Executive Session Director’s Progress Review of the
NOvA Project
August 4-5, 2010Dean A. Hoffer
Director's Progress Review of the NOvA Project
204-Aug-2010
Agenda for Executive Session• Charge to Reviewers• Review Focus• Review Agenda• Reporting Structure• Reviewer Assignments• Discussion
Director's Progress Review of the NOvA Project
304-Aug-2010
ChargeThis charge is for the Committee to conduct a Director’s Progress Review of the NOvA project at Fermilab. The review team is to evaluate the project’s progress against the approved baseline and determine if the project is on track to achieve the required scope of work within budget and schedule. Additional, confirm that the project is prepared for the DOE Independent Project Review (IPR) scheduled for August 31 – September 1, 2010.
The purpose of the NOvA project is to fabricate the NOvA near and far detectors and to provide a detector hall for the far detector, as well as upgrade the Fermilab Recycler and Main Injector accelerators and the NuMI beamline. The ensemble will permit the experimenters to study neutrino oscillations, in particular, to search for the oscillation of muon-type neutrinos to electron-type neutrinos. If these oscillations can be observed then the experimenters may be able to determine the mass-ordering of the neutrinos and to observe Charge Parity (CP) violation in the neutrino sector. Determination of the mass-ordering is a unique contribution made possible by NOvA’s very long baseline.
In performance of a general assessment of progress, current status, and the identification of potential issues, the committee should address the following specific items:
1. Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the cost contingency and schedule float remaining adequate for the risks?
Director's Progress Review of the NOvA Project
404-Aug-2010
Charge (continued)2. Management: Evaluate the management structure as to its adequacy to deliver the project within
specifications, budget and schedule. Has the project responded satisfactorily to the recommendations from the previous independent project review? In particular the two recommendations for the DOE IPR conducted on January 28, 2010. Has a contingency analysis been performed and a contingency spend plan documented that
identifies the decision dates and costs? Has an updated bottoms-up cost estimate been performed that reflects a realistic estimate to
complete the remaining scope of work? 3. Construction: Has there been adequate progress on the construction activities, particularly the
work funded by the American Reinvestment & Recovery Act of 2009? Have Fermilab and the project made the necessary preparations for the remaining activities?
4. Is the NOvA project appropriately prepared for the DOE Independent Project Review scheduled for August 31 – September 1, 2010?
Finally, the committee should present findings, comments, and recommendations at a closeout meeting with NOvA’s and Fermilab’s management and provide a written report soon after the review.
Director's Progress Review of the NOvA Project
5
Questions to be addressed in each breakouts
• What work has been accomplished and was the work done per the project’s plan (cost and schedule baseline)?
• Is the plan for the remaining work reasonable and achievable?
• Is the organization in place to accomplish the remaining work per the plan?
04-Aug-2010
Director's Progress Review of the NOvA Project
604-Aug-2010
AgendaWednesday, August 4, 2010
7:30 am Executive Session - One North (WH1N) ............................................................. D. Hoffer
8:15 am Plenary Session - One West (WH1W) 8:15 am Welcome .............................................................................................................. P. Oddone 8:20 am Project Overview ................................................................................................... J. Cooper 9:10 am Accelerator and NuMI Upgrades ........................................................................ P. Derwent 9:25 am Ash River Site and Building ................................................................................... S. Dixon
9:40 am Break - outside One West (WH1W)
10:00 am Plenary Session - One West (WH1W) 10:00 am Scintillator ............................................................................................................ S. Mufson 10:10 am Fiber ................................................................................................................. C. Bromberg 10:15 am PVC Extrusions ...................................................................................................... R. Talaga 10:25 am Extrusion Module Factory ..................................................................................... K. Heller 10:35 am Electronics and DAQ .......................................................................................... L. Mualem 10:45 am Near/Far Detector Assembly ................................................................................. P. Lukens 11:00 am Near Detector / Integration Prototype .................................................................. R. Tesarek
11:30 am Lunch
12:15 pm Tour of Near Detector / Integration Prototype .......................................................... All (bus to site, 45 minutes for tour, bus back to WH, no break)
Director's Progress Review of the NOvA Project
704-Aug-2010
Agenda (continued) 27-July-2010 1:30 pm Breakout Sessions
1. Accelerator and Beamline - Curia II (WH2SW) 2. Site and Building & Near Detector Cavern - Tabernacle (WH5E) 3. Commodities: Scintillator, Fiber, and PVC - Racetrack (WH7XO) 4. Extrusion Module Production - Snake Pit (WH2NE) 5. Electronics and DAQ - Black Hole (WH2NE) 6. Near and Far Detector Assembly - Fish Tank (WH13XO) 7. ES&H - Small Dining Room (WH1SW) 8. Project Management, Cost, and Schedule - One North (WH1N)
3:00 am Break - outside One West (WH1W)
3:15 am Breakout Sessions Continue in same conference rooms 5:00 pm Subcommittee Discussions – In Breakout Meeting Rooms .............. Subcommittee Leads 5:30 pm Full Committee Executive Session - One North (WH1N) ................................... D. Hoffer 6:30 pm Adjourn Thursday, August 5, 2010
8:00 am NOvA Respond to Committee Questions from 1st Day - One North (WH1N) 8:45 am Subcommittee Working Session/Report Writing - One North (WH1N) 11:15 am Full Committee Executive Session Dry Run - One North (WH1N) .................... D. Hoffer
12:00 pm Working Lunch
3:00 pm Summary and Closeout - One West (WH1W) ..................................................... D. Hoffer 4:00 pm Adjourn
Director's Progress Review of the NOvA Project
804-Aug-2010
Reviewer AssignmentsExecutive Summary Dean Hoffer 1.0 Introduction Dean Hoffer 2.0 Accelerator and Beamline (WBS 1/2.0) Alireza Nassiri*
Lionel Prost 3.0 Site and Building (WBS 1/2.1) & Near Detector Cavern Jason Budd*
Tim Wyman 4.0 Commodities: Scintillator/Fiber/PVC (WBS 1/2.2, 1/2.3, 1/2.4) Bill Cooper*
Mike Dinnon 5.0 Extrusion Module Production (WBS 1/2.5) Linda Stutte*
Jim Freeman 6.0 Electronics and DAQ (WBS 1/2.6, 1/2.7) Jonathan Lewis*
Mark Bowden 7.0 Near and Far Detector Assembly (WBS 1/2.8, 1/2.9) Charlie Cooper*
Rob Roser 8.0, Cost, Schedule, ES&H and Project Management Rich Stanek*
Fran Clark Cat James Jim Priest Jimmy Proudfoot
8.1 Cost Jimmy Proudfoot 8.2 Schedule Fran Clark 8.3 ES&H Jim Priest 8.4 Management Rich Stanek
02-Aug-2010
Note: Underlined names are the primary writer * Indicates Subcommittee Lead
Director's Progress Review of the NOvA Project
904-Aug-2010
Reviewer Assignments (continued) 02-Aug-2010
9.0 Charge Questions 9.1 Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the cost contingency and schedule float remaining adequate for the risks?
Fran Clark All
9.2 Management: Evaluate the management structure as to its adequacy to deliver the project within specifications, budget and schedule. Has the project responded satisfactorily to the recommendations from the previous independent project review? In particular the two recommendations for the DOE IPR conducted on January 28, 2010. • Has a contingency analysis been performed and a contingency spend plan documented that identifies the decision dates and costs? • Has an updated bottoms-up cost estimate been performed that reflects a realistic estimate to complete the remaining scope of work?
Rich Stanek All
9.3 Construction: Has there been adequate progress on the construction activities, particularly the work funded by the American Reinvestment & Recovery Act of 2009? Have Fermilab and the project made the necessary preparations for the remaining activities?
Rob Roser All
9.4 Is the NOvA project appropriately prepared for the DOE Independent Project Review scheduled for August 31 – September 1, 2010?
Rich Stanek All
Note: Underlined names are the primary writer * Indicates Subcommittee Lead
Director's Progress Review of the NOvA Project
1004-Aug-2010
Reviewer Assignments for Breakouts1) Accelerator and Beamline (Curia II – WH2SW) Alireza Nassiri
Lionel Prost 2) Site and Building & Near Detector Cavern (Tabernacle, WH5E) Jason Budd
Tim Wyman 3) Commodities – Scintillator/Fiber/PVC (Racetrack – WH7XO) Bill Cooper
Mike Dinnon 4) Extrusion Module Production (Snake Pit – WH2NE) Jim Freeman
Linda Stutte 5) Electronics and DAQ (Black Hole – WH2NW) Mark Bowden
Jonathan Lewis 6) Near and Far Detector Assembly (Fish Tank – WH13XO) Charlie Cooper
Rob Roser 7) ES&H (Small Dining Room – WH1SW) Jim Priest 8) Project Management, Cost, and Schedule (One North –WH1W) Fran Clark
Cat James Jimmy Proudfoot Rich Stanek
Director's Progress Review of the NOvA Project
1104-Aug-2010
Reporting Structure
• Review findings, comments, and recommendations should be presented in writing at a closeout with the NOvA’s and Fermilab’s management.
• Section for each “Level 2” WBS plus Cost, Schedule, Management sections.
Director's Progress Review of the NOvA Project
1204-Aug-2010
Findings, Comments, and Recommendations
• Findings
• Comments
• Recommendations
• Findings are statements of fact that summarize noteworthy information presented during the review.
• Comments are judgment statements about the facts presented during the review. The reviewers' comments are based on their experiences and expertise.
• The comments are to be evaluated by the project team and actions taken as deemed appropriate.
• Recommendations are statements of actions that should be addressed by the project team.
• A response to the recommendation is expected and that the actions taken would be reported on during future reviews.
Director's Progress Review of the NOvA Project
13
Examples of Findings, Comments, and Recommendations
Finding– A plan for the MI upgrades was presented. The major elements of
this plan consist of an upgrade of a MI quad power supply, which is nearly complete, and the addition of two more RF stations. The cavities to be installed currently exist as spares so there is no design and prototyping required.
Comment– The project has decided to build the DCCT in-house. The
committee supports this effort since the technology and design of this device is well developed and well known.
Recommendation– Work with Fermilab management to acquire resources needed to
complete the accelerator and beamline modifications.
04-Aug-2010
Director's Progress Review of the NOvA Project
1404-Aug-2010
Reviewer Write-ups
• Write-up template is posted on Director’s Review Webpage. http://www.fnal.gov/directorate/OPMO/Projects/NOvA/DirRev/2010/08_04/Closeout_Presentation_NOvA_Progress_2010-08-04.docx
• Write-ups are to be sent to Terry Erickson at [email protected] prior to 10:30 AM on Thursday, August 5 for the Closeout Dry Run
• A final report will be issued within 1 weeks after the closeout.
Director's Progress Review of the NOvA Project
1504-Aug-2010
Discussion
• Questions and Answers