Presenter 3: Gilles Bazabas Bronx Community College – CUNY Associate’s Degree in Applied Sciences, December 2013 Major: Electronic Engineering Technology

Field Operations Internship Presentation_Gilles Bazabas

Embed Size (px)

Citation preview

Page 1: Field Operations Internship Presentation_Gilles Bazabas

Presenter 3:Gilles Bazabas

Bronx Community College – CUNYAssociate’s Degree in Applied Sciences, December 2013Major: Electronic Engineering Technology

Page 2: Field Operations Internship Presentation_Gilles Bazabas

Introduction

2

Charlie OliverTechnician

Mentor

Gilles Bazabas

StudentField

Operations Intern

Anthony deJesus

Field Service Manager

Line Manager

Page 3: Field Operations Internship Presentation_Gilles Bazabas

Test And Inspect Overview:• Test operation of all devices that report to the Fire Alarm

Control Panel (FACP).• Check for their good operation, maintenance, and cleanings .• List and report all devices on maintenance ticket for office

and tenants records.• File smoke detectors maintenance Log Book that stays on

the premises.

Types of Services Provided:• Test and Inspect• Installation / Service Calls• Programming

Field Operations Department

3

Page 4: Field Operations Internship Presentation_Gilles Bazabas

List of devices to check throughout building: Smoke Detectors (SD) Duct Detectors (DD) Heat Detectors (HD) Manual Pull Stations (MPS) Water flow sensors (WF) Tamper Switches (TS) Warden Phones (WPH) Beam Detectors (BD)

Field Operations Department

4

Page 5: Field Operations Internship Presentation_Gilles Bazabas

Test and Inspect

Procedure Request for system to be put OFFLINE (FSD, BE,

Security, Technician) Call to Central Station (Statewide, AFA,

Central monitoring, etc.) Ask to be OFFLINE for four hours, or height

hours

Check for panel condition upon arrival at FACP Report on maintenance ticket Active points

and Disable points (Ap 0000, Dp 0000).

Si lent Test / L ive Test / Visual Test.

5

Page 6: Field Operations Internship Presentation_Gilles Bazabas

Test and Inspect

Silent Test

Put panel on TEST mode (IO-64, IO-500, EST-2, EST-3), or ensure all Audible and Visual devices are DISCONNECTED (Quick Start, NAC disconnect panels).

Disable Devices or Actions (Fan Shut Down, Elev. Recall, Door Release).

Check all devices when panel is on TEST and all Actions are DISABLED.

Write displayed message with last four numbers of device on maintenance ticket.

Reset panel and make sure all device are cleared, so won’t activate accidentally.

Take the panel OFF TEST, and ENABLE all Actions previously disabled.

Close ticket after made sure panel is in same or better condition at departure.

Si lent Test / L ive Test / Visual Test.

6

Page 7: Field Operations Internship Presentation_Gilles Bazabas

Test and InspectSi lent Test / L ive Test / Visual Test.

Live TestWhen Silent Test completed and panel put Off Test: Make announcement through Speakerphone. Activate any device that will put the building on Alarm. Check on every floor that all output devices of fire alarm system

are operational (Speaker/Strobes, Horn/strobes, Bells, Door release, Fan Shut Down, Elev. Recall) Acknowledge the Alarm message on FACP, then reset the FACP

to clear Alarm.

7

Page 8: Field Operations Internship Presentation_Gilles Bazabas

Test and InspectSilent Test / Live Test / Visual Test / Supervisory Test / Sensitivity Test.

Visual Test

No need to request account to be put Offline. Walk through all floors of the building and check if devices are in

good condition. Report with a check on maintenance ticket all devices that pass

visual inspection.

Supervisory Test

Tamper Pump Run/Fail Pressure High/Low Phase Reversal

8

Page 9: Field Operations Internship Presentation_Gilles Bazabas

Test And Inspect In PicturesCentral Station

Call to request system to be put offline Communicator Calls Fire Department if system not

offline

Panels (FACPs)

EST-2 EST-3Microphone

Quick Start (Disconnect NAC)

IO-64/IO-500 (Test Mode)

Commercial Fire

9

Page 10: Field Operations Internship Presentation_Gilles Bazabas

Conclusion

10

Recommendation to make the program better

Excellent program where intern can learn from the field to become good technicians.

A rotation between all departments of the Field Operation to have a better understanding of all parts of technical service.

Page 11: Field Operations Internship Presentation_Gilles Bazabas

Conclusion

What I’ve learned through this internship

The understanding of Fire alarm system. The need of effective communication. The necessity to pay attention to small details The overall qualities needed by a technician

11

Page 12: Field Operations Internship Presentation_Gilles Bazabas

Questions and Answers

Thanks to my mentor and to all the staff at High Rise for having given me this opportunity to succeed in this internship, and for having listened to my presentation.I hope you appreciated the time I dedicated to learning within your company.

If you have any questions, please feel free to ask me some.

With my Best regards,

Sincerely,

Gilles Bazabas