Upload
dodat
View
240
Download
5
Embed Size (px)
Citation preview
©2017 Doble Engineering Company. All Rights Reserved.
USING LABORATORY AND ON‐LINE DGA MONITORING TO KEEP A GSU OPERATIONAL DURING A CRITICAL SERVICE PERIOD
Pam Bahr and Jon Christensen
Intermountain Power Service Corporation
Paul Griffin and Lance Lewand
Doble Engineering Company
©2017 Doble Engineering Company. All Rights Reserved.
Confidential Notice
Doble Engineering (Doble) hereby grants the recipient (you) the right to retain thispresentation and materials included within (the Presentation) for private reference. Noother rights, title, or interest, including, but not limited to, the rights to copy, make use of,distribute, transmit, display or perform in public (or to third parties), edit, translate, orreformat any portion of the Presentation are hereby or otherwise granted and shallremain expressly reserved by Doble. You acknowledge and agree that such limitedlicense is expressly conditioned upon your acceptance of the terms herein. You furtheragree that, in the event of your breach, Doble will suffer irreparable damage and injuryfor which there is no adequate remedy at law. As such, Doble, in addition to any otherrights and remedies available, shall be entitled to seek injunction by a tribunal ofcompetent jurisdiction restricting you from committing or continuing any breach of theseterms.
©2017 Doble Engineering Company. All Rights Reserved. 3
OwnerIntermountain Power Agency
Operating AgentLADWP
OperatorIntermountain Power Service Corp.
• Construction began 1982
• Unit 1 Commercial Operation 1986
• Unit 2 Commercial Operation 1987
Intermountain Power Project
©2017 Doble Engineering Company. All Rights Reserved. 4
• Intermountain Generating Station
(two 950 MW units)
• 345 kV AC Switchyard
• 500 kV DC Converter Station
• Transmission Systems
(AC & DC)
Intermountain Power Project
©2017 Doble Engineering Company. All Rights Reserved. 5
Intermountain Power Project Transmission
©2017 Doble Engineering Company. All Rights Reserved.
General Electric Transformer
6
• Vintage 1982
• Voltage class 345 – 26 kV
• Power class 865/969 MVA
• Application: Generator Step‐up transformer
• 55/65°C rise rating
• Forced oil Forced air cooling (OFAF)
©2017 Doble Engineering Company. All Rights Reserved.
• Document strategy for leaving transformer with load sensitive problem in service
• Case involving more than 1 fault type
• Use on‐line DGA monitoring to manage the problem
• Laboratory testing confirmed on‐line DGA results
• Transformer in otherwise good condition – reasonably dry, paper aging at a low to normal rate
• Acoustic monitoring used for fault confirmation and location
Case Study
7
©2017 Doble Engineering Company. All Rights Reserved.
• Bare metal or paper‐wrapped conductor fault
– Generation rate of carbon oxide gases
– Ratio of carbon oxide gases
– Amount and rate of generation of 2‐furfural
– Ethylene/ethane ratio
Possible Sources of Gassing Behavior
8
©2017 Doble Engineering Company. All Rights Reserved.
• Normal for many years
• Excessive gassing associated with Shields 2013
• Second Event – 2014
– Shields again?
– Something new?
• Generation rate TCG increasing
Total Combustible Gas (TCG) Generation
9
©2017 Doble Engineering Company. All Rights Reserved.
• Two connections per shield
• Connections loose
• Carbonized oil between bolts and washers
• Replaced with larger washers
• Tightened loose bolts
First Problem with Shields Stating in 2012
10
60 flexible copper straps, 2 bolted connections each – approximately 30% loose
©2017 Doble Engineering Company. All Rights Reserved.
Overheating and pitting of plate resulting from poor connection
Second Problem: Lower Connection Plate of Shield
11
©2017 Doble Engineering Company. All Rights Reserved.
• Stable for long period of time
• Two issues developed
Generation of Combustible Gases
12
©2017 Doble Engineering Company. All Rights Reserved.
• Initial shield issue in 2012 and again in 2013
• Corrective actions take
• Issue again in 2014
• Gassing patterns similar
13
©2017 Doble Engineering Company. All Rights Reserved.
• Methane, Ethane, and Ethylene
• Ethylene/ethane ratio <4:1
• Typical paper wrapped conductor fault
• Typical of unintentional core ground
Generation of Hydrocarbon Gases
14
©2017 Doble Engineering Company. All Rights Reserved.
• Generation rate of total combustible gases >100 ppm/day
• Rate of increase in total combustible gas was increasing suggesting rapid deterioration of condition
• Issue could be with the magnetic circuit
• Issue could be paper wrapped conductor fault
• Unlikely to make it to planned outage
• Determine if the problem was load dependent by reducing load and using generation rate of gases as indicator
Excessive Rate of Gas Generation
15
©2017 Doble Engineering Company. All Rights Reserved.
Generation Rate Load Dependent
16
Reduced Load
©2017 Doble Engineering Company. All Rights Reserved.
• Gassing rate reduced to reasonable level
• None of the individual combustible gases started increasing significantly
• No acetylene detected
• Acoustic monitoring did not detect significant problem
Leave in Service
17
©2017 Doble Engineering Company. All Rights Reserved.
• Indicated fault might be on the LV side near the bottom
• Recommendation to check the low voltage side for the following possible problems: – Tank wall shields
– LV leads and bus connections
– Neutral leads and connections
– Bottom end frame shields (if present)
• Problem was found on the LV side but closer to the top
Acoustic Location
18
©2017 Doble Engineering Company. All Rights Reserved.
• Normal ratio CO2/CO
• Normal amounts Carbon oxides
• Generation rate increase during fault conditions
Carbon Oxide Gases
19
©2017 Doble Engineering Company. All Rights Reserved.
Second Problem Low Voltage Lead Crimp Connection
20
©2017 Doble Engineering Company. All Rights Reserved.
• Managed to remain in service as long as possible
• Not many strands left
Just in Time
21
©2017 Doble Engineering Company. All Rights Reserved.
Repaired: New Bolted Connection, New Insulation
22
©2017 Doble Engineering Company. All Rights Reserved.
• Solid insulation holds about 1/3 of its weight in oil
• Gases retained in oil in solid insulation takes about 3 months to equilibrate with bulk oil
• After 3 months stable gassing
• Repairs corrective
Continued DGA Post Repair
23
©2017 Doble Engineering Company. All Rights Reserved.
• Large oil volume transformer, sealed conservator
• Gases permeate membrane slowly
• Dissolved gases in oil will tend to change in step‐wise increase or very slow decreases
• Oxygen can vary more due to amount in air
Variation in DGA Results from Monitor
24
0
10
20
30
40
50
60
70
80
0
200
400
600
800
1000
1200
1400
1600
H2
O2
CH4
CO2
C2H4
TDCG
THC
Top Oil
©2017 Doble Engineering Company. All Rights Reserved.
Complete History of DGA Results
25
©2017 Doble Engineering Company. All Rights Reserved.
• Possible to manage load related faults for window of time
• More than one fault can take place at the same time
– Examine the relative composition of gases
– Examine ethylene/ethane ratio to evaluate if paper‐wrapped conductor fault
– Determine the rate of total combustible gas generation and examine slow of gassing curve for accelerated gassing profile
• It would appear that some of the gassing associated with the shield problem might have been from the low voltage lead crimp area
• It is possible that the 3rd problem was created in repairing the 2nd
• DGA accurate in indicating urgent response needed
Conclusions
26
©2017 Doble Engineering Company. All Rights Reserved.
• On‐line DGA monitoring used to manage retaining transformer in service for small window of time
• Allowed for field repair before destructive failure that might have required transformer replacement
• DGA results shows problem has been corrected
Conclusions
27