ERODE DISTRICT Kudimaramath works for the year 2020-21 Sl.No 1 Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross masonry structures in B.P.Agraharam Branch canal from mile 0/0 to 2/0 in Bhavani Distributory under the jurisdiction of the "M-1 Keel Bhavani Murai neer pasana vivasaigal sabai" in Lower Bhavani Irrigation system in Thayirpalayam village in Erode Taluk" Estimate Amount (Rs. In lakhs) 28.00 Date of commencement 20-5-2020 Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs) 25.03 Date of completion (If the work is in progress, mention the probable date of completion) 10.09.2020 Nature of work clearing jungle,desiltinge and sluice cross masonry repair work. Progress of work (% Completed) Work Completed Name of the Farmers Asssociation by which work has been executed M-1 Keel Bhavani Murai neer pasana vivasaigal sabai PHOTOS Before Execution After Execution

ERODE DISTRICT - wrd.tn.gov.in

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ERODE DISTRICT - wrd.tn.gov.in

ERODE DISTRICT

Kudimaramath works for the

year

2020-21

Sl.No 1

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in B.P.Agraharam Branch canal from mile 0/0 to 2/0 in

Bhavani Distributory under the jurisdiction of the "M-1 Keel Bhavani Murai

neer pasana vivasaigal sabai" in Lower Bhavani Irrigation system in

Thayirpalayam village in Erode Taluk"

Estimate Amount (Rs. In

lakhs)

28.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.03 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-1 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 2: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 2

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in Erode Distributory from mile 0/0 to 3/0 and

Distributory from mile 54/0 to mile 55/0 of LBP Main Canal under the

jurisdiction of the "M-4 Keel Bhavani Murai neer pasana vivasaigal sabai"

in Lower Bhavani Irrigation system in Mullampatty and Nasiyanur Village in

Perundurai taluk of Erode District "

Estimate Amount (Rs. In

lakhs)

29.00 Date of

commencement

22-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

26.1 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-4 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 3: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 3

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures of 2-1-60 Branch in Kugalur Distributory of

LBP Main canal under the jurisdiction of "U-5 Keel Bhavani Murai neer

pasana vivasaigal sabai" in Gobichettipalayam Taluk of Erode District."

Estimate Amount (Rs. In

lakhs)

40.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

35.04 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-5 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 4: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 4

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in Mettupalayam Distributory from mile 0/0 to mile 2/0

under the jurisdiction of the "U-10 Keel Bhavani Murai neer pasana

vivasaigal sabai" in Lower Bhavani Irrigation system in Pallapalayam

Village in Perundurai taluk "

Estimate Amount (Rs. In

lakhs)

45.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

40.39 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-10 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 5: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 5

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and

Cross masonry structures in Erode Distributory fro mile 3/0 to 4/0 and

ondikkaranpalayam sub branch canal under the jurisdiction of the "M-5

Keel Bhavani Murai neer pasana vivasaigal sabai" in Lower Bhavani

Irrigation system in Nasiyanur Village in Erode taluk of Erode District"

Estimate Amount (Rs. In

lakhs)

43.00 Date of

commencement

21-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

38.58 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-5 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 6: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 6

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures from mile 7/0 to Tailend of Kugalur distributory

and 6-5-158 Branch, 7-1-400 Rightside parallel channel of Kugalur

Distributory of LBP Main canal under the jurisdiction of U-6 Keel

Bhavani Murai neer pasana vivasaigal sabai" in Gobichettipalayam Taluk

of Erode District. "

Estimate Amount (Rs. In

lakhs)

39.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

34.67 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-6 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 7: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 7

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in Bhavani Distributory from mile 9/3 to tail end,

Vyramangalam branch and Siraimeetanpalayam branch under the

jurisdiction of the "M-3 Keel Bhavani Murai neer pasana vivasaigal sabai"

in Lower Bhavani Irrigation system in Periyapuliyur village in Bhavani

Taluk of Erode District"

Estimate Amount (Rs. In

lakhs)

28.50 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.54

Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-3 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 8: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 8

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures of 34-7-170 Distributory , Sub Branches 0-5-0

and 1-5-215 of 35-7-255 Distributory of LBP Main canal under the

jurisdiction of "U-7 Keel Bhavani Murai neer pasana vivasaigal sabai" in

Lower Bhavani Irrigation system in Gobichettipalayam Taluk of Erode

District.

Estimate Amount (Rs. In

lakhs)

45.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

40.41 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-7 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 9: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 9

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures of 3-2-415 distributory, 3-5-490 direct sluice,

Bommanur and Koonamolai Branches of 6-4-055 Distributory and mile 3/7

to 5/5 of LBP Main canal under the jurisdiction of "U-1 Keel Bhavani Murai

neer pasana vivasaigal sabai" in Sathyamangalam Taluk of Erode District.

"

Estimate Amount (Rs. In

lakhs)

28.75 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.79 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-1 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 10: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 10

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and

Cross masonry structures in Moolakkarai, Vannankattuvalasu,

Nanjanapuram Branch Canal in Thindal Distributory under the jurisdiction

of the "M-6 Keel Bhavani Murai neer pasana vivasaigal sabai" in Lower

Bhavani Irrigation system in Nanjanapuram Village in Erode taluk of Erode

District"

Estimate Amount (Rs. In

lakhs)

29.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

26.08 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-6 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 11: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 11

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in 1-0-349 (R ) branch canal and 0-4-520 (R ) sub

branch of 2-2-70 (L) branch of Unjalur Distributary under the jurisdiction of

the "M-7 Keel Bhavani Murai Neer Pasana Vivasaigal Sabai" in Lower

Bhavani Irrigation System In Perundurai and Modakuruchi of Erode District

Estimate Amount (Rs. In

lakhs)

28.00 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.17 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-7 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 12: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 12

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures from mile 2/2 to Tailend of 30-4-300

Distributory and from mile 29-7-000 to 30-6-000 of LBP Main canal under

the jurisdiction of "U-4 Keel Bhavani Murai neer pasana vivasaigal sabai"

in Lower Bhavani Irrigation system in Gobichettipalayam Taluk of Erode

District.

Estimate Amount (Rs. In

lakhs)

42.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

37.43 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-4 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 13: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 13

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in Mosakkaradu Branch from mile 2/4 to tail end and

pudur sub branch under the jurisdiction of the "M-2B Keel Bhavani Murai

neer pasana vivasaigal sabai" in Lower Bhavani Irrigation system in

Elavamalai village in Erode Taluk"

Estimate Amount (Rs. In

lakhs)

45.60 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

39.78 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-2B Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 14: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 14

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures of pasur branch canal,chinnamapuram sub

branch, uthandipalyam branch canal of kuraganpallam canal and desilting

in kuraganpallam anicut under the jurisdiction of the " M-10A Keel Bhavani

Murai Neer Pasana Vivasaigal Sabai" in Lower Bhavani Irrigation System

In Modakuruchi And Kodumudi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

28.50 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.63 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-10A Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 15: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 15

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures from of mile 48-6-540, 49-1-095 & 50-5-575

Distributories LBP Main canal under the jurisdiction of "U-9 Keel Bhavani

Murai neer pasana vivasaigal sabai" in Perundurai Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

45.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

40.43 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-9 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 16: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 16

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures from mile 0/0 to mile 3/5 and mile 1-5-120

subbranch of 41-2-078 Distributory of LBP Main canal under the

jurisdiction of "U-8A Keel Bhavani Murai neer pasana vivasaigal sabai" in

Bhavani Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

49.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

44.04 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-8A Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 17: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 17

Name of work Clearing the jungles, removal of shoals and repairs to sluices & the cross

masonry structures from mile 23/3 to 24/4 and 25/3 to 26/5 of LBP Main

canal under the jurisdiction of "U-3B Keel Bhavani Murai neer pasana

vivasaigal sabai" in Nambiyur Taluk of Erode District. "

Estimate Amount (Rs. In

lakhs)

39.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

34.78 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-3B Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 18: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 18

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in Kalingarayan channel from mile 12/4 to 19/2 under

the jurisdiction of the "Kalingarayan Madhagu Pasana Vivasaigal Sabai

no.1" in S.S.Agraharam village in Erode Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

24.8 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

21.14 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.1

PHOTOS

Before Execution After Execution

Page 19: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 19

Name of work Clearing the jungles , removal of shoals and repairs to the sluices and

cross masonry structures in 0-3-070 (L) sub branch canal and mile 0/0 to

1-2-160 of 7-0-225 ( R ) branch canal of Chennasamudram Distributory

under the juridication of the "L 5 Keel Bhavani Murai Neer Pasana

Vivasaigal Sabai " in Lower Bhavani Irrigation System in Kodumudi Taluk

of Erode District

Estimate Amount (Rs. In

lakhs)

44.00 Date of

commencement

18.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

38.12 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 5 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 20: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 20

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures of 14-6-100(L) branch canal and drop @ mile 13-6-

360,drop@ mile 15-7-420 of Unjalur Distributary under the jurisdiction of

the "M-11A Keel Bhavani Murai Neer Pasana Vivasaigal Sabai" In Lower

Bhavani Irrigation System in Modakuruchi and Kodumudi Taluks of Erode

District

Estimate Amount (Rs. In

lakhs)

28.00 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.18 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-11A Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 21: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 21

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures in Bhavani Distributory from mile 3/2 to 4/0,

Nadukkalipalayam branch and Semboothamapalayam branch under the

jurisdiction of the "M-2A Keel Bhavani Murai neer pasana vivasaigal sabai"

in Lower Bhavani Irrigation system in Pallapalayam village in Perundurai

Taluk of Erode District"

Estimate Amount (Rs. In

lakhs)

43.00 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

38.61

Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-2A Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 22: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 22

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures of 16-1-203(L) branch canal,18-4-620(L) branch canal

and drop @ mile 16-6-180,drop@ mile 18-6-20 of Unjalur Distributary

under the jurisdiction of the "M-11B Keel Bhavani Murai Neer Pasana

Vivasaigal Sabai" in Lower Bhavani Irrigation System in Kodumudi Taluk

of Erode District

Estimate Amount (Rs. In

lakhs)

27.95 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.12 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-11B Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 23: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 23

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures in 11-4-589(L) branch canal of Unjalur

Distributary under the jurisdiction of the "M-10 Keel Bhavani Murai Neer

Pasana Vivasaigal Sabai" in Lower Bhavani Irrigation System In

Modakuruchi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

29.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

26.09 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-10 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 24: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 24

Name of work Clearing the jungles , removal of shoals and repairs to the sluices and

cross masonry structures in between mile 0/0 to 0-5-550 and 0-5-500 (L)

sub branch canal of 9-7-320 (L) branch canal of Chennasamudram

Distributory under the juridication of the "L 6 Keel Bhavani Murai Neer

Pasana Vivasaigal Sabai " in Lower Bhavani Irrigation System in

Kodumudi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

44.00 Date of

commencement

18.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

38.48 Date of completion (If

the work is in progress,

mention the probable

date of completion)

17.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 6 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 25: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 25

Name of work aring the jungles, removal of shoals and repairs to the sluices and cross

masonry structures in 2-3-290 (L) sub branch, and in between mile 0/0 to

2/0 of 1-4-644 Elumathur branch of Chennasamudram Distributory under

the jurisdiction of the “L2 Keel Bhavani Murai Neer Pasana Vivasaigal

Sabai” in Lower Bhavani Irrigation system in Modakuruchi Taluk of Erode

District

Estimate Amount (Rs. In

lakhs)

29.00 Date of

commencement

22.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

24.82 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 2 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 26: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 26

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures in 9-0-180(L) and 7-1-380 (L) and 0/7 to 1/7 of 6-

2-275(L) branch canal of Unjalur Distributary under the jurisdiction of the

"M-9 Keel Bhavani Murai Neer Pasana Vivasaigal Sabai" in Lower Bhavani

Irrigation System in Modakuruchi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

25.75 Date of

commencement

24-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

23.16 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-9 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 27: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 27

Name of work Clearing the jungles , removal of shoals and repairs to the cross masonry

structures from mile 15/0 to 18/5 of Chennasamudram Distributory under

the juridication of the "L 8 Keel Bhavani Murai Neer Pasana Vivasaigal

Sabai " In Lower Bhavani Irrigation System in Kodumudi Taluk of Erode

District

Estimate Amount (Rs. In

lakhs)

45.00 Date of

commencement

22.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

39.71

Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 8 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 28: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 28

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures of 7-7-420 distributory and from mile 0/0 to 1/5

of 10-0-195 Distributory, 6-5-595 and 10-6-640 direct sluices and mile

12/2 to 13/4 of LBP Main canal under the jurisdiction of "U-2 Keel

Bhavani Murai neer pasana vivasaigal sabai" in Sathyamangalam Taluk of

Erode District. "

Estimate Amount (Rs. In

lakhs)

29.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

26.02 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-2 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 29: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 29

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures from mile 3/5 to tail end of mile 41-2-078

Distributory of LBP Main canal under the jurisdiction of "U-8B Keel Bhavani

Murai neer pasana vivasaigal sabai" in Bhavani Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

28.00 Date of

commencement

20-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.03 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-8B Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 30: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 30

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures of 74/5-060 distributory and 0/0 to 0/2-400 and

0/2 subbranch in 75/3-570 distributory under the jurisdiction of the "L-9

Keel Bhavani Muraineer pasana vivasalgal sabai" in Lower Bhavani

irrigation system in Modakuruchi and Perundurai Taluks of Erode District.

Estimate Amount (Rs. In

lakhs)

21.00 Date of

commencement

18.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

18.8 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 9 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 31: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 31

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures in 2-6-500 (L) sub branch, in between mile 1/0 to

2/5 of 0-5-042 Kongudaiyampalayam branch canal and mile 0-3-156

Distributory of Chennasamudram Distributory under the Jurisdiction of the

"L-1 Keel Bhavani Murai Neer Pasana Vivasigal Sabai" in Lower Bhavani

Irrigation System in Modakuruchi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

16.00 Date of

commencement

8.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

13.58 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 1 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 32: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 32

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures from mile 0-1-140 sub branch and from mile 2-7-400 to

5-0-000 of 5-0-30 (L) branch canal of Unjalur Distributary under the

jurisdiction of the "M-8B Keel Bhavani Murai Neer Pasana Vivasaigal

Sabai" in Lower Bhavani Irrigation System in Modakuruchi Taluk of Erode

District

Estimate Amount (Rs. In

lakhs)

43.50 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

39.14

Date of completion (If

the work is in progress,

mention the probable

date of completion)

17.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-8B Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 33: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 33

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures in mile 0/0 to 0-7-180 of 67-0-290 Poondurai

Distributory under the jurisdiction of the "M-12 Keel Bhavani Murai neer

pasana vivasaigal sabai" in Lower Bhavani Irrigation system in Perundurai

and Modakuruchi taluk of Erode District

Estimate Amount (Rs. In

lakhs)

26.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

22.80 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-12 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 34: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 34

Name of work Reparis to the sluices and cross masonry structures and protection wall

Kalingarayan Channel from mile 32/31/2 to 35/0 and 40/0 to 41/3 and

retaining wall at mile 37/4, 38/3 and Malaiyamapalayam Branch Channel

outlet at 4/1 under the jurisdiction of the ''Kalingarayan Madhagu Pasana

Vivasaigal Sabai No.4" in Kolanalli Village in Kodumudi Taluk of Erode

District.

Estimate Amount (Rs. In

lakhs)

22.50 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

20.04 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.4

PHOTOS

The photos before execution and after execution should be in the same location &

orientation.

Before Execution After Execution

Page 35: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl.No 35

Name of work Rehabilitation of Thadapalli channel flood damaged portion from mile 10/4 to 12/0 including construction of flood protection wall and bund strengthening in Gobi Taluk of Erode district.

Estimate Amount (Rs. In lakhs)

49.00

Date of commencement

24.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

43.90 Date of completion (If the work is in progress, mention the probable date of completion)

06.01.2021

Nature of work

Cleaning jungle and protection wall

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

Thadapalli vaigal pasana sabai T3, Lakkampatti, Gobi.

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 36: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 36

Name of work Clearing the jungles , removal of shoals and repairs to the sluices and

cross masonry structures in 3-3-380 (L) and 5-5-473 (L) sub branch canals

of Chennasamudram Distributory under the juridication of the "L 4 Keel

Bhavani Murai Neer Pasana Vivasaigal Sabai " in Lower Bhavani Irrigation

System in Kodumudi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

43.00 Date of

commencement

18.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

38.14 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 4 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 37: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 38

Name of work Reparis to the sluices and cross masonry structures and protection wall

Kalingarayan Channel from mile 26/0 to 27/6 and 29/2 to 32/31/2 under

the jurisdiction of the ''Kalingarayan Madhagu Pasana Vivasaigal Sabai

No.3" in Kangayampalayam Village in Modakurichi Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

23.00 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

20.48 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.3

PHOTOS

Before Execution After Execution

Page 38: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 39

Name of work Clearing the jungles, removal of shoals and repairs to the cross masonry

structures from mile 19/3 to 20/5 and 21/5 to 22/2 of LBP Main canal

under the jurisdiction of "U-3A Keel Bhavani Murai neer pasana

vivasaigal sabai" in Nambiyur Taluk of Erode District. "

Estimate Amount (Rs. In

lakhs)

40.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

35.73 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

U-3A Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 39: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl.No 40

Name of work Rehabilitation of LMC at L.S. 2.00 km to 3.00 km of PRS dam of left side main canal water users sabai of Kemmanaikanpalayam village in Sathy Taluk of Erode District.

Estimate Amount (Rs. In lakhs)

36.00 Date of commencement

27.05.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

32.27 Date of completion (If the work is in progress, mention the probable date of completion)

04.11.2020

Nature of work RR wall with pointing and plastering

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

Perumpallam anai idadhupura kalvai pasana vivasaigal sangam Reg.No.SRG/ Gobi/58/2020.

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 40: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl.No 41

Name of work Rehabilitation of LMC at LS 3.0 km to 4.0 km of PRS dam of left side main canal water users sabai of Kemmanaikanpalayam village in sathy taluk of Erode district.

Estimate Amount (Rs. In lakhs)

29.50 Date of commencement

27.05.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

26.4 Date of completion (If the work is in progress, mention the probable date of completion)

04.11.2020

Nature of work RR wall with pointing and plastering

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

Perumpallam anai idadhupura kalvai pasana vivasaigal sangam Reg.No.SRG/ Gobi/58/2020.

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 41: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl.No. 42

Name of work Rehabilitation of Thadapalli channel - Kugalur Branch channel flood damaged portion from mile 6/0 to 7/0 and 24/0 to 26/0 of Thadapalli channel including construction of flood protection wall and bund strengthening in Gobi Taluk of Erode district.

Estimate Amount (Rs. In lakhs)

Rs. 55.00 Lakhs Date of commencement

24.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

Rs. 49.37 Lakhs Date of completion (If the work is in progress, mention the probable date of completion)

10.02.2021

Nature of work

1.Sluice Reconstruction 2.Bridge Widening 3.Desilting channels 4.Flood Protection wall

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

Kodiveri Anicut - Thadapalli Vaikkal muraineer Pasana Vivasaigal Sangam T6

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 42: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 43

Name of work Reparis to the sluices and cross masonry structures and protection wall

Kalingarayan Channel from mile 41/3 to 42/0 and 44/0 to 45/0 and 48/2 to

49/1 and retaining wall at mile 42/3 under the jurisdiction of the

''Kalingarayan Madhagu Pasana Vivasaigal Sabai No.5" in

Vadakkupudupalayam Village in Kodumudi Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

22.00 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

19.66 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.5

PHOTOS

Before Execution After Execution

Page 43: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl.No 44

Name of work Rehabilitation of Thadapalli channel flood damaged portion from mile 6/4 to 10/4 including construction of flood protection wall and bund strengthening in Gobi Taluk of Erode district.

Estimate Amount (Rs. In lakhs)

45.00 Date of commencement

24.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

40.45 Date of completion (If the work is in progress, mention the probable date of completion)

30.09.2020

Nature of work Cleaning jungle & protection wall

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

Thadapalli vaigal pasana sabai T2, Solamadeikarai, Gobi.

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 44: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 45

Name of work Reparis to the sluices and cross masonry structures and protection wall

Kalingarayan Channel from mile 53/0 to 53/7 and retaining wall at mile

52/2.5 under the jurisdiction of the ''Kalingarayan Madhagu Pasana

Vivasaigal Sabai No.6" in Kodumudi Village in Kodumudi Taluk of Erode

District.

Estimate Amount (Rs. In

lakhs)

19.00 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

17.04 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.6

PHOTOS

Before Execution After Execution

Page 45: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 46

Name of work Reparis to the sluices and cross masonry structures and protection wall

Kalingarayan Channel from mile 55/0 to 55/3 and Avudairparai Branch

channel and retaining wall at mile 54/6 under the jurisdiction of the

''Kalingarayan Madhagu Pasana Vivasaigal Sabai No.7" in

Chennasamudram Village in Kodumudi Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

21.5 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

18.92 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.7

PHOTOS

Before Execution After Execution

Page 46: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 47

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures in 0-1-300 to tail end of 2-5-40 (L) sub branch

of 3-0-138 kagam branch canal of Chennasamudram Distributory under

the jurisdiction of the “L3 Keel Bhavani Murai Neer Pasana Vivasaigal

Sabai” in Lower Bhavani Irrigation system in Modakuruchi Taluk of Erode

District

Estimate Amount (Rs. In

lakhs)

29.00 Date of

commencement

20.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

25.57 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 3 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 47: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl.No

48

Name of work Rehabilitation of Thadapalli channel flood damaged portion from mile 2/1 to 5/0 including Reconstruction of Bridge at mile 2/2, construction of flood protection wall and bund strengthening in Gobi Taluk of Erode District.

Estimate Amount (Rs. In lakhs)

49.50 Date of commencement

24.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

44.41 Date of completion (If the work is in progress, mention the probable date of completion)

30.09.2020

Nature of work Reconstruction of Bridge

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

Thadapalli vaigal pasana sabai T1, Singripalayam, Gobi.

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 48: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 49

Name of work Clearing the jungles,removal of shoals and repairs to the sluices and cross

masonry structures from mile 0/0 to 1/0 and 1/3 to 1/5 of 1-2-85 (L) sub

branch canal of 5-0-30 (L) branch canal of Unjalur Distributary under the

jurisdiction of the "M-8A Keel Bhavani Murai Neer Pasana Vivasaigal

Sabai" in Lower Bhavani Irrigation System in Modakuruchi Taluk of Erode

District

Estimate Amount (Rs. In

lakhs)

29.50 Date of

commencement

27-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

26.51 Date of completion (If

the work is in progress,

mention the probable

date of completion)

17.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-8A Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 49: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 50

Name of work Reparis to the sluices and cross masonry structures and production wall

Kalingarayan Channel from mile 19/2 1/2 to 22/0 under the jurisdiction of

the ''Kalingarayan Madhagu Pasana Vivasaigal Sabai No.2" in

Thasampudur Village in Modakurich Taluk of Erode District.

Estimate Amount (Rs. In

lakhs)

20.00 Date of

commencement

03.06.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

17.91 Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

Kalingarayan Madhagu Pasana Vivasaigal Sabai no.2

PHOTOS

Before Execution After Execution

Page 50: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 51

Name of work Clearing the jungles, removal of shoals and repairs to the sluices and

cross masonry structures in mile 0-3-347 to 1-5-064 of 70-1-394

Distributory under the jurisdiction of the "M-13 Keel Bhavani Murai neer

pasana vivasaigal sabai" in Lower Bhavani Irrigation system in Perundurai

and Modakuruchi taluk of Erode District

Estimate Amount (Rs. In

lakhs)

26.00 Date of

commencement

18-5-2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

22.93

Date of completion (If

the work is in progress,

mention the probable

date of completion)

10.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

M-13 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 51: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the

year

2020-21

Sl.No 52

Name of work Clearing the jungles , removal of shoals and repairs to the sluices and

cross masonry structures in 12-5-504 (L) branch canal of

Chennasamudram Distributory under the juridication of the "L 7 Keel

Bhavani Murai Neer Pasana Vivasaigal Sabai " In Lower Bhavani Irrigation

System in Kodumudi Taluk of Erode District

Estimate Amount (Rs. In

lakhs)

43.00 Date of

commencement

18.05.2020

Expenditure w.r.t 90% of

Estimate Amount (Rs. In

lakhs)

38.32 Date of completion (If

the work is in progress,

mention the probable

date of completion)

17.09.2020

Nature of work

clearing

jungle,desiltinge and

sluice cross masonry

repair work.

Progress of work (%

Completed)

Work Completed

Name of the Farmers

Asssociation by which work

has been executed

L- 7 Keel Bhavani Murai neer pasana vivasaigal sabai

PHOTOS

Before Execution After Execution

Page 52: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020 -21

Sl.No

53

Name of work Rehabilitation of Arakkankottai Channel from mile 14/0 to 16/0 and repair to outlet at mile 14/5 , 15/7 in Gobi Taluk of Erode District.

Estimate Amount (Rs. In lakhs)

49.00 Lakhs Date of commencement 12.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

44.10 Lakhs / 43.97

Date of completion (If the work is in progress, mention the probable date of completion)

09.09.2020

Nature of work

Jungle Clearance , Special Repairs to Sluice, Bund Strengthening and Protection wall construction.

Progress of work (% Completed)

100% Completed

Name of the Farmers Asssociation by which work has been executed

President, KodiveriAnicutThittamArakkankottaiVaikkalMuraiNeerPasanaVivasaigalSangam, PasanaKottam No.4

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 53: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020 -21

Sl.No

54

Name of work Rehabilitation of Arakkankottai Channel from mile 19/0 to 20/1 in Gobi Taluk of Erode District.

Estimate Amount (Rs. In lakhs)

42.00 Lakhs Date of commencement 12.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

37.67 Lakhs Date of completion (If the work is in progress, mention the probable date of completion)

09.09.2020

Nature of work

Jungle Clearance, Special Repairs to Sluice, Bund Strengthening and Protection wall construction.

Progress of work (% Completed) 100% Completed

Name of the Farmers Asssociation by which work has been executed

President, KodiveriAnicutThittamArakkankottaiVaikkalMuraiNeerPasanaVivasaigalSangam, PasanaKottam No.4

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 54: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020 -21

Sl.No 55

Name of work Rehabilitation of Arakkankottai Channel from mile 8/0 to 10/0 and extension of Bridge at mile 8/4 in Gobi Taluk of Erode District.

Estimate Amount (Rs. In lakhs)

47.00 Lakhs Date of commencement 12.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

42.17 Lakhs Date of completion (If the work is in progress, mention the probable date of completion)

09.09.2020

Nature of work

Jungle Clearance, Special Repairs to Sluice, Bund Strengthening and Protection wall construction.

Progress of work (% Completed) 100% Completed

Name of the Farmers Asssociation by which work has been executed

President, KodiveriAnicutThittamArakkankottaiVaikkalMuraiNeerPasanaVivasaigalSangam, PasanaKottam No.2

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 55: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020 -21

Sl.No

56

Name of work Rehabilitation of Arakkankottai Channel from mile 10/0 to 12/0 and repair to outlet at mile 11/2 in Gobi Taluk of Erode District.

Estimate Amount (Rs. In lakhs)

47.00 Lakhs Date of commencement 12.06.2020

Expenditure w.r.t 90% of Estimate Amount (Rs. In lakhs)

42.17 Lakhs Date of completion (If the work is in progress, mention the probable date of completion)

09.09.2020

Nature of work

Jungle Clearance, Special Repairs to Sluice, Bund Strengthening and Protection wall construction.

Progress of work (% Completed) 100% Completed

Name of the Farmers Asssociation by which work has been executed

President, KodiveriAnicutThittamArakkankottaiVaikkalMuraiNeerPasanaVivasaigalSangam, PasanaKottam No.2

PHOTOS

The photos before execution and after execution should be in the same location & orientation.

Before Execution After Execution

Page 56: ERODE DISTRICT - wrd.tn.gov.in

Kudimaramath works for the year

2020-21

Sl. No. 57

Name of Work Rehabilitation of Field Channel below Sluices of Odathurai Tank in Odathurai Village in Bhavani Taluk of Erode District.

Estimate Amount (Rs. in Lakhs)

Rs.45.00 Lakhs Date of commencement

24.05.2020

Expenditure w.r.t. 90% of Estimate Amount (Rs. in Lakhs)

Rs. 40.47 Lakhs

Date of completion (if the work is in progress, mention the probable date of completion)

12.09.2020

Nature of work Field Channel Lining

Progress of work (% Completed)

100% work Completed

Name of the Farmers Association by which work has been executed.

Odathurai Yeri Neer Pasana Vivasayeegal Sangam

Before Execution After Execution