57
AFRICAN DEVELOPMENT FUND PROJECT COMPLETION REPORT ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA TRANSPORT DIVISION INFRASTRUCTURE DEPARTMENT-NORTH, EAST & SOUTH REGION FEBRUARY 2006

Ethiopia - Addis Ababa International Airport Development Project

  • Upload
    lythien

  • View
    253

  • Download
    0

Embed Size (px)

Citation preview

AFRICAN DEVELOPMENT FUND

PROJECT COMPLETION REPORT

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA

TRANSPORT DIVISION INFRASTRUCTURE DEPARTMENT-NORTH, EAST & SOUTH REGION

FEBRUARY 2006

TABLE OF CONTENTS

No. of Pages Equivalents and Abbreviations (i) Project Matrix (ii) Basic Project Data (iii-v) Executive Summary (vi-x)

1. INTRODUCTION 1 2. PROJECT OBJECTIVE AND FORMULATION 1 2.1 Project Objective 1

2.2 Description of the Project 1 2.3 Formulation, Evaluation and Approval 2

3. PROJECT EXECUTION 2 3.1 Effectiveness and Start-up 2 3.2 Modifications 2 3.3 Implementation Schedule 3 3.4 Reporting 4

3.5 Procurement 4 3.6 Financial Sources and Disbursements 5 4. PROJECT PERFORMANCE AND RESULTS 7 4.1 Overall Assessment 7 4.2 Operating Results 7 4.3 Institutional Performance 8 4.4 Management and Organisational Effectiveness 10 4.5 Staff Recruitment, Training and Development 10 4.6 Performance of Consultants, Contractors and Borrower 11 4.7 Conditions/Covenants 11 4.8 Economic Performance 11 4.9 Financial Performance 12 5. SOCIAL AND ENVIRONMENTAL IMPACT 13 5.1 Social Impact 13 5.2 Environmental Impact 13 6. PROJECT SUSTAINABILITY 13 7. PERFORMANCE OF THE BANK 14 8. OVERALL PERFORMANCE AND RATING 14 9. CONCLUSIONS, LESSONS LEARNT AND RECOMMENDATIONS 15

9.1 Conclusions 15 9.2 Lessons Learnt 16 9.3 Recommendations 17 This Report was prepared by Messrs. D.R.RAO, Consultant -Transport Engineer, D. GEBREMEDHIN, Consultant - Transport Economist and A. AKINTUNDE, Consultant-Financial Analyst, following their mission to Ethiopia from 31st December 2005 to 20th January 2006. The Task Manager is Mr. M.O.Ajijo, Principal Transport Economist, ONIN.3, Ext. 3110. Any inquiries relating to this report may be referred either to the Task Manager or to Mr. J. RWAMABUGA, Division Manager, ONIN.3, Ext. 2181.

LIST OF ANNEXES

Annex No. of No. Titles Pages

1. Project Location Map 1

2 Implementation Schedule (Appraisal Vs Actual) 3

3. Actual Project Costs (Component & Source) and Categories of Expenditure 5 4. Yearly Disbursements by Source of Funds 2

5. Comparison of actual with projected revenue and expenditure 1

6. Calculation of Financial Rate of Return 2

7 Calculation of Economic Rate of Return 7

8. Performance Evaluation and Rating 4

9. Recommendations and Follow-up Matrix 1

10. Sources of Information 1

i

EQUIVALENTS AND ABBREVIATIONS

CURRENCY EQUIVALENTS PCR Appraisal

1 UA = ETB 12.3595 9.1892

WEIGHTS AND MEASURES

1.00 meter (m) = 3.281 ft. 1.00 kilometre (km) = 0.621 mile 1.00 square kilometre (km2) = 0.386 square mile (mi2) 1.00 hectare (ha) = 2.471 acres 1.00 kilogram (kg) = 2.205 lbs.

FISCAL YEAR : 8th July – 7th July ABBREVIATIONS

ADB = African Development Bank ADF = African Development Fund APA = Advance Procurement Action CAA = Civil Aviation Authority DCF = Discounted Cash flow Analysis EA = Executing Agency EAE = Ethiopian Airport Enterprise EAL = Ethiopian Air lines ECAA = Ethiopian Civil Aviation Authority EIA = Environmental Impact Assessment EIRR = Economic Internal Rate of Return ETB = Ethiopian Birr FE = Foreign Exchange FIRR = Financial Internal Rate of Return GOE = Government of Ethiopia ICAO = International Civil Aviation Organisation ICB = International Competitive Bidding ILS = Instrument Landing System LC = Local Cost MOTAC = Ministry of Transport and Communications NPV = Net Present Value PCR = Project Completion Report PIU = Project Implementation Unit RE = Resident Engineer RFP = Request for Proposals TAF = Technical Assistance Fund TCDE = Transport Construction Design Enterprise TOR = Terms of Reference UA = Unit of Account UNDP = United Nations Development Programme WP 1 = Works Package for Airside Works WP 1 A = Works Package for Pavement Strengthening Works (Overlays)

iiETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT PROJECT COMPLETION REPORT: PROJECT MATRIX

Design Team: D.R Rao, D. Gebremedhin & A. Akintunde Verifiable Indicators Narrative Summary

Appraisal (1996) PCR (2006)

Means of Verification Assumptions/ Risks

Sector Goal 1.1 To improve the efficiency of the Transport Sector.

1.1 Aircraft time savings increased and unit cost of transport reduced by the year 1999 1.2 Aircraft movements increased

1.1 Aircraft time for air and taxiing in-out -time reduced from an average of 14 minutes to 12 minutes per aircraft in year2003. 1.2 Increase in intl. aircraft mov’t (11380– 14572), domestic( 7086-8373) and general aviation (14893-17848) between 2003 and 2005.

1.1 Transport statistics of Central Statistics Department

(Goal to Super goal)

Project Objective 2.1 The objective of the project is to upgrade the existing airside infrastructure facilities, improve Navaid-Communication Systems as per ICAO standards to meet the present and forecast levels of traffic over the next 20 years at Addis Ababa airport.

2.1 Commercial aircraft movement increase from 17272 in 1999 to 22095 in 2014 2.2 Compliance with ICAO standards 2.3 Operational services at the airport improved by 1999

2.1 Commercial aircraft movement increased from 14969 in 1999 and expected to increase further to 30981 in 2014 2.2 Complied with ICAO standards in 2003 2.3 Operational services at the airport improved in 2003.

2.1 Quarterly and annual reports of CAA. 2.2 PCR 2.3 CAA’s monthly operational summary records of Navigational and Communications systems and Project Performance Evaluation Reports( PPER)

(Project Objective to Goal) 2.1Forecast traffic growth requirements including hub traffic will materialise 2.2. Operational targets of CAA will be achieved

Outputs* 3.1 Additional facility of a New runway of 3800m long with five ( including 2 high speed) connecting exit taxiways together with ancillary structures i.e. airfield drainage, top soiling, security fencing and perimeter road. 3.2 Existing pavement and taxiways strengthened with overlays

3.1 Additional facility of new runway of 3800m long with 5 exit taxiways together with its associated works airfield drainage, top soiling, perimeter road and security fencing constructed as per speci- fications & operational by October 1998. 3.2 Existing pavement and taxiways strengthe- ned as per specifications before April 1999

3.1 3800m of New runway & five exit taxiways together with ancillary works (airfield drainage, top soiling, security fencing & perimeter road) completed in February 2003. 3.2 Strengthening of the existing pavement and taxiways completed in January 2004.

3.1 Quarterly Progress Reports (QPRS) 3.2 Supervision Reports (SRs). 3.3 Project Completion Report (PCR) 3.4 Audit Reports.

(Output to Project Objective) 3.1 Qualified & experienced staff remains with CAA to operate the facilities

Activities* A. Construction Works 4.1 Prequalification of contractors for New runway and its associated works 4.2 Issue and receipts of tenders, evaluation, negotia- tion and award of contracts. 4.3 Implementation of: (i) Construction 3800m of New Runway, five exit taxiways and related associated works (drainage, top soiling, security fencing & perimeter road). (ii) Strengthening of existing pavement and taxiways B. Consultancy Services for supervision of construction works of (i) & (ii) above. 4.4 Approval of TOR and Short list 4.5 Issue & receipt of RFP 4.6 Evaluation and approval and award of consultancy services 4.7 Commencement of services.

Inputs/Resources Inputs** (UA million) A. Civil works for: (i) New Runway, Five taxiways and associated Works (airfield drainage, top soi- ling, perimeter road & Security fencing 19.38 (ii) Strengthening of existing runway & taxiways 4.54 B. Consultancy Services for: • works at (i) 1.07 • works at (ii) 0.22 C. Proj. Audit 0.01 Contingencies.

-Physical & Price 5.14

Total 30.36 Resources (UA million) ADF 19.50 GOE 10.86 Total 30.36 EIRR (%) = 23.3 FIRR (%) = 23.0

Inputs/Resources Actual costs (UA million) A. Civil works for: (i) New Runway, Five taxiways and associated Works (airfield drainage, top soi- ling, perimeter road & Security fencing 21.174

(ii) Strengthening of existing runway & taxiways 3.064 B. Consultancy Services for: • works at (i) 1.657 • works at (ii) 0.083

C. Proj. Audit 0.004 Total 25.982 Resources (UA million) ADF 17.132 GOE 8.850 Total 25.982 EIRR (%) = 30.5 FIRR (%) = 30.0

4.1 Appraisal Estimates. 4.2 Quarterly Progress Reports 4.3 Supervision Reports 4.4 Project Completion Reports 4.5 Audited Accounts 4.6 Disbursement Records

4.1 All procurement actions are on schedule. 4.2 Payments for invoices are not delayed. 4.3 Effective coordination of donors and implementation monitoring by the executing agency

*The outputs & activities listed herein are for the project components of Works Packages WP I and WP IA financed by ADF and GOE. ** Input costs indicated in this column are the modified costs after modifications to the category of expenditures of ADF financed components.

iii

BASIC PROJECT DATA

1. Country : Ethiopia 2. Project : Addis Ababa International Airport Development Project 3. Loan Number : 2100150000304 4. Borrower : Government of Ethiopia 5. Beneficiary : Government of Ethiopia 6. Executing Agency : Civil Aviation Authority (CAA) A. LOAN DETAILS

Description At Appraisal

Actual

1.ADF Loan (UA million) 19.50 17.132 2. Commitment Fees 3. Service Charge

0.5% per annum on the un disbursed portion commencing 90 days after the signing of the loan agreement 0.75% per annum on amounts disbursed and outstanding.

4. Repayment Period 40 years

5. Grace Period 10 years

6. Repayment 1% of the principal each year from the eleventh to twentieth year inclusive and 3% each year thereafter.

7.Loan Negotiation Date 29-30 August 1996 8. Loan Approval Date 31-10-1996 9. Loan Signature Date 20-12-1996 10.Date of Entry into Force 11-07-1997

B. PROJECT DATA 1. Project Costs*

Item of Cost Appraisal Modified Actual Foreign Exchange Component 20.50 20.50 18. 219 Local Cost Component 12.43 9.86 7. 763 Total Cost 32.93 30.36 25. 982

(*Project Costs include for both Work packages WP1 & WP1A and Supervision services) 2. Source of Finance*

In UA Million Appraisal Modified Actual Source of

Finance F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total

ADF 19.50 - 19.50 19.50 - 19.50 17.132 - 17.132 GOE 1.00 12.43 13.43 1.00 9.86 10.86 1.087 7.763 8.850 Total 20.50 12.43 32.93 20.50 9.86 30.36 18.219 7.763 25.982

(* Source of Finance includes for both Work packages WP1 & WP1A and Supervision services) Appraisal Actual 3. Effective Date of First Disbursement: - 07 August 1997 4. Effective Date of Last Disbursement: 31 December 1999 31 December 2004 5. Commencement of Project: November 1996 March 1997 6. Completion of Project November 1998 January 2004

ivC. PERFORMANCE INDICATORS 1. Cost Under-run : 14.43% 2. Time Overrun( including additional works) : 58 months * Slippage on Effectiveness (%) : Nil * Slippage on Completion Date : 242% * Slippage on Last Disbursement : 500% * Number of Extensions of Loan Validity Period : 5 3. Project Implementation Status : Completed 4. List of Verifiable Indicators and Levels of Achievement

Score Evaluation Criterion Maximum Actual

1. Time Overruns 2. Cost Overruns / Under Run 3. Adherence to Contractual Conditions 4. Adequacy of Supervision and Reports 5. Operational Performance Total Score

4 4 4 4 4 20

2 3 2 3 3

13 5. Implementation Performance

* Institutional Performance : Satisfactory * Consultant’s Performance : Satisfactory * Contractor’s Performance : Satisfactory

6. Economic Internal Rate of Return (EIRR): Appraisal : 23.3%

Actual : 30.5% 7. Financial Internal Rate of Return( FIRR): Appraisal : 23% Actual : 30% D. MISSIONS

Project Cycle M/Y Numbers of Persons Composition Man Days 1. Identification - - - - 2. Preparation - - - - 3. Appraisal 05/1996 3 T.Engr, T.Econ, F.A 42 4. Supervision/follow up 03/ 1998

12/1998 09/1999 06/2000 11/2000 07/2001 11/2001 06/2002 12/2002 06/2003 11/2003 04/2004 11/2004

2 2 2 3 2 2 1 2 1 2 2 1 3

T.Engr;T.Econ T.Engr, F.A T.Engr,F.A DM,T.Engr,T.Econ T.Engr,T.Econ T.Engr,T.Econ T.Econ. T.Econ, T.Engr T.Econ. T.Econ, T.Engr T.Econ,T.Engr T.Econ. DM,T.Econ,T.Engr

42 28 28 50 42 42 14 42 19 28 28 10 42

5. PCR 01/2005 3 T.Engr, T.Econ, F.A 44 DM: Division Manager; T.Engr: Transport Engineer; T.E: Transport Economist; F.A: Financial Analyst.

v

E. BANK LOAN –DISBURSEMENTS (UA MILLION)

Appraisal Actual Year Amount Cum. (%) Amount Cum. (%)

1996 1997 1998 1999 2000 2001 2002 2003 2004

3.90 9.75 5.85

- - - - - -

20.0 70.0 100.0

- - - - - -

-

1.412 1.306 3.730 5.342 2.446 0.721 1.369 0.806

-

8.3 15.9 37.6 68.8 83.1 87.3 95.3 100.0

Total 19.50 100.0 17.132 100.0 Un-disbursed Loan Balance Cancelled

2.368

F. CONTRACTOR ( Package WP1 ) Name : Kajima-Keangnam JV (Japan-S. Korea)

Contract Description : Package WP1: Construction works for New Runway, 5 Taxiways, drainage structures, Perimeter Road &Security fencing Date Works Commenced : 14th March 1997

Date Contract Completed : February 2001 (excluding defects liability period of 12 months) Contract Duration : 59 months Amount : ETB 175.27 million (actual ETB 190.88 million) CONTRACTOR ( Package WP 1A) Name : M.A.Al-Kharafi and Sons ( Kuwait)

Contract Description : Package WP1A: Strengthening of Existing Runway and Taxiway Date Works Commenced : 4th April 2003

Date Contract Completed : 31 January 2004 (excluding defects liability period of 12 months) Contract Duration : 9 months Amount : ETB 45.94 million (actual ETB 32.45 million) G CONSULTANT ( Supervision of works for Package WP1, GOE financing) Name : Dar -Al Handasah (Lebanon) Contract Description : Supervision of Works for Works Package WP1 Date Contract Signed : 15th August 1996 Date Supervision Commenced : 15th August 1996 Date Contract Completed : 31 December 1998 (extended up to 28 Feb 2002) Contract Duration : 27 months, extended to 66 months Amount : US $ 1. 28 million + ETB 3.29 million (actual ETB 16.78 million) CONSULTANT ( Supervision of works for Package WP1A, GOE Financing) Name : Transport Construction Design Enterprise, TCDE (Ethiopia) Contract Description : Supervision of Works for Works Package WP 1A Date Contract Signed : 1st November 2001 Date Supervision Commenced : 1st November 2001 Date Contract Completed : 31 January 2004 Contract Duration : 27 months Amount : ETB 0.925 million

vi

EXECUTIVE SUMMARY

1. INTRODUCTION 1.1 Ethiopia, situated in the North-Eastern corner of Africa has an area of about 1.14 million km2 land. The country is bounded in the North by Eritrea, in the West by Sudan, in the East by Somalia and Djibouti, and in the South by Kenya (Annex 1). The projected population of the country is 73 million in 2005. The project is located within the capital city (Addis Ababa) international airport at Bole. 1.2 As a part of overall strategy to promote economic growth, priority was given by the Government of Ethiopia (GOE) to the development of transport infrastructure of the country with emphasis on airport infrastructure. As a follow up, Addis Ababa Airport which is the country’s main international and domestic airport, situated at Bole on the southern outskirts of the city, was accorded priority for its immediate development to the requirements of ICAO standards. Initial master plan studies for the Addis Ababa Airport were carried out under the UNDP-ICAO technical assistance. The Bank has to date approved two projects and one study in the air sub-sector, these have been successfully completed. 1.3 The detailed economic feasibility and engineering design of the project (both landside and airside packages) were completed in December 1993 with the assistance of ADF /TAF resources. During a Donors meeting in November 1995, the Bank agreed to finance some components of the airside package which included the construction of the new runway of 3800 m with five exit taxiways together with its ancillary structures. A Bank’s mission visited Ethiopia in May 1996 to appraise the project. The loan conditions were negotiated and there were no issues of disagreement raised by the Bank or the Borrower. The loan amount of UA 19.50 million was approved by the Board in October 1996, signed in December 1996 and declared effective in July 1997. 1.4 This Project Completion Report (PCR) is based on the appraisal report, project files in the Bank, Borrower’s quarterly progress reports, Construction final reports and PCR, interviews and site inspection conducted during an ADB mission to Ethiopia in January 2006. Project Objective and Description 1.5 The objective of the project is to upgrade the existing airside infrastructure facilities, improve Navaid-Communication Systems as per ICAO standards to meet the present and forecast levels of traffic over the next twenty years at Addis Ababa airport. 1.6 The project consists basically of six components:

(i) Civil works for (a) construction of a new runway of 3800m long with five exit taxi

ways; (b) airfield drainage and top soiling; and (c) security fencing and perimeter road;

(ii) Supply, installation and commissioning of Airside equipment, Airfield lighting and Navaid communication systems;

(iii) Construction of new rigid apron of 70,000 sq.m; (iv) Construction works for strengthening of existing pavements ( overlays); (v) Institutional Support to Project Management Unit ; (vi) Consultancy services for supervision of components (i) to (iv) above, and audit of

civil works of (i) above.

At appraisal, the ADF financed components were at (i) above and the audit of civil works under the component (vi). However, during implementation, after realising some savings under the approved ADF loan, the Bank at the request of the GOE, agreed to finance the strengthening works for the existing pavement (overlays) component at (iv) above, that was to be financed fully by the Government. GOE financed the supervision consultancy services for the above both components.

vii

1.7 There was no change in the project objective, however some modifications to the design were effected during implementation, due to the site conditions. Project Execution and Implementation Schedule

1.8 The Project was executed by the Civil Aviation Authority (CAA) through the Project Coordinator of the established Project Implementation Unit (PIU) and with the support of the supervision consultant. 1.9 The ADF financed components (airside package works) of the project as envisaged at appraisal was to commence in November 1996 and completed in November 1998 (24 months). Though procurement actions for the works were completed as early as in October 1996, due to protracted negotiations, the contract was awarded only on 8th March 1997 to the lowest evaluated bidder, i.e. M/s Kajima Keangnam, JV (Japan- S. Korea); works commenced on 14 March 1997 and were completed in all respects in February 2002 with long delay due to modifications to the pavement design, adverse weather conditions coupled with constraints of execution of works under the operational airport. The contract for the “Strengthening works of the existing pavement, WP 1A (overlays)”, was awarded to M/s M. A. Al-Kharafi & Sons (Lebanon) on 1st April 2003, and were completed in January 2004. 1.10 Consultancy services for supervision of ADF financed airside package WP I works (financed by GOE) was awarded to M/s Dar –Al Handsah (Lebanon). Services commenced on 15 August 1996 and were completed in February 2002. Similarly, consultancy services for the supervision of the strengthening works (WP IA) was awarded to Transport Construction Design Enterprise, TCDE (Ethiopia) on 1st November 2001 and continued until the completion of the strengthening works in January 2004. 1.11 In spite of delays during implementation, the final outputs of the new runway and its ancillary structures were well executed. The new facilities provided under the project at Addis Ababa Airport, benefited the country in the improvement of air transport services both in international and domestic routes. Annex 2 shows the implementation schedule at Appraisal vs Actual.

Project Costs and Financial Resources

1.12 At appraisal, the cost of the ADF financed works package WP I and WP IA (including project audit and supervision of works financed by GOE) was estimated at UA 32.93 million. The actual total cost of completion of the ADF financed package works WP 1 and WP 1A (including project audit and consultancy services for supervision) was UA 25.982 million. 1.13 The total completed cost of the ADF components of the project (UA 17.132 million) for both packages, i.e. WP 1 (New Runway and ancillary works) and WP 1A (strengthening works), was noted to be less than the approved loan amount of UA 19.50 million. The Bank with the consent of the Government cancelled the balance of UA 2.368 million realized as savings under the ADF loan. A summary of the project costs at appraisal, modified and actual is shown in Table 3.1 and details in Annex 3. Overall, there was a cost under run of about UA 4.38 million.

Overall Assessment 1.14 In spite of some delays during project implementation, a well designed new runway facility with Navaid and Communication systems at the Addis Ababa airport conforming to ICAO standards, had benefited the country with significant improvements in the air transport services both on the international and domestic routes. The operation of the airport with new facilities provided under the project, significantly reduced the aircraft movements time especially in taxi in- and -out times.

viii Economic Performance 1.15 The traffic projection at appraisal has been revised taking into account the 1994-2005 data, which is used as the basis for traffic forecast. The actual traffic after the project completion (2003 – 2005) shows an annual growth rate of 21.8% (international passengers), 8.8% (domestic passengers), 13.3% (international commercial aircraft movement), 8.7% (domestic aircraft movement), 9.5% (general aviation movement) and 32.3% (EAL cargo). However, a decline of 20.0% was recorded for foreign carrier cargo. Based on the historical traffic annual growth rates, the international passenger, domestic passenger, international aircraft, domestic aircraft, general aviation, EAL and foreign carrier cargo are projected to grow at an average annual growth rate of 3% to 6% between 2006 and 2010 and after the year 2011 by 2% to 4%. 1.16 The actual traffic for the year 2005 when compared with the appraisal forecasts shows an increase of 13.8%, 13.9%, 66.5% for international passenger, commercial international aircraft and general aircraft movement respectively. On the other hand, the domestic passenger, commercial domestic aircraft movement, EAL and foreign carrier cargoes have declined by 32.4 %, 25.6%, 66.4% and 49.2% respectively. The recalculated EIRR has been estimated to be 30.5 % (Annex 7 page 7 of 7). This compared with 23.3 % at appraisal is high, due to the growth in the international passenger, aircraft and general aircraft movement, 23.9 % reduction in the airside construction cost and capital cost disbursement over eight years period as compared to four years anticipated at appraisal. This EIRR of 30.5 % is well above the opportunity cost of capital of 11% in Ethiopia Financial Performance 1.17 The appraisal forecasts were in excess of actual revenue by an average of 12% per annum over the period. The projected expenses were equally over-estimated with actual performance yielding average savings of about 56% per annum over the same period. Consequently, the actual financial results surpassed appraisal forecasts on the average by as much as 100% per annum. The comparison of the actual with estimated revenue and expenses is presented in Annex 5. 1.18 A retrospective financial analysis based upon the resulting stream of cash flows adopting with and without scenarios is presented in Annex 6. Based on this, the financial internal rate of return is estimated to be 30%, which is well above the appraisal estimate of 23% and the current opportunity cost of capital of 11% in Ethiopia. This performance is accounted for by increased cash flows resulting from better margins than envisaged at appraisal, savings on project cost and longer spread of disbursements.

2. CONCLUSIONS, LESSONS LEARNT AND RECOMMENDATIONS

Conclusions

2.1 The overall objectives of the project have been fully achieved. The additional facilities provided at the Addis Ababa Airport with a new runway and its ancillary structures, significantly improved the air transport services both on international and domestic routes. The constructed new runway has a good riding smooth surface and found to be safe in landing and taking off operations and is environmentally protected. The value and quality of the project was greatly enhanced despite some delays during the project implementation. The re-calculated EIRR and FIRR at PCR in respect of the ADF components are 30.5 % and 30.0% respectively.

ix Lessons Learned 2.2 Lessons from the project are: The lessons learned from the project are given hereunder: The time period given for execution of works (24 months in this case) under working conditions of an operational airport appear to be un-practicable. A realistic time period taking into consideration the nature of works and the operational working conditions should have been allowed for execution of works of such complex nature. (para 3.3.3);

• Adequate attention is necessary by the concerned disbursement officers of the Bank when apportioning currencies of payments to the concerned parties, before effecting the disbursements. (para 3.6.4);

• The Bank ought to have followed up, during negotiation, some of the weaknesses observed at appraisal concerning the accounting and management practices of the EA, to obtain an undertaking from the Borrower to strengthen those weaknesses. (paras 4.3.3 and 4.3.8);

• The non-audit of financial statements of EAs also borders on non-compliance with local laws. The Bank ought to have ensured submission of the EAs audited accounts at the same time the project’s audited accounts were being submitted. (paras 4.3.5 and 4.3.6);

• In order to protect the investment, the tariff revision is important. GOE should therefore expedite approval of the recommendations of the tariff proposed by EAE for implementation without further delay. (paras 4.3.9 and 4.7.1);

• A pre-design review (before issue of tender bids) by the selected consultant (if different from the original detailed design consultant) before launching the bids is always preferable, as this would bring out the deficiencies if any, in the original design and at the same time avoid modifications (involving additional costs) during execution. In the case at hand, though there was an initial delay in the start up of the project construction due to pre-design review; this proved to be effective in the review of design deficiencies at the early stages and elimination of the unexpected risks and difficulties. The project was executed and completed successfully with no modifications during the execution stage. It is understood that this is now being followed for all Bank financed projects. (para 4.6.1). Recommendations

2.3 It is recommended that:

For the Borrower

• For execution of projects of similar nature (in particular under operational conditions), Borrowers should review and assess the time period required for completion in order to minimise time extensions and additional payments. (para 3.3.3);

• Rectify the defects observed during the field inspection of the completed project (Para. 4.2.2); • GOE should ensure strengthening of the financial management capacity of ECAA and EAE.

Specifically, the introduction of fixed assets register, aggressive debt collection, and preparation of periodic accounts on a timely basis should receive immediate attention. (para 4.3.3);

• GOE to ensure that the audit of financial statements of ECAA and EAE are undertaken firstly to clear the backlog and thereafter on a regular annual basis to ensure that they do not fall into arrears again in the future. (paras 4.3.5 and 4.3.6); and

• GOE should fulfil its undertaking given as one of the conditions precedent to first disbursement, that tariffs will be adjusted in line with market trend. Priority should be accorded to the approval and implementation of the revised tariffs proposed by EAE (paras 4.3.9 and 4.7.1).

For the Bank

• Bank should be more practical in examining and specifying realistic time period required (during appraisal stage) for execution of projects of similar nature (in particular under operational conditions). (para 3.3.3);

• Adequate care should be exercised in making entries concerning apportionment of currencies especially at the contract entry into SAP. (para 3.6.4);

x • Future Bank operations should not only look at the financial management capacity and health of

EAs, but also ensure where appropriate, insertion of clauses requiring that observed weaknesses in the accounting and management practices are strengthened to safeguard Bank’s investment. (para 4.3.3);

• Future Bank operations should ensure as a matter of routine, the enforcement of submission of audit reports of both the EA and project on timely basis. (paras 4.3.5 and 4.3.6);

• Bank to follow up with the GOE on the fulfillment of the undertaking on tariff adjustments given as part of the loan conditions. ( paras 4.3.9 and 4.7.1);

• The problems surrounding the non-fulfilment of loan conditions, weaknesses in financial and management practices of ECAA and EAE, non-audit of accounts should be taken up as issues for future policy dialogue with GOE; and

• The Bank should develop appropriate response to future similar laxities and non-fulfilment of loan conditions by Borrowers.

1

1. INTRODUCTION 1.1 Ethiopia, situated in the North-Eastern corner of Africa has an area of about 1.14 million square km2 land area. The country is landlocked and is bounded in the North by Eritrea, in the West by Sudan, in the East by Somalia and Djibouti, and in the South by Kenya (Annex 1). The projected population of the country is 73 million in 2005. The project is located within the capital city (Addis Ababa) international airport at Bole. 1.2 The transport system of Ethiopia consists of four modes of which road is the dominant. The four modes are: (i) a road network of about 37, 018 km, (ii) 781 km of railways, (iii) minor river and lake transport services; and (iv) fifteen commercial airports and several rudimentary airstrips. The country is served by two international airports (Addis Ababa and Dire Dawa), seven major and six medium sized domestic airports. At the time of the project appraisal, most of the airports ( including Addis Ababa airport at Bole) does not fully conform to the ICAO standard infrastructure requirements, as most of the main facilities, such as runway, taxi track etc had significantly deteriorated due to various factors. 1.3 As a part of overall strategy to promote economic growth, priority was given by the Government of Ethiopia (GOE) to the development of transport infrastructure of the country with emphasis on airport infrastructure. As a follow up, Addis Ababa airport which is the country’s main international and domestic airport, situated at Bole on the southern outskirts of the city, was accorded priority for its immediate development to the requirements of ICAO standards. Consequently, the GOE commissioned the initial master plan studies for the major international airports of the country under the UNDP-ICAO technical assistance. 1.4 The detailed economic feasibility and engineering design of the project (both landside and airside packages) were completed in December 1993 with the assistance of ADF /TAF resources. In order to mobilise the resources for both packages (airside and landside) of the project, a donors meeting was organised in November 1995; the Bank agreed to finance some components of the airside package which included the construction of the new runway with five exit taxiways together with its ancillary structures. A Bank’s mission visited Ethiopia in May 1996 to appraise the airside components of the project. The loan was approved by the Board in October 1996 and was signed in December 1996 for an amount of UA 19.50 million. 1.5 This Project Completion Report (PCR) is based on the appraisal report, project files in the Bank, Borrower’s quarterly progress reports and PCR, interviews and site inspection conducted during an ADB mission to Ethiopia in January 2006. 2. PROJECT OBJECTIVE AND FORMULATION

2.1 Project Objective The objective of the project is to upgrade the existing airside infrastructure facilities, improve Navaid-Communication Systems as per ICAO standards to meet the present and forecast levels of traffic over the next twenty years at Addis Ababa airport. 2.2 Description 2.2.1 The project consists basically of six components:

(i) Civil works for (a) construction of a new runway of 3800m long with five exit taxi

ways; (b) airfield drainage and top soiling; and (c) security fencing and perimeter road; (ii) Supply, installation and commissioning of Airside equipment, Airfield lighting and

Navaid communication systems; (iii) Construction of new rigid apron of 70,000 sq.m; (iv) Construction works for strengthening of existing pavements (overlays); (v) Institutional Support to Project Management Unit ; and (vi) Consultancy services for supervision of components (i) to (iv) above, and audit of civil

works of (i) above.

2

2.2.2 At appraisal, the ADF financed components were at (i) above and the audit of civil works under the component (vi). However, during implementation, after realising some savings under the approved ADF loan, the Bank at the request of the GOE, agreed to finance the strengthening works for the existing pavement ( overlays) component at (iv) above, that was to be financed fully by the Government.

2.3 Formulation, Evaluation and Approval

2.3.1 The necessity for improvements and development of national airports which are vital for the country’s economy was identified by the GOE in 1988 as an objective of its transport policy. A master plan study covering five major airports (including Addis Ababa) was undertaken and completed in May 1990. Due to fast deterioration of the only runway at Addis Ababa International Airport, the Government requested the assistance of the Bank for an update of the master plan study including preparation of the detailed engineering studies. Consequently, the feasibility update and detailed engineering design reports were completed in December 1993, which recommended three packages, viz. (i) airside works, Works Package WP I ( new runway, taxiways, (ii) landside works WP II ( New terminal building and associated works), and (iii) Navaid -Communication systems, Works Package WP III.

2.3.2 In early 1993, GOE had formally requested the Bank to finance the airside package. A donor

meeting was organised in November 1995 to secure funds for all the three packages of the project. Funds were mobilized for all the three packages and ADF participated in the financing of some components of the airside package. An appraisal mission comprising a Transport Engineer, a Transport Economist and a Financial Analyst visited Ethiopia in May 1996 to appraise the project. The loan conditions were negotiated and there were no issues of disagreement raised by the Bank or the Borrower concerning the project. The ADF loan amount of UA 19.50 million was approved on 31 October 1996.

3. PROJECT EXECUTION

3.1 Effectiveness and Start-up The loan was approved on 31 October 1996, signed on 20 December 1996 and declared effective on 11 July 1997. The loan was signed 36 days after approval (maximum allowable 180 days) and declared effective 8 months after approval (maximum allowable 12 months). In accordance with Clauses 9.01 and 15.01 of the General Conditions Applicable to Loan Agreement and Guarantee Agreement of the ADF, there were no slippages either in the loan signature or for the loan effectiveness.

3.2 Modifications 3.2.1 In the course of the project implementation, some modifications were effected in respect of (i) scope of work, and (ii) pavement design specification, after approval by the ADF Board of Directors. The relevant modifications are summarized below:

(a) Scope of Works

• A review of the total expenditure after substantial completion on the Bank

financed airside package works WPI, indicated some savings under the loan. Accordingly, GOE requested the Bank to undertake financing the foreign exchange costs (out of the savings) for component D, i.e. Strengthening works of existing pavement, WP IA (Overlays). The Bank agreed to the proposal and a modification to the original categories of expenditure was approved on 12 April 2001 to include this component for additional works.

3

(b) Design Modifications

• During implementation, two modifications were carried out to the original design.

The first change in design was in respect of the black cotton soil (BCS) that was recommended as fill material to form an embankment upon which the runway is laid with preloading of BCS with a top surcharge of 1.0m above the finished pavement level for a period of 6 months. However, after detailed investigation by the expert engineers, it was felt that a revision was necessary to the original proposal that a non-swelling fill material be used instead to minimise the potential risk of damage to the pavement structure.

• The second change in the design was for the drainage under the pavement, i.e.

provision of vertical sand drains vs vertical trenching. After a field test, it was found that drainage by trenching method was found to be much faster and efficient when compared to the sand drains; as such vertical trenching method was finally adopted.

(c) Pavement Design specifications

• Due to change in soil conditions and filling material, some modifications were effected and the original thickness of the pavement was revised. The crushed stone base course thickness of 405 mm (provided in the original design) was modified with a thickness varying from 405 mm to 520 mm. Similarly, the bituminous base course thickness of 200 mm was modified in the revised design and it varied from 200 to 280 mm. However, the crushed stone sub-base thickness of 710 mm (as per original design) was adopted for most part of the length of the runway pavement, except at very few places it was reduced to 640 mm. The above changes in the pavement thickness had resulted in increase in quantities of some items.

In addition, the constant thickness of bituminous wearing course of 125 mm for the total width of the pavement was modified in the revised design. The thickness was gradually reduced from 125 mm at the crown to 90 mm at the edges, based on the distribution load intensity of the aircraft. This modification of varying thickness had resulted in some reduction in the quantity of bituminous wearing course material.

• Minor additions to drainage were carried out based on the site conditions, by providing saucer drains at both ends of the blast pads for improving drainage.

3.3 Implementation Schedule

3.3.1 The Project was executed by the Civil Aviation Authority (CAA) through the Project Coordinator of the established Project Implementation Unit (PIU) and with the support of the supervision consultant. 3.3.2 The ADF financed components (airside package works) of the project as envisaged at appraisal was to commence in November 1996 and completed in November 1998 (24 months). The process for procurement of contractor (pre-qualification, floating of tenders, evaluation etc) for construction works was through Advance Procurement Action (APA) approved by the Bank. Even though, procurement actions for the construction works were completed as early as in October 1996, the contract was awarded only on 8th March 1997 to the lowest evaluated bidder, i.e. M/s Kajima Keangnam, JV (Japan- S. Korea); works commenced on 14 March 1997 and completed in February 2002. 3.3.3 There was substantial delay in the completion of the works package WP I due to various factors, some of them are given hereunder. It was noted that during implementation, a total of 5 time extensions were given to the contractor:

4

Delay in sub-soil investigation related to foundation design and treatment; modifications to foundation drainage (trench method vis-à-vis vertical sand drains); working conditions’ constraints under an operational airport; adverse weather conditions coupled with unexpected heavy rains; increase in quantities due to change in pavement design; additional ducting works for electrical cables; and interruption of works at taxiway junction (during airport operations) with the existing

runway. In addition, with execution of additional works, WP I A of Strengthening of the existing pavement (Overlays), the overall completion was further delayed up to January 2004, making thus a total delay of 58 months.

3.3.4 The contract for the “Strengthening works of the existing pavement (WP 1A)”, was awarded to the lowest bidder M/s M. A. Kharafi & Sons on 1st April 2003. Works for this component were commenced on 4th April 2003 and completed in January 2004. It was noted that in both procurements, there were no disputes or complaints in the award of contracts to these firms. 3.3.5 Consultancy services (financed by GOE) for supervision of ADF financed airside package (WP I) works was awarded to M/s Dar –Al Handsah (Lebanon) in August 1996 with a completion period of 27 months. Consultancy services commenced on 15 August 1996 and were to be completed on 15th November 1998. However, due to delays in the execution of construction works for the reasons indicated in para 3.3.3 above, the services continued until February 2003 with seven extensions through seven addenda. Similarly, consultancy services for the supervision of the strengthening works (WP IA) was awarded to M/s Transport Construction Design Enterprise, TCDE (Ethiopia) on 1st November 2001 and continued until the completion of the strengthening works in January 2004. 3.3.6 In spite of delays during implementation, the final outputs of new runway and its ancillary structures were well executed. The new facilities provided at Addis Ababa Airport under the project, benefited the country in the improvement of air transport services both on international and domestic routes. Annex 2 shows the implementation schedule at Appraisal vs Actual.

3.4 Reporting 3.4.1 The implementation of the project was monitored through monthly progress reports prepared by the consultants and quarterly progress reports prepared by the Government in the Bank’s format. In addition, the project was monitored through regular Bank’s supervision and follow up missions.

3.4.2 Pursuant to the provisions of the General Conditions of the Loan Agreement, the GOE submitted quarterly progress reports, the Consultant's final construction report, annual audit reports and the Borrower's PCR. The contents of the progress reports in terms of keeping the Bank informed continuously of the project status, was noted to be satisfactory. However, it was noted that the project audit reports (financed by the Bank) do not meet the requirements given in the guidelines for audit of Bank financed projects.

3.5 Procurement

Consultancy Services for Airside Works Package WP 1 (financed by GOE) 3.5.1 The consultant for the supervision of construction works was selected through a shortlist of qualified firms in accordance with the GOE’s procurement rules. Request for Proposals (RFP) was issued to twelve international consultants. It was noted that the TOR stipulated a review of the detailed design carried out by the original design consultant (TAMS, USA), before issue of tenders. Even though, this component was financed by GOE, being a condition precedent to the first disbursement, GOE obtained the consent of the Bank in respect of appointment of the supervision consultant for the works. The supervision contract was awarded to M/s Dar – Al Handasah (Lebanon) in August 1996.

5

Consultancy Services for Strengthening Works ( Overlays) Package WP 1 A (financed by GOE)

3.5.2 The consultancy services for the supervision of strengthening works (Overlays), financed under GOE resources was selected in accordance with GOE’s procurement rules. Based on the experience in design and supervision of airport projects, GOE procured the consultant TCDE (a Government owned entity) through direct negotiations to supervise the works under this package. The Bank reviewed the selection process and gave its “no objection” for its procurement; the contract was awarded to M/s TCDE in November 2001. Civil Construction Works for Airside Package WP I ( financed by ADF) 3.5.3 The Executing Agency (CAA) followed the Bank’s Rules of Procedure for Procurement of Goods and Works. The Civil Works contractor was procured on the basis of International Competitive Bidding procedures (ICB) with pre-qualification of contractors. Twenty ne applicants were pre-qualified for the works. Tenders were issued on 28 March 1996 and twelve firms submitted the bids by the closing date. Bids were opened on 28 June 1996 and were evaluated in accordance with Bank’s Rules of Procedure for procurement of works. In order to accommodate the pavement design modifications as indicated in section 3.2.1 above, the selection of the contractor was delayed by about six months. After protracted negotiations with the lowest evaluated bidder, the contract for the construction of New runway and its ancillary structures was awarded to the lowest bidder M/s Kajima- Keangnam, JV (Japan- S.Korea) on 8 March 1997. Civil Works for Strengthening Works ( Overlays) Package WP I A ( financed by ADF) 3.5.4 The Executing Agency (CAA) followed the Bank’s rules of procedure applicable for medium contracts following ICB procedures, for procurement of contractor for the execution of these works component. Tenders were issued on 30 September 2001 to seven firms, but only five submitted the bids by the closing date. Tender bids were opened on 30 November 2001, evaluated in accordance with Bank’s Rules of Procedures and the second lowest bidder (M/s M.A. Al- Kharafi, Kuwait) was chosen, since the lowest bidder’s offer was unacceptable as the bidder had asked for a longer period for mobilization. The Bank reviewed the selection process and gave its “no objection” for the award of the contract to the second lowest bidder. A letter of acceptance was given on 22 December 2002 and the contract was awarded to M/s M.A. Al- Kharfi ( Kuwait) on 1st April 2003. 3.6 Financial Sources and Disbursements Project Costs 3.6.1 The estimated overall cost (net of all taxes) of the project, at appraisal, was UA 49.55 million (ETB 455.04 million) of which the foreign exchange cost was UA 35.75 million (ETB 328.58 million) or 72.15 % of the total and the local cost was UA 13.80 million (ETB 126.50 million) or 27.85 % of the total. The actual overall cost at completion was UA 36.83 million of which the foreign exchange cost was UA 26.28 million or 71.34 % of the total and the local cost was UA 10.56 million or 28.66 % of the total. The overall project cost at appraisal vs actual by component is presented in Annex 3 (page 1 of 5) while the summary by component and source is given in Annex 3 (page 2 of 5). 3.6.2 At appraisal, the ADF financed package of the project, WP 1 (excluding consultancy services for supervision, but inclusive of Project Audit services) was estimated to cost UA 26.10 million of which, the foreign exchange component was UA 19.50 million and the balance of UA 6.60 million was the local cost component. The total cost at appraisal including supervision (financed by GOE) and audit for works package WP 1 was UA 27.25 million, of which the FE was UA 20.50 and the remaining UA 6.75 was the local cost. The actual total cost of completion of the ADF financed package works WP 1 and WP 1A (excluding consultancy services for supervision, but including audit) was UA 24.242 million, of which the FE was UA 17.132 million and the remaining UA 7.110 was the local costs. The actual total cost of completion of the Works Package WP 1 and WP 1A (including consultancy services for supervision and audit) was UA 25.982 million, of which the FE was UA 18.219 million and the

6

remaining UA 7.763 was the local costs. Overall, there was a cost under-run of about UA 4.38 million under the ADF financed airside package works of the project. 3.6.3 The completion cost (UA 17.132 million) of the ADF components of the project (both packages (New Runway and ancillary works, WPI and Strengthening of Pavement works, WPIA), was found to be less than the approved loan amount of UA 19.50 million. The reduction in the completion cost vis-à-vis appraisal costs was due to keen competition and submission of cost effective competitive offers by the bidders. As a result of this, a saving of UA 2.368 million was realized under the ADF loan, and the Bank with the consent of the Government, had cancelled this balance. A summary of the project costs at appraisal, as modified and actual is shown in Table 3.1 below and details in Annex 3 (page 3 of 5).

Table 3.1: Summary of Project Costs at Appraisal, Modified and Actual

(UA Million, net of taxes)

Appraisal Modified Actual Component F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total

A. Civil Works for: (i) New Runway, 5 taxiways airfield drainage, top soiling, security fencing & perimeter road. (ii) Strengthening of existing runway and taxiways(overlays)

16.28

-

5.00

4.54

21.28

4.54

14.38

2.57

5.00

1.97

19.38

4.54

15.307

1.821

5.867

1.243

21.174

3.064 B. Consultancy Supn for:

• Works at item A (i) • Works at item A (ii)

1.00 -

0.07 0.22

1.07 0.22

1.00 -

0.07 0.22

1.07 0.22

1.087 -

0.570 0.083

1.657 0.083

C. Audit of Civil Works Un- allocated (Physical & Price contingencies)

0.04

3.18

-

2.60

0.04

5.78

0.01

2.54

-

2.60

0.01

5.14

0.004

-

-

-

0.004

-

TOTAL 20.50 12.43 32.93 20.50 9.86 30.36 18.219 7.763 25.982 Financial Resources

3.6.4 The project was co-financed by ADF, EIB, Kuwait Fund/BADEA/OPEC Fund, UNDP and GOE. The overall project cost at appraisal vs actual by component and source is summarised in Annex 3 (page 2 of 5). The financing plan for the ADF package at appraisal, as modified and actual expenditures (in UA terms) by source of finance using historical exchange rates in the computation of local costs is presented below in Table 3.2. As can be seen from the table, there was a change in the overall financing plan with ADF’s contribution (modified slightly as explained in paragraph 3.2.1(a) above), increased from 64.2% to 65.9%, while GOE’s contribution decreased from 35.8% to 34.1%. The final completion cost of the project indicated a cost under run of UA 4.38 million relative to the modified appraisal estimate.

Table 3.2: Financing Plan – Appraisal, Modified Vs Actual (UA million)

Appraisal Modified Actual Source of Finance

F.E. L.C. Total % F.E. L.C. Total % F.E. L.C. Total %

ADF 19.50 - 19.50 59.2 19.50 - 19.50 64.2 17.132 - 17.132 65.9 GOE 1.00 12.43 13.43 40.8 1.00 9.86 10.86 35.8 1.087 7.763 8.850 34.1 Total 20.50 12.43 32.93 100 20.50 9.86 30.36 100 18.219 7.763 25.982 100

7

7

Disbursements

3.6.5 The ADF loan funds were disbursed by direct method to contractors. However, the slippage in the implementation schedule had significantly affected the disbursement schedules. The disbursements, which were to start as per appraisal in November 1996, actually commenced from August 1997. The loan amount, as per the original appraisal schedule, was to be fully disbursed between 1996 and 1998, but due to delays in the start up of project construction, the first disbursement on ADF loan was effected in August 1997 and the last disbursement took place in January 2005. There were some disbursements delays during the construction activities due to (i) relocation of the Bank’s Headquarters to the TRA in Tunis, and (ii) wrong apportionment of currencies for ADF share of FE payments to the contractor. As a result of the delayed disbursements, GOE incurred interest costs in the sum of USD 28,230.13 and Yen 485,828. It was noted that the GOE made adequate budgetary allocations and payment of its own share of the project costs without delay. Annex 4 presents the disbursement profile at appraisal vs actual. The un-disbursed balance of UA 2.368 million on the ADF loan was cancelled in March 2005. 4. PROJECT PERFORMANCE AND RESULTS

4.1 Overall Assessment 4.1.1 The project was well executed. The Borrower in consultation with the Bank had provided appropriate responses and solutions to the problems which arose during the course of implementation. Coordination and efforts of all parties (Bank, Borrower, Contractors and Consultants) involved was effective which resulted in successful completion of the project. 4.1.2 The loan covenants /conditions were appropriate and valuable to the execution of the project. The success of the project itself is evidence that the loan conditions were sufficient and no more additional conditions were necessary. Since the new facilities included under the project were of utmost importance to the country’s economy, GOE took no time to fulfil the stipulated conditions. However, due to various factors indicated earlier coupled with additional works, have contributed significantly to delays in the completion of the project.

4.2 Operating Results Civil Works 4.2.1 The ADF financed components of the project were inspected after 2 years of its completion. During field inspection, it was noted that the completed new runway and its ancillary structures were well executed. The workmanship and overall quality of work executed by the contractor was good. 4.2.2 The completed New Runway is in good condition having a smooth riding surface with no distress or deformations. Proper vertical and horizontal alignments complying with the required design were provided with good drainage systems. The culverts and other drainage structures constructed along the runway are structurally sound with no signs of distress. At few locations along the runway, the aircraft guide path markings along the centreline were faded. Similarly, some deformations/ swellings were noted at some locations of the perimeter road.

4.2.3 The Mission advised GOE to take appropriate remedial measures in order to protect the

investment.

Traffic 4.2.4 Ethiopian Air Lines (EAL) dominates both domestic and international air transport services in Ethiopia. The international passengers carried between 1996 to 2004 shows an annual average market share of 82 % as against 65 % at appraisal. This is mainly due to the increase in the fleet of EAL, from 35 (15 were small planes) at appraisal to 47 (21 are small planes) at PCR. In addition, EAL is planning to have ten B -787 in the coming years. At present EAL renders services to 41 international and 24 domestic destinations with ten foreign carriers providing international services at Addis Ababa Airport.

8

4.2.5 A review of the recent passenger, cargo and aircraft movement traffic data for the year 1994 – 2005 revealed an overall growth in the passenger, cargo and aircraft movement in the country as shown in Table 4.1 and Annex 7 pages 2 and 4. The historical passenger, cargo and aircraft movement traffic of the Addis Ababa Bole International Airport was reviewed and used as a basis for traffic forecast and is presented in the following table.

Table 4.1 Actual and Forecast Passenger, Cargo and Aircraft Movement (1994 – 2019) Percentage Growth Rate

Actual International Passenger

Domestic Passenger

International Aircraft

Domestic Aircraft

General Aircraft

EAL Cargo

Foreign Cargo

1994 – 2002 6.8 2.0 5.3 1.1 12.6 -7.0 19.3 2003 -2005 21.8 8.8 13.3 8.7 9.5 32.3 - 20.0

Forecast

2006-2010 6 5 4 4 3 5 4 2011 - 2019 4 3 3 2 2 3 3

4.2.6 The actual traffic for the year 2005 when compared with the appraisal forecasts shows an increase of 13.8%, 13.9%, and 66.5% for international passengers, commercial international aircraft and general aircraft movement respectively. On the other hand, the domestic passengers, commercial domestic aircraft movement, EAL cargo and foreign carrier cargo have declined by 32.4 %, 25.6%, 66.4% and 49.2% respectively. The increase in the international passenger could be attributed to the increase in the EAL fleet as mentioned above. On the other hand the main reason for the decline in the domestic passenger and aircraft movement is due to the decrease in the EAL domestic destinations from 35 at appraisal to 24 at PCR. This is due to the phasing out of the old operationally uneconomical fleet, closure of non-profitable destinations and inability of some airports to accommodate FK 50 aircraft. The decline in cargo could be attributed to low growth of perishable cargoes in the early 2000 but is improving due to the increase in the private investors’ involvement in horticulture and livestock export. The increase of EAL cargo in 2003 -2005 could be attributed to the improvement in the export of horticulture and livestock to Middle East and Europe. The new cargo terminal and apron facilities (under construction), which are expected to be operational in 2007, would improve the situation further. 4.3 Institutional Performance 4.3.1 The Executing Agency at appraisal (in 1996) was the Civil Aviation Authority (CAA) which was under the Ministry of Transport and Communications until 2000 and after October 2005. In between this period of about 4 years, CAA was under the Ministry of Infrastructure. It was noted that the above changes of supervisory ministry, did not however affect the project implementation; the project was implemented and completed successfully by the same Authority, CAA. Towards the end of project completion, a major institutional restructuring of the civil aviation industry in Ethiopia took place with the re-establishment of CAA as Ethiopian Civil Aviation Authority (ECAA) retaining the regulatory and control functions and the subsequent establishment of the Ethiopian Airport Enterprise (EAE), which took over the commercial functions as a profit making organization. This is in line with the Government policy of separating the regulatory and commercial functions of the economic services sectors. Although these reforms are not direct fall-outs of the ADF project covenants, they accord with and are in furtherance of the sector goal and project objectives, which include the strengthening of CAA capacity as envisaged under the UNDP-ICAO technical assistance programme. Although these changes do not affect the project implementation, they are expected to positively influence the sustainability of the project achievements because the airport will now be run on a purely commercial basis to generate funds required for maintenance of the facility. EAE is in the process of re-engineering to meet its mandate by recruiting staff, implementing management structure and related systems.

9

4.3.2 The technical performance of Executing Agency was noted to be satisfactory as supported by the quality of works completed. The Project coordinator had performed his functions to the satisfaction of the Bank and the Executing Agency (CAA). Effective contact was established between the Bank, Executing Agency, Consultants as well as the Contractors. Accounting and Budgeting 4.3.3 The accounting system of ECAA still remain weak as observed at appraisal. The periodic accounting and management information reports needed for management to make important decisions were not prepared on a timely basis. Even when eventually produced, the figures often appear unreliable. This situation was clearly manifested on the draft annual accounts for the accounting periods 1999/2000 to 2003/2004 whereby the turnover shown thereon in no way reflects the actual performance of the authority. As for EAE, the accounting system also needs to be strengthened especially as this is a profit making organization. The enterprise presented two versions of accounts for the same period (year ended 7th July 2005) thus casting doubts on the reliability of some of the figures. Both ECAA and EAE as of the PCR were not maintaining fixed assets registers despite being required to do so at appraisal. The importance of the register cannot be overemphasized as these are required to safeguard the assets of the organization because it does not take long to lose sight of some assets unless records are kept. 4.3.4 The budgeting processes for ECAA being undertaken by the Air Transport and Planning Department appear adequate to meet the need of the organization. Notwithstanding, it is still necessary to harmonize the financial forecasts with the outputs of the Finance Department especially the historical and budgeted figures or projections. The EAE has also not been able to harmonise its financial budgeting with operations. In actual fact, the enterprise could only prepare budget for one year and had not projected for say five or ten years as would be expected for such an organization. There is thus the need to establish a budgeting and budgetary control system to provide appropriate tools for planning and control, and to train the appropriate personnel in the planning, finance and other departments in the application of those tools.

Auditing and Insurance 4.3.5 The audits of ECAA accounts were in arrears for six years, the latest audited accounts being for the year ended 7th July 1999. This contravenes the ECAA re-establishment proclamation, which requires the authority to maintain full and accurate accounts of its revenue and expenditures, and to submit duly audited accounts to the supervising ministry within a period of six months after the expiry of each fiscal year. It should be emphasized that ECAA must ensure proper accounting and audits for statutory compliance, transparency and accountability. 4.3.6 The accounts of EAE as well have not been audited since establishment of the enterprise. The draft accounts up to 7th July 2005 were however ready and the selection process for an audit firm just completed. EAE should also ensure strict compliance with the auditing requirements. 4.3.7 The assets of EAE namely the runway, terminal and vehicles were insured. The runway insurance in particular addresses the Bank’s concern at appraisal that ADF financed assets should be insured.

Billings and Collection

4.3.8 The concern expressed during appraisal regarding the need for effective billing and collection policy and procedures were yet to be addressed. The Finance Department of EAE responsible for billing and collection appears to operate a weak accounting and management information system coupled with poor credit control policy leading to accumulation of collectibles, which stood at ETB 508 million as at 7th July 2004 as against a total revenue of ETB 136 million for the year ended on that date. Unless drastic actions are taken, this could jeopardise the very existence of EAE.

10

Tariff Policy and Structure 4.3.9 The tariff policy and structure for the airside services remain substantial unchanged since project appraisal. One of the conditions precedent to entry into force of the ADF loan was the undertaking by the Borrower that airside tariffs will be adjusted in line with market trends not later than 30th June 1999 and will be continually adjusted thereafter to reflect the cost of providing services. GOE fulfilled this condition by submitting the appropriate letter of undertaking. However, the time for fulfilment of the undertaking had lapsed and GOE was yet to adjust the tariff as required. It was understood that EAE had, based upon a tariff study, submitted proposals tariff revision for GOE approval. Although the project had been completed since the year 2003, GOE was yet to give approval for tariff adjustment as proposed by EAE.

4.4 Management and Organisational Effectiveness 4.4.1 A slight modification was made to the established PIU by the way of introduction of the post of a Deputy Project Coordinator. This was necessitated by the volume of work involved on the various components of the project. Apart from the Project Coordinator and his Deputy, there were 15 other members of staff comprising 3 Civil Engineers, 2 Electrical Engineers, 1 Finance Officer, 2 Accountants, 2 Secretaries, 1 Clerical Officer and 4 support staff. Following the aviation industry reform, the PIU was eventually attached to EAE where the project would be closed and the staff re-assigned. The enterprise now has in place, a separate management structure for the management of the Addis Ababa International Airport as recommended in the appraisal report but with slight modifications. These reforms in the aviation industry have positive implications for the project sustainability. 4.4.2 At present, both ECAA and EAE are under the MOTAC. ECAA has seven departments, namely Air Transport & Planning, Human Resources & Property, Finance, Training, Aerodrome Engineering, Air Navigation and Flight Safety. EAE is functioning with seven departments, namely, manpower administration, finance, purchasing & property administration, airport engineering, corporate marketing, Addis Ababa International and Regional Airports. EAE is in the process of re-engineering to meet its mandate by recruiting staff, implementing management structure and related systems. Being a performance oriented semi-autonomous commercial organization; the enterprise will be managed by qualified staffs that have the required skilled personnel to implement its mandate.

4.5 Staff Recruitment, training and Development 4.5.1 Both the ECAA and EAE have established posts required to be filled in accordance with their respective organization structure. Apart from the key personnel inherited from the defunct CAA, EAE has been recruiting from the open market in order to fill established vacancies created as a result of its management structure. It is rather too early to start assessing the staff turnover as a measure of EAE’s ability to attract and retain personnel since the organization is still young and now in its third year of operation. As at 6th July 2005, there were 1,605 established positions (Head office 272, Addis Ababa Airport 503, and Regional offices 830) of which 741 had been filled. A manpower requirements plan is in place to fill the remaining vacancies over the next 5 years. At the moment the Enterprise is contracting out and out outsourcing some of the activities to private sector organizations in order to efficiently utilize the airport facilities. It is expected that EAE will base the exercise on a well-articulated and rational human capital strategy in which case the long-term viability would be assured. 4.5.2 ECAA’s in-house training program covers in Air Traffic Services, Aeronautical Radio Maintenance, Navigational Aid Maintenance, Aeronautical Information Service, Basic Fire Fighting, Computer Operation, Basic Aviation Security, Aviation Supervisory Management and Team Building Workshops. In addition, it also arranges foreign training and workshops in regulatory and air traffic services. EAE does not have training program for its employees but maintains a budget allocation for local and foreign studies. Although some of the training programmes are donor sponsored, it is advisable that these be monetized and reflected in the budgets. Furthermore, the budgetary allocations for those to be financed from ECAA and EAE own resources appear inadequate considering the enormous need to update the manpower skill in virtually all technical and non-technical areas.

11

4.6 Performance of Consultants, Contractors and Borrower Consultants (M/s Dar –Al Handasah of Lebanon & Transport Construction Design Enterprise, TCDE) of Ethiopia ) 4.6.1 The overall performance of the consultants, M/s Dar –Al Handasah (Lebanon) & TCDE (Ethiopia) were noted to be satisfactory and to the satisfaction of the Government and the Bank. The preliminary design review carried out on the original design (undertaken by a different consultant TAMS of USA), in particular on the black cotton soil as fill material and the pavement drainage aspects, have eliminated the potential risk of damage to the pavement structure. The consultant’s (M/s Dar Al- Handasah) efforts, especially the pre-tender design review of the contract services and modifications proposed to the pavement structure, were really to be commended. The improvements suggested to the original design that were carried out in the field was mainly to produce a project with high quality standards. The Resident Engineer conducted regular pavement field tests as stipulated in the contract documents to conform to the specified requirements before incorporation in the works. Constant supervision of project works was undertaken under operational conditions by the Project Coordinator of the PIU and the supervision consultants at every stage to maintain the quality of works. Adding to this, the Consultants were regular in submitting progress reports to the EA for review and onward transmission to the Bank. Good coordination existed through out the execution between the Consultants and the Contractors. There were no complaints or disputes during execution of the works. 4.6.2 The Executing Agency had maintained close working relationship with the selected supervising consultants during the course of the project implementation. Contractors ( M/s Kajima- Keangnam of Japan- S. Korea & M/s M.A. Al- Kharafi) 4.6.3 The contractors selected for the project components have been active in Africa with several years of experience and executed many similar projects in other countries. The technical performances of the contractors in the execution of works especially the quality and workmanship were satisfactory. The Borrower 4.6.4 The Loan Agreement was signed by the Borrower on 20 December 1996 and declared effective on 11 July 1997. The loan was signed 36 days after approval (maximum allowable 180 days) and declared effective 8 months after approval (maximum allowable 12 months). As such, there was no slippage either on the signature or on the effectiveness. The performance of the Borrower with regard to fulfilment of the loan conditions for the loan effectiveness was satisfactory. 4.6.5 The Borrower had submitted regularly the quarterly progress reports and annual audit reports to the Bank as stated in paragraph 3.4.2. In conclusion, the performance of the Borrower can be rated as satisfactory. 4.7 Conditions/Covenants The GOE took about 6 months to fulfil the stipulated conditions precedent to the entry into force of the Loan Agreement, from the date of loan signature to the loan effectiveness date of 7th July 1997. Regarding the condition on the undertaking for “adjustment of air tariffs not later than 30 June 1999 in line with market trends and thereafter to reflect the cost of services”, GOE was yet to fulfil the undertaking. As stated in paragraph 4.3.9 above, two years after project completion, the tariff approval was yet to be given in order to fully accomplish the loan condition. 4.8 Economic Performance 4.8.1 At appraisal, the implementation of the airside works of the Addis Ababa Airport Project economic justification was evaluated based on an assessment of net incremental benefits by comparing

12

“With” and “Without” the project scenarios. The analysis was conducted using January 1996 prices, assuming construction would commence in November 1996 and would last for 32 months period, being complete in May 1999. A seventeen years analysis period (1999-2015) and 20% residual value by the end of 2015 have been assumed. The economic costs included construction, supervision and maintenance costs while the benefits were based on three types namely, incremental foreign carrier user fees; domestic aircraft operation cost savings; and incremental foreign exchange earnings from tourism. Net economic benefits were calculated from 2015 and discounted to the base year 1996. Based on the economic costs and benefits, the resulting economic internal rate of return of the Addis Ababa Airport Project was estimated at 23.3%. 4.8.2 The estimates of project benefits at PCR were based on incremental foreign carrier user fees; domestic aircraft operation cost savings; and incremental foreign exchange earnings from tourism with projected traffic growth as presented under Table 4.1 above. Summary of Economic Analysis at PCR is attached as Annex 7 page 1 of 7. The analysis was conducted in economic terms, which was derived from the financial costs using the relevant conversion factors applicable to Ethiopia. The actual construction, supervision, maintenance economic costs and a 20% residual value as well as the benefits emanating from the revised traffic forecasts, formed the basis in the re-calculation of EIRR. The re-calculated EIRR is 30.5 % and Net Present Value (NPV) of US$31.7 million at 11% discount rate (Annex 7 page 7 of 7). This EIRR of 30.5 % (when compared with 23.3% at appraisal) is high mainly due to the traffic growth in the international passenger, international aircraft and general aircraft movement (as presented in para 4.2.6), 23.9 % reduction in the airside construction cost and capital cost disbursement over eight years period when compared to four years anticipated at appraisal. The EIRR at 30.5 % is well above the opportunity cost of capital of 11% in Ethiopia. 4.8.3 Other indirect economic benefits derived from the implementation of the Addis Ababa Airport Project are expanded foreign trade and other private business activity; air traffic safety and security, multiplier effect of tourism development through out the economy, accelerated human resource development and job creation in air transport. The number of tourist arrival is expected to grow by 74.5% between 2006 and 2019 and revenue attributed to the project to increase from USD 0.22 million to USD 6.68 million during the same period. Besides, the project has also benefited the ECAA/ EAE in the foreign exchange revenue generation. Given the Country’s land -locked context, plans are underway to develop it as a regional airport for hub traffic, to other destinations in Africa to promote regional integration. 4.9 Financial Performance 4.9.1 The project was evaluated at appraisal on a “net incremental cash flow” basis whereby airside revenue and expenditures expected to accrue were compared in with and without project scenarios. The appraisal analyses gave a financial internal rate of return (FIRR) of 23% for the airside investment, well above the prevailing opportunity cost of capital then 11% thus asserting the financial viability of the project. A comparison of the actual revenue and expenditure over a period of 10 years, covering the entire period of project implementation and thereafter, indicates that airside revenue estimates were in excess of actual revenue by an average of 12% per annum over the period. The projected expenses were above the actual performance, yielding average savings of about 56% per annum over the same period. Consequently, the actual financial results (margins) surpassed appraisal forecasts on the average by as much as 100% per annum. The comparison of the actual with estimated revenue and expenditure is presented in Annex 5. 4.9.2 A retrospective financial analysis based upon the resulting stream of cash flows also adopting with and without scenarios is presented in Annex 6. The retrospective financial internal rate of return is estimated to be 30%, which is well above the appraisal estimate of 23% and the current opportunity cost of capital of 11% in Ethiopia. This performance is accounted for by the increased cash flows resulting from better margins than envisaged at appraisal, savings on project cost and longer spread of disbursements. It must however be pointed out that these results should not be the sole yardstick for measuring the project achievement or even the good health of the responsible institution. As mentioned in paragraph 4.3.8 above, EAE continues to carry a huge pile of collectibles, which could wipe of the gains, if appropriate steps are not taken on debt recovery.

13

5. SOCIAL AND ENVIRONMENTAL IMPACT 5.1 Social Impact The project had improved the aviation sub sector of the country by strengthening the airport capacity to service the increased traffic and assist in the socio-economic development of the Country. The project has also created employment opportunities during construction. Due to the type of the project, which is mainly equipment intensive, only 980 employees were recruited during peak season and only about 10% of the employees were women. At present 20.5% and 26.2% of the employees of the ECAA and EAE respectively are women. 5.2 Environmental Impact 5.2.1 A detailed Environmental Impact Assessment ( EIA) Report for the overall project was carried out by the consultant as part of a feasibility study financed by the Bank. In accordance with Bank's environmental assessment guidelines, the project has been categorized as II. Environmental impacts at the existing Bole Airport site are incremental in an already urbanized area compared to developing an entirely new site in an undeveloped area, which would require a major landscape transformation and provision of new structure. The environmental impacts on various aspects viz: settlements, soils / geology, historic structures, construction operations, air quality, aircraft noise, bird strike, water supply and drainage have been studied in detail. The overall assessment of the study concluded that some negative impacts have been identified and appropriate mitigative measures have been proposed and incorporated in the project design. 5.2.2 During project implementation, the necessary measures for the negative impacts as a result of the rehabilitation have been mitigated by standard environmental engineering practice. Re-plantation of the appropriate indigenous plant for the disturbed areas, provision for continuing technical expertise in the form of a dedicated staff person to monitor and manage the bird-strike hazard from the perspective of bird-scaring have been done. Appropriate cross fall, side drains and culverts have been provided in preventing stagnations of water and thereby protecting the surface. Hydraulic techniques such as protective ditches, box and pipe culverts have been used so as to channel storm water across the runway, taxiways and perimeter road to nearby streams without any threat to erosion. Due to the improved technology of aircrafts (which have minimum noise level) the noise level has been substantially reduced. All borrow pits and quarry sites in all places have been properly restored in conformity with the surrounding landscape. 5.2.3 A security fencing of 8500 meters long with 2.10 meters high connected by horizontal and vertical galvanized pipes with cross bracings has been incorporated into the project and this helped significantly for operational safety of the airport. 6. PROJECT SUSTAINABILITY 6.1 The main project outputs namely the runway and taxiways of the Addis Ababa International Airport now fall under the direct responsibility of the Ethiopian Airport Enterprise, (EAE). This is as a result of the institutional reforms, which had resulted in the creation of EAE to take over the commercial functions of the defunct CAA as a fully profit making organization. The emerging scenario would no doubt aid the long term viability of the airport enterprise and positively influence the sustainability of the project achievements. Sustaining the project achievements would mean keeping these facilities in good working order on a sustainable basis. This would be predicated on two key factors namely:

i) availability of capacity and resources to undertake routine and periodic maintenance and repairs of the project assets, and ii) the long term viability of the responsible institution i.e. the EAE.

6.2 EAE has inherited some capacity for maintenance and repairs from CAA and is developing the programme for routine and periodic maintenance along with the budget for the required resources. It is expected that the capacity would be further develop to enable EAE undertake some small and

14

medium scale maintenance on its own while major repairs would be contracted out. The routine maintenance comprises i) Asphalt pavement maintenance and clearing of movement areas on an annual basis, and ii) Strip clearing and grass cutting, drainage clearing and embankment rehabilitation. The periodic maintenance on the other hand would cover i) Pavement marking every 2 years, ii) Asphalt wearing course every 5 years, and iii) Asphalt concrete overlay rehabilitation every 10 years. The routine maintenance budget, which comes to approximately ETB 0.50 million per annum for both tasks could be absorbed in the regular annual budget, while the 5-year periodic maintenance are expected to cost ETB 4.5 million each in 2008 and 2013 respectively for three tasks, and the 10 year periodic maintenance, ETB 43 million in 2012. These estimates have been included in the cash flow projections used for the retrospective rates of return computations. An analysis of the historical financial performance indicates that EAE would be able to finance the maintenance on a sustainable basis. 6.3 The long term sustainability of EAE would depend on the effectiveness of the management in maintaining sound financial management capacity, attracting and retaining highly qualified and efficient personnel and continuous update of its human capital through mandatory continuous education, internal and external training, workshops, seminars and conferences to ensure that they match world standards. A few questions were raised regarding the accounting practices at EAE especially the weakness of the accounting and management information reporting system, poor strategic planning especially inability to project the financials beyond one year’s budget, and poor credit control policy, which had resulted in accumulation of huge collectibles. The problem of customer debts if not squarely addressed to improve the organization’s cash flow, could jeopardize the long term viability of EAE and impair project sustainability. The implementation of the proposed tariff mentioned in para. 4.3.9 above is equally essential to ensure that the cash flows are sufficient to cover debt service, annual operating and maintenance expenses and return on investment. The sustainability of the project hinges on continued availability of financial resources. 7. PERFORMANCE OF THE BANK 7.1 The project was in line with the Borrower’s priorities and with the Bank’s policy and strategies for intervention in the sector. The Bank’s timely intervention facilitated the GOE to improve the country’s airport services both on international as well as domestic routes. 7.2 The Bank carried out regular desk monitoring and field supervision during implementation. The project was supervised with thirteen (13) field missions (2.00 Missions per year) until its completion during the implementation period, the first mission was in March 1998 and the last was in November 2004. In addition follow up missions from other departments also took place. Staff members of the Executing Agency benefited from the visiting Bank Missions by way of learning the operational and procurement procedures, thereby enhancing their efficiency. 7.3 The Bank adhered to the agreed procurement schedule at appraisal. However, the slippages during implementation were caused mainly due to other factors stated in the earlier sections. 7.4 The processing of loan documents and disbursement applications were handled within the guidelines of the Disbursement manual. From the perspective of the Borrower, it appears that in general, there were some delays from the Bank in the release of payments to the contractors, mainly due to relocation of the Bank’s headquarters to Tunis and error in apportioning currencies for payment to contractors. Timely advice was given by the Bank to the Borrower to solve the problems regarding disbursements. 7.5 Overall, the performance of the Bank is judged satisfactory. 8. OVERALL PERFORMANCE AND RATING Assessment of Overall Project

8.1 The new facilities at Addis Ababa International Airport, which include the airside (runway with taxiways, the Air Traffic Control Tower with associated communications, navigation aid and power supply

15

systems) and the landside services (new International Passenger Terminal and related facilities), meet ICAO standards. The constructed new runway facilitated rapid clearing of aircraft movements and reduced the runway occupancy time. With the provision of new approach lighting system for the runway, taxiway and aprons, EAL switched over most of its daytime operations to night, thus facilitating easy connections to various destinations. The new rigid (concrete) apron of 70,000 sq. mt. (capable of accommodating the heavier aircraft of B747-400 series) provided parking space for additional aircrafts, apart from relieving the congestion during peak hour operations, apart from minimizing the parking time. The new Air Traffic Control Tower building equipped with the latest technology of Navaids communications systems, meteorological equipment and console systems, have been found very effective for safer air traffic operations. 8.2 The new International Passenger Terminal which has an area of 40,000 sq.mt with the latest airport terminal conveyance system can accommodate up to 3000 passengers per hour. The new safety features at the airport include automatic alarm, emergency exit announcement system and automatic emergency exit activation facility. The new terminal has provided entrance facilities for visitors who used to wait outside due to limited space in the old terminal. This increased the earnings of EAE from non-aeronautical revenues on visitors’ entrance fee. Similarly, with the provision of vehicle parking area, shops, cafeteria and office facilities for carriers, the EAE has been earning additional revenue. Operational wise, office support areas for Government inspection facilities, namely, ECAA, Customs, Immigration and Security have been improved. The old international terminal has been refurbished to handle domestic operations.

8.3 The impact of the overall project is being felt mainly in the areas of tourism and export trade through the expansion of air transport service and provision of modern facilities, which has made the country more competitive in the international aviation business. Performance Rating of the Bank Financed Package 8.4 In accordance with the implementation performance indicators (Annex 8), the overall assessment of implementation performance of the Bank financed package is satisfactory with a rating of 2.6 out of 4 maximum. The rating for the Bank's performance is 2.67 out of 4 maximum indicating satisfactory while the rating for the project outcome is satisfactory with a rating of 2.9 out of 4 maximum. In general, the overall performance of the project is satisfactory.

9. CONCLUSIONS, LESSONS LEARNT AND RECOMMENDATIONS 9.1 Conclusions 9.1.1 The overall objectives of the project have been fully achieved. Proper and timely co-ordination of the Bank and the Borrower coupled with effective supervision by the Consultants and good workmanship of the contractors made the project a successful one. The additional facilities provided at the Addis Ababa Airport with a new runway and its ancillary structures, significantly improved the air transport services both on international and domestic air transport services. The constructed new runway has a good riding smooth surface, was found to be safe in landing and taking off operations, and was environmentally protected. The value and quality of the project was greatly enhanced despite some delays during the project implementation. 9.1.2 There was a cost under-run of UA 4.38 million for the project as a whole. An amount of UA 2.368 million realized as savings under ADF loan was cancelled by the Bank in March 2005 (paras 3.6.2 and 3.6.3). 9.1.3 It was observed that GOE had to incur extra expenditure for some delays by the Bank on the disbursements, mainly due to (i) relocation of the Headquarters temporarily to Tunis, and (ii) wrong apportionment of currencies under the contract by the Bank for its share of foreign currency payments (para 3.6.5). 9.1.4 GOE made adequate budgetary allocations and fulfilled its obligations concerning counterpart funding without delay (para 3.6.5).

16

9.1.5 A number of key observations made during appraisal including poor accounting system, poor

billing and collection, and non- keeping of fixed assets register, which highlight major weaknesses in the accounting and management practices of the EA appear not to have been followed up during negotiation. A requirement for overhauling of the accounting and management practices of the EA would have removed some of these weaknesses, which may threaten the long-term stability of the EA (EAE) and by extension, the project sustainability (para 4.3.3). 9.1.6 The accounts of EAs are normally required to be audited annually under the statutes establishing such agencies, while in addition, the Bank requires separate audit of project accounts. However, it was noted that the accounts of ECAA were in arrears for six years and those of EAE for three years (paras 4.3.5 and 4.3.6). 9.1.7 The undertaking given by the Borrower as part of the loan conditions, which stipulated that the airside tariffs should be adjusted in line with market trends and continuously adjusted thereafter to reflect cost of providing services, was yet to be implemented two years after project completion (paras 4.3.9 and 4.7.1). 9.1.8 A pre-design review (before issue of tenders) and modifications, which suggested the use of non-swelling soil instead of black cotton soil and vertical trenching method for drainage of subsoil water under the pavement, had minimised the potential risk of damage to the runway pavement. Even though, the project construction start up was delayed due to the above modifications, the project was implemented and completed successfully with no major problems and the new facilities, which are under use, have benefited the country globally (para 4.6.1). 9.1.9 The performances of the Contractors, Consultants and the Borrower were satisfactory. As a result, the overall implementation of the project was adjudged satisfactory with a rating of 2.6 out of 4 (maximum) (paras 4.6.1 to 4.6.5).

9.1.10 The constructed new facilities at the airport are in good condition with no distress and with a smooth riding surface, except few local settlements at some places on the perimeter road, as indicated in earlier sections. The re-calculated EIRR and FIRR at PCR in respect of the airside components are 30.5 % and 30 % respectively, which are well above the opportunity cost of 11% in Ethiopia (paras 4.8.2 and 4.9.2).

9.1.11 The routine and periodic maintenance of the project facilities will not pose a problem as the financial analysis indicate that EAE would be able to finance from its own resources on a sustainable basis (para 6.2). 9.2 Lessons Learnt 9.2.1 The lessons learnt from the project are given hereunder:

• The time period given for execution of works (24 months in this case) under working conditions of an operational airport appear to be un-practicable. A realistic time period taking into consideration the nature of works and the operational working conditions should have been allowed for execution of works of such complex nature (para 3.3.3);

• Adequate attention is necessary by the concerned disbursement officers of the Bank when apportioning currencies of payments to the concerned parties, before effecting the disbursements (para 3.6.4);

• The Bank ought to have followed up some of the weaknesses observed at appraisal, in accounting and management practices of the EA, during negotiation to obtain an undertaking from the Borrower to strengthen those weaknesses. (paras 4.3.3 and 4.3.8);

• The non-audit of financial statements of EAs also borders of non-compliance with local laws. The Bank ought to have ensured submission of the EAs audited accounts at the same time the project’s audited accounts were being submitted (paras 4.3.5 and 4.3.6);

17

• In order to protect the investment, the tariff revision is important. GOE should therefore expedite approval of the recommendations of the tariff proposed by EAE for implementation without further delay (paras 4.3.9 and 4.7.1); and

• A pre-design review (before issue of tender bids) by the selected consultant (if different from the original detailed design consultant) before launching the bids is always preferable, as this would bring out the deficiencies if any, in the original design and at the same time avoid modifications (involving additional costs) during execution. In the case at hand, though there was an initial delay in the start up of the project construction due to pre-design review; this proved to be effective in the review of design deficiencies at the early stages and elimination of the unexpected risks and difficulties. The project was executed and completed successfully with no modifications during the execution stage. It is understood that this is now being followed for all Bank financed projects. (para 4.6.1)

9.3 Recommendations

9.3.1 It is recommended that:

For the Borrower

• For execution of projects of similar nature (in particular under operational conditions), Borrowers should review and assess the time period required for completion in order to minimise time extensions and additional payments (para 3.3.3);

• Rectify the defects observed during the field inspection of the completed project (Para. 4.2.2); • GOE should ensure strengthening of the financial management capacity of ECAA and EAE.

Specifically, the introduction of fixed assets register, aggressive debt collection, and preparation of periodic accounts on a timely basis should receive immediate attention (para 4.3.3);

• GOE to ensure that the audit of financial statements of ECAA and EAE are undertaken firstly to clear the backlog and thereafter on a regular annual basis to ensure that they do not fall into arrears again in the future (paras 4.3.5 and 4.3.6); and

• GOE should fulfil its undertaking given as one of the conditions precedent to first disbursement, that tariffs will be adjusted in line with market trend. Priority should be accorded to the approval and implementation of the revised tariffs proposed by EAE (paras 4.3.9 and 4.7.1).

For the Bank

• Bank should be more practical in examining and specifying realistic time period required (during appraisal stage) for execution of projects of similar nature (in particular under operational conditions) (para 3.3.3);

• Adequate care should be exercised in making entries concerning apportionment of currencies especially at the contract entry into SAP. (para 3.6.4);

• Future Bank operations should not only look at the financial management capacity and health of EAs, but also ensure where appropriate, insertion of clauses requiring that observed weaknesses in the accounting and management practices are strengthened to safeguard Bank’s investment. (para 4.3.3);

• Future Bank operations should ensure as a matter of routine, the enforcement of submission of audit reports of both the EA and project on timely basis. (paras 4.3.5 and 4.3.6);

• Bank to follow up with the GOE on the fulfillment of the undertaking on tariff adjustments given as part of the loan conditions. ( paras 4.3.9 and 4.7.1);

• The problems surrounding the non-fulfilment of loan conditions, weaknesses in financial and management practices of ECAA and EAE, non-audit of accounts should be taken up as issues for future policy dialogue with GOE; and

• The Bank should develop appropriate response to future similar laxities and non-fulfilment of loan conditions by Borrowers.

A matrix of recommendations is presented in Annex 9.

Annex 1

ETHIOPIA ADDIS ABABA

INTERNATIONAL AIRPORT DEVELOPMENT PROJECT GENERAL / PROJECT LOCATION MAP

This map has been drawn by African Development Bank Group exclusively for the use of the readers of the report to which it is attached. The names used and the broidery shown do not imply on the part of the Bank and its members any judgement concerning the legal status of a territory not any approval or acceptation of these borders.

Annex 2 Page 1

Annex 2 Page 2

Annex 2 Page 2

Annex 2 Page 3

Annex 3 Page 1 of 5

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT PROJECT COMPLETION REPORT

OVERALL PROJECT COST ESTIMATES BY COMPONENTS

(APPRAISAL VS ACTUAL) (UA million)

Appraisal Estimates Actual Cost Components

F.E L.C. Total F.E L.C. Total A. Civil Works for: (i) New runway, five exit taxiways airfield drainage, top soiling security fencing & perimeter road.

16.28 5.00 21.28 15.31 5.87 21.18

(ii) Consultancy services for:

- Supervision of works 0.95 0.12 1.07 1.83 1.83 - Audit of civil works 0.04 - 0.04 0.01 - 0.01

“A” sub total 17.27 5.12 22.39 15.32 7.70 23.01 B. Supply, Installation and Commissioning of:

(i) Airside equipment, Navaid communication & airfield lighting systems.

8.55 0.46 9.01 3.97 0.65 4.61

(ii) Consultancy Services for Supervision. 0.43 0.02 0.45 0.51 - 0.51 “B” sub Total 8.98 0.48 9.46 4.47 0.65 5.12 C. Construction Works for (i) New rigid apron and Total Rehabilitation of an old taxiway "C" to the level of the Apron

3.86 0.69 4.55 4.54 0.50 5.04

(ii) Consultancy services for supervision 0.19 0.03 0.22 0.25 0.01 0.26

C” sub-Total 4.05 0.72 4.77 4.79 0.51 5.31 D. Construction Works for (i) Strengthening of existing pavement (overlays)

- 4.54 4.54 1.82 1.06 2.88

(ii) Consultancy services for supervision - 0.22 0.22 - 0.10 0.10 “D” Sub-Total - 4.76 4.76 1.82 1.16 2.98 E. Cost and support of PIU 0.34 - 0.34 - 0.18 0.18 Sub Total A to E 30.64 11.08 41.72 26.40 10.19 36.59 Contingencies: - Physical (10%) 2.88 1.06 3.94 - Price 2.23 1.66 3.89 GRAND TOTAL 35.75 13.80 49.55 26.40 10.19 36.59 Percentage 72.15 27.85 100.00 72.14 27.86 100.00 Source: ECAA and ADB Mission, January 2006

Annex 3 Page 2 of 5

ETHIOPIA ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

OVERALL PROJECT COST ESTIMATES (COMPONENT and SOURCE) (APPRAISAL VS ACTUAL)

(UA million)

Component/Source ADF EIB Kuwait Fund/BADEA & OPEC Fund UNDP GOE Total

Appraisal Actual Appraisal Actual Appraisal Actual Appraisal Actual Appraisal Actual Appraisal Actual Difference

A. Civil Works (i) New runway, five exit taxiways airfield drainage, top soiling security fencing & perimeter road 19.46 15.31 - - - - - - 6.60

5.87 26.06 21.18 4.88

(ii) Consultancy Services for: - -

- Supervision of Works - - - - - - - 1.15

1.83 1.15 1.83 (0.68)

- Audit of Civil Works 0.04 0.01 - - - - - - - - 0.04 0.01 0.03

B. Supply, Installation and Commissioning of: - - (I.) Airside Equipment, and airfield lighting & Navaid comm. Systems - - 9.85

3.97 - - - 0.51

0.65 10.36 4.61 5.75

(ii.) Consultancy services for supervision - - 0.43 0.51 - - - 0.02

- 0.45 0.51 (0.06)

C. Construction works for: - - (I.) New rigid apron and Total Rehabilitation of an old taxiway "C" to the level of the Apron - - - 4.44

4.54 - - 0.81

0.50 5.25 5.04 0.21

(ii.) Consultancy services for supervision - - - 0.19 0.25 - - 0.03

0.01 0.22 0.26 (0.04)

D. Construction works for: - - (I.) Strengthening existing pavements (overlays) - 1.82 - - - 5.46 1.06 5.46 2.88 2.58 (ii.) Consultancy services for supervision - - - - - 0.22 0.10 0.22 0.10 0.12

E. Institutional support to PMU - - - 0.34 0.18 0.34 0.18 0.16

- -

TOTAL 19.50 17.13 10.28 4.47 4.63 4.79 0.34 0.18 14.80 10.38 49.55 36.59 12.96 Source: ECAA and ADB Mission, January 2006

Annex 3 Page 3 of 5

ETHIOPIA

Addis Ababa International Airport Development Project Project Completion Report (PCR)

Summary of Project Costs Works Packages WP I and WP IA (ADF + GOE financed Components) : Appraisal/Modified Vs Actual

(UA million, net of Taxes)

At Appraisal As Modified Actual Foreign

Exchange Local Cost

Total

%

Foreign Exchange

Local Cost

Total

%

Foreign Exchange

Local Cost

Total

%

A. Civil Works for:

(i) New Runway with five taxiways airfield drainage, top soiling, security fencing & perimeter road. (ii) Strengthening of existing taxiways(overlays)

16.28

-

5.00

4.54

21.28

4.54

14.38

2.57

5.00

1.97

19.38

4.54

15.307

1.821

5.867

1.243

21.174

3.064

B. Consultancy Supn. Services for:

• Works at item A (i) • Works at item A (ii)

1.00

-

0.07

0.22

1.07

0.22

1.00

-

0.07

0.22

1.07

0.22

1.087

-

0.570

0.083

1.657

0.083

C. Audit of Civil Works

0.004 - 0.004 0.01 - 0.01 0.004 - 0.004

Unallocated (Phys.& Price Contingencies)

3.18 2.60 5.78 2.54 2.60 5.14

TOTAL 20.50 12.43 32.93 100.0 20.50 9.86 30.36 100.0 18.219 7.763 25.982 100.0 Source: ECAA and ADB Mission, January 2006.

Annex 3 Page 4 of 5

ETHIOPIA

Addis Ababa International Airport Development Project Project Completion Report (PCR)

Actual Project Costs (Component and Source)

(UA million, net of Taxes)

ADF GOE Total Foreign

Exchange Local Cost

Total

%

Foreign Exchange

Local Cost

Total

%

Foreign Exchange

Local Cost

Total

%

A. Civil Works for:

(i) New Runway with five taxiways airfield drainage, top soiling, security fencing & perimeter road. (ii) Strengthening of existing taxiways(overlays)

15.307

1.821

-

-

15.307

1.821

89.3

10.6

-

-

5.867

1.243

5.867

1.243

66.3

14.1

15.307

1.821

5.867

1.243

21.174

3.064

81.5

11.8

B. Consultancy Supn. Services for:

• Works at item A (i) • Works at item A (ii)

-

-

-

-

-

-

1.087

-

0.570

0.083

1.657

0.083

18.7

0.9

1.087

-

0.570

0.083

1.657

0.083

6.4

0.3

C. Audit of Civil Works

0.004 0.004 0.1 - - 0.004 - 0.004 -

TOTAL 17.132 - 17.132 100.0 1.087 7.763 8.850 100.0 18.219 7.763 25.982 100.0 Source: ECAA and ADB Mission, January 2006.

Annex 3 Page 5 of 5 ETHIOPIA

Addis Ababa International Airport Development Project

Project Completion Report (PCR)

Categories of Expenditure Works Package WP I ( ADF Financed Components) at Appraisal / Modified Vs Actual (UA million, Net of Taxes)

At Appraisal As Modified Actual Components

F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total

A. Civil Works for: (i) New Runway, 5 taxiways airfield drainage, top soiling, security fencing and perimeter road.

(ii) Strengthening of existing runway taxiways(overlays)

16.28

-

5.00

-

21.28

-

14.38

2.57

5.00

-

19.38

2.57

15.307

1.821

5.867

1.243

21.174

3.064

B. Consultancy Services for • Audit of Civil Works

0.04

-

0.04

0.01

-

0.01

0.004

-

0.004

Un- allocated (Physical & Price contingencies)

3.18

1.60

4.78

2.54

1.60

4.14

-

-

-

TOTAL 19.50 6.60 26.10 19.50 6.60 26.10 17.132 7.110 24.242 Source: ECAA and ADB Mission, January 2006

Annex 4

Page 1 of 2

ETHIOPIA

Addis Ababa International Airport Development Project

PROJECT COMPLETION REPORT

YEARLY DISBURSEMENT BY SOURCE OF FUNDS (In UA MILLION)

ADF GOE TOTAL ( ADF+GOE)

As at Appraisal Actual As at Appraisal Actual As at Appraisal Actual Year

Amount Cum.(%) Amount Cum.(%) Amount Cum.(%) Amount Com.(%) Amount Cum.(%) Amount Cum.(%) 1996

3.90 20 - - 1.55 11.5 - - 5.45 16.6 - -

1997

9.75 70 1.412 8.3 4.76 46.9 0.602 8.5 14.51 60.6 2.014 8.3

1998

5.85 100 1.306 15.9 6.24 93.5 0.861 20.6 12.09 97.3 2.167 17.2

1999

- - 3.730 37.6 0.88 100 1.080 35.7 0.88 100 4.810 37.1

2000 - - 5.342 68.8 - - 2.074 64.9 7.416 67.7

2001 - - 2.446 83.1 - - 0.844 76.8 3.290 81.3

2002 - - 0.721 87.3 - - 0.406 82.5 1.127 85.9

2003 - - 1.369 95.3 - - 1.078 97.7 2.447 96.0

2004 - - 0.806 100 - 0.165 100 100 0.971 100

Total 19.50 100.0 17.132 100.0 13.43 100.0 7.110 100.00 32.93 100.0 24.242 100.0

Source: ECAA and ADB Mission, January 2006

Annex 4

Page 2 of 2

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT (PCR)

ADF DISBURSEMENT SCHEDULE (APPRAISAL VS ACTUAL) (UA Million)

Year

Appraisal Actual

Amount Cum. (%) Amount Cum. (%)

1996 1997 1998 1999 2000 2001 2002 2003 2004

3.90 9.75 5.85

- - - - - -

20.0 70.0 100.0

- - - - - -

-

1.412 1.306 3.730 5.342 2.446 0.721 1.369 0.806

-

8.3 15.9 37.6 68.8 83.1 87.3 95.3 100.0

Total

19.50 100.0 17.132 100.0

Un-disbursed Loan Balance Cancelled

2.368

Source: FFCO and ADB Mission, January 2006

Annex 5

ETHIOPIA ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

COMPARISON OF ACTUAL WITH PROJECT REVENUE AND EXPENDITURE (Million Birr)

2005 2004 2003 2002 2001 2000 1999 1998 1997 1996Revenue - Actual 132.471 122.634 119.7 96.75 85.86 92.7 73.44 80.955 56.259 63.12 - Projected 133.21 121 122.81 115.21 108.13 101.17 94.52 88.18 82.38 70.55Difference 0.739 -1.634 3.11 18.46 22.27 8.47 21.08 7.225 26.121 7.43

% 0.55 -1.35 2.53 16.02 20.60 8.37 22.30 8.19 31.71 10.53Expenditure - Actual 50.73 42.655 41.705 30.59 32.87 28.12 21.3465 23.218 19.08 19.47 - Projected 73.77 72.39 72.23 72.92 72.34 71.73 72.08 71.44 64.91 53.39Difference 23.04 29.735 30.525 42.33 39.47 43.61 50.7335 48.222 45.83 33.92

Excess/Savings % 31.23 41.08 42.26 58.05 54.56 60.80 70.38 67.50 70.61 63.53Result - Actual 81.741 79.979 77.995 66.16 52.99 64.58 52.0935 57.737 37.179 43.65 - Projected 59.44 48.61 50.58 42.29 35.79 29.44 22.44 16.74 17.47 17.16Difference 22.301 31.369 27.415 23.87 17.2 35.14 29.6535 40.997 19.709 26.49

% 37.52 64.53 54.20 56.44 48.06 119.36 132.15 244.90 112.82 154.37

Annex 6 Page 1 of 2

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

NOTES AND ASSUMPTIONS UNDERLYING FINANCIAL ANALYSIS The financial analysis are based upon a retrospective review of the Appraisal assumption with the following major variations and additions.

• The fiscal year 1996 has been assumed the revised base year since project implementation commenced in 1997. Accordingly, 1996 forecast and actual streams of cash flow are excluded;

• The capital costs under “with project” scenario are included at the actual amounts of airside, while the capital cost on major rehabilitation for the “without project” scenario are reflected as at appraisal estimate but now spear over two years as against one year rehabilitation period stated at appraisal. This is because experience during implementation had shown that construction is often delayed under an operating airport environment;

• The streams of cash flow for revenue and expenses are actual from 1997 up to 2005 under the “with project” scenario;

• The revenue and expenses for the “without project” scenario took account of the delayed commencement, hence the “with and without” project revenue and expenditures for the pre-completion years are assumed to be same;

• The revenue and expenses as from 2003 are projected up to 2017 based upon the revised trends for 1997 to 2002 under the “without project” scenario;

• The revenue and expenses as from 2006 are projected up to 2017 based upon the actual trends for 1997 to 2005 under the “with project” scenario;

• Repairs and maintenance expenses under “without project” scenario are retained as projected at appraisal;

• Repairs and maintenance expenses under “with project” scenario are based upon estimates obtained from EAE for routine and periodic maintenance;

• The residual value of investment is assumed to be 2005 of capital cost and added to the cash flow in the year 2017.

Annex 6

Page 2 of 2

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

COMPUTATION OF INTERNAL FINANCIAL RATE OF RETURN

WITH PROJECT SCENARIO WITHOUT PROJECT

SCENARIO Year Revenue Expenses Investment Revenue Expenses Investment

Net Incremental

Benefits 1997 56.26 19.08 5.60 33.76 13.36 11.181998 80.96 23.22 30.06 48.57 16.25 -4.651999 73.44 21.35 40.04 44.06 14.94 -17.062000 92.70 28.12 96.30 55.62 19.68 50.67 -16.982001 85.86 32.87 73.27 51.52 23.01 50.67 1.892002 96.75 30.59 46.40 58.05 21.41 -16.872003 119.70 41.71 45.98 71.82 29.19 -10.612004 122.63 42.66 9.03 85.84 29.86 14.962005 132.47 50.73 10.16 92.73 35.51 14.362006 140.08 58.50 98.05 40.95 24.472007 143.58 61.43 100.50 43.00 24.652008 147.17 64.50 4.5 103.02 45.15 46.57 66.872009 150.85 67.72 105.59 47.41 24.942010 154.62 71.11 108.23 49.78 25.052011 158.48 74.66 110.94 52.26 25.152012 162.45 78.40 43 113.71 54.88 -17.792013 166.51 82.32 4.5 116.55 57.62 20.762014 170.67 86.43 119.47 60.50 25.272015 174.94 90.75 122.46 63.53 25.252016 179.20 95.29 -71.37 125.44 66.70 46.57 143.11

FIRR 30%

Annex 7 Page 1 of 7

ETHIOPIA ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

SUMMARY OF ECONOMIC ANALYSIS AT PCR 1 The methodology adopted at appraisal has been used in the re-calculation of the EIRR at PCR. The implementation of the airside works of the Addis Ababa Airport Project has created incremental benefits for the existing and generated traffic, as a consequence of decrease in air traffic control delays and on ground in-out taxi times resulting in aircraft operating cost savings. The Ethiopian economy gains from the incremental revenue from the payment of a variety of landing fees, apron fees, navigation fees etc. both for the existing and generated foreign carrier traffic. At appraisal, these economic benefits for Ethiopia on incremental basis have been estimated at 80% of incremental aircraft operating costs savings accruing to foreign airlines as a result of the project, which can be captured in terms of incremental airside user fees. This assumption has been considered in the recalculation in the PCR and projected to grow from USD 0.52 million in 2003 to USD 1.55 million in year 2019. 2 A review of the 1996 to 2004 historical traffic data shows that EAL accounts for 82% of the international passenger and 100% of the airport's domestic commercial traffic. From the perspective of economic analysis, the benefits created by the project on the airside for EAL are aircraft operating cost savings on existing and generated traffic throughout the project period as a result of reduction in congestion and other efficiency associated with the new facility. These benefits, resulting from decreased in-air traffic control delays and on-ground in - out taxi times for the existing and generated traffic are estimated by comparing operating costs per aircraft movement, with and without the project. Total Domestic Aircraft operating cost savings are estimated to increase from USD 5.14 million in 2003 to USD 14.65 million in 2019. 3 The project in addition generated incremental foreign exchange earnings from tourism. Based on historical tourist arrival information, future tourist arrival with and without the project scenario have been estimated (Annex 7 page 6 of 7). Like appraisal, receipts per tourist stay of USD 487 and import content of 40% were assumed. Because tourism development is an indirect benefit, as well as a joint benefit among several sectors, about 10% of the incremental benefit from tourism is attributed to the project and is projected to increase from USD 0.22 million in year 2006 to USD 6.68 million in 2019.

4. Based on the historical annual traffic growth rates, the international passenger, domestic passenger,

international aircraft, domestic aircraft, general aviation, EAL and foreign carrier cargo are projected to grow at an average annual growth rate as presented below.

Percentage Growth Rate

Forecast International Passenger

DomesticPassenger

InternationalAircraft

DomesticAircraft

General Aircraft

EAL Cargo

Foreign Cargo

2006-2010 6 5 4 4 3 5 4 2011 - 2019 4 3 3 2 2 3 3

5. The economic analysis was conducted by converting the financial costs into economic terms by applying

relevant conversion factors applicable in Ethiopia. The actual construction, supervision and maintenance economic costs as well as the benefits mentioned above emanating from the revised traffic forecasts and a 20 % residual value formed the basis for re-evaluation of EIRR.

6. The EIRR of the investment in the Airside works of the Addis Ababa Airport is computed based on the

streams of incremental costs and benefits (Annex 7 page 7 of 7). The computation has been done under a "With" and “Without” scenarios, recognizing that an array of infrastructural improvements had to be undertaken to maintain operations at the airport at some minimum acceptable level of safety under the " Without” Project scenario. The recalculated EIRR is 30.5 % and NPV of US$31.7 million at 11% discount rate. This EIRR of 30.5 % (when compared with 23.3% at appraisal) is high mainly due to the traffic growth in the international passenger, aircraft and general aircraft movement (as presented in para 4.2.6), 23.9 % reduction in the airside construction cost and capital cost disbursement over eight years period as compared to four years anticipated at appraisal. This EIRR of 30.5 % is well above the opportunity cost of capital of 11% in Ethiopia.

ETHIOPIA Annex 7

Page 3 of 7 ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT (PCR)

TRAFFIC ANALYSIS FORECAST PASSENGER TRAFFIC 2006 - 2019 PASSENGER MOVEMENTS

Year International Domestic Total

1994 625,794 217,464 843,258

1995 642,107 231,928 874,035

1996 645,000 217,895 862,895

1997 695,210 275,919 971,129

1998 612,899 292,567 905,466

1999 712,445 227,966 940,411

2000 795,323 242,653 1,037,976

2001 848,776 247,829 1,096,605

2002 987,714 250,144 1,237,858

2003 1,068,058 246,682 1,314,740

2004 1,296,850 276,480 1,573,330

2005 1,585,023 291,801 1,876,824

2006 1,680,124 306,391 1,986,515

2007 1,780,932 321,711 2,102,642

2008 1,887,788 337,796 2,225,584

2009 2,001,055 354,686 2,355,741

2010 2,121,118 372,420 2,493,539

2011 2,205,963 383,593 2,589,556

2012 2,294,202 395,101 2,689,302

2013 2,385,970 406,954 2,792,923

2014 2,481,408 419,162 2,900,571

2015 2,580,665 431,737 3,012,402

2016 2,683,891 444,689 3,128,581

2017 2,791,247 458,030 3,249,277

2018 2,902,897 471,771 3,374,668

2019 3,019,013 485,924 3,504,937

Note : 1995 to 2004 figures are actual and 2005 is estimation based on 10 months actual.

Source: ECAA, EAE and ADB PCR Mission, January 2006

ETHIOPIA Annex 7 Page 4 of 7 ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT (PCR) TRAFFIC ANA FORECAST CARGO TRAFFIC 2006 - 2019

Ethiopian Foreign TONS

Year Airlines Airlines Total

1994 30,143 1,587 31,730

1995 32,395 1,736 34,131

1996 28,562 4,116 32,678

1997 30,626 5,035 35,661

1998 30,924 3,591 34,515

1999 25,249 4,201 29,450

2000 23,206 4,539 27,745

2001 23,449 4,195 27,644

2002 19,131 3,633 22,764

2003 18,126 2,442 20,568

2004 23,748 1,585 25,333

2005 31,694 1,507 33,201

2006 33,279 1,567 34,846

2007 34,943 1,630 36,573

2008 36,690 1,695 38,385

2009 38,524 1,763 40,287

2010 40,450 1,833 42,284

2011 41,664 1,889 43,552

2012 42,914 1,945 44,859

2013 44,201 2,004 46,205

2014 45,527 2,064 47,591

2015 46,893 2,126 49,019

2016 48,300 2,189 50,489

2017 49,749 2,255 52,004

2018 51,241 2,323 53,564

2019 52,779 2,392 55,171

%age growth

1994 -02 -7.0 19.3

2003-05 32.3 -20.0

Note : 1994 to 2004 figures are actual and 2005 is estimation based on 10 months actual. Source: ECAA, EAE and ADB PCR Mission, January 2006

Annex 7Page 5 of 7

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT PROJECT COMPLETION REPORT (PCR) TRAFFIC ANALYSISFORECAST AIRCRAFT MOVEMENT 2006 - 2019

General Total Commercial Aircraft Aviation Total Movements Aircraft Aircraft

Year International Domestic Total Commercial Movements Movements1994 7,308 6,412 13,720 6,243 19,963 1995 7,559 6,910 14,469 6,335 20,804 1996 7,364 6,827 14,191 8,005 22,196 1997 8,112 8,214 16,326 9,443 25,769 1998 7,633 8,016 15,649 7,594 23,243 1999 8,133 6,836 14,969 7,072 22,041 2000 8,748 7,521 16,269 10,146 26,415 2001 9,609 7,253 16,862 10,574 27,436 2002 10,741 7,175 17,916 12,937 30,853 2003 11,380 7,086 18,466 14,893 33,359 2004 13,515 7,621 21,136 16,707 37,843 2005 14,572 8,373 22,945 17,847 40,792 2006 15,155 8,708 23,863 18,382 42,245 2007 15,761 9,056 24,817 18,934 43,751 2008 16,392 9,418 25,810 19,502 45,312 2009 17,047 9,795 26,842 20,087 46,929 2010 17,729 10,187 27,916 20,690 48,606 2011 18,261 10,391 28,652 21,103 49,755 2012 18,809 10,599 29,407 21,525 50,933 2013 19,373 10,811 30,184 21,956 52,140 2014 19,954 11,027 30,981 22,395 53,376 2015 20,553 11,247 31,800 22,843 54,643 2016 21,169 11,472 32,642 23,300 55,941 2017 21,805 11,702 33,506 23,766 57,272 2018 22,459 11,936 34,394 24,241 58,636 2019 23,132 12,174 35,307 24,726 60,033

Note : 1995 to 2004 figures are actual and 2005 is estimation basedon10 months actualSource: ECAA, EAE and ADB PCR Mission, January 2006

ETHIOPIA

Annex 7Page 6 of 7

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT PROJECT COMPLETION REPORT (PCR)TOURIST ARRIVALS AND FORECAST

Year No of Tourists Year No of Tourists1990 79,346 2005 222,600 1991 81,581 2006 235,956 1992 83,213 2007 250,113 1993 93,072 2008 265,120 1994 98,070 2009 281,027 1995 103,336 2010 297,889 1996 108,885 2011 309,805 1997 139,000 2012 322,197 1998 112,000 2013 335,085 1999 115,000 2014 348,488 2000 135,954 2015 362,428 2001 148,438 2016 376,925 2002 156,327 2017 388,232 2003 179,910 2018 399,879 2004 210,000 2019 411,876

Note: The 1990 to 2004 data are actual and 2005 to 2019 are estimates ADB Mission January 2006Source: Ministry of Culture and Tourism, Tourist Development Dept.,

ETHIOPIA

Annex 7 Page 7 of 7

(USD Million)

INCREMENTAL COST INCREMENTAL BENEFITSTotal Foreign Domestic Project Total Net

Capital costs Operating Costs IncrementaAirlines Aircraft a/c Tourism Incremental IncrementalYear With Without Incrementa With Without IncrementaCosts Fees* Savings* Benefit Benefits Benefits1997 2.66 11.77 -9.11 0.00 0.00 0.00 -9.11 0.00 0.00 0.00 0.00 9.111998 2.80 2.80 0.00 0.00 0.00 2.80 0.00 0.00 0.00 0.00 -2.801999 8.93 8.93 0.00 0.00 0.00 8.93 0.00 0.00 0.00 0.00 -8.932000 12.04 12.04 0.00 0.00 0.00 12.04 0.00 0.00 0.00 0.00 -12.042001 6.67 6.67 0.00 0.00 0.00 6.67 0.00 0.00 0.00 0.00 -6.672002 4.06 4.06 0.00 0.00 0.00 4.06 0.00 0.00 0.00 0.00 -4.062003 3.28 3.28 0.58 0.76 -0.18 3.10 0.52 5.14 -0.59 5.07 1.972004 1.38 1.38 0.59 0.77 -0.18 1.20 0.60 5.85 0.22 6.67 5.472005 0.00 0.60 0.79 -0.19 -0.19 0.67 6.47 0.59 7.73 7.922006 4.84 -4.84 0.61 0.83 -0.22 -5.06 0.70 6.83 0.98 8.51 13.572007 0.00 0.63 0.84 -0.21 -0.21 0.76 7.34 1.39 9.49 9.702008 0.48 0.48 0.69 0.86 -0.17 0.31 0.82 7.93 1.83 10.58 10.272009 0.00 0.70 0.88 -0.18 -0.18 0.88 8.70 2.30 11.88 12.062010 0.00 0.72 0.90 -0.18 -0.18 0.93 8.96 2.79 12.68 12.862011 0.00 0.75 0.92 -0.17 -0.17 0.99 9.55 3.17 13.71 13.882012 4.58 4.58 0.77 0.92 -0.15 4.43 1.05 10.09 3.70 14.84 10.412013 0.48 0.48 0.79 0.97 -0.18 0.30 1.12 10.68 4.13 15.93 15.632014 0.00 0.82 0.98 -0.16 -0.16 1.18 11.27 4.60 17.05 17.212015 4.84 -4.84 0.84 1.00 -0.16 -5.00 1.25 11.86 4.99 18.10 23.102016 0.00 0.85 1.02 -0.17 -0.17 1.32 12.52 5.47 19.31 19.482017 0.00 0.87 1.03 -0.16 -0.16 1.39 13.19 5.86 20.44 20.602018 0.48 0.48 0.90 1.06 -0.16 0.32 1.47 13.90 6.27 21.64 21.322019 -8.36 -8.36 0.93 1.10 -0.17 -8.53 1.55 14.65 6.68 22.88 31.41

NPV $31.7 EIRR 30.5%* Incremental foreign airlines fees and domestic aircraft savings are arrived at by comparing with and without project aircraft time savings in air delays and taxi in out times.

Annex 8 Page 1 of 4

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT PROJECT COMPLETION REPORT

Performance Rating Scale and Evaluation Criteria 1. Rating Scale

X > 3 highly satisfactory

2 < X < 3 Satisfactory

1 < X < 2 Unsatisfactory

X < 1 Highly unsatisfactory

Where X is the value assigned to a performance variable. Classification: Implementation performance is considered satisfactory if the average value of X is > 2. 2. Evaluation Results

Component Indicators Score (1-4)

Remarks

1. Adherence to time schedule 2 A delay of 5 months for the project start up and the project was completed with a time over run of 58 months (including additional works).

2. Adherence to cost schedule 3 Project was completed within the approved budget with some savings

3. Compliance with covenants

2 No slippage in loan effectiveness However, implementation of the undertaking given on tariff is still pending.

4. Adequacy of monitoring & evaluation and reporting

3 Complied with submission of all the relevant reports

5. Satisfactory Operations (if applicable)

3 Works were well executed. EIRR and FIRR are higher than the opportunity cost of capital in Ethiopia.

TOTAL 13 Overall Assessment of Implementation Performance

2.6

Satisfactory

Annex 8 Page 2 of 4

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

FORM BP 1

BANK PERFORMANCE

Component Indicators

Score

(1 to 4)

Remarks

1. At Identification 3 The project was an outcome of the recommendations of the feasibility studies financed through ADF/TAF resources.

2. At preparation of project

- -

3. At appraisal

3

The project was of high priority to GOE.

4. At supervision

2

Technical issues were resolved in time and adequate measures taken. However, some delays in disbursements by the Bank resulted in additional costs to the GOE

Overall assessment of Bank Performance 2.67 Satisfactory

Annex 8 Page 3 of 4

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

FORM PO 1 PROJECT OUTCOME

No.

Component Indicators

Score (1 to 4)

Remarks

1 Relevance and Achievement of Objectives*

i)

Macro-economic policy

3

ii)

Sector Policy

3

iii)

Physical (incl. Production)

3

Well designed additional facilities at the Addis Ababa Airport improved the air transport services

iv)

Financial

3

v)

Poverty alleviation, social & gender

2

vi)

Environment

3

Provisions of the Environmental Guidelines were implemented.

vii)

Private sector development

3

viii)

Other (Specify)

2

Institutional Development (ID)

i) Institutional framework incl. Restructuring

2

ii) Financial and Management Information Systems including Audit Systems

2

There is no computerized Financial and MIS at ECAA Annual auditing of the project was done.

iii) Transfer of Technology 3 iv)

Staffing by qualified persons (incl. Turnover), training & counter-part staff

3

Annex 8

Page 4 of 4

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

FORM PO 1

PROJECT OUTCOME 3

Sustainability

Score

Remarks

i)

Continued Borrower Commitment

3

Borrower has shown commitment to airport maintenance by increasing its annual budgets

ii)

Environmental Policy

3

The National Environmental Agency for Environment Impact Assessment is staffed with qualified and experienced environmentalists. The Policy is appropriately followed.

iii)

Institutional Framework 3 The Implementing Agency CAA is well organised with technical staff skills and capabilities

iv)

Technical Viability and Staffing 3 EAE is manned with adequate professional technical staff.

v)

Financial viability including cost recovery systems

3

The investment of the project is financially viable

vi)

Economic Viability 3 The investment for the project is economically viable.

vii)

Environmental Viability 3 Project is well monitored to ensure compliance with environmental policies and requirements.

viii) O&M facilitation (availability of recurrent funding, foreign exchange, spare parts, workshop facilities etc.)

3

Sufficient funds and capacity for operations and Maintenance is available.

4

Economic Internal Rate of Return Financial Internal Rate of Return

4 4

EIRR : 30.5% FIRR : 30.0%

TOTAL 62

Overall Assessment of Outcome 2.9 Satisfactory

Annex 9 ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

RECOMMENDATIONS AND FOLLOW-UP MATRIX

Main Findings & Conclusions Lessons Learned/ Recommendations Follow-up Actions Responsibility Formulation & Project Rational: The project was a result of the airport studies financed by the Bank in February 1992 as part of the GOE’s emphasis on the development and improvements of the transport infrastructure, in particular airport infrastructure.

A design review by the Supervision consultant (in particular if the initial design was carried out by a different consultant) to make up any deficiencies in the original design is advantageous and desirable.

GOE be advised to continue to adopt same procedure of design review by the supervision consultant prior to issue of bids to ensure its structural adequacy for effective and efficient implementation of projects.

GOE

Project Implementation: Time overrun (delays during implementation) was mainly due to several factors listed in the relevant section of the report. The time period given for execution of works (24 months in this case) under working conditions of an operational airport appear to be un-practicable.

A realistic time period taking into consideration the nature of works and the operational working conditions should have been allowed for execution of works of such complex nature. Borrowers should review and assess the time period required for completion in order to minimise time extensions and additional payments.

For execution of projects of similar nature, Borrower should review and assess the time period required for completion to minimise delays and additional costs.

GOE / ADB

Compliance with Loan Conditions & Covenants: The undertaking given by the Borrower as part of the loan conditions, which stipulated that the airside tariffs should be adjusted in line with market trends and continuously adjusted thereafter to reflect cost of providing services, was yet to be implemented.

GOE should fulfil its undertaking, given as one of the conditions precedent to first disbursement, that tariffs will be adjusted in line with market trend.

Priority should be accorded to the approval and implementation of the revised tariffs proposed by EAE.

GOE

Performance Evaluation & Project Outcome: The overall project performance rating was judged to be satisfactory and the project objective was fully achieved.

Though the project is a well designed outcome with additional facilities for the improvement of air transport services at Addis Ababa Airport, the value of the project would have further enhanced (in terms of cost and time) if this had been completed as per appraisal schedule.

The GOE should make efforts to adhere to implementation schedules.

GOE

Sustainability: The tariff has not been revised and there is also accumulated debt by EAE’s clients with the attendant risk that sufficient fund might not be available to cover debt service, annual operating expenses, maintenance and return on investment.

EAE has submitted the revised tariff for Government approval.

GOE to its undertaking of adjusting the tariff. EAE to improve the debt collection efforts.

GOE

Annex 10

ETHIOPIA

ADDIS ABABA INTERNATIONAL AIRPORT DEVELOPMENT PROJECT

PROJECT COMPLETION REPORT

SOURCES OF INFORMATION

1. Borrower's Project Completion Report, June 2005. 2. Appraisal Report on Addis Ababa International Airport Development Project,

September 1996. 3. Consultant’s ( Dar Al- Handasah) Final Completion Report, March 2002 and

TCDE Final Completion Report, January 2004. 4. Project Files. 5. Supervision Mission Reports.

6. Addis Ababa Airport Infrastructure Study, Financial Analysis & Economic Evaluation,

TAMS Consultants Inc in Association with National Consultants and Transport Construction Design Enterprise, July 1993 (TCDE).

7. Ethiopian Airports Enterprise, Air Transport Statistics, Addis Ababa, November 2005.

8. Proclamation No. 273 / 2002 – The Ethiopian Civil Aviation Authority Re-

establishment Proclamation.

9. Council of Ministers Regulation No. 82/2003, Ethiopian Airports Enterprise Establishment Council of Ministers Regulation.

10. Charges for Aerodromes and Air Navigation Services, Civil Aviation Authority, Addis

Ababa. 11. National Bank of Ethiopia (Central Bank), Third Quarter of 2004/05 and Annual

2003/04, 2002/03 and 2001/02 Reports.

12. ECAA Audited Accounts 1995/1996 to 1998/99.

13. ECAA Management Accounts 1999/2000 to 2003/04.

14. EAE Draft Accounts 2003/2004 and 2004/2005. 15. Projected Audited Accounts for 2003 to 2005.