FCPS Liberty Elementary School Feasibility Study Meeting #5 – Notes PAA Project #18‐35 Meeting Date: January 31, 2019 – FCPS Central Office Board Room Meeting started at 2:00 pm Meeting ended at 3:50 pm Attendees: FCPS Educational Planning Team Holly Nelson – FCPS Facilities Planner Brian Staiger – FCPS Senior Construction Project Manager Adnan Mamoon – FCPS Director of Capital Programs Kim Day – FCPS Curriculum & Instruction Steve Raff – FCPS Elementary Director Dawn Worrell – FCPS Construction Accountant Patrick Little – FCPS Maintenance Todd Shaffer – Principal, Liberty Elementary School Design Team Kori Purdum Matheis – Proffitt & Associates – Principal Architect Madalyn Burns – Proffitt & Associates – Senior Architectural Designer Meeting Discussion: 5.1 Project Overview A. Schedule – Kori provide an update on the schedule, we are two‐thirds of the way done design options and are on track for completion of the draft study booklet by March. B. Existing Conditions Report Status – Kori provided an update that we have the report 99% complete and will have a draft report to Holly by the beginning of next week. C. ALTA Survey Status – Due to the weather, Adtek is 3‐4 weeks behind on the ALTA survey. It should be complete by late February. 5.2 Review updated conceptual design options and proposed phasing of construction A. Option 1 ‐ Renovations and Additions with partial demolition 1. In this option:

FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

FCPS Liberty Elementary School  Feasibility Study Meeting #5 – Notes PAA Project #18‐35  

Meeting Date: January 31, 2019 – FCPS Central Office Board Room Meeting started at 2:00 pm  Meeting ended at 3:50 pm 

Attendees: FCPS Educational Planning Team Holly Nelson – FCPS Facilities Planner  Brian Staiger – FCPS Senior Construction Project Manager Adnan Mamoon – FCPS Director of Capital Programs Kim Day – FCPS Curriculum & Instruction  Steve Raff – FCPS Elementary Director Dawn Worrell – FCPS Construction Accountant Patrick Little – FCPS Maintenance Todd Shaffer – Principal, Liberty Elementary School 

Design Team Kori Purdum Matheis – Proffitt & Associates – Principal Architect Madalyn Burns – Proffitt & Associates – Senior Architectural Designer 

Meeting Discussion: 

5.1 Project Overview A. Schedule – Kori provide an update on the schedule, we are two‐thirds of the way done design

options and are on track for completion of the draft study booklet by March.B. Existing Conditions Report Status – Kori provided an update  that we have  the  report 99%

complete and will have a draft report to Holly by the beginning of next week.C. ALTA Survey Status – Due to the weather, Adtek is 3‐4 weeks behind on the ALTA survey. It

should be complete by late February.

5.2 Review updated conceptual design options and proposed phasing of construction A. Option 1 ‐ Renovations and Additions with partial demolition

1. In this option:

Page 2: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

Feasibility Study Meeting #5 – Notes Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 

a. Construction phasing was proposed as follows:Phase 1 ‐  Existing building and driveways would remain in use. Construction of

new bus loop from Daysville Road and relocation of softball field. Phase 2 ‐  New bus  loop  from Daysville  Road  completed  and  in  use.  Existing 

building  and  Route  26  driveway  would  remain  in  use.  Demolish portion of existing Daysville driveway and existing bus loop/parking. Construction  of  north  addition,  soft  and  paved  play  areas,  and building services driveway.  

Phase 3 ‐  North  addition,  play  areas,  and  building  services  driveway  are completed  and  ready  to  use.  The  north  addition  includes  a  public entrance,  Gymnasium,  Cafeteria,  food  services,  building  services, music classrooms and a classroom cluster. Existing Route 26 driveway would remain in use. All of existing 1960s building and north portion of  existing  1980s  building  retained  and  in  use.  Demolish  south portion of 1980s building  (Media Center plus  two classrooms) and entirety of 1950s building.  

Phase 4 ‐  Demolish Route 26 driveway. Construction of south addition, pre‐k play area, and car/parking loop from Route 26.  

Final ‐   South addition, pre‐k play and car/parking loop from Route 26 are all complete and ready for use. South addition includes the new entry, media center, kindergarten classrooms, art classrooms and support spaces. 

2. Pros for this layout include:a. Good separation of buses, cars, and building services/loading.b. Lots of car queuing space.

3. Cons/action items for this layout includea. Lots of concern about traffic  in and out on Route 26 – especially concern with

anticipated increased volume of car traffic. Plans will be updated to retain a carentrance point from Route 26 and create a new exit driveway to Daysville Roadat west of property.

b. Keeping existing 1960s two‐story addition and tying the new two‐story structuresinto it may create a hardship in terms of ceiling height. Ramping will be requiredalong the second floor corridor in order to provide greater floor‐to‐floor heightat the addition than in the existing building.

c. No good route/easy access directly back to classrooms after recess.d. The Media Center and many support spaces do not have access to views to the

exterior. Daylight could still be incorporated via clerestory windows however.

B. Option 2 ‐ Renovations and Additions with limited demolition1. In this option:

a. Construction phasing would be as follows:Phase 1  ‐ Existing 1950s and 1980s portion of building and driveways would

remain in use. Construction of new bus loop from Daysville Road and softball field. Demolish existing 1960s portion in its entirety. Minor 

Page 3: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

Feasibility Study Meeting #5 – Notes Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 3 of 6 

modification  to  the  existing  Daysville  driveway/bus  loop  will  be required in order to complete this phase. 

Phase 2 ‐  New bus  loop from Daysville Road and new softball  field complete and ready to use. Portion of existing building and Route 26 driveway would  remain  in  use.  Demolish  Daysville  driveway/bus  loop. Construction of east addition, soft and paved play areas, and building services driveway.  

Phase 3 ‐  East addition, play areas and building services driveway complete and ready to use. East addition includes a public entrance, Gymnasium, Cafeteria,  food  services,  building  services,  music,  and  a  two‐story addition with  kindergarten  classrooms  and  support  spaces  on  the lower  level  and  new  classrooms  and  support  spaces  on  the main level. Renovation of existing gymnasium and cafeteria. Existing Route 26 driveway would be demolished. Construction of drop‐off/parking loop from Route 26. 

Phase 4 ‐  Drop‐off/parking loop from Route 26 is complete and ready to use.  Existing gymnasium has been renovated and is ready to occupy as a new media  center.  The existing  cafeteria has  been  converted  to  a new  administration  suite  and  is  ready  to  occupy.  Renovation  of existing administration and media center spaces occurs once these functions can move into their newly renovated areas. 

Final ‐  Renovations  of  the  existing  administration  suite  to  serve  as  new classrooms and support spaces and existing media center to be new art classrooms are completed and ready to occupy. 

2. Pros for this layout include:a. Good separation of buses and cars.b. Lots of car queuing space.c. Seems to provide more open green space compared to Option 1.

3. Cons/action items for this layout includea. Lots of concern about traffic  in and out on Route 26 – especially concern with

anticipated increased volume of car traffic. Plans will be updated to retain a carentrance point from Route 26 and create a new exit driveway to Daysville Roadat west of property.

b. Administration  suite and new main entrance at existing  cafeteria area are notdesirable because of low ceiling heights.

c. Possible  conflicts  for  construction  of  east  classroom  addition  if  the  existingfoundations  from  the  1920s  building  were  not  fully  demolished.  Possiblyadditional costs for hazardous material abatement.

d. Not optimal route/easy access directly to classrooms after recess. Could bus loopand play areas be flipped to provide better access?

e. Kindergarten and Pre‐K are on a different floor level than gymnasium, cafeteria,and specials.

Page 4: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

Feasibility Study Meeting #5 – Notes Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 4 of 6 

C. Option 3A ‐ New construction1. An option for Replacement was presented.2. In this option:

a. The proposed school is similar to the footprint of the future elementary schoolprototype (East County Elementary).

b. The new facility is sited so that it can be constructed while the existing buildingremains  operational,  then  once  it  is  occupied,  the  existing  building  can  bedemolished.

c. The main  entry wing with  administration  and  art  classrooms  is  located  to  thesouth west and faces Route 26. One of the two‐story classroom wings is locatedto the south east and the other to the north west. The public spaces including,music, cafeteria and gymnasium are located to the north east.

d. Car rider drop off loop and main parking would be accessed from Route 26. Thedriveway entrance is relocated to the crest of the hill along Route 26 for bettervisibility.

e. Bus  loop,  additional  parking  and  building  services  would  be  accessed  fromDaysville Road.

f. Paved and soft play areas are located near the gymnasium and cafeteria.3. Pros of this layout include:

a. New school can be constructed without demolition of the existing building.b. Daylight provided to all classrooms (required).c. Good separation of buses, cars, and building services/loading.d. Lots of car queuing space.

4. Cons/action items for this layout include:a. Flip  administration  and  kindergarten  classroom  wing  for  better  second  floor

layout.b. Gymnasium is far from softball field/green space and there is a lack of level green

open  space.  Can  we  pull  play  areas  apart  to  provide more  green  space  neargymnasium/cafeteria?

c. Not possible to bring second entrance/exit from Daysville Road due to position ofbuilding.

D. Option 3B ‐ New construction1. An option for Replacement was presented.2. In this option:

a. The proposed school is similar to the footprint of the future elementary schoolprototype (East County Elementary).

b. The new facility is sited so that the existing building will be demolished and thenthe new school is constructed.

c. The main  entry wing with  administration  and  art  classrooms  is  located  to  thesouth east and faces Route 26. One of the two‐story classroom wings is locatedto the south west and the other to the north east. The public spaces including,music, cafeteria and gymnasium are located to the north west.

d. Car rider drop off loop and main parking would be accessed from Daysville.

Page 5: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

Feasibility Study Meeting #5 – Notes Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 5 of 6 

e. Bus loop, additional parking and building services would be accessed from Route26.

f. Paved and soft play areas and softball fields are located near the gymnasium andcafeteria.

3. Pros of this layout include:a. New school is constructed without students on site, which will allow for quicker

construction and safety for students.b. Daylight provided to all classrooms (required).c. Good separation of buses, cars, and building services/loading.d. Lots of car queuing space.

4. Cons/action items for this layout include:a. Students will either have to be relocated to another facility off‐site or relocatables

will need to be brought on‐site to house students during the demolition and newconstruction  process.  Costs  for  relocatables  and  transportation  need  to  befigured into the estimates for this option. FCPS will help pull some numbers forthese items.

b. Flip  administration  and  kindergarten  classroom  wing  for  better  second  floorlayout.

c. Lots of concern about bus traffic in and out on 26. Look at an option showing carsand buses enter from Daysville then split on site.

d. Not possible to bring second entrance/exit from Daysville Road.

E. General discussion during review of options:1. Steve noted that there will likely be an increased need for Pre‐K classroom space if the

Kirwan Commission push for public Pre‐K is successful.2. In all options, remove the formal softball field and replace it with open green space.

Open space  is more flexible  for curriculum use. Phys Ed classes make use of  flexiblegreen space more often than paved play or larger, formal fields.

5.3 Discuss agenda/topics and presentation for Community Meeting #2 A. Plan  to  review  basics  and  briefly  highlight  existing  building  themes  and  feedback  from

Community Meeting #1.

B. Show comparison of size of current gym vs. proposed gym and current cafeteria vs. proposedcafeteria, along with some photos of the existing school compared with a new school.

C. Review four options. Get feedback (interactive). Ask attendees ‐ what are the pros and consof each option?

D. Show construction phasing and site plans. The site view is helpful and phasing plans help showtime frame.

E. Prepare for questions regarding where the students will be located during construction (i.e.onsite, portables, relocated)

Page 6: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

Feasibility Study Meeting #5 – Notes Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 6 of 6 

F. Reiterate that these are feasibility plans and not final design. Keep floor plans general. MakePre‐K, K, and Grade 1‐5 classrooms all  the same color. Specifics will be decided during theproject design phase.

5.4 Two week look‐ahead A. The  design  team  will  prepare  for  Community  Meeting,  continue  working  on  the  existing

building  conditions  narrative,  ALTA  survey,  and  modification  of  sketch  options  of  the

replacement, additions/renovations options to share at the next meeting.

The next regular design team meeting  is scheduled for February 14, 2019 from 2:00‐4:00 PM at FCPS Central Office Board Room. 

This  summarizes  the  topics  discussed  at  the meeting.  Please  review  and  address  any  comments  and corrections to the Architect within 5 days of receipt of these minutes. 

Kori Purdum Matheis, AIA, LEED AP BD+C

Distribution via email – all attendees & design committee members 

Attachments:    Meeting #5 Presentation Slides

Page 7: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

L I B E R T Y E L E M E N TA RY S C H O O LF E A S I B I L I T Y S T U D YF R E D E R I C K C O U N T Y P U B L I C S C H O O L S

F E A S I B I L I T Y S T U D Y M E E T I N G # 5J a n u a r y 3 1 , 2 0 1 9

Page 8: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

AGENDA

MEETING TOPICS:1. Project Overview

a. Scheduleb. Existing Conditions Report Statusc. ALTA Survey Status

2. Review updated conceptual design options and proposed phasing of construction

a. Renovations and Additions with partial demolitionb. New Constructionc. Discuss pros/cons of each – which goals are addressed and which are not?

3. Discuss agenda/topics and presentation for Community Meeting #2

Page 9: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

P R O J E C T S C H E D U L E

Page 10: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

FEASIBILITY STUDY OPTIONS

P R O J E C T A P P R O A C H

1. Renovation and Addition – Limited demolition

• Strategic renovations to the exterior and interior with partial demolition and

construction of additional space.

2. Renovation and Addition – Partial Demolition

• Complete renovation of the existing facility, extensive demolition of portions of the

existing building, and construction of additional space to meet the Educational

Specification requirements.

3. New Construction – replacement

• Construction of an entirely new facility on the existing site to meet the Educational

Specification requirements and demolition of the entire existing building.

Page 11: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

EXISTING FLOOR PLAN

M A I N L E V E L I S A P P R O X . 2 8 , 5 0 0 G S F

3

3

K

K

2 2

1

1

55

4

4

YM

CA

MU

SIC

SP

EC

.E

D.

AR

T

E X I S T I N G C O N D I T I O N S

Page 12: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

SITE AERIAL PHOTO

E X I S T I N G C O N D I T I O N S

Page 13: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1FLOOR PLANS

C O N C E P T F L O O R P L A N

BASE BID

L O W E R L E V E L

U P P E R L E V E L

Page 14: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1FLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

FUTURE EXPANSION

Page 15: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #13D LOWER LEVEL

C O N C E P T F L O O R P L A N

Page 16: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #13D UPPER LEVEL

C O N C E P T F L O O R P L A N

Page 17: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1PHASE 1

C O N C E P T F L O O R P L A N

Page 18: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1PHASE 2

C O N C E P T F L O O R P L A N

Page 19: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1PHASE 3

C O N C E P T F L O O R P L A N

Page 20: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1PHASE 4

C O N C E P T F L O O R P L A N

Page 21: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #1PHASE 5

C O N C E P T F L O O R P L A N

Page 22: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2FLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

BASE BID

Page 23: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2FLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

FUTURE EXPANSION

Page 24: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #23D LOWER LEVEL

C O N C E P T F L O O R P L A N

Page 25: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #23D UPPER LEVEL

C O N C E P T F L O O R P L A N

Page 26: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2PHASE 1

C O N C E P T F L O O R P L A N

Page 27: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2PHASE 2

C O N C E P T F L O O R P L A N

Page 28: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2PHASE 3

C O N C E P T F L O O R P L A N

Page 29: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2PHASE 4

C O N C E P T F L O O R P L A N

Page 30: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

ADDITION / RENOVATION OPTION #2PHASE 5

C O N C E P T F L O O R P L A N

Page 31: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

REPLACEMENT OPTION #3A & 3BFLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

Page 32: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

REPLACEMENT OPTION #3A3D VIEW

C O N C E P T F L O O R P L A N

Page 33: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

REPLACEMENT OPTION #3APHASE 1

C O N C E P T F L O O R P L A N

Page 34: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

REPLACEMENT OPTION #3APHASE 2

C O N C E P T F L O O R P L A N

Page 35: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

REPLACEMENT OPTION #3BPHASE 1

C O N C E P T F L O O R P L A N

Page 36: FCPS Liberty Elementary School Feasibility Study …...2019/01/31  · Liberty Elementary School PAA Project #18‐35 January 31, 2019 Page 2 of 6 a. Construction phasing was proposed

REPLACEMENT OPTION #3BPHASE 2

C O N C E P T F L O O R P L A N