Lifting Plan
Lifting Plan No:-
Project: - IWWTP @ Banyan Project
Date: - -- July 2012
Contractor: - Tricaftan Environmental Technology Pte Ltd
Lifting supervisor - Name:- Mongou
Main Contractor - Hitachi Plant Technologies, Ltd
Main contractor Engineer - Name:-Ms Amy Thoo
1. Specialist Lifting Contractor:-
Name: - Tricaftan
Mobile Crane, Lorry Crane or Crawler Crane (What crane identify) Mobile
Crane
What Type:- Mobile Crane (50 Tons)
2. Time: - 9:00 Am to 5:00 pm From: - --.07.2012 to --.07.2012
Brief Description Of Lifting Operation: - Hoisting up the ---nos: of
Chemical containers to on top of the ASR/CR concrete Tank
(Please Descript what activity will going to do)
3. Name of appointed Person from Contractor:- Mongou (Lifting Supervisor)
Experience and qualification-Above 4 years, Lifting Supervisor
Name Of Lifting Supervisor:-Mongou
LOA submitted to HPT? Please clarify hereYes
4. Name of singers/signalers qualification and experience:-
Rigger and Signalman
Page 1
7/27/2019 Final Lifting Plan Sample
2/7
Lifting Plan
a. ---------- (Signal)
b. Fazlul (Rigger)
LOA submitted to HPT? Please clarify hereYes
5. List means of identification (i.e. what clothing or color helmet etc will
identify them from other site workers.
Vest- Red color with RIGGER or SIGNALMAN sign at the back.
Safety helmet- Red color.
6. Description of Loads:-
a. Weight- Max weight of load shall be 80% of SWL.
b. Characteristics- Miscellaneous types of materials, equipment
c. Method of lifting- Using web belt sling and shackle.
d. Center of gravity- Align with crane hook.
e. Lifting point or method of sling- To be determined by lifting supervisor.
7. Lifting Equipment or appliance to be used:-
a. Make / Model: - KATO NK500E-III
b. Maximum capacity- 7.5 t x 9.5 m, 40m Boom
c. Counter Weight- 50T hook (500kg)
d. Main Boom Length- 40m
e. Fly Jib extension- 15m (2section)
f. Outrigger load- 39 tonne (front: approx. 15t, rear:approx. 24t)
Page 2
7/27/2019 Final Lifting Plan Sample
3/7
Lifting Plan
g. Maximum Radius- 11.5 m
h. Safe Working Load- boom 40m, 1.25 tons
8. Lifting Accessories to be used and SWL-
a.
b. LG H624 B.S.P. shackle SWL
c. LG H625 B.S.P. shackle SWL
d. LG H626 B.S.P. shackle SWL
e. LG H620 W.B. Sling SWL Refer to PTW
f. LG H621 W.B. Sling SWL
g. LG H623 W.B. Sling SWL
h. Lifting gears from ? AsiaGroup Leasing Pte Ltd
9. Proximity Hazards:-
a. Overhead Power Lines- None
b. Underground Tunnels- None
c. Airports- None
d. Other Strictures- None
e. Underground Services- None
f. Other Carnages None
g. Others (specify)-NA
10. Ground conditions & Appropriate Controls:-
Ground area is level and compacted Hardcore, concrete slab
Page 3
7/27/2019 Final Lifting Plan Sample
4/7
Lifting Plan
Steel plate supports to be used for the outrigger base
Outrigger is fully extended
Width of access area is adequate to allow passenger of crane including full
extended outriggers.
11. Are Temp Workers involved in the lift.
Described- 4 workers for support the lifting team
12. What demarcation will be used:-
a. Is the area an exclusion zone- Yes.
b. What barriers and signage- Temporary barriers Yellow and black flag or
orange plastic net and warring signages. (Temporary barriers Yellow and
black flag), (Danger, Keep Out Signage)
13. Control of load (tag lines etc)
Use of Tag line.
14. Crane Rigging requirement (ground condition)-
Stable and level ground, compacted hardcore, concrete slab
Steel plate for outrigger base.
15. Access/Egress (Lifting Equipment-vehicles etc.)
16. Wind speed( what is maximum wind speed for safe lifting, how is it
recorded)- 20mph
Page 4
7/27/2019 Final Lifting Plan Sample
5/7
Lifting Plan
17. Is lifting Open or blind? Describe of method of
signaling/dogging-(Specify the number of signalers to be used.)
One signalman is to be used. Communication is by hand signals, Visual
contact between operator and signalman is maintained. Whatever visibility is
not possible. Communication between operator and signalman shall be byradio.
18. Communication? (What means)
Communication between operator and signalman by hand signals and by
radio.
19. Have appropriate BLL and crane operator checklist been
completed.-
Yes.
20. Crane Operator Appointed Person (Contractor) Review & Date.
See guidance note in section 5 below
Signature-
Print Name-
Date-
21. Approved by BLL crane Coordinator.
Signature-
Print Name-
Page 5
7/27/2019 Final Lifting Plan Sample
6/7
Lifting Plan
Date-
The lifting plan is to be used no matter the type of lift; standard lifts may
need to be reviewed weekly (not weekly. Every lifting operation must submit
LP) to ensure nothing has changed. Should the lifting operation come under
scrutiny the lifting plan is evidence of addressing all aspect pertaining to theplanning of the operation. If lifts are to be repetitive (standard) type then the
one lifting plan can be put in place and remain as long as no significant
changes have taken place. However as stated preciously it must be reviewed
weekly by contractors appointed person.
Note: - For all the Lifting operation must prepare lifting plan to submit HPT
before commencement. And attach together Lifting permit.