Upload
mena-march
View
218
Download
0
Embed Size (px)
Citation preview
7/25/2019 FE6003 04 Handout
1/16
FE 6003 CORPORATEFINANCE
Asst.Prof.Dr. Pariyada Sukcharoensin
FE
6003CO
RPORATE
FINANCE
Overview of Corporate Finance
Theory of The Firm
Time Value of Money
Capital Budgeting Process and Techniques
Cost of Capital
Capital Structure: Part I
Capital Structure: Part II
1
2
3
4
5
6
7
Asst.Prof.Dr. Pariyada Sukcharoensin 2
Theory of the Firm2
Dividend Policy8
FE
6003CORPO
RATE
FINANCE
Mergers and Acquisitions
Mid-term Report Presentation
Company Visit
Special Issues in Capital Budgeting
Risk Analysis in Capital Budgeting
Case Study Analysis
9
11
12
13
14
15
Asst.Prof.Dr. Pariyada Sukcharoensin 3
Growth Strategy10
FE
6003CORPO
RATE
FINANCE
1 Wed. 13/1/2016 9.00-12.00 Overview of Corporate Finance
2 Wed. 20/1/2016 9.00-12.00 Theory of the Firm
3 Wed. 27/1/2016 9.00-12.00 Time Value of Money
4 Wed. 3/2/2016 9.00-12.00 Capital Budgeting Process and Techniques5 Wed. 3/2/2016 13.00-16.00 Cost of Capital
6 Wed. 10/2/2016 9.00-12.00 Capital Structure: Part I
7 Wed. 10/2/2016 13.00-16.00 Capital Structure: Part II
8 Wed. 17/2/2016 9.00-12.00 Dividend Policy
9 Wed. 24/2/2016 9.00-12.00 Mergers and Acquisitions
10 Wed. 2/3/2016 9.00-12.00 Growth Strategy
11 Wed. 23/3/2016 9.00-12.00 Mid-term Report Presentation
12 Wed. 30/3/2016 13.00-16.00 Company Visit
13 Wed. 20/4/2016 9.00-12.00 Special Issues in Capital Budgeting
14 Wed. 27/4/2016 13.00-16.00 Risk Analysis in Capital Budgeting
15 Wed. 11/5/2016 9.00-12.00 Case Study Analysis
Final Exam
4Asst.Prof.Dr. Pariyada Sukcharoensin
COURSESCHEDULE
7/25/2019 FE6003 04 Handout
2/16
CAPITALBUDGETING
FE
6003CO
RPORATE
FINANCE
(CAPITALBUDGETING)
Asst.Prof.Dr. Pariyada Sukcharoensin 6
FE
6003CORPO
RATE
FINANCE
CAPITALBUDGETINGDECISION
Asst.Prof.Dr. Pariyada Sukcharoensin 7
Identifying potentialinvestments
Reviewing, analyzing, andselecting from the proposals
that have been generated
Implementing andmonitoring the proposalsthat have been selected
Managers
should separate
investment and
financing
decisions
FE
6003CORPO
RATE
FINANCE
CapitalBudgeting
Account for thetime value of
money
Account for risk
Focus on cashflow
Rank competingprojectsappropriately
Lead toinvestment
decisions thatmaximize
shareholderswealth
8Asst.Prof.Dr. Pariyada Sukcharoensin
CAPITALBUDGETING
7/25/2019 FE6003 04 Handout
3/16
FE
6003CO
RPORATE
FINANCE
/
9Asst.Prof.Dr. Pariyada Sukcharoensin
CAPITALBUDGETINGPROCESSFE
6003CO
RPORATE
FINANCE
Asst.Prof.Dr. Pariyada Sukcharoensin
TYPEOFPROJECTS
(Mutually exclusive project) 1
(Independent project)
2
(Dependent project)
Complementary Substitute
10
CAPITALBUDGETINGDECISIONTECHNIQUES
FE
6003CORPO
RATE
FINANCE
CAPITALBUDGETINGDECISIONTECHNIQUES
Capital
Budgeting
Decision
Techniques
PB
DPB
NPV
IRR
MIRR
PI
12Asst.Prof.Dr. Pariyada Sukcharoensin
7/25/2019 FE6003 04 Handout
4/16
PAYBACKPERIOD: PB
FE
6003CO
RPORATE
FINANCE
(PAYBACKPERIOD: PB)
Asst.Prof.Dr. Pariyada Sukcharoensin 14
PB = (t)
+ t
FE
6003CORPO
RATE
FINANCE
15Asst.Prof.Dr. Pariyada Sukcharoensin
PROJECTB
PROJECTA
PBA =
CFt -100 10 60 80
Cumulative
0 1 2 3
CFt -100 70 50 20
Cumulative
0 1 2 3
PBB =
FE
6003CORPO
RATE
FINANCE
(PB RULE)
(PB < cutoff period)
(PB > cutoff period)
Asst.Prof.Dr. Pariyada Sukcharoensin 16
7/25/2019 FE6003 04 Handout
5/16
FE
6003CO
RPORATE
FINANCE
PROSANDCONSOFPAYBACKPERIOD
Asst.Prof.Dr. Pariyada Sukcharoensin 17
PROS
CONS
DISCOUNTEDPAYBACKPERIOD: DPB
FE
6003CORPO
RATE
FINANCE
(DISCOUNTEDPAYBACKPERIOD: DPB)
PB
Asst.Prof.Dr. Pariyada Sukcharoensin 19
FE
6003CORPO
RATE
FINANCE
20Asst.Prof.Dr. Pariyada Sukcharoensin
PROJECTB
PROJECTA
DPBA =
CFt -100 10 60 80
Cumulative
0 1 2 3
CFt -100 70 50 20
Cumulative
0 1 2 3
DPBB =
PV of CFt
10%
10%
PV of CFt
7/25/2019 FE6003 04 Handout
6/16
FE
6003CO
RPORATE
FINANCE
(DPB RULE)
(DPB < cutoff period)
(DPB > cutoff period)
Asst.Prof.Dr. Pariyada Sukcharoensin 21
FE
6003CO
RPORATE
FINANCE
PROSANDCONSOFDISCOUNTEDPAYBACKPERIOD
Asst.Prof.Dr. Pariyada Sukcharoensin 22
PROS
CONS
NETPRESENTVALUE: NPV
FE
6003CORPO
RATE
FINANCE
(NETPRESENTVALUE: NPV)
Asst.Prof.Dr. Pariyada Sukcharoensin 24
Choosingthe
appropriatediscount
rateaccounted
for risk
Discountingcash flowsaccountedfor the time
value ofmoney
The presentvalue of aprojects
cashinflows and
outflows
7/25/2019 FE6003 04 Handout
7/16
FE
6003CO
RPORATE
FINANCE
(NETPRESENTVALUE: NPV)
CFi = period ik =
Asst.Prof.Dr. Pariyada Sukcharoensin 25
FE
6003CO
RPORATE
FINANCE
26Asst.Prof.Dr. Pariyada Sukcharoensin
PROJECTB
PROJECTA
NPVA=
CFt -100 10 60 80
PV of CFt
0 1 2 3
CFt
-100 70 50 20
PV of CFt
0 1 2 3
NPVB=
10%
10%
FE
6003CORPO
RATE
FINANCE
DISCOUNTRATE
Asst.Prof.Dr. Pariyada Sukcharoensin 27
is a key input in NPV analysis
represents the minimum return that the projectmust earn to satisfy investors
varies with the risk of the firm and/or the risk ofthe project
FE
6003CORPO
RATE
FINANCE
(NPV RULE)
(NPV > 0)
(NPV < 0)
Asst.Prof.Dr. Pariyada Sukcharoensin 28
7/25/2019 FE6003 04 Handout
8/16
FE
6003CORPORATE
FINANCE
PROSANDCONSOFNETPRESENTVALUE
Asst.Prof.Dr. Pariyada Sukcharoensin 29
PROS
CONS
INTERNALRATEOFRETURN: IRR
FE
6003CORPO
RATE
FINANCE
(INTERNALRATEOFRETURN: IRR)
NPV
Asst.Prof.Dr. Pariyada Sukcharoensin 31
FE
6003CORPO
RATE
FINANCE
32Asst.Prof.Dr. Pariyada Sukcharoensin
PROJECTB
PROJECTA
IRRA=
CFt -100 10 60 80
0 1 2 3
CFt -100 70 50 20
0 1 2 3
IRRB=
IRR
IRR
7/25/2019 FE6003 04 Handout
9/16
FE
6003CORPORATE
FINANCE
NPV PROFILES
Asst.Prof.Dr. Pariyada Sukcharoensin 33
NPV Profiles NPV
IRR NPV ProfilesIRR NPV 0
FE
6003CORPORATE
FINANCE
C
34Asst.Prof.Dr. Pariyada Sukcharoensin
EXAMPLE: FINDIRR FROMNPV PROFILES
0
300
1
350
2
400
310%
320
4
PV0=
-1,000
FE
6003CORPO
RATE
FINANCE
EXAMPLE: FINDIRR FROMNPV PROFILES
C
0%
2%
4%
6%
8%
10%
12%
14%
16%
Asst.Prof.Dr. Pariyada Sukcharoensin35
FE
6003CORPO
RATE
FINANCE
EXAMPLE: FINDIRR FROMNPV PROFILES
Asst.Prof.Dr. Pariyada Sukcharoensin 36
IRRC = 13.61%
7/25/2019 FE6003 04 Handout
10/16
FE
6003CORPORATE
FINANCE
(IRR RULE)
(IRR > WACC)
(IRR < WACC)
Asst.Prof.Dr. Pariyada Sukcharoensin 37
FE
6003CORPORATE
FINANCE
PROSANDCONSOFINTERNALRATEOFRETURN
Asst.Prof.Dr. Pariyada Sukcharoensin 38
PROS
CONS
Lending vs.Borrowing
FE
6003CORPO
RATE
FINANCE
IRR Criteria
Invest when IRR > WACC
IRR Criteria
Invest when IRR < WACC
Lending Borrowing
39Asst.Prof.Dr. Pariyada Sukcharoensin
Discount
rate
IRR
NPV
Discount
rate
IRR
NPV
FE
6003CORPO
RATE
FINANCE
40Asst.Prof.Dr. Pariyada Sukcharoensin
EXAMPLE: LENDINGVSBORROWING
Year 0 1 2 3 4 5 IRR
Project 1 -1,000 200 200 300 350 500
Project 2 1,000 -200 -200 -300 -350 -500
Investment project.
The cash flow is negative in period 0, and positive in futureperiods.
Project 1
Borrowing project.
The initial cash flow is positive (the amount borrowed), and thesucceeding cash flows are negative (the repayment schedule).
Project 2
7/25/2019 FE6003 04 Handout
11/16
FE
6003CORPORATE
FINANCE
41Asst.Prof.Dr. Pariyada Sukcharoensin
EXAMPLE: LENDINGVSBORROWINGFE
6003CORPORATE
FINANCE
NON-NORMALCASHFLOWS& MULTIPLEIRRS
If a project has more than one change in the
sign of cash flows (non-normal cash flows),
there may be multiple IRRs. i.e. four changes in sign of CFs then have
four different IRRs
Though odd pattern, can be observed in high-
tech and other industries.
Asst.Prof.Dr. Pariyada Sukcharoensin 42
FE
6003CORPO
RATE
FINANCE
43Asst.Prof.Dr. Pariyada Sukcharoensin
EXAMPLE: NON-NORMALCASHFLOWS
0
800
1
350
2
400
3
-620
4
-1,000
0
800
1
-350
2
400
3
620
4
-1,000
0
800
1
-350
2
400
3
-620
4
-1,000
FE
6003CORPO
RATE
FINANCE
EXAMPLE: MULTIPLEIRRS
Asst.Prof.Dr. Pariyada Sukcharoensin 44
When project cash flows have multiple sign changes,
there can be multiple IRRs With multiple IRRs, which do we compare with the
cost of capital to accept/reject the project?
NPV
NPV0
NPV>0
Discount
rateNPV
7/25/2019 FE6003 04 Handout
12/16
FE
6003CORPORATE
FINANCE
45Asst.Prof.Dr. Pariyada Sukcharoensin
EXAMPLE: NON-NORMALCASHFLOWS
Year 0 1 2 3 4 5 IRR
Project 3 400 0 11,000 -8,800 -26,250 24,200
NPV
Discount
rate
FE
6003CORPORATE
FINANCE
EXAMPLE: MUTUALLYEXCLUSIVEPROJECTS
A
B
0%
5%
10% 18.78 19.99
15%
20%
25%
Asst.Prof.Dr. Pariyada Sukcharoensin46
NPV profile IRR A B
FE
6003CORPO
RATE
FINANCE
IRR VS. NPV
Asst.Prof.Dr. Pariyada Sukcharoensin 47
-10
0
10
20
30
40
50
60
5 10 15 20
NPV
Discount Rate (%)
IRRA=
IRRB=
Crossover Point
BA
..
...
.
.
..
.
25
IRRA< IRRB
NPVA= NPVB
FE
6003CORPO
RATE
FINANCE
48Asst.Prof.Dr. Pariyada Sukcharoensin
EXAMPLE: CROSSOVERPOINT
Project A: CFt -100 10 60 80
0 1 2 3
Project B: CFt -100 70 50 20
IRRDiff=
Diff: CFt
7/25/2019 FE6003 04 Handout
13/16
FE
6003CORPORATE
FINANCE
CONFLICTSBETWEENNPVANDIRR
NPV and IRRdo not alwaysagree when
rankingcompeting
projects
Asst.Prof.Dr. Pariyada Sukcharoensin 49
MODIFIEDINTERNALRATEOFRETURN: MIRR
FE
6003CORPO
RATE
FINANCE
MIRR is the discount rate which causes the
NPV of a project to equal zero.
MIRR is designed to deal with the non-normal
cash flows.
51Asst.Prof.Dr. Pariyada Sukcharoensin
(MIRR)FE
6003CORPO
RATE
FINANCE
PROJECTA
Asst.Prof.Dr. Pariyada Sukcharoensin 52
-100.0 10.0 60.0 80.0
0 1 2 310%
-100.0MIRR
MIRRA=
0 = -100 +(1 + MIRRA)
3
10%
10%
7/25/2019 FE6003 04 Handout
14/16
FE
6003CORPORATE
FINANCE
PROJECTB
Asst.Prof.Dr. Pariyada Sukcharoensin 53
-100.0 70.0 50.0 20.0
0 1 2 310%
-100.0MIRR
MIRRB=
10%
10%
(1 + MIRRB)3
0 = -100 +
FE
6003CORPORATE
FINANCE
(MIRR RULE)
(MIRR > WACC)
(MIRR < WACC)
Asst.Prof.Dr. Pariyada Sukcharoensin 54
FE
6003CORPO
RATE
FINANCE
PROSANDCONSOFMODIFIEDINTERNALRATEOFRETURN
Asst.Prof.Dr. Pariyada Sukcharoensin 55
PROS
CONS
PROFITABILITYINDEX: PI
7/25/2019 FE6003 04 Handout
15/16
FE
6003COR
PORATE
FINANCE
(PROFITABILITYINDEX: PI)
Asst.Prof.Dr. Pariyada Sukcharoensin 57
FE
6003COR
PORATE
FINANCE
58Asst.Prof.Dr. Pariyada Sukcharoensin
PROJECTB
PROJECTA
NPVA=
CFt -100 10 60 80
0 1 2 3
CFt -100 70 50 20
0 1 2 3
NPVB=
10%
10%
PIA=
PIB=
FE
6003CORPO
RATE
FINANCE
(PI RULE)
1.0 (PI > 1.0)
1.0 (PI < 1.0)
Asst.Prof.Dr. Pariyada Sukcharoensin 59
FE
6003CORPO
RATE
FINANCE
PROSANDCONSOFPROFITABILITYINDEX
Asst.Prof.Dr. Pariyada Sukcharoensin 60
PROS
CONS
7/25/2019 FE6003 04 Handout
16/16
FE
6003COR
PORATE
FINANCE
PROJECTAPB =
DPB =
NPV =
IRR =
MIRR =
PI =
PROJECTBPB =
DPB =
NPV =
IRR =
MIRR =
PI =
61Asst.Prof.Dr. Pariyada Sukcharoensin
CAPITALBUDGETINGDECISION: PI
THEEND