Upload
sudarshantare10
View
219
Download
0
Embed Size (px)
Citation preview
8/3/2019 Final Operations
1/38
CPM & PERTPrepa
redforOperationalResearch
1
Crystal Britto 71
Fenil Jiwani 80
Kirthika Nadar 84
Nikhil Vinchurkar 93
Sudarshan Tare 111
Sunil Dhake 113
8/3/2019 Final Operations
2/38
FLOW OF PRESENTATION
Introduction to CPM & PERT
History
Comparision between CPM & PERT
What is Crashing ?
Example on Crashing and Pert
Benefits/Advantages
Limitations/Disadvantages
Applications/uses of CPM/PERT
Case Study
8/3/2019 Final Operations
3/38
WHAT IS CPM/PERT?
y Critical path method and Project evaluation review technique
are the methods to estimate the tentative durations forcompleting a project.
These techniques help project managers to handle the
complexity and time based nature of the project.
3
8/3/2019 Final Operations
4/38
HISTORY
PERT developed by Booz Allen Hamilton and The US Navy for
planning and control of the Polaris missile program.
Emphasis- Completing the program in the shortest possibletime
CPM developed byMorgan R Walker of Du Pont in 1950.
Emphasis- Trade off between the cost of the project and its
overall completion time.
4
8/3/2019 Final Operations
5/38
CPM - CRITICAL PATH METHOD
Definition: The critical path method (CPM) is a step-by-step
technique for process planning that defines critical and non-
critical tasks with the goal of preventing time-frame problems
and process bottlenecks
y Single estimate of activity time
y Deterministic activity times
USED IN : Production management - for the jobs which are
repetitive in nature where the activity time estimates can
be predicted with considerable certainty due to the
existence of past experience.
8/3/2019 Final Operations
6/38
PERT -
PROJECT EVALUATION & REVIEW TECHNIQUES
Definition: PERT is a method to analyze the involved tasks incompleting a given project, especially the time needed tocomplete each task, and to identify the minimum time needed to
complete the total project.
Multiple time estimates
Probabilistic activity times
USED IN : Project management - for non-repetitive jobs(research and development work), where the time and costestimates tend to be quite uncertain. This technique usesprobabilistic time estimates.
8/3/2019 Final Operations
7/38
EMPHASIS ON LOGIC IN NETWORK
CONSTRUCTION Construction of network should be based on logical or technical
dependencies among activities
Example - before activity Approve Drawing can be started, theactivity Prepare Drawing must be completed
Common error build network on the basis of time logic (afeeling for proper sequence ) see example below
7
WRONG !!! CORRECT
8/3/2019 Final Operations
8/38
3 POINT ESTIMATES FOR PERT
8
8/3/2019 Final Operations
9/38
CRITICAL PATH
Longest path through a network.
Is that the sequence of activities and events where there is noslack i.e.. Zero slack
Determines the total time required to complete the project
9
8/3/2019 Final Operations
10/38
COMPARISON BETWEEN CPMAND PERT
CPM PERT
1 Uses network, calculate float or slack,identify critical path and activities,guides to monitor and controllingproject
Uses network, calculate total estimate& variance, identify critical path andactivities, guides to monitor andcontrolling project
2 Uses one value of activity time Requires 3 estimates of activity time
Calculates mean and variance of time
3 Used where times can be estimatedwith confidence, familiar activities
Used where times cannot be estimatedwith confidence.
Unfamiliar or new activities
4 Minimizing cost is more important Meeting time target or estimating
percent completion is more important5 Focuses on time and cost Focuses only on time
6 Example: construction projects,building one off machines, ships, etc
Example: Involving new activities orproducts, research and developmentetc 10
8/3/2019 Final Operations
11/38
QUESTIONSANSWERED BYCPM & PERT
Completion date?
On Schedule?
Within Budget?
Critical Activities?
How can the project be finished early at the least cost?
11
8/3/2019 Final Operations
12/38
WHAT IS CRASHING?
Project crashing is a method for shortening the project
duration by reducing the time of one or more of the
critical project activities to less than its normal
activity time.
The objective of crashing is to reduce project duration
at minimum cost.
12
8/3/2019 Final Operations
13/38
EXAMPLE:
Activity Precedin
g
Activity
Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
A - 3 2 18000 19000
B - 8 6 600 1000
C B 6 4 10000 12000
D B 5 2 4000 10000
E A 13 10 3000 9000
F A 4 4 15000 15000
G F 2 1 1200 1400
H C,E,G 6 4 3500 4500
I F 2 1 7000 800013
8/3/2019 Final Operations
14/38
Draw a project network diagram and find critical
path.
If a deadline of 17 weeks is imposed for
completion of the project, what activities will becrashed, What would be the additional cost, and
what would be the critical activities of the
network after crashing?
14
8/3/2019 Final Operations
15/38
NETWORK
15
1-2-4-6 A-F-I =9
1-2-4-5-6 A-F-G-H=15
1-2-5-6 A-E-H=22 CRITICAL PATH
1-3-5-6 B-C-H =20
1-3-6 B-D =13
8/3/2019 Final Operations
16/38
FORMULA
16
8/3/2019 Final Operations
17/38
Activity Path Crashing Cost (rs)
A 1-2 1000
B 1-3 200
C 3-5 1000
D 3-6 2000
E 2-5 2000
F 2-4 -
G 4-52
00H 5-6 500
I 4-6 1000
17
8/3/2019 Final Operations
18/38
Total cost= Normal cost + crash cost
62300+6200
=68500
18
8/3/2019 Final Operations
19/38
PERT
The owner of a chain of a fast food restaurants is
considering a new computer system for
accounting and inventory control. A computer
company sent the following information about the
system installation
19
8/3/2019 Final Operations
20/38
Activit
y
Description predecess
or
A Select the comp model - 4 6 8
B Design I/O system A 5 7 15
C Design monitoring system A 4 8 12
D Assemble computerhardware
B 15 20 25
E Develop the main
programmes
B 10 18 26
F Develop I/O routines C 8 9 16
G Create database E 4 8 12
H Install the system D,F 1 2 3
I Test & Implement G,H 6 7 8
20
8/3/2019 Final Operations
21/38
Construct an arrow diagram for this problem
Determine the critical path and complete the
expected project completion time.
Determine the probability of completing the project in 55 days
21
8/3/2019 Final Operations
22/38
Activi
ty
Path To Tm Tp Te
A 1-2 4 6 8 6 0.66 0.4356
B 2-3 5 7 15 8 1.66 2.7556
C 2-4 4 8 12 8 1.33 1.7689
D 3-6 15 20 25 20 1.66 2.7556
E 3-5 10 18 26 18 2.66 7.0756
F 4-6 8 9 16 10 1.33 1.7689
G 5-7 4 8 12 8 1.33 1.7689
H 6-7 1 2 3 2 0.33 0.1089
I 7-8 6 7 8 7 0.33 0.1089
22
8/3/2019 Final Operations
23/38
1-2-3-5-7-8
6+8+18+8+7=47 critical path
X=47
U=55 =3.496
8/3/2019 Final Operations
24/38
FORMULA
24
8/3/2019 Final Operations
25/38
The area between mean and z=2.89
0.5+0.4981=0.9981
8/3/2019 Final Operations
26/38
BENEFITS OF CPM/PERT
y Breakdown project into component tasks
y Forecast and Analyze Possibilities
y Focused and Disciplined
y
Improved Communication
26
8/3/2019 Final Operations
27/38
LIMITATIONS
There can be potentially hundreds or thousands of activities and
individual dependency relationships
PERT is not easily scalable for smaller projects
The network charts tend to be large and unwieldy requiringseveral pages to print and requiring special size paper
The lack of a timeframe on most PERT/CPM charts makes it
harder to show status although colors can help (e.g., specific color
for completed nodes)
When the PERT/CPM charts become unwieldy, they are nolonger used to manage the project.
27
8/3/2019 Final Operations
28/38
Packages are available to determine the shortest path and
other relevant information.
28
8/3/2019 Final Operations
29/38
Data entry window
29
8/3/2019 Final Operations
30/38
Output of the package
30
8/3/2019 Final Operations
31/38
Applications of CPM & PERT
1. Construction of a new plant.
2. Research and development of a new product.
3. NASA space exploration projects.
4. Movie productions.5. Building of a ship.
6. Government-sponsored projects for developing a new
weapons system.
7. Relocation of a major facility.
8. Maintenance of a nuclear reactor.
9. Installation of a management information system.10. Conducting an advertising campaign.
31
8/3/2019 Final Operations
32/38
CASE STUDY
The Reliable Construction Company has just made the winning bid
of $5.4 million to construct a new plant for a major manufacturer.
The manufacturer needs the plant to go into operation within a
year. Therefore, the contract includes the following provisions:
A penalty of $300,000 if Reliable has not completed construction
by the deadline 47 weeks from now.
To provide additional incentive for speedy construction, a bonus of
$150,000 to be paid to Reliable if the plant is completed within 40
weeks.
32
8/3/2019 Final Operations
33/38
Reliable assigned its best construction manager, David Perty,
to this project to help ensure that it stays on schedule. In
order to schedule the activities, Mr. Perty consults with each
of the crew foremen to develop an estimate of how long each
activity should take when it is done in the normal way.
Adding up these times gives a grand total of 79 weeks, which is
far beyond the deadline for the project. Fortunately, some of
the activities can be done in parallel, which substantially
reduces the project completion time.
CONT
33
8/3/2019 Final Operations
34/38
Activity Activity Description Immediate
Predecessors
Estimated
Duration
A Excavate 2 weeks
B Lay the foundation A 4 weeks
C Put up the rough wall B 10 weeks
D Put up the roof C 6 weeks
E Install the exterior plumbing C 4 weeks
F Install the interior plumbing E 5 weeks
G Put up the exterior siding D 7 weeks
H Do the exterior painting E, G 9 weeks
I Do the electrical work C 7 weeks
J Put up the wallboard F, I 8 weeks
K Install the flooring J 4 weeks
L Do the interior painting J 5 weeks
M Install the exterior fixtures H 2 weeks
N Install the interior fixtures K, L 6 weeks
Activity List for the Reliable Construction Co.Project
34
8/3/2019 Final Operations
35/38
CONCLUSION
35
8/3/2019 Final Operations
36/38
REFERENCES
http://en.wikipedia.org/wiki/Program_Evaluation
_and_Review_Technique
http://dl.acm.org/citation.cfm
Quantative Techniques in Management by N. D.VOHRA
http://www.mindtools.com/critpath.html
36
8/3/2019 Final Operations
37/38
Thank you
37
8/3/2019 Final Operations
38/38
WISH YOU ALL A VERY HAPPYPONGAL
38