Plan Internal Use Only Document Number: Usage Classification: NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page: 0004 R001 1 of 15 Title: PROGRAM SCHEDULE MANAGEMENT PLAN N-TMP-10010-R010 (Microsoft® 2007) © Ontario Power Generation Inc., 2013. This document has been produced and distributed for Ontario Power Generation Inc. purposes only. No part of this document may be reproduced, published, converted, or stored in any data retrieval system, or transmitted in any form or by any means (electronic, mechanical, photocopying, recording, or otherwise) without the prior written permission of Ontario Power Generation Inc. Program Schedule Management Plan NK38-PLAN-09701-10067-0004-R001 2013-03-27 Order Number: N/A Other Reference Number: Internal Use Only Prepared by: Robert Adly Section Manager-Process Scheduling Nuclear Refurbishment Reviewed by: Derek McAuley Manager, Project Management Office Nuclear Refurbishment Approved by: Gary Rose Director, Planning & Project Control Nuclear Refurbishment Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Internal Use ... · NK38-PLAN-09701-10067 ... The level 1 schedule is a roll up from the Level 2 Co-ordination and Control Schedule

  • Upload
    ngokhue

  • View
    215

  • Download
    2

Embed Size (px)

Citation preview

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 1 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

© Ontario Power Generation Inc., 2013. This document has been produced and distributed for Ontario Power Generation Inc. purposes only. No part of this document may be reproduced, published, converted, or stored in any data retrieval system, or transmitted in any form or by any means (electronic, mechanical, photocopying, recording, or otherwise) without the prior written permission of Ontario Power Generation Inc.

Program Schedule Management Plan

NK38-PLAN-09701-10067-0004-R001 2013-03-27

Order Number: N/A

Other Reference Number:

Internal Use Only

Prepared by: Robert Adly Section Manager-Process Scheduling Nuclear Refurbishment

Reviewed by: Derek McAuley Manager, Project Management Office Nuclear Refurbishment

Approved by: Gary Rose

Director, Planning & Project Control Nuclear Refurbishment

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 2 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

Revision Summary

Revision Number Date Comments

R001 2013-03-27 Modified to explain the interfaces between L3 schedules and Proliance for Earned Value calculation.

R000 2013-01-31 Initial issue.

Reviewed and updated to reflect planning development and new governance structure.

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 3 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

Table of Contents

Page

Revision Summary ........................................................................................................................ 2 

1.0  PROGRAM DESCRIPTION ........................................................................................... 4 

2.0  THE OVERALL PLANNING AND SCHEDULING PROCESS: ..................................... 4 

3.0  SCHEDULE INTEGRATION .......................................................................................... 5 

4.0  DEVELOPMENT OF WORK BREAKDOWN STRUCTURE (WBS) ............................. 6 

4.1  Modification of the WBS ................................................................................................. 6 

5.0  SCHEDULES BASELINE .............................................................................................. 6 

5.1  Overall Program Schedules Baseline ............................................................................. 6 5.2  Contractor’s baseline schedules .................................................................................... 7 5.3  Milestone Management .................................................................................................. 7 5.4  Schedule Contingency ................................................................................................... 8 

6.0  SCHEDULE CHANGE MANAGEMENT ........................................................................ 8 

7.0  BASIS OF SCHEDULES DOCUMENTS ....................................................................... 9 

8.0  SCHEDULE MONITORING AND CONTROL ................................................................ 9 

8.1  Schedule reporting (metrics and reports) ..................................................................... 10 

9.0  PROGRAM SCHEDULE MANAGEMENT AND CONTROLS GOVERNANCE .......... 10 

Appendix A:  Darlington Refurbishment Schedule Integration ................................................... 11 

Appendix B:  Darlington Refurbishment Work Breakdown Structure ......................................... 12 

Appendix C:  Key Program Milestones (as of January 1, 2013) ................................................. 14 

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 4 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

1.0 PROGRAM DESCRIPTION

Refer to Program Structure and Summary Plan NK38-PLAN-09701-10067-0001 as well as D-PCH-09701-10000, R001, Darlington Refurbishment Project Charter.

2.0 THE OVERALL PLANNING AND SCHEDULING PROCESS:

The overall planning and scheduling process can be represented in two major stages:

(a) Project Planning and Schedule Development, resulting in the formation of a Baseline Schedule

(b) Schedule Management, Monitoring, Analysis, Reporting, and Mitigation, resulting in regular periodic schedule updates

The planning process uses a top-down approach for schedule development and a bottom-up approach for schedule management.

The three levels of schedule hierarchy are outlined below; an overview of how the schedules interact with each other is included in Appendix A –Darlington Refurbishment Schedule Integration Overview.

Level 1 - Management Summary Level

The level 1 schedule provides a high-level management summary of the project. It will represent all Units, Phases, Bundles, Program and key project milestones.

The level 1 schedule is a roll up from the Level 2 Co-ordination and Control Schedule.

The schedule is prepared by OPG as part of the initial planning phase of the project and updated to reflect the progression of planning, i.e. as projects are better defined, the Level 2 Control and Co-ordination Schedule is updated.

Level 2 – Co-ordination and Control Schedule (C&C Schedule)

The level 2 schedule covers the scope of work by Phase, Unit USI, and Type of work and contains full Critical Path Method (CPM) logic. It is referred to as the C&C schedule, or, Control and Co-ordination schedule, as this is the schedule which will be used, at the Phase and Unit level, to track the overall schedule status of the Program. It will be updated and controlled by OPG and based on the Contractors detailed Level 3 Schedules. The following are some key features of the level 2 schedule:

Contains an adequate number of activities with realistic activity durations to clearly show the sequence and logic in performing all projects, within the Program, at the Phase and Unit level, in a systematic manner. It will include all interfaces between OPG and contractor, and or between contractors.

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 5 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

Defines the Program critical path and activity total floats

Level 3 – Detailed Schedules

The level 3 detailed schedules will be prepared by the group executing the work, mainly suppliers and contractors, however, in some case by OPG where OPG is self-performing work. The schedule must be prepared in accordance with the Program’s Work Breakdown Structure (“WBS”) and coding guideline. This schedule contains the lowest level of detail required to manage and execute the work. It is structured in a way to allow summarizing of the activities in order to update the Level 2 C&C Schedule.

The Level 3 will include the full scope of each suppliers / contractor showing all interfaces with other contractors / OPG.

The Schedule will be resource loaded to the lowest level of the defined Resource Breakdown Structure as agreed by OPG.

The Schedule will define all long lead procurements.

After being captured as a baseline, the schedule will be regularly updated, providing the basis for status reporting, progress physical percent complete at the activity / Work Package Level, forecasting, and change management.

All supplier / contractor baseline schedules needs to be approved by OPG to ensure program milestones, WBS and scheduling guidelines and coding are followed.

Schedule variances and mitigation plans will be analyzed from the Level 3 schedule.

Daily, Weekly and Monthly look-ahead reports will be generated from Level 3 schedule.

This method will also be utilized where OPG is self performing the work

3.0 SCHEDULE INTEGRATION

All Contractors' Level 3 Schedules or OPG Functional detailed schedule are fully aligned, utilizing a common Work Breakdown Structure and coding guideline, and integrated in the overall C& C Schedule.

The C&C Schedule will be the program’s basis for measuring schedule progress.

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 6 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

4.0 DEVELOPMENT OF WORK BREAKDOWN STRUCTURE (WBS)

As per PMI’s Practice Standard for WBS, second edition, Chapter 2: “The WBS subdivides the project work into smaller, more manageable pieces of work, with each descending level of the WBS representing an increasingly detailed definition of the project work. The planned work contained in the lowest level WBS components, which are work packages (WP), can be scheduled, cost estimated, monitored, and controlled.”

The WBS is subdivided to Bundles as related to Scope and aligned with contracting strategy.

Each work package (WP) is assigned an owner by the Project Management Team (PMT), called “Account Owner” (AO), who is accountable to the performance of the WP.

Every WP is represented with at least one activity in the C&C Schedule that integrates into Proliance for Earned Value calculations. The WP can be represented in Level 1, C&C and in the Detailed Level 3 schedule, as needed.

The WBS is controlled by the Program Management Office (PMO) Scheduling Group and is available from within Primavera Planner (P6). A visual copy of the WBS structure is included as Appendix B – Darlington Refurbishment WBS Structure.

4.1 Modification of the WBS

Modification of the WBS may be required for any new, removal of existing, or splitting of WBS elements.

All requests to modify the WBS shall be forwarded to the Scheduling Group who will update the master WBS structure and ensure a common implementation

5.0 SCHEDULES BASELINE

5.1 Overall Program Schedules Baseline

As project planning progresses in the Definition Phase of the Program, the overall Program Baseline will be updated and finally released, as Revision 0 (“zero”) at time of the Release Quality Estimate (RQE); October 15, 2015. However, the C&C Schedules will be prepared and issued as Revision A, B, C for the purpose of monitoring progress prior to RQE.

Revision A will be released after the initial setup of the C&C Schedules, further revisions will be issued as required as individual bundles passes through Gate 2 &3.

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 7 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

5.2 Contractor’s baseline schedules

Contractor’s baseline schedules will be reviewed to ensure compliance with program milestones, WBS and Scheduling guideline and will be released for use and monitoring after OPG Review.

L3 Schedule variances and progress measurement will be based on the Contractor’s baseline schedules

5.3 Milestone Management

Milestones within the Program will be managed at various levels per the following:

All phases will be controlled by Program Milestones. Adherence to milestone timelines and definitions is essential to ensure a successful Refurbishment. Refer to N-MAN-00120-10001 Nuclear Refurbishment – Milestone Definition Framework for the following:

Milestone Tier Structure Milestone Numbering Nomenclature Common Milestone Definition Template Milestone Completion Progress Monitoring Quality Requirements for Milestone Deliverables Milestone Closeout and Document Retention Requirements

Milestone Tier Structure identifies Key Program and Project Control Milestones. The Tiers are linked to the level of the Organization that the Milestone is reportable to and the Approval Level required for any deviation to the Milestone

(a) Program Tier 1 - Commitments to the Board of Directors

Reportable to: EVP Nuclear Refurbishment

Definition: Milestones that are commitments to the Board or decisions at Board Level.

Example: RQE Release Quality Estimate, and Unit Start/Finish dates

(b) Program Tier 2 – Critical Impact

Reportable to: EVP Nuclear Refurbishment

Definition: Milestones that are critical to the Program, normally documented in Phased based Program BCS’s per Release Strategy.

Example: CNSC Approval of ISR

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 8 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

(c) Program Tier 3 – Program Controls

Reportable to: SVP Direct Reports

Definition: Milestones that manage the health of the Program and keep it on track.

Example: All Projects Scope Freeze/Detailed Eng. Finished

(d) Project Tier 4 – Project Gates

Reportable to: VP Refurbishment Execution

Definition: Project Gates (checkpoints of project preparation progress at which funding is released for the next phase).

Example: G0 Project Scope Approval, G3 Definition Phase

(e) Project Tier 5 – Standard Project Milestones & Project Manager Milestones

Reportable to: Project Manager

Definition: Milestones that are within the gated process and are specific to the project life cycle.

Example: Turbine Generator Project Charter Approved (CHR), Management Plans completed, Project Long Lead Materials

Appendix C – Key Program Milestones provides a listing of the Tier 1 and 2 Program level milestones.

5.4 Schedule Contingency

Schedule contingency will be managed according to the Darlington Refurbishment Risk Management Plan, NK38-PLAN-09701-10067-Sht 0006.

6.0 SCHEDULE CHANGE MANAGEMENT

Changes to the baseline scope will be managed through a formal Change Control process as per the Program Cost Management Plan, N-MAN-00120-10001-PC-R000 and implemented at all levels of schedule.

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 9 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

7.0 BASIS OF SCHEDULES DOCUMENTS

Contractors must issue a basis of schedule document with the submission of the baseline schedule. The document must include the following:

Summary description of the scope and main deliverables

List of all Project/Payment milestones and key dates

WBS / Primavera files structures and integration

Coding structures for generating the various Schedules layouts

Calendars used with the various activities

Productivity rates / Assumptions

Benchmarking to similar projects for duration assumption

Progress measurement process for all work packages

Regular scheduling reports

8.0 SCHEDULE MONITORING AND CONTROL

The contractor’s / OPG Level 3 Schedule will be updated regularly using OPG guidelines. During the planning phase, schedules will be updated at least once per month; during execution, that will increase to as frequently as needed to manage the schedule, i.e. critical path activities may be updated daily, near critical path activities weekly, and others monthly.

Variance / critical path analysis, and percent complete at the work package level will be prepared for every schedule on a monthly basis.

OPG will assign a single point of contact or SPOC for each schedule; the SPOC will review the contractor’s schedule and prepare highlights of issues / corrective actions required and take appropriate steps working through the project team and the contractor to resolve.

The Level 3 will be summarized in order to update the Coordination and Control schedule.

Overall program variance / critical path analysis will be prepared from the C&C Schedule by OPG’s Program Management Office (Project Planning and Controls).

Forecast dates at the work package level and percent complete will be integrated with the Earned Value Software (“Proliance”) from L3 Schedules prepared by contractors or OPG, if they self performed the work.

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 10 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

8.1 Schedule reporting (metrics and reports)

Various reports and Metrics will be generated and published on the Program’s website within SharePoint.

9.0 PROGRAM SCHEDULE MANAGEMENT AND CONTROLS GOVERNANCE

Additional information, based on the Project Management Standard (N-STD-AS-0028), on the schedule management processes utilized by the Refurbishment Program can be found within the Project Management E-Manual (N-MAN-00120-10001, chapter or sheet “SCH”).

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 11 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

Appendix A: Darlington Refurbishment Schedule Integration

Level 3 Schedules Level 0, 1, 2

Risk Management

Estimating and Cost Control

Change Management

Prepare Level 3 Schedules following OPG WBS/Coding/Scheduling management guidelinePrepare basis of schedule documents/progress measurement proceduresCode Level 3 activity to allow roll up to the required Level 2 detailsProvide physical % complete to Level 3 activity and roll up to work package level (WP)Prepare Level 3 Schedule variance analysisPrepare level 3 Critical Path analysis

External Contractor

OPG (for OPG Managed Scope)

The Control & Coordination Schedule (C&C) Integrated Master Schedule

Schedules Integration

OversightQuality check all Level 3 Schedules

Monthly update Level 2 activity based on ALL Level 3 schedulesPrepare overall Program Critical Path analysisProvide Level 2 Schedule variance analysisProvide Percent Progress Complete by Work Package

OPG

Proliance for Earned Value Caluclation

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 12 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

Appendix B: Darlington Refurbishment Work Breakdown Structure

CONFIDENTIAL - FOR INTERNAL USE ONLYDarlington Refurbishment ProgramWork Breakdown Structure (WBS)REV 0 31-Jan-2013

Page 1 of 2

Darlington Refurbishment Program

Bundle 1 Bundle 2 Bundle 3Functional Deliverable

OPG Oversight & Integration Deliverable (Bundle Management)

Sub Bundle Sub BundleExecution Management

Division AProject Controls

Division B

UC U2 U1 U3 U4 UC U2 U1 U3 U4 UC U2 U1 U3 U4 UC U2 U1 U3 U4 UC U2 U1 U3 U4

Engineering Deliverable

Procurement Deliverable

ExecutionTesting &

CommissioningClose Out

Deliverable

Preliminary Engineering

Detailed Engineering

Group of Systems/Tools

Series

Group of Systems/Tools

Series

Group of Systems/Tools

Series

Group of Systems/Tool

Series

System A/Series X

System B/Series Y

WP1

WP2

See Page 2

“Scenario B”

“Scenario A”

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 13 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

CONFIDENTIAL - FOR INTERNAL USE ONLYDarlington Refurbishment ProgramSchedules Integration with WBSREV 0 31-Jan-2013

Page 2 of 2

Work Package

Schedule Level 0

Schedule (C&C) Level 2

Schedule Level 3

Level 2 ID

WP1

“Scenario A”

Work Package

Schedule Level 0

Schedule (C&C) Level 2

Schedule Level 3

Level 2 ID A

WP2

Level 2 ID B

Level 2 ID C

Activity X

Activity Z

L2 ID A

“Scenario B”

Control Account

Work Package

Work Package

Work Package

At the Work Package level budget and % progress will be calculated

WP1

WP2

WP3

CA

At the Control Account level

SPI/CPI will be calculated

Actual Spent

Activity Y

L2 ID Summary

WP Summary

WP Summary

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 14 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

Appendix C: Key Program Milestones (as of January 1, 2013)

I

Regulatory Key 031 ... Common

RGOIO ~"'M>n3g&"""'o.ciononlSR RG020 CI'tSC Accepmce oIlSR Proced • ...,

RG030 s.b:n .. """, 01 Ell Prcject Oesc'l'bm RGIli 1 S<b:nOSSlOll 01 DNGS l..t:ens. E>5e1lSlOfl,oq,lic..wn RG040 &b:nisoiOll 01 Fin:IIlSR ReJ>crt RGWJ S\b:nisoi<Jn of E1SfTSO'~ RG060 CNSC 9:;111 ...... F .... ISR Repo1 So.Ac;..ey ReYiew RGIlI5 CNSC fA _rog RG080 C<mont Uc""",, End D.1!e RG070 CNSC 0..:: ...... on fA RG075 CNSC Af>pIIN:aI for tmSi' l.Jcens.e Renewal RG090 CNSC Ce1I'ic:lllion of RWC Tf~ P:Ict:lQlO Des"" RGl00 CNSCSI:oIIAs.....".ntolF .... ISR Rep:>f1 RGl 10 ~,"""ofllP& Uanse R...-..IApPicotion RGI20 IPAw""'" byCNSC R"'IIul~l cry Key 031 ... 101 Un ll 2

RGI25 Ul Request Sit>mos,."n 01 OJI:Ige FNI ",","",:lis RGI30 U1CNSCOubge FiI:Il"w""'*" Place RG 140 Ul Res\art llc ........ Aj>pr<:l\lOlld

Rtil,l131cry K"I 031.,. 10' Unit! RG!43 Ul~tSo.bmiui:mdOJI3geF .... Jwr(f< ... RGI47 UI CHSCOuUgo Fnol"'Rl_*" PtIu RGI50 U1RMIC01Uc",,",,~

Rtogublory Key O.lIes lor Unit 3 RGl53 U3I«!questSWn .. ..,ndOJbgeFNI~. RG157 U3CNSCOutage Fn:.I~_ ... Pbce RG100 U3Resbr1l.ic ..... ~

Regulatory K"'Y DalesIo. unit.

RG 163 U4 ~t Sit>m • .,,,on 01 OJI:Ige F .... "'""""' ... RG167 U4 CNSC()uQge Fn:lI-""'''''' ..... PI.xe RGl70 U4ResI:lrtl.Jc""",,~OYeCI

Progr.m Rei.n. 0.1" RLll25 ReL4B: o.t.:.ilod Pbrnng RMooo ... B RLOOO ReLStfJROE: UnillOWga FW"""" RI1l4O R .... 7: 1JniI10u1ageReI"""" RlD50 Rel8: 1Jni130WgeReleose RlO6O Rel.9-Unl40ubg&ReI_

Out.ge Prep.r.lion Key Oat • • Unit Common Outage Prep Key OJ!es RPl20 Etv""""'9 ~p Premq ........ b ~ConIrxls(E:o:d_ 1lOp) RPI30 AlIP\"qects DeYiledEngineemg FiroIsI...t

Unit 2 Ouu.;. p,,,,, K~ O~I" 01'2040 U1LongLIYdM.lleri:>l. Id .... ed 0P1056 U1 Prq&<I Clablod Engneanng Fnohad (DMgn Mod Ii: ..... n CIoo.'n_ Finilhed) 0P2010 U11'1a"k Pacbglls ...... """9 ~Iete 0P20fi{I U1Re1urb Readi ....... AMes,....."", Fnshed

I

I5-Jar..2016

2S-~-20 1 9

15-,*",-2012 A

15-,*",·1011A 15-0<1·2015' 15-M:ly-2017" Ol-Feb-2019"

'''''''-15-~·2013

1 S-~.2013

15-'*"'· 2014

I I

31·Dec·2014 04-O<1·2010A :JO..Oec -20 lO A 2S-~-2OIl A 28-J...-2011 A 27-0<1-2011 A 0I.o.: ·201 1A Q6.Feb-2012A 03-(Mc..20I]A 2S-Feb-2013-:JO-~-2Ot3'

Ol-May-2013' 15-J...-2013' 0S-J .... 201Y 01.0.:-2013' 31.0.: ·2014' 1S-M.v·2019 1S-Jar..201S' 15-J .... 2OIS· 1s.r..br-2019'

'>So>""" 2S-Aug-2017" 25-Feb-20111" 15-Sap-2CI2Cr IS-Feb-2m2 2S-~-2019'

2Ml<I-2019' 15-Feb-2022' I S-M;oy-20Z3

Q6.0a:.2CJ20'

Q6.~-2011 '

15-May-2IlZ1' 15-J .... 2D20

()6.~.202T

15-Aug-2015 15-~-2013·

15-Aug-2015' 1S-J .... 2016 15-/11(>;·2014' 15-Aug-1015' 15-Sap-2015' 15-{)ct-2015'

,n

I

R-UuI3! ory Key 031 ... Common

RGOIO Pf'*>Cd .. M:In:Igo ...... ~""" on ISR RG020 CHSC Al:a:pI.1nCfI eliSA Procedol"f!

RGOlD &b:n" ...... cf Ell Prqect OescfllbOn RG051 Sl.b:nos""", of DNGS lJtens. ElSen.",,, AppIoca:.n

RG040 S<b:nio""" 01 FRli ISR ReJ1c<t RG(RI SWmi""icnolElSlTSO's RGOOJ CNSC Stall,."., F""'IISR RIIipo1 S~ ~ RG(JI5 CNSC EA I-Iaomg RGIl80 c.m.nlUc,,- End D3Ie RG070 eNS(; Oecsoon on Ell RG075 cnsc il9pllNoi for tNiSF I.Jcens.e R"""""'" RG090 CHSCCeniic:lbonclRWC T ....... ptft>Iion """*",,,"Oesl{rl RGl00 CNSCSt"",,"sessmenlalFNlISR RspOO RG 110 S...,,,,i .. i,,,, 01 UP & li"","" R-...oI Applic:olion

I

O4-0d:·2tI10A

I I

31.0.<: -:1014

04.Qa·201DA 3O-Dec-20IOA

2S-~-201! " 2S-J1n-2011 A 27.Qd·201 I II 01-Dec ·2011 A 06-F.t>-2012" OJ...l)8c..2012A 2S-FeI>-2(1)-

3O-~-2013'

OI-M3y-20!3" 15-J...-2013' 05-J .. 2013" 02.o.c·20I3'

RGI20 IIP~ IJtQISC Ihg ul310ry lIoy 031 ... for Un ll 2 •-"'~'"'C-- 31.0.:-2014'

1!>-Jan-2O'S I!>-Mot·20I'il

RGt2!) Ul FWJuest SlJ:mISSIOn cI 0..1:Ige FnaI Appro<I*

RG 130 Ul CW;C 0UI:Ige Fi-<l1 ""''''''. n Pbce RGI40 U2 ResIOrt llcoose Aj>prowd R-Uul~l ory KII'/ 031.,. lor Unll! RG143 UI RequestSoilm • .,ndo..i.19t F .... 1q>rcw. RG141 UI CNSCOut>go F .... 'AfIP""' ... Pbut RGI50 U1RaL1rll.Jc"-~

R"II 1I131ory Key O~tes lor Un n 3 RGI53 U3 I«1ques1SWm .. ..,nclOJI3geFNI ~aIs RG I!IJ' U3CNSCOutage F .... IIW_* n Pbut RG160 U3Resbr1l.ic .... Aw<-d

Roogulatcry 1'1"1 D3!"fDf Untl 4

RG1&3 U4~Slbm"""'n olOJI3ge F""AppI(H*

RG167 U4 CHSCOWge Fn:lIAw"""* flPI:>ao RGli'O U4 Rilsurt l.Jc ....... A;Ipr.,..,.;l

Program Release OatH RLIIl5 ReL4B; Doot.>olod Pbrnng RaIe.> .. H RLOOO ReL5.1lIROE: Unl20tA:1g8 ReI_ RUI40 ReL7_lIniI 1 0u1ageR!!I"""" RlD50 ReL8- Unl 30Wge R!!I"""" RlII60 ReL9-Unl40ulag&RIII_

Out.lge Pre~r.tlon Key Ome. UM Common OUlJge Prep K, y OJ!" RPI20 Engo~WPPr"""'llJl!l_bM:lpCtnrxls(Exd!lOP)

RP1 Xl ;\jI Pr"l_ DetaHd~gfinoshod

Un~ 2 OUI."IJ' p,,,!) K'Y OJI" 0P2040 U2 Long lf3d r.I:JIergI, ld""";ed 0P1055 U2 Prq&c:I Doot.>olod EngnefIIItIQ Fn!illad (DM9' Modfie ....... Doorn_ FInished) 0P2010 U2\'\O"kPxbgolsAs .. ~Ccmp,"", 0f'2II6II U21«!1\..t> Rmdj ...... """"",.." .... Fn!illad

2S--'"9-2tI17

28-~-2tI19

O6-0d:.2!J20

15-,*",-2012 A

15-_·2012A IS-Oa.201S' 15-M.1y-2017" 01-Feb-2019" IS--Ju1-2tI2O' 15-,lp-·2013

15-,lp-.XI13

15-"""'·2014

~

D)!:('~N '-rf"'nl' I"" -,,\

15-..1an-2016" 1S-J .. 201S-1s.-r..ur-2019'

,- "" 25-Aug-201r 25-FeI>-2018" 15-S.2CI2O" I !>-Feb-2022

26-~-2019'

28-0d-2019"

I5-F ... 2Il22' 15-M;rr:1023

Q6.0a.2O:2D" 0S-~-2021 '

15-M3y-2Il23"

''''''''''

06-..... ·2021

15-""-9-201S

lS--.o1v-2013· 1S--Aug-2015' 15-J .... 2016

l!i--/11<H·2014· 15-1I<.Ig.201S· IS-So!p.201S· 1S--Od-201S·

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4

Plan

Internal Use Only Document Number: Usage Classification:

NK38-PLAN-09701-10067 Sheet Number: Revision Number: Page:

0004 R001 15 of 15 Title:

PROGRAM SCHEDULE MANAGEMENT PLAN

N-TMP-10010-R010 (Microsoft® 2007)

I I

and

0P2100 and Tools On Site Untt 1 Out3ge Prep Ke-y DJles 2~Joo-20 1 6

OP1040 UllongLeadMaterialsldentified

OP1055 U 1 Project Detailed El'O]i"oeering Fnished (Desgn Mod licafun Do<unoots Finished) OP1070 U 1 W<rl Pac~ Assessng Corrplele OP1060 Ul Refl.rl!Readiress OP1100 Ullkli1lnilial Slagel.oberi:Jls&TooIsooSiIe

Untt 3 Out3ge Prep Ke-y DJles 2S-f eb-2018

OP3050 U3long Lead Materials Identified

OP3055 U3 Project Detailed El'O]i"oeering Fnished (Desgn Mod licafun Do<unoots Finished) 0P3070 U3 W<rl Pac~ Assessng Corrplele OP3060 U3 Refl.rl! Readiress

0P3100 U3 Initial Stao.;e Maleoials & Tools on Site Untt 4 Out3ge Prep Ke-y DJles 06-Aug-2019

OP4040 U4long Lead Materials Identified

OP4055 U4 Project Detailed El'O]i"oeering Fnished (Desgn Mod licafun Do<unoots Finished) OP4070 U4 W<rl Pac~ Assessng Corrplele OP4100 U4 Initial Stao.;e Ml1llfials & Tools on Site

Outage Execution Key Oates 1~Oct-2016

Untt 2 Refurb 15.-0ct-2016

I I

2f>-f eb-2018 25-Jln-2016' 25-Mar-201r 2S-Apr-2017' 2S-May-201r 2f>-Feb-20l 0' 2S-0ct-2019

28-Feb-2010'

28-No<i-2010' 28-Dec-2010' 28-J:n-2019' 28-0ct-2019'

O&-Apr-2021

06-Aug-2019' 06-May-2020' 06-Jln-2020' 06-Apr-2021 ' 27-Feb-2024

24-Dec-2019

24-Dec-2019'

01-Jln-2021 ' 2S-J3/l-202Q 3O-NO'V-2022

~e:;::== ~""",~",,,. 15.-Dec-20.24

27-Feb-2024'

15.-Dec-2024

-=-~

I

I I I

and

0P2100 ard Tools On Site

Un~ 1 Out3ge Prep 25.-Joo-2016

OP1040 U 1 Long Lead Materi:>ls kloolilied 2!>-.hn-2!l16' OP1G55 Ul Project DEtailed Engi-oe"';ng Fnshed (Desgn ModkaOOn DooJnoots Firished) I 25-Mar-2017'

OP1070 VI ....... k Packages Assessng Gorrplele 25.-Apr-2017'

OP1060 Ul ReI\.rilRm<i...".. :::--1'i'~"",~~"'~H~' OP1100 Ul Uri! InIia'Sia ge ~s& TooIs,..oo",,"~'-.__ I 25.-Feb-2018' Un~ 3 Out3ge Prep Ke-y Dales 2S-f eb-20 18 28-0Cl-2019

OP3050 U3 Long Lead Materi:>ls kloolilied ,23-Feb-2010' OP3055 U3 Project DEtailed Engi-oe"';ng Fnshed (Desgn ModkaOOn DooJnoots Firished) I 23-NtJ,.-2018'

0P3070 U3 ....... k Packages Assessng Gorrplele 28-0ec-201B'

OP3060 U3 Rel\.ril Rm<i...".. ----+1 28-J:n-2019' 0P3100 U3 IrOIiai Sla!;e Ml1enals & Trot<; on Site 28-0<:1-2019' Un~ 4 Out3ge Prep Ke-y Dales 0&-Aug-20 19 O&-Apr-2021

OP4040 U4 Long Lead Materi:>ls kloolilied ----li"'""'""~ "',. OP4055 U4 Project DEtailed Engi-oe"';ng Fnshed (Desgn ModkaOOn DooJnoots Firished) 1OG-M.y-202U'

OP4070 U4 ....... k Packages Assessng_Gorrplele 06-Joo-2020' OP4100 U4 lnilial Stao.;e Ml!OO35 & Tools on Site OS-Apr-2021'

Outage Execution Key Dates I!>-Od-2016 27-Feb-2024 Un~ 2 Refurb 1!>-Ocl-2016 24-Oec-2019

U4 FtII PIH/", & Handove< !oDNGS

Program Closeout Key Dates CL1M DR Ptogam Frul Accepta....,

I!>-Oct-2016'

15-Dec-2024

24-Oec-2019'

3O-Nov-2022'

27-Feb-2024'

1!HJec-2024

1!>-Dec-2024"

Filed: 2013-09-27 EB-2013-0321 Ex. D2-2-1 Attachment 4-4