ETC GDPR 01a Power System Design

Embed Size (px)

Citation preview

  • 7/31/2019 ETC GDPR 01a Power System Design

    1/32

  • 7/31/2019 ETC GDPR 01a Power System Design

    2/32

    2

    TOPIC OBJECTIVES

    Better understanding of:

    why and how the Power system design have influence on the securityof the system

    possible causes of faults on lines, transformers, busbars or equipmentin switchyards

    switchgear arrangements - maintainability and reliability

    hardware and software of fault clearance and control system

    specifics about Electric Power System of Nigeria

  • 7/31/2019 ETC GDPR 01a Power System Design

    3/32

  • 7/31/2019 ETC GDPR 01a Power System Design

    4/32

    4

    Transmission lines design

    Voltage level

    Overhead line or cable Single or double circuit

    Insulator chain design

    Towers design

    Shield wires

    Tower footing earthing

    Conductor thermal capability

  • 7/31/2019 ETC GDPR 01a Power System Design

    5/32

    5

    Faults on transmission line possible causes

    Lightning

    Switching

    Pollution

    Salt storms

    Growing trees

    Bush fires Damage or sabotage

    The most often!

  • 7/31/2019 ETC GDPR 01a Power System Design

    6/32

    6

    Power transformers design

    Voltage level Insulation level

    kV kV0.4 0.42

    0.415

    1

    6 7.2

    10 12

    11 12

    15 15.75

    20 24

    33 36

    35 38

    66 72

    110 123

    132 145

    220 245

    330 362

    400 420

    750

    1000

    EHV

    Group

    LV

    MV

    HV

    Purpose and capacity

    Step up or step down, ratio

    Insulation levels

    Neutral point earthing

    Tap changing (off/on load)

    Dry or oil immersed

    Cooling system

    Single phase or three phase

    Two/three windings or autotransformer

    Efficiency (loses)

    Impedance

    Vector group

  • 7/31/2019 ETC GDPR 01a Power System Design

    7/32

    7

    Power transformers vector groups

    N

    A

    B

    C

    a

    b

    c

    YNd11

    N

    A

    B

    C

    ma

    mb

    mc

    b

    c

    a

    YaNd11

    ZNyn1NA

    B

    C

    a

    b

    c

    n

    EARTHING TRANSFORMER

    POWER TRANSFORMER 132/33 KV INTERCONECTION AUTOTRANSFORMER330/132 KV

    TERTIARY WINDING

  • 7/31/2019 ETC GDPR 01a Power System Design

    8/32

    8

    Power transformer faults possible causes:

    Deterioration and ageing of insulation

    Mechanical damage of insulation Damage of conductor, poor contact in joints

    Tap-changer, wear, mechanical failure

    Tap-changer switching during overcurrent condition

    Transient overvoltage , e.g. at lightning or switching

    Contaminated oil Corona discharge

    Mechanical forces on windings and bushings

    Heavy current during external faults, switching-in, or at resonance

    Overheating

    High load current or circulation current between parallel transformers Reduced or lost cooling, sustained through-fault current

    Overexcitation or voltage rise with transformer core saturation

  • 7/31/2019 ETC GDPR 01a Power System Design

    9/32

    9

    Power transformer faults

    IEEE statistics about transformer faults

    Earth fault

    Short circuit Turn-to turn fault

    Flash over from HV to LV winding

    Core fault

    Tank fault

    External fault

  • 7/31/2019 ETC GDPR 01a Power System Design

    10/32

    10

    Switchyard design

    In many cases there is a tendency to have richly equippedswitchyards.

    The reason for this is often to have high dependability for the

    fault clearance, have a high probability of fault disconnection.

    We have to keep in mind that more equipment we have , thehigher probability for faults in the equipment we get!

  • 7/31/2019 ETC GDPR 01a Power System Design

    11/32

    11

    Switchyard design: HV equipment

    Busbar conductors and drop off connections, fittings

    Isolators/disconnectors

    Circuit breakers

    Current transformers

    Voltage transformers

    Surge arrestors Earthing switches

    Line (wave) traps

    The most important is typeof switchgear arrangement

    and the placement of HVequipment

  • 7/31/2019 ETC GDPR 01a Power System Design

    12/32

    12

    Switchyard design:Single breaker - single busbar

    Cheap, simple, in distribution sector

  • 7/31/2019 ETC GDPR 01a Power System Design

    13/32

    13

    For more feeders and incomers

    Bus section

    Switchyard design:Single busbar with bus section

  • 7/31/2019 ETC GDPR 01a Power System Design

    14/32

    14

    No feeder outage during maintenance of CB

    Switching logic of tripping to Line CB or Transfer bay CB

    Transfer bus

    Transfer bay

    Switchyard design:Single busbar with transfer bay

  • 7/31/2019 ETC GDPR 01a Power System Design

    15/32

    15

    Switchyard design: Double busbar

    The most common arrangement

    Bus coupler

  • 7/31/2019 ETC GDPR 01a Power System Design

    16/32

    16

    SWITCHGEAR ARRANGEMENTS: Breaker and a half

    For two lines Three breakers =3/2 = 1 1/2

  • 7/31/2019 ETC GDPR 01a Power System Design

    17/32

  • 7/31/2019 ETC GDPR 01a Power System Design

    18/32

    18

    Single busbar +

    Reserve busbar

    13%

    Single busbar

    27%

    Double busbar

    42%

    Poligone (ring)

    busbar

    1%Double busbar with

    2 breakers

    2%

    Double busbar with

    1.5 breaker

    4%

    Triple busbar

    4%

    Double busbar +

    Reserve busbar

    7%

    SWITCHGEAR ARRANGEMENTS

    CIGRE statistics about applied switchgear arrangements

  • 7/31/2019 ETC GDPR 01a Power System Design

    19/32

    19

    SWITCHGEAR ARRANGEMENTS: Busbar faults

    Fault causeType and number of faults

    Total %PE PPE 3P Unknown

    Flash over on busbar insulators 20 6 1 27 21%

    Circuit Breaker failure 16 2 2 20 16%

    Insulation on switching devices 19 2 1 22 17%

    Other on insulation 4 1 4 9 7%

    Current transformers 3 3 2%

    Disconnector opening on load 8 1 6 15 12%

    Not removed temporary earthing 6 1 8 15 12%

    Contacts (birds and other) 9 1 2 1 13 10%

    Misc. and unknown 2 1 1 1 5 4%Total 87 15 24 3 129

    % 67% 12% 19% 2%100%

    CIGRE statistics for 400 kV busbars 91-96.

  • 7/31/2019 ETC GDPR 01a Power System Design

    20/32

    20

    PROTECTION

    EQUIPMENT

    TRIP

    COIL

    TELE

    COM

    DC SYSTEM

    FAULT

    VOLTAGE

    TRANSFORMER

    CURRENT

    TRANSFORMER

    CIRCUIT BREAKER

    FAULT CLEARANCE SYSTEM

  • 7/31/2019 ETC GDPR 01a Power System Design

    21/32

    21

    PROTECTION

    EQUIPMENT

    TRIP

    COIL

    TELE

    COM

    DC SYSTEM

    FAULT

    VOLTAGE

    TRANSFORMER

    CURRENTTRANSFORMER

    CIRCUIT BREAKER

    FAULT CLEARANCE SYSTEM

    HARDWARE DC supply system Current transformers Voltage transformers Protective relays Switching devices Telecommunication equipment Wiring

    SOFTWARE

    Design Construction (installation) Configuration of the protection relays Setting of the protection relays Maintenance

  • 7/31/2019 ETC GDPR 01a Power System Design

    22/32

    22

    CONTROL SYSTEM

    Control commands(open, close, raise, lower )

    Indications(position, status )

    Alarms (protection trips, alerts, warnings)

    Metering(current, voltage, power, temperature )

    Synchro-check

    OLTCvoltage control

    Katampe 330/132 kV s/sCONTROL BOARD

  • 7/31/2019 ETC GDPR 01a Power System Design

    23/32

    23

    Specific characteristics of Power system of Nigeria

    Still in development

    Waste area with very different population density and consumption

    Still unable to supply the nations demand for electricity needs to build new

    generating plants and rehabilitate existing but not operational capacities

    Hydro generation in middle belt (Kainji, Jebba and Shiroro)

    Thermal generation on south (Egbin, Sapele, Afam, Delta)

    Total energy loses are still very high (about 30 %) Long lines needs to build new substations

    Radial lines needs to build new lines to close the loops

    Parallel SC lines, double circuits lines

    Low reliability of plants due to insufficient maintenance

    Low security and transient instability

    Persistent and frequent black-outs

    Deregulation and privatization in power sector goes very slow

  • 7/31/2019 ETC GDPR 01a Power System Design

    24/32

  • 7/31/2019 ETC GDPR 01a Power System Design

    25/32

    25

    KAINJI HPP

    JEBBA HPP

    JEBBA SHIRORO HPP

    OSHOGBOKATAMPE

    KADUNAKANO

    JOS

    GOMBEBIRNIN KEBBI

    157 km 3 x SC

    5,6 km DC

    AIYEDE

    IKEJA WEST

    EGBIN TPP

    251 km SC

    280 km DC

    62 km DC

    119 km SC

    137 km

    2 x SC

    BENIN

    AJAOKUTA

    195 km 2 X SC

    SAPELE TPP

    AKANGBA

    AJA

    50 km DC

    ONITSHA NEW HAVEN

    ALAOJI

    25 km DC

    AFAMALADJA

    DELTA IV TPP

    G

    G

    81km 2XSC

    310 km SC

    244 km 2XSC

    G

    230 km SC

    197 km SC

    265 km SC

    96 km 2XSC

    144 km DC

    G

    G

    G

    G

    137 km 2 X SC

    95 km SC

    138 km

    SC175 km

    SC

    107 km

    17 km

    63 km

    5 x 90 MVA

    2 x 150

    MVA

    4 x 150

    MVA

    2 x 150 MVA

    G

    6 x 220 MW

    60 MVA

    90 MVA150 MVA

    90 MVA

    2X60 MVA

    2 x 90

    MVA

    2 x 150

    MVA

    2 x 150

    MVA

    2 x 150MVA

    2 x 150

    MVA

    2x150 MVA

    4 x 150 MW

    4 x 200 MVA

    2x 120 MW

    2 x 100 MW

    4 x 80 MW

    6 x 90 MW

    2 x 150

    MVA

    6 x 120 MW

    4 x 71.25 MW

    6 x 140 MVA

    2 x 168.5 MVA

    3 x 50

    MVA

    2 x 150

    MVA

    2 x 150

    MVA

    2 x 90

    MVA

    150 MVA

    90 MVA

    60 MVA

    17 km DC

    16 km DC

    256 km SC

    330 kV Transmission Power Network of Nigeria

  • 7/31/2019 ETC GDPR 01a Power System Design

    26/32

    26

    Historical growth of NEPA generation

    Not suppressed power demand is 12,000 MW (unofficially)

  • 7/31/2019 ETC GDPR 01a Power System Design

    27/32

    27

    Generated energy in NEPA Power plants

  • 7/31/2019 ETC GDPR 01a Power System Design

    28/32

    28

    Status of NEPA Hydro power plant (2004)

    89 %

  • 7/31/2019 ETC GDPR 01a Power System Design

    29/32

    29

    Status of NEPA Thermal power plant (2004)

  • 7/31/2019 ETC GDPR 01a Power System Design

    30/32

    30

    Status of NEPA Thermal power plant (2004)

  • 7/31/2019 ETC GDPR 01a Power System Design

    31/32

  • 7/31/2019 ETC GDPR 01a Power System Design

    32/32

    32

    New power plants up to 2007

    Okpai Power Project(Agip) 450 MW

    Afam VI (Shell) 700 MW

    Geregu (Siemens) 414 MW

    Papalanto (Chinese Gov.) 335 MW

    Omotosho (Chinese Gov.) 335 MW

    Alaoji 400 MW Shell PDC Afam 700 MW

    3334 MW

    By Plan in 2007

    8500 MWIn total will be connected on network