Upload
hermione-demetra
View
67
Download
2
Tags:
Embed Size (px)
DESCRIPTION
Eskom’s Electrification Programme. Presented By Ms Ayanda Noah Group Executive: Distribution Division 15 March 2012 National Electrification Indaba. Eskom at a glance. Average cost per unit of electricity Generation c/kWh. +. Transmission (at high voltages) - PowerPoint PPT Presentation
Citation preview
Eskom’s Electrification Programme
Presented By
Ms Ayanda NoahGroup Executive: Distribution Division
15 March 2012
National Electrification Indaba
Eskom at a glance
Average cost per unit of electricity
Generationc/kWh
+Transmission (at high voltages) Contribution for asset use and technical losses
+Distribution (at high to lower voltages)Contribution for asset use and technical losses
+Administration and billing (service)By type of service received
NERSA approved costs and returns recovered from tariffs
Residential
Industry, commercial and farming
Mining, Metros and large industry
High voltage
Medium voltage
Lowvoltage
2
3
Contents
Looking back, what have we achieved and what have we learnt?
Electrification – There has been two distinct eras of installation: pre-2000 and post-2000
Number of annual grid connections
Thousand
Cost per connection
R '000
1994
12.413.4
8.79.0
6.06.15.24.14.55.05.96.37.08.1
1995
8.7
20092008200720062005200420032002200120001999199819971996
8.6
Self-funded and managed programme• Eskom exceeded the government's target
of 1.75M connections between 1994 and 2000
• Connection every 30 seconds, pole every 10 seconds, 200M cable every minute
• Connection costs steadily came down
Government funded programme• Energy White Paper (1998)• The numbers of annual connections by
Eskom have dropped, partly due to– Increased investment in infrastructure– The stringent processes that need to be
followed
Total investment from 1991 – 2011 to date: R7.5 bn and 4.1 m people electrified
4
12.4 11.8
2010 2011
5
Electrification – schools and clinics
Close to 400 clinics electrified since 1991
More than 11 000 schools electrified since 1991
The improvement of local infrastructure through strong impact projects is a key corporate social investment priority for Eskom
Summary of key learning points
Upfront planning (If you fail to plan, you plan to fail) - Pool of opportunities - Mobilise delivery machine - Overall flexibility
Fund your plan
Technology innovation - Standardisation - Life-cycle planning * - Growing needs of communities *
Community involvement - Engagement and resourcing
6
Summary of key learning points
Impact of electrification policy - Proclaimed vs. unproclaimed areas - Multiple stands dwellers
Importance of continuous improvement - new challenges, new solutions
Integrated approach in infrastructure development - Housing, Roads, Sewage and Electrical infrastructure
7
Key Learning Points
DESIGN AND CONSTRUCTION
Plans were prepared in advance (even though the situation on the ground may change) to allow for:• compilation of business plan and to identify technologies• determination of annual target cost per connection and
connection numbers
Previous Distribution approach was reactive - based on applications• this was changed to a target-driven approach ensuring
compliance to connection numbers and cost per connection
• villages approached at least 18 months in advance and interim designs tabled
• annual planning was done, 10 months before start of new year & included targets for the next 3 yrs; showing line lengths; transformer quantities & connection numbers
• Revisit plan every 3months & adjust, connections were moved b/n regions if there were areas that were not performing because of various reasons
TECHNICAL REQUIREMENTSAfter determining load requirements, supply options were investigated, i.e. single-phase (cheaper & sufficient for low demand); three-phase (more expensive but caters well for higher demand areas) or a combinationCurrently, three-phase networks are generally implemented as history has taught us that households soon acquire more appliances and consumption increases as a result
Equipment to be fully utilised
Lessons learnt when Eskom was given a target of 1,75m connections in the 90’s
Key Learning Points (Cont.)
• Optimal design and technology options were employed to reduce cost per connection, especially for deep rural areas
• planting of poles to be optimal by increasing spans to allowable technical standards
• Full loading of transformers planned
• Revenue management and metering, we are installing split metering in problematic areas currently (only ready-board and keypad installed in the house)
9
Key Learning Points (Cont.)
LOAD REQUIREMENTS
• Rural demand was initially planned at 3kVA/household, this was later revised to 1,5kVA initial ADMD and 3kVA final ADMD
• Load research was conducted over a number of years in different areas which resulted in further reductions to 0,6kVA initial ADMD and 1,5kVA final ADMD for rural areas
• The Division of Revenue Act of 2010/11 prescribed that the minimum load to be planned per household should be 1kVA
SUCCESS
• The success of achieving 300,000 connections per annum is attributed to up-front planning which entailed
• Identification of projects up-front (enabling fast tracking and/or deferment)
• Flexibility
10
11
Contents
Going forward, what is the picture?
NATIONAL ELECTRIFICATION BACKLOG
3,4million backlog in the country-% per province indicated on map,Source DoE
KZN 24%
LIMPOPO 9%
GAUTENG
MPUMALANGA7%NORTH WEST
6%
FREE STATE6%
NORTHEN CAPE1%
WESTERN CAPE 6%
EASTERN CAPE 19%
12
13
There is still a significant backlog of between 3.4 million households, of which 1.8 million are in proclaimed Eskom areas
SOURCE: Eskom
0.9
3.4
2.5
Households without electricity
Municipalities
Eskom
Proclaimed areas
1.8m (72%)
Unproclaimed areas
0.7m (28%)
Number of households without access to electricity1
Millions, 2011
1 The figure is based on an assumed increase in households without access at a rate of between 2-5% per annum, from 2.5 million in 2005, including Eskom’s areas of supply. The certainty in these figures is low and checks will have to be done in the pre-engineering.
Number of households without access to electricity in Eskom areas1
Millions, 2011Total = 2.5m
APPROXIMATE FIGURES
There are estimated 3.4m households without electricity1, 2.5m of which are in Eskom’s areas
Of the 2.5m households in Eskom’s areas, 1.8m are in proclaimed areas
14
Positive social impact
• Economic development – electricity creates value-adding opportunities and improves the GDP
• Health impact, e.g. reduced exposure to smoke from fires used for cooking
• Education impact e.g. improved ability to study after dark
• Improving gender equality e.g., women not having to spend hours a day collecting firewood
• Better public safety e.g. street lighting and reduced illegal connections
Electrification Funding and Social Impact
• With current DoE funding of ~R1.7bn p.a., universal access will only be achieved in SA in 2033/4 (proclaimed and un-proclaimed), against the original government target of 2014
• Past experience shows that this can be achieved much sooner given the Eskom’s National Electrification programme experience of the 90’s
• Availability of adequate upfront funding is key for facilitation of National Planning and Implementation
In terms of the White Paper on Energy, the responsibility for funding and planning of the Integrated National Electrification Programme is the function of the Dept. of Energy (DoE) with Eskom being the implementing agent in own areas of supply.
15
Contents
How could we move forward?
Electrification Challenges
Expectations exceed available funds - Current funding levels allow for connections of 150,000 households per annum
Universal Access to electricity by 2014 – funding inadequate
Integrated planning involving all stakeholders (Provincial, DME, Eskom & Municipalities) – delays implementation
Aligned policies to facilitate implementation process not in place(e.g. un-proclaimed, land usages)
Harmonisation of government initiatives e.g. electrification and housing programmes
High costs to electrify deep rural areas due to lack of bulk infrastructure
• There is a need to strengthen old electrification networks because they were configured to accommodate initial ADMD whereas saturation is reached sooner than planned.
Illegal connections in areas not electrified (which are in close proximity to electrified areas) because they have not been prioritised according to municipalities’ IDPs.
• Eradication of the backlog by grid connection will result in an additional 2TWh to the grid, new capacity required
16
Electrification Challenges (Cont.)
Electrification plans to be integrated, as far as possible, to optimise costs so that a bigger footprint can be reached
FBE – Free Basic Electricity cannot be extended to un-electrified customers
Some flexibility to be allowed on the plan, i.e. to manage the plan at programme level rather than project level
Creation of bulk infrastructure during the year of implementation gives rise to unnecessary delays – funding for infrastructure should be made available upfront.
17
Way Forward
Funding
• The fiscus to make adequate funding available in order to achieve UA• Exploring and partnering with all stakeholders to identify additional
funding for electrification
Integration
• Electrification plans to be integrated, as much as possible, to optimise costs so that a bigger footprint can be reached
• Electrification should form part of housing development in order not to increase backlog
Flexibility
• Allow flexibility iro implementing the plan, i.e. to manage the plan at programme level rather than project level
• Optimal utilisation of existing funding in order to get more connections i.e. allow conversion of schedule 6 and 7 grants as per DoRA
18
Siyabonga
19