Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Feasibility Study and DPR for Delhi- Gurgaon-Rewari-Alwar RRTS Corridor
Date:- 22/04/2017
NCR Planning Board
Implementation Models and Financing
Part I – Financial Analysis
Sequence of Financial Analysis
v Assessment of the project in generic terms i.e. without consideringthe implementation model and agency into account.
Estimating;Ø Project Completion cost (capital cost),Ø Various streams of revenue,Ø Operation and maintenance cost andØ Operational viability and returns from the project;
v Assessment of Proposed Project Implementation Models
Ø Calculation of returns from the project with regard to proposed modelsØ Deliberations on Advantages and disadvantages of each model
v Recommendations for suitable model
Assumptions for Analysis period
vTotal Analysis Period 30 years;
Ø Construction period: 6.5 years, Starting from FY 2018-19 (Oct 2018) to the full FY 2024-25.
Ø Operation Period: 25 years , from FY 2025-26.to FY 2049-50.
Particulars Total (Rs. Crore)
Land 5,429
Aggregate Project cost except Land 29,540
Total Project cost with cost of Land 34,969
General Charges including Design Charges (5% of cost except land)
1,477
Contingencies on all items at 3% 1,093
Total 37,539
Estimated Project Cost (EPC)
v Excludes tax on project goods and IDC. These components will be introduced subsequently in the analysis as per the requirement
vAdditional cost of procurement of AC midi buses for feeder system is introduced.
Particular2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
Total
Construction Phasing 10% 18% 20% 16% 14% 12% 10% 100%Project Cost (UnEscalated)
3754 6757 7508 6006 5255 4505 3754 37539
Project Cost (Escalated) 3942 7450 8691 7301 6707 6037 5282 45409
Central Taxes on Project Goods
434 821 957 804 739 665 582 5003
Total 4376 8270 9649 8105 7446 6702 5864 50412
Phasing of Construction and Completion Cost
1.34X
v Project Cost is escalated at 5% pa.
vCentral Taxes would be considered interest free sub debt contributed equally by central govt. and state govts.
v State taxes would be waived off/reimbursed by states and hence not taken.
v No major change is expected on the tax burden on Project Cost due to GST and therefore existing incidence is retained
Figures in Rs. Crores
Summary of Estimated O&M Expenses
Particular2025-26 2034-35 2044-45 2049-50 TOTAL
% of the Total
Rs. Crores
Staff Salaries 386 598 975 1244 18407 21%
Energy Expenses 675 1339 2518 3213 41407 48%
Replacement in Equipment /Addition of Rolling Stock
0 3806 7415 0 11221 13%
Repair & Maintenance Exp. 271 421 685 875 12946 15%Admin Expenses 60 93 151 193 2861 3%Operational Viability Funding to Feeder Bus Services
9 17 0 0 76 0%
Total 1401 6274 11744 5525 86918 100%
• O&M expenses are estimated based on actual experience of operational Metro Systems in India and abroad.
• Energy expenses could be more than half of the total O&M Expenses
8
Distance slabs in Km
0-10
10-20
20-30
30-40
40-50
50-60
60-70
70-80
80-90
90-100
100-110
110-120
120-130
130-140
140-150
150-160
160-170
170-180
Average Fares inpresent terms
(Rs.)30 40 55 70 88 105 122 138 154 169 184 198 211 224 236 248 259 270
Proposed Economy Class Fares
Initial Fare Fixation
Guiding Principles
Mix of distance based flat and increasing fares are adopted. Based on following principals
1. Affordability to the users2. Sustainability of the system3. Competitiveness with the other modes of transport on the similar route4. Flexibility for revision
RevisedFare=BaseFare+(100%ofBaseFarexPercentChangeinCPI)x(1-efficiencyfactor)Fare Revision Formula:
9
Particular2025-
262034-
352044-
452049-
50Daily Passenger ridership (In lakhs) 7.04 13.24 15.78 17.00
Daily pass holders (in lakhs) 4.23 7.94 9.47 10.20
Average Fare/Trip (Rs/pax) 85 125 205 275
Daily fare box from Economy Class A(Rs. Crores) 5.23 14.47 28.28 40.87
Daily Fare Box from Business Class B(Rs. Crores) 0.59 1.63 3.19 4.61
Daily Fare Box Collection = A+B (Rs. Crores) 5.83 16.10 31.48 45.49
Annual fare box collection (Rs. Crores) 1981 5473 10701 15465
• Ramp up of 70%,80% and 90% is taken in the estimateddaily ridership for initial 3 years.
• Pass-holders are estimated to be around 60% of the total daily ridership
• 10% concession for pass holders
• Around 7% of the total commuters may travel in business class by paying 1.5 times
higher fares.
Fare Box Revenue
Yr>> 2025-26 2029-30 2033-34 2039-40 Total
Phases Rs. Crores
Phase 1 1560 1560 0 0 7800
Phase 2 0 1557 1557 0 10900
Phase 3 0 0 2743 2700 19200
Total 1560 3117 4300 2743 37900
Revenue to Project from Property Development
Phase RRTS Stations Key AttributeBuilt up Area (Lakh Sqm)
Comm. Resi.
First 1) Panchgaon 2) Dharuhera Peripheral area of Gurgaon – Spillover advantage 3.81 1.98
Second 1) Rewari 2) MBIRRewari – Key transport/logistic node
MBIR – planned SIR 6.19 2.98
Third 1) BTK 2) SNB 3) AlwarSIRs – Key junctions – benefits of Planned area ;
semi urban settlements11.24 10.64
`Total 21.26 15.60
11
No. of Stations 19Total del. area for all stations (hac. ) 23864Land Area already developed 30%Land Area yet to be developed outside of developed areas 30%
Land Area yet to be developed (hac) 7159Remove 40% for green area/roads/common area (hac) 2864Net area for built up (hac) 4296Average FSI that will be consumed in DA 3Total BUA (hac) - (A) 12887
Existing Developed land area (hac) 7159Remove 65% for green, roads, common areas (hac) 4653Net developed Land Area (hac) 2506Average FSI consumed 1.5Total BUA (hac) - (B) 3759
Area approximating 2 km in radius around each stationcould be earmarked as the Delineated Area (DA).
Property owners whose properties are situated in the DAwould need to pay a cess on every transaction in addition tostamp duty and other statutory levies.
For this purpose cess of Rs 800/ sq mt for open area/plotsand Rs 600/- per sq mt for BUA has been taken.
Higher FAR of upto 3 could be permitted for this purpose.(Higher FAR may not be possible in stations situated in highdensity areas.
Levy of this cess shall begin with RRTS operations.
Structure Calculation of delineated area
Estimated Velocity of transactions in DA
Period Aggregate revenue
(Rs. Crore)
Operation Period of RRTS (25 years) 15564
Revenue from Cess
Cess on Property Transaction
Operation Period
Sale of Additional FAR
v Sale of additional FAR included as a strategy for non fare revenue augmentation.v Strategy useful for densification and value capturev Area approximating 1 KM around station shall be Delineated Area (DA) for sale of
additional FAR of the order of 1.v Ave. 16% of proposed/under construction properties in the DA may opt for purchase
of additional FAR.v Revenue from this sale is calculated @25% of prevailing land circle rates in the DA.v Circle rates are assumed to grow 5% annually.
Illustrative Year
Rate of absorption for add. FAR
A
Sale of Add. FAR (in hec.)
B
Land Circle Rates(Rs.Crores/Hec.)
C
Revenue for theyear (Rs. Crores)
C X B
2025-26 5% 74.58 5.26 392.58
2029-30 10% 149.15 6.40 954.36
2034-35 5% 74.58 8.17 609.01
2039-40 3% 44.75 10.42 466.36
2042-43 2% 29.83 12.07 359.92
TOTAL Rs. 10959 crores
Institutional Mechanism for Cess on Transaction and Sale of Additional FAR v In the state of Haryana
v The Town and Country Planning Department, Govt of Haryana vide Memo dated Date: 06/05/2016permits sale of additional FAR at Rs 120-700 per sq ft. for high and hyper buildings.
v Subsequently, relevant provision for Punjab Scheduled Roads and Controlled Areas Restriction ofUnregulated Development Rules, 1965 and Haryana Building Codes, 1995 to be amended to imposeCess on Transaction.
v In the States of GNCTD and Rajasthanv Similarly other states may give effect to 1) Cess on Property Transaction and 2) Sale of additional FAR
within station wise delineated areas on RRTS corridor by amending relevant acts and regulations.
v Collection and Ring Fencingv The Urban Local Bodies (ULBs)/ Revenue Circle Offices under which respective DA is falling can collect
cess on Transaction
v Revenue from sale of additional FAR within particular DA can be collected by applicable ULBs .
v The funds can be transferred through escrow arrangement to Proposed Regional Transit Fund managedBy NCRTC which will distribute the fund to the regional transit projects as per requirement
Urban Development departments of respective states and MoUD, GOI need to intervene for better coordination and implementation
14
Particular 2025-26 2034-35 2044-45 2049-50 Total As % of total
Rs. CroreFare Box 1981 1565 10702 7305 190056 74%
Property Development 1560 4300 0 0 37900 15%
Advertisement 52 81 133 169 2503 1%Stall Rentals 8 13 21 27 393 -Cess on transactions 631 788 394 0 15664 6%Sale of FAR 393 609 0 0 10959 4%
Total 4625 11265 5185 7988 257475 100%
Summary of revenue
• Fare Collection is the major source of revenue.
• Inflow from Property development and associated activities such as upfront leasepremium, cess on transactions and sale of FAR jointly contribute to around 25% ofrevenue
• This non fare revenue inflow during middle years of operations shall help in operationalsustainability of the project.
• Revenue from advertisement and license fees is expected to be insignificant.
• Inputs related to Depreciation and taxes are taken as per prevailing practices includingeffect of MAT and benefit available As per Income tax Act, u/s 80 IA.
• The operating surplus would remain > 65% as Fare box revenues is supported handsomelyby property development, cess income and sale of FAR.
• The fare revenue grows at 7% pa over 25 years (a combined effect of increase in faresbiannually and y-o-y increase in traffic). In comparison, O&M expenses grows at 5.65% paover 25 years.
• The operating ratio decreases during procurement of rolling stock for periodic replacementof assets though.
Operational Viability
Returns in Generic terms
Pre- Tax : 8.40%Post- Tax : 7.41%
Pre-tax Cashflow
-15000
-10000
-5000
0
5000
10000
15000
200002018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
2027-28
2028-29
2029-30
2030-31
2031-32
2032-33
2033-34
2034-35
2035-36
2036-37
2037-38
2038-39
2039-40
2040-41
2041-42
2042-43
2043-44
2044-45
2045-46
2046-47
2047-48
2048-49
2049-50
Rs.Crore
ProjectInvestments O&MCosts Taxes
FareBoxCollection CessonPropertyTransaction UpfrontLeasefromPropertyDevelopment
StallLinceses CarbonCredit
Project IRR
Implementation models
Following models are assessed;
1) Public Sector Model
2) Public Private Partnership Models a) Outsourcing of O&Mb) Viability Gap Funding (VGF)c) Hybrid Annuity Model
18
Public Sector Model
S. No. Means of FinanceContribution
% of Project Cost (Rs. Crores.)
1 Equity Contribution 30.00% 15729A Govt. of India 15.00% 7864
B Govt. of Delhi NCT 3.84% 2011
C Govt. of Haryana 8.57% 4492
D Govt. of Rajasthan 2.60% 1362
2Senior Debt from Multilateral Agencies (Int 2% pa, 30 years repayment + 5 grace period )
55.43% 29061
3 Regional Transit Fund (RTF) 5.00% 26214 Int. free Subordinate Debt from Raj and GNCTD Govt for Govt. Land 0.03% 145 Int. Free sub debt from Central and State Govt for Tax 9.54% 5003
A Govt. of India 4.77% 2501
B Govt. of Delhi NCT 1.22% 640
C Govt. of Haryana 2.72% 1429
D Govt. of Rajasthan 0.83% 433Total (1+2+3+4+5) 100% 52428
Project Structure • A Public sector special Purpose Vehicle (SPV) will
Finance, Build, operate and maintain the project.
• Bear all the risk associated to the project.
Project Cost
At 2017 Prices Escalated @5%
Rs. Crores
With cost of land, tax and IDC 37539 52428
Financing
At Concessional Rate – Hedging Cost to be borne byCentral Govt – Interest rate includes GuaranteeCommission form Central Govt
Interest Free sub debt and RTF reducescapital requirements and WACC andimproves debt service capabilities
Returns from Public Sector Model
Parameter Pre Tax Post Tax
Project IRR 8.40% 7.52%
Avg. DSCR 5.62
Min. DSCR 3.12
• Due to access to low cost funds the Project can achieve PIRR morethan 8% on pre-tax basis which is quite higher than WACC of apporx4.3%.
• The project would have adequate debt service capacity throughoutthe project period
Sensitivity of the project to change in Certain factors which may affect thereturns and debt service capacity are discussed further
Sensitivity Analysis - Public Sector Model S. No. Scenarios PIRR
(Pre Tax)Change in PIRR Minimum
DSCRChange in DSCR
+10% -10% +10% -10%
1. Change in Project Cost 8.40% 7.60% 9.30% 3.12 3.07 3.78
2. Change in O&M cost 8.40% 8.12% 8.66% 3.12 3.00 3.80
3.Change in Fare revenue 8.40% 9.09% 7.66% 3.12 3.76 3.02
4. Change in TOD revenue 8.40% 8.64% 8.15% 3.12 3.68 3.10
S. No. Other Scenarios Particulars
PIRR (Pre Tax) in
Base Case
PIRR with change Minimum
DSCR
Minimum DSCR with
Change
5. Higher Cost of Debt 10% 8.40% 8.40% 3.12 1.22
6.Change in Revenue Streams
Only Fare + Advt. + License Fee 8.40% 3.97% 3.12 <1
7.Change in Revenue streams
Only Fare + Revenue from TOD + Advt. +
License Fee8.40% 6.66% 3.12 2.44
PIRR is below 8% DSCR below 1
Implementation models
Following models are assessed;
1) Public Sector Model
2) Public Private Partnership Models a) Outsourcing of O&Mb) Viability Gap Funding (VGF)c) Hybrid Annuity Model
Sharing 50% of reduction in ER
Development of Property
Revenue from Property Development
Govt. SPV
Private O&M
company
Expected Revenue (ER)
(-)20% of ER
(+)20% of ER
Sharing of 50% of additional ER
Share Fixed % of ER
Fare Collection, Sale of advertising & licensing rights
Fare and non fare revenue
PPP Models – Outsourcing of O&M
Operations of RRTS & feeder service
Maintenance of rolling stock, E&M, Buses, Civil Assets
All Civil construction, E&M
, Traction, Signaling & other
costs
Rolling stock & Feeder Buses
• % of revenue share can be the award criteria since revenue is expected to remain higher than O&Mcost
• Key limitations of the model which can restrict private participation
• Unpredictability in Ridership• Safety Risk to be born by the SPV as per Metro Act despite of not being involved in O&M• Uncertainty over fare revision• Gross Cost Model is globally preferred model in comparison with proposed model
Implementation models
Following models are assessed;
1) Public Sector Model
2) Public Private Partnership Models a) Outsourcing of O&Mb) Viability Gap Funding (VGF)c) Hybrid Annuity Model
Particulars OutputFinancing : Equity: Debt 30:70Debt in form of Term Loan from domestic market with 10 +2 repayment Period and 10% pa interest rateWACC 13.80%Aggregate Project Cost to Pvt. Player @ 2017 prices (Rs. Crore) 40504VGF (Rs Crore) @ 40% of Est Project Cost (Maximum Limit) 16465Project IRR 9.44%Equity IRR 12.06%Minimum DSCR 0.47
PPP Models – Viability Gap Funding
Outcome
• The project is not viable under this model
• The returns would not be attractive to the private sector unless it is convinced about revenuepotential of property development as well as VGF is further increased .
• To get acceptable level of PIRR of 11% and EIRR of 18% plus, the actual viability gap rises to 55% whichis not permitted as per Govt. policy (max 40%) However DSCR may still remain below 1.
Project Structure
• A Private Player will Finance, Build, Operate and Maintain the project. All the risks, except Landacquisition risk, will be borne by private sector.
• Private Player will retain fare and TOD revenue. Govt will retain Cess on Property Transactions,Revenue from Sale of add. FAR.
• Govt will pay Viability Gap Funding on Project Completion cost.
Key Limitations
Implementation models
Following models are assessed;
1) Public Sector Model
2) Public Private Partnership Models a) Outsourcing of O&Mb) Viability Gap Funding (VGF)c) Hybrid Annuity Model
26
NCRTCStateGovt.
(Delhi,Haryana,Rajasthan)
Shareholder’sAgreement
50% 50%
LandAcquisition
Alignment&Formation
PDandStationsBldgs.
R&R
EPCContracts
Lenders(JICA/WB/
ADB)
LoanAgr.
Revenue- Fare-Ad
-License- Carboncredits
P-Way,TractionandPower
RollingStock
SignalingandTelecom
Utilities
TechnologyandOps.
Company(Pvt.)
CivilMaintenance
RollingStock,
E&MMaintenance
LendersBanks/FI
Concession
SPV
PrivateSectorCompany
Annuity payments for 15 years
Proposed Hybrid Annuity Model for DGRA RRTS Project Structure
Revenue- PropertyDevelopment
- Cess ontransaction
- SaleofaddlFAR
Item SPV Tech Ops TotalGovt. Land 12 0 12Pvt. Land 5417 0 5417Alignment and Formation 14678 0 14678Station Buildings 3013 0 3013E & M Works 0 1046 1046Depot 450 0 450Permanent Way 0 1699 1699Traction and Power 0 2521 2521Signalling and Telecom 0 1967 1967Rolling Stock (BG) 0 3174 3174Utilities 0 298 298Environmental, social and R&R costs 58 0 58CISF Barracks and Security equipments 150 0 150Special noise & vibration reduction treatment
100 0 100
Feeder Buses 0 132 132Miscellaneous Cost 127 127 254General Charges including Design Charges 929 549 1477Contingencies 585 345 1093Total without IDC and escalation 25519 11858 37539Share in un-escalated cost 68% 32% 100%
PPP Models – Hybrid Annuity Model
PPP Models – Hybrid Annuity Model S.
No.Means of Finance Contribution (%)
Project Cost Escalated (Rs. Crore)
SPV (Public Sector)1 Equity Contribution 26.15% 9334A Govt. of India 13.07% 4667B GNCT- Delhi 3.34% 1193C Govt. of Haryana 7.47% 2665D Govt. of Rajasthan 2.26% 8082 RRTF 5.00% 17853 Soft Loan (Multilaterals) 60% 21418
4Int. free Sub debt from state Government for land
0.04% 14
5Int. free Sub debt from Central & State govt. for Tax on project Goods
9% 3146
A Govt. of India 4.48% 1573B GNCT- Delhi 1.15% 402C Govt. of Haryana 2.56% 898D Govt. of Rajasthan 0.78% 272
Total of above 100% 35697Tech Ops Company (Private Sector)
Equity Contribution 30% 6272Senior Commercial debt@10% 70% 14635Total of above 100% 20907
Aggregate Total Govt. SPV and Tech Ops (Rs. Crores) 56604
29
PPP Models – Hybrid Annuity Model Returns
The Govt SPV will pay Annuity to the Tech.Ops appreciating latter’s viability (desired PIRR of 15% and EIRR of 18%) and capacity to serve the debt in time (DSCR > 1 during repayment period).
Returns for Tech Ops
• EIRR of 18% and Avg. DSCR of 1.4 on behest of;
• Annuity of Rs. 1550 crore per year for 15 years (cumulatively Rs. 23250 crores)• Revenue from fare box, advertisement and licenses
Returns for Govt SPV
• PIRR of 2.3% which is less than WACC of 5.33%. Average DSCR > 1 • Annuity Payout can be financed through revenue from Property Development, Cess on Property Transactions and Sale of FAR.
Model Limitations
• The project cost is escalated due to the need to service high cost private capital through annuities.
• Risky revenues sources like property development, cess, additional FAR etc. are with Govt. SPV while more certain fare revenue is with private sector SPV.
Conclusion
Model Construction O&MProperty
DevelopmentAttractiveness
Public Sector SPV SPV SPV HigherOutsourcing of O&M SPV Pvt. Sector SPV Limited
VGF Pvt. Sector Pvt. Sector Pvt. Sector LimitedHybrid Annuity SPV and Pvt. Sector Pvt. Sector SPV Moderate
Public Sector Model is recommendable due to following reasons;• Described public sector model is able to achieve threshold of 8% financial return.
• Cost of funding is lower for public sector. Access to low interest and high gestationmultilateral funding makes the project viable.
• Better in handling the risks of ROW clearance, land acquisition, urban development, TODand key approvals
• Higher concessions and supports from the Government in terms of equity support, interestfree sub-debt, property development rights, collection of cess and sale of FAR.
• The private sector capacity in metro development operations is evolving. Significantcapacity and understanding gaps can be disastrous for large scale projects.
• The option to outsource O&M can be worked out provided supporting regulatory frameworkgets into place as described in Model 1.
Part II – Economic Analysis
Sequence of Economic Analysis
• Conceptual Framework – Economic Analysis• Estimated Economic Costs and Benefits• Outcome
Conceptual Framework
RRTS Project
Inputs from Traffic demand Model (Passenger forecast, diverted trips etc.)
Life Cycle Economic Cost Life Cycle Economic Benefits
Conversion of Financial Cost toEconomic Cost by excluding taxes,subsidies, interest payment andthereafter applying StandardConversation factors of 0.9 to financialcost.
1. Project Cost2. O&M Cost3. Asset Replacement
Benefits accrued owing to Diversion ofTraffic from alternate mode leads (i.eRoads and Rails) to RRTS Project.
Benefits derived by Comparing user cost inWith Project and Do- Noting or Alternativescenario.
1. Quantifiable Benefits .a) Fuel Savings.b) Savings in Vehicle Operating
Costs (VOC) of ExistingSystem (Depreciation andMaintenance Cost).
c) Time Savingd) Savings in Infrastructure
Maintenance Costs.e) Pollution reductionf) Accident reduction
2. Non Quantifiable Benefits
Economic Viability Parameters • Economic Internal Rate of Return• Economic Net Present Value• Benefit/Cost Ratio
Sensitivity Analysis with respect to key parameters.
Objective : To Evaluate/Measure the Contribution of Project to Society and Region's Economy
Estimates of Economic Cost and Economic Benefits
Sr. No. Particulars Amount in Present Value terms (at 12% discount rate)
(Rs Crore)Economic Cost (A)
1 Capital Cost (Without Land) 19042
2 Maintenance Cost during operational period 4242
Total Economic Cost 23284Economic Benefits (B)
1 Fuel Savings 99012 Savings in VOC of Diverted Trips
(Depreciation cost + Maintenance Cost ) 4266
3 Time Savings 276644 Infrastructure Maintenance Cost Savings 7475 Accident Reduction Benefits 11416 Pollution Reduction 1530
Total Economic Benefits 45353Net Benefits (B-A) 22069
Key Features
• The Project shall also lead to significant savings in highway lanes and corresponding land acquisition costfor the additional highway lanes owing to diversion of vehicular road traffic to RRTS.
• The benefits of RRTS project shall also accrue to non diverted trips (i.e Residual Traffic ) due to lowercongestions. These benefits have not been captured.
Outcome of Economic Analysis
Particulars Economic Internal Rate of
Return
Economic Net Present Value (ENPV) @ 12% Discount rate
(Rs Crores)
Benefits to cost ratio
Without land cost 17.92% 22069 1.95With land cost 16.58% 18753 1.70
• Project provides 17.92% and 16.58% of E-IRR in without land and with land costscenario which are higher than the social opportunity cost of capital i.e.12% normallyused in the Asian context by ADB and World Bank. Thus on these counts, the returns arehigher than the opportunity cost.
• Further it also provides 1.95 of benefits to cost ratio indicating 95% higher benefitswould be accrued to the economy than the economic cost of the project if project isundertaken.
Economic Viability of Project under different sensitivities
Particular Economic Internal Rate of Return
Without Land cost With Land CostIncrease in Economic Cost of the Project (capex + opex) by 15%. 16.61% 15.32%
Decrease in benefits by 15%. 16.40% 15.10%Combined scenario of increase in Economic Cost of the Project by 15% and decrease in Economic benefits by 15%.
15.13% 13.92%
§ Project provides E-IRR of 13.92% in with land cost scenario under the most pessimisticcombined scenario of increase in economic Cost of the Project by 15% and decrease ineconomic benefits by 15% which is also determined to be higher than social cost of capital.
§ Project also provides many non quantifiable benefits as well as benefits to non divertedtrips which may further improve economic rate of returns.
§ Thus project is determined to be economically viable.
Thank you