PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
© Ontario Power Generation Inc., 2013. This document has been produced and distributed for Ontario Power Generation Inc. purposes only. No part of this document may be reproduced, published, converted, or stored in any data retrieval system, or transmitted in any form or by any means (electronic, mechanical, photocopying, recording, or otherwise) without the prior written permission of Ontario Power Generation Inc.
Program Schedule Management Plan
NK38-PLAN-09701-10067-0004-R001 2013-03-27
Order Number: N/A
Other Reference Number:
Internal Use Only
Prepared by: Robert Adly Section Manager-Process Scheduling Nuclear Refurbishment
Reviewed by: Derek McAuley Manager, Project Management Office Nuclear Refurbishment
Approved by: Gary Rose
Director, Planning & Project Control Nuclear Refurbishment
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 2 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
Revision Summary
Revision Number Date Comments
R001 2013-03-27 Modified to explain the interfaces between L3 schedules and Proliance for Earned Value calculation.
R000 2013-01-31 Initial issue.
Reviewed and updated to reflect planning development and new governance structure.
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 3 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
Table of Contents
Page
Revision Summary ........................................................................................................................ 2
1.0 PROGRAM DESCRIPTION ........................................................................................... 4
2.0 THE OVERALL PLANNING AND SCHEDULING PROCESS: ..................................... 4
3.0 SCHEDULE INTEGRATION .......................................................................................... 5
4.0 DEVELOPMENT OF WORK BREAKDOWN STRUCTURE (WBS) ............................. 6
4.1 Modification of the WBS ................................................................................................. 6
5.0 SCHEDULES BASELINE .............................................................................................. 6
5.1 Overall Program Schedules Baseline ............................................................................. 6 5.2 Contractor’s baseline schedules .................................................................................... 7 5.3 Milestone Management .................................................................................................. 7 5.4 Schedule Contingency ................................................................................................... 8
6.0 SCHEDULE CHANGE MANAGEMENT ........................................................................ 8
7.0 BASIS OF SCHEDULES DOCUMENTS ....................................................................... 9
8.0 SCHEDULE MONITORING AND CONTROL ................................................................ 9
8.1 Schedule reporting (metrics and reports) ..................................................................... 10
9.0 PROGRAM SCHEDULE MANAGEMENT AND CONTROLS GOVERNANCE .......... 10
Appendix A: Darlington Refurbishment Schedule Integration ................................................... 11
Appendix B: Darlington Refurbishment Work Breakdown Structure ......................................... 12
Appendix C: Key Program Milestones (as of January 1, 2013) ................................................. 14
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 4 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
1.0 PROGRAM DESCRIPTION
Refer to Program Structure and Summary Plan NK38-PLAN-09701-10067-0001 as well as D-PCH-09701-10000, R001, Darlington Refurbishment Project Charter.
2.0 THE OVERALL PLANNING AND SCHEDULING PROCESS:
The overall planning and scheduling process can be represented in two major stages:
(a) Project Planning and Schedule Development, resulting in the formation of a Baseline Schedule
(b) Schedule Management, Monitoring, Analysis, Reporting, and Mitigation, resulting in regular periodic schedule updates
The planning process uses a top-down approach for schedule development and a bottom-up approach for schedule management.
The three levels of schedule hierarchy are outlined below; an overview of how the schedules interact with each other is included in Appendix A –Darlington Refurbishment Schedule Integration Overview.
Level 1 - Management Summary Level
The level 1 schedule provides a high-level management summary of the project. It will represent all Units, Phases, Bundles, Program and key project milestones.
The level 1 schedule is a roll up from the Level 2 Co-ordination and Control Schedule.
The schedule is prepared by OPG as part of the initial planning phase of the project and updated to reflect the progression of planning, i.e. as projects are better defined, the Level 2 Control and Co-ordination Schedule is updated.
Level 2 – Co-ordination and Control Schedule (C&C Schedule)
The level 2 schedule covers the scope of work by Phase, Unit USI, and Type of work and contains full Critical Path Method (CPM) logic. It is referred to as the C&C schedule, or, Control and Co-ordination schedule, as this is the schedule which will be used, at the Phase and Unit level, to track the overall schedule status of the Program. It will be updated and controlled by OPG and based on the Contractors detailed Level 3 Schedules. The following are some key features of the level 2 schedule:
Contains an adequate number of activities with realistic activity durations to clearly show the sequence and logic in performing all projects, within the Program, at the Phase and Unit level, in a systematic manner. It will include all interfaces between OPG and contractor, and or between contractors.
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 5 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
Defines the Program critical path and activity total floats
Level 3 – Detailed Schedules
The level 3 detailed schedules will be prepared by the group executing the work, mainly suppliers and contractors, however, in some case by OPG where OPG is self-performing work. The schedule must be prepared in accordance with the Program’s Work Breakdown Structure (“WBS”) and coding guideline. This schedule contains the lowest level of detail required to manage and execute the work. It is structured in a way to allow summarizing of the activities in order to update the Level 2 C&C Schedule.
The Level 3 will include the full scope of each suppliers / contractor showing all interfaces with other contractors / OPG.
The Schedule will be resource loaded to the lowest level of the defined Resource Breakdown Structure as agreed by OPG.
The Schedule will define all long lead procurements.
After being captured as a baseline, the schedule will be regularly updated, providing the basis for status reporting, progress physical percent complete at the activity / Work Package Level, forecasting, and change management.
All supplier / contractor baseline schedules needs to be approved by OPG to ensure program milestones, WBS and scheduling guidelines and coding are followed.
Schedule variances and mitigation plans will be analyzed from the Level 3 schedule.
Daily, Weekly and Monthly look-ahead reports will be generated from Level 3 schedule.
This method will also be utilized where OPG is self performing the work
3.0 SCHEDULE INTEGRATION
All Contractors' Level 3 Schedules or OPG Functional detailed schedule are fully aligned, utilizing a common Work Breakdown Structure and coding guideline, and integrated in the overall C& C Schedule.
The C&C Schedule will be the program’s basis for measuring schedule progress.
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 6 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
4.0 DEVELOPMENT OF WORK BREAKDOWN STRUCTURE (WBS)
As per PMI’s Practice Standard for WBS, second edition, Chapter 2: “The WBS subdivides the project work into smaller, more manageable pieces of work, with each descending level of the WBS representing an increasingly detailed definition of the project work. The planned work contained in the lowest level WBS components, which are work packages (WP), can be scheduled, cost estimated, monitored, and controlled.”
The WBS is subdivided to Bundles as related to Scope and aligned with contracting strategy.
Each work package (WP) is assigned an owner by the Project Management Team (PMT), called “Account Owner” (AO), who is accountable to the performance of the WP.
Every WP is represented with at least one activity in the C&C Schedule that integrates into Proliance for Earned Value calculations. The WP can be represented in Level 1, C&C and in the Detailed Level 3 schedule, as needed.
The WBS is controlled by the Program Management Office (PMO) Scheduling Group and is available from within Primavera Planner (P6). A visual copy of the WBS structure is included as Appendix B – Darlington Refurbishment WBS Structure.
4.1 Modification of the WBS
Modification of the WBS may be required for any new, removal of existing, or splitting of WBS elements.
All requests to modify the WBS shall be forwarded to the Scheduling Group who will update the master WBS structure and ensure a common implementation
5.0 SCHEDULES BASELINE
5.1 Overall Program Schedules Baseline
As project planning progresses in the Definition Phase of the Program, the overall Program Baseline will be updated and finally released, as Revision 0 (“zero”) at time of the Release Quality Estimate (RQE); October 15, 2015. However, the C&C Schedules will be prepared and issued as Revision A, B, C for the purpose of monitoring progress prior to RQE.
Revision A will be released after the initial setup of the C&C Schedules, further revisions will be issued as required as individual bundles passes through Gate 2 &3.
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 7 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
5.2 Contractor’s baseline schedules
Contractor’s baseline schedules will be reviewed to ensure compliance with program milestones, WBS and Scheduling guideline and will be released for use and monitoring after OPG Review.
L3 Schedule variances and progress measurement will be based on the Contractor’s baseline schedules
5.3 Milestone Management
Milestones within the Program will be managed at various levels per the following:
All phases will be controlled by Program Milestones. Adherence to milestone timelines and definitions is essential to ensure a successful Refurbishment. Refer to N-MAN-00120-10001 Nuclear Refurbishment – Milestone Definition Framework for the following:
Milestone Tier Structure Milestone Numbering Nomenclature Common Milestone Definition Template Milestone Completion Progress Monitoring Quality Requirements for Milestone Deliverables Milestone Closeout and Document Retention Requirements
Milestone Tier Structure identifies Key Program and Project Control Milestones. The Tiers are linked to the level of the Organization that the Milestone is reportable to and the Approval Level required for any deviation to the Milestone
(a) Program Tier 1 - Commitments to the Board of Directors
Reportable to: EVP Nuclear Refurbishment
Definition: Milestones that are commitments to the Board or decisions at Board Level.
Example: RQE Release Quality Estimate, and Unit Start/Finish dates
(b) Program Tier 2 – Critical Impact
Reportable to: EVP Nuclear Refurbishment
Definition: Milestones that are critical to the Program, normally documented in Phased based Program BCS’s per Release Strategy.
Example: CNSC Approval of ISR
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 8 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
(c) Program Tier 3 – Program Controls
Reportable to: SVP Direct Reports
Definition: Milestones that manage the health of the Program and keep it on track.
Example: All Projects Scope Freeze/Detailed Eng. Finished
(d) Project Tier 4 – Project Gates
Reportable to: VP Refurbishment Execution
Definition: Project Gates (checkpoints of project preparation progress at which funding is released for the next phase).
Example: G0 Project Scope Approval, G3 Definition Phase
(e) Project Tier 5 – Standard Project Milestones & Project Manager Milestones
Reportable to: Project Manager
Definition: Milestones that are within the gated process and are specific to the project life cycle.
Example: Turbine Generator Project Charter Approved (CHR), Management Plans completed, Project Long Lead Materials
Appendix C – Key Program Milestones provides a listing of the Tier 1 and 2 Program level milestones.
5.4 Schedule Contingency
Schedule contingency will be managed according to the Darlington Refurbishment Risk Management Plan, NK38-PLAN-09701-10067-Sht 0006.
6.0 SCHEDULE CHANGE MANAGEMENT
Changes to the baseline scope will be managed through a formal Change Control process as per the Program Cost Management Plan, N-MAN-00120-10001-PC-R000 and implemented at all levels of schedule.
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 9 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
7.0 BASIS OF SCHEDULES DOCUMENTS
Contractors must issue a basis of schedule document with the submission of the baseline schedule. The document must include the following:
Summary description of the scope and main deliverables
List of all Project/Payment milestones and key dates
WBS / Primavera files structures and integration
Coding structures for generating the various Schedules layouts
Calendars used with the various activities
Productivity rates / Assumptions
Benchmarking to similar projects for duration assumption
Progress measurement process for all work packages
Regular scheduling reports
8.0 SCHEDULE MONITORING AND CONTROL
The contractor’s / OPG Level 3 Schedule will be updated regularly using OPG guidelines. During the planning phase, schedules will be updated at least once per month; during execution, that will increase to as frequently as needed to manage the schedule, i.e. critical path activities may be updated daily, near critical path activities weekly, and others monthly.
Variance / critical path analysis, and percent complete at the work package level will be prepared for every schedule on a monthly basis.
OPG will assign a single point of contact or SPOC for each schedule; the SPOC will review the contractor’s schedule and prepare highlights of issues / corrective actions required and take appropriate steps working through the project team and the contractor to resolve.
The Level 3 will be summarized in order to update the Coordination and Control schedule.
Overall program variance / critical path analysis will be prepared from the C&C Schedule by OPG’s Program Management Office (Project Planning and Controls).
Forecast dates at the work package level and percent complete will be integrated with the Earned Value Software (“Proliance”) from L3 Schedules prepared by contractors or OPG, if they self performed the work.
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 10 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
8.1 Schedule reporting (metrics and reports)
Various reports and Metrics will be generated and published on the Program’s website within SharePoint.
9.0 PROGRAM SCHEDULE MANAGEMENT AND CONTROLS GOVERNANCE
Additional information, based on the Project Management Standard (N-STD-AS-0028), on the schedule management processes utilized by the Refurbishment Program can be found within the Project Management E-Manual (N-MAN-00120-10001, chapter or sheet “SCH”).
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 11 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
Appendix A: Darlington Refurbishment Schedule Integration
Level 3 Schedules Level 0, 1, 2
Risk Management
Estimating and Cost Control
Change Management
Prepare Level 3 Schedules following OPG WBS/Coding/Scheduling management guidelinePrepare basis of schedule documents/progress measurement proceduresCode Level 3 activity to allow roll up to the required Level 2 detailsProvide physical % complete to Level 3 activity and roll up to work package level (WP)Prepare Level 3 Schedule variance analysisPrepare level 3 Critical Path analysis
External Contractor
OPG (for OPG Managed Scope)
The Control & Coordination Schedule (C&C) Integrated Master Schedule
Schedules Integration
OversightQuality check all Level 3 Schedules
Monthly update Level 2 activity based on ALL Level 3 schedulesPrepare overall Program Critical Path analysisProvide Level 2 Schedule variance analysisProvide Percent Progress Complete by Work Package
OPG
Proliance for Earned Value Caluclation
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 12 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
Appendix B: Darlington Refurbishment Work Breakdown Structure
CONFIDENTIAL - FOR INTERNAL USE ONLYDarlington Refurbishment ProgramWork Breakdown Structure (WBS)REV 0 31-Jan-2013
Page 1 of 2
Darlington Refurbishment Program
Bundle 1 Bundle 2 Bundle 3Functional Deliverable
OPG Oversight & Integration Deliverable (Bundle Management)
Sub Bundle Sub BundleExecution Management
Division AProject Controls
Division B
UC U2 U1 U3 U4 UC U2 U1 U3 U4 UC U2 U1 U3 U4 UC U2 U1 U3 U4 UC U2 U1 U3 U4
Engineering Deliverable
Procurement Deliverable
ExecutionTesting &
CommissioningClose Out
Deliverable
Preliminary Engineering
Detailed Engineering
Group of Systems/Tools
Series
Group of Systems/Tools
Series
Group of Systems/Tools
Series
Group of Systems/Tool
Series
System A/Series X
System B/Series Y
WP1
WP2
See Page 2
“Scenario B”
“Scenario A”
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 13 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
CONFIDENTIAL - FOR INTERNAL USE ONLYDarlington Refurbishment ProgramSchedules Integration with WBSREV 0 31-Jan-2013
Page 2 of 2
Work Package
Schedule Level 0
Schedule (C&C) Level 2
Schedule Level 3
Level 2 ID
WP1
“Scenario A”
Work Package
Schedule Level 0
Schedule (C&C) Level 2
Schedule Level 3
Level 2 ID A
WP2
Level 2 ID B
Level 2 ID C
Activity X
Activity Z
L2 ID A
“Scenario B”
Control Account
Work Package
Work Package
Work Package
At the Work Package level budget and % progress will be calculated
WP1
WP2
WP3
CA
At the Control Account level
SPI/CPI will be calculated
Actual Spent
Activity Y
L2 ID Summary
WP Summary
WP Summary
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 14 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
Appendix C: Key Program Milestones (as of January 1, 2013)
I
Regulatory Key 031 ... Common
RGOIO ~"'M>n3g&"""'o.ciononlSR RG020 CI'tSC Accepmce oIlSR Proced • ...,
RG030 s.b:n .. """, 01 Ell Prcject Oesc'l'bm RGIli 1 S<b:nOSSlOll 01 DNGS l..t:ens. E>5e1lSlOfl,oq,lic..wn RG040 &b:nisoiOll 01 Fin:IIlSR ReJ>crt RGWJ S\b:nisoi<Jn of E1SfTSO'~ RG060 CNSC 9:;111 ...... F .... ISR Repo1 So.Ac;..ey ReYiew RGIlI5 CNSC fA _rog RG080 C<mont Uc""",, End D.1!e RG070 CNSC 0..:: ...... on fA RG075 CNSC Af>pIIN:aI for tmSi' l.Jcens.e Renewal RG090 CNSC Ce1I'ic:lllion of RWC Tf~ P:Ict:lQlO Des"" RGl00 CNSCSI:oIIAs.....".ntolF .... ISR Rep:>f1 RGl 10 ~,"""ofllP& Uanse R...-..IApPicotion RGI20 IPAw""'" byCNSC R"'IIul~l cry Key 031 ... 101 Un ll 2
RGI25 Ul Request Sit>mos,."n 01 OJI:Ige FNI ",","",:lis RGI30 U1CNSCOubge FiI:Il"w""'*" Place RG 140 Ul Res\art llc ........ Aj>pr<:l\lOlld
Rtil,l131cry K"I 031.,. 10' Unit! RG!43 Ul~tSo.bmiui:mdOJI3geF .... Jwr(f< ... RGI47 UI CHSCOuUgo Fnol"'Rl_*" PtIu RGI50 U1RMIC01Uc",,",,~
Rtogublory Key O.lIes lor Unit 3 RGl53 U3I«!questSWn .. ..,ndOJbgeFNI~. RG157 U3CNSCOutage Fn:.I~_ ... Pbce RG100 U3Resbr1l.ic ..... ~
Regulatory K"'Y DalesIo. unit.
RG 163 U4 ~t Sit>m • .,,,on 01 OJI:Ige F .... "'""""' ... RG167 U4 CNSC()uQge Fn:lI-""'''''' ..... PI.xe RGl70 U4ResI:lrtl.Jc""",,~OYeCI
Progr.m Rei.n. 0.1" RLll25 ReL4B: o.t.:.ilod Pbrnng RMooo ... B RLOOO ReLStfJROE: UnillOWga FW"""" RI1l4O R .... 7: 1JniI10u1ageReI"""" RlD50 Rel8: 1Jni130WgeReleose RlO6O Rel.9-Unl40ubg&ReI_
Out.ge Prep.r.lion Key Oat • • Unit Common Outage Prep Key OJ!es RPl20 Etv""""'9 ~p Premq ........ b ~ConIrxls(E:o:d_ 1lOp) RPI30 AlIP\"qects DeYiledEngineemg FiroIsI...t
Unit 2 Ouu.;. p,,,,, K~ O~I" 01'2040 U1LongLIYdM.lleri:>l. Id .... ed 0P1056 U1 Prq&<I Clablod Engneanng Fnohad (DMgn Mod Ii: ..... n CIoo.'n_ Finilhed) 0P2010 U11'1a"k Pacbglls ...... """9 ~Iete 0P20fi{I U1Re1urb Readi ....... AMes,....."", Fnshed
I
I5-Jar..2016
2S-~-20 1 9
15-,*",-2012 A
15-,*",·1011A 15-0<1·2015' 15-M:ly-2017" Ol-Feb-2019"
'''''''-15-~·2013
1 S-~.2013
15-'*"'· 2014
I I
31·Dec·2014 04-O<1·2010A :JO..Oec -20 lO A 2S-~-2OIl A 28-J...-2011 A 27-0<1-2011 A 0I.o.: ·201 1A Q6.Feb-2012A 03-(Mc..20I]A 2S-Feb-2013-:JO-~-2Ot3'
Ol-May-2013' 15-J...-2013' 0S-J .... 201Y 01.0.:-2013' 31.0.: ·2014' 1S-M.v·2019 1S-Jar..201S' 15-J .... 2OIS· 1s.r..br-2019'
'>So>""" 2S-Aug-2017" 25-Feb-20111" 15-Sap-2CI2Cr IS-Feb-2m2 2S-~-2019'
2Ml<I-2019' 15-Feb-2022' I S-M;oy-20Z3
Q6.0a:.2CJ20'
Q6.~-2011 '
15-May-2IlZ1' 15-J .... 2D20
()6.~.202T
15-Aug-2015 15-~-2013·
15-Aug-2015' 1S-J .... 2016 15-/11(>;·2014' 15-Aug-1015' 15-Sap-2015' 15-{)ct-2015'
,n
I
R-UuI3! ory Key 031 ... Common
RGOIO Pf'*>Cd .. M:In:Igo ...... ~""" on ISR RG020 CHSC Al:a:pI.1nCfI eliSA Procedol"f!
RGOlD &b:n" ...... cf Ell Prqect OescfllbOn RG051 Sl.b:nos""", of DNGS lJtens. ElSen.",,, AppIoca:.n
RG040 S<b:nio""" 01 FRli ISR ReJ1c<t RG(RI SWmi""icnolElSlTSO's RGOOJ CNSC Stall,."., F""'IISR RIIipo1 S~ ~ RG(JI5 CNSC EA I-Iaomg RGIl80 c.m.nlUc,,- End D3Ie RG070 eNS(; Oecsoon on Ell RG075 cnsc il9pllNoi for tNiSF I.Jcens.e R"""""'" RG090 CHSCCeniic:lbonclRWC T ....... ptft>Iion """*",,,"Oesl{rl RGl00 CNSCSt"",,"sessmenlalFNlISR RspOO RG 110 S...,,,,i .. i,,,, 01 UP & li"","" R-...oI Applic:olion
I
O4-0d:·2tI10A
I I
31.0.<: -:1014
04.Qa·201DA 3O-Dec-20IOA
2S-~-201! " 2S-J1n-2011 A 27.Qd·201 I II 01-Dec ·2011 A 06-F.t>-2012" OJ...l)8c..2012A 2S-FeI>-2(1)-
3O-~-2013'
OI-M3y-20!3" 15-J...-2013' 05-J .. 2013" 02.o.c·20I3'
RGI20 IIP~ IJtQISC Ihg ul310ry lIoy 031 ... for Un ll 2 •-"'~'"'C-- 31.0.:-2014'
1!>-Jan-2O'S I!>-Mot·20I'il
RGt2!) Ul FWJuest SlJ:mISSIOn cI 0..1:Ige FnaI Appro<I*
RG 130 Ul CW;C 0UI:Ige Fi-<l1 ""''''''. n Pbce RGI40 U2 ResIOrt llcoose Aj>prowd R-Uul~l ory KII'/ 031.,. lor Unll! RG143 UI RequestSoilm • .,ndo..i.19t F .... 1q>rcw. RG141 UI CNSCOut>go F .... 'AfIP""' ... Pbut RGI50 U1RaL1rll.Jc"-~
R"II 1I131ory Key O~tes lor Un n 3 RGI53 U3 I«1ques1SWm .. ..,nclOJI3geFNI ~aIs RG I!IJ' U3CNSCOutage F .... IIW_* n Pbut RG160 U3Resbr1l.ic .... Aw<-d
Roogulatcry 1'1"1 D3!"fDf Untl 4
RG1&3 U4~Slbm"""'n olOJI3ge F""AppI(H*
RG167 U4 CHSCOWge Fn:lIAw"""* flPI:>ao RGli'O U4 Rilsurt l.Jc ....... A;Ipr.,..,.;l
Program Release OatH RLIIl5 ReL4B; Doot.>olod Pbrnng RaIe.> .. H RLOOO ReL5.1lIROE: Unl20tA:1g8 ReI_ RUI40 ReL7_lIniI 1 0u1ageR!!I"""" RlD50 ReL8- Unl 30Wge R!!I"""" RlII60 ReL9-Unl40ulag&RIII_
Out.lge Pre~r.tlon Key Ome. UM Common OUlJge Prep K, y OJ!" RPI20 Engo~WPPr"""'llJl!l_bM:lpCtnrxls(Exd!lOP)
RP1 Xl ;\jI Pr"l_ DetaHd~gfinoshod
Un~ 2 OUI."IJ' p,,,!) K'Y OJI" 0P2040 U2 Long lf3d r.I:JIergI, ld""";ed 0P1055 U2 Prq&c:I Doot.>olod EngnefIIItIQ Fn!illad (DM9' Modfie ....... Doorn_ FInished) 0P2010 U2\'\O"kPxbgolsAs .. ~Ccmp,"", 0f'2II6II U21«!1\..t> Rmdj ...... """"",.." .... Fn!illad
2S--'"9-2tI17
28-~-2tI19
O6-0d:.2!J20
15-,*",-2012 A
15-_·2012A IS-Oa.201S' 15-M.1y-2017" 01-Feb-2019" IS--Ju1-2tI2O' 15-,lp-·2013
15-,lp-.XI13
15-"""'·2014
~
D)!:('~N '-rf"'nl' I"" -,,\
15-..1an-2016" 1S-J .. 201S-1s.-r..ur-2019'
,- "" 25-Aug-201r 25-FeI>-2018" 15-S.2CI2O" I !>-Feb-2022
26-~-2019'
28-0d-2019"
I5-F ... 2Il22' 15-M;rr:1023
Q6.0a.2O:2D" 0S-~-2021 '
15-M3y-2Il23"
''''''''''
06-..... ·2021
15-""-9-201S
lS--.o1v-2013· 1S--Aug-2015' 15-J .... 2016
l!i--/11<H·2014· 15-1I<.Ig.201S· IS-So!p.201S· 1S--Od-201S·
Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4
Plan
Internal Use Only Document Number: Usage Classification:
NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:
0004 R001 15 of 15 Title:
PROGRAM SCHEDULE MANAGEMENT PLAN
N-TMP-10010-R010 (Microsoft® 2007)
I I
and
0P2100 and Tools On Site Untt 1 Out3ge Prep Ke-y DJles 2~Joo-20 1 6
OP1040 UllongLeadMaterialsldentified
OP1055 U 1 Project Detailed El'O]i"oeering Fnished (Desgn Mod licafun Do<unoots Finished) OP1070 U 1 W<rl Pac~ Assessng Corrplele OP1060 Ul Refl.rl!Readiress OP1100 Ullkli1lnilial Slagel.oberi:Jls&TooIsooSiIe
Untt 3 Out3ge Prep Ke-y DJles 2S-f eb-2018
OP3050 U3long Lead Materials Identified
OP3055 U3 Project Detailed El'O]i"oeering Fnished (Desgn Mod licafun Do<unoots Finished) 0P3070 U3 W<rl Pac~ Assessng Corrplele OP3060 U3 Refl.rl! Readiress
0P3100 U3 Initial Stao.;e Maleoials & Tools on Site Untt 4 Out3ge Prep Ke-y DJles 06-Aug-2019
OP4040 U4long Lead Materials Identified
OP4055 U4 Project Detailed El'O]i"oeering Fnished (Desgn Mod licafun Do<unoots Finished) OP4070 U4 W<rl Pac~ Assessng Corrplele OP4100 U4 Initial Stao.;e Ml1llfials & Tools on Site
Outage Execution Key Oates 1~Oct-2016
Untt 2 Refurb 15.-0ct-2016
I I
2f>-f eb-2018 25-Jln-2016' 25-Mar-201r 2S-Apr-2017' 2S-May-201r 2f>-Feb-20l 0' 2S-0ct-2019
28-Feb-2010'
28-No<i-2010' 28-Dec-2010' 28-J:n-2019' 28-0ct-2019'
O&-Apr-2021
06-Aug-2019' 06-May-2020' 06-Jln-2020' 06-Apr-2021 ' 27-Feb-2024
24-Dec-2019
24-Dec-2019'
01-Jln-2021 ' 2S-J3/l-202Q 3O-NO'V-2022
~e:;::== ~""",~",,,. 15.-Dec-20.24
27-Feb-2024'
15.-Dec-2024
-=-~
I
I I I
and
0P2100 ard Tools On Site
Un~ 1 Out3ge Prep 25.-Joo-2016
OP1040 U 1 Long Lead Materi:>ls kloolilied 2!>-.hn-2!l16' OP1G55 Ul Project DEtailed Engi-oe"';ng Fnshed (Desgn ModkaOOn DooJnoots Firished) I 25-Mar-2017'
OP1070 VI ....... k Packages Assessng Gorrplele 25.-Apr-2017'
OP1060 Ul ReI\.rilRm<i...".. :::--1'i'~"",~~"'~H~' OP1100 Ul Uri! InIia'Sia ge ~s& TooIs,..oo",,"~'-.__ I 25.-Feb-2018' Un~ 3 Out3ge Prep Ke-y Dales 2S-f eb-20 18 28-0Cl-2019
OP3050 U3 Long Lead Materi:>ls kloolilied ,23-Feb-2010' OP3055 U3 Project DEtailed Engi-oe"';ng Fnshed (Desgn ModkaOOn DooJnoots Firished) I 23-NtJ,.-2018'
0P3070 U3 ....... k Packages Assessng Gorrplele 28-0ec-201B'
OP3060 U3 Rel\.ril Rm<i...".. ----+1 28-J:n-2019' 0P3100 U3 IrOIiai Sla!;e Ml1enals & Trot<; on Site 28-0<:1-2019' Un~ 4 Out3ge Prep Ke-y Dales 0&-Aug-20 19 O&-Apr-2021
OP4040 U4 Long Lead Materi:>ls kloolilied ----li"'""'""~ "',. OP4055 U4 Project DEtailed Engi-oe"';ng Fnshed (Desgn ModkaOOn DooJnoots Firished) 1OG-M.y-202U'
OP4070 U4 ....... k Packages Assessng_Gorrplele 06-Joo-2020' OP4100 U4 lnilial Stao.;e Ml!OO35 & Tools on Site OS-Apr-2021'
Outage Execution Key Dates I!>-Od-2016 27-Feb-2024 Un~ 2 Refurb 1!>-Ocl-2016 24-Oec-2019
U4 FtII PIH/", & Handove< !oDNGS
Program Closeout Key Dates CL1M DR Ptogam Frul Accepta....,
I!>-Oct-2016'
15-Dec-2024
24-Oec-2019'
3O-Nov-2022'
27-Feb-2024'
1!HJec-2024
1!>-Dec-2024"