Fahud-Qarn Alam Road Safety Audit Report Sasa

Embed Size (px)

Citation preview

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    1/12

    1

    For:

    Fahud-Qarn Alam road

    Annex to: Oman North Graded Road Improvement Project

    Annex 1: The road survey reports from RSST Controller North for the

    immediate action for improving the layout of the road and the traffic signs

    Muscat

    23.01.2012

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    2/12

    2

    Document Control Sheet

    Project Name: North Graded Road Improvement ProjectProject Number:Document /

    Report Title: Fahud-Qarn Alam graded road improvement option appraisal Issue 1Document /

    Report Number:Issue Status/Amendment Prepared Reviewed Approved

    Issue 1

    Document reviewed for

    Public ExhibitionName:

    Sasa Kocic

    Signature:

    Sasa Kocic

    Date: 23/01/12

    Name:

    Fayel Zarei

    Signature:

    FAYEL ZAREI

    Date: 24/01/12

    Name:

    Signature:

    Date:

    Document reviewed Name:

    Signature:

    Date:

    Name:

    Signature:

    Date:

    Name:

    Signature:

    Date:

    Document reviewed and

    Additional material inserted Name:

    Signature:

    Date:

    Name:

    Signature:

    Date:

    Name:

    Signature:

    Date:

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    3/12

    3

    1. Foreword

    1.1.1. The purpose of this document is to summarize the work

    carried out by ONE and RSST with regard to the issues of

    tackling the road safety issues on the graded road from

    Fahud to Qarn Alam, which was indicated as the priority road

    for the upgrading into the asphalt road by the on-site

    engineers and later identified by the TOPSIS method as the

    priority road for the improvement.

    1.1.2. It outlines the advantages and disadvantages of the options

    considered for the improvement of the road makesrecommendations to be brought forward to future decision on

    the approval of the budget for the upgrading the road into the

    asphalt road or deciding on the different improvement

    measures to tackle the safety issues raised.

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    4/12

    4

    2. Road Appraisal

    2.1. Introduction

    2.1.1. The Fahud-Qarn Alam road is the arterial road between the

    Fahud and Qarn Alam cluster in the PDO concession area,

    predominantly used by the PDO and related contractors for

    the transport and commuting, with approximately 117

    vehicles per hour using this road.

    The road is 125km long and going through the mostly rolling

    (hilly) terrain, with several sections on the steep gradients.

    Figure 1: Road inrelation to the PDO

    Locations

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    5/12

    5

    2.1.2. At present the road is a graded road with varying width, andwith safety lanes on the most of the road sections.

    The road is maintained as per the PDO requirements and the

    budget constraints, but the proper requirement, as pre thestandards and directives it is that the whole road should be re-sheeted four times in a year.

    Regular re-sheeting is not carried out, but only the work inrelation to the most damaged areas.

    2.1.3. As part of the review process the roads indicated by the

    Operation and Engineering teams have been classified and

    prioritized by the use of TOPSYS and the criteria of numberof RTA, price for upgrade, price for the maintenance and the

    traffic counts.

    The Fahud-Qarn Alam graded road came to be the top one in

    these criteria mentioned previously.

    Figure 2: Priority of the roads by

    TOPSYS

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    6/12

    6

    2.1.4. The RTA data was collected for the previous three years and

    the analysis of this data has provided the following:

    RTA Date Type of RTA Main cause Contributory factor

    18.09.2009 Rollover Driver error

    Road layout: consecutive bends,steep decline,

    Road Surface: difference in friction

    factors

    29.07.2010 RolloverExcessive

    speed

    Road Surface: difference in friction

    factors

    09.09.2010 Rollover Tyre burstRoad Surface: difference in friction

    factors

    08.10.2010 Rollover

    Excessive

    speed

    Road Surface: difference in friction

    factors

    28.11.2010 RolloverExcessive

    speed

    Road Surface: difference in friction

    factors

    23.01.2011 RolloverExcessive

    speed

    Road Surface: difference in friction

    factors due to the wet and muddy

    surface of the road

    21.04.2011 Rollover Tyre burst

    Road layout: rolling terrain

    Road Surface: difference in friction

    factors

    22.10.2011 RolloverExcessive

    speed

    Road Surface: difference in friction

    factors, holes and cracks in the road

    surface

    03.12.2011 RolloverExcessive

    speed

    Missing traffic signs

    Road Surface: difference in friction

    factors

    The evidences collected from the RTA that happened on this

    road indicate that the road surface and the road layout play a

    significant part as the main contributory factors in all of the

    RTA that have happened.

    The main problem is indicated in the following picture, and it

    represents the issue that is common to all of this RTA-s.

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    7/12

    7

    Figure 3: Typical road surface composition for the Fahud-Qarn Alam graded

    road

    The road surface cannot be compacted enough to provide a

    same friction on all of the wheels of the vehicle, therefore it

    has the same effect as the water ponds on the asphalted

    roads, creating the difficulty for the driver to keep his vehicle

    in line, and encouraging the road users to try to drive on the

    whole carriageway, instead of driving only on their side of the

    road.

    Also, the dispersion of these RTA shows that intervention on

    one location would not be sufficient, considering that the RTA

    locations are dispersed along the whole road.

    The measure of the re-grading or re-sheeting the road would

    also require a lot of work and it would also affect the usage of

    this road, considering that the re-sheeting of the graded road

    uses water etc., therefore also creating the hazard of creatinga wet and muddy road surface while trying to improve the

    condition of the road surface itself.

    The following pictures are from the RTA-s that happened

    during the 2011, and they indicate the road surface condition

    at the time of the RTA:

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    8/12

    8

    The pictures are from different RTA-s but they show almost

    the same conditions of the road layout: straight section,

    almost level terrain, therefore the application of the traffic

    signs would not be appropriate because there is no specific

    danger or hazard to warn the road users of.

    This kind of interventions can be applied on the approaches

    to the graded road roundabout close to Qarn Alam, or on the

    approach to the consecutive bends near Fahud, but on the

    straight sections of road it would not give any additional

    information and would not provide the results needed.

    Further, the RTA locations on the road indicate that the area

    of intervention would be 98km which is almost the whole road

    length.

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    9/12

    9

    The intervention in regards to the hazard of the consecutive

    bends near Fahud, if the appropriate solution for the graded

    road is to be constructed would also require a lot of

    investment, considering the earthwork needed for the

    appropriate profile to be achieved.

    The following pictures indicate the difference in the levels of

    the existing terrain and the proposed level.

    And also the 3D representation of the corridor of the graded

    road, with proper safety lanes is shown to present the future

    layout.

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    10/12

    10

    Difference in the levels would be 16.3m, as indicated in the

    existing ground (green) and the future ground (red) levels

    presented below:

    The corridor would have to be as presented in the following

    picture, if terraced walls are not introduced (the picture is for

    presentation purposes only, the detail design need to be

    done in order to get the accurate layout and the quantities for

    the work needed.

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    11/12

    11

    3. Conclusion

    The Fahud-Qarn Alam graded road should be upgraded into

    the asphalt road considering the traffic volumes, cost for the

    maintenance and the fact that most of the RTA-s thathappened on a straight road, almost level terrain and the

    soft measures of the driver training and the traffic signs

    placement will not be sufficient.

    This is of course the justification for the Fahud-Qarn Alam

    road only and it cannot be generally applied for upgrading of

    any other graded road, except as a reference, considering

    that other graded roads have their own characteristics in

    terms of layout, RTA data and usage.

  • 7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa

    12/12

    12