Upload
jcaldanab
View
216
Download
0
Embed Size (px)
Citation preview
8/12/2019 Estimate Construction Waste China
1/7
Resources, Conservation and Recycling 74 (2013) 2026
Contents lists available at SciVerse ScienceDirect
Resources, Conservation and Recycling
journal homepage: www.elsevier .com/ locate / resconrec
A model for estimating construction waste generation indexfor building project in China
Jingru Li, Zhikun Ding, Xuming Mi,Jiayuan Wang
College of Civil Engineering, Shenzhen University, Shenzhen 518060, China
a r t i c l e i n f o
Article history:
Received 7 October 2012
Received in revised form 17 February 2013Accepted 20 February 2013
Keywords:
Waste generation pergross floor area
(WGA)
Theamount of constructionwaste
Material waste rate (MWR)
Building
China
a b s t r a c t
The increasing construction and demolition (C&D) waste causes both cost inefficiency and environmental
pollution. Many countries have developed regulations to minimize C&D waste. Implementation ofthese
regulations requires an understanding ofthe magnitude and material composition ofwaste stream. Con-
struction waste generation index is a useful tool for estimating the amount of construction waste and
can be used as a benchmark to enhance the sustainable performance ofconstruction industry. This paper
presents a model for quantifying waste generation per gross floor area (WGA) based on mass balance
principle for building construction in China. WGAs for major types ofmaterial are estimated using pur-
chased amount ofmajor materials and their material waste rate (MWR). The WGA for minor quantities
of materials is estimated together as a percentage of total construction waste. The model is applied to
a newly constructed residential building in Shenzhen city of South China. The WGA of this project is
40.7 kg/m2 , and concrete waste is the largest contributor to the index. Comparisons with transportation
records in site, empirical index in China and data in other economies reveal that the proposed model is
valid and practical. The proposed model can be used to setup a benchmark WGA for Chinese construction
industry by carrying out large-scale investigations in the future.
2013 Elsevier B.V. All rights reserved.
1. Introduction
Constructionand demolition (C&D) waste hasbecome an impor-
tant issue not only from the perspective of cost efficiency but
also due to its adverse effect on the environment. In an attempt
to protect the environment and to improve sustainability of the
construction industry, many countries and regions have devel-
oped various regulations and initiatives to minimize C&D waste.
In the United Kingdom, the Code for Sustainable Homes makes on-
site waste minimization, sorting and recycling obligatory (United
Kingdom Government Department for communities and Local
Government, 2006). Several regulations have existed to control
C&D waste in Hong Kong (Tam and Tam, 2008a). As an exam-
ple, waste management plan is compulsory for all construction
projects in Hong Kong since 2003 (Tam, 2008b). The Brazilian Envi-
ronmental Protection Agency published Resolution 307 in 2002,
whichrequires alllocal authorities to prepare andexecute plans for
the sustainablemanagementof C&Dwaste (Brazilian Government-
Environmental Protection Agency, 2002). In mainland China, the
Administration of Urban Construction Garbage was promulgated
in 2005 to promote a series of local regulations on C&D waste
Corresponding author. Tel.: +86 755 26732840; fax: +86 755 26732850.
E-mail address: [email protected] (J. Li).
management (Ministry of Housing and Urban-Rural Development
of the Peoples Republic of China, 2005).
However, implementation of these provisions requires an
understanding of the magnitude and material composition of the
waste stream(Cochran and Townsend,2010). A constructionwaste
management plan, for example, requires contractors to estimate
the quantity of total construction waste and its main components
at the planningphase, which willfacilitate waste reduction, reusing
and recycling during the construction process.
A number of researchers were aware of this situation and con-
centrated on quantification of C&D waste in various countries
(Llatas, 2011). These studies can be divided into two categories:
studies that determine an overall C&D waste generation amount
in a region (e.g. Bergsdal et al., 2007; Cochran et al., 2007;
Franklin Associates, 1998; Kofoworola and Gheewala, 2009; Yost
and Halstead, 1996) and those that measure C&Dwaste generation
index at project sites (e.g. Bossink and Brouwers, 1996; Formoso
et al., 2002; Poon et al., 2004a; Skoyles, 1976). In the second
category, most of researchers discussed the construction waste
generation index as estimation of this index is more difficult than
demolition waste generation index.
The constructionwaste generationindex is identifiedas a mean-
ingful tool to promote construction waste management. It can be
applied to predict the amount of construction waste generated in a
project, which will assist project stakeholders to prepare appro-
priate waste management plans. Comparing the index between
0921-3449/$ seefrontmatter 2013 Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.resconrec.2013.02.015
http://localhost/var/www/apps/conversion/tmp/scratch_3/dx.doi.org/10.1016/j.resconrec.2013.02.015http://localhost/var/www/apps/conversion/tmp/scratch_3/dx.doi.org/10.1016/j.resconrec.2013.02.015http://www.sciencedirect.com/science/journal/09213449http://www.elsevier.com/locate/resconrecmailto:[email protected]://localhost/var/www/apps/conversion/tmp/scratch_3/dx.doi.org/10.1016/j.resconrec.2013.02.015http://localhost/var/www/apps/conversion/tmp/scratch_3/dx.doi.org/10.1016/j.resconrec.2013.02.015mailto:[email protected]://www.elsevier.com/locate/resconrechttp://www.sciencedirect.com/science/journal/09213449http://localhost/var/www/apps/conversion/tmp/scratch_3/dx.doi.org/10.1016/j.resconrec.2013.02.0158/12/2019 Estimate Construction Waste China
2/7
J. Li et al. / Resources, Conservation and Recycling74 (2013) 2026 21
differentprojects canhelp project stakeholders to gainmore insight
about their construction waste management performance and to
review the effectiveness of construction waste management prac-
tices. Moreover, the amount of construction waste generated in a
region or a country can also be estimated by employing the index
and construction area (Cochran et al., 2007).
However, the consideration on construction waste manage-
ment is fairly negligible in mainland China. Low awareness of
sustainable construction accounts for the deficiency of data about
the amount of construction waste either at a macroscopic level
or a microscopic level. A widely cited construction waste gener-
ation index, 5060 kg/m2, was provided by Lu (1999) based on
empirical estimationwithout detailed interpretation. However, the
waste generation index will vary in a wide range with construc-
tion technology, structure type, building occupancy, and especially
management level (Li et al., 2010). The above empirical index
reveals limited information for project stakeholders for under-
standingthe magnitudeand compositionof constructionwaste and
preparing an appropriate construction waste management plan. In
particular, the culture and common practices of the construction
industry in China may not be entirely similar to other economies.
Thus, an approach to the measurement of a construction waste
generation index for the Chinese construction industry should be
investigated.Given the situation, the objective of this research is to present a
practical and simple model for measuring the construction waste
generation index for building projects in China. The study is struc-
tured in four parts. The first part includes a literature reviewon the
quantification of construction waste. The second section describes
the approach to measuringthe waste generation index for building
construction. Then, the method is illustrated using a newly con-
structed residential building project in Shenzhen, China. Finally, all
the findings are discussed in detail and conclusions are drawn.
2. Reviews
2.1. Main constructionwaste generation indexes
Amounts of construction waste generation have received sig-
nificant attention because this information is a prerequisite to
developing appropriate solutions for managing waste. A variety
of researchers have developed different methodologies to quan-
tify construction waste. As mentioned above, these studies can
be divided into two categories: studies that determine an overall
waste generation amount in a region and those that measure the
waste generation index at a project site.
Of the second category, some studies investigated material
waste rates (MWR),which are thepercentages of waste materialto
purchased material or required by the design, to indicate thewaste
generation level of construction projects. For an example, Skoyles
(1976) measured the MWRof major materials in UK and found thepercentages of waste materials ranged from 2 to 15%, on average
double the losses generally assumed. Enshassi (1996) found from
a study in the Gaza strip that the materials loss was approximately
3.611%. Formoso et al. (2002) indicated that the waste rate of
materials in theBrazilian building industry was fairlyhigh and var-
ied widely across different projects. Bossink and Brouwers (1996)
revealed that approximately 110% of the purchased construction
materials (by weight) was left as waste. In Hong Kong, Poon et al.
(2004b) identified the material waste levels of various trades for
public housing and private residential buildings. Tam et al. (2007)
investigated waste levels of five major types of construction mate-
rial in terms of subcontracting arrangements and project types.
Other studies derived a waste generation index using the vol-
ume or quantity of waste generated per gross floor area (WGA).
Poon et al. (2004a) calculated the WGAs for two public housing
construction sites as 0.14 m3/m2 and 0.21m3/m2. In China, Luet al.
(2011) performed a total of five measurement exercises to inves-
tigate the WGAs of four typical trades. Llatas (2011) developed a
model to estimate WGA and applied to a dwelling project in Spain.
A WGA of 0.1388 m3/m2 was obtainedfrom the case study. Another
study in Spain derived a WGA as 0.1075m3/m2 from a newly
constructed residential building that generated waste of approx-
imately 172.2m3 on a total of 1600m2 floor area (Sols-Guzmn
et al., 2009).
2.2. Measurementmethod of these constructionwaste generation
indexes
In addition to different units of measure, the above studies also
adopted varied approaches to measuringconstruction waste gener-
ation indexes. They reached their objectives using three different
approaches: (1) field monitoring; (2) interviews and (3) material
balance.
The first approach collects data by conducting field monitoring
because direct records of constructionwaste amounts are generally
unavailable at sites. Skoyles (1976) and Enshassi (1996) measured
the MWRby comparing contractors records of delivery with mea-
surements of finished work. Formoso et al. (2002) investigated theoccurrence of material waste in Brazil by direct observation of sites.
Bossink and Brouwers (1996) sorted and weighed all construction
waste materials at five housing constructionsites. This method was
also adopted by Lu et al. (2011). Poon et al. (2004a) conducted
regular site observations at construction sites and collected data
by visual inspection, tape measurements and truck load records.
The quantities of waste were calculated by multiplying the truck
volume and the total number of trucks used for waste disposal.
Apart from this type of hard methodfor measuringwaste, soft
methods, such as questionnaire surveys and interviews, have also
been adopted (Lu et al., 2011). For example, Poon et al. (2004b)
identified the waste levels of various trades based on site observa-
tions and interviews with professionals. Tam et al. (2007) collected
the waste levels of five major types of construction material frominterviews with project managers.
Another approach quantifies the construction waste generation
index based on the material balance principle. This approach con-
siders the fact that after the building materials are delivered to
the site, part of the materials are incorporated into the building
structure during construction, and the remainder is discarded as
wreckage waste or package waste on site (Cochran and Townsend,
2010). Sols-Guzmn et al. (2009) identified three categories of
waste in the construction process: demolished, wreckage and
package waste. They quantified these three types of waste by mul-
tiplying the quantities of material used in structural elements with
the corresponding transformation coefficients. The material used
in each structural elements is obtained from the budget document.
These coefficients were estimated from the Andalusian Construc-tion Costs Database and the guidelines of an expert team. Llatas
(2011) further applied the approach to quantify the amount of
waste expected in eachbuilding element according to the European
Waste List.
To quantify construction waste by carrying out field observa-
tion, on-site sorting, weighing and monitoring related documents
is a relatively accurate method but requires a great deal of time
and human resources. This approach requires field monitoring to
continue until the end of construction activity in order to obtain
the total quantity of waste generated on the site. This require-
ment is one key reason that only a few sample construction sites
were investigated in previous researches (Bossink and Brouwers,
1996; Poon et al., 2004a). Furthermore, our previous experimental
research also found that on-site sorting and weighing occupy too
8/12/2019 Estimate Construction Waste China
3/7
22 J. Li et al. / Resources, Conservationand Recycling74 (2013) 2026
much space and manpower and thus would encounter difficulties
forbulky waste streams on large constructionsites (Lu etal.,2011).
Measuringwasteas thedifference between theamountof materials
effectively purchased and the actual quantities used in building is
adopted by Skoyles (1976) and Enshassi (1996). However, Skoyles
(1976) also pointed out that bills of quantities in tendering doc-
uments only provided basic measurements of a project and the
measurement had to be repeated between 15 and 20 times during
the building process. The repeated measurements greatly increase
the difficulty in monitoring waste by comparing contractors deliv-
ery records with measurements of finished work.
By contrast, quantifying the construction waste based on the
material balance principle is a more practical substitute for large
construction sites. In particular, this method can estimate the gen-
eration index for each waste component, in additionto total waste,
which facilitates stakeholders to develop their waste reuse or
recycling plans. However, the process of gaining reasonable trans-
formation coefficients such as those in Sols-Guzmns study is a
critical problem. In the next section, the details of our approach
will be presented.
3. Methodology
Thissectionpresentsa newmodel to quantifyingWGA for build-
ing construction based on the mass balance principle. The model
costs less time and manpower to collect data than many exist-
ing methods, which makes it suitable to be used in conducting
large scale statistical investigations. The application of the model
includes five phases:
(1) Listing the major types of construction material;
(2) Investigating the purchased amount of these major materials;
(3) Investigating the actual MWRof each type of material listed in
phase 1;
(4) Estimation of the percentage of the remaining wastes;
(5) Calculating the total WGA and the WGA for each type of mate-
rial.
The first thing to notice is that this study will measure the WGA
by weight, although the majority of the aforementioned studies
calculated WGA by volume (Llatas, 2011; Poon et al., 2004a; Sols-
Guzmn et al., 2009). Poon et al. (2004a) collected data by visual
inspection, which is more convenient to calculate the quantities
of waste by volume. Llatas (2011) stated that volume is a valuable
datum that facilitates estimation of the size and numbers of con-
tainers. However, the density of the mixed waste may vary broadly
withvarious compositions,whichwill cause difficulty in comparing
the waste generation levels between different projects. Moreover,
the landfill fee in Chinais applied by weight using weight machines
at landfills. Thus, WGA by weight is considered in this study.
3.1. Listing the major types of constructionmaterial
Although buildings across the world is varied in building
structure and construction techniques, typical construction waste
components include concrete, brick and block, steel reinforcement,
timber, cement and mortar, ceramic tile, plastic and cardboard
packaging materials, etc. (Bossink and Brouwers, 1996; Formoso
et al., 2002; Poon et al., 2004b; Tam et al., 2012). However, the
proportions of these components may vary within a large range in
different countries and regions.
In China, multilayer or high-risebuildings comprisethe majority
of newly constructed buildings due to the highpopulation densities
of cities. The reinforced concrete structure is most popular in these
buildings. Thus, waste material is mainly sourced from concrete
Table 1
The major materials using in building construction projects.
No. Material Note
1 Concrete The major material of concrete work
2 Steel bar The major material of concrete work
3 B rick and block The m ajor mater ialo f m aso nr y work
4 Timber formwork The major material ofconcrete work
5 Mortar The major material of w et trades of finishing w ork
6 Tile The major material of wet trades of finishing work
work, masonry work, timber formwork, and the wet trades of fin-
ishing work, suchas screeding, plastering andtile laying (Poonetal.,
2004b). Other small amounts of waste come from water and wire
pipes, packaging material and other small goods. It is obvious that
the major types of construction materials, such as concrete, timber
formworkand steel bar, are the major source of constructionwaste
(Li et al., 2010).
For the popular reinforced concrete framework buildings in
China, the major materials consist of concrete, steel bar, brick and
block, timber formwork, mortar and tile, as listed in Table 1.
3.2. Investigating purchased amounts of major materials
Theamountof materialpurchased canbe collected fromthe pur-
chasing records of finished projects or from the budget documents
of ongoing projects. The amount in the budget document gener-
ally includes normal material loss during construction and thus is
close to the actual purchased amount. Because most types of mate-
rial are purchased batch by batch in China, a situation in which
the purchased material will significantly exceed the demand will
rarely occur. Even if this situation occurs, the extra amount can be
returned to the supplier. Thus, this situation is not considered in
this study.
3.3. Investigating actual MWR
MWR is measured by dividing the amount of waste by either
the amount of purchased material (Bossink and Brouwers, 1996;
Enshassi, 1996; Poon et al., 2004a; Skoyles, 1976; Tam et al., 2007)
or the amount of material required by the design (Formoso et al.,
2002). The two possible rates will differ to a very small extent
unlessthe rate is quite huge, forexample,73.7% forcement in Brazil
(Formoso et al., 2002). To facilitate the intuitive understanding and
estimation of project stakeholders, MWRis evaluated as the ratio
of waste material to purchased material expressed as a percentage
in this study.
As mentioned in Section 2.2, two different methods have been
adopted to measure MWR: hard methods, such as field monitor-
ing (Bossink and Brouwers, 1996; Enshassi, 1996; Formoso et al.,
2002; Poon et al., 2004a; Skoyles, 1976), and soft methods, suchas interviews (Poon et al., 2004b; Tam et al., 2007). In this study,
the MWR on each site is obtained from the project managers
estimation. In China, the project manager is the core person of
a construction project, who is fully responsible for project cost,
schedule and quality. Thus, project managers estimation is gen-
erally believable. In addition, there are other benefits to obtain an
estimation of the MWRfrom the project manager.
(1) It can minimize time and cost involvement of investigation. As
discussed above,field monitoring takes a great deal of time and
human resourcesand thereforeencounters difficulties for bulky
waste streams on large construction sites, such as multilayer or
high-risebuildings in China. In contrast, interviews withproject
managers and related managers have been verified as a valid
8/12/2019 Estimate Construction Waste China
4/7
J. Li et al. / Resources, Conservation and Recycling74 (2013) 2026 23
alternative approach (Poon et al., 2004b; Tam et al., 2007), and
can be used to collect data during a short time period.
(2) Actual MWRinstead of normal MWRis obtained. Although the
normal MWRcan be acquired from the Construction Norm (Lu
et al., 2011), our previous study revealed that MWRs in actual
construction practice significantly differ with that in the Con-
structionNorm (Lietal.,2010). Thus, usage ofthe actualMWRis
moreaccurate for estimating theconstructionwaste generation
index.
3.4. Estimation of the percentage of remaining wastes
In addition to the waste generated from the major materi-
als listed in first phase, there are also numerous types of small
quantities of waste, such as cardboard packaging, plastic pile, iron
wire, and so on. These remaining wastes include numerous cate-
gories, but comprise only a small part of the total waste by weight.
Among them, a small part of valuable waste, such as cardboard
packaging, may be voluntarily collected by site workers and resold
to secondhand buyers. Other remaining wastes may generally be
mixed together and are difficult to reuse or recycle on-site. Thus,
estimation of the remaining wastes by category is time- and cost-
consuming and unworthy.
In this study, these remaining wastes are estimated together by
the project manager. It is assumed to be a certain percentage of the
total waste. Our previous study revealed that the waste generated
from major materials accounts for nearly 90% of the total construc-
tion waste (Li et al., 2010). Bossink and Brouwers (1996) echo the
estimationthat the majorityof constructionwaste, excludingpack-
ing waste and small fractions waste, weighs nearly 90% of the total
amount of constructionwaste in the Netherlands. It canbe deduced
thatin thissituation these remaining wastes occupy approximately
10% of the total waste.
3.5. Calculation of WGA
In the first step, the total construction waste generated on site
is calculated using Eq. (1):
WG =
n
i=1
Mi ri +W0 (1)
where WG refers to thetotal constructionwaste generated fromthe
project by weight (kg), Mi means the purchased amount of major
material i in the identified list by weight (kg); ri i s the MWR of
major material i; W0 is the remaining waste; n is the number of
major material types.
In the second step, the total WGA is calculated using Eq. (2):
WGA =WG
GFA (2)
where GFA means the gross floor area of the building project (m2).
For the third step, the WGA for major material i is calculated
using Eq. (3):
WGAi =(Mi ri)
GFA (3)
4. Case study
Themethod presentedin the above section is applied to a newly
constructed building project in Shenzhen, a metropolis in South
China. The project is a residential building withreinforced concrete
framework. The detailed characteristics are illustrated in Table 2.
To collect related data, our research team visited the con-
struction site twice during March 2009. On the first visit, a short
interview was carried out with the project manager and site man-
agers. The objective of the interview was to introduce our research
and to explain the data we needed. We explained the implica-
tions of these data and then discussed the availability of these data
with the managers. One week later, our research team returned
with a questionnaire and collected all the required data from the
project manager. The project manager first confirmed that the
major materials on this project included the six types of mate-
rials as listed in Table 1. He provided the purchased amount of
thesemajor materialsfrom procurement records andestimatedthe
MWR for each major material. He also agreed that the remaining
wastes accounted for approximately 10%of the total waste. Table 2
presents the data collected.
It should be noted that the amounts of purchased material
(shown in the third column) are measured in different units; for
example, concrete is measured in cubic meters (m3) and form-
work in square meters (m2). These measurements are original data
drawn from procurement records. To calculatethe mass of WG, the
amount is uniformly transformed into tons using the density and
thickness of each material, if necessary.
Our research team calculated the total WGA and the WGA for
each major material (illustrated in Table 2) and then discussed the
results withthe project manager. The project manager verified that
the method is easy to understand and implete in site.It can be noted from Table 2 that the total WGA is 40.7kg/m2.
Concrete is a major contributor to total WGA, accounting for 43.5%
of the total WGA. The second major generator is timber formwork,
at 7.6 kg/m2, followed by steel, brick and block and mortar. WGA
for tile is least at only 0.5 kg/m2.
5. Discussion
5.1. WMR and WGAfor each major material
Concreting is a major building construction process. Shenzhen
requires theuse of ready-mixed concrete in the entireconstruction
projects. Concrete waste is mainly sourced from excessive order-ing, overfilling the formwork, broken formwork and redoing due
to poor quality. It is estimated that the WMRof concrete on this
site is only 1%, far lower than the 3% in Netherlands (Bossink and
Brouwers, 1996) and 35%in HongKong(Poon et al., 2004b). How-
ever, the amount of purchased concrete accounts for 85% of the
total amount of purchased material by weight. Due to this, con-
crete waste generated per gross floor area occupies nearly half of
the total WGA.
Due to inexpensive, lightweight and easy to cut, timber form-
work is widely used in construction projects in China. Timber
formwork is a type of revolving material, which will not be incor-
porated into the building during the construction process. It will
be discarded as waste, generally after being revolved five to ten
times. Thus, its waste material amount is quite large. In addition,the WGA for timber formwork is in directrelationto the number of
reuses times. If the timber formwork revolves only five times due
to low durability, then it will generate twice the amount of waste
as it revolved ten times. In this project, the timber formwork was
revolved an average of seven times. However, approximately 20%
of the timber formwork revolved only 34times andwas reused in
other projects after finishing concrete work. The MWRis estimated
as 80%.
Steel reinforcement bars are one of the principle materials in
building construction. Steel bar waste is mainly generated from
on-site cutting. A small amount results from abortive work. In this
project, the MWR of steel bar was 3.0%, slightly lower than the
35% in Hong Kong (Poon et al., 2004b). The project manager also
asserted that the MWRwas at a relatively low level in China. The
8/12/2019 Estimate Construction Waste China
5/7
24 J. Li et al. / Resources, Conservationand Recycling74 (2013) 2026
Table 2
WGA fora residential building in Shenzhen.
General information Building occupancy: residential building
Structure form: reinforced concrete framework
Underground/aboveground floors: 2/32
Gross floor area (GFA): 76117.7 m2
Commencement date/investigation date: May 2007/March 2009
Project progress Foundation: finished Building structure: finished
Masonry: finished Plastering: finished
Tiling: ongoing
Material MWR (%) Amount purchased Amount purchased (t) WG (t) WGA (kg/m2)
Concrete 1.0 56,011 m3 134426.4 1344.2 17.7 43.5%
Steel bar 3.0 10,204 t 10204.0 306.1 4.0 9.8%
Brick and block 5.0 6511 m3 5208.8 260.4 3.4 8.4%
Timber formwork 80.0 60,020 m2 720.2 576.1 7.6 18.7%
Mortar 4.0 6500 t 6500.0 260.0 3.4 8.4%
Tile 4.0 45,568 m2 1002.5 40.1 0.5 1.2%
2786.9 36.6 90.0%
W0 309.7 4.1 10.0%
Total WGA 3096.5 40.7 100.0%
low MWRof steel bar leads to a low WGA, although its purchased
amount is the second largest. Its WGA is 4.0 kg/m2, only half of the
WGA for timber formwork.Brickand block aremainly usedin masonrywork. A combination
of causes can lead to the waste of brick and block. Most loss hap-
pens during delivery, handling, and transportation, suchas damage
during loading and unloading, broken brick and block due to over-
stacking, cuttingdue to lackof modularcoordination, over-ordering
brick and block leftover as waste. The MWRfor brick and block can
vary within a wide range depending on the skill and responsibil-
ity of the workers. On the investigated site, the MWRis 5.0%, far
higher than 2.0% from the Shenzhen Construction Norm. Although
the site managers required the subcontractor workers to save as
much material as possible, the workers still paid little attention to
theirperformance. Thelow price of thematerial andlow awareness
about the environmental management are two critical reasons for
this apathy.Controlling the use of mortar on site is relatively difficult
because this material is used in several processes, for example,
masonry work, plastering and floor rendering. In situ production
of mortar commonly exceeds the demand because it is difficult to
accurately estimate the amount needed by each work team. The
surplus mortar will become waste. Waste is also generated when
mortar overflowsthe wheelbarrow during transportation. Dropped
mortar during masonry and plastering will also be wasted if not
reclaimedin time. In this site, the MWRof mortarwas 4.0% at aver-
age, similar to that in Hong Kong (Poon et al., 2004b) and the UK
(Skoyles, 1976). Fortunately, the constructionindustryin Shenzhen
has begun usingready-to-use mortar as required since 2011, which
will help to reduce mortar waste.
In China, residential buildings are commonly sold without fineindoor finishing. Tile is applied only in public spaces, such as cor-
ridors and stairways. Tile waste is mainly sourced from cutting to
fit the building modular. The MWRin this project was estimated
at 4.0%, lower than the 68% in Hong Kong (Poon et al., 2004b).
According to the managers, many irregular spaces and a variety of
paving patterns caused the high waste level, though the WGA for
tile was considerably smaller.
Of thesix major materials, concrete, brick andblock, mortarand
tile are inert materials, which are suitable for producing recycled
construction materials, such as recycled brick, recycled aggregate,
recycled concrete, and so on. Their generation accumulates up to
60% of the total waste in this project. However, this type of waste
is commonly deposited in public landfills in China. On one hand,
the original material is dissipating, coupled with the extensive
Table 3
Actual amount of waste material from records.
Material Amount
recorded
Amount
recorded (t)
WGA
(kg/m2)
Steel bar 390 t 390 5.1
Timber formwork 42,000 m2 504 6.6
Mixed waste 260 m3 390 5.1
development and redevelopment of the city. On the other hand,
there is not yet enough capacity to recycle such a large quantity of
inert construction waste. More effort has to be devoted to fill this
gap in China.
Wasted steel bar and large panel timber formwork will be col-
lected and resold to secondhand buyers or recycling companies.
Wastesteel bar generallycosts halfof the originalmaterial. Because
of its high value, more than 90% of waste steel bar is elaboratelyrecycled.
5.2. Comparison with transportation records in the project
The selected building project was at a finishing stage during
the investigation. Masonry and plastering work had been finished,
and 90% of the tiling work had been completed. As the majority of
the construction work was finished, our research team reviewed
the resale and transportation records to find the actual amounts of
waste material and the data are illustrated in Table 3. To measure
by weight, the amount is uniformly transformed into tons using the
density and thickness of each material, if necessary. The density of
mixed waste is assumed to be 1.5 ton/m3.
The recorded amount of steel is 390 ton and it is higher thanthe 306 ton estimated by our method. This deviation derives from
the slight underestimation of the MWR by the project manager.
The actual MWRdeduced from the records is up to 3.8%. However,
the difference between the two WGAs is only 1.1kg/m2, which
accounts for 23% of the total WGA. This deviation has a limited
effecton the total WGA. As mentionedabove, it is difficultto find an
extremely accurate waste rate unless the entire work is monitored
up to the end and all related documents are collected. Estimation
of MWRby project manager is not very precise but is a practical
alternative.
The amount of timber formwork in the record is approximately
504 ton, lower than our estimate of 576 ton. Two reasons may
causethis difference. First, our estimationincludes all timber form-
work waste, such as deteriorated large panels and cutting margins.
8/12/2019 Estimate Construction Waste China
6/7
J. Li et al. / Resources, Conservation and Recycling74 (2013) 2026 25
Table 4
Calculation of normal WGA.
Material Normal
MWRa (%)
The amount
purchased (t)
WG (t) WGA
(kg/m2)
Concrete 1.5 134426.4 2016.4 26.5
Steel bar 4.5 10204.0 459.2 6.0
Brick and block 2.0 5208.8 104.2 1.4
Timber formwork 100 720.2 720.2 9.5
Mortar 2.0 6500.0 130 1.7
Tile 2.0 1002.5 20.0 0.3
45.4
W0 5.0
Total WGA 50.4
a Data source: Shenzhen Construction Norm.
However, only large panels of timber formwork are sold and
recorded. The off-cut scrap is commonly collected and transported
together with other mixed waste without records. In addition, the
amount of resold timber formwork is derived from approximate
statistics, as this material is usually sold in bulk.
Themixedwastein this project includes wasteconcrete, broken
brick and block, off-cut tile, waste mortar, timber scrap, packag-
ing waste and plastics. The recorded amount is far lower than
the estimated amount. The total estimated amount of concrete,brick and block, mortar and tile is close to 2000 ton. After discus-
sion with the project manager and site visits, the possible reasons
for this discrepancy are summarized. First, waste concrete from
excessive ordering is usually poured out around the construction
site. Other concrete from overfilling or broken formwork is cleared
as backfill material, although this practice is prohibited by Con-
struction Specifications in China. Similarly, surplus mortar and
dropped waste mortar are also collected as backfill. A small quan-
tity of broken brick and block is used to backfill the foundation.
The majority of these types of waste are illicitly reclaimed on site.
This situation demonstrates that the estimation of construction
waste by reviewing related records is not a feasible approach in
China.
5.3. Comparisonwith empirical data in China
As mentioned above, a popular empirical WGA in China is
5060 kg/m2, given by Lu (1999). The WGA in this case is lower
than the empirical data. Although Lu (1999) did not mention the
measurement method of the empirical data, it is found that the
data is close to the normal WGA. It can be seen from Table 4 that
thenormalWGA is50.4kg/m2, which is calculated usingthe normal
MWRs from the Shenzhen Construction Norm.
Compared with Table 2, it is obvious that the normal MWRs for
concrete andsteelare higherthanthe actualMWRs of the surveyed
site. A main reasonis thatthesetwo types of materials arerelatively
expensive and also account for a large part of purchased material.
Thus, enormous attention is paid to reducing waste from deliveryand handling. The WGA for concrete in Table 2 is only 17.7kg/m2,
8.8 kg/m2 less than that in Table 4. Similarly, WGA for steel bar in
Table 2 decreases by 2.0 kg/m2. Moreover, as 20% of timber form-
work is reused in other projects, the WGA for timber formwork
in this case also decreases by 1.9kg/m2 from normal estimation.
Although the actual MWRs for brick and block, mortar and tile
are higher than the normal MWR, the increase in WGA is fairly
small. As a whole, the actual WGA is 20% lower than the normal
WGA.
5.4. Comparisonwith research data in other economies
Comparison between countries can help with benchmarking
and identifying good waste management practices (Lu et al., 2011).
However, comparing the WGA of different economies is difficult
due to the different construction technologies and work proce-
dures involved and because distinct measurement approaches
were adopted in each of them (Formoso et al., 2002). Despite
the lack of comparability between most of the WGAs in various
countries, comparison between the indexes with certain similarity
still can bring some enlightenment.
For this purpose, several WGAs in different economies are care-
fully selected by reviewing previous studies, as shown in Table 5.
All these three WGAs are obtained from concrete framework res-idential buildings and measured with the same units. The WGAs
in America and Norway result from previous empirical survey of
waste composition and generation. Seo and Hwang (1999) calcu-
lated WGA in Korea using a similar method with our approach.
In our case, the total WGA is slightly lower than that in America
and Korea but is higher than Norway. Because the building struc-
tures and occupancies are similar, the deviation of total WGA may
be contributed to differentconstruction practices and management
level. Table 5 further compares the WGA for each material in dif-
ferent countries and regions. Obviously, the WGAs for concrete
and brick in each economy are similar, but the WGAs for steel
and timber vary significantly. As mentioned above, timber form-
work is more popular than metal formwork in China. The timber
waste will decrease if the former can be widely substituted by thelatter. This may be the reason that timber waste in Norway is dis-
tinctly lower than in other countries. Steel waste is mainlysourced
from cutting steel bar on-site. If preassembled steel reinforcement
is applied, steel waste may be drastically reduced. This practice
may contribute to the remarkably low WGA for steel in America
and Norway.
In summary, comparisons with transportation records reveal
that the method presented in this study is valid and practical to
estimate the actual WGA. At the same time, comparisons between
empirical data in China and WGA in other economies indicate that
the waste generation level in China is decreasing as more atten-
tion being devoted to preventing the production of waste material.
But the WGA in China canstill be improved by adopting low-waste
technologies (Poon et al., 2003) or incentive system (Tam and Tam,
2008a).
Table 5
WGAs of residential buildings in other countriesor regions.
Countries Total WGA (kg/m2) WGAi(kg/m2)
Concrete Brick Steel Timber Mortar Tile
Americaa 43.7 22.9 0.9 6.4
Norwayb 30.7 19.11 0.48 2.75
Koreac 47.8 15.87 4.53 5.17 3.84 0.35 0.33
a Data sources: Cochran et al. (2007).b Data sources: Bergsdal et al. (2007), including office buildings and apartment buildings.c
Data sources: Seoand Hwang (1999), including concrete frame buildings, but notlimited to residential buildings.
8/12/2019 Estimate Construction Waste China
7/7
26 J. Li et al. / Resources, Conservationand Recycling74 (2013) 2026
6. Conclusions
This research proposes a model for quantifying WGA for build-
ing construction in China. Purchased amount and actual MWRs of
major material are used to estimate total WGA and WGA for each
major component. The WGA for other minor quantities of material
is estimated together to simplify the estimation approach. A newly
constructed residential building in Shenzhen is used as case study
to illustrate the model, and the WGA of this case is 40.7kg/m2. Of
that amount, concrete represented 43.5%, timber formwork 18.7%,
steel bar 9.8%, brick and block 8.4%, mortar 8.4% and tile 1.2%. The
data are compared with on-site transportation records, empirical
datain China, and datain othereconomies. Comparisons withthese
data revealthat the methodis valid andpractical forestimating the
actual WGA.
The proposed method is particularly suitable to be used for
conducting large-scale statistical investigations, as the model is
simple and related data is easy to obtain. By conducting statistical
investigation on a regional or a national scale, abundant knowl-
edge about construction waste magnitude and composition can be
obtained and used to develop appropriate waste management pol-
icy. Based on the investigation result, a benchmark WGA, which
will guide construction industry in taking more effective waste-
reduction practices, can be set up. It is the objective of our futureresearch.
A limitation of the proposed method is that the reliability of
WGA mainly relies on the accuracy of WMRprovided by project
manager. Requiring the project managers to explain their data in
detail may be a feasible solution to avoid significant deviation.
Moreover, themodelonly provides a rough estimation of construc-
tion waste generation and composition. If accurate estimation is
required, material should be further subdivided in term of building
elements or other characteristics like Llatas research. Of course,
the requirement will increase the complexity of this model.
Acknowledgments
The authors are very grateful for the constructive commentsprovided by the two anonymous reviewers. The present study is
partof the Humanities and Social Sciences research project entitled
Construction project stakeholders attitude and behavior toward
construction waste minimization and transformation mechanism
(11YJAZH047) funded by the Ministry of Education of the Peoples
Republic of China.
References
Bergsdal H, Bohne RA, Brattebo H. Projection of construction and demolition wastein Norway. Journal of Industrial Ecology 2007;11(3):2739.
Brazilian Government Environmental Protection Agency (CONAMA). Resolu-tion No. 307. Environmental Protection Agency, Brasilia, Brazil. ; 2002 [accessedMarch 2012].
Bossink BAG, Brouwers H.J.H. Construction waste: quantification and sourceevaluation. Journal of Construction Engineering and Management ASCE1996;122:5560.
Cochran K, Townsend T, Reinhart D, Heck H. Estimationof regional building-relatedC&D debris generationand composition: case studyfor Florida, US. WasteMan-agement 2007;27(7):92131.
Cochran kM, Townsend T G. Estimating construction and demolition debrisgeneration using a materials flow analysis approach. Waste Management2010;30(11):224754.
Enshassi A. Materials control and waste on building sites. Building Research andInformation 1996;24(1):314.
Formoso CT, SoibelmanL, CesareCD, Isatto EL.Material waste in building industry:main causesand prevention. Journal of Construction Engineering and Manage-ment 2002;128(4):31625.
Franklin Associates. Characterization of building related construction and demo-lition debris in the United States. EPA-530-R-98-010. USA: US EnvironmentalProtection Agency; 1998.
Kofoworola OF,GheewalaSH.Estimation ofconstructionwastegeneration andman-agement in Thailand. Waste Management 2009;29(2):7318.
LiJ , Mi X, Ding Z, Wang J. Investigationand analysis on generation rate of construc-tion waste. Construction Ecomomics 2010;1:836 (in Chinese).
Llatas C. A model for quantifying construction waste in projects according to theEuropean waste list. WasteManagement 2011;31(6):126176.
Lu K A. St at us quo and com pr eh ens ive utilization o f re fuse pro duce d fr omconstruction and removal of building in China. Construction Technology1999;28(5):445 (in Chinese).
LuW , Yuan H, Li J, Hao JL, Mi X, Ding Z. An empirical investigation of constructionand demolition waste generation rates in Shenzhen city, South China. WasteManagement 2011;31(4):6807.
Ministry of Housing and UrbanRural Development of the Peoples Republic of
China. Provisions on the administration of urban construction garbage, China,;2005 [accessedMarch 2012].
Poon CS, Yu ATW, Ng LH. Comparison of low-waste building technologies adoptedin public and private housing projects in Hong Kong. Engineering, Constructionand Architectural Management 2003;10(2):8898.
PoonCS, Yu ATW,WongSW, Cheung E. Management of constructionwaste in pub-lic housing projects in Hong Kong. Construction Management and Economics2004a;22(7):67589.
Poon CS, Y u ATW, Ja illon L. Reducing building waste at construction si tesin Hong Kong. Construction Management and Economic 2004 b;22:67589.
Seo S, Hwang Y. An estimation of construction and demolition debris in Seoul,Korea:wasteamount, type, andestimating model.Journal of theAir andWasteManagement Association 1999;49(8):9805.
Skoyles ER. Material wastage: a misuse of resources. Building Research and Practice1976;4(4):23243.
Sols-Guzmn J, Marrero M, Montes-Delgado MV, Ramrez-de-Arellano A. A Span-
ish model for quantification and management of construction waste. WasteManagement 2009;29(9):25428.TamVWY,ShenLY,TamCM.Assessingthelevelsof materialwastageaffected bysub-
contractingrelationshipsand projectstypeswith theircorrelations.BuildingandEnvironment 2007;42:14717.
Tam VW Y, Tam CM. Waste reduction through incentives: a case study. BuildingResearch and Information 2008a;36(1):3743.
Tam VWY.On theeffectivenessin implementing a waste-management planmethodin construction. Waste Management 2008b;28(6):107280.
TamVWY,Le KN,ZengSX. Reviewon wastemanagement systems inthe Hong Kongconstruction industry: use of spectral and bispectral methods. Journal of CivilEngineering and Management 2012;18(1):1423.
United Kingdom Government Department for Communities and Local Govern-ment. Code for Sustainable Homes. London, United Kingdom: The Departmentfor Communities and Local Government; 2006.
Yost P,HalsteadJ. A methodology forquantifying thevolume of constructionwaste.WasteManagement and Research 1996;14(5):45361.
http://www.mma.gov.br/port/conamahttp://www.mma.gov.br/port/conamahttp://www.fjjs.gov.cn/Xsgl/Wzxs/tabid/156/ArticleID/1385/Default.aspxhttp://www.fjjs.gov.cn/Xsgl/Wzxs/tabid/156/ArticleID/1385/Default.aspxhttp://www.mma.gov.br/port/conamahttp://www.mma.gov.br/port/conama