    MINISTRY OF ECONOMIC DEVELOPMENTAND

    PRESIDENTIAL TASK FORCE

    Housing Project under

    Indian Assistance

    Project ReportSeptember 2010

    Final Draft

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    2/30

    HOUSINGRECONSTRUCTIONPROGRAMMEINTHENORTHERNPROVINCE

    UNDERTHEASSISTANCE FROMTHEGOVERNMENTOFINDIA

    Contents:1.BackgroundandIntroduction2. ImplementationArrangement

    3.ProgrammeDescription4.ProgrammeImplementationProcessand Roles ofAgencies5.OperationalCost6.OperationalInstructions

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    3/30

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    4/30

    2

    1.4.2 Spatial Scope:

    Considering the (i) extent of displacement and (ii) severity of the housing damage, as at present, all

    the 50,000 are marked for the north. However, a certain percentage say 5% may be set aside for the

    east especially for those displaced in the chronically underdeveloped parts of Eastern Province.

    1.4.3 Land:

    As the investments in housing repair and reconstruction are spatially fixed, land is a criticalelement of

    the proposed program. While the land protection and property rights issues will not be overlooked,

    the programme will adopt a pragmatic approach to ensure a continuous processing of simpler, eligible

    cases while the more complex ones are resolved through existing and enhanced frameworks. The

    program will identify workable mechanisms to ensure that those receiving housing assistance are the

    rightful owners of the land on which they invest. The program, therefore, supports a land resolution

    and regularization strategy within the framework of existing land administration. To resolve villagespecific land issues, task forces will be established at district and provincial levels and these teams

    will resolve issues related to loss of records, boundary disputes and regularization of state land

    occupied by the claimants, etc.

    1.4.4 Limited Production Capacity:

    The scale of input price increases will be a major concern, especially input such as sand, timber and

    cement Adding a significant number of new housing units to these demands would have significant

    additional price effects. These capacity constraints could be sorted out by establishing the following

    a. Establishing regional bulk supply stations in each district with a supply network linking with state

    agencies such as Building Material Cooperation, State Timber Corporation and Malty Purpose

    Cooperative Societies.

    b. Encouraging private pre-cast construction materials producers to establish their yards in local with

    the support of National Engineering Research Development Center

    c. Identifying the locally available low cost and alternative construction materials, train the locally

    available construction employees in the technology and encourage to adopt.

    1.4.5.Quality of housing:

    The larger grant will bring with it grater expectation of quality construction, hence ensuring quality

    construction is essential. This requires at least one engineer per 1500 houses and one technical Officer

    per 75 houses under construction. A third party independent technical audit will ensure the quality of

    housing.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    5/30

    3

    1.4.6.Vocational and on the job training:

    There will be more demand for skill workers in the field of construction during the programme period.

    The Wanni area do not have adequate skill construction workers. As house construction is quite simple,

    arrangement will be made to provide on the job training for youths and beneficiaries to minimize the

    problem.

    1.4.7 Environment:

    The long years of conflict in the North East have resulted in significant natural resource degradation,

    particularly in the deforestation of the extensive forest cover in the region. The urgency for housing

    reconstruction could result in further aggravating the problem of conflict related deforestation through

    exploitation of forest resources for timber. In addition, the demand for construction material could

    increase sand and clay mining (the latter mainly for bricks). The mining of sand in rivers has the

    potential to cause the lowering of the riverbed, collapse of the banks, intrusion of seawater and

    reduced sand replenishment in the beaches. Mining of coastal sand exacerbates coastal erosion. Water

    resources are scarce, particularly in the North, and can pose problems during construction. Improper

    sanitary facilities or the lack of it, improper disposal of liquid and solid wastes are some of the other

    main issues concerned with the project. It is necessary to identify these risks and to incorporate proper

    strategies into the design of the project to mitigate such risks. Experience gained from the North East

    Housing Programme(NEHRP) will be used to screen the target villages under the project proper, for a

    rapid environmental assessment and to improve the overall implementation of the project.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    6/30

    4

    CHAPTER 2IMPLEMENTATIONARRANGEMENT

    2.1. The programme will be implemented in 2 stages.

    a. Construction of one thousand cluster based houses in relocated areas as a pilot project

    b. construction of 50,000 houses under home owner driven basis. This will be implemented in two stages

    as given below

    i. Repairs of 10,000 houses in both Jaffna and Vanni electorate.

    ii. Normal Programme- Construction of 40,000 houses (Both partly damaged and fully damaged).

    2.2 a.Construction of one thousand cluster based houses in relocated area

    2.2.1. Selection of Beneficiaries

    Under this stage, landless IDPs will be identified and be resettled in newly identified habitable areas. The

    most vulnerable groups will be given priority among the land less under this programme as indicated

    below

    a. Widowsb. Single headed house holdsc. Differently abled. Infirm as result of old agee. Infirm as a result of injuryf. Families below the poverty lineThe respective Government Agents have identified the beneficiaries according to the above said criteria

    and allocated land to them as indicated below.

    District DS Division GN Division Village No. of

    Beneficiaries

    Jaffna Jaffna J/68 Reclamation East 32

    J/69 Reclamation west 08

    Nallure J/90 Ariyalai East 50

    Thellipallai J/215 Allaveddy North 13

    J/216 Allaverddy Center 08

    J/217 Allaverddy East 09

    Karainagar J/44 Karainagar sourth 30

    Sub Total 150

    Kilinochchi Karaichchi Poonagar Arivial nagar 100

    Kandawalai Puliampotkanai Kandawalai 101

    Poonagari Pallikudah Thekerai 75

    Pachchilaipalli Soranpattu Karaithai 50

    Sub Total 326

    Mulaithivu Thunukai Uillankulam Uilnkulam 50

    Marritain Pattu Mulliyavallai west Vannan Vayal 50

    Oddisudan Thachchadampan Karripatta murripu 50

    Pandiyankulam Pandiankulam kaddukarai 50

    Sub Total 200

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    7/30

    5

    Mannar Manthai west Vellnkulam Vellankulam 12

    Kalliaddi Kalliaddi 60

    Madhu Parriapandivirichchan East Periyapandivirichchan

    East

    47

    Musalai Sillawathurai Sillavathurai 56

    Sub Total 175

    Vavuniya Vavuniya Vavuniya Marriadithakulam 50

    Vavuniya North Pulliyankulam North parasankulam 50

    Vavuniya South Mahamagilan Kulam Kudakacha Kodiya 50

    Venkalacheddikulam Andiyapulliyankulam Bihidiya farm 50

    Sub Total 200

    Arrangement have been made to provide basic community infrastructure and lively hood improvement

    facilities in the relocated villages

    2.2.2. Implementation mechanism

    Construction of houses will be contracted out and the housing construction will take place according

    to the beneficiaries preferred type plan (from among agreed and available type plans with the

    contractor) requirements and with their participation.

    The details of agreement made between the successful contractors and Government of India should be

    made available to the GOSL to enable the implementing agency to monitor carefully the quality of the

    construction and the progress of the programme. In view of the existing knowledge and experience

    available, the NEHRP (World Bank Funded Project) will be the implementing agency.

    2.2.3. Technical supervision and certification:

    NEHRP engineering unit will do the technical supervision on daily basis and certify for the payment

    of the constrictors as agreed on the contract.

    2.2.4 Monitoring arrangement :

    Monitoring will be carried out at three levels ie, District level, Provincial Level and National Level. At

    district level, District Coordinating committee will be monitoring the progress. Similarly at provincial

    level, provincial Project coordinating committee will monitor the project progress. A by weekly progress

    report will be submitted to the Hon. Governor, NPC highlighting important implementation issues.

    National steering Committee will be monitoring the progress on quarterly basis.

    2.3 .Construction of 50,000 houses under home owner driven basis.

    This will be implemented in two stages

    i. Repairs of 10,000 houses in both Jaffna and Vanni electorate.

    ii. Normal Programme- Construction of 40,000 houses (Both partly damaged and fully damaged).

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    8/30

    6

    2.3.1 Repairsof 10,000 houses in both Jaffna and Vanni electorate.

    Repair of 10,000 partly damaged houses will be undertaken during this stage following the

    implementation procedures stipulated in the chapters 3 and 4 as adopted by NEHRP under already

    implemented Home Owner Driven Programme.

    a. Terms of Payment: Maximum amount of SLRs. 200,000 will be released in three installments to thebeneficiaries bank account viz 1

    stpayment 50%, 2

    ndpayment 40% and 3

    rdpayment 10% based on

    the performance certified by the NEHRP technical officers. The beneficiaries entitlements will be

    according to the assessment by the technical team.

    b. Villages selection and beneficiaries selectionc. Grievance redress mechanismd. Land Ownership resolutione. Construction supervision and monitoring

    2.3.2 Normal Programme

    Implementation arrangement has been discussed in details in Chapters 3 & 4

    AsmentionedinChapter3&4

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    9/30

    7

    CHAPTER3 PROGRAMDESCRIPTION

    3.1 Program Components

    a. The Grant Description and Transfer Mechanism

    The Indian assistance will finance a cash grant to selected eligible beneficiary families (the

    eligibility criteria are described below). The selected eligible beneficiary families will qualify for

    one of two types of grants i.e. fully damaged housing grant or partly damaged housing grant.

    The assessment of fully damaged versus partly damaged houses will occur through a Housing

    Damage Assessment and Social Verification Survey. It will provide a cash grant of Rs600, 000 to

    beneficiary families whose house is assessed as fully damaged. It will provide a grant of Rs200,

    000 to beneficiary families whose house is assessed as partly damaged. It is estimated that 80% of

    the houses will be classified as fully damaged while 20% will be categorized as partly damaged.

    The grant will finance the physical requirement of at least a permanent foundation of 400 square

    feet, four walls and a roof and a toilet. Transfer of the cash grant to the joint bank accounts of the

    selected beneficiary will be made in four tranches for the fully damaged housing grant category

    and two tranches in the case of a partly damaged house. The pace of installments will be

    performance based.

    For fully damaged housing grants, initially Rs 100,000will be transferred to the joint bank account

    in the name of both husband and wife of each identified beneficiary household (unless it is a

    single headed household). This will be used to mobilize resources to reconstruct a fully damaged

    house. Upon verification by the divisional level engineer that the foundation has been completed

    and other construction progress has occurred, the second installment of Rs 200,000 will be

    transferred to enable the beneficiary to construct the superstructure. Upon completion of the

    foundation and superstructure, Rs 250,000 will be transferred to complete the house to

    specifications. Once the divisional engineer verifies completion of civil works by an on-site

    supervision, Rs 50,000 will be transferred to the beneficiarys bank account to reimburse the

    estimated remaining expenditure.

    For a partly damaged house, 50% of the estimated cost will be provided upfront. The second and

    final installment for repairs will be paid upon completion of the work.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    10/30

    8

    Each beneficiary family will be allowed a period of approximately six months for the completion

    of the physical works. This will mitigate against funds being recycled for other purposes. To

    facilitate compliance, each eligible beneficiary family will sign a memorandum of understanding

    with the District Program Unit. This will outline the target dates and construction progress

    required for each tranche payment to be triggered and any other obligations to be made by the

    beneficiary family.

    b. Apportioning of Funds across Beneficiaries and Districts

    TABLE No. 3.1

    IDPs, Housing Damage and Targeted Housing Repairs of 5000 Houses

    Electorate Districts NEHRP need

    assessment 2010

    (Tentative Estimate)

    Electorate

    allocation

    District allocation

    Jaffna Jaffna 9639 5,000 2,000

    Kilinochchi 2948 3,000

    Vanni Mulaithievu 1803 5,000 2,500

    Mannar 1432 1,250

    Vavuniya 1231 1,250

    17,053 10,000 10,000

    IDPs, Housing Damage and Targeted Housing New Construction

    Electrotrate Districts NEHRP need

    assessment

    2010(Tentative

    Estimate)

    District allocation

    in % of total

    District allocation

    in Numbers*

    Jaffna Jaffna 60,842 13.32% 5,800

    Kilinochchi 41,214 35% 13,600

    Vanni Mulaithievu 27,652 25% 10,000

    Mannar 23,926 13.34% 5,300

    Vavuniya 14,496 13.34% 5,300

    Total 40,000

    * Note: In Vavuniya District NEHRP completed its activities in 2008 and Vavuniya North has sustained heavy damage.

    In Jaffna district, the number of damage houses heavily influenced by the number of damaged houses took place from 2002.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    11/30

    9

    c. Village Selection and Beneficiary Selection

    Villages will be selected for participation based on a ranking system, taking into account: (i)

    caseload of damaged housing stock; (ii) caseload of returnees; (iii) extent of mine clearance and

    where available. Subsequent to selection of villages, grants will be allocated per village based on

    (i) caseload of returnees and; (ii) damaged housing stock. The list of villages to be included in the

    program, the number of grants per village, and a justification of each will be approved at the

    provincial level. It is estimated that approximately 500 villages will participate in this programme.

    Beneficiaries will be selected in the following manner: Subsequent to the selection of the villages

    and the allocation of grants per village through the process described above, a Housing Damage

    Assessment and Social Verification Survey in the selected villages will take place. The assessment

    team will consist of a Divisional technical officer, VRC member and a CBO representative

    supported by Grama Niladari of the village.

    A potential beneficiary must meet three eligibility conditions to be considered for the housing

    assistance to begin with. These are:

    The beneficiary, including the main breadwinner, should be permanently settled in the village. The beneficiary should possess a formal right to the land on which the reconstruction is proposed. The beneficiary should possess only one house which is fully or partly damaged and should not

    have been enlisted for assistance under any other programme. The beneficiary list of the housing

    programs of the particular area should be made available to this programme office for cross

    checking purpose. Families who meet the above eligibility criteria will then be prioritized based on

    the following prioritization criteria and using a quantified weighted scoring system as outlined in

    the Table 1.1 below.

    TABLE 3.2 : Weighted Scoring System for Beneficiary Selection

    Criteria applied to 1 point 2 points 3 points Additional

    Family Units Points

    No. of family members 6 persons 7-8 persons 9 and above

    Female single head With adult Children With children With children

    not supporting

    supporting children between 12- under 12 years

    or no children 18 years

    Disabled (mental and 1 person 2 persons 3 and above and

    physical) Parent/Breadwinner

    Elders Over 50 years Over 60 years Over 70 years

    Lost/Missing 1 person 2-3 persons 3 and above Breadwinner

    - 3 points

    Unaccompanied 1 person 2-3 persons 4 and above

    Minor/Orphan

    Total Score

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    12/30

    10

    Subsequent to the survey, there will be a computerized ranking and listing of eligible families in a

    particular village. The VRC will validate the list of identified beneficiaries equal in number to the

    number of allocated grants at a community meeting. Any amendments will be recorded in writing and

    will include the reasons as to why the amendment was made. The list will be subsequently advertised

    at a public place in the village concerned, together with the beneficiary scores. At a public meeting,

    the Divisional Secretary or his/her nominee will explain the methodology that drove the allocation

    process.

    d. Grievance Redress

    In the instance that any individual in a village disagrees with the list or his/her classification, he or she

    will be at liberty to participate in a grievance redress process. The grievance redress process will occur

    as follows:

    Subsequent to the publication of the list, the Divisional Secretary will visit a village, within a week,

    facilitated by the district office and convene a meeting of the VRC. Representatives of civil society

    will be invited to join the mobile divisional secretariat as observers. On that day, affected villagers

    may raise their grievances directly with the Divisional Secretary. These will be recorded in writing.

    Affected villagers may also send written grievances to the Divisional Secretary. These grievances

    must reach the Divisional Secretary by the date of his/her visit to the village. The Divisional

    Grievance Redress Committee consisting of the Divisional Secretary, two CBO representatives and

    the Heads of the VRCs from participating villages in that division, will review the complaints raised.

    Changes to the list will be introduced, if the committee sees fit. There will be a two week time-line

    between the public posting of identified recipients and the ruling of the Divisional Grievance

    Committee.

    Should the individual concerned remain dissatisfied at the perceived exclusion, he/she could take it up

    with the District level Grievance Redress Committee. This will consist of the District Secretary, the

    Assistant District Secretary and two representatives of the Community. At least, one person in the

    committee will have to be a woman and in districts with ethnic diversity, ethnic

    representation will have to be reflected at the committee level. This district level grievance redress

    mechanism will review all contested cases and rule accordingly.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    13/30

    11

    If the individual concerned is still dissatisfied with his/her exclusion he/she may submit his/her

    grievance to the Chief Secretary of the NPC for ruling. The ruling of the Chief Secretary is final.

    Such successful individuals may not necessarily receive their grants at the same time as the rest of

    their village. Instead, they will receive their grants subsequent to the ruling of the Chief Secretary,

    which may occur at a time subsequent to the beginning of the construction program in their village.

    The continuous social impact assessment will offer an added opportunity for those villagers with

    unresolved grievances to record their views to a neutral outside consultancy firm, bypassing the

    divisional and district administrations, for possible consideration at the next phase of construction.

    e. Land Ownership Resolution:

    The program will support the engagement of Land Task Forces (LTFs) that will accelerate the

    resolution of routine land ownership issues in program villages including encroachment on

    previously un -alienated State lands, occupation by adult children of un-subdivided land currently

    held in the name of a parent, and property boundary uncertainty.

    For grievances related to land ownership, the public posting of potential beneficiaries before

    finalization of the list will also allow for challenges based on land ownership, even in cases where

    the potential beneficiary has an apparently legitimate land ownership document. For the vast majority

    of lands which are state lands, statutory remedies to such challenges under the Land Development

    Ordinance and Crown Land Ordinance include determinations by the Divisional Secretary and appeal

    to the Provincial Land Commissioner. As with other grievances, attempts to settle such disputes at

    the community level through the VRCs and GSN Officers will first be explored. Where the grievance

    persists and, especially in disputes over private lands where the parties may wish to avoid the lengthy

    and costly court procedures, the appeal facility of the District Land Tribunals will be available. Each

    Tribunal will comprise three members reflective of the composition of the District, appointed by the

    Chief Secretary NPC on recommendation of the District Secretary.

    f. Environmental Clearance

    Subsequent to village selection, an environmental officer at the district or divisional level will screen

    that village for potential environmental impacts using a rapid assessment based on a questionnaire.

    The questionnaire (which has been designed and fine-tuned by NEHRP) will capture site-specific

    information to determine the type and degree of environmental risks associated with the program in

    the given area. In the event that significant environmental issues are identified, further analysis,

    through a village specific EIA, will be recommended. This EIA will include an Environmental

    Management Plan (EMP) that will specify measures to mitigate the identified impacts. Clearance will

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    14/30

    12

    be granted based on the findings of the village specific EIA and subject to the implementation of the

    recommended mitigatory measure/s spelt out in the EMP. In the event that no significant

    environmental issues are identified, environmental clearance will be granted on completion of the

    rapid assessment with or without subjection to the implementation of certain mitigatory conditions,

    as the case may be.

    g. The Construction Process

    Owner driven construction process

    In Owner Driven Construction programme, beneficiaries will plan out their housing requirement, draw

    the house plan with the support of the implementing unit or select suitable house plan from the

    implementing unit sample plans, construct on their own without deviating the housing construction

    standard and the project minimum requirement. The implementing agency will assist and ensure that

    the beneficiaries reconstruct a quality house and monitor the progress closely. The third party

    Independent Technical Audit Consultants will ensure quality construction in addition to the

    implementing unit.

    To mitigate the risks of environmentally unsustainable resource extraction, inflation and supply

    constraints the district/divisional administrative units will facilitate the supply of construction

    material in bulk for selected beneficiaries across a division. The beneficiary will however have a

    choice in opting into the bulk procurement system. The bulk procurement system is expected to

    function in the following way:

    The District/Divisional administrative units prepare a resource requirement plan based on materialneeds per district over the period of implementation based on existing phasing and grant apportioning

    plans, and on prices for a particular phase in particular districts;

    The District/Divisions begin discussion with relevant organizations such as the District Chambersof Commerce, the Multi-Purpose Cooperative Societies, on the supply of such materials from

    authorized sources. Arrangements will be made to establish bulk supply stations in each district to

    facilitate this process.

    Subsequent to the selection of beneficiaries, they be given 1-2 weeks to decide if they will opt for

    the bulk procurement/buyer society method;

    The District/Division subsequently assists the beneficiaries, either through VRC, or individually,to engage with the supplier for timely delivery of materials.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    15/30

    13

    h. Construction Supervision and Monitoring

    Monitoring of construction (i.e. outputs) and impacts will occur through several mechanisms:

    A continuous social impact assessment will monitor impact, outcome and outputs of the programusing quantitative and qualitative methodologies. It will also include a community social audit of the

    process of beneficiary selection, construction at each stage and other aspects of implementation.

    District and divisional secretaries will submit technical audits on, amongst others, number ofgrants disbursed and number of houses constructed in a phased manner, number of grievances per

    village, number of resolved grievances per village and technical quality of construction. Engineers at

    the Divisional Secretariat will certify the physical progress in civil works to authorize the release of

    funds at each stage.

    Continuous environmental monitoring will be conducted by the District/Divisional levelenvironmental officers of the Central Environmental Authority in order to ensure compliance with

    conditions based on which clearance has been granted.

    A third party technical audit of civil works will also be carried out by a consulting firm. Thisaudit will include monitoring of technical engineering standards, and number of houses

    constructed in a phased manner.

    i. Timing and PhasingThe program timing per activity is depicted in the table below. Note that the activities may run

    concurrently to each other.

    TABLE : 3.3 - Time Taken Per Activity

    Time Taken Activity

    9 months Land Redres Process ( Total Process)

    1 month Program familiarization campaign (Each village)

    2,3 months Beneficiary Selection Process (Each Village)

    6 months Construction (Individual Beneficiaries)

    The program will be completed within four years and will be divided into four phases. The notional

    number of targeted beneficiaries in each phase is depicted in the table below and was calculated using

    the percentage of damaged houses in each district

    TABLE : 3.4 - Project Number of Houses Constructed Per District/Per Phase

    District Phase 1 Phase 2 Phase 3 Phase 4 TOTALS

    Jaffna 2000 2175 2175 1450 7,800

    Kilinochchi 3000 5100 5100 3400 16,600

    Mullaithivu 2500 3750 3750 2500 12,500

    Mannar 1250 1988 1988 1325 6,550

    Vavuniya 1250 1987 1987 1325 6,550

    10,000 15,000 15,000 10,000 50,000

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    16/30

    14

    The total housing caseload of the program has been phased into approximately 000 units in year 1, 10,000

    for year 2, 16,000 for year 3 and 16,000 for year 4. This total caseload, including the approximate

    provision for land-related redress cases, will be allocated to each district based on the proportion of

    damaged houses.

    The Programme has planned to begin the village profiling and selection process in the last quarter of

    2010, preferably in November 2010. The land related grievance redress mechanism and regularization

    process will begin soon and these activities will be undertaken in parallel. The village profiling with

    layers of information such as damaged houses, number of displaced population and returnees, extent of

    landmine clearance, vulnerability and ethnicity will be mapped in each district. Villages having the

    highest scores will be selected in each district. Since village characteristics related to number of

    returnees, vulnerability, landmine clearance and ethnic composition of population change over a period of

    time, the profile exercise and mapping will be updated for each district at the beginning of the phase. A

    three-month period earmarked for conducting the damage assessment and social verification survey for

    the villages selected for the first phase will begin soon after the completion of village selection. The same

    survey will be carried out for the selected villages at the beginning of each phase.

    j. Project Cycle and Phasing Roll Over Strategy

    TABLE No. 3.5

    Project Activity Phasing

    Project Activities Year 1 Year 2 Year 3 Year 4 Remarks

    Village Profile Mapping The village

    and Selection profile will be

    updatedin

    each phase

    Housing Damage Undertakein

    Assessment and Social each phase

    Verification

    Resolution of Project Continuesfor

    Related Land Issues 8 to 9 Months

    Grievance Redress Process Continuous

    Housing Reconstruction Continuous

    3.2 Capacity Building and Monitoring:

    The programme requires acomprehensive technical assistance program to upgrade the existing

    implementation capacity of the following subcomponents:

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    17/30

    15

    Land Dispute Resolution pertaining to the housing reconstruction Skills Training for Construction Technical Assistance (TA) for Management Information Systems Continuous Social Impact Assessment Follow-up Environmental Impact Assessment Technical Audit of Construction

    (Note: The last three are also monitoring functions)

    a. Land Ownership Resolution and Grievance Processes :

    The program will have to support the engagement of Provincial Land Commissioners Office to

    strengthen its capacity.

    b. Skills-training for Construction:

    Skill training will be conducted in three stages.

    a. Skill Training for the Locally available Youthsb. Skill Training for the traditional construction workersc. Skill Training for the beneficiariesa. There is a shortage of construction labor in the North. At least,2000 skilled labourers to be trained

    during the programme period. This will decrease the costs of construction in the long run. It is

    estimated that one third of the estimated cost for the construction of a houses goes towards labor

    due to the scarcity of skilled labor which is often imported from the South.

    Training courses will be held locally in each district, each site training 20-60 skilled workers such as

    masons or carpenters at a time, depending on the capacity of the training venues. Participants will be

    recruited from that district in proportion to the extent of housing damage in that district. The number of

    participants per districts will be in proportion to the amount of houses constructed per district (Table 2.5)

    b. Considerable number of traditional construction workers are available locally, who do not know thelow cost and modern construction technologies, witch is most applicable for the housing

    construction. The Implementing unit will train those traditional construction workers in modern

    construction technologies which could be utilized for this programme effectively. The programmes

    will be shorter, probably 2 to 3 days training camp.

    c. Since beneficiaries reconstruct their houses on their own, they need short training in constructionmanagement, beneficiaries contribution, materials procurement, materials preserving and

    minimization of wastages. So, the implementing unit will train in three stages probably before the

    construction of foundation, roofing and finishing. The programme will be short and each may be one

    day.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    18/30

    16

    e. Technical Assistance for Program Implementation:

    This includes the following five activities:

    i.Communication Strategy:

    The programme needs the development and implementation of an information dissemination campaign,

    its materials, and subsequent implementation. The objective is to increase the transparency of the

    program. The communication strategy will cover, amongst others, topics such as the purpose of housing

    damage assessment and social verification survey, criteria for determining fully and partly damaged

    houses, beneficiary eligibility conditions, financial entitlement, process of financial disbursement and

    proposed opportunities for redressing their grievances. The targeted audience for these service include

    Village Rehabilitation Committees, Beneficiaries, and the general public. The communications campaign

    will be done by the project staff.

    ii. Continuous Social Impact Assessment

    This programme will arrange for a Continuous Social Impact Assessment (CSIA). The CSIA will

    facilitate the articulation of community perceptions, grievances and feedback vis--vis the selection of

    villages, the identification of beneficiaries and the mobilization of resources.

    The continuous SIA will help monitor the social dimensions of the programme and flag potential

    reputational risks. Through direct interaction with the beneficiary communities it will carry out an

    independent evaluation of the implementation of the social safeguards framework and equitable

    distribution of program benefits. The essence of the continuous SIA study is that it will gauge the impact

    of the program and help the programme to undertake necessary mitigation measures against the negative

    impacts. It will help incorporate measures of social soundness, inclusion and equity in the program.

    iii. Follow-up Environmental Impact Assessment

    This component will ensure proper management of the environmental dimensions of the program, as

    explained in previous sections of the report. It will not only identify measures to bring in environmental

    sustainability to the program but also identify opportunities to gain economic benefits through use of

    local raw material without causing detrimental effects on the environment.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    19/30

    17

    iv. Technical Audit of Civil Works

    The component will develop technical standards for the constructed houses and finance a technical audit

    to ensure that construction complies with the developed standards. The activity will audit approximately

    5% sample of all beneficiaries and will cover all beneficiary villages. The audit will be carried out during

    the course of construction and will include an audit of the quality of construction materials, and

    construction at each step of the staged construction process. The reports of this construction audit will be

    submitted to the Monitoring Committees. The activity will be carried out during the construction phases

    of each of the construction period.

    v. Technical Assistance for Management Information System:

    The sub-component will assist for the establishment of an MIS. It is important that the administration

    units (NEHRU, DPUs, and Divisional administration units) under this program establish an effective and

    user friendly management information system (MIS) at the start of the program in order to record and

    monitor the information related to program administration and implementation experience. The MIS

    should include detailed base line data on both operational aspects of the program (number of

    beneficiaries, information on their economic and social conditions, construction progress, capacity

    building/training programs, human and material resources, environmental issues, land disputes, and other

    relevant data) as well as financial aspects of the program (funds allocation, commitment,

    disbursements, pipeline of households for construction phases, etc.). These data will be collected by

    district officers at the village levels and will be monitored and updated regularly during the program

    implementation phases. In order to be able to carry out an ex-post social and economic impact

    assessment of the program during the mid-term review and at the end of the program, it would be

    important to monitor the operational aspects of the program (on sample basis) 9 months after the houses

    are built.

    3.3 Program Management

    The nature of the housing reconstruction program, its scale, the coverage area, and the condition of

    beneficiaries require that an effective program management and monitoring system to be in place in order

    to ensure smooth and successful implementation of the program. The program management and

    monitoring will be carried out at the Provincial, Division, and Districts levels.

    a. Program Management at the Provincial levelstaff arrangement to be discussedb. Program supervision by Districts and Divisional Secretariatto be discussed

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    20/30

    18

    CHAPTER4 PROGRAMIMPLEMENTATIONPROCESSANDROLESOFAGENCIES

    4.1 OVERVIEW

    The overall responsibility of the project will be with the Ministry of Economic Development,

    Government of Sri Lanka. While the Ministry of ED will review the project from time to time, it is

    primarily responsible for the coordination of the project with ongoing and future development programs

    in the North . The Northern Provincial Council (NPC) will be fully responsible for the implementation of

    the Program.

    NEHRU will be the main program implementation agency of the NPC. The decentralized implementation

    arrangements designed by the Project will entail a great deal of institutional coordination between

    NEHRP, District and Divisional Administrations as well as with other agencies. The broad institutional

    arrangements and responsibilities of agencies involved in the various components of the program are

    discussed below:

    4.2 DECISION MAKING PROCESS

    The decision making process in the program management is done at various levels. The executing agency

    of the Project is Ministry of ED. The National Steering Committee established at the Ministry of ED will

    coordinate the project activities and action plans at national level. The Secretary of Ministry of

    ED/Hon.Governer of EPC chairs the National Steering Committee. This national steering committee will

    include senior officials representing relevant infrastructure line agencies at the Center, province and the

    District Secretaries of the North. Included here would be the Central Ministry of Housing, the provincialMinistry , the National Housing Development Authority.

    At the provincial level, there will be a Provincial Program Coordination Committee (PPCC) to oversee

    the programme implementation and address bottlenecks. This will meet once in two months and will be

    chaired by the Chief Secretary of the North East Provincial Council. It will consist of all District

    Secretaries, Secretary to the Provincial Ministry of Rehabilitation, Deputy Chief Secretary/Planning,

    Provincial Director of Buildings Department, representatives of the Central Ministry of ED,and

    programme officials.

    The programme day to day implementation arrangements consists of three integrated but parallel

    structures. The PMU, the District Program Units and their Divisional counterparts will implement the

    technical aspects of the program. Divisional and District Grievance Redress Committees form the second

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    21/30

    19

    set of institutional structures. Program monitoring and supervision will occur through a parallel structure

    at National, Provincial, District and Divisional levels, together with a third party technical audit of

    construction, the continuous social impact assessment, and the follow-up environmental impact

    assessment.

    At the district level, there will be a District Coordinating and Monitoring Committee (DCMC). This too

    will meet once a month. The DCMC will consist of the District Secretary, Addl. G.A. or ADS, all

    Divisional Secretaries, the District Engineer, Senior Divisional Environmental Officer, Deputy Project

    Director,and Project Director/District Rehabilitation. Provision will be made to ensure that at least one

    woman is on the committee.

    At the divisional level, there will be a Divisional Monitoring Committee that will meet once a month.

    The Divisional Monitoring Committee will consist of the Divisional Secretary, the Divisional Technical

    Officer/Engineer, Divisional Environmental Officer, Divisional Planning Officer, and VRC chairpersons

    in that division. Provision will be made to ensure that at least one woman is on the Committee. The

    divisional level progress reports will be forwarded to the District Secretary each month.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    22/30

    20

    CHAPTER 5:OPERATIONALCOST

    The Indian grant will cover the total cost of construction of houses. The operational cost will be met by the

    GOSL. The following operational cost will be provided from the consolidated fund.

    Total Cost of the Project (In Sri Lankan Rupees)

    a. Housingi. Cluster Programme 1,000 x 0.6 mn = 600.00 mnii. Housing Repair - 10,000 x 0.2 mn = 2,000.00 mniii. Normal programme - 40,000 x 0.6 mn = 24,000.00 mn

    Sub Total = 26,600.00 mn

    b. Skill Training (2000 youths+ 2000 traditional Skill Workers) = 100.00 mnc.

    *Incremental expenditure (4%) = 798.00 mn

    Grant total = 27, 498.00 mn

    *Incremental expenditure

    Third Party Independent Technical Audit Consultancy Service

    Independent Social Impact Assessment Consultancy service

    Individual Consultants

    Equipment

    Vehicles

    Staff

    Day to day expenditure

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    23/30

    21

    CHAPTER6 OPERATIONALINSTRUCTIONS

    Housing Reconstruction Programme in the Northern P rovince under the assistance

    from the Government of India.

    Minutes of the Meeting

    Venue : District Secretariat, Kilinochchi

    Date : 13.09.2010 Time : 3.00pm

    Attendance

    1. Mr.A.Sivaswamy ChiefSecretary,NP2. Mr.S.Rangarajah SecretarytotheGovernor,NP3. Mr.R.Umakanthan DeputyChiefSecretary,Planning,NP4. Mr.A.E.S.Rajendra Secretary,M/Infrastructure,NP5. Mr.S.M.Croos ProgrammeDirector,NECCDEP6. Mr.N.Vethanayagam GovernmentAgent,Mullaitivu7. Mr.R.Ketheeswaran GovernmentAgent,Kilinochchi8. Mr.S.Mohanathan Addl.Govt.Agent, Mannar9. Mr.N.Thiruganasampanthar Addl.Govt.Agent, Vavuniya

    10.Mr.V.Sampasivam DeputyProjectDirector,NEHRP,Jaffna11.Mr.J.X.Selvanayagam Asst.ProjectDirector,NEHRP12.Mr.P.Thayananda Commissioner.D/LandAdm13.Mr.S.Achuthan R/ACLG,Vavuniya14.Mr.T.Mugunthan Asst.Govt.Agent, Palai15.Mr.K.S.Vasanthakumar Asst.Govt.Agent, Poonagari

    Hon.Governorpresidedoverthemeeting.Attheoutsetheexplainedthat,arrangementshavetobemade

    for reconstruction and repairs of fully and partly damage housing for resettlements families in the

    NorthernProvinceunderfinancialassistancebytheGovernmentofIndia.

    Hefurtherexplainedthat,theIndianassistancewouldprovidetheresettledIDPfamiliesafterMay2009in

    theNorthwhomeetsacceptedcriteriawithimprovedandaffordablehousingunits.

    IndianGovernmentwouldfacilitatethereconstructionof50,000housesintheNorthernProvincethrough

    theprovisionofhousinggrants.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    24/30

    22

    1. ImplementationArrangementsTheprogrammewillbeimplementedintwostages.

    Constructionof1,000clusterhousesinrelocatedareasonturnbybasis. Constructionof50,000housesunderhomeownerdrivenmodel.Thiswillbeimplemented

    intwostages.

    (a)Repairsof10,000housesinbothJaffnaandVannielectorateaspilotproject.(b)Reconstructionof40,000newhouses.

    Accept for the 1,000 houses under directed system all the other houses following the NEHRP

    model.ForthispurposePTF&IndianHighCommissionhasagreedprojectdesignon6th

    Sep.2010.

    Detailsofselectionofbeneficiaries,implementationsystem,etchavebeenexplainedinthisagreed

    document.CopingwillbedistributedtoalltheGovernmentAgents.

    2. Constructionof1,000cluster housesinrelocatedareaa.Selectionofbeneficiaries

    Underthisstage, landlessIDPswillbe identifiedandberesettled innewly identifiedhabitableareas.

    Themost vulnerable groups will be given priority among the land less under this programme as

    indicatedbelow.

    (a)Widows(b)Singleheadedhouseholds(c) Differentlyable(d)

    Infirm

    as

    result

    of

    old

    age

    (e) Infirmassresultofinjury(f) Familiesbelowthepovertyline

    Thesecriteriaaremoreexplainedintheagreedprojectdesigndocument.

    Government Agents have already identified the beneficiaries and land for housing scheme . The

    Districtwiseapportionmentsfor1050clusterhousesasfollows:

    Jaffna 150

    Kilinochchi 326

    Mullaitivu 200

    Mannar 175

    Vavuniya 200

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    25/30

    23

    b.RoleofNEHRP

    NEHRPwillbethe implementingagencycoordinatingtheprogramme.The implementationsystemwill

    beadjustedtoaccommodatetheimplementation&monitoringconcernoftheIndianGovernment.The

    routinetechnicalsupervision,certificationforpaymentetc.willbecarriedoutbyNEHRP.Inthecaseof

    directexecutionof1,000housesNEHRPwillappropriatelyplacemonitoringsystemconformingtothe

    conditioninthecontractbetweenIndianGovernmentandthecontractfirm.

    3. Repairsof10,000housesinbothJaffnaandVannielectorateDistricts.Hon.Governor mentioned that, repairs of 10,000 partly damaged houses will be undertaken

    immediately.Electoratewiseapportionmentwillbeasfollows.

    Jaffnaelectorate

    1. JaffnaDistrict 2000houses2. Kilinochchi 3000houses

    Subtotal 5000Vanni

    electorate

    1.Mullaitivu 2500houses2.Vavuniya 1250houses3.Mannar 1250houses

    Subtotal 5000Beneficiarieswillbeselectedaccordingtothecriteriaexplainedintheprojectdesign

    agreedon 6th

    Sep.2010withIndianHighCommission.

    4.Releaseoffundsforrepair

    AsumofRs.200,000wouldprovidefortherepairsin3stagesasindicatedbelow.

    Stage 1 50% of cash (Rs.100,000) will deposit to the beneficiaries bank account before pre

    commencementofwork.

    Stage2 Another40%(Rs.80,000)willprovideatthe1ststagecompletion.

    Stage3Balance10%(Rs.20,000)willprovideatthefinalstage.

    5.Listof

    beneficiaries

    WiththecurrentsystemofNEHRPselectionofbeneficiaries,prioritylistofbeneficiaries

    shouldbesubmittedbefore15th

    October2010.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    26/30

    24

    6.MonitoringSystem

    Hon.Governorexplainedthat,therewilllbethreelevelmonitoringduringthe

    constructionwork.

    NEHRPmonitoringsystem ProvincialcouncilmonitoringsystembyateamConsistingofChiefSecretary,Secretarytothe

    GovernorandSecretary,MinistryofInfrastructure

    DistrictmonitoringteamteamundertheleadershipofrelevantDistrictSecretaries.7.RegulatingMaterialSupply

    GovernmentAgentsshouldmakelocalarrangementaccordingtotheDistrictsituationto

    ensurequalitybuildingmaterialsaresuppliedatlowercost.Thedistricthousing

    committeemayappropriatelyengagedagenciesincludingCooperativesocietiesto

    providethematerialsatlocallevel.

    8.Constructionof40,000NewHouses

    Constructionof40,000newhouseswillbestaredaftertherepairsof10,000housingunit

    aspilot.Detailswillbeworkoutlater.

    9.OperationInstruction.

    Hon.Governor

    directed

    that

    detail

    operation

    instruction

    to

    be

    sent

    out

    by

    the

    NEHRP.

    The

    followingimmediateoperationalarrangementswereagreed.

    i)Prioritybeneficiariesselection

    SincethedemandforrepairofnewhousesisexpectedtowinmoreusingNEHRPapplicationform(

    asmodifiedtothisproject)willbeobtainfromeligiblebeneficiaries.Applicationformwasmodified

    and handed over to Government Agents at the meeting. On the basis of declaration by

    beneficiariesinitial

    assessment

    will

    be

    done

    by

    the

    team

    of

    3members,

    one

    rep.

    from

    Divisional

    Secretary,onememberofVRCandTechnicalOfficerwillrecommendthequantumofassistance.In

    the caseofhouses theassessmentofwhichmaybedifficultanEngineersofNEHRPpersonally

    inspectthehousesandrecommendquantumofassistance.Forthispurposea long listofeligible

    beneficiarieswillbe suppliedbyDivisional Secretaries to the team.Basedon the detailsof the

    assessmentformusingtheypointssystemexplained inthepaymentdocument.Thebeneficiaries

    willberankedandprioritize.TheprioritizebeneficiarieslistshouldbesenttothePTFthroughthe

    Hon.Governorbefore15th

    October2010.

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    27/30

    25

    ii) TechnicalOfficersandEngineers

    TheNEHRPwill assign 5TechnicalOfficers toeachdistrict to engage in thedamageestimation

    work.InadditionNEHRPwillhire5Engineersforshorttermtoengageinthistask.

    Itwaspointedoutatleast3experienceengineerswillbeneededtocertifythepaymentvouchers.

    ItwassuggestedinviewtheshortageofEngineerstoinducttheservicesofEngineeringstudentsto

    satthefinalexamwhocouldbequicklytrainedinconsultationwithPeredeniyaUniversity.

    iii)Documentation

    FollowingtheNEHRPprinciplesindividualcasefilewillbemaintainedinrespectofeachbeneficiary

    fromthestart.

    iv)GrievanceredressessystemAsexperienceinthepastenormousnumberofcomplaintwillbereceivedonrepairsofhouses,the

    GovernmentAgentswererequestedtostrictlyadheretothesystemandmaintainproperrecords

    in respect of all the graveness reported and themanner inwhich theywere shorted out. The

    recordsshouldbeavailableforfutureverification.

    v) Overhead

    TheGovernment

    Agents

    agreed

    to

    meet

    the

    initial

    cost

    of

    stationary

    and

    printing

    of

    forms

    except

    for Kilinochchi and Mullaitivu Districts. Other Districts will print their own assessment forms.

    NEHRPwillprintanddistribute forms toKilinochchiandMullaitivuDistricts.TheChiefSecretary

    wasrequestedtomakearrangementwithintheperiod.IndianHighCommissiontomeettheother

    overheadparticularlythesalariesofEngineers,hiringandmaintenanceofvehicleetc.

    vi) LogisticSince the implementationperiodwillbe thepeak implementationperiodofnormalprogramme.

    Specialattentionhastobepaidandspecificarrangementshouldbemaderegardtomobilityand

    engineeringstaff

    in

    order

    to

    prevent

    set

    back

    in

    the

    NEHRP

    programme

    which

    should

    be

    completed

    beforeDecember2010.

    A.Sivaswamy

    ChiefSecretary

    NorthernProvince

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    28/30

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    29/30

  • 8/8/2019 Final Draft of Project Report on Housing Project under Indian Assistant

    30/30