Upload
creda
View
26
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Facilities Modernization Program Funded by Measure B Project Report. May 21, 2012. PROJECT PROGRESS REPORT Student Services & Central Administration. LAS POSITAS COLLEGE May 21, 2012. Project Team: Architect : Steinberg Architects Construction Manager : Parsons Brinckerhoff - PowerPoint PPT Presentation
Citation preview
Facilities Modernization ProgramFunded by Measure B
Project Report
May 21, 2012
PROJECT PROGRESS REPORTStudent Services & Central Administration
Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction
Project Update:• Storefront installation is complete. Glazing is 95% installed in the Storefronts.• Curtainwall installation is complete. Glazing is 75% installed in the Curtainwalls.• Interior framing is 95% complete. Sheetrock installation and taping on the 2nd floor is 80% complete.
Single side of sheetrock is underway on the 1st floor.
• Data cable is continuing to be pulled throughout the second floor.• Elevators installation has started.• Mechanical units were delivered and installed on the roof. Ducting is underway.
Occupancy: Spring 2013
LAS POSITAS COLLEGEMay 21, 2012
PROJECT PROGRESS REPORTScience Building, Phase II
Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc
Project Update:• Interior Casework, Lighting and Fume hoods are installed.• Ceiling Tiles are installed in all rooms, Power to building complete, Elevator installed • Stair Treads and Guardrails are completed.• Greenhouse installed.• Exterior and Interior Painting is complete. Restrooms completed.• 2nd floor classrooms are completed, with furniture staged.• Storefront installation and Glazing Completed. • Exterior Hardscape and Flatwork is being completed.
Occupancy: 09/2012
LAS POSITAS COLLEGEMay 21, 2012
PROJECT PROGRESS REPORTCampus Boulevard Phase I-III
Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: Suarez & Munoz Construction, Inc.
Project Update:• Project was Bid on March 13, 2012 and Contractor was Board Approved April 17, 2012.• Construction Starts May 29, 2012
Occupancy: 10/2012
LAS POSITAS COLLEGEMay 21, 2012
PROJECT PROGRESS REPORTPhotovoltaic System Phase II
Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff
Project Update:• Fencing Completed.• Racking System and Array installation is completed.• Inverters and Transformer installed and completed. • New Switchgear tie in May 20, 2012.
Operational: February 2012
LAS POSITAS COLLEGEMay 21, 2012