Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
F acilities Construction
Leroy San Miguel ASSISTANT SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
NORTHSIDE INDEPENDENT SCHOOL DISTRICT
2014 Bond October 2019
James Evans DIRECTOR OF FACILITIES CONSTRUCTION
1
DR. CAROLINE WERNLI ELEMENTARY SCHOOL New Elementary School
(Formerly Rancho Del Lago Area ES)
Architect – Garza Bomberger & Associates Project Architect – Roy LewisNISD Project Manager – Marilyn Sevedge Contractor – Bartlett Cocke General Contractors, LLC Contract Amount – $25,401,000 Construction Period – March 2019 – May 2020 Project Scope – New Elementary School Construction Construction Status – 35%
Foundation second floor poured. Vertical Superstructure and CMU in progress and classroom.Roof joists in progress.
Rendering of Dr. Caroline Wernli Elementary School Aerial View
3
DR. CAROLINE WERNLI ELEMENTARY SCHOOL New Elementary School (Formerly Rancho Del Lago Area ES)
Classroom Wing Cafeteria / Gymansium Area
Corridor Hallway4
SAM RAYBURN MIDDLE SCHOOL Building Replacement
Architect – Marmon MokProject Architect – Monty HowardNISD Project Manager – James EvansContractor – Turner ConstructionContract Amount – $13,900,000Construction Period – June 2018 – August 2019 Project Scope - Building Replacement Construction Status – 90% Overall Gym - Complete (Locker rooms pending)Band - 95%Library - 85% (Pending Furniture)Courtyard - 60% (Pavers & Landscape in progress)Substantial Completion - Closeout in progress.
New Gym New Band Hall
6
SAM RAYBURN MIDDLE SCHOOL Building Replacement
New Library
Band Hall and Courtyard New Gym and Boys Lockers
7
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Bomberger & Associates Project Architect – Roy LewisNISD Project Manager – James EvansContractor – CGC General Contractors, Inc.Contract Amount - $4,249,000Construction Period – June 2018 – August 2019 Construction Status – CompleteProject Scope – Cafeteria / Kitchen Renovation
Seating Area
9
JOHN MARSHALL HIGH SCHOOL Library Upgrades
Architect – Garza Bomberger & AssociatesProject Architect – Roy LewisNISD Project Manager – James EvansContractor – WR Griggs ConstructionConstruction Budget - $4,000,000 Construction Period – June 2019 – March 2020 Project Scope - Library Addition & Renovation Construction Construction Status – 25%
Demolition complete. Excavation complete.Piers in progress.MEP Rough in progress.
Rendering of Interior View
11
JOHN MARSHALL HIGH SCHOOL Library Upgrades
Demolition - Existing Library
Demolition - Existing Library 12
Health Careers High School Expansion
Project Scope – Expansion of Health Careers High School & Northside Children's Center
Design Status – In Design
Nortside Children's Center
14
Anson Jones Middle School New Magnet Program
Project Scope – New Magnet School - Additions & Renovations
City OwnedFacility
Design Status – Programming in Progress
15
MEADOW VILLAGE ELEMENTARY SCHOOL ALE & Mechanical Upgrades
Architect – Chesney Morales Partners, Inc. Project Architect – Richard MoralesNISD Project Manager – Marilyn Sevedge Contractor – D.L. Bandy Constructors, Inc. Contract Amount - $3,222,000Construction Period – June 2019 – February 28, 2020 Project Scope – ALE and Mechanical Upgrades Construction Construction Status - 75% overall
Phase I - ALE Classrooms complete Phase II - Mechanical upgrades in progress. Phase III - Mechanical upgrades (Scheduled to start Nov. 25, 2019).
Library AreaALE Classroom
17
2019 SECURITY LOBBIES FOR 21 CAMPUSES
Architect – NextGen ArchitectsProject Architect – Joel HernandezNISD Project Manager – James EvansContractor – Marksmen General Contractors, Inc. Contract Amount - $3,998,000Construction Period – June 2019 – December 2019 Project Scope – Security LobbiesConstruction Status - 65% Overall
Phase I: CompleteJune - August 2019Driggers ES Evers ES Fernandez ES Fisher ESHatchett ESLieck ESMyers ESWestwood Terrace ES
Burke ES CarsonElrod ES Martin ESMurnin ESRaba ES
Behlau ESGalm ESLangley ESLewis ESOak Hills ESOtt ESNorthside Police Department
Phase II: In Progress Sept. - October 2019
Phase III: In Progress Nov. - December 2019
18
2019 SECURITY LOBBIES - BURKE ES, CARSON ES, MURNIN ES & ELROD ES
Carson ES
Burke ES Murnin ES
Elrod ES 19
WILLIAM P. HOBBY MIDDLE SCHOOL Bus / Student Covered Walkway
Architect – Shawn Kaarlsen & AssociatesProject Architect – Shawn KaarlsenNISD Project Manager – Marilyn SevedgeContractor – Central BuildersContract Amount – $2,269,000Construction Period – June 2019 - November 2019Project Scope – Bus / Student Covered Walkway and New Front Entry Construction Status – 85%
Masonry, Metal Roofing, and Soffit in progress.
New Front Canopy
20
WILLIAM P. HOBBY MIDDLE SCHOOL Bus / Student Covered Walkway
Ramp at Walkway Canopy
Walkway Canopy
21
GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building
Architect – Nextgen ArchitectsProject Architect – Joel HernandezNISD Sr. Project Manager – Thomas A. Curiel Contractor – Casias ConstructionContract Amount - $4,397,000Construction Period – June 2019 – July 2020Project Scope – Library and Classroom Building Addition Construction Status – 30%
Steel erection in progress.Concrete Foundation and columns complete.CMU commencing next week.
Rendering of Front Entry
22
GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building
Steel Framing Steel Framing
Steel Framing 23
NORTHWEST CROSSING ELEMENTARY SCHOOL Cafeteria / Kitchen Renovation
Architect – Pfluger ArchitectsProject Architect – Carr HornbuckleNISD Project Manager – Chris ParkerContractor – D.L. Bandy Constructors, Inc. Contract Amount – $2,320,000Construction Period – June 2019 - December 2019 Project Scope – Cafeteria / Kitchen Renovation Construction Status – 40% Overall
Phase II - Kitchen renovation - Masonry in progress, MEP in progress.
Kitchen TileKitchen Tile
24
NORTHWEST CROSSING ELEMENTARY SCHOOL Cafeteria / Kitchen Renovation
Exterior Masonry Exterior Masonry
Tile Kitchen 25
KALLISON RANCH AREA MIDDLE SCHOOL New Middle School
Architect – Alamo ArchitectsProject Architect – Jerry LammersNISD Project Manager – Thomas CurielCMAR – Bartlett Cocke General Contractors, LLC Construction Budget - $50,000,000 Construction Period – October 2019 – May 2021 Project Scope – New Middle School Construction Construction Status - 5%
Amendment I - Site & Superstructure - Board Approved Aug. 27, 2019Amendment II - Building - Pending Board Approval.
Rendering of Front Entrance
27
"GALM ROAD AREA" HIGH SCHOOL
Architect – Alamo ArchitectsProject Architect – Jerry LammersNISD Project Manager – James EvansCMAR – Joeris ContractorsConstruction Budget – $125,000,000 Construction Period – February 2020 - June 2022 Project Scope – New High School Construction Status – 0%
New High School
Rendering of Front Entrance
Amendment I - Groundwater control (Pending Board Approval) Amendment II - Structure (Pending Board Approval) Amendment III - Building (Drawings in progress) Amendment IV - Finishes (Drawings in progress)
29
MARSHALL LAW & MEDICAL SERVICES MAGNET HIGH SCHOOL
Architect – Pfluger ArchitectsProject Architect – Carr HornbuckleNISD Project Manager – Tom CurielContractor – TBDConstruction Budget - $24,000,000 Construction Period - March 2020 – August 2021 Project Scope - New Magnet High School - Replacement of Building "B" Construction Status - Drawings & Specifications in progress
Renovation of Building "L" and Relocation of Athletic Fields
Rendering of Future Elevation
30
PAT NEFF MIDDLE SCHOOL Cafeteria and Administration Upgrades
Architect – Garza ArchitectsProject Architect – Jesse GarzaNISD Project Manager – Tom CurielContractor – TBDConstruction Budget - $9,800,000Construction Period – June 2020 – February 2021Project Scope – Cafeteria Expansion and Administration Building Replacement Construction Status - Drawings & Specifications in progress
Rendering of Front Entrance
31
FM 471 NORTH AREA ES #4 New Elementary School
Architect – Garza Architects/NextGen Project Architect – Jesse GarzaNISD Project Manager – Marilyn SevedgeContractor – TBDConstruction Budget - $24,000,000 Construction Period – March 2020 - April 2021 Project Scope – New Elementary School Construction Status – Drawings & Specifications in progress
Rendering of Front Entrance
32
SAM RAYBURN MIDDLE SCHOOL Fine Arts Addition
Architect – Marmon MokContract Amount – $1,500,000Construction Period – April 2020 - December 2020 Project Scope - Fine Arts AdditionConstruction Status – Drawings & Specifications in progress
33
2018 BOND PROGRAM YEAR 2 (SUMMER 2020) PROJECTS IN DESIGN
PROJECT LIST
2020 Door Hardware at 7 CampusesFlooring Replacement - Luna MS / Helotes ES / Holmgreen Center / Lewis ES 2020 Security Lobbies at 23 Campuses Luna MS - Science Lab Addition/RenovationCody ES - Bus/Student Covered WalkwayPassmore ES - Library Addition/Renovation Rudder MS - Kitchen/Cafeteria Upgrades Adams Hill ES - Administration Upgrades Taft HS - Library Addition/Renovation Westwood Terrace ES - Building Replacement
34
Roofing Projects
Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
General Funds
NORTHSIDE INDEPENDENT SCHOOL DISTRICT
September 2019 Update
35
2016 Hail Damage Roofing Projects
Vale Middle SchoolZachry Middle School Driggers Elementary SchoolBriscoe Middle School Colonies North Elementary School Hoffmann Elementary School Scobee Elementary School Family Engagement CenterNorthwest Crossing Elementary School Henderson Elementary School Knowlton Elementary School
LIST OF SC HOOLS
Phase I, Phase II & Phase III - Complete
Phase IV - In Construction Phase V - In Construction
O'Connor High School (2nd Phase) Brandeis High School (1st Phase) Stinson Middle SchoolKuentz Elementary School Northside Learning Center
Phase VI – Bidding - Fall 2019
Wanke Elementary School Brandeis High School (Phase 2) Locke Hill Elementary School Carson Elementary School Alternative High SchoolDub Farris Athletic Complex NISD NatatoriumBurke Elementary School Human Resources (Bldg. A) Thornton Elementary School Brauchle Elementary School Hobby Middle School
Phase VII - Forthcoming - Summer 2020
Support Services CenterOak Hills Terrace Elementary School Kelly Smith Technology Center Northside Activity CenterNorth Transportation Station Pease Middle SchoolElrod Elementary School Fernandez Elementary SchoolBoone Elementary School
Holmes High School Rhodes Transportation Center Ward Elementary School McDermott Elementary SchoolMead Elementary SchoolMyers Elementary School
Health Careers High SchoolNorthside Tennis CenterJefferson Middle SchoolMarshall High SchoolBrennan High SchoolTaft High SchoolGarcia Middle SchoolMireles Elementary School
36
2014 & 2018 Bond Projects
ROOFING PROJECTS
Maintenance Annex Building (2014 Bond) - CompleteJohn Jay High School (2014/2018 Bond) - In Construction John Glenn Elementary School (2014/2018 Bond) - In Construction Adams Hill Elementary School (2018 Bond) - In ConstructionTaft High School (2014 Bond + Hail Damage) Forthcoming - (Summer 2020)
37