Facilities Planning & ConstructionReport 2016 – 17
2nd Quarter Ending December 31, 2016
Overview• District SRID Spending (MG100)
– Summary– By College– By Site
• District Program Overview– Construction– Design– Planning/ Administrative
– Selected Photographs
2
District SRID Spending Summary
• Original Measure G Budget: $ 180,000,000• Interest & Other Revenues: $ 24,003,976• Total SRID Funds: $ 204,003,976• Total Funds Spent To Date: $ 156,373,309• Total Funds Unspent To Date: $ 47,630,666
3
4
Original Measure G Budget/Interest &Other Revenues
Total SRID Funds Funds Spent to Date & RemainingBalance for Use
$180,000,000
$204,003,976
$156,373,309
$24,003,976
$47,630,667
SRID Overall Expenditures
Interest & Other Revenues
Original Measure GBudget
Total SRID Funds
Spent SRID Funds
Unspent SRID Funds
5
Total for KCCD, $156,373,309
Bakersfield College, $70,045,464
Cerro Coso College, $38,283,176
Porterville College, $25,681,877
District Office, $22,362,792
SRID Expenditures By College
By College
Unspent SRID Funds By College
Bakersfield College,
$31,194,334
Cerro Coso College,
$2,421,677
District Office, $8,684,601
Porterville College,
$5,330,354
(SRID Allocated – SRID Spent)
6
District Program Overview Completed Projects 2nd Quarter Ending December 31, 2016
7
Campus Type Project Name Project Organization CodeTotal Project Expenditures
Start Date
Completion Date
Anticipated DSA Close
Date
Project Funding Source
Construction/Design % Complete
Project % Complete
Change % Comments
BC CAP BC Performing Arts Modernization28F740
$ 17,305,028 Jun-13 Jan-17 Dec-15 SRID/State 100% 100% 2.7%
CC SMCC Prop 39 Yr 3 Ext Lighting FB1064
$ 117,147 Feb-16 Apr-16 N/A Prop 39/Campus 100% 100% 0.0%
CC SMBishop Roof Repairs FB4003
$ 92,657 May-16 Aug-16 N/A State 100% 100% 0.0%
PC CAPPC Photovoltaic System FC1073
$ 4,371,127 Sep-15 Feb-16 May-16 Loan 100% 100% 0.0%
PC SM Stadium Parking Lot E & W Sections FC1006 $ 390,343.79 Jan-16 Mar-16 N/A Campus 100% 100% 11.4%
PC SM PC Allied Health HVAC,Reroof,Floor,Transformer Repair FC1037 $ 368,669 May-15 Jan-16 N/A State 100% 100% 0.0%
PC SMPC Prop 39 Year 3 Exterior Lighting FC1082
$ 28,385 Apr-16 Jun-16 N/A Prop 39 100% 100% 0.0%
PC SMPC T&I Welding Shop Classroom Upgrade FC1014
$ 62,624 Apr-16 Oct-16 N/A SRID/Campus 100% 100% 0.0%
District Program Overview Construction Projects 2nd Quarter Ending December 31, 2016
8
Campus Type Project Name Project Organization Code
Total Project Expenditures
Start Date
Completion Date
Anticipated DSA Close
Date
Project Funding Source
Construction/Design % Complete
Project % Complete
Change %
Comments
BC CAP BC STEM Building FA1094 1,500,378$ Oct-15 Jul-16 Nov-16 SRID/Campus 100% 99% 0.0% NOC FiledBC CAP BC Maintenance and Operations Building FA1078 1,033,669$ Dec-15 Aug-17 Dec-17 SRID 100% 25% 0.0% DSA Plan Approval completedBC SM DC Fire Alarm Cert DSA FA2012 35,628$ Jun-14 Apr-17 Aug-17 SRID 100% 99% 27.6% Pending DSA Closeout documentsBC SM BC STEM Room 26 and 27 Renovation FA1047 10,562$ May-14 Feb-17 Jul-17 RP207 100% 95% 0.0% Design for DSA Close-outBC SM BC Prop 39 Lighting Replacement Year 2 FA1039 301,265$ Jun-15 Aug-15 Nov-15 Prop 39 100% 100% 6.8%BC SM BC Football Practice Field Lighting FA1038 285,723$ Dec-15 Aug-16 Nov-16 SRID 100% 100% 0.0% DSA Close out/Litigation PendingBC SM BC Gymnasium Air Conditioning FA1112 588,760$ Nov-15 Sep-16 Dec-16 SRID 100% 85% 0.0% DSA Close out after Fire Alarm project closeoutBC SM BC Path of Travel FA1115 503,379$ May-16 Oct-16 Aug-17 SRID/State 100% 99% 7.2% Pending DSA CloseoutBC SM BC Fire Alarm Repair and Code Compliance FA1116 145,529$ Jun-16 Feb-17 Jun-17 State 100% 90% 1.4% LD Letter issuedBC SM BC Exterior Wayfinding FA1117 20,096$ May-16 Feb-17 N/A SRID/Campus 100% 99% 0.5% PunchlistBC SM BC SMRS Concrete Repairs & Replacement FA1121 -$ Oct-16 Aug-17 N/A State 10% 0% 0.0%BC SM BC Emergency Generator Repairs FA1121 -$ Oct-16 Dec-17 N/A State 10% 0% 0.0% In scopeBC SM BC SMSR Interior Painting, Multiple Buildings FA1122 -$ Nov-16 Dec-17 N/A State 10% 0% 0.0% RFP issuedBC SM BC EMS Replacement Phase 1 FA1123 -$ Nov-16 Dec-17 N/A State 5% 0% 0.0% Engineer selectedBC SM BC SMSR Campus Wide ADA Entry Door Replacement FA1128 -$ Oct-16 Dec-17 N/A State 0% 0% 0.0% In scopeBC SM BC HVAC Replacement FA1125 -$ Nov-16 Dec-17 N/A State 10% 0% 0.0% Engineer selectedBC SM BC Window Covering Replacement FA1124 -$ Nov-16 Dec-17 N/A State 20% 0% 0.0% In scopeBC SM BC Prop 39 Lighting Replacement Year 3 FA1040 338,423$ Nov-15 Dec-16 N/A Prop 39 100% 95% 0.0% Final Form B issuedBC SM BC Prop 39 Year 4 Exterior Lighting FA1120 -$ Oct-16 Jun-17 N/A Prop 39 50% 5% 0.0% PO AwardedBC SM BC Roofing Repairs FA1118 180,886$ Aug-17 N/A State 75% 65% 0.0% Phase 2 Awarded 4/16/16BC SM BC Flooring Replacement FA1119 316,639$ Oct-16 Dec-17 N/A State 100% 99% 0.0%CC CAP CC Main Building Modernization FB1062 10,033,909$ Aug-15 Jan-18 May-18 SRID 100% 51% 8.2%CC SM CC SMRS 2016-17 CDC Renovation FB1065 -$ Oct-16 Aug-17 N/A State 50% 0% 0.0%DO CAP District Wide Security Access Hardware FD1025 3,459,953$ Apr-15 Apr-17 N/A SRID 100% 30% 0% Bid Awarded, in constructionDO CAP DO District-wide Wireless Networking FA3013 106,945$ Apr-12 Ongoing N/A SRID 90% 90% 0.0%DO SM Weill SMSR 2016-17 EMS Replacement & Upgrade FA3021 -$ Oct-16 Apr-17 N/A State 50% 0% 0.0%DO SM Weill HVAC Replacement Phase 2 FA3018 8,671$ May-16 Apr-17 N/A State 99% 90% 0.0%DO SM Weill SMSR 2016-17 Fire Alarm Panel Replmt FA3020 -$ Oct-16 Apr-17 N/A State 50% 0% 0.0%PC SM PC Campus Security Upgrades Phases 1 - 3 FC1010 49,423$ Aug-16 Apr-17 N/A SRID/Campus 100% 55% 4.0%PC SM PC Gym Roof & HVAC Replacement FC1005 2,583,277$ Apr-16 Dec-16 Apr-17 SRID/Campus 100% 99% 0.3% Punch work ongoingPC SM PC Science-Math Cooling Tower Refurbishment FC1089 -$ Feb-17 Apr-17 N/A SRID 85% 0% 0.0% Award to go to February boardPC SM PC SMSR 2016-17 High Voltage Electrical Improvement FC1090 -$ Nov-16 May-17 N/A State/SRID 80% 0% 0.0% Award expected to go to March 2017 BoardPC SM PC Math/Science Elevator Repair FC1083 28,384.55$ Jul-16 Jul-19 Nov-19 SRID 65% 0% 0.0% At DSA for Plan ReviewPC SM PC SMSR Painting Exterior FC1009 67,931.50$ Dec-15 Feb-17 N/A State 100% 99% 0.0% Punch work ongoing
District Program Overview Design Projects 2nd Quarter Ending December 31, 2016
9
Campus Type Project Name Project Organization Code
Total Project Expenditures
Start Date
Completion Date
Anticipated DSA Close
Date
Project Funding Source
Construction/Design % Complete
Project % Complete
Change %
Comments
BC SM BC Swing Space FA1100 303,710$ Aug-17 May-17 Aug-18 SRID/Campus 80% 20% 0.0%CC SM Mammoth Center Modernization FB5023 79,806$ Dec-16 Dec-17 Mar-18 Mammoth 75% 25% 0.0%DO CAP DO Public Address Notification FD1026 36,014$ May-17 Aug-17 N/A SRID 80% 25% 0.0%
District FPP and IPP Planning Activities
10
Project Total Budget State Contribution Local Contribution TypeBC Science and Engineering Replacemen $39,036,000 $19,518,000 $19,518,000 FPPDC LRC $24,772,000 $12,267,000 $12,505,000 FPPPC Allied Health Facility $16,574,000 $8,287,000 $8,287,000 FPP
FPP Total $80,382,000 $40,072,000 $40,310,000BC Fine Arts Remodel for Efficiency $16,407,000 $13,494,000 $2,913,000 IPPBC Language Arts Remodel for Efficiency $11,975,000 $7,677,000 $4,298,000 IPPBC Student Services Modernization $18,872,000 $15,758,000 $3,114,000 IPPBC Welcome Center $5,558,000 $4,722,000 $836,000 IPPPC Career Technology Building $16,476,000 $8,284,000 $8,192,000 IPPPC Human Performance and Kinesiology $12,217,000 $6,139,000 $6,078,000 IPPPC Student Services Modernization $9,656,000 $4,828,000 $4,828,000 IPP
IPP Total $91,161,000 $60,902,000 $30,259,000
Current Construction
Org CodeNo.Currently in Construction PhaseConstructionComments
BudgetSpent to date Project Funding Source% Construction CompleteChange Order % Description
Bakerfield College
FA11041Admin Building Entry Door Replacement$ 29,715$ 20,995SRID100%0.00%Closeout19945.25
2Baseball Clubhouse Phone/Fiber Conduit$ 61,737$ 45,000SRID100%0.00%Submitted to DSA
3Bookstore Barnes & Noble$ 260,000-0-B & N99%0.00%Lease Agreement
FA11054Business Ed Summer Projects$ 165,000$ 153,554SRID/Campus100%0.00%
FA11015Campus Water & Gas Line (Phase 1 & 2)$ 3,920,200$ 287,604SRID100%4.80%Phase 1 = 100% Complete
FA11026Central Chiller Plant Replacement$ 2,600,000$ 272,555SRID7%0.00%Equipment Purchased
FA11068FACE Bldg Summer Project$ 82,000$ 26,619SRID/Campus100%0.00%
FA11079Fine Arts Summer Project$ 201,000$ 109,687SRID/Campus100%4.00%
28F75810GET Facility$ 1,229,912$ 22,213GET/Campus99%N/APrimarily GET Funded
11Language Arts Building Entry Door Replacement$ 57,925-0-SRID100%0.00%Invoice not submitted
FA101712Math & Science Roof Repairs$ 18,993$ 16,863SRID/Campus100%0.00%NOC Filed
28F74013Performing Arts Modernization (SAM)$ 19,273,903$ 2,616,532SRID/State15%0.70%Change Orders Pending
28F13814Photo Voltaic$ 9,292,500$ 8,541,708CEG/ Lease Rev Bonds/Campus99%2.49%NOC to Board
FA108915Science & Engineering Roof Repairs$ 593,800$ 401,298SRID/Campus99%0.00%Punchlist, CO's Pending
FA110816Science Engineering Summer Project$ 175,000$ 167,372SRID/Campus100%0.00%
17Student Services Building Entry Door Replacement$ 88,637-0-SRID100%0.00%
28F13718Thermal Energy System Phase 2$ 3,586,200$ 1,994,652Campus100%4.20%Commissioning
Weill Center
18F74219NORAD HVAC Upgrades$ 356,800$346,957SRID100%6.15%Closeout
20SWC Modernization DSA Certification$ 136,204$0SRID0%0.00%Bid Phase
Porterville College
FC105121Fine Arts HVAC Replacement$ 78,900$33,364SRID/Campus100%0.00%
58F10822Fire Lane/ ADA Parking Lots$ 562,119$89,772SRID/Campus98%10.91%Punchlist
FC107223Gym Water Heater Tank Replacement$ 24,600$ 15,274SRID/Campus100%0.00%Closeout
58F1064 pcm01024Math Science HVAC, Boilers, Water Heaters, Pumps$ 974,548$ 728,732SRID/Campus98%-0.31%Punchlist, CO's Pending
58F11025Student Center Reroof and Interiors$ 855,359$ 588,736SRID/Campus90%10.15%Change Orders Pending
26Main Campus Electrical Upgrade$ 517,500$ 46,227SRID100%0.00%
&"-,Bold"KCCD Construction Status ReportFacilities Planning, Design, ConstructionAs of June 30, 2013
&D
Current Design
cCurrently in Design PhaseBudgetDesignComments
Approved PPRBudgetSpent to date Project Funding Source% Design completeRevised Work Authorization %Description
Bakersfield College
1Performing Arts East Side Improvementsü$ 1,303,872$ 43,600SRID100%0%
2NE Parking Lot ADA & Shade Structureü$ 365,453$ 3,259SRID100%0%Bid Phase
3Elevators Repair and Replaceü$ 353,873$ 116,964SRID90%5%
4Language Arts Basement Fireproofingü$ 62,000$ - 0SRID/Campus0%0%Not started
5Maintenance and Operations Building$ 3,861,360$ - 0SRID5%0%
6Exterior Lighting$ 544,037$ - 0Prop 395%0%
Delano Center
7Fire Alarm Certification for DSAü$ 26,044$ 6,850Campus80%0%
Weill Center
8Parking Lot Upgradesü$ 190,900$ 24,889Other95%0%DSA Reviewing
9KCCD Security Planningü$ 25,846$ 25,846SRID90%0%
Cerro Coso College
10Main Building Modernizationü$ 15,354,088$ 323,206SRID10%0%Construction Documents
11Campus Wide Fire Alarm Integrationü$ 150,000$ 15,213SRID100%0%
12Gym HVAC Replacementü$ 840,900$ 69,240SRID/Campus100%0%
13Occupational Lab Reroof/HVAC/Welding Expü$ 1,287,041$ 93,939SRID/Campus100%0%Bid Phase
14Occupancy & Evacuation Signage$ 84,020$ 27,203Campus100%0%Bid Phase
15Maintenance and Operations Building$ 300,000$ - 0SRID15%0%Design Development
Bishop
16Water Filtration$ 27,258$ - 0Grant5%0%
Mammoth
17Art Classroom Expansion and Monument Sign ü$ 300,396$ - 0Mammoth75%0%Design Development
18Parking Lot and Street Improvements$ 1,219,436$ - 0Mammoth35%0%Design Development
Porterville College
19Gymnasium Reroof & HVAC Replacementü$ 2,818,325$ 71,113SRID/Campus20%0%
20Path of Travel - to Main Streetü$ 126,400$ 14,811SRID95%0%DSA Review
21Central Plant and Chiller Loopü$ 1,300,000$ 54,265SRID98%0%Bidding in November
22Asphalt Plano Fire Lanes (Plano to Main)ü$ 363,400$ - 0SRID/Campus6%0%
23Mapping and Topoü$ 6,900$ - 0SRID/Campus50%0%
24Exterior Lightingü$ 130,000$ - 0Prop 395%0%
No.Currently in Planning & Studies PhaseBudgetDesignComments
Forecast CostSpent to date Funding Source% Complete
1Transition plans$ 130,000$ 114,520SRID100%
2Construction Standards$ 110,000$ 88,514SRID90%In final review
3CEQA$ 100,000$ - 0SRID0%
&"-,Bold"KCCD Design Status ReportFacilities Planning, Design, ConstructionAs of June 30, 2013
&D
Sheet1
Scheduled Maintenance$ 270,000on addington sheet
ESCC
Bishop Scheduled Maintenance$ 183,434$ 91,717on addington sheet
Bishop Water Well Remediation$ 64,500
Cerro Coso College
IT Electrical Room 120 - BishopIT funded
Relocation of UPS System - CCIT funded
IT Office relocation - CCcampus funded
Planning
ProjectTotal BudgetState ContributionLocal ContributionType
BC Science and Engineering Replacement$39,036,000$19,518,000$19,518,000FPP
DC LRC$24,772,000$12,267,000$12,505,000FPP
PC Allied Health Facility$16,574,000$8,287,000$8,287,000FPP
FPP Total$80,382,000$40,072,000$40,310,000
BC Fine Arts Remodel for Efficiency$16,407,000$13,494,000$2,913,000IPP
BC Language Arts Remodel for Efficiency$11,975,000$7,677,000$4,298,000IPP
BC Student Services Modernization$18,872,000$15,758,000$3,114,000IPP
BC Welcome Center$5,558,000$4,722,000$836,000IPP
PC Career Technology Building$16,476,000$8,284,000$8,192,000IPP
PC Human Performance and Kinesiology$12,217,000$6,139,000$6,078,000IPP
PC Student Services Modernization$9,656,000$4,828,000$4,828,000IPP
IPP Total$91,161,000$60,902,000$30,259,000
$171,543,000$70,569,000Grand Total
&"-,Bold"KCCD Planning Status ReportFacilities Planning, Design, ConstructionAs of June 30, 2013
&D
Pending and On going
Administrative & Research Activities
Accounting and Reporting (CM14 and P6)
Integration of systems
Design Guidelines
Document Management
Blueprints
Project Files
DSA Buildings Certification
Energy saving, Energy management, Energy generation
Working with CCC/IOU for Prop 39 projects
Fire Alarm Systems
Five-year Facilities Plan
Informational Website Development
Assisting IT Department
Security & Mass Notification
Assisting IT Department
Utilities Mapping
BC Maintenance & Operations
11
BC STEM Building
1212
CC Main Building Modernization
13
PC Gym Re-roof & HVAC Replacement
14
BOND OVERSIGHT COMMITTEE LISTINGCommittee Chair- Vacant
Vice Chair- Jesse Frederick (March 2016-February 2018)
Bruce Massa (October 2015-September 2017)
Matthew Anderson (December 2016-November 2018)
Doug Starr (February 2017-January 2019)
Rob Goff (February 2017-January 2019)
Steve Murray (February 2017-January 2019)
Cheryl M. Scott (February 2017-January 2019)
Paula De La Riva-Barrera (March 2017-February 2019)
Gregory D. King (March 2017-February 2019)
Marcus S. Hackler (March 2017-February 2019)
Student Trustee:Jose Herrera (July 2016 – June 2017)
15
Questions?
16
�Facilities �Planning & Construction�Report 2016 – 17��Overview�District SRID Spending �SummarySlide Number 4Slide Number 5Unspent SRID Funds By CollegeDistrict Program Overview �Completed Projects 2nd Quarter Ending December 31, 2016District Program Overview �Construction Projects 2nd Quarter Ending December 31, 2016District Program Overview �Design Projects 2nd Quarter Ending December 31, 2016District FPP and IPP Planning Activities BC Maintenance & Operations�BC STEM BuildingCC Main Building ModernizationPC Gym Re-roof & HVAC ReplacementBOND OVERSIGHT COMMITTEE LISTINGQuestions?