EvapORATIVE CoolING Split SysTEM

  • Upload
    asdthu

  • View
    237

  • Download
    0

Embed Size (px)

Citation preview

  • 8/11/2019 EvapORATIVE CoolING Split SysTEM

    1/5

    PLUMBING INDUSTRY COMMISSION

    7 : M E C H A N I C A L S E R V I C E S

    Current as at March 2001

    Page 1 of 2

    Evaporative Coolers

    Drainage provisions forevaporative coolers

    The discharge pipe from an evaporative cooler must besized in accordance with the manufacturers requirementsand must have continuous fall to the termination point.

    The discharge pipe must have an internal diameter of noless than the internal diameter of the unit connectionprovision supplied by the manufacturer.

    The following diagrams are typical and provide guidancefor evaporative cooler installers on the permitted ways todischarge the drains from evaporative coolers in accordancewith the Plumbing Standards Regulations.

    1. A discharge point to aroof gutter pop outlet,providing the downpipeis not used for thecollection of waterfor potable use.

    150mm min150mm min.Drain to dischargeover pop to preventponding in gutter

    Downpipe

    Drain

    EvaporativeCooler

    3. A surface stormwater drainage system.Provided the surface is graded awayfrom the building and ponding doesnot occur, and the discharge does notpresent a safety risk to pedestrians(eg. across a footpath).

    Tundish

    Sealed connection

    Downpipe

    EvaporativeCooler

    Air gap 25mm

    2. Direct to a downpipevia a tundish, providingthe downpipe is notused for thecollection of waterfor potable use.

    Stormwater pit

    Surface graded to pit

    Drain

    4. A sanitary drainage system via a tundish in one of thefollowing forms in accordance with AS/NZS 3500.2.2 1996 clause 4.6.7.8 & 11.22

    4 (a) To a disconnector gully.

    Drain

    Air gap 25mm

    DG

    40mm trappedwaste 3.5 max.

    or50mm trappedwaste 6m max.

    Drain

    Air gap 25mm

    FWG riser Untrapped waste DN 25max. length 10m

    4 (b) To a floor waste gully.

    Technical SolutionsTechnical SolutionsTechnical Solutions

  • 8/11/2019 EvapORATIVE CoolING Split SysTEM

    2/5

    Drain

    Stormwater drain

    Absorption pit

    Earth cover

    Stone, brick orlarge granular material

    PLUMBING INDUSTRY COMMISSION

    7 : M E C H A N I C A L S E R V I C E S

    Current as at March 2001

    Page 2 of 2

    Technical SolutionsTechnical SolutionsTechnical Solutions

    4 (c) Direct to a sanitary drain.

    Evaporative Coolers Cont.

    Drain

    Air gap 25mm

    40 or 50mmtrapped waste

    2.5m max. to a direct connection

    min. 65mm drain

    Drain

    Air gap 25mm

    40 or 50mm trapped waste2.5m max. to a stack

    5. An absorption pit. Provided the following conditions canbe met:

    Only permitted where no sanitary or surface waterdrainage is available.

    The pit can only be constructed in permeable ground. Of a size appropriate for the volume of discharge. Located so the discharge water will

    not cause damage to buildings bychanging moisture conditions.

  • 8/11/2019 EvapORATIVE CoolING Split SysTEM

    3/5

    Drain

    Indoor Unit300mm

    min.

    downpipe

    Angle cut to allowfor downpipeblockage

    Drain

    Sealedconnection

    Downpipe

    Bend one pipesize bigger thandrain

    PLUMBING INDUSTRY COMMISSION

    7 : M E C H A N I C A L S E R V I C E S

    Current as at March 2001

    Page 1 of 3

    Split System Air Conditioning

    Technical SolutionsTechnical SolutionsTechnical Solutions

    Condensate drainage forsplit system air conditioners

    Drain Material

    The material used for the drain must be suitable for thepurpose and if a plastics material is used it must be of a typesuitable for installation in direct sunlight.

    Pumped Condensate

    If condensate from an indoor unit has to be pumped toits drainage termination point it is essential that the pump isinstalled in an accessible position for service/maintenancepurposes.

    Termination points

    The following diagramsprovide guidance on the

    approved methods ofdischarge for condensatedrains from split system airconditioning.

    1. On to a garden bed.

    2. Concrete or paved surface.Provided the surface isgraded away from thebuilding and ponding doesnot occur, and thedischarge does not presenta safety risk to pedestrians(eg. across a footpath).

    Drain

    Garden bed

    Indoorunit

    Drain

    concrete or pavinggraded away from building

    Indoorunit

    3. To a downpipe provided the following two points areobserved;(a) Provided there is a form of disconnection to prevent

    leakage into the building from the indoor unit ifthere is a blockage in the downpipe. Figs 1 & 2.and

    (b) The connection to the downpipe is a minimum of300mm below the drain outlet of the indoor unit.Fig 3.

    Top of tee left opento allow for downpipeblockage

    Short sectionof pipe

    Drain

    Sealed connectionDownpipe

    Fig 1

    Fig 3

    Fig 2

  • 8/11/2019 EvapORATIVE CoolING Split SysTEM

    4/5

    Drain

    Air gap 25mm

    FWG riser Untrapped waste DN 25max. length 10m

    PLUMBING INDUSTRY COMMISSION

    7 : M E C H A N I C A L S E R V I C E S

    Current as at March 2001

    Page 2 of 3

    Technical SolutionsTechnical SolutionsTechnical Solutions

    Split System Air Conditioning Cont.

    4. To a down pipe via a lower metal roof.

    Discharge directlyover downpipe pop

    Drain

    Indoorunit

    Continued ... /

    Placement of an outdoor unit on a metaldeck roof.

    The following provides guidance for the installation ofsmall domestic size outdoor units on a metal deck roof.

    You must ensure that the weight of the unit is notexcessive for the design of the roof structure.

    Larger units may require engineering computations toensure adequate strength of the roof structure.

    If timber is to be used as a support material on a metal roofit should be redgum to minimise the possibility of stainingthe roof as it weathers. The redgum can be painted ifnecessary to further protect the timber and the roof.

    It is not permitted to install timber bearers in thetray section of a steel deck roof as support for anoutdoor unit as the flow of water in the tray isimpeded.

    Metal deck roof Roof drainage reducedby timber bearer

    5. A sanitary drainage system via a tundish in one of thefollowing forms in accordance with AS/NZS 3500.2.2 1996 clause 4.6.7.8 & 11.22.

    5. (a) To a fixture trap provided the connection is above thelevel of the water seal and the top of the tundish isabove the overflow level of the fixture.

    5. (b) To a floor waste gully.

    Drain

    25mm Air gap

    Tundish

  • 8/11/2019 EvapORATIVE CoolING Split SysTEM

    5/5

    PLUMBING INDUSTRY COMMISSION

    7 : M E C H A N I C A L S E R V I C E S

    Current as at March 2001

    Page 3 of 3

    Split System Air Conditioning cont.

    Technical SolutionsTechnical SolutionsTechnical Solutions

    If timber bearers are to be used as a support ensure theyare placed on top of the ribs and insulated from the metalby a suitable material (eg rubber waffle pads) to preventcorrosion occurring.

    Metal deck roof

    Timber bearer

    Insulation

    Placement of an outdoor unit at groundlevel.

    An outdoor unit should be mounted level on appropriateconcrete slabs and secured by means of suitable brackets toan adjacent wall.

    Bracket secured to wall