FASER LS2 works coordina3on: 3rd Mee3ng
Jamie Boyd 6/6/2019
1
Progress on a few unrelated areas reported (relevant for different WPs) Backup with more general slides (mostly from previous mee3ngs)
Op#cal Fiber installa#on for FASER experiment Discussed with Johannes Troller (EN-‐EL-‐FC) 21.5.19. • It seems it should be fairly simple to make a deriva3on of a microduct passing TI12 to bring 12 or 24 fibers from US15 (downstairs in p1) to TI12
• Not a big cost difference for 12 or 24 fibers • Can then be patched to exis3ng fibers that go from US15 to SR1
• It maybe that a fiber carrying clock/orbit signals could be patched in already in US15 (depending on the choice of source for these signals).
• Rack we want the fibers to go to in SR1 is 4Y.02-‐10=SR1, need to define the details of the rack loca3on in TI12 (also which connec3on we need there) • In case the deriva3on of the microduct is infeasible, the installa3on of a new duct with microducts plus fibre cable is required from US15 to TI12 • Or, as a backup if the above is problema3c could also try to use BI infrastructure to get fibers to TI12, but not preferred solu3on. • Work would be planned to be done by May 2020
• By that 3me the rack in TI12 and cable trays would need to be installed (will require some coordina3on at the 3me)
• Johannes will look into detail at available fibers, channels and come back with a detailed plan, including a cost es3mate • Liam to look into integra3on details (route of cable trays / telex in UJ12/TI12, final loca3on of FASER racks in TI12) once more informa3on from Johannes is available (by August) • Followed in 3cket: RQF1152082
Grounding / Earthing • Yann Maurer (EN-‐EL-‐EIC) can make a connec3on to the LHC earthing cable and connect this to FASER infrastructure: – Detector baseplane – Electronics rack housing
3
Picture from Liam, showing suggested (simplified) earthing cable rou3ng
Civil Engineering Strengthening Frames • Discussed with Pierre Thonet if it could be problema3c for the magne3c field if we have a steel frame that is not ‘under’ the magnet but also level with it:
4
• It seems this will not be problema3c • Going ahead with steel strengthening frames is therefore no problem!
Cooling • Have asked EN-‐CV if they can take responsibility for configuring and M&O for the FASER chiller – Informal discussion with Olivier quite posi3ve, awai3ng from from Roberto and Mauro
• Olivier will run a fluidic simula3on of the cooling in TI12, based on the following conserva3ve simplified model of heat dissipa3on:
5
Backup…
6
Proposed Workpackages 1. Prepara3on (F. Sanchez Galan (EA), L. Dougherty* (ACE))
– Lowering cable trays in UJ12 – Removing obsolete ven3la3on ducts in UJ12/TI12 – Removing GSM cable, installing GSM antenna – Installa3on of handling equipment Work to be completed in 2019
2. Civil Engineering (J. Gall (SMB)) Work to be completed during iden3fied 6 week (+4 weeks out of working hours) slot in Jan/Feb/March 2020
3. Installa3on (J. Boyd (EP), M. Bernardini (ACE)) – Transport of detector components – Installa3on of power – Installa3on of compressed air – Installa3on of op3cal fibers Work to be completed before cool down of sector 81 (early June 2020)
4. Detector Commissioning (J. Boyd (EP)) Work to be completed before end of LS2
ECRs to be wrinen for WP1, 2, 3 to outline technical details of needed work. WP1 ECR to be released soon.
7 * -‐ L. Dougherty would be worksite supervisor
Reminder!
Coordina3on • Propose bi-‐weekly coordina3on mee3ngs
– Chaired by J. Boyd (EP, Project Leader) (B. Petersen (deputy)) – Include:
• Work-‐package coordinators • F. Sanchez-‐Galan, L. Dougherty • J. Gall • LHC coordina3on: M. Bernardini • LHC Safety coordinators: J. Etheridge, S. Grillot • When necessary contacts for different teams:
– EL-‐EIC – Y. Maurer – EL-‐FC – Gael Girardot – EA – M. Papamichali – CV – O. Crespo-‐Lopez – HE – C. Bertone – SMB – E. Perez-‐Duenas – HSE – M. Andreini (FASER safety contact) – RP – C. Adorisio
• Mee3ng slot 14-‐15h Thursdays (every-‐other-‐week) – Next slot is a CERN holiday, so propose next mee3ng in 3 weeks (June 6th)
• Indico category for our mee3ngs: hnps://indico.cern.ch/category/11281/
8
e-‐group • I have setup an e-‐group for FASER LS2 work coordina3on: – faser-‐ls2-‐works-‐[email protected]
9 Updated since last mee3ng…
FASER EDMS • FASER EDMS node has been setup: – hnps://edms.cern.ch/ui/#!master/navigator/project?P:100368375:100368375:subDocs
10
Reminder Safety
• Launch Safety Agreement (LSA) released by Marco Andreini (FASER HSE contact) – EDMS link from AOB – Long list of safety documenta3on needed, please make sure relevant documenta3on is produced
• Expect relevant teams to produce safety documenta3on for their works – If you have ques3ons please check with HSE (keep me in the loop)
11
Cost so far…
• Overview of the costs incurred so far:
12
Work Cost kCHF
Lowering cable trays 3.4
Passerelle 9.1
Hoist for UJ12 27.1
Moving lights in UJ12 0.8
Moving cables/electronic equipment
1.5
SAS ?
Total 42.8