February 24 – February 28, 2013 Phoenix, Arizona Session #110 Collaboration in Long-Term Stewardship at DOE’s Hanford Site - Abstract # 13019 *Rick Moren, PG, *David Brown, **Ella Fiest, ***Keith Grindstaff, PMP, ***Jamie Zeisloft *Mission Support Alliance, LLC, Richland, WA **Washington Closure Hanford, LLC, Richland WA ***US Department of Energy, Richland Operations, Richland WA

February 24 – February 28, 2013 ♦ Phoenix , Arizona

  • Upload
    vanig

  • View
    40

  • Download
    0

Embed Size (px)

DESCRIPTION

Collaboration in Long-Term Stewardship at DOE’s Hanford Site - Abstract # 13019 * Rick Moren, PG, *David Brown, **Ella Fiest , ***Keith Grindstaff, PMP, *** Jamie Zeisloft *Mission Support Alliance, LLC, Richland, WA **Washington Closure Hanford, LLC, Richland WA - PowerPoint PPT Presentation

Citation preview

Page 1: February  24 – February 28, 2013  ♦  Phoenix , Arizona

February 24 – February 28, 2013 ♦ Phoenix, Arizona

Session #110

Collaboration in Long-Term Stewardship at DOE’s Hanford Site - Abstract # 13019

*Rick Moren, PG, *David Brown, **Ella Fiest, ***Keith Grindstaff, PMP, ***Jamie Zeisloft

*Mission Support Alliance, LLC, Richland, WA **Washington Closure Hanford, LLC, Richland WA ***US Department of Energy, Richland Operations, Richland WA

Page 2: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Background/History

Hanford Site1943-1987 Pu Production1989 Placed on NPL1998 Initial discussions of LTS2010 DOE/RL LTS Program2011 First land to LTS2013 First reactor to LTS

Page 3: February  24 – February 28, 2013  ♦  Phoenix , Arizona

LTS Today

3 DOE Programs3 Contractors

3 Periods of Performance3 Incentives

Page 4: February  24 – February 28, 2013  ♦  Phoenix , Arizona

ContractorsMission Support Alliance (MSA) LLC

(Services)Washington Closure Hanford (WCH) (River

Corridor Closure)CH2MHill Plateau Remediation Company

(PRC) (Central Plateau Cleanup)

Page 5: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Hanford’s LTS Program

Page 6: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Collaboration Elements

• Integrated Project Teamo DOE SMEs Technical and Contractso Contractor SMEs o Meet Bi-weeklyo Bias toward action – personal accountability o Builds relationships and working trusto Issues solved at lowest appropriate levelo Collaborative innovationo Risk management

Page 7: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Collaboration

• Transition package prepared by all three contractors

• Differing performance incentives/contract• Change from one transition to 14

transitions w/o significant REA• Allowed more efficient transition• New discovery process tested in first

transition

Page 8: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Transition ScheduleYEAR #2011 12012 22013 22014 42015 5

14• Schedule is accelerating into 2015

o New ideas to speed the processo ISS reactor transitiono Combine parcels

2011 2012 2013 2014 20150

2

4

6

8

10

12

14

16

Cumulative Transitions

Page 9: February  24 – February 28, 2013  ♦  Phoenix , Arizona

LTS Progress3 transitions98 mi2 to date1 cocooned reactor in 2013>149 Waste Sites

Institutional ControlsVegetation MonitoringRemedy Assessments

Page 10: February  24 – February 28, 2013  ♦  Phoenix , Arizona

ISS Reactor Transition• Transition 5 cocooned reactors in 2013

2 years early• Reschedule S&M activities

cost savings and efficiency

105-C 2014 105-H 2015105-DR, 105-D 2015

105-N 2015

Page 11: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Benefits of Collaboration• High performing team• Multiple transitions promotes efficient

closeout for WCH and DOE Closure documentation on a

manageable scale• MSA directly supports cleanup

mission and RL site vision

Page 12: February  24 – February 28, 2013  ♦  Phoenix , Arizona

Conclusions• Collaboration is essential for effective

progress• Transparency and open

communication drive collaboration• Strong team relationships and

individual accountability result in long term progress

• Strong DOE leadership

Page 13: February  24 – February 28, 2013  ♦  Phoenix , Arizona

QUESTIONS?