February 15, 2016
Kate Donegan, Superintendent Gary Dolinko, Board President Cyndi Cohen, CSBO Marcus Holleran, Director Buildings and
Grounds Carole Pugh, Architect, Green Associates Jeff Chamberlin, 20/10 Engineering Construction Management Team – Frederick
Quinn Company ◦ Adam Slotkus – Superintendent of Project ◦ John Eallonardo – Executive VP Construction ◦ Fred Marano, Executive VP Estimating
Phase I - Meyer School Underground Storm Water System ◦ Completed
Phase II - Meyer and Middleton Additions ◦ Most contracts have been awarded. Remaining bid
awarded in February and March.
Schedule: Site demolition, excavation, Geothermal, building foundation, mechanicals, wall, etc. ◦ Open in Fall 2017
ELIZABETH MEYER SCHOOL - SKOKIE SD 73.5
Meyer:
● Approximately 23,000 square feet
● Six classrooms
● Fine Arts classroom
● Gymnasium
● Library
● Gross motor room
● Four small instructional offices
Wellfield
Loop Pumps
Heat Pump Units
Middleton:
Approximately 1900 square feet
One multi-purpose space
Renovation of existing space for small instructional space and band rehearsal space
Construction Updates on the Web Site
Neighborhood Flyers
Construction Manager on site