19
Eskom’s Electrification Programme Presented By Ms Ayanda Noah Group Executive: Distribution Division 15 March 2012 National Electrification Indaba

Eskom’s Electrification Programme

Embed Size (px)

DESCRIPTION

Eskom’s Electrification Programme. Presented By Ms Ayanda Noah Group Executive: Distribution Division 15 March 2012 National Electrification Indaba. Eskom at a glance. Average cost per unit of electricity Generation c/kWh. +. Transmission (at high voltages) - PowerPoint PPT Presentation

Citation preview

Page 1: Eskom’s  Electrification Programme

Eskom’s Electrification Programme

Presented By

Ms Ayanda NoahGroup Executive: Distribution Division

15 March 2012

National Electrification Indaba

Page 2: Eskom’s  Electrification Programme

Eskom at a glance

Average cost per unit of electricity

Generationc/kWh

+Transmission (at high voltages) Contribution for asset use and technical losses

+Distribution (at high to lower voltages)Contribution for asset use and technical losses

+Administration and billing (service)By type of service received

NERSA approved costs and returns recovered from tariffs

Residential

Industry, commercial and farming

Mining, Metros and large industry

High voltage

Medium voltage

Lowvoltage

2

Page 3: Eskom’s  Electrification Programme

3

Contents

Looking back, what have we achieved and what have we learnt?

Page 4: Eskom’s  Electrification Programme

Electrification – There has been two distinct eras of installation: pre-2000 and post-2000

Number of annual grid connections

Thousand

Cost per connection

R '000

1994

12.413.4

8.79.0

6.06.15.24.14.55.05.96.37.08.1

1995

8.7

20092008200720062005200420032002200120001999199819971996

8.6

Self-funded and managed programme• Eskom exceeded the government's target

of 1.75M connections between 1994 and 2000

• Connection every 30 seconds, pole every 10 seconds, 200M cable every minute

• Connection costs steadily came down

Government funded programme• Energy White Paper (1998)• The numbers of annual connections by

Eskom have dropped, partly due to– Increased investment in infrastructure– The stringent processes that need to be

followed

Total investment from 1991 – 2011 to date: R7.5 bn and 4.1 m people electrified

4

12.4 11.8

2010 2011

Page 5: Eskom’s  Electrification Programme

5

Electrification – schools and clinics

Close to 400 clinics electrified since 1991

More than 11 000 schools electrified since 1991

The improvement of local infrastructure through strong impact projects is a key corporate social investment priority for Eskom

Page 6: Eskom’s  Electrification Programme

Summary of key learning points

Upfront planning (If you fail to plan, you plan to fail) - Pool of opportunities - Mobilise delivery machine - Overall flexibility

Fund your plan

Technology innovation - Standardisation - Life-cycle planning * - Growing needs of communities *

Community involvement - Engagement and resourcing

6

Page 7: Eskom’s  Electrification Programme

Summary of key learning points

Impact of electrification policy - Proclaimed vs. unproclaimed areas - Multiple stands dwellers

Importance of continuous improvement - new challenges, new solutions

Integrated approach in infrastructure development - Housing, Roads, Sewage and Electrical infrastructure

7

Page 8: Eskom’s  Electrification Programme

Key Learning Points

DESIGN AND CONSTRUCTION

Plans were prepared in advance (even though the situation on the ground may change) to allow for:• compilation of business plan and to identify technologies• determination of annual target cost per connection and

connection numbers

Previous Distribution approach was reactive - based on applications• this was changed to a target-driven approach ensuring

compliance to connection numbers and cost per connection

• villages approached at least 18 months in advance and interim designs tabled

• annual planning was done, 10 months before start of new year & included targets for the next 3 yrs; showing line lengths; transformer quantities & connection numbers

• Revisit plan every 3months & adjust, connections were moved b/n regions if there were areas that were not performing because of various reasons

TECHNICAL REQUIREMENTSAfter determining load requirements, supply options were investigated, i.e. single-phase (cheaper & sufficient for low demand); three-phase (more expensive but caters well for higher demand areas) or a combinationCurrently, three-phase networks are generally implemented as history has taught us that households soon acquire more appliances and consumption increases as a result

Equipment to be fully utilised

Lessons learnt when Eskom was given a target of 1,75m connections in the 90’s

Page 9: Eskom’s  Electrification Programme

Key Learning Points (Cont.)

• Optimal design and technology options were employed to reduce cost per connection, especially for deep rural areas

• planting of poles to be optimal by increasing spans to allowable technical standards

• Full loading of transformers planned

• Revenue management and metering, we are installing split metering in problematic areas currently (only ready-board and keypad installed in the house)

9

Page 10: Eskom’s  Electrification Programme

Key Learning Points (Cont.)

LOAD REQUIREMENTS

• Rural demand was initially planned at 3kVA/household, this was later revised to 1,5kVA initial ADMD and 3kVA final ADMD

• Load research was conducted over a number of years in different areas which resulted in further reductions to 0,6kVA initial ADMD and 1,5kVA final ADMD for rural areas

• The Division of Revenue Act of 2010/11 prescribed that the minimum load to be planned per household should be 1kVA

SUCCESS

• The success of achieving 300,000 connections per annum is attributed to up-front planning which entailed

• Identification of projects up-front (enabling fast tracking and/or deferment)

• Flexibility

10

Page 11: Eskom’s  Electrification Programme

11

Contents

Going forward, what is the picture?

Page 12: Eskom’s  Electrification Programme

NATIONAL ELECTRIFICATION BACKLOG

3,4million backlog in the country-% per province indicated on map,Source DoE

KZN 24%

LIMPOPO 9%

GAUTENG

MPUMALANGA7%NORTH WEST

6%

FREE STATE6%

NORTHEN CAPE1%

WESTERN CAPE 6%

EASTERN CAPE 19%

12

Page 13: Eskom’s  Electrification Programme

13

There is still a significant backlog of between 3.4 million households, of which 1.8 million are in proclaimed Eskom areas

SOURCE: Eskom

0.9

3.4

2.5

Households without electricity

Municipalities

Eskom

Proclaimed areas

1.8m (72%)

Unproclaimed areas

0.7m (28%)

Number of households without access to electricity1

Millions, 2011

1 The figure is based on an assumed increase in households without access at a rate of between 2-5% per annum, from 2.5 million in 2005, including Eskom’s areas of supply. The certainty in these figures is low and checks will have to be done in the pre-engineering. 

Number of households without access to electricity in Eskom areas1

Millions, 2011Total = 2.5m

APPROXIMATE FIGURES

There are estimated 3.4m households without electricity1, 2.5m of which are in Eskom’s areas

Of the 2.5m households in Eskom’s areas, 1.8m are in proclaimed areas

Page 14: Eskom’s  Electrification Programme

14

Positive social impact

• Economic development – electricity creates value-adding opportunities and improves the GDP

• Health impact, e.g. reduced exposure to smoke from fires used for cooking

• Education impact e.g. improved ability to study after dark

• Improving gender equality e.g., women not having to spend hours a day collecting firewood

• Better public safety e.g. street lighting and reduced illegal connections

Electrification Funding and Social Impact

• With current DoE funding of ~R1.7bn p.a., universal access will only be achieved in SA in 2033/4 (proclaimed and un-proclaimed), against the original government target of 2014

• Past experience shows that this can be achieved much sooner given the Eskom’s National Electrification programme experience of the 90’s

• Availability of adequate upfront funding is key for facilitation of National Planning and Implementation

In terms of the White Paper on Energy, the responsibility for funding and planning of the Integrated National Electrification Programme is the function of the Dept. of Energy (DoE) with Eskom being the implementing agent in own areas of supply.

Page 15: Eskom’s  Electrification Programme

15

Contents

How could we move forward?

Page 16: Eskom’s  Electrification Programme

Electrification Challenges

Expectations exceed available funds - Current funding levels allow for connections of 150,000 households per annum

Universal Access to electricity by 2014 – funding inadequate

Integrated planning involving all stakeholders (Provincial, DME, Eskom & Municipalities) – delays implementation

Aligned policies to facilitate implementation process not in place(e.g. un-proclaimed, land usages)

Harmonisation of government initiatives e.g. electrification and housing programmes

High costs to electrify deep rural areas due to lack of bulk infrastructure

• There is a need to strengthen old electrification networks because they were configured to accommodate initial ADMD whereas saturation is reached sooner than planned.

Illegal connections in areas not electrified (which are in close proximity to electrified areas) because they have not been prioritised according to municipalities’ IDPs.

• Eradication of the backlog by grid connection will result in an additional 2TWh to the grid, new capacity required

16

Page 17: Eskom’s  Electrification Programme

Electrification Challenges (Cont.)

Electrification plans to be integrated, as far as possible, to optimise costs so that a bigger footprint can be reached

FBE – Free Basic Electricity cannot be extended to un-electrified customers

Some flexibility to be allowed on the plan, i.e. to manage the plan at programme level rather than project level

Creation of bulk infrastructure during the year of implementation gives rise to unnecessary delays – funding for infrastructure should be made available upfront.

17

Page 18: Eskom’s  Electrification Programme

Way Forward

Funding

• The fiscus to make adequate funding available in order to achieve UA• Exploring and partnering with all stakeholders to identify additional

funding for electrification

Integration

• Electrification plans to be integrated, as much as possible, to optimise costs so that a bigger footprint can be reached

• Electrification should form part of housing development in order not to increase backlog

Flexibility

• Allow flexibility iro implementing the plan, i.e. to manage the plan at programme level rather than project level

• Optimal utilisation of existing funding in order to get more connections i.e. allow conversion of schedule 6 and 7 grants as per DoRA

18

Page 19: Eskom’s  Electrification Programme

Siyabonga

19