8/12/2019 EST05 -USGC Baslien and Productivity http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 1/15  AACE International’s 52 nd  Annual Meeting and ICEC’s 6th World Congress on Cost Engineering, Project Management, and Quantity Surveying © 2008 AACE International “What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” By Bruce Bradley – Fluor Re-counted by Habib Hajjar – SNC-Lavalin

EST05 -USGC Baslien and Productivity

Embed Size (px)

Citation preview

Page 1: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 1/15

 AACE International’s 52nd Annual Meeting

and ICEC’s 6th World Congress on Cost Engineering, Project Management, and Quantity Surveying© 2008 AACE International

“What is the U.S. Gulf Coast Baseline when

Estimating Site Productivity?”

By Bruce Bradley – Fluor

Re-counted by Habib Hajjar – SNC-Lavalin

Page 2: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 2/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International2 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

• Introduction

• Background

• History

• USGC Man-hour Development

• Site Productivity Efficiency

• Potential Conflicts

• Alignment• References

Page 3: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 3/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International3 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Introduction

• Bruce Bradley, Manager of Estimating, Fluor, Houston, TX

• 28+ years in the EPCM industry

• Current department staff 70+• BBA in Business Management, Texas A&M University, 1979

• Three primary employers during this timeframe, all of whombelieved their  baselines were the baseline!

• Two events during career stand out:

– Two simultaneous projects near Baytown, TX

– JV arrangement for a Louisiana project

Page 4: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 4/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International4 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Background

• “USGC Manhours” an overused phrase 

• Most everyone nods affirmatively signifying “agreement ”  

• In reality, not a single, identifiable baseline

• No one really knows what the “1.0” is 

• Not a deep, dark secret, but instead, a well knownmisunderstanding!

Page 5: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 5/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International5 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

History

• First significant oil discovery in Corsicana, TX, 1894

• Well known Spindletop discovery near Beaumont, TX1901

• Oil discovery led to oil production, which led to oilrefining

• First refineries located near coastal areas for portaccess and shipping

• Engineering & Construction companies for refineriesdeveloped

• Supply and manufacturing companies created

Page 6: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 6/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International6 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Texaco founder Joseph S.

"Buckskin Joe" Cullinan 

Page 7: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 7/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International7 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

U.S. Gulf Coast

Page 8: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 8/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International8 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

USGC Manhour Development – con’t. 

***Speculation***

• Construction labor data monitored and accumulated

– Possibly by the world’s first “cost engineer ”! 

• Metrics probably  included manhours to install primaryrefinery components:

– A cubic yard of concrete

– A ton of steel

– A piece of equipment– A foot of pipe

– A foot of wire/cable and conduit

– A tagged instrument

– Other items as required

Page 9: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 9/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International9 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

USGC Manhour Development – con’t. 

***Speculation***

• New projects may have reviewed this data in theirplanning stage

• Individual tasked with this activity may have been thefirst “cost estimator ”! 

• As competing companies were developing, they mayhave performed their own “historical data analysis”,

thus determining their own manhour “baselines”  • Construction workers undoubtedly migrated back and

forth between projects

• New and improved construction methods and

technology

Page 10: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 10/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International10 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

USGC Manhour Development – con’t. 

***Speculation***

• New information and old probably mixed together

• Data not easily “normalized ”  

• Each company adopted their own data as “unique”based on their management style and executionmethods

• Results became each individual company’s standardreference point

• Each company believed their  data to be the USGCbaseline!

Page 11: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 11/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International11 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Site Productivity Efficiency

• As construction moved away from the gulf coast, anew problem arose

• Reliance on local construction workforces unfamiliarwith refinery intricacies

• Determination may have been the need to makeadjustments to their baselines

• Result would have become a “site productivityadjustment ”  

• Upon new project completion, actual effort hoursmay have been compared to their baseline

Page 12: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 12/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International12 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Potential Conflicts

• Larger, more complex projects not as “simple” asbaseline history

• Companies working together in “Joint Venture”arrangements probably  had different baselines

• JV projects may have been segregated among thepartners by units or geographical boundaries

• Each developed their own baseline man-hours,agreeing to develop a site productivity adjustmenttogether

d

Page 13: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 13/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International13 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Alignment

• More in-depth analysis began taking place

• Focus into sub-categories became more prevalent– Ex.: Instead of total  CY of concrete, looked at:

• Paving

• Simple foundations

• Complex foundations

• Elevated structures• JV efforts could analyze their respective baselines

against one another by digging into more detail

C d & C C C

Page 14: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 14/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International14 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

Alignment – con’t. 

• Further productivity analysis into:– availability of work force

– skill of work force– work space congestion / area per worker

– working at grade versus elevated work

– weather conditions

– work hours per week

– single shifts versus double– turnaround versus non-turnaround

– grass roots versus revamps

• Today’s common estimating software systems allowsfor easier collaboration

AACE I t ti l’ 52 d A l M ti & ICEC’ 6th W ld C

Page 15: EST05 -USGC Baslien and Productivity

8/12/2019 EST05 -USGC Baslien and Productivity

http://slidepdf.com/reader/full/est05-usgc-baslien-and-productivity 15/15

 AACE International’s 52nd  Annual Meeting & ICEC’s 6th World Congress 

© 2008 AACE International15 

“What is the U.S. Gulf Coast Baseline when Estimating Site Productivity?” 

References

1. Brown, Stephen P. A. and Mine Yucel,

“Do Higher Oil Prices Still Benefit Texas? ,”

Federal Reserve Bank of Dallas, www.dallasfed.org,OCT-05.

2. Koottungal, Leena, Survey Editor,

“2007 Worldwide Refining Survey,”

Oil & Gas Journal, 24-DEC-07.

3. Ramos, Mary G., “Oil and Texas: A Cultural History,”

The Texas Almanac, www.texasalmanac.com,

2000- 2001 Edition.