Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
FINAL SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT
UCSF MEDICAL CENTER AT MISSION BAY—
PHASE 1 GARAGE
State Clearinghouse Number 2008012075
University of California, San Francisco
Certified by the UCSF Chancellor: June 21, 2011
Draft SEIR Publication Date: February 25, 2011
Draft SEIR Public Review Period: February 25, 2011 through April 11, 2011
Draft SEIR Public Hearing Date: March 28, 2011
Final SEIR Date: April 25, 2011
Notice of Determination Date: June 23, 2011
Lead Agency: The University of California
Prepared by: UCSF Campus Planning
654 Minnesota Street
San Francisco, CA 94143‐0286
Contact: Environmental Coordinator
(415) 476‐2911
University of California San Francisco Campus Planning
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
[This page intentionally left blank.]
i
TABLE OF CONTENTS SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT
UCSF MEDICAL CENTER AT MISSION BAY –
PHASE 1 GARAGE Page
1. INTRODUCTION
1.1 Purpose of this Document .................................................................................................... 1 1.2 Organization of the Document ............................................................................................ 3
2. SUMMARY
2.1 Background ............................................................................................................................ 4 2.2 Project Description ................................................................................................................ 4 2.3 Summary of Project Impacts ................................................................................................ 5 2.4 Summary of Alternatives Analysis ................................................................................... 12 2.5 Areas of Controversy .......................................................................................................... 14
3. PROJECT DESCRIPTION
3.1 Background .......................................................................................................................... 15 3.2 Project Description .............................................................................................................. 15 3.3 Project Objectives ................................................................................................................ 21 3.4 Mitigation Monitoring ........................................................................................................ 22 3.5 Required Approvals ............................................................................................................ 22
4. ENVIRONMENTAL SETTING, IMPACTS, AND MITIGATION
4.0 Scope of Analyses ............................................................................................................... 23 4.1 Greenhouse Gas Emissions ................................................................................................ 24 4.2 Transportation ..................................................................................................................... 56
5. CEQA STATUTORY SECTIONS
5.1 Significant Unavoidable Environmental Impacts ........................................................... 60 5.2 Cumulative Impacts ............................................................................................................ 60 5.3 Growth‐Inducing Impacts .................................................................................................. 60 5.4 Effects Found Not to Be Significant .................................................................................. 60 5.5 Significant Irreversible Environmental Changes ............................................................ 60
6. ALTERNATIVES
6.1 Alternatives Analysis .......................................................................................................... 62
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
ii
7. REPORT PREPARATION
7.1 Report Authors .................................................................................................................... 65
8. COMMENTS AND RESPONSES
8.1 Overview .............................................................................................................................. 66 8.2 Public Hearing Transcript .................................................................................................. 66
9. MITIGATION MONITORING AND REPORTING PROGRAM ...................................... 73
LIST OF FIGURES
3‐1 Project Location ................................................................................................................... 16 3‐2 Project Site ............................................................................................................................ 17 3‐3 Project Site Plan ................................................................................................................... 18 3‐4 Project Site Plan/First Floor Plan ....................................................................................... 19 3‐5 Approach from Owens Street ............................................................................................ 20
APPENDICES
A. Initial Study B. Air Emissions Estimates C. Energy Efficiency Projects
Note: A solid dot (●) indicates new chapter or section compared to the Draft SEIR.
Page 1 of 74
CHAPTER 1 INTRODUCTION
1.1 PURPOSE OF THIS DOCUMENT
This Supplemental Environmental Impact Report (“SEIR”) is an informational document
prepared in accordance with the California Environmental Quality Act, Public Resources Code
Sections 21000, et seq. (“CEQA”). It is intended to provide to decision‐makers and the public
supplemental environmental information concerning the proposed construction and operation of
a parking garage at the University of California, San Francisco (UCSF) Medical Center at Mission
Bay. The proposed parking garage is part of the phased development of an integrated hospital
complex to serve children, women and cancer patients at its existing 57‐acre campus site at
Mission Bay.
The University of California (University) is the Lead Agency and The Regents of the University
of California (The Regents), or its delegated committee or administrative official, is the decision‐
making body for the project. On September 17, 2008, The Regents certified the EIR for the UCSF
Medical Center at Mission Bay (MCMB) and approved components of Phase I consisting of the
hospital, energy center, outpatient building, medical helipad, and surface parking. Approval of
the cancer outpatient building and Phase I garage was deferred pending funding and design of
those facilities. Construction of the approved components of the Medical Center project has now
commenced, beginning with site development and construction of the hospital and outpatient
building.
The proposed Phase I parking garage was fully analyzed in the UCSF Medical Center at Mission
Bay EIR (UCSF MCMB EIR). This SEIR has been prepared to update the UCSF MCMB EIR in
order to analyze three minor changes to the proposed Phase I garage. In addition, this SEIR
updates the greenhouse gas (GHG) emissions analysis for the proposed Phase I garage in light of
new GHG significance criteria recently adopted by the Bay Area Air Quality Management
District (BAAQMD). This SEIR focuses on two topics that are affected by the proposed revisions
to the project: greenhouse gas emissions and transportation. All other environmental topics
were adequately analyzed in the UCSF MCMB EIR and require no further analysis, as
determined in the Initial Study for this project (see Appendix A). Pursuant to Section 15163(b),
this supplement to the EIR contains only the information necessary to make the previous EIR
adequate for the project as revised.
Under CEQA Guidelines Section 15162, a subsequent EIR is required only when, among other
criteria, “substantial changes are proposed in the project which will require major revisions of
the previous EIR or negative declaration due to the involvement of new significant
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 2 of 74
environmental effects or a substantial increase in the severity of previously identified significant
effects.” CEQA Guidelines Section 15163 allows the lead agency to choose to prepare a
supplement to an EIR rather than a subsequent EIR if “only minor additions or changes would be
necessary to make the previous EIR adequately apply to the project in the changed situation.”
The changes proposed to the project consist of the increase in the number of parking spaces
within the garage by 26 spaces (for a total of about 626 spaces), the increase in height by 15 feet
(to a total of about 105 feet), and relocation of the Phase I garage to a portion of the hospital site
north of the originally proposed site. Only minor additions to the UCSF MCMB EIR are
necessary for the EIR to adequately address the proposed project. Because of the modest nature
of these project changes, a supplement to the UCSF MCMB EIR has been prepared.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 3 of 74
1.2 ORGANIZATION OF THE DOCUMENT
This document is organized into the following chapters:
Chapter 1, Introduction: Describes the purpose of this SEIR.
Chapter 2, Summary: Summarizes the supplemental environmental impact analysis.
Chapter 3, Project Description: Provides a description of the modified project, project objectives, project consistency with the LRDP, mitigation monitoring, and required approvals by other agencies.
Chapter 4, Environmental Settings, Impacts and Mitigation Measures: Describes the scope of this SEIR, focusing on impact topics of relevance to the modified project.
Chapter 5, CEQA Statutory Sections: Discusses various CEQA mandated considerations including unavoidable environmental impacts, cumulative impacts, and growth inducing impacts.
Chapter 6, Alternatives: Discusses the alternatives to the project already analyzed in the UCSF MCMB EIR, and includes additional alternatives.
Chapter 7, Report Preparation: Lists report authors, in this case UCSF Campus Planning staff, and other consulting staff that assisted with the preparation and review of the SEIR. Identifies persons, agencies and organizations that were consulted.
Page 4 of 74
CHAPTER 2 SUMMARY
2.1 BACKGROUND
On September 17, 2008, The Regents certified the EIR for the UCSF Medical Center at Mission
Bay (MCMB) (State Clearinghouse No. 2008012075) and approved components of Phase I
consisting of the 289‐bed hospital, energy center, outpatient building, medical helipad, and
surface parking.1 Approval of the cancer outpatient building and Phase I garage was deferred
pending funding and design of those facilities. Construction of the approved components of the
Medical Center project has now commenced, beginning with site development and construction
of the hospital and outpatient building. The complex is scheduled to open in 2014. With
approved funding of the Phase I garage, the University is now prepared to seek approval of its
design and construction.
2.2 PROJECT DESCRIPTION
The Medical Center project site is bordered by 16th Street to the north, 3rd Street to the east, and
Mariposa Street to the south. In the future, a new segment of Owens Street will define the western
boundary of the project site. The parking structure analyzed in the MCMB EIR consisted of a 600‐
space garage of approximately 90 feet in height, located along the western edge of the site on
Owens Street between the South Connector Road and the Center Garage Access (now Parking
Structure Road). The medical center program envisioned in Phase II the expansion of the garage
to the north between the Center Garage Access and the North Connector Road. The garage is
now proposed to be approximately 626 spaces and an additional story at about 105 feet in height.
In addition, the Phase I garage is now proposed to the north, between the North Connector Road
and Parking Structure Road, the originally proposed location of the Phase II garage (see Figure 3‐
3). Phase II of the garage would expand the structure to the south from Parking Structure Road
to South Connector Road.
The number of surface parking spaces proposed on the remainder of Blocks 38 and 39 in Phase I
has been reduced from 475 spaces to approximately 429 spaces, with an additional 13 spaces east
of the future extension of 4th Street, in what is known as the east lot. The total surface parking
spaces would be approximately 442 compared to the 475 spaces analyzed in the 2008 EIR.
Therefore, the total number of parking spaces provided in Phase I (626 spaces in the parking
1 The UCSF Medical Center at Mission Bay EIR is available online at
http://campusplanning.ucsf.edu/physical/RFEIRHospital.php.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 5 of 74
structure and 442 surface parking spaces) would decrease by approximately seven spaces and
would total approximately 1,068‐parking spaces from 1,075 spaces (see Figure 3‐4).
2.3 SUMMARY OF PROJECT IMPACTS
2.3.1 GREENHOUSE GAS
Global climate change refers to any significant change in climate measurements, such as
temperature, precipitation, or wind, lasting for an extended period (i.e., decades or longer) (U.S.
EPA 2008b). To gauge the potency of GHGs, scientists have established a Global Warming
Potential (GWP) for each GHG based on its ability to absorb and re‐emit long‐wave radiation
over a specific period. The GWP of a gas is determined using CO2 as the reference gas, which has
a GWP of 1 over 100 years (IPCC 1996). The sum of each GHG multiplied by its associated GWP
is referred to as “carbon dioxide equivalents” (CO2e).
Significance Criteria
In accordance with Senate Bill (SB) 97, the Natural Resources Agency adopted amendments to
the State CEQA Guidelines on December 30, 2009 (effective March 2010), which include criteria for
evaluating GHG emissions.2 According to the amended Appendix G of the State CEQA
Guidelines, a project would have a significant effect on the environment if it would:
Generate greenhouse gas emissions, either directly or indirectly, that may have a
significant impact on the environment; or
Conflict with an applicable plan, policy or regulation adopted for the purpose of
reducing the emissions of greenhouse gases.
The Bay Area Air Quality Management District (BAAQMD) has established project‐level
screening criteria and significance thresholds for operational GHG emissions in its CEQA Air
Quality Guidelines. The BAAQMD’s thresholds of significance for operational‐related GHG
emissions are as follows:
For land use development projects, the threshold is compliance with a qualified GHG
Reduction Strategy; or annual emissions less than 1,100 metric tons CO2e per year
(MTCO2e/yr); or 4.6 MT CO2e/person/yr (residents plus employees). Land use
development projects include residential, commercial, industrial, and public land uses
and facilities.
For stationary‐source projects, the threshold is 10,000 MTCO2e/yr. Stationary‐source
projects include land uses that would accommodate processes and equipment that emit
GHG emissions and would require an Air District permit to operate.
2 http://ceres.ca.gov/ceqa/guidelines/
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 6 of 74
The BAAQMD guidelines do not contain a quantitative threshold of significance for the
evaluation of GHG emissions resulting from a project’s construction activities.
Based on the above, the proposed project’s significance with respect to the GHG emissions and
global climate change will be assessed based on the BAAQMD’s GHG thresholds of significance
and on the project features and GHG reduction measures that are consistent with the BAAQMD’s
recommended measures to reduce GHG emissions.
Impacts and Mitigation Measures
Impact GHG‐1: Project development would generate greenhouse gas emissions, either directly
or indirectly, that could have a significant impact on the environment. (Significant; Less than
significant with mitigation)
Operational Impacts
Once operational, the proposed project would generate direct operational emissions of GHGs,
primarily CO2, CH4, and N2O, which would be the result of fuel combustion from the building’s
lighting and elevator systems, from fuel combustion by the motor vehicles using the garage, and
from motor vehicle air conditioning.
Estimated emissions from mobile sources (transportation) would be 3,168 metric tons of CO2e,
and emissions from non‐mobile sources would be 627 metric tons of CO2e, resulting in a total of
about 3,795 metric tons of CO2e.
These emissions present a worst case scenario. Transportation emissions will decline in the
future as new motor vehicles with lower tailpipe emissions required by existing State (Pavley)
and Federal regulations are adopted into the vehicle fleet. As shown in Table 4.1‐3, the proposed
project’s operational emissions would exceed the project level threshold of 1,100 MTCO2e for
land use development projects. The project’s impact would therefore be significant.
Phase I Garage Mitigation: The Regents have committed the University system to reduce its
GHG emissions from all of its operations to the 1990 level by 2020. In furtherance of the goal to
meet these goals, the University is currently implementing the 2010‐12 Statewide Energy
Partnership Program (through the UC Strategic Energy Plan), an ambitious three year program
to help meet its goal. This 3 year program, in its second year of implementation, is expected to
reduce energy consumption by 11%, natural gas consumption by 8%, and greenhouse gas
emissions by 9% system‐wide.
As identified in the UCSF Climate Action Plan, UCSF is undertaking many of these energy
efficiency projects to retrofit existing facilities in order to assist the campus to meet its
greenhouse gas goals. These energy efficiency projects at UCSF provide more than 2,700
MtCO2e ongoing new reductions per year. Detail on campus specific reduction projects are
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 7 of 74
described in the UC system wide Strategic Energy Plan.3
The Regents has approved funding for the 2010 Statewide Energy Partnership Program / UC
Strategic Energy Plan. UCSF would mitigate at least 2,700 MtCO2e ongoing reductions per year,
e.g. the additional significant GHG emissions associated with the proposed garage project, with
the appropriate number of energy efficiency projects identified on the list in Supplemental EIR
Appendix C. Projects identified in Appendix C are those projects that are included in the
funded, UC Strategic Energy Plan and that are planned to be implemented by 2012, around the
time garage operations would begin.
Significance after Mitigation: Less than Significant
Construction Impacts
Construction of the proposed project, which would include activities such as grading/excavation,
trenching, building construction, and architectural coating, would result in one‐time emissions of
greenhouse gases. Construction of the proposed project is anticipated to commence in Summer
2011 and continue for approximately 12 months.
The BAAQMD does not have a quantitative threshold of significance for construction‐related
GHG emissions. However, the CEQA Air Quality Guidelines requires the Lead Agency to quantify
and disclose GHG emissions that would occur during construction. Table 4.1‐4, Estimated
Construction GHG Emissions shows a summary of total estimated GHG emissions from the
construction of the proposed project, about 500.5 metric tons of CO2e over the course of the two
year construction period (2011 and 2012). Given the low numbers, the fact that they are much
lower than the threshold for operational emissions, and the fact that these would be one‐time
emissions, the effect on global climate from the proposed project’s construction would not be
substantial.
Impact GHG‐2: The proposed project could conflict with an applicable plan, policy or
regulation adopted for the purpose of reducing the emissions of greenhouse gases. (Less than
Significant)
The primary GHG emissions regulation in California is AB 32, which is discussed above. The
BAAQMD GHG significance threshold was specifically designed to ensure compliance with AB
32 emissions reductions requirements in the Bay Area. The project would not set back AB 32
efforts for the Bay Area air basin.
The BAAQMD 2010 Clean Air Plan contains energy, transportation, and mobile source control
measures that would reduce operational GHG emissions and that would be potentially
applicable to the project. The project includes project design features that are generally consistent
with potentially applicable measures. Furthermore, UCSF has incorporated into the proposed
3 http://www.universityofcalifornia.edu/sustainability/documents/ucsep_sw.pdf page 14/21
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 8 of 74
project substantial sustainability features, including several GHG mitigation measures included
in the BAAQMD CEQA guidelines.
With implementation of the reduction projects identified in Impact GHG‐1, emissions would be
mitigated to less than 1,100 MMTCO2e /year. The proposed project would not conflict with an
applicable plan, policy or regulation adopted for the purpose of reducing the emissions of
greenhouse gases.
The Regents has committed the UC system to meet the State of California’s AB32 goal to reduce
GHG emissions to 1990 levels by 2020 through the policies identified in the University of
California Policy on Sustainable Practices.4 UCSF is in compliance with the University of
California’s Policy on Sustainable Practices by completing all four implementation procedures
identified in the Policy.
The proposed project would also be consistent with the UCSF Climate Action Plan (UCSF 2009).
The Climate Action Plan contains the following transportation‐related measures would reduce
transportation‐related GHG emissions:
Transportation Demand Management (TDM) Program – UCSF’s TDM conforms with San
Francisco’s Transit First Policy to encourage the use of alternative transportation to single‐
occupancy vehicles. UCSF has excellent transit ridership rates according to latest transportation
survey. About 25.6% of respondents (faculty, staff, and students) reported taking public transit
(e.g., Muni or other bus system) as their main transportation choice in the latest mobility
choices survey.
Bicycling Accommodations ‐Bicycle racks have been expanded from 400 spaces in 2003
to 680 in 2008. There are now 53 shuttle mounted bike racks. Expenditures on new bike
racks were $13,445 in 2008. UCSF bicyclists are eligible for a reduced price membership
in the San Francisco Bicycle Coalition.
Fuel Efficient Vehicles – The Campus supplies 2 electric vehicle charging stations. Fifteen
percent (42 of 273) of campus fleet vehicles are powered by alternative fuel or a hybrid
electric and gas. The Campus offers 103 motorcycle parking stalls.
Transit Pass sales –To further encourage transit use UCSF offers the Campus community
5 convenient locations to purchase city and regional transit passes. MUNI Fast Pass and
Bart Commuter Ticket Monthly sales are 600 passes in 2008.
Vanpools – The number of vanpools increased from 30 in 2003 to 46 in 2008 and the
number of car sharing from three to 17 during the same period. These efforts, led by
UCSF Transportation Services, earned UCSF a place on the inaugural 2006 national list of
Best Workplaces for Commuters from colleges and universities, awarded by the US
Environmental Protection Agency (EPA). Vanpools receive preferential parking spaces at
4 http://www.universityofcalifornia.edu/sustainability/documents/policy_sustain_prac.pdf
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 9 of 74
UCSF.
The UCSF Climate Action Plan contains the following Strategic Energy Plan improvements that
are pertinent to the proposed project. These measures will be investigated for potential
implementation by the proposed project and would reduce energy demand and associated GHG
emissions:
Lighting Projects UCSF will continue to convert existing T12 and 32 watt T8 fluorescent
light fixtures to 28 watt T8 lamps. Other possibilities include: broader use of occupancy
sensor controls, daylight harvesting, and new stairwell fixtures. The replacement of
lighting in parking structures and interior HID fixtures and with fluorescent will also be
evaluated. New technologies such as LED lighting, bi‐level fixtures and induction lamps
are anticipated to become readily available in the near future and these technologies will
be incorporated into energy efficiency retrofit projects where appropriate.
The proposed project includes secure bicycle parking, parking fees, and electric vehicle charging
stations. In addition, garage attendants would be available to provide information on alternative
transportation and sell transit passes. The project could also provide preferential parking spaces
for carpools and vanpools, depending on need, consistent with UCSF guidelines. These measures
would reduce transportation‐related GHG emissions consistent with the Climate Action Plan
measures. The project would also be designed to minimize the energy demand by using energy‐
efficient lighting (fluorescent, LED lighting, or similar depending on cost effectiveness). Based on
the inclusion of these project design features, the project would be consistent with applicable
plans that have been adopted to reduce GHG emissions. The impact would be less than
significant.
Mitigation: No additional mitigation is required.
2.3.2 TRANSPORTATION
This section evaluates potential changes to the transportation analysis of the MCMB EIR as a
result of the minor modifications to the proposed Phase I garage project. The MCMB EIR
concluded that the construction and operation of the Medical Center at Mission Bay, including
the proposed Phase I garage, would not cause a substantial adverse impact to transit, pedestrian,
bicycle, or parking conditions, nor result in inadequate emergency access. The modifications to
the proposed project would not change the effects anticipated in these topic areas. Therefore, this
analysis focuses on any potential changes to operational traffic impacts.
Significance Criteria
The significance criteria and analysis methodology of the MCMB EIR remain unchanged with
regard to transportation and traffic. Traffic impacts were analyzed using the concept of Level of
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 10 of 74
Service (LOS), which describes the level of the performance of an intersection based on the
average delay per vehicle. Intersection LOS ranges from LOS A, which indicates free‐flow
conditions with little or no delays, to LOS F, which indicates congested or overloaded conditions
with extremely long delays. LOS D, which indicates increasingly unacceptable, yet tolerable,
delays, is considered to be the minimum acceptable level of service.
As discussed in the Project Description, although the number of parking spaces within the
proposed garage has been increased from 600 spaces to 626 spaces with the modified project, the
number of parking spaces within the surface parking lot, which has been approved, has
decreased. The total number of parking spaces in Phase I (626 spaces in the parking structure
and 442 surface parking spaces) has decreased by approximately seven spaces and would total
approximately 1,068‐parking spaces, down from the previously analyzed 1,075 spaces. As
discussed in the Project Description, the Phase I garage is now proposed to the north, between
North Connector Road and Parking Structure Road. Roadways internal to the site and
connections to surrounding public streets, including Owens Street, would remain unchanged.
Impacts and Mitigation Measures
A Transportation Study was prepared for the MCMB EIR.5 The Transportation Study evaluated
both the Phase I and future buildout of the Phase II development. In addition, the traffic study
evaluated two potential alternatives for the operation of 4th Street through the Medical Center
site. Both alternatives would convert the proposed 4th Street right‐of‐way to University of
California property.
Based on the analysis contained with the Transportation Study, traffic impacts resulting from
Phase I of the Medical Center at Mission Bay would be less than significant, as all study
intersections would continue to operate at level‐of‐service D or better. The impacts analysis
below updates the impacts analysis of the MCMB EIR.
Construction Impacts
Impact MCMB.6‐1 of the MCMB EIR (analysis updated with this SEIR): The MCMB EIR
concluded that construction of the MCMB Phase I project, including the Phase I garage,
would not result in significant construction‐period impacts. (Less than Significant)
The MCMB EIR concluded that MCMB Phase I construction activities would temporarily
increase traffic on area roadways (due to construction employee auto trips and construction
truck traffic), as well as demand for parking in the area. In addition, the staging of vehicles and
construction materials would require temporary closure of on‐street parking near the
construction site. The MCMB EIR concluded that the LRDP Amendment #2 – Hospital
Replacement EIR mitigation measure 4.11‐1, which includes limiting the use of local roads as
haul routes, and/or limiting truck trips to off‐peak hours, and/or developing a parking plan for
5 Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation Study, March 2008.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 11 of 74
construction employees, would ensure transportation‐related construction impacts would be
reduced to less than significant levels. In furtherance of this mitigation measure, the proposed
Phase I garage, once completed, on a temporary basis would provide some construction
employee parking until construction of the hospital and surface parking lot is complete.
Mitigation: None required.
Operational Impacts
Impact MCMB.6‐2 of the MCMB EIR (analysis updated with this SEIR): The MCMB EIR
concluded that operation of the MCMB project, including the Phase I garage, would not result
in a significant impact on the adjacent roadway network. (Less than Significant)
As discussed in the Project Description, while the number of parking spaces in the parking
structure (from 600 to 626) would increase as a result of the changes to the proposed project,, the
total number of parking spaces would decrease by about 7 spaces as a result of the proposed
decrease in surface parking. Although the location of the Phase I garage is now proposed in the
location of the proposed Phase II garage, to the north of the previously proposed Phase I garage
site, effects on traffic would continue to be less than significant in Phase I. Overall site circulation
and access to the parking garage would remain substantially the same. Multiple access points
to/from the parking facility (including the adjoining surface lot) would continue to be from North
Connector Road, South Connector Road, West Connector Road, and Parking Structure Road
(formerly Center Garage Access), all campus streets on the Medical Center site. Effects on traffic
at surrounding study intersections would remain largely unchanged. As a result of the
relocation of the Phase I garage to north, Parking Structure Road/ Owens Street could experience
incrementally more traffic in Phase I than previously anticipated, but not to the degree that the
level of service would deteriorate to unacceptable levels. Multiple roadway access would
continue to be available to the garage, as previously analyzed, and assumptions regarding the
distribution of traffic at nearby intersections would not substantially change.
Mitigation: None required.
Impact MCMB.6‐3 of the MCMB EIR (analysis updated with this SEIR): Operation of the
UCSF Medical Center at Mission Bay project would increase traffic at intersections on the
adjacent roadway network in the Future Phase (Phase II). (Significant)
The MCMB EIR traffic analysis of the full project (Phase I and Phase II) would not change
substantially with the modified project. With the modified project, the construction of the Phase
II garage would occur to the south of the Phase I garage, at the original location of the Phase I
garage. The significant traffic impact at 16th/Owens in Phase II would continue to be significant
with the modified project. The potential impact at Owens/Center Garage Access would remain
speculative pending project‐level analysis of the traffic and circulation analyses for Phase II.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 12 of 74
Mitigation: The mitigation measures identified in the MCMB EIR to address significant traffic
impacts in Phase II would remain unchanged, as follows:
16th/Owens: Mitigation Measure 4.11‐2a from the LRDP Amendment #2 EIR identifies
modifications to the Owen Street lane configurations (i.e. restriping) to mitigate the
impact at this intersection: one southbound shared through‐left turn lane, one
southbound through lane, and one southbound exclusive right turn lane, would remain
the same.
Significance after Mitigation: Less than significant. Implementation of the re‐striping at
this location would improve the operating conditions at this intersection to an acceptable
LOS D. The City of San Francisco has found the mitigation measure to be feasible, and
has committed to working with UCSF to ensure its implementation.6
Owens Street at Center Garage Access: Mitigation Measure MCMB.6‐3 from the
Medical Center at Mission Bay EIR would require that UCSF conduct a project‐level
CEQA review at the time the Phase II development is considered for approval. In
addition, in order to determine the need for LOS improvements on Owens Street,
between 16th and Mariposa Streets at Center Garage Access (now Parking Structure
Road), such as a traffic signal, UCSF would coordinate with the City of San Francisco in
the periodic update of the Mission Bay traffic triggers survey and would monitor on‐site
parking access and circulation in order to determine the need for LOS improvements.
Significance after Mitigation: The need for LOS improvements on Owens Street at the
Center Garage Access in Phase II remains speculative pending a project‐level design of
parking requirements and project‐level traffic and circulation evaluation.
2.4 SUMMARY OF ALTERNATIVES ANALYSIS
2.4.1 NO PROJECT ALTERNATIVE
CEQA requires that a “No Project” alternative be considered. Under this alternative, the UCSF
Medical Center at Mission Bay would be developed as proposed except that the garage would
not be constructed. The 442‐parking space surface lots, which have been approved, would be
constructed as planned.
This alternative would not meet any of the project objectives.
Greenhouse Gas Emissions
With the proposed project, impacts on greenhouse gas emissions would be significant, but would
be reduced to less than significant levels with mitigation. While the No Project Alternative would
6 Comment letter dated July 3, 2008 from the San Francisco Municipal Transportation Agency, on the UCSF
Medical Center at Mission Bay Draft EIR.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 13 of 74
mean no parking structure would be provided, it is still anticipated that a substantial number of
patients, visitors, and employees would need to drive to the site. It is likely that the amount of
greenhouse gas emissions would be significant, as with the modified project, but those emissions
could be reduced to less‐than‐significant levels with the implementation of the energy efficiency
projects identified as mitigation for the modified project.
Transportation
The proposed project would result in less than significant impacts on traffic, as would the No
Project Alternative. Without a garage on the Medical Center at Mission Bay site, more drivers
may search for parking in the vicinity, thus more traffic may occur in the surrounding
neighborhood than with the proposed project. However, traffic impacts under the No Project
Alternative would be less than significant.
2.4.2 REDUCED PROJECT ALTERNATIVE
Under the Reduced Project Alternative, the number of parking spaces would be reduced to
approximately one‐half the number of spaces, or about 300 spaces. The number of parking
spaces within the surface parking lots, which have been approved, would remain the same at 442
spaces.
This alternative would meet the project objectives to (1) ensure that development is compatible
with and responsive to building scale and character in the surrounding areas; and (2) provide a
parking structure that incorporates sustainability features to the greatest extent feasible.
This alternative would only satisfy a portion of the expected parking demand by patients,
visitors, and staff, and therefore would only partially meet the project objectives to (1) develop a
patient‐friendly hospital (convenient location, availability of parking, efficient patient/emergency
access, proximity of related patient service, etc.); (2) develop a staff‐friendly hospital (availability
of parking, proximity to amenities, loading/delivery access, etc.); (3) support UCSF’s mission of
patient care by enhancing access to UCSF facilities through convenient, affordable parking for
those who often cannot utilize alternative forms of transportation; (4) provide parking for those
essential healthcare providers for whom alternative forms of transportation is infeasible due to
atypical work hours and responsibilities at multiple campus sites; and (5) avoid pressure on
neighborhood on‐street parking.
Greenhouse Gas Emissions
With the proposed project, impacts on greenhouse gas emissions would be significant, but would
be reduced to less than significant levels with mitigation. The Reduced Project Alternative would
likely result in significant greenhouse gas emissions that could be reduced to less than significant
levels with mitigation, similar to the proposed project.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 14 of 74
Transportation
The proposed project would result in less than significant impacts on traffic, as would the
Reduced Project Alternative. With fewer parking spaces on the Medical Center at Mission Bay
site, more drivers may search for parking in the vicinity, thus more traffic may occur in the
surrounding neighborhood than with the proposed project. However, traffic impacts under the
Reduced Project Alternative would be less than significant.
2.4.3 ENVIRONMENTALLY SUPERIOR ALTERNATIVE
An EIR is required to identify the environmentally superior alternative—that is, the alternative
having the fewest significant environmental impacts—from among the alternatives evaluated.
The environmentally superior alternative among those evaluated within this SEIR is the No
Project Alternative. Other than the No Project Alternative, the remaining alternative, the
Reduced Project Alternative, is the environmentally superior alternative.
2.5 AREAS OF CONTROVERSY
No concerns have been expressed regarding the proposed garage, and there are no known areas
of controversy about this project.
Page 15 of 74
CHAPTER 3 PROJECT DESCRIPTION
3.1 BACKGROUND
On September 17, 2008, The Regents certified the EIR for the UCSF Medical Center at Mission
Bay (MCMB) (State Clearinghouse No. 2008012075) and approved components of Phase I
consisting of the 289‐bed hospital, energy center, outpatient building, medical helipad, and
surface parking.7 Approval of the cancer outpatient building and Phase I garage was deferred
pending funding and design of those facilities. Construction of the approved components of the
Medical Center project has now commenced, beginning with site development and construction
of the hospital and outpatient building. The complex is scheduled to open in 2014. With
approved funding of the Phase I garage, the University is now prepared to seek approval of its
design and construction.
3.2 PROJECT DESCRIPTION
The location of the UCSF Medical Center at Mission Bay is as described in the UCSF Medical Center
at Mission Bay EIR. The 14.5‐acre site is located in the eastern portion of the City of San Francisco,
approximately one and one half miles south of downtown, and increases the UCSF Mission Bay
campus from 43 acres to 57 acres (see Figure 3‐1).8 The site lies within the 303‐acre Mission Bay
Redevelopment Plan Area, under the jurisdiction of the San Francisco Redevelopment Agency, and
consists of Mission Bay South Plan Parcels 36, 37, 38, 39, and X3.
7 The UCSF Medical Center at Mission Bay EIR is available online at
http://campusplanning.ucsf.edu/physical/RFEIRHospital.php. 8 The 14.5‐acre Medical Center project site was added to the 43‐acre UCSF Mission Bay campus site (a total
of 57 acres) in September 2008.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 16 of 74
Source: Environmental Science Associates, April 2008 Figure 3‐1
Location of UCSF Medical Center at
Mission Bay
Page 17 of 74
Source: UCSF, April 2008 Figure 3‐2
Project Site
Proposed Project
Page 18 of 74
Source: WRNS Studio Figure 3‐3
Project Site Plan
Page 19 of 74
Source: WRNS Studio Figure 3‐4
Project Site Plan/First Floor Plan
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 20 of 74
Source: Rudolph and Sletten and WRNS Studios LLP Figure 3‐5
Approach from Owens Street
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 21 of 74
The Medical Center project site is bordered by 16th Street to the north, 3rd Street to the east, and
Mariposa Street to the south. In the future, a new segment of Owens Street will define the western
boundary of the project site (see Figure 3‐2).
Structures that have not yet been approved under Phase I include the garage and the cancer
outpatient building. Minor changes to the garage in Phase I are proposed. The parking structure
analyzed in the MCMB EIR consisted of a 600‐space garage of approximately 90 feet in height,
located along the western edge of the site on Owens Street between the South Connector Road
and the Center Garage Access (now Parking Structure Road). The medical center program
envisioned in Phase II the expansion of the garage to the north between the Center Garage Access
and the North Connector Road. The garage is now proposed to be approximately 626 spaces and
an additional story at about 105 feet in height. In addition, the Phase I garage is now proposed to
the north, between the North Connector Road and Parking Structure Road, the original location
of the proposed Phase II garage (see Figure 3‐3). Phase II of the garage would expand the
structure to the south from Parking Structure Road to South Connector Road.
The number of surface parking spaces proposed on the remainder of Blocks 38 and 39 in Phase I
(see Figure 3‐3) has been reduced from 475 spaces to approximately 429 spaces, with an
additional 13 spaces east of the future extension of 4th Street, in what is known as the east lot.
The total surface parking spaces would be approximately 442 compared to the 475 spaces
analyzed in the 2008 EIR. Therefore, the total number of parking spaces provided in Phase I (626
spaces in the parking structure and 442 surface parking spaces) would decrease by
approximately seven spaces and would total approximately 1,068‐parking spaces from 1,075
spaces (see Figure 3‐4).
3.3 PROJECT OBJECTIVES
3.3.1 OBJECTIVES IN THE UCSF MEDICAL CENTER AT MISSION BAY
EIR
The Project Objectives described in the UCSF MCMB EIR remain unchanged. As a support
function to the hospital complex, all project objectives are applicable to the proposed garage, and
in particular the following Project Objectives to:
Ensure that development is compatible with and responsive to building scale and
character in the surrounding areas
Develop a patient‐friendly hospital (convenient location, availability of parking, efficient
patient/emergency access, proximity of related patient service, etc.)
Develop a staff‐friendly hospital (availability of parking, proximity to amenities,
loading/delivery access, etc.)
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 22 of 74
In addition, this SEIR identifies the following Project Objectives for the proposed garage:
To support UCSF’s mission of patient care by enhancing access to UCSF facilities
through convenient, affordable parking for those who often cannot utilize alternative
forms of transportation
To provide parking for those essential healthcare providers for whom alternative forms
of transportation is infeasible due to atypical work hours and responsibilities at multiple
campus sites
To provide a parking structure that incorporates sustainability features to the greatest
extent feasible
To avoid pressure on neighborhood on‐street parking
3.4 MITIGATION MONITORING
CEQA requires that when a public agency makes findings of significance based on an EIR, the
public agency must adopt a reporting or monitoring program to ensure that action is completed
on those mitigation measures which it has adopted, or made a condition of project approval, in
order to mitigate or avoid the project’s significant effects on the environment (Public Resources
Code Section 21081.6). A mitigation monitoring program for the Medical Center project was
adopted in September 2008 upon certification of the UCSF MCMB EIR and approval of the
Medical Center project. Upon certification of this SEIR and approval of the Phase I garage, the
revised mitigation monitoring program, updated to include mitigation measures identified in
this SEIR, would be adopted.
3.5 REQUIRED APPROVALS
The University of California is the CEQA lead agency in the review of the project. The Regents
of the University of California, or their delegated committee or administrative official, will
consider certification of this SEIR and approval of the Phase I garage.
_________________________
Page 23 of 74
CHAPTER 4 ENVIRONMENTAL SETTING, IMPACTS, AND MITIGATION
MEASURES
4.0 SCOPE OF ANALYSES
This SEIR updates the UCSF MCMB EIR by analyzing proposed minor changes to the Phase I
garage project. There are no changes proposed to the cancer outpatient building, the other
remaining building in Phase I that has not yet been approved. In addition, this SEIR updates the
greenhouse gas (GHG) emissions analysis in light of new GHG significance criteria recently
adopted by the Bay Area Air Quality Management District (BAAQMD). As such, this SEIR
focuses on two topics that are affected by the modified project: greenhouse gas emissions and
transportation. All other environmental topics were adequately analyzed and require no further
analysis, as determined in the Initial Study for this project (see Appendix A).
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 24 of 74
4.1 GREENHOUSE GAS EMISSIONS
4.1.1 INTRODUCTION
This section discusses the existing global, national, and statewide conditions for greenhouse
gases (GHG) and global climate change and evaluates the potential impacts on global climate
from the implementation of the proposed Medical Center at Mission Bay Garage project
(proposed project). The section also provides discussion of the applicable federal, state, regional,
and local agencies that regulate, monitor, and control GHG emissions. The impacts associated
with the proposed project are compared with the thresholds of significance adopted by the Bay
Area Air Quality Management District (BAAQMD). Copies of the modeling runs to estimate
GHG emissions associated with the proposed project and supporting technical data are found in
Appendix B.
The 2008 MCMB FEIR, certified by The Regents September 17, 20089, included an analysis of
greenhouse gas emissions. This analysis was done for the entire Medical Center at Mission Bay
project envelope including of the proposed Medical Center at Mission Bay Garage project.10 The
analysis was done using the URBEMIS2007 Version 9.2.4 software. Subsequent to the
certification of that EIR, additional guidance for the analysis of greenhouse gases has been
adopted.
The Natural Resources Agency adopted GHG CEQA Guideline Amendments on December 30,
2009. They became effective in March 2010.
The BAAQMD adopted updated CEQA Air Quality Guidelines on June 2, 2010. These guidelines
contain greenhouse gas operational emissions significance thresholds and recommended
methodologies and models to be used for assessing the impacts of project‐specific GHG
emissions on global climate change. The updated CEQA Air Quality Guidelines contain project‐
level screening criteria and recommended significance thresholds for evaluation of operational
GHG emissions from a proposed project. The guidelines also contain recommended
methodologies to use to estimate these emissions and provide recommended measures for
reducing GHG emissions from land use development projects and stationary sources. The
recommended methodology is the URBEMIS2007 Version 9.2.4 software with an additional Bay
Area specific spreadsheet module that takes into account Assembly Bill 1493 limitations on motor
vehicles.
9 State Clearinghouse No. 2008012075 10 http://campusplanning.ucsf.edu/pdf/RFEIR/UCSFMissionBayMedCtrRFEIRAppendices.pdf Table GHG-1
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 25 of 74
4.1.2 ENVIRONMENTAL SETTING
Background
Global climate change refers to any significant change in climate measurements, such as
temperature, precipitation, or wind, lasting for an extended period (i.e., decades or longer) (U.S.
EPA 2008b). Climate change may result from:
Natural factors, such as changes in the sun’s intensity or slow changes in the Earth’s
orbit around the sun (Milankovitch cycles);
Natural processes within the climate system (e.g., changes in ocean circulation,
changes in planetary albedo from the addition of gases to the atmosphere from
volcanic eruptions); and
Human activities that change the atmosphere’s composition (e.g., through burning
fossil fuels) and the land surface (e.g., deforestation, reforestation, urbanization,
desertification).
The natural process through which heat is retained in the troposphere11 is called the “greenhouse
effect.” The greenhouse effect traps heat in the troposphere through a threefold process as
follows: (1) short‐wave radiation in the form of visible light emitted by the Sun is absorbed by the
Earth as heat; (2) long‐wave radiation is re‐emitted by the Earth; and (3) certain gases termed
greenhouse gases in the upper atmosphere absorb a portion of the long‐wave radiation that
would otherwise have been emitted into space, warming the earth’s surface. This third process is
the focus of current climate change actions.
While water vapor and carbon dioxide (CO2) are the most abundant GHGs, other GHGs found in
trace amounts have a greater ability to absorb and re‐radiate long‐wave radiation. To gauge the
potency of GHGs, scientists have established a Global Warming Potential (GWP) for each GHG
based on its ability to absorb and re‐emit long‐wave radiation over a specific period. The GWP of
a gas is determined using CO2 as the reference gas, which has a GWP of 1 over 100 years (IPCC
1996). For example, a gas with a GWP of 10 is 10 times more potent than CO2 over 100 years. The
use of GWP allows GHG emissions to be reported using CO2 as a baseline. The sum of each GHG
multiplied by its associated GWP is referred to as “carbon dioxide equivalents” (CO2e). This
essentially means that 1 metric ton of a GHG with a GWP of 10 has the same climate change
impacts as 10 metric tons of CO2. The IPCC makes minor adjustments to the GWP values of the
various GHG’s as the scientific understanding of climate change advances.
Greenhouse Gases
11 The troposphere is the bottom layer of the atmosphere, which varies in height from the Earth’s surface to
10 to 12 kilometers).
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 26 of 74
State law defines GHGs to include the following six compounds:
Carbon Dioxide (CO2). Carbon dioxide primarily is generated by fossil fuel
combustion from stationary and mobile sources. Due to the emergence of industrial
facilities and mobile sources over the past 250 years, the concentration of carbon dioxide
in the atmosphere has increased 35 percent. (U.S. EPA 2008c). Carbon dioxide is the
most widely emitted GHG and is the reference gas (GWP of 1) for determining the GWP
of other GHGs. In 2004, 82.8 percent of California’s GHG emissions were carbon dioxide
(CEC 2007).
Methane (CH4). Methane is emitted from biogenic sources (i.e., resulting from the
activity of living organisms), incomplete combustion in forest fires, landfills, manure
management, and leaks in natural gas pipelines. In the United States, the top three
sources of methane are landfills, natural gas systems, and enteric fermentation (U.S.
EPA). Methane is the primary component of natural gas, which is used for space and
water heating, steam production, and power generation. The GWP of methane is 21.
Nitrous Oxide (N2O). Nitrous oxide is produced by natural and human‐related sources.
Primary human‐related sources include agricultural soil management, animal manure
management, sewage treatment, mobile and stationary combustion of fossil fuel, adipic
acid production, and nitric acid production. The GWP of nitrous oxide is 310.
Hydrofluorocarbons (HFCs). HFCs typically are used as refrigerants in both stationary
refrigeration and mobile air conditioning. The use of HFCs for cooling and foam‐blowing
is growing particularly as the continued phase‐out of chlorofluorocarbons (CFCs) and
hydrochlorofluorocarbons (HCFCs) gains momentum. The GWP of HFCs ranges from
140 for HFC‐152a to 6,300 for HFC‐236fa.
Perfluorocarbons (PFCs). Perfluorocarbons are compounds consisting of carbon and
fluorine. They are primarily created as a byproduct of aluminum production and
semiconductor manufacturing. Perfluorocarbons are potent GHGs with a GWP several
thousand times that of carbon dioxide, depending on the specific PFC. Another area of
concern regarding PFCs is their long atmospheric lifetime (up to 50,000 years) (EIA n.d.).
The GWPs of PFCs range from 5,700 to 11,900.
Sulfur Hexafluoride (SF6). Sulfur hexafluoride is a colorless, odorless, nontoxic,
nonflammable gas. It is mainly used in such purposes as magnesium casting operations,
semiconductor manufacture, and as an electrical insulator in high voltage equipment
that transmits and distributes electricity. Minor uses include certain medical and
laboratory uses. Sulfur hexafluoride is the most potent GHG that has been evaluated by
the Intergovernmental Panel (IPCC) on Climate Change with a GWP of 23,900. However,
its global warming contribution is not as high as the GWP would indicate due to its low
mixing ratio, as compared to carbon dioxide (4 parts per trillion [ppt] in 1990 versus 365
parts per million [ppm] of CO2) (U.S. EPA).
The primary GHGs of concern relative to the proposed project are CO2, CH4, and N2O. These
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 27 of 74
three GHGs are generally emitted from combustion activities. The other GHGs listed above are
related to specific industrial uses and not anticipated to be emitted in measurable or substantial
quantities by the project.
Contributions to Greenhouse Gas Emissions
Global
The World Meteorological Organization (WMO) and United Nations Environmental Program
(UNEP) established the Intergovernmental Panel on Climate Change (IPCC) in 1988. The goal of
the IPCC is to evaluate the risk of climate change caused by human activities. The IPCC assesses
information (i.e., scientific literature) regarding human‐induced climate change, impacts of
human‐induced climate change, and options for adaptation and mitigation of climate change.
The IPCC reports its evaluations in special reports called “assessment reports,” the latest of
which, AR4, was published in 2007.12
Worldwide anthropogenic (man‐made) GHG emissions are tracked for industrialized nations
and developing nations. The IPCC estimates worldwide emissions in 1990 were 39,400 million
metric tons of CO2 equivalent (MMTCO2e).13 The most recent anthropogenic GHG emissions
from industrialized and developing nations are available through 2007 and 2005, respectively.
The IPCC estimates sum of these emissions totaled approximately 43,363 MMTCO2e. This
translates into approximately 6.8 MTCO2e per capita. The IPCC projects a significant rise in
worldwide GHG emissions as world population continues to grow and underdeveloped
countries industrialize to raise living standards.
It should be noted that global emissions inventory data are not all from the same year and may
vary considerably depending on the quality and source of the emissions inventory data. While
the majority of global CO2 emissions are from the burning of fossil fuels, roughly a quarter of the
carbon entering the atmosphere is from land‐use changes, which are harder to track. The IPCC is
currently working to produce their Fifth Assessment Report with updated emissions estimates
and analysis. Table 4.1‐1 shows the most recently available comparative GHG emissions for
various relevant reporting entities.
United States
The most recent United States Greenhouse Gas Inventory Report of national GHG emissions was
prepared by the EPA in 2010. This inventory covers the period from 1990 to 2008. The EPA
estimates that the United States emitted 6,127 MMTCO2e in 1990. In 2008, total U.S. greenhouse
12 The IPCC’s Fourth Assessment Report is available online at http://www.ipcc.ch/. 13 The CO2 equivalent emissions commonly are expressed as “million metric tons of carbon dioxide equivalent
(MMTCO2E).” The carbon dioxide equivalent for a gas is derived by multiplying the tons of the gas by the associated GWP, such that MMTCO2E = (million metric tons of a GHG) x (GWP of the GHG). For example, the GWP for methane is 21. This means that the emission of one million metric tons of methane is equivalent to the emission of 21 million metric tons of CO2.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 28 of 74
gas emissions were 6,956 MMTCO2e, or approximately 20 MTCO2e per capita. Overall, total
U.S. emissions of GHG’s have risen by approximately 14 percent from 1990 to 2008. Emissions
declined from 2007 to 2008, decreasing by 2.9 percent. This decrease is primarily a result of a
decrease in demand for transportation fuels associated with the high costs of these fuels that
occurred in 2008. Additionally, electricity demand declined in 2008 in part due to a significant
increase in the cost of fuels used to generate electricity. Preliminary numbers for 2009 show
national emissions decreasing by an additional 3.4 percent.
The primary greenhouse gas emitted by human activities in the United States is CO2,
representing approximately 85.1 percent of total greenhouse gas emissions. The largest source of
CO2, and of overall greenhouse gas emissions, is fossil fuel combustion, primarily for
transportation and electricity generation.
Table 4.1‐1 Comparative GHG Emissions
GHG Emissions
(MMTCO2e)
~ Per Capita
(MTCO2e)
World 43,363 6.8
United States 6,956 20
California 474 14
Bay Area Region 97.4 15
San Francisco 8.5 11
State of California
The California Air Resources Board (CARB) compiles GHG inventories for the State of California.
Based upon the 2008 GHG inventory data, the latest year for which data are available, California
emitted 427 MMTCO2e in 1990 and 474 MMTCO2e in 2008. 14 This translates into approximately
14 MTCO2e per capita in 2008.
Between 1990 and 2008, the population of California grew by approximately 8.1 million (from
29.8 to 37.9 million), or 27.2 percent.15 In addition, the California economy, measured as gross
state product, grew from $788 billion in 1990 to $1.8 trillion in 2008 representing an increase of
approximately 128 percent.16 Despite the population and economic growth, California’s net GHG
emissions grew by only 11 percent. The California Energy Commission attributes the
proportionally slower rate of growth in greenhouse gas emissions in part to the success of
California’s energy efficiency and renewable energy programs.
14 Including emissions resulting from imported electrical power in 2008 15 California Department of Finance 2010a, U.S. Census Bureau 2010 16 California Department of Finance 2010
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 29 of 74
Table 4.1‐2, GHG Emissions in California, provides a summary of GHG emissions reported in
California in 1990 and 2008 separated by categories defined by the United Nations
Intergovernmental Panel on Climate Change (IPCC).
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 30 of 74
Table 4.1‐2 GHG Emission Detail in California
Source Category
1990
(MMTCO2e)
Percent
of Total
2008
(MMTCO2e)
Percent
of Total
ENERGY 386.41 89.2% 413.80 86.6%
Energy Industries 157.33 36.3% 171.23 35.8%
Manufacturing Industries & Construction 24.24 5.6% 16.67 3.5%
Transport 150.02 34.6% 173.94 36.4%
Other (Resident/Commercial/Institutional) 48.19 11.1% 46.59 9.8%
Non‐Specified 1.38 0.3% 0.00 0.0%
Fugitive Emissions ‐ Oil & Natural Gas 2.94 0.7% 3.28 0.7%
Fugitive Emissions Other Energy Prod. 2.31 0.5% 2.09 0.4%
INDUSTRIAL PROCESS & PRODUCT USE 18.34 4.2% 30.11 6.3%
Mineral Industry 4.85 1.1% 5.35 1.1%
Chemical Industry 2.34 0.5% 0.06 0.0%
Non‐Energy Products Fuels & Solvent Use 2.29 0.5% 1.97 0.4%
Electronics Industry 0.59 0.1% 0.80 0.2%
Substitutes ‐ Ozone Depleting Substances 0.04 0.0% 13.89 2.9%
Other Product Manufacture and Use 3.18 0.7% 1.66 0.3%
Other 5.05 1.2% 6.39 1.3%
AGRI., FORESTRY, & OTHER LAND USE 19.11 4.4% 24.42 5.1%
Livestock 11.67 2.7% 16.28 3.4%
Land 0.19 0.0% 0.19 0.0%
Aggr. Sources & Non‐CO2 Sources on Land 7.26 1.7% 7.95 1.7%
WASTE
Solid Waste Disposal
Wastewater Treatment & Discharge
9.42
6.26
3.17
2.2%
1.4%
0.7%
9.41
6.71
2.70
2.0%
1.4%
0.6%
EMISSIONS SUMMARY
Gross California Emissions
Sinks from Forests and Rangelands
Net California Emissions
433.29
‐6.69
426.60
477.74
‐3.98
473.76
Source:
California Air Resources Board. “California Greenhouse Gas 1990‐2004 Inventory by IPCC Category – Summary.”
http://www.arb.ca.gov/cc/inventory/data/data.htm 2007
California Air Resources Board. “California Greenhouse Gas 2000‐2008 Inventory by IPCC Category – Summary.”
http://www.arb.ca.gov/cc/inventory/data/data.htm 2010
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 31 of 74
Regional The Bay Area Air Quality Management (BAAQMD) has compiled several GHG inventories for
the nine county Bay Area region, the most recent of which was updated in February 2010.17
Based upon that GHG inventory, the entire region emitted 87.7 MMTCO2e in 1990, and, 97.4
MMTCO2e, or 11% more, in 2008.18 This translates into approximately 15 MTCO2e per capita.
Carbon Dioxide accounts for 91.6% of Bay Area emissions. Carbon dioxide emissions are mainly
associated with combustion of carbon‐bearing fossil fuels such as gasoline, diesel, and natural
gas used in mobile sources and energy‐generation‐related activities such as commercial power
plants.
San Francisco
The San Francisco Department of the Environment tracks the City’s greenhouse gas emissions.19
In 2002 the San Francisco Board of Supervisors adopted a resolution that called for the City to
develop plans to reduce its greenhouse gas emissions to 20% below 1990 levels by the year 2012.
In 2004 the Department of the Environment and the PUC, issued “The Climate Action Plan for
San Francisco” which included an accounting of greenhouse gas activities. In 1990, San
Francisco’s total greenhouse gas emissions were approximately 9.1 MMTCO2e. 20 San Franciscoʹs
Climate Action Plan found that 49% of the Cityʹs greenhouse gas emissions came from buildings,
and 51% from transportation.
In 2008 the City estimated that its greenhouse gas emissions had decreased to 8.5 MMTCO2e,
about 7 percent below the 1990 emissions levels. In May 2008 the Board of Supervisors updated
the City goals: that by 2017, reduce greenhouse gas emissions by 25% below 1990 levels; by 2025,
reduce greenhouse gas emissions by 40% below 1990 levels; by 2050, reduce greenhouse gas
emissions by 80% below 1990 levels.
Effects of Global Climate Change
The primary effect of global climate change has been a rise in the average global tropospheric
temperature of 0.2° Celsius per decade, determined from meteorological measurements
worldwide between 1990 and 2005 (IPCC 2007). Climate change modeling using 2000 emission
rates suggests that further warming is likely to occur, which would induce further changes in the
global climate system during the current century (IPCC 2007). Changes to the global climate
system and ecosystems, and to the proposed project site, could include:
Changing weather patterns, including changes to precipitation, ocean salinity, and wind
patterns, and more energetic aspects of extreme weather including droughts, heavy
17http://www.baaqmd.gov/~/media/Files/Planning%20and%20Research/Emission%20Inventory/regionalinventory200
7_2_10.ashx 18 http://hank.baaqmd.gov/pln/documents/regionalinventory2007_003_000_000.pdf 19 http://www.livablecity.org/campaigns/documents/SF%20climate%20ordinance%202008.pdf 20 http://www.sfenvironment.org/downloads/library/climateactionplan.pdf
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 32 of 74
precipitation, heat waves, extreme cold, and the intensity of tropical cyclones (IPCC
2007);
Declining sea ice, thereby increasing sea levels and sea surface evaporation rates with a
corresponding increase in tropospheric water vapor due to the atmosphere’s ability to
hold more water vapor at higher temperatures (IPCC 2007);
Summer warming projections in the first 30 years of the 21st century ranging from about
0.5 to 2 degrees Celsius (°C) (0.9 to 3.6 °F) and by the last 30 years of the 21st century,
from about 1.5 to 5.8 °C (2.7 to 10.5 °F) (CalEPA 2006).
4.1.3 REGULATORY CONSIDERATIONS
Federal
In Massachusetts vs. EPA, the Supreme Court held that United States Environmental Protection
Agency (U.S. EPA) has the statutory authority under Section 202 of the Clean Air Act (CAA) to
regulate GHGs from new motor vehicles. The court did not hold that the U.S. EPA was required
to regulate GHG emissions; however, it indicated that the agency must decide whether GHGs
from motor vehicles cause or contribute to air pollution that is reasonably anticipated to
endanger public health or welfare. Upon the final decision, the President signed Executive Order
13432 on May 14, 2007, directing the U.S. EPA, along with the Departments of Transportation,
Energy, and Agriculture, to initiate a regulatory process that responds to the Supreme Court’s
decision.
On July 11, 2008, the U.S. EPA issued an Advanced Notice of Proposed Rulemaking (ANPRM)
on regulating GHGs under the CAA. The ANPRM reviews the various CAA provisions that may
be applicable to the regulation of GHGs and presents potential regulatory approaches and
technologies for reducing GHG emissions. On April 10, 2009, the U.S. EPA published the
Proposed Mandatory Greenhouse Gas Reporting Rule in the Federal Register (U.S. EPA 2009). The
rule was adopted on September 22, 2009 and covers approximately 10,000 facilities nationwide,
accounting for 85 percent of U.S. GHG emissions.
On September 15, 2009, the U.S. EPA and the Department of Transportation’s (DOT) National
Highway Traffic Safety Administration (NHTSA) issued a joint proposal to establish a national
program consisting of new standards for model year 2012 through 2016 light‐duty vehicles that
will reduce GHG emissions and improve fuel economy. The proposed standards would be
phased in and would require passenger cars and light‐duty trucks to comply with a declining
emissions standard. In 2012, passenger cars and light‐duty trucks would have to meet an average
standard of 295 grams of CO2 per mile and 30.1 miles per gallon. By 2016, the vehicles would
have to meet an average standard of 250 grams of CO2 per mile and 35.5 miles per gallon.21
These standards were formally adopted by the U.S. EPA and DOT on April 1, 2010.
21 The CO2 emission standards and fuel economy standards stated are based on U.S. EPA formulas
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 33 of 74
On December 7, 2009, the U.S. EPA Administrator signed two distinct findings regarding GHGs
under section 202(a) of the Clean Air Act:
Endangerment Finding: The Administrator finds that the current and projected
concentrations of the six key well‐mixed GHGs (carbon dioxide, methane, nitrous oxide,
hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride) in the atmosphere
threaten the public health and welfare of current and future generations.
Cause or Contribute Finding: The Administrator finds that the combined emissions of
these well‐mixed greenhouse gases from new motor vehicles and new motor vehicle
engines contribute to the greenhouse gas pollution, which threatens public health and
welfare.
While these findings do not impose additional requirements on industry or other entities, this
action was a prerequisite to finalizing the U.S. EPA’s proposed GHG emissions standards for
light‐duty vehicles, which were jointly proposed by the U.S. EPA and DOT.
California
Key state laws and regulations related to GHG emissions are described below.
Executive Order S‐3‐05 and the Climate Action Team
In June 2005, Governor Schwarzenegger established California’s GHG emissions reduction
targets in Executive Order S‐3‐05. The Executive Order established the following goals: GHG
emissions should be reduced to 2000 levels by 2010, 1990 levels by 2020, and 80 percent below
1990 levels by 2050. The Secretary of Cal EPA is required to coordinate efforts of various agencies
in order to collectively and efficiently reduce GHGs. Some of the agency representatives involved
in the GHG reduction plan include the Secretary of the Business, Transportation and Housing
Agency, the Secretary of the Department of Food and Agriculture, the Secretary of the Resources
Agency, the Chairperson of CARB, the Chairperson of the CEC, and the President of the Public
Utilities Commission.
Representatives from each of the aforementioned agencies comprise the Climate Action Team.
The Cal/EPA secretary is required to submit a biannual progress report from the Climate Action
Team to the governor and state legislature disclosing the progress made toward GHG emission
reduction targets. In addition, another biannual report must be submitted illustrating the impacts
of global warming on California’s water supply, public health, agriculture, coastline, and forests,
and reporting possible mitigation and adaptation plans to combat these impacts. Strategies
currently being implemented by state agencies include CARB introducing vehicle climate change
standards and diesel anti‐idling measures, the Energy Commission implementing building and
appliance efficiency standards, and the Cal/EPA implementing their green building initiative.
The Climate Action Team also recommends future emission reduction strategies, such as using
only low‐GWP refrigerants in new vehicles, developing ethanol as an alternative fuel,
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 34 of 74
reforestation, solar power initiatives for homes and businesses, and investor‐owned utility
energy efficiency programs. According to the report, implementation of current and future
emission reduction strategies have the potential to achieve the goals set forth in Executive Order
S‐3‐05.
Assembly Bill 32
In furtherance of the goals established in Executive Order S‐3‐05, the legislature enacted
Assembly Bill 32, the California Global Warming Solutions Act of 2006, which Governor
Schwarzenegger signed on September 27, 2006. AB 32 represents the first enforceable statewide
program to limit GHG emissions from all major industries with penalties for noncompliance. AB
32 requires the State to undertake several actions – the major requirements are discussed
State of California Greenhouse Gas Inventory and 2020 Limit
As required under AB 32, on December 6, 2007, CARB approved the 1990 greenhouse gas
emissions inventory, thereby establishing the emissions limit for 2020. The 2020 emissions limit
was set at 427 MMTCO2e. CARB also projected the state’s 2020 GHG emissions under “business
as usual” (BAU) conditions—that is, emissions that would occur without any plans, policies, or
regulations to reduce GHG emissions. CARB used an average of the State’s GHG emissions from
2002 through 2004 and projected the 2020 levels based on population and economic forecasts.
The projected net emissions totaled approximately 596 MMTCO2e. Therefore, the state must
reduce its 2020 BAU emissions by approximately 29 percent in order to meet the 1990 target.
The inventory revealed that for transportation, the sector with the greatest amount of emissions,
in 1990 totaled about 150 million metric tons of CO2e (about 35 percent of the stateʹs total
emissions) (see Table 4.1‐2). By 2008, transportation‐related emissions rose to about 174 million
metric tons (about 36 percent of the state’s total emissions). AB 32 does not require individual
sectors to meet their individual 1990 GHG emissions inventory; the total statewide emissions are
required to meet the 1990 threshold by 2020.
CARB Mandatory Reporting Requirements
In addition to the 1990 emissions inventory, CARB also adopted regulations requiring the
mandatory reporting of GHG emissions for large facilities on December 6, 2007. The mandatory
reporting regulations require annual reporting from the largest facilities in the state, which
account for approximately 94 percent of point source greenhouse gas emissions from industrial
and commercial stationary sources in California. About 800 separate sources fall under the new
reporting rules and include electricity‐generating facilities, electricity retail providers and power
marketers, oil refineries, hydrogen plants, cement plants, cogeneration facilities, and industrial
sources that emit over 25,000 tons of carbon dioxide each year from on‐site stationary
combustion sources. Transportation sources, which account for 38 percent of California’s total
greenhouse gas emissions, are not covered by these regulations but will continue to be tracked
through existing means. Affected facilities will begin tracking their emissions in 2008, to be
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 35 of 74
reported beginning in 2009, with a phase‐in process to allow facilities to develop reporting
systems and train personnel in data collection. Emissions for 2008 may be based on best available
emission data. Beginning in 2010, however, emissions reporting requirements will be more
rigorous and will be subject to third‐party verification. Verification will take place annually or
every three years, depending on the type of facility. UCSF’s campus power plant falls under the
CARB mandatory reporting regulations, and has had its emission levels certified by third‐party
verification.
AB 32 Climate Change Scoping Plan
As indicated above, AB 32 requires CARB to adopt a scoping plan indicating how reductions in
significant GHG sources will be achieved through regulations, market mechanisms, and other
actions. After receiving public input on their discussion draft of the Climate Change Proposed
Scoping Plan released in June 2008, CARB released the Climate Change Proposed Scoping Plan in
October 2008 that contains an outline of the proposed state strategies to achieve the 2020
greenhouse gas emission limits. The CARB Governing Board approved the Climate Change
Scoping Plan on December 11, 2008. Key elements of the Scoping Plan include the following
recommendations:
Expanding and strengthening existing energy efficiency programs as well as building
and appliance standards;
Achieving a statewide renewable energy mix of 33 percent;
Developing a California cap‐and‐trade program that links with other Western Climate
Initiative partner programs to create a regional market system;
Creating targeted fees, including a public goods charge on water use, fees on high global
warming potential gases, and a fee to fund the administrative costs of the state’s long‐
term commitment to AB 32 implementation.
Establishing targets for transportation‐related greenhouse gas emissions for regions
throughout California and pursuing policies and incentives to achieve those targets; and Adopting and implementing measures pursuant to existing state laws and policies,
including California’s clean car standards, goods movement measures, and the Low
Carbon Fuel Standard.
Under the Scoping Plan, approximately 85 percent of the state’s stationary emissions are subject
to a cap‐and‐trade program where covered sectors are placed under a declining emissions cap.
The emissions cap incorporates a margin of safety whereas the 2020 emissions limit will still be
achieved even in the event that uncapped sectors do not fully meet their anticipated emission
reductions. Emissions reductions will be achieved through regulatory requirements and the
option to reduce emissions further or purchase allowances to cover compliance obligations. It is
expected that emission reduction from this cap‐and‐trade program will account for a large
portion of the reductions required by AB 32.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 36 of 74
On December 16th, 2010 CARB adopted cap‐and‐trade regulations designed to cut greenhouse
gases in the State 15 percent by 2020.22 These regulations were scheduled to go into effect Jan. 1,
2012.
On January 21, 2011 in Association of Irritated Residents, et al. v. California Air Resources Board, the
San Francisco Superior Court partially granted a peremptory writ of mandate to petitioners, e.g.
environmental justice groups, which had alleged CARB failed to comply with the California
Environmental Quality Act (CEQA) (Case No. CPF‐09‐509562). 23 Specifically, the petitioners
alleged that CARB failed to adequately analyze all potential alternatives and prematurely
adopted the Plan prior to fully responding to public comment. Under this tentative ruling,
CARB is ordered to delay implementation of the cap and trade program until CARB is in
ʺcomplete compliance with its obligations under its certified regulatory program and CEQA.ʺ
The cap‐and‐trade regulations are written to primarily affect stationary sources such as electricity
generation. Mobile source GHG emission reductions such as from automobiles are regulated by
other CARB programs.
Assembly Bill 1493 (Vehicular Emissions)
The Clean Air Act (CAA) gives California special authority to enact stricter air pollution
standards for motor vehicles than the federal government’s. The U.S. EPA must approve a
waiver, however, before California’s rules may go into effect. The California Air Resources
Board requested a waiver to the CAA in December 2005. On June 30, 2009, U.S. EPA granted of
Clean Air Act preemption to California for its greenhouse gas emission standards for motor
vehicles beginning with the 2009 model year24. On September 24, 2009, the ARB adopted
amendments to the Assembly Bill 1493 (Pavley) (2002) regulations that reduce greenhouse gas
(GHG) emissions in new passenger vehicles from 2009 through 2016. It is expected that the
Pavley regulations will reduce GHG emissions from California passenger vehicles by about 22
percent in 2012 and about 30 percent in 2016. These reductions, along with others approved
actions such as the low carbon fuel standard, are projected to reduce California transportation
associated emissions 35%, or by 67.8 MMTCO2e, by 2020.
Senate Bill 97 (CEQA Guidelines)
In August 2007, the legislature enacted SB 97 (Dutton), which directed the Governor’s Office of
Planning and Research (OPR) to develop guidelines under CEQA for the mitigation of
greenhouse gas emissions. A number of actions have taken place under SB 97, which are
discussed below.
22 http://www.arb.ca.gov/board/ma/2010/ma121610.htm 23 http://cdn.law.ucla.edu/SiteCollectionDocuments/Environmental%20Law/AIR%20v%20ARB%20Tentative%20Ruli
ng.pdf 24 http://www.epa.gov/otaq/climate/ca-waiver.htm
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 37 of 74
OPR Climate Change Technical Advisory
On June 19, 2008, OPR issued a technical advisory as interim guidance regarding the analysis of
GHG emissions in CEQA documents (OPR 2008). The advisory indicated that a project’s GHG
emissions, including those associated with vehicular traffic and construction activities should be
identified and estimated. The advisory further recommended that the lead agency determine
significance of the impacts and impose all mitigation measures that are necessary to reduce GHG
emissions to a less than significant level. The advisory did not recommend a specific threshold of
significance. Instead, OPR requested that CARB recommend a method for setting thresholds that
lead agencies may adopt (OPR 2009).
CEQA Guideline Amendments
In its work to formulate CEQA Guideline Amendments for GHG emissions, OPR submitted the
Proposed Draft CEQA Guideline Amendments for Greenhouse Gas Emissions to the Secretary for
Natural Resources on April 13, 2009. The Natural Resources Agency conducted formal
rulemaking procedures in 2009 and adopted the CEQA Guideline Amendments on December 30,
2009. They became effective in March 2010.
Senate Bill 375
The California legislature passed SB 375 (Steinberg) on September 1, 2008. SB 375 requires CARB
to set regional greenhouse gas reduction targets after consultation with local governments. The
target must then be incorporated within that region’s regional transportation plan (RTP), which
is used for long‐term transportation planning, in a Sustainable Communities Strategy. SB 375
also requires each region’s regional housing needs assessment (RHNA) to be adjusted based on
the Sustainable Communities Strategy in its RTP. Additionally, SB 375 reforms the
environmental review process to create incentives to implement the strategy, especially transit
priority projects. The governor signed SB 375 into law on September 30, 2008.
On January 23, 2009, CARB appointed a Regional Targets Advisory Committee (RTAC) to
provide recommendations and methodologies to be used in the target setting process. The RTAC
provided its recommendations in a report to CARB on September 29, 2009. On August 9, 2010,
CARB staff issued the Proposed Regional Greenhouse Gas Emission Reduction Targets For Automobiles
And Light Trucks Pursuant To Senate Bill 375 (CARB 2010b). CARB staff proposed draft reduction
targets for the four largest MPOs (Bay Area, Sacramento, Southern California, and San Diego) of
7 to 8 percent for 2020 and reduction targets between 13 to 16 percent for 2035. For the Bay Area,
CARB established a draft target of 7 percent for 2020 and 15 percent for 2035. These targets were
recommended to CARB by the Metropolitan Transportation Commission, which adopted the
thresholds for its planning purposes on July 28, 2010. Of note, the proposed reduction targets
explicitly exclude emission reductions expected from the AB 1493 and low carbon fuel standard
regulations. CARB adopted the final targets on September 23, 2010.
Title 24 Building Standards Code
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 38 of 74
The California Energy Commission first adopted Energy Efficiency Standards for Residential and
Nonresidential Buildings (California Code of Regulations, Title 24, Part 6) in 1978 in response to
a legislative mandate to reduce energy consumption in the state. Although not originally
intended to reduce GHG emissions, increased energy efficiency, and reduced consumption of
electricity, natural gas, and other fuels would result in fewer GHG emissions from residential
and nonresidential buildings subject to the standard. The standards are updated periodically to
allow for the consideration and inclusion of new energy efficiency technologies and methods.
The latest revisions were adopted in 2008 and became effective on January 1, 2010.
Part 11 of the Title 24 Building Standards Code is referred to as the California Green Building
Standards Code (CALGreen Code). The purpose of the CALGreen Code is to “improve public
health, safety and general welfare by enhancing the design and construction of buildings through
the use of building concepts having a positive environmental impact and encouraging
sustainable construction practices in the following categories: (1) Planning and design; (2) Energy
efficiency; (3) Water efficiency and conservation; (4) Material conservation and resource
efficiency; and (5) Environmental air quality” (California Building Standards Commission 2009).
Unless otherwise noted in the regulation, all newly constructed buildings in California are
subject to the requirements of the CALGreen Code.
Regional
Bay Area Air Quality Management District
On June 2, 2010, the BAAQMD adopted updated CEQA Air Quality Guidelines. These guidelines
contain greenhouse gas operational emissions significance thresholds and recommended
methodologies and models to be used for assessing the impacts of project‐specific GHG
emissions on global climate change (BAAQMD 2010a). The updated CEQA Air Quality Guidelines
contain project‐level screening criteria and recommended significance thresholds for evaluation
of operational GHG emissions from a proposed project. The guidelines also contain
recommended methodologies to use to estimate these emissions and provide recommended
measures for reducing GHG emissions from land use development projects and stationary
sources.
Local Plans and Policies
University of California Policy on Sustainable Practices
The Regents have delegated authority to the President for promulgating policy promoting
sustainable new capital projects, existing University facilities, and campus transportation
resources. The University of California Policy on Sustainable Practices is a system‐wide
commitment to minimize the University of California’s impact on the environment and reduce
the University’s dependence on non‐renewable energy sources.25 The University of California
25 http://www.universityofcalifornia.edu/sustainability/documents/policy_sustain_prac.pdf
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 39 of 74
Policy on Sustainable Practices promotes the principles of energy efficiency and sustainability in
the areas of Green Building Design; Clean Energy Standard; Climate Protection Practices;
Sustainable Transportation Practices; Sustainable Operations; Recycling and Waste Management;
Environmentally Preferable Purchasing Practices; and Food, all of which help reduce GHG
emissions from University operations, and meet the State goals of reducing GHG emissions to
1990 levels by 2020..
The Policy guidelines currently recommend that University operations:
Incorporate the principles of energy efficiency and sustainability in all capital projects,
renovation projects, operations and maintenance within budgetary constraints and
programmatic requirements.
Minimize the use of non‐renewable energy sources on behalf of the University’s built
environment by creating a portfolio approach to energy use, including the use of local
renewable energy and purchase of green power from the grid as well as conservation
measures that reduce energy consumption.
Incorporate alternative means of transportation to/from and within the campus to
improve the quality of life on campus and in the surrounding community. The campuses
will continue their strong commitment to provide affordable on‐campus housing, in
order to reduce the volume of commutes to and from campus. These housing goals are
detailed in the campuses’ Long Range Development Plans.
Track, report and minimize greenhouse gas emissions on behalf of University operations.
Minimize the amount of University‐generated waste sent to landfill.
Utilize the University’s purchasing power to meet its sustainability objectives.
UCSF Climate Action Plan
UCSF published its Climate Action Plan (CAP) in December of 2009 in order to comply with the
UC Policy on Sustainable Practices as well as meet the requirements of the American Colleges
and University Presidents Climate Commitment (ACUPCC), of which the UC system is a
signatory. The UCSF CAP includes the UCSF 1990 GHG emissions baseline, current (2008)
emissions, projected 2020 emissions, sustainability efforts to date, and outlines future reduction
measures UCSF will undertake in order to meet the emissions reduction goal. UCSF’s 1990 GHG
emissions levels were estimated to be 81,950 MTCO2e and its 2008 GHG emission levels to be
162,713 MTCO2e year. UCSF has committed to reduce its GHG emissions from all of its
operations to the 1990 level by 2020, with the eventual goal of achieving carbon neutrality for the
campus. As part of the system‐wide emissions reduction effort, UCSF regularly reports to The
Regents its emissions, progress towards reduction goals, and measures used or proposed to meet
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 40 of 74
the Policy on Sustainable Practices goals.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 41 of 74
4.1.4 SIGNIFICANCE STANDARDS AND ANALYSIS METHODOLOGY
Significance Criteria
In accordance with Senate Bill (SB) 97, the Natural Resources Agency adopted amendments to
the State CEQA Guidelines on December 30, 2009 (effective March 2010), which include criteria for
evaluating GHG emissions.26 According to the amended Appendix G of the State CEQA
Guidelines, a project would have a significant effect on the environment if it would:
Generate greenhouse gas emissions, either directly or indirectly, that may have a
significant impact on the environment; or
Conflict with an applicable plan, policy or regulation adopted for the purpose of
reducing the emissions of greenhouse gases.
The amended State CEQA Guidelines include a new Section 15064.4, which states that, when
making a determination of the significance of GHG emissions, a lead agency shall have
discretion to determine whether to: (1) Use a model or methodology to quantify greenhouse gas
emissions resulting from a project, and which model or methodology to use; and/or (2) Rely on a
qualitative analysis or performance based standards.
Section 15064.4 also states that a lead agency should consider the following factors when
assessing the significance of GHG emissions on the environment: (1) The extent to which the
project may increase or reduce greenhouse gas emissions as compared to the existing
environmental setting; (2) Whether the project emissions exceed a threshold of significance that
the lead agency determines applies to the project; and (3) The extent to which the project
complies with regulations or requirements adopted to implement a statewide, regional, or local
plan for the reduction or mitigation of greenhouse gas emissions.
The first Appendix G criteria may be evaluated by performing a direct calculation of the GHG
emissions resulting from the proposed project and comparing the emissions with the available
significance thresholds. The BAAQMD has established project‐level screening criteria and
significance thresholds for operational GHG emissions in its CEQA Air Quality Guidelines. The
BAAQMD’s thresholds of significance for operational‐related GHG emissions are as follows:
For land use development projects, the threshold is compliance with a qualified GHG
Reduction Strategy; or annual emissions less than 1,100 metric tons CO2e per year
(MTCO2e/yr); or 4.6 MT CO2e/person/yr (residents plus employees). Land use
development projects include residential, commercial, industrial, and public land uses
and facilities.
For stationary‐source projects, the threshold is 10,000 MTCO2e/yr. Stationary‐source
projects include land uses that would accommodate processes and equipment that emit
26 http://ceres.ca.gov/ceqa/guidelines/
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 42 of 74
GHG emissions and would require an Air District permit to operate.
The BAAQMD guidelines do not contain a quantitative threshold of significance for the
evaluation of GHG emissions resulting from a project’s construction activities.
The second Appendix G criteria may be evaluated by demonstrating compliance with plans,
policies, or regulations adopted by local governments to curb GHG emissions. According to the
Natural Resources Agency:
Provided that such plans contain specific requirements with respect to resources that are
within the agency‘s jurisdiction to avoid or substantially lessen the agency‘s
contributions to GHG emissions, both from its own projects and from private projects it
has approved or will approve, such plans may be appropriately relied on in a cumulative
impacts analysis (Natural Resources Agency 2009).
Under CEQA, “the determination of whether a project may have a significant effect on the
environment calls for careful judgment on the part of the public agency involved, based to the
extent possible on scientific and factual data” (CEQA Section 15064). CEQA grants agencies with
the general authority to adopt criteria for determining whether a given impact is “significant”
(California Public Resources Code Section 21082). When no guidance exists under CEQA, the
agency may look to and assess general compliance with comparable regulatory schemes. The
BAAQMD’s CEQA Air Quality Guidelines represent a comparable regulatory scheme.
Based on the above, the proposed project’s significance with respect to the GHG emissions and
global climate change will be assessed based on the BAAQMD’s GHG thresholds of significance
and on the project features and GHG reduction measures that are consistent with the BAAQMD’s
recommended measures to reduce GHG emissions.
Methodology
OPR in its Technical Advisory has recommended that GHG emissions from project‐related
traffic, energy consumption, water usage, and construction activities, should be identified and
estimated, to the extent that data are available to calculate such emissions. In addition, CARB
staff has considered extensively the value of indirect emissions in a mandatory reporting
program. CARB believes that indirect energy usage provides a more complete picture of the
emissions footprint of a facility: “As facilities consider changes that would affect their emissions
– addition of a cogeneration unit to boost overall efficiency even as it increases direct emissions,
for example – the relative impact on total (direct plus indirect) emissions by the facility should be
monitored. Annually reported indirect energy usage also aids the conservation awareness of the
facility and provides information” to CARB to be considered for future strategies by the
industrial sector. For these reasons, CARB has proposed requiring the calculation of direct and
indirect GHG emissions as part of the AB 32 reporting requirements, and this analysis does so
(CARB 2007).
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 43 of 74
The California Air Pollution Control Officers Association (CAPCOA) has stated that the
information needed to characterize GHG emissions from manufacture, transport, and end‐of‐life
of construction materials (often referred to as lifecycle emissions) would be speculative at the
CEQA analysis level (CAPCOA 2008). Since accurate and reliable data does not exist for
estimating lifecycle emissions for the proposed project, the analysis does not assess such lifecycle
GHG emissions.
The data sources and tools used to evaluate the GHG impacts associated with construction and
operation of the proposed project include the URBEMIS2007 Environmental Management
Software, and information provided in the Software User’s Guide [for] URBEMIS2007 for Windows
(Rimpo and Associates 2008) and calculation algorithms supported by the sources listed above.
The URBEMIS2007 model utilizes the EMFAC2007 emissions factor model for on‐road motor
vehicle sources and the OFFROAD2007 emissions factor model for off‐road equipment. Site‐
specific or project‐specific data were used in the URBEMIS2007 model where available. Where
information was not available for the project, model default values suggested by the BAAQMD
were selected. The average daily trip (ADT) generation rate for the proposed project was based
on the project’s traffic study. The BAAQMD has developed a greenhouse gas emissions modeling
spreadsheet, called BGM, which uses URBEMIS2007 files in conjunction with emission and
resource consumption factors specific to the Bay Area to calculate greenhouse gas emissions from
projects within the BAAQMD’s jurisdiction. The BGM is the BAAQMD’s preferred method for
estimating operational GHG emissions. The BGM was used in conjunction with URBEMIS2007.
Additional sources consulted for this analysis include data and guidance from the U.S. EPA, the
U.S. Energy Information Administration, CARB, the California Energy Commission, the
California Climate Action Registry’s General Reporting Protocol, and other GHG and global
climate change data as referenced. Emission calculations conducted for the proposed project are
contained in Appendix B.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 44 of 74
4.1.5 IMPACTS AND MITIGATION MEASURES
Impact GHG‐1: Project development would generate greenhouse gas emissions, either directly
or indirectly, that could have a significant impact on the environment. (Significant; Less than
significant with mitigation)
Operational Impacts
Once operational, the proposed project would generate direct operational emissions of GHGs,
primarily CO2, CH4, and N2O, which would be the result of fuel combustion from the building’s
lighting and elevator systems, from fuel combustion by the motor vehicles using the garage, and
from motor vehicle air conditioning. Motor vehicle air conditioning systems may also use HFCs
(and HCFCs and CFCs to the extent that they have not been completely phased out at later
dates); however, these emissions are not quantified since they would only occur through
accidental leaks and it is not possible to estimate the frequency of accidental leaks without some
level of speculation. It should be noted that CARB has adopted a mobile air conditioning
regulation that reduces emissions associated with the use of small containers of automotive
refrigerants. This regulation requires that refrigerant container be self‐sealing and went into
effect on January 1, 2010. CARB has also proposed regulations that require the use of lower GWP
refrigerants in vehicle air conditioners.
Mobile Source Emissions
Emissions from motor vehicles were calculated using the BAAQMD Greenhouse Gas Model
(BGM), which uses URBEMIS2007 files in conjunction with emission and consumption factors
specific to the Bay Area to calculate greenhouse gas emissions from projects within the
BAAQMD’s jurisdiction. The BGM is the BAAQMD’s preferred method for estimating
operational GHG emissions and takes into account the California specific emissions reductions
required for motor vehicles. For the purposes of estimating GHG emissions with BGM, the
proposed project was assumed to have similar non‐mobile source emissions characteristics to a
warehouse, as a parking garage is not included as a land use category in BGM. Mobile emissions
were based on traffic data provided by the traffic study for the proposed project. It should be
noted that parking structures do not generate vehicle trips; rather vehicle trips are generated by
the land uses that the parking structure serves. The proposed project would serve vehicle trips
associated with the Medical Center at Mission Bay Phase I buildings, which have commenced
construction. Nonetheless, for a conservative GHG analysis of the proposed garage, a portion of
the vehicle trips that would be generated by the Medical Center uses will be attributed to the
garage, even though such trips would be generated by already approved Medical Center uses.
The Medical Center at Mission Bay 2008 FEIR projected 4,465 vehicle trips per day associated
with Phase I of the MCMB project. Of these, about 2,616 vehicles per day (58.6%) associated with
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 45 of 74
the Medical Center at Mission Bay buildings could be attributed to the proposed garage.27 This
portion of the project is what is analyzed for the greenhouse gas emissions of the proposed
garage.
Non‐Mobile Source Emissions
Non‐mobile sources include area sources (landscaping, hearths and fireplaces), natural gas and
electricity consumption, water use and wastewater generation, and solid waste disposal.
Emissions from these sources were also calculated using the BGM. Neither the BGM nor the
URBEMIS2007 model includes a parking garage land‐use type and so the warehouse land‐use
type is typically used as a surrogate. Electricity and natural gas consumption, water and
wastewater generation, and solid waste estimates were based on a warehouse land‐use type. It
should be noted that emissions estimated from electricity and natural gas consumption, water
and wastewater generation, and solid waste estimates are highly conservative as a warehouse
would be expected to use significantly more electricity, natural gas, and water, and generate
more waste than a parking garage. The solid waste emissions take into account UCSF waste
diversion rate of 60 percent in 2010. The project would not be a major stationary source.28
Total Operational Emissions
Table 4.1‐5, Estimated Operational GHG Emissions, shows a summary of total estimated GHG
emissions from operation of the proposed project and compares these to the BAAQMD
significance thresholds.
These emissions present a worst case scenario. Transportation emissions will decline in the
future as new motor vehicles with lower tailpipe emissions required by existing State (Pavley)
and Federal regulations are adopted into the vehicle fleet.
The BAAQMD CEQA guideline prescribe a definition for calculating Service Population (SP =
residents + employees). The proportionate SP for the proposed project would be 786.
As shown in Table 4.1‐3, the proposed project’s operational emissions would exceed the project
level threshold of 1,100 MTCO2e for land use development projects. The project’s impact would
therefore be significant.
27 The total project parking, surface lot + garage, is 1,068 spaces. The proposed garage is 626 spaces, or
58.6% of the total spaces.
28 Parking garages are typically open to the air, and do not have large heating or air conditioning systems,
e.g. ‘permitted or major stationary sources’. The proposed project does not have a large heating or air
conditioning system.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 46 of 74
Table 4.1‐3 Estimated Operational GHG Emissions
Source Emissions
(MTCO2e)
Transportation 3,167.59
Electricity 451.16
Natural Gas 36.81
Water & Wastewater 6.05
Solid Waste 133.66
Total Operational GHG Emissions 3,795.27 MTCO2e /year
or
4.8 MTCO2e/SP/year
BAAQMD Threshold 1,100 MTCO2e /year
or
Compliance with a qualified
GHG Reduction Strategy
or
4.6 MTCO2e/SP/year
Exceeds Threshold Yes
Phase I Garage Mitigation: The Regents have committed the system to reduce its GHG
emissions from all of its operations to the 1990 level by 2020. In furtherance of the goal to meet
these goals, the University is currently implementing the 2010‐12 Statewide Energy Partnership
Program (through the UC Strategic Energy Plan), an ambitious three year program to help meet
its goal. In March 2009, The Regents approved $247 million of funding for the program.29 In
September 2010, The Regents approved an augmentation to the 2010‐12 Statewide Energy
Partnership Program, authorizing $15.7 million for additional projects at two campuses.30 This 3
year program, in its second year of implementation, is expected to reduce energy consumption
by 11%, natural gas consumption by 8%, and greenhouse gas emissions by 9% system‐wide.
As identified in the UCSF Climate Action Plan, UCSF is undertaking many of these energy
efficiency projects to retrofit existing facilities in order to assist the campus to meet its
greenhouse gas goals. These energy efficiency projects at UCSF provide more than 2,700
29 With external financing providing $178 million and utility incentive payments and other individual
Campus funds providing the balance.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 47 of 74
MtCO2e ongoing new reductions per year. Detail on campus specific reduction projects are
described in the UC system wide Strategic Energy Plan.31
As discussed above, The Regents has approved funding for the 2010 Statewide Energy
Partnership Program / UC Strategic Energy Plan. UCSF would mitigate at least 2,700 MtCO2e
ongoing reductions per year, e.g. the additional significant GHG emissions associated with the
proposed garage project, with the appropriate number of energy efficiency projects identified on
the list in the Phase I Garage Supplemental EIR Appendix C. Projects identified in Appendix C
are those projects that are included in the funded, UC Strategic Energy Plan and that are planned
to be implemented by 2012, around the time garage operations would begin.
Significance after Mitigation: Less than Significant
Construction Impacts
Construction of the proposed project would result in one‐time emissions of greenhouse gases.
The primary greenhouse gases during construction are CO2, CH4, and N2O. These emissions are
the result of fuel combustion by construction equipment and motor vehicles. The other GHGs
defined by state law (hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride) are
typically associated with specific industrial sources and processes and would not be emitted
during construction of the proposed project. The URBEMIS2007 Environmental Management
Software was used to estimate the construction‐related CO2 emissions. Construction of the
proposed project is anticipated to commence in Summer 2011 and continue for approximately 12
months. Construction activities would include grading/excavation, trenching, building
construction, and architectural coating. UCSF provided a preliminary schedule for construction
and grading amounts. The default construction equipment and vehicle mixes generated by
URBEMIS2007 were assumed for grading and building construction. The number of vendor trips
(e.g., transport of building materials) and worker trips were based on default values in the
URBEMIS2007 model. URBEMIS2007 only calculates CO2 emissions and does not provide
estimates of other GHGs associated with combustion (i.e., CH4 and N2O). Therefore, in order to
account for emissions of these compounds, the following adjustments were made to the
URBEMIS2007 emission calculations to convert CO2 emissions to a CO2e basis:
Construction Off‐Road and On‐Road Equipment. The CO2 emissions associated with
off‐road and on‐road equipment were multiplied by a factor based on the assumption
that CO2 represents approximately 99.1 and 99.9 percent, respectively, of the CO2e
emissions. These assumptions were derived from the California Climate Action Registry
(CCAR 2009) and the California Energy Commission (CEC 2002).
Motor Vehicles (Workers). The CO2 emissions associated with construction‐related
worker trips were multiplied by a factor based on the assumption that CO2 represents 95
30 Including $2.4 million additional for the UCSF campus.
31 http://www.universityofcalifornia.edu/sustainability/documents/ucsep_sw.pdf page 14/21
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 48 of 74
percent of the CO2e emissions associated with passenger vehicles, which account for
most of the project‐related trips (U.S. EPA 2005). The 95 percent factor accounts for CH4,
N2O and fugitive GHG emissions associated with mobile source air conditioning
equipment.
The BAAQMD does not have a quantitative threshold of significance for construction‐related
GHG emissions. However, the CEQA Air Quality Guidelines requires the Lead Agency to quantify
and disclose GHG emissions that would occur during construction. Table 4.1‐4, Estimated
Construction GHG Emissions shows a summary of total estimated GHG emissions from the
construction of the proposed project. Given the low numbers, the fact that they are much lower
than the threshold for operational emissions, and the fact that these would be one‐time
emissions, the effect on global climate from the proposed project’s construction would not be
substantial.
Table 4.1‐4 Estimated Construction GHG Emissions
Construction Year Emissions
(MTCO2e)
2011 250.25
2012 250.25
Total 500.5
BAAQMD Threshold None
Impact GHG‐2: The proposed project could conflict with an applicable plan, policy or
regulation adopted for the purpose of reducing the emissions of greenhouse gases. (Less than
Significant)
The primary GHG emissions regulation in California is AB 32, which is discussed above. The
BAAQMD GHG significance threshold was specifically designed to ensure compliance with AB
32 emissions reductions requirements in the Bay Area. This was accomplished by the BAAQMD
by inventorying existing GHG emissions, estimating projected GHG emissions based on
projected growth in the Bay Area, determining the reductions needed to comply with AB 32
target for the Bay Area, determining the GHG emissions allowable from new sources associated
with the growth, and arriving at the 1,100 MTCO2e threshold for a land development project as
an emission level that would not set back the area from the attainment of AB 32 goals. The
project would not set back AB 32 efforts for the Bay Area air basin.
The BAAQMD 2010 Clean Air Plan contains energy, transportation, and mobile source control
measures that would reduce operational GHG emissions and that would be potentially
applicable to the project. The following measures are taken from the 2010 CAP (BAAQMD
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 49 of 74
2010b).
MSM A‐2: Zero Emission Vehicles and Plug‐In Hybrids. Expand the use of Zero
Emission (ZEV) and Plug‐in Hybrid (PHEV) passenger vehicles and light‐duty trucks
within the Bay Area, working in partnership with the Bay Area Electric Vehicle Corridor
coalition.
TCM E‐2: Parking Pricing and Management Strategies. Promote policies to implement
market‐rate pricing of parking facilities, reduce parking requirements for new
development projects, parking “cash‐out,” unbundling of parking in residential and
commercial leases, shared parking at mixed‐use facilities, etc.
TCM E‐3: Implement Transportation Pricing Reform. Develop a regional transportation
pricing strategy that includes policy evaluation and implementation. Pricing policies to
be evaluated include gasoline taxes, bridge tolls, congestion pricing, parking pricing,
HOT lanes, VMT or carbon fees, pay‐as‐you‐drive insurance, etc.
The project includes project design features that are generally consistent with the above
measures. Furthermore, UCSF has incorporated into the proposed project substantial
sustainability features, including several GHG mitigation measures included in the BAAQMD
CEQA guidelines. These features include secure bicycle parking, parking fees, and electric
vehicle charging stations. In addition, garage attendants would be available to provide
information on alternative transportation and sell transit passes. Design features to minimize the
use of energy and water would also be employed. These features would reduce GHG emissions
from the levels estimated, which assumed no such features would be included, and ensure
compliance with the BAAQMD GHG control plans. In terms of pricing policies to discourage
single‐occupant vehicle commuters, UCSF plans to continue its annual parking fee increase on
employee parking permits – an annual increase of 7 percent to 8 percent or more for the
foreseeable future as a component of the campus’ overall sustainability efforts and in support of
the City’s transit first policy.
With implementation of the reduction projects identified in Impact GHG‐1, emissions would be
mitigated to less than 1,100 MMTCO2e /year. The proposed project would not conflict with an
applicable plan, policy or regulation adopted for the purpose of reducing the emissions of
greenhouse gases.
The Regents has committed the UC system to meet the State of California’s AB32 goal to reduce
GHG emissions to 1990 levels 2020 through the policies identified in the University of California
Policy on Sustainable Practices.32 The policy spells out four implementation procedures the
campuses will complete to ensure that the 2020 emission reduction goals are met.
Each UC campus will pursue individual membership with either the California Climate Action
Registry (CCAR) or The Climate Registry (TCR). The Senior Vice President, Business and
32 http://www.universityofcalifornia.edu/sustainability/documents/policy_sustain_prac.pdf
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 50 of 74
Finance, in coordination with campus administration, faculty, students and other stakeholders,
will form a Climate Change Working Group that will develop a protocol to allow for growth
adjustment and normalization of data and accurate reporting procedures. The Climate Change
Working Group will monitor progress toward reaching the stated goals for GHG reduction,
and will evaluate suggestions for programs to reach these goals.
By September 15, 2008, each UC campus will complete a greenhouse gas emissions inventory. To
comply with CCAR (or TCR) and ACUPCC requirements, inventories should contain emissions
from the six Kyoto greenhouse gasses, including: direct and indirect emissions outlined in the
ACUPCC implementation guide and CCAR or TCR general reporting protocol; air travel paid
for by or through the institution; and commuting to and from campus on a day to day basis by
students, faculty, and staff. As ACUPCC member institutions, all UC campuses will report their
updated emissions inventories through the ACUPCC on‐line reporting tool at least once every
other year.
By December 2008, the University will develop an action plan for becoming climate neutral
which will include: a feasibility study for meeting the 2014 and 2020 goals stated in the Policy
Guidelines, a target date for achieving climate neutrality as soon as possible while maintaining
the University’s overall mission, and a needs assessment of the resources required to
successfully achieve these goals. Climate neutrality means that the University will have a net
zero impact on the Earth’s climate, and will be achieved by minimizing GHG emissions as
much as possible and using carbon offsets or other measures to mitigate the remaining GHG
emissions.
By September 15, 2009, each UC campus will implement two of the seven tangible actions to
reduce greenhouse gas emissions that are outlined in the ACUPCC.
UCSF has completed all four implementation procedures identified above and is in compliance
with the University of California’s Policy on Sustainable Practices.
The proposed project would also be consistent with the UCSF Climate Action Plan (UCSF 2009).
The Climate Action Plan contains the following transportation‐related measures would reduce
transportation‐related GHG emissions:
Transportation Demand Management (TDM) Program – UCSF’s TDM conforms with San
Francisco’s Transit First Policy to encourage the use of alternative transportation to single‐
occupancy vehicles. UCSF has excellent transit ridership rates according to latest transportation
survey. About 25.6% of respondents (faculty, staff, and students) reported taking public transit
(e.g., Muni or other bus system) as their main transportation choice in the latest mobility
choices survey.
Bicycling Accommodations ‐Bicycle racks have been expanded from 400 spaces in 2003
to 680 in 2008. There are now 53 shuttle mounted bike racks. Expenditures on new bike
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 51 of 74
racks were $13,445 in 2008. UCSF bicyclists are eligible for a reduced price membership
in the San Francisco Bicycle Coalition.
Fuel Efficient Vehicles – The Campus supplies 2 electric vehicle charging stations. Fifteen
percent (42 of 273) of campus fleet vehicles are powered by alternative fuel or a hybrid
electric and gas. The Campus offers 103 motorcycle parking stalls.
Transit Pass sales –To further encourage transit use UCSF offers the Campus community
5 convenient locations to purchase city and regional transit passes. MUNI Fast Pass and
Bart Commuter Ticket Monthly sales are 600 passes in 2008.
Vanpools – The number of vanpools increased from 30 in 2003 to 46 in 2008 and the
number of car sharing from three to 17 during the same period. These efforts, led by
UCSF Transportation Services, earned UCSF a place on the inaugural 2006 national list of
Best Workplaces for Commuters from colleges and universities, awarded by the US
Environmental Protection Agency (EPA). Vanpools receive preferential parking spaces at
UCSF.
The UCSF Climate Action Plan contains the following Strategic Energy Plan improvements that
are pertinent to the proposed project. These measures will be investigated for potential
implementation by the proposed project and would reduce energy demand and associated GHG
emissions:
Lighting Projects UCSF will continue to convert existing T12 and 32 watt T8 fluorescent
light fixtures to 28 watt T8 lamps. Other possibilities include: broader use of occupancy
sensor controls, daylight harvesting, and new stairwell fixtures. The replacement of
lighting in parking structures and interior HID fixtures and with fluorescent will also be
evaluated. New technologies such as LED lighting, bi‐level fixtures and induction lamps
are anticipated to become readily available in the near future and these technologies will
be incorporated into energy efficiency retrofit projects where appropriate.
As noted above, the proposed project includes secure bicycle parking, parking fees, and electric
vehicle charging stations. In addition, garage attendants would be available to provide
information on alternative transportation and sell transit passes. The project could also provide
preferential parking spaces for carpools and vanpools, depending on need, consistent with UCSF
guidelines. These measures would reduce transportation‐related GHG emissions consistent with
the Climate Action Plan measures. The project would also be designed to minimize the energy
demand by using energy‐efficient lighting (fluorescent, LED lighting, or similar depending on
cost effectiveness). Based on the inclusion of these project design features, the project would be
consistent with applicable plans that have been adopted to reduce GHG emissions. The impact
would be less than significant.
Mitigation: No additional mitigation is required.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 52 of 74
4.1.5 References
Bay Area Air Quality Management District. 2010a. “CEQA Air Quality Guidelines.”
http://www.baaqmd.gov/Divisions/Planning‐and‐Research/CEQA‐
GUIDELINES/UpdatedCEQA‐Guidelines.aspx.
Bay Area Air Quality Management District. 2010b. “2010 Clean Air Plan.”
http://www.baaqmd.gov/ Divisions/Planning‐and‐Research/Plans/Clean‐Air‐Plans.aspx.
Bay Area Air Quality Management District. Source Inventory of Bay Area Greenhouse Gas
Emissions.
http://www.baaqmd.gov/~/media/Files/Planning%20and%20Research/Emission%20Inve
ntory/regionalinventory2007_2_10.ashx
California Air Pollution Control Officers Association. 2008. CEQA & Climate Change: Evaluating
and Addressing Greenhouse Gas Emissions from Projects Subject to the California
Environmental Quality Act.
California Air Resources Board. 2007. Initial Statement of Reasons for Rulemaking, Proposed
Regulation for Mandatory Reporting of Greenhouse Gas Emissions Pursuant to the California
Global Warming Solutions Act of 2006 (Assembly Bill 32).
California Air Resources Board. 2008. Local Government Operations Protocol for the Quantification
and Reporting of Greenhouse Gas Emissions Inventories Version 1.0.
California Air Resources Board. 2009. “Stationary Equipment Refrigerant Management
Program.” http://www.arb.ca.gov/cc/reftrack/reftrack.htm. This regulation is an early
action measure under AB 32.
California Air Resources Board. 2010a. “California Greenhouse Gas 2000‐2008 Inventory by
Scoping Plan Category – Summary.” http://www.arb.ca.gov/cc/inventory/data/data.htm.
California Air Resources Board. 2010b. Staff Report: Proposed Regional Greenhouse Gas Emission
Reduction Targets For Automobiles And Light Trucks Pursuant To Senate Bill 375.
California Building Standards Commission. 2009. 2008 California Green Building Standards Code.
California Building Standards Commission. 2010. “CALGreen.”
http://www.bsc.ca.gov/CALGreen/ default.htm.
California Climate Action Registry. 2009. General Reporting Protocol: Reporting Entity‐Wide
Greenhouse as Emissions Version 3.1.
California Climate Action Team. 2007. Updated Macroeconomic Analysis of Climate Strategies
Presented in the March 2006 Climate Action Team Report.
California Department of Finance. 2010a. “E‐5 Population and Housing Estimates for Cities,
Counties, and the State, 2001‐2008, with 2000 Benchmark.”
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 53 of 74
http://www.dof.ca.gov/research/demographic/ reports/estimates/e‐5/2009.
California Department of Finance. 2010b. “Financial & Economic Data: Gross Domestic Product,
California.” http://www.dof.ca.gov/HTML/FS_DATA/LatestEconData/FS_Misc.htm.
California Energy Commission. 2002. Diesel Use in California. Remarks by Commissioner James D.
Boyd.
California Energy Commission. 2006a. Inventory of California Greenhouse Gas Emissions and Sinks
1990 to 2004, Figure 2.
California Energy Commission. 2006b. Refining Estimates of Water‐Related Energy Use in California,
PIER Final Project Report (CEC‐500‐2006‐118). Prepared by Navigant Consulting, Inc.
California Energy Commission. 2007. “Revisions to the 1990‐2004 Greenhouse Gas Emissions
Inventory Report, Published in December 2006.”
http://www.energy.ca.gov/2006publications/CEC‐6002006‐013/2007‐01‐
23_GHG_INVENTORY_REVISIONS.PDF.
California Environmental Protection Agency, Climate Action Team. 2006. Climate Action Team
Report to Governor Schwarzenegger and the Legislature.
California Environmental Quality Act Guidelines. California Code of Regulations, Title 14,
Division 6, Chapter 3, Section 15064(b).
California Natural Resources Agency, Climate Action Team. 2009. 2009 California Climate
Adaptation Strategy: A Report to the Governor of the State of California in Response to Executive
Order S‐13‐2008. California Public Resources. nd. Code Section 21082.
California Office of the Attorney General. 2008. The California Environmental Quality Act:
Addressing Global Warming Impacts at the Local Agency Level.
California Office of the Attorney General. 2010. “Addressing Climate Change at the Project
Level,” http://ag.ca.gov/globalwarming/pdf/GW_mitigation_measures.pdf
City and County of San Francisco, Office of the Mayor. 2010. “Press Release: Mayor Newsom
Announces San Francisco’s Waste Diversion Rate At 77 Percent, Shattering City Goal
And National Recycling Records.” http://sfmayor.org/press‐room/press‐releases/press‐
release‐mayor‐newsom‐announcessan‐francisco%E2%80%99s‐waste‐diversion‐rate‐at‐
77‐percent‐shattering‐city‐goal‐and‐nationalrecycling‐records/.
Energy Information Administration. n.d. “Other Gases: Hydrofluorocarbons, Perfluorocarbons,
and Sulfut Hexafluoride.” http://www.eia.doe.gov/oiaf/1605/gg00rpt/other_gases.html.
Intergovernmental Panel on Climate Change. 1996. Climate Change 1995: The Science of Climate
Change – Contribution of Working Group I to the Second Assessment Report of the
Intergovernmental Panel on Climate Change.
Intergovernmental Panel on Climate Change. 2007. “Climate Change 2007: The Physical Science
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 54 of 74
Basis, Summary for Policymakers.”
http://ipccwg1.ucar.edu/wg1/docs/WG1AR4_SPM_Plenary Approved.pdf.
Letter to Governor Arnold Schwarzenegger from U.S. EPA Administrator Stephen L. Johnson,
December 19, 2007.
Natural Resources Agency. 2009. Final Statement of Reasons for Regulatory Action: Amendments to
the State CEQA Guidelines Addressing Analysis and Mitigation of Greenhouse Gas Emissions
Pursuant to SB97.
Office of Planning and Research. 2008a. CEQA and Climate Change: Addressing Climate Change
Through California Environmental Quality Act (CEQA) Review.
Office of Planning and Research. 2008b. Technical Advisory – CEQA and Climate Change: Addressing
Climate Change through California Environmental Quality Act (CEQA) Review.
Office of Planning and Research. 2009. Preliminary Draft CEQA Guideline Amendments for
Greenhouse Gas Emissions.
Rimpo and Associates. 2008. “URBEMIS2007 for Windows.” http://www.urbemis.com.
United States Census Bureau. 2010. “Data Finders.” http://www.census.gov/.
United States Environmental Protection Agency. 1998a. Compilation of Air Pollutant Emission
Factors, AP
42.
United States Environmental Protection Agency, Office of Solid Waste and Emergency Response.
1998b.
Greenhouse Gas Emission Factors for Management of Selected Materials in Municipal Solid
Waste (EPA530‐R‐98‐013).
United States Environmental Protection Agency, Office of Transportation and Air Quality. 2005.
Greenhouse Gas Emissions from a Typical Passenger Vehicle (EPA420‐F‐05‐004).
United States Environmental Protection Agency. 2008a. “Advance Notice of Proposed
Rulemaking:
Regulating Greenhouse Gas Emissions under the Clean Air Act.” http://www.epa.gov/
climatechange/anpr.html.
United States Environmental Protection Agency. 2008b. “Glossary of Climate Change Terms.”
http://www.epa.gov/climatechange/glossary.html.
United States Environmental Protection Agency. 2010. “Inventory of US Greenhouse Gas
Emissions and Sinks 1990‐2008.”
http://www.epa.gov/climatechange/emissions/usinventoryreport.html.
United States Environmental Protection Agency. n.d.a. “High GWP Gases and Climate Change.”
http://www.epa.gov/highgwp/scientific.html#sf6.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 55 of 74
United States Environmental Protection Agency. n.d.b. “Methane: Sources and Emissions.”
http://www.epa.gov/methane/sources.html.
University of California, San Francisco. 2008. Medical Center at Mission Bay FEIR.
http://campusplanning.ucsf.edu/physical/RFEIRHospital.php
University of California, San Francisco. 2009. Climate Action Plan.
http://www.universityofcalifornia.edu/ sustainability/documents/ucsf_cap_09.pdf
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 56 of 74
4.2 TRANSPORTATION
4.2.1 INTRODUCTION
This section evaluates potential changes to the transportation analysis of the MCMB EIR as a
result of the minor modifications to the proposed Phase I garage project. The MCMB EIR
concluded that the construction and operation of the Medical Center at Mission Bay, including
the proposed Phase I garage, would not cause a substantial adverse impact to transit, pedestrian,
bicycle, or parking conditions, nor result in inadequate emergency access. The modifications to
the proposed project would not change the effects anticipated in these topic areas. Therefore, this
analysis focuses on any potential changes to operational traffic impacts.
4.2.2 SETTING
The setting information is substantially the same as discussed in the UCSF Medical Center at
Mission Bay EIR (pp. 4.5‐1 through 4.5‐8), which is hereby incorporated by reference. However,
the current conditions of the project site have changed in that all existing structures and paving
on the site have been demolished and site work and construction of the hospital complex has
commenced.
4.2.3 SIGNIFICANCE CRITERIA AND ANALYSIS METHODOLOGY
The significance criteria and analysis methodology of the MCMB EIR remain unchanged with
regard to transportation and traffic. Traffic impacts were analyzed using the concept of Level of
Service (LOS), which describes the level of the performance of an intersection based on the
average delay per vehicle. Intersection LOS ranges from LOS A, which indicates free‐flow
conditions with little or no delays, to LOS F, which indicates congested or overloaded conditions
with extremely long delays. LOS D, which indicates increasingly unacceptable, yet tolerable,
delays, is considered to be the minimum acceptable level of service.
As discussed in the Project Description, although the number of parking spaces within the
proposed garage has been increased from 600 spaces to 626 spaces with the modified project, the
number of parking spaces within the surface parking lot, which has been approved, has
decreased. The total number of parking spaces in Phase I (626 spaces in the parking structure
and 442 surface parking spaces) has decreased by approximately seven spaces and would total
approximately 1,068‐parking spaces, down from the previously analyzed 1,075 spaces. As
discussed in the Project Description, the Phase I garage is now proposed to be located to the
north of its originally proposed site, between North Connector Road and Parking Structure Road.
Roadways internal to the site and connections to surrounding public streets, including Owens
Street, would remain unchanged.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 57 of 74
4.2.4 IMPACTS AND MITIGATION MEASURES
Medical Center at Mission Bay EIR Analysis A Transportation Study was prepared for the MCMB EIR.33 The Transportation Study evaluated
both the Phase I and future buildout of the Phase II development. In addition, the traffic study
evaluated two potential alternatives for the operation of 4th Street through the Medical Center
site. Both alternatives would convert the proposed 4th Street right‐of‐way to University of
California property.
Based on the analysis contained with the Transportation Study, traffic impacts resulting from
Phase I of the Medical Center at Mission Bay would be less than significant, as all study
intersections would continue to operate at level‐of‐service D or better.
Effects of Modified Project
The impacts analysis below updates the impacts analysis of the MCMB EIR.
Construction Impacts
Impact MCMB.6‐1 of the MCMB EIR (analysis updated with this SEIR): The MCMB EIR
concluded that construction of the MCMB Phase I project, including the Phase I garage,
would not result in significant construction‐period impacts. (Less than Significant)
The MCMB EIR concluded that MCMB Phase I construction activities would temporarily
increase traffic on area roadways (due to construction employee auto trips and construction
truck traffic), as well as demand for parking in the area. In addition, the staging of vehicles and
construction materials would require temporary closure of on‐street parking near the
construction site. The MCMB EIR concluded that the LRDP Amendment #2 – Hospital
Replacement EIR mitigation measure 4.11‐1, which includes limiting the use of local roads as
haul routes, and/or limiting truck trips to off‐peak hours, and/or developing a parking plan for
construction employees, would ensure transportation‐related construction impacts would be
reduced to less than significant levels. In furtherance of this mitigation measure, the proposed
Phase I garage, once completed, on a temporary basis would provide some construction
employee parking until construction of the hospital and surface parking lot is complete.
Mitigation: None required.
33 Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation Study, March 2008.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 58 of 74
Operational Impacts
Impact MCMB.6‐2 of the MCMB EIR (analysis updated with this SEIR): The MCMB EIR
concluded that operation of the MCMB Phase I project, including the Phase I garage, would
not result in a significant impact on the adjacent roadway network. (Less than Significant)
As discussed in the Project Description, while the number of parking spaces in the parking
structure (from 600 to 626) would increase as a result of the changes to the proposed project,, the
total number of parking spaces would decrease by about 7 spaces as a result of the proposed
decrease in surface parking. Although the location of the Phase I garage is now proposed in the
location of the Phase II garage, to the north of the previously proposed Phase I garage site, effects
on traffic would continue to be less than significant in Phase I. Overall site circulation and access
to the parking garage would remain substantially the same. Multiple access points to/from the
parking facility (including the adjoining surface lot) would continue to be from North Connector
Road, South Connector Road, West Connector Road, and Parking Structure Road (formerly
Center Garage Access), all campus streets on the Medical Center site. Effects on traffic at
surrounding study intersections would remain largely unchanged. As a result of the relocation
of the Phase I garage to north, Parking Structure Road/ Owens Street could experience
incrementally more traffic in Phase I than previously anticipated, but not to the degree that the
level of service would deteriorate to unacceptable levels. Multiple roadway access would
continue to be available to the garage, as previously analyzed, and assumptions regarding the
distribution of traffic at nearby intersections would not substantially change.
Mitigation: None required.
Impact MCMB.6‐3 of the MCMB EIR (analysis updated with this SEIR): The MCMB EIR
concluded that operation of the UCSF Medical Center at Mission Bay project would increase
traffic at intersections on the adjacent roadway network in the Future Phase (Phase II).
(Significant)
The MCMB EIR traffic analysis of the full project (Phase I and Phase II) would not change
substantially with the modified project. With the modified project, the construction of the Phase
II garage would occur to the south of the Phase I garage, at the originally proposed location of
the Phase I garage. The significant traffic impact at 16th/Owens in Phase II, which would be
mitigated to a less‐than‐significant level with the mitigation measure described below, would not
change with the modified project. The potential impact at Owens/Center Garage Access would
remain speculative pending project‐level analysis of the traffic and circulation analyses for Phase
II.
Mitigation: The mitigation measures identified in the MCMB EIR to address significant traffic
impacts in Phase II would remain unchanged, as follows:
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 59 of 74
16th/Owens: Mitigation Measure 4.11‐2a from the LRDP Amendment #2 EIR identifies
modifications to the Owen Street lane configurations (i.e. restriping) to mitigate the
impact at this intersection: one southbound shared through‐left turn lane, one
southbound through lane, and one southbound exclusive right turn lane, would remain
the same.
Significance after Mitigation: Less than significant. Implementation of the re‐striping at
this location would improve the operating conditions at this intersection to an acceptable
LOS D. The City of San Francisco has found the mitigation measure to be feasible, and
has committed to working with UCSF to ensure its implementation.34
Owens Street at Center Garage Access: Mitigation Measure MCMB.6‐3 from the
Medical Center at Mission Bay EIR would require that UCSF conduct a project‐level
CEQA review at the time the Phase II development is considered for approval. In
addition, in order to determine the need for LOS improvements on Owens Street,
between 16th and Mariposa Streets at Center Garage Access (now Parking Structure
Road), such as a traffic signal, UCSF would coordinate with the City of San Francisco in
the periodic update of the Mission Bay traffic triggers survey and would monitor on‐site
parking access and circulation in order to determine the need for LOS improvements.
Significance after Mitigation: The need for LOS improvements on Owens Street at the
Center Garage Access in Phase II remains speculative pending a project‐level design of
parking requirements and project‐level traffic and circulation evaluation.
34 Comment letter dated July 3, 2008 from the San Francisco Municipal Transportation Agency, on the
UCSF Medical Center at Mission Bay Draft EIR.
Page 60 of 74
CHAPTER 5 CEQA STATUTORY SECTIONS
5.1 SIGNIFICANT AND UNAVOIDABLE ENVIRONMENTAL
IMPACTS
Information regarding significant and unavoidable environmental impacts resulting from the
project is the same as discussed in the MCMB EIR (p. 5‐1). That information is hereby
incorporated by reference. The proposed garage would not affect the conclusions of the MCMB
EIR with regarding to significant unavoidable impacts.
5.2 CUMULATIVE IMPACTS
Information regarding cumulative impacts is the same as discussed in the UCSF Medical Center
at Mission Bay EIR (p. 5‐2), which is hereby incorporated by reference. The modified project
does not affect this analysis.
5.3 GROWTH‐INDUCING IMPACTS
Information regarding growth‐inducing impacts is the same as discussed in the UCSF Medical
Center at Mission Bay EIR (pp. 5‐3 to 5‐4), which is hereby incorporated by reference. The
modified project does not affect the analysis.
5.4 EFFECTS FOUND NOT TO BE SIGNIFICANT
Much of the information regarding effects found not to be significant is the same as discussed in
the UCSF Medical Center at Mission Bay EIR (pp. 5‐4 to 5‐5), which is hereby incorporated by
reference. The exception is that greenhouse gas emissions were determined in the MCMB EIR to
be less than significant. This SEIR found that greenhouse gas emissions of the modified project
would result in a significant impact, but the impact would be mitigated to a less than significant
level with the implementation of specified mitigation measures.
5.5 SIGNIFICANT IRREVERSIBLE ENVIRONMENTAL CHANGES
THAT WOULD BE CAUSED BY THE PROPOSED PROJECT
Information regarding significant irreversible environmental changes caused by the Medical
Center project is the same as discussed in the UCSF Medical Center at Mission Bay EIR (pp. 5‐4
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 61 of 74
to 5‐5), which is hereby incorporated by reference. The modified project does not affect the
analysis.
Page 62 of 74
CHAPTER 6 ALTERNATIVES
6.1 ALTERNATIVES TO THE PROJECT
The California Environmental Quality Act (CEQA) requires an evaluation of the comparative
effects of a range of reasonable alternatives that would attain most of the basic objectives of the
proposed project and avoid or substantially lessen one or more of the significant adverse effects
of the proposed project, including alternatives that are more costly or could otherwise impede to
some degree the attainment of the project’s objectives.
The LRDP Amendment #2 – Hospital Replacement EIR, evaluated at an equal level of detail a
number of hospital replacement scenarios at Mission Bay and Parnassus Heights that, for
purposes of CEQA, were alternatives to one another. These project scenarios include a 250‐bed
and 400‐bed scenario at the Mission Bay campus site (Mission Bay North and South sites); a 650‐
bed scenario at the Mission Bay campus site (Mission Bay South site); and a 250‐bed and 400‐bed
scenario at the Parnassus Heights campus site (Parnassus East and West sites). In addition, the
LRDP Amendment #2 EIR evaluated two No Project alternatives, and an Off‐Site Alternative at
the Mount Zion South Block. The Medical Center at Mission Bay EIR added an Off‐Site Helipad
alternative, a No Helipad alternative, and a 4th Street Closed to Through Traffic (No 4th Street)
alternative. The modified project would not affect the conclusions of the alternatives analyses,
including the 4th Street Closed to Through Traffic (No 4th Street) Alternative. However, in light of
the new greenhouse gas emissions significance standards and the significant impact of the
modified project, this SEIR considers two additional alternatives:
No Project Alternative
Reduced Project Alternative
6.1.2 NO PROJECT ALTERNATIVE
CEQA requires that a “No Project” alternative be considered. Under this alternative, the UCSF
Medical Center at Mission Bay would be developed as proposed except that the garage would
not be constructed. The 442‐parking space surface lots, which have been approved, would be
constructed as planned.
This alternative would not meet any of the project objectives.
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 63 of 74
Greenhouse Gas Emissions
With the proposed project, impacts on greenhouse gas emissions would be significant, but would
be reduced to less than significant levels with mitigation. While the No Project Alternative would
mean no parking structure would be provided, it is still anticipated that a substantial number of
patients, visitors, and employees would need to drive to the site. These persons would search for
on‐street parking or off‐street parking in nearby parking facilities, if available. Because this
alternative eliminates the proposed garage but not necessarily those who would continue to
drive, some amount of greenhouse gas emissions would still be expected under this alternative.
It is likely that the amount of greenhouse gas emissions would be significant, as with the
modified project, but those emissions could be reduced to less‐than‐significant levels with the
implementation of the energy efficiency projects identified as mitigation for the modified project.
Transportation
The proposed project would result in less than significant impacts on traffic, as would the No
Project Alternative. Without a garage on the Medical Center at Mission Bay site, more drivers
may search for parking in the vicinity, thus more traffic may occur in the surrounding
neighborhood than with the proposed project. However, traffic impacts under the No Project
Alternative would be less than significant.
Summary
The No Project alternative would avoid most of the impacts of the proposed project, but would
not meet any of the project objectives. Some amount of greenhouse gas emissions would
continue as some patients, visitors and employees would continue to drive to the site and search
for parking in the vicinity. However, greenhouse gas emissions could be mitigated to less than
significant levels, as with the project.
6.1.3 REDUCED PROJECT ALTERNATIVE
Under the Reduced Project Alternative, the number of parking spaces would be reduced to
approximately one‐half the number of spaces, or about 300 spaces. The number of parking
spaces within the surface parking lots, which have been approved, would remain the same at 442
spaces.
This alternative would meet the project objectives to (1) ensure that development is compatible
with and responsive to building scale and character in the surrounding areas; and (2) provide a
parking structure that incorporates sustainability features to the greatest extent feasible.
This alternative would only satisfy a portion of the expected parking demand by patients,
visitors, and staff, and therefore would only partially meet the project objectives to (1) develop a
patient‐friendly hospital (convenient location, availability of parking, efficient patient/emergency
access, proximity of related patient service, etc.); (2) develop a staff‐friendly hospital (availability
of parking, proximity to amenities, loading/delivery access, etc.); (3) support UCSF’s mission of
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 64 of 74
patient care by enhancing access to UCSF facilities through convenient, affordable parking for
those who often cannot utilize alternative forms of transportation; (4) provide parking for those
essential healthcare providers for whom alternative forms of transportation is infeasible due to
atypical work hours and responsibilities at multiple campus sites; and (5) avoid pressure on
neighborhood on‐street parking.
Greenhouse Gas Emissions
With the proposed project, impacts on greenhouse gas emissions would be significant, but would
be reduced to less than significant levels with mitigation. The Reduced Project Alternative would
likely result in significant greenhouse gas emissions that could be reduced to less than significant
levels with mitigation, similar to the proposed project.
Transportation
The proposed project would result in less than significant impacts on traffic, as would the
Reduced Project Alternative. With fewer parking spaces on the Medical Center at Mission Bay
site, more drivers may search for parking in the vicinity, thus more traffic may occur in the
surrounding neighborhood than with the proposed project. However, traffic impacts under the
Reduced Project Alternative would be less than significant.
Summary
The Reduced Project alternative would avoid most of the impacts of the proposed project, but
would meet only two of the seven project objectives. Some amount of greenhouse gas emissions
would continue as some patients, visitors and employees would continue to drive to the site and
search for parking in the vicinity. However, greenhouse gas emissions could be reduced to less
than significant levels with mitigation, as with the project.
6.1.4 ENVIRONMENTALLY SUPERIOR ALTERNATIVE
An EIR is required to identify the environmentally superior alternative—that is, the alternative
having the fewest significant environmental impacts—from among the alternatives evaluated.
The environmentally superior alternative among those evaluated within this SEIR is the No
Project Alternative. Other than the No Project Alternative, the remaining alternative, the
Reduced Project Alternative, is the environmentally superior alternative.
Page 65 of 74
CHAPTER 7 REPORT PREPARATION
7.1 REPORT AUTHORS
LEAD AGENCY
The University of California
Susan Desmond‐Hellmann, MD, MPH, Chancellor Arthur and Toni Rembe Rock Distinguished Professor University of California, San Francisco
AUTHORS
University of California, San Francisco
John Plotts, Senior Vice Chancellor, Finance and Administration Lori Yamauchi, Assistant Vice Chancellor Kevin Beauchamp, Director, Physical Planning Diane Wong, Senior Planner Tammy Chan, Senior Planner Paul Franke, Assistant Planner
University of California, Office of the President
Charlotte Strem, Director, Physical & Environmental Planning
Mary O’Keefe, Senior Planner
University of California, Office of General Counsel Elisabeth Gunther, University Counsel Legal Counsel Charles Olson, Esq., Sanger & Olson
CONSULTANTS
Transportation José Farrán, P.E., Principal Transportation Engineer, Adavant Consulting
Wind Charles Bennett, Environmental Science Associates
Page 66 of 74
CHAPTER 8 COMMENTS AND RESPONSES
8.1 OVERVIEW
This chapter documents public comments on the Draft Supplemental EIR prepared for the proposed
project, and the responses to comments. The public comment period was from February 25, 2011 to
April 11, 2011. In addition, a public hearing was held on the UCSF Mission Bay campus site on March
28, 2011, at which the public was given the opportunity to provide oral testimony. No public
comments were submitted by the close of the public comment period, and there was no oral testimony
at the public hearing.
8.2 PUBLIC HEARING TRANSCRIPT
A copy of the transcript of the March 28, 2011 public hearing on the Draft EIR follows.
CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417
University of California, San Francisco Mission Bay Campus 600 16th Street
Genentech Hall Auditorium San Francisco, CA
Public Meeting Re:
Draft Supplemental Environmental Impact Report
for the UCSF Medical Center at Mission Bay Phase I Garage
Monday, March 28, 2011
7:00 P.M.
Reported by Tahsha Sanbrailo
CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417
2
APPEARANCES
Present:
Lori Yamauchi Assistant Vice Chancellor, Campus Planning
1
CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417
3
P R O C E E D I N G S 1
MARCH 28, 2011 7:05 P.M. 2
Item 1 Welcome and Meeting Purpose. 3
MS. YAMAUCHI: Good evening. My name is Lori 4
Yamauchi, I am the Assistant Vice Chancellor, Campus 5
Planning, for the University of California, San Francisco. 6
I will be the Hearing Officer for tonight’s public hearing 7
on the Draft Supplemental Environmental Impact Report, or 8
Draft SEIR for the UCSF Medical Center Mission Bay Phase 1 9
Garage. 10
The primary purpose of this hearing is to receive 11
public testimony and evidence regarding the adequacy of the 12
Environmental Review for the proposed project. This is not 13
a hearing on the proposed project, itself. We have held 14
several community meetings regarding the project where we 15
received comments about the garage, the design, and about 16
parking, in general. 17
Tonight’s hearing is being conducted pursuant to 18
the University of California’s procedures for implementation 19
of the California Environmental Quality Act, or CEQA. 20
Public Notice regarding this hearing and the availability of 21
the Draft EIR included advertisements in the San Francisco 22
Examiner, postcard mailing to adjacent property owners, two 23
email notifications to a Listserv of about 500 people and 24
organizations, and posting on the Campus Planning Website, 25
CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417
4
Community Relations Website, and UCSF Events Calendar. 1
This hearing will be transcribed by a Reporter. A 2
complete transcript of this proceeding, as well as all 3
written comments received during the SEIR’s public review 4
period, will be included in and responded to in the Final 5
SEIR. All comments will be presented to the UCSF Chancellor 6
for review before considering the certification of the Final 7
SEIR. 8
If you do not wish to speak tonight, you may 9
submit written comments, which are given equal weight, with 10
oral remarks. Written comment sheets are available on the 11
table if you would like to use them outside in the back. 12
You may also supplement any oral testimony given tonight 13
with additional written material. 14
I would like to note that all comments must be 15
received by the close of the public review period on Monday, 16
April 11th, 2011, at 5:00 p.m. in order to be considered as 17
part of the record. Correspondence should be sent to Diane 18
Wong, Campus Planning, 654 Minnesota Street, San Francisco, 19
California 94143-0286. 20
Regarding the hearing tonight, if you would like 21
to speak and have not already signed up, please fill out a 22
speaker card now and return it to the staff. In order for 23
your testimony to be accurately recorded, and so that we may 24
respond accurately in the Final SEIR, please come forward 25
CALIFORNIA REPORTING LLC 52 Longwood Drive, San Rafael, CA 94901 (415) 457-4417
5
when called and use the microphone. As you begin your 1
remarks, please spell your name for the Reporter and 2
indicate the name of any organization you represent. 3
Because the purpose of this hearing is to receive testimony 4
and evidence for the Chancellor to consider, UCSF staff will 5
not attempt to respond to the testimony this evening, nor 6
engage in a dialogue with the public; however, I will be 7
happy to answer any procedural questions about the hearing. 8
Are there any questions that have not been 9
addressed by my comments? If not, is there anyone here who 10
wishes to speak on the SEIR? If not, then I will close the 11
public hearing and thank everyone for coming. 12
-oOo- 13
[Public Hearing Adjourned.] 14
15
16
17
18
19
20
21
22
23
24
25
Page 73 of 74
CHAPTER 9 MITIGATION MONITORING and REPORTING PROGRAM
9.1 OVERVIEW
The California Environmental Quality Act (CEQA) requires that a Lead Agency establish a
program to monitor and report on mitigation measures adopted as part of the environmental
review process to avoid or reduce the severity and magnitude of potentially significant
environmental impacts associated with project implementation. CEQA (Public Resources Code
Section 21081.6 (a)(1)) requires that a Mitigation Monitoring and Reporting Program (MMRP) be
adopted at the time that the agency determines to carry out a project for which an EIR has been
prepared, to ensure that mitigation measures identified in the EIR are fully implemented.
The MMRP for the Medical Center at Mission Bay ‐‐ Phase 1 Garage project is presented in the
following table, which includes the full text of project‐specific mitigation measures identified in
the Final EIR. The MMRP includes the mitigation measures adopted as part of the UCSF Medical
Center at Mission Bay project that are included as part of the Phase 1 Garage project, as well as
the LRDP Amendment #2 mitigation measures that are applicable to the project. The MMRP
describes implementation and monitoring procedures, responsibilities, and timing for each
mitigation measure identified in the EIR, including:
Significant Impact: Identifies the Impact Number and statement from the Final EIR.
MitigationMeasure: Provides full text of the mitigation measure as provided in the Final EIR.
Implementation: Summarizes the steps to be taken to implement the measure.
Responsible Unit: Designates responsibility for implementation of the mitigation measure.
Report Mechanism: Specifies procedures for documenting and reporting mitigation
implementation.
Consistent with UC policy, UCSF may modify the means by which a mitigation measure will be
implemented, as long as the alternative means ensure compliance during project
implementation. The responsibilities of mitigation implementation, monitoring and reporting
extend to several UCSF departments and offices. The manager or department lead of the
identified unit or department will be directly responsible for ensuring the responsible party
complies with the mitigation. The UCSF Campus Planning Department is responsible for the
overall administration of the program and for assisting relevant departments and project
UCSF Medical Center at Mission Bay Supplemental EIR
Phase 1 Garage
Page 74 of 74
managers in their oversight and reporting responsibilities. The Department is also responsible for
ensuring the relevant parties understand their charge and complete the required procedures
accurately and on schedule.
UCSF Medical Center at Mission Bay – Phase 1 Garage SEIR 1
MITIGATION MONITORING AND REPORTING PROGRAM
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
MITIGATION MEASURES NEWLY IDENTIFIED IN THE SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY PHASE 1 GARAGE
4.1 GREENHOUSE GAS EMISSIONS ‐ OPERATIONS
GHG‐1: Project development
would generate greenhouse gas
emissions, either directly or
indirectly, that could have a
significant impact on the
environment.
The Regents has approved funding
for the 2010 Statewide Energy
Partnership Program / UC Strategic
Energy Plan. UCSF would mitigate
at least 2,700 MtCO2e ongoing
reductions per year, e.g. the
additional significant GHG emissions
associated with the proposed garage
project, with the appropriate number
of energy efficiency projects
identified on the list in Supplemental
EIR Appendix C. Projects identified
in Appendix C are those projects that
are included in the funded, UC
Strategic Energy Plan and that are
planned to be implemented by 2012,
around the time garage operations
would begin.
Complete appropriate number of
energy efficiency projects included in
the 2010 Statewide Energy
Partnership Program / UC Strategic
Energy Plan to mitigate at least 2,700
MtCO2e ongoing reductions per
year.
UCSF Facilities
Management and/or
UCSF Medical Center
UCSF Campus Planning to monitor
implementation of energy efficiency
projects and document completion to
verify mitigation of impact.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 2
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
MITIGATION MEASURES IDENTIFIED IN THE UCSF MEDICAL CENTER AT MISSION BAY EIR THAT ARE APPLICABLE TO THE PHASE 1 GARAGE
PROJECT
4.2 AIR QUALITY
MCMB.2‐1: Demolition and
construction activities
associated with the Medical
Center at Mission Bay project
would generate fugitive dust
and criteria pollutant emissions
that could adversely affect local
air quality.
To further mitigate less‐than‐
significant project‐level impacts,
additional measures related to the
2007 CARB off‐road diesel rule on
equipment exhaust emissions from
construction equipment shall be
required in UCSF construction
contracts to comply with the
following measures:
Prohibit the use of conventional cutback asphalt for paving to
restrict the maximum VOC content
of asphalt emulsion. Diesel
portable generators less than 50
horsepower shall not be allowed at
the construction site, except for
those used by welders.
All diesel‐fueled engines used for on‐ and offsite construction
activities shall be fueled only with
ultralow sulfur diesel, which
contains no more than 15 ppm
sulfur.
All construction diesel engines used for on‐ and offsite activities
that have a rating of 100 hp or
more shall meet, at a minimum,
the Tier 2 California Emission
Standards for Off‐Road
Compression‐Ignition Engines as
Issue instructions in each bid
package of each construction project
for contractors to incorporate the
mitigation. The successful contractor
will prepare a construction air
pollution control strategy to report
on the implementation of the
mitigation measure.
Project Manager,
Medical Center Design
and Construction Team,
or Capital Programs
Facilities Management,
as appropriate.
Provide written verification in report
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provision for construction air
pollution control. Provide a report on
construction air pollution control
strategies and implementation and
report to Monitor upon request; but
no less than quarterly after beginning
each construction phase.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 3
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
specified in California Code of
Regulations, Title 13, section
2423(b)(1) unless it is certified by
the construction contractor that
such engine is not available for a
particular item of equipment. In
the event a Tier 2 engine is not
available for any off‐road engine
larger than 100 hp, that engine
shall be a Tier 1 engine. In the
event a Tier 1 or Tier 2 engine is
not available for any offroad
engine larger than 100 hp, that
engine shall be equipped with a
CARB Level 3‐verified diesel
emission control device (e.g.,
catalyzed diesel particulate filter),
unless the engine manufacturer or
the construction contractor
certifies that the use of such
devices is not practical for specific
engine types. In the event that a
CARB Level 3 verified diesel
emission control device is not
practical for the specific engine
type, then the engine shall be
equipped with a CARB Level 1‐ or
2‐verified control device (e.g.,
diesel oxidation catalyst), unless
the engine manufacturer or the
construction contractor certifies
that such devices are not available
for the engine in question. For
purposes of this condition, the use
of such devices is “not practical”
if, among other reasons:
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 4
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
1. The construction equipment is
intended to be onsite for ten
(10) days or less.
2. The use of the diesel emission
control device is excessively
reducing normal availability of
the construction equipment
due to increased downtime for
maintenance, and/or reduced
power output due to an
excessive increase in
backpressure.
3. The diesel emission control
device is causing or is
reasonably expected to cause
significant engine damage.
In the event that the use of a diesel
emission control device is to be
terminated, the construction
contractor shall be required to
inform the UCSF project manager
within 10 days prior to such
termination.
Construction equipment shall be
properly tuned and maintained in
accordance with manufacturers’
specifications.
Best management construction
practices shall be used to avoid (or
limit) unnecessary emissions (e.g.,
trucks and vehicles in loading and
unloading queues would turn their
engines off when not in use, and to
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 5
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
the extent practical, all diesel
heavy construction equipment
shall not remain running at idle for
more than five minutes)
Use alternative fueled equipment
when feasible (such as ULSD,
CNG, biodiesel, water emulsion
fuel, and electric). The
construction contracts shall require
each contractor and subcontractor
to consider this measure and adopt
it for their work unless they can
demonstrate to UCSF the
inapplicability or infeasibility of
the measure to their specific work,
or can provide mitigation
measures with equivalent or better
effectiveness. This information
shall be reported as part of the
Mitigation Monitoring Reporting
and Compliance Program.
Use on‐site power when feasible to
reduce reliance on portable
generators. The construction
contracts shall require each
contractor and subcontractor to
consider this measure and adopt it
for their work unless they can
demonstrate to UCSF the
inapplicability or infeasibility of
the measure to their specific work,
or can provide mitigation
measures with equivalent or better
effectiveness. This information
shall be reported as part of the
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 6
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
Mitigation Monitoring Reporting
and Compliance Program.
4.5 NOISE
MCMB.5‐1: Demolition and
construction activities
associated with the proposed
project would elevate noise
levels in and around the project
site, and particularly at nearby
sensitive receptors.
UCSF shall require construction
contractors to minimize unavoidable
construction noise impacts by use of
proper equipment and work
scheduling:
Limit construction hours to the
following schedule. [Monday
through Friday, 7 a.m. to 5 p.m. for
“Not Noisy” work; and Monday
through Friday 8 a.m. to 5 p.m. for
Noisy work] Approve extended
hours [Monday through Friday, 5
p.m. to 8 p.m.; Saturday 7 a.m. to 8
p.m.; and Sunday 8 a.m. to 4:30
p.m.] only with advanced notice
from the UCSF project manager.
Prohibit high impact noise on
Saturdays and Sundays.
Issue instructions in each bid
package of each construction project
for contractors to incorporate the
mitigation. The successful contractor
will prepare a construction noise
impact abatement plan to report on
the implementation of the mitigation
measure.
Project Manager,
Medical Center Design
and Construction Team,
or Capital Programs
Facilities Management,
as appropriate
Provide written verification in report
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provisions for construction
noise abatement (including limitations
on construction hours). Provide a
report on construction noise
abatement to Monitor upon request;
but no less than quarterly after
beginning each construction activity.
Designate a UCSF Community
Contact to receive and resolve
construction complaints.
Designate a UCSF Community
Contact to receive and resolve
construction noise complaints.
UCSF Community
Relations
Provide written verification to the
Monitor within 10 working days of the
first contract bid identifying the UCSF
Community Contact and contact
information.
4.6 TRANSPORTATION AND TRAFFIC
MCMB.6‐3: Operation of the
Medical Center at Mission Bay
project would increase traffic at
intersections on the adjacent
roadway network in the Future
Phase.
Regarding Owens Street at the
Center Garage Access, UCSF would
conduct project‐level CEQA review
at the time the Future Phase
development is considered for
approval. In addition, UCSF would
Conduct project‐level CEQA review
for Future Phase development.
Coordinate with the City of San
Francisco in the periodic update of
the Mission Bay traffic triggers
survey. Monitor on‐site parking
UCSF Campus Planning Prepare memo to Monitor within 10
days of preparation of Project
Planning Guide (PPG) for Future
Phase development that project‐level
CEQA review for Future Phase
development will be prepared.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 7
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
coordinate with the City of San
Francisco in the periodic update of
the Mission Bay traffic triggers
survey and would monitor on‐site
parking access and circulation in
order to determine the need for LOS
improvements on Owens Street
between 16th and Mariposa Streets.
UCSF would coordinate with the
Municipal Transportation Agency
(which includes the Department of
Parking and Traffic) and the
Planning Department to confirm the
feasibility and effectiveness of
mitigation measures resulting from
future analysis or consider
equivalent recommendations made
by these agencies, and UCSF will pay
its fair share of the cost of
implementing the selected
mitigation.
access and circulation in order to
determine the need for LOS
improvements on Owens Street
between 16th and Mariposa Streets.
Coordinate with the Municipal
Transportation Agency (including
the Department of Parking and
Traffic) and the Planning Department
to confirm the feasibility and
effectiveness of mitigation measures
resulting from future analysis or
consider equivalent
recommendations made by these
agencies. Pay for fair share of the
cost of implementing selected
mitigation.
Following project‐level CEQA review
for Future Phase development,
prepare additional memo to Monitor
describing status of LOS
improvements on Owens Street
between 16th and Mariposa,
coordination efforts with the City to
confirm the feasibility, acceptability
and effectiveness of mitigation
measures, and status of fair share
payments for cost of implementing
selected mitigation.
MITIGATION MEASURES CARRIED FORWARD FROM THE UCSF LRDP AMENDMENT #2 – HOSPITAL REPLACEMENT EIR
4.1. AESTHETICS
4.1‐1: New hospital
development at any of the sites
could increase light and glare
which could affect nighttime
views at the selected site and in
its vicinity.
Minimize light and glare from new
hospital development through the
orientation of buildings, use of
landscaping materials, and choice of
primary facade materials. Design
standards and guidelines to minimize
light and glare would be adopted for
the new hospital development,
including:
Reflective metal walls and mirrored
Issue instruction in each bid package
of each architectural services contract
for architects and design
professionals to incorporate the
mitigation as design criteria.
Working with the project and
construction managers, require
architects and design professionals to
document how siting and design
measures are addressed and
Medical Center Design
and Construction Team,
Project Manager.
Provide written verification in report
form to Monitor within 10 working
days of each contract bid on each
phase. Report will certify that selected
bids utilize design elements which
maximize compliance with design
criteria.
(Status: facade materials and
landscaping incorporated into the
MCMB Phase I Garage project design
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 8
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
glass walls shall not be used as
primary building materials for
facades.
Installation of illuminated building
signage shall strive to be consistent
with City Planning Code sign
requirements and/or Mission Bay
design guidelines.
Exterior light fixtures shall be
configured to emphasize close spacing
and lower intensity light. Light
fixtures shall use luminaries that
direct the cone of light downward.
(Modified from LRDP FEIR Mitigation
Measure 12LI‐3 for the LRDP and
Future Phases)
incorporated. Review design plans
for each new proposed structure to
ensure that such features have been
incorporated in the design to address
light/glare impacts.
minimize light and glare impacts.
Exterior light fixtures have been
designed to be directed downward.)
4.1‐2: Construction of a new
hospital could result in flood
lighting at any of the sites
during nighttime construction
activities.
UCSF would require a condition in
construction contracts that flood or
area lighting for construction
activities be placed and directed so
as to avoid potential disturbances to
adjacent residences or other uses.
(Modified from LRDP Mitigation
Measure 12L1‐4 for the LRDP and
Future Phases)
Issue instructions in each bid
package of each architectural services
contract for architects and design
professionals to incorporate the
mitigation as design criteria.
Working with the project and
construction managers, require
contractors to document how siting
and construction lighting measures
are incorporated. Review
construction documentation to
ensure that mitigation is included to
address lighting effects.
Medical Center Design
and Construction Team,
Project Manager.
Provide written verification in report
form to Monitor within 10 working
days of each contract bid on each
phase. Report will certify that selected
bids utilize design elements which
maximize compliance with design
criteria.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 9
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
4.1‐4: Construction and
operation of a hospital at the
Mission Bay South site could
substantially degrade the visual
quality of the Mission Bay
campus site or its
surroundings.
Extend to the CMPDG to the Mission
Bay South site or develop Mission
Bay South site land use designations
and design guidelines that apply
1996 LRDP goals and objectives for
visual quality, protection of view
corridors, creation of open space, and
compatibility with the surrounding
area. Implementation of this
measure would avoid a substantial
degradation of the visual quality due
to the Mission Bay South site
development. (Identified in the
LRDP Amendment #2 EIR for the
LRDP and Future Phases)
Prior to or as part of project‐specific
planning and design, develop design
guidelines for the Mission Bay South
site and adjacent blocks, as
applicable.
UCSF Campus Planning
and Medical Center
Design and Construction
Team
Issue new design guidelines with
specific prescriptions for the Mission
Bay South site and incorporate the site
as appropriate into the revised
CMPDG.
(Status: The Medical Center at
Mission Bay, including the Phase 1
Garage, is consistent with applicable
guidelines of the CMPDG. In
addition, specific design standards for
the Medical Center at Mission Bay
were developed and identified in the
Memorandum of Understanding
between the University and the San
Francisco Redevelopment Agency.)
4.2 AIR QUALITY
4.2‐1: Construction and
operation of replacement
hospital facilities would
generate vehicular, stationary
source, and helicopter‐related
emissions (depending on
scenario) that would contribute
to regional air pollution.
UCSF shall continue its existing
Transportation Demand
Management programs to promote
shuttle services, ride‐sharing, and
bicycle programs to reduce the
number of trips at its campus sites.
These transit options divert trips
from single occupancy vehicles and
would thus reduce impacts of
vehicular trips generated by the
project. (Modified from LRDP FEIR
Mitigation Measures 12D4‐2 for the
LRDP and Future Phase)
Extend UCSF shuttle service to the
project site; work to promote other
TDM programs at the project site,
such as pre‐tax transit passes and
ride‐sharing; consider in parking
plans allocations for vanpool,
motorcycle, and bicycle parking.
UCSF Parking &
Transportation Services
in conjunction with
UCSF Medical Center
and Campus Planning
Provide written verification to
Monitor regarding TDM programs
considered and implemented.
4.2‐2: Demolition and
construction activities
associated with the hospital
construction would generate
fugitive dust and criteria
During construction, UCSF shall
require the construction contractor to
implement the appropriate level of
BAAQMD’s dust control procedures
for all construction sites. UCSF shall
Issue instructions in each bid
package of each construction project
for contractors to incorporate the
mitigation. The successful contractor
will prepare a construction air
Project Manager,
Medical Center Design
and Construction Team.
Provide written verification in report
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provisions for construction
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 10
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
pollutant emissions that could
adversely affect local air
quality.
include this requirement in all
construction contracts. This mitigates
this impact to less than significant.
(Modified from LRDP FEIR
Mitigation Measure 12D1‐1 for the
LRDP and Future Phase)
pollution control strategy to report
on the implementation of the
mitigation measure.
air pollution control. Provide a report
on construction air pollution control
strategies and report to Monitor upon
request; but no less than quarterly
after beginning each construction
activity.
4.2‐5: Vehicular traffic
generated by construction and
operation of a 400‐bed or 650‐
bed hospital and associated
facilities, in conjunction with
traffic generated from
concurrent LRDP projects at
each campus site, plus non‐
UCSF projects, would result in
criteria pollutant emissions that
would have a significant
cumulative impact on the
ambient air quality.
Implement Mitigation Measure 4.2‐1.
4.3 CULTURAL RESOURCES
4.3‐1: Building construction,
including excavation and
grading associated with the
proposed project, could cause
substantial adverse changes to
archaeological resources at the
project sites.
If the discovery includes human
remains, CEQA Guidelines 15064.5
(e)(1) shall be followed:
In the event of the accidental
discovery or recognition of any
human remains in any location other
than a dedicated cemetery, the
following steps should be taken:
(1) There shall be no further
excavation or disturbance of the site
or any nearby area reasonably
suspected to overlie adjacent human
remains until:
Issue instructions in each bid
package of each construction project
for contractors to incorporate the
mitigation. The successful contractor
will demonstrate knowledge of
procedures and requirements when
cultural resources are discovered
during construction activities.
UCSF Capital Projects
Facilities Management
Project Manager.
Provide written verification in report
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provisions for mitigation if
cultural resources are discovered
during construction activities.
Provide construction status report to
Monitor upon request.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 11
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
(A) The coroner of the county in
which the remains are discovered
must be contacted to determine that
no investigation of the cause of death
is required, and
(B) If the coroner determines the
remains to be Native American:
(1) The coroner shall contact the
Native American Heritage
Commission within 24 hours. (2) The
Native American Heritage
Commission shall identify the person
or persons it believes to be the most
likely descended from the deceased
Native American. (3) The most likely
descendent may make
recommendations to the landowner
or the person responsible for the
excavation work, for means of
treating or disposing of, with
appropriate dignity, the human
remains and any associated grave
goods as provided in Public
Resources Code Section 5097.98, or
(2) Where the following conditions
occur, the landowner or his
authorized representative shall
rebury the Native American human
remains and associated grave goods
with appropriate dignity on the
property in a location not subject to
further subsurface disturbance.
(A) The Native American Heritage
Commission is unable to identify a
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 12
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
most likely descendent or the most
likely descendent failed to make a
recommendation within 24 hours
after being notified by the
commission.
(B) The descendant identified fails to
make a recommendation; or
(C) The landowner or his authorized
representative rejects the
recommendation of the descendant,
and the mediation by the Native
American Heritage Commission fails
to provide measures acceptable to
the landowner. (Identified in the
LRDP Amendment #2 EIR for the
LRDP and Future Phase)
4.4 GEOLOGY AND SOILS
4.4‐4: In the event of a major
earthquake in the region,
seismic ground shaking could
expose people and property to
liquefaction and earthquake‐
induced settlement at Mission
Bay.
A site‐specific, design‐level
geotechnical investigation shall be
completed based on the proposed
project design and shall provide
engineering recommendations for
mitigation of liquefiable soils, in
accordance with the California
Geological Survey’s Geology
Guidelines for Evaluating and
Mitigating Seismic Hazards (CGS
Special Publication 117, 1997). These
geotechnical recommendations shall
be incorporated into the final design
of the project. (Identified in the
LRDP Amendment #2 EIR for the
LRDP Phase)
Prepare a geotechnical survey and
incorporate the results of the
investigation into the project design
to address impacts.
UCSF Campus Planning,
and Medical Center
Design and Construction
Team.
Provide Medical Center Design and
Construction Team final geotechnical
investigation that reports feasible
measures and incorporates them into
project design.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 13
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
4.5 HAZARDS AND HAZARDOUS MATERIALS
4.5‐4: Operation of the new
hospital facilities would
generate hazardous waste that
could place an additional load
on hazardous waste
management facilities.
UCSF shall implement hazardous
waste handling, minimization, and
disposal procedures at any chosen
site for hospital replacement
consistent with safety requirements
and applicable laws and regulations.
UCSF shall extend its existing
hazardous waste minimization plan
to include any chosen site for
hospital replacement.
UCSF shall implement the
operational controls required to
comply with laws and regulations,
including, but not limited to,
monthly safety and compliance
audits and training of staff at any
chosen site for hospital replacement.
This would 1) allow efficient
processing of wastes for shipment to
treatment facilities or disposal,
reducing the time that hazardous
wastes are at a chosen hospital
replacement site, and 2) ensure that
safety controls such as OSHA
training, correct practices and safety
equipment are in place.
At the new hospital facilities, UCSF
will extend its program for
hazardous waste handling,
minimization and disposal, including
implementation of all the measures
identified in the mitigation measure.
In addition, in conjunction with bi‐
annual inspections of UCSF by the
City and County of San Francisco
Department of Public Health, and the
Department of Health Services,
Radiologic Health Branch, initiate a
review by the Chemical Safety
Officer and the Radiation Safety
Officer (in consultation with the
Chemical Safety Committee and the
Radiation Safety Committee as
required) of existing source reduction
and management plans for
additional measures that are feasible
to implement at UCSF to minimize
hazardous waste and dry long‐lived
radioactive waste.
Environmental Health &
Safety, Chemical Safety
Officer and Radiation
Safety Officer.
Notify Monitor when hazardous
waste handling, minimization and
disposal measures are extended to the
new hospital facilities. In addition,
provide hazardous chemical waste
and radioactive waste source
reduction and management review to
Monitor every other year as part of the
bi‐annual Business Plan inspection
and RHB inspection. Report feasible
measures to be implemented and
timetable for such additional
measures.
UCSF shall implement procedures to
minimize increases in the long‐lived
radioactive waste generation.
According to the California
Department of Health Services
Radiologic Health Branch, California,
radiologic licenses should:
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 14
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
1) minimize the amount of low‐level
radioactive waste in possession
and avoid accumulating waste
that cannot be disposed
promptly;
2) segregate for disposing radioactive wastes that are not
subject to Southwestern Low‐
Level Radioactive Waste Disposal
Compact regulations;
3) segregate waste that can be
disposed of or reduced in volume
by approved treatment methods;
4) segregate short‐lived radioactive waste for decay;
5) consider recycling radioactive materials;
6) consider extended on‐site storage of any remaining low‐level
radioactive waste; and
7) consider non‐radioactive substitutes. (Modified Measure
from LRDP FEIR Mitigation
Measure 12F1‐3)
4.5‐6: Soil and groundwater
contamination at the Mission
Bay North and South sites
could expose construction
workers, the public, and the
environment to hazards
associated with soil and
groundwater contamination.
UCSF shall develop a RMP for Parcel
X‐3 if it is acquired or extend the
1999 RMP to Parcel X‐3, if feasible.
The UCSF Office of Environmental
Health & Safety will coordinate with
the current land owner to prepare or
contract for preparation of a
complete site assessment and
implementation of the identified
mitigation measures. Alternatively,
UCSF could conduct the assessment
Environmental Health &
Safety, Asbestos /
Hazardous Materials
Removal Officer
Provide copies of the assessment and
remediation plans to Monitor for each
project and phase. Provide evidence
from the Regulatory Agency of
satisfactory completion of
remediation.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 15
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
and remediation itself in accordance
with federal and state requirements.
4.6 HYDROLOGY AND WATER QUALITY
4.6‐3: Construction of new
hospital buildings at the
Mission Bay North or South
sites by the LRDP Phase or
Future Phases could result in
hydrology and water quality
impacts at Mission Bay.
UCSF shall adopt Mitigation
Measures K.2, K.3 and K.4 of the
Mission Bay Subsequent EIR as
follows:
K.2 Participate in the City’s existing
Water Pollution Prevention Program.
Facilitate implementation of the
City’s Water Pollution Prevention
Program by providing and installing
wastewater sampling ports in any
building anticipated to have a
potentially significant discharge of
pollutants to the sanitary sewer, as
determined by the Water Pollution
Prevention Program of the San
Francisco Public Utilities
Commission’s Bureau of
Environmental Regulation and
Management, and in locations as
determined by the Water Pollution
Prevention Program.
This mitigation measure could be
implemented by including the Water
Pollution Prevention Program in the
review process, as each individual
construction is proposed. The Water
Pollution Prevention Program would
review each project, determine if one
or more sampling ports should be
installed in a particular building, and
specify the location of the sampling
Issue instructions in each bid
package of each construction project
for contractor to incorporate the
mitigation measures.
Medical Center Design
and Construction Team
Provide written verification in report
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provisions for mitigation
measures. Provide construction status
report to Monitor upon request.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 16
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
port(s).
K.3 Design and construct sewer
improvements such that potential
flows to the City’s combined sewer
system from the project do not
contribute to an increase in the
annual overflow volume as projected
by the Bayside Planning Model by
providing increased storage in
oversized pipes, centralized storage
facilities, smaller dispersed storage
facilities, or detention basins, or
through other means to reduce or
delay stormwater discharges to the
City system.
K.4 Implement alternative
technologies or use other means to
reduce settleable solids and floatable
materials in stormwater discharges to
China Basin Channel to levels
equivalent to, or better than, City‐
treated combined sewer overflows.
Such alternatives technologies could
include one or more of the following:
biofilter system, vortex sediment
system, catch basin filters, and/or
additional source control measures to
remove particulates from streets and
parking lots. (Identified in the LRDP
Amendment #2 EIR for the LRDP
and Future Phase)
4.8 NOISE
4.8‐1: The proposed Hospital Mitigation Measure 4.8‐1: UCSF Issue instructions in each bid Capital Projects Facilities Provide written verification in report
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 17
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
Replacement Program would
result in noise associated with
demolition and construction
activities.
shall require construction contractors
to minimize unavoidable
construction noise impacts by use of
proper equipment and work
scheduling:
Limit construction hours to between
7:00 a.m. and 8:00 p.m. on weekdays
and 9:00 a.m. to 5:00 p.m. on
weekends. Approve extended hours
only with advanced notice from
UCSF project manager. Prohibit high
impact noise on Sundays.
[Superceded by Mitigation Measure
MCMB.5‐1]
Require use of construction
equipment with noise reduction
devices (i.e., mufflers in good
working order).
Erect temporary noise walls to
protect adjacent noise‐sensitive areas.
Use of impact tools would be
minimized to the extent feasible.
Implement “quiet” pile‐driving
technology (such as pre‐drilling of
piles, and/or the use of more than
one pile driver to shorten the total
pile‐driving duration), where
feasible, in consideration of
geotechnical and structural
requirements and conditions.
Locate stationary noise sources away
from residential or other sensitive‐
receptor areas, and require use of
acoustic shielding with such
package of each construction project
for contractors to incorporate the
mitigation. The successful contractor
will prepare a construction noise
impact abatement plan to report on
the implementation of the mitigation
measure.
Management or Medical
Center Design and
Construction Team, as
appropriate
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provisions for construction
noise abatement. Provide a report on
noise abatement to Monitor upon
request; but no less than quarterly
after beginning each construction
activity.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 18
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
equipment when feasible and
appropriate.
(Modified measure from LRDP FEIR
Mitigation Measure 12E1‐1)
4.8‐2: Operational activities
and mechanical equipment
would increase noise levels at
sensitive receptors.
UCSF shall incorporate standard
industrial noise control measures for
stationary equipment at any site
chosen for hospital replacement.
UCSF shall also adopt noise
performance standards to ensure that
operational noise from UCSF sources
would not exceed noise guidelines
set forth in local General Plans or
ordinances for adjacent areas based
on use standards. If ambient noise
levels in areas adjacent to the site(s)’
proposed for hospital replacement
already exceed local noise standards,
UCSF shall not increase average
daily noise levels (Ldn) from
operational noise sources by 3 or
more dBA at the property line. USCF
shall use standard design features
including installation of relatively
quiet models, orientation or
shielding to protect sensitive uses,
and installation within enclosures
when necessary to reduce noise.
(Modified measure from LRDP FEIR
Mitigation Measure 12E1‐2)
All contractors and design
professionals responsible for
selecting mechanical equipment will
be required to perform noise
calculations based on mechanical
equipment specifications of the
vendor or measure equipment noise
levels at the nearest property line to
ensure the selected equipment meets
the criteria. If the projected
equipment noise levels exceed Noise
Ordinance specifications, the
contractor or design professional will
be required to implement additional
measures, to ensure that the
standards are met, and re‐monitor.
Medical Center Design
and Construction Team,
Project Manager.
Provide written verification to the
Monitor of the inclusion of the
performance standards and conduct
final monitoring as required.
4.8‐7: Site‐specific construction
and demolition activities at
each campus site would have a
local, significant cumulative
impact on the local noise
Implement Mitigation Measure 4.8‐1.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 19
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
environment.
4.11 TRANSPORTATION
4.11‐1: Building construction,
including demolition,
excavation, and grading
associated with the proposed
LRDP Amendment could cause
substantial adverse impacts to
traffic flow, circulation and
access as well as to transit,
pedestrian, and parking
conditions.
Mitigation 4.11‐1: To assure that
construction and/or demolition
activities minimize parking demand
and circulation obstruction, UCSF
shall require construction and/or
demolition contractors to develop
and implement construction traffic
and parking management plans
during demolition and/or
construction activities at all campus
sites. The plans would be expected
to include measures such as the
following:
Develop a traffic management plan
in consultation with the San
Francisco DPT and Muni to minimize
disruption due to lane closures. The
plan should be consistent with the
Regulations for Working in San
Francisco Streets and Chapter 6 of
the California Supplement to the
Manual of Uniform Traffic Control
Devices.
Prepare an offsite parking plan for
construction employees and
subcontractor employees. An
alternative plan would provide
shuttle service to/from designated
remote parking lots and/or public
transportation transfer nodes. This
plan would be incorporated into the
construction contract between UCSF
Issue instructions in each bid
package of each construction project
for contractors to incorporate the
mitigation. Require the successful
contractor to prepare a construction
traffic and circulation plan for each
new proposed construction project to
report on the implementation of the
mitigation measure.
Medical Center Design
and Construction Team,
Capital Projects Facilities
Management, as
appropriate.
Provide written verification in report
form to the Monitor within 10
working days of each contract bid on
each phase to certify that selected bid
includes provisions for a construction
traffic and circulation plan. Provide a
construction traffic and circulation
plan implementation report to
Monitor upon request; but no less
than quarterly after beginning each
construction activity.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 20
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
and the contractor.
Schedule heavy‐truck deliveries with
the construction project manager at
least one day in advance.
Whenever possible, make deliveries
using trucks of 40 feet maximum
bumper‐to‐bumper length.
Whenever possible schedule heavy
trucks deliveries to arrive at off‐peak
hours, outside of 7:00 a.m. to 9:00
a.m. and 4:00 p.m. to 6:00 p.m.
Note any deliveries that cannot
comply with the above requirements
for heavy trucks on the schedule, and
notify the UCSF construction project
manager at least 48 hours in advance.
The contractor may provide flagmen
to direct traffic in those cases.
(Identified in the LRDP Amendment
#2 EIR for the LRDP and Future
Phases)
4.11‐2: Operation of a hospital
at the Mission Bay North or
South sites would increase
traffic at intersections on the
adjacent roadway network.
See below.
4.11‐2a: Operation of a hospital
at the Mission Bay South site
would increase average delay
per vehicle during the p.m.
peak hour at the intersection of
16th Street / Owens Street.
UCSF shall coordinate with the City
of San Francisco to provide the
following lane configuration for the
southbound approach on Owens
Street at the intersection of 16th
Street / Owens Street: one
southbound shared through‐left‐turn
Work with appropriate City
Departments on lane configuration at
this intersection to achieve acceptable
level of service, or develop other
mitigation measures that are equally
effective and acceptable to the City.
Vice Chancellor ‐
University Advancement
& Planning, Campus
Planning, Government
Relations.
Report coordination efforts to Monitor
and provide documentation
confirming lane configuration has
been approved by City and
implemented.
MITIGATION MONITORING AND REPORTING PROGRAM (Continued)
SUPPLEMENTAL EIR FOR THE UCSF MEDICAL CENTER AT MISSION BAY – PHASE 1 GARAGE
UCSF Medical Center at Mission Bay – Phase I Garage SEIR 21
Significant Impact Mitigation Measure Implementation Responsible Unit Report Mechanism
lane, one southbound through‐lane,
and one southbound exclusive right‐
turn lane. (Identified in the LRDP
Amendment #2 EIR for the Future
Phase)
4.11‐2b: Operation of a hospital
at the Mission Bay South site
would increase average delay
per vehicle during the p.m.
peak hour at the intersection of
Mariposa Street / 3rd Street.
UCSF shall coordinate with the City
and County of San Francisco to
provide an additional southbound
exclusive right‐turn lane of a
minimum 50‐foot length on 3rd
Street at the intersection of Mariposa
Street / 3rd Street. (Identified in the
LRDP Amendment #2 EIR for Future
Phase)
Work with appropriate City
Departments to get Board of
Supervisor approval for the
dedication of land that would be
required for the lane, or develop
other mitigation measures that are
equally effective and acceptable to
the City.
Vice Chancellor ‐
University Advancement
& Planning, Campus
Planning, Government
Relations.
Report coordination efforts to
Monitor. If UCSF cannot dedicate to
City, this measure would remain a
significant unavoidable impact.
APPENDIX A INITIAL STUDY
INITIAL STUDY
University of California San Francisco
Medical Center at Mission Bay Phase I Garage
Lead Agency: The University of California
Prepared by: UCSF Campus Planning
654 Minnesota Street
San Francisco, CA 94143‐0286
February 25, 2011
University of California
San Francisco Campus Planning University Advancement and Planning
Organization of the Initial Study
This Initial Study is organized into the following sections:
Section I – Project Information: provides information about the proposed project, including project
location, lead agency, and contact information.
Section II –Project Description: describes the proposed project, the elements included in the project, and
the project approvals.
Section III –Environmental Factors Potentially Affected: identifies which environmental factors, if any,
would be affected by the project, including those that involve at least one significant or potentially
significant impact that cannot be reduced to a less‐than‐significant level.
Section IV – Determination: indicates whether impacts associated with the proposed project are
significant, and what, if any, additional environmental documentation is required.
Section V – Evaluation of Environmental Impacts: contains the Environmental Checklist form for each
resource area. The checklist is used to assist in evaluating the potential environmental impacts of the
proposed project and whether those impacts were adequately analyzed in the UCSF Medical Center at
Mission Bay EIR. This section also presents an explanation of all checklist answers.
Section VI – Supporting Information Sources: lists the references used in the preparation of this
document.
Section VII – Initial Study Preparers
‐ 1‐
I. PROJECT INFORMATION
1. Project title:
UCSF Medical Center at Mission Bay Phase I Garage
2. Lead agency name and address:
The Regents of the University of California
1111 Franklin Street
Oakland, California 94607
3. Contact person and phone number:
UCSF Campus Planning
Tammy Chan, Senior Planner
(415) 476‐9627
4. Project location:
UCSF Medical Center at Mission Bay
Portions of Blocks 38 and 39
San Francisco, California 94143
5. Project sponsor’s name and address:
Same as above.
6. Custodian of the administrative record for this project:
Same as above.
7. Identification of previous EIRs relied upon for tiering purposes (including all applicable
LRDP and project EIRs) and address where a copy is available for inspection.)
Document for which this Initial Study and SEIR is prepared:
Final EIR for UCSF Medical Center at Mission Bay, certified by The Regents on September 17,
2008 (State Clearinghouse No. 2008012075
Related UCSF documents that are referenced:
Final EIR on the 1996 LRDP certified by The Regents on January 17, 1997 (State
Clearinghouse No. 1995123032)
Final LRDP SEIR on LRDP Amendment #1, Mission Bay Housing Program, certified by The
Regents on January 17, 2002 (State Clearinghouse No. 1995123032)
Final LRDP FEIR on LRDP Amendment #2, Hospital Replacement Program, certified by The
Regents on March 17, 2005 (State Clearinghouse Number 2004072067)
UCSF Medical Center at Mission Bay FSEIR ‐ Residential Sound Reduction Program for
Helicopter Operations, certified by The Regents on April 20, 2009, (State Clearinghouse
Number No. 2008012075)
Copies of all relevant CEQA documents, including the 1996 LRDP and subsequent LRDP Amendments
are available at UCSF Campus Planning.
Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage
‐ 2 ‐
II. PROJECT DESCRIPTION
A. INTRODUCTION
This initial study evaluates revisions to the proposed parking structure previously analyzed in the 2008
UCSF Medical Center at Mission Bay EIR to determine whether the minor revisions to the parking garage
would cause new or substantially more significant environmental effects that were not previously
examined in the 2008 EIR. If the revisions to the project could cause new or substantially more significant
environmental effects that were not previously examined in the 2008 EIR, pursuant to Section 15163 of the
CEQA Guidelines, the lead agency may choose to prepare a supplement to an EIR rather than a
subsequent EIR if “only minor additions or changes would be necessary to make the previous EIR
adequately apply to the project in the changed situation.” This initial study would support the
preparation of the Supplemental EIR (SEIR) and Pursuant to Section 15163(b), “The supplement to the
EIR need contain only the information necessary to make the previous EIR adequate for the project as
revised.”
B. BACKGROUND
Each campus of the University of California is required to prepare a Long Range Development Plan
(“LRDP”) that sets forth concepts, principles, and plans to guide future growth of that campus. The
Board of Regents of the University of California (“The Regents”) adopted the 1996 LRDP, which outlines
development proposals for the University of California, San Francisco (“UCSF”) through the academic
year 2011/12. The LRDP has since been amended several times, and an EIR was prepared for each
amendment. The 1996 LRDP FEIR, together with the various EIRs prepared for LRDP amendments, are
collectively the “LRDP EIR.”
LRDP Amendment #2, approved in March 2005, described the planning process that considered potential
hospital replacement sites at Parnassus Heights, Mount Zion, and Mission Bay. A preferred plan to
develop three integrated specialty hospitals at Mission Bay on the Mission Bay South site located south of
16th Street was identified, but other sites remained in consideration. The Hospital Replacement Program
was analyzed at a program level in the LRDP Amendment #2‐ Hospital Replacement EIR (2005 EIR).
Subsequently, once the Mission Bay South site option was selected, the UCSF Medical Center at Mission
Bay EIR was prepared in September 2008. The 2008 EIR, which was tiered from the program‐level 2005
EIR, focused on the project‐level environmental effects of the Medical Center at Mission Bay.
The project proposed in the 2008 UCSF Medical Center at Mission Bay EIR was analyzed in two major
phases, the LRDP Phase (Phase I) and Future Phase (Phase II). Phase I included a 289‐bed hospital, an
Outpatient building and the Cancer Outpatient building, consisting of 336,500 gross square feet (GSF), a
36,000 GSF Energy Center, and a 600‐space parking structure with 475‐surface parking spaces, totaling
1,075‐parking spaces. In September 2008, The Regents approved the hospital, the Energy Center, the
Outpatient building, and the surface parking. Groundbreaking for the approved components of Phase I
began in October 2010, with the hospital complex scheduled to open in 2014. Approval of the other
components of Phase I, including the parking structure and the Cancer Outpatient building, would occur
at a future date. Phase II would include a 261‐bed hospital and approximately 225 to 925 parking spaces.
Upon completion of both phases, the UCSF Medical Center at Mission Bay would provide a 550‐bed
hospital, two outpatient facilities, and associated support space and parking. Phase II is assumed to start
following the completion of the Phase I, and would require subsequent project‐level environment review
once specific project design is available.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 3 ‐
The UCSF Medical Center at Mission Bay EIR was certified by The Regents on September 17, 2008. The
purpose of this initial study is to evaluate the proposed revisions to the parking structure in Phase I of the
UCSF Medical Center at Mission Bay. All other aspects of the Phase I project would remain the same.
Therefore, the focus of this initial study is on the revisions to the parking structure, no further discussion
is required for other components of the Phase I UCSF Medical Center at Mission Bay.
C. PROJECT LOCATION AND DESCRIPTION
The Mission Bay campus site is one of three major UCSF campus sites in San Francisco. As shown in
Figure 1, UCSF Campus Locations, the Mission Bay Campus is located approximately one and one‐half
miles south of downtown. The 2008 UCSF Medical Center at Mission Bay EIR analyzed a project site
consisting of 14.5 acres just south of the existing UCSF Mission Bay research campus. The site is within
the Mission Bay Redevelopment Plan and consists of the Mission Bay South Plan Parcels 36‐39, and X3.
The project site is bordered by 16th Street to the north, 3rd Street to the east, and Mariposa Street to the
south. In the future, a new segment of Owens Street would extend south of 16th Street to create the
western boundary of the project site. (See Figure 2, Project Location Map)
As analyzed in the 2008 EIR, the Medical Center at Mission Bay complex would be constructed on the
eastern portion of the site on Blocks 36, 37 and X3. A 600‐space parking structure at about 90 feet tall
would also be constructed as part of Phase I. The parking structure would be located along the
southwestern portion of the site. Surface parking for approximately 475 vehicles would be provided on
the remainder of Blocks 38 and 39. Therefore, at the completion of Phase I, approximately 1,075 parking
spaces for staff, patients, and visitors would be provided.
As currently proposed, the Phase I parking structure would be 105‐feet‐tall and would include 626
spaces. The location of the proposed garage has also shifted to the north so that it is closer to 16th Street.
(See Figure 3, Project Site Plan) The location of the proposed parking structure in relation to the Medical
Center at Mission Bay complex that is currently under construction is illustrated in Figure 4, Aerial Site
View. The number of surface parking spaces proposed in Phase I on the remainder of Blocks 38 and 39
has been reduced to approximately 429 spaces, with an additional 13 spaces east of the future extension
of 4th Street, in what is known as the east lot. The total surface parking spaces would be approximately
442 compared to the 475 spaces analyzed in the 2008 EIR. Therefore, the total number of parking spaces
provided in Phase I (626 spaces in the parking structure and 442 surface parking spaces) would decrease
by approximately seven spaces and would total approximately 1,068‐parking spaces from 1,075 spaces.
Figure 5, Ground Floor Plan, provides the footprint of the proposed parking structure while Figure 6,
North‐South Building Section, provides the section of the parking levels.
Subsequent to the publication of the 2008 EIR, the access roads from Owens and 4th Street, leading to the
proposed parking structure has been renamed from North and South Access Roads to North and South
Connector Roads, and the Center Garage Access is now referred to as Parking Structure Road. Similar to
the original proposed project, access and circulation to the site and the associated parking would be from
Owens or 4th Streets via the North and South Connector Roads, with Owens Street accommodating the
majority of the vehicular traffic.
A total of 114 bicycle spaces would be constructed, which is in excess of the one bike space per 20 vehicle
parking ratio required in the Design for Development of the Mission Bay South Plan Area. Of the 114
bicycle spaces provided, 72 secured spaces would be provided in a cage inside the garage and 42 spaces
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 4 ‐
would be outside the garage. In addition, 66 motorcycle stalls would be provided in the parking garage
and 16 motorcycle stalls would be provided in the surface parking lot.
Vertical metal louvers with an anodized finish are proposed on the exterior of the parking structure. This
would provide light and varying views into the garage from different viewpoints, while also allowing for
proper ventilation. The louvers would be finished in warm earth tones in color and would also act as
shades to reduce the effects of direct headlights from vehicles. Figure 7, Approach from Owens Street,
shows the visual aesthetics of the structure along Owens Street. To reduce the potential for light
pollution, roof top light fixtures are designed with cut off features that ensure no direct artificial light
spills over the uppermost parking level.
As noted above, Phase II was also analyzed in the Medical Center at Mission Bay EIR which would
include a 261‐bed hospital and approximately 225 to 925 additional parking spaces. No revisions are
being proposed for Phase II. However, subsequent project‐level environment review would be required
once specific project design is available. All adopted mitigation and improvement measures outlined in
the 2008 UCSF Medical Center at Mission Bay EIR would continue to be applicable.
D. PROJECT OBJECTIVES
The project objectives outlined in the 2008 UCSF Medical Center at Mission Bay EIR include the goals and
objectives developed for the 1996 LRDP and subsequent Amendments. The proposed parking structure
would support the Medical Center Project, analyzed in the 2008 Medical Center at Mission Bay EIR.
E. SURROUNDING LAND USES
The project site borders 16th Street to the north, 3rd Street to the east, and Mariposa Street to the south.
The western boundary of UCSF’s Mission Bay campus is along Owens Street, which currently ends at
16th Street. Just outside UCSF’s campus boundary, west of Owens and north of 16th Street, are the
Alexandria Life Science and Gladstone Institutes research and lab buildings. The project site is just south
of the existing UCSF Mission Bay research campus. The five story Genentech Hall and Byers Hall are
located directly north across 16th Street. The MUNI KT‐Third Street light rail is to the east, and runs
along Third Street. Upon the completion of Phase I, 4th Street would be extended through the site
providing access from 16th Street to the Potrero Hill and Dogpatch neighborhoods to the south.
Immediately south of parking proposed in Phase I is the site for a future City park, Mariposa Park. To the
west of the proposed parking structure, across from the future extension of Owens Street is a vacant
parcel, and the elevated I‐280 freeway.
F. DISCRETIONARY APPROVALS
Action by The Regents (including any Regents‐delegated committee or official): Anticipated project
actions and approvals include, but are not limited to approval of the design by the Chancellor for the
proposed Phase I Parking Structure at UCSF Medical Center at Mission Bay.
Action by Other Agencies: There are no responsible or trustee agencies that have approval authority over
the proposed project.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 5 ‐
G. CONSISTENCY WITH THE LRDP
Current development at UCSF is guided by the 1996 LRDP, as amended, which includes specific policies
related to future development and space needs at the various UCSF campuses. Amendment #1 amended
the LRDP to provide for on‐site student housing at Mission Bay. Amendment #2‐ Hospital Replacement
Program was analyzed at a program level in the LRDP Amendment #2‐ Hospital Replacement EIR (2005
EIR). Analyzed as part of the 2008 UCSF Medical Center at Mission Bay EIR, Amendment #3 added the
14.5‐acre UCSF Medical Center project to expand the UCSF Mission Bay campus to 57 acres, incorporated
the Mission Bay Planning Principles, and updated the functional zone maps at Mission Bay.
The 2008 UCSF Medical Center at Mission Bay EIR analyzed two major phases, LRDP Phase (Phase I) and
the Future Phase (Phase II). Phase I would include a 289‐bed hospital, two outpatient facilities, an Energy
Center, and associated parking. The original parking structure associated with Phase I would include 600
parking spaces with approximately 475‐surface parking spaces. No changes are currently proposed for
Phase II.
The revised project would include a 626‐space parking structure with approximately 442 total surface
parking spaces. All over, this would be a reduction of seven parking spaces. The revised project would be
generally consistent with the original program. One of the Mission Bay Planning Principle includes
community consultation during the life of a project regarding exterior design and landscape elements.
The project team for the proposed parking structure has been meeting with the San Francisco
Redevelopment Agency, the Mission Bay Citizens Advisory Committee, and a subgroup of the UCSF
Mission Bay Community Advisory Group ‐‐ the Mission Bay Community Action Team (CAT) ‐‐ on the
proposed exterior design. The proposed parking structure and the associated surface parking lot would
be consistent with the LRDP and the Mission Bay Planning Principles adopted as part of LRDP
Amendment #3.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 6 ‐
Figure 1: UCSF Campus Sites
Project Site is located within the Mission Bay Campus
Project Site
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 7 ‐
Figure 2: Mission Bay Campus Area
Proposed Project
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 8 ‐
Figure 3: Project Site Plan
Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage
‐ 9 ‐
Figure 4: Aerial View of the Proposed Project
Proposed Parking Garage
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 10 ‐
Figure 5: Proposed Ground Floor Plan
UCSF MEDICAL CENTER
AT MISSION BAY PARKING STRUCTURE Source: Rudolph and Sletten and WRNS Studios LLP
Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage
‐ 11 ‐
Figure 6: Proposed North‐South Building Section
UCSF MEDICAL CENTER
AT MISSION BAY PARKING STRUCTURE Source: Rudolph and Sletten and WRNS Studios LLP
Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage
‐ 12 ‐
Figure 7: Approach from Owens Street
UCSF MEDICAL CENTER AT MISSION BAY PARKING STRUCTURE Source: Rudolph and Sletten and WRNS Studios LLP
Initial Study for UCSF Medical Center at Mission Bay Phase I Parking Garage
‐ 13 ‐
III. ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED:
The environmental factors checked below would be potentially affected by this project, involving at least
one impact that is a “Potentially Significant Impact” as indicated by the checklist on the following pages.
□ Aesthetics □ Agriculture and Forestry
Resources □ Air Quality
□ Biological Resources □ Cultural Resources □ Geology/Soils
■ Greenhouse Gas Emissions □ Hazards & Hazardous
Materials □
Hydrology/Water
Quality
□ Land Use/Planning □ Mineral Resources □ Noise
□ Population/Housing □ Public Services □ Recreation
■ Transportation/Traffic □ Utilities/Service Systems ■ Mandatory Findings of
Significance
IV. DETERMINATION: (To be completed by the Lead Agency)
On the basis of the initial evaluation that follows:
■ I find that the proposed project could have a ʺpotentially significant impactʺ or ʺpotentially significant
unless mitigatedʺ impact on the environment, and that these effects have not been adequately analyzed by
an earlier EIR. A SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT will be prepared.
□
I find that although the proposed project could have a significant effect on the environment, because all
potentially significant effects (1) have been addressed adequately in an earlier environmental document
pursuant to applicable standards, and (2) either no changes or no substantial changes to the project are
proposed, and no new information of substantial importance has been identified. An ADDENDUM and/or
FINDINGS will be prepared.
Diane Wong, Environmental Coordinator
University of California, San Francisco
Date
V. EVALUATION OF ENVIRONMENTAL IMPACTS
The University has defined the column headings in the Initial Study checklist as follows:
A) “Additional Project‐level Impact Analysis Required” applies where the project may result in an
environmental impact that was not considered in an earlier document, or not considered in sufficient
detail, and/or substantial project changes, changed circumstances, or new information of substantial
importance triggering CEQA Section 15162 has occurred since certification of the earlier document.
B) “Project Impact Adequately Addressed in Earlier Environmental Document” applies where the
potential impacts of the proposed project were adequately addressed in an earlier environmental
document and either no changes or no substantial changes to the project are proposed, and no new
information of substantial importance has been identified.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 14 ‐
Impact Questions and Responses
The impact questions identified in this Section are the same as those in Appendix G of the CEQA
Guidelines. Additionally, in several impact topics there are impact questions that relate to significance
standards established in UCSF’s LRDP Final EIR, where they are not otherwise covered by Appendix G.
The impact questions consist of two types: those that require a qualitative evaluation, and those that
require a quantitative analysis. In general, the impact questions themselves constitute the standards of
significance, and where applicable, additional explanation and/or quantitative thresholds are provided
under the appropriate environmental topic.
Issues
Additional
Project‐level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
1. AESTHETICS – Would the project:
a) Have a substantial adverse effect on a scenic vista? □ ■
b) Substantially damage scenic resources, including,
but not limited to, trees, rock outcroppings, and
historic buildings within a state scenic highway?
□ ■
c) Substantially degrade the existing visual character
or quality of the site and its surroundings? □ ■
d) Create a new source of substantial light or glare
which would adversely affect day or nighttime views
in the area?
□ ■
e) Exceed the LRDP EIR significance standard by
substantially reducing sunlight or significantly
increasing shadows in public open space areas, or by
increasing pedestrian‐level wind speeds above the
hazard level set forth in the San Francisco Planning
Code?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 15 ‐
portion of the site as part of Phase I. The modified project would increase the height of the parking
structure to 105 feet tall, reduce the total number of parking spaces in Phase I by seven spaces, and shift
the location of the parking structure to the north, closer towards 16th Street, along the future Owens
Street extension. Due to the shift in the garage location, the intersection at Owens and Parking Structure
Road that would be constructed as part of Phase II in the original EIR analysis would be constructed as
part of Phase I. Therefore, under the revised project, three access points from Owens Street would be
created as part of Phase I, the North and South Connector Roads and the new intersection at Parking
Structure Road. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would
remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The 2008 Medical Center at Mission Bay EIR analyzed a 90‐foot‐tall, 600‐space parking structure located
on the southwestern portion of Block 38 as part of the Phase I Medical Center at Mission Bay project. The
general massing of Phase II of the parking garage was analyzed at a programmatic level. In Phase II,
approximately 225 to 925 additional parking spaces would be provided on the western portions of Blocks
38 and 39. The evaluation of visual quality in the Medical Center at Mission Bay EIR considered the
potential effects on visual character, views, light and glare, and wind.
1a) and b): As noted in the Notice of Preparation/Initial Study (NOP/IS) for the Medical Center at Mission
Bay, a scenic vista is defined as a public view from existing parks, plazas, roadways or other public areas,
and gateway or panoramic views from areas generally available to the general public. Views from private
residences and non‐public areas are not considered to be scenic views because they are not available to
the general public. The NOP/IS prepared for the Medical Center at Mission Bay concluded that
implementation of the project would not create impacts not previously considered in the Initial Study
prepared for the LRDP Amendment #2‐ Hospital Replacement EIR and would not have a substantial
adverse effect on a scenic vista. While the proposed parking structure has increased from 90 to 105 feet in
height, it would not have a substantial adverse effect on a scenic vista and the conclusion reached in the
NOP/IS under 1a) and b) would remain valid.
1c): The Medical Center at Mission Bay EIR concluded that implementation of the proposed project
would result in visual changes at the site with the demolition of the existing structures and development
and construction of a medical center. The adopted Mission Bay South Plan of the San Francisco
Redevelopment Agency (SFRA) calls for a densely built urban environment with building heights
ranging from 90 to 160 feet. The medical center would be developed to be visually consistent with the
surrounding development patterns in the Mission Bay mixed‐use neighborhood. In general, most
structures for the medical center project would be approximately 105 feet in height, with an additional 20
feet to the top of the mechanical components. The Medical Center at Mission Bay EIR concluded that
Phase I would be consistent with the development standards set forth in the SFRA MOU and compliance
with the SFRA MOU, as already required of UCSF, would ensure that the existing visual character or
quality of the site and its surroundings are not substantially degraded.
The modified parking garage would continue to be consistent with the development standards set forth
in the SFRA MOU, where the plan calls for a densely built urban environment with building heights
ranging from 90 to 160 feet and visual impacts would be less than significant.
The location of the Phase I parking structure has shifted further to the north, where it was previously the
area planned for the surface parking lot in Phase I. However, it should be noted that under full buildout
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 16 ‐
in Phase II, the entire site would be planned for a parking structure. Therefore, it would be consistent
with the use designated for this portion of Blocks 38 and 39 and consistent with the prior environmental
analysis. Access and circulation to the site and the proposed parking structure has been revised due to the
creation of the intersection at Owens and Parking Structure Road, during Phase I instead of Phase II. The
future Owens Street extension is still anticipated to accommodate the majority of the vehicular traffic.
Potential changes to the traffic analysis as a result of the modified project will be discussed in the SEIR.
The slight shift in the parking structure location would not substantially degrade or change the visual
quality of the site and impacts would be less than significant.
1d): The Medical Center at Mission Bay EIR analyzed the potential for the construction and operation of
the proposed development to increase the amount of light and glare in the area. The proposed medical
center would include cladding materials such as glass, precast concrete and metal panels. The EIR
concluded that any impacts associated with light and glare would be less than significant.
Similar to what was analyzed in the 2008 EIR, the revised parking garage would include metal panels
(louvers) on the exterior façade and would be generally consistent with the massing, materials, patterns,
and colors used for the Medical Center design. This would not change the analysis on this topic. To
mitigate any potential light spillover from the garage, the roof top light fixtures on the garage would
provide a cut off feature to ensure that no direct artificial light spillover from the uppermost parking
levels. Second, the metal louvered façade proposed for the parking structure would function as shades,
allowing for natural ventilation but reducing and refracting the artificial light from within the parking
structure. Therefore, the project design would further reduce any impacts associated with light and glare
and the conclusions reached in the EIR would remain valid and would be less than significant.
1e): A wind study was conducted in 2008 as part of the Medical Center at Mission Bay EIR. It was
conducted in response to the Mission Bay South Redevelopment Area requirement to identify and
mitigate significant impacts of pedestrian‐level winds, as stated in the Mission Bay Subsequent EIR1
Mitigation Measure D.7 (adopted through UCSF’s LRDP EIR Mitigation Measure 4.1‐7), as excerpt is as
stated as follows:
“D.7 The Redevelopment Agency would conduct wind review of high‐rise structures above 100 feet.
Wind tunnel testing would also be required unless… it is determined that… impacts, based on a 26‐mile‐
per‐hour hazard for a single hour of the year criterion, will not occur. The purpose of the wind tunnel
studies is to determine design‐specific impacts based on the above hazard criterion and to provide a basis
for design modifications to mitigate these impacts. Projects within Mission Bay, including UCSF, would
be required to meet this standard or to mitigate exceedances through building design.”
A wind study was conducted to determine design‐specific impacts based only on the Planning Code’s
Hazard Criterion and to provide a basis for design modifications to mitigate these impacts. Wind‐tunnel
tests were conducted at 24 test locations for two scenarios, the Phase I development, and the combined
Phase I and Phase II development in the Medical Center at Mission Bay EIR. Under the Phase I scenario,
two locations, the south side of 16th Street, at the intersection at Owens, and the southeast corner of
Mariposa and 3rd Streets, wind would exceed the wind hazard criterion set forth in Planning Code
Section 148. However, the total duration of these exceedances would be similar to but less than the
1 City and County of San Francisco, Final Mission Bay Subsequent EIR, Sept. 17, 1998, and University of California San Francisco LRDP Amendment #2- Hospital Replacement EIR, March 2005.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 17 ‐
duration of the existing wind hazards on the site, so the project would generally improve wind
conditions from those now existing and reduce the overall duration of hazard exceedances.
At the completion and full buildout of Phase II, two wind hazard exceedances that were identified under
Phase I would be eliminated. However, a new exceedance would be created at another location, at 3rd
and 16th Streets. Under the combined Phase I and Phase II scenario, the medical center would
substantially improve wind conditions by reducing the number of duration of previously occurring wind
hazard exceedances. The Phase II scenario would result in one remaining wind hazard exceedance at one
of the 24 pedestrian test point locations. As a result, the EIR concluded that continued actions under
UCSF Mitigation Measure 4.1‐7 and City Mitigation Measure D.7 (listed above) would be required to
eliminate this hazard through building design and no further mitigation measures were necessary.
As noted above, the Phase I parking structure has been modified and the height has increased to 105 feet
to the top‐of‐screen. Under Mitigation Measure D.7, because the structure would exceed 100 feet in
height, the revised structure would require a wind tunnel testing or technical review to determine the
potential wind conditions. An updated technical memorandum2 was prepared to evaluate potential
changes to the wind conditions due to the proposed design changes to the Phase I parking structure.
It should be noted that the 2008 wind tunnel test conducted for the UCSF Medical Center EIR included
the buildout, i.e. Phase II, however, without a defined design for the Phase II garage. The wind testing for
Phase II included the total building mass that would occupy that portion of the Campus, but made no
distinction between the allocations of building uses in the conceptual building mass of the Phase II
development. Therefore, the original proposed 600 space, 90‐foot‐tall parking structure was assumed to
be part of a larger conceptual building mass that would form the Phase II development.
The updated 2010 analysis considered whether the proposed modifications to the parking structure
would result in a hazardous wind condition. The mechanism in which buildings can adversely affect the
pedestrian wind environment is that buildings much taller than surrounding buildings intercept and
redirect winds that might otherwise flow overhead, bringing them down the vertical faces of the
buildings to the ground level, creating ground‐level wind.
An increase from 90 to 105 feet in height would not substantially rise above the height of the upwind
buildings in the Mission Bay South area. Thus, the updated analysis concluded that the resulting change
would not be substantial. The analysis also considered whether the screened (metal louvers), non‐solid
surface of the parking structure would gather and redirect winds to the ground level. It was determined
that although the screened façade would be taller, wind would not gather and be directed down the
vertical face of the garage to the ground level. As a result, the current building design would have a lesser
physical capability to gather and redirect winds down to the ground level than the building mass that
was modeled in the 2008 wind tunnel study. Therefore, the increase in height of the garage to 105 feet
would have no greater impact on the wind conditions than the project analyzed in the 2008 EIR and the
conclusions reached in the EIR would remain valid.
For the reasons noted, sunlight, shadow and wind impacts would be less than significant and will not be
further analyzed in the SEIR.
2 ESA, memo to Lori Yamauchi, Assistant Vice Chancellor UCSF Campus Planning, Technical Memorandum Potential Wind Conditions, UCSF Medical Center at Mission Bay, December 3, 2010.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 18 ‐
Issues
Additional
Project‐level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
2. AGRICULTURE AND FOREST RESOURCES –
Would the project:
a) Convert Prime Farmland, Unique Farmland, or
Farmland of Statewide Importance (Farmland), as
shown on the maps prepared pursuant to the
Farmland Mapping and Monitoring Program of the
CA Resources Agency, to non‐agricultural use?
□ ■
b) Conflict with existing zoning for agricultural use, or
a Williamson Act contract? □ ■
c) Conflict with existing zoning for, or cause rezoning
of, forest land (as defined in Public Resources Code
section 12220(g)), timberland (as defined by Public
Resources Code section 4526), or timberland zoned
Timberland Production (as defined by Government
Code section 51104(g))?
□ ■
d) Result in the loss of forest land or conversion of
forest land to non‐forest use? □ ■
e) Involve other changes in the existing environment
which, due to their location or nature, could result in
conversion of Farmland, to non‐agricultural use or
conversion of forest land to non‐forest use?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. The modified project would not
include any parking levels below grade. All other aspects of the Phase I and Phase II project that was
analyzed in the Medical Center at Mission Bay EIR would remain the same.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 19 ‐
Describe how the project is analyzed under this CEQA checklist topic:
2a), b) and e): The NOP/IS prepared for the Medical Center at Mission Bay concluded that
implementation of the project would not create impacts or result in a substantial adverse effect on
agricultural uses. The proposed project would not be constructed on Farmland or land otherwise in
agricultural use. The revisions to the proposed parking structure would not change the analysis or
conclusions reached in the NOP/IS prepared for the Medical Center at Mission Bay project. However,
since the publication of the EIR, the CEQA Guidelines was revised to include checklist questions 2c) and
2d) above. The site is located in a dense urban area, zoned for urban uses. Therefore, the Medical Center
at Mission Bay and the minor modifications to the proposed parking garage would not impact forest or
agricultural resources and no further environmental analysis for these checklist topics are required
pursuant to Section 15162 of the CEQA Guidelines.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 20 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
3. AIR QUALITY – Where available, the significance
criteria established by the applicable air quality
management or air pollution control district may be
relied upon to make the following determinations.
Would the project:
a) Conflict with or obstruct implementation of the
applicable air quality plan? □ ■
b) Violate any air quality standard or contribute
substantially to an existing or projected air quality
violation?
□ ■
c) Result in a cumulatively considerable net increase of
any criteria pollutant for which the project region is
non‐attainment under an applicable federal or state
ambient air quality standard (including releasing
emissions which exceed quantitative thresholds for
ozone precursors)?
□ ■
d) Expose sensitive receptors to substantial pollutant
concentrations? □ ■
e) Create objectionable odors affecting a substantial
number of people? □ ■
f) Exceed the applicable LRDP EIR standard of
significance by exposing receptors to toxic air
contaminant emissions that (1) result in a cancer risk
greater than 10 cancer cases per one million people
exposed in a lifetime; or (2) for acute or chronic effects,
result in concentrations of toxic air contaminant
emissions with a Hazard Index of 1.0 or greater
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic.
Discussion of Checklist Questions
Relevant elements of project:
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 21 ‐
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. The modified project would not
include any parking levels below grade.
As noted above, Phase II was also analyzed in the Medical Center at Mission Bay EIR which would
include a 261‐bed hospital and approximately 225 to 925 additional spaces in a parking structure. With
the completion of Phase II, the project would range from approximately 1,290 to 1,990 total parking
spaces. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would remain
the same. No revisions are currently being proposed for Phase II. However, subsequent project‐level
environment review would be required once specific Phase II project design is available.
Describe how project was analyzed in earlier environmental document:
3a‐d) and f): The potential construction and operational effects of the proposed medical center on air
quality was evaluated in the Medical Center at Mission Bay EIR. With the exception of construction
criteria pollutant and criteria pollutants due to the operation of the Phase II development, all other air
quality impacts were determined to be less than significant. The EIR concluded that implementation of
Mitigation Measure MCMB.2‐1, criteria pollutant construction impacts would be mitigated to less‐than‐
significant levels. The mitigation measure would require certain emission standards for UCSF
construction equipment. The EIR also determined that the operation of the medical facilities in Phase II
would generate criteria pollutant emissions that would contribute to regional air pollution and this
impact would be significant and unavoidable. In addition, prior to approval of the Phase II development,
UCSF would conduct additional CEQA review to consider any new recommendations and
methodologies for mitigating criteria pollutants available at the time of project approvals.
Greenhouse gas (GHG) emissions were also analyzed under in the Air Quality CEQA checklist topic in
the Medical Center at Mission Bay EIR. At the time of the EIR publication, no state or federal regulations
have been set for ambient air quality emission standards for greenhouse gas. The EIR quantified the
project’s emissions and included a GHG analysis, but used a significance standard that was consistent
with strategies to reduce GHG per AB32.3 The EIR concluded that the project would be consistent with
AB32 and impacts would be less than significant.
3e): The LRDP Amendment #2‐ Hospital Replacement EIR assessed the potential effects of the proposed
project to create objectionable odors. Odorous substances are regulated under BAAQMD Regulation 7
and is required as part of the hospital operations. The current medical center complies with the
regulations for odorous substances under BAAQMD Regulations and the future operation would
continue to meet the regulations. The LRDP Amendment #2 EIR and the NOP/IS for the Medical Center
determined the proposed project would not result in an adverse effect on odors and impacts would be
less than significant.
3 Global Warming Solutions Act of 2006, known as AB32, was passed by the Legislature and signed by Governor Schwarzenegger in 2006, which set the 2020 greenhouse gas emissions reduction goal into law.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 22 ‐
Describe how the minor project changes affect the earlier environmental analysis:
3a‐f): The revised parking structure would not result in new or substantially more significant air quality
impacts that were not previously examined in the Medical Center at Mission Bay EIR. The 26 additional
parking spaces in the parking garage would be offset by the decreased number of surface parking spaces.
The parking structure and associated surface parking lot would support the medical center that is
currently under construction and would not generate any additional new trips that was not previously
analyzed in the Medical Center at Mission Bay EIR. The parking structure would continue to be
developed as part of the Phase I project in the same timeframe that was analyzed in the EIR.
Implementation of Mitigation Measure MCMB.2‐1 from the Medical Center at Mission Bay EIR would
still be required. Similar to the conclusions reached in the EIR, Phase II of the project would generate
criteria pollutant emissions that would contribute to regional air pollution and this impact would be
significant and unavoidable. UCSF would implement all previously adopted measures and new
mitigation measures identified in the Medical Center at Mission Bay EIR, with additional CEQA review
at the time of project approval for Phase II to consider any new recommendations and methodologies for
mitigating criteria pollutants.
In June 2010, the BAAQMD adopted thresholds of significance for criteria air pollutants, GHGs, and
health risks from new sources. The recently adopted BAAQMD significance threshold for ROG, NOx,
and PM2.5 is 54lbs/day and 82lbs/day for PM10. An analysis for criteria air pollutants from new sources
based on the recently adopted BAAQMD thresholds of significance was conducted for Phase I.
With respect to the City of San Francisco’s fine‐particulate exposure standard for development proposals
located within 500 feet of a major roadway,4 the proposed project would incorporate filtration systems
into the general air supply systems of both the Phase I and Phase II projects. At this time, the proposed
261‐bed hospital in Phase II would be located within 500 feet of the I‐280 freeway, which could be at a
location where the potential for the PM2.5 concentration from local roadways to exceed 0.2 μg/m3. The
hospital plans to use high efficiency particulate filtration (such as HEPA or ULPA) within systems
serving bone marrow transfers, hematology/oncology treatment, radiation therapy, and pediatric
intensive care. Other air handling systems would include these filters as‐needed. Therefore, ambient
concentrations of fine particulates would not pose a substantial risk to patients, hospital workers or other
occupants of the hospital under construction in Phase I (which is beyond 500 feet) or the future hospital
in Phase II. However, as noted previously, subsequent project‐level environment review would be
required for the Phase II project once specific project design is available.
It can be assumed that the total criteria air pollutant emissions that were reported in the 2008 EIR would
remain the same under the current revised project since project revisions would not include any change
in overall use but slight change of location for the parking structure and a reduction of seven parking
spaces in Phase I. The “Proportional Emissions from the Revised Parking Structure in Phase 1” presented
below is the subset of emissions previous analyzed in the 2008 EIR. Based on the new adopted
significance criteria, the Phase I project would continue to be less than significant and the proportional
share of operational daily emissions for the proposed parking garage is listed in the table below:
4 As established by San Francisco Department of Public Health, the Potential Roadway Exposure Zones are defined as areas within the City and County of San Francisco that may exhibit high ambient PM2.5 concentrations due to their proximity to freeways and major roadways (i.e., “Local Roadway Traffic Sources”).
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 23 ‐
Table 3‐1: Project‐related Criteria Air Pollutant Emissions and CEQA Significance Standards
Emission Sources
Criteria Air Pollutant Emissions (lbs/day)
ROG NOx CO PM10 PM2.5
Total Phase I Project
(from 2008 MCMB EIR)
Mobile Sources
Area Sources
Stationary
Other1
Total
28.88
1.66
3.98
1.51
36.03
27.26
5.32
35.98
0.60
69.16
286.79
4.45
52.11
11.96
355.31
60.45
0.02
5.34
0.13
65.94
11.43
0.02
0.08
0.13
11.66
Proportional Emissions
from the Revised
Parking Structure in
Phase 1
Mobile Sources
Area Sources2
Stationary3
Other
Total
15.18
1.21
N/Ap
N/Ap
16.39
21.58
0.66
N/Ap
N/Ap
22.24
182.19
0.55
N/Ap
A/Ap
182.74
35.4
_
N/Ap
N/Ap
35.4
6.68
_
N/Ap
N/Ap
6.68
Prior BAAQMD
Guidelines (1999)
80 80 550
(screening)4
80 No
Threshold
BAAQMD Significance
Thresholds (June 2010)
54 54 See below5 82 54
Notes: ROG = reactive organic gases; NOx = oxides of nitrogen; CO = carbon monoxide; PM10 = particulate matter with an
aerodynamic resistance diameter of 10 micrometers or less; PM2.5 = fine particulate matter with an aerodynamic resistance diameter
of 2.5 micrometers or less, N/Ap = Not Applicable; ppm = parts per million
1 “Other Emissions” applies only to the operation of the hospital and would have no emission values associated with the proposed parking structure. 2 The proportional area emission from the revised parking structure is an amount that is below what is measureable. 3 Operation of the parking structure would not produce stationary source emissions, hence N/Ap. 4 The 1999 guidelines recommend this level as a threshold for conducting additional detailed analysis. 5 9.0 ppm (8-hour average), 20.0 ppm (1-hour average)
As shown in Table 3‐1, the proportional emission from the revised parking structure would be below the
prior 1999 BAAQMD Guidelines and the current 2010 BAAQMD significance thresholds for all criteria air
pollutants. It is BAAQMD policy that the adopted thresholds apply to projects for which a NOP is
published, or environmental analysis begins, on or after the applicable effective date.5 Therefore, while
the 2010 BAAQMD threshold for NOx was reduced from 80lbs/day to 54lbs/day, and the total NOx
emission for the total Phase I Project would be 69.16, this impact would not be significant and the
proportional emissions from the revised parking structure would be below the 54lbs/day significance
threshold. In regards to CO emissions, BAAQMD recommends analysis of CO emissions at a local, rather
than a regional, level. BAAQMD has established preliminary screening criteria to determine with fair
certainty that, if not violated, project‐generated, long‐term operational local mobile‐source emissions of
CO would not result in, or substantially contribute to, emissions concentrations that exceed the 1‐hour
ambient air quality standard of 20 ppm or the 8‐hour standard of 9 ppm, respectively.
Table 3‐2 below presents the thresholds of significance for operational‐related criteria air pollutant and
precursor emissions. These represent the levels at which a project‘s individual emissions of criteria air
pollutants or precursors would result in a cumulatively considerable contribution to the San Francisco
Bay Area Air Basin‘s existing air quality conditions. If daily average or annual emissions of operational‐
5 BAAQMD Adopted Air Quality CEQA Thresholds of Significance - June 2, 2010, available at: http://www.baaqmd.gov/~/media/Files/Planning%20and%20Research/CEQA/Adopted%20Thresholds%20Table_December%202010.ashx Accessed February 2011.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 24 ‐
related criteria air pollutants or precursors would exceed any applicable threshold of significance listed in
the table below, the proposed project would result in a cumulatively significant impact. As shown in
Table 3‐1, the revised parking structure would not exceed any applicable thresholds and would not have
a cumulatively considerable contribution to this impact.
Table 3‐2: Thresholds of Significance for Operational‐Related Criteria Air Pollutants and Precursors
Pollutant/Precursor Maximum Annual Emissions
(tpy)
Average Daily Emissions
(lbs/day)
ROG 10 54
NOX 10 54
PM10 15 82
PM2.5 10 54 Notes: tpy = tons per year; lbs/day = pounds per day; ROG = reactive organic gases; NOX = oxides of nitrogen; PM10 = respirable
particulate matter with an aerodynamic resistance diameter of 10 micrometers or less PM2.5 = fine particulate matter with an
aerodynamic resistance diameter of 2.5 micrometers or less.
Criteria air pollutants are monitored at several monitoring stations within the San Francisco Bay Area Air
Basin. The monitoring station nearest the project site is at 10 Arkansas Street in San Francisco. In general,
the ambient air‐quality measurements from this station are representative of the air quality in the vicinity
of the project site. During the last three years, the station did not register any days the state CO standards
were exceeded.6
The modifications to the proposed project would not cause significant air quality impacts and no further
environmental analysis for these checklist topics are required. Appendix G of the CEQA Guidelines was
amended and adopted in December 2009 which includes updated significance standard for evaluating
GHG emissions. Additional GHG discussion and analysis due to project revisions and changes to the
CEQA Guidelines will be presented in the Greenhouse Gas Emissions chapter in the SEIR.
6 California Air Resources Board (ARB), 2011, Air Quality Data Statistics, Available at: www.arb.ca.gov/adam/welcome.html, Accessed: January 2011.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 25 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
4. BIOLOGICAL RESOURCES ‐‐ Would the project:
a) Have a substantial adverse effect, either directly or
through habitat modifications, on any species identified
as a candidate, sensitive, or special status species in
local or regional plans, policies, or regulations, or by
the California Department of Fish and Game or U.S.
Fish and Wildlife Service?
□ ■
b) Have a substantial adverse effect on any riparian
habitat or other sensitive natural community identified
in local or regional plans, policies, regulations or by the
California Department of Fish and Game or US Fish
and Wildlife Service?
□ ■
c) Have a substantial adverse effect on federally
protected wetlands as defined by Section 404 of the
Clean Water Act (including, but not limited to, marsh,
vernal pool, coastal, etc.) through direct removal,
filling, hydrological interruption, or other means?
□ ■
d) Interfere substantially with the movement of any
native resident or migratory fish or wildlife species or
with established native resident or migratory wildlife
corridors, or impede the use of native wildlife nursery
sites?
□ ■
e) Conflict with any applicable policies protecting
biological resources? □ ■
f) Conflict with the provisions of an adopted Habitat
Conservation Plan, Natural Community Conservation
Plan, or other applicable habitat conservation plan?
□ ■
g) Exceed the applicable LRDP EIR standard of
significance by damaging or removing heritage or
landmark trees or native oak trees of a diameter
specified in a local ordinance?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. In
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 26 ‐
addition, the significance standard related to local tree ordinances is used as a basis to evaluate potential
heritage or landmark trees at UCSF campus sites.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. All other aspects of the Phase I and
Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same.
Describe how project is analyzed under this CEQA checklist topic:
The NOP/IS prepared for the Medical Center at Mission Bay concluded that the development of the
proposed project would not result in a significant impact on riparian habitats, sensitive or special status
species, sensitive natural communities, protected wetlands, or movement or migration of any fish or
wildlife species. The proposed project would also not conflict with any applicable policy or conservation
plans. Therefore, the NOP/IS concluded that the proposed project would not create any substantial
adverse effect on biological resources. The modifications to the proposed project would not affect the
prior impact analyses or conclusions reached in the Medical Center at Mission Bay EIR related to
biological resources. Thus, impacts to biological resources would be less than significant and will not be
further analyzed in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 27 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
5. CULTURAL RESOURCES ‐‐ Would the project:
a) Cause a substantial adverse change in the significance
of a historical resource as defined in Section 15064.5? □ ■
b) Cause a substantial adverse change in the significance
of an archaeological resource pursuant to Section
15064.5?
□ ■
c) Directly or indirectly destroy a unique paleontological
resource or site or unique geologic feature? □ ■
d) Disturb any human remains, including those
interred outside of formal cemeteries? □ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
Four structures were on the project site along the eastern boundary, which have since been demolished to
accommodate the construction of the Phase I Medical Center at Mission Bay, which is currently
underway. A 600‐space parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in
the EIR at the southwest portion of the site as part of Phase I. The modified project would reduce a total
of seven parking spaces in Phase I and shift the location of the parking structure to the north. All other
aspects of the Phase I and Phase II project that was analyzed in the EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The LRDP Amendment #2‐ Hospital Replacement EIR assessed the proposed Mission Bay South project
site for potential historical resources and concluded the demolition of the structures would have a less‐
than‐significant impact on historic resource. The NOP/IS for the Medical Center at Mission Bay project
concluded that implementation of Mitigation Measure 4.3‐1 from the LRDP Amendment #2 EIR would be
required. The mitigation measure would require that in the event that archaeological resource or human
remains was encountered, construction work would halt and a qualified archaeologist or paleontologist
would be consulted to determine the significance and the appropriate next steps. The modifications to the
proposed project would not affect the prior impact analyses or conclusions reached related to cultural
resources. Thus, these checklist topics will not be analyzed further in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 28 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
6. GEOLOGY AND SOILS ‐‐ Would the project:
a) Expose people or structures to potential substantial
adverse effects, including the risk of loss, injury, or
death involving:
i) Rupture of a known earthquake fault, as
delineated on the most recent Alquist‐Priolo
Earthquake Fault Zoning Map issued by the State
Geologist for the area or based on other substantial
evidence of a known fault? Refer to Division of
Mines and Geology Special Publication 42.
□ ■
ii) Strong seismic ground shaking? □ ■
iii) Seismic‐related ground failure, including
liquefaction? □ ■
iv) Landslides? □ ■
b) Result in substantial soil erosion or the loss of
topsoil? □ ■
c) Be located on a geologic unit or soil that is unstable,
or that would become unstable as a result of the project,
and potentially result in on‐ or off‐site landslide, lateral
spreading, subsidence, liquefaction or collapse?
□ ■
d) Be located on expansive soil, as defined in Table 18‐
1‐B of the Uniform Building Code (1994), creating
substantial risks to life or property?
□ ■
e) Have soils incapable of adequately supporting the
use of septic tanks or alternative waste water disposal
systems where sewers are not available for the disposal
of waste water?
□ ■
f) Exceed the applicable LRDP EIR standard of
significance by exposing people to structural hazards in □ ■
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 29 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
an existing building rated Poor, or Very Poor, under the
University’s seismic performance rating system, or
substantial nonstructural hazards?
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of parking structure to the north. The modified project would not include
any parking levels below grade. All other aspects of the Phase I and Phase II project that was analyzed in
the Medical Center at Mission Bay EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
Based on information from prior geological surveys, the NOP/IS prepared for the Medical Center at
Mission Bay concluded the impacts on soil erosion would be less than significant since the project would
be required to follow building code standards for drainage and earthwork. The LRDP Amendment #2‐
Hospital Replacement EIR concluded that exposure of people and property to liquefaction and
earthquake‐induced settlement at Mission Bay would be significant before mitigation.
The NOP/IS prepared for the Medical Center at Mission Bay concluded that implementation of Mitigation
Measure 4.4‐4 from the LRDP Amendment #2 EIR would be required. The mitigation measure would
require a site‐specific, design‐level geotechnical investigation be completed on the project design and
these geotechnical recommendations be incorporated into the final design of the project. Therefore, the
proposed project would not create any new impacts not previously considered or adversely affected by
geological seismic impacts that cannot be mitigated through implementation of LRDP Amendment #2
EIR Mitigation Measure 4.4‐4. The LRDP Amendment #2 EIR also concluded that the proposed
construction of new buildings for the medical center to meet current seismic codes and University policy
would future reduce potential seismic hazards.
The revisions to the proposed project would not affect the prior impact analyses or conclusions reached
related to geology and soils that were not previously examined in the Medical Center at Mission Bay EIR
or LRDP Amendment #2‐ Hospital Replacement EIR. Therefore, impacts regarding geology and soils
would be less than significant and will not be analyzed further in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 30 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
7. GREENHOUSE GAS EMISSIONS – Would the
project:
a) Generate greenhouse gas emissions, either directly or
indirectly, that may have a significant impact on the
environment?
■ □
b) Conflict with an applicable plan, policy or regulation
adopted for the purpose of reducing the emissions of
greenhouse gases?
■ □
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. The modified project would not
include any parking levels below grade.
As noted previously, Phase II was also analyzed in the Medical Center at Mission Bay EIR which would
include a 261‐bed hospital and approximately 225 to 925 additional spaces in a parking structure. With
the completion of Phase II, the project would range from approximately 1,290 to 1,990 total parking
spaces. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would remain
the same. No revisions are currently being proposed for Phase II. However, subsequent project‐level
environment review would be required once specific Phase II project design is available.
Describe how project was analyzed in earlier environmental document:
Greenhouse Gas was discussed as part of the Air Quality CEQA checklist topic in the Medical Center at
Mission Bay EIR. At the time of publication, no state or federal regulations had been set for ambient air
quality emission standards for greenhouse gas. The California Air Resources Board (CARB) approved 44
greenhouse gas reduction strategies under the California Global Warming Solutions Act of 2006 (AB 32)
and adopted mandatory reporting regulations requiring annual reporting from sources that generate
more than 25,000 metric tons of carbon dioxide each year. However, at the time of the Medical Center at
Mission Bay EIR, no guidance from CARB, Bay Area Air Quality Management District (BAAQMD), State
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 31 ‐
Clearinghouse or other resource agency on the relationship between AB32 and CEQA, and how GHG
emissions would be evaluated in an EIR had been developed.
At the time of the EIR, the University of California was developing a long‐term strategy to voluntarily
meet the State of California’s AB 32 goals to reduce GHG emissions to 1990 levels by 2020. Further, the
University was developing clean energy standards with the goal of reducing GHG emissions to 2000
levels by 2014 and to provide an action plan to become climate neutral. Each UC campus was to form a
Climate Change Working Group to monitor progress towards reaching the stated goals for GHG
reduction. Consistent with the UC’s sustainable policy, UCSF prepared a GHG inventory using the
California Climate Action Registry protocol followed by the development of a Climate Action Plan, and
by that action, UCSF is making reasonable progress on GHG emissions reduction.
The Medical Center at Mission Bay EIR quantified the project’s emissions and included a GHG analysis,
but used a significance standard that was consistent with strategies to reduce GHG per AB32. The EIR
concluded that the proposed project would be consistent with AB32 and would not conflict with the state
goals; therefore, impacts would be less than significant.
Describe how the minor project changes affect the earlier environmental analysis:
Since the certification of the EIR, the CEQA Guidelines was revised to include checklist questions 7a) and
b) above. In addition, in June 2010, the BAAQMD adopted new significance standards for criteria air
pollutants, GHGs, and health risks from new sources and an analysis methodology for the evaluation of
GHG emissions in CEQA documents. In general, parking structures do not by themselves generate
vehicle trips, rather they support the trips generated by nearby land use. As such, the proposed garage
and the associated surface parking lot would not generate vehicle trips and instead would accommodate
vehicles generated by the hospital, outpatient building, and other support uses of the Medical Center at
Mission Bay. Nonetheless, for a conservative analysis, the GHG emissions produced by vehicles that
would travel to the proposed garage will be analyzed in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 32 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
8. HAZARDS AND HAZARDOUS MATERIALS –
Would the project:
a) Create a significant hazard to the public or the
environment through the routine transport, use, or
disposal of hazardous materials?
□ ■
b) Create a significant hazard to the public or the
environment through reasonably foreseeable upset and
accident conditions involving the release of hazardous
materials into the environment?
□ ■
c) Emit hazardous emissions or handle hazardous or
acutely hazardous materials, substances, or waste
within one‐quarter mile of an existing or proposed
school?
□ ■
d) Be located on a site which is included on a list of
hazardous materials sites compiled pursuant to
Government Code Section 65962.5 and, as a result,
would it create a significant hazard to the public or the
environment?
□ ■
e) For a project located within an airport land use plan
or, where such a plan has not been adopted, within two
miles of a public airport or public use airport, would
the project result in a safety hazard for people residing
or working in the project area?
□ ■
f) For a project within the vicinity of a private airstrip,
would the project result in a safety hazard for people
residing or working in the project area?
□ ■
g) Impair implementation of or physically interfere
with an adopted emergency response plan or
emergency evacuation plan?
□ ■
h) Expose people or structures to a significant risk of
loss, injury or death involving wildland fires, including
where wildlands are adjacent to urbanized areas or
□ ■
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 33 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
where residences are intermixed with wildlands?
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the Medical Center at
Mission Bay EIR at the southwest portion of the site as part of Phase I. The modified project would
reduce a total of seven parking spaces in Phase I and shift the location of the parking structure to the
north. The modified project would not include any parking levels below grade. All other aspects of the
Phase I and Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain
the same.
Describe how the project is analyzed under this CEQA checklist topic:
The LRDP Amendment #2‐ Hospital Replacement EIR assessed the proposed Mission Bay South project
site for potential impacts of hazardous building material during demolition or renovation of existing
structures; use of hazardous materials in new construction; hazardous material transportation, storage
and disposal impacts during project operations; and exposure of the public to native contaminated soil or
groundwater. The EIR concluded that these impacts were less than significant and no mitigation
measures were recommended. However, the LRDP Amendment #2 EIR found that the generation of
hazardous waste could have a significant impact by contributing to additional loads on hazardous waste
management facilities outside California. The NOP/IS for the Medical Center at Mission Bay concluded
that implementation of Mitigation Measure 4.5‐4 from the LRDP Amendment #2 EIR would mitigate this
impact to less than significant.
The modifications to the proposed project would not affect the prior impact analyses or conclusions
reached related to hazards and hazardous materials that were previously examined in the Medical Center
at Mission Bay EIR or LRDP Amendment #2‐ Hospital Replacement EIR. Impacts from hazards and
hazardous materials would be less than significant and will not be analyzed further in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 34 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
9. HYDROLOGY AND WATER QUALITY ‐‐ Would
the project:
a) Violate any water quality standards or waste
discharge requirements? □ ■
b) Substantially deplete groundwater supplies or
interfere substantially with groundwater recharge such
that there would be a net deficit in aquifer volume or a
lowering of the local groundwater table level (e.g., the
production rate of pre‐existing nearby wells would
drop to a level which would not support existing land
uses or planned uses for which permits have been
granted)?
□ ■
c) Substantially alter the existing drainage pattern of
the site or area, including through the alteration of the
course of a stream or river, in a manner which would
result in substantial erosion or siltation on‐ or off‐site?
□ ■
d) Substantially alter the existing drainage pattern of
the site or area, including through the alteration of the
course of a stream or river, or substantially increase the
rate or amount of surface runoff in a manner which
would result in flooding on‐ or off‐site?
□ ■
e) Create or contribute runoff water which would
exceed the capacity of existing or planned stormwater
drainage systems or provide substantial additional
sources of polluted runoff?
□ ■
f) Otherwise substantially degrade water quality? □ ■
g) Place housing within a 100‐year flood hazard area as
mapped on a federal Flood Hazard Boundary or Flood
Insurance Rate Map or other flood hazard delineation
map?
□ ■
h) Place within a 100‐year flood hazard area structures
which would impede or redirect flood flows? □ ■
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 35 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
i) Expose people or structures to a significant risk of
loss, injury or death involving flooding, including
flooding as a result of the failure of a levee or dam?
□ ■
j) Inundation by seiche, tsunami, or mudflow? □ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the Medical Center at
Mission Bay EIR at the southwest portion of the site as part of Phase I. The modified project would
reduce a total of seven parking spaces in Phase I and shift the location of the parking structure to the
north. The modified project would not include any parking levels below grade. All other aspects of the
Phase I and Phase II project that was analyzed in the EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The project site is located in a dense urban area in the vicinity of China Basin Channel and the San
Francisco Bay. Groundwater is not used at the site and the project would not alter or interfere with
groundwater supplies or recharge or alter the course of a stream or river. The site is not located within a
100‐year flood hazard area, or near a levee or dam. Nor is the site within an area with the potential to be
inundated by seiche, tsunami, or mudflow. The modifications to the proposed project would not affect
the prior impact analyses or conclusions reached related to hydrology and water quality that were not
previously examined in the Medical Center at Mission Bay EIR or LRDP Amendment #2‐ Hospital
Replacement EIR. Therefore, no further environmental analysis of hydrology and water quality is
required and this topic will not be analyzed in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 36 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
10. LAND USE AND PLANNING ‐‐ Would the
project:
a) Physically divide an established community? □ ■
b) Conflict with any applicable land use plan, policy, or
regulation of an agency with jurisdiction over the
project (including, but not limited to the LRDP, general
plan, specific plan, local coastal program, or zoning
ordinance) adopted for the purpose of avoiding or
mitigating an environmental effect?
□ ■
c) Conflict with any applicable habitat conservation
plan or natural community conservation plan? □ ■
d) Exceed an applicable LRDP EIR standard of
significance by being substantially incompatible with
existing land uses, or by substantially conflicting use,
density, height and bulk restrictions of local zoning,
although UCSF is exempt from such restrictions?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the Medical Center at
Mission Bay EIR at the southwest portion of the site as part of Phase I. The modified project would
increase the height of the parking structure to 105‐feet‐tall, reduce the number of parking spaces in Phase
I by seven spaces, and shift the location of the parking structure to the north, closer towards 16th Street,
along the future Owens Street extension. Due to the shift in the garage location, the intersection at Owens
and Parking Structure Road would be constructed as part of Phase I instead of Phase II, as analyzed in
the original EIR analysis. Therefore, under the revised project, three access points from Owens Street
would be created as part of Phase I, the North and South Connector Roads and the new intersection at
Parking Structure Road.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 37 ‐
As noted previously, Phase II was also analyzed in the Medical Center at Mission Bay EIR which would
include a 261‐bed hospital and approximately 225 to 925 additional spaces in a parking structure. With
the completion of Phase II, the project would range from approximately 1,290 to 1,990 total parking
spaces. All other aspects of the Phase I and Phase II project that was analyzed in the EIR would remain
the same. No revisions are currently being proposed for Phase II. However, subsequent project‐level
environment review would be required once specific Phase II project design is available.
Describe how the project is analyzed under this CEQA checklist topic:
The project site is within an urban developed area and no habitat conservation plans or natural
community conservation plans apply to the Mission Bay area. The Medical Center at Mission Bay EIR
concluded that the implementation of the Medical Center at Mission Bay would not result in new impacts
not previously considered and would not have a substantial adverse effect. Therefore, potential land use
impacts would be less than significant.
As noted previously, the 2008 UCSF Medical Center at Mission Bay EIR analyzed two major phases,
Phase I and Phase II. Phase I would include a 289‐bed hospital, two outpatient facilities consisting of
336,500 gross square feet (GSF), a 36,000 GSF Energy Center, and a 600‐space parking structure with 475
surface parking spaces, totaling 1,075 parking spaces. Groundbreaking for Phase I began in October 2010.
The proposed project modifications would not change the uses proposed and analyzed in the 2008 EIR.
While the number of parking spaces in the parking structure (from 600 to 626) would increase, the
number of surface spaces would decrease (from 475 to approximately 442). Therefore, the overall number
of parking spaces would decrease by about seven spaces under Phase I. A decrease of seven parking
spaces would not change the prior impact discussion. The proposed parking facility would support the
medical center complex that is currently under construction and would be consistent with the existing
uses around the project site and UCSF’s LRDP, as amended.
The location of the Phase I parking structure has shifted further to the north, where it was previously
planned for surface parking in Phase I. However, it should be noted that under buildout of Phase II, the
entire site would be planned for a parking structure accommodating approximately 1,290 to 1,990
parking spaces. Therefore, it would be consistent with the use designated for this portion of Blocks 38 and
39 and consistent with the prior environmental analysis. Access and circulation to the site and the
proposed parking structure would remain the same, with the future Owen Street extension to
accommodate the majority of the vehicular traffic.
The project site is within the Mission Bay South Plan area where the allowable base building height is 90
feet with a provision for some building parcels to reach a maximum height of 160 feet. In addition, the
SFRA MOU established height limit standards that allowed a base height of 90 feet but may extend up to
105 feet for up to 75% of the medical center structures. The proposed height increase from 90 to 105 feet
would be consistent with the surrounding height and bulk restrictions and would be consistent with
SFRA MOU height standards.
Based on this analysis, the modified project would not result in new significant environmental impacts
related to land use that were not previously examined in the Medical Center at Mission Bay EIR.
Therefore, the proposed project would not have a significant land use impact and land use will not be
analyzed further in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 38 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
11. MINERAL RESOURCES ‐‐ Would the project:
a) Result in the loss of availability of a known mineral
resource that would be of value to the region and the
residents of the state?
□ ■
b) Result in the loss of availability of a locally‐
important mineral resource recovery site delineated on
a local general plan, specific plan or other land use
plan?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the Medical Center at
Mission Bay EIR at the southwest portion of the site as part of Phase I. The modified project would
reduce a total of seven parking spaces in Phase I and shift the location of the parking structure to the
north. The modified project would not require additional excavation. All other aspects of the Phase I and
Phase II project that was analyzed in the EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The proposed project site is not in an area of known mineral resources and would not otherwise conflict
with mineral resource recovery. The NOP/IS for the LRDP Amendment #2 and the NOP/IS for the
Medical Center at Mission Bay determined that no further study of mineral resources would be
necessary. Modifications to the proposed project would not result in new or substantially more severe
significant environmental impacts related to mineral resources that were not previously examined in the
Medical Center at Mission Bay EIR or LRDP Amendment #2‐ Hospital Replacement EIR. Therefore, these
checklist topics will not be analyzed further in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 39 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
12. NOISE ‐‐ Would the project:
a) Exposure of persons to or generation of noise levels
in excess of standards established in any applicable
plan or noise ordinance, or applicable standards of
other agencies?
□ ■
b) Exposure of persons to or generation of excessive
groundborne vibration or groundborne noise levels? □ ■
c) A substantial permanent increase in ambient noise
levels in the project vicinity above levels existing
without the project?
□ ■
d) A substantial temporary or periodic increase in
ambient noise levels in the project vicinity above levels
existing without the project (including construction)?
□ ■
e) For a project located within an airport land use plan
or, where such a plan has not been adopted, within two
miles of a public airport or public use airport, would
the project expose people residing or working in the
project area to excessive noise levels?
□ ■
f) For a project within the vicinity of a private airstrip,
would the project expose people residing or working in
the project area to excessive noise levels?
□ ■
g) Exceed an applicable LRDP EIR standard of
significance by contributing to an increase in average
daily noise levels (Ldn) of 3 dB(A) or more at property
lines, if ambient noise levels in areas adjacent to
proposed development already exceed local noise
levels set forth in local general plans or ordinances for
such areas based on their use?
□ ■
Standards of Significance
The impact questions above constitute the significance standards. Regarding question g), a project could
have a significant noise impact if it contributes to an increase in already exceeded noise ordinance levels.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 40 ‐
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the Medical Center at
Mission Bay EIR at the southwest portion of the site as part of Phase I. The modified project would
reduce a total of seven parking spaces in Phase I and shift the location of the parking structure to the
north. All other aspects of the Phase I and Phase II project that was analyzed in the Medical Center at
Mission Bay EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
12a‐d) and g): The Medical Center at Mission Bay EIR concluded that demolition and construction
activities associated with the proposed project would temporarily elevate noise levels to significant levels
in and around the project site, particularly near sensitive receptors. The closest sensitive receptors are
located in the Mission Bay research campus site, north of the project site, which includes a child care
center on Block 18 and the 430 residential units on Block 20. There is also the potential proposal for a
child care center on Block 23 and a site for a possible future SFUD public school on Block 14. Additional
residential uses are located south of the medical center site, along Mariposa and Pennsylvania Streets.
The revised parking structure would not result in new or substantially more significant demolition or
construction noise impacts that were not previously examined in the Medical Center at Mission Bay EIR
or LRDP Amendment #2‐ Hospital Replacement EIR. The parking structure would continue to be
developed as part of the Phase I project in the same timeframe that was analyzed in the EIR.
Implementation of Mitigation Measure MCMB.5‐1 from the Medical Center at Mission Bay EIR would
require construction contractors to minimize construction noise impacts by using proper equipment and
limiting construction hours, however, because the mitigation measure would not guarantee that
construction noise impacts would be reduced to less‐than‐significant levels, the EIR concluded that the
project would have a temporary but significant and unavoidable noise impact. Similar to the conclusions
reached in the EIR, the revised project would continue to have a temporary but significant and
unavoidable noise impact during project construction and demolition.
12e and f): The project site is more than two miles from an airport or private airstrip. The Medical Center
at Mission Bay EIR concluded that operation of the helicopter landing site (“helipad”) proposed as part of
the project would increase noise levels at nearby sensitive receptors. Mitigation Measure MCMB.5‐4 was
included in the EIR, which requires UCSF to develop a Residential Sound Reduction Program (RSRP)
prior to helicopter operation and to include any additional mitigation measures developed as part of the
community process for the RSRP. Subsequent to the publication of the Medical Center at Mission Bay
EIR, a Supplemental EIR was prepared in April of 2009 to address the RSRP mitigation measure. The
Supplemental EIR determined that implementation of Mitigation Measure MCMB.5‐4 from the Medical
Center at Mission Bay EIR, in conjunction with the RSRP Mitigation Measure MCMB.5‐4a from the
Supplemental EIR, would in general mitigate noise impacts on sensitive receptors from helicopter
operations to less‐than‐significant levels. However, because it may not be feasible for all property owners
to participate in the RSRP, this impact was determined to be significant and unavoidable. The revised
project would not affect the prior impact analysis. Therefore, noise effects will not be analyzed further in
the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 41 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
13. POPULATION AND HOUSING ‐‐Would the project:
a) Induce substantial population growth in an area,
either directly (for example, by proposing new homes
and businesses) or indirectly (for example, through
extension of roads or other infrastructure)?
□ ■
b) Displace substantial numbers of existing housing,
necessitating the construction of replacement housing
elsewhere?
□ ■
c) Displace substantial numbers of people, necessitating
the construction of replacement housing elsewhere? □ ■
d) Exceed an applicable LRDP or Program EIR
standard of significance by creating a demand for
housing outside the market area where the facilities or
site are located?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. Population
and housing changes, in and of themselves, are not normally considered significant impacts (substantial,
adverse impacts on the physical environment). However, CEQA does allow inclusion of secondary effects
as indicators and influences on other impacts, such as traffic, public services, and air quality.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. All other aspects of the Phase I and
Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The proposed project would not displace existing housing or residents. The LRDP Amendment #2‐
Hospital Replacement EIR assessed the proposed Mission Bay South project site for potential impacts
under these checklist topics and determined that these impacts were less than significant. The NOP/IS
prepared for the Medical Center at Mission Bay concluded that the implementation of the Medical Center
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 42 ‐
at Mission Bay would not create a new impact not previously considered and would not have a
substantial adverse effect.
The revised parking structure would not result in new or substantially more population and housing
impacts that were not previously examined in the Medical Center at Mission Bay EIR or the LRDP
Amendment #2‐ Hospital Replacement EIR. While the number of parking spaces in the parking structure
would increase from 600 to 626, the number of surface spaces would decrease from 475 to approximately
442. Therefore, the overall number of parking spaces would decrease by about seven spaces under Phase
I. The proposed Phase I parking structure and associated surface parking lot would accommodate the
trips generated from the medical center complex that is currently under construction and would not
create new population or housing demand. Therefore, impacts associated with population and housing
would be less than significant and this topic will not be analyzed further in the SEIR
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 43 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
14. PUBLIC SERVICES
Would the project result in substantial adverse physical
impacts associated with the provision of new or
physically altered governmental facilities, need for new
or physically altered governmental facilities, the
construction of which could cause significant
environmental impacts, in order to maintain acceptable
service ratios, response times or other performance
objectives for any of the public services:
a) Fire protection? □ ■
b) Police protection? □ ■
c) Schools? □ ■
d) Parks? □ ■
e) Other public facilities? □ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. All other aspects of the Phase I and
Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The LRDP Amendment #2‐ Hospital Replacement EIR assessed the proposed Mission Bay South project
site for potential impacts under these checklist topics and concluded that the project’s demand for police
services, fire services, emergency medical service, and local school enrollments would be less than
significant. As noted in CEQA topic 15) Recreation, the impacts of the proposed project on parks would
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 44 ‐
also be less than significant. The NOP/IS prepared for the Medical Center at Mission Bay concluded that
the implementation of the Medical Center at Mission Bay would not result in new impacts not previously
considered and potential impacts on public services would be less than significant.
The modifications to the proposed project would not result in an increase in public service demand that
were not previously examined in the Medical Center at Mission Bay EIR or the LRDP Amendment #2‐
Hospital Replacement EIR. While the number of parking spaces in the parking structure would increase
from 600 to 626, the number of surface spaces would decrease from 475 to approximately 442. Therefore,
the overall Phase I parking supply would reduce by approximately seven spaces. The proposed parking
spaces would continue to accommodate the visitors and employees generated by the medical center
complex that is currently under construction and would not create new population that would increase
demand on public services. Therefore, no further environmental analysis of public service is required and
this topic will not be analyzed further in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 45 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
15. RECREATION ‐‐
a) Would the project increase the use of existing
neighborhood and regional parks or other recreational
facilities such that substantial physical deterioration of
the facility would occur or be accelerated?
□ ■
b) Does the project include recreational facilities or
require the construction or expansion of recreational
facilities, which might have an adverse physical effect
on the environment?
□ ■
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic. There are
no additionally applicable LRDP significance standards.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. All other aspects of the Phase I and
Phase II project that was analyzed in the Medical Center at Mission Bay EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
This checklist topic was focused out in the NOP/IS that was prepared for the LRDP Amendment #2‐
Hospital Replacement EIR. The NOP/IS prepared for the Medical Center at Mission Bay concluded that
the implementation of the medical complex would not increase the use of existing neighborhood parks or
other recreational facilities in the area or result in the construction or expansion of existing recreational
facilities. The revisions to the proposed parking structure would not change the analysis or conclusions
reached in the NOP/IS prepared for the Medical Center at Mission Bay project. Therefore, potential
impacts on recreational resources would be less than significant and no further environmental analysis is
required in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 46 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
16. TRANSPORTATION/TRAFFIC ‐‐
Would the project:
a) Conflict with an applicable plan, ordinance or policy
establishing measures of effectiveness for the
performance of the circulation system, taking into
account all modes of transportation including mass
transit and non‐motorized travel and relevant
components of the circulation system, including but
not limited to intersections, streets, highways and
freeways, pedestrian and bicycle paths, and mass
transit?
■ □
b) Conflict with an applicable congestion management
program, including, but not limited to level of service
standards and travel demand measures, or other
standards established by the county congestion
management agency for designated roads or
highways?
■ □
c) Result in a change in air traffic patterns, including
either an increase in traffic levels or a change in
location that results in substantial safety risks?
■ □
d) Substantially increase hazards due to a design
feature (e.g., sharp curves or dangerous intersections)
or incompatible uses (e.g., farm equipment)?
■ □
e) Result in inadequate emergency access? ■ □
f) Result in inadequate parking capacity? ■ □
g) Conflict with adopted policies, plans, or programs
regarding public transit, bicycle, or pedestrian
facilities, or otherwise decrease the performance or
safety of such facilities?
■ □
h) Exceed the applicable LRDP or Program EIR
standard of significance by causing substantial conflict
among auto, bicyclists, pedestrians, and transit
■ □
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 47 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
vehicles?
i) Exceed the applicable LRDP standard of significance
by generating transit demand that transit systems or
projected transit service would not be able to
accommodate?
■ □
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic.
Discussion of Checklist Questions:
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. The Phase I
development includes a 289‐bed hospital and approximately 336,500 gross square feet of outpatient care
uses. A 600‐space parking structure at 90‐feet‐tall was analyzed in the EIR at the southwest portion of the
site as part of Phase I. Surface parking for approximately 475 vehicles would be provided on the
remainder of Blocks 38 and 39. Therefore, at the completion of Phase I, approximately 1,075 parking
spaces for staff, patients, and visitors would be provided on the Blocks 38 and 39 between 4th Street and
the proposed Owens Street extension.
Owens Street is designed to handle the majority of vehicular traffic. Therefore, the parking facilities are
located on the west side of the site. Fourth Street is envisioned as a low‐traffic street, with access to the
project site for drop‐offs and pick‐ups, access to the garage and deliveries, but limited through travel
between 16th and Mariposa Streets. Access to the Phase I parking structure and associated surface
parking spaces would be from Owens or 4th Streets via the North and South Connector Roads. The access
to the Phase I parking structure and associated surface parking would be located at the South Connector
Road with another ingress/egress along Owens Street (now the intersection of Owens Street and the
Parking Structure Road, located between the North and South Connector Roads. A secondary
ingress/egress into the parking structure is from the surface parking lot to the east.
Phase II would be located west of 4th Street and would include a 261‐bed hospital and approximately 225
to 925 parking spaces. Upon project completion and full buildout of Phase II, the onsite parking supply
for the medical center would range from 1,300 to 2,000 spaces. The 261‐bed hospital in Phase II would be
L‐shaped, running along 16th and 4th Streets on the eastern portion of Blocks 38 and 39 with the future
parking structure west of the hospital, along Owens Street. The Phase II parking structure would occupy
the western part of the site with three access points. Under Phase II, ingress/egress into the garage would
be provided from the new Parking Structure Road at Owens and North and South Connector Roads.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 48 ‐
The modified project would include a 626‐space parking structure at 105 feet tall as part of the Phase I
project. It would be located further north, closer towards 16th Street, along the future Owen Street
extension. Compared to the previously proposed project, which would include 475 surface parking
spaces, the revised project would include approximately 429 surface parking spaces on the remainder of
Blocks 38 and 39. Thirteen spaces would be provided on the east lot, at the south end of the proposed
hospital across the future 4th Street extension. Therefore, approximately 442 surface parking spaces
would be provided in Phase I. The total number of parking spaces provided in Phase I would decrease
by approximately seven spaces and would total approximately 1,068 spaces. With the decrease of seven
parking spaces in Phase I, at full buildout of Phase II, the onsite parking supply could also decrease by
approximately seven spaces to approximately 1,290 to 1,990 spaces.
In the revised project, the location of the Phase I parking structure would be located further north, closer
towards 16th Street, just south of North Connector Road, along the future Owen Street extension. Similar
to the original proposed project, access to the parking structure and associated surface parking spaces
would be from Owens or 4th Streets via the North and South Connector Roads, and from the Owens
driveway at what is now proposed to be Parking Structure Road. However, there would only be one
ingress/egress to the revised parking garage from the interior connector road. Aside from this change, no
other revisions are currently proposed. Subsequent project‐level environment review would be required
once specific project design is available for Phase II.
Describe how project was analyzed in earlier environmental document:
An expanded Transportation Study was prepared for the Medical Center at Mission Bay EIR.7 The
Transportation Study evaluated both the Phase I and future buildout of the Phase II development. In
addition, the traffic study evaluated two potential alternatives for the operation of 4th Street through the
Medical Center site. Both alternatives would convert the proposed 4th Street right‐of‐way to University of
California property.
Based on the analysis contained with the Transportation Study, traffic impacts resulting from Phase I of
the Medical Center at Mission Bay would be less than significant, as all study intersections would
continue to operate at level‐of‐service D or better.
At the completion Phase II, the Medical Center at Mission Bay EIR concluded that that the operation of
the full buildout, would increase traffic at intersections on adjacent roadways. The significant impact to
the southbound approach of Owens Street at 16th Street identified in the LRDP Amendment #2 EIR
would still occur with the proposed project. Mitigation Measure 4.11‐2a from the LRDP Amendment #2
EIR identifies modifications to the Owens Street lane configurations (i.e. restriping) to mitigate this
impact. Implementation of the re‐striping at this location would improve the operating conditions at this
intersection to an acceptable LOS D (with an average delay of 50.3 seconds) during the p.m. peak hour.
In addition, a new potential impact could result from the proposed project in Phase II if all parking access
to the Medical Center is from a stop‐controlled approach at the garage access at Owens Street, halfway
between 16th and Mariposa Streets. The “T” intersection would operate at an unacceptable LOS F.
Implementation of a traffic signal at this location would improve the operating conditions at this
intersection to an acceptable LOS B (with an average delay of 15.5 seconds) during the p.m. peak hour.
7 Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation Study, March 2008.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 49 ‐
Mitigation Measure MCMB.6‐3 from the Medical Center at Mission Bay EIR would require that UCSF
conduct a project‐level CEQA review at the time the Phase II development is considered for approval. In
addition, in order to determine the need for LOS improvements on Owens Street, between 16th and
Mariposa Streets, at Center Garage Access (now Parking Structure Road), such as a traffic signal, UCSF
would coordinate with the City of San Francisco in the periodic update of the Mission Bay traffic triggers
survey and would monitor on‐site parking access and circulation in order to determine the need for LOS
improvements.
Implementation of the restriping of southbound Owens Street at 16th Street would reduce this potential
Phase II impact to a less‐than‐significant level. The need for LOS improvements on Owens Street at the
Parking Structure Road in Phase II remains speculative pending a project‐level design of parking
requirements and project‐level traffic and circulation evaluation.
The estimated parking demand for Phase I would be approximately 900 spaces (390 spaces for patients
and visitors and 510 spaces for staff). As noted previously, the proposed onsite parking supply for the
medical center in Phase I is approximately 1,075 spaces (600 spaces in the parking structure and
approximately 475 surface parking spaces). Therefore, the proposed parking supply in Phase I (1,075
spaces) could accommodate the anticipated demand (900 spaces) and the proposed project would not
result in a shortfall of parking capacity under Phase I.
Under Phase II, the estimated parking demand at full buildout would be approximately 1,760 spaces (740
spaces for patients and visitors and 1,020 for staff). As noted previously, the proposed onsite parking
supply for the medical center in Phase II would range from approximately 1,300 to 2,000 spaces, resulting
in a potential shortfall in parking supply. As stated in the Medical Center at Mission Bay EIR, as part of
the proposed project, (as it does at other UCSF campus sites), UCSF would monitor parking demand at
each phase of development and adjust parking supply as demand warrants. Should the demand for
parking exceed onsite supply, priority for onsite parking would be given to patients and visitors, and if
necessary, UCSF would consider offsite parking to satisfy the anticipated staff demand. The additional
parking supply could be accommodated on the UCSF Mission Bay research campus, if available, or
elsewhere in the project vicinity. As the Mission Bay Campus develops, UCSF (through its Transportation
Services Office) will make efforts to educate faculty, staff and students about transit options in order to
reduce auto usage and parking demand. The Medical Center at Mission Bay EIR concluded that the
potential parking shortfall under the full project buildout under Phase II would be less than significant.
The Medical Center at Mission Bay EIR concluded that the construction and operation of the Medical
Center at Mission Bay would not cause a substantial adverse impact to transit, pedestrian, bicycle, or
parking conditions, nor result in inadequate emergency access.
Describe how the minor project changes affect the earlier environmental analysis:
While the number of parking spaces in the parking structure would increase from 600 to 626, the number
of surface spaces would decrease from 475 to approximately 442. Therefore, the overall number of
parking spaces would decrease by about seven spaces. While minor, the potential changes to the traffic
analysis contained in the Medical Center at Mission Bay EIR will be evaluated and discussed in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 50 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
17. UTILITIES AND SERVICE SYSTEMS
‐‐ Would the project:
a) Exceed wastewater treatment requirements of the
applicable Regional Water Quality Control Board? □ ■
b) Require or result in the construction of new water or
wastewater treatment facilities or expansion of existing
facilities, the construction of which could cause
significant environmental effects?
□ ■
c) Require or result in the construction of new storm
water drainage facilities or expansion of existing
facilities, the construction of which could cause
significant environmental effects?
□ ■
d) Have sufficient water supplies available to serve the
project from existing entitlements and resources, or are
new or expanded entitlements needed?
□ ■
e) Result in a determination by the wastewater
treatment provider, which serves or may serve the
project that it has adequate capacity to serve the
project’s projected demand in addition to the
provider’s existing commitments?
□ ■
f) Be served by a landfill with sufficient permitted
capacity to accommodate the project’s solid waste
disposal needs?
□ ■
g) Comply with applicable federal, state, and local
statutes and regulations related to solid waste? □ ■
h) Result in the wasteful, inefficient and unnecessary
consumption of energy (see CEQA Statutes Section
21100(b)(3))?
□ ■
i) Exceed the applicable LRDP EIR standard of
significance by requiring or resulting in the
construction of new electrical or natural gas facilities,
□ ■
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 51 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
which would cause significant environmental effects?
Standards of Significance
The impact questions above constitute the significance standards for this environmental topic.
Discussion of Checklist Questions
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the EIR at the southwest
portion of the site as part of Phase I. The modified project would reduce a total of seven parking spaces in
Phase I and shift the location of the parking structure to the north. The modified project would not
include any parking levels below grade. All other aspects of the Phase I and Phase II project that was
analyzed in the Medical Center at Mission Bay EIR would remain the same.
Describe how the project is analyzed under this CEQA checklist topic:
The LRDP Amendment #2‐ Hospital Replacement EIR evaluated the demand for utilities, energy, and
service systems by the hospital replacement program as compared to existing and determined less‐than‐
significant impact. The Medical Center at Mission Bay EIR provided an updated assessment of the
medical center project to evaluate the potential impacts to water supply systems, wastewater disposal
systems, and energy consumption and determined that the project project’s demand on utilities, energy
and service systems would be less than significant and no mitigation measure would be necessary. .
While the revised parking garage is slightly larger, the proposed project would not change the analysis or
conclusions reached in in the Medical Center at Mission Bay EIR and impacts would be less than
significant. Therefore, no further environmental analysis is required in the SEIR.
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 52 ‐
Issues
Additional
Project‐
level
Impact
Analysis
Required
Project Impact
Adequately
Addressed in
Earlier
Environmental
Document
18. MANDATORY FINDINGS OF SIGNIFICANCE – The lead agency shall find that
a project may have a significant effect on the environment and thereby require an EIR
to be prepared for the project where there is substantial evidence, in light of the whole
record, that any of the following conditions may occur. Where prior to commencement
of the environmental analysis a project proponent agrees to mitigation measures or
project modifications that would avoid any significant effect on the environment or
would mitigate the significant environmental effect, a lead agency need not prepare an
EIR solely because without mitigation the environmental effects would have been
significant (per Section 15065 of the State CEQA Guidelines):
a) Does the project have the potential to degrade the
quality of the environment, substantially reduce the
habitat of a fish or wildlife species, cause a fish or
wildlife population to drop below self‐sustaining
levels, threaten to eliminate a plant or animal
community, substantially reduce the number or restrict
the range of a rare or endangered plant or animal or
eliminate important examples of the major periods of
California history or prehistory?
□ ■
b) Does the project have impacts that are individually
limited, but cumulatively considerable? (“Cumulatively
considerable” means that the incremental effects of a
project are significant when viewed in connection with
the effects of past projects, the effects of other current
projects, and the effects of past, present and probable
future projects)?
■ □
c) Does the project have environmental effects which
will cause substantial adverse effects on human beings,
either directly or indirectly?
■ □
Relevant elements of project:
The construction of the Phase I Medical Center at Mission Bay is currently underway. A 600‐space
parking structure at 90‐feet‐tall with 475 surface parking spaces was analyzed in the Medical Center at
Mission Bay EIR at the southwest portion of the site as part of Phase I.
Discussion of Potential Project Impacts:
Initial Study for UCSF Medical Center at Mission Bay Phase I Garage
‐ 53 ‐
18a) The modifications to the proposed project would not affect fish or wildlife habitat, populations,
communities, or substantially reduce the number or restrict the range of a rare or endangered plant or
animal or eliminate important examples of the major periods of California history or prehistory.
18 b‐c): An evaluation of the proposed project’s potential cumulatively considerable impacts and the
project’s potential to result in substantial effects on human beings will be included in the SEIR.
VI. SUPPORTING INFORMATION SOURCES Adavant Consulting and Wilbur Smith Associates, UCSF Medical Center at Mission Bay Transportation
Study, March 2008.
ESA, memo to Lori Yamauchi, Assistant Vice Chancellor UCSF Campus Planning, Technical
Memorandum Potential Wind Conditions, UCSF Medical Center at Mission Bay, December 3,
2010.
San Francisco Redevelopment Agency, Design for Development of the Mission Bay South Plan Area,
March 16, 2004. Available at: http://www.sfredevelopment.org/Modules/ShowDocument.aspx?documentid=787 , accessed
January 20, 2011.
San Francisco Redevelopment Agency, Redevelopment Plan for the Mission Bay South Redevelopment
Project, November 2, 1998. Available at:
http://www.sfredevelopment.org/Modules/ShowDocument.aspx?documentid=767, accessed
January 20, 2011.
VII. INITIAL STUDY PREPARERS
UCSF Campus Planning
654 Minnesota Street, San Francisco CA 94143‐0286
APPENDIX B AIR EMISSIONS ESTIMATES
1/24/2011 6:15:28 PM
Page: 1
File Name: C:\Users\pfranke\AppData\Roaming\Urbemis\Version9a\Projects\Medical Center Garage 3.urb924
Project Name: Medical Center Garage 3
Project Location: San Francisco County
On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006
Off-Road Vehicle Emissions Based on: OFFROAD2007
Combined Annual Emissions Reports (Tons/Year)
Urbemis 2007 Version 9.2.4
Percent Reduction 0.00 20.00 16.67 NaN NaN NaN 20.00
TOTALS (tons/year, mitigated) 0.22 0.12 0.10 0.00 0.00 0.00 141.10
TOTALS (tons/year, unmitigated) 0.22 0.15 0.12 0.00 0.00 0.00 176.38
AREA SOURCE EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
2008 TOTALS (tons/year unmitigated) 2.43 2.43 3.06 0.00 0.03 0.12 0.14 0.01 0.11 0.12 448.52
2008 TOTALS (tons/year mitigated) 2.43 2.43 3.06 0.00 0.02 0.12 0.14 0.01 0.11 0.11 448.52
Percent Reduction 0.00 0.00 0.00 0.00 18.23 0.00 3.27 13.14 0.00 0.85 0.00
Percent Reduction 0.00 0.00 0.00 0.00 43.34 0.00 26.02 43.27 0.00 11.02 0.00
2007 TOTALS (tons/year unmitigated) 0.04 0.34 0.18 0.00 0.03 0.02 0.04 0.01 0.02 0.02 27.01
2007 TOTALS (tons/year mitigated) 0.04 0.34 0.18 0.00 0.01 0.02 0.03 0.00 0.02 0.02 27.01
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust
PM2.5 CO2
CONSTRUCTION EMISSION ESTIMATES
Summary Report:
1/24/2011 6:15:28 PM
Page: 2
Construction Unmitigated Detail Report:
CONSTRUCTION EMISSION ESTIMATES Annual Tons Per Year, Unmitigated
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2
Percent Reduction 0.00 0.73 0.06 0.00 0.00 0.00 0.98
TOTALS (tons/year, mitigated) 2.99 4.06 33.35 0.03 6.46 1.22 3,566.85
TOTALS (tons/year, unmitigated) 2.99 4.09 33.37 0.03 6.46 1.22 3,602.13
SUM OF AREA SOURCE AND OPERATIONAL EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
Percent Reduction 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTALS (tons/year, mitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75
TOTALS (tons/year, unmitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75
OPERATIONAL (VEHICLE) EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
1/24/2011 6:15:28 PM
Page: 3
2007 0.04 0.34 0.18 0.00 0.04 0.02 27.010.03 0.02 0.01 0.02
0.00Asphalt 12/28/2007-01/11/2008 0.00 0.01 0.01 0.00 0.00 1.170.00 0.00 0.00 0.00
Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01
Paving Worker Trips 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18
Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 0.00 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.98
0.04Fine Grading 11/30/2007-01/11/2008
0.04 0.33 0.17 0.00 0.02 25.840.03 0.02 0.01 0.02
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.12
Fine Grading Dust 0.00 0.00 0.00 0.00 0.03 0.00 0.03 0.01 0.00 0.01 0.00
Fine Grading Off Road Diesel 0.04 0.33 0.16 0.00 0.00 0.02 0.02 0.00 0.02 0.02 24.72
1/24/2011 6:15:28 PM
Page: 4
20 lbs per acre-day
Fugitive Dust Level of Detail: Default
Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description
Maximum Daily Acreage Disturbed: 0.12
Total Acres Disturbed: 0.5
Phase Assumptions
2008 2.43 2.43 3.06 0.00 0.14 0.12 448.520.03 0.12 0.01 0.11
0.12Building 01/11/2008-08/22/2008 0.26 2.24 2.92 0.00 0.10 430.130.01 0.11 0.01 0.10
Building Worker Trips 0.06 0.10 1.64 0.00 0.01 0.00 0.01 0.00 0.00 0.00 138.02
Building Vendor Trips 0.09 1.30 0.87 0.00 0.01 0.05 0.06 0.00 0.05 0.05 220.19
Building Off Road Diesel 0.11 0.84 0.41 0.00 0.00 0.05 0.05 0.00 0.05 0.05 71.92
0.00Coating 08/08/2008-09/05/2008 2.14 0.00 0.03 0.00 0.00 2.550.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.55
Architectural Coating 2.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.01Asphalt 12/28/2007-01/11/2008 0.01 0.06 0.04 0.00 0.00 5.270.00 0.01 0.00 0.00
Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06
Paving Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80
Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 0.01 0.06 0.03 0.00 0.00 0.01 0.01 0.00 0.00 0.00 4.41
0.02Fine Grading 11/30/2007-01/11/2008
0.02 0.13 0.07 0.00 0.01 10.570.01 0.01 0.00 0.01
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.46
Fine Grading Dust 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.00 0.00
Fine Grading Off Road Diesel 0.01 0.13 0.06 0.00 0.00 0.01 0.01 0.00 0.01 0.01 10.11
1/24/2011 6:15:28 PM
Page: 5
Construction Mitigated Detail Report:
1 Cranes (399 hp) operating at a 0.43 load factor for 4 hours per day
2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day
Phase: Building Construction 1/11/2008 - 8/22/2008 - Default Building Construction Description
Off-Road Equipment:
Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Phase: Architectural Coating 8/8/2008 - 9/5/2008 - Default Architectural Coating Description
Rule: Residential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Residential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day
On Road Truck Travel (VMT): 0
Off-Road Equipment:
1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day
4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day
1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day
1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day
Phase: Paving 12/28/2007 - 1/11/2008 - Default Paving Description
Acres to be Paved: 0.12
Off-Road Equipment:
1/24/2011 6:15:28 PM
Page: 6
CONSTRUCTION EMISSION ESTIMATES Annual Tons Per Year, Mitigated
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2
2007 0.04 0.34 0.18 0.00 0.03 0.02 27.010.01 0.02 0.00 0.02
0.00Asphalt 12/28/2007-01/11/2008 0.00 0.01 0.01 0.00 0.00 1.170.00 0.00 0.00 0.00
Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01
Paving Worker Trips 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18
Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 0.00 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.98
0.03Fine Grading 11/30/2007-01/11/2008
0.04 0.33 0.17 0.00 0.02 25.840.01 0.02 0.00 0.02
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.12
Fine Grading Dust 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.00 0.00
Fine Grading Off Road Diesel 0.04 0.33 0.16 0.00 0.00 0.02 0.02 0.00 0.02 0.02 24.72
1/24/2011 6:15:28 PM
Page: 7
2008 2.43 2.43 3.06 0.00 0.14 0.11 448.520.02 0.12 0.01 0.11
0.12Building 01/11/2008-08/22/2008 0.26 2.24 2.92 0.00 0.10 430.130.01 0.11 0.01 0.10
Building Worker Trips 0.06 0.10 1.64 0.00 0.01 0.00 0.01 0.00 0.00 0.00 138.02
Building Vendor Trips 0.09 1.30 0.87 0.00 0.01 0.05 0.06 0.00 0.05 0.05 220.19
Building Off Road Diesel 0.11 0.84 0.41 0.00 0.00 0.05 0.05 0.00 0.05 0.05 71.92
0.00Coating 08/08/2008-09/05/2008 2.14 0.00 0.03 0.00 0.00 2.550.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.55
Architectural Coating 2.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.01Asphalt 12/28/2007-01/11/2008 0.01 0.06 0.04 0.00 0.00 5.270.00 0.01 0.00 0.00
Paving On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06
Paving Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80
Paving Off-Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 0.01 0.06 0.03 0.00 0.00 0.01 0.01 0.00 0.00 0.00 4.41
0.01Fine Grading 11/30/2007-01/11/2008
0.02 0.13 0.07 0.00 0.01 10.570.01 0.01 0.00 0.01
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.46
Fine Grading Dust 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.00 0.00
Fine Grading Off Road Diesel 0.01 0.13 0.06 0.00 0.00 0.01 0.01 0.00 0.01 0.01 10.11
For Soil Stablizing Measures, the Water exposed surfaces 2x daily watering mitigation reduces emissions by:
PM10: 55% PM25: 55%
The following mitigation measures apply to Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description
Construction Related Mitigation Measures
1/24/2011 6:15:28 PM
Page: 8
Architectural Coatings 0.21
Consumer Products 0.00
Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Landscape
Natural Gas 0.01 0.15 0.12 0.00 0.00 0.00 176.38
TOTALS (tons/year, unmitigated) 0.22 0.15 0.12 0.00 0.00 0.00 176.38
Source ROG NOx CO SO2 PM10 PM2.5 CO2
AREA SOURCE EMISSION ESTIMATES Annual Tons Per Year, Unmitigated
Area Source Unmitigated Detail Report:
Area Source Mitigation Measures Selected
Architectural Coatings 0.21
Consumer Products 0.00
Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Landscape
Natural Gas 0.01 0.12 0.10 0.00 0.00 0.00 141.10
TOTALS (tons/year, mitigated) 0.22 0.12 0.10 0.00 0.00 0.00 141.10
Source ROG NOx CO SO2 PM10 PM2.5 CO2
AREA SOURCE EMISSION ESTIMATES Annual Tons Per Year, Mitigated
Industrial Increase Energy Efficiency Beyond Title 24 20.00
Mitigation Description Percent Reduction
Area Source Mitigated Detail Report:
Area Source Changes to Defaults
1/24/2011 6:15:28 PM
Page: 9
Residential Mitigation Measures
Operational Mitigation Options Selected
The Presence of Local-Serving Retail checkbox was NOT selected.
Percent Reduction in Trips is 0%
Inputs Selected:
---------------------------------------------------------------
Non-Residential Local-Serving Retail Mitigation
Nonresidential Mitigation Measures
OPERATIONAL EMISSION ESTIMATES Annual Tons Per Year, Mitigated
Warehouse 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75
TOTALS (tons/year, mitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75
Source ROG NOX CO SO2 PM10 PM25 CO2
Operational Mitigated Detail Report:
OPERATIONAL EMISSION ESTIMATES Annual Tons Per Year, Unmitigated
Warehouse 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75
TOTALS (tons/year, unmitigated) 2.77 3.94 33.25 0.03 6.46 1.22 3,425.75
Source ROG NOX CO SO2 PM10 PM25 CO2
Operational Unmitigated Detail Report:
Does not include correction for passby trips
Does not include double counting adjustment for internal trips
Operational Settings:
1/24/2011 6:15:28 PM
Page: 10
Heavy-Heavy Truck 33,001-60,000 lbs 0.1 0.0 0.0 100.0
Med-Heavy Truck 14,001-33,000 lbs 1.6 0.0 18.8 81.2
Motor Home 0.2 0.0 100.0 0.0
Other Bus 0.1 0.0 100.0 0.0
School Bus 0.1 0.0 0.0 100.0
Motorcycle 3.5 51.4 48.6 0.0
Urban Bus 0.3 0.0 0.0 100.0
Light Truck < 3750 lbs 11.0 0.0 99.1 0.9
Light Auto 61.0 0.3 99.5 0.2
Lite-Heavy Truck 10,001-14,000 lbs 0.5 0.0 60.0 40.0
Lite-Heavy Truck 8501-10,000 lbs 0.5 0.0 80.0 20.0
Med Truck 5751-8500 lbs 4.7 0.0 100.0 0.0
Light Truck 3751-5750 lbs 16.4 0.0 100.0 0.0
Vehicle Fleet Mix
Vehicle Type Percent Type Non-Catalyst Catalyst Diesel
Warehouse 13.08 1000 sq ft 200.00 2,616.00 20,633.70
2,616.00 20,633.70
Summary of Land Uses
Land Use Type Acreage Trip Rate Unit Type No. Units Total Trips Total VMT
Emfac: Version : Emfac2007 V2.3 Nov 1 2006
Analysis Year: 2012 Season: Annual
1/24/2011 6:15:28 PM
Page: 11
% of Trips - Residential 32.9 18.0 49.1
Trip speeds (mph) 35.0 35.0 35.0 35.0 35.0 35.0
% of Trips - Commercial (by land use)
Warehouse 25.0 12.5 62.5
Rural Trip Length (miles) 16.8 7.1 7.9 14.7 6.6 6.6
Urban Trip Length (miles) 10.8 7.3 7.5 9.5 7.4 7.4
Travel Conditions
Home-Work Home-Shop Home-Other Commute Non-Work Customer
Residential Commercial
Operational Changes to Defaults
1/24/2011 6:17:06 PM
Page: 1
File Name: C:\Users\pfranke\AppData\Roaming\Urbemis\Version9a\Projects\Medical Center Garage 3.urb924
Project Name: Medical Center Garage 3
Project Location: San Francisco County
On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006
Off-Road Vehicle Emissions Based on: OFFROAD2007
Combined Summer Emissions Reports (Pounds/Day)
Urbemis 2007 Version 9.2.4
Percent Reduction 0.81 20.99 20.59 NaN NaN NaN 20.00
TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16
TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44
AREA SOURCE EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
2008 TOTALS (lbs/day unmitigated) 207.30 69.39 60.30 0.04 2.60 3.89 6.49 0.57 3.57 4.14 8,863.45
2008 TOTALS (lbs/day mitigated) 207.30 69.39 60.30 0.04 1.55 3.89 5.44 0.35 3.57 3.92 8,863.45
2007 TOTALS (lbs/day mitigated) 6.04 43.98 25.01 0.00 1.37 2.71 4.08 0.29 2.49 2.78 3,520.26
2007 TOTALS (lbs/day unmitigated) 6.04 43.98 25.01 0.00 2.41 2.71 5.12 0.51 2.49 3.00 3,520.26
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust
PM2.5 CO2
CONSTRUCTION EMISSION ESTIMATES
Summary Report:
1/24/2011 6:17:06 PM
Page: 2
Construction Unmitigated Detail Report:
CONSTRUCTION EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2
Time Slice 11/30/2007-12/27/2007 Active Days: 20
3.56 29.72 15.47 0.00 3.90 1.87 2,349.392.40 1.49 0.50 1.37
3.90Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
Percent Reduction 0.06 0.87 0.08 0.00 0.00 0.00 0.94
TOTALS (lbs/day, mitigated) 16.04 19.30 179.67 0.20 35.38 6.70 20,438.20
TOTALS (lbs/day, unmitigated) 16.05 19.47 179.81 0.20 35.38 6.70 20,631.48
SUM OF AREA SOURCE AND OPERATIONAL EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
Percent Reduction 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTALS (lbs/day, mitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04
TOTALS (lbs/day, unmitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04
OPERATIONAL (VEHICLE) EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
1/24/2011 6:17:06 PM
Page: 3
Time Slice 12/28/2007-12/31/2007 Active Days: 2
6.04 43.98 25.01 0.00 5.12 3.00 3,520.262.41 2.71 0.51 2.49
3.90Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12
Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23
Time Slice 1/1/2008-1/10/2008 Active Days: 8
5.68 41.56 24.07 0.00 4.98 2.87 3,520.212.41 2.57 0.51 2.36
3.82Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
1/24/2011 6:17:06 PM
Page: 4
Time Slice 1/11/2008-1/11/2008 Active Days: 1
8.88 69.39 60.30 0.04 6.49 4.14 8,863.452.60 3.89 0.57 3.57
3.82Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
Time Slice 1/14/2008-8/7/2008 Active Days: 149
3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1/24/2011 6:17:06 PM
Page: 5
20 lbs per acre-day
Fugitive Dust Level of Detail: Default
Off-Road Equipment:
On Road Truck Travel (VMT): 0
Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description
Maximum Daily Acreage Disturbed: 0.12
Total Acres Disturbed: 0.5
1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day
1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day
1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
Phase Assumptions
Time Slice 8/25/2008-9/5/2008 Active Days: 10
204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Time Slice 8/8/2008-8/22/2008 Active Days: 11
207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1/24/2011 6:17:06 PM
Page: 6
Construction Mitigated Detail Report:
CONSTRUCTION EMISSION ESTIMATES Summer Pounds Per Day, Mitigated
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2
Phase: Architectural Coating 8/8/2008 - 9/5/2008 - Default Architectural Coating Description
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day
1 Cranes (399 hp) operating at a 0.43 load factor for 4 hours per day
2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day
Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Residential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Residential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day
1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day
Off-Road Equipment:
Phase: Paving 12/28/2007 - 1/11/2008 - Default Paving Description
Acres to be Paved: 0.12
Phase: Building Construction 1/11/2008 - 8/22/2008 - Default Building Construction Description
Off-Road Equipment:
1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
1/24/2011 6:17:06 PM
Page: 7
Time Slice 11/30/2007-12/27/2007 Active Days: 20
3.56 29.72 15.47 0.00 2.85 1.66 2,349.391.36 1.49 0.29 1.37
2.85Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
Time Slice 12/28/2007-12/31/2007 Active Days: 2
6.04 43.98 25.01 0.00 4.08 2.78 3,520.261.37 2.71 0.29 2.49
2.85Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12
Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23
1/24/2011 6:17:06 PM
Page: 8
Time Slice 1/1/2008-1/10/2008 Active Days: 8
5.68 41.56 24.07 0.00 3.94 2.65 3,520.211.37 2.57 0.29 2.36
2.78Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
1/24/2011 6:17:06 PM
Page: 9
Time Slice 1/11/2008-1/11/2008 Active Days: 1
8.88 69.39 60.30 0.04 5.44 3.92 8,863.451.55 3.89 0.35 3.57
2.78Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
Time Slice 1/14/2008-8/7/2008 Active Days: 149
3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1/24/2011 6:17:06 PM
Page: 10
Time Slice 8/25/2008-9/5/2008 Active Days: 10
204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Time Slice 8/8/2008-8/22/2008 Active Days: 11
207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
For Soil Stablizing Measures, the Water exposed surfaces 2x daily watering mitigation reduces emissions by:
PM10: 55% PM25: 55%
The following mitigation measures apply to Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description
Construction Related Mitigation Measures
1/24/2011 6:17:06 PM
Page: 11
Architectural Coatings 1.17
Consumer Products 0.00
Hearth - No Summer Emissions
Landscape
Natural Gas 0.06 0.81 0.68 0.00 0.00 0.00 966.44
TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44
Source ROG NOx CO SO2 PM10 PM2.5 CO2
AREA SOURCE EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated
Area Source Unmitigated Detail Report:
Area Source Mitigation Measures Selected
Architectural Coatings 1.17
Consumer Products 0.00
Hearth - No Summer Emissions
Landscape
Natural Gas 0.05 0.64 0.54 0.00 0.00 0.00 773.16
TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16
Source ROG NOx CO SO2 PM10 PM2.5 CO2
AREA SOURCE EMISSION ESTIMATES Summer Pounds Per Day, Mitigated
Industrial Increase Energy Efficiency Beyond Title 24 20.00
Mitigation Description Percent Reduction
Area Source Mitigated Detail Report:
Area Source Changes to Defaults
1/24/2011 6:17:06 PM
Page: 12
Residential Mitigation Measures
Operational Mitigation Options Selected
The Presence of Local-Serving Retail checkbox was NOT selected.
Percent Reduction in Trips is 0%
Inputs Selected:
---------------------------------------------------------------
Non-Residential Local-Serving Retail Mitigation
Nonresidential Mitigation Measures
OPERATIONAL EMISSION ESTIMATES Summer Pounds Per Day, Mitigated
Warehouse 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04
TOTALS (lbs/day, mitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04
Source ROG NOX CO SO2 PM10 PM25 CO2
Operational Mitigated Detail Report:
OPERATIONAL EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated
Warehouse 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04
TOTALS (lbs/day, unmitigated) 14.82 18.66 179.13 0.20 35.38 6.70 19,665.04
Source ROG NOX CO SO2 PM10 PM25 CO2
Operational Unmitigated Detail Report:
Does not include correction for passby trips
Does not include double counting adjustment for internal trips
Operational Settings:
1/24/2011 6:17:06 PM
Page: 13
Heavy-Heavy Truck 33,001-60,000 lbs 0.1 0.0 0.0 100.0
Med-Heavy Truck 14,001-33,000 lbs 1.6 0.0 18.8 81.2
Motor Home 0.2 0.0 100.0 0.0
Other Bus 0.1 0.0 100.0 0.0
School Bus 0.1 0.0 0.0 100.0
Motorcycle 3.5 51.4 48.6 0.0
Urban Bus 0.3 0.0 0.0 100.0
Light Truck < 3750 lbs 11.0 0.0 99.1 0.9
Light Auto 61.0 0.3 99.5 0.2
Lite-Heavy Truck 10,001-14,000 lbs 0.5 0.0 60.0 40.0
Lite-Heavy Truck 8501-10,000 lbs 0.5 0.0 80.0 20.0
Med Truck 5751-8500 lbs 4.7 0.0 100.0 0.0
Light Truck 3751-5750 lbs 16.4 0.0 100.0 0.0
Vehicle Fleet Mix
Vehicle Type Percent Type Non-Catalyst Catalyst Diesel
Warehouse 13.08 1000 sq ft 200.00 2,616.00 20,633.70
2,616.00 20,633.70
Summary of Land Uses
Land Use Type Acreage Trip Rate Unit Type No. Units Total Trips Total VMT
Emfac: Version : Emfac2007 V2.3 Nov 1 2006
Analysis Year: 2012 Temperature (F): 85 Season: Summer
1/24/2011 6:17:06 PM
Page: 14
% of Trips - Residential 32.9 18.0 49.1
Trip speeds (mph) 35.0 35.0 35.0 35.0 35.0 35.0
% of Trips - Commercial (by land use)
Warehouse 25.0 12.5 62.5
Rural Trip Length (miles) 16.8 7.1 7.9 14.7 6.6 6.6
Urban Trip Length (miles) 10.8 7.3 7.5 9.5 7.4 7.4
Travel Conditions
Home-Work Home-Shop Home-Other Commute Non-Work Customer
Residential Commercial
Operational Changes to Defaults
1/24/2011 6:16:43 PM
Page: 1
File Name: C:\Users\pfranke\AppData\Roaming\Urbemis\Version9a\Projects\Medical Center Garage 3.urb924
Project Name: Medical Center Garage 3
Project Location: San Francisco County
On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006
Off-Road Vehicle Emissions Based on: OFFROAD2007
Combined Winter Emissions Reports (Pounds/Day)
Urbemis 2007 Version 9.2.4
Percent Reduction 0.81 20.99 20.59 NaN NaN NaN 20.00
TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16
TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44
AREA SOURCE EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
2008 TOTALS (lbs/day unmitigated) 207.30 69.39 60.30 0.04 2.60 3.89 6.49 0.57 3.57 4.14 8,863.45
2008 TOTALS (lbs/day mitigated) 207.30 69.39 60.30 0.04 1.55 3.89 5.44 0.35 3.57 3.92 8,863.45
2007 TOTALS (lbs/day mitigated) 6.04 43.98 25.01 0.00 1.37 2.71 4.08 0.29 2.49 2.78 3,520.26
2007 TOTALS (lbs/day unmitigated) 6.04 43.98 25.01 0.00 2.41 2.71 5.12 0.51 2.49 3.00 3,520.26
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust
PM2.5 CO2
CONSTRUCTION EMISSION ESTIMATES
Summary Report:
1/24/2011 6:16:43 PM
Page: 2
Construction Unmitigated Detail Report:
CONSTRUCTION EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2
Time Slice 11/30/2007-12/27/2007 Active Days: 20
3.56 29.72 15.47 0.00 3.90 1.87 2,349.392.40 1.49 0.50 1.37
3.90Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
Percent Reduction 0.06 0.60 0.07 0.00 0.00 0.00 1.08
TOTALS (lbs/day, mitigated) 17.09 28.06 188.80 0.17 35.38 6.70 17,756.75
TOTALS (lbs/day, unmitigated) 17.10 28.23 188.94 0.17 35.38 6.70 17,950.03
SUM OF AREA SOURCE AND OPERATIONAL EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
Percent Reduction 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTALS (lbs/day, mitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59
TOTALS (lbs/day, unmitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59
OPERATIONAL (VEHICLE) EMISSION ESTIMATES
ROG NOx CO SO2 PM10 PM2.5 CO2
1/24/2011 6:16:43 PM
Page: 3
Time Slice 12/28/2007-12/31/2007 Active Days: 2
6.04 43.98 25.01 0.00 5.12 3.00 3,520.262.41 2.71 0.51 2.49
3.90Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.87 2,349.392.40 1.49 0.50 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12
Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23
Time Slice 1/1/2008-1/10/2008 Active Days: 8
5.68 41.56 24.07 0.00 4.98 2.87 3,520.212.41 2.57 0.51 2.36
3.82Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
1/24/2011 6:16:44 PM
Page: 4
Time Slice 1/11/2008-1/11/2008 Active Days: 1
8.88 69.39 60.30 0.04 6.49 4.14 8,863.452.60 3.89 0.57 3.57
3.82Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.80 2,349.372.40 1.41 0.50 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 2.40 0.00 2.40 0.50 0.00 0.50 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
Time Slice 1/14/2008-8/7/2008 Active Days: 149
3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1/24/2011 6:16:44 PM
Page: 5
20 lbs per acre-day
Fugitive Dust Level of Detail: Default
Off-Road Equipment:
On Road Truck Travel (VMT): 0
Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description
Maximum Daily Acreage Disturbed: 0.12
Total Acres Disturbed: 0.5
1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day
1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day
1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
Phase Assumptions
Time Slice 8/25/2008-9/5/2008 Active Days: 10
204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Time Slice 8/8/2008-8/22/2008 Active Days: 11
207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1/24/2011 6:16:44 PM
Page: 6
Construction Mitigated Detail Report:
CONSTRUCTION EMISSION ESTIMATES Winter Pounds Per Day, Mitigated
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5 CO2
Phase: Architectural Coating 8/8/2008 - 9/5/2008 - Default Architectural Coating Description
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day
1 Cranes (399 hp) operating at a 0.43 load factor for 4 hours per day
2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day
Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Residential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Residential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day
1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day
Off-Road Equipment:
Phase: Paving 12/28/2007 - 1/11/2008 - Default Paving Description
Acres to be Paved: 0.12
Phase: Building Construction 1/11/2008 - 8/22/2008 - Default Building Construction Description
Off-Road Equipment:
1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
1/24/2011 6:16:44 PM
Page: 7
Time Slice 11/30/2007-12/27/2007 Active Days: 20
3.56 29.72 15.47 0.00 2.85 1.66 2,349.391.36 1.49 0.29 1.37
2.85Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
Time Slice 12/28/2007-12/31/2007 Active Days: 2
6.04 43.98 25.01 0.00 4.08 2.78 3,520.261.37 2.71 0.29 2.49
2.85Fine Grading 11/30/2007-01/11/2008
3.56 29.72 15.47 0.00 1.66 2,349.391.36 1.49 0.29 1.37
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.08 1.29 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.07
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.52 29.64 14.18 0.00 0.00 1.49 1.49 0.00 1.37 1.37 2,247.32
1.22Asphalt 12/28/2007-01/11/2008 2.48 14.27 9.54 0.00 1.12 1,170.870.01 1.22 0.00 1.12
Paving On Road Diesel 0.01 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.08 0.13 2.26 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.62
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.36 14.02 7.24 0.00 0.00 1.21 1.21 0.00 1.11 1.11 979.23
1/24/2011 6:16:44 PM
Page: 8
Time Slice 1/1/2008-1/10/2008 Active Days: 8
5.68 41.56 24.07 0.00 3.94 2.65 3,520.211.37 2.57 0.29 2.36
2.78Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
1/24/2011 6:16:44 PM
Page: 9
Time Slice 1/11/2008-1/11/2008 Active Days: 1
8.88 69.39 60.30 0.04 5.44 3.92 8,863.451.55 3.89 0.35 3.57
2.78Fine Grading 11/30/2007-01/11/2008
3.35 28.07 14.77 0.00 1.59 2,349.371.36 1.41 0.29 1.30
Fine Grading On Road Diesel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Fine Grading Worker Trips 0.04 0.07 1.21 0.00 0.00 0.00 0.01 0.00 0.00 0.00 102.05
Fine Grading Dust 0.00 0.00 0.00 0.00 1.36 0.00 1.36 0.28 0.00 0.28 0.00
Fine Grading Off Road Diesel 3.31 28.00 13.56 0.00 0.00 1.41 1.41 0.00 1.30 1.30 2,247.32
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1.16Asphalt 12/28/2007-01/11/2008 2.33 13.49 9.30 0.00 1.07 1,170.840.01 1.15 0.00 1.06
Paving On Road Diesel 0.01 0.10 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02
Paving Worker Trips 0.07 0.12 2.12 0.00 0.01 0.00 0.01 0.00 0.00 0.01 178.60
Paving Off-Gas 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 2.22 13.27 7.15 0.00 0.00 1.15 1.15 0.00 1.06 1.06 979.23
Time Slice 1/14/2008-8/7/2008 Active Days: 149
3.19 27.83 36.23 0.04 1.50 1.27 5,343.230.18 1.32 0.06 1.21
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
1/24/2011 6:16:44 PM
Page: 10
Time Slice 8/25/2008-9/5/2008 Active Days: 10
204.11 0.17 2.88 0.00 0.02 0.01 242.990.01 0.01 0.00 0.00
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Time Slice 8/8/2008-8/22/2008 Active Days: 11
207.30 27.99 39.12 0.04 1.52 1.28 5,586.220.20 1.32 0.07 1.21
0.02Coating 08/08/2008-09/05/2008 204.11 0.17 2.88 0.00 0.01 242.990.01 0.01 0.00 0.00
Coating Worker Trips 0.10 0.17 2.88 0.00 0.01 0.01 0.02 0.00 0.00 0.01 242.99
Architectural Coating 204.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.50Building 01/11/2008-08/22/2008 3.19 27.83 36.23 0.04 1.27 5,343.230.18 1.32 0.06 1.21
Building Worker Trips 0.69 1.18 20.35 0.02 0.08 0.04 0.12 0.03 0.03 0.06 1,714.52
Building Vendor Trips 1.12 16.17 10.79 0.03 0.10 0.61 0.71 0.03 0.56 0.60 2,735.32
Building Off Road Diesel 1.39 10.47 5.09 0.00 0.00 0.67 0.67 0.00 0.61 0.61 893.39
For Soil Stablizing Measures, the Water exposed surfaces 2x daily watering mitigation reduces emissions by:
PM10: 55% PM25: 55%
The following mitigation measures apply to Phase: Fine Grading 11/30/2007 - 1/11/2008 - Default Fine Site Grading Description
Construction Related Mitigation Measures
1/24/2011 6:16:44 PM
Page: 11
Architectural Coatings 1.17
Consumer Products 0.00
Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Landscape
Natural Gas 0.06 0.81 0.68 0.00 0.00 0.00 966.44
TOTALS (lbs/day, unmitigated) 1.23 0.81 0.68 0.00 0.00 0.00 966.44
Source ROG NOx CO SO2 PM10 PM2.5 CO2
AREA SOURCE EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated
Area Source Unmitigated Detail Report:
Area Source Mitigation Measures Selected
Architectural Coatings 1.17
Consumer Products 0.00
Hearth 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Landscape
Natural Gas 0.05 0.64 0.54 0.00 0.00 0.00 773.16
TOTALS (lbs/day, mitigated) 1.22 0.64 0.54 0.00 0.00 0.00 773.16
Source ROG NOx CO SO2 PM10 PM2.5 CO2
AREA SOURCE EMISSION ESTIMATES Winter Pounds Per Day, Mitigated
Industrial Increase Energy Efficiency Beyond Title 24 20.00
Mitigation Description Percent Reduction
Area Source Mitigated Detail Report:
Area Source Changes to Defaults
1/24/2011 6:16:44 PM
Page: 12
Residential Mitigation Measures
Operational Mitigation Options Selected
The Presence of Local-Serving Retail checkbox was NOT selected.
Percent Reduction in Trips is 0%
Inputs Selected:
---------------------------------------------------------------
Non-Residential Local-Serving Retail Mitigation
Nonresidential Mitigation Measures
OPERATIONAL EMISSION ESTIMATES Winter Pounds Per Day, Mitigated
Warehouse 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59
TOTALS (lbs/day, mitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59
Source ROG NOX CO SO2 PM10 PM25 CO2
Operational Mitigated Detail Report:
OPERATIONAL EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated
Warehouse 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59
TOTALS (lbs/day, unmitigated) 15.87 27.42 188.26 0.17 35.38 6.70 16,983.59
Source ROG NOX CO SO2 PM10 PM25 CO2
Operational Unmitigated Detail Report:
Does not include correction for passby trips
Does not include double counting adjustment for internal trips
Operational Settings:
1/24/2011 6:16:44 PM
Page: 13
Heavy-Heavy Truck 33,001-60,000 lbs 0.1 0.0 0.0 100.0
Med-Heavy Truck 14,001-33,000 lbs 1.6 0.0 18.8 81.2
Motor Home 0.2 0.0 100.0 0.0
Other Bus 0.1 0.0 100.0 0.0
School Bus 0.1 0.0 0.0 100.0
Motorcycle 3.5 51.4 48.6 0.0
Urban Bus 0.3 0.0 0.0 100.0
Light Truck < 3750 lbs 11.0 0.0 99.1 0.9
Light Auto 61.0 0.3 99.5 0.2
Lite-Heavy Truck 10,001-14,000 lbs 0.5 0.0 60.0 40.0
Lite-Heavy Truck 8501-10,000 lbs 0.5 0.0 80.0 20.0
Med Truck 5751-8500 lbs 4.7 0.0 100.0 0.0
Light Truck 3751-5750 lbs 16.4 0.0 100.0 0.0
Vehicle Fleet Mix
Vehicle Type Percent Type Non-Catalyst Catalyst Diesel
Warehouse 13.08 1000 sq ft 200.00 2,616.00 20,633.70
2,616.00 20,633.70
Summary of Land Uses
Land Use Type Acreage Trip Rate Unit Type No. Units Total Trips Total VMT
Emfac: Version : Emfac2007 V2.3 Nov 1 2006
Analysis Year: 2012 Temperature (F): 40 Season: Winter
1/24/2011 6:16:44 PM
Page: 14
% of Trips - Residential 32.9 18.0 49.1
Trip speeds (mph) 35.0 35.0 35.0 35.0 35.0 35.0
% of Trips - Commercial (by land use)
Warehouse 25.0 12.5 62.5
Rural Trip Length (miles) 16.8 7.1 7.9 14.7 6.6 6.6
Urban Trip Length (miles) 10.8 7.3 7.5 9.5 7.4 7.4
Travel Conditions
Home-Work Home-Shop Home-Other Commute Non-Work Customer
Residential Commercial
Operational Changes to Defaults
Bay Area Air Quality Management District Greenhouse Gas Model (BGM) Version: 1.1.9 Beta
Copyright:
LINKS
Transportation
Area Source
Electricity and Natural Gas
Water and Wastewater
Solid Waste
AgricultureAssistance provided by:
Off-Road Equipment
Refrigerants
Mitigation
Carbon Sequestration
Enter data in yellow cells with values applicable to your project
Enter data in peach cells if you have information specific to your project; these values will be used in place of the default values
Summary Results
Open an Urbemis Project File
Step 1: Enable MacrosMacros must be enabled for this model to operate correctly. The method for enabling macros for this spreadsheet
differs depending on the security settings in Excel.
Step 2: Open an Urbemis Project File, or Refresh Urbemis DataBGM depends on the data and results from an URBEMIS project file. Two URBEMIS files can be specified : a project file and (optionally) a baseline file. To open a file, or to refresh the data in this spreadsheet after an URBEMIS file has been modified, go to the Settings tab by clicking on the Open an URBEMIS Project File link to the right . Select the URBEMIS file(s) that you want to import and hit the refresh data button. Please make sure that the Emfac Database Location is correct before clicking either of the Refresh buttons.
Step 4: View ResultsThe Results Tab presents a graphical and tabular view of the results of the Greenhouse Gas Calculator. Both a summary and detailed report are included on the Results tab. The user also has the option of selected project specific mitigation on the Mitigation tab and on the Carbon Sequestration tab.
Step 3: Data Entry OptionsThe bright yellow areas on each tab represent data entry locations, if applicable to your project. In some cases, there are optional data inputs (shown in peach). Some tabs, such as transportation and area sources, do not require any data input, as results are imported directly from URBEMIS. Certain other tabs ‐ electricty & natural gas, water & wastewater, and solid waste ‐ require some minor amount of user input, although most of the information used to estimate emissions is imported from URBEMIS. And for certain tabs, ‐ ag, off‐road, refrigerants, and carbon sequestration ‐ the user must enter project specific information to obtain emission estimates.
1 of 4
Summary Results
Project Name: Medical Center Garage 3
Project and Baseline Years: 2012 2011
ResultsTransportation: 3,167.59 3,167.59
Area Source: 0.00 0.00
Electricity: 563.95 451.16
Natural Gas: 46.01 36.81
Water & Wastewater: 6.32 6.05
Solid Waste: 334.16 133.66
Agriculture: 0.00 0.00
Off‐Road Equipment: 0.00 0.00
Refrigerants: 0.00 0.00
Sequestration: N/A 0.00
Purchase of Offsets: N/A 0.00
Total: 4,118.02 3,795.27
Baseline is currently: ON
Unmitigated Project‐Baseline CO2e (metric
tons/year)
Mitigated Project‐Baseline CO2e
(metric tons/year)
2 of 4
Baseline is Currently: ON
Target Year: 2012 2011 Target Year: 2012 2011
Unmitigated Transportation Mitigated TransportationProject Baseline Project‐Baseline Project Baseline Project‐Baseline
Operational Emissions from URBEMIS (CO2 tons/year) 3,425.75 0.00 Operational Vehicles from URBEMIS (CO2 tons/year): 3,425.75 0.00
Metric Ton Adjustment (CO2 metric tons/year) 3,108.67 0.00 Metric Ton Adjustment (CO2 metric tons/year): 3,108.67 0.00
Pavley Regulation Adjustment (CO2 metric tons/year): 3,020.08 0.00 Pavley Regulation Adjustment (CO2 metric tons/year): 3,020.08 0.00
US EPA Adjustment (CO2e metric tons/year): 3,179.03 0.00 US EPA Adjustment (CO2e metric tons/year): 3,179.03 0.00
Low Carbon Fuels Rule Adjustment (CO2e metric tons/year) 3,167.59 0.00 Low Carbon Fuels Adjustment (CO2e metric tons/year): 3,167.59 0.00
Total (CO2e metric tons/year): 3,167.59 Total (CO2e metric tons/year): 3,167.59
The BGM User's Manual describes in detail each step used to convert URBEMIS's transportation CO2 emissions to total CO2e.
These steps include converting from English to Metric units, adjusting for the Pavley Rule, converting CO2 to CO2e, and adjusting for the Low Carbon Fuels Rule.
Reference
Jump to the Following Transportation Related Tabs:
Transportation Detail for Operational Mitigation
Land Use Detail
Don't Need to
Adjust this
amt
Unadjusted
Amount
Affected by
Pavley Adjusted Adusted Adusted Adusted Adjusted
Not Affected
by Pavley
LDA/ LDT1/
LDT2/ MDV LDA LDT1 LDT2 MDV 4 totaled
Pavley Calculations ‐ Project Unmitigated 520.13 2,588.54 1,249.26 376.00 589.67 285.02 2,499.96
Pavley Calculations ‐ Baseline Unmitigated 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pavley Calculations ‐ Project Mitigated 520.13 2,588.54 1,249.26 376.00 589.67 285.02 2,499.96
Pavley Calculations ‐ Baseline Mitigated 0.00 0.00 0.00 0.00 0.00 0.00 0.00
U.S. EPA assumption that GHG emissions from other pollutants ‐ CH4, N20, and hydrofluorcarbons (HFCs) from leaking air conditioners account for 5 percent of emissions from vehicles, after accounting for global warming potentail of each GHG.
Transportation
3 of 4
Unmitigated CO2 (metric tpy) CH4 (metric tpy) N2O (metric tpy) CO2e (metric tpy) % of Total
Transportation*: 3,167.59 76.92%
Area Source: 0.00 0.00 0.00 0.00 0.00%
Electricity: 563.04 0.00 0.00 563.95 0.00%
Natural Gas: 45.89 0.00 0.00 46.01 0.00%
Water & Wastewater: 6.31 0.00 0.00 6.32 0.00%
Solid Waste: 2.44 15.80 N/A 334.16 0.00%
Agriculture: 0.00 0.00 0.00 0.00 0.00%
Off‐Road Equipment: 0.00 0.00 0.00 0.00 0.00%
Refrigerants: N/A N/A N/A 0.00 0.00%
Sequestration: N/A N/A N/A N/A N/A
Purchase of Offsets: N/A N/A N/A N/A N/A
Total: 4,118.02 76.92%
* Several adjustments were made to transportation emissions after they have been imported from URBEMIS.
After importing from URBEMIS, CO2 emissions are converted to metric tons and then adjusted to account for the "Pavley"
regulation. Then, CO2 is converted to CO2e by multiplying by 100/95 to account for the contribution of other GHGs (CH4, N2O, and HFCs [from leaking air con
Finally, CO2e is adjusted to account for th low carbon fuels rule.
Mitigated CO2 (metric tpy) CH4 (metric tpy) N2O (metric tpy) CO2e (metric tpy) % of Total
Transportation*: 3,167.59 83.46%
Area Source: 0.00 0.00 0.00 0.00 0.00%
Electricity: 450.44 0.00 0.00 451.16 11.89%
Natural Gas: 36.71 0.00 0.00 36.81 0.97%
Water & Wastewater: 6.04 0.00 0.00 6.05 0.16%
Solid Waste: 0.98 6.32 N/A 133.66 3.52%
Agriculture: 0.00 0.00 0.00 0.00 0.00%
Off‐Road Equipment: 0.00 0.00 0.00 0.00 0.00%
Refrigerants: N/A N/A N/A 0.00 0.00%
Sequestration: N/A N/A N/A 0.00 0.00%
Purchase of Offsets: N/A N/A N/A 0.00 0.00%
Total: 3,795.27 100.00%
Detailed Results
4 of 4
APPENDIX C ENERGY EFFICIENCY PROJECTS
UCSF - Energy Efficency Projects / Greenhouse Gas Reductions
SEP # Project Name Savings - kWh Savings - Therm GHG Reduction
( MTCO2e )B-3027 Genentech Hall -MBCx 2,107,045 200,550 1,672B-3576 Parnassus Steam Trap Retrofit 0 141,700 752B-3585 MCB Data Center - Return Air Retrofit 264,500 0 76B-3586 MCB Data Center - Server Virtualization 86,700 0 25B-3069 Mission Bay Housing - Light Retrofit 37,106 0 11B-3578 HSIR East - Building Exhaust Fan VFD 463,005 0 134B-3577 MCB Boiler Replacement 0 14,000 74B-3575 Hunters Point Boiler 0 4,480 24B-3574 HSIR East Main Manifold VFD 485,471 0 140B-3573 HSIR HW Pumps VFD 178,849 0 52B-3571 3Way - 2Way Chilled Water Valve 207,256 0 60B-3031 HSIR East - MBCx 963,758 136,764 1,004B-3032 HSIR West - MBCx 1,090,875 154,802 1,136B-3021 MCB - Chiller Replacement 432,266 0 125B-3570 MCB VFD System 4.2 438,542 0 127B-3100 HSIR T-12 to T-8 47,489 0 14B-3094 Oyster Point Light Retrofit 164,765 0 48B3579 515 Spruce Light Retrofit - Med Center 14,503 0 4B-3582 100 Buchannan Light Retrofit 77,108 0 22B-3546 Koret Vision _ Light Retrofit 125,506 0 36B-3581 PCUP Air Compressor 228,724 0 66B-3580 HSIR, MedSci, ClinSci - VacPmp VFD 275,667 0 80B-3583 Mt.Zion -Vivarium 243,638 23,306 194B-3080 Parnassus Refrigerator Replacement 43,404 0 13B-3572 HSIR East & West ( T-12 to T-8 ) 191,533 0 55B-3078 HSIR Freezer Replacement 77,282 0 22B-3083 Work Station Power Mgmt - Phase 1 500,000 0 144B-9050 OASIS - 3Par T400 Installation 35,416 0 10B-3590 OASIS - Data Center Storage Virtualization 72,966 0 21B-3588 MCB - VFDs 2.2 & 3.1 243,000 22,200 188B-3589 PC Power Mgmt - Phase 2 600,000 0 173B-3587 Koret Vision - VFDs AHU 1,2,3 259,000 47,000 324B-3034 Byers Hall MBCx 515,282 13,208 219B-3026 PSSRB MBCx 251,029 18,372 170B-3029 MCB MBCx 527,422 76,987 561B-3025 Laurel Heights MBCx 370,180 21,576 221B-3016 LPPI MBCx 70,974 21,769 136B-3008 Library MBCx 326,188 13,514 166B-3013 Medical Sciences 713,942 140,554 952B3011 Millberry Union Fitness Center - MBCx 433,848 15,734 209B-3012 Clinical Science MBCx 223,840 32,573 237B-3019 School of Nursing MBCx 79,155 18,000 118B-3028 Community Center 291,879 26,654 226
Total = 13,759,113 1,143,743 10,039