Explain The Concept of Resource Related Billing
Please explain to me the concept of resource related billing and its different
between periodic and milestone. In what kind of business scenario do we use it?
and what are the settings required to use it?
Periodic billing is used when you want to bill the customer at different points of time based
on the periodicity or progress of the work.
Milestone billing can be used for this type of billing purposes when you want to have
billing control from the project.
Resource billing is based on the resource consumption for the particular activities.
Dynamic Item Processor (DIP) profile is used for the resource related billing.
Steps to be followed:
1) Configure DIP Profile (T.code ODP1)
2) Specify the usage -
(i) Billing & Result Analysis (RRB)
(ii) Request Quotation (Sales Pricing)
3) Specify -
(i) Sales Document Type (PS2)
(ii) SD Doc Type CMR
4) In Sales Order Type --> Sales Order Category - "L" (Debit Memo Request)
5) Document Pricing Procedure --> PS (Customer Project)
6) Select the billing usage and click on characteristics. eg--> Activity Type
7) Then define sources. Select "Actual Cost" as we use actual cost for RRB. Define%
8) Sources --> Selection Criteria: This would display all characteristics. Now in Activity
Type --> Mention the activity type
9) If more activity type are being used then create set of activity type using T.code GS01
10) Material Determination --> Initially create material with "Material Type = Service"
11) The service material should be mentioned in the material determination
12) Criteria -- In criteria allocate the activity type for the specific material. (We can also
use cost element, cost center, which we have defined in characteristics)
13) Create Project (T.code CJ20N)
14) Create Sales Order (T.code VA01)
Explain The Concept of Resource Related Billing http://www.erpgreat.com/sap-sd/explain-the-concept-of-resource...
1 of 3 04/09/2014 16:34
15) Book CATS
16) Execute DP91 to view Sales Pricing
Common Errors:
AD01-155: Error during material determination for sales document item. Material
Origin field was not checked in the Costing tab of the material master.
IX-057: No cost management is provided for sales document (contract) item. This is
usually because there is no requirements type assigned to the contract item (see
procurement tab).
No material appears in DMR/CMR. In the material master costing view, set the
"Material Origin" checkbox (see OSS note 174382)
No expenditure item found.
Go back to the service order and check there are actual costs
Check your DIP Profile; specifically the sources section to ensure you are not filtering out
any dynamic items.
CO Configuration:
KL03: Check activity type validity dates
KA03: Check cost element validity dates
KA03: For labour, check cost element category is 43
KA03: Check if Record qty flag is set on Indicators tab
KA03: Check cost element assigned to your controlling area
KP26: Check that activity type is linked to cost centre
KP26: Check that there is a rate for the activity type/cost centre
KP26: Check are you using the correct version
Get help for your SAP SD problems
SAP SD Forums - Do you have a SAP SD Question?
SAP Sales and Distribution Books
SAP SD Books - Certification, Interview Questions and Configuration
Delivery Hints
SAP Logistics Execution
SAP Sales and Distribution Tips
SAP SD Discussion Forum and Sales/Distribution Tips
Best regards,
Explain The Concept of Resource Related Billing http://www.erpgreat.com/sap-sd/explain-the-concept-of-resource...
2 of 3 04/09/2014 16:34
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies. The site www.erpgreat.com is in no
way affiliated with SAP AG.
Every effort is made to ensure the content integrity. Information used on this site is at your own risk.
The content on this site may not be reproduced or redistributed without the express written
permission of
www.erpgreat.com or the content authors.
Explain The Concept of Resource Related Billing http://www.erpgreat.com/sap-sd/explain-the-concept-of-resource...
3 of 3 04/09/2014 16:34