INFORMATION BROCHURE Your opinion and comments in the process of project assessment have significant importance TBILISI RAILWAY BYPASS PROJECT The Brochure will introduce you with Tbilisi Railway Bypass project and give a brief description of some most sensitive environmental and social issues, which were identified at the project scoping stage and will require further inves- tigation. PROJECT DESCRIPTION “Georgian Railway” LLC, a Georgian state-owned railway company, is planning to implement Tbilisi Railway Bypass project for developing a new railway route bypass- ing the central area of the city of Tbilisi. The Project implies restructuring of railway structures in the Tbilisi urban area: • Tracks: cutting and complete dismantling of the present main railway line (incl. shunting areas, rail yards, rail sidings, depos and other infra structure) in the urban area between Didube in the north and Navtlughi in the south (in-between distance ca. 10 kilometres). A total of approximately 83.4 ha (out of which 73.2ha would be designated for urban development) of land should become free for new development. • Stations: (i) abandonment of Tbilisi Central Station and (ii) reahabilitation of stations Didube and Navtlughi. Navtlughi station will serve passengers trav elling to the east, and Didube those going to the west of Tbilisi. For the Project, GR is seeking international finance from the European Bank for Re- construction and Development (EBRD) and the European Investment Bank (EIB). PROJECT RATIONALE The railway section, which runs through Tbilisi, is the major thoroughfare for freight on the east-west transport corridor through Georgia. The traffic now carried by the railway is substantially transit oil traffic (both crude oil and refined product from Azerbaijan, Kazakhstan and Turkmenistan to ports on the Black Sea), a hazardous good which should not be transported through such a densely populated area. In 2008, about 10 million tonnes crude and oil products were transported which accounts for about half of the freight transported by GR. TIME FRAME, ESTIMATED COST AND PLANNING OF THE PROJECT Construction of the new railway line is preliminary estimated to take about 3 years according to the feasibility study. However, the final estimate will be made in November after obtaining the final engi- neering design and proj- ect plan. It is estimated that the existing railway structures will be dis- mantled within 6 months from the completion of construction works and launch of new rail bypass operations. “Georgian Railway” LLC is presently estimating the total budget of the Project at about 290 million Euro, not including VAT. “Georgian Railway” LLC have retained the Scientif- ic–Research and Design Institute of Transport Engineering of Ukraine (Kievgiprotrans – KGT) to undertake the technical planning of the Project. Urban development surrounds a number of the rail terminals, sidings and yards, many of which are now either obsolete or derelict. The railway acts as a major barrier to development on the northern bank as well as depressing land values in its vicinity. The Tbilisi Railway Bypass Project is closely interlinked with plans of the Tbilisi Municipality. The Bypass and the urban development are mentioned in the narrative description of the new General Plan for Perspective Development of Tbilisi. The land which becomes available between present Central station and Didube (some 73.2 ha) would be designated for urban development and the cleared rail corridor between present Central Station and Navtlughi station (ca. 6 km long, 10.2 ha) would be used as an urban traffic corridor. The municipality envisages installing a double track light rail passen- ger system (“Eurotram” type) for the greater Tbilisi agglomeration area, which would run from Mtskheta in the Northwest via Tbilisi Central, the Airport, Rustavi, to finally Gardabani in the Southeast. This Light Rail would run on basically the same route as will be abandoned by GR railway.

esTimaTeD cosT Tbilisi Railway bypass pRojecT anD … alTeRnaTives The main restricting factors for the selection of the preferred alternative route for the Tbilisi railway bypass

  • Upload
    vananh

  • View
    217

  • Download
    3

Embed Size (px)

Citation preview

Page 1: esTimaTeD cosT Tbilisi Railway bypass pRojecT anD … alTeRnaTives The main restricting factors for the selection of the preferred alternative route for the Tbilisi railway bypass

InformatIon Brochure

Your opinion and comments in the process of project assessment have significant importance

Tbilisi Railway bypass pRojecT The Brochure will introduce you with Tbilisi Railway Bypass project and give a brief description of some most sensitive environmental and social issues, which were identified at the project scoping stage and will require further inves-tigation.

pRojecT DescRipTion

“Georgian Railway” LLC, a Georgian state-owned railway company, is planning to implement Tbilisi Railway Bypass project for developing a new railway route bypass-ing the central area of the city of Tbilisi. The Project implies restructuring of railway structures in the Tbilisi urban area:

• Tracks: cutting and complete dismantling of the present main railway line (incl. shunting areas, rail yards, rail sidings, depos and other infra structure) in the urban area between Didube in the north and Navtlughi in the south (in-between distance ca. 10 kilometres). A total of approximately 83.4 ha (out of which 73.2ha would be designated for urban development) of land should become free for new development.

• Stations: (i) abandonment of Tbilisi Central Station and (ii) reahabilitation of stations Didube and Navtlughi. Navtlughi station will serve passengers trav elling to the east, and Didube those going to the west of Tbilisi.

For the Project, GR is seeking international finance from the European Bank for Re-construction and Development (EBRD) and the European Investment Bank (EIB).

pRojecT RaTionale

The railway section, which runs through Tbilisi, is the major thoroughfare for freight on the east-west transport corridor through Georgia. The traffic now carried by the railway is substantially transit oil traffic (both crude oil and refined product from Azerbaijan, Kazakhstan and Turkmenistan to ports on the Black Sea), a hazardous good which should not be transported through such a densely populated area. In 2008, about 10 million tonnes crude and oil products were transported which accounts for about half of the freight transported by GR.

Time fRame, esTimaTeD cosT anD planning of The pRojecT

Construction of the new railway line is preliminary estimated to take about 3 years according to the feasibility study. However, the final estimate will be made in November after obtaining the final engi-neering design and proj-ect plan. It is estimated that the existing railway structures will be dis-mantled within 6 months from the completion of construction works and launch of new rail bypass operations.

“Georgian Railway” LLC is presently estimating the total budget of the Project at about 290 million Euro, not including VAT.

“Georgian Railway” LLC have retained the Scientif-ic–Research and Design Institute of Transport Engineering of Ukraine (Kievgiprotrans – KGT) to undertake the technical planning of the Project.

Urban development surrounds a number of the rail terminals, sidings and yards, many of which are now either obsolete or derelict. The railway acts as a major barrier to development on the northern bank as well as depressing land values in its vicinity.

The Tbilisi Railway Bypass Project is closely interlinked with plans of the Tbilisi Municipality. The Bypass and the urban development are mentioned in the narrative description of the new General Plan for Perspective Development of Tbilisi. The land which becomes available between present Central station and Didube (some 73.2 ha) would be designated for urban development and the cleared rail corridor between present Central Station and Navtlughi station (ca. 6 km long,

10.2 ha) would be used as an urban traffic corridor. The municipality envisages installing a double track light rail passen-ger system (“Eurotram” type) for the greater Tbilisi agglomeration area, which would run from Mtskheta in the Northwest via Tbilisi Central, the Airport, Rustavi, to finally Gardabani in the Southeast. This Light Rail would run on basically the same route as will be abandoned by GR railway.

Page 2: esTimaTeD cosT Tbilisi Railway bypass pRojecT anD … alTeRnaTives The main restricting factors for the selection of the preferred alternative route for the Tbilisi railway bypass

pRojecT alTeRnaTives

The main restricting factors for the selection of the preferred alternative route for the Tbilisi railway bypass were mor-phology of the surface, financial expenditure for engineering, environmental sensitivities and social issues. “Geor-gian Railway” LLC considered the following alternative options for the Tbilisi railway bypass line:

• Alternative – “The city tunnel”: In this alternative, the railway section would pass through an underground tunnel within the limits of the city from “Didube” station to “Navtlughi”. This alternative was rejected at the initial stage of project development due to safety concerns (movement of hazardous goods under the central part of the city).

• Alternative – “The Tbilisi Sea”: In this option the major part of the bypass railway line would go through the close vi-cinity of the north-west side of the Tbilisi Sea (within 50 m). This alternative was rejected at the initial stage of project development due environmental concerns (location of the railway within the sanitary zone of the Tbilisi Sea).

• Alternative – “North with 18 gradient”: According to this longest alternative route, the Tbilisi bypass railway would go north to Zahesi settlement and pass through the northern part of the village of Norio. From Norio the route heads south along the left bank of the Lochini Khevi and joins the Baku-Tbilisi railway section at the village of Karajala. This option was rejected after preliminary cost estimation indicated high costs caused by the large number of necessary engineering structures.

• Alternative – “Central with 18 gradient”: In this alternative the Tbilisi bypass railway goes north to Zahesi settle-ment, passes Gldani Village east of Gldani lake, crosses the gorge of the Khevdzmara river and goes down to the Tbilisi Sea. The railway line passes the Tbilisi Sea to the north-west, then the track turns to the east at the village of Patara Lilo and crosses the Upper Samgori canal. The route joins the existing Kakheti railway line at Lilo settlement. There are two options for connecting this route with the existing Baku-Tbilisi railway section. • “Zero” (“do nothing”) alternative: the “zero” alternative considers retaining the present situation, i.e. vetoing the bypass railway project and retaining the existing railway line within the limits of the city.

• Proposed alternative – “Central”: At this stage Georgian Railway LLC proposes ”Central” alternative route, which has several sub-alternatives routes at some sections. ”Central” route diverts from the existing railway track, situated on the left bank of the river, at the end of Zahesi bridge and goes to the direction of Gldani lake in the east. At this section the route crosses Zahesi settlement and Gldani village. Gldani settlement will be crossed by means of 2.5 km tunnel. From Gldani Lake the route turns to the south-east, goes around the Giorgitsminda and Mukhiani settlements and enters the tunnel (app.1.2 km). At the section situated in 1.1 km distance from the Tbilisi Sea, the route turns to the east and goes along the Tbilisi Sea. The minimum distance from

the Tbilisi Sea is 900m. The route passes by the village of Patara Lilo (in 500m distance) from the south and turns sharply to the east. At this point the route crosses Visitors’ Zone of Tbilisi National Park. From Patara Lilo the route goes to the east almost in parallel to Kakheti highway – in 500-600m distance from the north. Construction of a new freight station is planned at this section. The route joins the existing Kakheti railway track in 1km distance from the new freight station. The route crosses different engineering communications of the city (gas pipeline, water pipeline, sewage, power transmission lines) at several places and also a branch of Saguramo’s 700mm central gas pipeline.

Page 3: esTimaTeD cosT Tbilisi Railway bypass pRojecT anD … alTeRnaTives The main restricting factors for the selection of the preferred alternative route for the Tbilisi railway bypass

Key issues iDenTifieD anD scope of esia sTuDy

ESIA of Tbilisi Railway Bypass Construction project is based on and guided by: the Georgian legislation; EBRD’s Environmental and Social Policy (2008); social and environmental requirements of EIB; international conventions (the Arhus Convention) that Georgia has ratified; European Union Council Directive 85/337/EEC on the assessment of the effects of certain public and private projects on the environment, as amended by Council directive 97/11/EC (Council of the European Union, 1985; 1997); and IFC’s Stakeholder Engagement (2007) manual.

ESIA of the Tbilisi Railway Bypass project is carried out by Consortium made of GDC Solution Ltd, CENN (Caucasian Environmental NGO Network) and APLR (Association for Protection of Landowners Rights).

project area of influence and some sensitive issues related to the proposed project

A corridor with 1 km on both sides is defined as a project influence area with increased level of detail research in the near field of the bypass alignment and the city area and extension where reasonably needed. As for the social area of influence, considering direct and indirect social impacts of the proposed project, it comprises the whole country.

possible miTigaTion measuRessome Key issues of The pRoposeD cenTRal RouTe

To develop relevant compensation and mitigation mea-sures in cooperation with the Ministry of Environment and Natural Protection.

protected areas: The route will pass by the traditional use zone of Tbilisi National Park at a distance of 45. At Tbilisi Sea it crosses the Visitors’ Zone of the National Park at two locations. The lengths of the crossings are 1300m and 360m.

Measures will be developed in cooperation with relevant agencies to avoid, mitigate and compensate the impact.

flora and fauna: Construction and operation of the railway track will have a certain impact on some endan-gered species of flora and fauna, which are included in the “Red List” of Georgia (2006).

Construction of double-sided concrete wall in sensitive areas.

Development of an Oil Spill Emergency Response Plan. It will be reasonable to equip the service department of the sensitive section of the railway with oil catching booms and train them in use of booms in case of oil spills. Observation of the safety rules by the personnel. Preventive checks of the equipment.

Observation of the rules of keeping materials, especially explosives and toxic substances.

Detailed guidelines for handling such large-scale acci-dents should be developed. The relevant services shall be trained periodically.

pollution and emergency situations: Ingress of chemi-cal substances or oil products into water or flash pollution of water during possible emergency situations (in case of accidents) as a result of damping of tanks loaded with oil or oil products.

Special attention should be paid to prevent the penetra-tion of oil products into the Tbilisi Sea, canals of the Samgori irrigation system and other less important water bodies (dry ravines, small rivers).

Such accidents will have severe consequences for the Tbilisi population as well as for the population of Garda-bani district receiving irrigation water though the lower main canal of the upper Samgori irrigation system fed by Tbilisi sea.

noise: “Hot spots”, i.e. those populated areas where, for certain reasons, it will be impossible to keep recommend-ed distances between the railway and the nearest private or public buildings, shall be identified.

Noise barriers like strips of greenery and technical means such as acoustic screens, embankments and other will be used on the basis of acoustic calculations.

Page 4: esTimaTeD cosT Tbilisi Railway bypass pRojecT anD … alTeRnaTives The main restricting factors for the selection of the preferred alternative route for the Tbilisi railway bypass

possible miTigaTion measuRessome Key issues of The pRoposeD cenTRal RouTe

Social and Economic Influences: Along the proposed Central route and its sub-alternatives extensive physical and economic resettlement is anticipated (the physical resettlement involves the change of place of residence, and economic the loss of income sources). A partial split of the social network is anticipated in the densely popu-lated areas crossed by the route.

Intensive relations and consultations with the popula-tions living along the route and private companies will be required to develop a relevant resettlement action plan, property acquisition/ compensation strategy and methods and actions for livelihood rehabilitation.

A mechanism for consideration and response to lawful complaints to ensure timely consideration of claims and complaints of the population affected by the project and implementation of mitigation measures should be devel-oped before the commencement of the process of land acquisition.

Implementation of actions for the rehabilitation of social network measures through the provision of alternative livelihoods or other mitigation measures.Issues and procedures for the compensation of damage caused to informal land users as a result of loss of im-movable property and source of income shall be consid-ered.

The next stages of ESIA process will be Impact Assessment and Environmental and Social Management Planning.

public DisclosuRe anD sTaKeholDeR involvemenT

According to Georgian legislation, as well as to international regulations, public consultations and public hearings are key components of environmental and social impact assessment (ESIA) process.

Stakeholder engagement is carried during two stages of ESIA of Tbilisi Railway Bypass project:

• environmental and social impact assessment – August, 2009; and • public hearing of the ESIA report – November, 2009.

“Georgian Railway” LLC will communicate detailed information about public participation opportunities in the process of ESIA of Tbilisi Railway Bypass project by means of publications in Georgian newspapers - “24 Saati” and “Kviris Palitra”.

how can you get involved?

Your involvement in the process of the environmental and social impact assessment is very important. Georgian Rail-way requests your active participation in this process. You are kindly asked to send your comments and complaints to the following address:

Mr. Dimitri KemoklidzeHead of Projects and Development Department Georgian Railway LLC15, Queen Tamar Ave.0112 Tbilisi, Georgia Tel.:+995 32 56 31 59Fax: +995 32 56 48 57E-mail: [email protected]

Additional information about the project can be obtained from Georgian Railways LLC.