19
1 19-Apr-15 YanWeiLi Liu Liang Cheng Yuguang Wu Yong Jun DH1/A3-C2/DE/M/2728 C 15-Mar-14 YanWeili Xie Ruzhi Cheng Yuguang Wu Yongjun DH1/A3-C2/DE/M/2617 B 26-Feb-14 YanWeili Xie Ruzhi Cheng Yuguang Wu Yongjun DH1/A3-C2/DE/M/2208 A 6-DEC-13 YanWeili Xie Ruzhi Cheng Yuguang Wu Yongjun FIRST ISSUE RE DATE PREPARED BY CHECKED BY REVIEWED BY APPROVED BY DESCRIPTION OWNER POWER GENERATION CORPORATION 1 THERMAL POWER PROJECT MANAGEMENT BOARD 3 CONSULTANT POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 2 CONTRACTOR DONGFANG ELECTRIC CORPORATION LIMITED SUBCONTRACTOR GUANG DONG ELECTRIC POWER DESIGN INSTITUTE HUNAN PROVINCIAL THERMAL POWER CONSTRUCTION COMPANY EVN Ref. No.: DH1/TD640/045/001/00 DEC Ref. No.: DH1-DE-A3-M-14-5121 PROJECT: DUYEN HAI 1 THERMAL POWER PLANT PROJECT CONTRACT No.DH1-30032010 Document Status: FOR APPROVAL Document Title: ITP for installation of equipment and pipe in Compressed Air System Document No.: F4281-GEDI-M-SS-ITP-1039-3 Rev.: 1

F4281-GEDI-M-SS-ITP-1039-3 ITP for equipment and pipe installation in_ compressed air system.pdf

Embed Size (px)

Citation preview

  • 1 19-Apr-15 YanWeiLi Liu Liang Cheng Yuguang WuYong Jun DH1/A3-C2/DE/M/2728

    C 15-Mar-14 YanWeili Xie Ruzhi Cheng Yuguang WuYongjun DH1/A3-C2/DE/M/2617

    B 26-Feb-14 YanWeili Xie Ruzhi Cheng Yuguang WuYongjun DH1/A3-C2/DE/M/2208

    A 6-DEC-13 YanWeili Xie Ruzhi Cheng Yuguang WuYongjun FIRST ISSUE

    RE

    V.

    DATE PREPARED BY CHECKED BY REVIEWED BY APPROVED BY DESCRIPTION

    OWNER

    POWER GENERATION CORPORATION 1THERMAL POWER PROJECT MANAGEMENT BOARD 3

    CONSULTANT

    POWER ENGINEERING CONSULTING JOINT STOCKCOMPANY 2

    CONTRACTOR

    DONGFANG ELECTRIC CORPORATION LIMITED

    SUBCONTRACTOR

    GUANG DONG ELECTRIC POWER DESIGN INSTITUTE

    HUNAN PROVINCIAL THERMAL POWER CONSTRUCTION

    COMPANYEVN Ref.

    No.:DH1/TD640/045/001/00

    DEC Ref.

    No.:DH1-DE-A3-M-14-5121

    PROJECT: DUYEN HAI 1 THERMAL POWER PLANT PROJECTCONTRACT No.

    DH1-30032010

    Document

    Status:FOR APPROVAL

    Document Title: ITP for installation of equipmentand pipe in Compressed Air System

    Document No.:

    F4281-GEDI-M-SS-ITP-1039-3Rev.:

    1

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    ITP for installation of equipment and pipe in Compressed Air SystemDH1-M-ITP-3-J/G-Date: 2015-04-18Rev.: 1

    NO Inspection/TestApplicable

    specification or rules Record formatPARTICIPATION BY

    FrequencyInspection

    criteriaSUBCON DEC A3-C2

    1Welder qualification check WPS/PQR

    ASME B31P H R Before installation Comply with requirements

    welder test in site P H W Before installation Comply with requirements

    2 Equipment installation

    Compressed air tank, buffer tank

    Design drawing

    DH1-M-ITP-3-J/G-0005-01-01

    P W W During and after installationComply with requirements

    Water-cooled air compressor DH1-M-ITP-3-J/G-0005-01-02dryer

    Installation of sewage pump Design drawing DH1-M-ITP-3-J/G-0005-02 P W W After installation

    Comply with requirements

    Visual inspection of equipment grouting DL/T5047-95 DH1-M-ITP-3-J/G-0005-01-01 P W W

    Before secondary grouting

    Comply with requirements

    3

    Pipe installation

    3.1 Inspection of take-in materials

    Check according to material list Design drawing DH1-M-ITP-3-J/G-0006-01 P W W Before installation

    Comply with requirements Appearance inspection

    position check DL5190.4-2004 DH1-M-ITP-3-J/G-0006-02 P W W After installation Comply with requirements

  • 3.2Pipe installation

    size check DL5190.4-2004 DH1-M-ITP-3-J/G-0006-02 P W W After installation Comply with requirements Pipe fit-up check Design drawing DH1-M-ITP-3-J/G-0006-05 P W W After installation Comply with requirements Welding apperance check Design drawing DH1-M-ITP-3-J/G-0006-06 P W W After installation Comply with requirementsNDT for pipe welded junction DL869-2004 DH1-M-ITP-3-J/G-0006-07 P W W After installation

    Comply with requirements

    3.3Pipe valve installation DL5190.4-2004 DH1-M-ITP-3-J/G-0006-03 P W W After installation Comply with requirements

    3.4 Installation of supports and hangers

    position check DL5190.4-2004 DH1-M-ITP-3-J/G-0006-04 P W W After installation Comply with requirementssize check DL5190.4-2004 DH1-M-ITP-3-J/G-0006-04 P W W After installation Comply with requirements Welding apperance check Design drawing DH1-M-ITP-3-J/G-0006-06 P W W After installation Comply with requirements

    4 Leak test and flushing of system

    test range

    Design drawing DH1-M-ITP-3-J/G-0006-08 P H H After installation Comply with requirements

    NDT record of checking pipe welded junction

    system line inspection

    check remaining work

    check test gage

    watering leak test

    pressurize to test pressure check

    4 Leak test and flushing of system

    test pressure falls to working pressure check

    Design drawing DH1-M-ITP-3-J/G-0006-08 P H H After installation Comply with requirementsflushing

    compressed air blowing

  • 5 Paint&anticorrosion for equipment and pipe WPP DH1-M-ITP-3-J/G-0006-09 P H W Before and after anticorrosion Comply with requirements

    6 Hand over to commission team

    punch list DH1-M-ITP-3-J/G-0007- After installation

    Review all inspection documents

    Legend HHold WWitness RRecord PPerform

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0005--01-01( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Tank installation

    Structure/Location: Air compressed house

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    No. Working procedure Inspection item Inspection criteriaAssessment

    DEC PECC2 TPMB3

    1

    Foundation check

    Centerline deviation 10mm

    2 Elevtion deviation 10mm

    3 Spacing check of anchor bolt 10mm

    4

    Equipment locating

    Horizontal deviation 5mm

    5 Centerline deviation 5mm

    6 Elevation deviation 10mm

    7 Orientation of inlet and outlet nozzle Comply with design requirements

    8 Visual inspection of equipment grouting clean, without debris

    9

    Visual check of equipment

    Equipment name

    10 KKS number

    11 Manufacturer

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form:M-ITP-3-J/G-0005--01-01

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0005--01-02( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Dryer and Water-cooled air compressor installation

    Structure/Location: Air compressed house

    Outlet Elevation

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    No. Working procedure Inspection item Inspection criteriaAssessment

    DEC PECC2 TPMB3

    1Foundation check

    Centerline deviation 10mm

    2 Elevtion deviation 10mm

    3

    Equipment locating

    Horizontal deviation 5mm

    4 Centerline deviation 5mm

    5 Elevation deviation 10mm

    6 Orientation of inlet and outlet nozzle Comply with design requirements

    7 Visual inspection of equipment grouting clean, without debris

    8

    Visual check of equipment

    Equipment name

    9 KKS number

    10 Manufacturer

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form:M-ITP-3-J/G-0005--01-02

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0005-02( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Installation of sewage pump

    Structure/Location: Air compressed house

    Centerline deviation

    Steel beam upper surface elevation

    Reference line

    Method of Inspection

    Visual Laboratory Test Measurement Survey Others:

    Working procedure Iinspection item Inspection criteria

    AssessmentDEC PECC2 TPMB3

    Equipment check

    Visual inspection of shell and component parts No damage,crack,deformation,and layering

    Installation of equipment

    Elevation deviation 10mm

    Centerline deviation 5mm

    Steel beam levelness deviation

    2mm

    Connection of equipment and pipe No stress connection

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. M-ITP-3-J/G-0005-02

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0006-01-( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Material inspection

    Based documentation for acceptance:

    1. Request for inspection:

    2. Approved drawings:

    3. Inspection and Test Plan or related standards(if any)

    4. Measurement and Test Result report:

    5. Site Diary

    6. Other relative documents (if any):

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    No. Type of material Specification Material Quantity Visual inspection

    Assessment

    ACC. REJ.

    1 Pipe

    2 Pipi fitting

    3 Valve

    4 Paint

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0006-01

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0006-02-( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Pipe installation

    Structure/Location: Air compressed house

    Based documentation for acceptance:

    1. Request for inspection:

    2. Internal inspection report, attached:

    3. Approved drawings:

    4. Inspection and Test Plan or related standards(if any)

    5. Measurement and Test Result report:

    6. Site Diary

    7. Other relative documents (if any):

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    Working procedure Inspection item Inspection criteriaAssessment

    DEC PECC2

    Pipe installation

    Verticality deviation of flange 2mm

    Coordinate deviation Overhead:10m Trench:15mm underfround:20mm

    Verticality deviation of stand pipe 2L/1000 and 15mm

    Material of spacer for supports and hangers Rubber,teflon or equivalent material as pipe

    Fit-up check

    Type and size of groove Comply with design requirements

    Straightness of butt-joint pipe

    Dn100mm 1mm

    Dn100mm 2mm

    Visual inspection of welding

    No slag inclusion,porosity and crack

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0006-02

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    EPC CONTRACTOR

    ID No.:DH1-M-ITP-3-J/G-0006-02-( )

    Date :

    Start Time:

    Finish Time:

    Inspected work: Pipe installation

    Structure/Location: Air compressed house

    Method of Inspection

    AssessmentTPMB3

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    OwnerTPMB3

    Form: M-ITP-3-J/G-0006-02

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-JG-0006-03-( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Valve installation for pipe

    Structure/Location: Air compressed house

    Based documentation for acceptance:

    1. Request for inspection:

    2. Internal inspection report, attached

    3. Approved drawings:

    4. Inspection and Test Plan or related standards(if any)

    5. Measurement and Test Result report:

    6. Site Diary

    7. Other relative documents (if any):

    Drg.No. Valve name Valve type KKS numberInstallation

    orientationas per drawing

    Bolt tightening

    Assessment

    DEC PECC2 TPMB3

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-JG-0006-03

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0006-04-( )Date :

    Sub. Contractor: GEDI/HTPC Start Time: Work title:Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Installation of supports and hangers for pipeStructure/Location: Air compressed houseBased documentation for acceptance:

    1. Request for inspection:2. Internal inspection report, attached:3. Approved drawings:4. Inspection and Test Plan or related standards(if any)5. Measurement and Test Result report:6. Site Diary7. Other relative documents (if any):

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    Working procedure Inspection item Inspection criteria

    Assessment

    DEC PECC2 TPMB3

    Configuration of supports and hangers

    Layout and process size Comply with design requirements

    Threaded suspender Not bent,burr-free thread,fit up with nut

    Clampholder base plate Smooth,planeness,fit well

    Root layout and process size Comply with design requirements

    Installation of supports and

    hangers

    Spacer of supports and hangers for stainless steel pipe teflon spacer or same material as pipe

    Span of supports and hangers Comply with design requirements

    Welding inpsection Comply with stipulation of DL/T869

    Comments from DEC:Comments from PECC2:Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0006-04

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-JG-0006-05-( )Date :

    Sub. Contractor: GEDI/HTPC Start Time: Work title: Installation of equipment and pipe in Compressed Air System

    Finish Time:

    Inspected work: Pipe fit-up inspection report

    Structure/Location: Air compressed house

    Drawing No. Line No./Part No. Joint No. MaterialPipe size(mm) Root

    Gap(mm)

    Status

    Diameter/Thickness ACC REJ

    Comments from DEC:Comments from PECC2:Comments from TPMB3:

    Conclusion:

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-JG-0006-05

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0006-06-( )Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Welding check for supports and hangers

    Structure/Location: Air compressed house

    Drawing No. Joint No. Welder ID Material Size ThicknessNDT Status

    RT UT MT PT ACC REJ

    Comments from DEC:Comments from PECC2:Comments from TPMB3:

    Conclusion:

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0006-06

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    RADIOGRAPHIC EXAMINATION REPORT ID No.: DH1-M-ITP-3-J/G-0006-07--( )

    Page of

    Client Name: Request No.:

    Acceptance criteria: Procedure No.: Date of shooting: Item:

    Welding process:

    Installation of equipment and pipe in Compressed Air System

    MATERIAL INFORMATION

    Drawing No.: Line No.: Material:

    EQU

    IPM

    ENT X-RAY GAMMA RAY

    Test Voltage : KV mA Isotope / Activity : Serial No.: Focal Spot Size : mm x mm Source Size : mmFFD SFD :

    MAT

    ERIA

    L

    Film type :

    TEC

    HN

    IQU

    E

    IQI : Film size : Location Source side Film side

    Intensifying Screen Type : Lead Development Manual Automatic Front: mm Rear: mm

    Shooting Technique

    SWSI DWSIDensity Required : DWDI Super imposedSensitivity Required : Panoramic

    EVALUATION

    Joint No. Welder ID. Film Location

    OD/Length(mm)

    Thk/SCH(mm)

    FilmDensity RESULT

    DEFECT (mm)Remarks

    Type Length Location

    (QUANTITY OF FILMS: 00 )ABBREVIATION : ACC-ACCEPTABLE REJ-REJECT RS-RESHOOT IP-INCOMPLETE PENETRANT

    P-POROSITY S-SLAG INCLUSION LF-LACK OF FUSION CV-CONCAVITYC-CRACK UC-UNDERCUT TI-TUNGSTEN INCLUSION BT-BURN THROUGHFM-FILM MARK CP-CLUSTER POROSITY RW-REWELD ER-EXCESSIVE ROOT

    APAVE ASIA PACIFIC CO., LTD DEC/EPC CONTRACTOR EVNPECC2 EVNTPMB3

    Evaluated by: Name: Name: Review by:

    Signature: Signature: Signature: Signature:

    Date: Date: Date: Date:Form:M-ITP-3-J/G-0006-07

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0006-08( )Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title:Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Leak testStructure/Location: Air compressed house

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    Working procedure Inspection item Inspection criteria

    AssessmentDEC PECC2 TPMB3

    Check before leak

    test

    Drawing No.Test boundary Refer to attachement

    NDT record of checking pipe welded junction Comply with ASME B31 requirements

    System line check Comply with design requirementsRemaining work check Comply with design requirementsPressure gauge check Attach the qualified calibration report

    Hydro test

    Test pressure 150% of design pressure

    water filling check No leakage

    Pressurized to test pressure No leakage

    Reduce to working pressure No leakage

    System flushing

    Water flushing Outlet water and inlet water with same transparency

    Compressed air purging Exhaust without smoke by visual inspectionComments from DEC:Comments from PECC2:Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0006-08

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECTOWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0006-09( )

    Date :

    Sub. Contractor: GEDI/HTPC Start Time:

    Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work:Painting and anticorrosion for equipment and pipe

    Structure/Location: Air compressed house

    Method of Inspection Visual Laboratory Test Measurement Survey Others:

    Check before painting

    Primer Type Lowest Derusting Grade Assessment

    DEC PECC2 TPMB3

    Asphalt primer St3 or Sa2

    Alkyd resin primer and epoxy aspalt primer St3 or Sa2

    Other type resin Sa2

    Zinc-rich primer of all kinds Sa2.5

    Installation location Primer Intermediate Finish

    Painting of indoor equipment,pipe,supports and hangers

    Epoxy zinc-rich 1 layer 50m

    Epoxy micaceous 1 layer 100m

    Epoxy anti-corrosive paint 1 layer 40m

    Painting of outdoor equipment,pipe,supports and hangers

    Epoxy xinc-rich 1 layer 80m

    Epoxy micaceous 1 layer 100m

    Polyurethane finish 1 layer 50m

    Indoor platform & ladder,and lifting facilities Epoxy xinc-rich 1 layer 50m

    Epoxy micaceous 1 layer 100m

    Epoxy anti-corrosive paint 1 layer 40m

    Outdoor platform & ladder,and lifting facilities

    Epoxy xinc-rich 1 layer 80m

    Epoxy micaceous 1 layer 100m

    Polyurethane finish 1 layer 50m

    Underground embedded pipeCoal tar epoxy anti-corrosive paint 1 layer 200um

    Modified epoxy anti-corrosive asphalt paint3 layers of glass

    cloth in 4 layers of paint 150m

    Trench pipeEpoxy asphalt primer 1 layer 200um

    Epoxy asphalt finish 1 layer100m

    Comments from DEC:Comments from PECC2:Comments from TPMB3:

    Conclusion: Accepted the above inspected work and agreed to carry out the next works.Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0006-09

  • DUYEN HAI 1 THERMAL POWER PLANT PROJECT

    OWNER CONSULTANT EPC CONTRACTOR

    INSPECTION REPORTID No.:DH1-M-ITP-3-J/G-0007-( )Date :

    Sub. Contractor: GEDI/HTPC Start Time: Work title: Installation of equipment and pipe in Compressed Air System Finish Time:

    Inspected work: Punch listStructure/Location: Air compressed house

    Item No. Description of defect Originator Responsible partyCOMPLETION

    DEC PECC2 TPMB3

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    Comments from DEC:

    Comments from PECC2:

    Comments from TPMB3:

    Conclusion:

    Sub-ContractorGEDI/HTPC

    EPC ContractorDEC

    ConsultantPECC2

    OwnerTPMB3

    Position

    Signature

    Full Name

    Note: = Accept, x = Reject. Form: M-ITP-3-J/G-0007

    A-ITP ITP 1