Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
DELHI JAL BOARD (DJB)
THE REPUBLIC OF INDIA
FINAL REPORT
ON
THE ASSISTANCE RELATED
TO
DELHI WATER SUPPLY IMPROVEMENT PROJECT
MARCH 2018
JAPAN INTERNATIONAL COOPERATION AGENCY
T E C I N T E R N AT I O N A L C O . , LT D .
T S S T O K Y O W AT E R C O . , L T D .
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
i
Location Map of Project AreaChandrawal WTP Command Area (Output 1)
SCADA Pilot Project Area (Output 2)Entire Delhi (Output 3)
Delhi
Chandrawal WTP Command Area
SCADA Pilot Project Area
Pitampura
Yamuna
River
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
ii
Layout Plan of Chandrawal WTP Command Area
Central
West
East
TransmissionPipe
Drainage
Railway
Reservoir
WTP
Yamuna River
Chandrawal WTP Phase II
Chandrawal WTP Phase I
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
iii
Organization Chart of Delhi Jal Board
Chai
rper
son
No
n-O
ffic
ial
Mem
ber
s
Vic
eC
hai
rper
son
Ex
-Off
icio
Mem
ber
sC
EO
Mem
ber
(Adm
inis
trat
ion
)
Mem
ber
(Fin
ance
)A
dd
itio
nal
CE
OM
ember
(Wat
erS
up
ply
)
Mem
ber
(Dra
inag
e)C
VO
Sec
reta
ryD
JB
Dir
ecto
r
(Adm
inis
trat
ion
)D
irec
tor
(Fin
ance
)
Dir
ecto
r
(Rev
enu
e)R
efo
rmC
ell
Dir
ecto
ro
f
Vig
ilan
ce
Con
sult
ant
(PR
)
Ass
ista
nt
Com
mis
sio
ner
Dep
uty
Dir
ecto
r
(F&
A)
ED
PC
ell
Join
tD
irec
tor
(Rev
enu
e)E
EA
dd
itio
nal
Dir
ecto
r
of
Vig
ilan
ce
Ad
mn
Off
icer
Acc
oun
ts
Off
icer
Ass
ista
nt
Co
mm
issi
one
rD
epu
tyD
irec
tor
CE
(WW
)-I
CE
(WW
)-II
CE
(W)
Pro
ject
CE
(Eas
t)C
E(W
est)
CE
(Sou
th)
CE
(Cen
tral
&
Nor
th)
CE
(DR
)P
R-I
CE
(DR
)P
R-I
IC
E(S
DW
)
SE
(WW
)D
IR
(T&
QC
)S
E(W
W)
SE
(W)
PL
NG
SE
(W)
PR
JTS
E(E
ast)
SE
(NE
)S
E(W
est)
SE
(NW
)S
E(S
out
h)S
E(S
W)
SE
(Cen
t)S
E(N
ort
h)S
E(D
R)
PL
NG
SE
(DR
)
PR
W&
C
SE
(DR
)P
R
N&
NW
SE
(DR
)P
R
E&
NE
SE
(DR
)P
R
N&
NW
SE
(SD
W)
EE
(WW
)C
WA
EE
(WW
)E
EP
LN
GE
E(W
)
PR
JTE
E(E
ast)
EE
(NE
)E
E(W
est)
EE
(NW
)E
E(S
ou
th)
EE
(SW
)E
E(C
ent)
EE
(No
rth)
EE
(P)
EE
(C)
DR
EE
(C)
DR
EE
(C)
DR
EE
(C)
DR
EE
(SD
W)
AE
AC
WA
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
AE
Pro
ject
Dir
ecto
r
Pro
ject
Man
ager
Ou
tput
1O
utp
ut1
and
3O
utp
ut2
Ou
tput
1
:P
erso
nin
char
geof
the
Pro
ject
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
iv
PICTURES
Common to all Activities
Kickoff Meeting19 June 2013
Mid Term Review Meeting3 August 2016
OUTPUT 1
Field Survey: Connection of water supplypipelines
Field Survey: Condition of removed pipes(20 years of use)
Field Survey: Water supply pipelines in Narainaarea
Field Survey: Trenchless road crossingconstruction observed in Delhi
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
v
OUTPUT 2
DJB zonal office in PitampuraPitampura UGR & BPS
Pump room
Pitampura UGR & BPSSCADA operation room
Private Roof Tank in the Pilot Project Area
House meters in the Pilot Project Area House meter in the Pilot Project Area
Valve Pit in the Pilot Project Area Valve Pit in the Pilot Project Area
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
vi
OUTPUT 3
Meeting with CEO of DJB Meeting with JICA India
Meeting with DJB Mapping CellMeetings among DJB, Japanese ODA loan
consultants and JET 12 March 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
vii
Final Reporton
The Assistance Related to Delhi Water Supply Improvement Project
Location MapsPictures
TABLE OF CONTENTS
CHAPTER 1 OUTLINE OF THE PROJECT ...............................................................................1-1
1.1 Background and Issue............................................................................................................1-1
1.2 “Assistance Project” and Japanese ODA Loan Project..........................................................1-2
1.3 Overall Goal and the Project Purpose....................................................................................1-3
1.4 JET and DJB Counterpart ......................................................................................................1-3
1.5 Equipment..............................................................................................................................1-5
1.6 Joint Coordination Committee (JCC) Meeting ......................................................................1-8
1.7 C/P Training in Japan...........................................................................................................1-12
1.8 Achievement of the Activities Suggested in the Joint Mid-Term Review ...........................1-13
1.9 Achievement of the Project Purposes (Outlie of results of joint terminal evaluation) ........1-17
CHAPTER 2 OUTPUT 1 (DJB’s capacity to manage data and information on watersupply facilities in Chandrawal command area is strengthened)....................................2-1
【1-1】Obtain necessary information for detailed design of Delhi water supply improvement
project. ..................................................................................................................................2-4
【1-2】Carry out survey and GIS mapping of WTPs, UGEs and BPSs, and verification of the data
(location and size, etc.) of pipes in Chandrawal WTP command area................................2-22
CHAPTER 3 OUTPUT 2 (DJB’s capacity to monitor and control the water distributionfor equitable distribution and non-revenue water management is upgraded)...............3-1
【2-1】Review SCADA application in DJB....................................................................................3-7
【2-2】Introduce Japanese experience and system to DJB..............................................................3-8
【2-3】 Implement pilot project for equitable distribution and non-revenue water (NRW)
monitoring by applying SCADA ..........................................................................................3-9
【2-4】Identify issues that need to be addressed for further enhancement of equitable distribution
and NRW monitoring..........................................................................................................3-50
CHAPTER 4 OUTPUT 3 (Draft of scenarios for stage wise development of GIS/RMSapplication in DJB is prepared)..........................................................................................4-1
【3-1】Review existing DJB’s management policy/vision and business plan ................................4-2
【3-2】Clarify the issue to be tackled to achieve the above-mentioned policy /vision and plan.....4-6
【3-3】Review GIS development and RMS in DJB......................................................................4-11
【3-4】Study Japanese experience and system of GIS and RMS..................................................4-18
【3-5】Draft GIS and RMS application scenario in DJB for year 2021........................................4-19
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
viii
【3-6】Draft GIS and RMS development scenario in DJB for year 2021.....................................4-21
【3-7】Draft the guideline as an action plan for realization of scenarios......................................4-23
CHAPTER 5 ISSUE, INNOVATIVE APPROACH, AND PRECEPT OF THE PROJECTIMPLEMENTATION..........................................................................................................5-1
5.1 Suggestion on Joint Work between JET and DJB..................................................................5-1
5.2 Disclosure of Guideline and Manual .....................................................................................5-1
5.3 Work Schedule Management .................................................................................................5-2
5.4 Construction of Chamber.......................................................................................................5-3
5.5 Hydraulic Isolation of DMA..................................................................................................5-4
5.6 Calculation of NRW Ratio .....................................................................................................5-4
CHAPTER 6 ACHIEVEMENT OF PROJECT PURPOSE.........................................................6-1
6.1 Annual Maintenance Contract of SCADA ............................................................................6-1
6.2 Trial for Equitable Water Distribution ...................................................................................6-2
6.3 Monitoring of NRW Ratio .....................................................................................................6-2
6.4 Involvement of Training Cell.................................................................................................6-3
6.5 Dissemination Seminar ..........................................................................................................6-3
6.6 Acceleration of DPRs Finalization ........................................................................................6-3
CHAPTER 7 SUGGESTION TO ACHIEVE OVERALL GOAL ...............................................7-1
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
ix
LIST OF TABLES
Table 1-1 Implementation Structure of the Project Implementation ..........................................1-4
Table 1-2 Equipment and Materials Procured by JET ...............................................................1-6
Table 1-3 Equipment and Materials Procured by JICA .............................................................1-6
Table 1-4 Equipment and Materials Procured by DJB...............................................................1-8
Table 1-5 JCC Meeting Dates and Agenda ................................................................................1-8
Table 1-6 Improvement of Chambers.......................................................................................1-13
Table 1-7 Suggested Items at the Joint Terminal Evaluation and Achievement.......................1-17
Table 2-1 Surveyed Length of Pipe Alignment Survey Regarding Activity 1-1-5 and Road
Survey Regarding Activity 1-1-7............................................................................2-19
Table 3-1 Salient Features of DMA ...........................................................................................3-2
Table 3-2 Outline of the SCADA system ...................................................................................3-2
Table 3-3 Planned/Actual Period of Activities in Output 2........................................................3-4
Table 3-4 Situation of SCADA Use in DJB ...............................................................................3-8
Table 3-5 Introduction of Japanese Experience and System about SCADA..............................3-9
Table 3-6 Results of Test Pit Survey ........................................................................................3-13
Table 3-7 Characteristic of Control Valve................................................................................3-15
Table 3-8 Characteristic of Flow Meters..................................................................................3-16
Table 3-9 Procurement Items of JICA Side and DJB Side.......................................................3-22
Table 3-10 Number of Connection as of Dec. 2013.................................................................3-24
Table 3-11 Billed Consumption based on RMS Data as of Dec. 2013 ....................................3-25
Table 3-12 Steps of Tender Process..........................................................................................3-27
Table 3-13 Work Schedule of SCADA Installation by RDS....................................................3-27
Table 3-14 Improvement Works...............................................................................................3-29
Table 3-15 Water Ingress into Chambers .................................................................................3-32
Table 3-16 Countermeasures against Water Ingress to Chambers............................................3-33
Table 3-17 Participants in the Training ....................................................................................3-39
Table 3-18 Baseline of the Average Outlet Water Pressure (kg/cm2) of DMAs.......................3-43
Table 3-19 Baseline of the Avg. Volume/Connection (m3/day) of DMAs................................3-43
Table 3-20 Values of Average Pressures to DMAs after SCADA Operation ...........................3-44
Table 3-21 Average Inflow to DMA with Connection Number in DMA after SCADA
Operation for Equitable Water Distribution............................................................3-44
Table 3-22 Result of the Door to Door Survey ........................................................................3-45
Table 3-23 Billed Water Volume and Number of Connection in 2017.....................................3-47
Table 3-24 Calculated NRW Ratio...........................................................................................3-47
Table 4-1 Method of Preparing for Asset Management Guideline Effectively..........................4-9
Table 4-2 Comparison of DSSDI and NIC Data related to the Layer Configuration and
Input Status .............................................................................................................4-15
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
x
Table 4-3 Status of Attribute Data by Layer.............................................................................4-16
Table 4-4 Number of Household Records in DSSDI ...............................................................4-17
Table 4-5 Contents of RMS......................................................................................................4-18
Table 6-1 Suggested Items at the Joint Terminal Evaluation and Achievement.........................6-1
LIST OF FIGURES
Figure 2-1 Original Tasks and Actual/Tasks in Output 1 ...........................................................2-3
Figure 2-2 Methods for Internal/External Investigation on Pipe and Pipe Connection .............2-6
Figure 2-3 Inspection Sheet of Test Pit ......................................................................................2-7
Figure 2-4 Comparison of DMA Boundaries in the MP and This Review ..............................2-10
Figure 2-5 Comparison of UGR Command Area in the MP and in This Review....................2-11
Figure 2-6 Comparison of Transmission Pipelines in MP (Left) and Reviewed Pipelines
(Right).....................................................................................................................2-12
Figure 2-7 Confirmation of the Existing Pipeline Information................................................2-13
Figure 2-8 Summary of Field Meetings and Map Correction Activities..................................2-16
Figure 2-9 Drawing of Result of Pipe Alignment Survey Regarding Activity 1-1-5 ...............2-20
Figure 2-10 Drawing of Result of Road Survey Regarding Activity 1-1-7 .............................2-21
Figure 2-11 Topographical Survey Area of Chandrawal I and II WTPs ..................................2-22
Figure 3-1 DMAs in Pitampura Pilot Project Area ....................................................................3-1
Figure 3-2 Schematic Diagram of Pipe-Network in Pilot Area (Detailed Planning Survey) ...3-10
Figure 3-3 Schematic Diagram of Revised Pipeline Network as of July 2013 ........................3-11
Figure 3-4 Schematic of Pipe Network (Location of 3-planned DMA)...................................3-12
Figure 3-5 Modified Points by Test Pit Survey........................................................................3-14
Figure 3-6 Pipe Jointing Works................................................................................................3-17
Figure 3-7 Sample of Couplings ..............................................................................................3-17
Figure 3-8 Schematic of SCADA System................................................................................3-18
Figure 3-9 Composition of SCADA System............................................................................3-19
Figure 3-10 Measurement Points in the Pilot Area ..................................................................3-20
Figure 3-11 SCADA Graphics Window of Existing UGR.......................................................3-21
Figure 3-12 Local Measurement Stations ................................................................................3-21
Figure 3-13 Pitampura UGR Command Area (Sub-Locality wise) .........................................3-23
Figure 3-14 Work Schedule of SCADA (Original Plan, Revised Plans and Actual Progress).3-26
Figure 3-15 Demonstration chamber........................................................................................3-34
Figure 3-16 Countermeasures to Chambers Constructed by DJB............................................3-37
Figure 3-17 Improvement Works of Constructed Chambers by JET .......................................3-38
Figure 3-18 SCADA Overall Monitoring Screen.....................................................................3-40
Figure 3-19 UGR Monitoring Screen.......................................................................................3-41
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
xi
Figure 3-20 Measurement Point Monitoring and Operation ....................................................3-41
Figure 3-21 Example of Measurement Point Report................................................................3-42
Figure 4-1 Household Information and Customer Information ...............................................4-17
Figure 4-2 Drawing Showing only Water Facilities.................................................................4-20
Figure 4-3 Drawing of Simplification and Standardization .....................................................4-21
APPENDICES
Appendix 1 Project Design Matrix (PDM ver.1 to 5)
PDM ver.1…………………………………………………………..…………A1-2PDM ver.2…………………………………………………………..…………A1-3PDM ver.3…………………………………………………………..…………A1-4PDM ver.4…………………………………………………………..…………A1-5PDM ver.5…………………………………………………………..…………A1-6
Appendix 2 Project Flowchart (PO ver. 5)
Appendix 3 Work Breakdown Structure as of March 2018
Appendix 4 Dispatch of the Experts (Manning Schedule as of March 2018)
Appendix 5 Counterpart Training in Japan
Appendix 6 Equipment Purchased in the Project and Transferred to DJB (Certificate of
Hand-Over with List)
Appendix 7 Progress Meeting of SCADA Procurement
Appendix 8 Minutes of Meeting on JCC Meeting
Work Plan……………………………………………………………………...A8-21st JCC…….……………………………………………………………….…..A8-62nd JCC…………………………………….………………………………....A8-26Memorandum at Training in Japan…..………………………………………A8-353rd JCC………………………………………………………………………..A8-384th JCC………………………………………………………………………..A8-51MM for Chamber Improvement…….…………………………………..……A8-655th JCC………………………………………………………………………..A8-746th JCC………………………………………………………………………..A8-887th JCC………………………………………………………………………..A8-978th JCC……………………………………………………………………....A8-112
Appendix 9 Summary of 6 Times Seminar and Presentation Materials
1st Seminar……..………………………………………………………..……..A9-12nd Seminar………..……………………………………………………….....A9-313rd Seminar………….………………………………………………………..A9-644th Seminar………………………………………………………………….A9-1005th Seminar…………….………………………………………………..…..A9-1536th Seminar………….…………………………………………………..…..A9-184
Appendix 10 Manual (SOP) and Guideline of Equitable Distribution and Non-Revenue Water
Management by Using SCADA
Manual (SOP)…………………….……………………………………….….A10-2
Guideline……………………………….……………………………..…….A10-66
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
xii
Technical Cooperation Products
Report on Pipe Replacement Criteria including Proposed
Drawing of Renewal and New Pipelines............................. Attached to the Progress Report (No.4)
Report on Pipe Alignment and Crossings & GIS Data
Creation including Proposed Drawing................................ Attached to the Progress Report (No. 4)
Report of GIS/RMS Application and Development
Scenario in DJB for Year 2021............................................ Attached to the Progress Report (No.3)
Asset Management Guideline for DJB................................ Attached to the Progress Report (No. 4)
LIST OF ABBREVIATIONS
Organization
ADB Asian Development Bank
CPWD Central Public Works Department
DDA Delhi Development Authority
DJB Delhi Jal Board
DEA Department of Economic Affairs, Ministry of Finance
JBIC Japan Bank of International Cooperation
JET JICA Expert Team
JICA Japan International Cooperation Agency
MCD Municipal Corporation of Delhi
LDI Leakage Detection and Investigation Unit
MoEF Ministry of Environment and Forests
MoF Ministry of Finance
MoUD Ministry of Urban Development
NCTD National Capital Territory of Delhi
NCR National Capital Region
NDMC New Delhi Municipal Council
NIC National Informatics Centre
NGO Non-Government Organization
PDA Planning and Development Authorities
PWD Public Works Department
WB World Bank
WHO World Health Organisation
Position
A.E. Assistant Engineer
C.E. Chief Engineer
C.E.O. Chief Executive Officer
C/P Counterpart
CVO Chief Vigilance Officer
EDP Enforcement Department
E.E. Executive Engineer
J.E. Junior Engineer
S.E. Superintending Engineer
Z.E. Zonal Engineer
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
xiii
Technical
ACP Asbestos Cement Pipe
BOT Build Operate Transfer
BPS Booster Pumping Station
CIP Cast Iron Pipe
DIP Ductile Iron Pipe
DPR Detailed Project Report
DSSDI Delhi State Spatial Data Infrastructure
DMA District Metering Area
DR Drainage
GIP Galvanized Iron Pipe
GIS Geographical Information System
GPS Global Positioning System
gpcd Gallon per capita per day
MGD Million Gallons per Day
MP Master Plan
lpcd Liter per capita per day
JCC Joint Coordination Committee
KNO K-number
NRW Non Revenue Water
ODA Official Development Assistance
O&M Operation and Maintenance
OHT Overhead tank / water tower
OJT On-the-Job Training
PDM Project Design Matrix
PLC Programmable Logic Controller
PO Plan of Operation
PS Pumping Station
RMS Revenue Management System
Rs Rupee
RTU Remote Terminal Unit
SCADA Supervisory Control And Data Acquisition
SDW Sewage Disposal Works
SIM Subscriber Identity Module
SOP Standard Operational Procedure
TECI TEC International Co. Ltd.
ToR Terms of Reference
TSS Tokyo Suido Service Co. Ltd.
UGR or UR Underground Reservoir
UPS Uninterruptible Power Supply
WBS Work Breakdown Structure
WTP Water Treatment Plant
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-1
CHAPTER 1 OUTLINE OF THE PROJECT
This report describes the activities of this Project carried out during June 2013 - March 2018 (4 years
and 10 months).
1.1 Background and Issue
The National Capital Territory of Delhi1 has high rate of non-revenue water (hereinafter referred to as
NRW). Water supply system is intermittent; water is supplied for a few hours in the morning and
evening. The current NRW level is estimated to be in between 40 to 50%. Inappropriate operational
management and aging of facilities are the main causes of this issue. Delhi has five major and a few
other smaller water treatment plants catering to a population of 16.7 million. Chandrawal Water
Treatment Plant (WTP) and its transmission and distribution systems are the oldest of them. This plant
was first constructed in 1937 and expanded later in 1950s.
Therefore, the necessity of upgrading the facilities is becoming more demanding. However, the
long-term asset management plan has not been formulated because of inadequate amount of data on
facilities and NRW. Moreover, there has been no proper maintenance management, and the analysis of
NRW and formulation of NRW reduction measures have not been conducted for long time. In addition
to postponement in upgradation, the disparity in water supply duration and pressure among areas is
worsening the water availability situation and NRW. The areas with higher water pressure have serious
water leakage problem. High NRW ratio also results into deteriorated financial situation that hinders
the accumulation of fund for facilities’ upgrade.
Under the situation described above, Delhi Jal Board (hereinafter referred to as “DJB”) is expected
to implement a Japanese ODA lone project based on the city development plan of Delhi Urban
Planning 2021 (Delhi Development Authority 2008). JICA contributed to the formulation of water
master plan (hereinafter referred to as “MP”) through Study on the Delhi Water Supply Improvement
Project.
The goal of the MP is to develop a rational water supply system to cater to increasing demand and to
mitigate the impact of water shortage. The target year of plan is 2021, which is same as the target year
of city development plan of Delhi. Specific goals and objectives of the MP are listed below.
(1) Equitable water supply (through introduction of 3-tier water distribution system and application
of SCADA)
(2) Development of water supply facilities for suburbs of Delhi
1 The National Capital Territory of Delhi consists of North Delhi, South Delhi, East Delhi, New Delhi, and Delhi
Cantonment. Except for the case which requires the individual name of Municipal Council, these are described as Delhi in
this report. In addition, DJB has the responsibility for water supply to North Delhi, South Delhi and East Delhi from WTPs,
and for bulk water supply only to New Delhi and Delhi Cantonment.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-2
(3) Demand control (through NRW reduction measures, etc.)
(4) Energy efficient system (through rational arrangement of water supply facilities, etc.)
(5) Achieving continuous water supply (through reduction of NRW, updating of customer
information data and linking to GIS system).
In general, these goals are consistent with the objectives of the 12 th Five-Year Plan of Government of
India (2012-2017)2 as listed below.
(1) 24 hours continuous water supply,
(2) Water supply to the entire urban population by 2017,
(3) Realization of equitable water supply, and
(4) Achievement of self-sustaining management of water utilities (Recovery of O & M cost from
collected tariff).
In the MP, all facilities related to water supply from WTP to the customer meters have been proposed
to be improved at the same time for areas covered by each WTP system.
1.2 “Assistance Project” and Japanese ODA Loan Project
According to the MP, with the prospect of reducing NRW and achieving equitable distribution, each
WTP command area is divided into three tiers: WTP to distribution reservoir, distribution reservoir to
District Metered Area (DMA) and inside of DMA. Subsequently, these three tiers are proposed to be
controlled and managed by Supervisory Control and Data Acquisition (SCADA) system.
Following to the MP, the Government of India requested for the Japanese ODA loan project named
Delhi Water Supply Improvement Project in Chandrawal WTP Command Area that was prioritized in
MP. The Japanese ODA loan project aims to improve the water supply service by rehabilitation and
improvement of the facilities under Chandrawal WTP area. There are 5 main WTPs in Delhi among
which the Chandrawal WTP is the oldest. It was first constructed in 1937 and later expanded in
1955/60 and supplies water to the core area of Delhi. Therefore, the necessity of upgrading the
facilities in the command area of this WTP is becoming more demanding. And as a result, Chandrawal
WTP command area has been selected by DJB to initially implement the improvement work with the
Japanese ODA loan.
The Japanese ODA loan project consists of 5 components as listed below.
Component 1: Reconstruction and renovation of treatment plant and installation of SCADA
Component 2: Construction and replacement of transmission and distribution systems in western
zone
2 The 12th Five-Year Plan was abolished in 2017. The plan has not been formulated after 2017.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-3
Component 3: Construction and replacement of transmission and distribution systems in central zone
Component 4: Construction and replacement of transmission and distribution systems in eastern zone
Component 5: Strengthening of GIS mapping
In relation to the Japanese ODA loan project, this Assistance Project named “The Assistance related to
Delhi Water Supply Improvement Project” (hereinafter referred to the Project) was agreed between
JICA and DJB to maximize the result of the Japanese ODA loan project by building the foundation for
the continuing the Project and strengthening the capacity of DJB.
1.3 Overall Goal and the Project Purpose
The overall goal is: “To achieve the equitable and continuous water distribution in the National Capital
Territory of Delhi, by improving the water supply network including service network to customers,
thereby contributing in upgrading citizen’s living standard”. This overall goal is the same as the goal
of the Japanese ODA loan project, which is set to be achieved in 2023, two years after the completion
of Japanese ODA loan project.
The Project’s purpose is “DJB’s capacity to implement, operate and maintain the Japanese ODA loan
project or “Delhi water supply improvement project” is strengthened”. This will enable smooth
implementation of the water supply services improvement in Delhi, through renovation of existing
water supply facilities and enhanced operation and management. The Japanese ODA loan project also
aims at achieving 24 hours continuous water supply and equitable and stable water supply services. To
achieve the above, activities under the Project were planned and implemented with the following 3
Outputs.
Output 1: DJB’s capacity to manage data and information on water supply facilities in Chandrawal
command area is strengthened.
Output 2: DJB’s capacity to monitor and control the water distribution for equitable distribution and
non-revenue water management is upgraded.
Output 3: Draft of scenarios for stage wise development of GIS/RMS application in DJB is prepared.
1.4 JET and DJB Counterpart
The Project team consisted of members of JICA Expert Team (JET) and DJB as shown in Table 1-1.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-4
Table 1-1 Implementation Structure of the Project Implementation
Projectposition
DJB/JET
Title Name Period assigned as C/P * Present designation
Projectdirector
Additional ChiefExecutiveOfficer/Director(Finance &Accounts)
Ms. NidhiSrivastava
2017/2 - 2018/3 Same as the title
Mr. NeerajSemwal
2015/8 - 2017/2 Out of DJB now
Mr. Amit Satija 2014/1 - 2015/8 Out of DJB now
Ms. NandiniPaliwal
2013/6 - 2013/12 Out of DJB now
Projectmanager
Chief Engineer(Water) Projects
Mr. Rajesh Mittal 2016/5 - 2018/3 Same as the Title
Mr. R. S. Negi 2014/4 - 2016/5 Member (Drainage)
Mr. J.P. Goel 2013/6 - 2014/3 Out of DJB now
Deputyprojectmanager
SuperintendingEngineer (Project)Water-III
Mr. Ajay Kumar 2016/5 - 2018/3 Same as the Title
Mr. Vikram Singh 2013/6 - 2016/5
Chief Engineer(Drainage)Project-II/SE MappingCell
JETChiefAdviser
ChiefAdvisor/WaterSupply Planning
Mr. KazufumiMomose
2013/6 – 2018/3 TECI
Output 1
SuperintendingEngineer (WW)-I
Mr. M K Hans 2017/7 – 2018/3 Same as the Title
Mr. A KChaudhary
2016 - 2017 Out of DJB Now
Mr. R.K. Bhalla 2013/6 -2015 Out of DJB Now
SuperintendingEngineer (Central)
Mr. MahendraKumar Jain
2015 - 2018/3 Same as the Title
Mr. Ajay Gupta 2013/6 - 2015SuperintendingEngineer (Project)Water-II
SuperintendingEngineer (Project)Water-III
Mr. Ajay Kumar 2016/5 - 2018/3SuperintendingEngineer (Project)Water-III
Mr. Vikram Singh 2013/6 - 2016/5
Chief Engineer(Drainage)Project-II/SE MappingCell
ExecutiveEngineer(Mapping)
Mr. ChanderPrakash
2013/6 - 2018/3 Same as the Title
Deputy ChiefAdviser/Pipe-Network 2
Mr. Minoru Ikei 2013/6 – 2018/3 TECI
Pipe-Network (1) Mr. Phatta Thapa 2013/6 – 2018/3 TECI
GIS Mapping 1 Mr. Sanjay Prasad 2013/6 – 2018/3 TECI
ProjectCoordinator/ GISMapping 2
Mr. KatayamaAlok kumar
2013/6 – 2017/1 TECI
GIS Mappingassistant
Mr. Yuhei Ito 2013/6 – 2017/1 TECI
Output 2
Chief Engineer(West II)
Mr. RameshThakur
2016/3 - 2018/3 Same as the Title
Superintending Mr. P K Jain 2016/3 - 2018/3 Same as the Title
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-5
Projectposition
DJB/JET
Title Name Period assigned as C/P * Present designation
Engineer (NorthWest)
Mr. RameshThakur
2013/6 - 2016/3 Chief Engineer (West)
SuperintendingEngineer (Project)Water-III
Mr. Ajay Kumar 2016/5 - 2018/3 Same as the Title
Mr. Vikram Singh 2013/6 - 2016/5
Chief Engineer(Drainage)Project-II/SE MappingCell
ExecutiveEngineer (NW) III
Mukesh Jindal 2016/6 – 2018/3 Same as the Title
V. K. Singh 2013/6 - 2016/5Transferred to otherarea within DJB
ExecutiveEngineer (E&M)W&S N/W
Mr. U. K. Rastogi 2015/8 - 2018/3 Same as the Title
Mr. Yash Prakash 2013/6 - 2015/8Executive Engineer(E&M) W&S-C/N
DMA Mr. Koichiro Azui 2013/6 – 2018/3 TECI
SCADAMr. ManabuFukushima
2013/6 – 2018/3 TSS
NRW AnalysisMr. WataruShimizu
2013/6 – 2018/3 TSS
Leak Detection 1 Mr. Hiroki Horie 2013/6 – 2014/8 -
Leak Detection 2Mr. TetsuoHayashi
2013/6 – 2014/8 -
Civil 1Mr. Eizou Kodera 2016/4 – 2017/3 -
Mr. Saito Noboru 2017/4 – 2018/3 TSS
Civil 2Mr. HiroshiKojima
2016/4 – 2018/3 TSS
Output 3
Director(Revenue)
Ms. NidhiSrivastava
2015/8 - 2018/3 Same as the Title
Mr. B. S. Jaglan 2013/6 - 2015/8 Out of DJB now
SuperintendingEngineer(Mapping)
Mr. Vikram Singh 2013/6 - 2018/3
Chief Engineer(Drainage)Project-II/SE MappingCell
ExecutiveEngineer(Mapping)
Mr. ChanderPrakash
2013/6 - 2018/3 Same as the Title
Water supplyManagement
Mr. YoichiYamamoto
2013/6- - 2015/3 -
GIS ApplicationMr. HiroshiIzumoto
2013/6- - 2015/3 -
* From the Project initiation as of June 2013
1.5 Equipment
Equipment and materials shown in the Table 1-2, 1-3 and 1-4, were provided to achieve the Project
purpose.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-6
(1) Equipment and Materials Procured by JET
Table 1-2 Equipment and Materials Procured by JET
SN Description Nos. Place
1
PC (Desktop)OS: Windows 7 ProfessionalOffice: Microsoft Office 2010 ProfessionalCPU: Core i7HDD: 500GB, Memory 8GB24 inch screen, Keyboard, Mouse, including Anti-VirusSoftware
21 in JET Room and1 in Mapping Cell, DJB
2UPS CS 650, APCfor Desktop PC mentioned above
2 Same as above
3Printer (A3 inkjet)HP-7500, Color
1 JET Room
4PlotterHP Design Jet 510 42inch
1 DJB Mapping Cell
5 GPS/ Trimble Juno 3B 1 JET Room
6 Arc Pad ver10.0 1 JET Room
7 Arc GIS/ Arc View Ver 10.1 1 DJB Mapping Cell
8 Auto CAD 2014 1 JET Room
9Pipe LocatorMXL DLV, Multi Frequency High Precision Pipe andCable Locator
4 JET Room
10Pipe thickness gaugeMX-5 DL Material Thickness Gauge
2 JET Room
Improvement Works of Chambers (for Output 2)
11Demonstration Chamber(Construction of Demonstration Chambers andConfirmation of Recommended Countermeasures)
1Pitampura Sewage PumpingStation
12Improvement Works of Chambers(Improvement of Gaps in Manhole and Opening)
14 Pilot Project Area in Pitampura
(2) Equipment and Materials Procured by JICA
The required equipment for the pilot project in Pitampura was provided as shown in Table below.
Table 1-3 Equipment and Materials Procured by JICA
SN Description Nos. Place(a) SCADA Centre and Wirings
1 SCADA System installed
(i)Server PC (Windows server with peripheral devices)(SCADA Server, Data Collection Server)
2 Control Room, Pitampura UGR& Booster Pumping Station(BPS)
(ii)
Desktop PC (PC, 21 LCD monitor)(Reporting system, Pipe Network Calculation)
2
Desktop PC (PC, 21 LCD monitor and color LBP)CE office and EE office at Pitampura in addition to atPitampura UGR & BPS
3CE office and EE office atPitampura in addition to atPitampura UGR & BPS
(iii) UPS (1hour protection) 3
(iv) SCADA application software 1
Control Room, Pitampura UGR& Booster Pumping Station(BPS)
(v) PLC & I/O (A/I and D/I at UGR) 1
(vi) Upgrading existing PLC & MCCB panel 1
(vii) Data Collection Application Software 1
(viii) Reporting System Application Software 1
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-7
SN Description Nos. Place(ix) Pipe Network Calculation Application Software 1
(x)Router, Ethernet Switch, and other network equipment,etc.
3
(xi) Printer and Power Branch panel 3
2 Instrumentation
(i) Flow meterUse of
Existingone
Under Ground Reservoir(UGR)/Booster Pumping Station(BPS)
(ii) Level meterUse of
Existingone
(iii) Pressure (Semiconductor strain gauge)Use of
Existingone
3 Wiring works(i) Wiring works of SCADA system at UGR 1 UGR
(ii) Wiring works and Kiosks for the SCADA system 14 DMAs and Control Points
(b) Pressure Gauges
(i) Pressure Gauges 21 In chamber
(c) SCADA Components
(i) PLC with peripheral devices 14
(ii) Valve Control circuit, outdoor type 14
(iii) Wireless transmission unit 14
(d) Control Valves with Actuators
(i) Pipe diameter 100mm 1
(ii) 150mm 3
(iii) 200mm 2
(iv) 250mm 2
(v) 300mm 1
(vi) 500mm 2
(vii) 800mm 1
(viii) 900mm 1
(e) Flow meters
(i) Pipe diameter 100mm 1
(ii) 150mm 3
(iii) 200mm 3
(iv) 250mm 2
(v) 300mm 1
(vi) 500mm 2
(vii) 800mm 1
(viii) 900mm 1
(f) Electricity leakage protection system
(i) Water level alarm system 14
(ii) Earth leakage circuit breaker 14Note: SCADA (Supervisory Control And Data Acquisition), PLC (Programmable Logic Controller), RTU(Remote Terminal Unit), F (Flow Meter), M (Motor for Control Valve), Q (Quantity; Water flow quantity), P(Pressure), Existing (using for the Project)
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-8
(3) Equipment and Materials Procured by DJB
Table 1-4 Equipment and Materials Procured by DJB
No. Description Nos. Place
1Office and furniture for JET related to Outputs 1and 3
1 Office near DJB Headquarters Office
2 Office and furniture for JET related to Output 2 1 Office at DJB field office at Pitampura3 Office and furniture in Pitampura PS 1 SCADA control room at Pitampura PS
4Chambers for containing SCADA devices related toOutput 2
14 Chambers construction at 14 locations
5Work for improving water tightness of chambers(inside construction. Waterproofing work) related toOutput 2
14Improvement work of the constructedchambers
JET Office JET office at Pitampura
1.6 Joint Coordination Committee (JCC) Meeting
Items discussed/ agreed are shown in the Table 1-5 while minutes of meetings are attached in
Appendix -8. PDM was revised several times and its change is shown in the Appendix-1. Prior to the
6th JCC meeting, JICA and DJB agreed to take countermeasures against water ingress to the chambers
with extension of the Project period on 10 December 2015.
Table 1-5 JCC Meeting Dates and Agenda
1st JCC 2nd 3rd 4th 5th 6th 7th 8th
Items Day30th Aug.
2013
27th Aug.
2014
26th Mar.
2015
24th Sep.
2015
10th Mar.
2016
4th Aug.
2016
29th Aug.
2017
29th Jan.
2018
GENERAL ○
Progress of the Japanese
ODA loan project○ ○ ○
Confirmation of PDM ○ ○ ○ ○ ○
Confirmation of PO ○ ○ ○ ○ ○
Logistics ○
Output 1 and Output3 ○ ○
Output 2
Extension of the Project
Duration○
Construction of ○ ○
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-9
1st JCC 2nd 3rd 4th 5th 6th 7th 8th
Items Day30th Aug.
2013
27th Aug.
2014
26th Mar.
2015
24th Sep.
2015
10th Mar.
2016
4th Aug.
2016
29th Aug.
2017
29th Jan.
2018
Demonstration
Chamber
Improvement Works to
Chambers and SCADA
System (Demarcation of
responsibility)
○ ○
Technology Transfer
(and Sharing knowledge
and technology with the
Indian side)
○ ○ ○ ○
SCADA Operation by
DJB○ ○ ○ ○
Utilization of the pilot
SCADA system after
completion of the
Project
○ ○ ○
Operation and
Maintenance of
Pitampura Training
Centre for SCADA
system
○ ○ ○
Billing Data and NRW
works○ ○ ○ ○ ○
(1) 1st JCC Meeting (30 August 2013)
The JCC approved overall goal, the Project purpose, PDM (ver.1) and 1 st year Plan of Operation (PO).
It further agreed on items of supply, installation and construction works for output 2 by Japanese and
Indian sides (Table 3-9).
1st JCC Meeting
(2) 2nd JCC Meeting (27 August 2014)
After discussion on the progress of the activity in the 1 st year and activity plan in the 2nd year, 2nd year
PO was agreed. Revision of PDM (ver. 2) was also agreed where determination date of the Project
indicator was deferred due to delay in activity of Output 2.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-10
2nd JCC Meeting (1) 2nd JCC Meeting (2)
(3) 3rd JCC Meeting (26 March 2015)
Acceleration of the Japanese ODA loan project was discussed mainly in this meeting. Trial pits and
pipe cutting works to prepare pipe replacement criteria were noted to be behind the schedule due to
delayed approval of road cuttings. In order to accomplish this on time, number of investigation of
internal/external condition of pipe was reduced.
(4) 4th JCC Meeting (24 September 2015)
After discussion on the progress of the activity in the 2nd year and activity plan in the 3rd year, 3rd
year’s PO was agreed. It was confirmed that the activities of Outputs 1 and 3 were completed in the 2 nd
year.
The activities of first term of 3rd year (June 2015 to December 2015) were presented. Along with this
outcome and activities to be carried out in the second term of 3 rd year (January 2016 to June 2016)
were also described.
The materials and equipment to be procured and installed by JICA (valve and flow meter) were
completed at 13 (out of 14) locations by the end of June 2015. Also, 13 out of 14 chambers were
constructed by DJB. However, after water ingress was observed in some of the constructed chambers
in July 2015 (on rainy days), DJB requested JICA to implement the countermeasures. Revision of
PDM (ver. 3) was also agreed where determination date of the Project indicator was deferred due to
delay in activity of output 2.
(5) 5th JCC Meeting (10 March 2016)
The MM concluded in December 2015 by JICA and DJB on methods and responsible organizations
for countermeasures was confirmed. As a result, the Project period was extended by 1 year and 10
months, ending in March 2018. The meeting also agreed on deferring determination date of the Project
indicator with a revision of PDM (ver. 4).
(6) 6th JCC Meeting (4 August 2016)
The activities and outcomes of 2nd term of 3rd year (January 2016 to June 2016) were presented.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-11
Activities to be carried out in the 1st half-term of 4th year (July 2016 to December 2016) were also
described and 4th year PO was agreed.
The outcome of mid-term review conducted in August 2016 was reported and agreed. PDM (ver. 5)
was also agreed where the English expressions were modified to be the same as in the original
document.
It was confirmed that the SCADA system would be transferred immediately after it is completely
installed, and DJB would operate and maintain it and utilize it as a training facility for equitable water
distribution and NRW calculation.
6th JCC Meeting
(7) 7th JCC Meeting (29 August 2017)
The activities and outcomes of 4th year were presented. Activities to be carried out in the 5 th year were
also described and 5th year PO was agreed. Countermeasures against ingress of water into some of the
chambers in July 2017 and delay in the installation of SCADA were mainly discussed in this meeting.
Strengthening measures of DJB and JET were discussed to avoid further delay of the Project. In
addition, the contents and agenda of the survey on operation guidance for the Project implemented in
August 2017 are as follows:
・ DJB’s responsibility of operation and maintenance of SCADA system and related facilities
・ Transfer of SCADA system to DJB immediately after completion of SCADA installation.
・ Demarcation of the work by DJB and JICA until handover of SCADA system to DJB by JICA
・ Operation and Maintenance of SCADA system by DJB
・ Inspection of SCADA system including the chambers at least two times every year
・ Utilization of the SCADA system as a Training Facility after the Project
・ Sharing Knowledge and Technology with the Indian Side
(8) 8th JCC Meeting (29 January 2018)
Report of joint terminal evaluation conducted in January 2018 was presented and agreed. The
remaining activities of the Project and activities of DJB beyond the Project period were confirmed.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-12
Lessons learned from the Project were also shared.
· Responsible person in SCADA operation in DJB
· Responsible section for ingress of water in the chamber during the Project implementation
· Transfer of SCADA system to DJB immediately after completion
· Operation and maintenance system of SCADA by DJB after transfer (outsourcing of operation
and maintenance)
· Time and number of SCADA's inspection including the chamber
· Utilize the SCADA system as a training facility
· Sharing technology within the DJB that prevents flooding in the chamber
1.7 C/P Training in Japan
Schedule and names of 8 DJB persons participated in the training held in Tokyo between 9 and 19
November 2014 is shown in Appendix-5. The themes of the training were 1) NRW reduction, 2)
utilization of GIS/RMS, and 3) equitable water distribution by SCADA system. The training was
assisted by Bureau of Waterworks of Tokyo Metropolitan Government, Hitachi, Ltd. and KUBOTA
Corporation. The training included visits to water supply facilities such as water treatment plant and
pipe laying sites, operation of GIS and SCADA and leak detection activities.
DJB showed interest in the followings;
・ More detailed knowledge on the latest GIS and SCADA technology
・ Operating modality of Tokyo Waterworks Bureau
・ Schemes of using subsidiary companies for efficient management of Tokyo Waterworks Bureau
・ Outsourcing of meter reading
Training in Japan (1): Visiting Misono WTP
12 November 2014Training in Japan (2): Meter reading
12 November 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-13
Training in Japan (3): Leak detection
12 November 2014Training in Japan (4): Closing Discussion
12 November 2014
Training in Japan (5): Introduction of SCADA (1)14 November 2014
Training in Japan (6): Introduction of SCADA (2)14 November 2014
1.8 Achievement of the Activities Suggested in the Joint Mid-Term Review
The joint Mid-Term Review was carried out from 18 th July to 4th August 2016. Achievements of the
activities suggested in the mid-term review report are shown below.
(1) Demarcation of responsibilities of improvement of the chambers
1) Suggestions and their Achievements
Improvement of chambers should be carried out by DJB and JET as shown in Table 1-6.
Table 1-6 Improvement of Chambers
Suggestion AchievementImprovement works ofthe valve chambersand the demarcation ofresponsibilities(starting October2016)
Stopping ingress of water into thechambers through the periphery ofmanhole/opening covers located on the topslab of the chambers is the responsibility ofthe JET
JET completed the work in September2017.
Stopping ingress of water into thechambers through the top slab and sidewalls of the chambers is the responsibilityof DJB. JET will provide technicalguidance of the method for improvement toDJB.
DJB completed the work in August 2017with JET’s assistance.
Construction of theremaining one valvechamber (startingOctober 2016)
DJB should construct the remaining onevalve chamber immediately after thecompletion of installation of a flow meterand control valve by RDS.
DJB completed the work in March 2017with JET’s assistance.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-14
(2) Quality control of chamber construction
1) Suggestion
It was relatively a new experience for DJB to construct chambers suitable for installing electrically
operated valves, and hence certain challenges were faced during the construction of the chambers.
Therefore, it is recommended that the top slab should be constructed post equipment installation as
there will be less opening required. In this way, water seepage to the chamber can be reduced. In
Japanese ODA loan project, learning from the lessons of this technical assistance, Reinforced Cement
Concreate (RCC) chambers with provision of a drain pit should be constructed.
2) Achievement
RCC chambers are designed in the Japanese ODA loan project.
(3) Ensuring sustainable utilization of the pilot SCADA system after the technical assistance
period by applying knowledge and techniques gained through the Project
1) Suggestion
DJB should continuously utilize the pilot SCADA system located in Pitampura as a training facility for
the enhancement of equitable water distribution and NRW monitoring even after completion of the
Project. The Project is designed with the aim of capacity building of DJB staff. It is expected for DJB
to maximize the utilization of the SCADA facility as the training site, where DJB staff from other
areas can visit and receive training from the trained staff about the methods of monitoring and control
of water flow and pressure for equitable water supply to DMAs. Therefore, it is recommended for DJB
C/Ps to start considering about how to disseminate, sustain and accumulate technical knowledge and
skills utilizing the training facility and manual with technical guidance by JET during Activity 2-3 &
2-4. For the remaining period of the Project, it is expected that DJB engineers could attend to the
participatory workshop, which consists of lecture and on-site practice rather than the simple
lecture-style seminar.
2) Achievement
JET together with SCADA supplier (RDS Company) gave the trainings to the engineers of civil and E
& M in the pilot project area twice in 2017. The engineers trained in the above gave an internal
training to DJB engineers in December 2017. The following long-term internal training program was
prepared by the training cell of DJB and approved as a part of annul training program by Addl CEO in
February 2018:
1) SCADA system for the training facility will be utilized.
2) Manual (SOP) and guideline prepared in the Project will be utilized.
3) About 10 engineers will be trained in one training program consisting of lecture and practice.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-15
4) Trainees include civil engineer, E & M engineer and meter inspectors.
5) Training cell will organize trainings under an annual training program.
(4) Adequate O&M of SCADA facility for ensuring quality control of service delivery
1) Suggestion
DJB should prepare for undertaking of responsibility for the operation and maintenance of the SCADA
system in Pitampura (Pitampura Training Facility for SCADA system), and secure necessary budget
and implementation structure for this purpose. Therefore, it is recommended that DJB will take up
O&M of the SCADA system by engaging a qualified agency after taking over the SCADA system
from JICA.
At the same time, DJB is also responsible for O&M of Chambers. From the technical point of view, it
is expected to conduct inspection at least once a year so that cleaning and dewatering can be done.
Therefore, by the end of the Project period, it is preferable that DJB engineers from Civil and E&M
units get necessary on-site training for the inspection process of chambers from JET since it requires
special process for ceiling of manhole, etc. to ensure water resistance.
2) Achievement
DJB is processing for a contract of SCADA O&M. However, the same has not yet been concluded. Its
progress at the time of writing the report is explained in section 6.1. DJB engineers from Civil and
E&M units got necessary on-site training for the inspection process of chambers from JET and
inspection methods are written in the guideline, Appendix 10.
(5) Consideration of the implementation process of the Project activities to enhance senior
officials’ involvement and sense of ownership towards the Project
1) Suggestion
In order to promote sustainability of the Project’s effects, it is essential to enhance the sense of
ownership towards the Project among senior officials of DJB. It is expected to further promote
information and opinion exchanges between DJB C/Ps and JET for the remaining period of the Project.
Therefore, it may be recommended for DJB C/Ps and JET to discuss and plan in order to increase
involvement of senior officials to the site before starting the pilot project at Pitampura (e.g. through
working together at the Pitampura site, OJT by JET, formulating working group for development of
manual, etc.). Moreover, in order to minimize the effect of personnel changes that frequently occur in
DJB, it is essential for JET to share their technical expertise and follow-up with more than one
engineer from Junior Engineers to Chief Engineers as well as operators through the remaining capacity
building activities.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-16
2) Achievement
JET could exchange opinions and views with CE、SE、EE、AE of the Project department and Mapping
Cell of DJB, C/P of Outputs 1 and 3.
Counterparts (C/P) other than the Project department involved in Output 2 are;
1) Operation and maintenance (civil): SE, EE, AE and JE in the Pitampura area
2) Operation and maintenance (E&M): SE, EE in the Pitampura area
3) Meter reading and bill collection: Addl CEO, Director (Revenue), Joint Director (Revenue),
Deputy Director (Revenue), Zonal Revenue Officer, Meter Inspector and Meter Readers
The above C/Ps involved in each stage of the Project are as follows.
Stage C/P
1 Planning of DMA Civil
2 Design of SCADA Civil and E & M
3 Supply and installation of SCADA E&M
4 Construction of chamber including improvement works to chamber Civil
5 SCADA operation Civil and E & M
6 NRW Civil, E & M and Revenue
SE (West), a nodal C/P of the output 2 and promoted to CE (West) in the later stage of the Project
contributed to the Project throughout the entire period.
Director (Revenue) also assumes Addl CEO position so that time is limited to exchange opinions
frequently. However, Addl CEOs as well as CEOs were eager to financial improvement of DJB and
understood DMA, SCADA and GIS well.
(6) Utilization of good practices and lessons of the technical assistance the Project to the
Japanese ODA loan project, etc.
1) Suggestion
It is recommended for DJB to continue reflecting good practices and lessons learned from the Project
to the Japanese ODA loan project in order to improve implementation process as well as other project
in an efficient manner (e.g. specifications of the chambers for preventing water ingress and electricity
leakage, the method of supervising civil works, process for obtaining road cutting permits from
different authorities, etc.). It is expected that impacts will be expanded throughout DJB.
2) Achievement
Good practices and lessons learned from the Project (e.g. specifications of chambers were changed to
RC concrete as mentioned in (2)) were transferred to the Japanese ODA loan consultants in August
2015 at the end of Output 1.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
1-17
1.9 Achievement of the Project Purposes (Outlie of results of joint terminal
evaluation)
Six (6) measures are suggested at the joint terminal evaluation in January 2018, to be taken by the end
of the Project. For the detail, refer to Chapter 6.
Table 1-7 Suggested Items at the Joint Terminal Evaluation and Achievement
No. Suggested Item Achievement Reference
1 Annual Maintenance of SCADA Not yet achieved.
2 Trial for the equitable water distribution Achieved. Output 2
3 Monitoring of the NRW ratio Achieved Output 2
4 Involvement of the Training Cell Achieved Output 2
5 Dissemination seminar Achieved Output 2
6 Acceleration of DPRs Finalization Not yet achieved.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-1
CHAPTER 2 OUTPUT 1 (DJB’s capacity to manage data and
information on water supply facilities in Chandrawal
command area is strengthened)
Output 1 was carried out to strengthen DJB’s capacity to manage data and information on water supply
facilities in Chandrawal WTP command area. More specifically, pipe data in the Chandrawal
command area were collected, and the compiled information transferred to the Japanese ODA loan
consultant, which in turn is carrying out detailed design of the Components 2 to 4 (The components of
pipe-network is divided into 3 areas; West, Central and East) of the Japanese ODA loan project.
Output 1 also included collection of information for making decision on pipe replacement, new pipe
alignment, pipe laying method etc. so that the Japanese ODA loan project consultants could decide and
carry out detailed design within a 2-year time frame (during December 2013 to November 2015).
Output 1 was carried out mainly by the following members.
DJB JET
In the original schedule, pipe information of the Central area (Component 3) was scheduled to be
transferred to the Japanese ODA loan consultant in the 1 st year for preparation of detailed design and
bidding documents, because this area is the biggest in terms of total pipe length and required
construction period. Then, in the 2nd year, pipe information of the remaining two (West and East) areas
where pipe length and construction periods were relatively shorter, was scheduled to be transferred.
However, an issue related to approval of the Project by DEA occurred and cooperation and
participation of DJB became weaker in the 1st year. Consequently, the result of survey for Central area
which was due to be completed by April 2014 got delayed, and was completed in December 2014. In
Chander Parkash
E. E. Mapping GIS
Ajay Gupta
S. E. (Central) WW-I Pipe-Network
Phatta Thapa
Pipe-Network (1)
Minoru Ikei
Pipe-Network (2)
Sanjay Prasad
GIS Mapping (1)
Alokkumar Katayama
GIS Mapping (2)
Ravindra Singh Negi
C. E. (Project) Pipe-Network/ GIS
Vikram Singh
S. E. (Project) W-III Pipe-Network/ GIS
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-2
connection with this delay, JET was concerned about the delay of the detail design in the Japanese
ODA loan project. In order to reduce the delay, JET and DJB took these measures: reduction of
number in road cutting and investigation of pipe exterior, and increase of pipe cutting and
investigation of pipe interior (refer to Activity (3) of 1-1-2). DJB’s cooperation was resumed after the
Project was approved by DEA. As a result, the survey result of West area which was due to be finished
in December 2014 was submitted almost on time. The result of East area was submitted as per
schedule in June 2015.
Results of investigation in all 3 areas (Central, West and East) titled "Report on Pipe Replacement
Criteria including Proposed Drawing of Renewal and New Pipelines" and "Report on Pipe Alignment
and Crossings & GIS Data Creation including Proposed Drawing" were submitted to DJB in August
2015, and the Output 1 was accomplished.
The implemented status in the Output 1 is shown in Figure 2-1.
Th
eA
ssis
tan
ceR
ela
ted
toD
elh
iW
ate
rS
up
ply
Imp
rovem
ent
Pro
ject
FIN
AL
RE
PO
RT
2-3
Fig
ure
2-1
Ori
gin
alT
asks
and
Act
ual
/Tas
ksin
Out
put
1
89
1011
121
23
45
67
89
1011
121
23
45
67
8
280
Sh
eets
280
Sh
eets
237
No
s.
221
No
s.
259
No
s.
50N
os.
680
km
Cen
tral
Dat
asu
bm
issi
on
680
km
Wes
tE
ast
Dat
asu
bm
issi
on
550
km
Dat
asu
bm
issi
on
135
Acr
e
Dat
asu
bm
issi
on
1,41
5km
Cen
tral
Wes
tE
ast
25N
os.
Cen
tral
Wes
tE
ast
15A
rea
Cen
tral
Wes
tE
ast
2se
t
Cen
tral
Wes
tE
ast
Act
ual
Pro
gre
ss
Rev
ised
Tas
k
Ori
gin
alT
ask
Co
nfi
rmat
ion
of
do
ub
tfu
lpip
esw
ith
DJB
Up
dat
eo
fP
ipe
info
rmat
ion
on
GIS
syst
em
Pro
cure
men
to
fro
adex
cav
atio
n
per
mis
sio
nth
rou
gh
DJB
Tes
tp
it&
Insp
ecti
on
Yea
ro
f20
1320
14
Qu
ota
tio
no
fro
adre
sto
rati
on
char
ge
fro
mM
CD
,etc
.
2015
Item
sQ
uan
tity
To
po
gra
ph
ical
surv
ey(W
TP
/UG
Rs)
Dat
aco
llect
ion
for
pip
elin
e
alig
nm
ents
Pip
ecu
ttin
g
Ro
adsu
rvey
(Cen
tral
)
Ro
adsu
rvey
(Wes
t/E
ast)
Ro
adsu
rvey
(su
b-W
est/
Eas
t)
Pre
par
atio
no
f“R
epo
rto
nR
epla
ced
Pip
eS
ecti
on
s”
Dat
aco
llect
ion
for
pip
elin
e
cro
ssin
gs
Est
ablis
hm
ent
of
GIS
dat
afr
om
the
Su
rvey
s
We
stco
mp
lete
d
East
com
ple
ted
Ce
ntr
alco
mp
lete
d
63
13
16
11
36
70
80
12
05
80
38
0
48
0
60
62
0
17
7
12
9
13
56
0
24
0
28
0
18
0
75
Sto
p
63
13
16
11
36
17
7
13
17
9
66
0
19
2
19
2
45
0
33
0
10
19
8
21
7
21
7
68
0
65
0
21
7
21
7
20
4
15
68
0
80
0
22
6 10
00
22
6 14
0
Stop for Monsoon
11
WTP
Sub
mit
ted
on
20
thFe
b.
All
dat
aSu
bm
itte
do
n5
thN
ov.
All
dat
aSu
bm
itte
do
n5
thN
ov.
Pe
nd
ing
Ap
pro
valP
eri
od
fro
mD
EA
26
2
24
2
45
0
Stop- Elections
23
7
35
56
1
29
55
0
23
7
22
1
50
25
9
19
2
All
dat
aSu
bm
itte
do
n5
thN
ov.
21
03
05
All
dat
aSu
bm
itte
do
nM
arch
.
11
00 5
12
00
22
9
21
7
37
5
28
0
14
15 9
Re
po
rts
Stop forDEA Approval
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-4
【1-1】Obtain necessary information for detailed design of Delhi water supply
improvement project.
【1-1-1】Review of data of existing pipeline
(1) GIS MAP and DSSDI MAP
1) GIS MAP
Pipe information was once collected and compiled in GIS format during the MP stage in 2010. This
pipe information was intended to show pipe connectivity and pipe sizes for the master plan target
year 2021. In the GIS map, the pipes are shown along the roads and labelled with pipe sizes and
pipe material. The year of installation of pipe, though approximate, are also shown in the GIS map.
2) DSSDI MAP
DSSDI maps developed by the Delhi government covers more items such as building footprint,
household information, road details, underground facilities including electricity cables, sewerage
networks, gas pipe lines and so on. DSSDI further identified alignment and depths of underground
utilities by use of ground penetrating radar system. Various other organizations under Delhi
government, except the telecommunication department, also participated in preparation of DSSDI
data of their own utilities. DJB’s water and sewerage pipes are available on the DSSDI maps and
DJB has the editorial rights of its information.
3) Comparison of the pipeline information in both maps
Due presumably to lack of manpower in DJB, accuracy of DSSDI information is not so high.
Therefore, in order to improve the accuracy, the Project conducted checking by comparing the two
different kinds of pipe information (MP version of GIS Map and DSSDI Map). Details are described
in Activity 1-1-4.
【1-1-2】Select pipelines to be replaced
According to the MP, approximately 700 km of 1,113 km pipe were selected for replacement. The
proportion of pipe requiring replacement in Chandrawal WTP command area can be much more than
the estimated length. This is because this command area includes higher proportion of older towns in
Delhi, and pipelines have not been replaced on a large scale after the 1950s. DJB is keen to replace the
leakage-prone pipes regardless of the proposed 700 km in MP.
Therefore, in order to select the existing pipes that require replacement, test pit survey and pipe cutting
survey were conducted within 2 years in Chandrawal WTP command area.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-5
(1) Screening of Pipe Replacement
The selection procedure and activities for pipe replacement conducted in the first year are described
below:
Identification of pipe material and pipe installation year: This activity was conducted through
interviews of DJB site staffs. The following tendencies were identified although the accuracy of
information was not so high;
1) most of the pipes were installed when DDA developed colonies/towns,
2) colonies development year was clear,
3) pipe material (ACP, GIP and CIP, etc.) used at the colony development was also clear,
4) some sections of pipes were replaced by DIP every year to reduce NRW and leakage.
Although DJB’s criteria on pipe replacement were not clear, such sections were relatively known to
DJB’s site staff.
(2) Selection of Location of Test Pit Survey
Pipe internal and external condition investigations were planned to establish the pipe replacement
criteria. About 300 sites of test pits were identified to carry out the pipe condition investigation in the
entire command area. Its purpose was to correlate pipe material, age, etc., with requirement of pipe
replacement. The locations of test pit survey were selected considering the following factors:
1) Doubtful locations were selected based on the Activity 1-1-4,
2) Pipe materials and sizes,
3) Age of pipe,
4) CIPs which are candidate of replacement,
5) DJB engineer's recommendation
6) Routes not along CPWD roads for which obtaining road cutting permission is difficult.
Also, of these test pits, pipe cutting was carried out at 50 locations in order to investigate the internal
and external condition of pipes. Pipe thickness was measured at the same test-pit points and was used
as supplemental data.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-6
Example of Investigated Pipe Interior Pipe Jointing by Coupling
Figure 2-2 Methods for Internal/External Investigation on Pipe and Pipe Connection
(3) Permission for road cutting and payment of road restoration charges
Test pit survey was carried out after obtaining permission for road cutting from relevant road
authorities through DJB, upon payment of road restoration charges. However, obtaining permission for
test pit digging was delayed due to several reasons3. Judging from this progress, it was realized that it
would take one more year (3rd year) to complete the pit digging at 600 locations as initially planned.
On the other hand, the Japanese ODA loan consultant needed relevant information for preparation of
the DPRs which required information on pipes selected for replacement based on the outcome of test
pit survey. In order to avoid delay in these works, in the 2nd JCC meeting, it was agreed that test pit
survey would be carried out for locations where road cutting permission was obtained by January
2015.
In the 3rd JCC meeting, together with the reduction in number of test pit survey, it was also agreed that
in order to increase the accuracy of the pipe selection for replacement, the number of pipe cutting and
pipe internal surveys for encrustation to increase from 30 locations originally planned. Accordingly,
the pipe cutting was carried out at 50 locations in total.
(4) Test pit survey and pipe investigation after pipe cutting
Test pit at 259 locations were dug and surveyed, and investigation of internal/external pipe after pipe
cuttings was conducted at 50 locations by the end of March 2015. The inspection sheet used by this
investigation is shown in the Figure 2-3.
3 Such as delay in approval of this Project by DEA, occurrence of monsoon, “Diwali” festival, Delhi Stateelection, etc.
Coupling
Cutting planeAging Pipes
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-7
Figure 2-3 Inspection Sheet of Test Pit
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-8
Trial digging and Pipe external investigation (TP170)16th April 2014
Trial digging and Pipe external investigation (TP238)22nd March 2014
Trial digging and Pipe external investigation (TP273)18th April 2014
Trial digging and Pipe external investigation (TP255)24th April 2014
Pipe cutting and pipe internal investigation (TP103)3rd July 2014
Pipe cutting and pipe internal investigation (TP247)9th July 2014
Pipe cutting and pipe external investigation (TP227)6th Jan 2015
Pipe cutting and pipe internal investigation (TP26)19th Dec 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-9
(5) Pipe external survey
In this survey, data on pipe thickness, pipe external condition, and pipe laying environment were
measured, observed and recorded. In order to evaluate the degradation level, pipe thicknesses were
compared with the Indian Standards related to CIP/DIP.
The result of this survey clarified that underground-pipe environment in Delhi has lower corrosiveness
of pipe due to soil, and measures against corrosion of pipe has low requirement.
(6) Pipe internal survey
The blockage status (internal encrustation) of pipes was measured during pipe internal survey of cut
pipes. The situation of pipe internal encrustation was estimated based on measurement result of pipe
internal survey. The survey result was compared with diameter reduction based on Hazen-Williams
formula and was found to be matching.
The result of surveys indicates that in case of internally unlined pipe such as CIP used for 30 years, the
Hazen-Williams friction loss coefficient (C value) decreases, and the head of water increases by twice
as compared to new pipe.
(7) Criteria proposed for pipe replacement
The criteria for the pipe replacement were proposed to DJB based on the findings of the pipe condition
survey. Consideration was given to results of pipe internal/external condition survey and use of
Japanese standards which gives more accuracy.
Pipes of 30 years or older are proposed to DJB as standard candidate for replacement. And then
"Report on Pipe Replacement Criteria including Proposed Drawing of Renewal and New Pipelines
"was prepared and submitted to DJB.
【1-1-3】Review of results of “the Study on Improvement of water supply system in
Delhi” to install new pipes
As a result of the field survey, it became clear that the elevation difference in the west area was
remarkable. In order to reduce the water pressure difference and achieve equal water supply,
boundaries of UGR and DMA were reviewed with discussion and adjustment with the Japanese ODA
loan consultants.
(1) Review of DMA
DMAs are proposed in the MP for entire Delhi as a means of managing water distribution and
controlling NRW. And also under the Japanese ODA loan project, introduction of DMA in Chandrawal
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-10
WTP command area is planned. JET confirmed some pockets of highly populated informal settlements
(slum) in the Project area during its site visit. Many of such pockets are located in the hilly areas. Such
locations commonly get water from private supply system or tankers as there is no DJB piped supply.
In addition, ground elevation was considered in detail in this review so that differences of ground
elevations within DMAs were the minimum. As a result, boundaries were changed for some DMAs.
These reviewed DMAs (see the following figure) were transferred to the Japanese ODA loan
consultants for finalization.
Note: Red lines show original boundary in the MP and blue lines show this reviewed boundary
Figure 2-4 Comparison of DMA Boundaries in the MP and This Review
(2) Review of UGR Command Area
UGR command areas were decided in the MP to utilize the existing UGRs to the maximum extent
possible because it was thought that there were no available lands for expansion of UGRs. Moreover,
Chandrawal WTP command area has many spots of high population density. Therefore, there is no
appropriate location for new construction of UGR.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-11
However, JET found the abandoned Anand Parbat Industrial UGR (area of the orange color in Figure
2-5) and proposed for the reconstruction of the UGR. This proposal was transferred to the Japanese
ODA loan consultant after review and decision with DJB. The consultant carried out the detail design
of reconstruction of this UGR for the Japanese ODA loan project. UGRs and their water supply areas
(UGR command areas) after this review are shown in the following figure.
Note: Left figure shows the command areas in the MP and Right figure shows in this review’ one
Figure 2-5 Comparison of UGR Command Area in the MP and in This Review
Confirmation of abandoned Anand Parbat Industrial UGR
(3) Review of the Transmission Pipeline and Pipe Network Analysis
This review of transmission pipeline was done by pipe network analysis and the result is shown in
Figure 2-6. Since existing transmission pipelines are located on the hill area, the possibility of aligning
the pipelines along the ridge center and abolition of Jandewaran BPS were looked through. By pipe
network analysis, the pipe diameter in the central portion was increased but the total pipe length is
◎ WTP
◎ DJB ◎ DJB
◎ WTP
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-12
shortened compared to the water pipelines proposed during the MP. In particular, there can be
significant reduction in the length and diameter of pipe for the East area. This result shown in the
following figure was handed over and finalized by the Japanese ODA loan consultant.
Figure 2-6 Comparison of Transmission Pipelines in MP (Left) and Reviewed Pipelines (Right)
(4) Road Survey
All roads where distribution pipes are laid were surveyed. Basic policy was that distribution pipes
should be extended to “in front of every household”, from where house connections and individual
meters can be installed in each household without installing a long house connection pipe. This kind of
arrangement can avoid long-distance service pipes and missing individual water meters, thereby
reducing high pipe friction loss, leakage in the form of illegal connections and thereby enhancing
revenue collection. The result is shown in the Activity 1-1-7.
【1-1-4】Obtain data and information on underground utilities by using DSSDI GIS data,
and reconfirm pipeline network data with support of DJB field staff
(1) Existing Pipe Information
In the Activity 1-1-1 described, there are two kinds of GIS information; one is provided by DSSDI and
another is provided by DJB Mapping Cell.
(2) Printing of Existing Pipe Network Drawing
JET was due to receive two kinds of information by digital data, and to confirm the pipe network.
However, due to security reason, digital data were not provided to JET from Mapping Cell and
alternatively the print-out data were provided. For this reason, JET printed the pipe network drawings
superimposing both the DSSDI and Mapping Cell and converted it into digital data again. Number of
the printed drawings was about 300 sheets at a scale of 1:1000 in A1 size.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-13
(3) Confirmation of the 2 Kinds of Existing Pipeline Information
In order to enhance the accuracy of pipe information and solve large discrepancies between the two
kinds of information, the following steps were taken in the first year:
1) Hard copy maps with pipe network information from the above-mentioned two sources were
first printed from the Mapping Cell.
2) Then, those maps were checked by JET one-by-one and line-by-line for any discrepancies
between the 2 sources of information and also for any unclear item in the pipe network. The
checked items were listed below.
a) Attribute data on pipes especially size, material, year of installation and laying depth
b) The difference of pipe sizes between adjoining sections
c) Existence of pipes in both residential and non-residential area
d) Information on valves and other appurtenances
e) Doubtful information (disconnection, abrupt pipe size changes, missing pipelines, etc.)
3) Subsequently, numerous interviews and site visits were conducted with the site staffs of DJB
who are supposed to know the most accurate data on pipe.
Figure 2-7 Confirmation of the Existing Pipeline Information
GIS map from MP study(Based on DJB’s GIS data)
Chandrawal TreatmentPlant System Pipe Network
Chandrawal CAUnderground Utilities Plan
Match Up(Interviews conducted)
GIS map from DSSDI(Data includes all kind of utilities)
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-14
Checking pipeline networks in printed Maps based onDSSDI data
Site survey along with DJB engineers to confirmpipelines
(4) Handing over of Map by Mapping Cell to Zonal Offices for Correction
The printed maps included sensitive information on water supply pipelines, sewers, electricity cables,
etc. It was decided by Mapping Cell that printed maps would be distributed to zonal office considering
security of data. For the confirmation of question and unknown part in the maps, explanation meeting
was held by Mapping Cell.
(5) Explanation Meeting
On 27 August 2013, an explanation meeting was convened by the Mapping Cell in association with
the JET including all EE of relevant zonal offices to explain them about the procedure of map
correction works in detail. About 2 week period were given from the Mapping Cell to each EE to
complete the correction of maps.
Briefing DJB Engineers (EE, ZE) on Map correction27 August 2013
(6) Identification of Discrepancy between the 2 type of Maps and Confirmation of Pipe
Information by DJB Engineers and Field Staff
Most of EE and ZE relied on the JEs, operators and workers for collection and clarification of
information. However, this had taken a considerable time since many JEs (although some were very
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-15
cooperative) were busy with their on-site works. Long vacation of Diwali also included during this
period. Repeated visits, field survey, and persistent encouragement from JET were required to
complete the verification work. The last clarified information was collected at the end of November
2013 (refer to the following Figure).
The corrected maps by DJB field offices were collected by the Mapping Cell and lent to JET.
Summary of field meetings and map correction activities is shown in Figure 2-8.
Checking pipelines networks in printed maps at DJBfield office
Th
eA
ssis
tan
ceR
ela
ted
toD
elh
iW
ate
rS
up
ply
Imp
rovem
ent
Pro
ject
FIN
AL
RE
PO
RT
2-1
6
Fig
ure
2-8
Su
mm
ary
of
Fie
ldM
eeti
ngs
and
Map
Cor
rect
ion
Act
ivit
ies
123456789
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30123456789
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31123456789
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
SunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSatSunMonTueWedThuFriSat
9M
alka
Gan
j■
■■
■■
■■
■■
■■
■▼
10T
imar
Pu
r■
■■
■■
■■
■■
■■
■▼
12G
.T.B
.Nag
ar■
■■
■■
■■
■■
■■
▼
69K
amla
Nag
ar■
■■
■▼
70R
ana
Pra
tap
Bag
h■
■■
■▼
77K
ash
mer
eG
ate
■■
■■
■■
■■
▼
78M
ajn
uK
aT
illa
■■
■■
■■
■■
▼
79Ja
ma
Mas
jid■
■■
■■
■■
■▼
80C
han
dn
iCh
ow
k■
■■
■■
■■
■▼
81M
into
Ro
ad■
■■
■■
■■
▼
82K
uch
aP
and
it■
■■
■■
■■
■▼
83B
azar
Sit
aR
am■
■■
■■
■■
■▼
84T
urk
man
Gat
e■
■■
■■
■■
■▼
85Id
gah
Ro
ad■
■■
■■
■■
■▼
86B
allim
aran
■■
■■
■■
■▼
87R
amN
agar
■■
■■
■■
■▼
88Q
asab
pu
ra■
■■
■■
■■
▼
73S
has
triN
agar
■■
■■
■■
■■
■■
■■
■■
▼
74In
der
Lo
kC
olo
ny
■■
■■
■■
■■
■■
■■
■■
▼
75K
ish
anG
anj
■■
■■
■■
■■
■■
■■
■■
▼
76D
epu
tyG
anj
■■
■■
■■
■■
■■
■■
■■
▼
89P
ahar
gan
j■
■■
■■
■■
■■
■■
■■
■▼
90M
od
elB
asti
■■
■■
■■
■■
■■
■■
■■
▼
91K
aro
lBag
h■
■■
■■
■■
■■
■■
■■
■▼
92D
evN
agar
■■
■■
■■
■■
■■
■■
■■
▼
93B
aljit
Nag
ar■
■■
■■
■■
■■
■■
■■
▼
94W
est
Pat
elN
agar
■■
■■
■■
■■
■■
■■
■▼
95E
ast
Pat
elN
agar
■■
■■
■■
■■
■■
■■
■▼
96N
ewR
anjit
Nag
ar■
■■
■■
■■
■■
■■
■▼
149
Raj
ind
erN
agar
■■
■■
■■
■■
■■
▼
150
Pu
sa■
■■
■■
■■
■■
■▼
151
Ind
erp
uri
■■
■■
■■
■■
■■
▼
152
Nar
ain
a■
■■
■■
■■
■■
■▼
S-I
I41
Jan
gp
ura
(Par
tial
)15
3D
ary
agan
j■
▼
166
Mu
nir
ika
■■
▼
167
R.K
.Pu
ram
■■
▼
168
Nan
akP
ura
■■
▼
Lege
nd
■Meetingdate
onfieldsforfollow-upan
dclarification
▼Completedmap
correctionan
dreturn
toMappingCell
SW
-III
Raj
ind
erN
agar
Pat
elN
agar
Kar
olB
agh
Bal
limar
an
23 24 39
C-I
C-I
I
Sad
arB
azar
Ch
and
niC
ho
wk
44R
.K.P
ura
m(P
arti
al)
W-I
I
1922
Mat
iaM
ahal
NW
-IV
Mo
del
To
wn
(Par
tial
)18
N-I
Tim
arp
ur
(Par
tial
)3 20 21
Oct.
Nov.
Sep.
DJ
B
Div
isio
nA
ssem
bly
No.
and
Nam
eW
ard
No.
and
Nam
e
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-17
【1-1-5】Draft pipe alignment and depth and【1-1-6】Draft pipe laying method (Open-cut
and Trenchless) and crossing method (railways, rivers, drainage and major
roads)
The Chandrawal WTP command area includes many important government buildings, embassies,
official residences of high officials, etc. Therefore, obtaining permission from road administration for
laying pipelines through open cut method is time consuming and even in some cases impossible.
Therefore, trenchless method was proposed in case of pipe laying along/across busy roads in the MP
stage. The optimal laying location for on-site environment and burial depth required to be selected.
At some locations, water distribution mains or pipelines were required to cross the major road,
drainage channel, and railway lines. For pipes crossing these locations, selection of appropriate
method was necessary considering the actual field conditions. The selection of construction method
was planned through the following procedure. In total, 25 nos. of such crossing points were identified.
(1) For revised pipelines network and proposed transmission pipes; the field conditions were
checked and information on type of roads, traffic situation, and obstructions such as drainage
canal or railways lines were collected.
(2) Pipe laying method was proposed.
(3) The locations of 25 crossings were selected based on collected data on pipes.
(4) Data on the pipe crossing construction methods was prepared for discussion of DJB with the
Japanese ODA loan consultant. .
【1-1-7】Carry out topographic survey along pipe-alignment.
Drawing of the pipe laying route has been a basic data for the detailed design and were prepared in the
Project. The road survey items include the following items:
(1) Topography with altitude,
(2) Road type,
(3) Existing facilities, and
(4) Above-mentioned drawing plan and profile
The achievement of survey is shown in the Table 2-1 and Figure 2-9 and Figure 2-10.
The total length of pipe alignment surveyed in Activity 1-1-5 is less than the total length of road
surveyed in Activity 1-1-7. As originally planned, location of pipe to be replaced based on the results
of Activity 1-1-5 needed to be selected first, and then road survey for the selected pipes should have
been conducted.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-18
However, the pipe internal/external survey for the criteria for pipe replacement got delayed due to the
delay in getting permission for road excavation caused by the delay in authorization of the Project
from DEA resulting in DJB staff's passive attitude. Therefore, road survey was conducted for all roads
in the Project area to avoid any remarkable delay of the Project. This resulted in the difference in
length between Activity 1-1-5 and 1-1-7.
Topographical survey for RoadTopographical survey for Road
5 February 2014
Pipeline route survey in slum area9 April 2014
Field Survey to identify suitable location for crossingof railway lines
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-19
Table 2-1 Surveyed Length of Pipe Alignment Survey Regarding Activity 1-1-5 and Road Survey
Regarding Activity 1-1-7
Nos UGR Command AreaPipe alignment survey
regarding [1-1-5]Road survey regarding
[1-1-7]Length (km) Road Network (km)
Transmission Pipe (TM)
1 Central (I) 20.4 -
2 Central (II) 13.3 -
3 West 37.8 -
4 East Not surveyed in order to use existing pipelines
Sub-total 71.5 71.5
Secondary Distribution Main Pipe
C-1 Flag Staff 20.5 -
C-2 Hindu Rao 11.8 -
C-3 MM Jeetgarh 21.78 -
C-4 Jhandewalan 10.3 -
C-5 Idgah 4.2 -
C-6 Ramjas 5.4 -
C-7 Ridge Road 9.9 -
C-8 Cant Palam Phase 1 24.0 -
W-1 Shastri Nagar 24.9 -
W-2 Shadipur 18.7 -
W-3 New Rajendra Nagar 12.3 -
W-4 Naraina 9.5 -
E-1 Subhash Park 2.6 -
E-2 Ramlila Phase-1 14.5 -
E-3 Ramlila Phase -2 11.7 -
Sub-total 202.8 196.6
Distribution Pipe
C-1 Flag Staff 68.5 115.0
C-2 Hindu Rao 16.5 52.0
C-3 MM Jeetgarh 111.2 190.0
C-4 Jhandewalan 65.3 113.0
C-5 Idgah 53.8 58.2
C-6 Ramjas 87.7 57.0
C-7 Ridge Road 47.4 71.0
C-8 Cant. Palam Phase-2 123.5 203.0
W-1 Shastri Nagar 178.5 98.0
W-2 Shadipur 150.0 173.0
W-3 New Rajendra Nagar 24.8 37.0
W-4 Naraina 82.5 233.0
E-1 Subhash Park 7.9 21.4
E-2 Ramlila Phase-1 106.4 140.8
E-3 Ramlila Phase-2 17.1 52.5
Sub-total 1,141.4 1,641.9
Total 1,415.4 1,910.0Notes: C is central area, W is west area, and E is east area.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-20
Note: Lines of distribution pipe, secondary mains and transmission main are surveyed.Figure 2-9 Drawing of Result of Pipe Alignment Survey Regarding Activity 1-1-5
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-21
Note: All roads are surveyed.
Figure 2-10 Drawing of Result of Road Survey Regarding Activity 1-1-7
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-22
【1-2】Carry out survey and GIS mapping of WTPs, UGEs and BPSs, and verification
of the data (location and size, etc.) of pipes in Chandrawal WTP command area
This Activity is divided into 3 components as described below.
(1) Topographical survey of Chandrawal I and II WTPs and UGR/BPS, and data conversion to GIS
drawings from survey results
(2) Verification of GIS data related to distribution pipelines in Chandrawal WTP command area
(3) Update Pipe information on GIS
(1)Topographical survey of Chandrawal I and II WTPs (approx. 18 ha) and UGR/BPS (approx.
28 ha), and data conversion to GIS drawings from survey results
Topographical survey for Chandrawal I and II WTPs was expanded (see the following figure) to cover
DJB properties situated between the 2 WTPs to have flexibility in planning/designing of the WTPs. In
DJB’s properties are Recycling Plant, employee lodgings and vacant lot, and adjoining existing
facilities of Chandrawal II WTP.
Note: Parts of yellow color are the existing area of Chandrawal I and II WTPs, and inside the frame of light-bluecolor is the surveyed area.
Figure 2-11 Topographical Survey Area of Chandrawal I and II WTPs
Small size of facilities such as reservoirs and BPSs are proposed to be abandoned in the MP. However,
review of DMA revealed that these are vital for water distribution to localized areas with high ground
elevations. Therefore, topographical survey of Anand Parbat Industrial Area UGR and Than Singh
Nagar BPS were added. Then, the Japanese ODA loan consultants carried out water supply planning
and detailed design for them.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-23
Topographical survey of Chandrawal I and II WTPs and 18 (number) UGR/BPS started in December
2013. All survey maps (CAD data) were converted into GIS data, and the data was transferred to DJB
in February 2014.
Confirmation of area to be surveyed near ChandrawalWTP
Survey in Chandrawal WTP area
Topographical survey in Chandrawal WTP phase II7th February 2014
Pipeline survey in Chandrawal WTP phase II7th February 2014
(2) Conversion to GIS from the Topographical Survey Results of WTP, UGR/BPS
The topographical survey results were converted to GIS data from the drawn CAD data.
(3) Update Pipe information on GIS
JET updated the information on water supply facilities in GIS (DSSDI data) which were identified
under the activity 1-1-4. GIS data updates progressed smoothly until December 2013 with 180 sheets
updated out of 280 sheets. But the updating work was suspended by the order of DJB after DEA
approval issue arose. Moreover, GIS updating work remained suspended for long time due to the
non-availability of space for JICA experts in Mapping Cell and security reason.
In order to recover the delay in activities, the TA office was linked in November 2014 with Mapping
Cell through optical fiber cable, and an Arc GIS server was established for GIS database access. Data
updating from a remote place was ensured by introducing this software.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
2-24
An expert who can manage Arc GIS server in DJB was dispatched during March - May 2015 and
operation of the server had started. As a result, all 280 sheets of pipe information were completed by
June 2015. And then, all survey results were converted into the GIS format, and were submitted to
DJB in June 2015.
Confirmation work of topographical survey data7th November 2014
Security door installed in the TA office2nd December 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-1
CHAPTER 3 OUTPUT 2 (DJB’s capacity to monitor and control the
water distribution for equitable distribution and
non-revenue water management is upgraded)
(1) General
By installing the SCADA in a distribution system, it becomes possible for operators to remotely
monitor and control the water supply volume by adjusting control valves thereby reducing manpower
and unifying operation. The pilot project was planned in part of Pitampura UGR command area (see
Figure 3.1) to monitor and control the water flow and pressure at selected DMAs for equitable water
distribution and NRW calculation by using SCADA System. In the pilot project, creation of 3 DMAs
and procurement, installation and operation of SCADA system was carried out. In parallel, techniques
of equitable water distribution and NRW calculation were transferred to DJB.
Part of the Pitampura UGR command area was selected in the detailed planning study conducted by
JICA because of adequate water pressure, clear pipe connection and so on. These DMA get water from
the Pitampura UGR/BPS to where water is supplied from Haiderpur WTP (200MGD: 900,000 m 3/day).
Salient features of the 3-DMAs are shown in Table 3-1.
Figure 3-1 DMAs in Pitampura Pilot Project Area
SCADA Server
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-2
Table 3-1 Salient Features of DMA
Size of DMA(ha)
Number of Connection(No.)
Billed Volume(liter/connection/day)
DetailedDesign Study
PilotProject
DetailedDesign Study
Project as ofDecember 2017
Project as ofDecember 2017
DMA1 3.8 3.8 796 796 392
DMA2 21.5 14.5 2,699 1,997 1,005
DMA3 10.0 10.0 572 572 1,335
Total 35.3 28.3 4,067 3,365 2,732
(2) Outline of the SCADA system
Outline of the SCADA system constructed in this pilot project is shown in Table 3-2.
Table 3-2 Outline of the SCADA system
Item Contents
Objective
・ Monitor water flow and pressure in the 3 DMAs of the Pitampura pilot project area.・ Regulate flow and pressure of DMAs by electric flow valve at the inlet of DMAs that is
controlled remotely by SCADA.・ Transfer of the technology on the above regulation procedure, namely technology of
equitable water distribution and NRW calculation.・ Utilize as a training facility of SCADA operation that will be provided under Japanese ODA
loan project for equitable water distribution
Function
・ Monitoring of Pitampura UGR & BPS (Acquiring and Monitoring the information such asUGR water level, pump operation time, flow/pressure of the water distribution in the existingSCADA of the Pitampura UGR & BPS)
・ Monitoring of measurement point (Monitoring flow/pressure/valve of 14 measurementpoints)
・ Controlling valves of measurement point (Controlling Valve opening with Actuator of 13measurement points)
MajorEquipment
Pitampura UGR& BPS(PitampuraUGR in Figure3-1)
a) Data collection Server (1 set):collect measurement data from PLC of eachlocal station using wireless communication (GPRS communication)
b) SCADA Server (1 set):supervise, control and manage the SCADA clientgraphic screen
c) Reporting system (1 set):generate report for equitable water supply andNRW calculation from SCADA data
d) Pipe network calculation system (1 set):realize real-time pipe networkcalculation
e) SCADA Client (1 set)
Offices ofE&M, and Civilengineers
Display information
Local Station(14 chambers)
a) GPRS communication modem: communicate between SCADA Server &Data collection Server and PLC by General Packet Radio Service (GPRS)using packet communication of mobile phone
b) PLC:send information of flow/pressure and Valve to Data collection, and
control the valve open/close by the instruction from SCADA Server.c) Valve Control circuit: manage of supply power to control the valve
Actuator
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-3
Note: Only monitoring purpose.
(3) Schedule
Activities of output 2 were initially planned for 3 years: installation of SCADA system in the 1 st year
followed by SCADA operation in the 2nd and 3rd years. However, they took 4 years and 10 months; 4
years and 6 months for the installation and 4 months for operation due to various reasons such as water
ingress in chambers, and delay in installation of SCADA. Summary of activities in Output 2 is shown
in Table 3-3.
(4) Delay of Procurement and Installation with Change of Work Schedule
Work schedules are presented in Activity 2-3-4.
Installation of SCADA system4 except actuators that are used to open/close electric control valves in
13 chambers5 with construction of the 13 chambers except 1 chamber (at No. 9) were completed in
July 2015, 2 years after the Project commencement.
However, water ingress in the chambers was observed in July 2015 and countermeasures and
extension of the Project duration of 1 year and 10 months were agreed in the 5 th JCC meeting in March
2016. Based on this agreement, a demonstration chamber was constructed in May 2016 to study the
proposed countermeasures and its effectiveness was confirmed in August 2016. Subsequently, DJB
made the countermeasures, water-proof mortar coating in the walls of the chambers in October to
December 2016. The remaining 1 chamber at No. 9 was also constructed in March 2017 by DJB after
installation of valves and flow meters in February 2017 by RDS.
RDS started replacement of actuators that were damaged by water ingress in January 2017 and
completed it in September 2017, far behind the schedule. Afterwards, RDS made correction works and
completed it in December 2017.
4 Installed by RDS and contracted by JICA.5 Construction of chambers including excavation, backfilling, road restoration and so on by DJB
Inside ofchamber(location isreferredto Figure 3-1)
LocationNo.
Control Valveswith Actuators
PressureGauge
Flowmeter
Water levelsensor
1
2
3
4
5
6
7
8
9
10
11
12
13 Note
14
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-4
Table 3-3 Planned/Actual Period of Activities in Output 2
StagePlannedPeriod
ActualPeriod Activity
Planningand
design
June 2013to
Jan. 2014(8 months)
June 2013to
Oct. 2014(13 months)
2-1: Review SCADA application in DJB2-2: Introduce Japanese experience and system to DJB2-3: Implement pilot project for equitable distribution and
non-revenue water (NRW) monitoring by applyingSCADA
2-3-1: Reconfirm the configurations of the existing distributionnetwork within the pilot project area and finalize theimplementation plan of the pilot project
2-3-2: Estimate the level of water demand in each DMA2-3-3: Procure equipment necessary for implementation of the
pilot project2-3-8: Calculate the total volume of water billed to the
customers in the area based on the RMS(1st)2-3-10: Demonstrate leakage detection activities in the area
Procurement,installation
andtest operation
Nov. 2013to
April 2014(6 months)
June 2014to
Dec. 2017(43 months)
2-3-4: (a) Construct a demonstration chamber to check itsperformance
(b) Implement improvement works for water ingress ofthe constructed chambers
(c) Install the equipment and conduct trial runs ofSCADA system
NRWAnalysis,
Operation andMonitoring
withon-the-jobtraining for
DJB
May 2014to
May 2015(24 months)
Dec. 2017to
Mar. 2018(4 months)
2-3-5: Monitor flows and pressures within the pilot project areathrough SCADA system
2-3-6: Monitor inequitable water supply in DMAs and studyhow to control flow/pressure to enhance equitable watersupply
2-3-7: Implement the flow/pressure control and confirm itseffectiveness
2-3-8: Calculate the total volume of water billed to thecustomers in the area based on the RMS (2nd)
2-3-9: Calculate NRW ratio in the area2-3-11: Prepare manual and guideline for flow/pressure control
and NRW monitoring2-3-12: Hold a seminar to disseminate the scope and outcome
of the pilot project across the entire DJB2-4: Identify issues that need to be addressed for further
enhancement of equitable distribution and NRWmonitoring
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-5
(5) Member in charge of Output 2
The main members in charge of Output 2 were as follows.
DJB JET
(1) DMA and Civil
(2) SCADA
(3) NRW
(4) Leak Detection
Ramesh Thakur
C. E. (NW) Overall
Hiroki Horie
Leak Detection (1)
Tetsuo Hayashi
Leak Detection (2)
P. K. Jain
S. E. (NW)
Mukesh Jindal
E. E. (NW) III
Sandeep Sharma
Z.E. (NW) III
V K Singh
E. E. (NW) III
Yogender Singh
J.E. (NW) III
Koichiro Azui
DMA
Noboru Saito
Civil (1)
Hiroshi Kojima
Civil (2)
U.K. Rastogi
E. E. (NW) E&M
Manabu Fukushima
SCADA
Ajay Kumar
S. E. (Project) W-III
Wataru Shimizu
NRW Analysis
Mukesh Jindal
E. E. (NW) III
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-6
(6) Technology transfer
1) Improvement of water tightness of constructed chamber
JET transferred know-how on water resistance improvement work on constructed chambers and
countermeasures after chamber inundation to EE (NW) III, who was responsible for DJB. In
addition, JET made OJT to DJB in December 2017, assuming chamber inspection after the rainy
season. These procedures are reflected in the SCADA guideline in Appendix 10.
Based on these experiences, JET made recommendations to DJB to make the chamber of RC
structure and PC structure and to adopt a highly watertight iron lid etc. Based on this
recommendation, RC chamber was adopted in Japanese ODA loan project.
2) SCADA
EE (E & M) and EE (NW)6 III in charge of the Pitampura district are appointed as DJB staff in
charge of SCADA operation and NRW from the start of the Project. EE (E&M) was responsible for
mechanical and electrical and EE (NW) was responsible for the civil. These appointed officials each
for E & M and civil have engineers (ZE, JE and AE), technicians and many workers under them and,
they can mobilize their staff as needs arise. Those engineers acquired the know-how such as
SCADA operation through SCADA installation work and 8 days of training. JET conducted simple
tests on attendees who attended the training for more than 6 days. JET certified 9 engineers who
passed the exam as trainers and awarded a certificate of completion.
In the future, the DJB trainer trained by the above-mentioned training will transfer technology of
SCADA system to the engineers involved in SCADA system in the water distribution area that will
be installed in the Japanese ODA loan project and other projects. DJB training cells included the
formulated long-term training plan of the SCADA into the training curriculum
3) NRW
EE (NW) III and his team (ZE, AE, JE, plumbers etc.) were also C/Ps of NRW.
JET transferred know-hows on NRW, its components consisting of unbilled authorized consumption,
apparent losses and physical losses referring to IWA guideline. JET also transferred know-hows on
its calculation method and importance of household survey to reduce apparent losses. In response,
DJB conducted such surveys twice in 2015 and 2017. Billed authorized consumption volume in
each DMA was obtained from the RMS data after confirming the number of connections in RMS
data and household survey which was almost equal (Illegal connections were few in the pilot project
area). Inflow to DMA was obtained from the SCADA system.
6EE (NW) III is correct although EE (NW) II was mistakenly mentioned as a responsible engineer to receive technical
transfer in the MM of 7th JCC meeting.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-7
Seasonal change in water consumption was not clear because of use of private pumps and roof tanks.
So, average volumes of billed authorized consumption and inflow to DMA was used for calculation
of NRW.
a) Billed Authorized Consumption Volume
Billed authorized consumption volume was obtained from RMS data. EE (NW) III compared
the numbers of connections in RMS with those in household survey and confirmed the both are
almost the same. Then the billed authorized consumption volume in RMD data covers almost
the entire DMA.
b) System Input Volume
EE (NW) III calculated System Input Volume using SCADA data.
c) Calculation of NRW
EE (NW) III calculated NRW using Billed Authorized Consumption Volumes and System Input
Volume. In addition, EE (NW) III performed the training to learn know-how of SCADA. EE
(NW) III delivered a lecture of NRW for trainees. JET was able to confirm that they understood
calculation of NRW.
4) Leak Detection
A demonstration to introduce Japanese technology on leakage detection was carried out for DJB
staff in August 25, 2014. Approximately 30 DJB staff attended. The leakage detection equipment
(sound hearing bar, electronic leakage detector, buried pipe detector) was explained in Pitampura
offices and then leakage detection technology using these leakage detection devices was introduced
in DMA 1. Many DJB officials including Addl. CEO tried to locate the buried pipe and check the
leakage noise.
The above technical transfers were a final step of the output 2. Organization and procedures of
operation and maintenance when equipment did not function, water entered into chambers and so on
was also practiced during the Project. These are included in SCADA manual (SOP)/ guideline
(Draft) and stored in the library of DJB for its wide use of DJB.
【2-1】Review SCADA application in DJB
(1) Usage situation of SCADA System in DJB
Table 3-4 shows the status of SCADA currently used by DJB. Most of the existing WTPs are old and
operations such as the opening/closing of valves and start/stop of equipment are manually done. Sonia
Vihar, Nangloi and Bhagirathi WTPs have already introduced the SCADA system. UGR/BPS in
Pitampura has SCADA system that is used for monitoring water level of UGR and operating the
distribution pumps.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-8
However, the current SCADA system of DJB monitors the WTPs and UGRs independently. It is not a
comprehensive SCADA system that should operate and monitor total flows from WTP, UGR/BPS, to
transmission and distribution pipe networks and water demands in DMAs.
Table 3-4 Situation of SCADA Use in DJB
WTP anddistribution area
WTP UGR/BPS Distribution/DMA Purpose
Sonia Vihar WTP Control and monitoring of WTP
Nangloi WTP anddistribution area
Control and monitoring of UGRsand WTP
Bhagirathi WTP anddistribution area
Control and monitoring of UGRsand WTP
PitampuraUGR/BPS
Control and monitoring of UGR
Pitampura pilotproject
(Distributioncontrol)
Control and monitoring ofDistribution Area
(2) Operation and management status of SCADA of Pitampura UGR/BPS
At the Pitampura UGR/BPS the operator monitors status of distribution pumps/valves, UGR water
level, flow and pressure. He also operates or turns on and off distribution pumps by SCADA system
for a pre-determined few hours every morning and evening in order to supply water at the
pre-determined fixed flow quantity. The following problems can be considered in the Pitampura
UGR/BPS.
1) Much water tends to be supplied to hydraulically advantaged areas like near to UGR/BPS.
2) Water might be inequitably supplied; however, there are no measures to prove this.
3) When water is supplied continuously, the current system of the fixed flow operation of pumps
needs to be shifted to the variable flow operation to cope with change of water demand.
【2-2】Introduce Japanese experience and system to DJB
Japan has one of the best technologies for total control of the entire water supply system. Also, DJB
strongly hopes to introduce in Delhi advanced technologies to monitor and control the entire water
supply system. JET had introduced 24 x 7 operation and equitable distribution by using the Japanese
system. In addition, JET had also introduced the advanced examples of Tokyo Waterworks Bureau and
the technologies of Japanese companies to DJB, concerning the measures against leakage reduction
through pressure optimization by pump operation and energy saving effects.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-9
Table 3-5 Introduction of Japanese Experience and System about SCADAOpportunity Date Introduction contents
2nd Seminar 6th March 2014Introduction of the Water Supply Operation Center of TokyoWaterworks as “Facility improvement of Tokyo”
C/P(counterpart)
training in Japan
11th November 2014to 18th November 2014
Through Visiting to Water Supply Operation Center, MisonoWTP and Koemon Water Supply Station of Tokyo WaterworksBureau and SCADA operation by demonstration in HitachiOmika Works, DJB have learned necessity of skillful engineersand training them with experience and know-how in eventualjudgment and emergency response, not only the facility outlineand equipment description, necessity of appropriate waterdistribution plan based on accumulated data and efficientmaintenance and maintenance through labor saving,
5th Seminar 29th August 2017
As “Realization of equitable water supply and NRWmanagement in Tokyo (Introduction of SCADA System)”, thesignificance and effect of introducing SCADA, the issues forintroduction were summarized while comparing the differencesbetween the situation of Delhi and Tokyo.
6th Seminar 27th February 2018
AS “Toward the development of the Delhi’s water supply-Current issues and future vision-”, in reviewing activities overthe past five years, for the stable water supply and sustainablewater business within limited water resources, importance ofdistribution management and NRW management using SCADAwere reviewed.
【2-3】 Implement pilot project for equitable distribution and non-revenue water (NRW)
monitoring by applying SCADA
【2-3-1】Reconfirm the configuration of the existing distribution network within the
pilot project area and finalize the implementation plan of the pilot project
Three DMAs that were planned in “Detailed Planning Survey in 2012” as shown in the schematic
diagram below, have been reviewed considering the following key points:
(1) Review of pipe alignment, material and diameter (hearings and DSSDI maps)
(2) Possibility of DMA to be isolated hydraulically
(3) Space of sites for installation of valves and flow meters
(4) Test pits for confirmation of the pipe alignment, pipe material, and pipe diameter
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-10
Figure 3-2 Schematic Diagram of Pipe-Network in Pilot Area (Detailed Planning Survey)
(1) Confirmation of existing pipe alignment, diameter and material
The following steps were taken by JET in cooperation with the DJB engineers for this purpose.
1) Pipe network maps with DSSDI data for Pitampura pilot project area was printed out in DJB
Mapping Cell.
2) Pipe alignment and diameter was confirmed through discussion and site visits with ZE and JE.
JET also conducted test pit survey to confirm the actual site condition such as pipe alignment,
depth and pipe diameter.
3) Confirmed pipe information was reflected into DSSDI data.
Survey of underground utilities was conducted for preparation of DSSDI map by the Delhi
government. The homepage of DSSDI says that the underground utilities comprising water, sewer,
telephones, power lines, etc., have been mapped for the first time using state-of-the-art technology.
The availability of underground utilities in digital form would enable the concerned line departments
to undertake preventive maintenance programs as well as locate the fault in the underground utility
with precision.
The printed maps of Pitampura area using DSSDI data has been reviewed upon discussion with DJB
engineers. The distribution network shown in DSSDI data was observed to be different than the actual
at some locations. One of the major differences is that Pitampura UGR’s main distribution network is
not updated from status when supply was made directly from old UGR. Currently used Pitampura
UGR and related major pipe line were constructed in 2010, and water supply network in DSSDI map
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-11
has not been updated after DSSDI survey carried out in 2009. Moreover, DJB has constructed new
distribution pipe at some places even after the Detailed Planning Survey Stage.
Figure 3-3 Schematic Diagram of Revised Pipeline Network as of July 2013
(2) Possibility of DMA to be isolated hydraulically
One of the purposes of establishing DMA is to monitor the water quantity/pressure within each DMA.
To achieve this, water in a particular DMA should be supplied only from distribution main pipe
feeding that DMA.
The MP prepared by JICA suggested that existing water supply network system need to be modified to
“three tier system”: Transmission Main system (From WTP to UGR), Distribution Main (From UGR
to DMA), and Distribution pipe (From taping from Distribution Main up to house connections).
In this regard, JET upon discussion with DJB confirmed that each DMA prepared by Detailed
Planning Survey can be isolated effectively7. JET also confirmed that no other water resources such as
tube wells existed in defined pilot project area.
(3) Availability of space to install valves and flow meter in Pitampura pilot project area
Large diameter pipes with diameter more than 300mm are required to have sufficient space to install
7 Hydraulic isolation of DMA is confirmed by zero pressure tests: To be confirmed if pressure is zero inside of DMA when
inlet valve is closed. Refer to Activity 2-3-9.
NEWNEW
NEW
NEW
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-12
the equipment. DMA 1 and DMA 3 were confirmed to have enough available spaces for installation of
valves and flow meters.
Area of DMA 2 was shifted because establishment of DMA 2 proposed earlier was difficult due to the
following reasons:
1) Control valves and flow meters need to be installed on the City Park Road, heavy traffic.
2) Some underground utilities such as pipes, drains, cable, etc., were laid on the same side of
the road.
3) The contractor would require sufficient working space which was not available.
The shifted DMA 2 of UP, VP, WP and UP blocks of Pitampura is well isolated from other supply
blocks, in which there is no other water source such as wells, and the water pressure of existing supply
is supposed to be at same level. This shift was approved in the 1 st JCC meeting. The detailed block
map is shown in Figure 3-13.
Figure 3-4 Schematic of Pipe Network (Location of 3-planned DMA)
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-13
Confirmation of Pipe alignment on sitewith DJB junior engineer -1
Confirmation of Pipe alignment on sitewith DJB junior engineer -2-
Interview to customers for getting information of watersupply conditions in Pilot area
(4) Test Pits Survey to confirm the pipe alignment, pipe material and diameter
Test pit survey for the confirmation of the pipe alignment, material and diameter was conducted at all
the potential locations, where flow meters and valves were to be installed. At some of these locations,
actual diameter of pipe was observed to be different from that of provided in the DSSDI data as shown
in Table 3-6 and Figure 3-5
Table 3-6 Results of Test Pit Survey
S. No No.in FigureVariation in Pipe Diameter
(DSSDI data Actual Measured Diameter)
1 No.5 Diameter 600mm 800mm
2 No.8 Diameter 150mm 200mm
3 No.9 Diameter 200mm 250mm
4 No.10 Diameter 200mm 250mm
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-14
Figure 3-5 Modified Points by Test Pit Survey
Confirmation of Pipe diameter and depthby test pit survey
【2-3-2】Procure equipment necessary for implementation of the pilot project
The followings were analyzed for preparation of the pilot project:
(1) Selection of Control and Monitoring Equipment
(2) Conceptual Design of SCADA Systems
(3) Procurement items of JICA side and DJB side
5
10
9
8
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-15
(1) Selection of Control and Monitoring Equipment
1) Selection of Control Valve
Table 3-7 shows variety of valves which are normally used to control water flow in pipes. Control
valves are to be operated by actuator under SCADA, proper adjustment of valve aperture will be
required in case of high water pressure inside pipe. Therefore, butterfly valve is more suitable than
ball valve because it can be operated by using less torque and its mechanism is simple to obtain easy
flow control.
Table 3-7 Characteristic of Control Valve
Butterfly Valve Ball Valve Globe Valve
Diagram
Advantage
Easy flow controlSmall body sizeLess fluid resistanceCompletely closeAvailability in largediameter
Small body sizeLess fluid resistanceCompletely close
Easy flow control
Disadvantage
Beware of mountingdirection
Difficulty in flowcontrolLarge torque is neededfor opening or closingthe valveUnavailable in largediameter
Large torque is neededfor opening or closingthe valve,Unavailable in largediameter
Conclusion Selected
2) Selection of flow meter
Two typical kinds of flow meter are “electromagnetic flow meter” and “ultrasonic flow meter”. The
image of each type is shown in Table 3-8. In case when air gets mixed up with water flow in
pipeline (intermittent water supply will invite air into the pipe), ultrasonic flow meter is unable to
detect the signal of flow velocity and flow data is not measured. Thus electromagnetic type meter
was adopted.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-16
Table 3-8 Characteristic of Flow Meters
Items Electromagnetic type Ultrasonic type
Diagram
Necessary length of straightpipe
Upstream: 5~10D,Downstream: 3D
Upstream: 10D,Downstream: 5D
Advantages
No pressure lossHigh accuracy (±0.5 to 1.0%)Corrosion resistantAvailable in large diameter
No pressure lossLow costVersatility
DisadvantagesExtra care is needed with respectto mounting direction
Influence of air bubbleNeed verification
Adopted
3) Pipe Connection method for Control Valves and Flow Meters
In order to install the equipment such as control valves and flow meters on the existing pipe line, it
is required to cut and remove existing pipe and then connect again after fixing the control valves
and flow meters. If the new pipe does not connect to existing pipe properly, water will leak out from
joints.
The CPWD specifications (2009) did not explain clearly the method of joining new pipe and
existing old pipe. Therefore, contractors usually adopt welding method in case of MS, push-in
method in case of Pre-stressed Concrete Pipe and CIP. In Push-in method, new MS pipe is pushed
into the existing pipe socket like “socket and spigot joint”. Hemp ropes are filled between the
clearance gap, and then lead in the form of liquid is poured into the socket as shown in Figure 3-6.
In pressure condition, universal coupling or stepped coupling shown in Figure 3-7 can be used for
connection between pipes of different outside diameters. These products are available in India.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-17
New pipe was pushed into the existing pipe socket.(Client : DJB)
Lead in the form of liquid was poured into a socket.(Client : DJB)
PSC pipe was replaced by MS pipe due to the leakage, but leakage was found at connecting point causedby the mismatch of pipe diameters and poor workmanship
Figure 3-6 Pipe Jointing Works
Universal Coupling Stepped Coupling
Figure 3-7 Sample of Couplings
(2) Conceptual Design of SCADA Systems
1) Plan for installing SCADA to existing distribution pipe network
Introduction of the SCADA system in the pilot area of Pitampura will enable operators to monitor
the flow/pressure in the pipeline network from the Pitampura BPS to each DMA and to confirm the
water distribution status. Thereby, equitable distribution is expected to be realized under
Existing Pipe(CI)
New Pipe (MS)
Existing PipeSocket
PSC Pipe
MS Pipe
PSC Pipe
MS Pipe
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-18
circumstances where water distribution is restricted to only a few hours a day by remotely
controlling the opening of valves. Figure 3-8 shows the outline of SCADA in the pilot project to
realize the equitable water supply.
Figure 3-8 Schematic of SCADA System
Descriptions of the SCADA system planned for the pilot project are as follows.
2) Introduction of SCADA system to Pitampura UGR/BPS
Figure 3-9 shows the configuration of the SCADA system introduced to Pitampura UGR/BPS.
a) Data collection Server:collect measurement data from PLC of each local station using
wireless communication (GPRS communication)
b) SCADA Server:supervise, control and manage the SCADA client graphic screen
c) Reporting system:generate report for equitable water supply and NRW calculation from
SCADA data
d) Pipe network calculation system:realize real-time pipe network calculation
e) SCADA Client:installed in each office of Pitampura UGR/BPS, E&M, and Civil engineers
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-19
Figure 3-9 Composition of SCADA System
3) Monitoring of flow/pressure
Figure 3-10 shows the measurement points installed in the pilot area. The SCADA monitors
flow/pressure in real time at each 14 measurement points as shown in Figure 3-10. The PLC of the
local panel sends the data on flow and pressure of each measured location to the SCADA through
GPRS transmission in real time and the status information is displayed on the screen of the SCADA
client.
Distribution SCADA is the first attempt at DJB, for example, an interface that allows geographical
understanding of flow/pressure at each measurement point was adopted.
4) Control of valves through the SCADA
Actuators are installed on the valves (13 locations except No.13 in Figure 3-10) to enable operators
to control remote operation of each valve. Operation instructions from the SCADA are passed on to
the PLC of outside panel at the site in order to control the valves.
Location of outside panels is selected such that they can receive power supply easily. For these
electricity meter connections and bill payments are to be carried out by DJB. Therefore, close
coordination among the contractor, DJB and the power company is required.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-20
Figure 3-10 Measurement Points in the Pilot Area
5) Entry of information from the existing SCADA
The existing SCADA of the Pitampura BPS monitors information such as UGR water level, pump
operation time, flow/pressure of the water distribution displayed on the existing SCADA graphics
window as shown in Figure 3-11. This information is required in order to achieve equitable
distribution of water in DMA of pilot area. Existing SCADA information is passed on to the
distribution SCADA.
For this purpose, the existing SCADA needed to be modified. The drawings of existing SCADA
systems was not available, therefore, on the basis of the site visit it was analyzed that branch
connections would be made at the signal cable terminals shown in the PLC panel of existing
SCADA.
Regarding the collection of information from existing SCADA and the installation of the
distribution SCADA at the Pitampura BPS, close coordination was required between the contractor
and DJB during the design and equipment procurement stage.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-21
Figure 3-11 SCADA Graphics Window of Existing UGR
6) Installation of outside measurement stations and GPRS transmission for the water
distribution pipeline network
Local measurement stations (Figure 3-12) are required to monitor flow/pressure and control valves
for the pipeline network. Distribution SCADA system has never been installed in Delhi. Equipment
was stored in the panel which was further fenced for security reason.
Although DJB was responsible for making the contract with telecommunication company regarding
GPRS transmission, coordination related to communication conditions was required between the
contractor and DJB.
Figure 3-12 Local Measurement Stations
Operation Status of
Pumps and Valves
UGR Water Level
Flow Rate
Water
Pressure
Pump
Operation
Time
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-22
7) Real time distribution network hydraulic calculation
In this pilot project, distribution network hydraulic calculation function that operates in real time
was set up to simulate the change in flow/pressure and direction of water pipe due to operation of
valve. With this real-time distribution network hydraulic calculation function, the situation of the
changes in pipeline such as pressure/flow, flow direction of water at places other than the measured
points at every moment is calculated and displayed on clients and SCADA operation can be
performed while visually confirming the influence of the valve operation.
(3) Procurement items of JICA side and DJB side
In the 1st JCC meeting (Aug 2013), input items from JICA side and DJB side were discussed and
decided for this component. Those items are listed in the table below.
Table 3-9 Procurement Items of JICA Side and DJB Side
No. ItemResponsible Organization
JICA(RDS) DJB
ASCADA center、 Instrumentation at
UGR、 Wiring works in UGR and DMAs
BSupply, installation, and commission ofControl valves
CSupply, installation, and commission ofFlow meters
DSupply, installation, and commission ofPressure gauges
E Civil works (Excavation for installation
of equipment)
(Chamber, backfilling and
road restoration)
FSCADA components for DMAs andcontrol points
GOperation cost (electricity、telecommunication)
HObtaining permission from relevantagencies
Pre-bid Meeting on Supply and Installation ofSCADA, 10 March 2014
Kick-off Meeting of Supply and Installation ofSCADA, 11 June 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-23
【2-3-3】Estimate the level of water demand in each DMA
This activity was conducted in December 2013 to confirm size of DMA area, decide size of equipment
such as control valves and flow meters.
(1) Pitampura Pilot Project Area
Housing blocks in nearby DMAs in the Pitampura area is shown in Figure 3-13. Based on the DSSDI
data, number of household (HH) in 3 DMAs is enumerated.
Source; DSSDI, DJB
Figure 3-13 Pitampura UGR Command Area (Sub-Locality wise)
(2) RMS data in Pitampura Pilot Project Area
1) Number of Connection
Table 3-10 shows 2,449 connections8 in total of 3 DMAs as of December 2013.
8 Numbers increased into more than 3,000 in the household survey in 2015 and 2017, detecting illegal connections.
YP
SP
ZP
WP
YP
VP UP
NU
MU
DMA1
DMA2
DMA3
City Center Mall
KPJP
HP
GP
JJ Cluster
RP
QPPP
NP
MP
LP
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-24
Table 3-10 Number of Connection as of Dec. 2013
Block NameNumber of Connection Based on RMS Data
(Households and bulk supply)
MU (DMA 1) 426
NU (DMA 1) 302
Total of DMA 1 728
UP (DMA 2) 179
VP (DMA 2) 108
WP (DMA 2) 703
YP (DMA 2) 185
Total of DMA 2 1,175
SP (DMA 3) 132
TP (DMA 3) 267
ZP (DMA 3) 147
Total of DMA 3 546
Grand Total 2,449
2) Billed Water Volume
DJB calculates the water charges based on the actual consumption of water based on meter reading
data. Meter readers have their defined territory (indicated by Area Code and Meter Reader Code).
Meter readers visit households in their area for reading the meters and they check customer code
and read the existing value of water meter. If any meter reader is unable to check the meter because
of being installed inside house and customer not present at house when meter reader visited, meter
reading is conducted in next cycle of reading. In the case that the meter is not installed or installed
but it is broken down, 0.73 m3/day (5 people x 145 lpcd) is billed as the estimated water
consumption.
Table 3-11 shows the billed consumption data in 2013. DJB charged for approximately 410m 3/day
of water in DMA 1, approximately 690 m3/day of water in DMA 2, and for approximately 260
m3/day of water in DMA 3 as revenue water.
For estimating the actual consumption, it is considered that;
DJB carries out water meter reading (Bill round) four times a year. Billing data in RMS is
put on the bill round in which customer pay their bill. For example, if DJB charges a bill
based on “Bill round 1” and customer pays this bill together with “Bill round 2 and 3”
during Bill round 3, the billing data is registered in “Bill round 3”. For this reason, even if
the customer is using water, if the customer is unpaid, it is not accounted for as the amount
of water (amount of water used) that can be charged.
Billing data includes the provisional consumption. For example, if water meter is broken or
not working properly, DJB charges 0.73m3/day (5 people x 145lpcd) as provisional
consumption.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-25
Table 3-11 Billed Consumption based on RMS Data as of Dec. 2013
BlockName
Billed Consumption (m3) Daily AverageBilled
Consumption(m3/day)
2013-01(Read in
Apr)
2013-02(Read in
July)
2013-03(Read inOctober)
Total
MU (DMA 1) 24,464 21,984 15,190 61,638
NU (DMA 1) 21,567 15,551 11,059 48,177
Total of DMA 1 46,031 37,535 26,249 109,815 Approx.410
UP (DMA 2) 11,598 8,517 7,622 27,737
VP (DMA 2) 5,109 4,320 5,616 15,097
WP (DMA 2) 43,624 43,241 31,439 118,252
YP (DMA 2) 8,499 9,124 8,448 26,071
Total of DMA 2 68,830 65,202 53,125 187,157 Approx.690
SP (DMA 3) 7,345 6,492 5,528 19,365
TP (DMA 3) 8,720 10,841 9,018 28,579
ZP (DMA 3) 7,628 8,130 6,575 22,333
Total of DMA 3 23,693 25,463 21,121 70,277 Approx.260
Grand Total 138、554 128,200 100,495 367,249Approx.
1,360
【 2-3-4】 (a) Construct a demonstration chamber to check its performance, (b)
Implement improvement works for water ingress of the constructed chambers,
and (c) Install the equipment and conduct trial runs of SCADA system
(1) Work Schedule
Activities (a) and (b) were added in March 2016 after water ingress to the chambers was observed in
July 2015. Work schedules were revised many times according to the actual progress Figure 3-14
shows the work schedule (original and revised plans and actual progress).
1) Original Work Plan
Installation of SCADA system was to be completed in April 2014 and afterwards SCADA operation
and technical transfer was scheduled for 2 years.
2) First Revision
Work plan (tendering schedule) was revised due to the followings:
obtaining of road cutting permission and additional road cutting to confirm pipe information,
selection of contractor of SCADA system,
change of contract style (from price competitive bidding to 2 envelope bidding)
JICA concluded the contract with RDS in June 2014.
Th
eA
ssis
tan
ceR
ela
ted
toD
elh
iW
ate
rS
up
ply
Imp
rovem
ent
Pro
ject
FIN
AL
RE
PO
RT
3-2
6
Fig
ure
3-1
4W
ork
Sch
edul
eof
SC
AD
A(O
rigi
nal
Pla
n,
Rev
ised
Pla
ns
and
Act
ual
Pro
gres
s)
Res
po
nsi
ble
67
89
1011
121
23
45
67
89
1011
121
23
45
67
89
1011
121
23
45
67
89
1011
121
23
45
67
89
1011
121
23
JET
JET
Pre
par
atio
no
fB
idd
ing
do
cum
ent
JET
Bid
din
gfo
rSC
AD
AEq
uip
men
tJI
CA
Bid
din
gfo
rch
amb
ers
DJB
Per
mis
sio
n(s
)fo
ro
ccu
pat
ion
of
road
spac
eD
JB
Ro
add
iggi
ng
per
mis
sio
n(s
)fr
om
MC
DD
JB
Co
nst
ruct
ion
of
cham
ber
DJB
Co
nst
ruct
ion
of
Dem
on
stra
tio
nch
amb
eran
dto
chec
kit
s
per
form
ance
JET
Bid
din
gfo
rIm
pro
vem
ent
of
cham
ber
DJB
Imp
rove
men
to
fch
amb
erin
sid
eD
JB
Imp
rove
men
to
fch
amb
erO
pen
ing/
Man
ho
leJE
T
Des
ign
/Do
cum
ents
sub
mis
sio
nfo
rap
pro
val
RD
S
Pro
cure
men
t/Fa
cto
ryTe
stR
DS
Inst
alla
tio
no
fSC
AD
AEq
uip
men
tR
DS
Co
ntr
act
of
elec
tric
ity/
com
mu
nic
atio
nD
JB
Po
wer
sup
ply
wo
rkD
JB
Mea
sure
sag
ain
stel
ectr
icit
yle
akag
eR
DS
Tria
lru
n/
Co
mm
issi
on
ing
RD
S
Ori
gina
lTas
k
Act
ualP
rogr
ess
Rev
ised
Task
asof
27D
ec20
16(R
DS'
sam
endm
ent
cont
ract
)
Rev
ised
Task
asof
19Ju
ne20
17(R
DS'
sam
endm
ent
cont
ract
)
3rdYe
ar
Rev
ised
Task
asof
10th
Mar
ch20
16(5
thJC
C)
Rev
ised
Task
asof
05Ju
ne20
14(R
DS'
sor
igin
alco
ntra
ct)
Rev
ised
Task
asof
Aug
ust
2016
(RD
S's
amen
dmen
tco
ntra
ct)
2014
2-3
-4.
(a)
Co
nst
ruct
ad
em
on
stra
tio
nch
amb
er
toch
eck
its
pe
rfo
rman
ce
1stYe
ar
Lege
nd:
2-3
-1.R
eco
nfi
rmth
eco
nfi
gura
tio
no
fth
ee
xist
ing
dis
trib
uti
on
ne
two
rkw
ith
inth
ep
ilo
tp
roje
ctar
ea
and
fin
aliz
eth
e
imp
lem
en
tati
on
pla
no
fth
ep
ilo
tp
roje
ct
2-3
-2.E
stim
ate
the
leve
lof
wat
er
de
man
din
eac
hD
MA
2-3
-3.P
rocu
ree
qu
ipm
en
tn
ece
ssar
yfo
rim
ple
me
nta
tio
no
fth
e
pil
ot
pro
ject
Year
2013
2016
Item
s
2-3
-4(c
)In
stal
lth
ee
qu
ipm
en
tan
dco
nd
uct
tria
lru
ns
of
SCA
DA
syst
em
2-3
-4.(
b)
Imp
lem
en
tim
pro
vem
en
tw
ork
sfo
rw
ate
rin
gre
sso
fth
e
con
stru
cte
dch
amb
ers
201
8
5th
Yea
r
2017
4thYe
ar2n
dYe
ar
2015
Han
do
ver
toD
JB
WaterIngresstoChamber
5thJCC
FailureofActuators
▲St
op
▲St
op
▲St
op
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-27
Table 3-12 Steps of Tender Process
Public Announcement of Tender24th February 2014 to 28th February2014 (on JICA India website)
Period of showing interest by Tenderers24th February 2014 to 28th February2014
Number of firms documents issued 3 firmsDate of pre-bid meeting (including site visits) 10 March 2014Submission and Opening Date of Technical Tender 1 April 2014Submission and Opening Date of Financial Tender 2 May 2014Date of issue of Contract Award 15 May 2014
Date of Signing the Contract5 June 2014, Contractor: RecktronicDevices and Systems (RDS)
Table 3-13 shows work schedule in the contract document submitted by RDS.
Table 3-13 Work Schedule of SCADA Installation by RDS
Preliminary Survey and Submission of Documents Jun-Jul 2014Submission of SCADA design for the Employer’s Approval Jul-Aug 2014Purchase Order Aug 2014Factory Inspection of Equipment and Delivery Sep- Nov 2014Installation of Equipment Oct 2014 - Jan 2015Site Inspection and Commissioning of Equipment Dec 2014 - Feb 2015Test Operation and Handover of SCADA System 2 May 2015
SCADA works were provisionally completed in July 2015 behind the schedule of RDS. The major
reasons of delay are shown below.
<Major reasons of delay>
a) Submission of SCADA design documents for approval was delayed and subsequently approval
of equipment manufacturing was delayed by 3 months (planned July to August 2014, actual July
to November 2014)
b) Specification of pipe material required confirmation of pipe material after trial digging.
However, DJB did not apply digging permission requested by RDS to the concerned road
agencies for a long period being afraid that the permission would not be obtained due to large
size of road digging. So the contractor could not get approval of road digging from the
concerned road agencies on time. Therefore, RDS could not order pipe materials in early stage.
(planned September to November 2014, actual October 2014 to June 2015)
c) Pipe material could not arrive at site on schedule due to the delay in pipe manufacturing. Date
of delivery is very flexible in India even if delivery time is mentioned on manufacture’s invoice.
(planned September to November 2014, actual October 2014 to June 2015)
d) Some section of distribution pipeline where valve and flowmeter were to be installed was
diverted due to the site condition (Drainage was found close to the distribution pipe. Therefore,
no space was available to construct chamber). Preparation of this contract deviation by RDS
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-28
was delayed.
e) Power supply work to be conducted by power supply company was delayed due to the lack of
human resources and materials during high demand season (in peak summer). (planned May
2015, actual July to August 2015)
PLC Panel installation(Location No.4)
Valve and Flowmeter installation(Location No.2) 25 May 2015
Flowmeter installation(Location No.4)
3) Second Revision
Water ingress was observed in July 2015 when SCADA equipment was almost installed. Fearing
electricity leakage leading to damage to equipment, RDS suspended installation of the actuators to
the electrically-driven control valves. Completion date of SCADA installation was deferred to April
2016 from the original date of March 2015 in the revised contract between JICA and RDS.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-29
Ingress of water was observed inside chamber(Location No.6) 11 August 2015
Ingress of water was observed inside chamber(Location No.11) 11 August 2015
4) Third Revision
In the 5th JCC meeting (March 2016), JICA and DJB agreed to take measures to prevent water
ingress to the chambers and to extend the Project period by 1 year and 8 months until March 2018.
The measures were to improve the water resistance of the chamber and install a water level sensor.
In order to confirm the effectiveness of the measures proposed by JET, a demonstration chamber
was constructed from April to May in 2016, and confirmed as effective in August 2016.
In addition, as the installation work of the water level sensor was additionally carried out by the
RDS, time limit of the SCADA equipment delivery was changed to February 2017 accordingly.
Table 3-14 Improvement Works
PlannedWork
ScheduleStep Purpose Measures
April toAugust2016
1st Step
Reduction of water ingress byimprovement of watertightness of chamber againstwater
・ Sealing of gaps between the opening andsupporting frame
・ Improvement of water tightness between themanhole and supporting frame
・ Water-proof mortar coating to walls and slabs(Construction of demonstration chamber andimplementation of water-proof test on theconstructed demonstration chamber)
Augustto
December 2016
2nd StepCut-off electricity supplybefore the equipment issubmerged
・ Detection of water level in chambers and shuttingdown of electricity before the water levelsincrease beyond safe level
3rd StepSecurity enhancement in caseof failure of 2nd step above
・ Equipment and cables with appropriatewaterproof performance (procured mainequipment already conformed to IP68)
・ Electrical grounding and earthing system, earthprotection relay, circuit breaker
August2016 to
February2017
1st to3rd
Proper safety measures worksupervision
・ Quality assurance of electric cabling worksupervised by the local expert hired by JET
・ Appropriate periodical maintenance of SCADAequipment by DJB
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-30
5) Fourth Revision
DJB finished improvement works to the chambers in December 2016 while RDS started
improvement works of the SCADA system in January 2017 after the contract revision. Delivery
deadline was also extended to August 2017 in the revised contract.
During improvement works, the followings were observed:
1) Limited spaces in chambers at 7, 8 and 14 to install pressure gauges
2) Malfunction of flow meter at No.10
3) Delay of power connection contract and payment
4) Malfunction of data transferring system between the center and chambers
DJB contracted MTNL, telecommunication company in June 2015 where the communication
service was planned to start in February 2017. However, it actually started in June 2017. In addition,
as the connectivity is not stable, so the provider was changed from MTNL to Airtel. Out of the 14
connections, 8 were again changed from Airtel to Vodafone.
6) Fifth Revision
Water ingress to the chambers was observed again in June 2017. Additional improvement works to
chambers were conducted with change of completion date of SCADA system from August 2017 to
September 2017.
During SCADA trial runs starting from September 2017, many defects were found and repaired. In
December 2017, after repairs of all defects, SCADA system was completed. Operation of the
SCADA started in December and the technical transfer lasted to March 2018, only 4 months from
the originally planned 2 years.
7) Progress Meetings on SCADA Procurement
The meetings were held 25 times between July 2014 and November 2017 to coordinate the works
among DJB, JICA, RDS, the civil contractor (Koli) and JET. The details are attached to
Attachment-7.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-31
Progress meeting on SCADA procurement atPitampura Pilot Project among JICA India,
JICA’s contractor, JET, DJB and DJB’scontractor on 15 December 2016
Progress meeting on SCADA procurement at Pitampura PilotProject among JICA India, JICA’s contractor, JET, DJB and
DJB’s contractor on 23 February 2017
【2-3-4】(a) Construct a demonstration chamber to check its performance
(1) Water Ingress to Chambers
The chambers were constructed by DJB to house control valves and flow meters. After the
construction, water ingress was observed in some of the chambers during rainy season.
Chamber No.9 under construction
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-32
Table 3-15 Water Ingress into Chambers
LocationInternal Size of Chamber Water Ingress
Equipment (by RDS)(constructed by DJB) July 2015 July 2016 July 2017
1W 2.70m x L 2.25m x D 2.30m No No No Control Valve (900mm)
W 2.70m x L 1.86m x D 2.30m No No No Flowmeter (900mm)
2W 2.30m x L 1.87m x D 2.20m No No No Control Valve (500mm)
W 2.30m x L 1.54m x D 2.20m No No No Flowmeter (500mm)
3 W 2.20m x L 2.64m x D 1.60m No NoNo Control Valve and Flowmeter
(150mm)
4 W 2.20m x L 2.64m x D 1.50m No NoNo Control Valve and Flowmeter
(150mm)
5W 2.70m x L 2.15m x D 1.70m No No No Control Valve (800mm)
W 2.70m x L 1.82m x D 1.70m No No No Flowmeter (800mm)
6W 2.30m x L 1.87m x D 1.50m Yes Yes Yes Control Valve (500mm)
W 2.30m x L 1.54m x D 1.50m Yes Yes Yes Flowmeter (500mm)
7 W 2.20m x L 2.71m x D 1.50m Yes YesYes Control Valve and Flowmeter
(200mm)
8 W 2.20m x L 2.71m x D 2.20m Yes YesNo Control Valve and Flowmeter
(200mm)
9 W 2.20m x L 3.11m x D 2.10mNot
constructed
Not
constructed
No Control Valve and Flowmeter
(250mm)
10 W 2.20m x L 3.11m x D 1.60m Yes YesNo Control Valve and Flowmeter
(250mm)
11 W 2.20m x L 3.36m x D 1.50m Yes YesNo Control Valve and Flowmeter
(300mm)
12 W 2.20m x L 2.54m x D 1.50m No NoNo Control Valve and Flowmeter
(100mm)
13 W 2.20m x L 1.50m x D 1.50m No No No Flowmeter (100mm)
14 W 2.20m x L 2.64m x D 1.60m Yes YesNo Control Valve and Flowmeter
(150mm)Notes: Refer to Figure 3.1 for the location MAP.
For the pipe with a diameter of less than 300mm, the control valve and flowmeter are installed in the same chamber.For the pipe with a diameter of more than 500mm, they are installed in separate chambers.
(2) Countermeasures against Water Ingress
The countermeasures against water ingress to the chambers which occurred in July 2015 were agreed
in December 2015 between DJB and JICA. They were confirmed in the 5th JCC meeting in March
2016. The demonstration chamber was built as the first step and the effectiveness of the
countermeasures were approved in the 6th JCC meeting held in August 2016. Table 3-16 shows the
background of countermeasures.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-33
Table 3-16 Countermeasures against Water Ingress to Chambers
ResponsibleOrganization
JET DJB JICA (RDS)
PeriodConstruction of a demonstration
chamber and confirmation ofeffectiveness of countermeasures
Improvement work ofchambers
Countermeasuresagainst electricity
leakage
March 2016- Implementation of improvement
works was approved at JCC.April – May
2016- Construction of demonstration
chamber
Construction supervision(OJT)June – July
2016
- Water resistance test usingdemonstration chamber
- Examination and determination ofwater resistance improvementmethod of chamber
- Water resistance test using ademonstration chamber in the rainyseason
August 2016- Confirmation and final inspection of
flood condition of rainy season indemonstration chamber
Same as left
Quotation onadditional leakagecountermeasureconstruction
August –September
2016
- Decision of specification ofimprovement work to the existingchamber
- Work order of improvementwork for 13 chambersexcept No. 9
- Acquisition of road cuttingpermission for No. 9chamber
- Estimate evaluationand Contractnegotiation
October –December
2016
- Construction management support ofDJB construction (right) andtechnology transfer
- Implement improvementwork (side wall, top plate,bottom plate) of 13 existingchambers except No. 9
Contract
January –April 2017
- Promotion of acquisition of roadcutting permission for constructionof chamber No. 9
- Support for supervision of chamberNo. 9 construction by DJB
- Acquisition of road cuttingpermission for constructionof chamber No. 9
- Construction of chamberNo. 9
- Installation ofSCADA equipment
- Support of No. 10 chamberconstruction supervision by DJB
- Water leakage detection andpipe repair near the chamberNo. 10
- Reconstruction of chamberNo. 10
May –September
2017
- Waterproofing work of openings forall 14 locations chambers
- Power supply for all 14locations chambers
- Installation ofSCADA equipment
(3) Construction of the demonstration chamber
In May 2016, JET and DJB constructed the demonstration chamber. This chamber was constructed
with the same specifications as DJB’s to confirm the water resistance of the chamber already
constructed by DJB and the effectiveness of improvement measures.
1) First Test
It was confirmed that water entered into the demonstration chamber.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-34
2) Second Test
After waterproofing work was carried out, the water resistance of the chamber was confirmed. With
this improvement work, water ingress through the walls and the top slab opening was prevented, but
through the top slab was observed due to its poor construction.
3) Third Test
Based on the result of the second test, the necessity is confirmed to improve the top slab on inside
the chamber, and additional improvement work was carried out. As a result, water ingress almost
lost. DJB's civil engineering manager (EE, NW) witnessed JET's resistance tests and confirmed its
effectiveness
Figure 3-15 Demonstration chamber
4) Final Test
In rainy season of August 2016, the water ingress to the demonstration chamber was observed and
then the improvement plan of the chamber was prepared.
Demonstration Chamber Constructionby DJB and JET
Discussion on Improvement Measures against WaterIngress to Chamber by DJB and JET
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-35
Water Proof Test on Side Wall of DemonstrationChamber
Water Proof Test on Top Slab of DemonstrationChamber
Meeting on Improvement of the ConstructedChambers among JET, DJB and Contractor
Chamber Improvement Work
Inspection by JET onImprovement of Constructed Chamber
(4) Other Measures
There was groundwater nearby the No. 10 chamber, and there was a risk of water ingress to the
chamber. So, JET requested DJB to investigate the source of the groundwater at the No.18 progress
meeting on SCADA procurement on 15 December 2016, but it was not identified by DJB. To
investigate the source, JET examined the groundwater using the simple residual chlorine kit, and
found that the source of groundwater was tap water (leakage water) containing chlorine. At the request
of JET, DJB found and repaired one illegal house connection and one inappropriate drain connection.
However, due to continued water leakage, DJB abandoned the detection of water leakage, and instead
eliminated the pipe and laid a bypass pipe.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-36
Furthermore, the chamber No. 10 could possibly be submerged again in the future because there was a
problem with the construction quality of base slab and this chamber itself interferes with the sewage
underdrain. At the No.19 progress meeting on SCADA procurement on 23 February 2017, JICA and
DJB agreed to re-construct the chamber No. 10 to reduce the risk of future water ingress. DJB
constructed the chamber No. 10 again from February to April 2017 under the support of construction
supervision by JET.
(5) Guideline
The manholes will be opened and closed sometimes for maintenance of chamber and SCADA
equipment in future. As a result, the waterproofing function of the manhole cover is lost. In order for
DJB to acquire know-how to continue waterproofing by them in the future, JET transferred the method
of waterproofing measures to DJB through OJT. Furthermore, the method is summarized in the
guideline in Appendix 10 that includes SCADA operation and NRW calculation (refer to activity
2-3-11.
【2-3-4】 (b) Implement improvement works for water ingress of the constructed
chambers
In the 6th JCC meeting held in August 2016, implementation of the improvement plan for chambers
was approved. Thereafter, DJB undertook water resistance improvement work for inside of chamber
that was constructed at 13 locations except for No. 9 which was still not constructed. Through support
of construction supervision, JET conducted technology transfer to DJB on construction supervision
method.
The content of the improvement work implemented by DJB is shown in Figure 3-16.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-37
Figure 3-16 Countermeasures to Chambers Constructed by DJB
JET also conducted the improvement works at manholes and openings in all chambers after
installation of actuators and other equipment by RDS. They are shown in the Figure 3-17.
1) Opening
Openings will be sealed completely with steel plate (3 mm thick), sealing material (silicon
sealant), jute rope and waterproof mortar because the openings are not required to open after the
equipment is installed inside the chambers.
2) Manhole
Manhole covers will be sealed with rubber material (rubber packing for pipes, Delhi Schedule of
Rates Item No. 1384), sealing material (silicon sealant), jute rope and covered again by sealing
material so that they can be opened easily when required for inspection of equipment installed in
the chambers and sealed back again easily.
Man-hole Openings
V MDistribution Pipe
DJB WorkWaterproofing Mortar (15mm)
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-38
Figure 3-17 Improvement Works of Constructed Chambers by JET
【2-3-4】(c) Install the equipment and conduct trial runs of SCADA system
(1) Trial Run of SCADA by RDS
The following defects were found in October 2017 during the trial runs:
Malfunction of flow signal at No. 2 chamber
Malfunction of pressure signal at No. 12
Malfunction of actuators at Nos.3, 8, 7, 9, 10, 11 and 12
Inspections were carried out jointly by RDS, DJB and JET on 25 and 27 October 2017 to identify the
remaining defects and work schedule of the remedial works. Inspections were again carried out jointly
on 29 and 30 November 2017 to confirm the repair of the defects identified in the previous inspection.
Most of the defects such as SCADA equipment, display of panels, roof and fences of the local stations,
cablings were repaired except 5 minor items. RDS repaired those 5 minor items by 14 December 2017
and SCADA system was completed.
(2) Completion Certificate
JET issued a completion certificate to JICA India office on 14 December 2017 who finalized the
contract with RDS. DJB (Addl. CEO) signed a completion certificate of SCADA system on 14
December 2017 and started its operation and maintenance.
(3) Training of SCADA
JET and RDS conducted trainings on outline and operation of SCADA system from 20 to 25
September 2017. Additional training comprising lecture and actual SCADA operation was conducted
from 29 November to 1 December 2017 when SCADA system was practically functioning.
Test was also conducted to check trainees’ understanding of the SCADA system which confirmed their
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-39
good understandings.
(4) Development of Trainers
Table 3-17 shows the participants in the trainings who attended more than 6 days out of the 8-days
training and passed the test. Certificate of the training was issued to them by DJB and JICA India
office in the 6th seminar. They will be the trainers for the internal training held in future.
Table 3-17 Participants in the Training
No. Name Position
1 U. K. Rastogi Executive Engineer (E&M)
2 Gaurav Yadav Assistant Engineer (E&M)
3 P. C. Gupta Assistant Engineer (E&M)
4 Kuldeep Junior Engineer (E&M)
5 Mukesh Jindal Executive Engineer (Civil)
6 Sandeep Sharma Zonal Engineer (Civil)
7 Pramod Prasad Junior Engineer (Civil)
8 Ram Swarup Assistant Engineer (Civil)
9 Yogendra Singh Junior Engineer (Civil)
【2-3-5】Monitor flows and pressures within the pilot project area through SCADA
system
The SCADA screens used for monitoring are as follows.
1) SCADA Overall Monitoring Screen (Figure 3-18): it can geographically grasp pressure/flow,
valve opening percentage and operating condition (normal: green, abnormal: red) of all
measurement points on one screen
2) UGR Monitoring Screen (Figure 3-19): it can grasp the reservoir level and the operation status
of distribution pump of Pitampura UGR/BPS
3) Measurement point monitoring and operation screen (Figure 3-20): it can grasp concrete
pressure /flow, valve opening degree and condition at the measurement point and operate the
valve
4) Example of measurement point report (Figure 3-21): it can generate print and save as excel
format data of each measurement point.
JET transferred procedure to the trainees in the training held from 20 to 25 September 2017 for EE (E
& M) to record daily monitoring results and sends the result to JET. DJB acquired flow and pressure
data from SCADA from October 2017 and reported the monitoring results to SCADA experts (JET)
via email on weekly basis.
From December 2017, when installation of SCADA was completed, DJB officially launched the
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-40
monitoring operation (SCADA operation, report preparation, etc.) of SCADA.
In the second week of December 2017, the baseline survey on the current distribution network was
conducted and the report of SCADA monitoring was prepared at DJB. Especially, the current
condition on the hydraulic situation (directions and rate of flow) and the amount of inflow to each
DMA and inflow pressure in the pilot area was confirmed and their trends were grasped.
Although there were some system troubles and failures, DJB responded well and JET confirmed
whether the monitoring operation by DJB was performed properly, and whenever there was a problem
on a daily task, JET advised DJB on the solutions.
Figure 3-18 SCADA Overall Monitoring Screen
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-41
Figure 3-19 UGR Monitoring Screen
Figure 3-20 Measurement Point Monitoring and Operation
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-42
Figure 3-21 Example of Measurement Point Report
【 2-3-6 】 Monitor inequitable water supply in DMAs and study how to control
flow/pressure to enhance equitable water supply
After inequitable water supply was observed among DMA 1, 2 and 3, pressure /flow control method
for equitable water supply was analyzed and the measures for equitable distribution were sought
through SCADA operation.
(1) Hydraulic Isolation of DMA
Zero pressure tests were conducted after completion of the SCADA system.
As a result, DMA 1 was confirmed hydraulically isolated because of zero pressure inside of DMA 1
when inlet valve was closed.
DMA 2 and DMA 3 were found not to be isolated hydraulically. DMA 2 shows slightly positive
pressure when closing the inlet valves indicating small-sized pipe connection to outside of DMA 2.
Pressure in DMA 3 shows almost the same pressure outside of DMA 3 indicating large-sized pipe
connection.
As a result, pressure and flow were controlled for DMAs 1 and 2.
(2) Problems related to equitable water supply
After the start of operation of SCADA from December 2017, (E&M) EE, AE, JE, (Civil) EE, AE, JE
and JET analyzed the result of monitoring of water supply situation based on SCADA monitoring
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-43
report. As a result, the following were set as conditions concerning equitable water supply.
1) The amount of water distributed in other than three DMAs will not be changed
2) Inflow valves into DMA will not be closed fully including in non-water supply time
(3) Consideration of equitable water supply
Based on the SCADA monitoring report of 4 th to 10th December 2017 prepared by DJB, baseline water
pressure and flow were set up as follows:
1) Pressure
The average values of the baseline pressure measurements are shown in Table 3-18. The gap of
pressure difference between DMA 1 (1.54 kg/cm2) and DMA 2 (1.59 kg/cm2) in Table 3-18 was
0.05 kg / cm2 (0.5 m).
Table 3-18 Baseline of the Average Outlet Water Pressure (kg/cm2) of DMAs
DMA No. Location No. Pressure Baseline
1 7 1.54 1.54
2
4 1.61
1.5914 1.57
9 1.60
2) Flow
Table 3-19 shows the average value per connection for baseline flow rate measurement. In this
Table, the gap of difference in flow rate between DMA 1 (maximum value 0.73 m 3/day) and DMA 2
(minimum value 0.62 m3/day) was 0.11 m3/day (110 L/day).
Table 3-19 Baseline of the Avg. Volume/Connection (m3/day) of DMAs
DMA No.Location
No.Flow (m3/day) Connection (No)
Baseline(m3/day/No)
1 7 599.4 821 0.73
2
4 331.0
2015 0.6214 560.9
9 350.9
【2-3-7】Implement the flow/pressure control and confirm its effectiveness
In order to reduce the gap of the inequitable flow/pressure in DMA 1 and 2 in Activity 2-3-6, equitable
water supply operation had been tried using SCADA.
In order to secure the pressure and flow rate according to the amount of water used, the opening of the
valve had been controlled. While monitoring the flow rate and pressure of each DMA with SCADA,
trial of valve opening operation of each DMA had been repeated and carried out by JET and DJB with
evaluation in February 2017.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-44
(1) Result of pressure adjustment
The results of pressure adjustment are shown in Table 3-20. The pressure difference of 0.05 kg/cm2
(0.5 m) in Table 3-20 was reduced to the difference of 0. 02 kg/cm2 (0.2 m) between DMA 1 (0.77
kg/cm2) and DMA 2 (0.79 kg/cm2) by pressure control.
Table 3-20 Values of Average Pressures to DMAs after SCADA Operation
DMA No. Location No. Pressure After SCADA Operation
1 7 0.77 0.77
2
4 0.77
0.7914 0.73
9 0.86
(2) Result of flow adjustment
The results of flow adjustment are shown in Table 3-21. The flow difference of 0.11 m3/day (110 l) in
Table 3-21was reduced to the difference 0 m3/day (0 l) between DMA 1 (0.62 m3/day) and DMA 2
(0.62 m3/day) by flow adjustment.
Table 3-21 Average Inflow to DMA with Connection Number in DMA after SCADA Operation for
Equitable Water Distribution
DMA No.Location
No.Flow (m3/day) Connection Baseline
1 7 509.0 821 0.62
2
4 259.8
2015 0.6214 571.4
9 418.0
Note: The valve at location No.8 in DMA 3 could not be operated properly since DMA 3 is probablynot hydraulically isolated. During the Project, hydraulic isolation could not be completed.
【2-3-8】Calculate the total volume of water billed to the customers in the area based on the
RMS
(1) First Survey of Billed Volume (2015)
NRW is estimated by calculating the difference between the amounts of water supplied (input volume)
and the amount of water billed in a particular target area. The amount of water supplied is measured by
using SCADA. In order to estimate the total amount of water billed, JET firstly identified customers
and collected and organized the customers’ water usage data in the area.
The consumption data in RMS was analyzed. Based on the results of the analysis, it was revealed that
DJB couldn’t conduct all households meter reading and the quantity of water consumption in RMS
was often input as the average value. Factors that hinder households meter reading are as follows.
1) The setting position of the meter is not decided by DJB. Therefore, the customers install meter
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-45
inside their house to prevent theft.
2) Because of the above reason, when nobody is present in any household, it is not possible to
read the water meter and the meter reader must visit the same household many times.
3) When the meter is broken, the corrective action is not decided by DJB because the meter is
owned by the customer.
Monitoring of Installed Meter28 Feb 2015
Monitoring of Installed Meter28 Feb 2015
(2) First door to door survey (2015)
This survey was undertaken in accordance with the decision taken in the 4 th JCC meeting (September,
2015). DJB conducted the door-to-door survey along with JET to cover all customers in DMA1 to 3
(about 3,400 households). As a result, DJB could grasp the situation of actual unauthorized
consumption as DJB can connect KNO, which is a management number of RMS, with a customer
management number of the GIS through this door to door survey.
This investigation was completed by October, 2015 by the survey team (this team consisted of Mr.
Yogendra Singh (JE, Civil) as the team leader and assisted by 12 other staff members) which was set
up in DJB Pitampura Office by Mr. Vikram Singh (SE (Project) Water III).
Table 3-22 Result of the Door to Door Survey
As a result of the door to door interaction with customer, the number of households that could be
categorized as water theft is found as 131 nos. It is about 4% of the total number of households
surveyed (i.e. about 3,400). In addition, unidentified pipes (The pipe which is not in use anymore as
users have migrated or for cases in which it is difficult to identify users due to absence) were found at
644 locations. The sum is 775, i.e. about 23%.
No. of HouseholdSurveyed
Illegal connection Unidentified pipe
DMA1 821 13 95
DMA2 2,015 105 529
DMA3 566 13 20
Total 3,402 131 644
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-46
Pic1 Meeting before door to door survey Pic2 Meeting before door to door survey
Pic3 Door to door survey Pic4 Door to door survey
(3) Integration of GIS data with RMS data
The data based on the survey results consists of the customer information (about 3,100 cases) which
has already been allocated a unique identification number in GIS along with other customer
information. Other than that (about 300 cases) have not yet been allocated unique identification
number in GIS as they are new customers.
DJB updated data that already has the unique identification number allocated in GIS.
(4) Second door to door survey (2017)
DJB conducted again the door-to-door survey in 2017 and made a list of the latest number of the
meters and KNO. Comparing RMS data with these findings, DJB calculated the latest billed
consumption volume.
DJB used the revised survey format and visited several times to houses to collect accurate information
when found absent in the first visit. The latest information on house connection is required, however,
the door to door surveys on the saturated and developed areas where movement of houses are few,
may take place once in 10 year.
【2-3-9】Calculate NRW ratio in the area
DJB calculated NRWs of DMAs based on the billed water volume of activity 2-3-8 and input volume
to DMAs obtained from SCADA system.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-47
(1) SCADA Data (System Input Volume)
EE (Civil), DJB calculated the average input volume from SCADA data dividing the accumulated one
in the monitoring period by number of monitoring period.
(2) Billed Authorized Consumption Volume
DJB obtained the latest RMS data in all Pitampura area in February 2018. DJB extracted data of each
DMA using KNO of RMS data and door-to-door survey results and calculated the billed water volume
in each DMA. The latest RMS data is shown in Table 3-23.
Table 3-23 Billed Water Volume and Number of Connection in 2017
Billed Water Volume (liter /connection /day) Number of Connection in 2017
DMA1 392 796
DMA2 1,005 1,990
DMA3 1,335 435
Total 2,732 3,221
(3) Calculation of NRW ratio
NRW was calculated in DMA 1 only and it was 60 %.
NRWs in DMAs 2 and 3 will be calculated after confirmation of hydraulic closure of DMAs 2 and 3.
NRW was calculated by EE (civil) but is to be calculated by DMA cell headed by Director (Revenue)
from April 2018. EE (civil) will be a lecturer when long-term training is conducted that was already
programmed by the Training Cell.
Table 3-24 Calculated NRW Ratio
Input VolumeBilled WaterVolume
NRW Ratio Note
DMA1 987 392 60%
DMA22,000 1,005 50%
Provisional due to incompleteDMA
DMA3 - 1,335 -
【2-3-10】Demonstrate leakage detection activities in the area
(1) Preparation of Demonstration
Technology of leakage detection practiced in Japan was demonstrated to DJB (particularly LDI unit of
DJB) using equipment brought from Japan. The site was selected after survey in 3 DMAs. The
followings were taken into account during the demonstration:
1) Noise emitting from leakage is difficult to detect due to heavy use of private pumps during
supply period in the mornings and evenings.
2) Correlator leakage detectors need valves or fire hydrants to connect directly to pipe but
adequate number of valves are not available in the pilot project area.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-48
3) LDI unit of DJB has leakage detection equipment such as acoustic rod, electric leak detector,
correlator, pipe locater, and metal locater, however, are not acquainted fully to them.
Electrical devices seem to be not calibrated.
(2) Implementation of Demonstration
The demonstration was held at DMA 1 in the early morning of 25 August, 2014. Approximately 50
participants attended the demonstration, consisting of approximately 30 persons from DJB including
Addl. CEO and 20 persons from Japanese side.
An explanation about water leak detectors (acoustic rod, electronic leak detector and electromagnetic
metal pipe detector) was made at Pitampura UGR/BPS, followed by OJT with water leak detectors. TS
Leak Checker (time integration method), which can help to rapidly detect water leak point and easily
handle without expertise, was introduced at that time.
Most of the participants from DJB including Addl. CEO experienced handling of the water leak
detectors and detecting buried pipes and water leak locations. The LDI unit received guidance directly
from JET to handle not only the devices brought by Japan but also the devices owned by DJB
(acoustic rod, electronic leak detector and electromagnetic metal pipe detector), which has not been
used because no one is aware of use of these devices.
JET made a presentation about outcomes of the demonstration in 3 rd seminar held on August 2014.
The major issue of high NRW rate in Delhi was presumed water leak and DJB showed keen interest in
the issues with several questions in the seminar.
Meeting of Leak Detection Demonstration forwater supply condition with DJB Zonal Engineer
Site Selection for Leak Detection Demonstration with DJBZonal Engineer
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-49
Meeting with DJB (LDI) staff to confirm theirequipment of leak detection
Equipment of leak detection and pipe locator owned byDJB
Technical Assistance for Leak Detection23 August 2014
Technical Assistance for Leak Detection with LDI23 August 2014
Leak Detection Demonstration-125 August 2014
Leak Detection Demonstration-225 August 2014
【2-3-11】Prepare manual and guideline for flow/pressure control and NRW monitoring
The manual was compiled as SOP (Standard Operating Procedure) together with RDS that are
attached in Manual (SOP) of Appendix 10.
Since October 2017, when SCADA system began operation, EE (E & M), DJB started preparation of
the weekly monitoring reports and sent them to JET and further sent to CE (West) to strengthen DJB's
SCADA operational capacity. This procedure is described in the guideline that is attached in
“guideline” of Appendix 10 with DJB.
In discussion with EE (E&M) at the end of October, JET consulted and agreed on the draft table of
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-50
contents of guideline for maintenance of the chambers and procedures related to SCADA system
maintenance.
Furthermore, by the 3rd week of December 2017, JET and DJB assigned the responsible person in DJB,
the procedure of equipment inspection, the regular reporting system, the procedure of equitable water
distribution by SCADA and calculation of the NRW rate, maintenance of the chamber and SCADA
with DJB along with the guideline’s table of contents
DJB and JET agreed in February 2018 to store the manual/guideline in the DJB Library so that they
can be accessible to all interested DJB engineers.
【2-3-12】Hold a seminar to disseminate the scope and outcome of the pilot project
across the entire DJB
In the 5th seminar held in August 2017, the objectives of introduction of SCADA, details of pilot
project, SCADA function, etc. were presented by E&M engineers in Pitampura and JET jointly.
In the 6th seminar held in February 2018, DJB's engineer in Pitampura presented introduction of the
SCADA system, the results of the activities 2-3-5 to 2-3-11 of the equitable water supply and the
calculation of NRW rate, introduction of the guideline, future training plan, O&M system and
challenges for the future.
【2-4】Identify issues that need to be addressed for further enhancement of equitable
distribution and NRW monitoring
The know-hows gained and the issues encountered in the pilot project are expected to contribute to
achievement of equitable water distribution in the Chandrawal WTP command area being developed
in the Japanese ODA loan project.
In order to share these findings within the DJB, DJB will make use of this SCADA system as a
training center to realize equitable water distribution in the entire Delhi.
The issues explained below are identified essential as a result of the Output 2 activity to achieve
equitable water distribution and NRW reduction.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
3-51
(1) Hydraulic isolation of DMA
Isolation of DMA should be maintained when new pipe lines are laid. In parallel, information on new
pipe lines should be updated in the Mapping Cell. Engineers responsible for pipe laying should
provide new information to the Mapping Cell.
(2) Optimization of pipeline
Equitable water distribution can be achieved by operation of valves by SCADA. In addition, pipe
network system (diameter, route etc.) should be adequate to distribute water smoothly.
Further, in order to achieve continuous water supply and to provide equitable and stable water supply,
the following steps are also required and introduced besides introduction of distribution SCADA and
prompt calculation of NRW rate.
Step1: Ensuring adequate amount of water by reducing NRW, especially the water leakage
Step2: After securing water volume, increase the discharge pressure of BPS
Step3: Shifting to 24x7 water supply and stopping of individual booster pumps and roof-tanks.
(3) DMA Cell
DMA cell currently calculates NRW in 33 DMAs and DJB needs to include NRW in the 3 DMAs of
the pilot project. DMA cell deals with mainly revenue issues and needs to extend its activity from
calculation of NRW to reduction measures of NRW. So cooperation between revenue side and civil
side is required.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-1
CHAPTER 4 OUTPUT 3 (Draft of scenarios for stage wise
development of GIS/RMS application in DJB is
prepared)
DJB has been facing vicious administration cycle: existence of the old facilities, inadequate operation
and maintenance of the old facilities, high ratio of NRW, worsening of financial balance and
insufficient budget for operation and maintenance and aging increase of NRW ratio. In order to break
this vicious administration cycle, ways leading to financial improvement to secure adequate O&M cost
need to be sought by setting of water charges covering for investment cost based on renewal timing of
facilities, and prolonging lives of the facilities by proper O&M. For such a purpose, GIS/RMS is very
useful tools to acquire data for administrative decision making. GIS/RMS data can be used to analyze
and visualize facility conditions, O&M conditions and financial condition.
GIS is often used as a tool to manage data on utilities such as water supply facilities, particularly
pipelines that are laid underground and invisible. By collecting and organizing sufficient data,
application of GIS can be expanded. The GIS/RMS application scenario was formulated in the Project
to help strengthen DJB’s management and financial position based on clear understanding of visions
of DJB.
The long-term and medium-term scenarios and asset management guideline upto 2021 in terms of
development and utilization of GIS/RMS were prepared and submitted to DJB in March 2015. Terms
of reference for the component 5 of Japanese ODA loan project, that is GIS data for the water facilities
in whole of Delhi and the asset management plan of DJB, is to be prepared based on this guideline.
Output 3 was implemented mainly by the following members.
DJB JET
Vikram Singh
S. E. (Project) W-III
Yoichi Yamamoto
Water Supply Management
Hiroshi Izumoto
GIS Application
Chander Parkash
E. E. Mapping
B. S. Jaglan,
Director (Revenue)
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-2
【3-1】Review existing DJB’s management policy/vision and business plan
JET discussed with DJB staffs including executives in DJB to find out direction of DJB for future
development. As a result, there seems to be no management policy, vision and business plan other than
“equitable water distribution, financial sustainability and accountability” that is shown in the website
of DJB. There is no defined standard for rehabilitation e.g. when or what condition.
Status of the facilities are not grasped and evaluated so that even if prioritization of rehabilitation of
the facilities or implementation of rehabilitation is carried out, its effectiveness is hard to evaluate. As
for the rehabilitation plan and construction of new plant, DJB usually carries out activities based on
Master plan and Feasibility study which is prepared by international cooperation.
Therefore, JET tried to identify issues after review and evaluation of the current situations on the
following aspects:
(1) WTP
(2) NRW reduction
(3) Water meter reading, collection of water charge and RMS
(4) Facility rehabilitation plan
(1) WTP
WTPs of Sonia Vihar, Nangloi and Dwarka were constructed after year 2000 and were constructed
based on Design, Build and Operate (DBO) contract. The contractor of construction is continuously
engaged in O&M.
WTPs of Chandrawal, Wazirabad, Hyderpur, Bhagirathi, Bawana and Okhla were constructed before
year 2000. These WTPs are operated by DJB directly. According to the rehabilitation plan of MP,
Bhagirathi WTP was rehabilitated with BOT contract, and O&M is carried out by the same contractor.
WTPs of Chandrawal and Wazirabad are respectively financed by JICA and ADB, and their
rehabilitations will be implemented by BOT.
1) Existing Condition of WTP operated by BOT
a) O&M is properly carried out by outsourced company. Those commissioning conditions are
arranged clearly. The supervising organization for facility management and analysis of water
quality are also prepared.
b) The O&M supporting system is introduced for staff to effectively implement O&M activities
such as daily working and periodic maintenance, management of maintenance schedule and
recording of equipment status. This system has also bridged the technical gap among the
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-3
staffs and enabled every staff to perform similar operation and maintenance activities.
Furthermore, it facilitates easy sharing of the information.
2) Existing Condition of WTP operated by DJB
a) Many facilities are operated manually like a start/stop switched by ON/OFF.
b) Operational staff is allocated to each facility exclusively for simple operation and no operation
manuals are required.
c) No drawing of facility layout etc.
d) No equipment lists.
e) No records and database on the status of maintenance and not good condition of the facilities.
f) Operation method is very ineffective to operate WTP appropriately. Each facility in WTP is
operated at the fixed time, regardless of change of condition.
3) Review and Evaluation of WTP operated by DJB
The following are required:
a) Unified standards for rehabilitation of facilities and equipment.
b) Design drawings. This may be one of the major issues related to not carrying out efficient
operation, maintenance and effective rehabilitation also.
c) List of asset, list of equipment, list of record of inspection and repair
Investigation at Sonia Vihar WTPInvestigation for database creation in Chandrawal
WTP phase II on 24th January 2014
Investigation for database creation in ChandrawalWTP phase I on 28 January 2014
Investigation at Chandrawal Ion 28 January 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-4
(2) NRW Reduction
1) Existing Condition
a) The total number of staff in LDI unit is 33 persons (1-EE, 4-AEs, 2-JEs and 26-fitter). LDI staff
identifies specifically leakage points based on the report of the zonal offices. However, they do
not repair leakages. Planned leakage detection and preventive measures are not carried out.
b) Zonal offices that are responsible overall distribution in their zones, repair leakages based on
the report of the customers. Planned leakage detection and preventive measures are not carried
out.
c) LDI has various kinds of leak detection equipment such as acoustic rod, correlation-type leak
detector and so on. However, it could not be confirmed on how DJB utilizes the equipment.
LDI unit confirms leakage only visually.
d) LDI staff cannot access GIS maps in the Mapping Cell. So, leakage detection is conducted
together with zonal engineer.
2) Review and Evaluation
The following are required:
a) Implementation of planned leakage detection activity
b) Establishment of organization of emergency repair work
c) Effective utilization of leakage equipment
d) Acquiring knowledge of leakage equipment
e) Preparation of DMA for implementing effective planned leakage detection activity
f) Investigation of reasons for leakage including a leakage history and a repair history
g) Implementation of planned leakage detection work based on the GIS maps
(3) Water Meter Reading, Collection of Water Charge and RMS
1) Outline
Approximately 600 staff members are working at about 20 zonal offices for water meter reading,
issuing of water charge bill and distributing the bill and so on. DJB has about 1,730,000 water
users. Only approximately 900,000 to 1,000,000 households are metered and pay water charge
based on water meter reading. The frequency of water meter reading is once every 3 months.
2) Process of water charge collection
a) Zonal staff reads water meter and records on MRD (Meter reading diary)
b) All data of water meter reading is sent to Head office in DJB
c) These data are input to RMS system by outsourced company
d) Water charge bills are issued by head office staff
e) Zonal office staff distributes water charge bills
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-5
3) Payment of the water charge bill
The credit card, debit card and online payment systems are available for the payment of water
charge bill. In the existing conditions, majority of users are making payment in cash. There are
various places where users can pay water charge bill, for example, CSC (Common Service Center),
Kiosk, designated banks and counter of DJB and so on. Of the total customers, about 25% pay at
CSC, about 20% pay at Kiosk, about 5% make payment in bank and about 50% go to the DJB
counter for making payment. There are about 90 DJB counters in total, of these about 60 counters
are operated directly and others are operated by outsourcing.
4) RMS
RMS is installed and connected to all the zonal offices. Individual KNO is allocated to a customer.
A customer can access to RMS using KNO at WEB-based environment.
5) Water meter reading
a) The water meter reading staff members seem to be facing big trouble with meter inspection.
The book of water user registration exists, and water meter reading is carried out. However,
staff members always have to compare the book with user’s water meters, which take a lot of
time.
b) The installation place of water meter differs depending on the house, and it is very difficult to
find the location of water meter. Also, it is very inconvenient for other meter-readers to be
shifted to a new area to understand the locations in such a condition.
c) Handy terminal system is very useful and efficient to record and issue water charge bill. But as
for the efficiency, it is not easy to find the installation place of the water meter. As a result,
even after using handy terminal system it will take a lot of time to carry out the reading of
water meter.
6) Review and Evaluation
The following are required:
a) Improvement of water meter management / standardization of location of water meter
b) Preparation of GIS map showing locations of water meter
c) Standardization of water meter calibration
d) Preparation of database of the book of water users’ registration
e) Efficient water meter reading
f) Unification of water meters number and KNO
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-6
Observation of water meter reading at site
(4) Rehabilitation Plan of Facility
1) Existing Condition
Many facilities like water treatment plants, transmission and distribution pipes, pumping stations,
are very old. Therefore, rehabilitation of such facilities is required. At present, major rehabilitation
program is carried out using foreign funds like Japanese ODA loan and ADB loan.
2) Review and Evaluation
DJB needs to prepare standards of inspection and rehabilitation of the facilities based on periodical
inspection of the facilities. Then, DJB can prolong the lives of the facilities and spend funds to
rehabilitate or renew the facilities adequately. Asset management will be an effective tool to conduct
the above and DJB needs to prepare and implement rehabilitation according to the asset
management.
【3-2】Clarify the issue to be tackled to achieve the above-mentioned policy /vision and
plan
(1) Issues and problems
Seven issues and problems of DJB were identified and classified.
1) Aging facility
a) Quantity of treated water decreases because of the capacity of WTP is getting worse by aging.
b) By the drop of the facility’s functioning, the water quality standard is difficult to maintain.
c) Stable water supply is difficult because of frequent breakdowns and outages of facility.
d) By the drop of the treatment efficiency, energy consumption increases unnecessarily.
e) Operation and maintenance cost increases.
f) There are frequent leakages in aging pipes.
g) Water supply pressure decreases due to the deterioration of pipe internal condition.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-7
h) Accurate water meter reading is difficult because old water meters are used.
2) Intermittent water supply
a) Consumers cannot get enough water when it is necessary.
b) There are lots of complaints from water consumers.
c) Unnecessary equipment such as booster pumps or roof tanks are necessary for getting water
and the burden on residents is very high.
d) It is difficult for poor people to get water service because they cannot prepare and purchase a
booster pump and a roof tank which is necessary for intermittent water supply.
e) Because of insufficient water supply water, users have no motivation to pay water tariff.
f) Water quality problems occur due to sewage inflow as a result of negative pressure in water
pipe.
g) It is difficult to detect water leakage point because water is not available all the time.
h) It becomes a trouble for the firefighting because water is not available all the time.
3) Unsatisfactory level of water quality
a) There are lots of complaints from water consumers.
b) Water consumers have no incentive to pay water charges because they are not satisfied with
the quality of water.
c) Water consumption does not increase because the water quality is not satisfactory for
consumers.
d) Increasing the annual revenue is difficult to anticipate.
4) Staff allocation
a) Surplus staff allocation at each WTP and BPS
-Personnel expense is very high.
-Personnel management is difficult.
b) DJB’s peculiar method of facility management
-Workers are usually located in specific facilities and perform the same task in their lives.
-Technical transfer is limited only to specific fields.
-Cooperation between other fields is less, as a result it is difficult to carry out effective
operation as a whole facility.
-It is difficult to make backups among WTPs because there are no sharing of information.
5) Deficient water leakage prevention
a) Emergency repair work is very difficult.
b) Planned leakage investigation is very difficult.
c) Technical knowledge about leakage detection and prevention are not transferred.
d) DJB staffs cannot use leakage detection equipment effectively.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-8
e) Water supply service worsens as a result of ignoring water leakage (water outage, water
pressure drop).
f) It is difficult to reduce NRW, bringing in worse management.
6) Inefficient water meter readings and water tariff collection
a) Due to no unifying location of water meter, it takes a lot of time to find water meters and
conduct water meter reading.
b) Because of small number of water meters, appropriate water charge collection is difficult.
c) There are many facilities which contribute to NRW such as public stand pipe and hand pump.
d) A large number of staff is necessary for inspecting water meter reading so that personnel
expenses are very high.
e) It is difficult to utilize RMS effectively (Number of RMS computer, Rule, System).
f) Due to inaccurate water meter reading, target of NRW ratio cannot be decided.
7) Defectiveness of As-Built drawings
a) There are no database of existing equipment and facility’s information. Information belongs
only to the veteran personnel.
b) It is difficult to grasp correct information about the location of laying pipe, the depth and the
pipe materials.
c) It is difficult to specify location of leakage so that emergency repair work cannot be carried
out.
d) Effective DMA setting for water leakage management is difficult.
e) Planned water leakage detection is difficult.
f) Location and operation of valve at the time of distribution route change is not understood.
g) The probability of accident occurrence is high when the construction starts because there is a
lack of information on correct location of electricity, gas and communication cables.
h) Connection between new pipe and existing pipe, and setting of necessary diameter is difficult.
i) Drafting of renewal plan and execution of asset management systematically are difficult.
j) It is difficult for inexperienced staff to understand the facilities.
One of the reasons for these problems might be the lack of staff capability and no appropriate
organizational structure in DJB. Other reason is that there are no visible management plans
(business plan and financial plan). Waterworks Bureau of Tokyo Metropolitan Government always
make three years management plan (business and financial plan) for three years.
In order to solve these problems, utilization of GIS and RMS and preparation of Asset Management
Guideline are necessary.Table 4-1 shows a more effective method to prepare an asset management
plan.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-9
Table 4-1 Method of Preparing for Asset Management Guideline Effectively
Method
1.A
gin
gfacility
2In
termitten
tw
atersu
pp
ly
3U
nsatisfacto
rylev
elo
fw
aterq
uality
4S
taffallo
cation
5D
eficient
water
leakag
ep
reven
tion
6In
efficient
water
meter
reading
san
dw
atertariff
collectio
n
7D
efectiven
esso
fA
s-Bu
iltd
rawin
gs
1) Implementation of plannedrenovation and prepare a draftrenewal plan (GIS/RMS)
2) Preparation of manuals forfacility, operation and maintenanceand business management
3) Capacity development foroperation and maintenance staff
4) Preparation of waterworksfacility database (GIS/RMS)
5) Implementation of 24×7continuous water supply
6) Strengthening of organization ofwater leakage prevention andImprovement of NRW
7) Establishment of organizationand rule for accurate water meterreading
8) Utilization of GIS for designing,operation and maintenance,planning and upgrading of service
(2) Preparation for Formulating Asset Management Guideline
During second half of 1st Year, the database of facility and daily maintenance sheet of facility were
prepared as a 1st step of preparation of the asset management guideline. However, required information
for the asset management except revenue expenditure and revenue, were very difficult to obtain or do
not exist at all.
1) Proposal of Preparing the database of facility
Many facilities that DJB manages have passed more than 50 years after their commissions.
Therefore, aging facilities are the main causes of the concerns, thus upgrading of the facility is
becoming necessary. However, there are few data of facilities, list of equipment and drawings with
adequate accuracy.
Though simple and handwritten drawing exists as for the pipe information there is not much
database and DJB’s veteran staffs only have data in their memory. Under this situation, there are lots
of problems in carrying out daily maintenance, emergency repair work and making a renewal plan
and so on.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-10
So, in order to proceed for efficient and effective water supply management, a facility database
would be very useful. This database would be utilized for proper O&M. JET prepared the sample of
the database for O&M of WTP. In order to utilize the prepared sample and to practice efficient
O&M, JET performed daily check (making of an inspection sheet, inspection record) of the
facilities of WTP with the technical staff of WTP of DJB.
2) Proposal of compositions of waterworks facility database
The facility database is composed of three parts: “Outline of facilities”, “Design drawing of
facilities” and “Flow chart of facilities”.
a) Outline of Facility
An outline of facility describes the key specification of all facilities and equipment such as
capacity, performance and year of installation. This information will be a base for repairing work
and making a renewal plan.
b) Design drawing of facilities
A floor plan of facilities and equipment drawings should be collected for operation and
maintenance.
c) Flow chart of facilities (WTP, UGR, BPS)
In order to understand water flow, water treatment process, and chemical injection point and
distribution route smoothly and effectively, a flow chart of water treatment facility including
water treatment plant and underground reservoir and booster pumping station will be useful.
3) Proposal of operation of facility database
This database would prove to be useful among operation and maintenance staff in DJB. It is better
to update data at DJB intranet. If it is difficult to use intranet, a booklet and PDF file can be
prepared and distributed to all branch offices.
4) Proposal of practice of daily inspection of water treatment plant
In order to prevent the troubles and accidents of mechanical and electrical equipment, it is important
to find early signs of abnormality through the daily and periodic inspection and take
countermeasures before reaching fatal accident. Because of this, sound, vibration, temperature and
current value of the equipment under operating condition is observed at daily inspection to grasp the
normal state of equipment. Based on the daily inspection, it is possible to recognize and judge the
sign of abnormality. And also, it is necessary to perform an inspection based on an inspection
standard covering inspection items and contents, inspection period and recording methods.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-11
a) Purpose of preparing daily maintenance sheet
- To establish daily maintenance as routine
- To accumulate records and utilize them for repair and replacement works effectively
- To grasp normal situation and find abnormal condition of each equipment quickly
b) Daily maintenance route
- Follow the process of water treatment from receiving well to transmission pump house
totally
- Carry out daily maintenance once a day
c) Maintenance sheet
- Grasp the condition of each facility by a maintenance sheet
- Record the condition of tanks (water level, oil film, suspended solid, etc.)
- Record the condition of equipment (appearance, damage, abnormal noise, nasty smell)
- Record the numerical value of thermometer, pressure gauge and flow meter etc.
- Save the sheet and share the result of daily inspection among the maintenance staff
5) Activities in This Project
JET prepared the daily check route and inspection items of Chandrawal WTP and also made the
reporting system to their boss as OJT of "daily inspection in water facilities". The engineer of
Chandrawal WTP presented this activity in the 4 th seminar held in March 2015.
Confirmation of maintenance routes for WTP Daily Joint inspection of Chandrawal WTP
【3-3】Review GIS development and RMS in DJB
(1) Confirmation and review on development situation of GIS
1) System configuration
a) DJB uses ArcGIS Ver.10.0. DJB does not have the application which is customized for
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-12
waterworks.
b) DJB has one ArcGIS server and 10 desktop computers with GIS. Those are placed in Mapping
Cell of DJB headquarters, and only Mapping Cell staff members can use the system.
2) Review and Evaluation
a) GIS is installed in only Mapping Cell. So other departments cannot use the system. In order to
widen the use of GIS, GIS should be installed in all departments of DJB.
b) ”ArcGIS” is used without customization so that operation is difficult without the help by GIS
professional staff. Easy-to-use GIS is necessary.
3) Activities in the Project
a) JET proposed the system where GIS data can be shared among all the zonal offices by
introduction of Web-GIS, and also proposed the introduction of Mobile-GIS where GIS can
be used not only at zonal office but at construction and a maintenance management site.
b) JET proposed to set up the facilities’ symbol of intelligible GIS visually in order to be
understood a facility arrangement easily.
(2) Varieties of GIS data
1) Present condition
DJB has two kinds of GIS data as described below.
a) Data established under NIC (National Informatics Center) project
Data built in the spatial information development project conducted by the central government
of India.
b) Data prepared by DSSDI (Delhi State Spatial Data Infrastructure)
Data built in the spatial information development project carried out by Delhi government.
The data covers all underground utilities, roads, buildings and houses. DJB has a copy of the
existing DSSDI database in the Mapping Cell. Development of GIS will be carried out based
on DSSDI.
2) Review and Evaluation
It is necessary to adopt a uniform spatial data source to avoid any confusion. Therefore,
conversion from NIC to DSSDI is necessary at the early stage.
3) Activities in This Project
In the case of conversion to DSSDI, JET proposed that corresponding data should be converted to
GIS simultaneously after confirming the existing data and implementation of test pit investigation
for unknown data.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-13
(3) Information management using the non-GIS
1) Present condition
a) Design drawings and as-built drawings prepared by contractors are archived as CAD data. The
CAD data exists only in case of large-scale construction.
b) DJB has “WaterGEMS” as hydraulic analysis system provided under JICA MP. However, DJB
has not updated Water GEMS’s data.
c) Other related information is archived in paper form. (Drawings, Leakage reports, etc.)
2) Review and Evaluation
a) In order to utilize huge information efficiently, changing the database storage media from
paper to digital form such as GIS is important.
b) It is desirable to carry out the simulation of the flow in pipe network analysis for the design of
a pipeline and O&M. After data creation is completed, introduction of the system of pipe
network analysis is desired.
3) Activities in the Project
a) Notes to be attentioned when converting data into GIS from CAD data are included in the
development scenario.
b) About the detailed information of the facilities where illustration is difficult in GIS (as built
drawing, facility database, flow diagram of WTP/UGR, etc.), JET proposed introduction of an
electronic file by introducing a GIS filing system.
c) About O&M information, including water leakage, a complaint, etc., JET proposed their
locations are plotted on GIS which can be understood visually.
d) As for the usage of future advanced GIS, JET proposed introduction of a pipe network analysis
system and development of an analysis model
(4) Actual situation of GIS utilization
1) Present condition
GIS is only used for confirmation of the location where pipeline construction is done before actual
work.
2) Review and Evaluation
a) It is necessary to expand the range of GIS utilization in order to improve the efficiency of the
waterworks operation.
b) GIS should be installed in all departments of DJB.
3) Activities in This Project
JET proposed that expansion of GIS including prevention work for leakage using the GIS
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-14
information, efficiency and improvement for measures of poor water supply, grasp of NRW for
each DMA using facilities/customer data, improvement of workability/accuracy for meter
inspection and utilization to asset management, and so on.
(5) Present situation of GIS data updating
1) Present condition
Updating of data is implemented in DSSDI.
a) Workflow of updating
Step1: Drawings covering the planned construction site are printed from GIS by Mapping Cell.
DJB passes the drawings to the contractors.
Step2: After the laying work of the pipeline, the contractor puts information and route of the
new pipeline on the drawings. After that, the contractor submits the drawings to DJB.
Step3: EE checks and approves the drawings submitted by the contractors.
Step4: Mapping Cell inputs the approved information into GIS
b) Personnel for updating work
Six DJB staffs, no sub-contracting of the work is done.
c) Frequency of data update
Mapping cell carries out updating work every day. In case of pipeline construction costing more
than 1 crore (ten million) Rupee, acceptance inspection of construction contracts is completed
only after the input to the GIS.
A pipeline design/as-built drawing of CAD data contractor prepared is stored. (However, it
seems that CAD data exists only in large-scale construction.)
WaterGEMS was introduced as a pipe network analysis system at the time of MP (in 2011).
However, data has not been updated yet.
Variety of information has been managed only with a paper drawing (various drawings,
leakage information, etc.).
2) Review and Evaluation
Data updating should be carried out immediately. In addition, it is necessary to make change or
improve present workflow to efficient one.
3) Activities in the Project
a) JET proposed an approach that each section (civil, O&M, customer) should update
information as timely as possible, using Web-GIS and Mobile-GIS.
b) JET proposed on how to connect site information with GIS information using Mobile-GIS at
daily meter reading.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-15
c) About underground pipe, JET proposed on how to accumulate and store information on
facilities property and aging information gained by test pit investigations in GIS
(6) Layer configuration progress
1) Present condition
a) DSSDI has layers for water source, treatment plant, pump, pipelines, valve, etc., covering
most of water supply facilities.
b) However, there are no layers for water hydrant and house connection such as water meter and
service pipe.
c) Layers for the maintenance management such as leakage record and pipe repair record are not
prepared.
Table 4-2 Comparison of DSSDI and NIC Data related to the Layer Configuration and Input Status
2) Review and Evaluation
a) It is necessary to prepare all layers covering all water facilities.(e.g. fire hydrant, water meter)
b) It is also necessary to prepare layers for maintenance management to improve the efficiency of
O&M. (e.g. leakage point, repair point, construction site, water meter)
c) Transfer of data on valves from NIC to DSSDI is slow and needs to be accelerated.
3) Activities in This Project
a) JET proposed the layer composition which covered facilities and O&M information, and their
attribute lists.
b) JET proposed to set up the facilities’ symbols on GIS in order for an easy - understanding.
(7) Attribute items and progress of attribute data input (DSSDI)
1) Present condition
Many attribute items have been prepared. However, more detailed attribute information is needed
for effective utilization.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-16
Table 4-3 Status of Attribute Data by Layer
2) Review and Evaluation
a) Information on size and material of pipes accounting for majority of the facilities are all input
to DSSDI. However, essential information on pipe age is missing and needs to be collected for
implementation of asset management.
b) Information on basic attribute of volume of wells and reservoirs are lacking. Similarly,
information on discharge volume and head of pumps is lacking and needs to be collected.
They are the basic information for O&M.
c) Status of openings and closing of valves is lacking. This is important when DMA is created.
d) Collection of important information is difficult because of few data in the past; however, study
on the methodology to obtain this information is required.
3) Activities in This Project
a) JET explained that filling of attribute data is important and linked with expandable use of GIS
directly through GIS and RMS application scenario.
b) JET proposed composition and attributes of layers covering both facilities and O&M.
(8) Development status of customer information
1) Present condition
a) DSSDI has a layer for household information (Approximately 6 million records have been
input).
b) DJB is trying to match the household information in DSSDI with the customer information in
RMS by using address data. About 60% of data was matched.
c) All customers of DJB have “KNO” as customer ID in RMS.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-17
Figure 4-1 Household Information and Customer Information
Table 4-4 Number of Household Records in DSSDI
Zone Number of records
Central 205,315
East 661,120
New Delhi 29,468
North 369,988
North East 660,397
North West 1,352,164
South 951,276
South West 730,802
West 996,741
Total 5,957,271
2) Review and Evaluation
a) Effective reduction of NRW requires information on household and bulled amount is displayed
on the maps. So, it is necessary to complete matching work of the household information in
DSSDI and the customer information in RMS.
b) It is better to input information on installation points of water meter with KNO instead of
household information in GIS. It also helps to increase the efficiency of meter reading work.
(9) Review of RMS
1) Confirmation and review of development situation of RMS
a) RMS has been established by DJB.
b) All 22 zonal offices can access RMS (30 terminals for DJB and 3 terminals for PPP project
site)
c) All customers are identified with identification number called KNO and customers can access
RMS using KNO via internet.
d) RMS consists of 4 contents shown in Table 4-5
KNO Name Address ・・・
5623341500 ○○ ○○ ・・・
5623373956 △△ aa ・・・
5623406412 ○○ ○○ ・・・
5623438868 △△ bb ・・・
5623471324 ○○ ○○ ・・・
5623503780 △△ △△ ・・・
5623536236 ○○ cc ・・・
5623568692 △△ △△ ・・・
5623601148 ○○ ○○ ・・・
5623633604 △△ △△ ・・・
・・・ ・・・ ・・・ ・・・
RMS information
Household information(Address data)
GIS(DSSDI)
aa
bb
cc
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-18
Table 4-5 Contents of RMS
RMS Application Remarks
Consumer Portal Water users can utilize for confirmation of consumption of water and watercharge bill. And also application of house connection is possible. All waterusers who have KNOs can use this system.
BI Publish Enterprise Various reports are prepared in DJB.
CCB (Customer Care andBilling)
DJB maintains and manages customer information.
UCM (Universal ContentMeasuring)
The paper-based data such as the application records and other records in thepast are scanned and accumulated in the system. It is possible to provide thesedata to users when requested.
2) Review and Evaluation
a) RMS is convenient system for water users.
b) It is necessary to connect RMS with GIS by placing customer information including water
consumption of RMS on sites of GIS. This will help reduction of NRW.
c) JET proposed that updating work will be conducted in each section by introducing Web-GIS
and increasing the user of GIS to increase works efficiently.
d) Linking of GIS and RMS is indispensable to the NRW reduction which is one of the big
problems on DJB management. This was taken into consideration as important matter in the
development item of GIS/RMS scenario.
3) Activities in This Project
JET proposed for linking of every house meter data on GIS and customer data on RMS,
improvement in efficiency for tariff collection work after linking, and an approach of improvement
in efficiency and effective measures of leakage.
【3-4】Study Japanese experience and system of GIS and RMS
The history of development and uses of Japan's GIS were introduced. The contents are shown below.
The introduction was conducted in March 2014 in Delhi and again in November 2014 in the training
in Japan.
(1) Overview of GIS application in Japan
- Field of applications
- History of introduction
- Update of GIS data
(2) Introduction of GIS utilization (including training by actual GIS operation)
- Data structure of GIS
- Function of minimizing affected areas by planned water supply interruption
- Hydraulic analysis (design of the pipe)
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-19
- Management of leakage history data
(3) Pipelines evaluation system
- Functional evaluation of the pipes (level of aging, anti-seismic, hydrogeological and water
quality)
- Prioritization of pipe replacement
Throughout the training, DJB participants were able to understand about advanced GIS and its
application in water supply services in Japan and the gap of GIS between Japan and DJB. DJB also
realized that more GIS development was required in DJB as an effective tool of asset management of
DJB. Further DJB understood the followings:
1) Accuracy of the GIS developed under the Output 1; service pipes locations were not included but
that needed to be developed in the next stage.
2) The proposed step-wise development of GIS was feasible for DJB.
3) The works proposed under the activities 3-5 and 3-6 were demarcated to each part: either
Japanese ODA loan project component 5 or DJB itself.
【3-5】Draft GIS and RMS application scenario in DJB for year 2021
DJB is planning to carry out topographic survey and input to DSSDI about all WTPs, UGRs, BPSs
and Tube wells. CAD data from topographic survey include not only water supply facilities, but also
all other structures that are not directly related to facilities’ management. In order to create GIS data
that focuses on the management of facilities, JET proposed the policy of conversion to GIS drawing
from CAD as shown in Figure 4-2.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-20
(1) Specialize in water facilities
Delete trees, electric pole, lamp post etc.
Figure 4-2 Drawing Showing only Water Facilities
(2) Simplification and standardization
1) Draw canal and pipe as single line in order to understand water flow easily.
2) Draw only outline of facilities and buildings.
3) Delete canal and pipe that is not related to water purification and distribution.
4) Draw equipment that related to water purification and distribution as standardized symbol. (Ex;
canal, pipe, valve, flow meter, pump)
5) Input specification (Ex; Dimension, type, capacity etc.) of each facilities and equipment as
attribute data.
6) Detail information (Ex; Drawings, Facility database etc.) are stored in Filing system.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-21
Figure 4-3 Drawing of Simplification and Standardization
【3-6】Draft GIS and RMS development scenario in DJB for year 2021
Based on the outcome of the study mentioned in Activities 3-2 and 3-3, JET prepared scenario of
application and development of GIS and RMS.
After discussion on the draft scenario with DJB, JET made a presentation on GIS/RMS scenario in
December 2014 before 23 officials of DJB (Including Addl. CEO), JICA India, and Japanese ODA
loan consultant. Prepared GIS/RMS scenario included the following:
(1) GIS utilization in Japan
(2) Review of water works management of DJB
(3) Review on development situation of GIS in DJB
(4) GIS/RMS application scenario in DJB
1) Database or drawings of facility (facility/pipeline) by using GIS.
2) Design, operation and maintenance, planning and improvement of service by using GIS.
3) Asset management (facility renewal plan) by using GIS.
(5) GIS/RMS development scenario
Step1: Reconstruct the existing Database structure of GIS
- Add or change layer structure and attribute items.
Attribute data
Drawing
⑤
⑥
・・・ ・・・
Centrifugal pump
500
50
・・・
・・・
・・・
・・・
・・・
・・・
Type
Diameter (mm)
Head (m)
Discharge volume (m3/min)
Revolving number (min1)
Voltage (V)
Motor Output (kW)
Number of Pole
Control method
Filing system
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-22
- Determine easy-to-understand symbols for each layer.
Step2: Feed existing data to GIS
- Past survey data/ As-built drawings/ NIC data etc. into GIS filing system
Step3: Add new information to GIS and improve data accuracy
- Data obtained from topographic survey. customers’ information
Step4: Expand GIS user in DJB
- Development of Web-GIS and Mobile-GIS, Method of data updating
Step5: Advanced application of GIS system
- Hydraulic analysis/ Asset management
(6) Schedule of developing GIS/RMS
After the presentation and discussion, the contents of GIS/RMS development scenario were classified
into the following 3 types with the development schedules.
1) Contents that should be carried out in the DJB.
2) Contents that should be included in Japanese ODA loan project Component 5.
3) Contents that should be included in Japanese ODA loan project Components 2, 3 and 4.
“Report of GIS/RMS Application and Development Scenario in DJB for Year 2021” (refer to the 3 rd
progress report) was submitted in December 2014 to DJB.
Presentation on GIS/RMS utilization application anddevelopment scenario on 12 December 2014
Presentation on Asset management12 December 2014
Discussion on Presentations12 December 2014
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
4-23
【3-7】Draft the guideline as an action plan for realization of scenarios
Asset management guideline was formulated by the analysis and use of GIS/RMS data. Before
preparation of draft asset management guideline, the management policy and issues of DJB have been
reviewed through the activities 3-1 and 3-2. Afterwards, a presentation was made before DJB officials
about "The concept of Asset Management" in December 2014.
JET explained on the “Asset Management Guideline for DJB” (refer to the 4 th progress report) by the
data analysis and utilization of GIS/RMS to DJB in March, 2015, and DJB approved it.
Description of introduced Asset Management guideline
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
5-1
CHAPTER 5 ISSUE, INNOVATIVE APPROACH, AND PRECEPT OF
THE PROJECT IMPLEMENTATION
5.1 Suggestion on Joint Work between JET and DJB
(1) Issue
Initially, DJB did not fully recognize the difference between the consultant’s service in Japanese ODA
loan project and the role of JET. So, officials of DJB were not active and rather responsive to the
actions and proposals of JET.
(2) Innovative Approach
JET and DJB had discussions on how to improve on the Project when DJB officials participated in the
training held in Japan. As a result, DJB reaffirmed on the purposes of the Project, and confirmed that
in order to achieve the objectives of the Project, active participation of DJB staff members in the
Project was necessary.
Furthermore, development of ownership of the Project by DJB executives was encouraged so that the
Project effect would be achieved effectively. In order to encourage DJB executives to participate in the
Project and improve their awareness on subjects, exchange of information and views between DJB
executives and JET was actively taken. As a result, the followings were observed:
DJB held JCC meeting proactively.
The Project Manager and Deputy Project Manager of DJB participated in JCC meetings and
progress meetings on SCADA procurement that was previously carried out without them by only
officials of Pitampura branch office.
(3) Lessons Learned
Officials of DJB tend to concentrate in the assigned tasks because of divided roles in each section of
the large-scale organization of DJB. In addition, there are limited responsibilities in the lower level
officials and great power and authority responsibilities in the executives. So, participation of the
executives in the Project accelerates on various decisions in the Project.
5.2 Disclosure of Guideline and Manual
(1) Issue
Various guidelines and manuals were prepared in the Project and they were utilized by the concerned
engineers. However, they are not disclosed and widely circulated in DJB and therefore not utilized by
other engineers.
(2) Innovative Approach
All guidelines and manuals including those on SCADA system were stored in DJB library. These were
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
5-2
used as a reference material for internal training, and long-term training plan utilizing manuals and
guidelines will be formulated by DJB’s Training Cell.
(3) Lessons Learned
The effective sharing method of prepared materials should be confirmed beforehand and involved in
the related departments. In addition, as a strategy for wide sharing of the outcomes of the Project to the
organization, a mechanism for more reliable and sustainable implementation of the training plan
should be created through the following methods:
・ storing the manuals and guidelines prepared in the Project to a library
・ incorporating a training plan formulated in the Project in existing training systems,
5.3 Work Schedule Management
(1) Issue
SCADA system was planned and constructed in Pitampura pilot project site under Output 2. The
responsibilities of the stakeholders were as follows:
No. Stakeholder Contents
1 DJB ・ Application for road cutting permission,・ Design, tendering, contract and construction supervision of chambers,・ Connection of electric power with payment of monthly electricity
charge・ Connection of communication with payment of monthly charge・ Construction of water-proof measures (part)
2 DJB’s contractor (Koli) ・ Construction of chamber
3 JICA ・ Tendering and contract of SCADA procurement
4 JICA’s contractor (RDS) ・ Supply and installation of equipment of SCADA system
5 JET ・ Preparation of tender document, evaluation of bid prices, supervisionof procurement and installation of SCADA system
・ Construction of model chamber・ Construction of water-proof measures (part)・ Technical transfer of SCADA operation
The devises such as control valves with actuators, flow meters and pressure gauges in the chambers
cannot be installed independently but need to be installed along with the construction of chamber
construction such as the basement of chamber is constructed first, then devices installed and so on.
Five stakeholders were involved in this work due to which coordination in execution of work and
revision of contract was complicated and difficult.
(2) Innovative Approach
Twenty five (25) progress meetings on SCADA procurement were held to coordinate the time
schedule of each work. Fourteen (14) meetings were held from July 2014 to July 2015 when most of
the equipment was installed. Afterwards, 4 meetings were held during work suspension period. Then,
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
5-3
7 meetings were held from June 2017 when the work re-started to November 2017.
(3) Lessons Learned
SCADA system consisting of various equipment and devises, chambers and connection of power and
telecommunication should not be constructed separately by multiple contractors but by a single
contractor. A single contractor with sole responsibility could prepare work schedule and implement it
smoothly.
If this kind of work separation is required, a project management engineer should be assigned for the
coordination. In addition, in the countries where construction culture is different from Japan, he or she
should be assigned continuously but not as spot for smooth management of construction schedule.
Time frame should also be planned as flexible in the Project preparation.
5.4 Construction of Chamber
(1) Issue
JET included 2 experts of DMA and SCADA works and they planned the pilot project such as creation
of DMAs and conceptual design of SCADA including local equipment such as valves and software in
the output 2. Based on the plan, DJB concluded the contract of chambers construction while JICA
concluded the contract of SCADA system as shown in Table in 5.4.
JET assisted JICA in TOR preparation, evaluation of the bidders’ cost estimation and coordinated work
schedule. JET and DJB decided jointly locations and sizes of chambers.
However, water ingress was observed in some of the chambers constructed by DJB that could lead to
electricity leakage with possible accident. In response, JET assigned civil engineer expert to prevent
water ingress by the measure of water-proofing of chambers.
(2) Innovative Approach
JET carried out water-proofing works on the top slabs of the constructed chambers while DJB did on
the side walls and basement of the constructed chambers. JET worked together with DJB to transfer
the methods of water proofing works, and these know-hows (preparation of standard specifications,
construction sequence, supervision, etc.) were also disclosed as recommendations in the seminar.
(3) Lessons Learned
JET did not assume that DJB would construct brick-made chambers that would be susceptible to water
ingress. Hence, JET should have assigned civil engineer expert at the early stage of the Project,
communicated closely with DJB, and checked the specifications of chambers that DJB designed.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
5-4
Furthermore, when constructing a structure such as chamber or procuring valves and flow meters at
the C/P’s cost specifications of such structure or equipment should be confirmed and agreed with C/P
at the detailed planning stage.
5.5 Hydraulic Isolation of DMA
(1) Issue
Hearings with the concerned engineers and trial diggings were conducted to create hydraulically
isolated DMAs at the beginning of the Project. After the creation of DMAs, a zero pressure test was
carried out to make a final confirmation of the hydraulic isolation of the 3 DMAs. Zero pressure
means that the water pressure in the DMA becomes zero when the inflow valve to the DMA is closed.
This test took place from December 2017 when the SCADA system started its operation to January
2018. As a result, it was found that although DMA1 was isolated, DMAs 2 and 3 were not isolated in
two places.
(2) Innovative Approach
At the beginning of the Project, it was expected that there were unknown pipes besides the existing
pipes in drawing and it was difficult to secure the independence of DMA. For this reason, the area
where the network was simple was selected as the pilot area.
In addition, JET reviewed pipe drawings in Mapping Cell, interviewed the civil engineers who were
familiar with the pipe network in this area, further conducted the trial diggings, and set up DMA.
(3) Lessons Learned
Nevertheless, securing DMA isolation was difficult. Construction of DMA was based on the procedure
of 1) construction of DMA, 2) implementation of zero pressure tests, 3) detection of non-isolation of
DMA, 4) identification of cause of non-isolation, 5) devising countermeasures, and 6) ensuring
isolation of DMA. In the Project, JET carried out the work until stage 3) and part of 4) with DJB's civil
engineers, but couldn’t finish due to time constraints.
If the pressure test were conducted in October 2017 when all equipment was installed and could be
operated by manual at sites earlier than December 2017, isolation or non-isolation status could have
been identified. Therefore, work schedule like zero pressure tests, which can delay the succeeding
activities, should be as flexible as possible.
5.6 Calculation of NRW Ratio
(1) Issue
NRW can be calculated from 1) the amount of water flowing into the DMA and 2) the billed water
volume to all customers in the DMA. The former can be easily obtained from the SCADA system.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
5-5
Billed water volume exists in RMS, but it is not organized by DMA unit. Therefore, based on the
customer number (KNO), the billed water volume in the DMA had to be counted for each DMA from
the RMS data corresponding to KNO.
(2) Innovative Approach
RMS data was received in December 2017. In order to compile more than 3,000 KNOs in 3 DMAs,
JET and DJB tried to improve the efficiency of work such as picking up KNOs that match with the
address in DMA using excel, but that still took time. For this reason, in February 2018, JET discussed
with Addl CEO, Director (Revenue), etc. who has jurisdiction over RMS and suggested that KNO data
be given a DMA number so that data extraction (billed water volume) for each DMA can be made in
future. As a result of the discussions, DJB committed to implement this after April 2018 when RMS
contractors change. Furthermore, in course of the discussion, it was also found that DMACell exists
and calculates NRW for 33 DMAs already set by DJB. DMA Cell agreed to also calculate the NRW of
the 3 DMAs of the pilot project.
(3) Lessons Learned
If JET had discussed the calculation method etc. in December 2017 when received RMS data, JET
would have been able to work with DMA Cell earlier. JET needs to promptly obtain relevant
organization reform information from C/P, and it is necessary to hold timely discussion with the C/P
that is quickly reorganized.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
6-1
CHAPTER 6 ACHIEVEMENT OF PROJECT PURPOSE
Six (6) measures are suggested at the joint terminal evaluation in January 2018, to be taken by the end
of the Project.
Table 6-1 Suggested Items at the Joint Terminal Evaluation and Achievement
No. Suggested Item Achievement Reference
1 Annual Maintenance of SCADA Not yet achieved.
2 Trial for the equitable water distribution Achieved. Output 2
3 Monitoring of the NRW ratio Achieved Output 2
4 Involvement of the Training Cell Achieved Output 2
5 Dissemination seminar Achieved
6 Acceleration of DPRs Finalization Not yet achieved.
6.1 Annual Maintenance Contract of SCADA
(1) Suggestion
DJB needs to accelerate the procedure to conclude the annual maintenance contract (AMC) by
February 2018 so as to operate and maintain SCADA system after the completion of the Project.
(2) Achievement
1) Background
DJB executives understood the importance of O&M of SCADA system and were preparing an AMC
of the SCADA system.
2) AMC of Soft Component
Contract of daily O&M of SCADA server with the supplier was being processed in DJB as of 7
March 2018. This is based on a single nominated contract because the supplied software is
customized to the pilot project and only the supplier has its operational know-how including
software.
3) AMC of Hard Component
DJB considered hard components to be covered by AMC from the beginning; however, it was
changed to 3 separate contracts.
a) Hard component 1 (devices and equipment) related to SCADA system like PLC
Devices and equipment have short life spans and are naturally vulnerable to damage. So, DJB
will procure 1 set of devices and equipment as spare parts and use instantly when damage occurs.
DJB was obtaining cost estimate for its budget preparation followed by tendering.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
6-2
b) Hard component 2
Such appurtenances as flow meters and pressure gauges have long life spans and will be less
vulnerable to damage. These appurtenances are commonly used in DJB, different from hard
component 1 that is rarely used in DJB. When such appurtenances are damaged, DJB will ask the
currently contracted suppliers as a variation order. This type of contract is similar to leakage
repair.
c) Hard Component 3
Such appurtenances as valves and actuators have also long lives and will be less vulnerable to
damage. These appurtenances are commonly used in DJB, different from hard component 1.
When such appurtenances are damaged, DJB will repair them through normal tendering process
that will take about 1 month.
4) Prospect of Contract
AMC of soft component will be concluded once the Member (Finance) of DJB approves it
internally. Contract of hard components will be taken whenever damages take place. This contract
will be handled at CE’s level that assured to take necessary actions and has sufficient budget. Even
if this procedure is not taken, DJB has adequate know-hows and can repair them by itself.
6.2 Trial for Equitable Water Distribution
(1) Suggestion
In order to demonstrate the way of enhancing equitable distribution of water through SCADA system,
it is required for the Project to set the target (Y) of “indicator b” of the Project Purpose and control
water flow to minimize the gap in water pressure and volume between the highest DMA and lowest
DMA even in a short interval by February 2018.
(2) Achievement
Trial for equitable water distribution was conducted in January and February 2018. As a result, gaps in
water pressure and volume between the highest and the lowest DMAs were narrowed down according
to the set target (Y) (refer to Chapter 3).
6.3 Monitoring of NRW Ratio
(1) Suggestion
It is required for the Project to have the stakeholder meeting to make clear demarcation of
responsibilities for NRW ratio calculation and obtain NRW ratio for DMA 1 by February 2018.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
6-3
(2) Achievement
DJB engineers and JET calculated a NRW ratio for DMA 1 as 60%. The result was reported through
CE (West) to Addl CEO on February 2018 (refer to Chapter 3).
6.4 Involvement of Training Cell
(1) Suggestion
In order to utilize the SCADA system located in Pitampura as the training facility effectively, it is
recommended to integrate the SCADA training into the DJB’s annual training program organized by
the Training Cell. In this way, the training can be conducted on a regular basis after the completion of
the Project. The Project should develop a draft long term training plan on SCADA and finalize the
plan with the Training Cell by February 2018
(2) Achievement
The Training Cell of DJB finalized a long-term training plan assisted by CE (West). Based on this, the
Training Cell announced in February 2018 to hold a seminar
6.5 Dissemination Seminar
(1) Suggestion
In order to widely share the benefits and good practices of the Project within DJB, it is recommended
to organize a seminar to disseminate the results of the Project before the completion of the Project.
(2) Achievement
DJB engineers (Civil and E&M) presented the results of trial of equitable distribution and NRW
calculation in a seminar held on 27 February 2018 with about 150 participants.
6.6 Acceleration of DPRs Finalization
(1) Suggestion
Though the DPRs for components 2, 3, 4 and 5 of the Japanese ODA loan project have been drafted
more than a year ago based on the inputs from the Project, they have not been finalized by DJB and
not submitted to the Approval Committee. This is holding back the Project Purpose from its full
achievement as well as the smooth implementation of Japanese ODA loan project. Therefore, it is
strongly recommended that the process be accelerated by DJB to finalize them by the end of the
Project.
(2) Achievement
DJB instructed the Japanese ODA loan consultants in February 2018 to revise DI pipe material class
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
6-4
that was a part of the latest draft DPRs of 3 components, submitted in January 2018. The consultants
were revising it and would submit it in March 2018. When this is approved by DJB, approval
committee including the Ministry of Urban Development will approve DPR.
However, since the first draft DPR was submitted more than a year ago, DPRs were revised many
times at the instruction of DJB mainly on pipe material and class. Therefore, it is difficult to estimate
when the DPRs will be approved.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
7-1
CHAPTER 7 SUGGESTION TO ACHIEVE OVERALL GOAL
Overall goal of the Project is: “To achieve the equitable and continuous water distribution in the
National Capital Territory of Delhi, by improving the water supply network including service network
to customers, thereby contributing in upgrading citizen’s living standard”. This overall goal is the
same as the goal of the Japanese ODA loan project, which is set to be achieved in 2023, two years
after the completion of the Japanese ODA loan project.
The agreement of the Japanese ODA loan project was concluded on 29 October 2012. Construction/
reconstruction/ replacement and renovation of the facilities will be conducted in the 4 components.
1.Water treatment plant
2.Transmission and distribution facilities including house connection in Western zone
3.Transmission and distribution facilities including house connection in Central zone
4.Transmission and distribution facilities including house connection in Eastern zone
Chandrawal WTP command area is divided into UGR command areas that are sub-divided into DMAs.
Water distribution will be managed on DMA basis. SCADA system will be introduced as a tool of
distribution management or equitable water distribution.
NRW ratio will be calculated in each DMA or DMA basis, ranked DMA according to NRW ratio.
Taking NRW reduction measures on the higher NRW ratio, water loss will be reduced and the saved
water can be used effectively, contributing to 24x7 water supply.
Thus the Project overall goal will be achieved when the project is constructed. The followings are
suggested for smooth implementation of the Japanese ODA loan project base on the Project:
(1) Early Implementation
More than 4 years have elapsed since November 2013 when the consultants started a detailed design.
However, no construction works have started yet in any of the 4 components.
As of March 2018, tendering is being processed for component 1 while DPRs of components 2 to 4
were under review by DJB. Although the facilities will not be completed by the target year of 2021
considering only 4 years are left and volume of works, the work should be accelerated to achieve the
Project purpose as early as possible. The followings are some of the measures considered:
Prompt decision by strengthening of the concerned section dealing with the Japanese ODA loan
project
Reduction in re-work by close communication between DJB and the consultants
Acceleration of tendering procedure between DJB and JICA
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
7-2
(2) Re-organization of Meter Reading Area (Suggested already in MP and terminal evaluation )
Three-tier distribution system will be established in the Chandrawal WTP command area for equitable
water distribution.
1st Tier:from WTP to UGR/BPS (Transmission Facilities)
2nd Tier:from UGR/BPS to DMA (Main Distribution Facilities)
3rd Tier:Inside of DMA (Distribution Facilities)
Distribution SCADA center, placed at the WTP will monitor and control water flow to each DMA for
equitable water distribution. To do so, water demand in each DMA is to be known and this can be
estimated based on number of house connection in each DMA.
DMA cell has already grasped number of house connection in more than 30 DMAs that were
established as an experimental base in Delhi. Similarly DJB should know number of house
connections in more than 100 DMAs in Chandrawal WTP command area. Re-organization of Meter
Reading Area is recommended.
(3) Re-organization of Distribution Office (Suggested already in MP and terminal evaluation )
Reduction of NRW is also a main purpose of the Project. Inflow to DMA can be measured by SCADA
system. Billed water volume can be obtained from RMS. If Meter Reading Area is re-organized
according to DMA, billed water volume can be easily obtained. Then, NRW ratio can be easily
calculated.
Once NRW ratio in each DMA is known, NRW reduction measures should be taken up starting from
the DMA with high NRW ratio. This will become the main works of distribution management offices
in addition to ensuring equitable water distribution. Hence, distribution offices should be re-organized
based on DMA.
(4) Integration of Household Survey Results with DSSDI maps
NRW consists of physical loss and non-physical (apparent) loss. Illegal connection is one of the main
apparent losses. Number of illegal connection is large although the number is being decreased thanks
to RMS.
Illegal connections are detected much easily than that of the leakages. In order to detect more, results
of household survey (connection) should be plotted into DSSDI maps in the Japanese ODA loan
project. This integration will clearly highlight connection status; legal or illegal.
(5) Integration of collected Pipe Information with GIS maps
In future in the mid- and long-term prospective, renewal plan needs to be formulated based on the
asset management; status or condition of each asset: Large benefit should be sought with small cost by
limiting facilities for renewal.
The Assistance Related to Delhi Water Supply Improvement Project FINAL REPORT
7-3
DSSDI maps are only information source of invisible pipes; however, status of pipes for rehabilitation
could not be evaluated based on DSSDI maps where there is little information on year of pipe
installation that is a major factor for rehabilitation.
The development scenario of GIS/RMS suggested the followings to accumulate correct information
for the future:
・ As-built drawings prepared under the components 2 to 4 should be input to GIS information.
・ Status of pipe by trial diggings should be reflected to GIS mapping of the component 5.
Asset management can be formulated accurately based on pipe information on GIS.
(6) Service Pipes and House Meters
Spaghetti-type house connections are commonly found in congested area with narrow streets where
distribution pipes are not properly laid out. In the Japanese ODA loan project, distribution pipes are
fully extended along every street and spaghetti-type house connections will be removed. It is
recommended that this type of arrangement can be applied in the entire Delhi.
(7) Suggested Items in the Mid-term Review
Although change of specification of chamber, method of construction supervision and process of road
cut permission (related to Output 1) was suggested and highlighted in the mid-term review, these were
already informed to the Japanese ODA loan consultants through DJB at the end of Output 1.