33
Exhibit A RFP- GM-85872 STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine Ray D. Nixon Power Plant, Fountain, CO Page 1 of 33 1.0 Introduction Colorado Springs Utilities is seeking CONTRACTOR(s) to provide supervision, labor, materials, equipment, supplies, design, and facilities to provide material, labor, supervision, tools, equipment (including forklift), supplies, facilities and services required to perform the Measurement and Inspection of HP/IP/LP Turbine as detailed in this document (Work). The Work shall be performed as shown in the Drawings, stated in these Specifications, or reasonably implied from them all in accordance with the Contract Documents. The Work in this Package shall be performed on a Firm Price Basis, unless otherwise noted. For the purpose of this document, Colorado Springs Utilities will be referred to as (“UTILITIES”). UTILITIES’ Project Manager will be referred to as (“PM”). CONTRACTOR, individual(s), or companies responding to this solicitation shall be referred to as (“CONTRACTOR”). LOCATION : The Ray Nixon Power Plant is located in the City of Fountain at exit 125, off of I-25. The plant has an elevation of 5,570 feet above sea level. The proper mailing address for the plant is: 6598 Ray Nixon Road, Fountain, CO 80817. 2.0 Scope and Background 2.1 Scope The following description, while not intended to cover all details, outlines the major Scope of Work for the disassembly of Ray D. Nixon’s unit 1 steam turbine and associated auxiliary equipment for a measurement inspection. All materials, tools, and workmanship (except where excluded) in all respects shall be furnished by this CONTRACTOR even though not specifically mentioned in these specifications. CONTRACTOR shall include all labor, materials, transportation costs, storage, equipment, etc., necessary to successfully complete the Work as herein specified. The intent of this scope is to remove the HP/IP & LP rotors. The lower casings and diaphragms will not be removed for the purposes of the measurement inspection; however the end pack casings will need to be removed from the HP / IP section for the measurement inspection. During the course of the inspection the CONTRACTOR shall make repair recommendations on items discovered during the course of the inspection. All repairs not listed in the Statement of Work will be performed on a T&M basis. CONTRACTOR shall provide a detailed schedule with emphasis on the date that the rotors have been removed from both sections (HP/IP & LP) so measurement inspections can commence. CONTRACTOR will have

Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 1 of 33

1.0 Introduction Colorado Springs Utilities is seeking CONTRACTOR(s) to provide supervision, labor, materials, equipment, supplies, design, and facilities to provide material, labor, supervision, tools, equipment (including forklift), supplies, facilities and services required to perform the Measurement and Inspection of HP/IP/LP Turbine as detailed in this document (Work). The Work shall be performed as shown in the Drawings, stated in these Specifications, or reasonably implied from them all in accordance with the Contract Documents. The Work in this Package shall be performed on a Firm Price Basis, unless otherwise noted. For the purpose of this document, Colorado Springs Utilities will be referred to as (“UTILITIES”). UTILITIES’ Project Manager will be referred to as (“PM”). CONTRACTOR, individual(s), or companies responding to this solicitation shall be referred to as (“CONTRACTOR”). LOCATION: The Ray Nixon Power Plant is located in the City of Fountain at exit 125, off of I-25. The plant has an elevation of 5,570 feet above sea level. The proper mailing address for the plant is: 6598 Ray Nixon Road, Fountain, CO 80817. 2.0 Scope and Background

2.1 Scope The following description, while not intended to cover all details, outlines the major Scope of Work for the disassembly of Ray D. Nixon’s unit 1 steam turbine and associated auxiliary equipment for a measurement inspection. All materials, tools, and workmanship (except where excluded) in all respects shall be furnished by this CONTRACTOR even though not specifically mentioned in these specifications. CONTRACTOR shall include all labor, materials, transportation costs, storage, equipment, etc., necessary to successfully complete the Work as herein specified. The intent of this scope is to remove the HP/IP & LP rotors. The lower casings and diaphragms will not be removed for the purposes of the measurement inspection; however the end pack casings will need to be removed from the HP / IP section for the measurement inspection. During the course of the inspection the CONTRACTOR shall make repair recommendations on items discovered during the course of the inspection. All repairs not listed in the Statement of Work will be performed on a T&M basis. CONTRACTOR shall provide a detailed schedule with emphasis on the date that the rotors have been removed from both sections (HP/IP & LP) so measurement inspections can commence. CONTRACTOR will have

Page 2: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 2 of 33

limited access to the steam turbine during the measurement inspection, which will take seven (7) working days from the date of commencement.

2.2 Background The turbine is a General Electric Model Type D-5, 3600 RPM, tandem compound reheat unit with a double-flow low pressure section. The high pressure and reheat stages are housed in an area with double shell construction. The HP section consists of eight (8) stages and the reheat section (IP) consists of six (6) stages. The HP/IP rotor is approximately 19 feet-8 inches long, weighs 31,877 pounds and has a 55 11/16-inch diameter at its widest point. The LP section consists of twelve (12) stages. The LP rotor is 21 feet 10-1/2 inches long, weighs 58,000 pounds, and is 8 feet 2 ¼ inches at its widest diameter. Unit Serial No. is 180X743. The unit has been in service since 1980 and has approximately 260,000 operating hours. The last outage that took place on the HP/IP section was 2007 and the LP section in 2005. The unit will be removed from service the evening of Friday, March 4, 2011 and the anticipated on-line date is Monday, April 4, 2011. The Work covered under this scope is scheduled to begin on Monday, March 7, 2011, with a scheduled completion date of April 3, 2011, @ 11:59 PM. The Work described herein will be performed on a turnkey basis. CONTRACTOR must be able to demonstrate the necessary qualifications as outlined in Section 3.8. If CONTRACTOR decides to subcontract any of the items outlined in this section, they must provide a list of subcontractors that would be used to complete the Work. All subcontractors are subject to UTILITIES approval.

3.0 Tasks & Deliverables 3.1 Mobilization / Site Preparation The following activities provide general guidelines for CONTRACTOR tasks prior to start of Work. This list is not all inclusive. CONTRACTOR shall follow Prudent Industry Practices during mobilization and site preparation for the work described herein. CONTRACTOR shall include mobilization activities in Work Schedule. CONTRACTOR shall include the cost of the assigned Project Manager to attending a mandatory coordination meeting on site at 9:00 AM local time on January 6, 2011. Person attending meeting must be the same person managing project on site. Failure to attend meeting by designated Project Manager will be considered a breach of Contract. CONTRACTOR shall be mobilized and prepared to begin Work by March 7, 2011. Mobilization activities include at a minimum, the following:

Page 3: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 3 of 33

1. Set up storage space for tools, rigging, and equipment 2. Set up office trailer 3. Set up area for blast cleaning and nondestructive testing 4. Pre-Outage shut down checks 5. Locate and inspect special turbine tools 6. Set up bolt heaters 7. Set up hose and cable bridges 8. Set up rotor stands 9. Set up flat bed trailers for storage of large parts 10. Set up barriers around valve access holes 3.2 Disassembly / Inspections The information below is intended for reference only and should not be construed as a complete procedure. The intent of this scope is to remove the HP/IP & LP rotors. The lower casings and diaphragms will not be removed for the purposes of the measurement inspection; however the end pack casings will need to be removed from the HP / IP section for the measurement inspection.

3.2.1 Prior to disassembly, CONTRACTOR shall perform the following tasks.

3.2.1.1 Use feeler gauges to measure gap between upper and lower casing and record results as part of the pre-disassembly inspection. Results will be documented on diagram of steam turbine casing.

3.2.1.2 CONTRACTOR will inspect casing bolts for looseness, and document results on drawing of steam turbine casing diagram.

3.2.1.3 Immediately after complete disassembly, CONTRACTOR shall handwork the horizontal joint of casings and re-assemble upper and lower casings without internals. Dimensional readings will be taken on all fits and all stages to check roundness of assembled casing halves. A blue check of split line will also be performed to further examine casing for distortion. CONTRACTOR will document results using digital photographs and provide narrative description of findings.

3.2.1.4 Take and record rotor radial position checks at T1, T2, T3 and T4 oil deflector fits before and after breaking coupling.

3.2.2 The following disassembly procedures are intended to

provide CONTRACTOR with a reference and general outline

Page 4: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 4 of 33

of the Work to be performed. CONTRACTOR shall reference OEM disassembly procedures, draw upon its own experience, and follow prudent industry practices to carry out this scope of Work.

I. BREAK "A" COUPLING AND CHECK ALIGNMENT

a. Remove coupling guard and windage covers b. Cap oil spray feed line c. Fabricate and install shaft centering device and

temporary thrust d. Locate shell jacking devices e. Check coupling run out prior to loosening studs. f. Locate, clean and mic alignment pins and temporary studs g. Loosen and remove coupling studs and install temporary

studs and pins h. Loosen and remove temporary coupling studs i. Install shell jacking device j. Jack shell to break coupling k. Maintain bearing lubrication l. Center rotors in bearings m. Take "A" coupling check - 16 point face, 4 point rim. n. Take and record rotor radial position checks at T1,

T2, T3 and T4 oil deflector fits before and after breaking coupling

o. Take and record rotor axial position relative to shell and standard

p. Cover bearing drain and feed lines. II. REMOVE HP-IP and LP UPPER OUTER SHELL

a. Remove gib key access cover and circular gib keys b. Remove HP-IP shell to #1 standard upper gib keys c. Remove HP-IP shell to #2 standard upper gib keys d. Remove shell thermocouples and pressure taps e. Loosen and remove vertical and horizontal joint bolts

and dowels on upper packing casings f. Remove upper half packing casings g. Take and record shell to rotor radial and axial position

checks at N1 and N3 before and after installing tops off keys(1)

h. Clean, mic, and install tops off keys i. Heat and loosen HP-IP-LP shell horizontal joint studs

Page 5: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 5 of 33

j. Remove lower nuts and washers, and remove studs as required

k. Heat, loosen, and remove upper steam lead flange studs l. Set up cribbing for landing HP-IP-LP shells m. Take horizontal joint feeler check and record.(1) n. Jack shell to break joint and to clear the fits and inlet pipes o. Rig and remove outer upper shell with proper rigging (2) p. Record N1 and N3 shell to rotor position after

removing upper outer shell q. Remove joint studs from HP-IP & LP shell and move

studs to cleaning area r. Cover inlet, extraction, and exhaust lines

III. REMOVE HP - IP & LP UPPER INNER SHELLS a. Heat and loosen HP-IP & LP inner shell horizontal joint studs b. Remove nuts and washers c. Take horizontal joint feeler check d. Jack shell(s) to break joint and clear fits and keys e. Rig and remove upper inner shell(s) f. Remove studs from inner shell(s) g. Cover horizontal joint(s) with plywood h. Cover inlet, extraction, and exhaust lines

IV. DISASSEMBLE #1 STANDARD AND COMPONENTS

a. Remove sufficient components to allow HP-IP & LP rotor removal b. Remove joint dowels c. Remove instrumentation d. Loosen and remove oil deflector e. Loosen and remove joint bolting f. Rig and remove #1 standard cover g. Remove governor table h. Disconnect electrical components (UTILITIES TO PERFORM) i. Disconnect control linkage to standard cover j. Remove supervisory instrumentation and control

devices (UTILITIES TO PERFORM.

Page 6: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 6 of 33

k. Loosen and remove pump casing dowels and joint bolting l. Rig and remove upper pump casing m. Cap open oil line and cover drain lines n. Remove lower half oil deflector

V. REMOVE #2 STANDARD COVER

a. Disconnect thrust bearing wear detector piping b. Remove vibration detectors c. Loosen and remove upper oil deflector bolting d. Loosen and remove standard dowels and joint bolting e. Break joint. Rig and remove standard cover f. Remove lower half oil deflectors

VI. REMOVE HP - IP & LP BEARINGS and ROTOR,

a. Check and record rotor runout b. Check and record rotor thrust bump and ball fit movement c. Take opening clearance readings d. Disassemble thrust bearing e. Identify, wrap, and store thrust bearing components f. Loosen and remove bolting from bearings and bearing rings g. Rig and remove upper bearing rings and bearings h. Rig and remove HP-IP & LP rotor i. Set rotor in stands j. Rig and remove HP-IP lower bearings and bearing rings

3.3 HP / IP & LP Section(s) – Clean and Inspect

I. CLEAN AND INSPECT HP - IP & LP BOLTING a. Clean threaded area of nuts b. Clean nut and washer faces c. Remove all nuts and washers that do not require drilling d. Clean threaded area of studs e. Clean ends of studs and hole through studs f. Clean threaded area of nuts g. Clean nut and washer faces h. Ultrasonic test studs for defects i. Magnaflux nut and small bolts

Page 7: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 7 of 33

II. CLEAN AND INSPECT HP - IP & LP OUTER SHELL(s)

a. Clean sealing surfaces, fits, bolt hole faces, flange surfaces and key fits

b. Visual inspection of HP-IP & LP upper outer shell c. Clean horizontal joint halves d. Free up outer shell seal rings e. Coat critical surfaces with rust preventative f. Clean and Inspect HP - IP & LP Inner Shell (both halves) g. Clean sealing surfaces, fits bolt hole faces, inlet pipes h. Mic inlet pipes and record dimensions. i. Visually inspect inlet pipes for wear and steam cutting, report

on condition j. Dye penetrant check inlet pipe stellite surfaces and record

condition k. Visually inspect shell fits for crush pin indentations and

steam cutting l. Coat critical surfaces with rust preventative

III. CLEAN AND INSPECT BEARINGS, THRUST BEARINGS, AND OIL DEFLECTORS

a. Clean all bearing parts and inspect for defects and

dimensions b. Ultrasonic test 100% of babbited surfaces for proper bonding

and map results c. Clean all oil deflectors and inspect for defects and

dimensions d. Blue bearing pads to mandrel, shim as required. e. Blue alignment pads to bearing standard bore fits f. Check pinch and ball seat fit g. Inspect thrust bearing parts for flatness h. Mic thrust bearing tongue and groove fit

IV. DUST BLAST SERVICES

CONTRACTOR will perform dust blasting on components specified in Table 2.3 A. The items listed are not considered to be inclusive of all dust blasting requirements. CONTRACTOR shall set-up temporary booth on steam turbine deck, or other suitable location, to perform all dust blasting work. Temporary area must be sealed sufficiently to prevent dust from escaping booth.

Page 8: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 8 of 33

Aluminum oxide grit size 220 shall be used for dust blasting. Note: Prior to grit blasting the rotor, CONTRACTOR shall completely cover the couplings and all journal areas.

Table 2.3A

Main Steam Flange Main Steam Valve Combined Reheat Valves

1. Bolts 2. Nuts 3. Washers 4. Inlet Pipe Flange Surface

1. Bolts 2. Nuts 3. Washers 4. Stem & Disc 5. Valve Seat

1. Bolts 2. Nuts 3. Washers 4. Stem & Disc 5. Valve Seat

Control Valves HP / IP Rotor HP / IP Rotor – Continued 1. Bolts 2. Nuts 3. Washers 4. Stem & Disc 5. Valve Seat

1. Outer Gland Area – Governor End

2. Balance Plane – Governor End

3. LP Dummy Area End 4. HP Reaction Blades –

Governor End 5. Impulse Blades 6. HP Dummy Area

7. IP Reaction Blades – Generator End

8. Balance Pin – Generator End

9. Outer Gland Area – Generator End

V. COMPONENT EVALUATION.

The following table dictates the minimum necessary component inspections and testing methods. All findings shall be documented and provided to UTILITIES in comprehensive report within 30 days of Work completion. Any inspections findings which exceed design clearances or reveal damage shall be reported to UTILITIES’ designated representative immediately The following abbreviations reference required component inspections as outlined in Table 2.3B. Abbreviations: NDT: Non-destructive Test VT: Visual Test PT: Dye Penetrating Test MT: Magnetic Particle Test UT: Ultrasonic Test DM: Dimension Check

Page 9: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 9 of 33

HP –IP / LP CASING Table 2.3B

Inspection Evaluation NDT (VT, PT, MT, UT) Life Assessment DM of Female Thread / Horizontal Flange DM of upper / lower casing

Wall Thickness Remaining Life Casing Distortion

BOLTS

Inspection Evaluation NDT (VT, PT, UT), HT Damage to Thread

Hardness

SEAL RINGS

Inspection Evaluation NDT (VT, PT), DM Clearance JOURNAL BEARINGS Inspection Evaluation NDT (VT, PT, UT) of White Metal DM of Inner Diameter Clearance THRUST BEARINGS Inspection Evaluation NDT (VT, PT, UT) of White Metal DM of Taper Thrust Plate Clearance TURNING DEVICE Inspection Evaluation NDT (VT) DM Backlash ROTOR Inspection Evaluation NDT (PT, MT) of Wheel Fillet NDT (VT, MT) of Journal / Labyrinth Run-out Check Life Assessment (for HP, IP, & LP Rotor)

Bowing Remaining Life

Page 10: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 10 of 33

COUPLING Inspection Evaluation NDT (VT, PT) of Thread DM of Reamer Bolts Clearance BLADES Inspection Evaluation NDT (VT, PT, MT, UT) DM of Dovetail Clearance DM of Tenon Life Assessment (for HP, IP stages)

Lifting Erosion Remaining Life

SHROUND BANDS Inspection Evaluation NDT (VT, PT, MT) DM of Clearance Lifting EROSION SHIELDS Inspection Evaluation NDT (PT) DM Erosion

3.4 OPTIONAL REPAIR WORK

The following work is anticipated to be performed. Items in Section 3.4 & 3.5 and shall be proposed and priced as options. CONTRACTOR shall follow instructions in Exhibit “B”, Supplier Response Form, when preparing proposal.

3.4.1 REBLADE 10TH STAGE UTILITIES has purchased a complete set of 10th stage turbine blades from OEM. Blades will be coated with GE’s SPE resistant coating. CONTRACTOR will be required to remove existing blades and install new 10th stage turbine blades and associated hardware. All blade work will be performed on-site by CONTRACTOR’s qualified personnel. 3.4.2 PERFORM LOW SPEED DYNAMIC BALANCE ON HP-IP

ROTOR ASSEMBLY CONTRACTOR shall perform an on site low speed dynamic balance on HP-IP rotor assembly after the installation of the 10th Stage buckets. All balance planes must be graphically documented using AutoCAD. Weight maps will identify all existing weights found, all additions or modifications made to each plane, and the

Page 11: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 11 of 33

size and configuration of each weight type. CONTRACTOR will provide detailed report on dynamic balance, which will include but not be limited to, outlines referenced above. Balance specifications will be performed in accordance with ISO 1940/1

3.5 Optional Work - INSPECT AND REPAIR STEAM TURBINE CONTROL

VALVES I. MAIN STOP VALVES

a. Disassemble stop valves b. Unbolt stop valve couplings c. Remove and store coupling spacers d. Unbolt and remove stop valve heads e. Remove stop valve strainers and lower pressure head assemblies f. Disassemble valve stems and disks from lower pressure head.

II. CLEAN / INSPECT STOP VALVE ACTUATORS a. Remove and inspect valve actuators

III. CLEAN / INSPECT STOP VALVE COMPONENTS

a. Remove and clean valve studs, prepare for sonic inspection b. Clean valve stems to restore bushing clearance and to

prepare for sonic inspection c. Check valve stem run-outs d. Blast-clean lower pressure head fits e. Clean stop valve bodies and strainers f. Visually inspect strainers and valves for cracks; inspect seat

contact pattern g. Check valve seats for cracks with penetrant h. Sonic inspect stop valve stems and studs i. Check critical areas of valve stems and disks for cracks with

liquid penetrant. j. Check bushing clearances with try bar k. Measure stem diameter

IV. ASSEMBLE STOP VALVES

a. Assemble valve stems, disks, and lower pressure heads b. Place assembly in stop valve casing c. Check valve; valve seat blue check d. Install stop valve disk and press head assemblies

Page 12: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 12 of 33

e. Install stop valve strainers f. Assemble valve heads and stretch bolting, g. Install stop valve coupling spacers h. Assemble couplings

V. INSPECT CONTROL VALVES

a. Disassemble control valve linkage as required to disassemble valves

b. Disassemble control valve stand, levers, disks, and crossheads as required for inspection

VI. CLEAN / INSPECT CONTROL ACTUATORS

a. Remove and inspect secondary operating cylinder

VII. CLEAN / INSPECT CONTROL VALVE COMPONENTS a. Clean valve studs to prepare for sonic inspection b. Disassemble valve stems and disks c. Clean valve stems to restore bushing clearances and

prepare for sonic inspection d. Check valve stem runouts e. Clean control valve bodies f. Visually inspect valve body for cracks; inspect seat contact g. Check valve seats for cracks with penetrant h. Blast-clean bushing fit areas i. Sonic inspection of control valve stems and studs j. Check critical areas of valve stems and disks for cracks with

liquid penetrant k. Check bushing clearance with try bar l. Measure stem diameter m. Make corrections as necessary n. Perform stem to X-head checks,

VIII. ASSEMBLE CONTROL VALVES AND LINKAGE a. Assemble valve stem, disk, stand and crosshead b. Check valve seat blue check c. Install control valve and stand assembly on control valve body d. Install and stretch bolting, e. Install control valve levers, tension rods, and push rods f. Assemble operator couplings

IX. INSPECT REHEAT VALVES & INTERCEPT VALVES

Page 13: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 13 of 33

a. Disassemble Reheat & Intercept Valves and Linkage b. Unbolt reheat stop valve couplings c. Remove and store coupling spacers d. Remove intercept valve linkage as required to disassemble valves e. Disconnect intercept valve operator couplings f. Remove push rods and tension rods from levers g. Remove intercept valve and head assemblies h. Remove reheat valve strainers and lower press seal head

assemblies i. Remove valve stems, disks, crossheads, and pressure seal heads

X. CLEAN / INSPECT INTERCEPT VALVE ACTUATORS

a. Remove and inspect valve actuators

XI. CLEAN / INSPECT REHEAT & INTERCEPT VALVE COMPONENTS

a. Clean valve studs to prepare for sonic inspection b. Disassemble valve stems and disks c. Clean valve stems to restore bushing clearances and to

prepare for sonic inspection d. Check valve stem runouts e. Blast-clean pressure seal head fits f. Clean stop valve bodies and strainers g. Visually inspect CRV bodies and strainers for cracks; inspect

valve seats for contact h. Check valve seats for cracks with penetrant i. Sonic inspection of CRV stems and studs j. Check critical areas of valve stems and disks for cracks with

liquid penetrant k. Check bushing clearances with try bar l. Measure stem diameter

XII. ASSEMBLE REHEAT & INTERCEPT VALVES AND LINKAGE

a. Assemble stems, disks, and lower pressure heads b. Install lower pressure head assemblies c. Check valve-valve seat blue check d. Repeat for intercept valves and upper pressure heads e. Install reheat stop valve stem and head assembly f. Install Reheat & Intercept Valves strainers g. Install intercept valve and head assembly h. Install and stretch bolting, ES-STM-D3.15.101

Page 14: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 14 of 33

i. Install reheat stop valve coupling spacers and assemble couplings j. Install intercept valve tension rods and push rods k. Assemble intercept operator couplings

XIII. MISCELLANEOUS VALVES BLOWDOWN, VENTILATOR, EQUALIZER VALVES

a. Disassemble b. Clean and inspect c. Reassemble

Note: 1. Fine mesh screen strainers (start-up strainers) will be installed

during valve reassembly. 3.6 HP / IP & LP SECTION CLEAN AND REASSEMBLE CONTRACTOR shall reassemble HP/IP & LP Sections once all Work has been completed. Alignment will be performed in accordance with OEM Specifications. 3.7 TECHNICAL SPECIFICATIONS

3.7.1 GENERAL TECHNIAL SPECIFICATIONS / UNIT HISTORY The following information provides general unit history and technical specifications that should be considered when preparing proposal.

3.7.1.1 Dust blast all buckets (aluminum oxide or possibly glass

beads) to remove: copper, iron, silica, and sodium deposits. 3.7.1.2 NDE (wet magnetic particle testing) of buckets and those

components most susceptible to erosion and stress induced cracking.

3.7.1.3 The N1 and N3 end packing clearances should be 20 mils -0/+5. The N2 packing clearance should be 35 mils -0/+5. The HP and IP inter-stage packing clearances should be set at 20 mils -0/+5.

3.7.2 OEM DESIGN AND SPECIFICATIONS CONTRACTOR shall follow all applicable OEM standards, procedures, and original design specifications during performance of Work. Deviation from original design specifications must be approved in writing by UTILITIES’ designated representative. The following OEM documents will be referenced and applied during the performance of Work. This list is not all inclusive of

Page 15: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 15 of 33

applicable documents applying to Nixon 1 steam turbine (SN 170X743). CONTRACTOR shall conduct review of OEM standards, design, procedures, bulletins, TIL’s, and other relevant documents, to ensure all Work conforms to OEM design.

3.7.2.1 GE Steam Turbine Rotor Technical Documents:

3.7.2.1.1 TIL 630-4 - Periodic Inspection of Last Stage Buckets. 3.7.2.1.2 TIL 689-3 - Cracking of Last Stage Bucket Dovetail Pins 3.7.2.1.3 TIL 1121-3A Inspection of Steam Turbine Rotor Wheel Finger

Dovetails 3.7.2.1.4 TIL 1131-3AR1 Inspection of Steam Turbine Rotor Wheel

Finger Dovetails 3.7.2.1.5 GEK 46354B Maintenance and Inspection of Turbine Rotors

and Buckets 3.7.2.1.6 GEK 63458 Rotor Coupling Inspection

3.7.2.2 GE Steam Turbine Journal Bearing Technical Documents:

3.7.2.2.1 TIL 791 Journal Bearing Alignment 3.7.2.2.2 TIL 930 Improving the Reliability of Journal Bearings 3.7.2.2.3 GEK 72345 Maintenance of Journal Bearings

3.7.2.3 GE Steam Turbine Alignment Technical Documents:

3.7.2.3.1 TIL 880 Turbine Generator Alignment Checks 3.7.2.3.2 TIL 917 Alignment Checks 3.7.2.3.3 GEK 72270 Turbine Rotor Runout Checks 3.7.2.3.4 GEK 63303 Bearing Alignment Diagram

3.7.2.4 GE Steam Turbine HP-IP Casing:

3.7.2.4.1 GEI-40800C – HP Turbine Shell Joint Separation 3.7.2.4.2 GEI-29017C – Lubrication of Shell Ledges Prior for

Disassembling 3.7.2.4.3 GEI-8860C – Diagram for Sequence of Disassembly 3.7.2.4.4 GEI -88723D – Horizontal Joint Stud Tightening 3.7.2.4.5 DWG. 137D3441-Arrangement of Joint Studs 3.7.2.4.6 GEK-37939 – Disassembly of Upper Exhaust Hood, Inner

Casing and Inner Shell 3.7.2.5 GE Steam Turbine Valve Inspection and Maintenance:

3.7.2.5.1 TIL 885 Valve Stem and Bushing Clearances for Fossil Units

Page 16: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 16 of 33

3.7.2.5.2 TIL 891 Valve Studs – Tightening, Inspection, and Replacement Recommendations

3.7.2.5.3 TIL 943 Stop and Control Valve Casing Inspection 3.7.2.5.4 TIL 951 Main Steam Inlet Flange Vibration 3.7.2.5.5 GEK 32969 Power Actuator Maintenance 3.7.2.5.6 GEK 33056 Steam Control Valves and Operating Mechanism 3.7.2.5.7 GEK 37937B Valve Studs – Tightening, Inspection, and

Replacement Recommendations 3.7.2.5.8 GEK 37953 Steam Packing Exhauster 3.7.2.5.9 GEK 41685 Combined Reheat and Intercept Valve 3.7.2.5.10 GEK 72220 Recommendations for Maintenance of Separate

Mounted Fossil Control Valves with Individual Actuators on LSTG Units

3.7.2.5.11 GEK 85252 Stop and Control Valve Casing Inspections 3.7.2.5.12 GEK 72354 Maintenance Operations for Camshaft Operated

Control Valves 3.7.2.5.13 TIL 771-3 Securing of Main Stop Valve Bolts on Fossil and

Nuclear Turbines 3.7.2.5.14 TIL 758-3 Stop Valve Cap Recommendations 3.7.2.5.15 GEK 27039 MSV with Mechanism for Full-Arc Admission

Operation 3.7.2.5.16 GEK 85280 Maintenance of Main Stop Valves for Fossil Units

3.7.3 APPLICABLE STANDARDS AND SPECIFICATIONS 3.7.3.1 All materials and services provided by the CONTRACTOR(s) shall comply with standards from ANSI, IEEE, ASME, ISO, SUTILITIES, NEMA, NFPA, OSHA, and OEM as applicable. 3.7.3.2 All Work on the General Electric machine shall be in accordance with the specifications as set forth In the General Electric Operation and Maintenance Manuals (including all applicable Service Bulletins) unless otherwise stated. UTILITIES will provide CONTRACTOR with all OEM manuals and technical documents to perform Work. However, CONTRACTOR is responsible for obtaining required GE technical documents not in UTILITIES’ possession, which are required to perform Work covered under this Contract.

3.7.4 WORK SCOPE SPECIFICATIONS, TESTS, AND INSPECTIONS

The following specifications, tests, and inspections, are not all inclusive or exhaustive of requirements under this Scope of Work. CONTRACTOR shall follow OEM guidelines and prudent industry practices when performing Work under this contract.

Page 17: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 17 of 33

Note: During pre-outage N2 testing, it was discovered that the HP-IP turbine has steam leakage in excess of 150,000 lbs/hr. Previous outage reports have shown indication of case distortion. Prior to disassembly the CONTRACTOR will perform the following inspections / tests.

3.7.4.1 Pre-Disassembly Checks / Procedures for HP-IP Section

3.7.4.1.1 CONTRACTOR will use feeler gauges to measure the gap along the horizontal split-line on HP-IP casing. Findings will be mapped on casing drawing No. 882E869 REV.2 (Arrangement of Joint Studs) and included in final report. Excessive gap measurements will be reported to UTILITIES’ representative Manny Zeringue or other designated UTILITIES’ representative.

3.7.4.1.2 CONTRACTOR will check for bolt tightness along HP-IP case

horizontal split-line prior to disassembly. Findings will be mapped on casing drawing No. 882E869 REV.2 (Arrangement of Joint Studs) and included in final report.

3.7.4.1.3 Insert hold down support shim, Part #7, prior to unbolting split

line. Reference GEI-69576C, GEI 79468D, and GE drawing number 519C502 (Rev.9) for details on this procedure.

3.7.4.1.4 Remove coupling bolts. 3.7.4.1.5 Take and record rotor thrust measurements prior to

disassembly. A hydraulic jack with a known force must be used when thrusting the rotor. The force to jack the rotor should not exceed 5 tons. Reference GEI-88667 for further instruction.

Note: The thrust bearing, which is located in the front standard, should be left assembled. The thrust bearing will prevent excessive differential movement between the rotor and stationary parts from occurring as the shell and rotor are being jacked.

3.7.4.2 Loosening of Bolts on HP-IP casing

CONTRACTOR shall perform hot loosening of the HP-IP turbine horizontal joint studs and cap nuts. If it is necessary to cut nuts and studs, CONTRACTOR shall notify UTILITIES’ representative Manny Zeringue. Induction heating method is to be used for opening and tightening of horizontal joint bolts. Bolt heater will be provided by CONTRACTOR.

Page 18: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 18 of 33

Indicators must be set up to measure the movements of the shell and HP rotor as they are being jacked. An indicator should also be used to measure any movement of the remaining rotors. If the remaining rotors move, wedges made of hard wood should be used to block the remaining rotors to hold them stationary.

3.7.4.3 Jacking and lifting HP-IP Upper Shell Casing

At a minimum, the following documents shall be referenced for disassembly of casing and lifting rotor: 3.7.4.3.1 GEI-40800C – HP Turbine Shell Joints (Method of Separating

Joints Using Hydraulic Joints) 3.7.4.3.2 GEI-29017C – Lubrication of Shell Ledges Prior to Lifting Outer

Shells in Disassembling 3.7.4.3.3 GEI 88660C - Jacking Device Assembly, Dwg. 915C930 (Rev.

3) 3.7.4.3.4 Key Identification List, Dwg. 206B9603 (Rev.0) 3.7.4.3.5 Gib and Key Clearance, Dwg. 839E891 (Rev.1) 3.7.4.3.6 GEK – 37939, Disassembly of Upper Exhaust Hood, Inner

Casing And Inner Shell 3.7.4.3.7 GEI – 79330A, Disassembly of Turbine End Rotor 3.7.4.3.8 GEK-11236, Methods for Lifting Rotors

3.7.4.4 Perform Blue Contact check on casing Casing halves shall be hand worked and prepared for contact check. Upper casing shall be reinstalled to perform blue contact check. Findings shall be documented with digital photos along with written narrative detailing results.

3.7.4.5 Design Clearances CONTRACTOR shall reference GE Dwg. 268R473 (REV.0) to obtain design clearances.

3.7.4.6 Bolts, Nuts, and Dowels

3.7.4.6.1 All the internal threads in casings, bearing pedestals, bearing covers, and associated steam turbine components are to be tapped with same size taps. Damaged threads are to be drilled and tapped to next higher size.

3.7.4.6.2 All casing nuts will be placed in vice and tapped with same size taps.

Page 19: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 19 of 33

3.7.4.6.3 Dowels or locating pins if required are to be reamed to new sizes and to be replaced. All taps are to be arranged by CONTRACTOR.

3.7.4.6.4 All casing stud threads are to be cleaned with same size dye. 3.7.4.6.5 Any bolt, nut, or dowels which fail inspections will be replaced.

UTILITIES will provide replacement bolts and nuts as required.

3.7.5 Steam Turbine Bearings – Inspection and Repair Criteria 3.7.5.1 Description – Tapered-Land Thrust Bearing

The thrust bearing is located on the main shaft of the turbine. Independently mounted inside the standard, the thrust bearing absorbs the axial thrust of the turbine and generator rotors. The tapered-land thrust bearing consists of two stationary thrust plates and two rotating thrust collars on the turbine shaft which will provide the front and back faces to the bearing. Reference: GEK 46382F, Machine and Operating Limit Recommendations for Tapered Land Thrust Bearings in Sliding Front Standards.

3.7.5.2 Inspection Criteria – Tapered-Land Thrust Bearing:

3.7.5.2.1 Receive visually and dimensionally inspect thrust plates. Record incoming flatness and land geometry

3.7.5.2.2 Perform ultrasonic inspection of babbitt bond 3.7.5.2.3 If the ultrasonic test results are acceptable, machine each thrust

plate to restore flatness and geometry to factory specifications. Note: If porosity is detected in the babbitt during machining, the thrust plate must be re-babbitted. 3.7.5.2.4 If the ultrasonic test results are not acceptable, or porosity is

detected in the babbitt while machining, repair each thrust plate as follows: a. Machine out old babbitt b. Prep and re-babbitt each thrust plate c. Machine to restore flatness and geometry to factory

specifications d. Perform final inspection and record flatness and land

geometry.

3.7.5.3 Description - Main Journal Bearings - #1, 2, 3, & 4

Page 20: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 20 of 33

The main journal thrust bearings consist of a housing containing six steel pads with babbitt centrifugally cast on the bearing surface. The pads are supported on a cylindrical bore in the bearing casing, three in each half.

3.7.5.4 Inspection Criteria - Main Journal Bearings - #1, 2, 3, & 4:

3.7.5.4.1 Perform inspection on all bearing parts 3.7.5.4.2 Check seal teeth diameters 3.7.5.4.3 Disassemble bearing 3.7.5.4.4 Inspect bearing pads, anti-rotation pins, dowel holes, and dowel

pins 3.7.5.4.5 Ultrasonic test babbitt bond line to shell 3.7.5.4.6 Blue check and scrape the babbitt liner to the bearing mandrel 3.7.5.4.7 Pinch check the assembled bearing to the mandrel 3.7.5.4.8 QA Check with Customer 3.7.5.4.9 Reassemble bearing

3.7.5.5 Repair Criteria – Main Journal Bearings 3.7.5.5.1 Dimensionally inspect the bearing pads 3.7.5.5.2 Remove shims - leave shims designated by drawings in place 3.7.5.5.3 Set up and secure the pads into the casing 3.7.5.5.4 Reassemble bearing and prepare the babbitt surfaces for TIG

weld 3.7.5.5.5 Babbitt weld pads 3.7.5.5.6 Finish machine the babbitt bore for design clearance 3.7.5.5.7 Disassemble bearing 3.7.5.5.8 Hand blend babbitt on pads at radii and edges 3.7.5.5.9 Remove seal teeth, weld and machine grooves 3.7.5.5.10 Install and machine two seal teeth 3.7.5.5.11 Drill corner jack screw holes per drawing (set of pads) 3.7.5.5.12 Blue check pads to mandrel and perform minor scraping as

necessary 3.7.5.5.13 Hardened bushing modification 3.7.5.5.14 Furnish material and manufacture mandrel

3.7.6 HP / IP & LP Rotor Inspections:

Note: Please note that tests marked with asterisk will be quoted as optional on the Supplier Response Form.

3.7.6.1 Runout Inspection: Rotor runout checks will be taken at two or three axial positions with the rotor in its bearings. Areas where runout checks are to be made will be cleaned with emery paper to remove loose scale. The readings will be taken every 1/8 turn, starting at a point that can be easily referenced to permanent angle markings on the rotor. The positions at

Page 21: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 21 of 33

which the readings are taken will be accurately documented for repeatability in future outages. Data will be taken and compared to 2001 readings. Any readings greater than 2 mils as compared to 2001 readings will be immediately reported to PM Manny Zeringue.

3.7.6.2 Clean and visually inspect 3.7.6.2.1 Tie Wires: Brazed or welded tire wires should be visually

inspected for cracks in the tie wire, the fillet between the wire and the vane, or in the vanes adjacent to the tie wire. Loose tie wires should be inspected for evidence of tie wire cracks. Fretting, or other damage in the area of the wire hole should also be inspected.

3.7.6.2.2 Erosion Shields: Visually and dye-penetrant check for evidence of cracking. Visual inspection should also be performed for severe erosion or failure of brazed joints.

3.7.6.2.3 Bucket Vane: The vane should be visually inspected for evidence of cracking or pitting, as well as trailing edge erosion.

3.7.6.2.4 Peened Covers: The cover should be inspected for indication of lifting or severe erosion of the cover or tenons. Inspection should also be made for missing covers.

3.7.6.2.5 Dovetail: The accessible area of the bucket dovetail should be inspected for any sign of distress, pitting of the wheel or dovetail pins or loose pins.

3.7.6.3 Perform non-destructive examination of rotor periphery 3.7.6.4 Magnetic particle test of rotor outer diameter to detect axial or

circumferential cracking 3.7.6.5 Perform dimensional inspections, including selective run outs, journals,

couplings, and mid-span 3.7.7 Optional 10th Stage Bucket Replacement: 3.7.7.1 Inspect existing 10th stage blades

a. Perform visual inspection – document with digital photos b. Take dimensional measurements on existing shroud width.

3.7.7.2 Remove old buckets and covers from turbine rotor 3.7.7.3 Clean dovetail and perform NDE 3.7.7.4 Weigh replacement buckets and plot for optimal balancing 3.7.7.5 Install new buckets and covers on rotor 3.7.7.6 Peen tenons 3.7.7.7 Machine buckets and covers to drawing dimensions 3.7.7.8 Perform magnetic particle inspection on new buckets, tenons, and covers.

Page 22: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 22 of 33

3.7.8 Optional General Alignment Specifications – Final assembly will include a low speed balance and tops on / tops off alignment

3.7.8.1 CONTRACTOR will use the OEM’s catenary curve and thermal growth

data for purposes of calculating alignment and incorporating rotor sag at each diaphragm location.

3.7.8.2 CONTRACTOR will perform a laser tops on / tops off alignment. Every effort should be made to take all diaphragm centerline deviation readings with the top on.

3.7.9 Equipment Weights for Lifting / Shipping Purposes Description Weight (lbs) Lifting Device

Rating - Weight (lbs)

Total Weight

HP / IP Rotor 31,877 4,600 36,477

Inner Upper Shell 19,000

Inner Lower Shell 19,000

LP Rotor 58,000 4,600 62,600

LP Outer Shell 46,000

LP Inner Shell 13,000 Cross Over Pipe 22,000

Stop & Control Valve Assembly

37,833

Stop Valves (Each) 13,621

Combined Reheat Valves

50,371

3.8 CONTRACTOR Requirements: 3.8.1 CONTRACTORs must have in house field technicians with extensive

experience in maintaining General Electric steam turbine generator type and model described in Section 2.0.

Page 23: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 23 of 33

3.8.2 CONTRACTOR must be able to demonstrate that they have an extensive library or access to a library of technical drawings and documentation to be able to support the maintaining and overhauling of General Electric steam turbine generators of the type and model stated in Section 1.0

3.8.3 A “field technician” as stated in this document refers to individuals that have at least 7 years experience in the repair, maintaining, overhauling, inspecting and testing of General Electric turbine generators and auxiliary equipment. These individuals have supervised, planned and executed repairs to large steam turbine/generator equipment. They have the authority to contact factory engineering personnel and make field technical decisions. Field technicians must have applicable experience on the types of equipment as described in Section TS-2.

3.8.4 CONTRACTOR must be able to provide OEM or equal parts for General Electric turbine generators

3.8.5 CONTRACTOR shall have in house shop facilities capable of but not limited to the following. If CONTRACTOR intends to use subcontractors for these services. CONTRACTOR must have a contractual agreement with said subcontractor. Subcontractors must be able to demonstrate extensive experience in the repair and modification of large steam turbine/generator equipment. UTILITIES reserves the right to reject any subcontractor offered under this section. 3.8.5.1 Low speed rotor balance on-site capabilities for rotor size

described in Section 1.0 3.8.5.2 Rotor blade replacement / repairs 3.8.5.3 Rotor journal repairs 3.8.5.4 Nozzle block and Major Partition repair capability 3.8.5.5 Turbine stationary blade repair capabilities 3.8.5.6 Turbine valve repair 3.8.5.7 Extensive field machining capabilities. 3.8.5.8 Extensive experience in NDE

4.0 Schedule

The Scope of Work referenced in section 3.0 shall have a Project Start Date of March 7, 2011. CONTRACTOR shall complete all mobilization activities prior to the Project Start Date. All Work on the Steam Turbine must be completed on or before April 3, 2011 at 11:59 PM. If upon inspection of the Steam Turbine it is determined that additional work outside of this scope of Work is required, CONTRACTOR and UTILITIES will adjust the Project Dates accordingly to reflect any additional work. Any additional work outside of this scope of work shall be performed on an agreed upon T&M rate.

Page 24: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 24 of 33

4.1 Commencement, Progress And Completion Of The Work CONTRACTOR shall complete the Work under the contract to meet the following Milestone dates listed in Table 4.1A. CONTRACTOR may propose alternate milestone dates. Any proposed changes to milestone dates must include a detailed explanation.

Table 4.1A Item No.:

Contract Milestone Description: Contract Milestone Dates:

1. Complete Disassembly and Inspection March 17, 2011 2. Complete all repairs as outlined in scope and

as discovered during inspection. March 26, 2011

3. Complete reassembly and return unit to UTILITIES for operations.

April 3, 2011 @ 11:59 PM

4.1.1 CONTRACTOR shall give UTILITIES full information in advance as to its

plans for performing each part of the Work. In addition, CONTRACTOR shall, within (ten) 10 calendar days of award of the Contract or thirty days prior to commencement of Work, which ever occurs first, submit to UTILITIES for concurrence a complete and detailed listing of all Work activities as outlined in section 3.0.

4.1.2 CONTRACTOR shall notify UTILITIES in writing of any actual or anticipated

delays immediately upon discovery. If at any time CONTRACTOR’s actual progress is inadequate to meet the requirements of this Contract, UTILITIES may notify CONTRACTOR to take such steps as may be necessary to improve its progress. If, within a reasonable period as determined by UTILITIES, CONTRACTOR does not improve performance to meet the Contract Milestone dates set forth above, UTILITIES may require an increase in CONTRACTOR’s labor force, the number of shifts, overtime operations, additional days of work per week, expedited shipment(s) of equipment and materials, and an increase in the amount of construction plant and equipment, all without additional cost to UTILITIES, providing such delays are not a result of extra work. Neither such notice nor UTILITIES’ failure to issue such notice shall relieve CONTRACTOR of its obligation to achieve the quality of work and rate of progress required by this Contract.

4.2 Contract Schedule

CONTRACTOR shall, within thirty (30) calendar days of contract award and before the first request for progress payment is made, submit to UTILITIES for its written approval a Contract Schedule using MS Project Scheduling Software. The schedule shall consist of a precedence network diagram

Page 25: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 25 of 33

using the critical path method (CPM) to show each individual essential activity in sequence to meet the Milestone dates of the Special Condition titled "COMMENCEMENT, PROGRESS AND COMPLETION OF THE WORK." The diagram shall show duration and dependencies including off-Jobsite activities such as design, fabrication of equipment, procurement, delivery of materials, and items to be furnished by UTILITIES. It shall show total float and free-float times. Float shall not be considered to be for the exclusive benefit of either UTILITIES or CONTRACTOR. Extensions of time for performance required under other contract clauses shall be made only to the extent that equitable time adjustments for affected activities exceed the total float available along their paths.

4.2.1 The Contract Schedule shall be complete in all respects, covering both on-

Site and off-Site activities including design, procurement, fabrication, and delivery of CONTRACTOR furnished materials and equipment repairs.

4.2.1.1 The activity listing shall show the following information for each

activity on the diagram:

4.2.1.1.1 Description of the task or event. 4.2.1.1.2 Individual activities within the task or event. 4.2.1.1.3 Duration. 4.2.1.1.4 Personnel by craft. 4.2.1.1.5 Equipment. 4.2.1.1.6 Earliest start and finish dates. 4.2.1.1.7 Latest start and finish dates

4.2.2 In addition CONTRACTOR shall submit a complementary and detailed narrative execution plan for performing the Work. The execution plan shall summarize with sufficient detail equipment and personnel requirements by craft to complete a resource loaded schedule.

CONTRACTOR shall promptly inform UTILITIES of any proposed change in the schedule and narrative and shall furnish UTILITIES with a revised electronic schedule and narrative within three (3) calendar days after approval by UTILITIES of such change. The schedule and narrative shall be kept up to date, taking into account the actual work progress and shall be revised, if necessary, every day. The revised schedule and narrative shall, as determined by UTILITIES, be sufficient to meet the requirements for completion of any separable part and all of the Work as set forth in this Contract.

Page 26: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 26 of 33

4.2.3 During the performance of the Work, CONTRACTOR shall submit to UTILITIES periodic reports on the actual progress. These reports shall include the following at a minimum:

4.2.3.1 Daily – A copy of the Contract Schedule showing actual progress to date

for the major parts of the Work, as compared to planned progress. 4.2.3.2 Daily – A daily work force listing all personnel by craft and work

assignment. 4.2.3.3 Schedules and reports shall be furnished in hardcopy and electronic

format deemed by UTILITIES. 4.2.4 Cost & Schedule Requirements: CONTRACTOR shall provide input to

UTILITIES’s Project Schedule appropriate to its work effort. 4.2.5 Potential changes or revisions to CONTRACTOR’s budget and baseline

schedule will adhere to the Change Orders process and must be approved by UTILITIES.

5.0 Performance Requirements The Work described herein shall be subject to a period of defect liability. “THE PERIOD OF DEFECT LIABILITY” in relation to the Work, means the specified period from the date that CONTRACTOR begins Work to the date of Work completion, which the CONTRACTOR stands responsible for rectifying all defects caused by CONTRACTOR or CONTRACTOR’s subcontractor(s). UTILITIES will not be liable for any repairs, labor, parts, or material, for any defects in Work caused by CONTRACTOR. 6.0 Performance Measurement Methods For the purposes of this contract, the period known as Completion of Work, will have occurred upon the successful start up and testing of the steam turbine. Upon the Completion of Work, UTILITIES will perform several tests, including but not limited to, N2 Leakage Test, and a Steam Turbine Performance Test. Unit Start-Up is projected to take place on or before May 15, 2007. CONTRACTOR shall maintain a minimum staff on site comprised of craft and supervisory personnel to address any potential problems associated with CONTRACTOR’s Work during Unit Start-up. Upon successful start-up and testing, Unit will be shut down. Once unit has been shut down, CONTRACTOR will remove steam turbine start-up strainer and re-torque casing bolts.

Page 27: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 27 of 33

7.0 Resource Requirements UTILITIES shall provide the following services, equipment, and tools for the performance of this Work.

7.1 UTILITIES-FURNISHED DRAWINGS AND SPECIFICATIONS 7.1.1 UTILITIES will furnish specifications and prints of engineering design

drawings for each part of the Work under this Contract where applicable. Such drawings will give information required for the preparation of shop detail drawings.

7.1.2 CONTRACTOR shall, immediately upon receipt thereof, check all

specifications and drawings furnished and shall promptly notify UTILITIES of any omissions or discrepancies in such specifications or drawings.

7.1.3 All drawings or technical documents listed in Section 10.0 (Applicable

Documents) provided by UTILITIES are a part of this Contract. All drawings and technical documents listed in Section 10.0 are proprietary to UTILITIES and shall only be used to carryout scope of Work described herein. Upon the completion of Work, CONTRACTOR shall return all drawings to the UTILITIES. Any modifications made as a result of Work will be reflected in redline drawings marked up by CONTRACTOR. CONTRACTOR will provide AS BUILT drawings to UTILITIES for any modifications with in thirty days of completion of Work.

7.2 UTILITIES, FACILITIES, AND SERVICES

The facilities listed below will be furnished by UTILITIES. Such facilities may be used by CONTRACTOR without charge, provided that any such use shall be subject to approval of UTILITIES. CONTRACTOR will be responsible for any damages caused by CONTRACTOR or CONTRACTOR’s subcontractors.

7.2.1 Jobsite Lay-down Area - UTILITIES shall provide an area for CONTRACTOR’s storage units and staging of equipment and material. CONTRACTOR will provide UTILITIES with storage and staging requirements thirty days prior to the storage of outage.

7.2.2 Jobsite Parking Area – UTILITIES will designate a parking area for vehicles of CONTRACTOR personnel. CONTRACTOR must provide UTILITIES with a list containing the names of all personnel assigned to perform Work by CONTRACTOR and any subcontractors one week prior to the start of outage. The list shall be updated anytime there is a change in employees.

7.2.3 CONTRACTOR / Subcontractor personnel. Failure to supply the list of names to UTILITIES will result in a delay of CONTRACTOR’s personnel

Page 28: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 28 of 33

getting on site. List shall be submitted to Carolyn Thompson at [email protected]. Ms. Thompson can be contacted in her office at 719-668-8945.

7.2.4 Telecommunications – UTILITIES will provide two (2) phone lines in close proximity to the CONTRACTOR’s office trailer. CONTRACTOR shall be responsible for setting up and maintaining these lines for the duration of the subcontract and all associated running and operating costs thereto.

7.2.5 UTILITIES will provide service air at the locations identified by CONTRACTOR. CONTRACTOR will provide layout detailing service air needs fourteen days prior to the commencement of work. CONTRACTOR will be responsible for supplying air hoses and all pneumatic tools required.

7.2.6 UTILITIES will provide and maintain portable toilets on the Site for CONTRACTOR’s personnel use.

7.2.7 UTILITIES will provide dumpsters on the Site for use by CONTRACTOR. Wherever possible, these dumpsters will be located in close proximity to CONTRACTORs work area, however due to activities, this may not be possible. CONTRACTOR shall be responsible for transporting material to the dumpsters and segregating the material as indicated on the dumpsters prior to placing the material inside.

7.2.8 CONTRACTOR shall provide for removal of regulated hazardous waste from Site. Should CONTRACTOR fail to remove hazardous waste, then UTILITIES will arrange for removal of such substances and back-charge CONTRACTOR for costs associated with disposal.

7.3 UTILITIES FURNISHED PARTS, LABOR, SERVICES, EQUIPMENT,

AND SPECIALTY TOOLS UTILITIES will furnish to CONTRACTOR, at UTILITIES's designated warehouse or Jobsite storage area, the items listed below to be incorporated into or used in performance of the Work under this Contract. Such items will be furnished, without cost to CONTRACTOR, provided that CONTRACTOR shall, at its expense, accept delivery thereof, load, unload, transport to points of use, and care for such items until final disposition thereof. At time of acceptance of any such item from UTILITIES, CONTRACTOR shall sign a receipt therefore. Signing of such receipt without reservation therein shall preclude any subsequent claim by CONTRACTOR that any such items were received from UTILITIES in a damaged condition and with shortages. If, at any time after acceptance of any such item from UTILITIES, any such item is damaged, lost, stolen, or destroyed, such item shall be repaired or replaced at the expense of CONTRACTOR. Items required to be replaced may, at its option, be furnished by UTILITIES. Upon completion of all the Work under this subcontract, CONTRACTOR shall, at its expense, return all surplus and

Page 29: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 29 of 33

unused items to UTILITIES’s designated warehouse or Jobsite storage area. UTILITIES will exert every reasonable effort to make delivery of such materials and equipment so as to avoid delay in the progress of the Work. However, should UTILITIES, for any reason, fail to make delivery of any such item and a delay results, the CONTRACTOR shall work with UTILITIES to take all appropriate action to mitigate the consequences of such delay.

7.3.1 The Parts / Services to be furnished by UTILITIES include but are not limited to the following:

7.3.1.1 10TH Stage Turbine Buckets and associated hardware. 7.3.1.2 Brush Tip Seals 7.3.1.3 Retractable Inter-stage brush type packing. 7.3.1.4 Engineering services and field direction for the installation of

brush tip seals and retractable inter-stage brush seals. 7.3.1.5 Upper and lower snout rings. 7.3.1.6 Spare parts for steam turbine valves to complete inspections. 7.3.1.7 Casing bolts damaged during disassembly. 7.3.1.8 Specialty tools required for the disassembly of steam turbine as

provided by the OEM. CONTRACTOR shall be responsible for inspecting all specialty tools prior to and after each use.

7.3.1.9 UTILITIES shall provide necessary labor to remove and install instrumentation and power sources from steam turbine and associated auxiliary equipment prior to disassembly and during reassembly.

7.3.1.10 Insulation and scaffold required to perform Work.

8.0 Supplier’s Key Personnel CONTRACTOR shall assign the below listed Key Personnel (Table 8.0A) to this contract. The listed Key Personnel shall be assigned to the contract for the duration of the contract in the positions represented. Key Personnel are subject to UTILITIES’s approval. Upon request, CONTRACTOR shall furnish substantiation of the required levels of education, training and experience of these personnel as represented by CONTRACTOR.

Table 8.0A

Name Title / Position

Project Manager Site Superintendent(s) Day Shift Foreman

Page 30: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 30 of 33

Night Shift Foreman Planner / Scheduler Principal Engineer Safety Representative(Note:1)

Note 1: If CONTRACTOR employs more than twenty (20) full time employees on site, including employees of subcontractors), then CONTRACTOR shall employ a full time Safety Representative whose sole job is to monitor safety of CONTRACTOR’s workforce.

8.1 CONTRACTOR’s Key Personnel are considered essential to the Work being performed under this Contract, and as such the following provisions will apply:

8.1.1 Prior to (1) diverting Key Personnel to other positions or (2) substituting

any of the specified Key Personnel or (3) proposing them as a Key person under another subcontract, CONTRACTOR shall notify UTILITIES in writing at least three (3) days in advance and shall submit justification (including proposed replacement with candidate resume) in sufficient detail to permit evaluation of the impact on the Work being performed under this contract.

8.1.2 In the event a replacement candidate proposed by CONTRACTOR does not meet the specific qualifications and experience as deemed by UTILITIES, UTILITIES may, at its sole discretion, determine that the proposed candidate may be acceptable by way of other qualifications and/or experience, and shall, in such circumstances, inform CONTRACTOR accordingly. UTILITIES is not under any obligation to exercise such discretion.

8.2 When UTILITIES finds that a correlation exists or appears to exist between a documented lack of CONTRACTOR performance and a lack of CONTRACTOR employee qualification performance, the CONTRACTOR agrees to immediately replace that individual with another employee with qualifications appropriate to the Work being performed. This requirement is inclusive of all CONTRACTOR personnel and CONTRACTOR’s subcontractor’s personnel.

8.3 UTILITIES may also require that CONTRACTOR remove from the job, at no additional cost to UTILITIES, employees who endanger persons or property, disruptive to the workforce, or whose continued employment under this Contract is inconsistent with the requirements of the Contract and/or interests of safety or security at the Ray Nixon Site.

Page 31: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 31 of 33

8.4 Replacement of personnel shall be at CONTRACTOR's expense and any delay occasioned by the replacement process shall not entitle CONTRACTOR to an adjustment in favor of CONTRACTOR.

8.5 UTILITIES’ Key Personnel

Table 8.5A identifies UTILITIES key personnel and primary plant contacts. Table 8.5A

Name Title / Position

Manny Zeringue Contract Administrator Gary Hefty Project Engineer Glenn Machos Sourcing and Contracts Representative Ken Garcia Outage Planner Gary Barsness Safety Representative

8.6 Authority Of UTILITIES’ Key Personnel 8.6.1 Contract Administrator: Administer the Contract terms and conditions and

act as UTILITIES's authorized representative. Additionally, all correspondence shall be issued and received by the designated Contract Administrator. The Contract Administrator is the only individual authorized to direct CONTRACTOR to deviate from the express, written terms of the Contract. All authorizations to deviate from Contract must be authorized in writing and signed by UTILITIES’s Contract Administrator and CONTRACTOR’s designated representative.

8.6.2 Project Engineer: Responsible for the technical aspects of the

performance of the Contract. The Project Engineer will be the primary contact with CONTRACTOR’s engineering team. The Project Engineer may designate other personnel to oversee the performance of the Work, sign field tickets, etc. However, the designated Project Engineer retains ultimate authority over the technical aspects of the Work. Should CONTRACTOR and Project Engineer disagree over the technical requirements of the subcontract; such matters will be immediately referred to UTILITIES’s Technical Services Manager and / or Maintenance Superintendent for resolution. The Project Engineer does not possess any authority, express or implied, to direct CONTRACTOR to deviate from the terms and conditions of the subcontract.

8.6.3 Sourcing and Contracts Representative: Responsible for negotiating all

terms and conditions of Contract. Coordinates pre-bid meetings, and will

Page 32: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 32 of 33

be CONTRACTOR’s primary point of contact through the bidding and evaluation process.

8.6.4 Outage Planner: Responsible for the integration of all CONTRACTORs’

schedules and maintains Site Master Schedule. Will serve as the primary contact for CONTRACTOR’s Planners.

8.6.5 Safety Representative: All UTILITIES employees have the right to STOP

CONTRACTORs work if it unsafe work practices are served. UTILITIES’s Safety representative will monitor CONTRACTOR work, and may request plans from CONTRACTOR for major lifts, or other activities requiring detailed safety plans as deemed by UTILITIES.

9.0 Applicable Documents

UTILITIES shall provide all CONTRACTORs with a complete set of drawings, OEM documents, and other resources as needed for CONTRACTOR to prepare proposal at the mandatory pre-bid meeting.

10.0 Security Requirements

In the performance of the Work under this Contract, CONTRACTOR shall be responsible and comply with the following requirements of UTILITIES’ security program:

10.1 Incidents CONTRACTOR’s assigned security representative or onsite project manager who will assume this role shall promptly report all incidents involving the loss, theft or vandalism of tools, equipment or material to UTILITIES’s Site security manager. Notification shall also include incidents of violence, threats against others, illegal activities and misconduct. All reported incidents will be followed up by a written report within 24 hours of verbal notification.

10.2 Prohibited Articles 10.2.1 Any person who possesses, transports, or uses prohibited articles on

UTILITIES sites are subject to immediate site removal. Prohibited Articles include but are not limited to:

10.2.1.1 Dangerous weapons. 10.2.1.2 Explosives, ammunition, and incendiary devices. 10.2.1.3 Controlled substances and drug paraphernalia (e.g., illegal

drugs and associated paraphernalia, but not prescription medication),

10.2.1.4 Alcoholic beverages (includes “near” and “non-alcoholic” beer and wine).

10.2.1.5 Contraband (includes other items prohibited by law).

Page 33: Exhibit A RFP- GM-85872 STATEMENT OF WORK For …

Exhibit A RFP- GM-85872

STATEMENT OF WORK For Measurement & Inspection of HP/IP/LP Turbine

Ray D. Nixon Power Plant, Fountain, CO

Page 33 of 33

10.2.2 CONTRACTOR’s employees and employees of its subcontractors

discovered on UTILITIES’ Site in possession of any prohibited article will have the prohibited article confiscated and UTILITIES’s Site security manager notified. If the prohibited article is illegal, the El Paso County Sheriffs Office will be contacted. In all cases, the person in possession of a prohibited article is subject to disciplinary action review to include access denial to the Site.

10.2.3 Controlled Articles – CONTRACTOR’s employees and employees of

subcontractors will not be allowed to bring recorders, video and still cameras and other controlled articles into the working area of the Site. These items may be left in the person’s personal vehicle. The only exception to this mandate will be the CONTRACTOR’s use of such equipment for documentation and reporting of Work.

10.2.4 UTILITIES’s Right To Search:

10.2.4.1 All vehicles entering and exiting the Site are subject to search. All personal containers, lunch boxes, brief cases, etc. are subject to search at the vehicle security access gates. Failure to submit to required search is in violation of Site work rules and grounds for permanent Site access denial.

10.3 Access to Site

CONTRACTOR must submit the names of all employees working on site. This list shall include the names of all subcontractor employees employed by CONTRACTOR. Names shall be submitted to UTILITIES’s designated representative at least 24 hours prior to employee’s scheduled arrival. Failure to submit names to UTILITIES will result in a delay of employee(s) access to site. UTILITIES will not be held responsible for such delays.

10.4 Site Orientation Nixon Site Orientation – CONTRACTOR’s employee(s) and employees of its lower-tier subcontractors must complete the UTILITIES’ Site Safety Orientation prior to commencing work. The orientation will take approximately one (1) hour.