    Pharping Hydro-Power Station

    Introduction

    Pharping hydropower station is the first power station of Nepaland second hydropower station of Asia.

    It is the oldest power project of Nepal. It was established in 1968 B.S by then Prime Minister Chandra

    Shamsher Rana.

    It is located in the Kathmandu district about 20km away from theheart of Kathmandu.

  • 8/13/2019 Far Ping

    2/10

  • 8/13/2019 Far Ping

    3/10

    CONSTRUCTION DETAILS

    1. Reservoir Weir

    The water has been tapped from the Satmule by laying 44 f steelpipelines and from Sesh Narayan by laying somewhere 10f and

    somewhere 9f steel pipelines to the reservoir.

    The reservoir is 200 diameter and 18 deeps reservoir with acapacity of 528,783cu.ft.

    This reservoir has been made with the help of bricks and cement.

  • 8/13/2019 Far Ping

    4/10

    2. Penstock pine

    Penstock pipe from the reservoir, riveted steel pipes of 20diameter as penstock pipe up to the power house.

    This penstock pipe is 2538 long and inclined 678 was made. In the middle portion of pipe, there is a valve for the maintenance

    and to clear the obstruction.

    Water from reservoir to the power house through penstock pipe inorder to run the pelton wheel turbines.

  • 8/13/2019 Far Ping

    5/10

  • 8/13/2019 Far Ping

    6/10

    4. Transmission Lines

    An over head transmission line of 6 miles was constructed. This line was brought to distribution substation at Tundhikhel from

    power station using some where steel poles and some where

    wooden poles.

    There are two major crossings of 600ft and 900ft on Bagmati Riverin the transmission line.

  • 8/13/2019 Far Ping

    7/10

    5. Distribution Sub-Station

    Initial voltage is made to reduce to 2300v by using switchtransformer.

    And other more required equipment was used for reliabledistribution.

    It was distributed to palace and streets around the city.

  • 8/13/2019 Far Ping

    8/10

    Technical, Socio-culture, Economic and Political condition of

    Pharping hydro-power station.

    1.Socio-culture Impacts: Communities around this Pharping hydropower station are not of

    same caste, culture and religious.

    Brahman, Chhetri thinks that they are the senior one and they areonly the responsible for care taking the station although Newari

    population is more.

    Different cultures are celebrated in the community on the base ofcaste, so no involvement of unity for development work in the

    concept of religious view.

    Hence, we can say that society culture may affect the developmentwork unless and until they get awareness about the cultural and

    religious importance.

  • 8/13/2019 Far Ping

    9/10

    2.Economic Impacts: Maximum people living around this power station depend on

    agriculture.

    So community income source is in agriculture. Some people are land lord and some are land less and people who

    have no land obviously are poor then they cannot show as well as

    participant in attitude that of land lord people, hence their voice is

    in behind.

    Due to unequal economic source people living in this community,they have conflict.

    This is also one of the main reasons; that they dont have unity inthe development work.

    Else if this hydropower station produces electricity, people livingin this region get easily job so, that reduces the way of youth

    jobless situation.

    Production of electricity creates environment of factory, mills andindustries within the community resulting the no economic crisis

    and works are easily solved; less manpower and less time.

    Hence community lifestyle will be high as they have their ownschools, hospitals and communication centers within the

    community.

  • 8/13/2019 Far Ping

    10/10

    3.Political Impacts: According to the people of that region, those are elected as leader

    will give no care in future after the election.

    Elected leader didnt visit that region after the completion ofelection, forgot the patriotism.

    We realize that leader should be of that region himself or herselfwho knows the problem about communities as well as required

    essential materials for that region for further promotion itself. We have seen, if the elected political leader had done the hard

    decision about this hydro power station, this power station may not

    close at this instant.