76
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009 Certification for a Sustainable World FINAL CCBA PROJECT VALIDATION REPORT KASIGAU CORRIDOR REDD PROJECT TAITA TAVETA, KENYA WILDLIFE WORKS CARBON LLC December 22, 2009 Validation Conducted by: Scientific Certification Systems Greenhouse Gas Verification Program 2200 Powell St. #725, Emeryville, CA 94608 USA Tel. 510.236.9016 • (Fax) 510.236.8598 • www.scscertified.com

FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

Certification for a Sustainable World ™

FINAL CCBA PROJECT VALIDATION REPORT

KASIGAU CORRIDOR REDD PROJECT

TAITA TAVETA, KENYA

WILDLIFE WORKS CARBON LLC

December 22, 2009

Validation Conducted by:

Scientific Certification Systems

Greenhouse Gas Verification Program

2200 Powell St. #725, Emeryville, CA 94608 USA

Tel. 510.236.9016 • (Fax) 510.236.8598 • www.scscertified.com

Page 2: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

Table of Contents

1.0 Introduction ......................................................................................................................... 1

1.1. Contact Information ........................................................................................................ 1

1.2. Objective .......................................................................................................................... 2

1.3. Scope and Criteria ........................................................................................................... 2

1.4. Project Description .......................................................................................................... 2

1.5. Summary of Validation Conclusion ................................................................................. 3

2.0 Methodology ....................................................................................................................... 3

2.1. CCB Standards ................................................................... Error! Bookmark not defined.

2.2. Auditor Qualifications ...................................................................................................... 3

2.3. Audit Process ................................................................................................................... 4

3.0 Stakeholder Comments ....................................................................................................... 5

3.1. CCB Validation Findings ................................................................................................... 5

3.2. General Section ............................................................................................................... 6

3.2.1. G1 – Original Conditions in the Project Area ........................................................... 6

3.2.2. G2 – Baseline Projections ...................................................................................... 12

3.2.3. G3 – Project Design and Goals .............................................................................. 15

3.2.4. G4 – Management Capacity and Best Practices .................................................... 24

3.2.5. G5 – Legal Status and Property Rights .................................................................. 32

3.3. Climate Section .............................................................................................................. 36

3.3.1. CL1 – Net Positive Climate Impacts ....................................................................... 36

3.3.2. CL2 – Offsite Climate Impacts (‘Leakage’) ............................................................. 39

3.3.3. CL3 – Climate Impact Monitoring .......................................................................... 42

3.4. Community Section ....................................................................................................... 43

3.4.1. CM1 – Net Positive Community Impacts ............................................................... 43

3.4.2. CM2 – Offsite Stakeholder Impacts ....................................................................... 45

3.4.3. CM3 – Community Impact Monitoring .................................................................. 48

3.5. Biodiversity Section ....................................................................................................... 50

3.5.1. B1 – Net Positive Biodiversity Impacts .................................................................. 50

3.5.2. B2 – Offsite Biodiversity Impacts ........................................................................... 53

3.5.3. B3 – Biodiversity Impact Monitoring ..................................................................... 55

3.6. Gold Level Section ......................................................................................................... 57

3.6.1. GL1 – Climate Change Adaptation Benefits .......................................................... 57

3.6.2. GL2 – Exceptional Community Benefits ................................................................ 59

3.6.3. GL3 – Exceptional Biodiversity Benefits ................................................................ 61

4.0 CCB Validation Conclusion ................................................................................................. 62

Appendix A CCBA Compliance Checklist

Appendix B Stakeholder Comments

Page 3: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

Table of Findings

NCR Number 1 of 19 for October 20, 2009 ..................................................................................... 7

NCR Number 19 of 19 for October 20, 2009 ................................................................................... 8

NIR Number 1 of 5 for October 20, 2009 ...................................................................................... 10

NCR Number 2 of 19 for October 20, 2009 ................................................................................... 11

OFI Number 1 of 4 for October 20, 2009 ...................................................................................... 14

NIR Number 2 of 5 for October 20, 2009 ...................................................................................... 16

NCR Number 3 of 19 for October 20, 2009 ................................................................................... 18

OFI Number 2 of 4 for October 20, 2009 ...................................................................................... 18

NCR Number 4 of 19 for October 20, 2009 ................................................................................... 20

NCR Number 1 of 1 for November 12, 2009 ................................................................................. 20

NCR Number 5 of 19 for October 20, 2009 ................................................................................... 23

NCR Number 6 of 19 for October 20, 2009 ................................................................................... 23

NCR Number 7 of 19 for October 20, 2009 ................................................................................... 25

NCR Number 8 of 19 for October 20, 2009 ................................................................................... 26

NCR Number 9 of 19 for October 20, 2009 ................................................................................... 27

OFI Number 3 of 4 for October 20, 2009 ...................................................................................... 28

OFI Number 1 of 1 for November 12, 2009 ................................................................................... 29

NCR Number 10 of 19 for October 20, 2009 ................................................................................. 31

NCR Number 11 of 19 for October 20, 2009 ................................................................................. 31

NIR Number 3 of 5 for October 20, 2009 ...................................................................................... 33

NIR Number 4 of 5 for October 20, 2009 ...................................................................................... 34

NCR Number 12 of 19 for October 20, 2009 ................................................................................. 38

NCR Number 13 of 19 for October 20, 2009 ................................................................................. 40

NCR Number 14 of 19 for October 20, 2009 ................................................................................. 43

NCR Number 18 of 19 for October 20, 2009 ................................................................................. 45

NCR Number 15 of 19 for October 20, 2009 ................................................................................. 46

NCR Number 16 of 19 for October 20, 2009 ................................................................................. 49

NCR Number 17 of 19 for October 20, 2009 ................................................................................. 52

OFI Number 4 of 4 for October 20, 2009 ...................................................................................... 55

NIR Number 5 of 5 for October 20, 2009 ...................................................................................... 58

Page 4: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

1.0 Introduction

This report presents the findings of an audit conducted by Sc

validate the claim made by Wildlife Works Carbon LLC

to the Climate, Community and Biodiversity Project Design Standards (

Certification Systems (SCS) has been accredited by the Climate, Community & Biodiversity Alliance

(CCBA) to perform such validation audits.

1.1. Contact Information

Project Developer contact information

Mike Korchinsky

Wildlife Works Carbon LLC

425 Market Street, 26th Floor

San Francisco, CA 94105

Tel. 415.332.8081

mike [at] wildlifeworks.com

Scientific Certification Systems contact

Todd Frank, Program Manager, GHG Verification Services

Scientific Certification Systems

2200 Powell Street, No. 725

Emeryville, CA 94608 USA

Tel. 510.236.9016

tfrank [at] scscertified.com

Auditor contact information:

Kyle Holland, Verification Forester, GHG

Scientific Certification Systems

2200 Powell Street, No. 725

Emeryville, CA 94608 USA

Tel. 510.236.9015

kholland [at] scscertified.com

Alex Obara, Kenyan Forestry

alexobara [at] hotmail.com

Client contact information:

Mike Korchinsky

Wildlife Works Carbon LLC

425 Market Street, 26th Floor

San Francisco, CA 94105

Tel. 415.332.8081

mike [at] wildlifeworks.com

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

1

This report presents the findings of an audit conducted by Scientific Certification Systems

Wildlife Works Carbon LLC that the Kasigau Corridor REDD

to the Climate, Community and Biodiversity Project Design Standards (Second Edition).

has been accredited by the Climate, Community & Biodiversity Alliance

audits.

information:

Floor

mike [at] wildlifeworks.com

contact information:

Todd Frank, Program Manager, GHG Verification Services

ific Certification Systems

2200 Powell Street, No. 725

Forester, GHG Verification Services

Scientific Certification Systems

2200 Powell Street, No. 725

ified.com

Forestry Specialist

[at] hotmail.com

Floor

mike [at] wildlifeworks.com

ientific Certification Systems (SCS), to

Kasigau Corridor REDD Project conforms

Edition). Scientific

has been accredited by the Climate, Community & Biodiversity Alliance

Page 5: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

1.2. Objective

The validation objective is an independent assessment by

all criteria defined by the Climate Biodiversity and Community Alliance (CCBA). Validation

concludes with an opinion of whether the project activi

whether the project should be submitted for registration with CCBA. The ultimate decision on the

registration of a proposed project rests with CCBA.

1.3. Scope and Criteria

The project was assessed against the CCB Standards Second Edition to determine which of the fourteen

required and three optional CCB Standards criteria the project satisfies. An “Approved” project is one

which satisfies all fourteen of the required CCB Standards criteria

The scope of services described in this

presented at the time of inception of project

Information Requests (NIRs) or Non

these findings by the Project Proponent. As necessary based on the

Auditor issued additional findings.

1.4. Project Description

The Kasigau Corridor REDD Project (“the p

Kenya, approximately two hours northwest of Mombasa, Kenya. The project

and Tsavo West National Parks and functions as a critical wildlife corridor between the two parks. T

are several communities located near the project area in the project zone. The project area is primarily

low density forestland, shrubland and grassland savannah.

This land is a private leasehold estate

Ltd. The majority shareholder of Rukinga Ranching Co

There are 46 shareholders of Rukinga Ranching Co

international was established by a princip

Carbon LLC. Wildlife Works Inc. is an export processor of consumer goods to retail markets in Europe

and the United States. Wildlife Works Inc. supports the conservation of wilderness habitats, t

creation of jobs and the construction of schools.

easement from Rukinga Ranching Company

easement effectively transferred all carbon and biodiversity rights

Wildlife Works Inc. Wildlife Works Inc. and Wildlife Works Carbon L

project activities and collectively these e

of project activities in this report.

Major project activities in the project area include the protection of the wildlife corridor, wildlife habitat

and carbon stocks. Major project

1 See http://www.wildlifeworks.com/mission/mission.html

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

2

objective is an independent assessment by SCS of the proposed project activities

defined by the Climate Biodiversity and Community Alliance (CCBA). Validation

on of whether the project activities are compliant with the CCB standards and

he project should be submitted for registration with CCBA. The ultimate decision on the

registration of a proposed project rests with CCBA.

assessed against the CCB Standards Second Edition to determine which of the fourteen

required and three optional CCB Standards criteria the project satisfies. An “Approved” project is one

of the required CCB Standards criteria.

described in this report encompasses an analysis of data and calculations as

presented at the time of inception of project validation. The SCS Lead Auditor issued

) or Non-Conformity Reports (NCRs), as needed, and analyze

these findings by the Project Proponent. As necessary based on the adequacy of responses, the Lead

gau Corridor REDD Project (“the project”) is located in Coast Province, Taita Taveta District

Kenya, approximately two hours northwest of Mombasa, Kenya. The project area is between Tsa

and Tsavo West National Parks and functions as a critical wildlife corridor between the two parks. T

are several communities located near the project area in the project zone. The project area is primarily

, shrubland and grassland savannah.

estate given by the Government of Kenya to Rukinga Ranching

majority shareholder of Rukinga Ranching Company is BenBo International, an offshore trust.

Rukinga Ranching Company, including BenBo International.

a principal investor of both Wildlife Works Inc. and Wildlif

Wildlife Works Inc. is an export processor of consumer goods to retail markets in Europe

and the United States. Wildlife Works Inc. supports the conservation of wilderness habitats, t

creation of jobs and the construction of schools.1 Wildlife Works Inc. was granted a conservation

inga Ranching Company in 2009 after the project start date of January 1, 2006

all carbon and biodiversity rights from Rukinga Ranching Company to

. Wildlife Works Inc. and Wildlife Works Carbon LLC have initiated or will

and collectively these entities are referred to as “the project proponent

roject area include the protection of the wildlife corridor, wildlife habitat

and carbon stocks. Major project activities in the project zone relate to the surrounding communities

http://www.wildlifeworks.com/mission/mission.html

of the proposed project activities against

defined by the Climate Biodiversity and Community Alliance (CCBA). Validation by SCS

compliant with the CCB standards and

he project should be submitted for registration with CCBA. The ultimate decision on the

assessed against the CCB Standards Second Edition to determine which of the fourteen

required and three optional CCB Standards criteria the project satisfies. An “Approved” project is one

analysis of data and calculations as

one or more New

), as needed, and analyzed responses to

of responses, the Lead

Coast Province, Taita Taveta District,

area is between Tsavo East

and Tsavo West National Parks and functions as a critical wildlife corridor between the two parks. There

are several communities located near the project area in the project zone. The project area is primarily

Ranching Company

nternational, an offshore trust.

, including BenBo International. BenBo

al investor of both Wildlife Works Inc. and Wildlife Works

Wildlife Works Inc. is an export processor of consumer goods to retail markets in Europe

and the United States. Wildlife Works Inc. supports the conservation of wilderness habitats, the

was granted a conservation

January 1, 2006. This

from Rukinga Ranching Company to

have initiated or will initiate the

roponent” in the context

roject area include the protection of the wildlife corridor, wildlife habitat

e surrounding communities

Page 6: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

and include greenhouse-based tree production, agricultural outreach, employment and the construction

of schools. The project lifetime and crediting period are 20 years.

1.5. Summary of Validation

Following completion of SCS’s duly

Corridor REDD Project conforms

Standards (Second Edition) at the Gold

the audit and were subsequently closed; in total, there were

Information Requests (NIRs) and 5 Opportunities for Improvement (OFIs)

2.0 Methodology

The audit commenced on September 25

Design Document (PDD). The site

Wildlife Works management, employees

members. Field tours were conducted of the project area and project zone. Following the site visit

upon further review of the collected evidence

issued. Audit findings were issued as NCRs, NIRs and OFIs. The Pro

of time to respond to the issued NCRs and NIRs. Upon the close of this period or the receipt of

satisfactory responses, the draft report was issued on December 21

allowed to comment on the draft report

comments made by the project proponent were considered but not all were incorporated into the final

report.

2.1. CCB Standards

The Project was validated against

Standards (Second Edition) (“the Standard”

of 4 categories: 1) General (5 criteria

Biodiversity (3 criteria). In addition,

least one of three criteria in the

required criteria and at least one optional

2.2. Auditor Qualifications

Lead Auditor: Kyle Holland, SCS Verification Forester

Mr. Holland is a Certified Forester

and remote sensing. Prior to joinin

Supervisor. Kyle has also worked with the

State of Wisconsin as a specialist in

currently completing his Ph.D. in biometrics and statistics at the Uni

holds a M.S. in biometrics and remote sensing from Berkeley, and

Minnesota and the University of Idaho in forestry and forest engineering, respectively.

professional memberships with the Society of American Foresters, the American Society for

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

3

based tree production, agricultural outreach, employment and the construction

of schools. The project lifetime and crediting period are 20 years.

Validation Conclusion

S’s duly-accredited validation process, it was concluded that T

to the CCBA Climate, Community and Biodiversity

Gold Level (see Appendix A). Findings were made durin

the audit and were subsequently closed; in total, there were 20 Non-Conformity Reports (NCRs)

Opportunities for Improvement (OFIs).

The audit commenced on September 25th with an opening meeting and a desk review

visit occurred the week of October 12th and included meetings with

Wildlife Works management, employees, Rukinga Ranching Company shareholders

ours were conducted of the project area and project zone. Following the site visit

upon further review of the collected evidence, public comments and PDD, several audit findings were

e issued as NCRs, NIRs and OFIs. The Project Proponent was allowed a period

of time to respond to the issued NCRs and NIRs. Upon the close of this period or the receipt of

report was issued on December 21st. The project proponent was

draft report prior to the submission of the final report to CCBA.

comments made by the project proponent were considered but not all were incorporated into the final

was validated against the CCB Climate, Community and Biodiversity Project Design

Edition) (“the Standard”). The Standard requires conformance to 1

criteria), 2) Climate (3 criteria), 3) Community (3

). In addition, applicants achieve a higher level of validation by conforming to at

Gold Level section. Projects with Gold Level status

optional Gold Level criterion of the Standard.

Auditor Qualifications

Lead Auditor: Kyle Holland, SCS Verification Forester

Holland is a Certified Forester (#3770) and biometrician specializing in forest inventory,

. Prior to joining SCS, Kyle worked with the Potlatch Corporation as a Resource

Supervisor. Kyle has also worked with the Chesapeake Bay Program, the State of Maryland and the

specialist in riparian forestry and forest management auditing.

in biometrics and statistics at the University of California, Berkeley. Kyle

holds a M.S. in biometrics and remote sensing from Berkeley, and degrees from the University of

ta and the University of Idaho in forestry and forest engineering, respectively.

professional memberships with the Society of American Foresters, the American Society for

based tree production, agricultural outreach, employment and the construction

ded that The Kasigau

to the CCBA Climate, Community and Biodiversity Project Design

. Findings were made during the course of

onformity Reports (NCRs), 5 New

review of the Project

and included meetings with

Company shareholders and community

ours were conducted of the project area and project zone. Following the site visit and

public comments and PDD, several audit findings were

ject Proponent was allowed a period

of time to respond to the issued NCRs and NIRs. Upon the close of this period or the receipt of

. The project proponent was

submission of the final report to CCBA. All

comments made by the project proponent were considered but not all were incorporated into the final

Climate, Community and Biodiversity Project Design

conformance to 14 criteria in each

Community (3 criteria), and 4)

by conforming to at

Projects with Gold Level status meet the core

(#3770) and biometrician specializing in forest inventory, modeling

worked with the Potlatch Corporation as a Resource

Chesapeake Bay Program, the State of Maryland and the

riparian forestry and forest management auditing. Mr. Holland is

versity of California, Berkeley. Kyle

degrees from the University of

ta and the University of Idaho in forestry and forest engineering, respectively. He also holds

professional memberships with the Society of American Foresters, the American Society for

Page 7: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Photogrammetry and Remote Sensing, the Institute of Mathematical Stati

Environmetrics Society. Mr. Holland

under FSC, CCX, CAR, CCB and VCS.

projects under VCS.

Auditor: Alex Oginga Obara, Kenyan Specialist and SCS Contractor

Mr. Obara is a native of Kenya specializing in forestry and wildlife management.

in Forest and Wildlife Management from the Moi University, Kenya

Biology from the Durell Institute of Conservation and Ecology at the University of Kent

United Kingdom. Alex also holds certificates in Biodiversity Measurement and Monitoring,

Environmental Leadership and Communication Skills from the

has broad experience in forest research, forest biometrics, landscape restoration, resource management

and ecological monitoring obtained from his work with

UNDP, UNIDO, WWF, the World Bank/GEF and Nippon Koei Co., Ltd.

2.3. Audit Process

The audit process included the following

• Opening meeting, introduction and project orientation (via conference call) on September 25

• Desk review of PDD and supplemental documentation including maps, data and models;

• Site visit from October 13th

o Project overview and orientation

o Interviews with Wildlife Works management;

o Interviews with Wildlife Works employees;

o Interviews with Rukinga

o A community meeting;

o Field tours of local communities;

o Interviews with community members;

o Tours of local schools;

o Interviews with local school teachers and administrators;

o Field tours of the project area;

o Tours of facilities and agricultural plantings;

o Closing meeting and presentation of preliminary findings;

• Review of stakeholder comments;

• Review of collected evidence and supporting documentation;

• Issuance of findings on October 2

• Project proponent responses to findings;

• Preparation of draft report;

• Technical review of draft report;

• Comment on draft report by project proponent; and

• Submission of final report to CCBA.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

4

Photogrammetry and Remote Sensing, the Institute of Mathematical Statistics and the International

Mr. Holland has conducted numerous verification and validation activities

under FSC, CCX, CAR, CCB and VCS. Mr. Holland is also an approved AFOLU expert for IFM and REDD

, Kenyan Specialist and SCS Contractor

a native of Kenya specializing in forestry and wildlife management. He holds a B

in Forest and Wildlife Management from the Moi University, Kenya, and a M.Sc. degree in Conserva

Biology from the Durell Institute of Conservation and Ecology at the University of Kent

Alex also holds certificates in Biodiversity Measurement and Monitoring,

Environmental Leadership and Communication Skills from the Smithsonian Institute, Virginia.

has broad experience in forest research, forest biometrics, landscape restoration, resource management

and ecological monitoring obtained from his work with the Masai Mara National Reserve in Kenya,

WWF, the World Bank/GEF and Nippon Koei Co., Ltd.

The audit process included the following timeline of events and activities:

Opening meeting, introduction and project orientation (via conference call) on September 25

and supplemental documentation including maps, data and models;

– October 17th;

Project overview and orientation

Interviews with Wildlife Works management;

Interviews with Wildlife Works employees;

Rukinga Ranching Company shareholders;

A community meeting;

Field tours of local communities;

Interviews with community members;

Tours of local schools;

Interviews with local school teachers and administrators;

Field tours of the project area;

and agricultural plantings;

Closing meeting and presentation of preliminary findings;

Review of stakeholder comments;

Review of collected evidence and supporting documentation;

of findings on October 2nd and November 11th;

nses to findings;

Preparation of draft report;

Technical review of draft report;

Comment on draft report by project proponent; and

Submission of final report to CCBA.

stics and the International

has conducted numerous verification and validation activities

is also an approved AFOLU expert for IFM and REDD

holds a B.Sc .degree

degree in Conservation

Biology from the Durell Institute of Conservation and Ecology at the University of Kent in Canterbury,

Alex also holds certificates in Biodiversity Measurement and Monitoring,

Smithsonian Institute, Virginia. Mr. Obara

has broad experience in forest research, forest biometrics, landscape restoration, resource management

Masai Mara National Reserve in Kenya,

Opening meeting, introduction and project orientation (via conference call) on September 25th;

and supplemental documentation including maps, data and models;

Page 8: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

3.0 Stakeholder Comments

The Project Design Document (PDD) was

comment period extended through

Appendix B).

Written comments were received from the

• James Ruwa, GAFFER HIV/AIDS Project Coordinator

• Kenneth Nyange, Project Manager

• Peterson Msinga Mwatate, Head Teacher

• Renson Dio, Director - Taita Ranching Co. Ltd.

• Engineer C.M Mwakulomba

• Sylvester Izaka, IT & Network support engineer

• Rehema Mwavuo, Volunteer Teacher

• V Wambua Masai, Teacher and Instructor

• Antony Lundi, Voi constituency

• Chief DUNCAN, Marungu Location as addressed to the Manager Wildlife Work

• Briviant Shako – Technical Works

• Pascal Kizaka, Chief of Kasigau Location, Voi/Kenya

• Driscilah M. Ngele, Assistant Chief’s Office

All comments have been addressed by the auditor in this report. General themes included

• Overwhelming support for the project’s

• Support for the protection of wild animals;

• Support for the greenhouse nursery program;

• Support for the school bursary program;

• Support for the construction of

• Recognition of Wildlife Work’s engagement with the

• Acknowledgement of the potential risks to the project area under the without

namely deforestation, conversion to agriculture and charcoal production;

• Appreciation for the intrinsic value of the proje

• Appreciation for employment opportunities offered by Wildlife Works.

3.1. CCB Validation Findings

The evidence and findings presented in this report address

each criterion, the Standard specifies

and issued to the project proponent as

(NIRs) and Opportunities for Improvement (OFIs)

stipulates the deficiency or lack of evidence

indicators. NCRs indicate broad non

project validation while NIRs and OFIs are less material. In the case of a NIR, the finding is to obtain

additional evidence to support the conformance of the project to an indicator. The project proponent

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

5

Stakeholder Comments

The Project Design Document (PDD) was posted on the CCBA website on September 9

comment period extended through October 9th. Comments were received from thirteen

Written comments were received from the following stakeholders:

HIV/AIDS Project Coordinator

Kenneth Nyange, Project Manager – Camp Tsavo

Peterson Msinga Mwatate, Head Teacher - Kale primary school

Taita Ranching Co. Ltd.

Engineer C.M Mwakulomba

Sylvester Izaka, IT & Network support engineer

ma Mwavuo, Volunteer Teacher – Marungu Secondary School

V Wambua Masai, Teacher and Instructor

Antony Lundi, Voi constituency – Maungu office

Chief DUNCAN, Marungu Location as addressed to the Manager Wildlife Work

Technical Works

izaka, Chief of Kasigau Location, Voi/Kenya

Driscilah M. Ngele, Assistant Chief’s Office

omments have been addressed by the auditor in this report. General themes included

helming support for the project’s climate, community and biodiversity benefits;

Support for the protection of wild animals;

Support for the greenhouse nursery program;

Support for the school bursary program;

Support for the construction of new schools and additions;

of Wildlife Work’s engagement with the community and community organizations;

Acknowledgement of the potential risks to the project area under the without

namely deforestation, conversion to agriculture and charcoal production;

Appreciation for the intrinsic value of the project area; and

Appreciation for employment opportunities offered by Wildlife Works.

Findings

The evidence and findings presented in this report address the criteria of the Standard by indicator

Standard specifies indicators for which findings are issued; findings are documented

and issued to the project proponent as Non-Conformity Reports (NCRs), New Information Requests

tunities for Improvement (OFIs). In the case of non-conformance, the

or lack of evidence posed by the project in the context of one or more

NCRs indicate broad non-conformance at the criterion level that must be satisf

project validation while NIRs and OFIs are less material. In the case of a NIR, the finding is to obtain

additional evidence to support the conformance of the project to an indicator. The project proponent

September 9th and the public

thirteen parties (see

omments have been addressed by the auditor in this report. General themes included:

benefits;

community and community organizations;

Acknowledgement of the potential risks to the project area under the without-project scenario,

of the Standard by indicator. For

for which findings are issued; findings are documented

nformation Requests

conformance, the NCR clearly

in the context of one or more

conformance at the criterion level that must be satisfied prior to

project validation while NIRs and OFIs are less material. In the case of a NIR, the finding is to obtain

additional evidence to support the conformance of the project to an indicator. The project proponent

Page 9: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

must respond to all NIRs before the

observation that may help the project proponent to improve their project. OFIs are optional however

may evolve into NCRs over time. Given the overlapping nature of the Standard’s indicators,

finding may address multiple indicators and criteria. In this report, findings are presented in order of

criterion and cross referenced subsequent to presentation.

Initially and upon conclusion of the audit, the project proponent

and how the project addresses the Standard in

Phase I – Rukinga Sanctuary, ultimately dated December 2009. This document is available to the public

on the CCBA website (http://www.climate

Design Document (PDD).

3.2. General Section

The General Section of the CCB Standards addresses

projections, project design and goals, management capacity

property rights.

3.2.1. G1 – Original Conditions

The original conditions at the project area

commences must be described. This description, along with

determine the likely impacts of the project.

Indicator G1.1. The location of the project and basic physical parameters (e.g., soil,

Findings: The location of the project area is described in the PDD. The basic physical parameters of the

project area and project zone are described in the PDD.

are found in Section G1.1 of the revised PDD.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G1.2. The types and condition of vegetation

Findings: Both the types and conditions of vegetation in the project area are described in the revised

PDD. Initially, the PDD lacked descriptions of the “OUT” and B

made during the site visit indicated that these types were notic

presented in the original PDD (see

trees and shrubs in the “OUT” type was less than the other types presented in the original PDD.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

6

must respond to all NIRs before the close of the audit. In the case of an OFI, the finding is an

observation that may help the project proponent to improve their project. OFIs are optional however

may evolve into NCRs over time. Given the overlapping nature of the Standard’s indicators,

finding may address multiple indicators and criteria. In this report, findings are presented in order of

criterion and cross referenced subsequent to presentation.

Initially and upon conclusion of the audit, the project proponent collated information about the project

project addresses the Standard in a document titled The Kasigau Corridor REDD Project

, ultimately dated December 2009. This document is available to the public

http://www.climate-standards.org). This document is referred to

The General Section of the CCB Standards addresses original conditions in the project are

projections, project design and goals, management capacity and best practices, and legal status and

Original Conditions in the Project Area

at the project area and the surrounding project zone before the project

commences must be described. This description, along with baseline projections (see G2), will help

determine the likely impacts of the project.

of the project and basic physical parameters (e.g., soil, geology, climate).

The location of the project area is described in the PDD. The basic physical parameters of the

project area and project zone are described in the PDD. Descriptions of the climate, soils and geology

of the revised PDD.

Yes No N/A

None

None

None

types and condition of vegetation within the project area.

Both the types and conditions of vegetation in the project area are described in the revised

PDD. Initially, the PDD lacked descriptions of the “OUT” and Boma vegetation types. Observations

made during the site visit indicated that these types were noticeably different than the vegetation types

(see NCR Number 1 of 19 for October 20, 2009). The stocking

trees and shrubs in the “OUT” type was less than the other types presented in the original PDD.

close of the audit. In the case of an OFI, the finding is an

observation that may help the project proponent to improve their project. OFIs are optional however

may evolve into NCRs over time. Given the overlapping nature of the Standard’s indicators, a single

finding may address multiple indicators and criteria. In this report, findings are presented in order of

ation about the project

The Kasigau Corridor REDD Project

, ultimately dated December 2009. This document is available to the public

This document is referred to as the Project

original conditions in the project are baseline

and legal status and

before the project

projections (see G2), will help to

geology, climate).

The location of the project area is described in the PDD. The basic physical parameters of the

Descriptions of the climate, soils and geology

Both the types and conditions of vegetation in the project area are described in the revised

ma vegetation types. Observations

eably different than the vegetation types

. The stocking level of

trees and shrubs in the “OUT” type was less than the other types presented in the original PDD.

Page 10: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Likewise, many Boma or cattle corrals were observed during the

the corrals were noticeably different than the

complete description of the vegetation types and conditions is in Sect

Conformance:

Non-Conformity Reports:

NCR Number 1 of 19 for October 20, 2009

Finding: The project proponents have omitted descriptions of some vegetation types and conditions

within the project area. The description must include these types and conditions of vegetation within

the project area.

Proponent Response on October 24

of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map

to Annex 1, which clearly indicates the boundary of the Project Z

Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image

and a KMZ file covering this area. We include the PDD text below.

We believe that this is a complete and adequate res

be closed.

Validator Response: The revisions made to the PDD are adequate.

New Information Requests:

Opportunities for Improvement:

Indicator G1.3. The boundaries of the project area and

Findings: Descriptions of the boundaries of the project area and project zone are given in Section G1.3

of the revised PDD. The project zone includes the land that falls between Tsavo East National Park and

Tsavo West National Park south and east of Voi town, and includes the communities of Maungu,

Itinyi, Buguta, Marungu, Kale, Mwakasinyi, Sasenyi and the privately held group ranches of

Kasigau, Taita, Amaka, Maungu, Mgeno, Kambanga, Wangala and Buchuma. A map of the project zone

is provided in the revised PDD (see

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

7

ma or cattle corrals were observed during the site visit. The vegetation conditions in

noticeably different than the vegetation types presented in the original PDD.

complete description of the vegetation types and conditions is in Section G1.2 of the revised PDD.

Yes No N/A

1 of 19 for October 20, 2009

The project proponents have omitted descriptions of some vegetation types and conditions

within the project area. The description must include these types and conditions of vegetation within

October 24, 2009: We have updated the description in section G1.3, and G3.3

of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map

to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD

Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image

and a KMZ file covering this area. We include the PDD text below.

We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19

The revisions made to the PDD are adequate.

None

None

The boundaries of the project area and the project zone.

Descriptions of the boundaries of the project area and project zone are given in Section G1.3

of the revised PDD. The project zone includes the land that falls between Tsavo East National Park and

uth and east of Voi town, and includes the communities of Maungu,

Itinyi, Buguta, Marungu, Kale, Mwakasinyi, Sasenyi and the privately held group ranches of

Kasigau, Taita, Amaka, Maungu, Mgeno, Kambanga, Wangala and Buchuma. A map of the project zone

provided in the revised PDD (see NCR Number 19 of 19 for October 20, 2009).

Yes No N/A

vegetation conditions in

vegetation types presented in the original PDD. A

ion G1.2 of the revised PDD.

The project proponents have omitted descriptions of some vegetation types and conditions

within the project area. The description must include these types and conditions of vegetation within

We have updated the description in section G1.3, and G3.3

of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map

one for the Kasigau Corridor REDD

Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image

ponse to this NCR #19 and we ask that the NCR #19

Descriptions of the boundaries of the project area and project zone are given in Section G1.3

of the revised PDD. The project zone includes the land that falls between Tsavo East National Park and

uth and east of Voi town, and includes the communities of Maungu,

Itinyi, Buguta, Marungu, Kale, Mwakasinyi, Sasenyi and the privately held group ranches of

Kasigau, Taita, Amaka, Maungu, Mgeno, Kambanga, Wangala and Buchuma. A map of the project zone

Page 11: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 19 of 19 for October 20, 2009

Finding: The boundaries of the project zon

the project zone should be clarified with an explicit map for Phase I.

Proponent Response on October 24

of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map

to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD

Project, with Phases I and II clearly indicated. We have also emailed the Validator a

and a KMZ file covering this area. We include the PDD text below.

We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19

be closed.

Validator Response: The new map provided in the revised PD

New Information Requests:

Opportunities for Improvement:

Indicator G1.4. Current carbon stocks

vegetation type and methods of carbon calculation (such as biomass plots, formulae, default values)

from the Intergovernmental Panel on Climate Change’s

for Agriculture, Forestry, and Other Land Use or a more robust and detailed methodology.

Findings: The project uses a VCS methodology (

double-approval process at the time of this report)

guidelines. Stratification and a sample of plots are used to estimate the current carbon stocks within

the project area. This method for estimating carbon stocks is the greatest level of detail specified by

IPCC as Tier 3.

Diameter measurements, stem counts and allometric equations are used to estimate the aboveground

biomass. Belowground biomass is estimated using ratio

from the IPCC guidance document. The allometric e

parameterized using a purposive sample within common species groups. The sample appeared to be

representative of the entire project area. The allometric equations for aboveground biomass were not

cross-validated for over fitting or selected using any statistical criteria. Given the limited number of

allometric equations available in the literature for this region of the continent, the constructed

equations seem adequate.

Soil organic carbon was estimated using a si

This method for estimating soil carbon appears to be adequate. The project proponent assumes that

the soil organic pool will remain constant throughout the life of the project, which is a reason

assumption.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

8

NCR Number 19 of 19 for October 20, 2009

The boundaries of the project zone are provided as a description; however the boundaries of

the project zone should be clarified with an explicit map for Phase I.

October 24, 2009: We have updated the description in section G1.3, and G3.3

w map for the Project Zone added in Annex 1. We have added the new map

to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD

Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image

and a KMZ file covering this area. We include the PDD text below.

We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19

The new map provided in the revised PDD is adequate.

None

None

Current carbon stocks within the project area(s), using stratification by land

vegetation type and methods of carbon calculation (such as biomass plots, formulae, default values)

Intergovernmental Panel on Climate Change’s 2006 Guidelines for National GHG Inventories

nd Other Land Use or a more robust and detailed methodology.

The project uses a VCS methodology (currently not approved by VCS and currently

process at the time of this report) and the VCS methodology conforms to IPCC

. Stratification and a sample of plots are used to estimate the current carbon stocks within

the project area. This method for estimating carbon stocks is the greatest level of detail specified by

stem counts and allometric equations are used to estimate the aboveground

biomass. Belowground biomass is estimated using ratios of above-to-belowground relative biomass

from the IPCC guidance document. The allometric equations for above ground biomass were

parameterized using a purposive sample within common species groups. The sample appeared to be

representative of the entire project area. The allometric equations for aboveground biomass were not

over fitting or selected using any statistical criteria. Given the limited number of

allometric equations available in the literature for this region of the continent, the constructed

Soil organic carbon was estimated using a simple random sample of soil cores analyzed by a third party.

This method for estimating soil carbon appears to be adequate. The project proponent assumes that

the soil organic pool will remain constant throughout the life of the project, which is a reason

however the boundaries of

We have updated the description in section G1.3, and G3.3

w map for the Project Zone added in Annex 1. We have added the new map

to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD

separate map image

We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19

stratification by land-use or

vegetation type and methods of carbon calculation (such as biomass plots, formulae, default values)

2006 Guidelines for National GHG Inventories

nd Other Land Use or a more robust and detailed methodology.

not approved by VCS and currently under the

and the VCS methodology conforms to IPCC

. Stratification and a sample of plots are used to estimate the current carbon stocks within

the project area. This method for estimating carbon stocks is the greatest level of detail specified by

stem counts and allometric equations are used to estimate the aboveground

belowground relative biomass

quations for above ground biomass were

parameterized using a purposive sample within common species groups. The sample appeared to be

representative of the entire project area. The allometric equations for aboveground biomass were not

over fitting or selected using any statistical criteria. Given the limited number of

allometric equations available in the literature for this region of the continent, the constructed

mple random sample of soil cores analyzed by a third party.

This method for estimating soil carbon appears to be adequate. The project proponent assumes that

the soil organic pool will remain constant throughout the life of the project, which is a reasonable

Page 12: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Conformance:

Non-Conformity Reports:

Opportunities for Improvement:

New Information Requests:

Indicator G1.5. A description of communities located in

economic and cultural information

communities (wealth, gender, ethnicity, etc.), identifies specific groups such as Indigenous Peoples and

describes any community characteristics.

Findings: The revised PDD contains a desc

specifically in Section G1.5. There are

Marungu, Kale, Mwakasinyi and Sasenyi.

these communities are small service business

employer in the project zone other than the school district. Given the limited diversity in socioeconom

conditions and culture, the provided

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G1.6. A description of current land use and

community property in the project zone, identifying any ongoing or unresolved conflicts or disputes and

indentifying and describing any disputes over land tenure that were resolved during the last ten years

(see also G5).

Findings: A description of the current land use, customary and legal rights is provided in the revised

PDD in Section 1.6. The description includes

recent history of the legal property rights of Rukinga Ranching Company. The description also includes

information about a solved dispute between emigrant Duruma which

the ranch now called the Sasenyi Valley Land Cooperative

outstanding conflicts are relatively minor and involve transient cattle herders

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

9

Yes No N/A

None

None

None

A description of communities located in the project zone, including basic socio

information that describes the social, economic and cultural diversity within

communities (wealth, gender, ethnicity, etc.), identifies specific groups such as Indigenous Peoples and

describes any community characteristics.

The revised PDD contains a description of all the communities located in the

There are several communities in the project zone: Maungu,

Marungu, Kale, Mwakasinyi and Sasenyi. These communities are rural Taitan and the econom

service businesses, small shops and bars. Wildlife Works is the only formal

one other than the school district. Given the limited diversity in socioeconom

culture, the provided description is adequate.

Yes No N/A

None

None

None

A description of current land use and customary and legal property rights including

community property in the project zone, identifying any ongoing or unresolved conflicts or disputes and

indentifying and describing any disputes over land tenure that were resolved during the last ten years

A description of the current land use, customary and legal rights is provided in the revised

PDD in Section 1.6. The description includes a history of the national system for land tenure and a

recent history of the legal property rights of Rukinga Ranching Company. The description also includes

information about a solved dispute between emigrant Duruma which resulted in the sale of a portion of

Sasenyi Valley Land Cooperative, prior to the project start date. Any

outstanding conflicts are relatively minor and involve transient cattle herders, mostly from Somalia.

Yes No N/A

None

, including basic socio-

that describes the social, economic and cultural diversity within

communities (wealth, gender, ethnicity, etc.), identifies specific groups such as Indigenous Peoples and

ription of all the communities located in the project zone,

project zone: Maungu, Itinyi, Buguta,

and the economies of

. Wildlife Works is the only formal

one other than the school district. Given the limited diversity in socioeconomic

customary and legal property rights including

community property in the project zone, identifying any ongoing or unresolved conflicts or disputes and

indentifying and describing any disputes over land tenure that were resolved during the last ten years

A description of the current land use, customary and legal rights is provided in the revised

national system for land tenure and a

recent history of the legal property rights of Rukinga Ranching Company. The description also includes

in the sale of a portion of

, prior to the project start date. Any

mostly from Somalia.

Page 13: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

New Information Requests:

Opportunities for Improvement:

Indicator G1.7. A description of current biodiversity within the project zone (diversity of species and

ecosystems) and threats to that biodiversity, using appropriate methodologies, substantiated where

possible with appropriate reference material.

Findings: The biodiversity diversity description provided in Section G1.7

comprehensive and adequate. The biodiversity description includes information about the ecosystem,

habitat and wildlife found within the project zone. Initially, the PDD lacked references to literature

containing descriptions of the methodologies by

for October 20, 2009).

Conformance:

Non-Conformity Reports:

New Information Requests:

NIR Number 1 of 5 for October 20, 2009

Finding: The project proponent has provided a description of biodiversity assumed to be partially based

on a literature review. A literature review is an appropriate methodology, however the project

proponent must provide appropriate reference material to substant

Proponent Response on October 30

text below, and have sent the Validator the references

information provided to the Validator is a more than adequate response to your finding and

Standard and we ask that you consider this finding NIR#1 closed.

Validator Response: The provided references indicate the use of a

therefore adequate.

Opportunities for Improvement:

Indicator G1.8. An evaluation of whether the project zone includes any of the following High

Conservation Values (HCVs) and a description of the qualifying attribut

8.1. Globally, regionally or nationally significant concentrations of biodiversity values;

a. protected areas

b. threatened species

c. endemic species

d. areas that support significant concentrations of a species during any time in their

(e.g. migrations, feeding grounds, breeding areas).

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

10

None

None

A description of current biodiversity within the project zone (diversity of species and

ecosystems) and threats to that biodiversity, using appropriate methodologies, substantiated where

appropriate reference material.

The biodiversity diversity description provided in Section G1.7 of the revised PDD is

comprehensive and adequate. The biodiversity description includes information about the ecosystem,

within the project zone. Initially, the PDD lacked references to literature

containing descriptions of the methodologies by which biodiversity was assessed (see NIR Number 1 of 5

Yes No N/A

None

NIR Number 1 of 5 for October 20, 2009

The project proponent has provided a description of biodiversity assumed to be partially based

on a literature review. A literature review is an appropriate methodology, however the project

proponent must provide appropriate reference material to substantiate this methodology, if possible.

October 30, 2009: We have revised sections G1.7 of the PDD to include the

text below, and have sent the Validator the references described in the text. We believe that this new

information provided to the Validator is a more than adequate response to your finding and

Standard and we ask that you consider this finding NIR#1 closed.

The provided references indicate the use of appropriate methodologies and are

None

An evaluation of whether the project zone includes any of the following High

Conservation Values (HCVs) and a description of the qualifying attributes:

8.1. Globally, regionally or nationally significant concentrations of biodiversity values;

areas that support significant concentrations of a species during any time in their

s, feeding grounds, breeding areas).

A description of current biodiversity within the project zone (diversity of species and

ecosystems) and threats to that biodiversity, using appropriate methodologies, substantiated where

of the revised PDD is

comprehensive and adequate. The biodiversity description includes information about the ecosystem,

within the project zone. Initially, the PDD lacked references to literature

NIR Number 1 of 5

The project proponent has provided a description of biodiversity assumed to be partially based

on a literature review. A literature review is an appropriate methodology, however the project

iate this methodology, if possible.

We have revised sections G1.7 of the PDD to include the

We believe that this new

information provided to the Validator is a more than adequate response to your finding and meets the

ppropriate methodologies and are

An evaluation of whether the project zone includes any of the following High

areas that support significant concentrations of a species during any time in their lifecycle

Page 14: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

8.2. Globally, regionally or nationally significant large landscape

most if not all naturally occurring species exist in natural patterns of distribution

8.3. Threatened or rare ecosystems;

8.4. Areas that provide critical ecosystem services (e.g., hydrological services, erosion control,

control);

8.5. Areas that are fundamental for meeting the basic needs of local communities (e.g., for

food, fuel, fodder, medicines or building materials without readily available

8.6. Areas that are critical for the traditional cultural identity of communities (e.g., areas of

ecological, economic or religious significance identifie

Findings: The revised PDD contains several descriptions of HCVs including threatened and endangered

species; the sanctuary as a corridor for significant concentrations of species; the area as a unique

dryland ecosystem; and Mount Kasigau which is used by the local population is a unique place on the

landscape. Initally, the PDD lacked information about Mount Kasigau

amended (see NCR Number 2 of 19 for October 20, 2009

local communities was discovered during the course of the site visit.

Conformance:

Non-Conformity Reports:

NCR Number 2 of 19 for October 20, 2009

Finding: The project zone includes at least one area that provides critical ecosystem services such as

hydrological and climate services that are not included in the description of the project zone in the PDD.

There are areas in the project zone that function as threatened ecosystems and are fundamental to

meeting the basic needs of local communities. The project proponent

description. Also, the project proponent must demonstrate that the project design includes specific

measures to ensure the maintenance or enhancement of these additional HCVs and that these areas will

not be negatively affected by the project. These additional H

community and biodiversity impact monitoring.

Proponent Response on October 30

B3.2 of the PDD to include the text

text.

We believe that this new information provided to the Validator is a more than adequate response to

your finding and meets the Standard and we ask that you consider this finding NCR#2

Validator Response: The supplemented PDD is adequate.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

11

8.2. Globally, regionally or nationally significant large landscape-level areas where viable

most if not all naturally occurring species exist in natural patterns of distribution and abundance;

Threatened or rare ecosystems;16

8.4. Areas that provide critical ecosystem services (e.g., hydrological services, erosion control,

8.5. Areas that are fundamental for meeting the basic needs of local communities (e.g., for

fuel, fodder, medicines or building materials without readily available alternatives); and

8.6. Areas that are critical for the traditional cultural identity of communities (e.g., areas of

ecological, economic or religious significance identified in collaboration with the communities).

The revised PDD contains several descriptions of HCVs including threatened and endangered

species; the sanctuary as a corridor for significant concentrations of species; the area as a unique

ecosystem; and Mount Kasigau which is used by the local population is a unique place on the

Initally, the PDD lacked information about Mount Kasigau however it

NCR Number 2 of 19 for October 20, 2009). The importance of Mount Kasigau to the

local communities was discovered during the course of the site visit.

Yes No N/A

NCR Number 2 of 19 for October 20, 2009

The project zone includes at least one area that provides critical ecosystem services such as

imate services that are not included in the description of the project zone in the PDD.

There are areas in the project zone that function as threatened ecosystems and are fundamental to

meeting the basic needs of local communities. The project proponent must include all HCV areas in the

description. Also, the project proponent must demonstrate that the project design includes specific

measures to ensure the maintenance or enhancement of these additional HCVs and that these areas will

fected by the project. These additional HCV areas must be assessed as part of

community and biodiversity impact monitoring.

October 30, 2009: We have revised sections G1.8, G3.6, CM1.2, CM3.2 and

B3.2 of the PDD to include the text below, and have sent the Validator the references described in the

We believe that this new information provided to the Validator is a more than adequate response to

your finding and meets the Standard and we ask that you consider this finding NCR#2 closed.

The supplemented PDD is adequate.

level areas where viable populations of

and abundance;

8.4. Areas that provide critical ecosystem services (e.g., hydrological services, erosion control, fire

8.5. Areas that are fundamental for meeting the basic needs of local communities (e.g., for essential

alternatives); and

8.6. Areas that are critical for the traditional cultural identity of communities (e.g., areas of cultural,

communities).

The revised PDD contains several descriptions of HCVs including threatened and endangered

species; the sanctuary as a corridor for significant concentrations of species; the area as a unique

ecosystem; and Mount Kasigau which is used by the local population is a unique place on the

it was subsequently

ance of Mount Kasigau to the

The project zone includes at least one area that provides critical ecosystem services such as

imate services that are not included in the description of the project zone in the PDD.

There are areas in the project zone that function as threatened ecosystems and are fundamental to

must include all HCV areas in the

description. Also, the project proponent must demonstrate that the project design includes specific

measures to ensure the maintenance or enhancement of these additional HCVs and that these areas will

areas must be assessed as part of

We have revised sections G1.8, G3.6, CM1.2, CM3.2 and

below, and have sent the Validator the references described in the

We believe that this new information provided to the Validator is a more than adequate response to

closed.

Page 15: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

New Information Requests:

Opportunities for Improvement:

3.2.2. G2 – Baseline Projections

A baseline projection is a description of expected conditions in the project zone in the

project activities. The project impacts will be measured against this ‘without

Indicators The project proponents must develop a defensible and well

scenario that must:

Indicator G2.1. Describe the most likely land

2006 GL for AFOLU or a more robust and detailed methodology,

landuse scenarios and the associated drivers of GHG emiss

selected is most likely.

Findings: The PDD provides a clear description of the identified land

project. The land-use scenario in the absence of the project is slash and bur

supported by condition of nearby, unprotected areas which have been cleared of forestland. Based on

interviews with community members conducted during the site visit, the selected land

very plausible. Also based on interviews conducted during the site visit, it is apparent that slash and

burn agriculture would proceed rapidly without the project.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G2.2. Document that project benefits would not have occurred in the absence of the project,

explaining how existing laws or regulations would likely affect land use and justifying

being claimed by the project are truly ‘additional’ and would be unlikely to occur without the project.

Findings: During the site visit, the benefits of the project were confirmed by interviews with local

community members. The PDD clearly documents

of the project. During the site visit, interviews with local autho

and regulations would not affect the likely land

enforced to prevent the conversation of forestland to agriculture. The term agriculture is used loosely in

the PDD and this report, and it implies both traditional agriculture and pastoralism.

Conformance:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

12

None

None

Baseline Projections

A baseline projection is a description of expected conditions in the project zone in the

project activities. The project impacts will be measured against this ‘without-project’ reference scenario.

The project proponents must develop a defensible and well-documented ‘without-

Describe the most likely land-use scenario in the absence of the project following IPCC

2006 GL for AFOLU or a more robust and detailed methodology, describing the range of potential

landuse scenarios and the associated drivers of GHG emissions and justifying why the land

The PDD provides a clear description of the identified land-use scenario in the absence of the

use scenario in the absence of the project is slash and burn agriculture which is clearly

supported by condition of nearby, unprotected areas which have been cleared of forestland. Based on

interviews with community members conducted during the site visit, the selected land

ased on interviews conducted during the site visit, it is apparent that slash and

burn agriculture would proceed rapidly without the project.

Yes No N/A

None

None

None

Document that project benefits would not have occurred in the absence of the project,

explaining how existing laws or regulations would likely affect land use and justifying

being claimed by the project are truly ‘additional’ and would be unlikely to occur without the project.

During the site visit, the benefits of the project were confirmed by interviews with local

community members. The PDD clearly documents the project benefits would not occur

. During the site visit, interviews with local authorities confirmed that the existing laws

and regulations would not affect the likely land-use without the project as there are no laws which are

enforced to prevent the conversation of forestland to agriculture. The term agriculture is used loosely in

PDD and this report, and it implies both traditional agriculture and pastoralism.

Yes No N/A

A baseline projection is a description of expected conditions in the project zone in the absence of

project’ reference scenario.

-project’ reference

use scenario in the absence of the project following IPCC

describing the range of potential

ions and justifying why the land-use scenario

use scenario in the absence of the

n agriculture which is clearly

supported by condition of nearby, unprotected areas which have been cleared of forestland. Based on

interviews with community members conducted during the site visit, the selected land-use scenario is

ased on interviews conducted during the site visit, it is apparent that slash and

Document that project benefits would not have occurred in the absence of the project,

explaining how existing laws or regulations would likely affect land use and justifying that the benefits

being claimed by the project are truly ‘additional’ and would be unlikely to occur without the project.

During the site visit, the benefits of the project were confirmed by interviews with local

occur in the absence

rities confirmed that the existing laws

use without the project as there are no laws which are

enforced to prevent the conversation of forestland to agriculture. The term agriculture is used loosely in

Page 16: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G2.3. Calculate the estimated carbon stock changes

reference scenario described above. This requires estimation of carbon stocks for each of the land

classes of concern and a definition of the carbon pools included, among the classes defined in the IPCC

2006 GL for AFOLU.19 The timeframe for this analysis can be either the project lifetime (see

project GHG accounting period, whichever is more appropriate.

emissions of non-CO2 GHG emissions such as CH

gases must be included if they are likely to account for more than 5% (in terms of CO

project’s overall GHG impact over each monitoring period.

Projects whose activities are designed to avoid GHG emissions

deforestation and forest degradation (REDD), avoiding conversion of non

improved forest management projects) must include an analysis of the relevant drivers and rates of

deforestation and/or degradation and a description and justification of the approaches,

and data used to perform this analysis. Regional

stage as long as there is a commitment to evaluate locally

project-specific spatial analysis of deforestation and/or degradation using an appropriately robust and

detailed carbon accounting methodology before the start of the project.

Findings: The estimated carbon stock changes

are presented in Section G2.3 using a

in 1995 and 1999. The rate is assumed to

to be linear in time. The latter of these assumptions is probably false (see

October 20, 2009), however the overall estimated deforestation rate is probably conservative based on

evidence from the site visit. Interviews with loc

area would likely be deforested in a very short period of time under the ‘without project’ scenario. An

analysis of the relevant drivers of deforestation is also presented in Section G2.3 of the PDD.

and despite the shortcomings of the deforestation model, the

the ‘without project’ scenario are reaso

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

13

None

None

None

Calculate the estimated carbon stock changes associated with the ‘without project’

reference scenario described above. This requires estimation of carbon stocks for each of the land

classes of concern and a definition of the carbon pools included, among the classes defined in the IPCC

The timeframe for this analysis can be either the project lifetime (see

project GHG accounting period, whichever is more appropriate. Estimate the net change in the

GHG emissions such as CH4 and N2O in the ‘without project’ scenario. Non

gases must be included if they are likely to account for more than 5% (in terms of CO2-

project’s overall GHG impact over each monitoring period.

Projects whose activities are designed to avoid GHG emissions (such as those reducing emissions from

deforestation and forest degradation (REDD), avoiding conversion of non-forest land, or certain

improved forest management projects) must include an analysis of the relevant drivers and rates of

degradation and a description and justification of the approaches,

and data used to perform this analysis. Regional-level estimates can be used at the project’s planning

stage as long as there is a commitment to evaluate locally-specific carbon stocks and to develop a

specific spatial analysis of deforestation and/or degradation using an appropriately robust and

detailed carbon accounting methodology before the start of the project.

The estimated carbon stock changes associated with the ‘without project’ reference scenario

are presented in Section G2.3 using an estimated rate measured from historical Landsat imagery taken

in 1995 and 1999. The rate is assumed to be linear in population size and population growth is assu

to be linear in time. The latter of these assumptions is probably false (see OFI Number 1 of 4 for

), however the overall estimated deforestation rate is probably conservative based on

evidence from the site visit. Interviews with local community members indicated that the entire project

area would likely be deforested in a very short period of time under the ‘without project’ scenario. An

analysis of the relevant drivers of deforestation is also presented in Section G2.3 of the PDD.

despite the shortcomings of the deforestation model, the estimated carbon stock changes under

the ‘without project’ scenario are reasonable and conservative.

Yes No N/A

None

None

associated with the ‘without project’

reference scenario described above. This requires estimation of carbon stocks for each of the land-use

classes of concern and a definition of the carbon pools included, among the classes defined in the IPCC

The timeframe for this analysis can be either the project lifetime (see G3) or the

Estimate the net change in the

t project’ scenario. Non-CO2

-equivalent) of the

(such as those reducing emissions from

forest land, or certain

improved forest management projects) must include an analysis of the relevant drivers and rates of

degradation and a description and justification of the approaches, assumptions

level estimates can be used at the project’s planning

carbon stocks and to develop a

specific spatial analysis of deforestation and/or degradation using an appropriately robust and

sociated with the ‘without project’ reference scenario

n estimated rate measured from historical Landsat imagery taken

linear in population size and population growth is assumed

OFI Number 1 of 4 for

), however the overall estimated deforestation rate is probably conservative based on

al community members indicated that the entire project

area would likely be deforested in a very short period of time under the ‘without project’ scenario. An

analysis of the relevant drivers of deforestation is also presented in Section G2.3 of the PDD. Overall

estimated carbon stock changes under

Page 17: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

OFI Number 1 of 4 for October 20, 2009

Finding: Whether valid or not, the model is conservative based on the evidence

However, the model for deforestation could be improved by examining the deforestation rates

elsewhere, in similar areas, and by

considering economic drivers.

Proponent Response on October 24

possible to identify the population growth model for the Project Zone in the 10 years immediately

preceding Wildlife Works arrival in anything other than a linear model. There is simply no evide

support another model. There are no National or sub

and we believe that if there were, our Project Zone would be demonstrated to have as high or higher a

deforestation rate as anywhere in Kenya over t

Dryland Forests being cleared for Slash and Burn Agriculture in Kenya, and most of those remaining are

in the Leakage Belt of this Project and will be addressed during Phase II of this project.

Validator Response: Population size over time is usually estimated using an exponential model.

Indicator G2.4. Describe how the ‘without project’ reference scenario would affect communities in the

project zone, including the impact of likely changes in water,

services.

Findings: Based on the PDD and the site visit, there would be obvious non

employment, subsistence agriculture and education under the without project scenario. Changes in

water, soil and other locally important ecosystem services would greatly impact communities in the

project zone as described in Section G2.4 of the PDD.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G2.5. Describe how the ‘without project’ reference scenario would affect biodiversity in the

project zone (e.g., habitat availability, landscape connectivity and threatened species

Findings: Given the habitat conditions present outside the pro

reflective of the without project scenario, there are obvious affects on biodiversity in the absence of the

project. These effects are directly re

between the two national parks and are described in Section G2.5 of the PDD.

Conformance:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

14

of 4 for October 20, 2009

Whether valid or not, the model is conservative based on the evidence from

However, the model for deforestation could be improved by examining the deforestation rates

elsewhere, in similar areas, and by examining the assumptions of linear population growth and

October 24, 2009: Kenya conducts a census every 10 years. As a result it is not

possible to identify the population growth model for the Project Zone in the 10 years immediately

preceding Wildlife Works arrival in anything other than a linear model. There is simply no evide

support another model. There are no National or sub-national deforestation rates published for Kenya

and we believe that if there were, our Project Zone would be demonstrated to have as high or higher a

deforestation rate as anywhere in Kenya over the ten years prior to our arrival. There are few similar

Dryland Forests being cleared for Slash and Burn Agriculture in Kenya, and most of those remaining are

in the Leakage Belt of this Project and will be addressed during Phase II of this project.

Population size over time is usually estimated using an exponential model.

Describe how the ‘without project’ reference scenario would affect communities in the

project zone, including the impact of likely changes in water, soil and other locally important ecosystem

Based on the PDD and the site visit, there would be obvious non-

employment, subsistence agriculture and education under the without project scenario. Changes in

and other locally important ecosystem services would greatly impact communities in the

project zone as described in Section G2.4 of the PDD.

Yes No N/A

None

None

None

Describe how the ‘without project’ reference scenario would affect biodiversity in the

project zone (e.g., habitat availability, landscape connectivity and threatened species).

Given the habitat conditions present outside the project area and the project zone which are

reflective of the without project scenario, there are obvious affects on biodiversity in the absence of the

project. These effects are directly related to the project area as a critical habitat and a wildlife corridor

between the two national parks and are described in Section G2.5 of the PDD.

Yes No N/A

from the site visit.

However, the model for deforestation could be improved by examining the deforestation rates

examining the assumptions of linear population growth and

Kenya conducts a census every 10 years. As a result it is not

possible to identify the population growth model for the Project Zone in the 10 years immediately

preceding Wildlife Works arrival in anything other than a linear model. There is simply no evidence to

national deforestation rates published for Kenya

and we believe that if there were, our Project Zone would be demonstrated to have as high or higher a

he ten years prior to our arrival. There are few similar

Dryland Forests being cleared for Slash and Burn Agriculture in Kenya, and most of those remaining are

Population size over time is usually estimated using an exponential model.

Describe how the ‘without project’ reference scenario would affect communities in the

soil and other locally important ecosystem

-improvements in

employment, subsistence agriculture and education under the without project scenario. Changes in

and other locally important ecosystem services would greatly impact communities in the

Describe how the ‘without project’ reference scenario would affect biodiversity in the

).

ject area and the project zone which are

reflective of the without project scenario, there are obvious affects on biodiversity in the absence of the

lated to the project area as a critical habitat and a wildlife corridor

Page 18: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.2.3. G3 – Project Design and Goals

The project must be described in sufficient detail so that a third

Projects must be designed to minimize risks to the expected

benefits and to maintain those benefits beyond the life of the project. Effective local participation in

project design and implementation is key to optimizing multiple benefits, equitably and sustainably.

Projects that operate in a transparent manner build confidence with stakeholders and outside parties

and enable them to contribute more effectively to the project.

Indicators

The project proponents must:

Indicator G3.1. Provide a summary of the project’s major climate,

objectives.

Findings: A summary of the major climate, community and biodiversity benefits are listed in Section

G3.1 of the PDD. These objectives broadly include the protection of the project area, long

sustainability, investment and outreach.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G3.2. Describe each project activity with expected climate, community and biod

impacts and its relevance to achieving the project’s objectives.

Findings: Section G3.2 is described in the revised PDD. Initially upon completion of the site visit, several

project activities were identified but missing from the original PDD (

20, 2009). These activities clearly contributed to the net positive impact of the project and were

therefore material to the validation.

amended to include all relevant project activities. The project proponent also provided an

implementation schedule for project

objectives (see Indicator G3.5).

Conformance:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

15

None

None

None

Project Design and Goals

The project must be described in sufficient detail so that a third-party can adequately evaluate it.

Projects must be designed to minimize risks to the expected climate, community and biodiversity

and to maintain those benefits beyond the life of the project. Effective local participation in

design and implementation is key to optimizing multiple benefits, equitably and sustainably.

operate in a transparent manner build confidence with stakeholders and outside parties

contribute more effectively to the project.

Provide a summary of the project’s major climate, community and biodiversity

A summary of the major climate, community and biodiversity benefits are listed in Section

G3.1 of the PDD. These objectives broadly include the protection of the project area, long

investment and outreach.

Yes No N/A

None

None

None

. Describe each project activity with expected climate, community and biod

relevance to achieving the project’s objectives.

Section G3.2 is described in the revised PDD. Initially upon completion of the site visit, several

were identified but missing from the original PDD (see NIR Number 2 of 5 for October

es clearly contributed to the net positive impact of the project and were

therefore material to the validation. Subsequent to the initial findings of the audit, the revised PDD was

amended to include all relevant project activities. The project proponent also provided an

implementation schedule for project activities to demonstrate their feasibility to achieving t

Yes No N/A

party can adequately evaluate it.

climate, community and biodiversity

and to maintain those benefits beyond the life of the project. Effective local participation in

design and implementation is key to optimizing multiple benefits, equitably and sustainably.

operate in a transparent manner build confidence with stakeholders and outside parties

community and biodiversity

A summary of the major climate, community and biodiversity benefits are listed in Section

G3.1 of the PDD. These objectives broadly include the protection of the project area, long-term

. Describe each project activity with expected climate, community and biodiversity

Section G3.2 is described in the revised PDD. Initially upon completion of the site visit, several

NIR Number 2 of 5 for October

es clearly contributed to the net positive impact of the project and were

Subsequent to the initial findings of the audit, the revised PDD was

amended to include all relevant project activities. The project proponent also provided an

to demonstrate their feasibility to achieving the project’s

Page 19: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Non-Conformity Reports:

New Information Requests:

NIR Number 2 of 5 for October 20, 2009

Finding: The PDD describes some project activities, however during the site visit, several project

activities were identified that were not included in the PDD. These project activities provide evidence to

support the net positive impact of the project. The project proponent must provide a complete list of

project activities. Also, a general implemen

sufficient detail for third-party evaluation.

Proponent Response on October 30

Implementation Schedule and have sent that

Activities, their start and end dates, and capital

which are then picked up in the detailed

We have also revised the text of Sections G3.2 and G3.4 to reflect the additional detail about the

activities that the Validator is referring to in this NIR.

Validator Response: The supplied list is inclusive of all relevant project activities and the su

implementation schedule shows milestone by which the project can be verified.

Opportunities for Improvement:

Indicator G3.3. Provide a map identifying the project location and boundaries of the project area(s),

where the project activities will occur, of the project zone and of additional surrounding locations that

are predicted to be impacted by project activities (e.g. through leakage).

Findings: The revised PDD contains maps of the project area and the project zone. The original PDD

was missing a map of the project zone which was subsequently added (see

October 20, 2009). The maps in the revised PDD also show the surrounding communities which are

predicted to be impacted by the project

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

16

None

NIR Number 2 of 5 for October 20, 2009

The PDD describes some project activities, however during the site visit, several project

activities were identified that were not included in the PDD. These project activities provide evidence to

support the net positive impact of the project. The project proponent must provide a complete list of

project activities. Also, a general implementation schedule for all project activities must be included in

party evaluation.

October 30, 2009: We have developed a detailed Project Activity List and

Implementation Schedule and have sent that to the Validator. This schedule shows specific Project

Activities, their start and end dates, and capital and operating budget amounts for their implementation

which are then picked up in the detailed Project Cash Flow provided to the Validator under NCR#6.

e also revised the text of Sections G3.2 and G3.4 to reflect the additional detail about the

activities that the Validator is referring to in this NIR.

The supplied list is inclusive of all relevant project activities and the su

implementation schedule shows milestone by which the project can be verified.

None

Provide a map identifying the project location and boundaries of the project area(s),

will occur, of the project zone and of additional surrounding locations that

predicted to be impacted by project activities (e.g. through leakage).

The revised PDD contains maps of the project area and the project zone. The original PDD

s missing a map of the project zone which was subsequently added (see NCR Number 19 of 19 for

). The maps in the revised PDD also show the surrounding communities which are

predicted to be impacted by the project activities.

Yes No N/A

See NCR Number 19 of 19 for October 20, 2009

None

None

The PDD describes some project activities, however during the site visit, several project

activities were identified that were not included in the PDD. These project activities provide evidence to

support the net positive impact of the project. The project proponent must provide a complete list of

tation schedule for all project activities must be included in

We have developed a detailed Project Activity List and

alidator. This schedule shows specific Project

and operating budget amounts for their implementation

Project Cash Flow provided to the Validator under NCR#6.

e also revised the text of Sections G3.2 and G3.4 to reflect the additional detail about the project

The supplied list is inclusive of all relevant project activities and the supplied

Provide a map identifying the project location and boundaries of the project area(s),

will occur, of the project zone and of additional surrounding locations that

The revised PDD contains maps of the project area and the project zone. The original PDD

NCR Number 19 of 19 for

). The maps in the revised PDD also show the surrounding communities which are

NCR Number 19 of 19 for October 20, 2009

Page 20: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Indicator G3.4. Define the project lifetime and

differences between them. Define an implementation schedule, indicating key dates and milestones in

the project’s development.

Findings: The project lifetime and the GHG accounting period are defined in Section G3.4 of the PDD.

The project lifetime and GHG accounting period are the same. Initially, key dates for the

implementation of project activities were undefined but were subsequently

(see NIR Number 2 of 5 for October 20, 2009

verify project activities during the project lifetime.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G3.5. Identify likely natural and human

biodiversity benefits during the project lifetime and outline measures adopted to

Findings: A list of major risks to expected climate, community and biodiversity benefits and outlined

measures are presented in Section G3.5 of the revised PDD. Initially, several risks were identified during

community meetings but were omitted from presented list (see

2009). The list was augmented in response to findings and the augmented list adequately includes all

identified risks and outlines measure adopted to mitigate identified risks.

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

17

Define the project lifetime and GHG accounting period and explain and justify any

between them. Define an implementation schedule, indicating key dates and milestones in

The project lifetime and the GHG accounting period are defined in Section G3.4 of the PDD.

The project lifetime and GHG accounting period are the same. Initially, key dates for the

implementation of project activities were undefined but were subsequently presented during the audit

NIR Number 2 of 5 for October 20, 2009). The supplied implementation schedule is im

es during the project lifetime.

Yes No N/A

None

See NIR Number 2 of 5 for October 20, 2009

None

Identify likely natural and human-induced risks to the expected climate, community and

biodiversity benefits during the project lifetime and outline measures adopted to mitigate these

A list of major risks to expected climate, community and biodiversity benefits and outlined

measures are presented in Section G3.5 of the revised PDD. Initially, several risks were identified during

were omitted from presented list (see NCR Number 3 of 19 for October 20,

). The list was augmented in response to findings and the augmented list adequately includes all

identified risks and outlines measure adopted to mitigate identified risks.

Yes No N/A

GHG accounting period and explain and justify any

between them. Define an implementation schedule, indicating key dates and milestones in

The project lifetime and the GHG accounting period are defined in Section G3.4 of the PDD.

The project lifetime and GHG accounting period are the same. Initially, key dates for the

presented during the audit

). The supplied implementation schedule is important to

induced risks to the expected climate, community and

mitigate these risks.

A list of major risks to expected climate, community and biodiversity benefits and outlined

measures are presented in Section G3.5 of the revised PDD. Initially, several risks were identified during

NCR Number 3 of 19 for October 20,

). The list was augmented in response to findings and the augmented list adequately includes all

Page 21: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 3 of 19 for October 20, 2009

Finding: The PDD describes some major risks,

exist. Based on community meetings and interviews, other potential risks are drought on wildlife,

drought on fruit tree plantings and invasion of people into the project area because of desirable grazing

areas. These are likely risks that must be addressed in sufficient detail for third party evaluation.

Proponent Response on October 30

text below, to provide additional risks and mitigation

provided to the Validator together with the additions made to Section GL1.2 in response to finding

NCR#18 and previously provided is a more than adequate response to your finding and meets the

Standard and we ask that you consider this finding NCR#3 closed.

Validator Response: The revised PDD now includes all identified risks and likewise presents mitigation

strategies.

New Information Requests:

Opportunities for Improvement:

OFI Number 2 of 4 for October 20, 2009

Finding: The PDD describes the potential risk of fire and some mitigation

project proponent may also consider constructing effective firebreaks as an additional mitigation

activity, especially given the evidence of recent fire in the project area, observed during the site visit .

Proponent Response on October 24

against the worst fires, as evidenced by the fact that in

enter into the Project Area from the North boundary, a distance including the road reserve of some two

hundred meters. This is because in high fire risk periods, smoldering elephant dung becomes airborne

and can travel on the wind some significant distance to relight dry grass on the other side of the

firebreaks.

Validator Response: NA

Indicator G3.6. Demonstrate that the project design includes specific measures to ensure the

maintenance or enhancement of the high conservation value attributes identified in

the precautionary principle.

Findings: The revised PDD demonstrates that the project design includes specific measures to ensure

the maintenance and enhancement of HCV

for missing HCV values under Indicator G1.8, Section G3.6 of the revised PDD contains references to

Mount Kasigau (see NCR Number 2 of 19 for October 20, 2009

affect the maintenance of HCV in the project zone.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

18

NCR Number 3 of 19 for October 20, 2009

The PDD describes some major risks, however other natural and human induced risks also

exist. Based on community meetings and interviews, other potential risks are drought on wildlife,

drought on fruit tree plantings and invasion of people into the project area because of desirable grazing

areas. These are likely risks that must be addressed in sufficient detail for third party evaluation.

October 30, 2009: We have revised sections G3.5 of the PDD to include the

text below, to provide additional risks and mitigation strategies. We believe that this new information

provided to the Validator together with the additions made to Section GL1.2 in response to finding

NCR#18 and previously provided is a more than adequate response to your finding and meets the

e ask that you consider this finding NCR#3 closed.

The revised PDD now includes all identified risks and likewise presents mitigation

None

October 20, 2009

The PDD describes the potential risk of fire and some mitigation activities

project proponent may also consider constructing effective firebreaks as an additional mitigation

dence of recent fire in the project area, observed during the site visit .

October 24, 2009: Fire breaks are unfortunately fairly ineffective in this area

against the worst fires, as evidenced by the fact that in 1998 fire jumped the Main Mombasa Highway to

enter into the Project Area from the North boundary, a distance including the road reserve of some two

hundred meters. This is because in high fire risk periods, smoldering elephant dung becomes airborne

some significant distance to relight dry grass on the other side of the

Demonstrate that the project design includes specific measures to ensure the

enhancement of the high conservation value attributes identified in G1

The revised PDD demonstrates that the project design includes specific measures to ensure

the maintenance and enhancement of HCV in the project zone. In response to an initial finding issued

for missing HCV values under Indicator G1.8, Section G3.6 of the revised PDD contains references to

NCR Number 2 of 19 for October 20, 2009). The project design does not ad

affect the maintenance of HCV in the project zone.

however other natural and human induced risks also

exist. Based on community meetings and interviews, other potential risks are drought on wildlife,

drought on fruit tree plantings and invasion of people into the project area because of desirable grazing

areas. These are likely risks that must be addressed in sufficient detail for third party evaluation.

We have revised sections G3.5 of the PDD to include the

strategies. We believe that this new information

provided to the Validator together with the additions made to Section GL1.2 in response to finding

NCR#18 and previously provided is a more than adequate response to your finding and meets the

The revised PDD now includes all identified risks and likewise presents mitigation

for this risk. The

project proponent may also consider constructing effective firebreaks as an additional mitigation

dence of recent fire in the project area, observed during the site visit .

Fire breaks are unfortunately fairly ineffective in this area

Main Mombasa Highway to

enter into the Project Area from the North boundary, a distance including the road reserve of some two

hundred meters. This is because in high fire risk periods, smoldering elephant dung becomes airborne

some significant distance to relight dry grass on the other side of the

Demonstrate that the project design includes specific measures to ensure the

G1 consistent with

The revised PDD demonstrates that the project design includes specific measures to ensure

in the project zone. In response to an initial finding issued

for missing HCV values under Indicator G1.8, Section G3.6 of the revised PDD contains references to

). The project design does not adversely

Page 22: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G3.7. Describe the measures that will

community and biodiversity benefits beyond the project lifetime.

Findings: The PDD describes three measures that will be taken to maintain and enhance the project

benefits beyond the lifetime of the project:

relatively permanent conservation easement. These measures clearly maintain and enhance the

project benefits beyond the lifetime of the project.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G3.8. Document and defend how communities and other stakeholders potentially affected by

the project activities have been identified and have been involved in project design

consultation, particularly with a view to optimizing community and stakeholder benefits, respecting

local customs and values and maintaining high conservation values. Project developers must document

stakeholder dialogues and indicate if

plan must be developed to continue communication and consultation between project managers and all

community groups about the project and its impacts to facilitate adaptive management through

life of the project.

Findings: Several stakeholder groups potentially affected by the project activities were involved in the

project design both formally and informally. Formal documentation was observed for the involvement

of the shareholders of the Rukinga Ranching Company. Community groups were

formal documentation was made regarding their involvement in project design. Based on interviews

with community members, the project does not appear to be disrespectful of loc

Also, the project appears to maintain HCV.

Given the overall lack of documentation regarding the involvement of stakeholders, it was unclear if all

the shareholders of Rukinga Ranching Company clearly supported the project. Given

shareholder rights to the project area and based on the evidence collected during the site visit, it was

found that the project proponent needed to clearly document the support of the shareholders for the

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

19

Yes No N/A

See NCR Number 2 of 19 for October 20, 2009

None

None

Describe the measures that will be taken to maintain and enhance the climate,

biodiversity benefits beyond the project lifetime.

The PDD describes three measures that will be taken to maintain and enhance the project

benefits beyond the lifetime of the project: long-term job creation, long-term financial health and

relatively permanent conservation easement. These measures clearly maintain and enhance the

project benefits beyond the lifetime of the project.

Yes No N/A

None

None

None

Document and defend how communities and other stakeholders potentially affected by

project activities have been identified and have been involved in project design

consultation, particularly with a view to optimizing community and stakeholder benefits, respecting

local customs and values and maintaining high conservation values. Project developers must document

stakeholder dialogues and indicate if and how the project proposal was revised based on such input. A

plan must be developed to continue communication and consultation between project managers and all

community groups about the project and its impacts to facilitate adaptive management through

Several stakeholder groups potentially affected by the project activities were involved in the

project design both formally and informally. Formal documentation was observed for the involvement

of the Rukinga Ranching Company. Community groups were involved

formal documentation was made regarding their involvement in project design. Based on interviews

with community members, the project does not appear to be disrespectful of local customs and values.

project appears to maintain HCV.

iven the overall lack of documentation regarding the involvement of stakeholders, it was unclear if all

the shareholders of Rukinga Ranching Company clearly supported the project. Given

shareholder rights to the project area and based on the evidence collected during the site visit, it was

found that the project proponent needed to clearly document the support of the shareholders for the

NCR Number 2 of 19 for October 20, 2009

be taken to maintain and enhance the climate,

The PDD describes three measures that will be taken to maintain and enhance the project

term financial health and

relatively permanent conservation easement. These measures clearly maintain and enhance the

Document and defend how communities and other stakeholders potentially affected by

project activities have been identified and have been involved in project design through effective

consultation, particularly with a view to optimizing community and stakeholder benefits, respecting

local customs and values and maintaining high conservation values. Project developers must document

based on such input. A

plan must be developed to continue communication and consultation between project managers and all

community groups about the project and its impacts to facilitate adaptive management throughout the

Several stakeholder groups potentially affected by the project activities were involved in the

project design both formally and informally. Formal documentation was observed for the involvement

involved as well but no

formal documentation was made regarding their involvement in project design. Based on interviews

al customs and values.

iven the overall lack of documentation regarding the involvement of stakeholders, it was unclear if all

the shareholders of Rukinga Ranching Company clearly supported the project. Given the materiality of

shareholder rights to the project area and based on the evidence collected during the site visit, it was

found that the project proponent needed to clearly document the support of the shareholders for the

Page 23: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

project (see NCR Number 1 of 1 f

conformance of the project to Indicators

conformance to this indicator in the context of the shareholders, however there was sufficient

evidence regarding the documentation of other stakeholders groups.

In response to an initial finding, the project proponent has enacted a plan to communicate the project

with all identified community groups (see

documentation on dialogs and adaptive management. However given the lack of documentation on the

involvement of stakeholders, in general, to the design of this project, here is

conformance to this indicator. However because no

customs, local values or high conservation values

this finding is immaterial to conformance with the criterion.

Conformance:

Non-Conformity Reports:

NCR Number 4 of 19 for October 20, 2009

Finding: Provide documentation of stakeholder dialogs and describe how the project proposal was

revised, if it was revised. The project proponent must also develop a plan to continue communication

with all community groups. This documentation and the plan must be addressed in sufficient detail for

third party evaluation.

Proponent Response on November 1

more specific about past meetings in

more formal monitoring going forward. The text of that section is included below. We believe this

represents a complete and acceptable response to your finding and meets the standard and we

you close finding NCR#4.

Validator Response: The project propo

documented evidence that all stakeholder groups were involved in project design. The plan for more

formal monitoring should be sufficient for future documentation under Criterion G3.

NCR Number 1 of 1 for November 12, 2009

Finding: The legal framework for the Carbon Easement is clear; however, no documentation has been

provided demonstrating that the project is undertaken

consent. The only evidence of consent is legal documentation, the Carbon Easement, stemming from a

convention of shareholders, not all of whom might have been present at the meeting. As no

documentation to the effect of attendance has been provided, it is unclear whether all shareholders

were present at the AGM and wheth

Further based on supplemental guidance provided by CCBA, consultation with those whose rights will be

affected by the project is required. Clearly, the Carbon Easement affects the right of all the

shareholders. No documented evidence, other than legal evidence, has been provided to demonstrate

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

20

for November 12, 2009). This evidence was further material to the

conformance of the project to Indicators G5.3 and G5.6. The presented documentation supported

conformance to this indicator in the context of the shareholders, however there was sufficient

evidence regarding the documentation of other stakeholders groups.

In response to an initial finding, the project proponent has enacted a plan to communicate the project

with all identified community groups (see NCR Number 4 of 19 for October 20, 2009). This plan entails

documentation on dialogs and adaptive management. However given the lack of documentation on the

involvement of stakeholders, in general, to the design of this project, here is insufficient

tor. However because no community benefits, stakeholder benefits,

high conservation values appear to be negatively affected by the project design

o conformance with the criterion.

Yes No N/A

NCR Number 4 of 19 for October 20, 2009

Provide documentation of stakeholder dialogs and describe how the project proposal was

revised, if it was revised. The project proponent must also develop a plan to continue communication

all community groups. This documentation and the plan must be addressed in sufficient detail for

November 1, 2009: We have significantly enhanced Section G3.8 to be much

more specific about past meetings in the formulation of the REDD project, and to demonstrate a plan for

more formal monitoring going forward. The text of that section is included below. We believe this

represents a complete and acceptable response to your finding and meets the standard and we

proponent has enhanced Section G3.8, however there is insufficient

documented evidence that all stakeholder groups were involved in project design. The plan for more

uld be sufficient for future documentation under Criterion G3.

for November 12, 2009

The legal framework for the Carbon Easement is clear; however, no documentation has been

provided demonstrating that the project is undertaken on behalf of the carbon owners with their full

consent. The only evidence of consent is legal documentation, the Carbon Easement, stemming from a

convention of shareholders, not all of whom might have been present at the meeting. As no

the effect of attendance has been provided, it is unclear whether all shareholders

were present at the AGM and whether all gave their full consent.

Further based on supplemental guidance provided by CCBA, consultation with those whose rights will be

ed by the project is required. Clearly, the Carbon Easement affects the right of all the

shareholders. No documented evidence, other than legal evidence, has been provided to demonstrate

). This evidence was further material to the

The presented documentation supported

conformance to this indicator in the context of the shareholders, however there was sufficient lack of

In response to an initial finding, the project proponent has enacted a plan to communicate the project

). This plan entails

documentation on dialogs and adaptive management. However given the lack of documentation on the

insufficient evidence for

stakeholder benefits, local

appear to be negatively affected by the project design,

Provide documentation of stakeholder dialogs and describe how the project proposal was

revised, if it was revised. The project proponent must also develop a plan to continue communication

all community groups. This documentation and the plan must be addressed in sufficient detail for

We have significantly enhanced Section G3.8 to be much

the formulation of the REDD project, and to demonstrate a plan for

more formal monitoring going forward. The text of that section is included below. We believe this

represents a complete and acceptable response to your finding and meets the standard and we ask that

there is insufficient

documented evidence that all stakeholder groups were involved in project design. The plan for more

The legal framework for the Carbon Easement is clear; however, no documentation has been

on behalf of the carbon owners with their full

consent. The only evidence of consent is legal documentation, the Carbon Easement, stemming from a

convention of shareholders, not all of whom might have been present at the meeting. As no

the effect of attendance has been provided, it is unclear whether all shareholders

Further based on supplemental guidance provided by CCBA, consultation with those whose rights will be

ed by the project is required. Clearly, the Carbon Easement affects the right of all the

shareholders. No documented evidence, other than legal evidence, has been provided to demonstrate

Page 24: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

that the project will not encroach uninvited on the rights of all s

evidence has been provided regarding the free, prior and informed consent of all shareholders.

Please provide documentation that all known shareholders were present at the AGM and gave their full

consent or please provide an opportunity to all shareholders to object to the project. Either of these

provisions will be considered adequate to demonstrate the consent (or objection) of all shareholders in

the context of indicators G3.8, G5.3 and G5.6. Should the latter of t

notification to each known shareholder must be documented and all shareholders must be allowed to

object in writing or person within a reasonable amount of time. A reasonable amount of time is at least

30 days from the date of notification.

Proponent Response on December 9

was to hold a Extraordinary General Meeting (EGM)of the Shareholders of Rukinga Ranching Co Ltd. for

which the agenda was one item; a resolution t

project, Phase I, and the Carbon Easement with Wildlife Works, Inc. that legalizes the pursuit of that

project. We mailed out 46 letters one to each Shareholder, inviting them to attend the EGM to be held

at Voi town on December 9th 2009, and we included in their letters a Proxy form by which they could

vote for or against the project in absentia without having to attend the EGM. The letters of invitation

provided for the statutory 21 days notice. The Valid

adequate. We have provided the Validator with copies of each letter sent out, together with the Proxy

form and the Resolution description. Wildlife Works staff then spent two full days in the community

trying to track down all the shareholders and were able to meet face to face with all except one, to

ensure they all knew of the meeting. We have provided the Validator with the minutes of the

Extraordinary General Meeting and with a shareholder count, and list of

vote was unanimous. Legally, only a simple majority of Rukinga’s Shareholders are required to approve

this Resolution, but we understand the Validator’s interest in knowing more detail behind the level of

support from the local shareholders, and we believe the results of this Extraordinary General Meeting

more than adequately demonstrate that the Shareholders of Rukinga Ranching Company

overwhelmingly support this REDD Project, and we ask that this finding be closed.

Please note the proceedings of the Extraordinary General Meeting are confidential and should not be

made part of the public record.

Validator Response: The provided proceedings clearly document the support of the project by the

shareholders of Rukinga Ranching Company.

New Information Requests:

Opportunities for Improvement:

Indicator G3.9. Describe what specific steps have been taken, and communications methods used, to

publicize the CCBA public comment period to communities and other stakeholders and to facilitate their

submission of comments to CCBA. Project proponents must play an active

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

21

that the project will not encroach uninvited on the rights of all shareholders. Likewise, no documented

evidence has been provided regarding the free, prior and informed consent of all shareholders.

Please provide documentation that all known shareholders were present at the AGM and gave their full

ide an opportunity to all shareholders to object to the project. Either of these

provisions will be considered adequate to demonstrate the consent (or objection) of all shareholders in

the context of indicators G3.8, G5.3 and G5.6. Should the latter of these options be pursued,

notification to each known shareholder must be documented and all shareholders must be allowed to

object in writing or person within a reasonable amount of time. A reasonable amount of time is at least

ification.

December 9, 2009: As agreed with the validator our response to this finding

was to hold a Extraordinary General Meeting (EGM)of the Shareholders of Rukinga Ranching Co Ltd. for

which the agenda was one item; a resolution to approve the pursuit of the Kasigau Corridor REDD

project, Phase I, and the Carbon Easement with Wildlife Works, Inc. that legalizes the pursuit of that

project. We mailed out 46 letters one to each Shareholder, inviting them to attend the EGM to be held

at Voi town on December 9th 2009, and we included in their letters a Proxy form by which they could

vote for or against the project in absentia without having to attend the EGM. The letters of invitation

provided for the statutory 21 days notice. The Validator agreed that the 21 day notice period was

adequate. We have provided the Validator with copies of each letter sent out, together with the Proxy

form and the Resolution description. Wildlife Works staff then spent two full days in the community

o track down all the shareholders and were able to meet face to face with all except one, to

ensure they all knew of the meeting. We have provided the Validator with the minutes of the

Extraordinary General Meeting and with a shareholder count, and list of those voting in favor, which

vote was unanimous. Legally, only a simple majority of Rukinga’s Shareholders are required to approve

this Resolution, but we understand the Validator’s interest in knowing more detail behind the level of

l shareholders, and we believe the results of this Extraordinary General Meeting

more than adequately demonstrate that the Shareholders of Rukinga Ranching Company

overwhelmingly support this REDD Project, and we ask that this finding be closed.

e the proceedings of the Extraordinary General Meeting are confidential and should not be

The provided proceedings clearly document the support of the project by the

Ranching Company.

None

None

Describe what specific steps have been taken, and communications methods used, to

publicize the CCBA public comment period to communities and other stakeholders and to facilitate their

submission of comments to CCBA. Project proponents must play an active role in distributing key project

hareholders. Likewise, no documented

evidence has been provided regarding the free, prior and informed consent of all shareholders.

Please provide documentation that all known shareholders were present at the AGM and gave their full

ide an opportunity to all shareholders to object to the project. Either of these

provisions will be considered adequate to demonstrate the consent (or objection) of all shareholders in

hese options be pursued,

notification to each known shareholder must be documented and all shareholders must be allowed to

object in writing or person within a reasonable amount of time. A reasonable amount of time is at least

As agreed with the validator our response to this finding

was to hold a Extraordinary General Meeting (EGM)of the Shareholders of Rukinga Ranching Co Ltd. for

o approve the pursuit of the Kasigau Corridor REDD

project, Phase I, and the Carbon Easement with Wildlife Works, Inc. that legalizes the pursuit of that

project. We mailed out 46 letters one to each Shareholder, inviting them to attend the EGM to be held

at Voi town on December 9th 2009, and we included in their letters a Proxy form by which they could

vote for or against the project in absentia without having to attend the EGM. The letters of invitation

ator agreed that the 21 day notice period was

adequate. We have provided the Validator with copies of each letter sent out, together with the Proxy

form and the Resolution description. Wildlife Works staff then spent two full days in the community

o track down all the shareholders and were able to meet face to face with all except one, to

ensure they all knew of the meeting. We have provided the Validator with the minutes of the

those voting in favor, which

vote was unanimous. Legally, only a simple majority of Rukinga’s Shareholders are required to approve

this Resolution, but we understand the Validator’s interest in knowing more detail behind the level of

l shareholders, and we believe the results of this Extraordinary General Meeting

more than adequately demonstrate that the Shareholders of Rukinga Ranching Company

e the proceedings of the Extraordinary General Meeting are confidential and should not be

The provided proceedings clearly document the support of the project by the

Describe what specific steps have been taken, and communications methods used, to

publicize the CCBA public comment period to communities and other stakeholders and to facilitate their

role in distributing key project

Page 25: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

documents to affected communities and stakeholders and hold widely publicized information meetings

in relevant local or regional languages.

Findings: The public comment period was well publicized as demonstrated by the la

submitted comments from the local community. Section G3.9 of the revised PDD describes the methods

used for publicizing the comment period, including how non

submitted for CCBA.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G3.10. Formalize a clear process for handling unresolved conflicts and grievances that arise

during project planning and implementation. The project design must include a process f

responding to and resolving community and other stakeholder grievances within a reasonable time

period. This grievance process must be publicized to communities and other stakeholders and must be

managed by a third party or mediator to prevent

attempt to resolve all reasonable grievances raised, and provide a written response to grievances within

30 days. Grievances and project responses must be documented.

Findings: Initially, no clear proces

that arise during project planning and implementation (see

However in response to an issued finding, a formal process was made and documented by

proponent in a document titled the “

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

22

documents to affected communities and stakeholders and hold widely publicized information meetings

in relevant local or regional languages.

The public comment period was well publicized as demonstrated by the la

submitted comments from the local community. Section G3.9 of the revised PDD describes the methods

used for publicizing the comment period, including how non-electronic comments were transcribed and

Yes No N/A

None

None

None

Formalize a clear process for handling unresolved conflicts and grievances that arise

during project planning and implementation. The project design must include a process f

responding to and resolving community and other stakeholder grievances within a reasonable time

period. This grievance process must be publicized to communities and other stakeholders and must be

managed by a third party or mediator to prevent any conflict of interest. Project management must

attempt to resolve all reasonable grievances raised, and provide a written response to grievances within

30 days. Grievances and project responses must be documented.

Initially, no clear processes was formalized for handling unresolved conflicts and grievances

that arise during project planning and implementation (see NCR Number 5 of 19 for October 20, 2009

However in response to an issued finding, a formal process was made and documented by

proponent in a document titled the “Wildlife Works Community Conflict Process.”

Yes No N/A

documents to affected communities and stakeholders and hold widely publicized information meetings

The public comment period was well publicized as demonstrated by the large number of

submitted comments from the local community. Section G3.9 of the revised PDD describes the methods

electronic comments were transcribed and

Formalize a clear process for handling unresolved conflicts and grievances that arise

during project planning and implementation. The project design must include a process for hearing,

responding to and resolving community and other stakeholder grievances within a reasonable time

period. This grievance process must be publicized to communities and other stakeholders and must be

any conflict of interest. Project management must

attempt to resolve all reasonable grievances raised, and provide a written response to grievances within

ses was formalized for handling unresolved conflicts and grievances

NCR Number 5 of 19 for October 20, 2009).

However in response to an issued finding, a formal process was made and documented by the project

Page 26: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 5 of 19 for October 20, 2009

Finding: The PDD contains a brief summary of the process for resolving disputes. However, the

proponent must formalize a plan to handle unresolved grievances that arise during the planning or

implementation of the project.

Proponent Response on October 26

Community Conflict Process to encapsulate the experience we have had over the years in resolving

disputes amicably within the communities of the Project Zone. We have updated the content of section

G3.10 of the PDD to refer to this document, and have included the text below. We beli

document together with our strong track record of excellent community relations demonstrates

categorically that we have a legitimate grievance and conflict resolution process, and we ask that you

close NCR#5.

Validator Response: The supplied docum

therefore adequate.

New Information Requests:

Opportunities for Improvement:

Indicator G3.11. Demonstrate that financial mechanisms adopted, including projected revenues from

emissions reductions and other sources, are likely to provide an adequate flow of funds for project

implementation and to achieve the anticipated climate, community and biodiversity benefits.

Findings: Detailed information regarding the financial mechanisms for project implementation were

absent from the initial PDD (see NCR Number 6 of 19 for October 20, 2009

initial finding, the project proponent supplied a detailed cash flo

adequate flow of funds for project implementation. The supplied analysis included the costs and

revenues of all project activities and therefore inherently shows that the anticipated climate, community

and biodiversity benefits can be achieved by the adopted financial mechanisms.

Conformance:

Non-Conformity Reports:

NCR Number 6 of 19 for October 20, 2009

Finding: The project proponent must provide a document to validate the adequacy of the flow of funds

for project implementation and the financial health of the implementing organization. Include all

expected revenues and estimated costs for project actives over time. The document must be of

sufficient detail for evaluation by a third party.

Proponent Response on October 28

Validators a detailed spreadsheet of the first two years cash flow for the project, indicating there will be

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

23

NCR Number 5 of 19 for October 20, 2009

The PDD contains a brief summary of the process for resolving disputes. However, the

proponent must formalize a plan to handle unresolved grievances that arise during the planning or

October 26, 2009: We have created a new document, the Wildlife Works

to encapsulate the experience we have had over the years in resolving

disputes amicably within the communities of the Project Zone. We have updated the content of section

G3.10 of the PDD to refer to this document, and have included the text below. We beli

document together with our strong track record of excellent community relations demonstrates

categorically that we have a legitimate grievance and conflict resolution process, and we ask that you

The supplied document is a formal plan to handle unresolved grievances and it

None

None

Demonstrate that financial mechanisms adopted, including projected revenues from

ions reductions and other sources, are likely to provide an adequate flow of funds for project

implementation and to achieve the anticipated climate, community and biodiversity benefits.

Detailed information regarding the financial mechanisms for project implementation were

NCR Number 6 of 19 for October 20, 2009). However

, the project proponent supplied a detailed cash flow analysis that demonstrated an

adequate flow of funds for project implementation. The supplied analysis included the costs and

revenues of all project activities and therefore inherently shows that the anticipated climate, community

fits can be achieved by the adopted financial mechanisms.

Yes No N/A

NCR Number 6 of 19 for October 20, 2009

The project proponent must provide a document to validate the adequacy of the flow of funds

and the financial health of the implementing organization. Include all

expected revenues and estimated costs for project actives over time. The document must be of

sufficient detail for evaluation by a third party.

October 28, 2009: Text added to Section G3.11 - We have sent the Project

Validators a detailed spreadsheet of the first two years cash flow for the project, indicating there will be

The PDD contains a brief summary of the process for resolving disputes. However, the project

proponent must formalize a plan to handle unresolved grievances that arise during the planning or

We have created a new document, the Wildlife Works

to encapsulate the experience we have had over the years in resolving

disputes amicably within the communities of the Project Zone. We have updated the content of section

G3.10 of the PDD to refer to this document, and have included the text below. We believe this

document together with our strong track record of excellent community relations demonstrates

categorically that we have a legitimate grievance and conflict resolution process, and we ask that you

ent is a formal plan to handle unresolved grievances and it

Demonstrate that financial mechanisms adopted, including projected revenues from

ions reductions and other sources, are likely to provide an adequate flow of funds for project

implementation and to achieve the anticipated climate, community and biodiversity benefits.

Detailed information regarding the financial mechanisms for project implementation were

. However subsequent to an

w analysis that demonstrated an

adequate flow of funds for project implementation. The supplied analysis included the costs and

revenues of all project activities and therefore inherently shows that the anticipated climate, community

The project proponent must provide a document to validate the adequacy of the flow of funds

and the financial health of the implementing organization. Include all

expected revenues and estimated costs for project actives over time. The document must be of

We have sent the Project

Validators a detailed spreadsheet of the first two years cash flow for the project, indicating there will be

Page 27: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

a large surplus of funds at the end of year 2, and showing the steady state finances for a

project from 2011 and onwards. The revenues in the cash flow are based on an actual transaction to sell

precertified carbon credits that is in the final stages and will close before end November 2009, so there

is very little speculation about this cash flow.

This cash flow matches the Project Implementation Schedule to be provided to the Validator under NIR

#2, and to support this cash flow document, we have also sent the Validator the following documents

which will demonstrate that we have extremely detailed knowledge of what the cap ex costs are to

accomplish the various project activities we are committing to in the implementation schedule;

1) Factory Addition Cell 2 Cost - EcoFactory Expansion Costing for Dye and Screen Print House

2) WW Shade House Costing – Provides cost of building additional shade house at Rukinga and also cost

of each of the 5 community nurseries we will build in the Villages

3) Bungule Guard Post Costing – provides the cost of adding a new Ranger Station to mon

boundary of the Project Area

4) Typical Classroom Budget – budget indicating that our $10K a year school construction maintenance

budget would be adequate to build a new classroom every year if that is what the community wanted.

We have revised sections 3.11 and 4.7 to include the text above and to reference these documents sent

to the validator. As we have indicated in the past this financial data is commercially sensitive and we ask

that it not become a part of the public record of the our CCB

We believe that this new information provided to the Validator clearly shows that the project has the

financial means to carry out the project activities, and we believe this is a more than adequate response

to your finding and we ask that you consid

Validator Response: The supplied cash flow analysis demonstrates that the adopted financial

mechanisms provide an adequate flow of funds.

New Information Requests:

Opportunities for Improvement:

3.2.4. G4 – Management Capacity

The success of a project depends upon the competence of the implementing management team.

Projects that include a significant capacity

likely to sustain the positive outcomes generated by the project and have them replicated elsewhere.

Best practices for project management include: local stakeho

safety and a clear process for handling grievances.

Indicators

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

24

a large surplus of funds at the end of year 2, and showing the steady state finances for a

project from 2011 and onwards. The revenues in the cash flow are based on an actual transaction to sell

precertified carbon credits that is in the final stages and will close before end November 2009, so there

bout this cash flow.

This cash flow matches the Project Implementation Schedule to be provided to the Validator under NIR

#2, and to support this cash flow document, we have also sent the Validator the following documents

ve extremely detailed knowledge of what the cap ex costs are to

accomplish the various project activities we are committing to in the implementation schedule;

EcoFactory Expansion Costing for Dye and Screen Print House

Provides cost of building additional shade house at Rukinga and also cost

of each of the 5 community nurseries we will build in the Villages

provides the cost of adding a new Ranger Station to mon

budget indicating that our $10K a year school construction maintenance

budget would be adequate to build a new classroom every year if that is what the community wanted.

sections 3.11 and 4.7 to include the text above and to reference these documents sent

to the validator. As we have indicated in the past this financial data is commercially sensitive and we ask

blic record of the our CCB PDD.

We believe that this new information provided to the Validator clearly shows that the project has the

financial means to carry out the project activities, and we believe this is a more than adequate response

to your finding and we ask that you consider this finding NCR#6 closed.

The supplied cash flow analysis demonstrates that the adopted financial

mechanisms provide an adequate flow of funds.

None

None

Capacity and Best Practices

The success of a project depends upon the competence of the implementing management team.

Projects that include a significant capacity-building (training, skill building, etc.) component are more

outcomes generated by the project and have them replicated elsewhere.

Best practices for project management include: local stakeholder employment, worker rights,

safety and a clear process for handling grievances.

a large surplus of funds at the end of year 2, and showing the steady state finances for a full year of the

project from 2011 and onwards. The revenues in the cash flow are based on an actual transaction to sell

precertified carbon credits that is in the final stages and will close before end November 2009, so there

This cash flow matches the Project Implementation Schedule to be provided to the Validator under NIR

#2, and to support this cash flow document, we have also sent the Validator the following documents

ve extremely detailed knowledge of what the cap ex costs are to

accomplish the various project activities we are committing to in the implementation schedule;

EcoFactory Expansion Costing for Dye and Screen Print House

Provides cost of building additional shade house at Rukinga and also cost

provides the cost of adding a new Ranger Station to monitor the SE

budget indicating that our $10K a year school construction maintenance

budget would be adequate to build a new classroom every year if that is what the community wanted.

sections 3.11 and 4.7 to include the text above and to reference these documents sent

to the validator. As we have indicated in the past this financial data is commercially sensitive and we ask

We believe that this new information provided to the Validator clearly shows that the project has the

financial means to carry out the project activities, and we believe this is a more than adequate response

The supplied cash flow analysis demonstrates that the adopted financial

The success of a project depends upon the competence of the implementing management team.

building (training, skill building, etc.) component are more

outcomes generated by the project and have them replicated elsewhere.

lder employment, worker rights, worker

Page 28: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

The project proponents must:

Indicator G4.1. Identify a single project proponent which is responsible for the project’s design and

implementation. If multiple organizations or individuals are involved in the project’s

implementation the governance structure, rol

individuals involved must also be described.

Findings: The revised PDD identifies a single project proponent which is responsible for the project’s

design and implementation, Wildlife Works. Subseq

7 of 19 for October 20, 2009), the roles and responsibilities of each individual are also presented in

Section G4.1 of the PDD.

Conformance:

Non-Conformity Reports:

NCR Number 7 of 19 for October 20, 2009

Finding: The PDD describes some of the organizations responsible for project design. Also provide a

description of the individuals responsible for project implementation including their roles and

responsibilities.

Proponent Response on October 29

text below.

We believe that this new information provided to the Validator

your finding and meets the Standard and we ask that you consider this finding NCR#7 closed.

Validator Response: The revised sections now provide an adequate description of all individual’s

responsibilities for project implementation.

New Information Requests:

Opportunities for Improvement:

Indicator G4.2. Document key technical skills that will be re

including community engagement, biodiversity assessment and

skills. Document the management team’s expertise and prior experience

management projects at the scale of this project. If relevant experience is

either demonstrate how other organizations will be partnered with to

recruitment strategy to fill the gaps.

Findings: Section G4.2 of the revised PDD documents

successfully implement the project. Initially, the PDD lacked information about the management team’s

expertise and prior experience implementing land management projects at the scale of this project (see

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

25

Identify a single project proponent which is responsible for the project’s design and

implementation. If multiple organizations or individuals are involved in the project’s

implementation the governance structure, roles and responsibilities of each of the organizations or

individuals involved must also be described.

The revised PDD identifies a single project proponent which is responsible for the project’s

design and implementation, Wildlife Works. Subsequent to a finding on this indicator (see

he roles and responsibilities of each individual are also presented in

Yes No N/A

7 of 19 for October 20, 2009

The PDD describes some of the organizations responsible for project design. Also provide a

description of the individuals responsible for project implementation including their roles and

October 29, 2009: We have revised sections G4.1 of the PDD to include the

We believe that this new information provided to the Validator is a more than adequate response to

your finding and meets the Standard and we ask that you consider this finding NCR#7 closed.

The revised sections now provide an adequate description of all individual’s

implementation.

None

None

Document key technical skills that will be required to implement the project

including community engagement, biodiversity assessment and carbon measurement and

skills. Document the management team’s expertise and prior experience implementing land

management projects at the scale of this project. If relevant experience is lacking, the proponents must

organizations will be partnered with to support the project or have a

recruitment strategy to fill the gaps.

Section G4.2 of the revised PDD documents the technical skills that will be required to

successfully implement the project. Initially, the PDD lacked information about the management team’s

implementing land management projects at the scale of this project (see

Identify a single project proponent which is responsible for the project’s design and

development and

the organizations or

The revised PDD identifies a single project proponent which is responsible for the project’s

uent to a finding on this indicator (see NCR Number

he roles and responsibilities of each individual are also presented in

The PDD describes some of the organizations responsible for project design. Also provide a

description of the individuals responsible for project implementation including their roles and

We have revised sections G4.1 of the PDD to include the

is a more than adequate response to

your finding and meets the Standard and we ask that you consider this finding NCR#7 closed.

The revised sections now provide an adequate description of all individual’s

quired to implement the project successfully,

carbon measurement and monitoring

implementing land

lacking, the proponents must

support the project or have a

the technical skills that will be required to

successfully implement the project. Initially, the PDD lacked information about the management team’s

implementing land management projects at the scale of this project (see

Page 29: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 8 of 19 for October 20, 2009

amended to include this information. The expertise and prior experience of the management team

seems to be adequate to the successful implementation of this pro

Conformance:

Non-Conformity Reports:

NCR Number 8 of 19 for October 20, 2009

Finding: Some of the individuals and their technical skills are provided in the PDD. However, there are

several other key technical skills that

mentioned the PDD. Also document the expertise and prior experience of the management team with

respect to land management projects.

Proponent Response on October 26

the PDD, and have included the text below. We believe this demonstrates categorically that we have

assembled the skills needed to continue to have success with this project into the future, and we ask

that you close NCR#8.

Validator Response: The amended PDD is now adequate with respect to this finding.

New Information Requests:

Opportunities for Improvement:

Indicator G4.3. Include a plan to provide orientation and training for the project’s

relevant people from the communities with an objective of building locally useful skills and knowledge

to increase local participation in project implementation. These capacity building efforts should

wide range of people in the communities, including minority and underrepresented

training will be passed on to new workers when there is staff turnover, so

lost.

Findings: The revised PDD contains information and references to orient

project’s employees. Initially, documented orientation and

the employees of the project (see NCR Number 9 of 19 for October 20, 2009

on this indicator, training manual were provided and references to the training manual were made in

the revised PDD. It was also noted that the project management could instate a documented policy to

include local community members in management positions as indicated by managem

site visit (see OFI Number 3 of 4 for October 20, 2009

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

26

Number 8 of 19 for October 20, 2009). Subsequent to a finding on this indicator, the PDD was

amended to include this information. The expertise and prior experience of the management team

seems to be adequate to the successful implementation of this project given the project’s size and scale.

Yes No N/A

NCR Number 8 of 19 for October 20, 2009

Some of the individuals and their technical skills are provided in the PDD. However, there are

several other key technical skills that are required to implement some of the project actives that are not

mentioned the PDD. Also document the expertise and prior experience of the management team with

respect to land management projects.

October 26, 2009: We have significantly updated the content of section 4.2 of

the PDD, and have included the text below. We believe this demonstrates categorically that we have

assembled the skills needed to continue to have success with this project into the future, and we ask

The amended PDD is now adequate with respect to this finding.

None

None

Include a plan to provide orientation and training for the project’s

from the communities with an objective of building locally useful skills and knowledge

ncrease local participation in project implementation. These capacity building efforts should

unities, including minority and underrepresented groups. Identify how

training will be passed on to new workers when there is staff turnover, so that local capacity will not be

The revised PDD contains information and references to orientation and training for the

documented orientation and training information was absent for most of

NCR Number 9 of 19 for October 20, 2009). Subsequent to a finding

ing manual were provided and references to the training manual were made in

the revised PDD. It was also noted that the project management could instate a documented policy to

include local community members in management positions as indicated by managem

OFI Number 3 of 4 for October 20, 2009).

Yes No N/A

). Subsequent to a finding on this indicator, the PDD was

amended to include this information. The expertise and prior experience of the management team

ject given the project’s size and scale.

Some of the individuals and their technical skills are provided in the PDD. However, there are

are required to implement some of the project actives that are not

mentioned the PDD. Also document the expertise and prior experience of the management team with

icantly updated the content of section 4.2 of

the PDD, and have included the text below. We believe this demonstrates categorically that we have

assembled the skills needed to continue to have success with this project into the future, and we ask

Include a plan to provide orientation and training for the project’s employees and

from the communities with an objective of building locally useful skills and knowledge

ncrease local participation in project implementation. These capacity building efforts should target a

groups. Identify how

that local capacity will not be

ation and training for the

ing information was absent for most of

). Subsequent to a finding

ing manual were provided and references to the training manual were made in

the revised PDD. It was also noted that the project management could instate a documented policy to

include local community members in management positions as indicated by management during the

Page 30: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 9 of 19 for October 20, 2009

Finding: The project proponents have includ

exists for training rangers, greenhouse staff or management positions. Please provide training plans for

all project employees. Also, indicate how community member will be given a fair chance to fil

for which they can be trained.

Proponent Response on October 24

Wildlife Works Rangers and the Organic Greenhouse Project and on review we believe them to still be of

excellent quality, addressing all aspects of those jobs including hazards and safety precautions. We have

submitted those documents electronically for your review and believe that this is a more than

acceptable response to this aspect of the finding.

With regard to the other aspect of the finding, it is our policy to always give preference for any job

position to members of the local community. This includes management roles. At present 100% of non

management roles are currently filled with local community members.

However as stated above we were unable to find local community members with the skills and

experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing

Factory Manager. As a result we hired 1 English expatriate, Rob Dodson wit

area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic

greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management

roles, Paschal Mulonzya (accountant), and Daniel Munyao (Sewing Factory Manager).

We believe in loyalty to our employees and as such as long as those three individuals continue to

perform their job responsibilities well, they will be retained. However, we do already have local peopl

filling three additional management roles within the Project/Company.

1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita

from the immediate community and was one of our first employees and was trained in

now holds – We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site

Manager, and he is being groomed for that role.

2) Joseph Mwanganda – Greenhouse and Jojoba Project Manager

Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project

Zone.Joseph has a wide range of Agricultural skills and experience.

3) Eric Sagwe – Head Wildlife Ranger

promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally

hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father

passed away unexpectedly. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different

region of Kenya, who had been brought in at the start of our Project because he had specific knowledge

and experience of how to set up and manage a Ranger force in the Kenyan bush,

poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

27

NCR Number 9 of 19 for October 20, 2009

The project proponents have included a plan for training factory workers, however no plan

exists for training rangers, greenhouse staff or management positions. Please provide training plans for

all project employees. Also, indicate how community member will be given a fair chance to fil

October 24, 2009: We have located the original training programs for both

Wildlife Works Rangers and the Organic Greenhouse Project and on review we believe them to still be of

lity, addressing all aspects of those jobs including hazards and safety precautions. We have

submitted those documents electronically for your review and believe that this is a more than

acceptable response to this aspect of the finding.

other aspect of the finding, it is our policy to always give preference for any job

position to members of the local community. This includes management roles. At present 100% of non

management roles are currently filled with local community members.

ver as stated above we were unable to find local community members with the skills and

experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing

Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge of the

area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic

greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management

countant), and Daniel Munyao (Sewing Factory Manager).

We believe in loyalty to our employees and as such as long as those three individuals continue to

perform their job responsibilities well, they will be retained. However, we do already have local peopl

filling three additional management roles within the Project/Company.

1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita

from the immediate community and was one of our first employees and was trained in

We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site

Manager, and he is being groomed for that role.

Greenhouse and Jojoba Project Manager – Joseph is a consultant to

Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project

Zone.Joseph has a wide range of Agricultural skills and experience.

Head Wildlife Ranger - Eric is a perfect example of our policy to hire locally and to

promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally

hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father

. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different

region of Kenya, who had been brought in at the start of our Project because he had specific knowledge

and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform anti

poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.

ed a plan for training factory workers, however no plan

exists for training rangers, greenhouse staff or management positions. Please provide training plans for

all project employees. Also, indicate how community member will be given a fair chance to fill positions

We have located the original training programs for both

Wildlife Works Rangers and the Organic Greenhouse Project and on review we believe them to still be of

lity, addressing all aspects of those jobs including hazards and safety precautions. We have

submitted those documents electronically for your review and believe that this is a more than

other aspect of the finding, it is our policy to always give preference for any job

position to members of the local community. This includes management roles. At present 100% of non

ver as stated above we were unable to find local community members with the skills and

experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing

h extensive knowledge of the

area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic

greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management

We believe in loyalty to our employees and as such as long as those three individuals continue to

perform their job responsibilities well, they will be retained. However, we do already have local people

1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita

from the immediate community and was one of our first employees and was trained into the position he

We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site

Joseph is a consultant to Wildlife

Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project

licy to hire locally and to

promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally

hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father

. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different

region of Kenya, who had been brought in at the start of our Project because he had specific knowledge

to patrol, perform anti

Page 31: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

We appreciate the communities desire to fill management roles within the Company/ Project and are

excited at their enthusiasm to do so. We will c

such times as management roles become available we will certainly consider local candidates fist, but

for the future success of the project we must always meet job skill and e

We believe this adequately addresses the finding NCR #9, and that this NCR should now be closed.

Validator Response: The added plans for

are adequate.

New Information Requests:

Opportunities for Improvement:

OFI Number 3 of 4 for October 20, 2009

Finding: Based on community meetings and interviews, the project proponent should consider

incorporating community members to be trained in management roles.

Proponent Response on October 24

to members of the local community. This includes management roles. 100% of non management roles

are currently filled with local community members.

However as stated above we were unable to find local community members with the skills and

experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing

Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge o

area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic

greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management

roles, Paschal Mulonzya (accountant), and Daniel M

We believe in loyalty to our employees and as such as long as those three individuals continue to

perform their job responsibilities well, they will be retained. However, we do already have local people

filling two additional management roles within the Project/Company.

1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita

from the immediate community and was one of our first employees and was trained into the position he

now holds – We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site

Manager, and he is being groomed for that role.

2) Joseph Mwanganda – Greenhouse and Jojoba Project Manager

Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project

Zone.

Joseph has a wide range of Agricultural skills and experience.

3) Eric Sagwe – Head Wildlife Ranger

promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

28

We appreciate the communities desire to fill management roles within the Company/ Project and are

excited at their enthusiasm to do so. We will continue to prioritize local employment and in the future at

such times as management roles become available we will certainly consider local candidates fist, but

for the future success of the project we must always meet job skill and experience requirement

We believe this adequately addresses the finding NCR #9, and that this NCR should now be closed.

The added plans for training rangers, greenhouse staff or management positions

None

OFI Number 3 of 4 for October 20, 2009

Based on community meetings and interviews, the project proponent should consider

incorporating community members to be trained in management roles.

ctober 24, 2009: It is our policy to always give preference for any job position

to members of the local community. This includes management roles. 100% of non management roles

are currently filled with local community members.

were unable to find local community members with the skills and

experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing

Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge o

area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic

greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management

roles, Paschal Mulonzya (accountant), and Daniel Munyao (Sewing Factory Manager).

We believe in loyalty to our employees and as such as long as those three individuals continue to

perform their job responsibilities well, they will be retained. However, we do already have local people

l management roles within the Project/Company.

1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita

from the immediate community and was one of our first employees and was trained into the position he

We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site

Manager, and he is being groomed for that role.

Greenhouse and Jojoba Project Manager – Joseph is a consultant to Wildlife

ion to his role as Agricultural Outreach Agent for the Government. He is from the Project

cultural skills and experience.

Head Wildlife Ranger - Eric is a perfect example of our policy to hire locally an

promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally

We appreciate the communities desire to fill management roles within the Company/ Project and are

ontinue to prioritize local employment and in the future at

such times as management roles become available we will certainly consider local candidates fist, but

xperience requirements as well.

We believe this adequately addresses the finding NCR #9, and that this NCR should now be closed.

training rangers, greenhouse staff or management positions

Based on community meetings and interviews, the project proponent should consider

It is our policy to always give preference for any job position

to members of the local community. This includes management roles. 100% of non management roles

were unable to find local community members with the skills and

experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing

Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge of the

area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic

greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management

We believe in loyalty to our employees and as such as long as those three individuals continue to

perform their job responsibilities well, they will be retained. However, we do already have local people

1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita

from the immediate community and was one of our first employees and was trained into the position he

We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site

Joseph is a consultant to Wildlife

ion to his role as Agricultural Outreach Agent for the Government. He is from the Project

Eric is a perfect example of our policy to hire locally and to

promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally

Page 32: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father

passed away unexpectedly. At that time the Head

region of Kenya, who had been brought in at the start of our Project because he had specific knowledge

and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform ant

poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.

We appreciate the communities desire to fill management roles within the Company/ Project and are

excited at their enthusiasm to do so. We will continue to prioritize lo

such times as management roles become available we will certainly consider local candidates fist, but

for the future success of the project we must always meet job skill and e

We believe this adequately addresses the finding OFI #3, and that this OFI should now be closed.

Validator Response: NA

Indicator G.4.4. Show that people from the communities will be given an equal opportunity to fill all

employment positions (including management)

must explain how employees will be selected for positions and where relevant, must indicate how local

community members, including women and other potentially underrepresented groups, will be

fair chance to fill positions for which they can be trained.

Findings: The revised PDD and interviews conducted with management during the site visit show that

people from the communities will be given an equal opportunity to fill all employment positions

However, no formal and documented policy was in place to include local people for the communities

into management roles as verbally indicated during the site visit (see

2009). Further, local community members cannot be

trained if no training plans are available (see

the site visit, the majority shareholder of Rukinga Ranching Company indicated that shares are available

to the local community should they choose to invest in the company, however no formal policy was in

place to clearly document how shares can be purchased and at what price (see OFI

November 12, 2009).

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

OFI Number 1 of 1 for November 12, 2009

Finding: The project proponent has invited the community to acquire shares in Rukinga Ranching

Company. Likewise, on more than one occasion during the site visit, community members have

demonstrated an interest in acquiring shares. However, no clear policy regardi

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

29

hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father

passed away unexpectedly. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different

region of Kenya, who had been brought in at the start of our Project because he had specific knowledge

and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform ant

poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.

We appreciate the communities desire to fill management roles within the Company/ Project and are

excited at their enthusiasm to do so. We will continue to prioritize local employment and in the future at

such times as management roles become available we will certainly consider local candidates fist, but

for the future success of the project we must always meet job skill and experience requirements as well.

is adequately addresses the finding OFI #3, and that this OFI should now be closed.

Show that people from the communities will be given an equal opportunity to fill all

positions (including management) if the job requirements are met. Project proponents

explain how employees will be selected for positions and where relevant, must indicate how local

community members, including women and other potentially underrepresented groups, will be

chance to fill positions for which they can be trained.

The revised PDD and interviews conducted with management during the site visit show that

people from the communities will be given an equal opportunity to fill all employment positions

However, no formal and documented policy was in place to include local people for the communities

into management roles as verbally indicated during the site visit (see OFI Number 3 of 4 for October 20,

). Further, local community members cannot be filled into positions in which they cannot be

trained if no training plans are available (see NCR Number 9 of 19 for October 20, 2009

the site visit, the majority shareholder of Rukinga Ranching Company indicated that shares are available

to the local community should they choose to invest in the company, however no formal policy was in

place to clearly document how shares can be purchased and at what price (see OFI Number

Yes No N/A

See NCR Number 9 of 19 for October 20, 2009

None

See OFI Number 3 of 4 for October 20, 2009

for November 12, 2009

The project proponent has invited the community to acquire shares in Rukinga Ranching

Company. Likewise, on more than one occasion during the site visit, community members have

demonstrated an interest in acquiring shares. However, no clear policy regarding the requirements for

hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father

Ranger was a Kenyan, Ekiru Mirimuk from a different

region of Kenya, who had been brought in at the start of our Project because he had specific knowledge

and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform anti

We appreciate the communities desire to fill management roles within the Company/ Project and are

cal employment and in the future at

such times as management roles become available we will certainly consider local candidates fist, but

xperience requirements as well.

is adequately addresses the finding OFI #3, and that this OFI should now be closed.

Show that people from the communities will be given an equal opportunity to fill all

if the job requirements are met. Project proponents

explain how employees will be selected for positions and where relevant, must indicate how local

community members, including women and other potentially underrepresented groups, will be given a

The revised PDD and interviews conducted with management during the site visit show that

people from the communities will be given an equal opportunity to fill all employment positions.

However, no formal and documented policy was in place to include local people for the communities

OFI Number 3 of 4 for October 20,

filled into positions in which they cannot be

NCR Number 9 of 19 for October 20, 2009). Lastly, during

the site visit, the majority shareholder of Rukinga Ranching Company indicated that shares are available

to the local community should they choose to invest in the company, however no formal policy was in

Number 1 of 1 for

ber 9 of 19 for October 20, 2009

The project proponent has invited the community to acquire shares in Rukinga Ranching

Company. Likewise, on more than one occasion during the site visit, community members have

ng the requirements for

Page 33: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

purchase or availability of shares has been made by BenBo International (or Wildlife Works on behalf of

BenBo). Consider making and publicizing a policy regarding the transfer of shares to the local

community.

Proponent Response on December 9

under which BenBo International would be prepared to sell shares to the local shareholders or other

members of the local community would be a good idea, although we want to be clear

private company, and Ben Bo is certainly under no obligation to sell any of their shares. We made it

known to the Board of Directors of Rukinga Ranching Company in a Board Meeting held immediately

following the Special General Meeting on De

obtaining a clear statement of the terms and conditions under which Ben Bo would be prepared to sell

some or all of its shares to local community members. The issues are that there would have to be a fair

price set, based on the price that outside third parties have expressed a willingness to pay, and there

would have to be a minimum number of shares per transaction, to justify the overhead expense of

legally papering the transaction. Wildlife Works has un

analysis at the next Annual General Meeting of Shareholders in Q1 2010 or at an earlier date, at such

time as a third party has made a credible offer to purchase shares from Ben Bo.

In addition we will undertake to contact the other shareholders who are not residents of the local

community to see whether any of them would be willing to sell their shares to local community

members and if so under what terms and conditions. Again we will undertake to present at the

AGM any opportunities that arise for local community members to purchase shares from other

shareholders.

We consider this to be an appropriate and complete response to this OFI and ask that this finding be

closed.

Validator Response: NA

Indicator G4.5. Submit a list of all relevant laws and regulations covering worker’s rights in the host

country.

Describe how the project will inform workers about their rights. Provide assurance that the

meets or exceeds all applicable laws and/or regula

demonstrate how compliance is achieved.

Findings: A complete list of relevant l

revised PDD (see NCR Number 10 of 19 for October 20, 2009

employees of these laws in a statement within employee contracts. Evidence was also collected from

government audits indicating that the project proponents are currently in compliance with these laws.

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

30

purchase or availability of shares has been made by BenBo International (or Wildlife Works on behalf of

BenBo). Consider making and publicizing a policy regarding the transfer of shares to the local

December 9, 2009: We accept that a clear policy regarding the conditions

under which BenBo International would be prepared to sell shares to the local shareholders or other

members of the local community would be a good idea, although we want to be clear that this is a

private company, and Ben Bo is certainly under no obligation to sell any of their shares. We made it

known to the Board of Directors of Rukinga Ranching Company in a Board Meeting held immediately

following the Special General Meeting on December 9th 2009 that we would approach Ben Bo about

obtaining a clear statement of the terms and conditions under which Ben Bo would be prepared to sell

some or all of its shares to local community members. The issues are that there would have to be a fair

price set, based on the price that outside third parties have expressed a willingness to pay, and there

would have to be a minimum number of shares per transaction, to justify the overhead expense of

legally papering the transaction. Wildlife Works has undertaken to present the results of BenBo’s

analysis at the next Annual General Meeting of Shareholders in Q1 2010 or at an earlier date, at such

time as a third party has made a credible offer to purchase shares from Ben Bo.

to contact the other shareholders who are not residents of the local

community to see whether any of them would be willing to sell their shares to local community

members and if so under what terms and conditions. Again we will undertake to present at the

AGM any opportunities that arise for local community members to purchase shares from other

We consider this to be an appropriate and complete response to this OFI and ask that this finding be

Submit a list of all relevant laws and regulations covering worker’s rights in the host

Describe how the project will inform workers about their rights. Provide assurance that the

meets or exceeds all applicable laws and/or regulations covering worker rights and,

demonstrate how compliance is achieved.

A complete list of relevant laws and regulations covering worker’s rights is provide

NCR Number 10 of 19 for October 20, 2009). The project proponent notifies

employees of these laws in a statement within employee contracts. Evidence was also collected from

government audits indicating that the project proponents are currently in compliance with these laws.

Yes No N/A

purchase or availability of shares has been made by BenBo International (or Wildlife Works on behalf of

BenBo). Consider making and publicizing a policy regarding the transfer of shares to the local

We accept that a clear policy regarding the conditions

under which BenBo International would be prepared to sell shares to the local shareholders or other

that this is a

private company, and Ben Bo is certainly under no obligation to sell any of their shares. We made it

known to the Board of Directors of Rukinga Ranching Company in a Board Meeting held immediately

cember 9th 2009 that we would approach Ben Bo about

obtaining a clear statement of the terms and conditions under which Ben Bo would be prepared to sell

some or all of its shares to local community members. The issues are that there would have to be a fair

price set, based on the price that outside third parties have expressed a willingness to pay, and there

would have to be a minimum number of shares per transaction, to justify the overhead expense of

dertaken to present the results of BenBo’s

analysis at the next Annual General Meeting of Shareholders in Q1 2010 or at an earlier date, at such

to contact the other shareholders who are not residents of the local

community to see whether any of them would be willing to sell their shares to local community

members and if so under what terms and conditions. Again we will undertake to present at the next

AGM any opportunities that arise for local community members to purchase shares from other

We consider this to be an appropriate and complete response to this OFI and ask that this finding be

Submit a list of all relevant laws and regulations covering worker’s rights in the host

Describe how the project will inform workers about their rights. Provide assurance that the project

and, where relevant,

aws and regulations covering worker’s rights is provided in the

The project proponent notifies

employees of these laws in a statement within employee contracts. Evidence was also collected from

government audits indicating that the project proponents are currently in compliance with these laws.

Page 34: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 10 of 19 for October 20, 2009

Finding: The project proponent has provided assurance that the project meets or exceeds local laws,

evidenced by government audits. However, the project proponent must also submit a list of all relevant

laws and regulations covering workers' rights.

Proponent Response on October 24

relevant employment laws including the new Labour

described how we know we are in compliance of each of the relevant laws. We believe that submission

of the updated text from the PDD below provides a complete and appropriate response to this NCR and

that this NCR should now be closed.

Validator Response: The revised PDD now contains a list of all relevant laws.

New Information Requests:

Opportunities for Improvement:

Indicator G4.6. Comprehensively assess situations and occupations that pose a substantial risk to

worker safety. A plan must be in place to inform workers of risks and to explain how to minimize such

risks. Where worker safety cannot be guaranteed, project proponents mus

minimized using best work practices.

Findings: Upon review of the original PDD and conclusion of the site visit, there was in adequate

evidence to support conformance to this indicator (see

Upon response to a finding for this indicator, the

comprehensive assessment of situations that pose substantial risk to employees. These manuals also

explain how to minimize risks to worker’s safety.

Conformance: Yes

Non-Conformity Reports:

NCR Number 11 of 19 for October 20, 2009

Finding: Provide a comprehensive assessment of situations and occupations that pose substantial risk,

including those for greenhouse workers and rangers. Document a plan to inform workers of r

explain how to minimize risks to workers' safety.

Proponent Response on October 26

Factory, Greenhouse and Rangers carry complete safety sections indicating risks and providing advice

and training in how to minimize risks. Soap Factory Training manual is published book on soap making

called “The SoapMaker’s Companion” by Susa

with our own worker safety guide also provided to the Validators. For such a small company we are in

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

31

NCR Number 10 of 19 for October 20, 2009

The project proponent has provided assurance that the project meets or exceeds local laws,

evidenced by government audits. However, the project proponent must also submit a list of all relevant

nd regulations covering workers' rights.

October 24, 2009: We have amended Section G4.5 of the PDD to include ALL

relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly

described how we know we are in compliance of each of the relevant laws. We believe that submission

of the updated text from the PDD below provides a complete and appropriate response to this NCR and

NCR should now be closed.

The revised PDD now contains a list of all relevant laws.

None

None

Comprehensively assess situations and occupations that pose a substantial risk to

worker safety. A plan must be in place to inform workers of risks and to explain how to minimize such

risks. Where worker safety cannot be guaranteed, project proponents must show how the risks will be

minimized using best work practices.

Upon review of the original PDD and conclusion of the site visit, there was in adequate

evidence to support conformance to this indicator (see NCR Number 11 of 19 for October 20,

Upon response to a finding for this indicator, the supplied training manuals each provide a

comprehensive assessment of situations that pose substantial risk to employees. These manuals also

explain how to minimize risks to worker’s safety.

Yes No N/A

NCR Number 11 of 19 for October 20, 2009

Provide a comprehensive assessment of situations and occupations that pose substantial risk,

including those for greenhouse workers and rangers. Document a plan to inform workers of r

explain how to minimize risks to workers' safety.

October 26, 2009: Training Manuals now provided to Validator

Factory, Greenhouse and Rangers carry complete safety sections indicating risks and providing advice

and training in how to minimize risks. Soap Factory Training manual is published book on soap making

called “The SoapMaker’s Companion” by Susan Miller Cavitch, but we have supplemented this book

with our own worker safety guide also provided to the Validators. For such a small company we are in

The project proponent has provided assurance that the project meets or exceeds local laws,

evidenced by government audits. However, the project proponent must also submit a list of all relevant

We have amended Section G4.5 of the PDD to include ALL

Relations Act of 2007, and we have explicitly

described how we know we are in compliance of each of the relevant laws. We believe that submission

of the updated text from the PDD below provides a complete and appropriate response to this NCR and

Comprehensively assess situations and occupations that pose a substantial risk to

worker safety. A plan must be in place to inform workers of risks and to explain how to minimize such

t show how the risks will be

Upon review of the original PDD and conclusion of the site visit, there was in adequate

NCR Number 11 of 19 for October 20, 2009).

supplied training manuals each provide a

comprehensive assessment of situations that pose substantial risk to employees. These manuals also

Provide a comprehensive assessment of situations and occupations that pose substantial risk,

including those for greenhouse workers and rangers. Document a plan to inform workers of risks and

Training Manuals now provided to Validator for Sewing

Factory, Greenhouse and Rangers carry complete safety sections indicating risks and providing advice

and training in how to minimize risks. Soap Factory Training manual is published book on soap making

n Miller Cavitch, but we have supplemented this book

with our own worker safety guide also provided to the Validators. For such a small company we are in

Page 35: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

rural Africa we consider these manuals and risks procedures to be more than adequate, and they have

allowed us to operate injury free for more than ten years. We ask that you close this NCR#11 at this

time.

Validator Response: The provided training manuals adequately address this finding.

New Information Requests: None

Opportunities for Improvement:

Indicator G4.7. Document the financial health of the implementing organization(s) to demonstrate that

financial resources budgeted will be adequate to implement the project.

Findings: The financial health of the implementing organization, Wildlife Works, is well documented in

the revised PDD and in a cash flow analysis (sees

flow analysis demonstrates that financial resources budgeted

project.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.2.5. G5 – Legal Status and Property Rights

The project must be based on a solid legal framework (e.g., appropriate contracts are in place) and the

project must satisfy applicable planning and regulatory requirements.

During the project design phase, the project proponents should communicate early on with relevant

local, regional and national authorities in order to allow adequate time to earn necessary approvals. The

project design should be sufficiently flexible to accommodate potential modifications that may arise as a

result of this process.

In the event of unresolved disputes over tenure or use rights to land or resources in the project zone,

the project should demonstrate how it will help to bring them to resolution so that there are no

unresolved disputes by the start of the project.

Indicators

Based on information about current property rights provided in

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

32

rural Africa we consider these manuals and risks procedures to be more than adequate, and they have

lowed us to operate injury free for more than ten years. We ask that you close this NCR#11 at this

The provided training manuals adequately address this finding.

None

None

Document the financial health of the implementing organization(s) to demonstrate that

financial resources budgeted will be adequate to implement the project.

The financial health of the implementing organization, Wildlife Works, is well documented in

the revised PDD and in a cash flow analysis (sees NCR Number 6 of 19 for October 20, 2009

flow analysis demonstrates that financial resources budgeted will be adequate to implement the

Yes No N/A

See NCR Number 6 of 19 for October 20, 2009

None

None

Legal Status and Property Rights

solid legal framework (e.g., appropriate contracts are in place) and the

project must satisfy applicable planning and regulatory requirements.

During the project design phase, the project proponents should communicate early on with relevant

l and national authorities in order to allow adequate time to earn necessary approvals. The

project design should be sufficiently flexible to accommodate potential modifications that may arise as a

es over tenure or use rights to land or resources in the project zone,

the project should demonstrate how it will help to bring them to resolution so that there are no

unresolved disputes by the start of the project.

urrent property rights provided in G1, the project proponents must:

rural Africa we consider these manuals and risks procedures to be more than adequate, and they have

lowed us to operate injury free for more than ten years. We ask that you close this NCR#11 at this

Document the financial health of the implementing organization(s) to demonstrate that

The financial health of the implementing organization, Wildlife Works, is well documented in

NCR Number 6 of 19 for October 20, 2009). The cash

will be adequate to implement the

NCR Number 6 of 19 for October 20, 2009

solid legal framework (e.g., appropriate contracts are in place) and the

During the project design phase, the project proponents should communicate early on with relevant

l and national authorities in order to allow adequate time to earn necessary approvals. The

project design should be sufficiently flexible to accommodate potential modifications that may arise as a

es over tenure or use rights to land or resources in the project zone,

the project should demonstrate how it will help to bring them to resolution so that there are no

, the project proponents must:

Page 36: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Indicator G5.1. Submit a list of all relevant national and local laws and regulations in the host country

and all applicable international treaties and agreements. Provide assurance that

with these and, where relevant, demonstrate how compliance is achieved.

Findings: The revised PDD contains a list of all relevant national and local laws and

no assurance was provided that the project will

October 20, 2009). Further, the project proponent did not document how compliance will be

demonstrated. In response to an initial finding for this indicator, the project proponent provided the

requested information.

Conformance:

Non-Conformity Reports:

New Information Requests:

NIR Number 3 of 5 for October 20, 2009

Finding: A list of applicable laws has been provided and compliance has been assured, however no

demonstration of compliance has been presented. The project proponent must explicitly demonstrate

how compliance is achieved where relevant.

Proponent Response on October 24

relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly

described how we know we are in compliance of each of the relevant laws. We believe that submission

of the updated PDD text below provides a complete and appropriate response to this NIR and that this

NIR should now be closed.

Validator Response: The amended PDD is adequate as i

comply with relevant national and local laws.

Opportunities for Improvement:

Indicator G5.2. Document that the project has approval from the appropriate authorities, including the

established formal and/or traditional authorities customarily required by the communities.

Findings: A signed conservation easement

authorities, including Rukinga Ranching Company. Interviews with the local authorities during the site

visit did not indicate any other approval is needed. Although the conservation easement clearly shows

that Rukinga Ranching Company has conveyed the climate and biological rights of

Wildlife Works, the project proponent,

Company gave their approval for the conservation easement. Based on guidance from CCBA, Wildlife

Works was required to confirm that inf

for November 12, 2009).

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

33

Submit a list of all relevant national and local laws and regulations in the host country

and all applicable international treaties and agreements. Provide assurance that the project will comply

with these and, where relevant, demonstrate how compliance is achieved.

The revised PDD contains a list of all relevant national and local laws and regulations. Initially,

no assurance was provided that the project will comply with these laws (see NIR Number 3 of 5 for

). Further, the project proponent did not document how compliance will be

demonstrated. In response to an initial finding for this indicator, the project proponent provided the

Yes No N/A

None

NIR Number 3 of 5 for October 20, 2009

A list of applicable laws has been provided and compliance has been assured, however no

demonstration of compliance has been presented. The project proponent must explicitly demonstrate

compliance is achieved where relevant.

October 24, 2009: We have amended Section G5.1 of the PDD to include ALL

relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly

are in compliance of each of the relevant laws. We believe that submission

of the updated PDD text below provides a complete and appropriate response to this NIR and that this

The amended PDD is adequate as it completely describes how the project will

comply with relevant national and local laws.

None

Document that the project has approval from the appropriate authorities, including the

or traditional authorities customarily required by the communities.

easement documents that the project has approval from the local

Ranching Company. Interviews with the local authorities during the site

visit did not indicate any other approval is needed. Although the conservation easement clearly shows

that Rukinga Ranching Company has conveyed the climate and biological rights of the project area to

Wildlife Works, the project proponent, it was unclear whether all shareholders of Rukinga Ranching

Company gave their approval for the conservation easement. Based on guidance from CCBA, Wildlife

Works was required to confirm that infact all shareholders support the project (see NCR Number

Submit a list of all relevant national and local laws and regulations in the host country

the project will comply

regulations. Initially,

NIR Number 3 of 5 for

). Further, the project proponent did not document how compliance will be

demonstrated. In response to an initial finding for this indicator, the project proponent provided the

A list of applicable laws has been provided and compliance has been assured, however no

demonstration of compliance has been presented. The project proponent must explicitly demonstrate

We have amended Section G5.1 of the PDD to include ALL

relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly

are in compliance of each of the relevant laws. We believe that submission

of the updated PDD text below provides a complete and appropriate response to this NIR and that this

t completely describes how the project will

Document that the project has approval from the appropriate authorities, including the

or traditional authorities customarily required by the communities.

documents that the project has approval from the local

Ranching Company. Interviews with the local authorities during the site

visit did not indicate any other approval is needed. Although the conservation easement clearly shows

the project area to

it was unclear whether all shareholders of Rukinga Ranching

Company gave their approval for the conservation easement. Based on guidance from CCBA, Wildlife

NCR Number 1 of 1

Page 37: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Conformance:

Non-Conformity Reports:

New Information Requests:

NIR Number 4 of 5 for October 20, 2009

Finding: The project proponent must provide a list of all shareholder owners whose rights the project

will affect. Please provide a copy of the signed conservation easement to document the free, prior,

informed and full consent of these shareholders for the project.

Proponent Response on October 24

time line of events leading to the unanimous approval by those Shareholders present at the February

13th 2009 AGM of Rukinga Ranching Company Ltd. to allow the Managing

project opportunity on Rukinga. We have included this text below, to avoid resending the entire PDD for

each finding response.

We have also provide you with a full list of all Shareholders currently known to the company (it is

possible that some of those Shareholders are deceased, and that family members are in the process of

acquiring Court papers granting them inheritance of the shares, but we will not be aware of this until

that process is complete and they present their proof

We have emailed you a copy of the presentation made to the Shareholders of Rukinga Ranching Co. Ltd

during the AGM of February 13th 2009 at which AGM they approved the pursuit of the Project, leading

to the signing of the Carbon Easement on February 15th 2009.

Finally we have provided you with a copy of the Carbon Easement signed between Rukinga

Company Ltd. and Wildlife Works, Inc. This Carbon Easement is also commercially sensitive, as it was

developed by Wildlife Works at significant expense, and we would ask the auditors and CCB NOT to post

this to the website.

We believe that as Rukinga is 100% of the land covered under the Project Area, and that it is Privately

owned by the Rukinga Ranching Company Ltd. that the information and documents provided above are

a complete response to the finding and therefore finding NIR #4 should be clo

Validator Response: The provided easement is adequate to satisfy this finding, however it is unclear

whether all shareholders of Rukinga Ranching Company support this easement (see

for November 12, 2009).

Opportunities for Improvement:

Indicator G5.3. Demonstrate with documented consultations and agreements that the project will not

encroach uninvited on private property, community property, or government property and has obtained

the free, prior, and informed consent of those whose rights will be affe

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

34

Yes No N/A

See NCR Number 1 of 1 for November 12, 2009

NIR Number 4 of 5 for October 20, 2009

proponent must provide a list of all shareholder owners whose rights the project

will affect. Please provide a copy of the signed conservation easement to document the free, prior,

informed and full consent of these shareholders for the project.

October 24, 2009: We have greatly expanded in the PDD in section G5.3 the

time line of events leading to the unanimous approval by those Shareholders present at the February

13th 2009 AGM of Rukinga Ranching Company Ltd. to allow the Managing Director to pursue the REDD

project opportunity on Rukinga. We have included this text below, to avoid resending the entire PDD for

We have also provide you with a full list of all Shareholders currently known to the company (it is

ossible that some of those Shareholders are deceased, and that family members are in the process of

acquiring Court papers granting them inheritance of the shares, but we will not be aware of this until

that process is complete and they present their proof of inheritance to the Company Secretary).

We have emailed you a copy of the presentation made to the Shareholders of Rukinga Ranching Co. Ltd

during the AGM of February 13th 2009 at which AGM they approved the pursuit of the Project, leading

g of the Carbon Easement on February 15th 2009.

Finally we have provided you with a copy of the Carbon Easement signed between Rukinga

Company Ltd. and Wildlife Works, Inc. This Carbon Easement is also commercially sensitive, as it was

developed by Wildlife Works at significant expense, and we would ask the auditors and CCB NOT to post

inga is 100% of the land covered under the Project Area, and that it is Privately

owned by the Rukinga Ranching Company Ltd. that the information and documents provided above are

a complete response to the finding and therefore finding NIR #4 should be closed.

The provided easement is adequate to satisfy this finding, however it is unclear

whether all shareholders of Rukinga Ranching Company support this easement (see NCR Number

None

Demonstrate with documented consultations and agreements that the project will not

encroach uninvited on private property, community property, or government property and has obtained

the free, prior, and informed consent of those whose rights will be affected by the project.

for November 12, 2009

proponent must provide a list of all shareholder owners whose rights the project

will affect. Please provide a copy of the signed conservation easement to document the free, prior,

We have greatly expanded in the PDD in section G5.3 the

time line of events leading to the unanimous approval by those Shareholders present at the February

Director to pursue the REDD

project opportunity on Rukinga. We have included this text below, to avoid resending the entire PDD for

We have also provide you with a full list of all Shareholders currently known to the company (it is

ossible that some of those Shareholders are deceased, and that family members are in the process of

acquiring Court papers granting them inheritance of the shares, but we will not be aware of this until

of inheritance to the Company Secretary).

We have emailed you a copy of the presentation made to the Shareholders of Rukinga Ranching Co. Ltd

during the AGM of February 13th 2009 at which AGM they approved the pursuit of the Project, leading

Finally we have provided you with a copy of the Carbon Easement signed between Rukinga Ranching

Company Ltd. and Wildlife Works, Inc. This Carbon Easement is also commercially sensitive, as it was

developed by Wildlife Works at significant expense, and we would ask the auditors and CCB NOT to post

inga is 100% of the land covered under the Project Area, and that it is Privately

owned by the Rukinga Ranching Company Ltd. that the information and documents provided above are

The provided easement is adequate to satisfy this finding, however it is unclear

NCR Number 1 of 1

Demonstrate with documented consultations and agreements that the project will not

encroach uninvited on private property, community property, or government property and has obtained

cted by the project.

Page 38: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Findings: The rights to the climate and biodiversity of the project area are owned by Wildlife Works and

were conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority

of shareholders affected this conveyance, it was initially unclear whether all shareholders supported the

transfer of their climate and biodiversity rights in the project area to Wildlife Works (see

of 1 for November 12, 2009). In response to a finding m

confirm the complete support of all Rukinga shareholders.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G5.4. Demonstrate that the project does not require the involuntary relocation of people or of

the activities important for the livelihoods and culture of the communities. If any relocation of

habitation or activities is undertaken within the terms of an agreeme

demonstrate that the agreement was made with the free, prior, and

concerned and includes provisions for just and fair compensation.

Findings: The project does not require the involuntary

project area as of the start date of the project.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator G5.5. Identify any illegal activities that could affect the project’s climate, community or

biodiversity impacts (e.g., logging) taking place in the project zone and descri

help to reduce these activities so that project benefits are not derived from illegal activities.

Findings: The two major illegal activities that could affect the project’s benefits are harvesting of

firewood and poaching. Both of these activities

in the project zone as a result of this project

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

35

The rights to the climate and biodiversity of the project area are owned by Wildlife Works and

were conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority

conveyance, it was initially unclear whether all shareholders supported the

transfer of their climate and biodiversity rights in the project area to Wildlife Works (see

). In response to a finding made by the validator, a special AGM was held to

confirm the complete support of all Rukinga shareholders.

Yes No N/A

See NCR Number 1 of 1 for November 12, 2009

None

None

Demonstrate that the project does not require the involuntary relocation of people or of

the activities important for the livelihoods and culture of the communities. If any relocation of

habitation or activities is undertaken within the terms of an agreement, the project proponents must

demonstrate that the agreement was made with the free, prior, and informed consent of those

concerned and includes provisions for just and fair compensation.

The project does not require the involuntary relocation of people as no people live in the

project area as of the start date of the project.

Yes No N/A

None

None

None

Identify any illegal activities that could affect the project’s climate, community or

impacts (e.g., logging) taking place in the project zone and describe how

reduce these activities so that project benefits are not derived from illegal activities.

The two major illegal activities that could affect the project’s benefits are harvesting of

firewood and poaching. Both of these activities and descriptions of how these activities will be reduced

in the project zone as a result of this project are identified in Section G5.5 of the PDD.

Yes No N/A

None

The rights to the climate and biodiversity of the project area are owned by Wildlife Works and

were conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority

conveyance, it was initially unclear whether all shareholders supported the

transfer of their climate and biodiversity rights in the project area to Wildlife Works (see NCR Number 1

tor, a special AGM was held to

for November 12, 2009

Demonstrate that the project does not require the involuntary relocation of people or of

the activities important for the livelihoods and culture of the communities. If any relocation of

nt, the project proponents must

informed consent of those

relocation of people as no people live in the

Identify any illegal activities that could affect the project’s climate, community or

be how the project will

reduce these activities so that project benefits are not derived from illegal activities.

The two major illegal activities that could affect the project’s benefits are harvesting of

and descriptions of how these activities will be reduced

Page 39: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

New Information Requests:

Opportunities for Improvement:

Indicator G5.6. Demonstrate that the project proponents have clear, uncontested

rights, or provide legal documentation demonstrating that the project is und

carbon owners with their full consent. Where local or national conditi

carbon rights at the time of validation against the Standards, t

evidence that their ownership of carbon rights is likely to be establi

transactions concerning the project’s carbon assets.

Findings: The rights to the climate benefits of the project area

conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority of

shareholders affected this conveyance, it was initially unclear whether all shareholders supported the

transfer of their climate and biodiversity rights in the project area to Wildlife Works (see

of 1 for November 12, 2009). In response to a finding made by the validator, a special AGM was held to

confirm the complete support of all Rukinga shareholders. The e

finding clearly demonstrates that the project proponents have clear, legal and uncontested title to the

carbon rights.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.3. Climate Section

3.3.1. CL1 – Net Positive Climate Impacts

Concept

The project must generate net positive impacts on atmospheric concentrations of greenhouse gases

(GHGs) over the project lifetime from land use changes within the project boundaries.

Indicators

The project proponents must:

Indicator CL1.1. Estimate the net change in carbon stocks due to the project activities using the

methods of calculation, formulae and default values of the IPCC 2006 GL for AFOLU or using a more

robust and detailed methodology. The n

minus carbon stock changes without

must be based on clearly defined and defendable assumptions about how project activities will

GHG emissions or carbon stocks over the duration of the project or the project GHG accounting period.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

36

None

None

Demonstrate that the project proponents have clear, uncontested title to the carbon

provide legal documentation demonstrating that the project is undertaken on behalf of the

owners with their full consent. Where local or national conditions preclude clear title to the

carbon rights at the time of validation against the Standards, the project proponents must provide

evidence that their ownership of carbon rights is likely to be established before they enter into any

transactions concerning the project’s carbon assets.

The rights to the climate benefits of the project area are owned by Wildlife Works and were

conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority of

shareholders affected this conveyance, it was initially unclear whether all shareholders supported the

climate and biodiversity rights in the project area to Wildlife Works (see

). In response to a finding made by the validator, a special AGM was held to

confirm the complete support of all Rukinga shareholders. The evidence collected in response to this

finding clearly demonstrates that the project proponents have clear, legal and uncontested title to the

Yes No N/A

See NCR Number 1 of 1 for November 12, 2009

See NIR Number 4 of 5 for October 20, 2009

None

Net Positive Climate Impacts

The project must generate net positive impacts on atmospheric concentrations of greenhouse gases

(GHGs) over the project lifetime from land use changes within the project boundaries.

Estimate the net change in carbon stocks due to the project activities using the

methods of calculation, formulae and default values of the IPCC 2006 GL for AFOLU or using a more

robust and detailed methodology. The net change is equal to carbon stock changes

without the project (the latter having been estimated in

must be based on clearly defined and defendable assumptions about how project activities will

GHG emissions or carbon stocks over the duration of the project or the project GHG accounting period.

title to the carbon

ertaken on behalf of the

ons preclude clear title to the

project proponents must provide

shed before they enter into any

are owned by Wildlife Works and were

conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority of

shareholders affected this conveyance, it was initially unclear whether all shareholders supported the

climate and biodiversity rights in the project area to Wildlife Works (see NCR Number 1

). In response to a finding made by the validator, a special AGM was held to

vidence collected in response to this

finding clearly demonstrates that the project proponents have clear, legal and uncontested title to the

for November 12, 2009

The project must generate net positive impacts on atmospheric concentrations of greenhouse gases

Estimate the net change in carbon stocks due to the project activities using the

methods of calculation, formulae and default values of the IPCC 2006 GL for AFOLU or using a more

et change is equal to carbon stock changes with the project

the project (the latter having been estimated in G2). This estimate

must be based on clearly defined and defendable assumptions about how project activities will alter

GHG emissions or carbon stocks over the duration of the project or the project GHG accounting period.

Page 40: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Findings: The estimated net change in carbon stocks

using an IPCC Tier 3 methodology and an

documented in Sections G1.4, G2.3 and CL1.1.

For current carbon stocks assumed to remain constant or increase over

project activities, diameter measurements,

the aboveground biomass. Belowground biomass is estimated using ratios of above

relative biomass from the IPCC guidance document. The allometric equations for above ground biomass

were parameterized using a purposive sample within common species groups. The sample appeared to

be representative of the entire project area. The allometric equations for aboveground biomass were

not cross-validated for over fitting or selected using an

allometric equations available in the literature for this region of the continent, the constructed

equations seem adequate.

Soil organic carbon was estimated using a simple random sample of soil cores a

This method for estimating soil carb

soil organic pool will remain constant throughout the life of the project, which is a reasonable

assumption.

Under the ‘without project’ reference scenario

population growth is assumed to be linear in time. The latter of these assumptions is probably false (see

OFI Number 1 of 4 for October 20, 2009

conservative based on evidence from the site visit.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CL1.2. Estimate the net change in the emissions of non

N2O in the with and without project scenarios if those gases are likely to account for more than a 5%

increase or de crease (in terms of CO2

removals over each monitoring period.

Findings: The non-CO2 GHG emissions in the

account for more than a 5% increase or de

removals over each monitoring period

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

37

The estimated net change in carbon stocks due to the project activities were estimated in part

using an IPCC Tier 3 methodology and an analysis of local deforestation. These procedures are

documented in Sections G1.4, G2.3 and CL1.1.

assumed to remain constant or increase over the lifetime of the project

project activities, diameter measurements, stem counts and allometric equations are used to estimate

the aboveground biomass. Belowground biomass is estimated using ratios of above

relative biomass from the IPCC guidance document. The allometric equations for above ground biomass

were parameterized using a purposive sample within common species groups. The sample appeared to

be representative of the entire project area. The allometric equations for aboveground biomass were

validated for over fitting or selected using any statistical criteria. Given the limited number of

allometric equations available in the literature for this region of the continent, the constructed

Soil organic carbon was estimated using a simple random sample of soil cores analyzed by a third party.

This method for estimating soil carbon appears to be adequate. The project proponent assumes that the

soil organic pool will remain constant throughout the life of the project, which is a reasonable

‘without project’ reference scenario, the rate is assumed to linear in population size and

population growth is assumed to be linear in time. The latter of these assumptions is probably false (see

OFI Number 1 of 4 for October 20, 2009), however the overall estimated deforestation rate is probably

conservative based on evidence from the site visit.

Yes No N/A

None

None

See OFI Number 1 of 4 for October 20, 2009

Estimate the net change in the emissions of non-CO2 GHG emissions such as CH4 and

project scenarios if those gases are likely to account for more than a 5%

increase or de crease (in terms of CO2-equivalent) of the project’s overall GHG emissions reductions or

removals over each monitoring period.

CO2 GHG emissions in the with and without project scenarios are

r more than a 5% increase or decrease of the project’s overall GHG emissions

removals over each monitoring period (see NCR Number 12 of 19 for October 20, 2009

Yes No N/A

were estimated in part

analysis of local deforestation. These procedures are

of the project due to

stem counts and allometric equations are used to estimate

the aboveground biomass. Belowground biomass is estimated using ratios of above-to-belowground

relative biomass from the IPCC guidance document. The allometric equations for above ground biomass

were parameterized using a purposive sample within common species groups. The sample appeared to

be representative of the entire project area. The allometric equations for aboveground biomass were

y statistical criteria. Given the limited number of

allometric equations available in the literature for this region of the continent, the constructed

nalyzed by a third party.

The project proponent assumes that the

soil organic pool will remain constant throughout the life of the project, which is a reasonable

he rate is assumed to linear in population size and

population growth is assumed to be linear in time. The latter of these assumptions is probably false (see

all estimated deforestation rate is probably

CO2 GHG emissions such as CH4 and

project scenarios if those gases are likely to account for more than a 5%

erall GHG emissions reductions or

project scenarios are not likely to

crease of the project’s overall GHG emissions reductions or

NCR Number 12 of 19 for October 20, 2009).

Page 41: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 12 of 19 for October 20, 2009

Finding: Based on anecdotal evidence obtained during the site visit, the GHG emissions

gases is likely less than 5% of the project's overall emissions reductions (within the project area and

zone). Also based on anecdotal evidence, the net climate impact of the project is likely positive.

However, the project proponent must esti

those emissions resulting from project activities. Also, demonstrate the net climate impact is positive

considering the estimated reductions, GHG emissions and unmitigated leakage (GL2.3).

Proponent Response on November 1

Project Activities both within the Project Area and the Project Zone to Section CL1.3 of the PDD text of

which is below, which encompasses our more detailed response to

categorically that our project has an overwhelmingly positive emissions reduction impact. We have

updated the leakage, and leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under

NCR#13, to support our argument for no unmitigated leakage, and we consider this to be a full and

complete response to this finding and ask that you close NCR#12.

Validator Response: The proponent’s response is adequate and shows the non

are not likely to account for more than a 5% increase or decrease of the project’s overall GHG emissions

reductions or removals over each monitoring period

there is in fact an overwhelming positive climate impact to the project.

New Information Requests:

Opportunities for Improvement:

Indicator CL1.3. Estimate any other GHG emissions resulting from project activities. Emissions sources

include, but are not limited to, emissions from biomass burning during site preparation, emissions from

fossil fuel combustion, direct emissions from the use of syntheti

decomposition of N-fixing species.

Findings: Other GHG emissions resulting from project activities

CL1.2 of the revised PDD (see NCR Number 12 of 19 for October 20, 2009

emissions listed in the PDD and the estimated emissions for these sources seem complete and accurate.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

38

NCR Number 12 of 19 for October 20, 2009

Based on anecdotal evidence obtained during the site visit, the GHG emissions

gases is likely less than 5% of the project's overall emissions reductions (within the project area and

zone). Also based on anecdotal evidence, the net climate impact of the project is likely positive.

However, the project proponent must estimate the net change in these non-CO2 emissions, including

those emissions resulting from project activities. Also, demonstrate the net climate impact is positive

considering the estimated reductions, GHG emissions and unmitigated leakage (GL2.3).

November 1, 2009: We have added a full carbon footprint analysis for all

Project Activities both within the Project Area and the Project Zone to Section CL1.3 of the PDD text of

which is below, which encompasses our more detailed response to CL2.4, and demonstrates

categorically that our project has an overwhelmingly positive emissions reduction impact. We have

updated the leakage, and leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under

t for no unmitigated leakage, and we consider this to be a full and

complete response to this finding and ask that you close NCR#12.

: The proponent’s response is adequate and shows the non-CO2 GHG emissions in

for more than a 5% increase or decrease of the project’s overall GHG emissions

reductions or removals over each monitoring period. The addition of unmitigated leakage shows that

there is in fact an overwhelming positive climate impact to the project.

None

None

Estimate any other GHG emissions resulting from project activities. Emissions sources

include, but are not limited to, emissions from biomass burning during site preparation, emissions from

fossil fuel combustion, direct emissions from the use of synthetic fertilizers, and emissions from the

GHG emissions resulting from project activities are estimated in Section

NCR Number 12 of 19 for October 20, 2009). The types of sour

emissions listed in the PDD and the estimated emissions for these sources seem complete and accurate.

Yes No N/A

See NCR Number 12 of 19 for October 20, 2009

None

None

Based on anecdotal evidence obtained during the site visit, the GHG emissions of non-CO2

gases is likely less than 5% of the project's overall emissions reductions (within the project area and

zone). Also based on anecdotal evidence, the net climate impact of the project is likely positive.

CO2 emissions, including

those emissions resulting from project activities. Also, demonstrate the net climate impact is positive

considering the estimated reductions, GHG emissions and unmitigated leakage (GL2.3).

We have added a full carbon footprint analysis for all

Project Activities both within the Project Area and the Project Zone to Section CL1.3 of the PDD text of

CL2.4, and demonstrates

categorically that our project has an overwhelmingly positive emissions reduction impact. We have

updated the leakage, and leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under

t for no unmitigated leakage, and we consider this to be a full and

CO2 GHG emissions in

for more than a 5% increase or decrease of the project’s overall GHG emissions

. The addition of unmitigated leakage shows that

Estimate any other GHG emissions resulting from project activities. Emissions sources

include, but are not limited to, emissions from biomass burning during site preparation, emissions from

c fertilizers, and emissions from the

are estimated in Section

). The types of sources of

emissions listed in the PDD and the estimated emissions for these sources seem complete and accurate.

NCR Number 12 of 19 for October 20, 2009

Page 42: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Indicator CL1.4. Demonstrate that the net climate impact of the project is positive. The net climate

impact of the project is the net change in carbon stocks plus net change in non

appropriate minus any other GHG emissions resulting from p

related unmitigated negative offsite climate impacts (see CL2.3).

Findings: Based on the evidence provided in the revised PDD and responses to findings (see

Numbers 12 and 13 of 19 for October 20, 2009

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CL1.5. Specify how double counting of GHG emissions reductions or removals will be avoided,

particularly for offsets sold on the voluntary market and generated in a country with an emissions cap.

Findings: GHG emissions reductions and removals cannot be doubl

have an emissions cap.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.3.2. CL2 – Offsite Climate Impacts (‘Leakage’)

Concept

The project proponents must quantify

project area and are caused by project activities (commonly referred to as ‘leakage’).

Indicators

The project proponents must:

Indicator CL2.1. Determine the types of leakage that are expected and estimate potential offsite

increases in GHGs (increases in emissions or decreases in sequestration) due to project activities. Where

relevant, define and justify where leakage is most likely to take pl

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

39

Demonstrate that the net climate impact of the project is positive. The net climate

impact of the project is the net change in carbon stocks plus net change in non-

appropriate minus any other GHG emissions resulting from project activities minus any likely project

related unmitigated negative offsite climate impacts (see CL2.3).

Based on the evidence provided in the revised PDD and responses to findings (see

for October 20, 2009), the project has a net positive climate impact.

Yes No N/A

See NCR Number 12 of 19 for October 20, 2009

See NCR Number 13 of 19 for October 20, 2009

None

None

Specify how double counting of GHG emissions reductions or removals will be avoided,

particularly for offsets sold on the voluntary market and generated in a country with an emissions cap.

GHG emissions reductions and removals cannot be double counted because Kenya does not

Yes No N/A

None

None

None

Offsite Climate Impacts (‘Leakage’)

The project proponents must quantify and mitigate increased GHG emissions that occur beyond the

project area and are caused by project activities (commonly referred to as ‘leakage’).

Determine the types of leakage that are expected and estimate potential offsite

increases in GHGs (increases in emissions or decreases in sequestration) due to project activities. Where

relevant, define and justify where leakage is most likely to take place.

Demonstrate that the net climate impact of the project is positive. The net climate

-CO2 GHGs where

roject activities minus any likely project-

Based on the evidence provided in the revised PDD and responses to findings (see NCR

project has a net positive climate impact.

NCR Number 12 of 19 for October 20, 2009

NCR Number 13 of 19 for October 20, 2009

Specify how double counting of GHG emissions reductions or removals will be avoided,

particularly for offsets sold on the voluntary market and generated in a country with an emissions cap.

e counted because Kenya does not

and mitigate increased GHG emissions that occur beyond the

Determine the types of leakage that are expected and estimate potential offsite

increases in GHGs (increases in emissions or decreases in sequestration) due to project activities. Where

Page 43: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Findings: Two types of leakage are identified in the PDD: activity shifting and market effects leakage.

There are no other apparent types of leakage for the project. Originally, the PDD did not

justify where leakage is most likely to ta

response to an initial finding, the PDD was revised to include the

(other unprotected ranches in the project zone) and market effects leakage (the commerce o

in the local communities).

Conformance:

Non-Conformity Reports:

NCR Number 13 of 19 for October 20, 2009

Finding: The PDD contains a description of the communities around the project area and not types of

leakage or where leakage is likely to take place. During the site visit, the project proponent determined

there are no expected types of leakage in the project zone. The project proponent must provide a

detailed description of how they determined there are no expected ty

due to project activities, primarily the exclusion of people from the project area to make charcoal and

practice agriculture. Provide this description in sufficient detail and refer to specific areas where

leakage may or may not take place within the project zone.

Proponent Response on November 1

Sections CL2.1, CL2.2, CL2.3 and CL1.4 and the text is included below. We have updated the leakage, and

leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under NCR#13, to support our

argument for no unmitigated leakage, and we consider this to be a full and complete response to this

finding and ask that you close NCR#13.

Validator Response: Based on evidence collected during the site visit, there is potential for market

effects in the commerce of charcoal originating from the project area. Although charcoal production

from private land is illegal, it is none

determining the overall net climate benefit of the project.

New Information Requests:

Opportunities for Improvement:

Indicator CL2.2. Document how any leakage will be mitigated and estimate the extent to which such

impacts will be reduced by these mitigation activities.

Findings: With respect to the activity shifting leakage, the project aims to protect other ranches in the

project zone from agricultural conversion.

With respect to market effects leakage, the project proponent claims that as a result of the project there

will be no commerce in firewood as historicall

household use. This is contradictory to the evidence collected during the site visit. The sale of charcoal

was observed outside the project area indicating commerce in firewood (via charcoal produc

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

40

Two types of leakage are identified in the PDD: activity shifting and market effects leakage.

There are no other apparent types of leakage for the project. Originally, the PDD did not

justify where leakage is most likely to take place (see NCR Number 13 of 19 for October 20, 2009

response to an initial finding, the PDD was revised to include the location of activity shifting leakage

(other unprotected ranches in the project zone) and market effects leakage (the commerce o

Yes No N/A

NCR Number 13 of 19 for October 20, 2009

The PDD contains a description of the communities around the project area and not types of

leakage is likely to take place. During the site visit, the project proponent determined

there are no expected types of leakage in the project zone. The project proponent must provide a

detailed description of how they determined there are no expected types of leakage in the project zone

due to project activities, primarily the exclusion of people from the project area to make charcoal and

practice agriculture. Provide this description in sufficient detail and refer to specific areas where

may not take place within the project zone.

November 1, 2009: We have added significantly to the PDD content of

Sections CL2.1, CL2.2, CL2.3 and CL1.4 and the text is included below. We have updated the leakage, and

on descriptions in Sections CL2.1, CL2.2, CL2.3 covered under NCR#13, to support our

argument for no unmitigated leakage, and we consider this to be a full and complete response to this

finding and ask that you close NCR#13.

vidence collected during the site visit, there is potential for market

effects in the commerce of charcoal originating from the project area. Although charcoal production

from private land is illegal, it is none-the-less a form of leakage and should be estimated when

determining the overall net climate benefit of the project.

None

None

Document how any leakage will be mitigated and estimate the extent to which such

impacts will be reduced by these mitigation activities.

With respect to the activity shifting leakage, the project aims to protect other ranches in the

from agricultural conversion. This activity will effectively mitigate activity shifting leakage.

With respect to market effects leakage, the project proponent claims that as a result of the project there

will be no commerce in firewood as historically firewood from within the project area was consumed for

household use. This is contradictory to the evidence collected during the site visit. The sale of charcoal

was observed outside the project area indicating commerce in firewood (via charcoal produc

Two types of leakage are identified in the PDD: activity shifting and market effects leakage.

There are no other apparent types of leakage for the project. Originally, the PDD did not define and

NCR Number 13 of 19 for October 20, 2009). In

location of activity shifting leakage

(other unprotected ranches in the project zone) and market effects leakage (the commerce of fuel wood

The PDD contains a description of the communities around the project area and not types of

leakage is likely to take place. During the site visit, the project proponent determined

there are no expected types of leakage in the project zone. The project proponent must provide a

pes of leakage in the project zone

due to project activities, primarily the exclusion of people from the project area to make charcoal and

practice agriculture. Provide this description in sufficient detail and refer to specific areas where

We have added significantly to the PDD content of

Sections CL2.1, CL2.2, CL2.3 and CL1.4 and the text is included below. We have updated the leakage, and

on descriptions in Sections CL2.1, CL2.2, CL2.3 covered under NCR#13, to support our

argument for no unmitigated leakage, and we consider this to be a full and complete response to this

vidence collected during the site visit, there is potential for market

effects in the commerce of charcoal originating from the project area. Although charcoal production

timated when

Document how any leakage will be mitigated and estimate the extent to which such

With respect to the activity shifting leakage, the project aims to protect other ranches in the

This activity will effectively mitigate activity shifting leakage.

With respect to market effects leakage, the project proponent claims that as a result of the project there

y firewood from within the project area was consumed for

household use. This is contradictory to the evidence collected during the site visit. The sale of charcoal

was observed outside the project area indicating commerce in firewood (via charcoal production). The

Page 44: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

revised PDD does not contain any mitigation strategies for the market effects of charcoal sales

Number 13 of 19 for October 20, 2009

shifting leakage can be applied to the leaka

generally a local activity, the protection of adjacent ranches in the project zone will suffice to mitigate

the market effects of firewood sales.

Despite the anticipated protection of adjacent ranche

that no charcoal production will occur on these ranches as a result of project activities. Based on the

evidence observed during the site visit, charcoal production on adjacent ranches has likely already

occurred since the project start date of January 2006. As of 2009, the adjacent ranches have not been

protected as an activity under this project. Therefore, leakage as a result of charcoal production should

have been estimated. However, since the amoun

ranches is expected to be relatively minor until the

ranches, non-conformance to this indicator is immaterial as this leakage will not affect the posit

climate benefits of this project.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CL2.3. Subtract any likely project

the climate benefits being claimed by the project and demonstrate that this has been included in the

evaluation of net climate impact of the project (as calculated in

Findings: Given the estimated positive benefits of the project and the anticipated but unestimated

leakage due to minor fuelwood consumption

climate impact of the project is positive.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CL2.4. Non-CO2 gases must be includ

increase or decrease (in terms of CO2

overall off-site GHG emissions reductions or removals over each monitoring period.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

41

revised PDD does not contain any mitigation strategies for the market effects of charcoal sales

Number 13 of 19 for October 20, 2009). However to some degree, the same argument as activity

shifting leakage can be applied to the leakage due to market effects. Since charcoal production is

generally a local activity, the protection of adjacent ranches in the project zone will suffice to mitigate

the market effects of firewood sales.

protection of adjacent ranches in the project zone, it is unreasonable to think

that no charcoal production will occur on these ranches as a result of project activities. Based on the

during the site visit, charcoal production on adjacent ranches has likely already

occurred since the project start date of January 2006. As of 2009, the adjacent ranches have not been

protected as an activity under this project. Therefore, leakage as a result of charcoal production should

have been estimated. However, since the amount of leakage due to fuelwood production on adjacent

ranches is expected to be relatively minor until the initiation of project activities to protect adjacent

conformance to this indicator is immaterial as this leakage will not affect the posit

Yes No N/A

See NCR Number 13 of 19 for October 20, 2009

None

None

Subtract any likely project-related unmitigated negative offsite climate impacts from

the climate benefits being claimed by the project and demonstrate that this has been included in the

evaluation of net climate impact of the project (as calculated in CL1.4).

estimated positive benefits of the project and the anticipated but unestimated

leakage due to minor fuelwood consumption (see NCR Number 13 of 19 for October 20, 2009

climate impact of the project is positive.

Yes No N/A

See NCR Number 13 of 19 for October 20, 2009

None

None

CO2 gases must be included if they are likely to account for more than a 5%

increase or decrease (in terms of CO2-equivalent) of the net change calculations (above) of the project’s

site GHG emissions reductions or removals over each monitoring period.

revised PDD does not contain any mitigation strategies for the market effects of charcoal sales (see NCR

. However to some degree, the same argument as activity

ge due to market effects. Since charcoal production is

generally a local activity, the protection of adjacent ranches in the project zone will suffice to mitigate

s in the project zone, it is unreasonable to think

that no charcoal production will occur on these ranches as a result of project activities. Based on the

during the site visit, charcoal production on adjacent ranches has likely already

occurred since the project start date of January 2006. As of 2009, the adjacent ranches have not been

protected as an activity under this project. Therefore, leakage as a result of charcoal production should

t of leakage due to fuelwood production on adjacent

of project activities to protect adjacent

conformance to this indicator is immaterial as this leakage will not affect the positive

f 19 for October 20, 2009

related unmitigated negative offsite climate impacts from

the climate benefits being claimed by the project and demonstrate that this has been included in the

estimated positive benefits of the project and the anticipated but unestimated

NCR Number 13 of 19 for October 20, 2009), the net

NCR Number 13 of 19 for October 20, 2009

ed if they are likely to account for more than a 5%

equivalent) of the net change calculations (above) of the project’s

Page 45: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Findings: Non-CO2 gases have been demonstrated to account for less than 5% of the net change in the

project’s overall off-site GHG emissions reduction or removals (see

20, 2009).

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.3.3. CL3 – Climate Impact Monitoring

Concept

Before a project begins, the project proponents must have an initial monitoring plan in place to quantify

and document changes (within and outside the project boundaries) in project

project emissions, and non-CO2 GHG emissions if appropriate. The monitoring plan must identify the

types of measurements, the sampling method, and the frequency of measurement.

Since developing a full monitoring plan can be costly, it is accepted that some of the plan details may

not be fully defined at the design stage, when projects are being validated against the Standards. This is

acceptable as long as there is an explicit com

Indicators

The project proponents must:

Indicator CL3.1. Develop an initial plan for selecting carbon pools and non

and determine the frequency of monitoring. Potential pools in

wood, belowground biomass, wood products, soil carbon and peat. Pools to monitor must include any

pools expected to decrease as a result of project activities, including those in the region outside the

project boundaries resulting from all types of leakage identified in CL2. A plan must be in place to

continue leakage monitoring for at least five years after all activity displacement or other leakage

causing activity has taken place. Individual GHG sources may be cons

have to be accounted for if together

emissions amount to less than 5% of the total CO2

CO2 gases must be included if they are likely to account for more than 5% (in terms of CO2

of the project’s overall GHG impact over each monitoring period. Direct field measurements using

scientifically robust sampling must be used to measure more significant elements

stocks. Other data must be suitable to the project site and specific forest type.

Findings: An initial monitoring plan has been established in Section CL3.1 of the revised PDD. Originally,

the PDD lacked information about the fr

20, 2009), however was later amended to include this information.

Conformance:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

42

CO2 gases have been demonstrated to account for less than 5% of the net change in the

site GHG emissions reduction or removals (see NCR Number 12 of 19 for October

Yes No N/A

See NCR Number 12 of 19 for October 20, 2009

None

None

Climate Impact Monitoring

Before a project begins, the project proponents must have an initial monitoring plan in place to quantify

(within and outside the project boundaries) in project-related carbon pools,

CO2 GHG emissions if appropriate. The monitoring plan must identify the

types of measurements, the sampling method, and the frequency of measurement.

ince developing a full monitoring plan can be costly, it is accepted that some of the plan details may

not be fully defined at the design stage, when projects are being validated against the Standards. This is

acceptable as long as there is an explicit commitment to develop and implement a monitoring plan.

Develop an initial plan for selecting carbon pools and non-CO2 GHGs to be monitored,

and determine the frequency of monitoring. Potential pools include aboveground biomass, litter, dead

wood, belowground biomass, wood products, soil carbon and peat. Pools to monitor must include any

pools expected to decrease as a result of project activities, including those in the region outside the

ries resulting from all types of leakage identified in CL2. A plan must be in place to

continue leakage monitoring for at least five years after all activity displacement or other leakage

causing activity has taken place. Individual GHG sources may be considered ‘insignificant’ and do not

together such omitted decreases in carbon pools and increases in GHG

emissions amount to less than 5% of the total CO2-equivalent benefits generated by the project. Non

ed if they are likely to account for more than 5% (in terms of CO2

of the project’s overall GHG impact over each monitoring period. Direct field measurements using

scientifically robust sampling must be used to measure more significant elements of the project’s carbon

stocks. Other data must be suitable to the project site and specific forest type.

An initial monitoring plan has been established in Section CL3.1 of the revised PDD. Originally,

the PDD lacked information about the frequency of monitoring (see NCR Number 14 of 19 for October

), however was later amended to include this information.

Yes No N/A

CO2 gases have been demonstrated to account for less than 5% of the net change in the

NCR Number 12 of 19 for October

ober 20, 2009

Before a project begins, the project proponents must have an initial monitoring plan in place to quantify

related carbon pools,

CO2 GHG emissions if appropriate. The monitoring plan must identify the

ince developing a full monitoring plan can be costly, it is accepted that some of the plan details may

not be fully defined at the design stage, when projects are being validated against the Standards. This is

mitment to develop and implement a monitoring plan.

CO2 GHGs to be monitored,

clude aboveground biomass, litter, dead

wood, belowground biomass, wood products, soil carbon and peat. Pools to monitor must include any

pools expected to decrease as a result of project activities, including those in the region outside the

ries resulting from all types of leakage identified in CL2. A plan must be in place to

continue leakage monitoring for at least five years after all activity displacement or other leakage

idered ‘insignificant’ and do not

such omitted decreases in carbon pools and increases in GHG

equivalent benefits generated by the project. Non-

ed if they are likely to account for more than 5% (in terms of CO2-equivalent)

of the project’s overall GHG impact over each monitoring period. Direct field measurements using

of the project’s carbon

An initial monitoring plan has been established in Section CL3.1 of the revised PDD. Originally,

NCR Number 14 of 19 for October

Page 46: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Non-Conformity Reports:

NCR Number 14 of 19 for October 20, 2009

Finding: The project proponent must specify the frequency of monitoring.

Proponent Response on October 30

text below, to provide specific frequencies of monitoring. We believe that this new information provided

to the Validator is a more than adequate response to your finding and meets the Standard and w

that you consider this finding NCR#14 closed.

Validator Response: The revised PD is adequate.

New Information Requests:

Opportunities for Improvement:

Indicator CL3.2. Commit to developing a full monitoring plan within six months of

or within twelve months of validation against the Standards and to disseminate this plan and the results

of monitoring, ensuring that they are made publicly available on the internet and are communicated to

the communities and other stakeholders.

Findings: The project proponent has committed to developing a full monitoring plan within twelve

months of the validation.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.4. Community Section

3.4.1. CM1 – Net Positive Community Impacts

Concept

The project must generate net positive impacts on the social and economic well

and ensure that costs and benefits are equitably shared among community members and constituent

groups during the project lifetime.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

43

14 of 19 for October 20, 2009

The project proponent must specify the frequency of monitoring.

October 30, 2009: We have revised sections CL3.1 of the PDD to include the

text below, to provide specific frequencies of monitoring. We believe that this new information provided

to the Validator is a more than adequate response to your finding and meets the Standard and w

that you consider this finding NCR#14 closed.

revised PD is adequate.

None

None

Commit to developing a full monitoring plan within six months of the project start date

or within twelve months of validation against the Standards and to disseminate this plan and the results

of monitoring, ensuring that they are made publicly available on the internet and are communicated to

stakeholders.

The project proponent has committed to developing a full monitoring plan within twelve

Yes No N/A

None

None

None

Net Positive Community Impacts

The project must generate net positive impacts on the social and economic well-being of communities

benefits are equitably shared among community members and constituent

We have revised sections CL3.1 of the PDD to include the

text below, to provide specific frequencies of monitoring. We believe that this new information provided

to the Validator is a more than adequate response to your finding and meets the Standard and we ask

the project start date

or within twelve months of validation against the Standards and to disseminate this plan and the results

of monitoring, ensuring that they are made publicly available on the internet and are communicated to

The project proponent has committed to developing a full monitoring plan within twelve

being of communities

benefits are equitably shared among community members and constituent

Page 47: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Projects must maintain or enhance the High Conservation Values (identified in

that are of particular importance to the commun

Indicators

The project proponents must:

Indicator CM1.1. Use appropriate methodologies to estimate the impacts on communities, including all

constituent socio-economic or cultural groups such as indigenous peoples (defined in

planned project activities. A credible estimate of impacts must include changes in community well

due to project activities and an evaluation of the impacts by the affected groups. This estimate must be

based on clearly defined and defenda

economic well-being, including potential impacts of changes in natural resources and ecosystem services

identified as important by the communities (including water and soil resources), over

project. The ‘with project’ scenario must then be compared with the ‘without project’ scenario of social

and economic well-being in the absence of the project (completed in

community benefit) must be positive for all community groups.

Findings: Wildlife Works carbon offset project’s PDD has details of the net positive impact that the

project will have on the local community. A thorough scrutiny and interviews with the local community

supports such sentiments presented in the PDD even in its current operational status and organisation.

Wildlife Works, the community confirmed, gives back quite substantially.

Wildlife Works currently offers employment to the local community at their Export Processing Zo

(EPZ) organic sewing factory. It also offers other employments opportunities to the locals as house

helps, night guards, game rangers, drivers, office management staff and mechanics

with the community the net benefits. All employme

always fair considerations and merits are the guiding principal in recruitments.

All these employment opportunities empower the local community members concern

appropriate skills that can as well

comparative advantages over other communities in the project zone and purchasing powers leading to

improved living standards.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CM1.2. Demonstrate that no High Conservation Values identified in

negatively affected by the project.

Findings: The project area links two very important conservation areas

National Parks. It is therefore a migratory corridor whose presence helps the wildlife from both parks to

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

44

Projects must maintain or enhance the High Conservation Values (identified in G1) in the project zone

that are of particular importance to the communities’ well-being.

Use appropriate methodologies to estimate the impacts on communities, including all

economic or cultural groups such as indigenous peoples (defined in G1

planned project activities. A credible estimate of impacts must include changes in community well

due to project activities and an evaluation of the impacts by the affected groups. This estimate must be

based on clearly defined and defendable assumptions about how project activities will alter social and

being, including potential impacts of changes in natural resources and ecosystem services

identified as important by the communities (including water and soil resources), over the duration of the

project. The ‘with project’ scenario must then be compared with the ‘without project’ scenario of social

being in the absence of the project (completed in G2). The difference (i.e., the

tive for all community groups.

Wildlife Works carbon offset project’s PDD has details of the net positive impact that the

project will have on the local community. A thorough scrutiny and interviews with the local community

ments presented in the PDD even in its current operational status and organisation.

Wildlife Works, the community confirmed, gives back quite substantially.

Wildlife Works currently offers employment to the local community at their Export Processing Zo

(EPZ) organic sewing factory. It also offers other employments opportunities to the locals as house

helps, night guards, game rangers, drivers, office management staff and mechanics-

with the community the net benefits. All employment opportunities are indiscriminate of gender and

always fair considerations and merits are the guiding principal in recruitments.

All these employment opportunities empower the local community members concern

appropriate skills that can as well be applied elsewhere, monthly cash flows which give them some

comparative advantages over other communities in the project zone and purchasing powers leading to

Yes No N/A

None

None

None

Demonstrate that no High Conservation Values identified in G1.8.4

The project area links two very important conservation areas-the Tsavo East and West

National Parks. It is therefore a migratory corridor whose presence helps the wildlife from both parks to

) in the project zone

Use appropriate methodologies to estimate the impacts on communities, including all

G1), resulting from

planned project activities. A credible estimate of impacts must include changes in community well-being

due to project activities and an evaluation of the impacts by the affected groups. This estimate must be

ble assumptions about how project activities will alter social and

being, including potential impacts of changes in natural resources and ecosystem services

the duration of the

project. The ‘with project’ scenario must then be compared with the ‘without project’ scenario of social

). The difference (i.e., the

Wildlife Works carbon offset project’s PDD has details of the net positive impact that the

project will have on the local community. A thorough scrutiny and interviews with the local community

ments presented in the PDD even in its current operational status and organisation.

Wildlife Works currently offers employment to the local community at their Export Processing Zone’s

(EPZ) organic sewing factory. It also offers other employments opportunities to the locals as house

-a form of sharing

nt opportunities are indiscriminate of gender and

All these employment opportunities empower the local community members concerned with

be applied elsewhere, monthly cash flows which give them some

comparative advantages over other communities in the project zone and purchasing powers leading to

G1.8.4-642 will be

the Tsavo East and West

National Parks. It is therefore a migratory corridor whose presence helps the wildlife from both parks to

Page 48: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

move freely in search of pasture, water and protection. The “wi

exposure of endemic and endangered wildlife to poaching while they migrate on the corridor because

the “without project scenario” will lead in vegetation destruction and land degradation.

The controlled fuel wood collection by the local community, the restricted over grazing of cattle also by

the local community, the strict surveillance and patrols to avert poaching of wildlife and trees, instituted

by the project through recruiting enough game rangers; will be positi

Values identified in G 1.8..4-642 and will not have negative effect on the said HCV in the area.

The foregoing finding of the audit team concurs with the explanations given by the project proponent

stated in the PDD.

Conformance:

Non-Conformity Reports:

NCR Number 18 of 19 for October 20, 2009

Finding: There are clear risks to the project's climate, community and biodiversity benefits (including

impacts on the well-beings of communit

posed by prolonged drought as a result of climate change. The project proponent must identify these

risks and explain how they will be mitigated.

Proponent Response on October 26

the PDD to include a lot more detail no Climate Change factors relevant to our Project. We believe that

submission of the updated PDD text below provides a complete and appropriate response to this NCR

and that this NCR should now be closed.

Validator Response: The response is adequate.

New Information Requests:

Opportunities for Improvement:

3.4.2. CM2 – Offsite Stakeholder Impacts

Concept

The project proponents must evaluate and mitigate

result in the decreased social and economic well

project zone resulting from project activities. Project activities should at least ‘do no harm’ to the we

being of offsite stakeholders.

Indicators

The project proponents must:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

45

move freely in search of pasture, water and protection. The “without project scenario” will result in

exposure of endemic and endangered wildlife to poaching while they migrate on the corridor because

the “without project scenario” will lead in vegetation destruction and land degradation.

lection by the local community, the restricted over grazing of cattle also by

the local community, the strict surveillance and patrols to avert poaching of wildlife and trees, instituted

by the project through recruiting enough game rangers; will be positive in promoting High Conservation

642 and will not have negative effect on the said HCV in the area.

The foregoing finding of the audit team concurs with the explanations given by the project proponent

Yes No N/A

See NCR Number 2 of 19 for October 20, 2009

NCR Number 18 of 19 for October 20, 2009

There are clear risks to the project's climate, community and biodiversity benefits (including

beings of communities and the conservation of biodiversity), including the risks

posed by prolonged drought as a result of climate change. The project proponent must identify these

risks and explain how they will be mitigated.

October 26, 2009: We have significantly amended Sections GL1.2 and GL1.3 of

the PDD to include a lot more detail no Climate Change factors relevant to our Project. We believe that

submission of the updated PDD text below provides a complete and appropriate response to this NCR

and that this NCR should now be closed.

The response is adequate.

None

None

Offsite Stakeholder Impacts

The project proponents must evaluate and mitigate any possible social and economic impacts that could

result in the decreased social and economic well-being of the main stakeholders living outside the

project zone resulting from project activities. Project activities should at least ‘do no harm’ to the we

thout project scenario” will result in

exposure of endemic and endangered wildlife to poaching while they migrate on the corridor because

the “without project scenario” will lead in vegetation destruction and land degradation.

lection by the local community, the restricted over grazing of cattle also by

the local community, the strict surveillance and patrols to avert poaching of wildlife and trees, instituted

ve in promoting High Conservation

642 and will not have negative effect on the said HCV in the area.

The foregoing finding of the audit team concurs with the explanations given by the project proponent

NCR Number 2 of 19 for October 20, 2009

There are clear risks to the project's climate, community and biodiversity benefits (including

ies and the conservation of biodiversity), including the risks

posed by prolonged drought as a result of climate change. The project proponent must identify these

ave significantly amended Sections GL1.2 and GL1.3 of

the PDD to include a lot more detail no Climate Change factors relevant to our Project. We believe that

submission of the updated PDD text below provides a complete and appropriate response to this NCR

any possible social and economic impacts that could

being of the main stakeholders living outside the

project zone resulting from project activities. Project activities should at least ‘do no harm’ to the well-

Page 49: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Indicator CM2.1. Identify any potential negative offsite stakeholder impacts that the project activities

are likely to cause.

Findings: The initial PDD claimed that there were no

the audit process, negative impacts were discovered. The project proponent responded to the NCR by

updating the PDD to include language explaining why this is the case. The auditors took the information

into consideration and found the proponent to be in conformance.

Conformance:

Non-Conformity Reports:

NCR Number 15 of 19 for October 20, 2009

Finding: The project proponent strongly claims there are no negative offsite impacts to stakeholders.

However, based on community meetings, interviews and observations conducted during the site visit,

potential negative offsite impacts indeed exist. Community members identified the following potential

negative offsite impacts: an exclusive dependence on Wildlife Works for livelihood, an increase in

wildlife-human conflicts and the exclusion of grazing from the sanctuary. Th

address these negative impacts to stakeholders and describe how they will be mitigated. Also,

demonstrate that project is not likely to result in net negative impacts on the well being of other

stakeholder groups. Note that the

CCBA.

Proponent Response on October 30

are potential negative impacts from the Project Activities by adding content to sections C

and CM2.3. We have included that text below and we believe that this provides an adequate and

complete response to your finding and as such we ask that you close finding NCR#15.

Validator Response: The response is adequate.

New Information Requests:

Opportunities for Improvement:

Indicator CM2.2. Describe how the project plans to mitigate these negative offsite social and economic

impacts.

Findings: Geographically, Taita district, the location of the project

marginalized. The major economic activity is dry land rain fed agriculture and pastoralism. With

emergence of persistent drought in Kenya, agriculture and pastoralism has been highly affected leading

to high failures and loss of otherwise dependable livelihood by the community in the area.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

46

Identify any potential negative offsite stakeholder impacts that the project activities

claimed that there were no net negative offsite stakeholder impacts. During

the audit process, negative impacts were discovered. The project proponent responded to the NCR by

updating the PDD to include language explaining why this is the case. The auditors took the information

consideration and found the proponent to be in conformance.

Yes No N/A

15 of 19 for October 20, 2009

The project proponent strongly claims there are no negative offsite impacts to stakeholders.

However, based on community meetings, interviews and observations conducted during the site visit,

site impacts indeed exist. Community members identified the following potential

negative offsite impacts: an exclusive dependence on Wildlife Works for livelihood, an increase in

human conflicts and the exclusion of grazing from the sanctuary. The project proponent must

address these negative impacts to stakeholders and describe how they will be mitigated. Also,

demonstrate that project is not likely to result in net negative impacts on the well being of other

stakeholder groups. Note that the Duruma are considered another stakeholder group as defined by the

October 30, 2009: We have addressed the community perception that there

are potential negative impacts from the Project Activities by adding content to sections C

and CM2.3. We have included that text below and we believe that this provides an adequate and

complete response to your finding and as such we ask that you close finding NCR#15.

The response is adequate.

None

None

Describe how the project plans to mitigate these negative offsite social and economic

Geographically, Taita district, the location of the project is categorised as a semi arid area and

marginalized. The major economic activity is dry land rain fed agriculture and pastoralism. With

emergence of persistent drought in Kenya, agriculture and pastoralism has been highly affected leading

es and loss of otherwise dependable livelihood by the community in the area.

Identify any potential negative offsite stakeholder impacts that the project activities

net negative offsite stakeholder impacts. During

the audit process, negative impacts were discovered. The project proponent responded to the NCR by

updating the PDD to include language explaining why this is the case. The auditors took the information

The project proponent strongly claims there are no negative offsite impacts to stakeholders.

However, based on community meetings, interviews and observations conducted during the site visit,

site impacts indeed exist. Community members identified the following potential

negative offsite impacts: an exclusive dependence on Wildlife Works for livelihood, an increase in

e project proponent must

address these negative impacts to stakeholders and describe how they will be mitigated. Also,

demonstrate that project is not likely to result in net negative impacts on the well being of other

uruma are considered another stakeholder group as defined by the

We have addressed the community perception that there

are potential negative impacts from the Project Activities by adding content to sections CM2.1, CM2.2

and CM2.3. We have included that text below and we believe that this provides an adequate and

Describe how the project plans to mitigate these negative offsite social and economic

is categorised as a semi arid area and

marginalized. The major economic activity is dry land rain fed agriculture and pastoralism. With

emergence of persistent drought in Kenya, agriculture and pastoralism has been highly affected leading

es and loss of otherwise dependable livelihood by the community in the area.

Page 50: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Wildlife Works has been supporting research work in collaboration with the Kenya Agricultural Research

Institute (KARI) to introduce and upscale some viable alternative cash crop

(Simmondsia chinensis), was introduced in Rukinga ranch before Wildlife Works purchased and took

over the management of the ranch. This crop has persisted the scarcity of rainfall and high temperature

variability in the area and has proved itself to be a viable and dependable cash crop in the area. With its

highly demanded and highly priced oil, Wildlife Works hopes to market the crop and supply its seeds and

seedlings to local community for commercial propagation. Already Wildlif

nursery for raising its seedlings. It is hoped that if the community accept this crop and plant it in large

scale, the area could turn to be a net exporter of Jojoba seeds and oil which has a global demand. The

success of this crop establishment and adoption of the crop by the local community will be a viable and

a more sustainable way of empowering the local community economically.

Wildlife Works has also established a Citrus fruit tree nursery in their organic green house and

adaptive research identified species that do well in different soils and ecological zones in the area. The

citrus species are sold to the local farmers for planting in their farms at subsidized prices. Through this

initiative; some farmers in the area have gone full scale in commercial citrus fruit farming and are

economically benefiting.

These efforts by Wildlife Works are viable initiatives and were considered by the audit team to mitigate

negative impacts on offsite stakeholders and will e

other sustainable income generation activities in the project area and project zone.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CM2.3. Demonstrate that the project is not likely to result in net negative impacts on the well

being of other stakeholder groups.

Findings:

In the community public meeting, it emerged that there will be negative impacts emanating from

human-wildlife conflicts, exclusion of some people still practicing traditional rituals in sites located in the

project area, fuel wood collection et

he argued that since taking over the management of the ranch, the communities who lived inside the

project area were moved out and with the concerted patrol of the ranch by rangers, direct

interaction between wildlife and community has been greatly minimized.

Cases of stray wildlife into the community residence, raiding their crops or attacking their cattle have

always been timely reported to the Kenya Wildlife Services (KWS)

wildlife in Kenya and who share VHF radio frequencies with

driven the wildlife back to the protected area.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

47

Wildlife Works has been supporting research work in collaboration with the Kenya Agricultural Research

Institute (KARI) to introduce and upscale some viable alternative cash crops in the area. Jojoba

(Simmondsia chinensis), was introduced in Rukinga ranch before Wildlife Works purchased and took

over the management of the ranch. This crop has persisted the scarcity of rainfall and high temperature

s proved itself to be a viable and dependable cash crop in the area. With its

highly demanded and highly priced oil, Wildlife Works hopes to market the crop and supply its seeds and

seedlings to local community for commercial propagation. Already Wildlife Works has established a

nursery for raising its seedlings. It is hoped that if the community accept this crop and plant it in large

scale, the area could turn to be a net exporter of Jojoba seeds and oil which has a global demand. The

rop establishment and adoption of the crop by the local community will be a viable and

a more sustainable way of empowering the local community economically.

Wildlife Works has also established a Citrus fruit tree nursery in their organic green house and

adaptive research identified species that do well in different soils and ecological zones in the area. The

citrus species are sold to the local farmers for planting in their farms at subsidized prices. Through this

area have gone full scale in commercial citrus fruit farming and are

These efforts by Wildlife Works are viable initiatives and were considered by the audit team to mitigate

negative impacts on offsite stakeholders and will eventually empower local people to diversify into

other sustainable income generation activities in the project area and project zone.

Yes No N/A

See NCR Number 15 of 19 for October 20, 2009

None

None

Demonstrate that the project is not likely to result in net negative impacts on the well

In the community public meeting, it emerged that there will be negative impacts emanating from

wildlife conflicts, exclusion of some people still practicing traditional rituals in sites located in the

project area, fuel wood collection etc. In the subsequent follow up meeting with the project proponent,

he argued that since taking over the management of the ranch, the communities who lived inside the

project area were moved out and with the concerted patrol of the ranch by rangers, direct

interaction between wildlife and community has been greatly minimized.

Cases of stray wildlife into the community residence, raiding their crops or attacking their cattle have

always been timely reported to the Kenya Wildlife Services (KWS) who are legally mandated to manage

wildlife in Kenya and who share VHF radio frequencies with Wildlife Works. In such cases KWS have

driven the wildlife back to the protected area.

Wildlife Works has been supporting research work in collaboration with the Kenya Agricultural Research

s in the area. Jojoba

(Simmondsia chinensis), was introduced in Rukinga ranch before Wildlife Works purchased and took

over the management of the ranch. This crop has persisted the scarcity of rainfall and high temperature

s proved itself to be a viable and dependable cash crop in the area. With its

highly demanded and highly priced oil, Wildlife Works hopes to market the crop and supply its seeds and

e Works has established a

nursery for raising its seedlings. It is hoped that if the community accept this crop and plant it in large

scale, the area could turn to be a net exporter of Jojoba seeds and oil which has a global demand. The

rop establishment and adoption of the crop by the local community will be a viable and

Wildlife Works has also established a Citrus fruit tree nursery in their organic green house and through

adaptive research identified species that do well in different soils and ecological zones in the area. The

citrus species are sold to the local farmers for planting in their farms at subsidized prices. Through this

area have gone full scale in commercial citrus fruit farming and are

These efforts by Wildlife Works are viable initiatives and were considered by the audit team to mitigate

ventually empower local people to diversify into

r 15 of 19 for October 20, 2009

Demonstrate that the project is not likely to result in net negative impacts on the well-

In the community public meeting, it emerged that there will be negative impacts emanating from

wildlife conflicts, exclusion of some people still practicing traditional rituals in sites located in the

c. In the subsequent follow up meeting with the project proponent,

he argued that since taking over the management of the ranch, the communities who lived inside the

project area were moved out and with the concerted patrol of the ranch by rangers, direct conflict and

Cases of stray wildlife into the community residence, raiding their crops or attacking their cattle have

who are legally mandated to manage

. In such cases KWS have

Page 51: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Being a wildlife corridor the project area play a vital role in ensuring

most of what they need and hardly attack the community. The protection of the wildlife too will ensure

the existence of the wildlife to perpetuity and so are the tourism industries which brings a lot of foreign

exchange for national development.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.4.3. CM3 – Community Impact Monitoring

Concept

The project proponents must have an initial

and economic well-being resulting from the project activities (for communities and other stakeholders).

The monitoring plan must indicate which communities and other stakeholders will be monitored,

identify the types of measurements, the sampling method, and the frequency of measurement.

Since developing a full community monitoring plan can be costly, it is accepted that some of the plan

details may not be fully defined at the design stage, whe

Standards. This is acceptable as long as there is an explicit commitment to develop and implement a

monitoring plan.

Indicators

The project proponents must:

Indicator CM3.1. Develop an initial plan for selectin

frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the

project’s community development objectives and to anticipated impacts (positive and negative).

Findings: The initial PDD did not include monitoring variables that addressed all of the community

development objectives. NCR 16 was issued. The project proponent subsequently revised the PDD to

include this information.

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

48

Being a wildlife corridor the project area play a vital role in ensuring that the migrating wildlife have

most of what they need and hardly attack the community. The protection of the wildlife too will ensure

the existence of the wildlife to perpetuity and so are the tourism industries which brings a lot of foreign

or national development. Thus the net impacts are positive.

Yes No N/A

None

None

None

Community Impact Monitoring

The project proponents must have an initial monitoring plan to quantify and document changes in social

being resulting from the project activities (for communities and other stakeholders).

The monitoring plan must indicate which communities and other stakeholders will be monitored,

identify the types of measurements, the sampling method, and the frequency of measurement.

Since developing a full community monitoring plan can be costly, it is accepted that some of the plan

details may not be fully defined at the design stage, when projects are being validated against the

Standards. This is acceptable as long as there is an explicit commitment to develop and implement a

Develop an initial plan for selecting community variables to be monitored and the

frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the

project’s community development objectives and to anticipated impacts (positive and negative).

The initial PDD did not include monitoring variables that addressed all of the community

development objectives. NCR 16 was issued. The project proponent subsequently revised the PDD to

Yes No N/A

that the migrating wildlife have

most of what they need and hardly attack the community. The protection of the wildlife too will ensure

the existence of the wildlife to perpetuity and so are the tourism industries which brings a lot of foreign

monitoring plan to quantify and document changes in social

being resulting from the project activities (for communities and other stakeholders).

The monitoring plan must indicate which communities and other stakeholders will be monitored, and

identify the types of measurements, the sampling method, and the frequency of measurement.

Since developing a full community monitoring plan can be costly, it is accepted that some of the plan

n projects are being validated against the

Standards. This is acceptable as long as there is an explicit commitment to develop and implement a

g community variables to be monitored and the

frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the

project’s community development objectives and to anticipated impacts (positive and negative).

The initial PDD did not include monitoring variables that addressed all of the community

development objectives. NCR 16 was issued. The project proponent subsequently revised the PDD to

Page 52: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NCR Number 16 of 19 for October 20, 2009

Finding: The selected monitoring variables do not address all of the community development

objectives. The monitoring variables must be directly linked to the community development objectives.

Proponent Response on November 1

extensive list of monitoring variables organized by specific Project Activity. The text of that section is

included below. We believe this represents a complete and acceptable response to your f

meets the standard and we ask that you close finding NCR#16.

Validator Response: The information provided is adequate.

New Information Requests:

Opportunities for Improvement:

Indicator CM3.2. Develop an initial plan for how they will assess the effectiveness of measures used to

maintain or enhance High Conservation Values related to community well

the project zone.

Findings: The project proponent has not outlined

assessing the effectiveness of measures used to maintain or enhance High Conservation Values related

to community well-being present in the project zone. However the proponent has described how the

project will use the game rangers on daily basis to monitor some of the endangered endemic wildlife

species in the ranch. They hope to use the carbon finance to upscale the wildlife monitoring intensity

and the range of monitoring.

In addition the Global Positioning System (GPS) coordinates of the areas where the monitored species of

wildlife are mostly sighted will help the management in designing an effective surveillance and

monitoring programme since such areas are more vulnerable to poaching or disease o

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator CM3.3. Commit to developing a full monitoring plan within six months of the project start

date or within twelve months of validation against the Standards and to disseminate this plan and the

results of monitoring, ensuring that they are made publicly available

communicated to the communities and other stakeholders.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

49

19 for October 20, 2009

The selected monitoring variables do not address all of the community development

objectives. The monitoring variables must be directly linked to the community development objectives.

November 1, 2009: We have significantly enhanced Section CM3.1 to add an

extensive list of monitoring variables organized by specific Project Activity. The text of that section is

included below. We believe this represents a complete and acceptable response to your f

meets the standard and we ask that you close finding NCR#16.

The information provided is adequate.

None

None

Develop an initial plan for how they will assess the effectiveness of measures used to

maintain or enhance High Conservation Values related to community well-being (G1.8.4

The project proponent has not outlined in the revised PDD, the means that will be used in

assessing the effectiveness of measures used to maintain or enhance High Conservation Values related

being present in the project zone. However the proponent has described how the

ect will use the game rangers on daily basis to monitor some of the endangered endemic wildlife

species in the ranch. They hope to use the carbon finance to upscale the wildlife monitoring intensity

itioning System (GPS) coordinates of the areas where the monitored species of

wildlife are mostly sighted will help the management in designing an effective surveillance and

monitoring programme since such areas are more vulnerable to poaching or disease out break.

Yes No N/A

See NCR Number 2 of 19 for October 20, 2009

None

None

Commit to developing a full monitoring plan within six months of the project start

date or within twelve months of validation against the Standards and to disseminate this plan and the

results of monitoring, ensuring that they are made publicly available on the internet and are

communicated to the communities and other stakeholders.

The selected monitoring variables do not address all of the community development

objectives. The monitoring variables must be directly linked to the community development objectives.

We have significantly enhanced Section CM3.1 to add an

extensive list of monitoring variables organized by specific Project Activity. The text of that section is

included below. We believe this represents a complete and acceptable response to your finding and

Develop an initial plan for how they will assess the effectiveness of measures used to

being (G1.8.4-6) present in

in the revised PDD, the means that will be used in

assessing the effectiveness of measures used to maintain or enhance High Conservation Values related

being present in the project zone. However the proponent has described how the

ect will use the game rangers on daily basis to monitor some of the endangered endemic wildlife

species in the ranch. They hope to use the carbon finance to upscale the wildlife monitoring intensity

itioning System (GPS) coordinates of the areas where the monitored species of

wildlife are mostly sighted will help the management in designing an effective surveillance and

ut break.

NCR Number 2 of 19 for October 20, 2009

Commit to developing a full monitoring plan within six months of the project start

date or within twelve months of validation against the Standards and to disseminate this plan and the

on the internet and are

Page 53: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Findings: The project proponent has committed in the revised PDD to develop a detailed monitoring

plan within twelve months of validation. He has also promise to make such a

stakeholders via the internet as required by the

During the field site visit, the project proponent assured the audit team that the project will establish a

detailed monitoring plan for the project.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.5. Biodiversity Section

3.5.1. B1 – Net Positive Biodiversity Impacts

Concept

The project must generate net positive impacts on biodiversity within the project z

project lifetime, measured against the baseline conditions.

The project should maintain or enhance any High Conservation Values (identified in

project zone that are of importance in conserving globally, regionally or

biodiversity.

Invasive species populations must not increase as a result of the project, either through direct use or

indirectly as a result of project activities.

Projects may not use genetically modified organisms (GMOs) to

removals. GMOs raise unresolved ethical, scientific and socio

attributes may result in invasive genes or species.

Indicators

The project proponents must:

Indicator B1.1. Use appropriate methodologies to estimate changes in biodiversity as a result of the

project in the project zone and in the project lifetime. This estimate must be based on clearly defined

and defendable assumptions. The ‘with project’ scenario should then be comp

‘without project’ biodiversity scenario completed in

must be positive.

Findings: Wildlife Works has addressed very well the changes on biodiversity in the revised PDD. It is

true that the management of Wildlife Works has been keen on estimating the biodiversity changes using

their rangers that go on daily patrols of the ranch.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

50

The project proponent has committed in the revised PDD to develop a detailed monitoring

plan within twelve months of validation. He has also promise to make such a plan available to the

stakeholders via the internet as required by the CCB Standards.

During the field site visit, the project proponent assured the audit team that the project will establish a

detailed monitoring plan for the project.

Yes No N/A

None

None

None

Net Positive Biodiversity Impacts

The project must generate net positive impacts on biodiversity within the project zone and within the

project lifetime, measured against the baseline conditions.

The project should maintain or enhance any High Conservation Values (identified in G1

project zone that are of importance in conserving globally, regionally or nationally significant

Invasive species populations must not increase as a result of the project, either through direct use or

indirectly as a result of project activities.

Projects may not use genetically modified organisms (GMOs) to generate GHG emissions reductions or

removals. GMOs raise unresolved ethical, scientific and socio-economic issues. For example, some GMO

attributes may result in invasive genes or species.

opriate methodologies to estimate changes in biodiversity as a result of the

the project zone and in the project lifetime. This estimate must be based on clearly defined

defendable assumptions. The ‘with project’ scenario should then be compared with the baseline

‘without project’ biodiversity scenario completed in G2. The difference (i.e., the net biodiversity

Wildlife Works has addressed very well the changes on biodiversity in the revised PDD. It is

true that the management of Wildlife Works has been keen on estimating the biodiversity changes using

s that go on daily patrols of the ranch.

The project proponent has committed in the revised PDD to develop a detailed monitoring

plan available to the

During the field site visit, the project proponent assured the audit team that the project will establish a

one and within the

G1) present in the

nationally significant

Invasive species populations must not increase as a result of the project, either through direct use or

generate GHG emissions reductions or

economic issues. For example, some GMO

opriate methodologies to estimate changes in biodiversity as a result of the

the project zone and in the project lifetime. This estimate must be based on clearly defined

ared with the baseline

. The difference (i.e., the net biodiversity benefit)

Wildlife Works has addressed very well the changes on biodiversity in the revised PDD. It is

true that the management of Wildlife Works has been keen on estimating the biodiversity changes using

Page 54: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

The project proponent provided documentary evidence of the methodologies used in biodiversity

changes in the ranch and these were availed to the audit team during the field site visit. During the field

site visit also the audit team also observed the biodiversity data collection technique and analysis.

The preservation of the ecosystems and habitat

rangers were seen keeping off the ranch those illegally grazing in the ranch and promoting over grazing

and land degradation in particular areas of the ranch. The intensity of patrol and surveillance ha

those poaching for bush meat for sale and trophies off not to operate in the ranch. By working together

with the Kenya Wildlife Services (KWS), Wildlife Works has asked for reinforcement whenever

necessary.

The permanent vegetation plots also help

time in a situation of free grazing by wildlife. However there are other components of biodiversity

which too are indicators of the biodiversity health and may need to be monitored as well becau

too are important in nutrient recycling. They include arthropods, birds, reptiles, amphibians, small

mammals besides large mammals like elephants, zebra, buffaloes, giraffe etc.

The ‘with project’ scenario will ensure sustainable conservation of

rightly described by the project proponent in the PDD. The ‘without project’ scenario will lead to quick

destruction and disappearance of the endemic and already endangered species of biodiversity in the

ranch because even at its protection and intense patrols and surveillance by the

there is pressure from those living around the ranch and generally in the project zone.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator B1.2. Demonstrate that no High Conservation Values identified in

affected by the project.

Findings: The project proponent stated in the revised PDD that there will not be any negative

the High Conservation Values, contending that it is their day to day duty to conserve such areas.

The results of the audit confirm that HCVs will not be negatively affected by the project.

Conformance:

Non-Conformity Reports:

New Information Requests:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

51

The project proponent provided documentary evidence of the methodologies used in biodiversity

ges in the ranch and these were availed to the audit team during the field site visit. During the field

site visit also the audit team also observed the biodiversity data collection technique and analysis.

The preservation of the ecosystems and habitat was also observed during the field site visit where

rangers were seen keeping off the ranch those illegally grazing in the ranch and promoting over grazing

and land degradation in particular areas of the ranch. The intensity of patrol and surveillance ha

those poaching for bush meat for sale and trophies off not to operate in the ranch. By working together

with the Kenya Wildlife Services (KWS), Wildlife Works has asked for reinforcement whenever

The permanent vegetation plots also help the ranch management in tracking vegetation transition with

time in a situation of free grazing by wildlife. However there are other components of biodiversity

which too are indicators of the biodiversity health and may need to be monitored as well becau

too are important in nutrient recycling. They include arthropods, birds, reptiles, amphibians, small

mammals besides large mammals like elephants, zebra, buffaloes, giraffe etc.

The ‘with project’ scenario will ensure sustainable conservation of biodiversity in the ranch as has been

rightly described by the project proponent in the PDD. The ‘without project’ scenario will lead to quick

destruction and disappearance of the endemic and already endangered species of biodiversity in the

e even at its protection and intense patrols and surveillance by the Wildlife Works rangers,

pressure from those living around the ranch and generally in the project zone.

Yes No N/A

None

None

None

Demonstrate that no High Conservation Values identified in G1.8.1-348 will be negatively

The project proponent stated in the revised PDD that there will not be any negative

the High Conservation Values, contending that it is their day to day duty to conserve such areas.

The results of the audit confirm that HCVs will not be negatively affected by the project.

Yes No N/A

None

None

The project proponent provided documentary evidence of the methodologies used in biodiversity

ges in the ranch and these were availed to the audit team during the field site visit. During the field

site visit also the audit team also observed the biodiversity data collection technique and analysis.

was also observed during the field site visit where

rangers were seen keeping off the ranch those illegally grazing in the ranch and promoting over grazing

and land degradation in particular areas of the ranch. The intensity of patrol and surveillance has kept

those poaching for bush meat for sale and trophies off not to operate in the ranch. By working together

with the Kenya Wildlife Services (KWS), Wildlife Works has asked for reinforcement whenever

the ranch management in tracking vegetation transition with

time in a situation of free grazing by wildlife. However there are other components of biodiversity

which too are indicators of the biodiversity health and may need to be monitored as well because they

too are important in nutrient recycling. They include arthropods, birds, reptiles, amphibians, small

biodiversity in the ranch as has been

rightly described by the project proponent in the PDD. The ‘without project’ scenario will lead to quick

destruction and disappearance of the endemic and already endangered species of biodiversity in the

Wildlife Works rangers,

48 will be negatively

The project proponent stated in the revised PDD that there will not be any negative impact on

the High Conservation Values, contending that it is their day to day duty to conserve such areas.

The results of the audit confirm that HCVs will not be negatively affected by the project.

Page 55: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Opportunities for Improvement:

Indicator B1.3. Identify all species to be used by the project and show that no known in

will be introduced into any area affected by the project and that the population of any invasive species

will not increase as a result of the project.

Findings: The project proponent has explained in the revised PDD that there are no new s

are being introduced in the project area and hence the action of the project will not lead to introduction

of the invasive species in the project area.

During the site visit, the audit team evaluated the species being raised in the project’s G

only noted that the composition of the species are agroforestry species and some exotic species which

have been researched on and found to be suitable for dryland afforestation activities and have no ability

for invasiveness and so are not a threat to the biodiversity conservation in the area.

The audit team also confirmed that Wildlife Works is following up the suitability of Jojoba (Simmondsia

chinensis) as a cash crop and confirmed that although this was introduced in the project area

years ago before Wildlife Works took over the management of the ranch. However this species too has

not spread beyond the areas where it was introduced, showing that it is not invasive and so has no

threat to the biodiversity of the project area.

Conformance:

Non-Conformity Reports:

NCR Number 17 of 19 for October 20, 2009

Finding: The project proponent must identify all species to be used by the project including those

provided by the greenhouse project activity and other project activities. If some of the

native , describe the possible adverse effects. Also, justify why non

species.

Proponent Response on October 29

include the text below.

We believe that this new information provided to the Validator is a more than adequate response to

your finding and we ask that you consider this finding NCR#17 closed.

Validator Response: The response is adequate.

New Information Requests:

Opportunities for Improvement:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

52

None

Identify all species to be used by the project and show that no known in

introduced into any area affected by the project and that the population of any invasive species

will not increase as a result of the project.

The project proponent has explained in the revised PDD that there are no new s

are being introduced in the project area and hence the action of the project will not lead to introduction

of the invasive species in the project area.

During the site visit, the audit team evaluated the species being raised in the project’s G

only noted that the composition of the species are agroforestry species and some exotic species which

have been researched on and found to be suitable for dryland afforestation activities and have no ability

threat to the biodiversity conservation in the area.

The audit team also confirmed that Wildlife Works is following up the suitability of Jojoba (Simmondsia

chinensis) as a cash crop and confirmed that although this was introduced in the project area

years ago before Wildlife Works took over the management of the ranch. However this species too has

not spread beyond the areas where it was introduced, showing that it is not invasive and so has no

threat to the biodiversity of the project area.

Yes No N/A

NCR Number 17 of 19 for October 20, 2009

The project proponent must identify all species to be used by the project including those

provided by the greenhouse project activity and other project activities. If some of the

native , describe the possible adverse effects. Also, justify why non-native species are used over native

October 29, 2009: We have revised sections B1.3 and B1.4 of the PDD to

We believe that this new information provided to the Validator is a more than adequate response to

your finding and we ask that you consider this finding NCR#17 closed.

The response is adequate.

None

None

Identify all species to be used by the project and show that no known invasive species

introduced into any area affected by the project and that the population of any invasive species

The project proponent has explained in the revised PDD that there are no new species that

are being introduced in the project area and hence the action of the project will not lead to introduction

During the site visit, the audit team evaluated the species being raised in the project’s Green House and

only noted that the composition of the species are agroforestry species and some exotic species which

have been researched on and found to be suitable for dryland afforestation activities and have no ability

The audit team also confirmed that Wildlife Works is following up the suitability of Jojoba (Simmondsia

chinensis) as a cash crop and confirmed that although this was introduced in the project area many

years ago before Wildlife Works took over the management of the ranch. However this species too has

not spread beyond the areas where it was introduced, showing that it is not invasive and so has no

The project proponent must identify all species to be used by the project including those

provided by the greenhouse project activity and other project activities. If some of the species are non-

native species are used over native

We have revised sections B1.3 and B1.4 of the PDD to

We believe that this new information provided to the Validator is a more than adequate response to

Page 56: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Indicator B1.4. Describe possible adverse effects of non

region’s environment, including impacts on native species and disease introduction or facilitation.

Project proponents must justify any use of non

Findings: The project prominent in the revised PDD explained that this indicator does not apply. And

during the site visit, the audit team too confirmed that the fast growing exotic species

project’s Green House nursery are not planted in the project area but are rather given out to the local

community for planting in their private farms as a way of empowering the community to produce their

own forest products for their use.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator B1.5. Guarantee that no GMOs will be used to generate GHG emissions reductions or

removals.

Findings: The project proponent has explained in the PDD that no GMOs will be used to generate GHG

emissions reductions or their removal.

This was confirmed by the audit team who confirmed that the species raised in the Green House tree

nursery are not planted in the Wildlife Works project and the Green House tree nursery does not raise

GMOs.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.5.2. B2 – Offsite Biodiversity Impacts

Concept

The project proponents must evaluate and mitigate likely negative impacts on biodiversity outside the

project zone resulting from project activities.

Indicators

The project proponents must:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

53

Describe possible adverse effects of non-native species used by the project on the

environment, including impacts on native species and disease introduction or facilitation.

ustify any use of non-native species over native species.

The project prominent in the revised PDD explained that this indicator does not apply. And

during the site visit, the audit team too confirmed that the fast growing exotic species

project’s Green House nursery are not planted in the project area but are rather given out to the local

community for planting in their private farms as a way of empowering the community to produce their

Yes No N/A

See NCR Number 17 of 19 for October 20, 2009

None

None

Guarantee that no GMOs will be used to generate GHG emissions reductions or

The project proponent has explained in the PDD that no GMOs will be used to generate GHG

emissions reductions or their removal.

This was confirmed by the audit team who confirmed that the species raised in the Green House tree

he Wildlife Works project and the Green House tree nursery does not raise

Yes No N/A

None

None

None

Offsite Biodiversity Impacts

aluate and mitigate likely negative impacts on biodiversity outside the

project zone resulting from project activities.

native species used by the project on the

environment, including impacts on native species and disease introduction or facilitation.

The project prominent in the revised PDD explained that this indicator does not apply. And

during the site visit, the audit team too confirmed that the fast growing exotic species raised in the

project’s Green House nursery are not planted in the project area but are rather given out to the local

community for planting in their private farms as a way of empowering the community to produce their

NCR Number 17 of 19 for October 20, 2009

Guarantee that no GMOs will be used to generate GHG emissions reductions or

The project proponent has explained in the PDD that no GMOs will be used to generate GHG

This was confirmed by the audit team who confirmed that the species raised in the Green House tree

he Wildlife Works project and the Green House tree nursery does not raise

aluate and mitigate likely negative impacts on biodiversity outside the

Page 57: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Indicator B2.1. Identify potential negative offsite biodiversity impacts that the project is likely to cause.

Findings: In the revised PDD, the project proponent has described that as a result of the project; there

will be no offsite negative impact on biodiversity.

Following the field site visit, the audit team established that as a result of the project, there will not be

any potential negative offsite biodiversity impacts that the project is likely to cause, but rather it will

have offsite positive biodiversity impact due to its activities.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator B2.2. Document how the project plans to mitigate these negative offsite biodiversity impacts.

Findings: Based on the response in B2.1 above, this indicator does not apply. The project proponent

has also responded the same in the revised PDD.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator B2.3. Evaluate likely unmitigated negative offsite biodiversity impacts

benefits of the project within the project boundaries. Justify and demonstrate that the net effect of the

project on biodiversity is positive.

Findings: The project proponent in the PDD does not anticipate any negative offsite bi

impacts from the project. But the net effect of the project on biodiversity in the Wildlife Works projects

and offsite is expected to be positive.

Conformance:

Non-Conformity Reports:

New Information Requests:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

54

Identify potential negative offsite biodiversity impacts that the project is likely to cause.

In the revised PDD, the project proponent has described that as a result of the project; there

will be no offsite negative impact on biodiversity.

Following the field site visit, the audit team established that as a result of the project, there will not be

any potential negative offsite biodiversity impacts that the project is likely to cause, but rather it will

mpact due to its activities.

Yes No N/A

None

None

None

Document how the project plans to mitigate these negative offsite biodiversity impacts.

on the response in B2.1 above, this indicator does not apply. The project proponent

has also responded the same in the revised PDD.

Yes No N/A

None

None

None

Evaluate likely unmitigated negative offsite biodiversity impacts against the biodiversity

benefits of the project within the project boundaries. Justify and demonstrate that the net effect of the

The project proponent in the PDD does not anticipate any negative offsite bi

impacts from the project. But the net effect of the project on biodiversity in the Wildlife Works projects

and offsite is expected to be positive.

Yes No N/A

None

None

Identify potential negative offsite biodiversity impacts that the project is likely to cause.

In the revised PDD, the project proponent has described that as a result of the project; there

Following the field site visit, the audit team established that as a result of the project, there will not be

any potential negative offsite biodiversity impacts that the project is likely to cause, but rather it will

Document how the project plans to mitigate these negative offsite biodiversity impacts.

on the response in B2.1 above, this indicator does not apply. The project proponent

against the biodiversity

benefits of the project within the project boundaries. Justify and demonstrate that the net effect of the

The project proponent in the PDD does not anticipate any negative offsite biodiversity

impacts from the project. But the net effect of the project on biodiversity in the Wildlife Works projects

Page 58: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Opportunities for Improvement:

3.5.3. B3 – Biodiversity Impact Monitoring

Concept

The project proponents must have an initial monitoring plan to quantify and document the changes in

biodiversity resulting from the project

monitoring plan must identify the types of measurements, the sampling method, and the frequency of

measurement.

Since developing a full biodiversity

details may not be fully defined at the design stage, when projects are being validated against the

Standards. This is acceptable as long as there is an explicit commitment to develop and implement a

monitoring plan.

Indicators

The project proponents must:

Indicator B3.1. Develop an initial plan for selecting biodiversity variables to be monitored and the

frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the

project’s biodiversity objectives and to anticipated impacts (positive and negative).

Findings: The project proponent has highlighted a monitoring schedule that will be used in Wildlife

Works REDD project and also listed a number of variables in the PDD that will be monitored with a

frequency being on a daily basis.

The project proponent however should consider recording the locations of animal and poacher sightings

using a GPS.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

OFI Number 4 of 4 for October 20, 2009

Finding: The project proponent may consider recording the locations of animal and poacher sightings

using a GPS. Also, the project proponent may consider observing characteristics of the population

structure of wildlife species.

Proponent Response on October 24

our Daily Ranger Patrol Sheet to include GPS location and population characteristics, and as this is the

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

55

None

Biodiversity Impact Monitoring

The project proponents must have an initial monitoring plan to quantify and document the changes in

biodiversity resulting from the project activities (within and outside the project boundaries). The

monitoring plan must identify the types of measurements, the sampling method, and the frequency of

Since developing a full biodiversity-monitoring plan can be costly, it is accepted that some of the plan

details may not be fully defined at the design stage, when projects are being validated against the

Standards. This is acceptable as long as there is an explicit commitment to develop and implement a

Develop an initial plan for selecting biodiversity variables to be monitored and the

frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the

ives and to anticipated impacts (positive and negative).

The project proponent has highlighted a monitoring schedule that will be used in Wildlife

Works REDD project and also listed a number of variables in the PDD that will be monitored with a

The project proponent however should consider recording the locations of animal and poacher sightings

Yes No N/A

None

None

OFI Number 4 of 4 for October 20, 2009

The project proponent may consider recording the locations of animal and poacher sightings

using a GPS. Also, the project proponent may consider observing characteristics of the population

October 24, 2009: This is an excellent suggestion and we have now adapted

our Daily Ranger Patrol Sheet to include GPS location and population characteristics, and as this is the

The project proponents must have an initial monitoring plan to quantify and document the changes in

activities (within and outside the project boundaries). The

monitoring plan must identify the types of measurements, the sampling method, and the frequency of

that some of the plan

details may not be fully defined at the design stage, when projects are being validated against the

Standards. This is acceptable as long as there is an explicit commitment to develop and implement a

Develop an initial plan for selecting biodiversity variables to be monitored and the

frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the

The project proponent has highlighted a monitoring schedule that will be used in Wildlife

Works REDD project and also listed a number of variables in the PDD that will be monitored with a

The project proponent however should consider recording the locations of animal and poacher sightings

The project proponent may consider recording the locations of animal and poacher sightings

using a GPS. Also, the project proponent may consider observing characteristics of the population

This is an excellent suggestion and we have now adapted

our Daily Ranger Patrol Sheet to include GPS location and population characteristics, and as this is the

Page 59: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

primary instrument for daily monitor

in every day by the three teams of Rangers in the bush, we believe this will provide us more granular

data on Biodiversity in the Project Area. We believe this fully address this OFI

considered closed.

Validator Response: NA

Indicator B3.2. Develop an initial plan for assessing the effectiveness of measures used to maintain or

enhance High Conservation Values related to globally, regionally or nationally

(G1.8.1-3) present in the project zone.

Findings: The project proponent stated in the revised PDD how Wildlife Works has used the rangers to

assess species richness in Rukinga ecosystem, avert illegal activities such as grazing o

and incidence of fire.

The intention to expand monitoring schedule to enhance High Conservation Values related to globally,

regionally or nationally significant biodiversity (G1.8.1

strengthen the species monitoring plan.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator B3.3. Commit to developing a full monitoring plan within six months of the project start date

or within twelve months of validation against the Standards and to disseminate this plan and the results

of monitoring, ensuring that they are made publicly available on the internet and are communicated to

the communities and other stakeholders.

Findings: At the time of the site visit, the project proponent had not fully developed a full monitoring

plan. However in the revised PDD, the project proponent has committed to develop full monitoring plan

within twelve months of validation against the Standards

He also committed to disseminate the plan and the results of monitoring, ensuring that they are made

publicly available on the internet and are communicated to the communities and other stakeholders

Conformance:

Non-Conformity Reports:

New Information Requests:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

56

primary instrument for daily monitoring of the health of the Biodiversity in the Project Area, and is filled

in every day by the three teams of Rangers in the bush, we believe this will provide us more granular

data on Biodiversity in the Project Area. We believe this fully address this OFI and this should now be

Develop an initial plan for assessing the effectiveness of measures used to maintain or

enhance High Conservation Values related to globally, regionally or nationally significant biodiversity

present in the project zone.

The project proponent stated in the revised PDD how Wildlife Works has used the rangers to

assess species richness in Rukinga ecosystem, avert illegal activities such as grazing o

The intention to expand monitoring schedule to enhance High Conservation Values related to globally,

regionally or nationally significant biodiversity (G1.8.1-3) present in the project zone is ideal too and will

strengthen the species monitoring plan.

Yes No N/A

See NCR Number 2 of 19 for October 20, 2009

None

None

Commit to developing a full monitoring plan within six months of the project start date

or within twelve months of validation against the Standards and to disseminate this plan and the results

ensuring that they are made publicly available on the internet and are communicated to

the communities and other stakeholders.

At the time of the site visit, the project proponent had not fully developed a full monitoring

revised PDD, the project proponent has committed to develop full monitoring plan

within twelve months of validation against the Standards

He also committed to disseminate the plan and the results of monitoring, ensuring that they are made

le on the internet and are communicated to the communities and other stakeholders

Yes No N/A

None

None

ing of the health of the Biodiversity in the Project Area, and is filled

in every day by the three teams of Rangers in the bush, we believe this will provide us more granular

and this should now be

Develop an initial plan for assessing the effectiveness of measures used to maintain or

significant biodiversity

The project proponent stated in the revised PDD how Wildlife Works has used the rangers to

assess species richness in Rukinga ecosystem, avert illegal activities such as grazing of cattle, poaching

The intention to expand monitoring schedule to enhance High Conservation Values related to globally,

3) present in the project zone is ideal too and will

NCR Number 2 of 19 for October 20, 2009

Commit to developing a full monitoring plan within six months of the project start date

or within twelve months of validation against the Standards and to disseminate this plan and the results

ensuring that they are made publicly available on the internet and are communicated to

At the time of the site visit, the project proponent had not fully developed a full monitoring

revised PDD, the project proponent has committed to develop full monitoring plan

He also committed to disseminate the plan and the results of monitoring, ensuring that they are made

le on the internet and are communicated to the communities and other stakeholders

Page 60: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Opportunities for Improvement:

3.6. Gold Level Section

3.6.1. GL1 – Climate Change Adaptation Bene

This Gold Level Climate Change Adaptation Benefits criterion identifies projects that will provide

significant support to assist communities and/or biodiversity in adapting to the impacts of climate

change. Anticipated local climate change and climate variability within the project zone could potentially

affect communities and biodiversity during the life of the project and beyond.

biodiversity in some areas of the world will be more vulnerable to the negative impacts of these changes

due to: vulnerability of key crops or production systems to climatic changes; lack of diversity of

livelihood resources and inadequate

strategies; and high levels of threat to species survival from habitat fragmentation. Land

projects have the potential to help local communities and biodiversity adapt to climate c

diversifying revenues and livelihood strategies; maintaining valuable ecosystem services such as

hydrological regulation, pollination, pest control and soil fertility; and increasing habitat connectivity

across a range of habitat and climate type

Indicators

The project proponents must:

Indicator GL1.1. Identify likely regional climate change and climate variability scenarios and impacts,

using available studies, and identify potential changes in the local land

change scenarios in the absence of the project.

Findings: The likely regional climate change and variability scenarios and impacts are identified in

Section GL1.1 of the revised PDD. These scenarios were supplemented with available studies (see

Number 5 of 5 for October 20, 2009

in the PDD seem accurate based on the references provided.

Conformance:

Non-Conformity Reports:

New Information Requests:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

57

None

Climate Change Adaptation Benefits

This Gold Level Climate Change Adaptation Benefits criterion identifies projects that will provide

communities and/or biodiversity in adapting to the impacts of climate

Anticipated local climate change and climate variability within the project zone could potentially

communities and biodiversity during the life of the project and beyond.

some areas of the world will be more vulnerable to the negative impacts of these changes

vulnerability of key crops or production systems to climatic changes; lack of diversity of

resources and inadequate resources, institutions and capacity to develop new livelihood

high levels of threat to species survival from habitat fragmentation. Land

potential to help local communities and biodiversity adapt to climate c

and livelihood strategies; maintaining valuable ecosystem services such as

pollination, pest control and soil fertility; and increasing habitat connectivity

climate types.

Identify likely regional climate change and climate variability scenarios and impacts,

available studies, and identify potential changes in the local land-use scenario due to these

change scenarios in the absence of the project.

The likely regional climate change and variability scenarios and impacts are identified in

Section GL1.1 of the revised PDD. These scenarios were supplemented with available studies (see

Number 5 of 5 for October 20, 2009). The identified potential changes in the local land

in the PDD seem accurate based on the references provided.

Yes No N/A

None

This Gold Level Climate Change Adaptation Benefits criterion identifies projects that will provide

communities and/or biodiversity in adapting to the impacts of climate

Anticipated local climate change and climate variability within the project zone could potentially

communities and biodiversity during the life of the project and beyond. Communities and

some areas of the world will be more vulnerable to the negative impacts of these changes

vulnerability of key crops or production systems to climatic changes; lack of diversity of

resources, institutions and capacity to develop new livelihood

high levels of threat to species survival from habitat fragmentation. Land-based carbon

potential to help local communities and biodiversity adapt to climate change by:

and livelihood strategies; maintaining valuable ecosystem services such as

pollination, pest control and soil fertility; and increasing habitat connectivity

Identify likely regional climate change and climate variability scenarios and impacts,

use scenario due to these climate

The likely regional climate change and variability scenarios and impacts are identified in

Section GL1.1 of the revised PDD. These scenarios were supplemented with available studies (see NIR

The identified potential changes in the local land-use as described

Page 61: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

NIR Number 5 of 5 for October 20, 2009

Finding: Provide references to available studies used to identify likely regional climate change and

climate variability scenarios.

Proponent Response on October 24

on Climate Change in Kenya, East Africa and Sub

included that text below. We believe this adequately addresses this finding and ask that the finding NIR

#5 be closed.

Validator Response: The response is adequate.

Opportunities for Improvement:

Indicator GL1.2.Identify any risks to the project’s climate, community and biodiversity benefits resulting

from likely climate change and climate variability impacts and explain how these risks will be

Findings: Given the likely climate change impacts described in Section GL1.1 of the revised PDD, the

project proponent has identified several risks to the project’s benefits: scarcity in food would affect the

demand for bush meat poached from the project

animals, increased pressure for cattle grazing within the project area and scarcity of water in general.

These identified risks are reasonable given the li

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator GL1.3. Demonstrate that current or anticipated climate changes are having or are likely to

have an impact on the well-being of communities

project zone and surrounding regions.

Findings: In Section GL1.2, the project proponent has demonstrated that current

changes are likely to have an impact on

biodiversity in the project zone. This section was supplemented for Indicator GL1.3 based on a finding

during the course of the audit (see

impacts are also likely to have an impact on

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

58

20, 2009

Provide references to available studies used to identify likely regional climate change and

October 24, 2009: We have added a list of published references to the impact

ange in Kenya, East Africa and Sub-Saharan Africa to the PDD in section GL1.1. We have

included that text below. We believe this adequately addresses this finding and ask that the finding NIR

The response is adequate.

None

Identify any risks to the project’s climate, community and biodiversity benefits resulting

likely climate change and climate variability impacts and explain how these risks will be

Given the likely climate change impacts described in Section GL1.1 of the revised PDD, the

project proponent has identified several risks to the project’s benefits: scarcity in food would affect the

demand for bush meat poached from the project area, degradation of the natural food sources for wild

animals, increased pressure for cattle grazing within the project area and scarcity of water in general.

These identified risks are reasonable given the likely climate change impacts for local land

Yes No N/A

None

None

None

Demonstrate that current or anticipated climate changes are having or are likely to

being of communities and/or the conservation status of biodiversity

zone and surrounding regions.

In Section GL1.2, the project proponent has demonstrated that current or anticipated climate

changes are likely to have an impact on the well-being of communities and the conse

zone. This section was supplemented for Indicator GL1.3 based on a finding

during the course of the audit (see Number 18 of 19 for October 20, 2009). These anticipated climate

impacts are also likely to have an impact on surrounding regions.

Yes No N/A

See NCR Number 18 of 19 for October 20, 2009

Provide references to available studies used to identify likely regional climate change and

We have added a list of published references to the impact

Saharan Africa to the PDD in section GL1.1. We have

included that text below. We believe this adequately addresses this finding and ask that the finding NIR

Identify any risks to the project’s climate, community and biodiversity benefits resulting

likely climate change and climate variability impacts and explain how these risks will be mitigated.

Given the likely climate change impacts described in Section GL1.1 of the revised PDD, the

project proponent has identified several risks to the project’s benefits: scarcity in food would affect the

area, degradation of the natural food sources for wild

animals, increased pressure for cattle grazing within the project area and scarcity of water in general.

kely climate change impacts for local land-use.

Demonstrate that current or anticipated climate changes are having or are likely to

rvation status of biodiversity in the

or anticipated climate

the conservation status of

zone. This section was supplemented for Indicator GL1.3 based on a finding

These anticipated climate

NCR Number 18 of 19 for October 20, 2009

Page 62: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

New Information Requests:

Opportunities for Improvement:

Indicator GL1.4. Demonstrate that the project activities will

adapt to the probable impacts of climate change.

Findings: As described in the revised PDD and observed during the site visit, the project proponent

demonstrates that the project activities will assist communities and biodiversity to adapt to the

probable impact of climate change. The project proponent will: create livelihoods alternative to

agriculture, improve efficiency of agriculture production and protection of t

poachers.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.6.2. GL2 – Exceptional Community Benefits

This Gold Level Exceptional Community Benefits criterion recognizes project approaches that are

explicitly pro-poor in terms of targeting benefits to globally poorer communities

vulnerable households and individuals within them. In so doing, land

significant contribution to reducing the poverty an

groups. Given that poorer people typically have less access to land and other natural assets, this

optional criterion requires innovative approaches that enable poorer households to participate

effectively in land-based carbon activities. Furthermore, this criterion requires that the project will ‘do

no harm’ to poorer and more vulnerable members of the communities, by establishing that no member

of a poorer or more vulnerable social group will experience a n

rights.

Indicators

Project proponents must:

Indicator GL2.1. Demonstrate that the project zone is in a low human development country OR in an

administrative area of a medium or high human development country in wh

population of that area is below the national poverty line.

Findings: The project proponent has elected not to pursue these optional Gold Level criteria.

Conformance:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

59

None

None

Demonstrate that the project activities will assist communities and/or

the probable impacts of climate change.

As described in the revised PDD and observed during the site visit, the project proponent

the project activities will assist communities and biodiversity to adapt to the

probable impact of climate change. The project proponent will: create livelihoods alternative to

agriculture, improve efficiency of agriculture production and protection of the project area from

Yes No N/A

None

None

None

Exceptional Community Benefits

This Gold Level Exceptional Community Benefits criterion recognizes project approaches that are

poor in terms of targeting benefits to globally poorer communities and

vulnerable households and individuals within them. In so doing, land-based carbon projects can make a

significant contribution to reducing the poverty and enhancing the sustainable livelihoods of these

Given that poorer people typically have less access to land and other natural assets, this

requires innovative approaches that enable poorer households to participate

carbon activities. Furthermore, this criterion requires that the project will ‘do

vulnerable members of the communities, by establishing that no member

social group will experience a net negative impact on their well

Demonstrate that the project zone is in a low human development country OR in an

administrative area of a medium or high human development country in which at least 50% of

population of that area is below the national poverty line.

The project proponent has elected not to pursue these optional Gold Level criteria.

Yes No N/A

and/or biodiversity to

As described in the revised PDD and observed during the site visit, the project proponent

the project activities will assist communities and biodiversity to adapt to the

probable impact of climate change. The project proponent will: create livelihoods alternative to

he project area from

This Gold Level Exceptional Community Benefits criterion recognizes project approaches that are

and the poorer, more

based carbon projects can make a

d enhancing the sustainable livelihoods of these

Given that poorer people typically have less access to land and other natural assets, this

requires innovative approaches that enable poorer households to participate

carbon activities. Furthermore, this criterion requires that the project will ‘do

vulnerable members of the communities, by establishing that no member

et negative impact on their well-being or

Demonstrate that the project zone is in a low human development country OR in an

ich at least 50% of the

The project proponent has elected not to pursue these optional Gold Level criteria.

Page 63: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator GL2.2. Demonstrate that at least 50% of households within the lowest category of well

(e.g., poorest quartile) of the community are likely to benefit substantially from the pr

Findings: The project proponent has elected not to pursue these optional Gold Level criteria.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator GL2.3. Demonstrate that any barriers or risks that might prevent benefits going to poorer

households have been identified and addressed in order to increase the probable flow of benefits

poorer households.

Findings: The project proponent has elected not to pursue these optional Gold Level criteria.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Indicator GL2.4. Demonstrate that measures have been taken to identify any poorer and more

vulnerable households and individuals whose well

project, and that the project design includes measures to avoid any such impacts.

impacts are unavoidable, demonstrate that they will be effectively mitigated.

Findings: The project proponent has elected not to pursue these optional Gold Level criteria.

Conformance:

Non-Conformity Reports:

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

60

None

None

None

Demonstrate that at least 50% of households within the lowest category of well

poorest quartile) of the community are likely to benefit substantially from the project.

The project proponent has elected not to pursue these optional Gold Level criteria.

Yes No N/A

None

None

None

Demonstrate that any barriers or risks that might prevent benefits going to poorer

have been identified and addressed in order to increase the probable flow of benefits

The project proponent has elected not to pursue these optional Gold Level criteria.

Yes No N/A

None

None

None

Demonstrate that measures have been taken to identify any poorer and more

households and individuals whose well-being or poverty may be negatively affected by the

project, and that the project design includes measures to avoid any such impacts.

impacts are unavoidable, demonstrate that they will be effectively mitigated.

The project proponent has elected not to pursue these optional Gold Level criteria.

Yes No N/A

None

Demonstrate that at least 50% of households within the lowest category of well-being

oject.

The project proponent has elected not to pursue these optional Gold Level criteria.

Demonstrate that any barriers or risks that might prevent benefits going to poorer

have been identified and addressed in order to increase the probable flow of benefits to

The project proponent has elected not to pursue these optional Gold Level criteria.

Demonstrate that measures have been taken to identify any poorer and more

being or poverty may be negatively affected by the

project, and that the project design includes measures to avoid any such impacts. Where negative

The project proponent has elected not to pursue these optional Gold Level criteria.

Page 64: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

New Information Requests:

Opportunities for Improvement:

Indicator GL2.5. Demonstrate that community impact monitoring will be able to identify positive and

negative impacts on poorer and more vulnerable groups. The social impact monitoring must take a

differentiated approach that can identify positive and negative impacts on

individuals and other disadvantaged groups, including women.

Findings: The project proponent has elected not to pursue these optional Gold Level criteria.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

3.6.3. GL3 – Exceptional Biodiversity Benefits

All projects conforming to the Standards must demonstrate net positive impacts on biodiversity within

their project zone. This Gold Level

conserve biodiversity at sites of global significance for biodiversity conservation. Sites meeting this

optional criterion must be based on the Key Biodiversity Area (KBA) framework of vu

irreplaceability. These criteria are defined in terms of species and population threat levels, since these

are the most clearly defined elements of biodiversity. These scientifically based criteria are drawn from

existing best practices that have been used, to date, to identify important sites for biodiversity in over

173 countries.

Indicators

Project proponents must demonstrate that the project zone includes a site of high biodiversity

conservation priority by meeting either the vulnerabili

Indicator GL3.1. Vulnerability

Regular occurrence of a globally threatened species (according to the IUCN Red List) at the site:

1.1. Critically Endangered (CR) and Endangered (EN) species

1.2. Vulnerable species (VU) - presence of at least 30 individuals or 10 pairs.

Findings: The project area is inhabited by African elephant (Loxodonta africana) and Grevy’s Zebras

(Equus grevyi), both are globally threatened

The presence of black rhino in both East and West National parks, a critically endangered wildlife species

makes the project area a very important corridor of wildlife.

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

61

None

None

Demonstrate that community impact monitoring will be able to identify positive and

impacts on poorer and more vulnerable groups. The social impact monitoring must take a

differentiated approach that can identify positive and negative impacts on poorer households and

individuals and other disadvantaged groups, including women.

The project proponent has elected not to pursue these optional Gold Level criteria.

Yes No N/A

None

None

None

Exceptional Biodiversity Benefits

All projects conforming to the Standards must demonstrate net positive impacts on biodiversity within

their project zone. This Gold Level Exceptional Biodiversity Benefits criterion identifies projects that

conserve biodiversity at sites of global significance for biodiversity conservation. Sites meeting this

optional criterion must be based on the Key Biodiversity Area (KBA) framework of vu

irreplaceability. These criteria are defined in terms of species and population threat levels, since these

are the most clearly defined elements of biodiversity. These scientifically based criteria are drawn from

t have been used, to date, to identify important sites for biodiversity in over

Project proponents must demonstrate that the project zone includes a site of high biodiversity

conservation priority by meeting either the vulnerability or irreplaceability criteria defined below:

Regular occurrence of a globally threatened species (according to the IUCN Red List) at the site:

1.1. Critically Endangered (CR) and Endangered (EN) species - presence of at least a single

presence of at least 30 individuals or 10 pairs.

The project area is inhabited by African elephant (Loxodonta africana) and Grevy’s Zebras

(Equus grevyi), both are globally threatened species according to the IUCN Red List.

The presence of black rhino in both East and West National parks, a critically endangered wildlife species

makes the project area a very important corridor of wildlife.

Demonstrate that community impact monitoring will be able to identify positive and

impacts on poorer and more vulnerable groups. The social impact monitoring must take a

poorer households and

The project proponent has elected not to pursue these optional Gold Level criteria.

All projects conforming to the Standards must demonstrate net positive impacts on biodiversity within

Exceptional Biodiversity Benefits criterion identifies projects that

conserve biodiversity at sites of global significance for biodiversity conservation. Sites meeting this

optional criterion must be based on the Key Biodiversity Area (KBA) framework of vulnerability and

irreplaceability. These criteria are defined in terms of species and population threat levels, since these

are the most clearly defined elements of biodiversity. These scientifically based criteria are drawn from

t have been used, to date, to identify important sites for biodiversity in over

Project proponents must demonstrate that the project zone includes a site of high biodiversity

irreplaceability criteria defined below:

Regular occurrence of a globally threatened species (according to the IUCN Red List) at the site:

east a single individual; or

The project area is inhabited by African elephant (Loxodonta africana) and Grevy’s Zebras

The presence of black rhino in both East and West National parks, a critically endangered wildlife species

Page 65: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1

Other threatened species, Critically

birds, reptiles, amphibians or even species of insects etc. These require proper research to establish a

more impressive check list of all the species of the ranch.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

Or,

Indicator GL3.1. Irreplaceability

A minimum proportion of a species’ global population present at the site at any stage of the

lifecycle according to the following thresholds:

2.1. Restricted-range species - species with a global range less than 50,000 km2

population at the site; or

2.2. Species with large but clumped distributions

2.3. Globally significant congregations

2.4. Globally significant source populations

Findings: The information provided by the project proponent regarding Gr

above. 3% of the global population of the species is found at the project site making it a globally

significant source population.

Conformance:

Non-Conformity Reports:

New Information Requests:

Opportunities for Improvement:

4.0 CCB Validation Conclusion

Following completion of SCS’s duly

Corridor REDD Project conforms to the CCBA Climate, Community and Biodiversity Project Design

Standards (Second Edition) at the Gold Level

CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009

62

Other threatened species, Critically Endangered (CE) and vulnerable species (VU) may be nocturnal,

birds, reptiles, amphibians or even species of insects etc. These require proper research to establish a

more impressive check list of all the species of the ranch.

Yes No N/A

None

None

None

A minimum proportion of a species’ global population present at the site at any stage of the

following thresholds:

species with a global range less than 50,000 km2

2.2. Species with large but clumped distributions - 5% of the global population at the site; or

significant congregations - 1% of the global population seasonally at the site; or

2.4. Globally significant source populations - 1% of the global population at the site.

The information provided by the project proponent regarding Grevy’s Zebr

above. 3% of the global population of the species is found at the project site making it a globally

Yes No N/A

None

None

None

Validation Conclusion

Following completion of SCS’s duly-accredited validation process, it is our opinion that

conforms to the CCBA Climate, Community and Biodiversity Project Design

Gold Level (see Appendix A).

Endangered (CE) and vulnerable species (VU) may be nocturnal,

birds, reptiles, amphibians or even species of insects etc. These require proper research to establish a

A minimum proportion of a species’ global population present at the site at any stage of the species’

species with a global range less than 50,000 km2 and 5% of global

5% of the global population at the site; or

1% of the global population seasonally at the site; or

’s Zebra conforms to 2.4

above. 3% of the global population of the species is found at the project site making it a globally

accredited validation process, it is our opinion that The Kasigau

conforms to the CCBA Climate, Community and Biodiversity Project Design

Page 66: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix A Page A-1

CCBA Compliance Checklist – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

General Section Conformance

G1. Original Conditions in the Project Area (Required) Yes No

G2. Baseline Projections (Required) Yes No

G3. Project Design and Goals (Required) Yes No

G4. Management Capacity and Best Practices (Required) Yes No

G5. Legal Status and Property Rights (Required) Yes No

Climate Section

CL1. Net Positive Climate Impacts (Required) Yes No

CL2. Offsite Climate Impacts (“Leakage”) (Required) Yes No

CL3. Climate Impact Monitoring (Required) Yes No

Community Section

CM1. Net Positive Community Impacts (Required) Yes No

CM2. Offsite Community Impacts (Required) Yes No

CM3. Community Impact Monitoring (Required) Yes No

Biodiversity Section

B1. Net Positive Biodiversity Impacts (Required) Yes No

B2. Offsite Biodiversity Impacts (Required) Yes No

B3. Biodiversity Impact Monitoring (Required) Yes No

Gold Section GL1. Climate Change Adaptation Benefits (Optional) Yes No

GL2. Exceptional Community Benefits (Optional) Yes No

GL3. Exceptional Biodiversity Benefits (Optional) Yes No

CCBA Validation Level Attained:

APPROVED (all requirements met)

GOLD (all requirements and also at least one optional Gold Level criterion met

Page 67: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-1

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

I would like to comment on the proposed Project Design Document for Rukinga Sanctuary carbon

project, the Kasigau corridor Reduced Emissions from Deforestation and Degradation (REDD) project.

Since the arrival of Wildlife Works in the year 1998, the community has benefited a lot. As I am part of

the community, I have personally benefited through secondary education sponsorship programme,

which Wildlife Works had introduced in 2002. Without Wildlife Works, education could have been only a

dream to me.

Wildlife Works projects have brought lots of benefits to most of the community members. Some of the

benefits include; Employment in the EPZ factory, wildlife rangers and the green house tree planting. All

these have so far improved the community’s living standard by increasing their monthly incomes.

Another benefit is the improvement of learning institutions such as primary and secondary schools. In

the 1990s, children used to go learn in grass-thatched classrooms. These rooms forced the children to go

home once there were indications that the rains were coming because they were leaking. With Wildlife

Works, children are staying in classes without fear. Those students who work hard and perform well are

sponsored by well-wishers through Wildlife Works.

Therefore, the proposed REDD project will highly benefit more community members. Most people near

the project zone are poor and some of them depend on agriculture and cutting down of trees for

charcoal. These lead to deforestation and hence pose problems. If the REDD project starts, there will

automatically be more employment opportunities for many locals. All those people who were initially

involved in environmental degradation activities will then be involved in constructive activities and

hence maintenance of trees in the area. This project will also make the community to be more exposed

because most tourists will come to the sanctuary and visit the community and schools too. Most of the

community members are not used to western people therefore frequent visits by the tourists will

expose these people more and more. More sponsorship for children is also expected due to increased

number of sponsors from abroad.

James Ruwa

GAFFER HIV/AIDS PROJECT COORDINATOR.

September 24, 2009

I am really encouraging the introduction of Kasigau corridor REDD project, for sure a lot will be done.

I knew wildlife works ten years ago, when they were handing over the classrooms they helped to build in

Buguta, Kale and Marungu where the ceremony was held.

I used to work with forestry department by that time and wildlife works invited me to help the guest of

honour with the planting of the ceremonial trees. From that time I got very much involved with them

especially with the training of the communities how to establish tree nurseries.

To help the communities living around Mt. Kasigau to conserve the mountain, wildlife works conducted

vegetation survey to find how much damage is done and involved the locals by identifying the plants in

each plot.

Wildlife works helped sponsoring bright children so that they could get good education; get good job

and stop poaching and making charcoal.

Page 68: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-2

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

To continue protecting Kasigau corridor, wildlife works helped with the training of community scouts

who patrols around the village to educate the communities the importance of wildlife and to remove

the snares put around the community’s farms. If it wasn’t wildlife works, Rukinga ranch could have been

encroached by the people living adjacent to it and could also make the movement of elephants from

Tsavo east to west impossible, as this is their migratory corridor.

Long Live Wildlife Works

Keep on working with communities.

Kenneth Nyange

Project Manager – Camp Tsavo

October 9, 2009

I’ personal feel that the proposed project has really benefited the community around this place. There is

a big improvement in schools, which have been guided by Wildlife Works. Since it was started in the

year 2002, to mention a few Wildlife Works has helped by constructing new classrooms, renovating

classes, putting up water tanks and buying desks for pupils. All these have led to the improvement of the

academic standards of the concerned schools.

Apart from this Wildlife works has sponsored so many students to higher education. I believe in future

the living standards of the community around will be highly improved. If it were not Wildlife Works then

standards of living will remain poor for so many years. To add on this Wildlife woks has employed

people to the Epz factory and others have been employed as Rangers at Rukinga sanctuary. This has

improved the living standards of the people around. I am sure the proposed REDD project will help and

benefit Members of the community around even more. I conclude by saying since Wildlife Works was

introduced, the community has learnt that poaching of animals is not good for it reduces economy of

our country. The community have also discovered that they should conserve and plant more trees so

that they can get rains and water.

Yours at service

Peterson Msinga Mwatate

Head teacher- Kale primary school.

October 9, 2009

I’ Renson Dio, Taita ranching company limited Director cum Treasurer applaud this project to take off

immediately as at now the current environmental climate change is leading the world to disaster.

Being a resident of Kasigau location and border Marungu Location, I have personal benefited from

Wildlife Works and the locals too, like sponsorship programs of our pupils to secondary schools and

colleges not forgetting university levels, employment to our locals in Epz Maungu, construction of

classrooms. In Taita Ranch headquarters the ranch benefited from Wildlife Works through giving four

buffalos that were being kept as in a zoo by providing maize germ during this drought period. Taita

Ranching through Mr. Renson Dio has benefited from Wildlife Works by being given vehicles for patrols

by Mr. Rob Dodson in our Ranch, to mention but a few.

I propose the project to take off immediately.

Page 69: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-3

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

Thanks

Renson Dio

Director

Taita Ranching Co. Ltd.

October 8, 2009

Comment A

This comment concerns the following aspects of the project.

1. G3 –project design and goals- schools construction and bursary scheme

2. CM1.1 – Estimate impacts on communities. While the achievements of the project are acknowledged

and highly appreciated, there is room for improvement in order to justify the assertion that there are no

negative impacts. For example facilities being provided for primary schools around Kasigau need to be

extended to the very few secondary schools in the area. This will remove a feeling that students going

from primary school to secondary school are moving a step backward rather than forward.

Comment B

‘Climate section’ is lacking relevant data on the rates of evaporation and transpiration associated with

the eco-system in general and the area species of vegetations in particular.

Comment C

Annex D: Village profiles should be edited so as to enhance its credibility. There is further more in

sufficient supporting statistical information to highlight claims of achievements of the project.

Engineer C.M Mwakulomba

Kasigau Location

October 9, 2009

Auditor’s Note: The standard does not require that evaporation and transpiration associated with the

ecosystem or species of vegetation be given. It is the opinion of the validator that the village profiles

provided in the PDD are sufficient given the diversity of livelihoods and economies relative to other

CCBA projects.

In regards to the respect that I uphold for Wildlife Works, as person, since I saw it as an organization to

the time I came to meet it, I must say that if you don’t know who they are then you better find out

because its in involving yourself with them that you get to find the gold that you either have been

throwing or the destruction that you can prevent yourself from.

As a person that is part of Wildlife Works project since 2002, through an education sponsorship program

it’s quite visible that Wildlife works cares for the well being of the community and the environment as a

whole. I also have success stories that were initiated by wildlife works, throughout my sponsorship

program, where we were informed on the importance of conserving the environment, hence started a

project of planting trees to prevent the land from deforestation, and land erosions.

Page 70: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-4

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

It’s from Wildlife Works that people have learnt how conserve the environment, how to live with the

wildlife, importance of Eco-system, effects of poaching, methods of farming within the community,

hence making a relationship between animals and the people living along the rukinga sanctuary.

Economically, the communities that live around rukinga have had benefits through employment in the

sanctuary, wardens, rangers etc, bright children have had a chance of studying to the 0-level (secondary

education), also to the A-level( University) that can enable them secure job opportunities and be part of

those who bring a change to the community.

Socially, the communities have grown in the sense that they known the importance of a clean

environment, why they need to reduce deforestation, importance of trees, the nature of their

environment, how to cope well with it and now the gaffer project that gives awareness of HIV/AIDS, and

reducing the idleness of the youths through involving them in events like sports.

Wildlife works has been supportive, educative both in the social and the economic lifestyles and we

hope that it will continue to dwell to see the fruits of the trees that it has planted for the betterment of

the wildlife, the community, our lifestyle and our land as a whole.

I fully support the efforts of Wildlife Works and all its projects including the REDD project in making our

land; people and animals have the best place for living in peace and togetherness.

Regards,

Sylvester Izaka,

IT & Network support engineer. (CBS)

October 8, 2009

Ever since the year the year 2000 when I came to know what actually Wildlife Works was, this

organization has been of very great importance to many. Not only to individuals but also the community

at large. I strongly believe that with the introduction of the Kasigau corridor REDD project, there will be

even more benefits to the community.

Education could have been history to most people in this region. Through Wildlife Works classrooms

were built in most primary schools in this region. This ensured smooth running of school programs

without being affected by the weather changes since the formerly grass thatched classrooms were out

of use during rainy season. Wildlife Works ensured that education of the bright children does not end at

primary level but it is continued to high school. This was done through introduction of the sponsorship

program and really benefited may including me.

Wildlife Works has also educated the community so as to live peacefully with wild animals in order to

reduce human wildlife conflict. This has in return reduced poaching in the region since most people are

now well informed with the dangers of bush meat.

I strongly support the introduction of the Kasigau corridor REDD project because it will create

employment to most people in our community and the standard of living will change. Many children in

this region will be able to go to high school and also a lot more trees will be planted in the region which

will attract rain leading to improved agriculture.

Page 71: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-5

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

Rehema Mwavuo

Volunteer Teacher – Marungu Secondary School.

Marungu Location, Nyangala Division, Voi District

September 30, 2009

Since the inception of Wildlife Works 11 years ago, great strands have been achieved. The most

noticeable one being cited here: -

a) There has been full acceptance of Wildlife Works as part of our inheritance and so great measures

have been put in place to conserve and co-existed. This has been due to education provided by Wildlife

Works and other stakeholders.

b) The town of Maungu has grown, Wildlife Works has provided market for the local produce, it has

cleaned and provided cleaning facilities and inseminated the inhabitants the need to live dirty free

environment.

c) Wildlife Works – Maungu has offered employment to many locals i.e. security, drivers, mechanics,

clerks, rangers etc curbing the rural urban migration and uplifting the living standards of our people.

d) Wildlife Works – Maungu has initiated, supported renovated and constructed classrooms. They have

also contributed for other school related facilities in many neighboring schools, a measure ‘‘we” as

Members of the community appreciated.

e) The GAFFER, which started through Wildlife Works, has given alternatives to our idle youth. They

have been made occupied, shown the importance of sports, appreciating and accepting one another

and accommodating other persons weaknesses through the sports spirit, a gesture that has made rather

hostile communities to co-exist peacefully.

f) The GAFFER has also initiated the planting of trees in different schools and other public institutions

around Wildlife Works. The community has really benefited. We fully support the REDD project.

g) The education trust under umbrella KELIMU TRUST has helped our destitute children to access hire

school education so far some have even joined tertiary institutions still under KELIMU TRUST. Wildlife

Works - Maungu has an upper hand in this and therefore it’s hard to detach this benefit from them.

h) During hard times such as drought and other natural disasters Wildlife Works come in hand to aid the

affected people. This has been evident recently when the aged and the poor got relief food from Born

Free organization still associated with Wildlife Works – Maungu.

And a move towards enhancing Wildlife Works will definitely assist us positively, their priority areas are

always friendly and we are sure the carbon project, Kasigau corridor Reduced Emission from

Deforestation and Degradation (REDD) will be a great advantage to us. The project diversity will finally

explore to tap rather the idle recourses likely to sum up more profit and benefit to Wildlife Works then

to us the surrounding community. The proposed REDD project will add value to the eco-system under

the umbrella of Wildlife Works. Care and security of our Wildlife will be assured.

Page 72: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-6

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

Our area is trans-passed by a railway line, trans Africa highway, and pipeline station all heavy emitters of

carbon and carbon monoxide gasses. The carbon project (REDD) will absorb and reduce their entry into

the atmosphere hence curbing fully or reducing the rate of global warming, we the community at large

support the REDD project due to the above stated aspects.

Thank you

The resident – Maungu

Teacher and Instructor

V Wambua Masai

September 29, 2009

I as resident of Maungu, would like to welcome the Rukinga sanctuary REDD project. Wildlife Works

have done a lot to the community since they started operations in 1998. Children have been taken to

secondary school, I being among the beneficiaries of the program. All the bright kids from the poor

families were being sponsored for higher education, which was started from 2002.

Wildlife Works has also created employment to the community by employing the youth as Rangers,

Mass production machinist, and some at the green house project.

In 2002 Wildlife Works contributed about three hundred desks in Marasi primary school this is due to

the children who had no where to sit in class.

Wildlife Works is bordered by the poor community who, big percentage depend on the charcoal burning

and bush meat poaching for survival, therefore I will recommend for more projects in the area for more

job creation.

Last and not least I am praying to God if Wildlife Works have can stay for long time and also keep on

helping our people in Marungu community. Our living standard could not have been changed if Wildlife

Works was not there.

Yours sincerely

Antony Lundi

Voi constituency – Maungu office

October 3, 2009

I would like to comment on the above mentioned project for Rukinga sanctuary.

Environment

What I never thought of and has been done by the project on environment is: seedlings provision to the

local community, environment conservation within the area, which has led to a better and beautiful

environment, modern jikos were constructed for the community which uses few firewood and also

reduces heavy smoke to the atmosphere. On the sanitary has accompanied the community especially at

Maungu town on rubbish collection.

Page 73: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-7

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

Wild animals have been conserved in the sanctuary, which has improved tourist attraction in Kenya

Education

The project has already assisted the community by improved education in the area by doing the

following: construction of classrooms, provision of desks, books and educating the bright student from

the poor families from form one to form four.

Employment

The project has economically assisted the community by employing the Rangers who assist on

environment, wildlife conservation and many other things.

Epz factory – by formation of the Epz many especially the youth got jobs.

Relief food

The project has assisted the community by provision on the relief food to the needy people.

In my opinion is to pray so that the project can be expanded to be a bigger project – We really

appreciate the project for all what has been done for us.

CHIEF’S OFFICE

THE MANAGER

WILDLIFE WORKS

P.O. BOX 310 – VOI

October 5, 2009

SASIGAU CORRIDOR REDD PROJECT- PUBLIC COMMENTS.

VOTE OF THANKS:

In your endeavors to educate, reduce poverty, conserve and protect the environment both flora and

fauna I give you kudos! Congratulations.

Your support in both primary and secondary class rooms construction, and providing higher education

support to high performers who are under – privileged is un- surpassed.

COMMENTS: RUKINGA SACTUARY

RE: FORESTATION

Encourage more tree nurseries and provide free seedling in exchange for any indigenous tree planted,

germinate seeds both indigenous, citrus fruits and climbers and disperse them aerially, and manually

near fertile wetlands and swamps during rain season.

WILDLIFE CONSERVATION

The long distance covered by wild life both grazers and browser etc is in search of water. Construct

more water pans and several boreholes, which can be wind-powered within the sanctuary.

SECURITY SURVEILANCE AND PROTECTION

Provide Rangers with sets of binoculars, V.H.F radios sets and construct strategic watchtower in flat

grassy areas to monitor and report cattle movement, wildlife poachers, wood loggers, smoke etc.

CONSTRUCT ELECTRIC FENCES IN WILDLIFE – HUMAN CORRIDORS.

Page 74: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-8

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

The animal ingressions into human settlement areas are well known. While the highly mountains act as

a natural shield. Five key areas require attention, where cheap P.V.C poles and solar power electric

fencing can be erected

FOOD AID: FOR TREES PLANTED AND SURVIVING

The foodstuff occasionally provided by Wildlife Works Epz should be complemented by the tree planted

and surviving from the beneficiaries.

DISABLED PEOPLES

While Wildlife Works Epz has done so much to the community at large, it has not involved itself deeply

in the disabled societies, or individuals. Provide basic training or seminars to the disabled and assist

them with working tools example: shoes marker, carpenters, masons, electricians and brick marker etc.

ENEMIES OF THE SANCTUARY

Charcoal burners, tree cutter, poacher, honey hunters miners and prospective grass harvesters and

cattle grazers, to mention but a few.

Solution: Electric fence at the strategic entry points, community policing i.e. employ informers and

guards within the bordering community/ settlement.

Thanks you:

Briviant Shako – Technical Works

P.o. Box 25 Voi - Maungu

Email: [email protected]

TEL: 0726445458

October 9, 2009

Auditor’s Note: It is not feasible for the project proponents to build an electric fence or provide

surveillance to the degree suggested by this comment. The idea of installing fences was discussed

during the site visit; however, it was concluded that an electric fence is too expensive and would require

continual maintenance.

I would like to make my comments for the Project Design Document (PDD) for Kasigau corridor Reduced

Emission Deforestation and Degradation (REDD) project as follows:-

Mount Kasigau – The Project needs to cover the mountain area by planting more trees because this is

the only water source neighbouring the project zone. Like other water towers in the country, Mt.

Kasigau is one of the affected due to harvesting of sandalwood and its ecosystem degraded. There is

need to incorporate Mt. Kasigau by establishing tree nurseries in the villages around the mountain to

mitigate the adverse sandalwood destruction effects to strengthen the weakened ecosystem at the

water tower.

Mechanism should be set up to help the integrity of the project and help the local community from

exploitation forces within and without the project area.

We appreciate Wildlife Works because they have contributed to the social, economic and well-being of

the community living next to the project zone. In addition they have done improvements in schools

Page 75: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-9

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

infrastructures, offering education bursaries to bright needy children in the community, aiding dame

scouts in de-snaring and arresting the game poachers, establishment of tree nurseries have created

environment awareness to the community.

Wildlife works also cooperate very well with the local community leaders in terms of development, like

for example they participate in most of the local Baraza’s to create wildlife and environment

conservation awareness. They contribute in clean ups of the towns within the project zone. The

community leaders also once assisted in eviction when the squatters invaded and developed part of

Rukinga Wildlife Sanctuary (5000 Acres).

This project zone is neighbored by farmlands with no cash crops to sustain farmers; the severe drought

that has exaggerated the area has forced most of the locals to destruct trees fro charcoal

burning/logging and poaching for livelihood. I will request for drought resistant cash crops like

jathropper and jojoba to be introduced in the farms neighboring the project zone in order to alleviate

poverty.

Pascal Kizaka

Chief of Kasigau Location, Voi/Kenya

September 28, 2009

I as an assistant chief of Maungu community, I do appreciate a lot to what Wildlife Works have done to

my people. Therefore I will highly support Kasigau corridor REDD project which is being implemented by

Wildlife Works. Below is what has been achieved by Wildlife Works for the last ten years:-

In education, the community has benefited a lot due to the sponsorships offered through Wildlife

Works. More than 50 kids have been sponsored to secondary school education and even some to

university level. Some of these kids have finished their education and are now working within the

community. These being the fruits of education, most of the parents are working hard to see their

children go to school.

We’ve been working together with Wildlife Works in environment conservation especially in cleaning

the towns. They have been helping the community with tools and materials for the clean ups activities,

at the same time provide seedlings for environment cover. Wildlife Works has also introduced

smokeless jikos to the community for clean environment.

The community has benefited a lot especially during drought seasons, the company together with other

related companies help in donation of aid food to the poorest families within the area of the project

zone.

Wildlife Works has created employment opportunities to the community from their projects within the

company, among the project are: EPZ eco-factory, Rukinga wildlife sanctuary, Green house project and

Jojoba research project.

I would like to congratulate Wildlife Works for all they have done to uplift the standard of living in this

community and therefore welcome the introduction of REDD project as we are still in need especially

water, this is still a major problem in the community and I hope it will be solved with the4 introduction

of REDD project.

Page 76: FINAL CCBA PROJECT VALIDATION REPORT - Amazon S3 · allowed to comment on the draft report comments made by the project proponent were considered but not all were incorporated into

CCBA Project Validation Report Appendix B Page B-10

Stakeholder Comments – The Kasigau Corridor REDD Project

Scientific Certification Systems

December 22, 2009

Thank you

Driscilah M. Ngele

Assistant Chief’s Office

Maungu Sub-Location

P.O.Box 134 – 80300

VOI

October 5, 2009