Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
FINAL
2002 OPERATIONS AND MAINTENANCE REPORT KEARSARGE METALLURGICAL CORPORATION
SUPERFUND SITE CONWAY, NEW HAMPSHIRE
Prepared for:
NEW HAMPSHIRE DEPARTMENT OF ENVIRONMENTAL SERVICES
6 Hazen Drive Concord, New Hampshire 03301
Prepared by:
WESTON SOLUTIONS, INC One Wall Street
Manchester, New Hampshire 03101-1501
May 2003
W.O. No. 01395.022.008
MNH|F:\USER\SHARE\KEARSARGE ESD DOCS\46949\TOC.DOC 6 OCTOBER 2003 i
MNH|F:\USER\SHARE\KEARSARGE ESD DOCS\46949\TOC.DOC 6 OCTOBER 2003 ii
TABLE OF CONTENTS
Section Page
1. INTRODUCTION ..................................................................................................... 1-1
2. GROUNDWATER EXTRACTION AND TREATMENT SYSTEM ..................... 2-1 2.1 SUMMARY OF VOLUMES PROCESSED .................................................... 2-1
2.2 INFLUENT/EFFLUENT QUALITY ............................................................... 2-2 2.3 UNIT PROCESS PERFORMANCE ................................................................ 2-4
2.3.1 Hobbs Street Wells ............................................................................... 2-4 2.3.2 Culvert Area Wells ............................................................................... 2-5 2.3.3 Groundwater Collection Trench and Associated Extraction Well .......... 2-6 2.3.4 Equalization and Metals Removal System ............................................ 2-6 2.3.5 Organic Contaminants Removal System............................................... 2-7
3. TREATMENT SYSTEM MAINTENANCE AND MODIFICATIONS ................. 3-1
4. GROUNDWATER SAMPLING AND ANALYSIS................................................. 4-1 4.1 LONG-TERM MONITORING........................................................................ 4-1
4.2 GROUNDWATER SAMPLING RESULTS .................................................... 4-2
5. ADDITIONAL INVESTIGATIONS ........................................................................ 5-1 5.1 PASSIVE SOIL GAS SURVEY ...................................................................... 5-1 5.2 VERTICAL PROFILING INVESTIGATION.................................................. 5-1
5.3 SOIL SAMPLE INVESTIGATION USING GEOPROBE ............................... 5-2 5.4 AQUITARD (CONFINING) LAYER.............................................................. 5-3
6. HISTORICAL GROUNDWATER DATABASE..................................................... 6-1
7. CONCLUSIONS AND RECOMMENDATIONS .................................................... 7-1 7.1 CONCLUSIONS ............................................................................................. 7-1 7.2 RECOMMENDATIONS ................................................................................. 7-2
MNH|F:\USER\SHARE\KEARSARGE ESD DOCS\46949\TOC.DOC 6 OCTOBER 2003 iii
LIST OF FIGURES
Title
Figure 1 Operations Report Site Plan
Figure 2 Process Flow Diagram
Figure 3 GWTP Average Monthly Flow Rate - Treated
Figure 4 Historical Well Data Total Chlorinated Solvents 1995 through 2002
Figure 5A Contaminant Concentrations in Well MW-4 as a Percent of Cleanup Goals
Figure 5B Contaminant Concentrations in Well MW-7 as a Percent of Cleanup Goals
Figure 5C Contaminant Concentrations in Well MW-114 as a Percent of Cleanup Goals
Figure 5D Contaminant Concentrations in Well MW-203 as a Percent of Cleanup Goals
Figure 5E Contaminant Concentrations in Well MW-205 as a Percent of Cleanup Goals
Figure 5F Contaminant Concentrations in Well MW-211 as a Percent of Cleanup Goals
Figure 5G Contaminant Concentrations in Well MW-213 as a Percent of Cleanup Goals
Figure 5H Contaminant Concentrations in Well CDM-1 as a Percent of Cleanup Goals
Figure 5I Contaminant Concentrations in Well EW-1 as a Percent of Cleanup Goals
Figure 5J Contaminant Concentrations in Well EW-2 as a Percent of Cleanup Goals
Figure 5K Contaminant Concentrations in Well EW-3 as a Percent of Cleanup Goals
Figure 5L Contaminant Concentrations in Well EW-9 as a Percent of Cleanup Goals
Figure 5M Contaminant Concentrations in Well EW-13 as a Percent of Cleanup Goals
Figure 5N Contaminant Concentrations in Well EW-13A as a Percent of Cleanup Goals
Figure 5O Contaminant Concentrations in Well EW-14 as a Percent of Cleanup Goals
Figure 6A 1,1,1-TCE Concentrations as a Percent of Cleanup Goal
MNH|F:\USER\SHARE\KEARSARGE ESD DOCS\46949\TOC.DOC 6 OCTOBER 2003 iv
LIST OF FIGURES (continued)
Title
Figure 6B 1,1-DCE Concentrations as a Percent of Cleanup Goal
Figure 6C-1 1,1-DCA Concentrations as a Percent of Cleanup Goal for MW-114, MW-203,
MW-205, MW-211, MW-213, EW-13, EW-13A
Figure 6C-2 1,1-DCA Concentrations as a Percent of Cleanup Goal for CDM-1, EW-9,
EW-14, MW-4, MW-7, EW-01, EW-02, EW-03
Figure 6D 1,2-DEC Concentrations as a Percent of Cleanup Goal
Figure 6E TCE Concentrations as a Percent of Cleanup Goal
Figure 7A 1,1,1-TCA Concentration in Well MW-7
Figure 7B 1,1-DCE Concentration in Well MWS-203 and MWS-205
Figure 7C 1,1-DCE Concentration in Well EW-14
Figure 7D 1,1-DCA Concentration in Well MWS-203, MWS-211, and MWS-114
Figure 7E 1,1-DCA Concentration in Well MW-4, CDM-1, and EW-14
Figure 7F TCE Concentration in Wells MWS-211 and MWS-213
Figure 7G 1,1-DCA Concentration in Well MW-114 and CDM-1
Figure 7H Contaminant Concentrations in Well CDM-1 as a Percent of Cleanup Goals
Figure 8 Total Target VOCs
Figure 9 Vertical Profile Investigation Total VOC Concentration Contours at Top of Silt
Layer
Figure 10 Geoprobe Core Investigation Contours of Maximum Detected Total VOC
Concentration in each Boring
MNH|F:\USER\SHARE\KEARSARGE ESD DOCS\46949\TOC.DOC 6 OCTOBER 2003 v
LIST OF TABLES
Title Page
Table 1-1 Groundwater Clean-up Goals ........................................................................... 1-1
Table 2-1 Influent and Effluent 2002 Analytical Data for Selected Compounds ............... 2-3
Table 3-1 Summary of Major Maintenance Items and Modifications................................ 3-2
Table 3-2 Routine Maintenance Items.............................................................................. 3-4
Table 4-1 2002 Monitoring Program Summary ................................................................ 4-3
Table 4-2 2002 Groundwater Data ................................................................................... 4-4
Table 4-3 Metals Data August 2002................................................................................. 4-6
MNH|F:\USER\SHARE\KEARSARGE ESD DOCS\46949\LIST OF ACRONYM1.DOC 6 OCTOBER 2003 vi
LIST OF ACRONYMS
µg/L micrograms per liter 1,1,1-TCA 1,1,1-trichloroethane
1,1-DCA 1,1-dichloroethane 1,1-DCE 1,1-dichloroethene
1,2-DCA 1,2-dichloroethane AGWQS Ambient Groundwater Quality Standard
bgs below ground surface EPA U.S. Environmental Protection Agency
ft feet GC gas chromatography
gpm gallons per minute GWTP Groundwater Treatment Plant
hp horsepower KMC Kearsarge Metallurgical Corporation
mg/L milligrams per liter MTBE Methyl t-butyl ether NHDES New Hampshire Department of Environmental Services
O&M Operations and Maintenance QC Quality Control
RCMP Risk Characterization and Management Policy ROD Record of Decision
Site Kearsarge Metallurgical Corporation Superfund Site TCE Trichloroethylene
VOCs volatile organic compounds WESTONSM Weston Solutions, Inc.
SECTION 1
INTRODUCTION
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 1-1 10/6/2003
1. INTRODUCTION
This 2002 Operations and Maintenance (O&M) Report presents the performance and results of
groundwater treatment at the Kearsarge Metallurgical Corporation (KMC) Superfund Site (Site)
from 1 January 2002 through 31 December 2002. The report includes a discussion of the
performance, maintenance, and modifications of the groundwater extraction and treatment
system, as well as recommendations to improve the performance of the system.
The Site is located in Conway, New Hampshire. A site plan is presented as Figure 1. Kearsarge
Metallurgical Corporation manufactured precision stainless steel castings at the site from 1964
to 1982. Wastes such as spent ceramic casting sands and molds, metal grindings, scrap metal, and
rusted steel drums were disposed in a waste pile located to the east of the facility buildings. The
waste pile was removed in October 1992. Waste solvents, such as 1,1,1-trichloroethane (1,1,1-
TCA), were also disposed in a septic tank/leach field located adjacent to the waste pile. These
waste disposal practices resulted in contamination of the site groundwater. Contaminants of
concern at the Site and associated groundwater clean-up levels are listed in Table 1-1.
Table 1-1
Groundwater Clean-up Goals
Contaminant of Concern Clean-up Goal (µg/l)
Chloroform 100
Chromium (dissolved) 50
1,1-Dichloroethane 4
1,2-Dichloroethane 5
1,1-Dichloroethene 7
Nickel (dissolved) 700
Trichloroethene 5
1,1,1-Trichloroethane 200
Operation of the groundwater remediation system at the Site began in October 1993.
Weston Solutions, Inc. (WESTONSM) has operated the system since August 1995. A discussion
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 1-2 10/6/2003
of treatment system components, performance, routine and non-routine maintenance, and
modifications during 2002 is provided in Sections 2 and 3. The results of the 2002 groundwater
sampling and analysis are presented in Section 4. Additional investigations conducted during 2002
to evaluate a potential continuing source of contamination are discussed in Section 5. Section 6 is
the updated Historical Groundwater Database. Conclusions and recommendations for
modifications to the remediation system at the Site are contained in Section 7.
SECTION 2
GROUNDWATER EXTRACTION AND TREATMENT SYSTEM
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-1 10/6/2003
2. GROUNDWATER EXTRACTION AND TREATMENT SYSTEM
A process flow diagram of the groundwater remediation system at the Site is presented as
Figure 2. The system at the Site consists of the following treatment processes:
! Groundwater extraction from three extraction wells (EW-01, EW-02, and EW-03) located west of the Groundwater Treatment Plant (GWTP) known as Hobbs Street wells, and nine extraction wells (EW-5 through EW-9 and EW-11 through EW-12, EW-13A, and EW-14) located southeast of the GWTP (Culvert Area wells). Extraction well EW-13A is associated with a groundwater collection trench installed in 2000 located in the vicinity of the Culvert Area wells. The well locations are shown on Figure 1.
! Equalization (T-1).
! Metals removal processes, including clarification and filtration. (T-2, FC-1, T-3, SF-1, SF-2, T-5).
! Organics removal, including air stripping with treatment of the stripper off-gas via vapor phase carbon. (AS-1, OTS-1, OTS-2).
! Sludge Storage (ST-1).
! Discharge of the plant effluent to the sanitary sewer (T-4).
Two additional extraction wells, EW-04 (Hobbs Street) and EW-10 (Culvert Area), were
formerly used to extract groundwater for the treatment system. These two wells were off-line in
2002. Extraction wells EW-04 and EW-10 were sampled in 2002, and the groundwater
contaminant concentrations in the vicinity of these wells were below clean-up goals. Culvert Area
well EW-13 was replaced with collection trench extraction well EW-13A in October 2000 and
now functions as a monitoring well.
2.1 SUMMARY OF VOLUMES PROCESSED
The design pumping rate of the groundwater extraction wells at the Site is approximately
42 gallons per minute (gpm), with 40 gpm extracted from the Hobbs Street wells and 1 to 2 gpm
extracted from the Culvert Area wells. During 2002, the Hobbs Street extraction well (EW-01,
EW-02, and EW-03) pumps were operated in a pulsed mode. The pulsed mode was tested
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-2 10/6/2003
beginning in January 2002. The pulsed mode, consisting of operating the well pumps for four days
and shutting off the well pumps for 3 days, began in April 2002.
The actual GWTP flow rates and monthly volumes treated from January 2002 through
December 2002 are presented in Figure 3. During this time, the GWTP average monthly flow rate
ranged from 22.1 gpm to 42.7 gpm, with an average of approximately 34 gpm and an average
treatment volume of approximately 1,122,800 gallons per month (approximate annual treated
volume of 13,473, 500 gallons).
In August 2002, the GWTP was shut down for 10 days (8/14/02 � 8/23/02) during non-duty
hours to prevent equipment damage due to a malfunction at Control Panel No. 1. In
September 2002, the GWTP was shut down for four days while the process piping was being
replaced. A discussion of the Year 2002 maintenance and modification activities is included in
Section 3 of this report.
2.2 INFLUENT/EFFLUENT QUALITY
Influent concentrations of 1,1-dichloroethane (1,1-DCA), 1,2-dichloroethane (1,2-DCA),
1,1,1-TCA, and 1,1-dichloroethene (1,1-DCE) historically have been above clean-up goals in the
Culvert Area extraction wells and below clean-up goals in the influent from the Hobbs Street
extraction wells. Between 2000 and 2002, the influent concentrations of 1,2-DCA and
Trichloroethylene (TCE) were consistently below the clean-up goals of 5 micrograms per
liter (µg/L) in the Culvert Area extraction wells. Influent concentrations for 1,1-DCA, 1,1-DCE,
and 1,1,1-TCA continued to exceed clean-up goals in the Culvert Area extraction wells. Influent
concentrations of selected volatile organic compounds (VOCs) for the year 2002 are presented in
Table 2-1.
Historically, TCE has been observed primarily in the Hobbs Street wells. However, the VOC
concentrations in the Hobbs Street extraction wells have remained below the TCE clean-up goal
in 1999, 2000, 2001, and 2002. The remaining VOC constituents were also below the clean-up
goal in the Hobbs Street extraction wells for 2002. However, concentrations of TCE in
monitoring well MW-211 [approximately 25 feet (ft) east of extraction well EW-01] continue to
exceed the cleanup goal.
Table 2-1Influent and Effluent 2002 Analytical Data for Selected Compounds
Kearsarge Metallurgical Corporation Superfund Site
Chemicals DetectedUnits
Cleanup Criteria
Location Well ID DateHobb Street EW01-EW03 23-Jan-02 2 U 2 U 1 U 2 U 2 U 190 25 U 470 40 U 5 U 10 U
Wells EW01-EW03 Pre-Batch 27-Mar-02 2 U 2 U 1 U 2 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 27-Mar-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 5-Apr-02 2 U 2 U 1 U 2.5 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 5-Apr-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 10-Apr-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 10-Apr-02 2 U 2 U 1 U 2.2 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 15-Apr-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 15-Apr-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 22-Apr-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 19-Apr-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 3-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 6-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 10-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 13-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 17-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 20-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 24-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 28-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 31-May-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 3-Jun-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 7-Jun-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 10-Jun-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 14-Jun-02 2 U 2 U 1 U 2 U 2.2 NS NS NS NS NS NSEW01-EW03 Pre-Batch 17-Jun-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 21-Jun-02 2 U 2 U 1 U 2 U 2.2 NS NS NS NS NS NSEW01-EW03 Post-Batch 24-Jun-02 2 U 2 U 1 U 2 U 2.2 NS NS NS NS NS NSEW01 Post-Batch 5-Jul-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Pre-Batch 8-Jul-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Post-Batch 12-Jul-02 2 U 2 U 1 U 2.3 2 U NS NS NS NS NS NSEW01 Pre-Batch 15-Jul-02 2 U 2 U 1 U 2.2 2 U NS NS NS NS NS NSEW01-EW03 Post-Batch 19-Jul-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01-EW03 Pre-Batch 22-Jul-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Pre-Batch 25-Jul-02 2 U 2 U 1 U 2.5 2 U NS NS NS NS NS NSEW01 Post-Batch 29-Jul-02 2 U 2 U 1 U 2.6 2 U NS NS NS NS NS NSEW01 Post batch 2-Aug-02 2 U 2.7 1 U 2.6 2.2 NS NS NS NS NS NSEW01 Pre-batch 5-Aug-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Post batch 9-Aug-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Pre-batch 12-Aug-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Post batch 16-Aug-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Pre-batch 19-Aug-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NSEW01 Pre-batch 26-Aug-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NS
Chemicals DetectedCulvert Wells EW5-EW9 & EW11-EW14 23-Jan-02 66 2 U 42 420 2 U 4100 25 U 56000 40 U 5 U 10 U
GWTP Effluent Date23-Jan-02 2 U 2 U 1 U 2 U 2 U 120 25 U 100 U 40 U 5 U 10 U27-Feb-02 2 U 2 U 1 U 2 U 2 U 52 25 U 100 U 40 U 5 U 10 U27-Mar-02 2 U 2 U 1 U 2 U 2 U 55 25 U 100 U 40 U 5 U 10 U5-Apr-02 2 U 2 U 1 U 2 U 2 U 54 25 U 100 U 40 U 5 U 10 U
10-Apr-02 2 U 2 U 1 U 2 U 2 U 71 25 U 100 U 40 U 5 U 10 U6-May-02 2 U 2 U 1 U 2 U 2 U 66 25 U 100 U 40 U 5 U 10 U19-Jun-02 2 U 2 U 1 U 2 U 2 U 170 25 U 100 U 40 U 5 U 10 U15-Jul-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NS
22-Aug-02 0.5 U 0.5 U 0.5 U 0.5 U 0.5 U 18 25 U 100 U 40 U 5 U 10 U12-Sep-02 2 U 2 U 1 U 2 U 2 U NS NS NS NS NS NS29-Oct-02 2 U 2 U 1 U 2 U 2 U 5000 72 650 40 U 5 U 10 U12-Nov-02 2 U 2 U 1 U 2 U 2 U 130 25 U 100 U 40 U 5 U 10 U10-Dec-02 2 U 2 U 1 U 2 U 2 U 64 25 U 100 U 40 U 5 U 10 U
U = Quantitation LimitNS = Not Sampled
* = Chemical analyses performed by EPA using an on-site GC.NR = Not Recorded in this report
Pre-Batch = Sample collected after wells shutdown for 2 to 3 days.Post Batch = Sample collected after wells had been pumping for 4 days.
Manganese Nickelµg/L700
Copper Ironµg/L
-µg/L
-
TCEµg/L µg/L µg/L µg/L µg/L
1,1 DCA 1,2-DCA
Effluent
Influent Influent
1,1 DCA 1,2-DCA 1,1,-DCE 1,1,1-TCA TCE
-4 5 7 200
Chromium1,1,-DCE 1,1,1-TCA
5µg/L
50
Leadµg/L
-µg/L
MNH\projects\01395022\008\annlrpt\final\TABLE2_1 2-3 10/6/2003
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-4 10/6/2003
Methyl t-butyl ether (MTBE), a contaminant not detected at the Site previous to 1998, was
observed in GWTP effluent samples on four occasions between May 1998 and October 1998.
Methyl t-butyl ether was detected at a concentration of 2.8 µg/L in an effluent sample collected in
June 2002 and 1.4 µg/L in an effluent sample collected in August 2002. The New Hampshire
Department of Environmental Services (NHDES) Ambient Groundwater Quality Standard
(AGWQS) for MTBE is 13 µg/L; none of the effluent sampling exceeded this regulatory limit for
MTBE.
Analytical data from the monitoring wells at the Site provide additional information regarding
groundwater contaminant distribution. A discussion of contaminant concentrations in the Site�s
monitoring wells is presented in Section 4.
2.3 UNIT PROCESS PERFORMANCE
2.3.1 Hobbs Street Wells
Historically extraction wells EW-01 EW-02, and EW-03 have performed reliably, with flow rates
averaging 40 gpm for all three wells combined. During 2002, pulsed operation of the
Hobbs Street wells was performed to clean up potential residual contamination in the vadose zone
in the Hobbs Street area. Beginning in January 2002, the Hobbs Street wells were operated in a
pulsed mode. During the pulsed mode, all three wells were simultaneously shut down for a period
of 2 to 3 days, followed by continuous pumping for a period of 3 days. The Hobbs Street pumps
were operated in this on/off cycling mode from January through September of 2002.
During the shut down period, groundwater elevations in the Hobbs Street area were allowed to
return to static (non-pumping) levels. This allowed any residual contamination in the normally
unsaturated soils (under pumping conditions) to come in contact with the groundwater.
If residual contamination existed in these soils, the raising and lowering of the groundwater
caused by the pulse operation mode would provide a flushing action to remove the residual
contamination from the normally unsaturated soils. To evaluate whether contamination was being
removed from the vadose zone, influent samples were collected after the 4-day pumping period,
prior to the shut down of the wells (post-batch samples), and again after conclusion of the 2- to 3-
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-5 10/6/2003
day shutdown period (pre-batch samples). Table 2-1 summarizes the analytical data for the pre-
and post-batch samples. The pre- and post-batch samples were collected until
August 2002 even though batching of the Hobbs Street wells continued for the entire year.
Beginning in July and August 2002, pre- and post-batch sampling was conducted on extraction
well EW-01 only to determine if elevated concentrations of VOCs were being diluted by the
influent from extraction wells EW-02 and EW-03. The analytical results from the EW-01 batch
samples were also below the clean-up criteria for the VOCs analyzed. In September, the pre- and
post- batch sampling was discontinued for all extraction wells. Analytical results from the
pre- and post-batch samples were continuously below cleanup criteria.
The extraction well pumps are typically removed one to two times per year for cleaning
(primarily/removal of iron bacteria and precipitated metals) and maintenance. In 2002, the
Hobbs Street extraction well pumps were removed for cleaning and maintenance in March and
November. In March, extraction well EW-03 pump motor and relay were replaced. In May 2002,
the pump motor was replaced in extraction well EW-01. Due to a decline in extraction well
efficiency, TDS (a WESTON Subcontractor) redeveloped extraction wells EW-01 and EW-03 in
November 2002.
2.3.2 Culvert Area Wells
The Culvert Area wells performed well during the 2002 reporting period, but because of the low
conductivity soils in the Culvert Area, they have much lower yields (2-3 gpm combined) than the
Hobbs Street wells (40 gpm combined). However, the highest groundwater contaminant
concentrations are in the Culvert Area and thus the Culvert Area wells provide substantial
contaminant removal. Two of the extraction wells (EW-4 and EW-10) attained the clean-up goals
and were shut down in November 1995 and April 1996, respectively. The aboveground piping to
EW-10 has been removed.
The pumps in the Culvert Area wells are pneumatically driven because of the low yields of these
wells. The pneumatic well pumps have performed reliably and, like the Hobbs Street well pumps,
require periodic removal and cleaning. In February 2002, Culvert Area extraction well pump EW-
13A was removed and cleaned. In July, pumps in extraction wells EW-05 through EW-09 were
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-6 10/6/2003
removed and cleaned. In August, extraction wells EW-11 through EW-14 were removed and
cleaned.
Extraction well EW-13A continues to extract an average of 1 gpm from the Culvert Area,
doubling the total rate of groundwater extraction within the Culvert Area from approximately
1 to 2 gpm, prior to installation of the EW-13A, to 2 to 3 gpm currently. In 2002, EW-13A had
the highest recorded flow rate of the Culvert Area extraction wells.
In February 2002, the cycle counter in extraction well EW-11 was replaced. In March 2002, a
discharge pipeline from pump head EW-13 to the well head was repaired.
2.3.3 Groundwater Collection Trench and Associated Extraction Well
The groundwater collection trench is 120 ft long, 4 ft wide, and slopes from approximately 9.5 ft
below ground surface (bgs) at each end to approximately 10.5 ft deep at the center, where the
new extraction well EW-13A is located. There is a one-foot-thick layer of washed, crushed stone
installed along the full-length of the trench bottom. The crushed stone layer provides a
high-permeability zone to facilitate flow of groundwater to EW-13A. A geotextile filter fabric
overlays the crushed stone layer. The objective of the filter fabric is to minimize downward
migration of fine soil particles into the crushed stone layer, and thereby maintain the permeability
of that layer. The bottom of the trench is located at the top of the low-permeability silt-clay layer,
9.5 to 10.5 ft bgs. The location of the groundwater collection trench is shown on Figure 1.
As mentioned in Subsection 2.3.2, the flow rate within extraction well EW-13A had the highest
recorded flow rate of the Culvert Area extraction wells, indicating the continued successful
performance of the groundwater collection trench. The trench is centered across the axis of a
concentrated portion of the contaminant plume and appears to be intercepting the plume as it
flows in an easterly direction.
2.3.4 Equalization and Metals Removal System
The components of this system are the equalization and pH adjustment tank (T-1), flash mix tank
(T-2), clarifier (FC-1), transfer tank (T-3), deep-bed sand filters (SF-1 and SF-2), and associated
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-7 10/6/2003
process and chemical feed pumps. The low concentration of metals in the treatment plant influent
required minimal active metals removal during 2002. Minimal settling of iron and other suspended
solids occurred in the clarifier. One of the two sand filters is operated continuously with the
second filter on standby. The operating sand filter is backwashed weekly. The backwash water
from the sand filters and the small amount of solids that settle in the clarifier are pumped to the
sludge holding tank (ST-1). The average thickness of settled sludge in the bottom of the sludge
holding tank was approximately 14 inches during 2002.
Due to the deterioration of the process piping and mineral deposits within the pipeline, continual
cleaning, flushing, and repairing of the pipeline was conducted to decrease head losses in the
piping within the treatment plant. In September 2002, the process piping was replaced by
Federal Piping Company to improve the overall operation of the treatment plant.
2.3.5 Organic Contaminants Removal System
The organic contaminants removal system consists of the air stripper (AS-1) and the vapor phase
activated carbon adsorption units (OTS-1 and OTS-2). This system has performed efficiently,
removing organic contaminants from the process water to below discharge criteria since GWTP
startup. A 2-horsepower (hp) air stripper blower draws outside air in through the tank ventilation
system and processes it through the air stripper. This blower is also used in the carbon system to
process the air stripper exhaust through two carbon vessels in series prior to discharge to the
atmosphere.
Toward the end of 2002, an increase in pressure loss in the airflow through air stripper has been
observed. This may be the result of a buildup of mineral deposits, such as iron and manganese, on
the air stripper packing material. Because the Hobbs Street wells were operated in a pulsed mode
during 2002 rather than the previous continuous mode, the average water quality was largely
influenced by the water quality of the Culvert Area, which contained higher concentrations of iron
and manganese. Therefore, it seems likely that the increase in pressure losses across the air
stripper is caused by mineral deposits that resulted from the altered influent water quality from the
pulsed pumping regime.
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 2-8 10/6/2003
The last carbon change out was conducted in October 1996. Total VOC concentration
measurements are taken at the discharges from the first and second carbon vessels on a monthly
basis with a photoionization detector. The readings collected at the discharge of the first vessel
periodically detected low concentrations of VOCs (0.1 parts per million) in 2002. As a preventive
maintenance measure, it is recommended that the first carbon vessel be removed and replaced by
the second carbon vessel. The spare carbon vessel, currently being stored on-site, will become the
new second carbon vessel. The readings collected after the second carbon vessel continue to be at
or below background levels, indicating that the carbon has not been exhausted in the second
vessel and that VOCs stripped from the groundwater are not passing through the carbon. The air
stream at the intake and discharge of each activated carbon filter is measured monthly for VOC
concentrations.
SECTION 3
TREATMENT SYSTEM MAINTENANCE AND MODIFICATIONS
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 3-1 10/6/2003
3. TREATMENT SYSTEM MAINTENANCE AND MODIFICATIONS
A summary of major maintenance items and modifications to the GWTP from January 2002
through December 2002 is presented in Table 3-1. The significant maintenance and modification
activities in 2002 included:
! Replace inoperable cycle counter at extraction well EW-11.
! Replace pump motor, thermal overload and relay in extraction well EW-03.
! Install new digital indicator for equalization tank level at CP-2.
! Repair leaking line and valve at extraction wells EW-05 and EW-07.
! Install upgraded process, fire, and security alarm system.
! Replace discharge pipeline from EW-13 pump head to well head.
! Replace extraction well pump motor for EW-01.
! Install vault cover over extraction well EW-01.
! Replace oxygen sensor and battery cell in combustible gas analyzer.
! Repair air stripper tower weather cap.
! Replace leaking process piping in GWTP.
! Redevelop Hobbs Street wells EW-01, EW-02, and EW-03.
! Repair hoses and replace a gasket in AC-1.
! Repair air stripper tower cap sheathing.
! Pulling of pumps in Hobbs Street and Culvert Area wells for cleaning, service, and maintenance.
In September 2002, the process piping was replaced by Federal Piping Company to improve the
overall operation of the treatment plant. Federal Piping Company replaced the effluent piping
from T-1 pumps to the flash mix tank, and the effluent piping from the filter supply pumps to the
effluent sand filter beds.
Table 3-1Summary of Major Maintenance Items and Modifications
Kearsarge Metallurgical Corporation Superfund Site
Date Item Maintenance/Modification
14-Jan-02 Process piping Air/Water scour process piping, maintenance to avoid clogging24-Jan-02 Process piping Air/Water scour process piping, maintenance to avoid clogging25-Jan-02 Equalization tank Inspect T-1 tank interior for condition, and tank level probe accuracy4-Feb-02 Alarm System Pope security on site to review alarm installation8-Feb-02 EW-11 Cycle counter at EW-11 inoperable, replaced with new unit21-Feb-02 Culvert area Pulled pump at EW-13A was inoperable - cleaned pump 25-Feb-02 Heatless air dryer Replaced pre and post coalescing filters at heatless air dryer12-Mar-02 EW-13 Repaired 5/8 inch discharge pipeline from pump head to well head.13-Mar-02 Digital indicator Troubleshoot 710D digital indicator with loop C39simulator. 710D unit-non-operational - returned for repair.18-Mar-02 Flow meter Schedule maintencance and cleaning of paddle wheel flow meter.20-Mar-02 EW-1,2,3 Maintenance/cleaning of well pumps.20-Mar-02 EW-3 pump EW-3 pump burned out.20-Mar-02 EW-1,2,3 Replaced check valves at EW-1,2,3 pump installations.25-Mar-02 CP-1 Hoffman electrician replaced burned out relay, pump motor, wire lead.26-Mar-02 CP-1 EW-3 relay burned out again 27-Mar-02 Well survey Conduct well elevation survey 28-Mar-02 EW-3 pump Grundfos electrician onsite pulled pump EW-3 and replaced motor and relay.1-Apr-02 Digital indicator Troubleshoot 710D digital indicator. Sent back to Mfg as warranty item.4-Apr-02 Digital indicator Install and set up new 710D digital indicator.4-Apr-02 873 pH Analyzer Specify and order a new pH sensor probe to T-1 tank.5-Apr-02 CGI Found CGI inoperable. Ordered a new 02 sensor.
16-Apr-02 CGI Replaced faulty 02 sensor in CGI.25-Apr-02 EW-5 and EW-7 Repaired damaged and leaking line and fittings in well head.26-Apr-02 Air Compressor Top off synthetic lubricant at air compressor #1.4-May-02 System Process T-1 tank full alarm, ran batch 11-May-02 System Process T-1 tank full alarm, ran batch 15-May-02 EW-1 EW-1 tripped check with amp probe15-May-01 710D Digital indicator Set alarm limits for T-4 effluent tank16-May-02 Security System Pope Security onsite to install upgraded system, answering service16-May-02 PLC Changed set point for pumps EW-5 and EW-1417-May-02 Security System Pope Security onsite to install upgraded system, answering service21-May-02 EW-1 pump motor Whitelaw Electric onsite, pulled pump, replaced bad motor.
G:\projects\01395022\008\annlrpt\final\TBL3_1\O&M 3-2 10/6/2003
Table 3-1Summary of Major Maintenance Items and Modifications
Kearsarge Metallurgical Corporation Superfund Site
Date Item Maintenance/Modification
24-Jun-02 Carbon Filters Air sampling for hydrocarbon detection, to determine carbon saturation27-Jun-02 Boring rods Bring boring equipment to machine shop to repair threads.9-Jul-02 Pneumatic wells Pulled pumps at EW-5 and EW-6 for preventative maintenance/cleaning
11-Jul-02 CGI CGI inoperable. Ordered new 02 sensor and battery cell as required.16-Jul-02 Pneumatic wells Pulled pumps at EW-7, 8, 9 for preventative maintenance/cleaning22-Jul-02 Carbon Exhaust blower Low air pre-alarm; removed condensation4-Aug-02 System process Reset air system5-Aug-02 EW-1 Throttle EW-1's pump discharge to eliminate pump cavatation.8-Aug-02 Extraction well pumps Pull pumps and conduct cleaning and preventive maintenance (Ext. wells 13 and 14).9-Aug-02 Extraction well pumps Pull pumps and conduct cleaning and preventive maintenance (Ext. wells 11 and 12).
14-Aug-02 CP-1 Found control problem with CP-1 (on-operational)15-Aug-02 pH probe pH Probe inoperable, reconfigure local control in process area.22-Aug-02 CP-1 Electrician onsite to install fuse block, & 3 min alarm shutdown delay module.23-Aug-02 CP-1 Malfunction at CP-1 caused by process shutdown, pulled 3 hour process alarm shutdown module.3-Sep-02 System process Discontinue process batch, Hobbs Pulsing, and batch sampling.3-Sep-02 System Effluent Granite Staet Analytical performed quarterly compliance sampling.18-Sep-02 ASTU Lift service onsite to facilitate ASTU cap sheathing repair.20-Sep-02 Process piping Federal Piping onsite to prefab pipe for shutdown.23-Sep-02 Process piping Federal Piping onsite to dismantle sand filter manifolds and applicable piping.25-Sep-02 P15, P16 flow meter Clean P15/P16 manifold assembly and magnetic flow meter.28-Sep-02 VFD Reset variable speed drive, 32.5 to 31 gpm due to T-1 low condition.3-Oct-02 Facility sump Solenoid failed at T-3, manually pumped down sump.
15-Oct-02 EW-1 and EW-3 Shut down wells, dose w/ LBA to prep for redevelopment of wells.17-Oct-02 EW-1 and EW-3 TDS onsite to redevelop wells - method unsuccessful.17-Oct-02 EW-1 and EW-3 Turned well pumps on - throttle EW-1 to 12 gpm.30-Oct-02 EW-1 and EW-3 TDS back onsite to redevelop wells. Shutdown EW-1 and EW-3 does with LBA31-Oct-02 EW-1 and EW-3 Turned EW-1 and EW-3 well pumps on.31-Oct-02 AC-1 Air Services Co. onsite to repair hoses and replace gasket on AC-1.13-Nov-02 EW-02 Pulled and serviced extraction well pump.11-Dec-02 Culvert Area Isolate extraction wells EW-5 & EW-11, blow out line. Off-line for the season.
G:\projects\01395022\008\annlrpt\final\TBL3_1\O&M 3-3 10/6/2003
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 3-4 10/6/2003
Although not part of the groundwater remediation facility, the old KMC building is located
adjacent to the treatment plant building. Over the past few years this building has undergone
significant deterioration. A safety inspection conducted by WESTON in 2001 indicated that this
building is no longer structurally stable and portions are in danger of collapse. No trespassing
signs have been posted to prevent the public from entering the building and fencing the perimeter
of the building is planned for 2003.
The maintenance and modification activities listed in Table 3-1 were performed on an as-needed
basis. Additional maintenance activities are routinely conducted at the Site weekly, monthly,
tri-annually, or annually. A summary of ongoing maintenance items and the frequency at which
they are conducted is presented in Table 3-2.
Table 3-2
Routine Maintenance Items
Frequency Task
Weekly Inspection of Culvert Area well pumps and recording of pump cycle totalizer readings
Weekly Collection of grab samples throughout the treatment process for pH and iron testing
Weekly Cleaning and calibration of T-1 pH probe
Monthly Equipment rotation (pumps, blowers, etc.)
Monthly Collection of effluent samples and delivery to the AMRO Laboratory
Every 5000 hours of operation Air compressor oil and air filter replacement
Every 4 Months Removal, dismantling, and cleaning of extraction well pumps
Quarterly Lubrication of pumps, motors, mixers, blowers
Quarterly Cleaning of paddle wheel influent flow meter
Quarterly Collection of influent samples and delivery to the AMRO Environmental Laboratory
As needed seasonally Outside maintenance including snow blowing, and mowing of grass and weeds around plant and wells
Annual Clarifier tank cleaning and residual sludge removal
Annual Removal and cleaning of P-30 (building sump pump)
Annual Replacement of belts on exhaust blower
Annual Inspection of interior of sand filters and leveling of media
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 3-5 10/6/2003
Frequency Task
As Needed Replacement of activated carbon in vapor phase carbon units
SECTION 4
GROUNDWATER SAMPLING AND ANALYSIS
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-1 10/6/2003
4. GROUNDWATER SAMPLING AND ANALYSIS
Groundwater sampling and analysis is conducted at the Site to evaluate performance of the
groundwater extraction system and to monitor progress towards attainment of clean-up goals.
Groundwater monitoring at the Site is conducted according to the Long-Term Monitoring Plan
for the Site as described in Subsections 4.1 and 4.2.
4.1 LONG-TERM MONITORING
A Long-Term Monitoring Plan for monitoring performance of the groundwater remediation
system was developed and submitted to NHDES in July 1996. The objectives of the monitoring
plan are as follows:
! Provide data to evaluate performance of the groundwater extraction system.
! Provide data that can be used to forecast if and when the groundwater extraction system will reduce groundwater contamination to acceptable levels.
! Provide data that can be used to justify and document alternative actions in the event that groundwater extraction proves to be technically impracticable.
The monitoring plan recommended:
! A list of selected wells at the Site to be monitored.
! Specific analytes that are indicators of overall groundwater contamination at the Site.
! Sampling frequency.
! Statistical methods for analyzing the resulting groundwater data.
The monitoring plan recommended tri-annual monitoring of five analytes (1,1-DCA, 1,1,1-TCA,
TCE, 1,2-DCA, and 1,1-DCE) in 13 wells (CDM-1, EW-01, EW-02, EW-03, EW-09, EW-14,
MW-4, MW-7, MWS-114, MWS-203, MWS-205, MWS-211, and MWS-213). Graphs of
contaminant concentrations versus time were recommended for analysis of trends in contaminant
concentrations.
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-2 10/6/2003
Three groundwater sampling rounds were conducted in 2002. During 2002, groundwater samples
were collected on April 3, 4, and 5, August 5, 6 and 7, and December 2, 3, and 4. Additional
sample locations not included in the original monitoring plan were sampled in 2002. In August,
the monitoring program was expanded to include a comprehensive sampling event with additional
wells that formerly contained concentrations less than the clean-up goals. This extensive
monitoring program included 39 wells. Table 4-1 summarizes the wells sampled during each 2002
sample event.
The groundwater samples were analyzed for VOCs via U.S. Environmental Protection Agency
(EPA) Method SW-8260. Laboratory analyses of the wells sampled in 2002 are summarized in
Table 4-2. Figure 4 shows the total VOC concentrations in the monitoring and extraction wells
from 1995 to 2002.
During the August 2002 sampling round, groundwater samples collected from MW-4, MW-7,
MW-8, MW-9, MW-11, MW-112, MW-114, MW-115, MW-203, MWS-205, MW-206,
MW-211, MW-213, MW-215, EW-01, and CDM-1 were analyzed for iron, manganese,
chromium, and nickel using EPA Method 200. Table 4-3 summarizes the metals data from this
sampling round. Concentrations of both chromium and nickel were below the clean-up goals in all
samples. Concentrations of iron up to 37.9 milligrams per liter (mg/L) and manganese up to
7.79 mg/L were observed in several Culvert Area wells, indicating that Culvert Area water would
likely require pretreatment if not diluted by water from the Hobbs Street extraction wells.
4.2 GROUNDWATER SAMPLING RESULTS
The historical groundwater monitoring data (VOC data only) for selected monitoring wells are
presented graphically in Figures 5A through 5O, 6A through 6E, and 7A through 7G. Because of
the wide range of contaminant concentrations displayed, Figures 5A through 5O and 6A through
6E are displayed in a semi-logarithmic format.
Figures 5A through 5O show the contaminant concentrations in each well as a percent of the
contaminant�s clean-up goal, and thus allow for evaluation of clean-up goal exceedances on a
well-specific basis.
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-3 10/6/2003
Table 4-1 2002 Monitoring Program Summary
Well Identification
Original Monitoring Plan
April Sample Event
August Sample Event
December Sample Event
EW-01 X X X XEW-02 X X X XEW-03 X X X XEW-05 X X EW-06 X X XEW-07 X X EW-08 X X XEW-09 X X X XEW-10 X EW-11 X X EW-12 X X XEW-13 X X
EW-13A X X XEW-14 X X X XCDM1 X X X XMW-01 X XMW-04 X X X XMW-07 X X X XMW-08 X MW-09 X MW-10 X MW-11 X MW-12 X
MW-104 X MW-105 X MW-112 X MW-113 X MW-114 X X X XMW-115 X MW-116 X MW-201 X MW-202 X MW-203 X X X XMW-204 X MW-205 X X X XMW-206 X MW-211 X X X XMW-213 X X X XMW-215 X
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-4 10/6/2003
Well Identification
Original Monitoring Plan
April Sample Event
August Sample Event
December Sample Event
MW-216 X
Table 4-22002 Groundwater Monitoring Data
Kearsarge Metallurgical Corporation Superfund Site
Well Date
CDM1 03-Apr-02 2 U 2 U 2 U 2 U 2 UCDM1 06-Aug-02 2 U 3.9 2 U 2 U 2 UCDM1 04-Dec-02 2 U 3.9 2 U 2 U 2 UEW01 03-Apr-02 2.5 2 U 2 U 2 U 2 UEW01 05-Aug-02 2 U 2 U 2 U 2 U 2 UEW01 04-Dec-02 2 U 2 U 2 U 2 U 2 UEW02 03-Apr-02 2 U 2 U 2 U 2 U 2 UEW02 05-Aug-02 2 U 2 U 2 U 2 U 2 UEW02 04-Dec-02 2 U 2 U 2 U 2 U 2 UEW03 03-Apr-02 2.7 2 U 2 U 2 U 2 UEW03 05-Aug-02 2.3 2 U 2 U 2 U 2 UEW03 04-Dec-02 2.3 2 U 2 U 2 U 2 UEW05 03-Apr-02 2 U 2.8 2 U 2 U 2 UEW05 05-Aug-02 2 U 49 8.8 2 U 2 UEW06 03-Apr-02 2 U 3.1 2 U 2 U 2 UEW06 05-Aug-02 3.5 49 9.5 2 U 2 UEW06 03-Dec-02 2 U 2 U 2 U 2 U 2 UEW07 03-Apr-02 3.7 6.1 2 U 2 U 2 UEW07 05-Aug-02 2.2 4.2 2 U 2 U 2 UEW08 03-Apr-02 5 2 U 2 U 2 U 2 UEW08 05-Aug-02 10 5.5 3.6 2 U 2 UEW08 03-Dec-02 5.8 5 2 U 2 U 2 UEW09 03-Apr-02 11 2 U 2.4 2 U 2 UEW09 05-Aug-02 2 U 2 U 2 U 2 U 2 UEW09 03-Dec-02 12 2 U 3.1 2 U 2 UEW10 06-Aug-02 3.6 2 U 2 U 2 U 2 UEW11 03-Apr-02 7.3 9.8 2 U 2 U 2 UEW11 05-Aug-02 2 U 2 U 2 U 2 U 2 UEW12 03-Apr-02 2.9 38 2.8 2 U 2 UEW12 05-Aug-02 2 30 2.1 2 U 2 UEW12 03-Dec-02 3.5 26 3.6 2 U 2 UEW13 03-Apr-02 16000 350 1200 2 U 2 UEW13 05-Aug-02 12000 570 1000 200 U 200 U
EW13A 03-Apr-02 550 26 37 2 U 2 UEW13A 05-Aug-02 520 39 35 2 U 2 UEW13A 03-Dec-02 400 32 31 2 U 2 UEW14 03-Apr-02 85 2.3 18 2 U 2 UEW14 05-Aug-02 60 2 U 11 2 U 2 UEW14 03-Dec-02 310 9.2 58 2 U 2 UMW1 03-Apr-02 74 4.3 5.2 2 U 2 UMW1 03-Dec-02 2 U 2 U 2 U 2 U 2 U
MW10 07-Aug-02 2 U 2 U 2 U 2 U 2 UMW104 07-Aug-02 2 U 2 U 2 U 2 U 2 UMW105 07-Aug-02 2 U 2 U 2 U 2 U 2 UMW11 05-Aug-02 2 U 2.7 2 U 2 U 2 UMW112 05-Aug-02 2 U 2 U 2 U 2 U 2 UMW113 06-Aug-02 2 U 2 U 2 U 2 U 2 UMW114 03-Apr-02 2 U 2 U 2 U 2 U 2 U
Cleanup Goal
1,1,1-TCA
200 557
1,1-DCA
4
1,2-DCA1,1-DCE TCE
FSMNH01\PROJECTS\01395022\008\ANNLRPT\final\TBL4_2\2002 4-4 10/6/2003
Table 4-22002 Groundwater Monitoring Data
Kearsarge Metallurgical Corporation Superfund Site
Well Date
Cleanup Goal
1,1,1-TCA
200 557
1,1-DCA
4
1,2-DCA1,1-DCE TCE
MW114 05-Aug-02 6.2 20 3.2 2 U 2 UMW114 03-Dec-02 2 U 9.6 2 U 2 U 2 UMW115 05-Aug-02 2.6 3 2 U 2 U 2 UMW116 07-Aug-02 2 U 2 U 2 U 2 U 2 UMW12 07-Aug-02 2 U 2 U 2 U 2 U 2 U
MW12-Dup 07-Aug-02 2 U 2 U 2 U 2 U 2 UMW201 06-Aug-02 2 U 2 U 2 U 2 U 2 UMW202 07-Aug-02 2 U 230 73 2 U 2 UMW203 03-Apr-02 3.4 27 3.4 2 U 2 UMW203 05-Aug-02 78 36 16 2 U 2 UMW203 03-Dec-02 7.5 21 4.4 2 U 2 U
MW203-Dup 05-Aug-02 78 35 16 2 U 2 UMW204 06-Aug-02 2 U 2 U 2 U 2 U 2 UMW205 03-Apr-02 21 2 U 5.9 2 U 2 UMW205 05-Aug-02 18 2 U 4.7 2 U 2 UMW205 03-Dec-02 19 2 U 5.2 2 U 2 U
MW205-Dup 03-Apr-02 21 2 U 6 2 U 2 UMW205-Dup 05-Aug-02 18 2 U 4.7 2 U 2 UMW205-Dup 03-Dec-02 17 2 U 4.7 2 U 2 U
MW206 06-Aug-02 2 U 2 U 2 U 2 U 2 UMW211 05-Apr-02 2 U 3.8 2 U 2 U 29MW211 06-Aug-02 2 U 2.6 2 U 2 U 16MW211 04-Dec-02 2 U 2.8 2 U 2 U 26MW213 05-Apr-02 2 U 2 U 2 U 2 U 2 UMW213 06-Aug-02 2 U 2 U 2 U 2 U 2 UMW213 04-Dec-02 2 U 2 U 2 U 2 U 2 U
MW213-Dup 04-Dec-02 2 U 2 U 2 U 2 U 2 UMW215 06-Aug-02 2 U 2 U 2 U 2 U 2 UMW216 07-Aug-02 2 U 2 U 2 U 2 U 2 UMW4 03-Apr-02 2 U 2 U 2 U 2 U 2 UMW4 05-Aug-02 2 U 8.4 2 U 2 U 2 UMW4 03-Dec-02 2 U 2 U 2 U 2 U 2 UMW7 03-Apr-02 2 U 2 U 2 U 2 U 2 UMW7 05-Aug-02 2 U 2 U 2 U 2 U 2 UMW7 03-Dec-02 2 U 2 U 2 U 2 U 2 UMW8 06-Aug-02 3.1 2 U 2 U 2 U 2 UMW9 06-Aug-02 2 U 2 U 2 U 2 U 2 U
Notes: 1. Units are ug/l2. U = non-detect
FSMNH01\PROJECTS\01395022\008\ANNLRPT\final\TBL4_2\2002 4-5 10/6/2003
Table 4-3Metals Data August 2002
Kearsarge Metallurgical Corporation Superfund Site
Monitoring Well Date Sampled Chromium Iron Manganese Nickel
Cleanup Goals - 0.05 - - 0.7CDM1 06-Aug-02 0.01 U 0.05 U 0.013 0.02 UEW-10 06-Aug-02 0.01 U 1.19 0.014 0.02 UMW-4 05-Aug-02 0.01 U 0.05 U 0.021 0.02 UMW-7 05-Aug-02 0.01 U 0.05 U 0.01 U 0.02 UMW-8 06-Aug-02 0.01 U 0.2925 0.018 0.02 UMW-9 06-Aug-02 0.01 U 0.05 U 0.01 U 0.02 UMW-10 07-Aug-02 0.01 U 0.073 0.016 0.02 UMW-11 05-Aug-02 0.01 U 0.05 U 0.042 0.02 UMW-12 07-Aug-02 0.01 U 1.4 1.04 0.064MW-104 07-Aug-02 0.05 U 25 3.4 0.1 UMW-105 07-Aug-02 0.01 U 310 20 0.02 UMW-112 05-Aug-02 0.01 U 0.064 0.01 U 0.02 UMW-113 06-Aug-02 0.01 U 0.117 0.038 0.02 UMW-114 05-Aug-02 0.01 U 5.23 4.25 0.02 UMW-115 05-Aug-02 0.01 U 0.05 U 0.042 0.02 UMW-116 07-Aug-02 0.05 U 11 4.3 0.1 UMW-201 06-Aug-02 0.01 U 0.37 6.7 0.023MW-202 07-Aug-02 0.05 U 22.5 2.24 0.1 UMW-203 05-Aug-02 0.01 U 37.9 7.79 0.02 UMW-204 06-Aug-02 0.01 U 0.05 U 0.182 0.02 UMW-205 05-Aug-02 0.01 U 0.083 6.68 0.02 UMW-206 06-Aug-02 0.01 U 0.133 0.075 0.02 UMW-211 06-Aug-02 0.01 U 0.076 0.047 0.02 UMW-213 06-Aug-02 0.01 U 0.167 0.095 0.02 UMW-215 06-Aug-02 0.01 U 0.05 U 0.01 U 0.02 UMW-216 07-Aug-02 0.01 U 0.973 0.594 0.02 U
Notes: 1. All units are mg/L2. U = Non-dectected
g:\projects\01395022\008\annl_rpt\TBL4-3\AnalyticalFilter_Crosstab 4-6 10/6/2003
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-8 10/6/2003
Figures 5A through 5O also show that prior to startup of the remediation system, five of the wells
in the monitoring program had substantial exceedances of clean-up criteria.
Five wells (MW-213, EW-01, EW-02, EW-03, and EW-09) have consistently had no exceedances
of clean-up criteria for several years. Since 1996, well MW-07 has met clean-up goals for all
compounds with the exception of one sampling round in November 2000. This sampling round
was conducted shortly after installation of the groundwater collection trench.
Concentrations of 1,1-DCA have been oscillating with a downward trend in Well MW-04;
however, the concentrations were still above the clean-up goal for this compound in the August
sampling round. All other compounds measured in well MW-04 have been below the clean-up
goals for several years.
The constituent 1,1-DCA found in wells MW-114 and MW-203 has not shown a considerable
decrease in concentrations since startup of the GWTP. The concentrations of 1,1-DCA appear to
have stabilized above the clean-up goal of 4 µg/L. TCE concentrations in well MW-211 have also
appeared to stabilize above the clean-up goal of 5 µg/L.
Extraction well EW-13A is located in the center of the groundwater collection trench.
Concentrations of all five analytes in this well have been decreasing since the installation of the
trench in October 2000. The concentrations of constituents 1,1,1-TCA, 1,1-DCA and 1,1-DCE in
well EW-13A are the highest concentrations observed in any of the wells with the exception of
well EW-13, which is approximately 10 ft upgradient of well EW-13A. During the last sampling
round, concentrations of 1,1,1-TCA, 1,1-DCA, and 1,1-DCE in well EW-13 were more than an
order of magnitude greater than concentrations of the same constituents in well EW-13A.
The variation in concentrations between these two wells maybe the result of dilution of well
EW-13A concentrations with less contaminated groundwater collected from the north and south
ends of the trench.
In general, the concentration of contaminants in the Hobbs Street Area of the Site appear to have
been decreasing since the beginning of the GWTP operations in 1993. Four of the six
Hobbs Street wells (EW-1, EW-2, EW-3, and MWS-213) have consistently met the clean-up goal
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-9 10/6/2003
for all contaminants from 1997 to the present. Hobbs Street well MWS-211 has achieved the
clean-up goal for all contaminants except TCE.
The Culvert Area wells have also seen a reduction in contaminant concentration since the
beginning of GWTP operation. Well EW-9, an outer tier well in the Culvert Area has achieved the
clean-up goals for all contaminants of concern from 1997 to the present. MW-7 another outer tier
well has achieved clean-up goals for all contaminants of concern from approximately 1996 to
August 2000. Concentrations of 1,1-DCE and 1,1,1-TCA were detected slightly above the
clean-up goals during November 2000 sampling event in well MW-7. However, the results from
the August and December 2002 sampling events indicated that concentrations have since dropped
below the clean-up goals for all compounds. An exceedance of the 1,1-DCA cleanup goal was
observed in the third outer tier well in the Culvert Area (MW-4) during the
August 2002 sampling event. An exceedance of the 1,1-DCA cleanup goal was also observed in
the fourth outer tier well (MW-114) during the August 2002 sample event.
Figures 6A through 6E allow evaluation of contaminant distribution on an analyte-specific basis
by plotting a specific analyte as a percent of clean-up goals for each of the wells graphed. These
figures show that the five analytes evaluated as part of the long-term monitoring program had
substantial exceedances in several wells prior to, or shortly after, startup of the treatment system.
After four years of treatment system operation these exceedances were reduced both in number
and in magnitude for four of these analytes (1,1,1-TCA, 1,1-DCE, 1,2- DCA, and TCE).
Constituent 1,2-DCA was consistently below the clean-up goal from 1999 through 2002 in all the
wells included in the original monitoring program (See Figure 6D).
Samples from twelve wells exceeded the clean-up goals for 1,1-DCA in 2002 including EW-05,
EW-06, EW-07, EW-08, EW-11, EW-12, EW-13, EW-13A, EW-14, MW-4, MW-114, and
MW-203. The compound 1,1-DCA is a breakdown product of 1,1,1-TCA. This may explain the
lesser rate of attenuation of 1,1-DCA when compared to the other chlorinated compounds. Wells
EW-13, EW-13A and EW-14 also exceeded the clean-up goal for 1,1,1-TCA during the 2002
sample events.
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-10 10/6/2003
The aforementioned exceedances for 1,1,-DCA are based on the clean-up goal for 1,1-DCA that
was established in the Record of Decision (ROD) (4 µg/L). At the time the ROD was established,
a federal or state maximum contaminant level had not been established for 1,1-DCA, however in
1996 the NHDES Risk Characterization and Management Policy (RCMP) GW-1 Standard (GW-
1)of 81 µg/L was established. If the 2002 analytical results for the monitoring wells are compared
to the GW-1 standard for 1,1-DCA, only EW-13 and MW 202 would exceed.
Figures 7A through 7G present contaminant concentrations in selected wells on a linear scale and
thus provide additional detail on specific contaminant concentrations and trends in each of the
wells. Figures 7A and 7F have shown a definite downward trend in contaminant concentrations at
the Site since the inception of the groundwater remediation system. However, a stabilizing trend
within particular wells has been more apparent in recent years as shown in Figures 7B, 7D, 7E,
and 7G. Figure 7B shows a general downward trend of 1,1-DCE in monitoring wells
MWS-203 and MWS-205 since the startup of the GWTP. However, the concentrations of
1,1-DCE appear to be stabilizing near the clean-up goal of 7 µg/L. Figure 7D indicates the
concentrations of 1,1-DCA have stabilized in well MWS-203 above the clean-up goal of 4 µg/L
between 1999 and 2002. Figure 7E indicates a stabilization of analyte 1,1-DCA in monitoring well
MW-4. Figure 7G also indicates a stabilizing trend of 1,1-DCA above the clean-up goal in wells
MW-114 and CDM-1. This stabilizing trend of analytes indicates a potential source may be
present on-site that continues to release contaminants to groundwater. Concentrations of
1,1-DCE and 1,1-DCA are continually detected at concentrations exceeding clean-up goals
Figures 7C, 7D, and 7E.
Approximately 49.5% of the contaminant mass in the Culvert Area has been removed via pump
and treat in during the nine years of operation, but 36.6% of the mass was removed during the
first year of operation. An average of less than 2% of the original total mass has been removed per
year for each of the last eight years. At a removal rate of 2% per year of continued operation,
approximately 50 more years would be required to meet cleanup goals.
Following each sample round, Figures 5A through 50, 6A through 6E, and 7A through 7G are
updated to allow ongoing evaluation of the contaminated groundwater remedial action at the Site.
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 4-11 10/6/2003
Although data from extraction wells EW-05, EW-06, EW-07, EW-08, EW-11, and EW-12 are
not plotted, these wells were sampled during the three sampling events in 2002. The analytical
results of all wells sampled in 2002 are reported in Table 4-2.
A summary of historical groundwater monitoring data is provided in Figure 4. Total VOC
concentrations for each of the wells sampled since 1995 is provided for each well location
sampled.
Groundwater samples collected during the August 2002 sampling round were analyzed for metals.
Concentrations of chromium and nickel were below cleanup goals in all samples collected during
this sampling round.
SECTION 5
ADDITIONAL INVESTIGATIONS
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 5-1 10/6/2003
5. ADDITIONAL INVESTIGATIONS
As discussed in the previous section, the concentrations of several chlorinated compounds have
stabilized above cleanup goals in many of the Culvert Area wells. This is an indication that a
continuing source of contamination may be present at the Site. Additional site investigations were
conducted in 2002 to evaluate potential source areas at the Site that may be contributing to
continued contamination of the groundwater.
5.1 PASSIVE SOIL GAS SURVEY
An active soil gas survey initially conducted by EPA in 1999 on the KMC property indicated
elevated levels of 1,1-TCA in vapor along the southwest portion of the KMC building.
In April 2002, a passive soil gas survey, using Gore-Sorber soil gas modules, was conducted to
further investigate potential source areas at the Site. The Gore-Sorber modules utilize a ePTFE
membrane to provide a gas permeable, waterproof layer of protection for the adsorbent media,
which might otherwise come in contact with liquid water or soil particles. The use of engineered
sorbents helps to minimize the water vapor uptake rate on the adsorbent media.
On April 15 and 16, 2002, 50 Gore-Sorber soil gas modules were installed approximately 3 ft bgs
in various locations on a grid laid out across the Site. The Gore-Sorbers were left in place for
approximately 15-16 days. On April 30, 2002, all the Gore-Sorber probes were retrieved and sent
to W.L. Gore & Associates for analyses. The soil gas samples were analyzed for target VOCs
using modified EPA Method 8260. The passive soil gas survey detected concentrations of VOCs
along the northern portion of the KMC building extending to the east of the building. Figure 8
depicts the results of the total VOC analyses of the Gore-Sorber probes. The complete results are
available in the Gore-Sorber Soil Screening Final Report dated May 21, 2002.
5.2 VERTICAL PROFILING INVESTIGATION
Based on previous site investigations and historical analytical results, a modified Waterloo Profiler
(Profiler) was used to collect groundwater samples in areas suspected to be potential sources of
contamination at the Site. The Profiler was able to provide limited vertical profile information of
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 5-2 10/6/2003
the soil stratigraphy, based on hydraulic conductivity and other physical parameters. The Profiler
also facilitated collection of groundwater samples at multiple depths at 23 locations during the
weeks of June 24 and July 1, 2002. Groundwater samples were collected at 5-ft depth intervals at
depths ranging from 10 to 50 ft bgs. The groundwater samples were analyzed for VOCs, specific
conductance, pH, dissolved oxygen, and oxidation-reduction potential. Volatile organic
compound analyses were performed using EPA Method 8260/8260B by the on-site EPA mobile
laboratory using a transportable gas chromatography (GC).
Ten percent (10%) of field samples were sent to the EPA fixed laboratory in Chelmsford, MA for
Quality Control (QC) verification of VOC analyses.
Vertical profiling was used to evaluate changes in contaminant concentrations with depth by
collecting samples at discrete intervals. In addition, using a tool called KPRO attached to the
Profiler tip, a real-time index of hydraulic conductivity was utilized to identify changes in
stratigraphy with depth and to select the optimum depths for sample collection.
Vertical profiling results were utilized to identify source areas and to target specific areas and
depths for additional site investigations. The vertical profiling results identified a VOC source area
between the Culvert Area wells and the old KMC building. The highest VOC concentrations were
observed at the top of a low permeability layer encountered at a depth of approximately 8 ft bgs,
approximately 30 ft southwest of EW-13A. Figure 9 depicts contours of total VOCs
concentrations at the top of the low permeability layer. Groundwater concentrations observed in
monitoring wells were used to extend the contours beyond the immediate vertical profiling study
area. Complete results from the vertical profiling study are available in the Vertical Profiling
Letter Report prepared by WESTON, dated 16 August 2002.
5.3 SOIL SAMPLE INVESTIGATION USING GEOPROBE
Based on the information obtained during the vertical profiling activities and previous site
activities, soil samples were collected to target the identified source areas at the Site and further
define the vertical extent of VOC contamination within the low permeability layer. During the
week of November 12, 2002, a total of 20 borings were completed using truck-mounted
hydraulic-drive/percussion hammer equipment (Geoprobe®). Soil cores were collected in
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 5-3 10/6/2003
transparent acetate sleeves, so that changes in stratigraphy could be observed. Soil samples were
collected from the cores and analyzed for VOCs by the on-site EPA mobile laboratory using a
transportable GC. Ten percent of field samples were sent off-site for QC verification of VOC
analyses.
The initial borings were drilled within the area identified as a potential source area during the
vertical profiling investigation. Subsequent borings were located by moving outward in concentric
circles around the initial borings in an effort to delineate the vertical and lateral extent of the
source area. The borings ranged in depth from approximately 16 to 20 ft. Results of the
on-site GC analysis allowed field decisions to be based on real-time data.
Soil cores were collected from each boring location, and selected soil samples from each boring
were analyzed on-site for VOCs using EPA Method 5035A/8260 by the on-site EPA mobile
laboratory. Eleven soil samples were sent to ESS Laboratory for analysis of fraction organic
carbon. One soil sample was collected for Toxicity Characteristic Leaching Procedure analysis for
metals, VOCs, and semi-volatile organic compounds to determine disposal characteristics of the
soil within the source area. Maximum VOC concentrations detected at each of the Geoprobe®
boring locations are shown on Figure 10. Complete results are available in the Geoprobe Coring
Letter Report prepared by WESTON, dated 17 December 2002.
The Geoprobe® investigation further defined the vertical and lateral extent of the source area
identified during the vertical profiling activities. The information from the Geoprobe® work was
used to estimate volumes of soil that would constitute a �source� and could therefore be
remediated or removed to expedite achievement of cleanup goals by pump and treat.
5.4 AQUITARD (CONFINING) LAYER
Evaluation of the vertical profiling investigation, the Geoprobe investigation, and historic boring
logs of wells installed at the Site confirm the existence of a confining grey silt aquitard located
beneath the site. The top of the aquitard appears to exist at depths varying from 12 to 16 ft bgs in
the Culvert Area extending to depths approximately 45 ft bgs in the Hobbs Street Area. A tan
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 5-4 10/6/2003
clayey silt layer, approximately 2 to 4 ft thick, was observed to overlie the grey silt aquitard in the
Culvert Area.
During the Geoprobe® investigation, soil samples were collected an average of every 2 ft within
the tan clayey silt layer and the grey silt aquitard to determine the depth of penetration of VOCs in
the source area soils at the Site. Based on chemical analyses of the soil samples, the highest
concentrations of VOCs (greater than 1 milligram per kilogram total VOCs) in the Culvert Area
were encountered from approximately 1 ft above the top of the tan clayey silt layer, through the
full depth of the tan clayey silt, and approximately 2 ft into the grey silt aquitard. Therefore, the
majority of the highly concentrated contaminant mass is located in these two layers of low
permeability soils at depths from 7 to 14 ft bgs.
SECTION 6
HISTORICAL GROUNDWATER DATABASE
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 6-1 10/6/2003
6. HISTORICAL GROUNDWATER DATABASE
WESTON has entered all available groundwater analytical data, including monitoring wells,
extraction wells, well points, and catch basins, into an Access database. The soil gas, vertical
profiling groundwater, and geoprobe soil data have not been entered into the database.
A compact disc containing the database with data collected prior to and including
December 2002 is included with this report. The database can be used to conduct queries on the
data to focus on data of particular interest, such as specific wells, contaminants, or sampling
dates. Where contaminant concentrations exceed the established clean-up goals, the
concentrations are presented in red.
SECTION 7
CONCLUSIONS AND RECOMMENDATIONS
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 7-1 10/6/2003
7. CONCLUSIONS AND RECOMMENDATIONS
7.1 CONCLUSIONS
On the western portion of the Site (Hobbs Street Area), it appears that the extraction wells have
continually been very effective in reducing groundwater contamination levels. Groundwater
samples from all of the operating extraction wells (EW-1, EW-2, and EW-3) have contaminant
concentrations below the clean-up goals. However, samples collected from monitoring well
MWS-211 continue to exceed the clean-up goals for TCE.
Although wells in the Hobbs Street Area have continued to show improvement
(VOC concentrations are now below cleanup goals in all but one monitoring well in the
Hobbs Street Area), VOC concentrations in many of the Culvert Area wells have not decreased
significantly since approximately 1997. In well EW-13, groundwater concentrations of the
primary contaminant, 1,1,1-TCA, are more than two orders of magnitude higher than the cleanup
goal 200 µg/L.
The highest groundwater contaminant concentrations observed during the last few years were
located in the Culvert Area in the vicinity of extraction wells EW-8, EW-12, EW-13, and EW-14
and most recently in EW-13A. The contaminant plume appears to be centralized northeast of the
former waste pile and migrating toward the north and east. A passive soil gas survey, vertical
profiling of groundwater concentrations, and soil sample collection using a Geoprobe drill rig
were conducted in 2001 and 2002. These investigations were focused in the Culvert Area where
the highest groundwater concentrations were consistently observed.
Results of the investigations clearly indicated a concentrated source of chlorinated organic
solvents in the Culvert Area of the Site. The vertical and horizontal extent of this source was
delineated, and options for removal or treatment of the source material were evaluated. The
majority of the contaminant mass was observed to be present in the saturated zone in low
permeability soils (silt and clayey silt with hydraulic conductivities on the order of 10-6 centimeter
per second) at a depth of 7 to 14 ft bgs. In situ chemical oxidation or stimulated biodegradation of
the VOCs is not considered feasible because of the high concentrations of VOCs and the difficulty
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 7-2 10/6/2003
associated with distributing amendments in the low permeability soils. The presence of the
chlorinated solvent source in the low permeability soils also means that attainment of cleanup
goals by pump and treat will not be achieved for decades unless other measures are taken to
remove the source. Because of the relatively shallow depth of the source materials, excavation
and off-site disposal will most likely be the most cost-effective approach for expedited removal of
the contaminant mass. More details on the rationale for excavation and off-site disposal of the
source area soils is presented in the Draft Source Removal Justification Memo prepared by
WESTON and dated 7 February 2003.
7.2 RECOMMENDATIONS
It appears unlikely that groundwater clean-up goals will be attained in the Culvert Area within the
next two years without implementing additional remedial measures. Although groundwater
contaminant concentrations have decreased overall at this site, and the plume has decreased in
aerial extent, there continues to be clean-up goal exceedances in multiple wells in the
Culvert Area during each sampling round. The following recommendations are intended to
expedite attainment of cleanup goals in the Culvert Area groundwater, minimize long-term O&M
costs, the following, and keep the treatment plant functioning efficiently throughout the remainder
of its operating life:
1. It is recommended that source area soils with total VOC concentrations greater than 6 mg/kg be excavated and disposed off-site. As discussed in the Draft Source Removal Justification Memo, the current rate of contaminant mass removal via pump and treat is estimated at 2% per year. At this rate, cleanup goals are not likely to be achieved in under 50 years. Removal of soils with VOC concentrations greater than 6 mg/kg will reduce the contaminant mass by 68% and would significantly reduce the length of time required to achieve cleanup goals by pump and treat.
2. It is recommended that a new groundwater extraction trench be installed within the excavated area. The bottom of the trench excavation should be filled with approximately 5 ft of crushed stone. One extraction well should be installed within the trench and piped into the groundwater treatment plant. The new extraction well would eliminate the need for the existing culvert extraction wells. Extraction wells in the culvert area that are not disturbed during the remedial effort should be left for groundwater monitoring.
F:\USER\SHARE\KEARSARGE ESD DOCS\46949\02RPTR_FNL.DOC 7-3 10/6/2003
3. It is recommended that an Explanation of Significant Differences be written changing the existing clean-up goal for 1,1-DCA from 4 µg/L to the NHDES RCMP GW-1 Standard of 81 µg/L.
4. It is recommended that the first carbon vessel be replaced with the second carbon vessel. The spare carbon vessel, currently being stored on-site, should become the new second carbon vessel. The spent carbon from the first vessel should be sent off-site for disposal for regeneration.
5. It is recommended that the packing in the air stripper be acid washed or replaced. The increased loss in pressure across the air stripper is indicative of clogging due to mineral deposits in the Jaeger Tripack packing material.
6. It is recommended that the sludge tank contents be sampled and analyzed for disposal characterization. Supernatant liquid from the sludge tank should be pumped into Tank T-1 and the sludge should be disposed of appropriately off-site.
7. It is recommended that the Hobbs Street wells (EW-1, EW-2, and EW-3) continue to operate since MW-211 continues to exceed the clean-up goal for TCE. The additional water from these wells will lower the average iron and manganese concentrations of the treatment plant influent, thus minimizing operational problems related to high metals concentrations.
8. It is recommended that the deposits be removed from the influent piping between the Hobbs Street wells and the treatment plant by jet cleaning to allow adequate flow from these wells to the plant.
9. The use passive vapor-diffusion samplers should be considered to collect the tri-annual groundwater samples. The sampling should be conducted in accordance with the Guidance on the Use of Passive Vapor-Diffusion Samplers to Detect Volatile Organic Compounds in Groundwater-Discharge Areas and Example Applications in New England, by Chuch, Vroblesky, Lyford and Willey, dated 2002.
10. It is recommended that a chain link fence should be installed around the former KMC building to restrict access to the building by the general public. Results of a safety evaluation conducted by WESTON in 2001 indicated that the walls and roofing of portions of the building were structurally unstable and in danger of collapse.
FIGURES
M:\Design\DWG\KRSARGE\NEW-FIG1.DWG, Model, 09/05/2003 02:20:25 PM, halle, 1:100
EW-06
WP-15
MW-1
LEGEND
EXTRACTION WELL BOX(GROUNDWATER ELEVATION)
EXISTING WELL POINT
MONITORING WELL(GROUNDWATER ELEVATION)
MWS-205^ PROPOSED LONG-TERMEW-09 m MONITORING LOCATION
PROPERTY BOUNDARY
YIELD HOUSEINDUSTRIES,
INC.
Ponded Excavation(Former Landfill)
GRAPHIC SCALE
50 150
100
7 In. = 100 ft
PEQUAWKETPOND
NHDESKMC SUPERFUND SITECONWAY, NEW HAMPSHIRE
OPERATIONS SITE PLAN
MAR 2003 | FIGURE 1
FIGURE 2PROCESS FLOW DIAGRAM
GROUNDWATER REMEDIATION FACILITYKMC SUPERFUND SITE
CONWAY, NEW HAMPSHIRE
DISCHARGETO AIR
HOBBS STREETWELLS (3)
CULVERTAREA
WELLS (9)
EQUALIZATIONTANK
(5,700 GALLON)
FLASHMIX TANK
CLARIFIERTANK
(9,000 GALLON) TRANSFERTANK
ProcessWater
DEEP-BEDSAND
FILTERS(2)
CARBONADSORPTION
UNITS(2)
T-2
POLYMERADDITION
FC-1L
IDHM
L
PRECIPITATION
Sludge
RECYCLETANK
(3,500 GALLON)
SLUDGEHOLDING
TANK(15,000 GALLON)
PLANTEFFLUENTTO SEWER
EFFLUENTHOLDING
TANK(20,000 GALLON)
45
40 --
a.w
Rat
eF
low
H
O
thly
so
35
30
25
20 --
15 --
Figure 3GWTP Average Monthly Flow Rate - Treated
Kearsarge Metallurgical Corporation Superfund Site, 2002 Operations Report
•h-—- 1
-- — 5 avg. flow
10
Jan-02 Feb-02 Mar-02 Apr-02 May-02 Jun-02 Jul-02 Aug-02 Sep-02 Oct-02 Nov-02 Dec-02
Date
MNH:G:\Projects\01395022\008\annlrpt\final\GWTPFLW(Chart1) 10/6/2003
WELLMW-213
WELLMW-218
DATE08/01/9512/07/99
TOT CHL SOLVND
ND*
WELLMW-112
DATE08/01/9512/07/998/5/02
TOT CHL SOLV19.3ND*ND
DATE08/01/9504/03/9608/07/9612/03/9604/17/9708/28/9712/11/9703/30/9808/19/9803/31/9908/16/9912/13/9912/14/9903/27/0008/16/0011/29/008/01/0112/04/0104/05/028/06/0212/04/02
TOT CHL SOLV3225102.1NDNDNDNDND2.4NDND
0.5*NDND
ND, DUP(ND)
NDND
ND, DUPCNDT
V-- 1
WELLEW-04
DATE08/01/95
TOT CHL SOLV1
WELLMW-10
DATE12/07/998/07/02
TOT CHL SOLVNDND
WELLMW-208
DATE08/01/95
TOT CHL SOLV1.4
T\ WELLEW-14
\/e\
WELLMWD-214
WELLEW-03
WELLMW-108
DATE08/01/9512/07/99
TOT CHL SOLV1.4
ND*
WELLEW-01
DATE08/01/9504/03/9608/07/9612/04/9604/17/9708/27/9712/11/9703/30/9808/19/9803/30/9908/16/9912/13/9903/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/0212/04/02
TOT CHL SOLV40.6
3.3NDNDND2.33.8NDND2.73.13.62.3
24.22.2NDND2.5NDND
DATE08/01/9504/03/9608/07/9612/03/9604/16/9708/28/9712/10/9703/30/9808/19/9808/16/9912/13/9903/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/0212/04/02
TOT CHL SOLV6.3
36.931.3
2614.99.88.9
10.55.94.55.7ND2.64.12.3ND2.72.72.32.3
WELLMW-115
DATE08/01/9512/07/9911/30/008/05/02
TOT CHL SOLV22.65.7*9.65.6
Gra velParking
WELLMW-206
DATE08/01/9512/07/998/06/02
TOT CHL SOLVND
ND*ND
CD
WELLMW-8
DATE08/01/9512/08/998/06/02
TOT CHL SOLV6.3
9.1*3.1
DATE04/03/9608/07/9612/03/9604/16/9708/27/9712/10/9703/30/9808/18/9803/30/9908/16/9912/14/9903/27/0008/15/0011/30/005/17/018/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV112.6
579354619
206.1263.8171.1131.8
538296
466*142.8
30186
56580
845105
71377
WELLEW-10
DATE12/08/9911/30/008/06/02
TOT CHL SOLV8.9*7.23.6 0̂
^\
0'
T
WELLMWR-109
WELLMW-11
DATE12/07/998/05/02
TOT CHL SOLV
WELLMWS-209B
5.6*2.7
WELLEW-13
DATE03/30/9908/16/9912/08/9903/27/0008/15/0011/30/0012/04/0104/03/028/05/02
TOT CHL SOLV16200124309462*
7181881015630111001755013570
WELLMW-215
DATE08/01/9512/08/998/06/02
TOT CHL SOLVND
5.7*ND
WELLMW-9
DATE08/01/958/06/02
TOT CHL SOLVNDND
WELLEW-09
DATE04/03/9608/07/9612/03/9604/16/9708/27/9712/10/9703/30/9808/18/9803/30/9908/16/9912/08/9903/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV1730.5
75.535.7
499.5
27.4ND3.66.46.1
53*8.62.2
16.6NDND45
13.4ND
15.1
WELLMW-205
DATE08/01/9504/03/9608/07/9612/03/9604/16/9708/29/9712/10/9703/30/9808/18/9803/31/9908/16/9912/13/9912/14/9912/08/9903/27/0008/15/0011/29/008/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV1035.5
452529506
335.9250.7
248.85184.35
155.4136.5
151.85161.882.0*126*
109.4112.5108.5
37.4, DUP(36)43.9
27, DUP23, DUP24, DUP
272322)
WELLMW-210
DATE08/01/9512/04/01
TOT CHL SOLVNDND
WELLMW-211
DATE08/01/9504/03/9608/07/9612/03/9604/17/9708/28/9712/11/9703/31/9808/19/9803/31/9908/16/9912/13/9912/14/9903/28/0008/16/0011/29/008/01/0112/04/0104/03/028/06/0212/04/02
TOT CHL SOLV90125
23.37.8
19.278
34.764.126.15.8
30.410.36.3*
ND12.313.519.823.532.818.628.8
WELLEW-02
DATE08/01/9504/03/9608/07/9612/03/9604/16/9708/28/9712/10/9703/30/9808/19/9803/30/9908/16/9912/13/9903/27/0008/15/0011/29/005/17/018/01/0112/04/014/03/028/05/0212/04/02
TOT CHL SOLV24.432.326.114.57.72.4NDNDNDNDNDNDND
24.5NDNDNDNDNDND
WELLEW-08
DATE12/08/9903/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV1444*
44502463021799125.92255
19.110.8
o
WELLWP-14
NOTES:1. TOTAL CHLORINATED SOLVENT VALUES ARE THESUMMATION OF DETECTED RESULTS FOR THEFOLLOWING COMPOUNDS : CHLOROFORM,1,1-DICHLOROETHANE, 1,2-DICHLOROETHANE,1,1-DICHLOROETHENE, 1,1,1-TRICHLOROETHANE ANDTRICHLOROETHENE.
2. DUPLICATES IN BOLD.
3. SAMPLES WITH ASTERISK (*) INDICATE SAMPLESANALYZED ON-SITE BY PORTABLE GC.
WELLCDM1
DATE08/01/9504/03/9608/07/9612/03/9604/17/9708/29/9712/11/9703/31/9808/18/9803/31/9908/16/9912/13/9912/14/9903/28/0008/16/0011/30/008/01/0112/05/0104/03/028/06/02
12/04/02
TOT CHL SOLV244.7
18.329.310.311.99.61311
4.619.214.73.0*
10.8.DUPM1.1)14.5,DUP(14.6)
16.218
24.4ND3.93.9
WELLMW-116
DATE08/01/9512/07/9912/04/018/07/02
TOT CHL SOLV9.5
ND*2.5ND
LEGEND
WELL
EXISTING WELL POINT
SURFACE WATER POINT
WELLMW-104
DATE08/01/9512/07/998/07/02
TOT CHL SOLV5.3
ND*ND
KEARSARGEMETALLURGICAL
CORPORA TION
WELLMW-1
DATE08/07/9612/07/9904/03/0212/03/02.
TOT CHL SOLV5.9
0.2*83.5ND
DATE08/15/0011/30/005/17/01
TOT CHL SOLV19071960808
\ \
\ \
WELLWP-15
DATE08/15/0011/30/005/17/01
TOT CHL SOLV7810182
WELLCDM-3
DATE08/01/9512/08/99
TOT CHL SOLV7.8
11.7*
/ •
\
~t
.
\ \
WELLCDM-2
DATE08/01/95
TOT CHL SOLVND
WELLMW-117
DATE08/01/9512/08/99
TOT CHL SOLVND
19.6*
WELLMW-7
DATE08/01/9504/03/9608/07/9612/03/9604/18/9708/27/9712/10/9703/30/9808/18/9803/30/9908/16/9912/13/9912/14/9903/27/0008/15/0011/29/008/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV871.3
8.4189.6195.6
2.27.35
11ND2.53.120
185.7130.8*
58.252
228.6148.7
9.2, DUPO.8)NDNDND
\ v WELL DATE08/15/00
TOT CHL SOLV28.117.1
WELLEW-12
WELLFORMER WASTEPILE SURFACEWATER
TOT CHL SOLV
ND
WELLMW-216
DATE08/01/9512/07/9912/04/018/07/02
TOT CHL SOLV5.1
ND*NDND
04/03/028/05/0212/03/02
WELLMW-102
DATE08/01/9512/08/99
TOT CHL SOLVND
ND*
\
Ponded Excavation(Pormer Landfill)
WELLEW-11
WELLMW-12
DATE08/01/9512/07/998/07/02
TOT CHL SOLV1.3
ND*ND, DUP(ND;
WELLMW107
DATE08/01/9512/07/99
TOT CHL SOLVND
ND*
• i
DATE12/08/9903/27/0008/15/0011/30/005/17/018/01/0112/04/0104/03/028/05/02
TOT CHL SOLV0.5*
NDNDNDNDND
200.117.1ND
DATE TOT CHL SOLV
WELLEW-13A
DATE11/30/0003/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV748058.2
52228.621401831677613594463
WELLMW-202
DATE08/01/95V08/16/9902/08/998/07/02
TOT CHL SOLV27.6
148.718*303
5OLV25.4
19*ND
WELLMW-203
DATE08/01/9504/03/9608/07/9612/03/9604/16/9708/28/9712/10/9703/30/9808/18/9803/30/9908/16/9912/13/9912/14/9912/08/9903/27/0008/15/0011/29/008/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV1024254
104.9334107111
534014040
859113.583.960.5
19.4*21.8*
3738.542.1
97100
33.8130, DUP(129)
32.9
V
WELLMW-114
DATE08/01/9504/03/9608/07/9612/03/9604/16/9708/27/9712/10/9703/30/9808/18/9803/30/9908/16/9912/13/9912/14/9903/27/0008/15/0011/29/008/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV375ND
45.910.2
ND7.52.4ND
16.4ND
16.714
3.1*ND
20.827.632.8
5.8ND
29.49.6
WELLMWR-111
WELLEW-06
DATE12/08/9903/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV15.3*
19.1ND
24.3ND1302503.162ND
WELLMW-106
DATE08/01/9512/08/99
TOT CHL SOLV14.8ND*
WELLMW105
en
1
DATE08/01/9512/02/998/07/02
TOT CHL SOLV2.3
ND*ND
25'±WELLMW-201
DATE08/01/9512/07/998/06/02
TOT CHL SOLVND
ND*ND
WELLEW-05
DATE12/08/9903/27/0008/15/0011/29/005/17/018/01/0112/04/0104/03/028/05/02
TOT CHL SOLV11.7*
15.86.742.8ND59
65.52.8
58.7
WELLsurfacewater, endof culvert
DEPTH
N/A
TOT CHL SOLV
5.2
WELLMW-4
DATE08/01/9508/07/9612/03/9604/18/9708/27/9712/10/9703/30/9808/18/9803/30/9908/16/9912/13/9912/14/9903/27/0008/15/0011/29/008/01/0112/04/0104/03/028/05/0212/03/02
TOT CHL SOLV268
52.33317
42.923.7
7.256.2
4.843.5
6.10.65*
2.54.3ND
23.15.1ND8.4ND
NO. DATE APPR. REVISION NO. DATE APPR. REVISION
NHDESKMC SUPERFUND SITE
CONWAY, NEW HAMPSHIRE
MANCHESTER =» NEW HAMPSHIRE
CHECKED
DES. ENG.
PROJ. ENG.
PROJ. MGR.
APPROVED
APPROVED
DATE CLIENT APPROVALS DATE
ISSUED FOR DATE
NEW HAMPSHIREDEPARTMENT OF
nvironmental. Services
HISTORICAL WELL DATATOTAL CHLORINATED SOLVENTS (ug/L)
1995 THROUGH 2002DRAWN
J.T.SCALE
AS SHOWN
DATE
FEBRUARY 2003W.O. NO.
01395-022-008
DWG. NO.
FIG-4REV. NO
SHT._ - O F .
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-4) 10/6/2003
Figure 5AContaminant Concentrations in Well MW-4 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-7) 10/6/2003
Figure 5BContaminant Concentrations in Well MW-7 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation SystemCleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-114) 10/6/2003
Figure 5CContaminant Concentrations in Well MW-114 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-203) 10/6/2003
Figure 5DContaminant Concentrations in Well MW-203 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-205) 10/6/2003
Figure 5EContaminant Concentrations in Well MW-205 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-211) 10/6/2003
Figure 5FContaminant Concentrations in Well MW-211 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(MW-213) 10/6/2003
Figure 5GContaminant Concentrations in Well MW-213 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(CDM-1) 10/6/2003
Figure 5HContaminant Concentrations in Well CDM-1 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-1) 10/6/2003
Figure 5IContaminant Concentrations in Well EW-1 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corparation Superfund Site
0
1
10
100
1,000
10,000
100,000
Oct-93 Oct-94 Oct-95 Oct-96 Oct-97 Oct-98 Oct-99 Oct-00 Oct-01 Oct-02 Oct-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-2) 10/6/2003
Figure 5JContaminant Concentrations in Well EW-2 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
Oct-93 Oct-94 Oct-95 Oct-96 Oct-97 Oct-98 Oct-99 Oct-00 Oct-01 Oct-02 Oct-03
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-3) 10/6/2003
Figure 5KContaminant Concentrations in Well EW-3 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
Oct-93 Oct-94 Oct-95 Oct-96 Oct-97 Oct-98 Oct-99 Oct-00 Oct-01 Oct-02 Oct-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-9) 10/6/2003
Figure 5LContaminant Concentrations in Well EW-9 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
Oct-93 Oct-94 Oct-95 Oct-96 Oct-97 Oct-98 Oct-99 Oct-00 Oct-01 Oct-02 Oct-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-13) 10/6/2003
Figure 5MContaminant Concentrations in Well EW-13 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
Nov-00 Nov-01 Nov-02
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-13A) 10/6/2003
Figure 5NContaminant Concentrations in Well EW-13A as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
Nov-00 Nov-01 Nov-02
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
100% of Cleanup Goal
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(EW-14) 10/6/2003
Figure 5OContaminant Concentrations in Well EW-14 as a Percent of Cleanup Goals
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
Oct-93 Oct-94 Oct-95 Oct-96 Oct-97 Oct-98 Oct-99 Oct-00 Oct-01 Oct-02 Oct-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
1,1-DCA1,1-DCA NDs1,2-DCA1,2-DCA NDs1,1-DCE1,1-DCE NDs1,1,1-TCA1,1,1-TCA NDsTCETCE NDs
Open marker indicates analyte was not detected above sample detection limit. Marker is plotted at 50% of sample detection limit (TYP.)
October 1993, Start- up of Remediation System
Cleanup Goals:1,1-DCA = 4 mg/l1,2-DCA = 5 mg/l1,1-DCE = 7 mg/l1,1,1-TCA = 200 mg/lTCE = 5 mg/l
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(1,1,1-TCA) 10/6/2003
Figure 6A1,1,1-TCA Concentrations as a Percent of Cleanup Goal
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83 Jan-84 Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
CDM-1EW-9EW-14MW-4MW-7MW-114MW-203MW-205MW-213MW-211EW-01EW-02EW-03EW-13EW-13A
October 1993, Startup of Remediation
100% of Cleanup Goal for 1,1,1-TCA (200 mg/L)
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(1,1-DCE) 10/6/2003
Figure 6B1,1-DCE Concentrations as a Percent of Cleanup GoalKearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83 Jan-84 Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
CDM-1EW-9EW-14MW-4MW-7MW-114MW-203MW-205MW-211MW-213EW-01EW-02EW-03EW-13EW-13A
100% of Cleanup Goal for 1,1-DCE (7 µg/L)
October 1993, Startup of Remediation
`
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(1,1-DCA ) 10/6/2003
Figure 6C-11,1-DCA Concentrations as a Percent of Cleanup Goal
For MW-114, MW-203, MW-205, MW-211, MW-213, EW-13, EW-13AKearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83 Jan-84 Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
MW-114
MW-203
MW-205
MW-211
MW-213
EW-13A
EW-13
100% of Cleanup Goal for 1,1-DCA (4 µg/L)
October 1993, Startup of Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(1,1-DCA (2)) 10/6/2003
Figure 6C-21,1-DCA Concentrations as a Percent of Cleanup Goal
For CDM-1, EW-9, EW-14, MW-4, MW-7, EW-01, EW-02, EW-03Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83 Jan-84 Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
CDM-1
EW-9
EW-14
MW-4
MW-7
EW-01
EW-02
EW-03
100% of Cleanup Goal for 1,1-DCA (4 µg/L)
October 1993, Startup of Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(1,2-DCA) 10/6/2003
Figure 6D1,2-DCA Concentrations as a Percent of Cleanup GoalKearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83 Jan-84 Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
CDM-1MW-4MW-7MW-114MW-203MW-205MW-211MW-213EW-01EW-02EW-03EW-09EW-14EW-13EW-13A
100% of Cleanup Goal for 1,2-DCA (5 µg/L)
October 1993, Startup of Remediation
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(TCE) 10/6/2003
Figure 6ETCE Concentrations as a Percent of Cleanup Goal
Kearsarge Metallurgical Corporation Superfund Site
0
1
10
100
1,000
10,000
100,000
1,000,000
Jan-83 Jan-84 Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n as
a P
erce
nt o
f Cle
anup
Goa
l
CDM-1EW01EW02EW03MW-4MW-7MW-114MW-203MW-205MW-211MW-213EW-09EW-14EW-13EW-13A
100% of Cleanup Goal for TCE (5 µg/L)
October 1993, Startup of Remediation
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(111TCA in MW-7,EW14) 10/6/2003
Figure 7A1,1,1-TCA Concentration in Well MW-7
Kearsarge Metallurgical Corporation Superfund Site
0
5,000
10,000
15,000
20,000
25,000
Jan-83
Jan-84
Jan-85
Jan-86
Jan-87
Jan-88
Jan-89
Jan-90
Jan-91
Jan-92
Jan-93
Jan-94
Jan-95
Jan-96
Jan-97
Jan-98
Jan-99
Jan-00
Jan-01
Jan-02
Jan-03
Con
cent
ratio
n of
1,1
,1-T
CA
in M
W-7
( µg/
L)
MW-7EW-14
Cleanup Goal for 1,1,1-TCA (200 µg/L)
October 1993, Startup of Groundwater Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(11DCE in MWS203 & 205) 10/6/2003
Figure 7B1,1-DCE Concentration in Wells MWS-203 & MWS-205Kearsarge Metallurgical Corporation Superfund Site
0
50
100
150
200
250
300
350
400
Jul-92 Jul-93 Jul-94 Jul-95 Jul-96 Jul-97 Jul-98 Jul-99 Jul-00 Jul-01 Jul-02 Jul-03
Con
cent
ratio
n ( µ
g/L
)
MWS-203MWS-205
Cleanup Goal for 1,1-DCE (7 µg/L)
October 1993, Startup of Groundwater Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(11DCE in EW-14) 10/6/2003
Figure 7C1,1-DCE Concentration in Well EW-14
Kearsarge Metallurgical Corporation Superfund Site
0
100
200
300
400
500
600
700
800
900
Jul-92 Jul-93 Jul-94 Jul-95 Jul-96 Jul-97 Jul-98 Jul-99 Jul-00 Jul-01 Jul-02 Jul-03
Con
cent
ratio
n ( µ
g/L
)
EW-14
Cleanup Goal for 1,1-DCA (4 µg/L)
October 1993, Startup of Groundwater Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(11DCA in MWS-203,211,114) 10/6/2003
Figure 7D1,1-DCA Concentration in Wells MWS-203, MWS-211, & MWS-114
Kearsarge Metallurgical Corporation Superfund Site
0
100
200
300
400
500
600
700
800
900
Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n ( µ
g/L
)
MWS-203MWS-211MWS-114
Cleanup Goal for 1,1-DCA (4 µg/L)
October 1993, Startup of Groundwater Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(11DCA in MW-4,EW14,CDM1) 10/6/2003
Figure 7E1,1-DCA Concentration in Well MW-4, CDM-1, EW-14Kearsarge Metallurgical Corporation Superfund Site
0
50
100
150
200
250
300
350
400
450
500
Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n ( µ
g/L
)
MW-4EW-14CDM-1
Cleanup Goal for 1,1,-DCA (4 µg/L)
October 1993, Startup of Groundwater Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(TCE in MWS-211& 213) 10/6/2003
Figure 7FTCE Concentration in Wells MWS-211 & MWS-213
Kearsarge Metallurgical Corporation Superfund Site
0
200
400
600
800
1,000
1,200
1,400
1,600
Jul-92 Jul-93 Jul-94 Jul-95 Jul-96 Jul-97 Jul-98 Jul-99 Jul-00 Jul-01 Jul-02 Jul-03
Con
cent
ratio
n ( µ
g/L
)
MWS-211MWS-213
Cleanup Goal for TCE (5 µg/L)
October 1993, Startup of Groundwater Remediation System
FSMNH01\PROJECTS\01395022\008\DATABASE\KMSANLY1(11DCA in MW-114&CDM1) 10/6/2003
Figure 7G1,1-DCA Concentration in Wells MW-114 & CDM-1
Kearsarge Metallurgical Corporation Superfund Site
0
200
400
600
800
1,000
1,200
1,400
Jan-85 Jan-86 Jan-87 Jan-88 Jan-89 Jan-90 Jan-91 Jan-92 Jan-93 Jan-94 Jan-95 Jan-96 Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03
Con
cent
ratio
n ( µ
g/L
)
MW-114CDM-1
Cleanup Goal for 1,1,-DCA (4 µg/L)
October 1993, Startup of Groundwater Remediation System
t. now.L
•v H
Scale 1:1200S O 1 0 0 15C 3CQ L11-:
12.3593.Q&3
0.4970.361
0.1900.1370.1000.Q720.052
o.raa0,020
Total Target VOCa
GORE-SORBER^Screening Survey
W.L. GORE 4 ASSOCIATES, INCBOULEviKO
Hill i l i ff*i
Roy F, Weston, Inc., Manchester, NHKearsarge Metallurgical Corpri Conwayt NH
Total Target VOCs
a-' t ^ULt
110WIM -ti
CARROLLINDUSTRIES
VERTICAL PROFILE ID
VP-01 (1)
VP-02
VP-03
VP-04
VP-05
VP-06
VP-07
VP-08 (2)
VP-09
VP-10
VP-11
VP-12
VP-13
VP-14 (3)
VP-15
VP-16
VP-17
VP-18
VP-19
VP-20
VP-21
VP-22
VP-23 (3)
INTERPRETED DEPTHTO SILT LENSE (FT
BGS)7'
8'
9'
11'
±13'
±17'
7-8'
7'
8'
7'
8'
8'
10'
8'
8'
15'
16'
3B'
8'
10'
9'
10'
42 '
DEPTH OF SAMPLE(FT BGS)
5.00'
7.00'
7.80'
9.75'
14.00'
18.10'
6.70'
7.01'
6.20'
6.18'
7.10'
7.10'
9.24'
6.10'
7.00'
13.58'
19.40'
39.60'
6.38'
10.67'
5.78'
5.92'
32.82'
TOTAL VOC CONC^(MG/L)
9.6
1663
32.1
0.13
0.70
ND
66100
258
54.10
1035
1393
2404
40.2
21.60
6250
4.90
0.40
13.3
106
21.0
42.0
109
19.9
(1) SAMPLE COLLECTED 2 FT.(2) HIGHEST CONCENTRATIONS(3) HIGHEST CONCENTRATIONS
NOTE: CONTOURS DEVELOPED2002 PROFILING AND RECENT
ABOVE TOP OF SILTAT WATER TABLE AND TOP OF SILTWERE NOT AT TOP OF SILT
USING ANALYTICAL RESULTS FROM JUNE/JULYHISTORICAL GROUNDWATER DATA.
KEARMETALLURCORPORATIO
Excavation
LEGEND
© VERTICAL PROFILE
• 0 - WELL
WELL POINT
EXISTING WELL POINT
• SURFACE WATER POINT
NOTE
CONCENTRATIONS IN ppb (TOTAL VOC)
NHDESKMC SUPERFUND SITE
CONWAY, NEW HAMPSHIRE
NEW HAMPSHIRE
CLIENT APPROVALS
nvironmentalServices
VERTICAL PROFILE INVESTIGATIONTOTAL VOC CONCENTRATION
CONTOURS AT TOP OF SILT LAYER
BEG
AS SHOWN
AUG 2002W.O. NO.
01395-022-007FIG 9
KEARSARGEMETALLURGICALCORPORATION
GROUNDWATERCOLLECTIONTRENCH
GP-15H
(8964)
GP-12H
(10838)GP-18H
(2193)
\ GP-08\ (922) GP-20
H(3446)
H GPV13
(3920)GP-TQ
(1769)
GP-07
(2760)
LEGEND
TOTAL VOC CONCENTRATION IN PPB
APPROXIMATE SCALE IN FEET
NHDESKMC SUPERFUND SITE
CONWAY, NEW HAMPSHIRE
NEW HAMPSHIRE
CLIENT APPROVALS
InvironmentalServices
GEOPROBE CORE INVESTIGATIONCONTOURS OF MAXIMUM DETECTED TOTAL
VOC CONCENTRATION IN EACH BORING
A.J.M.
AS SHOWN
FEB 2003
01395-022-008FIG. 10