construction Mitigated Detail Report:

CONSTRUCTION EMISSION ESTIMATES Summer Pounds Per Day, Mitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2

Phase: Architectural Coating 8/8/2008 - 9/5/2008 - Default Architectural Coating Description

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day

1 Cranes (399 hp) operating at a 0.43 load factor for 4 hours per day

2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day

Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Residential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Residential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day

1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day

Off-Road Equipment:

Phase: Paving 12/28/2007 - 1/11/2008 - Default Paving Description

Acres to be Paved: 0.12

Phase: Building Construction 1/11/2008 - 8/22/2008 - Default Building Construction Description

Off-Road Equipment:

1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

Page 178: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 7

Time Slice 11/30/2007-12/27/2007 Active Days: 20

3.56 29.72 15.47 0.00 2.85 1.66 2,349.391.36 1.49 0.29 1.37

2.85Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

Time Slice 12/28/2007-12/31/2007 Active Days: 2

6.04 43.98 25.01 0.00 4.08 2.78 3,520.261.37 2.71 0.29 2.49

2.85Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12

Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23

Page 179: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 8

Time Slice 1/1/2008-1/10/2008 Active Days: 8

5.68 41.56 24.07 0.00 3.94 2.65 3,520.211.37 2.57 0.29 2.36

2.78Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Page 180: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 9

Time Slice 1/11/2008-1/11/2008 Active Days: 1

8.88 69.39 60.30 0.04 5.44 3.92 8,863.451.55 3.89 0.35 3.57

2.78Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Time Slice 1/14/2008-8/7/2008 Active Days: 149

3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

Page 181: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 10

Time Slice 8/25/2008-9/5/2008 Active Days: 10

204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 8/8/2008-8/22/2008 Active Days: 11

207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

For Soil Stablizing Measures, the Water exposed surfaces 2x daily watering mitigation reduces emissions by:

PM10: 55% PM25: 55%

The following mitigation measures apply to Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description

Construction Related Mitigation Measures

Page 182: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 11

Architectural Coatings 1.17

Consumer Products 0.00

Hearth - No Summer Emissions

Landscape

Natural Gas 0.06 0.81 0.68 0.00 0.00 0.00 966.44

TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44

Source ROG NOx CO SO2 PM10 PM2.5 CO2

AREA SOURCE EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated

Area Source Unmitigated Detail Report:

Area Source Mitigation Measures Selected

Architectural Coatings 1.17

Consumer Products 0.00

Hearth - No Summer Emissions

Landscape

Natural Gas 0.05 0.64 0.54 0.00 0.00 0.00 773.16

TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16

Source ROG NOx CO SO2 PM10 PM2.5 CO2

AREA SOURCE EMISSION ESTIMATES Summer Pounds Per Day, Mitigated

Industrial Increase Energy Efficiency Beyond Title 24 20.00

Mitigation Description Percent Reduction

Area Source Mitigated Detail Report:

Area Source Changes to Defaults

Page 183: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 12

Residential Mitigation Measures

Operational Mitigation Options Selected

The Presence of Local-Serving Retail checkbox was NOT selected.

Percent Reduction in Trips is 0%

Inputs Selected:

---------------------------------------------------------------

Non-Residential Local-Serving Retail Mitigation

Nonresidential Mitigation Measures

OPERATIONAL EMISSION ESTIMATES Summer Pounds Per Day, Mitigated

Warehouse 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04

TOTALS (lbs/day, mitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04

Source ROG NOX CO SO2 PM10 PM25 CO2

Operational Mitigated Detail Report:

OPERATIONAL EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated

Warehouse 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04

TOTALS (lbs/day, unmitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04

Source ROG NOX CO SO2 PM10 PM25 CO2

Operational Unmitigated Detail Report:

Does not include correction for passby trips

Does not include double counting adjustment for internal trips

Operational Settings:

Page 184: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 13

Heavy-Heavy Truck 33,001-60,000 lbs 0.1 0.0 0.0 100.0

Med-Heavy Truck 14,001-33,000 lbs 1.6 0.0 18.8 81.2

Motor Home 0.2 0.0 100.0 0.0

Other Bus 0.1 0.0 100.0 0.0

School Bus 0.1 0.0 0.0 100.0

Motorcycle 3.5 51.4 48.6 0.0

Urban Bus 0.3 0.0 0.0 100.0

Light Truck < 3750 lbs 11.0 0.0 99.1 0.9

Light Auto 61.0 0.3 99.5 0.2

Lite-Heavy Truck 10,001-14,000 lbs 0.5 0.0 60.0 40.0

Lite-Heavy Truck 8501-10,000 lbs 0.5 0.0 80.0 20.0

Med Truck 5751-8500 lbs 4.7 0.0 100.0 0.0

Light Truck 3751-5750 lbs 16.4 0.0 100.0 0.0

Vehicle Fleet Mix

Vehicle Type Percent Type Non-Catalyst Catalyst Diesel

Warehouse 13.08 1000 sq ft 200.00 2,616.00 20,633.70

2,616.00 20,633.70

Summary of Land Uses

Land Use Type Acreage Trip Rate Unit Type No. Units Total Trips Total VMT

Emfac: Version : Emfac2007 V2.3 Nov 1 2006

Analysis Year: 2012 Temperature (F): 85 Season: Summer

Page 185: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:17:06 PM

Page: 14

% of Trips - Residential 32.9 18.0 49.1

Trip speeds (mph) 35.0 35.0 35.0 35.0 35.0 35.0

% of Trips - Commercial (by land use)

Warehouse 25.0 12.5 62.5

Rural Trip Length (miles) 16.8 7.1 7.9 14.7 6.6 6.6

Urban Trip Length (miles) 10.8 7.3 7.5 9.5 7.4 7.4

Travel Conditions

Home-Work Home-Shop Home-Other Commute Non-Work Customer

Residential Commercial

Operational Changes to Defaults

Page 186: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:43 PM

Page: 1

File Name: C:\Users\pfranke\AppData\Roaming\Urbemis\Version9a\Projects\Medical Center Garage 3.urb924

Project Name: Medical Center Garage 3

Project Location: San Francisco County

On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006

Off-Road Vehicle Emissions Based on: OFFROAD2007

Combined Winter Emissions Reports (Pounds/Day)

Urbemis 2007 Version 9.2.4

Percent Reduction 0.81 20.99 20.59 NaN NaN NaN 20.00

TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16

TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44

AREA SOURCE EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

2008 TOTALS (lbs/day unmitigated) 207.30 69.39 60.30 0.04 2.60 3.89 6.49 0.57 3.57 4.14 8,863.45

2008 TOTALS (lbs/day mitigated) 207.30 69.39 60.30 0.04 1.55 3.89 5.44 0.35 3.57 3.92 8,863.45

2007 TOTALS (lbs/day mitigated) 6.04 43.98 25.01 0.00 1.37 2.71 4.08 0.29 2.49 2.78 3,520.26

2007 TOTALS (lbs/day unmitigated) 6.04 43.98 25.01 0.00 2.41 2.71 5.12 0.51 2.49 3.00 3,520.26

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust

PM2.5 CO2

CONSTRUCTION EMISSION ESTIMATES

Summary Report:

Page 187: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:43 PM

Page: 2

Construction Unmitigated Detail Report:

CONSTRUCTION EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2

Time Slice 11/30/2007-12/27/2007 Active Days: 20

3.56 29.72 15.47 0.00 3.90 1.87 2,349.392.40 1.49 0.50 1.37

3.90Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

Percent Reduction 0.06 0.60 0.07 0.00 0.00 0.00 1.08

TOTALS (lbs/day, mitigated) 17.09 28.06 188.80 0.17 35.38 6.70 17,756.75

TOTALS (lbs/day, unmitigated) 17.10 28.23 188.94 0.17 35.38 6.70 17,950.03

SUM OF AREA SOURCE AND OPERATIONAL EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

Percent Reduction 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTALS (lbs/day, mitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59

TOTALS (lbs/day, unmitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59

OPERATIONAL (VEHICLE) EMISSION ESTIMATES

ROG NOx CO SO2 PM10 PM2.5 CO2

Page 188: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:43 PM

Page: 3

Time Slice 12/28/2007-12/31/2007 Active Days: 2

6.04 43.98 25.01 0.00 5.12 3.00 3,520.262.41 2.71 0.51 2.49

3.90Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12

Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23

Time Slice 1/1/2008-1/10/2008 Active Days: 8

5.68 41.56 24.07 0.00 4.98 2.87 3,520.212.41 2.57 0.51 2.36

3.82Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Page 189: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 4

Time Slice 1/11/2008-1/11/2008 Active Days: 1

8.88 69.39 60.30 0.04 6.49 4.14 8,863.452.60 3.89 0.57 3.57

3.82Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Time Slice 1/14/2008-8/7/2008 Active Days: 149

3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

Page 190: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 5

20 lbs per acre-day

Fugitive Dust Level of Detail: Default

Off-Road Equipment:

On Road Truck Travel (VMT): 0

Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description

Maximum Daily Acreage Disturbed: 0.12

Total Acres Disturbed: 0.5

1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day

1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day

1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

Phase Assumptions

Time Slice 8/25/2008-9/5/2008 Active Days: 10

204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 8/8/2008-8/22/2008 Active Days: 11

207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

Page 191: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 6

Construction Mitigated Detail Report:

CONSTRUCTION EMISSION ESTIMATES Winter Pounds Per Day, Mitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2

Phase: Architectural Coating 8/8/2008 - 9/5/2008 - Default Architectural Coating Description

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day

1 Cranes (399 hp) operating at a 0.43 load factor for 4 hours per day

2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day

Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Residential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Rule: Residential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day

1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day

Off-Road Equipment:

Phase: Paving 12/28/2007 - 1/11/2008 - Default Paving Description

Acres to be Paved: 0.12

Phase: Building Construction 1/11/2008 - 8/22/2008 - Default Building Construction Description

Off-Road Equipment:

1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day

1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

Page 192: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 7

Time Slice 11/30/2007-12/27/2007 Active Days: 20

3.56 29.72 15.47 0.00 2.85 1.66 2,349.391.36 1.49 0.29 1.37

2.85Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

Time Slice 12/28/2007-12/31/2007 Active Days: 2

6.04 43.98 25.01 0.00 4.08 2.78 3,520.261.37 2.71 0.29 2.49

2.85Fine Grading 11/30/2007-01/11/2008

3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32

1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12

Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23

Page 193: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 8

Time Slice 1/1/2008-1/10/2008 Active Days: 8

5.68 41.56 24.07 0.00 3.94 2.65 3,520.211.37 2.57 0.29 2.36

2.78Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Page 194: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 9

Time Slice 1/11/2008-1/11/2008 Active Days: 1

8.88 69.39 60.30 0.04 5.44 3.92 8,863.451.55 3.89 0.35 3.57

2.78Fine Grading 11/30/2007-01/11/2008

3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30

Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05

Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00

Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06

Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02

Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60

Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23

Time Slice 1/14/2008-8/7/2008 Active Days: 149

3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

Page 195: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 10

Time Slice 8/25/2008-9/5/2008 Active Days: 10

204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 8/8/2008-8/22/2008 Active Days: 11

207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21

0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00

Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99

Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21

Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52

Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32

Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39

For Soil Stablizing Measures, the Water exposed surfaces 2x daily watering mitigation reduces emissions by:

PM10: 55% PM25: 55%

The following mitigation measures apply to Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description

Construction Related Mitigation Measures

Page 196: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 11

Architectural Coatings 1.17

Consumer Products 0.00

Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Landscape

Natural Gas 0.06 0.81 0.68 0.00 0.00 0.00 966.44

TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44

Source ROG NOx CO SO2 PM10 PM2.5 CO2

AREA SOURCE EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated

Area Source Unmitigated Detail Report:

Area Source Mitigation Measures Selected

Architectural Coatings 1.17

Consumer Products 0.00

Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Landscape

Natural Gas 0.05 0.64 0.54 0.00 0.00 0.00 773.16

TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16

Source ROG NOx CO SO2 PM10 PM2.5 CO2

AREA SOURCE EMISSION ESTIMATES Winter Pounds Per Day, Mitigated

Industrial Increase Energy Efficiency Beyond Title 24 20.00

Mitigation Description Percent Reduction

Area Source Mitigated Detail Report:

Area Source Changes to Defaults

Page 197: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 12

Residential Mitigation Measures

Operational Mitigation Options Selected

The Presence of Local-Serving Retail checkbox was NOT selected.

Percent Reduction in Trips is 0%

Inputs Selected:

---------------------------------------------------------------

Non-Residential Local-Serving Retail Mitigation

Nonresidential Mitigation Measures

OPERATIONAL EMISSION ESTIMATES Winter Pounds Per Day, Mitigated

Warehouse 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59

TOTALS (lbs/day, mitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59

Source ROG NOX CO SO2 PM10 PM25 CO2

Operational Mitigated Detail Report:

OPERATIONAL EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated

Warehouse 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59

TOTALS (lbs/day, unmitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59

Source ROG NOX CO SO2 PM10 PM25 CO2

Operational Unmitigated Detail Report:

Does not include correction for passby trips

Does not include double counting adjustment for internal trips

Operational Settings:

Page 198: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 13

Heavy-Heavy Truck 33,001-60,000 lbs 0.1 0.0 0.0 100.0

Med-Heavy Truck 14,001-33,000 lbs 1.6 0.0 18.8 81.2

Motor Home 0.2 0.0 100.0 0.0

Other Bus 0.1 0.0 100.0 0.0

School Bus 0.1 0.0 0.0 100.0

Motorcycle 3.5 51.4 48.6 0.0

Urban Bus 0.3 0.0 0.0 100.0

Light Truck < 3750 lbs 11.0 0.0 99.1 0.9

Light Auto 61.0 0.3 99.5 0.2

Lite-Heavy Truck 10,001-14,000 lbs 0.5 0.0 60.0 40.0

Lite-Heavy Truck 8501-10,000 lbs 0.5 0.0 80.0 20.0

Med Truck 5751-8500 lbs 4.7 0.0 100.0 0.0

Light Truck 3751-5750 lbs 16.4 0.0 100.0 0.0

Vehicle Fleet Mix

Vehicle Type Percent Type Non-Catalyst Catalyst Diesel

Warehouse 13.08 1000 sq ft 200.00 2,616.00 20,633.70

2,616.00 20,633.70

Summary of Land Uses

Land Use Type Acreage Trip Rate Unit Type No. Units Total Trips Total VMT

Emfac: Version : Emfac2007 V2.3 Nov 1 2006

Analysis Year: 2012 Temperature (F): 40 Season: Winter

Page 199: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

1/24/2011 6:16:44 PM

Page: 14

% of Trips - Residential 32.9 18.0 49.1

Trip speeds (mph) 35.0 35.0 35.0 35.0 35.0 35.0

% of Trips - Commercial (by land use)

Warehouse 25.0 12.5 62.5

Rural Trip Length (miles) 16.8 7.1 7.9 14.7 6.6 6.6

Urban Trip Length (miles) 10.8 7.3 7.5 9.5 7.4 7.4

Travel Conditions

Home-Work Home-Shop Home-Other Commute Non-Work Customer

Residential Commercial

Operational Changes to Defaults

Page 200: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Bay Area Air Quality Management District Greenhouse Gas Model (BGM)   Version: 1.1.9 Beta

Copyright:

LINKS

Transportation

Area Source

Electricity and Natural Gas

Water and Wastewater

Solid Waste

AgricultureAssistance provided by:

Off-Road Equipment

Refrigerants

Mitigation

Carbon Sequestration

Enter data in yellow cells with values applicable to your project

Enter data in peach cells if you have information specific to your project; these values will be used in place of the default values

Summary Results

Open an Urbemis Project File

Step 1:  Enable MacrosMacros must be enabled for this model to operate correctly.  The method for enabling macros for this spreadsheet 

differs depending on the security settings in Excel.

Step 2:  Open an Urbemis Project File, or Refresh Urbemis DataBGM depends on the data and results from an URBEMIS project file.  Two URBEMIS files can be specified : a project file and (optionally) a baseline file. To open a file, or to refresh the data in this spreadsheet after an URBEMIS file has been modified,  go to the Settings tab by clicking on the Open an URBEMIS Project File link  to the right . Select the URBEMIS file(s) that you want to import and hit the refresh data button.  Please make sure that the Emfac Database Location is correct before clicking either of the Refresh buttons.

Step 4:  View ResultsThe Results Tab presents a graphical and tabular view of the results of the Greenhouse Gas Calculator.    Both a summary and detailed report  are included on the Results tab.  The user also has the option of selected  project specific mitigation on the Mitigation tab and on the Carbon Sequestration tab.

Step 3: Data Entry OptionsThe bright yellow areas on each tab represent data entry locations, if applicable to your project.  In some cases, there are optional data inputs (shown in peach).  Some tabs, such as transportation and area sources, do not require any data input, as results are imported directly from URBEMIS.  Certain other tabs ‐ electricty & natural gas, water & wastewater, and solid waste ‐ require some minor amount of user input, although most of the information used  to estimate emissions is imported from URBEMIS.  And for certain tabs, ‐ ag, off‐road, refrigerants, and carbon sequestration  ‐ the user must enter project specific information to obtain emission estimates.

1 of 4

Page 201: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Summary Results

Project Name: Medical Center Garage 3

Project and Baseline Years: 2012 2011

ResultsTransportation: 3,167.59 3,167.59

Area Source: 0.00 0.00

Electricity: 563.95 451.16

Natural Gas: 46.01 36.81

Water & Wastewater: 6.32 6.05

Solid Waste: 334.16 133.66

Agriculture: 0.00 0.00

Off‐Road Equipment: 0.00 0.00

Refrigerants: 0.00 0.00

Sequestration: N/A 0.00

Purchase of Offsets: N/A 0.00

Total: 4,118.02 3,795.27

Baseline is currently: ON

Unmitigated Project‐Baseline CO2e (metric 

tons/year)

Mitigated Project‐Baseline CO2e   

(metric tons/year)

2 of 4

Page 202: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Baseline is Currently: ON

Target Year:   2012 2011 Target Year: 2012 2011

Unmitigated Transportation Mitigated TransportationProject Baseline Project‐Baseline Project Baseline Project‐Baseline

Operational Emissions from URBEMIS (CO2 tons/year) 3,425.75 0.00 Operational Vehicles from URBEMIS (CO2 tons/year):  3,425.75 0.00

Metric Ton Adjustment (CO2 metric tons/year) 3,108.67 0.00 Metric Ton Adjustment (CO2 metric tons/year): 3,108.67 0.00

Pavley Regulation Adjustment (CO2 metric tons/year): 3,020.08 0.00 Pavley Regulation Adjustment (CO2 metric tons/year): 3,020.08 0.00

US EPA Adjustment (CO2e metric tons/year): 3,179.03 0.00 US EPA Adjustment (CO2e metric tons/year): 3,179.03 0.00

Low Carbon Fuels Rule Adjustment (CO2e metric tons/year) 3,167.59 0.00 Low Carbon Fuels Adjustment (CO2e metric tons/year): 3,167.59 0.00

Total (CO2e metric tons/year): 3,167.59 Total (CO2e metric tons/year): 3,167.59

The BGM User's Manual describes in detail each step used to convert URBEMIS's transportation CO2 emissions to total CO2e.

These steps include converting from English to Metric units, adjusting for the Pavley Rule, converting CO2 to CO2e, and adjusting for the Low Carbon Fuels Rule.  

Reference

Jump to the Following Transportation Related Tabs:

Transportation Detail for Operational Mitigation

Land Use Detail

Don't Need to 

Adjust this 

amt

Unadjusted 

Amount 

Affected by 

Pavley Adjusted Adusted Adusted Adusted Adjusted

Not Affected 

by Pavley

LDA/ LDT1/ 

LDT2/ MDV LDA LDT1 LDT2 MDV 4 totaled

Pavley Calculations ‐ Project Unmitigated 520.13 2,588.54 1,249.26 376.00 589.67 285.02 2,499.96

Pavley Calculations ‐ Baseline Unmitigated 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Pavley Calculations ‐ Project Mitigated 520.13 2,588.54 1,249.26 376.00 589.67 285.02 2,499.96

Pavley Calculations ‐ Baseline Mitigated 0.00 0.00 0.00 0.00 0.00 0.00 0.00

U.S. EPA assumption that GHG emissions from other pollutants ‐ CH4, N20, and hydrofluorcarbons (HFCs) from leaking air conditioners account for 5 percent of emissions from vehicles, after accounting for global warming potentail of each GHG.

Transportation

3 of 4

Page 203: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

Unmitigated CO2 (metric tpy) CH4 (metric tpy) N2O (metric tpy) CO2e (metric tpy) % of Total

Transportation*: 3,167.59 76.92%

Area Source: 0.00 0.00 0.00 0.00 0.00%

Electricity: 563.04 0.00 0.00 563.95 0.00%

Natural Gas: 45.89 0.00 0.00 46.01 0.00%

Water & Wastewater: 6.31 0.00 0.00 6.32 0.00%

Solid Waste: 2.44 15.80 N/A 334.16 0.00%

Agriculture: 0.00 0.00 0.00 0.00 0.00%

Off‐Road Equipment: 0.00 0.00 0.00 0.00 0.00%

Refrigerants: N/A N/A N/A 0.00 0.00%

Sequestration: N/A N/A N/A N/A N/A

Purchase of Offsets: N/A N/A N/A N/A N/A

Total: 4,118.02 76.92%

* Several adjustments were made to transportation emissions after they have been imported from URBEMIS.  

After importing from URBEMIS, CO2 emissions are converted to metric tons and then adjusted to account for the "Pavley" 

regulation.  Then, CO2 is converted to CO2e by multiplying by 100/95 to account for the contribution of other GHGs (CH4, N2O, and HFCs [from leaking air con

Finally, CO2e is adjusted to account for th low carbon fuels rule.

Mitigated CO2 (metric tpy) CH4 (metric tpy) N2O (metric tpy) CO2e (metric tpy) % of Total

Transportation*: 3,167.59 83.46%

Area Source: 0.00 0.00 0.00 0.00 0.00%

Electricity: 450.44 0.00 0.00 451.16 11.89%

Natural Gas: 36.71 0.00 0.00 36.81 0.97%

Water & Wastewater: 6.04 0.00 0.00 6.05 0.16%

Solid Waste: 0.98 6.32 N/A 133.66 3.52%

Agriculture: 0.00 0.00 0.00 0.00 0.00%

Off‐Road Equipment: 0.00 0.00 0.00 0.00 0.00%

Refrigerants: N/A N/A N/A 0.00 0.00%

Sequestration: N/A N/A N/A 0.00 0.00%

Purchase of Offsets: N/A N/A N/A 0.00 0.00%

Total: 3,795.27 100.00%

Detailed Results

4 of 4

Page 204: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 

Page 205: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

  

 

APPENDIX C ENERGY EFFICIENCY PROJECTS 

  

Page 206: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

 

Page 207: Final SEIR April 25, 2011 - UCSF€¦ · UCSF MCMB EIR, and includes additional alternatives. Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning

UCSF - Energy Efficency Projects / Greenhouse Gas Reductions

SEP # Project Name Savings - kWh Savings - Therm GHG Reduction

( MTCO2e )B-3027 Genentech Hall -MBCx 2,107,045 200,550 1,672B-3576 Parnassus Steam Trap Retrofit 0 141,700 752B-3585 MCB Data Center - Return Air Retrofit 264,500 0 76B-3586 MCB Data Center - Server Virtualization 86,700 0 25B-3069 Mission Bay Housing - Light Retrofit 37,106 0 11B-3578 HSIR East - Building Exhaust Fan VFD 463,005 0 134B-3577 MCB Boiler Replacement 0 14,000 74B-3575 Hunters Point Boiler 0 4,480 24B-3574 HSIR East Main Manifold VFD 485,471 0 140B-3573 HSIR HW Pumps VFD 178,849 0 52B-3571 3Way - 2Way Chilled Water Valve 207,256 0 60B-3031 HSIR East - MBCx 963,758 136,764 1,004B-3032 HSIR West - MBCx 1,090,875 154,802 1,136B-3021 MCB - Chiller Replacement 432,266 0 125B-3570 MCB VFD System 4.2 438,542 0 127B-3100 HSIR T-12 to T-8 47,489 0 14B-3094 Oyster Point Light Retrofit 164,765 0 48B3579 515 Spruce Light Retrofit - Med Center 14,503 0 4B-3582 100 Buchannan Light Retrofit 77,108 0 22B-3546 Koret Vision _ Light Retrofit 125,506 0 36B-3581 PCUP Air Compressor 228,724 0 66B-3580 HSIR, MedSci, ClinSci - VacPmp VFD 275,667 0 80B-3583 Mt.Zion -Vivarium 243,638 23,306 194B-3080 Parnassus Refrigerator Replacement 43,404 0 13B-3572 HSIR East & West ( T-12 to T-8 ) 191,533 0 55B-3078 HSIR Freezer Replacement 77,282 0 22B-3083 Work Station Power Mgmt - Phase 1 500,000 0 144B-9050 OASIS - 3Par T400 Installation 35,416 0 10B-3590 OASIS - Data Center Storage Virtualization 72,966 0 21B-3588 MCB - VFDs 2.2 & 3.1 243,000 22,200 188B-3589 PC Power Mgmt - Phase 2 600,000 0 173B-3587 Koret Vision - VFDs AHU 1,2,3 259,000 47,000 324B-3034 Byers Hall MBCx 515,282 13,208 219B-3026 PSSRB MBCx 251,029 18,372 170B-3029 MCB MBCx 527,422 76,987 561B-3025 Laurel Heights MBCx 370,180 21,576 221B-3016 LPPI MBCx 70,974 21,769 136B-3008 Library MBCx 326,188 13,514 166B-3013 Medical Sciences 713,942 140,554 952B3011 Millberry Union Fitness Center - MBCx 433,848 15,734 209B-3012 Clinical Science MBCx 223,840 32,573 237B-3019 School of Nursing MBCx 79,155 18,000 118B-3028 Community Center 291,879 26,654 226

Total = 13,759,113 1,143,743 10,039