Eskom Briefing in Majuba Power Station Silo collapse

Embed Size (px)

Citation preview

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    1/25

    Media Briefing

    Damage to Majuba powerstation coal storage silo

    03 November 2014

    Tshediso MatonaChief Executive

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    2/25

    2

    Introduction

    Conclusion

    Majuba power station incident

    The system outlook and plan

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    3/25

    3

    Introduction

    Conclusion

    Majuba power station incident

    The system outlook and plan

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    4/25

    Majuba power stationsituated in the Mpumalanga Province

    4

    Majuba

    It is the youngest

    commercially operatedpower station in the fleet

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    5/25

    Majuba Power Station

    Majuba Power Station, situated in Mpumalanga,has an installed capacity of 4110 MW generated

    The station is 13 years old and became fullyoperational in 2001 when the last of its six units came on line

    Three, 10 000 ton coal storage silos were constructed in 1994

    The latest civil visual inspection was conducted in September 2013 byan external specialist, in line with best practice

    The concrete structure was found to be in good condition.

    Some moderate cases of external physical damage that was reported hassince been repaired

    The risk classification was low

    5

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    6/25

    Sequence of events(1 November 2014)

    1 November 2014

    All Majuba power station

    units were running

    normally, contracted

    loads

    Approximately 12:30

    Operating staff

    reported a visible

    crack on silo 20

    Immediately

    thereafter all

    personnel

    working in the

    area evacuated

    13:12Silo 20

    collapsed

    No injuries

    reported.The area was

    secured and

    protected

    Station output

    immediately reduced

    from3 600 MW to 1800 MW

    and currently running at

    600 MW

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    7/25

    Majuba silo

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    8/25

    Majuba response

    Senior Engineers and

    members of the Executive

    Committee immediately

    joined the Power Station

    manager on-site

    Eskom triggered itsEmergency Command

    Centre. First priority was

    to protect the power grid

    and look at the impact of

    power supply to the

    country

    Arrangements

    were made for

    permits to

    transport mobile

    coal feeders to

    site to enable amanual feed of

    coal to five of the

    six units. This to

    ensure that the

    power station is

    able to operate at

    a minimum of half-load

    The cause and

    cost are yet to

    be determined

    as the incidentis now under

    investigation

    As a result of the early evacuation no injuries were reported

    The situation is

    being constantly

    monitored and

    progress updateson contingency

    plans will be

    communicated

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    9/25

    9

    Introduction

    Conclusion

    Majuba power station incident

    The system outlook and plan

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    10/25

    Majuba

    Main Supply, Coal from Coal Stock Yard,

    (Overland conveyers), 2 250 T/h

    Coal Supply to the Unit, (boiler Incline

    conveyer) 800T/h

    Max burn rate per Unit, 375 T/h. Station burn rate, 54 000 T/day

    Over silo link Conveyers, 1200T/h

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    11/25

    Majuba

    Coal

    stockyard

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    12/25

    Majuba

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    13/25

    Majuba

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    14/25

    14

    Introduction

    Conclusion

    Majuba power station incident

    The system outlook and plan

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    15/25

    15

    Summer profile

    The system remains tight in summer, with different challenges due to the load profile

    Unlike winter, where the demand increases significantly during the evening peak(5pm - 9pm), the demand profile during summer is much flatter with an increased

    demand profile throughout the day

    This is because of a relatively high percentage of almost constant industrial load and the

    impact of air conditioning in the commercial and marginally in the residential sector

    during the day. The significant residential component over evening peak is not as

    evident in summer. If there is a constraint, the system is constrained all day

    Summer is typically maintenance season, but this summer maintenance will increase

    based on the generation strategy as most of the maintenance is fixed and cant be

    deferred.

    The challenge is to ensure that there is sufficient generation capacity throughout the

    day, as we continue with our maintenance plan and focus on reducing unplannedoutages

    The degree of tightness will depend on the performance of the plant and the level of

    unplanned maintenance (UCLF) as well as the available capacity

    Eskom will not compromise its generation plant and will load shed if necessary

    to protect the power system from total collapse

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    16/25

    Summer profile continued

    Summer poses a different challenge as the profile looks flat and our plannedmaintenance (PCLF) increases significantly compared to Winter

    16

    22000

    24000

    26000

    28000

    30000

    32000

    34000

    00:00

    01:00

    02:00

    03:00

    04:00

    05:00

    06:00

    07:00

    08:00

    09:00

    10:00

    11:00

    12:00

    13:00

    14:00

    15:00

    16:00

    17:00

    18:00

    19:00

    20:00

    21:00

    22:00

    23:00

    Summer points to note

    Table Mountain profile

    Constrained all day incl. from 6am - 10pm Air-conditioning, geysers & pool pumps

    primarily impact demand

    Commercial, agricultural & residential customers

    can make the biggest difference

    Constrained all day

    I t f bl ti

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    17/25

    Renewable independent power

    producers peak at over 900 MW

    (about 1 274 MW installed)

    As we move more into a flatter

    profile, the renewables willincreasingly offset some of the

    OCGT usage

    IPPs (wind & solar variability)

    unavailable during evening peak

    when demand is high

    Impact of renewable generationon the system

    17September hourly Solar (PV) and Wind

    Overlap of renewable generation

    and OCGT for one week

    The situation today has been

    exaggerated by the generally cloudy

    conditions across the entire country

    which has reduced the supply from

    solar plants by almost 500 MW

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    18/25

    Sunday: No loss of additional MW andMajuba at 600MW output

    18

    Keeping to scheduled hours at Palmiet and Drakensberg.

    DateTime

    Current Avail Cap (Incl Primary

    Constraints)

    MW Expected to Return/Go

    OffForecast

    Shortfall/Surplus on

    demand

    02/11/2014 00:00 to 01:00 27440 0 22411 5029

    02/11/2014 01:00 to 02:00 27440 0 22021 5419

    02/11/2014 02:00 to 03:00 27440 0 21835 5605

    02/11/2014 03:00 to 04:00 27440 0 21717 5723

    02/11/2014 04:00 to 05:00 27440 0 21894 5546

    02/11/2014 05:00 to 06:00 27440 0 22527 4913

    02/11/2014 06:00 to 07:00 27890 0 23982 3908

    02/11/2014 07:00 to 08:00 28590 0 25945 2645

    02/11/2014 08:00 to 09:00 28590 0 27449 1141

    02/11/2014 09:00 to 10:00 28590 0 27857 733

    02/11/2014 10:00 to 11:00 28590 0 27699 891

    02/11/2014 11:00 to 12:00 28590 0 27606 984

    02/11/2014 12:00 to 13:00 28590 0 27407 1183

    02/11/2014 13:00 to 14:00 28590 0 26817 1773

    02/11/2014 14:00 to 15:00 28590 0 26181 240902/11/2014 15:00 to 16:00 28590 0 26011 2579

    02/11/2014 16:00 to 17:00 28590 0 26155 2435

    02/11/2014 17:00 to 18:00 28590 0 26674 1916

    02/11/2014 18:00 to 19:00 28590 0 27902 688

    02/11/2014 19:00 to 20:00 28790 0 29491 -701

    02/11/2014 20:00 to 21:00 28590 0 28155 435

    02/11/2014 21:00 to 22:00 28590 0 25785 2805

    02/11/2014 22:00 to 23:00 27690 0 24036 365402/11/2014 23:00 to 00:00 27440 0 22690 4750

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    19/25

    Monday: Units return as expected andMajuba at 600 MW output

    19

    Keeping to scheduled hours at Palmiet and Drakensberg.

    DateTime

    Current Avail Cap (Incl Primary

    Constraints)

    MW Expected to Return/Go

    OffForecast

    Shortfall/Surplus on

    demand

    03/11/2014 00:00 to 01:00 27440 679 22217 5902

    03/11/2014 01:00 to 02:00 27440 1358 21921 6802

    03/11/2014 02:00 to 03:00 27440 1358 21856 6867

    03/11/2014 03:00 to 04:00 27440 1358 22265 6458

    03/11/2014 04:00 to 05:00 27440 1451 23591 5132

    03/11/2014 05:00 to 06:00 28590 1543 26898 297503/11/2014 06:00 to 07:00 28590 1543 28346 1527

    03/11/2014 07:00 to 08:00 28590 1543 27931 1942

    03/11/2014 08:00 to 09:00 28590 1543 28676 1197

    03/11/2014 09:00 to 10:00 28590 1543 28835 1038

    03/11/2014 10:00 to 11:00 29040 1543 29146 1177

    03/11/2014 11:00 to 12:00 29040 1543 29057 1266

    03/11/2014 12:00 to 13:00 29040 1543 29019 1304

    03/11/2014 13:00 to 14:00 28840 1543 28820 1303

    03/11/2014 14:00 to 15:00 29090 1543 28882 149103/11/2014 15:00 to 16:00 28590 1543 29382 491

    03/11/2014 16:00 to 17:00 28590 1543 29621 252

    03/11/2014 17:00 to 18:00 29240 1543 29878 905

    03/11/2014 18:00 to 19:00 29990 1543 30868 665

    03/11/2014 19:00 to 20:00 29990 1543 31317 216

    03/11/2014 20:00 to 21:00 29990 1543 30157 1116

    03/11/2014 21:00 to 22:00 28590 1543 27986 1887

    03/11/2014 22:00 to 23:00 28590 1236 25914 3652

    03/11/2014 23:00 to 00:00 27890 928 24569 3989

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    20/25

    Outlook

    1. Sunday

    Sunday shedding at Stage 2 will build up reserves for the week ahead

    The current projection is to keep load shedding Stage 2 to ensure significantrecovery of the Peaking resources to ensure the impact of load shedding is lesssevere during the week

    Solar & wind currently sending out 160 MW and 90 MW respectively. Solar isnormally up to 500 MW (cloudiness affecting it significantly). Majuba currentlysending out about 600 MW (2 machines at half load)

    2. Monday projection

    Generation Capacity at 31 500 MW for the day, provided we do not have anyfurther breakdowns

    Demand forecast for evening peak (31 317 MW highest of the day)

    Risk of load shedding in particular between 18:0020:00

    20

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    21/25

    Outlook continued

    3. The rest of the week If the capacity stays at the same level, we would have similar system

    status. With the extensive usage of the water resources it would meanby Wednesday we start to be constrained with water

    If the capacity is still at the same level we would need to considerStage 1 load shedding possibly on Thursday (whole day) or as earlyas Wednesday evening ( 46 hours)

    21

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    22/25

    How can consumers help?

    Saving electricity reduces pressure on the grid and cuts your electricitybill and SouthAfricas carbon emissions

    The power system remains vulnerable all day up to 10pm

    1. Switch off air-conditioning or use efficiently

    - Set air-conditioning at 23 degrees

    2. Switch off all geysers and pool pumps all day until 10pm

    3. Switch off all non-essential lighting

    4. Respond to the Power Alert messages by switching off allappliances that are not being used

    22

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    23/25

    23

    Introduction

    Conclusion

    Majuba power station incident

    The system outlook and plan

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    24/25

    Conclusion

    While the system is tight, this unplanned incident exacerbatedthe situation and it is very

    likely that load shedding will continue for the week

    An investigation is already underway into the cause of the incident, but it appears that

    this is an isolated incident specific to the coal infrastructure at Majuba.

    Mobile coal feeders are on-site and the team is optimistic that they can maintain half of

    the total from the power station

    The Minister of DPE is being kept abreast of all developments. Eskom has alsoinformed all key stakeholders including the Department of Education and the national

    disaster management centre to minimise the impact for matriculants and all

    communities

    Eskom apologises to all electricity consumers but call on you yet again to switch off

    unnecessary lights, the geyser, pool pump and air-conditioning

    Load shedding schedules are available on Eskom website, and municipal customersshould contact their municipalities for details

    We are painfully aware of the impact of this incident given the electricity supply situation

    in the country

    We will continue to communicate via the media

  • 7/27/2019 Eskom Briefing in Majuba Power Station Silo collapse

    25/25

    Thank you

    25