Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Facility Infrastructure Study for Caseless Ammunition
NDIA Small Arms Conference24 MAY 2011
Christopher A. Perhala, Martin J. Hopkins, Steven C. Lorence, and C. Byron TolbertBattelle505 King Avenue, Columbus, OH 43201
2
Acknowledgement
Work supported byJSSAP, Picatinny Arsenal, New Jersey
throughArmy Research Office – Scientific Services Program (ARO/SSP)
under USG contract W911NF-07-D-0001
3
Project Scope
• Develop Rough Order of Magnitude (ROM) cost estimate for Caseless (CL) ammunition production
• CL has only two common components w/current (brass-cased) ammo: bullet & primer mixture
• Focus on new or unique infrastructure needed– Facilities– Equipment
• Consider two production rates:– 400 million rounds per year (sustainment)– 1 billion rounds per year (surge)
• Production concept not detailed – only defined sufficient to support ROM estimate
4
Caseless Ammunition Technology
5
Site Selection Trade Study
Location 3Location 2
Component D011
RetrofitFacility
New Facility(TBD)
Component F012.1
3.2.1
RetrofitFacility
New Facility(TBD)
Component A024.1
RetrofitFacility New Facility
Component C034.2
CommercialVendor New Facility
Component F026
Cartridge Load,Assemble, Pack
8
Component A033.1
RetrofitFacility New Facility
Component A013.2
New Facility(location TBD)
Component G012
CommercialVendor New Facility
Component F015
Component F037
Component F032.3
3.2.3
Component F022.2
3.2.2
Component C013
Component C024
CommercialVendor New Facility
CommercialVendor New Facility
CommercialVendor New Facility
CommercialVendor New Facility
New LAP Facility(location TBD)
Component D01
Component F01
Component A02
Component C03
Component F02
Component A03
Component A01Component G01
Component F01
Component F03
Component F03
Component F02
Component C01
Component C02
6
Capital Costing Approach
Existing Facility Site Assessment
New Facility Site Assessment
Start CommerciallyAvailable?
No Capital Cost
No
Yes
Yes
No
DefineProcess
DefineEquipment List
Apply Facility CostScaling Factors
Capital CostEstimate
Yes
ProcessExists? No
Facility Exists? No
SufficientCapacity?
Yes
At MultipleFacilities?
YesEstimate Shipping
Costs
Site SpecificAdjustments
Retrofit Costs Only
At MultipleFacilities?
Yes
NoRetrofitFeasible?
Yes
DefineEquipment List
Apply Facility CostScaling Factors
No No
OutsourceFabricationPossible?
No
Yes
Cost Knownfor SimilarFacility?
Yes
No
Real EstateAvailable? No
Yes
SME PoolAvaialble? No
YesFeasible to
Acquire SMEPool?
No
Yes
Site SpecificAdjustments
Generic SiteCapital Estimate
Disqualify SiteEstimate ShippingCosts
Estimate SMEPool Startup
Site Specific CostAdjustments
Site SelectionProcess
Estimate ToolingCost
7
CL Production Network Concept
Bullet1
Component G012.1
3.2.1
Component C044.1
Component C014.2
Component E016
CartridgeAssemble & Pack
8
Component B013.1
Component A023.2
Component A012
Component D015
Link7
Component F022.3
3.2.3
Component F012.2
3.2.2
Component A023
Component C034
Production Network Diagram
Ammo Magazine9
FACILITY #4FACILITY #2 FACILITY #3FACILITY #1
Component C024.2
Retrofit or New Existing
Component A023.2
Component A012
Retrofit or NewExistingExisting
8
Molding Concepts
Injection Molding•Binder and propellant in separate feed lines•Propellant and binder mixed during injection•May employ de-airing manifold (high-speed,
filling without air pockets)
Liquid Injection Molding•Propellant mixed with binder precursors in
separate pre-mixes•Premixes in separate feed lines•Premixes mixed prior to injection
•May employ de-airing manifold (high-speed, filling without air pockets)
9
Mold Assembly Concept
Injector Manifold•Static mixers paired to balance load on
mandrels•May employ de-airing manifold (high-speed,
filling without air pockets)
Two-Piece Mandrels•Form entire internal cavity without pinch points•Lower Mandrel used to eject Cartridge Bodies
Link Groove Inserts•Form Link Groove without pinch points
•Automatic engage/disengage via pins in top plate
10
Molding Line ConceptInjection Machine
•Propellant mix injected into mold
•Slight pressure applied ensures complete fill
Cure•Propellant in mold for
several fill cycles until cured enough for subsequent
handling
Unlatch & Lift•Mold top removed
Eject•Gripper plate lowered onto mold
•Cartridges ejected•Gripper plate engages OD of Bodies
•Cartridges transferred to remainder of production lineClean
•Mold is cleaned to remove residual propellant pieces
Spray Release•Mold release applied as required
- ensures clean separation of propellant from mold
Visual Inspection•Machine vision inspection of mold
•If evidence of residue mold flagged for maintenance
Close & Latch•Mold lid from previous cycle placed on lower mold
•Pins on mold lid push Link Groove Inserts into place
Pressure Inspection•Manifold applies air pressure test for vent blockages
•If blockage then mold flagged for maintenance
Maintenance Swap•Molds flagged for maintenance are swapped out with spares to avoid downtime; serviced off-line
Spare Staging
11
Summary
• Developed Rough Order of Magnitude (ROM) cost estimates for Caseless (CL) ammunition production for two production rates– 400 million rounds per year (sustainment)– 1 billion rounds per year (surge)
• Focused on new or unique infrastructure needed– Facilities– Equipment– Trained personnel
• Concepts for production tooling and a new kind of production line were defined to a level sufficient to support ROM estimate
12
Contact Information
Christopher A Perhala, PEPrincipal Research Engineer
Battelle505 King Avenue
Columbus, OH 43201