Feasibility Studies
2
Definition A process where, prior to the execution of
any given project, all aspects of the said project
Marketing Technical Financial
are assessed and evaluated under the prevailing conditions of the local economy where the project is to be executed.
3
Contents A feasibility study report should include:
1. Index.2. Introduction. 3. Executive summary.4. Marketing report.5. Technical report.6. Financial report.7. Appendixes.
4
Index (Table of contents)
Serves as an easy reference to various topics in the feasibility report.
Format:Main title page no. Subtitle page no.
It’s important to write the accurate page no. in front of each title.
5
6
Introduction (Preface)
A short & precise description of the project.
7
Executive summary
It summarizes the significant results of each part of the feasibility study (i.e. marketing, technical & financial)
It should be short & precise containing all the important results of the study, in order to enable executives to make an initial decision.
8
Marketing Report
Product Description Product Identification. Technical Specification.Applied Standards.Targeted Customers.
9
Marketing Report Market Survey
Market Size Historical Demand (5 years Min). Future Demand( Specify Projection Method). Market Gap.
Identification of competitive brands. Prices. Market Share. Producers. Agents.
10
Marketing Report Market Survey
Local Production List of local producing Plants (Name, Licensed
Capacity, and Actual Capacity) List of Plants under Construction.
Local Import Quantity. Value. Source of Import.
11
Marketing Report Results
Proposed production Capacity.Projected Market Share.Recommended Marketing Strategies.
Targeted Market Segment. Competitive Edge. Projected Selling Prices. Promotion Plans. Sales Strategies (i.e. Targeted Markets,
Distribution Channels, and Points of Sales).
12
Technical Report
Production Process: Process Description. Process Flow Chart.
13
Process Flow Chart (Phase I)
RAW MATERIALS
LEAD ORE
PHASE II
SCRAP BATTERIES OTHER LEAD SCRAPB.PLATES / DROSS / OXIDE / PASTE ETC
BATTERY BREAKING SYSTEM
METALLIC LEADLEAD PASTEPOLY PROPYLENECHIPS
WASHING&DRYINGSold To Third party
14
Process Flow Chart (Phase II)
SMELTING SECTION
HEAVY SLAG / /METALLIC
PHASE III
FLUE DUST C WITH CHEMICALS
POLUTION CONTROL/EXHAUST SYSTEM
CRUDE LEAD
FURNACE
SLAG SEGRAGATION
SAMPLE FOR TESTLIGHT SLAG
DISPOSAL
15
Process Flow Chart (Phase III)REFINING SECTION
SAMPLE ANALYSIS
STORES
CHARGING / MELTING
MOULDING
KETTLES
REFINING PROCESS
BLENDING & ALLOYING
LEAD ALLOYSPURE LEAD – 99.97(MIN)
SOFTENING
ANALYSIS AT EVERY STAGE
16
Technical Report
Production Capacity: Capacity at full
Production. Yearly Targeted
Production.
Year 1 Year 2 Year 3 Year 4 Year 5Quantity % Quantity % Quantity % Quantity % Quantity %
5,000 50 6,000 60 7,000 70 8,000 80 10,000 100
Full Production Capacity 10,000 MT/year
Yearly Production Schedule
17
Technical Report Land and location:
Proposed location (Justification). Total Area Required. Land Value or Annual Rent.
Buildings: Production Building. Stores and Warehouses. Administration Offices. Total Buildup Area. Landscape. Specification Analysis of Offers.
18
No. Building type Area (m2)Cost /m2
(S.R)Total cost
(S.R)
1 Production bldg. 2500 600 1,500,000
2 Offices 500 1000 500,000
3 Raw material warehouse 2000 300 600,000
4 Finished goods store 1000 400 400,000
Total Build up area 6000 3,000,000
19
Technical Report
Machinery and Equipments:Production Lines.Auxiliary Equipments. Lap Equipments. Installation and Commissioning SchedulesAnalysis of Offers (Technical and Cost
Analysis).Cost of Selected Machinery and Equipments.
20
No. Equipment type
Unit cost
No. of Units
Total cost
Utilities requirement
1 Rotary Furness 20,000 1 20,000 100 2 0.5 20
Equipments & machineries analysis :
Electricity
(Kwh)
Water
(m3)
Fuel
(l)
Air
(m3)
21
Technical Report
Raw Materials:Production raw materials.Packaging materials.
List By : Type – Source – Quantity per unit of production - Unit Price - Yearly Requirement – Total Cost
22
No. Item Source Cost / U
(S.R)Q / U of
production
Cost / U of production
(S.R)
1 Scrap batteries Local 200/mt 1.8mt/mt 360
2 Soda ash Imported 1000/mt 0.1mt/mt 100
3 Iron chips Local 1000/mt 0.04mt/mt 40
4 Wooden palettes Local 160 each 0.5/mt 80
5 Straps Local 5/lm 4lm/mt 20
Total cost of raw material for each ton of finished product S.R 600
Raw material cost / Unit :
23
year 1 2 3 4 5
Targeted production 5,000 6,000 7,000 8,000 10,000
Unit cost 600 600 600 600 600
Total cost 3,000,000 3,600,000 4,200,000 4,800,000 6,000,000
Yearly total cost of Raw material :
24
Technical Report Transportation Equipments:
Forklift. Trucks and Vans. Buses. Cars.
Furniture: Office Equipments Office Furniture. Accommodation Furniture.
Utilities: Electrical Power. Water. Fuel.
List yearly Requirements and cost.
25
Technical Report Manpower Requirements:
Management Staff. Technical Staff:
Production. Maintenance. Lab.
Supporting Staff: Labors. Drivers. Security.
Proposed Salary Scale. Proposed yearly total manpower cost (Salaries & benefits) Proposed Organization chart.
26
Yearly manpower requirements :
No. Position Year 1 Year 2 Year 3 Year 4 Year 5
1 G. Manager 1 1 1 1 1
2 P. Manager 1 1 1 2 2
3 M. Manager 1 1 1 2 2
4 Operator 10 12 14 16 20
5 Labor 10 12 14 16 20
27
Proposed salary scale :
No. Position Basic salary/ month benefits Total monthly
package Annual cost
1 G. Manager 10,000 5,000 15,000 180,000
2 P. Manager 8,000 4,000 12,000 144,000
3 M. Manager 6,000 3,000 9,000 108,000
4 Operator 1,500 500 2,000 24,000
5 Labor 900 300 1,200 14,400
28
Organization ChartOrganization Chart Executive General Manager
Marketing Manager
Accounts Supervisor
Accountant
Secretary
Financial Manager
Cashier
Warehouse
Human Resources Manager
Administration
Supervisor
shifts supervisor
operating Supervisor
Government Affairs
Personnel Supervisor
Production Manager
Lab Supervisor
Salesman
29
Financial Report Total Investment:
Fixed Capital: Fixed Assets.
Land. Buildings. Machinery and Equipments. Vehicles. Furniture.
Pre-operating Expenses. Cost of Feasibility Studies. Cost of Engineering Drawings. Licenses and Registrations. Recruitment cost. Pre-operating Salary.
30
Financial Report Total Investment:
Working Capital: Months of 1st operational year Total Operating Cost.( Based on business
nature ) Salaries and benefits. Row materials. Utilities. Maintenance Cost. Consumables. Marketing Expenses. Transportation cost. Rent. Other Acquired Services:
Legal. CPA.
31
Financial Report
Sources of Funds: Paid up capital. Loans.
Governmental loans.
Commercial loans.
Partners loan.
32
Financial Report
Financial Statements: In order to prepare the financial statements, the
following schedules have to be prepared: Loan’s repayment schedule.
Yearly income statement.
Depreciation & Amortization schedule.
Annual Maintenance table.
33
Financial Report
Financial Statements: Profit & loss statement.
Cash flow statement.
Balance sheet.
34
Financial Report
Financial Indicators: ROI : Net Profit before tax / total investment. ROE : Net Income / Owners Equity. IRR: the discount rate that makes estimated NPV of an
investment = 0 Break even point : Fixed cost/(Selling Price – Variable cost)
Payback period : length of time until the sum of cash flow = Initial Investment
35
Financial Report
Sensitivity analysis: Decrease income by 10% & fix operating costs.
Fix income & increase operating costs by 10%.
Decrease income by 10% & increase operating
costs by 10%.
36
Financial Report
S.W.O.T Analysis:
Strengths
Weaknesses
Opportunities
Threats
37
Appendix
Classified files of all working documents
organized in alphabetical order for easy
reference.
38
General Tips
Use simple English language. Avoid using long paragraphs. Use appropriate charts to
represent data.
21%
29%27%
23%
1st Qtr2nd Qtr3rd Qtr4th Qtr
Line Chart
Pie Chart
0102030405060708090
1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
EastWestNorth
Bar ChartSometimes called a frequency polygon
showing trends through time. Sometimes called a histogram showing comparisons through certain time.
Shows percentages of division of the whole or parts of the whole
39
General Tips Use facts & not assumptions. Indicate your source of information. Review the study for any contradictions in figures or information or any
illogical sequences. Be always in touch with your clients through:
Progress reports. Draft reports of various parts of the feasibility study. Submit draft of F.S for remarks and approval.
Be honest. Always remember a great presentation leaves good impression on your
client.