16
FACILITIES, PLANNING, AND CONSTRUCTION April 14, 2014 Construction Report

Facilities, Planning, and Construction April 14, 2014 Construction Report

  • Upload
    gail

  • View
    41

  • Download
    0

Embed Size (px)

DESCRIPTION

Facilities, Planning, and Construction April 14, 2014 Construction Report. Area Currently Under Construction/ Planning. Facilities under Construction: V.R. Eaton High School 540,000 SF __________ - PowerPoint PPT Presentation

Citation preview

Page 1: Facilities, Planning, and Construction April 14, 2014 Construction Report

FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report

Page 2: Facilities, Planning, and Construction April 14, 2014 Construction Report

Facilities under Construction:

V.R. Eaton High School 540,000 SF __________ Total 540,000 SF

Facilities in Planning/Bidding Stage:

Peterson E.S. Addition 14,000 SF Beck E.S. Addition 8,000 SFNHS Chiller Replacement NAPrairie View Drainage Improvement NA ____________ Total 22,000 SF

Total Projects under Construction, Planning and Bidding: 562,000 SF562,000 SF

Area Currently Under Construction/ Planning Area Currently Under Construction/ Planning

Page 3: Facilities, Planning, and Construction April 14, 2014 Construction Report

V. R. Eaton High SchoolV. R. Eaton High SchoolArchitect: Corgan Associates Contractor: Pogue Construction CompanyConst. Start Date: Spring 2013Completion Date: August 2015

Status:Pier drilling is completeGeothermal wells are completeGrade beams are 95% completeFoundation slab is 50% completeRough electrical and plumbing is being installedSite grading and utility installation is underwaySteel erection is approximately 10% complete

(Please note that the aerial photo was taken in March and does not reflect April progress)

Page 4: Facilities, Planning, and Construction April 14, 2014 Construction Report

May 2013

March 2014

Page 5: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 6: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 7: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 8: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 9: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 10: Facilities, Planning, and Construction April 14, 2014 Construction Report

Peterson Elementary School AdditionPeterson Elementary School AdditionArchitect: SHW ArchitectsContractor: Northstar BuildersConst. Start Date: Spring 2014Completion Date: August 2014

Status:Classroom concrete slabs have been pouredSteel has begun to be erected for classroomsGrade beams have been poured for stage/cafeteria/gym expansion

Page 11: Facilities, Planning, and Construction April 14, 2014 Construction Report

January 2014

April 2014

Page 12: Facilities, Planning, and Construction April 14, 2014 Construction Report

Beck Elementary School AdditionBeck Elementary School AdditionArchitect: SHW ArchitectsContractor: Balfour Beatty ConstructionConst. Start Date: Spring 2014Completion Date: August 2014

Status:Pier drilling is underwaySite work is underway

Page 13: Facilities, Planning, and Construction April 14, 2014 Construction Report

Possible ONCOR Electric Power

Distribution Line

Page 14: Facilities, Planning, and Construction April 14, 2014 Construction Report

Miscellaneous Maintenance Projects

• Prairie View Elementary School Drainage Improvement– Water drains toward the front of the building

during heavy rains and flows into the building– Project will be to route water to a retention pond

and ditch adjacent to FM 3433– Possible replacement of the front driveway

• Northwest High School– Replace a 22 year old chiller– Anticipating a major failure within the next year– Current chiller contains obsolete R-22 refrigerant– The repair cost does not justify the repair– The efficiency of the replacement chiller will

provide reduction in energy cost

Page 15: Facilities, Planning, and Construction April 14, 2014 Construction Report

Pending Project Close-Out Change Orders

• Cox Elementary School• Love Elementary School• Subvarsity Stadium

Page 16: Facilities, Planning, and Construction April 14, 2014 Construction Report

FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report