Estimation of Building House

Embed Size (px)

Citation preview

  • 8/2/2019 Estimation of Building House

    1/37

    S No. Description Amount (Rs.)

    1 Construction of Civil Dispensary 1,617,207

    2 Construvtion of Type 4 House (02) Nos #REF!

    3 Construction of Compound Wall 636,673

    4 Construction of Rain Water Drain 131,003

    5 Walk Way 169,514

    6 Tub Well 1,016,579

    7 External Water Supply 56,545

    8 Leveling & Dressing 5,301

    #REF!

    GENERAL ABSTRACT OF COST

    G.Total

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT---

    --------------------- FR D.I KHAN

    TASK- 6

  • 8/2/2019 Estimation of Building House

    2/37

    S No. Description Amount (Rs.)

    1 Type 4 House Civil Work #REF!

    2 Internal Electrification 78,713

    3 Water Supply 54,312

    4 Sewrage System 55,215

    #REF!

    #REF!

    #REF!

    ABSTRACT OF COST OF TYPE 4 HOUSE

    Sub-Total

    TASK-6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT---

    --------------------- FR D.I KHAN

    Add Cost for one more

    Grand Total:

  • 8/2/2019 Estimation of Building House

    3/37

    S No. Description Amount (Rs.)

    1 Civil Dispensary 1,374,893

    2 Internal Electrification 106,129

    3 Internal Water Supply 77,741

    4 Sewrage System 58,444

    1,617,207

    TASK-6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT---

    --------------------- FR D.I KHAN

    ABSTRACT OF COST OF CD

    G-Total

  • 8/2/2019 Estimation of Building House

    4/37

    http://mosttutorials.blogspot.com/

    A civil Engineering softwares tutorials,setups,ebooks website

    1

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Exam: Room Long Wall 2 14.75 3 3.5 309.75

    Exam: Room Short Wall 2 12.75 3 3.5 267.75

    Female Waiting Room Long Wall 2 10.75 3 3.5 225.75

    Female Waiting Room Short Wall 2 12.75 3 3.5 267.75

    Dispenser Room long Wall 1 12.75 3 3.5 133.88

    Dispenser Room Short Wall 2 12.75 3 3.5 267.75

    Store & Bath Long Wall 2 6.00 3 3.5 126.00

    Store & Bath Short Wall 2 12.33 3 3.5 258.93

    EPI Long Wall 1 12.75 3 3.5 133.88

    EPI Short Wall 2 12.75 3 3.5 267.75

    Male Waiting Room Long Wall 1 12.75 3 3.5 133.88

    Male Waiting Room Short Wall 2 10.75 3 3.5 225.75

    Bath Long Wall 1 6.75 3 3.5 70.88

    Bath Short Wall 1 7.75 3 3.5 81.38

    Ramp 1 6.25 2 2 25.00

    2771.06 cft

    2

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Exam: Room Long Wall 2 14.75 3 1 88.50

    Exam: Room Short Wall 2 12.75 3 1 76.50

    Female Waiting Room Long Wall 2 10.75 3 1 64.5

    Female Waiting Room Short Wall 2 12.75 3 1 76.50

    Dispenser Room long Wall 1 12.75 3 1 38.25

    Dispenser Room Short Wall 2 12.75 3 1 76.50

    Store & Bath Long Wall 2 6.00 3 1 36.00

    Store & Bath Short Wall 2 12.33 3 1 73.98

    EPI Long Wall 1 12.75 3 1 38.25

    EPI Short Wall 2 12.75 3 1 76.50Male Waiting Room Long Wall 1 12.75 3 1 38.25

    Male Waiting Room Short Wall 2 10.75 3 1 64.50

    Bath Long Wall 1 6.75 3 1 20.25

    Bath Short Wall 1 7.75 3 1 23.25

    Ramp 1 6.25 2 0.5 6.25

    Total:

    Task # 6

    0

    Estimate for Main Building CD

    Excavation in foundation of building, bridges etc complete : in hard soil or soft murum

    emen oncre e r c s one a as , . o nu a s ng e we gra e an c eane n oun a on

    http://mosttutorials.blogspot.com/http://mosttutorials.blogspot.com/
  • 8/2/2019 Estimation of Building House

    5/37

    791.73 cftTotal :

  • 8/2/2019 Estimation of Building House

    6/37

    3

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    1st Step 22.5" Thick

    Exam: Room Long Wall 2 14.75 1.87 0.5 27.58

    Exam: Room Short Wall 2 12.75 1.87 0.5 23.84

    Female Waiting Room Long Wall 2 10.75 1.87 0.5 20.10

    Female Waiting Room Short Wall 2 12.75 1.87 0.5 23.84Dispenser Room long Wall 1 12.75 1.87 0.5 11.92

    Dispenser Room Short Wall 2 12.75 1.87 0.5 23.84

    Store & Bath Long Wall 2 6.00 1.87 0.5 11.22

    Store & Bath Short Wall 2 12.33 1.87 0.5 23.06

    EPI Long Wall 1 12.75 1.87 0.5 11.92

    EPI Short Wall 2 12.75 1.87 0.5 23.84

    Male Waiting Room Long Wall 1 12.75 1.87 0.5 11.92

    Male Waiting Room Short Wall 2 10.75 1.87 0.5 20.10

    Bath Long Wall 1 6.75 1.87 0.5 6.31

    Bath Short Wall 1 7.75 1.87 0.5 7.25

    Ramp 1 6.25 1.13 0.5 3.53

    2nd Step 18" ThickExam: Room Long Wall 2 14.75 1.5 0.5 22.13

    Exam: Room Short Wall 2 12.75 1.5 0.5 19.13

    Female Waiting Room Long Wall 2 10.75 1.5 0.5 16.13

    Female Waiting Room Short Wall 2 12.75 1.5 0.5 19.13

    Dispenser Room long Wall 1 12.75 1.5 0.5 9.56

    Dispenser Room Short Wall 2 12.75 1.5 0.5 19.13

    Store & Bath Long Wall 2 6.00 1.5 0.5 9.00

    Store & Bath Short Wall 2 12.33 1.5 0.5 18.50

    EPI Long Wall 1 12.75 1.5 0.5 9.56

    EPI Short Wall 2 12.75 1.5 0.5 19.13

    Male Waiting Room Long Wall 1 12.75 1.5 0.5 9.56

    Male Waiting Room Short Wall 2 10.75 1.5 0.5 16.13

    Bath Long Wall 1 6.75 1.5 0.5 5.06

    Bath Short Wall 1 7.75 1.5 0.5 5.81

    Ramp 1 6.25 9 1 56.25

    3rd Step 13.5" Thick

    Exam: Room Long Wall 2 14.75 1.13 0.5 16.59

    Exam: Room Short Wall 2 12.75 1.13 0.5 14.34

    Female Waiting Room Long Wall 2 10.75 1.13 0.5 12.09

    Female Waiting Room Short Wall 2 12.75 1.13 0.5 14.34

    Dispenser Room long Wall 1 12.75 1.13 0.5 7.17

    Dispenser Room Short Wall 2 12.75 1.13 0.5 14.34

    Store & Bath Long Wall 2 6.00 1.13 0.5 6.75

    Store & Bath Short Wall 2 12.33 1.13 0.5 13.87

    EPI Long Wall 1 12.75 1.13 0.5 7.17EPI Short Wall 2 12.75 1.13 0.5 14.34

    Male Waiting Room Long Wall 1 12.75 1.13 0.5 7.17

    Male Waiting Room Short Wall 2 10.75 1.13 0.5 12.09

    Bath Long Wall 1 6.75 1.13 1.5 11.39

    Bath Short Wall 1 7.75 1.13 2.5 21.80

    Pacca brick work in foundation and plinth in Cement, sand mortar 1:6

  • 8/2/2019 Estimation of Building House

    7/37

    4th Step 9" Thick Wall

    Exam: Room Long Wall 2 14.75 0.75 2.5 55.31

    Exam: Room Short Wall 2 12.75 0.75 2.5 47.81

    Female Waiting Room Long Wall 2 10.75 0.75 2.5 40.31

    Female Waiting Room Short Wall 2 12.75 0.75 2.5 47.81

    Dispenser Room long Wall 1 12.75 0.75 2.5 23.91

    Dispenser Room Short Wall 2 12.75 0.75 2.5 47.81Store & Bath Long Wall 2 6.00 0.75 2.5 22.50

    Store & Bath Short Wall 2 12.33 0.75 2.5 46.24

    EPI Long Wall 1 12.75 0.75 2.5 23.91

    EPI Short Wall 2 12.75 0.75 2.5 47.81

    Male Waiting Room Long Wall 1 12.75 0.75 2.5 23.91

    Male Waiting Room Short Wall 2 10.75 0.75 2.5 40.31

    Bath Long Wall 1 6.75 0.75 2.5 12.66

    Bath Short Wall 1 7.75 0.75 2.5 14.53

    494.83 cft

    4

    Description No Width (ft) Quantity (sft)

    Exam: Room Long Wall 2 0.75 22.13

    Exam: Room Short Wall 2 0.75 19.13

    Female Waiting Room Long Wall 2 0.75 16.13

    Female Waiting Room Short Wall 2 0.75 19.13

    Dispenser Room long Wall 1 0.75 9.56

    Dispenser Room Short Wall 2 0.75 19.13

    Store & Bath Long Wall 2 0.75 9.00

    Store & Bath Short Wall 2 0.75 18.50

    EPI Long Wall 1 0.75 9.56

    EPI Short Wall 2 0.75 19.13

    Male Waiting Room Long Wall 1 0.75 9.56

    Male Waiting Room Short Wall 2 0.75 16.13

    Bath Long Wall 1 0.755.06Bath Short Wall 1 0.75 5.81

    197.93 sft

    Length (ft)

    Total:

    14.75

    12.75

    10.75

    12.75

    12.75

    10.75

    6.75

    Damp proof of cem. conc. 1:2:4 i/c bitumen coat, 1 layer polythene & 2 coats bitumen (2" thick)

    12.75

    12.75

    Total:

    6.00

    12.33

    12.75

    12.75

    7.75

  • 8/2/2019 Estimation of Building House

    8/37

    5

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Exam: Room Long Wall 2 14.75 0.75 11 243.38

    Exam: Room Short Wall 2 12.75 0.75 11 210.38

    Female Waiting Room Long Wall 2 10.75 0.75 11 177.38

    Female Waiting Room Short Wall 2 12.75 0.75 11 210.38

    Dispenser Room long Wall 1 12.75 0.75 11 105.19Dispenser Room Short Wall 2 12.75 0.75 11 210.38

    Store & Bath Long Wall 2 6.00 0.75 11 99.00

    Store & Bath Short Wall 2 12.33 0.75 11 203.45

    EPI Long Wall 1 12.75 0.75 11 105.19

    EPI Short Wall 2 12.75 0.75 11 210.38

    Male Waiting Room Long Wall 1 12.75 0.75 11 105.19

    Male Waiting Room Short Wall 2 10.75 0.75 11 177.38

    Bath Long Wall 1 6.75 0.75 11 55.69

    Bath Short Wall 1 7.75 0.75 11 63.94

    Perapet Wall 1 141.75 0.75 3.17 337.01

    2514.27 cft

    Deduction

    D1 6 3.50 0.75 7.00 110.25D2 1 3.00 0.75 7.00 15.75

    D3 2 2.50 0.75 7.00 26.25

    W1 5 6.00 0.75 5.00 112.50

    V1 3 3.00 0.75 2.00 13.50

    278.25

    2236.02

    6

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    RCC Slabe as per Coverd Area 0.5 537.855

    D1 6 5.00 0.75 0.5 11.25

    D2 1 4.50 0.75 0.5 1.69

    D3 2 4.00 0.75 0.5 3.00

    W1 5 7.50 0.75 0.5 14.06

    RCC Beam 1 16.75 0.83 0.50 6.98

    Sun Shade 1 156.75 3.00 0.33 155.18

    730.02 cft

    Pacca brick work in ground floor Cement, sand mortar 1:4

    Total:

    S.Total:

    Total:

    RCC in roof slab, beam, column & other structural members, insitu or precast. Type C (1:2:4)

    Total:

    1075.71

  • 8/2/2019 Estimation of Building House

    9/37

    7

    Steel Reinforcement 730.02 6.00 2240 1.96

    1.96 tonne

    8

    As per Coverd Area 0.14 150.60

    150.60 Cft9

    Description No Length (ft) Width (ft) Quantity (cft)

    As per Coverd Area 1075.71

    1075.71 sft

    10

    as per Coverd Area 1075.71

    1075.71 sft

    11

    As per Coverd Area 1075.71

    1075.71 sft

    12

    As per Coverd Area 1075.71

    1075.71 sft

    13

    6 3.50 7.00 147.000

    1 3.00 7.00 21.000

    2 2.50 7.00 35.000

    203.00 sft

    14

    6 3.50 7.00 147.00

    1 3.00 7.00 21.00

    2 2.50 7.00 35.00

    3 3.00 2.00 18.00

    221.00 sft

    156 3.50 7.00 147.00 sft

    147.00 sft

    16

    9.00

    9.00 Nos

    17

    No. Width (ft) Height (ft) Quantity (sft)

    5 6.00 5.00 150.00

    150.00 sft

    18

    5 6.00 5.00 150.00

    150.00 sft

    1075.71

    S/F of Polythene sheet on roof in two layers as spfd:

    Total:

    Earth filling over roof including watering, ramming etc 4" thick earth filling and 1" mud plaster

    1075.71

    Total:

    First class deodar wood wrought joinery work GI wire guaze fixed to chowkat with 1/2" stripD1

    9

    Description

    W1

    Total:

    Total:

    MS flat 1/2"x1/8" grill in windows of approved design.

    W1

    Make & fix cleats for doors & windows including hinges and screws.

    Cleats

    Total :

    Total:

    D2

    D3

    Total:

    Provide & fix 20 gauge steel chowkat for doors, windows & CS windows,including holdfast etc

    D1

    D2

    D3

    Total :

    Total:

    Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4) on Roof

    Total:

    1075.71

    First class deodar wood wrought joinery in doors and windows etc. complete : 1.5" thick

    D1

    V1

    Total:

    Supply & fabricate M.S. reinforcement for cement concrete (Hot Rold Bars) Grade 40

    Total:

    2 coats of bitumen laid hot using 34 lbs. for %sft over roof & blinded with sand at 1 cft per % sft

    1075.71

    1075.71

    Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1" mud plaster on top of RC roof slab

  • 8/2/2019 Estimation of Building House

    10/37

    19

    Description Side No. Width (ft) Height (ft) Quantity (sft)

    D1 2 6 3.50 7.00 294.00

    D2 2 1 3.00 7.00 42.00

    D3 2 2 2.50 7.00 70.00

    W1 2 5 6.00 5.00 300.00

    V1 2 3 3.00 2.00 36.00742.00 sft

    20

    Examinition Room 1 12.00 14.00 0.50 84.00

    F/Male Waiting Room 1 16.00 12.00 0.50 96.00

    Dispenser Room 1 12.00 12.00 0.50 72.00

    Store & Bath 1 11.58 6.00 0.50 34.74

    EPI 1 12.00 12.00 0.50 72.00

    Male Waiting 1 12.00 10.00 0.50 60.00

    Veranda 1 14.75 12.00 0.50 88.50

    Ramp 1 6.00 6.00 0.25 9.00

    516.24 cft

    21

    Examinition Room 1 12.00 14.00 0.33 55.44F/Male Waiting Room 1 16.00 12.00 0.33 63.36

    Dispenser Room 1 12.00 12.00 0.33 47.52

    Store & Bath 1 11.58 6.00 0.33 22.93

    EPI 1 12.00 12.00 0.33 47.52

    Male Waiting 1 12.00 10.00 0.33 39.60

    Veranda 1 14.75 12.00 0.33 58.41

    Ramp 1 6.00 6.00 0.25 9.00

    343.78 cft

    22

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Examinition Room 1 12.00 14.00 0.33 55.44

    F/Male Waiting Room 1 16.00 12.00 0.33 63.36

    Dispenser Room 1 12.00 12.00 0.33 47.52Store & Bath 1 11.58 6.00 0.33 22.93

    EPI 1 12.00 12.00 0.33 47.52

    Male Waiting 1 12.00 10.00 0.33 39.60

    Veranda 1 14.75 12.00 0.33 58.41

    Ramp 1 6.00 6.00 0.25 9.00

    343.78 cft

    23

    Description No Length (ft) Quantity (cft)

    Examinition Room 1 12.00 168.00

    F/Male Waiting Room 1 16.00 192.00

    Dispenser Room 1 12.00 144.00

    Store & Bath 1 11.58 69.48

    EPI 1 12.00 144.00

    Male Waiting 1 12.00 120.00

    Veranda 1 14.75 177.00

    Ramp 1 6.00 36.00

    1050.48 sft

    10.00

    12.00

    6.00

    Total:

    12.00

    12.00

    Filling, watering and ramming earth under floor with surplus earth from foundation, etc

    Total:

    Supplying and filling sand under floor or plugging in wells

    Total:

    Provide & lay topping of concrete 1:2:4, incl. surface finishing & dividing in panels : 2" thick

    Width (ft)

    14.00

    Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:4:8)

    Total:

    Prepare & paint new surface door & windows prime coat & 2nd Coat

    6.00

    12.00

    Total:

  • 8/2/2019 Estimation of Building House

    11/37

    24

    Description Side No. Length (ft) Height (ft) Quantity (sft)

    Exam: Room Long Wall 2 2 14.00 11 616.00

    Exam: Room Short Wall 2 2 12.00 11 528.00

    Female Waiting Room Long Wall 2 2 12.00 11 528.00

    Female Waiting Room Short Wall 2 2 10.00 11 440.00

    Dispenser Room long Wall 2 2 12.00 11 528.00

    Dispenser Room Short Wall 2 2 12.00 11 528.00Store & Bath Long Wall 2 2 6.00 11 264.00

    Store & Bath Short Wall 2 2 11.58 11 509.52

    EPI Long Wall 2 2 12.00 11 528.00

    EPI Short Wall 2 2 12.00 11 528.00

    Male Waiting Room Long Wall 2 2 10.00 11 440.00

    Male Waiting Room Short Wall 2 2 12.00 11 528.00

    Bath Long Wall 2 1 7.00 11 154.00

    Bath Short Wall 2 1 6.00 11 132.00

    Ceiling & Roof 2 1 1075.71 2151.42

    Perapet Wall 1 1 141.75 3.17 449.35

    8852.29 sft

    D1 1 6 3.50 7.00 147.00

    D2 1 1 3.00 7.00 21.00D3 1 2 2.50 7.00 35.00

    W1 1 5 6.00 5.00 150.00

    V1 1 3 3.00 2.00 18.00371.00 sft

    8481.29 sft

    25Description Side No. Length (ft) Height (ft) Quantity (sft)

    Exam: Room Long Wall 2 2 14 11 616.00

    Exam: Room Short Wall 2 2 12 11 528.00

    Female Waiting Room Long Wall 2 2 12 11 528.00

    Female Waiting Room Short Wall 2 2 10 11 440.00

    Dispenser Room long Wall 2 2 12 11 528.00

    Dispenser Room Short Wall 2 2 12.00 11 528.00

    Store & Bath Long Wall 2 2 6.00 11 264.00Store & Bath Short Wall 2 2 11.58 11 509.52

    EPI Long Wall 2 2 12.00 11 528.00

    EPI Short Wall 2 2 12.00 11 528.00

    Male Waiting Room Long Wall 2 2 10.00 11 440.00

    Male Waiting Room Short Wall 2 2 12.00 11 528.00

    Bath Long Wall 2 1 7.00 11 154.00

    Bath Short Wall 2 1 6.00 11 132.00

    Ceiling 1 1 1075.71 1075.71Pera et Wall 1 1 141.75 3.17 449.35

    7776.58 sft

    D1 1 6 3.50 7.00 147.00

    D2 1 1 3.00 7.00 21.00

    D3 1 2 2.50 7.00 35.00

    W1 1 5 6.00 5.00 150.00V1 1 3 3.00 2.00 18.00

    371.00 sft

    7405.58 sft

    Distempering New surface : Three coats

    S.Total :Deduction

    S.Total:

    Deduction

    Total:

    S.Total:

    Total:

    Cement plaster 1:4 upto 20' height 1/2" thick

    S.Total :

  • 8/2/2019 Estimation of Building House

    12/37

    26

    Description No. Length (ft) Weidth (ft) Height (ft) Quantity (Cft)

    Plinth Protiction (around the Building 1 156.75 3 0.25 117.56

    117.56 sft

    27

    Description No. Length (ft) Weidth (ft) Height (ft) Quantity (Cft)Stairs 3 8.5 0.75 0.75 14.34

    Copping of Perapet Wall 1 141.75 0.75 0.16 17.01

    31.35 Cft

    28

    Description No. Length (ft) Quantity (sft)

    Exam: Room Long Wall 2 14 14.00

    Exam: Room Short Wall 2 12 12.00

    Female Waiting Room Long Wall 2 12 12.00

    Female Waiting Room Short Wall 2 10 10.00

    Dispenser Room long Wall 2 12 12.00

    Dispenser Room Short Wall 2 12.00 12.00

    Store & Bath Long Wall 2 6.00 6.00

    Store & Bath Short Wall 2 11.58 11.58EPI Long Wall 2 12.00 12.00

    EPI Short Wall 2 12.00 12.00

    Male Waiting Room Long Wall 2 10.00 10.00

    Male Waiting Room Short Wall 2 12.00 12.00

    Bath Long Wall 1 7.00 3.50

    Bath Short Wall 1 6.00 3.00

    Perapet Wall (inner Side) 1 141.75 70.88

    212.96 sft

    29

    60.00 Rft

    30

    5 Nos

    315 Nos

    Khuras on roof 2'x2'x6"

    5

    Bottom khuras of brick masonry in c/s mortar 1:6,4'x2'x4.5" over 3" cem. concrete 1:4:8

    Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:3:6)

    Total:

    Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4)

    Total:

    0.5

    0.5

    0.5

    0.5

    5

    Total:

    Cast iron rain water down pipe fixed in position : 3" dia

    5 12

    Provide grey cement skirting 3/8" thick complete Extra if skirting or dado is finished with pigment

    Depth (ft)

    0.5

    0.5

    0.5

    0.5

    0.5

    0.5

    0.5

    0.5

    0.5

    0.5

    0.5

  • 8/2/2019 Estimation of Building House

    13/37

    S.

    No.

    CSR Item

    No.Description Unit Qty Rate (Rs.)

    Amount

    (Rs.)

    1 03-23-cExcavation in foundation of building, bridges

    etc complete : in hard soil or soft murumCft 2771.06 33.33 92345.41

    2 06-03-b

    Cement Concrete (brick/stone ballast, 1.5"

    to 2"/nullah shingle well graded and

    cleaned) in foundation & plinth (Ratio 1:4:8)

    Cft 791.73 73.01 57804.13

    3 07-04-a-05Pacca brick work in foundation and plinth in

    Cement, sand mortar 1:6Cft 494.83 97.89 48436.95

    4 06-22-a-02

    Damp proof of cem. conc. 1:2:4 i/c bitumen

    coat, 1 layer polythene & 2 coats bitumen

    (2" thick)

    sft 197.93 31.07 6149.68

    5 07-05-a-03Pacca brick work in ground floor Cement,

    sand mortar 1:4Cft 2236.02 111.15 248531.85

    6 06-06-a-03

    RCC in roof slab, beam, column & other

    structural members, insitu or precast. Type

    C (1:2:4)

    Cft 730.02 148.99 108764.60

    7 06-07-cSupply & fabricate M.S. reinforcement for

    cement concrete (Hot Rold Bars) Grade 40

    tonn

    e1.96 82234.55 160801.59

    8 12-07-c

    First class deodar wood wrought joinery in

    doors and windows etc. complete : 1.5"

    thick

    Sft 203 614.38 124719.14

    9 NSI

    Provide & fix 20 gauge steel chowkat for

    doors, windows & CS windows,including

    holdfast etc

    Sft 221 187.38 41410.98

    10 12-13-d

    First class deodar wood wrought joinery

    work GI wire guaze fixed to chowkat with

    1/2" strip

    sft 147 108.83 15998.01

    11 12-17-aP/F brass spring hinges to wire gauzed

    door.Each 6 219.82 1318.92

    12 12-27-aMake & fix cleats for doors & windows

    including hinges and screws.Each 9 84.91 764.19

    13 25-39-b-05

    Providing and Fixing steel windows with

    openable glazed panels With 22 SWG wire

    gauze : Glass pane 3mm

    Sft 150 430.76 64614.00

    14 12--50MS flat 1/2"x1/8" grill in windows of

    approved design.sft 150.00 140.31 21046.50

    15 03-16-aFilling, watering and ramming earth under

    floor with surplus earth from foundation, etcCft 516.24 14.26 7361.58

    16 07--30Supplying and filling sand under floor or

    plugging in wellsCft 343.78 11.86 4077.93

    #REF!

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT------------------------

    FR D.I KHAN

    Cost Estimate of Main Building

    New Construction of CD

  • 8/2/2019 Estimation of Building House

    14/37

    17 06-05-iPlain Cement Concrete including placing,

    compacting,finishing & curing (Ratio 1:4:8)Cft 343.78 81.84 28136.27

    18 10-15-e

    Provide & lay topping of concrete 1:2:4, incl.

    surface finishing & dividing in panels : 2"

    thick

    sft 1050.48 31.42 33006.50

    19 11-09-bCement plaster 1:4 upto 20' height 1/2"

    thicksft 8481.29 11.49 97449.99

    20 11-23-a-03 Distempering New surface : Three coats sft 7405.58 3.91 28934.33

    21 13-06-c-01Prepare & paint new surface door &

    windows prime coat.sft 742.00 7.14 5299.88

    22 13-06-c-02Prepare & paint new surface door &

    windows.Each Subsequent coat.sft 742.00 10.03 7439.14

    23 06-05-fPlain Cement Concrete including placing,

    compacting, finishing & curing (Ratio 1:2:4)Cft 150.60 117.70 17725.55

    24 NSIP/F Light Steel Grited in PCC (1:2:4) 3/4" x

    3/4" on Roofsft 1075.71 15.00 16135.65

    25 09--12

    2 coats of bitumen laid hot using 34 lbs. for

    %sft over roof & blinded with sand at 1 cft

    per % sft

    sft 1075.71 10.92 11751.59

    26 NSIS/F of Polythene sheet on roof in two layersas spfd:

    sft 1075.71 10.00 10757.10

    27 09-10-b

    Earth filling over roof including watering,

    ramming etc 4" thick earth filling and 1" mud

    plaster

    sft 1075.71 10.47 11262.90

    28 09--05

    Single layer of tiles 10"x5"x1.25" laid over 4"

    earth and 1" mud plaster on top of RC roof

    slab

    sft 1075.71 49.21 52937.73

    29 06-05-hPlain Cement Concrete including placing,

    compacting,finishing & curing (Ratio 1:3:6)Cft 117.56 98.46 11575.63

    30 06-05-f

    Plain Cement Concrete including placing,

    compacting, finishing & curing (Ratio 1:2:4)as a copping

    Cft 31.35 117.70 3690.23

    31 10-37-c

    Provide grey cement skirting 3/8" thick

    complete Extra if skirting or dado is finished

    with pigment

    sft 212.96 8.21 1748.85

    32 09-19-bCast iron rain water down pipe fixed in

    position : 3" diaRft 60.00 407.39 24443.40

    33 09--20

    Heads for cast iron rain water down pipe

    fixed in place including cost of clamp

    holdfast and painting

    Each 5.00 500.35 2501.75

    34 09--21Shoes, bends or offsets for cast iron ran

    water down pipe, including fixing & painting

    Each 5.00 445.79 2228.95

    35 09--15 Khuras on roof 2'x2'x6" Each 4.00 571.97 2287.88

    36 09--16

    Bottom khuras of brick masonry in c/s

    mortar 1:6,4'x2'x4.5" over 3" cem. concrete

    1:4:8

    Each 4.00 358.46 1433.84

    1374892.63Sub-Total:

  • 8/2/2019 Estimation of Building House

    15/37

    S.

    No.

    CSR Item

    No.Description Unit Qty Rate (Rs.)

    Amount

    (Rs.)

    1 14-08-b

    Providing and Fixing glazed earthen ware

    sink including set of brackets, waste pipe

    etc : 25"x18"

    Each 2 951.60 1903.20

    2 14-10-a

    Providing and Fixing glazed earthen ware

    low down flushing cistern 3 gallons capacity: White

    Each 3 1484.00 4452.00

    3 14-05-a-01

    Providing and Fixing glazed earthen ware

    WHB complete Size 22"x16" : White with

    pedestal

    Each 2 1611.05 3222.10

    4 14-06-a

    Providing and Fixing stainless steel sink

    with drain board size 48"x24", including set

    of brackets, waste pipe etc

    Each 2 2524.60 5049.20

    5 NSI

    Providing and Fixing best quality 5mm

    mirror 22"x16" size, Plastic towel rail,Plastic

    shelf 24"x5",CP soap dish.

    Set 1 1000.00 1000.00

    6 14-22-bProviding and Fixing CP stop-cock, heavy

    type : 1/2"Each 4 343.27 1373.08

    7 14-21-bProviding and Fixing CP pillar-cock, heavytype

    Each 4 417.08 1668.32

    8 14-41-bProviding and Fixing CP waste coupling :

    1.5"Each 3 299.83 899.49

    9 14-31-a

    Providing and Fixing CI floor trap including

    CI grating & concrete chamber all round :

    4"x2"

    Each 2 240.85 481.70

    10 14-48-aProviding and Fixing brass ball float valve

    1/2" diaEach 5 179.92 899.60

    11 14-55-fProviding and Fixing GI pipe & including

    specials complete 1/2" diaRft 84 153.98 12934.32

    12 14-69-b-03 P/F Polyethylene Water Tank 500 gallons(Vertical) Each 2 21928.84 43857.68

    77740.69

    Cost Estimate of Internal Water Supply of Main Building

    Sub-Total:

  • 8/2/2019 Estimation of Building House

    16/37

    S

    No.

    CSR Item

    CoadDescreption Unit Qty Rate Amount

    1 15-52

    Wiring of light point in 3/0.029 PVC

    insulated bars cable in PVC Pipe rescessed

    in wall comp

    Each 20 1592.54 31850.8

    2 15-48-c Wiring of sub main/earthing in 1 single corePVC insulated & sheathed cable : 7/0.044 Rft 150 27.99 4198.5

    3 15.24bP/F: 4' long tube light with starter, tube rod

    (Phillips) and choke.Nos 6 528.17 3169.02

    4 15.68c

    P/F: of 56" sweep capacitor type ceiling fan

    with dimmer, (Pak/Royal Fan Delux) i/c

    suspension rod and canopy etc.

    Nos 6 2191.13 13146.78

    5 15-56-b

    Supply and Erection white round globe with

    holder, gallery & 100 Watt bulb complete :

    8" dia.

    Nos 5 285.97 1429.85

    6 15-81 Supply and Fixing 20 Amp power plug Nos 5 182.7 913.5

    7 NSI

    P/F Main Board i/c switches and circuit

    breaker of best quality Complete,according

    to nomber of rooms and external wiring,

    approved by engineer incharge.

    Nos 1 10057.1 10057.1

    8 NSI

    P/Fixing: of 2 core 7/0.052 aluminum cable

    in PVC pipe of approved quality i/c

    connection from nearest source to main

    board.

    Rft 150 80.00 12000

    9 15.69aP/Fixing: 12" Sweep (Pak/Royal) Exhaust

    fan with louver.Nos. 2 1,571.40 3142.8

    10 NSIProviding and Fixing Electirc water geyser

    10 gallons best quality.No 2 10000 20000

    10 15-53

    Special earthing of iron/metal clad switches

    etc with copper wire No. 8 SWG in GI pipe

    1/2" dia

    Nos. 1 6,220.81 6220.81

    106,129.16Sub Total :

    Cost Estimate of Internal Eletrification of main Building

  • 8/2/2019 Estimation of Building House

    17/37

    S

    No.

    CSR Item

    CoadDescreption Unit Qty Rate Amount

    1 NSI

    Construction of 2'x2' or 2.5'dia BB manhole,

    upto required depth i/c 4" PCC 1:4:8 in bed,

    BB wall laid & plastered in 1:4 making

    channel inside and RCC 1:2:4 cover, 4"

    thick with 3/8" dia bars 4" C/C both side.

    Each 5.00 1700.00 8500

    2 14-37-cSupply and Fixing CI manhole cover with

    frame etc complete 24" diaEach 5.00 2742.31 13711.55

    3 23.01b

    P/L: in trench, jointing and testing 6" dia

    RCC pipe Complete as per specification

    and instruction of Engineer Incharge.

    Rft 54 98.32 5356.4736

    4 24-18-c-05

    Providing and Laying cut, joint, test,

    disinfect PVC pipe line BSS Class 'D'

    working pressure : 3" i/d

    Rft 20.00 127.59 2551.80

    5 14-34-a-02Providing and fitting CI soil pipe with : Lead

    & yarn caulked joint : 2" dia.Rft 24 264.69 6352.56

    6 14-36-a Providing and Fixing CI specials, such astees, bends etc Lead caulked joint

    Each 4 475.00 1900

    7 23-10 Septic Tank (int.Size: 7'x2'x5') complete Each 1 10,154.55 10154.55

    8 23-11 Soakage Pit (6'dia x 15' deep) complete Each 1 9,917.15 9917.15

    58444.08

    Sewerage system Of Main Building

    Total :

  • 8/2/2019 Estimation of Building House

    18/37

    1

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Long Wall

    Short wall

    2

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Long Wall

    Short wall

    3

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    1st Step 22.5" Thick

    Long Wall

    Short wall

    2nd Step 18" Thick

    Long Wall

    Short wall

    3rd Step 13.5" Thick

    Long Wall

    Short wall

    4th Step 9" Thick Wall

    Long Wall

    Short wall

    4

    Description No Width (ft) Quantity (sft)

    Long Wall

    Short wall

    5

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Long Wall

    Short wall

    Pacca brick work in ground floor Cement, sand mortar 1:4

    Damp proof of cem. conc. 1:2:4 i/c bitumen coat, 1 layer polythene & 2 coats bitumen (2" thick)

    Estimate for Type 1 Room

    Total:

    Excavation in foundation of building, bridges etc complete : in hard soil or soft murum

    Total:

    Total :

    Pacca brick work in foundation and plinth in Cement, sand mortar 1:6

    Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah shingle well graded and cleaned) in foundation &

    plinth (Ratio 1:4:8)

    Length (ft)

    Total:

    Total:

  • 8/2/2019 Estimation of Building House

    19/37

    Deduction

    D1

    W1

    6Description No Length Width (ft) Depth (ft) Quantity (cft)

    Slabe

    Room

    D1

    W1

    7

    Steel Reinforcement

    8

    Room

    9Description No Length Width (ft) Quantity (cft)

    Room

    10

    Room

    11

    Room

    12No. Width (ft) Height (ft) Quantity (sft)

    13No. Width (ft) Height (ft) Quantity (sft)

    Lintle

    Total:

    Total:

    RCC in roof slab, beam, column & other structural members, insitu or precast. Type C (1:2:4)

    Total:

    Total:

    2 coats of bitumen laid hot using 34 lbs. for %sft over roof & blinded with sand at 1 cft per % sft

    Total:

    Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4) On Roof

    Total:

    S/F of Polythene sheet on roof in two layers as spfd:

    W1

    S/F: of Steel doors 18 SWG MS sheet with angle iron frame 1"x1"x1/8", bolt, hinges & paint etc.

    Description

    Description

    Providing and Fixing steel windows with openable glazed panels With 22 SWG wire gauze : Glass pane

    3mm

    Supply & fabricate M.S. reinforcement for cement concrete (Hot Rold Bars) Grade 40

    Total:

    D1

    Total:

    Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1" mud plaster on top of RC roof slab

    S.Total:

    Total:

  • 8/2/2019 Estimation of Building House

    20/37

    14

    15

    Description Side No. Width (ft) Height (ft) Quantity (sft)

    D2

    W1

    16

    Room

    17

    Room

    18

    Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)

    Room

    19

    Description No Length (ft) Quantity (cft)

    Room

    20

    Description Side No. Length (ft) Height (ft) Quantity (sft)

    Room Long Wall

    Room Short Wall

    Ceiling Bed Room

    D1

    W1

    Total:

    Provide & lay topping of concrete 1:2:4, incl. surface finishing & dividing in panels : 2" thick

    Total:

    Prepare & paint new surface door & windows prime coat & 2nd Coat

    Total:

    Filling, watering and ramming earth under floor with surplus earth from foundation, etc

    Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:4:8)

    Cement plaster 1:4 upto 20' height 1/2" thick

    MS flat 1/2"x1/8" grill in windows of approved design.

    W1

    Width (ft)

    Total:

    Total:

    Total:

    Supplying and filling sand under floor or plugging in wells

    Deduction

    S.Total:

    Total:

    S.Total :

  • 8/2/2019 Estimation of Building House

    21/37

    21

    Description Side No. Length (ft) Height (ft) Quantity (sft)

    Room Long Wall

    Room Short Wall

    Ceiling Bed Room

    D1

    W1

    22

    Description No. Length (ft) Weidth (ft) Height (ft) Quantity (Cft)

    Plinth Protiction (around theBuilding

    23

    Description No. Length (ft) Weidth (ft) Height (ft) Quantity (Cft)

    Long Wall

    Short Wall

    24

    25

    26

    Khuras on roof 2'x2'x6"

    Bottom khuras of brick masonry in c/s mortar 1:6,4'x2'x4.5" over 3" cem. concrete 1:4:8

    Cast iron rain water down pipe fixed in position : 3" dia

    Total:

    Total:

    Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4) as a copping

    S.Total:

    Total:

    Deduction

    Distempering New surface : Three coats

    S.Total :

    Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:3:6)

  • 8/2/2019 Estimation of Building House

    22/37

    S. No.CSR Item

    No.Description Unit Qty Rate (Rs.)

    Amount

    (Rs.)

    1 03-23-c

    Excavation in foundation of building, bridges

    etc complete : in hard soil or soft murum Cft 0.00 33.33 0.00

    2 06-03-b

    Cement Concrete (brick/stone ballast, 1.5"

    to 2"/nullah shingle well graded and

    cleaned) in foundation & plinth (Ratio 1:4:8)

    Cft 0.00 73.01 0.00

    3 07-04-a-05Pacca brick work in foundation and plinth in

    Cement, sand mortar 1:6Cft 0.00 97.89 0.00

    4 06-22-a-02

    Damp proof of cem. conc. 1:2:4 i/c bitumen

    coat, 1 layer polythene & 2 coats bitumen

    (2" thick)

    sft 0.00 31.07 0.00

    5 07-05-a-03Pacca brick work in ground f loor Cement,

    sand mortar 1:4Cft 0.00 111.15 0.00

    6 06-06-a-03RCC in roof slab, beam, column & otherstructural members, insitu or precast. Type

    C (1:2:4)

    Cft 0.00 148.99 0.00

    7 06-07-cSupply & fabricate M.S. reinforcement for

    cement concrete (Hot Rold Bars) Grade 40tonne 0.00 82234.55 0.00

    8 25-47S/F: of Steel doors 18 SWG MS sheet with

    angle iron frame 1"x1"x1/8", bolt, hinges

    & paint etc.Main Gate

    sft 0 244.24 0.00

    9 12-07-cFirst class deodar wood wrought joinery in

    doors and windows etc. complete : 1.5" thickSft #REF! 614.38 #REF!

    10 NSI

    Provide & fix 20 gauge steel chowkat for

    doors, windows & CS windows,includingholdfast etc

    Sft #REF! 187.38 #REF!

    11 12-13-d

    First class deodar wood wrought joinery

    work GI wire guaze fixed to chowkat with

    1/2" strip

    sft #REF! 108.83 #REF!

    12 12-27-aMake & fix cleats for doors & windows

    including hinges and screws.Each #REF! 84.91 #REF!

    13 25-39-b-05

    Providing and Fixing steel windows with

    openable glazed panels With 22 SWG wire

    gauze : Glass pane 3mm

    Sft 0 430.76 0.00

    14 12--50MS flat 1/2"x1/8" grill in windows of

    approved design.sft 0.00 140.31 0.00

    15 07--30Supplying and filling sand under floor or

    plugging in wells Cft 0.00 11.86 0.00

    16 03-16-aFilling, watering and ramming earth under

    floor with surplus earth from foundation, etcCft 0.00 14.26 0.00

    #REF!

    #REF!

    Main Building Type v House

  • 8/2/2019 Estimation of Building House

    23/37

    17 06-05-iPlain Cement Concrete including placing,

    compacting,finishing & curing (Ratio 1:4:8)Cft 0.00 81.84 0.00

    18 10-15-e

    Provide & lay topping of concrete 1:2:4, incl.

    surface finishing & dividing in panels : 2"

    thick

    sft 0.00 31.42 0.00

    19 10--47

    Burnt brick (1st class) pavement on edge

    grouted with sand including preparation of

    bed

    sft #REF! 36.87 #REF!

    20 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick sft 0.00 11.49 0.00

    21 11-18-aCement pointing struck joints, on walls upto

    20' Hight Ratio (1:2)sft #REF! 12.74 #REF!

    22 11-23-a-03 Distempering New surface : Three coats sft 0.00 3.91 0.00

    23 13-06-c-01Prepare & paint new surface door &

    windows rime coat.sft 0.00 7.14 0.00

    24 13-06-c-02Prepare & paint new surface door &

    windows.Each Subsequent coat.sft 0.00 10.03 0.00

    25 06-05-fPlain Cement Concrete including placing,

    compacting, finishing & curing (Ratio 1:2:4)Cft 0.00 117.70 0.00

    26 09--12

    2 coats of bitumen laid hot using 34 lbs. for

    %sft over roof & blinded with sand at 1 cft

    per % sft

    sft 0 10.92 0.00

    27 NSIS/F of Polythene sheet on roof in two layers

    as spfd:sft 0.00 10.00 0.00

    28 09-10-b

    Earth filling over roof including watering,

    ramming etc 4" thick earth filling and 1" mud

    plaster

    sft 0.00 10.47 0.00

    29 09--05

    Single layer of tiles 10"x5"x1.25" laid over 4"

    earth and 1" mud plaster on top of RC roof

    slab

    sft 0.00 49.21 0.00

    30 06-05-hPlain Cement Concrete including placing,

    compacting,finishing & curing (Ratio 1:3:6)Cft 0.00 98.46 0.00

    31 06-05-f

    Plain Cement Concrete including placing,

    compacting, finishing & curing (Ratio 1:2:4)

    as a copping

    sft 0.00 117.70 0.00

    32 10-37-c

    Provide grey cement skirting 3/8" thick

    complete Extra if skirting or dado is finished

    with pigment

    sft #REF! 8.21 #REF!

    33 09-19-bCast iron rain water down pipe fixed in

    position : 3" diaRft 48.00 407.39 19554.72

    34 09--20

    Heads for cast iron rain water down pipe

    fixed in place including cost of clamp

    holdfast and painting

    Each 4.00 500.35 2001.40

    35 09--21Shoes, bends or offsets for cast iron ran

    water down pipe, including fixing & paintingEach 4.00 445.79 1783.16

    36 09--15 Khuras on roof 2'x2'x6" Each 4.00 571.97 2287.88

    37 09--16

    Bottom khuras of brick masonry in c/s

    mortar 1:6,4'x2'x4.5" over 3" cem. concrete

    1:4:8

    Each 4.00 358.46 1433.84

    #REF!Sub-Total:

  • 8/2/2019 Estimation of Building House

    24/37

    S. No.CSR Item

    No.Description Unit Qty Rate (Rs.)

    Amount

    (Rs.)

    1 14-08-b

    Providing and Fixing glazed earthen ware

    sink including set of brackets, waste pipe etc

    : 25"x18"

    Each 2 951.60 1903.20

    2 14-10-a

    Providing and Fixing glazed earthen ware

    low down flushing cistern 3 gallons capacity

    : White

    Each 1 1484.00 1484.00

    3 14-05-a-01Providing and Fixing glazed earthen ware

    WHB complete Size 22"x16" : White with

    pedestal

    Each 1 1611.05 1611.05

    4 14-06-a

    Providing and Fixing stainless steel sink with

    drain board size 48"x24", including set of

    brackets, waste pipe etc

    Each 1 2524.60 2524.60

    5 NSI

    Providing and Fixing best quality 5mm

    mirror 22"x16" size, Plastic towel rail,Plastic

    shelf 24"x5",CP soa dish.

    Set 1 1000.00 1000.00

    6 14-22-bProviding and Fixing CP stop-cock, heavy

    type : 1/2"Each 4 343.27 1373.08

    7 14-21-bProviding and Fixing CP pillar-cock, heavy

    typeEach 4 417.08 1668.32

    8 14-41-bProviding and Fixing CP waste coupling :

    1.5"Each 3 299.83 899.49

    9 14-31-a

    Providing and Fixing CI floor trap including

    CI grating & concrete chamber all round :

    4"x2"

    Each 3 240.85 722.55

    10 14-48-aProviding and Fixing brass ball float valve

    1/2" diaEach 4 179.92 719.68

    11 14-55-fProviding and Fixing GI pipe & including

    specials complete 1/2" diaRft 120 153.98 18477.60

    12 14-69-b-03P/F Polyethylene Water Tank 500 gallons

    (Vertical)Each 1 21928.84 21928.84

    54312.41Sub-Total:

    Internal Water Supply

  • 8/2/2019 Estimation of Building House

    25/37

    S No.CSR Item

    CoadDescreption Unit Qty Rate Amount

    1 15-52

    Wiring of light point in 3/0.029 PVC

    insulated bars cable in PVC Pipe rescessed

    in wall comp

    Each 15 1592.54 23888.1

    2 15-48-cWiring of sub main/earthing in 1 single core

    PVC insulated & sheathed cable : 7/0.044Rft 200 27.99 5598

    3 15.24bP/F: 4' long tube light with starter, tube rod

    (Phillips) and choke.Nos 2 528.17 1056.34

    4 15.68c

    P/F: of 56" sweep capacitor type ceiling fan

    with dimmer, (Pak/ Royal Fan Delux) i/c

    suspension rod and canopy etc.

    Nos 2 2191.13 4382.26

    5 15-56-b

    Supply and Erection white round globe with

    holder, gallery & 100 Watt bulb complete :

    8" dia.

    Nos 7 285.97 2001.79

    6 15-81 Supply and Fixing 20 Amp power plug Nos 2 182.7 365.4

    7 NSI

    P/F Main Board i/c switches and circuit

    breaker of best quality Complete,according

    to nomber of rooms and external wiring,

    approved by engineer incharge.

    Nos 1 10057.1 10057.1

    8 NSI

    P/Fixing: of 2 core 7/0.052 aluminum cable

    in PVC pipe of approved quality i/c

    connection from nearest source to main

    board.

    Rft 150 80.00 12000

    9 15.69aP/Fixing: 12" Sweep (Pak/Royal ) Exhaust

    fan with louver.Nos. 2 1,571.40 3142.8

    10 NSIProviding and Fixing Electirc water geyser

    10 gallons best quality.No 1 10000 10000

    11 15-53

    Special earthing of iron/metal clad switches

    etc with copper wire No. 8 SWG in GI pipe

    1/2" dia

    Nos. 1 6,220.81 6220.81

    78,712.60

    Internal Eletrification

    Sub Total :

  • 8/2/2019 Estimation of Building House

    26/37

    S No.CSR Item

    CoadDescreption Unit Qty Rate Amount

    1 NSI

    Construction of 2'x2' or 2.5'dia BB manhole,

    upto required depth i/c 4" PCC 1:4:8 in bed,

    BB wall laid & plastered in 1:4 making

    channel inside and RCC 1:2:4 cover, 4"

    thick with 3/8" dia bars 4" C/C both side.

    Each 4.00 1700.00 6800

    2 14-37-cSupply and Fixing CI manhole cover with

    frame etc complete 24" diaEach 4.00 2742.31 10969.24

    3 23.01b

    P/L: in trench, jointing and testing 6" dia

    RCC pipe Complete as per specification

    and instruction of Engineer Incharge.

    Rft 46 98.32 4521.7368

    4 24-18-c-05

    Providing and Laying cut, joint, test, disinfect

    PVC pipe line BSS Class 'D' working

    pressure : 3" i/d

    Rft 21.16 127.59 2699.80

    5 14-34-a-02Providing and fitting CI soil pipe with : Lead

    & yarn caulked joint : 2" dia.Rft 24 264.69 6352.56

    6 14-36-aProviding and Fixing CI specials, such as

    tees, bends etc Lead caulked jointEach 8 475.00 3800

    7 23-10 Septic Tank (int.Size: 7'x2'x5') complete Each 1 10,154.55 10154.55

    8 23-11 Soakage Pit (6'dia x 15' deep) complete Each 1 9,917.15 9917.15

    55215.04Total :

    Sewerage system Of Type 4 House

  • 8/2/2019 Estimation of Building House

    27/37

    S. No. Item No Description Nos. Length Width Hight Quantity

    1

    1 150.00 5.00 1.50 1125.00

    1125.00

    2

    20.00

    1 150.00 5.00 0.33 247.50

    267.5

    3

    1 150.00 5.00 0.16 120.00

    2 150.00 0.75 0.16 36.00

    156.00

    4

    2 150.00 1.13 0.75 254.25

    2 150.00 0.75 1.00 225.00

    479.25

    5

    2 6.00 5.00 0.75 45.00

    45.00

    6

    45.00 6 0.121

    12 4.00 4.16 2240.00 0.09

    0.21 tonn

    84 150.00 2.00 1200.00

    1200.00

    Plain Cement Concrete including placing, compacting, finishing & curring (Ratio 1:4:8 )

    2240

    For Drain Embankment (L/S)

    Coping

    TOTAL

    Supply & fabricate M.S reinforcement for cement concrete (hot rolled deformed bars Grade 60)

    Greting

    TOTAL

    TOTAL

    TOTAL

    For Side Walls

    Drain Bed

    Brick work for Side Walls 2nd Step

    Lintle on opning

    Estimate of Drain

    Earth Excavation in Irrigation Channels/Drains & disposal upto 25m & Dressing in Shingle/Gravel

    TOTAL

    Drain

    Plain Cement Concrete including placing, compacting, finishing & curring (Ratio 1:2:4)

    (PCC 1:2:4 in Drain Bed)

    Cement plaster 1:4 upto 20' height 3/4" thick

    TOTAL

    RCC in roof slab, beam, column & other structural members, insitu or precast Type C (1:2:4) lintle

    on opening

    Lintle on opning

    Task # 6

    #REF!

    For Drain Bed

    Pacca Brick Work in Foundation & Plinth in Cement, Sand Mortar (1:4)

    TOTAL

    Brick work for Side Walls 1st Step

  • 8/2/2019 Estimation of Building House

    28/37

    S. No. CSR Item No Description Unit Quantity Rate/Cft Amount

    1 03-23-d Excavation in Foundation of Building,bridges etc complete in shingle/gravel Cft 1125.00 3.78 4,254.75

    2 06-05-i

    Plain Cement Concrete including

    placing, compacting, finishing & curring

    (Ratio 1:4:8)

    Cft 267.50 81.84 21,893.32

    3 06-05-fPlain Cement Concrete including

    placing, compacting, finishing & curring

    (Ratio 1:2:4)

    Cft 156.00 117.70 18,361.20

    4 07-04-a-03Pacca Brick Work in Foundation &

    Plinth in Cement, Sand Mortar (1:4)Cft 479.25 103.64 49,669.61

    5 06-06-a-03

    RCC in roof slab, beam, column & other

    structural members, insitu or precastType C (1:2:4) lintle on opening

    Cft 45.00 148.99 6,704.51

    6 06-07-c

    Supply & fabricate M.S reinforcement

    for cement concrete (hot rolled

    deformed bars Grade 40)

    Ton 0.21 82234.55 17,242.82

    7 11-09-aCement plaster 1:4 upto 20' height 3/4"

    thickSft 1200.00 10.73 12,877.20

    131,003.42Total

    Cost Estimate of Drain

    Task # 6

    #REF!

  • 8/2/2019 Estimation of Building House

    29/37

    S No.CSR Item

    Coad

    Descreption Unit Qty Rate Amount

    1 3-23-b+3-16-a

    Excavation in foundation of building, bridges

    etc complete : in ordinary soil & Filling,

    watering and ramming earth under floor with

    surplus earth from foundation, etc

    Cft 4260.75 3.07 13080.50

    2 06-03-b

    Cement Concrete (brick/stone ballast, 1.5" to

    2"/nullah shingle well graded and cleaned) in

    foundation & plinth (Ratio 1:4:8)

    Cft 1149.75 73.01 83943.13

    3 7-04-a-5Pacca brick work in foundation and plinth in

    Cement, sand mortar 1:6Cft 1146.58 97.89 112233.66

    4 06-05-a-05Pacca brick work in ground floor Cement,

    sand mortar 1:4Cft 2787.59 111.15 309838.29

    5 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick Sft 3256.65 11.49 37418.91

    6 11-18-aCement pointing struck joints, on walls, upto

    20' height Ratio 1:2Sft 3256.65 12.74 41480.28

    7 11-25-a-03 White washing: New surface : Three coats Sft 3414.9 1.78 6074.77

    8 06-05-f

    Plain Cement Concrete including placing,

    compacting, finishing & curing (Ratio 1:2:4)

    as a Copping

    Cft 69.975 117.70 8235.81

    9 25-47-bSupplying and Fixing 18 SWG MS Sheet

    Gate with angle iron frame (2"x2"x3/16") with

    side window, lock, painting etc

    Sft 128.00 180 23040.00

    10 15.63aP/F: of gate light of approved quality and

    design.Each 2 663.90 1327.80

    636,673.14

    Cost Estimate of Compound Wall

    Sub Total:

    Task # 6

    #REF!

  • 8/2/2019 Estimation of Building House

    30/37

    S No. Descreption No length Wedth Height Qty

    1

    Boundry Wall 1 505.00 3.00 2.75 4166.25

    Gate Piller 3 3.00 3.00 3.50 94.50

    4260.75 cft

    2

    Boundry Wall 1 505.00 3.00 0.75 1136.25

    Gate Piller 3 3.00 3.00 0.50 13.50

    1149.75 cft

    3

    B/Wall 1st

    Step 1 505.00 1.50 0.60 454.50

    B/Wall 2nd Step 1 505.00 1.13 0.60 342.39

    B/Wall 3rd Step 1 505.00 1.13 0.50 284.06

    Gate Pillre 1st Step 3 2.50 2.50 3.50 65.63

    1146.58 cft

    5

    Compound Wall 1 505.00 0.75 6.33 2397.49

    Gate Piller 3 2.50 2.50 8.00 150.00

    Column 88 0.38 1.13 6.33 240.10

    2787.59 cft

    6

    Compuond Wall 1 505.00 3196.65

    Gate Piller 3 2.50 60.00

    3256.65 Sft

    Pacca brick work in ground floor Cement, sand mortar 1:4

    Total:

    8.00

    Pacca brick work in foundation and plinth in Cement, sand mortar 1:6

    Total:

    Cement plaster 1:4 upto 20' height 1/2" thick

    6.33

    Total:

    Excavation in foundation of building, bridges etc complete : in ordinary soil & Filling, watering and

    ramming earth under floor with surplus earth from foundation, etc

    Total:

    Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah shingle well graded and cleaned) in foundation

    & plinth (Ratio 1:4:8)

    Total:

    Task # 6

    #REF!

    ESTIMATE OF COMPOUND WALL

  • 8/2/2019 Estimation of Building House

    31/37

  • 8/2/2019 Estimation of Building House

    32/37

  • 8/2/2019 Estimation of Building House

    33/37

    S.No. Description No Lenght Weidth Hight Cty

    1

    Court Yard 1 200 100 1 20000 Cft

    20000 CftTotal:

    Task # 6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT---

    --------------------- FR D.I KHAN

    Estimate of Leveling & Dressing

    Earth fill in lawns including dressing & compaction with suitable earth borrowed.

  • 8/2/2019 Estimation of Building House

    34/37

    .NoCSR Item

    CoadDescription Unit Qty Rate Amount

    1 03-06-b

    Earth fill in lawns including

    dressing & compaction with

    suitable earth borrowed.

    Cft 2000 2.65 5,301.00

    5,301.00Total:

    Task # 6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT-----

    ------------------- FR D.I KHAN

    Cost Estimate of Leveling & Dressing

  • 8/2/2019 Estimation of Building House

    35/37

    S No. Descreption No Length Weidth Depth Qty

    1

    walk way Length 1 1.00 214.25 10.00 0.25 535.63

    walk way Length 2 1.00 61.00 6.00 0.25 91.50

    walk way Length 3 1.00 22.75 5.00 0.25 28.44

    655.56 cft

    2

    walk way Length 1 1.00 214.25 10.00 0.33 707.03

    walk way Length 2 1.00 61.00 6.00 0.33 120.78

    walk way Length 3 1.00 22.75 5.00 0.33 37.54

    865.34 cft

    3

    walk way Length 1 1.00 214.25 2142.50

    walk way Length 2 1.00 61.00 366.00

    walk way Length 3 1.00 22.75 113.75

    2622.25 sftTotal:

    10.00

    6.00

    5.00

    Task # 6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT-----

    ------------------ FR D.I KHAN

    Estimate of Walk Way

    Excavation in foundation of building, bridges etc complete : in ordinary soil &

    Dressing & levelling earth to designed sections Ashes, sand, silt or soft soil upto cut

    or fill 6 inches

    Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)

    Burnt brick (1st class) pavement on edge grouted with sand including preparation of

    bed

    Total:

    Total:

  • 8/2/2019 Estimation of Building House

    36/37

    S No.CSR Item

    Coad

    Descreption Unit Qty Rate Amount

    13-23-b+3-

    19-a

    Excavation in foundation of building,

    bridges etc complete : in ordinary soil &

    Dressing & levelling earth to designed

    sections Ashes, sand, silt or soft soil

    u to cut or fill 6 inches

    Cft 655.56 3.07 2012.58

    2 06-05-i

    Plain Cement Concrete including

    placing, compacting, finishing & curing

    (Ratio 1:4:8)

    CfT 865.34 81.84 70823.26

    3 10-47

    Burnt brick (1st class) pavement on edge

    grouted with sand including preparation

    of bed

    Sft 2622.25 36.87 96678.1619

    169514.00

    Cost Estimate of Walk Way

    Total:

    Task # 6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT------------------------

    FR D.I KHAN

  • 8/2/2019 Estimation of Building House

    37/37

    S No.

    CSR

    Item

    Coad

    Descreption Unit Qty Rate Amount

    124-16-c-

    06

    Providing and Laying cut, joint, test &

    disinfect GI pipe line Using light quality GI

    Pipe : 2" i/d

    Rft 186.1 233.41 43437.6

    2 14-28-cProviding and Fixing gun metal peet / gate

    valve (screwed) 2" diaEach 5.00 1,171.03 5855.15

    3 14-48-aProviding and Fixing brass ball float valve

    1/2" diaEach 5.00 179.92 899.6

    424.16c-

    01Providing and Fixing 1/2" dia GI pipe (IIL-L)or equivalent wrapping with sanitary tape

    i/c all required fittings and specials.

    Rft 120 41.5 4980

    5 14-22-bProviding and Fixing CP stop-cock, heavy

    type : 1/2"Each 2 343.27 686.54

    6 14-24-bProviding and Fixing CP bib-cock, heavy

    type : 1/2"Each 2 343.27 686.54

    56545.43

    Cost Estimate of External Water Supply

    Total:

    Task # 6

    HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF CIVIL DISPENSARY AT-----------------

    ------- FR D.I KHAN