FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report
Facilities under Construction:
V.R. Eaton High School 540,000 SF __________ Total 540,000 SF
Facilities in Planning/Bidding Stage:
Peterson E.S. Addition 14,000 SF Beck E.S. Addition 8,000 SFNHS Chiller Replacement NAPrairie View Drainage Improvement NA ____________ Total 22,000 SF
Total Projects under Construction, Planning and Bidding: 562,000 SF562,000 SF
Area Currently Under Construction/ Planning Area Currently Under Construction/ Planning
V. R. Eaton High SchoolV. R. Eaton High SchoolArchitect: Corgan Associates Contractor: Pogue Construction CompanyConst. Start Date: Spring 2013Completion Date: August 2015
Status:Pier drilling is completeGeothermal wells are completeGrade beams are 95% completeFoundation slab is 50% completeRough electrical and plumbing is being installedSite grading and utility installation is underwaySteel erection is approximately 10% complete
(Please note that the aerial photo was taken in March and does not reflect April progress)
May 2013
March 2014
Peterson Elementary School AdditionPeterson Elementary School AdditionArchitect: SHW ArchitectsContractor: Northstar BuildersConst. Start Date: Spring 2014Completion Date: August 2014
Status:Classroom concrete slabs have been pouredSteel has begun to be erected for classroomsGrade beams have been poured for stage/cafeteria/gym expansion
January 2014
April 2014
Beck Elementary School AdditionBeck Elementary School AdditionArchitect: SHW ArchitectsContractor: Balfour Beatty ConstructionConst. Start Date: Spring 2014Completion Date: August 2014
Status:Pier drilling is underwaySite work is underway
Possible ONCOR Electric Power
Distribution Line
Miscellaneous Maintenance Projects
• Prairie View Elementary School Drainage Improvement– Water drains toward the front of the building
during heavy rains and flows into the building– Project will be to route water to a retention pond
and ditch adjacent to FM 3433– Possible replacement of the front driveway
• Northwest High School– Replace a 22 year old chiller– Anticipating a major failure within the next year– Current chiller contains obsolete R-22 refrigerant– The repair cost does not justify the repair– The efficiency of the replacement chiller will
provide reduction in energy cost
Pending Project Close-Out Change Orders
• Cox Elementary School• Love Elementary School• Subvarsity Stadium
FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report