Upload
kocic-balicevac
View
218
Download
0
Embed Size (px)
Citation preview
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
1/12
1
For:
Fahud-Qarn Alam road
Annex to: Oman North Graded Road Improvement Project
Annex 1: The road survey reports from RSST Controller North for the
immediate action for improving the layout of the road and the traffic signs
Muscat
23.01.2012
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
2/12
2
Document Control Sheet
Project Name: North Graded Road Improvement ProjectProject Number:Document /
Report Title: Fahud-Qarn Alam graded road improvement option appraisal Issue 1Document /
Report Number:Issue Status/Amendment Prepared Reviewed Approved
Issue 1
Document reviewed for
Public ExhibitionName:
Sasa Kocic
Signature:
Sasa Kocic
Date: 23/01/12
Name:
Fayel Zarei
Signature:
FAYEL ZAREI
Date: 24/01/12
Name:
Signature:
Date:
Document reviewed Name:
Signature:
Date:
Name:
Signature:
Date:
Name:
Signature:
Date:
Document reviewed and
Additional material inserted Name:
Signature:
Date:
Name:
Signature:
Date:
Name:
Signature:
Date:
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
3/12
3
1. Foreword
1.1.1. The purpose of this document is to summarize the work
carried out by ONE and RSST with regard to the issues of
tackling the road safety issues on the graded road from
Fahud to Qarn Alam, which was indicated as the priority road
for the upgrading into the asphalt road by the on-site
engineers and later identified by the TOPSIS method as the
priority road for the improvement.
1.1.2. It outlines the advantages and disadvantages of the options
considered for the improvement of the road makesrecommendations to be brought forward to future decision on
the approval of the budget for the upgrading the road into the
asphalt road or deciding on the different improvement
measures to tackle the safety issues raised.
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
4/12
4
2. Road Appraisal
2.1. Introduction
2.1.1. The Fahud-Qarn Alam road is the arterial road between the
Fahud and Qarn Alam cluster in the PDO concession area,
predominantly used by the PDO and related contractors for
the transport and commuting, with approximately 117
vehicles per hour using this road.
The road is 125km long and going through the mostly rolling
(hilly) terrain, with several sections on the steep gradients.
Figure 1: Road inrelation to the PDO
Locations
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
5/12
5
2.1.2. At present the road is a graded road with varying width, andwith safety lanes on the most of the road sections.
The road is maintained as per the PDO requirements and the
budget constraints, but the proper requirement, as pre thestandards and directives it is that the whole road should be re-sheeted four times in a year.
Regular re-sheeting is not carried out, but only the work inrelation to the most damaged areas.
2.1.3. As part of the review process the roads indicated by the
Operation and Engineering teams have been classified and
prioritized by the use of TOPSYS and the criteria of numberof RTA, price for upgrade, price for the maintenance and the
traffic counts.
The Fahud-Qarn Alam graded road came to be the top one in
these criteria mentioned previously.
Figure 2: Priority of the roads by
TOPSYS
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
6/12
6
2.1.4. The RTA data was collected for the previous three years and
the analysis of this data has provided the following:
RTA Date Type of RTA Main cause Contributory factor
18.09.2009 Rollover Driver error
Road layout: consecutive bends,steep decline,
Road Surface: difference in friction
factors
29.07.2010 RolloverExcessive
speed
Road Surface: difference in friction
factors
09.09.2010 Rollover Tyre burstRoad Surface: difference in friction
factors
08.10.2010 Rollover
Excessive
speed
Road Surface: difference in friction
factors
28.11.2010 RolloverExcessive
speed
Road Surface: difference in friction
factors
23.01.2011 RolloverExcessive
speed
Road Surface: difference in friction
factors due to the wet and muddy
surface of the road
21.04.2011 Rollover Tyre burst
Road layout: rolling terrain
Road Surface: difference in friction
factors
22.10.2011 RolloverExcessive
speed
Road Surface: difference in friction
factors, holes and cracks in the road
surface
03.12.2011 RolloverExcessive
speed
Missing traffic signs
Road Surface: difference in friction
factors
The evidences collected from the RTA that happened on this
road indicate that the road surface and the road layout play a
significant part as the main contributory factors in all of the
RTA that have happened.
The main problem is indicated in the following picture, and it
represents the issue that is common to all of this RTA-s.
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
7/12
7
Figure 3: Typical road surface composition for the Fahud-Qarn Alam graded
road
The road surface cannot be compacted enough to provide a
same friction on all of the wheels of the vehicle, therefore it
has the same effect as the water ponds on the asphalted
roads, creating the difficulty for the driver to keep his vehicle
in line, and encouraging the road users to try to drive on the
whole carriageway, instead of driving only on their side of the
road.
Also, the dispersion of these RTA shows that intervention on
one location would not be sufficient, considering that the RTA
locations are dispersed along the whole road.
The measure of the re-grading or re-sheeting the road would
also require a lot of work and it would also affect the usage of
this road, considering that the re-sheeting of the graded road
uses water etc., therefore also creating the hazard of creatinga wet and muddy road surface while trying to improve the
condition of the road surface itself.
The following pictures are from the RTA-s that happened
during the 2011, and they indicate the road surface condition
at the time of the RTA:
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
8/12
8
The pictures are from different RTA-s but they show almost
the same conditions of the road layout: straight section,
almost level terrain, therefore the application of the traffic
signs would not be appropriate because there is no specific
danger or hazard to warn the road users of.
This kind of interventions can be applied on the approaches
to the graded road roundabout close to Qarn Alam, or on the
approach to the consecutive bends near Fahud, but on the
straight sections of road it would not give any additional
information and would not provide the results needed.
Further, the RTA locations on the road indicate that the area
of intervention would be 98km which is almost the whole road
length.
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
9/12
9
The intervention in regards to the hazard of the consecutive
bends near Fahud, if the appropriate solution for the graded
road is to be constructed would also require a lot of
investment, considering the earthwork needed for the
appropriate profile to be achieved.
The following pictures indicate the difference in the levels of
the existing terrain and the proposed level.
And also the 3D representation of the corridor of the graded
road, with proper safety lanes is shown to present the future
layout.
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
10/12
10
Difference in the levels would be 16.3m, as indicated in the
existing ground (green) and the future ground (red) levels
presented below:
The corridor would have to be as presented in the following
picture, if terraced walls are not introduced (the picture is for
presentation purposes only, the detail design need to be
done in order to get the accurate layout and the quantities for
the work needed.
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
11/12
11
3. Conclusion
The Fahud-Qarn Alam graded road should be upgraded into
the asphalt road considering the traffic volumes, cost for the
maintenance and the fact that most of the RTA-s thathappened on a straight road, almost level terrain and the
soft measures of the driver training and the traffic signs
placement will not be sufficient.
This is of course the justification for the Fahud-Qarn Alam
road only and it cannot be generally applied for upgrading of
any other graded road, except as a reference, considering
that other graded roads have their own characteristics in
terms of layout, RTA data and usage.
7/28/2019 Fahud-Qarn Alam Road Safety Audit Report Sasa
12/12
12