67
Feasibility Study CONCRETING OF TABIGUE-BALOCAWEHAY FARM TO MARKET ROAD Proponent: June 20154 Republic of the Philippines Department of Agriculture PHILIPPINE RURAL DEVELOPMENT PROJECT Republic of the Philippines Municipality of Abuyog Province of Leyte

Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

Embed Size (px)

Citation preview

Page 1: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

Feasibility Study

CONCRETING OF

TABIGUE-BALOCAWEHAY FARM TO MARKET ROAD

Proponent:

June 20154

Republic of the Philippines

Department of Agriculture

PHILIPPINE RURAL DEVELOPMENT PROJECT

Republic of the Philippines Municipality of Abuyog

Province of Leyte

Page 2: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

Republic of the Philippines

Province of Leyte

MUNICIPALITY OF ABUYOG -o0o-

OFFICE OF THE MUNICIPAL MAYOR

04 June 2015

ENGR. ALMA LANDIA Component Head

I-BUILD, Philippine Rural Development Project (PRDP)

Department of Agriculture (D.A.)

Regional Office No. 8

Kanhuraw Hill, Tacloban City

Dear Engr. Landia:

Mabuhay!

I am pleased to submit herewith the attached Feasibility Study (FS), Detailed Engineering Design

(DED) and other supporting documents for the Rehabilitation/Concreting of the Tabigue –

Balocawehay Farm to Market Road (FMR) which the LGU of Abuyog, Leyte is proposing for

funding under the I-BUILD Component of the Philippine Rural Development Project (PRDP) this year.

The sub-project is a critical component of our strategic focus on Rice and Coconut as the principal

agricultural commodities from which to anchor the economic development of our municipality. The

sub-project will effectively link the rice and coconut producing beneficiary barangays to the open

markets in Leyte province and is expected to further enhance the development of these industries of our

municipality.

The municipality’s focus in promoting rice and coconut is directly in harmony and aligned to the

priorities and development direction of the Provincial Government of Leyte which likewise identified

rice and coconut as the main crops to promote in the province.

Lastly, the LGU of Abuyog has already allocated a counterpart funding for said sub-project equivalent

to ten percnt (10%) of the total project cost.

We fervently hope for the most favorable I-BUILD/PRDP action and approval of our sub-project

proposal. Thank you and God bless.

Truly yours,

Hon. OCTAVIO J. TRAYA, JR. Municipal Mayor

Page 3: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

iii | P a g e

TABLE OF CONTENTS

Page

Title Page i

Transmittal Letter ii

Table of Contents iii

List of Tables vi

List of Exhibits vii

Annexes vii

Executive Summary 1

I. Project Profile 2

Municipal Profile of Abuyog, Leyte 2

1.1 Brief Historical Background 2

1.2 Barangays 2

1.3 Location 4

1.3.1 Geographic Boundaries 4

1.3.2 Relative Distance to Growth and Commercial Center 4

1.3.3 Existing Road Transport Network and Physical Condition 7

1.3.4. Availability of Public Transport 7

1.4 Total Land Area 9

1.4.1 General Land Use Classification 9

1.4.2 Agricultural Land Use Classification 9

1.4.3 Abuyog Land Area Relative to that of Leyte Province & Region 8 9

1.5 Topography 11

1.6 Soils and Suitability 11

1.7 Climate and Water Sources 11

1.8 Municipal Population 14

1.8.1 Total Population, Gender and Average Growth Rate 14

1.8.2 Number of Households and Average Household Size 14

1.9 Economic Activities and Sources of Income 14

1.9.1 On-Farm: Crops Production 14

1.9.2 On-Farm: Livestock and Poultry 15

1.9.3 Inland Fisheries 15

1.9.4 Off-Farm and Non-Farm Economic Sectors 16

1.9.4.1 Secondary Sub-Sector: Industry 16

1.9.4.2 Tertiary Sub-Sector 16

1.9.5 Employment and Income Sources 17

II. Project Background and Rationale 18

2.1. Statement of the Problem and Opportunities 18

2.2 Strategic Direction of the Municipality of Abuyog 18

2.2.1 Development Vision of the Municipality of Abuyog 18

2.2.2 Mission Statement 18

2.2.3 Goal 18

2.2.4 Objectives 18

2.3 Sub-Project Objectives 19

2.4 Brief Presentation of Socio-Economic Indicators 19

2.4.1 Location of the Tabigue-Balocawehay Road Project 19

2.4.2 Population Characteristics of Direct Road Influenced Area (RIA) 20

2.4.3 Main Agricultural Crops in the RIA Barangays 20

2.5 Description of the Priority Value Chain to be Served by the FMR 20

Page 4: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

iv | P a g e

Page

III. Project Description and Analyses 21

A. Market / Demand-Supply Situation 21

3.1 Existing Roads, Bridges and Transport System in the Area 21

3.2 Analysis of Road & Transport System (without & with road improvement) 21

3.2.1 Present road network condition 21

3.2.2 Availability of public transport vehicles 21

3.2.3 Seasonal Impassibility of Road Site 21

3.2.4 Alternate Route/s Within the Project Area 21

3.2.5 Availability of other Modes of Transport 22

3.2.6 Existing Modes of Transportation and Hauling of

Passenger and Cargo 22

3.2.7 Current Trip Volumes, Destinations, Travel times,

Volume/Capacity Ratios 22

3.2.8 Analysis of How the Proposed Road Facility Will Close

the Gap in Infrastructure Development Within the Area 22

B. Technical Analysis 23

4.1 Horizontal Road Alignment 23

4.2 Vertical Road Alignment 23

4.3 Drainage Analysis/Hydraulic 23

4.4 Geotechnical- Soil and Foundation Analysis 23

4.5 Structural Analysis- Pavement Thickness 23

4.6 Location of Quarries, Borrow Pits and Construction Materials 23

4.7 Items of Work and Cost 23

4.8 Implementation Schedule 24

C. Operational Analysis 25

5.1 Project Organization, Critical Activities and Project Outputs 25

5.1.1 Pre-Investment Phase 26

5.1.2 Project Execution/Implementation Phase 26

5.1.3 Post Project Implementation Phase 26

5.2 Plan for Management during Construction, Key Roles and

Responsibilities and Implementation Arrangements 26

5.3 Collection of Road Users Fees and Other Policies 30

5.4 Project Implementation Schedule 30

5.5 Project Monitoring and Supervision 30

5.6 Operation and Maintenance Scheme 31

D. Social Analysis 32

6.1 Project Beneficiaries 32

6.2 Indigenous Cultural Community/Indigenous Peoples (ICC/IP) 32

6.3 Site and Right-of-Way acquisition 32

6.4 Damage to Standing Crops, Houses and/or Properties 33

6.5 Physical Displacement of Persons 33

6.6 Economic Displacement of Persons 33

Page

Page 5: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

v | P a g e

E. Environmental Assessment 33

7.1 Natural Habitat 33

7.2 Physical Cultural Resources 33

7.3 Terrain, Soil Types and Rainfall 33

7.4 Drainage Situations and Flooding Potential 34

7.5 Impacts During Construction 34

7.5.1 Temporary Erosion and Sediment Control 34

7.5.2 Construction Noise Mitigation 34

7.5.3 Proper Handling of Construction Wastes 34

7.5.4 Public and Worker’s Safety 34

7.6 Status of Environmental Clearances 34

F. Financial Analysis 35

8.1 Total Project Cost by Financing Source and Cost Sharing 35

8.2 Total Project Cost Breakdown 35

8.2.1 Direct Costs 35

8.2.2 Indirect Costs 36

8.3 Status of LGU Equity Availability and LFC Certification 36

G. Economic Analysis and Evaluation 36

9.1 The Project Influence Area 36

9.1.1 Agricultural Production in the Road Influence Area 36

9.1.2 Population within the Direct Road Influence Area 37

9.1.3 Existing Vehicular Traffic Based on Traffic Survey Results 37

9.1.4 Transportation Costs by Animal/Human Haulers 38

9.1.5 Commuter Time Savings 38

9.1.6 Benefits of Newly Cultivated Agricultural Land 38

9.2 Economic Benefits 39

9.2.1 Vehicle Operating Cost Savings (VOCS) 39

9.2.2 Transport Cost Savings in Hauling Outputs and Inputs 39

9.2.3 Reduction in Travel Times from Farm to Market 39

9.2.4 Incremental benefits attributed to newly opened croplands 39

9.2.5 Other Benefits 40

9.3 Economic Costs 40

9.3.1 Capital Cost and O & M Cost Breakdown 40

9.4 Direct Jobs from Construction 41

9.5 Adjustment of Financial Values to Economic Terms 41

9.6 Results of the Economic Analysis 42

9.6.1. Economic Internal Rate of Return (EIRR) 42

9.6.2. Benefit-Cost Ratio (BCR) 42

9.6.3 Economic Net Present Value (ENPV) 42

9.7 Economic Sensitivity Analysis Results 42

9.7 List of Attached Models/Detailed Tables of EFA Templates 43

H. Conclusions and Recommendations 43

Annexes 44

Page 6: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

vi | P a g e

List of Tables

Table Page

1 Name, Areas, and Population of Barangays. Abuyog, Leyte. 3

2 Summary of Road Transport Network, Abuyog, Leyte 7

3 General Land Use Classification 9

4 Agricultural Land Utilization by Crops 9

5 Land Area of Abuyog vis-a-vis Provincial and Regional Total 9

6 Types of Soil in the Municipality of Abuyog, Leyte 11

7 Population Characteristics. Abuyog & Leyte (2010) 14

8 Agricultural Crops, Area Planted and Production Volume. Abuyog, Leyte 14

9 Livestock & Poultry, Production Volume/Value. Abuyog, Leyte. 2010. 15

10 Fishing Grounds, Fisheries Production Volume & Value. Abuyog, Leyte. 2011 15

11 List of Registered Businesses by Industry Sub-sectors. Abuyog, Leyte. 2010 16

12 List of Registered Businesses in Trade Sub-sector. Abuyog, Leyte. 2010 16

13 List of Registered Businesses, Personal Services Sub-sector. Abuyog, 2010 17

14 Employment & Revenues by Classification of Business & Trade. Abuyog, 2010 17

15 Population Characteristics of the RIA Barangays 20

16 Total Annual Production Volume and Value of Major Crops, RIA Barangays 20

17 Existing Roads and Transport System, RIA Barangays 21

18 Transport Data Taken from Traffic Survey. November 2014 19

19 Items of Work and Cost 24

20 Implementation Timetable 24

21 Duties and Responsibilities of Offices/Persons Involved in the Project 27

22 Annual Maintenance Cost, PCCP 31

23 Total Project Cost by Financing Source and Cost Sharing 35

24 Total Project Cost Breakdown 35

25 Production Areas, Volumes and Values of Crop in RIA Brgys., 2014 36

26 Population within the Road Influence Area (RIA), 2008. 37

27 Annual Ave. Daily Traffic, Canmarating-Can-aporong FMR, Nov. 2014 37

28 Prevailing Fares by Type of Vehicle, Travel Times & Distances, RIA, Nov. 2014 38

29 Average Travel Time of Commuters, RIA Barangays. Nov. 2014 38

30 Benefits of Newly Cultivated Agricultural Land 39

31 Total Investment and Operating & Maintenance Costs of Sub-project 40

32 Investment Costs of Sub-project (Financial & Economic) 41

33 Sensitivity Analysis, 20-Year Period 42

34 Economic Analysis 44

35 Sensitivity Analysis on Costs, Benefits and Delays 45

36 Investment and Maintenance Costs 47

37 Annual Road Maintenance Cost 47

Page 7: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

vii | P a g e

Table Page

38 Transport Data by Vehicle Type 48

39 Projected Number of Vehicles per Day 48

40 Projected Annual Average Daily Traffic (AADT) 48

41 Standard Vehicle Operating Cost Savings (Php) 49

42 Total Annual Vehicle Operating Cost Savings by Vehicle Type 49

43 Benefits – Vehicle Operating Costs (VOC) Savings 50

44 Benefits – Savings in Output Hauling 52

45 Benefits – Savings in Input Hauling 54

46 Benefits – Savings in Travel Time for Commuters 56

47 Benefits of Newly Cultivated Agricultural Land (Coconut, Rice) 58

List of Exhibits

Exhibit Page

1 Location Map of Abuyog, Leyte 5

2 Map of Abuyog Showing Its Barangays 6

3 Road Network Map of Abuyog, Leyte 8

4 Land Use Map of Abuyog, Leyte 10

5 Soil Map of Abuyog, Leyte 12

6 Mean Annual Rainfall. Abuyog, Leyte 13

7 Project Organization, Critical Activities and Project Output Chart 25

Annexes

Annex Page

1 Models/Detailed Tables of EFA Templates 45

2 Social Environmental Safeguards (SES) Compliance Documents 61

A. Abuyog Sanggunian Bayan (SB) Resolution No. 30-A, S. 2015 61

B. Abuyog Sanggunian Bayan (SB) Resolution No. 30-B, S. 2015 63

C. Local Finance Committee (LFC) Certification on Availability of Funds 66

D. Abuyog Sanggunian Bayan (SB) Resolution No. 29-A, S. 2015 65

E. Abuyog Municipal Development Council (MDC) Resolution No. 01, S. 2015 68

F. Certification of Non-Coverage (CNC), from EMB-DENR 72

G. Letter-Request for Certification that Odiongan & Layug Rivers are

Approved Sources of Aggregate Materials 73

H. Letter-Request for Certification that No Indigenous People/Community

Exists in Abuyog, Leyte 74

I. Minutes of Barangay Balocawehay Assembly/Consultative Meeting 75

J. Minutes of Barangay Tabigue Assembly/Consultative Meeting 82

K. Certification on Evidence of Road Right-of-Way Acquisition 83

L. Parcellary Map of PAP/List of Affected Property Owners within the Area 84

M. Waste Disposal and Dumping Site Certification 85

N. Certification Mayor’s Consent to Cut Trees Along the FMR Project 86

Page 8: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

1 | P a g e

Barangay

Total

Area

(has.)

Total Area

Planted

(has.)

Major Crops

Baloca-

wehay 615.03 571.40

Rice, Coconut, Corn,

Abaca, Banana

Tabigue 322.63 296.66 Rice, Coconut, Corn,

Banana, Rootcrops

Total 937.66 868.06

FEASIBILITY STUDY ON REHABILITATION/CONCRETING OF

TABIGUE - BALOCAWEHAY FARM TO MARKET ROAD, ABUYOG, LEYTE

EXECUTIVE SUMMARY

A. Project Title : Concreting of of Tabigue - Balocawehay

Farm to Market Road

B. Project Location : Brgys. Tabigue and Balocawehay,

Municipality of Abuyog, Province of Leyte

C. Project Category : Rural Access

D. Project Scale/Dimension : 2.0237 kilometers

E. Project Proponent : Local Government Unit (LGU) of Abuyog, Leyte

F. Implementing Unit : Local Government Unit (LGU) of Abuyog, Leyte

G. Income Classification : 1st Class Municipality

H. Total No. of Barangays : 63

I. Mode of Implementation : Contract

J. Road Influenced Areas :

K. Project Beneficiaries within Total Population= 4,767; Male= 2,454; Female= 2,313

the Road Influence Area : Number of Households = 1,046

L. Total Project Cost TPC = Php 15,102,142.39 (100%)

and Cost Sharing : WB Loan = Php 12,081,713.91 ( 80%)

DA/GOP = Php 1,510,214.24 ( 10%)

LGU Equity = Php 1,510,214.24 ( 10%)

M. Economic Viability : ENPV = Php 19,957,413.00

Indicators EIRR = 37.32 %

BCR = 2.42

N. Conclusion and The proposed sub-project is found to be feasible in

Recommendations : all aspects. Overall economic benefits far outweigh

economic costs as revealed by the economic viability

indicators evaluated at a discount rate of 15%. Project

implementation is shown to be technically and

operationally feasible. The proposed sub-project is

therefore highly recommended for approval.

Page 9: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

2 | P a g e

I. Project Profile

Municipal Profile of Abuyog, Leyte

1.1 Brief Historical Background

When the Spaniards landed at Homonhon Island in Samar, they found no potable water.

Some of the crews sailed westward to look for water and landed on the shores covered

by a swarm of bees. Surprisingly, the headman accompanied by his tribesmen met the

Spaniards cordially. When the Spaniards asked the natives about the name of the place,

the natives replied: “Ah, Buyog!”- thinking they were asked about the swarm of bees on

the seashore. From then on, the Spaniards called the place “Abuyog”.

Abuyog became a Spanish “encomienda” as early as 1591. Encomiendas are large

estates, assigned to “encomenderos” (Spaniards) for their care and administration and as

a reward for their services to the Spanish crown. After the abolition of encomiendas, local

governments called alcaldias (provinces) and pueblos (towns) were established. In 1885,

Abuyog became a pueblo when the Presidencia building was complete. Abuyog was

finally incorporated into a municipality of the Province of Leyte, Philippines by virtue of RA

No. 2565 enacted by Congress without executive approval on June 21, 1959.

Abuyog became a 1st class municipality in 2002. It has a total budget of Php175.5 million

in 2014. It is comprised of 63 barangays of which 22 are coastal and 41 are upland

barangays. In the 2012 Regional Social & Economic Trends (RSET)-Eastern Visayas, a

publication of the National Statistics Coordination Board (NSCB), Abuyog has a total

population of 55,509 living in 12,431 households and with an average household size of 4.5

persons. It is one of the most progressive and rapidly developing municipalities in Leyte

province in spite of the generally poor conditions of its hinterland barangays.

Abuyog is located at the eastern part of Leyte along the seacoast of Leyte Gulf and the

Pacific Ocean. It is 61.62 kilometers to Tacloban City, the regional center, along the

Philippine-Japan Friendship (Maharlika) Highway. See Exhibit 1.

1.2 Barangays

Abuyog is politically and administratively subdivided into 63 barangays, nine of which are

classified as urban barangays and mostly located within the poblacion area, while the

other 54 are generally rural barangays located in the outlying areas of the municipality.

(See Exhibit 2.)

Table 1 shows the names, classification and population characteristics of each of the

barangays of Abuyog.

Balocawehay is the biggest barangay in terms of population with 3,490 residents living in

766 households and the smallest is Mahayahay with only 160 residents in 40 households. In

terms of land area, Pinamanagan is the largest with 2,985 hectares while the smallest is

Nalibunan located in the Poblacion with only a little over 10 hectares.

The barangays covered in this sub-project are Brgy. Canmarating with 1,021 inhabitants in

243 households and Brgy. Can-aporong with 490 residents in 92 households.

Page 10: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

3 | P a g e

Table 1. Name, Total Area, Cultivated Area, Number of Households and Population of

Barangays in Abuyog, Leyte.

Barangay Total Area

(Has.)

Cultivated

Area (Has.) Population

No. of

Households

Urban

Bito 41.99 17.25 1,036 221

Buntay 21.01 2.97 1,791 411

Can-uguib 24.88 10.10 1,516 334

Guintagbucan 65.12 44.29 1,190 287

Loyonsawang 15.24 0.60 964 217

Nalibunan 10.11 776 171

Santa Fe 12.92 0.44 1,856 426

Santo Niño 41.37 1.00 2,333 500

Victory 13.63 0.83 2,475 560

Rural

Alangilan 721.10 304.71 318 80

Anibongon 1,636.43 227.50 286 80

Bagacay 1,801.19 243.29 472 113

Bahay 308.85 40.85 310 70

Balinsasayao 1,850.81 695.05 2,259 494

Balocawe 358.94 331.07 1,511 326

Balocawehay 615.03 571.40 3,490 766

Barayong 417.85 389.21 1,304 297

Bayabas 834.45 621.35 776 169

Buaya 923.97 79.53 691 188

Buenavista 205.67 163.20 660 158

Bulak 1,400.81 269.62 315 77

Bunga 283.46 255.20 1,500 353

Burubud-an 382.03 209.42 639 144

Cadac-an 242.51 191.76 373 90

Cagbolo 639.65 297.82 454 112

Can-aporong 177.01 139.72 430 92

Canmarating 363.54 337.22 1,021 243

Capilian 399.48 380.48 766 173

Combis 909.55 153.94 376 92

Dingle 488.13 266.51 582 123

Hampipila 1,713.57 363.03 1,331 324

Katipunan 1,259.92 371.20 1,131 234

Kikilo 944.53 79.41 543 131

Laray 278.93 255.59 252 57

Lawa-an 234.27 85.41 386 77

Libertad 961.42 291.89 1,030 239

Mag-atubang 149.96 132.41 265 67

Mahagna 817.48 130.93 479 109

Mahayahay 423.73 34.84 160 40

Maitum 393.07 361.25 558 118

Malaguicay 790.02 58.39 908 237

Matagnao 438.68 203.60 439 106

Page 11: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

4 | P a g e

Barangay Total Area

(Has.)

Cultivated

Area (Has.) Population

No. of

Households

Nebga 660.37 107.53 489 112

New Taligue 1,918.36 620.33 362 85

Odiongan 290.78 272.35 677 156

Old Taligue 956.24 227.48 355 77

Pagsang-an 237.32 202.98 932 218

Paguite 323.68 307.92 765 163

Parasanon 1,003.47 244.18 509 113

Picas Sur 271.58 240.07 554 127

Pilar 205.66 13.70 468 107

Pinamanagan 2,985.10 4.68 516 129

Salvacion 181.64 81.83 625 155

San Francisco 382.85 90.87 326 81

San Isidro 255.92 236.59 652 136

San Roque 909.22 90.50 908 206

Santa Lucia 771.58 55.22 305 71

Tabigue 322.63 296.66 1,277 280

Tadoc 181.26 151.92 364 86

Tib-o 520.35 77.76 671 141

Tinalian 400.23 122.37 411 84

Tinocolan 997.93 94.32 308 79

Tuy-a 942.08 286.54 718 174

Total 38,331 12,440 52,144 11,886

Source: CBMS Survey, DILG-Abuyog (2014)

1.3 Location

1.3.1 Geographic Characteristics and Location

Abuyog is located at the eastern part of Leyte along the seacoast of Leyte Gulf and

the Pacific Ocean. It is situated at 1250 01’ 00" east latitude, 100 45’ 00" north longitude.

It is bounded on the north by the Municipality of MacArthur, Leyte, on the northwest by

the Municipality of Javier, Leyte, on the south by the Municipality of Silago, Southern

Leyte, on the west by the Municipality of Mahaplag, Leyte and on the east by Leyte

Gulf and the Pacific Ocean.

1.3.2 Relative Distance to Major Growth and Commercial Centers

Abuyog is 61.62 kilometers to Tacloban City, the regional center of commerce and

trade, governance and education, along the Philippine-Japan Friendship Highway. It

is 24.98 kilometers to the town of Dulag, 27.18 kilometers to the town of Mahaplag, 41.44

kilometers to the interior town of Burauen, 46.19 kilometers to the town of Baybay and

2.5 hours by motorboat to the town of Silago, Southern Leyte.

.

Page 12: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

5 | P a g e

Exhibit 1. Location Map of Abuyog, Leyte

ABUYOG

PROVINCE

OF LEYTE

Page 13: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

6 | P a g e

Exhibit 2. Project Location: Brgys. Tabigue-Balocawehay FMR

Page 14: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

7 | P a g e

1.3.3 Existing Road Transport Network and Physical Condition

As shown in Table 2, the total road network of the municipality is roughly 683 kilometers.

Exhibit 3 displays the road network map of Abuyog. By classification, barangay roads

comprise the longest road network totalling 579.7 kms. or 85 % of total, while national

roads total 44.8 kms. or 6.5 %. On the other hand, municipal roads total 33.6 kms. or 4.92

% of total road network while provincial roads comprise 22.5 kms. The table also depicts

the general physical conditions of the roads and corresponding recommendations.

Table 2. Summary of Road Transport Network, Abuyog, Leyte

Classification Length

(km.)

% to

Total

Area

(has.)

Physical

Condition Recommendation

National 44.8 6.50 % 134.4 * Lacks maintenance * Needs Asphalting

* Additional FMR

Provincial 22.5 3.30 % 45 * Lacks maintenance * Needs Asphalting

* Additional FMR

Municipal 33.6 4.92 % 50.4 * Lacks maintenance * Needs Asphalting

Barangay 579.69 84.91% 347.81 * Some street are in

sand and gravel

* Concrete

pavement

Access Road 2.1 0.31 % 1.26 * Sand and gravel * Concrete

pavement

Total 682.69 100 % 399.47

Source: MPDO in Comprehensive Land Use Plan (CLUP). Abuyog, Leyte.

1.3.4. Availability of Public Transport

The Abuyog road along the Maharlika Highway is 61.62 kilometers to Tacloban City. It

is interconnected on the north by the town of MacArthur, on the northwest by the town

of Javier, on the south by the town of Silago, Southern Leyte and on the west by the

town of Mahaplag.

There are two means of transportation in the municipality: by land and by sea. Land

transportation facilities include buses, van, motor cabs, pedicabs and trucks. In areas

or barangays along rivers and seas, motorboats and bangcas are available.

Daily trips to Tacloban City depart every 30 minutes. Passenger jeeps leave Abuyog

bound for Baybay every morning and the last trip from Baybay is around 3:00 PM. Buses

and vans pass by Abuyog daily from Tacloban City en route to Baybay and Southern

Leyte and vice versa. Motorcabs and pedicabs serve passengers within the town

proper and neighboring barangays. For people in the hinterlands and rural barangays,

the popular “Habal-habal” or single motorcycle for hire, which can carry up to eight

persons including the driver, is the preferred mode of transportation.

For sea transportation, Abuyog has two wharves located at Tab-ok, Brgy. Nalibunan

and Brgy. Sto. Nino. There are seven mini seaports which are located at Brgys.

Bagacay, Buaya, Kikilo, Sta. Lucia, Malaguicay, and San Francisco. These mini seaports

however need improvements of its facilities which are only waiting sheds that can

accommodate 40 persons only and one service trip in a day. Some motorboats serve

the coastal barangays and reach the towns of Silago and Hinunangan, Southern Leyte.

Small motorboats serve the interior barangays along the Higasaan River.

Page 15: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

8 | P a g e

Exhibit 3. Road Network Map of Abuyog, Leyte

Page 16: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

9 | P a g e

1.4 Total Land Area

1.4.1 General Land Use Classification

Table 3 shows the general land use of the municipality of Abuyog, Leyte. Urban uses,

and Agro-Industrial & Industrial uses cover 1.49 %, and 0.02%, respectively.

Characteristically rural, Abuyog is generally more agricultural (32.45%) and forested

(63.59%). Exhibit 4 depicts the general land use of Abuyog.

Table 3. General Land Use Classification

Category (Areas) Area (has.) % Total

Urban Uses 531.91 1.49 %

Agro-Industrial and Industrial 9.51 0.02 %

Agricultural 12,440.08 32.45 %

Forest 24,376.29 63.59 %

Grassland/Pastures 57.54 0.15 %

Other Uses (Cemeteries; Sanitary Landfill; etc.) 62.89 0.16 %

Water Uses (Nipa Swamps; Mangroves; etc.) 852.34 2.22 %

Total 38,330.56 100.00 %

Source: Comprehensive Land Use Plan (CLUP). Abuyog, Leyte.

1.4.2 Agricultural Land Use Classification

Abuyog is basically an agricultural municipality with a big majority of its total population

highly dependent on agriculture for livelihood and sustenance. Principal agricultural

products of the municipality include coconut, rice, corn, rootcrops, vegetables and

abaca, among others. Table 4 shows the number of hectares devoted to each crop.

Coconut and rice are the top farm products in terms of total area planted.

Table 4. Agricultural Land Utilization by Crops

Crops Area Utilized (has.) Crops Area Utilized (has.)

Coconut 9,409.93 Banana 159.98

Rice 4,233.32 Pineapple 147.53

Corn 710.53 Mango 142.58

Rootcrops 518.63 Jackfruit 53.52

Vegetables 293.81 Cacao 9.82

Abaca 257.69 Coffee 5.58

Total 15,942.90

Source: Municipal Agriculture Office, Abuyog, Leyte .

1.4.3 Abuyog Land Area Relative to that of Leyte Province and Region 8

Table 5 shows the relative size of the land area of municiplaity of Abuyog to Leyte

Province, Leyte Island and Eastern Visayas Region.

Table 5. Land Area of Abuyog vis-a-vis Provincial and Regional Total (in has.)

Abuyog Leyte Province Leyte Island Region 8

38,331 651,510 831,230 2,323,000

Relative Size in Percent 5.88 % 4.61 % 1.65 %

Source: Regional Social and Economic Trends (RSET) 2012, a publication of the NSCB-8.

Page 17: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

10 | P a g e

Exhibit 4. Land Use Map of Abuyog

Page 18: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

11 | P a g e

1.5 Topography

The municipality of Abuyog has mix topographic reliefs. The mountainous area is located

in the southern portion of the municipality and along the boundary with the municipality

of Mahaplag and a little portion at the western part of the municipality. Along the seacoast

are flatlands where densely populated barangays are located. The municipality has many

rivers and creeks distributed evenly in the whole area, notably the Cadac-an River which

serves as the major drainage outlet into the sea.

The total land area of Abuyog is 38,330 hectares which includes forest land area of 24,809

hectares and alienable and disposable land area of 13,087 hectares. Its coastal/sea area

is estimated to be 42,809 hectares.

1.6 Soils and Suitability

Abuyog has five soil types distributed in the different barangays at varying volumes and

degrees. Table 6 shows the soil types with areas in hectares in decreasing order. Exhibit 5

depicts the Soil Map of Abuyog.

An analysis of the different soil types prevailing in the municipality of Abuyog is basic to the

determination of the suitable agricultural production expected. Soil fertility is relatively high

considering that silts and other fertile soil colloids from the upland areas are carried and

deposited by the various river systems into the low lying areas especially during rainy

seasons and seasonal flooding.

Table 6. Types of Soil in the Municipality of Abuyog, Leyte

Soil Type Area (has.) % to Total Area

Rocky Mountainous 29,531.35 77.04 %

Rough Mountainous 2,585.49 6.75 %

Hydrosol Fine Sand 3,919.27 10.23 %

Tacloban Clay Loam 2,132.65 5.56 %

Obando Fine Sand 161.74 0.42 %

Total 38,330.50 100.00 %

Source: Comprehensive Land Use Plan (CLUP). Abuyog, Leyte.

1.7 Climate and Water Sources

Exhibit 6 on page 13 shows that the municipality of Abuyog belongs to the range of

171.47mm. to 201.93mm. mean annual rainfall and 2,500 mm estimated rainfall. Abuyog

experiences high rainfall during the months of January to February and also during the

months of September to December.

But during the summer months from March to July, Abuyog receives low rainfall. This

information is based from the 35-year statistics on climatological normal from PAGASA for

the years 1965 to 2000 gathered from different weather substations throughout the

Philippine archipelago and analysis maps processed by NAMRIA for the Bureau of

Agricultural Research-Spatial Analysis and Information Laboratory (BAR-SAIL).

Page 19: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

12 | P a g e

Exhibit 5. Soil Map of Abuyog

Page 20: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

13 | P a g e

ABUYOG

Exhibit 6. Mean Annual Rainfall. Abuyog, Leyte

Page 21: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

14 | P a g e

1.8 Municipal Population

Abuyog is a 1st class municipality in the Province of Leyte, Philippines. In the 2012 RSET-

Eastern Visayas published by NSCB-8, the town has 55,509 inhabitants and the

municipality’s population density is 83 persons per square kilometer per census in 2010.

Table 7. Population, Gender, Number of Households, Average Household Size, Average

Population Growth Rate. Abuyog & Leyte (2010).

Town/

Province

Total

Population Women Men

No. of

Households

Average

Household

Size

Average Annual

Rate of Increase1

Abuyog 55,509 26,849 28,660 12,431 4.5 0.60

Leyte 1,563,364 758,583 804,781 346,346 4.5 1.04

1 Average annual rate of increase for Census Years 2000 and 2010

Source: RSET-2012, NSCB-8

1.8.1 Total Population, Gender and Average Growth Rate

Table 7 shows that Abuyog has 55,509 inhabitants. By gender, men outnumber women

both in Abuyog population (1.07 : 1) and Leyte population (1.06 : 1). The average

population rate of increase of Abuyog is far lower at 0.60 compared to the provincial

average of 1.04.

1.8.2 Number of Households and Average Household Size

Table 7 also shows that the 55,509 inhabitants of Abuyog are in 12,431 households and

that the average household size of the municipality is identical to that of the province

of Leyte at 4.5, per census year 2010.

1.9 Economic Activities and Sources of Income

1.9.1 On-Farm: Crops Production

Abuyog is primarily agricultural with almost 16,000 hectares of its total land area of

38,331 hectares devoted to agriculture. Table 8 depicts the major crops produced in

the municipality. Coconut is the dominant crop with around 9,410 hectares planted

while rice follows with 4,725 hectares. High value crops and fruit trees are also planted.

Table 8 shows total annual production per crop in metric tons and estimated value.

Table 8. Agricultural Crops, Area Planted (in has.) and Production Volume (in metric

tons). Abuyog, Leyte. 2010.

Major Crops Area

(has.)

Production

Volume (in metric tons) Value(Php)

Coconut 9,410 18,819 249,864,000

Rice, irrigated 3,114 12,174 182,584,250

Rice, rainfed 1,611 4,484 66,349,290

Banana 445 14,978 14,670,702

High Value Crops 195 2,915 No data available

Rootcrops 230 4,900 No data available

Vegetables 156 2,502 No data available

Fruit Trees 194 No data vailable No data available

Source: Comprehensive Land Use Plan (CLUP); Municipal Agriculture Office. Abuyog, Leyte.

Page 22: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

15 | P a g e

1.9.2 On-Farm: Livestock and Poultry

Livestock and poultry are another sources of livelihood and income for the people of

the municipality. Some are engaged in this kind of aconomic activity in commercial

scale, as a family business or a family’s way of living. But most of the time, livestock

raising is at backyard level production, or for family domestic consumption only.

The Municipality of Abuyog produces not only crops but also livestock and poultry

products. Table 9 shows the various livestock and poultry being raised either in

backyard or commercial scale with corresponding estimated total value.

Table 9. Livestock & Poultry, Scale of Operation, Production Volume/Value. Abuyog, Leyte. 2010.

Livestock (Purposes) Scale Production

Volume (heads) Value(Php)

Carabao (meat; breeders) Backyard/Commercial 1,644 41,100,000

Cattle (breeders) Backyard 20 700,000

Swine (meat; breeders) Backyard/Commercial 4,343 15,200,500

Goat (meat; breeders) Backyard 60 500,000

Horse (breeders) Backyard 25 75,000

Chicken (meat, eggs) Commercial 100,000 65,000,000

Duck (meat, eggs) Backyard/Commercial 3,070 340,000

Turkey (meat, eggs) Backyard 15 22,500

Source: Comprehensive Land Use Plan (CLUP); Municipal Agriculture Office. Abuyog, Leyte.

1.9.3 Fisheries and Aquaculture

Since Abuyog is along the Pacific and surrounded by rivers and swamps, it is abundant

in marine and fresh water products like fish, lobsters, shrimps, crabs and other products.

Table 10 shows that there are 39 barangays engage in fishing both in marine and

freshwater fisheries. Total production is 61 metric tons per day valued at Php 5,200,000

marketed locally. However, although the municipality produces marine and

aquaculture products in abundance, it has no processing and storage facilities.

Table 10. Fishing Grounds, Fisheries Production Volume & Value. Abuyog, Leyte. 2011.

Fishing Grounds No. of Barangays Volume Value (Php)

Marine Fisheries

- Municipal Territorial Waters 22 (coastal) 31 tons/day 3,100,000

- Aquaculture - - -

- Brackish Water Fishponds 7 15 tons/day 1,200,000

Inland Fisheries

- Tilapia Fishponds 10 15 tons/day 900,000

Source: Comprehensive Land Use Plan (CLUP); Municipal Agriculture Office. Abuyog, Leyte.

Page 23: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

16 | P a g e

1.9.4 Off-Farm and Non-Farm Economic Sectors

The off-farm and non-farm economic sectors in the municipality are composed of

secondary and tertiary sub-sectors that are the main sources of employment and

income for the people of Abuyog outside of the agriculture sector.

1.9.4.1 Secondary Sub-Sector: Industry

Table 11 shows the list of registered businesses in the manufacturing/processing (25)

and in the construction (22) industries in Abuyog, Leyte. These sub-sectors support

the local processing and building industries.

Table 11. List of Registered Businesses by Industry Sub-sectors. Abuyog, Leyte. 2010.

Commercial / Business No. Commercial / Business No.

Manufacturing/Processing Industry Construction Industry

Bakery / Bakeshop 11 Construction Firms 2

Engineering & Construction 1 Hardware Supplies 3

Welding Shop/Pedicab Assembler 10 Hollow Blocks Maker 4

Rice & Corn Mill 6 Contractor 3

Furniture Shop 1 Construction Supplies 4

Woodcraft, Handicraft, Weaving

& Fashion Accessories 1

Construction & Concrete

Products 2

Internet Shop and PC Accessories 1 Sand & Gravel 4

Total 25 Total 22

Source: Comprehensive Land Use Plan (CLUP), Abuyog, Leyte.

1.9.4.2 Tertiary Sub-Sector

Commerce – mainly concentrated in the central business district of Abuyog.

There are about 200 registered business establishments engaged in wholesale

& retail as of end of 2010 as shown in Table 12.

Table 12. List of Registered Businesses in Trade Sub-sector. Abuyog, Leyte. 2010.

Wholesale & Retail Trade No. Wholesale & Retail Trade No.

Fruits & Vegetables Vendors 4 Dry Goods 15

Copra, Palay & Abaca Buyer 21 Natasha Store 1

Rice & Corn Retailer 7 Used Clothing/Ukay-ukay 1

Meat Dealer 9 RTW Direct Selling 2

Dressed Chicken 3 School & Office Supplies 3

Chicken Dealer 1 Sari-sari Store 63

Lechon Manok 3 LPG Retailer 1

Fish Broker 1 Gasoline Station 4

Fish Vendor 4 Water Station 3

Salted & Dried Fish Dealer/Vendor 2 Scrap Buyer 3

Agrivet, Animal Feeds Retailer 7 Coco Lumber Dealer 2

Agriculture Supplies 1 Multi Enterprises 3

Glass/Kitchen-ware/Plastic Center 2 Grocery 6

Glass & Aluminum Supply 4 Gen. Merchandise 3

Electronics Supplies & Services 2 Appliances/Furniture Store 1

Pharmacy 8 Total 200

Source: Comprehensive Land Use Plan (CLUP), Abuyog, Leyte.

Page 24: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

17 | P a g e

Transportation – There are many transport operators of mini buses, public utility

jeepneys, tricycles, “habal-habal” (single motorcycles for hire), pedicabs

(bicycles with side car), cargo trucks and vans for hire.

Telecommunications – There are two (2) cell sites, a postal services office, a

telephone company and cable TV operators in the municipality.

Personal Services: There are about 35 registered businesses providing personal

services like beauty parlors, shops, photo studios, funeral parlors, etc.

Table 13. List of Registered Businesses, Personal Services Sub-sector. Abuyog, 2010.

Commercial / Business No. Commercial / Business No.

Personal Services Educational Institution

Photo Studio Center & Supplies 4 Kindergarten 1

Xerox Copier 1 Realty Lesson 1

Gift Shop 1 College Institution 1

Funeral Parlor 4 Total 3

Beauty & Refreshment Parlor 2

Barber Shop 2 Agro-Industrial

Pawnshop & Jewelry 6 Farm & Poultry Farm 4

Catering Services 2 Farmer Center 1

Cable TV Services 1 Farmers & Fishermen Asso. 1

Express Padala 2 Total 6

Money Trasfer/Money Changer 2

Electronic Services 2 Transpo. & Communication

Computer Services 2 Bicycle/Motor Parts/Services 8

Allied Services 2 Motorcycle/Bicycle Dealer 4

Cycle Center 1 Internet Cafe 13

Surveying Office 1 Cell Phone Enterprises 2

Total 35 Total 27

1.9.5 Employment and Income Sources

As an agricultural town, most of the employed persons are engaged in farm crop

production, livestock & poultry raising and marine & inland fisheries. While on-farm

economic activities are the principal sources of employment and income of the

people in Abuyog, off-farm and non-farm economic activities are good contributors

to the local economy. As shown in Table 14, these sub-sectors employed 5,407 and

provided an aggregate income of almost Php 17.5 million in 2010.

Table 14. Employment & Revenues by Classification of Business & Trade. Abuyog, 2010.

Classification of Business and Trade No. of

Employment

Revenues

(in Pesos)

Wholesale and Retail Trade 3,674 8,851,200

Banking and Finance 64 700,000

Real Estate & Construction 216 2,950,000

Services 1,204 3,054,400

Others (Communication & Transportation) 249 1,940,000

Total 5,407 17,495,600

Page 25: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

18 | P a g e

II. Project Background and Rationale

2.1. Statement of the Problem and Opportunities

The current state of barangay roads of the municipality of Abuyog can be generally

described as follows: there is lack, inadequate and poorly maintained barangay road

networks, including farm to market roads, that connect barangay crop production centers

to Abuyog town proper and markets. This is due to inadequate funds of the local

government of Abuyog to properly maintain these roads.

The following are the dire consequences:

a) High cost of transporting production inputs like seeds and fertilizers into farms;

b) High cost of hauling agricultural outputs from the farms to markets;

c) High cost of operating transport vehicles due to frequent maintenance

d) Longer travel times and unsafe, inconvenient trips

These consequences serve as disincentives to farmers (and investors) to produce and

invest more due to transportation problems and high costs in bringing their produce to the

market. The proposed project would greatly enhance crop production and movement of

goods and services within and outside of the target areas.

2.2 Strategic Direction of the Municipality of Abuyog

All the programs and projects of the municipality of Abuyog are grounded on its vision and

mission. Quoted hereunder are its Vision and Mission Statements, as well as its Goal and

Objectives, as reflected in its 2014-2016 Executive and Legislative Development Agenda:

2.2.1 Development Vision of the Municipality of Abuyog:

“Peaceful, agro-industrialized and self-reliant Abuyog with disaster-resilient, healthy

and empowered citizenry living in a developed eco-tourist destination and

environment-friendly community.”

2.2.2 Mission Statement

“Promote peace and order, develop infrastructure and agro-industrial technologies,

provide employment opportunties and deliver quality socio-economic services

through active participation of politically matured leaders and constituents who shall

be disaster-resilient and endeavor to protect and maintain a well-balanced

environment.”

2.2.3 Goal

“To transform into a climate-proofed eco-tourist destination and business-friendly

municipality and convert its barangays into high value crop and food producers

thereby creating livelihood opportunities to every Abuyognon.”

2.2.4 Objectives

a) To increase investments for domestic tourism, commerce and trade;

b) To provide efficient infrastructure facilities and utilities so as to attract investments;

c) To generate employment and livelihood opportunities;

d) To increase productivity levels of major food, high-value fruits and crops;

Page 26: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

19 | P a g e

e) To develop, protect and regenerate the coastal and forest resources;

f) To provide incentives to individuals/corporations who shall be exemplars in disaster

risk reduction and climate change adaptation best practices;

g) To improve the delivery of basic services to alleviate or reduce poverty.

2.3 Sub-Project Objectives

The LGU’s Objectives (b) and (d), which articulate advancing infrastructure development

to support the growth of its agriculture sector, find congruence and support from “the

Philippine Rural Development Project (PRDP), a 6-year program designed to establish the

government platform for a modern, climate-smart and market-oriented agri-fishery sector.

In partnership with the LGUs and the private sector, PRDP will provide key infrastructure,

facilities, technology, and information that will raise incomes, productivity, and

competitiveness in the countryside.” (PRDP Brief, 05 June 2014).

In 6 years the program intervention would have achieved the following general objectives:

Increased annual real farm incomes of PRDP household beneficiaries by at least 5%;

Increased income of targeted beneficiaries of enterprise development by at least 30%;

Increased value of annual marketed output by at least 7%;

Increased number of farmers and fishers with improved access to DA services by 20%.

This sub-project, concreting of the Can-aporong-Canmarating FMR, is primarily intended

to contribute to achieving a robust and sustained agro-industrial development and self-

sufficiency in major agricultural crops like rice, corn, vegetables, poultry and livestock

being enjoyed by healthy, strong and GOD-fearing Abuyognons. It is directly aligned to

the development priorities of the Provincial Government of Leyte which identified coconut

and rice as principal crops to propel the economic development of the province. The sub-

project area is mostly planted to coconuts and rice. The proposed FMR will therefore

directly benefit the coconut and rice farmers, as well as barangay residents by way of

providing convenient, cost-effective and safe access to said areas.

With the rehabilitation and concreting of the road network linking the two barangays to

the poblacion of Abuyog, the following specific objectives shall be achieved:

a. Reduced vehicle operating costs of transport operators and road users by at least 50%;

b. Reduced hauling costs for passengers and agricultural in/outputs by as much as 30%;

c. Reduced hauling costs for passengers and agricultural in/outputs by as much as 30%;

d. Reduced travel time of the target road section from the current 10 minutes to 4 minutes;

e. Promote cultivation and use of new farmlands of at least 10 hectares per crop (rice

and coconut) thereby further increasing production volume and farm income;

2.4 Brief Presentation of Socio-Economic Indicators

2.4.1 Location of the Tabigue-Balocawehay Road Project

The proposed FMR sub-project is located in Sitio San Vicente, Brgy. Tabigue to Sitio

Canario & Sitio Danao, Brgy. Balocawehay, Abuyog, Leyte. The said road section is an

existing 2.0237-kilometer road that connects the two barangays to the Abuyog-

Mahaplag section of the national highway. (See Exhibit 2, page 6).

Page 27: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

20 | P a g e

2.4.2 Population Characteristics of the Direct Road Influenced Area (RIA)

Table 15. Population Characteristics of the RIA Barangays

Barangay Population

No. of

House-

holds

Est. Economically

Active Population1

Unem-

ployed2 Employed3

Balocawehay 3,490 766 1,221 159 1,062

Tabigue 1,277 280 447 58 389

Total 4,767 1,046 1,668 217 1,451

Male 2,454 Average Household Size = 4.56

Female 2,313

1 15 years old & above; 35% of total population 2 & 3 13% & 87% of the total economically active population, respectively

Source of Population Data : 2008 Abuyog DILG-CBMS Survey

As shown in Table 15, the two barangays have total population of 4,767 persons of

which 2,454 are males and 2,313 are females, living in 1,046 households. The estimated

economically active population is 1,668 of which 1,451 are assumed to be employed.

2.4.3 Main Agricultural Crops in the RIA Barangays

Barangays Tabigue and Balocawehay of Abuyog are basically agricultural

communities with majority of the inhabitants engaged in agricultural crop production.

Data obtained from the Municipal Agriculturist Office (MAO) show the beneficiary

barangays are main producers of rice, coconuts and corn. (See table below).

Table 16. Total Annual Production Volume and Value of Major Crops, RIA Barangays.

Crop Area

(in has.)

Annual Production

Volume (kgs.) Total Annual Production

Value (Php)

Rice/palay 461.69 3,970,534.00 107,204,418.00

Coconut/copra 353.25 678,240.00 16,956,000.00

Corn 23.00 34,500.00 690,000.00

Abaca 20.00 22,500.00 1,260,000.00

Banana 10.13 22,792.50 455,850.00

Total 868.07 4,728,566.50 126,566,268.00

Source: Abuyog Municipal Agriculturist Office (MAO)

2.5 Description of the Priority Value Chain to be Served by the FMR

The proposed road sub-project is a critical component of LGU-Abuyog’s strategic focus on

coconut and rice as the principal agricultural commodities from which to anchor its

economic development. The sub-project will effectively link the coconut and rice

producing beneficiary barangays to the open markets in Leyte province and is expected

to further enhance the development of the coconut industry of Abuyog. The municipality’s

focus in promoting coconut and rice is directly in harmony and aligned to the priorities and

development direction of the Provincial Government of Leyte which likewise identified

coconut and rice as the main crops to promote in the province.

Page 28: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

21 | P a g e

III. Project Description and Analyses

A. Market Analysis/Demand-Supply Analysis

3.1 Existing Roads, Bridges and Transport System in the Area

Table 17. Existing Roads and Transport System (in kms.), RIA Barangays, Abuyog, Leyte.

Road

Type

Gravel Earth Concrete Total

Passa-

ble

Not Pas-

sable

Passa-

ble

Not

Passable

Passa-

ble

Not Pas-

sable

Passa-

ble Not Passable

Brgy/Farm-

to-Market

Roads

- - - a. 2.023700

b. 2.240322 - - -

a. 2.240322

b. 2.023700

Municipal - - - - - - - -

Provincial - - - - - - - -

National - - - - - - - -

* Tabigue-Balocawehay Source: Municipal Engineer’s Office, Abuyog, Leyte

** Can-aporong-Canmarating

3.2 Analysis of Road and Transport System (without and with road improvement)

3.2.1 Present road network condition

The Tabigue-Balocawehay road section is an existing 2.0237-kilometer road that

connects the two barangays to the Abuyog-Mahaplag portion of the national

highway. It is a Barangay Road/Farm-to-Market Road (FMR) classified as “earth road,

not passable.” There is no existing bridge along the said road.

The road is in a very sorry state, and over time has slowly deterioted into a trail because

of vegetation covering most of the road. This is due to neglect because of inadequate

funds of the local government to properly maintain the road section. The road is also

repeatedly damaged due to heavy rains. It is hardly passable to 4-wheel drive type

vehicles. It is passable to single type motor vehicles during dry season only.

Despite the bad shape of the road, it connects the two barangays’ crop production

areas to the town proper which is the market center/trading point.

3.2.2 Availability of public transport vehicles

The transport system consists mainly of single motorcycles for hire (“habal-habal”) and

tricycles. There are only occassional cargo trucks and jeepneys because most of the

road is impassable year-round.

3.2.3 Seasonal Impassibility of Road Site

The road segment is generally passable to “habal-habal” and other vehicles year-

round but the said road section is slippery and dangerous to motorists on rainy days

and very dusty during hot days.

3.2.4 Alternate route/s used within the project area and their condition

There is no alternate route being used in the area.

Page 29: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

22 | P a g e

3.2.5 Availability of Other Modes of Transport which Tend to Compete with the Project

There are no railways or new road infrastructure projects currently on-going within the

RIAs that may compete with the proposed sub-project. The proposed FMR will not

compete but rather will complement other sub-project FMRs that might be pursued in

advancing the total socio-economic development initiatives of Abuyog.

3.2.6 Existing modes of transport and hauling of passenger and cargo

The table below summarizes the results of a traffic survey conducted on November

2014. It shows that the most popular mode of transport between the two barangays is

“habal-habal” or single motorcycle for hire because of its flexibility and serviceability.

This validates the information that habal-habal constitutes the principal mode of

transportation going to and from the two beneficiary barangays. Occasionally, a few

trucks and jeepneys come to the barangays to haul agricultural products primarily

coconuts, rice and corn as well as farm inputs and other items. There are also non-

motorized vehicles being utilized by farmers and barangay residents like animal

(carabao)-drawn carts and bicycles.

Table 18. Transport/Traffic Survey Data, Brgys. Tabigue & Balocawehay, Abuyog, Leyte.

November 2014.

Vehicle Type No. of

Units

No. of

Trips/Day

Operating

Days/Year

Ave. Loading

Capacity

(sacks)

Observed Transport

Fares per Passenger/

Cargo (P)

Motorcycle

("Habal-habal") 39 43 260 8 P30 / P30

Tricycle 15 35 260 15 P30 / P30

Car/Van 4 4 156 - P30 /

Jeepney 2 3 156 50 P30 / P30

Truck 6 8 104 100 / P30

Note: 1. Average Distance travelled = 2.0237 kms.

2. Travel times: 10 minutes (w/out project); 4 minutes (with project).

3.2.7 Current trip volumes, destinations, travel times, volume /capacity ratios

To determine the current volume of vehicular traffic going through Brgys. Tabigue -

Balocawehay, an actual traffic flow survey was conducted for seven (7) days from

November 24 to 30, 2014 starting at 4 am up to 10 pm daily. The above table also

summarizes the results of the survey.

3.2.8 Analysis of how the proposed road facility will close in the gap in Infrastructure

Development within the area in terms of generated, induced and diverted traffic

The proposed road sub-project connects the two barangays to the national highway.

Concreting the road will significantly cut travel distance (and time) to the town proper.

Once the sub-project is completed, farmers and residents of the two barangays will

greatly benefit from it. Consequently, significant reduction in travel times by more than

50% (from 10 minutes to 4 minutes) and savings in transportation/ hauling costs will be

realized. On the other hand, with the improved road, transport operators will realize

substantial savings due to less frequent maintenance of their vehicles. Moreover, the

improved road would induce more transport vehicles to ply the said route.

Page 30: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

23 | P a g e

B. Technical Analysis

4.1 Horizontal Road Alignment

The proposed road will have a right of way of 8 meters wide, consisting of a 5-meter

concrete paved carriageway and 1.5 meters shoulders on both sides. It will start from Brgy.

Tabigue to Brgy. Balocawehay where it will be connected to an existing concrete paved

road that links the barangay to the town proper of Abuyog. There will be no curve widening

and side cuts to be done as there are no sharp curves exist.

4.2 Vertical Road Alignment

The proposed project starts from a generally flat terrain with some rolling areas to hilly

portion having a maximum 1.0 percent gradient and these will be downgraded to the

required grade elevation. There will be some minor side cuttings to be done in other areas

to bring the road to its correct grade level.

4.3 Drainage Analysis/Hydraulic

Some portions of the existing foot-trail path in Brgy. Tabigue and Brgy. Balocawehay is

flooded during heavy and continuous downpour, particularly the lowland which serves as

the catchment of the run-off water from the hillside. The flooding, however, subsides in a

few hours after the heavy downpour stops. To mitigate the flooding of the road, Reinforced

Concrete Pipe Culverts (RCPCs) will be installed/constructed at waterways road crossings.

4.4 Geotechnical- Soil and Foundation Analysis

The soil classification map of the province indicates that the Leyte Clay Type of soil is

prevalent in the project area with an American Association of the State Highway and

Transportation Officials (AASHTO) soil classification rating of A-7 which means that the soil

has a liquid limit of 41 min and a plasticity index of 11 min. It is clayey type of soil with a

general subgrade rating of fair to poor.

4.5 Structural Analysis- Pavement Thickness

With a recorded average daily traffic (ADT), a 0.15-meter thick, 5-meter wide carriageway

is the recommended program standard. And the construction of the pipe culverts will

adhere to Department of Public Works and Highways (DPWH) Standards.

4.6 Location of Quarries, Borrow Pits and Construction Materials

The proposed construction of the existing and deteriorated gravel road will use base

course and aggregates that will be sourced from the municipality of Abuyog in Leyte

which is just within the locality. The materials will be hauled from the source site at Leyte

and delivered to the project site using 10 cubic meter capacity dump trucks. Adequate

supply of these aggregates is guaranteed as Leyte is the main supplier of these resources

all over the region, with existing quarries. Base course that will be used for subgrade

preparation will also be sourced from Abuyog area.

4.7 Items of Work and Cost

The total project cost for the 2.0237-kilometer road is Php 15,102,142 or a unit cost of

Php7,462,639 per kilometer. Table 19 shows the cost per item of work of the project.

Page 31: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

24 | P a g e

Table 19. Items of Work and Cost

Item

No. Scope of Work

Percent

Weight Quantity Unit Unit Cost Total

A. Earthworks

Spl 1 Mobilizaton/ Demobilization 0.76% 1 l.s. 114,375.51 114,375.51

100 Clearing and Grubbing 1.47% 14,289.60 sq.m. 15.52 221,801.03

102 (2) Surplus Common Excavation 4.08% 2,002.75 cu.m. 307.37 615,578.96

103 (6) Pipe Culvert & Drain Excavation 0.21% 86.40 cu.m. 371.94 32,135.62

104 (1) Embankment from Excavation 0.81% 294.86 cu.m. 417.08 122,978.84

105 Subgrade Preparation 2.26% 16,189.60 sq.m. 21.05 340,740.06

B. Base Course

201 Aggregate Base Course 21.77% 4,644.39 cu.m. 707.89 3,287,726.51

C. Surface Course

311 PCCP 67.21% 10,118.50 sq.m. 1,003.08 10,149,708.76

D. Drainage & Slope Protection Structure

500 (3) RCPC, 910mm Ø 0.73% 16.00 lin.m. 6,855.34 109,685.46

506 Stone Masonry 0.57% 21.30 cu.m. 4,042.49 86,088.82

Spcl 1 Project Signboard 0.14% 1.00 lot 21,322.83 21,322.83

Total Project Cost 100.00% 15,102,142.39

4.8 Implementation Schedule

The total project duration is 80 calendar days with the expected start of the project on the

1st week of August 2015. Expected completion date is on the 2nd week of October 2015

(See Table 20).

Table 20. Implementation Timetable

ACTIVITIES 2015

M A M J J A S O

I. Preparation

1. FS/Preliminary Engineering Studies Preparation

2. Preparation of Detailed Engineering Design

3. Supporting Documents Submission

4. Subproject Approval and Implementation

Management Agreement Signing

5. Capability Training

II. Procurement Process

1. Publication

2. Pre-Bid Conference

3. Conduct of Public Bidding

4. Post-Qualification Evaluation

5. Awarding and Approval Contract

III. Implementation Stage

1. Project Billboard

2. Clearing and Grubbing

3. Surplus Common Excavation

4. Pipe Culvert & Drain Excavation

5. Embankment from Excavation

6. Subgrade Preparation

7. Aggregate Base Course

8. RCPC, 910mm Ø

9. Portland Cement Concrete Pavement

10. Stone Masonry

Page 32: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

25 | P a g e

C. Operational Analysis

This section depicts the management and operational requirements of the project from

Pre-investment, Project Implementation, and Post Project Implementation stages.

Essentially, these stages in the project cycle requires the setting-up of three different

operating structures to properly address the critical tasks at each point of the project cycle

to achieve the project goals and objectives.

5.1 Project Organization, Critical Activities and Project Outputs

Exhibit 7- Project Organization, Critical Activities and Project Output Chart

Phase 3:

Post-Investment

Persons/Offices

Responsible

Outputs

Critical

Activities

Municipal Planning &

Development Officer

Municipal Engineer

Municipal Agriculturist

Municipal Treasurer

Municipal Accountant

Municipal Budget

Officer

Municipal Assessor

Bids & Awards

Committee

Municipal Planning &

Development Officer

Municipal Engineer

Municipal Budget

Officer

Municipal Treasurer

Municipal Accountant

Contractor

Municipal Engineer

Operation and

Maintenance Unit

Barangay

Chairmen

Beneficiaries

Feasibility Study

Preparation

Detailed

Engineering Design

Preparation

Project Mobilization

Social Preparation

Public Bidding

Awarding of

Contract

Project Execution

Monitoring

/Evaluation

Fund Releases /

Liquidation

Proper Road

Maintenance

Routine

Maintenance

Periodic

Maintenance

Feasibility Study

Detailed Engineering

Design

Project Approval

Road Section

Rehabilitated

As-Built Plan

Project Acceptance

Road Section

Properly Maintained

and Operational

Phase 2:

Implementation

Project Manager

Sanggunian Bayan

Municipal Mayor

Municipal Project

Management and

Implementation Unit

DA-PRDP

World Bank

Phase 1:

Pre-Investment

Page 33: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

26 | P a g e

5.1.1 Pre-Investment Phase

The Pre-Investment Phase requires the conduct of in-depth studies and analysis of the

feasibility of the proposed project from the economic and engineering perspective. It

involves preparation and formulation of the necessary project feasibility study (PFS) and

detailed engineering designs (DED) leading to eventual approval of the project by the

DA-PRDP and by the funding agency the World Bank (WB). The critical units and

persons involve in this phase are the Municipal Planning and Development Office

(MPDO) as the lead unit, Municipal Engineers’ Office (MEO), Municipal Agriculturist

Office (MAO), Municipal Treasurer’s Office (MTO), Municipal Accountant (MA),

Municipal Budget Office (MBO) and Municipal Assessor’s Office (MAO).

5.1.2 Project Execution/Implementation Phase

This Phase involves conduct of public bidding by the Bids and Awards Committee

(BAC), awarding of contract to the winning contractor, project execution and

implementation, monitoring and evaluation and fund releases and liquidation among

other necessary and critical activities leading to project completion and acceptance.

BAC is the lead unit during the bidding and awarding process while the MEO takes over

project management during actual project implementation.

5.1.3 Post Project Implementation Phase

The last Phase basically involves proper use and maintenance of the road network after

project completion and acceptance. This requires the conduct of routine and periodic

maintenance activities. Routine maintenance work entails routine cutting and clearing

of vegetation and debris, repair of road shoulders, culverts, side ditches and canals,

filling of potholes and other minor road and maintenance repair jobs. This is highly labor

intensive work and should fall under the direct responsibility of the Brgy. Chairmen and

the host Barangays.

On the other hand, periodic maintenance entail more extensive work and require the

use of equipment and machineries not available within the Barangays as well as

substantial budget to carry out the task. Thus, the LGU of Abuyog must assume this

responsibility alone or in cooperation and partnership with the Provincial or National

Government.

5.2. Plan for Management during Construction, Key Roles and Responsibilities and

Implementation Arrangements

A Municipal Project Management and Implementation Unit (MPMIU) shall be created by

the Municipal Mayor through an Executive Order to carry out the project activities and

accomplish the corresponding outputs during the pre-investment, project implementation

and post-implementation stages of the project as shown in the Project Organization,

Critical Activities and Project Output Chart (Exhibit 7).

The MPMIU shall be under the direct supervision of the Municipal Mayor with proper

authority and policy direction support from the Sangguniang Bayan (SB). The MPMIU shall

be headed by a Project Manager who shall be tasked with the day-to-day operations

management of the Project. The unit shall be supported by the different critical operating

units/officers of the LGU such as the Municipal Planning Office, Municipal Engineer’s

Page 34: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

27 | P a g e

Office, Municipal Agriculturist, Municipal Treasurer, Budget Officer, Municipal Accountant

and Physical Office and Maintenance Office among others. The different roles and

responsibilities of the key offices/officers to be involved in the project are depicted in Table

21 as follows:

Table 21. Duties and Responsibilities of Offices/Persons Involved in the Project

Office/

Person

Pre-Investment

Phase

Implementation

Phase

Post

Implementation

Phase

Sanggunian

Bayan

(SB)

- Provide the necessary

budgetary allocation,

policy direction/ authority

to the Municipal Mayor to

enter into contract/

agreement with DA-PRDP,

contractors and other

groups/individuals

pursuant to the project.

- Monitor the execution and

implementation of the project.

- Monitor the

operation and

maintenance

of the FMR

Municipal

Mayor/

Local Chief

Executive

(MM/LCE)

- Secure the necessary SB

authority/ budget

allocation;

- Take overall responsibility

in project planning and

mobilization;

- Create the PRDP-MPMIU

through Executive Order;

- Negotiate with DA-PRDP

for project approval;

- Initiate/hold consultation

meetings/dialogues with

Brgy. officials and project

beneficiaries with the

support and assistance of

the PRDP-MPMIU

personnel and the

attached units and

departments.

- Create/organize the BAC that will

be responsible for the conduct of

public Bidding for the project;

- Sign contracts with winning

bidders upon the recom-

mendation of the BAC;

- Provide overall direction and

supervision in project

implementation

- authorize release and liquidation

of project funds;

- conduct regular site inspection

and meetings with contractors

and personnel of PRDP-MPMIU to

asses/evaluate project progress,

and;

- Undertake other necessary

measures needed to ensure

timely completion of the project

in accordance with the

approved plans and budget.

- Monitor the

operation and

maintenance

of the FMR.

Municipal

Project

Manage-

ment and

Implemen-

tation Unit

(MPMIU)

- Serve as technical,

executive and

administrative arm of the

Mayor during the project

planning, mobilization and

social preparation/pre-

investment stage of the

project;

- Conduct and/or facilitate

the preparation of the

necessary Project

Feasibility Study (FS) and

Detailed Engineering

Designs (DED) for

submission to DA-PRDP

with the support and

assistance of the different

LGU support units,

- Take overall responsibility for all

project activities, issues and

concerns during project

execution and implementation;

- Conduct progress monitoring and

evaluation of physical and

financial accomplishments;

- Submit the required

progress/liquidation reports to the

Mayor, DA-PRDP and the funding

agency;

- Procure the needed supplies,

equipment, personnel, logistics

and other support requirements

to ensure timely project

completion;

- Conduct post

project and

impact

evaluation;

- Prepare and

submit as built

plan to DA-

PRDP and

funding

agency;

- Responsible for

routine

maintenance

of the FMR.

Page 35: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

28 | P a g e

Office/

Person

Pre-Investment

Phase

Implementation

Phase

Post

Implementation

Phase

departments and officers

and staff;

- Comply with all the

required technical,

documentary and legal

requirements necessary for

project approval by the

DA-PRDP;

- Conduct consultation/

dialogues with Brgy.

Officials and beneficiaries.

- Take action on any

issues/concerns that may affect

project implementation upon

prior consultation and approval

by the Mayor;

Bids &

Awards

Committee

(BAC)

- Formulate Pre-Bidding/ Bidding

Rules & Regulations in

accordance with Philippine

government and World Bank

Procurement Guidelines;

- Conduct Pre-Bidding

Conferences and actual public

bidding for the project;

- Submit pre/post bidding reports to

the Mayor;

- Recommend to the Mayor the

winner of the public bidding.

Project

Manager

(PM)

- Initiate/lead/coordinate

the preparation and

conduct of pre-

investment/preparatory

activities such as the

conduct of geodetic

surveys, packaging of the

FS,DED, project proposals

and other documentary,

administrative and legal

requirements of the

project;

- Assist the Mayor in

negotiations with DA-

PRDP, World Bank and

other pertinent

government and private

agencies;

- Take the lead in project

mobilization and

preparation upon project

approval.

- Responsible for the day-to-day

operation, implement-tation and

management of the project

including supervision and mgt. of

the MPMIU, its attached units and

personnel;

- Prepare and submit the necessary

progress and liquidation reports

to the Mayor, DA-PRDP and the

funding agency with the

assistance of the other members

and staff of the PRDP-MPMIU;

- Procure the necessary personnel,

materials, equipment and

logistics needed in actual project

implementation;

- Conduct regular site inspections

and meetings with contractors,

Barangay Officials, beneficiaries

to discuss and solve operatio-nal

problems that may surface in the

course of project execution and

implementation, and;

- Represent the Mayor in meetings

and conferences with DA-PRDP,

World Bank and other groups and

institutions relative to the project

when the Mayor cannot attend

or join such meetings and

conferences.

- Conduct post

project impact

evaluation with

the support

and assistance

of the other

members of the

MPMIU;

- Assist the MEO

and MPDO in

the preparation

and formulation

of the As Built

Plan DED;

- Prepare and

submit the

Project

Terminal/Compl

etion Report,

and;

- Supervise the

prompt

liquidation of

project

funds/docume

nts to the DA-

PRDP and

World Bank to

formally close

the project.

Page 36: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

29 | P a g e

Office/

Person

Pre-Investment

Phase

Implementation

Phase

Post

Implementation

Phase

Municipal

Planning &

Develop-

ment Office

(MPDO)

- Take the lead in the

formulation and packaging

of the project Feasibility Study

with the support and

assistance of the members of

the MPMIU;

- Conduct the necessary social

preparation and validation

activities such as inventory of

affected persons, IPs, homes

and properties among others;

- Conduct the necessary

consultations and dialogues

with the beneficiaries,

affected persons, IPs and

other stakeholders, and;

- Secure the necessary

CNC/ECC form DENR.

- Undertake periodic progress

monitoring and evaluation on

the physical and financial

accomplishments of the

project together with the PM

and MEO;

- Assist the PM in

the conduct of

post-project

impact

evaluation and

preparation of

the Project

Terminal/Compl

etion Report.

Municipal

Engineer’s

Office

(MEO)

- Take the lead in the conduct

of geodetic surveys to

determine the direct path

and location of the FMR;

- Prepare and package the

Detailed Engineering Design

(DED) of the project with the

support of the PM, MPDO,

MAO, BO and other members

of the MPMIU;

- Manage/supervise the

rehabilitation and concreting

of the FMR;

- Tendering/procurement of

civil works, materials, services

and logistics

- Assist the PM and MPDO in

the conduct of progress

monitoring and evaluation of

the physical and financial

accomplishments of the

project

- Assist in the

operation and

maintenance

of the FMR

most

particularly in

the conduct of

periodic

maintenance

work of the

FMR.

Municipal

Agriculture

Office

(MAO)

- Provide accurate, realistic

and updated data and

statistics on the past and

current situation of the

agriculture sector of the

municipality and the

beneficiary Barangays;

- Assist the MPDO in the

inventory of affected crops

and trees and preparation of

the FS

- Assist farmer beneficiaries in

marketing their agricultural

products

- Provide training,

logistics and

material support

to farmer

beneficiaries to

expand

production

volume and

income.

Municipal

Budget

Office

(MBO)

- Take principal responsibility in

the procurement/availability

of counterpart fund for the

project.

- Secure funding for the

conduct of geodetic surveys,

FS, DED and other

preparatory activities for the

project.

- -

Page 37: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

30 | P a g e

Office/

Person

Pre-Investment

Phase

Implementation

Phase

Post

Implementation

Phase

Municipal

Treasurer’s

Office/

Municipal

Accountant’s

Office

(MTO/MAO)

-

- Manage the financial

aspect of the project;

- Ensure the appropriate and

timely disbursement and

liquidation of project funds;

- Take the lead in preparing

the regular

financial/liquidation reports

of the project in

coordination with the PM

and MBO.

- Prepare and

submit the

Terminal

Financial/Liquid

ation reports of

the project

Barangay

Chairmen/

Beneficia-

ries (BC/B)

- Ensure participation of Brgy.

residents/beneficiaries

during public hearings and

consultations

- Provide manpower/labor

services to the project

- Responsible for

the conduct of

routine

maintenance

work/activities

of the FMR

5.3 Collection of Road Users Fees and Other Policies

The Local Government Code of the Philippines empowers the Barangays to collect fees

from vehicles plying the route regularly such as delivery trucks that collect coconuts and

other agricultural products from the barangays and nearby areas and deliver basic goods

to the households. Thus, Barangays Suba, Kanangkaan, San Vicente and San Juan may

pass Barangay Road Users’ Ordinances to generate additional income for the barangays

that they may use for the repair and maintenance of the FMR.

5.4 Project Implementation Schedule

The proposed project shall be awarded and contracted to the lowest winning bidder as a

result of a Public Bidding conducted by the BAC in accordance with the Philippines and

World Bank Procurement Guidelines.

Project implementation shall commence seven (7) days after issuance and receipt of the

Notice to Proceed (NTP) by the winning Contractor up to the estimated project completion

period of 80 calendar days.

5.5 Project Monitoring and Supervision

Project Monitoring and Supervision shall be the responsibility of the Municipal Project

Management and Implementation Unit (MPMIU). Specifically, the Project Manager,

Municipal Planning and Development Officer (MPDO) and the Municipal Engineer/ Officer

(ME/O) who are key members of the MPMIU shall comprise the Project Monitoring and

Supervision Team (PMST) for the project. The PMST will be complemented by the Mayor

who shall be doing her own monitoring on the progress of the project being the Local Chief

Executive (LCE) of Abuyog LGU, the principal project proponent. The Sangguniang Bayan

(SB) shall also monitor the progress of the project on account of the authority it shall give

to the Mayor and for its own legislative agenda.

Page 38: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

31 | P a g e

5.6 Operation and Maintenance Scheme

Operation and maintenance work on the FMR shall be the joint responsibilities of the

Abuyog LGU and the beneficiary Barangays. As such, both local government units shall

allocate its own yearly budget for the operation and maintenance of the FMR to ensure its

long term usability and sustainability. Table 22 depicts the annual maintenance budget

matrix.

Road maintenance works are categorized as Routine and Periodic Maintenance. Routine

Maintenance is done every quarter and is normally labor-intensive. Works involve

vegetation control, cleaning and repair of culverts, reshaping of side ditches and canals,

filling of ruts and holes among others. With this kind and magnitude of maintenance works,

the barangay beneficiaries would be the logical holder of this responsibility. It would even

strengthen their chance to pass a Barangay Ordinance to collect road users’ fees from

motorists that use the FMR regularly.

Periodic Maintenance on the other hand, requires more extensive work and use of

equipment that are not normally or readily available in the barangays. Thus, the LGU of

Abuyog on account of its financial and management capability must assume total

responsibility for this kind of maintenance work.

Table 22. Annual Maintenance Cost, Portland Cement Concrete Pavement (PCCP)

Costs Unit 1 2 3 4 5 6

Road length

= 2.02370 km

Annual (Routine)

Maintenance cost PhP 77,446 77,446 77,446 77,446 77,446 77,446

Capital (Periodic)

Maintenance Cost,

every 6th year 1/

PhP 0 0 0 0 0 46,468

Total Annual

Maintenance Cost PhP 77,446 77,446 77,446 77,446 77,446 123,914

1/ Approximately +60% of annual maintenance cost

Page 39: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

32 | P a g e

D. Social Analysis

6.1 Project Beneficiaries

The project will directly benefit Barangays Tabigue and Balocawehay. The two barangays

have a combined population of 4,767 of which 2,454 (51.5 %) are males and 2,313 (48.5 %)

are females living in 1,046 households. (Please refer to Table 26 on page 37 on population

within the Road Influence Area Barangays). Majority of the beneficiaries are farmers

engaged in the cultivation of rice, coconuts, corn, vegetables and root crops. The

beneficiaries are eagerly awaiting the implementation of the project considering that the

road segment has been in a sorry state of disrepair for a long time.

The constituents of Brgys. Balocawehay and Tabigue were consulted on March 23, 2015 to

generate opinions, comments, views, endorsement and approval by the barangay

officials and residents relative to the project. Those were joint consultations per barangay,

namely, Barangay Council Consultation and Barangay Residents Consultation, attended

by barangay officials and residents including women. A team from the LGU-Abuyog

conducted the consultations and briefing.

During the open forum, questions raised by the attendees mainly centered on where is the

start and end (or length) of the road project and when will the project construction start.

They also expressed their anxiety that the 2-km. road project might end up into only a 200-

meter finished road, hinting of corruption in project implementation. The LGU team ably

answered all queries and gave assurance that the road project will have desired results.

After a thorough and exhaustive discussions on the matter, the Brgy. officials and residents

unanimously approved and endorsed the project. The Resolutions of the Sangguniang

Barangays and the Minutes of Barangay Assemblies and consultations are found in

Annexes 2-I and 2-J.

6.2 Indigenous Cultural Community/Indigenous Peoples (ICC/IP)

The sub-project will not infringe or disturb any indigenous cultural community since there

are no cultural minorities living within the area. Likewise, the sub-project will not encroach

or traverse in any ancestral domain considering that there are no ancestral domains in the

whole of Region 8.

Nevertheless, the Abuyog LGU has requested for a Certificate of Non-Overlap (CNO) from

the National Commission for Indigenous Peoples (NCIP). Likewise, the Municipal Mayor

issued a certification that the re is no existing indigenous cultural community or settlement

within the municipality of Abuyog. (See Annex 2-H).

6.3 Site and Right-of-Way Acquisition

The proposed site is an existing 2.02370 kms. barangay road. The right-of-way has been

acquired during construction of the road opening under the previous InFRES program. The

LGU-Abuyog was able to secure 10 meters of right-of-way through donation and/or

acquisition and the owners were properly compensated, so there is no need to secure

another right-of-way since the proposed sub-project will only have a maximum of 8 meters

width inclusive of 1.5 meters shoulder on each side of the road. (The RROW Certification,

Tax Declaration showing MLGU ownership on the acquired RROW and Parcellary Map are

shown in Annexes _______________.)

Page 40: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

33 | P a g e

6.4 Damage to Standing Crops, Houses and/or Properties

There are a few new growth coconut trees in the shouder of the barangay road as well as

shrubs and grasses. These need to be removed. There are minor structures like waiting shed

along the road shouder but such is made of temporary and light materials that can be

easily removed. All the safeguards necessary for the removal of the impediments shall be

complied with accordingly by using Form 1 & 2 for SES.

6.5 Physical Displacement of Persons

There are no houses that will be affected or relocated during the project so no persons will

be displaced during and after project completion.

6.6 Economic Displacement of Persons

Being an existing road, no persons will be economically displaced or alienated from their

traditional livelihoods during construction. On the contrary, local residents may find direct

or indirect opportunities as laborers, workers and vendors among others during the road

project implementation.

Page 41: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

34 | P a g e

E. Environmental Assessment

7.1 Natural Habitat

The proposed project is not within any protected area or wild life sanctuary nor will it entail

cutting of trees therefore, the natural environment will not be disturbed or affected in any

manner.

7.2 Physical Cultural Resources

There are no historical, cultural, monuments and other physical structures of national

cultural value within the project area that will be affected by the rehabilitation and

concreting works.

7.3 Terrain, Soil Types and Rainfall

The terrain in the project area is basically flat and sprawling fertile plains with no hills nor

mountainous. The whole land area is within the 5% slope limit which is generally flat.

There are five types of soils within the sub-project area. Soil fertility is relatively high

considering that silts and other fertile soil colloids from the upland areas are carried and

deposited by the various river systems into the low lying areas especially during rainy

seasons and seasonal flooding.

The area has no pronounced wet and dry season. Rainfall is almost evenly distributed

throughout the year with an average rainfall of 167.4 mm with maximum rainfall usually

recorded in the months of November to February. Minimum rainfall (100mm/month) usually

occurs in the months of April to May and August to September. There is no single dry month

in these areas. The cool months are October to December each year.

7.4 Drainage Situations and Flooding Potential

With rains evenly distributed throughout the year, the road surface areas and road

shoulders are always under threat of rain water and flooding. These will be mitigated by

introducing road cambers leading the water runoff immediately outside of the roadway

into the intercepting canals and drainage outlets and own to the receiving rivers and

streams. Likewise, trees shall be planted at the edges of the road shoulders to mitigate the

flow of rain water to the road surface and shoulders.

7.5 Impacts During Construction

7.5.1 Temporary Erosion and Sediment Control

Erosion and sediment control in construction areas will prevent sediment discharge to

nearby streams and rivers. Areas cleared of vegetation for construction and roadway

development would be minimized and slopes would be stabilized. Overland drainage

would be controlled to prevent channelling and sediment transport by diverting flows

from areas where soils are exposed, and/or by providing filter barriers or settling basins

to remove sediment before the runoff is discharged to surface waters.

Page 42: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

35 | P a g e

7.5.2 Construction Noise Mitigation

There are houses and establishments along and nearby the construction site especially

along the built-up areas. The construction involves the operation of heavy equipment

and will undoubtedly generate loud noises. As a mitigating measure, work activities

should be avoided during quiet periods of the day.

7.5.3 Proper Handling of Construction Wastes

The sub-project will generate surplus common excavation materials and debris.

Disposal sites have been identified to haul these surpluses outside the limits of the road

right of way. This will minimize the amount of site litters and will prevent the

indiscriminate dumping of surpluses along the roadsides. Assurances is made by the

LGU that these wastes will be collected and properly disposed of in accordance with

government regulations.

7.5.4 Public and Worker’s Safety

Safety of workers and the public is a must and shall be given utmost priority. Standard

construction safety protocols shall be observed and enforced at all times, such as

posting of road signs, among others.

7.6 Status of Environmental Clearances

The LGU-Abuyog has been issued a Certificate of Non-Coverage (CNC) by the EMB-

DENR (see Annex 2-D). Likewise, it has pending applications for Environmental

Clearance Certificate (ECC), Quarry Permit (QP) and other government regulatory

clearances required for this project. It is expected that all these clearances will be

obtained by the LGU before actual project implementation.

Page 43: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

36 | P a g e

F. Financial Analysis

8.1 Total Project Cost by Financing Source and Cost Sharing

The Total Project Cost (TPC) was computed and derived based on the following:

(a) Field survey results;

(b) Detailed Engineering Design (DED);

(c) prevailing prices of construction materials;

(d) prevailing labor cost in the municipality (but not below the official minimum wage);

(e) prevailing rental cost of equipment in the municipality; and

(f) other relevant information.

Table 23. Total Project Cost by Financing Source and Cost Sharing

Source Amount % Sharing

Loan / Grant (WB) 12,081,713.91 80%

GOP counterpart 1,510,214.24 10%

Equity: LGU counterpart 1,510,214.24 10%

Total Project Cost (TPC) 15,102,142.39 100%

Source: EFA_Tabigue-BalocawehayFMR_Tab1_Econ. Cost Revised

As shown in Table 23, the total investment requirement is Php 15,102,142. Per PRDP

guidelines, 90% of TPC will be financed by the Government of the Philippines (GOP) in the

form of a grant, composed of 80% loan proceeds from the World Bank (WB) and 10% GOP

counterpart. The LGU of Abuyog will provide the remaining 10% as counterpart funding in

the form of cash in the amount of Php 1,510,214.

8.2 Total Project Cost Breakdown

Table 24. Total Project Cost Breakdown

Particular Amount Percent

A. Direct Cost (DC) 11,539,672.03 76.4 %

1. Materials Cost 8,573,593.60 56.8 %

2. Labor Cost 294,843.26 2.0 %

3. Equipment Expenses 2,671,235.18 17.7 %

B. Indirect Cost 3,562,470.36 23.6%

1. Overhead, Contigencies and 1,029,379.59 6.8 %

Miscellaneous Expenses (OCM) – 9% of DC

2. Contractor’s Profit (CP) – 8% of DC 915,004.08 6.1 %

3. VAT Component (12% of DC+OCM+CP) 1,618,086.68 10.7 %

Estimated Project Cost (EPC) 15,102,142.39 100%

Source: EFA_Tabigue-BalocawehayFMR_Tab1_Econ. Cost Revised

Page 44: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

37 | P a g e

8.2.1 Direct Costs

Direct costs amounted to Php 11,539,672 or 76.4 % of TPC. It is composed of cost of

materials (56.8 %), equipment expenses (17.7 %) and cost of labor (2.0 %).

8.2.2 Indirect Costs

On the other hand, indirect costs totaled to Php 3,562,470 or 23.6 % of TPC. It includes

expenses on overhead, contingencies & miscellaneous (6.8 %) and contractor’s profit

(6.1 %). Value-added tax (VAT) is 10.7 % of TPC.

8.3 Status of LGU Equity availability and LFC Certification

The LGU of Abuyog has set aside a budget equivalent to the required cash counterpart of

Php 2,021,938.65 or 10% of TPC. This amount will be sourced from local funds of Abuyog

LGU. Likewise, there is a standby credit line with Land Bank of the Philippines (LBP) in case

of a need for funding augmentation. A certification from the Local Finance Committee

(LFC) evidencing the availability of funds is in Annex 2-C.

Page 45: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

38 | P a g e

G. Economic Analysis and Evaluation

9.1 The Project Influence Area

9.1.1 Agricultural Production in the Project Influence Area

Barangays Tabigue and Balocawehay are the direct road influence areas of the sub-

project. They are part of the identified economic growth zones in the Comprehensive

Land Use Plan (CLUP) of the municipality.

Table 25 shows the major agricultural crops of the two barangays. Rice (palay) is widely

produced with a combined area of 462 hectares devoted to it. The next major crop

cultivated is coconut (copra) with 353 hectares. Total area cultivated for the top 5 crops

(including corn, abaca and banana) is around 868 hectares.

Table 25. Agricultural Production Areas (has.), Production Volumes (kgs.) and Values

(Php) of Crops in the Road Influenced Area, 2014.

Crop

Area

Planted

(in has.)

Average

yield/ha./

cycle (kgs.)

No. of

turnover/

cropping

seasons/yr.

Annual

Production

Volume (kgs.)

Current Farm

Gate

Price/Kg.

(Php)

Total Annual

Production

Value (Php)

Rice 461.69 4,300 2 3,970,620 27.00 107,206,740.00

Coconut 353.25 480 4 678,202 25.00 16,955,040.00

Corn 23.00 750 2 34,500 25.00 862,500.00

Abaca 20.00 375 2 15,000 50.00 750,000.00

Banana 10.13 750 4 30,390 15.00 455,850.00

Total 868.07 4,728,712 126,230,130.00

Source: Abuyog Municipal Agriculturist Office (MAO)

It can be observed from the table that rice ranks as the top source of income of the

farmers. Total annual rice production reached 3.97 million kgs. valued at around

Php107.2 million. Coconut/copra production contributes almost Php17.0 million while

corn with Php 0.863 million. Abaca adds Php 0.75 million and banana with Php 0.456

million. Total value of all crops combined is over Php 126.23 million.

9.1.2 Population within the Direct Road Influence Area to Benefit from the Road Project.

The RIA of the proposed sub-project covers the entire geographical and administrative

boundaries of Brgys. Balocawehay and Tabigue.

The two barangays have a combined population of 4,767 of which 2,454 are males and

2,313 are females. There are 1,046 households with average household size of 4.56 as per

DILG-Abuyog’s CBMS Statistics Simulator in 2008. The annual population growth rate of

1.01% which is average for the whole municipality of Abuyog is nearly identical to that of

the whole Leyte province of 1.04%. Economically active population, which is 35% of total

population and are 15 years old and above, is 1,668 persons. Please refer to Table 26 on

the next page.

Page 46: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

39 | P a g e

Table 26. Population within the Road Influence Area (RIA), 2008.

Barangay Population No. of

Households

Economically Active

Population, 15 y.o. & above

(35%)

Balocawehay 3,490 766 1,221

Tabigue 1,277 280 447

Total 4,767 1,046 1,668

Male 2,454 Average Household Size = 4.56 Female 2,313

Average annual population growth rate = 1.01% Source: 2008 Abuyog DILG-CBMS Survey

9.1.3 Existing vehicular traffic based on Traffic Survey Results, indicating representative

vehicles, operating days per year, average daily trips, and travelled distance.

To establish vehicular traffic of the road sub-project, a rapid appraisal (actual survey) on

traffic flow was conducted in November 2014. Results are summarized below.

Table 27. Annual Average Daily Traffic, Brgys. Tabigue-Balocawehay FMR, 2014.

Existing Mode of

Transportation

in the Area

Number

of

Vehicle

units

Average

Operating

Days/

Year

Average

Number

of Daily

Trips

Average

Loading

Capacity

(sacks)

Observed

Transport Fares

for Passenger/

Cargo

Average

Travelled

Distance

(kms.)

Motorcycle/

Habal-habal 39 260 43 8 P30 / P30 2.0237

Tricycle 15 260 35 15 P30 / P30 2.0237

Car / Van 4 156 4 - P30 / 2.0237

Jeepney 2 156 3 50 P30 / P30 2.0237

Truck 6 104 8 100 / P30 2.0237

Note: Rapid appraisal (actual survey) on traffic flow conducted on November 24-30, 2014.

Several modes of transportation are present in the area. Among these, the most

common is “habal-habal” or single motorcycle with 39 units in operation. There are 15

tricycles, six trucks and two jeepneys in operation. There are also four private vehicles

cars. These vehicles are expected to increase in number over the years when the

concreting of the road will be finished.

9.1.4 Transport Fares, Distances Travelled, Travel Times, by Motorized Vehicles

With improved road conditions, farmers and other residents will be able to transport their

farm products, farm inputs and other commodities faster, cheaper and easier. Results of

a rapid appraisal (actual survey) on traffic flow conducted in November 2014 were

summarized in Table 28.

The transport fare for cargo (per sack) and passenger (per head) are not differentiated

for all types of vehicle at Php 30.00. It is expected that transport fares will be reduced

once the rehabilitation and concreting of the sub-project is completed.

Page 47: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

40 | P a g e

Differences in travel times in minutes, without and with project, was also determined. It

takes an average of 10 minutes to traverse the road section with the current/existing

conditions (“without project”) using “habal-habal” as vehicle. On the other hand, it is

expected that with the project, travel time will be reduced to only four (4) minutes.

Table 28. Prevailing Transport Fares by Type of Vehicle, Travel Times and Distances,

Poblacion to RIA Barangays, June 2014.

Distance

(kms.)

Travel Time (one way, in mins.) Prevailing Transport Fare (Php)

w/out Project w/ Project Passenger (per head) Cargo (per sack)

2.0237 10 4 Php 30.00 Php 30.00

Source: Rapid appraisal (actual survey) on traffic flow conducted on November 24-30, 2014

9.1.5 Commuter Time Savings

With improved road condition, commuters within the influence area will be able to

benefit from the reduction in their travel times. As shown in Table 29, the savings in travel

times to traverse the road section (one way) were converted as percent share of saved

time for work.

The table also shows average of two (2) trips per person per day, a 240-day work year

and average daily wage rate of Php 257. Commuter time savings expectedly could

translate into benefits to the economically active residents.

Table 29. Average Travel Time of Commuters, Poblacion to RIA Barangays, Nov. 2014

Distance

(kms.)

Travel Time

(one way, in mins.)

Ave. No. of

Trips per

Person/Day

No. of

Working

Days/Year

% Share of

Saved Time for

Work

Average Daily

Wage Rate

(Php) w/out Project with Project

2.0237 10 4 2 240 53% 257.00

Source: Rapid appraisal (actual survey) on traffic flow conducted on November 24-30, 2014

9.1.6 Benefits of Newly Cultivated Agricultural Land

The rehabilitation and concreting of the road will stimulate the cultivation of potential

land areas for agriculture. Considering the top two (2) profitable crops of the two

barangays, at least 5 additional hectares can be developed for rice cultivation and at

least 2 hectares per year for the next 5 years, or a total of 10 hectares for coconut.

Considering all relevant costs (land development, production and marketing), these new

cultivated lands have the potential to generate additional revenues/benefits to the

locality and the municipality as a whole.

Table 30. Benefits of Newly Cultivated Agricultural Land

Crop Area

(Has.)

Potential Land

for Cultivation

(Has.)

Farm Gate

Price/Sack

(Php)

Land Dev’t.

Cost per Ha.

(Php)

Production

Cost per Ha.

(Php)

Marketing

Cost per

Sack (Php)

Rice 462 5 25.00 25,000 15,000 15.00

Coconut 353 10 27.00 33,500 13,500 15.00

Total 815 15

Page 48: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

41 | P a g e

9.2 Economic Benefits

The road concreting sub-project when completed will certainly bring tangible and intangible

socio-economic benefits to Barangays Balocawehay and Tabigue and the municipality of

Abuyog as a whole.

The quantifiable benefits ensuing from the project completion are the following:

9.2.1 Vehicle Operating Cost Savings (VOCS)

This was calculated from the projected average annual daily traffic data multiplied by the

vehicle operating cost difference (changes in VOC with and without project scenarios)

and the actual road length.

9.2.2 Transport Cost Savings In Hauling Agricultural Outputs And Inputs

For the purpose of estimating this benefit, only the top three agricultural commodities of

the area (rice, coconut and corn) were considered. The benefit was computed based on

the difference in hauling cost under current and improved (concrete) road conditions

multiplied by quantity of produce that is to be marketed. Likewise, savings in hauling costs

of inputs of production to the farm was also computed using the changes in transport costs

with and without the road project multiplied by the estimated quantity of required inputs,

primarily fertilizers and seeds.

9.2.3 Reduction In Travel Times From Farm To Market In Subproject Areas

The savings in travel time is derived by using the assumption that commuters will benefit

from the changes (reduction) in their travel time, which would translate to increase in

productive time per capita.

9.2.4 Incremental Increase In Crops Production Attributed To Newly Opened Croplands.

Benefits that can be derived from potential agricultural areas that can be cultivated and

used for additonal crop productions (primarily coconut and rice) because of the sub-

project were also included.

9.2.5 Other benefits

Other benefits that may happen once the road section is fully rehabilitated and concreted

under the proposed project are the following:

Increase in volume of commerce and trade for local products, basic commodities and

manufactured goods;

Increase in the number of passenger motorcycles, cargo trucks and private vehicles

plying the area;

Increased traffic volume of people, goods and services traversing the road section

Government services delivery will be more efficient and accessible for and by the

people living in the area;

Pre- and post-harvest facilities and extension services will be improved;

More primary, secondary and tertiary employment will be generated;

School participation rate among pre-elementary, primary and secondary school

children will increase.

Page 49: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

42 | P a g e

9.3 Economic Costs

9.3.1 Capital Cost and O & M Cost Breakdown

Table 31 shows in economic terms, the total amount of investment for the sub-project,

which is Php 13,526,994 and annual operating and maintenance cost amounting to Php

77,446. It must be noted that capital (periodic) maintenance is undertaken every six years

and is approximately 60% higher than regular annual maintenance cost at Php 123,914.

Table 31. Total Investment and Operating & Maintenance Costs of Sub-project

Year Total Investment

Cost

Operating &

Maintenance Cost

Year

Operating &

Maintenance Cost

0 13,526,994

1 77,446 11 77,446

2 77,446 12 123,914

3 77,446 13 77,446

4 77,446 14 77,446

5 77,446 15 77,446

6 123,914 16 77,446

7 77,446 17 77,446

8 77,446 18 123,914

9 77,446 19 77,446

10 77,446 20 77,446

Source: EFA_Tabigue-Balocawehay FMR_Tab2_InvestCost

9.4 Direct Jobs from Construction

The LGU of Abuyog will see to it that residents of the RIA barangays and/or nearby barangays

will have priority for employment as laborers in the road sub-project implementation. The sub-

project would need skilled laborers (66% of total labor cost) and unskilled workers (34% of total)

for a total economic cost of labor at Php 240,809.

Unskilled laborers will be assigned as helpers in road concreting, installation of drainage

facilities, and as helpers to heavy equipment operators. Skilled laborers will be hired as team

leaders for various works and as operators of heavy equipment.

9.5. Adjustment of Financial Values to Economic Terms

The total financial cost amounts to Php 16,256,109.60 which comprises the materials,

equipment and labor costs, as well as overhead, contingencies & miscellaneous expenses,

contractor’s profit, and 12% value-added tax. The cost of feasibility study, detailed enginnering

design preparation and engineering supervision is also included, although it is to the account

of LGU-Abuyog. Using the necessary conversion factors provided by PRDP, financial cost is now

adjusted to total economic cost of Php 13,526,993.88. Please refer to Table 32.

Page 50: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

43 | P a g e

Table 32. Investment Costs of Sub-project (Financial & Economic)

Cost Item Financial Cost

(current prices)

Conversion

factors Economic Cost

Materials 8,573,593.60 0.12 7,750,528.61

Equipment 2,671,235.18 2,671,235.18

Labor: Skilled 159,758.17 159,758.17

Unskilled 135,085.09 0.60 81,051.05

Subtotal Labor 294,843.26 240,809.22

Total Base/Direct Cost 11,539,672.03 10,662,573.01

Overhead, Contingencies and

Miscellaneous (OCM) 1,029,379.59 0.12 919,088.92

Contractor’s Profit 915,004.08 915,004.08

Total (Base/Direct Cost + OCM + CP) 13,484,055.71 12,496,666.02

Taxes (12% on DC+OCM+CP) 1,618,086.68 0.00

FS & DED Preparation + Engineering

Supervision (10% of DC) * 1,153,967.20 0.12 1,030,327.86

Total Cost 16,256,109.60 13,526,993.88

* - Cost incurred will be shouldered by the proponent LGU.

Source: EFA_Tabigue-Balocawehay FMR_Tab1_Econ. Cost Revised

9.6 Results of the Economic Analysis The results of the economic analysis are very encouraging.

9.6.1 Economic Internal Rate of Return (EIRR) = 37.32 %

The EIRR equates the present values of the net incremental benefits with the

amount of the initial investment; that is, it is that rate which makes the net present

value (NPV) equal to zero. The computed EIRR of the proposed sub-project is

37.32% which is more than double the required 15%.

9.6.2 Benefit-Cost Ratio (BCR) = 2.42

BCR is the ratio of the present value of gross benefits to the present value of its cost.

It should be >1 for a project to be considered favorably. The BCR of the proposed

sub-project is 2.42 evaluated using 15% discount rate. In simple terms, for every

Php1.00 of cost, the benefit is equivalent to Php 2.42.

9.6.3 Economic Net Present Value (ENPV) = Php 19,957,413.00

ENPV is the difference between the present worth of the benefits that the project

is expected to yield and the present worth of the construction and maintenance

cost incurred. The ENPV evaluated at 15% discount rate is Php 19,957,413.

9.7 Economic Sensitivity Analysis Results

Sensitivity analysis is being done to test the susceptibility of the proposed project to changes

in variables that directly affect its economic viability. The resulting EIRR, ENPV and BCR are then

evaluated as to the required rates or amounts. These are also compared to that of a base

scenario (no increases nor decreases).

Page 51: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

44 | P a g e

Table 33 shows that in all test case scenarios, the EIRR, ENPV and BCR results remain at

acceptable levels. Even with a delay of benefits for 2 years and no benefits accruing from new

agricultural areas cultivated, the indicators are way above the required rates. Hence, the

project proved to be generally robust and unwavering to changes.

Table 33. Sensitivity Analysis, 20-Year Period

Measures Base

scenario

Costs Increase Increase of Benefits Decrease of Benefits Delay of

Benefits No

Bene-

fits * +10% +20% +50% +10% +20% +30% -10% -20% -30% 1 year 2 years

EIRR 37% 34% 31% 25% 41% 45% 48% 34% 30% 26% 24% 18% 31%

ENPV

(PhP’000) 19,957 18,553 17,149 12,935 23,358 26,758 30,158 16,557 13,157 9,757 11,597 4,058 13,457

BCR 2.42 2.20 2.02 1.61 2.66 2.91 3.15 2.18 1.94 1.69 1.83 1.29 1.96

* No benefits deriving from new agricultural land

Source: EFA_Tabigue-Balocawehay FMR_Tab10_Sensitivity Analysis

9.8 List of Attached Models /Detailed Tables of EFA Templates (Please see Annex)

a. Table 34. Economic Analysis

b. Table 35. Sensitivity Analysis

c. Table 36. Investment and Maintenance Costs

d. Table 37. Annual Road Maintenance Cost

e. Table 38. Transport Data by Vehicles Type

f. Table 39. Projected No. of Vehicles per Day

g. Table 40. Projected Annual Average Daily Traffic (AADT)

h. Table 41. Standard Vehicle Operating Cost Savings

i. Table 42. Total Annual Vehicle Operating Cost Savings by Vehicle Type

j. Table 43. Benefits - Vehicle Operating Costs (VOC) Savings

k. Table 44. Benefits - Savings in Output Hauling

l. Table 45. Benefits - Savings in Input Hauling

m. Table 46. Benefits - Savings in Travel Time for Commuters

n. Table 47. Benefits of Newly Cultivated Agricultural Land

H. Conclusions and Recommendations

10.1 Conclusions

The findings of this study are very conclusive and serve to reinforce the initial stand that the

proposed sub-project is feasible in all aspects of marketing, technical, operational, social and

environmental dimensions. Moreover, the results of the financial and economic analysis all the

more support this contention.

10.2 Recommendations

With the aforementioned conclusion, the municiplaity of Abuyog, Leyte is highly

recommending for the approval of this feasibility study and implementation of the proposed

road project since it is highly regarded to contribute largely to the social and economic well-

being of the farmers and other residents within the influence areas, as well as the surrounding

barangays, to the municipality of Abuyog and to the province of Leyte as a whole.

Page 52: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

45 | P a g e

ANNEX 1: Models/Detailed Tables of EFA Templates Table 34. Economic Analysis

Inputs (Php'000) 0 1 2 3 4 5 6 7 8 9 10

Total Investment (Economic Value) 13,527 - - - - - - - - - -

Total Operating (Maintenance) Cost - 77 77 77 77 77 124 77 77 77 77

Total Inputs 13,527 77 77 77 77 77 124 77 77 77 77

Incremental Benefits (Php'000)

VOC Savings 2,829 2,858 2,887 2,916 2,946 2,976 3,006 3,037 3,068 3,099

Savings in Output Hauling Costs 618 618 618 618 618 618 618 618 618 618

Savings in Input Hauling Costs 198 198 198 198 198 198 198 198 198 198

Savings in Travel Time for Commuters 410 434 461 489 518 550 583 618 656 696

Earnings fr. New Cultivated Agri. Land 791 916 916 916 916 983 1,058 1,133 1,208 1,283

Total Incremental Benefits 0 4,846 5,024 5,080 5,137 5,196 5,325 5,463 5,604 5,748 5,894

Net Incremental Benefits (Php'000) (13,527) 4,768 4,947 5,002 5,060 5,119 5,201 5,386 5,527 5,670 5,816

Inputs (Php'000) 11 12 13 14 15 16 17 18 19 20

Total Investment (Economic Value) - - - - - - - - - -

Total Operating Cost (Maintenance) 77 124 77 77 77 77 77 124 77 77

Total Inputs (Php'000) 77 124 77 77 77 77 77 124 77 77 Incremental Benefits (Php'000)

VOC Savings 3,130 3,162 3,194 3,227 3,260 3,293 3,326 3,360 3,394 3,429

Savings in Output Hauling Costs 618 618 618 618 618 618 618 618 618 618

Savings in Input Hauling Costs 198 198 198 198 198 198 198 198 198 198

Savings in Travel Time for Commuters 738 782 830 880 934 990 1,050 1,114 1,181 1,253

Earnings fr. New Cultivated Agri. Land 1,359 1,359 1,359 1,359 1,359 1,359 1,359 1,359 1,359 1,359

Total Incremental Benefits (Php'000) 6,043 6,119 6,199 6,282 6,368 6,457 6,551 6,648 6,750 6,856

Net Incremental Benefits (Php'000) 5,965 5,995 6,121 6,204 6,290 6,380 6,474 6,525 6,673 6,779

Economic NPV @15% (Php ’000) 19,957.41 Total Present Value of Project Benefits (Php ’000) 34,001.70

EIRR 37.32% Total Present Value of Project Costs (Php ’000) 14,044.29

BCR 2.42 Net Present Value (NPV) (Php ’000) 19,957.41

Source: EFA_Tabigue-Balocawehay FMR_Tab9_EconAnalysis

Page 53: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

46 | P a g e

Table 35. Sensitivity Analysis on Costs, Benefits and Delays (Php‘000) Note: Discount rate= 15%

Scenarios Year 0 1 2 3 4 5 6 7 8 9 10

Incremental Benefits

base scenario 0 4,846 5,024 5,080 5,137 5,196 5,325 5,463 5,604 5,748 5,894

benefits +10% 0 5,330 5,527 5,588 5,651 5,716 5,857 6,010 6,165 6,323 6,483

benefits +20% 0 5,815 6,029 6,096 6,164 6,235 6,389 6,556 6,725 6,897 7,073

benefits +30% 0 6,299 6,532 6,604 6,678 6,755 6,922 7,102 7,286 7,472 7,662

benefits -10% 0 4,361 4,522 4,572 4,623 4,677 4,792 4,917 5,044 5,173 5,305

benefits -20% 0 3,877 4,020 4,064 4,110 4,157 4,260 4,371 4,483 4,598 4,715

benefits -30% 0 3,392 3,517 3,556 3,596 3,637 3,727 3,824 3,923 4,023 4,126

benefits delayed 1 year 0 -4,846 5,024 5,080 5,137 5,196 5,325 5,463 5,604 5,748 5,894

benefit delayed 2 years 0 -4,846 -5,024 5,080 5,137 5,196 5,325 5,463 5,604 5,748 5,894

no benefit from new agri. land 0 4,055 4,109 4,164 4,221 4,280 4,342 4,405 4,471 4,540 4,611

Project Costs

base scenario 13,527 77 77 77 77 77 124 77 77 77 77

costs +10% 14,880 85 85 85 85 85 136 85 85 85 85

costs +20% 16,232 93 93 93 93 93 149 93 93 93 93

costs +50% 20,290 116 116 116 116 116 186 116 116 116 116

costs delayed 1 year 13,527 0 77 77 77 77 124 77 77 77 77

costs delayed 2 years 13,527 0 0 77 77 77 124 77 77 77 77

Net Incremental Benefits

base scenario -13,527 4,768 4,947 5,002 5,060 5,119 5,201 5,386 5,527 5,670 5,816

costs +10% -14,880 4,761 4,939 4,994 5,052 5,111 5,188 5,378 5,519 5,663 5,809

costs +20% -16,232 4,753 4,932 4,987 5,044 5,103 5,176 5,370 5,511 5,655 5,801

costs +50% -20,290 4,730 4,908 4,964 5,021 5,080 5,139 5,347 5,488 5,632 5,778

benefits +10% -13,527 5,253 5,449 5,510 5,573 5,638 5,733 5,932 6,087 6,245 6,406

benefits +20% -13,527 5,737 5,952 6,018 6,087 6,158 6,266 6,478 6,648 6,820 6,995

benefits + 30% -13,527 6,222 6,454 6,526 6,601 6,678 6,798 7,025 7,208 7,395 7,585

benefits -10% -13,527 4,284 4,445 4,494 4,546 4,599 4,668 4,840 4,966 5,096 5,227

benefits -20% -13,527 3,799 3,942 3,986 4,032 4,080 4,136 4,293 4,406 4,521 4,638

benefits -30% -13,527 3,315 3,440 3,478 3,518 3,560 3,603 3,747 3,846 3,946 4,048

benefits delayed 1 year -13,527 -4,846 4,947 5,002 5,060 5,119 5,201 5,386 5,527 5,670 5,816

benefits delayed 2 years -13,527 -4,846 -5,024 5,002 5,060 5,119 5,201 5,386 5,527 5,670 5,816

no benefit from new agri. land -13,527 3,977 4,031 4,086 4,144 4,203 4,218 4,328 4,394 4,462 4,533

Page 54: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

47 | P a g e

Table 35. Sensitivity Analysis on Costs, Benefits and Delays (Php‘000)

Scenarios Year 11 12 13 14 15 16 17 18 19 20 PV a/

Incremental Benefits

Base Scenario 6,043 6,119 6,199 6,282 6,368 6,457 6,551 6,648 6,750 6,856 34,002

benefits +10% 6,647 6,731 6,819 6,910 7,005 7,103 7,206 7,313 7,425 7,542 37,402

benefits +20% 7,251 7,343 7,439 7,538 7,641 7,749 7,861 7,978 8,100 8,228 40,802

benefits +30% 7,856 7,955 8,058 8,166 8,278 8,395 8,516 8,643 8,775 8,913 44,202

benefits -10% 5,438 5,507 5,579 5,653 5,731 5,812 5,896 5,984 6,075 6,171 30,602

benefits -20% 4,834 4,895 4,959 5,025 5,094 5,166 5,241 5,319 5,400 5,485 27,201

benefits -30% 4,230 4,283 4,339 4,397 4,457 4,520 4,586 4,654 4,725 4,799 23,801

benefits delayed 1 year 6,043 6,119 6,199 6,282 6,368 6,457 6,551 6,648 6,750 6,856 25,574

benefit delayed 2 years 6,043 6,119 6,199 6,282 6,368 6,457 6,551 6,648 6,750 6,856 17,976

no benefit from new agri. land 4,684 4,761 4,840 4,923 5,009 5,099 5,192 5,290 5,392 5,498 27,501

Project Costs

Base Scenario 77 124 77 77 77 77 77 124 77 77 14,044

costs +10% 85 136 85 85 85 85 85 136 85 85 15,449

costs +20% 93 149 93 93 93 93 93 149 93 93 16,853

costs +50% 116 186 116 116 116 116 116 186 116 116 21,066

benefits delayed 1 year 77 124 77 77 77 77 77 124 77 77 13,977

benefit delayed 2 years 77 124 77 77 77 77 77 124 77 77 13,918

Net Incremental Benefits EIRR ENPV a/ BCR

Base Scenario 5,965 5,995 6,121 6,204 6,290 6,380 6,474 6,525 6,673 6,779 37.3% 19,957 2.42

costs +10% 5,958 5,983 6,114 6,196 6,283 6,372 6,466 6,512 6,665 6,771 34.0% 18,553 2.20

costs +20% 5,950 5,971 6,106 6,189 6,275 6,365 6,458 6,500 6,657 6,763 31.2% 17,149 2.02

costs +50% 5,927 5,933 6,083 6,165 6,252 6,341 6,435 6,463 6,634 6,740 25.0% 12,935 1.61

benefits +10% 6,570 6,607 6,741 6,832 6,927 7,026 7,129 7,189 7,348 7,464 41.0% 23,358 2.66

benefits +20% 7,174 7,219 7,361 7,460 7,564 7,672 7,784 7,854 8,023 8,150 44.6% 26,758 2.91

benefits + 30% 7,778 7,831 7,981 8,089 8,201 8,317 8,439 8,519 8,698 8,836 48.2% 30,158 3.15

benefits -10% 5,361 5,383 5,501 5,576 5,654 5,734 5,818 5,860 5,998 6,093 33.7% 16,557 2.18

benefits -20% 4,757 4,771 4,882 4,948 5,017 5,089 5,163 5,195 5,323 5,408 30.0% 13,157 1.94

benefits -30% 4,152 4,160 4,262 4,320 4,380 4,443 4,508 4,530 4,648 4,722 26.3% 9,757 1.69

benefits delayed 1 year 5,965 5,995 6,121 6,204 6,290 6,380 6,474 6,525 6,673 6,779 24.1% 11,597 1.83

benefits delayed 2 years 5,965 5,995 6,121 6,204 6,290 6,380 6,474 6,525 6,673 6,779 17.6% 4,058 1.29

no benefit from new agri. land 4,607 4,637 4,763 4,846 4,932 5,022 5,115 5,166 5,314 5,420 30.6% 13,457 1.96

a/ - Discount rate= 15% Source: EFA_Tabigue-Balocawehay FMR_Tab10_SensitivityAnalysis

Page 55: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

48 | P a g e

Table 36. Investment and Maintenance Costs

Costs Year 0 1 2 3 4 5 6 7 8 9

Total Investment (Economic value) 13,526,994 - - - - - - - - -

Total Operating (Maintenance) Cost 77,446 77,446 77,446 77,446 77,446 123,914 77,446 77,446 77,446

Total Inputs 13,526,994 77,446 77,446 77,446 77,446 77,446 123,914 77,446 77,446 77,446

Costs Year 10 11 12 13 14 15 16 17 18 19 20

Total Operating

(Maintenance) Cost 77,446 77,446 123,914 77,446 77,446 77,446 77,446 77,446 123,914 77,446 77,446

Total Inputs 77,446 77,446 123,914 77,446 77,446 77,446 77,446 77,446 123,914 77,446 77,446

Note: Total operating (maintenance) cost is approx. +60% of annual operating cost every six years. Source: EFA_Tabigue-Balocawehay FMR_Tab2_InvestCost

Table 37. Annual Road Maintenance Cost

Costs Year 1 2 3 4 5 6 7 8 9 10

Road length (kms.) Portland Cement

Concrete Pavement (PCCP) 2.02370 - - - - - - - - -

Unit Maintenance cost 38,270 38,270 38,270 38,270 38,270 38,270 38,270 38,270 38,270 38,270

Annual Maintenance cost

1. Subtotal Annual Maintenance cost 77,446 77,446 77,446 77,446 77,446 77,446 77,446 77,446 77,446 77,446

2. Capital maintenance every 6th year a/ 0 0 0 0 0 46,468 0 0 0 0

Total Annual Maintenance cost 77,446 77,446 77,446 77,446 77,446 123,914 77,446 77,446 77,446 77,446

Costs Year 11 12 13 14 15 16 17 18 19 20

Portland Cement Concrete Pavement (PCCP)

Unit Maintenance cost 38,270 38,270 38,270 38,270 38,270 38,270 38,270 38,270 38,270 38,270

Annual Maintenance cost

1. Subtotal Annual Maintenance cost 77,446 77,446 77,446 77,446 77,446 77,446 77,446 77,446 77,446 77,446

2. Capital maintenance every 6th year a/ 0 46,468 0 0 0 0 0 46,468 0 0

Total Annual Maintenance cost 77,446 123,914 77,446 77,446 77,446 77,446 77,446 123,914 77,446 77,446

a/ Approximately 60% of annual maintenance cost Source: EFA_Tabigue-Balocawehay FMR_Tab2_InvestCost

Page 56: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

49 | P a g e

Table 38. Transport Data by Vehicles Type (Source: InFRES 2006)

Vehicles Elasticities Traffic Growth rate Vehicles Elasticities Traffic Growth rate

Car/ Van 1.80 1.0360 % Tricycle 1.10 1.0220 %

Jeepney 1.50 1.0300 % Trucks 1.00 1.0200 %

Motorcycles 1.10 1.0220 %

Total Road Length= 2.02370 kms. Per capita income growth rate= 2.00 Ave. population growth rate = 1.01

Table 39. Projected No. of Vehicles per Day = No. of units X Traffic Growth Rate

Year Car / Van Jeepney Motorcycle Tricycle Truck

2014 4 2 39 15 6

2015 4 2 39 15 6

2016 4 2 40 15 6

2017 4 2 40 15 6

2018 4 2 41 16 6

2019 4 2 41 16 6

2020 4 2 41 16 6

2021 4 2 42 16 6

2022 4 2 42 16 7

2023 4 2 43 16 7

2024 4 2 43 17 7

2025 4 2 44 17 7

2026 5 2 44 17 7

2027 5 2 45 17 7

2028 5 2 45 17 7

2029 5 2 45 17 7

2030 5 2 46 18 7

2031 5 2 46 18 7

2032 5 2 47 18 7

2033 5 2 47 18 7

2034 5 2 48 18 7

Table 40. Projected Annual Average Daily Traffic (AADT) = (# Vehicles) X (# Trips/day) X (# days/year)

Year Car / Van Jeepney Motorcycle Tricycle Truck

2015 2,522 946 440,476 137,895 5,043

2016 2,548 955 444,978 139,304 5,094

2017 2,574 965 449,525 140,728 5,146

2018 2,601 975 454,120 142,166 5,199

2019 2,628 985 458,761 143,619 5,252

2020 2,655 995 463,449 145,087 5,305

2021 2,683 1,006 468,186 146,570 5,360

2022 2,711 1,016 472,971 148,068 5,414

2023 2,739 1,026 477,804 149,581 5,469

2024 2,767 1,037 482,687 151,110 5,525

2025 2,796 1,048 487,621 152,654 5,582

2026 2,825 1,058 492,604 154,214 5,638

2027 2,854 1,069 497,638 155,790 5,696

2028 2,883 1,080 502,724 157,382 5,754

2029 2,913 1,092 507,862 158,991 5,813

2030 2,943 1,103 513,052 160,616 5,872

2031 2,974 1,114 518,296 162,257 5,932

2032 3,005 1,126 523,593 163,915 5,992

2033 3,036 1,137 528,944 165,591 6,054

2034 3,067 1,149 534,350 167,283 6,115

Trips/ day 4 3 43 35 8

Days/ year 156 156 260 260 104

Page 57: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

50 | P a g e

Table 41. Standard Vehicle Operating Cost Savings (PhP)

Surface Condition Vehicle Type

Car/ Van Jeepney Motorcycle Tricycle Truck

Paved

Good (A) 7.807 6.483 1.034 2.705 13.182

Very Bad (B) 12.670 11.199 4.372 8.048 26.253

Gravel

Good (C) 9.010 7.588 1.093 2.879 16.609

Very Bad (D) 15.385 14.934 2.148 8.395 34.990

Vehicle Operating Cost

Difference

Vehicle Type

Car/ Van Jeepney Motorcycle Tricycle Truck

Paved (B-A) 4.863 4.716 3.338 5.343 13.071

Gravel (D-C) 6.375 7.346 1.055 5.516 18.381

Gravel-Paved (D-A) 7.578 8.451 1.114 5.690 21.808

Total Road Length (kms.) = 2.02370

Table 42. Total Annual Vehicle Operating Cost Savings* by Vehicle Type (PhP)

Year Car / Van Jeepney Motorcycle Tricycle Truck Total

2015 38,674 16,173 993,010 1,587,841 222,558 2,858,256

2016 39,075 16,339 1,003,159 1,604,069 224,828 2,887,470

2017 39,480 16,507 1,013,411 1,620,462 227,122 2,916,982

2018 39,889 16,678 1,023,768 1,637,023 229,438 2,946,796

2019 40,302 16,849 1,034,231 1,653,754 231,779 2,976,915

2020 40,719 17,023 1,044,801 1,670,655 234,143 3,007,341

2021 41,141 17,198 1,055,479 1,687,729 236,531 3,038,078

2022 41,568 17,375 1,066,266 1,704,978 238,944 3,069,130

2023 41,998 17,554 1,077,163 1,722,403 241,381 3,100,499

2024 42,433 17,735 1,088,172 1,740,006 243,843 3,132,189

2025 42,873 17,918 1,099,293 1,757,789 246,330 3,164,202

2026 43,317 18,102 1,110,527 1,775,753 248,843 3,196,543

2027 43,766 18,289 1,121,877 1,793,901 251,381 3,229,214

2028 44,219 18,477 1,133,343 1,812,235 253,945 3,262,219

2029 44,677 18,667 1,144,925 1,830,756 256,535 3,295,561

2030 45,140 18,860 1,156,626 1,849,466 259,152 3,329,245

2031 45,608 19,054 1,168,447 1,868,368 261,795 3,363,272

2032 46,080 19,250 1,180,389 1,887,463 264,466 3,397,648

2033 46,558 19,449 1,192,452 1,906,753 267,163 3,432,374

2034 47,040 19,649 1,204,639 1,926,240 269,888 3,467,456

* VOC Savings for particular year= (the difference in VOCs for the surface type with and without

project) X (projected annual average daily traffic per vehicle type) X (actual road length).

Source of Tables 31, 32, 33, 34, & 35: EFA_Tabigue-Balocawehay FMR_Tab4a Vehicle Data.

Page 58: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

51 | P a g e

Table 43. Benefits - Vehicle Operating Costs (VOC) Savings

Benefits Unit 1 2 3 4 5 6 7 8 9 10

Motorcycle/"Habal-habal"

Total number unit 39 39 40 40 41 41 41 42 42 43

Number of trips per day trip/day 43 43 43 43 43 43 43 43 43 43

Number of days in operation day/year 260 260 260 260 260 260 260 260 260 260

Subtotal Php 982,964 993,010 1,003,159 1,013,411 1,023,768 1,034,231 1,044,801 1,055,479 1,066,266 1,077,163

Tricycle

Total number unit 15 15 15 15 16 16 16 16 16 16

Number of trips per day trip/day 35 35 35 35 35 35 35 35 35 35

Number of days in operation day/year 260 260 260 260 260 260 260 260 260 260

Subtotal Php 1,571,777 1,587,841 1,604,069 1,620,462 1,637,023 1,653,754 1,670,655 1,687,729 1,704,978 1,722,403

Cars/Vans

Total number unit 4 4 4 4 4 4 4 4 4 4

Number of trips per day trip/day 4 4 4 4 4 4 4 4 4 4

Number of days in operation day 156 156 156 156 156 156 156 156 156 156

Subtotal Php 38,278 38,674 39,075 39,480 39,889 40,302 40,719 41,141 41,568 41,998

Jeepney

Total number unit 2 2 2 2 2 2 2 2 2 2

Number of trips per day trip/day 3 3 3 3 3 3 3 3 3 3

Number of days in operation day 156 156 156 156 156 156 156 156 156 156

Subtotal 16,008 16,173 16,008 16,008 16,008 16,008 16,008 16,008 16,008 16,008

Truck

Total number unit 6 6 6 6 6 6 6 6 7 7

Number of trips per day trip/day 8 8 8 8 8 8 8 8 8 8

Number of days in operation day 104 104 104 104 104 104 104 104 104 104

Subtotal 220,311 222,558 224,828 227,122 229,438 231,779 234,143 236,531 238,944 241,381

Total Benefits PhP 7,132,504 7,205,385 7,279,011 7,353,389 7,428,527 7,504,433 7,581,115 7,658,580 7,736,836 7,815,893

Notes: 1. VOC Difference per Vehicle Type, (see Table 41. Standard VOCS - DPWH standard): 3. Total VOCS per Vehicle Type= No. of Vehicles X No. of Trips/Day X No. of Days

(a) Motorcycle = 1.114 (c) Car/Van = 7.578 (e) Truck = 21.81 Operation/Year X VOC Difference X Road Length

(b) Tricycle = 5.690 (d) Jeepney = 8.451

2. Road length = 2.02370 kms. Source: EFA_Tabigue-Balocawehay FMR_Tab4_VOC Saving

Page 59: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

52 | P a g e

Table 43. Benefits - Vehicle Operating Costs (VOC) Savings

Benefits Unit 11 12 13 14 15 16 17 18 19 20

Motorcycle/"Habal-habal"

Total number unit 43 44 44 45 45 45 46 46 47 47

Number of trips per day trip/day 43 43 43 43 43 43 43 43 43 43

Number of days in operation day/year 260 260 260 260 260 260 260 260 260 260

Subtotal Php 1,088,172 1,099,293 1,110,527 1,121,877 1,133,343 1,144,925 1,156,626 1,168,447 1,180,389 1,192,452

Tricycle

Total number unit 17 17 17 17 17 17 18 18 18 18

Number of trips per day trip/day 35 35 35 35 35 35 35 35 35 35

Number of days in operation day/year 260 260 260 260 260 260 260 260 260 260

Subtotal Php 1,740,006 1,757,789 1,775,753 1,793,901 1,812,235 1,830,756 1,849,466 1,868,368 1,887,463 1,906,753

Cars/Vans

Total number unit 4 4 5 5 5 5 5 5 5 5

Number of trips per day trip/day 4 4 4 4 4 4 4 4 4 4

Number of days in operation day 156 156 156 156 156 156 156 156 156 156

Subtotal Php 42,433 42,873 43,317 43,766 44,219 44,677 45,140 45,608 46,080 46,558

Jeepney

Total number unit 2 2 2 2 2 2 2 2 2 2

Number of trips per day trip/day 3 3 3 3 3 3 3 3 3 3

Number of days in operation day 156 156 156 156 156 156 156 156 156 156

Subtotal 16,008 16,008 16,008 16,008 16,008 16,008 16,008 16,008 16,008 16,008

Truck

Total number unit 7 7 7 7 7 7 7 7 7 7

Number of trips per day trip/day 8 8 8 8 8 8 8 8 8 8

Number of days in operation day 104 104 104 104 104 104 104 104 104 104

Subtotal 243,843 246,330 248,843 251,381 253,945 256,535 259,152 261,795 264,466 267,163

Total Benefits PhP 3,130,461 3,162,292 3,194,448 3,226,933 3,259,750 3,292,902 3,326,393 3,360,226 3,394,405 3,428,933

Notes: 1. VOC Difference per Vehicle Type, (see Table 41. Standard VOCS - DPWH standard): 3. Total VOCS per Vehicle Type= No. of Vehicles X No. of Trips/Day X No. of Days

(a) Motorcycle = 1.114 (c) Car/Van = 7.578 (e) Truck = 21.81 Operation/Year X VOC Difference X Road Length

(b) Tricycle = 5.690 (d) Jeepney = 8.451

2. Road length = 2.02370 kms. Source: EFA_Tabigue-Balocawehay FMR_Tab4_VOC Saving

Page 60: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

53 | P a g e

Table 44. Benefits - Savings in Output Hauling Costs a/

Benefits Unit 1 2 3 4 5 6 7 8 9 10

Hauling cost

Current hauling cost b/ Php/sack 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00

Estimated hauling cost Php/sack 20 20 20 20 20 20 20 20 20 20

Hauling cost saving Php/sack 10 10 10 10 10 10 10 10 10 10

Rice

Average production/ha. per year c/ sack 172 172 172 172 172 172 172 172 172 172

Area planted ha 462 462 462 462 462 462 462 462 462 462

Total output sack 79,412 79,412 79,412 79,412 79,412 79,412 79,412 79,412 79,412 79,412

% of harvest brought to poblacion % 60% 60% 60% 60% 60% 60% 60% 60% 60% 60%

Total volume of harvest marketed sack 47,647 47,647 47,647 47,647 47,647 47,647 47,647 47,647 47,647 47,647

Sub-total savings in hauling cost Php 476,474 476,474 476,474 476,474 476,474 476,474 476,474 476,474 476,474 476,474

Coconut

Average production/ha. per year c/ sack 38.4 38.4 38.4 38.4 38.4 38.4 38.4 38.4 38.4 38.4

Area planted ha 353 353 353 353 353 353 353 353 353 353

Total output sack 13,564 13,564 13,564 13,564 13,564 13,564 13,564 13,564 13,564 13,564

% of harvest brought to poblacion % 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%

Total volume of harvest marketed sack 13,428 13,428 13,428 13,428 13,428 13,428 13,428 13,428 13,428 13,428

Sub-total savings in hauling cost Php 134,284 134,284 134,284 134,284 134,284 134,284 134,284 134,284 134,284 134,284

Corn

Average production/ha. per year c/ sack 30 30 30 30 30 30 30 30 30 30

Area planted ha 23 23 23 23 23 23 23 23 23 23

Total output sack 690 690 690 690 690 690 690 690 690 690

% of harvest brought to poblacion % 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%

Total volume of harvest marketed sack 683 683 683 683 683 683 683 683 683 683

Sub-total savings in hauling cost Php 6,831 6,831 6,831 6,831 6,831 6,831 6,831 6,831 6,831 6,831

Total Savings in Hauling Cost Php 617,589 617,589 617,589 617,589 617,589 617,589 617,589 617,589 617,589 617,589

a/ Influence area covering the barangay Source: EFA_Tabigue-Balocawehay FMR_Tab5a_Savings Output Hauling

b/ Brgy. Tabigue – Brgy. Balocawehay c/ One sack = 50 kgs.

Page 61: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

54 | P a g e

Table 44. Benefits - Savings in Output Hauling Costs a/

Benefits Unit 11 12 13 14 15 16 17 18 19 20

Hauling cost

Current hauling cost b/ Php/sack 30 30 30 30 30 30 30 30 30 30

Estimated hauling cost Php/sack 20 20 20 20 20 20 20 20 20 20

Hauling cost saving Php/sack 10 10 10 10 10 10 10 10 10 10

Rice

Average production/ha. per year c/ sack 172 172 172 172 172 172 172 172 172 172

Area planted ha 462 462 462 462 462 462 462 462 462 462

Total output sack 79,412 79,412 79,412 79,412 79,412 79,412 79,412 79,412 79,412 79,412

% of harvest brought to poblacion % 60% 60% 60% 60% 60% 60% 60% 60% 60% 60%

Total volume of harvest marketed sack 47,647 47,647 47,647 47,647 47,647 47,647 47,647 47,647 47,647 47,647

Sub-total savings in hauling cost Php 476,474 476,474 476,474 476,474 476,474.40 476,474 476,474 476,474 476,474 476,474

Coconut

Average production/ha. per year c/ Sack 38 38 38 38 38 38 38 38 38 38

Area planted ha 353 353 353 353 353 353 353 353 353 353

Total output sack 13,564 13,564 13,564 13,564 13,564 13,564 13,564 13,564 13,564 13,564

% of harvest brought to poblacion % 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%

Total volume of harvest marketed sack 13,428 13,428 13,428 13,428 13,428 13,428 13,428 13,428 13,428 13,428

Sub-total savings in hauling cost Php 134,284 134,284 134,284 134,284 134,284 134,284 134,284 134,284 134,284 134,284

Corn

Average production/ha. per year c/ sack 30 30 30 30 30 30 30 30 30 30

Area planted ha 23 23 23 23 23 23 23 23 23 23

Total output sack 690 690 690 690 690 690 690 690 690 690

% of harvest brought to poblacion % 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%

Total volume of harvest marketed sack 683 683 683 683 683 683 683 683 683 683

Sub-total savings in hauling cost Php 6,831 6,831 6,831 6,831 6,831 6,831 6,831 6,831 6,831 6,831

Total Savings in Hauling Cost Php 617,589 617,589 617,589 617,589 617,589 617,589 617,589 617,589 617,589 617,589

a/ Influence area covering the barangay Source: EFA_Tabigue-Balocawehay FMR_Tab5a_Savings Output Hauling

b/ Brgy. Abaca – Brgy. Panda c/ One sack = 50 kgs.

Page 62: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

55 | P a g e

Table 45. Benefits - Savings in Input Hauling Costs a/

Benefits Unit 1 2 3 4 5 6 7 8 9 10

Hauling cost

Current hauling cost b/ Php/sack 30 30 30 30 30 30 30 30 30 30

Estimated hauling cost Php/sack 20 20 20 20 20 20 20 20 20 20

Hauling cost saving Php/sack 10 10 10 10 10 10 10 10 10 10

Rice

Mineral fertilizer sack/ha 16 16 16 16 16 16 16 16 16 16

Seeds d/ sack/ha 4 4 4 4 4 4 4 4 4 4

Total number of sacks sack/ha 20 20 20 20 20 20 20 20 20 20

Area planted ha 462 462 462 462 462 462 462 462 462 462

Total fertilizer and seeds sack 9,234 9,234 9,234 9,234 9,234 9,234 9,234 9,234 9,234 9,234

Sub-total savings in hauling cost Php 138,510 138,510 138,510 138,510 138,510 138,510 138,510 138,510 138,510 138,510

Copra

Mineral fertilizer sack/ha 10 10 10 10 10 10 10 10 10 10

Seeds d/ sack/ha - - - - - - - - - -

Total number of sacks sack/ha 10 10 10 10 10 10 10 10 10 10

Area planted ha 353 353 353 353 353 353 353 353 353 353

Total fertilizer and seeds sack 3,532 3,532 3,532 3,532 3,532 3,532 3,532 3,532 3,532 3,532

Sub-total savings in hauling cost 52,985 52,985 52,985 52,985 52,985 52,985 52,985 52,985 52,985 52,985

Corn

Mineral fertilizer c/ sack/ha 16 16 16 16 16 16 16 16 16 16

Seeds d/ sack/ha 4 4 4 4 4 4 4 4 4 4

Total number of sacks sack/ha 20 20 20 20 20 20 20 20 20 20

Area planted ha 23 23 23 23 23 23 23 23 23 23

Total fertilizer and seeds sack 460 460 460 460 460 460 460 460 460 460

Sub-total savings in hauling cost Php 6,900 6,900 6,900 6,900 6,900 6,900 6,900 6,900 6,900 6,900

Total savings in hauling cost Php 198,395 198,395 198,395 198,395 198,395 198,395 198,395 198,395 198,395 198,395

a/ Relevant or applicable only to the Road Influenced Area (RIA) Barangays Source: EFA_Tabigue-Balocawehay FMR_Tab5b_Savings Input Hauling

b/ For the distance from Brgy. Abaca – Brgy. Panda

c/ 2 croping season per year. 8 sacks of mineral fertilizer per cropping season

d/ Certified seeds: 2 sacks per hectare (1 sack=50 Kg), 2 croping seasons

Page 63: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

56 | P a g e

Table 45. Benefits - Savings in Input Hauling Costs a/

Benefits Unit 11 12 13 14 15 16 17 18 19 20

Hauling cost

Current hauling cost b/ Php/sack 30 30 30 30 30 30 30 30 30 30

Estimated hauling cost Php/sack 20 20 20 20 20 20 20 20 20 20

Hauling cost saving Php/sack 10 10 10 10 10 10 10 10 10 10

Rice

Mineral fertilizer c/ sack/ha 16 16 16 16 16 16 16 16 16 16

Seeds d/ sack/ha 4 4 4 4 4 4 4 4 4 4

Total number of sacks sack/ha 20 20 20 20 20 20 20 20 20 20

Area planted ha 462 462 462 462 462 462 462 462 462 462

Total fertilizer and seeds sack 9,234 9,234 9,234 9,234 9,234 9,234 9,234 9,234 9,234 9,234

Sub-total savings in hauling cost Php 138,510 138,510 138,510 138,510 138,510 138,510 138,510 138,510 138,510 138,510

Copra

Mineral fertilizer sack/ha 10 10 10 10 10 10 10 10 10 10

Seeds d/ sack/ha - - - - - - - - - -

Total number of sacks sack/ha 10 10 10 10 10 10 10 10 10 10

Area planted ha 353 353 353 353 353 353 353 353 353 353

Total fertilizer and seeds sack 3,532 3,532 3,532 3,532 3,532 3,532 3,532 3,532 3,532 3,532

Sub-total savings in hauling cost Php 52,985 52,985 52,985 52,985 52,985 52,985 52,985 52,985 52,985 52,985

Corn

Mineral fertilizer c/ sack/ha 16 16 16 16 16 16 16 16 16 16

Seeds d/ sack/ha 4 4 4 4 4 4 4 4 4 4

Total number of sacks sack/ha 20 20 20 20 20 20 20 20 20 20

Area planted ha 23 23 23 23 23 23 23 23 23 23

Total fertilizer and seeds sack 460 460 460 460 460 460 460 460 460 460

Sub-total savings in hauling cost Php 6,900 6,900 6,900 6,900 6,900 6,900 6,900 6,900 6,900 6,900

Total savings in hauling cost Php 198,395 198,395 198,395 198,395 198,395 198,395 198,395 198,395 198,395 198,395

a/ Relevant or applicable only to the Road Influenced Area (RIA) Barangays Source: EFA_Tabigue-Balocawehay FMR_Tab5b_Savings Input Hauling

b/ For the distance from Brgy. San Juan to Poblacion

c/ 2 croping season per year. 8 sacks of mineral fertilizer per cropping season

d/ Certified seeds: 2 sacks per hectare (1 sack=50 Kg), 2 croping seasons

Page 64: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

57 | P a g e

Table 46. Benefits - Savings in travel time for commuters

Benefits Unit 1 2 3 4 5 6 7 8 9 10

Projected population a/ person 4,767 4,815 4,864 4,913 4,963 5,013 5,063 5,114 5,166 5,218

Est'd. % of econ. active population 35%

Estimated number of economically

active population person 1,668 1,685 1,702 1,720 1,737 1,754 1,772 1,790 1,808 1,826

% of commuters in econ. active pop. 50%

Estimated number of commuters person 834 843 851 860 868 877 886 895 904 913

Number of one way trips per day trip/day 2 2 2 2 2 2 2 2 2 2

Number of working days w.day 240 240 240 240 240 240 240 240 240 240

Total number of trips, all commuters trip 400,428 404,472 408,557 412,684 416,852 421,062 425,315 429,611 433,950 438,333

Time saving for commuters b/ min/trip 6 6 6 6 6 6 6 6 6 6

Total time saving in min min 2,402,568 2,426,834 2,451,345 2,476,104 2,501,112 2,526,373 2,551,890 2,577,664 2,603,698 2,629,996

Total time saving in days c/ w.day 5,005 5,056 5,107 5,159 5,211 5,263 5,316 5,370 5,424 5,479

Share of saved time used for work 53%

Net total time saving in days w.day 2,653 2,679.63 2,706.69 2,734 2,762 2,790 2,818 2,846 2,875 2,904

Average labor cost d/ PhP/w.day 257 270 284 298 313 328 345 362 380 399

Labor cost (economic) PhP/w.day 154 162 170 179 188 197 207 217 228 240

Time saving value PhP 409,608 434,433 460,762 488,686 518,303 549,715 583,030 618,365 655,840 695,588

a/ Population growth rate = 1.01% Source: EFA_Tabigue-Balocawehay FMR_Tab6_Travel Time Commuters

b/ 10 min before and 4 min after subproject

c/ 60 min x 8 working hours = 480 min

d/ Assumed to increase by 5% annually

Page 65: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

58 | P a g e

Table 46. Benefits - Savings in Travel Time for Commuters

Benefits Unit 11 12 13 14 15 16 17 18 19 20

Projected population a/ person 5,271 5,324 5,378 5,432 5,487 5,543 5,599 5,655 5,712 5,770

Est'd. % of econ. active population 35%

Estimated number of ec.active

population person 1,845 1,863 1,882 1,901 1,921 1,940 1,959 1,979 1,999 2,019

% commuters in econ.active pop. 50%

Estimated number of commuters person 922 932 941 951 960 970 980 990 1,000 1,010

Number of one way trips per day trip/day 2 2 2 2 2 2 2 2 2 2

Number of working days per year w.day 240 240 240 240 240 240 240 240 240 240

Total number of trips for all

commuters trip 442,760 447,232 451,749 456,311 460,920 465,575 470,278 475,027 479,825 484,672

Time saving for commuters b/ min/trip 6 6 6 6 6 6 6 6 6 6

Total time saving in min min 2,656,559 2,683,390 2,710,492 2,737,868 2,765,521 2,793,452 2,821,666 2,850,165 2,878,952 2,908,029

Total time saving in days c/ w.day 5,534.50 5,590 5,647 5,704 5,762 5,820 5,878 5,938 5,998 6,058

Share of saved time used for work 40%

Net total time saving in days w.day 2,933 2,962.91 2,993 3,023 3,054 3,084 3,116 3,147 3,179 3,211

Average labor cost d/ PhP/w.day 419 440 462 485 510 535 562 590 619 650

Labor cost (economic) PhP/w.day 252 264 277 291 306 321 337 354 372 390

Time saving value PhP 737,744 782,455 829,875 880,170 933,513 990,088 1,050,093 1,113,733 1,181,231 1,252,820

a/ Population growth rate = 1.01% Source: EFA_Tabigue-Balocawehay FMR_Tab6_Travel Time Commuters

b/ 10 min before and 4 min after subproject

c/ 60 min x 8 working hours = 480 min

d/ Assumed to increase by 5% annually

Page 66: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

59 | P a g e

Table 47. Benefits of newly cultivated agricultural land (rice and coconut)

Benefits Unit 1 2 3 4 5 6 7 8 9 10

Rice

Newly Cultivated Agri. Land ha 5 5 5 5 5 5 5 5 5 5

Average Production/Ha./Year b/ sack 172 172 172 172 172 172 172 172 172 172

Total Output sack 860 860 860 860 860 860 860 860 860 860

Output Price (farm gate) c/ PhP/kg. 25 25 25 25 25 25 25 25 25 25

Output Value b/ PhP 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000

Land Development Cost/Ha. PhP 25,000 - - - - - - - - -

Production Cost/Ha PhP 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000

Marketing cost PhP/sack 17,200 17,200 17,200 17,200 17,200 17,200 17,200 17,200 17,200 17,200

Total Cost Php 217,200 92,200 92,200 92,200 92,200 92,200 92,200 92,200 92,200 92,200

Net Benefit Php 857,800 982,800 982,800 982,800 982,800 982,800 982,800 982,800 982,800 982,800

Coconut

Newly Cultivated Agri. Land a/ ha 2 2 2 2 2 - 2 4 6 8

Average Production/Ha./Year b/ sack 38.40 38.40 38.40 38.40

Total Output sack - - - - - - 77 154 230 307

Output Price (farm gate) c/ PhP/kg. - - - - - - 27 27 27 27

Output Value b/ PhP - - - - - - 103,680 207,360 311,040 414,720

Land Development Cost/Ha. PhP 33,500 33,500 33,500 33,500 33,500 - - - - -

Production Cost/Ha PhP 13,500 13,500 13,500 13,500

Marketing cost PhP/sack - - - - - - 1,536 3,072 4,608 6,144

Total Cost Php 67,000 67,000 67,000 67,000 67,000 - 28,536 57,072 85,608 114,144

Net Benefit Php (67,000) (67,000) (67,000) (67,000) (67,000) - 75,144 150,288 225,432 300,576

TOTAL BENEFITS Php 790,800 915,800 915,800 915,800 915,800 982,800 1,057,944 1,133,088 1,208,232 1,283,376

a/ Potential new agri. land for coconut = 5 has., to be developed in increments of 1 hectares for the first 5 years. b/ May vary according to Region c/ 1 sack = 50kgs Source: EFA_Tabigue-Balocawehay FMR_Tab7_New Agri. Area

Page 67: Feasibility Study - drive.daprdp.netdrive.daprdp.net/ses/pdf/FS_Tabigue-Balocawehay FMR_rev._6-04-2015...Feasibility Study CONCRETING OF ... C. Local Finance Committee ... I. Minutes

A Feasibility Study: Rehabilitation/Concreting of Tabigue - Balocawehay FMR

60 | P a g e

Table 47. Benefits of newly cultivated agricultural land (rice and coconut)

Benefits Unit 11 12 13 14 15 16 17 18 19 20

Rice

Newly Cultivated Agri. Land ha 5 5 5 5 5 5 5 5 5 5

Average Production/Ha./Year b/ sack 172 172 172 172 172 172 172 172 172 172

Total Output sack 860 860 860 860 860 860 860 860 860 860

Output Price (farm gate) c/ PhP/kg. 25 25 25 25 25 25 25 25 25 25

Output Value b/ PhP 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000 1,075,000

Land Development Cost/Ha. PhP - - - - - - - - - -

Production Cost/Ha PhP 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000

Marketing cost PhP/sack 17,200 17,200 17,200 17,200 17,200 17,200 17,200 17,200 17,200 17,200

Total Cost Php 92,200 92,200 92,200 92,200 92,200 92,200 92,200 92,200 92,200 92,200

Net Benefit Php 982,800 982,800 982,800 982,800 982,800 982,800 982,800 982,800 982,800 982,800

Coconut

Newly Cultivated Agri. Land a/ ha 10 10 10 10 10 10 10 10 10 10

Average Production/Ha./Year b/ sack 38.40 38.40 38.40 38.40 38.40 38.40 38.40 38.40 38.40 38.40

Total Output sack 384 384 384 384 384 384 384 384 384 384

Output Price (farm gate) c/ PhP/kg. 27 27 27 27 27 27 27 27 27 27

Output Value b/ PhP 518,400 518,400 518,400 518,400 518,400 518,400 518,400 518,400 518,400 518,400

Land Development Cost/Ha. PhP - - - - - - - - - -

Production Cost/Ha PhP 13,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500

Marketing cost PhP/sack 7,680 7,680 7,680 7,680 7,680 7,680 7,680 7,680 7,680 7,680

Total Cost Php 142,680 142,680 142,680 142,680 142,680 142,680 142,680 142,680 142,680 142,680

Net Benefit Php 375,720 375,720 375,720 375,720 375,720 375,720 375,720 375,720 375,720 375,720

TOTAL BENEFITS Php 1,358,520 1,358,520 1,358,520 1,358,520 1,358,520 1,358,520 1,358,520 1,358,520 1,358,520 1,358,520

a/ Potential new agri. land for coconut = 5 has., to be developed in increments of 1 hectares for the first 5 years. b/ May vary according to Region c/ 1 sack = 50kgs Source: EFA_Tabigue-Balocawehay FMR_Tab7_New Agri. Area