Upload
doanminh
View
215
Download
0
Embed Size (px)
Citation preview
ROMANIANational Commission for Nuclear Activities Control
Experience of CNCAN in Licensing the First CANDU NPP
Dr. Lucian BIRO Nuclear Safety and Security Senior Expert
TM/WS on the Introduction of Nuclear Power Programmes:Management and Evolution of a National Infrastructure
Vienna, 8-11 Fe3bruary 2011
2
Historical BackgroundSpecifics of Regulatory EnvironmentLegislation and Regulations BasisPSAR & FSAR ContentReview BasisCNCAN Concept for Licensing ProcessCNCAN Regulatory Review ObjectivesCommissioning & Licensing ProcessLicensing Steps for Cernavoda 1 NPP Important Plant Programs as Support for
Licensing ProcessConclusions
Contents
3
Historical Background (1)
Year Event
1971 Institute for Nuclear Technologies (ITN) have been established;
1972 Nuclear regulatory commission (ISCAN-AC) has been set up;
1975 Nuclear safety regulation have been issued;
1976 Physical protection regulation have been issued;
1977 Institute for Nuclear Power Reactors (IRNE);
1980 Construction of Cernavoda NPP started with 5 units in the same time;
4
Year Event1982 Quality Assurance Law was issued;1983 QA Regulations started to be issued one by one;
1990 ISCAN-CAN was transformed in the National
Commission for Nuclear Activities Control (CNCAN);
1994 CNCAN/AECB – Canada Contract in place for 3 years
1996 First criticality of the Cernavoda #1 NPP; New Nuclear Act (Law No. 111/1996);
1997 Construction of Cernavoda U2 NPP stopped;
2001 The Law on third party liability in the case of
nuclear damages; Construction of Cernavoda U2 NPP restarted; New Physical Protection regulations in force;
Historical Background (2)
5
Year Event
2007 CNCAN issued the Operation Licence for
Cernavoda NPP #2; CNNP #2 at full power.
2010 EC DG Energy positive opinion have been issued for Cernavoda NPP units 3&4 construction
Historical Background (3)
6
Cernavoda NPP
Construction started in 1980 with 5 units;U1 - Full Power: December 1996;U2 - Full Power: September 2007;U3 - Full Power: 2017;U4 - Full Power: 2018;U5 – Project stopped.
7
Romania has two units in operation and two unitsunder construction, on Cernavoda site, a CANDU-6 type reactor
CNCAN regulatory approach is a prescriptiveorientated one
The Operating License is issued for 2 years
The two years license renewal cycle will takes intoconsideration the regulatory assessment on thestatus of the actions developed by the utility toimplement the regulatory requirements anddispositions
Specifics of Regulatory Environment
8
CNCAN Responsibilities
By Law CNCAN is responsible for:
Nuclear Legislation & RegulationsNuclear SafetyRadiation ProtectionQuality AssuranceSafeguardsEmergency PreparednessPhysical ProtectionNuclear and Radiological SecurityNuclear LiabilityTransportationRadioactive Waste ManagementOperators CertificationInternational Treaties and Conventions
9
Romanian Legislations and Regulations
IAEA NUSS series of standards;
US 10 Code of Federal Regulations;
ASME Code Provisions;
Canadian Regulations & Practices;
ICRP Recommendations;
The experience of the countries with developednuclear energy;
Legislation and Regulations Basis
10
Regulatory Requirements, Criteria and Conditions
Law
Regulations,Standards and Codes
Regulatory letters+
licensee’s documents previously approved by CNCAN (such as Safety Analysis Reports, Management Manuals, etc.)
CNCAN dispositions and actions stated in the inspection reports
+licensee’s procedures previously approved by CNCAN(such as reference documents, station instructions, etc.)
11
Civil constructionCivil construction
Licensing proceduresLicensing procedures
Radiological securityRadiological security
TransportTransport
DecommissioningDecommissioning
RadioprotectionRadioprotection
Quality managementQuality management
Radioactive contaminationRadioactive contamination
Radwaste managementRadwaste management
Physical protectionPhysical protection
Civil constructionCivil construction
Licensing proceduresLicensing procedures
Radiological securityRadiological security
TransportTransport
DecommissioningDecommissioning
RadioprotectionRadioprotection
Quality managementQuality management
Radioactive contaminationRadioactive contamination
Radwaste managementRadwaste management
Physical protectionPhysical protection
Civil constructionCivil construction
Licensing proceduresLicensing procedures
Radiological securityRadiological security
TransportTransport
DecommissioningDecommissioning
RadioprotectionRadioprotection
Quality managementQuality management
Radioactive contaminationRadioactive contamination
Radwaste managementRadwaste management
Physical protectionPhysical protection
Civil constructionCivil construction
Licensing proceduresLicensing procedures
Radiological securityRadiological security
TransportTransport
DecommissioningDecommissioning
RadioprotectionRadioprotection
Quality managementQuality management
Radioactive contaminationRadioactive contamination
Radwaste managementRadwaste management
Physical protectionPhysical protection
CNCAN Regulations
12
Chapter 1: Introduction and general description of the NPP Chapter 2: Site characteristics Chapter 3: Design of structures, components, equipment
and systems Chapter 4: Reactor Chapter 5: Reactor Coolant System Chapter 6: Safety Systems Chapter 7: Instrumentation and Control Chapter 8: Electrical Power Chapter 9: Auxiliary Systems Chapter 10: Turbine & Electrical Generator Chapter 11: Radioactive Waste Management Chapter 12: Radiation Protection Chapter 13: Conduct of Operations Chapter 14: Initial Test Program Chapter 15: Accident Analysis Chapter 16: Operating Policies and Principles Chapter 17: Quality Assurance
PSAR & FSAR Content
14
CNCAN Concept for Licensing Process
Level of Excellence
Minimum Level
Acceptable Level
Requirements Level
Operation Domain
No
Lice
nseMargins
Lice
nse
Level of CNCAN Requirementsfor Operation License
CNCAN Requirements meet by Licensee
CNCAN assessment of NPP status and regulatory requirements for corrective actions
Plant corrective actions implementation
15
to check and to assess that safety regulations andfactors affecting safety have been adequatelycovered
to check the adequacy and acceptability of theaccident analysis
to review safety margin in operation
to review “as-built” plant configuration againstinitial design
to review plant organizational structure andprocedures
to define license conditions, if any
CNCAN Regulatory Review Objectives
16
Phase "A": Non-nuclear tests for individual systems
Phase "B": Reactor physics tests
Phase "C": Integral tests for whole plant at various power level. Includes the process of reactor power run-up from 0 to
100% of full power. It starts with the completion of phase"B" commissioning
Phase "D": Conforms completion of commissioning phase. includes
the process of reactor power run-up at 100% of full powerto perform guarantee tests etc. Preparation for plantcommercial operation.
Commissioning & Licensing Process
Site approval
Based on Initial Safety Assessment Report
site evaluation from the safety point of view exclusion area low population zone seismology geology meteorology hydrology demographic social and human activities characteristics
censing Steps for Cernavoda 1 NPP (1)
Construction Permits for NPP Systems (1980 - 1993)
“System-by-system” approach;
Based on safety documentation made by applicantfor particular constructions and systems;
Based on Safety Systems Classification List;
censing Steps for Cernavoda 1 NPP (2)
Final Construction License(19 August 1993)
Based on: Complete PSAR Status of work to conclude the Construction Licensing
Process (Utility Report) CNCAN Inspections
Commissioning License No. 1/1995(15 May 1995)
Based on FSAR Phase I; Licensing procedures: Level I Schedule for Commissioning Process; CNCAN Level II requirements for Licensing Activities
censing Steps for Cernavoda 1 NPP (3)
Commissioning License No. 1/1995Rev. 1/29.05.1996
Based on:
updated information resulted from supplementary safetydocuments and the Commissioning CompletionAssurance process results and status;
Compliance with the generic licensing procedures andFSAR Phase I.
censing Steps for Cernavoda 1 NPP (4)
Probationary Operation License(July 31.1997)
Based on:
FSAR Phase II; Licensing procedures:
Level I Schedule for Commissioning Process; CNCAN Level II requirements for Licensing Activities.
Supplementary safety documents Commissioning Reports results Plant status CNCAN inspections results
censing Steps for Cernavoda 1 NPP (5)
Operation License(May.1999)
Based on:
Plant status CNCAN inspections results
censing Steps for Cernavoda 1 NPP (6)
Station Improvements Program.Radiation Protection ProgramRadioactive Waste Management ProgramEffluent and Environmental Monitoring ProgramsALARA ProgramEmergency Preparedness and Response ProgramChange Control ProgramReliability ProgramQuality Assurance ProgramTraining ProgramPlant Surveillance and Reporting Programs
mportant Plant Programs as Support for Licensing Process (1)
Periodic Inspection ProgramMaintenance and Maintenance Support ProgramsFire Protection ProgramSafeguards ProgramHousekeeping and Plan Material Condition
ProgramSignificant events for nuclear safety analysisProbabilistic Safety Analyses ProgramR&D ProgramSystematic Review of Spare Parts ProgramOrganization structure & administrative issues.
mportant Plant Programs as Support for Licensing Process (2)
m Milestone DateAcquire & Store Heavy Water AD 09.12.2005Commissioning License CL 08.10.2006Acquire & Store Fuel AF 14.10.2006Load Fuel LF 14.02.2007Load Heavy Water Into PHT System HD 01.03.2007
Hot Performance HP 24.03.2007First Criticality CR 04.05.2007Power Increase to 5 %FP PI 27.06.2007Raise Power above 25 %FP PP1 03.07.2007
0 Raise Power above 50 %FP PP2 15.08.2007R i P b 75 %FP PP3 21 08 2007
CNPP #2- Licensing Milestone -
19 20 21 22 23 24 25 26 27 28 29 30 30 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2005 2006 2007
T/O 66400 Station Control Computers (DCCs)T/O 55000 Class 1 & 2 UPS
T/O 51340 TO5 (SST)T/O 75120 Instrument Air
T/O 71310 Raw Service Water (RSW)T/O 71340 Recirculated Cooling Water (RCW)
T/O 33100 Main Heat Transport CircuitT/O 68300 Shutdown System No 1T/O 43230 Main Feedwater Circuit
TURNOVERS (Current Forecast)
COMMISSIONING CONTROL POINTS (To Be Confirmed) AD - Aquire and Store D2O
AF - Aquire and Store Nuclear Fuel
MD - Moderator Fill with D2OLT - Reactor Building Leak Rate Test
HC - Hot Conditioning
PF - Power Failure (Loss of Class 4 Power Test)LF - Load Fuel
HD – PHT Fill with D2O
CR First Reactor Criticality (Start Phase B)
Cernavoda 2 Commissioning Targets
16 17 18
Jul Aug Sep
T/O 51340 TO6 (SST)
COMMISSIONING PROCEDURE PREPARATION
COMMISSIONING EXECUTION PROCESSES
T/O 67885 Post Accident Monitoring
HP- Hot Performance Tests with D2O
COMMISSIONING COMPLETION ASSURANCE
49 50
Apr May
Commissioning Targets
Conclusions (1)
Nuclear power program in Romania started in
60’s;
The integration factor of the foreign nuclear
technologies in the Romanian industry was
quite high;
CANDU 6 Nuclear Fuel Technology fully
implemented in Romania;
V d d R i l f l
Conclusions (2)
The Romanian Heavy Water Plant produce the
heavy water with high quality;
The national capabilities in the nuclear sector
are well maintain;
CNCAN approach in the regulatory business is a
prescriptive one;
Conclusions (3)
The main actors of the Romanian nuclear
sector promote a large international
cooperation;
The international cooperation is extensively
followed by Romania;
The IAEA Missions (OSART, IRRS, INSAR,
SEDO, SCART etc.) are well received by the