  • 8/12/2019 Fertiliers Estimates

    1/62

    Description No'S Length Breadth Dep/H

    t Qty Units Rate/unit AMOUNT

    in feet in feet in feet in cft/sft

    FOUNDATION WORK

    2 Earth work excavation for column

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    21224.00 Cub.Ft 6.00 127344.00

    3 P.C.C. 1:4:8 for below columns

    FOOTING ( F1 ) 18 12 11.5 0.32 794.88

    FOOTING ( F2 ) 4 6.5 6.5 0.36 60.84

    855.72 Cub.Ft 75.00 64179.00

    4 Column footings (in 1: 1 1/2 : 3 prop)

    FOOTING ( F1 ) 18 11 10.5 2.75 5717.25

    FOOTING ( F2 ) 4 6 6 2 288.00

    6005.25 Cub.Ft 102 612535.50

    5 Columns in RCC (in 1: 1 1/2 : 3 prop)

    COLUMN ( C1 ) 18 2 2.5 37 3330.00

    COLUMN ( C2 ) 4 0.75 0.45 37 49.95

    3379.95 Cub.Ft 132 446153.40

    6 Plinth beams in RCC (in 1:2:4 prop)

    1 547 0.75 1 410.25

    410.25 Cub.Ft 125 51281.25

    7 Refilling with Good gravel

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    DEDUCTION P.C.C. 18 12 11.5 0.32 -794.88

    COLUMN FOOTING 18 11 10.5 2.75 -5717.25

    COLUMN 18 2 2.5 5 -450.00

    12909.87 Cub.Ft

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    DEDUCTION P.C.C. 4 6.5 6.5 0.36 -60.84

    COLUMN FOOTING 4 6 6 2 -288.00

    COLUMN 4 0.75 0.45 5 -6.75

    ESTIMATION FOR PROPOSED FERTILIZERS ASSOCIATION BUILDING AT WARANGAL

  • 8/12/2019 Fertiliers Estimates

    2/62

    Description No'S Length Breadth Dep/H

    t Qty Units Rate/unit AMOUNT

    GROUND FLOOR

    18 Superstructure with first class table

    mounted brick (1:4CM)

    2 39.25 0.75 9.5 559.31

    3 31.75 0.75 9.5 678.66

    3 11.5 0.36 9.5 117.99

    Deductions

    Doors 3 3 0.75 7 -47.25

    1 6 0.75 7 -31.50

    2 2.5 0.36 7 -12.60windows 6 4.5 0.75 4.5 -91.13

    Ventilator 1 6 0.75 2 -9.00

    1164.48 Cub.Ft 72 83842.83

    19 Beams at slab level in P.T.

    (in 1:1:3 prop)

    9 51 4 1 1836.00

    1836.00 Cub.Ft 131 240516.00

    Beams at slab level in R.c.c.(in 1:2:4 prop) 1 371 0.75 1 278.25

    278.25 Cub.Ft 131 36450.75

    20 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    1969.11 Cub.Ft 131 257953.41

    22 Plastering in cement mortar in 2 coats

    (1st 1:6 CM & 2nd 1:4CM)

    INSIDE

    1 324.5 - 9.5 3082.75

    Deductions

    Doors 3 3 - 7 -63.00

    1 6 - 7 -42.00

    2 2.5 - 7 -35.00

    2942.75 Sq.Ft

    OUTSIDE 1 168 - 9.5 1596.00

    windows 12 4.5 - 4.5 -243.00

    Ventilator 2 6 - 2 -24.00

    1329.00 Sq.Ft

  • 8/12/2019 Fertiliers Estimates

    3/62

    Description No'S Length Breadth Dep/H

    t Qty Units Rate/unit AMOUNT

    FIRST FLOOR

    29 Superstructure with first class table 2 97 0.75 9.5 1382.25

    mounted brick (4 1/2" thick, 1:4CM) 2 39.25 0.75 9.5 559.312 15.25 0.375 9.5 108.66

    Deductions

    Shutters 18 6 0.75 8 -648.00

    Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    1357.22 Cub.Ft 72 97719.75

    19 Beams at slab level in P.T.

    (in 1:2:4 prop)

    9 51 4 1 1836.001836.00 Cub.Ft 131 240516.00

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75 1 278.25

    278.25 Cub.Ft 131 36450.75

    20 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    1969.11 Cub.Ft 131 257953.41

    22 Plastering in cement mortar in 2 coats

    (1st 1:6 CM & 2nd 1:4CM)

    INSIDE

    1 404 - 9.5 3838.00

    Deductions

    Doors 4 3 - 7 -84.00

    2 6 - 7 -84.00

    4 2.5 - 7 -70.00

    3600.00 Sq.Ft

    OUTSIDE 1 283 - 9.5 2688.50

    windows 36 4.5 - 4.5 -729.00

    Ventilator 4 3 - 2 -24.00

    1935.50 Sq.Ft

    Ceiling 1 107 - 50 5350.00

    16 50 - 1 800.00

    8085.50 Sq.Ft 13 105111.50

  • 8/12/2019 Fertiliers Estimates

    4/62

    Description No'S Length Breadth Dep/H

    t Qty Units Rate/unit AMOUNT

    SECOND FLOOR

    29 Superstructure with first class table 2 97 0.75 9.5 1382.25mounted brick (9" thick, 1:4CM) 2 39.25 0.75 9.5 559.31

    Deductions

    Shutters 18 6 0.75 8 -648.00

    Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    1248.56 Cub.Ft 72 89896.50

    19 Beams at slab level in P.T.

    (in 1:2:4 prop)9 51 4 1 1836.00

    1836.00 Cub.Ft 131 240516.00

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75 1 278.25

    278.25 Cub.Ft 131 36450.75

    20 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    1969.11 Cub.Ft 131 257953.41

    22Plastering in cement mortar in 2 coats

    (1st 1:6 CM & 2nd 1:4CM)

    INSIDE

    1 404 - 9.5 3838.00

    Deductions

    Doors 4 3 - 7 -84.002 6 - 7 -84.00

    4 2.5 - 7 -70.00

    3600.00 Sq.Ft

    OUTSIDE 1 276 - 9.5 2622.00

    windows 36 4.5 - 4.5 -729.00

    Ventilator 4 3 - 2 -24.00

    1869.00 Sq.Ft

    Ceiling 1 107 - 50 5350.00

    16 50 - 1 800.00

    6126.00 Sq.Ft 79638.00

  • 8/12/2019 Fertiliers Estimates

    5/62

    Description No'S Length Breadth Dep/H

    t Qty Units Rate/unit AMOUNT

    73 Electrification - including transformer,

    panel boards, wiring, switches, all of

    reputed brands, all labor charges forfixing, lead and lift, etc., complete

    finished works.

    Lumsum

    373998.89

    74 Sanitary and Plumbing Works, including

    sanitary pipelines, fixtures, plumbing

    lines, faucets, all labor charges for fixing,

    lead and lift, etc., complete finished

    works.

    Lumsum

    140249.58

    .75 Contingencies - unforeseen conditions,

    labor insurance, price variation, theft of

    materials etc..

    Lumsum

    93499.72

    GRAND TOTAL 5282734.27

    FOURTYSIX LAKHS SIXTY ONE THOUSAND EIGHT SEVENTY TWO RUPEES ONLY

    Lumsum @ 8%

    Lumsum @ 3%

    Lumsum @ 2%

  • 8/12/2019 Fertiliers Estimates

    6/62

    Description No'S Length Breadth

    in feet in feet

    FOUNDATION WORK

    2 Earth work excavation for column

    FOOTING ( F1 ) 18 12 11.5

    FOOTING ( F2 ) 4 6.5 6.5

    3 P.C.C. 1:4:8 for below columns

    FOOTING ( F1 ) 18 12 11.5

    FOOTING ( F2 ) 4 6.5 6.5

    4 Column footings (in 1: 1 1/2 : 3 prop)

    FOOTING ( F1 ) 18 11 10.5

    FOOTING ( F2 ) 4 6 6

    5 Columns in RCC (in 1: 1 1/2 : 3 prop)

    COLUMN ( C1 ) 18 2 2.5

    COLUMN ( C2 ) 4 0.75 0.45

    6 Plinth beams in RCC (in 1:2:4 prop)1 547 0.75

    7 Refilling with Good gravel

    ESTIMATION FOR PROPOSED FERTILIZERS ASSOCIATION

  • 8/12/2019 Fertiliers Estimates

    7/62

    FOOTING ( F2 ) 4 6.5 6.5

    DEDUCTION P.C.C. 4 6.5 6.5

    COLUMN FOOTING 4 6 6

    COLUMN 4 0.75 0.45

    GROUND FLOOR

    18 Superstructure with first class table

    mounted brick (1:4CM)

    2 39.25 0.753 31.75 0.75

    3 11.5 0.36

    Deductions

    Doors 3 3 0.75

    1 6 0.75

    2 2.5 0.36

    windows 6 4.5 0.75Ventilator 1 6 0.75

    19 Beams at slab level in P.T.

    (in 1:1:3 prop)

    9 51 4

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75

  • 8/12/2019 Fertiliers Estimates

    8/62

    INSIDE

    1 324.5 -

    Deductions

    Doors 3 3 -

    1 6 -

    2 2.5 -

    OUTSIDE 1 168 -

    windows 12 4.5 -

    Ventilator 2 6 -

    Ceiling 1 107 -

    16 50 -

    23 Flooring with 2'-0" X 2'-0" Vitrified Tiles 1 1 1634

    Flooring with 1'-0" X 1'-0" paving Tiles 1 1 3688

    25 apply two coats of Birla type Wall putty

    in interiors

    25 Painting of interior with emulsion in

    2 coats and 1 primer coat

    Quantity same as internal plastering - - -

    26 Painting of exterior in snowcem

    Quantity same as out side plastering - - -

  • 8/12/2019 Fertiliers Estimates

    9/62

    Ventilator 2 3 0.75

    DOOR 1 6 0.75

    19 Beams at slab level in P.T.(in 1:2:4 prop)

    9 51 4

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75

    20 Slab in P.T. (in 1:2:4 prop) 1 107.25 51

    22Plastering in cement mortar in 2 coats(1st 1:6 CM & 2nd 1:4CM)

    INSIDE

    1 404 -

    Deductions

    Doors 4 3 -

    2 6 -

    4 2.5 -

    OUTSIDE 1 283 -

    windows 36 4.5 -

    Ventilator 4 3 -

    Ceiling 1 107 -

  • 8/12/2019 Fertiliers Estimates

    10/62

    25 apply two coats of Birla type Wall putty

    in interiors

    25 Painting of interior with emulsion in2 coats and 1 primer coat

    Quantity same as internal plastering - - -

    26 Painting of exterior in snowcem

    Quantity same as out side plastering - - -

    STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN1 246.00 1

    SECOND FLOOR

    29 Superstructure with first class table 2 97 0.75

    mounted brick (9" thick, 1:4CM) 2 39.25 0.75

    Deductions

    Shutters 18 6 0.75

    Ventilator 2 3 0.75

    DOOR 1 6 0.75

    19 Beams at slab level in P.T.(in 1:2:4 prop)

    9 51 4

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75

    20 Slab in P.T. (in 1:2:4 prop) 1 107.25 51

  • 8/12/2019 Fertiliers Estimates

    11/62

    Doors 4 3 -

    2 6 -

    4 2.5 -

    OUTSIDE 1 276 -

    windows 36 4.5 -

    Ventilator 4 3 -

    Ceiling 1 107 -

    16 50 -

    23 Flooring with 2'-0" X 2'-0" Vitrified Tiles 1 1 5446

    25 apply two coats of Birla type Wall putty

    in interiors

    25 Painting of interior with emulsion in

    2 coats and 1 primer coatQuantity same as internal plastering - - -

    26 Painting of exterior in snowcem

    Quantity same as out side plastering - - -

    69 Steel Reinforcement Including Bending

    & Placement

    1 1 16371

    71elevation works as per architects design

    ( stone, acp, and texture finish)1 1 107

  • 8/12/2019 Fertiliers Estimates

    12/62

    73 Electrification - including transformer,

    panel boards, wiring, switches, all of

    reputed brands, all labor charges for

    fixing, lead and lift, etc., complete

    finished works.

    74

    Sanitary and Plumbing Works, includingsanitary pipelines, fixtures, plumbing

    lines, faucets, all labor charges for fixing,

    lead and lift, etc., complete finished

    works.

    75 Contingencies - unforeseen conditions,

    labor insurance, price variation, theft ofmaterials etc..

    GRAND TOTAL

    FOURTYSIX LAKHS SIXTY ONE THOUSAND EIGHT SE

    TOTAL

    Lumsum @ 8%

    Lumsum @ 5%

    Lumsum @ 2%

  • 8/12/2019 Fertiliers Estimates

    13/62

    Dep/Ht Qty Units Rate/unit AMOUNT

    in feet in cft/sft

    8 19872.00

    8 1352.00

    21224.00 Cub.Ft 8.00 169792.00

    0.32 794.88

    0.36 60.84

    855.72 Cub.Ft 85.00 72736.20

    2.75 5717.25

    2 288.00

    6005.25 Cub.Ft150

    900787.50

    37 3330.00

    37 49.95

    3379.95 Cub.Ft 165 557691.75

    1 410.25

    410.25 Cub.Ft 160 65640.00

    UILDING AT WARANGAL

  • 8/12/2019 Fertiliers Estimates

    14/62

  • 8/12/2019 Fertiliers Estimates

    15/62

    9.5 3082.75

    7 -63.007 -42.00

    7 -35.00

    2942.75 Sq.Ft 21 61797.75

    9.5 1596.00

    4.5 -243.00

    2 -24.00

    1329.00 Sq.Ft 21 27909.00

    50 5350.00

    1 800.00

    7479.00 Sq.Ft 21 157059.00

    1634.00 70 114380.00

    3688.00 45 165960.00

    5322.00 Sq.Ft

    2942.75 Sq.Ft11

    32370.25

    - 2942.75 Sq.Ft 6 17656.50

    - 1329.00 Sq.Ft 9 11961.00

  • 8/12/2019 Fertiliers Estimates

    16/62

    2 -9.00

    8 -36.00

    1357.22 Cub.Ft 90 122149.69

    1 1836.00

    1836.00 Cub.Ft 170 312120.00

    1 278.25

    278.25 Cub.Ft 170 47302.50

    0.36 1969.11

    1969.11 Cub.Ft 170 334748.70

    9.5 3838.00

    7 -84.00

    7 -84.00

    7 -70.00

    3600.00 Sq.Ft 21 75600.00

    9.5 2688.50

    4.5 -729.00

    2 -24.00

    1935.50 Sq.Ft 21 40645.50

    50 5350.00

  • 8/12/2019 Fertiliers Estimates

    17/62

    3600.00 Sq.Ft11

    39600.00

    - 3600.00 Sq.Ft 6 21600.00

    - 1935.50 Sq.Ft 17419.50

    1 246.00 R.Ft 510 125460.00

    9.5 1382.25

    9.5 559.31

    8 -648.00

    2 -9.00

    8 -36.00

    1248.56 Cub.Ft 90 112370.63

    1 1836.00

    1836.00 Cub.Ft 170 312120.00

    1 278.25

    278.25 Cub.Ft 170 47302.50

    0.36 1969.11

    1969 11 Cub Ft 170 334748 70

  • 8/12/2019 Fertiliers Estimates

    18/62

    7 -84.00

    7 -84.00

    7 -70.00

    3600.00 Sq.Ft 21 75600.00

    9.5 2622.00

    4.5 -729.00

    2 -24.00

    1869.00 Sq.Ft 21 39249.00

    50 5350.00

    1 800.00

    6126.00 Sq.Ft 128646.00

    5446.00

    5446.00 Sq.Ft 70 381220.00

    3600.00 Sq.Ft11

    39600.00

    - 3600.00 Sq.Ft 6 21600.00

    - 1869.00 Sq.Ft 16821.00

    3 49113.00 K.g 50 2455650.00

    28 137.00 Sq.Ft 150 20550.00

  • 8/12/2019 Fertiliers Estimates

    19/62

    Lumsum

    747360.41

    Lumsum

    467100.26

    Lumsum

    186840.10

    10743305.91

    ENTY TWO RUPEES ONLY

    9342005.14

  • 8/12/2019 Fertiliers Estimates

    20/62

    Description No'S Length Breadth Dep/Ht Qty Units Rate/unit AMOUNT

    in feet in feet in feet in cft/sft in cft/sft

    SCHEDULE-A

    FOUNDATION WORK

    1

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    21224.00 Cub.Ft 8.00 169792.00

    2

    FOOTING ( F1 ) 18 12 11.5 0.32 794.88

    FOOTING ( F2 ) 4 6.5 6.5 0.36 60.84

    855.72 Cub.Ft 85.00 72736.20

    3

    FOOTING ( F1 ) 18 11 10.5 2.75 5717.25

    FOOTING ( F2 ) 4 6 6 2 288.00

    6005.25 Cub.Ft 150 900787.50

    ESTIMATION FOR PROPOSED FERTILIZERS ASSOCIATION BUILDING AT WARANGAL

    Earth work excavation for foundatins and depositing at site with an intial lead of 10 mts and lift of 2 mts in mixture ofgravel and soft disintegrated rock like shales ordinary gravel, stony earth and earth mixed with fair sized boulders

    including all operational, incidental, labour charges such as shoring, sheeting, planking shuttering etc comlete for

    finished item of work as per SS 302 & 303

    Vibrated plain cement concrete (1:4:8) proportion (cement) fine aggregate coarse aggregate for foundation using

    40mm size HBG Metal (SS.5) from approved quarry including cost and conveyanceof all materials like cement, sandcoarse aggregate water including machine mixing and vibrating charges, seneriage charges etc.to site including of all

    materials and all labour charges etc. complete. for finished item of work as per SS 405 of APSS for levelling course.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarryas per SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine

    aggregate and coarse aggregate water etc to site cost at seigniorage and all materials including centering shuttering,

    machine mix laying concrete vibrations, curing etc complete for finished item of work but excluding cost of steel at its

    for finished item of work.as per SS 403, but excluding cost of reinforcement steel and its fabrication charges for

    Column footings

  • 8/12/2019 Fertiliers Estimates

    21/62

    4

    COLUMN ( C1 ) 18 2 2.5 40 3600.00

    COLUMN ( C2 ) 4 0.75 0.45 40 54.00

    3654.00 Cub.Ft 165 602910.00

    5

    1 547 0.75 1 410.25

    410.25 Cub.Ft 160 65640.00

    6

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    DEDUCTION P.C.C. 18 12 11.5 0.32 -794.88

    COLUMN FOOTING 18 11 10.5 2.75 -5717.25

    COLUMN 18 2 2.5 5 -450.00

    12909.87 Cub.Ft

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    DEDUCTION P.C.C. 4 6.5 6.5 0.36 -60.84

    COLUMN FOOTING 4 6 6 2 -288.00

    COLUMN 4 0.75 0.45 5 -6.75

    996.41 Cub.Ft

    13906.28 Cub.Ft 8 111250.24

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry

    as per SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fineaggregate and coarse aggregate water etc to site cost at seigniorage and all materials including centering shuttering,

    machine mix laying concrete vibrations, curing etc complete for finished item of work but excluding cost of steel at its

    for finished item of work.as per SS 403, but excluding cost of reinforcement steel and its fabrication charges for

    Column

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarryas per SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine

    aggregate and coarse aggregate water etc to site cost at seigniorage and all materials including centering shuttering,

    machine mix laying concrete vibrations, curing etc complete for finished item of work but excluding cost of steel at its

    for finished item of work.as per SS 403, but excluding cost of reinforcement steel and its fabrication charges for

    Plinth beams.

    Refilling with excavated soils or other than expansive soils in foundations and plinth in 150 mm layers including

    watering and consolidation according to standard specifications, cost and conveyence of all materials and labour

    charges as directed complete for finished item of work as per SS 309 and 310 of APSS

  • 8/12/2019 Fertiliers Estimates

    22/62

    GROUND FLOOR

    7

    2 39.25 0.75 9.5 559.31

    3 31.75 0.75 9.5 678.66

    3 11.5 0.36 9.5 117.99

    Deductions

    Doors 3 3 0.75 8 -54.00

    1 6 0.75 8 -36.00

    2 2.5 0.36 8 -14.40

    windows 6 6 0.75 5.5 -148.50

    Ventilator 1 6 0.75 2 -9.00

    1094.06 Cub.Ft 98465.29

    8 Beams at slab level in P.T.

    (M 35 Prop. )

    9 51 4 1 1836.00

    1836.00 Cub.Ft 170 312120.00

    9

    1 371 0.75 1 278.25

    278.25 Cub.Ft 170 47302.50

    10 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    (M 35 Prop. )

    1969.11 Cub.Ft 170 334748.70

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and

    conveyance of all materials like cement sand bricks water etc to site cost of seigniorage charges and all materials

    and all mixing lifting charges and all labour charges etc complete for finished item of work APSS No: 504 & 501 for

    Superstructure in Ground floor.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry

    as per SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine

    aggregate and coarse aggregate water etc to site cost at seigniorage and all materials including centering shuttering,

    machine mix laying concrete vibrations, curing etc complete for finished item of work but excluding cost of steel at its

    for finished item of work.as per SS 403, but excluding cost of reinforcement steel and its fabrication charges for

    Beams

  • 8/12/2019 Fertiliers Estimates

    23/62

    11

    INSIDE

    1 324.5 - 9.5 3082.75

    Deductions

    Doors 3 3 - 8 -72.00

    1 6 - 8 -48.00

    2 2.5 - 8 -40.00

    2922.75 Sq.Ft 21 61377.75

    OUTSIDE 1 168 - 11 1848.00

    DEDUCTION

    windows 12 6 - 5.5 -396.00

    Ventilator 2 6 - 2 -24.00

    1428.00 Sq.Ft 29988.00

    12

    1 107 - 50 5350.00

    16 50 - 1 800.00

    7578.00 Sq.Ft 21 159138.00

    13

    2' X 2' Vitrified Tiles 1 1 1634 1634.00 Sq.Ft 70 114380.00

    14

    PAVING TILES 1'0" X1'0" 1 1 3688 3688.00 Sq.Ft 45 165960.00

    Flooring with PAVING TILESof 1st. Quality of size not exceeding 1'0" X1'0" , laid over C.C. Flooring bed set over 20

    mm thick C.M. (1:3) prop base coat and neat grey cement slurry of honey like consistency spread at the rate of 3.3

    kgs of cement per sqm and jointed with neat cement paste, including seignourage, cost and conveyance of all

    materials and water from approved sources to work site and all operational, incidental, labour charges such as mixing

    mortar, dressing, laying, lift charges, curring etc, complete for finished item of work as per SS.703, but excluding cost

    of C.C.bed.

    Ceiling Plastering 20mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in

    CM(1:4) prop with dubara sponge finishing including cost & conveyance of materials and water to work site

    seigniorage and all operational, incidental charges etc., complete for finished item.

    Plastering 12mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4)

    prop with dubara sponge finishing including cost & conveyance of materials and water to work site seigniorage and all

    operational, incidental, labour charges such as scaffolding, mixing mortor, lift charges, curing etc complete for

    finished item of work as per SS No.901 & 904

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop

    base coat and neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and

    jointed with neat cement paste, including seignourage, cost and conveyance of all materials and water from approved

    sources to work site and all operational, incidental, labour charges such as mixing mortar, dressing, laying, lift

    charges, curring etc, complete for finished item of work as per SS.703, but excluding cost of C.C.bed.

  • 8/12/2019 Fertiliers Estimates

    24/62

    15

    2922.75 Sq.Ft 17 49686.75

    17

    Painting of exterior in snowcem

    Quantity same as out side plastering - - - - 1428.00 Sq.Ft 15 21420.00

    FIRST FLOOR

    18

    Superstructure with first class table 2 97 0.75 12.75 1855.13

    mounted brick (4 1/2" thick, 1:4CM) 2 39.25 0.75 12.75 750.66

    2 15.25 0.375 12.75 145.83

    Deductions

    windows 18 6 0.75 8 -648.00Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    2058.61 Cub.Ft 90 185274.84

    19 Beams at slab level in P.T. ( M35 )

    9 51 4 1 1836.00

    1836.00 Cub.Ft 170 312120.00

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved

    brand and shade over the base coat of approved white cement primer making three-coats in all to give an even

    shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, all

    operational, incidental charges including cost of brushes and all labour charges etc., complete for finished item of

    work as per SS911

    Providing Painting to new walls with two coats of Emulsion wall Putty with two coats of Oil bound distemper of

    approved brand and shade over the base coat of appropriate primer of approved brand making 3-coats in all to give

    an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powedered materials,

    including all operational, incidental charges including cost of brushes and all labour charges etc., complete for

    finished item of work as per SS911

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and

    conveyance of all materials like cement sand bricks water etc to site cost of seigniorage charges and all materials

    and all mixing lifting charges and all labour charges etc complete for finished item of work APSS No: 504 & 501 for

    Superstructure in Ground floor.

  • 8/12/2019 Fertiliers Estimates

    25/62

  • 8/12/2019 Fertiliers Estimates

    26/62

    24

    1 1 5446 5446.00

    5446.00 Sq.Ft 70 381220.00

    25

    Quantity same as in side plastering 4879.00 Sq.Ft 17 82943.00

    27

    Quantity same as out side plastering - - - - 2750.00 Sq.Ft 15 41250.00

    STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN1 246.00 1 1 246.00 R.Ft 510 125460.00

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop

    base coat and neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and

    jointed with neat cement paste, including seignourage, cost and conveyance of all materials and water from approved

    sources to work site and all operational, incidental, labour charges such as mixing mortar, dressing, laying, lift

    charges, curring etc, complete for finished item of work as per SS.703, but excluding cost of C.C.bed.

    Providing Painting to new walls with two coats of emuision wall Putty with two coats of Oil bound distemper of

    approved brand and shade over the base coat of appropriate primer of approved brand making 3-coats in all to give

    an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powedered materials,

    including all operational, incidental charges including cost of brushes and all labour charges etc., complete for

    finished item of work as per SS911

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved

    brand and shade over the base coat of approved white cement primer making three-coats in all to give an even

    shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, all

    operational, incidental charges including cost of brushes and all labour charges etc., complete for finished item of

    work as per SS911

  • 8/12/2019 Fertiliers Estimates

    27/62

    SECOND FLOOR

    28

    Superstructure with first class table 2 97 0.75 9.5 1382.25mounted brick (9" thick, 1:4CM) 2 39.25 0.75 9.5 559.31

    Deductions

    WINDOWS 18 6 0.75 5.5 -445.50

    Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    1451.06 Cub.Ft 90 130595.63

    29 Beams at slab level in P.T. ( M35 )9 51 4 1 1836.00

    1836.00 Cub.Ft 170 312120.00

    30

    (in 1:1:3 prop) 1 371 0.75 1 278.25

    278.25 Cub.Ft 170 47302.50

    31 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    1969.11 Cub.Ft 170 334748.70

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and

    conveyance of all materials like cement sand bricks water etc to site cost of seigniorage charges and all materials

    and all mixing lifting charges and all labour charges etc complete for finished item of work APSS No: 504 & 501 for

    Superstructure in Ground floor.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry

    as per SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine

    aggregate and coarse aggregate water etc to site cost at seigniorage and all materials including centering shuttering,

    machine mix laying concrete vibrations, curing etc complete for finished item of work but excluding cost of steel at its

    for finished item of work.as per SS 403, but excluding cost of reinforcement steel and its fabrication charges for

    Beams

  • 8/12/2019 Fertiliers Estimates

    28/62

    32

    INSIDE

    1 404 - 9.5 3838.00

    Deductions

    Doors 4 3 - 8 -96.002 6 - 8 -96.00

    4 2.5 - 8 -80.00

    3566.00 Sq.Ft 21 74886.00

    OUTSIDE 1 276 - 9.5 2622.00

    Deductions

    windows 36 6 - 5.5 -1188.00

    Ventilator 4 3 - 2 -24.00

    1410.00 Sq.Ft 21 29610.00

    33

    Ceiling 1 107 - 50 5350.00

    16 50 - 1 800.00

    6126.00 Sq.Ft 21 128646.00

    34

    Flooring with 2'-0" X 2'-0" Vitrified Tiles 1 1 5446 5446.00

    5446.00 Sq.Ft 70 381220.00

    Plastering 12mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4)

    prop with dubara sponge finishing including cost & conveyance of materials and water to work site seigniorage and all

    operational, incidental, labour charges such as scaffolding, mixing mortor, lift charges, curing etc complete for

    finished item of work as per SS No.901 & 904

    Ceiling Plastering 20mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in

    CM(1:4) prop with dubara sponge finishing including cost & conveyance of materials and water to work site

    seigniorage and all operational, incidental charges etc., complete for finished item.

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop

    base coat and neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and

    jointed with neat cement paste, including seignourage, cost and conveyance of all materials and water from approved

    sources to work site and all operational, incidental, labour charges such as mixing mortar, dressing, laying, lift

    charges, curring etc, complete for finished item of work as per SS.703, but excluding cost of C.C.bed.

  • 8/12/2019 Fertiliers Estimates

    29/62

    35

    apply two coats of Birla type Wall puttyin interiors

    3566.00 Sq.Ft 17 60622.00

    Quantity same as internal plastering

    37

    Quantity same as out side plastering - - - - 1410.00 Sq.Ft9

    12690.00

    38

    1 1 16371 3 49113.00 K.g 55 2701215.00

    39

    42 6 - 5.5 1386.00 S.Ft. 450 623700.00

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved

    brand and shade over the base coat of approved white cement primer making three-coats in all to give an even

    shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, all

    operational, incidental charges including cost of brushes and all labour charges etc., complete for finished item of

    work as per SS911

    Providing High Yield Strength deformed bars Fe 415 made of different diameters cutting and bending to required size

    and shape placing in position with cover blocks of approved materials and size, tying firmely with M.S. binding wire,

    forming grills for reinforcement work as per approved designed drawing to be supplied at the time of execution work

    excluding cost and conveyance of deformed bars, but including binding wire, cover blocks and all operational,

    labour charges such as cutting, bending placing in position, tying etc complete. for finished item of work. (Payment

    will be made on the basis of weight of fabricated deformed bars only)

    Supplying and fixing of fully glazed/ Partially glazed fenesta type window as per drawing, using 5mm thick glass

    including cost and conveyance to site of aluminium sections, glass,including labour charges for manufacturing

    windows, fixing in position using wooden blocks and sheet metal screws etc., complete for finished item and as per

    consultants.

    Providing Painting to new walls with two coats of emulsion wall Putty with two coats of Oil bound distemper of

    approved brand and shade over the base coat of appropriate primer of approved brand making 3-coats in all to give

    an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powedered materials,

    including all operational, incidental charges including cost of brushes and all labour charges etc., complete for

    finished item of work as per SS911

  • 8/12/2019 Fertiliers Estimates

    30/62

    40elevation works as per architects design

    ( stone, A.C.P. , and texture finish)

    1 1 107 28 2996.00 Sq.Ft

    deduction windows 16 6 - 5.5 -528.00 S.Ft.

    2468.00 S.Ft. 150 449400.00

    41Supplying and fixing of ELEVATOR of

    Jhonson brand10 PASSENGERS 1 1Each 800000.00 800000.00

    42

    STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN 1 246.00 1 1 246.00 R.Ft 350 86100.00

    43 Compound wall 1 1 396 396.00 R.Ft 800 316800.00

    SCHEDULE -B

    44

    Electrification - including transformer,

    panel boards, wiring, switches, all of

    reputed brands, all labor charges for

    fixing, lead and lift, etc., complete

    finished works.

    Lumsum

    933182.94

    45

    Sanitary and Plumbing Works, including

    sanitary pipelines, fixtures, plumbing

    lines, faucets, all labor charges forfixing, lead and lift, etc., complete

    finished works.

    Lumsum

    583239.34

    46

    Contingencies - unforeseen conditions,

    labor insurance, price variation, theft of

    materials etc..

    Lumsum233295.74

    47 Architect's fee Lumsum 233295.74

    TOTAL11664786.80

    Lumsum @ 8%

    Lumsum @ 5%

    Lumsum @ 2%

    Lumsum @ 2%

  • 8/12/2019 Fertiliers Estimates

    31/62

    GRAND TOTAL 13414504.82

    ONE CRORE THIRTYFOUR LAKHS FOURTEEN THOUSAND FIVE HUNDREN AND FIVE RUPEES ONLY

  • 8/12/2019 Fertiliers Estimates

    32/62

    NOTE :

    1BASE PRICE OF CEMENT =Rs. 250 / BAG.

    2 BASE PRICE OF STEEL =45/ KG.

  • 8/12/2019 Fertiliers Estimates

    33/62

    Description No'S Length Breadth Dep/Ht Qty

    in feet in feet in feet in cft/sft

    SCHEDULE-A

    FOUNDATION WORK

    1

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    21224.00

    2

    FOOTING ( F1 ) 18 12 11.5 0.32 794.88

    FOOTING ( F2 ) 4 6.5 6.5 0.36 60.84

    855.72

    3

    FOOTING ( F1 ) 18 11 10.5 2.75 5717.25

    FOOTING ( F2 ) 4 6 6 2 288.00

    6005.25

    4

    COLUMN ( C1 ) 18 2 2.5 40 3600.00

    COLUMN ( C2 ) 4 0.75 0.45 40 54.00

    3654.00

    ESTIMATION FOR PROPOSED FERTILIZERS ASSOCIATION BUILDING AT WARANGAL

    Earth work excavation for foundatins and depositing at site with an intial lead of 10 mts and lift of 2 mts in mixture of gravel

    and soft disintegrated rock like shales ordinary gravel, stony earth and earth mixed with fair sized boulders including all

    operational, incidental, labour charges such as shoring, sheeting, planking shuttering etc comlete for finished item of work

    as per SS 302 & 303

    Vibrated plain cement concrete (1:4:8) proportion (cement) fine aggregate coarse aggregate for foundation using 40mm

    size HBG Metal (SS.5) from approved quarry including cost and conveyanceof all materials like cement, sand coarse

    aggregate water including machine mixing and vibrating charges, seneriage charges etc.to site including of all materials

    and all labour charges etc. complete. for finished item of work as per SS 405 of APSS for levelling course. P.C.C.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per

    SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine aggregate and coarse

    aggregate water etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete

    vibrations, curing etc complete for finished item of work but excluding cost of steel at its for finished item of work.as per SS

    403, but excluding cost of reinforcement steel and its fabrication charges for Column footings

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per

    SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine aggregate and coarse

    aggregate water etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete

    vibrations, curing etc complete for finished item of work but excluding cost of steel at its for finished item of work.as per SS403, but excluding cost of reinforcement steel and its fabrication charges for Column

  • 8/12/2019 Fertiliers Estimates

    34/62

    6

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    DEDUCTION P.C.C. 18 12 11.5 0.32 -794.88

    COLUMN FOOTING 18 11 10.5 2.75 -5717.25

    COLUMN 18 2 2.5 5 -450.00

    12909.87

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    DEDUCTION P.C.C. 4 6.5 6.5 0.36 -60.84

    COLUMN FOOTING 4 6 6 2 -288.00

    COLUMN 4 0.75 0.45 5 -6.75

    996.41

    13906.28

    7

    8000.00 S.Ft 5 40000.00

    8

    1 107 51 0.15 818.55

    GROUND FLOOR

    9

    2 39.25 0.75 9.5 559.31

    3 31.75 0.75 9.5 678.66

    3 11.5 0.36 9.5 117.99

    Refilling with excavated soils or other than expansive soils in foundations and plinth in 150 mm layers including watering

    and consolidation according to standard specifications, cost and conveyence of all materials and labour charges as

    directed complete for finished item of work as per SS 309 and 310 of APSS

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and

    conveyance of all materials like cement sand bricks water etc to site cost of seigniorage charges and all materials and allmixing lifting charges and all labour charges etc complete for finished item of work APSS No: 504 & 501 for Superstructure

    in Ground floor.

    Filling with GRAVEL in basement & surrounding areas, brought from out side and dumping in layers not exceeding 15cmthick, consolidating each deposited layer by watering and ramming including all operational , incidental labour charges, hire

    charges of T & P etc., complete for finished item of work. (APSS no. - 309 & 310) GRAVEL FROM OUT SIDE

    Vibrated plain cement concrete (1:4:8) proportion (cement) fine aggregate coarse aggregate for foundation using 40mm

    size HBG Metal (SS.5) from approved quarry including cost and conveyanceof all materials like cement, sand coarse

    aggregate water including machine mixing and vibrating charges, seneriage charges etc.to site including of all materials

    and all labour charges etc. complete. for finished item of work as per SS 405 of APSS for levelling course. P.C.C ATBASEMENT LEVEL

  • 8/12/2019 Fertiliers Estimates

    35/62

  • 8/12/2019 Fertiliers Estimates

    36/62

    17

    2922.75

    18

    Painting of exterior in snowcem

    Quantity same as out side plastering - - - - 1428.00

    FIRST FLOOR

    19

    Superstructure with first class table 2 97 0.75 12.75 1855.13

    mounted brick (4 1/2" thick, 1:4CM) 2 39.25 0.75 12.75 750.66

    2 15.25 0.375 12.75 145.83

    Deductions

    windows 18 6 0.75 8 -648.00

    Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    2058.61

    20 Beams at slab level in P.T. ( M35 )

    9 51 4 1 1836.00

    1836.00

    21

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75 1 278.25

    278.25

    Providing Painting to new walls with two coats of Emulsion wall Putty with two coats of Oil bound distemper of approved

    brand and shade over the base coat of appropriate primer of approved brand making 3-coats in all to give an even shade

    after thoroughly brushing the surface to remove all dirt and remains of loose powedered materials, including all operational,

    incidental charges including cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved brand

    and shade over the base coat of approved white cement primer making three-coats in all to give an even shade after

    thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, all operational, incidental

    charges including cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and

    conveyance of all materials like cement sand bricks water etc to site cost of seigniorage charges and all materials and all

    mixing lifting charges and all labour charges etc complete for finished item of work APSS No: 504 & 501 for Superstructure

    in Ground floor.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per

    SS108 with necessary reinforcement including cost and conveyance of all materials like cement, fine aggregate and coarse

    aggregate water etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete

    vibrations, curing etc complete for finished item of work but excluding cost of steel at its for finished item of work.as per SS

    403, but excluding cost of reinforcement steel and its fabrication charges for Beams

  • 8/12/2019 Fertiliers Estimates

    37/62

    Ventilator 4 3 - 2 -24.00

    2750.00

  • 8/12/2019 Fertiliers Estimates

    38/62

    24

    Ceiling 1 107 - 50 5350.00

    16 50 - 1 800.00

    8900.00

    25

    1 1 5446 5446.00

    5446.00

    26

    Quantity same as in side plastering 4879.00

    27

    Quantity same as out side plastering - - - - 2750.00

    28STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN1 246.00 1 1 246.00

    SECOND FLOOR

    29

    Superstructure with first class table 2 97 0.75 9.5 1382.25

    mounted brick (9" thick, 1:4CM) 2 39.25 0.75 9.5 559.31

    Ceiling Plastering 20mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4)

    prop with dubara sponge finishing including cost & conveyance of materials and water to work site seigniorage and all

    operational, incidental charges etc., complete for finished item.

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop base

    coat and neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and jointed with

    neat cement paste, including seignourage, cost and conveyance of all materials and water from approved sources to work

    site and all operational, incidental, labour charges such as mixing mortar, dressing, laying, lift charges, curring etc,

    complete for finished item of work as per SS.703, but excluding cost of C.C.bed.

    Providing Painting to new walls with two coats of emuision wall Putty with two coats of Oil bound distemper of approved

    brand and shade over the base coat of appropriate primer of approved brand making 3-coats in all to give an even shade

    after thoroughly brushing the surface to remove all dirt and remains of loose powedered materials, including all operational,

    incidental charges including cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved brand

    and shade over the base coat of approved white cement primer making three-coats in all to give an even shade after

    thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, all operational, incidental

    charges including cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and

    conveyance of all materials like cement sand bricks water etc to site cost of seigniorage charges and all materials and all

    mixing lifting charges and all labour charges etc complete for finished item of work APSS No: 504 & 501 for Superstructure

    in Ground floor.

  • 8/12/2019 Fertiliers Estimates

    39/62

  • 8/12/2019 Fertiliers Estimates

    40/62

    38

    1 1 16371 3 49113.00

    39

    42 6 - 5.5 1386.00

    40elevation works as per architects design

    ( stone, A.C.P. , and texture finish)1 1 107 28 2996.00

    deduction windows 16 6 - 5.5 -528.00

    2468.00

    41Supplying and fixing of ELEVATOR of

    Jhonson brand10 PASSENGERS 1 1

    42STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN1 246.00 1 1 246.00

    43 Compound wall 1 1 396 396.00

    SCHEDULE -B

    44

    Electrification - including transformer,

    panel boards, wiring, switches, all ofreputed brands, all labor charges for

    fixing, lead and lift, etc., complete

    finished works.

    Sanitary and Plumbing Works including

    ONE CRORE SIXTEEN LAKHS SIXTY FOUR THOUSAND SEVEN HUNDRED AND EIGHTY SIX R

    Supplying and fixing of fully glazed/ Partially glazed fenesta type window as per drawing, using 5mm thick glass including

    cost and conveyance to site of aluminium sections, glass,including labour charges for manufacturing windows, fixing in

    position using wooden blocks and sheet metal screws etc., complete for finished item and as per consultants.

    TOTAL

    Lumsum @ 8%

    Providing High Yield Strength deformed bars Fe 415 made of different diameters cutting and bending to required size and

    shape placing in position with cover blocks of approved materials and size, tying firmely with M.S. binding wire, forming

    grills for reinforcement work as per approved designed drawing to be supplied at the time of execution work excluding

    cost and conveyance of deformed bars, but including binding wire, cover blocks and all operational, labour charges such

    as cutting, bending placing in position, tying etc complete. for finished item of work. (Payment will be made on the basis of

    weight of fabricated deformed bars only)

  • 8/12/2019 Fertiliers Estimates

    41/62

    1BASE PRICE OF CEMENT =Rs. 250 / BAG.

    2 BASE PRICE OF STEEL =45/ KG.

  • 8/12/2019 Fertiliers Estimates

    42/62

    Units Rate/unit AMOUNT

    in cft/sft

    Cub.Ft 10.00 212240.00

    Cub.Ft 95.00 81293.40

    Cub.Ft 165 990866.25

    Cub.Ft 175 639450.00

  • 8/12/2019 Fertiliers Estimates

    43/62

    Cub.Ft

    Cub.Ft

    Cub.Ft 10 139062.80

    Cub.Ft 12 480000.00

    Cub.Ft 95.00 77762.25

  • 8/12/2019 Fertiliers Estimates

    44/62

    Cub.Ft 185 51476.25

    Cub.Ft

    185

    364285.35

    Sq.Ft 21 61377.75

    Sq.Ft 21 29988.00

    Sq.Ft 21 159138.00

  • 8/12/2019 Fertiliers Estimates

    45/62

    Sq.Ft 17 49686.75

    Sq.Ft 15 21420.00

    Cub.Ft 95 195567.89

    Cub.Ft 185 339660.00

    Cub.Ft 185 51476.25

  • 8/12/2019 Fertiliers Estimates

    46/62

    Sq.Ft 21 57750.00

  • 8/12/2019 Fertiliers Estimates

    47/62

    Sq.Ft 21 186900.00

    Sq.Ft 70 381220.00

    Sq.Ft 17 82943.00

    Sq.Ft 15 41250.00

    R.Ft 510 125460.00

  • 8/12/2019 Fertiliers Estimates

    48/62

    Cub.Ft185

    364285.35

    Sq.Ft 21 74886.00

    Sq.Ft 21 29610.00

    Sq.Ft 21 128646.00

    Sq.Ft 70 381220.00

  • 8/12/2019 Fertiliers Estimates

    49/62

    K.g 55 2701215.00

    S.Ft. 450 623700.00

    Sq.Ft

    S.Ft.

    S.Ft. 150 449400.00

    Each 800000.00 800000.00

    R.Ft 350 86100.00

    R.Ft 800 316800.00

    Lumsum

    1011272.73

    UPEES ONLY

    12640909.16

  • 8/12/2019 Fertiliers Estimates

    50/62

    Description No'S Length Breadth Dep/Ht Qty Units Rate/unit AMOUNT

    in feet in feet in feet in cft/sft in cft/sft

    SCHEDULE-A

    FOUNDATION WORK

    1

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    21224.00 Cub.Ft 10.00 212240.00

    2

    FOOTING ( F1 ) 18 12 11.5 0.32 794.88

    FOOTING ( F2 ) 4 6.5 6.5 0.36 60.84

    855.72 Cub.Ft 95.00 81293.40

    3

    FOOTING ( F1 ) 18 11 10.5 2.75 5717.25

    FOOTING ( F2 ) 4 6 6 2 288.00

    6005.25 Cub.Ft 165 990866.25

    NAME OF WORK :- CONSTRUCTION OF NEW BUILDING FOR WARANGAL DIST. FERTILIZERS, PESTICIDES & SEEDS WELFARE ASSOCIATION AT WARANGAL.

    Earth work excavation for foundatins and depositing at site with an intial lead of 10 mts and lift of 2 mts in mixture of gravel and soft

    disintegrated rock like shales ordinary gravel, stony earth and earth mixed with fair sized boulders including all operational, incidental,

    labour charges such as shoring, sheeting, planking shuttering etc comlete for finished item of work as per SS 302 & 303

    Vibrated plain cement concrete (1:4:8) proportion (cement) fine aggregate coarse aggregate for foundation using 40mm size HBG

    Metal (SS.5) from approved quarry including cost and conveyanceof all materials l ike cement, sand coarse aggregate water including

    machine mixing and vibrating charges, seneriage charges etc.to site including of all materials and all labour charges etc. complete.for finished item of work as per SS 405 of APSS for levelling course. P.C.C.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per SS108

    with necessary reinforcement including cost and conveyance of all materials l ike cement, fine aggregate and coarse aggregate water

    etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete vibrations, curing etccomplete for finished item of work but excluding cost of steel at its for finished item of work.as per SS 403, but excluding cost of

    reinforcement steel and its fabrication charges for Column footings

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 50

  • 8/12/2019 Fertiliers Estimates

    51/62

    4

    COLUMN ( C1 ) 18 2 2.5 40 3600.00

    COLUMN ( C2 ) 4 0.75 0.45 40 54.00

    3654.00 Cub.Ft 175 639450.00

    5

    1 547 0.75 1 410.25

    410.25 Cub.Ft 175 71793.75

    6

    FOOTING ( F1 ) 18 12 11.5 8 19872.00

    DEDUCTION P.C.C. 18 12 11.5 0.32 -794.88

    COLUMN FOOTING 18 11 10.5 2.75 -5717.25

    COLUMN 18 2 2.5 5 -450.00

    12909.87 Cub.Ft

    FOOTING ( F2 ) 4 6.5 6.5 8 1352.00

    DEDUCTION P.C.C. 4 6.5 6.5 0.36 -60.84

    COLUMN FOOTING 4 6 6 2 -288.00

    COLUMN 4 0.75 0.45 5 -6.75

    996.41 Cub.Ft

    13906.28 Cub.Ft 10 139062.80

    Refilling with excavated soils or other than expansive soils in foundations and plinth in 150 mm layers including watering and

    consolidation according to standard specifications, cost and conveyence of all materials and labour charges as directed complete for

    finished item of work as per SS 309 and 310 of APSS

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per SS108

    with necessary reinforcement including cost and conveyance of all materials like cement, fine aggregate and coarse aggregate water

    etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete vibrations, curing etccomplete for finished item of work but excluding cost of steel at its for finished item of work.as per SS 403, but excluding cost of

    reinforcement steel and its fabrication charges for Plinth beams.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per SS108

    with necessary reinforcement including cost and conveyance of all materials like cement, fine aggregate and coarse aggregate water

    etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete vibrations, curing etccomplete for finished item of work but excluding cost of steel at its for finished item of work.as per SS 403, but excluding cost of

    reinforcement steel and its fabrication charges for Column

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 51

  • 8/12/2019 Fertiliers Estimates

    52/62

    7

    8000.00 S.Ft 5 40000.00 Cub.Ft 12 480000.00

    8

    1 107 51 0.15 818.55 Cub.Ft 95.00 77762.25

    Filling with GRAVEL in basement & surrounding areas, brought from out side and dumping in layers not exceeding 15cm thick,

    consolidating each deposited layer by watering and ramming including all operational , incidental labour charges, hire charges of T &

    P etc., complete for finished item of work. (APSS no. - 309 & 310) GRAVEL FROM OUT SIDE

    Vibrated plain cement concrete (1:4:8) proportion (cement) fine aggregate coarse aggregate for foundation using 40mm size HBG

    Metal (SS.5) from approved quarry including cost and conveyanceof all materials like cement, sand coarse aggregate water including

    machine mixing and vibrating charges, seneriage charges etc.to site including of all materials and all labour charges etc. complete.

    for finished item of work as per SS 405 of APSS for levelling course. P.C.C AT BASEMENT LEVEL

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 52

  • 8/12/2019 Fertiliers Estimates

    53/62

    GROUND FLOOR

    9

    2 39.25 0.75 9.5 559.31

    3 31.75 0.75 9.5 678.66

    3 11.5 0.36 9.5 117.99

    Deductions

    Doors 3 3 0.75 8 -54.00

    1 6 0.75 8 -36.00

    2 2.5 0.36 8 -14.40

    windows 6 6 0.75 5.5 -148.50

    Ventilator 1 6 0.75 2 -9.00

    1094.06 Cub.Ft 95 103935.58

    10 Beams at slab level in P.T.

    (M 35 Prop. )

    9 51 4 1 1836.00

    1836.00 Cub.Ft 185 339660.00

    11

    1 371 0.75 1 278.25

    278.25 Cub.Ft 185 51476.25

    12 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    (M 35 Prop. )

    1969.11 Cub.Ft 185 364285.35

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and conveyance of all

    materials like cement sand bricks water etc to site cost of seigniorage charges and all materials and all mixing lifting charges and all

    labour charges etc complete for finished item of work APSS No: 504 & 501 for Superstructure in Ground floor.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per SS108

    with necessary reinforcement including cost and conveyance of al l materials like cement, fine aggregate and coarse aggregate water

    etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete vibrations, curing etc

    complete for finished item of work but excluding cost of steel at its for finished item of work.as per SS 403, but excluding cost of

    reinforcement steel and its fabrication charges for Beams

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 53

  • 8/12/2019 Fertiliers Estimates

    54/62

    13

    INSIDE

    1 324.5 - 9.5 3082.75

    Deductions

    Doors 3 3 - 8 -72.00

    1 6 - 8 -48.00

    2 2.5 - 8 -40.00

    2922.75 Sq.Ft 21 61377.75

    OUTSIDE 1 168 - 11 1848.00

    DEDUCTION

    windows 12 6 - 5.5 -396.00

    Ventilator 2 6 - 2 -24.00

    1428.00 Sq.Ft 21 29988.00

    14

    1 107 - 50 5350.00

    16 50 - 1 800.00

    7578.00 Sq.Ft 21 159138.00

    15

    2' X 2' Vitrified Tiles 1 1 1634 1634.00 Sq.Ft 70 114380.00

    16

    PAVING TILES 1'0" X1'0" 1 1 3688 3688.00 Sq.Ft 45 165960.00

    Plastering 12mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4) prop with dubara

    sponge finishing including cost & conveyance of materials and water to work site seigniorage and all operational, incidental, labour

    charges such as scaffolding, mixing mortor, lift charges, curing etc complete for finished item of work as per SS No.901 & 904

    Ceiling Plastering 20mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4) prop with

    dubara sponge finishing including cost & conveyance of materials and water to work site seigniorage and all operational, incidental

    charges etc., complete for finished item.

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop base coat and

    neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and jointed with neat cement paste,

    including seignourage, cost and conveyance of all materials and water from approved sources to work site and all operational,

    incidental, labour charges such as mixing mortar, dressing, laying, lift charges, curring etc, complete for finished item of work as per

    SS.703, but excluding cost of C.C.bed.

    Flooring with PAVING TILESof 1st. Quality of size not exceeding 1'0" X1'0" , laid over C.C. Flooring bed set over 20 mm thick C.M.

    (1:3) prop base coat and neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and

    jointed with neat cement paste, including seignourage, cost and conveyance of all materials and water from approved sources to work

    site and all operational, incidental, labour charges such as mixing mortar, dressing, laying, lift charges, curring etc, complete for

    finished item of work as per SS.703, but excluding cost of C.C.bed.

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 54

  • 8/12/2019 Fertiliers Estimates

    55/62

    17

    2922.75 Sq.Ft 17 49686.75

    18

    Painting of exterior in snowcem

    Quantity same as out side plastering - - - - 1428.00 Sq.Ft 15 21420.00

    Providing Painting to new walls with two coats of Emulsion wall Putty with two coats of Oil bound distemper of approved brand and

    shade over the base coat of appropriate primer of approved brand making 3-coats in all to give an even shade after thoroughlybrushing the surface to remove all dirt and remains of loose powedered materials, including all operational, incidental charges

    including cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved brand and shade

    over the base coat of approved white cement primer making three-coats in all to give an even shade after thoroughly brushing the

    surface to remove all dirt and remains of loose powdered materials, all operational, incidental charges including cost of brushes and

    all labour charges etc., complete for finished item of work as per SS911

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 55

  • 8/12/2019 Fertiliers Estimates

    56/62

    FIRST FLOOR

    19

    Superstructure with first class table 2 97 0.75 12.75 1855.13

    mounted brick (4 1/2" thick, 1:4CM) 2 39.25 0.75 12.75 750.66

    2 15.25 0.375 12.75 145.83Deductions

    windows 18 6 0.75 8 -648.00

    Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    2058.61 Cub.Ft 95 195567.89

    20 Beams at slab level in P.T. ( M35 )

    9 51 4 1 1836.00

    1836.00 Cub.Ft 185 339660.00

    21

    Beams at slab level in R.c.c.

    (in 1:2:4 prop) 1 371 0.75 1 278.25

    278.25 Cub.Ft 185 51476.25

    22 Slab in P.T. (in M35 prop) 1 107.25 51 0.36 1969.11

    1969.11 Cub.Ft 185 364285.35

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per SS108

    with necessary reinforcement including cost and conveyance of all materials like cement, fine aggregate and coarse aggregate water

    etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete vibrations, curing etc

    complete for finished item of work but excluding cost of steel at its for finished item of work.as per SS 403, but excluding cost of

    reinforcement steel and its fabrication charges for Beams

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and conveyance of all

    materials like cement sand bricks water etc to site cost of seigniorage charges and all materials and all mixing lifting charges and all

    labour charges etc complete for finished item of work APSS No: 504 & 501 for Superstructure in Ground floor.

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 56

  • 8/12/2019 Fertiliers Estimates

    57/62

    23

    INSIDE

    1 404 - 12.75 5151.00

    Deductions

    Doors 4 3 - 8 -96.00

    2 6 - 8 -96.00

    4 2.5 - 8 -80.00

    4879.00 Sq.Ft 21 102459.00

    OUTSIDE 1 283 - 14 3962.00

    windows 36 6 - 5.5 -1188.00

    Ventilator 4 3 - 2 -24.00

    2750.00 Sq.Ft 21 57750.00

    24

    Ceiling 1 107 - 50 5350.00

    16 50 - 1 800.00

    8900.00 Sq.Ft 21 186900.00

    25

    1 1 5446 5446.00

    5446.00 Sq.Ft 70 381220.00

    Plastering 12mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4) prop with dubara

    sponge finishing including cost & conveyance of materials and water to work site seigniorage and all operational, incidental, labourcharges such as scaffolding, mixing mortor, lift charges, curing etc complete for finished item of work as per SS No.901 & 904

    Ceiling Plastering 20mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4) prop with

    dubara sponge finishing including cost & conveyance of materials and water to work site seigniorage and all operational, incidentalcharges etc., complete for finished item.

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop base coat and

    neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and jointed with neat cement paste,

    including seignourage, cost and conveyance of all materials and water from approved sources to work site and all operational,incidental, labour charges such as mixing mortar, dressing, laying, lift charges, curring etc, complete for finished item of work as per

    SS.703, but excluding cost of C.C.bed.

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 57

  • 8/12/2019 Fertiliers Estimates

    58/62

    26

    Quantity same as in side plastering 4879.00 Sq.Ft 17 82943.00

    27

    Quantity same as out side plastering - - - - 2750.00 Sq.Ft 15 41250.00

    28STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN1 246.00 1 1 246.00 R.Ft 510 125460.00

    Providing Painting to new walls with two coats of emuision wall Putty with two coats of Oil bound distemper of approved brand and

    shade over the base coat of appropriate primer of approved brand making 3-coats in all to give an even shade after thoroughly

    brushing the surface to remove all dirt and remains of loose powedered materials, including all operational, incidental chargesincluding cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved brand and shade

    over the base coat of approved white cement primer making three-coats in all to give an even shade after thoroughly brushing the

    surface to remove all dirt and remains of loose powdered materials, all operational, incidental charges including cost of brushes and

    all labour charges etc., complete for finished i tem of work as per SS911

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 58

  • 8/12/2019 Fertiliers Estimates

    59/62

    SECOND FLOOR

    29

    Superstructure with first class table 2 97 0.75 9.5 1382.25

    mounted brick (9" thick, 1:4CM) 2 39.25 0.75 9.5 559.31

    Deductions

    WINDOWS 18 6 0.75 5.5 -445.50

    Ventilator 2 3 0.75 2 -9.00

    DOOR 1 6 0.75 8 -36.00

    1451.06 Cub.Ft 95 137850.94

    30 Beams at slab level in P.T. ( M35 )

    9 51 4 1 1836.00

    1836.00 Cub.Ft 185 339660.00

    31

    (in 1:1:3 prop) 1 371 0.75 1 278.25

    278.25 Cub.Ft 185 51476.25

    32 Slab in P.T. (in 1:2:4 prop) 1 107.25 51 0.36 1969.11

    1969.11 Cub.Ft 185 364285.35

    Brick masonary in Cement motor (1:6) mix using 2 nd class bricks and approved sourse and including cost and conveyance of all

    materials like cement sand bricks water etc to site cost of seigniorage charges and all materials and all mixing lifting charges and all

    labour charges etc complete for finished item of work APSS No: 504 & 501 for Superstructure in Ground floor.

    VRCC(1:1 :3) prop nominal mix using 6 to 20mm(SS-5) graded HBG machine crushed metal for approved quarry as per SS108

    with necessary reinforcement including cost and conveyance of al l materials like cement, fine aggregate and coarse aggregate water

    etc to site cost at seigniorage and all materials including centering shuttering, machine mix laying concrete vibrations, curing etc

    complete for finished item of work but excluding cost of steel at its for finished item of work.as per SS 403, but excluding cost of

    reinforcement steel and its fabrication charges for Beams

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 59

  • 8/12/2019 Fertiliers Estimates

    60/62

    33

    INSIDE

    1 404 - 9.5 3838.00

    Deductions

    Doors 4 3 - 8 -96.00

    2 6 - 8 -96.00

    4 2.5 - 8 -80.00

    3566.00 Sq.Ft 21 74886.00

    OUTSIDE 1 276 - 9.5 2622.00

    Deductions

    windows 36 6 - 5.5 -1188.00

    Ventilator 4 3 - 2 -24.00

    1410.00 Sq.Ft 21 29610.00

    34

    Ceiling 1 107 - 50 5350.00

    16 50 - 1 800.00

    6126.00 Sq.Ft 21 128646.00

    35

    Flooring with 2'-0" X 2'-0" Vitrified Tiles 1 1 5446 5446.00

    5446.00 Sq.Ft 381220.00

    Plastering 12mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4) prop with dubara

    sponge finishing including cost & conveyance of materials and water to work site seigniorage and all operational, incidental, labour

    charges such as scaffolding, mixing mortor, lift charges, curing etc complete for finished item of work as per SS No.901 & 904

    Ceiling Plastering 20mm thick in two coats with base coat of 9mm thick in CM(1:5) prop & top coat of 3mm thick in CM(1:4) prop with

    dubara sponge finishing including cost & conveyance of materials and water to work site seigniorage and all operational, incidentalcharges etc., complete for finished item.

    Flooring with 2' X 2' Vitrified Tilesof 1st. Quality , laid over C.C. Flooring bed set over 20 mm thick C.M. (1:3) prop base coat and

    neat grey cement slurry of honey like consistency spread at the rate of 3.3 kgs of cement per sqm and jointed with neat cement paste,

    including seignourage, cost and conveyance of all materials and water from approved sources to work si te and all operational,incidental, labour charges such as mixing mortar, dressing, laying, lift charges, curring etc, complete for finished item of work as per

    SS.703, but excluding cost of C.C.bed.

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 60

  • 8/12/2019 Fertiliers Estimates

    61/62

    36

    apply two coats of Birla type Wall putty

    in interiors3566.00 Sq.Ft

    17 60622.00

    Quantity same as internal plastering

    37

    Quantity same as out side plastering - - - - 1410.00 Sq.Ft 9 12690.00

    38

    1 1 16371 3 49113.00 K.g 55 2701215.00

    39

    42 6 - 5.5 1386.00 S.Ft. 450 623700.00

    40elevation works as per architects design

    ( stone, A.C.P. , and texture finish)1 1 107 28 2996.00 Sq.Ft

    deduction windows 16 6 - 5.5 -528.00 S.Ft.

    2468.00 S.Ft. 150 449400.00

    Painting to new walls over two coats of exterior cement based wall Putty with two coats of SNOWCEM of approved brand and shade

    over the base coat of approved white cement primer making three-coats in all to give an even shade after thoroughly brushing thesurface to remove all dirt and remains of loose powdered materials, all operational, incidental charges including cost of brushes and

    all labour charges etc., complete for finished item of work as per SS911

    Providing High Yield Strength deformed bars Fe 415 made of different diameters cutting and bending to required size and shape

    placing in position with cover blocks of approved materials and size, tying firmely with M.S. binding wire, forming grills for

    reinforcement work as per approved designed drawing to be supplied at the time of execution work excluding cost and conveyance

    of deformed bars, but including binding wire, cover blocks and all operational, labour charges such as cutting, bending placing in

    position, tying etc complete. for finished i tem of work. (Payment will be made on the basis of weight of fabricated deformed bars only)

    Supplying and fixing of fully glazed/ Partially glazed fenesta type window as per drawing, using 5mm thick glass including cost and

    conveyance to site of aluminium sections, glass,including labour charges for manufacturing windows, fixing in position using wooden

    blocks and sheet metal screws etc., complete for finished item and as per consultants.

    Providing Painting to new walls with two coats of emulsion wall Putty with two coats of Oil bound distemper of approved brand andshade over the base coat of appropriate primer of approved brand making 3-coats in all to give an even shade after thoroughly

    brushing the surface to remove all dirt and remains of loose powedered materials, including all operational, incidental charges

    including cost of brushes and all labour charges etc., complete for finished item of work as per SS911

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 61

  • 8/12/2019 Fertiliers Estimates

    62/62

    41Supplying and fixing of ELEVATOR of

    Jhonson brand10 PASSENGERS 1 1Each 800000.00 800000.00

    42STAINLESS STEEL RAILING AS PER

    ARCHITECTS DESIGN1 246.00 1 1 246.00 R.Ft 350 86100.00

    43 Compound wall 1 1 396 396.00 R.Ft 800 316800.00

    12640909.16

    GRAND TOTAL

    TOTAL

    ADD CONTRACTOR'S PERCENTAGE AT PAR/ BELOW/ABOVE

    THE WARANGAL DIST. FERTILIZERS, PESTICIDESSEEDS WELFARE ASSOCIATION 6/17/2014 Page 62