Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure planning

Embed Size (px)

Citation preview

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    1/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 1

    Fighting the Pipe: neo-liberal governance and barriers to effective community

    participation in energy infrastructure planning

    Christopher Groves, Max Munday, and Natalia Yakovleva

    Abstract

    Development of effective participatory mechanisms within infrastructure planning

    governance has been dependent on how far the outputs of participatory processes have an

    impact upon strategic policy priorities. However, neoliberal modes of governance are

    characterised by recentralisation within arms-length regulatory bodies and private

    corporations. Tensions between participatory governance and re-centralisation are

    exemplified by the relationship between energy privatisation and energy infrastructure

    planning. This study examines these tensions using a case study of a critical infrastructure

    project in the UK, the South Wales Gas Pipeline. Findings confirm arguments in the literature

    that siting conflicts often centre on policy issues as much as local concerns. The study reveals

    that the neoliberal recentralisation of some governance functions exacerbates such conflicts.It argues although new efforts to secure effective participation in neoliberal regimes are

    necessary, they will face obstacles in the form of risk-based governance structures, as

    exemplified by the privatised energy sector.

    Keywords

    Infrastructure planning, participatory governance, pipelines, planning cascade, privatisation.

    Introduction

    The heart of conflicts over the siting of nationally-important infrastructure is often seen as a

    clash between not-in-my-backyard (NIMBY) local interests and national policy. It has alsobeen argued, however, that siting conflicts over such infrastructure often act as condensation

    points for wider concerns, which can cross scale from the interests of a specific community

    to connect with national and even international issuessuch as mitigating climate change,

    protecting indigenous peoples rights and so on (see Owens 2004). As a result, participatory

    planning may be seen as more than just a means of improvingprocedural fairness, as

    emphasised by some commentators (e.g. Gross 2007). By linking siting proposals to broader

    political priorities, genuinely effective participation has a substantive dimension, exemplified

    by the case of the Mackenzie Valley gas pipeline in Canada (Gamble 1978). Nonetheless,

    Owens (2004) and Cowell and Owens (2006) have pointed, in the UK context, to how a

    countervailing streamlining tendency in land-use planning can close down opportunities for

    participatory decision-making, reducing siting decisions to a trade-off between national needand local interests. In this paper, we explore how such trade-offs, and conflicts driven by

    them, are the product of forms of governance which characterise neo-liberal societies, with

    the aid of a major energy infrastructure case study from the UK (the South Wales Gas

    Pipeline, or SWGP). Our argument is that, while participatory decision-making has made

    inroads into governance within contemporary societies, the decentralisation of power

    associated with neoliberalism (and in our case study, with energy privatisation in particular)

    brings with it a distributed re-centralisation of decision-making. Such re-centralisation may

    intensify streamlining tendencies within planning governance, and can prevent

    participatory mechanisms from taking forms which achieve either procedural fairness or true

    effectiveness, i.e. substantive impact. We show that, in line with significant recent literature,

    that substantive issues often form the focus of planning conflicts. We also suggest that, basedon our case study, how the power to shape the policy priorities that drive infrastructure

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    2/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 2

    development is distributed may be among these issues. The paper is structured as follows.

    First, it examines the literature in order to argue that the effectiveness of participatory

    mechanisms is dependent on whether they allow second-order reflection on the policies and

    purposes which drive infrastructure development. Second, it shows how this mode ofsubstantive participation stands in tension with risk-based modes of neo-liberal governance

    exemplified by the privatised national energy network in the UK. Third, the paper explores

    the history of the SWGP project and investigates how community groups engaged with the

    planning process, before discussing how this case can help us understand the tensions

    between the drive for more participation, and the re-centralisation of governance. We show

    how, although the Pipeline was built under a planning regime that has been superseded in the

    UK following the 2008 Planning Act, the issues it raises are perhaps even more significant

    under the new regime.

    Background

    Participatory governance

    Since the 1970s, land-use planning has seen a variety of experiments with participatory

    processes as an alternative to the classic technocratic model of decide-announce-defend,

    often associated with a high modernist model of government (Scott 1998). Simultaneously,

    the emergence of neo-liberal forms of economic governance during the same period gradually

    transformed the relationship between the state and society. Increasingly, the state became a

    facilitator of development rather than its agent. The privatisation of public utilities in many

    societies since the 1980s has consolidated this new role. However, as has been observed in

    the case of the UK, this new form of state may have its own utopian projects quite as

    ambitious as those of high modernism (Moran 2007 p. 6). The need for society to be legible

    to an administrative centre did not decrease. Indeed, it increasedproportionate to the

    degree to which administrative responsibilities are re-distributed and more and moreactivities become subject to audit and measurement. Further, the auditing gaze does not

    simply survey the present. It also takes on a new temporal aspect by seeking to render thefuture more legible, through risk thinking (Rose 1999).

    A new focus on participation, along with risk thinking, represent two tendencies within a

    broad stream of governance reform that flowed through the 1960s to the 1990s (Walls et al.

    2005, pp. 641-643). On the one hand, greater participation is seen as a means both of

    enhancing the ability to anticipate perhaps overlooked negative outcomes of action, and of

    also improving the legitimacy of governance by balancing the privatisation of governance

    with greater involvement of stakeholders in decisions. On the other, the internalisation of

    risk thinking as a discourse of quantification and auditing within organisations became a wayof creating another model of legitimacy for governance. The tense relationship between these

    two tendencies is important for understanding how infrastructure planning has evolved under

    neoliberalism.

    In what follows, we set out, in more detail, key features of the two tendencies in relation to

    planning. With respect to participatory governance, it has been argued that it may improve

    decision making with regard to the potential social and environmental impacts of

    infrastructure development (Ward 2001). Participatory processes may marshal a more

    comprehensive and inclusive evidence base that draws on a variety of perspectives including

    local knowledge. In this sense, they can be instrumentally useful. They may, however, be

    preferred on account ofjustice. By allowing more perspectives on a proposal to be included,they can enhance distributive andproceduraljustice (Gross 2007). They may also enable

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    3/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 3

    greater recognition of historical injustices, including e.g. local accumulations of polluting

    infrastructure that stigmatize particular places and communities (Walker 2009). To be

    effective in serving these three purposes, participation should ideally be early, when

    alternatives are still open; be inclusive and feature two-way communication; allow access to

    key information; offer genuine opportunities to influence or even veto decisions; take into

    account the diverse values of participants; and be transparent (Bond et al. 2004). However,

    participation may be effective in another sense by allowing public reflection on substantive

    issuesincluding what kind of society participants wish to inhabit, questions of national

    interest, and other matters. In this way, participation around planning concerns at local and

    regional scales can provide an arena for focused reflection on the assumed purposes of

    national strategies (Cowell and Owens 2006, 2011).

    Consequently, participation can embody reflexivity in an expanded sense, even if it takes

    place downstream of strategic decisions. If a piece of infrastructure is a kind of solution to

    a problem, then participatory governance may, by including more perspectives, enable the

    problem itself to be examined, along with the ways in which it has been framed as a problem.

    In this way, whether participation is effective or not depends on how far it enacts second-order reflexivity towards both means and presupposed ends. Substantively effective

    participation may be imagined as creating a feedback loop (Rough 2011), which begins with

    an examination of localised impacts, benefits and risks associated with a given proposal.

    Widening participation in examining these illuminates, in turn, considerations which may

    lead to a critique and re-framing of the policy problem to which the planning proposal

    appears as a viable solution. In this way, local planning conflicts can lead to modifications in

    assumed definitions of the national interest, even if they do not end in consensus (Owens

    2004).

    Risk thinking, power and energy infrastructure planning under neoliberalismWe now turn to the second of the aforementioned tendencies, i.e. the internalisation of risk

    thinking within governance as a legitimatory discourse, and how this shapes the distribution

    of power in planning. The relationship between this tendency and the evolution of

    participation as a form of second-order reflexivity is often conflictual. The tension here

    derives from the opposed logics of power which characterise the two tendencies. Where

    effective participation demands dispersed power (Ward 2001), embodied in institutionalized

    processes that drive critical scrutiny of policy problems as well as solutions, neo-liberal

    enrolment of private companies and other governance actors decentralises while

    simultaneously recentralising. The creation of new centres of calculation (e.g. privatised

    energy utilities, industry regulators) is accompanied by the need to render the field in which

    they operate legible to government, both in the present and with a view to its projectedfuturesrequirements in which risk thinking plays a significant role. In the next section, we

    will explore the internalisation of risk thinking within the UKs planning regime in relation to

    energy privatisation, and how risk knowledge and power are linked.

    As noted at the beginning of the previous section, the neo-liberal state can be viewed as

    evolving, in some respects, out of the high-modernist state. The high-modernist state evolved

    a set of tools for transforming an uncertain future into a meaningful parameter of planning,

    one that could be both told and tamed (Adam and Groves 2007). State bureaucracies

    developed quantitative criteria for measuring the success or failure of policies, depoliticizing

    decision making in the process and recreating the domain of politics in a way amenable to

    bureaucratic management (Rose 1999, pp. 198-199). Representing the future in terms of risk,

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    4/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 4

    and developing methods for estimating and comparing risks, extends the legibility of society

    into the future.

    Neoliberalism re-affirms this legitimatory role for risk. In relation to the UK, Moran (2007)

    observes that the contemporary British neo-liberal state has adopted a role of regulating and

    balancing markets as providers of public goods. The amount of statistical information the

    new regulatory state requires means that new and closer relationships have to be built

    between government bureaucracies and expert advisors. The persistence of a centralised and

    linear predict and provide approach to the future in contemporary British infrastructure

    planning has been noted (Cowell and Owens 2006; Marshall 2010, p. 30), a durable high-

    modernist element of a British political system where the stress, historically, has

    consistently been upon strong, centralized, efficient government, rather than responsive

    government, and in which the government has traditionally been seen as the sole judge of

    the national interest (Marsh and Hall 2007). What changes with energy privatization is that

    the centre where information is collated and future risk scenarios produced is no longer

    singular and located in Whitehall, but multiple and dispersedlocated in the corporate

    headquarters of privatised utilities and of regulatory agencies (Scott et al. 1998).

    An important UK example of these changes is energy privatisation. Before privatisation in

    the 1980s, the production and distribution of energy in the UK was a public duty of state-

    controlled bodies. With privatisation, this universal obligation is lost (Guy et al. 1997).

    Instead of one organisation, a multitude of providers is created, who have public service

    obligations but also private commercial obligations. Away from energy production, the

    electricity and gas distribution network was signed over to a private monopoly (National Grid

    plc, formerly Transco, the sole transmission network operator or TNO in England and

    Wales). Part of the public duties falling on National Grid (NG) as a TNO is to forecast future

    demand and infrastructure needs and inform policy frameworks. In fulfilling the duties, NG

    produces annual ten-year statements (e.g. National Grid 2005), which inform white papers,statements of need and other elements ofgovernment policy through fora which have

    included (between 2001 and 2006) the Joint Energy Security of Supply Working Group

    (JESS), whose remit was to assess risks to the UK's future gas and electricity supplies

    (Department for Business Innovation and Skills (BIS) 2009) and to identify relevant policy

    issues and consider implications (Winstone et al. 2007, p. 5). Under the new planning

    regime introduced by the Planning Act 2008, this information continues to be the main source

    of demand forecasts which inform the National Policy Statements (NPS) relevant to gas and

    electricity infrastructure (DECC 2009, p. 11). As a result, policy answers to the essentially

    political question of what is in the national interest with respect to energy are significantly

    influenced by essentially administrative bodies such as JESS.

    NG thus plays the role of a key centre of calculation, providing future demand forecasts

    which help tame uncertainty, while also being a developer that constructs infrastructure in

    response to these forecasts. Following privatization, the commercial arrangements for

    downstream supply of gas became much more complex. Increased uncertainty and risk for

    investment in infrastructure created a greater need for stability, so that long-term supply

    contracts guaranteeing stability of supply could be signed (Manners 1997, p. 302). In

    contrast, the Government itself is no longer a developer, nor is it a strategic planner, having

    adopted a governance role ofnon-decision making (Cowell 2004, pp. 312-313). Another

    such centre is the energy industrys regulatory body, the Office of Gas and Electricity

    Markets (Ofgem), which was responsible, along with the then Department of Trade and

    Industry (DTI), for chairing JESS. Ofgem was created in 1999 with the primary remit of

    making privatised energy production utilities accountable to consumers (Moran 2007) and of

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    5/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 5

    facilitating a predictable environment for investment through forward price signals

    (Department of Trade and Industry 2003, p. 14). The need for a regulatory regime stronger

    than that which operates across the rest of the private sector is necessitated by the statutory

    duties which fall on utilities (established in the UK under, inter alia, the Gas Act 1986 and

    Electricity Act 1989) to provide essential goods. Ofgem is often seen as an agency whose

    primary goal is to encourage competition and hold energy producers accountable for their

    pricing strategies. Nonetheless, it also has responsibilities for regulating the wider

    environmental and social impacts of electricity and gas provision, including the infrastructure

    which NG constructs. It has, however, proven difficult to translate these responsibilities into

    concrete practice (Guy et al. 1997, p. 214; Cowell 2004, pp. 319-320).

    At the strategic level, then, the relationship between NG and Ofgem as centres of calculation

    is not strictly one of regulated and regulator, as Ofgem has historically concentrated on its

    duties as a representative of energy consumers. NGs input into policy means that it occupies

    a special role in the UK system, consolidated by the predict and provide strategic approach

    to energy infrastructure, in which demand is something to be met, rather than managed. Since

    the 1970s, the need for longer-term energy demand forecasting in neo-liberal societies hasincreasinglybeen framed in terms of maintaining energy security (Marshall 2010), an issue

    defined by the International Energy Agency in terms of interlinked systemic risks (Winstone

    et al. 2007, p. 1). Such discourses locate policy debates within narratives of necessity, in

    which the national interest is assumed to lie in providing for projected energy demand, which

    will in turn generate more economic growth (Cowell and Owens 2011, p. 15). This generates

    the fundamental set of policy problems, in relation to which technical advice (from

    companies like NG), white papers and infrastructure proposals (from companies like NG)

    represent steps towards solutions. The position of energy utilities, TNOs and regulatory

    agencies within high-level planning processes is thus defined within these narratives of

    necessity. Their power to affect spatial planning is proportional to their role as centres of

    calculation of need and risk, joined to their role as developers. While Ofgem is active intrying to regulate energy markets, it is not so in regulating infrastructure planning in any

    high-level strategic sense. This is left to downstream processes of impact assessment and

    review within the planning system. The lack of strategic regulation of environmental and

    social impacts reinforces what Owens (2004) has described as a planning cascade, in which

    policy problems, cloaked in necessity, drive policies which define national need, before being

    translated into concrete infrastructure proposals. Only at this latter stage can participatory

    mechanisms be activated, solely to determine where the infrastructural solution to the

    policy problem should go, rather than enacting effective, substantive reflection on strategic

    problems. In this way, planning conflicts emerge as, primarily, conflicts between local

    interests and the national interest, this latter having become largely insulated from

    reflection and critique in the process.

    Recent changes to the UK planning system

    Making the situation still more difficult for effective participatory governance are changes in

    the mechanics of planning governance.1

    Until 2008, the Town and Country Planning Act

    (TCPA) was the chief legal instrument for oversight of land use planning in England and

    Wales. For larger installations of national importance, consents were traditionally granted by

    the relevant department of the UK Government, a system of deemed consent which

    overrode the need, under the TCPA, for developers to seek permission from a local planning

    1Note that this discussion applies primarily to the situation in England and Wales within the UK. Planning

    governance in Scotland and Northern Ireland differs in relation to many or all of the following considerations.

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    6/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 6

    authority (LPA). This made it less imperative for LPAs to map out forward-looking policy on

    the acceptability of different kinds of energy infrastructure in particular locations (Kellet

    1993, p. 96). Consequently, the relationship between local authorities and privatised utilities

    with regard to planning was generally, though not always (Guy et al. 1999), a highly reactive

    one (Scott et al. 1998, p. 539). With respect to regional and local spatial planning local or

    regional spatial development plans (LDPs, RDPs) were the medium through which LPAs

    translated into policy the short- and longer-term interests of communities for whom they were

    responsible. How the centralized decision-making processes of utility companies related to

    these spatial strategies within the planning system was therefore complex and often

    problematic (Guy et al. 1996). LPAs which attempted to use its LDP or RDP to ensure that a

    particular area that had been historically burdened with hazardous and/or polluting

    infrastructure developed along a different economic path have generally found that this was

    not enough to stop planning permission being granted for more infrastructure of this kind

    (Scott et al. 1998). Provided consent was given by the Secretary of State, then the only

    further obstacle was having a proposal called in by a government minister, something

    which opponents could request. Nonetheless, this system saw a series of significant,

    successful challenges brought against major infrastructure projects in the 1980s and 1990s.As such, the planning system contained counterweights to technocratic, predict-and-

    provide-style planning.

    These challenges created a perception within government and industry that the planning

    system was subject to blockages and in need of being modernised. At the same time, the

    increased demand for participatory governance in planning was acknowledged. The result

    was an uncomfortable synthesis of proposals for streamlining planning and for public

    engagement in spatial planning, manifested within the Governments Planning: Delivering a

    Fundamental Change Green Paper in 2001 (Cowell and Owens 2006, p. 407). The

    subsequent Barker Review of Land Use Planning (2006) added to the momentum behind

    modernisation, ahead of the 2008 Planning Act, which included two main innovations.First, new strategic policy instruments (National Policy Statements or NPS) relevant to large

    infrastructure of national importance, and second, a new centre of calculation, the

    Infrastructure Planning Commission (IPC), whose role was to assess planning proposals

    designed to fulfil needs identified in an NPS. The IPC could, in theory, find against a

    proposal which might impose excessive costs on local communities, but would have to

    disregard representations that relate to the merits of policy set out in a national policy

    statement during [...] decision making (Woolley 2010, p. 236). Without a clearly negative

    net local effect, the IPC would be likely to decide quickly in favour of the national interest, as

    defined by an NPS, over local interests in any given case. This led some commentators to

    interpret the new regime as reinforcing planning cascades by closing off opportunity

    structures within which objectors could link particular proposals to reflections on strategicconcerns, in the way that substantively effective participation demands (Rough 2011, pp. 40-

    41). Although some consultative input was allowed into the formation of NPS, the level of

    abstraction involved here meant that these consultations were unlikely to benefit from the

    energetic mobilisation of different perspectives with which local campaigns often connect

    localised impacts to national policy (Woolley 2010, p. 237).

    Not long after the Conservative-Liberal Democrat Coalition took power in 2010, the IPC was

    dissolved, with its role and powers being assigned to a section of the Planning Inspectorate.Revisiting their 2006 paper on the modernisation of planning, Cowell and Owens (2010)

    noted that, under the Coalition, infrastructure planning would likely not be materially

    different to the streamlined cascade structure established by the 2008 Act. The significance

    of the localism governance agenda introduced by the Coalition, most notably with the

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    7/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 7

    Localism Act 2011, for these issues remains to be seen, although some have suggested that

    negative impacts from the Act are likely to be felt on local democracy generally, and

    planning in particular (Cowell 2012; Le-Las and Shirley 2012).

    The potential for planning cascades shaped by high-level, technocratic processes of need and

    risk management is thus characteristic of the UK planning system, before and after the 2008

    Act, and is particularly evident in relation to energy infrastructure. The delegation of

    legitimate authority to manage future energy risk by government to privatised utilities renders

    decision-making non-transparent, creating facts on the ground to which LPAs and

    communities affected by infrastructure plans have to respond when the cascade reaches them.

    This reinstates a technocratic, modernist decide-announce-defend model of planning

    strategy within neo-liberal governance (Hardy and Ritchie 2010, p. 15). The opportunity for

    wider participation in the planning process comes far downstream from the point where a

    piece of infrastructure has been judged nationally necessary, and a set of alternative sites

    determined (Cotton and Devine-Wright 2011, p. 954). Consultation with regard to NPS

    notwithstanding, the regime established by the 2008 Act does not establish opportunity

    structures that might counteract the cascade, by allowing effective and substantiveparticipatory reflection on policy and the national interest. Under the neo-liberal

    governance regime that prevails in energy privatisation, the responsibilities and power

    delegated to TNOs like NG appears to put them in a unique position, where their strategic

    role is counterbalanced neither by significant strategic regulatory oversight of the social and

    environmental impacts of their activities, nor by upstream participatory negotiation of the

    priorities they help define. Some have argued that the need for such counterweights is

    underlined by the concern that with privatisation comes potential conflict between the public

    duties of utility companies and their private obligations to shareholders and others, which can

    result in negative consequences for service users and those affected by planning decisions

    (Defeuilley 1999; Hall and Lobina 2004).

    Case Study: The South Wales Gas Pipeline (SWGP)

    The South Wales Gas Pipeline project, in which NG was a major actor, was framed by NG

    and government against the background of an impending energy crisis linked to the

    dependence of the UK on imported gas (e.g. Department of Trade and Industry 2003).

    Official definitions of national need reflected assumptions that the country would

    experience continually-growing demand for gas and other resources (Marshall 2011). In the

    first years of the 21st

    century, two consortia of petrochemical companies submitted plans to

    build LNG terminals at sites around Milford Haven in West Wales in response to policy

    signals regarding future demand for gas. NG signed contracts with these consortia that

    imposed upon it an obligation to provide infrastructure to connect these terminals to the UKNational Transmission System (NTS) at a site across the English border in Gloucestershire.

    The pipeline to connect the Milford Haven terminals to the NTS would be of unusually large

    diameter (1220 mm, 48 inches) and run at a pressure higher than usual for the UK NTS (94

    rather than 75 barg). The pipeline construction work comprised two phases (see Figure 1).

    Phase 1 ran from Milford Haven to Aberdulais, with a length of 120 km (75 miles), and

    Phase 2 ran from Felindre to Tirley, being 196 km (122 miles) long. The pipeline fell outside

    the scope of powers granted to the Welsh Assembly in the 1998 Government of Wales Act.

    Our research into how communities experienced the planning process for the pipeline took

    the form of a series of 17 semi-structured interviews during 2007-09. Studying the impact of

    network infrastructure like pipelines presents particular methodological difficulties. In order

    to provide as comprehensive a picture as possible of concerns along the route, interviews

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    8/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 8

    were conducted with representatives of various campaign organisations from flash -point

    sites along the full length of the pipeline, including Safe Haven (Milford Haven and

    Waterston, the sites of the two terminals), CRA (Cilfrew Residents Association, concerned

    with a pressure reduction station), CRAG (Cwmtawe Residents Action Group, at Trebanos,

    concerned with Phase 1 of the pipeline), a looser group centring on Brecon and Hay-on-Wye

    (concerned with Phase 2) and CAPRI (Campaign Against the Pressure Reduction Installation,

    at Tirley). Participants were selected using a snowballing method (Bryman and Bell 2007).

    Interview material was transcribed, coded and qualitatively analysed with NVivo 8 software

    to identify and compare community concerns and how campaigns (and their primary

    concerns) developed over time. Secondary materials were also used to help construct a

    timeline of events. These included press reports, publications and press releases from NG, its

    contractors, and the Milford Haven Port Authority, and planning documents. Case

    development also drew on research undertaken on the impacts of LNG in West Wales by one

    of the authors for Pembrokeshire Business Initiative during 2007 (Bryan and Munday 2007;

    Bryan et al. 2007).

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    9/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 9

    Figure 1: The South Wales Gas Pipeline, Phases 1 & 2

    Initial stages and early conflicts

    Interviewees in Milford Haven, a town with a long history of petrochemical infrastructure

    development, reported first being informed of the LNG terminal projects via exhibitions held

    in the town during 2004, at least a year after the planning proposals had been submitted toPembrokeshire Council. They reported that local people had not being given any opportunity

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    10/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 10

    to comment on the applications during the period prior to this, when the proposals were being

    considered by the LPA (Interviewee, Waterston, 31 July 2008). Concern began to crystallize

    around how the risks of allowing LNG tankers into the narrow and busy Cleddau estuary had

    been assessed, particularly following the Sea Empress disaster in 1996. Unsuccessful requests

    to the terminal consortia and to Milford Haven Port Authority (MHPA) for risk assessments

    in November 2004 resulted in a court case being brought by the members of what would

    become the Safe Havens campaign group to compel MHPA to release the relevant

    information. This case was unsuccessful, largely because the request had come too late in the

    planning process for the release of the information relevant to make a difference: theyve

    spent millions of pounds, therefore youve lost your window of opportunity (Interviewee,

    Milford Haven, 23 July 2008). Safe Havens felt that the proposal had, thanks to concerns

    about energy security, too much momentum and that Milfords existing concentration of

    heavy industry had made it the ideal destination for the terminals, despite international best

    practice recommendations on LNG facility siting recommending that they be sited offshore

    (Interviewees, Milford Haven, 23 July 2008, and Waterston, 31 July 2008). When risk

    assessment information was made available, after a ruling against MHPA from the

    Information Commissioner, the content was felt to be generic rather than specific to theconditions in the Cleddau. Attempts to persuade the Welsh Assembly to intervene were

    unsuccessful, an experience shared by Welsh campaigners against the pipeline later on.

    Although the Assembly has no powers regarding strategic assessment of proposals of this

    kind, it was a statutory consultee in both cases, and some interviewees expressed surprise that

    it had not objected on the grounds of the Welsh Assembly Governments obligation to

    promote sustainable development (Interviewee, Cilfrew, 22 July 2008).

    For its part, NG submitted planning proposals for the two phases of the pipeline in 2004 in

    line with the requirements of the Public Gas Transporter Regulations 1999 (subject to

    deemed consent rather than to the TCPA). In its proposals, it justified the pipeline by

    invoking an energy security national interest argument, buttressed by demand forecasts. Inaddition, it stated the pipeline was also necessary for it to fulfil its public service obligations

    under the Gas Act 1986 to maintain efficient and economical gas supply infrastructure.

    This second argument concerning public duties resurfaced at subsequent planning inquiriesalongside invocations of national interest. The relationship between these duties and NGs

    private interest in fulfilling the contracts it had signed with LNG importers to finish the

    pipeline by early 2007, would prove of particular interest to campaigners. To what extent,

    campaigners would ask, were the criteria of efficient and economical an adequate way of

    understandingNGs public duty, given that the fulfilment of private contracts for completion

    by a certain date would determine how efficient and economical the infrastructure would

    be. Campaigners were suspicious that consultation was kept to a minimum as a way of

    avoiding siting conflicts and thus reducing commercial risk. The possibility of conflicts ofinterest ran alongside a lack of incentives for NG to promote participatory engagement.

    Research suggests that energy infrastructure companies tend to view consultation as primarily

    one-way and informational (Barnett et al. 2012). Network infrastructure, such as pipelines or

    overhead power lines, which connect together multiple sites, presents particular practical

    obstacles for public engagement. In such cases, researchers have also documented

    assumptions held by developers about the publics inability to take the strategic view

    necessary for looking at the network as a whole (Cotton and Devine-Wright 2010a).

    The process of impact assessment and route choice for the two phases of construction

    provided the first opportunity for opposition to the pipeline to crystallize. During 2004-05,

    NG provided assessments of the viability and impact of a number of potential offshore and

    onshore pipeline routes. Following the granting of consent for Phase 1 in December 2005, the

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    11/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 11

    selected route options for Phase 2 produced significant controversy. At this stage, the DTI

    sought responses from statutory consultees, including relevant regulatory bodies, LPAs and

    businesses. The Brecon Beacons National Park Authority, from the outset, took a strongly

    critical stance towards any route through the Beacons. In responding to NGs proposals, the

    BBNPA noted that (a) the route choices, (b) the judgement that a pipeline connecting Milford

    Haven to the NTS was necessary for NG to fulfil its public obligations and in the wider

    national interest, and (c) that a pipeline of just this specification was in the national interest

    and required by NGs public obligations were all questionable. It suggested that it was for the

    DTI to provide its own independent judgement on these issues, preferably by means of a

    strategic environmental assessment of the whole project andpost-privatisation governance

    (BBNPA 2005a, b).

    The objections put forward by the BBNPA exploited its position as a statutory consultee by

    seeking to establish a link between the potential harmful impacts of NGs specific proposals

    and what it saw as illegitimate policy priorities. In doing so, it presented a strategic critique of

    the pipeline project as a whole, rooted in its assessment of impacts on its locality.NGs

    statement of need was interpreted by BBNPA as being in conflictwith its public dutiesunder the Governments planning guidance on sustainable development (ODPM 2004). This

    was because a conflict of interest was perceived within the very choice of a predict and

    provide methodology for assessing national need, given that NG also had a commercial

    interest in stimulating gas demand (BBNPA 2005b, p. 6). Indeed, a subsidiary part of the case

    for new infrastructure was that it would aid development and [] give opportunities for

    industry and users of gas to create business opportunities (BBC News 2006). Further, the

    argument from need did not acknowledge concerns first voiced in the late 1990s that

    increasing demand for gas might create infrastructural path dependencies that could decrease

    energy security (Sadler 2001, p. 14) and that demand should be managed rather than met.

    BBNPAs argument was thus that the national need case for a pipeline was questionable, but

    also that no national interest case could be made for any particular route. Further, it arguedthat there was a clear alternative definition of the national interest: protecting National Parks

    held in trust for future generations, and driving energy infrastructure development faster

    towards better use of renewables (BBNPA 2005b). The strategic arguments first put forward

    by the BBNPA were subsequently employed by the various campaigning groups who became

    active along the length of the pipeline, as they began to coordinate and share information,

    thus allowing each group to create a strategic position on the need for the pipeline as a whole

    which shared key feature with those developed by other community groups.

    By the middle of 2006, Safe Havens had been joined by four other campaign groups. Cilfrew

    Residents Association (CRA) and Campaign Against the Pressure Reduction Installation

    (CAPRI) in Tirley were concerned with proposals for gas re-pressurization installations(PRIs) which, unlike the pipeline itself, fell under the TCPA and were subject to normal

    planning consultation processes. The PRI in Cilfrew was part of Phase 1 of the pipeline,

    while that at Tirley would connect Phase 2 to the main UK NTS. Cwmtawe Residents' Action

    Group in Trebanos (CRAG) and a looser group of campaigners around Brecon and Hay-on-

    Wye were concerned about issues relating directly to Phases 1 and 2 of the pipeline

    respectively. In each case, interviewees reported that the groups had organised themselves in

    response to what they felt was a failure on the part of NG to consult adequately, and in

    particularly, a failure to involve communities in impact assessment processes.

    In early 2006, CRA established that the PRI environmental impact assessment NG had

    submitted was for the wrong site (Interviewee, Cilfrew, 22 July 2008), which required a

    resubmission. When the LPAs planning committee approved the proposal in September

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    12/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 12

    2006, four councillors who had met CRA were excluded (Harris 2007). On the basis that this

    had violated procedure, CRA applied for a judicial review of the grant of approval, which

    they won in March 2007. The proposal was voted on again in May of that year and approved,

    despite continuing and largely unanswered representations from CRA regarding its social and

    environmental impact (Interviewee, Cilfrew, 15 October 2008).

    In Trebanos, CRAG discovered in June 2006 that NGs contractors intended to use blasting

    as part of the Phase 1 construction, following an exhibition on 5 and 6 June. CRAG objected

    to the blasting taking place, on the grounds that the pipeline route took it close to peoples

    houses, as well as through an area historically affected by subsidence and by unmapped mine

    workings where laying of mains gas pipes was not permitted (Interviewee, Trebanos, 25

    October 2008). In addition, they discovered that planning permission from the LPA was

    needed, and had not been granted (Harris 2007). Following a failure to get the Welsh

    Assembly to intervene, the group succeeded in getting the LPAs planning committee to vote

    at the end of August on the blasting, which since 8 June had been taking place without

    planning permission. However, like the Cilfrew planning committee vote, this was also

    subject to procedural irregularities (Interviewee, Trebanos, 30 July 2008; Harris 2007).Thereafter, they contacted an environmental group called Rising Tide and independent

    activists from Newport and Cardiff, who in November 2006 organised direct action protests.

    Subsequently, on 22 November, the DTI contacted NG and CRAG to announce that

    permission to blast had been denied.

    Pipeline Phase 2 and the Gloucestershire PRI

    Phase 2 of the pipeline was given consent on 7 February 2007. The decision to grant consent

    drew on the application of the Silkin Test, a planning criterion set out in 1949 by Lewis

    Silkin MP, designed to balance the national need for certain developments against the

    localized impacts of such developments in national parks. This set out that development mustbe in the national interest and minimize damage to the park, and that no practical alternative

    to must exist. In applying the Silkin Test, the Secretary of State identified the national interest

    with the public duties of NG. The judgement stated that it was

    desirable that the proposed pipe-line works should be carried out in the interests of the

    development and maintenance of an efficient and economical system for the conveyance of

    gas [...] (DTI 2007, pp. 5-6)

    The BBNPA had suggested, as noted above, that the statement of need put forward by NG

    conflated its public duty, the predetermined national interest in meeting gas demand, and the

    private obligations NG bore to gas importers with whom it had signed contracts to completethe pipeline by a particular deadline. The decision to grant consent did not address this point.

    The BBNPA had also objected that the assessment regime for the project had been deficient,

    insofar as no high level strategic assessment had been undertaken by the DTI on the impact of

    gas infrastructure development across South Wales, and indeed, of the broader impact of the

    marketised modes of energy need and risk assessment that had emerged under privatisation.

    The DTI ruled against this objection, noting that the governments role in relation to gas

    infrastructure was not one of centralised strategic direction or installation development, and

    that the DTI managed only a reactive, project-oriented handling system (DTI 2007, p.3) for

    consents.

    Following Phase 2 consent, campaigners increasingly began crossing scales, by questioning

    in public the strategic social priorities behind the project as a whole at the same time as

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    13/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 13

    linking local impact concerns across different sites, and bringing together issues of safety and

    environmental risks from different localities which crystallised concerns about the haste

    with which the SWGP was being constructed, allegedly under commercial pressure. These

    efforts began largely with campaigners in Tirley and Brecon who, with assistance from civil

    and retired pipeline engineers living in their respective communities, began asking a series of

    technical questions about the safety of the pipeline.

    As had been the case at Milford Haven, campaigners expressed concern about the generic

    content of risk assessments. A brief document, relating to the pipeline itself (as opposed to

    the PRI) was submitted by NG as part of its planning application at Tirley (McCollum 2006).

    This document was criticized for failing to include actual calculations and to set out its

    assumptions, which campaigners felt suggested it hadbeen prepared at head office rather

    than by someone with direct knowledge of local conditions which might affect the

    assumptions behind the analysis (Interviewee, Tirley, 24 July 2008; two interviewees,

    Brecon, 29 July 2008). Technical information on failure risk and what were felt to be

    unaddressed uncertainties were circulated between CAPRI, the Brecon group, CRAG, CRA

    and Safe Haven at a series of meetings involving two or more of the groups during 2006. Therationale behind the increased 94 barg operating pressure of the pipeline was subsequently

    widely questioned. It was suggested that the increase in pressure resulted in a significant and

    exponential reduction of the pipelines operational safety margin, but that it also increased

    gas flow rate substantially (an important commercial consideration).

    The strategic viewpoint adopted by campaign groups therefore focused on an alleged trade-

    off between commercial interests (as distinct from the national interest) and the impacts on

    affected communities. In Tirley, an additional localised focus for objections was the

    environmental impacts of the proposed PRI on a historically unspoilt location. As with the

    generic nature of risk assessments in Milford Haven and at Tirley, the difficulty of

    obtaining information on these impacts was felt to reflect what we have referred to above asthe re-centralisation of decision making after privatisation: as a result of planning and

    operational decisions being taken by NG at their headquarters in Warwick, and

    communications being run by the companys public relations staff in London, the company

    were not on the ground throughout the planning and construction process (Interviewee,

    Brecon, 19 November 2008). Subsequently, the PRIs environmental impact assessment was

    submitted late. When it was made available, part of its case for siting the PRI in this location

    was that the specific choice of site was represented as being in the national interest.

    CAPRI solicited over 1600 written objections to the proposal. A key point made by a

    significant number of objectors, as well as by CAPRI itself, was that, while it might be true

    that a PRI somewhere (to reduce gas pressure enough for it to flow into the NTS) would be inthe national interest, placing it in one precise location could not justifiably be said to be. AtTirley, what Owens (2004) describes as the it has to go somewhere dynamic of the

    planning cascadebecame it has to go here. A direct, and to campaigners inexplicable,

    connection was made between the national interest in energy security and positioning a PRI

    in a specific field in Gloucestershire. Alternative sites were available, in particular near an

    existing PRI 40km away. Consequently, environmental impacts and safety risks associated

    with this site should not simply be traded off against the national interest, and the need for a

    PRI at Tirley should be assessed primarily against social and environmental considerations.

    The LPA agreed, and refused planning permission on the grounds that the environmental

    impact of a PRI at Tirley had been underplayed in NGs EIA, and would be too significant,

    given commitments in the LPAs LDP to preserve the integrity of the area.

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    14/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 14

    NG appealed. A planning inquiry was held in April-May 2007, at which the national interest

    argument for the Tirley site was reiterated (RPS Planning 2007). This inquiry upheld the

    LPAs decision, and refused the appeal, a decision ratified by the Secretary of State in

    December 2007 (Plummer and Mellish 2007). This decision denied validity to NGs assertion

    that granting planning permission for one specific location was in the national interest, and

    advised other locations should be examined. A planning application for a new site, which fellwithin neighbouring Tewkesbury Councils jurisdiction, was submitted in December 2008.

    Following another campaign by CAPRI, the council refused permission in February 2010,

    leading to another appeal and a further planning inquiry in July of that year. This time, the

    Secretary of State followed the recommendations of the planning inspector by granting

    planning permission.

    During the Tirley campaign, after the terminals, pipeline phases 1 and 2, and the Cilfrew PRI

    had all been consented and (mostly) constructed, the national interest and public duty

    arguments advanced by NG for the pipeline and associated infrastructure were finally

    subjected to intensive public examination on the basis of strategic arguments first articulated

    by the BBNPA and developed, in relation to local risks, by a campaigners network thatextended the full length of the route. Nonetheless, the 2010 inquiry inspectors report stated

    that to serve national need, NG should carry out its licensed and contractual obligations

    to supply gas at the required higher volume and pressure through the pipeline, thus requiring

    the PRI (Tester 2010, pp. 87-88).

    Discussion

    The SWGP case, we suggest, has to be understood as a series of siting conflicts which

    emerged, in the first place, from repeated failures to facilitate early engagement, but which

    were driven by a systemic lack of opportunity structures for effective engagement.

    Consultation by the TNO over its strategic plans seems to have shared shortcomings with theefforts of the Milford Haven terminal developers: community campaigners reported these

    being partial, often late, and non-inclusive, with NG subsequently being found unresponsive

    and even obstructive by some. Following Freudenberg and Pastors (1992) recommendation

    that siting conflicts be considered as, essentially, systemic products, we would suggest that

    the possibility of effective engagement may be undermined by, first, the structures of

    governance that shape policy, and second, the planning system through which infrastructure

    proposals pass. We described the neoliberal de- and re-centralization of energy policy and

    infrastructure development as a key development through which the opportunity structures

    for effective engagement are restricted. By effectively black-boxing the mechanisms

    through which national energy needs and appropriate policy responses are assessed, these

    adjunct processes of privatisation make substantive, participatory reflection unlikely if notimpossible. In addition, re-centralisation may lead to materially worse impact assessment

    procedures, and communication difficulties, as described by interviewees at Milford Haven

    and Tirley.

    Again and again, the campaigns around the SWGP sought to open up these processes to

    scrutiny, to repoliticise processes which, having been framed as technical operations of risk

    analysis and management carried out by new centres of calculation, had become de-

    politicised, administrative processes. Safety and environmental risks were used to open up

    reflexive links between local impacts and the justifiability of national policies. More

    importantly, they were used to reframe the nature of the planning conflict. Campaigners

    suggested that the question of unacceptability would appear in a different light if the focus

    moved to the strategic conflict surrounding the pipeline. They essentially argued that this was

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    15/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 15

    not between a fixed national interest and local interests. Instead, it was between the role of

    essentially unaccountable, private commercial interests in shaping the national interest, and

    the proper contribution which diverse localised community interests (in place, amenity, safety

    etc.) could make to shaping assessments of national need.

    Arguments about commercial versus community interest first emerged in the BBNPAs

    criticisms of NGs choice of route for Phase 2, which, interviewees attested, subsequently

    became a key reference point for campaigning (Interviewee, Gorseinon, 30 July 2008). They

    managed to go far beyond a focus on amenity and safety to question the legitimacy of high-

    level governance mechanisms such as the capacity auctions on which future planning

    proposals and the private obligations entered into by privatised energy utilities are dependent

    (Brecon Beacons National Park Authority 2005b; Tester 2010). Instead ofaccepting the it

    has to go somewhere framing of the planning cascade and the attendant trade-off between

    national and local interests, campaigners questioned the assumptions about social priorities

    and legitimate expertise which allow such a trade-off to be constructed at all. They asked for

    opportunities to represent different conceptions of national interest, such as might be rooted

    in the kinds of often intangible and non-quantifiable values held to be the rightful concern ofstewardship organisations like the BBNPA (Interviewee, Hay-on-Wye, 28 July 2008).

    However, the successes achieved by campaigners were mainly at planning inquiries where

    the main issues were ones of environmental impact to be resolved under the TCPA. Although

    campaigners succeeded in ventilating strategic issues, the key points of contention which they

    were forced to address were, in the end, ones traditionally encountered at the far end of a

    planning cascade, i.e. whether a particular site was acceptable.

    Overall, the SWGP case is an example of how major infrastructure proposals were handled

    under the TCPA and deemed consent system. How might the 2008 Planning Act and

    subsequent developments have altered things? Is there any possibility that they might have

    instituted new opportunity structures within which local interests in impacts could crossscales and produce strategic reflections on the relationship between proposals and policy?

    As noted previously, there is much uncertainty in this regard. Nonetheless, there are reasons

    to remain sceptical. On the one hand, since 2008, NG has demonstrated different approaches

    to public engagement in early and wide consultation on strategic infrastructure route options

    in relation to overhead linesalthough these approaches may still be based on traditional

    developers assumptions about the public (Cotton and Devine-Wright 2012). On the other,

    the strategic need for large projects is still settled, after the 2008 Act, in a way which

    promises to reproduce planning cascades. NPS present certain forms of facility as desirable

    in a way which is enduring, a priori to, and largely insulated from concerns about the

    environmental consequences that may arise from individual projects (Cowell 2012), and

    retain the same role for some privatised centres of calculation (such as NG) in shaping policyas existed in the days of JESS (DECC 2009, p. 11). The 2008 Act was supposed to allow

    Parliament more say on the content of statements on national need. Nonetheless, critical

    comment from MPs on the six approved energy NPS (approved in July 2011) produced only

    a limited number of caveats. Interestingly, these echoed the worries about gas contributing to

    energy insecurity registered by Sadler (2001), as well as the BBNPAs criticisms of new

    infrastructure as increasing rather than simply meeting demanda perverse impact of a

    new dash for gas (ECCC 2011, p. 84). Furthermore, the creation of a new centre of

    calculation by the Coalition (a special unit within the Planning Inspectorate, to replace the

    IPC), is likely to exacerbate concerns about transparency rather than reduce them.

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    16/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 16

    Conclusion

    In this paper, we began with the tension between two tendencies within contemporary neo-

    liberal societies: increasing use of participatory governance, and developments that entrench

    risk thinkingin new centres of calculation. We examined how this tension plays out

    within a specific case study, originating within a privatised energy industry that has been

    used as a template for international energy governance by development organisations like theWorld Bank (Guy et al. 1999, p. 161). This case shows how siting conflicts within neoliberal

    systems of governance may centre on clashes of interests that are not reducible to national

    need and local concern. If the need for participation is a legitimate need, then it requires, we

    would suggest, procedurally fair implementation which focuses on substantive concerns,

    including such conflicts of interests. What the SWGP case demonstrates is that, in systems of

    governance where power is redistributed, to some degree, to private organisations with public

    duties, the accountability of these organisations in assessing need and managing risk must be

    included in the substantive issues participation considers. We therefore concur with recent

    scholarship (Cowell and Owens 2006; Cotton and Devine-Wright 2010a; Cotton and Devine-

    Wright 2010b; Cowell and Owens 2011; Cotton and Devine-Wright 2012) which suggests

    that questions of national interest are likely to continue to prove their importance in shapinginfrastructure siting conflicts. The interaction of the planning system with the assumptions

    and storylines (such as the centrality of risk management to governance, and the priority of

    energy security) through which governance is framed by the executive emerges as a key

    theme for further research. It is through these interactions that opportunity structures for

    effective, i.e. substantive participation will be shaped. The implementation of effective

    participatory governance faces serious obstacles, both in continued efforts to streamline

    planning systems (as per the 2008 Act), and in the potential for conflicts between the private

    obligations of private companies like NG and their public duties. Issues of commercial

    confidentiality, for example, particularly with respect to supply contracts, proved an obstacle

    to campaigners in the SWGP case seeking information about the case for national need.

    With such issues in mind, it is not enough to call for early and wider consultation. It isnecessary to recognise that the evolution of governance under neoliberalism requires forms of

    engagement which address both the redistribution of power to which this evolution has led,

    and the continuing possibility of conflicts between private commercial interests and

    community interests over how the national interest, and its relation to planning, is shaped.

    References

    Adam B and Groves C, 2007, Future Matters: Action, Knowledge, Ethics (Brill, Leiden)

    BBC News, 2006, New pipeline 'will aid industry', 17 July,

    http://news.bbc.co.uk/1/hi/wales/south_west/5181336.stm

    Barker K 2006,Barker Review of Land Use Planning. (HM Treasury, London).

    Barnett J, Burningham K, Walker G and CassN 2012, Imagined publics and engagement

    around renewable energy technologies in the UK. Public Understanding of Science

    21(1), pp. 36-50.

    Bond A, Palerm J and Haigh P 2004, Public participation in EIA of nuclear power plant

    decommissioning projects: a case study analysisEnvironmental Impact Assessment

    Review24(6), pp 617-641

    Brecon Beacons National Park Authority (BBNPA), 2005a Response to South Wales and

    the West Reinforcement Pipelines Route Corridor Investigation Study (RCIS) Report

    (BBNPA, Brecon)

    Brecon Beacons National Park Authority (BBNPA), 2005b, Statement of Objection by the

    Brecon Beacons National Park Authority to the Department of Trade and Industry(BBNPA, Brecon)

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    17/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 17

    Bryman A, and Bell E (2007)Business Research Methods (Oxford University Press, Oxford)

    Cotton M and Devine-Wright P, 2010a, Making electricity networks "visible": Industry

    actor representations of "publics" and public engagement in infrastructure planning

    Public Understanding of Science27(1), pp 17-35

    Cotton M and Devine-Wright P 2010b, NIMBYism and community consultation in

    electricity transmission network planning in Renewable energy and the public: from

    NIMBY to participation ed. Devine-Wright P (London: Earthscan) pp. 115-130.

    Cotton M and Devine-Wright P 2011, Discourses of energy infrastructure development: a

    Q-method study of electricity transmission line siting in the UKEnvironment and

    Planning A43(4), pp 942-960

    Cotton M and Devine-Wright P 2012, Putting pylons into place: a UK case study of public

    perspectives on the impacts of high voltage overhead transmission linesJournal of

    Environmental Planning and Management, forthcoming.

    Cowell R 2004, Market regulation and planning action: burying the impact of electricity

    networks?Planning Theory and Practice5, pp 307-325

    Cowell R 2012, The Greenest Government ever? Planning and sustainability in England

    after the May 2010 elections, Planning Practice and Research, forthcoming.Cowell R and Owens S, 1998, Suitable Locations: Equity and Sustainability in the Minerals

    Planning ProcessRegional Studies32(9), pp 797-811

    Cowell R and Owens S, 2006, Governing space: planning reform and the politics of

    sustainabilityEnvironment and Planning C: Government and Policy24, pp 403-421

    Cowell R and Owens S 2010, Revisiting ... Governing space: planning reform and the

    politics of sustainabilityEnvironment and Planning C: Government and Policy

    28(6), pp. 952-957.

    Cowell R and Owens S, 2011,Land and Limits: Interpreting Sustainability in the Planning

    Process 2nd edition (Routledge, London)

    Defeuilley C, 1999, Competition and Public Service Obligations: Regulatory Rules and

    Industries GamesAnnals of Public and Cooperative Economics70(1), pp 25-48Department for Business Innovation and Skills (BIS), 2009,Joint Energy Security Of Supply

    Working Group (JESS) http://www.berr.gov.uk/energy/reliability/security-

    supply/jess/index.html

    Department of Energy and Climate Change (DECC) 2009,Draft Overarching National

    Policy Statement for Energy (EN-1) (The Stationery Office, London)

    Department of Trade and Industry (DTI), 2003, Our Energy Future - Creating a Low Carbon

    Economy (The Stationery Office, Norwich)

    Department of Trade and Industry (DTI), 2007, The Public Gas Transporter Pipe-Line Works

    (Environmental Impact Assessment) Regulations 1999, Regulation 14: Felindre to

    Tirley Pipe-Line (The Stationery Office, London)

    Freudenburg W R and Pastor S K 1992, NIMBYs and LULUs: Stalking the SyndromesJournal of Social Issues48(4), pp. 39-61.

    Gamble D J, 1978, The Berger Inquiry: An Impact Assessment ProcessScience199(4332),

    pp 946-951

    Gross C 2007, Community perspectives of wind energy in Australia: The application of a

    justice and community fairness framework to increase social acceptanceEnergy

    Policy35(5), pp 2727-2736.

    Guy S, Graham S, and Marvin S, 1996, Privatized Utilities and Regional Governance: The

    New Regional Managers?Regional Studies30(8), pp 733-739

    Guy S, Graham S, and Marvin S, 1997, Splintering Networks: Cities and Technical

    Networks in 1990s BritainUrban Studies34(2), pp 191-216

    Guy S, Graham S, and Marvin S, 1999, Cities, regions and privatised utilitiesProgress in

    Planning51, pp 91-169

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    18/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 18

    Hall D and Lobina E, 2004, Private and public interests in water and energyNatural

    Resources Forum28(4), pp 268-277

    Hardy M and Ritchie H, 2010, Energy Distribution and the New Politics of Regulation

    paper for Science & Technology Policy Research Conference: "Energy transitions in

    an interdependent world: what and where are the future social science research

    agendas?" University of Sussex 25-26 February,

    http://www.neopanora.com/en/sustainable-development/115.html

    Harris J, 2007, How green was my valleyThe Guardian 2 April,

    http://www.guardian.co.uk/environment/2007/apr/27/energy.activists

    House of Commons Energy and Climate Change Committee (ECCC) 2011, The revised draft

    National Policy Statements on energy (The Stationery Office, London)

    Kellet J E, 1993, Role of the town and country planning system in controlling development

    of electricity generating installationsIEE Proceedings A140(1), pp 94-99

    Le-Las W and Shirley E 2012, Does the planning system need a teaparty?Journal of

    Planning & Environment Law3, pp. 239-243.

    Manners G, 1997, Gas market liberalization in Britain: Some geographical observations

    Regional Studies31(3), p 296Marshall T, 2010, Planning major infrastructure sectors in the UK during recent decades

    Oxford Brookes School of the Built Environment Working Paper,

    http://planning.brookes.ac.uk/projects/resources/engsectoralConclusions.pdf

    Marshall T, 2011, Reforming the process for infrastructure planning in the UK/England

    1990-2010Town Planning Review82(6), forthcoming

    Marsh D and Hall M 2007, The British Political Tradition: Explaining the Fate of New

    Labour's Constitutional Reform AgendaBritish Politics2(2), pp. 215-238.

    McCollum D, 2006,AGI risk assessment - Corse PRISubmission to planning inquiry,

    application reference P0624/06/FUL, Forest of Dean District Council

    Moran M, 2007, The British Regulatory State: High Modernism and Hyper-Innovation

    (Oxford University Press, Oxford)National Grid, 2005, Gas Transportation Ten Year Statement 2005 (National Grid, Warwick)

    Office of the Deputy Prime Minister (ODPM), 2004, Planning Policy Statement 7:

    sustainable development in rural areas (HMSO, London)

    Owens S, 2004, Siting, sustainable development and social prioritiesJournal of Risk

    Research7(2), pp 101-114

    Plummer M and Mellish R, 2007, Secretary of State's Decision in respect of Corse gas

    pressure reduction installation, application reference P0624/06/FUL, Forest of Dean

    District Council

    Rose N, 1999, The powers of freedom: reframing political thought(Cambridge University

    Press, Cambridge)

    Rough E 2011, Policy learning through public inquiries? The case of UK nuclear energypolicy 1955-61Environment and Planning C: Government and Policy29(1), pp. 24-

    45.

    RPS Planning, 2007, Full Planning Application to Install Natural Gas Pressure Reduction

    Installation at Land Adjacent to Lime Street and Moorend Road off B4211, Corse,

    Gloucestershire: Statement of Case on Behalf of National Grid, application

    reference P0624/06/FUL, Forest of Dean District Council

    Sadler D 2001, The political economy and regional implications of energy policy in Britain

    in the 1990sEnvironment and Planning C: Government and Policy19(1), pp. 3-28.

    Scott, J C, 1998, Seeing like a state: how certain schemes to improve the human condition

    have failed(Yale University Press, New Haven)

  • 8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure

    19/19

    DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 19

    Scott P, Miller C and Wood C, 1998, Planning and pollution: an unusual perspective on

    central - local relationsEnvironment and Planning C: Government and Policy16(5),

    pp 529-542

    Tester D, 2010,Report to the Secretary of State for Communities and Local Government and

    to the Secretary of State for Energy & Climate Change: Town and Country Planning

    Act 1990 Appeal by National Grid Gas plc, Tirley Gas Pressure Reduction

    Installation, Tewkesbury Borough Council (Planning Inspectorate, Bristol)

    Walker G 2009, Beyond Distribution and Proximity: Exploring the Multiple Spatialities of

    Environmental JusticeAntipode41(4), pp. 614-636.

    Walls, J, O'Riordan, T, Horlick-Jones T, Niewhner, J, 2005, The meta-governance of risk

    and new technologies: GM crops and mobile telephonesJournal of Risk Research

    8(7-8), pp 635-661

    Ward D, 2001, Stakeholder involvement in transport planning: participation and power

    Impact Assessment and Project Appraisal19, pp 119-130

    Winstone R, Bolton P and Gore D 2007,Energy Security (House of Commons Library,

    London)

    Woolley O 2010, Trouble on the Horizon? Addressing Place-based Values in Planning forOffshore Wind EnergyJournal of Environmental Law22(2), pp. 223-250.