Upload
chris-groves
View
216
Download
0
Embed Size (px)
Citation preview
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
1/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 1
Fighting the Pipe: neo-liberal governance and barriers to effective community
participation in energy infrastructure planning
Christopher Groves, Max Munday, and Natalia Yakovleva
Abstract
Development of effective participatory mechanisms within infrastructure planning
governance has been dependent on how far the outputs of participatory processes have an
impact upon strategic policy priorities. However, neoliberal modes of governance are
characterised by recentralisation within arms-length regulatory bodies and private
corporations. Tensions between participatory governance and re-centralisation are
exemplified by the relationship between energy privatisation and energy infrastructure
planning. This study examines these tensions using a case study of a critical infrastructure
project in the UK, the South Wales Gas Pipeline. Findings confirm arguments in the literature
that siting conflicts often centre on policy issues as much as local concerns. The study reveals
that the neoliberal recentralisation of some governance functions exacerbates such conflicts.It argues although new efforts to secure effective participation in neoliberal regimes are
necessary, they will face obstacles in the form of risk-based governance structures, as
exemplified by the privatised energy sector.
Keywords
Infrastructure planning, participatory governance, pipelines, planning cascade, privatisation.
Introduction
The heart of conflicts over the siting of nationally-important infrastructure is often seen as a
clash between not-in-my-backyard (NIMBY) local interests and national policy. It has alsobeen argued, however, that siting conflicts over such infrastructure often act as condensation
points for wider concerns, which can cross scale from the interests of a specific community
to connect with national and even international issuessuch as mitigating climate change,
protecting indigenous peoples rights and so on (see Owens 2004). As a result, participatory
planning may be seen as more than just a means of improvingprocedural fairness, as
emphasised by some commentators (e.g. Gross 2007). By linking siting proposals to broader
political priorities, genuinely effective participation has a substantive dimension, exemplified
by the case of the Mackenzie Valley gas pipeline in Canada (Gamble 1978). Nonetheless,
Owens (2004) and Cowell and Owens (2006) have pointed, in the UK context, to how a
countervailing streamlining tendency in land-use planning can close down opportunities for
participatory decision-making, reducing siting decisions to a trade-off between national needand local interests. In this paper, we explore how such trade-offs, and conflicts driven by
them, are the product of forms of governance which characterise neo-liberal societies, with
the aid of a major energy infrastructure case study from the UK (the South Wales Gas
Pipeline, or SWGP). Our argument is that, while participatory decision-making has made
inroads into governance within contemporary societies, the decentralisation of power
associated with neoliberalism (and in our case study, with energy privatisation in particular)
brings with it a distributed re-centralisation of decision-making. Such re-centralisation may
intensify streamlining tendencies within planning governance, and can prevent
participatory mechanisms from taking forms which achieve either procedural fairness or true
effectiveness, i.e. substantive impact. We show that, in line with significant recent literature,
that substantive issues often form the focus of planning conflicts. We also suggest that, basedon our case study, how the power to shape the policy priorities that drive infrastructure
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
2/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 2
development is distributed may be among these issues. The paper is structured as follows.
First, it examines the literature in order to argue that the effectiveness of participatory
mechanisms is dependent on whether they allow second-order reflection on the policies and
purposes which drive infrastructure development. Second, it shows how this mode ofsubstantive participation stands in tension with risk-based modes of neo-liberal governance
exemplified by the privatised national energy network in the UK. Third, the paper explores
the history of the SWGP project and investigates how community groups engaged with the
planning process, before discussing how this case can help us understand the tensions
between the drive for more participation, and the re-centralisation of governance. We show
how, although the Pipeline was built under a planning regime that has been superseded in the
UK following the 2008 Planning Act, the issues it raises are perhaps even more significant
under the new regime.
Background
Participatory governance
Since the 1970s, land-use planning has seen a variety of experiments with participatory
processes as an alternative to the classic technocratic model of decide-announce-defend,
often associated with a high modernist model of government (Scott 1998). Simultaneously,
the emergence of neo-liberal forms of economic governance during the same period gradually
transformed the relationship between the state and society. Increasingly, the state became a
facilitator of development rather than its agent. The privatisation of public utilities in many
societies since the 1980s has consolidated this new role. However, as has been observed in
the case of the UK, this new form of state may have its own utopian projects quite as
ambitious as those of high modernism (Moran 2007 p. 6). The need for society to be legible
to an administrative centre did not decrease. Indeed, it increasedproportionate to the
degree to which administrative responsibilities are re-distributed and more and moreactivities become subject to audit and measurement. Further, the auditing gaze does not
simply survey the present. It also takes on a new temporal aspect by seeking to render thefuture more legible, through risk thinking (Rose 1999).
A new focus on participation, along with risk thinking, represent two tendencies within a
broad stream of governance reform that flowed through the 1960s to the 1990s (Walls et al.
2005, pp. 641-643). On the one hand, greater participation is seen as a means both of
enhancing the ability to anticipate perhaps overlooked negative outcomes of action, and of
also improving the legitimacy of governance by balancing the privatisation of governance
with greater involvement of stakeholders in decisions. On the other, the internalisation of
risk thinking as a discourse of quantification and auditing within organisations became a wayof creating another model of legitimacy for governance. The tense relationship between these
two tendencies is important for understanding how infrastructure planning has evolved under
neoliberalism.
In what follows, we set out, in more detail, key features of the two tendencies in relation to
planning. With respect to participatory governance, it has been argued that it may improve
decision making with regard to the potential social and environmental impacts of
infrastructure development (Ward 2001). Participatory processes may marshal a more
comprehensive and inclusive evidence base that draws on a variety of perspectives including
local knowledge. In this sense, they can be instrumentally useful. They may, however, be
preferred on account ofjustice. By allowing more perspectives on a proposal to be included,they can enhance distributive andproceduraljustice (Gross 2007). They may also enable
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
3/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 3
greater recognition of historical injustices, including e.g. local accumulations of polluting
infrastructure that stigmatize particular places and communities (Walker 2009). To be
effective in serving these three purposes, participation should ideally be early, when
alternatives are still open; be inclusive and feature two-way communication; allow access to
key information; offer genuine opportunities to influence or even veto decisions; take into
account the diverse values of participants; and be transparent (Bond et al. 2004). However,
participation may be effective in another sense by allowing public reflection on substantive
issuesincluding what kind of society participants wish to inhabit, questions of national
interest, and other matters. In this way, participation around planning concerns at local and
regional scales can provide an arena for focused reflection on the assumed purposes of
national strategies (Cowell and Owens 2006, 2011).
Consequently, participation can embody reflexivity in an expanded sense, even if it takes
place downstream of strategic decisions. If a piece of infrastructure is a kind of solution to
a problem, then participatory governance may, by including more perspectives, enable the
problem itself to be examined, along with the ways in which it has been framed as a problem.
In this way, whether participation is effective or not depends on how far it enacts second-order reflexivity towards both means and presupposed ends. Substantively effective
participation may be imagined as creating a feedback loop (Rough 2011), which begins with
an examination of localised impacts, benefits and risks associated with a given proposal.
Widening participation in examining these illuminates, in turn, considerations which may
lead to a critique and re-framing of the policy problem to which the planning proposal
appears as a viable solution. In this way, local planning conflicts can lead to modifications in
assumed definitions of the national interest, even if they do not end in consensus (Owens
2004).
Risk thinking, power and energy infrastructure planning under neoliberalismWe now turn to the second of the aforementioned tendencies, i.e. the internalisation of risk
thinking within governance as a legitimatory discourse, and how this shapes the distribution
of power in planning. The relationship between this tendency and the evolution of
participation as a form of second-order reflexivity is often conflictual. The tension here
derives from the opposed logics of power which characterise the two tendencies. Where
effective participation demands dispersed power (Ward 2001), embodied in institutionalized
processes that drive critical scrutiny of policy problems as well as solutions, neo-liberal
enrolment of private companies and other governance actors decentralises while
simultaneously recentralising. The creation of new centres of calculation (e.g. privatised
energy utilities, industry regulators) is accompanied by the need to render the field in which
they operate legible to government, both in the present and with a view to its projectedfuturesrequirements in which risk thinking plays a significant role. In the next section, we
will explore the internalisation of risk thinking within the UKs planning regime in relation to
energy privatisation, and how risk knowledge and power are linked.
As noted at the beginning of the previous section, the neo-liberal state can be viewed as
evolving, in some respects, out of the high-modernist state. The high-modernist state evolved
a set of tools for transforming an uncertain future into a meaningful parameter of planning,
one that could be both told and tamed (Adam and Groves 2007). State bureaucracies
developed quantitative criteria for measuring the success or failure of policies, depoliticizing
decision making in the process and recreating the domain of politics in a way amenable to
bureaucratic management (Rose 1999, pp. 198-199). Representing the future in terms of risk,
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
4/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 4
and developing methods for estimating and comparing risks, extends the legibility of society
into the future.
Neoliberalism re-affirms this legitimatory role for risk. In relation to the UK, Moran (2007)
observes that the contemporary British neo-liberal state has adopted a role of regulating and
balancing markets as providers of public goods. The amount of statistical information the
new regulatory state requires means that new and closer relationships have to be built
between government bureaucracies and expert advisors. The persistence of a centralised and
linear predict and provide approach to the future in contemporary British infrastructure
planning has been noted (Cowell and Owens 2006; Marshall 2010, p. 30), a durable high-
modernist element of a British political system where the stress, historically, has
consistently been upon strong, centralized, efficient government, rather than responsive
government, and in which the government has traditionally been seen as the sole judge of
the national interest (Marsh and Hall 2007). What changes with energy privatization is that
the centre where information is collated and future risk scenarios produced is no longer
singular and located in Whitehall, but multiple and dispersedlocated in the corporate
headquarters of privatised utilities and of regulatory agencies (Scott et al. 1998).
An important UK example of these changes is energy privatisation. Before privatisation in
the 1980s, the production and distribution of energy in the UK was a public duty of state-
controlled bodies. With privatisation, this universal obligation is lost (Guy et al. 1997).
Instead of one organisation, a multitude of providers is created, who have public service
obligations but also private commercial obligations. Away from energy production, the
electricity and gas distribution network was signed over to a private monopoly (National Grid
plc, formerly Transco, the sole transmission network operator or TNO in England and
Wales). Part of the public duties falling on National Grid (NG) as a TNO is to forecast future
demand and infrastructure needs and inform policy frameworks. In fulfilling the duties, NG
produces annual ten-year statements (e.g. National Grid 2005), which inform white papers,statements of need and other elements ofgovernment policy through fora which have
included (between 2001 and 2006) the Joint Energy Security of Supply Working Group
(JESS), whose remit was to assess risks to the UK's future gas and electricity supplies
(Department for Business Innovation and Skills (BIS) 2009) and to identify relevant policy
issues and consider implications (Winstone et al. 2007, p. 5). Under the new planning
regime introduced by the Planning Act 2008, this information continues to be the main source
of demand forecasts which inform the National Policy Statements (NPS) relevant to gas and
electricity infrastructure (DECC 2009, p. 11). As a result, policy answers to the essentially
political question of what is in the national interest with respect to energy are significantly
influenced by essentially administrative bodies such as JESS.
NG thus plays the role of a key centre of calculation, providing future demand forecasts
which help tame uncertainty, while also being a developer that constructs infrastructure in
response to these forecasts. Following privatization, the commercial arrangements for
downstream supply of gas became much more complex. Increased uncertainty and risk for
investment in infrastructure created a greater need for stability, so that long-term supply
contracts guaranteeing stability of supply could be signed (Manners 1997, p. 302). In
contrast, the Government itself is no longer a developer, nor is it a strategic planner, having
adopted a governance role ofnon-decision making (Cowell 2004, pp. 312-313). Another
such centre is the energy industrys regulatory body, the Office of Gas and Electricity
Markets (Ofgem), which was responsible, along with the then Department of Trade and
Industry (DTI), for chairing JESS. Ofgem was created in 1999 with the primary remit of
making privatised energy production utilities accountable to consumers (Moran 2007) and of
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
5/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 5
facilitating a predictable environment for investment through forward price signals
(Department of Trade and Industry 2003, p. 14). The need for a regulatory regime stronger
than that which operates across the rest of the private sector is necessitated by the statutory
duties which fall on utilities (established in the UK under, inter alia, the Gas Act 1986 and
Electricity Act 1989) to provide essential goods. Ofgem is often seen as an agency whose
primary goal is to encourage competition and hold energy producers accountable for their
pricing strategies. Nonetheless, it also has responsibilities for regulating the wider
environmental and social impacts of electricity and gas provision, including the infrastructure
which NG constructs. It has, however, proven difficult to translate these responsibilities into
concrete practice (Guy et al. 1997, p. 214; Cowell 2004, pp. 319-320).
At the strategic level, then, the relationship between NG and Ofgem as centres of calculation
is not strictly one of regulated and regulator, as Ofgem has historically concentrated on its
duties as a representative of energy consumers. NGs input into policy means that it occupies
a special role in the UK system, consolidated by the predict and provide strategic approach
to energy infrastructure, in which demand is something to be met, rather than managed. Since
the 1970s, the need for longer-term energy demand forecasting in neo-liberal societies hasincreasinglybeen framed in terms of maintaining energy security (Marshall 2010), an issue
defined by the International Energy Agency in terms of interlinked systemic risks (Winstone
et al. 2007, p. 1). Such discourses locate policy debates within narratives of necessity, in
which the national interest is assumed to lie in providing for projected energy demand, which
will in turn generate more economic growth (Cowell and Owens 2011, p. 15). This generates
the fundamental set of policy problems, in relation to which technical advice (from
companies like NG), white papers and infrastructure proposals (from companies like NG)
represent steps towards solutions. The position of energy utilities, TNOs and regulatory
agencies within high-level planning processes is thus defined within these narratives of
necessity. Their power to affect spatial planning is proportional to their role as centres of
calculation of need and risk, joined to their role as developers. While Ofgem is active intrying to regulate energy markets, it is not so in regulating infrastructure planning in any
high-level strategic sense. This is left to downstream processes of impact assessment and
review within the planning system. The lack of strategic regulation of environmental and
social impacts reinforces what Owens (2004) has described as a planning cascade, in which
policy problems, cloaked in necessity, drive policies which define national need, before being
translated into concrete infrastructure proposals. Only at this latter stage can participatory
mechanisms be activated, solely to determine where the infrastructural solution to the
policy problem should go, rather than enacting effective, substantive reflection on strategic
problems. In this way, planning conflicts emerge as, primarily, conflicts between local
interests and the national interest, this latter having become largely insulated from
reflection and critique in the process.
Recent changes to the UK planning system
Making the situation still more difficult for effective participatory governance are changes in
the mechanics of planning governance.1
Until 2008, the Town and Country Planning Act
(TCPA) was the chief legal instrument for oversight of land use planning in England and
Wales. For larger installations of national importance, consents were traditionally granted by
the relevant department of the UK Government, a system of deemed consent which
overrode the need, under the TCPA, for developers to seek permission from a local planning
1Note that this discussion applies primarily to the situation in England and Wales within the UK. Planning
governance in Scotland and Northern Ireland differs in relation to many or all of the following considerations.
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
6/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 6
authority (LPA). This made it less imperative for LPAs to map out forward-looking policy on
the acceptability of different kinds of energy infrastructure in particular locations (Kellet
1993, p. 96). Consequently, the relationship between local authorities and privatised utilities
with regard to planning was generally, though not always (Guy et al. 1999), a highly reactive
one (Scott et al. 1998, p. 539). With respect to regional and local spatial planning local or
regional spatial development plans (LDPs, RDPs) were the medium through which LPAs
translated into policy the short- and longer-term interests of communities for whom they were
responsible. How the centralized decision-making processes of utility companies related to
these spatial strategies within the planning system was therefore complex and often
problematic (Guy et al. 1996). LPAs which attempted to use its LDP or RDP to ensure that a
particular area that had been historically burdened with hazardous and/or polluting
infrastructure developed along a different economic path have generally found that this was
not enough to stop planning permission being granted for more infrastructure of this kind
(Scott et al. 1998). Provided consent was given by the Secretary of State, then the only
further obstacle was having a proposal called in by a government minister, something
which opponents could request. Nonetheless, this system saw a series of significant,
successful challenges brought against major infrastructure projects in the 1980s and 1990s.As such, the planning system contained counterweights to technocratic, predict-and-
provide-style planning.
These challenges created a perception within government and industry that the planning
system was subject to blockages and in need of being modernised. At the same time, the
increased demand for participatory governance in planning was acknowledged. The result
was an uncomfortable synthesis of proposals for streamlining planning and for public
engagement in spatial planning, manifested within the Governments Planning: Delivering a
Fundamental Change Green Paper in 2001 (Cowell and Owens 2006, p. 407). The
subsequent Barker Review of Land Use Planning (2006) added to the momentum behind
modernisation, ahead of the 2008 Planning Act, which included two main innovations.First, new strategic policy instruments (National Policy Statements or NPS) relevant to large
infrastructure of national importance, and second, a new centre of calculation, the
Infrastructure Planning Commission (IPC), whose role was to assess planning proposals
designed to fulfil needs identified in an NPS. The IPC could, in theory, find against a
proposal which might impose excessive costs on local communities, but would have to
disregard representations that relate to the merits of policy set out in a national policy
statement during [...] decision making (Woolley 2010, p. 236). Without a clearly negative
net local effect, the IPC would be likely to decide quickly in favour of the national interest, as
defined by an NPS, over local interests in any given case. This led some commentators to
interpret the new regime as reinforcing planning cascades by closing off opportunity
structures within which objectors could link particular proposals to reflections on strategicconcerns, in the way that substantively effective participation demands (Rough 2011, pp. 40-
41). Although some consultative input was allowed into the formation of NPS, the level of
abstraction involved here meant that these consultations were unlikely to benefit from the
energetic mobilisation of different perspectives with which local campaigns often connect
localised impacts to national policy (Woolley 2010, p. 237).
Not long after the Conservative-Liberal Democrat Coalition took power in 2010, the IPC was
dissolved, with its role and powers being assigned to a section of the Planning Inspectorate.Revisiting their 2006 paper on the modernisation of planning, Cowell and Owens (2010)
noted that, under the Coalition, infrastructure planning would likely not be materially
different to the streamlined cascade structure established by the 2008 Act. The significance
of the localism governance agenda introduced by the Coalition, most notably with the
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
7/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 7
Localism Act 2011, for these issues remains to be seen, although some have suggested that
negative impacts from the Act are likely to be felt on local democracy generally, and
planning in particular (Cowell 2012; Le-Las and Shirley 2012).
The potential for planning cascades shaped by high-level, technocratic processes of need and
risk management is thus characteristic of the UK planning system, before and after the 2008
Act, and is particularly evident in relation to energy infrastructure. The delegation of
legitimate authority to manage future energy risk by government to privatised utilities renders
decision-making non-transparent, creating facts on the ground to which LPAs and
communities affected by infrastructure plans have to respond when the cascade reaches them.
This reinstates a technocratic, modernist decide-announce-defend model of planning
strategy within neo-liberal governance (Hardy and Ritchie 2010, p. 15). The opportunity for
wider participation in the planning process comes far downstream from the point where a
piece of infrastructure has been judged nationally necessary, and a set of alternative sites
determined (Cotton and Devine-Wright 2011, p. 954). Consultation with regard to NPS
notwithstanding, the regime established by the 2008 Act does not establish opportunity
structures that might counteract the cascade, by allowing effective and substantiveparticipatory reflection on policy and the national interest. Under the neo-liberal
governance regime that prevails in energy privatisation, the responsibilities and power
delegated to TNOs like NG appears to put them in a unique position, where their strategic
role is counterbalanced neither by significant strategic regulatory oversight of the social and
environmental impacts of their activities, nor by upstream participatory negotiation of the
priorities they help define. Some have argued that the need for such counterweights is
underlined by the concern that with privatisation comes potential conflict between the public
duties of utility companies and their private obligations to shareholders and others, which can
result in negative consequences for service users and those affected by planning decisions
(Defeuilley 1999; Hall and Lobina 2004).
Case Study: The South Wales Gas Pipeline (SWGP)
The South Wales Gas Pipeline project, in which NG was a major actor, was framed by NG
and government against the background of an impending energy crisis linked to the
dependence of the UK on imported gas (e.g. Department of Trade and Industry 2003).
Official definitions of national need reflected assumptions that the country would
experience continually-growing demand for gas and other resources (Marshall 2011). In the
first years of the 21st
century, two consortia of petrochemical companies submitted plans to
build LNG terminals at sites around Milford Haven in West Wales in response to policy
signals regarding future demand for gas. NG signed contracts with these consortia that
imposed upon it an obligation to provide infrastructure to connect these terminals to the UKNational Transmission System (NTS) at a site across the English border in Gloucestershire.
The pipeline to connect the Milford Haven terminals to the NTS would be of unusually large
diameter (1220 mm, 48 inches) and run at a pressure higher than usual for the UK NTS (94
rather than 75 barg). The pipeline construction work comprised two phases (see Figure 1).
Phase 1 ran from Milford Haven to Aberdulais, with a length of 120 km (75 miles), and
Phase 2 ran from Felindre to Tirley, being 196 km (122 miles) long. The pipeline fell outside
the scope of powers granted to the Welsh Assembly in the 1998 Government of Wales Act.
Our research into how communities experienced the planning process for the pipeline took
the form of a series of 17 semi-structured interviews during 2007-09. Studying the impact of
network infrastructure like pipelines presents particular methodological difficulties. In order
to provide as comprehensive a picture as possible of concerns along the route, interviews
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
8/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 8
were conducted with representatives of various campaign organisations from flash -point
sites along the full length of the pipeline, including Safe Haven (Milford Haven and
Waterston, the sites of the two terminals), CRA (Cilfrew Residents Association, concerned
with a pressure reduction station), CRAG (Cwmtawe Residents Action Group, at Trebanos,
concerned with Phase 1 of the pipeline), a looser group centring on Brecon and Hay-on-Wye
(concerned with Phase 2) and CAPRI (Campaign Against the Pressure Reduction Installation,
at Tirley). Participants were selected using a snowballing method (Bryman and Bell 2007).
Interview material was transcribed, coded and qualitatively analysed with NVivo 8 software
to identify and compare community concerns and how campaigns (and their primary
concerns) developed over time. Secondary materials were also used to help construct a
timeline of events. These included press reports, publications and press releases from NG, its
contractors, and the Milford Haven Port Authority, and planning documents. Case
development also drew on research undertaken on the impacts of LNG in West Wales by one
of the authors for Pembrokeshire Business Initiative during 2007 (Bryan and Munday 2007;
Bryan et al. 2007).
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
9/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 9
Figure 1: The South Wales Gas Pipeline, Phases 1 & 2
Initial stages and early conflicts
Interviewees in Milford Haven, a town with a long history of petrochemical infrastructure
development, reported first being informed of the LNG terminal projects via exhibitions held
in the town during 2004, at least a year after the planning proposals had been submitted toPembrokeshire Council. They reported that local people had not being given any opportunity
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
10/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 10
to comment on the applications during the period prior to this, when the proposals were being
considered by the LPA (Interviewee, Waterston, 31 July 2008). Concern began to crystallize
around how the risks of allowing LNG tankers into the narrow and busy Cleddau estuary had
been assessed, particularly following the Sea Empress disaster in 1996. Unsuccessful requests
to the terminal consortia and to Milford Haven Port Authority (MHPA) for risk assessments
in November 2004 resulted in a court case being brought by the members of what would
become the Safe Havens campaign group to compel MHPA to release the relevant
information. This case was unsuccessful, largely because the request had come too late in the
planning process for the release of the information relevant to make a difference: theyve
spent millions of pounds, therefore youve lost your window of opportunity (Interviewee,
Milford Haven, 23 July 2008). Safe Havens felt that the proposal had, thanks to concerns
about energy security, too much momentum and that Milfords existing concentration of
heavy industry had made it the ideal destination for the terminals, despite international best
practice recommendations on LNG facility siting recommending that they be sited offshore
(Interviewees, Milford Haven, 23 July 2008, and Waterston, 31 July 2008). When risk
assessment information was made available, after a ruling against MHPA from the
Information Commissioner, the content was felt to be generic rather than specific to theconditions in the Cleddau. Attempts to persuade the Welsh Assembly to intervene were
unsuccessful, an experience shared by Welsh campaigners against the pipeline later on.
Although the Assembly has no powers regarding strategic assessment of proposals of this
kind, it was a statutory consultee in both cases, and some interviewees expressed surprise that
it had not objected on the grounds of the Welsh Assembly Governments obligation to
promote sustainable development (Interviewee, Cilfrew, 22 July 2008).
For its part, NG submitted planning proposals for the two phases of the pipeline in 2004 in
line with the requirements of the Public Gas Transporter Regulations 1999 (subject to
deemed consent rather than to the TCPA). In its proposals, it justified the pipeline by
invoking an energy security national interest argument, buttressed by demand forecasts. Inaddition, it stated the pipeline was also necessary for it to fulfil its public service obligations
under the Gas Act 1986 to maintain efficient and economical gas supply infrastructure.
This second argument concerning public duties resurfaced at subsequent planning inquiriesalongside invocations of national interest. The relationship between these duties and NGs
private interest in fulfilling the contracts it had signed with LNG importers to finish the
pipeline by early 2007, would prove of particular interest to campaigners. To what extent,
campaigners would ask, were the criteria of efficient and economical an adequate way of
understandingNGs public duty, given that the fulfilment of private contracts for completion
by a certain date would determine how efficient and economical the infrastructure would
be. Campaigners were suspicious that consultation was kept to a minimum as a way of
avoiding siting conflicts and thus reducing commercial risk. The possibility of conflicts ofinterest ran alongside a lack of incentives for NG to promote participatory engagement.
Research suggests that energy infrastructure companies tend to view consultation as primarily
one-way and informational (Barnett et al. 2012). Network infrastructure, such as pipelines or
overhead power lines, which connect together multiple sites, presents particular practical
obstacles for public engagement. In such cases, researchers have also documented
assumptions held by developers about the publics inability to take the strategic view
necessary for looking at the network as a whole (Cotton and Devine-Wright 2010a).
The process of impact assessment and route choice for the two phases of construction
provided the first opportunity for opposition to the pipeline to crystallize. During 2004-05,
NG provided assessments of the viability and impact of a number of potential offshore and
onshore pipeline routes. Following the granting of consent for Phase 1 in December 2005, the
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
11/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 11
selected route options for Phase 2 produced significant controversy. At this stage, the DTI
sought responses from statutory consultees, including relevant regulatory bodies, LPAs and
businesses. The Brecon Beacons National Park Authority, from the outset, took a strongly
critical stance towards any route through the Beacons. In responding to NGs proposals, the
BBNPA noted that (a) the route choices, (b) the judgement that a pipeline connecting Milford
Haven to the NTS was necessary for NG to fulfil its public obligations and in the wider
national interest, and (c) that a pipeline of just this specification was in the national interest
and required by NGs public obligations were all questionable. It suggested that it was for the
DTI to provide its own independent judgement on these issues, preferably by means of a
strategic environmental assessment of the whole project andpost-privatisation governance
(BBNPA 2005a, b).
The objections put forward by the BBNPA exploited its position as a statutory consultee by
seeking to establish a link between the potential harmful impacts of NGs specific proposals
and what it saw as illegitimate policy priorities. In doing so, it presented a strategic critique of
the pipeline project as a whole, rooted in its assessment of impacts on its locality.NGs
statement of need was interpreted by BBNPA as being in conflictwith its public dutiesunder the Governments planning guidance on sustainable development (ODPM 2004). This
was because a conflict of interest was perceived within the very choice of a predict and
provide methodology for assessing national need, given that NG also had a commercial
interest in stimulating gas demand (BBNPA 2005b, p. 6). Indeed, a subsidiary part of the case
for new infrastructure was that it would aid development and [] give opportunities for
industry and users of gas to create business opportunities (BBC News 2006). Further, the
argument from need did not acknowledge concerns first voiced in the late 1990s that
increasing demand for gas might create infrastructural path dependencies that could decrease
energy security (Sadler 2001, p. 14) and that demand should be managed rather than met.
BBNPAs argument was thus that the national need case for a pipeline was questionable, but
also that no national interest case could be made for any particular route. Further, it arguedthat there was a clear alternative definition of the national interest: protecting National Parks
held in trust for future generations, and driving energy infrastructure development faster
towards better use of renewables (BBNPA 2005b). The strategic arguments first put forward
by the BBNPA were subsequently employed by the various campaigning groups who became
active along the length of the pipeline, as they began to coordinate and share information,
thus allowing each group to create a strategic position on the need for the pipeline as a whole
which shared key feature with those developed by other community groups.
By the middle of 2006, Safe Havens had been joined by four other campaign groups. Cilfrew
Residents Association (CRA) and Campaign Against the Pressure Reduction Installation
(CAPRI) in Tirley were concerned with proposals for gas re-pressurization installations(PRIs) which, unlike the pipeline itself, fell under the TCPA and were subject to normal
planning consultation processes. The PRI in Cilfrew was part of Phase 1 of the pipeline,
while that at Tirley would connect Phase 2 to the main UK NTS. Cwmtawe Residents' Action
Group in Trebanos (CRAG) and a looser group of campaigners around Brecon and Hay-on-
Wye were concerned about issues relating directly to Phases 1 and 2 of the pipeline
respectively. In each case, interviewees reported that the groups had organised themselves in
response to what they felt was a failure on the part of NG to consult adequately, and in
particularly, a failure to involve communities in impact assessment processes.
In early 2006, CRA established that the PRI environmental impact assessment NG had
submitted was for the wrong site (Interviewee, Cilfrew, 22 July 2008), which required a
resubmission. When the LPAs planning committee approved the proposal in September
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
12/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 12
2006, four councillors who had met CRA were excluded (Harris 2007). On the basis that this
had violated procedure, CRA applied for a judicial review of the grant of approval, which
they won in March 2007. The proposal was voted on again in May of that year and approved,
despite continuing and largely unanswered representations from CRA regarding its social and
environmental impact (Interviewee, Cilfrew, 15 October 2008).
In Trebanos, CRAG discovered in June 2006 that NGs contractors intended to use blasting
as part of the Phase 1 construction, following an exhibition on 5 and 6 June. CRAG objected
to the blasting taking place, on the grounds that the pipeline route took it close to peoples
houses, as well as through an area historically affected by subsidence and by unmapped mine
workings where laying of mains gas pipes was not permitted (Interviewee, Trebanos, 25
October 2008). In addition, they discovered that planning permission from the LPA was
needed, and had not been granted (Harris 2007). Following a failure to get the Welsh
Assembly to intervene, the group succeeded in getting the LPAs planning committee to vote
at the end of August on the blasting, which since 8 June had been taking place without
planning permission. However, like the Cilfrew planning committee vote, this was also
subject to procedural irregularities (Interviewee, Trebanos, 30 July 2008; Harris 2007).Thereafter, they contacted an environmental group called Rising Tide and independent
activists from Newport and Cardiff, who in November 2006 organised direct action protests.
Subsequently, on 22 November, the DTI contacted NG and CRAG to announce that
permission to blast had been denied.
Pipeline Phase 2 and the Gloucestershire PRI
Phase 2 of the pipeline was given consent on 7 February 2007. The decision to grant consent
drew on the application of the Silkin Test, a planning criterion set out in 1949 by Lewis
Silkin MP, designed to balance the national need for certain developments against the
localized impacts of such developments in national parks. This set out that development mustbe in the national interest and minimize damage to the park, and that no practical alternative
to must exist. In applying the Silkin Test, the Secretary of State identified the national interest
with the public duties of NG. The judgement stated that it was
desirable that the proposed pipe-line works should be carried out in the interests of the
development and maintenance of an efficient and economical system for the conveyance of
gas [...] (DTI 2007, pp. 5-6)
The BBNPA had suggested, as noted above, that the statement of need put forward by NG
conflated its public duty, the predetermined national interest in meeting gas demand, and the
private obligations NG bore to gas importers with whom it had signed contracts to completethe pipeline by a particular deadline. The decision to grant consent did not address this point.
The BBNPA had also objected that the assessment regime for the project had been deficient,
insofar as no high level strategic assessment had been undertaken by the DTI on the impact of
gas infrastructure development across South Wales, and indeed, of the broader impact of the
marketised modes of energy need and risk assessment that had emerged under privatisation.
The DTI ruled against this objection, noting that the governments role in relation to gas
infrastructure was not one of centralised strategic direction or installation development, and
that the DTI managed only a reactive, project-oriented handling system (DTI 2007, p.3) for
consents.
Following Phase 2 consent, campaigners increasingly began crossing scales, by questioning
in public the strategic social priorities behind the project as a whole at the same time as
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
13/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 13
linking local impact concerns across different sites, and bringing together issues of safety and
environmental risks from different localities which crystallised concerns about the haste
with which the SWGP was being constructed, allegedly under commercial pressure. These
efforts began largely with campaigners in Tirley and Brecon who, with assistance from civil
and retired pipeline engineers living in their respective communities, began asking a series of
technical questions about the safety of the pipeline.
As had been the case at Milford Haven, campaigners expressed concern about the generic
content of risk assessments. A brief document, relating to the pipeline itself (as opposed to
the PRI) was submitted by NG as part of its planning application at Tirley (McCollum 2006).
This document was criticized for failing to include actual calculations and to set out its
assumptions, which campaigners felt suggested it hadbeen prepared at head office rather
than by someone with direct knowledge of local conditions which might affect the
assumptions behind the analysis (Interviewee, Tirley, 24 July 2008; two interviewees,
Brecon, 29 July 2008). Technical information on failure risk and what were felt to be
unaddressed uncertainties were circulated between CAPRI, the Brecon group, CRAG, CRA
and Safe Haven at a series of meetings involving two or more of the groups during 2006. Therationale behind the increased 94 barg operating pressure of the pipeline was subsequently
widely questioned. It was suggested that the increase in pressure resulted in a significant and
exponential reduction of the pipelines operational safety margin, but that it also increased
gas flow rate substantially (an important commercial consideration).
The strategic viewpoint adopted by campaign groups therefore focused on an alleged trade-
off between commercial interests (as distinct from the national interest) and the impacts on
affected communities. In Tirley, an additional localised focus for objections was the
environmental impacts of the proposed PRI on a historically unspoilt location. As with the
generic nature of risk assessments in Milford Haven and at Tirley, the difficulty of
obtaining information on these impacts was felt to reflect what we have referred to above asthe re-centralisation of decision making after privatisation: as a result of planning and
operational decisions being taken by NG at their headquarters in Warwick, and
communications being run by the companys public relations staff in London, the company
were not on the ground throughout the planning and construction process (Interviewee,
Brecon, 19 November 2008). Subsequently, the PRIs environmental impact assessment was
submitted late. When it was made available, part of its case for siting the PRI in this location
was that the specific choice of site was represented as being in the national interest.
CAPRI solicited over 1600 written objections to the proposal. A key point made by a
significant number of objectors, as well as by CAPRI itself, was that, while it might be true
that a PRI somewhere (to reduce gas pressure enough for it to flow into the NTS) would be inthe national interest, placing it in one precise location could not justifiably be said to be. AtTirley, what Owens (2004) describes as the it has to go somewhere dynamic of the
planning cascadebecame it has to go here. A direct, and to campaigners inexplicable,
connection was made between the national interest in energy security and positioning a PRI
in a specific field in Gloucestershire. Alternative sites were available, in particular near an
existing PRI 40km away. Consequently, environmental impacts and safety risks associated
with this site should not simply be traded off against the national interest, and the need for a
PRI at Tirley should be assessed primarily against social and environmental considerations.
The LPA agreed, and refused planning permission on the grounds that the environmental
impact of a PRI at Tirley had been underplayed in NGs EIA, and would be too significant,
given commitments in the LPAs LDP to preserve the integrity of the area.
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
14/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 14
NG appealed. A planning inquiry was held in April-May 2007, at which the national interest
argument for the Tirley site was reiterated (RPS Planning 2007). This inquiry upheld the
LPAs decision, and refused the appeal, a decision ratified by the Secretary of State in
December 2007 (Plummer and Mellish 2007). This decision denied validity to NGs assertion
that granting planning permission for one specific location was in the national interest, and
advised other locations should be examined. A planning application for a new site, which fellwithin neighbouring Tewkesbury Councils jurisdiction, was submitted in December 2008.
Following another campaign by CAPRI, the council refused permission in February 2010,
leading to another appeal and a further planning inquiry in July of that year. This time, the
Secretary of State followed the recommendations of the planning inspector by granting
planning permission.
During the Tirley campaign, after the terminals, pipeline phases 1 and 2, and the Cilfrew PRI
had all been consented and (mostly) constructed, the national interest and public duty
arguments advanced by NG for the pipeline and associated infrastructure were finally
subjected to intensive public examination on the basis of strategic arguments first articulated
by the BBNPA and developed, in relation to local risks, by a campaigners network thatextended the full length of the route. Nonetheless, the 2010 inquiry inspectors report stated
that to serve national need, NG should carry out its licensed and contractual obligations
to supply gas at the required higher volume and pressure through the pipeline, thus requiring
the PRI (Tester 2010, pp. 87-88).
Discussion
The SWGP case, we suggest, has to be understood as a series of siting conflicts which
emerged, in the first place, from repeated failures to facilitate early engagement, but which
were driven by a systemic lack of opportunity structures for effective engagement.
Consultation by the TNO over its strategic plans seems to have shared shortcomings with theefforts of the Milford Haven terminal developers: community campaigners reported these
being partial, often late, and non-inclusive, with NG subsequently being found unresponsive
and even obstructive by some. Following Freudenberg and Pastors (1992) recommendation
that siting conflicts be considered as, essentially, systemic products, we would suggest that
the possibility of effective engagement may be undermined by, first, the structures of
governance that shape policy, and second, the planning system through which infrastructure
proposals pass. We described the neoliberal de- and re-centralization of energy policy and
infrastructure development as a key development through which the opportunity structures
for effective engagement are restricted. By effectively black-boxing the mechanisms
through which national energy needs and appropriate policy responses are assessed, these
adjunct processes of privatisation make substantive, participatory reflection unlikely if notimpossible. In addition, re-centralisation may lead to materially worse impact assessment
procedures, and communication difficulties, as described by interviewees at Milford Haven
and Tirley.
Again and again, the campaigns around the SWGP sought to open up these processes to
scrutiny, to repoliticise processes which, having been framed as technical operations of risk
analysis and management carried out by new centres of calculation, had become de-
politicised, administrative processes. Safety and environmental risks were used to open up
reflexive links between local impacts and the justifiability of national policies. More
importantly, they were used to reframe the nature of the planning conflict. Campaigners
suggested that the question of unacceptability would appear in a different light if the focus
moved to the strategic conflict surrounding the pipeline. They essentially argued that this was
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
15/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 15
not between a fixed national interest and local interests. Instead, it was between the role of
essentially unaccountable, private commercial interests in shaping the national interest, and
the proper contribution which diverse localised community interests (in place, amenity, safety
etc.) could make to shaping assessments of national need.
Arguments about commercial versus community interest first emerged in the BBNPAs
criticisms of NGs choice of route for Phase 2, which, interviewees attested, subsequently
became a key reference point for campaigning (Interviewee, Gorseinon, 30 July 2008). They
managed to go far beyond a focus on amenity and safety to question the legitimacy of high-
level governance mechanisms such as the capacity auctions on which future planning
proposals and the private obligations entered into by privatised energy utilities are dependent
(Brecon Beacons National Park Authority 2005b; Tester 2010). Instead ofaccepting the it
has to go somewhere framing of the planning cascade and the attendant trade-off between
national and local interests, campaigners questioned the assumptions about social priorities
and legitimate expertise which allow such a trade-off to be constructed at all. They asked for
opportunities to represent different conceptions of national interest, such as might be rooted
in the kinds of often intangible and non-quantifiable values held to be the rightful concern ofstewardship organisations like the BBNPA (Interviewee, Hay-on-Wye, 28 July 2008).
However, the successes achieved by campaigners were mainly at planning inquiries where
the main issues were ones of environmental impact to be resolved under the TCPA. Although
campaigners succeeded in ventilating strategic issues, the key points of contention which they
were forced to address were, in the end, ones traditionally encountered at the far end of a
planning cascade, i.e. whether a particular site was acceptable.
Overall, the SWGP case is an example of how major infrastructure proposals were handled
under the TCPA and deemed consent system. How might the 2008 Planning Act and
subsequent developments have altered things? Is there any possibility that they might have
instituted new opportunity structures within which local interests in impacts could crossscales and produce strategic reflections on the relationship between proposals and policy?
As noted previously, there is much uncertainty in this regard. Nonetheless, there are reasons
to remain sceptical. On the one hand, since 2008, NG has demonstrated different approaches
to public engagement in early and wide consultation on strategic infrastructure route options
in relation to overhead linesalthough these approaches may still be based on traditional
developers assumptions about the public (Cotton and Devine-Wright 2012). On the other,
the strategic need for large projects is still settled, after the 2008 Act, in a way which
promises to reproduce planning cascades. NPS present certain forms of facility as desirable
in a way which is enduring, a priori to, and largely insulated from concerns about the
environmental consequences that may arise from individual projects (Cowell 2012), and
retain the same role for some privatised centres of calculation (such as NG) in shaping policyas existed in the days of JESS (DECC 2009, p. 11). The 2008 Act was supposed to allow
Parliament more say on the content of statements on national need. Nonetheless, critical
comment from MPs on the six approved energy NPS (approved in July 2011) produced only
a limited number of caveats. Interestingly, these echoed the worries about gas contributing to
energy insecurity registered by Sadler (2001), as well as the BBNPAs criticisms of new
infrastructure as increasing rather than simply meeting demanda perverse impact of a
new dash for gas (ECCC 2011, p. 84). Furthermore, the creation of a new centre of
calculation by the Coalition (a special unit within the Planning Inspectorate, to replace the
IPC), is likely to exacerbate concerns about transparency rather than reduce them.
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
16/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 16
Conclusion
In this paper, we began with the tension between two tendencies within contemporary neo-
liberal societies: increasing use of participatory governance, and developments that entrench
risk thinkingin new centres of calculation. We examined how this tension plays out
within a specific case study, originating within a privatised energy industry that has been
used as a template for international energy governance by development organisations like theWorld Bank (Guy et al. 1999, p. 161). This case shows how siting conflicts within neoliberal
systems of governance may centre on clashes of interests that are not reducible to national
need and local concern. If the need for participation is a legitimate need, then it requires, we
would suggest, procedurally fair implementation which focuses on substantive concerns,
including such conflicts of interests. What the SWGP case demonstrates is that, in systems of
governance where power is redistributed, to some degree, to private organisations with public
duties, the accountability of these organisations in assessing need and managing risk must be
included in the substantive issues participation considers. We therefore concur with recent
scholarship (Cowell and Owens 2006; Cotton and Devine-Wright 2010a; Cotton and Devine-
Wright 2010b; Cowell and Owens 2011; Cotton and Devine-Wright 2012) which suggests
that questions of national interest are likely to continue to prove their importance in shapinginfrastructure siting conflicts. The interaction of the planning system with the assumptions
and storylines (such as the centrality of risk management to governance, and the priority of
energy security) through which governance is framed by the executive emerges as a key
theme for further research. It is through these interactions that opportunity structures for
effective, i.e. substantive participation will be shaped. The implementation of effective
participatory governance faces serious obstacles, both in continued efforts to streamline
planning systems (as per the 2008 Act), and in the potential for conflicts between the private
obligations of private companies like NG and their public duties. Issues of commercial
confidentiality, for example, particularly with respect to supply contracts, proved an obstacle
to campaigners in the SWGP case seeking information about the case for national need.
With such issues in mind, it is not enough to call for early and wider consultation. It isnecessary to recognise that the evolution of governance under neoliberalism requires forms of
engagement which address both the redistribution of power to which this evolution has led,
and the continuing possibility of conflicts between private commercial interests and
community interests over how the national interest, and its relation to planning, is shaped.
References
Adam B and Groves C, 2007, Future Matters: Action, Knowledge, Ethics (Brill, Leiden)
BBC News, 2006, New pipeline 'will aid industry', 17 July,
http://news.bbc.co.uk/1/hi/wales/south_west/5181336.stm
Barker K 2006,Barker Review of Land Use Planning. (HM Treasury, London).
Barnett J, Burningham K, Walker G and CassN 2012, Imagined publics and engagement
around renewable energy technologies in the UK. Public Understanding of Science
21(1), pp. 36-50.
Bond A, Palerm J and Haigh P 2004, Public participation in EIA of nuclear power plant
decommissioning projects: a case study analysisEnvironmental Impact Assessment
Review24(6), pp 617-641
Brecon Beacons National Park Authority (BBNPA), 2005a Response to South Wales and
the West Reinforcement Pipelines Route Corridor Investigation Study (RCIS) Report
(BBNPA, Brecon)
Brecon Beacons National Park Authority (BBNPA), 2005b, Statement of Objection by the
Brecon Beacons National Park Authority to the Department of Trade and Industry(BBNPA, Brecon)
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
17/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 17
Bryman A, and Bell E (2007)Business Research Methods (Oxford University Press, Oxford)
Cotton M and Devine-Wright P, 2010a, Making electricity networks "visible": Industry
actor representations of "publics" and public engagement in infrastructure planning
Public Understanding of Science27(1), pp 17-35
Cotton M and Devine-Wright P 2010b, NIMBYism and community consultation in
electricity transmission network planning in Renewable energy and the public: from
NIMBY to participation ed. Devine-Wright P (London: Earthscan) pp. 115-130.
Cotton M and Devine-Wright P 2011, Discourses of energy infrastructure development: a
Q-method study of electricity transmission line siting in the UKEnvironment and
Planning A43(4), pp 942-960
Cotton M and Devine-Wright P 2012, Putting pylons into place: a UK case study of public
perspectives on the impacts of high voltage overhead transmission linesJournal of
Environmental Planning and Management, forthcoming.
Cowell R 2004, Market regulation and planning action: burying the impact of electricity
networks?Planning Theory and Practice5, pp 307-325
Cowell R 2012, The Greenest Government ever? Planning and sustainability in England
after the May 2010 elections, Planning Practice and Research, forthcoming.Cowell R and Owens S, 1998, Suitable Locations: Equity and Sustainability in the Minerals
Planning ProcessRegional Studies32(9), pp 797-811
Cowell R and Owens S, 2006, Governing space: planning reform and the politics of
sustainabilityEnvironment and Planning C: Government and Policy24, pp 403-421
Cowell R and Owens S 2010, Revisiting ... Governing space: planning reform and the
politics of sustainabilityEnvironment and Planning C: Government and Policy
28(6), pp. 952-957.
Cowell R and Owens S, 2011,Land and Limits: Interpreting Sustainability in the Planning
Process 2nd edition (Routledge, London)
Defeuilley C, 1999, Competition and Public Service Obligations: Regulatory Rules and
Industries GamesAnnals of Public and Cooperative Economics70(1), pp 25-48Department for Business Innovation and Skills (BIS), 2009,Joint Energy Security Of Supply
Working Group (JESS) http://www.berr.gov.uk/energy/reliability/security-
supply/jess/index.html
Department of Energy and Climate Change (DECC) 2009,Draft Overarching National
Policy Statement for Energy (EN-1) (The Stationery Office, London)
Department of Trade and Industry (DTI), 2003, Our Energy Future - Creating a Low Carbon
Economy (The Stationery Office, Norwich)
Department of Trade and Industry (DTI), 2007, The Public Gas Transporter Pipe-Line Works
(Environmental Impact Assessment) Regulations 1999, Regulation 14: Felindre to
Tirley Pipe-Line (The Stationery Office, London)
Freudenburg W R and Pastor S K 1992, NIMBYs and LULUs: Stalking the SyndromesJournal of Social Issues48(4), pp. 39-61.
Gamble D J, 1978, The Berger Inquiry: An Impact Assessment ProcessScience199(4332),
pp 946-951
Gross C 2007, Community perspectives of wind energy in Australia: The application of a
justice and community fairness framework to increase social acceptanceEnergy
Policy35(5), pp 2727-2736.
Guy S, Graham S, and Marvin S, 1996, Privatized Utilities and Regional Governance: The
New Regional Managers?Regional Studies30(8), pp 733-739
Guy S, Graham S, and Marvin S, 1997, Splintering Networks: Cities and Technical
Networks in 1990s BritainUrban Studies34(2), pp 191-216
Guy S, Graham S, and Marvin S, 1999, Cities, regions and privatised utilitiesProgress in
Planning51, pp 91-169
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
18/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 18
Hall D and Lobina E, 2004, Private and public interests in water and energyNatural
Resources Forum28(4), pp 268-277
Hardy M and Ritchie H, 2010, Energy Distribution and the New Politics of Regulation
paper for Science & Technology Policy Research Conference: "Energy transitions in
an interdependent world: what and where are the future social science research
agendas?" University of Sussex 25-26 February,
http://www.neopanora.com/en/sustainable-development/115.html
Harris J, 2007, How green was my valleyThe Guardian 2 April,
http://www.guardian.co.uk/environment/2007/apr/27/energy.activists
House of Commons Energy and Climate Change Committee (ECCC) 2011, The revised draft
National Policy Statements on energy (The Stationery Office, London)
Kellet J E, 1993, Role of the town and country planning system in controlling development
of electricity generating installationsIEE Proceedings A140(1), pp 94-99
Le-Las W and Shirley E 2012, Does the planning system need a teaparty?Journal of
Planning & Environment Law3, pp. 239-243.
Manners G, 1997, Gas market liberalization in Britain: Some geographical observations
Regional Studies31(3), p 296Marshall T, 2010, Planning major infrastructure sectors in the UK during recent decades
Oxford Brookes School of the Built Environment Working Paper,
http://planning.brookes.ac.uk/projects/resources/engsectoralConclusions.pdf
Marshall T, 2011, Reforming the process for infrastructure planning in the UK/England
1990-2010Town Planning Review82(6), forthcoming
Marsh D and Hall M 2007, The British Political Tradition: Explaining the Fate of New
Labour's Constitutional Reform AgendaBritish Politics2(2), pp. 215-238.
McCollum D, 2006,AGI risk assessment - Corse PRISubmission to planning inquiry,
application reference P0624/06/FUL, Forest of Dean District Council
Moran M, 2007, The British Regulatory State: High Modernism and Hyper-Innovation
(Oxford University Press, Oxford)National Grid, 2005, Gas Transportation Ten Year Statement 2005 (National Grid, Warwick)
Office of the Deputy Prime Minister (ODPM), 2004, Planning Policy Statement 7:
sustainable development in rural areas (HMSO, London)
Owens S, 2004, Siting, sustainable development and social prioritiesJournal of Risk
Research7(2), pp 101-114
Plummer M and Mellish R, 2007, Secretary of State's Decision in respect of Corse gas
pressure reduction installation, application reference P0624/06/FUL, Forest of Dean
District Council
Rose N, 1999, The powers of freedom: reframing political thought(Cambridge University
Press, Cambridge)
Rough E 2011, Policy learning through public inquiries? The case of UK nuclear energypolicy 1955-61Environment and Planning C: Government and Policy29(1), pp. 24-
45.
RPS Planning, 2007, Full Planning Application to Install Natural Gas Pressure Reduction
Installation at Land Adjacent to Lime Street and Moorend Road off B4211, Corse,
Gloucestershire: Statement of Case on Behalf of National Grid, application
reference P0624/06/FUL, Forest of Dean District Council
Sadler D 2001, The political economy and regional implications of energy policy in Britain
in the 1990sEnvironment and Planning C: Government and Policy19(1), pp. 3-28.
Scott, J C, 1998, Seeing like a state: how certain schemes to improve the human condition
have failed(Yale University Press, New Haven)
8/3/2019 Fighting the Pipe: neo-liberal governance and barriers to effective community participation in energy infrastructure
19/19
DRAFT VERSION DO NOT QUOTE WITHOUT PERMISSION 19
Scott P, Miller C and Wood C, 1998, Planning and pollution: an unusual perspective on
central - local relationsEnvironment and Planning C: Government and Policy16(5),
pp 529-542
Tester D, 2010,Report to the Secretary of State for Communities and Local Government and
to the Secretary of State for Energy & Climate Change: Town and Country Planning
Act 1990 Appeal by National Grid Gas plc, Tirley Gas Pressure Reduction
Installation, Tewkesbury Borough Council (Planning Inspectorate, Bristol)
Walker G 2009, Beyond Distribution and Proximity: Exploring the Multiple Spatialities of
Environmental JusticeAntipode41(4), pp. 614-636.
Walls, J, O'Riordan, T, Horlick-Jones T, Niewhner, J, 2005, The meta-governance of risk
and new technologies: GM crops and mobile telephonesJournal of Risk Research
8(7-8), pp 635-661
Ward D, 2001, Stakeholder involvement in transport planning: participation and power
Impact Assessment and Project Appraisal19, pp 119-130
Winstone R, Bolton P and Gore D 2007,Energy Security (House of Commons Library,
London)
Woolley O 2010, Trouble on the Horizon? Addressing Place-based Values in Planning forOffshore Wind EnergyJournal of Environmental Law22(2), pp. 223-250.