Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
i
EVALUATING THE QUALITY OF EIA SCOPING REPORTS
ASSOCIATED WITH HAZARDOUS WASTE MANAGEMENT
ACTIVITIES IN SOUTH AFRICA
By
BRADLEY KEVIN THORPE
MINOR-DISSERTATION
Submitted in partial fulfilment of the requirements for the degree of
MASTER of SCIENCE
in
ENVIRONMENTAL MANAGEMENT
in the
FACULTY of SCIENCE
at the
UNIVERSITY of JOHANNESBURG
SUPERVISOR: Dr. I. T. RAMPEDI
MAY 2014
ii
iii
ACKNOWLEDGEMENTS
I would like to express sincere thanks to Dr. I.T. Rampedi for his guidance and academic
support, as well as my wife for her continued moral support and patience, during the last two
years. The completion of this research and this minor-dissertation would have been a
challenge without either of their inputs and advice. Lee-Ann Foster is gratefully
acknowledged for assistance in some of the technical aspects in the structure of this
dissertation.
iv
ABSTRACT
The minimum requirements for environmental impact assessment (EIA) in South Africa are
prescribed in the 2010 EIA Regulations under the National Environmental Management Act
(Act No. 107 of 1998) [NEMA]; where EIA is used as a decision-support tool by competent
authorities in evaluating the environmental authorisation applications of activities likely to
have adverse environmental impacts. Regulations under the National Environmental
Management: Waste Act (Act No. 59 of 2008) [NEM:WA] define the nature and thresholds of
those waste management activities for which environmental authorisation, in the form of a
waste management licence, is required.
The aforementioned regulations make a distinction between Category A activities and
Category B activities; where an application for authorisation for Category B activities needs
to be supported by a comprehensive Scoping and EIA (SIA) process undertaken by an
independent environmental assessment practitioner (EAP). With the exception of the
disposal of general waste to land, Category B activities relate to hazardous waste storage,
treatment, reuse, recycling, recovery and disposal. The above-mentioned SIA process is
implemented in two distinct phases, the first of which is the scoping phase; which aims to
identify the key potential impacts that could be realised from a development proposal and to
set the terms of reference for the subsequent EIA phase. Scoping thus aims, inter alia, to
ensure that the overall EIA is undertaken in an efficient and effective manner, with emphasis
on identification of impacts of potential significance.
By using a modified version of the South African adapted Lee and Colley (1992) Review
Package, this dissertation presents the findings of an evaluation of the quality of hazardous
waste-related Scoping Reports prepared in South Africa. A sample of 20 Scoping Reports
was assessed using the aforementioned review package. The results indicated that 75% of
Scoping Reports were undertaken satisfactorily in terms of overall quality. Conversely, 25%
of these reports were deemed to be of an unsatisfactory quality, with 10% having been very
poorly attempted and deficient in many material respects. This is concerning in respect of
the sectoral focus (hazardous waste management) of this research; where by definition,
owing to the inherent physical, chemical or toxicological characteristics, the handling of
hazardous waste may have a significant detrimental impact on human health and the
environment if managed inappropriately.
KEY WORDS: Scoping Report; quality appraisal; EIA; South Africa; hazardous waste.
v
ABBREVIATIONS
DEA: Department of Environmental Affairs
DWAF: Department of Water Affairs and Forestry
EAP: Environmental Assessment Practitioner
EAPASA: Environmental Assessment Practitioner Association of South Africa
ECA: Environment Conservation Act (Act No. 73 of 1989)
EIA: Environmental Impact Assessment
ES: Environmental Statement
IAPs: Interested and Affected Parties
NEMA: National Environmental Management Act (Act No. 107 of 1998)
NEM:WA: National Environmental Management: Waste Act (Act No. 59 of 2008)
EIR: Environmental Impact Report
PoSEIA: Plan of Study for EIA
S & EIA: Scoping and Environmental Impact Assessment
ToR: Terms of Reference
vi
TABLE OF CONTENTS
ACKNOWLEDGEMENTS .................................................................................................... iii
ABSTRACT ......................................................................................................................... iv
ABBREVIATIONS ................................................................................................................ v
TABLE OF CONTENTS ...................................................................................................... vi
LIST OF FIGURES ............................................................................................................ viii
LIST OF TABLES ................................................................................................................ ix
CHAPTER 1 ......................................................................................................................... 1
INTRODUCTION AND RESEARCH BACKGROUND .......................................................... 1
1.1 INTRODUCTION .................................................................................................... 1
1.1.1 The value of scoping in EIA processes .................................................................. 2
1.2 STATEMENT OF THE RESEARCH PROBLEM ..................................................... 5
1.3 JUSTIFICATION AND SIGNIFICANCE OF THE STUDY ........................................ 5
1.4 RESEARCH OBJECTIVES ..................................................................................... 7
1.5 BRIEF OVERVIEW OF RESEARCH DESIGN AND METHODOLOGY ................... 7
1.6 ORGANISATION OF THE DISSERTATION ........................................................... 8
1.7 LIMITATIONS TO THE RESEARCH ....................................................................... 9
CHAPTER 2 ....................................................................................................................... 10
LITERATURE REVIEW ...................................................................................................... 10
2.1 INTRODUCTION ....................................................................................................... 10
2.2 ENVIRONMENTAL IMPACT ASSESSMENT ............................................................ 10
2.2.1 The development of EIA practice ........................................................................ 10
2.2.2 EIA in South Africa .............................................................................................. 12
2.2.3 Scoping ............................................................................................................... 13
2.3 HAZARDOUS WASTE MANAGEMENT IN SOUTH AFRICA .................................... 14
2.3.1 Hazardous waste management reform in South Africa ........................................ 15
2.3.2 Challenges facing hazardous waste management in South Africa ...................... 19
2.4 METHODS OF APPRAISING EIA QUALITY ............................................................. 20
2.4.1 Lee and Colley EIR Review Package .................................................................. 20
2.4.2 European Commission Guidelines ...................................................................... 21
vii
2.4.3 Oxford-Brookes University Review Package ....................................................... 22
2.4.4 Legal compliance ................................................................................................ 22
2.5 EIA QUALITY APPRAISAL IN SOUTH AFRICA ........................................................ 23
CHAPTER 3 ....................................................................................................................... 25
RESEARCH METHODOLOGY ........................................................................................... 25
3.1 INTRODUCTION ....................................................................................................... 25
3.2 LEE AND COLLEY REVIEW PACKAGE ................................................................... 25
3.2.1 Sample size selection ......................................................................................... 25
3.2.2 Primary data sourcing procedures ....................................................................... 29
3.2.2.1 Sourcing Primary Data from Department of Environmental Affairs ................... 29
3.2.2.2 PAIA Application and Administrative Fees ........................................................ 29
3.2.2.3 EAP Websites .................................................................................................. 29
3.2.3 Primary data analytical procedures ..................................................................... 30
3.2.3.1 Report Reviewing ............................................................................................. 30
CHAPTER 4 ....................................................................................................................... 34
RESEARCH FINDINGS AND DISCUSSION ...................................................................... 34
4.1 INTRODUCTION ....................................................................................................... 34
4.2 REVIEW AREA 1: DESCRIPTION OF THE PROPOSED ACTIVITIES AND
RECEIVING ENVIRONMENT ......................................................................................... 35
4.3 REVIEW AREA 2: SCOPING .................................................................................... 40
4.4 REVIEW AREA 3: COMPLIANCE TO LEGISLATIVE, GUIDELINE AND POLICY
FRAMEWORK ................................................................................................................. 44
4.5 REVIEW AREA 4: COMMUNICATION OF RESULTS ............................................... 47
4.6 OVERALL SCOPING REPORT QUALITY ................................................................. 51
4.7 MINIMUM CONTENT OF A SCOPING REPORT ...................................................... 57
4.8 AREAS OF WEAKNESS ........................................................................................... 60
4.9 AREAS OF STRENGTH ............................................................................................ 61
CHAPTER 5 ....................................................................................................................... 62
CONCLUSIONS AND RECOMMENDATIONS ................................................................... 62
5.1 INTRODUCTION ....................................................................................................... 62
5.2 CONCLUSIONS ........................................................................................................ 62
5.3 RECOMMENDATIONS FOR FURTHER ASSESSMENT / STUDY ........................... 63
LIST OF REFERENCES ..................................................................................................... 65
viii
LIST OF FIGURES
FIGURE 1: EIA Process Flow diagram, in terms of GNR. 543 of 18 June 2010. ....... 4
FIGURE 2: The Assessment Pyramid. ..................................................................... 28
FIGURE 3: Schematic Representation of the Review Topic Hierarchy in Review
Areas 1 & 2. ............................................................................................................. 28
FIGURE 4: Review Area 1 - Description of Project and Receiving Environment ...... 37
FIGURE 5: Review Area 2 - 'Scoping and Impact Identification'. ............................. 42
FIGURE 6: Review Area 3 – ‘Legislative and Policy Framework’. ............................ 46
FIGURE 7: Review Area 4 - 'Communication of Results’. ........................................ 49
FIGURE 8: Trends Analysis of Results for Review Area 2 and 3. ............................ 53
FIGURE 9: Scoping Report Quality Appraisal. ......................................................... 54
FIGURE 10: Review Area Quality Appraisal Comparism. ........................................ 55
FIGURE 11: Review Area Quality Appraisal Comparison Summary. ....................... 56
ix
LIST OF TABLES
TABLE 1: Hazard Classes of the SANs 10234 (GHS) Classification System. .......... 16
TABLE 2: Waste Disposal Restrictions under the Standard for Disposal of Waste to
Landfill (GNR 645 of 23 August 2013). ..................................................................... 17
TABLE 3: Waste Type Determinations and Landfill Requirements under the Waste
Classification and Management Regulations (GNR 643 of August 2013). ............... 18
TABLE 4: Assessment Symbols for Review Topics (Lee and Colley). ..................... 27
TABLE 5: Assessment Symbol Aggregation. ........................................................... 27
TABLE 6: Tabular Summary of Review Areas, Categories and Sub-categories Used.
................................................................................................................................. 32
TABLE 7: Frequency of Specific Waste-Management Activities in the EIRs under
Scrutiny. ................................................................................................................... 34
TABLE 8: Tabular Summary of Review Results for Review area 1 and Associated
review Categories..................................................................................................... 36
TABLE 9: Review Area 1, Scoring of Quality Level for Sub-categories. ................... 37
TABLE 10: Summary of Review Results for Review Area 2 and Associated Review
Categories. ............................................................................................................... 41
TABLE 11: Review Area 2, Scoring of Quality Level for Sub-categories. ................. 43
TABLE 12: Summary of Review Results for Review area 3 and Associated Review
Categories. ............................................................................................................... 45
TABLE 13: Review Area 3, Scoring of Quality Level for Sub-categories. ................. 47
TABLE 14: Summary of Review results for review Are 4 and associated Review
Categories. ............................................................................................................... 49
TABLE 15: Review Area 4, Scoring of Quality Level for Sub-categories. ................. 50
TABLE 16: Tabular Summary of Overall Review Results and Associated Review
Areas. ....................................................................................................................... 54
TABLE 17: Regulatory Requirements for Sub-category Scoring. ............................. 58
TABLE 18: Tabular Summary of Performance Against Regulatory Requirements. .. 60
1
CHAPTER 1
INTRODUCTION AND RESEARCH BACKGROUND
1.1 INTRODUCTION
Environmental impact assessment plays a critical role in ensuring the integration of
sustainability principles in project planning and implementation, as well as the
involvement and consultation of stakeholders in decision-making processes likely to
affect human health and environmental quality (Lee and Colley, 1992; Wood et al.,
2006; Sandham and Pretorius, 2008; Fuggle and Rabie, 2009; Aucamp, 2010;
Peterson, 2010). Environmental impact assessment (EIA) was formally adopted in
South Africa as early as 1997 as a means of improving the quality of environmental
management decision-making processes regarding the sustainability of development
actions, especially those with significant environmental impacts (Hoffman, 2007;
Fuggle and Rabie, 2009). The promulgation of the National Environmental
Management Act (Act No. 107 of 1998) [NEMA], as well as the first EIA Regulations
under NEMA in 2006 and subsequent revision thereof in 2010, indicate the quest for
better environmental management in South Africa.
Numerous environmental management processes have been introduced since that
time to help improve the effectiveness and efficiency of the South African EIA
system. Although scoping is not legally prescribed in countries such as Bangladesh,
Russia, Vietnam, and the UK (George, 2000; Glasson et al., 2012), it is a
compulsory and a mandatory step in South Africa for certain EIAs (FIGURE 1). As a
result, the amended National Environmental Management Act (Act No. 107 of 1998)
[NEMA], with its latest Environmental Impact Assessment Regulations (2010)
(particularly GNR. 543, Part 3) explains all the requirements for a full EIA, which
involves Scoping and an Environmental Impact Report (S & EIR). The 2010 NEMA
EIA Regulations (GNR. 543), also provides specific procedures to be adhered to
when it comes to a Basic Assessment as well. In addition to these requirements, the
2
National Environmental Management: Waste Act (Act No. 59 of 2008) [NEM:WA]
and its associated regulations, is mandatory for development actions dealing with
waste management and its minimisation.
1.1.1 The value of scoping in EIA processes
Scoping identifies relevant and priority issues from a wide range of potential issues
worthy of consideration in an EIA study (Wood et al., 2006). Thus, the scoping
process is geared to determine the terms of reference (ToR) for the EIA, the purpose
being to ensure that more focused environmental impact assessments are
undertaken and relevant and useful EIRs are ultimately prepared (Wood, 2000).
Weston (2000a), as cited in Wood et al. (2006), emphasises the vital role of scoping
in EIA practice. According to Mulvihill and Jacobs (1998), the importance of the
scoping phase in EIA practice is often undermined both by researchers and
practitioners alike. Since scoping determines the ToR for inculcating sustainability
assurance in development actions (DEAT, 2007), it is supposed to be an open
process involving relevant authorities, the developer or proponent as well as
interested and affected stakeholders (GNR. 543 NEMA EIA Regulation, 2010).
Therefore, scoping is extremely crucial and decisive in an EIA process because of
the following benefits:
It enhances optimal allocation of limited resources available to the EIA team
(Wood et al., 2006);
It helps to prevent confusion and misunderstanding between parties that
determine the information required in an environmental impact report
(Glasson et al., 2012);
It provides high quality information needed in environmental review
documents, along with key information on cumulative and indirect
environmental impacts (Gregory et al., 1992; Baker and Rapaport, 2005); and
It helps to provide information for setting environmental baselines, upon which
to compare the potential effects of proposed actions.
Thus, effective scoping can help enormously to save time and financial resources as
well as determine the focus and quality of an environmental impact assessment
3
report (EIR). However, when significant environmental issues are not identified
timeously during scoping and addressed adequately, this could give rise to
inadequate and poor environmental decisions by regulatory or competent authorities
and other role players involved. Moreover, financially costly delays may be
experienced while missing environmental information is to be gathered and
assessed (Wood, 2000).
4
FIGURE 1: EIA Process Flow diagram, in terms of GNR. 543 of 18 June 2010.
Source: DEA (2010).
5
1.2 STATEMENT OF THE RESEARCH PROBLEM
Although the quality of a limited number of EIA reports have been examined in South
Africa within the framework of previous EIA Regulations (2006 NEMA EIA) (for
instance, Kruger and Chapman, 2005; Du Pisani and Sandham, 2006; Sandham and
Pretorius, 2008; Retief et al., 2011), there is generally a lack of detailed scientific
knowledge on the quality of environmental impact assessment reports (EIR) dealing
with the environmental authorization of hazardous waste management activities
under the new NEMA EIA (2010) Regulations. Moreover, EIA Reports (EIARs) are
often criticized for being unfocused, too costly and time consuming, as well as being
of a poor quality (Mulvihill and Jacobs, 1998; Wood, 2006; Pinho et al., 2007).
Hence, the current research has evaluated the quality of scoping reports based on
EIA applications dealing with the environmental authorization of a selected number
of hazardous waste management projects in South Africa.
1.3 JUSTIFICATION AND SIGNIFICANCE OF THE STUDY
It has been reported that there are “too few adequate, compliant landfills and
hazardous waste management facilities in South Africa, which hinders the safe
disposal of all waste streams” (Department of Environmental Affairs (DEA), 2011);
and of the more than 2 000 waste management facilities existing in South Africa, a
significant number of them are not properly permitted and licensed (DEA, 2011).
Hazardous waste, given its physical, chemical and toxicological characteristics may
have detrimental impacts on human health and the environment if poorly or
inappropriately managed (NEM:WA, 2008). This is a significant point since Section
24 of the South African Constitution (1996) maintains that:
“Everyone has the right-
(a) To an environment that is not harmful to their health or well-
being, and
(b) To have the environment protected, for the benefit of present
and future generations, through reasonable legislative and other
measures that –
i. Prevent pollution and ecological degradation;
6
ii. Promote conservation; and
iii. Secure ecologically sustainable development and use of
natural resources while promoting economic and social
development”.
Source: Constitution of South Africa (Act No. 108 of 1996).
Thus, the management and disposal of hazardous waste remains a serious
environmental management challenge in South Africa, and as a result the National
Environmental Management: Waste Act (Act No. 59 of 2008) [NEM:WA] makes
provisions for mandatory EIAs of different types regarding, inter alia, the storage,
recovery, treatment or disposal of any hazardous waste. Despite these points, the
quality of scoping processes associated with these EIAs as well as the licensing of
such projects has never been evaluated in a systematic manner in South Africa.
Even so, when scoping is imprecisely undertaken, it can have undesirable effects on
the entire environmental assessment process (Glasson et al., 2012), apart from
compromising the ability of interested and affected parties (I&APs) to participate
meaningfully in the decision-making processes pertaining to the authorization and
licensing of waste management activities. More importantly, appraising the quality of
scoping processes and associated reporting has the potential to give an overview on
whether EIAs submitted for review and authorization are functioning as initially
intended by the regulators.
Thus, by concentrating on the quality of EIA scoping processes, the current study
aims to add further insights on how EIA can help to ensure (1) adequate evaluation
of impact significance and mitigation regarding the management of hazardous waste,
(2) environmentally responsible approaches in such activities, (3) integration of views
and concerns of interested and affected parties, and (4) the achievement of the
triple-bottom line sustainability principles in environmental management. Such
systematic review of the quality of sector specific Scoping Reports may ultimately
become more widely used as a measure of rapid quality control in the waste
management sector while improving the quality of subsequent EIR procedures (Lee
et al., 1999).
7
1.4 RESEARCH OBJECTIVES
The problem statement enunciated above is associated with four research
objectives, as outlined below:
1. To evaluate the quality of submitted Scoping Reports in South Africa that deal
with the licensing of hazardous waste management projects;
2. To determine whether or not the selected Scoping Reports have complied
with the relevant environmental legislation;
3. To analyse the strengths and weaknesses inherent in the Scoping Reports
compiled; and
4. To draw recommendations relevant to EIA practice in South Africa.
1.5 BRIEF OVERVIEW OF RESEARCH DESIGN AND
METHODOLOGY
There are various methods of determining the quality and effectiveness of EIA
worldwide (Wood, 2006; Pinho et al., 2007; Peterson, 2010). Based on research
conducted by Sandham and Pretorius (2008), ‘matrix systems’ and ‘review
packages’ are regarded as the two most predominant methods of EIR quality
appraisal, with the ‘review package’ method being most commonly used
internationally. On the other hand, Kruger and Chapman (2005), have used
checklists successfully in assessing EIA report quality in the South African context.
In the current study, the internationally recognized Lee and Colley Review Package
(Lee and Colley, 1992), as adapted for South African applicability by Sandham and
Pretorius (2007), was used. However, for the purpose of the present study, this
‘South African Review Package’ was further modified in certain respects to ensure
local appropriateness to the South African hazardous waste management sector, as
well as to the scoping phase of an EIA. Such adaptation has been applied previously
with success by various researchers, for example in Bangladesh (Kabir et al., 2010),
South Africa (Hoffman, 2007; Sandham and Pretorius, 2008; Sandham et al.,
2010/2008) and Lesotho (Talime, 2010).
8
1.6 ORGANISATION OF THE DISSERTATION
This dissertation is presented in five different chapters, and they are briefly
explained. Chapter 1 is based on the introduction and research background. This
chapter provides a brief introduction and outlines the research problem, research
objectives while providing justification and significance for the research. This is
presented together with a concise overview of the role and objectives of the scoping
process in environmental impact assessment, as well as the methodology applied in
undertaking such studies.
Chapter 2 deals with the review of literature pertaining to the research problem. This
chapter commences with an overview of the role of formal EIA practice as a tool
towards the achievement of informed environmental decision-making and the
sustainable development goal in the authorization of development proposals. In this
chapter, the role of scoping in the EIA process is specifically dealt with. The chapter
then proceeds to outline the role of EIA quality reviews as a measure of the
adequacy and functioning of the EIA system under which they are implemented.
Lastly, the chapter provides a concise summary of different methods employed both
locally and internationally to undertake EIA Report (EIR) / Environmental Statement
(ES) quality appraisals and the extent to which such methods have been applied in
South Africa and elsewhere on the continent.
Chapter 3 explains the research methodology used for the current research. This
chapter provides detail on the review package used in undertaking the quality
appraisal, as well as the factors leading to the selection of the chosen review
package. The chapter also provides an overview of aspects of the research relating
to data sourcing, data analysis, quality control and the minimisation of subjectivity
from the study.
Chapter 4 presents the research findings as well as their discussion. These findings
are presented in a series of tabular and graphic summaries. The findings are initially
presented and discussed separately for each of the four review areas and later on,
an overview of the overall quality of Scoping Reports is provided. Lastly, chapter 5
focuses on the conclusions and recommendations relevant for the study.
9
1.7 LIMITATIONS TO THE RESEARCH
Given the nature of the study (a minor dissertation), the research was only
undertaken for EIA Scoping Reports and did not include any quality evaluation of
subsequent stages. Research focussing only on scoping procedures is justifiable in
South Africa, in view of the revised and detailed substantive (or beefed-up)
requirements prescribed in the National Environment Management Act: EIA (2010)
Regulations. Lastly, only a limited number of 20 Scoping Reports were evaluated.
10
CHAPTER 2
LITERATURE REVIEW
2.1 INTRODUCTION
This study is primarily concerned with appraising the quality of Scoping Reports and
scoping procedures pertaining to environmental impact assessment (EIA) processes
in South Africa dealing with hazardous waste management activities; where such
includes hazardous waste storage, treatment, recovery, incineration as well as
disposal. This chapter commences with an overview of the role of formal EIA
practice as a tool towards the achievement of sustainable development goals and
informed environmental decision-making in respect of development proposals. The
role of scoping in the EIA process is specifically dealt with. The chapter then
proceeds to outline the role of EIA quality reviews as a measure of the adequacy and
functioning of the EIA system under which they are implemented. Lastly, the chapter
provides a concise summary of the different methods employed both locally and
internationally to undertake EIA Report (EIR) / Environmental Statement (ES) quality
appraisals and the extent to which such methods have been applied in South Africa
and elsewhere on the continent.
2.2 ENVIRONMENTAL IMPACT ASSESSMENT
2.2.1 The development of EIA practice
There has been a notable increase in consciousness and awareness over
environmental issues and problems in the last three decades; where such has been
mirrored by the introduction of legislation with ‘environmental protection’ focus in
many countries since (Hoffmann, 2007; Glasson et al., 2012). Glasson et al. (2012)
furthermore, describes the important role of introducing such legislation in
establishing the relationships between development proposals and the environment,
the prime purpose being to enhance the improvement of decision-making processes
both by planning and competent authorities.
11
The publication of Rachel Carson’s Silent Spring in 1962, as well as the publication
of Garret Hardin’s The Tragedy of the Commons in the same decade, contributed
significantly to what Aucamp (2010) describes as a drive toward increasing
environmental consciousness. Given the rapidly increasing impetus and momentum
with regard to the sustainability agenda, EIA legislation was first formally adopted by
countries such as, inter alia, the USA and UK as far back as 1969 and 1985,
respectively (Hoffmann, 2007; Glasson et al., 2012); where the USA’s National
Environmental Policy Act (NEPA) of 1969 has been an important model for the
development of other EIA systems since that time (Macintosh, 2010; Glasson et al.,
2012).
Environmental impact assessment (EIA) can be broadly described as the process of
assessing the potential environmental impacts of a proposed development proposal
on the receiving environment, such that informed decision-making around the
potential approval of such a project can take place (Lee and Colley, 1992; Sandham
and Pretorius, 2008; Sandham et al., 2008; Mbhele, 2009; Peterson, 2010). The UK
Department of Communities and Local Government (2006), as cited in Morris and
Therivel (2010), define the formal EIA process as the assimilation of information
relevant to the potential impacts of a development proposal, and subsequent
interrogation thereof towards informing decision-making with respect to
environmental permitting. The quality of decision-making on whether or not to
approve developments with potential environmental impacts is thus only as good as
the EIA process and the reporting mechanism used to inform such decision-making.
The early application of EIA, however, witnessed a discrete fragmentation of its
application toward assessing the impact of development actions on individual
biophysical aspects (e.g. impacts on air, water, soil and biodiversity), and it was only
in the late 1980’s that public participation and social impact assessment were
introduced into formal EIA practice (UP, 2012). It should always be kept in mind,
however, that it is the natural environment that provides the ecological goods and
services, as well as natural resources, on which all societies and associated
economic systems depend upon for their existence. The current approach to EIA can
thus see the potential significance of natural environmental aspects reduced,
comparable to EIA practice of 30 years ago, but “EIA should at all times be
12
maintained as a process that must seek to facilitate the attainment of sustainable
development through the careful assessment of all relevant considerations so as to
appropriately inform environmental decision-making” (UP, 2012: Chapter 1:1).
South Africa’s National Environmental Management Act (Act No. 107 of 1998)
[NEMA] provides for a broad ranging definition of the term ‘Environment’ that is
indeed cognisant of the broadening sustainability agenda in EIA practice and is
inclusive of biophysical (natural environment), social and economic elements, as well
as the interactions amongst and between these elements. EIA practice in the South
African context (which it must be said is not unique to EIA practice worldwide)
requires that a holistic approach be adopted to ensure that all relevant elements
contributing to the sustainability of decision-making in respect of development
proposals be given due and proportional consideration.
2.2.2 EIA in South Africa
EIA, as a formal means of informing decision-making concerning the potential
environmental impacts of development proposals, was first formally adopted in South
Africa under the auspices of the Environment Conservation Act (Act No. 73 of 1989)
[ECA]. EIA was practiced on a voluntary basis prior to this, but on a somewhat lesser
scale (UP, 2012). The promulgation of the ECA represented South Africa’s first
statute focused solely on environmental protection, and coincided with the
establishment of the first National Department of Environmental Affairs (DEA) around
that time (Aucamp, 2009).
The ECA was superseded by the National Environmental Management Act (Act No.
107 of 1998) [NEMA] in 1998, with the exception of Sections 21, 22, and 26 thereof,
as well as the ECA EIA Regulations, which were only repealed some time later in
2006 by Regulations promulgated under NEMA (Hoffmann, 2007). The
aforementioned NEMA EIA Regulations were amended in June 2010 by the DEA in
an attempt to further streamline EIA process in South Africa (namely GNR. 543, 544,
545 and 546 of 18th June 2010). Importantly, and in the context of this study, both
the ECA and NEMA advocate(d) a discrete scoping phase in requisite EIA practices
of their time, although the application of scoping as a discrete phase of EIA was
13
often lacking, or amalgamated with the EIA phase, through the submission for
decision-making of what Sandham and Pretorius (2008) refer to as ‘beefed-up
Scoping Reports’, under ECA.
NEMA furthermore provides for Ministerial powers for the promulgation of Specific
Environmental Management Acts (SEMA) thereunder, relating to the regulation of
specific environmental aspects and activities. It was these aforementioned provisions
that saw the promulgation of the National Environmental Management: Waste Act
(Act No. 59 of 2008) [NEM:WA] in June 2009 as a SEMA under the over-arching
principles and application of NEMA and its associated EIA Regulations. The
NEM:WA itself, as well as schedules of listed general and hazardous waste
management activities thereunder, set the framework for the management of waste
in South Africa, together with various strategy and policy documents. The minimum
administrative, procedural and content requirements for EIAs required in terms of the
NEM:WA are dictated by the 2010 NEMA EIA Regulations of 18th June 2010 (GNR.
543 of 18 June 2010).
NEM:WA makes clear provision for the holders of waste (with extension to waste
managers alike) to investigate, assess and evaluate the impact of that waste on
human health and well-being and the environment (Papu-Zamxaku et al., 2010). This
requirement is formalised through the publication of listed waste management
activities under NEM:WA, which guide waste generators and managers alike on the
requirements for a waste management licence application and EIA; where any such
EIA (be it a Basic EIA or Full Scoping and EIA process) is to be undertaken in terms
of the relevant provisions for such under the current NEMA EIA Regulations. Any
proposed activity involving the management (excluding storage <35m3) or disposal
of hazardous waste requires an application for a waste management licence to be
supported by a comprehensive scoping and an EIA process.
2.2.3 Scoping
Scoping was developed as a tool in EIA practice in the late 1980’s in order to identify
and focus on the important and pertinent potential environmental impacts of a
development proposal (UP, 2012). The importance of the scoping phase in the EIA
14
process thus needs to be given due recognition towards the relevance and quality of
decision-making around development proposals. Scoping in the EIA process,
whether as a distinct phase thereof, or integrated with the greater assessment, aims
to identify the priority issues from a broader range of potential impacts and issues for
assessment in the EIA (Wood, 2000; Aucamp, 2009; Glasson et al., 2012). In this
manner, keeping the focus of the EIA relevant and allowing the process to be
implemented efficiently and effectively. The importance of scoping, as a stand-alone
phase in EIA practice, is recognised by Kruger and Chapman (2005:52); where they
recommend that “the EIA process in South Africa reverts back to the ‘traditional’
scoping report, where scoping solely involves a thorough identification of issues.
This will eliminate the inconsistencies found between normal scoping reports and
‘beefed-up’ scoping reports”.
According to Hoffmann (2007), the review and quality appraisal of EIA reports and
processes is deemed necessary to ensure that the EIA system under which they
were developed achieves its ultimate goals. The preparation of high quality Scoping
Reports (where scoping is deemed an integrated precursor to actual impact
assessment) could thus under these auspices be seen as an effective translation of
EIA policy and regulations into practice (Talime, 2010).
According to DEAT (2004), Leu et al. (1996), Sadler (1996) and Wood (2003), as
cited in Sandham and Pretorius (2008:229), “Since the EIA Report (EIR) is a major
component of the EIA process, the quality of the report can contribute towards better
decision-making regarding environmental issues, and a review of EIR quality is
therefore an important aspect of measuring the effectiveness of EIA process”.
Similarly, the quality of Scoping Reports can contribute toward the quality of the
overall EIA process and thus ultimately the quality of the decision-making processes
which it is intended to guide and inform.
2.3 HAZARDOUS WASTE MANAGEMENT IN SOUTH AFRICA
Waste management in South Africa has since the late 1990’s been largely informed
by a series of documents called the Minimum Requirements 2nd Edition, which was
published by the then Department of Water Affairs and Forestry in 1998 as ‘Minimum
15
Requirements for the Handling, Classification and Disposal of Hazardous Waste;
Minimum Requirements for Waste Disposal by Landfill; and Minimum Requirements
for the Monitoring of Water Quality at Waste Management Facilities’, respectively.
These minimum requirements were aimed at providing a norm by means of which
authorities, waste generators, permit- and licence holders and other interested and
affected parties (I&APs) could differentiate acceptable waste management practices
from unacceptable practices. The classification and management provisions in the
Minimum Requirements Series had no legal standing in itself, although certain
provisions thereof were historically formalised and enforced in varying degrees
through inclusion into the conditions of waste permits issued in terms Section 20 of
the Environment Conservation Act (Act No. 73 of 1989) [ECA], as well as
subsequent waste management licences issued in terms of NEM:WA.
Through the implementation of the Minimum Requirements Waste Classification
System over the past 15 years, a number of short-comings were identified by
regulatory authorities, industry and waste managers. In an attempt to address these
issues, a draft 3rd Edition of the Minimum Requirements was published in 2005, but
the revised system was never finalised and implemented.
2.3.1 Hazardous waste management reform in South Africa
In the light of the aforementioned, the Department of Environmental Affairs (DEA),
has initiated a project in 2009 to develop a revised waste classification and
management system for South Africa, which would support the move away from
landfilling towards waste management options which favour waste recovery and
reuse, and address some of the concerns that have been raised with respect to
implementing the current Minimum Requirements, 2nd Edition (Thorpe et al., 2012). It
was the DEA’s intention that this new National Waste Classification and
Management System be formalised into Regulations under NEM:WA, with
associated Schedules and/or Norms and Standards in terms of the Act as
appropriate.
The DEA ultimately, on the 23rd August 2013, promulgated the Waste Classification
and Management Regulations under the NEM:WA, together with two Standards for
16
the Assessment and Disposal of Waste to Landfill. This new approach to the
classification of waste, as well as the assessment thereof for disposal to landfill
(where indeed landfilled) represents a notable paradigm shift away from the previous
system in the Department of Water Affairs’ Minimum Requirements for the Handling,
Classification and Disposal of Hazardous Waste (2nd Ed., DWAF, 1998).
The ‘new’ regulations require that wastes be classified in terms of SANS 10234, the
Globally Harmonized System of Classification and Labelling of Chemicals (GHS),
which provides the criteria for classification of waste based on physical, health and
environmental hazards (TABLE 1) (Crous and Thorpe, 2012). In addition, unlike the
minimum requirements, the new regulations do not prescribe specific management
requirements based on whether a waste is classified as hazardous or not,
particularly the type of landfill in which these wastes are to be disposed of (Crous
and Thorpe, 2012).
TABLE 1: Hazard Classes of the SANs 10234 (GHS) Classification System.
Physical Hazards Health Hazards Hazards to the
Aquatic
Environment
Explosives
Flammable gases
Flammable aerosols
Oxidizing gases
Gases under pressure
Flammable liquids
Flammable solids
Self-reactive substances
Pyrophoric substances
Self-heating substances
Substances that emit flammable
gases on contact with water
Oxidizing substances
Organic peroxides
Corrosive to metals
Acute toxicity
Skin corrosion & skin irritation
Serious eye damage & eye
irritation
Respiratory sensitization & skin
sensitization
Germ cell mutagenicity
Carcinogenicity
Reproductive toxicity
Specific target organ toxicity:
single exposure
Specific target organ toxicity:
repeated exposure
Aspiration hazards
Acute aquatic
toxicity
Chronic aquatic
toxicity
17
The Department of Environmental Affairs’ proposed new approach to the
assessment of waste for disposal to landfill requires a comparison of the Leachable-
(LC) and Total Concentrations (TC), of chemical contaminants reasonably believed
to be contained therein, with specified threshold limit values in order to determine a
‘risk profile’ for the waste (Thorpe et al., 2012). This assessment designates five
types of waste, each with specific corresponding disposal requirements (TABLE 3).
Particular types of waste are required to be disposed of at one of four new classes of
landfills, each with a proposed new pollution containment barrier designs (Thorpe et
al., 2012). The Standards also include specific waste disposal prohibitions, aimed at
eliminating the disposal of certain wastes within a set period of time (TABLE 2)
(Thorpe et al., 2012).
TABLE 2: Waste Disposal Restrictions under the Standard for Disposal of
Waste to Landfill (GNR 645 of 23 August 2013).
Waste Prohibited or Restricted in terms of Disposal Compliance
Time-frame
(a) Waste which, in the conditions of a landfill, is explosive, corrosive, oxidizing, or
flammable (according to SANS 10234 or SANS10228). Immediate
(b) Waste with a pH value of <6 or >12. Immediate
(c) Reactive waste that may react with water, air, acids or components of the waste, or
that could generate unacceptable amounts of toxic gases within the landfill. Immediate
(d) Waste compressed gases (according to SANS 10234 or SANS 10228). Immediate
(e) Untreated Healthcare Risk Waste (HCRW). Immediate
(f) (i) POPs pesticides listed under the Stockholm Convention.
(ii) Other waste pesticides.
Five (5) years
Three (3) years
(g) Lead acid batteries. Immediate
(h) Other batteries Eight (8) years
(i) Re-usable, recoverable or recyclable used lubricating mineral oils, as well as oil filters,
but excluding other oil containing wastes. Four (4) years
(j) Reclaimable or recyclable used or spent solvents. Five (5) years
(k) PCB containing wastes (>50 mg/kg or 50 ppm). Five (5) years
(l) Waste Electric and Electronic Equipment (WEEE) – Lamps. Three (3) years
(m) Waste Electric and Electronic Equipment (WEEE) – Other. Eight (8) years
(n) Waste tyres: Whole. Immediate
(o) Waste tyres: Quartered. Five (5) years
(p) Liquid waste–
(i) Waste which has an angle of repose of less than 5 degrees, or becomes free-
flowing at or below 60ºC or when it is transported, or is not generally capable of being
Five (5) years
18
Waste Prohibited or Restricted in terms of Disposal Compliance
Time-frame
picked up by a spade or shovel; or
(ii) Waste with a moisture content of >40% or that liberates moisture under pressure in
landfill conditions, and which has not been stabilised by treatment.
(q) Hazardous waste with a calorific value of:
(i) > 25 MJ/kg.
(ii) > 20 MJ/kg.
(iii) > 10 MJ/kg.
(iv) > 6% TOC.
Four (4) years
Six (6) years
Eight (8) years
Ten(10) years
(r) Brine or waste with a high salt content (TDS > 5%), and a leachable concentration for
TDS of more than 100 000 mg/l. Eight (8) years
(s) Disposal of garden waste:
(i) 25% diversion from the baseline at a particular landfill of separated garden waste.
(ii) 50% diversion from the baseline at a particular landfill of separated garden waste
Five (5) years
Ten (10) years
(t) Infectious animal carcasses and animal waste Immediate
TABLE 3: Waste Type Determinations and Landfill Requirements under the
Waste Classification and Management Regulations (GNR 643 of August 2013).
Disposal Risk Rating Landfill Disposal Requirements Type 0: Very High Risk LC > LCT3, or TC > TCT2
The disposal of Type 0 waste to landfill is not allowed. The waste must be treated and re-assessed in terms of the Standard for Assessment of Waste for Landfill Disposal to determine the level of risk associated with disposing the waste to landfill.
Type 1: High Risk LCT2 < LC ≤ LCT3, or TCT1 < TC ≤ TCT2
Type 1 waste may only be disposed of at a Class A landfill
Type 2: Moderate Risk LCT1 < LC≤ LCT2, and TC ≤ TCT1
Type 2 waste may only be disposed of at a Class B landfill
Type 3: Low Risk LCT1 < LC ≤ LCT0, and TC ≤ TCT1
Type 3 waste may only be disposed of at a Class C landfill
Type 4: ‘Inert’ Waste LC ≤ LCT0, and TC ≤ TCT0
Type 4 waste disposal allowed at a Class D landfill
19
2.3.2 Challenges facing hazardous waste management in South Africa
The healthcare risk waste (HCRW) industry in South Africa, for example, was
described by the then Deputy Director-General of Environmental Affairs and
Tourism, Joanne Yawitch, as being “...in crisis. It is cut-throat and something is very
wrong...” (Sunday Times, 2 December 2007; as cited in DA, 2009:2). According to
the Democratic Alliance (DA) discussion document published in October 2009, on
“addressing problems in the medical waste sector”, the illegal dumping and storage
of medical waste in South Africa were described as verging on a national crisis. The
aforementioned discussion document claimed that as much as 800 tons of medical
waste is believed to be illegally dumped each year in South Africa (DA, 2009).
“Untrained personnel, lax oversight, poor regulation, dodgy tenders and the murky
delineation of responsibilities” were sighted in the aforementioned discussion
document as being the root of the problem (DA, 2009:4).
Although having featured prominently in the South African press in recent times, the
challenges faced in the HCRW management industry are not unique, with similar
problems facing the greater hazardous waste management sector nationally. The
illegal dumping of other types of hazardous waste is also not uncommon in South
Africa; where capacity to police such activities remains a problem. The South African
Department of Environmental Affairs’ 2012/13 National Environmental Compliance
and Enforcement Report, by way of example, indicates a total of 209-waste related
(NEM:WA) contravention being investigated nationally within the indicated reporting
period. The highest sentence handed down in the reporting period was incidentally
related to pollution and a waste case; where the guilty party was sentenced to a fine
of R 200 000 or 6 years imprisonment, with half suspended for 5 years.
There are only a handful of licensed hazardous waste disposal sites in South Africa,
located in only four of South Africa’s nine provinces, i.e. Gauteng, Western Cape,
Eastern Cape, and Kwazulu-Natal. The most notable of which are the Holfontein
Hazardous Waste Disposal Facility in Springs, Gauteng, and the Vissershok
Hazardous Landfill, just outside of Cape Town in the Western Cape.
20
Section 16 of NEM:WA places a general duty on waste generators to take all
reasonable measures to reduce, reuse, recycle, and recover their waste. This is a
challenge in respect of hazardous waste management, with limited management
alternatives to disposal presently available in the South African context. The disposal
of hazardous waste to land in South Africa, irrespective of the volume disposed of or
the area covered, is an activity requiring a waste management licence; with the
aforementioned license application to be supported by a scoping and EIA process so
as to allow for informed decision-making on the part of the competent authority (i.e.
the Department of Environmental Affairs).
2.4 METHODS OF APPRAISING EIA QUALITY
Many analytical methods can be applied to the assessment of the quality of EIA
Reports. These range from the matrices adopted by Leu et al. (1996) in Taiwan, to
the more commonly applied review packages and checklists adopted elsewhere in
developed and developing nations (Sandham and Pretorius, 2008).
2.4.1 Lee and Colley EIR Review Package
The so-called ‘Lee and Colley’ Review Package has been widely used to review the
quality of environmental statements of proposed project environmental impact
assessments (EIA). Ibrahim (1992), Rout (1994), as well as Mwalyosi and Hughes
(1998) describe this particular review package as the most commonly applied
package in respect of EIA quality reviews in both developed and developing nations
(cited in Sandham et al., 2008). Lee and George (2000) as well as Glasson et al.
(2005) also make assertions as to the wide reaching application of the package
worldwide in EIR quality appraisals. The package has furthermore been adapted in
many instances to undertake, on a more strategic level, quality assessments of
environmental appraisals for local government plans, policies and programmes
(Simpson, 2001).
The methodology applied by Lee and Colley is comprehensively described in
Chapter 3. For the sake of comparison with other, similar, review packages
described in this section, a summarised description of the package is provided. The
21
quality review method using the Lee and Colley Review Package involves evaluating
how well a number of assessment tasks (Sub-categories, Categories and Review
Areas) have been conducted (Talime, 2010). Then drawing upon such assessments,
subsequent reviews proceed upwards progressively from one level to the next whilst
applying more complex criteria to broader tasks until the whole assessment is
completed. A nominal scale from A to F is used to denote the completeness and
quality of the review categories across the four-tier hierarchical structure of the
package (Lee et al., 1999; Sandham et al., 2010). Whereas the alphabetical letter ‘A’
is denoting superior EIA quality; the letter ‘F’ represents inferior or unacceptable EIR
Report quality whereby no attempt has been made by the environmental assessment
practitioner (EAP) to address the review category adequately.
2.4.2 European Commission Guidelines
The EC Guidelines for the review of EIR quality consist of a three-tier checklist type
system that asks 143 sequential review questions distributed across seven different
sections ranging from the ‘description of the project’ through to ‘quality of
presentation’ (Peterson, 2010; Talime, 2011). The guidelines are similar to the Lee
and Colley EIR Review Package in that a simple nominal scale from A to E is used
to assist a reviewer in answering the review questions; where positive answers from
A to C would be regarded as sufficient provision of information for decision-making
with differing levels of quality, and D to E corresponding with poor EIR quality and
the provision of insufficient information to appropriately inform decision-making
(Peterson, 2010).
A three level approach is used by a reviewer in applying the questionnaire to a
review, as follows (Peterson, 2010):
1. A reviewer firstly questions the relevance of each of the review questions to
the subject project, by simply answering ‘yes’ or ‘no’;
2. A reviewer then answers the relevant review questions using the nominal
scale described in the preceding paragraph; and
3. Finally, the reviewer uses the same nominal scale to assess the overall EIR
quality, using the answers to the relevant review questions to inform such an
overall assessment.
22
The EC guidelines differ from the Lee and Colley Review Package in that the
questions to be answered by a reviewer are only asked in one of the three primary
review areas. These areas being the level of the sub-section under each of the
seven respective review sections, as well as at an ‘overall EIR quality’ level. The Lee
and Colley Review Package, however, requires reviewer to appraise quality at four
levels; where these are the i) the overall EIR quality synopsis ii) review areas, iii)
review categories and iv) review sub-categories.
2.4.3 Oxford-Brookes University Review Package
Talime (2010) describes the EIR review package developed by the Oxford-Brookes
University as a type of hybrid between the Lee and Colley Review Package (1992)
and the aforementioned EC guidelines developed for EIR review; where the review
package is commonly called the ‘Impact Assessment Unit’ (IAU) Review Package,
by virtue of its origin of development within the stated unit of the Oxford Brookes
University (Glasson et al., 2005). This review package was developed to specifically
evaluate changes in EIR quality over time.
The review package also takes a hierarchical approach to EIR quality appraisal;
where similar to the Lee and Colley Review Package (1992), the review criteria (of
which there are 92 in total) are distributed amongst review categories (of which there
are eight), and their underlying review sub-categories (Talime, 2010). Whereas the
Lee and Colley Review Package assesses EIR quality across four levels, the subject
package excludes review areas and thus only assesses three hierarchal levels of
quality in the EIR.
2.4.4 Legal compliance
The review package used to appraise EIR or Scoping Report quality, further to
exploring the application of best practice principles in the development thereof
(reporting and procedurally), should at least assess the EIR/ Scoping Report’s
compliance according to the requisite minimum legal requirements for such in the
country of origin for the development of such reports. The Lee and Colley Review
Package (Lee et al., 1999) in fact requires that the sub-categories that broadly
correspond with regulatory minimum requirements be specifically listed by the
23
reviewer. In fact, Kruger and Chapman (2005) adopted a checklist type approach to
EIR quality review in the Free State Province of South Africa, based almost solely on
the requirements of the South African EIA Regulations and EIA guidelines published
by government.
2.5 EIA QUALITY APPRAISAL IN SOUTH AFRICA
The quality review of Environmental Impact Reports (EIR) for EIA process in South
Africa was until very recently limited to a small handful of studies with geographic,
sectoral and/or activity specific focus. The Lee and Colley Review Package has been
used with success locally to appraise the quality of EIRs. This has been done for i)
the provincial level in the North West Province (Sandham and Pretorius, 2008), ii)
the mining, explosives and housing sectors (Hoffman, 2007; Van der Vyver, 2008
and Mbhele, 2009, respectively), filling stations (Kruger, 2012), as well as for iii)
environmental aspect specific EIR quality appraisals relating to projects with
potential impacts on wetland systems (Sandham et al., 2008) and the release of
genetically modified organisms (Sandham et al., 2010).
As a matter of fact, Sandham and Pretorius (2008) adapted the package to create
the North West University (NWU) Review Package, for EIR quality review in the
North West Province. Hoffman (2007) further adapted the NWU Review Package
toward assessing EIR quality within the South African mining sector; where such led
to the development of the Potchefstroom Review Package for the Mining Industry
(PRPMI).
Furthermore, until as recently as 2013 (Sandham et al., 2013), no EIA quality studies
had been undertaken to review EIRs on a national scale, nor those in the hazardous
waste management sector. Moreover, the majority of available literature to date on
EIR quality appraisals undertaken for EIA processes in South Africa have been
executed in terms of the Environment Conservation Act (Act No. 73 of 1989) [ECA],
which was almost entirely repealed by the provisions of National Environmental
Management Act (Act No. 107 of 1998, as amended) [NEMA] in 2006. It appears
that it is only Sandham et al. (2013) to date who have assessed South African EIA
24
Report quality in terms of EIAs conducted in terms of the 2006 NEMA EIA
Regulations.
The latter study by Sandham et al. (2013) provided a comparative quality review, on
a national scale, of EIAs conducted in terms of the 2006 NEMA EIA Regulations,
against those conducted in terms of the previous regulatory regime under the ECA.
The findings of the study showed that despite attempts to improve overall EIR quality
through regulatory reform (i.e. the promulgation of the 2006 NEMA EIA Regulations),
the quality of EIRs under ECA was in fact superior to those compiled under the new
regulations (Sandham et al., 2013).
25
CHAPTER 3
RESEARCH METHODOLOGY
3.1 INTRODUCTION
The quality appraisal of 20 Scoping Reports was undertaken using an adaptation of
the environmental statement (ES) review package developed by Lee and Colley in
1990 [ES, hereinafter, known as environmental impact assessment report (EIR) in
South Africa], and then published with minor amendment in 1992 (Lee et al., 1999).
3.2 LEE AND COLLEY REVIEW PACKAGE
This specific review package was selected because it has been widely used and
successfully adapted to i) different environmental-legal regimes in different countries
(i.e. other than the UK where it originally was developed), as well as ii) specific
development typologies. Lee et al. (1999) clearly state that the review package can,
with limited amendment, be adapted and applied successfully in other countries. The
review package amendments were implemented in a manner that accounted for the
specific provisions for scoping procedures outlined in the 2010 NEMA EIA
Regulations (Lee et al., 1999). The review package used also considered
adaptations already made by Sandham and Pretorius (2008) for applicability to the
South African EIA system context, and it has already been used successfully in the
South African context (Hoffman, 2007; Mbhele, 2009).
3.2.1 Sample size selection
The chosen sample size was selected on the basis of previous EIR quality
appraisals cited in existing literature (Talime, 2010:- 15 EIRs in Lesotho; Mbhele,
2009:– 20 EIRs; Hoffman, 2007:- 20 EIRs specific to the mining sector in the North
West Province of South Africa; Sandham et al., 2008:– 4 EIRs specific to projects
with potential impacts on wetland systems in South Africa; Sandham and Pretorius,
2008:– 28 EIRs undertaken in the North West Province of South Africa; Peterson,
2010:- 50 EIRs in Estonia).
26
The review package entails the hierarchical assessment of a list of criteria or review
topics (Lee et al., 1999). The assessment begins with an assessment of review sub-
categories, arranged in an ordered manner beneath, broader, review categories and
review areas. The completeness / appropriateness of each respective review topic
was rated by the reviewer(s) according to the nominal scale developed by Lee et al.
(1999). A letter was ascribed to each review topic during the review, with an ‘A’, for
example, indicating that the relevant tasks catered to by the review topic were well
performed with no important tasks left incomplete, and an ‘F’ being indicative of very
unsatisfactory performance with important tasks having been all omitted, or very
poorly completed (TABLE 4).
The system of aggregation used for reporting ‘quality’ under Chapter 4 hereto has
been adapted from Van der Vyver (2008); where the symbols A-C are taken to
reflect reports, review areas, categories and sub-categories that are of a satisfactory
quality, with symbols D-F being synonymous with unsatisfactory quality,
respectively.
Similarly, symbols A and B are used as a broad measure of reports, review areas,
categories and sub-categories that have been well performed with only minor
omissions, and with symbols E and F used to denote the extreme opposite end of
the scale (i.e. unacceptable performance with reasonable ground for rejection by
competent authorities and the inability for IAPs to comment meaningfully,
respectively (TABLE 5).
27
TABLE 4: Assessment Symbols for Review Topics (Lee and Colley).
Symbol Explanation Aggregation
A Generally well performed, no important tasks left incomplete.
Satisfactory
B Generally satisfactory and complete, only minor omissions and
inadequacies.
C Can be considered just satisfactory despite omissions and or
inadequacies.
D Parts are well attempted bust must, as a whole be considered
just unsatisfactory because of omissions or inadequacies.
Unsatisfactory E Not satisfactory. Significant omissions or inadequacies.
F Very unsatisfactory, important task(s) poorly done or not
attempted.
N/A Not applicable. The review topic is irrelevant in the context of the
subject Scoping Report N/A
TABLE 5: Assessment Symbol Aggregation.
The review commences with a review of sub-categories. The sub-category
assessments, together with any other impressions gained from the report, are then
used to assess the corresponding review categories. Likewise, the assessment of
the review categories is used to assess the corresponding review areas, which
Symbol Aggregation
A Well Performed
Satisfactory B
C -
D -
Unsatisfactory E Poorly Performed
F
N/A - -
28
assessment is in turn used to document an overall assessment rating for each of the
subject reports (FIGURE 2 and FIGURE 3).
FIGURE 2: The Assessment Pyramid.
Source: (Lee et al. 1999).
FIGURE 3: Schematic Representation of the Review Topic Hierarchy in Review
Areas 1 & 2.
Source: Lee et al. (1999).
29
3.2.2 Primary data sourcing procedures
3.2.2.1 Sourcing Primary Data from Department of Environmental Affairs
Initial efforts to source the Scoping Reports necessary to undertake the study were
focused on obtaining them in hardcopy from the National Department of
Environmental Affairs (Directorate: Waste Management Licensing). Following a
telephonic request, the Department courteously provided access to the report
hardcopy archives, and 20 Scoping Reports for hazardous waste management EIA
processes were randomly selected from existing departmental archives. All selected
reports had been compiled subsequent to the promulgation of the National
Environmental Management: Waste Act (Act No. 59 of 2008) [NEM:WA].
3.2.2.2 PAIA Application and Administrative Fees
Policy at the Department of Environmental Affairs dictates that no original hardcopy
versions of the selected reports could be removed from the Department’s premises.
For this reason, a formal, written, request for copies of the selected Scoping Reports
had to be made in terms of the Promotion of Access to Information Act (Act No. 2 of
2000) [PAIA]. The submission of the PAIA application was subject to payment of a
nominal administrative fee. Following the submission of the PAIA application, not all
of the requested copies were forthcoming, and when they were made available there
were missing elements or sections. Subsequently, the reasons for such an outcome
were not made clear nor communicated further to the application. Unfortunately, the
delays experienced in sourcing the required reports or missing elements
necessitated a change in approach, which then involved obtaining the required
reports from an alternative source, namely, the various EAP websites in South
Africa.
3.2.2.3 EAP Websites
Given some material omissions in some of the Scoping Reports provided by the
Department of Environmental Affairs, and resultant delays which could jeopardise
the planned schedule for the current research project, the required 20 Scoping
Reports were ultimately accessed in soft copy from websites of a range of
30
environmental assessment practitioners (EAP) that deal with hazardous waste
management EIAs in South Africa. Again, the Scoping Reports obtained were
compiled subsequent to the promulgation of the NEM:WA on 1st July 2008. Obtaining
primary data in this manner is also acceptable, especially as it is common practice in
South Africa for EAPs to use their consulting company websites, as one of the
platforms for obtaining stakeholder review and comment on draft, as well as finalised
Scoping and EIA Reports.
3.2.3 Primary data analytical procedures
3.2.3.1 Report Reviewing
Prior to reviewing all the 20 Scoping Reports, a sample of ten was subjected to an
external moderation review by an independent reviewer. The purpose of the double
reviewer mechanism was to ensure that the review package yields consistent and
objective appraisals. Lee et al. (1999:42) state that, “It should be noted that, in order
to promote objectivity in ES reviewing, it is recommended that each ES [EIR] should
initially be separately reviewed by two different reviewers who should then
endeavour to reconcile any differences when finalising a joint review”.
Subsequently, the following broad review areas were carefully adapted (Lee et al.,
1999; Sandham and Pretorius, 2008) to be in line with the current research problem.
Adjustments made were as follows:
1. Description of the proposed waste management activities, associated
structures and infrastructure, the receiving environment of the site
(baseline conditions);
2. Scoping;
3. Legislative, guideline and policy review; and
4. Communication of results.
The need to adapt the Potchefstroom Review Package arose mainly because in the
current research the focus is on Scoping Reports and not the entire environmental
assessment process under the NEMA EIA Regulations. Whilst aligned toward
achieving the same end goal (i.e. informed decision-making around development
31
proposals with the potential to impact on the environment), the aims and objectives
of the scoping phase of an EIA process are quite different to those of the subsequent
impact assessment phase. The reporting requirements for each of these distinct
phases in the EIA process are also different. A few of the key differences leading to
the review package adaptation are discussed below.
Firstly, scoping is intended to comprehensively identify potential issues and impacts
of concern that may result from a development proposal. The scoping phase does
not, however, require the detailed evaluation of, for instance, impact significance.
Specialist studies aiding in impact significance assessment are also only
implemented during the EIA phase of the assessment. Secondly, while the scoping
phase requires the identification of potential alternatives to a development proposal,
it is only at the EIA phase that the potential significance of each need to be assessed
exhaustively. Lastly, it would also be premature to discuss and assign mitigating
measures to impacts identified at the scoping phase; a stage when the EAP has not
yet evaluated the significance of identified impacts and the need and potential to
mitigate them.
It is for these reasons that the review package was adapted, in order to maintain its
relevance to the scope of the current research. A quality review concerning the
consideration and documentations of ‘impact mitigation’ would, for example, be a
moot exercise in the context of this research scope. An evaluation of ‘impact
significance’ too would be a disputable exercise; as would the i) the detailed
assessment and selection of alternatives, ii) the documentation and integration of
specialist study findings, as well as, iv) EAP recommendations and impact
statements. Therefore, any review area, category or sub-category with no defensible
relevance to scoping was removed from the package.
However, the requirements, for example, relating to the description of i) the proposed
activity, ii) the site in question and ii) the receiving environment of the site remain
common requirements across all reporting phases of the EIA process under the
NEMA EIA Regulations. Any such review areas, categories or sub-categories were
left largely unchanged in subject review package. The same is principally true for
stakeholder engagement. Review Area 4 was left altogether unchanged; where the
32
appropriate communication of results remains a principle requirement across all
reporting phases of the EIA process. In adapting the review package, the inclusion of
minimum legal requirements (as either a review area, category, or sub-category)
under the NEMA EIA Regulations was also affected. This is particularly true in
respect of the total revision to Review Area 3; where it was decided that the current
scope thereof was largely irrelevant to ‘Scoping’, and where the importance of
identifying and considering legislation, guidelines and policies relevant to the
development proposal was not deemed adequately catered for in the Potchefstroom
Review Package. The sub-division of review categories and associated sub-
categories is summarised as follows (TABLE 6).
TABLE 6: Tabular Summary of Review Areas, Categories and Sub-categories
Used.
Review area 1 - Description of the activity(ies) and the environment 2.2.2 All possible impacts must be
identified
1.1 DESCRIPTION OF THE ACTIVITY(IES) 2.2.4
Impacts identified for
alternatives under
consideration
1.1.1 Identification of Applicant 2.3 STAKEHOLDER ENGAGEMENT
1.1.2 Identification of EAP 2.3.1 Example of notice published
in media
1.1.2 Need and desirability of the Activity(ies) 2.3.2 On-site notice
1.1.3 Description and nature of activity/development 2.3.3 Identify affected people
1.1.4 Description of site 2.3.4 Identify people that have an
interest in the project
1.1.5 Site plan: Sighting of project with respect to surrounding land uses and activities 2.3.5
Procedure whereby
interested and affected
parties can participate
1.1.6 Description of waste management processes & technology employed 2.3.6
Provision for interested and
affected parties to express
their views
1.1.7 Raw materials used during different phases 2.3.7 List of issues identified
1.1.8 Source and availability of water and materials 2.3.8 Notification criteria
1.2 SITE DESCRIPTION: Description of onsite land requirements and duration of each land use 2.3.9 Record of all views as an
addendum
1.2.1 Site Plan 2.3.10
Evidence that interested and
affected parties were
approached
1.2.2 Description and demarcation of land use areas 2.3.11 Key impacts / issues raised
1.2.3 Estimated duration of different phases 2.4 PLAN OF STUDY FOR EIA
1.2.4 Expected number of workers and visitors 2.4.1 Method of impact
significance assessment
1.2.5 Access to site and likely means of transport 2.4.2 Specialist assessment(s)
1.2.6 Infrastructure required 2.4.3 Public participation for EIA
phase
33
1.3 WASTE Review Area 3 - Legislative,
Guideline and Policy Review
1.3.1 Waste characterisation / classification (managed) 3.1 LEGAL
1.3.2 Volumes managed 3.1.1 Trigger Legislation /
Regulations
1.3.3 Effluent generated from waste management activity 3.1.2 Other Relevant Legislation
1.3.4 Emissions generated from waste management activity(ies) 3.2 POLICIES / GUIDELINES
1.4 ENVIRONMENTAL DESCRIPTION: Area and location likely to be affected by development 3.2.1 Policy / Guidelines
1.4.1 Indication of likely area to be affected 3.2.2 Spatial Development and
Sectoral Plans / Frameworks
1.4.2 Biophysical description Review Area 4 - Communication of
Results
1.4.3 Biological description 4.1 LAYOUT
1.4.4 Social characteristics 4.1.1 Introduction
1.4.6 Important components of the affected environment 4.1.2 Arrangement of information
1.5 ALTERNATIVES 4.1.3 External sources
1.5.1 Description of methods used to identify alternatives 4.2 PRESENTATION
1.5.2 Description of analysis of range of alternatives 4.2.1 Presentation of information
1.5.3 Due consideration of no-go alternative 4.2.2 Presented as an integrated
whole
Review Area 2 - SCOPING 4.3 EMPHASIS
2.1 DEFINITION OF IMPACTS & METHODS USED 4.3.1 Prominence and emphasis
given to
2.1.1 Description of potential effects of project on environment 4.3.2 Scoping Report is unbiased
2.1.2 Description of methods used to identify potential impacts and issues 4.4 NON-TECHNICAL SUMMARY
2.2 IDENTIFICATION OF IMPACTS 4.4.1
Non-technical summary
including main findings and
conclusions
2.2.1 Assessing impact activities from four different phases 4.4.2 Scoping Report summary of
main issues
2.2.3 Impacts from non-standard operating procedure or deviation from baseline conditions
34
CHAPTER 4
RESEARCH FINDINGS AND DISCUSSION
4.1 INTRODUCTION
Four different sets of research findings were obtained from this study. Firstly, the
quality of a limited sample of EIA Scoping Reports was evaluated, of which
satisfactory or unsatisfactory quality or grades in between these extremes are
highlighted. Secondly, the results identify strengths and weaknesses in scoping
procedures involved, of which such an assessment is vital for improving EIA
effectiveness and environmental decision-making. Thirdly, the results show and
demonstrate whether or not the scoping processes undertaken are complying with
existing and relevant environmental legislation, regulatory provisions and other
criteria of EIA effectiveness. Lastly, some recommendations for further study are
made.
The cumulative frequency stemming from waste management activity categories
associated with Scoping Reports reviewed in this research is provided below
(TABLE 7). Based on the table, it can be seen that the scope of the reports reviewed
is wide and varied. Moreover, each of the 20 Scoping Reports reviewed entailed
more than one waste management activity type as shown in the table.
TABLE 7: Frequency of Specific Waste-Management Activities in the EIRs
under Scrutiny.
Hazardous waste management activity No. of occurrences
Storage of hazardous waste 10
Treatment of hazardous waste 9
Recovery of hazardous waste 9
Hazardous waste recycling 1
Hazardous waste disposal to landfill 4
Decommissioning of hazardous waste management facility 2
35
The proposed locations of the various waste management activities linked to the
Scoping Reports being reviewed for EIA quality involved Gauteng (13), Mpumalanga
(2), Kwazulu-Natal (3), and Limpopo (2) provinces in South Africa. The sectors
specific to the proposed waste management activities included i) waste management
(9), ii) electricity generation (2), iii) mining/industrial (6), iv) paper/pulp (2) and v)
tertiary education (1).
4.2 REVIEW AREA 1: DESCRIPTION OF THE PROPOSED
ACTIVITIES AND RECEIVING ENVIRONMENT
A description of the proposed hazardous waste management activities / facilities,
coupled with a description of the receiving environment (i.e. baseline environmental
description), is imperative toward developing an informed understanding of a
proposed project’s potential impacts on the receiving environment and visa versa. If
either the project or the receiving environment are poorly understood and described,
it may have negative ripple effects in the proper identification of potential impacts
and issues resulting from their proposed interactions.
Of the 20 Scoping Reports reviewed, 70% were generally satisfactorily performed
while 30% were unsatisfactorily conducted regarding Review Area 1. Review Area 1
entails the ‘Description of Activities and the Environment’ (FIGURE 4). Amongst the
satisfactory category, it was found out that 55% of these Scoping Reports were well
performed. On the other hand, 15% of them were poorly performed (FIGURE 4).
These research findings bear some resemblances with the quality review conducted
by Kruger (2012) who found out that 65% of EIA Reports evaluated according to this
criterion were of satisfactory quality level. By contrast, studies conducted by Van Der
Vyver (2008) and Mbhele (2009) revealed that all (100%) of the EIA Reports they
have assessed for quality considerations were generally satisfactorily carried out.
Eighty percent (80%) of the reports were performed satisfactorily in terms of
providing a description of baseline environmental conditions of the development site
(Review Category 1.4) (TABLE 8), as well as a description of the proposed waste
management activities (Review Category 1.1) (TABLE 8).
36
Nevertheless, it is noted with environmental management concern that 45% of the
Scoping Reports reviewed performed unsatisfactorily when it came to identifying and
describing alternatives to be considered and analysed further during the EIA phase
which involves a detailed assessment (Review Category 1.5) where this is a
requisite legal requirement (as with the criteria under Review Categories 1.1 to 1.4)
in terms of the current NEMA EIA Regulations. Unsatisfactory quality was also
observed with respect to the identification and description of waste and residuals
(Review Category 1.3,TABLE 8); where 35% of Scoping Reports were reviewed as
not complying with this specific criteria. Similarly, this is concerning given the
sectoral focus of this research. It can be argued that the ability for stakeholders to
participate meaningfully in the EIA process, as well as the quality of decisions taken
by competent authorities, may be compromised by a poor understanding of the
wastes and residuals involved in the waste management activities for which
environmental authorisation is being requested.
TABLE 8: Tabular Summary of Review Results for Review area 1 and
Associated review Categories.
Review area and category numbering / descriptions
Well performed
Satisfactory,
minor omission
s
Satisfactory,
omissions,
inadequacies
Unsatisfactory
Poorly attemp
ted
No attem
pt
Not applica
ble
SUMMARY OF REVIEW AREA 1 CATEGORY SCORES: 'Description of the activity(ies) and the environment’
A B C D E F G
1.1 Description of the development 0% 55% 25% 10% 10% 0% 0%
1.2 Site description 0% 30% 30% 20% 15% 5% 0%
1.3 Waste and residuals 25% 20% 20% 15% 5% 15% 0%
1.4 Environmental description / Baseline
50% 20% 10% 15% 5% 0% 0%
1.5 Alternatives 50% 5% 0% 30% 10% 5% 0%
FINAL GRADE REVIEW AREA 1 15% 40% 15% 15% 15% 0% 0%
37
FIGURE 4: Review Area 1 - Description of Project and Receiving Environment
TABLE 9: Review Area 1, Scoring of Quality Level for Sub-categories.
Review areas and category numbering / descriptions Well
performed
Satisfactory, minor
omissions
Satisfactory, omissions,
inadequacies Unsatisfactory
Poorly attempted
No attempt
Not applicable
Review area 1: Description of the activity(ies) and the environment A B C D E F G
1.1 DESCRIPTION OF THE ACTIVITY(IES)
1.1.1 Identification of Applicant 50% 5% 25% 20% 0% 0% 0%
1.1.2 Identification of EAP 85% 10% 0% 5% 0% 0% 0%
1.1.3 Need and desirability of the Activity(ies) 50% 10% 10% 20% 5% 5% 0%
1.1.4 Description and nature of activity/development 40% 25% 10% 20% 5% 0% 0%
Review Area 1 Quality
38
1.1.5 Description of site 20% 50% 15% 10% 5% 0% 0%
1.1.6 Site plan: Sighting of project with respect to surrounding land uses and activities 35% 25% 20% 5% 10% 0% 5%
1.1.7 Description of waste management processes & technology employed 15% 40% 20% 5% 15% 5% 0%
1.1.8 Raw materials used during different phases 0% 30% 20% 0% 5% 45% 0%
1.1.9 Source and availability of water and materials 0% 35% 10% 0% 5% 50% 0%
1.2 SITE DESCRIPTION: Description of onsite land requirements and duration of each land use
1.2.1 Site Plan 35% 10% 15% 15% 10% 10% 5%
1.2.2 Description and demarcation of land use areas 40% 20% 10% 5% 5% 15% 5%
1.2.3 Estimated duration of different phases 5% 0% 25% 0% 0% 45% 25%
1.2.4 Expected number of workers and visitors 0% 10% 5% 0% 0% 80% 5%
1.2.5 Access to site and likely means of transport 5% 40% 5% 0% 0% 45% 5%
1.2.6 Infrastructure required 20% 30% 20% 10% 5% 15% 0%
1.3 WASTE
1.3.1 Waste characterisation / classification (managed) 20% 15% 20% 25% 5% 15% 0%
1.3.2 Volumes managed 45% 20% 5% 15% 0% 15% 0%
1.3.3 Effluent generated from waste management activity 25% 15% 5% 15% 5% 25% 10%
1.3.4 Emissions generated from waste management activity(ies) 20% 20% 0% 5% 5% 40% 10%
1.4 ENVIRONMENTAL DESCRIPTION: Area and location likely to be affected by development
1.4.1 Indication of likely area to be affected 65% 15% 0% 5% 10% 0% 5%
1.4.2 Biophysical description 80% 5% 5% 10% 0% 0% 0%
1.4.3 Biological description 70% 5% 5% 5% 0% 0% 15%
1.4.4 Social characteristics 30% 20% 20% 5% 5% 15% 5%
1.4.6 Important components of the affected environment 40% 30% 5% 10% 15% 0% 0%
1.5 ALTERNATIVES
1.5.1 Description of methods used to identify alternatives 35% 10% 20% 15% 5% 15% 0%
1.5.2 Description of analysis of range of alternatives 55% 0% 5% 10% 10% 20% 0%
1.5.3 Due consideration of no-go alternative 70% 0% 5% 5% 0% 20% 0%
39
Most notably, 95% of reports were well performed (symbol A and B) with respect to
providing details of the environmental assessment practitioner (EAP) who compiled
the Scoping Report, as well as their qualifications (Review Sub-Category 1.1.2,
TABLE 9). This was the best performing sub-category of all that were evaluated as
part of this study. The 2010 NEMA EIA Regulations require that the EAPs
undertaking the EIA demonstrate their competence through providing information on
relevant training and experience in undertaking EIAs. This aspect of the regulations
is in some instances taken by EAPs as an opportunity to market their respective
business consultancies, which goes beyond the intention of the regulations. This
level of self-promotion is undesirable and seemingly unnecessary in EIA practice.
The EAP’s description of a project’s ‘need and desirability’ was performed
unsatisfactorily in 30% of cases (Review Sub-category 1.1.2, (TABLE 9)), with the
‘estimations of the duration of different project phases’ (Review Sub-category 1.2.3)
and ‘number of workers / visitors’ (Review Sub-category 1.2.4) performing even
more poorly, with unsatisfactory quality appraisals in 45% and 85% of cases,
respectively.
Only 55% of the Scoping Reports reviewed were performed satisfactorily with
respect to describing the wastes and residues to be generated from-, or managed at,
the proposed facilities; with 35% and 20% performing well and poorly, respectively
(Review Category 1.3,(TABLE 8)).
This is worrying due to the hazardous nature of the wastes to be generated from-, or
managed at, the facilities that are currently seeking environmental authorization.
Contrary to the above, Hoffman (2007) reported this review category to have been
performed satisfactorily in 100% of the EIA reports reviewed concerning the quality
of EIA reports in the mining sector in South Africa. Furthermore, Van der Vyver
(2008) too assessed this review category to be satisfactorily performed in 100% of
EIA Reports reviewed; where the research focused on the quality of EIA reports for
the explosive industry projects in South Africa. Mbhele (2009) reported that
performance in this aspect for housing development EIRs was generally satisfactory;
where much of the waste generation in that sector could be inferred to be general
40
waste with less complexity than the hazardous waste to be managed at the
proposed facilities subject to the current research.
Also noteworthy is the observation that the EAPs ‘description and preliminary
analysis of alternatives’ was unsatisfactorily in 40% of the scoping reports (Review
Sub-category 1.5.2); with no alternatives being provided in 20% of the Scoping
Reports reviewed. The inclusion and assessment of alternatives (over and above the
mandatory ‘no-go’ alternative) is a requisite legal requirement in terms of the 2010
NEMA EIA Regulations. It is therefore disturbing that in 20% of cases this
requirement was not adequately complied with. The ‘no-go alternative’ was also
given no proper attention in 20% of the Scoping Reports reviewed, despite being a
legal requirement.
A 2005 study by Kruger and Chapman (2005) under the ECA Regulations indicated
that ‘alternatives’ were also given low priority by EAPs in the EIA reports reviewed as
part of their study. Hoffman (2007) reported similar deficiencies in the identification
and assessment of alternatives. Kruger and Chapman (2005) suggested that this
situation could be improved by stipulating regulations or guidelines for the
assessment of alternatives in EIA in South Africa. Despite the DEA’s publication of a
guideline to this effect in 2005, as well as the stipulation of clear requirements for the
assessment of alternatives in the 2010 NEMA EIA Regulations, there appears to
have been little improvement in the quality dimension of this aspect in EIA practice
amongst the waste management Scoping Reports evaluated in this study.
4.3 REVIEW AREA 2: SCOPING
Review Area 2 relates to the definition and identification of potential impacts and
issues that could potentially result from a proposed project, as well as the translation
thereof into clear terms of reference (ToR) for undertaking the subsequent EIA
phase of the process (in the form of a plan of study for EIA or PoSEIA). The
identification of potential impacts, issues and matters of public concern, through
conducting stakeholder engagement, is viewed as an important aspect towards
satisfactory scoping, resulting impacts and issues of concern for a development
41
proposal. If not satisfactorily achieved, the scope and focus of the subsequent EIA
phase of the process would potentially be too broad, narrow or misdirected.
Of the 20 Scoping Reports reviewed, 70% were satisfactorily performed, 30% were
unsatisfactorily performed. In fact, only 5% of Scoping Reports were well performed
(FIGURE 5). If the identification of impacts is the cornerstone of a ‘scoping’ process
in EIA practice (Sandham et al., 2010), it is perturbing that only 60% of the reports
reviewed scored satisfactorily with respect to the corresponding review category
(Review Category 2.2); with only half being performed well in this respect (50% A
and B symbols). Sandham et al. (2010) described similar weaknesses in their study
with regard to ‘impact identification and scoping’, which they describe as being at the
heart of any EIA, as did Sandham et al. (2008) and Van der Vyver (2008).
Stakeholder engagement was generally performed satisfactorily (85%), with the
remaining 15% of Scoping Reports performing poorly in this respect (Review
Category 2.3, TABLE 10). Of the 20 Scoping Reports reviewed, 80% failed to
provide clear definitions of the type of impacts that could result from such projects
(e.g. positive/negative, cumulative, direct, indirect, reversible/irreversible) (Review
Sub-category 2.1.1; with 70% of the reports performing unsatisfactorily in providing
an indication of the methods used by the EAP / specialist(s) to actually identify
potential impacts (Review Sub-category 2.1.2).
TABLE 10: Summary of Review Results for Review Area 2 and Associated
Review Categories.
Review area and category numbering / descriptions
Well performed
Satisfactory,
minor omissio
ns
Satisfactory,
omissions,
inadequacies
Unsatisfactory
Poorly attempted
No attempt
Not applicable
SUMMARY OF REVIEW AREA 2 CATEGORY SCORES: 'Scoping'
A B C D E F G
2.1
Definition of impacts& methods used for identification thereof
0% 0% 20% 40% 20% 20% 0%
2.2
Identification of impacts 0% 30% 30% 10% 30% 0% 0%
2.3
Stakeholder engagement 45% 25% 15% 0% 5% 10% 0%
2.4
Plan of study for EIA 35% 15% 25% 20% 5% 0% 0%
FINAL GRADE: REVIEW AREA 2 0% 50% 20% 25% 5% 0% 0%
42
FIGURE 5: Review Area 2 - 'Scoping and Impact Identification'.
43
TABLE 11: Review Area 2, Scoring of Quality Level for Sub-categories.
Review areas and category numbering / descriptions Well
performed
Satisfactory, minor
omissions
Satisfactory,
omissions, inadequaci
es
Unsatisfactory
Poorly attempt
ed
No attem
pt
Not applica
ble
Review Area 2: SCOPING A B C D E F G
2.1 DEFINITION OF IMPACTS & METHODS USED
2.1.1 Description of potential effects of project on environment 0% 5% 15% 10% 5% 65% 0%
2.1.2 Description of methods used to identify potential impacts and issues 0% 15% 15% 20% 25% 25% 0%
2.2 IDENTIFICATION OF IMPACTS
2.2.1 Assessing impact activities from four different phases 5% 25% 5% 5% 5% 50% 5%
2.2.2 All possible impacts must be identified 45% 20% 20% 10% 5% 0% 0%
2.2.3 Impacts from non-standard operating procedure or deviation from baseline conditions
15% 5% 5% 0% 0% 75% 0%
2.2.4 Impacts identified for alternatives under consideration 5% 25% 15% 0% 0% 15% 40%
2.3 STAKEHOLDER ENGAGEMENT
2.3.1 Example of notice published in media 60% 25% 5% 0% 0% 10% 0%
2.3.2 On-site notice 90% 0% 0% 0% 0% 10% 0%
2.3.3 Identify affected people 85% 0% 0% 0% 0% 15% 0%
2.3.4 Identify people that have an interest in 85% 0% 0% 0% 0% 15% 0%
2.3.5 Procedure whereby interested and affected parties can participate 55% 15% 0% 15% 0% 15% 0%
2.3.6 Provision for interested and affected parties to express their views 55% 10% 0% 20% 0% 15% 0%
2.3.7 List of issues identified 35% 15% 0% 0% 5% 40% 5%
2.3.8 Notification criteria which entails 40% 25% 5% 10% 5% 15% 0%
2.3.9 Record of all views as an addendum 75% 0% 0% 0% 0% 15% 10%
2.3.10
Evidence that interested and affected parties were approached 85% 0% 0% 0% 5% 10% 0%
2.3.11
Key impacts / issues raised 35% 15% 5% 5% 0% 35% 5%
2.4 PLAN OF STUDY FOR EIA
2.4.1 Method of impact significance assessment 50% 15% 10% 10% 5% 10% 0%
2.4.2 Specialist assessment(s) 45% 0% 10% 30% 0% 15% 0%
2.4.3 Public participation for EIA phase 50% 25% 10% 15% 0% 0% 0%
44
Again, if the identification of potential impacts and issues resulting from the proposed
projects is regarded as another cornerstone of scoping, it is alarming that only 35%
and 25% of reports performed satisfactorily in assessing potential impacts through
the full project lifecycle (Review Sub-category 2.2.1) and for non-standard operating
conditions satisfactorily (Review Sub-category 2.2.3), respectively.
Of the Scoping Reports reviewed, 75% of them performed satisfactorily with respect
to providing a comprehensive plan of study for the remaining EIA study (PoSEIA)
(Review Category 2.4, TABLE 11). The poorest performed criterion in this regard
was, however, Review Sub-category 2.4.2 (‘Specialist Assessments’); because 45%
of Scoping Reports failed to provide a clear indication of the terms of reference set
for specialist assessments to be undertaken during the EIA phase, or the anticipated
deliverables / outputs of such specialist assessments.
One aspect of stakeholder engagement which markedly came out as being poorly
performed (45%) was the lack of inclusion of a summary of issues raised by
interested and affected parties within the body of the Scoping Report (Review Sub-
category 2.3.7); whereby it could have been authentically attested that IAPs were in
fact legitimately approached for comment.
4.4 REVIEW AREA 3: COMPLIANCE TO LEGISLATIVE,
GUIDELINE AND POLICY FRAMEWORK
Review area 3 was the most poorly performed review area of the four evaluated in
this study. This review area performed unsatisfactorily in 55% of the Scoping
Reports reviewed (TABLE 12, FIGURE 6). In most instances, the EAP simply
provided a long list of ‘other’ legislation with potential environmental relevance, but
with little or no attempt to relate or integrate their specific relevance to the specific
project proposal, or aspect(s) thereof. By way of example, the EAPs simply provided
a blanket listing of all ‘Section 21’ water uses under the National Water Act (Act No.
36 of 1998) [NWA] requiring a water use licence form the Department of Water
Affairs, with no genuine attempt to single out the specific uses therein (a-k) that are
triggered by one or another aspects of the project proposal.
45
The poor results obtained for Review Area 3 again raise environmental management
concerns as to the limited extent to which the Scoping Reports reviewed appear to
achieve the minimum requirements stated in the 2010 NEMA EIA Regulations;
where Regulation 28 (1) (f) of GNR. 543 (18th June 2010:35) specifically requires
that Scoping Reports should include, “the identification of all legislation and
guidelines that have been considered in the preparation of the scoping report.”
TABLE 12: Summary of Review Results for Review area 3 and Associated
Review Categories.
Review area and category numbering / descriptions
Well performed
Satisfactory,
minor omission
s
Satisfactory,
omissions,
inadequacies
Unsatisfactory
Poorly attemp
ted
No attem
pt
Not applica
ble
SUMMARY OF REVIEW AREA 3 CATEGORY SCORES: 'Legislative, Guideline and Policy Review'
A B C D E F G
3.1 Legal 45% 10% 15% 25% 5% 0% 0%
3.2 Policy / Guidelines 15% 15% 10% 5% 5% 50% 0%
FINAL GRADE REVIEW AREA 3 25% 20% 0% 25% 30% 0% 0%
46
FIGURE 6: Review Area 3 – ‘Legislative and Policy Framework’.
47
TABLE 13: Review Area 3, Scoring of Quality Level for Sub-categories.
Review areas and category numbering / descriptions
Well performed
Satisfactory,
minor omissio
ns
Satisfactory,
omissions,
inadequacies
Unsatisfactory
Poorly attempted
No attempt
Not applicable
Review Area 3: Legislative, Guideline and Policy Review
A B C D E F G
3.1 LEGAL
3.1.1 Trigger Legislation / Regulations 60% 10% 10% 20% 0% 0% 0%
3.1.2 Other Relevant Legislation 40% 5% 5% 35% 5% 10% 0%
3.2 POLICIES / GUIDELINES
3.2.1 Policy / Guidelines 15% 15% 15% 0% 5% 50% 0%
3.2.2 Spatial Development and Sectoral Plans / Frameworks
5% 5% 5% 0% 0% 55% 30%
The biggest contributor to the poor review area appraisal was in 55% of cases (as
denoted by quality symbols E and F), a lack of consideration by the EAPs regarding
existing policies / guidelines (Review Sub-category 3.2.1; (TABLE 13)) and spatial
development plans / frameworks (Review Sub-category 3.2.2) with potential
relevance to the specific projects being considered (Review Category 3.2,
On a positive note, though, the legislative trigger(s) for having to undertake the EIA,
as well as the requirements of the associated EIA process and licensing
requirements (Review Sub-category 3.1.1) were satisfactorily described in 80% of
Scoping Reports. However, the associated description of other relevant legislation
(Review Sub-category 3.1.2) was poorly performed, with this aspect performed
satisfactorily only in 50% of the review cases.
4.5 REVIEW AREA 4: COMMUNICATION OF RESULTS
A well administered and technically sound scoping process (as guided by the EIA
Regulations under NEMA) needs to be concise, well-directed and unambiguous with
respect to the communication of the results obtained from the scoping process.
Given that the primary aim of performing an EIA is to allow for informed decision-
making regarding the sustainability of a development proposal, the communication of
48
the results obtained from the administrative/ technical scoping process (in the form of
a Scoping Report) is as important as the process itself.
The ‘communication of results’ (Review Area 4) was generally satisfactorily
undertaken (80%), with 40% of reports assigned a quality rating described as well
performed (FIGURE 7). This result corresponds well with results obtained by Kruger
(2012), Van der Vyver (2008) and Sandham (2008) in EIR quality appraisals using
the South African Review Package; with results of 80%, 80% and 100% satisfactory
quality, respectively.
The poorest performing review category was encountered in appraising the quality of
the presentation of a ‘non-technical summary’ (Review Category 4.4, (TABLE 14));
whereby only 55% of reports were found to have been satisfactorily performed in this
instance.
However, the ‘presentation of information’ in the reports (Review Category 4.2,
(TABLE 14)) was satisfactorily performed in 85% of the review cases. Similarly, the
extent to which the ‘prominence of emphasis’ was directed to the key impacts and
issues of concerns for each project was observed to be satisfactorily performed in
85% of the reports analysed.
49
TABLE 14: Summary of Review results for review Are 4 and associated Review Categories.
Review area and category numbering / descriptions Well performed Satisfactory,
minor omissions
Satisfactory, omissions,
inadequacies Unsatisfactory
Poorly attempted
No attempt Not
applicable
SUMMARY OF REVIEW AREA 4 CATEGORY SCORES: 'Communication of results'
A B C D E F G
4.1 Layout 30% 40% 0% 30% 0% 0% 0%
4.2 Presentation 10% 40% 35% 15% 0% 0% 0%
4.3 Emphasis 40% 15% 30% 15% 0% 0% 0%
4.4 Non-technical summary 30% 0% 25% 5% 0% 40% 0%
FINAL GRADE REVIEW AREA 4 20% 20% 40% 20% 0% 0% 0%
FIGURE 7: Review Area 4 - 'Communication of Results’.
50
TABLE 15: Review Area 4, Scoring of Quality Level for Sub-categories.
Review areas and category numbering / descriptions Well
performed
Satisfactory, minor
omissions
Satisfactory, omissions,
inadequacies Unsatisfactory
Poorly attempted
No attempt
Not applicable
Review Area 4 - Review Category Summary: Communication of results A B C D E F G
4.1 LAYOUT
4.1.1 Introduction 55% 20% 5% 20% 0% 0% 0%
4.1.2 Arrangement of information 25% 40% 5% 30% 0% 0% 0%
4.1.3 External sources 10% 50% 15% 10% 10% 5% 0%
4.2 PRESENTATION
4.2.1 Presentation of information 15% 40% 20% 15% 5% 0% 0%
4.2.2 Presented as an integrated whole 10% 50% 25% 15% 0% 0% 0%
4.3 EMPHASIS
4.3.1 Prominence and emphasis given to 30% 25% 25% 15% 5% 0% 0%
4.3.2 Scoping Report is unbiased 35% 30% 15% 15% 5% 0% 0%
4.4 NON-TECHNICAL SUMMARY
4.4.1 Non-technical summary including main findings and conclusions 40% 5% 10% 5% 0% 40% 0%
4.4.2 Scoping Report summary of main issues 30% 0% 10% 10% 0% 50% 0%
51
The inclusion of a non-technical summary (Review Sub-category 4.4.1, (TABLE 15))
or Scoping Report conclusion (Review Category 4.4.2) are not an explicit
requirement under the 2010 NEMA EIA Regulations, but are generally considered as
best practice in compiling a Scoping Report (Glasson et al., 2012). An interesting
observation in this regard, although not expressly quantified, is that review sub-
categories that are not legal requirements are generally less well performed than
those which are regulatory requirements in respect of the 2010 NEMA EIA
Regulations. Review Category 4.4.1 and 4.4.2 in the current study were performed to
a satisfactory level in 55% and 40% of the review cases, respectively.
In a related quality study, Mbhele (2009) reported that only 66% of EIR reports
reviewed, for example, contained an executive summary, which is not a clear
regulatory requirement, which compares favourably with this study; where only 60%
of the reports reviewed contained an executive summary.
It is disconcerting that bias, in favour of the project proposal, was noted in 20% of the
Scoping Reports reviewed as part of this study (Review Sub-category 4.3.2). This is
approximately double that noted by Sandham and Pretorius (2008). This bias is well
associated with those reports that performed poorly in respect of their overall quality
appraisal, as well as the review areas, categories and sub-categories. It is not clear,
however, whether the poor performance of such reports is reflective of an intentional
omission of material information in favour of the applicant (i.e. information that may
potentially jeopardise the granting of a waste management licence), or whether the
EAPs responsible were simply lacking requisite analytical skills and were unaware of
the bias that filters through in their writing style, whether intentionally or not.
4.6 OVERALL SCOPING REPORT QUALITY
A summary of results obtained for the study are presented in table 16, figure 9, 10
and 11. The quality appraisal of the 20 EIA Scoping Reports dealing with the
management of hazardous waste has shown that these reports have been
satisfactorily (assessment symbols A-C) conducted and prepared in 75% of the
cases involved (TABLE 16). However, only 40% of Scoping Reports were well
performed (assessment symbols A and B), with 10% being poorly performed
52
(assessment symbols E and F). Of environmental management concern is that 35%
of the Scoping Reports reviewed (just over one third), although ‘satisfactory’, were
presented with significant omissions and inadequacies (FIGURE 9: Scoping Report
Quality Appraisal.), thus constraining the quality of the decisions being made.
These research findings (i.e. 75% overall satisfactory performance) are comparable
to the outcome of other EIR quality appraisals using the adapted South African Lee
and Colley Review Package. For instance, according to a quality evaluation
conducted by Mbhele (2009), 73% of EIRs in the housing sector were performed
satisfactorily meanwhile Kruger (2012) found a 67% level of satisfactory performance
amongst EIRs compiled for proposed filling stations in South Africa, which is in
agreement with the findings of international EIR quality appraisals, which revealed
higher levels (from 67% and above) of satisfactory quality. Hoffman (2007) found out
that the overall quality amongst EIRs in the mining sector was 85% compliant in
terms of the level of satisfactoriness and were also congruent with results obtained
by both Moloto (2005) and Pretorius (2006).
The worst performing review area in this study was noted to be Review Area 3,
‘Legislative, Guideline and Policy Review’; with the minority of reports (45%) having
been performed satisfactorily in this respect (FIGURE 11: Review Area Quality
Appraisal Comparison Summary. and FIGURE 12). Review Areas 1 and 2,
‘Description of the Development and Receiving Environment’ and ‘Scoping’
respectively, were equally well performed; where 70% of reports in both instances
were satisfactorily conducted regarding these review areas (FIGURE 11: Review
Area Quality Appraisal Comparison Summary.). The best performed review area was
Review Area 4, ‘Communication of Results’; with 80% of reports being well prepared
in this instance (FIGURE 11: Review Area Quality Appraisal Comparison Summary.).
Furthermore, another best performed review area in the study (i.e. as a percentage
of reports ‘well performed’ per review area) was Review Area 3, ‘Legislative,
Guideline and Policy Review’; which was also ironically the worst performed review
area in the current study, with scores of 25% and 35%, respectively (FIGURE 10:
Review Area Quality Appraisal Comparism., TABLE 16). The opposite trend (i.e.
opposite to that noted for Review Area 3 above) was observed in the results
53
obtained for Review Area 2, ‘Scoping’; where only 5% of the reports reviewed were
‘poorly attempted’, and none were ‘well performed’ in this respect (FIGURE 8:
Trends Analysis of Results for Review Area 2 and 3.). The majority of reports (70%)
were performed simply ‘satisfactorily’ in this respect (TABLE 16).
FIGURE 8: Trends Analysis of Results for Review Area 2 and 3.
0
10
20
30
40
50
60
Wellperformed
Satisfactory,minor
omissions
Satisfactory,omissions,
inadequacies
Unsatisfactory PoorlyattemptedP
erc
en
tage
of
Rep
ort
s R
evie
we
d
Scoping &ImpactIdentification
Legislative,Guideline andPolicy Review
54
TABLE 16: Tabular Summary of Overall Review Results and Associated Review Areas.
Review areas and category numbering / descriptions Well
performed
Satisfactory, minor
omissions
Satisfactory, omissions,
inadequacies Unsatisfactory
Poorly attempted
No attempt
Not applicable
SUMMARY OF REVIEW AREA AND OVERALL SCORES A B C D E F G
1 Description of the development and receiving environment 20% 35% 15% 15% 15% 0% 0%
2 Scoping / Impact identification 0% 50% 20% 25% 5% 0% 0%
3 Legislative, Guideline and Policy review 25% 20% 0% 20% 35% 0% 0%
4 Communication of results 20% 20% 40% 20% 0% 0% 0%
FINAL GRADE SCOPING REPORT 10% 30% 35% 15% 10% 0% 0%
FIGURE 9: Scoping Report Quality Appraisal.
55
FIGURE 10: Review Area Quality Appraisal Comparism.
0%
10%
20%
30%
40%
50%
Well performed
Satisfactory, minor omissions
Satisfactory, omissions,…
Unsatisfactory
Poorly attempted
Pe
rcen
tage
of
Sco
pin
g R
ep
ort
s R
evie
we
d
Description of the development and receivingenvironment
Scoping / Impact identification
Legislative, Guideline and Policy review
Communication of results
: Review Area 3
: Review Area 2
: Review Area 4
: Review Area 1
56
FIGURE 11: Review Area Quality Appraisal Comparison Summary.
0%
10%
20%
30%
40%
50%
60%
70%
80%
Description of thedevelopment and
receivingenvironment
Scoping / Impactidentification Legislative,
Guideline andPolicy review
Communicationof results
Well / SatisfactorilyPreformed
Pe
rcen
tage
of
Scop
ing R
ep
ort
s R
evie
we
d
Poorly / Unsatisfactorily Performed
57
4.7 MINIMUM CONTENT OF A SCOPING REPORT
The minimum content requirements for a Scoping Report in South Africa are
specified under Regulation 28 (1) of the 2010 NEMA EIA Regulations (GNR. 543 of
18 June 2010:35); which states that, “a Scoping Report must contain all the
information that is necessary for a proper understanding of the nature of issues
identified during scoping”, and must include, as a minimum, all the information
included in the table that follows (TABLE 17).
‘Legally motivated sub-categories’ (Kruger, 2012) in the adapted review package are
also indicated in TABLE 17 and are listed together with their corresponding sub-
regulations. In some instances, there are a few sub-categories contributing to a
single regulatory requirement. Given that the requirements listed in TABLE 17 are
legal imperatives in respect of an EAP’s compilation of a Scoping Report, should any
aspect be performed in a less than satisfactory manner, such reports should not in
practice be accepted by the competent authority for environmental authorization.
It is noted with environmental management concern that certain sub-categories that
are clear legal requirements were performed in a less than satisfactory manner
(scoring D, E or F) in as many as 55% of the Scoping Reports reviewed. These are
highlighted in TABLE 17. The poorest performing legally motivated sub-categories in
this respect relate to i) the description of the proposed activity, ii) an identification of
all legislation and guidelines that were considered in the preparation of the Scoping
Report, as well as iii) identification of tasks to be undertaken in the EIA phase of the
study (i.e. the plan of study for EIA).
It is evident that the Scoping Reports reviewed for this study conform poorly to
relevant South African legislation given the lower percentages of the total number of
relevant Review Sub-categories, as depicted in TABLE 18. This trend was also
observed in other related studies that appraised the quality of EIRs in the South
African context (Kruger and Chapman, 2005; Kruger, 2012). The strictest legal
interpretation of Regulation 28 (1) of the 2010 NEMA EIA Regulations by the DEA
would see nearly 55% of all hazardous waste related Scoping Reports submitted by
EAPs being rejected due to significant inadequacies and/or omissions. Alternatively,
58
the DEA could apply some discretion and adopt a holistic view of the overall quality
of the Scoping Report itself, ignoring legal inadequacies. Unless the quality of
Scoping Reports within this industry sector is improved and minimum legal
requirements are strictly adhered to, the DEA’s resources could be unnecessarily
wasted in having to repeatedly review and reject reports on legal technicalities, even
if the remainder of the report is well performed.
TABLE 17: Regulatory Requirements for Sub-category Scoring.
Requirements (Regulation 28) Review sub-category Satisfactory
Details of —
the EAP who prepared the report; and 1.1.2 95%
the expertise of the EAP to carry out scoping
procedures.
1.1.2 95%
A description of the proposed activity. 1.1.3 75%
1.1.6 75%
1.1.7 50%
1.1.8 45%
1.3.1 55%
1.3.2 70%
1.3.3 45%
1.3.4 40%
A description of any feasible and reasonable
alternatives that have been identified.
1.5.2 60%
1.5.3 75%
A description of the property on which the activity is to
be undertaken and the location of the activity on the
property….
1.2.1 60%
1.1.4 85%
1.1.5 80%
A description of the environment that may be affected
by the activity and the manner in which activity may be
affected by the environment;
1.4.1 80%
1.4.2 90%
1.4.3 80%
1.4.4 70%
An identification of all legislation and guidelines that
have been considered in the preparation of the scoping
report;
3.1.1 80%
3.1.2 50%
3.2.1 45%
A description of environmental issues and potential
impacts, including cumulative impacts, that have been
identified;
2.2.2 85%
the steps that were taken to notify potentially
interested and affected parties of the application;
2.3.10 85%
proof that notice boards, advertisements and
notices notifying potentially interested and affected
2.3.2 90%
59
parties of the application have been displayed,
placed or given;
a list of all persons or organisations that were
identified and registered in terms of regulation 55
as interested and affected parties in relation to the
application; and
2.3.3 85%
2.3.4 85%
a summary of the issues raised by interested and
affected parties, the date of receipt of and the
response of the EAP to those issues.
2.3.7 90%
A description of the need and desirability of the
proposed activity.
1.1.3 70%
A description of identified potential alternatives to the
proposed activity, including advantages and
disadvantages that the proposed activity or alternatives
may have on the environment and the community that
may be affected by the activity.
1.5.2 60%
1.5.3 75%
Copies of any representations, and comments received
in connection with the application or the scoping report
from interested and affected parties.
2.3.9 75%
a description of the tasks that will be undertaken as
part of the environmental impact assessment
process, including any specialist reports or
specialised processes, and the manner in which
such tasks will be undertaken;
2.4.2 55%
a description of the proposed method of assessing
the environmental issues and alternatives, including
the option of not proceeding with the activity; and
2.4.1 75%
particulars of the public participation process that
will be conducted during the environmental impact
assessment process.
2.4.3 85%
Source: Adapted from Kruger (2012).
60
TABLE 18: Tabular Summary of Performance Against Regulatory
Requirements.
Percentage of
Scoping Reports
with satisfactory
performance *
Relevant sub-categories
Percentage of total
No. of relevant sub-
categories
90 – 100 % 1.1.2, 1.4.2, 2.3.2 and 2.3.7 12.5%
80 – 89 % 1.1.4, 1.1.5, 1.4.1, 1.4.3, 3.1.1, 2.2.2,
2.3.10, 2.3.3, 2.3.4 and 2.4.3
31.25%
70 – 79 % 1.1.3, 1.1.6, 1.3.2, 1.5.3, 1.4.4, 1.5.3,
2.3.9 and 2.4.1
25%
60 – 69 % 1.5.2 and 1.2.1 6.25%
50 – 59 % 1.1.7, 1.3.1, 3.1.2 and 2.4.2 12.5%
40 – 49 % 1.1.8, 1.3.3, 1.3.4 and 3.2.1 12.5%
* Expressed as a percentage of the total number of reports reviewed that were found to be of a
satisfactory quality in respect of the indicated review sub-categories.
4.8 AREAS OF WEAKNESS
Key areas of weakness in scoping procedures / reports identified in this study are as
follows:
A lack of comprehensive description of the proposed projects and ancillary
structures and infrastructure supportive thereof, and absence of site plans,
process flows / mass balances and supportive graphics;
No systematic consideration and analyses of alternatives (i.e. other than the
no-go alternative; which was generally well performed). These observations
are in line with the findings of studies undertaken by Hoffman (2007), as well
as Chapman and Kruger (2005);
Poor identification of potential impacts and issues across the full lifecycle of
the proposed development, as well as estimates of the anticipated duration of
each phase;
Poor consideration and identification of raw materials (i.e. source and
demand) to be used;
61
Inadequate characterization of hazardous wastes, effluents and emissions to
atmosphere;
Insufficient identification of methods used to identify potential project impacts,
as well as the provision of descriptions of the types of impacts that can
reasonably be anticipated to occur;
Poor identification of impacts that may potentially arise from non-
standard/upset operating conditions;
Too little description and consideration of guidelines, policies and spatial
development tools potentially applicable to the project;
Deficient inclusion of comprehensive terms of reference for specialist studies
proposed in terms of the plan of study for EIA; and
Potential bias by EAPs in favor of the development proposals.
4.9 AREAS OF STRENGTH
Key areas of strength in the scoping procedures / reports identified in this study are
as follows:
Stakeholder engagement was generally satisfactorily performed, with obvious
deficiencies observed in only 15% of Scoping Reports reviewed;
The descriptions provided for biophysical and biological site elements were
well performed in 85% and 75% of cases;
Good identification of the EAP and expertise and experience in undertaking
EIAs; and
The communication of results was performed satisfactorily by EAPs in 80% of
reports, which in the broader sense can be considered an area of strength in
practice, although distinct sub-categories were substantively deficient.
62
CHAPTER 5
CONCLUSIONS AND RECOMMENDATIONS
5.1 INTRODUCTION
The main research goal in this study was to evaluate the quality aspects of
hazardous waste related Scoping Reports that were submitted to the DEA for
environmental authorisation subsequent to the promulgation of the 2010 NEMA EIA
Regulations (GNR. 543, 544, 545 and 546 of 18 June 2010). Firstly, conclusions
arising from the research results are provided. Secondly, some recommendations
are made for further studies.
5.2 CONCLUSIONS
Only 75% of Scoping Reports reviewed performed satisfactorily in respect of their
overall quality. This is somewhat concerning regarding the sectoral focus (hazardous
waste management) of this research. More disturbingly, of the 25% reports that were
identified as being of ‘unsatisfactory’ quality, 10% of them were very poorly
attempted and deficient in many material respects. It is clear that despite the high
level of technical competency required by EAPs to undertake EIAs in respect of
hazardous waste management license applications in particular, there appears to be
a level of incompetence that filters through into the assessment tasks involved;
where this is likely to result in wasted time and effort for both project applicants and
the regulator (DEA) alike.
The poor overall quality noted in this study, as well as the identification of key areas
of weakness that follows, is not inferred to be a consequence of a poorly defined or
implemented EIA system in South Africa, but rather possibly due to a concerning low
level of competence amongst a handful of EAPs. This statement is made in the light
of the fact that many of the deficiencies and omissions observed are clear legal
requirements in terms of the prescribed legal environment for EIA in South Africa
(often with associated guidelines), yet such requirements are still poorly adhered to.
63
It is hoped that with the expected and compulsory professional registration of
environmental assessment practitioners, the quality of environmental impact reports
will improve in South Africa since the only people with the required skills set will be
those registered by the new Environmental Assessment Practitioners Association of
South Africa (EAPASA), thus preventing ill-prepared and under qualified people from
practicing environmental assessment.
5.3 RECOMMENDATIONS FOR FURTHER ASSESSMENT / STUDY
Based on the scope and the research findings stemming from this study, the
following recommendations are made for possible future studies aimed at ultimately
assisting in improving the quality of EIA processes in South Africa.
Firstly, a quality appraisal of the entire EIRs produced subsequent to the scoping
processes that resulted in the generation of the 20 Scoping Reports reviewed as part
of this study is highly recommended. This research would allow for direct comparison
between the overall quality of reviewed Scoping Reports and the proposed EIRs,
further providing indications of the extent to which weaknesses identified in the
Scoping Reports continue further as shortcomings in the finalized EIRs. Such
research would also provide an indication of the extent to which the Department of
Environmental Affairs’ ultimate review and decision-making (i.e. if in respect of the
Scoping Reports reviewed as part of this assessment) deals with inherent
weaknesses identified in the Scoping Reports.
With the promulgation of the Waste Classification and Management Regulations
under NEM:WA on 23rd August 2013, it is recommended that a comparative
assessment be undertaken in future in respect of the number of proposed hazardous
waste treatment, recovery, reuse and recycling facility EIAs conducted in South
Africa pre- and past- the promulgation of the aforementioned regulations. This would
provide a base of comparison of the extent to which the DEA’s landfill prohibitions for
certain waste types have in fact promoted a diversion of hazardous waste from
landfill towards other management options further up along the waste hierarchy (i.e.
reuse, recovery recycling and treatment). Should the number of such applications
indeed have increased significantly, the study could also provide insight into the
64
Regulator’s (DEA) readiness to deal with such, in terms of available technical and
resource capacity.
The requirements for environmental assessment practitioners (EAPs) in South Africa
to be registered / certified by an independent, professional, industry body is not yet in
force. Interim certification is, however, awarded at present through the environmental
assessment practitioner association of South Africa (EAPASA). This body operates
independently of-, but in collaboration with, the National Department of
Environmental Affairs, and has its own board and constitution. The certification
process entails prospective candidates having to solicit the support of two sponsors
and undergo a process of peer review toward becoming a certified EAP.
Certification with EAPASA has been voluntary to date, and is not a legal requirement
for EAPs undertaking EIAs or compiling EIRs in South Africa. The interim
certification of EAPs is, however, seen as a move toward ensuring better quality and
professionalism in the assessment tasks undertaken by EAPs. By comparing the
outcomes of the quality appraisal of the 20 Scoping Reports involved in the current
research against another 20 randomly selected hazardous Waste related Scoping
Reports compiled by registered EAPs (i.e. once the registration process becomes a
legal pre-requisite in South Africa for practitioners) in the future, further research
could help in evaluating the effectiveness of the newly proposed system of formal
EAP registration.
65
LIST OF REFERENCES
Aucamp, P.J. (2009). Environmental Impact Assessment: A Practical Guide for the
Discerning Practitioner. Pretoria: Van Schaik.
Baker, D. and E. Rapaport. (2005). The Science of Assessment: Identifying and Predicting
Environmental Impacts. In: Hanna, K.S. (Ed.), Environmental Impact Assessment:
Practice and Participation. Oxford: Oxford University Press.
Constitution of the Republic of South Africa (Act No. 108 of 1996). (1996). Pretoria:
Government Printers.
Crous, H. and B. K. Thorpe. (2012). Waste Classification and Management Regulations:
Overview of New Approach and Legal Requirements for the Classification of Waste,
Conference Paper, Wastecon 2012. Institute for Waste Management in Southern
Africa.
DEA. (2011). National Waste Management Strategy. Department of Environmental Affairs
(DEA), South African Government.
DEAT. (2004). Environmental Impact Reporting, Integrated Environmental Management,
Information Series 15, Department of Environmental Affairs and Tourism (DEAT).
Pretoria, South Africa.
DEAT. (2007). Strategic Environmental Assessment Guideline, Integrated Environmental
Guidelines Series 4. Department of Environmental Affairs and Tourism (DEAT).
Pretoria, South Africa.
Democratic Alliance (DA). (2009). Discussion Document: Addressing problems in the
medical waste sector. Democratic Alliance.
Department of Water Affairs and Forestry (DWAF). (1998). Waste Management Series.
Minimum Requirements for the Handling, Classification and Disposal of Hazardous
Waste, Edition 2, 1998. Pretoria: DWAF
Du Pisani, J.A. and L.A. Sandham. (2006). Assessing the Performance of SIA in the EIA
66
Context: A Case Study of South Africa. Environmental Impact Assessment Review
26: 707–724.
Environment Conservation Act (ECA) (Act No. 73 of 1989). (1989). Pretoria: Government
Printers
Fuggle, R.F. and M.A. Rabie. (2009). Environmental Management in South Africa, (2nd
Edition). Cape Town: Juta.
George, C. (2000). Comparative review of environmental assessment procedures and
practice. In Lee, N & C. Clive (eds). 2000. Environmental Assessment in Developing
and Transitional Countries. London: Wiley.
Glasson, J., R. Therivel. and A. Chadwick. (2012). Introduction to Environmental Impact
Assessment, (4th Edition). New York: Routledge Taylor and Francis Group.
Glasson, J., R. Therivel. and A. Chadwick. (2005). Introduction to environmental impact
assessment, (3rd Edition). New York: UCL Press.
Gregory, R., Keeney, R. and D. von Winterfeldt. (1992). Adapting the Environmental Impact
Statement Process to inform Decision Makers. Journal of Policy Analysis and
Management 11: 58–75.
Hoffman, A. R. (2007). An Appraisal of the Quality of Mining EIA Reports. MSc Dissertation.
Potchefstroom: North-West University.
Kabir, S. M. Z, S. Momtaz and W. Gladstone. (2010). The Quality of Environmental Impact
Statement (EIS) in Bangladesh. Paper represented at the International Association
for Impact Assessment (IAIA) Conference, Conference Papers and Notes. Geneva,
Switzerland.
Kruger, E. and O. A. Chapman. (2005). Quality Aspects of Environmental Impact
Assessment Reports in the Free State Province, South Africa. South African
Geographical Journal 87(1): 52-57
67
Kruger, R. A. (2012). A critical analysis of the quality of EIA reports for filling stations in
South Africa. Mini-Dissertation, University of the North-West.
Lee, N. and R. Colley. (1992). Reviewing the Quality of Environmental statements,
Occasional Paper Number 24, EIA Centre, Department of Planning and Landscape,
University of Manchester.
Lee, N. and C. George. (2000). Environmental Assessment in Developing and Transitional
Countries. John Wiley & Sons, 290p.
Lee, N., R. Colley, J. Bonde and J. Simpson. (1999). Reviewing the Quality of
Environmental Statements and Environmental Appraisals, Occasional Paper Number
55, EIA Centre, Department of Planning and Landscape, University of Manchester.
Leu, W., W. P. Williams and A. W. Bark. (1996). Development of an Environmental Impact
Assessment Evaluation Model and its Application: Taiwan Case Study.
Environmental Impact Assessment Review 16: 115-133.
Macintosh, A. (2010). Best Practice Environmental Impact Assessment: A Model
Framework for Australia. Australian Journal of Public Administration 69(4): 401-407.
Mbhele, M. P. (2009). The Quality of EIA Reports for Housing Developments in the
Nkangala District of the Mpumalanga Province, South Africa. Mini-Dissertation,
University of the North West.
Morris, P. and R. Therivel. (2010). Methods of Environmental Impact Assessment, (3rd
Edition). New York: Routledge Taylor and Francis Group.
Mulvihill, P. R. and P. Jacobs. (1998). Using Scoping as a Design Process. Environmental
Impact Assessment Review 18: 351-369.
National Environmental Management Act (NEMA) (Act No. 107 of 1998). (2010).
Environmental Impact Assessment Regulations GNR. 543 18th June 2010. Pretoria:
Government Printers.
68
National Environmental Management Act (NEMA) (Act No. 107 of 1998). (2006).
Environmental Impact Assessment Regulations GN. R. 385 of 21st April 2006.
Pretoria: Government Printers.
National Environmental Management: Waste Act (NEM:WA) (Act No. 59 of 2008). (2008).
Pretoria: Government Printers.
National Environmental Compliance and Enforcement Report 2012/13. (2013). Department
of Environmental Affairs, Directorate: Compliance and Enforcement Services.
National Water Act (NWA) (Act No. 36 of 1998). (1998). Pretoria: Government Printers.
Papu-Zamxaka, V., T., Harpman and A. Mathee. (2010). Environmental Legislation and
Contamination: The Gap between Theory and Reality in South Africa. Journal of
Environmental Management 91: 2275-2280.
Peterson, K. (2010). Quality of Environmental Impact Statements and Variability of Scrutiny
by Reviewers. Environmental Impact Assessment Review 30: 169-176.
Pinho, P., R. Maia and A. Monterroso. (2007). The Quality of Portuguese Environmental
Impact Studies: The Case of Small Hydropower Projects. Environmental Impact
Assessment Review 27: 189-205.
Promotion of Access to Information Act (PAIA) (Act No. 2 of 2000). (2000). Pretoria:
Government Printers.
Retief, F., C.N.J. Welman. and L. Sandham. (2011). Performance of environmental impact
assessment (EIA) screening in South Africa: a comparative analysis between the
1997 and 2006 EIA regimes. South African Geographical Journal 93(2): 154–171.
Sandham, L. A. and H. M. Pretorius. (2008). A Review of EIA Report Quality in the North
West Province of South Africa. Environmental Impact Assessment Review 28: 229-
240.
69
Sandham, L. A., T. H. Carroll and F. P. Retief. (2010). The Contribution of Environmental
Impact Assessment (EIA) to Decision Making for Biological Pest Control in South
Africa – The Case of Lantana camara. Biological Control 55: 141–149
Sandham, L. A., M. J. Moloto. and F. P. Retief. (2008). The Quality of Environmental Impact
Reports for Projects with the Potential of affecting Wetlands in South Africa. Water
SA 34 (2): 155-162.
Sandham, L. A., van Heerden A. J., Jones C. E., Retief F. P. and A.N. Morrison-Saunders.
(2013). Does enhanced Regulation improve EIA Report Quality? Lessons from
South Africa. Environmental Impact Assessment Review 30: 155-162.
Simpson, J. (2001). Developing a Review Package to assess the Quality of EA Reports of
Local Authority Structure and Local Plans in the UK. Environmental Impact
Assessment Review 21: 83-95.
SANS 10234-2. (2010). Globally Harmonised System of Classification and Labelling of
Chemicals (GHS). South African Bureau of Standards, Pretoria, South Africa.
South African National Standard for the Assessment of Waste for Disposal to Landfill.
Government Notice No. 635 of 23rd August 2013. (2013). National Department of
Environmental Affairs, Pretoria, South Africa.
South African National Standard for the Disposal of Waste to Landfill. Government Notice
No. 635 of 23rd August 2013. (2013). National Department of Environmental Affairs,
Pretoria, South Africa.
Talime, L. A. (2010). A critical review of the quality of environmental impact assessment
reports in Lesotho. MSc. Dissertation (Geography), University of the Free State,
Bloemfontein.
Thorpe, B. K., H Crous and D. Baldwin. (2012). National Waste Classification and
Management Regulations: New Approach and Legal Requirements for the
Assessment and Disposal of Waste to Landfill, Conference Paper, Wastecon 2012.
Institute for Waste Management in Southern Africa.
70
University of Pretoria (UP). (2012). EIA Administration and Review Training Manual.
National Department of Environmental Affairs, Pretoria, South Africa.
Van der Vyver, F. (2008). The Quality of Environmental Impact Reports for Explosives
Industry Projects. Mini-Dissertation (Environmental Management Studies), University
of the North West.
Waste Classification and Management Regulations. Government Notice No. 634 of 23
August 2013. (2013). National Department of Environmental Affairs. Pretoria, South
Africa
Wood, C. (2000). Screening and scoping. In Lee, N and C. Clive (Eds). 2000.
Environmental Assessment in Developing and Transitional Countries. London: Wiley.
Wood, G., J. Glasson and J. Becker. (2006). EIA Scoping in England and Wales:
Practitioner Approaches, Perspectives and Constraints. Environmental Impact
Assessment Review 26: 221-241.