Failure mode impact studiesand
LV system commissioning tests
Technical review on UPS power distribution of the LHC Beam Dumping System
N.Magnin - 20.06.2012
2
Outline
• LBDS components - Powering summary• LBDS diagnosis systems• Expected power failure impact• Commissioning tests• How to perform commissioning ?• When to perform commissioning ?
20.06.2012
3
LBDS componentsPowering summary (1)
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
(Suggested powering after LS1)
4
LBDS componentsPowering summary (2)
1. EN/EL circuit-breaker.
2. 4x LBDS UPS-A circuit-breaker.
3. LBDS MAIN circuit-breaker.
4. LBDS UPS-B circuit-breaker.
20.06.2012
EN /EL
U PS-BU PS-A
LBD SM AIN
LBD SU PS-B
LBD SU PS-A
1
LBD S CO M PO N EN TS
432
5
LBDS diagnosis systems (1)
SCSS (WinCC):– Checks all redundant signals for presence
(Triggers and Re-triggers).– Surveillance of Main and UPS power presence.
20.06.2012
6
LBDS diagnosis systems (2)
TSU - FESA:Checks the status of internal TSU registers.(Detected clients,BRF presence,PLL locked, etc…)
20.06.2012
7
LBDS diagnosis systems (3)
IPOC - TSU:Checks signals at input and output of TSU for presence and correct synchronisation.
20.06.2012
8
LBDS diagnosis systems (4)
IPOC - MKD:Checks MKD current waveforms for correct strength and synchronisation.
Synchronous trigger
Asynchronous trigger(Switch erratic)
20.06.2012
9
LBDS diagnosis systems (5)
XPOC:• BTVDD: Shows beam position on TDE.• BLMs: Show beam losses during extraction.• BPMD: Shows beam position in extraction line.
20.06.2012
10
Expected power failure impact1 - Main failure
• Expected scenario:1) LBDS MASTER PLC detects MAIN failure.2) LBDS MASTER PLC issues an internal
dump request to TSU cards.3) Synchronous dump executed before MKD
generator voltages reach their tracking limits (BETS/SCSS).
•Expected result: Synchronous dump•Missing diagnosis systems :
- NONE!
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: OK
11
Expected power failure impact2 - UPS-A failure (a)
• Expected scenario a):1) LBDS MASTER PLC powers off.2) Safety link to TSU is broken
= TSU internal dump request.3) Synchronous dump executed before
MKD PTU and generator voltages reach their tracking limits.
•Expected result: Synchronous dump•Missing diagnosis systems :
- IPOC1-MKD- TSU-A registers- SCSS (WinCC)
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: OK
12
Expected power failure impact2 - UPS-A failure (b)
•Expected scenario b):1) TSU-A powers off.2) TSU-B detects TSU-A problem
= TSU-B internal dump request.3) Synchronous dump executed before
MKD PTU and generator voltages reach their tracking limits.
•Expected result: Synchronous dump•Missing diagnosis systems :
- IPOC1-MKD- TSU-B registers- SCSS (WinCC)
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: OK
13
Expected power failure impact2 - UPS-A failure (c)
• Expected scenario c):1) TSU-A detects power failure
= TSU-A internal dump request.2) Synchronous dump executed before
MKD PTU and generator voltages reach their tracking limits.
•Expected result: Synchronous dump•Missing diagnosis systems :
- IPOC1-MKD.- TSU-A internal statuses.- SCSS (WinCC)
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: OK
14
Expected power failure impact3 - UPS-B failure
• Expected scenario:1) TSU-B detects power failure
= TSU-B internal dump request.2) Synchronous dump executed.
•Expected result: Synchronous dump
•Missing diagnosis systems :- IPOC2-MKD.- TSU-B internal statuses.
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: OK
15
Expected power failure impact4 - TOTAL failure
•E xpected scenario:1) TSU-A/B detects power failure
= TSU internal dump request.2) Synchronous dump executed before
MKD PTU and generator voltages reach their tracking limits.
•Expected result: Synchronous dump
•Missing diagnosis systems :- ALL ! (But XPOC in REMOTE with BEAM)
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTB-A X LBDS operationRTB-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: BAD !
16
Expected power failure impact5 - Shortcut in TSU crate (+12V)
• Expected scenario:1) TSU-A/B detects power failure
= TSU internal dump request.2) Synchronous dump executed.
•Expected result: Synchronous dump
•Missing diagnosis systems :- NONE
20.06.2012
Systems MAIN UPS-A UPS-B Function15 MKD HV PS X LBDS operation15 MKD PLC X LBDS operation15 MKD PTU X LBDS operationLBDS MASTER PLC X LBDS operationTFO-A X LBDS operationTFO-B X LBDS operationRTU-A X LBDS operationRTU-B X LBDS operationTSU-A FEC X LBDS operationTSU-B FEC X LBDS operationTSI FEC X X LBDS operationBETS FEC X X LBDS operation
IPOC - TSU FEC X X LBDS diagnosisIPOC1 - MKD FEC X LBDS diagnosisIPOC2 - MKD FEC X LBDS diagnosis
Assessment of correct LBDS behaviour: OK
17
Commissioning tests Tests already performed - Main failure
Tests performed locally at Point 6 in 2006.
LBDS-MAIN circuit-breaker has been opened manually.
Resulted in a synchronous dump.
20.06.2012
EN/EL
UPS
LBDSMAIN
LBDSUPS-A
LBDS COMPONENTS
18
Commissioning testsTests already performed – UPS failure
Tests performed locally at Point 6 in 2006.
Four LBDS UPS circuit-breakers have been opened manually ‘at the same time’.
Resulted in a synchronous dump.
Is it representative of a real UPS failure ?
20.06.2012
EN/EL
UPS
LBDSMAIN
LBDSUPS-A
LBDS COMPONENTS
19
Commissioning testsTests foreseen for end of LS1
• MAIN failure:– Already done in 2006.
• UPS-A failure:– Already done in 2006 (manually = not real UPS failure ?).
• UPS-B failure:– Never done so far !
• UPS-A + UPS-B failure– Never done so far !
• TOTAL failure (Main + UPS-A + UPS-B)– Never done so far !
20.06.2012
20
How to perform the commissioning LOCAL or REMOTE ?
20.06.2012
CONS:•We need to arm LBDS:- Close BIS loops.- Close LASS.- Arm BETS (connect BETS-Simulator).•Test with beam is not possible !•Cannot be done on regular basis.•...
PROS:• Tests performed from 450 GeV to7 TeV.• Team on site in case of LBDS problem.• ...
LOCAL commissioning at Point 6: REMOTE commissioning from CCC:
PROS:• Test with pilot beam at 450 GeV is
possible.• Check LBDS with external diagnosis
systems (XPOC).• Arming of LBDS is easy.• Could be done on a regular basis.• ...
CONS:• How to cut/re-establish power
remotely ?• Tests at 7 TeV not possible.• Access needed in case of LBDS
problem.• ...
21
How to perform the commissioningProvoke TOTAL power failure ?
1. By-Pass mode for both UPS.
2. Opening of EN/EL Circuit-Breaker.
Impact of total power loss on other LHC equipment ?(Cryogenics, QPS, Vacuum, BIS, …)
20.06.2012
EN/EL
UPS-BUPS-A
LBDSMAIN
LBDSUPS-B
LBDSUPS-A
1 1
2
LBDS COMPONENTS
Is this possible in REMOTE mode ?
22
How to perform the commissioning Assess correct LBDS behaviour
• We need the most important diagnosis FECs:
– IPOC - TSU:• Check for correct TSU card behaviour.• Check LBDS synchronisation with beam.
– IPOC - MKD:• Check for correct MKD strength.• Check for correct MKD synchronisation wrt each other.
Þ We need power for at least these two important diagnosis FECs.Þ We need power for the network infrastructure.
20.06.2012
Do we need a special power feed for diagnosis FECs & IT equipment ?(At least in case TOTAL failure test is feasible)
23
How to perform the commissioningEN/EL modifications needed ?
- Insert new circuit-breakers ?(Temporarily / Definitively ) ?
- Remote control of circuit-breakers ?
- Powering of diagnosis FECs from upstream of new circuit-breakers ?
- …
20.06.2012
EN /EL
U PS-BU PS-A
LBD SM AIN
LBD SU PS-B
LBD SU PS-A
LBD S CO M PO N EN TS
24
When to perform the commissioning
• Must be done at the end of LS1 !– We will have all LOCAL conditions to arm LBDS.– Test procedure to be defined...
• Should we do it on a regular basis ?– Should we do it at the end of every WS ??
- LOCAL ? / REMOTE ?
– Should we do it at the end of every TS ???- REMOTE ?
20.06.2012