Final Operations

Embed Size (px)

Citation preview

  • 8/3/2019 Final Operations

    1/38

    CPM & PERTPrepa

    redforOperationalResearch

    1

    Crystal Britto 71

    Fenil Jiwani 80

    Kirthika Nadar 84

    Nikhil Vinchurkar 93

    Sudarshan Tare 111

    Sunil Dhake 113

  • 8/3/2019 Final Operations

    2/38

    FLOW OF PRESENTATION

    Introduction to CPM & PERT

    History

    Comparision between CPM & PERT

    What is Crashing ?

    Example on Crashing and Pert

    Benefits/Advantages

    Limitations/Disadvantages

    Applications/uses of CPM/PERT

    Case Study

  • 8/3/2019 Final Operations

    3/38

    WHAT IS CPM/PERT?

    y Critical path method and Project evaluation review technique

    are the methods to estimate the tentative durations forcompleting a project.

    These techniques help project managers to handle the

    complexity and time based nature of the project.

    3

  • 8/3/2019 Final Operations

    4/38

    HISTORY

    PERT developed by Booz Allen Hamilton and The US Navy for

    planning and control of the Polaris missile program.

    Emphasis- Completing the program in the shortest possibletime

    CPM developed byMorgan R Walker of Du Pont in 1950.

    Emphasis- Trade off between the cost of the project and its

    overall completion time.

    4

  • 8/3/2019 Final Operations

    5/38

    CPM - CRITICAL PATH METHOD

    Definition: The critical path method (CPM) is a step-by-step

    technique for process planning that defines critical and non-

    critical tasks with the goal of preventing time-frame problems

    and process bottlenecks

    y Single estimate of activity time

    y Deterministic activity times

    USED IN : Production management - for the jobs which are

    repetitive in nature where the activity time estimates can

    be predicted with considerable certainty due to the

    existence of past experience.

  • 8/3/2019 Final Operations

    6/38

    PERT -

    PROJECT EVALUATION & REVIEW TECHNIQUES

    Definition: PERT is a method to analyze the involved tasks incompleting a given project, especially the time needed tocomplete each task, and to identify the minimum time needed to

    complete the total project.

    Multiple time estimates

    Probabilistic activity times

    USED IN : Project management - for non-repetitive jobs(research and development work), where the time and costestimates tend to be quite uncertain. This technique usesprobabilistic time estimates.

  • 8/3/2019 Final Operations

    7/38

    EMPHASIS ON LOGIC IN NETWORK

    CONSTRUCTION Construction of network should be based on logical or technical

    dependencies among activities

    Example - before activity Approve Drawing can be started, theactivity Prepare Drawing must be completed

    Common error build network on the basis of time logic (afeeling for proper sequence ) see example below

    7

    WRONG !!! CORRECT

  • 8/3/2019 Final Operations

    8/38

    3 POINT ESTIMATES FOR PERT

    8

  • 8/3/2019 Final Operations

    9/38

    CRITICAL PATH

    Longest path through a network.

    Is that the sequence of activities and events where there is noslack i.e.. Zero slack

    Determines the total time required to complete the project

    9

  • 8/3/2019 Final Operations

    10/38

    COMPARISON BETWEEN CPMAND PERT

    CPM PERT

    1 Uses network, calculate float or slack,identify critical path and activities,guides to monitor and controllingproject

    Uses network, calculate total estimate& variance, identify critical path andactivities, guides to monitor andcontrolling project

    2 Uses one value of activity time Requires 3 estimates of activity time

    Calculates mean and variance of time

    3 Used where times can be estimatedwith confidence, familiar activities

    Used where times cannot be estimatedwith confidence.

    Unfamiliar or new activities

    4 Minimizing cost is more important Meeting time target or estimating

    percent completion is more important5 Focuses on time and cost Focuses only on time

    6 Example: construction projects,building one off machines, ships, etc

    Example: Involving new activities orproducts, research and developmentetc 10

  • 8/3/2019 Final Operations

    11/38

    QUESTIONSANSWERED BYCPM & PERT

    Completion date?

    On Schedule?

    Within Budget?

    Critical Activities?

    How can the project be finished early at the least cost?

    11

  • 8/3/2019 Final Operations

    12/38

    WHAT IS CRASHING?

    Project crashing is a method for shortening the project

    duration by reducing the time of one or more of the

    critical project activities to less than its normal

    activity time.

    The objective of crashing is to reduce project duration

    at minimum cost.

    12

  • 8/3/2019 Final Operations

    13/38

    EXAMPLE:

    Activity Precedin

    g

    Activity

    Normal

    Time

    Crash

    Time

    Normal

    Cost

    Crash

    Cost

    A - 3 2 18000 19000

    B - 8 6 600 1000

    C B 6 4 10000 12000

    D B 5 2 4000 10000

    E A 13 10 3000 9000

    F A 4 4 15000 15000

    G F 2 1 1200 1400

    H C,E,G 6 4 3500 4500

    I F 2 1 7000 800013

  • 8/3/2019 Final Operations

    14/38

    Draw a project network diagram and find critical

    path.

    If a deadline of 17 weeks is imposed for

    completion of the project, what activities will becrashed, What would be the additional cost, and

    what would be the critical activities of the

    network after crashing?

    14

  • 8/3/2019 Final Operations

    15/38

    NETWORK

    15

    1-2-4-6 A-F-I =9

    1-2-4-5-6 A-F-G-H=15

    1-2-5-6 A-E-H=22 CRITICAL PATH

    1-3-5-6 B-C-H =20

    1-3-6 B-D =13

  • 8/3/2019 Final Operations

    16/38

    FORMULA

    16

  • 8/3/2019 Final Operations

    17/38

    Activity Path Crashing Cost (rs)

    A 1-2 1000

    B 1-3 200

    C 3-5 1000

    D 3-6 2000

    E 2-5 2000

    F 2-4 -

    G 4-52

    00H 5-6 500

    I 4-6 1000

    17

  • 8/3/2019 Final Operations

    18/38

    Total cost= Normal cost + crash cost

    62300+6200

    =68500

    18

  • 8/3/2019 Final Operations

    19/38

    PERT

    The owner of a chain of a fast food restaurants is

    considering a new computer system for

    accounting and inventory control. A computer

    company sent the following information about the

    system installation

    19

  • 8/3/2019 Final Operations

    20/38

    Activit

    y

    Description predecess

    or

    A Select the comp model - 4 6 8

    B Design I/O system A 5 7 15

    C Design monitoring system A 4 8 12

    D Assemble computerhardware

    B 15 20 25

    E Develop the main

    programmes

    B 10 18 26

    F Develop I/O routines C 8 9 16

    G Create database E 4 8 12

    H Install the system D,F 1 2 3

    I Test & Implement G,H 6 7 8

    20

  • 8/3/2019 Final Operations

    21/38

    Construct an arrow diagram for this problem

    Determine the critical path and complete the

    expected project completion time.

    Determine the probability of completing the project in 55 days

    21

  • 8/3/2019 Final Operations

    22/38

    Activi

    ty

    Path To Tm Tp Te

    A 1-2 4 6 8 6 0.66 0.4356

    B 2-3 5 7 15 8 1.66 2.7556

    C 2-4 4 8 12 8 1.33 1.7689

    D 3-6 15 20 25 20 1.66 2.7556

    E 3-5 10 18 26 18 2.66 7.0756

    F 4-6 8 9 16 10 1.33 1.7689

    G 5-7 4 8 12 8 1.33 1.7689

    H 6-7 1 2 3 2 0.33 0.1089

    I 7-8 6 7 8 7 0.33 0.1089

    22

  • 8/3/2019 Final Operations

    23/38

    1-2-3-5-7-8

    6+8+18+8+7=47 critical path

    X=47

    U=55 =3.496

  • 8/3/2019 Final Operations

    24/38

    FORMULA

    24

  • 8/3/2019 Final Operations

    25/38

    The area between mean and z=2.89

    0.5+0.4981=0.9981

  • 8/3/2019 Final Operations

    26/38

    BENEFITS OF CPM/PERT

    y Breakdown project into component tasks

    y Forecast and Analyze Possibilities

    y Focused and Disciplined

    y

    Improved Communication

    26

  • 8/3/2019 Final Operations

    27/38

    LIMITATIONS

    There can be potentially hundreds or thousands of activities and

    individual dependency relationships

    PERT is not easily scalable for smaller projects

    The network charts tend to be large and unwieldy requiringseveral pages to print and requiring special size paper

    The lack of a timeframe on most PERT/CPM charts makes it

    harder to show status although colors can help (e.g., specific color

    for completed nodes)

    When the PERT/CPM charts become unwieldy, they are nolonger used to manage the project.

    27

  • 8/3/2019 Final Operations

    28/38

    Packages are available to determine the shortest path and

    other relevant information.

    28

  • 8/3/2019 Final Operations

    29/38

    Data entry window

    29

  • 8/3/2019 Final Operations

    30/38

    Output of the package

    30

  • 8/3/2019 Final Operations

    31/38

    Applications of CPM & PERT

    1. Construction of a new plant.

    2. Research and development of a new product.

    3. NASA space exploration projects.

    4. Movie productions.5. Building of a ship.

    6. Government-sponsored projects for developing a new

    weapons system.

    7. Relocation of a major facility.

    8. Maintenance of a nuclear reactor.

    9. Installation of a management information system.10. Conducting an advertising campaign.

    31

  • 8/3/2019 Final Operations

    32/38

    CASE STUDY

    The Reliable Construction Company has just made the winning bid

    of $5.4 million to construct a new plant for a major manufacturer.

    The manufacturer needs the plant to go into operation within a

    year. Therefore, the contract includes the following provisions:

    A penalty of $300,000 if Reliable has not completed construction

    by the deadline 47 weeks from now.

    To provide additional incentive for speedy construction, a bonus of

    $150,000 to be paid to Reliable if the plant is completed within 40

    weeks.

    32

  • 8/3/2019 Final Operations

    33/38

    Reliable assigned its best construction manager, David Perty,

    to this project to help ensure that it stays on schedule. In

    order to schedule the activities, Mr. Perty consults with each

    of the crew foremen to develop an estimate of how long each

    activity should take when it is done in the normal way.

    Adding up these times gives a grand total of 79 weeks, which is

    far beyond the deadline for the project. Fortunately, some of

    the activities can be done in parallel, which substantially

    reduces the project completion time.

    CONT

    33

  • 8/3/2019 Final Operations

    34/38

    Activity Activity Description Immediate

    Predecessors

    Estimated

    Duration

    A Excavate 2 weeks

    B Lay the foundation A 4 weeks

    C Put up the rough wall B 10 weeks

    D Put up the roof C 6 weeks

    E Install the exterior plumbing C 4 weeks

    F Install the interior plumbing E 5 weeks

    G Put up the exterior siding D 7 weeks

    H Do the exterior painting E, G 9 weeks

    I Do the electrical work C 7 weeks

    J Put up the wallboard F, I 8 weeks

    K Install the flooring J 4 weeks

    L Do the interior painting J 5 weeks

    M Install the exterior fixtures H 2 weeks

    N Install the interior fixtures K, L 6 weeks

    Activity List for the Reliable Construction Co.Project

    34

  • 8/3/2019 Final Operations

    35/38

    CONCLUSION

    35

  • 8/3/2019 Final Operations

    36/38

    REFERENCES

    http://en.wikipedia.org/wiki/Program_Evaluation

    _and_Review_Technique

    http://dl.acm.org/citation.cfm

    Quantative Techniques in Management by N. D.VOHRA

    http://www.mindtools.com/critpath.html

    36

  • 8/3/2019 Final Operations

    37/38

    Thank you

    37

  • 8/3/2019 Final Operations

    38/38

    WISH YOU ALL A VERY HAPPYPONGAL

    38