Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 1
(I) BASIC INFORMATION
S.
No.
Items Details
1 Name of the Project Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
2 Serial No. in schedule
8(a) Building and Construction
Projects as per MoEF Notification
14/9/2006
3 Proposed
capacity/area/length/tonnage to be
handled/command area/lease
area/number of wells to be drilled
Total Plot Area 49851.931 m2
(12.3187
Acres)
Permissible FAR @1.75% (80902.5 m2)
Achieved FAR @ 173.54% (80228.47
m2)
Permissible Ground Coverage @ 40 %
(11557.50 m2)
Achieved Ground Coverage (1891.911
m2)
4 New/Expansion/Modernization Renewal
5 Existing capacity/Area etc. Not Applicable
6 Category of project B
7 Does it attract the general
condition? If Yes, please specify No
8 Does it attract the specific
condition? If Yes, please specify No
9 i) Location of unit
ii) Plot, Survey No, Khasra No.
iii) Village
iv) Tehsil
v) District
vi) State
Village-Gwal Pahari, Gurgaon
Faridabad road, Sector-3 District-
Gurgaon
25//18, 22, 23, 35//15/2, 16/1/1, 36//
3/1/2, 3/2, 1/2, 10/1, 11/1, 2/1, 9/2,
12/1, 3/1/1, 2/2, 9/1, 12/2, 7, 8, 13,
14/1, 15/1/1
Gwal Pahari
Sohna
Gurgaon
Haryana
10 Nearest Railway station/Airport
along with distance in kms.
Gurgaon Railway Station Approx 14.5
km in West Direction & Indira Gandhi
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 2
International Air Port 13 Km North
West
11 Nearest town, City, Dist. Head
Quarter along with distance in kms.
Gurgaon City 12 Km, West
12 Village Panchayat, Zila Parishad,
Municipal Corporation, Local
body(Complete postal addresses
with telephone nos. to be given)
Municipal Corporation
Civil Lines, Officers Colony,
Gurgaon, Haryana
Phone: 18001801817
Email: [email protected]
13 Name of Applicant M/s Lavish Buildmart Pvt. Ltd.
14 Regd. Address Office No. 2, Second Floor, Mahipalpur
Extension, Delhi-110037
15 Address for correspondence(1):
Name
Designation
Address
Pin Code
E mail
Telephone
Mobile
Fax No.
M/s Jasmine Buildmart Pvt. Ltd.
406 4th floor, Elegance Tower 8 Jasola
District Center New Delhi
Mr. Satish Seth
Authorized Signatory
Pegasus One, Ground Floor, Behind
IBIS Hotel, Golf Course Road,
DLF Phase-V, Sector-53, Gurgaon
122002
0124 499 8250
8826195020
Address of correspondence(2): Environment Consultant
M/s Vardan EnviroNet
(Accredited from QCI/NABET)
D-142,SushantLok-III, Golf Course
Extension Road,
Gurgaon, Haryana
Tel No.0124-4291036
Email: [email protected]
16 Detail of alternative site, if any.
Location of these sites should be
shown on a topo-sheet.
This is a Group Housing Colony project
for which renewal of license has
already been awarded by Director
Town and Country Planning and most
of the construction most has been
completed.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 3
Hence, Not applicable in this case.
17 Interlinked Project There is not any interlinked project.
18 Whether separate application for
interlinked project has been
submitted
Not Applicable. In view of item No. 17
above
19 If, Yes Date of Submission
Not Applicable. In view of item No. 17
above
20 If no , reason
Not Applicable. In view of item No. 17
above
21 Whether proposal involves
approval/clearance under: if yes,
details of same and status to given
a) Forest (conservation) Act
1980?
b) Wild life protection Act 1972?
c) c) CRZ notification 1991?
No. The unit does not fall in any
notified reserved forest area.
No. The proposed project site does not
fall in any wildlife protected area.
No. The unit does not fall in any
Notified coastal regulation zone.
22 Whether there is any Govt.
order/policy relevant/relating site?
1.Town and Country Planning
Department
2. Assurance of water supply from
HUDA
23 Forest land involved (hectares)
No Forest land is involved in the
proposed project.
24 Whether there is any litigation
pending against the project and / or
land in which is project is proposed
to be setup:
a) Name of court
b) Case No.
c) Orders/directions of Court, if
any and its relevance with
the proposed project.
There is no litigation pending against
the project and land.
Therefore, Information required
against point a, b & c is not applicable.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 4
(II) ACTIVITY:
1. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes
in water bodies, etc.)
S. No. Information/Checklist
Confirmation Yes/ No
Details thereof (with approximate
quantities/ rates, wherever possible)
with source of information data
1.1 Permanent or temporary
change in land use, land
cover or topography
including increase in
intensity of land use(with
respect to local land use
plan) Yes
a.) The selected site falls under
Residential land use as per the Gurgaon
Manesar Urban development plan 2031
and will be developed as per the same.
b.) The proposed project site was a
vacant land and does not involve
activity of any type and construction is
under progress. It is anticipated that
the construction activities of the
proposed project would not have an
adverse effect on the land use Further,
local land use planning department will
control the type, density and location of
development.
1.2 Clearance of existing land,
vegetation and building?
Yes
Few shrubs and grasses were found to
be existing on the project site; which
were cleared before starting
construction no extensive clearing of
vegetation is required.
No building demolition.
1.3 Creation of new land
uses? Yes
The site will be developed as per the
Gurgaon Manesar Master Plan 2031.
1.4 Pre-construction
investigations e.g. bore
house, soil testing?
Yes
Soil investigation was carried out and
the results were found satisfactory.
1.5 Construction works?
Yes
The Construction activities will be
confined within the project premises;
there will be no physical change outside
the project boundary.
1.6 Demolition works? No
Project site was vacant land. Hence,
demolition was not required.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 5
1.7 Temporary sites used for
construction works or
Housing of construction
workers? No
All the construction activity including
stocking of raw materials is being
confined within the project site only.
No temporary shelters for labour are
required. Local labors from nearby area
are hired. Sanitation facilities are being
developed at site.
1.8 Above ground building,
structures or Earthworks
including linear structures,
cut and fill or excavations
Yes
Excavation has been carried out for
foundation of buildings only. The
excavated soil will be used in
backfilling and other area development
activities.
1.9 Underground work
including mining or
tunneling?
No
No underground work including
mining/ tunneling is required except
excavation of earth.
1.10 Reclamation works? No No reclamation work is required.
1.11 Dredging? No No dredging is required.
1.12 Offshore structures? No No offshore structure is required.
1.13 Production and
manufacturing processes? No
No production/ manufacturing process
is involved as the proposed project is a
Group Housing Colony.
1.14 Facilities for storage of
goods or materials?
Yes
Raw material is being stored at site in a
covered area. Cement is being
separately stored under cover in bales.
Sand is being stacked neatly under
tarpaulin cover. Bricks and steel is being
laid in open.
1.15 Facilities for treatment or
disposal of solid waste or
liquid effluents?
Yes
Solid Waste:
The solid waste generated from the
project will be in the form of:
Domestic Waste:
Approximately 747 kg/day domestic
solid waste is estimated to be
generated from the project activity; this
is being collected from designated
locations and segregated into inorganic
and organic wastes. The inorganic non-
biodegradable wastes is being sold to
authorize vendors for recycling and the
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 6
biodegradable wastes will be disposed
according to MSW (Management&
Handling) Rules, 2000.
Hazardous Waste
No hazardous waste will be produced
from project activities except waste oil
from DG sets.
Liquid Effluents
During construction phase, sewage will
be treated through septic tank. The
wastewater in operation phase will be
treated up to tertiary level in a STP
having the capacity of 186 KLD and the
treated sewage will be reused for
flushing and landscape development.
The rest of the treated water will be
given to the nearby construction site
for construction purpose only.
Dewatered/dried sludge generated
from the STP plant will be used as
manure for landscape development &
tree plantation.
1.16 Facilities for long term
housing of operational
workers? No
Local labour is being hired from nearby
areas during construction phase. So,
there is no need to create permanent
facilities for long-term housing of
operational workers.
1.17 New road, rail or sea
traffic during construction
of operation?
No
The site has good connectivity to NH-8.
Only internal roads, paths will be
developed for vehicular movements of
construction material during
construction phase whereas internal
tracks and paths will be developed for
traffic circulation (to avoid any
congestion) during operational phase.
1.18 New road, rail, air
waterborne or other
transport infrastructure
including new or altered
No
The site is well connected through the
road network. The nearest highway is
NH-8 at a distance of approximately 8.8
km towards West.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 7
routes and stations, ports,
airport etc?
1.19 Closure or diversion of
existing transport routes
or infrastructure leading
to changes in traffic
movements?
No
Since the site is well connected to
Gurgaon Faridabad Road which has
high traffic density; not required the
diversion or closure of existing traffic
routes.
1.20 New or diverted
transmission lines or
pipelines?
No
There will not be any new/diverted
transmission line or pipeline around the
proposed project.
1.21 Impoundment, damming,
culverting, realignment or
other changes to the
hydrology of watercourses
or aquifers?
No
No impoundment, damming, culverting,
realignment or other changes to the
hydrology of surface watercourses is
proposed.
1.22 Stream crossings? No
There is no stream running across the
site.
1.23
Abstraction or transfers of
water from ground or
surface waters?
No
Total water requirement will be 226
KLD, which include 114 KLD for fresh
water requirement & 112 KLD for
recycled water requirement out of
which 64 KLD will be used for flushing,
38 KLD will be used for landscape
development and 10 KLD will be used
for DG Cooling. During construction
phase, water demand is being fulfilled
by STP treated water. During
operational phase, water will be
supplied through HUDA.
1.24
Changes in water bodies
or the land surface
affecting drainage or run-
off?
No
Runoff will increase due to increased
paved surface. However, increased
runoff will be managed by well-
designed rainwater harvesting system
and storm water management plan.
1.25
Transport of personnel or
materials for construction,
operation or
decommissioning?
Yes
Transport of personnel/material during
construction and operation phase are
envisaged. Adequate parking space
within the project site for loading and
unloading of materials will be provided.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 8
Adequate parking space will be
provided during operational phase of
the project for the visitors & staff
within the premises.
1.26 Long-term dismantling or
decommissioning or
restoration works?
No
No Long term dismantling or
decommissioning or restoration work
will be involved.
1.27 Ongoing activity during
decommissioning which
could have an impact on
the environment?
No
No decommissioning activity is
involved, Hence, No impact on the
environment by the proposed project is
supposed.
1.28 Influx of people to an area
in either temporarily or
permanently?
No
Local laborers from nearby area are
being employed during the construction
phase. In the operation phase, most of
the expected occupants will be from
the surrounding areas. Hence, the
project will lead to a redistribution of
occupants within the city. Thus, no
significant influx of people is envisaged.
1.29 Introduction of alien
species? No
The landscaping is being carried out
with mainly local species with a few
ornamental varieties of flora that are
well suited to the local conditions.
1.30 Loss of native species or
genetic diversity? No
There is being no significant impact on
the native species or genetic diversity.
2. Use of Natural resources for construction or operation of the Project (such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S. No. Information/Checklist
confirmation Yes/No
Details thereof (with approximate
quantities/ rates, wherever
possible) with source of
information data
2.1 Land especially undeveloped
or agricultural land (ha) No
Proposed site was having wild
grasses which were cleared and the
Group Housing Colony is under
constructed on vacant land. Local
and indigenous plant species will
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 9
also be planted at proposed site.
2.2 Water (expected source &
competing users) unit: KLD Yes
Total water requirement for the
proposed will be 226 KLD which
include 114 KLD for Fresh water
requirement and 112 KLD for
recycled /treated water
requirement
2.3 Minerals (MT) Yes
Minerals such as sand and
aggregates is being required during
the construction phase.
2.4
Construction material –
stone, aggregates, and/soil
(expected source – MT)
Yes
All materials for construction is
being arranged through selected
suppliers.
2.5 Forests and timber (source –
MT) Yes
All material forests and timber is
being provided by selected
suppliers. However, steel frames
etc shall be used to minimize the
use of timber.
2.6
Energy including electricity
and fuels (source, competing
users) Unit: fuel (MT), energy
(MW)
Yes
The total demand load is estimated
6000 KW Power is being supplied
by DHBVN
2.7
Any other natural resources
(use appropriate standard
units)
No
No other natural resource will be
involved in the project except the
mentioned above.
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about
actual or perceived risks to human health.
S. No.
Information/Checklist
confirmation
Yes/No Details thereof (with
approximate quantities/ rates,
wherever possible) with source
of information data
3.1 Use of substance or materials,
which are hazardous (as per
MSIHC rules) to human health
or the environment (flora,
Yes The project site is proposed for
development of Group Housing
Colony project. Hence, storage of
hazardous chemicals (as per
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 10
fauna and water supplies) MSIHC Rules) is not expected.
3.2 Changes in occurrence of
disease or affect disease
vectors (e.g. insect or water
borne diseases)
No Suitable drainage and waste
management measures (with
frequent spray of insecticides
etc.) is being adopted in both the
construction and operational
phase such that there will be no
stagnation of water or
accumulation of waste. This will
effectively restrict the
reproduction and growth of
disease vectors.
3.3 Affect the welfare of people
e.g. by changing living
conditions?
Yes Socio-economic standard of
people will improve due to
increased employment
opportunities provided by this
project. This will lead to better
quality of life and will also set a
standard for future developments
in the area.
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patients,
children, the elderly etc
No Impacts of this type are not
expected.
3.5 Any other causes No
No other causes are involved
except the mentioned above.
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
S.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with
approximate quantities/ rates,
wherever possible) with source
of information data
4.1 Spoil, overburden or mine
wastes
No No such spoil, overburden or mine
wastes is being generated.
4.2 Municipal waste (domestic
and or commercial wastes)
Yes The total municipal solid waste to
be generated is approximately 747
kg/ day. The inorganic non-
biodegradable wastes will be sold
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 11
to authorized vendors for
recycling and the biodegradable
wastes will be disposed according
to MSW (Management &
Handling) Rules, 2000.
4.3 Hazardous wastes (as per
Hazardous Waste
Management Rules)
NO No Hazardous Waste is been
expected from the proposed
project.
4.4 Other industrial process
wastes
No Not applicable as this is a Group
Housing Colony project.
4.5 Surplus product No Not applicable as this is a Group
Housing Colony project.
4.6 Sewage sludge or other
sludge from effluent
treatment
Yes Sludge generated from the STP
plant will be dried and later will be
used as manure for landscape
development.
4.7 Construction or demolition
wastes
Yes The construction waste will
consist of excess earth and
construction debris along with
cement bags, steel in bits and
pieces, insulating and packaging
materials etc.
Recyclable waste construction
materials is being sold to
authorized recyclers. Unusable
and excess construction debris is
being disposed at designated
places in tune with the local
norms.
4.8 Redundant machinery or
equipment
No Redundant machinery will not be
generated.
4.9 Contaminated soils or other
materials No
Contaminated soils or other
materials will not be generated.
4.10 Agricultural wastes No No agricultural wastes will be
generated.
4.11 Other solid wastes No No other solid waste would be
generated.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 12
5. Release for pollutants or any hazardous, toxic or noxious substances to air
(Kg/hr).
S.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with
approximate quantities/ rates,
wherever possible) with source
of information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes The project does not envisage
any major air pollution sources
except vehicles. The pollution
generated from the vehicular
movement is being check by
regular check up of vehicles. Local
native plants is being used in tree
plantation to reduce the impact
of pollution.
5.2 Emissions from production
processes
No No production processes is
involved as it is a Group Housing
Colony project. Hence, there will
be no such emissions.
5.3 Emissions from materials
handling including storage or
transport
Yes Small quantities of fugitive
emissions are envisaged during
transport and handling of
construction materials. Such
emissions will be temporary and
controlled by the use of sprinkling
and other viable techniques like
covering of loose material.
5.4 Emissions from construction
activities including plant and
equipment
Yes This is being restricted to the
construction phase and the
construction site only.
5.5 Dust or odors from handling
of materials including
construction materials,
sewage and waste
Yes Dust is anticipated during loading
and unloading of construction
material and excavation of upper
earth surface. These will however
be temporary in nature, which is
being controlled by providing
water sprinklers. Tarpaulin cover
is being provided on stored loose
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 13
materials to reduce the dust
emission.
5.6 Emissions from incineration
of wastes
No Not applicable. There will not be
any incineration of waste is
proposed.
5.7 Emissions from burning of
waste in open air (e.g. slash
materials, construction
debris)
No Open burning of biomass/other
material is being prohibited on
site as this is a construction of
Residential project.
5.8 Emissions from any other
sources
No Not Applicable
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S. No. Information/Checklist
confirmation Yes/No
Details thereof (with
approximate quantities/ rates,
wherever possible) with source
of information data
6.1
From operation of
equipment e.g. engines,
ventilation plant, crushers
Yes
The machinery to be used for
construction is of high standard
and adhere to international
standard. These standards itself
take care of noise
control/vibration control and air
emission control. Hence,
insignificant impacts due to
construction machinery are
envisaged. Apart from this, the
construction activities is being
restricted to day time only. All the
machinery is being of highest
standard of reputed make and will
comply with standard.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 14
6.2
From industrial or similar
processes
No
No industrial processes is being
carried out in the proposed
project except running of various
construction equipments/
machinery. Proper maintenance of
machineries will reduce the
generation of noise and vibration.
All the workers are equipped with
PPE’s during construction phase.
6.3
From construction or
demolition
Yes
Due to various construction
activities, there are short-term
noise impacts in the immediate
vicinity of the project site. The
construction activities will include
the following noise generating
activities:
Concreting, mixing &
operation of DG sets.
Construction plant and heavy
vehicle movement.
6.4 From blasting or piling
No No blasting or mechanized piling is
being done.
6.5
From construction or
operational traffic Yes
Some noise is being generated
from vehicular movement in the
construction and operational
phase but that is being mitigated
with landscape development.
6.6
From lighting or cooling
systems No
No significant noise impact will
result from lighting or cooling
systems.
6.7
From any other sources
No
There is being no other sources for
noise & vibration generation
except the mentioned above.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 15
7. Risks of contamination of land or water from releases of pollutants into the
ground of into sewers, surface waters, groundwater, coastal waters or the sea:
S.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/ rates, wherever
possible) with source of
information data
7.1 From handling, storage, use or
spillage of hazardous materials
No There is being no handling, storage,
use or spillage of any type of
hazardous material.
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and
place of discharge)
No There will be no discharge of
untreated sewage on land or into
water bodies. Adequate treatment
of sewage will be carried out in STP
having the capacity of 186 KLD
within the project premises.
Recycled water will be re-used for
flushing and landscaping and rest
of the recycled water will be given
to nearby construction sites for
construction purpose only.
7.3 By deposition of pollutants
emitted to air into the land or
into water
No There will be no deposition of
pollutants emitted to air into the
land or into water by any source.
7.4 From any other sources No No other sources are involved
except the mentioned above.
7.5 Is there a risk of long term
build up of pollutants in the
environment from these
sources?
No
There is being no such risk in the
coming future.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 16
8. Risk of accidents during construction or operation of the Project, which could
affect human health or the environment
S. No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/ rates, wherever
possible) with source of information
data
8.1 From explosions, spillages,
fires etc from storage,
handling, use or
production of hazardous
substances
Yes This is a Residential Group Housing
project and does not involve major
hazardous construction activity.
Hence chances of explosions,
spillages, fires etc. are minimal.
During construction, suitable personal
protective equipment is being
provided to all construction workers
as required under the health & safety
norms. Awareness & Training about
safety norms is being provided to all
the supervisor and construction
workers involved in construction
activities.
To deal with any fire related accident,
fire fighting facility of single handed
hydrant valve, long hose reel, and
portable fire extinguisher shall be
provided.
8.2 From any other causes No No other causes are involved except
the mentioned above.
8.3 Could the project be
affected by natural
disasters causing
environmental damage
(e.g. floods, earthquakes,
landslides, cloudburst
etc)?
No The project falls under seismic active
Zone IV according to the Indian
Standard Seismic Zoning Map.
Suitable seismic coefficient is being
adopted in horizontal and vertical
direction respectively, while designing
the structure.
There is no possibility of flood as per
records available on the proposed
project site.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 17
9. Factors which should be considered (such as consequential development) which
could lead to environmental effects or the potential for cumulative impacts with
other existing or planned activities in the locality.
S.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/ rates, wherever
possible) with source of
information data
9.1 Lead to development of
supporting facilities, ancillary
development or development
stimulated by the project
which could have impact on
the environment e.g.
Supporting
infrastructure (roads,
power supply, waster
or wastewater
treatment, etc.)
housing development
extractive industries
supply industries
other
Yes
Yes
Yes
No
No
No
The proposed project is for
Residential use; it may lead to
development of supporting services
and infrastructure in and around
the area.
The project will have positive
impact on the ancillary
infrastructure like road, markets,
public health, amenities,
conveyance facilities etc.
The project is proposed Residential
only.
Not Applicable
Not Applicable
Not Applicable
9.2 Lead to after-use of the site,
which could have an impact
on the environment
No Not Anticipated
9.3 Set a precedent for later
developments No Not Applicable
9.4 Have cumulative effects due
to proximity to other existing
or planned projects with
similar effects
No Not Applicable
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 18
(III) ENVIRONMENTAL SENSITIVITY
S.N
o.
Information/Checklist
confirmation Name/ Identity
Aerial distance (within
15 km.)Proposed
project location
boundary
1. Areas protected under
international conventions,
national or local legislation
for their ecological,
landscape, cultural or other
related value.
No
There is no area under
international
conventions, national
or local legislation for
their ecological,
landscape, cultural or
other related value.
2. Areas which are important
or sensitive for ecological
reasons – Wetlands,
watercourses or other
water bodies, coastal zone,
biospheres, mountains &
forests
No
There is no area which
is important or
sensitive for ecological
reasons.
3. Areas used by protected,
important or sensitive
species of flora or fauna for
breeding, nesting, foraging,
resting, over wintering,
migration
No
There is no ecologically
sensitive species of
flora or fauna found in
the study area.
4. Inland, coastal, marine or
underground waters. Not Applicable Not Applicable
5. State, National boundaries
No
No State or
International Boundary
falls within the 15 km
radius of the project
site.
6. Routes or facilities used by
the public for access to
recreation or other tourist,
pilgrim areas.
Gurgaon Faridabad
Road
Approx 0.1 km in S
direction
7. Defense installations Not Applicable Not Applicable
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 19
8. Densely populated or built-
up area Gurgaon City
Approximately 12 km
towards West
9. Areas occupied by sensitive
manmade land uses
(hospitals, schools, places of
worship, community
facilities)
S.
No. Particulars Distance Direction
Hospitals
1.
Arunodaya Eye
Hospital Sector
55 Gurgaon
4.09 km W
2. Alchemist
Hospital 3.36 km W
Temples
1.
Hanuman
Mandir Village
Gwal Pahari
0.9 km E
2. Shiv Temple
Mandi 0.94 km E
Banks
1. HDFC Bank Sec
53 Gurgaon
3.5 km W
2. Axis bank 3.9 km W
School/ College
1. Pathways World
School
1.38 km SW
2. Gurgaon Public
School
3.68 km W
10. Areas containing important,
high quality or scarce
resources (ground water
resources, surface
resources, forestry,
agriculture, fisheries,
tourism, minerals)
Yes
Ground-water
resources in the study
area are depleting at
very fast rate and
declared as scarce
resources.
11. Areas already subjected to
pollution or environmental
damage. (Those where
existing legal environmental
standards are exceeded)
No
There is no area which
is subjected to
pollution or
environmental
damage. All
parameters of Air,
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM I
Prepared by: Vardan EnviroNet, Gurgaon Page 20
Water and Noise etc. is
being maintained
within permissible limit
specified by SPCB/CPCB
with proper mitigation
measures.
12. Areas susceptible to natural
hazard which could cause
the project to present
environmental problems
(earthquakes, subsidence,
landslides, erosion, flooding
or extreme or adverse
climatic conditions)
Yes
The site falls under the
zone IV as per the
Seismic Zone Map of
India.
There is no possibility
of flood as per records
available on the
proposed project site.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 21
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed Environmental
Management Plan & Monitoring Programmed).
SECTION 1- LAND ENVIRONMENT:
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get significantly altered from the project that is consistent
with the surroundings? (Land use must conform to the approved Master Plan/Development
Plan of the area. Change of land use, if any and the statutory approval from the competent
authority are submitted). Attach Maps of (i) site location, (ii) surrounding features of the site
(within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not
available attach only conceptual plans.
No
The project site lies in Residential zone as per the Gurgaon-Master Urban complex Plan-2031. It
is thus anticipated that the construction activities of the proposed project would not have an
adverse effect on the land use activities in the project area. The development of the green belt
and other landscape would enhance the visual aesthetics of the area.
Location Map, Map showing surrounding features of the site within 2 Km and Contour Map
indicating levels and contours are enclosed in the report.
CONNECTIVITY
S. NO. DETAIL DISTANCE DIRECTION
1. Nearest Highway (NH-8) 8.8 Km West
2. Gurgaon Railway Station 14.5 Km West
3. Indira Gandhi International Airport 13 Km North-West
1.2 List out all the major project requirements in terms of the land area, built up area,
water consumption, power requirement, connectivity, community facilities, parking
needs etc.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 22
LAND REQUIREMENT
Table 1: Area Statement
S. No. Particulars Area ( m2)
1. Project Name
Extension of Environment Clearance
Group Housing Colony
M/s Jasmine Buildmart Pvt. Ltd.
2. Activity in the complex Retail area, Residential Dwelling Units and EWS
Units
3. Total Plot Area 49851.931 m2
(12.3187 Acres)
4. Permissible FAR @ 175 80902.5 m2
5. Achieved FAR @ 173.542 80228.47 m2
6. Permissible Ground Coverage
@ 25 % 11557.50 m
2
7. Achieved Ground Coverage 1891.911 m2
8. Built-up Area Detail (FAR +
Non-FAR) 89457.172 m
2
9.
Parking Required 312 ECS
Proposed Surface Parking 80 ECS
Total Parking Proposed
316 ECS Proposed Basement Parking 149 ECS
Proposed Stilt Parking 87 ECS
10. Power Requirement & Sources
6000 KW
Source: Dakshin Haryana Bijli Vitran Nigam
(DHBVN)
11. No. of DG Sets 4 Nos. of DG Sets having Total Capacity of 5000
KVA (1 x 1500 KVA + 2 x 1250 KVA + 1000 KVA)
12. Water requirement & Sources
Total Water Requirement: 333 KLD
Fresh Water Requirement: 216 KLD
Treated/Recycled Water Requirement: 116.6 KLD
Source: HUDA
13. Sewage Treatment & Disposal
STP capacity :186 KLD
Sewage discharge: Total 140 KLD of water will be
obtained after the recycling of wastewater out of
which 64 KLD shall be utilized for the purpose of
flushing, 38 KLD for landscape development, 10
KLD for DG Cooling and 28 KLD will be supplied to
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 23
nearby construction sites for construction
pupose.
14. Estimated Population Total: 2926 Persons including visitors & other
staff
15. Green Area Required @ 15 % 6934.5 m
2
Proposed Green Area @16.48
% 2830.00 m
2
16. Cost of the project Rs. 118.18 Crores (Approx.)
*FAR = Floor Area Ratio
1.3 What are the likely impacts of the activity on the existing facilities adjacent to the
site? (Such as open spaces, community facilities, details of the existing land use and
disturbance to the local ecology).
The project being a well planned activity will result in organized open spaces and green areas.
About 7621 m2 of the area is earmarked for landscaping. The project will have an overall
positive impact on the existing land use and will not cause any disturbance to the local ecology.
Hence, proposed activity shall have no impact on surroundings.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Detail of soil type slope analysis, vulnerability to subsidence, seismicity etc may
be given).
There shall be no land disturbance resulting in erosion, subsidence and instability as it is a flat
land. The project site falls under the zone IV i.e., High Damage Risk Zone (MSK-VIII) as per
Earthquake Hazard Map of Haryana. The project will be earthquake resistant taking into
account the latest provisions of Indian Standards Codes.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 24
Source: Maps of India
Figure-2: Earthquake Hazard Map of Haryana showing Project Site
1.5 Will the proposal involve alteration of natural drainage system? (Give details on a
contour map showing the natural drainage near the project site).
The project does not intersect any natural drainage route. No perennial or non-perennial
drainage system is found to exist in the project area or being obstructed by the project. The
surroundings comprise an urbanized stretch. Well planned storm water drainage has been
designed to take care of internal storm water drainage. Thus, no impact on the natural drainage
system is anticipated.
1.6 What are the quantities of earthwork involved in the construction activity-cutting,
filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc?)
PROJECT SITE
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 25
The only excavation work is involved in the proposed project for establishing the foundation &
Basement of Group Housing Colony. The filling works will be done by the excavated material
and no extra material will be used. All the topsoil excavated from construction activities has
been stored separately and used in landscape development within the project site. Hence, the
need for movement of soil to and from the site is not required.
1.7 Give details regarding water supply, waste handling etc. during the construction
period.
Water requirement during construction phase is being met from STP treated water.
Waste handling during the construction phase is being done by the site contractor whose
responsibility lies with collection and storage of construction and demolition waste
generated on the site. All construction wastes generated during construction will be used
within the site itself for filling the floors, roads, aggregate for mortar etc. to the extent
feasible. Remaining will be sent to the agency for proper disposal.
1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the activity).
No. The site area is a flat land and the surroundings are characterized by an urbanized stretch.
No low lying areas or wetlands are found in the vicinity of the project site.
1.9 Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the
construction labor and the means of disposal).
No significant health hazard is associated with the proposed construction.
During construction period, source of fugitive dust generation is material handling and
vehicular movement. Impact due to fugitive dust emission is negligible as water sprinklers is
being used to suppress fugitive dust emission as and when generate. However, the impacts is
being confined to laborers/ workers particularly with regard to occupational exposure.
Proper Personal Protective Equipments are provided to the workers working in the potential
areas (e.g. masks, ear plugs, Gloves and Safety shoes etc.).
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 26
Careful design, planning and good site management would minimize waste of materials such
as concrete, mortars and cement grouts. Construction wastes are segregated as much as
possible at site itself to increase the feasibility of recycling concrete and masonry as filling
material and steel pieces as saleable scrap. Litter disposal and collection points are
established around the work sites. Empty packaging materials, drums, glass, tin, paper,
plastic, pet bottles, wood, thermocol and other packaging materials, etc is being disposed
through recyclers. The construction spoils is being temporarily stored at designated dumpsite
located inside the site premises. Later on these wastes will be used for land filling / leveling
work within the site premises. An estimate of the average composition of waste generated
from the onsite construction activities given in Table-2.
Table-2: Waste Composition - During Construction Phase
S. No. Constituents Percentage Composition (%)
1 Soil, Sand and Gravel 35.80
2 Brick and Masonry 30.66
3 Concrete 23.24
4 Metal 5.10
5 Bitumen 2.10
6 Wood 2.10
7 Other 1.00
Total 100.00
“ource: TIFAC Report Utilizatio of Waste fro Co structio I dustry,
SECTION-2 WATER REQUIREMENT
2.1 Give the total quantity of water requirement for the proposed project with the breakup of
requirement for various uses, how will the water requirement met? State the sources &
quantities and furnish a water balance statement.
The water will be supplied through HUDA. Total water requirement of the project will be
approximately 226 KLD, out of which 114 KLD is fresh water requirement and 112 KLD is
recycled/ treated water. The Water balance diagram is showing given below in Figure-4.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 27
Figure-4: Water Balance Diagram
2.2 What is the capacity (dependable flow or yield) of proposed sources of water?
Water requirement will be fulfilled by HUDA water supply.
2.3 What is the quality of water required, in case, the supply is not from a municipal
source? (Provide physical, chemical, Biological characteristics with class of water quality).
Not Applicable as the water requirement will be fulfilled from HUDA.
To nearby construction sites by tanker (28 KLD)
Total Water Requirement (226 KLD)
Fresh Water Requirement (114 KLD)
Recycled/Treated Water (112 KLD)
@ 100%
Wastewater generated (91.2 KLD)
Domestic Water Requirement (114 KLD) Flushing (64 KLD)
Total wastewater generated (155 KLD)
STP Capacity (186 KLD)
@ 90% of wastewater generated
Recycled/Treated water (140 KLD)
Horticulture (38 KLD) DG Cooling (10 KLD)
Wastewater generated (64 KLD)
Wastewater generated (NIL)
Wastewater generated (NIL)
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 28
2.4 How much of water requirement can be met from the recycling of treated
wastewater? (Give the details of quantities, sources and usage)
The water requirement for flushing and landscaping will be met through treated water from
Sewage Treatment Plant (STP) of 186 KLD.
2.5 Will there be diversion of water from other users? (Please assess the impacts of the
project on other existing uses and quantities of consumption).
No, there will be no diversion of water from other users.
2.6 What is the incremental pollution load from wastewater generated from the activity?
(Give details of the quantities and composition of wastewater generated from the activity)
Approximately 155 KLD of wastewater will be generated during the operational phase of the
proposed project. This wastewater generated will be treated in well designed sewage treatment
plant. Dual plumbing system will be provided for reuse of treated water in flushing and
landscaping. Hence, no incremental pollution load is been expected from wastewater generated
from the activity.
2.7 Give details of the water requirements met from water harvesting? Furnish details of
the facilities created.
Rainwater harvesting is proposed as a water conservation tool. Total 12 nos. of rain water
harvesting pits will be provided the storm water drainage within the project premises at selected
locations, which will catch the maximum run-off from the area. It is self-sufficient to avoid any
collection/stagnation and flooding of water.
1) Since the existing topography is congenial to surface disposal, a network of storm water pipe
drains is planned adjacent to roads. All building roof water will be brought down through rain
water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular
intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement storm
water storage tank. This water will be pumped out to the nearest external storm water drain.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 29
4) Peak Hourly rainfall of 45 mm/ hr shall be considered for designing the storm water drainage
system. Rain water harvesting has been catered to and designed as per the guidelines of
CGWA. At the bottom of the recharge well, a filter media is provided to avoid choking of the
recharge bore. Design specifications of the rain water harvesting plan are as follows:
Catchments/ roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags
and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is
flushed off.
No sewage or wastewater would be admitted into the system.
2.8 What would be the impact of the land use changes occurring due to the project on the
runoff characteristics (quantitative as well as qualitative) of the area in the post construction
phase on a long term basis? Would it aggravate the problems of flooding or water logging in
any way?
The project will include paved areas and thus the runoff from the plot is expected to increase
due to reduced infiltration. However, the increased runoff will not cause flooding or water
logging as a well designed storm water drainage will be provided. The runoff will finally be
collected into rainwater harvesting pits for groundwater recharging. The Desilting chamber with
oil & grease trap has been proposed to improve the quality of the runoff.
2.9 What are the impacts of the proposal on the ground water? (will there be tapping of
ground water; give the details of ground water table, recharging capacity and approvals
obtained from competent authority, if any)
Water demand will be fulfilled from HUDA. No adverse impact is expected on this account as
extensive rainwater harvesting will be implemented across the project site. To reduce the
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 30
freshwater demand and hence the groundwater stress, recycled wastewater will be used for
landscaping and flushing.
2.10 What precautions/ measures have been to check the surface run-off, as well as
uncontrolled flow of water into any water body?
The following management measures are suggested to protect the water quality are:
Avoid excavation during monsoon season.
Care would be taken to avoid soil erosion.
Community toilets shall be constructed on the site during construction phase and the
wastewater will be channelized to the septic tank in order to prevent wastewater from
entering the water bodies.
Any area with loose debris/soil within the site shall be fully planted by local plant species.
To prevent surface and ground water contamination by oil/grease, leak proof containers
would be used for storage and transportation of oil/grease. The floors of oil/grease handling
area would be kept effectively impervious.
Collection and settling in the storm water, prohibition of equipment wash downs, and
prevention of soil loss and toxic release from the construction site will be adhered to
minimize water pollution.
2.11 How is the storm water from within the site managed? (State the provisions made to
avoid flooding of the area, details of the drainage facilities provided along with a site layout
indication contour levels).
Most of the storm water produced on site will be harvested for ground water recharge. Thus
proper management of this resource is a must to ensure that it is free of contamination. A
detailed Storm Water Management Plan will be developed which will consider the sources of
storm water. The plan will incorporate best management practices which will include the
following:
Regular inspection and cleaning of storm drains.
Installation of clarifiers or Oil/ Water separators/traps system of adequate capacity
around parking areas and garages as per requirement.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 31
Avoid application of pesticides and herbicides before wet season.
Conducting routine inspections to ensure cleanliness.
Preparation of spill response plans, particularly for fuel and oil storage areas.
Provision of silt traps in storm water drains.
Good housekeeping in the above areas.
2.12 Will the deployment of construction laborers particularly in the peak period lead to
unsanitary conditions around the project site (Justify with proper explanation).
No, mostly local laborers are employed during the construction phase and thus negligible
quantities of wastes is being generated. Mobile toilets will be provided and the wastewater
generated will be collected in septic tanks.
2.13 What on-site facilities are provided for the collection, treatment & safe disposal of
sewage? (Give details of the quantities of wastewater generation, treatment capacities with
technology & facilities for recycling and disposal).
It is expected that the project will generate approx. 155 KLD of waste water. The wastewater
will be treated in the STP provided within the premises generating 140 of recoverable/
recycled water will be used in flushing, DG cooling and horticulture.
Separate garbage bins with different colours will be provided for the management of bio-
degradable and non-bio-degradable waste.
2.14 Give details of dual plumbing system if treated waste used for flushing of toilets or
any other use.
Total water requirement of project will be 226 KLD. The fresh water required will be 114 KLD
and treated water will be 112 KLD. During operation phase, 155 KLD of waste water will be
generated which will be treated in STP having the capacity of 186 KLD. Treated water obtained
from STP shall be 140 KLD, out of which 64 KLD shall be utilized for the purpose of flushing, 38
KLD use in green area development and 10 KLD use in DG cooling and rest 28 KLD of water will
be supplied to nearby construction sites for construction purpose.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 32
SECTION-3: VEGETATION
3.1 Is there any threat of the project to the biodiversity? (Give a description of the local
ecosystem with its unique features, if any).
No ecologically sensitive area falls within the project site. Hence, no ecological/ biological
threat has been anticipated.
3.2 Will the construction involve extensive clearing or modification of vegetation?
(Provide a detailed account of the trees & vegetation affected by the project)
The project does not involve any significant vegetation clearing. It was a barren land. The
project will develop landscape by planting native plant species to enhance the aesthetic value
of the region and also provide an excellent habitat for various faunal groups.
3.3 What are the measures to be taken to minimize the likely impacts on important site –
features (Give details of proposal for tree plantation, landscaping creation of water bodies
etc along with a layout plan to an appropriate scale?)
Tree plantation will be done along the internal parks and lawns. The landscape area of the
project is 7621 m2. Plantation would be of large leaf trees that provide adequate shade and are
evergreen to semi-evergreen.
SECTION 4: FAUNA
4.1 Is there likely to be any displacement of fauna both terrestrial and aquatic or creation
of barriers for their movement? Provide the details.
No, the existing land use around the site is urban and does not provide a habitat for wild
species. The tree plantation will provide an excellent habitat for the native fauna.
4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.
The project will not have any direct or indirect impacts on the avifauna of the area. However,
planting of trees bearing fruits will be an attraction to the local bird population.
4.3 Prescribe measures such as corridors, fish ladders etc. to mitigate adverse impacts on
fauna.
No direct or indirect impact on fauna is envisaged.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 33
SECTION 5: AIR ENVIRONMENT
5.1 Will the project increase atmospheric concentration of gases & result in heat islands?
(Give details of background air quality levels with predicted values based on dispersion
models taking into account the increased traffic generation as a result of the construction).
Ambient air monitoring was carried out at the project site during the environmental
assessment.
During the post construction phase, cars, scooter/motorcycle will be owned by the visitors &
staff of the Group Housing Colony. Vehicular emissions will be the major source of air pollution
in addition to DG set. Quantum and dispersion of pollutants from vehicular emission will
depend upon the following:
Volume of traffic on the roads,
Meteorological conditions.
Emission sources
From vehicular emissions, PM, NO2 and CO is pollutants of primary concern. The dispersion of
vehicular emission would be confined within 100 m from the road and concentration will
decrease with increase in distance from road. It is anticipated that the contribution of vehicular
emission in ambient air quality will be marginal but well within the stipulated National Ambient.
Dispersion will be faster at higher wind speed.
Mitigation Measures: The proposed project will develop suitable landscape along with
prominent tree plantation inside the premises of the project site and along the internal road,
which will work as a barrier for the movement of pollutants and help in pollution control.
5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous
gases? Give details in relation to all the meteorological parameters.
Ambient air monitoring was done on site and all values were found within the NAAQS for
commercial land use. During operational phase of the project, there will be increase in
atmospheric concentration of gases and particulate matter due to running of DG sets. Total 3
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 34
Nos. of DG sets of total capacity 5000 KVA (1×1500 + 2×500 + 1×1000 KVA) will be provided as
power back up during power failure. This will cause emissions of PM, SO2, NO2 and CO.
However, the D.G. sets will be functional only during power failure and ultra low sulphur diesel
will be used. Adequate stack height for D.G. sets will be provided as per the stipulated
guidelines of Central Pollution Control Board (CPCB) to facilitate natural dispersion of exhaust
gases.
5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the
present level of transport infrastructure and measures for improvement including the traffic
management at the entry and exit to the project site.
Adequate provision will be kept for car/ vehicles parking at the project. There shall also be
adequate provision for visitors parking so as not to disturb the traffic and allow smooth
movement at the site.
5.4 Provide details of the movement patterns with internal roads, bicycle tracks,
pedestrian pathways, footpaths etc, with areas under each category.
Internal roads of 6-8 m width, footpaths/ pedestrian pathways have been well planned for the
project.
5.5 Will there be significant increase in traffic noise & vibrations? Give details of the
sources and the measures for mitigation of the above.
No significant impact of noise has been anticipated within and outside of the project site due to
provision of wide roads for smooth flow of traffic and avenue plantation along the roads.
5.6 What will be the impact of D.G. sets and other equipment on noise levels and
vibration in ambient air quality around the project site? Provide details.
During operational phase of the project, vehicular movement and operation of DG sets will be
the major sources of noise pollution. But both these activities- DG set and vehicular movement
will not have any significant impact on the people residing in the area. Since DG set will not be
operational continuously and moreover it will be placed away from populated area and will be
enclosed with suitable enclosures. Hence, no or minimal impact will be anticipated due to DG
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 35
set and vehicular emission. It is envisaged that the movement of the motor vehicles will be
restricted to designated carriageways only.
SECTION-6: AESTHETICS
6.1 Will the construction in any way result in the obstruction of a view, scenic amenity or
landscapes? Are these considerations taken into account by the proponents?
The construction of proposed project is well planned. Thus, no obstruction of view or scenic
beauty or landscape is anticipated. Furthermore, the construction is being planned in such a
way that the organized open spaces and landscaped areas will render the plot aesthetically
appealing.
6.2 Will there be any adverse impacts from new constructions on the existing structures?
What are the considerations taken into account?
No impacts anticipated.
6.3. Whether there are any local considerations of urban form & urban design
influencing the design criteria? They may be explicitly spelt out.
The project will strictly follow the Area Building Regulation Norms of NBC. All norms on Ground
Coverage, FAR, Height, Setbacks, Fire Safety Requirements, Structural Design and other
parameters will be strictly adhered to.
6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any
other significant features in the vicinity of the site have been considered?
No anthropological or archaeological sites or artifacts are found near the site area.
SECTION-7: SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any changes to the demographic structure of local
population? Provide the details.
The project is situated in the Residential zone and hence there will be no change in
demographic structure.
Construction phase: Since local laborers are being engaged during construction phase,
alteration to the existing demographic profile of the area is not anticipated.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 36
Operation phase: The changing demography in the area is another impact that needs attention.
The project will mainly lead to spatial redistribution of local population and hence no
considerable influx of population is envisaged owing to the project.
7.2 Give details of the existing social infrastructure around the project.
The area around the project is surrounded by local land area. However all sorts of social
infrastructure like transportation facilities, water supply & sanitation facilities, communication
facilities, educational institutes, hospital, markets, banks, cultural amenities etc. already exist in
Gurgaon.
7.3 Will the project cause adverse effects on local communities, disturbance to sacred
sites or other cultural values? What are the safeguards?
Construction phase: There are no religious sites or archeological monuments of historical
significance in or near the project site. Hence, no adverse impact in this regard is anticipated.
Rather, this phase will generate jobs that relate to unskilled, semi skilled as well as skilled
labour category. Few supervisory positions will also open up, for which local candidates will be
considered based on merit.
Operation phase: The project will provide state-of-the-art facility in the area, thereby improving
the quality of life. A Group Housing Colony of such scale will also boost the local economy.
SECTION-8: BUILDING MATERIALS
8.1 May involve the use of building materials with high embodied energy. Are the
construction materials produced with energy efficient processes? (Give details of energy
conservation measures in the selection of building materials and their energy efficiency)
For the purpose of paved path, sun dried pavers will be used instead of baked pavers as they are
manufactured through energy efficient processes.
8.2 Transport and handling of materials during construction may results in pollution, noise
and public nuisance. What measures are taken to minimize the impacts?
Mitigation Measures for Air Pollution during Construction Stage:
• Construction materials will be suitably covered with tarpaulin cover etc during
transportation.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 37
• Water sprinkling is being done on haul roads where dust generation is anticipated.
• Raw material storage and handling yard is being enclosed from all sides.
• To minimize the occupational health hazard, proper personal protective gears i.e. mask are
be provided to the workers working in the dust prone areas.
Mitigation Measures for Noise Pollution during Construction Stage:
• Administrative as well as engineering control of noise is being implemented.
• Isolation of noise generation sources and temporal differentiation of noise generating
acti ities ill e sure i i u oise at recei er’s e d.
• To prevent any occupational hazard, earmuff / earplug is being given to the workers
working around construction plant & machinery emitting high noise levels.
• Use of such plant or machinery shall not be allowed during night time. Careful planning of
machinery operation and scheduling of operations shall be done to minimise such impact.
8.3 Are recycled materials used in roads and structures? State the extent of savings
achieved?
Yes, construction waste/ debris; generated during construction is being utilized for road
construction. Construction waste/ debris will be used as fillers in base and sub-base of the
carriageway, footpaths pavements or pedestrian way, as needed.
8.4 Give detail of the methods of collection, segregation & disposal of the garbage
generated during the operation phases of the project.
The solid waste of the project will be segregated into biodegradable waste and non-
biodegradable. Biodegradable waste and non biodegradable waste will be collected in separate
bins. Biodegradable waste shall be disposed off as per MSW Rules 2000 & amendment 2008.
The recyclable wastes will be sent off to the government authorized recyclers. Proper
guidelines for segregation, collection and storage will be prepared as per Municipal Solid
Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 38
SECTION-9: ENERGY CONSERVATION
9.1 Give details of the power requirements, source and supply, backup source etc. What is
the energy consumption assumed per square foot of built-up area? How have you tried to
minimize energy consumption?
The details of power requirement, sources, and backup power requirement are given in the
Table below:
Power Requirement, Sources and Backup Plan
Power Requirement 6000 KW
Sources of Power Dakshin Haryana Bijli Vitran Nigam (DHBVN)
Backup power supply arrangement 4 Nos. of DG sets of total capacity 5000 KVA (1 × 1500
KVA + 2 × 500 KVA + 1 × 1000 KVA)
9.2 What type and capacity of power backup do you plan to provide?
Power backup will be provided by 4 Nos. of DG sets of total capacity 5000 KVA (1 × 1500 KVA +
2 × 500 KVA + 1 × 1000 KVA). The DG sets will be operated during power failure only.
9.3 What are the characteristics of the glass you plan to use? Provide specifications of its
characteristics related to both short wave and long wave radiation?
Suitable thickness of glass will be adopted depending upon the panel size to keep the U value as
per the requirement of ECBC.
9.4 What passive solar architectural features are being used in the building? Illustrate the
applications made in the project.
Passive solar design refers the use of the su ’s e ergy for heati g a d cooli g of li i g spaces.
Pergolas, projections, façade elements, metal louvers will be provided for sun shading to
reduce the heat influx into the building and thus reduce the air conditioning loads.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 39
9.5 Does the layout of street & building maximize the potential for solar energy devices?
Have you considered the use of street lighting, emergency lighting and solar hot water
systems for use in the building complex? Substantiate with details.
Layout of buildings has been done as per the sun path analysis so that the design cuts off direct
radiations of critical hours which are specific to the orientation. Solar energy will be harnessed
through solar street lights etc.
9.6 Is the shading effectively used to reduce cooling/heating lands? What principles have
been used to maximize the shading of walls on the East and the West and the Roof? How
much energy saving has been effected?
Pergolas, projection, façade elements, metal louvers will be provided to reduce cooling loads.
Green area and open areas will be so spaced that a reduction in temperature is achieved.
9.7 Do the structures use energy-efficient space conditioning, lightening and mechanical
systems? Provide technical details. Provide details of the transformers and motor efficiencies,
lightening intensity and air conditioning load assumption? Are you using CFC and HCFC free
chillers? Provide specifications.
Yes. The walls and rooms will be insulated such that air conditioning load is reduced. Well
designed building structures will allow natural light to enter. Measures prescribed in Energy
Conservation Building Code 2007 will be adopted to reduce the heat influx by walls, roofs and
openings. Only prescribed quality of glasses will be used.
9.8 What are the likely effects of the building activity in altering the micro-climates?
Provide a self assessment on likely impacts of the construction on creation of heat island &
inversion effects?
Heat emissions from the construction may be from the following sources:
Heat absorbed from the paved and concrete structures
Heat generated from equipment/appliances
Heat increase due to population increase
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 40
However, the heat generated will not be significant and will be dissipated in the greens
and open areas provided within the project area.
9.9 What are the thermal characteristics of the building envelope? (a) Roof (b) external
walls and (c) fenestration? Give details of the material used and the U value or the R values of
the individual components.
The roof tops of the buildings will be planned with puffing/ bricks for water proofing and
thermal insulation.
External wall-external opening will have regular door windows with slightly tinted glass. Regular
walls have some cladding/ fixture paints.
What precautions & safety measures are against fire hazards? Furnish details of emergency
plans.
Firefighting measures shall be adopted as per the guidelines of NBC. In addition, 10 kg fire
extinguishers will be provided for class A, B, and C fires. CO2 extinguishers will also be provided.
9.11 If you are using glass as wall materials, provide details and specifications including
emissivity and thermal characteristics.
The project being a Group Housing Colony project will not involve use of glass as wall material.
All fenestration with U-factors, SHGC, or visible light transmittance determined, certified and
labeled in accordance with ISO 15099 shall be adopted.
9.12 What is the rate of air infiltration in to the building? Provide details of how you are
mitigating the effects of infiltration.
The project will not be centrally air conditioned and hence there will be provision for ample
natural ventilation.
9.13 To what extent the non–conventional energy technologies are utilized in the overall
energy consumption? Provide details of the renewable energy technologies used.
Solar energy will be harnessed through solar street lights etc. Green area is provided along with
tree plantation which will result in natural air cooling and will reduce the load on conventional
energy sources.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 41
SECTION-10: ENVIRONMENT MANAGEMENT PLAN
10.1 The Environment Management Plan (EMP) would consist of all mitigation measures for
each component of the environment due to the activities increased during the construction,
operation and the entire life cycle to minimize adverse environmental impacts resulting from
the activities of the project. It would also delineate the environmental monitoring plan for
compliance of various environmental regulations. It will state the steps to be taken in case of
emergency such as accidents at the sites including fire.
A detailed environmental management plan is presented in Table-6 & 7 to mitigate all the
identified environmental impacts that are found to be significant.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 42
Table-6: Environmental Management Plan – Construction Phase
S. No Environmental Impacts Mitigation Measures Implementing
Agency
Monitoring
Agency
(i) Air pollution due to emissions
from construction machinery
and movement of vehicles.
a) Vehicles transporting construction materials prone to fugitive
dust emissions should be covered.
b) Trucks carrying sand should be provided with tarpaulin sheets to
cover the bed and sides of the trucks.
c) Idling of delivery trucks or other equipment should not be
permitted during loading and unloading.
d) All construction vehicles should comply with air emission
standards and be maintained properly.
e) Development of alternative access routes to the site by passing
the commercial areas to avoid air pollution.
Building
Contractor
Project
proponent
(ii) Air pollution, noise and safety
hazard due to movement of
construction vehicles through
internal roads of project
premises.
a) Improvement of road surface to standards adequate to
withstand movement of heavy construction vehicles
b) Installing appropriate signage and deploying flagmen during
peak traffic period to regulate the movement of traffic
Building
Contractor
Project
proponent
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 43
(iii) Noise pollution due to
operation of construction
machinery at the site.
a) Construction contracts should specify that the construction
equipment should meet the noise and air emission levels as per
EPA Rules, 1986.
b) Generator sets should be provided with noise shields around
them.
c) Vehicles used for transportation of construction material should
be well maintained.
d) The workers operating high noise machinery or operating near it
should be provided with ear plugs
e) The high noise generating stationary machinery should be
located at the southern or central portion of the site
Building
Contractor
Project
proponent
(iv) Impact on community water
resources (quality).
a) All waste water discharges from construction site will be
received in septic tanks, adequate capacity and soak pits.
b) Oil handling and storage area will be surfaced and provided with
catch pit to intercept any accidental spillages.
Building
Contractor
Project
proponent
(v) Sanitation and healthcare at
workers camp
a) The contractor shall install adequate lavatories; soak pits and
baths at the construction camp to cater to the requirements of
the workers.
b) The construction camp should be located on the south-west
Building
Contractor
Project
proponent
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 44
corner of the site
c) The contractor shall build septic tanks with adequate capacity at
the workers colony and at construction yard.
d) All organic waste shall be disposed off according to Municipal
Solid Waste (Management & Handling) Rules 2000 &
Amendment 2008.
e) Quarterly health check-ups of construction workers should be
organized at workers colony.
f) Adequate provision of water supply and fuel for cooking should
be made at workers colony.
(vii) Improvement of Access Roads
to the site
a) Improvement and widening of the existing access roads.
b) Establishing road connection
c) Relocation of the encroachments in temporary shelters if the
approach road along the boundary of the project site connecting
the road is used for transportation of construction materials to
the site.
Building
Contractor
Project
proponent
(viii) Impact on Micro Climate a) On-site planting of shading trees
b) Planting of numbers of trees, of species suitable to the semi arid
climatic condition and alluvial soil of the project site along the
Building
Contractor
Project
proponent
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 45
roads and on the designated open spaces to ensure the
improvement of micro-climatic condition of the project site.
Table-7: Environmental Management Plan - Operational Phase
S. No. Environmental
Impacts Mitigation Measures
Organizational /
Monitoring
Arrangements
Training
Requirements
Implementing
Arrangements
(i) Unsanitary conditions
in the rehabilitation
site due to
inadequate
management of solid
waste
1. Provision for door–to-
door collection of
waste from the
households and
arrangement for its
regular removal from
the site
2. Participation of
community groups in
the collection and
disposal process
Formation of housing
society by involving
community voluntary
groups and creation of a
corpus funds that could
be utilized for the solid
waste management in
the project site.
1. Training and
awareness
programs with the
community
members.
2. Training for the
segregation of
waste.
Apartment Staffs would
monitor the solid waste
collection and will be
responsible for the
disposal of the waste.
Day to day functioning of
waste collection and
management of fund
would be the
responsibility of the
housing society
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 46
(ii) Maintenance of
adequate quality of
life standard in the
resettlement site
1. Provision of rainwater
infiltration through
shallow wells at the
site to augment
ground water
resources
Association between the
community group,
housing society and
project proponent for
the maintenance and
operation of the system
Training and
awareness program
with the community
members for the
proper maintenance of
the facility
Apartment Staff through
the community group
2. Provision for regular
potable water supply
to meet the drinking
water needs of the
visitors & staff
population
project proponent
forming a task force with
the Local Municipal
Corporation to monitor
the consistency in supply
of potable water
Awareness program
with the visitors &
staff population for
the conservation of
potable water
3. Provision for adequate
maintenance of assets
to ensure their
smooth functioning
Association between the
community group,
housing society and
project proponent for
the maintenance and
operation of the system
Training for the
community groups on
the maintenance
needs.
Housing society with the
Community group
4. Development and project proponent in Training to the Housing society with the
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 47
maintenance of green-
belt and green areas
to overcome micro-
climatic impacts
association with the
community monitoring
group
community group on
plant maintenance
community group
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 48
INTRODUCTION
M/s Jasmine Buildmart Pvt. Ltd. having its office at 406 4th floor, Elegance Tower 8 Jasola
District Center New Delhi. The company is developing a Group Housing Colony on area
measuring 12.3187 Acres at Village Gwal Pahari, Sector 3, District Gurgaon, Haryana. The
renewal of license has already been taken Directorate Town and Country Planning, Haryana
vide Memo No. LC-1638-A-JE (S)-2014/16771 dated 31/07/2014 which is renewed upto
14/05/2016.
SITE LOCATION AND SURROUNDINGS
The proposed project site is located at Village- Gwal Pahari, Sector 3, District- Gurgaon,
Haryana. The GPS Co-ordinates of the project site is 28°25'51.91"N, 77° 8'34.62"E.
Figure-1: Google Image of the Project Site
CONNECTIVITY
S. NO. DETAIL DISTANCE DIRECTION
1. Nearest Highway (NH-8) 8.8 Km West
2. Gurgaon Railway Station 14.5 Km West
3. Indira Gandhi International Airport 13 Km North-West
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 49
PROJECT LAYOUT AND ENVIRONMENTAL CONTEXT
The total plot area of the Group Housing Colony is estimated 49851.931 m2
(12.3187
Acres). The detailed Area Statement is provided below in Table 1.
SALIENT FEATURES OF PROJECT:
Table 1: Area Statement
S. No. Particulars Area ( m2)
1. Project Name
Extension of Environment Clearance
Group Housing Colony
M/s Jasmine Buildmart Pvt. Ltd.
2. Activity in the complex Retail area, Residential Dwelling Units and EWS
Units
3. Total Plot Area 49851.931 m2
(12.3187 Acres)
4. Permissible FAR @ 175 80902.5 m2
5. Achieved FAR @ 173.542 80228.47 m2
6. Permissible Ground Coverage
@ 25 % 11557.50 m
2
7. Achieved Ground Coverage 1891.911 m2
8. Built-up Area Detail (FAR +
Non-FAR) 89457.172 m
2
9.
Parking Required 312 ECS
Proposed Surface Parking 80 ECS
Total Parking Proposed
316 ECS Proposed Basement Parking 149 ECS
Proposed Stilt Parking 87 ECS
10. Power Requirement & Sources
6000 KW
Source: Dakshin Haryana Bijli Vitran Nigam
(DHBVN)
11. No. of DG Sets 4 Nos. of DG Sets having Total Capacity of 5000
KVA (1 x 1500 KVA + 2 x 1250 KVA + 1000 KVA)
12. Water requirement & Sources
Total Water Requirement: 333 KLD
Fresh Water Requirement: 216 KLD
Treated/Recycled Water Requirement: 116.6 KLD
Source: HUDA
13. Sewage Treatment & Disposal
STP capacity :186 KLD
Sewage discharge: Total 140 KLD of water will be
obtained after the recycling of wastewater out of
which 64 KLD shall be utilized for the purpose of
flushing, 38 KLD for landscape development, 10
KLD for DG Cooling and 28 KLD will be supplied to
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 50
nearby construction sites for construction
pupose.
14. Estimated Population Total: 2926 Persons including visitors & other
staff
15. Green Area Required @ 15 % 6934.5 m
2
Proposed Green Area @16.48
% 2830.00 m
2
16. Cost of the project Rs. 118.18 Crores (Approx.)
*FAR = Floor Area Ratio
POPULATION DENSITY
The Total population of the project will be 2926 Persons including visitors. The detailed
population breakup is showing as given below in the Table 2.
Table-2: Population Break up
Residential Dwelling Units
No. of
Units/Area
Population
Per Unit
Population
breakup Total
Dwelling units population 176 5 880
1184
EWS population 32 5 160
Servant Units Population 18 2 32
Total Residential Population 1076
Visitors @10% of resident
population
108
Ground Floor Commercial Area
Commercial population 230.688 m2
3 m2/
person
77
77
population of shopkeeper @ 1/3 of
retail area population
26
Floating Population (Visitors or
Shoppers) @ 2/3rd of retail area
population
51
Community Hall
Community Hall population 723.33 m2
1.5 m2/
person 482 482
Security, Maintenance &
Housekeeping Staff
@ 10% of
residential
Population 108 108
Total population 2926
PROJECT COST
The total estimated cost of the project is Rs. 118.8 Crores which includes the cost of the
land as well as the developmental cost.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 51
WATER REQUIREMENT
The water will be supplied through HUDA. Total water requirement of the project will be
approximately 226 KLD, out of which 114 is fresh water requirement and 112 KLD is
recycled/treated water. The calculation of total water requirement and total waste water
generation is showing as Table-3.
Table-3: Calculations for Daily Water Demand
S No Particulars Occupancy/
Area(sqm)
Rate of
water
demand (Lt)
Daily Water Demand (KLD) Wastewater
Generated Domestic Flushing Total
1. Residential
Population 1076 150 107.6 53.80 161.40 139.88
2. visitors of
Residential
Appartments
108 15 0.65 0.9684 1.614 1.48
3. Shopkeepers 26 45 0.4 0.77 1.15 1.08
4. visitors of
retail area 51 15 0.31 0.46 0.77 0.71
5. Horticulture 7621 5 l/sqm 38.1 0
6. Community
Hall 482 15 2.89 4.34 7.23 6.65
7.
Security,
Maintenance
&
Housekeeping
Staff
108 45 1.61 3.23 4.84 4.52
8. Total 113.44 63.57 215.12 154.32
say 114
KLD
say 64
KLD
say 215
KLD say 155 KLD
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 52
Hence, total water requirement of the project will be as follows;
Total Water Requirement : 226 KLD
Fresh Water Requirement : 114 KLD
Flushing : 64 KLD
Total Waste Water Generation : 155 KLD
Recycled/ Treated water : 140 KLD
The water balance diagram is showing in Figure-2.
Figure-2: Water Balance Diagram
To nearby construction sites by tanker (28 KLD)
Total Water Requirement (226 KLD)
Fresh Water Requirement (114 KLD)
Recycled/Treated Water (112 KLD)
@ 100%
Wastewater generated (91.2 KLD)
Domestic Water Requirement (114 KLD) Flushing (64 KLD)
Total wastewater generated (155 KLD)
STP Capacity (186 KLD)
@ 90% of wastewater generated
Recycled/Treated water (140 KLD)
Horticulture (38 KLD) DG Cooling (10 KLD)
Wastewater generated (64 KLD)
Wastewater generated (NIL)
Wastewater generated (NIL)
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 53
Wastewater Generation & Treatment:
An external sewage network shall collect the sewage from all units, and flow by gravity to
the proposed sewage treatment plant. Following are the benefits of providing the Sewage
Treatment Plant in the present circumstances:
Reduced net daily water requirements from tube wells for Horticultural purposes, by
utilizing the treated effluent for the same. This shall consequently lead to a lower
withdrawal from the underground aquifer water sources.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant shall be rich in organic materials and is
an excellent fertilizer for horticultural purposes.
a. Wastewater Details (Before Treatment)
(a) Daily load : 132.6 KLD
(b) Oil & Grease : 50-100 mg/l
(c) Temperature : Maximum 32oC
(d) pH : 6.5 to 8.5
(e) Colour : Mild
(f) Suspended Solids (mg/l) : 400-600 mg/l
(g) BOD5 (mg/l) : 250-400 mg/l
(h) COD (mg/l) : 500-700 mg/l
b. Wastewater Details (After Treatment)
(a) Daily load : 132.6 KLD
(b) Oil & Grease : <10mg/l
(c) Temperature : Maximum 32oC
(d) pH : 7.0 to 7.5
(e) Colour : Mild
(f) Suspended Solids (mg/l) : <100 mg/l
(g) BOD5 (mg/l) : <30 mg/l
(h) COD (mg/l) : <250 mg/l
Description of Treatment Process and Units:
The main criteria for treatment of domestic effluent are its bio degradability, made
possible by the existence of a balance of nutrients for the bacteria and characterized by its
biological oxygen demand (BOD).
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 54
Treatment of the effluent is proposed to be performed by aerobic biological process. The
process is designed to induce the growth of bacteria, which by physical and physiochemical
action retain the organic pollution and live on it. This growth is obtained by putting a
bacterial culture disposal as a flock in suspension in the effluent inside a stirrer, i.e.
aeration tank. Stirring in the aeration tank is required to avoid settlement of the aeration
tank is required to avoid homogenous the mixture of the bacterial floc and the effluent
called mixed liquor. To have efficient treatment extended aeration system is proposed by
submerged fine bubble diffusers.
Main Component of Sewage Treatment Plant
In the proposed treatment scheme the following component unit shall be provided. The
schematic diagram of STP is given in figure below:
Screen/ Grit chamber within effluent collection sump.
Equalization sump
Submersible type raw effluent re-lift pumps
Aeration Tank (min 1 day HRT)
Secondary clarifier
Clarified water tank/clear water storage tank
Filter feed pump
Sludge return pump
Sludge holding tank
Sludge drying beds, Centrifuge/ Filter Press
Treatment Description
Wastewater will be collected in raw effluent collection sump. Manually cleaned bar screen
will be installed to screen any large pieces within the sump. From the sump the wastewater
will be pumped via two submersible solids handling pumps (1 working + 1 standby) into
adjoining equalization tank on controlled rate via a flow-regulating box.
From equalization tank, effluent flow by gravity into an adjoining aeration tank on a
controlled rate via a flow-regulation box. Grit collected at the bottom of sump is removed
by pumps.
In the aeration tank wastewater will be mixed with microorganisms in presence of
dissolved oxygen. Microorganisms will assimilate organic impurities. The mixed-liquor
suspended solids will be maintained at levels of 3500 mg/lit to 4000 mg/lit. The bottom of
the aeration tank will be supplied through two positive displacements (roots type) air
blowers (1 working + 1 standby) located outside the tank. Submerged air diffusers will
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 55
provide mixing and oxygen for the needs of microorganisms. The blowers will be sized to
maintain dissolved oxygen level in the aeration tank of approximately 2 mg/lit.
From the aeration tank mixed liquor will flow by gravity into adjoining clarifier tank. The
solids will settle in the clarifier tank. A sludge return pump will provide for pump the
settled sludge from the clarifier tank back to the aeration tank. Clarifier tank will also be
provided with skimmer system to pump floating scum back to the aeration tank to keep the
clarifier surface clean.
An overflow well with scum baffle will be provided in the clarifier to take treated
wastewater out of the clarifier. From the clarifier treated wastewater will flow by gravity
into adjoining chlorine contact tank/clarified water tank. In this tank chlorine will be added
in the form of calcium or sodium hypochlorite solution by a suitable chlorinator. A free
residual chlorine level of 1 ppm will be maintained.
Treated water after chlorine contact tank will be clear, odourless, low BOD (20 mg/lit), low
suspend solids and can be used for many non potable applications like
gardening/horticulture purpose etc. or can be disposed directly to public/natural drain.
It is further filtered through Pressure sand filter and activated carbon filter for further
reduction of suspended solids to make it suitable for recycling for irrigation purpose. Excess
sludge from the clarifier tank will be taken periodically into sludge holding tank. In this tank
sludge will be aerated for self-stabilization. Air will be shut off periodically and
superannuate water will be transferred to the aeration tank creating stabilized sludge. This
stabilized sludge is dried on sludge drying beds and disposed off profitably by selling in the
market or using as manure to the horticulture purpose.
Re-Use & Disposal of Treated Effluent It is expected that the project would generate
approx. 155 KLD of waste water. The whole quantity of domestic sewage will be treated
through proposed Sewage Treatment Plant of capacity 186 KLD to be developed within the
project premises. The recycled water from proposed Sewage Treatment Plant will be
around 140 KLD which will be used for DG cooling, flushing and horticulture purposes.
Working Principle:
Bacteria grow rapidly in the Bio-Pac unit under properly engineered conditions. They
consume organic chemical for their growth and remove them from the wastewater. The
bacteria converts chemical into biological cells, which under proper growth conditions,
form slims. The bacteria adhere to available surfaces and accumulate into what we call
random biological film or fixed film. The high surface area-to-volume ratio of the units
allows for accumulation of substantial concentration of bacteria in the relatively small
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 56
reactor units. Further, the accumulated bacteria which provides high rates of removal or
organic chemicals are fixed in the system and do not need to be recycled back to the basin.
In the Bio Reactor system the water is constantly flowing through rigid PVC matrix to which
the biological film attached. As the water flows past the biological film, bacteria in the film
absorb organic chemicals as well as oxygen, nitrogen, phosphorus, and other trace
nutrients required for their growth.
As the bacteria grow on the matrix and as more chemicals are added to the unit, the
stationary biological film will continue to build in thickness. As the film becomes thicker the
depth of penetration by diffusion of the absorbed material such as oxygen or other
nutrients is not sufficient to reach the entire distance through the slime of the plastic
media. At some point, the film will become sufficiently thick and portion of the film closest
to the plastic media will not receive any food or nutrient, particularly oxygen. The inner
layer of the film becomes anaerobic and the organisms lose their ability to adhere to the
media surface. The shear forces of the water and / or air bubbles flowing through the
matrix will ultimately become great enough to tear this portion of the biological film loose
from the media. This process is called sloughing. The solids which slough from the media
will flow out of the system with the sewages and are to be removed from the water
through clarification in a settling module. The exposed portion of media surface will repeat
the process of slime accumulation and sloughing.
In actual operation of the Bio Reactor units, biological film will be in a state of dynamic,
continuous growth and sloughing. At any given time, portion of the media are always at
some point between forming a new film sloughing.
Sewage Quality:
The Sewage discharged from the Bio reactor system will contain sloughed biological solids,
but would be relatively free of soluble organic chemicals. The quantity of biological solids in
the sewage will depend substantially on the quantity of suspended solids and the
concentration of soluble BOD entering system. It is therefore necessary to provide means
of separating the biological mass from the sewage. Package unit contains tube settlers for
sedimentation and 60 Gross fluted Rigid PVC fill media for the FAB units to treat the
wastewater for discharge into the receiving waters and/or the sanitary sewers as per the
local regulations. The media thickness changes with the design parameters/depth of the
unit and can vary from 0.25 to 0.40 mm thickness.
1. Tube Settler:
Here we are providing the Tube Settler along with the PVC media which will
enhance the contact period and thereby the improved performance. The Tube
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 57
settler will have a determined lope in the bottom to collect the suspended solids
from the waste water. The sludge will be suited to the Sludge Drying Beds.
2. Pressure Sand Filter:
Here the treated water coming from the TSS will be treated for the suspended
impurity removal.
3. Activated Carbon Filter:
Here the water coming from the ACF will be treated for colour removal, suspended
impurity removal and the treated water shall be sent to the sewer.
4. Filter Press:
A filter comprises a set of vertical, juxtaposed recessed plates, presses against each
other by hydraulic jacks at one end of the set. The pressure applied to the joint face
of each filtering plate must withstand the chamber internal pressure developed by
the sludge pumping system. This vertical plate layout forms watertight filtration
chambers allowing easy mechanization for the discharge of cakes. Filter clothes
finely or tightly meshed are applied to the two grooved surfaces in this plat.
Primary Treatment:
This is the first step of inlet waste mainly consist of removal of coarse particles, oil and
grace and mixing co-agents in the water for removal of suspended solids through
sedimentations. After this treatment scheme, the BOD, TSS, COD, and O&G level comes
down to 20% of initial levels.
Secondary Treatment:
This is second step of waste water treatment. It mainly consist aerobic process of the
Primary treated water, bacterial growth, EM dosing addition of oxygen and chemical which
help in bacterial growth and lastly settlement of the biological waste as sludge. Normally it
is found that the reduction level in TSS, BOD, O & G and COD after an efficient secondary
treatment will be as under-
Tertiary Treatment:
This is the final stage of treatment where the Sewage after secondary treatment first is
mixed with Sodium Hypo Chloride and then Sewage will be passed through (PSF) dual
media filter and (ACF) activated carbon filter where sand, anthracite and activated carbon
will be used as filtration media. Once the above limits achieved thereafter the final outlet
water will also confirms the Bio Assay test of 90% of fish survive.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 58
Technical Specifications & Design for Sewage Treatment Plant of 186 KLD
CIVIL WORKS
1. BAR SCREEN CHAMBER
Quantity 1 No.
Size 0.6 m x 0.5 m x 0.3 + FB
MOC SS-304
2. OIL & GREASE TRAP
Quantity 1 No.
Size 0.6 m x 1.2 m x 0.8 m + FB
Capacity 0.57 m3
MOC Civil
3. COLLECTION CUM EQUALIZATION TANK
Quantity 1 No.
Size 4.0 m x 4.0 m x 2.5 m + 0.5 m FB
Capacity 40 m3
MOC Civil
4. SLUDGE HOLDING TANK
Quantity 1 No.
Size 4.0 m x 2.0 m x 3.0 m + 0.5 m FB
Capacity 24 m3
MOC Civil
ELECTROMECHANICAL EQUIPMENTS
1. BASKET SCREEN
Quantity 1 No.
Size 500 mm x 400 mm
MOC SS-304
2. SEWAGE LIFTING PUMPS
Quantity 2 Nos. (1W + 1S)
Capacity 7.0 m3/hr
Head 10 m
MOC CI
Type Submersible Pump
Make KSB / Wilo or Equivalent
3. MBBR REACTOR (FAB REACTOR)
Quantity 2 Nos.
Capacity 16.0 m3
Media Type Floating Media
Size 2.0 m x 2.0 m x 4.0 m + 0.5 m FB
MOC MS 5 mm Thickness
Surface Protection Inside Epoxy; Outside Enamel
4. SECONDARY TUBE SETTLER
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 59
Quantity 1 No.
Tube Plan 4.4 m2
Tube Height 0.678 mm
Size 2.0 m x 2.2 m x 1.25 m + 0.5 m FB + Hopper Bottom
MOC MS 5 mm Thickness
Surface Protection Inside Epoxy; Outside Enamel
5. CLEAR WATER TANK
Quantity 1 No.
Size 2.0 m x 3.0 m x 2.0 m + 0.5 m FB
Capacity 12.0 m3
MOC MS 5 mm Thickness
Surface Protection Inside Epoxy; Outside Enamel
6. FILTER FEED PUMPS
Quantity 2 Nos. (1W + 1S)
Capacity 8.0 m3/hr
Head 25 m
MOC CI
Type Centrifugal, Monobloc
Make Kirloskar or Equivalent
7. SLUDGE RECIRCULATION PUMPS
Quantity 2 Nos. (1W + 1S)
Flow 2.0 m3/hr
Head 10 m
MOC CI
Type Self Priming Pump
Make Kirloskar / Equivalent
8. ROOT AIR BLOWERS
Quantity 2 Nos. (1W + 1S)
Capacity 150 m3/hr @ 5000 mm WC
Motor Power 7.5 HP
Type Twin Lobe Type
Make Everest / Beta or Equivalent
9. MULTIGRADE FILTER COLUMN
Quantity 1 No.
Type Down Flow
Dia 900 mm
HOS 1800 mm
Material of Construction FRP
Filter Media Fine Sand, Pebbles, Gravels
10. ACTIVATED CARBON FILTER COLUMN
Quantity 1 No.
Type Down Flow
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 60
Dia 900 mm
HOS 1800 mm
Material of Construction FRP
Filter Media Activated Carbon & Supporting Sand
11. CHLORINE DOSING SYSTEM
Quantity 1 Set
(Pump -1 No. / Tank -1 No.)
DOSING PUMP
Capacity 0 - 6 LPH
MOC PP
Type Metering Dosing Pump
Rating 0.5 HP
Make Seko / Asia LMI or Equivalent
DOSING TANK
Capacity 200 Litres
Type MS Skid Mounted
Accessories Cover, Funnel & Sight Tube
MOC FRP
Mixing Diffused agitation from existing blower
12. FINE BUBBLE DIFFUSERS
Quantity 16 Nos.
Size 63 mm Dia x 600 mm Long
MOC PVC
Make Rehau or Equivalent
13. COARSE BUBBLE DIFFUSERS
Quantity 12 Nos.
Size 150 mm Dia
MOC PVC
Make Rehau or Equivalent
14. FILTER PRESS
Quantity 1 No.
Make W2P / Pharmatech or Equivalent
Size 18" x 18"
No. of Plates 18
Type Manual
15. FILTER PRESS FEED PUMPS
Quantity 2 Nos. (1W + 1S)
Size 1 m3/hr
Head 40 m
MOC CI
Type Screw Pump
Make Rotomac / Roto or Equivalent
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 61
16. TREATED WATER SUPPLY PUMPS FOR FLUSHING & HORTICULTURE
Quantity 2 Nos. (1W + 1S)
Capacity 8.0 m3/hr
Head 55 m
MOC CI
Type Centrifugal, Monobloc
Make Kirloskar or Equivalent
17. MEDIA FOR MGF & ECF Fine Sand, Pebbles, Gravels & Activated Carbon
18. MEDIA FOR MBBR TANKS FAB media (Qty - 16 m3)
19. MEDIA FOR TUBE SETTLERS Tube deck media (Qty - 2.4 m3)
20. ELECTROMAGNETIC FLOWMETER
Quantity 1 No. (Outlet)
Line Size 40 NB
Make RLT / Electronet or Equivalent
21. ELECTRICALS
10 DOL Starter panel + 1 Starter + 2 stage level controller, energy meter, mimic diagram
Electrical Wiring
22. PLUMBING
Piping & Valves with aeration
grid
GI / PVC/MS - Epoxy as per requirement
Figure-3: Schematic Diagram of STP
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 62
RAIN WATER HARVESTING
The storm water disposal system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. Storm water drainage plan of the project is
enclosed. The amount of storm water run-off depends upon many factors such as intensity
and duration of precipitation, characteristics of the tributary area and the time required for
such flow to reach the drains. The drains shall be located near the carriage way along either
side of the roads. Taking the advantage of road camber, the rainfall run off from roads shall
flow towards the drains. Storm water from various plots/shall be connected to adjacent
drain by a pipe through catch basins. Therefore, it has been calculated to provide 12
rainwater harvesting pits at selected locations, which will catch the maximum run-off from
the area.
1) Since the existing topography is congenial to surface disposal, a network of storm
water pipe drains is planned adjacent to roads. All building roof water will be brought
down through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at
regular intervals for rain water harvesting and ground water recharging.
3) Peak Hourly rainfall of 45mm/hr shall be considered for designing the storm water
drainage system. Rain water harvesting has been catered to and designed as per the
guideline of CGWA. At the bottom of the recharge well, a filter media is provided to
avoid choking of the recharge bore. Design specifications of the rain water harvesting
plan are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be
damaged allowing release of material into the water. Roof painting has been
avoided since most paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would
be installed. Most of the debris carried by the water from the rooftop like leaves,
plastic bags and paper pieces will get arrested by the mesh at the terrace outlet
and to prevent contamination by ensuring that the runoff from the first 10-20
minutes of rainfall is flushed off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been
connected to the system.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 63
Table-5: Rainwater Harvesting Calculation
S.
No. Particulars
Catchment Area
in m2 (A)
Runoff
Coefficient
(C)
Rainfall Intensity
in mm (I)
Discharge
(m3/hr)
1. Rooftop area 1,891.91 0.9 45.0 72.4
2. Green area 7,621.00 0.2 45.0 68.6
3. Paved area 36,717.09 0.7 45.0 1,074.0
Total Runoff 1,214.9
Taking 15 minutes retention time, total volume of storm water= 1,214.9 × 0.25 = 303.73 m3
Taking the effective diameter and depth of a Recharge pit 3.0 m and 3.5 m respectively,
Volu e of a si gle Re harge pit (πr2h) = 3.14 × 1.5 × 1.5 × 3.5 = 26.376 m
3
Hence No. of pits required = 303.73/ 26.376= 11.52 Say 12 Pits
Total 12 nos. of Rain Water Harvesting pits are being proposed for artificial rain water
recharge within the project premises.
Figure-4: Typical Rain Water Harvesting Pit Design
NO. OF PITS: 12
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 64
VEHICLE PARKING FACILITIES
Parking Required
Number of Dwelling Units = 176
No of EWS Units = 32
Total Units (176 + 32) = 208
Parking Required per unit = 1.5 ECS
Parking Required = 1.5 X 208 = 312 ECS
Covered Parking Required = 75 % of total parking i.e. 25% of 312= 234 ECS
Open Parking Required = 74 ECS
Parking Proposed
Surface and Basement Parking:
S. No. Proposed Parking
Area
required per
ECS
Area Available Parking spaces in
ECS
1 Parking proposed in
Basement 35 m
2 5244.158 149.833 Say 149
2 Parking proposed under
Stilt 30 m
2 2630.728 87.691 Say 87
3 Parking proposed on
Surface 25 m
2 2004.68 80.187 Say 80
Total Parking Provided 316 ECS
Hence, adequate space for parking will be provided within the project premises.
POWER REQUIREMENT
The power shall be supplied by Dakshin Haryana Bijli Vitran Nigam (DHBVN).The connected
load for the Group Housing Colony will be approx. 6000 KW.
Details of DG Sets
There is provision of 4 nos. of DG sets having Total Capacity of 5000 KVA (1 x 1500 KVA + 2
x 1250 KVA + 1 x 1000 KVA ) will be provided as power back up during power failure. The
proposed DG sets will be equipped with acoustic enclosure with proper stack height to
minimize the emission and noise generation.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 65
SOLID WASTE GENERATION
Solid waste would be generated both during the construction as well as during the
operation phase. The solid waste expected to be generated during the construction phase
will comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc.
The following steps are proposed to be followed for the management of solid waste:
Construction yards are proposed for storage of construction materials.
The excavated material such as topsoil and stones will be stacked for reuse during later
stages of construction
Excavated top soil will be stored in temporary constructed soil bank and will be reused
for landscaping of the proposed Group Housing Colony project.
Remaining soil shall be utilized for refilling/ road work/ rising of site level at locations/
selling to outside agency for construction of roads etc.
Figure-5: Solid Waste Management Scheme during Construction Phase
During the operation phase, waste will generate from mall, offices, retail shops/ area
etc.The solid waste generated from the project shall be mainly commercial waste and
estimated quantity will be 747 kg/ day approximately.
Used in re-filling, raising site level
Sold to agency for recycling
Top soil conserved for landscaping, balance
used in re-filling
As per MSW Rules, 2000
and amended Rules, 2008
Solid Waste
Construction Waste Food Waste
Construction waste, Broken Bricks, Waste Plaster
Empty cement Bags,Containers
etc.
Excavated Soil
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 66
Table-5: Calculation of Solid Waste Generation
S. No. Source of Solid Waste Generation
Waste
Generation
Rate
(kg/cap/day)
Total
Population
Waste
Generated
(kg/day)
1. Residential Refuse 0.45 1076 484.2
2. Visitors Refuse 0.15 215.20 32.28
3. Retail area refuse 0.15 77 11.534385
4. Street sweeping/ Green Area Refuse 0.05 2926 146.31593
5. Community Hall 0.15 482 72.3334
Total 746.66
Kg/ Day
(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health &
Environment Engineering Organization, Ministry of Urban Development, (Government of
India, May 2000))
Figure-6: Solid Waste Management Scheme during Operation Phase (Part-II)
Biodegradable Waste (523 kg/day)
Non-Biodegradable Waste (224 kg/day)
Green Bins
Municipal Solid Wastes
(Management and
Handling) Rules, 2000
Manure
Blue Bins Dark Gray Bins
Final disposal through a Govt. approved agency to recycling
industry
Final disposal through a Govt. approved agency
Solid Waste (747 kg/day)
Recyclable Waste (157 kg/day)
Non-Recyclable Waste (67 kg/day)
Dispose as per Municipal Solid Wastes
(Management and Handling) Rules, 2000&
amendment 2008
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 67
Following arrangements will be made at the site in accordance to Municipal Solid
Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008.
1 Collection and Segregation of waste
A door to door collection system will be provided for collection of domestic waste
in colored bins from household units.
Separate colored bins will be provided for dry recyclables and bio-degradable
waste.
For institutional waste collection, adequate number of colored bins (Green and
Blue bins for bio-degradable and non bio-degradable respectively) are proposed to
be provided.
Litter bin will also be provided in open areas like parks etc.
Treatment of waste
Bio-Degradable wastes
Bio-degradable waste shall be disposed-off as per MSW (Management & Handling)
Rules 2000 & amendments 2008.
STP sludge is proposed to be used as manure for horticulture.
Recyclable Wastes
Grass Recycling – The cropped grass will be spread on the green area. It will act as
manure after decomposition.
Recyclable wastes like paper, plastic etc. will be sold off to recyclables.
Hazardous wastes such as waste oil will be sold off to authorized recyclers. Buy
back arrangement will be made for batteries.
2 Disposal
The Municipal Solid Waste Management will be collected as per the guidelines of Municipal
Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2008. The inert
non-recyclable wastes will be disposed through government approved agency for land
filling. A solid waste management scheme is depicted in the following figure for the Group
Housing Colony project.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 68
GREEN AREA
Total green area measures 7621 m2 i.e. 16.4849 % of the plot area which will be area under
tree plantation within the offices and along the roads. Evergreen tall and ornamental trees
and ornamental shrubs have been proposed to be planted inside the premises. Parks will
also be developed by the management.
Table-6: Green Area Calculation
S. NO. DESCRIPTION GREEN AREA
1. Peripheral Plantation Area @ 9 % 4160.7 m2
2. Avenue Plantation Area @ 4 % 1849.2 m2
3. Shrubs & Lawn Plantation Area @ 6.8% 1611.069 m2
Total Green area proposed @ 16.4849 % 7621 m
2
Plantation & Landscaping
Selection of the plant species would be done on the basis of their adaptability to the
existing geographical conditions and the vegetation composition of the forest type of the
region earlier found or currently observed.
Tree Plantation Plan
The plantation matrix adopted for the tree plantation pit of 0.3 m × 0.3 m size with a
spacing of 2 m x 2 m. In addition, earth filling and manure may also be required for the
proper nutritional balance and nourishment of the sapling. It is also recommended that the
plantation has to be taken up randomly and the landscaping aspects could be taken into
consideration.
Multi-layered plantation comprising of medium height trees (7 m to 10 m) and shrubs (5 m
height) will be the part of landscape development. In addition creepers will be planted
along the boundary wall to enhance its insulation capacity.
Selection of Plant Species for Tree Plantation
The selection of plant species for the development depends on various factors such as
climate, elevation and soil.
S. No. NAME OF SPECIES (SHRUBS)
Botanical Name Common Name
1 Artocarppusheterophyllus Kathal
2 Balanitesroxburghii Desert - Date
3 Bambusaarundinacia Thorny Bamboo
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 69
4 Bambusa vulgaris Golden Bamboo
5 Alstoniascholans Apocynaceae
6 Acacia catechu Khair
7 Bauhinia acuninata Kanchan
8 Callistemon citrinus Bottle brush
9 Citrus aurantium Nebu
10 Durantarepens Duranta
S.No. NAME OF SPECIES (TREES)
Botanical Name Common Name
1 Bauhinia Semla Semla
2 Albiziachinensis Siran
3 Albizialebbeck The Siris tree
4 Cassia pumila Yellow Cassia
5 Anthocephaluschinensis Kadamba
6 Azadirachtaindica Neem Tree
7 Delbergialatifolio Black wood
8 Delonixregia Gulmohar
9 Eucalyptus citriodora Eucalyptus
10 Ficusbenghalensis Banyan Tree
11 Ficuselastiaca Indian Rubber Tree
12 Ficusreligosa Peepal Tree
13 Grevillearobusta Silky Oak
14 Jacaranda mimosaeolia Nil - Gulmohar
15 Mangiferaindica Mango Tree
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 70
DETAIL OF CONSTRUCTION MATERIALS
Following building material will be used at site:
S. No. Building Material
1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Pipe scaffolding (cup lock system)
8. Bricks
9. CLC fly ash blocks
10. Crazy (white marble) in grey cement
11. P.V.C. conduit
12. MDS, MCBs
13. PVC overhead water tanks
14. / '’ thi k red olour pa er tiles
15. PPR (ISI marked)
16. PVC waste water lines
17. S.W. sewer line up to main sewer
18. PVC rain water down take
19. Stainless steel sink in kitchen
20. Joinery hardware- ISI marked
MATERIALS USED FOR CONSTRUCTION & THEIR U VALUES
S. No Building Material Proposed with U
& R Values
‘ Values
(in Sq m. Deg
C/ Watts )
U Values
(in Watts/ Sq
m. Deg C)
Solar Heat
Gain Factor
1. WALL
Brick wall (230 mm thick), both side
thick sand cement plaster (12-
18mm) with insulation
3.55 0.28 0.46
2. ROOF
200 mm RCC slab with mud phuska
& clay tiles with 75 mm insulation
1.25 0.80 0.32
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 71
LIST OF MACHINERY USED DURING CONSTRUCTION
Following machineries will be used at site during construction:
S. NO. NAME OF MACHINERY
1. Dumper
2. Concrete mixer with hopper
3. Excavator
4. Concrete Batching Plant
5. Cranes
6. Road roller
7. Bulldozer
8. RMC Plant
9. Tower Cranes
10. Hoist
11. Labor Lifts
12. Pile Boring Machines
13. Concrete pressure pumps
14. Mobile transit mixer
ENERGY CONSERVATION
Energy conservation program will be implemented through measures taken both on energy
demand and supply.
Energy conservation will be one of the main focuses during the complex planning and
operation stages. The conservation efforts would consist of the following:
Supply Energy Conservation Demand
Utilize energy-efficient diesel genetators Exploring the possibilities of introducing renewable energy
Reduce consumption Use energy efficient appliances Create Guest Awareness
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 72
Architectural design
Maximum utilization of solar light will be done.
Maximize the use of natural lighting through design.
The orientation of the buildings will be done in such a way that maximum
daylight is available.
The green areas will be spaced, so that a significant reduction in the
temperature can take place.
Energy Saving Practices
Energy efficient lamps will be provided within the complex.
Constant monitoring of energy consumption and defining targets for energy
conservation.
Adjusting the settings and illumination levels to ensure minimum energy used
for desired comfort levels.
Behavioral Change on Consumption
Promoting resident awareness on energy conservation
Training staff on methods of energy conservation and to be vigilant to such
opportunities.
ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN
For the effective and consistent functioning of the complex, an Environmental
Management system (EMS) would be established at the site. The EMS would include the
following:
An Environmental management cell
Environmental Monitoring.
Personnel Training.
Regular Environmental audits and Correction measures.
ENVIRONMENTAL MANAGEMENT CELL
Apart from having an Environmental Management Plan, it is also proposed to have a
permanent organizational set up charged with the task of ensuring its effective
implementation of mitigation measures and to conduct environmental monitoring.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 73
Hierarchical Structure of Environmental Management Cell:
Normal activities of the EMP cell would be supervised by a dedicated person who will
report to the site manager/coordinator of the Group Housing Colony. The hierarchical
structure of suggested Environmental Management Cell is given in following Figure-7.
Figure-7: Environnent Management Cell Structure
ENVIRONMENTAL MONITORING
The purpose of environmental monitoring is to evaluate the effectiveness of
implementation of Environmental Management Plan (EMP) by periodic monitoring. The
important environmental parameters within the impact area are selected so that any
adverse effects are detected and time action can be taken. The project proponent will
monitor ambient air Quality, Ground Water Quality and Quantity, and Soil Quality in
accordance with an approved monitoring schedule.
Table- 7: Suggested Monitoring Program for Proposed Group Housing Colony Project
Monitoring Frequency of Monitoring
Air & Stack:
• Ambient Air Quality at appropriate location for PM10,
PM2.5
, SO2, NO2, HC
• Stack emission for point sources PM, SO2, NO2, HC
&CO
• Six monthly
• Six monthly
Corporate Environmental
Division
Site Manager
Rep from Corporate
Planning group
Site Environmental Coordinator
Wastewater Treatment Plant
Operator
Greenbelt Development
Incharge
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 74
Water & Wastewater:
• Water Quality Monitoring for relevant parameters of
IS – 10500
• Waste Water Quality (Treated & Untreated) for pH ,
TSS, Oil & Grease,
• Waste water quality pH, TSS, oil & Grease. BOD, COD,
MLSS, TKN & Phosphate.
• Six Monthly
• Daily till stabilization of
STP
• Weekly till one month
then annually
Noise: - Day & Night level Noise Monitoring (Leqday,
Leqnight)
• Six Monthly
Soil:
• Soil Monitoring, Qualitative and quantitative
testing/analysis to check the soil fertility, porosity,
texture, water holding opacity etc.
• Six Monthly
Awareness and Training: Training and human resource development is an important link to
achieve sustainable operation of the facility and environment management. For successful
functioning of the project, relevant EMP would be communicated to:
Residents and Contractors: Residents must be made aware of the importance of waste
segregation and disposal, water and energy conservation. The awareness can be provided
by periodic Integrated Society meetings. They would be informed of their duties.
Environmental Audits and Corrective Action Plans: To assess whether the implemented
EMP is adequate, periodic environmental audits will be conducted by the project
propo e t’s E iro e tal di isio . These audits ill e follo ed y Corre tio A tio Plan (CAP) to correct various issues identified during the audits.
ENVIRONMENT MANAGEMENT PLAN
The Environment Management Plan (EMP) would consist of all mitigation measures for
each component of the environment due to the activities increased during the construction
and operational phase of the project and these are discussed in later subsections.
The EMP is generally
Prepared in accordance with the rules and requirements of the MoEF and CPCB/ SPCB
To ensure that the component of facilities are operated in accordance with the design
A process that confirms proper operation through supervision and monitoring
A system that addresses public complaints during construction and operation of the
facilities and
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 75
A plan that ensures remedial measures is implemented immediately.
The key benefits of the EMP are that it offers means of managing its environmental
performance thereby allowing it to contribute to improved environmental quality. The
other benefit includes cost control and improved relations with the stakeholders.
EMP includes four major elements:
Commitment & Policy: The management will strive to provide and implement the
Environmental Management Plan that incorporates all issues related to air, water, land
and noise.
Planning: This includes identification of environmental impacts, legal requirements
and setting environmental objectives.
Implementation: This comprises of resources available to the developers,
accountability of contractors, training of operational staff associated with
environmental control facilities and documentation of measures to be taken.
Measurement & Evaluation: This includes monitoring, counteractive actions and
record keeping.
It is suggested that as part of the EMP, a monitoring committee would be formed by M/s
Jasmine Buildmart Pvt. Ltd. de-comprising of the site in-charge/ coordinator,
environmental group representative and project implementation team representative. The
o ittee’s role ould e to e sure proper operatio a d a age e t of the EMP including the regulatory compliance. The components of the environmental management
plan, potential impacts arising, out of the project and remediation measures are
summarized below in Table-8.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 76
Table-8: Summary of Potential Impacts and Remedial Measures
S.
No.
Environment
al
components
Potential
Impacts Potential Source of Impact
Controls Through EMP &
Design Impact Evaluation Remedial Measures
1. Ground
Water Quality
Ground Water
Contamination
Construction Phase
Waste water generated
from temporary labor
tents.
No surface accumulation
will be allowed.
No significant impact as
majority of labors would
be locally deployed
Operation Phase
Discharge from the
project
Proponent will provide
the STP to treat the
discharge of Group
Housing Colony.
No negative impact on
ground water quality
envisaged. Not
significant.
2. Ground
Water
Quantity
Ground Water
Depletion
Construction Phase
Use of ground water
for construction
activity.
Controlled use of water
during construction
No significant impact on
ground water quantity
envisaged.
Operation Phase
The source of water
during operation phase
is HUDA Supply.
Black and Grey water
treatment and reuse.
Awareness Campaign to
reduce the water
consumption
No significant impact on
surface/ground water
quantity envisaged.
In an unlikely event of
non-availability of water
supply, water will be
brought using tankers.
3. Surface Surface water Construction Phase Silt traps and other No off-site impact
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 77
Water Quality contamination Surface runoff from
site during construction
activity.
measures such as
additional on site diversion
ditches will be constructed
to control surface run-off
during site development
envisaged as no surface
water receiving body is
present in the core
zone.
Operation Phase
Discharge of domestic
wastewater to STP.
Domestic water will be
treated in STP
No off-site impact
envisaged
Excess of water will be
used for irrigation
purposes outside the
project site after proper
treatment. CPCB
standards for usage of
treated waste water for
irrigation purposes will
be followed.
4. Air Quality Dust Emissions Construction Phase
All heavy construction
activities
Suitable control measures
will be adopted for
mitigating the PM2.5& PM10
level in the air as per air
pollution control plan.
Not significant because
dust generation will be
temporary and will
settle fast due to dust
suppression techniques.
During construction
phase the contractors
are advised to facilitate
masks for the labors.
Water sprinklers will be
used for suppression of
dust during construction
phase.
Emissions of
PM2.5 & PM10,
SO2, NOx and
Construction Phase
Operation of
Rapid on-site
construction and improved
maintenance of equipment
Not significant. Regular monitoring of
emissions and control
measures will be taken
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 78
CO construction
equipment and
vehicles during site
development.
Running D.G. set (back
up)
to reduce the emission
levels.
Operation Phase
Power generation by
DG Set during power
failure
Emission from
vehicular traffic in use
Use of low sulphur diesel
if available
Providing footpath and
pedestrian ways within
the site for the residents
landscape development
with tree plantation will
be developed with
specific species to help to
reduce PM2.5& PM10 level
Use of equipment fitted
with silencers
Proper maintenance of
equipment
Not significant.
DG set would be used as
power back-up (approx
6 hours)
No significant increase
in ambient air quality
level is expected from
the proje t’s a ti ities.
There are no sensitive
receptors located within
the vicinity of site.
Use of Personal
Protective
Equipment (PPE) like
earmuffs and
earplugs during
construction
activities.
Stack height of DG
set above the tallest
building as per CPCB
standards
5. Noise Environment
Operation Phase
Noise from vehicular
movement
Landscape development
Development of silence
zones to check the traffic
No significant impact
due to prominent
landscape
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 79
Noise from DG sets
operation
movement
Provision of noise
shields near the heavy
construction operations
and acoustic enclosures
for DG set.
Construction activity will
be limited to day time
hours only
DG set will be equipped
with acoustic enclosures
6. Land
Environment
Soil
contaminatio
n
Construction Phase
Disposal of
construction debris
Construction debris will
be collected and suitably
used on site as per the
solid waste management
plan for construction
phase
No significant impact.
Impact will be local, as
waste generated will
be reused for filling of
low lying areas etc.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 80
Operation Phase
Generation of
municipal solid waste
Used oil generated
from D.G. set
It is that the solid
waste generated will be
managed as per MSW
Rules, 2000 and amended
Rules, 2008.
Collection, Segregation,
transportation and
disposal will be done as
per MSW Management
Rules, 2000 by the
authorized agency
Used oil generated will
be sold to authorized
recyclers
Since solid waste is
handled by the
authorized agency,
waste dumping is not
going to be allowed.
Not significant.
Negligible impact.
7. Biological
Environment
(Flora and
Fauna)
Displacement
of Flora and
Fauna on site
Construction Phase
Site Development
during construction
Important species of
trees, if any, will be
identified and marked
and will be merged with
landscape plan
The site has shrubs as
vegetation
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 81
Operation Phase
Increase in green
covered area
Suitable landscape
development with tree
plantation will be
developed as per
landscaping plan in and
around the site using
local flora
Beneficial impact
8. Socio-
Economic
Environment
Population
displacement
and loss of
income
Construction Phase
Construction activities
leading to relocation
Earmarked for Residential
purpose as per Gurgaon-
Manesar Urban Complex-
2031
No negative impact
Operation Phase
Site operation
Project will provide
employment
opportunities to the local
people in terms of labor
during construction and
service personnel
(guards,securities,
gardeners etc) during
operations
Providing quality-
Integrated infrastructure.
Beneficial impact
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 82
9. Traffic
Pattern
Increase of
vehicular
traffic
Construction Phase
Heavy Vehicular
movement during
construction
Heavy Vehicular
movement will be
restricted to daytime only
and adequate parking
facility will be provided
No negative impact
Operation Phase
Traffic due to
residentsonce the
project is operational
Vehicular movement
will be regulated inside
the project with
adequate roads and
parking lots in the
colony.
No major significant
impact as landscape
development with tree
plantation will be
developed which will
help in minimizing the
impact on
environment.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 83
EMP FOR AIR ENVIRONMENT DURING CONSTRUCTION PHASE:
To mitigate the impacts of PM10& PM2.5 during the construction phase of the project, the
following measures are recommended for implementation:
A dust control plan
Procedural changes to construction activities
Dust Control Plan
The most cost-effective dust suppressant is water because water is easily available on
construction site. Water can be applied using water trucks, handled sprayers and automatic
sprinkler systems. Furthermore, incoming loads could be covered to avoid loss of material in
transport, especially if material is transported off-site.
Procedural Changes to Construction Activities
Idle Time Reduction: Construction equipment is commonly left idle while the operators are on
break or waiting for the completion of another task. Emission from idle equipment tends to be
high, since catalytic converters cools down, thus reducing the efficiency of hydrocarbon and
carbon monoxide oxidation. Existing idle control technologies comprises of power saving mode,
which automatically off the engine at preset time and reduces emissions, without intervention
from the operators.
Improved Maintenance: Significant emission reductions can be achieved through regular
equipment maintenance. Contractors will be asked to provide maintenance records for their
fleet as part of the contract bid, and at regular intervals throughout the life of the contract.
Incentive provisions will be established to encourage contractors to comply with regular
maintenance requirements.
Reduction of On-Site Construction Time: Rapid on-site construction would reduce the duration
of traffic interference and therefore, will reduce emissions from traffic delay.
EMP FOR AIR ENVIRONMENT DURING OPERATION PHASE:
To mitigate the impacts of pollutants from DG set and vehicular traffic during the operational
phase of the Colony, following measures are recommended for implementation:
DG set emission control measures
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 84
Vehicular emission controls and alternatives
Landscape development
Diesel Generator Set Emission Control Measures
Adequate stack height will be maintained to disperse the air pollutants generated from the
operation of DG set to dilute the pollutants concentration within the immediate vicinity. Hence,
no additional emission control measures have been suggested.
Vehicle Emission Controls and Alternatives
During construction, vehicles will be properly maintained to reduce emission. As it is a Group
Housing Colony, ehi les ill e ge erally ha i g PCU ertifi ate. Footpaths and Pedestrian ways: Adequate footpaths and pedestrian ways would be provided at
the site to encourage non-polluting methods of transportation.
Landscape Development
Tree plantation is one of the preferred methods to mitigate air and noise pollution. Plants serve
as a sink for pollutants, act as a barrier to break the wind speed as well as allow the dust and
other particulates to settle on the leaves. It also helps to reduce the noise level at large extent.
Table given in green area indicates various species of the trees that can be used to act as a
barrier.
EMP FOR NOISE ENVIRONMENT DURING CONSTRUCTION PHASE:
To mitigate the impacts of noise from construction equipment during the construction phase on
the site, the following measures are recommended for implementation.
Time of Operation: Noisy construction equipment would not be allowed to use.
Job Rotation and Hearing Protection: Workers employed in high noise areas will be employed
on shift basis. Hearing protection such as earplugs/muffs will be provided to those working very
close to the noise generating machinery.
EMP FOR NOISE ENVIRONMENT DURING OPERATION PHASE:
To mitigate the impacts of noise from diesel generator set during operational phase, the
following measures are recommended:
Adoption of Noise emission control technologies
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 85
Landscape development
Noise Emission Control Technologies
It would be ensured that the manufacturer provides acoustic enclosure as an integral part along
with the diesel generators set. Further, enclosure of the services area with 4 m high wall will
reduce noise levels and ensure that noise is at a permissible limit for resident of the site and
surrounding receptors.
EMP FOR ECOLOGICAL ENVIRONMENT DURING CONSTRUCTION PHASE:
Construction activity changes the natural environment. But Group Housing Colony also creates
a built environment for its inhabitants. The project requires the implementation of following
choices exclusively or in combination.
Restriction of construction activities to defined project areas, which are ecologically
sensitive
Restrictions on location of temporary labor tents and offices for project staff near the
project area to avoid human induced secondary additional impacts on the flora and fauna
species
Cutting, uprooting, coppicing of trees or small trees if present in and around the project
site for cooking, burning or heating purposes by the labors will be prohibited and suitable
alternatives for this purpose will be made
Along with the construction work, the peripheral landscape development with tree
plantation would be developed with suggested native plant species, as they will grow to a
full-fledged covered at the time of completion.
EMP FOR ECOLOGICAL ENVIRONMENT DURING OPERATION PHASE:
Improvement of the current ecology of the project site will entail the following measures:
Plantation and Landscaping
Landscape development with tree plantation
Park and Avenue Plantation
The section below summarizes the techniques to be applied to achieve the above objectives:
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 86
Plantation & Landscaping
Selection of the plant species would be done on the basis of their adaptability to the existing
geographical conditions and the vegetation composition of the forest type of the region earlier
found or currently observed.
Tree Plantation Plan
The plantation matrix adopted for the tree plantation includes pit of 0.3 m × 0.3 m size with a
spacing of 2 m x 2 m. In addition, earth filling and manure may also be required for the proper
nutritional balance and nourishment of the sapling. It is also recommended that the plantation
has to be taken up randomly and the landscaping aspects could be taken into consideration.
Multi-layered plantation comprising of medium height trees (7 m to 10 m) and shrubs (5 m
height) are for the landscape development with tree plantation. In addition creepers will be
planted along the boundary wall to enhance its insulation capacity.
Selection of Plant Species for Tree Plantation
The selection of plant species for the development depends on various factors such as climate,
elevation and soil. The plants would exhibit the following desirable characteristics in order to be
selected for plantation
1. The species should be fast growing and providing optimum penetrability
2. The species should be wind-firm and deep rooted
3. The species should form a dense canopy
4. As far as possible, the species should be indigenous and locally available
5. Species tolerance to air pollutants like SO2 and NOx should be preferred
6. The species should be permeable to help create air turbulence and mixing within the belt
7. There should be no large gaps for the air to spill through
8. Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces
9. Ability to withstand conditions like inundation and drought
10. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter)
11. Attractive appearance with good flowering and fruit bearing
12. Bird and insect attracting tree species
13. Sustainable green cover with minimal maintenance.
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 87
Parks and Avenue Plantation
Parks and gardens maintained for recreational and ornamental purposes will not only
improve the quality of existing ecology at the project site but also will improve the
aesthetic value.
Avenue Plantation
1. Trees with colonial canopy with attractive flowering
2. Trees with branching at 7 feet and above
3. Trees with medium spreading branches to avoid obstruction to the traffic
4. Fruit trees to be avoided because children may obstruct traffic and general movement of
public.
EMP FOR SOCIO-ECONOMIC ENVIRONMENT:
The social management plan has been designed to take proactive steps and adopt best
practices, which are sensitive to the socio-cultural setting of the region. The Social Management
Plan for Group Housing Colony project focuses on the following components:
Income Generation Opportunity During Construction and Operation Phase
The project would provide employment opportunity during construction and operation
phase. There would also be a wide economic impact in terms of generating opportunities
for secondary occupation within and around the complex. The main principles considered
for employment and income generation opportunities are out lined below:
a) Employment strategy will provide for preferential employment of local people.
b) Conditions of employment would address issues like minimum wages and medical care
for the workers. Contractors would be required to abide to employment priority
towards locals and abide by the labor laws regarding standards on employee terms
and conditions.
Improved Working Environment for Employees
The project would provide safe and improved working conditions for the workers employed
at the facility during construction and operation phase. With the ambience and facilities
provided, the complex will provide a new experience in living and recreations. Following
measures would be taken to improve the working environment of the area:
a) Less use of chemicals and biological agents with hazard potential
Extension of Environment Clearance
Group Housing Colony Project
M/s Jasmine Buildmart Pvt. Ltd.
Village- Gwal Pahari, Sector -3, District- Gurgaon, Haryana CONCEPTUAL PLAN
Prepared by: Vardan EnviroNet, Gurgaon Page 88
b) Developing a proper interface between the work and the human resource through a
system of skill improvement
c) Provision of facilities for nature care and recreation e.g. indoor games facilities
d) Measures to reduce the incidence of work related injuries, fatalities and diseases
e) Maintenance and beautifications of the complex and the surrounding road