Trimble FastTest iPad v1.2 Page 1
FastTest iPad
Amtech is an Institution of Electrical Engineers (IEE) Endorsed Provider and is registered with the Chartered Institute of Building Services Engineers (CIBSE) as a CPD course provider.
Trimble FastTest iPad v1.2 Page 2
FastTest for iPad ....................................................................................................... 3
First Installation ...................................................................................................................... 3
Login ........................................................................................................................................ 4
Registering your FastTest iPad account ............................................................................................. 4
Toolbar Overview ...................................................................................................... 5
Bottom toolbar ..................................................................................................................................... 5
Top toolbar .......................................................................................................................................... 5
Filter Certificate ................................................................................................................................... 5
Delete certificates ................................................................................................................................ 6
Downloading admin details ................................................................................................................. 6
Download Certificates ......................................................................................................................... 6
Forgotten Password ............................................................................................................................ 6
Training Exercise 1 – Creating a certificate ......................................................................... 6
Add Certificate..................................................................................................................................... 6
Client and certificate type .................................................................................................................... 7
Lock button ......................................................................................................................................... 8
Installation ........................................................................................................................................... 8
Navigation through a certificate ........................................................................................................... 9
Entering certificate data. .....................................................................................................11
Text Boxes ........................................................................................................................................ 11
List Boxes ......................................................................................................................................... 12
Check Boxes ..................................................................................................................................... 12
Details of the Minor Works ................................................................................................................ 12
Details of the Modified Circuit............................................................................................................ 13
Inspection and Testing of the Modified Circuit and Related Parts ..................................................... 13
Details of approved Contractor.......................................................................................................... 14
Declaration ........................................................................................................................................ 14
Managing Completed Certificates.......................................................................... 16
Uploading finished certificates........................................................................................................... 16
Training Exercise 2 – working with downloaded data and boards ...................... 17
Downloaded certificates .................................................................................................................... 17
Observations ..................................................................................................................................... 18
Editing, Creating and Copying Boards .............................................................................................. 18
Re-Naming Boards ............................................................................................................................ 20
Interconnecting Boards ..................................................................................................................... 20
Boards and Circuits .............................................................................................................21
General ............................................................................................................................................. 21
Board Data Input ............................................................................................................................... 21
Creating and Defining Circuits........................................................................................................... 22
Sub Mains ......................................................................................................................................... 25
Flood fill ............................................................................................................................................. 25
Circuit Test Data Input ...................................................................................................................... 26
Trimble FastTest iPad v1.2 Page 3
FastTest for iPad
FastTest for iPad is used to enter Electrical certificate data on site for the production of the actual
certificate in FastTest
There are two types of setup for FastTest for iPad
Single User (single FastTest license)
• 1 User Limit.
• Can transfer existing data in FastTest (certificates or Admin details) to and from a
single FastTest iPad app.
• Can generate certificates on FastTest iPad app for sending to stand alone FastTest
Multi User (single or multiple FastTest Plus/Pro licenses)
• User limit linked to version. (FastTest Plus and Pro 2 user licenses).
• Can transfer existing data in FastTest (certificates or Admin details) to and from
multiple FastTest iPad apps.
• Can transfer data between FastTest iPad app users
• Can generate certificates on FastTest iPad app for sending to networked and
standalone installations of FastTest
First Installation
Once installed on your iPad you can use FastTest for iPad straight away to generate certificates.
To allow you to print or email them you will, however, require a licensed copy of FastTest.
Trimble FastTest iPad v1.2 Page 4
Login
Users will need to log-in to allow the transfer of data from the FastTest iPad to FastTest
All users’ login names and passwords will have been generated via the Amtech cloud website
(cloud.amtech.co.uk) first. (1)
Once entered you can select to remember your login and password (2)
Selecting Login (3) will take you to the FastTest iPad interface.
Registering your FastTest iPad account
The first time you successfully login your device will be automatically be registered to your cloud account.
Trimble FastTest iPad v1.2 Page 5
Toolbar Overview
Bottom toolbar
The bottom toolbar contains the tools to login and out of FastTest iPad app and
open and edit Existing Certificates and to create New Certificates.
Bottom Toolbar Buttons
Log in and out of FastTest iPad
View Existing Certificate list.
Edit existing Certificates
Create New Certificates.
View Help dialog
Top toolbar
The Top toolbar allows you to administer and view existing certificates and to
download data from the Amtech Cloud
Top Toolbar
Filter Certificate
Once multiple certificates have been entered you can use this to filter by Date, Client, Installation or Status
Trimble FastTest iPad v1.2 Page 6
Delete certificates
By selecting this option any certificate in your list can be selected and then deleted
Downloading admin details
If you wish to start a certificate from scratch on site but do not wish to duplicate existing data on the master
database admin details such as Client name, Installation name and Company name and Engineer details can be
sent to the FastTest iPad app so that when generating a certificate the data is already present.
Download Certificates
See section Downloaded certificates below
Forgotten Password
On the login page you can request a forgotten password which will be emailed to you.
Training Exercise 1 – Creating a certificate
Add Certificate
Select the Add Certificate button from Display.
Trimble FastTest iPad v1.2 Page 7
Client and certificate type
As we do not have an imported client we need to make one.
Select the Plus (+) symbol for Client and enter the detail
Select the Plus (+) symbol for Client and enter the details. Anything marked with an asterisk is a
required field
Once entered hit save
Use the certificate selector arrow (1) and select a Minor Works (2) then hit Select (3)
Use the same principle to select the format AMTECH.
Trimble FastTest iPad v1.2 Page 8
Now enter a Job Number (whatever you like) and select the 100% Zs value and tap “Create”
Lock button
If you wish to lock the section to prevent accidental data deletion or entry you can tap the Lock button.
Once selected the section will be locked and un-editable until the lock is removed with a tap.
If you need to alter the Client address details select the “Edit” Icon
Installation
As we do not have an installation we need to make one.
Select the Plus (+) symbol for Installation and enter the details
Trimble FastTest iPad v1.2 Page 9
Select the Plus (+) symbol for Installation and enter the details
Once entered hit save
If you need to alter the Installation address details select the “Edit” Icon
You now have all you need to enter the data into the certificate and transfer the data to FastTest or
another iPad user.
Navigation through a certificate
The sections drop down will also indicate the status of each section of the certificate
Green – Completed
Orange – partially completed
Blue – not started
Trimble FastTest iPad v1.2 Page 10
You can navigate through the certificate by swiping the screen or tapping Back/Next or by using the
Sections dropdown
Trimble FastTest iPad v1.2 Page 11
Entering certificate data.
You should now fill in the details, working methodically from the start, taking note of the points described
below.
Text Boxes
Text boxes are plain white boxes into which alphanumeric text can be typed. The amount of text a box
contains is related to the amount of text that can be fitted into the box on the finished certificate.
On selecting a Text Box the iPad keyboard should appear
Using the Back/Next Keys
The best way to navigate from one data entry box to the next is to use the Next key on your keyboard.
After entering data in a box, pressing the Next key will send the cursor to the next text entry or dropdown
box in sequence.
You can also use Back to move back to a previous data entry box.
Trimble FastTest iPad v1.2 Page 12
List Boxes
List boxes are similar to text boxes with the addition of an arrow button on the right hand side. Clicking on
the arrow displays the contents of the list box.
Use the up and down swipe action to scroll through the lists. In most cases it is possible to type in your
own entry if the selection required is not present among the items listed.
By double tapping on an item from the list, or tapping select, it is then entered in that box.
Check Boxes
Generally, Check Boxes have two states, ‘Selected’ or ‘Not Selected’. Tapping in the box changes the
previous state. When the box is empty the item associated with it is not selected. When the box contains
a tick or a cross it is selected.
Details of the Minor Works
If you need to change the date you can swipe the Day/Month/Year sections respectively.
Trimble FastTest iPad v1.2 Page 13
Details of the Modified Circuit
List boxes are provided for most of the data required for the circuit protective device, residual current
device and wiring system. These List Boxes contain most of the standard selections, for example, for
Method of Protection against Direct Contact all the standard methods (ADS etc.) are listed. In the
unlikely event that you require a method not listed, you can simply type it in.
Inspection and Testing of the Modified Circuit and Related Parts
The List Boxes in this section can be used to avoid having to repeatedly type ‘N/A’ for test results that are
not applicable.
Trimble FastTest iPad v1.2 Page 14
Details of approved Contractor
By selecting the cross on the right you can enter the Contractor details
If you need to alter the Trading title address details select the “Edit” Icon
Declaration
Trimble FastTest iPad v1.2 Page 15
You can add engineers by selecting the plus (+) to the right of the name selections
If you need to alter the engineer address details select the “Edit” Icon
The next right to left swipe will take you back to the beginning of the certificate.
You can check that all areas have been completed by checking the Sections drop down shows all green
Trimble FastTest iPad v1.2 Page 16
Managing Completed Certificates
Uploading finished certificates
When certificates are completed the will be available on the Home screen in list format
From here you can reopen the certificate by tapping on its row (1)
Check the current completeness status (2)
Upload to the cloud (3)
Once you are happy for the certificate to be returned to FastTest for review/completion/printing etc. select the
Upload button.
Confirm you wish to upload
Once completed this message should appear
Back on the home page the upload section should now show a tick
Trimble FastTest iPad v1.2 Page 17
Training Exercise 2 – working with downloaded data and boards
Downloaded certificates
As your FastTest iPad app is logged in via your email address when a certificate(s) has been uploaded to you should
receive an email informing you of such.
You can also click the “Download Certificate” button to see if any are available.
If there are new certificates you will receive a FastTest popup confirming it
Click ok and you will now see the new certificate in your list.
Tap the certificate Client to open it.
Once open navigation and data entry are the same as previously covered.
Trimble FastTest iPad v1.2 Page 18
Observations
Most areas have been covered but, here is a brief explanation of the Observations section on the
Electrical Installation condition Report.
Select the following observations …(1) to allow data entry (2) and the addition/deletion (3/4).
The Code is selected from a dropdown (5) you can also tick further investigation (6).
The code count (7) is automatically updated.
Editing, Creating and Copying Boards
If an Electrical Installation Certificate or an Electrical Installation Condition Report is created for an
installation for which neither of these certificate types has been produced before, FastTest will create an
empty board as a starting point for the installation. The number of ways for the board can be changed
and also further boards can be added, as required.
On the certificate, a dropdown option will be shown, with the option to select an existing board (1) add a
board (2) Delete a board (3) Copy a board (4) or insert a board (5)
Trimble FastTest iPad v1.2 Page 19
The first board will be labelled DB1, with sub headers Circuit Details, Test Results and Schedule. New
boards are automatically allocated the name DB (n+1) where ‘n’ is the total number of boards including
any hidden boards. The Circuit Details, Test Results can be displayed, by clicking on the appropriate tab.
When board details are displayed, the Boards panel is shown in the Certificate Viewer header. This
contains the following controls:
Main Board
Checking this item sets the currently selected board as the Main Board, i.e., a board connected directly to
the supply. Any number of boards in an installation can be nominated as the Main Board.
Looped Supply
Checking this item allows a number of boards to be connected to the same sub-main cable.
No. of Ways
Set the number of ways for the board.
Phases
For single phase boards, the appropriate phase can be selected. For a wholly single-phase installation and
where the phasing is not known, Single, S can be selected (this option MUST not be selected for a single-
phase board in three phase installation; instead the correct phase L1, L2 or L3 should be selected).
Add
Click on Add to create a new board. The new board will have the same phase and number of ways as the
currently selected board and be added to the end of the existing boards.
Trimble FastTest iPad v1.2 Page 20
Copy
Adds a new board. The new board is identical to the current board, including circuit details. The board will be placed
at the end of the existing boards.
Delete
Deletes the current board from the current installation.
Insert
Inserts a new board immediately to the right hand side of the current board. The new board has the same
number of ways and phasing as the current board.
Re-Naming Boards
Boards can be renamed via the ‘Distribution Board Designation’ field, just tap in the field and rename the
board. This will automatically update the board dropdown.
Interconnecting Boards
For installations with multiple boards connected to a common supply, to ensure that interconnections
between boards are correctly defined, proceed as follows:
Multiple Boards connected to the Origin
Where more than one board is connected directly to the supply, each of the directly connected boards
should be defined as a Main Board, i.e., the Check Box ‘Main Board’ in the ‘Boards’ data
(displayed in the header in the Certificate Viewer) is checked.
Sub Boards connected via Sub Mains
This is a two stage process:
1. Define a suitable circuit as a Sub Main in the Circuit Details for the board feeding the Sub Board it is not
necessary to define the destination board at this stage.
2. Create the Sub Board. In the Board Details, select the previously defined Sub Main in the Supply to
Distribution Board is from list box. The two boards should now be correctly interconnected. The
Overcurrent Protective Device’ data should now be filled with the data previously entered for the Sub
Main. Also, the Sub Main Circuit designation will now contain the name of the destination board (Sub
Board).
Trimble FastTest iPad v1.2 Page 21
Looped board connections
Where a number of boards are connected to a single Sub Main, this can be defined using the Looped
Supply check box in the Boards data. First define the Sub Main interconnection as described above, then
for all the other boards connected to the Sub Main, check the Looped Supply check box. The Board data
for each of the boards will now correspond to the details for the Sub Main circuit.
Boards and Circuits
General
Details of the Boards and Circuits for an installation are defined in FastTest iPad app when creating the
first Electrical Installation Certificate or Electrical Installation Condition Report for that installation. The
procedures for inputting data for the main body of the certificate are described in the sections below.
The procedures for entering board and circuit details are described in this section and are the same
whether an Electrical Installation Certificate or Electrical Installation Condition Report is being produced.
Board Data Input
For each board, the Board data is entered in the fields located at the top of the Board Tab.
For every board the Location and Designation should be entered.
Trimble FastTest iPad v1.2 Page 22
For boards connected to the Origin of the Installation no other data is required. For all other boards, it is
necessary to define where the Supply to Distribution Board is From, Nominal Voltage, Overcurrent
Protective Device details and Residual Current Device details, where installed.
NOTE: The entry for Supply to Distribution Board is from can be selected only after a suitable Sub Main
circuit has been defined in another board; it cannot be typed in. When the Sub Main circuit has been
selected, the overcurrent protective device details for that Sub Main are automatically inserted in the
relevant fields. The data inputs for Residual Current Device, Operating Current, Type and No. of Poles,
will need to be completed. See Interconnecting Boards below, for details on how to create Sub Main
circuits to supply Sub Boards.
Creating and Defining Circuits
The number of ways and phases in a board are set in the Boards panel displayed in the Certificate Viewer
header (see Creating Boards above).
Where a board contains a large number of ways, swiping up and down allows the user to move up and
down the list of circuits.
To reduce the amount of typing required when entering circuit details, wherever possible List Boxes are
provided from which the necessary inputs can be selected. Inputs that have to be typed in are: Number of
Trimble FastTest iPad v1.2 Page 23
points served, Overcurrent Protective Device Short-Circuit Capacity (entered automatically for standard
types) and Max. Zs (entered automatically for standard types). Where the required input does not exist in
the relevant List Box, click in the box and type in the desired text.
Defining Circuit Number and Phase
For a single phase board the phasing is fixed with one single phase circuit per way. For three phase
boards, each way is initially set as one three phase circuit (labelled x/TP, where x is the number of the
way). Alternatively, each way can be defined as three single phase circuits (x/L1, x/L2, x/L3, where x is the
number of the way).
Circuit Number and Phase
This is contained in a List Box. To change a way from a single three phase circuit to three single phase
circuits, click in the box and select a single phase circuit. The way will now be split into three single phase
circuits.
Circuit designation,
Initially, all circuits are set to “SPARE”. Where a circuit is to be defined, tap in the box and type in the
circuit designation.
When typing data into a circuit designation a new option appears on the iPad keyboard
This allows you to see and edit the full extent of this field.
Where a way is physically not available for connection within a board, select one of the following items
from the List Box as appropriate: Way Not Available, RCD Module (Split Board), RCD Module Covering. For
circuits with these designations, no further details can be entered.
Where a circuit exists within the installation, but is not to be included in the scope of the certificate (i.e.,
not tested), the designation” Circuit Not Tested” should be selected.
Trimble FastTest iPad v1.2 Page 24
Note: The designation “Circuit Not Tested” applies only to the current certificate. For example, an
Electrical Installation Certificate is produced for an installation, including a circuit designated “Lighting 1st
Floor”. Subsequently an Electrical Installation Condition Report is compiled but the “Lighting 1st Floor”
circuit is not tested and therefore is designated “Circuit Not Tested”. This does not change the underlying
designation for that circuit within the installation, so that, when later, another Electrical Installation
Condition Report is carried out and the circuit is tested, its original designation “Lighting 1st Floor” is
shown for that circuit.
Trimble FastTest iPad v1.2 Page 25
Sub Mains
Where a circuit is a Sub Main connecting another board in the installation, select the designation Sub
Mains and fill in the circuit details. The destination board is then defined, not in the circuit details, but in
the Board Details for the destination board. See Interconnecting Boards below.
Flood fill
Details can easily be copied up or down a whole set of fields using the column fill feature. Tapping Fill up
or Fill down on an occupied field will copy that data down the relevant column into all empty cells. This
applies to only to Circuit Details.
The Board Test Data dialog can be accessed by tapping on the Test Results tab on the right
The Zs, Ipf and RCD operating times need not be filled in where the board in question is directly
connected to the source of supply.
Trimble FastTest iPad v1.2 Page 26
Test Instruments serial numbers can be typed in where a serial number has not been previously noted.
Circuit Test Data Input
Circuit Test Data appears below the panel containing the Board Test Data and is listed in the same order
as the corresponding circuits.