Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
Certification for a Sustainable World ™
FINAL CCBA PROJECT VALIDATION REPORT
KASIGAU CORRIDOR REDD PROJECT
TAITA TAVETA, KENYA
WILDLIFE WORKS CARBON LLC
December 22, 2009
Validation Conducted by:
Scientific Certification Systems
Greenhouse Gas Verification Program
2200 Powell St. #725, Emeryville, CA 94608 USA
Tel. 510.236.9016 • (Fax) 510.236.8598 • www.scscertified.com
Table of Contents
1.0 Introduction ......................................................................................................................... 1
1.1. Contact Information ........................................................................................................ 1
1.2. Objective .......................................................................................................................... 2
1.3. Scope and Criteria ........................................................................................................... 2
1.4. Project Description .......................................................................................................... 2
1.5. Summary of Validation Conclusion ................................................................................. 3
2.0 Methodology ....................................................................................................................... 3
2.1. CCB Standards ................................................................... Error! Bookmark not defined.
2.2. Auditor Qualifications ...................................................................................................... 3
2.3. Audit Process ................................................................................................................... 4
3.0 Stakeholder Comments ....................................................................................................... 5
3.1. CCB Validation Findings ................................................................................................... 5
3.2. General Section ............................................................................................................... 6
3.2.1. G1 – Original Conditions in the Project Area ........................................................... 6
3.2.2. G2 – Baseline Projections ...................................................................................... 12
3.2.3. G3 – Project Design and Goals .............................................................................. 15
3.2.4. G4 – Management Capacity and Best Practices .................................................... 24
3.2.5. G5 – Legal Status and Property Rights .................................................................. 32
3.3. Climate Section .............................................................................................................. 36
3.3.1. CL1 – Net Positive Climate Impacts ....................................................................... 36
3.3.2. CL2 – Offsite Climate Impacts (‘Leakage’) ............................................................. 39
3.3.3. CL3 – Climate Impact Monitoring .......................................................................... 42
3.4. Community Section ....................................................................................................... 43
3.4.1. CM1 – Net Positive Community Impacts ............................................................... 43
3.4.2. CM2 – Offsite Stakeholder Impacts ....................................................................... 45
3.4.3. CM3 – Community Impact Monitoring .................................................................. 48
3.5. Biodiversity Section ....................................................................................................... 50
3.5.1. B1 – Net Positive Biodiversity Impacts .................................................................. 50
3.5.2. B2 – Offsite Biodiversity Impacts ........................................................................... 53
3.5.3. B3 – Biodiversity Impact Monitoring ..................................................................... 55
3.6. Gold Level Section ......................................................................................................... 57
3.6.1. GL1 – Climate Change Adaptation Benefits .......................................................... 57
3.6.2. GL2 – Exceptional Community Benefits ................................................................ 59
3.6.3. GL3 – Exceptional Biodiversity Benefits ................................................................ 61
4.0 CCB Validation Conclusion ................................................................................................. 62
Appendix A CCBA Compliance Checklist
Appendix B Stakeholder Comments
Table of Findings
NCR Number 1 of 19 for October 20, 2009 ..................................................................................... 7
NCR Number 19 of 19 for October 20, 2009 ................................................................................... 8
NIR Number 1 of 5 for October 20, 2009 ...................................................................................... 10
NCR Number 2 of 19 for October 20, 2009 ................................................................................... 11
OFI Number 1 of 4 for October 20, 2009 ...................................................................................... 14
NIR Number 2 of 5 for October 20, 2009 ...................................................................................... 16
NCR Number 3 of 19 for October 20, 2009 ................................................................................... 18
OFI Number 2 of 4 for October 20, 2009 ...................................................................................... 18
NCR Number 4 of 19 for October 20, 2009 ................................................................................... 20
NCR Number 1 of 1 for November 12, 2009 ................................................................................. 20
NCR Number 5 of 19 for October 20, 2009 ................................................................................... 23
NCR Number 6 of 19 for October 20, 2009 ................................................................................... 23
NCR Number 7 of 19 for October 20, 2009 ................................................................................... 25
NCR Number 8 of 19 for October 20, 2009 ................................................................................... 26
NCR Number 9 of 19 for October 20, 2009 ................................................................................... 27
OFI Number 3 of 4 for October 20, 2009 ...................................................................................... 28
OFI Number 1 of 1 for November 12, 2009 ................................................................................... 29
NCR Number 10 of 19 for October 20, 2009 ................................................................................. 31
NCR Number 11 of 19 for October 20, 2009 ................................................................................. 31
NIR Number 3 of 5 for October 20, 2009 ...................................................................................... 33
NIR Number 4 of 5 for October 20, 2009 ...................................................................................... 34
NCR Number 12 of 19 for October 20, 2009 ................................................................................. 38
NCR Number 13 of 19 for October 20, 2009 ................................................................................. 40
NCR Number 14 of 19 for October 20, 2009 ................................................................................. 43
NCR Number 18 of 19 for October 20, 2009 ................................................................................. 45
NCR Number 15 of 19 for October 20, 2009 ................................................................................. 46
NCR Number 16 of 19 for October 20, 2009 ................................................................................. 49
NCR Number 17 of 19 for October 20, 2009 ................................................................................. 52
OFI Number 4 of 4 for October 20, 2009 ...................................................................................... 55
NIR Number 5 of 5 for October 20, 2009 ...................................................................................... 58
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
1.0 Introduction
This report presents the findings of an audit conducted by Sc
validate the claim made by Wildlife Works Carbon LLC
to the Climate, Community and Biodiversity Project Design Standards (
Certification Systems (SCS) has been accredited by the Climate, Community & Biodiversity Alliance
(CCBA) to perform such validation audits.
1.1. Contact Information
Project Developer contact information
Mike Korchinsky
Wildlife Works Carbon LLC
425 Market Street, 26th Floor
San Francisco, CA 94105
Tel. 415.332.8081
mike [at] wildlifeworks.com
Scientific Certification Systems contact
Todd Frank, Program Manager, GHG Verification Services
Scientific Certification Systems
2200 Powell Street, No. 725
Emeryville, CA 94608 USA
Tel. 510.236.9016
tfrank [at] scscertified.com
Auditor contact information:
Kyle Holland, Verification Forester, GHG
Scientific Certification Systems
2200 Powell Street, No. 725
Emeryville, CA 94608 USA
Tel. 510.236.9015
kholland [at] scscertified.com
Alex Obara, Kenyan Forestry
alexobara [at] hotmail.com
Client contact information:
Mike Korchinsky
Wildlife Works Carbon LLC
425 Market Street, 26th Floor
San Francisco, CA 94105
Tel. 415.332.8081
mike [at] wildlifeworks.com
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
1
This report presents the findings of an audit conducted by Scientific Certification Systems
Wildlife Works Carbon LLC that the Kasigau Corridor REDD
to the Climate, Community and Biodiversity Project Design Standards (Second Edition).
has been accredited by the Climate, Community & Biodiversity Alliance
audits.
information:
Floor
mike [at] wildlifeworks.com
contact information:
Todd Frank, Program Manager, GHG Verification Services
ific Certification Systems
2200 Powell Street, No. 725
Forester, GHG Verification Services
Scientific Certification Systems
2200 Powell Street, No. 725
ified.com
Forestry Specialist
[at] hotmail.com
Floor
mike [at] wildlifeworks.com
ientific Certification Systems (SCS), to
Kasigau Corridor REDD Project conforms
Edition). Scientific
has been accredited by the Climate, Community & Biodiversity Alliance
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
1.2. Objective
The validation objective is an independent assessment by
all criteria defined by the Climate Biodiversity and Community Alliance (CCBA). Validation
concludes with an opinion of whether the project activi
whether the project should be submitted for registration with CCBA. The ultimate decision on the
registration of a proposed project rests with CCBA.
1.3. Scope and Criteria
The project was assessed against the CCB Standards Second Edition to determine which of the fourteen
required and three optional CCB Standards criteria the project satisfies. An “Approved” project is one
which satisfies all fourteen of the required CCB Standards criteria
The scope of services described in this
presented at the time of inception of project
Information Requests (NIRs) or Non
these findings by the Project Proponent. As necessary based on the
Auditor issued additional findings.
1.4. Project Description
The Kasigau Corridor REDD Project (“the p
Kenya, approximately two hours northwest of Mombasa, Kenya. The project
and Tsavo West National Parks and functions as a critical wildlife corridor between the two parks. T
are several communities located near the project area in the project zone. The project area is primarily
low density forestland, shrubland and grassland savannah.
This land is a private leasehold estate
Ltd. The majority shareholder of Rukinga Ranching Co
There are 46 shareholders of Rukinga Ranching Co
international was established by a princip
Carbon LLC. Wildlife Works Inc. is an export processor of consumer goods to retail markets in Europe
and the United States. Wildlife Works Inc. supports the conservation of wilderness habitats, t
creation of jobs and the construction of schools.
easement from Rukinga Ranching Company
easement effectively transferred all carbon and biodiversity rights
Wildlife Works Inc. Wildlife Works Inc. and Wildlife Works Carbon L
project activities and collectively these e
of project activities in this report.
Major project activities in the project area include the protection of the wildlife corridor, wildlife habitat
and carbon stocks. Major project
1 See http://www.wildlifeworks.com/mission/mission.html
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
2
objective is an independent assessment by SCS of the proposed project activities
defined by the Climate Biodiversity and Community Alliance (CCBA). Validation
on of whether the project activities are compliant with the CCB standards and
he project should be submitted for registration with CCBA. The ultimate decision on the
registration of a proposed project rests with CCBA.
assessed against the CCB Standards Second Edition to determine which of the fourteen
required and three optional CCB Standards criteria the project satisfies. An “Approved” project is one
of the required CCB Standards criteria.
described in this report encompasses an analysis of data and calculations as
presented at the time of inception of project validation. The SCS Lead Auditor issued
) or Non-Conformity Reports (NCRs), as needed, and analyze
these findings by the Project Proponent. As necessary based on the adequacy of responses, the Lead
gau Corridor REDD Project (“the project”) is located in Coast Province, Taita Taveta District
Kenya, approximately two hours northwest of Mombasa, Kenya. The project area is between Tsa
and Tsavo West National Parks and functions as a critical wildlife corridor between the two parks. T
are several communities located near the project area in the project zone. The project area is primarily
, shrubland and grassland savannah.
estate given by the Government of Kenya to Rukinga Ranching
majority shareholder of Rukinga Ranching Company is BenBo International, an offshore trust.
Rukinga Ranching Company, including BenBo International.
a principal investor of both Wildlife Works Inc. and Wildlif
Wildlife Works Inc. is an export processor of consumer goods to retail markets in Europe
and the United States. Wildlife Works Inc. supports the conservation of wilderness habitats, t
creation of jobs and the construction of schools.1 Wildlife Works Inc. was granted a conservation
inga Ranching Company in 2009 after the project start date of January 1, 2006
all carbon and biodiversity rights from Rukinga Ranching Company to
. Wildlife Works Inc. and Wildlife Works Carbon LLC have initiated or will
and collectively these entities are referred to as “the project proponent
roject area include the protection of the wildlife corridor, wildlife habitat
and carbon stocks. Major project activities in the project zone relate to the surrounding communities
http://www.wildlifeworks.com/mission/mission.html
of the proposed project activities against
defined by the Climate Biodiversity and Community Alliance (CCBA). Validation by SCS
compliant with the CCB standards and
he project should be submitted for registration with CCBA. The ultimate decision on the
assessed against the CCB Standards Second Edition to determine which of the fourteen
required and three optional CCB Standards criteria the project satisfies. An “Approved” project is one
analysis of data and calculations as
one or more New
), as needed, and analyzed responses to
of responses, the Lead
Coast Province, Taita Taveta District,
area is between Tsavo East
and Tsavo West National Parks and functions as a critical wildlife corridor between the two parks. There
are several communities located near the project area in the project zone. The project area is primarily
Ranching Company
nternational, an offshore trust.
, including BenBo International. BenBo
al investor of both Wildlife Works Inc. and Wildlife Works
Wildlife Works Inc. is an export processor of consumer goods to retail markets in Europe
and the United States. Wildlife Works Inc. supports the conservation of wilderness habitats, the
was granted a conservation
January 1, 2006. This
from Rukinga Ranching Company to
have initiated or will initiate the
roponent” in the context
roject area include the protection of the wildlife corridor, wildlife habitat
e surrounding communities
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
and include greenhouse-based tree production, agricultural outreach, employment and the construction
of schools. The project lifetime and crediting period are 20 years.
1.5. Summary of Validation
Following completion of SCS’s duly
Corridor REDD Project conforms
Standards (Second Edition) at the Gold
the audit and were subsequently closed; in total, there were
Information Requests (NIRs) and 5 Opportunities for Improvement (OFIs)
2.0 Methodology
The audit commenced on September 25
Design Document (PDD). The site
Wildlife Works management, employees
members. Field tours were conducted of the project area and project zone. Following the site visit
upon further review of the collected evidence
issued. Audit findings were issued as NCRs, NIRs and OFIs. The Pro
of time to respond to the issued NCRs and NIRs. Upon the close of this period or the receipt of
satisfactory responses, the draft report was issued on December 21
allowed to comment on the draft report
comments made by the project proponent were considered but not all were incorporated into the final
report.
2.1. CCB Standards
The Project was validated against
Standards (Second Edition) (“the Standard”
of 4 categories: 1) General (5 criteria
Biodiversity (3 criteria). In addition,
least one of three criteria in the
required criteria and at least one optional
2.2. Auditor Qualifications
Lead Auditor: Kyle Holland, SCS Verification Forester
Mr. Holland is a Certified Forester
and remote sensing. Prior to joinin
Supervisor. Kyle has also worked with the
State of Wisconsin as a specialist in
currently completing his Ph.D. in biometrics and statistics at the Uni
holds a M.S. in biometrics and remote sensing from Berkeley, and
Minnesota and the University of Idaho in forestry and forest engineering, respectively.
professional memberships with the Society of American Foresters, the American Society for
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
3
based tree production, agricultural outreach, employment and the construction
of schools. The project lifetime and crediting period are 20 years.
Validation Conclusion
S’s duly-accredited validation process, it was concluded that T
to the CCBA Climate, Community and Biodiversity
Gold Level (see Appendix A). Findings were made durin
the audit and were subsequently closed; in total, there were 20 Non-Conformity Reports (NCRs)
Opportunities for Improvement (OFIs).
The audit commenced on September 25th with an opening meeting and a desk review
visit occurred the week of October 12th and included meetings with
Wildlife Works management, employees, Rukinga Ranching Company shareholders
ours were conducted of the project area and project zone. Following the site visit
upon further review of the collected evidence, public comments and PDD, several audit findings were
e issued as NCRs, NIRs and OFIs. The Project Proponent was allowed a period
of time to respond to the issued NCRs and NIRs. Upon the close of this period or the receipt of
report was issued on December 21st. The project proponent was
draft report prior to the submission of the final report to CCBA.
comments made by the project proponent were considered but not all were incorporated into the final
was validated against the CCB Climate, Community and Biodiversity Project Design
Edition) (“the Standard”). The Standard requires conformance to 1
criteria), 2) Climate (3 criteria), 3) Community (3
). In addition, applicants achieve a higher level of validation by conforming to at
Gold Level section. Projects with Gold Level status
optional Gold Level criterion of the Standard.
Auditor Qualifications
Lead Auditor: Kyle Holland, SCS Verification Forester
Holland is a Certified Forester (#3770) and biometrician specializing in forest inventory,
. Prior to joining SCS, Kyle worked with the Potlatch Corporation as a Resource
Supervisor. Kyle has also worked with the Chesapeake Bay Program, the State of Maryland and the
specialist in riparian forestry and forest management auditing.
in biometrics and statistics at the University of California, Berkeley. Kyle
holds a M.S. in biometrics and remote sensing from Berkeley, and degrees from the University of
ta and the University of Idaho in forestry and forest engineering, respectively.
professional memberships with the Society of American Foresters, the American Society for
based tree production, agricultural outreach, employment and the construction
ded that The Kasigau
to the CCBA Climate, Community and Biodiversity Project Design
. Findings were made during the course of
onformity Reports (NCRs), 5 New
review of the Project
and included meetings with
Company shareholders and community
ours were conducted of the project area and project zone. Following the site visit and
public comments and PDD, several audit findings were
ject Proponent was allowed a period
of time to respond to the issued NCRs and NIRs. Upon the close of this period or the receipt of
. The project proponent was
submission of the final report to CCBA. All
comments made by the project proponent were considered but not all were incorporated into the final
Climate, Community and Biodiversity Project Design
conformance to 14 criteria in each
Community (3 criteria), and 4)
by conforming to at
Projects with Gold Level status meet the core
(#3770) and biometrician specializing in forest inventory, modeling
worked with the Potlatch Corporation as a Resource
Chesapeake Bay Program, the State of Maryland and the
riparian forestry and forest management auditing. Mr. Holland is
versity of California, Berkeley. Kyle
degrees from the University of
ta and the University of Idaho in forestry and forest engineering, respectively. He also holds
professional memberships with the Society of American Foresters, the American Society for
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Photogrammetry and Remote Sensing, the Institute of Mathematical Stati
Environmetrics Society. Mr. Holland
under FSC, CCX, CAR, CCB and VCS.
projects under VCS.
Auditor: Alex Oginga Obara, Kenyan Specialist and SCS Contractor
Mr. Obara is a native of Kenya specializing in forestry and wildlife management.
in Forest and Wildlife Management from the Moi University, Kenya
Biology from the Durell Institute of Conservation and Ecology at the University of Kent
United Kingdom. Alex also holds certificates in Biodiversity Measurement and Monitoring,
Environmental Leadership and Communication Skills from the
has broad experience in forest research, forest biometrics, landscape restoration, resource management
and ecological monitoring obtained from his work with
UNDP, UNIDO, WWF, the World Bank/GEF and Nippon Koei Co., Ltd.
2.3. Audit Process
The audit process included the following
• Opening meeting, introduction and project orientation (via conference call) on September 25
• Desk review of PDD and supplemental documentation including maps, data and models;
• Site visit from October 13th
o Project overview and orientation
o Interviews with Wildlife Works management;
o Interviews with Wildlife Works employees;
o Interviews with Rukinga
o A community meeting;
o Field tours of local communities;
o Interviews with community members;
o Tours of local schools;
o Interviews with local school teachers and administrators;
o Field tours of the project area;
o Tours of facilities and agricultural plantings;
o Closing meeting and presentation of preliminary findings;
• Review of stakeholder comments;
• Review of collected evidence and supporting documentation;
• Issuance of findings on October 2
• Project proponent responses to findings;
• Preparation of draft report;
• Technical review of draft report;
• Comment on draft report by project proponent; and
• Submission of final report to CCBA.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
4
Photogrammetry and Remote Sensing, the Institute of Mathematical Statistics and the International
Mr. Holland has conducted numerous verification and validation activities
under FSC, CCX, CAR, CCB and VCS. Mr. Holland is also an approved AFOLU expert for IFM and REDD
, Kenyan Specialist and SCS Contractor
a native of Kenya specializing in forestry and wildlife management. He holds a B
in Forest and Wildlife Management from the Moi University, Kenya, and a M.Sc. degree in Conserva
Biology from the Durell Institute of Conservation and Ecology at the University of Kent
Alex also holds certificates in Biodiversity Measurement and Monitoring,
Environmental Leadership and Communication Skills from the Smithsonian Institute, Virginia.
has broad experience in forest research, forest biometrics, landscape restoration, resource management
and ecological monitoring obtained from his work with the Masai Mara National Reserve in Kenya,
WWF, the World Bank/GEF and Nippon Koei Co., Ltd.
The audit process included the following timeline of events and activities:
Opening meeting, introduction and project orientation (via conference call) on September 25
and supplemental documentation including maps, data and models;
– October 17th;
Project overview and orientation
Interviews with Wildlife Works management;
Interviews with Wildlife Works employees;
Rukinga Ranching Company shareholders;
A community meeting;
Field tours of local communities;
Interviews with community members;
Tours of local schools;
Interviews with local school teachers and administrators;
Field tours of the project area;
and agricultural plantings;
Closing meeting and presentation of preliminary findings;
Review of stakeholder comments;
Review of collected evidence and supporting documentation;
of findings on October 2nd and November 11th;
nses to findings;
Preparation of draft report;
Technical review of draft report;
Comment on draft report by project proponent; and
Submission of final report to CCBA.
stics and the International
has conducted numerous verification and validation activities
is also an approved AFOLU expert for IFM and REDD
holds a B.Sc .degree
degree in Conservation
Biology from the Durell Institute of Conservation and Ecology at the University of Kent in Canterbury,
Alex also holds certificates in Biodiversity Measurement and Monitoring,
Smithsonian Institute, Virginia. Mr. Obara
has broad experience in forest research, forest biometrics, landscape restoration, resource management
Masai Mara National Reserve in Kenya,
Opening meeting, introduction and project orientation (via conference call) on September 25th;
and supplemental documentation including maps, data and models;
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
3.0 Stakeholder Comments
The Project Design Document (PDD) was
comment period extended through
Appendix B).
Written comments were received from the
• James Ruwa, GAFFER HIV/AIDS Project Coordinator
• Kenneth Nyange, Project Manager
• Peterson Msinga Mwatate, Head Teacher
• Renson Dio, Director - Taita Ranching Co. Ltd.
• Engineer C.M Mwakulomba
• Sylvester Izaka, IT & Network support engineer
• Rehema Mwavuo, Volunteer Teacher
• V Wambua Masai, Teacher and Instructor
• Antony Lundi, Voi constituency
• Chief DUNCAN, Marungu Location as addressed to the Manager Wildlife Work
• Briviant Shako – Technical Works
• Pascal Kizaka, Chief of Kasigau Location, Voi/Kenya
• Driscilah M. Ngele, Assistant Chief’s Office
All comments have been addressed by the auditor in this report. General themes included
• Overwhelming support for the project’s
• Support for the protection of wild animals;
• Support for the greenhouse nursery program;
• Support for the school bursary program;
• Support for the construction of
• Recognition of Wildlife Work’s engagement with the
• Acknowledgement of the potential risks to the project area under the without
namely deforestation, conversion to agriculture and charcoal production;
• Appreciation for the intrinsic value of the proje
• Appreciation for employment opportunities offered by Wildlife Works.
3.1. CCB Validation Findings
The evidence and findings presented in this report address
each criterion, the Standard specifies
and issued to the project proponent as
(NIRs) and Opportunities for Improvement (OFIs)
stipulates the deficiency or lack of evidence
indicators. NCRs indicate broad non
project validation while NIRs and OFIs are less material. In the case of a NIR, the finding is to obtain
additional evidence to support the conformance of the project to an indicator. The project proponent
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
5
Stakeholder Comments
The Project Design Document (PDD) was posted on the CCBA website on September 9
comment period extended through October 9th. Comments were received from thirteen
Written comments were received from the following stakeholders:
HIV/AIDS Project Coordinator
Kenneth Nyange, Project Manager – Camp Tsavo
Peterson Msinga Mwatate, Head Teacher - Kale primary school
Taita Ranching Co. Ltd.
Engineer C.M Mwakulomba
Sylvester Izaka, IT & Network support engineer
ma Mwavuo, Volunteer Teacher – Marungu Secondary School
V Wambua Masai, Teacher and Instructor
Antony Lundi, Voi constituency – Maungu office
Chief DUNCAN, Marungu Location as addressed to the Manager Wildlife Work
Technical Works
izaka, Chief of Kasigau Location, Voi/Kenya
Driscilah M. Ngele, Assistant Chief’s Office
omments have been addressed by the auditor in this report. General themes included
helming support for the project’s climate, community and biodiversity benefits;
Support for the protection of wild animals;
Support for the greenhouse nursery program;
Support for the school bursary program;
Support for the construction of new schools and additions;
of Wildlife Work’s engagement with the community and community organizations;
Acknowledgement of the potential risks to the project area under the without
namely deforestation, conversion to agriculture and charcoal production;
Appreciation for the intrinsic value of the project area; and
Appreciation for employment opportunities offered by Wildlife Works.
Findings
The evidence and findings presented in this report address the criteria of the Standard by indicator
Standard specifies indicators for which findings are issued; findings are documented
and issued to the project proponent as Non-Conformity Reports (NCRs), New Information Requests
tunities for Improvement (OFIs). In the case of non-conformance, the
or lack of evidence posed by the project in the context of one or more
NCRs indicate broad non-conformance at the criterion level that must be satisf
project validation while NIRs and OFIs are less material. In the case of a NIR, the finding is to obtain
additional evidence to support the conformance of the project to an indicator. The project proponent
September 9th and the public
thirteen parties (see
omments have been addressed by the auditor in this report. General themes included:
benefits;
community and community organizations;
Acknowledgement of the potential risks to the project area under the without-project scenario,
of the Standard by indicator. For
for which findings are issued; findings are documented
nformation Requests
conformance, the NCR clearly
in the context of one or more
conformance at the criterion level that must be satisfied prior to
project validation while NIRs and OFIs are less material. In the case of a NIR, the finding is to obtain
additional evidence to support the conformance of the project to an indicator. The project proponent
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
must respond to all NIRs before the
observation that may help the project proponent to improve their project. OFIs are optional however
may evolve into NCRs over time. Given the overlapping nature of the Standard’s indicators,
finding may address multiple indicators and criteria. In this report, findings are presented in order of
criterion and cross referenced subsequent to presentation.
Initially and upon conclusion of the audit, the project proponent
and how the project addresses the Standard in
Phase I – Rukinga Sanctuary, ultimately dated December 2009. This document is available to the public
on the CCBA website (http://www.climate
Design Document (PDD).
3.2. General Section
The General Section of the CCB Standards addresses
projections, project design and goals, management capacity
property rights.
3.2.1. G1 – Original Conditions
The original conditions at the project area
commences must be described. This description, along with
determine the likely impacts of the project.
Indicator G1.1. The location of the project and basic physical parameters (e.g., soil,
Findings: The location of the project area is described in the PDD. The basic physical parameters of the
project area and project zone are described in the PDD.
are found in Section G1.1 of the revised PDD.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G1.2. The types and condition of vegetation
Findings: Both the types and conditions of vegetation in the project area are described in the revised
PDD. Initially, the PDD lacked descriptions of the “OUT” and B
made during the site visit indicated that these types were notic
presented in the original PDD (see
trees and shrubs in the “OUT” type was less than the other types presented in the original PDD.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
6
must respond to all NIRs before the close of the audit. In the case of an OFI, the finding is an
observation that may help the project proponent to improve their project. OFIs are optional however
may evolve into NCRs over time. Given the overlapping nature of the Standard’s indicators,
finding may address multiple indicators and criteria. In this report, findings are presented in order of
criterion and cross referenced subsequent to presentation.
Initially and upon conclusion of the audit, the project proponent collated information about the project
project addresses the Standard in a document titled The Kasigau Corridor REDD Project
, ultimately dated December 2009. This document is available to the public
http://www.climate-standards.org). This document is referred to
The General Section of the CCB Standards addresses original conditions in the project are
projections, project design and goals, management capacity and best practices, and legal status and
Original Conditions in the Project Area
at the project area and the surrounding project zone before the project
commences must be described. This description, along with baseline projections (see G2), will help
determine the likely impacts of the project.
of the project and basic physical parameters (e.g., soil, geology, climate).
The location of the project area is described in the PDD. The basic physical parameters of the
project area and project zone are described in the PDD. Descriptions of the climate, soils and geology
of the revised PDD.
Yes No N/A
None
None
None
types and condition of vegetation within the project area.
Both the types and conditions of vegetation in the project area are described in the revised
PDD. Initially, the PDD lacked descriptions of the “OUT” and Boma vegetation types. Observations
made during the site visit indicated that these types were noticeably different than the vegetation types
(see NCR Number 1 of 19 for October 20, 2009). The stocking
trees and shrubs in the “OUT” type was less than the other types presented in the original PDD.
close of the audit. In the case of an OFI, the finding is an
observation that may help the project proponent to improve their project. OFIs are optional however
may evolve into NCRs over time. Given the overlapping nature of the Standard’s indicators, a single
finding may address multiple indicators and criteria. In this report, findings are presented in order of
ation about the project
The Kasigau Corridor REDD Project
, ultimately dated December 2009. This document is available to the public
This document is referred to as the Project
original conditions in the project are baseline
and legal status and
before the project
projections (see G2), will help to
geology, climate).
The location of the project area is described in the PDD. The basic physical parameters of the
Descriptions of the climate, soils and geology
Both the types and conditions of vegetation in the project area are described in the revised
ma vegetation types. Observations
eably different than the vegetation types
. The stocking level of
trees and shrubs in the “OUT” type was less than the other types presented in the original PDD.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Likewise, many Boma or cattle corrals were observed during the
the corrals were noticeably different than the
complete description of the vegetation types and conditions is in Sect
Conformance:
Non-Conformity Reports:
NCR Number 1 of 19 for October 20, 2009
Finding: The project proponents have omitted descriptions of some vegetation types and conditions
within the project area. The description must include these types and conditions of vegetation within
the project area.
Proponent Response on October 24
of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map
to Annex 1, which clearly indicates the boundary of the Project Z
Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image
and a KMZ file covering this area. We include the PDD text below.
We believe that this is a complete and adequate res
be closed.
Validator Response: The revisions made to the PDD are adequate.
New Information Requests:
Opportunities for Improvement:
Indicator G1.3. The boundaries of the project area and
Findings: Descriptions of the boundaries of the project area and project zone are given in Section G1.3
of the revised PDD. The project zone includes the land that falls between Tsavo East National Park and
Tsavo West National Park south and east of Voi town, and includes the communities of Maungu,
Itinyi, Buguta, Marungu, Kale, Mwakasinyi, Sasenyi and the privately held group ranches of
Kasigau, Taita, Amaka, Maungu, Mgeno, Kambanga, Wangala and Buchuma. A map of the project zone
is provided in the revised PDD (see
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
7
ma or cattle corrals were observed during the site visit. The vegetation conditions in
noticeably different than the vegetation types presented in the original PDD.
complete description of the vegetation types and conditions is in Section G1.2 of the revised PDD.
Yes No N/A
1 of 19 for October 20, 2009
The project proponents have omitted descriptions of some vegetation types and conditions
within the project area. The description must include these types and conditions of vegetation within
October 24, 2009: We have updated the description in section G1.3, and G3.3
of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map
to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD
Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image
and a KMZ file covering this area. We include the PDD text below.
We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19
The revisions made to the PDD are adequate.
None
None
The boundaries of the project area and the project zone.
Descriptions of the boundaries of the project area and project zone are given in Section G1.3
of the revised PDD. The project zone includes the land that falls between Tsavo East National Park and
uth and east of Voi town, and includes the communities of Maungu,
Itinyi, Buguta, Marungu, Kale, Mwakasinyi, Sasenyi and the privately held group ranches of
Kasigau, Taita, Amaka, Maungu, Mgeno, Kambanga, Wangala and Buchuma. A map of the project zone
provided in the revised PDD (see NCR Number 19 of 19 for October 20, 2009).
Yes No N/A
vegetation conditions in
vegetation types presented in the original PDD. A
ion G1.2 of the revised PDD.
The project proponents have omitted descriptions of some vegetation types and conditions
within the project area. The description must include these types and conditions of vegetation within
We have updated the description in section G1.3, and G3.3
of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map
one for the Kasigau Corridor REDD
Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image
ponse to this NCR #19 and we ask that the NCR #19
Descriptions of the boundaries of the project area and project zone are given in Section G1.3
of the revised PDD. The project zone includes the land that falls between Tsavo East National Park and
uth and east of Voi town, and includes the communities of Maungu,
Itinyi, Buguta, Marungu, Kale, Mwakasinyi, Sasenyi and the privately held group ranches of
Kasigau, Taita, Amaka, Maungu, Mgeno, Kambanga, Wangala and Buchuma. A map of the project zone
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 19 of 19 for October 20, 2009
Finding: The boundaries of the project zon
the project zone should be clarified with an explicit map for Phase I.
Proponent Response on October 24
of the PDD to refer to a new map for the Project Zone added in Annex 1. We have added the new map
to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD
Project, with Phases I and II clearly indicated. We have also emailed the Validator a
and a KMZ file covering this area. We include the PDD text below.
We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19
be closed.
Validator Response: The new map provided in the revised PD
New Information Requests:
Opportunities for Improvement:
Indicator G1.4. Current carbon stocks
vegetation type and methods of carbon calculation (such as biomass plots, formulae, default values)
from the Intergovernmental Panel on Climate Change’s
for Agriculture, Forestry, and Other Land Use or a more robust and detailed methodology.
Findings: The project uses a VCS methodology (
double-approval process at the time of this report)
guidelines. Stratification and a sample of plots are used to estimate the current carbon stocks within
the project area. This method for estimating carbon stocks is the greatest level of detail specified by
IPCC as Tier 3.
Diameter measurements, stem counts and allometric equations are used to estimate the aboveground
biomass. Belowground biomass is estimated using ratio
from the IPCC guidance document. The allometric e
parameterized using a purposive sample within common species groups. The sample appeared to be
representative of the entire project area. The allometric equations for aboveground biomass were not
cross-validated for over fitting or selected using any statistical criteria. Given the limited number of
allometric equations available in the literature for this region of the continent, the constructed
equations seem adequate.
Soil organic carbon was estimated using a si
This method for estimating soil carbon appears to be adequate. The project proponent assumes that
the soil organic pool will remain constant throughout the life of the project, which is a reason
assumption.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
8
NCR Number 19 of 19 for October 20, 2009
The boundaries of the project zone are provided as a description; however the boundaries of
the project zone should be clarified with an explicit map for Phase I.
October 24, 2009: We have updated the description in section G1.3, and G3.3
w map for the Project Zone added in Annex 1. We have added the new map
to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD
Project, with Phases I and II clearly indicated. We have also emailed the Validator a separate map image
and a KMZ file covering this area. We include the PDD text below.
We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19
The new map provided in the revised PDD is adequate.
None
None
Current carbon stocks within the project area(s), using stratification by land
vegetation type and methods of carbon calculation (such as biomass plots, formulae, default values)
Intergovernmental Panel on Climate Change’s 2006 Guidelines for National GHG Inventories
nd Other Land Use or a more robust and detailed methodology.
The project uses a VCS methodology (currently not approved by VCS and currently
process at the time of this report) and the VCS methodology conforms to IPCC
. Stratification and a sample of plots are used to estimate the current carbon stocks within
the project area. This method for estimating carbon stocks is the greatest level of detail specified by
stem counts and allometric equations are used to estimate the aboveground
biomass. Belowground biomass is estimated using ratios of above-to-belowground relative biomass
from the IPCC guidance document. The allometric equations for above ground biomass were
parameterized using a purposive sample within common species groups. The sample appeared to be
representative of the entire project area. The allometric equations for aboveground biomass were not
over fitting or selected using any statistical criteria. Given the limited number of
allometric equations available in the literature for this region of the continent, the constructed
Soil organic carbon was estimated using a simple random sample of soil cores analyzed by a third party.
This method for estimating soil carbon appears to be adequate. The project proponent assumes that
the soil organic pool will remain constant throughout the life of the project, which is a reason
however the boundaries of
We have updated the description in section G1.3, and G3.3
w map for the Project Zone added in Annex 1. We have added the new map
to Annex 1, which clearly indicates the boundary of the Project Zone for the Kasigau Corridor REDD
separate map image
We believe that this is a complete and adequate response to this NCR #19 and we ask that the NCR #19
stratification by land-use or
vegetation type and methods of carbon calculation (such as biomass plots, formulae, default values)
2006 Guidelines for National GHG Inventories
nd Other Land Use or a more robust and detailed methodology.
not approved by VCS and currently under the
and the VCS methodology conforms to IPCC
. Stratification and a sample of plots are used to estimate the current carbon stocks within
the project area. This method for estimating carbon stocks is the greatest level of detail specified by
stem counts and allometric equations are used to estimate the aboveground
belowground relative biomass
quations for above ground biomass were
parameterized using a purposive sample within common species groups. The sample appeared to be
representative of the entire project area. The allometric equations for aboveground biomass were not
over fitting or selected using any statistical criteria. Given the limited number of
allometric equations available in the literature for this region of the continent, the constructed
mple random sample of soil cores analyzed by a third party.
This method for estimating soil carbon appears to be adequate. The project proponent assumes that
the soil organic pool will remain constant throughout the life of the project, which is a reasonable
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Conformance:
Non-Conformity Reports:
Opportunities for Improvement:
New Information Requests:
Indicator G1.5. A description of communities located in
economic and cultural information
communities (wealth, gender, ethnicity, etc.), identifies specific groups such as Indigenous Peoples and
describes any community characteristics.
Findings: The revised PDD contains a desc
specifically in Section G1.5. There are
Marungu, Kale, Mwakasinyi and Sasenyi.
these communities are small service business
employer in the project zone other than the school district. Given the limited diversity in socioeconom
conditions and culture, the provided
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G1.6. A description of current land use and
community property in the project zone, identifying any ongoing or unresolved conflicts or disputes and
indentifying and describing any disputes over land tenure that were resolved during the last ten years
(see also G5).
Findings: A description of the current land use, customary and legal rights is provided in the revised
PDD in Section 1.6. The description includes
recent history of the legal property rights of Rukinga Ranching Company. The description also includes
information about a solved dispute between emigrant Duruma which
the ranch now called the Sasenyi Valley Land Cooperative
outstanding conflicts are relatively minor and involve transient cattle herders
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
9
Yes No N/A
None
None
None
A description of communities located in the project zone, including basic socio
information that describes the social, economic and cultural diversity within
communities (wealth, gender, ethnicity, etc.), identifies specific groups such as Indigenous Peoples and
describes any community characteristics.
The revised PDD contains a description of all the communities located in the
There are several communities in the project zone: Maungu,
Marungu, Kale, Mwakasinyi and Sasenyi. These communities are rural Taitan and the econom
service businesses, small shops and bars. Wildlife Works is the only formal
one other than the school district. Given the limited diversity in socioeconom
culture, the provided description is adequate.
Yes No N/A
None
None
None
A description of current land use and customary and legal property rights including
community property in the project zone, identifying any ongoing or unresolved conflicts or disputes and
indentifying and describing any disputes over land tenure that were resolved during the last ten years
A description of the current land use, customary and legal rights is provided in the revised
PDD in Section 1.6. The description includes a history of the national system for land tenure and a
recent history of the legal property rights of Rukinga Ranching Company. The description also includes
information about a solved dispute between emigrant Duruma which resulted in the sale of a portion of
Sasenyi Valley Land Cooperative, prior to the project start date. Any
outstanding conflicts are relatively minor and involve transient cattle herders, mostly from Somalia.
Yes No N/A
None
, including basic socio-
that describes the social, economic and cultural diversity within
communities (wealth, gender, ethnicity, etc.), identifies specific groups such as Indigenous Peoples and
ription of all the communities located in the project zone,
project zone: Maungu, Itinyi, Buguta,
and the economies of
. Wildlife Works is the only formal
one other than the school district. Given the limited diversity in socioeconomic
customary and legal property rights including
community property in the project zone, identifying any ongoing or unresolved conflicts or disputes and
indentifying and describing any disputes over land tenure that were resolved during the last ten years
A description of the current land use, customary and legal rights is provided in the revised
national system for land tenure and a
recent history of the legal property rights of Rukinga Ranching Company. The description also includes
in the sale of a portion of
, prior to the project start date. Any
mostly from Somalia.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
New Information Requests:
Opportunities for Improvement:
Indicator G1.7. A description of current biodiversity within the project zone (diversity of species and
ecosystems) and threats to that biodiversity, using appropriate methodologies, substantiated where
possible with appropriate reference material.
Findings: The biodiversity diversity description provided in Section G1.7
comprehensive and adequate. The biodiversity description includes information about the ecosystem,
habitat and wildlife found within the project zone. Initially, the PDD lacked references to literature
containing descriptions of the methodologies by
for October 20, 2009).
Conformance:
Non-Conformity Reports:
New Information Requests:
NIR Number 1 of 5 for October 20, 2009
Finding: The project proponent has provided a description of biodiversity assumed to be partially based
on a literature review. A literature review is an appropriate methodology, however the project
proponent must provide appropriate reference material to substant
Proponent Response on October 30
text below, and have sent the Validator the references
information provided to the Validator is a more than adequate response to your finding and
Standard and we ask that you consider this finding NIR#1 closed.
Validator Response: The provided references indicate the use of a
therefore adequate.
Opportunities for Improvement:
Indicator G1.8. An evaluation of whether the project zone includes any of the following High
Conservation Values (HCVs) and a description of the qualifying attribut
8.1. Globally, regionally or nationally significant concentrations of biodiversity values;
a. protected areas
b. threatened species
c. endemic species
d. areas that support significant concentrations of a species during any time in their
(e.g. migrations, feeding grounds, breeding areas).
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
10
None
None
A description of current biodiversity within the project zone (diversity of species and
ecosystems) and threats to that biodiversity, using appropriate methodologies, substantiated where
appropriate reference material.
The biodiversity diversity description provided in Section G1.7 of the revised PDD is
comprehensive and adequate. The biodiversity description includes information about the ecosystem,
within the project zone. Initially, the PDD lacked references to literature
containing descriptions of the methodologies by which biodiversity was assessed (see NIR Number 1 of 5
Yes No N/A
None
NIR Number 1 of 5 for October 20, 2009
The project proponent has provided a description of biodiversity assumed to be partially based
on a literature review. A literature review is an appropriate methodology, however the project
proponent must provide appropriate reference material to substantiate this methodology, if possible.
October 30, 2009: We have revised sections G1.7 of the PDD to include the
text below, and have sent the Validator the references described in the text. We believe that this new
information provided to the Validator is a more than adequate response to your finding and
Standard and we ask that you consider this finding NIR#1 closed.
The provided references indicate the use of appropriate methodologies and are
None
An evaluation of whether the project zone includes any of the following High
Conservation Values (HCVs) and a description of the qualifying attributes:
8.1. Globally, regionally or nationally significant concentrations of biodiversity values;
areas that support significant concentrations of a species during any time in their
s, feeding grounds, breeding areas).
A description of current biodiversity within the project zone (diversity of species and
ecosystems) and threats to that biodiversity, using appropriate methodologies, substantiated where
of the revised PDD is
comprehensive and adequate. The biodiversity description includes information about the ecosystem,
within the project zone. Initially, the PDD lacked references to literature
NIR Number 1 of 5
The project proponent has provided a description of biodiversity assumed to be partially based
on a literature review. A literature review is an appropriate methodology, however the project
iate this methodology, if possible.
We have revised sections G1.7 of the PDD to include the
We believe that this new
information provided to the Validator is a more than adequate response to your finding and meets the
ppropriate methodologies and are
An evaluation of whether the project zone includes any of the following High
areas that support significant concentrations of a species during any time in their lifecycle
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
8.2. Globally, regionally or nationally significant large landscape
most if not all naturally occurring species exist in natural patterns of distribution
8.3. Threatened or rare ecosystems;
8.4. Areas that provide critical ecosystem services (e.g., hydrological services, erosion control,
control);
8.5. Areas that are fundamental for meeting the basic needs of local communities (e.g., for
food, fuel, fodder, medicines or building materials without readily available
8.6. Areas that are critical for the traditional cultural identity of communities (e.g., areas of
ecological, economic or religious significance identifie
Findings: The revised PDD contains several descriptions of HCVs including threatened and endangered
species; the sanctuary as a corridor for significant concentrations of species; the area as a unique
dryland ecosystem; and Mount Kasigau which is used by the local population is a unique place on the
landscape. Initally, the PDD lacked information about Mount Kasigau
amended (see NCR Number 2 of 19 for October 20, 2009
local communities was discovered during the course of the site visit.
Conformance:
Non-Conformity Reports:
NCR Number 2 of 19 for October 20, 2009
Finding: The project zone includes at least one area that provides critical ecosystem services such as
hydrological and climate services that are not included in the description of the project zone in the PDD.
There are areas in the project zone that function as threatened ecosystems and are fundamental to
meeting the basic needs of local communities. The project proponent
description. Also, the project proponent must demonstrate that the project design includes specific
measures to ensure the maintenance or enhancement of these additional HCVs and that these areas will
not be negatively affected by the project. These additional H
community and biodiversity impact monitoring.
Proponent Response on October 30
B3.2 of the PDD to include the text
text.
We believe that this new information provided to the Validator is a more than adequate response to
your finding and meets the Standard and we ask that you consider this finding NCR#2
Validator Response: The supplemented PDD is adequate.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
11
8.2. Globally, regionally or nationally significant large landscape-level areas where viable
most if not all naturally occurring species exist in natural patterns of distribution and abundance;
Threatened or rare ecosystems;16
8.4. Areas that provide critical ecosystem services (e.g., hydrological services, erosion control,
8.5. Areas that are fundamental for meeting the basic needs of local communities (e.g., for
fuel, fodder, medicines or building materials without readily available alternatives); and
8.6. Areas that are critical for the traditional cultural identity of communities (e.g., areas of
ecological, economic or religious significance identified in collaboration with the communities).
The revised PDD contains several descriptions of HCVs including threatened and endangered
species; the sanctuary as a corridor for significant concentrations of species; the area as a unique
ecosystem; and Mount Kasigau which is used by the local population is a unique place on the
Initally, the PDD lacked information about Mount Kasigau however it
NCR Number 2 of 19 for October 20, 2009). The importance of Mount Kasigau to the
local communities was discovered during the course of the site visit.
Yes No N/A
NCR Number 2 of 19 for October 20, 2009
The project zone includes at least one area that provides critical ecosystem services such as
imate services that are not included in the description of the project zone in the PDD.
There are areas in the project zone that function as threatened ecosystems and are fundamental to
meeting the basic needs of local communities. The project proponent must include all HCV areas in the
description. Also, the project proponent must demonstrate that the project design includes specific
measures to ensure the maintenance or enhancement of these additional HCVs and that these areas will
fected by the project. These additional HCV areas must be assessed as part of
community and biodiversity impact monitoring.
October 30, 2009: We have revised sections G1.8, G3.6, CM1.2, CM3.2 and
B3.2 of the PDD to include the text below, and have sent the Validator the references described in the
We believe that this new information provided to the Validator is a more than adequate response to
your finding and meets the Standard and we ask that you consider this finding NCR#2 closed.
The supplemented PDD is adequate.
level areas where viable populations of
and abundance;
8.4. Areas that provide critical ecosystem services (e.g., hydrological services, erosion control, fire
8.5. Areas that are fundamental for meeting the basic needs of local communities (e.g., for essential
alternatives); and
8.6. Areas that are critical for the traditional cultural identity of communities (e.g., areas of cultural,
communities).
The revised PDD contains several descriptions of HCVs including threatened and endangered
species; the sanctuary as a corridor for significant concentrations of species; the area as a unique
ecosystem; and Mount Kasigau which is used by the local population is a unique place on the
it was subsequently
ance of Mount Kasigau to the
The project zone includes at least one area that provides critical ecosystem services such as
imate services that are not included in the description of the project zone in the PDD.
There are areas in the project zone that function as threatened ecosystems and are fundamental to
must include all HCV areas in the
description. Also, the project proponent must demonstrate that the project design includes specific
measures to ensure the maintenance or enhancement of these additional HCVs and that these areas will
areas must be assessed as part of
We have revised sections G1.8, G3.6, CM1.2, CM3.2 and
below, and have sent the Validator the references described in the
We believe that this new information provided to the Validator is a more than adequate response to
closed.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
New Information Requests:
Opportunities for Improvement:
3.2.2. G2 – Baseline Projections
A baseline projection is a description of expected conditions in the project zone in the
project activities. The project impacts will be measured against this ‘without
Indicators The project proponents must develop a defensible and well
scenario that must:
Indicator G2.1. Describe the most likely land
2006 GL for AFOLU or a more robust and detailed methodology,
landuse scenarios and the associated drivers of GHG emiss
selected is most likely.
Findings: The PDD provides a clear description of the identified land
project. The land-use scenario in the absence of the project is slash and bur
supported by condition of nearby, unprotected areas which have been cleared of forestland. Based on
interviews with community members conducted during the site visit, the selected land
very plausible. Also based on interviews conducted during the site visit, it is apparent that slash and
burn agriculture would proceed rapidly without the project.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G2.2. Document that project benefits would not have occurred in the absence of the project,
explaining how existing laws or regulations would likely affect land use and justifying
being claimed by the project are truly ‘additional’ and would be unlikely to occur without the project.
Findings: During the site visit, the benefits of the project were confirmed by interviews with local
community members. The PDD clearly documents
of the project. During the site visit, interviews with local autho
and regulations would not affect the likely land
enforced to prevent the conversation of forestland to agriculture. The term agriculture is used loosely in
the PDD and this report, and it implies both traditional agriculture and pastoralism.
Conformance:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
12
None
None
Baseline Projections
A baseline projection is a description of expected conditions in the project zone in the
project activities. The project impacts will be measured against this ‘without-project’ reference scenario.
The project proponents must develop a defensible and well-documented ‘without-
Describe the most likely land-use scenario in the absence of the project following IPCC
2006 GL for AFOLU or a more robust and detailed methodology, describing the range of potential
landuse scenarios and the associated drivers of GHG emissions and justifying why the land
The PDD provides a clear description of the identified land-use scenario in the absence of the
use scenario in the absence of the project is slash and burn agriculture which is clearly
supported by condition of nearby, unprotected areas which have been cleared of forestland. Based on
interviews with community members conducted during the site visit, the selected land
ased on interviews conducted during the site visit, it is apparent that slash and
burn agriculture would proceed rapidly without the project.
Yes No N/A
None
None
None
Document that project benefits would not have occurred in the absence of the project,
explaining how existing laws or regulations would likely affect land use and justifying
being claimed by the project are truly ‘additional’ and would be unlikely to occur without the project.
During the site visit, the benefits of the project were confirmed by interviews with local
community members. The PDD clearly documents the project benefits would not occur
. During the site visit, interviews with local authorities confirmed that the existing laws
and regulations would not affect the likely land-use without the project as there are no laws which are
enforced to prevent the conversation of forestland to agriculture. The term agriculture is used loosely in
PDD and this report, and it implies both traditional agriculture and pastoralism.
Yes No N/A
A baseline projection is a description of expected conditions in the project zone in the absence of
project’ reference scenario.
-project’ reference
use scenario in the absence of the project following IPCC
describing the range of potential
ions and justifying why the land-use scenario
use scenario in the absence of the
n agriculture which is clearly
supported by condition of nearby, unprotected areas which have been cleared of forestland. Based on
interviews with community members conducted during the site visit, the selected land-use scenario is
ased on interviews conducted during the site visit, it is apparent that slash and
Document that project benefits would not have occurred in the absence of the project,
explaining how existing laws or regulations would likely affect land use and justifying that the benefits
being claimed by the project are truly ‘additional’ and would be unlikely to occur without the project.
During the site visit, the benefits of the project were confirmed by interviews with local
occur in the absence
rities confirmed that the existing laws
use without the project as there are no laws which are
enforced to prevent the conversation of forestland to agriculture. The term agriculture is used loosely in
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G2.3. Calculate the estimated carbon stock changes
reference scenario described above. This requires estimation of carbon stocks for each of the land
classes of concern and a definition of the carbon pools included, among the classes defined in the IPCC
2006 GL for AFOLU.19 The timeframe for this analysis can be either the project lifetime (see
project GHG accounting period, whichever is more appropriate.
emissions of non-CO2 GHG emissions such as CH
gases must be included if they are likely to account for more than 5% (in terms of CO
project’s overall GHG impact over each monitoring period.
Projects whose activities are designed to avoid GHG emissions
deforestation and forest degradation (REDD), avoiding conversion of non
improved forest management projects) must include an analysis of the relevant drivers and rates of
deforestation and/or degradation and a description and justification of the approaches,
and data used to perform this analysis. Regional
stage as long as there is a commitment to evaluate locally
project-specific spatial analysis of deforestation and/or degradation using an appropriately robust and
detailed carbon accounting methodology before the start of the project.
Findings: The estimated carbon stock changes
are presented in Section G2.3 using a
in 1995 and 1999. The rate is assumed to
to be linear in time. The latter of these assumptions is probably false (see
October 20, 2009), however the overall estimated deforestation rate is probably conservative based on
evidence from the site visit. Interviews with loc
area would likely be deforested in a very short period of time under the ‘without project’ scenario. An
analysis of the relevant drivers of deforestation is also presented in Section G2.3 of the PDD.
and despite the shortcomings of the deforestation model, the
the ‘without project’ scenario are reaso
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
13
None
None
None
Calculate the estimated carbon stock changes associated with the ‘without project’
reference scenario described above. This requires estimation of carbon stocks for each of the land
classes of concern and a definition of the carbon pools included, among the classes defined in the IPCC
The timeframe for this analysis can be either the project lifetime (see
project GHG accounting period, whichever is more appropriate. Estimate the net change in the
GHG emissions such as CH4 and N2O in the ‘without project’ scenario. Non
gases must be included if they are likely to account for more than 5% (in terms of CO2-
project’s overall GHG impact over each monitoring period.
Projects whose activities are designed to avoid GHG emissions (such as those reducing emissions from
deforestation and forest degradation (REDD), avoiding conversion of non-forest land, or certain
improved forest management projects) must include an analysis of the relevant drivers and rates of
degradation and a description and justification of the approaches,
and data used to perform this analysis. Regional-level estimates can be used at the project’s planning
stage as long as there is a commitment to evaluate locally-specific carbon stocks and to develop a
specific spatial analysis of deforestation and/or degradation using an appropriately robust and
detailed carbon accounting methodology before the start of the project.
The estimated carbon stock changes associated with the ‘without project’ reference scenario
are presented in Section G2.3 using an estimated rate measured from historical Landsat imagery taken
in 1995 and 1999. The rate is assumed to be linear in population size and population growth is assu
to be linear in time. The latter of these assumptions is probably false (see OFI Number 1 of 4 for
), however the overall estimated deforestation rate is probably conservative based on
evidence from the site visit. Interviews with local community members indicated that the entire project
area would likely be deforested in a very short period of time under the ‘without project’ scenario. An
analysis of the relevant drivers of deforestation is also presented in Section G2.3 of the PDD.
despite the shortcomings of the deforestation model, the estimated carbon stock changes under
the ‘without project’ scenario are reasonable and conservative.
Yes No N/A
None
None
associated with the ‘without project’
reference scenario described above. This requires estimation of carbon stocks for each of the land-use
classes of concern and a definition of the carbon pools included, among the classes defined in the IPCC
The timeframe for this analysis can be either the project lifetime (see G3) or the
Estimate the net change in the
t project’ scenario. Non-CO2
-equivalent) of the
(such as those reducing emissions from
forest land, or certain
improved forest management projects) must include an analysis of the relevant drivers and rates of
degradation and a description and justification of the approaches, assumptions
level estimates can be used at the project’s planning
carbon stocks and to develop a
specific spatial analysis of deforestation and/or degradation using an appropriately robust and
sociated with the ‘without project’ reference scenario
n estimated rate measured from historical Landsat imagery taken
linear in population size and population growth is assumed
OFI Number 1 of 4 for
), however the overall estimated deforestation rate is probably conservative based on
al community members indicated that the entire project
area would likely be deforested in a very short period of time under the ‘without project’ scenario. An
analysis of the relevant drivers of deforestation is also presented in Section G2.3 of the PDD. Overall
estimated carbon stock changes under
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
OFI Number 1 of 4 for October 20, 2009
Finding: Whether valid or not, the model is conservative based on the evidence
However, the model for deforestation could be improved by examining the deforestation rates
elsewhere, in similar areas, and by
considering economic drivers.
Proponent Response on October 24
possible to identify the population growth model for the Project Zone in the 10 years immediately
preceding Wildlife Works arrival in anything other than a linear model. There is simply no evide
support another model. There are no National or sub
and we believe that if there were, our Project Zone would be demonstrated to have as high or higher a
deforestation rate as anywhere in Kenya over t
Dryland Forests being cleared for Slash and Burn Agriculture in Kenya, and most of those remaining are
in the Leakage Belt of this Project and will be addressed during Phase II of this project.
Validator Response: Population size over time is usually estimated using an exponential model.
Indicator G2.4. Describe how the ‘without project’ reference scenario would affect communities in the
project zone, including the impact of likely changes in water,
services.
Findings: Based on the PDD and the site visit, there would be obvious non
employment, subsistence agriculture and education under the without project scenario. Changes in
water, soil and other locally important ecosystem services would greatly impact communities in the
project zone as described in Section G2.4 of the PDD.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G2.5. Describe how the ‘without project’ reference scenario would affect biodiversity in the
project zone (e.g., habitat availability, landscape connectivity and threatened species
Findings: Given the habitat conditions present outside the pro
reflective of the without project scenario, there are obvious affects on biodiversity in the absence of the
project. These effects are directly re
between the two national parks and are described in Section G2.5 of the PDD.
Conformance:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
14
of 4 for October 20, 2009
Whether valid or not, the model is conservative based on the evidence from
However, the model for deforestation could be improved by examining the deforestation rates
elsewhere, in similar areas, and by examining the assumptions of linear population growth and
October 24, 2009: Kenya conducts a census every 10 years. As a result it is not
possible to identify the population growth model for the Project Zone in the 10 years immediately
preceding Wildlife Works arrival in anything other than a linear model. There is simply no evide
support another model. There are no National or sub-national deforestation rates published for Kenya
and we believe that if there were, our Project Zone would be demonstrated to have as high or higher a
deforestation rate as anywhere in Kenya over the ten years prior to our arrival. There are few similar
Dryland Forests being cleared for Slash and Burn Agriculture in Kenya, and most of those remaining are
in the Leakage Belt of this Project and will be addressed during Phase II of this project.
Population size over time is usually estimated using an exponential model.
Describe how the ‘without project’ reference scenario would affect communities in the
project zone, including the impact of likely changes in water, soil and other locally important ecosystem
Based on the PDD and the site visit, there would be obvious non-
employment, subsistence agriculture and education under the without project scenario. Changes in
and other locally important ecosystem services would greatly impact communities in the
project zone as described in Section G2.4 of the PDD.
Yes No N/A
None
None
None
Describe how the ‘without project’ reference scenario would affect biodiversity in the
project zone (e.g., habitat availability, landscape connectivity and threatened species).
Given the habitat conditions present outside the project area and the project zone which are
reflective of the without project scenario, there are obvious affects on biodiversity in the absence of the
project. These effects are directly related to the project area as a critical habitat and a wildlife corridor
between the two national parks and are described in Section G2.5 of the PDD.
Yes No N/A
from the site visit.
However, the model for deforestation could be improved by examining the deforestation rates
examining the assumptions of linear population growth and
Kenya conducts a census every 10 years. As a result it is not
possible to identify the population growth model for the Project Zone in the 10 years immediately
preceding Wildlife Works arrival in anything other than a linear model. There is simply no evidence to
national deforestation rates published for Kenya
and we believe that if there were, our Project Zone would be demonstrated to have as high or higher a
he ten years prior to our arrival. There are few similar
Dryland Forests being cleared for Slash and Burn Agriculture in Kenya, and most of those remaining are
Population size over time is usually estimated using an exponential model.
Describe how the ‘without project’ reference scenario would affect communities in the
soil and other locally important ecosystem
-improvements in
employment, subsistence agriculture and education under the without project scenario. Changes in
and other locally important ecosystem services would greatly impact communities in the
Describe how the ‘without project’ reference scenario would affect biodiversity in the
).
ject area and the project zone which are
reflective of the without project scenario, there are obvious affects on biodiversity in the absence of the
lated to the project area as a critical habitat and a wildlife corridor
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.2.3. G3 – Project Design and Goals
The project must be described in sufficient detail so that a third
Projects must be designed to minimize risks to the expected
benefits and to maintain those benefits beyond the life of the project. Effective local participation in
project design and implementation is key to optimizing multiple benefits, equitably and sustainably.
Projects that operate in a transparent manner build confidence with stakeholders and outside parties
and enable them to contribute more effectively to the project.
Indicators
The project proponents must:
Indicator G3.1. Provide a summary of the project’s major climate,
objectives.
Findings: A summary of the major climate, community and biodiversity benefits are listed in Section
G3.1 of the PDD. These objectives broadly include the protection of the project area, long
sustainability, investment and outreach.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G3.2. Describe each project activity with expected climate, community and biod
impacts and its relevance to achieving the project’s objectives.
Findings: Section G3.2 is described in the revised PDD. Initially upon completion of the site visit, several
project activities were identified but missing from the original PDD (
20, 2009). These activities clearly contributed to the net positive impact of the project and were
therefore material to the validation.
amended to include all relevant project activities. The project proponent also provided an
implementation schedule for project
objectives (see Indicator G3.5).
Conformance:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
15
None
None
None
Project Design and Goals
The project must be described in sufficient detail so that a third-party can adequately evaluate it.
Projects must be designed to minimize risks to the expected climate, community and biodiversity
and to maintain those benefits beyond the life of the project. Effective local participation in
design and implementation is key to optimizing multiple benefits, equitably and sustainably.
operate in a transparent manner build confidence with stakeholders and outside parties
contribute more effectively to the project.
Provide a summary of the project’s major climate, community and biodiversity
A summary of the major climate, community and biodiversity benefits are listed in Section
G3.1 of the PDD. These objectives broadly include the protection of the project area, long
investment and outreach.
Yes No N/A
None
None
None
. Describe each project activity with expected climate, community and biod
relevance to achieving the project’s objectives.
Section G3.2 is described in the revised PDD. Initially upon completion of the site visit, several
were identified but missing from the original PDD (see NIR Number 2 of 5 for October
es clearly contributed to the net positive impact of the project and were
therefore material to the validation. Subsequent to the initial findings of the audit, the revised PDD was
amended to include all relevant project activities. The project proponent also provided an
implementation schedule for project activities to demonstrate their feasibility to achieving t
Yes No N/A
party can adequately evaluate it.
climate, community and biodiversity
and to maintain those benefits beyond the life of the project. Effective local participation in
design and implementation is key to optimizing multiple benefits, equitably and sustainably.
operate in a transparent manner build confidence with stakeholders and outside parties
community and biodiversity
A summary of the major climate, community and biodiversity benefits are listed in Section
G3.1 of the PDD. These objectives broadly include the protection of the project area, long-term
. Describe each project activity with expected climate, community and biodiversity
Section G3.2 is described in the revised PDD. Initially upon completion of the site visit, several
NIR Number 2 of 5 for October
es clearly contributed to the net positive impact of the project and were
Subsequent to the initial findings of the audit, the revised PDD was
amended to include all relevant project activities. The project proponent also provided an
to demonstrate their feasibility to achieving the project’s
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Non-Conformity Reports:
New Information Requests:
NIR Number 2 of 5 for October 20, 2009
Finding: The PDD describes some project activities, however during the site visit, several project
activities were identified that were not included in the PDD. These project activities provide evidence to
support the net positive impact of the project. The project proponent must provide a complete list of
project activities. Also, a general implemen
sufficient detail for third-party evaluation.
Proponent Response on October 30
Implementation Schedule and have sent that
Activities, their start and end dates, and capital
which are then picked up in the detailed
We have also revised the text of Sections G3.2 and G3.4 to reflect the additional detail about the
activities that the Validator is referring to in this NIR.
Validator Response: The supplied list is inclusive of all relevant project activities and the su
implementation schedule shows milestone by which the project can be verified.
Opportunities for Improvement:
Indicator G3.3. Provide a map identifying the project location and boundaries of the project area(s),
where the project activities will occur, of the project zone and of additional surrounding locations that
are predicted to be impacted by project activities (e.g. through leakage).
Findings: The revised PDD contains maps of the project area and the project zone. The original PDD
was missing a map of the project zone which was subsequently added (see
October 20, 2009). The maps in the revised PDD also show the surrounding communities which are
predicted to be impacted by the project
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
16
None
NIR Number 2 of 5 for October 20, 2009
The PDD describes some project activities, however during the site visit, several project
activities were identified that were not included in the PDD. These project activities provide evidence to
support the net positive impact of the project. The project proponent must provide a complete list of
project activities. Also, a general implementation schedule for all project activities must be included in
party evaluation.
October 30, 2009: We have developed a detailed Project Activity List and
Implementation Schedule and have sent that to the Validator. This schedule shows specific Project
Activities, their start and end dates, and capital and operating budget amounts for their implementation
which are then picked up in the detailed Project Cash Flow provided to the Validator under NCR#6.
e also revised the text of Sections G3.2 and G3.4 to reflect the additional detail about the
activities that the Validator is referring to in this NIR.
The supplied list is inclusive of all relevant project activities and the su
implementation schedule shows milestone by which the project can be verified.
None
Provide a map identifying the project location and boundaries of the project area(s),
will occur, of the project zone and of additional surrounding locations that
predicted to be impacted by project activities (e.g. through leakage).
The revised PDD contains maps of the project area and the project zone. The original PDD
s missing a map of the project zone which was subsequently added (see NCR Number 19 of 19 for
). The maps in the revised PDD also show the surrounding communities which are
predicted to be impacted by the project activities.
Yes No N/A
See NCR Number 19 of 19 for October 20, 2009
None
None
The PDD describes some project activities, however during the site visit, several project
activities were identified that were not included in the PDD. These project activities provide evidence to
support the net positive impact of the project. The project proponent must provide a complete list of
tation schedule for all project activities must be included in
We have developed a detailed Project Activity List and
alidator. This schedule shows specific Project
and operating budget amounts for their implementation
Project Cash Flow provided to the Validator under NCR#6.
e also revised the text of Sections G3.2 and G3.4 to reflect the additional detail about the project
The supplied list is inclusive of all relevant project activities and the supplied
Provide a map identifying the project location and boundaries of the project area(s),
will occur, of the project zone and of additional surrounding locations that
The revised PDD contains maps of the project area and the project zone. The original PDD
NCR Number 19 of 19 for
). The maps in the revised PDD also show the surrounding communities which are
NCR Number 19 of 19 for October 20, 2009
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Indicator G3.4. Define the project lifetime and
differences between them. Define an implementation schedule, indicating key dates and milestones in
the project’s development.
Findings: The project lifetime and the GHG accounting period are defined in Section G3.4 of the PDD.
The project lifetime and GHG accounting period are the same. Initially, key dates for the
implementation of project activities were undefined but were subsequently
(see NIR Number 2 of 5 for October 20, 2009
verify project activities during the project lifetime.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G3.5. Identify likely natural and human
biodiversity benefits during the project lifetime and outline measures adopted to
Findings: A list of major risks to expected climate, community and biodiversity benefits and outlined
measures are presented in Section G3.5 of the revised PDD. Initially, several risks were identified during
community meetings but were omitted from presented list (see
2009). The list was augmented in response to findings and the augmented list adequately includes all
identified risks and outlines measure adopted to mitigate identified risks.
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
17
Define the project lifetime and GHG accounting period and explain and justify any
between them. Define an implementation schedule, indicating key dates and milestones in
The project lifetime and the GHG accounting period are defined in Section G3.4 of the PDD.
The project lifetime and GHG accounting period are the same. Initially, key dates for the
implementation of project activities were undefined but were subsequently presented during the audit
NIR Number 2 of 5 for October 20, 2009). The supplied implementation schedule is im
es during the project lifetime.
Yes No N/A
None
See NIR Number 2 of 5 for October 20, 2009
None
Identify likely natural and human-induced risks to the expected climate, community and
biodiversity benefits during the project lifetime and outline measures adopted to mitigate these
A list of major risks to expected climate, community and biodiversity benefits and outlined
measures are presented in Section G3.5 of the revised PDD. Initially, several risks were identified during
were omitted from presented list (see NCR Number 3 of 19 for October 20,
). The list was augmented in response to findings and the augmented list adequately includes all
identified risks and outlines measure adopted to mitigate identified risks.
Yes No N/A
GHG accounting period and explain and justify any
between them. Define an implementation schedule, indicating key dates and milestones in
The project lifetime and the GHG accounting period are defined in Section G3.4 of the PDD.
The project lifetime and GHG accounting period are the same. Initially, key dates for the
presented during the audit
). The supplied implementation schedule is important to
induced risks to the expected climate, community and
mitigate these risks.
A list of major risks to expected climate, community and biodiversity benefits and outlined
measures are presented in Section G3.5 of the revised PDD. Initially, several risks were identified during
NCR Number 3 of 19 for October 20,
). The list was augmented in response to findings and the augmented list adequately includes all
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 3 of 19 for October 20, 2009
Finding: The PDD describes some major risks,
exist. Based on community meetings and interviews, other potential risks are drought on wildlife,
drought on fruit tree plantings and invasion of people into the project area because of desirable grazing
areas. These are likely risks that must be addressed in sufficient detail for third party evaluation.
Proponent Response on October 30
text below, to provide additional risks and mitigation
provided to the Validator together with the additions made to Section GL1.2 in response to finding
NCR#18 and previously provided is a more than adequate response to your finding and meets the
Standard and we ask that you consider this finding NCR#3 closed.
Validator Response: The revised PDD now includes all identified risks and likewise presents mitigation
strategies.
New Information Requests:
Opportunities for Improvement:
OFI Number 2 of 4 for October 20, 2009
Finding: The PDD describes the potential risk of fire and some mitigation
project proponent may also consider constructing effective firebreaks as an additional mitigation
activity, especially given the evidence of recent fire in the project area, observed during the site visit .
Proponent Response on October 24
against the worst fires, as evidenced by the fact that in
enter into the Project Area from the North boundary, a distance including the road reserve of some two
hundred meters. This is because in high fire risk periods, smoldering elephant dung becomes airborne
and can travel on the wind some significant distance to relight dry grass on the other side of the
firebreaks.
Validator Response: NA
Indicator G3.6. Demonstrate that the project design includes specific measures to ensure the
maintenance or enhancement of the high conservation value attributes identified in
the precautionary principle.
Findings: The revised PDD demonstrates that the project design includes specific measures to ensure
the maintenance and enhancement of HCV
for missing HCV values under Indicator G1.8, Section G3.6 of the revised PDD contains references to
Mount Kasigau (see NCR Number 2 of 19 for October 20, 2009
affect the maintenance of HCV in the project zone.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
18
NCR Number 3 of 19 for October 20, 2009
The PDD describes some major risks, however other natural and human induced risks also
exist. Based on community meetings and interviews, other potential risks are drought on wildlife,
drought on fruit tree plantings and invasion of people into the project area because of desirable grazing
areas. These are likely risks that must be addressed in sufficient detail for third party evaluation.
October 30, 2009: We have revised sections G3.5 of the PDD to include the
text below, to provide additional risks and mitigation strategies. We believe that this new information
provided to the Validator together with the additions made to Section GL1.2 in response to finding
NCR#18 and previously provided is a more than adequate response to your finding and meets the
e ask that you consider this finding NCR#3 closed.
The revised PDD now includes all identified risks and likewise presents mitigation
None
October 20, 2009
The PDD describes the potential risk of fire and some mitigation activities
project proponent may also consider constructing effective firebreaks as an additional mitigation
dence of recent fire in the project area, observed during the site visit .
October 24, 2009: Fire breaks are unfortunately fairly ineffective in this area
against the worst fires, as evidenced by the fact that in 1998 fire jumped the Main Mombasa Highway to
enter into the Project Area from the North boundary, a distance including the road reserve of some two
hundred meters. This is because in high fire risk periods, smoldering elephant dung becomes airborne
some significant distance to relight dry grass on the other side of the
Demonstrate that the project design includes specific measures to ensure the
enhancement of the high conservation value attributes identified in G1
The revised PDD demonstrates that the project design includes specific measures to ensure
the maintenance and enhancement of HCV in the project zone. In response to an initial finding issued
for missing HCV values under Indicator G1.8, Section G3.6 of the revised PDD contains references to
NCR Number 2 of 19 for October 20, 2009). The project design does not ad
affect the maintenance of HCV in the project zone.
however other natural and human induced risks also
exist. Based on community meetings and interviews, other potential risks are drought on wildlife,
drought on fruit tree plantings and invasion of people into the project area because of desirable grazing
areas. These are likely risks that must be addressed in sufficient detail for third party evaluation.
We have revised sections G3.5 of the PDD to include the
strategies. We believe that this new information
provided to the Validator together with the additions made to Section GL1.2 in response to finding
NCR#18 and previously provided is a more than adequate response to your finding and meets the
The revised PDD now includes all identified risks and likewise presents mitigation
for this risk. The
project proponent may also consider constructing effective firebreaks as an additional mitigation
dence of recent fire in the project area, observed during the site visit .
Fire breaks are unfortunately fairly ineffective in this area
Main Mombasa Highway to
enter into the Project Area from the North boundary, a distance including the road reserve of some two
hundred meters. This is because in high fire risk periods, smoldering elephant dung becomes airborne
some significant distance to relight dry grass on the other side of the
Demonstrate that the project design includes specific measures to ensure the
G1 consistent with
The revised PDD demonstrates that the project design includes specific measures to ensure
in the project zone. In response to an initial finding issued
for missing HCV values under Indicator G1.8, Section G3.6 of the revised PDD contains references to
). The project design does not adversely
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G3.7. Describe the measures that will
community and biodiversity benefits beyond the project lifetime.
Findings: The PDD describes three measures that will be taken to maintain and enhance the project
benefits beyond the lifetime of the project:
relatively permanent conservation easement. These measures clearly maintain and enhance the
project benefits beyond the lifetime of the project.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G3.8. Document and defend how communities and other stakeholders potentially affected by
the project activities have been identified and have been involved in project design
consultation, particularly with a view to optimizing community and stakeholder benefits, respecting
local customs and values and maintaining high conservation values. Project developers must document
stakeholder dialogues and indicate if
plan must be developed to continue communication and consultation between project managers and all
community groups about the project and its impacts to facilitate adaptive management through
life of the project.
Findings: Several stakeholder groups potentially affected by the project activities were involved in the
project design both formally and informally. Formal documentation was observed for the involvement
of the shareholders of the Rukinga Ranching Company. Community groups were
formal documentation was made regarding their involvement in project design. Based on interviews
with community members, the project does not appear to be disrespectful of loc
Also, the project appears to maintain HCV.
Given the overall lack of documentation regarding the involvement of stakeholders, it was unclear if all
the shareholders of Rukinga Ranching Company clearly supported the project. Given
shareholder rights to the project area and based on the evidence collected during the site visit, it was
found that the project proponent needed to clearly document the support of the shareholders for the
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
19
Yes No N/A
See NCR Number 2 of 19 for October 20, 2009
None
None
Describe the measures that will be taken to maintain and enhance the climate,
biodiversity benefits beyond the project lifetime.
The PDD describes three measures that will be taken to maintain and enhance the project
benefits beyond the lifetime of the project: long-term job creation, long-term financial health and
relatively permanent conservation easement. These measures clearly maintain and enhance the
project benefits beyond the lifetime of the project.
Yes No N/A
None
None
None
Document and defend how communities and other stakeholders potentially affected by
project activities have been identified and have been involved in project design
consultation, particularly with a view to optimizing community and stakeholder benefits, respecting
local customs and values and maintaining high conservation values. Project developers must document
stakeholder dialogues and indicate if and how the project proposal was revised based on such input. A
plan must be developed to continue communication and consultation between project managers and all
community groups about the project and its impacts to facilitate adaptive management through
Several stakeholder groups potentially affected by the project activities were involved in the
project design both formally and informally. Formal documentation was observed for the involvement
of the Rukinga Ranching Company. Community groups were involved
formal documentation was made regarding their involvement in project design. Based on interviews
with community members, the project does not appear to be disrespectful of local customs and values.
project appears to maintain HCV.
iven the overall lack of documentation regarding the involvement of stakeholders, it was unclear if all
the shareholders of Rukinga Ranching Company clearly supported the project. Given
shareholder rights to the project area and based on the evidence collected during the site visit, it was
found that the project proponent needed to clearly document the support of the shareholders for the
NCR Number 2 of 19 for October 20, 2009
be taken to maintain and enhance the climate,
The PDD describes three measures that will be taken to maintain and enhance the project
term financial health and
relatively permanent conservation easement. These measures clearly maintain and enhance the
Document and defend how communities and other stakeholders potentially affected by
project activities have been identified and have been involved in project design through effective
consultation, particularly with a view to optimizing community and stakeholder benefits, respecting
local customs and values and maintaining high conservation values. Project developers must document
based on such input. A
plan must be developed to continue communication and consultation between project managers and all
community groups about the project and its impacts to facilitate adaptive management throughout the
Several stakeholder groups potentially affected by the project activities were involved in the
project design both formally and informally. Formal documentation was observed for the involvement
involved as well but no
formal documentation was made regarding their involvement in project design. Based on interviews
al customs and values.
iven the overall lack of documentation regarding the involvement of stakeholders, it was unclear if all
the shareholders of Rukinga Ranching Company clearly supported the project. Given the materiality of
shareholder rights to the project area and based on the evidence collected during the site visit, it was
found that the project proponent needed to clearly document the support of the shareholders for the
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
project (see NCR Number 1 of 1 f
conformance of the project to Indicators
conformance to this indicator in the context of the shareholders, however there was sufficient
evidence regarding the documentation of other stakeholders groups.
In response to an initial finding, the project proponent has enacted a plan to communicate the project
with all identified community groups (see
documentation on dialogs and adaptive management. However given the lack of documentation on the
involvement of stakeholders, in general, to the design of this project, here is
conformance to this indicator. However because no
customs, local values or high conservation values
this finding is immaterial to conformance with the criterion.
Conformance:
Non-Conformity Reports:
NCR Number 4 of 19 for October 20, 2009
Finding: Provide documentation of stakeholder dialogs and describe how the project proposal was
revised, if it was revised. The project proponent must also develop a plan to continue communication
with all community groups. This documentation and the plan must be addressed in sufficient detail for
third party evaluation.
Proponent Response on November 1
more specific about past meetings in
more formal monitoring going forward. The text of that section is included below. We believe this
represents a complete and acceptable response to your finding and meets the standard and we
you close finding NCR#4.
Validator Response: The project propo
documented evidence that all stakeholder groups were involved in project design. The plan for more
formal monitoring should be sufficient for future documentation under Criterion G3.
NCR Number 1 of 1 for November 12, 2009
Finding: The legal framework for the Carbon Easement is clear; however, no documentation has been
provided demonstrating that the project is undertaken
consent. The only evidence of consent is legal documentation, the Carbon Easement, stemming from a
convention of shareholders, not all of whom might have been present at the meeting. As no
documentation to the effect of attendance has been provided, it is unclear whether all shareholders
were present at the AGM and wheth
Further based on supplemental guidance provided by CCBA, consultation with those whose rights will be
affected by the project is required. Clearly, the Carbon Easement affects the right of all the
shareholders. No documented evidence, other than legal evidence, has been provided to demonstrate
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
20
for November 12, 2009). This evidence was further material to the
conformance of the project to Indicators G5.3 and G5.6. The presented documentation supported
conformance to this indicator in the context of the shareholders, however there was sufficient
evidence regarding the documentation of other stakeholders groups.
In response to an initial finding, the project proponent has enacted a plan to communicate the project
with all identified community groups (see NCR Number 4 of 19 for October 20, 2009). This plan entails
documentation on dialogs and adaptive management. However given the lack of documentation on the
involvement of stakeholders, in general, to the design of this project, here is insufficient
tor. However because no community benefits, stakeholder benefits,
high conservation values appear to be negatively affected by the project design
o conformance with the criterion.
Yes No N/A
NCR Number 4 of 19 for October 20, 2009
Provide documentation of stakeholder dialogs and describe how the project proposal was
revised, if it was revised. The project proponent must also develop a plan to continue communication
all community groups. This documentation and the plan must be addressed in sufficient detail for
November 1, 2009: We have significantly enhanced Section G3.8 to be much
more specific about past meetings in the formulation of the REDD project, and to demonstrate a plan for
more formal monitoring going forward. The text of that section is included below. We believe this
represents a complete and acceptable response to your finding and meets the standard and we
proponent has enhanced Section G3.8, however there is insufficient
documented evidence that all stakeholder groups were involved in project design. The plan for more
uld be sufficient for future documentation under Criterion G3.
for November 12, 2009
The legal framework for the Carbon Easement is clear; however, no documentation has been
provided demonstrating that the project is undertaken on behalf of the carbon owners with their full
consent. The only evidence of consent is legal documentation, the Carbon Easement, stemming from a
convention of shareholders, not all of whom might have been present at the meeting. As no
the effect of attendance has been provided, it is unclear whether all shareholders
were present at the AGM and whether all gave their full consent.
Further based on supplemental guidance provided by CCBA, consultation with those whose rights will be
ed by the project is required. Clearly, the Carbon Easement affects the right of all the
shareholders. No documented evidence, other than legal evidence, has been provided to demonstrate
). This evidence was further material to the
The presented documentation supported
conformance to this indicator in the context of the shareholders, however there was sufficient lack of
In response to an initial finding, the project proponent has enacted a plan to communicate the project
). This plan entails
documentation on dialogs and adaptive management. However given the lack of documentation on the
insufficient evidence for
stakeholder benefits, local
appear to be negatively affected by the project design,
Provide documentation of stakeholder dialogs and describe how the project proposal was
revised, if it was revised. The project proponent must also develop a plan to continue communication
all community groups. This documentation and the plan must be addressed in sufficient detail for
We have significantly enhanced Section G3.8 to be much
the formulation of the REDD project, and to demonstrate a plan for
more formal monitoring going forward. The text of that section is included below. We believe this
represents a complete and acceptable response to your finding and meets the standard and we ask that
there is insufficient
documented evidence that all stakeholder groups were involved in project design. The plan for more
The legal framework for the Carbon Easement is clear; however, no documentation has been
on behalf of the carbon owners with their full
consent. The only evidence of consent is legal documentation, the Carbon Easement, stemming from a
convention of shareholders, not all of whom might have been present at the meeting. As no
the effect of attendance has been provided, it is unclear whether all shareholders
Further based on supplemental guidance provided by CCBA, consultation with those whose rights will be
ed by the project is required. Clearly, the Carbon Easement affects the right of all the
shareholders. No documented evidence, other than legal evidence, has been provided to demonstrate
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
that the project will not encroach uninvited on the rights of all s
evidence has been provided regarding the free, prior and informed consent of all shareholders.
Please provide documentation that all known shareholders were present at the AGM and gave their full
consent or please provide an opportunity to all shareholders to object to the project. Either of these
provisions will be considered adequate to demonstrate the consent (or objection) of all shareholders in
the context of indicators G3.8, G5.3 and G5.6. Should the latter of t
notification to each known shareholder must be documented and all shareholders must be allowed to
object in writing or person within a reasonable amount of time. A reasonable amount of time is at least
30 days from the date of notification.
Proponent Response on December 9
was to hold a Extraordinary General Meeting (EGM)of the Shareholders of Rukinga Ranching Co Ltd. for
which the agenda was one item; a resolution t
project, Phase I, and the Carbon Easement with Wildlife Works, Inc. that legalizes the pursuit of that
project. We mailed out 46 letters one to each Shareholder, inviting them to attend the EGM to be held
at Voi town on December 9th 2009, and we included in their letters a Proxy form by which they could
vote for or against the project in absentia without having to attend the EGM. The letters of invitation
provided for the statutory 21 days notice. The Valid
adequate. We have provided the Validator with copies of each letter sent out, together with the Proxy
form and the Resolution description. Wildlife Works staff then spent two full days in the community
trying to track down all the shareholders and were able to meet face to face with all except one, to
ensure they all knew of the meeting. We have provided the Validator with the minutes of the
Extraordinary General Meeting and with a shareholder count, and list of
vote was unanimous. Legally, only a simple majority of Rukinga’s Shareholders are required to approve
this Resolution, but we understand the Validator’s interest in knowing more detail behind the level of
support from the local shareholders, and we believe the results of this Extraordinary General Meeting
more than adequately demonstrate that the Shareholders of Rukinga Ranching Company
overwhelmingly support this REDD Project, and we ask that this finding be closed.
Please note the proceedings of the Extraordinary General Meeting are confidential and should not be
made part of the public record.
Validator Response: The provided proceedings clearly document the support of the project by the
shareholders of Rukinga Ranching Company.
New Information Requests:
Opportunities for Improvement:
Indicator G3.9. Describe what specific steps have been taken, and communications methods used, to
publicize the CCBA public comment period to communities and other stakeholders and to facilitate their
submission of comments to CCBA. Project proponents must play an active
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
21
that the project will not encroach uninvited on the rights of all shareholders. Likewise, no documented
evidence has been provided regarding the free, prior and informed consent of all shareholders.
Please provide documentation that all known shareholders were present at the AGM and gave their full
ide an opportunity to all shareholders to object to the project. Either of these
provisions will be considered adequate to demonstrate the consent (or objection) of all shareholders in
the context of indicators G3.8, G5.3 and G5.6. Should the latter of these options be pursued,
notification to each known shareholder must be documented and all shareholders must be allowed to
object in writing or person within a reasonable amount of time. A reasonable amount of time is at least
ification.
December 9, 2009: As agreed with the validator our response to this finding
was to hold a Extraordinary General Meeting (EGM)of the Shareholders of Rukinga Ranching Co Ltd. for
which the agenda was one item; a resolution to approve the pursuit of the Kasigau Corridor REDD
project, Phase I, and the Carbon Easement with Wildlife Works, Inc. that legalizes the pursuit of that
project. We mailed out 46 letters one to each Shareholder, inviting them to attend the EGM to be held
at Voi town on December 9th 2009, and we included in their letters a Proxy form by which they could
vote for or against the project in absentia without having to attend the EGM. The letters of invitation
provided for the statutory 21 days notice. The Validator agreed that the 21 day notice period was
adequate. We have provided the Validator with copies of each letter sent out, together with the Proxy
form and the Resolution description. Wildlife Works staff then spent two full days in the community
o track down all the shareholders and were able to meet face to face with all except one, to
ensure they all knew of the meeting. We have provided the Validator with the minutes of the
Extraordinary General Meeting and with a shareholder count, and list of those voting in favor, which
vote was unanimous. Legally, only a simple majority of Rukinga’s Shareholders are required to approve
this Resolution, but we understand the Validator’s interest in knowing more detail behind the level of
l shareholders, and we believe the results of this Extraordinary General Meeting
more than adequately demonstrate that the Shareholders of Rukinga Ranching Company
overwhelmingly support this REDD Project, and we ask that this finding be closed.
e the proceedings of the Extraordinary General Meeting are confidential and should not be
The provided proceedings clearly document the support of the project by the
Ranching Company.
None
None
Describe what specific steps have been taken, and communications methods used, to
publicize the CCBA public comment period to communities and other stakeholders and to facilitate their
submission of comments to CCBA. Project proponents must play an active role in distributing key project
hareholders. Likewise, no documented
evidence has been provided regarding the free, prior and informed consent of all shareholders.
Please provide documentation that all known shareholders were present at the AGM and gave their full
ide an opportunity to all shareholders to object to the project. Either of these
provisions will be considered adequate to demonstrate the consent (or objection) of all shareholders in
hese options be pursued,
notification to each known shareholder must be documented and all shareholders must be allowed to
object in writing or person within a reasonable amount of time. A reasonable amount of time is at least
As agreed with the validator our response to this finding
was to hold a Extraordinary General Meeting (EGM)of the Shareholders of Rukinga Ranching Co Ltd. for
o approve the pursuit of the Kasigau Corridor REDD
project, Phase I, and the Carbon Easement with Wildlife Works, Inc. that legalizes the pursuit of that
project. We mailed out 46 letters one to each Shareholder, inviting them to attend the EGM to be held
at Voi town on December 9th 2009, and we included in their letters a Proxy form by which they could
vote for or against the project in absentia without having to attend the EGM. The letters of invitation
ator agreed that the 21 day notice period was
adequate. We have provided the Validator with copies of each letter sent out, together with the Proxy
form and the Resolution description. Wildlife Works staff then spent two full days in the community
o track down all the shareholders and were able to meet face to face with all except one, to
ensure they all knew of the meeting. We have provided the Validator with the minutes of the
those voting in favor, which
vote was unanimous. Legally, only a simple majority of Rukinga’s Shareholders are required to approve
this Resolution, but we understand the Validator’s interest in knowing more detail behind the level of
l shareholders, and we believe the results of this Extraordinary General Meeting
more than adequately demonstrate that the Shareholders of Rukinga Ranching Company
e the proceedings of the Extraordinary General Meeting are confidential and should not be
The provided proceedings clearly document the support of the project by the
Describe what specific steps have been taken, and communications methods used, to
publicize the CCBA public comment period to communities and other stakeholders and to facilitate their
role in distributing key project
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
documents to affected communities and stakeholders and hold widely publicized information meetings
in relevant local or regional languages.
Findings: The public comment period was well publicized as demonstrated by the la
submitted comments from the local community. Section G3.9 of the revised PDD describes the methods
used for publicizing the comment period, including how non
submitted for CCBA.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G3.10. Formalize a clear process for handling unresolved conflicts and grievances that arise
during project planning and implementation. The project design must include a process f
responding to and resolving community and other stakeholder grievances within a reasonable time
period. This grievance process must be publicized to communities and other stakeholders and must be
managed by a third party or mediator to prevent
attempt to resolve all reasonable grievances raised, and provide a written response to grievances within
30 days. Grievances and project responses must be documented.
Findings: Initially, no clear proces
that arise during project planning and implementation (see
However in response to an issued finding, a formal process was made and documented by
proponent in a document titled the “
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
22
documents to affected communities and stakeholders and hold widely publicized information meetings
in relevant local or regional languages.
The public comment period was well publicized as demonstrated by the la
submitted comments from the local community. Section G3.9 of the revised PDD describes the methods
used for publicizing the comment period, including how non-electronic comments were transcribed and
Yes No N/A
None
None
None
Formalize a clear process for handling unresolved conflicts and grievances that arise
during project planning and implementation. The project design must include a process f
responding to and resolving community and other stakeholder grievances within a reasonable time
period. This grievance process must be publicized to communities and other stakeholders and must be
managed by a third party or mediator to prevent any conflict of interest. Project management must
attempt to resolve all reasonable grievances raised, and provide a written response to grievances within
30 days. Grievances and project responses must be documented.
Initially, no clear processes was formalized for handling unresolved conflicts and grievances
that arise during project planning and implementation (see NCR Number 5 of 19 for October 20, 2009
However in response to an issued finding, a formal process was made and documented by
proponent in a document titled the “Wildlife Works Community Conflict Process.”
Yes No N/A
documents to affected communities and stakeholders and hold widely publicized information meetings
The public comment period was well publicized as demonstrated by the large number of
submitted comments from the local community. Section G3.9 of the revised PDD describes the methods
electronic comments were transcribed and
Formalize a clear process for handling unresolved conflicts and grievances that arise
during project planning and implementation. The project design must include a process for hearing,
responding to and resolving community and other stakeholder grievances within a reasonable time
period. This grievance process must be publicized to communities and other stakeholders and must be
any conflict of interest. Project management must
attempt to resolve all reasonable grievances raised, and provide a written response to grievances within
ses was formalized for handling unresolved conflicts and grievances
NCR Number 5 of 19 for October 20, 2009).
However in response to an issued finding, a formal process was made and documented by the project
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 5 of 19 for October 20, 2009
Finding: The PDD contains a brief summary of the process for resolving disputes. However, the
proponent must formalize a plan to handle unresolved grievances that arise during the planning or
implementation of the project.
Proponent Response on October 26
Community Conflict Process to encapsulate the experience we have had over the years in resolving
disputes amicably within the communities of the Project Zone. We have updated the content of section
G3.10 of the PDD to refer to this document, and have included the text below. We beli
document together with our strong track record of excellent community relations demonstrates
categorically that we have a legitimate grievance and conflict resolution process, and we ask that you
close NCR#5.
Validator Response: The supplied docum
therefore adequate.
New Information Requests:
Opportunities for Improvement:
Indicator G3.11. Demonstrate that financial mechanisms adopted, including projected revenues from
emissions reductions and other sources, are likely to provide an adequate flow of funds for project
implementation and to achieve the anticipated climate, community and biodiversity benefits.
Findings: Detailed information regarding the financial mechanisms for project implementation were
absent from the initial PDD (see NCR Number 6 of 19 for October 20, 2009
initial finding, the project proponent supplied a detailed cash flo
adequate flow of funds for project implementation. The supplied analysis included the costs and
revenues of all project activities and therefore inherently shows that the anticipated climate, community
and biodiversity benefits can be achieved by the adopted financial mechanisms.
Conformance:
Non-Conformity Reports:
NCR Number 6 of 19 for October 20, 2009
Finding: The project proponent must provide a document to validate the adequacy of the flow of funds
for project implementation and the financial health of the implementing organization. Include all
expected revenues and estimated costs for project actives over time. The document must be of
sufficient detail for evaluation by a third party.
Proponent Response on October 28
Validators a detailed spreadsheet of the first two years cash flow for the project, indicating there will be
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
23
NCR Number 5 of 19 for October 20, 2009
The PDD contains a brief summary of the process for resolving disputes. However, the
proponent must formalize a plan to handle unresolved grievances that arise during the planning or
October 26, 2009: We have created a new document, the Wildlife Works
to encapsulate the experience we have had over the years in resolving
disputes amicably within the communities of the Project Zone. We have updated the content of section
G3.10 of the PDD to refer to this document, and have included the text below. We beli
document together with our strong track record of excellent community relations demonstrates
categorically that we have a legitimate grievance and conflict resolution process, and we ask that you
The supplied document is a formal plan to handle unresolved grievances and it
None
None
Demonstrate that financial mechanisms adopted, including projected revenues from
ions reductions and other sources, are likely to provide an adequate flow of funds for project
implementation and to achieve the anticipated climate, community and biodiversity benefits.
Detailed information regarding the financial mechanisms for project implementation were
NCR Number 6 of 19 for October 20, 2009). However
, the project proponent supplied a detailed cash flow analysis that demonstrated an
adequate flow of funds for project implementation. The supplied analysis included the costs and
revenues of all project activities and therefore inherently shows that the anticipated climate, community
fits can be achieved by the adopted financial mechanisms.
Yes No N/A
NCR Number 6 of 19 for October 20, 2009
The project proponent must provide a document to validate the adequacy of the flow of funds
and the financial health of the implementing organization. Include all
expected revenues and estimated costs for project actives over time. The document must be of
sufficient detail for evaluation by a third party.
October 28, 2009: Text added to Section G3.11 - We have sent the Project
Validators a detailed spreadsheet of the first two years cash flow for the project, indicating there will be
The PDD contains a brief summary of the process for resolving disputes. However, the project
proponent must formalize a plan to handle unresolved grievances that arise during the planning or
We have created a new document, the Wildlife Works
to encapsulate the experience we have had over the years in resolving
disputes amicably within the communities of the Project Zone. We have updated the content of section
G3.10 of the PDD to refer to this document, and have included the text below. We believe this
document together with our strong track record of excellent community relations demonstrates
categorically that we have a legitimate grievance and conflict resolution process, and we ask that you
ent is a formal plan to handle unresolved grievances and it
Demonstrate that financial mechanisms adopted, including projected revenues from
ions reductions and other sources, are likely to provide an adequate flow of funds for project
implementation and to achieve the anticipated climate, community and biodiversity benefits.
Detailed information regarding the financial mechanisms for project implementation were
. However subsequent to an
w analysis that demonstrated an
adequate flow of funds for project implementation. The supplied analysis included the costs and
revenues of all project activities and therefore inherently shows that the anticipated climate, community
The project proponent must provide a document to validate the adequacy of the flow of funds
and the financial health of the implementing organization. Include all
expected revenues and estimated costs for project actives over time. The document must be of
We have sent the Project
Validators a detailed spreadsheet of the first two years cash flow for the project, indicating there will be
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
a large surplus of funds at the end of year 2, and showing the steady state finances for a
project from 2011 and onwards. The revenues in the cash flow are based on an actual transaction to sell
precertified carbon credits that is in the final stages and will close before end November 2009, so there
is very little speculation about this cash flow.
This cash flow matches the Project Implementation Schedule to be provided to the Validator under NIR
#2, and to support this cash flow document, we have also sent the Validator the following documents
which will demonstrate that we have extremely detailed knowledge of what the cap ex costs are to
accomplish the various project activities we are committing to in the implementation schedule;
1) Factory Addition Cell 2 Cost - EcoFactory Expansion Costing for Dye and Screen Print House
2) WW Shade House Costing – Provides cost of building additional shade house at Rukinga and also cost
of each of the 5 community nurseries we will build in the Villages
3) Bungule Guard Post Costing – provides the cost of adding a new Ranger Station to mon
boundary of the Project Area
4) Typical Classroom Budget – budget indicating that our $10K a year school construction maintenance
budget would be adequate to build a new classroom every year if that is what the community wanted.
We have revised sections 3.11 and 4.7 to include the text above and to reference these documents sent
to the validator. As we have indicated in the past this financial data is commercially sensitive and we ask
that it not become a part of the public record of the our CCB
We believe that this new information provided to the Validator clearly shows that the project has the
financial means to carry out the project activities, and we believe this is a more than adequate response
to your finding and we ask that you consid
Validator Response: The supplied cash flow analysis demonstrates that the adopted financial
mechanisms provide an adequate flow of funds.
New Information Requests:
Opportunities for Improvement:
3.2.4. G4 – Management Capacity
The success of a project depends upon the competence of the implementing management team.
Projects that include a significant capacity
likely to sustain the positive outcomes generated by the project and have them replicated elsewhere.
Best practices for project management include: local stakeho
safety and a clear process for handling grievances.
Indicators
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
24
a large surplus of funds at the end of year 2, and showing the steady state finances for a
project from 2011 and onwards. The revenues in the cash flow are based on an actual transaction to sell
precertified carbon credits that is in the final stages and will close before end November 2009, so there
bout this cash flow.
This cash flow matches the Project Implementation Schedule to be provided to the Validator under NIR
#2, and to support this cash flow document, we have also sent the Validator the following documents
ve extremely detailed knowledge of what the cap ex costs are to
accomplish the various project activities we are committing to in the implementation schedule;
EcoFactory Expansion Costing for Dye and Screen Print House
Provides cost of building additional shade house at Rukinga and also cost
of each of the 5 community nurseries we will build in the Villages
provides the cost of adding a new Ranger Station to mon
budget indicating that our $10K a year school construction maintenance
budget would be adequate to build a new classroom every year if that is what the community wanted.
sections 3.11 and 4.7 to include the text above and to reference these documents sent
to the validator. As we have indicated in the past this financial data is commercially sensitive and we ask
blic record of the our CCB PDD.
We believe that this new information provided to the Validator clearly shows that the project has the
financial means to carry out the project activities, and we believe this is a more than adequate response
to your finding and we ask that you consider this finding NCR#6 closed.
The supplied cash flow analysis demonstrates that the adopted financial
mechanisms provide an adequate flow of funds.
None
None
Capacity and Best Practices
The success of a project depends upon the competence of the implementing management team.
Projects that include a significant capacity-building (training, skill building, etc.) component are more
outcomes generated by the project and have them replicated elsewhere.
Best practices for project management include: local stakeholder employment, worker rights,
safety and a clear process for handling grievances.
a large surplus of funds at the end of year 2, and showing the steady state finances for a full year of the
project from 2011 and onwards. The revenues in the cash flow are based on an actual transaction to sell
precertified carbon credits that is in the final stages and will close before end November 2009, so there
This cash flow matches the Project Implementation Schedule to be provided to the Validator under NIR
#2, and to support this cash flow document, we have also sent the Validator the following documents
ve extremely detailed knowledge of what the cap ex costs are to
accomplish the various project activities we are committing to in the implementation schedule;
EcoFactory Expansion Costing for Dye and Screen Print House
Provides cost of building additional shade house at Rukinga and also cost
provides the cost of adding a new Ranger Station to monitor the SE
budget indicating that our $10K a year school construction maintenance
budget would be adequate to build a new classroom every year if that is what the community wanted.
sections 3.11 and 4.7 to include the text above and to reference these documents sent
to the validator. As we have indicated in the past this financial data is commercially sensitive and we ask
We believe that this new information provided to the Validator clearly shows that the project has the
financial means to carry out the project activities, and we believe this is a more than adequate response
The supplied cash flow analysis demonstrates that the adopted financial
The success of a project depends upon the competence of the implementing management team.
building (training, skill building, etc.) component are more
outcomes generated by the project and have them replicated elsewhere.
lder employment, worker rights, worker
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
The project proponents must:
Indicator G4.1. Identify a single project proponent which is responsible for the project’s design and
implementation. If multiple organizations or individuals are involved in the project’s
implementation the governance structure, rol
individuals involved must also be described.
Findings: The revised PDD identifies a single project proponent which is responsible for the project’s
design and implementation, Wildlife Works. Subseq
7 of 19 for October 20, 2009), the roles and responsibilities of each individual are also presented in
Section G4.1 of the PDD.
Conformance:
Non-Conformity Reports:
NCR Number 7 of 19 for October 20, 2009
Finding: The PDD describes some of the organizations responsible for project design. Also provide a
description of the individuals responsible for project implementation including their roles and
responsibilities.
Proponent Response on October 29
text below.
We believe that this new information provided to the Validator
your finding and meets the Standard and we ask that you consider this finding NCR#7 closed.
Validator Response: The revised sections now provide an adequate description of all individual’s
responsibilities for project implementation.
New Information Requests:
Opportunities for Improvement:
Indicator G4.2. Document key technical skills that will be re
including community engagement, biodiversity assessment and
skills. Document the management team’s expertise and prior experience
management projects at the scale of this project. If relevant experience is
either demonstrate how other organizations will be partnered with to
recruitment strategy to fill the gaps.
Findings: Section G4.2 of the revised PDD documents
successfully implement the project. Initially, the PDD lacked information about the management team’s
expertise and prior experience implementing land management projects at the scale of this project (see
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
25
Identify a single project proponent which is responsible for the project’s design and
implementation. If multiple organizations or individuals are involved in the project’s
implementation the governance structure, roles and responsibilities of each of the organizations or
individuals involved must also be described.
The revised PDD identifies a single project proponent which is responsible for the project’s
design and implementation, Wildlife Works. Subsequent to a finding on this indicator (see
he roles and responsibilities of each individual are also presented in
Yes No N/A
7 of 19 for October 20, 2009
The PDD describes some of the organizations responsible for project design. Also provide a
description of the individuals responsible for project implementation including their roles and
October 29, 2009: We have revised sections G4.1 of the PDD to include the
We believe that this new information provided to the Validator is a more than adequate response to
your finding and meets the Standard and we ask that you consider this finding NCR#7 closed.
The revised sections now provide an adequate description of all individual’s
implementation.
None
None
Document key technical skills that will be required to implement the project
including community engagement, biodiversity assessment and carbon measurement and
skills. Document the management team’s expertise and prior experience implementing land
management projects at the scale of this project. If relevant experience is lacking, the proponents must
organizations will be partnered with to support the project or have a
recruitment strategy to fill the gaps.
Section G4.2 of the revised PDD documents the technical skills that will be required to
successfully implement the project. Initially, the PDD lacked information about the management team’s
implementing land management projects at the scale of this project (see
Identify a single project proponent which is responsible for the project’s design and
development and
the organizations or
The revised PDD identifies a single project proponent which is responsible for the project’s
uent to a finding on this indicator (see NCR Number
he roles and responsibilities of each individual are also presented in
The PDD describes some of the organizations responsible for project design. Also provide a
description of the individuals responsible for project implementation including their roles and
We have revised sections G4.1 of the PDD to include the
is a more than adequate response to
your finding and meets the Standard and we ask that you consider this finding NCR#7 closed.
The revised sections now provide an adequate description of all individual’s
quired to implement the project successfully,
carbon measurement and monitoring
implementing land
lacking, the proponents must
support the project or have a
the technical skills that will be required to
successfully implement the project. Initially, the PDD lacked information about the management team’s
implementing land management projects at the scale of this project (see
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 8 of 19 for October 20, 2009
amended to include this information. The expertise and prior experience of the management team
seems to be adequate to the successful implementation of this pro
Conformance:
Non-Conformity Reports:
NCR Number 8 of 19 for October 20, 2009
Finding: Some of the individuals and their technical skills are provided in the PDD. However, there are
several other key technical skills that
mentioned the PDD. Also document the expertise and prior experience of the management team with
respect to land management projects.
Proponent Response on October 26
the PDD, and have included the text below. We believe this demonstrates categorically that we have
assembled the skills needed to continue to have success with this project into the future, and we ask
that you close NCR#8.
Validator Response: The amended PDD is now adequate with respect to this finding.
New Information Requests:
Opportunities for Improvement:
Indicator G4.3. Include a plan to provide orientation and training for the project’s
relevant people from the communities with an objective of building locally useful skills and knowledge
to increase local participation in project implementation. These capacity building efforts should
wide range of people in the communities, including minority and underrepresented
training will be passed on to new workers when there is staff turnover, so
lost.
Findings: The revised PDD contains information and references to orient
project’s employees. Initially, documented orientation and
the employees of the project (see NCR Number 9 of 19 for October 20, 2009
on this indicator, training manual were provided and references to the training manual were made in
the revised PDD. It was also noted that the project management could instate a documented policy to
include local community members in management positions as indicated by managem
site visit (see OFI Number 3 of 4 for October 20, 2009
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
26
Number 8 of 19 for October 20, 2009). Subsequent to a finding on this indicator, the PDD was
amended to include this information. The expertise and prior experience of the management team
seems to be adequate to the successful implementation of this project given the project’s size and scale.
Yes No N/A
NCR Number 8 of 19 for October 20, 2009
Some of the individuals and their technical skills are provided in the PDD. However, there are
several other key technical skills that are required to implement some of the project actives that are not
mentioned the PDD. Also document the expertise and prior experience of the management team with
respect to land management projects.
October 26, 2009: We have significantly updated the content of section 4.2 of
the PDD, and have included the text below. We believe this demonstrates categorically that we have
assembled the skills needed to continue to have success with this project into the future, and we ask
The amended PDD is now adequate with respect to this finding.
None
None
Include a plan to provide orientation and training for the project’s
from the communities with an objective of building locally useful skills and knowledge
ncrease local participation in project implementation. These capacity building efforts should
unities, including minority and underrepresented groups. Identify how
training will be passed on to new workers when there is staff turnover, so that local capacity will not be
The revised PDD contains information and references to orientation and training for the
documented orientation and training information was absent for most of
NCR Number 9 of 19 for October 20, 2009). Subsequent to a finding
ing manual were provided and references to the training manual were made in
the revised PDD. It was also noted that the project management could instate a documented policy to
include local community members in management positions as indicated by managem
OFI Number 3 of 4 for October 20, 2009).
Yes No N/A
). Subsequent to a finding on this indicator, the PDD was
amended to include this information. The expertise and prior experience of the management team
ject given the project’s size and scale.
Some of the individuals and their technical skills are provided in the PDD. However, there are
are required to implement some of the project actives that are not
mentioned the PDD. Also document the expertise and prior experience of the management team with
icantly updated the content of section 4.2 of
the PDD, and have included the text below. We believe this demonstrates categorically that we have
assembled the skills needed to continue to have success with this project into the future, and we ask
Include a plan to provide orientation and training for the project’s employees and
from the communities with an objective of building locally useful skills and knowledge
ncrease local participation in project implementation. These capacity building efforts should target a
groups. Identify how
that local capacity will not be
ation and training for the
ing information was absent for most of
). Subsequent to a finding
ing manual were provided and references to the training manual were made in
the revised PDD. It was also noted that the project management could instate a documented policy to
include local community members in management positions as indicated by management during the
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 9 of 19 for October 20, 2009
Finding: The project proponents have includ
exists for training rangers, greenhouse staff or management positions. Please provide training plans for
all project employees. Also, indicate how community member will be given a fair chance to fil
for which they can be trained.
Proponent Response on October 24
Wildlife Works Rangers and the Organic Greenhouse Project and on review we believe them to still be of
excellent quality, addressing all aspects of those jobs including hazards and safety precautions. We have
submitted those documents electronically for your review and believe that this is a more than
acceptable response to this aspect of the finding.
With regard to the other aspect of the finding, it is our policy to always give preference for any job
position to members of the local community. This includes management roles. At present 100% of non
management roles are currently filled with local community members.
However as stated above we were unable to find local community members with the skills and
experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing
Factory Manager. As a result we hired 1 English expatriate, Rob Dodson wit
area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic
greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management
roles, Paschal Mulonzya (accountant), and Daniel Munyao (Sewing Factory Manager).
We believe in loyalty to our employees and as such as long as those three individuals continue to
perform their job responsibilities well, they will be retained. However, we do already have local peopl
filling three additional management roles within the Project/Company.
1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita
from the immediate community and was one of our first employees and was trained in
now holds – We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site
Manager, and he is being groomed for that role.
2) Joseph Mwanganda – Greenhouse and Jojoba Project Manager
Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project
Zone.Joseph has a wide range of Agricultural skills and experience.
3) Eric Sagwe – Head Wildlife Ranger
promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally
hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father
passed away unexpectedly. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different
region of Kenya, who had been brought in at the start of our Project because he had specific knowledge
and experience of how to set up and manage a Ranger force in the Kenyan bush,
poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
27
NCR Number 9 of 19 for October 20, 2009
The project proponents have included a plan for training factory workers, however no plan
exists for training rangers, greenhouse staff or management positions. Please provide training plans for
all project employees. Also, indicate how community member will be given a fair chance to fil
October 24, 2009: We have located the original training programs for both
Wildlife Works Rangers and the Organic Greenhouse Project and on review we believe them to still be of
lity, addressing all aspects of those jobs including hazards and safety precautions. We have
submitted those documents electronically for your review and believe that this is a more than
acceptable response to this aspect of the finding.
other aspect of the finding, it is our policy to always give preference for any job
position to members of the local community. This includes management roles. At present 100% of non
management roles are currently filled with local community members.
ver as stated above we were unable to find local community members with the skills and
experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing
Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge of the
area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic
greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management
countant), and Daniel Munyao (Sewing Factory Manager).
We believe in loyalty to our employees and as such as long as those three individuals continue to
perform their job responsibilities well, they will be retained. However, we do already have local peopl
filling three additional management roles within the Project/Company.
1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita
from the immediate community and was one of our first employees and was trained in
We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site
Manager, and he is being groomed for that role.
Greenhouse and Jojoba Project Manager – Joseph is a consultant to
Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project
Zone.Joseph has a wide range of Agricultural skills and experience.
Head Wildlife Ranger - Eric is a perfect example of our policy to hire locally and to
promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally
hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father
. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different
region of Kenya, who had been brought in at the start of our Project because he had specific knowledge
and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform anti
poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.
ed a plan for training factory workers, however no plan
exists for training rangers, greenhouse staff or management positions. Please provide training plans for
all project employees. Also, indicate how community member will be given a fair chance to fill positions
We have located the original training programs for both
Wildlife Works Rangers and the Organic Greenhouse Project and on review we believe them to still be of
lity, addressing all aspects of those jobs including hazards and safety precautions. We have
submitted those documents electronically for your review and believe that this is a more than
other aspect of the finding, it is our policy to always give preference for any job
position to members of the local community. This includes management roles. At present 100% of non
ver as stated above we were unable to find local community members with the skills and
experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing
h extensive knowledge of the
area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic
greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management
We believe in loyalty to our employees and as such as long as those three individuals continue to
perform their job responsibilities well, they will be retained. However, we do already have local people
1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita
from the immediate community and was one of our first employees and was trained into the position he
We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site
Joseph is a consultant to Wildlife
Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project
licy to hire locally and to
promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally
hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father
. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different
region of Kenya, who had been brought in at the start of our Project because he had specific knowledge
to patrol, perform anti
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
We appreciate the communities desire to fill management roles within the Company/ Project and are
excited at their enthusiasm to do so. We will c
such times as management roles become available we will certainly consider local candidates fist, but
for the future success of the project we must always meet job skill and e
We believe this adequately addresses the finding NCR #9, and that this NCR should now be closed.
Validator Response: The added plans for
are adequate.
New Information Requests:
Opportunities for Improvement:
OFI Number 3 of 4 for October 20, 2009
Finding: Based on community meetings and interviews, the project proponent should consider
incorporating community members to be trained in management roles.
Proponent Response on October 24
to members of the local community. This includes management roles. 100% of non management roles
are currently filled with local community members.
However as stated above we were unable to find local community members with the skills and
experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing
Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge o
area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic
greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management
roles, Paschal Mulonzya (accountant), and Daniel M
We believe in loyalty to our employees and as such as long as those three individuals continue to
perform their job responsibilities well, they will be retained. However, we do already have local people
filling two additional management roles within the Project/Company.
1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita
from the immediate community and was one of our first employees and was trained into the position he
now holds – We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site
Manager, and he is being groomed for that role.
2) Joseph Mwanganda – Greenhouse and Jojoba Project Manager
Works, in addition to his role as Agricultural Outreach Agent for the Government. He is from the Project
Zone.
Joseph has a wide range of Agricultural skills and experience.
3) Eric Sagwe – Head Wildlife Ranger
promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
28
We appreciate the communities desire to fill management roles within the Company/ Project and are
excited at their enthusiasm to do so. We will continue to prioritize local employment and in the future at
such times as management roles become available we will certainly consider local candidates fist, but
for the future success of the project we must always meet job skill and experience requirement
We believe this adequately addresses the finding NCR #9, and that this NCR should now be closed.
The added plans for training rangers, greenhouse staff or management positions
None
OFI Number 3 of 4 for October 20, 2009
Based on community meetings and interviews, the project proponent should consider
incorporating community members to be trained in management roles.
ctober 24, 2009: It is our policy to always give preference for any job position
to members of the local community. This includes management roles. 100% of non management roles
are currently filled with local community members.
were unable to find local community members with the skills and
experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing
Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge o
area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic
greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management
roles, Paschal Mulonzya (accountant), and Daniel Munyao (Sewing Factory Manager).
We believe in loyalty to our employees and as such as long as those three individuals continue to
perform their job responsibilities well, they will be retained. However, we do already have local people
l management roles within the Project/Company.
1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita
from the immediate community and was one of our first employees and was trained into the position he
We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site
Manager, and he is being groomed for that role.
Greenhouse and Jojoba Project Manager – Joseph is a consultant to Wildlife
ion to his role as Agricultural Outreach Agent for the Government. He is from the Project
cultural skills and experience.
Head Wildlife Ranger - Eric is a perfect example of our policy to hire locally an
promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally
We appreciate the communities desire to fill management roles within the Company/ Project and are
ontinue to prioritize local employment and in the future at
such times as management roles become available we will certainly consider local candidates fist, but
xperience requirements as well.
We believe this adequately addresses the finding NCR #9, and that this NCR should now be closed.
training rangers, greenhouse staff or management positions
Based on community meetings and interviews, the project proponent should consider
It is our policy to always give preference for any job position
to members of the local community. This includes management roles. 100% of non management roles
were unable to find local community members with the skills and
experience for the following roles; 1) Project General Manager 2) Company Accountant 3) Sewing
Factory Manager. As a result we hired 1 English expatriate, Rob Dodson with extensive knowledge of the
area, and with a wide range of skills needed to manage a wildlife sanctuary, sewing factory, organic
greenhouse etc., and we hired 2 Kenyans from other parts of Kenya to fill the other two management
We believe in loyalty to our employees and as such as long as those three individuals continue to
perform their job responsibilities well, they will be retained. However, we do already have local people
1) Lenjo Laurian is our Office Manager and handles Community Relations and Personnel, and he is Taita
from the immediate community and was one of our first employees and was trained into the position he
We are also considering Lenjo as a valid candidate to succeed Rob Dodson as Rukinga Site
Joseph is a consultant to Wildlife
ion to his role as Agricultural Outreach Agent for the Government. He is from the Project
Eric is a perfect example of our policy to hire locally and to
promote from within. Eric grew up less than 1 mile from our Project Headquarters, and was originally
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father
passed away unexpectedly. At that time the Head
region of Kenya, who had been brought in at the start of our Project because he had specific knowledge
and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform ant
poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.
We appreciate the communities desire to fill management roles within the Company/ Project and are
excited at their enthusiasm to do so. We will continue to prioritize lo
such times as management roles become available we will certainly consider local candidates fist, but
for the future success of the project we must always meet job skill and e
We believe this adequately addresses the finding OFI #3, and that this OFI should now be closed.
Validator Response: NA
Indicator G.4.4. Show that people from the communities will be given an equal opportunity to fill all
employment positions (including management)
must explain how employees will be selected for positions and where relevant, must indicate how local
community members, including women and other potentially underrepresented groups, will be
fair chance to fill positions for which they can be trained.
Findings: The revised PDD and interviews conducted with management during the site visit show that
people from the communities will be given an equal opportunity to fill all employment positions
However, no formal and documented policy was in place to include local people for the communities
into management roles as verbally indicated during the site visit (see
2009). Further, local community members cannot be
trained if no training plans are available (see
the site visit, the majority shareholder of Rukinga Ranching Company indicated that shares are available
to the local community should they choose to invest in the company, however no formal policy was in
place to clearly document how shares can be purchased and at what price (see OFI
November 12, 2009).
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
OFI Number 1 of 1 for November 12, 2009
Finding: The project proponent has invited the community to acquire shares in Rukinga Ranching
Company. Likewise, on more than one occasion during the site visit, community members have
demonstrated an interest in acquiring shares. However, no clear policy regardi
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
29
hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father
passed away unexpectedly. At that time the Head Ranger was a Kenyan, Ekiru Mirimuk from a different
region of Kenya, who had been brought in at the start of our Project because he had specific knowledge
and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform ant
poaching and other activities. When Ekiru retired, Eric was promoted to Head Ranger.
We appreciate the communities desire to fill management roles within the Company/ Project and are
excited at their enthusiasm to do so. We will continue to prioritize local employment and in the future at
such times as management roles become available we will certainly consider local candidates fist, but
for the future success of the project we must always meet job skill and experience requirements as well.
is adequately addresses the finding OFI #3, and that this OFI should now be closed.
Show that people from the communities will be given an equal opportunity to fill all
positions (including management) if the job requirements are met. Project proponents
explain how employees will be selected for positions and where relevant, must indicate how local
community members, including women and other potentially underrepresented groups, will be
chance to fill positions for which they can be trained.
The revised PDD and interviews conducted with management during the site visit show that
people from the communities will be given an equal opportunity to fill all employment positions
However, no formal and documented policy was in place to include local people for the communities
into management roles as verbally indicated during the site visit (see OFI Number 3 of 4 for October 20,
). Further, local community members cannot be filled into positions in which they cannot be
trained if no training plans are available (see NCR Number 9 of 19 for October 20, 2009
the site visit, the majority shareholder of Rukinga Ranching Company indicated that shares are available
to the local community should they choose to invest in the company, however no formal policy was in
place to clearly document how shares can be purchased and at what price (see OFI Number
Yes No N/A
See NCR Number 9 of 19 for October 20, 2009
None
See OFI Number 3 of 4 for October 20, 2009
for November 12, 2009
The project proponent has invited the community to acquire shares in Rukinga Ranching
Company. Likewise, on more than one occasion during the site visit, community members have
demonstrated an interest in acquiring shares. However, no clear policy regarding the requirements for
hired as a young man with no formal training to be a Wildlife Ranger in the Sanctuary, when his father
Ranger was a Kenyan, Ekiru Mirimuk from a different
region of Kenya, who had been brought in at the start of our Project because he had specific knowledge
and experience of how to set up and manage a Ranger force in the Kenyan bush, to patrol, perform anti
We appreciate the communities desire to fill management roles within the Company/ Project and are
cal employment and in the future at
such times as management roles become available we will certainly consider local candidates fist, but
xperience requirements as well.
is adequately addresses the finding OFI #3, and that this OFI should now be closed.
Show that people from the communities will be given an equal opportunity to fill all
if the job requirements are met. Project proponents
explain how employees will be selected for positions and where relevant, must indicate how local
community members, including women and other potentially underrepresented groups, will be given a
The revised PDD and interviews conducted with management during the site visit show that
people from the communities will be given an equal opportunity to fill all employment positions.
However, no formal and documented policy was in place to include local people for the communities
OFI Number 3 of 4 for October 20,
filled into positions in which they cannot be
NCR Number 9 of 19 for October 20, 2009). Lastly, during
the site visit, the majority shareholder of Rukinga Ranching Company indicated that shares are available
to the local community should they choose to invest in the company, however no formal policy was in
Number 1 of 1 for
ber 9 of 19 for October 20, 2009
The project proponent has invited the community to acquire shares in Rukinga Ranching
Company. Likewise, on more than one occasion during the site visit, community members have
ng the requirements for
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
purchase or availability of shares has been made by BenBo International (or Wildlife Works on behalf of
BenBo). Consider making and publicizing a policy regarding the transfer of shares to the local
community.
Proponent Response on December 9
under which BenBo International would be prepared to sell shares to the local shareholders or other
members of the local community would be a good idea, although we want to be clear
private company, and Ben Bo is certainly under no obligation to sell any of their shares. We made it
known to the Board of Directors of Rukinga Ranching Company in a Board Meeting held immediately
following the Special General Meeting on De
obtaining a clear statement of the terms and conditions under which Ben Bo would be prepared to sell
some or all of its shares to local community members. The issues are that there would have to be a fair
price set, based on the price that outside third parties have expressed a willingness to pay, and there
would have to be a minimum number of shares per transaction, to justify the overhead expense of
legally papering the transaction. Wildlife Works has un
analysis at the next Annual General Meeting of Shareholders in Q1 2010 or at an earlier date, at such
time as a third party has made a credible offer to purchase shares from Ben Bo.
In addition we will undertake to contact the other shareholders who are not residents of the local
community to see whether any of them would be willing to sell their shares to local community
members and if so under what terms and conditions. Again we will undertake to present at the
AGM any opportunities that arise for local community members to purchase shares from other
shareholders.
We consider this to be an appropriate and complete response to this OFI and ask that this finding be
closed.
Validator Response: NA
Indicator G4.5. Submit a list of all relevant laws and regulations covering worker’s rights in the host
country.
Describe how the project will inform workers about their rights. Provide assurance that the
meets or exceeds all applicable laws and/or regula
demonstrate how compliance is achieved.
Findings: A complete list of relevant l
revised PDD (see NCR Number 10 of 19 for October 20, 2009
employees of these laws in a statement within employee contracts. Evidence was also collected from
government audits indicating that the project proponents are currently in compliance with these laws.
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
30
purchase or availability of shares has been made by BenBo International (or Wildlife Works on behalf of
BenBo). Consider making and publicizing a policy regarding the transfer of shares to the local
December 9, 2009: We accept that a clear policy regarding the conditions
under which BenBo International would be prepared to sell shares to the local shareholders or other
members of the local community would be a good idea, although we want to be clear that this is a
private company, and Ben Bo is certainly under no obligation to sell any of their shares. We made it
known to the Board of Directors of Rukinga Ranching Company in a Board Meeting held immediately
following the Special General Meeting on December 9th 2009 that we would approach Ben Bo about
obtaining a clear statement of the terms and conditions under which Ben Bo would be prepared to sell
some or all of its shares to local community members. The issues are that there would have to be a fair
price set, based on the price that outside third parties have expressed a willingness to pay, and there
would have to be a minimum number of shares per transaction, to justify the overhead expense of
legally papering the transaction. Wildlife Works has undertaken to present the results of BenBo’s
analysis at the next Annual General Meeting of Shareholders in Q1 2010 or at an earlier date, at such
time as a third party has made a credible offer to purchase shares from Ben Bo.
to contact the other shareholders who are not residents of the local
community to see whether any of them would be willing to sell their shares to local community
members and if so under what terms and conditions. Again we will undertake to present at the
AGM any opportunities that arise for local community members to purchase shares from other
We consider this to be an appropriate and complete response to this OFI and ask that this finding be
Submit a list of all relevant laws and regulations covering worker’s rights in the host
Describe how the project will inform workers about their rights. Provide assurance that the
meets or exceeds all applicable laws and/or regulations covering worker rights and,
demonstrate how compliance is achieved.
A complete list of relevant laws and regulations covering worker’s rights is provide
NCR Number 10 of 19 for October 20, 2009). The project proponent notifies
employees of these laws in a statement within employee contracts. Evidence was also collected from
government audits indicating that the project proponents are currently in compliance with these laws.
Yes No N/A
purchase or availability of shares has been made by BenBo International (or Wildlife Works on behalf of
BenBo). Consider making and publicizing a policy regarding the transfer of shares to the local
We accept that a clear policy regarding the conditions
under which BenBo International would be prepared to sell shares to the local shareholders or other
that this is a
private company, and Ben Bo is certainly under no obligation to sell any of their shares. We made it
known to the Board of Directors of Rukinga Ranching Company in a Board Meeting held immediately
cember 9th 2009 that we would approach Ben Bo about
obtaining a clear statement of the terms and conditions under which Ben Bo would be prepared to sell
some or all of its shares to local community members. The issues are that there would have to be a fair
price set, based on the price that outside third parties have expressed a willingness to pay, and there
would have to be a minimum number of shares per transaction, to justify the overhead expense of
dertaken to present the results of BenBo’s
analysis at the next Annual General Meeting of Shareholders in Q1 2010 or at an earlier date, at such
to contact the other shareholders who are not residents of the local
community to see whether any of them would be willing to sell their shares to local community
members and if so under what terms and conditions. Again we will undertake to present at the next
AGM any opportunities that arise for local community members to purchase shares from other
We consider this to be an appropriate and complete response to this OFI and ask that this finding be
Submit a list of all relevant laws and regulations covering worker’s rights in the host
Describe how the project will inform workers about their rights. Provide assurance that the project
and, where relevant,
aws and regulations covering worker’s rights is provided in the
The project proponent notifies
employees of these laws in a statement within employee contracts. Evidence was also collected from
government audits indicating that the project proponents are currently in compliance with these laws.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 10 of 19 for October 20, 2009
Finding: The project proponent has provided assurance that the project meets or exceeds local laws,
evidenced by government audits. However, the project proponent must also submit a list of all relevant
laws and regulations covering workers' rights.
Proponent Response on October 24
relevant employment laws including the new Labour
described how we know we are in compliance of each of the relevant laws. We believe that submission
of the updated text from the PDD below provides a complete and appropriate response to this NCR and
that this NCR should now be closed.
Validator Response: The revised PDD now contains a list of all relevant laws.
New Information Requests:
Opportunities for Improvement:
Indicator G4.6. Comprehensively assess situations and occupations that pose a substantial risk to
worker safety. A plan must be in place to inform workers of risks and to explain how to minimize such
risks. Where worker safety cannot be guaranteed, project proponents mus
minimized using best work practices.
Findings: Upon review of the original PDD and conclusion of the site visit, there was in adequate
evidence to support conformance to this indicator (see
Upon response to a finding for this indicator, the
comprehensive assessment of situations that pose substantial risk to employees. These manuals also
explain how to minimize risks to worker’s safety.
Conformance: Yes
Non-Conformity Reports:
NCR Number 11 of 19 for October 20, 2009
Finding: Provide a comprehensive assessment of situations and occupations that pose substantial risk,
including those for greenhouse workers and rangers. Document a plan to inform workers of r
explain how to minimize risks to workers' safety.
Proponent Response on October 26
Factory, Greenhouse and Rangers carry complete safety sections indicating risks and providing advice
and training in how to minimize risks. Soap Factory Training manual is published book on soap making
called “The SoapMaker’s Companion” by Susa
with our own worker safety guide also provided to the Validators. For such a small company we are in
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
31
NCR Number 10 of 19 for October 20, 2009
The project proponent has provided assurance that the project meets or exceeds local laws,
evidenced by government audits. However, the project proponent must also submit a list of all relevant
nd regulations covering workers' rights.
October 24, 2009: We have amended Section G4.5 of the PDD to include ALL
relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly
described how we know we are in compliance of each of the relevant laws. We believe that submission
of the updated text from the PDD below provides a complete and appropriate response to this NCR and
NCR should now be closed.
The revised PDD now contains a list of all relevant laws.
None
None
Comprehensively assess situations and occupations that pose a substantial risk to
worker safety. A plan must be in place to inform workers of risks and to explain how to minimize such
risks. Where worker safety cannot be guaranteed, project proponents must show how the risks will be
minimized using best work practices.
Upon review of the original PDD and conclusion of the site visit, there was in adequate
evidence to support conformance to this indicator (see NCR Number 11 of 19 for October 20,
Upon response to a finding for this indicator, the supplied training manuals each provide a
comprehensive assessment of situations that pose substantial risk to employees. These manuals also
explain how to minimize risks to worker’s safety.
Yes No N/A
NCR Number 11 of 19 for October 20, 2009
Provide a comprehensive assessment of situations and occupations that pose substantial risk,
including those for greenhouse workers and rangers. Document a plan to inform workers of r
explain how to minimize risks to workers' safety.
October 26, 2009: Training Manuals now provided to Validator
Factory, Greenhouse and Rangers carry complete safety sections indicating risks and providing advice
and training in how to minimize risks. Soap Factory Training manual is published book on soap making
called “The SoapMaker’s Companion” by Susan Miller Cavitch, but we have supplemented this book
with our own worker safety guide also provided to the Validators. For such a small company we are in
The project proponent has provided assurance that the project meets or exceeds local laws,
evidenced by government audits. However, the project proponent must also submit a list of all relevant
We have amended Section G4.5 of the PDD to include ALL
Relations Act of 2007, and we have explicitly
described how we know we are in compliance of each of the relevant laws. We believe that submission
of the updated text from the PDD below provides a complete and appropriate response to this NCR and
Comprehensively assess situations and occupations that pose a substantial risk to
worker safety. A plan must be in place to inform workers of risks and to explain how to minimize such
t show how the risks will be
Upon review of the original PDD and conclusion of the site visit, there was in adequate
NCR Number 11 of 19 for October 20, 2009).
supplied training manuals each provide a
comprehensive assessment of situations that pose substantial risk to employees. These manuals also
Provide a comprehensive assessment of situations and occupations that pose substantial risk,
including those for greenhouse workers and rangers. Document a plan to inform workers of risks and
Training Manuals now provided to Validator for Sewing
Factory, Greenhouse and Rangers carry complete safety sections indicating risks and providing advice
and training in how to minimize risks. Soap Factory Training manual is published book on soap making
n Miller Cavitch, but we have supplemented this book
with our own worker safety guide also provided to the Validators. For such a small company we are in
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
rural Africa we consider these manuals and risks procedures to be more than adequate, and they have
allowed us to operate injury free for more than ten years. We ask that you close this NCR#11 at this
time.
Validator Response: The provided training manuals adequately address this finding.
New Information Requests: None
Opportunities for Improvement:
Indicator G4.7. Document the financial health of the implementing organization(s) to demonstrate that
financial resources budgeted will be adequate to implement the project.
Findings: The financial health of the implementing organization, Wildlife Works, is well documented in
the revised PDD and in a cash flow analysis (sees
flow analysis demonstrates that financial resources budgeted
project.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.2.5. G5 – Legal Status and Property Rights
The project must be based on a solid legal framework (e.g., appropriate contracts are in place) and the
project must satisfy applicable planning and regulatory requirements.
During the project design phase, the project proponents should communicate early on with relevant
local, regional and national authorities in order to allow adequate time to earn necessary approvals. The
project design should be sufficiently flexible to accommodate potential modifications that may arise as a
result of this process.
In the event of unresolved disputes over tenure or use rights to land or resources in the project zone,
the project should demonstrate how it will help to bring them to resolution so that there are no
unresolved disputes by the start of the project.
Indicators
Based on information about current property rights provided in
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
32
rural Africa we consider these manuals and risks procedures to be more than adequate, and they have
lowed us to operate injury free for more than ten years. We ask that you close this NCR#11 at this
The provided training manuals adequately address this finding.
None
None
Document the financial health of the implementing organization(s) to demonstrate that
financial resources budgeted will be adequate to implement the project.
The financial health of the implementing organization, Wildlife Works, is well documented in
the revised PDD and in a cash flow analysis (sees NCR Number 6 of 19 for October 20, 2009
flow analysis demonstrates that financial resources budgeted will be adequate to implement the
Yes No N/A
See NCR Number 6 of 19 for October 20, 2009
None
None
Legal Status and Property Rights
solid legal framework (e.g., appropriate contracts are in place) and the
project must satisfy applicable planning and regulatory requirements.
During the project design phase, the project proponents should communicate early on with relevant
l and national authorities in order to allow adequate time to earn necessary approvals. The
project design should be sufficiently flexible to accommodate potential modifications that may arise as a
es over tenure or use rights to land or resources in the project zone,
the project should demonstrate how it will help to bring them to resolution so that there are no
unresolved disputes by the start of the project.
urrent property rights provided in G1, the project proponents must:
rural Africa we consider these manuals and risks procedures to be more than adequate, and they have
lowed us to operate injury free for more than ten years. We ask that you close this NCR#11 at this
Document the financial health of the implementing organization(s) to demonstrate that
The financial health of the implementing organization, Wildlife Works, is well documented in
NCR Number 6 of 19 for October 20, 2009). The cash
will be adequate to implement the
NCR Number 6 of 19 for October 20, 2009
solid legal framework (e.g., appropriate contracts are in place) and the
During the project design phase, the project proponents should communicate early on with relevant
l and national authorities in order to allow adequate time to earn necessary approvals. The
project design should be sufficiently flexible to accommodate potential modifications that may arise as a
es over tenure or use rights to land or resources in the project zone,
the project should demonstrate how it will help to bring them to resolution so that there are no
, the project proponents must:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Indicator G5.1. Submit a list of all relevant national and local laws and regulations in the host country
and all applicable international treaties and agreements. Provide assurance that
with these and, where relevant, demonstrate how compliance is achieved.
Findings: The revised PDD contains a list of all relevant national and local laws and
no assurance was provided that the project will
October 20, 2009). Further, the project proponent did not document how compliance will be
demonstrated. In response to an initial finding for this indicator, the project proponent provided the
requested information.
Conformance:
Non-Conformity Reports:
New Information Requests:
NIR Number 3 of 5 for October 20, 2009
Finding: A list of applicable laws has been provided and compliance has been assured, however no
demonstration of compliance has been presented. The project proponent must explicitly demonstrate
how compliance is achieved where relevant.
Proponent Response on October 24
relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly
described how we know we are in compliance of each of the relevant laws. We believe that submission
of the updated PDD text below provides a complete and appropriate response to this NIR and that this
NIR should now be closed.
Validator Response: The amended PDD is adequate as i
comply with relevant national and local laws.
Opportunities for Improvement:
Indicator G5.2. Document that the project has approval from the appropriate authorities, including the
established formal and/or traditional authorities customarily required by the communities.
Findings: A signed conservation easement
authorities, including Rukinga Ranching Company. Interviews with the local authorities during the site
visit did not indicate any other approval is needed. Although the conservation easement clearly shows
that Rukinga Ranching Company has conveyed the climate and biological rights of
Wildlife Works, the project proponent,
Company gave their approval for the conservation easement. Based on guidance from CCBA, Wildlife
Works was required to confirm that inf
for November 12, 2009).
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
33
Submit a list of all relevant national and local laws and regulations in the host country
and all applicable international treaties and agreements. Provide assurance that the project will comply
with these and, where relevant, demonstrate how compliance is achieved.
The revised PDD contains a list of all relevant national and local laws and regulations. Initially,
no assurance was provided that the project will comply with these laws (see NIR Number 3 of 5 for
). Further, the project proponent did not document how compliance will be
demonstrated. In response to an initial finding for this indicator, the project proponent provided the
Yes No N/A
None
NIR Number 3 of 5 for October 20, 2009
A list of applicable laws has been provided and compliance has been assured, however no
demonstration of compliance has been presented. The project proponent must explicitly demonstrate
compliance is achieved where relevant.
October 24, 2009: We have amended Section G5.1 of the PDD to include ALL
relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly
are in compliance of each of the relevant laws. We believe that submission
of the updated PDD text below provides a complete and appropriate response to this NIR and that this
The amended PDD is adequate as it completely describes how the project will
comply with relevant national and local laws.
None
Document that the project has approval from the appropriate authorities, including the
or traditional authorities customarily required by the communities.
easement documents that the project has approval from the local
Ranching Company. Interviews with the local authorities during the site
visit did not indicate any other approval is needed. Although the conservation easement clearly shows
that Rukinga Ranching Company has conveyed the climate and biological rights of the project area to
Wildlife Works, the project proponent, it was unclear whether all shareholders of Rukinga Ranching
Company gave their approval for the conservation easement. Based on guidance from CCBA, Wildlife
Works was required to confirm that infact all shareholders support the project (see NCR Number
Submit a list of all relevant national and local laws and regulations in the host country
the project will comply
regulations. Initially,
NIR Number 3 of 5 for
). Further, the project proponent did not document how compliance will be
demonstrated. In response to an initial finding for this indicator, the project proponent provided the
A list of applicable laws has been provided and compliance has been assured, however no
demonstration of compliance has been presented. The project proponent must explicitly demonstrate
We have amended Section G5.1 of the PDD to include ALL
relevant employment laws including the new Labour Relations Act of 2007, and we have explicitly
are in compliance of each of the relevant laws. We believe that submission
of the updated PDD text below provides a complete and appropriate response to this NIR and that this
t completely describes how the project will
Document that the project has approval from the appropriate authorities, including the
or traditional authorities customarily required by the communities.
documents that the project has approval from the local
Ranching Company. Interviews with the local authorities during the site
visit did not indicate any other approval is needed. Although the conservation easement clearly shows
the project area to
it was unclear whether all shareholders of Rukinga Ranching
Company gave their approval for the conservation easement. Based on guidance from CCBA, Wildlife
NCR Number 1 of 1
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Conformance:
Non-Conformity Reports:
New Information Requests:
NIR Number 4 of 5 for October 20, 2009
Finding: The project proponent must provide a list of all shareholder owners whose rights the project
will affect. Please provide a copy of the signed conservation easement to document the free, prior,
informed and full consent of these shareholders for the project.
Proponent Response on October 24
time line of events leading to the unanimous approval by those Shareholders present at the February
13th 2009 AGM of Rukinga Ranching Company Ltd. to allow the Managing
project opportunity on Rukinga. We have included this text below, to avoid resending the entire PDD for
each finding response.
We have also provide you with a full list of all Shareholders currently known to the company (it is
possible that some of those Shareholders are deceased, and that family members are in the process of
acquiring Court papers granting them inheritance of the shares, but we will not be aware of this until
that process is complete and they present their proof
We have emailed you a copy of the presentation made to the Shareholders of Rukinga Ranching Co. Ltd
during the AGM of February 13th 2009 at which AGM they approved the pursuit of the Project, leading
to the signing of the Carbon Easement on February 15th 2009.
Finally we have provided you with a copy of the Carbon Easement signed between Rukinga
Company Ltd. and Wildlife Works, Inc. This Carbon Easement is also commercially sensitive, as it was
developed by Wildlife Works at significant expense, and we would ask the auditors and CCB NOT to post
this to the website.
We believe that as Rukinga is 100% of the land covered under the Project Area, and that it is Privately
owned by the Rukinga Ranching Company Ltd. that the information and documents provided above are
a complete response to the finding and therefore finding NIR #4 should be clo
Validator Response: The provided easement is adequate to satisfy this finding, however it is unclear
whether all shareholders of Rukinga Ranching Company support this easement (see
for November 12, 2009).
Opportunities for Improvement:
Indicator G5.3. Demonstrate with documented consultations and agreements that the project will not
encroach uninvited on private property, community property, or government property and has obtained
the free, prior, and informed consent of those whose rights will be affe
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
34
Yes No N/A
See NCR Number 1 of 1 for November 12, 2009
NIR Number 4 of 5 for October 20, 2009
proponent must provide a list of all shareholder owners whose rights the project
will affect. Please provide a copy of the signed conservation easement to document the free, prior,
informed and full consent of these shareholders for the project.
October 24, 2009: We have greatly expanded in the PDD in section G5.3 the
time line of events leading to the unanimous approval by those Shareholders present at the February
13th 2009 AGM of Rukinga Ranching Company Ltd. to allow the Managing Director to pursue the REDD
project opportunity on Rukinga. We have included this text below, to avoid resending the entire PDD for
We have also provide you with a full list of all Shareholders currently known to the company (it is
ossible that some of those Shareholders are deceased, and that family members are in the process of
acquiring Court papers granting them inheritance of the shares, but we will not be aware of this until
that process is complete and they present their proof of inheritance to the Company Secretary).
We have emailed you a copy of the presentation made to the Shareholders of Rukinga Ranching Co. Ltd
during the AGM of February 13th 2009 at which AGM they approved the pursuit of the Project, leading
g of the Carbon Easement on February 15th 2009.
Finally we have provided you with a copy of the Carbon Easement signed between Rukinga
Company Ltd. and Wildlife Works, Inc. This Carbon Easement is also commercially sensitive, as it was
developed by Wildlife Works at significant expense, and we would ask the auditors and CCB NOT to post
inga is 100% of the land covered under the Project Area, and that it is Privately
owned by the Rukinga Ranching Company Ltd. that the information and documents provided above are
a complete response to the finding and therefore finding NIR #4 should be closed.
The provided easement is adequate to satisfy this finding, however it is unclear
whether all shareholders of Rukinga Ranching Company support this easement (see NCR Number
None
Demonstrate with documented consultations and agreements that the project will not
encroach uninvited on private property, community property, or government property and has obtained
the free, prior, and informed consent of those whose rights will be affected by the project.
for November 12, 2009
proponent must provide a list of all shareholder owners whose rights the project
will affect. Please provide a copy of the signed conservation easement to document the free, prior,
We have greatly expanded in the PDD in section G5.3 the
time line of events leading to the unanimous approval by those Shareholders present at the February
Director to pursue the REDD
project opportunity on Rukinga. We have included this text below, to avoid resending the entire PDD for
We have also provide you with a full list of all Shareholders currently known to the company (it is
ossible that some of those Shareholders are deceased, and that family members are in the process of
acquiring Court papers granting them inheritance of the shares, but we will not be aware of this until
of inheritance to the Company Secretary).
We have emailed you a copy of the presentation made to the Shareholders of Rukinga Ranching Co. Ltd
during the AGM of February 13th 2009 at which AGM they approved the pursuit of the Project, leading
Finally we have provided you with a copy of the Carbon Easement signed between Rukinga Ranching
Company Ltd. and Wildlife Works, Inc. This Carbon Easement is also commercially sensitive, as it was
developed by Wildlife Works at significant expense, and we would ask the auditors and CCB NOT to post
inga is 100% of the land covered under the Project Area, and that it is Privately
owned by the Rukinga Ranching Company Ltd. that the information and documents provided above are
The provided easement is adequate to satisfy this finding, however it is unclear
NCR Number 1 of 1
Demonstrate with documented consultations and agreements that the project will not
encroach uninvited on private property, community property, or government property and has obtained
cted by the project.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Findings: The rights to the climate and biodiversity of the project area are owned by Wildlife Works and
were conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority
of shareholders affected this conveyance, it was initially unclear whether all shareholders supported the
transfer of their climate and biodiversity rights in the project area to Wildlife Works (see
of 1 for November 12, 2009). In response to a finding m
confirm the complete support of all Rukinga shareholders.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G5.4. Demonstrate that the project does not require the involuntary relocation of people or of
the activities important for the livelihoods and culture of the communities. If any relocation of
habitation or activities is undertaken within the terms of an agreeme
demonstrate that the agreement was made with the free, prior, and
concerned and includes provisions for just and fair compensation.
Findings: The project does not require the involuntary
project area as of the start date of the project.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator G5.5. Identify any illegal activities that could affect the project’s climate, community or
biodiversity impacts (e.g., logging) taking place in the project zone and descri
help to reduce these activities so that project benefits are not derived from illegal activities.
Findings: The two major illegal activities that could affect the project’s benefits are harvesting of
firewood and poaching. Both of these activities
in the project zone as a result of this project
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
35
The rights to the climate and biodiversity of the project area are owned by Wildlife Works and
were conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority
conveyance, it was initially unclear whether all shareholders supported the
transfer of their climate and biodiversity rights in the project area to Wildlife Works (see
). In response to a finding made by the validator, a special AGM was held to
confirm the complete support of all Rukinga shareholders.
Yes No N/A
See NCR Number 1 of 1 for November 12, 2009
None
None
Demonstrate that the project does not require the involuntary relocation of people or of
the activities important for the livelihoods and culture of the communities. If any relocation of
habitation or activities is undertaken within the terms of an agreement, the project proponents must
demonstrate that the agreement was made with the free, prior, and informed consent of those
concerned and includes provisions for just and fair compensation.
The project does not require the involuntary relocation of people as no people live in the
project area as of the start date of the project.
Yes No N/A
None
None
None
Identify any illegal activities that could affect the project’s climate, community or
impacts (e.g., logging) taking place in the project zone and describe how
reduce these activities so that project benefits are not derived from illegal activities.
The two major illegal activities that could affect the project’s benefits are harvesting of
firewood and poaching. Both of these activities and descriptions of how these activities will be reduced
in the project zone as a result of this project are identified in Section G5.5 of the PDD.
Yes No N/A
None
The rights to the climate and biodiversity of the project area are owned by Wildlife Works and
were conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority
conveyance, it was initially unclear whether all shareholders supported the
transfer of their climate and biodiversity rights in the project area to Wildlife Works (see NCR Number 1
tor, a special AGM was held to
for November 12, 2009
Demonstrate that the project does not require the involuntary relocation of people or of
the activities important for the livelihoods and culture of the communities. If any relocation of
nt, the project proponents must
informed consent of those
relocation of people as no people live in the
Identify any illegal activities that could affect the project’s climate, community or
be how the project will
reduce these activities so that project benefits are not derived from illegal activities.
The two major illegal activities that could affect the project’s benefits are harvesting of
and descriptions of how these activities will be reduced
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
New Information Requests:
Opportunities for Improvement:
Indicator G5.6. Demonstrate that the project proponents have clear, uncontested
rights, or provide legal documentation demonstrating that the project is und
carbon owners with their full consent. Where local or national conditi
carbon rights at the time of validation against the Standards, t
evidence that their ownership of carbon rights is likely to be establi
transactions concerning the project’s carbon assets.
Findings: The rights to the climate benefits of the project area
conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority of
shareholders affected this conveyance, it was initially unclear whether all shareholders supported the
transfer of their climate and biodiversity rights in the project area to Wildlife Works (see
of 1 for November 12, 2009). In response to a finding made by the validator, a special AGM was held to
confirm the complete support of all Rukinga shareholders. The e
finding clearly demonstrates that the project proponents have clear, legal and uncontested title to the
carbon rights.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.3. Climate Section
3.3.1. CL1 – Net Positive Climate Impacts
Concept
The project must generate net positive impacts on atmospheric concentrations of greenhouse gases
(GHGs) over the project lifetime from land use changes within the project boundaries.
Indicators
The project proponents must:
Indicator CL1.1. Estimate the net change in carbon stocks due to the project activities using the
methods of calculation, formulae and default values of the IPCC 2006 GL for AFOLU or using a more
robust and detailed methodology. The n
minus carbon stock changes without
must be based on clearly defined and defendable assumptions about how project activities will
GHG emissions or carbon stocks over the duration of the project or the project GHG accounting period.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
36
None
None
Demonstrate that the project proponents have clear, uncontested title to the carbon
provide legal documentation demonstrating that the project is undertaken on behalf of the
owners with their full consent. Where local or national conditions preclude clear title to the
carbon rights at the time of validation against the Standards, the project proponents must provide
evidence that their ownership of carbon rights is likely to be established before they enter into any
transactions concerning the project’s carbon assets.
The rights to the climate benefits of the project area are owned by Wildlife Works and were
conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority of
shareholders affected this conveyance, it was initially unclear whether all shareholders supported the
climate and biodiversity rights in the project area to Wildlife Works (see
). In response to a finding made by the validator, a special AGM was held to
confirm the complete support of all Rukinga shareholders. The evidence collected in response to this
finding clearly demonstrates that the project proponents have clear, legal and uncontested title to the
Yes No N/A
See NCR Number 1 of 1 for November 12, 2009
See NIR Number 4 of 5 for October 20, 2009
None
Net Positive Climate Impacts
The project must generate net positive impacts on atmospheric concentrations of greenhouse gases
(GHGs) over the project lifetime from land use changes within the project boundaries.
Estimate the net change in carbon stocks due to the project activities using the
methods of calculation, formulae and default values of the IPCC 2006 GL for AFOLU or using a more
robust and detailed methodology. The net change is equal to carbon stock changes
without the project (the latter having been estimated in
must be based on clearly defined and defendable assumptions about how project activities will
GHG emissions or carbon stocks over the duration of the project or the project GHG accounting period.
title to the carbon
ertaken on behalf of the
ons preclude clear title to the
project proponents must provide
shed before they enter into any
are owned by Wildlife Works and were
conveyed in a conservation easement from Rukinga Ranching Company. Although a legal majority of
shareholders affected this conveyance, it was initially unclear whether all shareholders supported the
climate and biodiversity rights in the project area to Wildlife Works (see NCR Number 1
). In response to a finding made by the validator, a special AGM was held to
vidence collected in response to this
finding clearly demonstrates that the project proponents have clear, legal and uncontested title to the
for November 12, 2009
The project must generate net positive impacts on atmospheric concentrations of greenhouse gases
Estimate the net change in carbon stocks due to the project activities using the
methods of calculation, formulae and default values of the IPCC 2006 GL for AFOLU or using a more
et change is equal to carbon stock changes with the project
the project (the latter having been estimated in G2). This estimate
must be based on clearly defined and defendable assumptions about how project activities will alter
GHG emissions or carbon stocks over the duration of the project or the project GHG accounting period.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Findings: The estimated net change in carbon stocks
using an IPCC Tier 3 methodology and an
documented in Sections G1.4, G2.3 and CL1.1.
For current carbon stocks assumed to remain constant or increase over
project activities, diameter measurements,
the aboveground biomass. Belowground biomass is estimated using ratios of above
relative biomass from the IPCC guidance document. The allometric equations for above ground biomass
were parameterized using a purposive sample within common species groups. The sample appeared to
be representative of the entire project area. The allometric equations for aboveground biomass were
not cross-validated for over fitting or selected using an
allometric equations available in the literature for this region of the continent, the constructed
equations seem adequate.
Soil organic carbon was estimated using a simple random sample of soil cores a
This method for estimating soil carb
soil organic pool will remain constant throughout the life of the project, which is a reasonable
assumption.
Under the ‘without project’ reference scenario
population growth is assumed to be linear in time. The latter of these assumptions is probably false (see
OFI Number 1 of 4 for October 20, 2009
conservative based on evidence from the site visit.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CL1.2. Estimate the net change in the emissions of non
N2O in the with and without project scenarios if those gases are likely to account for more than a 5%
increase or de crease (in terms of CO2
removals over each monitoring period.
Findings: The non-CO2 GHG emissions in the
account for more than a 5% increase or de
removals over each monitoring period
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
37
The estimated net change in carbon stocks due to the project activities were estimated in part
using an IPCC Tier 3 methodology and an analysis of local deforestation. These procedures are
documented in Sections G1.4, G2.3 and CL1.1.
assumed to remain constant or increase over the lifetime of the project
project activities, diameter measurements, stem counts and allometric equations are used to estimate
the aboveground biomass. Belowground biomass is estimated using ratios of above
relative biomass from the IPCC guidance document. The allometric equations for above ground biomass
were parameterized using a purposive sample within common species groups. The sample appeared to
be representative of the entire project area. The allometric equations for aboveground biomass were
validated for over fitting or selected using any statistical criteria. Given the limited number of
allometric equations available in the literature for this region of the continent, the constructed
Soil organic carbon was estimated using a simple random sample of soil cores analyzed by a third party.
This method for estimating soil carbon appears to be adequate. The project proponent assumes that the
soil organic pool will remain constant throughout the life of the project, which is a reasonable
‘without project’ reference scenario, the rate is assumed to linear in population size and
population growth is assumed to be linear in time. The latter of these assumptions is probably false (see
OFI Number 1 of 4 for October 20, 2009), however the overall estimated deforestation rate is probably
conservative based on evidence from the site visit.
Yes No N/A
None
None
See OFI Number 1 of 4 for October 20, 2009
Estimate the net change in the emissions of non-CO2 GHG emissions such as CH4 and
project scenarios if those gases are likely to account for more than a 5%
increase or de crease (in terms of CO2-equivalent) of the project’s overall GHG emissions reductions or
removals over each monitoring period.
CO2 GHG emissions in the with and without project scenarios are
r more than a 5% increase or decrease of the project’s overall GHG emissions
removals over each monitoring period (see NCR Number 12 of 19 for October 20, 2009
Yes No N/A
were estimated in part
analysis of local deforestation. These procedures are
of the project due to
stem counts and allometric equations are used to estimate
the aboveground biomass. Belowground biomass is estimated using ratios of above-to-belowground
relative biomass from the IPCC guidance document. The allometric equations for above ground biomass
were parameterized using a purposive sample within common species groups. The sample appeared to
be representative of the entire project area. The allometric equations for aboveground biomass were
y statistical criteria. Given the limited number of
allometric equations available in the literature for this region of the continent, the constructed
nalyzed by a third party.
The project proponent assumes that the
soil organic pool will remain constant throughout the life of the project, which is a reasonable
he rate is assumed to linear in population size and
population growth is assumed to be linear in time. The latter of these assumptions is probably false (see
all estimated deforestation rate is probably
CO2 GHG emissions such as CH4 and
project scenarios if those gases are likely to account for more than a 5%
erall GHG emissions reductions or
project scenarios are not likely to
crease of the project’s overall GHG emissions reductions or
NCR Number 12 of 19 for October 20, 2009).
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 12 of 19 for October 20, 2009
Finding: Based on anecdotal evidence obtained during the site visit, the GHG emissions
gases is likely less than 5% of the project's overall emissions reductions (within the project area and
zone). Also based on anecdotal evidence, the net climate impact of the project is likely positive.
However, the project proponent must esti
those emissions resulting from project activities. Also, demonstrate the net climate impact is positive
considering the estimated reductions, GHG emissions and unmitigated leakage (GL2.3).
Proponent Response on November 1
Project Activities both within the Project Area and the Project Zone to Section CL1.3 of the PDD text of
which is below, which encompasses our more detailed response to
categorically that our project has an overwhelmingly positive emissions reduction impact. We have
updated the leakage, and leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under
NCR#13, to support our argument for no unmitigated leakage, and we consider this to be a full and
complete response to this finding and ask that you close NCR#12.
Validator Response: The proponent’s response is adequate and shows the non
are not likely to account for more than a 5% increase or decrease of the project’s overall GHG emissions
reductions or removals over each monitoring period
there is in fact an overwhelming positive climate impact to the project.
New Information Requests:
Opportunities for Improvement:
Indicator CL1.3. Estimate any other GHG emissions resulting from project activities. Emissions sources
include, but are not limited to, emissions from biomass burning during site preparation, emissions from
fossil fuel combustion, direct emissions from the use of syntheti
decomposition of N-fixing species.
Findings: Other GHG emissions resulting from project activities
CL1.2 of the revised PDD (see NCR Number 12 of 19 for October 20, 2009
emissions listed in the PDD and the estimated emissions for these sources seem complete and accurate.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
38
NCR Number 12 of 19 for October 20, 2009
Based on anecdotal evidence obtained during the site visit, the GHG emissions
gases is likely less than 5% of the project's overall emissions reductions (within the project area and
zone). Also based on anecdotal evidence, the net climate impact of the project is likely positive.
However, the project proponent must estimate the net change in these non-CO2 emissions, including
those emissions resulting from project activities. Also, demonstrate the net climate impact is positive
considering the estimated reductions, GHG emissions and unmitigated leakage (GL2.3).
November 1, 2009: We have added a full carbon footprint analysis for all
Project Activities both within the Project Area and the Project Zone to Section CL1.3 of the PDD text of
which is below, which encompasses our more detailed response to CL2.4, and demonstrates
categorically that our project has an overwhelmingly positive emissions reduction impact. We have
updated the leakage, and leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under
t for no unmitigated leakage, and we consider this to be a full and
complete response to this finding and ask that you close NCR#12.
: The proponent’s response is adequate and shows the non-CO2 GHG emissions in
for more than a 5% increase or decrease of the project’s overall GHG emissions
reductions or removals over each monitoring period. The addition of unmitigated leakage shows that
there is in fact an overwhelming positive climate impact to the project.
None
None
Estimate any other GHG emissions resulting from project activities. Emissions sources
include, but are not limited to, emissions from biomass burning during site preparation, emissions from
fossil fuel combustion, direct emissions from the use of synthetic fertilizers, and emissions from the
GHG emissions resulting from project activities are estimated in Section
NCR Number 12 of 19 for October 20, 2009). The types of sour
emissions listed in the PDD and the estimated emissions for these sources seem complete and accurate.
Yes No N/A
See NCR Number 12 of 19 for October 20, 2009
None
None
Based on anecdotal evidence obtained during the site visit, the GHG emissions of non-CO2
gases is likely less than 5% of the project's overall emissions reductions (within the project area and
zone). Also based on anecdotal evidence, the net climate impact of the project is likely positive.
CO2 emissions, including
those emissions resulting from project activities. Also, demonstrate the net climate impact is positive
considering the estimated reductions, GHG emissions and unmitigated leakage (GL2.3).
We have added a full carbon footprint analysis for all
Project Activities both within the Project Area and the Project Zone to Section CL1.3 of the PDD text of
CL2.4, and demonstrates
categorically that our project has an overwhelmingly positive emissions reduction impact. We have
updated the leakage, and leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under
t for no unmitigated leakage, and we consider this to be a full and
CO2 GHG emissions in
for more than a 5% increase or decrease of the project’s overall GHG emissions
. The addition of unmitigated leakage shows that
Estimate any other GHG emissions resulting from project activities. Emissions sources
include, but are not limited to, emissions from biomass burning during site preparation, emissions from
c fertilizers, and emissions from the
are estimated in Section
). The types of sources of
emissions listed in the PDD and the estimated emissions for these sources seem complete and accurate.
NCR Number 12 of 19 for October 20, 2009
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Indicator CL1.4. Demonstrate that the net climate impact of the project is positive. The net climate
impact of the project is the net change in carbon stocks plus net change in non
appropriate minus any other GHG emissions resulting from p
related unmitigated negative offsite climate impacts (see CL2.3).
Findings: Based on the evidence provided in the revised PDD and responses to findings (see
Numbers 12 and 13 of 19 for October 20, 2009
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CL1.5. Specify how double counting of GHG emissions reductions or removals will be avoided,
particularly for offsets sold on the voluntary market and generated in a country with an emissions cap.
Findings: GHG emissions reductions and removals cannot be doubl
have an emissions cap.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.3.2. CL2 – Offsite Climate Impacts (‘Leakage’)
Concept
The project proponents must quantify
project area and are caused by project activities (commonly referred to as ‘leakage’).
Indicators
The project proponents must:
Indicator CL2.1. Determine the types of leakage that are expected and estimate potential offsite
increases in GHGs (increases in emissions or decreases in sequestration) due to project activities. Where
relevant, define and justify where leakage is most likely to take pl
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
39
Demonstrate that the net climate impact of the project is positive. The net climate
impact of the project is the net change in carbon stocks plus net change in non-
appropriate minus any other GHG emissions resulting from project activities minus any likely project
related unmitigated negative offsite climate impacts (see CL2.3).
Based on the evidence provided in the revised PDD and responses to findings (see
for October 20, 2009), the project has a net positive climate impact.
Yes No N/A
See NCR Number 12 of 19 for October 20, 2009
See NCR Number 13 of 19 for October 20, 2009
None
None
Specify how double counting of GHG emissions reductions or removals will be avoided,
particularly for offsets sold on the voluntary market and generated in a country with an emissions cap.
GHG emissions reductions and removals cannot be double counted because Kenya does not
Yes No N/A
None
None
None
Offsite Climate Impacts (‘Leakage’)
The project proponents must quantify and mitigate increased GHG emissions that occur beyond the
project area and are caused by project activities (commonly referred to as ‘leakage’).
Determine the types of leakage that are expected and estimate potential offsite
increases in GHGs (increases in emissions or decreases in sequestration) due to project activities. Where
relevant, define and justify where leakage is most likely to take place.
Demonstrate that the net climate impact of the project is positive. The net climate
-CO2 GHGs where
roject activities minus any likely project-
Based on the evidence provided in the revised PDD and responses to findings (see NCR
project has a net positive climate impact.
NCR Number 12 of 19 for October 20, 2009
NCR Number 13 of 19 for October 20, 2009
Specify how double counting of GHG emissions reductions or removals will be avoided,
particularly for offsets sold on the voluntary market and generated in a country with an emissions cap.
e counted because Kenya does not
and mitigate increased GHG emissions that occur beyond the
Determine the types of leakage that are expected and estimate potential offsite
increases in GHGs (increases in emissions or decreases in sequestration) due to project activities. Where
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Findings: Two types of leakage are identified in the PDD: activity shifting and market effects leakage.
There are no other apparent types of leakage for the project. Originally, the PDD did not
justify where leakage is most likely to ta
response to an initial finding, the PDD was revised to include the
(other unprotected ranches in the project zone) and market effects leakage (the commerce o
in the local communities).
Conformance:
Non-Conformity Reports:
NCR Number 13 of 19 for October 20, 2009
Finding: The PDD contains a description of the communities around the project area and not types of
leakage or where leakage is likely to take place. During the site visit, the project proponent determined
there are no expected types of leakage in the project zone. The project proponent must provide a
detailed description of how they determined there are no expected ty
due to project activities, primarily the exclusion of people from the project area to make charcoal and
practice agriculture. Provide this description in sufficient detail and refer to specific areas where
leakage may or may not take place within the project zone.
Proponent Response on November 1
Sections CL2.1, CL2.2, CL2.3 and CL1.4 and the text is included below. We have updated the leakage, and
leakage mitigation descriptions in Sections CL2.1, CL2.2, CL2.3 covered under NCR#13, to support our
argument for no unmitigated leakage, and we consider this to be a full and complete response to this
finding and ask that you close NCR#13.
Validator Response: Based on evidence collected during the site visit, there is potential for market
effects in the commerce of charcoal originating from the project area. Although charcoal production
from private land is illegal, it is none
determining the overall net climate benefit of the project.
New Information Requests:
Opportunities for Improvement:
Indicator CL2.2. Document how any leakage will be mitigated and estimate the extent to which such
impacts will be reduced by these mitigation activities.
Findings: With respect to the activity shifting leakage, the project aims to protect other ranches in the
project zone from agricultural conversion.
With respect to market effects leakage, the project proponent claims that as a result of the project there
will be no commerce in firewood as historicall
household use. This is contradictory to the evidence collected during the site visit. The sale of charcoal
was observed outside the project area indicating commerce in firewood (via charcoal produc
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
40
Two types of leakage are identified in the PDD: activity shifting and market effects leakage.
There are no other apparent types of leakage for the project. Originally, the PDD did not
justify where leakage is most likely to take place (see NCR Number 13 of 19 for October 20, 2009
response to an initial finding, the PDD was revised to include the location of activity shifting leakage
(other unprotected ranches in the project zone) and market effects leakage (the commerce o
Yes No N/A
NCR Number 13 of 19 for October 20, 2009
The PDD contains a description of the communities around the project area and not types of
leakage is likely to take place. During the site visit, the project proponent determined
there are no expected types of leakage in the project zone. The project proponent must provide a
detailed description of how they determined there are no expected types of leakage in the project zone
due to project activities, primarily the exclusion of people from the project area to make charcoal and
practice agriculture. Provide this description in sufficient detail and refer to specific areas where
may not take place within the project zone.
November 1, 2009: We have added significantly to the PDD content of
Sections CL2.1, CL2.2, CL2.3 and CL1.4 and the text is included below. We have updated the leakage, and
on descriptions in Sections CL2.1, CL2.2, CL2.3 covered under NCR#13, to support our
argument for no unmitigated leakage, and we consider this to be a full and complete response to this
finding and ask that you close NCR#13.
vidence collected during the site visit, there is potential for market
effects in the commerce of charcoal originating from the project area. Although charcoal production
from private land is illegal, it is none-the-less a form of leakage and should be estimated when
determining the overall net climate benefit of the project.
None
None
Document how any leakage will be mitigated and estimate the extent to which such
impacts will be reduced by these mitigation activities.
With respect to the activity shifting leakage, the project aims to protect other ranches in the
from agricultural conversion. This activity will effectively mitigate activity shifting leakage.
With respect to market effects leakage, the project proponent claims that as a result of the project there
will be no commerce in firewood as historically firewood from within the project area was consumed for
household use. This is contradictory to the evidence collected during the site visit. The sale of charcoal
was observed outside the project area indicating commerce in firewood (via charcoal produc
Two types of leakage are identified in the PDD: activity shifting and market effects leakage.
There are no other apparent types of leakage for the project. Originally, the PDD did not define and
NCR Number 13 of 19 for October 20, 2009). In
location of activity shifting leakage
(other unprotected ranches in the project zone) and market effects leakage (the commerce of fuel wood
The PDD contains a description of the communities around the project area and not types of
leakage is likely to take place. During the site visit, the project proponent determined
there are no expected types of leakage in the project zone. The project proponent must provide a
pes of leakage in the project zone
due to project activities, primarily the exclusion of people from the project area to make charcoal and
practice agriculture. Provide this description in sufficient detail and refer to specific areas where
We have added significantly to the PDD content of
Sections CL2.1, CL2.2, CL2.3 and CL1.4 and the text is included below. We have updated the leakage, and
on descriptions in Sections CL2.1, CL2.2, CL2.3 covered under NCR#13, to support our
argument for no unmitigated leakage, and we consider this to be a full and complete response to this
vidence collected during the site visit, there is potential for market
effects in the commerce of charcoal originating from the project area. Although charcoal production
timated when
Document how any leakage will be mitigated and estimate the extent to which such
With respect to the activity shifting leakage, the project aims to protect other ranches in the
This activity will effectively mitigate activity shifting leakage.
With respect to market effects leakage, the project proponent claims that as a result of the project there
y firewood from within the project area was consumed for
household use. This is contradictory to the evidence collected during the site visit. The sale of charcoal
was observed outside the project area indicating commerce in firewood (via charcoal production). The
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
revised PDD does not contain any mitigation strategies for the market effects of charcoal sales
Number 13 of 19 for October 20, 2009
shifting leakage can be applied to the leaka
generally a local activity, the protection of adjacent ranches in the project zone will suffice to mitigate
the market effects of firewood sales.
Despite the anticipated protection of adjacent ranche
that no charcoal production will occur on these ranches as a result of project activities. Based on the
evidence observed during the site visit, charcoal production on adjacent ranches has likely already
occurred since the project start date of January 2006. As of 2009, the adjacent ranches have not been
protected as an activity under this project. Therefore, leakage as a result of charcoal production should
have been estimated. However, since the amoun
ranches is expected to be relatively minor until the
ranches, non-conformance to this indicator is immaterial as this leakage will not affect the posit
climate benefits of this project.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CL2.3. Subtract any likely project
the climate benefits being claimed by the project and demonstrate that this has been included in the
evaluation of net climate impact of the project (as calculated in
Findings: Given the estimated positive benefits of the project and the anticipated but unestimated
leakage due to minor fuelwood consumption
climate impact of the project is positive.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CL2.4. Non-CO2 gases must be includ
increase or decrease (in terms of CO2
overall off-site GHG emissions reductions or removals over each monitoring period.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
41
revised PDD does not contain any mitigation strategies for the market effects of charcoal sales
Number 13 of 19 for October 20, 2009). However to some degree, the same argument as activity
shifting leakage can be applied to the leakage due to market effects. Since charcoal production is
generally a local activity, the protection of adjacent ranches in the project zone will suffice to mitigate
the market effects of firewood sales.
protection of adjacent ranches in the project zone, it is unreasonable to think
that no charcoal production will occur on these ranches as a result of project activities. Based on the
during the site visit, charcoal production on adjacent ranches has likely already
occurred since the project start date of January 2006. As of 2009, the adjacent ranches have not been
protected as an activity under this project. Therefore, leakage as a result of charcoal production should
have been estimated. However, since the amount of leakage due to fuelwood production on adjacent
ranches is expected to be relatively minor until the initiation of project activities to protect adjacent
conformance to this indicator is immaterial as this leakage will not affect the posit
Yes No N/A
See NCR Number 13 of 19 for October 20, 2009
None
None
Subtract any likely project-related unmitigated negative offsite climate impacts from
the climate benefits being claimed by the project and demonstrate that this has been included in the
evaluation of net climate impact of the project (as calculated in CL1.4).
estimated positive benefits of the project and the anticipated but unestimated
leakage due to minor fuelwood consumption (see NCR Number 13 of 19 for October 20, 2009
climate impact of the project is positive.
Yes No N/A
See NCR Number 13 of 19 for October 20, 2009
None
None
CO2 gases must be included if they are likely to account for more than a 5%
increase or decrease (in terms of CO2-equivalent) of the net change calculations (above) of the project’s
site GHG emissions reductions or removals over each monitoring period.
revised PDD does not contain any mitigation strategies for the market effects of charcoal sales (see NCR
. However to some degree, the same argument as activity
ge due to market effects. Since charcoal production is
generally a local activity, the protection of adjacent ranches in the project zone will suffice to mitigate
s in the project zone, it is unreasonable to think
that no charcoal production will occur on these ranches as a result of project activities. Based on the
during the site visit, charcoal production on adjacent ranches has likely already
occurred since the project start date of January 2006. As of 2009, the adjacent ranches have not been
protected as an activity under this project. Therefore, leakage as a result of charcoal production should
t of leakage due to fuelwood production on adjacent
of project activities to protect adjacent
conformance to this indicator is immaterial as this leakage will not affect the positive
f 19 for October 20, 2009
related unmitigated negative offsite climate impacts from
the climate benefits being claimed by the project and demonstrate that this has been included in the
estimated positive benefits of the project and the anticipated but unestimated
NCR Number 13 of 19 for October 20, 2009), the net
NCR Number 13 of 19 for October 20, 2009
ed if they are likely to account for more than a 5%
equivalent) of the net change calculations (above) of the project’s
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Findings: Non-CO2 gases have been demonstrated to account for less than 5% of the net change in the
project’s overall off-site GHG emissions reduction or removals (see
20, 2009).
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.3.3. CL3 – Climate Impact Monitoring
Concept
Before a project begins, the project proponents must have an initial monitoring plan in place to quantify
and document changes (within and outside the project boundaries) in project
project emissions, and non-CO2 GHG emissions if appropriate. The monitoring plan must identify the
types of measurements, the sampling method, and the frequency of measurement.
Since developing a full monitoring plan can be costly, it is accepted that some of the plan details may
not be fully defined at the design stage, when projects are being validated against the Standards. This is
acceptable as long as there is an explicit com
Indicators
The project proponents must:
Indicator CL3.1. Develop an initial plan for selecting carbon pools and non
and determine the frequency of monitoring. Potential pools in
wood, belowground biomass, wood products, soil carbon and peat. Pools to monitor must include any
pools expected to decrease as a result of project activities, including those in the region outside the
project boundaries resulting from all types of leakage identified in CL2. A plan must be in place to
continue leakage monitoring for at least five years after all activity displacement or other leakage
causing activity has taken place. Individual GHG sources may be cons
have to be accounted for if together
emissions amount to less than 5% of the total CO2
CO2 gases must be included if they are likely to account for more than 5% (in terms of CO2
of the project’s overall GHG impact over each monitoring period. Direct field measurements using
scientifically robust sampling must be used to measure more significant elements
stocks. Other data must be suitable to the project site and specific forest type.
Findings: An initial monitoring plan has been established in Section CL3.1 of the revised PDD. Originally,
the PDD lacked information about the fr
20, 2009), however was later amended to include this information.
Conformance:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
42
CO2 gases have been demonstrated to account for less than 5% of the net change in the
site GHG emissions reduction or removals (see NCR Number 12 of 19 for October
Yes No N/A
See NCR Number 12 of 19 for October 20, 2009
None
None
Climate Impact Monitoring
Before a project begins, the project proponents must have an initial monitoring plan in place to quantify
(within and outside the project boundaries) in project-related carbon pools,
CO2 GHG emissions if appropriate. The monitoring plan must identify the
types of measurements, the sampling method, and the frequency of measurement.
ince developing a full monitoring plan can be costly, it is accepted that some of the plan details may
not be fully defined at the design stage, when projects are being validated against the Standards. This is
acceptable as long as there is an explicit commitment to develop and implement a monitoring plan.
Develop an initial plan for selecting carbon pools and non-CO2 GHGs to be monitored,
and determine the frequency of monitoring. Potential pools include aboveground biomass, litter, dead
wood, belowground biomass, wood products, soil carbon and peat. Pools to monitor must include any
pools expected to decrease as a result of project activities, including those in the region outside the
ries resulting from all types of leakage identified in CL2. A plan must be in place to
continue leakage monitoring for at least five years after all activity displacement or other leakage
causing activity has taken place. Individual GHG sources may be considered ‘insignificant’ and do not
together such omitted decreases in carbon pools and increases in GHG
emissions amount to less than 5% of the total CO2-equivalent benefits generated by the project. Non
ed if they are likely to account for more than 5% (in terms of CO2
of the project’s overall GHG impact over each monitoring period. Direct field measurements using
scientifically robust sampling must be used to measure more significant elements of the project’s carbon
stocks. Other data must be suitable to the project site and specific forest type.
An initial monitoring plan has been established in Section CL3.1 of the revised PDD. Originally,
the PDD lacked information about the frequency of monitoring (see NCR Number 14 of 19 for October
), however was later amended to include this information.
Yes No N/A
CO2 gases have been demonstrated to account for less than 5% of the net change in the
NCR Number 12 of 19 for October
ober 20, 2009
Before a project begins, the project proponents must have an initial monitoring plan in place to quantify
related carbon pools,
CO2 GHG emissions if appropriate. The monitoring plan must identify the
ince developing a full monitoring plan can be costly, it is accepted that some of the plan details may
not be fully defined at the design stage, when projects are being validated against the Standards. This is
mitment to develop and implement a monitoring plan.
CO2 GHGs to be monitored,
clude aboveground biomass, litter, dead
wood, belowground biomass, wood products, soil carbon and peat. Pools to monitor must include any
pools expected to decrease as a result of project activities, including those in the region outside the
ries resulting from all types of leakage identified in CL2. A plan must be in place to
continue leakage monitoring for at least five years after all activity displacement or other leakage
idered ‘insignificant’ and do not
such omitted decreases in carbon pools and increases in GHG
equivalent benefits generated by the project. Non-
ed if they are likely to account for more than 5% (in terms of CO2-equivalent)
of the project’s overall GHG impact over each monitoring period. Direct field measurements using
of the project’s carbon
An initial monitoring plan has been established in Section CL3.1 of the revised PDD. Originally,
NCR Number 14 of 19 for October
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Non-Conformity Reports:
NCR Number 14 of 19 for October 20, 2009
Finding: The project proponent must specify the frequency of monitoring.
Proponent Response on October 30
text below, to provide specific frequencies of monitoring. We believe that this new information provided
to the Validator is a more than adequate response to your finding and meets the Standard and w
that you consider this finding NCR#14 closed.
Validator Response: The revised PD is adequate.
New Information Requests:
Opportunities for Improvement:
Indicator CL3.2. Commit to developing a full monitoring plan within six months of
or within twelve months of validation against the Standards and to disseminate this plan and the results
of monitoring, ensuring that they are made publicly available on the internet and are communicated to
the communities and other stakeholders.
Findings: The project proponent has committed to developing a full monitoring plan within twelve
months of the validation.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.4. Community Section
3.4.1. CM1 – Net Positive Community Impacts
Concept
The project must generate net positive impacts on the social and economic well
and ensure that costs and benefits are equitably shared among community members and constituent
groups during the project lifetime.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
43
14 of 19 for October 20, 2009
The project proponent must specify the frequency of monitoring.
October 30, 2009: We have revised sections CL3.1 of the PDD to include the
text below, to provide specific frequencies of monitoring. We believe that this new information provided
to the Validator is a more than adequate response to your finding and meets the Standard and w
that you consider this finding NCR#14 closed.
revised PD is adequate.
None
None
Commit to developing a full monitoring plan within six months of the project start date
or within twelve months of validation against the Standards and to disseminate this plan and the results
of monitoring, ensuring that they are made publicly available on the internet and are communicated to
stakeholders.
The project proponent has committed to developing a full monitoring plan within twelve
Yes No N/A
None
None
None
Net Positive Community Impacts
The project must generate net positive impacts on the social and economic well-being of communities
benefits are equitably shared among community members and constituent
We have revised sections CL3.1 of the PDD to include the
text below, to provide specific frequencies of monitoring. We believe that this new information provided
to the Validator is a more than adequate response to your finding and meets the Standard and we ask
the project start date
or within twelve months of validation against the Standards and to disseminate this plan and the results
of monitoring, ensuring that they are made publicly available on the internet and are communicated to
The project proponent has committed to developing a full monitoring plan within twelve
being of communities
benefits are equitably shared among community members and constituent
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Projects must maintain or enhance the High Conservation Values (identified in
that are of particular importance to the commun
Indicators
The project proponents must:
Indicator CM1.1. Use appropriate methodologies to estimate the impacts on communities, including all
constituent socio-economic or cultural groups such as indigenous peoples (defined in
planned project activities. A credible estimate of impacts must include changes in community well
due to project activities and an evaluation of the impacts by the affected groups. This estimate must be
based on clearly defined and defenda
economic well-being, including potential impacts of changes in natural resources and ecosystem services
identified as important by the communities (including water and soil resources), over
project. The ‘with project’ scenario must then be compared with the ‘without project’ scenario of social
and economic well-being in the absence of the project (completed in
community benefit) must be positive for all community groups.
Findings: Wildlife Works carbon offset project’s PDD has details of the net positive impact that the
project will have on the local community. A thorough scrutiny and interviews with the local community
supports such sentiments presented in the PDD even in its current operational status and organisation.
Wildlife Works, the community confirmed, gives back quite substantially.
Wildlife Works currently offers employment to the local community at their Export Processing Zo
(EPZ) organic sewing factory. It also offers other employments opportunities to the locals as house
helps, night guards, game rangers, drivers, office management staff and mechanics
with the community the net benefits. All employme
always fair considerations and merits are the guiding principal in recruitments.
All these employment opportunities empower the local community members concern
appropriate skills that can as well
comparative advantages over other communities in the project zone and purchasing powers leading to
improved living standards.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CM1.2. Demonstrate that no High Conservation Values identified in
negatively affected by the project.
Findings: The project area links two very important conservation areas
National Parks. It is therefore a migratory corridor whose presence helps the wildlife from both parks to
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
44
Projects must maintain or enhance the High Conservation Values (identified in G1) in the project zone
that are of particular importance to the communities’ well-being.
Use appropriate methodologies to estimate the impacts on communities, including all
economic or cultural groups such as indigenous peoples (defined in G1
planned project activities. A credible estimate of impacts must include changes in community well
due to project activities and an evaluation of the impacts by the affected groups. This estimate must be
based on clearly defined and defendable assumptions about how project activities will alter social and
being, including potential impacts of changes in natural resources and ecosystem services
identified as important by the communities (including water and soil resources), over the duration of the
project. The ‘with project’ scenario must then be compared with the ‘without project’ scenario of social
being in the absence of the project (completed in G2). The difference (i.e., the
tive for all community groups.
Wildlife Works carbon offset project’s PDD has details of the net positive impact that the
project will have on the local community. A thorough scrutiny and interviews with the local community
ments presented in the PDD even in its current operational status and organisation.
Wildlife Works, the community confirmed, gives back quite substantially.
Wildlife Works currently offers employment to the local community at their Export Processing Zo
(EPZ) organic sewing factory. It also offers other employments opportunities to the locals as house
helps, night guards, game rangers, drivers, office management staff and mechanics-
with the community the net benefits. All employment opportunities are indiscriminate of gender and
always fair considerations and merits are the guiding principal in recruitments.
All these employment opportunities empower the local community members concern
appropriate skills that can as well be applied elsewhere, monthly cash flows which give them some
comparative advantages over other communities in the project zone and purchasing powers leading to
Yes No N/A
None
None
None
Demonstrate that no High Conservation Values identified in G1.8.4
The project area links two very important conservation areas-the Tsavo East and West
National Parks. It is therefore a migratory corridor whose presence helps the wildlife from both parks to
) in the project zone
Use appropriate methodologies to estimate the impacts on communities, including all
G1), resulting from
planned project activities. A credible estimate of impacts must include changes in community well-being
due to project activities and an evaluation of the impacts by the affected groups. This estimate must be
ble assumptions about how project activities will alter social and
being, including potential impacts of changes in natural resources and ecosystem services
the duration of the
project. The ‘with project’ scenario must then be compared with the ‘without project’ scenario of social
). The difference (i.e., the
Wildlife Works carbon offset project’s PDD has details of the net positive impact that the
project will have on the local community. A thorough scrutiny and interviews with the local community
ments presented in the PDD even in its current operational status and organisation.
Wildlife Works currently offers employment to the local community at their Export Processing Zone’s
(EPZ) organic sewing factory. It also offers other employments opportunities to the locals as house
-a form of sharing
nt opportunities are indiscriminate of gender and
All these employment opportunities empower the local community members concerned with
be applied elsewhere, monthly cash flows which give them some
comparative advantages over other communities in the project zone and purchasing powers leading to
G1.8.4-642 will be
the Tsavo East and West
National Parks. It is therefore a migratory corridor whose presence helps the wildlife from both parks to
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
move freely in search of pasture, water and protection. The “wi
exposure of endemic and endangered wildlife to poaching while they migrate on the corridor because
the “without project scenario” will lead in vegetation destruction and land degradation.
The controlled fuel wood collection by the local community, the restricted over grazing of cattle also by
the local community, the strict surveillance and patrols to avert poaching of wildlife and trees, instituted
by the project through recruiting enough game rangers; will be positi
Values identified in G 1.8..4-642 and will not have negative effect on the said HCV in the area.
The foregoing finding of the audit team concurs with the explanations given by the project proponent
stated in the PDD.
Conformance:
Non-Conformity Reports:
NCR Number 18 of 19 for October 20, 2009
Finding: There are clear risks to the project's climate, community and biodiversity benefits (including
impacts on the well-beings of communit
posed by prolonged drought as a result of climate change. The project proponent must identify these
risks and explain how they will be mitigated.
Proponent Response on October 26
the PDD to include a lot more detail no Climate Change factors relevant to our Project. We believe that
submission of the updated PDD text below provides a complete and appropriate response to this NCR
and that this NCR should now be closed.
Validator Response: The response is adequate.
New Information Requests:
Opportunities for Improvement:
3.4.2. CM2 – Offsite Stakeholder Impacts
Concept
The project proponents must evaluate and mitigate
result in the decreased social and economic well
project zone resulting from project activities. Project activities should at least ‘do no harm’ to the we
being of offsite stakeholders.
Indicators
The project proponents must:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
45
move freely in search of pasture, water and protection. The “without project scenario” will result in
exposure of endemic and endangered wildlife to poaching while they migrate on the corridor because
the “without project scenario” will lead in vegetation destruction and land degradation.
lection by the local community, the restricted over grazing of cattle also by
the local community, the strict surveillance and patrols to avert poaching of wildlife and trees, instituted
by the project through recruiting enough game rangers; will be positive in promoting High Conservation
642 and will not have negative effect on the said HCV in the area.
The foregoing finding of the audit team concurs with the explanations given by the project proponent
Yes No N/A
See NCR Number 2 of 19 for October 20, 2009
NCR Number 18 of 19 for October 20, 2009
There are clear risks to the project's climate, community and biodiversity benefits (including
beings of communities and the conservation of biodiversity), including the risks
posed by prolonged drought as a result of climate change. The project proponent must identify these
risks and explain how they will be mitigated.
October 26, 2009: We have significantly amended Sections GL1.2 and GL1.3 of
the PDD to include a lot more detail no Climate Change factors relevant to our Project. We believe that
submission of the updated PDD text below provides a complete and appropriate response to this NCR
and that this NCR should now be closed.
The response is adequate.
None
None
Offsite Stakeholder Impacts
The project proponents must evaluate and mitigate any possible social and economic impacts that could
result in the decreased social and economic well-being of the main stakeholders living outside the
project zone resulting from project activities. Project activities should at least ‘do no harm’ to the we
thout project scenario” will result in
exposure of endemic and endangered wildlife to poaching while they migrate on the corridor because
the “without project scenario” will lead in vegetation destruction and land degradation.
lection by the local community, the restricted over grazing of cattle also by
the local community, the strict surveillance and patrols to avert poaching of wildlife and trees, instituted
ve in promoting High Conservation
642 and will not have negative effect on the said HCV in the area.
The foregoing finding of the audit team concurs with the explanations given by the project proponent
NCR Number 2 of 19 for October 20, 2009
There are clear risks to the project's climate, community and biodiversity benefits (including
ies and the conservation of biodiversity), including the risks
posed by prolonged drought as a result of climate change. The project proponent must identify these
ave significantly amended Sections GL1.2 and GL1.3 of
the PDD to include a lot more detail no Climate Change factors relevant to our Project. We believe that
submission of the updated PDD text below provides a complete and appropriate response to this NCR
any possible social and economic impacts that could
being of the main stakeholders living outside the
project zone resulting from project activities. Project activities should at least ‘do no harm’ to the well-
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Indicator CM2.1. Identify any potential negative offsite stakeholder impacts that the project activities
are likely to cause.
Findings: The initial PDD claimed that there were no
the audit process, negative impacts were discovered. The project proponent responded to the NCR by
updating the PDD to include language explaining why this is the case. The auditors took the information
into consideration and found the proponent to be in conformance.
Conformance:
Non-Conformity Reports:
NCR Number 15 of 19 for October 20, 2009
Finding: The project proponent strongly claims there are no negative offsite impacts to stakeholders.
However, based on community meetings, interviews and observations conducted during the site visit,
potential negative offsite impacts indeed exist. Community members identified the following potential
negative offsite impacts: an exclusive dependence on Wildlife Works for livelihood, an increase in
wildlife-human conflicts and the exclusion of grazing from the sanctuary. Th
address these negative impacts to stakeholders and describe how they will be mitigated. Also,
demonstrate that project is not likely to result in net negative impacts on the well being of other
stakeholder groups. Note that the
CCBA.
Proponent Response on October 30
are potential negative impacts from the Project Activities by adding content to sections C
and CM2.3. We have included that text below and we believe that this provides an adequate and
complete response to your finding and as such we ask that you close finding NCR#15.
Validator Response: The response is adequate.
New Information Requests:
Opportunities for Improvement:
Indicator CM2.2. Describe how the project plans to mitigate these negative offsite social and economic
impacts.
Findings: Geographically, Taita district, the location of the project
marginalized. The major economic activity is dry land rain fed agriculture and pastoralism. With
emergence of persistent drought in Kenya, agriculture and pastoralism has been highly affected leading
to high failures and loss of otherwise dependable livelihood by the community in the area.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
46
Identify any potential negative offsite stakeholder impacts that the project activities
claimed that there were no net negative offsite stakeholder impacts. During
the audit process, negative impacts were discovered. The project proponent responded to the NCR by
updating the PDD to include language explaining why this is the case. The auditors took the information
consideration and found the proponent to be in conformance.
Yes No N/A
15 of 19 for October 20, 2009
The project proponent strongly claims there are no negative offsite impacts to stakeholders.
However, based on community meetings, interviews and observations conducted during the site visit,
site impacts indeed exist. Community members identified the following potential
negative offsite impacts: an exclusive dependence on Wildlife Works for livelihood, an increase in
human conflicts and the exclusion of grazing from the sanctuary. The project proponent must
address these negative impacts to stakeholders and describe how they will be mitigated. Also,
demonstrate that project is not likely to result in net negative impacts on the well being of other
stakeholder groups. Note that the Duruma are considered another stakeholder group as defined by the
October 30, 2009: We have addressed the community perception that there
are potential negative impacts from the Project Activities by adding content to sections C
and CM2.3. We have included that text below and we believe that this provides an adequate and
complete response to your finding and as such we ask that you close finding NCR#15.
The response is adequate.
None
None
Describe how the project plans to mitigate these negative offsite social and economic
Geographically, Taita district, the location of the project is categorised as a semi arid area and
marginalized. The major economic activity is dry land rain fed agriculture and pastoralism. With
emergence of persistent drought in Kenya, agriculture and pastoralism has been highly affected leading
es and loss of otherwise dependable livelihood by the community in the area.
Identify any potential negative offsite stakeholder impacts that the project activities
net negative offsite stakeholder impacts. During
the audit process, negative impacts were discovered. The project proponent responded to the NCR by
updating the PDD to include language explaining why this is the case. The auditors took the information
The project proponent strongly claims there are no negative offsite impacts to stakeholders.
However, based on community meetings, interviews and observations conducted during the site visit,
site impacts indeed exist. Community members identified the following potential
negative offsite impacts: an exclusive dependence on Wildlife Works for livelihood, an increase in
e project proponent must
address these negative impacts to stakeholders and describe how they will be mitigated. Also,
demonstrate that project is not likely to result in net negative impacts on the well being of other
uruma are considered another stakeholder group as defined by the
We have addressed the community perception that there
are potential negative impacts from the Project Activities by adding content to sections CM2.1, CM2.2
and CM2.3. We have included that text below and we believe that this provides an adequate and
Describe how the project plans to mitigate these negative offsite social and economic
is categorised as a semi arid area and
marginalized. The major economic activity is dry land rain fed agriculture and pastoralism. With
emergence of persistent drought in Kenya, agriculture and pastoralism has been highly affected leading
es and loss of otherwise dependable livelihood by the community in the area.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Wildlife Works has been supporting research work in collaboration with the Kenya Agricultural Research
Institute (KARI) to introduce and upscale some viable alternative cash crop
(Simmondsia chinensis), was introduced in Rukinga ranch before Wildlife Works purchased and took
over the management of the ranch. This crop has persisted the scarcity of rainfall and high temperature
variability in the area and has proved itself to be a viable and dependable cash crop in the area. With its
highly demanded and highly priced oil, Wildlife Works hopes to market the crop and supply its seeds and
seedlings to local community for commercial propagation. Already Wildlif
nursery for raising its seedlings. It is hoped that if the community accept this crop and plant it in large
scale, the area could turn to be a net exporter of Jojoba seeds and oil which has a global demand. The
success of this crop establishment and adoption of the crop by the local community will be a viable and
a more sustainable way of empowering the local community economically.
Wildlife Works has also established a Citrus fruit tree nursery in their organic green house and
adaptive research identified species that do well in different soils and ecological zones in the area. The
citrus species are sold to the local farmers for planting in their farms at subsidized prices. Through this
initiative; some farmers in the area have gone full scale in commercial citrus fruit farming and are
economically benefiting.
These efforts by Wildlife Works are viable initiatives and were considered by the audit team to mitigate
negative impacts on offsite stakeholders and will e
other sustainable income generation activities in the project area and project zone.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CM2.3. Demonstrate that the project is not likely to result in net negative impacts on the well
being of other stakeholder groups.
Findings:
In the community public meeting, it emerged that there will be negative impacts emanating from
human-wildlife conflicts, exclusion of some people still practicing traditional rituals in sites located in the
project area, fuel wood collection et
he argued that since taking over the management of the ranch, the communities who lived inside the
project area were moved out and with the concerted patrol of the ranch by rangers, direct
interaction between wildlife and community has been greatly minimized.
Cases of stray wildlife into the community residence, raiding their crops or attacking their cattle have
always been timely reported to the Kenya Wildlife Services (KWS)
wildlife in Kenya and who share VHF radio frequencies with
driven the wildlife back to the protected area.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
47
Wildlife Works has been supporting research work in collaboration with the Kenya Agricultural Research
Institute (KARI) to introduce and upscale some viable alternative cash crops in the area. Jojoba
(Simmondsia chinensis), was introduced in Rukinga ranch before Wildlife Works purchased and took
over the management of the ranch. This crop has persisted the scarcity of rainfall and high temperature
s proved itself to be a viable and dependable cash crop in the area. With its
highly demanded and highly priced oil, Wildlife Works hopes to market the crop and supply its seeds and
seedlings to local community for commercial propagation. Already Wildlife Works has established a
nursery for raising its seedlings. It is hoped that if the community accept this crop and plant it in large
scale, the area could turn to be a net exporter of Jojoba seeds and oil which has a global demand. The
rop establishment and adoption of the crop by the local community will be a viable and
a more sustainable way of empowering the local community economically.
Wildlife Works has also established a Citrus fruit tree nursery in their organic green house and
adaptive research identified species that do well in different soils and ecological zones in the area. The
citrus species are sold to the local farmers for planting in their farms at subsidized prices. Through this
area have gone full scale in commercial citrus fruit farming and are
These efforts by Wildlife Works are viable initiatives and were considered by the audit team to mitigate
negative impacts on offsite stakeholders and will eventually empower local people to diversify into
other sustainable income generation activities in the project area and project zone.
Yes No N/A
See NCR Number 15 of 19 for October 20, 2009
None
None
Demonstrate that the project is not likely to result in net negative impacts on the well
In the community public meeting, it emerged that there will be negative impacts emanating from
wildlife conflicts, exclusion of some people still practicing traditional rituals in sites located in the
project area, fuel wood collection etc. In the subsequent follow up meeting with the project proponent,
he argued that since taking over the management of the ranch, the communities who lived inside the
project area were moved out and with the concerted patrol of the ranch by rangers, direct
interaction between wildlife and community has been greatly minimized.
Cases of stray wildlife into the community residence, raiding their crops or attacking their cattle have
always been timely reported to the Kenya Wildlife Services (KWS) who are legally mandated to manage
wildlife in Kenya and who share VHF radio frequencies with Wildlife Works. In such cases KWS have
driven the wildlife back to the protected area.
Wildlife Works has been supporting research work in collaboration with the Kenya Agricultural Research
s in the area. Jojoba
(Simmondsia chinensis), was introduced in Rukinga ranch before Wildlife Works purchased and took
over the management of the ranch. This crop has persisted the scarcity of rainfall and high temperature
s proved itself to be a viable and dependable cash crop in the area. With its
highly demanded and highly priced oil, Wildlife Works hopes to market the crop and supply its seeds and
e Works has established a
nursery for raising its seedlings. It is hoped that if the community accept this crop and plant it in large
scale, the area could turn to be a net exporter of Jojoba seeds and oil which has a global demand. The
rop establishment and adoption of the crop by the local community will be a viable and
Wildlife Works has also established a Citrus fruit tree nursery in their organic green house and through
adaptive research identified species that do well in different soils and ecological zones in the area. The
citrus species are sold to the local farmers for planting in their farms at subsidized prices. Through this
area have gone full scale in commercial citrus fruit farming and are
These efforts by Wildlife Works are viable initiatives and were considered by the audit team to mitigate
ventually empower local people to diversify into
r 15 of 19 for October 20, 2009
Demonstrate that the project is not likely to result in net negative impacts on the well-
In the community public meeting, it emerged that there will be negative impacts emanating from
wildlife conflicts, exclusion of some people still practicing traditional rituals in sites located in the
c. In the subsequent follow up meeting with the project proponent,
he argued that since taking over the management of the ranch, the communities who lived inside the
project area were moved out and with the concerted patrol of the ranch by rangers, direct conflict and
Cases of stray wildlife into the community residence, raiding their crops or attacking their cattle have
who are legally mandated to manage
. In such cases KWS have
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Being a wildlife corridor the project area play a vital role in ensuring
most of what they need and hardly attack the community. The protection of the wildlife too will ensure
the existence of the wildlife to perpetuity and so are the tourism industries which brings a lot of foreign
exchange for national development.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.4.3. CM3 – Community Impact Monitoring
Concept
The project proponents must have an initial
and economic well-being resulting from the project activities (for communities and other stakeholders).
The monitoring plan must indicate which communities and other stakeholders will be monitored,
identify the types of measurements, the sampling method, and the frequency of measurement.
Since developing a full community monitoring plan can be costly, it is accepted that some of the plan
details may not be fully defined at the design stage, whe
Standards. This is acceptable as long as there is an explicit commitment to develop and implement a
monitoring plan.
Indicators
The project proponents must:
Indicator CM3.1. Develop an initial plan for selectin
frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the
project’s community development objectives and to anticipated impacts (positive and negative).
Findings: The initial PDD did not include monitoring variables that addressed all of the community
development objectives. NCR 16 was issued. The project proponent subsequently revised the PDD to
include this information.
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
48
Being a wildlife corridor the project area play a vital role in ensuring that the migrating wildlife have
most of what they need and hardly attack the community. The protection of the wildlife too will ensure
the existence of the wildlife to perpetuity and so are the tourism industries which brings a lot of foreign
or national development. Thus the net impacts are positive.
Yes No N/A
None
None
None
Community Impact Monitoring
The project proponents must have an initial monitoring plan to quantify and document changes in social
being resulting from the project activities (for communities and other stakeholders).
The monitoring plan must indicate which communities and other stakeholders will be monitored,
identify the types of measurements, the sampling method, and the frequency of measurement.
Since developing a full community monitoring plan can be costly, it is accepted that some of the plan
details may not be fully defined at the design stage, when projects are being validated against the
Standards. This is acceptable as long as there is an explicit commitment to develop and implement a
Develop an initial plan for selecting community variables to be monitored and the
frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the
project’s community development objectives and to anticipated impacts (positive and negative).
The initial PDD did not include monitoring variables that addressed all of the community
development objectives. NCR 16 was issued. The project proponent subsequently revised the PDD to
Yes No N/A
that the migrating wildlife have
most of what they need and hardly attack the community. The protection of the wildlife too will ensure
the existence of the wildlife to perpetuity and so are the tourism industries which brings a lot of foreign
monitoring plan to quantify and document changes in social
being resulting from the project activities (for communities and other stakeholders).
The monitoring plan must indicate which communities and other stakeholders will be monitored, and
identify the types of measurements, the sampling method, and the frequency of measurement.
Since developing a full community monitoring plan can be costly, it is accepted that some of the plan
n projects are being validated against the
Standards. This is acceptable as long as there is an explicit commitment to develop and implement a
g community variables to be monitored and the
frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the
project’s community development objectives and to anticipated impacts (positive and negative).
The initial PDD did not include monitoring variables that addressed all of the community
development objectives. NCR 16 was issued. The project proponent subsequently revised the PDD to
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NCR Number 16 of 19 for October 20, 2009
Finding: The selected monitoring variables do not address all of the community development
objectives. The monitoring variables must be directly linked to the community development objectives.
Proponent Response on November 1
extensive list of monitoring variables organized by specific Project Activity. The text of that section is
included below. We believe this represents a complete and acceptable response to your f
meets the standard and we ask that you close finding NCR#16.
Validator Response: The information provided is adequate.
New Information Requests:
Opportunities for Improvement:
Indicator CM3.2. Develop an initial plan for how they will assess the effectiveness of measures used to
maintain or enhance High Conservation Values related to community well
the project zone.
Findings: The project proponent has not outlined
assessing the effectiveness of measures used to maintain or enhance High Conservation Values related
to community well-being present in the project zone. However the proponent has described how the
project will use the game rangers on daily basis to monitor some of the endangered endemic wildlife
species in the ranch. They hope to use the carbon finance to upscale the wildlife monitoring intensity
and the range of monitoring.
In addition the Global Positioning System (GPS) coordinates of the areas where the monitored species of
wildlife are mostly sighted will help the management in designing an effective surveillance and
monitoring programme since such areas are more vulnerable to poaching or disease o
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator CM3.3. Commit to developing a full monitoring plan within six months of the project start
date or within twelve months of validation against the Standards and to disseminate this plan and the
results of monitoring, ensuring that they are made publicly available
communicated to the communities and other stakeholders.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
49
19 for October 20, 2009
The selected monitoring variables do not address all of the community development
objectives. The monitoring variables must be directly linked to the community development objectives.
November 1, 2009: We have significantly enhanced Section CM3.1 to add an
extensive list of monitoring variables organized by specific Project Activity. The text of that section is
included below. We believe this represents a complete and acceptable response to your f
meets the standard and we ask that you close finding NCR#16.
The information provided is adequate.
None
None
Develop an initial plan for how they will assess the effectiveness of measures used to
maintain or enhance High Conservation Values related to community well-being (G1.8.4
The project proponent has not outlined in the revised PDD, the means that will be used in
assessing the effectiveness of measures used to maintain or enhance High Conservation Values related
being present in the project zone. However the proponent has described how the
ect will use the game rangers on daily basis to monitor some of the endangered endemic wildlife
species in the ranch. They hope to use the carbon finance to upscale the wildlife monitoring intensity
itioning System (GPS) coordinates of the areas where the monitored species of
wildlife are mostly sighted will help the management in designing an effective surveillance and
monitoring programme since such areas are more vulnerable to poaching or disease out break.
Yes No N/A
See NCR Number 2 of 19 for October 20, 2009
None
None
Commit to developing a full monitoring plan within six months of the project start
date or within twelve months of validation against the Standards and to disseminate this plan and the
results of monitoring, ensuring that they are made publicly available on the internet and are
communicated to the communities and other stakeholders.
The selected monitoring variables do not address all of the community development
objectives. The monitoring variables must be directly linked to the community development objectives.
We have significantly enhanced Section CM3.1 to add an
extensive list of monitoring variables organized by specific Project Activity. The text of that section is
included below. We believe this represents a complete and acceptable response to your finding and
Develop an initial plan for how they will assess the effectiveness of measures used to
being (G1.8.4-6) present in
in the revised PDD, the means that will be used in
assessing the effectiveness of measures used to maintain or enhance High Conservation Values related
being present in the project zone. However the proponent has described how the
ect will use the game rangers on daily basis to monitor some of the endangered endemic wildlife
species in the ranch. They hope to use the carbon finance to upscale the wildlife monitoring intensity
itioning System (GPS) coordinates of the areas where the monitored species of
wildlife are mostly sighted will help the management in designing an effective surveillance and
ut break.
NCR Number 2 of 19 for October 20, 2009
Commit to developing a full monitoring plan within six months of the project start
date or within twelve months of validation against the Standards and to disseminate this plan and the
on the internet and are
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Findings: The project proponent has committed in the revised PDD to develop a detailed monitoring
plan within twelve months of validation. He has also promise to make such a
stakeholders via the internet as required by the
During the field site visit, the project proponent assured the audit team that the project will establish a
detailed monitoring plan for the project.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.5. Biodiversity Section
3.5.1. B1 – Net Positive Biodiversity Impacts
Concept
The project must generate net positive impacts on biodiversity within the project z
project lifetime, measured against the baseline conditions.
The project should maintain or enhance any High Conservation Values (identified in
project zone that are of importance in conserving globally, regionally or
biodiversity.
Invasive species populations must not increase as a result of the project, either through direct use or
indirectly as a result of project activities.
Projects may not use genetically modified organisms (GMOs) to
removals. GMOs raise unresolved ethical, scientific and socio
attributes may result in invasive genes or species.
Indicators
The project proponents must:
Indicator B1.1. Use appropriate methodologies to estimate changes in biodiversity as a result of the
project in the project zone and in the project lifetime. This estimate must be based on clearly defined
and defendable assumptions. The ‘with project’ scenario should then be comp
‘without project’ biodiversity scenario completed in
must be positive.
Findings: Wildlife Works has addressed very well the changes on biodiversity in the revised PDD. It is
true that the management of Wildlife Works has been keen on estimating the biodiversity changes using
their rangers that go on daily patrols of the ranch.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
50
The project proponent has committed in the revised PDD to develop a detailed monitoring
plan within twelve months of validation. He has also promise to make such a plan available to the
stakeholders via the internet as required by the CCB Standards.
During the field site visit, the project proponent assured the audit team that the project will establish a
detailed monitoring plan for the project.
Yes No N/A
None
None
None
Net Positive Biodiversity Impacts
The project must generate net positive impacts on biodiversity within the project zone and within the
project lifetime, measured against the baseline conditions.
The project should maintain or enhance any High Conservation Values (identified in G1
project zone that are of importance in conserving globally, regionally or nationally significant
Invasive species populations must not increase as a result of the project, either through direct use or
indirectly as a result of project activities.
Projects may not use genetically modified organisms (GMOs) to generate GHG emissions reductions or
removals. GMOs raise unresolved ethical, scientific and socio-economic issues. For example, some GMO
attributes may result in invasive genes or species.
opriate methodologies to estimate changes in biodiversity as a result of the
the project zone and in the project lifetime. This estimate must be based on clearly defined
defendable assumptions. The ‘with project’ scenario should then be compared with the baseline
‘without project’ biodiversity scenario completed in G2. The difference (i.e., the net biodiversity
Wildlife Works has addressed very well the changes on biodiversity in the revised PDD. It is
true that the management of Wildlife Works has been keen on estimating the biodiversity changes using
s that go on daily patrols of the ranch.
The project proponent has committed in the revised PDD to develop a detailed monitoring
plan available to the
During the field site visit, the project proponent assured the audit team that the project will establish a
one and within the
G1) present in the
nationally significant
Invasive species populations must not increase as a result of the project, either through direct use or
generate GHG emissions reductions or
economic issues. For example, some GMO
opriate methodologies to estimate changes in biodiversity as a result of the
the project zone and in the project lifetime. This estimate must be based on clearly defined
ared with the baseline
. The difference (i.e., the net biodiversity benefit)
Wildlife Works has addressed very well the changes on biodiversity in the revised PDD. It is
true that the management of Wildlife Works has been keen on estimating the biodiversity changes using
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
The project proponent provided documentary evidence of the methodologies used in biodiversity
changes in the ranch and these were availed to the audit team during the field site visit. During the field
site visit also the audit team also observed the biodiversity data collection technique and analysis.
The preservation of the ecosystems and habitat
rangers were seen keeping off the ranch those illegally grazing in the ranch and promoting over grazing
and land degradation in particular areas of the ranch. The intensity of patrol and surveillance ha
those poaching for bush meat for sale and trophies off not to operate in the ranch. By working together
with the Kenya Wildlife Services (KWS), Wildlife Works has asked for reinforcement whenever
necessary.
The permanent vegetation plots also help
time in a situation of free grazing by wildlife. However there are other components of biodiversity
which too are indicators of the biodiversity health and may need to be monitored as well becau
too are important in nutrient recycling. They include arthropods, birds, reptiles, amphibians, small
mammals besides large mammals like elephants, zebra, buffaloes, giraffe etc.
The ‘with project’ scenario will ensure sustainable conservation of
rightly described by the project proponent in the PDD. The ‘without project’ scenario will lead to quick
destruction and disappearance of the endemic and already endangered species of biodiversity in the
ranch because even at its protection and intense patrols and surveillance by the
there is pressure from those living around the ranch and generally in the project zone.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator B1.2. Demonstrate that no High Conservation Values identified in
affected by the project.
Findings: The project proponent stated in the revised PDD that there will not be any negative
the High Conservation Values, contending that it is their day to day duty to conserve such areas.
The results of the audit confirm that HCVs will not be negatively affected by the project.
Conformance:
Non-Conformity Reports:
New Information Requests:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
51
The project proponent provided documentary evidence of the methodologies used in biodiversity
ges in the ranch and these were availed to the audit team during the field site visit. During the field
site visit also the audit team also observed the biodiversity data collection technique and analysis.
The preservation of the ecosystems and habitat was also observed during the field site visit where
rangers were seen keeping off the ranch those illegally grazing in the ranch and promoting over grazing
and land degradation in particular areas of the ranch. The intensity of patrol and surveillance ha
those poaching for bush meat for sale and trophies off not to operate in the ranch. By working together
with the Kenya Wildlife Services (KWS), Wildlife Works has asked for reinforcement whenever
The permanent vegetation plots also help the ranch management in tracking vegetation transition with
time in a situation of free grazing by wildlife. However there are other components of biodiversity
which too are indicators of the biodiversity health and may need to be monitored as well becau
too are important in nutrient recycling. They include arthropods, birds, reptiles, amphibians, small
mammals besides large mammals like elephants, zebra, buffaloes, giraffe etc.
The ‘with project’ scenario will ensure sustainable conservation of biodiversity in the ranch as has been
rightly described by the project proponent in the PDD. The ‘without project’ scenario will lead to quick
destruction and disappearance of the endemic and already endangered species of biodiversity in the
e even at its protection and intense patrols and surveillance by the Wildlife Works rangers,
pressure from those living around the ranch and generally in the project zone.
Yes No N/A
None
None
None
Demonstrate that no High Conservation Values identified in G1.8.1-348 will be negatively
The project proponent stated in the revised PDD that there will not be any negative
the High Conservation Values, contending that it is their day to day duty to conserve such areas.
The results of the audit confirm that HCVs will not be negatively affected by the project.
Yes No N/A
None
None
The project proponent provided documentary evidence of the methodologies used in biodiversity
ges in the ranch and these were availed to the audit team during the field site visit. During the field
site visit also the audit team also observed the biodiversity data collection technique and analysis.
was also observed during the field site visit where
rangers were seen keeping off the ranch those illegally grazing in the ranch and promoting over grazing
and land degradation in particular areas of the ranch. The intensity of patrol and surveillance has kept
those poaching for bush meat for sale and trophies off not to operate in the ranch. By working together
with the Kenya Wildlife Services (KWS), Wildlife Works has asked for reinforcement whenever
the ranch management in tracking vegetation transition with
time in a situation of free grazing by wildlife. However there are other components of biodiversity
which too are indicators of the biodiversity health and may need to be monitored as well because they
too are important in nutrient recycling. They include arthropods, birds, reptiles, amphibians, small
biodiversity in the ranch as has been
rightly described by the project proponent in the PDD. The ‘without project’ scenario will lead to quick
destruction and disappearance of the endemic and already endangered species of biodiversity in the
Wildlife Works rangers,
48 will be negatively
The project proponent stated in the revised PDD that there will not be any negative impact on
the High Conservation Values, contending that it is their day to day duty to conserve such areas.
The results of the audit confirm that HCVs will not be negatively affected by the project.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Opportunities for Improvement:
Indicator B1.3. Identify all species to be used by the project and show that no known in
will be introduced into any area affected by the project and that the population of any invasive species
will not increase as a result of the project.
Findings: The project proponent has explained in the revised PDD that there are no new s
are being introduced in the project area and hence the action of the project will not lead to introduction
of the invasive species in the project area.
During the site visit, the audit team evaluated the species being raised in the project’s G
only noted that the composition of the species are agroforestry species and some exotic species which
have been researched on and found to be suitable for dryland afforestation activities and have no ability
for invasiveness and so are not a threat to the biodiversity conservation in the area.
The audit team also confirmed that Wildlife Works is following up the suitability of Jojoba (Simmondsia
chinensis) as a cash crop and confirmed that although this was introduced in the project area
years ago before Wildlife Works took over the management of the ranch. However this species too has
not spread beyond the areas where it was introduced, showing that it is not invasive and so has no
threat to the biodiversity of the project area.
Conformance:
Non-Conformity Reports:
NCR Number 17 of 19 for October 20, 2009
Finding: The project proponent must identify all species to be used by the project including those
provided by the greenhouse project activity and other project activities. If some of the
native , describe the possible adverse effects. Also, justify why non
species.
Proponent Response on October 29
include the text below.
We believe that this new information provided to the Validator is a more than adequate response to
your finding and we ask that you consider this finding NCR#17 closed.
Validator Response: The response is adequate.
New Information Requests:
Opportunities for Improvement:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
52
None
Identify all species to be used by the project and show that no known in
introduced into any area affected by the project and that the population of any invasive species
will not increase as a result of the project.
The project proponent has explained in the revised PDD that there are no new s
are being introduced in the project area and hence the action of the project will not lead to introduction
of the invasive species in the project area.
During the site visit, the audit team evaluated the species being raised in the project’s G
only noted that the composition of the species are agroforestry species and some exotic species which
have been researched on and found to be suitable for dryland afforestation activities and have no ability
threat to the biodiversity conservation in the area.
The audit team also confirmed that Wildlife Works is following up the suitability of Jojoba (Simmondsia
chinensis) as a cash crop and confirmed that although this was introduced in the project area
years ago before Wildlife Works took over the management of the ranch. However this species too has
not spread beyond the areas where it was introduced, showing that it is not invasive and so has no
threat to the biodiversity of the project area.
Yes No N/A
NCR Number 17 of 19 for October 20, 2009
The project proponent must identify all species to be used by the project including those
provided by the greenhouse project activity and other project activities. If some of the
native , describe the possible adverse effects. Also, justify why non-native species are used over native
October 29, 2009: We have revised sections B1.3 and B1.4 of the PDD to
We believe that this new information provided to the Validator is a more than adequate response to
your finding and we ask that you consider this finding NCR#17 closed.
The response is adequate.
None
None
Identify all species to be used by the project and show that no known invasive species
introduced into any area affected by the project and that the population of any invasive species
The project proponent has explained in the revised PDD that there are no new species that
are being introduced in the project area and hence the action of the project will not lead to introduction
During the site visit, the audit team evaluated the species being raised in the project’s Green House and
only noted that the composition of the species are agroforestry species and some exotic species which
have been researched on and found to be suitable for dryland afforestation activities and have no ability
The audit team also confirmed that Wildlife Works is following up the suitability of Jojoba (Simmondsia
chinensis) as a cash crop and confirmed that although this was introduced in the project area many
years ago before Wildlife Works took over the management of the ranch. However this species too has
not spread beyond the areas where it was introduced, showing that it is not invasive and so has no
The project proponent must identify all species to be used by the project including those
provided by the greenhouse project activity and other project activities. If some of the species are non-
native species are used over native
We have revised sections B1.3 and B1.4 of the PDD to
We believe that this new information provided to the Validator is a more than adequate response to
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Indicator B1.4. Describe possible adverse effects of non
region’s environment, including impacts on native species and disease introduction or facilitation.
Project proponents must justify any use of non
Findings: The project prominent in the revised PDD explained that this indicator does not apply. And
during the site visit, the audit team too confirmed that the fast growing exotic species
project’s Green House nursery are not planted in the project area but are rather given out to the local
community for planting in their private farms as a way of empowering the community to produce their
own forest products for their use.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator B1.5. Guarantee that no GMOs will be used to generate GHG emissions reductions or
removals.
Findings: The project proponent has explained in the PDD that no GMOs will be used to generate GHG
emissions reductions or their removal.
This was confirmed by the audit team who confirmed that the species raised in the Green House tree
nursery are not planted in the Wildlife Works project and the Green House tree nursery does not raise
GMOs.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.5.2. B2 – Offsite Biodiversity Impacts
Concept
The project proponents must evaluate and mitigate likely negative impacts on biodiversity outside the
project zone resulting from project activities.
Indicators
The project proponents must:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
53
Describe possible adverse effects of non-native species used by the project on the
environment, including impacts on native species and disease introduction or facilitation.
ustify any use of non-native species over native species.
The project prominent in the revised PDD explained that this indicator does not apply. And
during the site visit, the audit team too confirmed that the fast growing exotic species
project’s Green House nursery are not planted in the project area but are rather given out to the local
community for planting in their private farms as a way of empowering the community to produce their
Yes No N/A
See NCR Number 17 of 19 for October 20, 2009
None
None
Guarantee that no GMOs will be used to generate GHG emissions reductions or
The project proponent has explained in the PDD that no GMOs will be used to generate GHG
emissions reductions or their removal.
This was confirmed by the audit team who confirmed that the species raised in the Green House tree
he Wildlife Works project and the Green House tree nursery does not raise
Yes No N/A
None
None
None
Offsite Biodiversity Impacts
aluate and mitigate likely negative impacts on biodiversity outside the
project zone resulting from project activities.
native species used by the project on the
environment, including impacts on native species and disease introduction or facilitation.
The project prominent in the revised PDD explained that this indicator does not apply. And
during the site visit, the audit team too confirmed that the fast growing exotic species raised in the
project’s Green House nursery are not planted in the project area but are rather given out to the local
community for planting in their private farms as a way of empowering the community to produce their
NCR Number 17 of 19 for October 20, 2009
Guarantee that no GMOs will be used to generate GHG emissions reductions or
The project proponent has explained in the PDD that no GMOs will be used to generate GHG
This was confirmed by the audit team who confirmed that the species raised in the Green House tree
he Wildlife Works project and the Green House tree nursery does not raise
aluate and mitigate likely negative impacts on biodiversity outside the
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Indicator B2.1. Identify potential negative offsite biodiversity impacts that the project is likely to cause.
Findings: In the revised PDD, the project proponent has described that as a result of the project; there
will be no offsite negative impact on biodiversity.
Following the field site visit, the audit team established that as a result of the project, there will not be
any potential negative offsite biodiversity impacts that the project is likely to cause, but rather it will
have offsite positive biodiversity impact due to its activities.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator B2.2. Document how the project plans to mitigate these negative offsite biodiversity impacts.
Findings: Based on the response in B2.1 above, this indicator does not apply. The project proponent
has also responded the same in the revised PDD.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator B2.3. Evaluate likely unmitigated negative offsite biodiversity impacts
benefits of the project within the project boundaries. Justify and demonstrate that the net effect of the
project on biodiversity is positive.
Findings: The project proponent in the PDD does not anticipate any negative offsite bi
impacts from the project. But the net effect of the project on biodiversity in the Wildlife Works projects
and offsite is expected to be positive.
Conformance:
Non-Conformity Reports:
New Information Requests:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
54
Identify potential negative offsite biodiversity impacts that the project is likely to cause.
In the revised PDD, the project proponent has described that as a result of the project; there
will be no offsite negative impact on biodiversity.
Following the field site visit, the audit team established that as a result of the project, there will not be
any potential negative offsite biodiversity impacts that the project is likely to cause, but rather it will
mpact due to its activities.
Yes No N/A
None
None
None
Document how the project plans to mitigate these negative offsite biodiversity impacts.
on the response in B2.1 above, this indicator does not apply. The project proponent
has also responded the same in the revised PDD.
Yes No N/A
None
None
None
Evaluate likely unmitigated negative offsite biodiversity impacts against the biodiversity
benefits of the project within the project boundaries. Justify and demonstrate that the net effect of the
The project proponent in the PDD does not anticipate any negative offsite bi
impacts from the project. But the net effect of the project on biodiversity in the Wildlife Works projects
and offsite is expected to be positive.
Yes No N/A
None
None
Identify potential negative offsite biodiversity impacts that the project is likely to cause.
In the revised PDD, the project proponent has described that as a result of the project; there
Following the field site visit, the audit team established that as a result of the project, there will not be
any potential negative offsite biodiversity impacts that the project is likely to cause, but rather it will
Document how the project plans to mitigate these negative offsite biodiversity impacts.
on the response in B2.1 above, this indicator does not apply. The project proponent
against the biodiversity
benefits of the project within the project boundaries. Justify and demonstrate that the net effect of the
The project proponent in the PDD does not anticipate any negative offsite biodiversity
impacts from the project. But the net effect of the project on biodiversity in the Wildlife Works projects
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Opportunities for Improvement:
3.5.3. B3 – Biodiversity Impact Monitoring
Concept
The project proponents must have an initial monitoring plan to quantify and document the changes in
biodiversity resulting from the project
monitoring plan must identify the types of measurements, the sampling method, and the frequency of
measurement.
Since developing a full biodiversity
details may not be fully defined at the design stage, when projects are being validated against the
Standards. This is acceptable as long as there is an explicit commitment to develop and implement a
monitoring plan.
Indicators
The project proponents must:
Indicator B3.1. Develop an initial plan for selecting biodiversity variables to be monitored and the
frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the
project’s biodiversity objectives and to anticipated impacts (positive and negative).
Findings: The project proponent has highlighted a monitoring schedule that will be used in Wildlife
Works REDD project and also listed a number of variables in the PDD that will be monitored with a
frequency being on a daily basis.
The project proponent however should consider recording the locations of animal and poacher sightings
using a GPS.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
OFI Number 4 of 4 for October 20, 2009
Finding: The project proponent may consider recording the locations of animal and poacher sightings
using a GPS. Also, the project proponent may consider observing characteristics of the population
structure of wildlife species.
Proponent Response on October 24
our Daily Ranger Patrol Sheet to include GPS location and population characteristics, and as this is the
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
55
None
Biodiversity Impact Monitoring
The project proponents must have an initial monitoring plan to quantify and document the changes in
biodiversity resulting from the project activities (within and outside the project boundaries). The
monitoring plan must identify the types of measurements, the sampling method, and the frequency of
Since developing a full biodiversity-monitoring plan can be costly, it is accepted that some of the plan
details may not be fully defined at the design stage, when projects are being validated against the
Standards. This is acceptable as long as there is an explicit commitment to develop and implement a
Develop an initial plan for selecting biodiversity variables to be monitored and the
frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the
ives and to anticipated impacts (positive and negative).
The project proponent has highlighted a monitoring schedule that will be used in Wildlife
Works REDD project and also listed a number of variables in the PDD that will be monitored with a
The project proponent however should consider recording the locations of animal and poacher sightings
Yes No N/A
None
None
OFI Number 4 of 4 for October 20, 2009
The project proponent may consider recording the locations of animal and poacher sightings
using a GPS. Also, the project proponent may consider observing characteristics of the population
October 24, 2009: This is an excellent suggestion and we have now adapted
our Daily Ranger Patrol Sheet to include GPS location and population characteristics, and as this is the
The project proponents must have an initial monitoring plan to quantify and document the changes in
activities (within and outside the project boundaries). The
monitoring plan must identify the types of measurements, the sampling method, and the frequency of
that some of the plan
details may not be fully defined at the design stage, when projects are being validated against the
Standards. This is acceptable as long as there is an explicit commitment to develop and implement a
Develop an initial plan for selecting biodiversity variables to be monitored and the
frequency of monitoring and reporting to ensure that monitoring variables are directly linked to the
The project proponent has highlighted a monitoring schedule that will be used in Wildlife
Works REDD project and also listed a number of variables in the PDD that will be monitored with a
The project proponent however should consider recording the locations of animal and poacher sightings
The project proponent may consider recording the locations of animal and poacher sightings
using a GPS. Also, the project proponent may consider observing characteristics of the population
This is an excellent suggestion and we have now adapted
our Daily Ranger Patrol Sheet to include GPS location and population characteristics, and as this is the
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
primary instrument for daily monitor
in every day by the three teams of Rangers in the bush, we believe this will provide us more granular
data on Biodiversity in the Project Area. We believe this fully address this OFI
considered closed.
Validator Response: NA
Indicator B3.2. Develop an initial plan for assessing the effectiveness of measures used to maintain or
enhance High Conservation Values related to globally, regionally or nationally
(G1.8.1-3) present in the project zone.
Findings: The project proponent stated in the revised PDD how Wildlife Works has used the rangers to
assess species richness in Rukinga ecosystem, avert illegal activities such as grazing o
and incidence of fire.
The intention to expand monitoring schedule to enhance High Conservation Values related to globally,
regionally or nationally significant biodiversity (G1.8.1
strengthen the species monitoring plan.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator B3.3. Commit to developing a full monitoring plan within six months of the project start date
or within twelve months of validation against the Standards and to disseminate this plan and the results
of monitoring, ensuring that they are made publicly available on the internet and are communicated to
the communities and other stakeholders.
Findings: At the time of the site visit, the project proponent had not fully developed a full monitoring
plan. However in the revised PDD, the project proponent has committed to develop full monitoring plan
within twelve months of validation against the Standards
He also committed to disseminate the plan and the results of monitoring, ensuring that they are made
publicly available on the internet and are communicated to the communities and other stakeholders
Conformance:
Non-Conformity Reports:
New Information Requests:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
56
primary instrument for daily monitoring of the health of the Biodiversity in the Project Area, and is filled
in every day by the three teams of Rangers in the bush, we believe this will provide us more granular
data on Biodiversity in the Project Area. We believe this fully address this OFI and this should now be
Develop an initial plan for assessing the effectiveness of measures used to maintain or
enhance High Conservation Values related to globally, regionally or nationally significant biodiversity
present in the project zone.
The project proponent stated in the revised PDD how Wildlife Works has used the rangers to
assess species richness in Rukinga ecosystem, avert illegal activities such as grazing o
The intention to expand monitoring schedule to enhance High Conservation Values related to globally,
regionally or nationally significant biodiversity (G1.8.1-3) present in the project zone is ideal too and will
strengthen the species monitoring plan.
Yes No N/A
See NCR Number 2 of 19 for October 20, 2009
None
None
Commit to developing a full monitoring plan within six months of the project start date
or within twelve months of validation against the Standards and to disseminate this plan and the results
ensuring that they are made publicly available on the internet and are communicated to
the communities and other stakeholders.
At the time of the site visit, the project proponent had not fully developed a full monitoring
revised PDD, the project proponent has committed to develop full monitoring plan
within twelve months of validation against the Standards
He also committed to disseminate the plan and the results of monitoring, ensuring that they are made
le on the internet and are communicated to the communities and other stakeholders
Yes No N/A
None
None
ing of the health of the Biodiversity in the Project Area, and is filled
in every day by the three teams of Rangers in the bush, we believe this will provide us more granular
and this should now be
Develop an initial plan for assessing the effectiveness of measures used to maintain or
significant biodiversity
The project proponent stated in the revised PDD how Wildlife Works has used the rangers to
assess species richness in Rukinga ecosystem, avert illegal activities such as grazing of cattle, poaching
The intention to expand monitoring schedule to enhance High Conservation Values related to globally,
3) present in the project zone is ideal too and will
NCR Number 2 of 19 for October 20, 2009
Commit to developing a full monitoring plan within six months of the project start date
or within twelve months of validation against the Standards and to disseminate this plan and the results
ensuring that they are made publicly available on the internet and are communicated to
At the time of the site visit, the project proponent had not fully developed a full monitoring
revised PDD, the project proponent has committed to develop full monitoring plan
He also committed to disseminate the plan and the results of monitoring, ensuring that they are made
le on the internet and are communicated to the communities and other stakeholders
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Opportunities for Improvement:
3.6. Gold Level Section
3.6.1. GL1 – Climate Change Adaptation Bene
This Gold Level Climate Change Adaptation Benefits criterion identifies projects that will provide
significant support to assist communities and/or biodiversity in adapting to the impacts of climate
change. Anticipated local climate change and climate variability within the project zone could potentially
affect communities and biodiversity during the life of the project and beyond.
biodiversity in some areas of the world will be more vulnerable to the negative impacts of these changes
due to: vulnerability of key crops or production systems to climatic changes; lack of diversity of
livelihood resources and inadequate
strategies; and high levels of threat to species survival from habitat fragmentation. Land
projects have the potential to help local communities and biodiversity adapt to climate c
diversifying revenues and livelihood strategies; maintaining valuable ecosystem services such as
hydrological regulation, pollination, pest control and soil fertility; and increasing habitat connectivity
across a range of habitat and climate type
Indicators
The project proponents must:
Indicator GL1.1. Identify likely regional climate change and climate variability scenarios and impacts,
using available studies, and identify potential changes in the local land
change scenarios in the absence of the project.
Findings: The likely regional climate change and variability scenarios and impacts are identified in
Section GL1.1 of the revised PDD. These scenarios were supplemented with available studies (see
Number 5 of 5 for October 20, 2009
in the PDD seem accurate based on the references provided.
Conformance:
Non-Conformity Reports:
New Information Requests:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
57
None
Climate Change Adaptation Benefits
This Gold Level Climate Change Adaptation Benefits criterion identifies projects that will provide
communities and/or biodiversity in adapting to the impacts of climate
Anticipated local climate change and climate variability within the project zone could potentially
communities and biodiversity during the life of the project and beyond.
some areas of the world will be more vulnerable to the negative impacts of these changes
vulnerability of key crops or production systems to climatic changes; lack of diversity of
resources and inadequate resources, institutions and capacity to develop new livelihood
high levels of threat to species survival from habitat fragmentation. Land
potential to help local communities and biodiversity adapt to climate c
and livelihood strategies; maintaining valuable ecosystem services such as
pollination, pest control and soil fertility; and increasing habitat connectivity
climate types.
Identify likely regional climate change and climate variability scenarios and impacts,
available studies, and identify potential changes in the local land-use scenario due to these
change scenarios in the absence of the project.
The likely regional climate change and variability scenarios and impacts are identified in
Section GL1.1 of the revised PDD. These scenarios were supplemented with available studies (see
Number 5 of 5 for October 20, 2009). The identified potential changes in the local land
in the PDD seem accurate based on the references provided.
Yes No N/A
None
This Gold Level Climate Change Adaptation Benefits criterion identifies projects that will provide
communities and/or biodiversity in adapting to the impacts of climate
Anticipated local climate change and climate variability within the project zone could potentially
communities and biodiversity during the life of the project and beyond. Communities and
some areas of the world will be more vulnerable to the negative impacts of these changes
vulnerability of key crops or production systems to climatic changes; lack of diversity of
resources, institutions and capacity to develop new livelihood
high levels of threat to species survival from habitat fragmentation. Land-based carbon
potential to help local communities and biodiversity adapt to climate change by:
and livelihood strategies; maintaining valuable ecosystem services such as
pollination, pest control and soil fertility; and increasing habitat connectivity
Identify likely regional climate change and climate variability scenarios and impacts,
use scenario due to these climate
The likely regional climate change and variability scenarios and impacts are identified in
Section GL1.1 of the revised PDD. These scenarios were supplemented with available studies (see NIR
The identified potential changes in the local land-use as described
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
NIR Number 5 of 5 for October 20, 2009
Finding: Provide references to available studies used to identify likely regional climate change and
climate variability scenarios.
Proponent Response on October 24
on Climate Change in Kenya, East Africa and Sub
included that text below. We believe this adequately addresses this finding and ask that the finding NIR
#5 be closed.
Validator Response: The response is adequate.
Opportunities for Improvement:
Indicator GL1.2.Identify any risks to the project’s climate, community and biodiversity benefits resulting
from likely climate change and climate variability impacts and explain how these risks will be
Findings: Given the likely climate change impacts described in Section GL1.1 of the revised PDD, the
project proponent has identified several risks to the project’s benefits: scarcity in food would affect the
demand for bush meat poached from the project
animals, increased pressure for cattle grazing within the project area and scarcity of water in general.
These identified risks are reasonable given the li
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator GL1.3. Demonstrate that current or anticipated climate changes are having or are likely to
have an impact on the well-being of communities
project zone and surrounding regions.
Findings: In Section GL1.2, the project proponent has demonstrated that current
changes are likely to have an impact on
biodiversity in the project zone. This section was supplemented for Indicator GL1.3 based on a finding
during the course of the audit (see
impacts are also likely to have an impact on
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
58
20, 2009
Provide references to available studies used to identify likely regional climate change and
October 24, 2009: We have added a list of published references to the impact
ange in Kenya, East Africa and Sub-Saharan Africa to the PDD in section GL1.1. We have
included that text below. We believe this adequately addresses this finding and ask that the finding NIR
The response is adequate.
None
Identify any risks to the project’s climate, community and biodiversity benefits resulting
likely climate change and climate variability impacts and explain how these risks will be
Given the likely climate change impacts described in Section GL1.1 of the revised PDD, the
project proponent has identified several risks to the project’s benefits: scarcity in food would affect the
demand for bush meat poached from the project area, degradation of the natural food sources for wild
animals, increased pressure for cattle grazing within the project area and scarcity of water in general.
These identified risks are reasonable given the likely climate change impacts for local land
Yes No N/A
None
None
None
Demonstrate that current or anticipated climate changes are having or are likely to
being of communities and/or the conservation status of biodiversity
zone and surrounding regions.
In Section GL1.2, the project proponent has demonstrated that current or anticipated climate
changes are likely to have an impact on the well-being of communities and the conse
zone. This section was supplemented for Indicator GL1.3 based on a finding
during the course of the audit (see Number 18 of 19 for October 20, 2009). These anticipated climate
impacts are also likely to have an impact on surrounding regions.
Yes No N/A
See NCR Number 18 of 19 for October 20, 2009
Provide references to available studies used to identify likely regional climate change and
We have added a list of published references to the impact
Saharan Africa to the PDD in section GL1.1. We have
included that text below. We believe this adequately addresses this finding and ask that the finding NIR
Identify any risks to the project’s climate, community and biodiversity benefits resulting
likely climate change and climate variability impacts and explain how these risks will be mitigated.
Given the likely climate change impacts described in Section GL1.1 of the revised PDD, the
project proponent has identified several risks to the project’s benefits: scarcity in food would affect the
area, degradation of the natural food sources for wild
animals, increased pressure for cattle grazing within the project area and scarcity of water in general.
kely climate change impacts for local land-use.
Demonstrate that current or anticipated climate changes are having or are likely to
rvation status of biodiversity in the
or anticipated climate
the conservation status of
zone. This section was supplemented for Indicator GL1.3 based on a finding
These anticipated climate
NCR Number 18 of 19 for October 20, 2009
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
New Information Requests:
Opportunities for Improvement:
Indicator GL1.4. Demonstrate that the project activities will
adapt to the probable impacts of climate change.
Findings: As described in the revised PDD and observed during the site visit, the project proponent
demonstrates that the project activities will assist communities and biodiversity to adapt to the
probable impact of climate change. The project proponent will: create livelihoods alternative to
agriculture, improve efficiency of agriculture production and protection of t
poachers.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.6.2. GL2 – Exceptional Community Benefits
This Gold Level Exceptional Community Benefits criterion recognizes project approaches that are
explicitly pro-poor in terms of targeting benefits to globally poorer communities
vulnerable households and individuals within them. In so doing, land
significant contribution to reducing the poverty an
groups. Given that poorer people typically have less access to land and other natural assets, this
optional criterion requires innovative approaches that enable poorer households to participate
effectively in land-based carbon activities. Furthermore, this criterion requires that the project will ‘do
no harm’ to poorer and more vulnerable members of the communities, by establishing that no member
of a poorer or more vulnerable social group will experience a n
rights.
Indicators
Project proponents must:
Indicator GL2.1. Demonstrate that the project zone is in a low human development country OR in an
administrative area of a medium or high human development country in wh
population of that area is below the national poverty line.
Findings: The project proponent has elected not to pursue these optional Gold Level criteria.
Conformance:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
59
None
None
Demonstrate that the project activities will assist communities and/or
the probable impacts of climate change.
As described in the revised PDD and observed during the site visit, the project proponent
the project activities will assist communities and biodiversity to adapt to the
probable impact of climate change. The project proponent will: create livelihoods alternative to
agriculture, improve efficiency of agriculture production and protection of the project area from
Yes No N/A
None
None
None
Exceptional Community Benefits
This Gold Level Exceptional Community Benefits criterion recognizes project approaches that are
poor in terms of targeting benefits to globally poorer communities and
vulnerable households and individuals within them. In so doing, land-based carbon projects can make a
significant contribution to reducing the poverty and enhancing the sustainable livelihoods of these
Given that poorer people typically have less access to land and other natural assets, this
requires innovative approaches that enable poorer households to participate
carbon activities. Furthermore, this criterion requires that the project will ‘do
vulnerable members of the communities, by establishing that no member
social group will experience a net negative impact on their well
Demonstrate that the project zone is in a low human development country OR in an
administrative area of a medium or high human development country in which at least 50% of
population of that area is below the national poverty line.
The project proponent has elected not to pursue these optional Gold Level criteria.
Yes No N/A
and/or biodiversity to
As described in the revised PDD and observed during the site visit, the project proponent
the project activities will assist communities and biodiversity to adapt to the
probable impact of climate change. The project proponent will: create livelihoods alternative to
he project area from
This Gold Level Exceptional Community Benefits criterion recognizes project approaches that are
and the poorer, more
based carbon projects can make a
d enhancing the sustainable livelihoods of these
Given that poorer people typically have less access to land and other natural assets, this
requires innovative approaches that enable poorer households to participate
carbon activities. Furthermore, this criterion requires that the project will ‘do
vulnerable members of the communities, by establishing that no member
et negative impact on their well-being or
Demonstrate that the project zone is in a low human development country OR in an
ich at least 50% of the
The project proponent has elected not to pursue these optional Gold Level criteria.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator GL2.2. Demonstrate that at least 50% of households within the lowest category of well
(e.g., poorest quartile) of the community are likely to benefit substantially from the pr
Findings: The project proponent has elected not to pursue these optional Gold Level criteria.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator GL2.3. Demonstrate that any barriers or risks that might prevent benefits going to poorer
households have been identified and addressed in order to increase the probable flow of benefits
poorer households.
Findings: The project proponent has elected not to pursue these optional Gold Level criteria.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Indicator GL2.4. Demonstrate that measures have been taken to identify any poorer and more
vulnerable households and individuals whose well
project, and that the project design includes measures to avoid any such impacts.
impacts are unavoidable, demonstrate that they will be effectively mitigated.
Findings: The project proponent has elected not to pursue these optional Gold Level criteria.
Conformance:
Non-Conformity Reports:
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
60
None
None
None
Demonstrate that at least 50% of households within the lowest category of well
poorest quartile) of the community are likely to benefit substantially from the project.
The project proponent has elected not to pursue these optional Gold Level criteria.
Yes No N/A
None
None
None
Demonstrate that any barriers or risks that might prevent benefits going to poorer
have been identified and addressed in order to increase the probable flow of benefits
The project proponent has elected not to pursue these optional Gold Level criteria.
Yes No N/A
None
None
None
Demonstrate that measures have been taken to identify any poorer and more
households and individuals whose well-being or poverty may be negatively affected by the
project, and that the project design includes measures to avoid any such impacts.
impacts are unavoidable, demonstrate that they will be effectively mitigated.
The project proponent has elected not to pursue these optional Gold Level criteria.
Yes No N/A
None
Demonstrate that at least 50% of households within the lowest category of well-being
oject.
The project proponent has elected not to pursue these optional Gold Level criteria.
Demonstrate that any barriers or risks that might prevent benefits going to poorer
have been identified and addressed in order to increase the probable flow of benefits to
The project proponent has elected not to pursue these optional Gold Level criteria.
Demonstrate that measures have been taken to identify any poorer and more
being or poverty may be negatively affected by the
project, and that the project design includes measures to avoid any such impacts. Where negative
The project proponent has elected not to pursue these optional Gold Level criteria.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
New Information Requests:
Opportunities for Improvement:
Indicator GL2.5. Demonstrate that community impact monitoring will be able to identify positive and
negative impacts on poorer and more vulnerable groups. The social impact monitoring must take a
differentiated approach that can identify positive and negative impacts on
individuals and other disadvantaged groups, including women.
Findings: The project proponent has elected not to pursue these optional Gold Level criteria.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
3.6.3. GL3 – Exceptional Biodiversity Benefits
All projects conforming to the Standards must demonstrate net positive impacts on biodiversity within
their project zone. This Gold Level
conserve biodiversity at sites of global significance for biodiversity conservation. Sites meeting this
optional criterion must be based on the Key Biodiversity Area (KBA) framework of vu
irreplaceability. These criteria are defined in terms of species and population threat levels, since these
are the most clearly defined elements of biodiversity. These scientifically based criteria are drawn from
existing best practices that have been used, to date, to identify important sites for biodiversity in over
173 countries.
Indicators
Project proponents must demonstrate that the project zone includes a site of high biodiversity
conservation priority by meeting either the vulnerabili
Indicator GL3.1. Vulnerability
Regular occurrence of a globally threatened species (according to the IUCN Red List) at the site:
1.1. Critically Endangered (CR) and Endangered (EN) species
1.2. Vulnerable species (VU) - presence of at least 30 individuals or 10 pairs.
Findings: The project area is inhabited by African elephant (Loxodonta africana) and Grevy’s Zebras
(Equus grevyi), both are globally threatened
The presence of black rhino in both East and West National parks, a critically endangered wildlife species
makes the project area a very important corridor of wildlife.
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
61
None
None
Demonstrate that community impact monitoring will be able to identify positive and
impacts on poorer and more vulnerable groups. The social impact monitoring must take a
differentiated approach that can identify positive and negative impacts on poorer households and
individuals and other disadvantaged groups, including women.
The project proponent has elected not to pursue these optional Gold Level criteria.
Yes No N/A
None
None
None
Exceptional Biodiversity Benefits
All projects conforming to the Standards must demonstrate net positive impacts on biodiversity within
their project zone. This Gold Level Exceptional Biodiversity Benefits criterion identifies projects that
conserve biodiversity at sites of global significance for biodiversity conservation. Sites meeting this
optional criterion must be based on the Key Biodiversity Area (KBA) framework of vu
irreplaceability. These criteria are defined in terms of species and population threat levels, since these
are the most clearly defined elements of biodiversity. These scientifically based criteria are drawn from
t have been used, to date, to identify important sites for biodiversity in over
Project proponents must demonstrate that the project zone includes a site of high biodiversity
conservation priority by meeting either the vulnerability or irreplaceability criteria defined below:
Regular occurrence of a globally threatened species (according to the IUCN Red List) at the site:
1.1. Critically Endangered (CR) and Endangered (EN) species - presence of at least a single
presence of at least 30 individuals or 10 pairs.
The project area is inhabited by African elephant (Loxodonta africana) and Grevy’s Zebras
(Equus grevyi), both are globally threatened species according to the IUCN Red List.
The presence of black rhino in both East and West National parks, a critically endangered wildlife species
makes the project area a very important corridor of wildlife.
Demonstrate that community impact monitoring will be able to identify positive and
impacts on poorer and more vulnerable groups. The social impact monitoring must take a
poorer households and
The project proponent has elected not to pursue these optional Gold Level criteria.
All projects conforming to the Standards must demonstrate net positive impacts on biodiversity within
Exceptional Biodiversity Benefits criterion identifies projects that
conserve biodiversity at sites of global significance for biodiversity conservation. Sites meeting this
optional criterion must be based on the Key Biodiversity Area (KBA) framework of vulnerability and
irreplaceability. These criteria are defined in terms of species and population threat levels, since these
are the most clearly defined elements of biodiversity. These scientifically based criteria are drawn from
t have been used, to date, to identify important sites for biodiversity in over
Project proponents must demonstrate that the project zone includes a site of high biodiversity
irreplaceability criteria defined below:
Regular occurrence of a globally threatened species (according to the IUCN Red List) at the site:
east a single individual; or
The project area is inhabited by African elephant (Loxodonta africana) and Grevy’s Zebras
The presence of black rhino in both East and West National parks, a critically endangered wildlife species
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1
Other threatened species, Critically
birds, reptiles, amphibians or even species of insects etc. These require proper research to establish a
more impressive check list of all the species of the ranch.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
Or,
Indicator GL3.1. Irreplaceability
A minimum proportion of a species’ global population present at the site at any stage of the
lifecycle according to the following thresholds:
2.1. Restricted-range species - species with a global range less than 50,000 km2
population at the site; or
2.2. Species with large but clumped distributions
2.3. Globally significant congregations
2.4. Globally significant source populations
Findings: The information provided by the project proponent regarding Gr
above. 3% of the global population of the species is found at the project site making it a globally
significant source population.
Conformance:
Non-Conformity Reports:
New Information Requests:
Opportunities for Improvement:
4.0 CCB Validation Conclusion
Following completion of SCS’s duly
Corridor REDD Project conforms to the CCBA Climate, Community and Biodiversity Project Design
Standards (Second Edition) at the Gold Level
CCB_WildlifeWorks_RPT_ValidationReport_Final2.1_122009
62
Other threatened species, Critically Endangered (CE) and vulnerable species (VU) may be nocturnal,
birds, reptiles, amphibians or even species of insects etc. These require proper research to establish a
more impressive check list of all the species of the ranch.
Yes No N/A
None
None
None
A minimum proportion of a species’ global population present at the site at any stage of the
following thresholds:
species with a global range less than 50,000 km2
2.2. Species with large but clumped distributions - 5% of the global population at the site; or
significant congregations - 1% of the global population seasonally at the site; or
2.4. Globally significant source populations - 1% of the global population at the site.
The information provided by the project proponent regarding Grevy’s Zebr
above. 3% of the global population of the species is found at the project site making it a globally
Yes No N/A
None
None
None
Validation Conclusion
Following completion of SCS’s duly-accredited validation process, it is our opinion that
conforms to the CCBA Climate, Community and Biodiversity Project Design
Gold Level (see Appendix A).
Endangered (CE) and vulnerable species (VU) may be nocturnal,
birds, reptiles, amphibians or even species of insects etc. These require proper research to establish a
A minimum proportion of a species’ global population present at the site at any stage of the species’
species with a global range less than 50,000 km2 and 5% of global
5% of the global population at the site; or
1% of the global population seasonally at the site; or
’s Zebra conforms to 2.4
above. 3% of the global population of the species is found at the project site making it a globally
accredited validation process, it is our opinion that The Kasigau
conforms to the CCBA Climate, Community and Biodiversity Project Design
CCBA Project Validation Report Appendix A Page A-1
CCBA Compliance Checklist – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
General Section Conformance
G1. Original Conditions in the Project Area (Required) Yes No
G2. Baseline Projections (Required) Yes No
G3. Project Design and Goals (Required) Yes No
G4. Management Capacity and Best Practices (Required) Yes No
G5. Legal Status and Property Rights (Required) Yes No
Climate Section
CL1. Net Positive Climate Impacts (Required) Yes No
CL2. Offsite Climate Impacts (“Leakage”) (Required) Yes No
CL3. Climate Impact Monitoring (Required) Yes No
Community Section
CM1. Net Positive Community Impacts (Required) Yes No
CM2. Offsite Community Impacts (Required) Yes No
CM3. Community Impact Monitoring (Required) Yes No
Biodiversity Section
B1. Net Positive Biodiversity Impacts (Required) Yes No
B2. Offsite Biodiversity Impacts (Required) Yes No
B3. Biodiversity Impact Monitoring (Required) Yes No
Gold Section GL1. Climate Change Adaptation Benefits (Optional) Yes No
GL2. Exceptional Community Benefits (Optional) Yes No
GL3. Exceptional Biodiversity Benefits (Optional) Yes No
CCBA Validation Level Attained:
APPROVED (all requirements met)
GOLD (all requirements and also at least one optional Gold Level criterion met
CCBA Project Validation Report Appendix B Page B-1
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
I would like to comment on the proposed Project Design Document for Rukinga Sanctuary carbon
project, the Kasigau corridor Reduced Emissions from Deforestation and Degradation (REDD) project.
Since the arrival of Wildlife Works in the year 1998, the community has benefited a lot. As I am part of
the community, I have personally benefited through secondary education sponsorship programme,
which Wildlife Works had introduced in 2002. Without Wildlife Works, education could have been only a
dream to me.
Wildlife Works projects have brought lots of benefits to most of the community members. Some of the
benefits include; Employment in the EPZ factory, wildlife rangers and the green house tree planting. All
these have so far improved the community’s living standard by increasing their monthly incomes.
Another benefit is the improvement of learning institutions such as primary and secondary schools. In
the 1990s, children used to go learn in grass-thatched classrooms. These rooms forced the children to go
home once there were indications that the rains were coming because they were leaking. With Wildlife
Works, children are staying in classes without fear. Those students who work hard and perform well are
sponsored by well-wishers through Wildlife Works.
Therefore, the proposed REDD project will highly benefit more community members. Most people near
the project zone are poor and some of them depend on agriculture and cutting down of trees for
charcoal. These lead to deforestation and hence pose problems. If the REDD project starts, there will
automatically be more employment opportunities for many locals. All those people who were initially
involved in environmental degradation activities will then be involved in constructive activities and
hence maintenance of trees in the area. This project will also make the community to be more exposed
because most tourists will come to the sanctuary and visit the community and schools too. Most of the
community members are not used to western people therefore frequent visits by the tourists will
expose these people more and more. More sponsorship for children is also expected due to increased
number of sponsors from abroad.
James Ruwa
GAFFER HIV/AIDS PROJECT COORDINATOR.
September 24, 2009
I am really encouraging the introduction of Kasigau corridor REDD project, for sure a lot will be done.
I knew wildlife works ten years ago, when they were handing over the classrooms they helped to build in
Buguta, Kale and Marungu where the ceremony was held.
I used to work with forestry department by that time and wildlife works invited me to help the guest of
honour with the planting of the ceremonial trees. From that time I got very much involved with them
especially with the training of the communities how to establish tree nurseries.
To help the communities living around Mt. Kasigau to conserve the mountain, wildlife works conducted
vegetation survey to find how much damage is done and involved the locals by identifying the plants in
each plot.
Wildlife works helped sponsoring bright children so that they could get good education; get good job
and stop poaching and making charcoal.
CCBA Project Validation Report Appendix B Page B-2
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
To continue protecting Kasigau corridor, wildlife works helped with the training of community scouts
who patrols around the village to educate the communities the importance of wildlife and to remove
the snares put around the community’s farms. If it wasn’t wildlife works, Rukinga ranch could have been
encroached by the people living adjacent to it and could also make the movement of elephants from
Tsavo east to west impossible, as this is their migratory corridor.
Long Live Wildlife Works
Keep on working with communities.
Kenneth Nyange
Project Manager – Camp Tsavo
October 9, 2009
I’ personal feel that the proposed project has really benefited the community around this place. There is
a big improvement in schools, which have been guided by Wildlife Works. Since it was started in the
year 2002, to mention a few Wildlife Works has helped by constructing new classrooms, renovating
classes, putting up water tanks and buying desks for pupils. All these have led to the improvement of the
academic standards of the concerned schools.
Apart from this Wildlife works has sponsored so many students to higher education. I believe in future
the living standards of the community around will be highly improved. If it were not Wildlife Works then
standards of living will remain poor for so many years. To add on this Wildlife woks has employed
people to the Epz factory and others have been employed as Rangers at Rukinga sanctuary. This has
improved the living standards of the people around. I am sure the proposed REDD project will help and
benefit Members of the community around even more. I conclude by saying since Wildlife Works was
introduced, the community has learnt that poaching of animals is not good for it reduces economy of
our country. The community have also discovered that they should conserve and plant more trees so
that they can get rains and water.
Yours at service
Peterson Msinga Mwatate
Head teacher- Kale primary school.
October 9, 2009
I’ Renson Dio, Taita ranching company limited Director cum Treasurer applaud this project to take off
immediately as at now the current environmental climate change is leading the world to disaster.
Being a resident of Kasigau location and border Marungu Location, I have personal benefited from
Wildlife Works and the locals too, like sponsorship programs of our pupils to secondary schools and
colleges not forgetting university levels, employment to our locals in Epz Maungu, construction of
classrooms. In Taita Ranch headquarters the ranch benefited from Wildlife Works through giving four
buffalos that were being kept as in a zoo by providing maize germ during this drought period. Taita
Ranching through Mr. Renson Dio has benefited from Wildlife Works by being given vehicles for patrols
by Mr. Rob Dodson in our Ranch, to mention but a few.
I propose the project to take off immediately.
CCBA Project Validation Report Appendix B Page B-3
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
Thanks
Renson Dio
Director
Taita Ranching Co. Ltd.
October 8, 2009
Comment A
This comment concerns the following aspects of the project.
1. G3 –project design and goals- schools construction and bursary scheme
2. CM1.1 – Estimate impacts on communities. While the achievements of the project are acknowledged
and highly appreciated, there is room for improvement in order to justify the assertion that there are no
negative impacts. For example facilities being provided for primary schools around Kasigau need to be
extended to the very few secondary schools in the area. This will remove a feeling that students going
from primary school to secondary school are moving a step backward rather than forward.
Comment B
‘Climate section’ is lacking relevant data on the rates of evaporation and transpiration associated with
the eco-system in general and the area species of vegetations in particular.
Comment C
Annex D: Village profiles should be edited so as to enhance its credibility. There is further more in
sufficient supporting statistical information to highlight claims of achievements of the project.
Engineer C.M Mwakulomba
Kasigau Location
October 9, 2009
Auditor’s Note: The standard does not require that evaporation and transpiration associated with the
ecosystem or species of vegetation be given. It is the opinion of the validator that the village profiles
provided in the PDD are sufficient given the diversity of livelihoods and economies relative to other
CCBA projects.
In regards to the respect that I uphold for Wildlife Works, as person, since I saw it as an organization to
the time I came to meet it, I must say that if you don’t know who they are then you better find out
because its in involving yourself with them that you get to find the gold that you either have been
throwing or the destruction that you can prevent yourself from.
As a person that is part of Wildlife Works project since 2002, through an education sponsorship program
it’s quite visible that Wildlife works cares for the well being of the community and the environment as a
whole. I also have success stories that were initiated by wildlife works, throughout my sponsorship
program, where we were informed on the importance of conserving the environment, hence started a
project of planting trees to prevent the land from deforestation, and land erosions.
CCBA Project Validation Report Appendix B Page B-4
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
It’s from Wildlife Works that people have learnt how conserve the environment, how to live with the
wildlife, importance of Eco-system, effects of poaching, methods of farming within the community,
hence making a relationship between animals and the people living along the rukinga sanctuary.
Economically, the communities that live around rukinga have had benefits through employment in the
sanctuary, wardens, rangers etc, bright children have had a chance of studying to the 0-level (secondary
education), also to the A-level( University) that can enable them secure job opportunities and be part of
those who bring a change to the community.
Socially, the communities have grown in the sense that they known the importance of a clean
environment, why they need to reduce deforestation, importance of trees, the nature of their
environment, how to cope well with it and now the gaffer project that gives awareness of HIV/AIDS, and
reducing the idleness of the youths through involving them in events like sports.
Wildlife works has been supportive, educative both in the social and the economic lifestyles and we
hope that it will continue to dwell to see the fruits of the trees that it has planted for the betterment of
the wildlife, the community, our lifestyle and our land as a whole.
I fully support the efforts of Wildlife Works and all its projects including the REDD project in making our
land; people and animals have the best place for living in peace and togetherness.
Regards,
Sylvester Izaka,
IT & Network support engineer. (CBS)
October 8, 2009
Ever since the year the year 2000 when I came to know what actually Wildlife Works was, this
organization has been of very great importance to many. Not only to individuals but also the community
at large. I strongly believe that with the introduction of the Kasigau corridor REDD project, there will be
even more benefits to the community.
Education could have been history to most people in this region. Through Wildlife Works classrooms
were built in most primary schools in this region. This ensured smooth running of school programs
without being affected by the weather changes since the formerly grass thatched classrooms were out
of use during rainy season. Wildlife Works ensured that education of the bright children does not end at
primary level but it is continued to high school. This was done through introduction of the sponsorship
program and really benefited may including me.
Wildlife Works has also educated the community so as to live peacefully with wild animals in order to
reduce human wildlife conflict. This has in return reduced poaching in the region since most people are
now well informed with the dangers of bush meat.
I strongly support the introduction of the Kasigau corridor REDD project because it will create
employment to most people in our community and the standard of living will change. Many children in
this region will be able to go to high school and also a lot more trees will be planted in the region which
will attract rain leading to improved agriculture.
CCBA Project Validation Report Appendix B Page B-5
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
Rehema Mwavuo
Volunteer Teacher – Marungu Secondary School.
Marungu Location, Nyangala Division, Voi District
September 30, 2009
Since the inception of Wildlife Works 11 years ago, great strands have been achieved. The most
noticeable one being cited here: -
a) There has been full acceptance of Wildlife Works as part of our inheritance and so great measures
have been put in place to conserve and co-existed. This has been due to education provided by Wildlife
Works and other stakeholders.
b) The town of Maungu has grown, Wildlife Works has provided market for the local produce, it has
cleaned and provided cleaning facilities and inseminated the inhabitants the need to live dirty free
environment.
c) Wildlife Works – Maungu has offered employment to many locals i.e. security, drivers, mechanics,
clerks, rangers etc curbing the rural urban migration and uplifting the living standards of our people.
d) Wildlife Works – Maungu has initiated, supported renovated and constructed classrooms. They have
also contributed for other school related facilities in many neighboring schools, a measure ‘‘we” as
Members of the community appreciated.
e) The GAFFER, which started through Wildlife Works, has given alternatives to our idle youth. They
have been made occupied, shown the importance of sports, appreciating and accepting one another
and accommodating other persons weaknesses through the sports spirit, a gesture that has made rather
hostile communities to co-exist peacefully.
f) The GAFFER has also initiated the planting of trees in different schools and other public institutions
around Wildlife Works. The community has really benefited. We fully support the REDD project.
g) The education trust under umbrella KELIMU TRUST has helped our destitute children to access hire
school education so far some have even joined tertiary institutions still under KELIMU TRUST. Wildlife
Works - Maungu has an upper hand in this and therefore it’s hard to detach this benefit from them.
h) During hard times such as drought and other natural disasters Wildlife Works come in hand to aid the
affected people. This has been evident recently when the aged and the poor got relief food from Born
Free organization still associated with Wildlife Works – Maungu.
And a move towards enhancing Wildlife Works will definitely assist us positively, their priority areas are
always friendly and we are sure the carbon project, Kasigau corridor Reduced Emission from
Deforestation and Degradation (REDD) will be a great advantage to us. The project diversity will finally
explore to tap rather the idle recourses likely to sum up more profit and benefit to Wildlife Works then
to us the surrounding community. The proposed REDD project will add value to the eco-system under
the umbrella of Wildlife Works. Care and security of our Wildlife will be assured.
CCBA Project Validation Report Appendix B Page B-6
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
Our area is trans-passed by a railway line, trans Africa highway, and pipeline station all heavy emitters of
carbon and carbon monoxide gasses. The carbon project (REDD) will absorb and reduce their entry into
the atmosphere hence curbing fully or reducing the rate of global warming, we the community at large
support the REDD project due to the above stated aspects.
Thank you
The resident – Maungu
Teacher and Instructor
V Wambua Masai
September 29, 2009
I as resident of Maungu, would like to welcome the Rukinga sanctuary REDD project. Wildlife Works
have done a lot to the community since they started operations in 1998. Children have been taken to
secondary school, I being among the beneficiaries of the program. All the bright kids from the poor
families were being sponsored for higher education, which was started from 2002.
Wildlife Works has also created employment to the community by employing the youth as Rangers,
Mass production machinist, and some at the green house project.
In 2002 Wildlife Works contributed about three hundred desks in Marasi primary school this is due to
the children who had no where to sit in class.
Wildlife Works is bordered by the poor community who, big percentage depend on the charcoal burning
and bush meat poaching for survival, therefore I will recommend for more projects in the area for more
job creation.
Last and not least I am praying to God if Wildlife Works have can stay for long time and also keep on
helping our people in Marungu community. Our living standard could not have been changed if Wildlife
Works was not there.
Yours sincerely
Antony Lundi
Voi constituency – Maungu office
October 3, 2009
I would like to comment on the above mentioned project for Rukinga sanctuary.
Environment
What I never thought of and has been done by the project on environment is: seedlings provision to the
local community, environment conservation within the area, which has led to a better and beautiful
environment, modern jikos were constructed for the community which uses few firewood and also
reduces heavy smoke to the atmosphere. On the sanitary has accompanied the community especially at
Maungu town on rubbish collection.
CCBA Project Validation Report Appendix B Page B-7
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
Wild animals have been conserved in the sanctuary, which has improved tourist attraction in Kenya
Education
The project has already assisted the community by improved education in the area by doing the
following: construction of classrooms, provision of desks, books and educating the bright student from
the poor families from form one to form four.
Employment
The project has economically assisted the community by employing the Rangers who assist on
environment, wildlife conservation and many other things.
Epz factory – by formation of the Epz many especially the youth got jobs.
Relief food
The project has assisted the community by provision on the relief food to the needy people.
In my opinion is to pray so that the project can be expanded to be a bigger project – We really
appreciate the project for all what has been done for us.
CHIEF’S OFFICE
THE MANAGER
WILDLIFE WORKS
P.O. BOX 310 – VOI
October 5, 2009
SASIGAU CORRIDOR REDD PROJECT- PUBLIC COMMENTS.
VOTE OF THANKS:
In your endeavors to educate, reduce poverty, conserve and protect the environment both flora and
fauna I give you kudos! Congratulations.
Your support in both primary and secondary class rooms construction, and providing higher education
support to high performers who are under – privileged is un- surpassed.
COMMENTS: RUKINGA SACTUARY
RE: FORESTATION
Encourage more tree nurseries and provide free seedling in exchange for any indigenous tree planted,
germinate seeds both indigenous, citrus fruits and climbers and disperse them aerially, and manually
near fertile wetlands and swamps during rain season.
WILDLIFE CONSERVATION
The long distance covered by wild life both grazers and browser etc is in search of water. Construct
more water pans and several boreholes, which can be wind-powered within the sanctuary.
SECURITY SURVEILANCE AND PROTECTION
Provide Rangers with sets of binoculars, V.H.F radios sets and construct strategic watchtower in flat
grassy areas to monitor and report cattle movement, wildlife poachers, wood loggers, smoke etc.
CONSTRUCT ELECTRIC FENCES IN WILDLIFE – HUMAN CORRIDORS.
CCBA Project Validation Report Appendix B Page B-8
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
The animal ingressions into human settlement areas are well known. While the highly mountains act as
a natural shield. Five key areas require attention, where cheap P.V.C poles and solar power electric
fencing can be erected
FOOD AID: FOR TREES PLANTED AND SURVIVING
The foodstuff occasionally provided by Wildlife Works Epz should be complemented by the tree planted
and surviving from the beneficiaries.
DISABLED PEOPLES
While Wildlife Works Epz has done so much to the community at large, it has not involved itself deeply
in the disabled societies, or individuals. Provide basic training or seminars to the disabled and assist
them with working tools example: shoes marker, carpenters, masons, electricians and brick marker etc.
ENEMIES OF THE SANCTUARY
Charcoal burners, tree cutter, poacher, honey hunters miners and prospective grass harvesters and
cattle grazers, to mention but a few.
Solution: Electric fence at the strategic entry points, community policing i.e. employ informers and
guards within the bordering community/ settlement.
Thanks you:
Briviant Shako – Technical Works
P.o. Box 25 Voi - Maungu
Email: [email protected]
TEL: 0726445458
October 9, 2009
Auditor’s Note: It is not feasible for the project proponents to build an electric fence or provide
surveillance to the degree suggested by this comment. The idea of installing fences was discussed
during the site visit; however, it was concluded that an electric fence is too expensive and would require
continual maintenance.
I would like to make my comments for the Project Design Document (PDD) for Kasigau corridor Reduced
Emission Deforestation and Degradation (REDD) project as follows:-
Mount Kasigau – The Project needs to cover the mountain area by planting more trees because this is
the only water source neighbouring the project zone. Like other water towers in the country, Mt.
Kasigau is one of the affected due to harvesting of sandalwood and its ecosystem degraded. There is
need to incorporate Mt. Kasigau by establishing tree nurseries in the villages around the mountain to
mitigate the adverse sandalwood destruction effects to strengthen the weakened ecosystem at the
water tower.
Mechanism should be set up to help the integrity of the project and help the local community from
exploitation forces within and without the project area.
We appreciate Wildlife Works because they have contributed to the social, economic and well-being of
the community living next to the project zone. In addition they have done improvements in schools
CCBA Project Validation Report Appendix B Page B-9
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
infrastructures, offering education bursaries to bright needy children in the community, aiding dame
scouts in de-snaring and arresting the game poachers, establishment of tree nurseries have created
environment awareness to the community.
Wildlife works also cooperate very well with the local community leaders in terms of development, like
for example they participate in most of the local Baraza’s to create wildlife and environment
conservation awareness. They contribute in clean ups of the towns within the project zone. The
community leaders also once assisted in eviction when the squatters invaded and developed part of
Rukinga Wildlife Sanctuary (5000 Acres).
This project zone is neighbored by farmlands with no cash crops to sustain farmers; the severe drought
that has exaggerated the area has forced most of the locals to destruct trees fro charcoal
burning/logging and poaching for livelihood. I will request for drought resistant cash crops like
jathropper and jojoba to be introduced in the farms neighboring the project zone in order to alleviate
poverty.
Pascal Kizaka
Chief of Kasigau Location, Voi/Kenya
September 28, 2009
I as an assistant chief of Maungu community, I do appreciate a lot to what Wildlife Works have done to
my people. Therefore I will highly support Kasigau corridor REDD project which is being implemented by
Wildlife Works. Below is what has been achieved by Wildlife Works for the last ten years:-
In education, the community has benefited a lot due to the sponsorships offered through Wildlife
Works. More than 50 kids have been sponsored to secondary school education and even some to
university level. Some of these kids have finished their education and are now working within the
community. These being the fruits of education, most of the parents are working hard to see their
children go to school.
We’ve been working together with Wildlife Works in environment conservation especially in cleaning
the towns. They have been helping the community with tools and materials for the clean ups activities,
at the same time provide seedlings for environment cover. Wildlife Works has also introduced
smokeless jikos to the community for clean environment.
The community has benefited a lot especially during drought seasons, the company together with other
related companies help in donation of aid food to the poorest families within the area of the project
zone.
Wildlife Works has created employment opportunities to the community from their projects within the
company, among the project are: EPZ eco-factory, Rukinga wildlife sanctuary, Green house project and
Jojoba research project.
I would like to congratulate Wildlife Works for all they have done to uplift the standard of living in this
community and therefore welcome the introduction of REDD project as we are still in need especially
water, this is still a major problem in the community and I hope it will be solved with the4 introduction
of REDD project.
CCBA Project Validation Report Appendix B Page B-10
Stakeholder Comments – The Kasigau Corridor REDD Project
Scientific Certification Systems
December 22, 2009
Thank you
Driscilah M. Ngele
Assistant Chief’s Office
Maungu Sub-Location
P.O.Box 134 – 80300
VOI
October 5, 2009