40
Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman Commissioner 1

February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

Roosevelt/Clark Public Hearing – TIF Designation Developer Designation

February 5, 2019

Rahm Emanuel Mayor

David Reifman Commissioner

1

Page 2: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

1. The Basics of TIF 2. Roosevelt/Clark TIF District Designation 3. Redevelopment Project and Developer

Designation

AGENDA

2

Page 3: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

PREVIOUS: REVISED:

3

ROOSEVELT/CLARK: UPDATED MAP BOUNDARIES

Page 4: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

Cottontail Park

15th St.

16th St.

Clar

k St

.

Stat

e St

.

ROOSEVELT/CLARK: UPDATED BOUNDARY DETAILS

4

Page 5: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

• Generates resources for economic and community development improvements • Subject to regulatory framework established by the State • Limited to areas that meet specific requirements • TIF funds are restricted in how they can be used. • 23-year terms

5

TIF PROGRAM: OVERVIEW

Page 6: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

Total allocations by location

85.8% Neighborbhoods 14.2% Downtown

$435M

$2.64B

Total allocations by type

Economic Development

Transit Facilities

Schools Plans, Studies & Admin

Public Infrastructure

Affordable Housing

Municipal Facilities

Parks & Open Spaces

6

TIF PROGRAM: ALLOCATIONS, 2011 – 2018

Page 7: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK: DISTRICT DESIGNATION

Page 8: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

8

ROOSEVELT/CLARK TIF: CONTEXT

F f

Page 9: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

WHAT IS IT? 141 total acres - the majority of which is vacant. Qualifies as a blighted area per TIF Act

WHY IS IT BEING CREATED? Address the lack of public infrastructure in the area and the issues that has created, including the vacancy of the 78 site for more than 40 years.

HOW WILL FUNDS BE USED? Funds pledged for the construction of public infrastructure

9

ROOSEVELT/CLARK TIF: OVERVIEW

Page 10: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

IMPROVED AREA VACANT AREA Obsolescence Obsolete Platting

Lack of Community Planning Environmental Remediation

Inadequate Utilities Unused Disposal Site

Deterioration

Deleterious Land Use

Per the TIF Act, the area qualifies as a Blighted Area

10

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

Page 11: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

11

Page 12: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

12

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

Page 13: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

13

Page 14: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

14

Page 15: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

15

Page 16: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK TIF: ELIGIBILITY FACTORS

16

Page 17: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

1. Develop the area as a jobs center, including a

dense, mixed-use residential community 2. Provide better access to all transportation

modes 3. Develop the area as mixed-use including a

jobs center and residential community

17

The critical objective for the TIF is to be a source of funds for public infrastructure

ROOSEVELT/CLARK TIF: REDEVELOPMENT GOALS

Page 18: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

• Public Works Improvements $605 million

• Site Preparations $25 million

• Surveys, Analysis, Legal Costs $25 million

• Affordable Housing Construction* $20 million

• Job Training $20 million

• Interest Costs $5 million

$700 million *Does NOT include affordable housing provided through ARO obligation.

18

ROOSEVELT/CLARK TIF: REDEVELOPMENT BUDGET

Page 19: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

19

Taylor Street Bridge Construction

Wells/Wentworth Connector

ROOSEVELT/CLARK TIF: PROPOSED IMPROVEMENTS

PREVIOUSLY PLANNED IMPROVEMENTS

Seawall Construction (50%) $10.1 M

New CTA Station $364.6 M

Relocated Metra Tracks $84.5 M

Clark Street Improvements $79.0 M

15th Street Construction $13.0 M

TOTAL INFRASTRUCTURE $551.2 M

Page 20: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

ROOSEVELT/CLARK: REDEVELOPMENT PROJECT & DEVELOPER DESIGNATION

Page 21: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

21

Seawall Construction (50%) $10.1 M

New CTA Station $364.6 M

Relocated Metra Tracks $84.5 M

Clark Street Improvements $79.0 M

15th Street Construction $13.0 M

TOTAL INFRASTRUCTURE $551.2 M

NEW PUBLIC INFRASTRUCTURE: PROJECT OVERVIEW AND BUDGET

Page 22: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

•TIF will be used for public infrastructure - not private development costs.

•Related Midwest will construct infrastructure projects on behalf of the City and will be reimbursed for those costs.

•The City has financial protection – TIF is only provided as increment is generated.

22

REDEVELOPMENT AGREEMENT: STRUCTURE

Page 23: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

23

PUBLIC INFRASTRUCTURE: 15TH STREET CTA STATION

Page 24: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

24

PUBLIC INFRASTRUCTURE : 15TH STREET CTA STATION

Page 25: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

25

PUBLIC INFRASTRUCTURE: METRA REALIGNMENT

Page 26: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

26

PUBLIC INFRASTRUCTURE: CLARK STREET IMPROVEMENT

Page 27: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

27

PUBLIC INFRASTRUCTURE: 15TH STREET CONSTRUCTION

Page 28: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

28

PUBLIC INFRASTRUCTURE: SEAWALL RECONSTRUCTION

Page 29: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

29

Seawall Construction (50%) $10.1 M

New CTA Station $364.6 M

Relocated Metra Tracks $84.5 M

Clark Street Improvements $79.0 M

15th Street Construction $13.0 M

TOTAL INFRASTRUCTURE $551.2 M

NEW PUBLIC INFRASTRUCTURE: PROJECT OVERVIEW AND BUDGET

Page 30: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

• Related Midwest to undertake the development of public infrastructure improvements to the City’s specifications.

• The Developer will be reimbursed through increment generated from Roosevelt/Clark TIF District.

• Project will potentially use an SSA to provide additional security.

30

REDEVELOPMENT AGREEMENT: FINANCIAL STRUCTURE

Page 31: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

• $7 billion dollars private investment • 24,000 new permanent jobs

• 10,000 new construction job • 2,000 new affordable housing units,

which includes up to $200 million in ARO funds

• $25 million Neighborhood Opportunity Bonus payment

• 12 acres of public open space

• 100-foot wide river walk

31

REDEVELOPMENT AGREEMENT: CITY-WIDE BENEFITS

Page 32: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

Roosevelt/Clark Public Hearing – Eligibility Criteria Redevelopment Plan Developer Designation

February 5, 2019

Rahm Emanuel Mayor

David Reifman Commissioner

32

Page 33: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

BACK UP SLIDES

33

Page 34: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

TIF PROGRAM REFORM 2011-2018

Since 2011, the number of designated TIF districts citywide decreased by 15%, from 162 to 138 districts. • 24 terminations/repeals • 9 expirations • 9 designations By 2026, TIF districts citywide will decrease to 49 districts, due to current expiration schedules of 89 existing districts.

Support for Neighborhoods 86% of citywide TIF allocations have been directed toward neighborhood projects. Annual Surplus Strategy Applies to any district that has a 25% or more uncommitted cash balance, resulting in $1.2 billion returned to taxing bodies since 2011. Freeze in Downtown Spending No new, non-infrastructure spending in seven downtown districts since 2015. Improved Transparency The City publishes spending allocation on the open data portal as well as all relevant Redevelopment Agreements and Annual Reports.

Consistent progress to reduce program breadth and scope

34

Page 35: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

35

Page 36: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

PIN 17-21-210-137

Cottontail Park

15th St.

16th St.

Clar

k St

.

Stat

e St

.

Page 37: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

The 78 ARO Obligation Under the 2015 ARO, the following requirements would apply Total units in project

ARO requirement Units Notes

10,000

20% (required because of TIF)

2,000

Under the 2015 ARO, • At least 25% of ARO obligation (500 units) are

“Required Units” • “Required Units” could be built either off-site (within

2 miles and in higher income area) or on-site • Remaining 75% could be paid in-lieu

36

Page 38: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

The 78 ARO Obligation Under the PD, we negotiated the following ARO mix ARO units Units Notes

On-site At least 5% 500+ Units should be distributed throughout development

Off-site Up to 10% 500-1,000

Off-site units must be • Within two miles

AND/OR • At least 50% of off-site units must be built in Pilsen-

Little Village Pilot area • City would provide credit for units built in the Pilsen-

Little Village Pilot in partnership with Non-Profit Affordable Housing developments

In-lieu fee At least 5% 500+ 2019 fee: $182,748/unit

500 units = $91 million

37

Page 39: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

Where do the in-lieu fees go? $91 million in-lieu would be deposited into the Affordable Housing Opportunity Fund (AHOF), where it is split 50:50 between • Chicago Low Income Housing Trust Fund, which provides rental subsidies for very-low income households AND • Affordable housing construction, preservation, and rehab units and programs across the City $91 million would provide • Trust Fund Rental subsidies for 300 families at risk of homelessness – for 15 years AND • 150 new long-term affordable units - and/or funding for affordable housing programs including Homeowner Improvement Grants and PEAR

38

Page 40: February 5, 2019 Roosevelt/Clark Public Hearing – TIF ......Roosevelt/Clark Public Hearing – TIF Designation Developer Designation February 5, 2019 Rahm Emanuel Mayor David Reifman

Pilsen- Little Village Pilot Boundaries

39