Feasibility Study and Detailed Project Report for Six Bypasses on Gurgaon - Kotputli - Jaipur Section of NH-8 PROGRESS REPORT 1.0 Introduction The Ministry of Road Transport & Highways (MoRT&H) acting through the National Highways Authority of India (NHAI) has decided to provide 6-lane divided carriageway configuration bypasses for Manesar, Dharuhera, Behror, Kotputli, Paota and Shahpura towns on Gurgaon-Kotputli-Jaipur Section of NH-8. RITES has been entrusted with Consultancy services for preparation of Feasibility Study and Detailed Project Report for 6-Bypass for Manesar, Dharuhera, Behror, Kotputli, Paota and Shahpura towns on Gurgaon-Kotputli-Jaipur Section of NH-8 by National Highways Authority of India. The letter of Acceptance has been issued by National Highways Authority of India vide letter No. NHAI/12011/1/Bypasses/2010/ Raj/550 dated 9th July 2011. The Contract Agreement for the services has been signed on 7th September 2011, subsequently the letter of commencement has been issued by the Client, NHAI vide letter no. NHAI/12011/1/Bypasses/2010/Raj/2694 dated 7th September 2011. The project is located in two states namely Haryana and Rajasthan. The location of bypasses and relevant details are mentioned below.
Sl. No. Name of Town
Tentative extent of Towns Length (km)Northing (N) Easting (E) From (km) To (km)
1. Manesar 28°-21’-18” 76°-56’-16” 47.500 50.000 2.502. Dharuhera 28°-12’-30” 76°-47’-30” 67.000 73.850 6.853. Behror 27°-53’-30” 76°-16’-46” 131.050 135.570 4.524. Kotputli 27°-42’-43” 76°-12’-11” 153.170 159.520 6.355. Paota 27°-35’-09” 76°-04’-24” 174.400 176.000 1.606. Shahpura 27°-22’-01” 75°-57’-42” 199.800 203.500 3.70Total Length (km) 50.0
2.0 Report Submission Quality Assurance Plan (QAP) The Quality Assurance Plan was discussed during a meeting with PIU Jaipur officials and accordingly QAP was submitted by the Consultant vide letter No. RITES/HW/NHAI/9014-30/6-BYPASSES/DPR/2011 dated 12th September 2011. Inception Report (IR)
The Inception Report have been prepared satisfying the ToR as well as the valuable suggestions deliberated and discussed at PIU Jaipur. The Inception Report had already been submitted by the Consultant vide letter No. RITES/HW/NHAI/9014-30/6-BYPASSES/DPR/2011 dated 16th September 2011. 3.0 Status of the Project 3.1 Mobilization Upon signing of contract Agreement between NHAI and RITES Ltd., the Consultants mobilized the teams for conducting different aspects of the study. The team for the present study comprising of the Senior Highway Engineer/Team Leader, Highway Engineer, Pavement Specialist, Bridge Engineer, Traffic Engineer, Material-cum-Geotechnical Engineer, Senior Survey Engineer, Financial Analyst, Environmental Specialist and Resettlement & Rehabilitation Specialist Quantity Surveyor/Documentation Expert. These personnel were assembled in Gurgaon, the head quarters, to formulate an effective work programme for the successful completion of the project to the entire satisfaction of the client. Several Meetings were also held with NHAI officials at Delhi office and Jaipur, PIU to streamline the work programme and effective completion of the work. Presently the project status is as under: 3.2 Survey instruments mobilized at site
Sl. No.
Instrument Quantity
1. Hand Held GPS 4 nos.2. Lap top Computers 4 nos.3. Axle Load Pad 4 nos.
3.3 Progress of Field Work
1.
Traffic survey: Date Status
7 days Classified Traffic Volume Count Study at 3 locations:(i) Manoharpur Toll Plaza (km 211)(ii) Shahajahanpur (km 116)(iii) Manesar (Kherki Daula at km 42)
14.10.2011To22.10.2011
Completed
3 days confirmatory Classified
22.10.2011To
Completed
Traffic Volume Count Study at 3 locations:(i) Dharuhera (km 64/860)(ii) Kotputli (km 152/050)(iii) Paota (km 179/950)
25.10.2011
2.
Origin and Destination (O-D) Survey at 3 locations:(i) Manoharpur Toll Plaza (km 211)(ii) Shahajahanpur (km 116)(iii) Manesar (Kherki Daula at km 42)
17.10.2011To23.10.2011
Completed
3.
Axle Load Survey at 2 locations:(i) Manoharpur Toll Plaza (km 211)(ii) Shahajahanpur (km 116)
17.10.2011 to 20.10.2011
Completed
3.4 Meetings and Discussions The consultants have made various meetings/discussions with NHAI and other government officials to formulate the entire work for successful completion of the project. The details of such meetings are as follows:
Sl. No Date Location/ Place
Contact Official RITES Representative
Remarks
1 14.7.2011 Shahpura Tehsildar, Shahpura and Tehsil Revenue Accountant (TRA)
RITES representatives S. Vishu Kumar, Vijay Kumar, Ishwar Singh, Rahul Kr. Tewary, Manoj Kr. Sahani,
Discussed regarding land issues, rates, availability of khasara maps and apprised about the project.
2 15.7.2011 Shahpura Shri. Madan Lal Meena, Patwari, Shahpura
RITES representatives S. Vishu Kumar, Vijay Kumar, Ishwar Singh, Rahul Kr. Tewary, Manoj Kr. Sahani,
Information regarding land rate and appraised about the project for land related issues.
3 16.7.2011 Kotputli and Paota
Tehsil Revenue Accountant (TRA), Kotputli
RITES representatives S. Vishu Kumar, Vijay Kumar, Ishwar Singh, Rahul Kr. Tewary, Manoj Kr. Sahani,
Information regarding land rate and appraised about the project for land related issues.
4 27.7.2011 Jaipur Sri Rakesh Gupta, PD, PIU, Jaipur
Rahul Kr. Tewary, AM/HW
Meeting with the Project Director, PIU, Jaipur and appraised about the project.
5 08.08.2011
Manesar Sri R K Manchanda GM Design & Construction PECPL Office
RITES representatives Ishwar Singh, R K Tewary
Requested about the design and drawings of existing project to interface the proposal of proposed bypasses with existing road.
6 19.08.2011
Kotputli Sri Vivek Mehta RITES representativesIshwar singh, RK Tewary, JK Yadav, MK Sahani, Harsh Kr., Prashant Singh, Bharat Singh
Discussed about the source of materials and available data available at Toll locations.
7 01.09.2011
Manesar Sri R K Manchanda PECPL Office
RITES representatives Ishwar Singh, R K Tewary
Requested about the design and drawings of existing project to interface the proposal of proposed bypasses with existing road.
8 15.09.2011
Jaipur Sri Rakesh Gupta, PD, PIU, Jaipur
Ishwar Singh, Rahul Kr. Tewary
Meeting with the Project Director, PIU, Jaipur and discussion on alignment corridor of proposed bypasses.
9 10.10.2011
Jaipur Sri P R Patelia, CGM, RO, Rajasthan, Jaipur
RITES representatives S. Vishu Kumar, Vijay Kumar, Ishwar Singh, J K Yadav
Meeting with theCGM, RO, Rajasthan, at Jaipur, and appraised the alignment corridor of proposed bypasses.
10 10.10.2011
Jaipur Sri Rakesh Gupta, PD, PIU, Jaipur
RITES representatives S. Vishu Kumar, Vijay Kumar, Ishwar Singh, J K Yadav.
Meeting with the Project Director, PIU, Jaipur and discussion on modified alignment corridor of proposed bypasses as suggested by the Project Director in the last meeting held on 15.09.2011.
11 12.10.2011
Shahpura Patwaris of Shahpura Tehsil1. Sri Madan Lal Meena2. Sri Rajendra Kr.
RITES representatives S. Vishu Kumar, Vijay Kumar, Ishwar Singh, J K
Requested Khasara maps for transfer of proposed alignment corridors on khasara maps and information
Sl. No Date Location/ Place
Contact Official RITES Representative
Remarks
Sharma3. Sri Shravan Lal Kumawat4. Sri Ashok Kr Sharma5. Sri Ram Pal Yadav6. Sri Prithvi Singh Sekhawat7. Sri Kalu Ram Chaudhary
Yadav. regarding “Delhi Panth” Road at Shahpura.
12 14.10.2011
Kotputli Patwaris of Kotputli Tehsil1. Sri Phool Chand Verma2. Sri Hardan Singh Chaudhary3. Sri Naresh Kr Sharma4. Sri Satyavir Mukkar5. Sri Rajmal Meena
RITES representatives Ishwar Singh, J K Yadav, R K Tewary
Requested Khasara maps for transfer of proposed alignment corridors on Khasara map of each affected village
During the meeting held with Tehsildar of Shahpura, Kotputli and Behror, it was informed that the Khasara maps of each village will be provided against the payment of each khasara falling in each village map. At this stage of work, the consultant requires the copy of the revenue map only for transfer of alignment corridor on the khasara maps. The Project Director, NHAI, PIU, Jaipur is requested to help in this matter in obtaining Khasara maps at a nominal fee for desk study purposes, because unless otherwise without transferring proposed alignment corridor on the Khasara maps, affected khasaras will not be identified. For the affected khasaras required for preparation of 3D Gazette notification informations, the payment would be made for each affected khasaras accordingly. 3.5 Way Forward Presentation of proposed alignment corridor options at NHAI (HQ) and subsequent approval of alignment corridors shall enable the Consultant to proceed further for design and preparation of Quality Report and submission of various submittals. 3.6 Reasons for Delay, if any The project progress was hampered due to the following reasons: i) Road alignment study was hampered due to rainy season and sowing of crops.ii) Remaining field study could not be completed due to pending harvesting of crops.iii) The important activity of traffic study was not completed during September-October months due to important festival seasons which would affect the normal traffic by the induced traffic due to festival seasons. 3.7 Project Report Submission
The schedule of submission of the project report is as under:
Sl. No.
Content Schedule of Submission
1. Feasibility Report 20.11.20112. Preliminary Project Report 30.11.20113. Detailed Project Report 01.12.2011
3.8 Outstanding Issues (a) Approval on Inception Report (IR)(b) Technical Presentation 3.9 Conclusion Even though, initial delay has been seen in the project, RITES is committed to complete the study in time. The project completion would be within the stipulated time period. 3.10 Contact Details
M/s RITES Ltd.ROC Gurgaon4th Floor, Highway DivisionPlot-1, Sector-29Gurgaon-122001 (Haryana)Ph. #: 0124-2818418, 2818416, 2818426, 2818410, 2818483Fax #: 0124-2571645