Upload
truongnguyet
View
217
Download
0
Embed Size (px)
Citation preview
European Bank for Reconstruction and
Development
NEC Contracts
neccontract.com © nec 07/2011
NEC Contracts
Peter Higgins
NEC Group
22 July 2011
Agenda
• Introduction to the NEC system
• Key features of the NEC - delivering client requirements
neccontract.com © nec 07/2011
• Clarity, Flexibility, Stimulus to good management
• Experience in the use of the NEC
• Implementation of NEC
About the ICE
• Established 1818
• First President Thomas Telford (1820 – 1834)
• 85,000 members spanning 164 countries
• 12 offices worldwide
neccontract.com © nec 07/2011
• 12 offices worldwide
ICE Role in Contract Writing
1945 - 1st Edition of ICE Conditions of Contract1955 – 4th Edition of ICE Conditions of Contract
adopted for International use and published as the FIDIC Contract
2001 – 7th Edition of ICE Conditions of Contract
neccontract.com © nec 07/2011
2001 – 7 Edition of ICE Conditions of Contract
1991 - First publication of NEC contract1995 – 2nd Edition of NEC contract2005 – 3rd Edition of NEC family of contracts
2011 – Support for ICE conditions withdrawn
NEC family of contracts
NEC is a comprehensive project management tool
• Engineering and Construction Contract & Subcontract• Short Contract & Subcontract
• Professional Services Contract
• Term Service Contract
neccontract.com © nec 07/2011
• Term Service Contract• Short Contract
• Supply Contract• Short Contract
• Framework Contract
• Adjudicator’s Contract
NEC family
• Guidance Notes & Flow Charts
• To support all the NEC3 contracts
neccontract.com © nec 07/2011
• NEC Procurement and Contract Strategies
• A guide for users in application of NEC3 contracts in different procurement and contract strategies
neccontract.com © nec 07/2011
NEC family
EmployerProject Manager
PSCAdjudicator
AC
Typical design &
neccontract.com © nec 07/2011
Contractor
ECC
Supplier
SC or SSC
Subcontractor
ECS or ECSS
Supervisor
PSC
Designer
PSC
Typical design &
build arrangement
Contract choice
Contract EBRD current NEC options
Construction work FIDIC 1st/HarmonisedNECOther approved
NEC ECCNEC ECC Short
Goods MDB NEC Supply
neccontract.com © nec 07/2011
Goods MDB NEC SupplyNEC Supply Short
Plant supply & installation
World Bank 1995 NEC ECCNEC ECC Short
Consultancy FIDICInternal
NEC PSC
Asset operation/management
NEC TSCNEC TSC Short
People in the NEC contracts
• Project Manager
• Employer’s representative
• Duty to certify
neccontract.com © nec 07/2011
• Supervisor
• Responsible for quality
• Adjudicator
• Dispute review expert
NEC contract design
• Defines the actions of the parties needed to manage the contract successfully
• Defines the obligations of the parties, so that when a dispute arises, the arbitrator
neccontract.com © nec 07/2011
that when a dispute arises, the arbitrator or court can identify responsibilities
ECC payment options
• Lump sums (activity schedule)
• Bill of quantities
• Target (with activity schedule/ bill of
neccontract.com © nec 07/2011
• Target (with activity schedule/ bill of quantities)
• Cost reimbursement
• Management
Financial risk allocation
target
neccontract.com © nec 07/2011
Employer ContractorFINANCIAL RISK
cost reimbursable
lumpsum
measurement
NEC – the contracts
neccontract.com © nec 07/2011
NEC Key Concepts
• Clarity of document
• Flexibility of use
• Stimulus to good management
neccontract.com © nec 07/2011
• Stimulus to good management
Key Concepts - Clarity
• Uses language and procedures which are straightforward and easily understood
• Present tense defines actions of parties not liabilities
neccontract.com © nec 07/2011
not liabilities
• Minimal subjective judgements
• Minimal legal jargon
• Procedural logic backed up by flow charts
Language
The Employer shall indemnify and hold harmless the Contractor, the Contractor’s Personnel, and their respective agents, against and from all claims, damages, losses and expenses (including legal fees and expenses) in respect of (1) bodily injury, sickness,
neccontract.com © nec 07/2011
expenses) in respect of (1) bodily injury, sickness, disease or death, which is attributable to any negligence, wilful act or breach of the Contract by the Employer, the Employer’s Personnel, or any of their respective agents, and (2) the matters for which liability may be excluded from insurance cover, as described in sub-paragraphs (d)(i), (ii) and (iii) of Sub-Clause 18.3 [Insurance Against Injury to Persons and Damage to Property].
NEC
Each Party indemnifies the other against claims, proceedings, compensation and costs due to an event which is at his risk.
neccontract.com © nec 07/2011
From the starting date until the Defects Certificate has been issued, the risks which are not carried by the Employer are carried by the Contractor.
FIDIC imperative
• The Contractor shall commence the execution of the Works as soon as is reasonably practicable after the Commencement Date, and shall then
neccontract.com © nec 07/2011
Commencement Date, and shall then proceed with the Works with due expedition and without delay.
• The Contractor shall complete the whole of the Works, and each Section (if any), within the Time for Completion for the Works or Section (as the case may be)
NEC present tense
• The Contractor does not start work on the Site until the first access date and does the work so that Completion is on or before the Completion Date.
neccontract.com © nec 07/2011
before the Completion Date.
Subjective judgements
Extension of time for weather - FIDIC
• exceptionally adverse climatic conditions
neccontract.com © nec 07/2011
NEC approach
• a weather measurement is recorded the value of which, by comparison with the weather data, is shown to occur on average less frequently than once in ten years.
Key Concepts - Flexibility
• Multi-disciplinary
• Complete family of contracts
• Design & build - any mix allowed
neccontract.com © nec 07/2011
• Design & build - any mix allowed
• Risk allocation - by employer - not fixed by contract
• International application of contract
Multi-disciplinary
• Engineering and Construction Contract
• suitable for all types of construction
• Professional Services
neccontract.com © nec 07/2011
• suitable for all consultancy services
• Term covers any service
• Supply of any goods
Design & build
• Any extent of design permitted• minor – culvert crossing• major – EPC contract
• Employer provides design specification
neccontract.com © nec 07/2011
• Employer provides design specification• Contractor provides design proposals at tender if required
• Contractor provides design details for acceptance as required
• Contractor takes risk of change in his design needed to meet Employer design specification
International application
His Honour Humphrey Lloyd QC considers that there are no real barriers to the NEC3 Engineering and Construction Contract being used internationally.
neccontract.com © nec 07/2011
internationally.
His Honour Humphrey Lloyd QC was a judge of the
UK Technology and Construction Court in London
from 1993 to 2005 and has been a member of the
Commission on International Arbitration of the
International Chamber of Commerce (ICC) since
1980
Key concepts - stimulus to good management
• Stimulates good management of
• the relationship between the parties
neccontract.com © nec 07/2011
• the work in the contract
• Examples in contract
• programme
• early warning
• notification of compensation events
Relationships in construction contracts
yesterday
Confrontation
today
Cooperation
tomorrow
Partnering
neccontract.com © nec 07/2011
Confrontation
Disputes
Claims
Cooperation
Active project management
Positive profitability
Partnering
Mutual objectives
Success
NEC relationships
The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation.
neccontract.com © nec 07/2011
mutual trust and co-operation.
Programme
• Programme provided at tender or after award as required
• Active project management tool• Includes allowances for float and risk, method statement
neccontract.com © nec 07/2011
statement• Regular updates
• Shows work done to date• Shows proposed timing of work to be done at date of revision
• Currently accepted programme used for assessments• previous programmes only relevant for as built records
Early Warning
• Notification by both parties• change in cost or delay
• impairment of the works
• Meeting
neccontract.com © nec 07/2011
• Meeting• cooperate to seek solutions in joint interest
• Action to manage events, not react to them
• Record actions in Risk Register
Compensation events
• List of events in contract
• Sole means of changing price/programme
• Payment and delay assessed together
neccontract.com © nec 07/2011
• Payment and delay assessed together
• Project Manager decides how to deal with event
• Assessed at time of event
• Transfers risk to Contractor of future effects of event
Managing NEC contracts
• contract is project management based
• contract provides project management system
• contract provisions simple to follow
neccontract.com © nec 07/2011
• intended to be read by project manager
• procedures need to be followed
• contract is not left in the drawer
• training in project management likely to help
FIDIC & NECFIDIC NEC
Language traditional imperative present tense defines actions
Flexibility limited selection of clauses main & secondary options
Additional requirements particular conditions Z clauses
Pricing fixed price or measurement fixed, measurement, target, cost, management
Management of contract
designed to allocate liabilities
detailed management procedures and responsibilities
neccontract.com © nec 07/2011
neccontract.com
contract liabilities procedures and responsibilities
Relationships adversarial approach co-operative approach
Programme Initial programme accepted Regularly updated programmes accepted
Changes Variations priced at bill rates Compensation events based on forecast cost
Claims time & cost claimed separately
time & cost assessed together & balance decided by PM
Claim assessment Records of cost Priced in advance as compensation events
Dispute resolution DAB - Arbitration Adjudicator - Tribunal
People in the NEC contracts
FIDIC NEC
Engineer Project Manager
neccontract.com © nec 07/2011
Resident Engineer/ Inspector
Supervisor
Dispute Adjudication Board
Adjudicator
Choice of forms
FIDIC NEC
Building and Engineering Works Engineering and Construction Contract
Plant and Design-Build Engineering and Construction Contract
EPC/Turnkey Projects Engineering and Construction Contract
neccontract.com © nec 07/2011
Short Form of Contract Engineering and Construction Short contract
Dredgers Contract Engineering and Construction Short contract
Client Consultant Model Services Agreement Professional Services Contract
Sub-Consultancy Agreement Professional Services Contract
Term Service Contract
Supply Contract
Framework Contract
Risk allocation options
Type of work FIDIC NEC
Works contract -admeasurement
Edition 1/ Harmonisedconditions
ECC bill of quantities option
Works contract –payment against work
Edition 1/ Harmonisedconditions with schedule
ECC lump sum option
neccontract.com © nec 07/2011
payment against work completed
conditions with schedule of payments
Target price - ECC target options
Cost reimbursable - ECC cost reimbursable option
Management - ECC management option
Examples of NEC in use
• South Africa – ESKOM power supply contracts, Pebble Bed Modular Nuclear Reactor contract
• India - Hydrerabad and Delhi airports works contracts
• Philippines - new British Embassy in Manila
neccontract.com © nec 07/2011
• Philippines - new British Embassy in Manila• South Africa – eThekwini water and sanitation project
• England – all public sector construction work• New Zealand – Meridian Energy power works, Christchurch airport
• Hong Kong government – several pilot contracts
British Embassy, Warsaw Poland
Al Raha development UAE$10bn
Durban Pier South Africa $120m
neccontract.com © nec 07/2011
Halley VI ice station Antarctica $22mEngland – Channel Tunnel Rail Link $6bn
IMPLEMENTATION OF NEC
neccontract.com © nec 07/2011
IMPLEMENTATION OF NEC
Implementation tools
• Standard Tender Documents and User’s Guide
• Contract preparation & procurement on web based electronic document compiler, or under licence for in house server
• Web based contract management system
• Extensive and proven direct and online training packages
neccontract.com © nec 07/2011
• Extensive and proven direct and online training packages
• Dedicated user group support
• Online access to funders and recipients providing information and guidance
• seminars & workshops
• helpdesk providing technical support
Standard Tender Documents and User’s Guide
• EBRD contracts and documents• Works• Supply• Plant
neccontract.com © nec 07/2011
• Plant
• NEC version standard tender document and User’s Guide covering all aspects of project• Engineering and Construction/ Short Contract• Supply/ Short Contract• Professional Services Contract• Term Service/ Short Contract
neccontract.com © nec 07/2011
neccontract.com
Example of support service
• Assistance to UK Government
• NEC group provides training & support to all public sector users
• Standard additional government clauses
neccontract.com © nec 07/2011
• Standard additional government clauses drafted
Government endorsement
• UK government recommends the use of NEC3 by public sector construction procurers on their construction projects
neccontract.com © nec 07/2011
• NEC one of four forms of contract permitted for S Africa work
Summary
NEC is
• clear and can be used for all types of work
• integrated between all levels in the procurement chain.
• free of legal association of any jurisdiction
neccontract.com © nec 07/2011
• suitable for international use
• strong project and programme management systems
• proven track record
Following the NEC philosophy leads to a successful project
Further information
• NEC integration into MDB standard bidding document
• integration into EDRB standard tender documents
• Access to current user group
neccontract.com © nec 07/2011
• Access to current user group
• Access to eLearning module
• Electronic copy of contract
• Further briefing/ advice through a dedicated consultant
NEC CONTRACTS
neccontract.com © nec 07/2011
Questions?